AG GAS PLANT, 50mmscf & Date Revision Checked Approved

15-Dec-2... REV 1 Mr. Segun O. & Mr. Fe... Mr. Rotimi A.


16", 25.5 KM EXPORT PIPELINE
Activity ID Activity Name Original Planned Start Planned Finish 2022 2023 2024
Duration D J F M A M J J A S O N D J F M A M J J A S O N D J F

AG Gas Plant, 50mmscfd & 16" Export line to Amenam-Kpono Projects-L1 20m 31-Jan-22 0 12-Sep-23 13 12-Sep-23 ...

MAJOR MILESTONES 20m 31-Jan-22 0 12-Sep-23 1 12-Sep-23 ...

MILS 1 Signing Letter of Intent (LOI) 0m 31-Jan-22 0

MILS 2 Complete Engineering 0m 30-Jul-22 0 30-Jul-22 ...


MILS 3 Complete Procurement 0m 24-Dec-22 7 24-Dec-22 ...
MILS 4 Complete Fabrication 0m 26-Jan-23 0 26-Jan-23 ...
MILS 5 Complete Installation & Hook-up 0m 14-Jul-23 1 14-Jul-23 ...

MILS 6 Commissioning & Start-up 0m 12-Sep-23 1 12-Sep-23 ...


CONTRACT AWARD 0m 31-Jan-22 0 31-Jan-22 0 31-Jan-22 ...

CON1000 Contract award / Signing Letter of Intent (LOI) 0m 31-Jan-22 0

ENGINEERING 6m 31-Jan-22 0 30-Jul-22 0 30-Jul-22 ...

ENG1000 16" Gas Pipline from AG Plant to Amenam-Kpono 6m 31-Jan-22 0 30-Jul-22 0 6m 30-Jul-22 ...

ENG1010 Jack-Up Barge, AG Plant & Compression facilities 6m 31-Jan-22 0 30-Jul-22 0 6m 30-Jul-22 ...

PROCUREMENT 9m 27-Mar-22 8 24-Dec-22 7 24-Dec-22 ...

PRO1000 Procure LLI and bulk materials for 16" 25.5km Export Gas Pipline 9m 27-Mar-22 8 22-Dec-22 8 9m 22-Dec-22 ...
PRO1010 Procure LLI & bulk materials for Jack-Up Barge, AG Plant & 9m 29-Mar-22 7 24-Dec-22 7 9m 24-Dec-22 ...
Compression facilities
FABRICATION 6m 30-Jul-22 0 26-Jan-23 0 26-Jan-23 ...

FAB1000 Fabrication for 16" Gas Pipline from AG Plant to Amenam-Kpono 4m 9-Sep-22 4 7-Jan-23 4 4m 7-Jan-23 4...

FAB1010 Fabrication & assembly for AG Plant & Compression facilities 6m 30-Jul-22 0 26-Jan-23 0 6m 26-Jan-23 ...
INSTALLATION / HOOK-UP 6m 26-Jan-23 0 14-Jul-23 1 14-Jul-23 ...

INST1010 Install & hook-up 16" Gas Pipline from AG Plant to Amenam-Kpono 3m 15-Apr-23 1 14-Jul-23 1 3m 14-Jul-23 ...

INST1020 Install & hook-up AG Plant & Compression facilities 4m 26-Jan-23 0 26-May-23 0 4m 26-May-23 ...
PRE-COMMISSIONING 3m 26-May-23 0 13-Aug-23 1 13-Aug-23 ...

PRECOM1020 Precom Gas Export Pipeline from AG Plant to Amenam-Kpono 1m 14-Jul-23 1 13-Aug-23 1 1m 13-Aug-23 ...

PRECOM1030 Precom AG Plant & Compression facilities 2m 26-May-23 0 25-Jul-23 0 2m 25-Jul-23 ...

Critical remaining Remaining Work Summary Page 1 of 2 TASK filter: All Activities

Actual Work Milestone © Oracle Corporation


AG GAS PLANT, 50mmscf & Date Revision Checked Approved
15-Dec-2... REV 1 Mr. Segun O. & Mr. Fe... Mr. Rotimi A.
16", 25.5 KM EXPORT PIPELINE
Activity ID Activity Name Original Planned Start Planned Finish 2022 2023 2024
Duration D J F M A M J J A S O N D J F M A M J J A S O N D J F
COMMISSIONING & START-UP 1m 13-Aug-23 1 12-Sep-23 1 12-Sep-23 ...

CSP1000 Commissioning & Start-Up 1m 13-Aug-23 1 12-Sep-23 1 1m 12-Sep-23 ...

PROJECT MANAGEMENT 20m 31-Jan-22 13 12-Sep-23 13 12-Sep-23 ...

PMT1000 Project management 20m 31-Jan-22 13 12-Sep-23 13 Project ma...

Critical remaining Remaining Work Summary Page 2 of 2 TASK filter: All Activities