W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
W-02A 1341 21-May-22 A 20-Oct-26 20-Oct-26, W-02A

MILESTONES 1341 30-May-22 A 20-Oct-26 20-Oct-26, MILESTONES


LEAD EVENTS 140 30-May-22 A 13-Nov-22 13-Nov-22, LEAD EVENTS
RAM-MLS-LE.101 Notice to Proceed (Commencement Date) 1 30-May-22 A 30-May-22 A Notice to Proceed (Commencement Date)

RAM-MLS-LE.111 Kickoff Meeting 1 31-May-22 A 31-May-22 A Kickoff Meeting

RAM-MLS-LE.121 Complete Mobilization 0 13-Nov-22* Complete Mobilization

RAM-MLS-LE.126 Complete Facilties 0 13-Nov-22 Complete Facilties

IFC DRAWINGS 2 15-Jun-22 A 19-Oct-22 A 19-Oct-22 A, IFC DRAWINGS


RAM-MLS-LE.116 Civil / Tunnel Structural 1 15-Jun-22 A 30-Aug-22 A Civil / Tunnel Structural

RAM-MLS-LE.131 Pedestrian Bridges 1 15-Jun-22 A 15-Jun-22 A Pedestrian Bridges

RAM-MLS-LE.132 Tunnel Architectural 1 26-Jun-22 A 19-Oct-22 A Tunnel Architectural

RAM-MLS-LE.133 Dry & Wet Culverts 1 15-Jun-22 A 15-Jun-22 A Dry & Wet Culverts

RAM-MLS-LE.134 Wet Utilities 1 18-Jun-22 A 18-Jun-22 A Wet Utilities

RAM-MLS-LE.136 Dry Utilities 1 15-Jun-22 A 15-Jun-22 A Dry Utilities

RAM-MLS-LE.141 MEP Rooms 1 27-Jun-22 A 01-Sep-22 A MEP Rooms

RAM-MLS-LE.146 Mechanical 1 27-Jun-22 A 05-Oct-22 A Mechanical

RAM-MLS-LE.151 Electrical 1 27-Jun-22 A 05-Oct-22 A Electrical

RAM-MLS-LE.156 Plumbing 1 27-Jun-22 A 05-Oct-22 A Plumbing

CONTRACTUAL KEY MILESTONES 602 28-Oct-24 20-Oct-26 20-Oct-26, CONTRACTUAL KEY MI


RAM-MLS-CKM.100 Section 1 - Tunnel 2 + Part of JAH Tunnel Structural Works untill Backfilling 0 02-Feb-25* Section 1 - Tunnel 2 + Part of JAH Tunnel Structural Works untill Backfilling

RAM-MLS-CKM.105 Section 2 - West of Airport Road (Tunnel & Utility Culvert Structural works and Surrounding Infrastructure Works 0 28-Oct-24* Section 2 - West of Airport Road (Tunnel & Utility Culvert Structural works and Surrounding Infrastructure Works

RAM-MLS-CKM.110 Section 3 - King Abdulaziz Road Tunnel 1 Structural Works Untill Backfilling 0 13-May-25* Section 3 - King Abdulaziz Road Tunnel 1 Structural Works Untill Backfilling

RAM-MLS-PM.155 Overall Project Completion 0 20-Oct-26* Overall Project Completion

PERFORMANCE MILESTONE 331 17-Jun-25 18-Jul-26 18-Jul-26, PERFORMANCE MILESTONE


RAM-MLS-PM.100 Overall Completion of Zone 04 0 25-Jun-25* Overall Completion of Zone 04

RAM-MLS-PM.105 Overall Completion of Zone 08 0 18-Jul-26* Overall Completion of Zone 08

RAM-MLS-PM.110 Overall Completion of Zone 02 0 17-Jun-25* Overall Completion of Zone 02

RAM-MLS-PM.115 Overall Completion of Zone 11 0 03-Jul-25* Overall Completion of Zone 11

RAM-MLS-PM.120 Overall Completion of Zone 10 0 30-Oct-25* Overall Completion of Zone 10

RAM-MLS-PM.125 Overall Completion of Zone 09 0 14-Apr-26* Overall Completion of Zone 09

RAM-MLS-PM.130 Overall Completion of Zone 07 0 15-Feb-26* Overall Completion of Zone 07

RAM-MLS-PM.135 Overall Completion of Zone 06 0 24-Aug-25* Overall Completion of Zone 06

RAM-MLS-PM.140 Overall Completion of Zone 03 0 23-Feb-26* Overall Completion of Zone 03

RAM-MLS-PM.145 Overall Completion of Zone 01 0 24-Dec-25* Overall Completion of Zone 01

RAM-MLS-PM.150 Overall Completion of Zone 05 0 27-Dec-25* Overall Completion of Zone 05

INTERMEDIATE MILESTONE 1197 16-Nov-22 20-Oct-26 20-Oct-26, INTERMEDIATE MILESTO


RAM-MLS-INS.100 Complete Approved Subcontractor and Vendor (Civil) 0 16-Nov-22* Complete Approved Subcontractor and Vendor (Civil)

RAM-MLS-INS.105 Complete Approved Subcontractor and Vendor (Mechanical) 0 01-Dec-22* Complete Approved Subcontractor and Vendor (Mechanical)

RAM-MLS-INS.110 Complete Approved Subcontractor and Vendor (Electrical) 0 11-Jan-23* Complete Approved Subcontractor and Vendor (Electrical)

RAM-MLS-INS.120 Completion of Infrastructure Utilities at Superblock 2 0 04-Jun-25* Completion of Infrastructure Utilities at Superblock 2

RAM-MLS-INS.125 Completion of Infrastructure Utilities at Superblock 1 0 13-Mar-25* Completion of Infrastructure Utilities at Superblock 1

RAM-MLS-INS.135 Completion of Infrastructure Utilities at District 9 0 11-Nov-24* Completion of Infrastructure Utilities at District 9

RAM-MLS-INS.140 Completion of Infrastructure Utilities at Superblock 3 0 17-Apr-25* Completion of Infrastructure Utilities at Superblock 3

RAM-MLS-INS.150 Completion of Infrastructure Utilities at Superblock 8 0 21-Mar-24* Completion of Infrastructure Utilities at Superblock 8

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
1 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM-MLS-INS.155 Completion of Infrastructure Utilities at District 10 0 10-Mar-25* Completion of Infrastructure Utilities at District 10

RAM-MLS-INS.165 Completion of Pedestrian Bridge No. 01 0 01-Apr-26* Completion of Pedestrian Bridge No. 01

RAM-MLS-INS.170 Completion of MEP Rooms in Zone 1 0 11-Jan-26* Completion of MEP Rooms in Zone 1

RAM-MLS-INS.175 Complete External Roads 0 04-Feb-26* Complete External Roads

RAM-MLS-INS.180 Completion of Pedestrian Bridge No. 04 0 27-Jan-26* Completion of Pedestrian Bridge No. 04

RAM-MLS-INS.185 Completion of Pedestrian Bridge No. 02 0 12-Jan-26* Completion of Pedestrian Bridge No. 02

RAM-MLS-INS.190 Complete Local Roads 0 09-Feb-26* Complete Local Roads

RAM-MLS-INS.195 Completion of Pedestrian Bridge No. 03 0 20-Oct-26* Completion of Pedestrian Bridge No. 03

RAM-MLS-INS.200 Completion of MEP Rooms in Zone 2 0 13-Aug-25* Completion of MEP Rooms in Zone 2

RAM-MLS-INS.205 Completion of MEP Rooms in Zone 3 0 27-Sep-25* Completion of MEP Rooms in Zone 3

RAM-MLS-INS.210 Completion of MEP Rooms in Zone 4 0 24-Sep-25* Completion of MEP Rooms in Zone 4

RAM-MLS-INS.215 Completion of MEP Rooms in Zone 5 0 20-May-25* Completion of MEP Rooms in Zone 5

RAM-MLS-INS.220 Completion of MEP Rooms in Zone 6 0 17-Aug-25* Completion of MEP Rooms in Zone 6

RAM-MLS-INS.225 Completion of MEP Rooms in Zone 9 0 11-Jun-25* Completion of MEP Rooms in Zone 9

RAM-MLS-INS.230 Completion of MEP Rooms in Zone 10 0 18-Feb-25* Completion of MEP Rooms in Zone 10

RAM-MLS-INS.235 Completion of MEP Rooms in Zone 11 0 21-Jul-25* Completion of MEP Rooms in Zone 11

DELAY EVENTS 1138 31-May-22 A 16-Feb-26 16-Feb-26, DELAY EVENTS


DELAY EVENT-1 374 31-May-22 A 20-May-23 20-May-23, DELAY EVENT-1
DELAY EVENT-1-A 101 31-May-22 A 28-Sep-22 A 28-Sep-22 A, DELAY EVENT-1-A
DE-001A Site Handing Over and Possession of Site (MIP-PAR-JVC-PMC-TRF-00022) Z6 101 31-May-22 A 28-Sep-22 A Site Handing Over and Possession of Site (MIP-PAR-JVC-PMC-TRF-00022) Z6

DELAY EVENT-1-B 204 31-May-22 A 26-Jan-23 A 26-Jan-23 A, DELAY EVENT-1-B


DE-001B Site Handing Over and Possession of Site (MIP-PAR-JVC--PMC-TRF-00065) Z5 204 31-May-22 A 26-Jan-23 A Site Handing Over and Possession of Site (MIP-PAR-JVC--PMC-TRF-00065) Z5

DELAY EVENT-1-C 301 31-May-22 A 19-Feb-23 19-Feb-23, DELAY EVENT-1-C


DE-001C Site Handing Over and Possession of Site (MIP-PAR-JVC--PMC-TRF-00106) Z10+Z9 301 31-May-22 A 19-Feb-23 Site Handing Over and Possession of Site (MIP-PAR-JVC--PMC-TRF-00106) Z10+Z9

DELAY EVENT-1-D 369 31-May-22 A 14-May-23 14-May-23, DELAY EVENT-1-D


RAM1135 Site Handing Over and Possession of Site (PAR-JVC--PMC-LTR-000556) Z1 369 31-May-22 A 14-May-23 Site Handing Over and Possession of Site (PAR-JVC--PMC-LTR-000556) Z1

DELAY EVENT-1-E 374 31-May-22 A 20-May-23 20-May-23, DELAY EVENT-1-E


RAM1140 Site Handing Over and Possession of Site (JVC-PAR-CON-LTR-000369-00) Z8+Z9 374 31-May-22 A 20-May-23 Site Handing Over and Possession of Site (JVC-PAR-CON-LTR-000369-00) Z8+Z9

DELAY EVENT-2 142 31-May-22 A 15-Nov-22 A 15-Nov-22 A, DELAY EVENT-2


DE-002 Delay in Verification of Survey Monuments/Bench Marks/Traverse/Control Points 142 31-May-22 A 15-Nov-22 A Delay in Verification of Survey Monuments/Bench Marks/Traverse/Control Points

DELAY EVENT-3 198 31-May-22 A 05-Jan-23 05-Jan-23, DELAY EVENT-3


DE-003-A Delay in Release of IFC Drawings issued for Construction 186 31-May-22 A 05-Jan-23 A Delay in Release of IFC Drawings issued for Construction

DE-003-B X-Section of earth work preparation and submission 12 07-Jan-23 A 06-Nov-22


DE-003-C X-Section of earth work review and approval 12 07-Nov-22 20-Nov-22 X-Section of earth work review and approval

DELAY EVENT-4 190 31-May-22 A 10-Jan-23 A 10-Jan-23 A, DELAY EVENT-4


DELAY EVENT-4-A 109 31-May-22 A 08-Oct-22 A 08-Oct-22 A, DELAY EVENT-4-A
RAM1145 Delays due to AIP Stockpiles part of Zone 10 109 31-May-22 A 08-Oct-22 A Delays due to AIP Stockpiles part of Zone 10

DELAY EVENT-4-B 124 31-May-22 A 24-Oct-22 A 24-Oct-22 A, DELAY EVENT-4-B


RAM1150 Delays due to AIP Stockpiles part of Zone 3&4 124 31-May-22 A 24-Oct-22 A Delays due to AIP Stockpiles part of Zone 3&4

DELAY EVENT-4-C 124 31-May-22 A 24-Oct-22 A 24-Oct-22 A, DELAY EVENT-4-C


RAM1155 Delays due to AIP Stockpiles part of Zone 8 124 31-May-22 A 24-Oct-22 A Delays due to AIP Stockpiles part of Zone 8

DELAY EVENT-4-D 124 31-May-22 A 24-Oct-22 A 24-Oct-22 A, DELAY EVENT-4-D


RAM1165 Delays due to AIP Stockpiles part of Zone 4,10&11 124 31-May-22 A 24-Oct-22 A Delays due to AIP Stockpiles part of Zone 4,10&11

DELAY EVENT-4-E 168 31-May-22 A 15-Dec-22 A 15-Dec-22 A, DELAY EVENT-4-E


RAM1170 Delays due to AIP Stockpiles Zone 2 & part of zone 8 168 31-May-22 A 15-Dec-22 A Delays due to AIP Stockpiles Zone 2 & part of zone 8

DELAY EVENT-4-F 171 31-May-22 A 19-Dec-22 A 19-Dec-22 A, DELAY EVENT-4-F

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
2 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM1175 Delays due to AIP Stockpiles Zone 1 171 31-May-22 A 19-Dec-22 A Delays due to AIP Stockpiles Zone 1

DELAY EVENT-4-G 171 31-May-22 A 19-Dec-22 A 19-Dec-22 A, DELAY EVENT-4-G


RAM1180 Delays due to AIP Stockpiles part of Zone 5 171 31-May-22 A 19-Dec-22 A Delays due to AIP Stockpiles part of Zone 5

DELAY EVENT-4-H 190 31-May-22 A 10-Jan-23 A 10-Jan-23 A, DELAY EVENT-4-H


RAM1160 Delays due to AIP Stockpiles part of Zone 4 190 31-May-22 A 10-Jan-23 A Delays due to AIP Stockpiles part of Zone 4

DELAY EVENT-5 615 31-May-22 A 01-Jun-24 01-Jun-24, DELAY EVENT-5


RAM1195 Delays to Changes in Scope of Works under Variation Instructions – viz. Soil Improvement 151 31-May-22 A 26-Nov-22 A Delays to Changes in Scope of Works under Variation Instructions – viz. Soil Improvement

ZONE 1 180 15-Aug-23 12-Mar-24 12-Mar-24, ZONE 1


RAM1190 Soil Improvement @Sta. 0+293~ 0+393 70 30-Oct-23 18-Jan-24 Soil Improvement @Sta. 0+293~ 0+393

RAM1200 Soil Improvement @Sta. 0+393~ 0+510 46 20-Jan-24 12-Mar-24 Soil Improvement @Sta. 0+393~ 0+510

RAM1205 Soil Improvement investigation @Sta. 0+173~ 0+293 14 15-Aug-23 30-Aug-23 Soil Improvement investigation @Sta. 0+173~ 0+293

ZONE 2 297 29-Apr-23 16-Apr-24 16-Apr-24, ZONE 2


RAM1210 Soil Improvement @Sta. 0+510~ 0+610 61 29-Apr-23 11-Jul-23 Soil Improvement @Sta. 0+510~ 0+610

RAM1215 Soil Improvement @Sta. 0+610~ 0+710 61 12-Jul-23 20-Sep-23 Soil Improvement @Sta. 0+610~ 0+710

RAM1220 Soil Improvement @Sta. 0+710~ 0+810 61 21-Sep-23 02-Dec-23 Soil Improvement @Sta. 0+710~ 0+810

RAM1225 Soil Improvement @Sta. 0+810~ 0+910 61 03-Dec-23 11-Feb-24 Soil Improvement @Sta. 0+810~ 0+910

RAM1230 Soil Improvement @Sta. 0+910~ 0+993 53 12-Feb-24 16-Apr-24 Soil Improvement @Sta. 0+910~ 0+993

ZONE 3 143 01-Mar-23 21-Aug-23 21-Aug-23, ZONE 3


RAM1235 Soil Improvement @Sta. 0+1173~ 0+1273 50 01-Mar-23 01-May-23 Soil Improvement @Sta. 0+1173~ 0+1273

RAM1240 Soil Improvement @Sta. 0+1073~ 0+1173 50 02-May-23 02-Jul-23 Soil Improvement @Sta. 0+1073~ 0+1173

RAM1245 Soil Improvement @Sta. 0+993~ 0+1073 43 03-Jul-23 21-Aug-23 Soil Improvement @Sta. 0+993~ 0+1073

ZONE 4 273 30-May-23 20-Apr-24 20-Apr-24, ZONE 4


RAM1250 Soil Improvement @Sta. 0+1273~ 0+1373 56 30-May-23 06-Aug-23 Soil Improvement @Sta. 0+1273~ 0+1373

RAM1255 Soil Improvement @Sta. 0+1373~ 0+1473 56 07-Aug-23 11-Oct-23 Soil Improvement @Sta. 0+1373~ 0+1473

RAM1260 Soil Improvement @Sta. 0+1473~ 0+1573 56 12-Oct-23 16-Dec-23 Soil Improvement @Sta. 0+1473~ 0+1573

RAM1265 Soil Improvement @Sta. 0+1573~ 0+1673 56 17-Dec-23 19-Feb-24 Soil Improvement @Sta. 0+1573~ 0+1673

RAM1270 Soil Improvement @Sta. 0+1673~ 0+1753 49 20-Feb-24 20-Apr-24 Soil Improvement @Sta. 0+1673~ 0+1753

ZONE 5 240 22-Aug-23 01-Jun-24 01-Jun-24, ZONE 5


RAM1275 Soil Improvement @Sta. 0+1753~ 0+1853 60 22-Aug-23 31-Oct-23 Soil Improvement @Sta. 0+1753~ 0+1853

RAM1280 Soil Improvement @Sta. 0+1853~ 0+1953 60 01-Nov-23 09-Jan-24 Soil Improvement @Sta. 0+1853~ 0+1953

RAM1285 Soil Improvement @Sta. 0+1953~ 0+2052 59 10-Jan-24 18-Mar-24 Soil Improvement @Sta. 0+1953~ 0+2052

RAM1290 Soil Improvement @Sta. 0+2052~ 0+2157 61 19-Mar-24 01-Jun-24 Soil Improvement @Sta. 0+2052~ 0+2157

ZONE 6 153 20-Dec-22 19-Jun-23 19-Jun-23, ZONE 6


MAIN TUNNEL 34 26-Dec-22 02-Feb-23 02-Feb-23, MAIN TUNNEL
RAM1295 Soil Improvement @Sta. 2+157~ 2+198 34 26-Dec-22 02-Feb-23 Soil Improvement @Sta. 2+157~ 2+198

RAM1300 Soil Improvement investigation @Sta. 2+198~ 2+518 14 29-Dec-22 14-Jan-23 Soil Improvement investigation @Sta. 2+198~ 2+518

WET CULVERT 153 20-Dec-22 19-Jun-23 19-Jun-23, WET CULVERT


RAM1390 Soil Improvement @Sta. 2+203~ 2+318 22 01-Jan-23 25-Jan-23 Soil Improvement @Sta. 2+203~ 2+318

RAM1395 Soil Improvement investigation @Sta. 2+318~ 2+460 14 20-Dec-22 04-Jan-23 Soil Improvement investigation @Sta. 2+318~ 2+460

RAM1400 Soil Improvement @Sta. 2+460~ 2+499 22 15-Jan-23 08-Feb-23 Soil Improvement @Sta. 2+460~ 2+499

RAM1405 Soil Improvement @Sta. 2+499~ 2+699 43 09-Feb-23 30-Mar-23 Soil Improvement @Sta. 2+499~ 2+699

RAM1410 Soil Improvement @Sta. 2+699~ 2+899 43 01-Apr-23 23-May-23 Soil Improvement @Sta. 2+699~ 2+899

RAM1415 Soil Improvement @Sta. 2+899~ 2+943 23 24-May-23 19-Jun-23 Soil Improvement @Sta. 2+899~ 2+943

DRY CULVERT 116 20-Dec-22 07-May-23 07-May-23, DRY CULVERT


RAM1420 Soil Improvement @Sta. 1+978~ 2+025 25 26-Dec-22 23-Jan-23 Soil Improvement @Sta. 1+978~ 2+025

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
3 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM1425 Soil Improvement investigation @Sta. 2+025~ 2+260 14 20-Dec-22 04-Jan-23 Soil Improvement investigation @Sta. 2+025~ 2+260

RAM1430 Soil Improvement @Sta. 2+260~ 2+465 44 15-Jan-23 06-Mar-23 Soil Improvement @Sta. 2+260~ 2+465

RAM1435 Soil Improvement @Sta. 2+465~ 2+725 50 07-Mar-23 07-May-23 Soil Improvement @Sta. 2+465~ 2+725

ZONE 7 111 20-Dec-23 30-Apr-24 30-Apr-24, ZONE 7


RAM1440 Soil Improvement @Sta. 0+040~ 0+140 55 20-Dec-23 21-Feb-24 Soil Improvement @Sta. 0+040~ 0+140

RAM1445 Soil Improvement investigation @Sta. 0+140~ 0+360 14 15-Apr-24 30-Apr-24 Soil Improvement investigation @Sta. 0+140~ 0+360

ZONE 8 170 26-Aug-23 11-Mar-24 11-Mar-24, ZONE 8


RAM1310 Soil Improvement investigation @Sta. 0+040~ 0+380 14 15-Oct-23 30-Oct-23 Soil Improvement investigation @Sta. 0+040~ 0+380

RAM1315 Soil Improvement @Sta. 0+380~ 0+453 63 30-Dec-23 11-Mar-24 Soil Improvement @Sta. 0+380~ 0+453

RAM1320 Soil Improvement @Sta. 0+453~ 0+552 70 26-Aug-23 15-Nov-23 Soil Improvement @Sta. 0+453~ 0+552

ZONE 9 142 16-Jul-23 28-Dec-23 28-Dec-23, ZONE 9


RAM1325 Soil Improvement @Sta. 0+041~ 0+121 45 16-Jul-23 05-Sep-23 Soil Improvement @Sta. 0+041~ 0+121

RAM1330 Soil Improvement @Sta. 0+121~ 0+201 45 06-Sep-23 29-Oct-23 Soil Improvement @Sta. 0+121~ 0+201

RAM1335 Soil Improvement @Sta. 0+201~ 0+301 52 30-Oct-23 28-Dec-23 Soil Improvement @Sta. 0+201~ 0+301

ZONE 10 170 11-Dec-22 03-Jul-23 03-Jul-23, ZONE 10


RAM1340 Soil Improvement investigation @Sta. 0+014~ 0+100 14 11-Dec-22 26-Dec-22 Soil Improvement investigation @Sta. 0+014~ 0+100

RAM1350 Soil Improvement @Sta. 0+100~ 0+203 44 26-Jan-23 18-Mar-23 Soil Improvement @Sta. 0+100~ 0+203

RAM1355 Soil Improvement @Sta. 0+203~ 0+308 44 19-Mar-23 11-May-23 Soil Improvement @Sta. 0+203~ 0+308

RAM1360 Soil Improvement @Sta. 0+308~ 0+402 42 13-May-23 03-Jul-23 Soil Improvement @Sta. 0+308~ 0+402

ZONE 11 181 18-May-23 19-Dec-23 19-Dec-23, ZONE 11


RAM1365 Soil Improvement investigation @Sta. 0+040~ 0+065 14 18-May-23 03-Jun-23 Soil Improvement investigation @Sta. 0+040~ 0+065

RAM1370 Soil Improvement @Sta. 0+065~ 0+161 42 22-Jun-23 13-Aug-23 Soil Improvement @Sta. 0+065~ 0+161

RAM1375 Soil Improvement @Sta. 0+162~ 0+262 42 31-Jul-23 17-Sep-23 Soil Improvement @Sta. 0+162~ 0+262

RAM1380 Soil Improvement @Sta. 0+262~ 0+362 43 18-Sep-23 07-Nov-23 Soil Improvement @Sta. 0+262~ 0+362

RAM1385 Soil Improvement @Sta. 0+362~ 0+434 36 08-Nov-23 19-Dec-23 Soil Improvement @Sta. 0+362~ 0+434

DELAY EVENT-6 1138 31-May-22 A 16-Feb-26 16-Feb-26, DELAY EVENT-6


MEP ROOMS &LIFT STATION AND PUMP STATION 1138 31-May-22 A 16-Feb-26 16-Feb-26, MEP ROOMS &LIFT STATION AND PUMP STATI
RAM1015 Delay in Release of IFC Drawings of MEP Rooms 377 31-May-22 A 23-May-23 Delay in Release of IFC Drawings of MEP Rooms

VECHICULAR ROOM 837 24-May-23 16-Feb-26 16-Feb-26, VECHICULAR ROOM


VECHICULAR ROOM 01 (IN ZONE 01) 837 24-May-23 16-Feb-26 16-Feb-26, VECHICULAR ROOM 01 (IN ZONE 01)
ENGINEERING 131 24-May-23 28-Oct-23 28-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 131 24-May-23 28-Oct-23 28-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 112 24-May-23 05-Oct-23 05-Oct-23, EARTH WORKS
JAH-ENG-VR01-SI.862Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

JAH-ENG-VR01-SI.863Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

JAH-ENG-VR01-SI.865Soil Improvement Design Preparation & Submission 14 03-Sep-23 18-Sep-23 Soil Improvement Design Preparation & Submission

JAH-ENG-VR01-SI.870Soil Improvement Design Review & Approval 14 18-Sep-23 05-Oct-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VTR-1-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VTR-1-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VTR-1-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VTR-1-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VTR-1-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VTR-1-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VTR-1-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
4 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VTR-1-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VTR-1-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VTR-1-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VTR-1-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VTR-1-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VTR-1-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VTR-1-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VTR-1-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VTR-1-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VTR-1-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VTR-1-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VTR-1-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 08-Jun-23 12-Jul-23 12-Jul-23, LIGHTNING PROTECTION SYSTEM


VTR-1-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Lightning Protection Drawings Preparation & Submission

VTR-1-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, EARTHING SYSTEM


VTR-1-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Earthing System Shop Drawings Preparation & Submission

VTR-1-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VTR-1-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VTR-1-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VTR-1-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VTR-1-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VTR-1-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VTR-1-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VTR-1-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VTR-1-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 131 24-May-23 28-Oct-23 28-Oct-23, DRY UTILITIES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
5 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER 131 24-May-23 28-Oct-23 28-Oct-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.375
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.385
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


MEP-VR01-ENG-PWR.395
Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

MEP-VR01-ENG-PWR.405
Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


MEP-VR01-ENG-PWR.415
Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

MEP-VR01-ENG-PWR.425
Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


MEP-VR01-ENG-PWR.435
Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

MEP-VR01-ENG-PWR.445
Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

MVSG 31 28-Aug-23 04-Oct-23 04-Oct-23, MVSG


MEP-VR01-ENG-PWR.475
Prepare and submit MVSG shopdrawings 20 28-Aug-23 20-Sep-23 Prepare and submit MVSG shopdrawings

MEP-VR01-ENG-PWR.485
Review and approval MVSG shopdrawings 11 20-Sep-23 04-Oct-23 Review and approval MVSG shopdrawings

BATTERY ROOM 31 20-Sep-23 28-Oct-23 28-Oct-23, BATTERY ROOM


MEP-VR01-ENG-PWR.495
Prepare and submit Battery room shopdrawings 20 20-Sep-23 15-Oct-23 Prepare and submit Battery room shopdrawings

MEP-VR01-ENG-PWR.505
Review and approval Battery room shopdrawings 11 15-Oct-23 28-Oct-23 Review and approval Battery room shopdrawings

PROCUREMENT 262 09-Mar-25 17-Jan-26 17-Jan-26, PROCUREMENT


CIVIL/STRUCTURAL 16 09-Mar-25 26-Mar-25 26-Mar-25, CIVIL/STRUCTURAL
MEP-PRO-CVL.110 Issue Purchase Order 6 09-Mar-25 15-Mar-25 Issue Purchase Order

MEP-PRO-CVL.115 Material Delivery 10 16-Mar-25 26-Mar-25 Material Delivery

MECHANICAL 120 28-Aug-25 17-Jan-26 17-Jan-26, MECHANICAL


FIRE FIGHTING SYSTEM 105 15-Sep-25 17-Jan-26 17-Jan-26, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 15-Sep-25 17-Jan-26 17-Jan-26, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRI
MEP-PRO-MC-FT.110Issue Purchase Order 15 15-Sep-25 04-Oct-25 Issue Purchase Order

MEP-PRO-MC-FT.115Material Delivery 90 04-Oct-25 17-Jan-26 Material Delivery

VENTILATION SYSTEM 105 04-Sep-25 06-Jan-26 06-Jan-26, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 04-Sep-25 06-Jan-26 06-Jan-26, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FAN
MEP-PRO-MC-DCT.110
Issue Purchase Order 15 04-Sep-25 22-Sep-25 Issue Purchase Order

MEP-PRO-MC-DCT.115
Material Delivery 90 22-Sep-25 06-Jan-26 Material Delivery

AIR CONDITIONING WORKS 105 04-Sep-25 06-Jan-26 06-Jan-26, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 04-Sep-25 06-Jan-26 06-Jan-26, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTING
MEP-PRO-MC-SPU.110
Issue Purchase Order 15 04-Sep-25 22-Sep-25 Issue Purchase Order

MEP-PRO-MC-SPU.115
Material Delivery 90 22-Sep-25 06-Jan-26 Material Delivery

PLUMBING SYSTEM 105 28-Aug-25 30-Dec-25 30-Dec-25, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 28-Aug-25 30-Dec-25 30-Dec-25, PUMPS,PIPES,FITTINGS,VALVES
MEP-PRO-MC-PMI.110
Issue Purchase Order 15 28-Aug-25 15-Sep-25 Issue Purchase Order

MEP-PRO-MC-PMI.115
Material Delivery 90 15-Sep-25 30-Dec-25 Material Delivery

ELECTRICAL 137 24-Jul-25 31-Dec-25 31-Dec-25, ELECTRICAL


CABLE TRAY 105 11-Aug-25 13-Dec-25 13-Dec-25, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 11-Aug-25 13-Dec-25 13-Dec-25, CABLE TRAY AND ACCESSORIES,PVC DUCT
MEP-PRO-EL-CTRY.130
Issue Purchase Order 15 11-Aug-25 28-Aug-25 Issue Purchase Order

MEP-PRO-EL-CTRY.135
Material Delivery 90 28-Aug-25 13-Dec-25 Material Delivery

POWER CABLES 105 13-Aug-25 15-Dec-25 15-Dec-25, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 13-Aug-25 15-Dec-25 15-Dec-25, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
MEP-PRO-EL-PWCL.140
Issue Purchase Order 15 13-Aug-25 31-Aug-25 Issue Purchase Order

MEP-PRO-EL-PWCL.145
Material Delivery 90 31-Aug-25 15-Dec-25 Material Delivery

LIGHTING SYSTEM 105 09-Aug-25 10-Dec-25 10-Dec-25, LIGHTING SYSTEM


CONDUIT,LIGHT 105 09-Aug-25 10-Dec-25 10-Dec-25, CONDUIT,LIGHT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
6 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
MEP-PRO-EL-LTS.110Issue Purchase Order 15 09-Aug-25 26-Aug-25 Issue Purchase Order

MEP-PRO-EL-LTS.115Material Delivery 90 26-Aug-25 10-Dec-25 Material Delivery

ELECTRICAL INSTALLATIONS 105 21-Aug-25 23-Dec-25 23-Dec-25, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 21-Aug-25 23-Dec-25 23-Dec-25, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATE
MEP-PRO-EL-INSL.190
Issue Purchase Order 15 21-Aug-25 08-Sep-25 Issue Purchase Order

MEP-PRO-EL-INSL.195
Material Delivery 90 08-Sep-25 23-Dec-25 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 24-Jul-25 25-Nov-25 25-Nov-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 24-Jul-25 25-Nov-25 25-Nov-25, LIGHTNING PROTECTION SYSTEM
MEP-PRO-EL-LPS.110Issue Purchase Order 15 24-Jul-25 11-Aug-25 Issue Purchase Order

MEP-PRO-EL-LPS.115Material Delivery 90 11-Aug-25 25-Nov-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 24-Jul-25 25-Nov-25 25-Nov-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 24-Jul-25 25-Nov-25 25-Nov-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
MEP-PRO-EL-ERS.120
Issue Purchase Order 15 24-Jul-25 11-Aug-25 Issue Purchase Order

MEP-PRO-EL-ERS.125
Material Delivery 90 11-Aug-25 25-Nov-25 Material Delivery

LOW CURRENT 114 19-Aug-25 31-Dec-25 31-Dec-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 19-Aug-25 21-Dec-25 21-Dec-25, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 19-Aug-25 21-Dec-25 21-Dec-25, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER,
MEP-PR-ELL-FA.130Issue Purchase Order 15 19-Aug-25 06-Sep-25 Issue Purchase Order

MEP-PR-ELL-FA.135Material Delivery 90 06-Sep-25 21-Dec-25 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 30-Aug-25 31-Dec-25 31-Dec-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHO
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 30-Aug-25 31-Dec-25 31-Dec-25, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI
MEP-PR-ELL-PH.130Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-PH.135Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 30-Aug-25 31-Dec-25 31-Dec-25, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTE
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 30-Aug-25 31-Dec-25 31-Dec-25, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
MEP-PR-ELL-PA.120Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-PA.125Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

VIDEO SURVEILLANCE 105 30-Aug-25 31-Dec-25 31-Dec-25, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 30-Aug-25 31-Dec-25 31-Dec-25, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,AC
MEP-PR-ELL-VS.120Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-VS.125Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

ACCESS CONTROL SYSTEM 105 30-Aug-25 31-Dec-25 31-Dec-25, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 30-Aug-25 31-Dec-25 31-Dec-25, CABLE,DOOR CONTACT,CONTROL PANEL,CARD RE
MEP-PR-ELL-AC.130Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-AC.135Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 30-Aug-25 31-Dec-25 31-Dec-25, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 30-Aug-25 31-Dec-25 31-Dec-25, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
MEP-PR-ELL-RB.120Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-RB.125Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

SCADA SYSTEM 105 30-Aug-25 31-Dec-25 31-Dec-25, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 30-Aug-25 31-Dec-25 31-Dec-25, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCE
MEP-PR-ELL-SDA.130
Issue Purchase Order 15 30-Aug-25 16-Sep-25 Issue Purchase Order

MEP-PR-ELL-SDA.135
Material Delivery 90 16-Sep-25 31-Dec-25 Material Delivery

CONSTRUCTION 813 21-Jun-23 16-Feb-26 16-Feb-26, CONSTRUCTION


EXCAVATION WORKS 60 21-Jun-23 02-Sep-23 02-Sep-23, EXCAVATION WORKS
JAH-CON-VR01-EX.170Excavation 60 21-Jun-23 02-Sep-23 Excavation

SOIL IMPROVEMENT WORKS 28 05-Oct-23 07-Nov-23 07-Nov-23, SOIL IMPROVEMENT WORKS


JAH-CON-VR01-SI.190Soil Improvement 28 05-Oct-23 07-Nov-23 Soil Improvement

STRUCTURAL WORKS 347 24-Nov-24 11-Jan-26 11-Jan-26, STRUCTURAL WORKS


FOUNDATION 123 24-Nov-24 20-Apr-25 20-Apr-25, FOUNDATION
LIFTING STATION 96 24-Nov-24 16-Mar-25 16-Mar-25, LIFTING STATION
FOUNDATION 28 24-Nov-24 26-Dec-24 26-Dec-24, FOUNDATION

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
7 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
SW-F-LS.100 Foundation Blinding concrete casting casting 1 24-Nov-24 24-Nov-24 Foundation Blinding concrete casting casting

SW-F-LS.105 Foundation water proofing on blinding concrete 3 24-Nov-24 27-Nov-24 Foundation water proofing on blinding concrete

SW-F-LS.110 Foundation Protection screed on water poofing 1 27-Nov-24 28-Nov-24 Foundation Protection screed on water poofing

SW-F-LS.115 Foundation Curing for screed 2 28-Nov-24 01-Dec-24 Foundation Curing for screed

SW-F-LS.120 Foundation Rebar installation 10 01-Dec-24 12-Dec-24 Foundation Rebar installation

SW-F-LS.125 Foundation Formwork installation 8 12-Dec-24 22-Dec-24 Foundation Formwork installation

SW-F-LS.135 Foundation concrete casting 1 22-Dec-24 23-Dec-24 Foundation concrete casting

SW-F-LS.140 Foundation concrete curing 1 23-Dec-24 24-Dec-24 Foundation concrete curing

SW-F-LS.145 Foundation Formwork Removal 2 24-Dec-24 26-Dec-24 Foundation Formwork Removal

WALLS 32 26-Dec-24 02-Feb-25 02-Feb-25, WALLS


SW-W-LS.100 Room Walls Scafolding for rebar 6 26-Dec-24 02-Jan-25 Room Walls Scafolding for rebar

SW-W-LS.105 Room Walls Rebar Installation 10 02-Jan-25 14-Jan-25 Room Walls Rebar Installation

SW-W-LS.115 Room Walls Formwork Installation 11 14-Jan-25 27-Jan-25 Room Walls Formwork Installation

SW-W-LS.120 Room Walls Concrete Casting 1 27-Jan-25 28-Jan-25 Room Walls Concrete Casting

SW-W-LS.125 Room Walls Curing work 1 28-Jan-25 29-Jan-25 Room Walls Curing work

SW-W-LS.130 Room Walls Formwork Removel 3 29-Jan-25 02-Feb-25 Room Walls Formwork Removel

SLAB 36 02-Feb-25 16-Mar-25 16-Mar-25, SLAB


SW-S-LS.100 Room Top Slab Formwork Installation 11 02-Feb-25 15-Feb-25 Room Top Slab Formwork Installation

SW-S-LS.105 Room Top Slab Rebar Installation 8 15-Feb-25 24-Feb-25 Room Top Slab Rebar Installation

SW-S-LS.110 Room Top Slab Concrete Casting 1 24-Feb-25 25-Feb-25 Room Top Slab Concrete Casting

SW-S-LS.115 Room Top slab Curing work 12 25-Feb-25 11-Mar-25 Room Top slab Curing work

SW-S-LS.120 Room Top Slab Formwork Removel 4 11-Mar-25 16-Mar-25 Room Top Slab Formwork Removel

Part-1 22 11-Mar-25 09-Apr-25 09-Apr-25, Part-1


VTR-1-FDN-P1.150 Foundation Blinding concrete casting casting 1 11-Mar-25 12-Mar-25 Foundation Blinding concrete casting casting

VTR-1-FDN-P1.155 Foundation water proofing on blinding concrete 3 12-Mar-25 16-Mar-25 Foundation water proofing on blinding concrete

VTR-1-FDN-P1.160 Foundation Protection screed on water poofing 1 16-Mar-25 16-Mar-25 Foundation Protection screed on water poofing

VTR-1-FDN-P1.165 Foundation Curing for screed 1 17-Mar-25 17-Mar-25 Foundation Curing for screed

VTR-1-FDN-P1.170 Foundation Rebar installation 8 18-Mar-25 26-Mar-25 Foundation Rebar installation

VTR-1-FDN-P1.175 Foundation Formwork installation 4 27-Mar-25 05-Apr-25 Foundation Formwork installation

VTR-1-FDN-P1.185 Foundation concrete casting 1 06-Apr-25 06-Apr-25 Foundation concrete casting

VTR-1-FDN-P1.190 Foundation concrete curing 1 07-Apr-25 07-Apr-25 Foundation concrete curing

VTR-1-FDN-P1.195 Foundation Formwork Removal 2 08-Apr-25 09-Apr-25 Foundation Formwork Removal

Part-2 25 18-Mar-25 20-Apr-25 20-Apr-25, Part-2


VTR-1-FDN-P2.150 Foundation Blinding concrete casting casting 1 18-Mar-25 18-Mar-25 Foundation Blinding concrete casting casting

VTR-1-FDN-P2.155 Foundation water proofing on blinding concrete 3 18-Mar-25 22-Mar-25 Foundation water proofing on blinding concrete

VTR-1-FDN-P2.160 Foundation Protection screed on water poofing 1 22-Mar-25 23-Mar-25 Foundation Protection screed on water poofing

VTR-1-FDN-P2.165 Foundation Curing for screed 2 23-Mar-25 25-Mar-25 Foundation Curing for screed

VTR-1-FDN-P2.170 Foundation Rebar installation 10 25-Mar-25 10-Apr-25 Foundation Rebar installation

VTR-1-FDN-P2.175 Foundation Formwork installation 4 10-Apr-25 15-Apr-25 Foundation Formwork installation

VTR-1-FDN-P2.185 Foundation concrete casting 1 15-Apr-25 16-Apr-25 Foundation concrete casting

VTR-1-FDN-P2.190 Foundation concrete curing 1 16-Apr-25 17-Apr-25 Foundation concrete curing

VTR-1-FDN-P2.195 Foundation Formwork Removal 2 17-Apr-25 20-Apr-25 Foundation Formwork Removal

Part-3 25 24-Nov-24 23-Dec-24 23-Dec-24, Part-3


VTR-1-FDN-P3.150 Foundation Blinding concrete casting casting 1 24-Nov-24 25-Nov-24 Foundation Blinding concrete casting casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
8 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-FDN-P3.155 Foundation water proofing on blinding concrete 3 25-Nov-24 28-Nov-24 Foundation water proofing on blinding concrete

VTR-1-FDN-P3.160 Foundation Protection screed on water poofing 1 28-Nov-24 30-Nov-24 Foundation Protection screed on water poofing

VTR-1-FDN-P3.165 Foundation Curing for screed 2 30-Nov-24 02-Dec-24 Foundation Curing for screed

VTR-1-FDN-P3.170 Foundation Rebar installation 10 02-Dec-24 14-Dec-24 Foundation Rebar installation

VTR-1-FDN-P3.175 Foundation Formwork installation 4 14-Dec-24 18-Dec-24 Foundation Formwork installation

VTR-1-FDN-P3.185 Foundation concrete casting 1 18-Dec-24 19-Dec-24 Foundation concrete casting

VTR-1-FDN-P3.190 Foundation concrete curing 1 19-Dec-24 21-Dec-24 Foundation concrete curing

VTR-1-FDN-P3.195 Foundation Formwork Removal 2 21-Dec-24 23-Dec-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 132 19-Dec-24 27-May-25 27-May-25, WALLS UP TO SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 132 19-Dec-24 27-May-25 27-May-25, WALL CONCRETE CASTING STAGE-1
Part-1 35 07-Apr-25 17-May-25 17-May-25, Part-1
VTR-1-WL-S2-P1.135Room Walls Rebar Installation 10 13-Apr-25 24-Apr-25 Room Walls Rebar Installation

VTR-1-WL-S2-P1.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 24-Apr-25 27-Apr-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-P1.145Room Walls Formwork Installation 12 27-Apr-25 11-May-25 Room Walls Formwork Installation

VTR-1-WL-S2-P1.150Room Walls Concrete Casting 1 11-May-25 12-May-25 Room Walls Concrete Casting

VTR-1-WL-S2-P1.155Room Walls Curing work 1 12-May-25 13-May-25 Room Walls Curing work

VTR-1-WL-S2-P1.160Room Walls Formwork Removel 3 13-May-25 17-May-25 Room Walls Formwork Removel

VTR-1-WL-S2-P1.165Room Walls Scafolding for rebar 6 07-Apr-25 13-Apr-25 Room Walls Scafolding for rebar

Part-2 35 16-Apr-25 27-May-25 27-May-25, Part-2


VTR-1-WL-S2-P2.135Room Walls Rebar Installation 12 23-Apr-25 07-May-25 Room Walls Rebar Installation

VTR-1-WL-S2-P2.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 07-May-25 10-May-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-P2.145Room Walls Formwork Installation 10 10-May-25 21-May-25 Room Walls Formwork Installation

VTR-1-WL-S2-P2.150Room Walls Concrete Casting 1 21-May-25 22-May-25 Room Walls Concrete Casting

VTR-1-WL-S2-P2.155Room Walls Curing work 1 22-May-25 24-May-25 Room Walls Curing work

VTR-1-WL-S2-P2.160Room Walls Formwork Removel 3 24-May-25 27-May-25 Room Walls Formwork Removel

VTR-1-WL-S2-P2.165Room Walls Scafolding for rebar 6 16-Apr-25 23-Apr-25 Room Walls Scafolding for rebar

Part-3 35 19-Dec-24 29-Jan-25 29-Jan-25, Part-3


VTR-1-WL-S2-P3.134Room Walls Scafolding for rebar 6 19-Dec-24 26-Dec-24 Room Walls Scafolding for rebar

VTR-1-WL-S2-P3.135Room Walls Rebar Installation 12 26-Dec-24 09-Jan-25 Room Walls Rebar Installation

VTR-1-WL-S2-P3.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 09-Jan-25 12-Jan-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-P3.145Room Walls Formwork Installation 10 12-Jan-25 23-Jan-25 Room Walls Formwork Installation

VTR-1-WL-S2-P3.150Room Walls Concrete Casting 1 23-Jan-25 25-Jan-25 Room Walls Concrete Casting

VTR-1-WL-S2-P3.155Room Walls Curing work 1 25-Jan-25 26-Jan-25 Room Walls Curing work

VTR-1-WL-S2-P3.160Room Walls Formwork Removel 3 26-Jan-25 29-Jan-25 Room Walls Formwork Removel

TOP SLAB BELOW GROUND LEVEL 79 17-May-25 20-Aug-25 20-Aug-25, TOP SLAB BELOW GROUND LEVEL
Part-1 40 17-May-25 06-Jul-25 06-Jul-25, Part-1
VTR-1-TS-P1.125 Room Top Slab Formwork Installation 15 17-May-25 03-Jun-25 Room Top Slab Formwork Installation

VTR-1-TS-P1.130 Room Top Slab Rebar Installation 8 03-Jun-25 16-Jun-25 Room Top Slab Rebar Installation

VTR-1-TS-P1.135 Room Top Slab Concrete Casting 1 16-Jun-25 17-Jun-25 Room Top Slab Concrete Casting

VTR-1-TS-P1.140 Room Top slab Curing work 12 17-Jun-25 01-Jul-25 Room Top slab Curing work

VTR-1-TS-P1.145 Room Top Slab Formwork Removel 4 01-Jul-25 06-Jul-25 Room Top Slab Formwork Removel

Part-2 39 06-Jul-25 20-Aug-25 20-Aug-25, Part-2


VTR-1-TS-P2.125 Room Top Slab Formwork Installation 15 06-Jul-25 23-Jul-25 Room Top Slab Formwork Installation

VTR-1-TS-P2.130 Room Top Slab Rebar Installation 7 23-Jul-25 31-Jul-25 Room Top Slab Rebar Installation

VTR-1-TS-P2.135 Room Top Slab Concrete Casting 1 31-Jul-25 02-Aug-25 Room Top Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
9 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-TS-P2.140 Room Top slab Curing work 12 02-Aug-25 16-Aug-25 Room Top slab Curing work

VTR-1-TS-P2.145 Room Top Slab Formwork Removel 4 16-Aug-25 20-Aug-25 Room Top Slab Formwork Removel

Part-3 39 06-Jul-25 20-Aug-25 20-Aug-25, Part-3


VTR-1-TS-P3.125 Room Top Slab Formwork Installation 15 06-Jul-25 23-Jul-25 Room Top Slab Formwork Installation

VTR-1-TS-P3.130 Room Top Slab Rebar Installation 7 23-Jul-25 31-Jul-25 Room Top Slab Rebar Installation

VTR-1-TS-P3.135 Room Top Slab Concrete Casting 1 31-Jul-25 02-Aug-25 Room Top Slab Concrete Casting

VTR-1-TS-P3.140 Room Top slab Curing work 12 02-Aug-25 16-Aug-25 Room Top slab Curing work

VTR-1-TS-P3.145 Room Top Slab Formwork Removel 4 16-Aug-25 20-Aug-25 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 97 01-Jul-25 25-Oct-25 25-Oct-25, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 68 01-Jul-25 18-Sep-25 18-Sep-25, WALL CONCRETE CASTING STAGE-1
Part-1 29 01-Jul-25 04-Aug-25 04-Aug-25, Part-1
VTR-1-WL-S1-A.135Room Walls Rebar Installation 8 08-Jul-25 17-Jul-25 Room Walls Rebar Installation

VTR-1-WL-S1-A.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 17-Jul-25 20-Jul-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S1-A.145Room Walls Formwork Installation 8 20-Jul-25 29-Jul-25 Room Walls Formwork Installation

VTR-1-WL-S1-A.150Room Walls Concrete Casting 1 29-Jul-25 30-Jul-25 Room Walls Concrete Casting

VTR-1-WL-S1-A.155Room Walls Curing work 1 30-Jul-25 31-Jul-25 Room Walls Curing work

VTR-1-WL-S1-A.160Room Walls Formwork Removel 3 31-Jul-25 04-Aug-25 Room Walls Formwork Removel

VTR-1-WL-S1-A.165Room Walls Scafolding for rebar 6 01-Jul-25 08-Jul-25 Room Walls Scafolding for rebar

Part-2 29 16-Aug-25 18-Sep-25 18-Sep-25, Part-2


VTR-1-WL-S1-B.135Room Walls Rebar Installation 8 23-Aug-25 01-Sep-25 Room Walls Rebar Installation

VTR-1-WL-S1-B.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 01-Sep-25 03-Sep-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S1-B.145Room Walls Formwork Installation 8 03-Sep-25 13-Sep-25 Room Walls Formwork Installation

VTR-1-WL-S1-B.150Room Walls Concrete Casting 1 13-Sep-25 14-Sep-25 Room Walls Concrete Casting

VTR-1-WL-S1-B.155Room Walls Curing work 1 14-Sep-25 15-Sep-25 Room Walls Curing work

VTR-1-WL-S1-B.160Room Walls Formwork Removel 3 15-Sep-25 18-Sep-25 Room Walls Formwork Removel

VTR-1-WL-S1-B.165Room Walls Scafolding for rebar 6 16-Aug-25 23-Aug-25 Room Walls Scafolding for rebar

Part-3 29 16-Aug-25 18-Sep-25 18-Sep-25, Part-3


VTR-1-WL-S1-C.134Room Walls Scafolding for rebar 6 16-Aug-25 23-Aug-25 Room Walls Scafolding for rebar

VTR-1-WL-S1-C.135Room Walls Rebar Installation 8 23-Aug-25 01-Sep-25 Room Walls Rebar Installation

VTR-1-WL-S1-C.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 01-Sep-25 03-Sep-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S1-C.145Room Walls Formwork Installation 8 03-Sep-25 13-Sep-25 Room Walls Formwork Installation

VTR-1-WL-S1-C.150Room Walls Concrete Casting 1 13-Sep-25 14-Sep-25 Room Walls Concrete Casting

VTR-1-WL-S1-C.155Room Walls Curing work 1 14-Sep-25 15-Sep-25 Room Walls Curing work

VTR-1-WL-S1-C.160Room Walls Formwork Removel 3 15-Sep-25 18-Sep-25 Room Walls Formwork Removel

WALL CONCRETE CASTING STAGE-2 69 04-Aug-25 25-Oct-25 25-Oct-25, WALL CONCRETE CASTING STAGE-2
Part-1 30 04-Aug-25 08-Sep-25 08-Sep-25, Part-1
VTR-1-WL-S2-A.135Room Walls Rebar Installation 8 11-Aug-25 20-Aug-25 Room Walls Rebar Installation

VTR-1-WL-S2-A.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 20-Aug-25 23-Aug-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-A.145Room Walls Formwork Installation 9 23-Aug-25 02-Sep-25 Room Walls Formwork Installation

VTR-1-WL-S2-A.150Room Walls Concrete Casting 1 02-Sep-25 03-Sep-25 Room Walls Concrete Casting

VTR-1-WL-S2-A.155Room Walls Curing work 1 03-Sep-25 04-Sep-25 Room Walls Curing work

VTR-1-WL-S2-A.160Room Walls Formwork Removel 3 04-Sep-25 08-Sep-25 Room Walls Formwork Removel

VTR-1-WL-S2-A.165Room Walls Scafolding for rebar 6 04-Aug-25 11-Aug-25 Room Walls Scafolding for rebar

Part-2 30 18-Sep-25 25-Oct-25 25-Oct-25, Part-2


VTR-1-WL-S2-B.134Room Walls Scafolding for rebar 6 18-Sep-25 27-Sep-25 Room Walls Scafolding for rebar

VTR-1-WL-S2-B.135Room Walls Rebar Installation 8 27-Sep-25 06-Oct-25 Room Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
10 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-WL-S2-B.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 06-Oct-25 08-Oct-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-B.145Room Walls Formwork Installation 9 08-Oct-25 19-Oct-25 Room Walls Formwork Installation

VTR-1-WL-S2-B.150Room Walls Concrete Casting 1 19-Oct-25 20-Oct-25 Room Walls Concrete Casting

VTR-1-WL-S2-B.155Room Walls Curing work 1 20-Oct-25 21-Oct-25 Room Walls Curing work

VTR-1-WL-S2-B.160Room Walls Formwork Removel 3 21-Oct-25 25-Oct-25 Room Walls Formwork Removel

Part-3 30 18-Sep-25 25-Oct-25 25-Oct-25, Part-3


VTR-1-WL-S2-C.135Room Walls Rebar Installation 8 27-Sep-25 06-Oct-25 Room Walls Rebar Installation

VTR-1-WL-S2-C.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 06-Oct-25 08-Oct-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-1-WL-S2-C.145Room Walls Formwork Installation 9 08-Oct-25 19-Oct-25 Room Walls Formwork Installation

VTR-1-WL-S2-C.150Room Walls Concrete Casting 1 19-Oct-25 20-Oct-25 Room Walls Concrete Casting

VTR-1-WL-S2-C.155Room Walls Curing work 1 20-Oct-25 21-Oct-25 Room Walls Curing work

VTR-1-WL-S2-C.160Room Walls Formwork Removel 3 21-Oct-25 25-Oct-25 Room Walls Formwork Removel

VTR-1-WL-S2-C.165Room Walls Scafolding for rebar 6 18-Sep-25 27-Sep-25 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 66 08-Sep-25 25-Nov-25 25-Nov-25, SLAB ABOVE GROUND LEVEL
Part-1 27 08-Sep-25 11-Oct-25 11-Oct-25, Part-1
VTR-1-SLB-A.125 Room Top Slab Formwork Installation 6 08-Sep-25 15-Sep-25 Room Top Slab Formwork Installation

VTR-1-SLB-A.130 Room Top Slab Rebar Installation 4 15-Sep-25 20-Sep-25 Room Top Slab Rebar Installation

VTR-1-SLB-A.135 Room Top Slab Concrete Casting 1 20-Sep-25 21-Sep-25 Room Top Slab Concrete Casting

VTR-1-SLB-A.140 Room Top slab Curing work 12 21-Sep-25 06-Oct-25 Room Top slab Curing work

VTR-1-SLB-A.145 Room Top Slab Formwork Removel 4 06-Oct-25 11-Oct-25 Room Top Slab Formwork Removel

Part-2 27 25-Oct-25 25-Nov-25 25-Nov-25, Part-2


VTR-1-SLB-B.125 Room Top Slab Formwork Installation 6 25-Oct-25 01-Nov-25 Room Top Slab Formwork Installation

VTR-1-SLB-B.130 Room Top Slab Rebar Installation 4 01-Nov-25 05-Nov-25 Room Top Slab Rebar Installation

VTR-1-SLB-B.135 Room Top Slab Concrete Casting 1 05-Nov-25 06-Nov-25 Room Top Slab Concrete Casting

VTR-1-SLB-B.140 Room Top slab Curing work 12 06-Nov-25 20-Nov-25 Room Top slab Curing work

VTR-1-SLB-B.145 Room Top Slab Formwork Removel 4 20-Nov-25 25-Nov-25 Room Top Slab Formwork Removel

Part-3 27 25-Oct-25 25-Nov-25 25-Nov-25, Part-3


VTR-1-SLB-C.125 Room Top Slab Formwork Installation 6 25-Oct-25 01-Nov-25 Room Top Slab Formwork Installation

VTR-1-SLB-C.130 Room Top Slab Rebar Installation 4 01-Nov-25 05-Nov-25 Room Top Slab Rebar Installation

VTR-1-SLB-C.135 Room Top Slab Concrete Casting 1 05-Nov-25 06-Nov-25 Room Top Slab Concrete Casting

VTR-1-SLB-C.140 Room Top slab Curing work 12 06-Nov-25 20-Nov-25 Room Top slab Curing work

VTR-1-SLB-C.145 Room Top Slab Formwork Removel 4 20-Nov-25 25-Nov-25 Room Top Slab Formwork Removel

WATER PROOFING 47 18-Nov-25 11-Jan-26 11-Jan-26, WATER PROOFING


WALL WATER PROOFING STAGE-1 24 18-Nov-25 16-Dec-25 16-Dec-25, WALL WATER PROOFING STAGE-1
VTR-1-WP-WL-S1.115Surface preparation work 6 18-Nov-25 25-Nov-25 Surface preparation work

VTR-1-WP-WL-S1.120Applying of waterproofing material 12 25-Nov-25 09-Dec-25 Applying of waterproofing material

VTR-1-WP-WL-S1.125VR Back filling 6 09-Dec-25 16-Dec-25 VR Back filling

WALL WATER PROOFING STAGE-2 24 25-Nov-25 23-Dec-25 23-Dec-25, WALL WATER PROOFING STAGE-2
VTR-1-WP-WL-S2.115Surface preparation work 6 25-Nov-25 02-Dec-25 Surface preparation work

VTR-1-WP-WL-S2.120Applying of waterproofing material 12 02-Dec-25 16-Dec-25 Applying of waterproofing material

VTR-1-WP-WL-S2.125VR Back filling 6 16-Dec-25 23-Dec-25 VR Back filling

WALL WATER PROOFING STAGE-3 24 02-Dec-25 30-Dec-25 30-Dec-25, WALL WATER PROOFING STAGE-3
VTR-1-WP-WL-S3.115Surface preparation work 6 02-Dec-25 09-Dec-25 Surface preparation work

VTR-1-WP-WL-S3.120Applying of waterproofing material 12 09-Dec-25 23-Dec-25 Applying of waterproofing material

VTR-1-WP-WL-S3.125VR Back filling 6 23-Dec-25 30-Dec-25 VR Back filling

WALL WATER PROOFING STAGE-4 24 09-Dec-25 06-Jan-26 06-Jan-26, WALL WATER PROOFING STAGE-4

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
11 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-WP-WL-S4.115Surface preparation work 6 09-Dec-25 16-Dec-25 Surface preparation work

VTR-1-WP-WL-S4.120Applying of waterproofing material 12 16-Dec-25 30-Dec-25 Applying of waterproofing material

VTR-1-WP-WL-S4.125VR Back filling 6 30-Dec-25 06-Jan-26 VR Back filling

TOP SLAB WATER PROOFING 41 25-Nov-25 11-Jan-26 11-Jan-26, TOP SLAB WATER PROOFING
VTR-1-WP-SLB-S1.115
Surface preparation work 12 25-Nov-25 09-Dec-25 Surface preparation work

VTR-1-WP-SLB-S1.120
Applying of waterproofing material 15 23-Dec-25 10-Jan-26 Applying of waterproofing material

VTR-1-WP-SLB-S1.125
Leak Test 1 10-Jan-26 11-Jan-26 Leak Test

MECHANICAL ROOM MEP 72 25-Nov-25 16-Feb-26 16-Feb-26, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 64 25-Nov-25 08-Feb-26 08-Feb-26, ELECTRICAL WORK IN ROOM
POWER SYSTEM 57 25-Nov-25 31-Jan-26 31-Jan-26, POWER SYSTEM
EARTHING SYSTEM 25 25-Nov-25 23-Dec-25 23-Dec-25, EARTHING SYSTEM
VTR-1-EES-105 Earthing system soil resistivity test 6 25-Nov-25 01-Dec-25 Earthing system soil resistivity test

VTR-1-EES-115 Earthing system Copper rod/ earthing pit installation 8 02-Dec-25 10-Dec-25 Earthing system Copper rod/ earthing pit installation

VTR-1-EES-125 Earthing system Termination 6 10-Dec-25 17-Dec-25 Earthing system Termination

VTR-1-EES-135 Earthing system Initial Testing 5 17-Dec-25 23-Dec-25 Earthing system Initial Testing

LIGHTING SYSTEM 37 02-Dec-25 13-Jan-26 13-Jan-26, LIGHTING SYSTEM


VTR-1-ELI.105 Lighting system Conduit and boxes Installation 8 02-Dec-25 10-Dec-25 Lighting system Conduit and boxes Installation

VTR-1-ELI.115 Lighting system Cable Pulling 8 10-Dec-25 20-Dec-25 Lighting system Cable Pulling

VTR-1-ELI.125 Lighting system Installations 8 20-Dec-25 29-Dec-25 Lighting system Installations

VTR-1-ELI.135 Lighting system Termination 8 29-Dec-25 07-Jan-26 Lighting system Termination

VTR-1-ELI.145 Lighting system Initial Testing 5 07-Jan-26 13-Jan-26 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 02-Dec-25 26-Jan-26 26-Jan-26, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-1-ECT.105 Cable Tray Installation 10 02-Dec-25 13-Dec-25 Cable Tray Installation

VTR-1-ECT.115 Cable Tray Inspection 10 13-Dec-25 24-Dec-25 Cable Tray Inspection

VTR-1-ECT.125 LV Cable pulling 10 24-Dec-25 05-Jan-26 LV Cable pulling

VTR-1-ECT.135 LV Cable Termination 10 05-Jan-26 17-Jan-26 LV Cable Termination

VTR-1-ECT.145 LV Cable Initial Testing 8 17-Jan-26 26-Jan-26 LV Cable Initial Testing

SMALL POWER SYSTEM 39 02-Dec-25 15-Jan-26 15-Jan-26, SMALL POWER SYSTEM


VTR-1-ESP.105 Small Power Conduit and boxes Installation 12 02-Dec-25 15-Dec-25 Small Power Conduit and boxes Installation

VTR-1-ESP.115 Small Power Cable Pulling 10 15-Dec-25 27-Dec-25 Small Power Cable Pulling

VTR-1-ESP.125 Small Power Installations 6 27-Dec-25 03-Jan-26 Small Power Installations

VTR-1-ESP.135 Small Power Termination 6 03-Jan-26 10-Jan-26 Small Power Termination

VTR-1-ESP.145 Small Power Initial Testing 5 10-Jan-26 15-Jan-26 Small Power Initial Testing

POWER DISTRIBUTION 39 15-Dec-25 31-Jan-26 31-Jan-26, POWER DISTRIBUTION


GENERATOR 39 15-Dec-25 31-Jan-26 31-Jan-26, GENERATOR
VTR-1-EPD.105 Generator Cable Tray Installation 7 15-Dec-25 23-Dec-25 Generator Cable Tray Installation

VTR-1-EPD.115 Generator Cable Pulling 7 23-Dec-25 31-Dec-25 Generator Cable Pulling

VTR-1-EPD.125 Generator Cell Pannel Installation 7 31-Dec-25 08-Jan-26 Generator Cell Pannel Installation

VTR-1-EPD.135 Generator Installation 7 08-Jan-26 17-Jan-26 Generator Installation

VTR-1-EPD.145 Generator Pannel / Cable Termination 7 17-Jan-26 25-Jan-26 Generator Pannel / Cable Termination

VTR-1-EPD.155 Generator Pannel / Cable initial Testing 5 25-Jan-26 31-Jan-26 Generator Pannel / Cable initial Testing

UPS 28 15-Dec-25 18-Jan-26 18-Jan-26, UPS


VTR-1-EPD.165 UPS Cable Tray Installation 5 15-Dec-25 21-Dec-25 UPS Cable Tray Installation

VTR-1-EPD.175 UPS Cable Pulling 5 21-Dec-25 27-Dec-25 UPS Cable Pulling

VTR-1-EPD.185 UPS Pannel Installation 5 27-Dec-25 01-Jan-26 UPS Pannel Installation

VTR-1-EPD.195 UPS Installation 5 01-Jan-26 07-Jan-26 UPS Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
12 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-EPD.205 UPS Pannel / Cable Termination 5 07-Jan-26 13-Jan-26 UPS Pannel / Cable Termination

VTR-1-EPD.215 UPS Pannel / Cable initial Testing 4 13-Jan-26 18-Jan-26 UPS Pannel / Cable initial Testing

MDB 33 15-Dec-25 22-Jan-26 22-Jan-26, MDB


VTR-1-EPD.225 MDB Cable Tray Installation 7 15-Dec-25 23-Dec-25 MDB Cable Tray Installation

VTR-1-EPD.235 MDB Cable Pulling 7 23-Dec-25 31-Dec-25 MDB Cable Pulling

VTR-1-EPD.245 MDB Pannel Installation 7 31-Dec-25 08-Jan-26 MDB Pannel Installation

VTR-1-EPD.255 MDB Pannel / Cable Termination 7 08-Jan-26 17-Jan-26 MDB Pannel / Cable Termination

VTR-1-EPD.265 MDB Pannel / Cable initial Testing 5 17-Jan-26 22-Jan-26 MDB Pannel / Cable initial Testing

MCC 33 15-Dec-25 22-Jan-26 22-Jan-26, MCC


VTR-1-EPD.325 MCC Cable Tray Installation 7 15-Dec-25 23-Dec-25 MCC Cable Tray Installation

VTR-1-EPD.335 MCC Cable Pulling 7 23-Dec-25 31-Dec-25 MCC Cable Pulling

VTR-1-EPD.345 MCC Pannel Installation 7 31-Dec-25 08-Jan-26 MCC Pannel Installation

VTR-1-EPD.355 MCC Pannel / Cable Termination 7 08-Jan-26 17-Jan-26 MCC Pannel / Cable Termination

VTR-1-EPD.365 MCC Pannel / Cable initial Testing 5 17-Jan-26 22-Jan-26 MCC Pannel / Cable initial Testing

SMSB 24 15-Dec-25 12-Jan-26 12-Jan-26, SMSB


VTR-1-EPD.275 SMSB Cable Tray Installation 5 15-Dec-25 21-Dec-25 SMSB Cable Tray Installation

VTR-1-EPD.285 SMSB Cable Pulling 5 21-Dec-25 27-Dec-25 SMSB Cable Pulling

VTR-1-EPD.295 SMSB Pannel Installation 5 27-Dec-25 01-Jan-26 SMSB Pannel Installation

VTR-1-EPD.305 SMSB Pannel / Cable Termination 5 01-Jan-26 07-Jan-26 SMSB Pannel / Cable Termination

VTR-1-EPD.315 SMSB Pannel / Cable initial Testing 4 07-Jan-26 12-Jan-26 SMSB Pannel / Cable initial Testing

DB 24 15-Dec-25 12-Jan-26 12-Jan-26, DB


VTR-1-EPD.375 DB Cable Tray Installation 5 15-Dec-25 21-Dec-25 DB Cable Tray Installation

VTR-1-EPD.385 DB Cable Pulling 5 21-Dec-25 27-Dec-25 DB Cable Pulling

VTR-1-EPD.395 DB Pannel Installation 5 27-Dec-25 01-Jan-26 DB Pannel Installation

VTR-1-EPD.405 DB Pannel / Cable Termination 5 01-Jan-26 07-Jan-26 DB Pannel / Cable Termination

VTR-1-EPD.415 DB Pannel / Cable initial Testing 4 07-Jan-26 12-Jan-26 DB Pannel / Cable initial Testing

ISOLATOR 24 15-Dec-25 12-Jan-26 12-Jan-26, ISOLATOR


VTR-1-EPD.425 Isolators Cable Tray Installation 5 15-Dec-25 21-Dec-25 Isolators Cable Tray Installation

VTR-1-EPD.435 Isolators Cable Pulling 5 21-Dec-25 27-Dec-25 Isolators Cable Pulling

VTR-1-EPD.445 Isolators Pannel Installation 5 27-Dec-25 01-Jan-26 Isolators Pannel Installation

VTR-1-EPD.455 Isolators Pannel / Cable Termination 5 01-Jan-26 07-Jan-26 Isolators Pannel / Cable Termination

VTR-1-EPD.465 Isolators Pannel / Cable initial Testing 4 07-Jan-26 12-Jan-26 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 15-Dec-25 12-Jan-26 12-Jan-26, LCP/ ELCP


VTR-1-EPD.475 LCP/ELCP Cable Tray Installation 5 15-Dec-25 21-Dec-25 LCP/ELCP Cable Tray Installation

VTR-1-EPD.485 LCP/ELCP Cable Pulling 5 21-Dec-25 27-Dec-25 LCP/ELCP Cable Pulling

VTR-1-EPD.495 LCP/ELCP Pannel Installation 5 27-Dec-25 01-Jan-26 LCP/ELCP Pannel Installation

VTR-1-EPD.505 LCP/ELCP Pannel / Cable Termination 5 01-Jan-26 07-Jan-26 LCP/ELCP Pannel / Cable Termination

VTR-1-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 07-Jan-26 12-Jan-26 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 10-Dec-25 08-Feb-26 08-Feb-26, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 10-Dec-25 28-Jan-26 28-Jan-26, FIRE ALARM SYSTEM
VTR-1-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 10-Dec-25 21-Dec-25 Fire Alarm Conduit /Cable Tray Installation

VTR-1-ELFA.115 Fire Alarm Cable Pulling 9 21-Dec-25 31-Dec-25 Fire Alarm Cable Pulling

VTR-1-ELFA.125 Fire Alarm Devices Installation 9 31-Dec-25 11-Jan-26 Fire Alarm Devices Installation

VTR-1-ELFA.135 Fire Alarm Devices and Cable Termination 9 11-Jan-26 21-Jan-26 Fire Alarm Devices and Cable Termination

VTR-1-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 21-Jan-26 28-Jan-26 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 21-Dec-25 08-Feb-26 08-Feb-26, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPH

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
13 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-1-ELVS.105 ICT System Conduit /Cable Tray Installation 9 21-Dec-25 31-Dec-25 ICT System Conduit /Cable Tray Installation

VTR-1-ELVS.115 ICT System Cable Pulling 9 31-Dec-25 11-Jan-26 ICT System Cable Pulling

VTR-1-ELVS.125 ICT System Devices Installation 9 11-Jan-26 21-Jan-26 ICT System Devices Installation

VTR-1-ELVS.135 ICT System Devices and Cable Termination 9 21-Jan-26 01-Feb-26 ICT System Devices and Cable Termination

VTR-1-ELVS.145 ICT System Devices and Cable initial Testing 6 01-Feb-26 08-Feb-26 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 21-Dec-25 08-Feb-26 08-Feb-26, ACCESS CONTROL SYSTEM


VTR-1-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 21-Dec-25 31-Dec-25 Access Control System Conduit /Cable Tray Installation

VTR-1-ELAC.115 Access Control System Cable Pulling 9 31-Dec-25 11-Jan-26 Access Control System Cable Pulling

VTR-1-ELAC.125 Access Control System Devices Installation 9 11-Jan-26 21-Jan-26 Access Control System Devices Installation

VTR-1-ELAC.135 Access Control System Devices and Cable Termination 9 21-Jan-26 01-Feb-26 Access Control System Devices and Cable Termination

VTR-1-ELAC.145 Access Control System Devices and Cable initial Testing 6 01-Feb-26 08-Feb-26 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 21-Dec-25 08-Feb-26 08-Feb-26, PUBLIC ADDRESS SYSTEM


VTR-1-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 21-Dec-25 31-Dec-25 Public Address System Conduit /Cable Tray Installation

VTR-1-ELPA.115 Public Address System Cable Pulling 9 31-Dec-25 11-Jan-26 Public Address System Cable Pulling

VTR-1-ELPA.125 Public Address System Devices Installation 9 11-Jan-26 21-Jan-26 Public Address System Devices Installation

VTR-1-ELPA.135 Public Address System Devices and Cable Termination 9 21-Jan-26 01-Feb-26 Public Address System Devices and Cable Termination

VTR-1-ELPA.145 Public Address System Devices and Cable initial Testing 6 01-Feb-26 08-Feb-26 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 21-Dec-25 08-Feb-26 08-Feb-26, SCADA SYSTEM


VTR-1-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 21-Dec-25 31-Dec-25 SCADA System Conduit /Cable Tray Installation

VTR-1-ELSC.115 SCADA System Cable Pulling 9 31-Dec-25 11-Jan-26 SCADA System Cable Pulling

VTR-1-ELSC.125 SCADA System Devices Installation 9 11-Jan-26 21-Jan-26 SCADA System Devices Installation

VTR-1-ELSC.135 SCADA System Devices and Cable Termination 9 21-Jan-26 01-Feb-26 SCADA System Devices and Cable Termination

VTR-1-ELSC.145 SCADA System Devices and Cable initial Testing 6 01-Feb-26 08-Feb-26 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 21-Dec-25 08-Feb-26 08-Feb-26, RADIO RE- BROADCOASTING/ TETRA
VTR-1-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 21-Dec-25 31-Dec-25 Radio/TETRA System Conduit /Cable Tray Installation

VTR-1-ELRD.115 Radio/TETRA System Cable Pulling 9 31-Dec-25 11-Jan-26 Radio/TETRA System Cable Pulling

VTR-1-ELRD.125 Radio/TETRA System Devices Installation 9 11-Jan-26 21-Jan-26 Radio/TETRA System Devices Installation

VTR-1-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 21-Jan-26 01-Feb-26 Radio/TETRA System Devices and Cable Termination

VTR-1-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 01-Feb-26 08-Feb-26 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 50 20-Dec-25 16-Feb-26 16-Feb-26, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 23-Dec-25 20-Jan-26 20-Jan-26, FIRE FIGHTING
VTR-1-MFF.105 Fire Fighting system Pipe and accessories installation 21 23-Dec-25 17-Jan-26 Fire Fighting system Pipe and accessories installation

VTR-1-MFF.115 Fire Fighting system deluge valve installation 16 29-Dec-25 17-Jan-26 Fire Fighting system deluge valve installation

VTR-1-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 10-Jan-26 17-Jan-26 Fire Fighting system fire hose cabinet/extingusher installation

VTR-1-MFF.140 Fire Fighting system initial testing 3 17-Jan-26 20-Jan-26 Fire Fighting system initial testing

VTR-1-MFF.145 Fire Fighting clean agent system 2 14-Jan-26 17-Jan-26 Fire Fighting clean agent system

HVAC 50 20-Dec-25 16-Feb-26 16-Feb-26, HVAC


VTR-1-MHV.115 Air conditioning system installation 12 23-Dec-25 06-Jan-26 Air conditioning system installation

VTR-1-MHV.120 Fan installation 15 20-Dec-25 06-Jan-26 Fan installation

VTR-1-MHV.125 Duct and accessories installation 28 06-Jan-26 08-Feb-26 Duct and accessories installation

VTR-1-MHV.135 HVAC inital testing 7 08-Feb-26 16-Feb-26 HVAC inital testing

PLUMBING 8 23-Dec-25 01-Jan-26 01-Jan-26, PLUMBING


VTR-1-MPL.105 Plumbing drainage system installation 6 23-Dec-25 30-Dec-25 Plumbing drainage system installation

VTR-1-MPL.115 Plumbing drainage system initial testing 2 30-Dec-25 01-Jan-26 Plumbing drainage system initial testing

DRY UTILITES 22 23-Dec-25 19-Jan-26 19-Jan-26, DRY UTILITES


POWER 22 23-Dec-25 19-Jan-26 19-Jan-26, POWER

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
14 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER LV 16 23-Dec-25 11-Jan-26 11-Jan-26, POWER LV
DU-P-LV.100 Installation of support 1 23-Dec-25 24-Dec-25 Installation of support

DU-P-LV.110 Installation of horizontal busbar 2 24-Dec-25 27-Dec-25 Installation of horizontal busbar

DU-P-LV.120 Installation of vertical busbar 2 27-Dec-25 28-Dec-25 Installation of vertical busbar

DU-P-LV.130 Installation of left/right elbow 2 28-Dec-25 30-Dec-25 Installation of left/right elbow

DU-P-LV.140 Installation of right horizintal offset 2 30-Dec-25 31-Dec-25 Installation of right horizintal offset

DU-P-LV.150 Instalaltion of upward vertical offset 3 01-Jan-26 05-Jan-26 Instalaltion of upward vertical offset

DU-P-LV.160 Installation of downward vertical offset 3 05-Jan-26 08-Jan-26 Installation of downward vertical offset

DU-P-LV.170 Installation of transformer and panel connection 2 08-Jan-26 11-Jan-26 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 23-Dec-25 13-Jan-26 13-Jan-26, MEDIUM VOLTAGE


DU-P-MV.100 Installation of cable try, arm, racks and ladder 6 23-Dec-25 31-Dec-25 Installation of cable try, arm, racks and ladder

DU-P-MV.110 Installation of MV Cable 4 31-Dec-25 05-Jan-26 Installation of MV Cable

DU-P-MV.120 Installation of cable cleats 2 05-Jan-26 06-Jan-26 Installation of cable cleats

DU-P-MV.130 Installation of gland 1 06-Jan-26 07-Jan-26 Installation of gland

DU-P-MV.140 splicing/termination of MV cable 2 07-Jan-26 10-Jan-26 splicing/termination of MV cable

DU-P-MV.150 Testing and Pre-commissioning of cable 2 10-Jan-26 11-Jan-26 Testing and Pre-commissioning of cable

DU-P-MV.160 Energezation 2 11-Jan-26 13-Jan-26 Energezation

TRANSFORMER 16 23-Dec-25 11-Jan-26 11-Jan-26, TRANSFORMER


MEP-VR01-ELE-PWR.905
Installation of Transformer unit 2 23-Dec-25 25-Dec-25 Installation of Transformer unit

MEP-VR01-ELE-PWR.915
Testing and Pre-Commissioning of unit 1 25-Dec-25 27-Dec-25 Testing and Pre-Commissioning of unit

MEP-VR01-ELE-PWR.925
Termination and Splicing of MV Cable 3 27-Dec-25 30-Dec-25 Termination and Splicing of MV Cable

MEP-VR01-ELE-PWR.935
Termination and Splicing of LV Cable/bus way 3 30-Dec-25 03-Jan-26 Termination and Splicing of LV Cable/bus way

MEP-VR01-ELE-PWR.945
Installation and connection of I/O system 2 03-Jan-26 05-Jan-26 Installation and connection of I/O system

MEP-VR01-ELE-PWR.955
Installation of Grounding and Protection System 2 06-Jan-26 08-Jan-26 Installation of Grounding and Protection System

MEP-VR01-ELE-PWR.965
Testing and Commissioning of MV System 1 08-Jan-26 10-Jan-26 Testing and Commissioning of MV System

MEP-VR01-ELE-PWR.975
Testing and Commissioning of LV System 1 10-Jan-26 10-Jan-26 Testing and Commissioning of LV System

MEP-VR01-ELE-PWR.985
Energezation 1 11-Jan-26 11-Jan-26 Energezation

RMU 16 23-Dec-25 11-Jan-26 11-Jan-26, RMU


DU-P-RMU.100 Installation RMU unit 2 23-Dec-25 27-Dec-25 Installation RMU unit

DU-P-RMU.110 Testing and Pre-Commissioning of unit 2 27-Dec-25 28-Dec-25 Testing and Pre-Commissioning of unit

DU-P-RMU.120 Termination and Splicing of Ring-MV Cable 4 28-Dec-25 01-Jan-26 Termination and Splicing of Ring-MV Cable

DU-P-RMU.130 Termination and Splicing of T-MV Cable 4 01-Jan-26 06-Jan-26 Termination and Splicing of T-MV Cable

DU-P-RMU.140 Installation of Grounding and Protection System 2 06-Jan-26 10-Jan-26 Installation of Grounding and Protection System

DU-P-RMU.150 Testing and Commissioning of MV System 1 10-Jan-26 10-Jan-26 Testing and Commissioning of MV System

DU-P-RMU.160 Energezation 1 11-Jan-26 11-Jan-26 Energezation

MVSG 22 23-Dec-25 19-Jan-26 19-Jan-26, MVSG


DU-P-MVSG.100 Installation of MVSG module unit 6 23-Dec-25 30-Dec-25 Installation of MVSG module unit

DU-P-MVSG.110 Testing and Pre-Commissioning of each module 3 30-Dec-25 03-Jan-26 Testing and Pre-Commissioning of each module

DU-P-MVSG.120 Termination and Splicing of MV Cable each module 6 04-Jan-26 10-Jan-26 Termination and Splicing of MV Cable each module

DU-P-MVSG.130 Installation of Grounding system and protection 2 11-Jan-26 13-Jan-26 Installation of Grounding system and protection

DU-P-MVSG.140 Installation and connection of I/O system 2 13-Jan-26 15-Jan-26 Installation and connection of I/O system

DU-P-MVSG.150 Testing and Commissioning of MV System 1 15-Jan-26 17-Jan-26 Testing and Commissioning of MV System

DU-P-MVSG.160 Testing and Commissioning of Metered System 1 17-Jan-26 18-Jan-26 Testing and Commissioning of Metered System

DU-P-MVSG.170 Energezation 1 18-Jan-26 19-Jan-26 Energezation

BATTERY ROOM 16 23-Dec-25 11-Jan-26 11-Jan-26, BATTERY ROOM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
15 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-BATRM.100 Installation of Battery racks 3 23-Dec-25 27-Dec-25 Installation of Battery racks

DU-P-BATRM.110 Installation of batterys 3 28-Dec-25 31-Dec-25 Installation of batterys

DU-P-BATRM.120 Installation of DC cable 3 31-Dec-25 04-Jan-26 Installation of DC cable

DU-P-BATRM.130 Installation of battery control panel 2 04-Jan-26 06-Jan-26 Installation of battery control panel

DU-P-BATRM.140 installation of grounding system 2 06-Jan-26 10-Jan-26 installation of grounding system

DU-P-BATRM.150 Testing and Commissioning 2 10-Jan-26 11-Jan-26 Testing and Commissioning

VECHICULAR ROOM 06 (IN ZONE 04) 450 24-May-23 12-Nov-24 12-Nov-24, VECHICULAR ROOM 06 (IN ZONE 04)
ENGINEERING 109 24-May-23 03-Oct-23 03-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 109 24-May-23 03-Oct-23 03-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 91 24-May-23 10-Sep-23 10-Sep-23, EARTH WORKS
JAH-ENG-VR06-SI.882Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

JAH-ENG-VR06-SI.883Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

JAH-ENG-VR06-SI.885Soil Improvement Design Preparation & Submission 14 09-Aug-23 24-Aug-23 Soil Improvement Design Preparation & Submission

JAH-ENG-VR06-SI.890Soil Improvement Design Review & Approval 14 24-Aug-23 10-Sep-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VTR.6-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VTR.6-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VTR.6-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VTR.6-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VTR.6-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VTR.6-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VTR.6-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VTR.6-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VTR.6-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VTR.6-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VTR.6-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VTR.6-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VTR.6-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VTR.6-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VTR.6-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VTR.6-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VTR.6-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VTR.6-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VTR.6-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VTR.6-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


VTR.6-ENG-EL-LP.110Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

VTR.6-ENG-EL-LP.115Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
16 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR.6-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

VTR.6-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VTR.6-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VTR.6-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VTR.6-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VTR.6-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VTR.6-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VTR.6-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VTR.6-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VTR.6-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY ULTITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY ULTITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-PLV.100 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-PLV.110 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-PMV.100 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-PMV.110 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-PT.100 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-PT.110 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-PRMU.100 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-PRMU.110 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 281 04-Dec-23 04-Nov-24 04-Nov-24, PROCUREMENT


CIVIL/STRUCTURAL 16 04-Dec-23 21-Dec-23 21-Dec-23, CIVIL/STRUCTURAL
VTR.6-PRO-CV.110 Issue Purchase Order 6 04-Dec-23 10-Dec-23 Issue Purchase Order

VTR.6-PRO-CV.115 Material Delivery 10 11-Dec-23 21-Dec-23 Material Delivery

MECHANICAL 145 14-May-24 04-Nov-24 04-Nov-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 14-May-24 17-Sep-24 17-Sep-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 14-May-24 17-Sep-24 17-Sep-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VTR.6-PR-MC-FF.110Issue Purchase Order 15 14-May-24 30-May-24 Issue Purchase Order

VTR.6-PR-MC-FF.115Material Delivery 90 01-Jun-24 17-Sep-24 Material Delivery

VENTILATION SYSTEM 105 04-Jul-24 04-Nov-24 04-Nov-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 04-Jul-24 04-Nov-24 04-Nov-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VTR.6-PR-MC-DS.110Issue Purchase Order 15 04-Jul-24 21-Jul-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
17 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR.6-PR-MC-DS.115Material Delivery 90 22-Jul-24 04-Nov-24 Material Delivery

AIR CONDITIONING WORKS 105 04-Jul-24 04-Nov-24 04-Nov-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 04-Jul-24 04-Nov-24 04-Nov-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VTR.6-PR-MC-AC.110Issue Purchase Order 15 04-Jul-24 21-Jul-24 Issue Purchase Order

VTR.6-PR-MC-AC.115Material Delivery 90 22-Jul-24 04-Nov-24 Material Delivery

PLUMBING SYSTEM 105 27-Jun-24 28-Oct-24 28-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 27-Jun-24 28-Oct-24 28-Oct-24, PUMPS,PIPES,FITTINGS,VALVES
VTR.6-PR-MC-PI.110Issue Purchase Order 15 27-Jun-24 14-Jul-24 Issue Purchase Order

VTR.6-PR-MC-PI.115Material Delivery 90 15-Jul-24 28-Oct-24 Material Delivery

ELECTRICAL 212 25-Dec-23 04-Sep-24 04-Sep-24, ELECTRICAL


CABLE TRAY 105 23-Apr-24 27-Aug-24 27-Aug-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 23-Apr-24 27-Aug-24 27-Aug-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
VTR.6-PR-EL-CT.110 Issue Purchase Order 15 23-Apr-24 09-May-24 Issue Purchase Order

VTR.6-PR-EL-CT.115 Material Delivery 90 11-May-24 27-Aug-24 Material Delivery

POWER CABLES 105 23-Apr-24 27-Aug-24 27-Aug-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 23-Apr-24 27-Aug-24 27-Aug-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VTR.6-PR-EL-PC.110Issue Purchase Order 15 23-Apr-24 09-May-24 Issue Purchase Order

VTR.6-PR-EL-PC.115Material Delivery 90 11-May-24 27-Aug-24 Material Delivery

LIGHTING SYSTEM 105 25-Dec-23 29-Apr-24 29-Apr-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 25-Dec-23 29-Apr-24 29-Apr-24, CONDUIT,LIGHT
VTR.6-PR-EL-LS.110 Issue Purchase Order 15 25-Dec-23 11-Jan-24 Issue Purchase Order

VTR.6-PR-EL-LS.115 Material Delivery 90 11-Jan-24 29-Apr-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 20-Apr-24 24-Aug-24 24-Aug-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 20-Apr-24 24-Aug-24 24-Aug-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VTR.6-PR-EL-EI.110 Issue Purchase Order 15 20-Apr-24 06-May-24 Issue Purchase Order

VTR.6-PR-EL-EI.115 Material Delivery 90 07-May-24 24-Aug-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 08-Apr-24 17-Aug-24 17-Aug-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 08-Apr-24 17-Aug-24 17-Aug-24, LIGHTNING PROTECTION SYSTEM
VTR.6-PR-EL-LP.110 Issue Purchase Order 15 08-Apr-24 29-Apr-24 Issue Purchase Order

VTR.6-PR-EL-LP.115 Material Delivery 90 29-Apr-24 17-Aug-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 08-Apr-24 17-Aug-24 17-Aug-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 08-Apr-24 17-Aug-24 17-Aug-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VTR.6-PR-EL-ES.110 Issue Purchase Order 15 08-Apr-24 29-Apr-24 Issue Purchase Order

VTR.6-PR-EL-ES.115 Material Delivery 90 29-Apr-24 17-Aug-24 Material Delivery

LOW CURRENT 105 30-Apr-24 04-Sep-24 04-Sep-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 30-Apr-24 04-Sep-24 04-Sep-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 30-Apr-24 04-Sep-24 04-Sep-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VTR.6-PR-ELL-FA.20Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-FA.25Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 30-Apr-24 04-Sep-24 04-Sep-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 30-Apr-24 04-Sep-24 04-Sep-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VTR.6-PR-ELL-PH.20
Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-PH.25
Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 30-Apr-24 04-Sep-24 04-Sep-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 30-Apr-24 04-Sep-24 04-Sep-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VTR.6-PR-ELL-PA.20Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-PA.25Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

VIDEO SURVEILLANCE 105 30-Apr-24 04-Sep-24 04-Sep-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 30-Apr-24 04-Sep-24 04-Sep-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VTR.6-PR-ELL-VS.20
Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-VS.25
Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
18 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ACCESS CONTROL SYSTEM 105 30-Apr-24 04-Sep-24 04-Sep-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 30-Apr-24 04-Sep-24 04-Sep-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
VTR.6-PR-ELL-AC.20
Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-AC.25
Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 30-Apr-24 04-Sep-24 04-Sep-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 30-Apr-24 04-Sep-24 04-Sep-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VTR.6-PR-ELL-RB.20
Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-RB.25
Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

SCADA SYSTEM 105 30-Apr-24 04-Sep-24 04-Sep-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 30-Apr-24 04-Sep-24 04-Sep-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VTR.6-PR-ELL-SD.20
Issue Purchase Order 15 30-Apr-24 18-May-24 Issue Purchase Order

VTR.6-PR-ELL-SD.25
Material Delivery 90 18-May-24 04-Sep-24 Material Delivery

CONSTRUCTION 426 21-Jun-23 12-Nov-24 12-Nov-24, CONSTRUCTION


EXCAVATION WORKS 39 21-Jun-23 08-Aug-23 08-Aug-23, EXCAVATION WORKS
JAH-CON-VR01-EX.175Excavation 39 21-Jun-23 08-Aug-23 Excavation

SOIL IMPROVEMENT WORKS 10 10-Sep-23 21-Sep-23 21-Sep-23, SOIL IMPROVEMENT WORKS


JAH-CON-VR01-SI.195Soil Improvement 10 10-Sep-23 21-Sep-23 Soil Improvement

STRUCTURAL WORKS 226 23-Dec-23 19-Sep-24 19-Sep-24, STRUCTURAL WORKS


FOUNDATION 37 23-Dec-23 03-Feb-24 03-Feb-24, FOUNDATION
Part-1 30 23-Dec-23 27-Jan-24 27-Jan-24, Part-1
VTR-6-FDN-P1.150 Foundation Blinding concrete casting casting 1 23-Dec-23 23-Dec-23 Foundation Blinding concrete casting casting

VTR-6-FDN-P1.155 Foundation water proofing on blinding concrete 3 23-Dec-23 26-Dec-23 Foundation water proofing on blinding concrete

VTR-6-FDN-P1.160 Foundation Protection screed on water poofing 1 26-Dec-23 27-Dec-23 Foundation Protection screed on water poofing

VTR-6-FDN-P1.165 Foundation Curing for screed 2 27-Dec-23 30-Dec-23 Foundation Curing for screed

VTR-6-FDN-P1.170 Foundation Rebar installation 10 30-Dec-23 10-Jan-24 Foundation Rebar installation

VTR-6-FDN-P1.175 Foundation Formwork installation 8 10-Jan-24 20-Jan-24 Foundation Formwork installation

VTR-6-FDN-P1.180 Foundation Construction joint work 2 20-Jan-24 22-Jan-24 Foundation Construction joint work

VTR-6-FDN-P1.185 Foundation concrete casting 1 22-Jan-24 23-Jan-24 Foundation concrete casting

VTR-6-FDN-P1.190 Foundation concrete curing 1 23-Jan-24 24-Jan-24 Foundation concrete curing

VTR-6-FDN-P1.195 Foundation Formwork Removal 2 24-Jan-24 27-Jan-24 Foundation Formwork Removal

Part-2 30 30-Dec-23 03-Feb-24 03-Feb-24, Part-2


VTR-6-FDN-P2.150 Foundation Blinding concrete casting casting 1 30-Dec-23 31-Dec-23 Foundation Blinding concrete casting casting

VTR-6-FDN-P2.155 Foundation water proofing on blinding concrete 3 31-Dec-23 03-Jan-24 Foundation water proofing on blinding concrete

VTR-6-FDN-P2.160 Foundation Protection screed on water poofing 1 03-Jan-24 04-Jan-24 Foundation Protection screed on water poofing

VTR-6-FDN-P2.165 Foundation Curing for screed 2 04-Jan-24 07-Jan-24 Foundation Curing for screed

VTR-6-FDN-P2.170 Foundation Rebar installation 10 07-Jan-24 18-Jan-24 Foundation Rebar installation

VTR-6-FDN-P2.175 Foundation Formwork installation 8 18-Jan-24 27-Jan-24 Foundation Formwork installation

VTR-6-FDN-P2.180 Foundation Construction joint work 2 28-Jan-24 29-Jan-24 Foundation Construction joint work

VTR-6-FDN-P2.185 Foundation concrete casting 1 30-Jan-24 30-Jan-24 Foundation concrete casting

VTR-6-FDN-P2.190 Foundation concrete curing 1 31-Jan-24 31-Jan-24 Foundation concrete curing

VTR-6-FDN-P2.195 Foundation Formwork Removal 2 01-Feb-24 03-Feb-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 44 23-Jan-24 14-Mar-24 14-Mar-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 44 23-Jan-24 14-Mar-24 14-Mar-24, WALL CONCRETE CASTING STAGE-1
Part-1 37 23-Jan-24 06-Mar-24 06-Mar-24, Part-1
VTR-6-WL-S1-P1.135Room Walls Rebar Installation 12 30-Jan-24 13-Feb-24 Room Walls Rebar Installation

VTR-6-WL-S1-P1.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 13-Feb-24 15-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-6-WL-S1-P1.145Room Walls Formwork Installation 12 15-Feb-24 29-Feb-24 Room Walls Formwork Installation

VTR-6-WL-S1-P1.150Room Walls Concrete Casting 1 29-Feb-24 02-Mar-24 Room Walls Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
19 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-6-WL-S1-P1.155Room Walls Curing work 1 02-Mar-24 03-Mar-24 Room Walls Curing work

VTR-6-WL-S1-P1.160Room Walls Formwork Removel 3 03-Mar-24 06-Mar-24 Room Walls Formwork Removel

VTR-6-WL-S1-P1.165Room Walls Scafolding for rebar 6 23-Jan-24 30-Jan-24 Room Walls Scafolding for rebar

Part-2 37 01-Feb-24 14-Mar-24 14-Mar-24, Part-2


VTR-6-WL-S1-P2.135Room Walls Rebar Installation 12 07-Feb-24 21-Feb-24 Room Walls Rebar Installation

VTR-6-WL-S1-P2.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Feb-24 24-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-6-WL-S1-P2.145Room Walls Formwork Installation 12 24-Feb-24 09-Mar-24 Room Walls Formwork Installation

VTR-6-WL-S1-P2.150Room Walls Concrete Casting 1 09-Mar-24 10-Mar-24 Room Walls Concrete Casting

VTR-6-WL-S1-P2.155Room Walls Curing work 1 10-Mar-24 11-Mar-24 Room Walls Curing work

VTR-6-WL-S1-P2.160Room Walls Formwork Removel 3 11-Mar-24 14-Mar-24 Room Walls Formwork Removel

VTR-6-WL-S1-P2.165Room Walls Scafolding for rebar 6 01-Feb-24 07-Feb-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 41 06-Mar-24 27-Apr-24 27-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 41 06-Mar-24 27-Apr-24 27-Apr-24, Part-1
VTR-6-TS-P1.125 Room Top Slab Formwork Installation 12 06-Mar-24 20-Mar-24 Room Top Slab Formwork Installation

VTR-6-TS-P1.130 Room Top Slab Rebar Installation 12 20-Mar-24 03-Apr-24 Room Top Slab Rebar Installation

VTR-6-TS-P1.135 Room Top Slab Concrete Casting 1 03-Apr-24 04-Apr-24 Room Top Slab Concrete Casting

VTR-6-TS-P1.140 Room Top slab Curing work 12 04-Apr-24 22-Apr-24 Room Top slab Curing work

VTR-6-TS-P1.145 Room Top Slab Formwork Removel 4 22-Apr-24 27-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 60 22-Apr-24 06-Jul-24 06-Jul-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 29 22-Apr-24 25-May-24 25-May-24, WALL CONCRETE CASTING STAGE-1
Part-2 29 22-Apr-24 25-May-24 25-May-24, Part-2
VTR-6-WL-SG-1-P2.135
Room Walls Rebar Installation 10 29-Apr-24 09-May-24 Room Walls Rebar Installation

VTR-6-WL-SG-1-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 09-May-24 12-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-6-WL-SG-1-P2.145
Room Walls Formwork Installation 6 12-May-24 19-May-24 Room Walls Formwork Installation

VTR-6-WL-SG-1-P2.150
Room Walls Concrete Casting 1 19-May-24 20-May-24 Room Walls Concrete Casting

VTR-6-WL-SG-1-P2.155
Room Walls Curing work 1 20-May-24 21-May-24 Room Walls Curing work

VTR-6-WL-SG-1-P2.160
Room Walls Formwork Removel 3 21-May-24 25-May-24 Room Walls Formwork Removel

VTR-6-WL-SG-1-P2.165
Room Walls Scafolding for rebar 6 22-Apr-24 28-Apr-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-2 32 25-May-24 06-Jul-24 06-Jul-24, WALL CONCRETE CASTING STAGE-2
Part-2 32 25-May-24 06-Jul-24 06-Jul-24, Part-2
VTR-6-WL-SG-2-P2.135
Room Walls Rebar Installation 12 01-Jun-24 19-Jun-24 Room Walls Rebar Installation

VTR-6-WL-SG-2-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 19-Jun-24 22-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-6-WL-SG-2-P2.145
Room Walls Formwork Installation 6 22-Jun-24 29-Jun-24 Room Walls Formwork Installation

VTR-6-WL-SG-2-P2.150
Room Walls Concrete Casting 2 29-Jun-24 01-Jul-24 Room Walls Concrete Casting

VTR-6-WL-SG-2-P2.155
Room Walls Curing work 1 01-Jul-24 02-Jul-24 Room Walls Curing work

VTR-6-WL-SG-2-P2.160
Room Walls Formwork Removel 3 02-Jul-24 06-Jul-24 Room Walls Formwork Removel

VTR-6-WL-SG-2-P2.165
Room Walls Scafolding for rebar 6 25-May-24 01-Jun-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 30 06-Jul-24 10-Aug-24 10-Aug-24, SLAB ABOVE GROUND LEVEL
Part-2 30 06-Jul-24 10-Aug-24 10-Aug-24, Part-2
VTR-6-SLB-AG-P1.125
Room Top Slab Formwork Installation 8 06-Jul-24 15-Jul-24 Room Top Slab Formwork Installation

VTR-6-SLB-AG-P1.130
Room Top Slab Rebar Installation 5 15-Jul-24 21-Jul-24 Room Top Slab Rebar Installation

VTR-6-SLB-AG-P1.135
Room Top Slab Concrete Casting 1 21-Jul-24 22-Jul-24 Room Top Slab Concrete Casting

VTR-6-SLB-AG-P1.140
Room Top slab Curing work 12 22-Jul-24 05-Aug-24 Room Top slab Curing work

VTR-6-SLB-AG-P1.145
Room Top Slab Formwork Removel 4 05-Aug-24 10-Aug-24 Room Top Slab Formwork Removel

WATER PROOFING 65 06-Jul-24 19-Sep-24 19-Sep-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 21 06-Jul-24 30-Jul-24 30-Jul-24, WALL WATER PROOFING STAGE-1
VTR-6-WP-WL-S1.115Surface preparation work 6 06-Jul-24 13-Jul-24 Surface preparation work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
20 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-6-WP-WL-S1.120Applying of waterproofing material 10 13-Jul-24 24-Jul-24 Applying of waterproofing material

VTR-6-WP-WL-S1.125VR Back filling 5 24-Jul-24 30-Jul-24 VR Back filling

WALL WATER PROOFING STAGE-2 24 13-Jul-24 10-Aug-24 10-Aug-24, WALL WATER PROOFING STAGE-2
VTR-6-WP-WL-S2.115Surface preparation work 6 13-Jul-24 20-Jul-24 Surface preparation work

VTR-6-WP-WL-S2.120Applying of waterproofing material 10 20-Jul-24 31-Jul-24 Applying of waterproofing material

VTR-6-WP-WL-S2.125VR Back filling 5 04-Aug-24 10-Aug-24 VR Back filling

WALL WATER PROOFING STAGE-3 23 20-Jul-24 15-Aug-24 15-Aug-24, WALL WATER PROOFING STAGE-3
VTR-6-WP-WL-S3.115Surface preparation work 6 20-Jul-24 27-Jul-24 Surface preparation work

VTR-6-WP-WL-S3.120Applying of waterproofing material 10 27-Jul-24 07-Aug-24 Applying of waterproofing material

VTR-6-WP-WL-S3.125VR Back filling 5 10-Aug-24 15-Aug-24 VR Back filling

WALL WATER PROOFING STAGE-4 21 27-Jul-24 20-Aug-24 20-Aug-24, WALL WATER PROOFING STAGE-4
VTR-6-WP-WL-S4.115Surface preparation work 6 27-Jul-24 03-Aug-24 Surface preparation work

VTR-6-WP-WL-S4.120Applying of waterproofing material 10 03-Aug-24 14-Aug-24 Applying of waterproofing material

VTR-6-WP-WL-S4.125VR Back filling 5 14-Aug-24 20-Aug-24 VR Back filling

TOP SLAB WATER PROOFING 26 20-Aug-24 19-Sep-24 19-Sep-24, TOP SLAB WATER PROOFING
VTR-6-WP-SLB-S1.115
Surface preparation work 12 20-Aug-24 03-Sep-24 Surface preparation work

VTR-6-WP-SLB-S1.120
Applying of waterproofing material 13 03-Sep-24 18-Sep-24 Applying of waterproofing material

VTR-6-WP-SLB-S1.125
Leak Test 1 18-Sep-24 19-Sep-24 Leak Test

MECHANICAL ROOM MEP 81 10-Aug-24 12-Nov-24 12-Nov-24, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 55 10-Aug-24 14-Oct-24 14-Oct-24, ELECTRICAL WORK IN ROOM
POWER SYSTEM 53 10-Aug-24 12-Oct-24 12-Oct-24, POWER SYSTEM
EARTHING SYSTEM 25 10-Aug-24 07-Sep-24 07-Sep-24, EARTHING SYSTEM
VTR-6-EES-105 Earthing system soil resistivity test 6 10-Aug-24 17-Aug-24 Earthing system soil resistivity test

VTR-6-EES-115 Earthing system Copper rod/ earthing pit installation 8 17-Aug-24 25-Aug-24 Earthing system Copper rod/ earthing pit installation

VTR-6-EES-125 Earthing system Termination 6 26-Aug-24 01-Sep-24 Earthing system Termination

VTR-6-EES-135 Earthing system Initial Testing 5 01-Sep-24 07-Sep-24 Earthing system Initial Testing

LIGHTING SYSTEM 37 17-Aug-24 29-Sep-24 29-Sep-24, LIGHTING SYSTEM


VTR-6-ELI.105 Lighting system Conduit and boxes Installation 8 17-Aug-24 25-Aug-24 Lighting system Conduit and boxes Installation

VTR-6-ELI.115 Lighting system Cable Pulling 8 26-Aug-24 03-Sep-24 Lighting system Cable Pulling

VTR-6-ELI.125 Lighting system Installations 8 03-Sep-24 12-Sep-24 Lighting system Installations

VTR-6-ELI.135 Lighting system Termination 8 12-Sep-24 22-Sep-24 Lighting system Termination

VTR-6-ELI.145 Lighting system Initial Testing 5 22-Sep-24 29-Sep-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 17-Aug-24 12-Oct-24 12-Oct-24, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-6-ECT.105 Cable Tray Installation 10 17-Aug-24 27-Aug-24 Cable Tray Installation

VTR-6-ECT.115 Cable Tray Inspection 10 28-Aug-24 08-Sep-24 Cable Tray Inspection

VTR-6-ECT.125 LV Cable pulling 10 08-Sep-24 19-Sep-24 LV Cable pulling

VTR-6-ECT.135 LV Cable Termination 10 19-Sep-24 02-Oct-24 LV Cable Termination

VTR-6-ECT.145 LV Cable Initial Testing 8 02-Oct-24 12-Oct-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 17-Aug-24 01-Oct-24 01-Oct-24, SMALL POWER SYSTEM


VTR-6-ESP.105 Small Power Conduit and boxes Installation 12 17-Aug-24 29-Aug-24 Small Power Conduit and boxes Installation

VTR-6-ESP.115 Small Power Cable Pulling 10 31-Aug-24 10-Sep-24 Small Power Cable Pulling

VTR-6-ESP.125 Small Power Installations 6 10-Sep-24 17-Sep-24 Small Power Installations

VTR-6-ESP.135 Small Power Termination 6 17-Sep-24 25-Sep-24 Small Power Termination

VTR-6-ESP.145 Small Power Initial Testing 5 25-Sep-24 01-Oct-24 Small Power Initial Testing

POWER DISTRIBUTION 39 17-Aug-24 02-Oct-24 02-Oct-24, POWER DISTRIBUTION


GENERATOR 39 17-Aug-24 02-Oct-24 02-Oct-24, GENERATOR
VTR-6-EPD.105 Generator Cable Tray Installation 7 17-Aug-24 24-Aug-24 Generator Cable Tray Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
21 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-6-EPD.115 Generator Cable Pulling 7 25-Aug-24 01-Sep-24 Generator Cable Pulling

VTR-6-EPD.125 Generator Cell Pannel Installation 7 01-Sep-24 09-Sep-24 Generator Cell Pannel Installation

VTR-6-EPD.135 Generator Installation 7 09-Sep-24 17-Sep-24 Generator Installation

VTR-6-EPD.145 Generator Pannel / Cable Termination 7 17-Sep-24 26-Sep-24 Generator Pannel / Cable Termination

VTR-6-EPD.155 Generator Pannel / Cable initial Testing 5 26-Sep-24 02-Oct-24 Generator Pannel / Cable initial Testing

UPS 28 25-Aug-24 28-Sep-24 28-Sep-24, UPS


VTR-6-EPD.165 UPS Cable Tray Installation 5 25-Aug-24 29-Aug-24 UPS Cable Tray Installation

VTR-6-EPD.175 UPS Cable Pulling 5 29-Aug-24 04-Sep-24 UPS Cable Pulling

VTR-6-EPD.185 UPS Pannel Installation 5 04-Sep-24 10-Sep-24 UPS Pannel Installation

VTR-6-EPD.195 UPS Installation 5 10-Sep-24 16-Sep-24 UPS Installation

VTR-6-EPD.205 UPS Pannel / Cable Termination 5 16-Sep-24 22-Sep-24 UPS Pannel / Cable Termination

VTR-6-EPD.215 UPS Pannel / Cable initial Testing 4 22-Sep-24 28-Sep-24 UPS Pannel / Cable initial Testing

MDB 33 25-Aug-24 02-Oct-24 02-Oct-24, MDB


VTR-6-EPD.225 MDB Cable Tray Installation 7 25-Aug-24 01-Sep-24 MDB Cable Tray Installation

VTR-6-EPD.235 MDB Cable Pulling 7 01-Sep-24 09-Sep-24 MDB Cable Pulling

VTR-6-EPD.245 MDB Pannel Installation 7 09-Sep-24 17-Sep-24 MDB Pannel Installation

VTR-6-EPD.255 MDB Pannel / Cable Termination 7 17-Sep-24 26-Sep-24 MDB Pannel / Cable Termination

VTR-6-EPD.265 MDB Pannel / Cable initial Testing 5 26-Sep-24 02-Oct-24 MDB Pannel / Cable initial Testing

MCC 33 25-Aug-24 02-Oct-24 02-Oct-24, MCC


VTR-6-EPD.325 MCC Cable Tray Installation 7 25-Aug-24 01-Sep-24 MCC Cable Tray Installation

VTR-6-EPD.335 MCC Cable Pulling 7 01-Sep-24 09-Sep-24 MCC Cable Pulling

VTR-6-EPD.345 MCC Pannel Installation 7 09-Sep-24 17-Sep-24 MCC Pannel Installation

VTR-6-EPD.355 MCC Pannel / Cable Termination 7 17-Sep-24 26-Sep-24 MCC Pannel / Cable Termination

VTR-6-EPD.365 MCC Pannel / Cable initial Testing 5 26-Sep-24 02-Oct-24 MCC Pannel / Cable initial Testing

SMSB 24 25-Aug-24 21-Sep-24 21-Sep-24, SMSB


VTR-6-EPD.275 SMSB Cable Tray Installation 5 25-Aug-24 29-Aug-24 SMSB Cable Tray Installation

VTR-6-EPD.285 SMSB Cable Pulling 5 29-Aug-24 04-Sep-24 SMSB Cable Pulling

VTR-6-EPD.295 SMSB Pannel Installation 5 04-Sep-24 10-Sep-24 SMSB Pannel Installation

VTR-6-EPD.305 SMSB Pannel / Cable Termination 5 10-Sep-24 16-Sep-24 SMSB Pannel / Cable Termination

VTR-6-EPD.315 SMSB Pannel / Cable initial Testing 4 16-Sep-24 21-Sep-24 SMSB Pannel / Cable initial Testing

DB 24 25-Aug-24 21-Sep-24 21-Sep-24, DB


VTR-6-EPD.375 DB Cable Tray Installation 5 25-Aug-24 29-Aug-24 DB Cable Tray Installation

VTR-6-EPD.385 DB Cable Pulling 5 29-Aug-24 04-Sep-24 DB Cable Pulling

VTR-6-EPD.395 DB Pannel Installation 5 04-Sep-24 10-Sep-24 DB Pannel Installation

VTR-6-EPD.405 DB Pannel / Cable Termination 5 10-Sep-24 16-Sep-24 DB Pannel / Cable Termination

VTR-6-EPD.415 DB Pannel / Cable initial Testing 4 16-Sep-24 21-Sep-24 DB Pannel / Cable initial Testing

ISOLATOR 24 25-Aug-24 21-Sep-24 21-Sep-24, ISOLATOR


VTR-6-EPD.425 Isolators Cable Tray Installation 5 25-Aug-24 29-Aug-24 Isolators Cable Tray Installation

VTR-6-EPD.435 Isolators Cable Pulling 5 29-Aug-24 04-Sep-24 Isolators Cable Pulling

VTR-6-EPD.445 Isolators Pannel Installation 5 04-Sep-24 10-Sep-24 Isolators Pannel Installation

VTR-6-EPD.455 Isolators Pannel / Cable Termination 5 10-Sep-24 16-Sep-24 Isolators Pannel / Cable Termination

VTR-6-EPD.465 Isolators Pannel / Cable initial Testing 4 16-Sep-24 21-Sep-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 25-Aug-24 21-Sep-24 21-Sep-24, LCP/ ELCP


VTR-6-EPD.475 LCP/ELCP Cable Tray Installation 5 25-Aug-24 29-Aug-24 LCP/ELCP Cable Tray Installation

VTR-6-EPD.485 LCP/ELCP Cable Pulling 5 29-Aug-24 04-Sep-24 LCP/ELCP Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
22 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-6-EPD.495 LCP/ELCP Pannel Installation 5 04-Sep-24 10-Sep-24 LCP/ELCP Pannel Installation

VTR-6-EPD.505 LCP/ELCP Pannel / Cable Termination 5 10-Sep-24 16-Sep-24 LCP/ELCP Pannel / Cable Termination

VTR-6-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 16-Sep-24 21-Sep-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 42 26-Aug-24 14-Oct-24 14-Oct-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 26-Aug-24 14-Oct-24 14-Oct-24, FIRE ALARM SYSTEM
VTR-6-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 Fire Alarm Conduit /Cable Tray Installation

VTR-6-ELFA.115 Fire Alarm Cable Pulling 9 04-Sep-24 15-Sep-24 Fire Alarm Cable Pulling

VTR-6-ELFA.125 Fire Alarm Devices Installation 9 15-Sep-24 26-Sep-24 Fire Alarm Devices Installation

VTR-6-ELFA.135 Fire Alarm Devices and Cable Termination 9 26-Sep-24 07-Oct-24 Fire Alarm Devices and Cable Termination

VTR-6-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 26-Aug-24 14-Oct-24 14-Oct-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-6-ELVS.105 ICT System Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 ICT System Conduit /Cable Tray Installation

VTR-6-ELVS.115 ICT System Cable Pulling 9 04-Sep-24 15-Sep-24 ICT System Cable Pulling

VTR-6-ELVS.125 ICT System Devices Installation 9 15-Sep-24 26-Sep-24 ICT System Devices Installation

VTR-6-ELVS.135 ICT System Devices and Cable Termination 9 26-Sep-24 07-Oct-24 ICT System Devices and Cable Termination

VTR-6-ELVS.145 ICT System Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 26-Aug-24 14-Oct-24 14-Oct-24, ACCESS CONTROL SYSTEM


VTR-6-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 Access Control System Conduit /Cable Tray Installation

VTR-6-ELAC.115 Access Control System Cable Pulling 9 04-Sep-24 15-Sep-24 Access Control System Cable Pulling

VTR-6-ELAC.125 Access Control System Devices Installation 9 15-Sep-24 26-Sep-24 Access Control System Devices Installation

VTR-6-ELAC.135 Access Control System Devices and Cable Termination 9 26-Sep-24 07-Oct-24 Access Control System Devices and Cable Termination

VTR-6-ELAC.145 Access Control System Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 26-Aug-24 14-Oct-24 14-Oct-24, PUBLIC ADDRESS SYSTEM


VTR-6-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 Public Address System Conduit /Cable Tray Installation

VTR-6-ELPA.115 Public Address System Cable Pulling 9 04-Sep-24 15-Sep-24 Public Address System Cable Pulling

VTR-6-ELPA.125 Public Address System Devices Installation 9 15-Sep-24 26-Sep-24 Public Address System Devices Installation

VTR-6-ELPA.135 Public Address System Devices and Cable Termination 9 26-Sep-24 07-Oct-24 Public Address System Devices and Cable Termination

VTR-6-ELPA.145 Public Address System Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 26-Aug-24 14-Oct-24 14-Oct-24, SCADA SYSTEM


VTR-6-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 SCADA System Conduit /Cable Tray Installation

VTR-6-ELSC.115 SCADA System Cable Pulling 9 04-Sep-24 15-Sep-24 SCADA System Cable Pulling

VTR-6-ELSC.125 SCADA System Devices Installation 9 15-Sep-24 26-Sep-24 SCADA System Devices Installation

VTR-6-ELSC.135 SCADA System Devices and Cable Termination 9 26-Sep-24 07-Oct-24 SCADA System Devices and Cable Termination

VTR-6-ELSC.145 SCADA System Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 26-Aug-24 14-Oct-24 14-Oct-24, RADIO RE- BROADCOASTING/ TETRA
VTR-6-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 26-Aug-24 04-Sep-24 Radio/TETRA System Conduit /Cable Tray Installation

VTR-6-ELRD.115 Radio/TETRA System Cable Pulling 9 04-Sep-24 15-Sep-24 Radio/TETRA System Cable Pulling

VTR-6-ELRD.125 Radio/TETRA System Devices Installation 9 15-Sep-24 26-Sep-24 Radio/TETRA System Devices Installation

VTR-6-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 26-Sep-24 07-Oct-24 Radio/TETRA System Devices and Cable Termination

VTR-6-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 07-Oct-24 14-Oct-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 68 25-Aug-24 12-Nov-24 12-Nov-24, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 25-Aug-24 21-Sep-24 21-Sep-24, FIRE FIGHTING
VTR-6-MFF.105 Fire Fighting system Pipe and accessories installation 21 25-Aug-24 17-Sep-24 Fire Fighting system Pipe and accessories installation

VTR-6-MFF.115 Fire Fighting system deluge valve installation 16 31-Aug-24 17-Sep-24 Fire Fighting system deluge valve installation

VTR-6-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 11-Sep-24 17-Sep-24 Fire Fighting system fire hose cabinet/extingusher installation

VTR-6-MFF.140 Fire Fighting system initial testing 3 18-Sep-24 21-Sep-24 Fire Fighting system initial testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
23 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-6-MFF.145 Fire Fighting clean agent system 2 16-Sep-24 17-Sep-24 Fire Fighting clean agent system

HVAC 47 18-Sep-24 12-Nov-24 12-Nov-24, HVAC


VTR-6-MHV.115 Air conditioning system installation 12 22-Oct-24 04-Nov-24 Air conditioning system installation

VTR-6-MHV.120 Fan installation 15 19-Oct-24 04-Nov-24 Fan installation

VTR-6-MHV.125 Duct and accessories installation 28 18-Sep-24 21-Oct-24 Duct and accessories installation

VTR-6-MHV.135 HVAC inital testing 7 05-Nov-24 12-Nov-24 HVAC inital testing

PLUMBING 8 22-Oct-24 30-Oct-24 30-Oct-24, PLUMBING


VTR-6-MPL.105 Plumbing drainage system installation 6 22-Oct-24 28-Oct-24 Plumbing drainage system installation

VTR-6-MPL.115 Plumbing drainage system initial testing 2 29-Oct-24 30-Oct-24 Plumbing drainage system initial testing

DRY UTILITIES 25 25-Aug-24 22-Sep-24 22-Sep-24, DRY UTILITIES


POWER 25 25-Aug-24 22-Sep-24 22-Sep-24, POWER
POWER LV 16 25-Aug-24 11-Sep-24 11-Sep-24, POWER LV
DU-P-PLV.1 Installation of support 1 25-Aug-24 25-Aug-24 Installation of support

DU-P-PLV.15 Installation of horizontal busbar 2 25-Aug-24 27-Aug-24 Installation of horizontal busbar

DU-P-PLV.25 Installation of vertical busbar 2 27-Aug-24 28-Aug-24 Installation of vertical busbar

DU-P-PLV.35 Installation of left/right elbow 2 29-Aug-24 31-Aug-24 Installation of left/right elbow

DU-P-PLV.45 Installation of right horizintal offset 2 31-Aug-24 02-Sep-24 Installation of right horizintal offset

DU-P-PLV.55 Instalaltion of upward vertical offset 3 02-Sep-24 05-Sep-24 Instalaltion of upward vertical offset

DU-P-PLV.65 Installation of downward vertical offset 3 05-Sep-24 09-Sep-24 Installation of downward vertical offset

DU-P-PLV.75 Installation of transformer and panel connection 2 09-Sep-24 11-Sep-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 25-Aug-24 15-Sep-24 15-Sep-24, MEDIUM VOLTAGE


DU-P-PMV.1 Installation of cable try, arm, racks and ladder 6 25-Aug-24 02-Sep-24 Installation of cable try, arm, racks and ladder

DU-P-PMV.15 Installation of MV Cable 4 02-Sep-24 07-Sep-24 Installation of MV Cable

DU-P-PMV.25 Installation of cable cleats 2 07-Sep-24 08-Sep-24 Installation of cable cleats

DU-P-PMV.35 Installation of gland 1 08-Sep-24 09-Sep-24 Installation of gland

DU-P-PMV.45 splicing/termination of MV cable 2 09-Sep-24 11-Sep-24 splicing/termination of MV cable

DU-P-PMV.55 Testing and Pre-commissioning of cable 2 11-Sep-24 12-Sep-24 Testing and Pre-commissioning of cable

DU-P-PMV.65 Energezation 2 12-Sep-24 15-Sep-24 Energezation

TRANSFORMER 16 02-Sep-24 21-Sep-24 21-Sep-24, TRANSFORMER


DU-P-PT.1 Installation of Transformer unit 2 02-Sep-24 03-Sep-24 Installation of Transformer unit

DU-P-PT.15 Testing and Pre-Commissioning of unit 1 03-Sep-24 04-Sep-24 Testing and Pre-Commissioning of unit

DU-P-PT.25 Termination and Splicing of MV Cable 3 04-Sep-24 08-Sep-24 Termination and Splicing of MV Cable

DU-P-PT.35 Termination and Splicing of LV Cable/bus way 3 08-Sep-24 11-Sep-24 Termination and Splicing of LV Cable/bus way

DU-P-PT.45 Installation and connection of I/O system 2 12-Sep-24 15-Sep-24 Installation and connection of I/O system

DU-P-PT.55 Installation of Grounding and Protection System 2 15-Sep-24 17-Sep-24 Installation of Grounding and Protection System

DU-P-PT.65 Testing and Commissioning of MV System 1 17-Sep-24 18-Sep-24 Testing and Commissioning of MV System

DU-P-PT.75 Testing and Commissioning of LV System 1 18-Sep-24 19-Sep-24 Testing and Commissioning of LV System

DU-P-PT.85 Energezation 1 19-Sep-24 21-Sep-24 Energezation

RMU 16 03-Sep-24 22-Sep-24 22-Sep-24, RMU


DU-P-PRMU.1 Installation RMU unit 2 03-Sep-24 07-Sep-24 Installation RMU unit

DU-P-PRMU.15 Testing and Pre-Commissioning of unit 2 07-Sep-24 08-Sep-24 Testing and Pre-Commissioning of unit

DU-P-PRMU.25 Termination and Splicing of Ring-MV Cable 4 08-Sep-24 12-Sep-24 Termination and Splicing of Ring-MV Cable

DU-P-PRMU.35 Termination and Splicing of T-MV Cable 4 12-Sep-24 17-Sep-24 Termination and Splicing of T-MV Cable

DU-P-PRMU.45 Installation of Grounding and Protection System 2 17-Sep-24 21-Sep-24 Installation of Grounding and Protection System

DU-P-PRMU.55 Testing and Commissioning of MV System 1 21-Sep-24 21-Sep-24 Testing and Commissioning of MV System

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
24 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-PRMU.65 Energezation 1 22-Sep-24 22-Sep-24 Energezation

VECHICULAR ROOM 10 (IN ZONE 05) 717 24-May-23 30-Sep-25 30-Sep-25, VECHICULAR ROOM 10 (IN ZONE 05)
ENGINEERING 119 24-May-23 14-Oct-23 14-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 119 24-May-23 14-Oct-23 14-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 115 24-May-23 09-Oct-23 09-Oct-23, EARTH WORKS
JAH-ENG-VR10-SI.892Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

JAH-ENG-VR10-SI.893Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

JAH-ENG-VR10-SI.895Soil Improvement Design Preparation & Submission 14 06-Sep-23 21-Sep-23 Soil Improvement Design Preparation & Submission

JAH-ENG-VR10-SI.900Soil Improvement Design Review & Approval 14 21-Sep-23 09-Oct-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VTR.10-ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VTR.10-ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VTR.10-ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VTR.10-ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VTR.10-ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VTR.10-ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VTR.10-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VTR.10-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VTR.10-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VTR.10-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VTR.10-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VTR.10-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VTR.10-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VTR.10-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VTR.10-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VTR.10-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VTR.10-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VTR.10-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VTR.10-ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VTR.10-ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


VTR.10-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

VTR.10-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM


VTR.10-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

VTR.10-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VTR.10-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
25 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VTR.10-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VTR.10-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VTR.10-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VTR.10-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VTR.10-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VTR.10-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VTR.10-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 119 24-May-23 14-Oct-23 14-Oct-23, DRY UTILITIES


POWER 119 24-May-23 14-Oct-23 14-Oct-23, POWER
POWER LV 48 24-May-23 22-Jul-23 22-Jul-23, POWER LV
SD-DU-P-PLV.15 Review and approval power system shopdrawings 11 24-May-23 06-Jun-23 Review and approval power system shopdrawings

SD-DU-P-PLV.5 Prepare and submit power system shopdrawings 20 25-Jun-23 22-Jul-23 Prepare and submit power system shopdrawings

MEDIUM VOLTAGE 31 22-Jul-23 27-Aug-23 27-Aug-23, MEDIUM VOLTAGE


SD-DU-P-PMV.15 Review and approval medium voltage shopdrawings 11 14-Aug-23 27-Aug-23 Review and approval medium voltage shopdrawings

SD-DU-P-PMV.5 Prepare and submit medium voltage shopdrawings 20 22-Jul-23 14-Aug-23 Prepare and submit medium voltage shopdrawings

TRANSFORMER 31 14-Aug-23 19-Sep-23 19-Sep-23, TRANSFORMER


SD-DU-P-PT.100 Prepare and submit transformer shopdrawings 20 14-Aug-23 06-Sep-23 Prepare and submit transformer shopdrawings

SD-DU-P-PT.105 Review and approval transformer shopdrawings 11 06-Sep-23 19-Sep-23 Review and approval transformer shopdrawings

RMU 31 06-Sep-23 14-Oct-23 14-Oct-23, RMU


SD-DU-P-PRMU.100Prepare and submit RMU shopdrawings 20 06-Sep-23 01-Oct-23 Prepare and submit RMU shopdrawings

SD-DU-P-PRMU.105Review and approval RMU shopdrawings 11 01-Oct-23 14-Oct-23 Review and approval RMU shopdrawings

PROCUREMENT 300 24-Aug-24 18-Aug-25 18-Aug-25, PROCUREMENT


CIVIL/STRUCTURAL 16 24-Aug-24 10-Sep-24 10-Sep-24, CIVIL/STRUCTURAL
VTR.10-PRO-CV.110 Issue Purchase Order 6 24-Aug-24 29-Aug-24 Issue Purchase Order

VTR.10-PRO-CV.115 Material Delivery 10 31-Aug-24 10-Sep-24 Material Delivery

MECHANICAL 133 08-Mar-25 18-Aug-25 18-Aug-25, MECHANICAL


FIRE FIGHTING SYSTEM 105 08-Mar-25 16-Jul-25 16-Jul-25, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 08-Mar-25 16-Jul-25 16-Jul-25, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VTR.10-PR-MC-FF.110Issue Purchase Order 15 08-Mar-25 25-Mar-25 Issue Purchase Order

VTR.10-PR-MC-FF.115Material Delivery 90 25-Mar-25 16-Jul-25 Material Delivery

VENTILATION SYSTEM 105 14-Apr-25 18-Aug-25 18-Aug-25, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 14-Apr-25 18-Aug-25 18-Aug-25, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VTR.10-PR-MC-DS.110
Issue Purchase Order 15 14-Apr-25 01-May-25 Issue Purchase Order

VTR.10-PR-MC-DS.115
Material Delivery 90 01-May-25 18-Aug-25 Material Delivery

AIR CONDITIONING WORKS 105 14-Apr-25 18-Aug-25 18-Aug-25, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 14-Apr-25 18-Aug-25 18-Aug-25, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VTR.10-PR-MC-AC.110
Issue Purchase Order 15 14-Apr-25 01-May-25 Issue Purchase Order

VTR.10-PR-MC-AC.115
Material Delivery 90 01-May-25 18-Aug-25 Material Delivery

PLUMBING SYSTEM 105 06-Apr-25 10-Aug-25 10-Aug-25, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 06-Apr-25 10-Aug-25 10-Aug-25, PUMPS,PIPES,FITTINGS,VALVES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
26 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR.10-PR-MC-PI.110Issue Purchase Order 15 06-Apr-25 23-Apr-25 Issue Purchase Order

VTR.10-PR-MC-PI.115Material Delivery 90 23-Apr-25 10-Aug-25 Material Delivery

ELECTRICAL 141 20-Feb-25 11-Aug-25 11-Aug-25, ELECTRICAL


CABLE TRAY 105 09-Mar-25 17-Jul-25 17-Jul-25, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 09-Mar-25 17-Jul-25 17-Jul-25, CABLE TRAY AND ACCESSORIES,PVC DUCT
VTR.10-PR-EL-CT.110Issue Purchase Order 15 09-Mar-25 26-Mar-25 Issue Purchase Order

VTR.10-PR-EL-CT.115Material Delivery 90 26-Mar-25 17-Jul-25 Material Delivery

POWER CABLES 105 09-Mar-25 17-Jul-25 17-Jul-25, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 09-Mar-25 17-Jul-25 17-Jul-25, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VTR.10-PR-EL-PC.110Issue Purchase Order 15 09-Mar-25 26-Mar-25 Issue Purchase Order

VTR.10-PR-EL-PC.115Material Delivery 90 26-Mar-25 17-Jul-25 Material Delivery

LIGHTING SYSTEM 105 27-Feb-25 08-Jul-25 08-Jul-25, LIGHTING SYSTEM


CONDUIT,LIGHT 105 27-Feb-25 08-Jul-25 08-Jul-25, CONDUIT,LIGHT
VTR.10-PR-EL-LS.110Issue Purchase Order 15 27-Feb-25 17-Mar-25 Issue Purchase Order

VTR.10-PR-EL-LS.115Material Delivery 90 17-Mar-25 08-Jul-25 Material Delivery

ELECTRICAL INSTALLATIONS 105 27-Feb-25 08-Jul-25 08-Jul-25, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 27-Feb-25 08-Jul-25 08-Jul-25, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORM
VTR.10-PR-EL-EI.110Issue Purchase Order 15 27-Feb-25 17-Mar-25 Issue Purchase Order

VTR.10-PR-EL-EI.115Material Delivery 90 17-Mar-25 08-Jul-25 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 20-Feb-25 01-Jul-25 01-Jul-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 20-Feb-25 01-Jul-25 01-Jul-25, LIGHTNING PROTECTION SYSTEM
VTR.10-PR-EL-LP.110Issue Purchase Order 15 20-Feb-25 10-Mar-25 Issue Purchase Order

VTR.10-PR-EL-LP.115Material Delivery 90 10-Mar-25 01-Jul-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 20-Feb-25 01-Jul-25 01-Jul-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 20-Feb-25 01-Jul-25 01-Jul-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VTR.10-PR-EL-ES.110Issue Purchase Order 15 20-Feb-25 10-Mar-25 Issue Purchase Order

VTR.10-PR-EL-ES.115Material Delivery 90 10-Mar-25 01-Jul-25 Material Delivery

LOW CURRENT 105 07-Apr-25 11-Aug-25 11-Aug-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 07-Apr-25 11-Aug-25 11-Aug-25, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 07-Apr-25 11-Aug-25 11-Aug-25, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C
VTR.10-PR-ELL-FA.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-FA.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 07-Apr-25 11-Aug-25 11-Aug-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 07-Apr-25 11-Aug-25 11-Aug-25, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE
VTR.10-PR-ELL-PH.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-PH.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 07-Apr-25 11-Aug-25 11-Aug-25, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 07-Apr-25 11-Aug-25 11-Aug-25, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VTR.10-PR-ELL-PA.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-PA.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

VIDEO SURVEILLANCE 105 07-Apr-25 11-Aug-25 11-Aug-25, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 07-Apr-25 11-Aug-25 11-Aug-25, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VTR.10-PR-ELL-VS.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-VS.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

ACCESS CONTROL SYSTEM 105 07-Apr-25 11-Aug-25 11-Aug-25, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 07-Apr-25 11-Aug-25 11-Aug-25, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCE
VTR.10-PR-ELL-AC.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-AC.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 07-Apr-25 11-Aug-25 11-Aug-25, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 07-Apr-25 11-Aug-25 11-Aug-25, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VTR.10-PR-ELL-RB.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
27 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR.10-PR-ELL-RB.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

SCADA SYSTEM 105 07-Apr-25 11-Aug-25 11-Aug-25, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 07-Apr-25 11-Aug-25 11-Aug-25, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VTR.10-PR-ELL-SD.20
Issue Purchase Order 15 07-Apr-25 24-Apr-25 Issue Purchase Order

VTR.10-PR-ELL-SD.25
Material Delivery 90 24-Apr-25 11-Aug-25 Material Delivery

CONSTRUCTION 693 21-Jun-23 30-Sep-25 30-Sep-25, CONSTRUCTION


EXCAVATION WORKS 63 21-Jun-23 05-Sep-23 05-Sep-23, EXCAVATION WORKS
JAH-CON-VR01-EX.180Excavation 63 21-Jun-23 05-Sep-23 Excavation

SOIL IMPROVEMENT WORKS 40 09-Oct-23 25-Nov-23 25-Nov-23, SOIL IMPROVEMENT WORKS


JAH-CON-VR01-SI.200Soil Improvement 40 09-Oct-23 25-Nov-23 Soil Improvement

STRUCTURAL WORKS 304 11-Sep-24 10-Sep-25 10-Sep-25, STRUCTURAL WORKS


FOUNDATION 59 11-Sep-24 20-Nov-24 20-Nov-24, FOUNDATION
Part-1 30 11-Sep-24 17-Oct-24 17-Oct-24, Part-1
VTR-10-FDN-P1.150 Foundation Blinding concrete casting casting 1 11-Sep-24 11-Sep-24 Foundation Blinding concrete casting casting

VTR-10-FDN-P1.155 Foundation water proofing on blinding concrete 3 11-Sep-24 15-Sep-24 Foundation water proofing on blinding concrete

VTR-10-FDN-P1.160 Foundation Protection screed on water poofing 1 15-Sep-24 16-Sep-24 Foundation Protection screed on water poofing

VTR-10-FDN-P1.165 Foundation Curing for screed 2 16-Sep-24 18-Sep-24 Foundation Curing for screed

VTR-10-FDN-P1.170 Foundation Rebar installation 10 18-Sep-24 01-Oct-24 Foundation Rebar installation

VTR-10-FDN-P1.175 Foundation Formwork installation 8 01-Oct-24 10-Oct-24 Foundation Formwork installation

VTR-10-FDN-P1.180 Foundation Construction joint work 2 10-Oct-24 13-Oct-24 Foundation Construction joint work

VTR-10-FDN-P1.185 Foundation concrete casting 1 13-Oct-24 14-Oct-24 Foundation concrete casting

VTR-10-FDN-P1.190 Foundation concrete curing 1 14-Oct-24 15-Oct-24 Foundation concrete curing

VTR-10-FDN-P1.195 Foundation Formwork Removal 2 15-Oct-24 17-Oct-24 Foundation Formwork Removal

Part-2 39 18-Sep-24 04-Nov-24 04-Nov-24, Part-2


VTR-10-FDN-P2.150 Foundation Blinding concrete casting casting 1 18-Sep-24 19-Sep-24 Foundation Blinding concrete casting casting

VTR-10-FDN-P2.155 Foundation water proofing on blinding concrete 3 19-Sep-24 24-Sep-24 Foundation water proofing on blinding concrete

VTR-10-FDN-P2.160 Foundation Protection screed on water poofing 1 24-Sep-24 25-Sep-24 Foundation Protection screed on water poofing

VTR-10-FDN-P2.165 Foundation Curing for screed 2 25-Sep-24 28-Sep-24 Foundation Curing for screed

VTR-10-FDN-P2.170 Foundation Rebar installation 10 28-Sep-24 09-Oct-24 Foundation Rebar installation

VTR-10-FDN-P2.175 Foundation Formwork installation 8 17-Oct-24 27-Oct-24 Foundation Formwork installation

VTR-10-FDN-P2.180 Foundation Construction joint work 2 27-Oct-24 29-Oct-24 Foundation Construction joint work

VTR-10-FDN-P2.185 Foundation concrete casting 2 29-Oct-24 31-Oct-24 Foundation concrete casting

VTR-10-FDN-P2.190 Foundation concrete curing 1 31-Oct-24 02-Nov-24 Foundation concrete curing

VTR-10-FDN-P2.195 Foundation Formwork Removal 2 02-Nov-24 04-Nov-24 Foundation Formwork Removal

Part-3 46 28-Sep-24 20-Nov-24 20-Nov-24, Part-3


VTR-10-FDN-P3.150 Foundation Blinding concrete casting casting 1 28-Sep-24 29-Sep-24 Foundation Blinding concrete casting casting

VTR-10-FDN-P3.155 Foundation water proofing on blinding concrete 3 29-Sep-24 01-Oct-24 Foundation water proofing on blinding concrete

VTR-10-FDN-P3.160 Foundation Protection screed on water poofing 1 02-Oct-24 02-Oct-24 Foundation Protection screed on water poofing

VTR-10-FDN-P3.165 Foundation Curing for screed 2 02-Oct-24 05-Oct-24 Foundation Curing for screed

VTR-10-FDN-P3.170 Foundation Rebar installation 10 05-Oct-24 16-Oct-24 Foundation Rebar installation

VTR-10-FDN-P3.175 Foundation Formwork installation 8 04-Nov-24 13-Nov-24 Foundation Formwork installation

VTR-10-FDN-P3.180 Foundation Construction joint work 2 13-Nov-24 16-Nov-24 Foundation Construction joint work

VTR-10-FDN-P3.185 Foundation concrete casting 1 16-Nov-24 17-Nov-24 Foundation concrete casting

VTR-10-FDN-P3.190 Foundation concrete curing 1 17-Nov-24 18-Nov-24 Foundation concrete curing

VTR-10-FDN-P3.195 Foundation Formwork Removal 2 18-Nov-24 20-Nov-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 67 14-Oct-24 30-Dec-24 30-Dec-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 67 14-Oct-24 30-Dec-24 30-Dec-24, WALL CONCRETE CASTING STAGE-1

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
28 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Part-1 49 14-Oct-24 10-Dec-24 10-Dec-24, Part-1
VTR-10-WL-S1-P1.134
Room Walls Scafolding for rebar 6 14-Oct-24 21-Oct-24 Room Walls Scafolding for rebar

VTR-10-WL-S1-P1.135
Room Walls Rebar Installation 12 21-Oct-24 04-Nov-24 Room Walls Rebar Installation

VTR-10-WL-S1-P1.145
Room Walls Formwork Installation 12 20-Nov-24 04-Dec-24 Room Walls Formwork Installation

VTR-10-WL-S1-P1.150
Room Walls Concrete Casting 1 04-Dec-24 05-Dec-24 Room Walls Concrete Casting

VTR-10-WL-S1-P1.155
Room Walls Curing work 1 05-Dec-24 07-Dec-24 Room Walls Curing work

VTR-10-WL-S1-P1.160
Room Walls Formwork Removel 3 07-Dec-24 10-Dec-24 Room Walls Formwork Removel

Part-2 35 02-Nov-24 11-Dec-24 11-Dec-24, Part-2


VTR-10-WL-S1-P2.134
Room Walls Scafolding for rebar 6 02-Nov-24 09-Nov-24 Room Walls Scafolding for rebar

VTR-10-WL-S1-P2.135
Room Walls Rebar Installation 12 09-Nov-24 21-Nov-24 Room Walls Rebar Installation

VTR-10-WL-S1-P2.145
Room Walls Formwork Installation 12 23-Nov-24 05-Dec-24 Room Walls Formwork Installation

VTR-10-WL-S1-P2.150
Room Walls Concrete Casting 1 07-Dec-24 07-Dec-24 Room Walls Concrete Casting

VTR-10-WL-S1-P2.155
Room Walls Curing work 1 08-Dec-24 08-Dec-24 Room Walls Curing work

VTR-10-WL-S1-P2.160
Room Walls Formwork Removel 3 09-Dec-24 11-Dec-24 Room Walls Formwork Removel

Part-3 37 18-Nov-24 30-Dec-24 30-Dec-24, Part-3


VTR-10-WL-S1-P3.134
Room Walls Scafolding for rebar 6 18-Nov-24 24-Nov-24 Room Walls Scafolding for rebar

VTR-10-WL-S1-P3.135
Room Walls Rebar Installation 12 25-Nov-24 08-Dec-24 Room Walls Rebar Installation

VTR-10-WL-S1-P3.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 08-Dec-24 10-Dec-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-10-WL-S1-P3.145
Room Walls Formwork Installation 12 10-Dec-24 24-Dec-24 Room Walls Formwork Installation

VTR-10-WL-S1-P3.150
Room Walls Concrete Casting 1 24-Dec-24 25-Dec-24 Room Walls Concrete Casting

VTR-10-WL-S1-P3.155
Room Walls Curing work 1 25-Dec-24 26-Dec-24 Room Walls Curing work

VTR-10-WL-S1-P3.160
Room Walls Formwork Removel 3 26-Dec-24 30-Dec-24 Room Walls Formwork Removel

TOP SLAB BELOW GROUND LEVEL 78 10-Dec-24 10-Mar-25 10-Mar-25, TOP SLAB BELOW GROUND LEVEL
Part-1 39 10-Dec-24 23-Jan-25 23-Jan-25, Part-1
VTR-10-TS-P1.125 Room Top Slab Formwork Installation 10 10-Dec-24 22-Dec-24 Room Top Slab Formwork Installation

VTR-10-TS-P1.130 Room Top Slab Rebar Installation 12 22-Dec-24 04-Jan-25 Room Top Slab Rebar Installation

VTR-10-TS-P1.135 Room Top Slab Concrete Casting 1 05-Jan-25 05-Jan-25 Room Top Slab Concrete Casting

VTR-10-TS-P1.140 Room Top slab Curing work 12 06-Jan-25 19-Jan-25 Room Top slab Curing work

VTR-10-TS-P1.145 Room Top Slab Formwork Removel 4 20-Jan-25 23-Jan-25 Room Top Slab Formwork Removel

Part-2 39 25-Jan-25 10-Mar-25 10-Mar-25, Part-2


VTR-10-TS-P2.125 Room Top Slab Formwork Installation 10 25-Jan-25 04-Feb-25 Room Top Slab Formwork Installation

VTR-10-TS-P2.130 Room Top Slab Rebar Installation 12 05-Feb-25 18-Feb-25 Room Top Slab Rebar Installation

VTR-10-TS-P2.135 Room Top Slab Concrete Casting 1 18-Feb-25 19-Feb-25 Room Top Slab Concrete Casting

VTR-10-TS-P2.140 Room Top slab Curing work 12 19-Feb-25 05-Mar-25 Room Top slab Curing work

VTR-10-TS-P2.145 Room Top Slab Formwork Removel 4 05-Mar-25 10-Mar-25 Room Top Slab Formwork Removel

Part-3 39 25-Jan-25 10-Mar-25 10-Mar-25, Part-3


VTR-10-TS-P3.125 Room Top Slab Formwork Installation 10 25-Jan-25 04-Feb-25 Room Top Slab Formwork Installation

VTR-10-TS-P3.130 Room Top Slab Rebar Installation 12 05-Feb-25 18-Feb-25 Room Top Slab Rebar Installation

VTR-10-TS-P3.135 Room Top Slab Concrete Casting 1 18-Feb-25 19-Feb-25 Room Top Slab Concrete Casting

VTR-10-TS-P3.140 Room Top slab Curing work 12 19-Feb-25 05-Mar-25 Room Top slab Curing work

VTR-10-TS-P3.145 Room Top Slab Formwork Removel 4 05-Mar-25 10-Mar-25 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 101 25-Jan-25 26-May-25 26-May-25, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 66 25-Jan-25 15-Apr-25 15-Apr-25, WALL CONCRETE CASTING STAGE-1
Part-1 50 25-Jan-25 23-Mar-25 23-Mar-25, Part-1
VTR-10-WL-SG.1-P1.44
Room Walls Scafolding for rebar 6 25-Jan-25 30-Jan-25 Room Walls Scafolding for rebar

VTR-10-WL-SG.1-P1.45
Room Walls Rebar Installation 10 30-Jan-25 11-Feb-25 Room Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
29 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-10-WL-SG.1-P1.55
Room Walls Formwork Installation 6 10-Mar-25 17-Mar-25 Room Walls Formwork Installation

VTR-10-WL-SG.1-P1.60
Room Walls Concrete Casting 1 17-Mar-25 18-Mar-25 Room Walls Concrete Casting

VTR-10-WL-SG.1-P1.65
Room Walls Curing work 1 18-Mar-25 19-Mar-25 Room Walls Curing work

VTR-10-WL-SG.1-P1.70
Room Walls Formwork Removel 3 19-Mar-25 23-Mar-25 Room Walls Formwork Removel

Part-2 27 10-Mar-25 15-Apr-25 15-Apr-25, Part-2


VTR-10-WL-SG.1-P2.44
Room Walls Scafolding for rebar 6 10-Mar-25 17-Mar-25 Room Walls Scafolding for rebar

VTR-10-WL-SG.1-P2.45
Room Walls Rebar Installation 10 17-Mar-25 29-Mar-25 Room Walls Rebar Installation

VTR-10-WL-SG.1-P2.55
Room Walls Formwork Installation 6 29-Mar-25 09-Apr-25 Room Walls Formwork Installation

VTR-10-WL-SG.1-P2.60
Room Walls Concrete Casting 1 09-Apr-25 10-Apr-25 Room Walls Concrete Casting

VTR-10-WL-SG.1-P2.65
Room Walls Curing work 1 10-Apr-25 12-Apr-25 Room Walls Curing work

VTR-10-WL-SG.1-P2.70
Room Walls Formwork Removel 3 12-Apr-25 15-Apr-25 Room Walls Formwork Removel

WALL CONCRETE CASTING STAGE-2 51 23-Mar-25 26-May-25 26-May-25, WALL CONCRETE CASTING STAGE-2
Part-1 29 23-Mar-25 30-Apr-25 30-Apr-25, Part-1
VTR-10-WL.SG.2-P1.44
Room Walls Scafolding for rebar 6 23-Mar-25 03-Apr-25 Room Walls Scafolding for rebar

VTR-10-WL.SG.2-P1.45
Room Walls Rebar Installation 10 03-Apr-25 15-Apr-25 Room Walls Rebar Installation

VTR-10-WL.SG.2-P1.50
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 15-Apr-25 17-Apr-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-10-WL.SG.2-P1.55
Room Walls Formwork Installation 6 17-Apr-25 24-Apr-25 Room Walls Formwork Installation

VTR-10-WL.SG.2-P1.60
Room Walls Concrete Casting 1 24-Apr-25 26-Apr-25 Room Walls Concrete Casting

VTR-10-WL.SG.2-P1.65
Room Walls Curing work 1 26-Apr-25 27-Apr-25 Room Walls Curing work

VTR-10-WL.SG.2-P1.70
Room Walls Formwork Removel 3 27-Apr-25 30-Apr-25 Room Walls Formwork Removel

Part-2 35 15-Apr-25 26-May-25 26-May-25, Part-2


VTR-10-WL.SG.2-P2.44
Room Walls Scafolding for rebar 6 15-Apr-25 22-Apr-25 Room Walls Scafolding for rebar

VTR-10-WL.SG.2-P2.45
Room Walls Rebar Installation 10 22-Apr-25 04-May-25 Room Walls Rebar Installation

VTR-10-WL.SG.2-P2.50
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 04-May-25 06-May-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-10-WL.SG.2-P2.55
Room Walls Formwork Installation 12 06-May-25 20-May-25 Room Walls Formwork Installation

VTR-10-WL.SG.2-P2.60
Room Walls Concrete Casting 1 20-May-25 21-May-25 Room Walls Concrete Casting

VTR-10-WL.SG.2-P2.65
Room Walls Curing work 1 21-May-25 22-May-25 Room Walls Curing work

VTR-10-WL.SG.2-P2.70
Room Walls Formwork Removel 3 22-May-25 26-May-25 Room Walls Formwork Removel

SLAB ABOVE GROUND LEVEL 50 30-Apr-25 01-Jul-25 01-Jul-25, SLAB ABOVE GROUND LEVEL
Part-1 28 30-Apr-25 02-Jun-25 02-Jun-25, Part-1
VTR-10-SL.ABG-P1.125
Room Top Slab Formwork Installation 6 30-Apr-25 07-May-25 Room Top Slab Formwork Installation

VTR-10-SL.ABG-P1.130
Room Top Slab Rebar Installation 5 07-May-25 13-May-25 Room Top Slab Rebar Installation

VTR-10-SL.ABG-P1.135
Room Top Slab Concrete Casting 1 13-May-25 14-May-25 Room Top Slab Concrete Casting

VTR-10-SL.ABG-P1.140
Room Top slab Curing work 12 14-May-25 28-May-25 Room Top slab Curing work

VTR-10-SL.ABG-P1.145
Room Top Slab Formwork Removel 4 28-May-25 02-Jun-25 Room Top Slab Formwork Removel

Part-2 28 26-May-25 01-Jul-25 01-Jul-25, Part-2


VTR-10-SL.ABG-P2.125
Room Top Slab Formwork Installation 6 26-May-25 02-Jun-25 Room Top Slab Formwork Installation

VTR-10-SL.ABG-P2.130
Room Top Slab Rebar Installation 5 02-Jun-25 11-Jun-25 Room Top Slab Rebar Installation

VTR-10-SL.ABG-P2.135
Room Top Slab Concrete Casting 1 11-Jun-25 12-Jun-25 Room Top Slab Concrete Casting

VTR-10-SL.ABG-P2.140
Room Top slab Curing work 12 12-Jun-25 26-Jun-25 Room Top slab Curing work

VTR-10-SL.ABG-P2.145
Room Top Slab Formwork Removel 4 26-Jun-25 01-Jul-25 Room Top Slab Formwork Removel

WATER PROOFING 67 24-Jun-25 10-Sep-25 10-Sep-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 22 24-Jun-25 20-Jul-25 20-Jul-25, WALL WATER PROOFING STAGE-1
VTR-10-WP-WL-S1.115
Surface preparation work 6 24-Jun-25 01-Jul-25 Surface preparation work

VTR-10-WP-WL-S1.120
Applying of waterproofing material 11 01-Jul-25 14-Jul-25 Applying of waterproofing material

VTR-10-WP-WL-S1.125
VR Back filling 5 14-Jul-25 20-Jul-25 VR Back filling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
30 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL WATER PROOFING STAGE-2 22 01-Jul-25 27-Jul-25 27-Jul-25, WALL WATER PROOFING STAGE-2
VTR-10-WP-WL-S2.115
Surface preparation work 6 01-Jul-25 08-Jul-25 Surface preparation work

VTR-10-WP-WL-S2.120
Applying of waterproofing material 11 08-Jul-25 21-Jul-25 Applying of waterproofing material

VTR-10-WP-WL-S2.125
VR Back filling 5 21-Jul-25 27-Jul-25 VR Back filling

WALL WATER PROOFING STAGE-3 22 08-Jul-25 03-Aug-25 03-Aug-25, WALL WATER PROOFING STAGE-3
VTR-10-WP-WL-S3.115
Surface preparation work 6 08-Jul-25 15-Jul-25 Surface preparation work

VTR-10-WP-WL-S3.120
Applying of waterproofing material 11 15-Jul-25 28-Jul-25 Applying of waterproofing material

VTR-10-WP-WL-S3.125
VR Back filling 5 28-Jul-25 03-Aug-25 VR Back filling

WALL WATER PROOFING STAGE-4 22 15-Jul-25 10-Aug-25 10-Aug-25, WALL WATER PROOFING STAGE-4
VTR-10-WP-WL-S4.115
Surface preparation work 6 15-Jul-25 22-Jul-25 Surface preparation work

VTR-10-WP-WL-S4.120
Applying of waterproofing material 11 22-Jul-25 04-Aug-25 Applying of waterproofing material

VTR-10-WP-WL-S4.125
VR Back filling 5 04-Aug-25 10-Aug-25 VR Back filling

TOP SLAB WATER PROOFING 27 10-Aug-25 10-Sep-25 10-Sep-25, TOP SLAB WATER PROOFING
VTR-10-WP-SLB-S1.115
Surface preparation work 12 10-Aug-25 24-Aug-25 Surface preparation work

VTR-10-WP-SLB-S1.120
Applying of waterproofing material 14 24-Aug-25 09-Sep-25 Applying of waterproofing material

VTR-10-WP-SLB-S1.125
Leak Test 1 09-Sep-25 10-Sep-25 Leak Test

MECHANICAL ROOM MEP 77 01-Jul-25 30-Sep-25 30-Sep-25, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 77 01-Jul-25 30-Sep-25 30-Sep-25, ELECTRICAL WORK IN ROOM
POWER SYSTEM 62 01-Jul-25 11-Sep-25 11-Sep-25, POWER SYSTEM
EARTHING SYSTEM 25 01-Jul-25 29-Jul-25 29-Jul-25, EARTHING SYSTEM
VTR-10-EES-105 Earthing system soil resistivity test 6 01-Jul-25 08-Jul-25 Earthing system soil resistivity test

VTR-10-EES-115 Earthing system Copper rod/ earthing pit installation 8 08-Jul-25 17-Jul-25 Earthing system Copper rod/ earthing pit installation

VTR-10-EES-125 Earthing system Termination 6 17-Jul-25 23-Jul-25 Earthing system Termination

VTR-10-EES-135 Earthing system Initial Testing 5 24-Jul-25 29-Jul-25 Earthing system Initial Testing

LIGHTING SYSTEM 37 08-Jul-25 19-Aug-25 19-Aug-25, LIGHTING SYSTEM


VTR-10-ELI.105 Lighting system Conduit and boxes Installation 8 08-Jul-25 17-Jul-25 Lighting system Conduit and boxes Installation

VTR-10-ELI.115 Lighting system Cable Pulling 8 17-Jul-25 26-Jul-25 Lighting system Cable Pulling

VTR-10-ELI.125 Lighting system Installations 8 27-Jul-25 04-Aug-25 Lighting system Installations

VTR-10-ELI.135 Lighting system Termination 8 04-Aug-25 13-Aug-25 Lighting system Termination

VTR-10-ELI.145 Lighting system Initial Testing 5 13-Aug-25 19-Aug-25 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 17-Jul-25 10-Sep-25 10-Sep-25, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-10-ECT.105 Cable Tray Installation 10 17-Jul-25 28-Jul-25 Cable Tray Installation

VTR-10-ECT.115 Cable Tray Inspection 10 29-Jul-25 09-Aug-25 Cable Tray Inspection

VTR-10-ECT.125 LV Cable pulling 10 09-Aug-25 20-Aug-25 LV Cable pulling

VTR-10-ECT.135 LV Cable Termination 10 20-Aug-25 01-Sep-25 LV Cable Termination

VTR-10-ECT.145 LV Cable Initial Testing 8 01-Sep-25 10-Sep-25 LV Cable Initial Testing

SMALL POWER SYSTEM 39 29-Jul-25 11-Sep-25 11-Sep-25, SMALL POWER SYSTEM


VTR-10-ESP.105 Small Power Conduit and boxes Installation 12 29-Jul-25 11-Aug-25 Small Power Conduit and boxes Installation

VTR-10-ESP.115 Small Power Cable Pulling 10 11-Aug-25 23-Aug-25 Small Power Cable Pulling

VTR-10-ESP.125 Small Power Installations 6 23-Aug-25 30-Aug-25 Small Power Installations

VTR-10-ESP.135 Small Power Termination 6 30-Aug-25 06-Sep-25 Small Power Termination

VTR-10-ESP.145 Small Power Initial Testing 5 06-Sep-25 11-Sep-25 Small Power Initial Testing

POWER DISTRIBUTION 44 08-Jul-25 28-Aug-25 28-Aug-25, POWER DISTRIBUTION


GENERATOR 39 08-Jul-25 23-Aug-25 23-Aug-25, GENERATOR
VTR-10-EPD.105 Generator Cable Tray Installation 7 08-Jul-25 16-Jul-25 Generator Cable Tray Installation

VTR-10-EPD.115 Generator Cable Pulling 7 16-Jul-25 23-Jul-25 Generator Cable Pulling

VTR-10-EPD.125 Generator Cell Pannel Installation 7 24-Jul-25 31-Jul-25 Generator Cell Pannel Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
31 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-10-EPD.135 Generator Installation 7 31-Jul-25 09-Aug-25 Generator Installation

VTR-10-EPD.145 Generator Pannel / Cable Termination 7 09-Aug-25 17-Aug-25 Generator Pannel / Cable Termination

VTR-10-EPD.155 Generator Pannel / Cable initial Testing 5 17-Aug-25 23-Aug-25 Generator Pannel / Cable initial Testing

UPS 28 16-Jul-25 18-Aug-25 18-Aug-25, UPS


VTR-10-EPD.165 UPS Cable Tray Installation 5 16-Jul-25 21-Jul-25 UPS Cable Tray Installation

VTR-10-EPD.175 UPS Cable Pulling 5 22-Jul-25 27-Jul-25 UPS Cable Pulling

VTR-10-EPD.185 UPS Pannel Installation 5 27-Jul-25 02-Aug-25 UPS Pannel Installation

VTR-10-EPD.195 UPS Installation 5 02-Aug-25 07-Aug-25 UPS Installation

VTR-10-EPD.205 UPS Pannel / Cable Termination 5 07-Aug-25 13-Aug-25 UPS Pannel / Cable Termination

VTR-10-EPD.215 UPS Pannel / Cable initial Testing 4 13-Aug-25 18-Aug-25 UPS Pannel / Cable initial Testing

MDB 33 22-Jul-25 28-Aug-25 28-Aug-25, MDB


VTR-10-EPD.225 MDB Cable Tray Installation 7 22-Jul-25 29-Jul-25 MDB Cable Tray Installation

VTR-10-EPD.235 MDB Cable Pulling 7 29-Jul-25 06-Aug-25 MDB Cable Pulling

VTR-10-EPD.245 MDB Pannel Installation 7 06-Aug-25 14-Aug-25 MDB Pannel Installation

VTR-10-EPD.255 MDB Pannel / Cable Termination 7 14-Aug-25 23-Aug-25 MDB Pannel / Cable Termination

VTR-10-EPD.265 MDB Pannel / Cable initial Testing 5 23-Aug-25 28-Aug-25 MDB Pannel / Cable initial Testing

MCC 33 16-Jul-25 23-Aug-25 23-Aug-25, MCC


VTR-10-EPD.325 MCC Cable Tray Installation 7 16-Jul-25 23-Jul-25 MCC Cable Tray Installation

VTR-10-EPD.335 MCC Cable Pulling 7 24-Jul-25 31-Jul-25 MCC Cable Pulling

VTR-10-EPD.345 MCC Pannel Installation 7 31-Jul-25 09-Aug-25 MCC Pannel Installation

VTR-10-EPD.355 MCC Pannel / Cable Termination 7 09-Aug-25 17-Aug-25 MCC Pannel / Cable Termination

VTR-10-EPD.365 MCC Pannel / Cable initial Testing 5 17-Aug-25 23-Aug-25 MCC Pannel / Cable initial Testing

SMSB 24 16-Jul-25 12-Aug-25 12-Aug-25, SMSB


VTR-10-EPD.275 SMSB Cable Tray Installation 5 16-Jul-25 21-Jul-25 SMSB Cable Tray Installation

VTR-10-EPD.285 SMSB Cable Pulling 5 22-Jul-25 27-Jul-25 SMSB Cable Pulling

VTR-10-EPD.295 SMSB Pannel Installation 5 27-Jul-25 02-Aug-25 SMSB Pannel Installation

VTR-10-EPD.305 SMSB Pannel / Cable Termination 5 02-Aug-25 07-Aug-25 SMSB Pannel / Cable Termination

VTR-10-EPD.315 SMSB Pannel / Cable initial Testing 4 07-Aug-25 12-Aug-25 SMSB Pannel / Cable initial Testing

DB 24 22-Jul-25 18-Aug-25 18-Aug-25, DB


VTR-10-EPD.375 DB Cable Tray Installation 5 22-Jul-25 27-Jul-25 DB Cable Tray Installation

VTR-10-EPD.385 DB Cable Pulling 5 27-Jul-25 02-Aug-25 DB Cable Pulling

VTR-10-EPD.395 DB Pannel Installation 5 02-Aug-25 07-Aug-25 DB Pannel Installation

VTR-10-EPD.405 DB Pannel / Cable Termination 5 07-Aug-25 13-Aug-25 DB Pannel / Cable Termination

VTR-10-EPD.415 DB Pannel / Cable initial Testing 4 13-Aug-25 18-Aug-25 DB Pannel / Cable initial Testing

ISOLATOR 24 22-Jul-25 18-Aug-25 18-Aug-25, ISOLATOR


VTR-10-EPD.425 Isolators Cable Tray Installation 5 22-Jul-25 27-Jul-25 Isolators Cable Tray Installation

VTR-10-EPD.435 Isolators Cable Pulling 5 27-Jul-25 02-Aug-25 Isolators Cable Pulling

VTR-10-EPD.445 Isolators Pannel Installation 5 02-Aug-25 07-Aug-25 Isolators Pannel Installation

VTR-10-EPD.455 Isolators Pannel / Cable Termination 5 07-Aug-25 13-Aug-25 Isolators Pannel / Cable Termination

VTR-10-EPD.465 Isolators Pannel / Cable initial Testing 4 13-Aug-25 18-Aug-25 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 22-Jul-25 18-Aug-25 18-Aug-25, LCP/ ELCP


VTR-10-EPD.475 LCP/ELCP Cable Tray Installation 5 22-Jul-25 27-Jul-25 LCP/ELCP Cable Tray Installation

VTR-10-EPD.485 LCP/ELCP Cable Pulling 5 27-Jul-25 02-Aug-25 LCP/ELCP Cable Pulling

VTR-10-EPD.495 LCP/ELCP Pannel Installation 5 02-Aug-25 07-Aug-25 LCP/ELCP Pannel Installation

VTR-10-EPD.505 LCP/ELCP Pannel / Cable Termination 5 07-Aug-25 13-Aug-25 LCP/ELCP Pannel / Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
32 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-10-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 13-Aug-25 18-Aug-25 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 42 11-Aug-25 30-Sep-25 30-Sep-25, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 11-Aug-25 30-Sep-25 30-Sep-25, FIRE ALARM SYSTEM
VTR-10-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 Fire Alarm Conduit /Cable Tray Installation

VTR-10-ELFA.115 Fire Alarm Cable Pulling 9 21-Aug-25 01-Sep-25 Fire Alarm Cable Pulling

VTR-10-ELFA.125 Fire Alarm Devices Installation 9 01-Sep-25 11-Sep-25 Fire Alarm Devices Installation

VTR-10-ELFA.135 Fire Alarm Devices and Cable Termination 9 11-Sep-25 22-Sep-25 Fire Alarm Devices and Cable Termination

VTR-10-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 11-Aug-25 30-Sep-25 30-Sep-25, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DAT
VTR-10-ELVS.105 ICT System Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 ICT System Conduit /Cable Tray Installation

VTR-10-ELVS.115 ICT System Cable Pulling 9 21-Aug-25 01-Sep-25 ICT System Cable Pulling

VTR-10-ELVS.125 ICT System Devices Installation 9 01-Sep-25 11-Sep-25 ICT System Devices Installation

VTR-10-ELVS.135 ICT System Devices and Cable Termination 9 11-Sep-25 22-Sep-25 ICT System Devices and Cable Termination

VTR-10-ELVS.145 ICT System Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 11-Aug-25 30-Sep-25 30-Sep-25, ACCESS CONTROL SYSTEM


VTR-10-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 Access Control System Conduit /Cable Tray Installation

VTR-10-ELAC.115 Access Control System Cable Pulling 9 21-Aug-25 01-Sep-25 Access Control System Cable Pulling

VTR-10-ELAC.125 Access Control System Devices Installation 9 01-Sep-25 11-Sep-25 Access Control System Devices Installation

VTR-10-ELAC.135 Access Control System Devices and Cable Termination 9 11-Sep-25 22-Sep-25 Access Control System Devices and Cable Termination

VTR-10-ELAC.145 Access Control System Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 11-Aug-25 30-Sep-25 30-Sep-25, PUBLIC ADDRESS SYSTEM


VTR-10-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 Public Address System Conduit /Cable Tray Installation

VTR-10-ELPA.115 Public Address System Cable Pulling 9 21-Aug-25 01-Sep-25 Public Address System Cable Pulling

VTR-10-ELPA.125 Public Address System Devices Installation 9 01-Sep-25 11-Sep-25 Public Address System Devices Installation

VTR-10-ELPA.135 Public Address System Devices and Cable Termination 9 11-Sep-25 22-Sep-25 Public Address System Devices and Cable Termination

VTR-10-ELPA.145 Public Address System Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 11-Aug-25 30-Sep-25 30-Sep-25, SCADA SYSTEM


VTR-10-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 SCADA System Conduit /Cable Tray Installation

VTR-10-ELSC.115 SCADA System Cable Pulling 9 21-Aug-25 01-Sep-25 SCADA System Cable Pulling

VTR-10-ELSC.125 SCADA System Devices Installation 9 01-Sep-25 11-Sep-25 SCADA System Devices Installation

VTR-10-ELSC.135 SCADA System Devices and Cable Termination 9 11-Sep-25 22-Sep-25 SCADA System Devices and Cable Termination

VTR-10-ELSC.145 SCADA System Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 11-Aug-25 30-Sep-25 30-Sep-25, RADIO RE- BROADCOASTING/ TETRA
VTR-10-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 11-Aug-25 21-Aug-25 Radio/TETRA System Conduit /Cable Tray Installation

VTR-10-ELRD.115 Radio/TETRA System Cable Pulling 9 21-Aug-25 01-Sep-25 Radio/TETRA System Cable Pulling

VTR-10-ELRD.125 Radio/TETRA System Devices Installation 9 01-Sep-25 11-Sep-25 Radio/TETRA System Devices Installation

VTR-10-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 11-Sep-25 22-Sep-25 Radio/TETRA System Devices and Cable Termination

VTR-10-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 22-Sep-25 30-Sep-25 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 47 16-Jul-25 09-Sep-25 09-Sep-25, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 16-Jul-25 13-Aug-25 13-Aug-25, FIRE FIGHTING
VTR-10-MFF.105 Fire Fighting system Pipe and accessories installation 21 16-Jul-25 10-Aug-25 Fire Fighting system Pipe and accessories installation

VTR-10-MFF.115 Fire Fighting system deluge valve installation 16 22-Jul-25 10-Aug-25 Fire Fighting system deluge valve installation

VTR-10-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 03-Aug-25 10-Aug-25 Fire Fighting system fire hose cabinet/extingusher installation

VTR-10-MFF.140 Fire Fighting system initial testing 3 10-Aug-25 13-Aug-25 Fire Fighting system initial testing

VTR-10-MFF.145 Fire Fighting clean agent system 2 07-Aug-25 10-Aug-25 Fire Fighting clean agent system

HVAC 47 16-Jul-25 09-Sep-25 09-Sep-25, HVAC

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
33 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-10-MHV.115 Air conditioning system installation 12 18-Aug-25 01-Sep-25 Air conditioning system installation

VTR-10-MHV.120 Fan installation 15 14-Aug-25 01-Sep-25 Fan installation

VTR-10-MHV.125 Duct and accessories installation 28 16-Jul-25 18-Aug-25 Duct and accessories installation

VTR-10-MHV.135 HVAC inital testing 7 01-Sep-25 09-Sep-25 HVAC inital testing

PLUMBING 8 10-Aug-25 19-Aug-25 19-Aug-25, PLUMBING


VTR-10-MPL.105 Plumbing drainage system installation 6 10-Aug-25 17-Aug-25 Plumbing drainage system installation

VTR-10-MPL.115 Plumbing drainage system initial testing 2 17-Aug-25 19-Aug-25 Plumbing drainage system initial testing

DRY UTILITIES 25 16-Jul-25 13-Aug-25 13-Aug-25, DRY UTILITIES


POWER 25 16-Jul-25 13-Aug-25 13-Aug-25, POWER
POWER LV 16 16-Jul-25 04-Aug-25 04-Aug-25, POWER LV
VTR-10-PLV.100 Installation of support 1 16-Jul-25 16-Jul-25 Installation of support

VTR-10-PLV.105 Installation of horizontal busbar 2 16-Jul-25 19-Jul-25 Installation of horizontal busbar

VTR-10-PLV.110 Installation of vertical busbar 2 19-Jul-25 21-Jul-25 Installation of vertical busbar

VTR-10-PLV.115 Installation of left/right elbow 2 21-Jul-25 22-Jul-25 Installation of left/right elbow

VTR-10-PLV.120 Installation of right horizintal offset 2 22-Jul-25 24-Jul-25 Installation of right horizintal offset

VTR-10-PLV.125 Instalaltion of upward vertical offset 3 24-Jul-25 28-Jul-25 Instalaltion of upward vertical offset

VTR-10-PLV.130 Installation of downward vertical offset 3 28-Jul-25 31-Jul-25 Installation of downward vertical offset

VTR-10-PLV.135 Installation of transformer and panel connection 2 31-Jul-25 04-Aug-25 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 16-Jul-25 06-Aug-25 06-Aug-25, MEDIUM VOLTAGE


VTR-10-PMV.100 Installation of cable try, arm, racks and ladder 6 16-Jul-25 24-Jul-25 Installation of cable try, arm, racks and ladder

VTR-10-PMV.105 Installation of MV Cable 4 24-Jul-25 29-Jul-25 Installation of MV Cable

VTR-10-PMV.110 Installation of cable cleats 2 29-Jul-25 30-Jul-25 Installation of cable cleats

VTR-10-PMV.115 Installation of gland 1 30-Jul-25 31-Jul-25 Installation of gland

VTR-10-PMV.120 splicing/termination of MV cable 2 31-Jul-25 03-Aug-25 splicing/termination of MV cable

VTR-10-PMV.125 Testing and Pre-commissioning of cable 2 03-Aug-25 04-Aug-25 Testing and Pre-commissioning of cable

VTR-10-PMV.130 Energezation 2 04-Aug-25 06-Aug-25 Energezation

TRANSFORMER 16 24-Jul-25 12-Aug-25 12-Aug-25, TRANSFORMER


VTR-10-PTF.100 Installation of Transformer unit 2 24-Jul-25 26-Jul-25 Installation of Transformer unit

VTR-10-PTF.105 Testing and Pre-Commissioning of unit 1 26-Jul-25 27-Jul-25 Testing and Pre-Commissioning of unit

VTR-10-PTF.110 Termination and Splicing of MV Cable 3 27-Jul-25 30-Jul-25 Termination and Splicing of MV Cable

VTR-10-PTF.115 Termination and Splicing of LV Cable/bus way 3 30-Jul-25 04-Aug-25 Termination and Splicing of LV Cable/bus way

VTR-10-PTF.120 Installation and connection of I/O system 2 04-Aug-25 06-Aug-25 Installation and connection of I/O system

VTR-10-PTF.125 Installation of Grounding and Protection System 2 06-Aug-25 09-Aug-25 Installation of Grounding and Protection System

VTR-10-PTF.130 Testing and Commissioning of MV System 1 09-Aug-25 10-Aug-25 Testing and Commissioning of MV System

VTR-10-PTF.135 Testing and Commissioning of LV System 1 10-Aug-25 11-Aug-25 Testing and Commissioning of LV System

VTR-10-PTF.140 Energezation 1 11-Aug-25 12-Aug-25 Energezation

RMU 16 26-Jul-25 13-Aug-25 13-Aug-25, RMU


VTR-10-RMU.100 Installation RMU unit 2 26-Jul-25 29-Jul-25 Installation RMU unit

VTR-10-RMU.105 Testing and Pre-Commissioning of unit 2 29-Jul-25 30-Jul-25 Testing and Pre-Commissioning of unit

VTR-10-RMU.110 Termination and Splicing of Ring-MV Cable 4 30-Jul-25 04-Aug-25 Termination and Splicing of Ring-MV Cable

VTR-10-RMU.115 Termination and Splicing of T-MV Cable 4 04-Aug-25 09-Aug-25 Termination and Splicing of T-MV Cable

VTR-10-RMU.120 Installation of Grounding and Protection System 2 09-Aug-25 12-Aug-25 Installation of Grounding and Protection System

VTR-10-RMU.125 Testing and Commissioning of MV System 1 12-Aug-25 13-Aug-25 Testing and Commissioning of MV System

VTR-10-RMU.130 Energezation 1 13-Aug-25 13-Aug-25 Energezation

VECHICULAR ROOM 3C (IN ZONE 08) 644 24-May-23 05-Jul-25 05-Jul-25, VECHICULAR ROOM 3C (IN ZONE 08)
ENGINEERING 109 24-May-23 03-Oct-23 03-Oct-23, ENGINEERING

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
34 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
SHOP DRAWING SUBMITTAL ANDAPPROVAL 109 24-May-23 03-Oct-23 03-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE
VR-3C-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VR-3C-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VR-3C-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VR-3C-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VR-3C-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VR-3C-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VR-3C-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VR-3C-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VR-3C-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VR-3C-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VR-3C-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VR-3C-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VR-3C-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VR-3C-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VR-3C-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VR-3C-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VR-3C-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VR-3C-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VR-3C-ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VR-3C-ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


VR-3C-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

VR-3C-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM


VR-3C-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

VR-3C-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VR-3C-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VR-3C-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VR-3C-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VR-3C-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
35 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR-3C-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VR-3C-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VR-3C-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VR-3C-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VR-3C-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY UTILITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.200 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.205 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.200 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.205 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.200 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.205 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.200 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.205 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 223 05-Sep-24 29-May-25 29-May-25, PROCUREMENT


CIVIL/STRUCTURAL 16 05-Sep-24 25-Sep-24 25-Sep-24, CIVIL/STRUCTURAL
VR-3C-PRO-CV.110 Issue Purchase Order 6 05-Sep-24 12-Sep-24 Issue Purchase Order

VR-3C-PRO-CV.115 Material Delivery 10 12-Sep-24 25-Sep-24 Material Delivery

MECHANICAL 154 26-Nov-24 29-May-25 29-May-25, MECHANICAL


FIRE FIGHTING SYSTEM 105 26-Nov-24 29-Mar-25 29-Mar-25, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 26-Nov-24 29-Mar-25 29-Mar-25, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VR-3C-PR-MC-FF.110Issue Purchase Order 15 26-Nov-24 14-Dec-24 Issue Purchase Order

VR-3C-PR-MC-FF.115Material Delivery 90 14-Dec-24 29-Mar-25 Material Delivery

VENTILATION SYSTEM 105 22-Jan-25 29-May-25 29-May-25, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 22-Jan-25 29-May-25 29-May-25, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VR-3C-PR-MC-DS.110
Issue Purchase Order 15 22-Jan-25 09-Feb-25 Issue Purchase Order

VR-3C-PR-MC-DS.115
Material Delivery 90 09-Feb-25 29-May-25 Material Delivery

AIR CONDITIONING WORKS 105 22-Jan-25 29-May-25 29-May-25, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 22-Jan-25 29-May-25 29-May-25, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VR-3C-PR-MC-AC.110
Issue Purchase Order 15 22-Jan-25 09-Feb-25 Issue Purchase Order

VR-3C-PR-MC-AC.115
Material Delivery 90 09-Feb-25 29-May-25 Material Delivery

PLUMBING SYSTEM 105 21-Dec-24 27-Apr-25 27-Apr-25, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 21-Dec-24 27-Apr-25 27-Apr-25, PUMPS,PIPES,FITTINGS,VALVES
VR-3C-PR-MC-PI.110Issue Purchase Order 15 21-Dec-24 07-Jan-25 Issue Purchase Order

VR-3C-PR-MC-PI.115Material Delivery 90 07-Jan-25 27-Apr-25 Material Delivery

ELECTRICAL 120 21-Dec-24 14-May-25 14-May-25, ELECTRICAL


CABLE TRAY 105 28-Dec-24 04-May-25 04-May-25, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 28-Dec-24 04-May-25 04-May-25, CABLE TRAY AND ACCESSORIES,PVC DUCT
VR-3C-PR-EL-CT.110Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-EL-CT.115Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

POWER CABLES 105 28-Dec-24 04-May-25 04-May-25, POWER CABLES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
36 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 28-Dec-24 04-May-25 04-May-25, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VR-3C-PR-EL-PC.110Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-EL-PC.115Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

LIGHTING SYSTEM 105 28-Dec-24 04-May-25 04-May-25, LIGHTING SYSTEM


CONDUIT,LIGHT 105 28-Dec-24 04-May-25 04-May-25, CONDUIT,LIGHT
VR-3C-PR-EL-LS.110Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-EL-LS.115Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

ELECTRICAL INSTALLATIONS 105 28-Dec-24 04-May-25 04-May-25, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 28-Dec-24 04-May-25 04-May-25, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VR-3C-PR-EL-EI.110 Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-EL-EI.115 Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 28-Dec-24 04-May-25 04-May-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 28-Dec-24 04-May-25 04-May-25, LIGHTNING PROTECTION SYSTEM
VR-3C-PR-EL-LP.110 Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-EL-LP.115 Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 21-Dec-24 27-Apr-25 27-Apr-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 21-Dec-24 27-Apr-25 27-Apr-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VR-3C-PR-EL-ES.110Issue Purchase Order 15 21-Dec-24 07-Jan-25 Issue Purchase Order

VR-3C-PR-EL-ES.115Material Delivery 90 07-Jan-25 27-Apr-25 Material Delivery

LOW CURRENT 114 28-Dec-24 14-May-25 14-May-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 28-Dec-24 04-May-25 04-May-25, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 28-Dec-24 04-May-25 04-May-25, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VR-3C-PR-ELL-FA.20
Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-FA.25
Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 28-Dec-24 04-May-25 04-May-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 28-Dec-24 04-May-25 04-May-25, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VR-3C-PR-ELL-PH.20
Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-PH.25
Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 28-Dec-24 04-May-25 04-May-25, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 28-Dec-24 04-May-25 04-May-25, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VR-3C-PR-ELL-PA.20
Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-PA.25
Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

VIDEO SURVEILLANCE 105 28-Dec-24 04-May-25 04-May-25, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 28-Dec-24 04-May-25 04-May-25, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VR-3C-PR-ELL-VS.20
Issue Purchase Order 15 28-Dec-24 14-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-VS.25
Material Delivery 90 14-Jan-25 04-May-25 Material Delivery

ACCESS CONTROL SYSTEM 105 07-Jan-25 14-May-25 14-May-25, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 07-Jan-25 14-May-25 14-May-25, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
VR-3C-PR-ELL-AC.20
Issue Purchase Order 15 07-Jan-25 25-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-AC.25
Material Delivery 90 25-Jan-25 14-May-25 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 07-Jan-25 14-May-25 14-May-25, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 07-Jan-25 14-May-25 14-May-25, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VR-3C-PR-ELL-RB.20
Issue Purchase Order 15 07-Jan-25 25-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-RB.25
Material Delivery 90 25-Jan-25 14-May-25 Material Delivery

SCADA SYSTEM 105 07-Jan-25 14-May-25 14-May-25, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 07-Jan-25 14-May-25 14-May-25, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VR-3C-PR-ELL-SD.20
Issue Purchase Order 15 07-Jan-25 25-Jan-25 Issue Purchase Order

VR-3C-PR-ELL-SD.25
Material Delivery 90 25-Jan-25 14-May-25 Material Delivery

CONSTRUCTION 243 16-Sep-24 05-Jul-25 05-Jul-25, CONSTRUCTION


STRUCTURAL WORKS 180 16-Sep-24 19-Apr-25 19-Apr-25, STRUCTURAL WORKS
PLAIN CONCRETE ABOVE TUNNEL SLAB 9 16-Sep-24 26-Sep-24 26-Sep-24, PLAIN CONCRETE ABOVE TUNNEL SLAB
Part-1 4 16-Sep-24 19-Sep-24 19-Sep-24, Part-1

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
37 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR-3C-PC-P1.120 Plain Concrete Above Top Slab Formwork Installation 2 16-Sep-24 17-Sep-24 Plain Concrete Above Top Slab Formwork Installation

VR-3C-PC-P1.125 Plain Concrete Casting 1 18-Sep-24 18-Sep-24 Plain Concrete Casting

VR-3C-PC-P1.135 Plain Concrete Formwork removal 1 19-Sep-24 19-Sep-24 Plain Concrete Formwork removal

Part-2 5 21-Sep-24 26-Sep-24 26-Sep-24, Part-2


VR-3C-PC-P2.120 Plain Concrete Above Top Slab Formwork Installation 2 21-Sep-24 22-Sep-24 Plain Concrete Above Top Slab Formwork Installation

VR-3C-PC-P2.125 Plain Concrete Casting 1 24-Sep-24 24-Sep-24 Plain Concrete Casting

VR-3C-PC-P2.130 Plain Concrete curing work 1 25-Sep-24 25-Sep-24 Plain Concrete curing work

VR-3C-PC-P2.135 Plain Concrete Formwork removal 1 25-Sep-24 26-Sep-24 Plain Concrete Formwork removal

FOUNDATION 31 21-Sep-24 27-Oct-24 27-Oct-24, FOUNDATION


Part-1 24 21-Sep-24 19-Oct-24 19-Oct-24, Part-1
VR-3C-FDN-P1.150 Foundation water proofing on blinding concrete 3 21-Sep-24 24-Sep-24 Foundation water proofing on blinding concrete

VR-3C-FDN-P1.155 Foundation Protection screed on water poofing 1 24-Sep-24 25-Sep-24 Foundation Protection screed on water poofing

VR-3C-FDN-P1.165 Foundation Rebar installation 10 25-Sep-24 07-Oct-24 Foundation Rebar installation

VR-3C-FDN-P1.170 Foundation Formwork installation 4 07-Oct-24 12-Oct-24 Foundation Formwork installation

VR-3C-FDN-P1.175 Foundation Construction joint work 2 12-Oct-24 14-Oct-24 Foundation Construction joint work

VR-3C-FDN-P1.180 Foundation concrete casting 1 14-Oct-24 15-Oct-24 Foundation concrete casting

VR-3C-FDN-P1.185 Foundation concrete curing 1 15-Oct-24 16-Oct-24 Foundation concrete curing

VR-3C-FDN-P1.190 Foundation Formwork Removal 2 16-Oct-24 19-Oct-24 Foundation Formwork Removal

Part-2 26 26-Sep-24 27-Oct-24 27-Oct-24, Part-2


VR-3C-FDN-P2.150 Foundation water proofing on blinding concrete 3 26-Sep-24 30-Sep-24 Foundation water proofing on blinding concrete

VR-3C-FDN-P2.155 Foundation Protection screed on water poofing 1 30-Sep-24 01-Oct-24 Foundation Protection screed on water poofing

VR-3C-FDN-P2.160 Foundation Curing for screed 2 01-Oct-24 03-Oct-24 Foundation Curing for screed

VR-3C-FDN-P2.165 Foundation Rebar installation 10 03-Oct-24 15-Oct-24 Foundation Rebar installation

VR-3C-FDN-P2.170 Foundation Formwork installation 4 15-Oct-24 20-Oct-24 Foundation Formwork installation

VR-3C-FDN-P2.175 Foundation Construction joint work 2 20-Oct-24 22-Oct-24 Foundation Construction joint work

VR-3C-FDN-P2.180 Foundation concrete casting 1 22-Oct-24 23-Oct-24 Foundation concrete casting

VR-3C-FDN-P2.185 Foundation concrete curing 1 23-Oct-24 24-Oct-24 Foundation concrete curing

VR-3C-FDN-P2.190 Foundation Formwork Removal 2 24-Oct-24 27-Oct-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 38 15-Oct-24 28-Nov-24 28-Nov-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 38 15-Oct-24 28-Nov-24 28-Nov-24, WALL CONCRETE CASTING STAGE-1
Part-1 29 15-Oct-24 18-Nov-24 18-Nov-24, Part-1
VR-3C-WL-S1-P1.135
Room Walls Rebar Installation 10 20-Oct-24 31-Oct-24 Room Walls Rebar Installation

VR-3C-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 31-Oct-24 03-Nov-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VR-3C-WL-S1-P1.145
Room Walls Formwork Installation 8 03-Nov-24 12-Nov-24 Room Walls Formwork Installation

VR-3C-WL-S1-P1.150
Room Walls Concrete Casting 1 12-Nov-24 13-Nov-24 Room Walls Concrete Casting

VR-3C-WL-S1-P1.155
Room Walls Curing work 1 13-Nov-24 14-Nov-24 Room Walls Curing work

VR-3C-WL-S1-P1.160
Room Walls Formwork Removel 3 14-Nov-24 18-Nov-24 Room Walls Formwork Removel

VR-3C-WL-S1-P1.165
Room Walls Scafolding for rebar 4 15-Oct-24 20-Oct-24 Room Walls Scafolding for rebar

Part-2 30 24-Oct-24 28-Nov-24 28-Nov-24, Part-2


VR-3C-WL-S1-P2.135
Room Walls Rebar Installation 10 30-Oct-24 11-Nov-24 Room Walls Rebar Installation

VR-3C-WL-S1-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 11-Nov-24 13-Nov-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VR-3C-WL-S1-P2.145
Room Walls Formwork Installation 8 13-Nov-24 23-Nov-24 Room Walls Formwork Installation

VR-3C-WL-S1-P2.150
Room Walls Concrete Casting 1 23-Nov-24 24-Nov-24 Room Walls Concrete Casting

VR-3C-WL-S1-P2.155
Room Walls Curing work 1 24-Nov-24 25-Nov-24 Room Walls Curing work

VR-3C-WL-S1-P2.160
Room Walls Formwork Removel 3 25-Nov-24 28-Nov-24 Room Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
38 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR-3C-WL-S1-P2.165
Room Walls Scafolding for rebar 5 24-Oct-24 30-Oct-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 72 18-Nov-24 10-Feb-25 10-Feb-25, TOP SLAB BELOW GROUND LEVEL
Part-1 36 18-Nov-24 30-Dec-24 30-Dec-24, Part-1
VR-3C-TS-P1.125 Room Top Slab Formwork Installation 9 18-Nov-24 28-Nov-24 Room Top Slab Formwork Installation

VR-3C-TS-P1.130 Room Top Slab Rebar Installation 10 28-Nov-24 10-Dec-24 Room Top Slab Rebar Installation

VR-3C-TS-P1.135 Room Top Slab Concrete Casting 1 10-Dec-24 11-Dec-24 Room Top Slab Concrete Casting

VR-3C-TS-P1.140 Room Top slab Curing work 12 11-Dec-24 25-Dec-24 Room Top slab Curing work

VR-3C-TS-P1.145 Room Top Slab Formwork Removel 4 25-Dec-24 30-Dec-24 Room Top Slab Formwork Removel

Part-2 36 30-Dec-24 10-Feb-25 10-Feb-25, Part-2


VR-3C-TS-P2.125 Room Top Slab Formwork Installation 9 30-Dec-24 09-Jan-25 Room Top Slab Formwork Installation

VR-3C-TS-P2.130 Room Top Slab Rebar Installation 10 09-Jan-25 21-Jan-25 Room Top Slab Rebar Installation

VR-3C-TS-P2.135 Room Top Slab Concrete Casting 1 21-Jan-25 22-Jan-25 Room Top Slab Concrete Casting

VR-3C-TS-P2.140 Room Top slab Curing work 12 22-Jan-25 05-Feb-25 Room Top slab Curing work

VR-3C-TS-P2.145 Room Top Slab Formwork Removel 4 05-Feb-25 10-Feb-25 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 47 30-Dec-24 23-Feb-25 23-Feb-25, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 47 30-Dec-24 23-Feb-25 23-Feb-25, WALL CONCRETE CASTING STAGE-1
Part-1 27 30-Dec-24 30-Jan-25 30-Jan-25, Part-1
VR-3C-WL-S1-A.105Room Walls Rebar Installation 10 05-Jan-25 16-Jan-25 Room Walls Rebar Installation

VR-3C-WL-S1-A.115Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 16-Jan-25 19-Jan-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VR-3C-WL-S1-A.125Room Walls Formwork Installation 5 19-Jan-25 25-Jan-25 Room Walls Formwork Installation

VR-3C-WL-S1-A.135Room Walls Concrete Casting 1 25-Jan-25 26-Jan-25 Room Walls Concrete Casting

VR-3C-WL-S1-A.145Room Walls Curing work 1 26-Jan-25 27-Jan-25 Room Walls Curing work

VR-3C-WL-S1-A.155Room Walls Formwork Removel 3 27-Jan-25 30-Jan-25 Room Walls Formwork Removel

VR-3C-WL-S1-A.165Room Walls Scafolding for rebar 5 30-Dec-24 05-Jan-25 Room Walls Scafolding for rebar

Part-2 27 22-Jan-25 23-Feb-25 23-Feb-25, Part-2


VR-3C-WL-S1-B.135Room Walls Rebar Installation 10 28-Jan-25 09-Feb-25 Room Walls Rebar Installation

VR-3C-WL-S1-B.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 09-Feb-25 11-Feb-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VR-3C-WL-S1-B.145Room Walls Formwork Installation 5 11-Feb-25 17-Feb-25 Room Walls Formwork Installation

VR-3C-WL-S1-B.150Room Walls Concrete Casting 1 17-Feb-25 18-Feb-25 Room Walls Concrete Casting

VR-3C-WL-S1-B.155Room Walls Curing work 1 18-Feb-25 19-Feb-25 Room Walls Curing work

VR-3C-WL-S1-B.160Room Walls Formwork Removel 3 19-Feb-25 23-Feb-25 Room Walls Formwork Removel

VR-3C-WL-S1-B.165Room Walls Scafolding for rebar 5 22-Jan-25 28-Jan-25 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 49 30-Jan-25 29-Mar-25 29-Mar-25, SLAB ABOVE GROUND LEVEL
Part-1 29 30-Jan-25 05-Mar-25 05-Mar-25, Part-1
VR-3C-SLB-P1.105 Room Top Slab Formwork Installation 6 30-Jan-25 06-Feb-25 Room Top Slab Formwork Installation

VR-3C-SLB-P1.115 Room Top Slab Rebar Installation 6 06-Feb-25 13-Feb-25 Room Top Slab Rebar Installation

VR-3C-SLB-P1.125 Room Top Slab Concrete Casting 1 13-Feb-25 15-Feb-25 Room Top Slab Concrete Casting

VR-3C-SLB-P1.135 Room Top slab Curing work 12 15-Feb-25 01-Mar-25 Room Top slab Curing work

VR-3C-SLB-P1.145 Room Top Slab Formwork Removel 4 01-Mar-25 05-Mar-25 Room Top Slab Formwork Removel

Part-2 29 23-Feb-25 29-Mar-25 29-Mar-25, Part-2


VR-3C-SLB-P2.125 Room Top Slab Formwork Installation 6 23-Feb-25 02-Mar-25 Room Top Slab Formwork Installation

VR-3C-SLB-P2.130 Room Top Slab Rebar Installation 6 02-Mar-25 09-Mar-25 Room Top Slab Rebar Installation

VR-3C-SLB-P2.135 Room Top Slab Concrete Casting 1 09-Mar-25 10-Mar-25 Room Top Slab Concrete Casting

VR-3C-SLB-P2.140 Room Top slab Curing work 12 10-Mar-25 24-Mar-25 Room Top slab Curing work

VR-3C-SLB-P2.145 Room Top Slab Formwork Removel 4 24-Mar-25 29-Mar-25 Room Top Slab Formwork Removel

WATER PROOFING 36 03-Mar-25 19-Apr-25 19-Apr-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 03-Mar-25 15-Mar-25 15-Mar-25, WALL WATER PROOFING STAGE-1

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
39 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR-3C-WP-WL-S1.115Surface preparation work 2 03-Mar-25 05-Mar-25 Surface preparation work

VR-3C-WP-WL-S1.120Applying of waterproofing material 3 05-Mar-25 09-Mar-25 Applying of waterproofing material

VR-3C-WP-WL-S1.125VR Back filling 5 09-Mar-25 15-Mar-25 VR Back filling

WALL WATER PROOFING STAGE-2 13 05-Mar-25 20-Mar-25 20-Mar-25, WALL WATER PROOFING STAGE-2
VR-3C-WP-WL-S2.115Surface preparation work 2 05-Mar-25 08-Mar-25 Surface preparation work

VR-3C-WP-WL-S2.120Applying of waterproofing material 3 08-Mar-25 11-Mar-25 Applying of waterproofing material

VR-3C-WP-WL-S2.125VR Back filling 5 15-Mar-25 20-Mar-25 VR Back filling

WALL WATER PROOFING STAGE-3 16 08-Mar-25 26-Mar-25 26-Mar-25, WALL WATER PROOFING STAGE-3
VR-3C-WP-WL-S3.115Surface preparation work 2 08-Mar-25 10-Mar-25 Surface preparation work

VR-3C-WP-WL-S3.120Applying of waterproofing material 3 10-Mar-25 13-Mar-25 Applying of waterproofing material

VR-3C-WP-WL-S3.125VR Back filling 5 20-Mar-25 26-Mar-25 VR Back filling

WALL WATER PROOFING STAGE-4 19 10-Mar-25 06-Apr-25 06-Apr-25, WALL WATER PROOFING STAGE-4
VR-3C-WP-WL-S4.115Surface preparation work 2 10-Mar-25 12-Mar-25 Surface preparation work

VR-3C-WP-WL-S4.120Applying of waterproofing material 3 12-Mar-25 16-Mar-25 Applying of waterproofing material

VR-3C-WP-WL-S4.125VR Back filling 5 26-Mar-25 06-Apr-25 VR Back filling

TOP SLAB WATER PROOFING 14 29-Mar-25 19-Apr-25 19-Apr-25, TOP SLAB WATER PROOFING
VR-3C-WP-SLB-S1.115
Surface preparation work 4 29-Mar-25 07-Apr-25 Surface preparation work

VR-3C-WP-SLB-S1.120
Applying of waterproofing material 9 07-Apr-25 17-Apr-25 Applying of waterproofing material

VR-3C-WP-SLB-S1.125
Leak Test 1 17-Apr-25 19-Apr-25 Leak Test

MECHANICAL ROOM MEP 77 29-Mar-25 05-Jul-25 05-Jul-25, MECHANICAL ROOM MEP


MECHANICAL WORK IN ROOM 68 29-Mar-25 24-Jun-25 24-Jun-25, MECHANICAL WORK IN ROOM
FIRE FIGHTING 24 29-Mar-25 30-Apr-25 30-Apr-25, FIRE FIGHTING
VTR-3C-MFF.105 Fire Fighting system Pipe and accessories installation 21 29-Mar-25 27-Apr-25 Fire Fighting system Pipe and accessories installation

VTR-3C-MFF.115 Fire Fighting system deluge valve installation 16 08-Apr-25 27-Apr-25 Fire Fighting system deluge valve installation

VTR-3C-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 20-Apr-25 27-Apr-25 Fire Fighting system fire hose cabinet/extingusher installation

VTR-3C-MFF.140 Fire Fighting system initial testing 3 27-Apr-25 30-Apr-25 Fire Fighting system initial testing

VTR-3C-MFF.145 Fire Fighting clean agent system 2 24-Apr-25 27-Apr-25 Fire Fighting clean agent system

HVAC 47 27-Apr-25 24-Jun-25 24-Jun-25, HVAC


VTR-3C-MHV.115 Air conditioning system installation 12 29-May-25 16-Jun-25 Air conditioning system installation

VTR-3C-MHV.120 Fan installation 15 26-May-25 16-Jun-25 Fan installation

VTR-3C-MHV.125 Duct and accessories installation 28 27-Apr-25 29-May-25 Duct and accessories installation

VTR-3C-MHV.135 HVAC inital testing 7 16-Jun-25 24-Jun-25 HVAC inital testing

PLUMBING 8 27-Apr-25 06-May-25 06-May-25, PLUMBING


VTR-3C-MPL.105 Plumbing drainage system installation 6 27-Apr-25 04-May-25 Plumbing drainage system installation

VTR-3C-MPL.115 Plumbing drainage system initial testing 2 04-May-25 06-May-25 Plumbing drainage system initial testing

ELECTRICAL WORK IN ROOM 56 27-Apr-25 05-Jul-25 05-Jul-25, ELECTRICAL WORK IN ROOM


POWER SYSTEM 53 27-Apr-25 01-Jul-25 01-Jul-25, POWER SYSTEM
EARTHING SYSTEM 25 27-Apr-25 26-May-25 26-May-25, EARTHING SYSTEM
VTR-3C-EES-105 Earthing system soil resistivity test 6 27-Apr-25 04-May-25 Earthing system soil resistivity test

VTR-3C-EES-115 Earthing system Copper rod/ earthing pit installation 8 04-May-25 13-May-25 Earthing system Copper rod/ earthing pit installation

VTR-3C-EES-125 Earthing system Termination 6 13-May-25 20-May-25 Earthing system Termination

VTR-3C-EES-135 Earthing system Initial Testing 5 20-May-25 26-May-25 Earthing system Initial Testing

LIGHTING SYSTEM 37 04-May-25 18-Jun-25 18-Jun-25, LIGHTING SYSTEM


VTR-3C-ELI.105 Lighting system Conduit and boxes Installation 8 04-May-25 13-May-25 Lighting system Conduit and boxes Installation

VTR-3C-ELI.115 Lighting system Cable Pulling 8 13-May-25 22-May-25 Lighting system Cable Pulling

VTR-3C-ELI.125 Lighting system Installations 8 22-May-25 01-Jun-25 Lighting system Installations

VTR-3C-ELI.135 Lighting system Termination 8 01-Jun-25 12-Jun-25 Lighting system Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
40 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3C-ELI.145 Lighting system Initial Testing 5 14-Jun-25 18-Jun-25 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 04-May-25 01-Jul-25 01-Jul-25, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-3C-ECT.105 Cable Tray Installation 10 04-May-25 15-May-25 Cable Tray Installation

VTR-3C-ECT.115 Cable Tray Inspection 10 15-May-25 27-May-25 Cable Tray Inspection

VTR-3C-ECT.125 LV Cable pulling 10 27-May-25 11-Jun-25 LV Cable pulling

VTR-3C-ECT.135 LV Cable Termination 10 11-Jun-25 22-Jun-25 LV Cable Termination

VTR-3C-ECT.145 LV Cable Initial Testing 8 23-Jun-25 01-Jul-25 LV Cable Initial Testing

SMALL POWER SYSTEM 39 04-May-25 21-Jun-25 21-Jun-25, SMALL POWER SYSTEM


VTR-3C-ESP.105 Small Power Conduit and boxes Installation 12 04-May-25 18-May-25 Small Power Conduit and boxes Installation

VTR-3C-ESP.115 Small Power Cable Pulling 10 18-May-25 29-May-25 Small Power Cable Pulling

VTR-3C-ESP.125 Small Power Installations 6 29-May-25 09-Jun-25 Small Power Installations

VTR-3C-ESP.135 Small Power Termination 6 09-Jun-25 15-Jun-25 Small Power Termination

VTR-3C-ESP.145 Small Power Initial Testing 5 16-Jun-25 21-Jun-25 Small Power Initial Testing

POWER DISTRIBUTION 39 04-May-25 22-Jun-25 22-Jun-25, POWER DISTRIBUTION


GENERATOR 39 04-May-25 22-Jun-25 22-Jun-25, GENERATOR
VTR-3C-EPD.105 Generator Cable Tray Installation 7 04-May-25 12-May-25 Generator Cable Tray Installation

VTR-3C-EPD.115 Generator Cable Pulling 7 12-May-25 20-May-25 Generator Cable Pulling

VTR-3C-EPD.125 Generator Cell Pannel Installation 7 20-May-25 28-May-25 Generator Cell Pannel Installation

VTR-3C-EPD.135 Generator Installation 7 28-May-25 04-Jun-25 Generator Installation

VTR-3C-EPD.145 Generator Pannel / Cable Termination 7 09-Jun-25 16-Jun-25 Generator Pannel / Cable Termination

VTR-3C-EPD.155 Generator Pannel / Cable initial Testing 5 16-Jun-25 22-Jun-25 Generator Pannel / Cable initial Testing

UPS 28 12-May-25 17-Jun-25 17-Jun-25, UPS


VTR-3C-EPD.165 UPS Cable Tray Installation 5 12-May-25 18-May-25 UPS Cable Tray Installation

VTR-3C-EPD.175 UPS Cable Pulling 5 18-May-25 24-May-25 UPS Cable Pulling

VTR-3C-EPD.185 UPS Pannel Installation 5 24-May-25 28-May-25 UPS Pannel Installation

VTR-3C-EPD.195 UPS Installation 5 29-May-25 03-Jun-25 UPS Installation

VTR-3C-EPD.205 UPS Pannel / Cable Termination 5 03-Jun-25 12-Jun-25 UPS Pannel / Cable Termination

VTR-3C-EPD.215 UPS Pannel / Cable initial Testing 4 12-Jun-25 17-Jun-25 UPS Pannel / Cable initial Testing

MDB 33 12-May-25 22-Jun-25 22-Jun-25, MDB


VTR-3C-EPD.225 MDB Cable Tray Installation 7 12-May-25 20-May-25 MDB Cable Tray Installation

VTR-3C-EPD.235 MDB Cable Pulling 7 20-May-25 28-May-25 MDB Cable Pulling

VTR-3C-EPD.245 MDB Pannel Installation 7 28-May-25 04-Jun-25 MDB Pannel Installation

VTR-3C-EPD.255 MDB Pannel / Cable Termination 7 09-Jun-25 16-Jun-25 MDB Pannel / Cable Termination

VTR-3C-EPD.265 MDB Pannel / Cable initial Testing 5 16-Jun-25 22-Jun-25 MDB Pannel / Cable initial Testing

MCC 33 12-May-25 22-Jun-25 22-Jun-25, MCC


VTR-3C-EPD.325 MCC Cable Tray Installation 7 12-May-25 20-May-25 MCC Cable Tray Installation

VTR-3C-EPD.335 MCC Cable Pulling 7 20-May-25 28-May-25 MCC Cable Pulling

VTR-3C-EPD.345 MCC Pannel Installation 7 28-May-25 04-Jun-25 MCC Pannel Installation

VTR-3C-EPD.355 MCC Pannel / Cable Termination 7 09-Jun-25 16-Jun-25 MCC Pannel / Cable Termination

VTR-3C-EPD.365 MCC Pannel / Cable initial Testing 5 16-Jun-25 22-Jun-25 MCC Pannel / Cable initial Testing

SMSB 24 12-May-25 11-Jun-25 11-Jun-25, SMSB


VTR-3C-EPD.275 SMSB Cable Tray Installation 5 12-May-25 18-May-25 SMSB Cable Tray Installation

VTR-3C-EPD.285 SMSB Cable Pulling 5 18-May-25 24-May-25 SMSB Cable Pulling

VTR-3C-EPD.295 SMSB Pannel Installation 5 24-May-25 28-May-25 SMSB Pannel Installation

VTR-3C-EPD.305 SMSB Pannel / Cable Termination 5 29-May-25 03-Jun-25 SMSB Pannel / Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
41 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3C-EPD.315 SMSB Pannel / Cable initial Testing 4 03-Jun-25 11-Jun-25 SMSB Pannel / Cable initial Testing

DB 24 12-May-25 11-Jun-25 11-Jun-25, DB


VTR-3C-EPD.375 DB Cable Tray Installation 5 12-May-25 18-May-25 DB Cable Tray Installation

VTR-3C-EPD.385 DB Cable Pulling 5 18-May-25 24-May-25 DB Cable Pulling

VTR-3C-EPD.395 DB Pannel Installation 5 24-May-25 28-May-25 DB Pannel Installation

VTR-3C-EPD.405 DB Pannel / Cable Termination 5 29-May-25 03-Jun-25 DB Pannel / Cable Termination

VTR-3C-EPD.415 DB Pannel / Cable initial Testing 4 03-Jun-25 11-Jun-25 DB Pannel / Cable initial Testing

ISOLATOR 24 12-May-25 11-Jun-25 11-Jun-25, ISOLATOR


VTR-3C-EPD.425 Isolators Cable Tray Installation 5 12-May-25 18-May-25 Isolators Cable Tray Installation

VTR-3C-EPD.435 Isolators Cable Pulling 5 18-May-25 24-May-25 Isolators Cable Pulling

VTR-3C-EPD.445 Isolators Pannel Installation 5 24-May-25 28-May-25 Isolators Pannel Installation

VTR-3C-EPD.455 Isolators Pannel / Cable Termination 5 29-May-25 03-Jun-25 Isolators Pannel / Cable Termination

VTR-3C-EPD.465 Isolators Pannel / Cable initial Testing 4 03-Jun-25 11-Jun-25 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 12-May-25 11-Jun-25 11-Jun-25, LCP/ ELCP


VTR-3C-EPD.475 LCP/ELCP Cable Tray Installation 5 12-May-25 18-May-25 LCP/ELCP Cable Tray Installation

VTR-3C-EPD.485 LCP/ELCP Cable Pulling 5 18-May-25 24-May-25 LCP/ELCP Cable Pulling

VTR-3C-EPD.495 LCP/ELCP Pannel Installation 5 24-May-25 28-May-25 LCP/ELCP Pannel Installation

VTR-3C-EPD.505 LCP/ELCP Pannel / Cable Termination 5 29-May-25 03-Jun-25 LCP/ELCP Pannel / Cable Termination

VTR-3C-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 03-Jun-25 11-Jun-25 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 04-May-25 05-Jul-25 05-Jul-25, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 04-May-25 24-Jun-25 24-Jun-25, FIRE ALARM SYSTEM
VTR-3C-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 04-May-25 14-May-25 Fire Alarm Conduit /Cable Tray Installation

VTR-3C-ELFA.115 Fire Alarm Cable Pulling 9 14-May-25 25-May-25 Fire Alarm Cable Pulling

VTR-3C-ELFA.125 Fire Alarm Devices Installation 9 25-May-25 04-Jun-25 Fire Alarm Devices Installation

VTR-3C-ELFA.135 Fire Alarm Devices and Cable Termination 9 04-Jun-25 17-Jun-25 Fire Alarm Devices and Cable Termination

VTR-3C-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 18-Jun-25 24-Jun-25 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 04-May-25 24-Jun-25 24-Jun-25, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-3C-ELVS.105 ICT System Conduit /Cable Tray Installation 9 04-May-25 14-May-25 ICT System Conduit /Cable Tray Installation

VTR-3C-ELVS.115 ICT System Cable Pulling 9 14-May-25 25-May-25 ICT System Cable Pulling

VTR-3C-ELVS.125 ICT System Devices Installation 9 25-May-25 04-Jun-25 ICT System Devices Installation

VTR-3C-ELVS.135 ICT System Devices and Cable Termination 9 04-Jun-25 17-Jun-25 ICT System Devices and Cable Termination

VTR-3C-ELVS.145 ICT System Devices and Cable initial Testing 6 18-Jun-25 24-Jun-25 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 14-May-25 05-Jul-25 05-Jul-25, ACCESS CONTROL SYSTEM


VTR-3C-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 14-May-25 25-May-25 Access Control System Conduit /Cable Tray Installation

VTR-3C-ELAC.115 Access Control System Cable Pulling 9 25-May-25 04-Jun-25 Access Control System Cable Pulling

VTR-3C-ELAC.125 Access Control System Devices Installation 9 04-Jun-25 17-Jun-25 Access Control System Devices Installation

VTR-3C-ELAC.135 Access Control System Devices and Cable Termination 9 18-Jun-25 28-Jun-25 Access Control System Devices and Cable Termination

VTR-3C-ELAC.145 Access Control System Devices and Cable initial Testing 6 28-Jun-25 05-Jul-25 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 14-May-25 05-Jul-25 05-Jul-25, PUBLIC ADDRESS SYSTEM


VTR-3C-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 14-May-25 25-May-25 Public Address System Conduit /Cable Tray Installation

VTR-3C-ELPA.115 Public Address System Cable Pulling 9 25-May-25 04-Jun-25 Public Address System Cable Pulling

VTR-3C-ELPA.125 Public Address System Devices Installation 9 04-Jun-25 17-Jun-25 Public Address System Devices Installation

VTR-3C-ELPA.135 Public Address System Devices and Cable Termination 9 18-Jun-25 28-Jun-25 Public Address System Devices and Cable Termination

VTR-3C-ELPA.145 Public Address System Devices and Cable initial Testing 6 28-Jun-25 05-Jul-25 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 14-May-25 05-Jul-25 05-Jul-25, SCADA SYSTEM


VTR-3C-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 14-May-25 25-May-25 SCADA System Conduit /Cable Tray Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
42 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3C-ELSC.115 SCADA System Cable Pulling 9 25-May-25 04-Jun-25 SCADA System Cable Pulling

VTR-3C-ELSC.125 SCADA System Devices Installation 9 04-Jun-25 17-Jun-25 SCADA System Devices Installation

VTR-3C-ELSC.135 SCADA System Devices and Cable Termination 9 18-Jun-25 28-Jun-25 SCADA System Devices and Cable Termination

VTR-3C-ELSC.145 SCADA System Devices and Cable initial Testing 6 28-Jun-25 05-Jul-25 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 14-May-25 05-Jul-25 05-Jul-25, RADIO RE- BROADCOASTING/ TETRA
VTR-3C-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 14-May-25 25-May-25 Radio/TETRA System Conduit /Cable Tray Installation

VTR-3C-ELRD.115 Radio/TETRA System Cable Pulling 9 25-May-25 04-Jun-25 Radio/TETRA System Cable Pulling

VTR-3C-ELRD.125 Radio/TETRA System Devices Installation 9 04-Jun-25 17-Jun-25 Radio/TETRA System Devices Installation

VTR-3C-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 18-Jun-25 28-Jun-25 Radio/TETRA System Devices and Cable Termination

VTR-3C-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 28-Jun-25 05-Jul-25 Radio/TETRA System Devices and Cable initial Testing

DRY UTILITIES 25 14-May-25 16-Jun-25 16-Jun-25, DRY UTILITIES


POWER 25 14-May-25 16-Jun-25 16-Jun-25, POWER
POWER LV 16 14-May-25 02-Jun-25 02-Jun-25, POWER LV
DU-P-LV.210 Installation of support 1 14-May-25 15-May-25 Installation of support

DU-P-LV.215 Installation of horizontal busbar 2 15-May-25 17-May-25 Installation of horizontal busbar

DU-P-LV.220 Installation of vertical busbar 2 17-May-25 19-May-25 Installation of vertical busbar

DU-P-LV.225 Installation of left/right elbow 2 19-May-25 20-May-25 Installation of left/right elbow

DU-P-LV.230 Installation of right horizintal offset 2 20-May-25 22-May-25 Installation of right horizintal offset

DU-P-LV.235 Instalaltion of upward vertical offset 3 22-May-25 26-May-25 Instalaltion of upward vertical offset

DU-P-LV.240 Installation of downward vertical offset 3 26-May-25 29-May-25 Installation of downward vertical offset

DU-P-LV.245 Installation of transformer and panel connection 2 29-May-25 02-Jun-25 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 15-May-25 04-Jun-25 04-Jun-25, MEDIUM VOLTAGE


DU-P-MV.210 Installation of cable try, arm, racks and ladder 6 15-May-25 22-May-25 Installation of cable try, arm, racks and ladder

DU-P-MV.215 Installation of MV Cable 4 22-May-25 27-May-25 Installation of MV Cable

DU-P-MV.220 Installation of cable cleats 2 27-May-25 29-May-25 Installation of cable cleats

DU-P-MV.225 Installation of gland 1 29-May-25 29-May-25 Installation of gland

DU-P-MV.230 splicing/termination of MV cable 2 29-May-25 01-Jun-25 splicing/termination of MV cable

DU-P-MV.235 Testing and Pre-commissioning of cable 2 01-Jun-25 03-Jun-25 Testing and Pre-commissioning of cable

DU-P-MV.240 Energezation 2 03-Jun-25 04-Jun-25 Energezation

TRANSFORMER 16 22-May-25 14-Jun-25 14-Jun-25, TRANSFORMER


DU-P-T.210 Installation of Transformer unit 2 22-May-25 25-May-25 Installation of Transformer unit

DU-P-T.215 Testing and Pre-Commissioning of unit 1 25-May-25 25-May-25 Testing and Pre-Commissioning of unit

DU-P-T.220 Termination and Splicing of MV Cable 3 25-May-25 29-May-25 Termination and Splicing of MV Cable

DU-P-T.225 Termination and Splicing of LV Cable/bus way 3 29-May-25 02-Jun-25 Termination and Splicing of LV Cable/bus way

DU-P-T.230 Installation and connection of I/O system 2 02-Jun-25 04-Jun-25 Installation and connection of I/O system

DU-P-T.235 Installation of Grounding and Protection System 2 04-Jun-25 11-Jun-25 Installation of Grounding and Protection System

DU-P-T.240 Testing and Commissioning of MV System 1 11-Jun-25 11-Jun-25 Testing and Commissioning of MV System

DU-P-T.245 Testing and Commissioning of LV System 1 11-Jun-25 12-Jun-25 Testing and Commissioning of LV System

DU-P-T.250 Energezation 1 12-Jun-25 14-Jun-25 Energezation

RMU 16 25-May-25 16-Jun-25 16-Jun-25, RMU


DU-P-RMU.210 Installation RMU unit 2 25-May-25 27-May-25 Installation RMU unit

DU-P-RMU.215 Testing and Pre-Commissioning of unit 2 27-May-25 29-May-25 Testing and Pre-Commissioning of unit

DU-P-RMU.220 Termination and Splicing of Ring-MV Cable 4 29-May-25 03-Jun-25 Termination and Splicing of Ring-MV Cable

DU-P-RMU.225 Termination and Splicing of T-MV Cable 4 03-Jun-25 11-Jun-25 Termination and Splicing of T-MV Cable

DU-P-RMU.230 Installation of Grounding and Protection System 2 11-Jun-25 14-Jun-25 Installation of Grounding and Protection System

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
43 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-RMU.235 Testing and Commissioning of MV System 1 14-Jun-25 15-Jun-25 Testing and Commissioning of MV System

DU-P-RMU.240 Energezation 1 15-Jun-25 16-Jun-25 Energezation

VECHICULAR ROOM 3A (IN ZONE 09) 476 24-May-23 14-Dec-24 14-Dec-24, VECHICULAR ROOM 3A (IN ZONE 09)
ENGINEERING 153 24-May-23 22-Nov-23 22-Nov-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 153 24-May-23 22-Nov-23 22-Nov-23, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 153 24-May-23 22-Nov-23 22-Nov-23, EARTH WORKS
T1-ENG-VR3A-SI.872 Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

T1-ENG-VR3A-SI.873 Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

T1-ENG-VR3A-SI.875 Soil Improvement Design Preparation & Submission 14 22-Oct-23 06-Nov-23 Soil Improvement Design Preparation & Submission

T1-ENG-VR3A-SI.880 Soil Improvement Design Review & Approval 14 06-Nov-23 22-Nov-23 Soil Improvement Design Review & Approval

T1-ENG-VR3A-SI.885 Shoring drawings Preparation & Submission 12 24-May-23 06-Jun-23 Shoring drawings Preparation & Submission

T1-ENG-VR3A-SI.890 Shoring shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Shoring shop drawings Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VTR-3A-ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VTR-3A-ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VTR-3A-ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VTR-3A-ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VTR-3A-ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VTR-3A-ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VTR-3A-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VTR-3A-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VTR-3A-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VTR-3A-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VTR-3A-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VTR-3A-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VTR-3A-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VTR-3A-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VTR-3A-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VTR-3A-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VTR-3A-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VTR-3A-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VTR-3A-ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VTR-3A-ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 14-Aug-23 13-Sep-23 13-Sep-23, LIGHTNING PROTECTION SYSTEM


VTR-3A-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 14-Aug-23 30-Aug-23 Lightning Protection Drawings Preparation & Submission

VTR-3A-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 30-Aug-23 13-Sep-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 30-Aug-23 01-Oct-23 01-Oct-23, EARTHING SYSTEM


VTR-3A-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 30-Aug-23 16-Sep-23 Earthing System Shop Drawings Preparation & Submission

VTR-3A-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 16-Sep-23 01-Oct-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
44 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VTR-3A-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VTR-3A-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VTR-3A-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VTR-3A-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VTR-3A-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VTR-3A-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VTR-3A-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VTR-3A-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILTIES 151 24-May-23 20-Nov-23 20-Nov-23, DRY UTILTIES


POWER 151 24-May-23 20-Nov-23 20-Nov-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.300 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.305 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.300 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.305 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.300 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.305 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.300 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.305 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

MRMU 31 28-Aug-23 04-Oct-23 04-Oct-23, MRMU


DU-P-MRMU.300 Prepare and submit MRMU shopdrawings 20 28-Aug-23 20-Sep-23 Prepare and submit MRMU shopdrawings

DU-P-MRMU.305 Review and approval MRMU shopdrawings 11 20-Sep-23 04-Oct-23 Review and approval MRMU shopdrawings

MVSG 31 20-Sep-23 28-Oct-23 28-Oct-23, MVSG


DU-P-MVSG.300 Prepare and submit MVSG shopdrawings 20 20-Sep-23 15-Oct-23 Prepare and submit MVSG shopdrawings

DU-P-MVSG.305 Review and approval MVSG shopdrawings 11 15-Oct-23 28-Oct-23 Review and approval MVSG shopdrawings

BATTERY ROOM 31 15-Oct-23 20-Nov-23 20-Nov-23, BATTERY ROOM


DU-P-BARM.300 Prepare and submit Battery room shopdrawings 20 15-Oct-23 07-Nov-23 Prepare and submit Battery room shopdrawings

DU-P-BARM.305 Review and approval Battery room shopdrawings 11 07-Nov-23 20-Nov-23 Review and approval Battery room shopdrawings

PROCUREMENT 269 15-Jan-24 04-Dec-24 04-Dec-24, PROCUREMENT


CIVIL/STRUCTURAL 16 15-Jan-24 03-Feb-24 03-Feb-24, CIVIL/STRUCTURAL
VTR-3A-PRO-CV.110 Issue Purchase Order 6 15-Jan-24 22-Jan-24 Issue Purchase Order

VTR-3A-PRO-CV.115 Material Delivery 10 22-Jan-24 03-Feb-24 Material Delivery

MECHANICAL 166 19-May-24 04-Dec-24 04-Dec-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 19-May-24 24-Sep-24 24-Sep-24, FIRE FIGHTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
45 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 19-May-24 24-Sep-24 24-Sep-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VTR-3A-PR-MC-FF.110
Issue Purchase Order 15 19-May-24 05-Jun-24 Issue Purchase Order

VTR-3A-PR-MC-FF.115
Material Delivery 90 05-Jun-24 24-Sep-24 Material Delivery

VENTILATION SYSTEM 105 20-Jul-24 20-Nov-24 20-Nov-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 20-Jul-24 20-Nov-24 20-Nov-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VTR-3A-PR-MC-DS.110
Issue Purchase Order 15 20-Jul-24 06-Aug-24 Issue Purchase Order

VTR-3A-PR-MC-DS.115
Material Delivery 90 06-Aug-24 20-Nov-24 Material Delivery

AIR CONDITIONING WORKS 105 20-Jul-24 20-Nov-24 20-Nov-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 20-Jul-24 20-Nov-24 20-Nov-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VTR-3A-PR-MC-AC.110
Issue Purchase Order 15 20-Jul-24 06-Aug-24 Issue Purchase Order

VTR-3A-PR-MC-AC.115
Material Delivery 90 06-Aug-24 20-Nov-24 Material Delivery

PLUMBING SYSTEM 105 03-Aug-24 04-Dec-24 04-Dec-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 03-Aug-24 04-Dec-24 04-Dec-24, PUMPS,PIPES,FITTINGS,VALVES
VTR-3A-PR-MC-PI.110
Issue Purchase Order 15 03-Aug-24 20-Aug-24 Issue Purchase Order

VTR-3A-PR-MC-PI.115
Material Delivery 90 20-Aug-24 04-Dec-24 Material Delivery

ELECTRICAL 142 04-May-24 21-Oct-24 21-Oct-24, ELECTRICAL


CABLE TRAY 105 11-May-24 15-Sep-24 15-Sep-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 11-May-24 15-Sep-24 15-Sep-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
VTR-3A-PR-EL-CT.110
Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VTR-3A-PR-EL-CT.115
Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

POWER CABLES 105 11-May-24 15-Sep-24 15-Sep-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 11-May-24 15-Sep-24 15-Sep-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VTR-3A-PR-EL-PC.110
Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VTR-3A-PR-EL-PC.115
Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

LIGHTING SYSTEM 105 11-May-24 15-Sep-24 15-Sep-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 11-May-24 15-Sep-24 15-Sep-24, CONDUIT,LIGHT
VTR-3A-PR-EL-LS.110
Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VTR-3A-PR-EL-LS.115
Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 11-May-24 15-Sep-24 15-Sep-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 11-May-24 15-Sep-24 15-Sep-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VTR-3A-PR-EL-EI.110Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VTR-3A-PR-EL-EI.115Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, LIGHTNING PROTECTION SYSTEM
VTR-3A-PR-EL-LP.110Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

VTR-3A-PR-EL-LP.115Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 04-May-24 08-Sep-24 08-Sep-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VTR-3A-PR-EL-ES.110
Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

VTR-3A-PR-EL-ES.115
Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

LOW CURRENT 114 05-Jun-24 21-Oct-24 21-Oct-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 05-Jun-24 10-Oct-24 10-Oct-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 05-Jun-24 10-Oct-24 10-Oct-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VTR-3A-PR-ELL-FA.20
Issue Purchase Order 15 05-Jun-24 26-Jun-24 Issue Purchase Order

VTR-3A-PR-ELL-FA.25
Material Delivery 90 27-Jun-24 10-Oct-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 19-Jun-24 21-Oct-24 21-Oct-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 19-Jun-24 21-Oct-24 21-Oct-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VTR-3A-PR-ELL-PH.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-PH.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 19-Jun-24 21-Oct-24 21-Oct-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 19-Jun-24 21-Oct-24 21-Oct-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
46 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-PR-ELL-PA.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-PA.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

VIDEO SURVEILLANCE 105 19-Jun-24 21-Oct-24 21-Oct-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 19-Jun-24 21-Oct-24 21-Oct-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VTR-3A-PR-ELL-VS.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-VS.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

ACCESS CONTROL SYSTEM 105 19-Jun-24 21-Oct-24 21-Oct-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 19-Jun-24 21-Oct-24 21-Oct-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
VTR-3A-PR-ELL-AC.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-AC.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 19-Jun-24 21-Oct-24 21-Oct-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 19-Jun-24 21-Oct-24 21-Oct-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VTR-3A-PR-ELL-RB.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-RB.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

SCADA SYSTEM 105 19-Jun-24 21-Oct-24 21-Oct-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 19-Jun-24 21-Oct-24 21-Oct-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VTR-3A-PR-ELL-SD.20
Issue Purchase Order 15 19-Jun-24 07-Jul-24 Issue Purchase Order

VTR-3A-PR-ELL-SD.25
Material Delivery 90 07-Jul-24 21-Oct-24 Material Delivery

CONSTRUCTION 452 21-Jun-23 14-Dec-24 14-Dec-24, CONSTRUCTION


EXCAVATION WORKS 101 21-Jun-23 21-Oct-23 21-Oct-23, EXCAVATION WORKS
T1-CON-VR3A-EX.190Excavation & shoring 35 10-Sep-23 21-Oct-23 Excavation & shoring

T1-CON-VR3A-EX.195Piles (110 Nos.) 36 21-Jun-23 05-Aug-23 Piles (110 Nos.)

T1-CON-VR3A-EX.200Capping Beam 20 06-Aug-23 28-Aug-23 Capping Beam

T1-CON-VR3A-EX.205Anchors 10 29-Aug-23 09-Sep-23 Anchors

SOIL IMPROVEMENT WORKS 30 22-Nov-23 27-Dec-23 27-Dec-23, SOIL IMPROVEMENT WORKS


T1-CON-VR3A-SI.210 Soil Improvement 30 22-Nov-23 27-Dec-23 Soil Improvement

STRUCTURAL WORKS 266 27-Jan-24 10-Dec-24 10-Dec-24, STRUCTURAL WORKS


FOUNDATION 36 27-Jan-24 09-Mar-24 09-Mar-24, FOUNDATION
Part-1 23 27-Jan-24 21-Feb-24 21-Feb-24, Part-1
VTR-3A-FDN-P1.150 Foundation Blinding concrete casting casting 1 27-Jan-24 27-Jan-24 Foundation Blinding concrete casting casting

VTR-3A-FDN-P1.155 Foundation water proofing on blinding concrete 3 28-Jan-24 30-Jan-24 Foundation water proofing on blinding concrete

VTR-3A-FDN-P1.160 Foundation Protection screed on water poofing 1 30-Jan-24 31-Jan-24 Foundation Protection screed on water poofing

VTR-3A-FDN-P1.165 Foundation Curing for screed 2 31-Jan-24 03-Feb-24 Foundation Curing for screed

VTR-3A-FDN-P1.170 Foundation Rebar installation 6 03-Feb-24 10-Feb-24 Foundation Rebar installation

VTR-3A-FDN-P1.175 Foundation Formwork installation 4 10-Feb-24 14-Feb-24 Foundation Formwork installation

VTR-3A-FDN-P1.180 Foundation Construction joint work 2 14-Feb-24 17-Feb-24 Foundation Construction joint work

VTR-3A-FDN-P1.185 Foundation concrete casting 1 17-Feb-24 18-Feb-24 Foundation concrete casting

VTR-3A-FDN-P1.190 Foundation concrete curing 1 18-Feb-24 19-Feb-24 Foundation concrete curing

VTR-3A-FDN-P1.195 Foundation Formwork Removal 2 19-Feb-24 21-Feb-24 Foundation Formwork Removal

Part-2 23 03-Feb-24 29-Feb-24 29-Feb-24, Part-2


VTR-3A-FDN-P2.150 Foundation Blinding concrete casting casting 1 03-Feb-24 04-Feb-24 Foundation Blinding concrete casting casting

VTR-3A-FDN-P2.155 Foundation water proofing on blinding concrete 3 04-Feb-24 07-Feb-24 Foundation water proofing on blinding concrete

VTR-3A-FDN-P2.160 Foundation Protection screed on water poofing 1 07-Feb-24 08-Feb-24 Foundation Protection screed on water poofing

VTR-3A-FDN-P2.165 Foundation Curing for screed 2 08-Feb-24 11-Feb-24 Foundation Curing for screed

VTR-3A-FDN-P2.170 Foundation Rebar installation 6 11-Feb-24 18-Feb-24 Foundation Rebar installation

VTR-3A-FDN-P2.175 Foundation Formwork installation 4 18-Feb-24 22-Feb-24 Foundation Formwork installation

VTR-3A-FDN-P2.180 Foundation Construction joint work 2 22-Feb-24 25-Feb-24 Foundation Construction joint work

VTR-3A-FDN-P2.185 Foundation concrete casting 1 25-Feb-24 26-Feb-24 Foundation concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
47 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-FDN-P2.190 Foundation concrete curing 1 26-Feb-24 27-Feb-24 Foundation concrete curing

VTR-3A-FDN-P2.195 Foundation Formwork Removal 2 27-Feb-24 29-Feb-24 Foundation Formwork Removal

Part-3 23 11-Feb-24 09-Mar-24 09-Mar-24, Part-3


VTR-3A-FDN-P3.150 Foundation Blinding concrete casting casting 1 11-Feb-24 12-Feb-24 Foundation Blinding concrete casting casting

VTR-3A-FDN-P3.155 Foundation water proofing on blinding concrete 3 12-Feb-24 15-Feb-24 Foundation water proofing on blinding concrete

VTR-3A-FDN-P3.160 Foundation Protection screed on water poofing 1 15-Feb-24 17-Feb-24 Foundation Protection screed on water poofing

VTR-3A-FDN-P3.165 Foundation Curing for screed 2 17-Feb-24 19-Feb-24 Foundation Curing for screed

VTR-3A-FDN-P3.170 Foundation Rebar installation 6 19-Feb-24 26-Feb-24 Foundation Rebar installation

VTR-3A-FDN-P3.175 Foundation Formwork installation 4 26-Feb-24 02-Mar-24 Foundation Formwork installation

VTR-3A-FDN-P3.180 Foundation Construction joint work 2 02-Mar-24 04-Mar-24 Foundation Construction joint work

VTR-3A-FDN-P3.185 Foundation concrete casting 1 04-Mar-24 05-Mar-24 Foundation concrete casting

VTR-3A-FDN-P3.190 Foundation concrete curing 1 05-Mar-24 06-Mar-24 Foundation concrete curing

VTR-3A-FDN-P3.195 Foundation Formwork Removal 2 06-Mar-24 09-Mar-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 45 18-Feb-24 14-Apr-24 14-Apr-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 45 18-Feb-24 14-Apr-24 14-Apr-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 18-Feb-24 24-Mar-24 24-Mar-24, Part-1
VTR-3A-WL-S1-P1.135
Room Walls Rebar Installation 8 24-Feb-24 04-Mar-24 Room Walls Rebar Installation

VTR-3A-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 04-Mar-24 06-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S1-P1.145
Room Walls Formwork Installation 10 06-Mar-24 18-Mar-24 Room Walls Formwork Installation

VTR-3A-WL-S1-P1.150
Room Walls Concrete Casting 1 18-Mar-24 19-Mar-24 Room Walls Concrete Casting

VTR-3A-WL-S1-P1.155
Room Walls Curing work 1 19-Mar-24 20-Mar-24 Room Walls Curing work

VTR-3A-WL-S1-P1.160
Room Walls Formwork Removel 3 20-Mar-24 24-Mar-24 Room Walls Formwork Removel

VTR-3A-WL-S1-P1.165
Room Walls Scafolding for rebar 5 18-Feb-24 24-Feb-24 Room Walls Scafolding for rebar

Part-2 31 27-Feb-24 03-Apr-24 03-Apr-24, Part-2


VTR-3A-WL-S1-P2.135
Room Walls Rebar Installation 8 05-Mar-24 14-Mar-24 Room Walls Rebar Installation

VTR-3A-WL-S1-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 14-Mar-24 17-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S1-P2.145
Room Walls Formwork Installation 10 17-Mar-24 28-Mar-24 Room Walls Formwork Installation

VTR-3A-WL-S1-P2.150
Room Walls Concrete Casting 1 28-Mar-24 30-Mar-24 Room Walls Concrete Casting

VTR-3A-WL-S1-P2.155
Room Walls Curing work 1 30-Mar-24 31-Mar-24 Room Walls Curing work

VTR-3A-WL-S1-P2.160
Room Walls Formwork Removel 3 31-Mar-24 03-Apr-24 Room Walls Formwork Removel

VTR-3A-WL-S1-P2.165
Room Walls Scafolding for rebar 6 27-Feb-24 05-Mar-24 Room Walls Scafolding for rebar

Part-3 31 06-Mar-24 14-Apr-24 14-Apr-24, Part-3


VTR-3A-WL-S1-P3.135
Room Walls Rebar Installation 8 13-Mar-24 21-Mar-24 Room Walls Rebar Installation

VTR-3A-WL-S1-P3.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 23-Mar-24 24-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S1-P3.145
Room Walls Formwork Installation 10 24-Mar-24 04-Apr-24 Room Walls Formwork Installation

VTR-3A-WL-S1-P3.150
Room Walls Concrete Casting 1 04-Apr-24 06-Apr-24 Room Walls Concrete Casting

VTR-3A-WL-S1-P3.155
Room Walls Curing work 1 06-Apr-24 07-Apr-24 Room Walls Curing work

VTR-3A-WL-S1-P3.160
Room Walls Formwork Removel 3 07-Apr-24 14-Apr-24 Room Walls Formwork Removel

VTR-3A-WL-S1-P3.165
Room Walls Scafolding for rebar 6 06-Mar-24 12-Mar-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 74 24-Mar-24 26-Jun-24 26-Jun-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 24-Mar-24 09-May-24 09-May-24, Part-1
VTR-3A-TS-P1.125 Room Top Slab Formwork Installation 10 24-Mar-24 04-Apr-24 Room Top Slab Formwork Installation

VTR-3A-TS-P1.130 Room Top Slab Rebar Installation 10 04-Apr-24 20-Apr-24 Room Top Slab Rebar Installation

VTR-3A-TS-P1.135 Room Top Slab Concrete Casting 1 20-Apr-24 21-Apr-24 Room Top Slab Concrete Casting

VTR-3A-TS-P1.140 Room Top slab Curing work 12 21-Apr-24 05-May-24 Room Top slab Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
48 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-TS-P1.145 Room Top Slab Formwork Removel 4 05-May-24 09-May-24 Room Top Slab Formwork Removel

Part-2 37 09-May-24 26-Jun-24 26-Jun-24, Part-2


VTR-3A-TS-P2.125 Room Top Slab Formwork Installation 10 09-May-24 21-May-24 Room Top Slab Formwork Installation

VTR-3A-TS-P2.130 Room Top Slab Rebar Installation 10 21-May-24 02-Jun-24 Room Top Slab Rebar Installation

VTR-3A-TS-P2.135 Room Top Slab Concrete Casting 1 02-Jun-24 03-Jun-24 Room Top Slab Concrete Casting

VTR-3A-TS-P2.140 Room Top slab Curing work 12 03-Jun-24 22-Jun-24 Room Top slab Curing work

VTR-3A-TS-P2.145 Room Top Slab Formwork Removel 4 22-Jun-24 26-Jun-24 Room Top Slab Formwork Removel

Part-3 37 14-Apr-24 27-May-24 27-May-24, Part-3


VTR-3A-TS-P3.125 Room Top Slab Formwork Installation 10 14-Apr-24 25-Apr-24 Room Top Slab Formwork Installation

VTR-3A-TS-P3.130 Room Top Slab Rebar Installation 10 25-Apr-24 07-May-24 Room Top Slab Rebar Installation

VTR-3A-TS-P3.135 Room Top Slab Concrete Casting 1 07-May-24 08-May-24 Room Top Slab Concrete Casting

VTR-3A-TS-P3.140 Room Top slab Curing work 12 08-May-24 22-May-24 Room Top slab Curing work

VTR-3A-TS-P3.145 Room Top Slab Formwork Removel 4 22-May-24 27-May-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 89 21-Apr-24 07-Aug-24 07-Aug-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 63 21-Apr-24 08-Jul-24 08-Jul-24, WALL CONCRETE CASTING STAGE-1
Part-1 26 21-Apr-24 21-May-24 21-May-24, Part-1
VTR-3A-WL-S1-A.135
Room Walls Rebar Installation 8 28-Apr-24 07-May-24 Room Walls Rebar Installation

VTR-3A-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 07-May-24 09-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S1-A.145
Room Walls Formwork Installation 5 09-May-24 15-May-24 Room Walls Formwork Installation

VTR-3A-WL-S1-A.150
Room Walls Concrete Casting 1 15-May-24 16-May-24 Room Walls Concrete Casting

VTR-3A-WL-S1-A.155
Room Walls Curing work 1 16-May-24 18-May-24 Room Walls Curing work

VTR-3A-WL-S1-A.160
Room Walls Formwork Removel 3 18-May-24 21-May-24 Room Walls Formwork Removel

VTR-3A-WL-S1-A.165
Room Walls Scafolding for rebar 6 21-Apr-24 28-Apr-24 Room Walls Scafolding for rebar

Part-2 26 03-Jun-24 08-Jul-24 08-Jul-24, Part-2


VTR-3A-WL-S1-B.135
Room Walls Rebar Installation 8 10-Jun-24 24-Jun-24 Room Walls Rebar Installation

VTR-3A-WL-S1-B.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 24-Jun-24 26-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S1-B.145
Room Walls Formwork Installation 5 26-Jun-24 02-Jul-24 Room Walls Formwork Installation

VTR-3A-WL-S1-B.150
Room Walls Concrete Casting 1 02-Jul-24 03-Jul-24 Room Walls Concrete Casting

VTR-3A-WL-S1-B.155
Room Walls Curing work 1 03-Jul-24 04-Jul-24 Room Walls Curing work

VTR-3A-WL-S1-B.160
Room Walls Formwork Removel 3 04-Jul-24 08-Jul-24 Room Walls Formwork Removel

VTR-3A-WL-S1-B.165
Room Walls Scafolding for rebar 6 03-Jun-24 10-Jun-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-2 63 21-May-24 07-Aug-24 07-Aug-24, WALL CONCRETE CASTING STAGE-2
Part-1 26 21-May-24 25-Jun-24 25-Jun-24, Part-1
VTR-3A-WL-S2-A.135
Room Walls Rebar Installation 8 28-May-24 06-Jun-24 Room Walls Rebar Installation

VTR-3A-WL-S2-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 06-Jun-24 09-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S2-A.145
Room Walls Formwork Installation 5 09-Jun-24 19-Jun-24 Room Walls Formwork Installation

VTR-3A-WL-S2-A.150
Room Walls Concrete Casting 1 19-Jun-24 20-Jun-24 Room Walls Concrete Casting

VTR-3A-WL-S2-A.155
Room Walls Curing work 1 20-Jun-24 22-Jun-24 Room Walls Curing work

VTR-3A-WL-S2-A.160
Room Walls Formwork Removel 3 22-Jun-24 25-Jun-24 Room Walls Formwork Removel

VTR-3A-WL-S2-A.165
Room Walls Scafolding for rebar 6 21-May-24 28-May-24 Room Walls Scafolding for rebar

Part-2 26 08-Jul-24 07-Aug-24 07-Aug-24, Part-2


VTR-3A-WL-S2-B.135
Room Walls Rebar Installation 8 15-Jul-24 24-Jul-24 Room Walls Rebar Installation

VTR-3A-WL-S2-B.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 24-Jul-24 27-Jul-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3A-WL-S2-B.145
Room Walls Formwork Installation 5 27-Jul-24 01-Aug-24 Room Walls Formwork Installation

VTR-3A-WL-S2-B.150
Room Walls Concrete Casting 1 01-Aug-24 03-Aug-24 Room Walls Concrete Casting

VTR-3A-WL-S2-B.155
Room Walls Curing work 1 03-Aug-24 04-Aug-24 Room Walls Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
49 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-WL-S2-B.160
Room Walls Formwork Removel 3 04-Aug-24 07-Aug-24 Room Walls Formwork Removel

VTR-3A-WL-S2-B.165
Room Walls Scafolding for rebar 6 08-Jul-24 15-Jul-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 64 25-Jun-24 08-Sep-24 08-Sep-24, SLAB ABOVE GROUND LEVEL
Part 1 27 25-Jun-24 27-Jul-24 27-Jul-24, Part 1
VTR-3A-SLB-A.125 Room Top Slab Formwork Installation 6 25-Jun-24 02-Jul-24 Room Top Slab Formwork Installation

VTR-3A-SLB-A.130 Room Top Slab Rebar Installation 4 02-Jul-24 07-Jul-24 Room Top Slab Rebar Installation

VTR-3A-SLB-A.135 Room Top Slab Concrete Casting 1 07-Jul-24 08-Jul-24 Room Top Slab Concrete Casting

VTR-3A-SLB-A.140 Room Top slab Curing work 12 08-Jul-24 22-Jul-24 Room Top slab Curing work

VTR-3A-SLB-A.145 Room Top Slab Formwork Removel 4 22-Jul-24 27-Jul-24 Room Top Slab Formwork Removel

Part 2 27 07-Aug-24 08-Sep-24 08-Sep-24, Part 2


VTR-3A-SLB-B.125 Room Top Slab Formwork Installation 6 07-Aug-24 14-Aug-24 Room Top Slab Formwork Installation

VTR-3A-SLB-B.130 Room Top Slab Rebar Installation 4 14-Aug-24 19-Aug-24 Room Top Slab Rebar Installation

VTR-3A-SLB-B.135 Room Top Slab Concrete Casting 1 19-Aug-24 20-Aug-24 Room Top Slab Concrete Casting

VTR-3A-SLB-B.140 Room Top slab Curing work 12 20-Aug-24 03-Sep-24 Room Top slab Curing work

VTR-3A-SLB-B.145 Room Top Slab Formwork Removel 4 03-Sep-24 08-Sep-24 Room Top Slab Formwork Removel

WATER PROOFING 116 27-Jul-24 10-Dec-24 10-Dec-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 17 08-Sep-24 29-Sep-24 29-Sep-24, WALL WATER PROOFING STAGE-1
VTR-3A-WP-WL-S1.115
Surface preparation work 5 08-Sep-24 14-Sep-24 Surface preparation work

VTR-3A-WP-WL-S1.120
Applying of waterproofing material 8 14-Sep-24 24-Sep-24 Applying of waterproofing material

VTR-3A-WP-WL-S1.125
VR Back filling 4 24-Sep-24 29-Sep-24 VR Back filling

WALL WATER PROOFING STAGE-2 17 29-Sep-24 19-Oct-24 19-Oct-24, WALL WATER PROOFING STAGE-2
VTR-3A-WP-WL-S2.115
Surface preparation work 5 29-Sep-24 05-Oct-24 Surface preparation work

VTR-3A-WP-WL-S2.120
Applying of waterproofing material 8 05-Oct-24 14-Oct-24 Applying of waterproofing material

VTR-3A-WP-WL-S2.125
VR Back filling 4 14-Oct-24 19-Oct-24 VR Back filling

WALL WATER PROOFING STAGE-3 17 19-Oct-24 06-Nov-24 06-Nov-24, WALL WATER PROOFING STAGE-3
VTR-3A-WP-WL-S3.115
Surface preparation work 5 19-Oct-24 24-Oct-24 Surface preparation work

VTR-3A-WP-WL-S3.120
Applying of waterproofing material 8 24-Oct-24 02-Nov-24 Applying of waterproofing material

VTR-3A-WP-WL-S3.125
VR Back filling 4 03-Nov-24 06-Nov-24 VR Back filling

WALL WATER PROOFING STAGE-4 17 06-Nov-24 26-Nov-24 26-Nov-24, WALL WATER PROOFING STAGE-4
VTR-3A-WP-WL-S4.115
Surface preparation work 5 06-Nov-24 12-Nov-24 Surface preparation work

VTR-3A-WP-WL-S4.120
Applying of waterproofing material 8 12-Nov-24 21-Nov-24 Applying of waterproofing material

VTR-3A-WP-WL-S4.125
VR Back filling 4 21-Nov-24 26-Nov-24 VR Back filling

TOP SLAB WATER PROOFING 116 27-Jul-24 10-Dec-24 10-Dec-24, TOP SLAB WATER PROOFING
VTR-3A-WP-SLB-S1.115
Surface preparation work 12 27-Jul-24 10-Aug-24 Surface preparation work

VTR-3A-WP-SLB-S1.120
Applying of waterproofing material 11 26-Nov-24 09-Dec-24 Applying of waterproofing material

VTR-3A-WP-SLB-S1.125
Leak Test 1 09-Dec-24 10-Dec-24 Leak Test

MECHANICAL ROOM MEP 82 08-Sep-24 14-Dec-24 14-Dec-24, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 78 08-Sep-24 09-Dec-24 09-Dec-24, ELECTRICAL WORK IN ROOM
POWER SYSTEM 54 08-Sep-24 11-Nov-24 11-Nov-24, POWER SYSTEM
EARTHING SYSTEM 25 08-Sep-24 07-Oct-24 07-Oct-24, EARTHING SYSTEM
VTR-3A-EES-105 Earthing system soil resistivity test 6 08-Sep-24 15-Sep-24 Earthing system soil resistivity test

VTR-3A-EES-115 Earthing system Copper rod/ earthing pit installation 8 15-Sep-24 25-Sep-24 Earthing system Copper rod/ earthing pit installation

VTR-3A-EES-125 Earthing system Termination 6 25-Sep-24 01-Oct-24 Earthing system Termination

VTR-3A-EES-135 Earthing system Initial Testing 5 02-Oct-24 07-Oct-24 Earthing system Initial Testing

LIGHTING SYSTEM 37 15-Sep-24 28-Oct-24 28-Oct-24, LIGHTING SYSTEM


VTR-3A-ELI.105 Lighting system Conduit and boxes Installation 8 15-Sep-24 25-Sep-24 Lighting system Conduit and boxes Installation

VTR-3A-ELI.115 Lighting system Cable Pulling 8 25-Sep-24 03-Oct-24 Lighting system Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
50 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-ELI.125 Lighting system Installations 8 05-Oct-24 13-Oct-24 Lighting system Installations

VTR-3A-ELI.135 Lighting system Termination 8 13-Oct-24 22-Oct-24 Lighting system Termination

VTR-3A-ELI.145 Lighting system Initial Testing 5 22-Oct-24 28-Oct-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 15-Sep-24 10-Nov-24 10-Nov-24, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-3A-ECT.105 Cable Tray Installation 10 15-Sep-24 28-Sep-24 Cable Tray Installation

VTR-3A-ECT.115 Cable Tray Inspection 10 28-Sep-24 08-Oct-24 Cable Tray Inspection

VTR-3A-ECT.125 LV Cable pulling 10 09-Oct-24 20-Oct-24 LV Cable pulling

VTR-3A-ECT.135 LV Cable Termination 10 20-Oct-24 31-Oct-24 LV Cable Termination

VTR-3A-ECT.145 LV Cable Initial Testing 8 31-Oct-24 10-Nov-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 28-Sep-24 11-Nov-24 11-Nov-24, SMALL POWER SYSTEM


VTR-3A-ESP.105 Small Power Conduit and boxes Installation 12 28-Sep-24 10-Oct-24 Small Power Conduit and boxes Installation

VTR-3A-ESP.115 Small Power Cable Pulling 10 12-Oct-24 22-Oct-24 Small Power Cable Pulling

VTR-3A-ESP.125 Small Power Installations 6 22-Oct-24 29-Oct-24 Small Power Installations

VTR-3A-ESP.135 Small Power Termination 6 29-Oct-24 05-Nov-24 Small Power Termination

VTR-3A-ESP.145 Small Power Initial Testing 5 05-Nov-24 11-Nov-24 Small Power Initial Testing

POWER DISTRIBUTION 39 15-Sep-24 31-Oct-24 31-Oct-24, POWER DISTRIBUTION


GENERATOR 39 15-Sep-24 31-Oct-24 31-Oct-24, GENERATOR
VTR-3A-EPD.105 Generator Cable Tray Installation 7 15-Sep-24 24-Sep-24 Generator Cable Tray Installation

VTR-3A-EPD.115 Generator Cable Pulling 7 24-Sep-24 01-Oct-24 Generator Cable Pulling

VTR-3A-EPD.125 Generator Cell Pannel Installation 7 02-Oct-24 09-Oct-24 Generator Cell Pannel Installation

VTR-3A-EPD.135 Generator Installation 7 09-Oct-24 17-Oct-24 Generator Installation

VTR-3A-EPD.145 Generator Pannel / Cable Termination 7 17-Oct-24 26-Oct-24 Generator Pannel / Cable Termination

VTR-3A-EPD.155 Generator Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 Generator Pannel / Cable initial Testing

UPS 28 24-Sep-24 27-Oct-24 27-Oct-24, UPS


VTR-3A-EPD.165 UPS Cable Tray Installation 5 24-Sep-24 29-Sep-24 UPS Cable Tray Installation

VTR-3A-EPD.175 UPS Cable Pulling 5 30-Sep-24 05-Oct-24 UPS Cable Pulling

VTR-3A-EPD.185 UPS Pannel Installation 5 05-Oct-24 10-Oct-24 UPS Pannel Installation

VTR-3A-EPD.195 UPS Installation 5 10-Oct-24 16-Oct-24 UPS Installation

VTR-3A-EPD.205 UPS Pannel / Cable Termination 5 16-Oct-24 22-Oct-24 UPS Pannel / Cable Termination

VTR-3A-EPD.215 UPS Pannel / Cable initial Testing 4 22-Oct-24 27-Oct-24 UPS Pannel / Cable initial Testing

MDB 33 24-Sep-24 31-Oct-24 31-Oct-24, MDB


VTR-3A-EPD.225 MDB Cable Tray Installation 7 24-Sep-24 01-Oct-24 MDB Cable Tray Installation

VTR-3A-EPD.235 MDB Cable Pulling 7 02-Oct-24 09-Oct-24 MDB Cable Pulling

VTR-3A-EPD.245 MDB Pannel Installation 7 09-Oct-24 17-Oct-24 MDB Pannel Installation

VTR-3A-EPD.255 MDB Pannel / Cable Termination 7 17-Oct-24 26-Oct-24 MDB Pannel / Cable Termination

VTR-3A-EPD.265 MDB Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 MDB Pannel / Cable initial Testing

MCC 33 24-Sep-24 31-Oct-24 31-Oct-24, MCC


VTR-3A-EPD.325 MCC Cable Tray Installation 7 24-Sep-24 01-Oct-24 MCC Cable Tray Installation

VTR-3A-EPD.335 MCC Cable Pulling 7 02-Oct-24 09-Oct-24 MCC Cable Pulling

VTR-3A-EPD.345 MCC Pannel Installation 7 09-Oct-24 17-Oct-24 MCC Pannel Installation

VTR-3A-EPD.355 MCC Pannel / Cable Termination 7 17-Oct-24 26-Oct-24 MCC Pannel / Cable Termination

VTR-3A-EPD.365 MCC Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 MCC Pannel / Cable initial Testing

SMSB 24 24-Sep-24 21-Oct-24 21-Oct-24, SMSB


VTR-3A-EPD.275 SMSB Cable Tray Installation 5 24-Sep-24 29-Sep-24 SMSB Cable Tray Installation

VTR-3A-EPD.285 SMSB Cable Pulling 5 30-Sep-24 05-Oct-24 SMSB Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
51 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-EPD.295 SMSB Pannel Installation 5 05-Oct-24 10-Oct-24 SMSB Pannel Installation

VTR-3A-EPD.305 SMSB Pannel / Cable Termination 5 10-Oct-24 16-Oct-24 SMSB Pannel / Cable Termination

VTR-3A-EPD.315 SMSB Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 SMSB Pannel / Cable initial Testing

DB 24 24-Sep-24 21-Oct-24 21-Oct-24, DB


VTR-3A-EPD.375 DB Cable Tray Installation 5 24-Sep-24 29-Sep-24 DB Cable Tray Installation

VTR-3A-EPD.385 DB Cable Pulling 5 30-Sep-24 05-Oct-24 DB Cable Pulling

VTR-3A-EPD.395 DB Pannel Installation 5 05-Oct-24 10-Oct-24 DB Pannel Installation

VTR-3A-EPD.405 DB Pannel / Cable Termination 5 10-Oct-24 16-Oct-24 DB Pannel / Cable Termination

VTR-3A-EPD.415 DB Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 DB Pannel / Cable initial Testing

ISOLATOR 24 24-Sep-24 21-Oct-24 21-Oct-24, ISOLATOR


VTR-3A-EPD.425 Isolators Cable Tray Installation 5 24-Sep-24 29-Sep-24 Isolators Cable Tray Installation

VTR-3A-EPD.435 Isolators Cable Pulling 5 30-Sep-24 05-Oct-24 Isolators Cable Pulling

VTR-3A-EPD.445 Isolators Pannel Installation 5 05-Oct-24 10-Oct-24 Isolators Pannel Installation

VTR-3A-EPD.455 Isolators Pannel / Cable Termination 5 10-Oct-24 16-Oct-24 Isolators Pannel / Cable Termination

VTR-3A-EPD.465 Isolators Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 24-Sep-24 21-Oct-24 21-Oct-24, LCP/ ELCP


VTR-3A-EPD.475 LCP/ELCP Cable Tray Installation 5 24-Sep-24 29-Sep-24 LCP/ELCP Cable Tray Installation

VTR-3A-EPD.485 LCP/ELCP Cable Pulling 5 30-Sep-24 05-Oct-24 LCP/ELCP Cable Pulling

VTR-3A-EPD.495 LCP/ELCP Pannel Installation 5 05-Oct-24 10-Oct-24 LCP/ELCP Pannel Installation

VTR-3A-EPD.505 LCP/ELCP Pannel / Cable Termination 5 10-Oct-24 16-Oct-24 LCP/ELCP Pannel / Cable Termination

VTR-3A-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 12-Oct-24 09-Dec-24 09-Dec-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 12-Oct-24 28-Nov-24 28-Nov-24, FIRE ALARM SYSTEM
VTR-3A-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 12-Oct-24 21-Oct-24 Fire Alarm Conduit /Cable Tray Installation

VTR-3A-ELFA.115 Fire Alarm Cable Pulling 9 21-Oct-24 31-Oct-24 Fire Alarm Cable Pulling

VTR-3A-ELFA.125 Fire Alarm Devices Installation 9 31-Oct-24 11-Nov-24 Fire Alarm Devices Installation

VTR-3A-ELFA.135 Fire Alarm Devices and Cable Termination 9 11-Nov-24 21-Nov-24 Fire Alarm Devices and Cable Termination

VTR-3A-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 21-Nov-24 28-Nov-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 21-Oct-24 09-Dec-24 09-Dec-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-3A-ELVS.105 ICT System Conduit /Cable Tray Installation 9 21-Oct-24 31-Oct-24 ICT System Conduit /Cable Tray Installation

VTR-3A-ELVS.115 ICT System Cable Pulling 9 31-Oct-24 11-Nov-24 ICT System Cable Pulling

VTR-3A-ELVS.125 ICT System Devices Installation 9 11-Nov-24 21-Nov-24 ICT System Devices Installation

VTR-3A-ELVS.135 ICT System Devices and Cable Termination 9 21-Nov-24 02-Dec-24 ICT System Devices and Cable Termination

VTR-3A-ELVS.145 ICT System Devices and Cable initial Testing 6 02-Dec-24 09-Dec-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 21-Oct-24 09-Dec-24 09-Dec-24, ACCESS CONTROL SYSTEM


VTR-3A-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 21-Oct-24 31-Oct-24 Access Control System Conduit /Cable Tray Installation

VTR-3A-ELAC.115 Access Control System Cable Pulling 9 31-Oct-24 11-Nov-24 Access Control System Cable Pulling

VTR-3A-ELAC.125 Access Control System Devices Installation 9 11-Nov-24 21-Nov-24 Access Control System Devices Installation

VTR-3A-ELAC.135 Access Control System Devices and Cable Termination 9 21-Nov-24 02-Dec-24 Access Control System Devices and Cable Termination

VTR-3A-ELAC.145 Access Control System Devices and Cable initial Testing 6 02-Dec-24 09-Dec-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 21-Oct-24 09-Dec-24 09-Dec-24, PUBLIC ADDRESS SYSTEM


VTR-3A-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 21-Oct-24 31-Oct-24 Public Address System Conduit /Cable Tray Installation

VTR-3A-ELPA.115 Public Address System Cable Pulling 9 31-Oct-24 11-Nov-24 Public Address System Cable Pulling

VTR-3A-ELPA.125 Public Address System Devices Installation 9 11-Nov-24 21-Nov-24 Public Address System Devices Installation

VTR-3A-ELPA.135 Public Address System Devices and Cable Termination 9 21-Nov-24 02-Dec-24 Public Address System Devices and Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
52 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3A-ELPA.145 Public Address System Devices and Cable initial Testing 6 02-Dec-24 09-Dec-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 21-Oct-24 09-Dec-24 09-Dec-24, SCADA SYSTEM


VTR-3A-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 21-Oct-24 31-Oct-24 SCADA System Conduit /Cable Tray Installation

VTR-3A-ELSC.115 SCADA System Cable Pulling 9 31-Oct-24 11-Nov-24 SCADA System Cable Pulling

VTR-3A-ELSC.125 SCADA System Devices Installation 9 11-Nov-24 21-Nov-24 SCADA System Devices Installation

VTR-3A-ELSC.135 SCADA System Devices and Cable Termination 9 21-Nov-24 02-Dec-24 SCADA System Devices and Cable Termination

VTR-3A-ELSC.145 SCADA System Devices and Cable initial Testing 6 02-Dec-24 09-Dec-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 21-Oct-24 09-Dec-24 09-Dec-24, RADIO RE- BROADCOASTING/ TETRA
VTR-3A-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 21-Oct-24 31-Oct-24 Radio/TETRA System Conduit /Cable Tray Installation

VTR-3A-ELRD.115 Radio/TETRA System Cable Pulling 9 31-Oct-24 11-Nov-24 Radio/TETRA System Cable Pulling

VTR-3A-ELRD.125 Radio/TETRA System Devices Installation 9 11-Nov-24 21-Nov-24 Radio/TETRA System Devices Installation

VTR-3A-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 21-Nov-24 02-Dec-24 Radio/TETRA System Devices and Cable Termination

VTR-3A-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 02-Dec-24 09-Dec-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 69 24-Sep-24 14-Dec-24 14-Dec-24, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 24-Sep-24 22-Oct-24 22-Oct-24, FIRE FIGHTING
VTR-3A-MFF.105 Fire Fighting system Pipe and accessories installation 21 24-Sep-24 19-Oct-24 Fire Fighting system Pipe and accessories installation

VTR-3A-MFF.115 Fire Fighting system deluge valve installation 16 30-Sep-24 19-Oct-24 Fire Fighting system deluge valve installation

VTR-3A-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 12-Oct-24 19-Oct-24 Fire Fighting system fire hose cabinet/extingusher installation

VTR-3A-MFF.140 Fire Fighting system initial testing 3 19-Oct-24 22-Oct-24 Fire Fighting system initial testing

VTR-3A-MFF.145 Fire Fighting clean agent system 2 16-Oct-24 19-Oct-24 Fire Fighting clean agent system

HVAC 47 19-Oct-24 12-Dec-24 12-Dec-24, HVAC


VTR-3A-MHV.115 Air conditioning system installation 12 20-Nov-24 04-Dec-24 Air conditioning system installation

VTR-3A-MHV.120 Fan installation 15 17-Nov-24 04-Dec-24 Fan installation

VTR-3A-MHV.125 Duct and accessories installation 28 19-Oct-24 20-Nov-24 Duct and accessories installation

VTR-3A-MHV.135 HVAC inital testing 7 04-Dec-24 12-Dec-24 HVAC inital testing

PLUMBING 8 04-Dec-24 14-Dec-24 14-Dec-24, PLUMBING


VTR-3A-MPL.105 Plumbing drainage system installation 6 04-Dec-24 11-Dec-24 Plumbing drainage system installation

VTR-3A-MPL.115 Plumbing drainage system initial testing 2 11-Dec-24 14-Dec-24 Plumbing drainage system initial testing

DRY UTILITIES 30 24-Sep-24 28-Oct-24 28-Oct-24, DRY UTILITIES


POWER 30 24-Sep-24 28-Oct-24 28-Oct-24, POWER
POWER LV 16 24-Sep-24 13-Oct-24 13-Oct-24, POWER LV
DU-P-LV.310 Installation of support 1 24-Sep-24 24-Sep-24 Installation of support

DU-P-LV.315 Installation of horizontal busbar 2 24-Sep-24 26-Sep-24 Installation of horizontal busbar

DU-P-LV.320 Installation of vertical busbar 2 26-Sep-24 29-Sep-24 Installation of vertical busbar

DU-P-LV.325 Installation of left/right elbow 2 29-Sep-24 30-Sep-24 Installation of left/right elbow

DU-P-LV.330 Installation of right horizintal offset 2 30-Sep-24 02-Oct-24 Installation of right horizintal offset

DU-P-LV.335 Instalaltion of upward vertical offset 3 02-Oct-24 06-Oct-24 Instalaltion of upward vertical offset

DU-P-LV.340 Installation of downward vertical offset 3 06-Oct-24 09-Oct-24 Installation of downward vertical offset

DU-P-LV.345 Installation of transformer and panel connection 2 09-Oct-24 13-Oct-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 24-Sep-24 15-Oct-24 15-Oct-24, MEDIUM VOLTAGE


DU-P-MV.310 Installation of cable try, arm, racks and ladder 6 24-Sep-24 02-Oct-24 Installation of cable try, arm, racks and ladder

DU-P-MV.315 Installation of MV Cable 4 02-Oct-24 07-Oct-24 Installation of MV Cable

DU-P-MV.320 Installation of cable cleats 2 07-Oct-24 08-Oct-24 Installation of cable cleats

DU-P-MV.325 Installation of gland 1 08-Oct-24 09-Oct-24 Installation of gland

DU-P-MV.330 splicing/termination of MV cable 2 09-Oct-24 12-Oct-24 splicing/termination of MV cable

DU-P-MV.335 Testing and Pre-commissioning of cable 2 12-Oct-24 13-Oct-24 Testing and Pre-commissioning of cable

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
53 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-MV.340 Energezation 2 13-Oct-24 15-Oct-24 Energezation

TRANSFORMER 16 24-Sep-24 13-Oct-24 13-Oct-24, TRANSFORMER


DU-P-T.310 Installation of Transformer unit 2 24-Sep-24 26-Sep-24 Installation of Transformer unit

DU-P-T.315 Testing and Pre-Commissioning of unit 1 26-Sep-24 28-Sep-24 Testing and Pre-Commissioning of unit

DU-P-T.320 Termination and Splicing of MV Cable 3 28-Sep-24 01-Oct-24 Termination and Splicing of MV Cable

DU-P-T.325 Termination and Splicing of LV Cable/bus way 3 01-Oct-24 05-Oct-24 Termination and Splicing of LV Cable/bus way

DU-P-T.330 Installation and connection of I/O system 2 05-Oct-24 08-Oct-24 Installation and connection of I/O system

DU-P-T.335 Installation of Grounding and Protection System 2 08-Oct-24 10-Oct-24 Installation of Grounding and Protection System

DU-P-T.340 Testing and Commissioning of MV System 1 10-Oct-24 12-Oct-24 Testing and Commissioning of MV System

DU-P-T.345 Testing and Commissioning of LV System 1 12-Oct-24 13-Oct-24 Testing and Commissioning of LV System

DU-P-T.350 Energezation 1 13-Oct-24 13-Oct-24 Energezation

RMU 16 26-Sep-24 15-Oct-24 15-Oct-24, RMU


DU-P-RMU.310 Installation RMU unit 2 26-Sep-24 29-Sep-24 Installation RMU unit

DU-P-RMU.315 Testing and Pre-Commissioning of unit 2 29-Sep-24 01-Oct-24 Testing and Pre-Commissioning of unit

DU-P-RMU.320 Termination and Splicing of Ring-MV Cable 4 01-Oct-24 06-Oct-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.325 Termination and Splicing of T-MV Cable 4 06-Oct-24 10-Oct-24 Termination and Splicing of T-MV Cable

DU-P-RMU.330 Installation of Grounding and Protection System 2 10-Oct-24 13-Oct-24 Installation of Grounding and Protection System

DU-P-RMU.335 Testing and Commissioning of MV System 1 13-Oct-24 14-Oct-24 Testing and Commissioning of MV System

DU-P-RMU.340 Energezation 1 14-Oct-24 15-Oct-24 Energezation

MRMU 18 29-Sep-24 20-Oct-24 20-Oct-24, MRMU


DU-P-MRMU.310 Installation MRMU unit 2 29-Sep-24 02-Oct-24 Installation MRMU unit

DU-P-MRMU.315 Testing and Pre-Commissioning of unit 3 02-Oct-24 06-Oct-24 Testing and Pre-Commissioning of unit

DU-P-MRMU.320 Termination and Splicing of Ring-MV Cable 3 06-Oct-24 09-Oct-24 Termination and Splicing of Ring-MV Cable

DU-P-MRMU.325 Termination and Splicing of T-MV Cable 3 09-Oct-24 13-Oct-24 Termination and Splicing of T-MV Cable

DU-P-MRMU.330 Installation and connection of I/O system 2 13-Oct-24 16-Oct-24 Installation and connection of I/O system

DU-P-MRMU.335 Testing and Commissioning of MV System 1 16-Oct-24 17-Oct-24 Testing and Commissioning of MV System

DU-P-MRMU.340 Testing and Commissioning of Metered System 1 17-Oct-24 17-Oct-24 Testing and Commissioning of Metered System

DU-P-MRMU.345 Energezation 2 17-Oct-24 20-Oct-24 Energezation

MVSG 22 02-Oct-24 28-Oct-24 28-Oct-24, MVSG


DU-P-MVSG.310 Installation of MVSG module unit 6 02-Oct-24 09-Oct-24 Installation of MVSG module unit

DU-P-MVSG.315 Testing and Pre-Commissioning of each module 3 09-Oct-24 13-Oct-24 Testing and Pre-Commissioning of each module

DU-P-MVSG.320 Termination and Splicing of MV Cable each module 6 13-Oct-24 20-Oct-24 Termination and Splicing of MV Cable each module

DU-P-MVSG.325 Installation of Grounding system and protection 2 20-Oct-24 22-Oct-24 Installation of Grounding system and protection

DU-P-MVSG.330 Installation and connection of I/O system 2 22-Oct-24 26-Oct-24 Installation and connection of I/O system

DU-P-MVSG.335 Testing and Commissioning of MV System 1 26-Oct-24 27-Oct-24 Testing and Commissioning of MV System

DU-P-MVSG.340 Testing and Commissioning of Metered System 1 27-Oct-24 27-Oct-24 Testing and Commissioning of Metered System

DU-P-MVSG.345 Energezation 1 27-Oct-24 28-Oct-24 Energezation

BATTERY ROOM 16 09-Oct-24 28-Oct-24 28-Oct-24, BATTERY ROOM


DU-P-BARM.310 Installation of Battery racks 3 09-Oct-24 13-Oct-24 Installation of Battery racks

DU-P-BARM.315 Installation of batterys 3 13-Oct-24 16-Oct-24 Installation of batterys

DU-P-BARM.320 Installation of DC cable 3 16-Oct-24 20-Oct-24 Installation of DC cable

DU-P-BARM.325 Installation of battery control panel 2 20-Oct-24 23-Oct-24 Installation of battery control panel

DU-P-BARM.330 installation of grounding system 2 23-Oct-24 26-Oct-24 installation of grounding system

DU-P-BARM.335 Testing and Commissioning 2 26-Oct-24 28-Oct-24 Testing and Commissioning

VECHICULAR ROOM 3B (IN ZONE 09) 679 24-May-23 14-Aug-25 14-Aug-25, VECHICULAR ROOM 3B (IN ZONE 09)

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
54 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGINEERING 109 24-May-23 03-Oct-23 03-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 109 24-May-23 03-Oct-23 03-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE
VTR-3B-ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VTR-3B-ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VTR-3B-ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VTR-3B-ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VTR-3B-ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VTR-3B-ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VTR-3B-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VTR-3B-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VTR-3B-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VTR-3B-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VTR-3B-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VTR-3B-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VTR-3B-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VTR-3B-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VTR-3B-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VTR-3B-ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 26 31-Jul-23 30-Aug-23 30-Aug-23, TRANSFORMERS INSTALLATION


VTR-3B-ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Transformers Installation Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, LIGHTNING PROTECTION SYSTEM


VTR-3B-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Lightning Protection Drawings Preparation & Submission

VTR-3B-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, EARTHING SYSTEM


VTR-3B-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 Earthing System Shop Drawings Preparation & Submission

VTR-3B-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 18-Sep-23 03-Oct-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VTR-3B-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VTR-3B-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
55 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VTR-3B-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VTR-3B-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VTR-3B-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VTR-3B-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VTR-3B-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTITIES 62 24-May-23 08-Aug-23 08-Aug-23, DRY UTITIES


POWER 62 24-May-23 08-Aug-23 08-Aug-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.400 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.405 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 03-Jul-23 08-Aug-23 08-Aug-23, MEDIUM VOLTAGE


DU-P-MV.400 Prepare and submit medium voltage shopdrawings 20 03-Jul-23 25-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.405 Review and approval medium voltage shopdrawings 11 26-Jul-23 08-Aug-23 Review and approval medium voltage shopdrawings

PROCUREMENT 257 17-Sep-24 23-Jul-25 23-Jul-25, PROCUREMENT


CIVIL/STRUCTURAL 16 17-Sep-24 07-Oct-24 07-Oct-24, CIVIL/STRUCTURAL
VTR-3B-PRO-CV.110 Issue Purchase Order 6 17-Sep-24 25-Sep-24 Issue Purchase Order

VTR-3B-PRO-CV.115 Material Delivery 10 25-Sep-24 07-Oct-24 Material Delivery

MECHANICAL 154 16-Jan-25 23-Jul-25 23-Jul-25, MECHANICAL


FIRE FIGHTING SYSTEM 105 16-Jan-25 24-May-25 24-May-25, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 16-Jan-25 24-May-25 24-May-25, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VTR-3B-PR-MC-FF.110
Issue Purchase Order 15 16-Jan-25 03-Feb-25 Issue Purchase Order

VTR-3B-PR-MC-FF.115
Material Delivery 90 03-Feb-25 24-May-25 Material Delivery

VENTILATION SYSTEM 105 15-Mar-25 23-Jul-25 23-Jul-25, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 15-Mar-25 23-Jul-25 23-Jul-25, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VTR-3B-PR-MC-DS.110
Issue Purchase Order 15 15-Mar-25 06-Apr-25 Issue Purchase Order

VTR-3B-PR-MC-DS.115
Material Delivery 90 06-Apr-25 23-Jul-25 Material Delivery

AIR CONDITIONING WORKS 105 15-Mar-25 23-Jul-25 23-Jul-25, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 15-Mar-25 23-Jul-25 23-Jul-25, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VTR-3B-PR-MC-AC.110
Issue Purchase Order 15 15-Mar-25 06-Apr-25 Issue Purchase Order

VTR-3B-PR-MC-AC.115
Material Delivery 90 06-Apr-25 23-Jul-25 Material Delivery

PLUMBING SYSTEM 105 10-Feb-25 21-Jun-25 21-Jun-25, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 10-Feb-25 21-Jun-25 21-Jun-25, PUMPS,PIPES,FITTINGS,VALVES
VTR-3B-PR-MC-PI.110
Issue Purchase Order 15 10-Feb-25 27-Feb-25 Issue Purchase Order

VTR-3B-PR-MC-PI.115
Material Delivery 90 27-Feb-25 21-Jun-25 Material Delivery

ELECTRICAL 132 01-Jan-25 12-Jun-25 12-Jun-25, ELECTRICAL


CABLE TRAY 105 08-Jan-25 15-May-25 15-May-25, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 08-Jan-25 15-May-25 15-May-25, CABLE TRAY AND ACCESSORIES,PVC DUCT
VTR-3B-PR-EL-CT.110
Issue Purchase Order 15 08-Jan-25 26-Jan-25 Issue Purchase Order

VTR-3B-PR-EL-CT.115
Material Delivery 90 26-Jan-25 15-May-25 Material Delivery

POWER CABLES 105 08-Jan-25 15-May-25 15-May-25, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 08-Jan-25 15-May-25 15-May-25, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VTR-3B-PR-EL-PC.110
Issue Purchase Order 15 08-Jan-25 26-Jan-25 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
56 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-PR-EL-PC.115
Material Delivery 90 26-Jan-25 15-May-25 Material Delivery

LIGHTING SYSTEM 105 08-Jan-25 15-May-25 15-May-25, LIGHTING SYSTEM


CONDUIT,LIGHT 105 08-Jan-25 15-May-25 15-May-25, CONDUIT,LIGHT
VTR-3B-PR-EL-LS.110
Issue Purchase Order 15 08-Jan-25 26-Jan-25 Issue Purchase Order

VTR-3B-PR-EL-LS.115
Material Delivery 90 26-Jan-25 15-May-25 Material Delivery

ELECTRICAL INSTALLATIONS 105 08-Jan-25 15-May-25 15-May-25, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 08-Jan-25 15-May-25 15-May-25, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VTR-3B-PR-EL-EI.110Issue Purchase Order 15 08-Jan-25 26-Jan-25 Issue Purchase Order

VTR-3B-PR-EL-EI.115Material Delivery 90 26-Jan-25 15-May-25 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 01-Jan-25 08-May-25 08-May-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 01-Jan-25 08-May-25 08-May-25, LIGHTNING PROTECTION SYSTEM
VTR-3B-PR-EL-LP.110Issue Purchase Order 15 01-Jan-25 19-Jan-25 Issue Purchase Order

VTR-3B-PR-EL-LP.115Material Delivery 90 19-Jan-25 08-May-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 01-Jan-25 08-May-25 08-May-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 01-Jan-25 08-May-25 08-May-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VTR-3B-PR-EL-ES.110
Issue Purchase Order 15 01-Jan-25 19-Jan-25 Issue Purchase Order

VTR-3B-PR-EL-ES.115
Material Delivery 90 19-Jan-25 08-May-25 Material Delivery

LOW CURRENT 114 22-Jan-25 12-Jun-25 12-Jun-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 22-Jan-25 29-May-25 29-May-25, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 22-Jan-25 29-May-25 29-May-25, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VTR-3B-PR-ELL-FA.20
Issue Purchase Order 15 22-Jan-25 09-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-FA.25
Material Delivery 90 09-Feb-25 29-May-25 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 02-Feb-25 12-Jun-25 12-Jun-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 02-Feb-25 12-Jun-25 12-Jun-25, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VTR-3B-PR-ELL-PH.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-PH.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 02-Feb-25 12-Jun-25 12-Jun-25, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 02-Feb-25 12-Jun-25 12-Jun-25, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VTR-3B-PR-ELL-PA.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-PA.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

VIDEO SURVEILLANCE 105 02-Feb-25 12-Jun-25 12-Jun-25, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 02-Feb-25 12-Jun-25 12-Jun-25, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VTR-3B-PR-ELL-VS.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-VS.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

ACCESS CONTROL SYSTEM 105 02-Feb-25 12-Jun-25 12-Jun-25, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 02-Feb-25 12-Jun-25 12-Jun-25, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORI
VTR-3B-PR-ELL-AC.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-AC.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 02-Feb-25 12-Jun-25 12-Jun-25, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 02-Feb-25 12-Jun-25 12-Jun-25, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VTR-3B-PR-ELL-RB.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-RB.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

SCADA SYSTEM 105 02-Feb-25 12-Jun-25 12-Jun-25, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 02-Feb-25 12-Jun-25 12-Jun-25, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VTR-3B-PR-ELL-SD.20
Issue Purchase Order 15 02-Feb-25 19-Feb-25 Issue Purchase Order

VTR-3B-PR-ELL-SD.25
Material Delivery 90 19-Feb-25 12-Jun-25 Material Delivery

CONSTRUCTION 278 16-Sep-24 14-Aug-25 14-Aug-25, CONSTRUCTION


STRUCTURAL WORKS 223 16-Sep-24 11-Jun-25 11-Jun-25, STRUCTURAL WORKS
PLAIN CONCRETE ABOVE TUNNEL SLAB 35 16-Sep-24 28-Oct-24 28-Oct-24, PLAIN CONCRETE ABOVE TUNNEL SLAB
Part-1 12 16-Sep-24 30-Sep-24 30-Sep-24, Part-1
VTR-3B-PC-P1.120 Plain Concrete Above Top Slab Formwork Installation 7 16-Sep-24 24-Sep-24 Plain Concrete Above Top Slab Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
57 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-PC-P1.125 Plain Concrete Casting 1 24-Sep-24 25-Sep-24 Plain Concrete Casting

VTR-3B-PC-P1.130 Plain Concrete curing work 1 25-Sep-24 26-Sep-24 Plain Concrete curing work

VTR-3B-PC-P1.135 Plain Concrete Formwork removal 3 26-Sep-24 30-Sep-24 Plain Concrete Formwork removal

Part-2 12 30-Sep-24 14-Oct-24 14-Oct-24, Part-2


VTR-3B-PC-P2.120 Plain Concrete Above Top Slab Formwork Installation 7 30-Sep-24 08-Oct-24 Plain Concrete Above Top Slab Formwork Installation

VTR-3B-PC-P2.125 Plain Concrete Casting 1 08-Oct-24 09-Oct-24 Plain Concrete Casting

VTR-3B-PC-P2.130 Plain Concrete curing work 1 09-Oct-24 10-Oct-24 Plain Concrete curing work

VTR-3B-PC-P2.135 Plain Concrete Formwork removal 3 10-Oct-24 14-Oct-24 Plain Concrete Formwork removal

Part-3 12 14-Oct-24 28-Oct-24 28-Oct-24, Part-3


VTR-3B-PC-P3.120 Plain Concrete Above Top Slab Formwork Installation 7 14-Oct-24 22-Oct-24 Plain Concrete Above Top Slab Formwork Installation

VTR-3B-PC-P3.125 Plain Concrete Casting 1 22-Oct-24 23-Oct-24 Plain Concrete Casting

VTR-3B-PC-P3.130 Plain Concrete curing work 1 23-Oct-24 24-Oct-24 Plain Concrete curing work

VTR-3B-PC-P3.135 Plain Concrete Formwork removal 3 24-Oct-24 28-Oct-24 Plain Concrete Formwork removal

FOUNDATION 57 30-Sep-24 05-Dec-24 05-Dec-24, FOUNDATION


Part-1 30 30-Sep-24 04-Nov-24 04-Nov-24, Part-1
VTR-3B-FDN-P1.150 Foundation water proofing on blinding concrete 3 30-Sep-24 03-Oct-24 Foundation water proofing on blinding concrete

VTR-3B-FDN-P1.155 Foundation Protection screed on water poofing 1 03-Oct-24 05-Oct-24 Foundation Protection screed on water poofing

VTR-3B-FDN-P1.160 Foundation Curing for screed 2 05-Oct-24 07-Oct-24 Foundation Curing for screed

VTR-3B-FDN-P1.165 Foundation Rebar installation 10 07-Oct-24 19-Oct-24 Foundation Rebar installation

VTR-3B-FDN-P1.170 Foundation Formwork installation 8 19-Oct-24 28-Oct-24 Foundation Formwork installation

VTR-3B-FDN-P1.175 Foundation Construction joint work 2 28-Oct-24 30-Oct-24 Foundation Construction joint work

VTR-3B-FDN-P1.180 Foundation concrete casting 1 30-Oct-24 31-Oct-24 Foundation concrete casting

VTR-3B-FDN-P1.185 Foundation concrete curing 1 31-Oct-24 02-Nov-24 Foundation concrete curing

VTR-3B-FDN-P1.190 Foundation Formwork Removal 2 02-Nov-24 04-Nov-24 Foundation Formwork Removal

Part-2 30 14-Oct-24 17-Nov-24 17-Nov-24, Part-2


VTR-3B-FDN-P2.150 Foundation water proofing on blinding concrete 3 14-Oct-24 17-Oct-24 Foundation water proofing on blinding concrete

VTR-3B-FDN-P2.155 Foundation Protection screed on water poofing 1 17-Oct-24 19-Oct-24 Foundation Protection screed on water poofing

VTR-3B-FDN-P2.160 Foundation Curing for screed 2 19-Oct-24 21-Oct-24 Foundation Curing for screed

VTR-3B-FDN-P2.165 Foundation Rebar installation 10 21-Oct-24 31-Oct-24 Foundation Rebar installation

VTR-3B-FDN-P2.170 Foundation Formwork installation 8 02-Nov-24 10-Nov-24 Foundation Formwork installation

VTR-3B-FDN-P2.175 Foundation Construction joint work 2 10-Nov-24 12-Nov-24 Foundation Construction joint work

VTR-3B-FDN-P2.180 Foundation concrete casting 1 12-Nov-24 13-Nov-24 Foundation concrete casting

VTR-3B-FDN-P2.185 Foundation concrete curing 1 13-Nov-24 14-Nov-24 Foundation concrete curing

VTR-3B-FDN-P2.190 Foundation Formwork Removal 2 14-Nov-24 17-Nov-24 Foundation Formwork Removal

Part-3 30 02-Nov-24 05-Dec-24 05-Dec-24, Part-3


VTR-3B-FDN-P3.150 Foundation water proofing on blinding concrete 3 02-Nov-24 04-Nov-24 Foundation water proofing on blinding concrete

VTR-3B-FDN-P3.155 Foundation Protection screed on water poofing 1 04-Nov-24 05-Nov-24 Foundation Protection screed on water poofing

VTR-3B-FDN-P3.160 Foundation Curing for screed 2 05-Nov-24 07-Nov-24 Foundation Curing for screed

VTR-3B-FDN-P3.165 Foundation Rebar installation 10 07-Nov-24 19-Nov-24 Foundation Rebar installation

VTR-3B-FDN-P3.170 Foundation Formwork installation 8 19-Nov-24 28-Nov-24 Foundation Formwork installation

VTR-3B-FDN-P3.175 Foundation Construction joint work 2 28-Nov-24 01-Dec-24 Foundation Construction joint work

VTR-3B-FDN-P3.180 Foundation concrete casting 1 01-Dec-24 02-Dec-24 Foundation concrete casting

VTR-3B-FDN-P3.185 Foundation concrete curing 1 02-Dec-24 03-Dec-24 Foundation concrete curing

VTR-3B-FDN-P3.190 Foundation Formwork Removal 2 03-Dec-24 05-Dec-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 61 31-Oct-24 11-Jan-25 11-Jan-25, WALLS UP TO SLAB LEVEL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
58 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL CONCRETE CASTING STAGE-1 61 31-Oct-24 11-Jan-25 11-Jan-25, WALL CONCRETE CASTING STAGE-1
Part-1 35 31-Oct-24 10-Dec-24 10-Dec-24, Part-1
VTR-3B-WL-S1-P1.135
Room Walls Rebar Installation 12 07-Nov-24 20-Nov-24 Room Walls Rebar Installation

VTR-3B-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Nov-24 23-Nov-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3B-WL-S1-P1.145
Room Walls Formwork Installation 10 23-Nov-24 04-Dec-24 Room Walls Formwork Installation

VTR-3B-WL-S1-P1.150
Room Walls Concrete Casting 1 04-Dec-24 05-Dec-24 Room Walls Concrete Casting

VTR-3B-WL-S1-P1.155
Room Walls Curing work 1 05-Dec-24 07-Dec-24 Room Walls Curing work

VTR-3B-WL-S1-P1.160
Room Walls Formwork Removel 3 07-Dec-24 10-Dec-24 Room Walls Formwork Removel

VTR-3B-WL-S1-P1.165
Room Walls Scafolding for rebar 6 31-Oct-24 07-Nov-24 Room Walls Scafolding for rebar

Part-2 33 14-Nov-24 23-Dec-24 23-Dec-24, Part-2


VTR-3B-WL-S1-P2.134
Room Walls Scafolding for rebar 6 14-Nov-24 21-Nov-24 Room Walls Scafolding for rebar

VTR-3B-WL-S1-P2.135
Room Walls Rebar Installation 12 21-Nov-24 05-Dec-24 Room Walls Rebar Installation

VTR-3B-WL-S1-P2.145
Room Walls Formwork Installation 10 05-Dec-24 17-Dec-24 Room Walls Formwork Installation

VTR-3B-WL-S1-P2.150
Room Walls Concrete Casting 1 17-Dec-24 18-Dec-24 Room Walls Concrete Casting

VTR-3B-WL-S1-P2.155
Room Walls Curing work 1 18-Dec-24 19-Dec-24 Room Walls Curing work

VTR-3B-WL-S1-P2.160
Room Walls Formwork Removel 3 19-Dec-24 23-Dec-24 Room Walls Formwork Removel

Part-3 33 03-Dec-24 11-Jan-25 11-Jan-25, Part-3


VTR-3B-WL-S1-P3.134
Room Walls Scafolding for rebar 6 03-Dec-24 10-Dec-24 Room Walls Scafolding for rebar

VTR-3B-WL-S1-P3.135
Room Walls Rebar Installation 12 10-Dec-24 24-Dec-24 Room Walls Rebar Installation

VTR-3B-WL-S1-P3.145
Room Walls Formwork Installation 10 24-Dec-24 05-Jan-25 Room Walls Formwork Installation

VTR-3B-WL-S1-P3.150
Room Walls Concrete Casting 1 05-Jan-25 06-Jan-25 Room Walls Concrete Casting

VTR-3B-WL-S1-P3.155
Room Walls Curing work 1 06-Jan-25 07-Jan-25 Room Walls Curing work

VTR-3B-WL-S1-P3.160
Room Walls Formwork Removel 3 07-Jan-25 11-Jan-25 Room Walls Formwork Removel

TOP SLAB BELOW GROUND LEVEL 88 10-Dec-24 23-Mar-25 23-Mar-25, TOP SLAB BELOW GROUND LEVEL
Part-1 35 10-Dec-24 20-Jan-25 20-Jan-25, Part-1
VTR-3B-TS-P1.125 Room Top Slab Formwork Installation 10 10-Dec-24 22-Dec-24 Room Top Slab Formwork Installation

VTR-3B-TS-P1.130 Room Top Slab Rebar Installation 8 22-Dec-24 31-Dec-24 Room Top Slab Rebar Installation

VTR-3B-TS-P1.135 Room Top Slab Concrete Casting 1 31-Dec-24 01-Jan-25 Room Top Slab Concrete Casting

VTR-3B-TS-P1.140 Room Top slab Curing work 12 01-Jan-25 15-Jan-25 Room Top slab Curing work

VTR-3B-TS-P1.145 Room Top Slab Formwork Removel 4 15-Jan-25 20-Jan-25 Room Top Slab Formwork Removel

Part-2 35 20-Jan-25 02-Mar-25 02-Mar-25, Part-2


VTR-3B-TS-P2.125 Room Top Slab Formwork Installation 10 20-Jan-25 01-Feb-25 Room Top Slab Formwork Installation

VTR-3B-TS-P2.130 Room Top Slab Rebar Installation 8 01-Feb-25 10-Feb-25 Room Top Slab Rebar Installation

VTR-3B-TS-P2.135 Room Top Slab Concrete Casting 1 10-Feb-25 11-Feb-25 Room Top Slab Concrete Casting

VTR-3B-TS-P2.140 Room Top slab Curing work 12 11-Feb-25 25-Feb-25 Room Top slab Curing work

VTR-3B-TS-P2.145 Room Top Slab Formwork Removel 4 25-Feb-25 02-Mar-25 Room Top Slab Formwork Removel

Part-3 35 10-Feb-25 23-Mar-25 23-Mar-25, Part-3


VTR-3B-TS-P3.125 Room Top Slab Formwork Installation 10 10-Feb-25 22-Feb-25 Room Top Slab Formwork Installation

VTR-3B-TS-P3.130 Room Top Slab Rebar Installation 8 22-Feb-25 03-Mar-25 Room Top Slab Rebar Installation

VTR-3B-TS-P3.135 Room Top Slab Concrete Casting 1 03-Mar-25 04-Mar-25 Room Top Slab Concrete Casting

VTR-3B-TS-P3.140 Room Top slab Curing work 12 04-Mar-25 18-Mar-25 Room Top slab Curing work

VTR-3B-TS-P3.145 Room Top Slab Formwork Removel 4 18-Mar-25 23-Mar-25 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 28 02-Mar-25 08-Apr-25 08-Apr-25, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 28 02-Mar-25 08-Apr-25 08-Apr-25, WALL CONCRETE CASTING STAGE-1
Part-2 28 02-Mar-25 08-Apr-25 08-Apr-25, Part-2
VTR-3B-WL-S1-B.134
Room Walls Scafolding for rebar 6 02-Mar-25 09-Mar-25 Room Walls Scafolding for rebar

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
59 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-WL-S1-B.135
Room Walls Rebar Installation 10 09-Mar-25 20-Mar-25 Room Walls Rebar Installation

VTR-3B-WL-S1-B.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 20-Mar-25 23-Mar-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-3B-WL-S1-B.145
Room Walls Formwork Installation 5 23-Mar-25 29-Mar-25 Room Walls Formwork Installation

VTR-3B-WL-S1-B.150
Room Walls Concrete Casting 1 29-Mar-25 03-Apr-25 Room Walls Concrete Casting

VTR-3B-WL-S1-B.155
Room Walls Curing work 1 03-Apr-25 05-Apr-25 Room Walls Curing work

VTR-3B-WL-S1-B.160
Room Walls Formwork Removel 3 05-Apr-25 08-Apr-25 Room Walls Formwork Removel

SLAB ABOVE GROUND LEVEL 26 08-Apr-25 08-May-25 08-May-25, SLAB ABOVE GROUND LEVEL
Part-2 26 08-Apr-25 08-May-25 08-May-25, Part-2
VTR-3B-SLB-P2.125 Room Top Slab Formwork Installation 5 08-Apr-25 14-Apr-25 Room Top Slab Formwork Installation

VTR-3B-SLB-P2.130 Room Top Slab Rebar Installation 4 14-Apr-25 19-Apr-25 Room Top Slab Rebar Installation

VTR-3B-SLB-P2.135 Room Top Slab Concrete Casting 1 19-Apr-25 20-Apr-25 Room Top Slab Concrete Casting

VTR-3B-SLB-P2.140 Room Top slab Curing work 12 20-Apr-25 04-May-25 Room Top slab Curing work

VTR-3B-SLB-P2.145 Room Top Slab Formwork Removel 4 04-May-25 08-May-25 Room Top Slab Formwork Removel

WATER PROOFING 52 08-Apr-25 11-Jun-25 11-Jun-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 08-Apr-25 20-Apr-25 20-Apr-25, WALL WATER PROOFING STAGE-1
VTR-3B-WP-WL-S1.115
Surface preparation work 2 08-Apr-25 10-Apr-25 Surface preparation work

VTR-3B-WP-WL-S1.120
Applying of waterproofing material 3 10-Apr-25 14-Apr-25 Applying of waterproofing material

VTR-3B-WP-WL-S1.125
VR Back filling 5 14-Apr-25 20-Apr-25 VR Back filling

WALL WATER PROOFING STAGE-2 13 10-Apr-25 26-Apr-25 26-Apr-25, WALL WATER PROOFING STAGE-2
VTR-3B-WP-WL-S2.115
Surface preparation work 2 10-Apr-25 13-Apr-25 Surface preparation work

VTR-3B-WP-WL-S2.120
Applying of waterproofing material 3 13-Apr-25 16-Apr-25 Applying of waterproofing material

VTR-3B-WP-WL-S2.125
VR Back filling 5 20-Apr-25 26-Apr-25 VR Back filling

WALL WATER PROOFING STAGE-3 10 26-Apr-25 07-May-25 07-May-25, WALL WATER PROOFING STAGE-3
VTR-3B-WP-WL-S3.115
Surface preparation work 2 26-Apr-25 28-Apr-25 Surface preparation work

VTR-3B-WP-WL-S3.120
Applying of waterproofing material 3 28-Apr-25 01-May-25 Applying of waterproofing material

VTR-3B-WP-WL-S3.125
VR Back filling 5 01-May-25 07-May-25 VR Back filling

WALL WATER PROOFING STAGE-4 13 28-Apr-25 13-May-25 13-May-25, WALL WATER PROOFING STAGE-4
VTR-3B-WP-WL-S4.115
Surface preparation work 2 28-Apr-25 30-Apr-25 Surface preparation work

VTR-3B-WP-WL-S4.120
Applying of waterproofing material 3 30-Apr-25 04-May-25 Applying of waterproofing material

VTR-3B-WP-WL-S4.125
VR Back filling 5 07-May-25 13-May-25 VR Back filling

TOP SLAB WATER PROOFING 26 08-May-25 11-Jun-25 11-Jun-25, TOP SLAB WATER PROOFING
VTR-3B-WP-SLB-S1.115
Surface preparation work 12 08-May-25 22-May-25 Surface preparation work

VTR-3B-WP-SLB-S1.120
Applying of waterproofing material 13 22-May-25 10-Jun-25 Applying of waterproofing material

VTR-3B-WP-SLB-S1.125
Leak Test 1 10-Jun-25 11-Jun-25 Leak Test

MECHANICAL ROOM MEP 81 08-May-25 14-Aug-25 14-Aug-25, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 68 08-May-25 30-Jul-25 30-Jul-25, ELECTRICAL WORK IN ROOM
POWER SYSTEM 53 08-May-25 14-Jul-25 14-Jul-25, POWER SYSTEM
EARTHING SYSTEM 25 08-May-25 10-Jun-25 10-Jun-25, EARTHING SYSTEM
VTR-3B-EES-105 Earthing system soil resistivity test 6 08-May-25 15-May-25 Earthing system soil resistivity test

VTR-3B-EES-115 Earthing system Copper rod/ earthing pit installation 8 15-May-25 25-May-25 Earthing system Copper rod/ earthing pit installation

VTR-3B-EES-125 Earthing system Termination 6 25-May-25 01-Jun-25 Earthing system Termination

VTR-3B-EES-135 Earthing system Initial Testing 5 01-Jun-25 10-Jun-25 Earthing system Initial Testing

LIGHTING SYSTEM 37 15-May-25 01-Jul-25 01-Jul-25, LIGHTING SYSTEM


VTR-3B-ELI.105 Lighting system Conduit and boxes Installation 8 15-May-25 25-May-25 Lighting system Conduit and boxes Installation

VTR-3B-ELI.115 Lighting system Cable Pulling 8 25-May-25 03-Jun-25 Lighting system Cable Pulling

VTR-3B-ELI.125 Lighting system Installations 8 03-Jun-25 16-Jun-25 Lighting system Installations

VTR-3B-ELI.135 Lighting system Termination 8 16-Jun-25 25-Jun-25 Lighting system Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
60 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-ELI.145 Lighting system Initial Testing 5 25-Jun-25 01-Jul-25 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 15-May-25 14-Jul-25 14-Jul-25, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-3B-ECT.105 Cable Tray Installation 10 15-May-25 27-May-25 Cable Tray Installation

VTR-3B-ECT.115 Cable Tray Inspection 10 27-May-25 11-Jun-25 Cable Tray Inspection

VTR-3B-ECT.125 LV Cable pulling 10 11-Jun-25 23-Jun-25 LV Cable pulling

VTR-3B-ECT.135 LV Cable Termination 10 23-Jun-25 05-Jul-25 LV Cable Termination

VTR-3B-ECT.145 LV Cable Initial Testing 8 05-Jul-25 14-Jul-25 LV Cable Initial Testing

SMALL POWER SYSTEM 39 15-May-25 03-Jul-25 03-Jul-25, SMALL POWER SYSTEM


VTR-3B-ESP.105 Small Power Conduit and boxes Installation 12 15-May-25 29-May-25 Small Power Conduit and boxes Installation

VTR-3B-ESP.115 Small Power Cable Pulling 10 29-May-25 14-Jun-25 Small Power Cable Pulling

VTR-3B-ESP.125 Small Power Installations 6 14-Jun-25 21-Jun-25 Small Power Installations

VTR-3B-ESP.135 Small Power Termination 6 21-Jun-25 28-Jun-25 Small Power Termination

VTR-3B-ESP.145 Small Power Initial Testing 5 28-Jun-25 03-Jul-25 Small Power Initial Testing

POWER DISTRIBUTION 39 15-May-25 03-Jul-25 03-Jul-25, POWER DISTRIBUTION


GENERATOR 39 15-May-25 03-Jul-25 03-Jul-25, GENERATOR
VTR-3B-EPD.105 Generator Cable Tray Installation 7 15-May-25 24-May-25 Generator Cable Tray Installation

VTR-3B-EPD.115 Generator Cable Pulling 7 24-May-25 01-Jun-25 Generator Cable Pulling

VTR-3B-EPD.125 Generator Cell Pannel Installation 7 01-Jun-25 12-Jun-25 Generator Cell Pannel Installation

VTR-3B-EPD.135 Generator Installation 7 12-Jun-25 21-Jun-25 Generator Installation

VTR-3B-EPD.145 Generator Pannel / Cable Termination 7 21-Jun-25 29-Jun-25 Generator Pannel / Cable Termination

VTR-3B-EPD.155 Generator Pannel / Cable initial Testing 5 29-Jun-25 03-Jul-25 Generator Pannel / Cable initial Testing

UPS 28 24-May-25 29-Jun-25 29-Jun-25, UPS


VTR-3B-EPD.165 UPS Cable Tray Installation 5 24-May-25 29-May-25 UPS Cable Tray Installation

VTR-3B-EPD.175 UPS Cable Pulling 5 29-May-25 04-Jun-25 UPS Cable Pulling

VTR-3B-EPD.185 UPS Pannel Installation 5 04-Jun-25 14-Jun-25 UPS Pannel Installation

VTR-3B-EPD.195 UPS Installation 5 14-Jun-25 19-Jun-25 UPS Installation

VTR-3B-EPD.205 UPS Pannel / Cable Termination 5 19-Jun-25 24-Jun-25 UPS Pannel / Cable Termination

VTR-3B-EPD.215 UPS Pannel / Cable initial Testing 4 25-Jun-25 29-Jun-25 UPS Pannel / Cable initial Testing

MDB 33 24-May-25 03-Jul-25 03-Jul-25, MDB


VTR-3B-EPD.225 MDB Cable Tray Installation 7 24-May-25 01-Jun-25 MDB Cable Tray Installation

VTR-3B-EPD.235 MDB Cable Pulling 7 01-Jun-25 12-Jun-25 MDB Cable Pulling

VTR-3B-EPD.245 MDB Pannel Installation 7 12-Jun-25 21-Jun-25 MDB Pannel Installation

VTR-3B-EPD.255 MDB Pannel / Cable Termination 7 21-Jun-25 29-Jun-25 MDB Pannel / Cable Termination

VTR-3B-EPD.265 MDB Pannel / Cable initial Testing 5 29-Jun-25 03-Jul-25 MDB Pannel / Cable initial Testing

MCC 33 24-May-25 03-Jul-25 03-Jul-25, MCC


VTR-3B-EPD.325 MCC Cable Tray Installation 7 24-May-25 01-Jun-25 MCC Cable Tray Installation

VTR-3B-EPD.335 MCC Cable Pulling 7 01-Jun-25 12-Jun-25 MCC Cable Pulling

VTR-3B-EPD.345 MCC Pannel Installation 7 12-Jun-25 21-Jun-25 MCC Pannel Installation

VTR-3B-EPD.355 MCC Pannel / Cable Termination 7 21-Jun-25 29-Jun-25 MCC Pannel / Cable Termination

VTR-3B-EPD.365 MCC Pannel / Cable initial Testing 5 29-Jun-25 03-Jul-25 MCC Pannel / Cable initial Testing

SMSB 24 24-May-25 23-Jun-25 23-Jun-25, SMSB


VTR-3B-EPD.275 SMSB Cable Tray Installation 5 24-May-25 29-May-25 SMSB Cable Tray Installation

VTR-3B-EPD.285 SMSB Cable Pulling 5 29-May-25 04-Jun-25 SMSB Cable Pulling

VTR-3B-EPD.295 SMSB Pannel Installation 5 04-Jun-25 14-Jun-25 SMSB Pannel Installation

VTR-3B-EPD.305 SMSB Pannel / Cable Termination 5 14-Jun-25 19-Jun-25 SMSB Pannel / Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
61 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-EPD.315 SMSB Pannel / Cable initial Testing 4 19-Jun-25 23-Jun-25 SMSB Pannel / Cable initial Testing

DB 24 24-May-25 23-Jun-25 23-Jun-25, DB


VTR-3B-EPD.375 DB Cable Tray Installation 5 24-May-25 29-May-25 DB Cable Tray Installation

VTR-3B-EPD.385 DB Cable Pulling 5 29-May-25 04-Jun-25 DB Cable Pulling

VTR-3B-EPD.395 DB Pannel Installation 5 04-Jun-25 14-Jun-25 DB Pannel Installation

VTR-3B-EPD.405 DB Pannel / Cable Termination 5 14-Jun-25 19-Jun-25 DB Pannel / Cable Termination

VTR-3B-EPD.415 DB Pannel / Cable initial Testing 4 19-Jun-25 23-Jun-25 DB Pannel / Cable initial Testing

ISOLATOR 24 24-May-25 23-Jun-25 23-Jun-25, ISOLATOR


VTR-3B-EPD.425 Isolators Cable Tray Installation 5 24-May-25 29-May-25 Isolators Cable Tray Installation

VTR-3B-EPD.435 Isolators Cable Pulling 5 29-May-25 04-Jun-25 Isolators Cable Pulling

VTR-3B-EPD.445 Isolators Pannel Installation 5 04-Jun-25 14-Jun-25 Isolators Pannel Installation

VTR-3B-EPD.455 Isolators Pannel / Cable Termination 5 14-Jun-25 19-Jun-25 Isolators Pannel / Cable Termination

VTR-3B-EPD.465 Isolators Pannel / Cable initial Testing 4 19-Jun-25 23-Jun-25 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 24-May-25 23-Jun-25 23-Jun-25, LCP/ ELCP


VTR-3B-EPD.475 LCP/ELCP Cable Tray Installation 5 24-May-25 29-May-25 LCP/ELCP Cable Tray Installation

VTR-3B-EPD.485 LCP/ELCP Cable Pulling 5 29-May-25 04-Jun-25 LCP/ELCP Cable Pulling

VTR-3B-EPD.495 LCP/ELCP Pannel Installation 5 04-Jun-25 14-Jun-25 LCP/ELCP Pannel Installation

VTR-3B-EPD.505 LCP/ELCP Pannel / Cable Termination 5 14-Jun-25 19-Jun-25 LCP/ELCP Pannel / Cable Termination

VTR-3B-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 19-Jun-25 23-Jun-25 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 29-May-25 30-Jul-25 30-Jul-25, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 29-May-25 20-Jul-25 20-Jul-25, FIRE ALARM SYSTEM
VTR-3B-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 29-May-25 12-Jun-25 Fire Alarm Conduit /Cable Tray Installation

VTR-3B-ELFA.115 Fire Alarm Cable Pulling 9 12-Jun-25 23-Jun-25 Fire Alarm Cable Pulling

VTR-3B-ELFA.125 Fire Alarm Devices Installation 9 23-Jun-25 03-Jul-25 Fire Alarm Devices Installation

VTR-3B-ELFA.135 Fire Alarm Devices and Cable Termination 9 03-Jul-25 14-Jul-25 Fire Alarm Devices and Cable Termination

VTR-3B-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 14-Jul-25 20-Jul-25 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 12-Jun-25 30-Jul-25 30-Jul-25, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-3B-ELVS.105 ICT System Conduit /Cable Tray Installation 9 12-Jun-25 23-Jun-25 ICT System Conduit /Cable Tray Installation

VTR-3B-ELVS.115 ICT System Cable Pulling 9 23-Jun-25 03-Jul-25 ICT System Cable Pulling

VTR-3B-ELVS.125 ICT System Devices Installation 9 03-Jul-25 14-Jul-25 ICT System Devices Installation

VTR-3B-ELVS.135 ICT System Devices and Cable Termination 9 14-Jul-25 23-Jul-25 ICT System Devices and Cable Termination

VTR-3B-ELVS.145 ICT System Devices and Cable initial Testing 6 24-Jul-25 30-Jul-25 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 12-Jun-25 30-Jul-25 30-Jul-25, ACCESS CONTROL SYSTEM


VTR-3B-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 12-Jun-25 23-Jun-25 Access Control System Conduit /Cable Tray Installation

VTR-3B-ELAC.115 Access Control System Cable Pulling 9 23-Jun-25 03-Jul-25 Access Control System Cable Pulling

VTR-3B-ELAC.125 Access Control System Devices Installation 9 03-Jul-25 14-Jul-25 Access Control System Devices Installation

VTR-3B-ELAC.135 Access Control System Devices and Cable Termination 9 14-Jul-25 23-Jul-25 Access Control System Devices and Cable Termination

VTR-3B-ELAC.145 Access Control System Devices and Cable initial Testing 6 24-Jul-25 30-Jul-25 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 12-Jun-25 30-Jul-25 30-Jul-25, PUBLIC ADDRESS SYSTEM


VTR-3B-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 12-Jun-25 23-Jun-25 Public Address System Conduit /Cable Tray Installation

VTR-3B-ELPA.115 Public Address System Cable Pulling 9 23-Jun-25 03-Jul-25 Public Address System Cable Pulling

VTR-3B-ELPA.125 Public Address System Devices Installation 9 03-Jul-25 14-Jul-25 Public Address System Devices Installation

VTR-3B-ELPA.135 Public Address System Devices and Cable Termination 9 14-Jul-25 23-Jul-25 Public Address System Devices and Cable Termination

VTR-3B-ELPA.145 Public Address System Devices and Cable initial Testing 6 24-Jul-25 30-Jul-25 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 12-Jun-25 30-Jul-25 30-Jul-25, SCADA SYSTEM


VTR-3B-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 12-Jun-25 23-Jun-25 SCADA System Conduit /Cable Tray Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
62 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-3B-ELSC.115 SCADA System Cable Pulling 9 23-Jun-25 03-Jul-25 SCADA System Cable Pulling

VTR-3B-ELSC.125 SCADA System Devices Installation 9 03-Jul-25 14-Jul-25 SCADA System Devices Installation

VTR-3B-ELSC.135 SCADA System Devices and Cable Termination 9 14-Jul-25 23-Jul-25 SCADA System Devices and Cable Termination

VTR-3B-ELSC.145 SCADA System Devices and Cable initial Testing 6 24-Jul-25 30-Jul-25 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 12-Jun-25 30-Jul-25 30-Jul-25, RADIO RE- BROADCOASTING/ TETRA
VTR-3B-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 12-Jun-25 23-Jun-25 Radio/TETRA System Conduit /Cable Tray Installation

VTR-3B-ELRD.115 Radio/TETRA System Cable Pulling 9 23-Jun-25 03-Jul-25 Radio/TETRA System Cable Pulling

VTR-3B-ELRD.125 Radio/TETRA System Devices Installation 9 03-Jul-25 14-Jul-25 Radio/TETRA System Devices Installation

VTR-3B-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 14-Jul-25 23-Jul-25 Radio/TETRA System Devices and Cable Termination

VTR-3B-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 24-Jul-25 30-Jul-25 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 68 24-May-25 14-Aug-25 14-Aug-25, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 24-May-25 24-Jun-25 24-Jun-25, FIRE FIGHTING
VTR-3B-MFF.105 Fire Fighting system Pipe and accessories installation 21 24-May-25 21-Jun-25 Fire Fighting system Pipe and accessories installation

VTR-3B-MFF.115 Fire Fighting system deluge valve installation 16 29-May-25 21-Jun-25 Fire Fighting system deluge valve installation

VTR-3B-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 14-Jun-25 21-Jun-25 Fire Fighting system fire hose cabinet/extingusher installation

VTR-3B-MFF.140 Fire Fighting system initial testing 3 21-Jun-25 24-Jun-25 Fire Fighting system initial testing

VTR-3B-MFF.145 Fire Fighting clean agent system 2 18-Jun-25 21-Jun-25 Fire Fighting clean agent system

HVAC 47 21-Jun-25 14-Aug-25 14-Aug-25, HVAC


VTR-3B-MHV.115 Air conditioning system installation 12 23-Jul-25 06-Aug-25 Air conditioning system installation

VTR-3B-MHV.120 Fan installation 15 20-Jul-25 06-Aug-25 Fan installation

VTR-3B-MHV.125 Duct and accessories installation 28 21-Jun-25 23-Jul-25 Duct and accessories installation

VTR-3B-MHV.135 HVAC inital testing 7 06-Aug-25 14-Aug-25 HVAC inital testing

PLUMBING 8 21-Jun-25 30-Jun-25 30-Jun-25, PLUMBING


VTR-3B-MPL.105 Plumbing drainage system installation 6 21-Jun-25 28-Jun-25 Plumbing drainage system installation

VTR-3B-MPL.115 Plumbing drainage system initial testing 2 28-Jun-25 30-Jun-25 Plumbing drainage system initial testing

DRY UTILTIES 18 24-May-25 17-Jun-25 17-Jun-25, DRY UTILTIES


POWER 18 24-May-25 17-Jun-25 17-Jun-25, POWER
POWER LV 16 24-May-25 15-Jun-25 15-Jun-25, POWER LV
DU-P-LV.410 Installation of support 1 24-May-25 25-May-25 Installation of support

DU-P-LV.415 Installation of horizontal busbar 2 25-May-25 26-May-25 Installation of horizontal busbar

DU-P-LV.420 Installation of vertical busbar 2 26-May-25 28-May-25 Installation of vertical busbar

DU-P-LV.425 Installation of left/right elbow 2 28-May-25 31-May-25 Installation of left/right elbow

DU-P-LV.430 Installation of right horizintal offset 2 31-May-25 01-Jun-25 Installation of right horizintal offset

DU-P-LV.435 Instalaltion of upward vertical offset 3 01-Jun-25 04-Jun-25 Instalaltion of upward vertical offset

DU-P-LV.440 Installation of downward vertical offset 3 04-Jun-25 12-Jun-25 Installation of downward vertical offset

DU-P-LV.445 Installation of transformer and panel connection 2 12-Jun-25 15-Jun-25 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 25-May-25 17-Jun-25 17-Jun-25, MEDIUM VOLTAGE


DU-P-MV.410 Installation of cable try, arm, racks and ladder 6 25-May-25 01-Jun-25 Installation of cable try, arm, racks and ladder

DU-P-MV.415 Installation of MV Cable 4 01-Jun-25 09-Jun-25 Installation of MV Cable

DU-P-MV.420 Installation of cable cleats 2 09-Jun-25 11-Jun-25 Installation of cable cleats

DU-P-MV.425 Installation of gland 1 11-Jun-25 12-Jun-25 Installation of gland

DU-P-MV.430 splicing/termination of MV cable 2 12-Jun-25 14-Jun-25 splicing/termination of MV cable

DU-P-MV.435 Testing and Pre-commissioning of cable 2 14-Jun-25 16-Jun-25 Testing and Pre-commissioning of cable

DU-P-MV.440 Energezation 2 16-Jun-25 17-Jun-25 Energezation

VECHICULAR ROOM 11 (IN ZONE 10) 506 24-May-23 16-Jan-25 16-Jan-25, VECHICULAR ROOM 11 (IN ZONE 10)
ENGINEERING 151 24-May-23 20-Nov-23 20-Nov-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 151 24-May-23 20-Nov-23 20-Nov-23, SHOP DRAWING SUBMITTALAND APPROVAL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
63 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EARTH WORKS 96 24-May-23 16-Sep-23 16-Sep-23, EARTH WORKS
T2-ENG-VR11-SI.923 Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

T2-ENG-VR11-SI.924 Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

T2-ENG-VR11-SI.925 Soil Improvement Design Preparation & Submission 14 15-Aug-23 30-Aug-23 Soil Improvement Design Preparation & Submission

T3-ENG-VR11-SI.930 Soil Improvement Design Review & Approval 14 31-Aug-23 16-Sep-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VR.11-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VR.11-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VR.11-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VR.11-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VR.11-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VR.11-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VR.11-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VR.11-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VR.11-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VR.11-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


VR.11-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VR.11-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VR.11-ENG-EL-CT.110Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VR.11-ENG-EL-CT.115Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VR.11-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VR.11-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VR.11-ENG-EL-LS.110Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VR.11-ENG-EL-LS.115Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VR.11-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VR.11-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


VR.11-ENG-EL-LP.110Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

VR.11-ENG-EL-LP.115Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM


VR.11-ENG-EL-ES.110Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

VR.11-ENG-EL-ES.115Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VR.11-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VR.11-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VR.11-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VR.11-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
64 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR.11-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VR.11-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VR.11-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VR.11-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VR.11-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VR.11-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VR.11-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VR.11-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VR.11-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VR.11-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 151 24-May-23 20-Nov-23 20-Nov-23, DRY UTILITIES


POWER 151 24-May-23 20-Nov-23 20-Nov-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.500 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.505 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.500 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.505 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.500 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.505 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.500 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.505 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

MRMU 31 28-Aug-23 04-Oct-23 04-Oct-23, MRMU


DU-P-MRMU.500 Prepare and submit MRMU shopdrawings 20 28-Aug-23 20-Sep-23 Prepare and submit MRMU shopdrawings

DU-P-MRMU.505 Review and approval MRMU shopdrawings 11 20-Sep-23 04-Oct-23 Review and approval MRMU shopdrawings

MVSG 31 20-Sep-23 28-Oct-23 28-Oct-23, MVSG


DU-P-MVSG.500 Prepare and submit MVSG shopdrawings 20 20-Sep-23 15-Oct-23 Prepare and submit MVSG shopdrawings

DU-P-MVSG.505 Review and approval MVSG shopdrawings 11 15-Oct-23 28-Oct-23 Review and approval MVSG shopdrawings

BATTERY ROOM 31 15-Oct-23 20-Nov-23 20-Nov-23, BATTERY ROOM


DU-P-BARM.500 Prepare and submit Battery room shopdrawings 20 15-Oct-23 07-Nov-23 Prepare and submit Battery room shopdrawings

DU-P-BARM.505 Review and approval Battery room shopdrawings 11 07-Nov-23 20-Nov-23 Review and approval Battery room shopdrawings

PROCUREMENT 295 31-Oct-23 19-Oct-24 19-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 31-Oct-23 19-Nov-23 19-Nov-23, CIVIL/STRUCTURAL
VR.11-PRO-CV.110 Issue Purchase Order 6 31-Oct-23 07-Nov-23 Issue Purchase Order

VR.11-PRO-CV.115 Material Delivery 10 07-Nov-23 19-Nov-23 Material Delivery

MECHANICAL 126 19-May-24 19-Oct-24 19-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 19-May-24 24-Sep-24 24-Sep-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 19-May-24 24-Sep-24 24-Sep-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VR.11-PR-MC-FF.110 Issue Purchase Order 15 19-May-24 05-Jun-24 Issue Purchase Order

VR.11-PR-MC-FF.115 Material Delivery 90 05-Jun-24 24-Sep-24 Material Delivery

VENTILATION SYSTEM 105 19-May-24 24-Sep-24 24-Sep-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 19-May-24 24-Sep-24 24-Sep-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VR.11-PR-MC-DS.110Issue Purchase Order 15 19-May-24 05-Jun-24 Issue Purchase Order

VR.11-PR-MC-DS.115Material Delivery 90 05-Jun-24 24-Sep-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
65 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AIR CONDITIONING WORKS 105 19-May-24 24-Sep-24 24-Sep-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 19-May-24 24-Sep-24 24-Sep-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VR.11-PR-MC-AC.110Issue Purchase Order 15 19-May-24 05-Jun-24 Issue Purchase Order

VR.11-PR-MC-AC.115Material Delivery 90 05-Jun-24 24-Sep-24 Material Delivery

PLUMBING SYSTEM 105 12-Jun-24 19-Oct-24 19-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 12-Jun-24 19-Oct-24 19-Oct-24, PUMPS,PIPES,FITTINGS,VALVES
VR.11-PR-MC-PI.110 Issue Purchase Order 15 12-Jun-24 04-Jul-24 Issue Purchase Order

VR.11-PR-MC-PI.115 Material Delivery 90 04-Jul-24 19-Oct-24 Material Delivery

ELECTRICAL 132 04-May-24 10-Oct-24 10-Oct-24, ELECTRICAL


CABLE TRAY 105 11-May-24 15-Sep-24 15-Sep-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 11-May-24 15-Sep-24 15-Sep-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
VR.11-PR-EL-CT.110 Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VR.11-PR-EL-CT.115 Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

POWER CABLES 105 11-May-24 15-Sep-24 15-Sep-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 11-May-24 15-Sep-24 15-Sep-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VR.11-PR-EL-PC.110 Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VR.11-PR-EL-PC.115 Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

LIGHTING SYSTEM 105 11-May-24 15-Sep-24 15-Sep-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 11-May-24 15-Sep-24 15-Sep-24, CONDUIT,LIGHT
VR.11-PR-EL-LS.110 Issue Purchase Order 15 11-May-24 28-May-24 Issue Purchase Order

VR.11-PR-EL-LS.115 Material Delivery 90 28-May-24 15-Sep-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 19-May-24 24-Sep-24 24-Sep-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 19-May-24 24-Sep-24 24-Sep-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VR.11-PR-EL-EI.110 Issue Purchase Order 15 19-May-24 05-Jun-24 Issue Purchase Order

VR.11-PR-EL-EI.115 Material Delivery 90 05-Jun-24 24-Sep-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, LIGHTNING PROTECTION SYSTEM
VR.11-PR-EL-LP.110 Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

VR.11-PR-EL-LP.115 Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 04-May-24 08-Sep-24 08-Sep-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VR.11-PR-EL-ES.110 Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

VR.11-PR-EL-ES.115 Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

LOW CURRENT 114 25-May-24 10-Oct-24 10-Oct-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 25-May-24 30-Sep-24 30-Sep-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 25-May-24 30-Sep-24 30-Sep-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VR.11-PR-ELL-FA.20Issue Purchase Order 15 25-May-24 11-Jun-24 Issue Purchase Order

VR.11-PR-ELL-FA.25Material Delivery 90 11-Jun-24 30-Sep-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 04-Jun-24 10-Oct-24 10-Oct-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 04-Jun-24 10-Oct-24 10-Oct-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VR.11-PR-ELL-PH.20Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-PH.25Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 04-Jun-24 10-Oct-24 10-Oct-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VR.11-PR-ELL-PA.20Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-PA.25Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

VIDEO SURVEILLANCE 105 04-Jun-24 10-Oct-24 10-Oct-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 04-Jun-24 10-Oct-24 10-Oct-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VR.11-PR-ELL-VS.20Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-VS.25Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

ACCESS CONTROL SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 04-Jun-24 10-Oct-24 10-Oct-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
66 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR.11-PR-ELL-AC.20
Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-AC.25
Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 04-Jun-24 10-Oct-24 10-Oct-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VR.11-PR-ELL-RB.20Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-RB.25Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

SCADA SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 04-Jun-24 10-Oct-24 10-Oct-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VR.11-PR-ELL-SD.20Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

VR.11-PR-ELL-SD.25Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

CONSTRUCTION 482 21-Jun-23 16-Jan-25 16-Jan-25, CONSTRUCTION


EXCAVATION WORKS 44 21-Jun-23 14-Aug-23 14-Aug-23, EXCAVATION WORKS
T2-CON-VR11-EX.200 Excavation 44 21-Jun-23 14-Aug-23 Excavation

SOIL IMPROVEMENT WORKS 47 17-Sep-23 11-Nov-23 11-Nov-23, SOIL IMPROVEMENT WORKS


T2-CON-VR11-SI.220 Soil Improvement 47 17-Sep-23 11-Nov-23 Soil Improvement

STRUCTURAL WORKS 363 12-Nov-23 16-Jan-25 16-Jan-25, STRUCTURAL WORKS


FOUNDATION 60 12-Nov-23 21-Jan-24 21-Jan-24, FOUNDATION
Part-1 31 12-Nov-23 17-Dec-23 17-Dec-23, Part-1
VTR-11-FDN-P1.150 Foundation Blinding concrete casting casting 1 12-Nov-23 12-Nov-23 Foundation Blinding concrete casting casting

VTR-11-FDN-P1.155 Foundation water proofing on blinding concrete 3 13-Nov-23 15-Nov-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P1.160 Foundation Protection screed on water poofing 1 15-Nov-23 16-Nov-23 Foundation Protection screed on water poofing

VTR-11-FDN-P1.165 Foundation Curing for screed 2 16-Nov-23 19-Nov-23 Foundation Curing for screed

VTR-11-FDN-P1.170 Foundation Rebar installation 10 19-Nov-23 30-Nov-23 Foundation Rebar installation

VTR-11-FDN-P1.175 Foundation Formwork installation 8 30-Nov-23 10-Dec-23 Foundation Formwork installation

VTR-11-FDN-P1.180 Foundation Construction joint work 2 10-Dec-23 12-Dec-23 Foundation Construction joint work

VTR-11-FDN-P1.185 Foundation concrete casting 1 12-Dec-23 13-Dec-23 Foundation concrete casting

VTR-11-FDN-P1.190 Foundation concrete curing 1 13-Dec-23 14-Dec-23 Foundation concrete curing

VTR-11-FDN-P1.195 Foundation Formwork Removal 2 14-Dec-23 17-Dec-23 Foundation Formwork Removal

Part-2 31 19-Nov-23 25-Dec-23 25-Dec-23, Part-2


VTR-11-FDN-P2.150 Foundation Blinding concrete casting 1 19-Nov-23 20-Nov-23 Foundation Blinding concrete casting

VTR-11-FDN-P2.155 Foundation water proofing on blinding concrete 3 20-Nov-23 23-Nov-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P2.160 Foundation Protection screed on water poofing 1 23-Nov-23 25-Nov-23 Foundation Protection screed on water poofing

VTR-11-FDN-P2.165 Foundation Curing for screed 2 25-Nov-23 27-Nov-23 Foundation Curing for screed

VTR-11-FDN-P2.170 Foundation Rebar installation 10 27-Nov-23 09-Dec-23 Foundation Rebar installation

VTR-11-FDN-P2.175 Foundation Formwork installation 8 09-Dec-23 18-Dec-23 Foundation Formwork installation

VTR-11-FDN-P2.180 Foundation Construction joint work 2 18-Dec-23 20-Dec-23 Foundation Construction joint work

VTR-11-FDN-P2.185 Foundation concrete casting 1 20-Dec-23 21-Dec-23 Foundation concrete casting

VTR-11-FDN-P2.190 Foundation concrete curing 1 21-Dec-23 23-Dec-23 Foundation concrete curing

VTR-11-FDN-P2.195 Foundation Formwork Removal 2 23-Dec-23 25-Dec-23 Foundation Formwork Removal

Part-3 31 27-Nov-23 01-Jan-24 01-Jan-24, Part-3


VTR-11-FDN-P3.150 Foundation Blinding concrete casting 1 27-Nov-23 28-Nov-23 Foundation Blinding concrete casting

VTR-11-FDN-P3.155 Foundation water proofing on blinding concrete 3 28-Nov-23 02-Dec-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P3.160 Foundation Protection screed on water poofing 1 02-Dec-23 03-Dec-23 Foundation Protection screed on water poofing

VTR-11-FDN-P3.165 Foundation Curing for screed 2 03-Dec-23 05-Dec-23 Foundation Curing for screed

VTR-11-FDN-P3.170 Foundation Rebar installation 10 05-Dec-23 16-Dec-23 Foundation Rebar installation

VTR-11-FDN-P3.175 Foundation Formwork installation 8 17-Dec-23 25-Dec-23 Foundation Formwork installation

VTR-11-FDN-P3.180 Foundation Construction joint work 2 25-Dec-23 27-Dec-23 Foundation Construction joint work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
67 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-FDN-P3.185 Foundation concrete casting 1 27-Dec-23 28-Dec-23 Foundation concrete casting

VTR-11-FDN-P3.190 Foundation concrete curing 1 28-Dec-23 30-Dec-23 Foundation concrete curing

VTR-11-FDN-P3.195 Foundation Formwork Removal 2 30-Dec-23 01-Jan-24 Foundation Formwork Removal

Part-4 31 05-Dec-23 09-Jan-24 09-Jan-24, Part-4


VTR-11-FDN-P4.150 Foundation Blinding concrete casting 1 05-Dec-23 06-Dec-23 Foundation Blinding concrete casting

VTR-11-FDN-P4.155 Foundation water proofing on blinding concrete 3 06-Dec-23 09-Dec-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P4.160 Foundation Protection screed on water poofing 1 10-Dec-23 10-Dec-23 Foundation Protection screed on water poofing

VTR-11-FDN-P4.165 Foundation Curing for screed 2 10-Dec-23 12-Dec-23 Foundation Curing for screed

VTR-11-FDN-P4.170 Foundation Rebar installation 10 12-Dec-23 24-Dec-23 Foundation Rebar installation

VTR-11-FDN-P4.175 Foundation Formwork installation 8 24-Dec-23 02-Jan-24 Foundation Formwork installation

VTR-11-FDN-P4.180 Foundation Construction joint work 2 02-Jan-24 04-Jan-24 Foundation Construction joint work

VTR-11-FDN-P4.185 Foundation concrete casting 1 04-Jan-24 06-Jan-24 Foundation concrete casting

VTR-11-FDN-P4.190 Foundation concrete curing 1 06-Jan-24 07-Jan-24 Foundation concrete curing

VTR-11-FDN-P4.195 Foundation Formwork Removal 2 07-Jan-24 09-Jan-24 Foundation Formwork Removal

Part-5 31 10-Dec-23 15-Jan-24 15-Jan-24, Part-5


VTR-11-FDN-P5.150 Foundation Blinding concrete casting 1 10-Dec-23 11-Dec-23 Foundation Blinding concrete casting

VTR-11-FDN-P5.155 Foundation water proofing on blinding concrete 3 11-Dec-23 14-Dec-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P5.160 Foundation Protection screed on water poofing 1 14-Dec-23 16-Dec-23 Foundation Protection screed on water poofing

VTR-11-FDN-P5.165 Foundation Curing for screed 2 16-Dec-23 18-Dec-23 Foundation Curing for screed

VTR-11-FDN-P5.170 Foundation Rebar installation 10 18-Dec-23 30-Dec-23 Foundation Rebar installation

VTR-11-FDN-P5.175 Foundation Formwork installation 8 30-Dec-23 08-Jan-24 Foundation Formwork installation

VTR-11-FDN-P5.180 Foundation Construction joint work 2 08-Jan-24 10-Jan-24 Foundation Construction joint work

VTR-11-FDN-P5.185 Foundation concrete casting 1 10-Jan-24 11-Jan-24 Foundation concrete casting

VTR-11-FDN-P5.190 Foundation concrete curing 1 11-Jan-24 13-Jan-24 Foundation concrete curing

VTR-11-FDN-P5.195 Foundation Formwork Removal 2 13-Jan-24 15-Jan-24 Foundation Formwork Removal

Part-6 31 16-Dec-23 21-Jan-24 21-Jan-24, Part-6


VTR-11-FDN-P6.150 Foundation Blinding concrete casting 1 16-Dec-23 17-Dec-23 Foundation Blinding concrete casting

VTR-11-FDN-P6.155 Foundation water proofing on blinding concrete 3 17-Dec-23 20-Dec-23 Foundation water proofing on blinding concrete

VTR-11-FDN-P6.160 Foundation Protection screed on water poofing 1 20-Dec-23 21-Dec-23 Foundation Protection screed on water poofing

VTR-11-FDN-P6.165 Foundation Curing for screed 2 21-Dec-23 24-Dec-23 Foundation Curing for screed

VTR-11-FDN-P6.170 Foundation Rebar installation 10 24-Dec-23 04-Jan-24 Foundation Rebar installation

VTR-11-FDN-P6.175 Foundation Formwork installation 8 04-Jan-24 14-Jan-24 Foundation Formwork installation

VTR-11-FDN-P6.180 Foundation Construction joint work 2 14-Jan-24 16-Jan-24 Foundation Construction joint work

VTR-11-FDN-P6.185 Foundation concrete casting 1 16-Jan-24 17-Jan-24 Foundation concrete casting

VTR-11-FDN-P6.190 Foundation concrete curing 1 17-Jan-24 18-Jan-24 Foundation concrete curing

VTR-11-FDN-P6.195 Foundation Formwork Removal 2 18-Jan-24 21-Jan-24 Foundation Formwork Removal

WALL CONCRETE CASTING STAGE-1 65 13-Dec-23 27-Feb-24 27-Feb-24, WALL CONCRETE CASTING STAGE-1
Part-1 35 13-Dec-23 23-Jan-24 23-Jan-24, Part-1
VTR-11-WL-S1-P1.135Room Walls Rebar Installation 12 20-Dec-23 03-Jan-24 Room Walls Rebar Installation

VTR-11-WL-S1-P1.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 03-Jan-24 06-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P1.145Room Walls Formwork Installation 10 06-Jan-24 17-Jan-24 Room Walls Formwork Installation

VTR-11-WL-S1-P1.150Room Walls Concrete Casting 1 17-Jan-24 18-Jan-24 Room Walls Concrete Casting

VTR-11-WL-S1-P1.155Room Walls Curing work 1 18-Jan-24 20-Jan-24 Room Walls Curing work

VTR-11-WL-S1-P1.160Room Walls Formwork Removel 3 20-Jan-24 23-Jan-24 Room Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
68 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-WL-S1-P1.165Room Walls Scafolding for rebar 6 13-Dec-23 20-Dec-23 Room Walls Scafolding for rebar

Part-2 35 23-Dec-23 31-Jan-24 31-Jan-24, Part-2


VTR-11-WL-S1-P2.135Room Walls Rebar Installation 12 30-Dec-23 11-Jan-24 Room Walls Rebar Installation

VTR-11-WL-S1-P2.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 13-Jan-24 14-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P2.145Room Walls Formwork Installation 10 14-Jan-24 25-Jan-24 Room Walls Formwork Installation

VTR-11-WL-S1-P2.150Room Walls Concrete Casting 1 25-Jan-24 27-Jan-24 Room Walls Concrete Casting

VTR-11-WL-S1-P2.155Room Walls Curing work 1 27-Jan-24 28-Jan-24 Room Walls Curing work

VTR-11-WL-S1-P2.160Room Walls Formwork Removel 3 28-Jan-24 31-Jan-24 Room Walls Formwork Removel

VTR-11-WL-S1-P2.165Room Walls Scafolding for rebar 6 23-Dec-23 30-Dec-23 Room Walls Scafolding for rebar

Part-3 35 30-Dec-23 08-Feb-24 08-Feb-24, Part-3


VTR-11-WL-S1-P3.135Room Walls Rebar Installation 12 06-Jan-24 20-Jan-24 Room Walls Rebar Installation

VTR-11-WL-S1-P3.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 20-Jan-24 22-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P3.145Room Walls Formwork Installation 10 22-Jan-24 03-Feb-24 Room Walls Formwork Installation

VTR-11-WL-S1-P3.150Room Walls Concrete Casting 1 03-Feb-24 04-Feb-24 Room Walls Concrete Casting

VTR-11-WL-S1-P3.155Room Walls Curing work 1 04-Feb-24 05-Feb-24 Room Walls Curing work

VTR-11-WL-S1-P3.160Room Walls Formwork Removel 3 05-Feb-24 08-Feb-24 Room Walls Formwork Removel

VTR-11-WL-S1-P3.165Room Walls Scafolding for rebar 6 30-Dec-23 06-Jan-24 Room Walls Scafolding for rebar

Part-4 35 07-Jan-24 17-Feb-24 17-Feb-24, Part-4


VTR-11-WL-S1-P4.135Room Walls Rebar Installation 12 14-Jan-24 28-Jan-24 Room Walls Rebar Installation

VTR-11-WL-S1-P4.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 28-Jan-24 30-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P4.145Room Walls Formwork Installation 10 30-Jan-24 11-Feb-24 Room Walls Formwork Installation

VTR-11-WL-S1-P4.150Room Walls Concrete Casting 1 11-Feb-24 12-Feb-24 Room Walls Concrete Casting

VTR-11-WL-S1-P4.155Room Walls Curing work 1 12-Feb-24 13-Feb-24 Room Walls Curing work

VTR-11-WL-S1-P4.160Room Walls Formwork Removel 3 13-Feb-24 17-Feb-24 Room Walls Formwork Removel

VTR-11-WL-S1-P4.165Room Walls Scafolding for rebar 6 07-Jan-24 14-Jan-24 Room Walls Scafolding for rebar

Part-5 35 13-Jan-24 22-Feb-24 22-Feb-24, Part-5


VTR-11-WL-S1-P5.135Room Walls Rebar Installation 12 20-Jan-24 03-Feb-24 Room Walls Rebar Installation

VTR-11-WL-S1-P5.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 03-Feb-24 05-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P5.145Room Walls Formwork Installation 10 05-Feb-24 17-Feb-24 Room Walls Formwork Installation

VTR-11-WL-S1-P5.150Room Walls Concrete Casting 1 17-Feb-24 18-Feb-24 Room Walls Concrete Casting

VTR-11-WL-S1-P5.155Room Walls Curing work 1 18-Feb-24 19-Feb-24 Room Walls Curing work

VTR-11-WL-S1-P5.160Room Walls Formwork Removel 3 19-Feb-24 22-Feb-24 Room Walls Formwork Removel

VTR-11-WL-S1-P5.165Room Walls Scafolding for rebar 6 13-Jan-24 20-Jan-24 Room Walls Scafolding for rebar

Part-6 35 18-Jan-24 27-Feb-24 27-Feb-24, Part-6


VTR-11-WL-S1-P6.135Room Walls Rebar Installation 12 25-Jan-24 07-Feb-24 Room Walls Rebar Installation

VTR-11-WL-S1-P6.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 08-Feb-24 10-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S1-P6.145Room Walls Formwork Installation 10 10-Feb-24 21-Feb-24 Room Walls Formwork Installation

VTR-11-WL-S1-P6.150Room Walls Concrete Casting 1 21-Feb-24 22-Feb-24 Room Walls Concrete Casting

VTR-11-WL-S1-P6.155Room Walls Curing work 1 22-Feb-24 24-Feb-24 Room Walls Curing work

VTR-11-WL-S1-P6.160Room Walls Formwork Removel 3 24-Feb-24 27-Feb-24 Room Walls Formwork Removel

VTR-11-WL-S1-P6.165Room Walls Scafolding for rebar 6 18-Jan-24 25-Jan-24 Room Walls Scafolding for rebar

INTERMEDIATE SLAB 103 23-Jan-24 26-May-24 26-May-24, INTERMEDIATE SLAB


Part-1 52 23-Jan-24 23-Mar-24 23-Mar-24, Part-1
VTR-11-IS-P1.125 Room Internediate Slab Formwork Installation 21 23-Jan-24 17-Feb-24 Room Internediate Slab Formwork Installation

VTR-11-IS-P1.130 Room Internediate Slab Rebar Installation 12 17-Feb-24 02-Mar-24 Room Internediate Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
69 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-IS-P1.135 Room Internediate Slab Concrete Casting 1 02-Mar-24 03-Mar-24 Room Internediate Slab Concrete Casting

VTR-11-IS-P1.140 Room Internediate slab Curing work 12 03-Mar-24 16-Mar-24 Room Internediate slab Curing work

VTR-11-IS-P1.145 Room Internediate Slab Formwork Removel 6 17-Mar-24 23-Mar-24 Room Internediate Slab Formwork Removel

Part-2 52 23-Mar-24 26-May-24 26-May-24, Part-2


VTR-11-IS-P2.125 Room Internediate Slab Formwork Installation 21 23-Mar-24 20-Apr-24 Room Internediate Slab Formwork Installation

VTR-11-IS-P2.130 Room Internediate Slab Rebar Installation 12 20-Apr-24 04-May-24 Room Internediate Slab Rebar Installation

VTR-11-IS-P2.135 Room Internediate Slab Concrete Casting 1 04-May-24 05-May-24 Room Internediate Slab Concrete Casting

VTR-11-IS-P2.140 Room Internediate slab Curing work 12 05-May-24 19-May-24 Room Internediate slab Curing work

VTR-11-IS-P2.145 Room Internediate Slab Formwork Removel 6 19-May-24 26-May-24 Room Internediate Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 64 03-Mar-24 19-May-24 19-May-24, WALL CONCRETE CASTING STAGE-2
Part-1 34 03-Mar-24 14-Apr-24 14-Apr-24, Part-1
VTR-11-WL-S2-P3.135Room Walls Rebar Installation 12 10-Mar-24 23-Mar-24 Room Walls Rebar Installation

VTR-11-WL-S2-P3.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 23-Mar-24 25-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S2-P3.145Room Walls Formwork Installation 9 25-Mar-24 04-Apr-24 Room Walls Formwork Installation

VTR-11-WL-S2-P3.150Room Walls Concrete Casting 1 04-Apr-24 06-Apr-24 Room Walls Concrete Casting

VTR-11-WL-S2-P3.155Room Walls Curing work 1 06-Apr-24 07-Apr-24 Room Walls Curing work

VTR-11-WL-S2-P3.160Room Walls Formwork Removel 3 07-Apr-24 14-Apr-24 Room Walls Formwork Removel

VTR-11-WL-S2-P3.165Room Walls Scafolding for rebar 6 03-Mar-24 09-Mar-24 Room Walls Scafolding for rebar

Part-2 34 06-Apr-24 19-May-24 19-May-24, Part-2


VTR-11-WL-S2-P4.135Room Walls Rebar Installation 12 16-Apr-24 30-Apr-24 Room Walls Rebar Installation

VTR-11-WL-S2-P4.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 30-Apr-24 02-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-S2-P4.145Room Walls Formwork Installation 9 02-May-24 13-May-24 Room Walls Formwork Installation

VTR-11-WL-S2-P4.150Room Walls Concrete Casting 1 13-May-24 14-May-24 Room Walls Concrete Casting

VTR-11-WL-S2-P4.155Room Walls Curing work 1 14-May-24 15-May-24 Room Walls Curing work

VTR-11-WL-S2-P4.160Room Walls Formwork Removel 3 15-May-24 19-May-24 Room Walls Formwork Removel

VTR-11-WL-S2-P4.165Room Walls Scafolding for rebar 6 06-Apr-24 16-Apr-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 119 08-Feb-24 04-Jul-24 04-Jul-24, TOP SLAB BELOW GROUND LEVEL
Part-1 36 14-Apr-24 26-May-24 26-May-24, Part-1
VTR-11-TS-P1.125 Room Top Slab Formwork Installation 12 14-Apr-24 28-Apr-24 Room Top Slab Formwork Installation

VTR-11-TS-P1.130 Room Top Slab Rebar Installation 7 28-Apr-24 06-May-24 Room Top Slab Rebar Installation

VTR-11-TS-P1.135 Room Top Slab Concrete Casting 1 06-May-24 07-May-24 Room Top Slab Concrete Casting

VTR-11-TS-P1.140 Room Top slab Curing work 12 07-May-24 21-May-24 Room Top slab Curing work

VTR-11-TS-P1.145 Room Top Slab Formwork Removel 4 21-May-24 26-May-24 Room Top Slab Formwork Removel

Part-2 36 19-May-24 04-Jul-24 04-Jul-24, Part-2


VTR-11-TS-P2.125 Room Top Slab Formwork Installation 12 19-May-24 02-Jun-24 Room Top Slab Formwork Installation

VTR-11-TS-P2.130 Room Top Slab Rebar Installation 7 02-Jun-24 10-Jun-24 Room Top Slab Rebar Installation

VTR-11-TS-P2.135 Room Top Slab Concrete Casting 1 10-Jun-24 11-Jun-24 Room Top Slab Concrete Casting

VTR-11-TS-P2.140 Room Top slab Curing work 12 11-Jun-24 30-Jun-24 Room Top slab Curing work

VTR-11-TS-P2.145 Room Top Slab Formwork Removel 4 30-Jun-24 04-Jul-24 Room Top Slab Formwork Removel

Part-3 36 08-Feb-24 21-Mar-24 21-Mar-24, Part-3


VTR-11-TS-P3.125 Room Top Slab Formwork Installation 12 08-Feb-24 22-Feb-24 Room Top Slab Formwork Installation

VTR-11-TS-P3.130 Room Top Slab Rebar Installation 7 22-Feb-24 02-Mar-24 Room Top Slab Rebar Installation

VTR-11-TS-P3.135 Room Top Slab Concrete Casting 1 02-Mar-24 03-Mar-24 Room Top Slab Concrete Casting

VTR-11-TS-P3.140 Room Top slab Curing work 12 03-Mar-24 17-Mar-24 Room Top slab Curing work

VTR-11-TS-P3.145 Room Top Slab Formwork Removel 4 17-Mar-24 21-Mar-24 Room Top Slab Formwork Removel

Part-4 36 17-Feb-24 30-Mar-24 30-Mar-24, Part-4

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
70 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-TS-P4.125 Room Top Slab Formwork Installation 12 17-Feb-24 02-Mar-24 Room Top Slab Formwork Installation

VTR-11-TS-P4.130 Room Top Slab Rebar Installation 7 02-Mar-24 10-Mar-24 Room Top Slab Rebar Installation

VTR-11-TS-P4.135 Room Top Slab Concrete Casting 1 10-Mar-24 11-Mar-24 Room Top Slab Concrete Casting

VTR-11-TS-P4.140 Room Top slab Curing work 12 11-Mar-24 25-Mar-24 Room Top slab Curing work

VTR-11-TS-P4.145 Room Top Slab Formwork Removel 4 25-Mar-24 30-Mar-24 Room Top Slab Formwork Removel

Part-5 36 22-Feb-24 04-Apr-24 04-Apr-24, Part-5


VTR-11-TS-P5.125 Room Top Slab Formwork Installation 12 22-Feb-24 07-Mar-24 Room Top Slab Formwork Installation

VTR-11-TS-P5.130 Room Top Slab Rebar Installation 7 07-Mar-24 16-Mar-24 Room Top Slab Rebar Installation

VTR-11-TS-P5.135 Room Top Slab Concrete Casting 1 16-Mar-24 17-Mar-24 Room Top Slab Concrete Casting

VTR-11-TS-P5.140 Room Top slab Curing work 12 17-Mar-24 31-Mar-24 Room Top slab Curing work

VTR-11-TS-P5.145 Room Top Slab Formwork Removel 4 31-Mar-24 04-Apr-24 Room Top Slab Formwork Removel

Part-6 36 27-Feb-24 13-Apr-24 13-Apr-24, Part-6


VTR-11-TS-P6.125 Room Top Slab Formwork Installation 12 27-Feb-24 12-Mar-24 Room Top Slab Formwork Installation

VTR-11-TS-P6.130 Room Top Slab Rebar Installation 7 12-Mar-24 20-Mar-24 Room Top Slab Rebar Installation

VTR-11-TS-P6.135 Room Top Slab Concrete Casting 1 20-Mar-24 21-Mar-24 Room Top Slab Concrete Casting

VTR-11-TS-P6.140 Room Top slab Curing work 12 21-Mar-24 04-Apr-24 Room Top slab Curing work

VTR-11-TS-P6.145 Room Top Slab Formwork Removel 4 04-Apr-24 13-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 104 21-Mar-24 29-Jul-24 29-Jul-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 79 21-Mar-24 30-Jun-24 30-Jun-24, WALL CONCRETE CASTING STAGE-1
Part-1 26 26-May-24 30-Jun-24 30-Jun-24, Part-1
VTR-11-WL-SG1-P1.135
Room Walls Rebar Installation 7 02-Jun-24 10-Jun-24 Room Walls Rebar Installation

VTR-11-WL-SG1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 10-Jun-24 12-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG1-P1.145
Room Walls Formwork Installation 6 12-Jun-24 24-Jun-24 Room Walls Formwork Installation

VTR-11-WL-SG1-P1.150
Room Walls Concrete Casting 1 24-Jun-24 25-Jun-24 Room Walls Concrete Casting

VTR-11-WL-SG1-P1.155
Room Walls Curing work 1 25-Jun-24 26-Jun-24 Room Walls Curing work

VTR-11-WL-SG1-P1.160
Room Walls Formwork Removel 3 26-Jun-24 30-Jun-24 Room Walls Formwork Removel

VTR-11-WL-SG1-P1.165
Room Walls Scafolding for rebar 6 26-May-24 02-Jun-24 Room Walls Scafolding for rebar

Part-3 25 21-Mar-24 23-Apr-24 23-Apr-24, Part-3


VTR-11-WL-SG1-P3.135
Room Walls Rebar Installation 7 28-Mar-24 06-Apr-24 Room Walls Rebar Installation

VTR-11-WL-SG1-P3.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 06-Apr-24 08-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG1-P3.145
Room Walls Formwork Installation 5 08-Apr-24 17-Apr-24 Room Walls Formwork Installation

VTR-11-WL-SG1-P3.150
Room Walls Concrete Casting 1 17-Apr-24 18-Apr-24 Room Walls Concrete Casting

VTR-11-WL-SG1-P3.155
Room Walls Curing work 1 18-Apr-24 20-Apr-24 Room Walls Curing work

VTR-11-WL-SG1-P3.160
Room Walls Formwork Removel 3 20-Apr-24 23-Apr-24 Room Walls Formwork Removel

VTR-11-WL-SG1-P3.165
Room Walls Scafolding for rebar 6 21-Mar-24 28-Mar-24 Room Walls Scafolding for rebar

Part-4 25 30-Mar-24 01-May-24 01-May-24, Part-4


VTR-11-WL-SG1-P4.135
Room Walls Rebar Installation 7 06-Apr-24 17-Apr-24 Room Walls Rebar Installation

VTR-11-WL-SG1-P4.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 17-Apr-24 20-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG1-P4.145
Room Walls Formwork Installation 5 20-Apr-24 25-Apr-24 Room Walls Formwork Installation

VTR-11-WL-SG1-P4.150
Room Walls Concrete Casting 1 25-Apr-24 27-Apr-24 Room Walls Concrete Casting

VTR-11-WL-SG1-P4.155
Room Walls Curing work 1 27-Apr-24 28-Apr-24 Room Walls Curing work

VTR-11-WL-SG1-P4.160
Room Walls Formwork Removel 3 28-Apr-24 01-May-24 Room Walls Formwork Removel

VTR-11-WL-SG1-P4.165
Room Walls Scafolding for rebar 6 30-Mar-24 06-Apr-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-2 79 23-Apr-24 29-Jul-24 29-Jul-24, WALL CONCRETE CASTING STAGE-2
Part-1 25 30-Jun-24 29-Jul-24 29-Jul-24, Part-1
VTR-11-WL-SG2-P1.135
Room Walls Rebar Installation 7 07-Jul-24 15-Jul-24 Room Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
71 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-WL-SG2-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 15-Jul-24 17-Jul-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG2-P1.145
Room Walls Formwork Installation 5 17-Jul-24 23-Jul-24 Room Walls Formwork Installation

VTR-11-WL-SG2-P1.150
Room Walls Concrete Casting 1 23-Jul-24 24-Jul-24 Room Walls Concrete Casting

VTR-11-WL-SG2-P1.155
Room Walls Curing work 1 24-Jul-24 25-Jul-24 Room Walls Curing work

VTR-11-WL-SG2-P1.160
Room Walls Formwork Removel 3 25-Jul-24 29-Jul-24 Room Walls Formwork Removel

VTR-11-WL-SG2-P1.165
Room Walls Scafolding for rebar 6 30-Jun-24 07-Jul-24 Room Walls Scafolding for rebar

Part-3 26 23-Apr-24 23-May-24 23-May-24, Part-3


VTR-11-WL-SG2-P3.135
Room Walls Rebar Installation 7 30-Apr-24 08-May-24 Room Walls Rebar Installation

VTR-11-WL-SG2-P3.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 08-May-24 11-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG2-P3.145
Room Walls Formwork Installation 6 11-May-24 18-May-24 Room Walls Formwork Installation

VTR-11-WL-SG2-P3.150
Room Walls Concrete Casting 1 18-May-24 19-May-24 Room Walls Concrete Casting

VTR-11-WL-SG2-P3.155
Room Walls Curing work 1 19-May-24 20-May-24 Room Walls Curing work

VTR-11-WL-SG2-P3.160
Room Walls Formwork Removel 3 20-May-24 23-May-24 Room Walls Formwork Removel

VTR-11-WL-SG2-P3.165
Room Walls Scafolding for rebar 6 23-Apr-24 30-Apr-24 Room Walls Scafolding for rebar

Part-4 26 01-May-24 01-Jun-24 01-Jun-24, Part-4


VTR-11-WL-SG2-P4.135
Room Walls Rebar Installation 7 08-May-24 16-May-24 Room Walls Rebar Installation

VTR-11-WL-SG2-P4.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 16-May-24 19-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-11-WL-SG2-P4.145
Room Walls Formwork Installation 6 19-May-24 26-May-24 Room Walls Formwork Installation

VTR-11-WL-SG2-P4.150
Room Walls Concrete Casting 1 26-May-24 27-May-24 Room Walls Concrete Casting

VTR-11-WL-SG2-P4.155
Room Walls Curing work 1 27-May-24 28-May-24 Room Walls Curing work

VTR-11-WL-SG2-P4.160
Room Walls Formwork Removel 3 28-May-24 01-Jun-24 Room Walls Formwork Removel

VTR-11-WL-SG2-P4.165
Room Walls Scafolding for rebar 6 01-May-24 08-May-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 88 23-May-24 08-Sep-24 08-Sep-24, SLAB ABOVE GROUND LEVEL
Part-1 29 29-Jul-24 01-Sep-24 01-Sep-24, Part-1
VTR-11-SB-ABG-P1.125
Room Top Slab Formwork Installation 8 29-Jul-24 07-Aug-24 Room Top Slab Formwork Installation

VTR-11-SB-ABG-P1.130
Room Top Slab Rebar Installation 5 07-Aug-24 13-Aug-24 Room Top Slab Rebar Installation

VTR-11-SB-ABG-P1.135
Room Top Slab Concrete Casting 1 13-Aug-24 14-Aug-24 Room Top Slab Concrete Casting

VTR-11-SB-ABG-P1.140
Room Top slab Curing work 12 14-Aug-24 28-Aug-24 Room Top slab Curing work

VTR-11-SB-ABG-P1.145
Room Top Slab Formwork Removel 3 28-Aug-24 01-Sep-24 Room Top Slab Formwork Removel

Part-3 85 23-May-24 04-Sep-24 04-Sep-24, Part-3


VTR-11-SB-ABG-P3.125
Room Top Slab Formwork Installation 6 23-May-24 30-May-24 Room Top Slab Formwork Installation

VTR-11-SB-ABG-P3.130
Room Top Slab Rebar Installation 5 30-May-24 05-Jun-24 Room Top Slab Rebar Installation

VTR-11-SB-ABG-P3.135
Room Top Slab Concrete Casting 1 05-Jun-24 06-Jun-24 Room Top Slab Concrete Casting

VTR-11-SB-ABG-P3.140
Room Top slab Curing work 12 06-Jun-24 25-Jun-24 Room Top slab Curing work

VTR-11-SB-ABG-P3.145
Room Top Slab Formwork Removel 3 01-Sep-24 04-Sep-24 Room Top Slab Formwork Removel

Part-4 81 01-Jun-24 08-Sep-24 08-Sep-24, Part-4


VTR-11-SB-ABG-P4.125
Room Top Slab Formwork Installation 7 01-Jun-24 09-Jun-24 Room Top Slab Formwork Installation

VTR-11-SB-ABG-P4.130
Room Top Slab Rebar Installation 4 09-Jun-24 12-Jun-24 Room Top Slab Rebar Installation

VTR-11-SB-ABG-P4.135
Room Top Slab Concrete Casting 1 13-Jun-24 13-Jun-24 Room Top Slab Concrete Casting

VTR-11-SB-ABG-P4.140
Room Top slab Curing work 12 19-Jun-24 02-Jul-24 Room Top slab Curing work

VTR-11-SB-ABG-P4.145
Room Top Slab Formwork Removel 3 04-Sep-24 08-Sep-24 Room Top Slab Formwork Removel

WATER PROOFING 114 04-Sep-24 16-Jan-25 16-Jan-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 22 04-Sep-24 01-Oct-24 01-Oct-24, WALL WATER PROOFING STAGE-1
VTR-11-WP-WL-S1.115
Surface preparation work 6 04-Sep-24 11-Sep-24 Surface preparation work

VTR-11-WP-WL-S1.120
Applying of waterproofing material 11 11-Sep-24 25-Sep-24 Applying of waterproofing material

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
72 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-WP-WL-S1.125
VR Back filling 5 25-Sep-24 01-Oct-24 VR Back filling

WALL WATER PROOFING STAGE-2 22 01-Oct-24 27-Oct-24 27-Oct-24, WALL WATER PROOFING STAGE-2
VTR-11-WP-WL-S2.115
Surface preparation work 6 01-Oct-24 08-Oct-24 Surface preparation work

VTR-11-WP-WL-S2.120
Applying of waterproofing material 11 08-Oct-24 21-Oct-24 Applying of waterproofing material

VTR-11-WP-WL-S2.125
VR Back filling 5 21-Oct-24 27-Oct-24 VR Back filling

WALL WATER PROOFING STAGE-3 22 27-Oct-24 20-Nov-24 20-Nov-24, WALL WATER PROOFING STAGE-3
VTR-11-WP-WL-S3.115
Surface preparation work 6 27-Oct-24 03-Nov-24 Surface preparation work

VTR-11-WP-WL-S3.120
Applying of waterproofing material 11 03-Nov-24 14-Nov-24 Applying of waterproofing material

VTR-11-WP-WL-S3.125
VR Back filling 5 16-Nov-24 20-Nov-24 VR Back filling

WALL WATER PROOFING STAGE-4 22 21-Nov-24 16-Dec-24 16-Dec-24, WALL WATER PROOFING STAGE-4
VTR-11-WP-WL-S4.115
Surface preparation work 6 21-Nov-24 27-Nov-24 Surface preparation work

VTR-11-WP-WL-S4.120
Applying of waterproofing material 11 28-Nov-24 10-Dec-24 Applying of waterproofing material

VTR-11-WP-WL-S4.125
VR Back filling 5 10-Dec-24 16-Dec-24 VR Back filling

TOP SLAB WATER PROOFING 27 16-Dec-24 16-Jan-25 16-Jan-25, TOP SLAB WATER PROOFING
VTR-11-WP-SLB-S1.115
Surface preparation work 12 16-Dec-24 30-Dec-24 Surface preparation work

VTR-11-WP-SLB-S1.120
Applying of waterproofing material 14 30-Dec-24 15-Jan-25 Applying of waterproofing material

VTR-11-WP-SLB-S1.125
Leak Test 1 15-Jan-25 16-Jan-25 Leak Test

MECHANICAL ROOM MEP 81 08-Sep-24 12-Dec-24 12-Dec-24, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 68 08-Sep-24 27-Nov-24 27-Nov-24, ELECTRICAL WORK IN ROOM
POWER SYSTEM 53 08-Sep-24 10-Nov-24 10-Nov-24, POWER SYSTEM
EARTHING SYSTEM 25 08-Sep-24 08-Oct-24 08-Oct-24, EARTHING SYSTEM
VTR-11-EES-105 Earthing system soil resistivity test 6 08-Sep-24 15-Sep-24 Earthing system soil resistivity test

VTR-11-EES-115 Earthing system Copper rod/ earthing pit installation 8 15-Sep-24 25-Sep-24 Earthing system Copper rod/ earthing pit installation

VTR-11-EES-125 Earthing system Termination 6 25-Sep-24 02-Oct-24 Earthing system Termination

VTR-11-EES-135 Earthing system Initial Testing 5 02-Oct-24 08-Oct-24 Earthing system Initial Testing

LIGHTING SYSTEM 37 15-Sep-24 28-Oct-24 28-Oct-24, LIGHTING SYSTEM


VTR-11-ELI.105 Lighting system Conduit and boxes Installation 8 15-Sep-24 25-Sep-24 Lighting system Conduit and boxes Installation

VTR-11-ELI.115 Lighting system Cable Pulling 8 25-Sep-24 05-Oct-24 Lighting system Cable Pulling

VTR-11-ELI.125 Lighting system Installations 8 05-Oct-24 14-Oct-24 Lighting system Installations

VTR-11-ELI.135 Lighting system Termination 8 14-Oct-24 22-Oct-24 Lighting system Termination

VTR-11-ELI.145 Lighting system Initial Testing 5 23-Oct-24 28-Oct-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 15-Sep-24 10-Nov-24 10-Nov-24, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-11-ECT.105 Cable Tray Installation 10 15-Sep-24 28-Sep-24 Cable Tray Installation

VTR-11-ECT.115 Cable Tray Inspection 10 28-Sep-24 09-Oct-24 Cable Tray Inspection

VTR-11-ECT.125 LV Cable pulling 10 09-Oct-24 21-Oct-24 LV Cable pulling

VTR-11-ECT.135 LV Cable Termination 10 21-Oct-24 31-Oct-24 LV Cable Termination

VTR-11-ECT.145 LV Cable Initial Testing 8 02-Nov-24 10-Nov-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 15-Sep-24 30-Oct-24 30-Oct-24, SMALL POWER SYSTEM


VTR-11-ESP.105 Small Power Conduit and boxes Installation 12 15-Sep-24 30-Sep-24 Small Power Conduit and boxes Installation

VTR-11-ESP.115 Small Power Cable Pulling 10 30-Sep-24 12-Oct-24 Small Power Cable Pulling

VTR-11-ESP.125 Small Power Installations 6 12-Oct-24 19-Oct-24 Small Power Installations

VTR-11-ESP.135 Small Power Termination 6 19-Oct-24 24-Oct-24 Small Power Termination

VTR-11-ESP.145 Small Power Initial Testing 5 26-Oct-24 30-Oct-24 Small Power Initial Testing

POWER DISTRIBUTION 39 15-Sep-24 31-Oct-24 31-Oct-24, POWER DISTRIBUTION


GENERATOR 39 15-Sep-24 31-Oct-24 31-Oct-24, GENERATOR
VTR-11-EPD.105 Generator Cable Tray Installation 7 15-Sep-24 24-Sep-24 Generator Cable Tray Installation

VTR-11-EPD.115 Generator Cable Pulling 7 24-Sep-24 02-Oct-24 Generator Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
73 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-EPD.125 Generator Cell Pannel Installation 7 02-Oct-24 10-Oct-24 Generator Cell Pannel Installation

VTR-11-EPD.135 Generator Installation 7 10-Oct-24 17-Oct-24 Generator Installation

VTR-11-EPD.145 Generator Pannel / Cable Termination 7 19-Oct-24 26-Oct-24 Generator Pannel / Cable Termination

VTR-11-EPD.155 Generator Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 Generator Pannel / Cable initial Testing

UPS 28 24-Sep-24 27-Oct-24 27-Oct-24, UPS


VTR-11-EPD.165 UPS Cable Tray Installation 5 24-Sep-24 30-Sep-24 UPS Cable Tray Installation

VTR-11-EPD.175 UPS Cable Pulling 5 30-Sep-24 06-Oct-24 UPS Cable Pulling

VTR-11-EPD.185 UPS Pannel Installation 5 06-Oct-24 10-Oct-24 UPS Pannel Installation

VTR-11-EPD.195 UPS Installation 5 12-Oct-24 16-Oct-24 UPS Installation

VTR-11-EPD.205 UPS Pannel / Cable Termination 5 16-Oct-24 22-Oct-24 UPS Pannel / Cable Termination

VTR-11-EPD.215 UPS Pannel / Cable initial Testing 4 22-Oct-24 27-Oct-24 UPS Pannel / Cable initial Testing

MDB 33 24-Sep-24 31-Oct-24 31-Oct-24, MDB


VTR-11-EPD.225 MDB Cable Tray Installation 7 24-Sep-24 02-Oct-24 MDB Cable Tray Installation

VTR-11-EPD.235 MDB Cable Pulling 7 02-Oct-24 10-Oct-24 MDB Cable Pulling

VTR-11-EPD.245 MDB Pannel Installation 7 10-Oct-24 17-Oct-24 MDB Pannel Installation

VTR-11-EPD.255 MDB Pannel / Cable Termination 7 19-Oct-24 26-Oct-24 MDB Pannel / Cable Termination

VTR-11-EPD.265 MDB Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 MDB Pannel / Cable initial Testing

MCC 33 24-Sep-24 31-Oct-24 31-Oct-24, MCC


VTR-11-EPD.325 MCC Cable Tray Installation 7 24-Sep-24 02-Oct-24 MCC Cable Tray Installation

VTR-11-EPD.335 MCC Cable Pulling 7 02-Oct-24 10-Oct-24 MCC Cable Pulling

VTR-11-EPD.345 MCC Pannel Installation 7 10-Oct-24 17-Oct-24 MCC Pannel Installation

VTR-11-EPD.355 MCC Pannel / Cable Termination 7 19-Oct-24 26-Oct-24 MCC Pannel / Cable Termination

VTR-11-EPD.365 MCC Pannel / Cable initial Testing 5 26-Oct-24 31-Oct-24 MCC Pannel / Cable initial Testing

SMSB 24 24-Sep-24 21-Oct-24 21-Oct-24, SMSB


VTR-11-EPD.275 SMSB Cable Tray Installation 5 24-Sep-24 30-Sep-24 SMSB Cable Tray Installation

VTR-11-EPD.285 SMSB Cable Pulling 5 30-Sep-24 06-Oct-24 SMSB Cable Pulling

VTR-11-EPD.295 SMSB Pannel Installation 5 06-Oct-24 10-Oct-24 SMSB Pannel Installation

VTR-11-EPD.305 SMSB Pannel / Cable Termination 5 12-Oct-24 16-Oct-24 SMSB Pannel / Cable Termination

VTR-11-EPD.315 SMSB Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 SMSB Pannel / Cable initial Testing

DB 24 24-Sep-24 21-Oct-24 21-Oct-24, DB


VTR-11-EPD.375 DB Cable Tray Installation 5 24-Sep-24 30-Sep-24 DB Cable Tray Installation

VTR-11-EPD.385 DB Cable Pulling 5 30-Sep-24 06-Oct-24 DB Cable Pulling

VTR-11-EPD.395 DB Pannel Installation 5 06-Oct-24 10-Oct-24 DB Pannel Installation

VTR-11-EPD.405 DB Pannel / Cable Termination 5 12-Oct-24 16-Oct-24 DB Pannel / Cable Termination

VTR-11-EPD.415 DB Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 DB Pannel / Cable initial Testing

ISOLATOR 24 24-Sep-24 21-Oct-24 21-Oct-24, ISOLATOR


VTR-11-EPD.425 Isolators Cable Tray Installation 5 24-Sep-24 30-Sep-24 Isolators Cable Tray Installation

VTR-11-EPD.435 Isolators Cable Pulling 5 30-Sep-24 06-Oct-24 Isolators Cable Pulling

VTR-11-EPD.445 Isolators Pannel Installation 5 06-Oct-24 10-Oct-24 Isolators Pannel Installation

VTR-11-EPD.455 Isolators Pannel / Cable Termination 5 12-Oct-24 16-Oct-24 Isolators Pannel / Cable Termination

VTR-11-EPD.465 Isolators Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 24-Sep-24 21-Oct-24 21-Oct-24, LCP/ ELCP


VTR-11-EPD.475 LCP/ELCP Cable Tray Installation 5 24-Sep-24 30-Sep-24 LCP/ELCP Cable Tray Installation

VTR-11-EPD.485 LCP/ELCP Cable Pulling 5 30-Sep-24 06-Oct-24 LCP/ELCP Cable Pulling

VTR-11-EPD.495 LCP/ELCP Pannel Installation 5 06-Oct-24 10-Oct-24 LCP/ELCP Pannel Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
74 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-11-EPD.505 LCP/ELCP Pannel / Cable Termination 5 12-Oct-24 16-Oct-24 LCP/ELCP Pannel / Cable Termination

VTR-11-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 16-Oct-24 21-Oct-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 30-Sep-24 27-Nov-24 27-Nov-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 30-Sep-24 17-Nov-24 17-Nov-24, FIRE ALARM SYSTEM
VTR-11-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 30-Sep-24 10-Oct-24 Fire Alarm Conduit /Cable Tray Installation

VTR-11-ELFA.115 Fire Alarm Cable Pulling 9 10-Oct-24 21-Oct-24 Fire Alarm Cable Pulling

VTR-11-ELFA.125 Fire Alarm Devices Installation 9 21-Oct-24 30-Oct-24 Fire Alarm Devices Installation

VTR-11-ELFA.135 Fire Alarm Devices and Cable Termination 9 31-Oct-24 10-Nov-24 Fire Alarm Devices and Cable Termination

VTR-11-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 10-Nov-24 17-Nov-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 10-Oct-24 27-Nov-24 27-Nov-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-11-ELVS.105 ICT System Conduit /Cable Tray Installation 9 10-Oct-24 21-Oct-24 ICT System Conduit /Cable Tray Installation

VTR-11-ELVS.115 ICT System Cable Pulling 9 21-Oct-24 30-Oct-24 ICT System Cable Pulling

VTR-11-ELVS.125 ICT System Devices Installation 9 31-Oct-24 10-Nov-24 ICT System Devices Installation

VTR-11-ELVS.135 ICT System Devices and Cable Termination 9 10-Nov-24 20-Nov-24 ICT System Devices and Cable Termination

VTR-11-ELVS.145 ICT System Devices and Cable initial Testing 6 20-Nov-24 27-Nov-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 10-Oct-24 27-Nov-24 27-Nov-24, ACCESS CONTROL SYSTEM


VTR-11-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 10-Oct-24 21-Oct-24 Access Control System Conduit /Cable Tray Installation

VTR-11-ELAC.115 Access Control System Cable Pulling 9 21-Oct-24 30-Oct-24 Access Control System Cable Pulling

VTR-11-ELAC.125 Access Control System Devices Installation 9 31-Oct-24 10-Nov-24 Access Control System Devices Installation

VTR-11-ELAC.135 Access Control System Devices and Cable Termination 9 10-Nov-24 20-Nov-24 Access Control System Devices and Cable Termination

VTR-11-ELAC.145 Access Control System Devices and Cable initial Testing 6 20-Nov-24 27-Nov-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 10-Oct-24 27-Nov-24 27-Nov-24, PUBLIC ADDRESS SYSTEM


VTR-11-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 10-Oct-24 21-Oct-24 Public Address System Conduit /Cable Tray Installation

VTR-11-ELPA.115 Public Address System Cable Pulling 9 21-Oct-24 30-Oct-24 Public Address System Cable Pulling

VTR-11-ELPA.125 Public Address System Devices Installation 9 31-Oct-24 10-Nov-24 Public Address System Devices Installation

VTR-11-ELPA.135 Public Address System Devices and Cable Termination 9 10-Nov-24 20-Nov-24 Public Address System Devices and Cable Termination

VTR-11-ELPA.145 Public Address System Devices and Cable initial Testing 6 20-Nov-24 27-Nov-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 10-Oct-24 27-Nov-24 27-Nov-24, SCADA SYSTEM


VTR-11-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 10-Oct-24 21-Oct-24 SCADA System Conduit /Cable Tray Installation

VTR-11-ELSC.115 SCADA System Cable Pulling 9 21-Oct-24 30-Oct-24 SCADA System Cable Pulling

VTR-11-ELSC.125 SCADA System Devices Installation 9 31-Oct-24 10-Nov-24 SCADA System Devices Installation

VTR-11-ELSC.135 SCADA System Devices and Cable Termination 9 10-Nov-24 20-Nov-24 SCADA System Devices and Cable Termination

VTR-11-ELSC.145 SCADA System Devices and Cable initial Testing 6 20-Nov-24 27-Nov-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 10-Oct-24 27-Nov-24 27-Nov-24, RADIO RE- BROADCOASTING/ TETRA
VTR-11-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 10-Oct-24 21-Oct-24 Radio/TETRA System Conduit /Cable Tray Installation

VTR-11-ELRD.115 Radio/TETRA System Cable Pulling 9 21-Oct-24 30-Oct-24 Radio/TETRA System Cable Pulling

VTR-11-ELRD.125 Radio/TETRA System Devices Installation 9 31-Oct-24 10-Nov-24 Radio/TETRA System Devices Installation

VTR-11-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 10-Nov-24 20-Nov-24 Radio/TETRA System Devices and Cable Termination

VTR-11-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 20-Nov-24 27-Nov-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 68 24-Sep-24 12-Dec-24 12-Dec-24, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 24-Sep-24 22-Oct-24 22-Oct-24, FIRE FIGHTING
VTR-11-MFF.105 Fire Fighting system Pipe and accessories installation 21 24-Sep-24 19-Oct-24 Fire Fighting system Pipe and accessories installation

VTR-11-MFF.115 Fire Fighting system deluge valve installation 16 30-Sep-24 19-Oct-24 Fire Fighting system deluge valve installation

VTR-11-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 12-Oct-24 19-Oct-24 Fire Fighting system fire hose cabinet/extingusher installation

VTR-11-MFF.140 Fire Fighting system initial testing 3 19-Oct-24 22-Oct-24 Fire Fighting system initial testing

VTR-11-MFF.145 Fire Fighting clean agent system 2 16-Oct-24 19-Oct-24 Fire Fighting clean agent system

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
75 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
HVAC 47 19-Oct-24 12-Dec-24 12-Dec-24, HVAC
VTR-11-MHV.115 Air conditioning system installation 12 20-Nov-24 04-Dec-24 Air conditioning system installation

VTR-11-MHV.120 Fan installation 15 17-Nov-24 04-Dec-24 Fan installation

VTR-11-MHV.125 Duct and accessories installation 28 19-Oct-24 20-Nov-24 Duct and accessories installation

VTR-11-MHV.135 HVAC inital testing 7 04-Dec-24 12-Dec-24 HVAC inital testing

PLUMBING 8 19-Oct-24 28-Oct-24 28-Oct-24, PLUMBING


VTR-11-MPL.105 Plumbing drainage system installation 6 19-Oct-24 26-Oct-24 Plumbing drainage system installation

VTR-11-MPL.115 Plumbing drainage system initial testing 2 26-Oct-24 28-Oct-24 Plumbing drainage system initial testing

DRY UTILITIES 36 24-Sep-24 05-Nov-24 05-Nov-24, DRY UTILITIES


POWER 36 24-Sep-24 05-Nov-24 05-Nov-24, POWER
POWER LV 16 24-Sep-24 13-Oct-24 13-Oct-24, POWER LV
DU-P-LV.510 Installation of support 1 24-Sep-24 25-Sep-24 Installation of support

DU-P-LV.515 Installation of horizontal busbar 2 25-Sep-24 26-Sep-24 Installation of horizontal busbar

DU-P-LV.520 Installation of vertical busbar 2 26-Sep-24 29-Sep-24 Installation of vertical busbar

DU-P-LV.525 Installation of left/right elbow 2 29-Sep-24 30-Sep-24 Installation of left/right elbow

DU-P-LV.530 Installation of right horizintal offset 2 30-Sep-24 02-Oct-24 Installation of right horizintal offset

DU-P-LV.535 Instalaltion of upward vertical offset 3 02-Oct-24 06-Oct-24 Instalaltion of upward vertical offset

DU-P-LV.540 Installation of downward vertical offset 3 06-Oct-24 09-Oct-24 Installation of downward vertical offset

DU-P-LV.545 Installation of transformer and panel connection 2 09-Oct-24 13-Oct-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 25-Sep-24 15-Oct-24 15-Oct-24, MEDIUM VOLTAGE


DU-P-MV.510 Installation of cable try, arm, racks and ladder 6 25-Sep-24 02-Oct-24 Installation of cable try, arm, racks and ladder

DU-P-MV.515 Installation of MV Cable 4 02-Oct-24 07-Oct-24 Installation of MV Cable

DU-P-MV.520 Installation of cable cleats 2 07-Oct-24 09-Oct-24 Installation of cable cleats

DU-P-MV.525 Installation of gland 1 09-Oct-24 09-Oct-24 Installation of gland

DU-P-MV.530 splicing/termination of MV cable 2 09-Oct-24 12-Oct-24 splicing/termination of MV cable

DU-P-MV.535 Testing and Pre-commissioning of cable 2 12-Oct-24 14-Oct-24 Testing and Pre-commissioning of cable

DU-P-MV.540 Energezation 2 14-Oct-24 15-Oct-24 Energezation

TRANSFORMER 16 02-Oct-24 21-Oct-24 21-Oct-24, TRANSFORMER


DU-P-T.510 Installation of Transformer unit 2 02-Oct-24 05-Oct-24 Installation of Transformer unit

DU-P-T.515 Testing and Pre-Commissioning of unit 1 05-Oct-24 05-Oct-24 Testing and Pre-Commissioning of unit

DU-P-T.520 Termination and Splicing of MV Cable 3 05-Oct-24 09-Oct-24 Termination and Splicing of MV Cable

DU-P-T.525 Termination and Splicing of LV Cable/bus way 3 09-Oct-24 13-Oct-24 Termination and Splicing of LV Cable/bus way

DU-P-T.530 Installation and connection of I/O system 2 13-Oct-24 15-Oct-24 Installation and connection of I/O system

DU-P-T.535 Installation of Grounding and Protection System 2 15-Oct-24 19-Oct-24 Installation of Grounding and Protection System

DU-P-T.540 Testing and Commissioning of MV System 1 19-Oct-24 19-Oct-24 Testing and Commissioning of MV System

DU-P-T.545 Testing and Commissioning of LV System 1 19-Oct-24 20-Oct-24 Testing and Commissioning of LV System

DU-P-T.550 Energezation 1 20-Oct-24 21-Oct-24 Energezation

RMU 16 05-Oct-24 23-Oct-24 23-Oct-24, RMU


DU-P-RMU.510 Installation RMU unit 2 05-Oct-24 07-Oct-24 Installation RMU unit

DU-P-RMU.515 Testing and Pre-Commissioning of unit 2 07-Oct-24 09-Oct-24 Testing and Pre-Commissioning of unit

DU-P-RMU.520 Termination and Splicing of Ring-MV Cable 4 09-Oct-24 14-Oct-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.525 Termination and Splicing of T-MV Cable 4 14-Oct-24 19-Oct-24 Termination and Splicing of T-MV Cable

DU-P-RMU.530 Installation of Grounding and Protection System 2 19-Oct-24 21-Oct-24 Installation of Grounding and Protection System

DU-P-RMU.535 Testing and Commissioning of MV System 1 21-Oct-24 22-Oct-24 Testing and Commissioning of MV System

DU-P-RMU.540 Energezation 1 22-Oct-24 23-Oct-24 Energezation

MRMU 18 07-Oct-24 28-Oct-24 28-Oct-24, MRMU

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
76 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-MRMU.510 Installation MRMU unit 2 07-Oct-24 09-Oct-24 Installation MRMU unit

DU-P-MRMU.515 Testing and Pre-Commissioning of unit 3 09-Oct-24 14-Oct-24 Testing and Pre-Commissioning of unit

DU-P-MRMU.520 Termination and Splicing of Ring-MV Cable 3 14-Oct-24 17-Oct-24 Termination and Splicing of Ring-MV Cable

DU-P-MRMU.525 Termination and Splicing of T-MV Cable 3 17-Oct-24 21-Oct-24 Termination and Splicing of T-MV Cable

DU-P-MRMU.530 Installation and connection of I/O system 2 21-Oct-24 23-Oct-24 Installation and connection of I/O system

DU-P-MRMU.535 Testing and Commissioning of MV System 1 23-Oct-24 24-Oct-24 Testing and Commissioning of MV System

DU-P-MRMU.540 Testing and Commissioning of Metered System 1 24-Oct-24 26-Oct-24 Testing and Commissioning of Metered System

DU-P-MRMU.545 Energezation 2 26-Oct-24 28-Oct-24 Energezation

MVSG 22 09-Oct-24 05-Nov-24 05-Nov-24, MVSG


DU-P-MVSG.510 Installation of MVSG module unit 6 09-Oct-24 16-Oct-24 Installation of MVSG module unit

DU-P-MVSG.515 Testing and Pre-Commissioning of each module 3 16-Oct-24 21-Oct-24 Testing and Pre-Commissioning of each module

DU-P-MVSG.520 Termination and Splicing of MV Cable each module 6 21-Oct-24 28-Oct-24 Termination and Splicing of MV Cable each module

DU-P-MVSG.525 Installation of Grounding system and protection 2 28-Oct-24 30-Oct-24 Installation of Grounding system and protection

DU-P-MVSG.530 Installation and connection of I/O system 2 30-Oct-24 02-Nov-24 Installation and connection of I/O system

DU-P-MVSG.535 Testing and Commissioning of MV System 1 02-Nov-24 03-Nov-24 Testing and Commissioning of MV System

DU-P-MVSG.540 Testing and Commissioning of Metered System 1 03-Nov-24 04-Nov-24 Testing and Commissioning of Metered System

DU-P-MVSG.545 Energezation 1 04-Nov-24 05-Nov-24 Energezation

BATTERY ROOM 16 16-Oct-24 04-Nov-24 04-Nov-24, BATTERY ROOM


DU-P-BARM.510 Installation of Battery racks 3 16-Oct-24 21-Oct-24 Installation of Battery racks

DU-P-BARM.515 Installation of batterys 3 21-Oct-24 24-Oct-24 Installation of batterys

DU-P-BARM.520 Installation of DC cable 3 24-Oct-24 28-Oct-24 Installation of DC cable

DU-P-BARM.525 Installation of battery control panel 2 28-Oct-24 30-Oct-24 Installation of battery control panel

DU-P-BARM.530 installation of grounding system 2 30-Oct-24 03-Nov-24 installation of grounding system

DU-P-BARM.535 Testing and Commissioning 2 03-Nov-24 04-Nov-24 Testing and Commissioning

VECHICULAR ROOM 12B (IN ZONE 11) 443 24-May-23 04-Nov-24 04-Nov-24, VECHICULAR ROOM 12B (IN ZONE 11)
ENGINEERING 109 24-May-23 03-Oct-23 03-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 109 24-May-23 03-Oct-23 03-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 72 24-May-23 19-Aug-23 19-Aug-23, EARTH WORKS
T3-ENG-VR12B-SI.942Excavation shop drawings Preparation & Submission 12 24-May-23 06-Jun-23 Excavation shop drawings Preparation & Submission

T3-ENG-VR12B-SI.943Excavation shop drawings Review & Approval 12 07-Jun-23 20-Jun-23 Excavation shop drawings Review & Approval

T3-ENG-VR12B-SI.945Soil Improvement Design Preparation & Submission 14 18-Jul-23 02-Aug-23 Soil Improvement Design Preparation & Submission

T3-ENG-VR12B-SI.950Soil Improvement Design Review & Approval 14 03-Aug-23 19-Aug-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


VR.12-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

VR.12-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

VR.12-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

VR.12-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

VR.12-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

VR.12-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
VR.12-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

VR.12-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
VR.12-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

VR.12-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
77 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM
VR.12-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

VR.12-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 109 24-May-23 03-Oct-23 03-Oct-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
VR.12-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

VR.12-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


VR.12-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

VR.12-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


VR.12-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

VR.12-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


VR.12-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

VR.12-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 26 31-Jul-23 30-Aug-23 30-Aug-23, TRANSFORMERS INSTALLATION


VR.12-ENG-EL-TI.110Transformers Installation Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Transformers Installation Shop Drawings Preparation & Submission

VR.12-ENG-EL-TI.115Transformers Installation Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, LIGHTNING PROTECTION SYSTEM


VR.12-ENG-EL-LP.110Lightning Protection Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Lightning Protection Drawings Preparation & Submission

VR.12-ENG-EL-LP.115Lightning Protection Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, EARTHING SYSTEM


VR.12-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 Earthing System Shop Drawings Preparation & Submission

VR.12-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 18-Sep-23 03-Oct-23 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
VR.12-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

VR.12-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
VR.12-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

VR.12-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
VR.12-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

VR.12-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


VR.12-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

VR.12-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


VR.12-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

VR.12-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


VR.12-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

VR.12-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


VR.12-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

VR.12-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
78 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-LV.700 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.705 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 24-May-23 03-Jul-23 03-Jul-23, MEDIUM VOLTAGE


DU-P-MV.700 Prepare and submit medium voltage shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.705 Review and approval medium voltage shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 24-May-23 03-Jul-23 03-Jul-23, TRANSFORMER


DU-P-T.700 Prepare and submit transformer shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit transformer shopdrawings

DU-P-T.705 Review and approval transformer shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval transformer shopdrawings

RMU 31 24-May-23 03-Jul-23 03-Jul-23, RMU


DU-P-RMU.700 Prepare and submit RMU shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit RMU shopdrawings

DU-P-RMU.705 Review and approval RMU shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval RMU shopdrawings

PROCUREMENT 275 18-Nov-23 13-Oct-24 13-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 18-Nov-23 06-Dec-23 06-Dec-23, CIVIL/STRUCTURAL
VR.12-PRO-CV.110 Issue Purchase Order 6 18-Nov-23 25-Nov-23 Issue Purchase Order

VR.12-PRO-CV.115 Material Delivery 10 25-Nov-23 06-Dec-23 Material Delivery

MECHANICAL 154 07-Apr-24 13-Oct-24 13-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 07-Apr-24 15-Aug-24 15-Aug-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 07-Apr-24 15-Aug-24 15-Aug-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
VR.12-PR-MC-FF.110Issue Purchase Order 15 07-Apr-24 28-Apr-24 Issue Purchase Order

VR.12-PR-MC-FF.115Material Delivery 90 28-Apr-24 15-Aug-24 Material Delivery

VENTILATION SYSTEM 105 06-Jun-24 13-Oct-24 13-Oct-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 06-Jun-24 13-Oct-24 13-Oct-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
VR.12-PR-MC-DS.110Issue Purchase Order 15 06-Jun-24 29-Jun-24 Issue Purchase Order

VR.12-PR-MC-DS.115Material Delivery 90 29-Jun-24 13-Oct-24 Material Delivery

AIR CONDITIONING WORKS 105 06-Jun-24 13-Oct-24 13-Oct-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 06-Jun-24 13-Oct-24 13-Oct-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
VR.12-PR-MC-AC.110Issue Purchase Order 15 06-Jun-24 29-Jun-24 Issue Purchase Order

VR.12-PR-MC-AC.115Material Delivery 90 29-Jun-24 13-Oct-24 Material Delivery

PLUMBING SYSTEM 105 05-May-24 09-Sep-24 09-Sep-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 05-May-24 09-Sep-24 09-Sep-24, PUMPS,PIPES,FITTINGS,VALVES
VR.12-PR-MC-PI.110Issue Purchase Order 15 05-May-24 22-May-24 Issue Purchase Order

VR.12-PR-MC-PI.115Material Delivery 90 22-May-24 09-Sep-24 Material Delivery

ELECTRICAL 141 23-Mar-24 11-Sep-24 11-Sep-24, ELECTRICAL


CABLE TRAY 105 16-Apr-24 21-Aug-24 21-Aug-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 16-Apr-24 21-Aug-24 21-Aug-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
VR.12-PR-EL-CT.110 Issue Purchase Order 15 16-Apr-24 04-May-24 Issue Purchase Order

VR.12-PR-EL-CT.115 Material Delivery 90 04-May-24 21-Aug-24 Material Delivery

POWER CABLES 105 30-Mar-24 07-Aug-24 07-Aug-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 30-Mar-24 07-Aug-24 07-Aug-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
VR.12-PR-EL-PC.110 Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

VR.12-PR-EL-PC.115 Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

LIGHTING SYSTEM 105 30-Mar-24 07-Aug-24 07-Aug-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 30-Mar-24 07-Aug-24 07-Aug-24, CONDUIT,LIGHT
VR.12-PR-EL-LS.110 Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

VR.12-PR-EL-LS.115 Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 30-Mar-24 07-Aug-24 07-Aug-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 30-Mar-24 07-Aug-24 07-Aug-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
VR.12-PR-EL-EI.110 Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

VR.12-PR-EL-EI.115 Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 23-Mar-24 31-Jul-24 31-Jul-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 23-Mar-24 31-Jul-24 31-Jul-24, LIGHTNING PROTECTION SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
79 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VR.12-PR-EL-LP.110 Issue Purchase Order 15 23-Mar-24 13-Apr-24 Issue Purchase Order

VR.12-PR-EL-LP.115 Material Delivery 90 13-Apr-24 31-Jul-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 23-Mar-24 31-Jul-24 31-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 23-Mar-24 31-Jul-24 31-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
VR.12-PR-EL-ES.110 Issue Purchase Order 15 23-Mar-24 13-Apr-24 Issue Purchase Order

VR.12-PR-EL-ES.115 Material Delivery 90 13-Apr-24 31-Jul-24 Material Delivery

LOW CURRENT 123 16-Apr-24 11-Sep-24 11-Sep-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 16-Apr-24 21-Aug-24 21-Aug-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 16-Apr-24 21-Aug-24 21-Aug-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
VR.12-PR-ELL-FA.20Issue Purchase Order 15 16-Apr-24 04-May-24 Issue Purchase Order

VR.12-PR-ELL-FA.25Material Delivery 90 04-May-24 21-Aug-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 27-Apr-24 01-Sep-24 01-Sep-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 27-Apr-24 01-Sep-24 01-Sep-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
VR.12-PR-ELL-PH.20Issue Purchase Order 15 27-Apr-24 14-May-24 Issue Purchase Order

VR.12-PR-ELL-PH.25Material Delivery 90 14-May-24 01-Sep-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 27-Apr-24 01-Sep-24 01-Sep-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 27-Apr-24 01-Sep-24 01-Sep-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
VR.12-PR-ELL-PA.20Issue Purchase Order 15 27-Apr-24 14-May-24 Issue Purchase Order

VR.12-PR-ELL-PA.25Material Delivery 90 14-May-24 01-Sep-24 Material Delivery

VIDEO SURVEILLANCE 105 27-Apr-24 01-Sep-24 01-Sep-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 27-Apr-24 01-Sep-24 01-Sep-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
VR.12-PR-ELL-VS.20Issue Purchase Order 15 27-Apr-24 14-May-24 Issue Purchase Order

VR.12-PR-ELL-VS.25Material Delivery 90 14-May-24 01-Sep-24 Material Delivery

ACCESS CONTROL SYSTEM 105 27-Apr-24 01-Sep-24 01-Sep-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 27-Apr-24 01-Sep-24 01-Sep-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
VR.12-PR-ELL-AC.20
Issue Purchase Order 15 27-Apr-24 14-May-24 Issue Purchase Order

VR.12-PR-ELL-AC.25
Material Delivery 90 14-May-24 01-Sep-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 07-May-24 11-Sep-24 11-Sep-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 07-May-24 11-Sep-24 11-Sep-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
VR.12-PR-ELL-RB.20Issue Purchase Order 15 07-May-24 25-May-24 Issue Purchase Order

VR.12-PR-ELL-RB.25Material Delivery 90 25-May-24 11-Sep-24 Material Delivery

SCADA SYSTEM 105 27-Apr-24 01-Sep-24 01-Sep-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 27-Apr-24 01-Sep-24 01-Sep-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
VR.12-PR-ELL-SD.20Issue Purchase Order 15 27-Apr-24 14-May-24 Issue Purchase Order

VR.12-PR-ELL-SD.25Material Delivery 90 14-May-24 01-Sep-24 Material Delivery

CONSTRUCTION 419 21-Jun-23 04-Nov-24 04-Nov-24, CONSTRUCTION


EXCAVATION WORKS 20 21-Jun-23 17-Jul-23 17-Jul-23, EXCAVATION WORKS
T3-CON-VR12B-EX.210Excavation 20 21-Jun-23 17-Jul-23 Excavation

SOIL IMPROVEMENT WORKS 24 20-Aug-23 16-Sep-23 16-Sep-23, SOIL IMPROVEMENT WORKS


T3-CON-VR12B-SI.230Soil Improvement 24 20-Aug-23 16-Sep-23 Soil Improvement

STRUCTURAL WORKS 255 29-Nov-23 30-Sep-24 30-Sep-24, STRUCTURAL WORKS


FOUNDATION 37 29-Nov-23 11-Jan-24 11-Jan-24, FOUNDATION
Part-1 31 29-Nov-23 03-Jan-24 03-Jan-24, Part-1
VTR-12-FDN-P1.150 Foundation Blinding concrete casting 1 29-Nov-23 29-Nov-23 Foundation Blinding concrete casting

VTR-12-FDN-P1.155 Foundation water proofing on blinding concrete 3 30-Nov-23 03-Dec-23 Foundation water proofing on blinding concrete

VTR-12-FDN-P1.160 Foundation Protection screed on water poofing 1 03-Dec-23 04-Dec-23 Foundation Protection screed on water poofing

VTR-12-FDN-P1.165 Foundation Curing for screed 2 04-Dec-23 06-Dec-23 Foundation Curing for screed

VTR-12-FDN-P1.170 Foundation Rebar installation 10 06-Dec-23 18-Dec-23 Foundation Rebar installation

VTR-12-FDN-P1.175 Foundation Formwork installation 8 18-Dec-23 27-Dec-23 Foundation Formwork installation

VTR-12-FDN-P1.180 Foundation Construction joint work 2 27-Dec-23 30-Dec-23 Foundation Construction joint work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
80 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-12-FDN-P1.185 Foundation concrete casting 1 30-Dec-23 31-Dec-23 Foundation concrete casting

VTR-12-FDN-P1.190 Foundation concrete curing 1 31-Dec-23 01-Jan-24 Foundation concrete curing

VTR-12-FDN-P1.195 Foundation Formwork Removal 2 01-Jan-24 03-Jan-24 Foundation Formwork Removal

Part-2 31 06-Dec-23 11-Jan-24 11-Jan-24, Part-2


VTR-12-FDN-P2.150 Foundation Blinding concrete casting casting 1 06-Dec-23 07-Dec-23 Foundation Blinding concrete casting casting

VTR-12-FDN-P2.155 Foundation water proofing on blinding concrete 3 07-Dec-23 11-Dec-23 Foundation water proofing on blinding concrete

VTR-12-FDN-P2.160 Foundation Protection screed on water poofing 1 11-Dec-23 12-Dec-23 Foundation Protection screed on water poofing

VTR-12-FDN-P2.165 Foundation Curing for screed 2 12-Dec-23 14-Dec-23 Foundation Curing for screed

VTR-12-FDN-P2.170 Foundation Rebar installation 10 14-Dec-23 26-Dec-23 Foundation Rebar installation

VTR-12-FDN-P2.175 Foundation Formwork installation 8 26-Dec-23 04-Jan-24 Foundation Formwork installation

VTR-12-FDN-P2.180 Foundation Construction joint work 2 04-Jan-24 07-Jan-24 Foundation Construction joint work

VTR-12-FDN-P2.185 Foundation concrete casting 1 07-Jan-24 08-Jan-24 Foundation concrete casting

VTR-12-FDN-P2.190 Foundation concrete curing 1 08-Jan-24 09-Jan-24 Foundation concrete curing

VTR-12-FDN-P2.195 Foundation Formwork Removal 2 09-Jan-24 11-Jan-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 43 31-Dec-23 19-Feb-24 19-Feb-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 43 31-Dec-23 19-Feb-24 19-Feb-24, WALL CONCRETE CASTING STAGE-1
Part-1 36 31-Dec-23 11-Feb-24 11-Feb-24, Part-1
VTR-12-WL-S1-P1.135
Room Walls Rebar Installation 12 07-Jan-24 21-Jan-24 Room Walls Rebar Installation

VTR-12-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Jan-24 23-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-12-WL-S1-P1.145
Room Walls Formwork Installation 11 23-Jan-24 05-Feb-24 Room Walls Formwork Installation

VTR-12-WL-S1-P1.150
Room Walls Concrete Casting 1 05-Feb-24 06-Feb-24 Room Walls Concrete Casting

VTR-12-WL-S1-P1.155
Room Walls Curing work 1 06-Feb-24 07-Feb-24 Room Walls Curing work

VTR-12-WL-S1-P1.160
Room Walls Formwork Removel 3 07-Feb-24 11-Feb-24 Room Walls Formwork Removel

VTR-12-WL-S1-P1.165
Room Walls Scafolding for rebar 6 31-Dec-23 07-Jan-24 Room Walls Scafolding for rebar

Part-2 36 09-Jan-24 19-Feb-24 19-Feb-24, Part-2


VTR-12-WL-S1-P2.135
Room Walls Rebar Installation 12 16-Jan-24 29-Jan-24 Room Walls Rebar Installation

VTR-12-WL-S1-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 30-Jan-24 31-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-12-WL-S1-P2.145
Room Walls Formwork Installation 11 31-Jan-24 13-Feb-24 Room Walls Formwork Installation

VTR-12-WL-S1-P2.150
Room Walls Concrete Casting 1 13-Feb-24 14-Feb-24 Room Walls Concrete Casting

VTR-12-WL-S1-P2.155
Room Walls Curing work 1 14-Feb-24 15-Feb-24 Room Walls Curing work

VTR-12-WL-S1-P2.160
Room Walls Formwork Removel 3 15-Feb-24 19-Feb-24 Room Walls Formwork Removel

VTR-12-WL-S1-P2.165
Room Walls Scafolding for rebar 6 09-Jan-24 16-Jan-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 82 11-Feb-24 20-May-24 20-May-24, TOP SLAB BELOW GROUND LEVEL
Part-1 41 11-Feb-24 30-Mar-24 30-Mar-24, Part-1
VTR-12-TS-P1.125 Room Top Slab Formwork Installation 12 11-Feb-24 25-Feb-24 Room Top Slab Formwork Installation

VTR-12-TS-P1.130 Room Top Slab Rebar Installation 12 25-Feb-24 10-Mar-24 Room Top Slab Rebar Installation

VTR-12-TS-P1.135 Room Top Slab Concrete Casting 1 10-Mar-24 11-Mar-24 Room Top Slab Concrete Casting

VTR-12-TS-P1.140 Room Top slab Curing work 12 11-Mar-24 25-Mar-24 Room Top slab Curing work

VTR-12-TS-P1.145 Room Top Slab Formwork Removel 4 25-Mar-24 30-Mar-24 Room Top Slab Formwork Removel

Part-2 41 30-Mar-24 20-May-24 20-May-24, Part-2


VTR-12-TS-P2.125 Room Top Slab Formwork Installation 12 30-Mar-24 16-Apr-24 Room Top Slab Formwork Installation

VTR-12-TS-P2.130 Room Top Slab Rebar Installation 12 16-Apr-24 30-Apr-24 Room Top Slab Rebar Installation

VTR-12-TS-P2.135 Room Top Slab Concrete Casting 1 30-Apr-24 01-May-24 Room Top Slab Concrete Casting

VTR-12-TS-P2.140 Room Top slab Curing work 12 01-May-24 15-May-24 Room Top slab Curing work

VTR-12-TS-P2.145 Room Top Slab Formwork Removel 4 15-May-24 20-May-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 71 30-Mar-24 27-Jun-24 27-Jun-24, WALLS ABOVE SLAB LEVEL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
81 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL CONCRETE CASTING STAGE-1 71 30-Mar-24 27-Jun-24 27-Jun-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 30-Mar-24 06-May-24 06-May-24, Part-1
VTR-12-WL-SG1-P2.135
Room Walls Rebar Installation 10 06-Apr-24 20-Apr-24 Room Walls Rebar Installation

VTR-12-WL-SG1-P2.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Apr-24 22-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-12-WL-SG1-P2.145
Room Walls Formwork Installation 7 23-Apr-24 30-Apr-24 Room Walls Formwork Installation

VTR-12-WL-SG1-P2.150
Room Walls Concrete Casting 1 01-May-24 01-May-24 Room Walls Concrete Casting

VTR-12-WL-SG1-P2.155
Room Walls Curing work 1 02-May-24 02-May-24 Room Walls Curing work

VTR-12-WL-SG1-P2.160
Room Walls Formwork Removel 3 04-May-24 06-May-24 Room Walls Formwork Removel

VTR-12-WL-SG1-P2.165
Room Walls Scafolding for rebar 6 30-Mar-24 06-Apr-24 Room Walls Scafolding for rebar

Part-2 30 20-May-24 27-Jun-24 27-Jun-24, Part-2


VTR-12-WL-SG1-P3.135
Room Walls Rebar Installation 10 27-May-24 06-Jun-24 Room Walls Rebar Installation

VTR-12-WL-SG1-P3.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 06-Jun-24 09-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

VTR-12-WL-SG1-P3.145
Room Walls Formwork Installation 7 09-Jun-24 22-Jun-24 Room Walls Formwork Installation

VTR-12-WL-SG1-P3.150
Room Walls Concrete Casting 1 22-Jun-24 23-Jun-24 Room Walls Concrete Casting

VTR-12-WL-SG1-P3.155
Room Walls Curing work 1 23-Jun-24 24-Jun-24 Room Walls Curing work

VTR-12-WL-SG1-P3.160
Room Walls Formwork Removel 3 24-Jun-24 27-Jun-24 Room Walls Formwork Removel

VTR-12-WL-SG1-P3.165
Room Walls Scafolding for rebar 6 20-May-24 26-May-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 70 07-May-24 31-Jul-24 31-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 29 07-May-24 09-Jun-24 09-Jun-24, Part-1
VTR-12-SB-ABG-P2.125
Room Top Slab Formwork Installation 8 07-May-24 15-May-24 Room Top Slab Formwork Installation

VTR-12-SB-ABG-P2.130
Room Top Slab Rebar Installation 5 15-May-24 21-May-24 Room Top Slab Rebar Installation

VTR-12-SB-ABG-P2.135
Room Top Slab Concrete Casting 1 21-May-24 22-May-24 Room Top Slab Concrete Casting

VTR-12-SB-ABG-P2.140
Room Top slab Curing work 12 22-May-24 05-Jun-24 Room Top slab Curing work

VTR-12-SB-ABG-P2.145
Room Top Slab Formwork Removel 3 05-Jun-24 09-Jun-24 Room Top Slab Formwork Removel

Part-2 29 27-Jun-24 31-Jul-24 31-Jul-24, Part-2


VTR-12-SB-ABG-P3.125
Room Top Slab Formwork Installation 8 27-Jun-24 07-Jul-24 Room Top Slab Formwork Installation

VTR-12-SB-ABG-P3.130
Room Top Slab Rebar Installation 5 07-Jul-24 13-Jul-24 Room Top Slab Rebar Installation

VTR-12-SB-ABG-P3.135
Room Top Slab Concrete Casting 1 13-Jul-24 14-Jul-24 Room Top Slab Concrete Casting

VTR-12-SB-ABG-P3.140
Room Top slab Curing work 12 14-Jul-24 28-Jul-24 Room Top slab Curing work

VTR-12-SB-ABG-P3.145
Room Top Slab Formwork Removel 3 28-Jul-24 31-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 80 27-Jun-24 30-Sep-24 30-Sep-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 20 27-Jun-24 21-Jul-24 21-Jul-24, WALL WATER PROOFING STAGE-1
VTR-12-WP-WL-S1.115
Surface preparation work 6 27-Jun-24 04-Jul-24 Surface preparation work

VTR-12-WP-WL-S1.120
Applying of waterproofing material 9 04-Jul-24 15-Jul-24 Applying of waterproofing material

VTR-12-WP-WL-S1.125
VR Back filling 5 15-Jul-24 21-Jul-24 VR Back filling

WALL WATER PROOFING STAGE-2 20 21-Jul-24 13-Aug-24 13-Aug-24, WALL WATER PROOFING STAGE-2
VTR-12-WP-WL-S2.115
Surface preparation work 6 21-Jul-24 28-Jul-24 Surface preparation work

VTR-12-WP-WL-S2.120
Applying of waterproofing material 9 28-Jul-24 07-Aug-24 Applying of waterproofing material

VTR-12-WP-WL-S2.125
VR Back filling 5 07-Aug-24 13-Aug-24 VR Back filling

WALL WATER PROOFING STAGE-3 20 13-Aug-24 05-Sep-24 05-Sep-24, WALL WATER PROOFING STAGE-3
VTR-12-WP-WL-S3.115
Surface preparation work 6 13-Aug-24 20-Aug-24 Surface preparation work

VTR-12-WP-WL-S3.120
Applying of waterproofing material 9 20-Aug-24 31-Aug-24 Applying of waterproofing material

VTR-12-WP-WL-S3.125
VR Back filling 5 31-Aug-24 05-Sep-24 VR Back filling

WALL WATER PROOFING STAGE-4 20 05-Sep-24 30-Sep-24 30-Sep-24, WALL WATER PROOFING STAGE-4
VTR-12-WP-WL-S4.115
Surface preparation work 6 05-Sep-24 12-Sep-24 Surface preparation work

VTR-12-WP-WL-S4.120
Applying of waterproofing material 9 12-Sep-24 24-Sep-24 Applying of waterproofing material

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
82 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-12-WP-WL-S4.125
VR Back filling 5 24-Sep-24 30-Sep-24 VR Back filling

TOP SLAB WATER PROOFING 25 31-Jul-24 29-Aug-24 29-Aug-24, TOP SLAB WATER PROOFING
VTR-12-WP-SLB-S1.115
Surface preparation work 12 31-Jul-24 14-Aug-24 Surface preparation work

VTR-12-WP-SLB-S1.120
Applying of waterproofing material 12 14-Aug-24 28-Aug-24 Applying of waterproofing material

VTR-12-WP-SLB-S1.125
Leak Test 1 28-Aug-24 29-Aug-24 Leak Test

MECHANICAL ROOM MEP 81 31-Jul-24 04-Nov-24 04-Nov-24, MECHANICAL ROOM MEP


ELECTRICAL WORK IN ROOM 77 31-Jul-24 30-Oct-24 30-Oct-24, ELECTRICAL WORK IN ROOM
POWER SYSTEM 53 31-Jul-24 03-Oct-24 03-Oct-24, POWER SYSTEM
EARTHING SYSTEM 25 31-Jul-24 29-Aug-24 29-Aug-24, EARTHING SYSTEM
VTR-12B-EES-105 Earthing system soil resistivity test 6 31-Jul-24 07-Aug-24 Earthing system soil resistivity test

VTR-12B-EES-115 Earthing system Copper rod/ earthing pit installation 8 07-Aug-24 17-Aug-24 Earthing system Copper rod/ earthing pit installation

VTR-12B-EES-125 Earthing system Termination 6 17-Aug-24 24-Aug-24 Earthing system Termination

VTR-12B-EES-135 Earthing system Initial Testing 5 24-Aug-24 29-Aug-24 Earthing system Initial Testing

LIGHTING SYSTEM 37 07-Aug-24 19-Sep-24 19-Sep-24, LIGHTING SYSTEM


VTR-12B-ELI.105 Lighting system Conduit and boxes Installation 8 07-Aug-24 17-Aug-24 Lighting system Conduit and boxes Installation

VTR-12B-ELI.115 Lighting system Cable Pulling 8 17-Aug-24 26-Aug-24 Lighting system Cable Pulling

VTR-12B-ELI.125 Lighting system Installations 8 26-Aug-24 04-Sep-24 Lighting system Installations

VTR-12B-ELI.135 Lighting system Termination 8 04-Sep-24 14-Sep-24 Lighting system Termination

VTR-12B-ELI.145 Lighting system Initial Testing 5 14-Sep-24 19-Sep-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 07-Aug-24 03-Oct-24 03-Oct-24, CABLE TRAY /CABLE ROUTING SYSTEM
VTR-12B-ECT.105 Cable Tray Installation 10 07-Aug-24 19-Aug-24 Cable Tray Installation

VTR-12B-ECT.115 Cable Tray Inspection 10 19-Aug-24 31-Aug-24 Cable Tray Inspection

VTR-12B-ECT.125 LV Cable pulling 10 31-Aug-24 11-Sep-24 LV Cable pulling

VTR-12B-ECT.135 LV Cable Termination 10 11-Sep-24 24-Sep-24 LV Cable Termination

VTR-12B-ECT.145 LV Cable Initial Testing 8 24-Sep-24 03-Oct-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 07-Aug-24 22-Sep-24 22-Sep-24, SMALL POWER SYSTEM


VTR-12B-ESP.105 Small Power Conduit and boxes Installation 12 07-Aug-24 21-Aug-24 Small Power Conduit and boxes Installation

VTR-12B-ESP.115 Small Power Cable Pulling 10 21-Aug-24 02-Sep-24 Small Power Cable Pulling

VTR-12B-ESP.125 Small Power Installations 6 02-Sep-24 09-Sep-24 Small Power Installations

VTR-12B-ESP.135 Small Power Termination 6 09-Sep-24 16-Sep-24 Small Power Termination

VTR-12B-ESP.145 Small Power Initial Testing 5 16-Sep-24 22-Sep-24 Small Power Initial Testing

POWER DISTRIBUTION 39 07-Aug-24 22-Sep-24 22-Sep-24, POWER DISTRIBUTION


GENERATOR 39 07-Aug-24 22-Sep-24 22-Sep-24, GENERATOR
VTR-12B-EPD.105 Generator Cable Tray Installation 7 07-Aug-24 15-Aug-24 Generator Cable Tray Installation

VTR-12B-EPD.115 Generator Cable Pulling 7 15-Aug-24 24-Aug-24 Generator Cable Pulling

VTR-12B-EPD.125 Generator Cell Pannel Installation 7 24-Aug-24 01-Sep-24 Generator Cell Pannel Installation

VTR-12B-EPD.135 Generator Installation 7 01-Sep-24 09-Sep-24 Generator Installation

VTR-12B-EPD.145 Generator Pannel / Cable Termination 7 09-Sep-24 17-Sep-24 Generator Pannel / Cable Termination

VTR-12B-EPD.155 Generator Pannel / Cable initial Testing 5 17-Sep-24 22-Sep-24 Generator Pannel / Cable initial Testing

UPS 28 15-Aug-24 17-Sep-24 17-Sep-24, UPS


VTR-12B-EPD.165 UPS Cable Tray Installation 5 15-Aug-24 21-Aug-24 UPS Cable Tray Installation

VTR-12B-EPD.175 UPS Cable Pulling 5 21-Aug-24 27-Aug-24 UPS Cable Pulling

VTR-12B-EPD.185 UPS Pannel Installation 5 27-Aug-24 02-Sep-24 UPS Pannel Installation

VTR-12B-EPD.195 UPS Installation 5 02-Sep-24 08-Sep-24 UPS Installation

VTR-12B-EPD.205 UPS Pannel / Cable Termination 5 08-Sep-24 12-Sep-24 UPS Pannel / Cable Termination

VTR-12B-EPD.215 UPS Pannel / Cable initial Testing 4 14-Sep-24 17-Sep-24 UPS Pannel / Cable initial Testing

MDB 33 15-Aug-24 22-Sep-24 22-Sep-24, MDB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
83 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-12B-EPD.225 MDB Cable Tray Installation 7 15-Aug-24 24-Aug-24 MDB Cable Tray Installation

VTR-12B-EPD.235 MDB Cable Pulling 7 24-Aug-24 01-Sep-24 MDB Cable Pulling

VTR-12B-EPD.245 MDB Pannel Installation 7 01-Sep-24 09-Sep-24 MDB Pannel Installation

VTR-12B-EPD.255 MDB Pannel / Cable Termination 7 09-Sep-24 17-Sep-24 MDB Pannel / Cable Termination

VTR-12B-EPD.265 MDB Pannel / Cable initial Testing 5 17-Sep-24 22-Sep-24 MDB Pannel / Cable initial Testing

MCC 33 15-Aug-24 22-Sep-24 22-Sep-24, MCC


VTR-12B-EPD.325 MCC Cable Tray Installation 7 15-Aug-24 24-Aug-24 MCC Cable Tray Installation

VTR-12B-EPD.335 MCC Cable Pulling 7 24-Aug-24 01-Sep-24 MCC Cable Pulling

VTR-12B-EPD.345 MCC Pannel Installation 7 01-Sep-24 09-Sep-24 MCC Pannel Installation

VTR-12B-EPD.355 MCC Pannel / Cable Termination 7 09-Sep-24 17-Sep-24 MCC Pannel / Cable Termination

VTR-12B-EPD.365 MCC Pannel / Cable initial Testing 5 17-Sep-24 22-Sep-24 MCC Pannel / Cable initial Testing

SMSB 24 15-Aug-24 11-Sep-24 11-Sep-24, SMSB


VTR-12B-EPD.275 SMSB Cable Tray Installation 5 15-Aug-24 21-Aug-24 SMSB Cable Tray Installation

VTR-12B-EPD.285 SMSB Cable Pulling 5 21-Aug-24 27-Aug-24 SMSB Cable Pulling

VTR-12B-EPD.295 SMSB Pannel Installation 5 27-Aug-24 02-Sep-24 SMSB Pannel Installation

VTR-12B-EPD.305 SMSB Pannel / Cable Termination 5 02-Sep-24 08-Sep-24 SMSB Pannel / Cable Termination

VTR-12B-EPD.315 SMSB Pannel / Cable initial Testing 4 08-Sep-24 11-Sep-24 SMSB Pannel / Cable initial Testing

DB 24 15-Aug-24 11-Sep-24 11-Sep-24, DB


VTR-12B-EPD.375 DB Cable Tray Installation 5 15-Aug-24 21-Aug-24 DB Cable Tray Installation

VTR-12B-EPD.385 DB Cable Pulling 5 21-Aug-24 27-Aug-24 DB Cable Pulling

VTR-12B-EPD.395 DB Pannel Installation 5 27-Aug-24 02-Sep-24 DB Pannel Installation

VTR-12B-EPD.405 DB Pannel / Cable Termination 5 02-Sep-24 08-Sep-24 DB Pannel / Cable Termination

VTR-12B-EPD.415 DB Pannel / Cable initial Testing 4 08-Sep-24 11-Sep-24 DB Pannel / Cable initial Testing

ISOLATOR 24 15-Aug-24 11-Sep-24 11-Sep-24, ISOLATOR


VTR-12B-EPD.425 Isolators Cable Tray Installation 5 15-Aug-24 21-Aug-24 Isolators Cable Tray Installation

VTR-12B-EPD.435 Isolators Cable Pulling 5 21-Aug-24 27-Aug-24 Isolators Cable Pulling

VTR-12B-EPD.445 Isolators Pannel Installation 5 27-Aug-24 02-Sep-24 Isolators Pannel Installation

VTR-12B-EPD.455 Isolators Pannel / Cable Termination 5 02-Sep-24 08-Sep-24 Isolators Pannel / Cable Termination

VTR-12B-EPD.465 Isolators Pannel / Cable initial Testing 4 08-Sep-24 11-Sep-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 15-Aug-24 11-Sep-24 11-Sep-24, LCP/ ELCP


VTR-12B-EPD.475 LCP/ELCP Cable Tray Installation 5 15-Aug-24 21-Aug-24 LCP/ELCP Cable Tray Installation

VTR-12B-EPD.485 LCP/ELCP Cable Pulling 5 21-Aug-24 27-Aug-24 LCP/ELCP Cable Pulling

VTR-12B-EPD.495 LCP/ELCP Pannel Installation 5 27-Aug-24 02-Sep-24 LCP/ELCP Pannel Installation

VTR-12B-EPD.505 LCP/ELCP Pannel / Cable Termination 5 02-Sep-24 08-Sep-24 LCP/ELCP Pannel / Cable Termination

VTR-12B-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 08-Sep-24 11-Sep-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 59 21-Aug-24 30-Oct-24 30-Oct-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 21-Aug-24 09-Oct-24 09-Oct-24, FIRE ALARM SYSTEM
VTR-12B-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 21-Aug-24 01-Sep-24 Fire Alarm Conduit /Cable Tray Installation

VTR-12B-ELFA.115 Fire Alarm Cable Pulling 9 01-Sep-24 11-Sep-24 Fire Alarm Cable Pulling

VTR-12B-ELFA.125 Fire Alarm Devices Installation 9 11-Sep-24 22-Sep-24 Fire Alarm Devices Installation

VTR-12B-ELFA.135 Fire Alarm Devices and Cable Termination 9 22-Sep-24 03-Oct-24 Fire Alarm Devices and Cable Termination

VTR-12B-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 03-Oct-24 09-Oct-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 01-Sep-24 20-Oct-24 20-Oct-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
VTR-12B-ELVS.105 ICT System Conduit /Cable Tray Installation 9 01-Sep-24 11-Sep-24 ICT System Conduit /Cable Tray Installation

VTR-12B-ELVS.115 ICT System Cable Pulling 9 11-Sep-24 22-Sep-24 ICT System Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
84 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VTR-12B-ELVS.125 ICT System Devices Installation 9 22-Sep-24 03-Oct-24 ICT System Devices Installation

VTR-12B-ELVS.135 ICT System Devices and Cable Termination 9 03-Oct-24 13-Oct-24 ICT System Devices and Cable Termination

VTR-12B-ELVS.145 ICT System Devices and Cable initial Testing 6 14-Oct-24 20-Oct-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 01-Sep-24 20-Oct-24 20-Oct-24, ACCESS CONTROL SYSTEM


VTR-12B-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 01-Sep-24 11-Sep-24 Access Control System Conduit /Cable Tray Installation

VTR-12B-ELAC.115 Access Control System Cable Pulling 9 11-Sep-24 22-Sep-24 Access Control System Cable Pulling

VTR-12B-ELAC.125 Access Control System Devices Installation 9 22-Sep-24 03-Oct-24 Access Control System Devices Installation

VTR-12B-ELAC.135 Access Control System Devices and Cable Termination 9 03-Oct-24 13-Oct-24 Access Control System Devices and Cable Termination

VTR-12B-ELAC.145 Access Control System Devices and Cable initial Testing 6 14-Oct-24 20-Oct-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 01-Sep-24 20-Oct-24 20-Oct-24, PUBLIC ADDRESS SYSTEM


VTR-12B-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 01-Sep-24 11-Sep-24 Public Address System Conduit /Cable Tray Installation

VTR-12B-ELPA.115 Public Address System Cable Pulling 9 11-Sep-24 22-Sep-24 Public Address System Cable Pulling

VTR-12B-ELPA.125 Public Address System Devices Installation 9 22-Sep-24 03-Oct-24 Public Address System Devices Installation

VTR-12B-ELPA.135 Public Address System Devices and Cable Termination 9 03-Oct-24 13-Oct-24 Public Address System Devices and Cable Termination

VTR-12B-ELPA.145 Public Address System Devices and Cable initial Testing 6 14-Oct-24 20-Oct-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 01-Sep-24 20-Oct-24 20-Oct-24, SCADA SYSTEM


VTR-12B-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 01-Sep-24 11-Sep-24 SCADA System Conduit /Cable Tray Installation

VTR-12B-ELSC.115 SCADA System Cable Pulling 9 11-Sep-24 22-Sep-24 SCADA System Cable Pulling

VTR-12B-ELSC.125 SCADA System Devices Installation 9 22-Sep-24 03-Oct-24 SCADA System Devices Installation

VTR-12B-ELSC.135 SCADA System Devices and Cable Termination 9 03-Oct-24 13-Oct-24 SCADA System Devices and Cable Termination

VTR-12B-ELSC.145 SCADA System Devices and Cable initial Testing 6 14-Oct-24 20-Oct-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 11-Sep-24 30-Oct-24 30-Oct-24, RADIO RE- BROADCOASTING/ TETRA
VTR-12B-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 11-Sep-24 22-Sep-24 Radio/TETRA System Conduit /Cable Tray Installation

VTR-12B-ELRD.115 Radio/TETRA System Cable Pulling 9 22-Sep-24 03-Oct-24 Radio/TETRA System Cable Pulling

VTR-12B-ELRD.125 Radio/TETRA System Devices Installation 9 03-Oct-24 13-Oct-24 Radio/TETRA System Devices Installation

VTR-12B-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 14-Oct-24 23-Oct-24 Radio/TETRA System Devices and Cable Termination

VTR-12B-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 23-Oct-24 30-Oct-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN ROOM 68 15-Aug-24 04-Nov-24 04-Nov-24, MECHANICAL WORK IN ROOM


FIRE FIGHTING 24 15-Aug-24 12-Sep-24 12-Sep-24, FIRE FIGHTING
VTR-12B-MFF.105 Fire Fighting system Pipe and accessories installation 21 15-Aug-24 09-Sep-24 Fire Fighting system Pipe and accessories installation

VTR-12B-MFF.115 Fire Fighting system deluge valve installation 16 21-Aug-24 09-Sep-24 Fire Fighting system deluge valve installation

VTR-12B-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 6 02-Sep-24 09-Sep-24 Fire Fighting system fire hose cabinet/extingusher installation

VTR-12B-MFF.140 Fire Fighting system initial testing 3 09-Sep-24 12-Sep-24 Fire Fighting system initial testing

VTR-12B-MFF.145 Fire Fighting clean agent system 2 07-Sep-24 09-Sep-24 Fire Fighting clean agent system

HVAC 47 09-Sep-24 04-Nov-24 04-Nov-24, HVAC


VTR-12B-MHV.115 Air conditioning system installation 12 13-Oct-24 27-Oct-24 Air conditioning system installation

VTR-12B-MHV.120 Fan installation 15 09-Oct-24 27-Oct-24 Fan installation

VTR-12B-MHV.125 Duct and accessories installation 28 09-Sep-24 13-Oct-24 Duct and accessories installation

VTR-12B-MHV.135 HVAC inital testing 7 27-Oct-24 04-Nov-24 HVAC inital testing

PLUMBING 8 09-Sep-24 18-Sep-24 18-Sep-24, PLUMBING


VTR-12B-MPL.105 Plumbing drainage system installation 6 09-Sep-24 16-Sep-24 Plumbing drainage system installation

VTR-12B-MPL.115 Plumbing drainage system initial testing 2 16-Sep-24 18-Sep-24 Plumbing drainage system initial testing

DRY UTILITIES 25 15-Aug-24 14-Sep-24 14-Sep-24, DRY UTILITIES


POWER 25 15-Aug-24 14-Sep-24 14-Sep-24, POWER
POWER LV 16 15-Aug-24 03-Sep-24 03-Sep-24, POWER LV
DU-P-LV.710 Installation of support 1 15-Aug-24 17-Aug-24 Installation of support

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
85 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-LV.715 Installation of horizontal busbar 2 17-Aug-24 18-Aug-24 Installation of horizontal busbar

DU-P-LV.720 Installation of vertical busbar 2 18-Aug-24 20-Aug-24 Installation of vertical busbar

DU-P-LV.725 Installation of left/right elbow 2 20-Aug-24 22-Aug-24 Installation of left/right elbow

DU-P-LV.730 Installation of right horizintal offset 2 22-Aug-24 24-Aug-24 Installation of right horizintal offset

DU-P-LV.735 Instalaltion of upward vertical offset 3 24-Aug-24 27-Aug-24 Instalaltion of upward vertical offset

DU-P-LV.740 Installation of downward vertical offset 3 27-Aug-24 01-Sep-24 Installation of downward vertical offset

DU-P-LV.745 Installation of transformer and panel connection 2 01-Sep-24 03-Sep-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 17-Aug-24 05-Sep-24 05-Sep-24, MEDIUM VOLTAGE


DU-P-MV.710 Installation of cable try, arm, racks and ladder 6 17-Aug-24 24-Aug-24 Installation of cable try, arm, racks and ladder

DU-P-MV.715 Installation of MV Cable 4 24-Aug-24 28-Aug-24 Installation of MV Cable

DU-P-MV.720 Installation of cable cleats 2 28-Aug-24 31-Aug-24 Installation of cable cleats

DU-P-MV.725 Installation of gland 1 31-Aug-24 01-Sep-24 Installation of gland

DU-P-MV.730 splicing/termination of MV cable 2 01-Sep-24 02-Sep-24 splicing/termination of MV cable

DU-P-MV.735 Testing and Pre-commissioning of cable 2 02-Sep-24 04-Sep-24 Testing and Pre-commissioning of cable

DU-P-MV.740 Energezation 2 04-Sep-24 05-Sep-24 Energezation

TRANSFORMER 16 24-Aug-24 11-Sep-24 11-Sep-24, TRANSFORMER


DU-P-T.710 Installation of Transformer unit 2 24-Aug-24 26-Aug-24 Installation of Transformer unit

DU-P-T.715 Testing and Pre-Commissioning of unit 1 26-Aug-24 27-Aug-24 Testing and Pre-Commissioning of unit

DU-P-T.720 Termination and Splicing of MV Cable 3 27-Aug-24 31-Aug-24 Termination and Splicing of MV Cable

DU-P-T.725 Termination and Splicing of LV Cable/bus way 3 31-Aug-24 03-Sep-24 Termination and Splicing of LV Cable/bus way

DU-P-T.730 Installation and connection of I/O system 2 03-Sep-24 05-Sep-24 Installation and connection of I/O system

DU-P-T.735 Installation of Grounding and Protection System 2 05-Sep-24 09-Sep-24 Installation of Grounding and Protection System

DU-P-T.740 Testing and Commissioning of MV System 1 09-Sep-24 10-Sep-24 Testing and Commissioning of MV System

DU-P-T.745 Testing and Commissioning of LV System 1 10-Sep-24 10-Sep-24 Testing and Commissioning of LV System

DU-P-T.750 Energezation 1 10-Sep-24 11-Sep-24 Energezation

RMU 16 26-Aug-24 14-Sep-24 14-Sep-24, RMU


DU-P-RMU.710 Installation RMU unit 2 26-Aug-24 28-Aug-24 Installation RMU unit

DU-P-RMU.715 Testing and Pre-Commissioning of unit 2 28-Aug-24 31-Aug-24 Testing and Pre-Commissioning of unit

DU-P-RMU.720 Termination and Splicing of Ring-MV Cable 4 31-Aug-24 04-Sep-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.725 Termination and Splicing of T-MV Cable 4 04-Sep-24 09-Sep-24 Termination and Splicing of T-MV Cable

DU-P-RMU.730 Installation of Grounding and Protection System 2 09-Sep-24 11-Sep-24 Installation of Grounding and Protection System

DU-P-RMU.735 Testing and Commissioning of MV System 1 11-Sep-24 12-Sep-24 Testing and Commissioning of MV System

DU-P-RMU.740 Energezation 1 12-Sep-24 14-Sep-24 Energezation

UTILITY ROOM 597 24-May-23 08-May-25 08-May-25, UTILITY ROOM


UTILITY ROOM 19 (IN ZONE 01) ON BACKFILL (FLD +15.85 m) 349 24-May-23 17-Jul-24 17-Jul-24, UTILITY ROOM 19 (IN ZONE 01) ON BACKFILL (FLD +15.85 m)
ENGINEERING 211 24-May-23 29-Jan-24 29-Jan-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 211 24-May-23 29-Jan-24 29-Jan-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR19-SI.930Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR19-SI.935Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.19ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.19ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.19ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.19ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.19ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
86 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.19ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 28 24-May-23 25-Jun-23 25-Jun-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.19ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.19ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 24-May-23 25-Jun-23 25-Jun-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.19ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.19ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, PLUMBING SYSTEM


UCR.19ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Plumbing System Shop Drawings Preparation & Submission

UCR.19ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 125 04-Sep-23 29-Jan-24 29-Jan-24, ELECTRICAL


CABLE TRAYS 107 04-Sep-23 08-Jan-24 08-Jan-24, CABLE TRAYS
UCR.19ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 04-Sep-23 20-Sep-23 Cable Tray Shop Drawings Preparation & Submission

UCR.19ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 26-Dec-23 08-Jan-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 111 20-Sep-23 29-Jan-24 29-Jan-24, POWER CABLES


UCR.19ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 20-Sep-23 08-Oct-23 Power Cables Shop Drawings Preparation & Submission

UCR.19ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 15-Jan-24 29-Jan-24 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 81 08-Oct-23 10-Jan-24 10-Jan-24, LIGHTING SYSTEM


UCR.19ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 08-Oct-23 24-Oct-23 Lighting System Shop Drawings Preparation & Submission

UCR.19ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 28-Dec-23 10-Jan-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 75 24-Oct-23 20-Jan-24 20-Jan-24, ELECTRICAL INSTALLATIONS


UCR.19ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 24-Oct-23 09-Nov-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.19ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 06-Jan-24 20-Jan-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 62 09-Nov-23 20-Jan-24 20-Jan-24, TRANSFORMERS INSTALLATION


UCR.19ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 09-Nov-23 26-Nov-23 Transformers Installation Shop Drawings Preparation & Submission

UCR.19ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 06-Jan-24 20-Jan-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 26-Nov-23 10-Jan-24 10-Jan-24, LIGHTNING PROTECTION SYSTEM


UCR.19ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 26-Nov-23 12-Dec-23 Lightning Protection Drawings Preparation & Submission

UCR.19ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 28-Dec-23 10-Jan-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 12-Dec-23 10-Jan-24 10-Jan-24, EARTHING SYSTEM


UCR.19ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 12-Dec-23 27-Dec-23 Earthing System Shop Drawings Preparation & Submission

UCR.19ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 28-Dec-23 10-Jan-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 13-Sep-23 20-Jan-24 20-Jan-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 100 13-Sep-23 09-Jan-24 09-Jan-24, FIRE DETECTION AND ALARM SYSTEM
UCR.19ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 13-Sep-23 01-Oct-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.19ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 27-Dec-23 09-Jan-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 86 01-Oct-23 09-Jan-24 09-Jan-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.19ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 01-Oct-23 17-Oct-23 Telephone Shop Drawings Preparation & Submission

UCR.19ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 27-Dec-23 09-Jan-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 73 17-Oct-23 09-Jan-24 09-Jan-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.19ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 17-Oct-23 02-Nov-23 Public Address system Shop Drawings Preparation & Submission

UCR.19ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 27-Dec-23 09-Jan-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 59 02-Nov-23 09-Jan-24 09-Jan-24, VIDEO SURVEILLANCE


UCR.19ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 02-Nov-23 19-Nov-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.19ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 27-Dec-23 09-Jan-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 45 19-Nov-23 09-Jan-24 09-Jan-24, ACCESS CONTROL SYSTEM


UCR.19ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 19-Nov-23 05-Dec-23 Access Control system Shop Drawings Preparation & Submission

UCR.19ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 27-Dec-23 09-Jan-24 Access Control system Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
87 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RADIO RE-BROADCASTING SYSTEM 40 05-Dec-23 20-Jan-24 20-Jan-24, RADIO RE-BROADCASTING SYSTEM
UCR.19ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 05-Dec-23 20-Dec-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.19ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 06-Jan-24 20-Jan-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 21-Dec-23 20-Jan-24 20-Jan-24, SCADA SYSTEM


UCR.19ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 21-Dec-23 06-Jan-24 SCADA system Shop Drawings Preparation & Submission

UCR.19ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 06-Jan-24 20-Jan-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.655
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.665
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

PROCUREMENT 135 07-Jan-24 19-Jun-24 19-Jun-24, PROCUREMENT


CIVIL/STRUCTURAL 16 07-Jan-24 24-Jan-24 24-Jan-24, CIVIL/STRUCTURAL
UCR.19PRO-CV.110 Issue Purchase Order 6 07-Jan-24 13-Jan-24 Issue Purchase Order

UCR.19PRO-CV.115 Material Delivery 10 14-Jan-24 24-Jan-24 Material Delivery

MECHANICAL 116 28-Jan-24 19-Jun-24 19-Jun-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 28-Jan-24 02-Jun-24 02-Jun-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 28-Jan-24 02-Jun-24 02-Jun-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.19PR-MC-FF.110Issue Purchase Order 15 28-Jan-24 14-Feb-24 Issue Purchase Order

UCR.19PR-MC-FF.115Material Delivery 90 14-Feb-24 02-Jun-24 Material Delivery

VENTILATION SYSTEM 105 10-Feb-24 19-Jun-24 19-Jun-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 10-Feb-24 19-Jun-24 19-Jun-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.19PR-MC-DS.110
Issue Purchase Order 15 10-Feb-24 27-Feb-24 Issue Purchase Order

UCR.19PR-MC-DS.115
Material Delivery 90 27-Feb-24 19-Jun-24 Material Delivery

AIR CONDITIONING WORKS 105 10-Feb-24 19-Jun-24 19-Jun-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 10-Feb-24 19-Jun-24 19-Jun-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.19PR-MC-AC.110
Issue Purchase Order 15 10-Feb-24 27-Feb-24 Issue Purchase Order

UCR.19PR-MC-AC.115
Material Delivery 90 27-Feb-24 19-Jun-24 Material Delivery

PLUMBING SYSTEM 105 10-Feb-24 19-Jun-24 19-Jun-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 10-Feb-24 19-Jun-24 19-Jun-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.19PR-MC-PI.110Issue Purchase Order 15 10-Feb-24 27-Feb-24 Issue Purchase Order

UCR.19PR-MC-PI.115Material Delivery 90 27-Feb-24 19-Jun-24 Material Delivery

ELECTRICAL 123 08-Jan-24 03-Jun-24 03-Jun-24, ELECTRICAL


CABLE TRAY 105 08-Jan-24 13-May-24 13-May-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 08-Jan-24 13-May-24 13-May-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.19PR-EL-CT.110Issue Purchase Order 15 08-Jan-24 25-Jan-24 Issue Purchase Order

UCR.19PR-EL-CT.115Material Delivery 90 25-Jan-24 13-May-24 Material Delivery

POWER CABLES 105 29-Jan-24 03-Jun-24 03-Jun-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 29-Jan-24 03-Jun-24 03-Jun-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.19PR-EL-PC.110Issue Purchase Order 15 29-Jan-24 15-Feb-24 Issue Purchase Order

UCR.19PR-EL-PC.115Material Delivery 90 15-Feb-24 03-Jun-24 Material Delivery

LIGHTING SYSTEM 105 10-Jan-24 15-May-24 15-May-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 10-Jan-24 15-May-24 15-May-24, CONDUIT,LIGHT
UCR.19PR-EL-LS.110Issue Purchase Order 15 10-Jan-24 28-Jan-24 Issue Purchase Order

UCR.19PR-EL-LS.115Material Delivery 90 28-Jan-24 15-May-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 20-Jan-24 25-May-24 25-May-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 20-Jan-24 25-May-24 25-May-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.19PR-EL-EI.110 Issue Purchase Order 15 20-Jan-24 06-Feb-24 Issue Purchase Order

UCR.19PR-EL-EI.115 Material Delivery 90 06-Feb-24 25-May-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 10-Jan-24 15-May-24 15-May-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 10-Jan-24 15-May-24 15-May-24, LIGHTNING PROTECTION SYSTEM
UCR.19PR-EL-LP.110Issue Purchase Order 15 10-Jan-24 28-Jan-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
88 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.19PR-EL-LP.115Material Delivery 90 28-Jan-24 15-May-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 10-Jan-24 15-May-24 15-May-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 10-Jan-24 15-May-24 15-May-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.19PR-EL-ES.110Issue Purchase Order 15 10-Jan-24 28-Jan-24 Issue Purchase Order

UCR.19PR-EL-ES.115Material Delivery 90 28-Jan-24 15-May-24 Material Delivery

LOW CURRENT 114 09-Jan-24 25-May-24 25-May-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 09-Jan-24 14-May-24 14-May-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 09-Jan-24 14-May-24 14-May-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.19PR-ELL-FA.20
Issue Purchase Order 15 09-Jan-24 27-Jan-24 Issue Purchase Order

UCR.19PR-ELL-FA.25
Material Delivery 90 27-Jan-24 14-May-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 09-Jan-24 14-May-24 14-May-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 09-Jan-24 14-May-24 14-May-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.19PR-ELL-PH.20
Issue Purchase Order 15 09-Jan-24 27-Jan-24 Issue Purchase Order

UCR.19PR-ELL-PH.25
Material Delivery 90 27-Jan-24 14-May-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 09-Jan-24 14-May-24 14-May-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 09-Jan-24 14-May-24 14-May-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.19PR-ELL-PA.20
Issue Purchase Order 15 09-Jan-24 27-Jan-24 Issue Purchase Order

UCR.19PR-ELL-PA.25
Material Delivery 90 27-Jan-24 14-May-24 Material Delivery

VIDEO SURVEILLANCE 105 09-Jan-24 14-May-24 14-May-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 09-Jan-24 14-May-24 14-May-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.19PR-ELL-VS.20
Issue Purchase Order 15 09-Jan-24 27-Jan-24 Issue Purchase Order

UCR.19PR-ELL-VS.25
Material Delivery 90 27-Jan-24 14-May-24 Material Delivery

ACCESS CONTROL SYSTEM 105 09-Jan-24 14-May-24 14-May-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 09-Jan-24 14-May-24 14-May-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.19PR-ELL-AC.20
Issue Purchase Order 15 09-Jan-24 27-Jan-24 Issue Purchase Order

UCR.19PR-ELL-AC.25
Material Delivery 90 27-Jan-24 14-May-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 20-Jan-24 25-May-24 25-May-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 20-Jan-24 25-May-24 25-May-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.19PR-ELL-RB.20
Issue Purchase Order 15 20-Jan-24 06-Feb-24 Issue Purchase Order

UCR.19PR-ELL-RB.25
Material Delivery 90 06-Feb-24 25-May-24 Material Delivery

SCADA SYSTEM 105 20-Jan-24 25-May-24 25-May-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 20-Jan-24 25-May-24 25-May-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.19PR-ELL-SD.20
Issue Purchase Order 15 20-Jan-24 06-Feb-24 Issue Purchase Order

UCR.19PR-ELL-SD.25
Material Delivery 90 06-Feb-24 25-May-24 Material Delivery

CONSTRUCTION 152 14-Jan-24 17-Jul-24 17-Jul-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 10 14-Jan-24 24-Jan-24 24-Jan-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR19-SI.240Soil Improvement 10 14-Jan-24 24-Jan-24 Soil Improvement

STRUCTURAL WORKS 101 25-Jan-24 25-May-24 25-May-24, STRUCTURAL WORKS


FOUNDATION 14 25-Jan-24 10-Feb-24 10-Feb-24, FOUNDATION
Part-1 14 25-Jan-24 10-Feb-24 10-Feb-24, Part-1
UCR-19-FDN-P1.150 Foundation Blinding concrete casting 1 25-Jan-24 25-Jan-24 Foundation Blinding concrete casting

UCR-19-FDN-P1.155 Foundation water proofing on blinding concrete 1 27-Jan-24 27-Jan-24 Foundation water proofing on blinding concrete

UCR-19-FDN-P1.160 Foundation Protection screed on water poofing 1 28-Jan-24 28-Jan-24 Foundation Protection screed on water poofing

UCR-19-FDN-P1.170 Foundation Rebar installation 4 28-Jan-24 01-Feb-24 Foundation Rebar installation

UCR-19-FDN-P1.175 Foundation Formwork installation 2 01-Feb-24 04-Feb-24 Foundation Formwork installation

UCR-19-FDN-P1.180 Foundation Construction joint work 2 04-Feb-24 06-Feb-24 Foundation Construction joint work

UCR-19-FDN-P1.185 Foundation concrete casting 1 06-Feb-24 07-Feb-24 Foundation concrete casting

UCR-19-FDN-P1.190 Foundation concrete curing 1 07-Feb-24 08-Feb-24 Foundation concrete curing

UCR-19-FDN-P1.195 Foundation Formwork Removal 1 08-Feb-24 10-Feb-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 19 07-Feb-24 29-Feb-24 29-Feb-24, WALLS UP TO SLAB LEVEL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
89 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL CONCRETE CASTING STAGE-1 19 07-Feb-24 29-Feb-24 29-Feb-24, WALL CONCRETE CASTING STAGE-1
Part-1 19 07-Feb-24 29-Feb-24 29-Feb-24, Part-1
UCR-19-WL-S1-P1.135
Room Walls Rebar Installation 6 11-Feb-24 18-Feb-24 Room Walls Rebar Installation

UCR-19-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 0 18-Feb-24 18-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-19-WL-S1-P1.145
Room Walls Formwork Installation 6 18-Feb-24 25-Feb-24 Room Walls Formwork Installation

UCR-19-WL-S1-P1.150
Room Walls Concrete Casting 1 25-Feb-24 26-Feb-24 Room Walls Concrete Casting

UCR-19-WL-S1-P1.155
Room Walls Curing work 1 26-Feb-24 27-Feb-24 Room Walls Curing work

UCR-19-WL-S1-P1.160
Room Walls Formwork Removel 2 27-Feb-24 29-Feb-24 Room Walls Formwork Removel

UCR-19-WL-S1-P1.165
Room Walls Scafolding for rebar 3 07-Feb-24 11-Feb-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 29 29-Feb-24 03-Apr-24 03-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 29 29-Feb-24 03-Apr-24 03-Apr-24, Part-1
UCR-19-TS-P1.125 Room Top Slab Formwork Installation 8 29-Feb-24 10-Mar-24 Room Top Slab Formwork Installation

UCR-19-TS-P1.130 Room Top Slab Rebar Installation 6 10-Mar-24 17-Mar-24 Room Top Slab Rebar Installation

UCR-19-TS-P1.135 Room Top Slab Concrete Casting 1 17-Mar-24 18-Mar-24 Room Top Slab Concrete Casting

UCR-19-TS-P1.140 Room Top slab Curing work 12 18-Mar-24 01-Apr-24 Room Top slab Curing work

UCR-19-TS-P1.145 Room Top Slab Formwork Removel 2 01-Apr-24 03-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 20 18-Mar-24 14-Apr-24 14-Apr-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 20 18-Mar-24 14-Apr-24 14-Apr-24, WALL CONCRETE CASTING STAGE-1
Part-1 20 18-Mar-24 14-Apr-24 14-Apr-24, Part-1
UCR-19-WL-S1-A.135
Room Walls Rebar Installation 6 21-Mar-24 28-Mar-24 Room Walls Rebar Installation

UCR-19-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 28-Mar-24 31-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-19-WL-S1-A.145
Room Walls Formwork Installation 6 31-Mar-24 07-Apr-24 Room Walls Formwork Installation

UCR-19-WL-S1-A.150
Room Walls Concrete Casting 1 07-Apr-24 08-Apr-24 Room Walls Concrete Casting

UCR-19-WL-S1-A.155
Room Walls Curing work 1 08-Apr-24 13-Apr-24 Room Walls Curing work

UCR-19-WL-S1-A.160
Room Walls Formwork Removel 1 13-Apr-24 14-Apr-24 Room Walls Formwork Removel

UCR-19-WL-S1-A.165
Room Walls Scafolding for rebar 3 18-Mar-24 21-Mar-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 27 14-Apr-24 15-May-24 15-May-24, SLAB ABOVE GROUND LEVEL
Part-1 27 14-Apr-24 15-May-24 15-May-24, Part-1
UCR-19-SLB-A.125 Room Top Slab Formwork Installation 6 14-Apr-24 21-Apr-24 Room Top Slab Formwork Installation

UCR-19-SLB-A.130 Room Top Slab Rebar Installation 6 21-Apr-24 28-Apr-24 Room Top Slab Rebar Installation

UCR-19-SLB-A.135 Room Top Slab Concrete Casting 1 28-Apr-24 29-Apr-24 Room Top Slab Concrete Casting

UCR-19-SLB-A.140 Room Top slab Curing work 12 29-Apr-24 13-May-24 Room Top slab Curing work

UCR-19-SLB-A.145 Room Top Slab Formwork Removel 2 13-May-24 15-May-24 Room Top Slab Formwork Removel

WATER PROOFING 8 15-May-24 25-May-24 25-May-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 8 15-May-24 25-May-24 25-May-24, WALL WATER PROOFING STAGE-1
UCR-19-WP-WL-S1.115
Surface preparation work 3 15-May-24 19-May-24 Surface preparation work

UCR-19-WP-WL-S1.120
Applying of waterproofing material 2 19-May-24 21-May-24 Applying of waterproofing material

UCR-19-WP-WL-S1.125
UR Bck filling 3 21-May-24 25-May-24 UR Bck filling

TOP SLAB WATER PROOFING 5 15-May-24 21-May-24 21-May-24, TOP SLAB WATER PROOFING
UCR-19-WP-SLB-S1.115
Surface preparation work 2 15-May-24 18-May-24 Surface preparation work

UCR-19-WP-SLB-S1.120
Applying of waterproofing material 2 18-May-24 20-May-24 Applying of waterproofing material

UCR-19-WP-SLB-S1.125
Leak Test 1 20-May-24 21-May-24 Leak Test

MECHANICAL ROOM MEP (UCR) 51 13-May-24 17-Jul-24 17-Jul-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 51 13-May-24 17-Jul-24 17-Jul-24, ELECTRICAL WORK IN UCR
POWER SYSTEM 49 13-May-24 15-Jul-24 15-Jul-24, POWER SYSTEM
LIGHTING SYSTEM 37 15-May-24 02-Jul-24 02-Jul-24, LIGHTING SYSTEM
UCR-19-ELI.105 Lighting system Conduit and boxes Installation 8 15-May-24 25-May-24 Lighting system Conduit and boxes Installation

UCR-19-ELI.115 Lighting system Cable Pulling 8 25-May-24 03-Jun-24 Lighting system Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
90 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-19-ELI.125 Lighting system Installations 8 03-Jun-24 12-Jun-24 Lighting system Installations

UCR-19-ELI.135 Lighting system Termination 8 12-Jun-24 26-Jun-24 Lighting system Termination

UCR-19-ELI.145 Lighting system Initial Testing 5 26-Jun-24 02-Jul-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 40 13-May-24 03-Jul-24 03-Jul-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-19-ECT.105 Cable Tray Installation 10 13-May-24 25-May-24 Cable Tray Installation

UCR-19-ECT.115 Cable Tray Inspection 8 25-May-24 03-Jun-24 Cable Tray Inspection

UCR-19-ECT.125 LV Cable pulling 10 03-Jun-24 19-Jun-24 LV Cable pulling

UCR-19-ECT.135 LV Cable Termination 8 19-Jun-24 29-Jun-24 LV Cable Termination

UCR-19-ECT.145 LV Cable Initial Testing 4 29-Jun-24 03-Jul-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 25-May-24 14-Jul-24 14-Jul-24, SMALL POWER SYSTEM


UCR-19-ESP.105 Small Power Conduit and boxes Installation 12 25-May-24 08-Jun-24 Small Power Conduit and boxes Installation

UCR-19-ESP.115 Small Power Cable Pulling 10 08-Jun-24 24-Jun-24 Small Power Cable Pulling

UCR-19-ESP.125 Small Power Installations 6 24-Jun-24 01-Jul-24 Small Power Installations

UCR-19-ESP.135 Small Power Termination 6 01-Jul-24 08-Jul-24 Small Power Termination

UCR-19-ESP.145 Small Power Initial Testing 5 08-Jul-24 14-Jul-24 Small Power Initial Testing

POWER DISTRIBUTION 39 25-May-24 15-Jul-24 15-Jul-24, POWER DISTRIBUTION


GENERATOR 39 25-May-24 15-Jul-24 15-Jul-24, GENERATOR
UCR-19-EPD.105 Generator Cable Tray Installation 7 25-May-24 02-Jun-24 Generator Cable Tray Installation

UCR-19-EPD.115 Generator Cable Pulling 7 02-Jun-24 10-Jun-24 Generator Cable Pulling

UCR-19-EPD.125 Generator Cell Pannel Installation 7 10-Jun-24 23-Jun-24 Generator Cell Pannel Installation

UCR-19-EPD.135 Generator Installation 7 23-Jun-24 01-Jul-24 Generator Installation

UCR-19-EPD.145 Generator Pannel / Cable Termination 7 01-Jul-24 09-Jul-24 Generator Pannel / Cable Termination

UCR-19-EPD.155 Generator Pannel / Cable initial Testing 5 09-Jul-24 15-Jul-24 Generator Pannel / Cable initial Testing

UPS 28 02-Jun-24 10-Jul-24 10-Jul-24, UPS


UCR-19-EPD.165 UPS Cable Tray Installation 5 02-Jun-24 08-Jun-24 UPS Cable Tray Installation

UCR-19-EPD.175 UPS Cable Pulling 5 08-Jun-24 13-Jun-24 UPS Cable Pulling

UCR-19-EPD.185 UPS Pannel Installation 5 13-Jun-24 24-Jun-24 UPS Pannel Installation

UCR-19-EPD.195 UPS Installation 5 24-Jun-24 30-Jun-24 UPS Installation

UCR-19-EPD.205 UPS Pannel / Cable Termination 5 30-Jun-24 06-Jul-24 UPS Pannel / Cable Termination

UCR-19-EPD.215 UPS Pannel / Cable initial Testing 4 06-Jul-24 10-Jul-24 UPS Pannel / Cable initial Testing

MDB 33 25-May-24 07-Jul-24 07-Jul-24, MDB


UCR-19-EPD.225 MDB Cable Tray Installation 7 25-May-24 02-Jun-24 MDB Cable Tray Installation

UCR-19-EPD.235 MDB Cable Pulling 7 02-Jun-24 10-Jun-24 MDB Cable Pulling

UCR-19-EPD.245 MDB Pannel Installation 7 10-Jun-24 23-Jun-24 MDB Pannel Installation

UCR-19-EPD.255 MDB Pannel / Cable Termination 7 23-Jun-24 01-Jul-24 MDB Pannel / Cable Termination

UCR-19-EPD.265 MDB Pannel / Cable initial Testing 5 01-Jul-24 07-Jul-24 MDB Pannel / Cable initial Testing

MCC 33 25-May-24 07-Jul-24 07-Jul-24, MCC


UCR-19-EPD.325 MCC Cable Tray Installation 7 25-May-24 02-Jun-24 MCC Cable Tray Installation

UCR-19-EPD.335 MCC Cable Pulling 7 02-Jun-24 10-Jun-24 MCC Cable Pulling

UCR-19-EPD.345 MCC Pannel Installation 7 10-Jun-24 23-Jun-24 MCC Pannel Installation

UCR-19-EPD.355 MCC Pannel / Cable Termination 7 23-Jun-24 01-Jul-24 MCC Pannel / Cable Termination

UCR-19-EPD.365 MCC Pannel / Cable initial Testing 5 01-Jul-24 07-Jul-24 MCC Pannel / Cable initial Testing

SMSB 24 02-Jun-24 04-Jul-24 04-Jul-24, SMSB


UCR-19-EPD.275 SMSB Cable Tray Installation 5 02-Jun-24 08-Jun-24 SMSB Cable Tray Installation

UCR-19-EPD.285 SMSB Cable Pulling 5 08-Jun-24 13-Jun-24 SMSB Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
91 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-19-EPD.295 SMSB Pannel Installation 5 13-Jun-24 24-Jun-24 SMSB Pannel Installation

UCR-19-EPD.305 SMSB Pannel / Cable Termination 5 24-Jun-24 30-Jun-24 SMSB Pannel / Cable Termination

UCR-19-EPD.315 SMSB Pannel / Cable initial Testing 4 30-Jun-24 04-Jul-24 SMSB Pannel / Cable initial Testing

DB 24 02-Jun-24 04-Jul-24 04-Jul-24, DB


UCR-19-EPD.375 DB Cable Tray Installation 5 02-Jun-24 08-Jun-24 DB Cable Tray Installation

UCR-19-EPD.385 DB Cable Pulling 5 08-Jun-24 13-Jun-24 DB Cable Pulling

UCR-19-EPD.395 DB Pannel Installation 5 13-Jun-24 24-Jun-24 DB Pannel Installation

UCR-19-EPD.405 DB Pannel / Cable Termination 5 24-Jun-24 30-Jun-24 DB Pannel / Cable Termination

UCR-19-EPD.415 DB Pannel / Cable initial Testing 4 30-Jun-24 04-Jul-24 DB Pannel / Cable initial Testing

ISOLATOR 24 02-Jun-24 04-Jul-24 04-Jul-24, ISOLATOR


UCR-19-EPD.425 Isolators Cable Tray Installation 5 02-Jun-24 08-Jun-24 Isolators Cable Tray Installation

UCR-19-EPD.435 Isolators Cable Pulling 5 08-Jun-24 13-Jun-24 Isolators Cable Pulling

UCR-19-EPD.445 Isolators Pannel Installation 5 13-Jun-24 24-Jun-24 Isolators Pannel Installation

UCR-19-EPD.455 Isolators Pannel / Cable Termination 5 24-Jun-24 30-Jun-24 Isolators Pannel / Cable Termination

UCR-19-EPD.465 Isolators Pannel / Cable initial Testing 4 30-Jun-24 04-Jul-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 02-Jun-24 04-Jul-24 04-Jul-24, LCP/ ELCP


UCR-19-EPD.475 LCP/ELCP Cable Tray Installation 5 02-Jun-24 08-Jun-24 LCP/ELCP Cable Tray Installation

UCR-19-EPD.485 LCP/ELCP Cable Pulling 5 08-Jun-24 13-Jun-24 LCP/ELCP Cable Pulling

UCR-19-EPD.495 LCP/ELCP Pannel Installation 5 13-Jun-24 24-Jun-24 LCP/ELCP Pannel Installation

UCR-19-EPD.505 LCP/ELCP Pannel / Cable Termination 5 24-Jun-24 30-Jun-24 LCP/ELCP Pannel / Cable Termination

UCR-19-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 30-Jun-24 04-Jul-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 14-May-24 17-Jul-24 17-Jul-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 14-May-24 07-Jul-24 07-Jul-24, FIRE ALARM SYSTEM
UCR-19-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 14-May-24 25-May-24 Fire Alarm Conduit /Cable Tray Installation

UCR-19-ELFA.115 Fire Alarm Cable Pulling 9 25-May-24 04-Jun-24 Fire Alarm Cable Pulling

UCR-19-ELFA.125 Fire Alarm Devices Installation 9 04-Jun-24 19-Jun-24 Fire Alarm Devices Installation

UCR-19-ELFA.135 Fire Alarm Devices and Cable Termination 9 19-Jun-24 30-Jun-24 Fire Alarm Devices and Cable Termination

UCR-19-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 30-Jun-24 07-Jul-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 14-May-24 07-Jul-24 07-Jul-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-19-ELVS.105 ICT System Conduit /Cable Tray Installation 9 14-May-24 25-May-24 ICT System Conduit /Cable Tray Installation

UCR-19-ELVS.115 ICT System Cable Pulling 9 25-May-24 04-Jun-24 ICT System Cable Pulling

UCR-19-ELVS.125 ICT System Devices Installation 9 04-Jun-24 19-Jun-24 ICT System Devices Installation

UCR-19-ELVS.135 ICT System Devices and Cable Termination 9 19-Jun-24 30-Jun-24 ICT System Devices and Cable Termination

UCR-19-ELVS.145 ICT System Devices and Cable initial Testing 6 30-Jun-24 07-Jul-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 14-May-24 07-Jul-24 07-Jul-24, ACCESS CONTROL SYSTEM


UCR-19-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 14-May-24 25-May-24 Access Control System Conduit /Cable Tray Installation

UCR-19-ELAC.115 Access Control System Cable Pulling 9 25-May-24 04-Jun-24 Access Control System Cable Pulling

UCR-19-ELAC.125 Access Control System Devices Installation 9 04-Jun-24 19-Jun-24 Access Control System Devices Installation

UCR-19-ELAC.135 Access Control System Devices and Cable Termination 9 19-Jun-24 30-Jun-24 Access Control System Devices and Cable Termination

UCR-19-ELAC.145 Access Control System Devices and Cable initial Testing 6 30-Jun-24 07-Jul-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 14-May-24 07-Jul-24 07-Jul-24, PUBLIC ADDRESS SYSTEM


UCR-19-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 14-May-24 25-May-24 Public Address System Conduit /Cable Tray Installation

UCR-19-ELPA.115 Public Address System Cable Pulling 9 25-May-24 04-Jun-24 Public Address System Cable Pulling

UCR-19-ELPA.125 Public Address System Devices Installation 9 04-Jun-24 19-Jun-24 Public Address System Devices Installation

UCR-19-ELPA.135 Public Address System Devices and Cable Termination 9 19-Jun-24 30-Jun-24 Public Address System Devices and Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
92 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-19-ELPA.145 Public Address System Devices and Cable initial Testing 6 30-Jun-24 07-Jul-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 25-May-24 17-Jul-24 17-Jul-24, SCADA SYSTEM


UCR-19-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 25-May-24 04-Jun-24 SCADA System Conduit /Cable Tray Installation

UCR-19-ELSC.115 SCADA System Cable Pulling 9 04-Jun-24 19-Jun-24 SCADA System Cable Pulling

UCR-19-ELSC.125 SCADA System Devices Installation 9 19-Jun-24 30-Jun-24 SCADA System Devices Installation

UCR-19-ELSC.135 SCADA System Devices and Cable Termination 9 30-Jun-24 10-Jul-24 SCADA System Devices and Cable Termination

UCR-19-ELSC.145 SCADA System Devices and Cable initial Testing 6 10-Jul-24 17-Jul-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 25-May-24 17-Jul-24 17-Jul-24, RADIO RE- BROADCOASTING/ TETRA
UCR-19-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 25-May-24 04-Jun-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-19-ELRD.115 Radio/TETRA System Cable Pulling 9 04-Jun-24 19-Jun-24 Radio/TETRA System Cable Pulling

UCR-19-ELRD.125 Radio/TETRA System Devices Installation 9 19-Jun-24 30-Jun-24 Radio/TETRA System Devices Installation

UCR-19-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 30-Jun-24 10-Jul-24 Radio/TETRA System Devices and Cable Termination

UCR-19-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 10-Jul-24 17-Jul-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 26 02-Jun-24 07-Jul-24 07-Jul-24, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 02-Jun-24 22-Jun-24 22-Jun-24, FIRE FIGHTING
UCR-19-MFF.105 Fire Fighting system Pipe and accessories installation 11 02-Jun-24 19-Jun-24 Fire Fighting system Pipe and accessories installation

UCR-19-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 11-Jun-24 19-Jun-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-19-MFF.135 Fire Fighting system initial testing 2 19-Jun-24 22-Jun-24 Fire Fighting system initial testing

HVAC 15 19-Jun-24 07-Jul-24 07-Jul-24, HVAC


UCR-19-MHV.105 Duct and accessories installation 12 19-Jun-24 03-Jul-24 Duct and accessories installation

UCR-19-MHV.115 Fan installation 4 29-Jun-24 03-Jul-24 Fan installation

UCR-19-MHV.135 HVAC inital testing 3 03-Jul-24 07-Jul-24 HVAC inital testing

PLUMBING 4 19-Jun-24 24-Jun-24 24-Jun-24, PLUMBING


UCR-19-MPL.105 Plumbing drainage system installation 3 19-Jun-24 23-Jun-24 Plumbing drainage system installation

UCR-19-MPL.115 Plumbing drainage system initial testing 1 23-Jun-24 24-Jun-24 Plumbing drainage system initial testing

DRY UTILITIES 16 15-May-24 03-Jun-24 03-Jun-24, DRY UTILITIES


POWER 16 15-May-24 03-Jun-24 03-Jun-24, POWER
POWER LV 16 15-May-24 03-Jun-24 03-Jun-24, POWER LV
DU-P-LV.800 Installation of support 1 15-May-24 16-May-24 Installation of support

DU-P-LV.805 Installation of horizontal busbar 2 16-May-24 19-May-24 Installation of horizontal busbar

DU-P-LV.810 Installation of vertical busbar 2 19-May-24 20-May-24 Installation of vertical busbar

DU-P-LV.815 Installation of left/right elbow 2 20-May-24 22-May-24 Installation of left/right elbow

DU-P-LV.820 Installation of right horizintal offset 2 22-May-24 25-May-24 Installation of right horizintal offset

DU-P-LV.825 Instalaltion of upward vertical offset 3 25-May-24 28-May-24 Instalaltion of upward vertical offset

DU-P-LV.830 Installation of downward vertical offset 3 28-May-24 01-Jun-24 Installation of downward vertical offset

DU-P-LV.835 Installation of transformer and panel connection 2 01-Jun-24 03-Jun-24 Installation of transformer and panel connection

UTILITY ROOM 18 (IN ZONE 02) ON BACKFILL (FLD+15m) 482 24-May-23 19-Dec-24 19-Dec-24, UTILITY ROOM 18 (IN ZONE 02) ON BACKFILL (FLD +15 m)
ENGINEERING 335 24-May-23 01-Jul-24 01-Jul-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 335 24-May-23 01-Jul-24 01-Jul-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR18-SI.960Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR18-SI.965Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.18ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.18ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.18ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.18ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
93 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.18ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.18ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.18ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.18ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.18ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.18ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.18ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.18ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 148 02-Jan-24 01-Jul-24 01-Jul-24, ELECTRICAL


CABLE TRAYS 117 02-Jan-24 21-May-24 21-May-24, CABLE TRAYS
UCR.18ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 02-Jan-24 18-Jan-24 Cable Tray Shop Drawings Preparation & Submission

UCR.18ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 07-May-24 21-May-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 103 18-Jan-24 21-May-24 21-May-24, POWER CABLES


UCR.18ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 18-Jan-24 04-Feb-24 Power Cables Shop Drawings Preparation & Submission

UCR.18ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 07-May-24 21-May-24 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 81 04-Feb-24 12-May-24 12-May-24, LIGHTING SYSTEM


UCR.18ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 04-Feb-24 20-Feb-24 Lighting System Shop Drawings Preparation & Submission

UCR.18ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 28-Apr-24 12-May-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 75 20-Feb-24 21-May-24 21-May-24, ELECTRICAL INSTALLATIONS


UCR.18ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 20-Feb-24 07-Mar-24 Electrical Installations Shop Drawings Preparation & Submission

UCR.18ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 07-May-24 21-May-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 62 07-Mar-24 21-May-24 21-May-24, TRANSFORMERS INSTALLATION


UCR.18ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 07-Mar-24 24-Mar-24 Transformers Installation Shop Drawings Preparation & Submission

UCR.18ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 07-May-24 21-May-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 24-Mar-24 12-May-24 12-May-24, LIGHTNING PROTECTION SYSTEM


UCR.18ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 24-Mar-24 08-Apr-24 Lightning Protection Drawings Preparation & Submission

UCR.18ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 28-Apr-24 12-May-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 13-Apr-24 12-May-24 12-May-24, EARTHING SYSTEM


UCR.18ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 13-Apr-24 28-Apr-24 Earthing System Shop Drawings Preparation & Submission

UCR.18ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 28-Apr-24 12-May-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 17-Feb-24 01-Jul-24 01-Jul-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 100 17-Feb-24 20-Jun-24 20-Jun-24, FIRE DETECTION AND ALARM SYSTEM
UCR.18ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 17-Feb-24 04-Mar-24 Fire Alarm Shop Drawings Preparation & Submission

UCR.18ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 02-Jun-24 20-Jun-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 04-Mar-24 01-Jul-24 01-Jul-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.18ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 04-Mar-24 19-Mar-24 Telephone Shop Drawings Preparation & Submission

UCR.18ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 81 20-Mar-24 01-Jul-24 01-Jul-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.18ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 20-Mar-24 04-Apr-24 Public Address system Shop Drawings Preparation & Submission

UCR.18ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 04-Apr-24 01-Jul-24 01-Jul-24, VIDEO SURVEILLANCE


UCR.18ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 04-Apr-24 24-Apr-24 Video Surveillance system Shop Drawings Preparation & Submission

UCR.18ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 54 24-Apr-24 01-Jul-24 01-Jul-24, ACCESS CONTROL SYSTEM


UCR.18ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 24-Apr-24 11-May-24 Access Control system Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
94 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.18ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 11-May-24 01-Jul-24 01-Jul-24, RADIO RE-BROADCASTING SYSTEM


UCR.18ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 11-May-24 27-May-24 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.18ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 27-May-24 01-Jul-24 01-Jul-24, SCADA SYSTEM


UCR.18ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 27-May-24 12-Jun-24 SCADA system Shop Drawings Preparation & Submission

UCR.18ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 12-Jun-24 01-Jul-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.675
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.685
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

PROCUREMENT 194 11-Mar-24 02-Nov-24 02-Nov-24, PROCUREMENT


CIVIL/STRUCTURAL 16 11-Mar-24 28-Mar-24 28-Mar-24, CIVIL/STRUCTURAL
UCR.18PRO-CV.110 Issue Purchase Order 6 11-Mar-24 17-Mar-24 Issue Purchase Order

UCR.18PRO-CV.115 Material Delivery 10 18-Mar-24 28-Mar-24 Material Delivery

MECHANICAL 128 29-May-24 31-Oct-24 31-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 29-May-24 05-Oct-24 05-Oct-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 29-May-24 05-Oct-24 05-Oct-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.18PR-MC-FF.110Issue Purchase Order 15 29-May-24 20-Jun-24 Issue Purchase Order

UCR.18PR-MC-FF.115Material Delivery 90 20-Jun-24 05-Oct-24 Material Delivery

VENTILATION SYSTEM 105 11-Jun-24 17-Oct-24 17-Oct-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 11-Jun-24 17-Oct-24 17-Oct-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.18PR-MC-DS.110
Issue Purchase Order 15 11-Jun-24 03-Jul-24 Issue Purchase Order

UCR.18PR-MC-DS.115
Material Delivery 90 03-Jul-24 17-Oct-24 Material Delivery

AIR CONDITIONING WORKS 105 11-Jun-24 17-Oct-24 17-Oct-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 11-Jun-24 17-Oct-24 17-Oct-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.18PR-MC-AC.110
Issue Purchase Order 15 11-Jun-24 03-Jul-24 Issue Purchase Order

UCR.18PR-MC-AC.115
Material Delivery 90 03-Jul-24 17-Oct-24 Material Delivery

PLUMBING SYSTEM 105 30-Jun-24 31-Oct-24 31-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 30-Jun-24 31-Oct-24 31-Oct-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.18PR-MC-PI.110Issue Purchase Order 15 30-Jun-24 17-Jul-24 Issue Purchase Order

UCR.18PR-MC-PI.115Material Delivery 90 17-Jul-24 31-Oct-24 Material Delivery

ELECTRICAL 144 12-May-24 02-Nov-24 02-Nov-24, ELECTRICAL


CABLE TRAY 105 21-May-24 26-Sep-24 26-Sep-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 21-May-24 26-Sep-24 26-Sep-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.18PR-EL-CT.110Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.18PR-EL-CT.115Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

POWER CABLES 105 21-May-24 26-Sep-24 26-Sep-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 21-May-24 26-Sep-24 26-Sep-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.18PR-EL-PC.110Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.18PR-EL-PC.115Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

LIGHTING SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 12-May-24 16-Sep-24 16-Sep-24, CONDUIT,LIGHT
UCR.18PR-EL-LS.110Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

UCR.18PR-EL-LS.115Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 21-May-24 26-Sep-24 26-Sep-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 21-May-24 26-Sep-24 26-Sep-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.18PR-EL-EI.110 Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.18PR-EL-EI.115 Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, LIGHTNING PROTECTION SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
95 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.18PR-EL-LP.110Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

UCR.18PR-EL-LP.115Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 12-May-24 16-Sep-24 16-Sep-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.18PR-EL-ES.110Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

UCR.18PR-EL-ES.115Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

LOW CURRENT 114 20-Jun-24 02-Nov-24 02-Nov-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 20-Jun-24 22-Oct-24 22-Oct-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 20-Jun-24 22-Oct-24 22-Oct-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.18PR-ELL-FA.20
Issue Purchase Order 15 20-Jun-24 08-Jul-24 Issue Purchase Order

UCR.18PR-ELL-FA.25
Material Delivery 90 08-Jul-24 22-Oct-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 01-Jul-24 02-Nov-24 02-Nov-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 01-Jul-24 02-Nov-24 02-Nov-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.18PR-ELL-PH.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-PH.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 01-Jul-24 02-Nov-24 02-Nov-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 01-Jul-24 02-Nov-24 02-Nov-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.18PR-ELL-PA.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-PA.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

VIDEO SURVEILLANCE 105 01-Jul-24 02-Nov-24 02-Nov-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 01-Jul-24 02-Nov-24 02-Nov-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.18PR-ELL-VS.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-VS.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

ACCESS CONTROL SYSTEM 105 01-Jul-24 02-Nov-24 02-Nov-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 01-Jul-24 02-Nov-24 02-Nov-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.18PR-ELL-AC.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-AC.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 01-Jul-24 02-Nov-24 02-Nov-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 01-Jul-24 02-Nov-24 02-Nov-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.18PR-ELL-RB.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-RB.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

SCADA SYSTEM 105 01-Jul-24 02-Nov-24 02-Nov-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 01-Jul-24 02-Nov-24 02-Nov-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.18PR-ELL-SD.20
Issue Purchase Order 15 01-Jul-24 18-Jul-24 Issue Purchase Order

UCR.18PR-ELL-SD.25
Material Delivery 90 18-Jul-24 02-Nov-24 Material Delivery

CONSTRUCTION 238 09-Mar-24 19-Dec-24 19-Dec-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 09-Mar-24 28-Mar-24 28-Mar-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR18-SI.250Soil Improvement 18 09-Mar-24 28-Mar-24 Soil Improvement

STRUCTURAL WORKS 154 30-Mar-24 03-Oct-24 03-Oct-24, STRUCTURAL WORKS


FOUNDATION 21 30-Mar-24 25-Apr-24 25-Apr-24, FOUNDATION
Part-1 21 30-Mar-24 25-Apr-24 25-Apr-24, Part-1
UCR-18-FDN-P1.150 Foundation Blinding concrete casting 1 30-Mar-24 30-Mar-24 Foundation Blinding concrete casting

UCR-18-FDN-P1.155 Foundation water proofing on blinding concrete 2 31-Mar-24 01-Apr-24 Foundation water proofing on blinding concrete

UCR-18-FDN-P1.160 Foundation Protection screed on water poofing 1 01-Apr-24 02-Apr-24 Foundation Protection screed on water poofing

UCR-18-FDN-P1.170 Foundation Rebar installation 8 02-Apr-24 15-Apr-24 Foundation Rebar installation

UCR-18-FDN-P1.175 Foundation Formwork installation 4 15-Apr-24 20-Apr-24 Foundation Formwork installation

UCR-18-FDN-P1.180 Foundation Construction joint work 2 20-Apr-24 22-Apr-24 Foundation Construction joint work

UCR-18-FDN-P1.185 Foundation concrete casting 1 22-Apr-24 23-Apr-24 Foundation concrete casting

UCR-18-FDN-P1.190 Foundation concrete curing 1 23-Apr-24 24-Apr-24 Foundation concrete curing

UCR-18-FDN-P1.195 Foundation Formwork Removal 1 24-Apr-24 25-Apr-24 Foundation Formwork Removal

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
96 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALLS UP TO SLAB LEVEL 32 25-Apr-24 02-Jun-24 02-Jun-24, WALLS UP TO SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 32 25-Apr-24 02-Jun-24 02-Jun-24, WALL CONCRETE CASTING STAGE-1
Part-1 32 25-Apr-24 02-Jun-24 02-Jun-24, Part-1
UCR-18-WL-S1-P1.135
Room Walls Rebar Installation 10 01-May-24 13-May-24 Room Walls Rebar Installation

UCR-18-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 13-May-24 15-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-18-WL-S1-P1.145
Room Walls Formwork Installation 11 15-May-24 28-May-24 Room Walls Formwork Installation

UCR-18-WL-S1-P1.150
Room Walls Concrete Casting 1 28-May-24 29-May-24 Room Walls Concrete Casting

UCR-18-WL-S1-P1.155
Room Walls Curing work 1 29-May-24 30-May-24 Room Walls Curing work

UCR-18-WL-S1-P1.160
Room Walls Formwork Removel 2 30-May-24 02-Jun-24 Room Walls Formwork Removel

UCR-18-WL-S1-P1.165
Room Walls Scafolding for rebar 5 25-Apr-24 01-May-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 37 02-Jun-24 20-Jul-24 20-Jul-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 02-Jun-24 20-Jul-24 20-Jul-24, Part-1
UCR-18-TS-P1.125 Room Top Slab Formwork Installation 10 02-Jun-24 13-Jun-24 Room Top Slab Formwork Installation

UCR-18-TS-P1.130 Room Top Slab Rebar Installation 10 13-Jun-24 30-Jun-24 Room Top Slab Rebar Installation

UCR-18-TS-P1.135 Room Top Slab Concrete Casting 1 30-Jun-24 01-Jul-24 Room Top Slab Concrete Casting

UCR-18-TS-P1.140 Room Top slab Curing work 12 01-Jul-24 15-Jul-24 Room Top slab Curing work

UCR-18-TS-P1.145 Room Top Slab Formwork Removel 4 15-Jul-24 20-Jul-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 30 01-Jul-24 05-Aug-24 05-Aug-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 30 01-Jul-24 05-Aug-24 05-Aug-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 01-Jul-24 05-Aug-24 05-Aug-24, Part-1
UCR-18--S1-A.135 Room Walls Rebar Installation 9 07-Jul-24 17-Jul-24 Room Walls Rebar Installation

UCR-18--S1-A.140 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 17-Jul-24 20-Jul-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-18--S1-A.145 Room Walls Formwork Installation 10 20-Jul-24 31-Jul-24 Room Walls Formwork Installation

UCR-18--S1-A.150 Room Walls Concrete Casting 1 31-Jul-24 01-Aug-24 Room Walls Concrete Casting

UCR-18--S1-A.155 Room Walls Curing work 1 01-Aug-24 03-Aug-24 Room Walls Curing work

UCR-18--S1-A.160 Room Walls Formwork Removel 2 03-Aug-24 05-Aug-24 Room Walls Formwork Removel

UCR-18--S1-A.165 Room Walls Scafolding for rebar 5 01-Jul-24 07-Jul-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 36 05-Aug-24 16-Sep-24 16-Sep-24, SLAB ABOVE GROUND LEVEL
Part-1 36 05-Aug-24 16-Sep-24 16-Sep-24, Part-1
UCR-18-SLB-A.125 Room Top Slab Formwork Installation 10 05-Aug-24 17-Aug-24 Room Top Slab Formwork Installation

UCR-18-SLB-A.130 Room Top Slab Rebar Installation 9 17-Aug-24 27-Aug-24 Room Top Slab Rebar Installation

UCR-18-SLB-A.135 Room Top Slab Concrete Casting 1 27-Aug-24 28-Aug-24 Room Top Slab Concrete Casting

UCR-18-SLB-A.140 Room Top slab Curing work 12 28-Aug-24 11-Sep-24 Room Top slab Curing work

UCR-18-SLB-A.145 Room Top Slab Formwork Removel 4 11-Sep-24 16-Sep-24 Room Top Slab Formwork Removel

WATER PROOFING 14 16-Sep-24 03-Oct-24 03-Oct-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 14 16-Sep-24 03-Oct-24 03-Oct-24, WALL WATER PROOFING STAGE-1
UCR-18-WL-S1.115 Surface preparation work 6 16-Sep-24 24-Sep-24 Surface preparation work

UCR-18-WL-S1.120 Applying of waterproofing material 5 24-Sep-24 30-Sep-24 Applying of waterproofing material

UCR-18-WL-S1.125 UR Bck filling 3 30-Sep-24 03-Oct-24 UR Bck filling

TOP SLAB WATER PROOFING 11 16-Sep-24 30-Sep-24 30-Sep-24, TOP SLAB WATER PROOFING
UCR-18-SLB-S1.115 Surface preparation work 4 16-Sep-24 21-Sep-24 Surface preparation work

UCR-18-SLB-S1.120 Applying of waterproofing material 6 21-Sep-24 29-Sep-24 Applying of waterproofing material

UCR-18-SLB-S1.125 Leak Test 1 29-Sep-24 30-Sep-24 Leak Test

MECHANICAL ROOM MEP (UCR) 80 16-Sep-24 19-Dec-24 19-Dec-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 80 16-Sep-24 19-Dec-24 19-Dec-24, ELECTRICAL WORK IN UCR
POWER SYSTEM 56 16-Sep-24 23-Nov-24 23-Nov-24, POWER SYSTEM
LIGHTING SYSTEM 37 16-Sep-24 30-Oct-24 30-Oct-24, LIGHTING SYSTEM
UCR-18-ELI.105 Lighting system Conduit and boxes Installation 8 16-Sep-24 26-Sep-24 Lighting system Conduit and boxes Installation

UCR-18-ELI.115 Lighting system Cable Pulling 8 26-Sep-24 06-Oct-24 Lighting system Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
97 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-18-ELI.125 Lighting system Installations 8 06-Oct-24 15-Oct-24 Lighting system Installations

UCR-18-ELI.135 Lighting system Termination 8 15-Oct-24 24-Oct-24 Lighting system Termination

UCR-18-ELI.145 Lighting system Initial Testing 5 24-Oct-24 30-Oct-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 26-Sep-24 21-Nov-24 21-Nov-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-18-ECT.105 Cable Tray Installation 10 26-Sep-24 08-Oct-24 Cable Tray Installation

UCR-18-ECT.115 Cable Tray Inspection 10 08-Oct-24 20-Oct-24 Cable Tray Inspection

UCR-18-ECT.125 LV Cable pulling 10 20-Oct-24 31-Oct-24 LV Cable pulling

UCR-18-ECT.135 LV Cable Termination 10 31-Oct-24 12-Nov-24 LV Cable Termination

UCR-18-ECT.145 LV Cable Initial Testing 8 12-Nov-24 21-Nov-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 08-Oct-24 23-Nov-24 23-Nov-24, SMALL POWER SYSTEM


UCR-18-ESP.105 Small Power Conduit and boxes Installation 12 08-Oct-24 22-Oct-24 Small Power Conduit and boxes Installation

UCR-18-ESP.115 Small Power Cable Pulling 10 22-Oct-24 03-Nov-24 Small Power Cable Pulling

UCR-18-ESP.125 Small Power Installations 6 03-Nov-24 10-Nov-24 Small Power Installations

UCR-18-ESP.135 Small Power Termination 6 10-Nov-24 17-Nov-24 Small Power Termination

UCR-18-ESP.145 Small Power Initial Testing 5 17-Nov-24 23-Nov-24 Small Power Initial Testing

POWER DISTRIBUTION 39 26-Sep-24 12-Nov-24 12-Nov-24, POWER DISTRIBUTION


GENERATOR 39 26-Sep-24 12-Nov-24 12-Nov-24, GENERATOR
UCR-18-EPD.105 Generator Cable Tray Installation 7 26-Sep-24 05-Oct-24 Generator Cable Tray Installation

UCR-18-EPD.115 Generator Cable Pulling 7 05-Oct-24 13-Oct-24 Generator Cable Pulling

UCR-18-EPD.125 Generator Cell Pannel Installation 7 13-Oct-24 21-Oct-24 Generator Cell Pannel Installation

UCR-18-EPD.135 Generator Installation 7 21-Oct-24 29-Oct-24 Generator Installation

UCR-18-EPD.145 Generator Pannel / Cable Termination 7 29-Oct-24 06-Nov-24 Generator Pannel / Cable Termination

UCR-18-EPD.155 Generator Pannel / Cable initial Testing 5 06-Nov-24 12-Nov-24 Generator Pannel / Cable initial Testing

UPS 28 05-Oct-24 06-Nov-24 06-Nov-24, UPS


UCR-18-EPD.165 UPS Cable Tray Installation 5 05-Oct-24 10-Oct-24 UPS Cable Tray Installation

UCR-18-EPD.175 UPS Cable Pulling 5 10-Oct-24 16-Oct-24 UPS Cable Pulling

UCR-18-EPD.185 UPS Pannel Installation 5 16-Oct-24 22-Oct-24 UPS Pannel Installation

UCR-18-EPD.195 UPS Installation 5 22-Oct-24 28-Oct-24 UPS Installation

UCR-18-EPD.205 UPS Pannel / Cable Termination 5 28-Oct-24 03-Nov-24 UPS Pannel / Cable Termination

UCR-18-EPD.215 UPS Pannel / Cable initial Testing 4 03-Nov-24 06-Nov-24 UPS Pannel / Cable initial Testing

MDB 33 05-Oct-24 12-Nov-24 12-Nov-24, MDB


UCR-18-EPD.225 MDB Cable Tray Installation 7 05-Oct-24 13-Oct-24 MDB Cable Tray Installation

UCR-18-EPD.235 MDB Cable Pulling 7 13-Oct-24 21-Oct-24 MDB Cable Pulling

UCR-18-EPD.245 MDB Pannel Installation 7 21-Oct-24 29-Oct-24 MDB Pannel Installation

UCR-18-EPD.255 MDB Pannel / Cable Termination 7 29-Oct-24 06-Nov-24 MDB Pannel / Cable Termination

UCR-18-EPD.265 MDB Pannel / Cable initial Testing 5 06-Nov-24 12-Nov-24 MDB Pannel / Cable initial Testing

MCC 33 05-Oct-24 12-Nov-24 12-Nov-24, MCC


UCR-18-EPD.325 MCC Cable Tray Installation 7 05-Oct-24 13-Oct-24 MCC Cable Tray Installation

UCR-18-EPD.335 MCC Cable Pulling 7 13-Oct-24 21-Oct-24 MCC Cable Pulling

UCR-18-EPD.345 MCC Pannel Installation 7 21-Oct-24 29-Oct-24 MCC Pannel Installation

UCR-18-EPD.355 MCC Pannel / Cable Termination 7 29-Oct-24 06-Nov-24 MCC Pannel / Cable Termination

UCR-18-EPD.365 MCC Pannel / Cable initial Testing 5 06-Nov-24 12-Nov-24 MCC Pannel / Cable initial Testing

SMSB 24 05-Oct-24 02-Nov-24 02-Nov-24, SMSB


UCR-18-EPD.275 SMSB Cable Tray Installation 5 05-Oct-24 10-Oct-24 SMSB Cable Tray Installation

UCR-18-EPD.285 SMSB Cable Pulling 5 10-Oct-24 16-Oct-24 SMSB Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
98 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-18-EPD.295 SMSB Pannel Installation 5 16-Oct-24 22-Oct-24 SMSB Pannel Installation

UCR-18-EPD.305 SMSB Pannel / Cable Termination 5 22-Oct-24 28-Oct-24 SMSB Pannel / Cable Termination

UCR-18-EPD.315 SMSB Pannel / Cable initial Testing 4 28-Oct-24 02-Nov-24 SMSB Pannel / Cable initial Testing

DB 24 05-Oct-24 02-Nov-24 02-Nov-24, DB


UCR-18-EPD.375 DB Cable Tray Installation 5 05-Oct-24 10-Oct-24 DB Cable Tray Installation

UCR-18-EPD.385 DB Cable Pulling 5 10-Oct-24 16-Oct-24 DB Cable Pulling

UCR-18-EPD.395 DB Pannel Installation 5 16-Oct-24 22-Oct-24 DB Pannel Installation

UCR-18-EPD.405 DB Pannel / Cable Termination 5 22-Oct-24 28-Oct-24 DB Pannel / Cable Termination

UCR-18-EPD.415 DB Pannel / Cable initial Testing 4 28-Oct-24 02-Nov-24 DB Pannel / Cable initial Testing

ISOLATOR 24 05-Oct-24 02-Nov-24 02-Nov-24, ISOLATOR


UCR-18-EPD.425 Isolators Cable Tray Installation 5 05-Oct-24 10-Oct-24 Isolators Cable Tray Installation

UCR-18-EPD.435 Isolators Cable Pulling 5 10-Oct-24 16-Oct-24 Isolators Cable Pulling

UCR-18-EPD.445 Isolators Pannel Installation 5 16-Oct-24 22-Oct-24 Isolators Pannel Installation

UCR-18-EPD.455 Isolators Pannel / Cable Termination 5 22-Oct-24 28-Oct-24 Isolators Pannel / Cable Termination

UCR-18-EPD.465 Isolators Pannel / Cable initial Testing 4 28-Oct-24 02-Nov-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 05-Oct-24 02-Nov-24 02-Nov-24, LCP/ ELCP


UCR-18-EPD.475 LCP/ELCP Cable Tray Installation 5 05-Oct-24 10-Oct-24 LCP/ELCP Cable Tray Installation

UCR-18-EPD.485 LCP/ELCP Cable Pulling 5 10-Oct-24 16-Oct-24 LCP/ELCP Cable Pulling

UCR-18-EPD.495 LCP/ELCP Pannel Installation 5 16-Oct-24 22-Oct-24 LCP/ELCP Pannel Installation

UCR-18-EPD.505 LCP/ELCP Pannel / Cable Termination 5 22-Oct-24 28-Oct-24 LCP/ELCP Pannel / Cable Termination

UCR-18-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 28-Oct-24 02-Nov-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 22-Oct-24 19-Dec-24 19-Dec-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 22-Oct-24 09-Dec-24 09-Dec-24, FIRE ALARM SYSTEM
UCR-18-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 22-Oct-24 02-Nov-24 Fire Alarm Conduit /Cable Tray Installation

UCR-18-ELFA.115 Fire Alarm Cable Pulling 9 02-Nov-24 12-Nov-24 Fire Alarm Cable Pulling

UCR-18-ELFA.125 Fire Alarm Devices Installation 9 12-Nov-24 23-Nov-24 Fire Alarm Devices Installation

UCR-18-ELFA.135 Fire Alarm Devices and Cable Termination 9 23-Nov-24 03-Dec-24 Fire Alarm Devices and Cable Termination

UCR-18-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 03-Dec-24 09-Dec-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 02-Nov-24 19-Dec-24 19-Dec-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-18-ELVS.105 ICT System Conduit /Cable Tray Installation 9 02-Nov-24 12-Nov-24 ICT System Conduit /Cable Tray Installation

UCR-18-ELVS.115 ICT System Cable Pulling 9 12-Nov-24 23-Nov-24 ICT System Cable Pulling

UCR-18-ELVS.125 ICT System Devices Installation 9 23-Nov-24 03-Dec-24 ICT System Devices Installation

UCR-18-ELVS.135 ICT System Devices and Cable Termination 9 03-Dec-24 12-Dec-24 ICT System Devices and Cable Termination

UCR-18-ELVS.145 ICT System Devices and Cable initial Testing 6 14-Dec-24 19-Dec-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 02-Nov-24 19-Dec-24 19-Dec-24, ACCESS CONTROL SYSTEM


UCR-18-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 02-Nov-24 12-Nov-24 Access Control System Conduit /Cable Tray Installation

UCR-18-ELAC.115 Access Control System Cable Pulling 9 12-Nov-24 23-Nov-24 Access Control System Cable Pulling

UCR-18-ELAC.125 Access Control System Devices Installation 9 23-Nov-24 03-Dec-24 Access Control System Devices Installation

UCR-18-ELAC.135 Access Control System Devices and Cable Termination 9 03-Dec-24 12-Dec-24 Access Control System Devices and Cable Termination

UCR-18-ELAC.145 Access Control System Devices and Cable initial Testing 6 14-Dec-24 19-Dec-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 02-Nov-24 19-Dec-24 19-Dec-24, PUBLIC ADDRESS SYSTEM


UCR-18-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 02-Nov-24 12-Nov-24 Public Address System Conduit /Cable Tray Installation

UCR-18-ELPA.115 Public Address System Cable Pulling 9 12-Nov-24 23-Nov-24 Public Address System Cable Pulling

UCR-18-ELPA.125 Public Address System Devices Installation 9 23-Nov-24 03-Dec-24 Public Address System Devices Installation

UCR-18-ELPA.135 Public Address System Devices and Cable Termination 9 03-Dec-24 12-Dec-24 Public Address System Devices and Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
99 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-18-ELPA.145 Public Address System Devices and Cable initial Testing 6 14-Dec-24 19-Dec-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 02-Nov-24 19-Dec-24 19-Dec-24, SCADA SYSTEM


UCR-18-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 02-Nov-24 12-Nov-24 SCADA System Conduit /Cable Tray Installation

UCR-18-ELSC.115 SCADA System Cable Pulling 9 12-Nov-24 23-Nov-24 SCADA System Cable Pulling

UCR-18-ELSC.125 SCADA System Devices Installation 9 23-Nov-24 03-Dec-24 SCADA System Devices Installation

UCR-18-ELSC.135 SCADA System Devices and Cable Termination 9 03-Dec-24 12-Dec-24 SCADA System Devices and Cable Termination

UCR-18-ELSC.145 SCADA System Devices and Cable initial Testing 6 14-Dec-24 19-Dec-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 02-Nov-24 19-Dec-24 19-Dec-24, RADIO RE- BROADCOASTING/ TETRA
UCR-18-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 02-Nov-24 12-Nov-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-18-ELRD.115 Radio/TETRA System Cable Pulling 9 12-Nov-24 23-Nov-24 Radio/TETRA System Cable Pulling

UCR-18-ELRD.125 Radio/TETRA System Devices Installation 9 23-Nov-24 03-Dec-24 Radio/TETRA System Devices Installation

UCR-18-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 03-Dec-24 12-Dec-24 Radio/TETRA System Devices and Cable Termination

UCR-18-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 14-Dec-24 19-Dec-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 27 05-Oct-24 05-Nov-24 05-Nov-24, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 05-Oct-24 20-Oct-24 20-Oct-24, FIRE FIGHTING
UCR-18-MFF.105 Fire Fighting system Pipe and accessories installation 11 05-Oct-24 17-Oct-24 Fire Fighting system Pipe and accessories installation

UCR-18-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 14-Oct-24 17-Oct-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-18-MFF.135 Fire Fighting system initial testing 2 17-Oct-24 20-Oct-24 Fire Fighting system initial testing

HVAC 15 17-Oct-24 04-Nov-24 04-Nov-24, HVAC


UCR-18-MHV.105 Duct and accessories installation 12 17-Oct-24 31-Oct-24 Duct and accessories installation

UCR-18-MHV.115 Fan installation 4 27-Oct-24 31-Oct-24 Fan installation

UCR-18-MHV.135 HVAC inital testing 3 31-Oct-24 04-Nov-24 HVAC inital testing

PLUMBING 4 31-Oct-24 05-Nov-24 05-Nov-24, PLUMBING


UCR-18-MPL.105 Plumbing drainage system installation 3 31-Oct-24 04-Nov-24 Plumbing drainage system installation

UCR-18-MPL.115 Plumbing drainage system initial testing 1 04-Nov-24 05-Nov-24 Plumbing drainage system initial testing

DRY UTILITIES 16 05-Oct-24 23-Oct-24 23-Oct-24, DRY UTILITIES


POWER 16 05-Oct-24 23-Oct-24 23-Oct-24, POWER
POWER LV 16 05-Oct-24 23-Oct-24 23-Oct-24, POWER LV
DU-P-LV.650 Installation of support 1 05-Oct-24 06-Oct-24 Installation of support

DU-P-LV.655 Installation of horizontal busbar 2 06-Oct-24 07-Oct-24 Installation of horizontal busbar

DU-P-LV.660 Installation of vertical busbar 2 08-Oct-24 09-Oct-24 Installation of vertical busbar

DU-P-LV.665 Installation of left/right elbow 2 09-Oct-24 12-Oct-24 Installation of left/right elbow

DU-P-LV.670 Installation of right horizintal offset 2 12-Oct-24 13-Oct-24 Installation of right horizintal offset

DU-P-LV.675 Instalaltion of upward vertical offset 3 13-Oct-24 16-Oct-24 Instalaltion of upward vertical offset

DU-P-LV.680 Installation of downward vertical offset 3 17-Oct-24 21-Oct-24 Installation of downward vertical offset

DU-P-LV.685 Installation of transformer and panel connection 2 21-Oct-24 23-Oct-24 Installation of transformer and panel connection

UTILITY ROOM 15 (IN ZONE 03) ON BACKFILL (FLD +14.55 m) 480 24-May-23 17-Dec-24 17-Dec-24, UTILITY ROOM 15 (IN ZONE 03) ON BACKFILL (FLD +14.55 m)
ENGINEERING 333 24-May-23 29-Jun-24 29-Jun-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 333 24-May-23 29-Jun-24 29-Jun-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR15-SI.1010
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR15-SI.1015
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.15ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.15ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.15ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.15ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
100 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.15ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.15ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.15ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.15ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.15ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.15ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.15ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.15ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 124 28-Jan-24 29-Jun-24 29-Jun-24, ELECTRICAL


CABLE TRAYS 117 28-Jan-24 20-Jun-24 20-Jun-24, CABLE TRAYS
UCR.15ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 28-Jan-24 13-Feb-24 Cable Tray Shop Drawings Preparation & Submission

UCR.15ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 02-Jun-24 20-Jun-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 103 13-Feb-24 20-Jun-24 20-Jun-24, POWER CABLES


UCR.15ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 13-Feb-24 29-Feb-24 Power Cables Shop Drawings Preparation & Submission

UCR.15ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 02-Jun-24 20-Jun-24 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 81 29-Feb-24 06-Jun-24 06-Jun-24, LIGHTING SYSTEM


UCR.15ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 29-Feb-24 17-Mar-24 Lighting System Shop Drawings Preparation & Submission

UCR.15ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 23-May-24 06-Jun-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 75 17-Mar-24 20-Jun-24 20-Jun-24, ELECTRICAL INSTALLATIONS


UCR.15ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 17-Mar-24 01-Apr-24 Electrical Installations Shop Drawings Preparation & Submission

UCR.15ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 02-Jun-24 20-Jun-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 62 02-Apr-24 20-Jun-24 20-Jun-24, TRANSFORMERS INSTALLATION


UCR.15ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 02-Apr-24 21-Apr-24 Transformers Installation Shop Drawings Preparation & Submission

UCR.15ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 02-Jun-24 20-Jun-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 21-Apr-24 06-Jun-24 06-Jun-24, LIGHTNING PROTECTION SYSTEM


UCR.15ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 21-Apr-24 07-May-24 Lightning Protection Drawings Preparation & Submission

UCR.15ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 23-May-24 06-Jun-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 07-May-24 06-Jun-24 06-Jun-24, EARTHING SYSTEM


UCR.15ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 07-May-24 23-May-24 Earthing System Shop Drawings Preparation & Submission

UCR.15ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 23-May-24 06-Jun-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 14-Feb-24 29-Jun-24 29-Jun-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 109 14-Feb-24 29-Jun-24 29-Jun-24, FIRE DETECTION AND ALARM SYSTEM
UCR.15ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 14-Feb-24 02-Mar-24 Fire Alarm Shop Drawings Preparation & Submission

UCR.15ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 02-Mar-24 29-Jun-24 29-Jun-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.15ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 02-Mar-24 17-Mar-24 Telephone Shop Drawings Preparation & Submission

UCR.15ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 81 18-Mar-24 29-Jun-24 29-Jun-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.15ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 18-Mar-24 02-Apr-24 Public Address system Shop Drawings Preparation & Submission

UCR.15ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 02-Apr-24 29-Jun-24 29-Jun-24, VIDEO SURVEILLANCE


UCR.15ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 02-Apr-24 22-Apr-24 Video Surveillance system Shop Drawings Preparation & Submission

UCR.15ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 54 22-Apr-24 29-Jun-24 29-Jun-24, ACCESS CONTROL SYSTEM


UCR.15ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 22-Apr-24 08-May-24 Access Control system Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
101 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.15ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 08-May-24 29-Jun-24 29-Jun-24, RADIO RE-BROADCASTING SYSTEM


UCR.15ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 08-May-24 25-May-24 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.15ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 25-May-24 29-Jun-24 29-Jun-24, SCADA SYSTEM


UCR.15ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 25-May-24 10-Jun-24 SCADA system Shop Drawings Preparation & Submission

UCR.15ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 10-Jun-24 29-Jun-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.775
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.785
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

PROCUREMENT 170 06-Apr-24 30-Oct-24 30-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 06-Apr-24 27-Apr-24 27-Apr-24, CIVIL/STRUCTURAL
UCR.15PRO-CV.110 Issue Purchase Order 6 06-Apr-24 15-Apr-24 Issue Purchase Order

UCR.15PRO-CV.115 Material Delivery 10 16-Apr-24 27-Apr-24 Material Delivery

MECHANICAL 105 29-Jun-24 30-Oct-24 30-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 29-Jun-24 30-Oct-24 30-Oct-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.15PR-MC-FF.110Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-MC-FF.115Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

VENTILATION SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 29-Jun-24 30-Oct-24 30-Oct-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.15PR-MC-DS.110
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-MC-DS.115
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

AIR CONDITIONING WORKS 105 29-Jun-24 30-Oct-24 30-Oct-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 29-Jun-24 30-Oct-24 30-Oct-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.15PR-MC-AC.110
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-MC-AC.115
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

PLUMBING SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 29-Jun-24 30-Oct-24 30-Oct-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.15PR-MC-PI.110Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-MC-PI.115Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

ELECTRICAL 120 06-Jun-24 30-Oct-24 30-Oct-24, ELECTRICAL


CABLE TRAY 105 20-Jun-24 22-Oct-24 22-Oct-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 20-Jun-24 22-Oct-24 22-Oct-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.15PR-EL-CT.110Issue Purchase Order 15 20-Jun-24 08-Jul-24 Issue Purchase Order

UCR.15PR-EL-CT.115Material Delivery 90 08-Jul-24 22-Oct-24 Material Delivery

POWER CABLES 105 20-Jun-24 22-Oct-24 22-Oct-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 20-Jun-24 22-Oct-24 22-Oct-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.15PR-EL-PC.110Issue Purchase Order 15 20-Jun-24 08-Jul-24 Issue Purchase Order

UCR.15PR-EL-PC.115Material Delivery 90 08-Jul-24 22-Oct-24 Material Delivery

LIGHTING SYSTEM 105 06-Jun-24 13-Oct-24 13-Oct-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 06-Jun-24 13-Oct-24 13-Oct-24, CONDUIT,LIGHT
UCR.15PR-EL-LS.110Issue Purchase Order 15 06-Jun-24 29-Jun-24 Issue Purchase Order

UCR.15PR-EL-LS.115Material Delivery 90 29-Jun-24 13-Oct-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 20-Jun-24 22-Oct-24 22-Oct-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 20-Jun-24 22-Oct-24 22-Oct-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.15PR-EL-EI.110 Issue Purchase Order 15 20-Jun-24 08-Jul-24 Issue Purchase Order

UCR.15PR-EL-EI.115 Material Delivery 90 08-Jul-24 22-Oct-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 06-Jun-24 13-Oct-24 13-Oct-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 06-Jun-24 13-Oct-24 13-Oct-24, LIGHTNING PROTECTION SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
102 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.15PR-EL-LP.110Issue Purchase Order 15 06-Jun-24 29-Jun-24 Issue Purchase Order

UCR.15PR-EL-LP.115Material Delivery 90 29-Jun-24 13-Oct-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 06-Jun-24 13-Oct-24 13-Oct-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 06-Jun-24 13-Oct-24 13-Oct-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.15PR-EL-ES.110Issue Purchase Order 15 06-Jun-24 29-Jun-24 Issue Purchase Order

UCR.15PR-EL-ES.115Material Delivery 90 29-Jun-24 13-Oct-24 Material Delivery

LOW CURRENT 105 29-Jun-24 30-Oct-24 30-Oct-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 29-Jun-24 30-Oct-24 30-Oct-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.15PR-ELL-FA.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-FA.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 29-Jun-24 30-Oct-24 30-Oct-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 29-Jun-24 30-Oct-24 30-Oct-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.15PR-ELL-PH.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-PH.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 29-Jun-24 30-Oct-24 30-Oct-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.15PR-ELL-PA.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-PA.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

VIDEO SURVEILLANCE 105 29-Jun-24 30-Oct-24 30-Oct-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 29-Jun-24 30-Oct-24 30-Oct-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.15PR-ELL-VS.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-VS.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

ACCESS CONTROL SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 29-Jun-24 30-Oct-24 30-Oct-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.15PR-ELL-AC.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-AC.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 29-Jun-24 30-Oct-24 30-Oct-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.15PR-ELL-RB.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-RB.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

SCADA SYSTEM 105 29-Jun-24 30-Oct-24 30-Oct-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 29-Jun-24 30-Oct-24 30-Oct-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.15PR-ELL-SD.20
Issue Purchase Order 15 29-Jun-24 16-Jul-24 Issue Purchase Order

UCR.15PR-ELL-SD.25
Material Delivery 90 16-Jul-24 30-Oct-24 Material Delivery

CONSTRUCTION 214 03-Apr-24 17-Dec-24 17-Dec-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 03-Apr-24 27-Apr-24 27-Apr-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR15-SI.275Soil Improvement 18 03-Apr-24 27-Apr-24 Soil Improvement

STRUCTURAL WORKS 162 28-Apr-24 07-Nov-24 07-Nov-24, STRUCTURAL WORKS


FOUNDATION 22 28-Apr-24 22-May-24 22-May-24, FOUNDATION
Part-1 22 28-Apr-24 22-May-24 22-May-24, Part-1
UCR-15-FDN-P1.150 Foundation Blinding concrete casting 1 28-Apr-24 28-Apr-24 Foundation Blinding concrete casting

UCR-15-FDN-P1.155 Foundation water proofing on blinding concrete 2 29-Apr-24 30-Apr-24 Foundation water proofing on blinding concrete

UCR-15-FDN-P1.160 Foundation Protection screed on water poofing 1 30-Apr-24 01-May-24 Foundation Protection screed on water poofing

UCR-15-FDN-P1.170 Foundation Rebar installation 9 01-May-24 12-May-24 Foundation Rebar installation

UCR-15-FDN-P1.175 Foundation Formwork installation 4 12-May-24 16-May-24 Foundation Formwork installation

UCR-15-FDN-P1.180 Foundation Construction joint work 2 16-May-24 19-May-24 Foundation Construction joint work

UCR-15-FDN-P1.185 Foundation concrete casting 1 19-May-24 20-May-24 Foundation concrete casting

UCR-15-FDN-P1.190 Foundation concrete curing 1 20-May-24 21-May-24 Foundation concrete curing

UCR-15-FDN-P1.195 Foundation Formwork Removal 1 21-May-24 22-May-24 Foundation Formwork Removal

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
103 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALLS UP TO SLAB LEVEL 30 22-May-24 01-Jul-24 01-Jul-24, WALLS UP TO SLAB LEVEL
WALL CONCRETE CASTING STAGE-1 30 22-May-24 01-Jul-24 01-Jul-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 22-May-24 01-Jul-24 01-Jul-24, Part-1
UCR-15-WL-S1-P1.135
Room Walls Rebar Installation 10 27-May-24 08-Jun-24 Room Walls Rebar Installation

UCR-15-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 08-Jun-24 10-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-15-WL-S1-P1.145
Room Walls Formwork Installation 9 10-Jun-24 25-Jun-24 Room Walls Formwork Installation

UCR-15-WL-S1-P1.150
Room Walls Concrete Casting 1 25-Jun-24 26-Jun-24 Room Walls Concrete Casting

UCR-15-WL-S1-P1.155
Room Walls Curing work 1 26-Jun-24 27-Jun-24 Room Walls Curing work

UCR-15-WL-S1-P1.160
Room Walls Formwork Removel 3 27-Jun-24 01-Jul-24 Room Walls Formwork Removel

UCR-15-WL-S1-P1.165
Room Walls Scafolding for rebar 4 22-May-24 27-May-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 36 01-Jul-24 12-Aug-24 12-Aug-24, TOP SLAB BELOW GROUND LEVEL
Part-1 36 01-Jul-24 12-Aug-24 12-Aug-24, Part-1
UCR-15-TS-P1.125 Room Top Slab Formwork Installation 10 01-Jul-24 13-Jul-24 Room Top Slab Formwork Installation

UCR-15-TS-P1.130 Room Top Slab Rebar Installation 9 13-Jul-24 23-Jul-24 Room Top Slab Rebar Installation

UCR-15-TS-P1.135 Room Top Slab Concrete Casting 1 23-Jul-24 24-Jul-24 Room Top Slab Concrete Casting

UCR-15-TS-P1.140 Room Top slab Curing work 12 24-Jul-24 07-Aug-24 Room Top slab Curing work

UCR-15-TS-P1.145 Room Top Slab Formwork Removel 4 07-Aug-24 12-Aug-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 32 24-Jul-24 31-Aug-24 31-Aug-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 32 24-Jul-24 31-Aug-24 31-Aug-24, WALL CONCRETE CASTING STAGE-1
Part-1 32 24-Jul-24 31-Aug-24 31-Aug-24, Part-1
UCR-15-WL-S1-A.135
Room Walls Rebar Installation 10 31-Jul-24 12-Aug-24 Room Walls Rebar Installation

UCR-15-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 12-Aug-24 14-Aug-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-15-WL-S1-A.145
Room Walls Formwork Installation 9 14-Aug-24 25-Aug-24 Room Walls Formwork Installation

UCR-15-WL-S1-A.150
Room Walls Concrete Casting 1 25-Aug-24 26-Aug-24 Room Walls Concrete Casting

UCR-15-WL-S1-A.155
Room Walls Curing work 1 26-Aug-24 27-Aug-24 Room Walls Curing work

UCR-15-WL-S1-A.160
Room Walls Formwork Removel 3 27-Aug-24 31-Aug-24 Room Walls Formwork Removel

UCR-15-WL-S1-A.165
Room Walls Scafolding for rebar 6 24-Jul-24 31-Jul-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 36 31-Aug-24 13-Oct-24 13-Oct-24, SLAB ABOVE GROUND LEVEL
Part-1 36 31-Aug-24 13-Oct-24 13-Oct-24, Part-1
UCR-15-SLB-A.125 Room Top Slab Formwork Installation 10 31-Aug-24 11-Sep-24 Room Top Slab Formwork Installation

UCR-15-SLB-A.130 Room Top Slab Rebar Installation 9 11-Sep-24 22-Sep-24 Room Top Slab Rebar Installation

UCR-15-SLB-A.135 Room Top Slab Concrete Casting 1 22-Sep-24 24-Sep-24 Room Top Slab Concrete Casting

UCR-15-SLB-A.140 Room Top slab Curing work 12 24-Sep-24 08-Oct-24 Room Top slab Curing work

UCR-15-SLB-A.145 Room Top Slab Formwork Removel 4 08-Oct-24 13-Oct-24 Room Top Slab Formwork Removel

WATER PROOFING 28 06-Oct-24 07-Nov-24 07-Nov-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 16 06-Oct-24 24-Oct-24 24-Oct-24, WALL WATER PROOFING STAGE-1
UCR-15-WP-WL-S1.115
Surface preparation work 6 06-Oct-24 13-Oct-24 Surface preparation work

UCR-15-WP-WL-S1.120
Applying of waterproofing material 6 13-Oct-24 20-Oct-24 Applying of waterproofing material

UCR-15-WP-WL-S1.125
UR Bck filling 4 20-Oct-24 24-Oct-24 UR Bck filling

TOP SLAB WATER PROOFING 22 13-Oct-24 07-Nov-24 07-Nov-24, TOP SLAB WATER PROOFING
UCR-15-WP-SLB-S1.115
Surface preparation work 12 13-Oct-24 27-Oct-24 Surface preparation work

UCR-15-WP-SLB-S1.120
Applying of waterproofing material 9 27-Oct-24 06-Nov-24 Applying of waterproofing material

UCR-15-WP-SLB-S1.125
Leak Test 1 06-Nov-24 07-Nov-24 Leak Test

MECHANICAL ROOM MEP (UCR) 56 13-Oct-24 17-Dec-24 17-Dec-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 56 13-Oct-24 17-Dec-24 17-Dec-24, ELECTRICAL WORK IN UCR
POWER SYSTEM 55 13-Oct-24 16-Dec-24 16-Dec-24, POWER SYSTEM
LIGHTING SYSTEM 37 13-Oct-24 25-Nov-24 25-Nov-24, LIGHTING SYSTEM
UCR-15-ELI.105 Lighting system Conduit and boxes Installation 8 13-Oct-24 22-Oct-24 Lighting system Conduit and boxes Installation

UCR-15-ELI.115 Lighting system Cable Pulling 8 22-Oct-24 31-Oct-24 Lighting system Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
104 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-15-ELI.125 Lighting system Installations 8 31-Oct-24 10-Nov-24 Lighting system Installations

UCR-15-ELI.135 Lighting system Termination 8 10-Nov-24 19-Nov-24 Lighting system Termination

UCR-15-ELI.145 Lighting system Initial Testing 5 19-Nov-24 25-Nov-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 22-Oct-24 16-Dec-24 16-Dec-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-15-ECT.105 Cable Tray Installation 10 22-Oct-24 03-Nov-24 Cable Tray Installation

UCR-15-ECT.115 Cable Tray Inspection 10 03-Nov-24 14-Nov-24 Cable Tray Inspection

UCR-15-ECT.125 LV Cable pulling 10 14-Nov-24 26-Nov-24 LV Cable pulling

UCR-15-ECT.135 LV Cable Termination 10 26-Nov-24 08-Dec-24 LV Cable Termination

UCR-15-ECT.145 LV Cable Initial Testing 8 08-Dec-24 16-Dec-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 22-Oct-24 05-Dec-24 05-Dec-24, SMALL POWER SYSTEM


UCR-15-ESP.105 Small Power Conduit and boxes Installation 12 22-Oct-24 05-Nov-24 Small Power Conduit and boxes Installation

UCR-15-ESP.115 Small Power Cable Pulling 10 05-Nov-24 17-Nov-24 Small Power Cable Pulling

UCR-15-ESP.125 Small Power Installations 6 17-Nov-24 24-Nov-24 Small Power Installations

UCR-15-ESP.135 Small Power Termination 6 24-Nov-24 01-Dec-24 Small Power Termination

UCR-15-ESP.145 Small Power Initial Testing 5 01-Dec-24 05-Dec-24 Small Power Initial Testing

POWER DISTRIBUTION 39 22-Oct-24 07-Dec-24 07-Dec-24, POWER DISTRIBUTION


GENERATOR 39 22-Oct-24 07-Dec-24 07-Dec-24, GENERATOR
UCR-15-EPD.105 Generator Cable Tray Installation 7 22-Oct-24 30-Oct-24 Generator Cable Tray Installation

UCR-15-EPD.115 Generator Cable Pulling 7 30-Oct-24 07-Nov-24 Generator Cable Pulling

UCR-15-EPD.125 Generator Cell Pannel Installation 7 07-Nov-24 16-Nov-24 Generator Cell Pannel Installation

UCR-15-EPD.135 Generator Installation 7 16-Nov-24 24-Nov-24 Generator Installation

UCR-15-EPD.145 Generator Pannel / Cable Termination 7 24-Nov-24 01-Dec-24 Generator Pannel / Cable Termination

UCR-15-EPD.155 Generator Pannel / Cable initial Testing 5 02-Dec-24 07-Dec-24 Generator Pannel / Cable initial Testing

UPS 28 22-Oct-24 24-Nov-24 24-Nov-24, UPS


UCR-15-EPD.165 UPS Cable Tray Installation 5 22-Oct-24 28-Oct-24 UPS Cable Tray Installation

UCR-15-EPD.175 UPS Cable Pulling 5 28-Oct-24 03-Nov-24 UPS Cable Pulling

UCR-15-EPD.185 UPS Pannel Installation 5 03-Nov-24 09-Nov-24 UPS Pannel Installation

UCR-15-EPD.195 UPS Installation 5 09-Nov-24 14-Nov-24 UPS Installation

UCR-15-EPD.205 UPS Pannel / Cable Termination 5 14-Nov-24 19-Nov-24 UPS Pannel / Cable Termination

UCR-15-EPD.215 UPS Pannel / Cable initial Testing 4 20-Nov-24 24-Nov-24 UPS Pannel / Cable initial Testing

MDB 33 22-Oct-24 28-Nov-24 28-Nov-24, MDB


UCR-15-EPD.225 MDB Cable Tray Installation 7 22-Oct-24 30-Oct-24 MDB Cable Tray Installation

UCR-15-EPD.235 MDB Cable Pulling 7 30-Oct-24 07-Nov-24 MDB Cable Pulling

UCR-15-EPD.245 MDB Pannel Installation 7 07-Nov-24 16-Nov-24 MDB Pannel Installation

UCR-15-EPD.255 MDB Pannel / Cable Termination 7 16-Nov-24 24-Nov-24 MDB Pannel / Cable Termination

UCR-15-EPD.265 MDB Pannel / Cable initial Testing 5 24-Nov-24 28-Nov-24 MDB Pannel / Cable initial Testing

MCC 33 22-Oct-24 28-Nov-24 28-Nov-24, MCC


UCR-15-EPD.325 MCC Cable Tray Installation 7 22-Oct-24 30-Oct-24 MCC Cable Tray Installation

UCR-15-EPD.335 MCC Cable Pulling 7 30-Oct-24 07-Nov-24 MCC Cable Pulling

UCR-15-EPD.345 MCC Pannel Installation 7 07-Nov-24 16-Nov-24 MCC Pannel Installation

UCR-15-EPD.355 MCC Pannel / Cable Termination 7 16-Nov-24 24-Nov-24 MCC Pannel / Cable Termination

UCR-15-EPD.365 MCC Pannel / Cable initial Testing 5 24-Nov-24 28-Nov-24 MCC Pannel / Cable initial Testing

SMSB 24 22-Oct-24 18-Nov-24 18-Nov-24, SMSB


UCR-15-EPD.275 SMSB Cable Tray Installation 5 22-Oct-24 28-Oct-24 SMSB Cable Tray Installation

UCR-15-EPD.285 SMSB Cable Pulling 5 28-Oct-24 03-Nov-24 SMSB Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
105 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-15-EPD.295 SMSB Pannel Installation 5 03-Nov-24 09-Nov-24 SMSB Pannel Installation

UCR-15-EPD.305 SMSB Pannel / Cable Termination 5 09-Nov-24 14-Nov-24 SMSB Pannel / Cable Termination

UCR-15-EPD.315 SMSB Pannel / Cable initial Testing 4 14-Nov-24 18-Nov-24 SMSB Pannel / Cable initial Testing

DB 24 22-Oct-24 18-Nov-24 18-Nov-24, DB


UCR-15-EPD.375 DB Cable Tray Installation 5 22-Oct-24 28-Oct-24 DB Cable Tray Installation

UCR-15-EPD.385 DB Cable Pulling 5 28-Oct-24 03-Nov-24 DB Cable Pulling

UCR-15-EPD.395 DB Pannel Installation 5 03-Nov-24 09-Nov-24 DB Pannel Installation

UCR-15-EPD.405 DB Pannel / Cable Termination 5 09-Nov-24 14-Nov-24 DB Pannel / Cable Termination

UCR-15-EPD.415 DB Pannel / Cable initial Testing 4 14-Nov-24 18-Nov-24 DB Pannel / Cable initial Testing

ISOLATOR 24 22-Oct-24 18-Nov-24 18-Nov-24, ISOLATOR


UCR-15-EPD.425 Isolators Cable Tray Installation 5 22-Oct-24 28-Oct-24 Isolators Cable Tray Installation

UCR-15-EPD.435 Isolators Cable Pulling 5 28-Oct-24 03-Nov-24 Isolators Cable Pulling

UCR-15-EPD.445 Isolators Pannel Installation 5 03-Nov-24 09-Nov-24 Isolators Pannel Installation

UCR-15-EPD.455 Isolators Pannel / Cable Termination 5 09-Nov-24 14-Nov-24 Isolators Pannel / Cable Termination

UCR-15-EPD.465 Isolators Pannel / Cable initial Testing 4 14-Nov-24 18-Nov-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 22-Oct-24 18-Nov-24 18-Nov-24, LCP/ ELCP


UCR-15-EPD.475 LCP/ELCP Cable Tray Installation 5 22-Oct-24 28-Oct-24 LCP/ELCP Cable Tray Installation

UCR-15-EPD.485 LCP/ELCP Cable Pulling 5 28-Oct-24 03-Nov-24 LCP/ELCP Cable Pulling

UCR-15-EPD.495 LCP/ELCP Pannel Installation 5 03-Nov-24 09-Nov-24 LCP/ELCP Pannel Installation

UCR-15-EPD.505 LCP/ELCP Pannel / Cable Termination 5 09-Nov-24 14-Nov-24 LCP/ELCP Pannel / Cable Termination

UCR-15-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 14-Nov-24 18-Nov-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 42 30-Oct-24 17-Dec-24 17-Dec-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 30-Oct-24 17-Dec-24 17-Dec-24, FIRE ALARM SYSTEM
UCR-15-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 Fire Alarm Conduit /Cable Tray Installation

UCR-15-ELFA.115 Fire Alarm Cable Pulling 9 10-Nov-24 20-Nov-24 Fire Alarm Cable Pulling

UCR-15-ELFA.125 Fire Alarm Devices Installation 9 20-Nov-24 01-Dec-24 Fire Alarm Devices Installation

UCR-15-ELFA.135 Fire Alarm Devices and Cable Termination 9 01-Dec-24 10-Dec-24 Fire Alarm Devices and Cable Termination

UCR-15-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 30-Oct-24 17-Dec-24 17-Dec-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-15-ELVS.105 ICT System Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 ICT System Conduit /Cable Tray Installation

UCR-15-ELVS.115 ICT System Cable Pulling 9 10-Nov-24 20-Nov-24 ICT System Cable Pulling

UCR-15-ELVS.125 ICT System Devices Installation 9 20-Nov-24 01-Dec-24 ICT System Devices Installation

UCR-15-ELVS.135 ICT System Devices and Cable Termination 9 01-Dec-24 10-Dec-24 ICT System Devices and Cable Termination

UCR-15-ELVS.145 ICT System Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 30-Oct-24 17-Dec-24 17-Dec-24, ACCESS CONTROL SYSTEM


UCR-15-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 Access Control System Conduit /Cable Tray Installation

UCR-15-ELAC.115 Access Control System Cable Pulling 9 10-Nov-24 20-Nov-24 Access Control System Cable Pulling

UCR-15-ELAC.125 Access Control System Devices Installation 9 20-Nov-24 01-Dec-24 Access Control System Devices Installation

UCR-15-ELAC.135 Access Control System Devices and Cable Termination 9 01-Dec-24 10-Dec-24 Access Control System Devices and Cable Termination

UCR-15-ELAC.145 Access Control System Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 30-Oct-24 17-Dec-24 17-Dec-24, PUBLIC ADDRESS SYSTEM


UCR-15-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 Public Address System Conduit /Cable Tray Installation

UCR-15-ELPA.115 Public Address System Cable Pulling 9 10-Nov-24 20-Nov-24 Public Address System Cable Pulling

UCR-15-ELPA.125 Public Address System Devices Installation 9 20-Nov-24 01-Dec-24 Public Address System Devices Installation

UCR-15-ELPA.135 Public Address System Devices and Cable Termination 9 01-Dec-24 10-Dec-24 Public Address System Devices and Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
106 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-15-ELPA.145 Public Address System Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 30-Oct-24 17-Dec-24 17-Dec-24, SCADA SYSTEM


UCR-15-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 SCADA System Conduit /Cable Tray Installation

UCR-15-ELSC.115 SCADA System Cable Pulling 9 10-Nov-24 20-Nov-24 SCADA System Cable Pulling

UCR-15-ELSC.125 SCADA System Devices Installation 9 20-Nov-24 01-Dec-24 SCADA System Devices Installation

UCR-15-ELSC.135 SCADA System Devices and Cable Termination 9 01-Dec-24 10-Dec-24 SCADA System Devices and Cable Termination

UCR-15-ELSC.145 SCADA System Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 30-Oct-24 17-Dec-24 17-Dec-24, RADIO RE- BROADCOASTING/ TETRA
UCR-15-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 30-Oct-24 10-Nov-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-15-ELRD.115 Radio/TETRA System Cable Pulling 9 10-Nov-24 20-Nov-24 Radio/TETRA System Cable Pulling

UCR-15-ELRD.125 Radio/TETRA System Devices Installation 9 20-Nov-24 01-Dec-24 Radio/TETRA System Devices Installation

UCR-15-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 01-Dec-24 10-Dec-24 Radio/TETRA System Devices and Cable Termination

UCR-15-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 11-Dec-24 17-Dec-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 15 30-Oct-24 17-Nov-24 17-Nov-24, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 30-Oct-24 14-Nov-24 14-Nov-24, FIRE FIGHTING
UCR-15-MFF.105 Fire Fighting system Pipe and accessories installation 11 30-Oct-24 12-Nov-24 Fire Fighting system Pipe and accessories installation

UCR-15-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 09-Nov-24 12-Nov-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-15-MFF.135 Fire Fighting system initial testing 2 12-Nov-24 14-Nov-24 Fire Fighting system initial testing

HVAC 15 30-Oct-24 17-Nov-24 17-Nov-24, HVAC


UCR-15-MHV.105 Duct and accessories installation 12 30-Oct-24 13-Nov-24 Duct and accessories installation

UCR-15-MHV.115 Fan installation 4 09-Nov-24 13-Nov-24 Fan installation

UCR-15-MHV.135 HVAC inital testing 3 13-Nov-24 17-Nov-24 HVAC inital testing

PLUMBING 4 30-Oct-24 04-Nov-24 04-Nov-24, PLUMBING


UCR-15-MPL.105 Plumbing drainage system installation 3 30-Oct-24 03-Nov-24 Plumbing drainage system installation

UCR-15-MPL.115 Plumbing drainage system initial testing 1 03-Nov-24 04-Nov-24 Plumbing drainage system initial testing

DRY UTILITIES 16 30-Oct-24 18-Nov-24 18-Nov-24, DRY UTILITIES


POWER 16 30-Oct-24 18-Nov-24 18-Nov-24, POWER
POWER LV 16 30-Oct-24 18-Nov-24 18-Nov-24, POWER LV
DU-P-LV.1075 Installation of support 1 30-Oct-24 31-Oct-24 Installation of support

DU-P-LV.1080 Installation of horizontal busbar 2 31-Oct-24 02-Nov-24 Installation of horizontal busbar

DU-P-LV.1085 Installation of vertical busbar 2 02-Nov-24 04-Nov-24 Installation of vertical busbar

DU-P-LV.1090 Installation of left/right elbow 2 04-Nov-24 05-Nov-24 Installation of left/right elbow

DU-P-LV.1095 Installation of right horizintal offset 2 06-Nov-24 07-Nov-24 Installation of right horizintal offset

DU-P-LV.1100 Instalaltion of upward vertical offset 3 07-Nov-24 11-Nov-24 Instalaltion of upward vertical offset

DU-P-LV.1105 Installation of downward vertical offset 3 11-Nov-24 14-Nov-24 Installation of downward vertical offset

DU-P-LV.1110 Installation of transformer and panel connection 2 16-Nov-24 18-Nov-24 Installation of transformer and panel connection

UTILITY ROOM 16 (IN ZONE 03) ON BACKFILL (FLD+15.85 m) 402 24-May-23 16-Sep-24 16-Sep-24, UTILITY ROOM 16 (IN ZONE 03) ON BACKFILL (FLD +15.85 m)
ENGINEERING 255 24-May-23 21-Mar-24 21-Mar-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 255 24-May-23 21-Mar-24 21-Mar-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR16-SI.1020
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR16-SI.1025
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.16ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.16ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.16ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.16ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
107 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.16ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.16ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.16ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.16ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.16ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.16ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.16ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.16ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 122 31-Oct-23 21-Mar-24 21-Mar-24, ELECTRICAL


CABLE TRAYS 115 31-Oct-23 13-Mar-24 13-Mar-24, CABLE TRAYS
UCR.16ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 31-Oct-23 16-Nov-23 Cable Tray Shop Drawings Preparation & Submission

UCR.16ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 28-Feb-24 13-Mar-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 101 16-Nov-23 13-Mar-24 13-Mar-24, POWER CABLES


UCR.16ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 16-Nov-23 03-Dec-23 Power Cables Shop Drawings Preparation & Submission

UCR.16ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 28-Feb-24 13-Mar-24 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 87 03-Dec-23 13-Mar-24 13-Mar-24, LIGHTING SYSTEM


UCR.16ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 03-Dec-23 19-Dec-23 Lighting System Shop Drawings Preparation & Submission

UCR.16ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 28-Feb-24 13-Mar-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 73 19-Dec-23 13-Mar-24 13-Mar-24, ELECTRICAL INSTALLATIONS


UCR.16ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 19-Dec-23 03-Jan-24 Electrical Installations Shop Drawings Preparation & Submission

UCR.16ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 28-Feb-24 13-Mar-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 60 04-Jan-24 13-Mar-24 13-Mar-24, TRANSFORMERS INSTALLATION


UCR.16ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 04-Jan-24 20-Jan-24 Transformers Installation Shop Drawings Preparation & Submission

UCR.16ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 28-Feb-24 13-Mar-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 20-Jan-24 06-Mar-24 06-Mar-24, LIGHTNING PROTECTION SYSTEM


UCR.16ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 20-Jan-24 05-Feb-24 Lightning Protection Drawings Preparation & Submission

UCR.16ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 21-Feb-24 06-Mar-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 05-Feb-24 06-Mar-24 06-Mar-24, EARTHING SYSTEM


UCR.16ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 05-Feb-24 21-Feb-24 Earthing System Shop Drawings Preparation & Submission

UCR.16ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 21-Feb-24 06-Mar-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 15-Nov-23 21-Mar-24 21-Mar-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 109 15-Nov-23 21-Mar-24 21-Mar-24, FIRE DETECTION AND ALARM SYSTEM
UCR.16ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 15-Nov-23 02-Dec-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.16ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 02-Dec-23 21-Mar-24 21-Mar-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.16ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 02-Dec-23 17-Dec-23 Telephone Shop Drawings Preparation & Submission

UCR.16ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 81 18-Dec-23 21-Mar-24 21-Mar-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.16ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 18-Dec-23 02-Jan-24 Public Address system Shop Drawings Preparation & Submission

UCR.16ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 02-Jan-24 21-Mar-24 21-Mar-24, VIDEO SURVEILLANCE


UCR.16ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 02-Jan-24 18-Jan-24 Video Surveillance system Shop Drawings Preparation & Submission

UCR.16ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 54 18-Jan-24 21-Mar-24 21-Mar-24, ACCESS CONTROL SYSTEM


UCR.16ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 18-Jan-24 04-Feb-24 Access Control system Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
108 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.16ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 04-Feb-24 21-Mar-24 21-Mar-24, RADIO RE-BROADCASTING SYSTEM


UCR.16ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 04-Feb-24 20-Feb-24 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.16ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 20-Feb-24 21-Mar-24 21-Mar-24, SCADA SYSTEM


UCR.16ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 20-Feb-24 07-Mar-24 SCADA system Shop Drawings Preparation & Submission

UCR.16ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 07-Mar-24 21-Mar-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY UTILITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.1200 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.1205 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.1200 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.1205 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.1200 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.1205 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.1200 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.1205 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 200 28-Dec-23 26-Aug-24 26-Aug-24, PROCUREMENT


CIVIL/STRUCTURAL 16 28-Dec-23 15-Jan-24 15-Jan-24, CIVIL/STRUCTURAL
UCR.16PRO-CV.110 Issue Purchase Order 6 28-Dec-23 03-Jan-24 Issue Purchase Order

UCR.16PRO-CV.115 Material Delivery 10 04-Jan-24 15-Jan-24 Material Delivery

MECHANICAL 128 21-Mar-24 26-Aug-24 26-Aug-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 21-Mar-24 30-Jul-24 30-Jul-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.16PR-MC-FF.110Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-MC-FF.115Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

VENTILATION SYSTEM 105 21-Apr-24 26-Aug-24 26-Aug-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 21-Apr-24 26-Aug-24 26-Aug-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.16PR-MC-DS.110
Issue Purchase Order 15 21-Apr-24 08-May-24 Issue Purchase Order

UCR.16PR-MC-DS.115
Material Delivery 90 08-May-24 26-Aug-24 Material Delivery

AIR CONDITIONING WORKS 105 21-Apr-24 26-Aug-24 26-Aug-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 21-Apr-24 26-Aug-24 26-Aug-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.16PR-MC-AC.110
Issue Purchase Order 15 21-Apr-24 08-May-24 Issue Purchase Order

UCR.16PR-MC-AC.115
Material Delivery 90 08-May-24 26-Aug-24 Material Delivery

PLUMBING SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 21-Mar-24 30-Jul-24 30-Jul-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.16PR-MC-PI.110Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-MC-PI.115Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

ELECTRICAL 118 06-Mar-24 30-Jul-24 30-Jul-24, ELECTRICAL


CABLE TRAY 105 13-Mar-24 22-Jul-24 22-Jul-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 13-Mar-24 22-Jul-24 22-Jul-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.16PR-EL-CT.110Issue Purchase Order 15 13-Mar-24 31-Mar-24 Issue Purchase Order

UCR.16PR-EL-CT.115Material Delivery 90 31-Mar-24 22-Jul-24 Material Delivery

POWER CABLES 105 13-Mar-24 22-Jul-24 22-Jul-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 13-Mar-24 22-Jul-24 22-Jul-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.16PR-EL-PC.110Issue Purchase Order 15 13-Mar-24 31-Mar-24 Issue Purchase Order

UCR.16PR-EL-PC.115Material Delivery 90 31-Mar-24 22-Jul-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
109 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LIGHTING SYSTEM 105 13-Mar-24 22-Jul-24 22-Jul-24, LIGHTING SYSTEM
CONDUIT,LIGHT 105 13-Mar-24 22-Jul-24 22-Jul-24, CONDUIT,LIGHT
UCR.16PR-EL-LS.110Issue Purchase Order 15 13-Mar-24 31-Mar-24 Issue Purchase Order

UCR.16PR-EL-LS.115Material Delivery 90 31-Mar-24 22-Jul-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 13-Mar-24 22-Jul-24 22-Jul-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 13-Mar-24 22-Jul-24 22-Jul-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.16PR-EL-EI.110 Issue Purchase Order 15 13-Mar-24 31-Mar-24 Issue Purchase Order

UCR.16PR-EL-EI.115 Material Delivery 90 31-Mar-24 22-Jul-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 06-Mar-24 15-Jul-24 15-Jul-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 06-Mar-24 15-Jul-24 15-Jul-24, LIGHTNING PROTECTION SYSTEM
UCR.16PR-EL-LP.110Issue Purchase Order 15 06-Mar-24 24-Mar-24 Issue Purchase Order

UCR.16PR-EL-LP.115Material Delivery 90 24-Mar-24 15-Jul-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 06-Mar-24 15-Jul-24 15-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 06-Mar-24 15-Jul-24 15-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.16PR-EL-ES.110Issue Purchase Order 15 06-Mar-24 24-Mar-24 Issue Purchase Order

UCR.16PR-EL-ES.115Material Delivery 90 24-Mar-24 15-Jul-24 Material Delivery

LOW CURRENT 105 21-Mar-24 30-Jul-24 30-Jul-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 21-Mar-24 30-Jul-24 30-Jul-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.16PR-ELL-FA.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-FA.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 21-Mar-24 30-Jul-24 30-Jul-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 21-Mar-24 30-Jul-24 30-Jul-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.16PR-ELL-PH.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-PH.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 21-Mar-24 30-Jul-24 30-Jul-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.16PR-ELL-PA.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-PA.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

VIDEO SURVEILLANCE 105 21-Mar-24 30-Jul-24 30-Jul-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 21-Mar-24 30-Jul-24 30-Jul-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.16PR-ELL-VS.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-VS.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

ACCESS CONTROL SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 21-Mar-24 30-Jul-24 30-Jul-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.16PR-ELL-AC.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-AC.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 21-Mar-24 30-Jul-24 30-Jul-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.16PR-ELL-RB.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-RB.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

SCADA SYSTEM 105 21-Mar-24 30-Jul-24 30-Jul-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 21-Mar-24 30-Jul-24 30-Jul-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.16PR-ELL-SD.20
Issue Purchase Order 15 21-Mar-24 08-Apr-24 Issue Purchase Order

UCR.16PR-ELL-SD.25
Material Delivery 90 08-Apr-24 30-Jul-24 Material Delivery

CONSTRUCTION 213 04-Jan-24 16-Sep-24 16-Sep-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 10 04-Jan-24 15-Jan-24 15-Jan-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR16-SI.280Soil Improvement 10 04-Jan-24 15-Jan-24 Soil Improvement

STRUCTURAL WORKS 158 16-Jan-24 25-Jul-24 25-Jul-24, STRUCTURAL WORKS


FOUNDATION 20 16-Jan-24 07-Feb-24 07-Feb-24, FOUNDATION
Part-1 20 16-Jan-24 07-Feb-24 07-Feb-24, Part-1
UCR-16-FDN-P1.150 Foundation Blinding concrete casting 1 16-Jan-24 16-Jan-24 Foundation Blinding concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
110 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-16-FDN-P1.155 Foundation water proofing on blinding concrete 2 17-Jan-24 18-Jan-24 Foundation water proofing on blinding concrete

UCR-16-FDN-P1.160 Foundation Protection screed on water poofing 1 18-Jan-24 20-Jan-24 Foundation Protection screed on water poofing

UCR-16-FDN-P1.170 Foundation Rebar installation 7 20-Jan-24 28-Jan-24 Foundation Rebar installation

UCR-16-FDN-P1.175 Foundation Formwork installation 4 28-Jan-24 01-Feb-24 Foundation Formwork installation

UCR-16-FDN-P1.180 Foundation Construction joint work 2 01-Feb-24 04-Feb-24 Foundation Construction joint work

UCR-16-FDN-P1.185 Foundation concrete casting 1 04-Feb-24 05-Feb-24 Foundation concrete casting

UCR-16-FDN-P1.190 Foundation concrete curing 1 05-Feb-24 06-Feb-24 Foundation concrete curing

UCR-16-FDN-P1.195 Foundation Formwork Removal 1 06-Feb-24 07-Feb-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 30 07-Feb-24 13-Mar-24 13-Mar-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 30 07-Feb-24 13-Mar-24 13-Mar-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 07-Feb-24 13-Mar-24 13-Mar-24, Part-1
UCR-16-WL-P1.135 Room Walls Rebar Installation 9 13-Feb-24 24-Feb-24 Room Walls Rebar Installation

UCR-16-WL-P1.140 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 24-Feb-24 26-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-16-WL-P1.145 Room Walls Formwork Installation 9 26-Feb-24 07-Mar-24 Room Walls Formwork Installation

UCR-16-WL-P1.150 Room Walls Concrete Casting 1 07-Mar-24 09-Mar-24 Room Walls Concrete Casting

UCR-16-WL-P1.155 Room Walls Curing work 1 09-Mar-24 10-Mar-24 Room Walls Curing work

UCR-16-WL-P1.160 Room Walls Formwork Removel 3 10-Mar-24 13-Mar-24 Room Walls Formwork Removel

UCR-16-WL-P1.165 Room Walls Scafolding for rebar 5 07-Feb-24 13-Feb-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 36 13-Mar-24 28-Apr-24 28-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 36 13-Mar-24 28-Apr-24 28-Apr-24, Part-1
UCR-16-TS-P1.125 Room Top Slab Formwork Installation 10 13-Mar-24 25-Mar-24 Room Top Slab Formwork Installation

UCR-16-TS-P1.130 Room Top Slab Rebar Installation 9 25-Mar-24 04-Apr-24 Room Top Slab Rebar Installation

UCR-16-TS-P1.135 Room Top Slab Concrete Casting 1 04-Apr-24 06-Apr-24 Room Top Slab Concrete Casting

UCR-16-TS-P1.140 Room Top slab Curing work 12 06-Apr-24 23-Apr-24 Room Top slab Curing work

UCR-16-TS-P1.145 Room Top Slab Formwork Removel 4 23-Apr-24 28-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 29 06-Apr-24 13-May-24 13-May-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 29 06-Apr-24 13-May-24 13-May-24, WALL CONCRETE CASTING STAGE-1
Part-1 29 06-Apr-24 13-May-24 13-May-24, Part-1
UCR-16-WL-S1-A.135
Room Walls Rebar Installation 8 14-Apr-24 23-Apr-24 Room Walls Rebar Installation

UCR-16-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 23-Apr-24 25-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-16-WL-S1-A.145
Room Walls Formwork Installation 10 25-Apr-24 07-May-24 Room Walls Formwork Installation

UCR-16-WL-S1-A.150
Room Walls Concrete Casting 1 07-May-24 08-May-24 Room Walls Concrete Casting

UCR-16-WL-S1-A.155
Room Walls Curing work 1 08-May-24 09-May-24 Room Walls Curing work

UCR-16-WL-S1-A.160
Room Walls Formwork Removel 3 09-May-24 13-May-24 Room Walls Formwork Removel

UCR-16-WL-S1-A.165
Room Walls Scafolding for rebar 4 06-Apr-24 14-Apr-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 36 13-May-24 29-Jun-24 29-Jun-24, SLAB ABOVE GROUND LEVEL
Part-1 36 13-May-24 29-Jun-24 29-Jun-24, Part-1
UCR-16-SLB-A.115 Room Top Slab Formwork Installation 10 13-May-24 25-May-24 Room Top Slab Formwork Installation

UCR-16-SLB-A.120 Room Top Slab Rebar Installation 9 25-May-24 04-Jun-24 Room Top Slab Rebar Installation

UCR-16-SLB-A.125 Room Top Slab Concrete Casting 1 04-Jun-24 05-Jun-24 Room Top Slab Concrete Casting

UCR-165-SLB-A.125 Room Top slab Curing work 12 05-Jun-24 24-Jun-24 Room Top slab Curing work

UCR-165-SLB-A.130 Room Top Slab Formwork Removel 4 24-Jun-24 29-Jun-24 Room Top Slab Formwork Removel

WATER PROOFING 23 29-Jun-24 25-Jul-24 25-Jul-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 29-Jun-24 10-Jul-24 10-Jul-24, WALL WATER PROOFING STAGE-1
UCR-16-WL-S1.115 Surface preparation work 3 29-Jun-24 02-Jul-24 Surface preparation work

UCR-16-WL-S1.120 Applying of waterproofing material 5 02-Jul-24 08-Jul-24 Applying of waterproofing material

UCR-16-WL-S1.125 UR Bck filling 2 08-Jul-24 10-Jul-24 UR Bck filling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
111 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB WATER PROOFING 23 29-Jun-24 25-Jul-24 25-Jul-24, TOP SLAB WATER PROOFING
UCR-16-SLB-S1.115 Surface preparation work 12 29-Jun-24 13-Jul-24 Surface preparation work

UCR-16-SLB-S1.120 Applying of waterproofing material 10 13-Jul-24 24-Jul-24 Applying of waterproofing material

UCR-16-SLB-S1.125 Leak Test 1 24-Jul-24 25-Jul-24 Leak Test

MECHANICAL ROOM MEP (UCR) 68 29-Jun-24 16-Sep-24 16-Sep-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN TUNNEL 68 29-Jun-24 16-Sep-24 16-Sep-24, ELECTRICAL WORK IN TUNNEL
POWER SYSTEM 67 29-Jun-24 15-Sep-24 15-Sep-24, POWER SYSTEM
EARTHING SYSTEM 25 29-Jun-24 28-Jul-24 28-Jul-24, EARTHING SYSTEM
UCR-16-EES.105 Earthing system Termination 6 15-Jul-24 22-Jul-24 Earthing system Termination

UCR-16-EES.115 Earthing system Initial Testing 5 22-Jul-24 28-Jul-24 Earthing system Initial Testing

UCR-16-EES.125 Earthing system soil resistivity test 6 29-Jun-24 06-Jul-24 Earthing system soil resistivity test

UCR-16-EES.135 Earthing system Copper rod/ earthing pit installation 8 06-Jul-24 15-Jul-24 Earthing system Copper rod/ earthing pit installation

LIGHTING SYSTEM 37 22-Jul-24 02-Sep-24 02-Sep-24, LIGHTING SYSTEM


UCR-16-ELI.105 Lighting system Conduit and boxes Installation 8 22-Jul-24 31-Jul-24 Lighting system Conduit and boxes Installation

UCR-16-ELI.115 Lighting system Cable Pulling 8 31-Jul-24 10-Aug-24 Lighting system Cable Pulling

UCR-16-ELI.125 Lighting system Installations 8 10-Aug-24 19-Aug-24 Lighting system Installations

UCR-16-ELI.135 Lighting system Termination 8 19-Aug-24 28-Aug-24 Lighting system Termination

UCR-16-ELI.145 Lighting system Initial Testing 5 28-Aug-24 02-Sep-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 22-Jul-24 15-Sep-24 15-Sep-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-16-ECT.105 Cable Tray Installation 10 22-Jul-24 03-Aug-24 Cable Tray Installation

UCR-16-ECT.115 Cable Tray Inspection 10 03-Aug-24 14-Aug-24 Cable Tray Inspection

UCR-16-ECT.125 LV Cable pulling 10 14-Aug-24 26-Aug-24 LV Cable pulling

UCR-16-ECT.135 LV Cable Termination 10 26-Aug-24 07-Sep-24 LV Cable Termination

UCR-16-ECT.145 LV Cable Initial Testing 8 07-Sep-24 15-Sep-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 22-Jul-24 04-Sep-24 04-Sep-24, SMALL POWER SYSTEM


UCR-16-ESP.105 Small Power Conduit and boxes Installation 12 22-Jul-24 05-Aug-24 Small Power Conduit and boxes Installation

UCR-16-ESP.115 Small Power Cable Pulling 10 05-Aug-24 17-Aug-24 Small Power Cable Pulling

UCR-16-ESP.125 Small Power Installations 6 17-Aug-24 24-Aug-24 Small Power Installations

UCR-16-ESP.135 Small Power Termination 6 24-Aug-24 31-Aug-24 Small Power Termination

UCR-16-ESP.145 Small Power Initial Testing 5 31-Aug-24 04-Sep-24 Small Power Initial Testing

POWER DISTRIBUTION 39 22-Jul-24 05-Sep-24 05-Sep-24, POWER DISTRIBUTION


GENERATOR 39 22-Jul-24 05-Sep-24 05-Sep-24, GENERATOR
UCR-16-EPD.105 Generator Cable Tray Installation 7 22-Jul-24 30-Jul-24 Generator Cable Tray Installation

UCR-16-EPD.115 Generator Cable Pulling 7 30-Jul-24 07-Aug-24 Generator Cable Pulling

UCR-16-EPD.125 Generator Cell Pannel Installation 7 07-Aug-24 15-Aug-24 Generator Cell Pannel Installation

UCR-16-EPD.135 Generator Installation 7 15-Aug-24 24-Aug-24 Generator Installation

UCR-16-EPD.145 Generator Pannel / Cable Termination 7 24-Aug-24 31-Aug-24 Generator Pannel / Cable Termination

UCR-16-EPD.155 Generator Pannel / Cable initial Testing 5 01-Sep-24 05-Sep-24 Generator Pannel / Cable initial Testing

UPS 28 22-Jul-24 24-Aug-24 24-Aug-24, UPS


UCR-16-EPD.165 UPS Cable Tray Installation 5 22-Jul-24 28-Jul-24 UPS Cable Tray Installation

UCR-16-EPD.175 UPS Cable Pulling 5 28-Jul-24 03-Aug-24 UPS Cable Pulling

UCR-16-EPD.185 UPS Pannel Installation 5 03-Aug-24 08-Aug-24 UPS Pannel Installation

UCR-16-EPD.195 UPS Installation 5 08-Aug-24 14-Aug-24 UPS Installation

UCR-16-EPD.205 UPS Pannel / Cable Termination 5 14-Aug-24 19-Aug-24 UPS Pannel / Cable Termination

UCR-16-EPD.215 UPS Pannel / Cable initial Testing 4 20-Aug-24 24-Aug-24 UPS Pannel / Cable initial Testing

MDB 33 22-Jul-24 28-Aug-24 28-Aug-24, MDB


UCR-16-EPD.225 MDB Cable Tray Installation 7 22-Jul-24 30-Jul-24 MDB Cable Tray Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
112 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-16-EPD.235 MDB Cable Pulling 7 30-Jul-24 07-Aug-24 MDB Cable Pulling

UCR-16-EPD.245 MDB Pannel Installation 7 07-Aug-24 15-Aug-24 MDB Pannel Installation

UCR-16-EPD.255 MDB Pannel / Cable Termination 7 15-Aug-24 24-Aug-24 MDB Pannel / Cable Termination

UCR-16-EPD.265 MDB Pannel / Cable initial Testing 5 24-Aug-24 28-Aug-24 MDB Pannel / Cable initial Testing

MCC 33 22-Jul-24 28-Aug-24 28-Aug-24, MCC


UCR-16-EPD.325 MCC Cable Tray Installation 7 22-Jul-24 30-Jul-24 MCC Cable Tray Installation

UCR-16-EPD.335 MCC Cable Pulling 7 30-Jul-24 07-Aug-24 MCC Cable Pulling

UCR-16-EPD.345 MCC Pannel Installation 7 07-Aug-24 15-Aug-24 MCC Pannel Installation

UCR-16-EPD.355 MCC Pannel / Cable Termination 7 15-Aug-24 24-Aug-24 MCC Pannel / Cable Termination

UCR-16-EPD.365 MCC Pannel / Cable initial Testing 5 24-Aug-24 28-Aug-24 MCC Pannel / Cable initial Testing

SMSB 24 22-Jul-24 18-Aug-24 18-Aug-24, SMSB


UCR-16-EPD.275 SMSB Cable Tray Installation 5 22-Jul-24 28-Jul-24 SMSB Cable Tray Installation

UCR-16-EPD.285 SMSB Cable Pulling 5 28-Jul-24 03-Aug-24 SMSB Cable Pulling

UCR-16-EPD.295 SMSB Pannel Installation 5 03-Aug-24 08-Aug-24 SMSB Pannel Installation

UCR-16-EPD.305 SMSB Pannel / Cable Termination 5 08-Aug-24 14-Aug-24 SMSB Pannel / Cable Termination

UCR-16-EPD.315 SMSB Pannel / Cable initial Testing 4 14-Aug-24 18-Aug-24 SMSB Pannel / Cable initial Testing

DB 24 22-Jul-24 18-Aug-24 18-Aug-24, DB


UCR-16-EPD.375 DB Cable Tray Installation 5 22-Jul-24 28-Jul-24 DB Cable Tray Installation

UCR-16-EPD.385 DB Cable Pulling 5 28-Jul-24 03-Aug-24 DB Cable Pulling

UCR-16-EPD.395 DB Pannel Installation 5 03-Aug-24 08-Aug-24 DB Pannel Installation

UCR-16-EPD.405 DB Pannel / Cable Termination 5 08-Aug-24 14-Aug-24 DB Pannel / Cable Termination

UCR-16-EPD.415 DB Pannel / Cable initial Testing 4 14-Aug-24 18-Aug-24 DB Pannel / Cable initial Testing

ISOLATOR 24 22-Jul-24 18-Aug-24 18-Aug-24, ISOLATOR


UCR-16-EPD.425 Isolators Cable Tray Installation 5 22-Jul-24 28-Jul-24 Isolators Cable Tray Installation

UCR-16-EPD.435 Isolators Cable Pulling 5 28-Jul-24 03-Aug-24 Isolators Cable Pulling

UCR-16-EPD.445 Isolators Pannel Installation 5 03-Aug-24 08-Aug-24 Isolators Pannel Installation

UCR-16-EPD.455 Isolators Pannel / Cable Termination 5 08-Aug-24 14-Aug-24 Isolators Pannel / Cable Termination

UCR-16-EPD.465 Isolators Pannel / Cable initial Testing 4 14-Aug-24 18-Aug-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 22-Jul-24 18-Aug-24 18-Aug-24, LCP/ ELCP


UCR-16-EPD.475 LCP/ELCP Cable Tray Installation 5 22-Jul-24 28-Jul-24 LCP/ELCP Cable Tray Installation

UCR-16-EPD.485 LCP/ELCP Cable Pulling 5 28-Jul-24 03-Aug-24 LCP/ELCP Cable Pulling

UCR-16-EPD.495 LCP/ELCP Pannel Installation 5 03-Aug-24 08-Aug-24 LCP/ELCP Pannel Installation

UCR-16-EPD.505 LCP/ELCP Pannel / Cable Termination 5 08-Aug-24 14-Aug-24 LCP/ELCP Pannel / Cable Termination

UCR-16-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 14-Aug-24 18-Aug-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 42 30-Jul-24 16-Sep-24 16-Sep-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 30-Jul-24 16-Sep-24 16-Sep-24, FIRE ALARM SYSTEM
UCR-16-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 Fire Alarm Conduit /Cable Tray Installation

UCR-16-ELFA.115 Fire Alarm Cable Pulling 9 10-Aug-24 20-Aug-24 Fire Alarm Cable Pulling

UCR-16-ELFA.125 Fire Alarm Devices Installation 9 20-Aug-24 31-Aug-24 Fire Alarm Devices Installation

UCR-16-ELFA.135 Fire Alarm Devices and Cable Termination 9 31-Aug-24 09-Sep-24 Fire Alarm Devices and Cable Termination

UCR-16-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 30-Jul-24 16-Sep-24 16-Sep-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-16-ELVS.105 ICT System Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 ICT System Conduit /Cable Tray Installation

UCR-16-ELVS.115 ICT System Cable Pulling 9 10-Aug-24 20-Aug-24 ICT System Cable Pulling

UCR-16-ELVS.125 ICT System Devices Installation 9 20-Aug-24 31-Aug-24 ICT System Devices Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
113 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-16-ELVS.135 ICT System Devices and Cable Termination 9 31-Aug-24 09-Sep-24 ICT System Devices and Cable Termination

UCR-16-ELVS.145 ICT System Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 30-Jul-24 16-Sep-24 16-Sep-24, ACCESS CONTROL SYSTEM


UCR-16-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 Access Control System Conduit /Cable Tray Installation

UCR-16-ELAC.115 Access Control System Cable Pulling 9 10-Aug-24 20-Aug-24 Access Control System Cable Pulling

UCR-16-ELAC.125 Access Control System Devices Installation 9 20-Aug-24 31-Aug-24 Access Control System Devices Installation

UCR-16-ELAC.135 Access Control System Devices and Cable Termination 9 31-Aug-24 09-Sep-24 Access Control System Devices and Cable Termination

UCR-16-ELAC.145 Access Control System Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 30-Jul-24 16-Sep-24 16-Sep-24, PUBLIC ADDRESS SYSTEM


UCR-16-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 Public Address System Conduit /Cable Tray Installation

UCR-16-ELPA.115 Public Address System Cable Pulling 9 10-Aug-24 20-Aug-24 Public Address System Cable Pulling

UCR-16-ELPA.125 Public Address System Devices Installation 9 20-Aug-24 31-Aug-24 Public Address System Devices Installation

UCR-16-ELPA.135 Public Address System Devices and Cable Termination 9 31-Aug-24 09-Sep-24 Public Address System Devices and Cable Termination

UCR-16-ELPA.145 Public Address System Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 30-Jul-24 16-Sep-24 16-Sep-24, SCADA SYSTEM


UCR-16-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 SCADA System Conduit /Cable Tray Installation

UCR-16-ELSC.115 SCADA System Cable Pulling 9 10-Aug-24 20-Aug-24 SCADA System Cable Pulling

UCR-16-ELSC.125 SCADA System Devices Installation 9 20-Aug-24 31-Aug-24 SCADA System Devices Installation

UCR-16-ELSC.135 SCADA System Devices and Cable Termination 9 31-Aug-24 09-Sep-24 SCADA System Devices and Cable Termination

UCR-16-ELSC.145 SCADA System Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 30-Jul-24 16-Sep-24 16-Sep-24, RADIO RE- BROADCOASTING/ TETRA
UCR-16-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 30-Jul-24 10-Aug-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-16-ELRD.115 Radio/TETRA System Cable Pulling 9 10-Aug-24 20-Aug-24 Radio/TETRA System Cable Pulling

UCR-16-ELRD.125 Radio/TETRA System Devices Installation 9 20-Aug-24 31-Aug-24 Radio/TETRA System Devices Installation

UCR-16-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 31-Aug-24 09-Sep-24 Radio/TETRA System Devices and Cable Termination

UCR-16-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 10-Sep-24 16-Sep-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN TUNNEL 31 30-Jul-24 04-Sep-24 04-Sep-24, MECHANICAL WORK IN TUNNEL


FIRE FIGHTING 13 30-Jul-24 14-Aug-24 14-Aug-24, FIRE FIGHTING
UCR-16-MFF.105 Fire Fighting system Pipe and accessories installation 11 30-Jul-24 12-Aug-24 Fire Fighting system Pipe and accessories installation

UCR-16-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 3 08-Aug-24 12-Aug-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-16-MFF.140 Fire Fighting system initial testing 2 12-Aug-24 14-Aug-24 Fire Fighting system initial testing

UCR-16-MFF.145 Fire Fighting clean agent system 2 10-Aug-24 12-Aug-24 Fire Fighting clean agent system

HVAC 20 12-Aug-24 04-Sep-24 04-Sep-24, HVAC


UCR-16-MHV.115 Air conditioning system installation 5 26-Aug-24 01-Sep-24 Air conditioning system installation

UCR-16-MHV.120 Fan installation 4 27-Aug-24 01-Sep-24 Fan installation

UCR-16-MHV.125 Duct and accessories installation 12 12-Aug-24 26-Aug-24 Duct and accessories installation

UCR-16-MHV.135 HVAC inital testing 3 01-Sep-24 04-Sep-24 HVAC inital testing

PLUMBING 4 30-Jul-24 04-Aug-24 04-Aug-24, PLUMBING


UCR-16-MPL.105 Plumbing drainage system installation 3 30-Jul-24 03-Aug-24 Plumbing drainage system installation

UCR-16-MPL.115 Plumbing drainage system initial testing 1 03-Aug-24 04-Aug-24 Plumbing drainage system initial testing

DRY UTILITIES 18 30-Jul-24 19-Aug-24 19-Aug-24, DRY UTILITIES


POWER 18 30-Jul-24 19-Aug-24 19-Aug-24, POWER
POWER LV 16 30-Jul-24 18-Aug-24 18-Aug-24, POWER LV
DU-P-LV.1120 Installation of support 1 30-Jul-24 31-Jul-24 Installation of support

DU-P-LV.1125 Installation of horizontal busbar 2 31-Jul-24 01-Aug-24 Installation of horizontal busbar

DU-P-LV.1130 Installation of vertical busbar 2 01-Aug-24 04-Aug-24 Installation of vertical busbar

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
114 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-LV.1135 Installation of left/right elbow 2 04-Aug-24 05-Aug-24 Installation of left/right elbow

DU-P-LV.1140 Installation of right horizintal offset 2 06-Aug-24 07-Aug-24 Installation of right horizintal offset

DU-P-LV.1145 Instalaltion of upward vertical offset 3 07-Aug-24 11-Aug-24 Instalaltion of upward vertical offset

DU-P-LV.1150 Installation of downward vertical offset 3 11-Aug-24 14-Aug-24 Installation of downward vertical offset

DU-P-LV.1155 Installation of transformer and panel connection 2 15-Aug-24 18-Aug-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 30-Jul-24 19-Aug-24 19-Aug-24, MEDIUM VOLTAGE


DU-P-MV.1120 Installation of cable try, arm, racks and ladder 6 30-Jul-24 06-Aug-24 Installation of cable try, arm, racks and ladder

DU-P-MV.1125 Installation of MV Cable 4 06-Aug-24 11-Aug-24 Installation of MV Cable

DU-P-MV.1130 Installation of cable cleats 2 11-Aug-24 13-Aug-24 Installation of cable cleats

DU-P-MV.1135 Installation of gland 1 13-Aug-24 14-Aug-24 Installation of gland

DU-P-MV.1140 splicing/termination of MV cable 2 14-Aug-24 15-Aug-24 splicing/termination of MV cable

DU-P-MV.1145 Testing and Pre-commissioning of cable 2 15-Aug-24 18-Aug-24 Testing and Pre-commissioning of cable

DU-P-MV.1150 Energezation 2 18-Aug-24 19-Aug-24 Energezation

TRANSFORMER 16 30-Jul-24 18-Aug-24 18-Aug-24, TRANSFORMER


DU-P-T.1120 Installation of Transformer unit 2 30-Jul-24 31-Jul-24 Installation of Transformer unit

DU-P-T.1125 Testing and Pre-Commissioning of unit 1 01-Aug-24 01-Aug-24 Testing and Pre-Commissioning of unit

DU-P-T.1130 Termination and Splicing of MV Cable 3 01-Aug-24 05-Aug-24 Termination and Splicing of MV Cable

DU-P-T.1135 Termination and Splicing of LV Cable/bus way 3 06-Aug-24 10-Aug-24 Termination and Splicing of LV Cable/bus way

DU-P-T.1140 Installation and connection of I/O system 2 10-Aug-24 12-Aug-24 Installation and connection of I/O system

DU-P-T.1145 Installation of Grounding and Protection System 2 12-Aug-24 14-Aug-24 Installation of Grounding and Protection System

DU-P-T.1150 Testing and Commissioning of MV System 1 15-Aug-24 15-Aug-24 Testing and Commissioning of MV System

DU-P-T.1155 Testing and Commissioning of LV System 1 15-Aug-24 17-Aug-24 Testing and Commissioning of LV System

DU-P-T.1160 Energezation 1 17-Aug-24 18-Aug-24 Energezation

RMU 16 30-Jul-24 18-Aug-24 18-Aug-24, RMU


DU-P-RMU.1120 Installation RMU unit 2 30-Jul-24 01-Aug-24 Installation RMU unit

DU-P-RMU.1125 Testing and Pre-Commissioning of unit 2 01-Aug-24 04-Aug-24 Testing and Pre-Commissioning of unit

DU-P-RMU.1130 Termination and Splicing of Ring-MV Cable 4 04-Aug-24 08-Aug-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.1135 Termination and Splicing of T-MV Cable 4 08-Aug-24 13-Aug-24 Termination and Splicing of T-MV Cable

DU-P-RMU.1140 Installation of Grounding and Protection System 2 13-Aug-24 15-Aug-24 Installation of Grounding and Protection System

DU-P-RMU.1145 Testing and Commissioning of MV System 1 15-Aug-24 17-Aug-24 Testing and Commissioning of MV System

DU-P-RMU.1150 Energezation 1 17-Aug-24 18-Aug-24 Energezation

UTILITY ROOM 13 (IN ZONE 04) ON BACKFILL (FLD+13.35 m) 597 24-May-23 08-May-25 08-May-25, UTILITY ROOM 13 (IN ZONE 04) ON BACKFILL (FLD +13.35 m)
ENGINEERING 481 24-May-23 19-Dec-24 19-Dec-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 481 24-May-23 19-Dec-24 19-Dec-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR13-SI.1030
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR13-SI.1035
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.13ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.13ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.13ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.13ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.13ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.13ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
115 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.13ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.13ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.13ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.13ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.13ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.13ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 481 24-May-23 19-Dec-24 19-Dec-24, ELECTRICAL


CABLE TRAYS 40 24-May-23 12-Jul-23 12-Jul-23, CABLE TRAYS
UCR.13ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

UCR.13ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


UCR.13ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

UCR.13ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


UCR.13ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

UCR.13ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 40 15-Jul-23 30-Aug-23 30-Aug-23, ELECTRICAL INSTALLATIONS


UCR.13ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.13ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 26 31-Jul-23 30-Aug-23 30-Aug-23, TRANSFORMERS INSTALLATION


UCR.13ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Transformers Installation Shop Drawings Preparation & Submission

UCR.13ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 03-Nov-24 19-Dec-24 19-Dec-24, LIGHTNING PROTECTION SYSTEM


UCR.13ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 03-Nov-24 19-Nov-24 Lightning Protection Drawings Preparation & Submission

UCR.13ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 05-Dec-24 19-Dec-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 19-Nov-24 19-Dec-24 19-Dec-24, EARTHING SYSTEM


UCR.13ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 19-Nov-24 05-Dec-24 Earthing System Shop Drawings Preparation & Submission

UCR.13ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 05-Dec-24 19-Dec-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
UCR.13ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.13ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 54 08-Jun-23 14-Aug-23 14-Aug-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.13ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

UCR.13ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.13ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

UCR.13ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


UCR.13ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.13ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


UCR.13ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

UCR.13ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


UCR.13ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.13ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
116 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM
UCR.13ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

UCR.13ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY UTILITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.795
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.805
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


MEP-VR01-ENG-PWR.815
Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

MEP-VR01-ENG-PWR.825
Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


MEP-VR01-ENG-PWR.835
Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

MEP-VR01-ENG-PWR.845
Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


MEP-VR01-ENG-PWR.855
Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

MEP-VR01-ENG-PWR.865
Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 561 22-Jun-23 26-Apr-25 26-Apr-25, PROCUREMENT


CIVIL/STRUCTURAL 16 08-Sep-24 26-Sep-24 26-Sep-24, CIVIL/STRUCTURAL
UCR.13PRO-CV.110 Issue Purchase Order 6 08-Sep-24 14-Sep-24 Issue Purchase Order

UCR.13PRO-CV.115 Material Delivery 10 15-Sep-24 26-Sep-24 Material Delivery

MECHANICAL 128 27-Sep-23 24-Feb-24 24-Feb-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 27-Sep-23 28-Jan-24 28-Jan-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 27-Sep-23 28-Jan-24 28-Jan-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.13PR-MC-FF.110Issue Purchase Order 15 27-Sep-23 15-Oct-23 Issue Purchase Order

UCR.13PR-MC-FF.115Material Delivery 90 15-Oct-23 28-Jan-24 Material Delivery

VENTILATION SYSTEM 105 24-Oct-23 24-Feb-24 24-Feb-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 24-Oct-23 24-Feb-24 24-Feb-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.13PR-MC-DS.110
Issue Purchase Order 15 24-Oct-23 11-Nov-23 Issue Purchase Order

UCR.13PR-MC-DS.115
Material Delivery 90 11-Nov-23 24-Feb-24 Material Delivery

AIR CONDITIONING WORKS 105 24-Oct-23 24-Feb-24 24-Feb-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 24-Oct-23 24-Feb-24 24-Feb-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.13PR-MC-AC.110
Issue Purchase Order 15 24-Oct-23 11-Nov-23 Issue Purchase Order

UCR.13PR-MC-AC.115
Material Delivery 90 11-Nov-23 24-Feb-24 Material Delivery

PLUMBING SYSTEM 105 24-Oct-23 24-Feb-24 24-Feb-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 24-Oct-23 24-Feb-24 24-Feb-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.13PR-MC-PI.110Issue Purchase Order 15 24-Oct-23 11-Nov-23 Issue Purchase Order

UCR.13PR-MC-PI.115Material Delivery 90 11-Nov-23 24-Feb-24 Material Delivery

ELECTRICAL 561 22-Jun-23 26-Apr-25 26-Apr-25, ELECTRICAL


CABLE TRAY 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.13PR-EL-CT.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.13PR-EL-CT.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.13PR-EL-PC.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.13PR-EL-PC.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

LIGHTING SYSTEM 105 29-Jul-23 29-Nov-23 29-Nov-23, LIGHTING SYSTEM


CONDUIT,LIGHT 105 29-Jul-23 29-Nov-23 29-Nov-23, CONDUIT,LIGHT
UCR.13PR-EL-LS.110Issue Purchase Order 15 29-Jul-23 15-Aug-23 Issue Purchase Order

UCR.13PR-EL-LS.115Material Delivery 90 15-Aug-23 29-Nov-23 Material Delivery

ELECTRICAL INSTALLATIONS 105 30-Aug-23 01-Jan-24 01-Jan-24, ELECTRICAL INSTALLATIONS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
117 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 30-Aug-23 01-Jan-24 01-Jan-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.13PR-EL-EI.110 Issue Purchase Order 15 30-Aug-23 17-Sep-23 Issue Purchase Order

UCR.13PR-EL-EI.115 Material Delivery 90 17-Sep-23 01-Jan-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 19-Dec-24 26-Apr-25 26-Apr-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 19-Dec-24 26-Apr-25 26-Apr-25, LIGHTNING PROTECTION SYSTEM
UCR.13PR-EL-LP.110Issue Purchase Order 15 19-Dec-24 06-Jan-25 Issue Purchase Order

UCR.13PR-EL-LP.115Material Delivery 90 06-Jan-25 26-Apr-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 19-Dec-24 26-Apr-25 26-Apr-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 19-Dec-24 26-Apr-25 26-Apr-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.13PR-EL-ES.110Issue Purchase Order 15 19-Dec-24 06-Jan-25 Issue Purchase Order

UCR.13PR-EL-ES.115Material Delivery 90 06-Jan-25 26-Apr-25 Material Delivery

LOW CURRENT 188 22-Jun-23 03-Feb-24 03-Feb-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.13PR-ELL-FA.20
Issue Purchase Order 15 22-Jun-23 13-Jul-23 Issue Purchase Order

UCR.13PR-ELL-FA.25
Material Delivery 90 13-Jul-23 28-Oct-23 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 14-Aug-23 16-Dec-23 16-Dec-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 14-Aug-23 16-Dec-23 16-Dec-23, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.13PR-ELL-PH.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.13PR-ELL-PH.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 29-Jul-23 29-Nov-23 29-Nov-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 29-Jul-23 29-Nov-23 29-Nov-23, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.13PR-ELL-PA.20
Issue Purchase Order 15 29-Jul-23 15-Aug-23 Issue Purchase Order

UCR.13PR-ELL-PA.25
Material Delivery 90 15-Aug-23 29-Nov-23 Material Delivery

VIDEO SURVEILLANCE 105 14-Aug-23 16-Dec-23 16-Dec-23, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 14-Aug-23 16-Dec-23 16-Dec-23, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.13PR-ELL-VS.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.13PR-ELL-VS.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

ACCESS CONTROL SYSTEM 105 30-Aug-23 01-Jan-24 01-Jan-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 30-Aug-23 01-Jan-24 01-Jan-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.13PR-ELL-AC.20
Issue Purchase Order 15 30-Aug-23 17-Sep-23 Issue Purchase Order

UCR.13PR-ELL-AC.25
Material Delivery 90 17-Sep-23 01-Jan-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 16-Sep-23 17-Jan-24 17-Jan-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 16-Sep-23 17-Jan-24 17-Jan-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.13PR-ELL-RB.20
Issue Purchase Order 15 16-Sep-23 04-Oct-23 Issue Purchase Order

UCR.13PR-ELL-RB.25
Material Delivery 90 04-Oct-23 17-Jan-24 Material Delivery

SCADA SYSTEM 105 03-Oct-23 03-Feb-24 03-Feb-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 03-Oct-23 03-Feb-24 03-Feb-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.13PR-ELL-SD.20
Issue Purchase Order 15 03-Oct-23 21-Oct-23 Issue Purchase Order

UCR.13PR-ELL-SD.25
Material Delivery 90 21-Oct-23 03-Feb-24 Material Delivery

CONSTRUCTION 466 28-Oct-23 08-May-25 08-May-25, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 05-Sep-24 26-Sep-24 26-Sep-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR13-SI.285Soil Improvement 18 05-Sep-24 26-Sep-24 Soil Improvement

STRUCTURAL WORKS 187 28-Sep-24 07-May-25 07-May-25, STRUCTURAL WORKS


FOUNDATION 23 28-Sep-24 23-Oct-24 23-Oct-24, FOUNDATION
Part-1 23 28-Sep-24 23-Oct-24 23-Oct-24, Part-1
UCR-13-FDN-P1.150 Foundation Blinding concrete casting 1 28-Sep-24 28-Sep-24 Foundation Blinding concrete casting

UCR-13-FDN-P1.155 Foundation water proofing on blinding concrete 2 29-Sep-24 30-Sep-24 Foundation water proofing on blinding concrete

UCR-13-FDN-P1.160 Foundation Protection screed on water poofing 1 30-Sep-24 01-Oct-24 Foundation Protection screed on water poofing

UCR-13-FDN-P1.165 Foundation Curing for screed 2 01-Oct-24 03-Oct-24 Foundation Curing for screed

UCR-13-FDN-P1.170 Foundation Rebar installation 8 03-Oct-24 13-Oct-24 Foundation Rebar installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
118 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-13-FDN-P1.175 Foundation Formwork installation 4 13-Oct-24 17-Oct-24 Foundation Formwork installation

UCR-13-FDN-P1.180 Foundation Construction joint work 2 17-Oct-24 20-Oct-24 Foundation Construction joint work

UCR-13-FDN-P1.185 Foundation concrete casting 1 20-Oct-24 21-Oct-24 Foundation concrete casting

UCR-13-FDN-P1.190 Foundation concrete curing 1 21-Oct-24 22-Oct-24 Foundation concrete curing

UCR-13-FDN-P1.195 Foundation Formwork Removal 1 22-Oct-24 23-Oct-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 33 23-Oct-24 01-Dec-24 01-Dec-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 33 23-Oct-24 01-Dec-24 01-Dec-24, WALL CONCRETE CASTING STAGE-1
Part-1 33 23-Oct-24 01-Dec-24 01-Dec-24, Part-1
UCR-13-WL-S1-P1.135
Room Walls Rebar Installation 10 30-Oct-24 11-Nov-24 Room Walls Rebar Installation

UCR-13-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 11-Nov-24 13-Nov-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-13-WL-S1-P1.145
Room Walls Formwork Installation 10 13-Nov-24 25-Nov-24 Room Walls Formwork Installation

UCR-13-WL-S1-P1.150
Room Walls Concrete Casting 1 25-Nov-24 26-Nov-24 Room Walls Concrete Casting

UCR-13-WL-S1-P1.155
Room Walls Curing work 1 26-Nov-24 27-Nov-24 Room Walls Curing work

UCR-13-WL-S1-P1.160
Room Walls Formwork Removel 3 27-Nov-24 01-Dec-24 Room Walls Formwork Removel

UCR-13-WL-S1-P1.165
Room Walls Scafolding for rebar 6 23-Oct-24 30-Oct-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 39 01-Dec-24 15-Jan-25 15-Jan-25, TOP SLAB BELOW GROUND LEVEL
Part-1 39 01-Dec-24 15-Jan-25 15-Jan-25, Part-1
UCR-13-TS-P1.125 Room Top Slab Formwork Installation 12 01-Dec-24 15-Dec-24 Room Top Slab Formwork Installation

UCR-13-TS-P1.130 Room Top Slab Rebar Installation 10 15-Dec-24 26-Dec-24 Room Top Slab Rebar Installation

UCR-13-TS-P1.135 Room Top Slab Concrete Casting 1 26-Dec-24 28-Dec-24 Room Top Slab Concrete Casting

UCR-13-TS-P1.140 Room Top slab Curing work 12 28-Dec-24 11-Jan-25 Room Top slab Curing work

UCR-13-TS-P1.145 Room Top Slab Formwork Removel 4 11-Jan-25 15-Jan-25 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 29 15-Jan-25 18-Feb-25 18-Feb-25, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 29 15-Jan-25 18-Feb-25 18-Feb-25, WALL CONCRETE CASTING STAGE-1
Part-1 29 15-Jan-25 18-Feb-25 18-Feb-25, Part-1
UCR-13-WL.SG1-P1.135
Room Walls Rebar Installation 8 20-Jan-25 29-Jan-25 Room Walls Rebar Installation

UCR-13-WL.SG1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 29-Jan-25 01-Feb-25 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-13-WL.SG1-P1.145
Room Walls Formwork Installation 10 01-Feb-25 12-Feb-25 Room Walls Formwork Installation

UCR-13-WL.SG1-P1.150
Room Walls Concrete Casting 1 12-Feb-25 13-Feb-25 Room Walls Concrete Casting

UCR-13-WL.SG1-P1.155
Room Walls Curing work 1 13-Feb-25 15-Feb-25 Room Walls Curing work

UCR-13-WL.SG1-P1.160
Room Walls Formwork Removel 3 15-Feb-25 18-Feb-25 Room Walls Formwork Removel

UCR-13-WL.SG1-P1.165
Room Walls Scafolding for rebar 4 15-Jan-25 20-Jan-25 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 39 18-Feb-25 09-Apr-25 09-Apr-25, SLAB ABOVE GROUND LEVEL
Part-1 39 18-Feb-25 09-Apr-25 09-Apr-25, Part-1
UCR-13-SLB-A.125 Room Top Slab Formwork Installation 12 18-Feb-25 04-Mar-25 Room Top Slab Formwork Installation

UCR-13-SLB-A.130 Room Top Slab Rebar Installation 10 04-Mar-25 16-Mar-25 Room Top Slab Rebar Installation

UCR-13-SLB-A.135 Room Top Slab Concrete Casting 1 16-Mar-25 17-Mar-25 Room Top Slab Concrete Casting

UCR-13-SLB-A.140 Room Top slab Curing work 12 17-Mar-25 05-Apr-25 Room Top slab Curing work

UCR-13-SLB-A.145 Room Top Slab Formwork Removel 4 05-Apr-25 09-Apr-25 Room Top Slab Formwork Removel

WATER PROOFING 24 09-Apr-25 07-May-25 07-May-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 13 09-Apr-25 24-Apr-25 24-Apr-25, WALL WATER PROOFING STAGE-1
UCR-13-WP-WL-S1.115
Surface preparation work 3 09-Apr-25 13-Apr-25 Surface preparation work

UCR-13-WP-WL-S1.120
Applying of waterproofing material 8 13-Apr-25 22-Apr-25 Applying of waterproofing material

UCR-13-WP-WL-S1.125
UR Bck filling 2 22-Apr-25 24-Apr-25 UR Bck filling

TOP SLAB WATER PROOFING 24 09-Apr-25 07-May-25 07-May-25, TOP SLAB WATER PROOFING
U.C.R-13-SLB-S1.115Surface preparation work 12 09-Apr-25 23-Apr-25 Surface preparation work

U.C.R-13-SLB-S1.120Applying of waterproofing material 11 23-Apr-25 06-May-25 Applying of waterproofing material

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
119 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
U.C.R-13-SLB-S1.125Leak Test 1 06-May-25 07-May-25 Leak Test

MECHANICAL ROOM MEP (UCR) 466 28-Oct-23 08-May-25 08-May-25, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN TUNNEL 466 28-Oct-23 08-May-25 08-May-25, ELECTRICAL WORK IN TUNNEL
POWER SYSTEM 453 13-Nov-23 08-May-25 08-May-25, POWER SYSTEM
EARTHING SYSTEM 25 09-Apr-25 08-May-25 08-May-25, EARTHING SYSTEM
UCR-13-EES.105 Earthing system Termination 6 26-Apr-25 03-May-25 Earthing system Termination

UCR-13-EES.115 Earthing system Initial Testing 5 03-May-25 08-May-25 Earthing system Initial Testing

UCR-13-EES.125 Earthing system soil resistivity test 6 09-Apr-25 16-Apr-25 Earthing system soil resistivity test

UCR-13-EES.135 Earthing system Copper rod/ earthing pit installation 8 16-Apr-25 26-Apr-25 Earthing system Copper rod/ earthing pit installation

LIGHTING SYSTEM 37 29-Nov-23 11-Jan-24 11-Jan-24, LIGHTING SYSTEM


UCR-13-ELI.105 Lighting system Conduit and boxes Installation 8 29-Nov-23 09-Dec-23 Lighting system Conduit and boxes Installation

UCR-13-ELI.115 Lighting system Cable Pulling 8 09-Dec-23 18-Dec-23 Lighting system Cable Pulling

UCR-13-ELI.125 Lighting system Installations 8 18-Dec-23 27-Dec-23 Lighting system Installations

UCR-13-ELI.135 Lighting system Termination 8 27-Dec-23 06-Jan-24 Lighting system Termination

UCR-13-ELI.145 Lighting system Initial Testing 5 06-Jan-24 11-Jan-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 13-Nov-23 08-Jan-24 08-Jan-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-13-ECT.105 Cable Tray Installation 10 13-Nov-23 25-Nov-23 Cable Tray Installation

UCR-13-ECT.115 Cable Tray Inspection 10 25-Nov-23 06-Dec-23 Cable Tray Inspection

UCR-13-ECT.125 LV Cable pulling 10 06-Dec-23 18-Dec-23 LV Cable pulling

UCR-13-ECT.135 LV Cable Termination 10 18-Dec-23 30-Dec-23 LV Cable Termination

UCR-13-ECT.145 LV Cable Initial Testing 8 30-Dec-23 08-Jan-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 13-Feb-24 28-Mar-24 28-Mar-24, SMALL POWER SYSTEM


UCR-13-ESP.105 Small Power Conduit and boxes Installation 12 13-Feb-24 26-Feb-24 Small Power Conduit and boxes Installation

UCR-13-ESP.115 Small Power Cable Pulling 10 27-Feb-24 09-Mar-24 Small Power Cable Pulling

UCR-13-ESP.125 Small Power Installations 6 09-Mar-24 16-Mar-24 Small Power Installations

UCR-13-ESP.135 Small Power Termination 6 16-Mar-24 23-Mar-24 Small Power Termination

UCR-13-ESP.145 Small Power Initial Testing 5 23-Mar-24 28-Mar-24 Small Power Initial Testing

POWER DISTRIBUTION 40 01-Jan-24 17-Feb-24 17-Feb-24, POWER DISTRIBUTION


GENERATOR 39 01-Jan-24 15-Feb-24 15-Feb-24, GENERATOR
UCR-13-EPD.105 Generator Cable Tray Installation 7 01-Jan-24 09-Jan-24 Generator Cable Tray Installation

UCR-13-EPD.115 Generator Cable Pulling 7 09-Jan-24 17-Jan-24 Generator Cable Pulling

UCR-13-EPD.125 Generator Cell Pannel Installation 7 17-Jan-24 25-Jan-24 Generator Cell Pannel Installation

UCR-13-EPD.135 Generator Installation 7 25-Jan-24 01-Feb-24 Generator Installation

UCR-13-EPD.145 Generator Pannel / Cable Termination 7 03-Feb-24 10-Feb-24 Generator Pannel / Cable Termination

UCR-13-EPD.155 Generator Pannel / Cable initial Testing 5 10-Feb-24 15-Feb-24 Generator Pannel / Cable initial Testing

UPS 28 09-Jan-24 11-Feb-24 11-Feb-24, UPS


UCR-13-EPD.165 UPS Cable Tray Installation 5 09-Jan-24 15-Jan-24 UPS Cable Tray Installation

UCR-13-EPD.175 UPS Cable Pulling 5 15-Jan-24 21-Jan-24 UPS Cable Pulling

UCR-13-EPD.185 UPS Pannel Installation 5 21-Jan-24 25-Jan-24 UPS Pannel Installation

UCR-13-EPD.195 UPS Installation 5 27-Jan-24 31-Jan-24 UPS Installation

UCR-13-EPD.205 UPS Pannel / Cable Termination 5 31-Jan-24 06-Feb-24 UPS Pannel / Cable Termination

UCR-13-EPD.215 UPS Pannel / Cable initial Testing 4 06-Feb-24 11-Feb-24 UPS Pannel / Cable initial Testing

MDB 33 09-Jan-24 15-Feb-24 15-Feb-24, MDB


UCR-13-EPD.225 MDB Cable Tray Installation 7 09-Jan-24 17-Jan-24 MDB Cable Tray Installation

UCR-13-EPD.235 MDB Cable Pulling 7 17-Jan-24 25-Jan-24 MDB Cable Pulling

UCR-13-EPD.245 MDB Pannel Installation 7 25-Jan-24 01-Feb-24 MDB Pannel Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
120 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-13-EPD.255 MDB Pannel / Cable Termination 7 03-Feb-24 10-Feb-24 MDB Pannel / Cable Termination

UCR-13-EPD.265 MDB Pannel / Cable initial Testing 5 10-Feb-24 15-Feb-24 MDB Pannel / Cable initial Testing

MCC 33 09-Jan-24 15-Feb-24 15-Feb-24, MCC


UCR-13-EPD.325 MCC Cable Tray Installation 7 09-Jan-24 17-Jan-24 MCC Cable Tray Installation

UCR-13-EPD.335 MCC Cable Pulling 7 17-Jan-24 25-Jan-24 MCC Cable Pulling

UCR-13-EPD.345 MCC Pannel Installation 7 25-Jan-24 01-Feb-24 MCC Pannel Installation

UCR-13-EPD.355 MCC Pannel / Cable Termination 7 03-Feb-24 10-Feb-24 MCC Pannel / Cable Termination

UCR-13-EPD.365 MCC Pannel / Cable initial Testing 5 10-Feb-24 15-Feb-24 MCC Pannel / Cable initial Testing

SMSB 24 09-Jan-24 05-Feb-24 05-Feb-24, SMSB


UCR-13-EPD.275 SMSB Cable Tray Installation 5 09-Jan-24 15-Jan-24 SMSB Cable Tray Installation

UCR-13-EPD.285 SMSB Cable Pulling 5 15-Jan-24 21-Jan-24 SMSB Cable Pulling

UCR-13-EPD.295 SMSB Pannel Installation 5 21-Jan-24 25-Jan-24 SMSB Pannel Installation

UCR-13-EPD.305 SMSB Pannel / Cable Termination 5 27-Jan-24 31-Jan-24 SMSB Pannel / Cable Termination

UCR-13-EPD.315 SMSB Pannel / Cable initial Testing 4 31-Jan-24 05-Feb-24 SMSB Pannel / Cable initial Testing

DB 24 09-Jan-24 05-Feb-24 05-Feb-24, DB


UCR-13-EPD.375 DB Cable Tray Installation 5 09-Jan-24 15-Jan-24 DB Cable Tray Installation

UCR-13-EPD.385 DB Cable Pulling 5 15-Jan-24 21-Jan-24 DB Cable Pulling

UCR-13-EPD.395 DB Pannel Installation 5 21-Jan-24 25-Jan-24 DB Pannel Installation

UCR-13-EPD.405 DB Pannel / Cable Termination 5 27-Jan-24 31-Jan-24 DB Pannel / Cable Termination

UCR-13-EPD.415 DB Pannel / Cable initial Testing 4 31-Jan-24 05-Feb-24 DB Pannel / Cable initial Testing

ISOLATOR 24 15-Jan-24 11-Feb-24 11-Feb-24, ISOLATOR


UCR-13-EPD.425 Isolators Cable Tray Installation 5 15-Jan-24 21-Jan-24 Isolators Cable Tray Installation

UCR-13-EPD.435 Isolators Cable Pulling 5 21-Jan-24 25-Jan-24 Isolators Cable Pulling

UCR-13-EPD.445 Isolators Pannel Installation 5 27-Jan-24 31-Jan-24 Isolators Pannel Installation

UCR-13-EPD.455 Isolators Pannel / Cable Termination 5 31-Jan-24 06-Feb-24 Isolators Pannel / Cable Termination

UCR-13-EPD.465 Isolators Pannel / Cable initial Testing 4 06-Feb-24 11-Feb-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 21-Jan-24 17-Feb-24 17-Feb-24, LCP/ ELCP


UCR-13-EPD.475 LCP/ELCP Cable Tray Installation 5 21-Jan-24 25-Jan-24 LCP/ELCP Cable Tray Installation

UCR-13-EPD.485 LCP/ELCP Cable Pulling 5 27-Jan-24 31-Jan-24 LCP/ELCP Cable Pulling

UCR-13-EPD.495 LCP/ELCP Pannel Installation 5 31-Jan-24 06-Feb-24 LCP/ELCP Pannel Installation

UCR-13-EPD.505 LCP/ELCP Pannel / Cable Termination 5 06-Feb-24 12-Feb-24 LCP/ELCP Pannel / Cable Termination

UCR-13-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 12-Feb-24 17-Feb-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 125 28-Oct-23 21-Mar-24 21-Mar-24, LOW CURRENT SYSTEM
FIRE ALARM SYSTEM 42 28-Oct-23 16-Dec-23 16-Dec-23, FIRE ALARM SYSTEM
UCR-13-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 28-Oct-23 07-Nov-23 Fire Alarm Conduit /Cable Tray Installation

UCR-13-ELFA.115 Fire Alarm Cable Pulling 9 07-Nov-23 18-Nov-23 Fire Alarm Cable Pulling

UCR-13-ELFA.125 Fire Alarm Devices Installation 9 18-Nov-23 28-Nov-23 Fire Alarm Devices Installation

UCR-13-ELFA.135 Fire Alarm Devices and Cable Termination 9 28-Nov-23 09-Dec-23 Fire Alarm Devices and Cable Termination

UCR-13-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 09-Dec-23 16-Dec-23 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 16-Dec-23 01-Feb-24 01-Feb-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-13-ELVS.105 ICT System Conduit /Cable Tray Installation 9 16-Dec-23 26-Dec-23 ICT System Conduit /Cable Tray Installation

UCR-13-ELVS.115 ICT System Cable Pulling 9 26-Dec-23 06-Jan-24 ICT System Cable Pulling

UCR-13-ELVS.125 ICT System Devices Installation 9 06-Jan-24 16-Jan-24 ICT System Devices Installation

UCR-13-ELVS.135 ICT System Devices and Cable Termination 9 16-Jan-24 27-Jan-24 ICT System Devices and Cable Termination

UCR-13-ELVS.145 ICT System Devices and Cable initial Testing 6 27-Jan-24 01-Feb-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 01-Jan-24 18-Feb-24 18-Feb-24, ACCESS CONTROL SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
121 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-13-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 01-Jan-24 11-Jan-24 Access Control System Conduit /Cable Tray Installation

UCR-13-ELAC.115 Access Control System Cable Pulling 9 11-Jan-24 22-Jan-24 Access Control System Cable Pulling

UCR-13-ELAC.125 Access Control System Devices Installation 9 22-Jan-24 01-Feb-24 Access Control System Devices Installation

UCR-13-ELAC.135 Access Control System Devices and Cable Termination 9 01-Feb-24 11-Feb-24 Access Control System Devices and Cable Termination

UCR-13-ELAC.145 Access Control System Devices and Cable initial Testing 6 12-Feb-24 18-Feb-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 29-Nov-23 17-Jan-24 17-Jan-24, PUBLIC ADDRESS SYSTEM


UCR-13-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 29-Nov-23 10-Dec-23 Public Address System Conduit /Cable Tray Installation

UCR-13-ELPA.115 Public Address System Cable Pulling 9 10-Dec-23 20-Dec-23 Public Address System Cable Pulling

UCR-13-ELPA.125 Public Address System Devices Installation 9 20-Dec-23 31-Dec-23 Public Address System Devices Installation

UCR-13-ELPA.135 Public Address System Devices and Cable Termination 9 31-Dec-23 10-Jan-24 Public Address System Devices and Cable Termination

UCR-13-ELPA.145 Public Address System Devices and Cable initial Testing 6 10-Jan-24 17-Jan-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 03-Feb-24 21-Mar-24 21-Mar-24, SCADA SYSTEM


UCR-13-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 03-Feb-24 13-Feb-24 SCADA System Conduit /Cable Tray Installation

UCR-13-ELSC.115 SCADA System Cable Pulling 9 13-Feb-24 22-Feb-24 SCADA System Cable Pulling

UCR-13-ELSC.125 SCADA System Devices Installation 9 24-Feb-24 04-Mar-24 SCADA System Devices Installation

UCR-13-ELSC.135 SCADA System Devices and Cable Termination 9 04-Mar-24 14-Mar-24 SCADA System Devices and Cable Termination

UCR-13-ELSC.145 SCADA System Devices and Cable initial Testing 6 14-Mar-24 21-Mar-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 17-Jan-24 05-Mar-24 05-Mar-24, RADIO RE- BROADCOASTING/ TETRA
UCR-13-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 17-Jan-24 28-Jan-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-13-ELRD.115 Radio/TETRA System Cable Pulling 9 28-Jan-24 07-Feb-24 Radio/TETRA System Cable Pulling

UCR-13-ELRD.125 Radio/TETRA System Devices Installation 9 07-Feb-24 17-Feb-24 Radio/TETRA System Devices Installation

UCR-13-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 18-Feb-24 27-Feb-24 Radio/TETRA System Devices and Cable Termination

UCR-13-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 27-Feb-24 05-Mar-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN TUNNEL 31 28-Jan-24 04-Mar-24 04-Mar-24, MECHANICAL WORK IN TUNNEL


FIRE FIGHTING 13 28-Jan-24 12-Feb-24 12-Feb-24, FIRE FIGHTING
UCR-13-MFF.105 Fire Fighting system Pipe and accessories installation 11 28-Jan-24 10-Feb-24 Fire Fighting system Pipe and accessories installation

UCR-13-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 3 06-Feb-24 10-Feb-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-13-MFF.140 Fire Fighting system initial testing 2 10-Feb-24 12-Feb-24 Fire Fighting system initial testing

UCR-13-MFF.145 Fire Fighting clean agent system 2 07-Feb-24 10-Feb-24 Fire Fighting clean agent system

HVAC 20 10-Feb-24 04-Mar-24 04-Mar-24, HVAC


UCR-13-MHV.115 Air conditioning system installation 5 24-Feb-24 29-Feb-24 Air conditioning system installation

UCR-13-MHV.120 Fan installation 4 25-Feb-24 29-Feb-24 Fan installation

UCR-13-MHV.125 Duct and accessories installation 12 10-Feb-24 24-Feb-24 Duct and accessories installation

UCR-13-MHV.135 HVAC inital testing 3 29-Feb-24 04-Mar-24 HVAC inital testing

PLUMBING 4 24-Feb-24 28-Feb-24 28-Feb-24, PLUMBING


UCR-13-MPL.105 Plumbing drainage system installation 3 24-Feb-24 27-Feb-24 Plumbing drainage system installation

UCR-13-MPL.115 Plumbing drainage system initial testing 1 27-Feb-24 28-Feb-24 Plumbing drainage system initial testing

DRY UTILITIES 25 27-Feb-24 26-Mar-24 26-Mar-24, DRY UTILITIES


POWER 25 27-Feb-24 26-Mar-24 26-Mar-24, POWER
POWER LV 16 27-Feb-24 17-Mar-24 17-Mar-24, POWER LV
DU-P-LV.1300 Installation of support 1 27-Feb-24 27-Feb-24 Installation of support

DU-P-LV.1305 Installation of horizontal busbar 2 28-Feb-24 29-Feb-24 Installation of horizontal busbar

DU-P-LV.1310 Installation of vertical busbar 2 29-Feb-24 03-Mar-24 Installation of vertical busbar

DU-P-LV.1315 Installation of left/right elbow 2 03-Mar-24 04-Mar-24 Installation of left/right elbow

DU-P-LV.1320 Installation of right horizintal offset 2 04-Mar-24 06-Mar-24 Installation of right horizintal offset

DU-P-LV.1325 Instalaltion of upward vertical offset 3 06-Mar-24 10-Mar-24 Instalaltion of upward vertical offset

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
122 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-LV.1330 Installation of downward vertical offset 3 10-Mar-24 13-Mar-24 Installation of downward vertical offset

DU-P-LV.1335 Installation of transformer and panel connection 2 13-Mar-24 17-Mar-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 28-Feb-24 19-Mar-24 19-Mar-24, MEDIUM VOLTAGE


DU-P-MV.1300 Installation of cable try, arm, racks and ladder 6 28-Feb-24 06-Mar-24 Installation of cable try, arm, racks and ladder

DU-P-MV.1305 Installation of MV Cable 4 06-Mar-24 11-Mar-24 Installation of MV Cable

DU-P-MV.1310 Installation of cable cleats 2 11-Mar-24 12-Mar-24 Installation of cable cleats

DU-P-MV.1315 Installation of gland 1 13-Mar-24 13-Mar-24 Installation of gland

DU-P-MV.1320 splicing/termination of MV cable 2 13-Mar-24 16-Mar-24 splicing/termination of MV cable

DU-P-MV.1325 Testing and Pre-commissioning of cable 2 16-Mar-24 17-Mar-24 Testing and Pre-commissioning of cable

DU-P-MV.1330 Energezation 2 18-Mar-24 19-Mar-24 Energezation

TRANSFORMER 16 06-Mar-24 25-Mar-24 25-Mar-24, TRANSFORMER


DU-P-T.1300 Installation of Transformer unit 2 06-Mar-24 07-Mar-24 Installation of Transformer unit

DU-P-T.1305 Testing and Pre-Commissioning of unit 1 09-Mar-24 09-Mar-24 Testing and Pre-Commissioning of unit

DU-P-T.1310 Termination and Splicing of MV Cable 3 09-Mar-24 12-Mar-24 Termination and Splicing of MV Cable

DU-P-T.1315 Termination and Splicing of LV Cable/bus way 3 13-Mar-24 17-Mar-24 Termination and Splicing of LV Cable/bus way

DU-P-T.1320 Installation and connection of I/O system 2 17-Mar-24 19-Mar-24 Installation and connection of I/O system

DU-P-T.1325 Installation of Grounding and Protection System 2 19-Mar-24 21-Mar-24 Installation of Grounding and Protection System

DU-P-T.1330 Testing and Commissioning of MV System 1 23-Mar-24 23-Mar-24 Testing and Commissioning of MV System

DU-P-T.1335 Testing and Commissioning of LV System 1 23-Mar-24 24-Mar-24 Testing and Commissioning of LV System

DU-P-T.1340 Energezation 1 24-Mar-24 25-Mar-24 Energezation

RMU 16 09-Mar-24 26-Mar-24 26-Mar-24, RMU


DU-P-RMU.1300 Installation RMU unit 2 09-Mar-24 11-Mar-24 Installation RMU unit

DU-P-RMU.1305 Testing and Pre-Commissioning of unit 2 11-Mar-24 12-Mar-24 Testing and Pre-Commissioning of unit

DU-P-RMU.1310 Termination and Splicing of Ring-MV Cable 4 13-Mar-24 17-Mar-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.1315 Termination and Splicing of T-MV Cable 4 18-Mar-24 21-Mar-24 Termination and Splicing of T-MV Cable

DU-P-RMU.1320 Installation of Grounding and Protection System 2 23-Mar-24 25-Mar-24 Installation of Grounding and Protection System

DU-P-RMU.1325 Testing and Commissioning of MV System 1 25-Mar-24 26-Mar-24 Testing and Commissioning of MV System

DU-P-RMU.1330 Energezation 1 26-Mar-24 26-Mar-24 Energezation

UTILITY ROOM 14 (IN ZONE 04) ON BACKFILL (FLD +14 m) 466 24-May-23 02-Dec-24 02-Dec-24, UTILITY ROOM 14 (IN ZONE 04) ON BACKFILL (FLD +14 m)
ENGINEERING 325 24-May-23 13-Jun-24 13-Jun-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 325 24-May-23 13-Jun-24 13-Jun-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR14-SI.1040
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR14-SI.1045
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.14ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.14ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.14ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.14ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.14ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.14ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.14ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.14ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
123 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.14ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.14ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.14ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.14ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 325 24-May-23 13-Jun-24 13-Jun-24, ELECTRICAL


CABLE TRAYS 40 24-May-23 12-Jul-23 12-Jul-23, CABLE TRAYS
UCR.14ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

UCR.14ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


UCR.14ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

UCR.14ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 268 02-Aug-23 13-Jun-24 13-Jun-24, LIGHTING SYSTEM


UCR.14ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 02-Aug-23 17-Aug-23 Lighting System Shop Drawings Preparation & Submission

UCR.14ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 30-May-24 13-Jun-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 40 17-Aug-23 04-Oct-23 04-Oct-23, ELECTRICAL INSTALLATIONS


UCR.14ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 17-Aug-23 03-Sep-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.14ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 19-Sep-23 04-Oct-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 26 03-Sep-23 04-Oct-23 04-Oct-23, TRANSFORMERS INSTALLATION


UCR.14ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 03-Sep-23 19-Sep-23 Transformers Installation Shop Drawings Preparation & Submission

UCR.14ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 19-Sep-23 04-Oct-23 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 29-Apr-24 13-Jun-24 13-Jun-24, LIGHTNING PROTECTION SYSTEM


UCR.14ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 29-Apr-24 14-May-24 Lightning Protection Drawings Preparation & Submission

UCR.14ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 30-May-24 13-Jun-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 15-May-24 13-Jun-24 13-Jun-24, EARTHING SYSTEM


UCR.14ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 15-May-24 30-May-24 Earthing System Shop Drawings Preparation & Submission

UCR.14ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 30-May-24 13-Jun-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
UCR.14ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.14ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 54 08-Jun-23 14-Aug-23 14-Aug-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.14ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

UCR.14ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 40 25-Jun-23 14-Aug-23 14-Aug-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.14ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

UCR.14ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


UCR.14ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.14ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


UCR.14ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

UCR.14ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


UCR.14ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.14ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


UCR.14ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

UCR.14ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
124 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DRY UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY UTILITIES
POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.875
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.885
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


MEP-VR01-ENG-PWR.895
Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

MEP-VR01-ENG-PWR.905
Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


MEP-VR01-ENG-PWR.915
Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

MEP-VR01-ENG-PWR.925
Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


MEP-VR01-ENG-PWR.935
Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

MEP-VR01-ENG-PWR.945
Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 404 22-Jun-23 20-Oct-24 20-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 05-May-24 22-May-24 22-May-24, CIVIL/STRUCTURAL
UCR.14PRO-CV.110 Issue Purchase Order 6 05-May-24 11-May-24 Issue Purchase Order

UCR.14PRO-CV.115 Material Delivery 10 12-May-24 22-May-24 Material Delivery

MECHANICAL 133 25-Jun-23 02-Dec-23 02-Dec-23, MECHANICAL


FIRE FIGHTING SYSTEM 105 25-Jun-23 30-Oct-23 30-Oct-23, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 25-Jun-23 30-Oct-23 30-Oct-23, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.14PR-MC-FF.110Issue Purchase Order 15 25-Jun-23 16-Jul-23 Issue Purchase Order

UCR.14PR-MC-FF.115Material Delivery 90 16-Jul-23 30-Oct-23 Material Delivery

VENTILATION SYSTEM 105 15-Jul-23 15-Nov-23 15-Nov-23, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 15-Jul-23 15-Nov-23 15-Nov-23, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.14PR-MC-DS.110
Issue Purchase Order 15 15-Jul-23 01-Aug-23 Issue Purchase Order

UCR.14PR-MC-DS.115
Material Delivery 90 01-Aug-23 15-Nov-23 Material Delivery

AIR CONDITIONING WORKS 105 15-Jul-23 15-Nov-23 15-Nov-23, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 15-Jul-23 15-Nov-23 15-Nov-23, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.14PR-MC-AC.110
Issue Purchase Order 15 15-Jul-23 01-Aug-23 Issue Purchase Order

UCR.14PR-MC-AC.115
Material Delivery 90 01-Aug-23 15-Nov-23 Material Delivery

PLUMBING SYSTEM 105 31-Jul-23 02-Dec-23 02-Dec-23, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 31-Jul-23 02-Dec-23 02-Dec-23, PUMPS,PIPES,FITTINGS,VALVES
UCR.14PR-MC-PI.110Issue Purchase Order 15 31-Jul-23 17-Aug-23 Issue Purchase Order

UCR.14PR-MC-PI.115Material Delivery 90 17-Aug-23 02-Dec-23 Material Delivery

ELECTRICAL 404 22-Jun-23 20-Oct-24 20-Oct-24, ELECTRICAL


CABLE TRAY 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.14PR-EL-CT.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.14PR-EL-CT.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.14PR-EL-PC.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.14PR-EL-PC.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

LIGHTING SYSTEM 105 13-Jun-24 20-Oct-24 20-Oct-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 13-Jun-24 20-Oct-24 20-Oct-24, CONDUIT,LIGHT
UCR.14PR-EL-LS.110Issue Purchase Order 15 13-Jun-24 06-Jul-24 Issue Purchase Order

UCR.14PR-EL-LS.115Material Delivery 90 06-Jul-24 20-Oct-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 04-Oct-23 04-Feb-24 04-Feb-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 04-Oct-23 04-Feb-24 04-Feb-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.14PR-EL-EI.110 Issue Purchase Order 15 04-Oct-23 22-Oct-23 Issue Purchase Order

UCR.14PR-EL-EI.115 Material Delivery 90 22-Oct-23 04-Feb-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
125 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LIGHTNING PROTECTION SYSTEM 105 13-Jun-24 20-Oct-24 20-Oct-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 13-Jun-24 20-Oct-24 20-Oct-24, LIGHTNING PROTECTION SYSTEM
UCR.14PR-EL-LP.110Issue Purchase Order 15 13-Jun-24 06-Jul-24 Issue Purchase Order

UCR.14PR-EL-LP.115Material Delivery 90 06-Jul-24 20-Oct-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 13-Jun-24 20-Oct-24 20-Oct-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 13-Jun-24 20-Oct-24 20-Oct-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.14PR-EL-ES.110Issue Purchase Order 15 13-Jun-24 06-Jul-24 Issue Purchase Order

UCR.14PR-EL-ES.115Material Delivery 90 06-Jul-24 20-Oct-24 Material Delivery

LOW CURRENT 188 22-Jun-23 03-Feb-24 03-Feb-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.14PR-ELL-FA.20
Issue Purchase Order 15 22-Jun-23 13-Jul-23 Issue Purchase Order

UCR.14PR-ELL-FA.25
Material Delivery 90 13-Jul-23 28-Oct-23 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 14-Aug-23 16-Dec-23 16-Dec-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 14-Aug-23 16-Dec-23 16-Dec-23, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.14PR-ELL-PH.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.14PR-ELL-PH.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 14-Aug-23 16-Dec-23 16-Dec-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 14-Aug-23 16-Dec-23 16-Dec-23, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.14PR-ELL-PA.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.14PR-ELL-PA.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

VIDEO SURVEILLANCE 105 14-Aug-23 16-Dec-23 16-Dec-23, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 14-Aug-23 16-Dec-23 16-Dec-23, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.14PR-ELL-VS.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.14PR-ELL-VS.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

ACCESS CONTROL SYSTEM 105 30-Aug-23 01-Jan-24 01-Jan-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 30-Aug-23 01-Jan-24 01-Jan-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.14PR-ELL-AC.20
Issue Purchase Order 15 30-Aug-23 17-Sep-23 Issue Purchase Order

UCR.14PR-ELL-AC.25
Material Delivery 90 17-Sep-23 01-Jan-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 16-Sep-23 17-Jan-24 17-Jan-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 16-Sep-23 17-Jan-24 17-Jan-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.14PR-ELL-RB.20
Issue Purchase Order 15 16-Sep-23 04-Oct-23 Issue Purchase Order

UCR.14PR-ELL-RB.25
Material Delivery 90 04-Oct-23 17-Jan-24 Material Delivery

SCADA SYSTEM 105 03-Oct-23 03-Feb-24 03-Feb-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 03-Oct-23 03-Feb-24 03-Feb-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.14PR-ELL-SD.20
Issue Purchase Order 15 03-Oct-23 21-Oct-23 Issue Purchase Order

UCR.14PR-ELL-SD.25
Material Delivery 90 21-Oct-23 03-Feb-24 Material Delivery

CONSTRUCTION 336 28-Oct-23 02-Dec-24 02-Dec-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 02-May-24 22-May-24 22-May-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR14-SI.290Soil Improvement 18 02-May-24 22-May-24 Soil Improvement

STRUCTURAL WORKS 146 23-May-24 14-Nov-24 14-Nov-24, STRUCTURAL WORKS


FOUNDATION 21 23-May-24 20-Jun-24 20-Jun-24, FOUNDATION
Part-1 21 23-May-24 20-Jun-24 20-Jun-24, Part-1
UCR-14-FDN-P1.150 Foundation Blinding concrete casting 1 23-May-24 23-May-24 Foundation Blinding concrete casting

UCR-14-FDN-P1.155 Foundation water proofing on blinding concrete 2 25-May-24 26-May-24 Foundation water proofing on blinding concrete

UCR-14-FDN-P1.160 Foundation Protection screed on water poofing 1 26-May-24 27-May-24 Foundation Protection screed on water poofing

UCR-14-FDN-P1.170 Foundation Rebar installation 8 27-May-24 05-Jun-24 Foundation Rebar installation

UCR-14-FDN-P1.175 Foundation Formwork installation 4 05-Jun-24 10-Jun-24 Foundation Formwork installation

UCR-14-FDN-P1.180 Foundation Construction joint work 2 10-Jun-24 12-Jun-24 Foundation Construction joint work

UCR-14-FDN-P1.185 Foundation concrete casting 1 12-Jun-24 13-Jun-24 Foundation concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
126 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-14-FDN-P1.190 Foundation concrete curing 1 13-Jun-24 19-Jun-24 Foundation concrete curing

UCR-14-FDN-P1.195 Foundation Formwork Removal 1 19-Jun-24 20-Jun-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 25 20-Jun-24 20-Jul-24 20-Jul-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 25 20-Jun-24 20-Jul-24 20-Jul-24, WALL CONCRETE CASTING STAGE-1
Part-1 25 20-Jun-24 20-Jul-24 20-Jul-24, Part-1
UCR-14-S1-P1.135 Room Walls Rebar Installation 8 24-Jun-24 03-Jul-24 Room Walls Rebar Installation

UCR-14-S1-P1.140 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 03-Jul-24 06-Jul-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-14-S1-P1.145 Room Walls Formwork Installation 8 06-Jul-24 15-Jul-24 Room Walls Formwork Installation

UCR-14-S1-P1.150 Room Walls Concrete Casting 1 15-Jul-24 16-Jul-24 Room Walls Concrete Casting

UCR-14-S1-P1.155 Room Walls Curing work 1 16-Jul-24 17-Jul-24 Room Walls Curing work

UCR-14-S1-P1.160 Room Walls Formwork Removel 2 17-Jul-24 20-Jul-24 Room Walls Formwork Removel

UCR-14-S1-P1.165 Room Walls Scafolding for rebar 3 20-Jun-24 24-Jun-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 32 20-Jul-24 26-Aug-24 26-Aug-24, TOP SLAB BELOW GROUND LEVEL
Part-1 32 20-Jul-24 26-Aug-24 26-Aug-24, Part-1
UCR-14-TS-P1.125 Room Top Slab Formwork Installation 7 20-Jul-24 28-Jul-24 Room Top Slab Formwork Installation

UCR-14-TS-P1.130 Room Top Slab Rebar Installation 8 28-Jul-24 06-Aug-24 Room Top Slab Rebar Installation

UCR-14-TS-P1.135 Room Top Slab Concrete Casting 1 06-Aug-24 07-Aug-24 Room Top Slab Concrete Casting

UCR-14-TS-P1.140 Room Top slab Curing work 12 07-Aug-24 21-Aug-24 Room Top slab Curing work

UCR-14-TS-P1.145 Room Top Slab Formwork Removel 4 21-Aug-24 26-Aug-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 28 07-Aug-24 09-Sep-24 09-Sep-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 28 07-Aug-24 09-Sep-24 09-Sep-24, WALL CONCRETE CASTING STAGE-1
Part-1 28 07-Aug-24 09-Sep-24 09-Sep-24, Part-1
UCR-14-S1-A.135 Room Walls Rebar Installation 8 12-Aug-24 21-Aug-24 Room Walls Rebar Installation

UCR-14-S1-A.140 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Aug-24 24-Aug-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-14-S1-A.145 Room Walls Formwork Installation 9 24-Aug-24 03-Sep-24 Room Walls Formwork Installation

UCR-14-S1-A.150 Room Walls Concrete Casting 1 03-Sep-24 04-Sep-24 Room Walls Concrete Casting

UCR-14-S1-A.155 Room Walls Curing work 1 04-Sep-24 05-Sep-24 Room Walls Curing work

UCR-14-S1-A.160 Room Walls Formwork Removel 3 05-Sep-24 09-Sep-24 Room Walls Formwork Removel

UCR-14-S1-A.165 Room Walls Scafolding for rebar 4 07-Aug-24 12-Aug-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 34 09-Sep-24 20-Oct-24 20-Oct-24, SLAB ABOVE GROUND LEVEL
Part-1 34 09-Sep-24 20-Oct-24 20-Oct-24, Part-1
-1321-SLB-A.125 Room Top Slab Formwork Installation 9 09-Sep-24 19-Sep-24 Room Top Slab Formwork Installation

-1321-SLB-A.130 Room Top Slab Rebar Installation 8 19-Sep-24 30-Sep-24 Room Top Slab Rebar Installation

-1321-SLB-A.135 Room Top Slab Concrete Casting 1 30-Sep-24 01-Oct-24 Room Top Slab Concrete Casting

-1321-SLB-A.140 Room Top slab Curing work 12 01-Oct-24 15-Oct-24 Room Top slab Curing work

-1321-SLB-A.145 Room Top Slab Formwork Removel 4 15-Oct-24 20-Oct-24 Room Top Slab Formwork Removel

WATER PROOFING 38 01-Oct-24 14-Nov-24 14-Nov-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 16 01-Oct-24 20-Oct-24 20-Oct-24, WALL WATER PROOFING STAGE-1
UCR-14-WL-S1.115 Surface preparation work 6 01-Oct-24 08-Oct-24 Surface preparation work

UCR-14-WL-S1.120 Applying of waterproofing material 6 08-Oct-24 15-Oct-24 Applying of waterproofing material

UCR-14-WL-S1.125 UR Bck filling 4 15-Oct-24 20-Oct-24 UR Bck filling

TOP SLAB WATER PROOFING 22 20-Oct-24 14-Nov-24 14-Nov-24, TOP SLAB WATER PROOFING
UCR-14-13SLB-S1.115Surface preparation work 12 20-Oct-24 03-Nov-24 Surface preparation work

UCR-14-13SLB-S1.120Applying of waterproofing material 9 03-Nov-24 13-Nov-24 Applying of waterproofing material

UCR-14-13SLB-S1.125Leak Test 1 13-Nov-24 14-Nov-24 Leak Test

MECHANICAL ROOM MEP (UCR) 336 28-Oct-23 02-Dec-24 02-Dec-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 336 28-Oct-23 02-Dec-24 02-Dec-24, ELECTRICAL WORK IN UCR
POWER SYSTEM 322 13-Nov-23 02-Dec-24 02-Dec-24, POWER SYSTEM
LIGHTING SYSTEM 37 20-Oct-24 02-Dec-24 02-Dec-24, LIGHTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
127 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-14-ELI.105 Lighting system Conduit and boxes Installation 8 20-Oct-24 29-Oct-24 Lighting system Conduit and boxes Installation

UCR-14-ELI.115 Lighting system Cable Pulling 8 29-Oct-24 07-Nov-24 Lighting system Cable Pulling

UCR-14-ELI.125 Lighting system Installations 8 07-Nov-24 17-Nov-24 Lighting system Installations

UCR-14-ELI.135 Lighting system Termination 8 17-Nov-24 26-Nov-24 Lighting system Termination

UCR-14-ELI.145 Lighting system Initial Testing 5 26-Nov-24 02-Dec-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 13-Nov-23 08-Jan-24 08-Jan-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-14-ECT.105 Cable Tray Installation 10 13-Nov-23 25-Nov-23 Cable Tray Installation

UCR-14-ECT.115 Cable Tray Inspection 10 25-Nov-23 06-Dec-23 Cable Tray Inspection

UCR-14-ECT.125 LV Cable pulling 10 06-Dec-23 18-Dec-23 LV Cable pulling

UCR-14-ECT.135 LV Cable Termination 10 18-Dec-23 30-Dec-23 LV Cable Termination

UCR-14-ECT.145 LV Cable Initial Testing 8 30-Dec-23 08-Jan-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 13-Feb-24 28-Mar-24 28-Mar-24, SMALL POWER SYSTEM


UCR-14-ESP.105 Small Power Conduit and boxes Installation 12 13-Feb-24 26-Feb-24 Small Power Conduit and boxes Installation

UCR-14-ESP.115 Small Power Cable Pulling 10 27-Feb-24 09-Mar-24 Small Power Cable Pulling

UCR-14-ESP.125 Small Power Installations 6 09-Mar-24 16-Mar-24 Small Power Installations

UCR-14-ESP.135 Small Power Termination 6 16-Mar-24 23-Mar-24 Small Power Termination

UCR-14-ESP.145 Small Power Initial Testing 5 23-Mar-24 28-Mar-24 Small Power Initial Testing

POWER DISTRIBUTION 42 04-Feb-24 24-Mar-24 24-Mar-24, POWER DISTRIBUTION


GENERATOR 39 04-Feb-24 20-Mar-24 20-Mar-24, GENERATOR
UCR-14-EPD.105 Generator Cable Tray Installation 7 04-Feb-24 12-Feb-24 Generator Cable Tray Installation

UCR-14-EPD.115 Generator Cable Pulling 7 12-Feb-24 20-Feb-24 Generator Cable Pulling

UCR-14-EPD.125 Generator Cell Pannel Installation 7 20-Feb-24 28-Feb-24 Generator Cell Pannel Installation

UCR-14-EPD.135 Generator Installation 7 28-Feb-24 07-Mar-24 Generator Installation

UCR-14-EPD.145 Generator Pannel / Cable Termination 7 07-Mar-24 16-Mar-24 Generator Pannel / Cable Termination

UCR-14-EPD.155 Generator Pannel / Cable initial Testing 5 16-Mar-24 20-Mar-24 Generator Pannel / Cable initial Testing

UPS 28 12-Feb-24 16-Mar-24 16-Mar-24, UPS


UCR-14-EPD.165 UPS Cable Tray Installation 5 12-Feb-24 18-Feb-24 UPS Cable Tray Installation

UCR-14-EPD.175 UPS Cable Pulling 5 18-Feb-24 24-Feb-24 UPS Cable Pulling

UCR-14-EPD.185 UPS Pannel Installation 5 24-Feb-24 29-Feb-24 UPS Pannel Installation

UCR-14-EPD.195 UPS Installation 5 29-Feb-24 06-Mar-24 UPS Installation

UCR-14-EPD.205 UPS Pannel / Cable Termination 5 06-Mar-24 11-Mar-24 UPS Pannel / Cable Termination

UCR-14-EPD.215 UPS Pannel / Cable initial Testing 4 12-Mar-24 16-Mar-24 UPS Pannel / Cable initial Testing

MDB 33 12-Feb-24 20-Mar-24 20-Mar-24, MDB


UCR-14-EPD.225 MDB Cable Tray Installation 7 12-Feb-24 20-Feb-24 MDB Cable Tray Installation

UCR-14-EPD.235 MDB Cable Pulling 7 20-Feb-24 28-Feb-24 MDB Cable Pulling

UCR-14-EPD.245 MDB Pannel Installation 7 28-Feb-24 07-Mar-24 MDB Pannel Installation

UCR-14-EPD.255 MDB Pannel / Cable Termination 7 07-Mar-24 16-Mar-24 MDB Pannel / Cable Termination

UCR-14-EPD.265 MDB Pannel / Cable initial Testing 5 16-Mar-24 20-Mar-24 MDB Pannel / Cable initial Testing

MCC 33 12-Feb-24 20-Mar-24 20-Mar-24, MCC


UCR-14-EPD.325 MCC Cable Tray Installation 7 12-Feb-24 20-Feb-24 MCC Cable Tray Installation

UCR-14-EPD.335 MCC Cable Pulling 7 20-Feb-24 28-Feb-24 MCC Cable Pulling

UCR-14-EPD.345 MCC Pannel Installation 7 28-Feb-24 07-Mar-24 MCC Pannel Installation

UCR-14-EPD.355 MCC Pannel / Cable Termination 7 07-Mar-24 16-Mar-24 MCC Pannel / Cable Termination

UCR-14-EPD.365 MCC Pannel / Cable initial Testing 5 16-Mar-24 20-Mar-24 MCC Pannel / Cable initial Testing

SMSB 24 20-Feb-24 18-Mar-24 18-Mar-24, SMSB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
128 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-14-EPD.275 SMSB Cable Tray Installation 5 20-Feb-24 26-Feb-24 SMSB Cable Tray Installation

UCR-14-EPD.285 SMSB Cable Pulling 5 26-Feb-24 03-Mar-24 SMSB Cable Pulling

UCR-14-EPD.295 SMSB Pannel Installation 5 03-Mar-24 09-Mar-24 SMSB Pannel Installation

UCR-14-EPD.305 SMSB Pannel / Cable Termination 5 09-Mar-24 13-Mar-24 SMSB Pannel / Cable Termination

UCR-14-EPD.315 SMSB Pannel / Cable initial Testing 4 14-Mar-24 18-Mar-24 SMSB Pannel / Cable initial Testing

DB 24 20-Feb-24 18-Mar-24 18-Mar-24, DB


UCR-14-EPD.375 DB Cable Tray Installation 5 20-Feb-24 26-Feb-24 DB Cable Tray Installation

UCR-14-EPD.385 DB Cable Pulling 5 26-Feb-24 03-Mar-24 DB Cable Pulling

UCR-14-EPD.395 DB Pannel Installation 5 03-Mar-24 09-Mar-24 DB Pannel Installation

UCR-14-EPD.405 DB Pannel / Cable Termination 5 09-Mar-24 13-Mar-24 DB Pannel / Cable Termination

UCR-14-EPD.415 DB Pannel / Cable initial Testing 4 14-Mar-24 18-Mar-24 DB Pannel / Cable initial Testing

ISOLATOR 24 20-Feb-24 18-Mar-24 18-Mar-24, ISOLATOR


UCR-14-EPD.425 Isolators Cable Tray Installation 5 20-Feb-24 26-Feb-24 Isolators Cable Tray Installation

UCR-14-EPD.435 Isolators Cable Pulling 5 26-Feb-24 03-Mar-24 Isolators Cable Pulling

UCR-14-EPD.445 Isolators Pannel Installation 5 03-Mar-24 09-Mar-24 Isolators Pannel Installation

UCR-14-EPD.455 Isolators Pannel / Cable Termination 5 09-Mar-24 13-Mar-24 Isolators Pannel / Cable Termination

UCR-14-EPD.465 Isolators Pannel / Cable initial Testing 4 14-Mar-24 18-Mar-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 26-Feb-24 24-Mar-24 24-Mar-24, LCP/ ELCP


UCR-14-EPD.475 LCP/ELCP Cable Tray Installation 5 26-Feb-24 03-Mar-24 LCP/ELCP Cable Tray Installation

UCR-14-EPD.485 LCP/ELCP Cable Pulling 5 03-Mar-24 09-Mar-24 LCP/ELCP Cable Pulling

UCR-14-EPD.495 LCP/ELCP Pannel Installation 5 09-Mar-24 13-Mar-24 LCP/ELCP Pannel Installation

UCR-14-EPD.505 LCP/ELCP Pannel / Cable Termination 5 14-Mar-24 19-Mar-24 LCP/ELCP Pannel / Cable Termination

UCR-14-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 19-Mar-24 24-Mar-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 125 28-Oct-23 21-Mar-24 21-Mar-24, LOW CURRENT SYSTEM
FIRE ALARM SYSTEM 42 28-Oct-23 16-Dec-23 16-Dec-23, FIRE ALARM SYSTEM
UCR-14-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 28-Oct-23 07-Nov-23 Fire Alarm Conduit /Cable Tray Installation

UCR-14-ELFA.115 Fire Alarm Cable Pulling 9 07-Nov-23 18-Nov-23 Fire Alarm Cable Pulling

UCR-14-ELFA.125 Fire Alarm Devices Installation 9 18-Nov-23 28-Nov-23 Fire Alarm Devices Installation

UCR-14-ELFA.135 Fire Alarm Devices and Cable Termination 9 28-Nov-23 09-Dec-23 Fire Alarm Devices and Cable Termination

UCR-14-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 09-Dec-23 16-Dec-23 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 16-Dec-23 01-Feb-24 01-Feb-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-14-ELVS.105 ICT System Conduit /Cable Tray Installation 9 16-Dec-23 26-Dec-23 ICT System Conduit /Cable Tray Installation

UCR-14-ELVS.115 ICT System Cable Pulling 9 26-Dec-23 06-Jan-24 ICT System Cable Pulling

UCR-14-ELVS.125 ICT System Devices Installation 9 06-Jan-24 16-Jan-24 ICT System Devices Installation

UCR-14-ELVS.135 ICT System Devices and Cable Termination 9 16-Jan-24 27-Jan-24 ICT System Devices and Cable Termination

UCR-14-ELVS.145 ICT System Devices and Cable initial Testing 6 27-Jan-24 01-Feb-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 01-Jan-24 18-Feb-24 18-Feb-24, ACCESS CONTROL SYSTEM


UCR-14-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 01-Jan-24 11-Jan-24 Access Control System Conduit /Cable Tray Installation

UCR-14-ELAC.115 Access Control System Cable Pulling 9 11-Jan-24 22-Jan-24 Access Control System Cable Pulling

UCR-14-ELAC.125 Access Control System Devices Installation 9 22-Jan-24 01-Feb-24 Access Control System Devices Installation

UCR-14-ELAC.135 Access Control System Devices and Cable Termination 9 01-Feb-24 11-Feb-24 Access Control System Devices and Cable Termination

UCR-14-ELAC.145 Access Control System Devices and Cable initial Testing 6 12-Feb-24 18-Feb-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 07-Nov-23 26-Dec-23 26-Dec-23, PUBLIC ADDRESS SYSTEM


UCR-14-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 07-Nov-23 18-Nov-23 Public Address System Conduit /Cable Tray Installation

UCR-14-ELPA.115 Public Address System Cable Pulling 9 18-Nov-23 28-Nov-23 Public Address System Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
129 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-14-ELPA.125 Public Address System Devices Installation 9 28-Nov-23 09-Dec-23 Public Address System Devices Installation

UCR-14-ELPA.135 Public Address System Devices and Cable Termination 9 09-Dec-23 19-Dec-23 Public Address System Devices and Cable Termination

UCR-14-ELPA.145 Public Address System Devices and Cable initial Testing 6 19-Dec-23 26-Dec-23 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 03-Feb-24 21-Mar-24 21-Mar-24, SCADA SYSTEM


UCR-14-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 03-Feb-24 13-Feb-24 SCADA System Conduit /Cable Tray Installation

UCR-14-ELSC.115 SCADA System Cable Pulling 9 13-Feb-24 22-Feb-24 SCADA System Cable Pulling

UCR-14-ELSC.125 SCADA System Devices Installation 9 24-Feb-24 04-Mar-24 SCADA System Devices Installation

UCR-14-ELSC.135 SCADA System Devices and Cable Termination 9 04-Mar-24 14-Mar-24 SCADA System Devices and Cable Termination

UCR-14-ELSC.145 SCADA System Devices and Cable initial Testing 6 14-Mar-24 21-Mar-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 17-Jan-24 05-Mar-24 05-Mar-24, RADIO RE- BROADCOASTING/ TETRA
UCR-14-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 17-Jan-24 28-Jan-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-14-ELRD.115 Radio/TETRA System Cable Pulling 9 28-Jan-24 07-Feb-24 Radio/TETRA System Cable Pulling

UCR-14-ELRD.125 Radio/TETRA System Devices Installation 9 07-Feb-24 17-Feb-24 Radio/TETRA System Devices Installation

UCR-14-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 18-Feb-24 27-Feb-24 Radio/TETRA System Devices and Cable Termination

UCR-14-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 27-Feb-24 05-Mar-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 32 30-Oct-23 06-Dec-23 06-Dec-23, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 30-Oct-23 14-Nov-23 14-Nov-23, FIRE FIGHTING
UCR-14-MFF.105 Fire Fighting system Pipe and accessories installation 11 30-Oct-23 12-Nov-23 Fire Fighting system Pipe and accessories installation

UCR-14-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 08-Nov-23 12-Nov-23 Fire Fighting system fire hose cabinet/extingusher installation

UCR-14-MFF.135 Fire Fighting system initial testing 2 12-Nov-23 14-Nov-23 Fire Fighting system initial testing

HVAC 15 15-Nov-23 03-Dec-23 03-Dec-23, HVAC


UCR-14-MHV.105 Duct and accessories installation 12 15-Nov-23 29-Nov-23 Duct and accessories installation

UCR-14-MHV.115 Fan installation 4 25-Nov-23 29-Nov-23 Fan installation

UCR-14-MHV.135 HVAC inital testing 3 29-Nov-23 03-Dec-23 HVAC inital testing

PLUMBING 4 02-Dec-23 06-Dec-23 06-Dec-23, PLUMBING


UCR-14-MPL.105 Plumbing drainage system installation 3 02-Dec-23 05-Dec-23 Plumbing drainage system installation

UCR-14-MPL.115 Plumbing drainage system initial testing 1 05-Dec-23 06-Dec-23 Plumbing drainage system initial testing

DRY UTILITIES 66 05-Dec-23 20-Feb-24 20-Feb-24, DRY UTILITIES


POWER 66 05-Dec-23 20-Feb-24 20-Feb-24, POWER
POWER LV 16 05-Dec-23 24-Dec-23 24-Dec-23, POWER LV
DU-P-LV.1410 Installation of support 1 05-Dec-23 06-Dec-23 Installation of support

DU-P-LV.1415 Installation of horizontal busbar 2 06-Dec-23 07-Dec-23 Installation of horizontal busbar

DU-P-LV.1420 Installation of vertical busbar 2 09-Dec-23 10-Dec-23 Installation of vertical busbar

DU-P-LV.1425 Installation of left/right elbow 2 10-Dec-23 12-Dec-23 Installation of left/right elbow

DU-P-LV.1430 Installation of right horizintal offset 2 12-Dec-23 13-Dec-23 Installation of right horizintal offset

DU-P-LV.1435 Instalaltion of upward vertical offset 3 13-Dec-23 17-Dec-23 Instalaltion of upward vertical offset

DU-P-LV.1440 Installation of downward vertical offset 3 18-Dec-23 21-Dec-23 Installation of downward vertical offset

DU-P-LV.1445 Installation of transformer and panel connection 2 21-Dec-23 24-Dec-23 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 24-Dec-23 14-Jan-24 14-Jan-24, MEDIUM VOLTAGE


DU-P-MV.1410 Installation of cable try, arm, racks and ladder 6 24-Dec-23 31-Dec-23 Installation of cable try, arm, racks and ladder

DU-P-MV.1415 Installation of MV Cable 4 01-Jan-24 04-Jan-24 Installation of MV Cable

DU-P-MV.1420 Installation of cable cleats 2 06-Jan-24 07-Jan-24 Installation of cable cleats

DU-P-MV.1425 Installation of gland 1 07-Jan-24 08-Jan-24 Installation of gland

DU-P-MV.1430 splicing/termination of MV cable 2 08-Jan-24 09-Jan-24 splicing/termination of MV cable

DU-P-MV.1435 Testing and Pre-commissioning of cable 2 10-Jan-24 11-Jan-24 Testing and Pre-commissioning of cable

DU-P-MV.1440 Energezation 2 11-Jan-24 14-Jan-24 Energezation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
130 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TRANSFORMER 16 14-Jan-24 01-Feb-24 01-Feb-24, TRANSFORMER
DU-P-T.1410 Installation of Transformer unit 2 14-Jan-24 15-Jan-24 Installation of Transformer unit

DU-P-T.1415 Testing and Pre-Commissioning of unit 1 15-Jan-24 16-Jan-24 Testing and Pre-Commissioning of unit

DU-P-T.1420 Termination and Splicing of MV Cable 3 16-Jan-24 20-Jan-24 Termination and Splicing of MV Cable

DU-P-T.1425 Termination and Splicing of LV Cable/bus way 3 20-Jan-24 23-Jan-24 Termination and Splicing of LV Cable/bus way

DU-P-T.1430 Installation and connection of I/O system 2 24-Jan-24 27-Jan-24 Installation and connection of I/O system

DU-P-T.1435 Installation of Grounding and Protection System 2 27-Jan-24 29-Jan-24 Installation of Grounding and Protection System

DU-P-T.1440 Testing and Commissioning of MV System 1 29-Jan-24 30-Jan-24 Testing and Commissioning of MV System

DU-P-T.1445 Testing and Commissioning of LV System 1 30-Jan-24 31-Jan-24 Testing and Commissioning of LV System

DU-P-T.1450 Energezation 1 31-Jan-24 01-Feb-24 Energezation

RMU 16 01-Feb-24 20-Feb-24 20-Feb-24, RMU


DU-P-RMU.1410 Installation RMU unit 2 01-Feb-24 04-Feb-24 Installation RMU unit

DU-P-RMU.1415 Testing and Pre-Commissioning of unit 2 04-Feb-24 06-Feb-24 Testing and Pre-Commissioning of unit

DU-P-RMU.1420 Termination and Splicing of Ring-MV Cable 4 06-Feb-24 11-Feb-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.1425 Termination and Splicing of T-MV Cable 4 11-Feb-24 15-Feb-24 Termination and Splicing of T-MV Cable

DU-P-RMU.1430 Installation of Grounding and Protection System 2 15-Feb-24 18-Feb-24 Installation of Grounding and Protection System

DU-P-RMU.1435 Testing and Commissioning of MV System 1 18-Feb-24 19-Feb-24 Testing and Commissioning of MV System

DU-P-RMU.1440 Energezation 1 19-Feb-24 20-Feb-24 Energezation

UTILITY ROOM 11 (IN ZONE 05) ON BACKFILL (FLD +14.55 m) 534 24-May-23 19-Feb-25 19-Feb-25, UTILITY ROOM 11 (IN ZONE 05) ON BACKFILL (FLD +14.55 m)
ENGINEERING 393 24-May-23 05-Sep-24 05-Sep-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 393 24-May-23 05-Sep-24 05-Sep-24, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR11-SI.1050
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR11-SI.1055
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.11ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.11ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.11ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.11ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.11ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.11ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.11ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.11ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.11ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.11ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.11ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.11ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 393 24-May-23 05-Sep-24 05-Sep-24, ELECTRICAL


CABLE TRAYS 40 24-May-23 12-Jul-23 12-Jul-23, CABLE TRAYS
UCR.11ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

UCR.11ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


UCR.11ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
131 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.11ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 365 25-Jun-23 05-Sep-24 05-Sep-24, LIGHTING SYSTEM


UCR.11ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

UCR.11ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 22-Aug-24 05-Sep-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 40 15-Jul-23 30-Aug-23 30-Aug-23, ELECTRICAL INSTALLATIONS


UCR.11ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.11ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 26 31-Jul-23 30-Aug-23 30-Aug-23, TRANSFORMERS INSTALLATION


UCR.11ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Transformers Installation Shop Drawings Preparation & Submission

UCR.11ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 22-Jul-24 05-Sep-24 05-Sep-24, LIGHTNING PROTECTION SYSTEM


UCR.11ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 22-Jul-24 06-Aug-24 Lightning Protection Drawings Preparation & Submission

UCR.11ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 22-Aug-24 05-Sep-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 07-Aug-24 05-Sep-24 05-Sep-24, EARTHING SYSTEM


UCR.11ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 07-Aug-24 22-Aug-24 Earthing System Shop Drawings Preparation & Submission

UCR.11ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 22-Aug-24 05-Sep-24 Earthing System Drawings Review & Approval

LOW CURRENT 109 24-May-23 03-Oct-23 03-Oct-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
UCR.11ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.11ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 54 08-Jun-23 14-Aug-23 14-Aug-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.11ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

UCR.11ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.11ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

UCR.11ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


UCR.11ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.11ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


UCR.11ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

UCR.11ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


UCR.11ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.11ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 02-Sep-23 03-Oct-23 03-Oct-23, SCADA SYSTEM


UCR.11ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 SCADA system Shop Drawings Preparation & Submission

UCR.11ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 18-Sep-23 03-Oct-23 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.1500 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.1505 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

PROCUREMENT 472 22-Jun-23 07-Jan-25 07-Jan-25, PROCUREMENT


CIVIL/STRUCTURAL 16 10-Sep-24 29-Sep-24 29-Sep-24, CIVIL/STRUCTURAL
UCR.11PRO-CV.110 Issue Purchase Order 6 10-Sep-24 16-Sep-24 Issue Purchase Order

UCR.11PRO-CV.115 Material Delivery 10 17-Sep-24 29-Sep-24 Material Delivery

MECHANICAL 133 25-Jun-23 02-Dec-23 02-Dec-23, MECHANICAL


FIRE FIGHTING SYSTEM 105 25-Jun-23 30-Oct-23 30-Oct-23, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 25-Jun-23 30-Oct-23 30-Oct-23, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
132 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.11PR-MC-FF.110Issue Purchase Order 15 25-Jun-23 16-Jul-23 Issue Purchase Order

UCR.11PR-MC-FF.115Material Delivery 90 16-Jul-23 30-Oct-23 Material Delivery

VENTILATION SYSTEM 105 15-Jul-23 15-Nov-23 15-Nov-23, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 15-Jul-23 15-Nov-23 15-Nov-23, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.11PR-MC-DS.110
Issue Purchase Order 15 15-Jul-23 01-Aug-23 Issue Purchase Order

UCR.11PR-MC-DS.115
Material Delivery 90 01-Aug-23 15-Nov-23 Material Delivery

AIR CONDITIONING WORKS 105 15-Jul-23 15-Nov-23 15-Nov-23, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 15-Jul-23 15-Nov-23 15-Nov-23, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.11PR-MC-AC.110
Issue Purchase Order 15 15-Jul-23 01-Aug-23 Issue Purchase Order

UCR.11PR-MC-AC.115
Material Delivery 90 01-Aug-23 15-Nov-23 Material Delivery

PLUMBING SYSTEM 105 31-Jul-23 02-Dec-23 02-Dec-23, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 31-Jul-23 02-Dec-23 02-Dec-23, PUMPS,PIPES,FITTINGS,VALVES
UCR.11PR-MC-PI.110Issue Purchase Order 15 31-Jul-23 17-Aug-23 Issue Purchase Order

UCR.11PR-MC-PI.115Material Delivery 90 17-Aug-23 02-Dec-23 Material Delivery

ELECTRICAL 472 22-Jun-23 07-Jan-25 07-Jan-25, ELECTRICAL


CABLE TRAY 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 12-Jul-23 13-Nov-23 13-Nov-23, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.11PR-EL-CT.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.11PR-EL-CT.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 12-Jul-23 13-Nov-23 13-Nov-23, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.11PR-EL-PC.110Issue Purchase Order 15 12-Jul-23 30-Jul-23 Issue Purchase Order

UCR.11PR-EL-PC.115Material Delivery 90 30-Jul-23 13-Nov-23 Material Delivery

LIGHTING SYSTEM 105 05-Sep-24 07-Jan-25 07-Jan-25, LIGHTING SYSTEM


CONDUIT,LIGHT 105 05-Sep-24 07-Jan-25 07-Jan-25, CONDUIT,LIGHT
UCR.11PR-EL-LS.110Issue Purchase Order 15 05-Sep-24 24-Sep-24 Issue Purchase Order

UCR.11PR-EL-LS.115Material Delivery 90 24-Sep-24 07-Jan-25 Material Delivery

ELECTRICAL INSTALLATIONS 105 30-Aug-23 01-Jan-24 01-Jan-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 30-Aug-23 01-Jan-24 01-Jan-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.11PR-EL-EI.110 Issue Purchase Order 15 30-Aug-23 17-Sep-23 Issue Purchase Order

UCR.11PR-EL-EI.115 Material Delivery 90 17-Sep-23 01-Jan-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 05-Sep-24 07-Jan-25 07-Jan-25, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 05-Sep-24 07-Jan-25 07-Jan-25, LIGHTNING PROTECTION SYSTEM
UCR.11PR-EL-LP.110Issue Purchase Order 15 05-Sep-24 24-Sep-24 Issue Purchase Order

UCR.11PR-EL-LP.115Material Delivery 90 24-Sep-24 07-Jan-25 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 05-Sep-24 07-Jan-25 07-Jan-25, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 05-Sep-24 07-Jan-25 07-Jan-25, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.11PR-EL-ES.110Issue Purchase Order 15 05-Sep-24 24-Sep-24 Issue Purchase Order

UCR.11PR-EL-ES.115Material Delivery 90 24-Sep-24 07-Jan-25 Material Delivery

LOW CURRENT 188 22-Jun-23 03-Feb-24 03-Feb-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 22-Jun-23 28-Oct-23 28-Oct-23, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.11PR-ELL-FA.20
Issue Purchase Order 15 22-Jun-23 13-Jul-23 Issue Purchase Order

UCR.11PR-ELL-FA.25
Material Delivery 90 13-Jul-23 28-Oct-23 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 14-Aug-23 16-Dec-23 16-Dec-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 14-Aug-23 16-Dec-23 16-Dec-23, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.11PR-ELL-PH.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.11PR-ELL-PH.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 29-Jul-23 29-Nov-23 29-Nov-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 29-Jul-23 29-Nov-23 29-Nov-23, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.11PR-ELL-PA.20
Issue Purchase Order 15 29-Jul-23 15-Aug-23 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
133 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.11PR-ELL-PA.25
Material Delivery 90 15-Aug-23 29-Nov-23 Material Delivery

VIDEO SURVEILLANCE 105 14-Aug-23 16-Dec-23 16-Dec-23, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 14-Aug-23 16-Dec-23 16-Dec-23, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.11PR-ELL-VS.20
Issue Purchase Order 15 14-Aug-23 31-Aug-23 Issue Purchase Order

UCR.11PR-ELL-VS.25
Material Delivery 90 31-Aug-23 16-Dec-23 Material Delivery

ACCESS CONTROL SYSTEM 105 30-Aug-23 01-Jan-24 01-Jan-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 30-Aug-23 01-Jan-24 01-Jan-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.11PR-ELL-AC.20
Issue Purchase Order 15 30-Aug-23 17-Sep-23 Issue Purchase Order

UCR.11PR-ELL-AC.25
Material Delivery 90 17-Sep-23 01-Jan-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 16-Sep-23 17-Jan-24 17-Jan-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 16-Sep-23 17-Jan-24 17-Jan-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.11PR-ELL-RB.20
Issue Purchase Order 15 16-Sep-23 04-Oct-23 Issue Purchase Order

UCR.11PR-ELL-RB.25
Material Delivery 90 04-Oct-23 17-Jan-24 Material Delivery

SCADA SYSTEM 105 03-Oct-23 03-Feb-24 03-Feb-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 03-Oct-23 03-Feb-24 03-Feb-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.11PR-ELL-SD.20
Issue Purchase Order 15 03-Oct-23 21-Oct-23 Issue Purchase Order

UCR.11PR-ELL-SD.25
Material Delivery 90 21-Oct-23 03-Feb-24 Material Delivery

CONSTRUCTION 404 28-Oct-23 19-Feb-25 19-Feb-25, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 08-Sep-24 29-Sep-24 29-Sep-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR11-SI.295Soil Improvement 18 08-Sep-24 29-Sep-24 Soil Improvement

STRUCTURAL WORKS 94 30-Sep-24 16-Jan-25 16-Jan-25, STRUCTURAL WORKS


FOUNDATION 16 30-Sep-24 17-Oct-24 17-Oct-24, FOUNDATION
Part-1 16 30-Sep-24 17-Oct-24 17-Oct-24, Part-1
UCR-11-FDN-P1.150 Foundation Blinding concrete casting 1 30-Sep-24 30-Sep-24 Foundation Blinding concrete casting

UCR-11-FDN-P1.155 Foundation water proofing on blinding concrete 2 01-Oct-24 02-Oct-24 Foundation water proofing on blinding concrete

UCR-11-FDN-P1.160 Foundation Protection screed on water poofing 1 02-Oct-24 03-Oct-24 Foundation Protection screed on water poofing

UCR-11-FDN-P1.170 Foundation Rebar installation 4 03-Oct-24 08-Oct-24 Foundation Rebar installation

UCR-11-FDN-P1.175 Foundation Formwork installation 4 08-Oct-24 13-Oct-24 Foundation Formwork installation

UCR-11-FDN-P1.180 Foundation Construction joint work 1 13-Oct-24 14-Oct-24 Foundation Construction joint work

UCR-11-FDN-P1.185 Foundation concrete casting 1 14-Oct-24 15-Oct-24 Foundation concrete casting

UCR-11-FDN-P1.190 Foundation concrete curing 1 15-Oct-24 16-Oct-24 Foundation concrete curing

UCR-11-FDN-P1.195 Foundation Formwork Removal 1 16-Oct-24 17-Oct-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 18 17-Oct-24 07-Nov-24 07-Nov-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 18 17-Oct-24 07-Nov-24 07-Nov-24, WALL CONCRETE CASTING STAGE-1
Part-1 18 17-Oct-24 07-Nov-24 07-Nov-24, Part-1
UCR-11-WL-S1-P1.135
Room Walls Rebar Installation 5 21-Oct-24 27-Oct-24 Room Walls Rebar Installation

UCR-11-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 27-Oct-24 29-Oct-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-11-WL-S1-P1.145
Room Walls Formwork Installation 4 29-Oct-24 03-Nov-24 Room Walls Formwork Installation

UCR-11-WL-S1-P1.150
Room Walls Concrete Casting 1 03-Nov-24 04-Nov-24 Room Walls Concrete Casting

UCR-11-WL-S1-P1.155
Room Walls Curing work 1 04-Nov-24 05-Nov-24 Room Walls Curing work

UCR-11-WL-S1-P1.160
Room Walls Formwork Removel 2 05-Nov-24 07-Nov-24 Room Walls Formwork Removel

UCR-11-WL-S1-P1.165
Room Walls Scafolding for rebar 3 17-Oct-24 21-Oct-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 24 07-Nov-24 05-Dec-24 05-Dec-24, TOP SLAB BELOW GROUND LEVEL
Part-1 24 07-Nov-24 05-Dec-24 05-Dec-24, Part-1
UCR-11-TS-P1.125 Room Top Slab Formwork Installation 5 07-Nov-24 13-Nov-24 Room Top Slab Formwork Installation

UCR-11-TS-P1.130 Room Top Slab Rebar Installation 4 13-Nov-24 18-Nov-24 Room Top Slab Rebar Installation

UCR-11-TS-P1.135 Room Top Slab Concrete Casting 1 18-Nov-24 19-Nov-24 Room Top Slab Concrete Casting

UCR-11-TS-P1.140 Room Top slab Curing work 12 19-Nov-24 03-Dec-24 Room Top slab Curing work

UCR-11-TS-P1.145 Room Top Slab Formwork Removel 2 03-Dec-24 05-Dec-24 Room Top Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
134 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALLS ABOVE SLAB 17 19-Nov-24 09-Dec-24 09-Dec-24, WALLS ABOVE SLAB
WALL CONCRETE CASTING STAGE-1 17 19-Nov-24 09-Dec-24 09-Dec-24, WALL CONCRETE CASTING STAGE-1
Part-1 17 19-Nov-24 09-Dec-24 09-Dec-24, Part-1
UCR-11-WL-S1-A.135
Room Walls Rebar Installation 5 23-Nov-24 28-Nov-24 Room Walls Rebar Installation

UCR-11-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 28-Nov-24 01-Dec-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-11-WL-S1-A.145
Room Walls Formwork Installation 4 01-Dec-24 05-Dec-24 Room Walls Formwork Installation

UCR-11-WL-S1-A.150
Room Walls Concrete Casting 1 05-Dec-24 07-Dec-24 Room Walls Concrete Casting

UCR-11-WL-S1-A.155
Room Walls Curing work 1 07-Dec-24 08-Dec-24 Room Walls Curing work

UCR-11-WL-S1-A.160
Room Walls Formwork Removel 1 08-Dec-24 09-Dec-24 Room Walls Formwork Removel

UCR-11-WL-S1-A.165
Room Walls Scafolding for rebar 3 19-Nov-24 23-Nov-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 25 09-Dec-24 07-Jan-25 07-Jan-25, SLAB ABOVE GROUND LEVEL
Part-1 25 09-Dec-24 07-Jan-25 07-Jan-25, Part-1
UCR-11-SLB-A.125 Room Top Slab Formwork Installation 5 09-Dec-24 15-Dec-24 Room Top Slab Formwork Installation

UCR-11-SLB-A.130 Room Top Slab Rebar Installation 5 15-Dec-24 21-Dec-24 Room Top Slab Rebar Installation

UCR-11-SLB-A.135 Room Top Slab Concrete Casting 1 21-Dec-24 22-Dec-24 Room Top Slab Concrete Casting

UCR-11-SLB-A.140 Room Top slab Curing work 12 22-Dec-24 05-Jan-25 Room Top slab Curing work

UCR-11-SLB-A.145 Room Top Slab Formwork Removel 2 05-Jan-25 07-Jan-25 Room Top Slab Formwork Removel

WATER PROOFING 8 07-Jan-25 16-Jan-25 16-Jan-25, WATER PROOFING


WALL WATER PROOFING STAGE-1 8 07-Jan-25 16-Jan-25 16-Jan-25, WALL WATER PROOFING STAGE-1
UCR-11-WP-WL-S1.115
Surface preparation work 3 07-Jan-25 11-Jan-25 Surface preparation work

UCR-11-WP-WL-S1.120
Applying of waterproofing material 2 11-Jan-25 13-Jan-25 Applying of waterproofing material

UCR-11-WP-WL-S1.125
UR Bck filling 3 13-Jan-25 16-Jan-25 UR Bck filling

TOP SLAB WATER PROOFING 5 07-Jan-25 13-Jan-25 13-Jan-25, TOP SLAB WATER PROOFING
UCR-11-WP-SLB-S1.115
Surface preparation work 2 07-Jan-25 09-Jan-25 Surface preparation work

UCR-11-WP-SLB-S1.120
Applying of waterproofing material 2 09-Jan-25 12-Jan-25 Applying of waterproofing material

UCR-11-WP-SLB-S1.125
Leak Test 1 12-Jan-25 13-Jan-25 Leak Test

MECHANICAL ROOM MEP (UCR) 404 28-Oct-23 19-Feb-25 19-Feb-25, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 404 28-Oct-23 19-Feb-25 19-Feb-25, ELECTRICAL WORK IN UCR
POWER SYSTEM 390 13-Nov-23 19-Feb-25 19-Feb-25, POWER SYSTEM
LIGHTING SYSTEM 37 07-Jan-25 19-Feb-25 19-Feb-25, LIGHTING SYSTEM
UCR-11-ELI.105 Lighting system Conduit and boxes Installation 8 07-Jan-25 16-Jan-25 Lighting system Conduit and boxes Installation

UCR-11-ELI.115 Lighting system Cable Pulling 8 16-Jan-25 26-Jan-25 Lighting system Cable Pulling

UCR-11-ELI.125 Lighting system Installations 8 26-Jan-25 04-Feb-25 Lighting system Installations

UCR-11-ELI.135 Lighting system Termination 8 04-Feb-25 13-Feb-25 Lighting system Termination

UCR-11-ELI.145 Lighting system Initial Testing 5 13-Feb-25 19-Feb-25 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 13-Nov-23 08-Jan-24 08-Jan-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-11-ECT.105 Cable Tray Installation 10 13-Nov-23 25-Nov-23 Cable Tray Installation

UCR-11-ECT.115 Cable Tray Inspection 10 25-Nov-23 06-Dec-23 Cable Tray Inspection

UCR-11-ECT.125 LV Cable pulling 10 06-Dec-23 18-Dec-23 LV Cable pulling

UCR-11-ECT.135 LV Cable Termination 10 18-Dec-23 30-Dec-23 LV Cable Termination

UCR-11-ECT.145 LV Cable Initial Testing 8 30-Dec-23 08-Jan-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 13-Feb-24 28-Mar-24 28-Mar-24, SMALL POWER SYSTEM


UCR-11-ESP.105 Small Power Conduit and boxes Installation 12 13-Feb-24 26-Feb-24 Small Power Conduit and boxes Installation

UCR-11-ESP.115 Small Power Cable Pulling 10 27-Feb-24 09-Mar-24 Small Power Cable Pulling

UCR-11-ESP.125 Small Power Installations 6 09-Mar-24 16-Mar-24 Small Power Installations

UCR-11-ESP.135 Small Power Termination 6 16-Mar-24 23-Mar-24 Small Power Termination

UCR-11-ESP.145 Small Power Initial Testing 5 23-Mar-24 28-Mar-24 Small Power Initial Testing

POWER DISTRIBUTION 46 01-Jan-24 24-Feb-24 24-Feb-24, POWER DISTRIBUTION

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
135 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
GENERATOR 39 01-Jan-24 15-Feb-24 15-Feb-24, GENERATOR
UCR-11-EPD.105 Generator Cable Tray Installation 7 01-Jan-24 09-Jan-24 Generator Cable Tray Installation

UCR-11-EPD.115 Generator Cable Pulling 7 09-Jan-24 17-Jan-24 Generator Cable Pulling

UCR-11-EPD.125 Generator Cell Pannel Installation 7 17-Jan-24 25-Jan-24 Generator Cell Pannel Installation

UCR-11-EPD.135 Generator Installation 7 25-Jan-24 01-Feb-24 Generator Installation

UCR-11-EPD.145 Generator Pannel / Cable Termination 7 03-Feb-24 10-Feb-24 Generator Pannel / Cable Termination

UCR-11-EPD.155 Generator Pannel / Cable initial Testing 5 10-Feb-24 15-Feb-24 Generator Pannel / Cable initial Testing

UPS 28 09-Jan-24 11-Feb-24 11-Feb-24, UPS


UCR-11-EPD.165 UPS Cable Tray Installation 5 09-Jan-24 15-Jan-24 UPS Cable Tray Installation

UCR-11-EPD.175 UPS Cable Pulling 5 15-Jan-24 21-Jan-24 UPS Cable Pulling

UCR-11-EPD.185 UPS Pannel Installation 5 21-Jan-24 25-Jan-24 UPS Pannel Installation

UCR-11-EPD.195 UPS Installation 5 27-Jan-24 31-Jan-24 UPS Installation

UCR-11-EPD.205 UPS Pannel / Cable Termination 5 31-Jan-24 06-Feb-24 UPS Pannel / Cable Termination

UCR-11-EPD.215 UPS Pannel / Cable initial Testing 4 06-Feb-24 11-Feb-24 UPS Pannel / Cable initial Testing

MDB 33 09-Jan-24 15-Feb-24 15-Feb-24, MDB


UCR-11-EPD.225 MDB Cable Tray Installation 7 09-Jan-24 17-Jan-24 MDB Cable Tray Installation

UCR-11-EPD.235 MDB Cable Pulling 7 17-Jan-24 25-Jan-24 MDB Cable Pulling

UCR-11-EPD.245 MDB Pannel Installation 7 25-Jan-24 01-Feb-24 MDB Pannel Installation

UCR-11-EPD.255 MDB Pannel / Cable Termination 7 03-Feb-24 10-Feb-24 MDB Pannel / Cable Termination

UCR-11-EPD.265 MDB Pannel / Cable initial Testing 5 10-Feb-24 15-Feb-24 MDB Pannel / Cable initial Testing

MCC 33 17-Jan-24 24-Feb-24 24-Feb-24, MCC


UCR-11-EPD.325 MCC Cable Tray Installation 7 17-Jan-24 25-Jan-24 MCC Cable Tray Installation

UCR-11-EPD.335 MCC Cable Pulling 7 25-Jan-24 01-Feb-24 MCC Cable Pulling

UCR-11-EPD.345 MCC Pannel Installation 7 03-Feb-24 10-Feb-24 MCC Pannel Installation

UCR-11-EPD.355 MCC Pannel / Cable Termination 7 10-Feb-24 18-Feb-24 MCC Pannel / Cable Termination

UCR-11-EPD.365 MCC Pannel / Cable initial Testing 5 18-Feb-24 24-Feb-24 MCC Pannel / Cable initial Testing

SMSB 24 09-Jan-24 05-Feb-24 05-Feb-24, SMSB


UCR-11-EPD.275 SMSB Cable Tray Installation 5 09-Jan-24 15-Jan-24 SMSB Cable Tray Installation

UCR-11-EPD.285 SMSB Cable Pulling 5 15-Jan-24 21-Jan-24 SMSB Cable Pulling

UCR-11-EPD.295 SMSB Pannel Installation 5 21-Jan-24 25-Jan-24 SMSB Pannel Installation

UCR-11-EPD.305 SMSB Pannel / Cable Termination 5 27-Jan-24 31-Jan-24 SMSB Pannel / Cable Termination

UCR-11-EPD.315 SMSB Pannel / Cable initial Testing 4 31-Jan-24 05-Feb-24 SMSB Pannel / Cable initial Testing

DB 24 15-Jan-24 11-Feb-24 11-Feb-24, DB


UCR-11-EPD.375 DB Cable Tray Installation 5 15-Jan-24 21-Jan-24 DB Cable Tray Installation

UCR-11-EPD.385 DB Cable Pulling 5 21-Jan-24 25-Jan-24 DB Cable Pulling

UCR-11-EPD.395 DB Pannel Installation 5 27-Jan-24 31-Jan-24 DB Pannel Installation

UCR-11-EPD.405 DB Pannel / Cable Termination 5 31-Jan-24 06-Feb-24 DB Pannel / Cable Termination

UCR-11-EPD.415 DB Pannel / Cable initial Testing 4 06-Feb-24 11-Feb-24 DB Pannel / Cable initial Testing

ISOLATOR 24 15-Jan-24 11-Feb-24 11-Feb-24, ISOLATOR


UCR-11-EPD.425 Isolators Cable Tray Installation 5 15-Jan-24 21-Jan-24 Isolators Cable Tray Installation

UCR-11-EPD.435 Isolators Cable Pulling 5 21-Jan-24 25-Jan-24 Isolators Cable Pulling

UCR-11-EPD.445 Isolators Pannel Installation 5 27-Jan-24 31-Jan-24 Isolators Pannel Installation

UCR-11-EPD.455 Isolators Pannel / Cable Termination 5 31-Jan-24 06-Feb-24 Isolators Pannel / Cable Termination

UCR-11-EPD.465 Isolators Pannel / Cable initial Testing 4 06-Feb-24 11-Feb-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 21-Jan-24 17-Feb-24 17-Feb-24, LCP/ ELCP

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
136 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-11-EPD.475 LCP/ELCP Cable Tray Installation 5 21-Jan-24 25-Jan-24 LCP/ELCP Cable Tray Installation

UCR-11-EPD.485 LCP/ELCP Cable Pulling 5 27-Jan-24 31-Jan-24 LCP/ELCP Cable Pulling

UCR-11-EPD.495 LCP/ELCP Pannel Installation 5 31-Jan-24 06-Feb-24 LCP/ELCP Pannel Installation

UCR-11-EPD.505 LCP/ELCP Pannel / Cable Termination 5 06-Feb-24 12-Feb-24 LCP/ELCP Pannel / Cable Termination

UCR-11-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 12-Feb-24 17-Feb-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 125 28-Oct-23 21-Mar-24 21-Mar-24, LOW CURRENT SYSTEM
FIRE ALARM SYSTEM 42 28-Oct-23 16-Dec-23 16-Dec-23, FIRE ALARM SYSTEM
UCR-11-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 28-Oct-23 07-Nov-23 Fire Alarm Conduit /Cable Tray Installation

UCR-11-ELFA.115 Fire Alarm Cable Pulling 9 07-Nov-23 18-Nov-23 Fire Alarm Cable Pulling

UCR-11-ELFA.125 Fire Alarm Devices Installation 9 18-Nov-23 28-Nov-23 Fire Alarm Devices Installation

UCR-11-ELFA.135 Fire Alarm Devices and Cable Termination 9 28-Nov-23 09-Dec-23 Fire Alarm Devices and Cable Termination

UCR-11-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 09-Dec-23 16-Dec-23 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 16-Dec-23 01-Feb-24 01-Feb-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-11-ELVS.105 ICT System Conduit /Cable Tray Installation 9 16-Dec-23 26-Dec-23 ICT System Conduit /Cable Tray Installation

UCR-11-ELVS.115 ICT System Cable Pulling 9 26-Dec-23 06-Jan-24 ICT System Cable Pulling

UCR-11-ELVS.125 ICT System Devices Installation 9 06-Jan-24 16-Jan-24 ICT System Devices Installation

UCR-11-ELVS.135 ICT System Devices and Cable Termination 9 16-Jan-24 27-Jan-24 ICT System Devices and Cable Termination

UCR-11-ELVS.145 ICT System Devices and Cable initial Testing 6 27-Jan-24 01-Feb-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 01-Jan-24 18-Feb-24 18-Feb-24, ACCESS CONTROL SYSTEM


UCR-11-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 01-Jan-24 11-Jan-24 Access Control System Conduit /Cable Tray Installation

UCR-11-ELAC.115 Access Control System Cable Pulling 9 11-Jan-24 22-Jan-24 Access Control System Cable Pulling

UCR-11-ELAC.125 Access Control System Devices Installation 9 22-Jan-24 01-Feb-24 Access Control System Devices Installation

UCR-11-ELAC.135 Access Control System Devices and Cable Termination 9 01-Feb-24 11-Feb-24 Access Control System Devices and Cable Termination

UCR-11-ELAC.145 Access Control System Devices and Cable initial Testing 6 12-Feb-24 18-Feb-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 29-Nov-23 17-Jan-24 17-Jan-24, PUBLIC ADDRESS SYSTEM


UCR-11-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 29-Nov-23 10-Dec-23 Public Address System Conduit /Cable Tray Installation

UCR-11-ELPA.115 Public Address System Cable Pulling 9 10-Dec-23 20-Dec-23 Public Address System Cable Pulling

UCR-11-ELPA.125 Public Address System Devices Installation 9 20-Dec-23 31-Dec-23 Public Address System Devices Installation

UCR-11-ELPA.135 Public Address System Devices and Cable Termination 9 31-Dec-23 10-Jan-24 Public Address System Devices and Cable Termination

UCR-11-ELPA.145 Public Address System Devices and Cable initial Testing 6 10-Jan-24 17-Jan-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 03-Feb-24 21-Mar-24 21-Mar-24, SCADA SYSTEM


UCR-11-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 03-Feb-24 13-Feb-24 SCADA System Conduit /Cable Tray Installation

UCR-11-ELSC.115 SCADA System Cable Pulling 9 13-Feb-24 22-Feb-24 SCADA System Cable Pulling

UCR-11-ELSC.125 SCADA System Devices Installation 9 24-Feb-24 04-Mar-24 SCADA System Devices Installation

UCR-11-ELSC.135 SCADA System Devices and Cable Termination 9 04-Mar-24 14-Mar-24 SCADA System Devices and Cable Termination

UCR-11-ELSC.145 SCADA System Devices and Cable initial Testing 6 14-Mar-24 21-Mar-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 17-Jan-24 05-Mar-24 05-Mar-24, RADIO RE- BROADCOASTING/ TETRA
UCR-11-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 17-Jan-24 28-Jan-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-11-ELRD.115 Radio/TETRA System Cable Pulling 9 28-Jan-24 07-Feb-24 Radio/TETRA System Cable Pulling

UCR-11-ELRD.125 Radio/TETRA System Devices Installation 9 07-Feb-24 17-Feb-24 Radio/TETRA System Devices Installation

UCR-11-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 18-Feb-24 27-Feb-24 Radio/TETRA System Devices and Cable Termination

UCR-11-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 27-Feb-24 05-Mar-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 32 30-Oct-23 06-Dec-23 06-Dec-23, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 30-Oct-23 14-Nov-23 14-Nov-23, FIRE FIGHTING
UCR-11-MFF.105 Fire Fighting system Pipe and accessories installation 11 30-Oct-23 12-Nov-23 Fire Fighting system Pipe and accessories installation

UCR-11-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 08-Nov-23 12-Nov-23 Fire Fighting system fire hose cabinet/extingusher installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
137 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-11-MFF.135 Fire Fighting system initial testing 2 12-Nov-23 14-Nov-23 Fire Fighting system initial testing

HVAC 15 15-Nov-23 03-Dec-23 03-Dec-23, HVAC


UCR-11-MHV.105 Duct and accessories installation 12 15-Nov-23 29-Nov-23 Duct and accessories installation

UCR-11-MHV.115 Fan installation 4 25-Nov-23 29-Nov-23 Fan installation

UCR-11-MHV.135 HVAC inital testing 3 29-Nov-23 03-Dec-23 HVAC inital testing

PLUMBING 4 02-Dec-23 06-Dec-23 06-Dec-23, PLUMBING


UCR-11-MPL.105 Plumbing drainage system installation 3 02-Dec-23 05-Dec-23 Plumbing drainage system installation

UCR-11-MPL.115 Plumbing drainage system initial testing 1 05-Dec-23 06-Dec-23 Plumbing drainage system initial testing

DRY UTILITIES 16 05-Dec-23 24-Dec-23 24-Dec-23, DRY UTILITIES


POWER 16 05-Dec-23 24-Dec-23 24-Dec-23, POWER
POWER LV 16 05-Dec-23 24-Dec-23 24-Dec-23, POWER LV
DU-P-LV.1540 Installation of support 1 05-Dec-23 06-Dec-23 Installation of support

DU-P-LV.1545 Installation of horizontal busbar 2 06-Dec-23 07-Dec-23 Installation of horizontal busbar

DU-P-LV.1550 Installation of vertical busbar 2 09-Dec-23 10-Dec-23 Installation of vertical busbar

DU-P-LV.1555 Installation of left/right elbow 2 10-Dec-23 12-Dec-23 Installation of left/right elbow

DU-P-LV.1560 Installation of right horizintal offset 2 12-Dec-23 13-Dec-23 Installation of right horizintal offset

DU-P-LV.1565 Instalaltion of upward vertical offset 3 13-Dec-23 17-Dec-23 Instalaltion of upward vertical offset

DU-P-LV.1570 Installation of downward vertical offset 3 18-Dec-23 21-Dec-23 Installation of downward vertical offset

DU-P-LV.1575 Installation of transformer and panel connection 2 21-Dec-23 24-Dec-23 Installation of transformer and panel connection

UTILITY ROOM 12 (IN ZONE 05) ON BACKFILL (FLD +13.85m) 391 24-May-23 04-Sep-24 04-Sep-24, UTILITY ROOM 12 (IN ZONE 05) ON BACKFILL (FLD +13.85m)
ENGINEERING 253 24-May-23 18-Mar-24 18-Mar-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 253 24-May-23 18-Mar-24 18-Mar-24, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR12-SI.1060
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR12-SI.1065
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.12ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.12ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.12ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.12ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.12ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.12ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.12ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.12ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.12ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.12ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.12ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.12ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 126 23-Oct-23 18-Mar-24 18-Mar-24, ELECTRICAL


CABLE TRAYS 91 12-Nov-23 26-Feb-24 26-Feb-24, CABLE TRAYS
UCR.12ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 12-Nov-23 28-Nov-23 Cable Tray Shop Drawings Preparation & Submission

UCR.12ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 13-Feb-24 26-Feb-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 78 28-Nov-23 26-Feb-24 26-Feb-24, POWER CABLES


UCR.12ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 28-Nov-23 14-Dec-23 Power Cables Shop Drawings Preparation & Submission

UCR.12ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 13-Feb-24 26-Feb-24 Power Cables Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
138 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LIGHTING SYSTEM 74 14-Dec-23 09-Mar-24 09-Mar-24, LIGHTING SYSTEM
UCR.12ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 14-Dec-23 31-Dec-23 Lighting System Shop Drawings Preparation & Submission

UCR.12ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 60 31-Dec-23 09-Mar-24 09-Mar-24, ELECTRICAL INSTALLATIONS


UCR.12ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 31-Dec-23 16-Jan-24 Electrical Installations Shop Drawings Preparation & Submission

UCR.12ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 46 16-Jan-24 09-Mar-24 09-Mar-24, TRANSFORMERS INSTALLATION


UCR.12ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 16-Jan-24 31-Jan-24 Transformers Installation Shop Drawings Preparation & Submission

UCR.12ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 01-Feb-24 18-Mar-24 18-Mar-24, LIGHTNING PROTECTION SYSTEM


UCR.12ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 01-Feb-24 17-Feb-24 Lightning Protection Drawings Preparation & Submission

UCR.12ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 04-Mar-24 18-Mar-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 17-Feb-24 18-Mar-24 18-Mar-24, EARTHING SYSTEM


UCR.12ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 17-Feb-24 04-Mar-24 Earthing System Shop Drawings Preparation & Submission

UCR.12ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 04-Mar-24 18-Mar-24 Earthing System Drawings Review & Approval

LOW CURRENT 118 23-Oct-23 09-Mar-24 09-Mar-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 118 23-Oct-23 09-Mar-24 09-Mar-24, FIRE DETECTION AND ALARM SYSTEM
UCR.12ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 23-Oct-23 08-Nov-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.12ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 08-Nov-23 27-Feb-24 27-Feb-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.12ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Nov-23 25-Nov-23 Telephone Shop Drawings Preparation & Submission

UCR.12ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 14-Feb-24 27-Feb-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 90 25-Nov-23 09-Mar-24 09-Mar-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.12ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Nov-23 11-Dec-23 Public Address system Shop Drawings Preparation & Submission

UCR.12ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 11-Dec-23 27-Feb-24 27-Feb-24, VIDEO SURVEILLANCE


UCR.12ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 11-Dec-23 27-Dec-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.12ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 14-Feb-24 27-Feb-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 63 27-Dec-23 09-Mar-24 09-Mar-24, ACCESS CONTROL SYSTEM


UCR.12ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 27-Dec-23 13-Jan-24 Access Control system Shop Drawings Preparation & Submission

UCR.12ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 24-Feb-24 09-Mar-24 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 13-Jan-24 27-Feb-24 27-Feb-24, RADIO RE-BROADCASTING SYSTEM


UCR.12ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 13-Jan-24 29-Jan-24 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.12ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 14-Feb-24 27-Feb-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 29-Jan-24 27-Feb-24 27-Feb-24, SCADA SYSTEM


UCR.12ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 29-Jan-24 13-Feb-24 SCADA system Shop Drawings Preparation & Submission

UCR.12ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 14-Feb-24 27-Feb-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 31 24-May-23 03-Jul-23 03-Jul-23, DRY UTILITIES


POWER 31 24-May-23 03-Jul-23 03-Jul-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
MEP-VR01-ENG-PWR.955
Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

MEP-VR01-ENG-PWR.965
Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

PROCUREMENT 134 26-Feb-24 08-Aug-24 08-Aug-24, PROCUREMENT


CIVIL/STRUCTURAL 16 24-Mar-24 14-Apr-24 14-Apr-24, CIVIL/STRUCTURAL
UCR.12PRO-CV.110 Issue Purchase Order 6 24-Mar-24 30-Mar-24 Issue Purchase Order

UCR.12PRO-CV.115 Material Delivery 10 31-Mar-24 14-Apr-24 Material Delivery

MECHANICAL 117 17-Mar-24 08-Aug-24 08-Aug-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 17-Mar-24 25-Jul-24 25-Jul-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 17-Mar-24 25-Jul-24 25-Jul-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.12PR-MC-FF.110Issue Purchase Order 15 17-Mar-24 03-Apr-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
139 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.12PR-MC-FF.115Material Delivery 90 03-Apr-24 25-Jul-24 Material Delivery

VENTILATION SYSTEM 105 31-Mar-24 08-Aug-24 08-Aug-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 31-Mar-24 08-Aug-24 08-Aug-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.12PR-MC-DS.110
Issue Purchase Order 15 31-Mar-24 21-Apr-24 Issue Purchase Order

UCR.12PR-MC-DS.115
Material Delivery 90 21-Apr-24 08-Aug-24 Material Delivery

AIR CONDITIONING WORKS 105 31-Mar-24 08-Aug-24 08-Aug-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 31-Mar-24 08-Aug-24 08-Aug-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.12PR-MC-AC.110
Issue Purchase Order 15 31-Mar-24 21-Apr-24 Issue Purchase Order

UCR.12PR-MC-AC.115
Material Delivery 90 21-Apr-24 08-Aug-24 Material Delivery

PLUMBING SYSTEM 105 17-Mar-24 25-Jul-24 25-Jul-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 17-Mar-24 25-Jul-24 25-Jul-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.12PR-MC-PI.110Issue Purchase Order 15 17-Mar-24 03-Apr-24 Issue Purchase Order

UCR.12PR-MC-PI.115Material Delivery 90 03-Apr-24 25-Jul-24 Material Delivery

ELECTRICAL 123 26-Feb-24 27-Jul-24 27-Jul-24, ELECTRICAL


CABLE TRAY 105 26-Feb-24 06-Jul-24 06-Jul-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 26-Feb-24 06-Jul-24 06-Jul-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.12PR-EL-CT.110Issue Purchase Order 15 26-Feb-24 14-Mar-24 Issue Purchase Order

UCR.12PR-EL-CT.115Material Delivery 90 14-Mar-24 06-Jul-24 Material Delivery

POWER CABLES 105 26-Feb-24 06-Jul-24 06-Jul-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 26-Feb-24 06-Jul-24 06-Jul-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.12PR-EL-PC.110Issue Purchase Order 15 26-Feb-24 14-Mar-24 Issue Purchase Order

UCR.12PR-EL-PC.115Material Delivery 90 14-Mar-24 06-Jul-24 Material Delivery

LIGHTING SYSTEM 105 09-Mar-24 17-Jul-24 17-Jul-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 09-Mar-24 17-Jul-24 17-Jul-24, CONDUIT,LIGHT
UCR.12PR-EL-LS.110Issue Purchase Order 15 09-Mar-24 26-Mar-24 Issue Purchase Order

UCR.12PR-EL-LS.115Material Delivery 90 26-Mar-24 17-Jul-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 09-Mar-24 17-Jul-24 17-Jul-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 09-Mar-24 17-Jul-24 17-Jul-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.12PR-EL-EI.110 Issue Purchase Order 15 09-Mar-24 26-Mar-24 Issue Purchase Order

UCR.12PR-EL-EI.115 Material Delivery 90 26-Mar-24 17-Jul-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 18-Mar-24 27-Jul-24 27-Jul-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 18-Mar-24 27-Jul-24 27-Jul-24, LIGHTNING PROTECTION SYSTEM
UCR.12PR-EL-LP.110Issue Purchase Order 15 18-Mar-24 04-Apr-24 Issue Purchase Order

UCR.12PR-EL-LP.115Material Delivery 90 04-Apr-24 27-Jul-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 18-Mar-24 27-Jul-24 27-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 18-Mar-24 27-Jul-24 27-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.12PR-EL-ES.110Issue Purchase Order 15 18-Mar-24 04-Apr-24 Issue Purchase Order

UCR.12PR-EL-ES.115Material Delivery 90 04-Apr-24 27-Jul-24 Material Delivery

LOW CURRENT 114 27-Feb-24 17-Jul-24 17-Jul-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 09-Mar-24 17-Jul-24 17-Jul-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 09-Mar-24 17-Jul-24 17-Jul-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.12PR-ELL-FA.20
Issue Purchase Order 15 09-Mar-24 26-Mar-24 Issue Purchase Order

UCR.12PR-ELL-FA.25
Material Delivery 90 26-Mar-24 17-Jul-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 27-Feb-24 07-Jul-24 07-Jul-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 27-Feb-24 07-Jul-24 07-Jul-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.12PR-ELL-PH.20
Issue Purchase Order 15 27-Feb-24 16-Mar-24 Issue Purchase Order

UCR.12PR-ELL-PH.25
Material Delivery 90 16-Mar-24 07-Jul-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 09-Mar-24 17-Jul-24 17-Jul-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 09-Mar-24 17-Jul-24 17-Jul-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.12PR-ELL-PA.20
Issue Purchase Order 15 09-Mar-24 26-Mar-24 Issue Purchase Order

UCR.12PR-ELL-PA.25
Material Delivery 90 26-Mar-24 17-Jul-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
140 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
VIDEO SURVEILLANCE 105 27-Feb-24 07-Jul-24 07-Jul-24, VIDEO SURVEILLANCE
FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 27-Feb-24 07-Jul-24 07-Jul-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.12PR-ELL-VS.20
Issue Purchase Order 15 27-Feb-24 16-Mar-24 Issue Purchase Order

UCR.12PR-ELL-VS.25
Material Delivery 90 16-Mar-24 07-Jul-24 Material Delivery

ACCESS CONTROL SYSTEM 105 09-Mar-24 17-Jul-24 17-Jul-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 09-Mar-24 17-Jul-24 17-Jul-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.12PR-ELL-AC.20
Issue Purchase Order 15 09-Mar-24 26-Mar-24 Issue Purchase Order

UCR.12PR-ELL-AC.25
Material Delivery 90 26-Mar-24 17-Jul-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 27-Feb-24 07-Jul-24 07-Jul-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 27-Feb-24 07-Jul-24 07-Jul-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.12PR-ELL-RB.20
Issue Purchase Order 15 27-Feb-24 16-Mar-24 Issue Purchase Order

UCR.12PR-ELL-RB.25
Material Delivery 90 16-Mar-24 07-Jul-24 Material Delivery

SCADA SYSTEM 105 27-Feb-24 07-Jul-24 07-Jul-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 27-Feb-24 07-Jul-24 07-Jul-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.12PR-ELL-SD.20
Issue Purchase Order 15 27-Feb-24 16-Mar-24 Issue Purchase Order

UCR.12PR-ELL-SD.25
Material Delivery 90 16-Mar-24 07-Jul-24 Material Delivery

CONSTRUCTION 133 25-Mar-24 04-Sep-24 04-Sep-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 15 25-Mar-24 14-Apr-24 14-Apr-24, SOIL IMPROVEMENT WORKS
JAH-CON-UR12-SI.300Soil Improvement 15 25-Mar-24 14-Apr-24 Soil Improvement

STRUCTURAL WORKS 79 15-Apr-24 20-Jul-24 20-Jul-24, STRUCTURAL WORKS


FOUNDATION 13 15-Apr-24 29-Apr-24 29-Apr-24, FOUNDATION
Part-1 13 15-Apr-24 29-Apr-24 29-Apr-24, Part-1
UCR-12-FDN-P1.150 Foundation Blinding concrete casting 1 15-Apr-24 15-Apr-24 Foundation Blinding concrete casting

UCR-12-FDN-P1.155 Foundation water proofing on blinding concrete 1 16-Apr-24 16-Apr-24 Foundation water proofing on blinding concrete

UCR-12-FDN-P1.160 Foundation Protection screed on water poofing 1 17-Apr-24 17-Apr-24 Foundation Protection screed on water poofing

UCR-12-FDN-P1.170 Foundation Rebar installation 3 17-Apr-24 21-Apr-24 Foundation Rebar installation

UCR-12-FDN-P1.175 Foundation Formwork installation 3 21-Apr-24 24-Apr-24 Foundation Formwork installation

UCR-12-FDN-P1.180 Foundation Construction joint work 1 24-Apr-24 25-Apr-24 Foundation Construction joint work

UCR-12-FDN-P1.185 Foundation concrete casting 1 25-Apr-24 27-Apr-24 Foundation concrete casting

UCR-12-FDN-P1.190 Foundation concrete curing 1 27-Apr-24 28-Apr-24 Foundation concrete curing

UCR-12-FDN-P1.195 Foundation Formwork Removal 1 28-Apr-24 29-Apr-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 14 27-Apr-24 13-May-24 13-May-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 14 27-Apr-24 13-May-24 13-May-24, WALL CONCRETE CASTING STAGE-1
Part-1 14 27-Apr-24 13-May-24 13-May-24, Part-1
UCR-12-WL-S1-P1.135
Room Walls Rebar Installation 4 29-Apr-24 04-May-24 Room Walls Rebar Installation

UCR-12-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 0 04-May-24 04-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-12-WL-S1-P1.145
Room Walls Formwork Installation 5 04-May-24 09-May-24 Room Walls Formwork Installation

UCR-12-WL-S1-P1.150
Room Walls Concrete Casting 1 09-May-24 11-May-24 Room Walls Concrete Casting

UCR-12-WL-S1-P1.155
Room Walls Curing work 1 11-May-24 12-May-24 Room Walls Curing work

UCR-12-WL-S1-P1.160
Room Walls Formwork Removel 1 12-May-24 13-May-24 Room Walls Formwork Removel

UCR-12-WL-S1-P1.165
Room Walls Scafolding for rebar 2 27-Apr-24 29-Apr-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 23 13-May-24 09-Jun-24 09-Jun-24, TOP SLAB BELOW GROUND LEVEL
Part-1 23 13-May-24 09-Jun-24 09-Jun-24, Part-1
UCR-12-TS-P1.125 Room Top Slab Formwork Installation 5 13-May-24 19-May-24 Room Top Slab Formwork Installation

UCR-12-TS-P1.130 Room Top Slab Rebar Installation 3 19-May-24 22-May-24 Room Top Slab Rebar Installation

UCR-12-TS-P1.135 Room Top Slab Concrete Casting 1 22-May-24 23-May-24 Room Top Slab Concrete Casting

UCR-12-TS-P1.140 Room Top slab Curing work 12 23-May-24 06-Jun-24 Room Top slab Curing work

UCR-12-TS-P1.145 Room Top Slab Formwork Removel 2 06-Jun-24 09-Jun-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 17 23-May-24 12-Jun-24 12-Jun-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 17 23-May-24 12-Jun-24 12-Jun-24, WALL CONCRETE CASTING STAGE-1

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
141 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Part-1 17 23-May-24 12-Jun-24 12-Jun-24, Part-1
UCR-12-WL-S1-A.135
Room Walls Rebar Installation 4 27-May-24 01-Jun-24 Room Walls Rebar Installation

UCR-12-WL-S1-A.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 0 01-Jun-24 01-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-12-WL-S1-A.145
Room Walls Formwork Installation 4 01-Jun-24 05-Jun-24 Room Walls Formwork Installation

UCR-12-WL-S1-A.150
Room Walls Concrete Casting 1 05-Jun-24 06-Jun-24 Room Walls Concrete Casting

UCR-12-WL-S1-A.155
Room Walls Curing work 1 06-Jun-24 08-Jun-24 Room Walls Curing work

UCR-12-WL-S1-A.160
Room Walls Formwork Removel 3 09-Jun-24 12-Jun-24 Room Walls Formwork Removel

UCR-12-WL-S1-A.165
Room Walls Scafolding for rebar 3 23-May-24 27-May-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 20 12-Jun-24 10-Jul-24 10-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 20 12-Jun-24 10-Jul-24 10-Jul-24, Part-1
UCR-12-SLB-A.125 Room Top Slab Formwork Installation 3 12-Jun-24 20-Jun-24 Room Top Slab Formwork Installation

UCR-12-SLB-A.130 Room Top Slab Rebar Installation 3 20-Jun-24 24-Jun-24 Room Top Slab Rebar Installation

UCR-12-SLB-A.135 Room Top Slab Concrete Casting 1 24-Jun-24 25-Jun-24 Room Top Slab Concrete Casting

UCR-12-SLB-A.140 Room Top slab Curing work 12 25-Jun-24 09-Jul-24 Room Top slab Curing work

UCR-12-SLB-A.145 Room Top Slab Formwork Removel 1 09-Jul-24 10-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 8 10-Jul-24 20-Jul-24 20-Jul-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 7 10-Jul-24 18-Jul-24 18-Jul-24, WALL WATER PROOFING STAGE-1
UCR-12-WP-WL-S1.115
Surface preparation work 2 10-Jul-24 13-Jul-24 Surface preparation work

UCR-12-WP-WL-S1.120
Applying of waterproofing material 2 13-Jul-24 15-Jul-24 Applying of waterproofing material

UCR-12-WP-WL-S1.125
UR Bck filling 3 15-Jul-24 18-Jul-24 UR Bck filling

TOP SLAB WATER PROOFING 8 10-Jul-24 20-Jul-24 20-Jul-24, TOP SLAB WATER PROOFING
UCR-12-WP-SLB-S1.115
Surface preparation work 2 10-Jul-24 13-Jul-24 Surface preparation work

UCR-12-WP-SLB-S1.120
Applying of waterproofing material 2 13-Jul-24 15-Jul-24 Applying of waterproofing material

UCR-12-WP-SLB-S1.125
Leak Test 1 18-Jul-24 20-Jul-24 Leak Test

MECHANICAL ROOM MEP (UCR) 52 06-Jul-24 04-Sep-24 04-Sep-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN TUNNEL 52 06-Jul-24 04-Sep-24 04-Sep-24, ELECTRICAL WORK IN TUNNEL
POWER SYSTEM 49 06-Jul-24 02-Sep-24 02-Sep-24, POWER SYSTEM
EARTHING SYSTEM 25 10-Jul-24 08-Aug-24 08-Aug-24, EARTHING SYSTEM
UCR-12-EES.105 Earthing system Termination 6 27-Jul-24 03-Aug-24 Earthing system Termination

UCR-12-EES.115 Earthing system Initial Testing 5 03-Aug-24 08-Aug-24 Earthing system Initial Testing

UCR-12-EES.125 Earthing system soil resistivity test 6 10-Jul-24 17-Jul-24 Earthing system soil resistivity test

UCR-12-EES.135 Earthing system Copper rod/ earthing pit installation 8 17-Jul-24 27-Jul-24 Earthing system Copper rod/ earthing pit installation

LIGHTING SYSTEM 37 17-Jul-24 29-Aug-24 29-Aug-24, LIGHTING SYSTEM


UCR-12-ELI.105 Lighting system Conduit and boxes Installation 8 17-Jul-24 27-Jul-24 Lighting system Conduit and boxes Installation

UCR-12-ELI.115 Lighting system Cable Pulling 8 27-Jul-24 05-Aug-24 Lighting system Cable Pulling

UCR-12-ELI.125 Lighting system Installations 8 05-Aug-24 14-Aug-24 Lighting system Installations

UCR-12-ELI.135 Lighting system Termination 8 14-Aug-24 24-Aug-24 Lighting system Termination

UCR-12-ELI.145 Lighting system Initial Testing 5 24-Aug-24 29-Aug-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 06-Jul-24 31-Aug-24 31-Aug-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-12-ECT.105 Cable Tray Installation 10 06-Jul-24 17-Jul-24 Cable Tray Installation

UCR-12-ECT.115 Cable Tray Inspection 10 17-Jul-24 29-Jul-24 Cable Tray Inspection

UCR-12-ECT.125 LV Cable pulling 10 29-Jul-24 10-Aug-24 LV Cable pulling

UCR-12-ECT.135 LV Cable Termination 10 10-Aug-24 21-Aug-24 LV Cable Termination

UCR-12-ECT.145 LV Cable Initial Testing 8 21-Aug-24 31-Aug-24 LV Cable Initial Testing

SMALL POWER SYSTEM 37 06-Jul-24 18-Aug-24 18-Aug-24, SMALL POWER SYSTEM


UCR-12-ESP.105 Small Power Conduit and boxes Installation 10 06-Jul-24 17-Jul-24 Small Power Conduit and boxes Installation

UCR-12-ESP.115 Small Power Cable Pulling 10 17-Jul-24 29-Jul-24 Small Power Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
142 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-12-ESP.125 Small Power Installations 6 29-Jul-24 05-Aug-24 Small Power Installations

UCR-12-ESP.135 Small Power Termination 6 05-Aug-24 12-Aug-24 Small Power Termination

UCR-12-ESP.145 Small Power Initial Testing 5 12-Aug-24 18-Aug-24 Small Power Initial Testing

POWER DISTRIBUTION 39 17-Jul-24 02-Sep-24 02-Sep-24, POWER DISTRIBUTION


GENERATOR 39 17-Jul-24 02-Sep-24 02-Sep-24, GENERATOR
UCR-12-EPD.105 Generator Cable Tray Installation 7 17-Jul-24 25-Jul-24 Generator Cable Tray Installation

UCR-12-EPD.115 Generator Cable Pulling 7 25-Jul-24 03-Aug-24 Generator Cable Pulling

UCR-12-EPD.125 Generator Cell Pannel Installation 7 03-Aug-24 11-Aug-24 Generator Cell Pannel Installation

UCR-12-EPD.135 Generator Installation 7 11-Aug-24 19-Aug-24 Generator Installation

UCR-12-EPD.145 Generator Pannel / Cable Termination 7 19-Aug-24 27-Aug-24 Generator Pannel / Cable Termination

UCR-12-EPD.155 Generator Pannel / Cable initial Testing 5 27-Aug-24 02-Sep-24 Generator Pannel / Cable initial Testing

UPS 28 17-Jul-24 20-Aug-24 20-Aug-24, UPS


UCR-12-EPD.165 UPS Cable Tray Installation 5 17-Jul-24 23-Jul-24 UPS Cable Tray Installation

UCR-12-EPD.175 UPS Cable Pulling 5 23-Jul-24 29-Jul-24 UPS Cable Pulling

UCR-12-EPD.185 UPS Pannel Installation 5 29-Jul-24 04-Aug-24 UPS Pannel Installation

UCR-12-EPD.195 UPS Installation 5 04-Aug-24 10-Aug-24 UPS Installation

UCR-12-EPD.205 UPS Pannel / Cable Termination 5 10-Aug-24 15-Aug-24 UPS Pannel / Cable Termination

UCR-12-EPD.215 UPS Pannel / Cable initial Testing 4 15-Aug-24 20-Aug-24 UPS Pannel / Cable initial Testing

MDB 33 17-Jul-24 25-Aug-24 25-Aug-24, MDB


UCR-12-EPD.225 MDB Cable Tray Installation 7 17-Jul-24 25-Jul-24 MDB Cable Tray Installation

UCR-12-EPD.235 MDB Cable Pulling 7 25-Jul-24 03-Aug-24 MDB Cable Pulling

UCR-12-EPD.245 MDB Pannel Installation 7 03-Aug-24 11-Aug-24 MDB Pannel Installation

UCR-12-EPD.255 MDB Pannel / Cable Termination 7 11-Aug-24 19-Aug-24 MDB Pannel / Cable Termination

UCR-12-EPD.265 MDB Pannel / Cable initial Testing 5 19-Aug-24 25-Aug-24 MDB Pannel / Cable initial Testing

MCC 33 17-Jul-24 25-Aug-24 25-Aug-24, MCC


UCR-12-EPD.325 MCC Cable Tray Installation 7 17-Jul-24 25-Jul-24 MCC Cable Tray Installation

UCR-12-EPD.335 MCC Cable Pulling 7 25-Jul-24 03-Aug-24 MCC Cable Pulling

UCR-12-EPD.345 MCC Pannel Installation 7 03-Aug-24 11-Aug-24 MCC Pannel Installation

UCR-12-EPD.355 MCC Pannel / Cable Termination 7 11-Aug-24 19-Aug-24 MCC Pannel / Cable Termination

UCR-12-EPD.365 MCC Pannel / Cable initial Testing 5 19-Aug-24 25-Aug-24 MCC Pannel / Cable initial Testing

SMSB 24 17-Jul-24 14-Aug-24 14-Aug-24, SMSB


UCR-12-EPD.275 SMSB Cable Tray Installation 5 17-Jul-24 23-Jul-24 SMSB Cable Tray Installation

UCR-12-EPD.285 SMSB Cable Pulling 5 23-Jul-24 29-Jul-24 SMSB Cable Pulling

UCR-12-EPD.295 SMSB Pannel Installation 5 29-Jul-24 04-Aug-24 SMSB Pannel Installation

UCR-12-EPD.305 SMSB Pannel / Cable Termination 5 04-Aug-24 10-Aug-24 SMSB Pannel / Cable Termination

UCR-12-EPD.315 SMSB Pannel / Cable initial Testing 4 10-Aug-24 14-Aug-24 SMSB Pannel / Cable initial Testing

DB 24 17-Jul-24 14-Aug-24 14-Aug-24, DB


UCR-12-EPD.375 DB Cable Tray Installation 5 17-Jul-24 23-Jul-24 DB Cable Tray Installation

UCR-12-EPD.385 DB Cable Pulling 5 23-Jul-24 29-Jul-24 DB Cable Pulling

UCR-12-EPD.395 DB Pannel Installation 5 29-Jul-24 04-Aug-24 DB Pannel Installation

UCR-12-EPD.405 DB Pannel / Cable Termination 5 04-Aug-24 10-Aug-24 DB Pannel / Cable Termination

UCR-12-EPD.415 DB Pannel / Cable initial Testing 4 10-Aug-24 14-Aug-24 DB Pannel / Cable initial Testing

ISOLATOR 24 17-Jul-24 14-Aug-24 14-Aug-24, ISOLATOR


UCR-12-EPD.425 Isolators Cable Tray Installation 5 17-Jul-24 23-Jul-24 Isolators Cable Tray Installation

UCR-12-EPD.435 Isolators Cable Pulling 5 23-Jul-24 29-Jul-24 Isolators Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
143 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-12-EPD.445 Isolators Pannel Installation 5 29-Jul-24 04-Aug-24 Isolators Pannel Installation

UCR-12-EPD.455 Isolators Pannel / Cable Termination 5 04-Aug-24 10-Aug-24 Isolators Pannel / Cable Termination

UCR-12-EPD.465 Isolators Pannel / Cable initial Testing 4 10-Aug-24 14-Aug-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 17-Jul-24 14-Aug-24 14-Aug-24, LCP/ ELCP


UCR-12-EPD.475 LCP/ELCP Cable Tray Installation 5 17-Jul-24 23-Jul-24 LCP/ELCP Cable Tray Installation

UCR-12-EPD.485 LCP/ELCP Cable Pulling 5 23-Jul-24 29-Jul-24 LCP/ELCP Cable Pulling

UCR-12-EPD.495 LCP/ELCP Pannel Installation 5 29-Jul-24 04-Aug-24 LCP/ELCP Pannel Installation

UCR-12-EPD.505 LCP/ELCP Pannel / Cable Termination 5 04-Aug-24 10-Aug-24 LCP/ELCP Pannel / Cable Termination

UCR-12-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 10-Aug-24 14-Aug-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 07-Jul-24 04-Sep-24 04-Sep-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 17-Jul-24 04-Sep-24 04-Sep-24, FIRE ALARM SYSTEM
UCR-12-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 17-Jul-24 28-Jul-24 Fire Alarm Conduit /Cable Tray Installation

UCR-12-ELFA.115 Fire Alarm Cable Pulling 9 28-Jul-24 07-Aug-24 Fire Alarm Cable Pulling

UCR-12-ELFA.125 Fire Alarm Devices Installation 9 07-Aug-24 18-Aug-24 Fire Alarm Devices Installation

UCR-12-ELFA.135 Fire Alarm Devices and Cable Termination 9 18-Aug-24 28-Aug-24 Fire Alarm Devices and Cable Termination

UCR-12-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 07-Jul-24 25-Aug-24 25-Aug-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-12-ELVS.105 ICT System Conduit /Cable Tray Installation 9 07-Jul-24 17-Jul-24 ICT System Conduit /Cable Tray Installation

UCR-12-ELVS.115 ICT System Cable Pulling 9 17-Jul-24 28-Jul-24 ICT System Cable Pulling

UCR-12-ELVS.125 ICT System Devices Installation 9 28-Jul-24 07-Aug-24 ICT System Devices Installation

UCR-12-ELVS.135 ICT System Devices and Cable Termination 9 07-Aug-24 18-Aug-24 ICT System Devices and Cable Termination

UCR-12-ELVS.145 ICT System Devices and Cable initial Testing 6 18-Aug-24 25-Aug-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 17-Jul-24 04-Sep-24 04-Sep-24, ACCESS CONTROL SYSTEM


UCR-12-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 17-Jul-24 28-Jul-24 Access Control System Conduit /Cable Tray Installation

UCR-12-ELAC.115 Access Control System Cable Pulling 9 28-Jul-24 07-Aug-24 Access Control System Cable Pulling

UCR-12-ELAC.125 Access Control System Devices Installation 9 07-Aug-24 18-Aug-24 Access Control System Devices Installation

UCR-12-ELAC.135 Access Control System Devices and Cable Termination 9 18-Aug-24 28-Aug-24 Access Control System Devices and Cable Termination

UCR-12-ELAC.145 Access Control System Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 17-Jul-24 04-Sep-24 04-Sep-24, PUBLIC ADDRESS SYSTEM


UCR-12-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 17-Jul-24 28-Jul-24 Public Address System Conduit /Cable Tray Installation

UCR-12-ELPA.115 Public Address System Cable Pulling 9 28-Jul-24 07-Aug-24 Public Address System Cable Pulling

UCR-12-ELPA.125 Public Address System Devices Installation 9 07-Aug-24 18-Aug-24 Public Address System Devices Installation

UCR-12-ELPA.135 Public Address System Devices and Cable Termination 9 18-Aug-24 28-Aug-24 Public Address System Devices and Cable Termination

UCR-12-ELPA.145 Public Address System Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 07-Jul-24 25-Aug-24 25-Aug-24, SCADA SYSTEM


UCR-12-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 07-Jul-24 17-Jul-24 SCADA System Conduit /Cable Tray Installation

UCR-12-ELSC.115 SCADA System Cable Pulling 9 17-Jul-24 28-Jul-24 SCADA System Cable Pulling

UCR-12-ELSC.125 SCADA System Devices Installation 9 28-Jul-24 07-Aug-24 SCADA System Devices Installation

UCR-12-ELSC.135 SCADA System Devices and Cable Termination 9 07-Aug-24 18-Aug-24 SCADA System Devices and Cable Termination

UCR-12-ELSC.145 SCADA System Devices and Cable initial Testing 6 18-Aug-24 25-Aug-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 07-Jul-24 25-Aug-24 25-Aug-24, RADIO RE- BROADCOASTING/ TETRA
UCR-12-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 07-Jul-24 17-Jul-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-12-ELRD.115 Radio/TETRA System Cable Pulling 9 17-Jul-24 28-Jul-24 Radio/TETRA System Cable Pulling

UCR-12-ELRD.125 Radio/TETRA System Devices Installation 9 28-Jul-24 07-Aug-24 Radio/TETRA System Devices Installation

UCR-12-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 07-Aug-24 18-Aug-24 Radio/TETRA System Devices and Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
144 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-12-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 18-Aug-24 25-Aug-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN TUNNEL 20 25-Jul-24 18-Aug-24 18-Aug-24, MECHANICAL WORK IN TUNNEL


FIRE FIGHTING 13 25-Jul-24 10-Aug-24 10-Aug-24, FIRE FIGHTING
UCR-12-MFF.105 Fire Fighting system Pipe and accessories installation 11 25-Jul-24 07-Aug-24 Fire Fighting system Pipe and accessories installation

UCR-12-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 3 04-Aug-24 07-Aug-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-12-MFF.140 Fire Fighting system initial testing 2 07-Aug-24 10-Aug-24 Fire Fighting system initial testing

UCR-12-MFF.145 Fire Fighting clean agent system 2 05-Aug-24 07-Aug-24 Fire Fighting clean agent system

HVAC 20 25-Jul-24 18-Aug-24 18-Aug-24, HVAC


UCR-12-MHV.115 Air conditioning system installation 5 08-Aug-24 14-Aug-24 Air conditioning system installation

UCR-12-MHV.120 Fan installation 4 10-Aug-24 14-Aug-24 Fan installation

UCR-12-MHV.125 Duct and accessories installation 12 25-Jul-24 08-Aug-24 Duct and accessories installation

UCR-12-MHV.135 HVAC inital testing 3 14-Aug-24 18-Aug-24 HVAC inital testing

PLUMBING 4 25-Jul-24 30-Jul-24 30-Jul-24, PLUMBING


UCR-12-MPL.105 Plumbing drainage system installation 3 25-Jul-24 29-Jul-24 Plumbing drainage system installation

UCR-12-MPL.115 Plumbing drainage system initial testing 1 29-Jul-24 30-Jul-24 Plumbing drainage system initial testing

DRY UTILITIES 16 25-Jul-24 13-Aug-24 13-Aug-24, DRY UTILITIES


POWER 16 25-Jul-24 13-Aug-24 13-Aug-24, POWER
POWER LV 16 25-Jul-24 13-Aug-24 13-Aug-24, POWER LV
DU-P-LV.1610 Installation of support 1 25-Jul-24 27-Jul-24 Installation of support

DU-P-LV.1615 Installation of horizontal busbar 2 27-Jul-24 29-Jul-24 Installation of horizontal busbar

DU-P-LV.1620 Installation of vertical busbar 2 29-Jul-24 30-Jul-24 Installation of vertical busbar

DU-P-LV.1625 Installation of left/right elbow 2 30-Jul-24 01-Aug-24 Installation of left/right elbow

DU-P-LV.1630 Installation of right horizintal offset 2 01-Aug-24 03-Aug-24 Installation of right horizintal offset

DU-P-LV.1635 Instalaltion of upward vertical offset 3 03-Aug-24 07-Aug-24 Instalaltion of upward vertical offset

DU-P-LV.1640 Installation of downward vertical offset 3 07-Aug-24 11-Aug-24 Installation of downward vertical offset

DU-P-LV.1645 Installation of transformer and panel connection 2 11-Aug-24 13-Aug-24 Installation of transformer and panel connection

UTILITY ROOM 5 (IN ZONE 06) ON BACKFILL (FLD +13 m) 337 24-May-23 02-Jul-24 02-Jul-24, UTILITY ROOM 5 (IN ZONE 06) ON BACKFILL (FLD +13 m)
ENGINEERING 296 24-May-23 12-May-24 12-May-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 296 24-May-23 12-May-24 12-May-24, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
JAH-ENG-UR05-SI.1150
Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

JAH-ENG-UR05-SI.1155
Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.5-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.5-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.5-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.5-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.5-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.5-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.5-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.5-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.5-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.5-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.5-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
145 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.5-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 232 10-Aug-23 12-May-24 12-May-24, ELECTRICAL


CABLE TRAYS 115 16-Aug-23 30-Dec-23 30-Dec-23, CABLE TRAYS
UCR.5-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Cable Tray Shop Drawings Preparation & Submission

UCR.5-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 16-Dec-23 30-Dec-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 101 02-Sep-23 30-Dec-23 30-Dec-23, POWER CABLES


UCR.5-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 02-Sep-23 18-Sep-23 Power Cables Shop Drawings Preparation & Submission

UCR.5-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 16-Dec-23 30-Dec-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 87 18-Sep-23 30-Dec-23 30-Dec-23, LIGHTING SYSTEM


UCR.5-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 18-Sep-23 05-Oct-23 Lighting System Shop Drawings Preparation & Submission

UCR.5-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 16-Dec-23 30-Dec-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 73 05-Oct-23 30-Dec-23 30-Dec-23, ELECTRICAL INSTALLATIONS


UCR.5-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 05-Oct-23 21-Oct-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.5-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 16-Dec-23 30-Dec-23 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 171 22-Oct-23 12-May-24 12-May-24, TRANSFORMERS INSTALLATION


UCR.5-ENG-EL-TI.110Transformers Installation Shop Drawings Preparation & Submission 14 22-Oct-23 06-Nov-23 Transformers Installation Shop Drawings Preparation & Submission

UCR.5-ENG-EL-TI.115Transformers Installation Shop Drawings Review & Approval 12 28-Apr-24 12-May-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 06-Nov-23 23-Dec-23 23-Dec-23, LIGHTNING PROTECTION SYSTEM


UCR.5-ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 06-Nov-23 22-Nov-23 Lightning Protection Drawings Preparation & Submission

UCR.5-ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 09-Dec-23 23-Dec-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 22-Nov-23 23-Dec-23 23-Dec-23, EARTHING SYSTEM


UCR.5-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 22-Nov-23 09-Dec-23 Earthing System Shop Drawings Preparation & Submission

UCR.5-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 09-Dec-23 23-Dec-23 Earthing System Drawings Review & Approval

LOW CURRENT 118 10-Aug-23 27-Dec-23 27-Dec-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 109 10-Aug-23 17-Dec-23 17-Dec-23, FIRE DETECTION AND ALARM SYSTEM
UCR.5-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 10-Aug-23 27-Aug-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 27-Aug-23 17-Dec-23 17-Dec-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.5-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 27-Aug-23 12-Sep-23 Telephone Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 90 12-Sep-23 27-Dec-23 27-Dec-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.5-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 12-Sep-23 30-Sep-23 Public Address system Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 13-Dec-23 27-Dec-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 30-Sep-23 17-Dec-23 17-Dec-23, VIDEO SURVEILLANCE


UCR.5-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 30-Sep-23 16-Oct-23 Video Surveillance system Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 54 16-Oct-23 17-Dec-23 17-Dec-23, ACCESS CONTROL SYSTEM


UCR.5-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 16-Oct-23 31-Oct-23 Access Control system Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 01-Nov-23 17-Dec-23 17-Dec-23, RADIO RE-BROADCASTING SYSTEM


UCR.5-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 01-Nov-23 16-Nov-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 16-Nov-23 17-Dec-23 17-Dec-23, SCADA SYSTEM


UCR.5-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 16-Nov-23 03-Dec-23 SCADA system Shop Drawings Preparation & Submission

UCR.5-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 03-Dec-23 17-Dec-23 SCADA system Shop Drawings Review & Approval

DRU UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRU UTILITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.2500 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
146 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-LV.2505 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.2500 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

DU-P-MV.2505 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.2500 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.2505 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.2500 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.2505 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 155 23-Nov-23 26-May-24 26-May-24, PROCUREMENT


CIVIL/STRUCTURAL 16 23-Nov-23 11-Dec-23 11-Dec-23, CIVIL/STRUCTURAL
UCR.5RO-CVL.110 Issue Purchase Order 6 23-Nov-23 29-Nov-23 Issue Purchase Order

UCR.5RO-CVL.115 Material Delivery 10 30-Nov-23 11-Dec-23 Material Delivery

MECHANICAL 117 07-Jan-24 26-May-24 26-May-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 07-Jan-24 12-May-24 12-May-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 07-Jan-24 12-May-24 12-May-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.5RO-MC-FT.110Issue Purchase Order 15 07-Jan-24 24-Jan-24 Issue Purchase Order

UCR.5RO-MC-FT.115Material Delivery 90 24-Jan-24 12-May-24 Material Delivery

VENTILATION SYSTEM 105 21-Jan-24 26-May-24 26-May-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 21-Jan-24 26-May-24 26-May-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.5RO-MC-DCT.110
Issue Purchase Order 15 21-Jan-24 07-Feb-24 Issue Purchase Order

UCR.5RO-MC-DCT.115
Material Delivery 90 07-Feb-24 26-May-24 Material Delivery

AIR CONDITIONING WORKS 105 21-Jan-24 26-May-24 26-May-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 21-Jan-24 26-May-24 26-May-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.5RO-MC-SPU.110
Issue Purchase Order 15 21-Jan-24 07-Feb-24 Issue Purchase Order

UCR.5RO-MC-SPU.115
Material Delivery 90 07-Feb-24 26-May-24 Material Delivery

PLUMBING SYSTEM 105 07-Jan-24 12-May-24 12-May-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 07-Jan-24 12-May-24 12-May-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.5RO-MC-PMI.110
Issue Purchase Order 15 07-Jan-24 24-Jan-24 Issue Purchase Order

UCR.5RO-MC-PMI.115
Material Delivery 90 24-Jan-24 12-May-24 Material Delivery

ELECTRICAL 116 17-Dec-23 04-May-24 04-May-24, ELECTRICAL


CABLE TRAY 105 30-Dec-23 04-May-24 04-May-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 30-Dec-23 04-May-24 04-May-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.5RO-EL-CTRY.130
Issue Purchase Order 15 30-Dec-23 16-Jan-24 Issue Purchase Order

UCR.5RO-EL-CTRY.135
Material Delivery 90 16-Jan-24 04-May-24 Material Delivery

POWER CABLES 105 30-Dec-23 04-May-24 04-May-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 30-Dec-23 04-May-24 04-May-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.5RO-EL-PWCL.140
Issue Purchase Order 15 30-Dec-23 16-Jan-24 Issue Purchase Order

UCR.5RO-EL-PWCL.145
Material Delivery 90 16-Jan-24 04-May-24 Material Delivery

LIGHTING SYSTEM 105 30-Dec-23 04-May-24 04-May-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 30-Dec-23 04-May-24 04-May-24, CONDUIT,LIGHT
UCR.5RO-EL-LTS.110Issue Purchase Order 15 30-Dec-23 16-Jan-24 Issue Purchase Order

UCR.5RO-EL-LTS.115Material Delivery 90 16-Jan-24 04-May-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 30-Dec-23 04-May-24 04-May-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 30-Dec-23 04-May-24 04-May-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.5RO-EL-INSL.190
Issue Purchase Order 15 30-Dec-23 16-Jan-24 Issue Purchase Order

UCR.5RO-EL-INSL.195
Material Delivery 90 16-Jan-24 04-May-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, LIGHTNING PROTECTION SYSTEM
UCR.5RO-EL-LPS.110Issue Purchase Order 15 23-Dec-23 09-Jan-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
147 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.5RO-EL-LPS.115Material Delivery 90 09-Jan-24 27-Apr-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 23-Dec-23 27-Apr-24 27-Apr-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
UCR.5RO-EL-ERS.120Issue Purchase Order 15 23-Dec-23 09-Jan-24 Issue Purchase Order

UCR.5RO-EL-ERS.125Material Delivery 90 09-Jan-24 27-Apr-24 Material Delivery

LOW CURRENT 114 17-Dec-23 01-May-24 01-May-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 17-Dec-23 21-Apr-24 21-Apr-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 17-Dec-23 21-Apr-24 21-Apr-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.5R-ELL-FA130 Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-FA135 Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 17-Dec-23 21-Apr-24 21-Apr-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 17-Dec-23 21-Apr-24 21-Apr-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.5R-ELL-PH.130Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-PH.135Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 27-Dec-23 01-May-24 01-May-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 27-Dec-23 01-May-24 01-May-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.5R-ELL-PA.120Issue Purchase Order 15 27-Dec-23 14-Jan-24 Issue Purchase Order

UCR.5R-ELL-PA.125Material Delivery 90 14-Jan-24 01-May-24 Material Delivery

VIDEO SURVEILLANCE 105 17-Dec-23 21-Apr-24 21-Apr-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 17-Dec-23 21-Apr-24 21-Apr-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.5R-ELL-VS.120Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-VS.125Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

ACCESS CONTROL SYSTEM 105 17-Dec-23 21-Apr-24 21-Apr-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 17-Dec-23 21-Apr-24 21-Apr-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.5R-ELL-AC.130Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-AC.135Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 17-Dec-23 21-Apr-24 21-Apr-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 17-Dec-23 21-Apr-24 21-Apr-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.5R-ELL-RB.120Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-RB.125Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

SCADA SYSTEM 105 17-Dec-23 21-Apr-24 21-Apr-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 17-Dec-23 21-Apr-24 21-Apr-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.5R-ELL-SDA.130
Issue Purchase Order 15 17-Dec-23 03-Jan-24 Issue Purchase Order

UCR.5R-ELL-SDA.135
Material Delivery 90 03-Jan-24 21-Apr-24 Material Delivery

CONSTRUCTION 180 28-Nov-23 02-Jul-24 02-Jul-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 12 28-Nov-23 11-Dec-23 11-Dec-23, SOIL IMPROVEMENT WORKS
JAH-CON-UR5-SI.325 Soil Improvement 12 28-Nov-23 11-Dec-23 Soil Improvement

STRUCTURAL WORKS 119 12-Dec-23 01-May-24 01-May-24, STRUCTURAL WORKS


FOUNDATION 17 12-Dec-23 31-Dec-23 31-Dec-23, FOUNDATION
Part-1 17 12-Dec-23 31-Dec-23 31-Dec-23, Part-1
UCR-5-FDN-P1.150 Foundation Blinding concrete casting 1 12-Dec-23 12-Dec-23 Foundation Blinding concrete casting

UCR-5-FDN-P1.155 Foundation water proofing on blinding concrete 2 13-Dec-23 14-Dec-23 Foundation water proofing on blinding concrete

UCR-5-FDN-P1.160 Foundation Protection screed on water poofing 1 14-Dec-23 16-Dec-23 Foundation Protection screed on water poofing

UCR-5-FDN-P1.170 Foundation Rebar installation 5 16-Dec-23 21-Dec-23 Foundation Rebar installation

UCR-5-FDN-P1.175 Foundation Formwork installation 4 21-Dec-23 26-Dec-23 Foundation Formwork installation

UCR-5-FDN-P1.180 Foundation Construction joint work 1 26-Dec-23 27-Dec-23 Foundation Construction joint work

UCR-5-FDN-P1.185 Foundation concrete casting 1 27-Dec-23 28-Dec-23 Foundation concrete casting

UCR-5-FDN-P1.190 Foundation concrete curing 1 28-Dec-23 30-Dec-23 Foundation concrete curing

UCR-5-FDN-P1.195 Foundation Formwork Removal 1 30-Dec-23 31-Dec-23 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 24 31-Dec-23 28-Jan-24 28-Jan-24, WALLS UP TO SLAB LEVEL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
148 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL CONCRETE CASTING STAGE-1 24 31-Dec-23 28-Jan-24 28-Jan-24, WALL CONCRETE CASTING STAGE-1
Part-1 24 31-Dec-23 28-Jan-24 28-Jan-24, Part-1
UCR-5-WL-S1-P1.135
Room Walls Rebar Installation 6 04-Jan-24 11-Jan-24 Room Walls Rebar Installation

UCR-5-WL-S1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 11-Jan-24 13-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-5-WL-S1-P1.145
Room Walls Formwork Installation 8 13-Jan-24 22-Jan-24 Room Walls Formwork Installation

UCR-5-WL-S1-P1.150
Room Walls Concrete Casting 1 22-Jan-24 23-Jan-24 Room Walls Concrete Casting

UCR-5-WL-S1-P1.155
Room Walls Curing work 1 23-Jan-24 24-Jan-24 Room Walls Curing work

UCR-5-WL-S1-P1.160
Room Walls Formwork Removel 3 24-Jan-24 28-Jan-24 Room Walls Formwork Removel

UCR-5-WL-S1-P1.165
Room Walls Scafolding for rebar 4 31-Dec-23 04-Jan-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 31 28-Jan-24 04-Mar-24 04-Mar-24, TOP SLAB BELOW GROUND LEVEL
Part-1 31 28-Jan-24 04-Mar-24 04-Mar-24, Part-1
UCR-5-TS-P1.125 Room Top Slab Formwork Installation 9 28-Jan-24 07-Feb-24 Room Top Slab Formwork Installation

UCR-5-TS-P1.130 Room Top Slab Rebar Installation 5 07-Feb-24 13-Feb-24 Room Top Slab Rebar Installation

UCR-5-TS-P1.135 Room Top Slab Concrete Casting 1 13-Feb-24 14-Feb-24 Room Top Slab Concrete Casting

UCR-5-TS-P1.140 Room Top slab Curing work 12 14-Feb-24 28-Feb-24 Room Top slab Curing work

UCR-5-TS-P1.145 Room Top Slab Formwork Removel 4 28-Feb-24 04-Mar-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 21 14-Feb-24 10-Mar-24 10-Mar-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 21 14-Feb-24 10-Mar-24 10-Mar-24, WALL CONCRETE CASTING STAGE-1
Part-1 21 14-Feb-24 10-Mar-24 10-Mar-24, Part-1
UCR-5-WL-S1-A.135Room Walls Rebar Installation 6 18-Feb-24 25-Feb-24 Room Walls Rebar Installation

UCR-5-WL-S1-A.140Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 25-Feb-24 26-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-5-WL-S1-A.145Room Walls Formwork Installation 6 26-Feb-24 04-Mar-24 Room Walls Formwork Installation

UCR-5-WL-S1-A.150Room Walls Concrete Casting 1 04-Mar-24 05-Mar-24 Room Walls Concrete Casting

UCR-5-WL-S1-A.155Room Walls Curing work 1 05-Mar-24 06-Mar-24 Room Walls Curing work

UCR-5-WL-S1-A.160Room Walls Formwork Removel 3 06-Mar-24 10-Mar-24 Room Walls Formwork Removel

UCR-5-WL-S1-A.165Room Walls Scafolding for rebar 3 14-Feb-24 18-Feb-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 24 10-Mar-24 07-Apr-24 07-Apr-24, SLAB ABOVE GROUND LEVEL
Part-1 24 10-Mar-24 07-Apr-24 07-Apr-24, Part-1
UCR-5-SLB-A.125 Room Top Slab Formwork Installation 5 10-Mar-24 16-Mar-24 Room Top Slab Formwork Installation

UCR-5-SLB-A.130 Room Top Slab Rebar Installation 4 16-Mar-24 20-Mar-24 Room Top Slab Rebar Installation

UCR-5-SLB-A.135 Room Top Slab Concrete Casting 1 20-Mar-24 21-Mar-24 Room Top Slab Concrete Casting

UCR-5-SLB-A.140 Room Top slab Curing work 12 21-Mar-24 04-Apr-24 Room Top slab Curing work

UCR-5-SLB-A.145 Room Top Slab Formwork Removel 2 04-Apr-24 07-Apr-24 Room Top Slab Formwork Removel

WATER PROOFING 18 07-Apr-24 01-May-24 01-May-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 07-Apr-24 22-Apr-24 22-Apr-24, WALL WATER PROOFING STAGE-1
UCR-5-WP-WL-S1.115Surface preparation work 3 07-Apr-24 14-Apr-24 Surface preparation work

UCR-5-WP-WL-S1.120Applying of waterproofing material 4 14-Apr-24 18-Apr-24 Applying of waterproofing material

UCR-5-WP-WL-S1.125UR Bck filling 3 18-Apr-24 22-Apr-24 UR Bck filling

TOP SLAB WATER PROOFING 8 22-Apr-24 01-May-24 01-May-24, TOP SLAB WATER PROOFING
UCR-5-WP-SLB-S1.115
Surface preparation work 4 22-Apr-24 27-Apr-24 Surface preparation work

UCR-5-WP-SLB-S1.120
Applying of waterproofing material 3 27-Apr-24 30-Apr-24 Applying of waterproofing material

UCR-5-WP-SLB-S1.125
Leak Test 1 30-Apr-24 01-May-24 Leak Test

MECHANICAL ROOM MEP (UCR) 67 07-Apr-24 02-Jul-24 02-Jul-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN TUNNEL 67 07-Apr-24 02-Jul-24 02-Jul-24, ELECTRICAL WORK IN TUNNEL
POWER SYSTEM 67 07-Apr-24 02-Jul-24 02-Jul-24, POWER SYSTEM
EARTHING SYSTEM 25 07-Apr-24 09-May-24 09-May-24, EARTHING SYSTEM
UCR-5-EES.105 Earthing system Termination 6 27-Apr-24 04-May-24 Earthing system Termination

UCR-5-EES.115 Earthing system Initial Testing 5 04-May-24 09-May-24 Earthing system Initial Testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
149 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-5-EES.125 Earthing system soil resistivity test 6 07-Apr-24 17-Apr-24 Earthing system soil resistivity test

UCR-5-EES.135 Earthing system Copper rod/ earthing pit installation 8 17-Apr-24 27-Apr-24 Earthing system Copper rod/ earthing pit installation

LIGHTING SYSTEM 37 04-May-24 19-Jun-24 19-Jun-24, LIGHTING SYSTEM


UCR-5-ELI.105 Lighting system Conduit and boxes Installation 8 04-May-24 13-May-24 Lighting system Conduit and boxes Installation

UCR-5-ELI.115 Lighting system Cable Pulling 8 13-May-24 22-May-24 Lighting system Cable Pulling

UCR-5-ELI.125 Lighting system Installations 8 22-May-24 01-Jun-24 Lighting system Installations

UCR-5-ELI.135 Lighting system Termination 8 01-Jun-24 10-Jun-24 Lighting system Termination

UCR-5-ELI.145 Lighting system Initial Testing 5 10-Jun-24 19-Jun-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 04-May-24 02-Jul-24 02-Jul-24, CABLE TRAY /CABLE ROUTING SYSTEM
UCR-5-ECT.105 Cable Tray Installation 10 04-May-24 15-May-24 Cable Tray Installation

UCR-5-ECT.115 Cable Tray Inspection 10 15-May-24 27-May-24 Cable Tray Inspection

UCR-5-ECT.125 LV Cable pulling 10 27-May-24 08-Jun-24 LV Cable pulling

UCR-5-ECT.135 LV Cable Termination 10 08-Jun-24 24-Jun-24 LV Cable Termination

UCR-5-ECT.145 LV Cable Initial Testing 8 24-Jun-24 02-Jul-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 17-Apr-24 02-Jun-24 02-Jun-24, SMALL POWER SYSTEM


UCR-5-ESP.105 Small Power Conduit and boxes Installation 12 17-Apr-24 01-May-24 Small Power Conduit and boxes Installation

UCR-5-ESP.115 Small Power Cable Pulling 10 01-May-24 13-May-24 Small Power Cable Pulling

UCR-5-ESP.125 Small Power Installations 6 13-May-24 20-May-24 Small Power Installations

UCR-5-ESP.135 Small Power Termination 6 20-May-24 27-May-24 Small Power Termination

UCR-5-ESP.145 Small Power Initial Testing 5 27-May-24 02-Jun-24 Small Power Initial Testing

POWER DISTRIBUTION 39 04-May-24 23-Jun-24 23-Jun-24, POWER DISTRIBUTION


GENERATOR 39 04-May-24 23-Jun-24 23-Jun-24, GENERATOR
UCR-5-EPD.105 Generator Cable Tray Installation 7 04-May-24 12-May-24 Generator Cable Tray Installation

UCR-5-EPD.115 Generator Cable Pulling 7 12-May-24 20-May-24 Generator Cable Pulling

UCR-5-EPD.125 Generator Cell Pannel Installation 7 20-May-24 28-May-24 Generator Cell Pannel Installation

UCR-5-EPD.135 Generator Installation 7 28-May-24 05-Jun-24 Generator Installation

UCR-5-EPD.145 Generator Pannel / Cable Termination 7 05-Jun-24 12-Jun-24 Generator Pannel / Cable Termination

UCR-5-EPD.155 Generator Pannel / Cable initial Testing 5 13-Jun-24 23-Jun-24 Generator Pannel / Cable initial Testing

UPS 28 04-May-24 05-Jun-24 05-Jun-24, UPS


UCR-5-EPD.165 UPS Cable Tray Installation 5 04-May-24 09-May-24 UPS Cable Tray Installation

UCR-5-EPD.175 UPS Cable Pulling 5 09-May-24 15-May-24 UPS Cable Pulling

UCR-5-EPD.185 UPS Pannel Installation 5 15-May-24 21-May-24 UPS Pannel Installation

UCR-5-EPD.195 UPS Installation 5 21-May-24 27-May-24 UPS Installation

UCR-5-EPD.205 UPS Pannel / Cable Termination 5 27-May-24 01-Jun-24 UPS Pannel / Cable Termination

UCR-5-EPD.215 UPS Pannel / Cable initial Testing 4 02-Jun-24 05-Jun-24 UPS Pannel / Cable initial Testing

MDB 33 04-May-24 10-Jun-24 10-Jun-24, MDB


UCR-5-EPD.225 MDB Cable Tray Installation 7 04-May-24 12-May-24 MDB Cable Tray Installation

UCR-5-EPD.235 MDB Cable Pulling 7 12-May-24 20-May-24 MDB Cable Pulling

UCR-5-EPD.245 MDB Pannel Installation 7 20-May-24 28-May-24 MDB Pannel Installation

UCR-5-EPD.255 MDB Pannel / Cable Termination 7 28-May-24 05-Jun-24 MDB Pannel / Cable Termination

UCR-5-EPD.265 MDB Pannel / Cable initial Testing 5 05-Jun-24 10-Jun-24 MDB Pannel / Cable initial Testing

MCC 33 04-May-24 10-Jun-24 10-Jun-24, MCC


UCR-5-EPD.325 MCC Cable Tray Installation 7 04-May-24 12-May-24 MCC Cable Tray Installation

UCR-5-EPD.335 MCC Cable Pulling 7 12-May-24 20-May-24 MCC Cable Pulling

UCR-5-EPD.345 MCC Pannel Installation 7 20-May-24 28-May-24 MCC Pannel Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
150 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-5-EPD.355 MCC Pannel / Cable Termination 7 28-May-24 05-Jun-24 MCC Pannel / Cable Termination

UCR-5-EPD.365 MCC Pannel / Cable initial Testing 5 05-Jun-24 10-Jun-24 MCC Pannel / Cable initial Testing

SMSB 24 04-May-24 30-May-24 30-May-24, SMSB


UCR-5-EPD.275 SMSB Cable Tray Installation 5 04-May-24 09-May-24 SMSB Cable Tray Installation

UCR-5-EPD.285 SMSB Cable Pulling 5 09-May-24 15-May-24 SMSB Cable Pulling

UCR-5-EPD.295 SMSB Pannel Installation 5 15-May-24 21-May-24 SMSB Pannel Installation

UCR-5-EPD.305 SMSB Pannel / Cable Termination 5 21-May-24 27-May-24 SMSB Pannel / Cable Termination

UCR-5-EPD.315 SMSB Pannel / Cable initial Testing 4 27-May-24 30-May-24 SMSB Pannel / Cable initial Testing

DB 24 04-May-24 30-May-24 30-May-24, DB


UCR-5-EPD.375 DB Cable Tray Installation 5 04-May-24 09-May-24 DB Cable Tray Installation

UCR-5-EPD.385 DB Cable Pulling 5 09-May-24 15-May-24 DB Cable Pulling

UCR-5-EPD.395 DB Pannel Installation 5 15-May-24 21-May-24 DB Pannel Installation

UCR-5-EPD.405 DB Pannel / Cable Termination 5 21-May-24 27-May-24 DB Pannel / Cable Termination

UCR-5-EPD.415 DB Pannel / Cable initial Testing 4 27-May-24 30-May-24 DB Pannel / Cable initial Testing

ISOLATOR 24 04-May-24 30-May-24 30-May-24, ISOLATOR


UCR-5-EPD.425 Isolators Cable Tray Installation 5 04-May-24 09-May-24 Isolators Cable Tray Installation

UCR-5-EPD.435 Isolators Cable Pulling 5 09-May-24 15-May-24 Isolators Cable Pulling

UCR-5-EPD.445 Isolators Pannel Installation 5 15-May-24 21-May-24 Isolators Pannel Installation

UCR-5-EPD.455 Isolators Pannel / Cable Termination 5 21-May-24 27-May-24 Isolators Pannel / Cable Termination

UCR-5-EPD.465 Isolators Pannel / Cable initial Testing 4 27-May-24 30-May-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 04-May-24 30-May-24 30-May-24, LCP/ ELCP


UCR-5-EPD.475 LCP/ELCP Cable Tray Installation 5 04-May-24 09-May-24 LCP/ELCP Cable Tray Installation

UCR-5-EPD.485 LCP/ELCP Cable Pulling 5 09-May-24 15-May-24 LCP/ELCP Cable Pulling

UCR-5-EPD.495 LCP/ELCP Pannel Installation 5 15-May-24 21-May-24 LCP/ELCP Pannel Installation

UCR-5-EPD.505 LCP/ELCP Pannel / Cable Termination 5 21-May-24 27-May-24 LCP/ELCP Pannel / Cable Termination

UCR-5-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 27-May-24 30-May-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 21-Apr-24 24-Jun-24 24-Jun-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 21-Apr-24 09-Jun-24 09-Jun-24, FIRE ALARM SYSTEM
UCR-5-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 21-Apr-24 01-May-24 Fire Alarm Conduit /Cable Tray Installation

UCR-5-ELFA.115 Fire Alarm Cable Pulling 9 01-May-24 12-May-24 Fire Alarm Cable Pulling

UCR-5-ELFA.125 Fire Alarm Devices Installation 9 12-May-24 22-May-24 Fire Alarm Devices Installation

UCR-5-ELFA.135 Fire Alarm Devices and Cable Termination 9 22-May-24 02-Jun-24 Fire Alarm Devices and Cable Termination

UCR-5-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 02-Jun-24 09-Jun-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 21-Apr-24 09-Jun-24 09-Jun-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-5-ELVS.105 ICT System Conduit /Cable Tray Installation 9 21-Apr-24 01-May-24 ICT System Conduit /Cable Tray Installation

UCR-5-ELVS.115 ICT System Cable Pulling 9 01-May-24 12-May-24 ICT System Cable Pulling

UCR-5-ELVS.125 ICT System Devices Installation 9 12-May-24 22-May-24 ICT System Devices Installation

UCR-5-ELVS.135 ICT System Devices and Cable Termination 9 22-May-24 02-Jun-24 ICT System Devices and Cable Termination

UCR-5-ELVS.145 ICT System Devices and Cable initial Testing 6 02-Jun-24 09-Jun-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 21-Apr-24 09-Jun-24 09-Jun-24, ACCESS CONTROL SYSTEM


UCR-5-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 21-Apr-24 01-May-24 Access Control System Conduit /Cable Tray Installation

UCR-5-ELAC.115 Access Control System Cable Pulling 9 01-May-24 12-May-24 Access Control System Cable Pulling

UCR-5-ELAC.125 Access Control System Devices Installation 9 12-May-24 22-May-24 Access Control System Devices Installation

UCR-5-ELAC.135 Access Control System Devices and Cable Termination 9 22-May-24 02-Jun-24 Access Control System Devices and Cable Termination

UCR-5-ELAC.145 Access Control System Devices and Cable initial Testing 6 02-Jun-24 09-Jun-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 01-May-24 24-Jun-24 24-Jun-24, PUBLIC ADDRESS SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
151 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-5-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 01-May-24 12-May-24 Public Address System Conduit /Cable Tray Installation

UCR-5-ELPA.115 Public Address System Cable Pulling 9 12-May-24 22-May-24 Public Address System Cable Pulling

UCR-5-ELPA.125 Public Address System Devices Installation 9 22-May-24 02-Jun-24 Public Address System Devices Installation

UCR-5-ELPA.135 Public Address System Devices and Cable Termination 9 02-Jun-24 12-Jun-24 Public Address System Devices and Cable Termination

UCR-5-ELPA.145 Public Address System Devices and Cable initial Testing 6 12-Jun-24 24-Jun-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 21-Apr-24 09-Jun-24 09-Jun-24, SCADA SYSTEM


UCR-5-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 21-Apr-24 01-May-24 SCADA System Conduit /Cable Tray Installation

UCR-5-ELSC.115 SCADA System Cable Pulling 9 01-May-24 12-May-24 SCADA System Cable Pulling

UCR-5-ELSC.125 SCADA System Devices Installation 9 12-May-24 22-May-24 SCADA System Devices Installation

UCR-5-ELSC.135 SCADA System Devices and Cable Termination 9 22-May-24 02-Jun-24 SCADA System Devices and Cable Termination

UCR-5-ELSC.145 SCADA System Devices and Cable initial Testing 6 02-Jun-24 09-Jun-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 21-Apr-24 09-Jun-24 09-Jun-24, RADIO RE- BROADCOASTING/ TETRA
UCR-5-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 21-Apr-24 01-May-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-5-ELRD.115 Radio/TETRA System Cable Pulling 9 01-May-24 12-May-24 Radio/TETRA System Cable Pulling

UCR-5-ELRD.125 Radio/TETRA System Devices Installation 9 12-May-24 22-May-24 Radio/TETRA System Devices Installation

UCR-5-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 22-May-24 02-Jun-24 Radio/TETRA System Devices and Cable Termination

UCR-5-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 02-Jun-24 09-Jun-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN TUNNEL 20 12-May-24 04-Jun-24 04-Jun-24, MECHANICAL WORK IN TUNNEL


FIRE FIGHTING 13 12-May-24 27-May-24 27-May-24, FIRE FIGHTING
UCR-5-MFF.105 Fire Fighting system Pipe and accessories installation 11 12-May-24 25-May-24 Fire Fighting system Pipe and accessories installation

UCR-5-MFF.135 Fire Fighting system fire hose cabinet/extingusher installation 3 21-May-24 25-May-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-5-MFF.140 Fire Fighting system initial testing 2 25-May-24 27-May-24 Fire Fighting system initial testing

UCR-5-MFF.145 Fire Fighting clean agent system 2 22-May-24 25-May-24 Fire Fighting clean agent system

HVAC 20 12-May-24 04-Jun-24 04-Jun-24, HVAC


UCR-5-MHV.115 Air conditioning system installation 5 26-May-24 01-Jun-24 Air conditioning system installation

UCR-5-MHV.120 Fan installation 4 27-May-24 01-Jun-24 Fan installation

UCR-5-MHV.125 Duct and accessories installation 12 12-May-24 26-May-24 Duct and accessories installation

UCR-5-MHV.135 HVAC inital testing 3 01-Jun-24 04-Jun-24 HVAC inital testing

PLUMBING 4 12-May-24 16-May-24 16-May-24, PLUMBING


UCR-5-MPL.105 Plumbing drainage system installation 3 12-May-24 15-May-24 Plumbing drainage system installation

UCR-5-MPL.115 Plumbing drainage system initial testing 1 15-May-24 16-May-24 Plumbing drainage system initial testing

DRY UTILITIES 18 12-May-24 01-Jun-24 01-Jun-24, DRY UTILITIES


POWER 18 12-May-24 01-Jun-24 01-Jun-24, POWER
POWER LV 16 12-May-24 30-May-24 30-May-24, POWER LV
DU-P-LV.2600 Installation of support 1 12-May-24 13-May-24 Installation of support

DU-P-LV.2605 Installation of horizontal busbar 2 13-May-24 14-May-24 Installation of horizontal busbar

DU-P-LV.2610 Installation of vertical busbar 2 14-May-24 16-May-24 Installation of vertical busbar

DU-P-LV.2615 Installation of left/right elbow 2 16-May-24 18-May-24 Installation of left/right elbow

DU-P-LV.2620 Installation of right horizintal offset 2 19-May-24 20-May-24 Installation of right horizintal offset

DU-P-LV.2625 Instalaltion of upward vertical offset 3 20-May-24 23-May-24 Instalaltion of upward vertical offset

DU-P-LV.2630 Installation of downward vertical offset 3 23-May-24 27-May-24 Installation of downward vertical offset

DU-P-LV.2635 Installation of transformer and panel connection 2 28-May-24 30-May-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 12-May-24 01-Jun-24 01-Jun-24, MEDIUM VOLTAGE


DU-P-MV.2600 Installation of cable try, arm, racks and ladder 6 12-May-24 19-May-24 Installation of cable try, arm, racks and ladder

DU-P-MV.2605 Installation of MV Cable 4 19-May-24 23-May-24 Installation of MV Cable

DU-P-MV.2610 Installation of cable cleats 2 23-May-24 26-May-24 Installation of cable cleats

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
152 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-MV.2615 Installation of gland 1 26-May-24 27-May-24 Installation of gland

DU-P-MV.2620 splicing/termination of MV cable 2 27-May-24 28-May-24 splicing/termination of MV cable

DU-P-MV.2625 Testing and Pre-commissioning of cable 2 28-May-24 30-May-24 Testing and Pre-commissioning of cable

DU-P-MV.2630 Energezation 2 30-May-24 01-Jun-24 Energezation

TRANSFORMER 16 12-May-24 30-May-24 30-May-24, TRANSFORMER


DU-P-T.2600 Installation of Transformer unit 2 12-May-24 13-May-24 Installation of Transformer unit

DU-P-T.2605 Testing and Pre-Commissioning of unit 1 14-May-24 14-May-24 Testing and Pre-Commissioning of unit

DU-P-T.2610 Termination and Splicing of MV Cable 3 14-May-24 18-May-24 Termination and Splicing of MV Cable

DU-P-T.2615 Termination and Splicing of LV Cable/bus way 3 19-May-24 22-May-24 Termination and Splicing of LV Cable/bus way

DU-P-T.2620 Installation and connection of I/O system 2 22-May-24 25-May-24 Installation and connection of I/O system

DU-P-T.2625 Installation of Grounding and Protection System 2 25-May-24 27-May-24 Installation of Grounding and Protection System

DU-P-T.2630 Testing and Commissioning of MV System 1 28-May-24 28-May-24 Testing and Commissioning of MV System

DU-P-T.2635 Testing and Commissioning of LV System 1 28-May-24 29-May-24 Testing and Commissioning of LV System

DU-P-T.2640 Energezation 1 29-May-24 30-May-24 Energezation

RMU 16 12-May-24 30-May-24 30-May-24, RMU


DU-P-RMU.2600 Installation RMU unit 2 12-May-24 14-May-24 Installation RMU unit

DU-P-RMU.2605 Testing and Pre-Commissioning of unit 2 14-May-24 16-May-24 Testing and Pre-Commissioning of unit

DU-P-RMU.2610 Termination and Splicing of Ring-MV Cable 4 16-May-24 21-May-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.2615 Termination and Splicing of T-MV Cable 4 21-May-24 26-May-24 Termination and Splicing of T-MV Cable

DU-P-RMU.2620 Installation of Grounding and Protection System 2 26-May-24 28-May-24 Installation of Grounding and Protection System

DU-P-RMU.2625 Testing and Commissioning of MV System 1 28-May-24 29-May-24 Testing and Commissioning of MV System

DU-P-RMU.2630 Energezation 1 29-May-24 30-May-24 Energezation

UTILITY ROOM 17 (IN ZONE 09) (FLD +15.85 m) 451 24-May-23 13-Nov-24 13-Nov-24, UTILITY ROOM 17 (IN ZONE 09) (FLD +15.85 m)
ENGINEERING 304 24-May-23 21-May-24 21-May-24, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 304 24-May-23 21-May-24 21-May-24, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 38 24-May-23 10-Jul-23 10-Jul-23, EARTH WORKS
T1-ENG-UR17-SI.1100Soil Improvement Design Preparation & Submission 26 24-May-23 22-Jun-23 Soil Improvement Design Preparation & Submission

T1-ENG-UR17-SI.1105Soil Improvement Design Review & Approval 12 24-Jun-23 10-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


UCR.17ENG-CV-ST.130
Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

UCR.17ENG-CV-ST.135
Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

UCR.17ENG-CV-ST.140
Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

UCR.17ENG-CV-ST.145
Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

UCR.17ENG-CV-ST.150
Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

UCR.17ENG-CV-ST.155
Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
UCR.17ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

UCR.17ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
UCR.17ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

UCR.17ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


UCR.17ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

UCR.17ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 304 24-May-23 21-May-24 21-May-24, ELECTRICAL


CABLE TRAYS 239 24-May-23 02-Mar-24 02-Mar-24, CABLE TRAYS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
153 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.17ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

UCR.17ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 18-Feb-24 02-Mar-24 Cable Tray Shop Drawings Review & Approval

POWER CABLES 103 12-Nov-23 11-Mar-24 11-Mar-24, POWER CABLES


UCR.17ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 12-Nov-23 28-Nov-23 Power Cables Shop Drawings Preparation & Submission

UCR.17ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 26-Feb-24 11-Mar-24 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 81 28-Nov-23 02-Mar-24 02-Mar-24, LIGHTING SYSTEM


UCR.17ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 28-Nov-23 14-Dec-23 Lighting System Shop Drawings Preparation & Submission

UCR.17ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 18-Feb-24 02-Mar-24 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 99 14-Dec-23 08-Apr-24 08-Apr-24, ELECTRICAL INSTALLATIONS


UCR.17ENG-EL-EI.110
Electrical Installations Shop Drawings Preparation & Submission 14 14-Dec-23 31-Dec-23 Electrical Installations Shop Drawings Preparation & Submission

UCR.17ENG-EL-EI.115
Electrical Installations Shop Drawings Review & Approval 12 25-Mar-24 08-Apr-24 Electrical Installations Shop Drawings Review & Approval

TRANSFORMERS INSTALLATION 85 31-Dec-23 08-Apr-24 08-Apr-24, TRANSFORMERS INSTALLATION


UCR.17ENG-EL-TI.110
Transformers Installation Shop Drawings Preparation & Submission 14 31-Dec-23 16-Jan-24 Transformers Installation Shop Drawings Preparation & Submission

UCR.17ENG-EL-TI.115
Transformers Installation Shop Drawings Review & Approval 12 25-Mar-24 08-Apr-24 Transformers Installation Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 40 16-Jan-24 02-Mar-24 02-Mar-24, LIGHTNING PROTECTION SYSTEM


UCR.17ENG-EL-LP.110
Lightning Protection Drawings Preparation & Submission 14 16-Jan-24 01-Feb-24 Lightning Protection Drawings Preparation & Submission

UCR.17ENG-EL-LP.115
Lightning Protection Shop Drawings Review & Approval 12 18-Feb-24 02-Mar-24 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 01-Feb-24 02-Mar-24 02-Mar-24, EARTHING SYSTEM


UCR.17ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 01-Feb-24 17-Feb-24 Earthing System Shop Drawings Preparation & Submission

UCR.17ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 18-Feb-24 02-Mar-24 Earthing System Drawings Review & Approval

LOW CURRENT 304 24-May-23 21-May-24 21-May-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 304 24-May-23 21-May-24 21-May-24, FIRE DETECTION AND ALARM SYSTEM
UCR.17ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

UCR.17ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 07-May-24 21-May-24 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 95 27-Jan-24 21-May-24 21-May-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UCR.17ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 27-Jan-24 12-Feb-24 Telephone Shop Drawings Preparation & Submission

UCR.17ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 07-May-24 21-May-24 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 81 12-Feb-24 21-May-24 21-May-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
UCR.17ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 12-Feb-24 28-Feb-24 Public Address system Shop Drawings Preparation & Submission

UCR.17ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 07-May-24 21-May-24 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 68 28-Feb-24 21-May-24 21-May-24, VIDEO SURVEILLANCE


UCR.17ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 28-Feb-24 16-Mar-24 Video Surveillance system Shop Drawings Preparation & Submission

UCR.17ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 07-May-24 21-May-24 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 54 16-Mar-24 21-May-24 21-May-24, ACCESS CONTROL SYSTEM


UCR.17ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 16-Mar-24 01-Apr-24 Access Control system Shop Drawings Preparation & Submission

UCR.17ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 07-May-24 21-May-24 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 40 01-Apr-24 21-May-24 21-May-24, RADIO RE-BROADCASTING SYSTEM


UCR.17ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 01-Apr-24 21-Apr-24 Radio Re Broadcasting system Shop Drawings Preparation & Submission

UCR.17ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 07-May-24 21-May-24 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 21-Apr-24 21-May-24 21-May-24, SCADA SYSTEM


UCR.17ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 21-Apr-24 07-May-24 SCADA system Shop Drawings Preparation & Submission

UCR.17ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 07-May-24 21-May-24 SCADA system Shop Drawings Review & Approval

DRY UTILITIES 91 24-May-23 10-Sep-23 10-Sep-23, DRY UTILITIES


POWER 91 24-May-23 10-Sep-23 10-Sep-23, POWER
POWER LV 31 24-May-23 03-Jul-23 03-Jul-23, POWER LV
DU-P-LV.3300 Prepare and submit power system shopdrawings 20 24-May-23 15-Jun-23 Prepare and submit power system shopdrawings

DU-P-LV.3305 Review and approval power system shopdrawings 11 15-Jun-23 03-Jul-23 Review and approval power system shopdrawings

MEDIUM VOLTAGE 31 15-Jun-23 25-Jul-23 25-Jul-23, MEDIUM VOLTAGE


DU-P-MV.3300 Prepare and submit medium voltage shopdrawings 20 15-Jun-23 12-Jul-23 Prepare and submit medium voltage shopdrawings

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
154 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-MV.3305 Review and approval medium voltage shopdrawings 11 12-Jul-23 25-Jul-23 Review and approval medium voltage shopdrawings

TRANSFORMER 31 12-Jul-23 17-Aug-23 17-Aug-23, TRANSFORMER


DU-P-T.3300 Prepare and submit transformer shopdrawings 20 12-Jul-23 05-Aug-23 Prepare and submit transformer shopdrawings

DU-P-T.3305 Review and approval transformer shopdrawings 11 05-Aug-23 17-Aug-23 Review and approval transformer shopdrawings

RMU 31 05-Aug-23 10-Sep-23 10-Sep-23, RMU


DU-P-RMU.3300 Prepare and submit RMU shopdrawings 20 05-Aug-23 28-Aug-23 Prepare and submit RMU shopdrawings

DU-P-RMU.3305 Review and approval RMU shopdrawings 11 28-Aug-23 10-Sep-23 Review and approval RMU shopdrawings

PROCUREMENT 216 09-Jan-24 26-Sep-24 26-Sep-24, PROCUREMENT


CIVIL/STRUCTURAL 16 09-Jan-24 27-Jan-24 27-Jan-24, CIVIL/STRUCTURAL
UCR.17PRO-CV.110 Issue Purchase Order 6 09-Jan-24 15-Jan-24 Issue Purchase Order

UCR.17PRO-CV.115 Material Delivery 10 16-Jan-24 27-Jan-24 Material Delivery

MECHANICAL 105 04-May-24 08-Sep-24 08-Sep-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 04-May-24 08-Sep-24 08-Sep-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
UCR.17PR-MC-FF.110Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

UCR.17PR-MC-FF.115Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

VENTILATION SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 04-May-24 08-Sep-24 08-Sep-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
UCR.17PR-MC-DS.110
Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

UCR.17PR-MC-DS.115
Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

AIR CONDITIONING WORKS 105 04-May-24 08-Sep-24 08-Sep-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 04-May-24 08-Sep-24 08-Sep-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
UCR.17PR-MC-AC.110
Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

UCR.17PR-MC-AC.115
Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

PLUMBING SYSTEM 105 04-May-24 08-Sep-24 08-Sep-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 04-May-24 08-Sep-24 08-Sep-24, PUMPS,PIPES,FITTINGS,VALVES
UCR.17PR-MC-PI.110Issue Purchase Order 15 04-May-24 21-May-24 Issue Purchase Order

UCR.17PR-MC-PI.115Material Delivery 90 21-May-24 08-Sep-24 Material Delivery

ELECTRICAL 170 02-Mar-24 26-Sep-24 26-Sep-24, ELECTRICAL


CABLE TRAY 105 02-Mar-24 10-Jul-24 10-Jul-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 02-Mar-24 10-Jul-24 10-Jul-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
UCR.17PR-EL-CT.110Issue Purchase Order 15 02-Mar-24 19-Mar-24 Issue Purchase Order

UCR.17PR-EL-CT.115Material Delivery 90 19-Mar-24 10-Jul-24 Material Delivery

POWER CABLES 105 11-Mar-24 20-Jul-24 20-Jul-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 11-Mar-24 20-Jul-24 20-Jul-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
UCR.17PR-EL-PC.110Issue Purchase Order 15 11-Mar-24 28-Mar-24 Issue Purchase Order

UCR.17PR-EL-PC.115Material Delivery 90 28-Mar-24 20-Jul-24 Material Delivery

LIGHTING SYSTEM 105 02-Mar-24 10-Jul-24 10-Jul-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 02-Mar-24 10-Jul-24 10-Jul-24, CONDUIT,LIGHT
UCR.17PR-EL-LS.110Issue Purchase Order 15 02-Mar-24 19-Mar-24 Issue Purchase Order

UCR.17PR-EL-LS.115Material Delivery 90 19-Mar-24 10-Jul-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 08-Apr-24 17-Aug-24 17-Aug-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 08-Apr-24 17-Aug-24 17-Aug-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
UCR.17PR-EL-EI.110 Issue Purchase Order 15 08-Apr-24 29-Apr-24 Issue Purchase Order

UCR.17PR-EL-EI.115 Material Delivery 90 29-Apr-24 17-Aug-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 02-Mar-24 10-Jul-24 10-Jul-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 02-Mar-24 10-Jul-24 10-Jul-24, LIGHTNING PROTECTION SYSTEM
UCR.17PR-EL-LP.110Issue Purchase Order 15 02-Mar-24 19-Mar-24 Issue Purchase Order

UCR.17PR-EL-LP.115Material Delivery 90 19-Mar-24 10-Jul-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 02-Mar-24 10-Jul-24 10-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 02-Mar-24 10-Jul-24 10-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
155 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR.17PR-EL-ES.110Issue Purchase Order 15 02-Mar-24 19-Mar-24 Issue Purchase Order

UCR.17PR-EL-ES.115Material Delivery 90 19-Mar-24 10-Jul-24 Material Delivery

LOW CURRENT 105 21-May-24 26-Sep-24 26-Sep-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 21-May-24 26-Sep-24 26-Sep-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 21-May-24 26-Sep-24 26-Sep-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
UCR.17PR-ELL-FA.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-FA.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 21-May-24 26-Sep-24 26-Sep-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 21-May-24 26-Sep-24 26-Sep-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
UCR.17PR-ELL-PH.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-PH.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 21-May-24 26-Sep-24 26-Sep-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 21-May-24 26-Sep-24 26-Sep-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
UCR.17PR-ELL-PA.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-PA.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

VIDEO SURVEILLANCE 105 21-May-24 26-Sep-24 26-Sep-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 21-May-24 26-Sep-24 26-Sep-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
UCR.17PR-ELL-VS.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-VS.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

ACCESS CONTROL SYSTEM 105 21-May-24 26-Sep-24 26-Sep-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 21-May-24 26-Sep-24 26-Sep-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
UCR.17PR-ELL-AC.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-AC.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 21-May-24 26-Sep-24 26-Sep-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 21-May-24 26-Sep-24 26-Sep-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
UCR.17PR-ELL-RB.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-RB.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

SCADA SYSTEM 105 21-May-24 26-Sep-24 26-Sep-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 21-May-24 26-Sep-24 26-Sep-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
UCR.17PR-ELL-SD.20
Issue Purchase Order 15 21-May-24 08-Jun-24 Issue Purchase Order

UCR.17PR-ELL-SD.25
Material Delivery 90 08-Jun-24 26-Sep-24 Material Delivery

CONSTRUCTION 260 07-Jan-24 13-Nov-24 13-Nov-24, CONSTRUCTION


SOIL IMPROVEMENT WORKS 18 07-Jan-24 27-Jan-24 27-Jan-24, SOIL IMPROVEMENT WORKS
T1-CON-UR17-SI.350 Soil Improvement 18 07-Jan-24 27-Jan-24 Soil Improvement

STRUCTURAL WORKS 157 28-Jan-24 05-Aug-24 05-Aug-24, STRUCTURAL WORKS


FOUNDATION 22 28-Jan-24 21-Feb-24 21-Feb-24, FOUNDATION
Part-1 22 28-Jan-24 21-Feb-24 21-Feb-24, Part-1
UCR-17-FDN-P1.150 Foundation Blinding concrete casting 1 28-Jan-24 28-Jan-24 Foundation Blinding concrete casting

UCR-17-FDN-P1.155 Foundation water proofing on blinding concrete 2 29-Jan-24 30-Jan-24 Foundation water proofing on blinding concrete

UCR-17-FDN-P1.160 Foundation Protection screed on water poofing 1 30-Jan-24 31-Jan-24 Foundation Protection screed on water poofing

UCR-17-FDN-P1.170 Foundation Rebar installation 9 31-Jan-24 11-Feb-24 Foundation Rebar installation

UCR-17-FDN-P1.175 Foundation Formwork installation 4 11-Feb-24 15-Feb-24 Foundation Formwork installation

UCR-17-FDN-P1.180 Foundation Construction joint work 2 15-Feb-24 18-Feb-24 Foundation Construction joint work

UCR-17-FDN-P1.185 Foundation concrete casting 1 18-Feb-24 19-Feb-24 Foundation concrete casting

UCR-17-FDN-P1.190 Foundation concrete curing 1 19-Feb-24 20-Feb-24 Foundation concrete curing

UCR-17-FDN-P1.195 Foundation Formwork Removal 1 20-Feb-24 21-Feb-24 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 30 21-Feb-24 27-Mar-24 27-Mar-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 30 21-Feb-24 27-Mar-24 27-Mar-24, WALL CONCRETE CASTING STAGE-1
Part-1 30 21-Feb-24 27-Mar-24 27-Mar-24, Part-1
UCR-17-WL-P1.105 Room Walls Rebar Installation 10 26-Feb-24 09-Mar-24 Room Walls Rebar Installation

UCR-17-WL-P1.115 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 09-Mar-24 11-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
156 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-17-WL-P1.125 Room Walls Formwork Installation 9 11-Mar-24 21-Mar-24 Room Walls Formwork Installation

UCR-17-WL-P1.135 Room Walls Concrete Casting 1 21-Mar-24 23-Mar-24 Room Walls Concrete Casting

UCR-17-WL-P1.145 Room Walls Curing work 1 23-Mar-24 24-Mar-24 Room Walls Curing work

UCR-17-WL-P1.155 Room Walls Formwork Removel 3 24-Mar-24 27-Mar-24 Room Walls Formwork Removel

UCR-17-WL-P1.165 Room Walls Scafolding for rebar 4 21-Feb-24 26-Feb-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 35 27-Mar-24 11-May-24 11-May-24, TOP SLAB BELOW GROUND LEVEL
Part-1 35 27-Mar-24 11-May-24 11-May-24, Part-1
UCR-17-TS-P1.125 Room Top Slab Formwork Installation 10 27-Mar-24 08-Apr-24 Room Top Slab Formwork Installation

UCR-17-TS-P1.130 Room Top Slab Rebar Installation 8 08-Apr-24 21-Apr-24 Room Top Slab Rebar Installation

UCR-17-TS-P1.135 Room Top Slab Concrete Casting 1 21-Apr-24 22-Apr-24 Room Top Slab Concrete Casting

UCR-17-TS-P1.140 Room Top slab Curing work 12 22-Apr-24 06-May-24 Room Top slab Curing work

UCR-17-TS-P1.145 Room Top Slab Formwork Removel 4 06-May-24 11-May-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB 29 22-Apr-24 26-May-24 26-May-24, WALLS ABOVE SLAB


WALL CONCRETE CASTING STAGE-1 29 22-Apr-24 26-May-24 26-May-24, WALL CONCRETE CASTING STAGE-1
Part-1 29 22-Apr-24 26-May-24 26-May-24, Part-1
UCR-174-S1-A.135 Room Walls Rebar Installation 9 27-Apr-24 07-May-24 Room Walls Rebar Installation

UCR-174-S1-A.140 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 07-May-24 09-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

UCR-174-S1-A.145 Room Walls Formwork Installation 9 09-May-24 20-May-24 Room Walls Formwork Installation

UCR-174-S1-A.150 Room Walls Concrete Casting 1 20-May-24 21-May-24 Room Walls Concrete Casting

UCR-174-S1-A.155 Room Walls Curing work 1 21-May-24 22-May-24 Room Walls Curing work

UCR-174-S1-A.160 Room Walls Formwork Removel 3 22-May-24 26-May-24 Room Walls Formwork Removel

UCR-174-S1-A.165 Room Walls Scafolding for rebar 4 22-Apr-24 27-Apr-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 35 26-May-24 10-Jul-24 10-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 35 26-May-24 10-Jul-24 10-Jul-24, Part-1
UCR-17-SLB-A.125 Room Top Slab Formwork Installation 10 26-May-24 06-Jun-24 Room Top Slab Formwork Installation

UCR-17-SLB-A.130 Room Top Slab Rebar Installation 8 06-Jun-24 20-Jun-24 Room Top Slab Rebar Installation

UCR-17-SLB-A.135 Room Top Slab Concrete Casting 1 20-Jun-24 22-Jun-24 Room Top Slab Concrete Casting

UCR-17-SLB-A.140 Room Top slab Curing work 12 22-Jun-24 06-Jul-24 Room Top slab Curing work

UCR-17-SLB-A.145 Room Top Slab Formwork Removel 4 06-Jul-24 10-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 22 10-Jul-24 05-Aug-24 05-Aug-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 16 10-Jul-24 29-Jul-24 29-Jul-24, WALL WATER PROOFING STAGE-1
UCR-17-WL-S1.115 Surface preparation work 6 10-Jul-24 17-Jul-24 Surface preparation work

UCR-17-WL-S1.120 Applying of waterproofing material 6 17-Jul-24 24-Jul-24 Applying of waterproofing material

UCR-17-WL-S1.125 UR Bck filling 4 24-Jul-24 29-Jul-24 UR Bck filling

TOP SLAB WATER PROOFING 22 10-Jul-24 05-Aug-24 05-Aug-24, TOP SLAB WATER PROOFING
UCR-17-WP-SLB-S1.115
Surface preparation work 12 10-Jul-24 24-Jul-24 Surface preparation work

UCR-17-WP-SLB-S1.120
Applying of waterproofing material 9 24-Jul-24 04-Aug-24 Applying of waterproofing material

UCR-17-WP-SLB-S1.125
Leak Test 1 04-Aug-24 05-Aug-24 Leak Test

MECHANICAL ROOM MEP (UCR) 107 10-Jul-24 13-Nov-24 13-Nov-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK IN UCR 107 10-Jul-24 13-Nov-24 13-Nov-24, ELECTRICAL WORK IN UCR
POWER SYSTEM 76 10-Jul-24 08-Oct-24 08-Oct-24, POWER SYSTEM
LIGHTING SYSTEM 37 10-Jul-24 22-Aug-24 22-Aug-24, LIGHTING SYSTEM
UCR-17-ELI.105 Lighting system Conduit and boxes Installation 8 10-Jul-24 20-Jul-24 Lighting system Conduit and boxes Installation

UCR-17-ELI.115 Lighting system Cable Pulling 8 20-Jul-24 29-Jul-24 Lighting system Cable Pulling

UCR-17-ELI.125 Lighting system Installations 8 29-Jul-24 07-Aug-24 Lighting system Installations

UCR-17-ELI.135 Lighting system Termination 8 07-Aug-24 17-Aug-24 Lighting system Termination

UCR-17-ELI.145 Lighting system Initial Testing 5 17-Aug-24 22-Aug-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 20-Jul-24 14-Sep-24 14-Sep-24, CABLE TRAY /CABLE ROUTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
157 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-17-ECT.105 Cable Tray Installation 10 20-Jul-24 31-Jul-24 Cable Tray Installation

UCR-17-ECT.115 Cable Tray Inspection 10 31-Jul-24 12-Aug-24 Cable Tray Inspection

UCR-17-ECT.125 LV Cable pulling 10 12-Aug-24 24-Aug-24 LV Cable pulling

UCR-17-ECT.135 LV Cable Termination 10 24-Aug-24 04-Sep-24 LV Cable Termination

UCR-17-ECT.145 LV Cable Initial Testing 8 04-Sep-24 14-Sep-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 17-Aug-24 01-Oct-24 01-Oct-24, SMALL POWER SYSTEM


UCR-17-ESP.105 Small Power Conduit and boxes Installation 12 17-Aug-24 31-Aug-24 Small Power Conduit and boxes Installation

UCR-17-ESP.115 Small Power Cable Pulling 10 31-Aug-24 11-Sep-24 Small Power Cable Pulling

UCR-17-ESP.125 Small Power Installations 6 11-Sep-24 18-Sep-24 Small Power Installations

UCR-17-ESP.135 Small Power Termination 6 18-Sep-24 26-Sep-24 Small Power Termination

UCR-17-ESP.145 Small Power Initial Testing 5 26-Sep-24 01-Oct-24 Small Power Initial Testing

POWER DISTRIBUTION 44 17-Aug-24 08-Oct-24 08-Oct-24, POWER DISTRIBUTION


GENERATOR 39 17-Aug-24 02-Oct-24 02-Oct-24, GENERATOR
UCR-17-EPD.105 Generator Cable Tray Installation 7 17-Aug-24 25-Aug-24 Generator Cable Tray Installation

UCR-17-EPD.115 Generator Cable Pulling 7 25-Aug-24 02-Sep-24 Generator Cable Pulling

UCR-17-EPD.125 Generator Cell Pannel Installation 7 02-Sep-24 10-Sep-24 Generator Cell Pannel Installation

UCR-17-EPD.135 Generator Installation 7 10-Sep-24 18-Sep-24 Generator Installation

UCR-17-EPD.145 Generator Pannel / Cable Termination 7 18-Sep-24 26-Sep-24 Generator Pannel / Cable Termination

UCR-17-EPD.155 Generator Pannel / Cable initial Testing 5 28-Sep-24 02-Oct-24 Generator Pannel / Cable initial Testing

UPS 28 31-Aug-24 03-Oct-24 03-Oct-24, UPS


UCR-17-EPD.165 UPS Cable Tray Installation 5 31-Aug-24 05-Sep-24 UPS Cable Tray Installation

UCR-17-EPD.175 UPS Cable Pulling 5 05-Sep-24 11-Sep-24 UPS Cable Pulling

UCR-17-EPD.185 UPS Pannel Installation 5 11-Sep-24 17-Sep-24 UPS Pannel Installation

UCR-17-EPD.195 UPS Installation 5 17-Sep-24 22-Sep-24 UPS Installation

UCR-17-EPD.205 UPS Pannel / Cable Termination 5 24-Sep-24 29-Sep-24 UPS Pannel / Cable Termination

UCR-17-EPD.215 UPS Pannel / Cable initial Testing 4 29-Sep-24 03-Oct-24 UPS Pannel / Cable initial Testing

MDB 33 31-Aug-24 08-Oct-24 08-Oct-24, MDB


UCR-17-EPD.225 MDB Cable Tray Installation 7 31-Aug-24 08-Sep-24 MDB Cable Tray Installation

UCR-17-EPD.235 MDB Cable Pulling 7 08-Sep-24 16-Sep-24 MDB Cable Pulling

UCR-17-EPD.245 MDB Pannel Installation 7 16-Sep-24 25-Sep-24 MDB Pannel Installation

UCR-17-EPD.255 MDB Pannel / Cable Termination 7 25-Sep-24 02-Oct-24 MDB Pannel / Cable Termination

UCR-17-EPD.265 MDB Pannel / Cable initial Testing 5 03-Oct-24 08-Oct-24 MDB Pannel / Cable initial Testing

MCC 33 31-Aug-24 08-Oct-24 08-Oct-24, MCC


UCR-17-EPD.325 MCC Cable Tray Installation 7 31-Aug-24 08-Sep-24 MCC Cable Tray Installation

UCR-17-EPD.335 MCC Cable Pulling 7 08-Sep-24 16-Sep-24 MCC Cable Pulling

UCR-17-EPD.345 MCC Pannel Installation 7 16-Sep-24 25-Sep-24 MCC Pannel Installation

UCR-17-EPD.355 MCC Pannel / Cable Termination 7 25-Sep-24 02-Oct-24 MCC Pannel / Cable Termination

UCR-17-EPD.365 MCC Pannel / Cable initial Testing 5 03-Oct-24 08-Oct-24 MCC Pannel / Cable initial Testing

SMSB 24 31-Aug-24 28-Sep-24 28-Sep-24, SMSB


UCR-17-EPD.275 SMSB Cable Tray Installation 5 31-Aug-24 05-Sep-24 SMSB Cable Tray Installation

UCR-17-EPD.285 SMSB Cable Pulling 5 05-Sep-24 11-Sep-24 SMSB Cable Pulling

UCR-17-EPD.295 SMSB Pannel Installation 5 11-Sep-24 17-Sep-24 SMSB Pannel Installation

UCR-17-EPD.305 SMSB Pannel / Cable Termination 5 17-Sep-24 22-Sep-24 SMSB Pannel / Cable Termination

UCR-17-EPD.315 SMSB Pannel / Cable initial Testing 4 24-Sep-24 28-Sep-24 SMSB Pannel / Cable initial Testing

DB 24 31-Aug-24 28-Sep-24 28-Sep-24, DB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
158 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-17-EPD.375 DB Cable Tray Installation 5 31-Aug-24 05-Sep-24 DB Cable Tray Installation

UCR-17-EPD.385 DB Cable Pulling 5 05-Sep-24 11-Sep-24 DB Cable Pulling

UCR-17-EPD.395 DB Pannel Installation 5 11-Sep-24 17-Sep-24 DB Pannel Installation

UCR-17-EPD.405 DB Pannel / Cable Termination 5 17-Sep-24 22-Sep-24 DB Pannel / Cable Termination

UCR-17-EPD.415 DB Pannel / Cable initial Testing 4 24-Sep-24 28-Sep-24 DB Pannel / Cable initial Testing

ISOLATOR 24 31-Aug-24 28-Sep-24 28-Sep-24, ISOLATOR


UCR-17-EPD.425 Isolators Cable Tray Installation 5 31-Aug-24 05-Sep-24 Isolators Cable Tray Installation

UCR-17-EPD.435 Isolators Cable Pulling 5 05-Sep-24 11-Sep-24 Isolators Cable Pulling

UCR-17-EPD.445 Isolators Pannel Installation 5 11-Sep-24 17-Sep-24 Isolators Pannel Installation

UCR-17-EPD.455 Isolators Pannel / Cable Termination 5 17-Sep-24 22-Sep-24 Isolators Pannel / Cable Termination

UCR-17-EPD.465 Isolators Pannel / Cable initial Testing 4 24-Sep-24 28-Sep-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 31-Aug-24 28-Sep-24 28-Sep-24, LCP/ ELCP


UCR-17-EPD.475 LCP/ELCP Cable Tray Installation 5 31-Aug-24 05-Sep-24 LCP/ELCP Cable Tray Installation

UCR-17-EPD.485 LCP/ELCP Cable Pulling 5 05-Sep-24 11-Sep-24 LCP/ELCP Cable Pulling

UCR-17-EPD.495 LCP/ELCP Pannel Installation 5 11-Sep-24 17-Sep-24 LCP/ELCP Pannel Installation

UCR-17-EPD.505 LCP/ELCP Pannel / Cable Termination 5 17-Sep-24 22-Sep-24 LCP/ELCP Pannel / Cable Termination

UCR-17-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 24-Sep-24 28-Sep-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 42 26-Sep-24 13-Nov-24 13-Nov-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 26-Sep-24 13-Nov-24 13-Nov-24, FIRE ALARM SYSTEM
UCR-17-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 Fire Alarm Conduit /Cable Tray Installation

UCR-17-ELFA.115 Fire Alarm Cable Pulling 9 07-Oct-24 16-Oct-24 Fire Alarm Cable Pulling

UCR-17-ELFA.125 Fire Alarm Devices Installation 9 16-Oct-24 27-Oct-24 Fire Alarm Devices Installation

UCR-17-ELFA.135 Fire Alarm Devices and Cable Termination 9 27-Oct-24 06-Nov-24 Fire Alarm Devices and Cable Termination

UCR-17-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 26-Sep-24 13-Nov-24 13-Nov-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
UCR-17-ELVS.105 ICT System Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 ICT System Conduit /Cable Tray Installation

UCR-17-ELVS.115 ICT System Cable Pulling 9 07-Oct-24 16-Oct-24 ICT System Cable Pulling

UCR-17-ELVS.125 ICT System Devices Installation 9 16-Oct-24 27-Oct-24 ICT System Devices Installation

UCR-17-ELVS.135 ICT System Devices and Cable Termination 9 27-Oct-24 06-Nov-24 ICT System Devices and Cable Termination

UCR-17-ELVS.145 ICT System Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 26-Sep-24 13-Nov-24 13-Nov-24, ACCESS CONTROL SYSTEM


UCR-17-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 Access Control System Conduit /Cable Tray Installation

UCR-17-ELAC.115 Access Control System Cable Pulling 9 07-Oct-24 16-Oct-24 Access Control System Cable Pulling

UCR-17-ELAC.125 Access Control System Devices Installation 9 16-Oct-24 27-Oct-24 Access Control System Devices Installation

UCR-17-ELAC.135 Access Control System Devices and Cable Termination 9 27-Oct-24 06-Nov-24 Access Control System Devices and Cable Termination

UCR-17-ELAC.145 Access Control System Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 26-Sep-24 13-Nov-24 13-Nov-24, PUBLIC ADDRESS SYSTEM


UCR-17-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 Public Address System Conduit /Cable Tray Installation

UCR-17-ELPA.115 Public Address System Cable Pulling 9 07-Oct-24 16-Oct-24 Public Address System Cable Pulling

UCR-17-ELPA.125 Public Address System Devices Installation 9 16-Oct-24 27-Oct-24 Public Address System Devices Installation

UCR-17-ELPA.135 Public Address System Devices and Cable Termination 9 27-Oct-24 06-Nov-24 Public Address System Devices and Cable Termination

UCR-17-ELPA.145 Public Address System Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 26-Sep-24 13-Nov-24 13-Nov-24, SCADA SYSTEM


UCR-17-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 SCADA System Conduit /Cable Tray Installation

UCR-17-ELSC.115 SCADA System Cable Pulling 9 07-Oct-24 16-Oct-24 SCADA System Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
159 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UCR-17-ELSC.125 SCADA System Devices Installation 9 16-Oct-24 27-Oct-24 SCADA System Devices Installation

UCR-17-ELSC.135 SCADA System Devices and Cable Termination 9 27-Oct-24 06-Nov-24 SCADA System Devices and Cable Termination

UCR-17-ELSC.145 SCADA System Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 26-Sep-24 13-Nov-24 13-Nov-24, RADIO RE- BROADCOASTING/ TETRA
UCR-17-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 26-Sep-24 06-Oct-24 Radio/TETRA System Conduit /Cable Tray Installation

UCR-17-ELRD.115 Radio/TETRA System Cable Pulling 9 07-Oct-24 16-Oct-24 Radio/TETRA System Cable Pulling

UCR-17-ELRD.125 Radio/TETRA System Devices Installation 9 16-Oct-24 27-Oct-24 Radio/TETRA System Devices Installation

UCR-17-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 27-Oct-24 06-Nov-24 Radio/TETRA System Devices and Cable Termination

UCR-17-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 06-Nov-24 13-Nov-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK IN UCR 15 08-Sep-24 26-Sep-24 26-Sep-24, MECHANICAL WORK IN UCR


FIRE FIGHTING 13 08-Sep-24 24-Sep-24 24-Sep-24, FIRE FIGHTING
UCR-17-MFF.105 Fire Fighting system Pipe and accessories installation 11 08-Sep-24 21-Sep-24 Fire Fighting system Pipe and accessories installation

UCR-17-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 17-Sep-24 21-Sep-24 Fire Fighting system fire hose cabinet/extingusher installation

UCR-17-MFF.135 Fire Fighting system initial testing 2 21-Sep-24 24-Sep-24 Fire Fighting system initial testing

HVAC 15 08-Sep-24 26-Sep-24 26-Sep-24, HVAC


UCR-17-MHV.105 Duct and accessories installation 12 08-Sep-24 22-Sep-24 Duct and accessories installation

UCR-17-MHV.115 Fan installation 4 17-Sep-24 22-Sep-24 Fan installation

UCR-17-MHV.135 HVAC inital testing 3 22-Sep-24 26-Sep-24 HVAC inital testing

PLUMBING 4 08-Sep-24 12-Sep-24 12-Sep-24, PLUMBING


UCR-17-MPL.105 Plumbing drainage system installation 3 08-Sep-24 11-Sep-24 Plumbing drainage system installation

UCR-17-MPL.115 Plumbing drainage system initial testing 1 11-Sep-24 12-Sep-24 Plumbing drainage system initial testing

DRY UTILITIES 18 08-Sep-24 29-Sep-24 29-Sep-24, DRY UTILITIES


POWER 18 08-Sep-24 29-Sep-24 29-Sep-24, POWER
POWER LV 16 08-Sep-24 28-Sep-24 28-Sep-24, POWER LV
DU-P-LV.3400 Installation of support 1 08-Sep-24 09-Sep-24 Installation of support

DU-P-LV.3405 Installation of horizontal busbar 2 09-Sep-24 10-Sep-24 Installation of horizontal busbar

DU-P-LV.3410 Installation of vertical busbar 2 10-Sep-24 12-Sep-24 Installation of vertical busbar

DU-P-LV.3415 Installation of left/right elbow 2 12-Sep-24 14-Sep-24 Installation of left/right elbow

DU-P-LV.3420 Installation of right horizintal offset 2 14-Sep-24 16-Sep-24 Installation of right horizintal offset

DU-P-LV.3425 Instalaltion of upward vertical offset 3 16-Sep-24 19-Sep-24 Instalaltion of upward vertical offset

DU-P-LV.3430 Installation of downward vertical offset 3 19-Sep-24 24-Sep-24 Installation of downward vertical offset

DU-P-LV.3435 Installation of transformer and panel connection 2 24-Sep-24 28-Sep-24 Installation of transformer and panel connection

MEDIUM VOLTAGE 18 08-Sep-24 29-Sep-24 29-Sep-24, MEDIUM VOLTAGE


DU-P-MV.3400 Installation of cable try, arm, racks and ladder 6 08-Sep-24 15-Sep-24 Installation of cable try, arm, racks and ladder

DU-P-MV.3405 Installation of MV Cable 4 15-Sep-24 19-Sep-24 Installation of MV Cable

DU-P-MV.3410 Installation of cable cleats 2 19-Sep-24 22-Sep-24 Installation of cable cleats

DU-P-MV.3415 Installation of gland 1 22-Sep-24 24-Sep-24 Installation of gland

DU-P-MV.3420 splicing/termination of MV cable 2 24-Sep-24 25-Sep-24 splicing/termination of MV cable

DU-P-MV.3425 Testing and Pre-commissioning of cable 2 25-Sep-24 28-Sep-24 Testing and Pre-commissioning of cable

DU-P-MV.3430 Energezation 2 28-Sep-24 29-Sep-24 Energezation

TRANSFORMER 16 08-Sep-24 28-Sep-24 28-Sep-24, TRANSFORMER


DU-P-T.3400 Installation of Transformer unit 2 08-Sep-24 09-Sep-24 Installation of Transformer unit

DU-P-T.3405 Testing and Pre-Commissioning of unit 1 09-Sep-24 10-Sep-24 Testing and Pre-Commissioning of unit

DU-P-T.3410 Termination and Splicing of MV Cable 3 10-Sep-24 14-Sep-24 Termination and Splicing of MV Cable

DU-P-T.3415 Termination and Splicing of LV Cable/bus way 3 14-Sep-24 18-Sep-24 Termination and Splicing of LV Cable/bus way

DU-P-T.3420 Installation and connection of I/O system 2 18-Sep-24 21-Sep-24 Installation and connection of I/O system

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
160 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DU-P-T.3425 Installation of Grounding and Protection System 2 21-Sep-24 24-Sep-24 Installation of Grounding and Protection System

DU-P-T.3430 Testing and Commissioning of MV System 1 24-Sep-24 25-Sep-24 Testing and Commissioning of MV System

DU-P-T.3435 Testing and Commissioning of LV System 1 25-Sep-24 26-Sep-24 Testing and Commissioning of LV System

DU-P-T.3440 Energezation 1 26-Sep-24 28-Sep-24 Energezation

RMU 16 08-Sep-24 28-Sep-24 28-Sep-24, RMU


DU-P-RMU.3400 Installation RMU unit 2 08-Sep-24 10-Sep-24 Installation RMU unit

DU-P-RMU.3405 Testing and Pre-Commissioning of unit 2 10-Sep-24 12-Sep-24 Testing and Pre-Commissioning of unit

DU-P-RMU.3410 Termination and Splicing of Ring-MV Cable 4 12-Sep-24 17-Sep-24 Termination and Splicing of Ring-MV Cable

DU-P-RMU.3415 Termination and Splicing of T-MV Cable 4 17-Sep-24 22-Sep-24 Termination and Splicing of T-MV Cable

DU-P-RMU.3420 Installation of Grounding and Protection System 2 22-Sep-24 25-Sep-24 Installation of Grounding and Protection System

DU-P-RMU.3425 Testing and Commissioning of MV System 1 25-Sep-24 26-Sep-24 Testing and Commissioning of MV System

DU-P-RMU.3430 Energezation 1 26-Sep-24 28-Sep-24 Energezation

LIFTSTATION 460 09-May-23 10-Nov-24 10-Nov-24, LIFTSTATION


lIFTING STATION 02 (IN ZONE 06) 443 24-May-23 05-Nov-24 05-Nov-24, lIFTING STATION 02 (IN ZONE 06)
ENGINEERING 95 24-May-23 16-Sep-23 16-Sep-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 95 24-May-23 16-Sep-23 16-Sep-23, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 28 24-Jun-23 29-Jul-23 29-Jul-23, EARTH WORKS
LS2-EN-SD-EW.100 Shoring Design Preparation & Submission 14 24-Jun-23 12-Jul-23 Shoring Design Preparation & Submission

LS2-EN-SD-EW.105 Soil Improvement Design Preparation & Submission 14 24-Jun-23 12-Jul-23 Soil Improvement Design Preparation & Submission

LS2-EN-SD-EW.110 Shoring Design Review & Approval 14 12-Jul-23 29-Jul-23 Shoring Design Review & Approval

LS2-EN-SD-EW.115 Soil Improvement Design Review & Approval 14 12-Jul-23 29-Jul-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


LS2-EN-SD-STR.100 Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

LS2-EN-SD-STR.105 Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

LS2-EN-SD-STR.110 Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

LS2-EN-SD-STR.115 Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

LS2-EN-SD-STR.120 Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

LS2-EN-SD-STR.125 Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
LS2-EN-SD-M-FFS.100
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

LS2-EN-SD-M-FFS.105
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
LS2-EN-SD-M-VEN.100
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

LS2-EN-SD-M-VEN.105
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


LS2-EN-SD-M-PS.100Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

LS2-EN-SD-M-PS.105Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 95 24-May-23 16-Sep-23 16-Sep-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
LS2-EN-SD-E-CT.100Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

LS2-EN-SD-E-CT.105Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


LS2-EN-SD-E-PC.100Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

LS2-EN-SD-E-PC.105Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


LS2-EN-SD-E-LS.100Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

LS2-EN-SD-E-LS.105Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
161 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS
LS2-EN-SD-E-EI.100 Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

LS2-EN-SD-E-EI.105 Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 15-Jul-23 14-Aug-23 14-Aug-23, LIGHTNING PROTECTION SYSTEM


LS2-EN-SD-E-LPS.100Lightning Protection Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Lightning Protection Drawings Preparation & Submission

LS2-EN-SD-E-LPS.105Lightning Protection Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, EARTHING SYSTEM


LS2-EN-SD-E-ES.100Earthing System Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Earthing System Shop Drawings Preparation & Submission

LS2-EN-SD-E-ES.105Earthing System Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Earthing System Drawings Review & Approval

LOW CURRENT 95 24-May-23 16-Sep-23 16-Sep-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
LS2-EN-SD-LC-FD.100
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

LS2-EN-SD-LC-FD.105
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
LS2-EN-SD-LC-CS.100
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

LS2-EN-SD-LC-CS.105
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
LS2-EN-SD-LC-VE.100
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

LS2-EN-SD-LC-VE.105
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


LS2-EN-SD-LC-VS.100
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

LS2-EN-SD-LC-VS.105
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


LS2-EN-SD-LC-ACS.100
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

LS2-EN-SD-LC-ACS.105
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


LS2-EN-SD-LC-RRB.100
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

LS2-EN-SD-LC-RRB.105
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, SCADA SYSTEM


LS2-EN-SD-LC-SS.100
SCADA system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 SCADA system Shop Drawings Preparation & Submission

LS2-EN-SD-LC-SS.105
SCADA system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 SCADA system Shop Drawings Review & Approval

PROCUREMENT 299 01-Nov-23 24-Oct-24 24-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 01-Nov-23 20-Nov-23 20-Nov-23, CIVIL/STRUCTURAL
LS2-EN-PR-CS.100 Issue Purchase Order 6 01-Nov-23 08-Nov-23 Issue Purchase Order

LS2-EN-PR-CS.105 Material Delivery 10 08-Nov-23 20-Nov-23 Material Delivery

MECHANICAL 128 22-May-24 24-Oct-24 24-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 22-May-24 28-Sep-24 28-Sep-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 22-May-24 28-Sep-24 28-Sep-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
LS2-EN-PR-M-FFS.100
Issue Purchase Order 15 22-May-24 09-Jun-24 Issue Purchase Order

LS2-EN-PR-M-FFS.105
Material Delivery 90 09-Jun-24 28-Sep-24 Material Delivery

VENTILATION SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 04-Jun-24 10-Oct-24 10-Oct-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
LS2-EN-PR-M-VS.100Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

LS2-EN-PR-M-VS.105Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

AIR CONDITIONING WORKS 105 04-Jun-24 10-Oct-24 10-Oct-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 04-Jun-24 10-Oct-24 10-Oct-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
LS2-EN-PR-M-ACW.100
Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

LS2-EN-PR-M-ACW.105
Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

PLUMBING SYSTEM 105 23-Jun-24 24-Oct-24 24-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 23-Jun-24 24-Oct-24 24-Oct-24, PUMPS,PIPES,FITTINGS,VALVES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
162 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-EN-PR-M-PS.100Issue Purchase Order 15 23-Jun-24 10-Jul-24 Issue Purchase Order

LS2-EN-PR-M-PS.105Material Delivery 90 10-Jul-24 24-Oct-24 Material Delivery

ELECTRICAL 162 03-Mar-24 16-Sep-24 16-Sep-24, ELECTRICAL


CABLE TRAY 105 03-Mar-24 11-Jul-24 11-Jul-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 03-Mar-24 11-Jul-24 11-Jul-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
LS2-EN-PR-E-CT.100 Issue Purchase Order 15 03-Mar-24 20-Mar-24 Issue Purchase Order

LS2-EN-PR-E-CT.105 Material Delivery 90 20-Mar-24 11-Jul-24 Material Delivery

POWER CABLES 105 26-Mar-24 04-Aug-24 04-Aug-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 26-Mar-24 04-Aug-24 04-Aug-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
LS2-EN-PR-E-PC.100Issue Purchase Order 15 26-Mar-24 16-Apr-24 Issue Purchase Order

LS2-EN-PR-E-PC.105Material Delivery 90 16-Apr-24 04-Aug-24 Material Delivery

LIGHTING SYSTEM 105 03-Mar-24 11-Jul-24 11-Jul-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 03-Mar-24 11-Jul-24 11-Jul-24, CONDUIT,LIGHT
LS2-EN-PR-E-LS.100 Issue Purchase Order 15 03-Mar-24 20-Mar-24 Issue Purchase Order

LS2-EN-PR-E-LS.105 Material Delivery 90 20-Mar-24 11-Jul-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 26-Mar-24 04-Aug-24 04-Aug-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 26-Mar-24 04-Aug-24 04-Aug-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
LS2-EN-PR-E-EI.100 Issue Purchase Order 15 26-Mar-24 16-Apr-24 Issue Purchase Order

LS2-EN-PR-E-EI.105 Material Delivery 90 16-Apr-24 04-Aug-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 26-Mar-24 04-Aug-24 04-Aug-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 26-Mar-24 04-Aug-24 04-Aug-24, LIGHTNING PROTECTION SYSTEM
LS2-EN-PR-E-LPS.100Issue Purchase Order 15 26-Mar-24 16-Apr-24 Issue Purchase Order

LS2-EN-PR-E-LPS.105Material Delivery 90 16-Apr-24 04-Aug-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 03-Mar-24 11-Jul-24 11-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 03-Mar-24 11-Jul-24 11-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
LS2-EN-PR-E-ES.100 Issue Purchase Order 15 03-Mar-24 20-Mar-24 Issue Purchase Order

LS2-EN-PR-E-ES.105 Material Delivery 90 20-Mar-24 11-Jul-24 Material Delivery

LOW CURRENT 114 02-May-24 16-Sep-24 16-Sep-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 02-May-24 05-Sep-24 05-Sep-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 02-May-24 05-Sep-24 05-Sep-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
LS2-EN-PR-LC-FDA.100
Issue Purchase Order 15 02-May-24 19-May-24 Issue Purchase Order

LS2-EN-PR-LC-FDA.105
Material Delivery 90 20-May-24 05-Sep-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 02-May-24 05-Sep-24 05-Sep-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 02-May-24 05-Sep-24 05-Sep-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
LS2-EN-PR-LC-UTP.100
Issue Purchase Order 15 02-May-24 19-May-24 Issue Purchase Order

LS2-EN-PR-LC-UTP.105
Material Delivery 90 20-May-24 05-Sep-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 12-May-24 16-Sep-24 16-Sep-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
LS2-EN-PR-LC-VE.100
Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

LS2-EN-PR-LC-VE.105
Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

VIDEO SURVEILLANCE 105 02-May-24 05-Sep-24 05-Sep-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 02-May-24 05-Sep-24 05-Sep-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
LS2-EN-PR-LC-VS.100
Issue Purchase Order 15 02-May-24 19-May-24 Issue Purchase Order

LS2-EN-PR-LC-VS.105
Material Delivery 90 20-May-24 05-Sep-24 Material Delivery

ACCESS CONTROL SYSTEM 105 02-May-24 05-Sep-24 05-Sep-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 02-May-24 05-Sep-24 05-Sep-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
LS2-EN-PR-LC-ACS.100
Issue Purchase Order 15 02-May-24 19-May-24 Issue Purchase Order

LS2-EN-PR-LC-ACS.105
Material Delivery 90 20-May-24 05-Sep-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 12-May-24 16-Sep-24 16-Sep-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
LS2-EN-PR-LC-RRB.100
Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
163 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-EN-PR-LC-RRB.105
Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

SCADA SYSTEM 105 12-May-24 16-Sep-24 16-Sep-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 12-May-24 16-Sep-24 16-Sep-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
LS2-EN-PR-LC-SS.100
Issue Purchase Order 15 12-May-24 29-May-24 Issue Purchase Order

LS2-EN-PR-LC-SS.105
Material Delivery 90 29-May-24 16-Sep-24 Material Delivery

CONSTRUCTION 404 12-Jul-23 05-Nov-24 05-Nov-24, CONSTRUCTION


EXCAVATION WORKS 91 12-Jul-23 28-Oct-23 28-Oct-23, EXCAVATION WORKS
LS2-EN-CON-EW.100 Excavation 91 12-Jul-23 28-Oct-23 Excavation

SHORING WORKS 0 12-Jul-23 12-Jul-23 12-Jul-23, SHORING WORKS


LS2-EN-CON-SW.100 Piles 0 12-Jul-23 12-Jul-23 Piles

LS2-EN-CON-SW.105 Capping Beam 0 12-Jul-23 12-Jul-23 Capping Beam

LS2-EN-CON-SW.110 Anchore 0 12-Jul-23 12-Jul-23 Anchore

SOIL IMPROVEMENT WORKS 20 28-Oct-23 20-Nov-23 20-Nov-23, SOIL IMPROVEMENT WORKS


LS2-EN-CON-SIW.100 Soil Improvement 20 28-Oct-23 20-Nov-23 Soil Improvement

STRUCTURAL WORKS 248 20-Nov-23 12-Sep-24 12-Sep-24, STRUCTURAL WORKS


FOUNDATION 17 20-Nov-23 10-Dec-23 10-Dec-23, FOUNDATION
Part-1 17 20-Nov-23 10-Dec-23 10-Dec-23, Part-1
LS2-EN-CON-SW-FP1.10
Foundation Blinding concrete casting 1 20-Nov-23 21-Nov-23 Foundation Blinding concrete casting

LS2-EN-CON-SW-FP1.15
Foundation water proofing on blinding concrete 2 21-Nov-23 23-Nov-23 Foundation water proofing on blinding concrete

LS2-EN-CON-SW-FP1.20
Foundation Protection screed on water poofing 1 23-Nov-23 25-Nov-23 Foundation Protection screed on water poofing

LS2-EN-CON-SW-FP1.25
Foundation Curing for screed 1 25-Nov-23 26-Nov-23 Foundation Curing for screed

LS2-EN-CON-SW-FP1.30
Foundation Rebar installation 5 26-Nov-23 02-Dec-23 Foundation Rebar installation

LS2-EN-CON-SW-FP1.35
Foundation Formwork installation 4 02-Dec-23 06-Dec-23 Foundation Formwork installation

LS2-EN-CON-SW-FP1.45
Foundation concrete casting 1 06-Dec-23 07-Dec-23 Foundation concrete casting

LS2-EN-CON-SW-FP1.50
Foundation concrete curing 1 07-Dec-23 09-Dec-23 Foundation concrete curing

LS2-EN-CON-SW-FP1.55
Foundation Formwork Removal 1 09-Dec-23 10-Dec-23 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 21 07-Dec-23 01-Jan-24 01-Jan-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 21 07-Dec-23 01-Jan-24 01-Jan-24, WALL CONCRETE CASTING STAGE-1
Part-1 21 07-Dec-23 01-Jan-24 01-Jan-24, Part-1
LS2-EN-CON-SW-WWC.10
Room Walls Scafolding for rebar 3 07-Dec-23 11-Dec-23 Room Walls Scafolding for rebar

LS2-EN-CON-SW-WWC.15
Room Walls Rebar Installation 6 11-Dec-23 18-Dec-23 Room Walls Rebar Installation

LS2-EN-CON-SW-WWC.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 18-Dec-23 19-Dec-23 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS2-EN-CON-SW-WWC.25
Room Walls Formwork Installation 7 19-Dec-23 27-Dec-23 Room Walls Formwork Installation

LS2-EN-CON-SW-WWC.30
Room Walls Concrete Casting 1 27-Dec-23 28-Dec-23 Room Walls Concrete Casting

LS2-EN-CON-SW-WWC.35
Room Walls Curing work 1 28-Dec-23 30-Dec-23 Room Walls Curing work

LS2-EN-CON-SW-WWC.40
Room Walls Formwork Removel 2 30-Dec-23 01-Jan-24 Room Walls Formwork Removel

MIDDLE SLAB 37 01-Jan-24 13-Feb-24 13-Feb-24, MIDDLE SLAB


Part-1 37 01-Jan-24 13-Feb-24 13-Feb-24, Part-1
LS2-EN-CON-SW-MP1.10
Room Top Slab Formwork Installation 12 01-Jan-24 15-Jan-24 Room Top Slab Formwork Installation

LS2-EN-CON-SW-MP1.15
Room Top Slab Rebar Installation 8 15-Jan-24 24-Jan-24 Room Top Slab Rebar Installation

LS2-EN-CON-SW-MP1.20
Room Top Slab Concrete Casting 1 24-Jan-24 25-Jan-24 Room Top Slab Concrete Casting

LS2-EN-CON-SW-MP1.25
Room Top slab Curing work 12 25-Jan-24 08-Feb-24 Room Top slab Curing work

LS2-EN-CON-SW-MP1.30
Room Top Slab Formwork Removel 4 08-Feb-24 13-Feb-24 Room Top Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 20 13-Feb-24 07-Mar-24 07-Mar-24, WALL CONCRETE CASTING STAGE-2
Part-1 20 13-Feb-24 07-Mar-24 07-Mar-24, Part-1
LS2-EN-CON-SW-WP1.10
Room Walls Scafolding for rebar 3 13-Feb-24 17-Feb-24 Room Walls Scafolding for rebar

LS2-EN-CON-SW-WP1.15
Room Walls Rebar Installation 5 17-Feb-24 22-Feb-24 Room Walls Rebar Installation

LS2-EN-CON-SW-WP1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 22-Feb-24 24-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
164 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-EN-CON-SW-WP1.25
Room Walls Formwork Installation 7 24-Feb-24 03-Mar-24 Room Walls Formwork Installation

LS2-EN-CON-SW-WP1.30
Room Walls Concrete Casting 1 03-Mar-24 04-Mar-24 Room Walls Concrete Casting

LS2-EN-CON-SW-WP1.35
Room Walls Curing work 1 04-Mar-24 05-Mar-24 Room Walls Curing work

LS2-EN-CON-SW-WP1.40
Room Walls Formwork Removel 2 05-Mar-24 07-Mar-24 Room Walls Formwork Removel

TOP SLAB BELOW GROUND LEVEL 37 07-Mar-24 23-Apr-24 23-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 07-Mar-24 23-Apr-24 23-Apr-24, Part-1
LS2-EN-CON-SW-TP1.10
Room Top Slab Formwork Installation 12 07-Mar-24 21-Mar-24 Room Top Slab Formwork Installation

LS2-EN-CON-SW-TP1.15
Room Top Slab Rebar Installation 8 21-Mar-24 31-Mar-24 Room Top Slab Rebar Installation

LS2-EN-CON-SW-TP1.20
Room Top Slab Concrete Casting 1 31-Mar-24 01-Apr-24 Room Top Slab Concrete Casting

LS2-EN-CON-SW-TP1.25
Room Top slab Curing work 12 01-Apr-24 18-Apr-24 Room Top slab Curing work

LS2-EN-CON-SW-TP1.30
Room Top Slab Formwork Removel 4 18-Apr-24 23-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 17 18-Apr-24 08-May-24 08-May-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-3 17 18-Apr-24 08-May-24 08-May-24, WALL CONCRETE CASTING STAGE-3
Part-1 17 18-Apr-24 08-May-24 08-May-24, Part-1
LS2-CON-SW-S3P1.10
Room Walls Scafolding for rebar 3 18-Apr-24 22-Apr-24 Room Walls Scafolding for rebar

LS2-CON-SW-S3P1.15
Room Walls Rebar Installation 4 22-Apr-24 27-Apr-24 Room Walls Rebar Installation

LS2-CON-SW-S3P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 27-Apr-24 28-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS2-CON-SW-S3P1.25
Room Walls Formwork Installation 5 28-Apr-24 04-May-24 Room Walls Formwork Installation

LS2-CON-SW-S3P1.30
Room Walls Concrete Casting 1 04-May-24 05-May-24 Room Walls Concrete Casting

LS2-CON-SW-S3P1.35
Room Walls Curing work 1 05-May-24 06-May-24 Room Walls Curing work

LS2-CON-SW-S3P1.40
Room Walls Formwork Removel 2 06-May-24 08-May-24 Room Walls Formwork Removel

WALL CONCRETE CASTING STAGE-4 18 08-May-24 29-May-24 29-May-24, WALL CONCRETE CASTING STAGE-4
Part-1 18 08-May-24 29-May-24 29-May-24, Part-1
LS2-CON-SW-WS4P1.10
Room Walls Scafolding for rebar 3 08-May-24 12-May-24 Room Walls Scafolding for rebar

LS2-CON-SW-WS4P1.15
Room Walls Rebar Installation 4 12-May-24 16-May-24 Room Walls Rebar Installation

LS2-CON-SW-WS4P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 16-May-24 18-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS2-CON-SW-WS4P1.25
Room Walls Formwork Installation 6 18-May-24 25-May-24 Room Walls Formwork Installation

LS2-CON-SW-WS4P1.30
Room Walls Concrete Casting 1 25-May-24 26-May-24 Room Walls Concrete Casting

LS2-CON-SW-WS4P1.35
Room Walls Curing work 1 26-May-24 27-May-24 Room Walls Curing work

LS2-CON-SW-WS4P1.40
Room Walls Formwork Removel 2 27-May-24 29-May-24 Room Walls Formwork Removel

SLAB ABOVE GROUND LEVEL 33 29-May-24 11-Jul-24 11-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 33 29-May-24 11-Jul-24 11-Jul-24, Part-1
LS2-CON-SW-SS4P1.10
Room Top Slab Formwork Installation 8 29-May-24 08-Jun-24 Room Top Slab Formwork Installation

LS2-CON-SW-SS4P1.15
Room Top Slab Rebar Installation 8 08-Jun-24 22-Jun-24 Room Top Slab Rebar Installation

LS2-CON-SW-SS4P1.20
Room Top Slab Concrete Casting 1 22-Jun-24 23-Jun-24 Room Top Slab Concrete Casting

LS2-CON-SW-SS4P1.25
Room Top slab Curing work 12 23-Jun-24 07-Jul-24 Room Top slab Curing work

LS2-CON-SW-SS4P1.30
Room Top Slab Formwork Removel 4 07-Jul-24 11-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 45 11-Jul-24 02-Sep-24 02-Sep-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 11-Jul-24 23-Jul-24 23-Jul-24, WALL WATER PROOFING STAGE-1
LS2-CON-SW-WWWS1.10
Surface preparation work 2 11-Jul-24 14-Jul-24 Surface preparation work

LS2-CON-SW-WWWS1.15
Applying of waterproofing material &Membrane Protection work 2 14-Jul-24 16-Jul-24 Applying of waterproofing material &Membrane Protection work

LS2-CON-SW-WWWS1.20
L.S Back Filling 6 16-Jul-24 23-Jul-24 L.S Back Filling

WALL WATER PROOFING STAGE-2 10 23-Jul-24 04-Aug-24 04-Aug-24, WALL WATER PROOFING STAGE-2
LS2-CON-SW-WWWS2.10
Surface preparation work 2 23-Jul-24 25-Jul-24 Surface preparation work

LS2-CON-SW-WWWS2.15
Applying of waterproofing material &Membrane Protection work 2 25-Jul-24 28-Jul-24 Applying of waterproofing material &Membrane Protection work

LS2-CON-SW-WWWS2.20
L.S Back Filling 6 28-Jul-24 04-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-3 10 04-Aug-24 15-Aug-24 15-Aug-24, WALL WATER PROOFING STAGE-3

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
165 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-CON-SW-WWWS3.10
Surface preparation work 2 04-Aug-24 06-Aug-24 Surface preparation work

LS2-CON-SW-WWWS3.15
Applying of waterproofing material &Membrane Protection work 2 06-Aug-24 08-Aug-24 Applying of waterproofing material &Membrane Protection work

LS2-CON-SW-WWWS3.20
L.S Back Filling 6 08-Aug-24 15-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-4 10 15-Aug-24 27-Aug-24 27-Aug-24, WALL WATER PROOFING STAGE-4
LS2-CON-SW-WWWS4.10
Surface preparation work 2 15-Aug-24 18-Aug-24 Surface preparation work

LS2-CON-SW-WWWS4.15
Applying of waterproofing material &Membrane Protection work 2 18-Aug-24 20-Aug-24 Applying of waterproofing material &Membrane Protection work

LS2-CON-SW-WWWS4.20
L.S Back Filling 6 20-Aug-24 27-Aug-24 L.S Back Filling

TOP SLAB WATER PROOFING 5 27-Aug-24 02-Sep-24 02-Sep-24, TOP SLAB WATER PROOFING
LS2-CON-SW-TSW.10Surface preparation work 2 27-Aug-24 29-Aug-24 Surface preparation work

LS2-CON-SW-TSW.15Applying of waterproofing material &Membrane Protection work 2 29-Aug-24 01-Sep-24 Applying of waterproofing material &Membrane Protection work

LS2-CON-SW-TSW.20Leak Test 1 01-Sep-24 02-Sep-24 Leak Test

PLAIN CONCRETE ABOVE SLAB 9 02-Sep-24 12-Sep-24 12-Sep-24, PLAIN CONCRETE ABOVE SLAB
Part-1 9 02-Sep-24 12-Sep-24 12-Sep-24, Part-1
LS2-CON-SW-PCP1.10
Plain Concrete Above Top Slab Formwork Installation 6 02-Sep-24 09-Sep-24 Plain Concrete Above Top Slab Formwork Installation

LS2-CON-SW-PCP1.15
Plain Concrete Casting 1 09-Sep-24 10-Sep-24 Plain Concrete Casting

LS2-CON-SW-PCP1.20
Plain Concrete curing work 1 10-Sep-24 11-Sep-24 Plain Concrete curing work

LS2-CON-SW-PCP1.25
Plain Concrete Formwork removal 1 11-Sep-24 12-Sep-24 Plain Concrete Formwork removal

MECHANICAL ROOM MEP (UCR) 99 11-Jul-24 05-Nov-24 05-Nov-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK 99 11-Jul-24 05-Nov-24 05-Nov-24, ELECTRICAL WORK
POWER SYSTEM 71 11-Jul-24 03-Oct-24 03-Oct-24, POWER SYSTEM
LIGHTING SYSTEM 37 11-Jul-24 24-Aug-24 24-Aug-24, LIGHTING SYSTEM
LS2-CON-M-EW-PSLS.10
Lighting system Conduit and boxes Installation 8 11-Jul-24 21-Jul-24 Lighting system Conduit and boxes Installation

LS2-CON-M-EW-PSLS.15
Lighting system Cable Pulling 8 21-Jul-24 30-Jul-24 Lighting system Cable Pulling

LS2-CON-M-EW-PSLS.20
Lighting system Installations 8 30-Jul-24 08-Aug-24 Lighting system Installations

LS2-CON-M-EW-PSLS.25
Lighting system Termination 8 08-Aug-24 18-Aug-24 Lighting system Termination

LS2-CON-M-EW-PSLS.30
Lighting system Initial Testing 5 18-Aug-24 24-Aug-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 11-Jul-24 05-Sep-24 05-Sep-24, CABLE TRAY /CABLE ROUTING SYSTEM
LS2-CON-M-EW-PSCT.10
Cable Tray Installation 10 11-Jul-24 23-Jul-24 Cable Tray Installation

LS2-CON-M-EW-PSCT.15
Cable Tray Inspection 10 23-Jul-24 04-Aug-24 Cable Tray Inspection

LS2-CON-M-EW-PSCT.20
LV Cable pulling 10 04-Aug-24 15-Aug-24 LV Cable pulling

LS2-CON-M-EW-PSCT.25
LV Cable Termination 10 15-Aug-24 27-Aug-24 LV Cable Termination

LS2-CON-M-EW-PSCT.30
LV Cable Initial Testing 8 27-Aug-24 05-Sep-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 21-Jul-24 04-Sep-24 04-Sep-24, SMALL POWER SYSTEM


LS2-CON-M-EW-PSSP.10
Small Power Conduit and boxes Installation 12 21-Jul-24 04-Aug-24 Small Power Conduit and boxes Installation

LS2-CON-M-EW-PSSP.15
Small Power Cable Pulling 10 04-Aug-24 15-Aug-24 Small Power Cable Pulling

LS2-CON-M-EW-PSSP.20
Small Power Installations 6 15-Aug-24 22-Aug-24 Small Power Installations

LS2-CON-M-EW-PSSP.25
Small Power Termination 6 22-Aug-24 29-Aug-24 Small Power Termination

LS2-CON-M-EW-PSSP.30
Small Power Initial Testing 5 29-Aug-24 04-Sep-24 Small Power Initial Testing

POWER DISTRIBUTION 51 04-Aug-24 03-Oct-24 03-Oct-24, POWER DISTRIBUTION


GENERATOR 39 04-Aug-24 18-Sep-24 18-Sep-24, GENERATOR
LS2-CON-M-E-PDGEN.10
Generator Cable Tray Installation 7 04-Aug-24 12-Aug-24 Generator Cable Tray Installation

LS2-CON-M-E-PDGEN.15
Generator Cable Pulling 7 12-Aug-24 20-Aug-24 Generator Cable Pulling

LS2-CON-M-E-PDGEN.20
Generator Cell Pannel Installation 7 20-Aug-24 28-Aug-24 Generator Cell Pannel Installation

LS2-CON-M-E-PDGEN.25
Generator Installation 7 28-Aug-24 05-Sep-24 Generator Installation

LS2-CON-M-E-PDGEN.30
Generator Pannel / Cable Termination 7 05-Sep-24 12-Sep-24 Generator Pannel / Cable Termination

LS2-CON-M-E-PDGEN.35
Generator Pannel / Cable initial Testing 5 14-Sep-24 18-Sep-24 Generator Pannel / Cable initial Testing

UPS 28 12-Aug-24 14-Sep-24 14-Sep-24, UPS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
166 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-CON-M-E-PDUPS.10
UPS Cable Tray Installation 5 12-Aug-24 18-Aug-24 UPS Cable Tray Installation

LS2-CON-M-E-PDUPS.15
UPS Cable Pulling 5 18-Aug-24 24-Aug-24 UPS Cable Pulling

LS2-CON-M-E-PDUPS.20
UPS Pannel Installation 5 24-Aug-24 29-Aug-24 UPS Pannel Installation

LS2-CON-M-E-PDUPS.25
UPS Installation 5 29-Aug-24 03-Sep-24 UPS Installation

LS2-CON-M-E-PDUPS.30
UPS Pannel / Cable Termination 5 04-Sep-24 09-Sep-24 UPS Pannel / Cable Termination

LS2-CON-M-E-PDUPS.35
UPS Pannel / Cable initial Testing 4 09-Sep-24 14-Sep-24 UPS Pannel / Cable initial Testing

MDB 33 18-Aug-24 25-Sep-24 25-Sep-24, MDB


LS2-CON-M-E-PDMDB.10
MDB Cable Tray Installation 7 18-Aug-24 26-Aug-24 MDB Cable Tray Installation

LS2-CON-M-E-PDMDB.15
MDB Cable Pulling 7 26-Aug-24 03-Sep-24 MDB Cable Pulling

LS2-CON-M-E-PDMDB.20
MDB Pannel Installation 7 03-Sep-24 10-Sep-24 MDB Pannel Installation

LS2-CON-M-E-PDMDB.25
MDB Pannel / Cable Termination 7 11-Sep-24 18-Sep-24 MDB Pannel / Cable Termination

LS2-CON-M-E-PDMDB.30
MDB Pannel / Cable initial Testing 5 18-Sep-24 25-Sep-24 MDB Pannel / Cable initial Testing

MCC 33 26-Aug-24 03-Oct-24 03-Oct-24, MCC


LS2-CON-M-E-PDMCC.10
MCC Cable Tray Installation 7 26-Aug-24 03-Sep-24 MCC Cable Tray Installation

LS2-CON-M-E-PDMCC.15
MCC Cable Pulling 7 03-Sep-24 10-Sep-24 MCC Cable Pulling

LS2-CON-M-E-PDMCC.20
MCC Pannel Installation 7 11-Sep-24 18-Sep-24 MCC Pannel Installation

LS2-CON-M-E-PDMCC.25
MCC Pannel / Cable Termination 7 18-Sep-24 28-Sep-24 MCC Pannel / Cable Termination

LS2-CON-M-E-PDMCC.30
MCC Pannel / Cable initial Testing 5 28-Sep-24 03-Oct-24 MCC Pannel / Cable initial Testing

SMSB 24 26-Aug-24 22-Sep-24 22-Sep-24, SMSB


LS2-CON-M-E-PDSMS.10
SMSB Cable Tray Installation 5 26-Aug-24 01-Sep-24 SMSB Cable Tray Installation

LS2-CON-M-E-PDSMS.15
SMSB Cable Pulling 5 01-Sep-24 05-Sep-24 SMSB Cable Pulling

LS2-CON-M-E-PDSMS.20
SMSB Pannel Installation 5 07-Sep-24 11-Sep-24 SMSB Pannel Installation

LS2-CON-M-E-PDSMS.25
SMSB Pannel / Cable Termination 5 11-Sep-24 17-Sep-24 SMSB Pannel / Cable Termination

LS2-CON-M-E-PDSMS.30
SMSB Pannel / Cable initial Testing 4 17-Sep-24 22-Sep-24 SMSB Pannel / Cable initial Testing

DB 24 26-Aug-24 22-Sep-24 22-Sep-24, DB


LS2-CON-M-E-PDDB.10
DB Cable Tray Installation 5 26-Aug-24 01-Sep-24 DB Cable Tray Installation

LS2-CON-M-E-PDDB.15
DB Cable Pulling 5 01-Sep-24 05-Sep-24 DB Cable Pulling

LS2-CON-M-E-PDDB.20
DB Pannel Installation 5 07-Sep-24 11-Sep-24 DB Pannel Installation

LS2-CON-M-E-PDDB.25
DB Pannel / Cable Termination 5 11-Sep-24 17-Sep-24 DB Pannel / Cable Termination

LS2-CON-M-E-PDDB.30
DB Pannel / Cable initial Testing 4 17-Sep-24 22-Sep-24 DB Pannel / Cable initial Testing

ISOLATOR 24 01-Sep-24 29-Sep-24 29-Sep-24, ISOLATOR


LS2-CON-M-E-PDISO.10
Isolators Cable Tray Installation 5 01-Sep-24 05-Sep-24 Isolators Cable Tray Installation

LS2-CON-M-E-PDISO.15
Isolators Cable Pulling 5 07-Sep-24 11-Sep-24 Isolators Cable Pulling

LS2-CON-M-E-PDISO.20
Isolators Pannel Installation 5 11-Sep-24 17-Sep-24 Isolators Pannel Installation

LS2-CON-M-E-PDISO.25
Isolators Pannel / Cable Termination 5 17-Sep-24 24-Sep-24 Isolators Pannel / Cable Termination

LS2-CON-M-E-PDISO.30
Isolators Pannel / Cable initial Testing 4 24-Sep-24 29-Sep-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 01-Sep-24 29-Sep-24 29-Sep-24, LCP/ ELCP


LS2-CON-M-E-PDLCP.10
LCP/ELCP Cable Tray Installation 5 01-Sep-24 05-Sep-24 LCP/ELCP Cable Tray Installation

LS2-CON-M-E-PDLCP.15
LCP/ELCP Cable Pulling 5 07-Sep-24 11-Sep-24 LCP/ELCP Cable Pulling

LS2-CON-M-E-PDLCP.20
LCP/ELCP Pannel Installation 5 11-Sep-24 17-Sep-24 LCP/ELCP Pannel Installation

LS2-CON-M-E-PDLCP.25
LCP/ELCP Pannel / Cable Termination 5 17-Sep-24 24-Sep-24 LCP/ELCP Pannel / Cable Termination

LS2-CON-M-E-PDLCP.30
LCP/ELCP Pannel / Cable initial Testing 4 24-Sep-24 29-Sep-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 07-Sep-24 05-Nov-24 05-Nov-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 07-Sep-24 26-Oct-24 26-Oct-24, FIRE ALARM SYSTEM
LS2-CO-M-E-LC-FAS.10
Fire Alarm Conduit /Cable Tray Installation 9 07-Sep-24 16-Sep-24 Fire Alarm Conduit /Cable Tray Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
167 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS2-CO-M-E-LC-FAS.15
Fire Alarm Cable Pulling 9 16-Sep-24 28-Sep-24 Fire Alarm Cable Pulling

LS2-CO-M-E-LC-FAS.20
Fire Alarm Devices Installation 9 28-Sep-24 08-Oct-24 Fire Alarm Devices Installation

LS2-CO-M-E-LC-FAS.25
Fire Alarm Devices and Cable Termination 9 08-Oct-24 19-Oct-24 Fire Alarm Devices and Cable Termination

LS2-CO-M-E-LC-FAS.30
Fire Alarm Devices and Cable initial Testing 6 19-Oct-24 26-Oct-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 07-Sep-24 26-Oct-24 26-Oct-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
LS2-CO-M-E-LC-ICT.10
ICT System Conduit /Cable Tray Installation 9 07-Sep-24 16-Sep-24 ICT System Conduit /Cable Tray Installation

LS2-CO-M-E-LC-ICT.15
ICT System Cable Pulling 9 16-Sep-24 28-Sep-24 ICT System Cable Pulling

LS2-CO-M-E-LC-ICT.20
ICT System Devices Installation 9 28-Sep-24 08-Oct-24 ICT System Devices Installation

LS2-CO-M-E-LC-ICT.25
ICT System Devices and Cable Termination 9 08-Oct-24 19-Oct-24 ICT System Devices and Cable Termination

LS2-CO-M-E-LC-ICT.30
ICT System Devices and Cable initial Testing 6 19-Oct-24 26-Oct-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 07-Sep-24 26-Oct-24 26-Oct-24, ACCESS CONTROL SYSTEM


LS2-CO-M-E-LC-ACS.10
Access Control System Conduit /Cable Tray Installation 9 07-Sep-24 16-Sep-24 Access Control System Conduit /Cable Tray Installation

LS2-CO-M-E-LC-ACS.15
Access Control System Cable Pulling 9 16-Sep-24 28-Sep-24 Access Control System Cable Pulling

LS2-CO-M-E-LC-ACS.20
Access Control System Devices Installation 9 28-Sep-24 08-Oct-24 Access Control System Devices Installation

LS2-CO-M-E-LC-ACS.25
Access Control System Devices and Cable Termination 9 08-Oct-24 19-Oct-24 Access Control System Devices and Cable Termination

LS2-CO-M-E-LC-ACS.30
Access Control System Devices and Cable initial Testing 6 19-Oct-24 26-Oct-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 16-Sep-24 05-Nov-24 05-Nov-24, PUBLIC ADDRESS SYSTEM


LS2-CO-M-E-LC-PAS.10
Public Address System Conduit /Cable Tray Installation 9 16-Sep-24 28-Sep-24 Public Address System Conduit /Cable Tray Installation

LS2-CO-M-E-LC-PAS.15
Public Address System Cable Pulling 9 28-Sep-24 08-Oct-24 Public Address System Cable Pulling

LS2-CO-M-E-LC-PAS.20
Public Address System Devices Installation 9 08-Oct-24 19-Oct-24 Public Address System Devices Installation

LS2-CO-M-E-LC-PAS.25
Public Address System Devices and Cable Termination 9 19-Oct-24 29-Oct-24 Public Address System Devices and Cable Termination

LS2-CO-M-E-LC-PAS.30
Public Address System Devices and Cable initial Testing 6 29-Oct-24 05-Nov-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 16-Sep-24 05-Nov-24 05-Nov-24, SCADA SYSTEM


LS2-CO-M-E-LC-SS.10
SCADA System Conduit /Cable Tray Installation 9 16-Sep-24 28-Sep-24 SCADA System Conduit /Cable Tray Installation

LS2-CO-M-E-LC-SS.15
SCADA System Cable Pulling 9 28-Sep-24 08-Oct-24 SCADA System Cable Pulling

LS2-CO-M-E-LC-SS.20
SCADA System Devices Installation 9 08-Oct-24 19-Oct-24 SCADA System Devices Installation

LS2-CO-M-E-LC-SS.25
SCADA System Devices and Cable Termination 9 19-Oct-24 29-Oct-24 SCADA System Devices and Cable Termination

LS2-CO-M-E-LC-SS.30
SCADA System Devices and Cable initial Testing 6 29-Oct-24 05-Nov-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 16-Sep-24 05-Nov-24 05-Nov-24, RADIO RE- BROADCOASTING/ TETRA
LS2-CO-M-E-LC-RRB.10
Radio/TETRA System Conduit /Cable Tray Installation 9 16-Sep-24 28-Sep-24 Radio/TETRA System Conduit /Cable Tray Installation

LS2-CO-M-E-LC-RRB.15
Radio/TETRA System Cable Pulling 9 28-Sep-24 08-Oct-24 Radio/TETRA System Cable Pulling

LS2-CO-M-E-LC-RRB.20
Radio/TETRA System Devices Installation 9 08-Oct-24 19-Oct-24 Radio/TETRA System Devices Installation

LS2-CO-M-E-LC-RRB.25
Radio/TETRA System Devices and Cable Termination 9 19-Oct-24 29-Oct-24 Radio/TETRA System Devices and Cable Termination

LS2-CO-M-E-LC-RRB.30
Radio/TETRA System Devices and Cable initial Testing 6 29-Oct-24 05-Nov-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK 27 28-Sep-24 29-Oct-24 29-Oct-24, MECHANICAL WORK


FIRE FIGHTING 13 28-Sep-24 13-Oct-24 13-Oct-24, FIRE FIGHTING
LS2-CO-MR-MW-FF.10
Fire Fighting system Pipe and accessories installation 11 28-Sep-24 10-Oct-24 Fire Fighting system Pipe and accessories installation

LS2-CO-MR-MW-FF.15
Fire Fighting system fire hose cabinet/extingusher installation 3 07-Oct-24 10-Oct-24 Fire Fighting system fire hose cabinet/extingusher installation

LS2-CO-MR-MW-FF.20
Fire Fighting system initial testing 2 10-Oct-24 13-Oct-24 Fire Fighting system initial testing

HVAC 15 10-Oct-24 28-Oct-24 28-Oct-24, HVAC


LS2-CO-MR-MW-HVAC.10
Duct and accessories installation 12 10-Oct-24 24-Oct-24 Duct and accessories installation

LS2-CO-MR-MW-HVAC.15
Fan installation 4 20-Oct-24 24-Oct-24 Fan installation

LS2-CO-MR-MW-HVAC.20
HVAC inital testing 3 24-Oct-24 28-Oct-24 HVAC inital testing

PLUMBING 4 24-Oct-24 29-Oct-24 29-Oct-24, PLUMBING


LS2-CO-MR-MW-PB.10
Plumbing drainage system installation 3 24-Oct-24 28-Oct-24 Plumbing drainage system installation

LS2-CO-MR-MW-PB.15
Plumbing drainage system initial testing 1 28-Oct-24 29-Oct-24 Plumbing drainage system initial testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
168 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
lIFTING STATION 03 (IN ZONE 10) 448 24-May-23 10-Nov-24 10-Nov-24, lIFTING STATION 03 (IN ZONE 10)
ENGINEERING 95 24-May-23 16-Sep-23 16-Sep-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 95 24-May-23 16-Sep-23 16-Sep-23, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 42 24-Jun-23 14-Aug-23 14-Aug-23, EARTH WORKS
LS3-EN-SD-EW.10 Shoring Design Preparation & Submission 14 24-Jun-23 12-Jul-23 Shoring Design Preparation & Submission

LS3-EN-SD-EW.15 Soil Improvement Design Preparation & Submission 14 24-Jun-23 12-Jul-23 Soil Improvement Design Preparation & Submission

LS3-EN-SD-EW.20 Soil Improvement Design Review & Approval 14 12-Jul-23 29-Jul-23 Soil Improvement Design Review & Approval

LS3-EN-SD-EW.25 Shoring Design Review & Approval 14 29-Jul-23 14-Aug-23 Shoring Design Review & Approval

STRUCTURE 70 24-May-23 16-Aug-23 16-Aug-23, STRUCTURE


LS3-EN-SD-STR.10 Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

LS3-EN-SD-STR.15 Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

LS3-EN-SD-STR.20 Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

LS3-EN-SD-STR.25 Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

LS3-EN-SD-STR.30 Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

LS3-EN-SD-STR.35 Slab Shop Drawings Review & Approval 14 31-Jul-23 16-Aug-23 Slab Shop Drawings Review & Approval

MECHANICAL-1 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL-1


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
LS3-EN-SD-ME-FFS.10
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

LS3-EN-SD-ME-FFS.15
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
LS3-EN-SD-ME-VS.10HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

LS3-EN-SD-ME-VS.15HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


LS3-EN-SD-ME-PS.10Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

LS3-EN-SD-ME-PS.15Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 95 24-May-23 16-Sep-23 16-Sep-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
LS3-EN-SD-E-CT.10 Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

LS3-EN-SD-E-CT.15 Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


LS3-EN-SD-E-PC.10 Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

LS3-EN-SD-E-PC.15 Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


LS3-EN-SD-E-LS.10 Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

LS3-EN-SD-E-LS.15 Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


LS3-EN-SD-E-EI.10 Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

LS3-EN-SD-E-EI.15 Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


LS3-EN-SD-E-LPS.10Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

LS3-EN-SD-E-LPS.15Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM


LS3-EN-SD-E-ES.10 Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

LS3-EN-SD-E-ES.15 Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 95 24-May-23 16-Sep-23 16-Sep-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
LS3-EN-SD-E-LC-FD.10
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-FD.15
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
169 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS3-EN-SD-E-LC-CS.10
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-CS.15
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
LS3-EN-SD-E-LC-VE.10
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-VE.15
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


LS3-EN-SD-E-LC-VS.10
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-VS.15
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


LS3-EN-SD-E-LC-AC.10
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-AC.15
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


LS3-EN-SD-E-LC-RB.10
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-RB.15
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, SCADA SYSTEM


LS3-EN-SD-E-LC-SS.10
SCADA system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 SCADA system Shop Drawings Preparation & Submission

LS3-EN-SD-E-LC-SS.15
SCADA system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 SCADA system Shop Drawings Review & Approval

PROCUREMENT 301 29-Oct-23 23-Oct-24 23-Oct-24, PROCUREMENT


CIVIL/STRUCTURAL 16 29-Oct-23 16-Nov-23 16-Nov-23, CIVIL/STRUCTURAL
LS3-EN-PR-CS.10 Issue Purchase Order 6 29-Oct-23 05-Nov-23 Issue Purchase Order

LS3-EN-PR-CS.15 Material Delivery 10 05-Nov-23 16-Nov-23 Material Delivery

MECHANICAL 116 04-Jun-24 23-Oct-24 23-Oct-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 04-Jun-24 10-Oct-24 10-Oct-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 04-Jun-24 10-Oct-24 10-Oct-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
LS3-EN-PR-M-FFS.10Issue Purchase Order 15 04-Jun-24 26-Jun-24 Issue Purchase Order

LS3-EN-PR-M-FFS.15Material Delivery 90 26-Jun-24 10-Oct-24 Material Delivery

VENTILATION SYSTEM 105 22-Jun-24 23-Oct-24 23-Oct-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 22-Jun-24 23-Oct-24 23-Oct-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
LS3-EN-PR-M-VS.10 Issue Purchase Order 15 22-Jun-24 09-Jul-24 Issue Purchase Order

LS3-EN-PR-M-VS.15 Material Delivery 90 09-Jul-24 23-Oct-24 Material Delivery

AIR CONDITIONING WORKS 105 22-Jun-24 23-Oct-24 23-Oct-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 22-Jun-24 23-Oct-24 23-Oct-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
LS3-EN-PR-M-ACW.10
Issue Purchase Order 15 22-Jun-24 09-Jul-24 Issue Purchase Order

LS3-EN-PR-M-ACW.15
Material Delivery 90 09-Jul-24 23-Oct-24 Material Delivery

PLUMBING SYSTEM 105 22-Jun-24 23-Oct-24 23-Oct-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 22-Jun-24 23-Oct-24 23-Oct-24, PUMPS,PIPES,FITTINGS,VALVES
LS3-EN-PR-M-PS.10 Issue Purchase Order 15 22-Jun-24 09-Jul-24 Issue Purchase Order

LS3-EN-PR-M-PS.15 Material Delivery 90 09-Jul-24 23-Oct-24 Material Delivery

ELECTRICAL 129 16-Dec-23 18-May-24 18-May-24, ELECTRICAL


CABLE TRAY 105 16-Dec-23 20-Apr-24 20-Apr-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 16-Dec-23 20-Apr-24 20-Apr-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
LS3-EN-PR-E-CT.10 Issue Purchase Order 15 16-Dec-23 02-Jan-24 Issue Purchase Order

LS3-EN-PR-E-CT.15 Material Delivery 90 02-Jan-24 20-Apr-24 Material Delivery

POWER CABLES 105 16-Dec-23 20-Apr-24 20-Apr-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 16-Dec-23 20-Apr-24 20-Apr-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
LS3-EN-PR-E-PC.10 Issue Purchase Order 15 16-Dec-23 02-Jan-24 Issue Purchase Order

LS3-EN-PR-E-PC.15 Material Delivery 90 02-Jan-24 20-Apr-24 Material Delivery

LIGHTING SYSTEM 105 16-Dec-23 20-Apr-24 20-Apr-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 16-Dec-23 20-Apr-24 20-Apr-24, CONDUIT,LIGHT
LS3-EN-PR-E-LS10 Issue Purchase Order 15 16-Dec-23 02-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LS15 Material Delivery 90 02-Jan-24 20-Apr-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
170 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ELECTRICAL INSTALLATIONS 105 25-Dec-23 29-Apr-24 29-Apr-24, ELECTRICAL INSTALLATIONS
M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 25-Dec-23 29-Apr-24 29-Apr-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
LS3-EN-PR-E-EI10 Issue Purchase Order 15 25-Dec-23 11-Jan-24 Issue Purchase Order

LS3-EN-PR-E-EI15 Material Delivery 90 11-Jan-24 29-Apr-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 16-Dec-23 20-Apr-24 20-Apr-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 16-Dec-23 20-Apr-24 20-Apr-24, LIGHTNING PROTECTION SYSTEM
LS3-EN-PR-E-LPS.10Issue Purchase Order 15 16-Dec-23 02-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LPS.15Material Delivery 90 02-Jan-24 20-Apr-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 13-Jan-24 18-May-24 18-May-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 13-Jan-24 18-May-24 18-May-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
LS3-EN-PR-E-ES.10 Issue Purchase Order 15 13-Jan-24 30-Jan-24 Issue Purchase Order

LS3-EN-PR-E-ES.15 Material Delivery 90 30-Jan-24 18-May-24 Material Delivery

LOW CURRENT 114 02-Jan-24 18-May-24 18-May-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 02-Jan-24 07-May-24 07-May-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 02-Jan-24 07-May-24 07-May-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
LS3-EN-PR-E-LC-FD.10
Issue Purchase Order 15 02-Jan-24 20-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-FD.15
Material Delivery 90 20-Jan-24 07-May-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 02-Jan-24 07-May-24 07-May-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 02-Jan-24 07-May-24 07-May-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
LS3-EN-PR-E-LC-CS.10
Issue Purchase Order 15 02-Jan-24 20-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-CS.15
Material Delivery 90 20-Jan-24 07-May-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 13-Jan-24 18-May-24 18-May-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 13-Jan-24 18-May-24 18-May-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
LS3-EN-PR-E-LC-VE.10
Issue Purchase Order 15 13-Jan-24 30-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-VE.15
Material Delivery 90 30-Jan-24 18-May-24 Material Delivery

VIDEO SURVEILLANCE 105 02-Jan-24 07-May-24 07-May-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 02-Jan-24 07-May-24 07-May-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
LS3-EN-PR-E-LC-VS.10
Issue Purchase Order 15 02-Jan-24 20-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-VS.15
Material Delivery 90 20-Jan-24 07-May-24 Material Delivery

ACCESS CONTROL SYSTEM 105 02-Jan-24 07-May-24 07-May-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 02-Jan-24 07-May-24 07-May-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
LS3-EN-PR-E-LC-AC.10
Issue Purchase Order 15 02-Jan-24 20-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-AC.15
Material Delivery 90 20-Jan-24 07-May-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 13-Jan-24 18-May-24 18-May-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 13-Jan-24 18-May-24 18-May-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
LS3-EN-PR-E-LC-RB.10
Issue Purchase Order 15 13-Jan-24 30-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-RB.15
Material Delivery 90 30-Jan-24 18-May-24 Material Delivery

SCADA SYSTEM 105 13-Jan-24 18-May-24 18-May-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 13-Jan-24 18-May-24 18-May-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
LS3-EN-PR-E-LC-SS.10
Issue Purchase Order 15 13-Jan-24 30-Jan-24 Issue Purchase Order

LS3-EN-PR-E-LC-SS.15
Material Delivery 90 30-Jan-24 18-May-24 Material Delivery

CONSTRUCTION 380 14-Aug-23 10-Nov-24 10-Nov-24, CONSTRUCTION


EXCAVATION WORKS 25 25-Sep-23 24-Oct-23 24-Oct-23, EXCAVATION WORKS
LS3-EN-CO-EW.10 Excavation 25 25-Sep-23 24-Oct-23 Excavation

SHORING WORKS 57 14-Aug-23 21-Oct-23 21-Oct-23, SHORING WORKS


LS3-EN-CO-SW.10 Piles 30 14-Aug-23 18-Sep-23 Piles

LS3-EN-CO-SW.15 Capping Beam 5 18-Sep-23 25-Sep-23 Capping Beam

LS3-EN-CO-SW.20 Anchore 22 25-Sep-23 21-Oct-23 Anchore

SOIL IMPROVEMENT WORKS 20 24-Oct-23 16-Nov-23 16-Nov-23, SOIL IMPROVEMENT WORKS


LS3-EN-CO-SIW.10 Soil Improvement 20 24-Oct-23 16-Nov-23 Soil Improvement

STRUCTURAL WORKS 247 16-Nov-23 08-Sep-24 08-Sep-24, STRUCTURAL WORKS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
171 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
FOUNDATION 17 16-Nov-23 06-Dec-23 06-Dec-23, FOUNDATION
Part-1 17 16-Nov-23 06-Dec-23 06-Dec-23, Part-1
LS3-EN-CO-SW-FP1.10
Foundation Blinding concrete casting 1 16-Nov-23 18-Nov-23 Foundation Blinding concrete casting

LS3-EN-CO-SW-FP1.15
Foundation water proofing on blinding concrete 2 18-Nov-23 20-Nov-23 Foundation water proofing on blinding concrete

LS3-EN-CO-SW-FP1.20
Foundation Protection screed on water poofing 1 20-Nov-23 21-Nov-23 Foundation Protection screed on water poofing

LS3-EN-CO-SW-FP1.25
Foundation Curing for screed 1 21-Nov-23 22-Nov-23 Foundation Curing for screed

LS3-EN-CO-SW-FP1.30
Foundation Rebar installation 5 22-Nov-23 28-Nov-23 Foundation Rebar installation

LS3-EN-CO-SW-FP1.35
Foundation Formwork installation 4 28-Nov-23 03-Dec-23 Foundation Formwork installation

LS3-EN-CO-SW-FP1.45
Foundation concrete casting 1 03-Dec-23 04-Dec-23 Foundation concrete casting

LS3-EN-CO-SW-FP1.50
Foundation concrete curing 1 04-Dec-23 05-Dec-23 Foundation concrete curing

LS3-EN-CO-SW-FP1.55
Foundation Formwork Removal 1 05-Dec-23 06-Dec-23 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 21 04-Dec-23 28-Dec-23 28-Dec-23, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 21 04-Dec-23 28-Dec-23 28-Dec-23, WALL CONCRETE CASTING STAGE-1
Part-1 21 04-Dec-23 28-Dec-23 28-Dec-23, Part-1
LS3-EN-CO-SWWS1P1.10
Room Walls Scafolding for rebar 3 04-Dec-23 07-Dec-23 Room Walls Scafolding for rebar

LS3-EN-CO-SWWS1P1.15
Room Walls Rebar Installation 6 07-Dec-23 14-Dec-23 Room Walls Rebar Installation

LS3-EN-CO-SWWS1P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 14-Dec-23 16-Dec-23 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS3-EN-CO-SWWS1P1.25
Room Walls Formwork Installation 7 16-Dec-23 24-Dec-23 Room Walls Formwork Installation

LS3-EN-CO-SWWS1P1.30
Room Walls Concrete Casting 1 24-Dec-23 25-Dec-23 Room Walls Concrete Casting

LS3-EN-CO-SWWS1P1.35
Room Walls Curing work 1 25-Dec-23 26-Dec-23 Room Walls Curing work

LS3-EN-CO-SWWS1P1.40
Room Walls Formwork Removel 2 26-Dec-23 28-Dec-23 Room Walls Formwork Removel

MIDDLE SLAB 37 28-Dec-23 10-Feb-24 10-Feb-24, MIDDLE SLAB


Part-1 37 28-Dec-23 10-Feb-24 10-Feb-24, Part-1
LS3-EN-CO-SWMS1P1.10
Room Top Slab Formwork Installation 12 28-Dec-23 11-Jan-24 Room Top Slab Formwork Installation

LS3-EN-CO-SWMS1P1.15
Room Top Slab Rebar Installation 8 11-Jan-24 21-Jan-24 Room Top Slab Rebar Installation

LS3-EN-CO-SWMS1P1.20
Room Top Slab Concrete Casting 1 21-Jan-24 22-Jan-24 Room Top Slab Concrete Casting

LS3-EN-CO-SWMS1P1.25
Room Top slab Curing work 12 22-Jan-24 05-Feb-24 Room Top slab Curing work

LS3-EN-CO-SWMS1P1.30
Room Top Slab Formwork Removel 4 05-Feb-24 10-Feb-24 Room Top Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 20 10-Feb-24 04-Mar-24 04-Mar-24, WALL CONCRETE CASTING STAGE-2
Part-1 20 10-Feb-24 04-Mar-24 04-Mar-24, Part-1
LS3-EN-CO-SWWS2P1.10
Room Walls Scafolding for rebar 3 10-Feb-24 13-Feb-24 Room Walls Scafolding for rebar

LS3-EN-CO-SWWS2P1.15
Room Walls Rebar Installation 5 13-Feb-24 19-Feb-24 Room Walls Rebar Installation

LS3-EN-CO-SWWS2P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 19-Feb-24 20-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS3-EN-CO-SWWS2P1.25
Room Walls Formwork Installation 7 20-Feb-24 28-Feb-24 Room Walls Formwork Installation

LS3-EN-CO-SWWS2P1.30
Room Walls Concrete Casting 1 28-Feb-24 29-Feb-24 Room Walls Concrete Casting

LS3-EN-CO-SWWS2P1.35
Room Walls Curing work 1 29-Feb-24 02-Mar-24 Room Walls Curing work

LS3-EN-CO-SWWS2P1.40
Room Walls Formwork Removel 2 02-Mar-24 04-Mar-24 Room Walls Formwork Removel

TOP SLAB BELOW GROUND LEVEL 37 04-Mar-24 20-Apr-24 20-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 04-Mar-24 20-Apr-24 20-Apr-24, Part-1
LS3-EN-CO-SWTS2P1.10
Room Top Slab Formwork Installation 12 04-Mar-24 18-Mar-24 Room Top Slab Formwork Installation

LS3-EN-CO-SWTS2P1.15
Room Top Slab Rebar Installation 8 18-Mar-24 27-Mar-24 Room Top Slab Rebar Installation

LS3-EN-CO-SWTS2P1.20
Room Top Slab Concrete Casting 1 27-Mar-24 28-Mar-24 Room Top Slab Concrete Casting

LS3-EN-CO-SWTS2P1.25
Room Top slab Curing work 12 28-Mar-24 15-Apr-24 Room Top slab Curing work

LS3-EN-CO-SWTS2P1.30
Room Top Slab Formwork Removel 4 15-Apr-24 20-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 17 15-Apr-24 05-May-24 05-May-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-3 17 15-Apr-24 05-May-24 05-May-24, WALL CONCRETE CASTING STAGE-3
Part-1 17 15-Apr-24 05-May-24 05-May-24, Part-1

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
172 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS3-EN-CO-SWWS3P1.10
Room Walls Scafolding for rebar 3 15-Apr-24 18-Apr-24 Room Walls Scafolding for rebar

LS3-EN-CO-SWWS3P1.15
Room Walls Rebar Installation 4 18-Apr-24 23-Apr-24 Room Walls Rebar Installation

LS3-EN-CO-SWWS3P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 23-Apr-24 24-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS3-EN-CO-SWWS3P1.25
Room Walls Formwork Installation 5 24-Apr-24 30-Apr-24 Room Walls Formwork Installation

LS3-EN-CO-SWWS3P1.30
Room Walls Concrete Casting 1 30-Apr-24 01-May-24 Room Walls Concrete Casting

LS3-EN-CO-SWWS3P1.35
Room Walls Curing work 1 01-May-24 02-May-24 Room Walls Curing work

LS3-EN-CO-SWWS3P1.40
Room Walls Formwork Removel 2 02-May-24 05-May-24 Room Walls Formwork Removel

WALL CONCRETE CASTING STAGE-4 17 05-May-24 25-May-24 25-May-24, WALL CONCRETE CASTING STAGE-4
Part-1 17 05-May-24 25-May-24 25-May-24, Part-1
LS3-EN-CO-SWWS4P1.10
Room Walls Scafolding for rebar 3 05-May-24 08-May-24 Room Walls Scafolding for rebar

LS3-EN-CO-SWWS4P1.15
Room Walls Rebar Installation 4 08-May-24 13-May-24 Room Walls Rebar Installation

LS3-EN-CO-SWWS4P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 13-May-24 14-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS3-EN-CO-SWWS4P1.25
Room Walls Formwork Installation 5 14-May-24 20-May-24 Room Walls Formwork Installation

LS3-EN-CO-SWWS4P1.30
Room Walls Concrete Casting 1 20-May-24 21-May-24 Room Walls Concrete Casting

LS3-EN-CO-SWWS4P1.35
Room Walls Curing work 1 21-May-24 22-May-24 Room Walls Curing work

LS3-EN-CO-SWWS4P1.40
Room Walls Formwork Removel 2 22-May-24 25-May-24 Room Walls Formwork Removel

SLAB ABOVE GROUND LEVEL 33 25-May-24 07-Jul-24 07-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 33 25-May-24 07-Jul-24 07-Jul-24, Part-1
LS3-EN-CO-SWSAGP1.10
Room Top Slab Formwork Installation 8 25-May-24 03-Jun-24 Room Top Slab Formwork Installation

LS3-EN-CO-SWSAGP1.15
Room Top Slab Rebar Installation 8 03-Jun-24 12-Jun-24 Room Top Slab Rebar Installation

LS3-EN-CO-SWSAGP1.20
Room Top Slab Concrete Casting 1 12-Jun-24 13-Jun-24 Room Top Slab Concrete Casting

LS3-EN-CO-SWSAGP1.25
Room Top slab Curing work 12 13-Jun-24 02-Jul-24 Room Top slab Curing work

LS3-EN-CO-SWSAGP1.30
Room Top Slab Formwork Removel 4 02-Jul-24 07-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 45 07-Jul-24 28-Aug-24 28-Aug-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 07-Jul-24 18-Jul-24 18-Jul-24, WALL WATER PROOFING STAGE-1
LS3-EN-CO-SWWPS1.10
Surface preparation work 2 07-Jul-24 09-Jul-24 Surface preparation work

LS3-EN-CO-SWWPS1.15
Applying of waterproofing material &Membrane Protection work 2 09-Jul-24 11-Jul-24 Applying of waterproofing material &Membrane Protection work

LS3-EN-CO-SWWPS1.20
L.S Back Filling 6 11-Jul-24 18-Jul-24 L.S Back Filling

WALL WATER PROOFING STAGE-2 10 18-Jul-24 30-Jul-24 30-Jul-24, WALL WATER PROOFING STAGE-2
LS3-EN-CO-SWWPS2.10
Surface preparation work 2 18-Jul-24 21-Jul-24 Surface preparation work

LS3-EN-CO-SWWPS2.15
Applying of waterproofing material &Membrane Protection work 2 21-Jul-24 23-Jul-24 Applying of waterproofing material &Membrane Protection work

LS3-EN-CO-SWWPS2.20
L.S Back Filling 6 23-Jul-24 30-Jul-24 L.S Back Filling

WALL WATER PROOFING STAGE-3 10 30-Jul-24 11-Aug-24 11-Aug-24, WALL WATER PROOFING STAGE-3
LS3-EN-CO-SWWPS3.10
Surface preparation work 2 30-Jul-24 01-Aug-24 Surface preparation work

LS3-EN-CO-SWWPS3.15
Applying of waterproofing material &Membrane Protection work 2 01-Aug-24 04-Aug-24 Applying of waterproofing material &Membrane Protection work

LS3-EN-CO-SWWPS3.20
L.S Back Filling 6 04-Aug-24 11-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-4 10 11-Aug-24 22-Aug-24 22-Aug-24, WALL WATER PROOFING STAGE-4
LS3-EN-CO-SWWPS4.10
Surface preparation work 2 11-Aug-24 13-Aug-24 Surface preparation work

LS3-EN-CO-SWWPS4.15
Applying of waterproofing material &Membrane Protection work 2 13-Aug-24 15-Aug-24 Applying of waterproofing material &Membrane Protection work

LS3-EN-CO-SWWPS4.20
L.S Back Filling 6 15-Aug-24 22-Aug-24 L.S Back Filling

TOP SLAB WATER PROOFING 5 22-Aug-24 28-Aug-24 28-Aug-24, TOP SLAB WATER PROOFING
LS3-EN-CO-SWTSWP.10
Surface preparation work 2 22-Aug-24 25-Aug-24 Surface preparation work

LS3-EN-CO-SWTSWP.15
Applying of waterproofing material &Membrane Protection work 2 25-Aug-24 27-Aug-24 Applying of waterproofing material &Membrane Protection work

LS3-EN-CO-SWTSWP.20
Leak Test 1 27-Aug-24 28-Aug-24 Leak Test

PLAIN CONCRETE ABOVE SLAB 9 28-Aug-24 08-Sep-24 08-Sep-24, PLAIN CONCRETE ABOVE SLAB
Part-1 9 28-Aug-24 08-Sep-24 08-Sep-24, Part-1
LS3-EN-CO-SWPCP1.10
Plain Concrete Above Top Slab Formwork Installation 6 28-Aug-24 04-Sep-24 Plain Concrete Above Top Slab Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
173 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS3-EN-CO-SWPCP1.15
Plain Concrete Casting 1 04-Sep-24 05-Sep-24 Plain Concrete Casting

LS3-EN-CO-SWPCP1.20
Plain Concrete curing work 1 05-Sep-24 07-Sep-24 Plain Concrete curing work

LS3-EN-CO-SWPCP1.25
Plain Concrete Formwork removal 1 07-Sep-24 08-Sep-24 Plain Concrete Formwork removal

MECHANICAL ROOM MEP (UCR) 170 20-Apr-24 10-Nov-24 10-Nov-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK 65 20-Apr-24 09-Jul-24 09-Jul-24, ELECTRICAL WORK
POWER SYSTEM 48 20-Apr-24 13-Jun-24 13-Jun-24, POWER SYSTEM
LIGHTING SYSTEM 37 20-Apr-24 01-Jun-24 01-Jun-24, LIGHTING SYSTEM
LS3-EN-CO-MR-EPLS.10
Lighting system Conduit and boxes Installation 8 20-Apr-24 29-Apr-24 Lighting system Conduit and boxes Installation

LS3-EN-CO-MR-EPLS.15
Lighting system Cable Pulling 8 29-Apr-24 08-May-24 Lighting system Cable Pulling

LS3-EN-CO-MR-EPLS.20
Lighting system Installations 8 08-May-24 18-May-24 Lighting system Installations

LS3-EN-CO-MR-EPLS.25
Lighting system Termination 8 18-May-24 27-May-24 Lighting system Termination

LS3-EN-CO-MR-EPLS.30
Lighting system Initial Testing 5 27-May-24 01-Jun-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 20-Apr-24 13-Jun-24 13-Jun-24, CABLE TRAY /CABLE ROUTING SYSTEM
LS3-EN-CO-MR-EPCT.10
Cable Tray Installation 10 20-Apr-24 01-May-24 Cable Tray Installation

LS3-EN-CO-MR-EPCT.15
Cable Tray Inspection 10 01-May-24 13-May-24 Cable Tray Inspection

LS3-EN-CO-MR-EPCT.20
LV Cable pulling 10 13-May-24 25-May-24 LV Cable pulling

LS3-EN-CO-MR-EPCT.25
LV Cable Termination 10 25-May-24 05-Jun-24 LV Cable Termination

LS3-EN-CO-MR-EPCT.30
LV Cable Initial Testing 8 05-Jun-24 13-Jun-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 20-Apr-24 03-Jun-24 03-Jun-24, SMALL POWER SYSTEM


LS3-EN-CO-MR-EPSP.10
Small Power Conduit and boxes Installation 12 20-Apr-24 04-May-24 Small Power Conduit and boxes Installation

LS3-EN-CO-MR-EPSP.15
Small Power Cable Pulling 10 04-May-24 15-May-24 Small Power Cable Pulling

LS3-EN-CO-MR-EPSP.20
Small Power Installations 6 15-May-24 22-May-24 Small Power Installations

LS3-EN-CO-MR-EPSP.25
Small Power Termination 6 22-May-24 29-May-24 Small Power Termination

LS3-EN-CO-MR-EPSP.30
Small Power Initial Testing 5 29-May-24 03-Jun-24 Small Power Initial Testing

POWER DISTRIBUTION 39 20-Apr-24 04-Jun-24 04-Jun-24, POWER DISTRIBUTION


GENERATOR 39 20-Apr-24 04-Jun-24 04-Jun-24, GENERATOR
LS3-EN-CO-MR-PDG.10
Generator Cable Tray Installation 7 20-Apr-24 28-Apr-24 Generator Cable Tray Installation

LS3-EN-CO-MR-PDG.15
Generator Cable Pulling 7 28-Apr-24 06-May-24 Generator Cable Pulling

LS3-EN-CO-MR-PDG.20
Generator Cell Pannel Installation 7 06-May-24 14-May-24 Generator Cell Pannel Installation

LS3-EN-CO-MR-PDG.25
Generator Installation 7 14-May-24 22-May-24 Generator Installation

LS3-EN-CO-MR-PDG.30
Generator Pannel / Cable Termination 7 22-May-24 29-May-24 Generator Pannel / Cable Termination

LS3-EN-CO-MR-PDG.35
Generator Pannel / Cable initial Testing 5 30-May-24 04-Jun-24 Generator Pannel / Cable initial Testing

UPS 28 20-Apr-24 22-May-24 22-May-24, UPS


LS3-EN-CO-MR-PDU.10
UPS Cable Tray Installation 5 20-Apr-24 25-Apr-24 UPS Cable Tray Installation

LS3-EN-CO-MR-PDU.15
UPS Cable Pulling 5 25-Apr-24 01-May-24 UPS Cable Pulling

LS3-EN-CO-MR-PDU.20
UPS Pannel Installation 5 01-May-24 07-May-24 UPS Pannel Installation

LS3-EN-CO-MR-PDU.25
UPS Installation 5 07-May-24 13-May-24 UPS Installation

LS3-EN-CO-MR-PDU.30
UPS Pannel / Cable Termination 5 13-May-24 18-May-24 UPS Pannel / Cable Termination

LS3-EN-CO-MR-PDU.35
UPS Pannel / Cable initial Testing 4 19-May-24 22-May-24 UPS Pannel / Cable initial Testing

MDB 33 25-Apr-24 02-Jun-24 02-Jun-24, MDB


LS3-EN-CO-MR-PDMD.10
MDB Cable Tray Installation 7 25-Apr-24 04-May-24 MDB Cable Tray Installation

LS3-EN-CO-MR-PDMD.15
MDB Cable Pulling 7 04-May-24 12-May-24 MDB Cable Pulling

LS3-EN-CO-MR-PDMD.20
MDB Pannel Installation 7 12-May-24 20-May-24 MDB Pannel Installation

LS3-EN-CO-MR-PDMD.25
MDB Pannel / Cable Termination 7 20-May-24 27-May-24 MDB Pannel / Cable Termination

LS3-EN-CO-MR-PDMD.30
MDB Pannel / Cable initial Testing 5 28-May-24 02-Jun-24 MDB Pannel / Cable initial Testing

MCC 33 25-Apr-24 02-Jun-24 02-Jun-24, MCC

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
174 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS3-EN-CO-MR-PDMC.10
MCC Cable Tray Installation 7 25-Apr-24 04-May-24 MCC Cable Tray Installation

LS3-EN-CO-MR-PDMC.15
MCC Cable Pulling 7 04-May-24 12-May-24 MCC Cable Pulling

LS3-EN-CO-MR-PDMC.20
MCC Pannel Installation 7 12-May-24 20-May-24 MCC Pannel Installation

LS3-EN-CO-MR-PDMC.25
MCC Pannel / Cable Termination 7 20-May-24 27-May-24 MCC Pannel / Cable Termination

LS3-EN-CO-MR-PDMC.30
MCC Pannel / Cable initial Testing 5 28-May-24 02-Jun-24 MCC Pannel / Cable initial Testing

SMSB 19 25-Apr-24 16-May-24 16-May-24, SMSB


LS3-EN-CO-MR-PDSM.10
SMSB Cable Tray Installation 5 25-Apr-24 01-May-24 SMSB Cable Tray Installation

LS3-EN-CO-MR-PDSM.15
SMSB Cable Pulling 5 25-Apr-24 01-May-24 SMSB Cable Pulling

LS3-EN-CO-MR-PDSM.20
SMSB Pannel Installation 5 01-May-24 07-May-24 SMSB Pannel Installation

LS3-EN-CO-MR-PDSM.25
SMSB Pannel / Cable Termination 5 07-May-24 13-May-24 SMSB Pannel / Cable Termination

LS3-EN-CO-MR-PDSM.30
SMSB Pannel / Cable initial Testing 4 13-May-24 16-May-24 SMSB Pannel / Cable initial Testing

DB 24 25-Apr-24 22-May-24 22-May-24, DB


LS3-EN-CO-MR-PDDB.10
DB Cable Tray Installation 5 25-Apr-24 01-May-24 DB Cable Tray Installation

LS3-EN-CO-MR-PDDB.15
DB Cable Pulling 5 01-May-24 07-May-24 DB Cable Pulling

LS3-EN-CO-MR-PDDB.20
DB Pannel Installation 5 07-May-24 13-May-24 DB Pannel Installation

LS3-EN-CO-MR-PDDB.25
DB Pannel / Cable Termination 5 13-May-24 18-May-24 DB Pannel / Cable Termination

LS3-EN-CO-MR-PDDB.30
DB Pannel / Cable initial Testing 4 19-May-24 22-May-24 DB Pannel / Cable initial Testing

ISOLATOR 24 01-May-24 28-May-24 28-May-24, ISOLATOR


LS3-EN-CO-MR-PDIS.10
Isolators Cable Tray Installation 5 01-May-24 07-May-24 Isolators Cable Tray Installation

LS3-EN-CO-MR-PDIS.15
Isolators Cable Pulling 5 07-May-24 13-May-24 Isolators Cable Pulling

LS3-EN-CO-MR-PDIS.20
Isolators Pannel Installation 5 13-May-24 18-May-24 Isolators Pannel Installation

LS3-EN-CO-MR-PDIS.25
Isolators Pannel / Cable Termination 5 19-May-24 23-May-24 Isolators Pannel / Cable Termination

LS3-EN-CO-MR-PDIS.30
Isolators Pannel / Cable initial Testing 4 23-May-24 28-May-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 01-May-24 28-May-24 28-May-24, LCP/ ELCP


LS3-EN-CO-MR-PDLC.10
LCP/ELCP Cable Tray Installation 5 01-May-24 07-May-24 LCP/ELCP Cable Tray Installation

LS3-EN-CO-MR-PDLC.15
LCP/ELCP Cable Pulling 5 07-May-24 13-May-24 LCP/ELCP Cable Pulling

LS3-EN-CO-MR-PDLC.20
LCP/ELCP Pannel Installation 5 13-May-24 18-May-24 LCP/ELCP Pannel Installation

LS3-EN-CO-MR-PDLC.25
LCP/ELCP Pannel / Cable Termination 5 19-May-24 23-May-24 LCP/ELCP Pannel / Cable Termination

LS3-EN-CO-MR-PDLC.30
LCP/ELCP Pannel / Cable initial Testing 4 23-May-24 28-May-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 07-May-24 09-Jul-24 09-Jul-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 07-May-24 29-Jun-24 29-Jun-24, FIRE ALARM SYSTEM
LS3-EN-CO-MR-LCFA.10
Fire Alarm Conduit /Cable Tray Installation 9 07-May-24 18-May-24 Fire Alarm Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCFA.15
Fire Alarm Cable Pulling 9 18-May-24 27-May-24 Fire Alarm Cable Pulling

LS3-EN-CO-MR-LCFA.20
Fire Alarm Devices Installation 9 28-May-24 06-Jun-24 Fire Alarm Devices Installation

LS3-EN-CO-MR-LCFA.25
Fire Alarm Devices and Cable Termination 9 06-Jun-24 22-Jun-24 Fire Alarm Devices and Cable Termination

LS3-EN-CO-MR-LCFA.30
Fire Alarm Devices and Cable initial Testing 6 22-Jun-24 29-Jun-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 07-May-24 29-Jun-24 29-Jun-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
LS3-EN-CO-MR-LCIS.10
ICT System Conduit /Cable Tray Installation 9 07-May-24 18-May-24 ICT System Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCIS.15
ICT System Cable Pulling 9 18-May-24 27-May-24 ICT System Cable Pulling

LS3-EN-CO-MR-LCIS.20
ICT System Devices Installation 9 28-May-24 06-Jun-24 ICT System Devices Installation

LS3-EN-CO-MR-LCIS.25
ICT System Devices and Cable Termination 9 06-Jun-24 22-Jun-24 ICT System Devices and Cable Termination

LS3-EN-CO-MR-LCIS.30
ICT System Devices and Cable initial Testing 6 22-Jun-24 29-Jun-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 07-May-24 29-Jun-24 29-Jun-24, ACCESS CONTROL SYSTEM


LS3-EN-CO-MR-LCAC.10
Access Control System Conduit /Cable Tray Installation 9 07-May-24 18-May-24 Access Control System Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCAC.15
Access Control System Cable Pulling 9 18-May-24 27-May-24 Access Control System Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
175 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS3-EN-CO-MR-LCAC.20
Access Control System Devices Installation 9 28-May-24 06-Jun-24 Access Control System Devices Installation

LS3-EN-CO-MR-LCAC.25
Access Control System Devices and Cable Termination 9 06-Jun-24 22-Jun-24 Access Control System Devices and Cable Termination

LS3-EN-CO-MR-LCAC.30
Access Control System Devices and Cable initial Testing 6 22-Jun-24 29-Jun-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 18-May-24 09-Jul-24 09-Jul-24, PUBLIC ADDRESS SYSTEM


LS3-EN-CO-MR-LCPA.10
Public Address System Conduit /Cable Tray Installation 9 18-May-24 27-May-24 Public Address System Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCPA.15
Public Address System Cable Pulling 9 28-May-24 06-Jun-24 Public Address System Cable Pulling

LS3-EN-CO-MR-LCPA.20
Public Address System Devices Installation 9 06-Jun-24 22-Jun-24 Public Address System Devices Installation

LS3-EN-CO-MR-LCPA.25
Public Address System Devices and Cable Termination 9 22-Jun-24 02-Jul-24 Public Address System Devices and Cable Termination

LS3-EN-CO-MR-LCPA.30
Public Address System Devices and Cable initial Testing 6 02-Jul-24 09-Jul-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 18-May-24 09-Jul-24 09-Jul-24, SCADA SYSTEM


LS3-EN-CO-MR-LCSS.10
SCADA System Conduit /Cable Tray Installation 9 18-May-24 27-May-24 SCADA System Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCSS.15
SCADA System Cable Pulling 9 28-May-24 06-Jun-24 SCADA System Cable Pulling

LS3-EN-CO-MR-LCSS.20
SCADA System Devices Installation 9 06-Jun-24 22-Jun-24 SCADA System Devices Installation

LS3-EN-CO-MR-LCSS.25
SCADA System Devices and Cable Termination 9 22-Jun-24 02-Jul-24 SCADA System Devices and Cable Termination

LS3-EN-CO-MR-LCSS.30
SCADA System Devices and Cable initial Testing 6 02-Jul-24 09-Jul-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 18-May-24 09-Jul-24 09-Jul-24, RADIO RE- BROADCOASTING/ TETRA
LS3-EN-CO-MR-LCRB.10
Radio/TETRA System Conduit /Cable Tray Installation 9 18-May-24 27-May-24 Radio/TETRA System Conduit /Cable Tray Installation

LS3-EN-CO-MR-LCRB.15
Radio/TETRA System Cable Pulling 9 28-May-24 06-Jun-24 Radio/TETRA System Cable Pulling

LS3-EN-CO-MR-LCRB.20
Radio/TETRA System Devices Installation 9 06-Jun-24 22-Jun-24 Radio/TETRA System Devices Installation

LS3-EN-CO-MR-LCRB.25
Radio/TETRA System Devices and Cable Termination 9 22-Jun-24 02-Jul-24 Radio/TETRA System Devices and Cable Termination

LS3-EN-CO-MR-LCRB.30
Radio/TETRA System Devices and Cable initial Testing 6 02-Jul-24 09-Jul-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK 26 10-Oct-24 10-Nov-24 10-Nov-24, MECHANICAL WORK


FIRE FIGHTING 13 10-Oct-24 26-Oct-24 26-Oct-24, FIRE FIGHTING
LS3-EN-CO-MR-MWFF.10
Fire Fighting system Pipe and accessories installation 11 10-Oct-24 23-Oct-24 Fire Fighting system Pipe and accessories installation

LS3-EN-CO-MR-MWFF.15
Fire Fighting system fire hose cabinet/extingusher installation 3 20-Oct-24 23-Oct-24 Fire Fighting system fire hose cabinet/extingusher installation

LS3-EN-CO-MR-MWFF.20
Fire Fighting system initial testing 2 23-Oct-24 26-Oct-24 Fire Fighting system initial testing

HVAC 15 23-Oct-24 10-Nov-24 10-Nov-24, HVAC


LS3-EN-CO-MR-HVAC.10
Duct and accessories installation 12 23-Oct-24 06-Nov-24 Duct and accessories installation

LS3-EN-CO-MR-HVAC.15
Fan installation 4 02-Nov-24 06-Nov-24 Fan installation

LS3-EN-CO-MR-HVAC.20
HVAC inital testing 3 06-Nov-24 10-Nov-24 HVAC inital testing

PLUMBING 4 23-Oct-24 28-Oct-24 28-Oct-24, PLUMBING


LS3-EN-CO-MR-MWPB.10
Plumbing drainage system installation 3 23-Oct-24 27-Oct-24 Plumbing drainage system installation

LS3-EN-CO-MR-MWPB.15
Plumbing drainage system initial testing 1 27-Oct-24 28-Oct-24 Plumbing drainage system initial testing

lIFTING STATION 04 (IN ZONE 11) 392 24-May-23 04-Sep-24 04-Sep-24, lIFTING STATION 04 (IN ZONE 11)
ENGINEERING 95 24-May-23 16-Sep-23 16-Sep-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 95 24-May-23 16-Sep-23 16-Sep-23, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 28 12-Jul-23 14-Aug-23 14-Aug-23, EARTH WORKS
LS4-EN-SD-EW.10 Shoring Design Preparation & Submission 14 12-Jul-23 29-Jul-23 Shoring Design Preparation & Submission

LS4-EN-SD-EW.15 Soil Improvement Design Preparation & Submission 14 12-Jul-23 29-Jul-23 Soil Improvement Design Preparation & Submission

LS4-EN-SD-EW.20 Shoring Design Review & Approval 14 29-Jul-23 14-Aug-23 Shoring Design Review & Approval

LS4-EN-SD-EW.25 Soil Improvement Design Review & Approval 14 29-Jul-23 14-Aug-23 Soil Improvement Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


LS4-EN-SD-STR.10 Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

LS4-EN-SD-STR.15 Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

LS4-EN-SD-STR.20 Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

LS4-EN-SD-STR.25 Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

LS4-EN-SD-STR.30 Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
176 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS4-EN-SD-STR.35 Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
LS4-EN-SD-M-FFS.10Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

LS4-EN-SD-M-FFS.15Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
LS4-EN-SD-M-VS.10HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

LS4-EN-SD-M-VS.15HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


LS4-EN-SD-M-PS.10 Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

LS4-EN-SD-M-PS.15 Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 95 24-May-23 16-Sep-23 16-Sep-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
LS4-EN-SD-E-CT.10 Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

LS4-EN-SD-E-CT.15 Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


LS4-EN-SD-E-PC.10 Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

LS4-EN-SD-E-PC.15 Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


LS4-EN-SD-E-LS.10 Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

LS4-EN-SD-E-LS.15 Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


LS4-EN-SD-E-EI10 Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

LS4-EN-SD-E-EI15 Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, LIGHTNING PROTECTION SYSTEM


LS4-EN-SD-E-LPS.10Lightning Protection Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Lightning Protection Drawings Preparation & Submission

LS4-EN-SD-E-LPS.15Lightning Protection Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, EARTHING SYSTEM


LS4-EN-SD-E-ES.10 Earthing System Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Earthing System Shop Drawings Preparation & Submission

LS4-EN-SD-E-ES.15 Earthing System Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Earthing System Drawings Review & Approval

LOW CURRENT 95 24-May-23 16-Sep-23 16-Sep-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
LS4-EN-SD-E-LCFD.10
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCFD.15
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
LS4-EN-SD-E-LCCS.10
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCCS.15
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
LS4-EN-SD-E-LCVE.10
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCVE.15
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


LS4-EN-SD-E-LCVS.10
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCVS.15
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


LS4-EN-SD-E-LCACS.10
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCACS.15
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


LS4-EN-SD-E-LCRRB.10
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCRRB.15
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
177 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
SCADA SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, SCADA SYSTEM
LS4-EN-SD-E-LCSS.10
SCADA system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 SCADA system Shop Drawings Preparation & Submission

LS4-EN-SD-E-LCSS.15
SCADA system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 SCADA system Shop Drawings Review & Approval

PROCUREMENT 200 28-Oct-23 25-Jun-24 25-Jun-24, PROCUREMENT


CIVIL/STRUCTURAL 16 28-Oct-23 15-Nov-23 15-Nov-23, CIVIL/STRUCTURAL
LS4-EN-PR-CS.10 Issue Purchase Order 6 28-Oct-23 04-Nov-23 Issue Purchase Order

LS4-EN-PR-CS.15 Material Delivery 10 04-Nov-23 15-Nov-23 Material Delivery

MECHANICAL 113 06-Feb-24 25-Jun-24 25-Jun-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 06-Feb-24 11-Jun-24 11-Jun-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 06-Feb-24 11-Jun-24 11-Jun-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
LS4-EN-PR-M-FFS.10Issue Purchase Order 15 06-Feb-24 24-Feb-24 Issue Purchase Order

LS4-EN-PR-M-FFS.15Material Delivery 90 24-Feb-24 11-Jun-24 Material Delivery

VENTILATION SYSTEM 105 15-Feb-24 25-Jun-24 25-Jun-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 15-Feb-24 25-Jun-24 25-Jun-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
LS4-EN-PR-M-VS.10 Issue Purchase Order 15 15-Feb-24 04-Mar-24 Issue Purchase Order

LS4-EN-PR-M-VS.15 Material Delivery 90 04-Mar-24 25-Jun-24 Material Delivery

AIR CONDITIONING WORKS 105 15-Feb-24 25-Jun-24 25-Jun-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 15-Feb-24 25-Jun-24 25-Jun-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
LS4-EN-PR-M-ACS.10Issue Purchase Order 15 15-Feb-24 04-Mar-24 Issue Purchase Order

LS4-EN-PR-M-ACS.15Material Delivery 90 04-Mar-24 25-Jun-24 Material Delivery

PLUMBING SYSTEM 105 06-Feb-24 11-Jun-24 11-Jun-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 06-Feb-24 11-Jun-24 11-Jun-24, PUMPS,PIPES,FITTINGS,VALVES
LS4-EN-PR-M-PS.10 Issue Purchase Order 15 06-Feb-24 24-Feb-24 Issue Purchase Order

LS4-EN-PR-M-PS.15 Material Delivery 90 24-Feb-24 11-Jun-24 Material Delivery

ELECTRICAL 143 13-Dec-23 01-Jun-24 01-Jun-24, ELECTRICAL


CABLE TRAY 105 13-Dec-23 17-Apr-24 17-Apr-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 13-Dec-23 17-Apr-24 17-Apr-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
LS4-EN-PR-E-CT.10 Issue Purchase Order 15 13-Dec-23 31-Dec-23 Issue Purchase Order

LS4-EN-PR-E-CT.15 Material Delivery 90 31-Dec-23 17-Apr-24 Material Delivery

POWER CABLES 105 13-Dec-23 17-Apr-24 17-Apr-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 13-Dec-23 17-Apr-24 17-Apr-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
LS4-EN-PR-E-PC.10 Issue Purchase Order 15 13-Dec-23 31-Dec-23 Issue Purchase Order

LS4-EN-PR-E-PC.15 Material Delivery 90 31-Dec-23 17-Apr-24 Material Delivery

LIGHTING SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 23-Dec-23 27-Apr-24 27-Apr-24, CONDUIT,LIGHT
LS4-EN-PR-E-LS.10 Issue Purchase Order 15 23-Dec-23 09-Jan-24 Issue Purchase Order

LS4-EN-PR-E-LS.15 Material Delivery 90 09-Jan-24 27-Apr-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 23-Dec-23 27-Apr-24 27-Apr-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 23-Dec-23 27-Apr-24 27-Apr-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
LS4-EN-PR-E-EI.10 Issue Purchase Order 15 23-Dec-23 09-Jan-24 Issue Purchase Order

LS4-EN-PR-E-EI.15 Material Delivery 90 09-Jan-24 27-Apr-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 23-Dec-23 27-Apr-24 27-Apr-24, LIGHTNING PROTECTION SYSTEM
LS4-EN-PR-E-LPS.10Issue Purchase Order 15 23-Dec-23 09-Jan-24 Issue Purchase Order

LS4-EN-PR-E-LPS.15Material Delivery 90 09-Jan-24 27-Apr-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 01-Jan-24 06-May-24 06-May-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 01-Jan-24 06-May-24 06-May-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
LS4-EN-PR-E-ES.10 Issue Purchase Order 15 01-Jan-24 18-Jan-24 Issue Purchase Order

LS4-EN-PR-E-ES.15 Material Delivery 90 18-Jan-24 06-May-24 Material Delivery

LOW CURRENT 114 16-Jan-24 01-Jun-24 01-Jun-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 16-Jan-24 21-May-24 21-May-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 16-Jan-24 21-May-24 21-May-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
178 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS4-EN-PR-E-LCFD.10
Issue Purchase Order 15 16-Jan-24 03-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCFD.15
Material Delivery 90 03-Feb-24 21-May-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 16-Jan-24 21-May-24 21-May-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 16-Jan-24 21-May-24 21-May-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
LS4-EN-PR-E-LCCS.10
Issue Purchase Order 15 16-Jan-24 03-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCCS.15
Material Delivery 90 03-Feb-24 21-May-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 114 16-Jan-24 01-Jun-24 01-Jun-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 114 16-Jan-24 01-Jun-24 01-Jun-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
LS4-EN-PR-E-LCVE.10
Issue Purchase Order 15 16-Jan-24 03-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCVE.15
Material Delivery 90 13-Feb-24 01-Jun-24 Material Delivery

VIDEO SURVEILLANCE 105 16-Jan-24 21-May-24 21-May-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 16-Jan-24 21-May-24 21-May-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
LS4-EN-PR-E-LCVS.10
Issue Purchase Order 15 16-Jan-24 03-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCVS.15
Material Delivery 90 03-Feb-24 21-May-24 Material Delivery

ACCESS CONTROL SYSTEM 105 16-Jan-24 21-May-24 21-May-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 16-Jan-24 21-May-24 21-May-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
LS4-EN-PR-E-LCAC.10
Issue Purchase Order 15 16-Jan-24 03-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCAC.15
Material Delivery 90 03-Feb-24 21-May-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 27-Jan-24 01-Jun-24 01-Jun-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 27-Jan-24 01-Jun-24 01-Jun-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
LS4-EN-PR-E-LCRRB.10
Issue Purchase Order 15 27-Jan-24 13-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCRRB.15
Material Delivery 90 13-Feb-24 01-Jun-24 Material Delivery

SCADA SYSTEM 105 27-Jan-24 01-Jun-24 01-Jun-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 27-Jan-24 01-Jun-24 01-Jun-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
LS4-EN-PR-E-LCSS.10
Issue Purchase Order 15 27-Jan-24 13-Feb-24 Issue Purchase Order

LS4-EN-PR-E-LCSS.15
Material Delivery 90 13-Feb-24 01-Jun-24 Material Delivery

CONSTRUCTION 324 14-Aug-23 04-Sep-24 04-Sep-24, CONSTRUCTION


EXCAVATION WORKS 43 31-Aug-23 22-Oct-23 22-Oct-23, EXCAVATION WORKS
LS4-EN-CO-EW.10 Excavation 43 31-Aug-23 22-Oct-23 Excavation

SHORING WORKS 24 14-Aug-23 11-Sep-23 11-Sep-23, SHORING WORKS


LS4-EN-CO-SW.10 Piles 9 14-Aug-23 24-Aug-23 Piles

LS4-EN-CO-SW.15 Capping Beam 6 24-Aug-23 31-Aug-23 Capping Beam

LS4-EN-CO-SW.20 Anchore 9 31-Aug-23 11-Sep-23 Anchore

SOIL IMPROVEMENT WORKS 20 22-Oct-23 14-Nov-23 14-Nov-23, SOIL IMPROVEMENT WORKS


LS4-EN-CO-SIW.10 Soil Improvement 20 22-Oct-23 14-Nov-23 Soil Improvement

STRUCTURAL WORKS 246 14-Nov-23 04-Sep-24 04-Sep-24, STRUCTURAL WORKS


FOUNDATION 21 14-Nov-23 09-Dec-23 09-Dec-23, FOUNDATION
Part-1 21 14-Nov-23 09-Dec-23 09-Dec-23, Part-1
LS4-EN-CO-SWFP1.10Foundation Blinding concrete casting 1 14-Nov-23 15-Nov-23 Foundation Blinding concrete casting

LS4-EN-CO-SWFP1.15Foundation water proofing on blinding concrete 2 15-Nov-23 18-Nov-23 Foundation water proofing on blinding concrete

LS4-EN-CO-SWFP1.20Foundation Protection screed on water poofing 1 18-Nov-23 19-Nov-23 Foundation Protection screed on water poofing

LS4-EN-CO-SWFP1.25Foundation Curing for screed 1 19-Nov-23 20-Nov-23 Foundation Curing for screed

LS4-EN-CO-SWFP1.30Foundation Rebar installation 5 20-Nov-23 26-Nov-23 Foundation Rebar installation

LS4-EN-CO-SWFP1.35Foundation Formwork installation 4 26-Nov-23 30-Nov-23 Foundation Formwork installation

LS4-EN-CO-SWFP1.45Foundation concrete casting 1 30-Nov-23 02-Dec-23 Foundation concrete casting

LS4-EN-CO-SWFP1.50Foundation concrete curing 1 02-Dec-23 03-Dec-23 Foundation concrete curing

LS4-EN-CO-SWFP1.55Foundation Formwork Removal 1 03-Dec-23 04-Dec-23 Foundation Formwork Removal

Part-1 17 19-Nov-23 09-Dec-23 09-Dec-23, Part-1


LS4-EN-CO-SWFP1.100
Foundation concrete curing 1 06-Dec-23 07-Dec-23 Foundation concrete curing

LS4-EN-CO-SWFP1.105
Foundation Formwork Removal 1 07-Dec-23 09-Dec-23 Foundation Formwork Removal

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
179 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS4-EN-CO-SWFP1.60
Foundation Blinding concrete casting 1 19-Nov-23 20-Nov-23 Foundation Blinding concrete casting

LS4-EN-CO-SWFP1.65
Foundation water proofing on blinding concrete 2 20-Nov-23 22-Nov-23 Foundation water proofing on blinding concrete

LS4-EN-CO-SWFP1.70
Foundation Protection screed on water poofing 1 22-Nov-23 23-Nov-23 Foundation Protection screed on water poofing

LS4-EN-CO-SWFP1.75
Foundation Curing for screed 1 23-Nov-23 25-Nov-23 Foundation Curing for screed

LS4-EN-CO-SWFP1.80
Foundation Rebar installation 5 25-Nov-23 30-Nov-23 Foundation Rebar installation

LS4-EN-CO-SWFP1.85
Foundation Formwork installation 4 30-Nov-23 05-Dec-23 Foundation Formwork installation

LS4-EN-CO-SWFP1.95
Foundation concrete casting 1 05-Dec-23 06-Dec-23 Foundation concrete casting

WALLS UP TO SLAB LEVEL 21 02-Dec-23 26-Dec-23 26-Dec-23, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 21 02-Dec-23 26-Dec-23 26-Dec-23, WALL CONCRETE CASTING STAGE-1
Part-1 21 02-Dec-23 26-Dec-23 26-Dec-23, Part-1
LS4-EN-CO-SWWS1P1.10
Room Walls Scafolding for rebar 3 02-Dec-23 05-Dec-23 Room Walls Scafolding for rebar

LS4-EN-CO-SWWS1P1.15
Room Walls Rebar Installation 6 05-Dec-23 12-Dec-23 Room Walls Rebar Installation

LS4-EN-CO-SWWS1P1.20
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 12-Dec-23 13-Dec-23 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

LS4-EN-CO-SWWS1P1.25
Room Walls Formwork Installation 7 13-Dec-23 21-Dec-23 Room Walls Formwork Installation

LS4-EN-CO-SWWS1P1.30
Room Walls Concrete Casting 1 21-Dec-23 23-Dec-23 Room Walls Concrete Casting

LS4-EN-CO-SWWS1P1.35
Room Walls Curing work 1 23-Dec-23 24-Dec-23 Room Walls Curing work

LS4-EN-CO-SWWS1P1.40
Room Walls Formwork Removel 2 24-Dec-23 26-Dec-23 Room Walls Formwork Removel

MIDDLE SLAB 37 26-Dec-23 07-Feb-24 07-Feb-24, MIDDLE SLAB


Part-1 37 26-Dec-23 07-Feb-24 07-Feb-24, Part-1
LS4-EN-CO-SWMSP1.10
Room Top Slab Formwork Installation 12 26-Dec-23 09-Jan-24 Room Top Slab Formwork Installation

LS4-EN-CO-SWMSP1.15
Room Top Slab Rebar Installation 8 09-Jan-24 18-Jan-24 Room Top Slab Rebar Installation

LS4-EN-CO-SWMSP1.20
Room Top Slab Concrete Casting 1 18-Jan-24 20-Jan-24 Room Top Slab Concrete Casting

LS4-EN-CO-SWMSP1.25
Room Top slab Curing work 12 20-Jan-24 03-Feb-24 Room Top slab Curing work

LS4-EN-CO-SWMSP1.30
Room Top Slab Formwork Removel 4 03-Feb-24 07-Feb-24 Room Top Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 20 07-Feb-24 02-Mar-24 02-Mar-24, WALL CONCRETE CASTING STAGE-2
Part-1 20 07-Feb-24 02-Mar-24 02-Mar-24, Part-1
PMP.4-WL-SG-2-P1.140
Room Walls Rebar Installation 5 11-Feb-24 17-Feb-24 Room Walls Rebar Installation

PMP.4-WL-SG-2-P1.150
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 17-Feb-24 18-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-2-P1.160
Room Walls Formwork Installation 7 18-Feb-24 26-Feb-24 Room Walls Formwork Installation

PMP.4-WL-SG-2-P1.170
Room Walls Concrete Casting 1 26-Feb-24 27-Feb-24 Room Walls Concrete Casting

PMP.4-WL-SG-2-P1.180
Room Walls Curing work 1 27-Feb-24 28-Feb-24 Room Walls Curing work

PMP.4-WL-SG-2-P1.190
Room Walls Formwork Removel 2 28-Feb-24 02-Mar-24 Room Walls Formwork Removel

PMP.4-WL-SG-2-P1.200
Room Walls Scafolding for rebar 3 07-Feb-24 11-Feb-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 37 02-Mar-24 17-Apr-24 17-Apr-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 02-Mar-24 17-Apr-24 17-Apr-24, Part-1
PMP.4-TS-P1.130 Room Top Slab Formwork Installation 12 02-Mar-24 16-Mar-24 Room Top Slab Formwork Installation

PMP.4-TS-P1.140 Room Top Slab Rebar Installation 8 16-Mar-24 25-Mar-24 Room Top Slab Rebar Installation

PMP.4-TS-P1.150 Room Top Slab Concrete Casting 1 25-Mar-24 26-Mar-24 Room Top Slab Concrete Casting

PMP.4-TS-P1.160 Room Top slab Curing work 12 26-Mar-24 13-Apr-24 Room Top slab Curing work

PMP.4-TS-P1.170 Room Top Slab Formwork Removel 4 13-Apr-24 17-Apr-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 17 13-Apr-24 02-May-24 02-May-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-3 17 13-Apr-24 02-May-24 02-May-24, WALL CONCRETE CASTING STAGE-3
Part-1 17 13-Apr-24 02-May-24 02-May-24, Part-1
PMP.4-WL-SG-3-P1.140
Room Walls Rebar Installation 4 16-Apr-24 21-Apr-24 Room Walls Rebar Installation

PMP.4-WL-SG-3-P1.150
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 21-Apr-24 22-Apr-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-3-P1.160
Room Walls Formwork Installation 5 22-Apr-24 28-Apr-24 Room Walls Formwork Installation

PMP.4-WL-SG-3-P1.170
Room Walls Concrete Casting 1 28-Apr-24 29-Apr-24 Room Walls Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
180 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.4-WL-SG-3-P1.180
Room Walls Curing work 1 29-Apr-24 30-Apr-24 Room Walls Curing work

PMP.4-WL-SG-3-P1.190
Room Walls Formwork Removel 2 30-Apr-24 02-May-24 Room Walls Formwork Removel

PMP.4-WL-SG-3-P1.200
Room Walls Scafolding for rebar 3 13-Apr-24 16-Apr-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-4 17 02-May-24 22-May-24 22-May-24, WALL CONCRETE CASTING STAGE-4
Part-1 17 02-May-24 22-May-24 22-May-24, Part-1
PMP.4-WL-SG-4-P1.140
Room Walls Rebar Installation 4 06-May-24 11-May-24 Room Walls Rebar Installation

PMP.4-WL-SG-4-P1.150
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 11-May-24 12-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-4-P1.160
Room Walls Formwork Installation 5 12-May-24 18-May-24 Room Walls Formwork Installation

PMP.4-WL-SG-4-P1.170
Room Walls Concrete Casting 1 18-May-24 19-May-24 Room Walls Concrete Casting

PMP.4-WL-SG-4-P1.180
Room Walls Curing work 1 19-May-24 20-May-24 Room Walls Curing work

PMP.4-WL-SG-4-P1.190
Room Walls Formwork Removel 2 20-May-24 22-May-24 Room Walls Formwork Removel

PMP.4-WL-SG-4-P1.200
Room Walls Scafolding for rebar 3 02-May-24 06-May-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 33 22-May-24 04-Jul-24 04-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 33 22-May-24 04-Jul-24 04-Jul-24, Part-1
PMP.4-SLB-AG-P1.130
Room Top Slab Formwork Installation 8 22-May-24 01-Jun-24 Room Top Slab Formwork Installation

PMP.4-SLB-AG-P1.140
Room Top Slab Rebar Installation 8 01-Jun-24 10-Jun-24 Room Top Slab Rebar Installation

PMP.4-SLB-AG-P1.150
Room Top Slab Concrete Casting 1 10-Jun-24 11-Jun-24 Room Top Slab Concrete Casting

PMP.4-SLB-AG-P1.160
Room Top slab Curing work 12 11-Jun-24 30-Jun-24 Room Top slab Curing work

PMP.4-SLB-AG-P1.170
Room Top Slab Formwork Removel 4 30-Jun-24 04-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 45 04-Jul-24 25-Aug-24 25-Aug-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 04-Jul-24 16-Jul-24 16-Jul-24, WALL WATER PROOFING STAGE-1
PMP.4-WP-WL-S1.120Surface preparation work 2 04-Jul-24 07-Jul-24 Surface preparation work

PMP.4-WP-WL-S1.130Applying of waterproofing material &Membrane Protection work 2 07-Jul-24 09-Jul-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S1.140L.S Back Filling 6 09-Jul-24 16-Jul-24 L.S Back Filling

WALL WATER PROOFING STAGE-2 10 16-Jul-24 28-Jul-24 28-Jul-24, WALL WATER PROOFING STAGE-2
PMP.4-WP-WL-S2.120Surface preparation work 2 16-Jul-24 18-Jul-24 Surface preparation work

PMP.4-WP-WL-S2.130Applying of waterproofing material &Membrane Protection work 2 18-Jul-24 21-Jul-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S2.140L.S Back Filling 6 21-Jul-24 28-Jul-24 L.S Back Filling

WALL WATER PROOFING STAGE-3 10 28-Jul-24 07-Aug-24 07-Aug-24, WALL WATER PROOFING STAGE-3
PMP.4-WP-WL-S3.120Surface preparation work 2 28-Jul-24 30-Jul-24 Surface preparation work

PMP.4-WP-WL-S3.130Applying of waterproofing material &Membrane Protection work 2 30-Jul-24 01-Aug-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S3.140L.S Back Filling 6 01-Aug-24 07-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-4 10 08-Aug-24 19-Aug-24 19-Aug-24, WALL WATER PROOFING STAGE-4
PMP.4-WP-WL-S4.120Surface preparation work 2 08-Aug-24 10-Aug-24 Surface preparation work

PMP.4-WP-WL-S4.130Applying of waterproofing material &Membrane Protection work 2 11-Aug-24 12-Aug-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S4.140L.S Back Filling 6 13-Aug-24 19-Aug-24 L.S Back Filling

TOP SLAB WATER PROOFING 5 19-Aug-24 25-Aug-24 25-Aug-24, TOP SLAB WATER PROOFING
PMP.4-WP-SLB-S1.120
Surface preparation work 2 19-Aug-24 21-Aug-24 Surface preparation work

PMP.4-WP-SLB-S1.130
Applying of waterproofing material &Membrane Protection work 2 21-Aug-24 24-Aug-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-SLB-S1.140
Leak Test 1 24-Aug-24 25-Aug-24 Leak Test

PLAIN CONCRETE ABOVE SLAB 9 25-Aug-24 04-Sep-24 04-Sep-24, PLAIN CONCRETE ABOVE SLAB
Part-1 9 25-Aug-24 04-Sep-24 04-Sep-24, Part-1
PMP.4-PC-P1.125 Plain Concrete Above Top Slab Formwork Installation 6 25-Aug-24 01-Sep-24 Plain Concrete Above Top Slab Formwork Installation

PMP.4-PC-P1.135 Plain Concrete Casting 1 01-Sep-24 02-Sep-24 Plain Concrete Casting

PMP.4-PC-P1.145 Plain Concrete curing work 1 02-Sep-24 03-Sep-24 Plain Concrete curing work

PMP.4-PC-P1.155 Plain Concrete Formwork removal 1 03-Sep-24 04-Sep-24 Plain Concrete Formwork removal

ELECTRICAL WORK 80 17-Apr-24 24-Jul-24 24-Jul-24, ELECTRICAL WORK

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
181 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER SYSTEM 52 17-Apr-24 22-Jun-24 22-Jun-24, POWER SYSTEM
LIGHTING SYSTEM 37 17-Apr-24 30-May-24 30-May-24, LIGHTING SYSTEM
LS-4-ELI.150 Lighting system Conduit and boxes Installation 8 17-Apr-24 27-Apr-24 Lighting system Conduit and boxes Installation

LS-4-ELI.160 Lighting system Cable Pulling 8 27-Apr-24 06-May-24 Lighting system Cable Pulling

LS-4-ELI.170 Lighting system Installations 8 06-May-24 15-May-24 Lighting system Installations

LS-4-ELI.180 Lighting system Termination 8 15-May-24 25-May-24 Lighting system Termination

LS-4-ELI.190 Lighting system Initial Testing 5 25-May-24 30-May-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 17-Apr-24 12-Jun-24 12-Jun-24, CABLE TRAY /CABLE ROUTING SYSTEM
LS-4-ECT.150 Cable Tray Installation 10 17-Apr-24 29-Apr-24 Cable Tray Installation

LS-4-ECT.160 Cable Tray Inspection 10 29-Apr-24 11-May-24 Cable Tray Inspection

LS-4-ECT.170 LV Cable pulling 10 11-May-24 22-May-24 LV Cable pulling

LS-4-ECT.180 LV Cable Termination 10 22-May-24 03-Jun-24 LV Cable Termination

LS-4-ECT.190 LV Cable Initial Testing 8 03-Jun-24 12-Jun-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 17-Apr-24 02-Jun-24 02-Jun-24, SMALL POWER SYSTEM


LS-4-ESP.150 Small Power Conduit and boxes Installation 12 17-Apr-24 01-May-24 Small Power Conduit and boxes Installation

LS-4-ESP.160 Small Power Cable Pulling 10 01-May-24 13-May-24 Small Power Cable Pulling

LS-4-ESP.170 Small Power Installations 6 13-May-24 20-May-24 Small Power Installations

LS-4-ESP.180 Small Power Termination 6 20-May-24 27-May-24 Small Power Termination

LS-4-ESP.190 Small Power Initial Testing 5 27-May-24 02-Jun-24 Small Power Initial Testing

POWER DISTRIBUTION 40 01-May-24 22-Jun-24 22-Jun-24, POWER DISTRIBUTION


GENERATOR 40 01-May-24 22-Jun-24 22-Jun-24, GENERATOR
LS-4-EPD.520 Generator Cable Tray Installation 7 01-May-24 09-May-24 Generator Cable Tray Installation

LS-4-EPD.530 Generator Cable Pulling 7 09-May-24 18-May-24 Generator Cable Pulling

LS-4-EPD.540 Generator Cell Pannel Installation 7 18-May-24 26-May-24 Generator Cell Pannel Installation

LS-4-EPD.550 Generator Installation 7 26-May-24 03-Jun-24 Generator Installation

LS-4-EPD.560 Generator Pannel / Cable Termination 7 03-Jun-24 11-Jun-24 Generator Pannel / Cable Termination

LS-4-EPD.570 Generator Pannel / Cable initial Testing 5 11-Jun-24 22-Jun-24 Generator Pannel / Cable initial Testing

UPS 29 01-May-24 04-Jun-24 04-Jun-24, UPS


LS-4-EPD.580 UPS Cable Tray Installation 5 01-May-24 07-May-24 UPS Cable Tray Installation

LS-4-EPD.590 UPS Cable Pulling 5 07-May-24 13-May-24 UPS Cable Pulling

LS-4-EPD.600 UPS Pannel Installation 5 13-May-24 19-May-24 UPS Pannel Installation

LS-4-EPD.610 UPS Installation 5 19-May-24 25-May-24 UPS Installation

LS-4-EPD.620 UPS Pannel / Cable Termination 5 25-May-24 30-May-24 UPS Pannel / Cable Termination

LS-4-EPD.630 UPS Pannel / Cable initial Testing 4 30-May-24 04-Jun-24 UPS Pannel / Cable initial Testing

MDB 33 01-May-24 09-Jun-24 09-Jun-24, MDB


LS-4-EPD.640 MDB Cable Tray Installation 7 01-May-24 09-May-24 MDB Cable Tray Installation

LS-4-EPD.650 MDB Cable Pulling 7 09-May-24 18-May-24 MDB Cable Pulling

LS-4-EPD.660 MDB Pannel Installation 7 18-May-24 26-May-24 MDB Pannel Installation

LS-4-EPD.670 MDB Pannel / Cable Termination 7 26-May-24 03-Jun-24 MDB Pannel / Cable Termination

LS-4-EPD.680 MDB Pannel / Cable initial Testing 5 03-Jun-24 09-Jun-24 MDB Pannel / Cable initial Testing

MCC 33 09-May-24 22-Jun-24 22-Jun-24, MCC


LS-4-EPD.740 MCC Cable Tray Installation 7 09-May-24 18-May-24 MCC Cable Tray Installation

LS-4-EPD.750 MCC Cable Pulling 7 18-May-24 26-May-24 MCC Cable Pulling

LS-4-EPD.760 MCC Pannel Installation 7 26-May-24 03-Jun-24 MCC Pannel Installation

LS-4-EPD.770 MCC Pannel / Cable Termination 7 03-Jun-24 11-Jun-24 MCC Pannel / Cable Termination

LS-4-EPD.780 MCC Pannel / Cable initial Testing 5 11-Jun-24 22-Jun-24 MCC Pannel / Cable initial Testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
182 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
SMSB 24 09-May-24 06-Jun-24 06-Jun-24, SMSB
LS-4-EPD.690 SMSB Cable Tray Installation 5 09-May-24 15-May-24 SMSB Cable Tray Installation

LS-4-EPD.700 SMSB Cable Pulling 5 15-May-24 21-May-24 SMSB Cable Pulling

LS-4-EPD.710 SMSB Pannel Installation 5 21-May-24 27-May-24 SMSB Pannel Installation

LS-4-EPD.720 SMSB Pannel / Cable Termination 5 27-May-24 02-Jun-24 SMSB Pannel / Cable Termination

LS-4-EPD.730 SMSB Pannel / Cable initial Testing 4 02-Jun-24 06-Jun-24 SMSB Pannel / Cable initial Testing

DB 24 09-May-24 06-Jun-24 06-Jun-24, DB


LS-4-EPD.790 DB Cable Tray Installation 5 09-May-24 15-May-24 DB Cable Tray Installation

LS-4-EPD.800 DB Cable Pulling 5 15-May-24 21-May-24 DB Cable Pulling

LS-4-EPD.810 DB Pannel Installation 5 21-May-24 27-May-24 DB Pannel Installation

LS-4-EPD.820 DB Pannel / Cable Termination 5 27-May-24 02-Jun-24 DB Pannel / Cable Termination

LS-4-EPD.830 DB Pannel / Cable initial Testing 4 02-Jun-24 06-Jun-24 DB Pannel / Cable initial Testing

ISOLATOR 24 15-May-24 12-Jun-24 12-Jun-24, ISOLATOR


LS-4-EPD.840 Isolators Cable Tray Installation 5 15-May-24 21-May-24 Isolators Cable Tray Installation

LS-4-EPD.850 Isolators Cable Pulling 5 21-May-24 27-May-24 Isolators Cable Pulling

LS-4-EPD.860 Isolators Pannel Installation 5 27-May-24 02-Jun-24 Isolators Pannel Installation

LS-4-EPD.870 Isolators Pannel / Cable Termination 5 02-Jun-24 08-Jun-24 Isolators Pannel / Cable Termination

LS-4-EPD.880 Isolators Pannel / Cable initial Testing 4 08-Jun-24 12-Jun-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 15-May-24 12-Jun-24 12-Jun-24, LCP/ ELCP


LS-4-EPD.890 LCP/ELCP Cable Tray Installation 5 15-May-24 21-May-24 LCP/ELCP Cable Tray Installation

LS-4-EPD.900 LCP/ELCP Cable Pulling 5 21-May-24 27-May-24 LCP/ELCP Cable Pulling

LS-4-EPD.910 LCP/ELCP Pannel Installation 5 27-May-24 02-Jun-24 LCP/ELCP Pannel Installation

LS-4-EPD.920 LCP/ELCP Pannel / Cable Termination 5 02-Jun-24 08-Jun-24 LCP/ELCP Pannel / Cable Termination

LS-4-EPD.930 LCP/ELCP Pannel / Cable initial Testing 4 08-Jun-24 12-Jun-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 51 21-May-24 24-Jul-24 24-Jul-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 21-May-24 14-Jul-24 14-Jul-24, FIRE ALARM SYSTEM
LS-4-ELFA.150 Fire Alarm Conduit /Cable Tray Installation 9 21-May-24 01-Jun-24 Fire Alarm Conduit /Cable Tray Installation

LS-4-ELFA.160 Fire Alarm Cable Pulling 9 01-Jun-24 11-Jun-24 Fire Alarm Cable Pulling

LS-4-ELFA.170 Fire Alarm Devices Installation 9 11-Jun-24 26-Jun-24 Fire Alarm Devices Installation

LS-4-ELFA.180 Fire Alarm Devices and Cable Termination 9 26-Jun-24 07-Jul-24 Fire Alarm Devices and Cable Termination

LS-4-ELFA.190 Fire Alarm Devices and Cable initial Testing 6 07-Jul-24 14-Jul-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 21-May-24 14-Jul-24 14-Jul-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
LS-4-ELVS.150 ICT System Conduit /Cable Tray Installation 9 21-May-24 01-Jun-24 ICT System Conduit /Cable Tray Installation

LS-4-ELVS.160 ICT System Cable Pulling 9 01-Jun-24 11-Jun-24 ICT System Cable Pulling

LS-4-ELVS.170 ICT System Devices Installation 9 11-Jun-24 26-Jun-24 ICT System Devices Installation

LS-4-ELVS.180 ICT System Devices and Cable Termination 9 26-Jun-24 07-Jul-24 ICT System Devices and Cable Termination

LS-4-ELVS.190 ICT System Devices and Cable initial Testing 6 07-Jul-24 14-Jul-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 21-May-24 14-Jul-24 14-Jul-24, ACCESS CONTROL SYSTEM


LS-4-ELAC.150 Access Control System Conduit /Cable Tray Installation 9 21-May-24 01-Jun-24 Access Control System Conduit /Cable Tray Installation

LS-4-ELAC.160 Access Control System Cable Pulling 9 01-Jun-24 11-Jun-24 Access Control System Cable Pulling

LS-4-ELAC.170 Access Control System Devices Installation 9 11-Jun-24 26-Jun-24 Access Control System Devices Installation

LS-4-ELAC.180 Access Control System Devices and Cable Termination 9 26-Jun-24 07-Jul-24 Access Control System Devices and Cable Termination

LS-4-ELAC.190 Access Control System Devices and Cable initial Testing 6 07-Jul-24 14-Jul-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 01-Jun-24 24-Jul-24 24-Jul-24, PUBLIC ADDRESS SYSTEM


LS-4-ELPA.150 Public Address System Conduit /Cable Tray Installation 9 01-Jun-24 11-Jun-24 Public Address System Conduit /Cable Tray Installation

LS-4-ELPA.160 Public Address System Cable Pulling 9 11-Jun-24 26-Jun-24 Public Address System Cable Pulling

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
183 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-4-ELPA.170 Public Address System Devices Installation 9 26-Jun-24 07-Jul-24 Public Address System Devices Installation

LS-4-ELPA.180 Public Address System Devices and Cable Termination 9 07-Jul-24 17-Jul-24 Public Address System Devices and Cable Termination

LS-4-ELPA.190 Public Address System Devices and Cable initial Testing 6 17-Jul-24 24-Jul-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 01-Jun-24 24-Jul-24 24-Jul-24, SCADA SYSTEM


LS-4-ELSC.150 SCADA System Conduit /Cable Tray Installation 9 01-Jun-24 11-Jun-24 SCADA System Conduit /Cable Tray Installation

LS-4-ELSC.160 SCADA System Cable Pulling 9 11-Jun-24 26-Jun-24 SCADA System Cable Pulling

LS-4-ELSC.170 SCADA System Devices Installation 9 26-Jun-24 07-Jul-24 SCADA System Devices Installation

LS-4-ELSC.180 SCADA System Devices and Cable Termination 9 07-Jul-24 17-Jul-24 SCADA System Devices and Cable Termination

LS-4-ELSC.190 SCADA System Devices and Cable initial Testing 6 17-Jul-24 24-Jul-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 01-Jun-24 24-Jul-24 24-Jul-24, RADIO RE- BROADCOASTING/ TETRA
LS-4-ELRD.150 Radio/TETRA System Conduit /Cable Tray Installation 9 01-Jun-24 11-Jun-24 Radio/TETRA System Conduit /Cable Tray Installation

LS-4-ELRD.160 Radio/TETRA System Cable Pulling 9 11-Jun-24 26-Jun-24 Radio/TETRA System Cable Pulling

LS-4-ELRD.170 Radio/TETRA System Devices Installation 9 26-Jun-24 07-Jul-24 Radio/TETRA System Devices Installation

LS-4-ELRD.180 Radio/TETRA System Devices and Cable Termination 9 07-Jul-24 17-Jul-24 Radio/TETRA System Devices and Cable Termination

LS-4-ELRD.190 Radio/TETRA System Devices and Cable initial Testing 6 17-Jul-24 24-Jul-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK 15 11-Jun-24 03-Jul-24 03-Jul-24, MECHANICAL WORK


FIRE FIGHTING 13 11-Jun-24 01-Jul-24 01-Jul-24, FIRE FIGHTING
LS-4-MFF.140 Fire Fighting system Pipe and accessories installation 11 11-Jun-24 29-Jun-24 Fire Fighting system Pipe and accessories installation

LS-4-MFF.150 Fire Fighting system fire hose cabinet/extingusher installation 3 25-Jun-24 29-Jun-24 Fire Fighting system fire hose cabinet/extingusher installation

LS-4-MFF.160 Fire Fighting system initial testing 2 29-Jun-24 01-Jul-24 Fire Fighting system initial testing

HVAC 15 11-Jun-24 03-Jul-24 03-Jul-24, HVAC


LS-4-MHV.140 Fan installation 4 25-Jun-24 30-Jun-24 Fan installation

LS-4-MHV.150 Duct and accessories installation 12 11-Jun-24 30-Jun-24 Duct and accessories installation

LS-4-MHV.160 HVAC inital testing 3 30-Jun-24 03-Jul-24 HVAC inital testing

PLUMBING 4 11-Jun-24 20-Jun-24 20-Jun-24, PLUMBING


LS-4-MPL.120 Plumbing drainage system installation 3 11-Jun-24 19-Jun-24 Plumbing drainage system installation

LS-4-MPL.130 Plumbing drainage system initial testing 1 19-Jun-24 20-Jun-24 Plumbing drainage system initial testing

lIFTING STATION 05 (IN ZONE 04) 405 09-May-23 05-Sep-24 05-Sep-24, lIFTING STATION 05 (IN ZONE 04)
ENGINEERING 95 24-May-23 16-Sep-23 16-Sep-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 95 24-May-23 16-Sep-23 16-Sep-23, SHOP DRAWING SUBMITTALAND APPROVAL
EARTH WORKS 28 29-Jul-23 30-Aug-23 30-Aug-23, EARTH WORKS
JAH-ENG-SH-LS05.975
Shoring Design Preparation & Submission 14 29-Jul-23 14-Aug-23 Shoring Design Preparation & Submission

JAH-ENG-SH-LS05.980
Shoring Design Review & Approval 14 14-Aug-23 30-Aug-23 Shoring Design Review & Approval

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


PMP.3-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

PMP.3-ENG-CV-ST.135Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

PMP.3-ENG-CV-ST.140Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

PMP.3-ENG-CV-ST.145Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

PMP.3-ENG-CV-ST.150Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

PMP.3-ENG-CV-ST.155Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
PMP.3-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

PMP.3-ENG-MC-ST.115
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
PMP.3-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

PMP.3-ENG-MC-HC.115
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
184 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.3-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

PMP.3-ENG-MC-PI.115
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 95 24-May-23 16-Sep-23 16-Sep-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
PMP.3-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

PMP.3-ENG-EL-CT.115
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


PMP.3-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

PMP.3-ENG-EL-PC.115
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


PMP.3-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

PMP.3-ENG-EL-LS.115
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


PMP.3-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

PMP.3-ENG-EL-EI.115Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 08-Jun-23 12-Jul-23 12-Jul-23, LIGHTNING PROTECTION SYSTEM


PMP.3-ENG-EL-LP.110Lightning Protection Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Lightning Protection Drawings Preparation & Submission

PMP.3-ENG-EL-LP.115Lightning Protection Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Lightning Protection Shop Drawings Review & Approval

EARTHING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, EARTHING SYSTEM


PMP.3-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Earthing System Shop Drawings Preparation & Submission

PMP.3-ENG-EL-ES.115
Earthing System Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Earthing System Drawings Review & Approval

LOW CURRENT 95 24-May-23 16-Sep-23 16-Sep-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
PMP.3-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-FA.25
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
PMP.3-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-PH.25
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
PMP.3-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-PA.25
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


PMP.3-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-VS.25
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


PMP.3-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-AC.25
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


PMP.3-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-RB.25
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, SCADA SYSTEM


PMP.3-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 SCADA system Shop Drawings Preparation & Submission

PMP.3-ENG-ELL-SD.25
SCADA system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 SCADA system Shop Drawings Review & Approval

PROCUREMENT 294 12-Aug-23 29-Jul-24 29-Jul-24, PROCUREMENT


CIVIL/STRUCTURAL 16 12-Aug-23 30-Aug-23 30-Aug-23, CIVIL/STRUCTURAL
PMP.3RO-CVL.110 Issue Purchase Order 6 12-Aug-23 19-Aug-23 Issue Purchase Order

PMP.3RO-CVL.115 Material Delivery 10 19-Aug-23 30-Aug-23 Material Delivery

MECHANICAL 105 20-Mar-24 29-Jul-24 29-Jul-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 20-Mar-24 29-Jul-24 29-Jul-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 20-Mar-24 29-Jul-24 29-Jul-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
185 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.3RO-MC-FT.110 Issue Purchase Order 15 20-Mar-24 07-Apr-24 Issue Purchase Order

PMP.3RO-MC-FT.115 Material Delivery 90 07-Apr-24 29-Jul-24 Material Delivery

VENTILATION SYSTEM 105 20-Mar-24 29-Jul-24 29-Jul-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 20-Mar-24 29-Jul-24 29-Jul-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
PMP.3RO-MC-DCT.110
Issue Purchase Order 15 20-Mar-24 07-Apr-24 Issue Purchase Order

PMP.3RO-MC-DCT.115
Material Delivery 90 07-Apr-24 29-Jul-24 Material Delivery

AIR CONDITIONING WORKS 105 20-Mar-24 29-Jul-24 29-Jul-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 20-Mar-24 29-Jul-24 29-Jul-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
PMP.3RO-MC-SPU.110
Issue Purchase Order 15 20-Mar-24 07-Apr-24 Issue Purchase Order

PMP.3RO-MC-SPU.115
Material Delivery 90 07-Apr-24 29-Jul-24 Material Delivery

PLUMBING SYSTEM 105 20-Mar-24 29-Jul-24 29-Jul-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 20-Mar-24 29-Jul-24 29-Jul-24, PUMPS,PIPES,FITTINGS,VALVES
PMP.3RO-MC-PMI.110
Issue Purchase Order 15 20-Mar-24 07-Apr-24 Issue Purchase Order

PMP.3RO-MC-PMI.115
Material Delivery 90 07-Apr-24 29-Jul-24 Material Delivery

ELECTRICAL 143 27-Jan-24 18-Jul-24 18-Jul-24, ELECTRICAL


CABLE TRAY 105 27-Jan-24 01-Jun-24 01-Jun-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 27-Jan-24 01-Jun-24 01-Jun-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
PMP.3RO-EL-CTRY.130
Issue Purchase Order 15 27-Jan-24 13-Feb-24 Issue Purchase Order

PMP.3RO-EL-CTRY.135
Material Delivery 90 13-Feb-24 01-Jun-24 Material Delivery

POWER CABLES 105 27-Jan-24 01-Jun-24 01-Jun-24, POWER CABLES


HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 27-Jan-24 01-Jun-24 01-Jun-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
PMP.3RO-EL-PWCL.140
Issue Purchase Order 15 27-Jan-24 13-Feb-24 Issue Purchase Order

PMP.3RO-EL-PWCL.145
Material Delivery 90 13-Feb-24 01-Jun-24 Material Delivery

LIGHTING SYSTEM 105 05-Feb-24 10-Jun-24 10-Jun-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 05-Feb-24 10-Jun-24 10-Jun-24, CONDUIT,LIGHT
PMP.3RO-EL-LTS.110Issue Purchase Order 15 05-Feb-24 22-Feb-24 Issue Purchase Order

PMP.3RO-EL-LTS.115Material Delivery 90 22-Feb-24 10-Jun-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 05-Feb-24 10-Jun-24 10-Jun-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 05-Feb-24 10-Jun-24 10-Jun-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
PMP.3RO-EL-INSL.190
Issue Purchase Order 15 05-Feb-24 22-Feb-24 Issue Purchase Order

PMP.3RO-EL-INSL.195
Material Delivery 90 22-Feb-24 10-Jun-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 14-Feb-24 24-Jun-24 24-Jun-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 14-Feb-24 24-Jun-24 24-Jun-24, LIGHTNING PROTECTION SYSTEM
PMP.3RO-EL-LPS.110Issue Purchase Order 15 14-Feb-24 03-Mar-24 Issue Purchase Order

PMP.3RO-EL-LPS.115Material Delivery 90 03-Mar-24 24-Jun-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 14-Feb-24 24-Jun-24 24-Jun-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 14-Feb-24 24-Jun-24 24-Jun-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
PMP.3RO-EL-ERS.120Issue Purchase Order 15 14-Feb-24 03-Mar-24 Issue Purchase Order

PMP.3RO-EL-ERS.125Material Delivery 90 03-Mar-24 24-Jun-24 Material Delivery

LOW CURRENT 114 29-Feb-24 18-Jul-24 18-Jul-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 29-Feb-24 09-Jul-24 09-Jul-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 29-Feb-24 09-Jul-24 09-Jul-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
PMP.3R-ELL-FA130 Issue Purchase Order 15 29-Feb-24 18-Mar-24 Issue Purchase Order

PMP.3R-ELL-FA135 Material Delivery 90 18-Mar-24 09-Jul-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 29-Feb-24 09-Jul-24 09-Jul-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 29-Feb-24 09-Jul-24 09-Jul-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
PMP.3R-ELL-PH.130Issue Purchase Order 15 29-Feb-24 18-Mar-24 Issue Purchase Order

PMP.3R-ELL-PH.135Material Delivery 90 18-Mar-24 09-Jul-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 11-Mar-24 18-Jul-24 18-Jul-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 11-Mar-24 18-Jul-24 18-Jul-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
PMP.3R-ELL-PA.120Issue Purchase Order 15 11-Mar-24 27-Mar-24 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
186 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.3R-ELL-PA.125Material Delivery 90 28-Mar-24 18-Jul-24 Material Delivery

VIDEO SURVEILLANCE 105 29-Feb-24 09-Jul-24 09-Jul-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 29-Feb-24 09-Jul-24 09-Jul-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
PMP.3R-ELL-VS.120Issue Purchase Order 15 29-Feb-24 18-Mar-24 Issue Purchase Order

PMP.3R-ELL-VS.125Material Delivery 90 18-Mar-24 09-Jul-24 Material Delivery

ACCESS CONTROL SYSTEM 105 29-Feb-24 09-Jul-24 09-Jul-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 29-Feb-24 09-Jul-24 09-Jul-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
PMP.3R-ELL-AC.130Issue Purchase Order 15 29-Feb-24 18-Mar-24 Issue Purchase Order

PMP.3R-ELL-AC.135Material Delivery 90 18-Mar-24 09-Jul-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 11-Mar-24 18-Jul-24 18-Jul-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 11-Mar-24 18-Jul-24 18-Jul-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
PMP.3R-ELL-RB.120Issue Purchase Order 15 11-Mar-24 27-Mar-24 Issue Purchase Order

PMP.3R-ELL-RB.125Material Delivery 90 28-Mar-24 18-Jul-24 Material Delivery

SCADA SYSTEM 105 11-Mar-24 18-Jul-24 18-Jul-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 11-Mar-24 18-Jul-24 18-Jul-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
PMP.3R-ELL-SDA.130
Issue Purchase Order 15 11-Mar-24 27-Mar-24 Issue Purchase Order

PMP.3R-ELL-SDA.135
Material Delivery 90 28-Mar-24 18-Jul-24 Material Delivery

CONSTRUCTION 405 09-May-23 05-Sep-24 05-Sep-24, CONSTRUCTION


EXCAVATION WORKS 94 09-May-23 30-Aug-23 30-Aug-23, EXCAVATION WORKS
T2-CON-Z10-EX-LS.155Excavation 94 09-May-23 30-Aug-23 Excavation

SHORING WORKS 0 30-Aug-23 30-Aug-23 30-Aug-23, SHORING WORKS


T2-CON-Z10-SH-LS.230Piles 0 30-Aug-23 30-Aug-23 Piles

T2-CON-Z10-SH-LS.235Capping Beam 0 30-Aug-23 30-Aug-23 Capping Beam

T2-CON-Z10-SH-LS.240Anchore 0 30-Aug-23 30-Aug-23 Anchore

SOIL IMPROVEMENT WORKS 0


STRUCTURAL WORKS 235 30-Aug-23 04-Jun-24 04-Jun-24, STRUCTURAL WORKS
FOUNDATION 16 30-Aug-23 18-Sep-23 18-Sep-23, FOUNDATION
Part-1 16 30-Aug-23 18-Sep-23 18-Sep-23, Part-1
PMP.3-FDN-P1.150 Foundation Blinding concrete casting 1 30-Aug-23 31-Aug-23 Foundation Blinding concrete casting

PMP.3-FDN-P1.155 Foundation water proofing on blinding concrete 1 31-Aug-23 02-Sep-23 Foundation water proofing on blinding concrete

PMP.3-FDN-P1.160 Foundation Protection screed on water poofing 1 02-Sep-23 03-Sep-23 Foundation Protection screed on water poofing

PMP.3-FDN-P1.165 Foundation Curing for screed 1 03-Sep-23 04-Sep-23 Foundation Curing for screed

PMP.3-FDN-P1.170 Foundation Rebar installation 5 04-Sep-23 10-Sep-23 Foundation Rebar installation

PMP.3-FDN-P1.175 Foundation Formwork installation 4 10-Sep-23 14-Sep-23 Foundation Formwork installation

PMP.3-FDN-P1.185 Foundation concrete casting 1 14-Sep-23 16-Sep-23 Foundation concrete casting

PMP.3-FDN-P1.190 Foundation concrete curing 1 16-Sep-23 17-Sep-23 Foundation concrete curing

PMP.3-FDN-P1.195 Foundation Formwork Removal 1 17-Sep-23 18-Sep-23 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 21 16-Sep-23 11-Oct-23 11-Oct-23, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 21 16-Sep-23 11-Oct-23 11-Oct-23, WALL CONCRETE CASTING STAGE-1
Part-1 21 16-Sep-23 11-Oct-23 11-Oct-23, Part-1
PMP.3-WL-SG-1-P1.135
Room Walls Rebar Installation 6 19-Sep-23 27-Sep-23 Room Walls Rebar Installation

PMP.3-WL-SG-1-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 27-Sep-23 28-Sep-23 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.3-WL-SG-1-P1.145
Room Walls Formwork Installation 7 28-Sep-23 07-Oct-23 Room Walls Formwork Installation

PMP.3-WL-SG-1-P1.150
Room Walls Concrete Casting 1 07-Oct-23 08-Oct-23 Room Walls Concrete Casting

PMP.3-WL-SG-1-P1.155
Room Walls Curing work 1 08-Oct-23 09-Oct-23 Room Walls Curing work

PMP.3-WL-SG-1-P1.160
Room Walls Formwork Removel 2 09-Oct-23 11-Oct-23 Room Walls Formwork Removel

PMP.3-WL-SG-1-P1.165
Room Walls Scafolding for rebar 3 16-Sep-23 19-Sep-23 Room Walls Scafolding for rebar

MIDDLE SLAB 37 11-Oct-23 23-Nov-23 23-Nov-23, MIDDLE SLAB


Part-1 37 11-Oct-23 23-Nov-23 23-Nov-23, Part-1
PMP.3-MS-P1.125 Room Top Slab Formwork Installation 12 11-Oct-23 25-Oct-23 Room Top Slab Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
187 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.3-MS-P1.130 Room Top Slab Rebar Installation 8 25-Oct-23 04-Nov-23 Room Top Slab Rebar Installation

PMP.3-MS-P1.135 Room Top Slab Concrete Casting 1 04-Nov-23 05-Nov-23 Room Top Slab Concrete Casting

PMP.3-MS-P1.140 Room Top slab Curing work 12 05-Nov-23 19-Nov-23 Room Top slab Curing work

PMP.3-MS-P1.145 Room Top Slab Formwork Removel 4 19-Nov-23 23-Nov-23 Room Top Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 20 23-Nov-23 17-Dec-23 17-Dec-23, WALL CONCRETE CASTING STAGE-2
Part-1 20 23-Nov-23 17-Dec-23 17-Dec-23, Part-1
PMP.3-WL-SG-2-P1.135
Room Walls Rebar Installation 5 27-Nov-23 03-Dec-23 Room Walls Rebar Installation

PMP.3-WL-SG-2-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 03-Dec-23 04-Dec-23 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.3-WL-SG-2-P1.145
Room Walls Formwork Installation 7 04-Dec-23 12-Dec-23 Room Walls Formwork Installation

PMP.3-WL-SG-2-P1.150
Room Walls Concrete Casting 1 12-Dec-23 13-Dec-23 Room Walls Concrete Casting

PMP.3-WL-SG-2-P1.155
Room Walls Curing work 1 13-Dec-23 14-Dec-23 Room Walls Curing work

PMP.3-WL-SG-2-P1.160
Room Walls Formwork Removel 2 14-Dec-23 17-Dec-23 Room Walls Formwork Removel

PMP.3-WL-SG-2-P1.165
Room Walls Scafolding for rebar 3 23-Nov-23 27-Nov-23 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 37 17-Dec-23 29-Jan-24 29-Jan-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 17-Dec-23 29-Jan-24 29-Jan-24, Part-1
PMP.3-TS-P1.125 Room Top Slab Formwork Installation 12 17-Dec-23 31-Dec-23 Room Top Slab Formwork Installation

PMP.3-TS-P1.130 Room Top Slab Rebar Installation 8 31-Dec-23 09-Jan-24 Room Top Slab Rebar Installation

PMP.3-TS-P1.135 Room Top Slab Concrete Casting 1 09-Jan-24 10-Jan-24 Room Top Slab Concrete Casting

PMP.3-TS-P1.140 Room Top slab Curing work 12 10-Jan-24 24-Jan-24 Room Top slab Curing work

PMP.3-TS-P1.145 Room Top Slab Formwork Removel 4 24-Jan-24 29-Jan-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 17 24-Jan-24 13-Feb-24 13-Feb-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-3 17 24-Jan-24 13-Feb-24 13-Feb-24, WALL CONCRETE CASTING STAGE-3
Part-1 17 24-Jan-24 13-Feb-24 13-Feb-24, Part-1
PMP.3-WL-SG-3-P1.135
Room Walls Rebar Installation 4 28-Jan-24 01-Feb-24 Room Walls Rebar Installation

PMP.3-WL-SG-3-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 01-Feb-24 03-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.3-WL-SG-3-P1.145
Room Walls Formwork Installation 5 03-Feb-24 08-Feb-24 Room Walls Formwork Installation

PMP.3-WL-SG-3-P1.150
Room Walls Concrete Casting 1 08-Feb-24 10-Feb-24 Room Walls Concrete Casting

PMP.3-WL-SG-3-P1.155
Room Walls Curing work 1 10-Feb-24 11-Feb-24 Room Walls Curing work

PMP.3-WL-SG-3-P1.160
Room Walls Formwork Removel 2 11-Feb-24 13-Feb-24 Room Walls Formwork Removel

PMP.3-WL-SG-3-P1.165
Room Walls Scafolding for rebar 3 24-Jan-24 28-Jan-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-4 17 13-Feb-24 03-Mar-24 03-Mar-24, WALL CONCRETE CASTING STAGE-4
Part-1 17 13-Feb-24 03-Mar-24 03-Mar-24, Part-1
PMP.3-WL-SG-4-P1.135
Room Walls Rebar Installation 4 17-Feb-24 21-Feb-24 Room Walls Rebar Installation

PMP.3-WL-SG-4-P1.140
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 21-Feb-24 21-Feb-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.3-WL-SG-4-P1.145
Room Walls Formwork Installation 5 22-Feb-24 27-Feb-24 Room Walls Formwork Installation

PMP.3-WL-SG-4-P1.150
Room Walls Concrete Casting 1 28-Feb-24 28-Feb-24 Room Walls Concrete Casting

PMP.3-WL-SG-4-P1.155
Room Walls Curing work 1 29-Feb-24 29-Feb-24 Room Walls Curing work

PMP.3-WL-SG-4-P1.160
Room Walls Formwork Removel 2 02-Mar-24 03-Mar-24 Room Walls Formwork Removel

PMP.3-WL-SG-4-P1.165
Room Walls Scafolding for rebar 3 13-Feb-24 17-Feb-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 33 04-Mar-24 14-Apr-24 14-Apr-24, SLAB ABOVE GROUND LEVEL
Part-1 33 04-Mar-24 14-Apr-24 14-Apr-24, Part-1
PMP.3-SLB-AG-P1.125
Room Top Slab Formwork Installation 8 04-Mar-24 12-Mar-24 Room Top Slab Formwork Installation

PMP.3-SLB-AG-P1.130
Room Top Slab Rebar Installation 8 13-Mar-24 21-Mar-24 Room Top Slab Rebar Installation

PMP.3-SLB-AG-P1.135
Room Top Slab Concrete Casting 1 23-Mar-24 23-Mar-24 Room Top Slab Concrete Casting

PMP.3-SLB-AG-P1.140
Room Top slab Curing work 12 24-Mar-24 06-Apr-24 Room Top slab Curing work

PMP.3-SLB-AG-P1.145
Room Top Slab Formwork Removel 4 07-Apr-24 14-Apr-24 Room Top Slab Formwork Removel

WATER PROOFING 35 15-Apr-24 25-May-24 25-May-24, WATER PROOFING

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
188 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL WATER PROOFING STAGE-1 8 15-Apr-24 23-Apr-24 23-Apr-24, WALL WATER PROOFING STAGE-1
PMP.3-WP-WL-S1.115Surface preparation work 2 15-Apr-24 16-Apr-24 Surface preparation work

PMP.3-WP-WL-S1.120Applying of waterproofing material &Membrane Protection work 2 17-Apr-24 18-Apr-24 Applying of waterproofing material &Membrane Protection work

PMP.3-WP-WL-S1.125L.S Back Filling 4 20-Apr-24 23-Apr-24 L.S Back Filling

WALL WATER PROOFING STAGE-2 8 23-Apr-24 02-May-24 02-May-24, WALL WATER PROOFING STAGE-2
PMP.3-WP-WL-S2.115Surface preparation work 2 23-Apr-24 25-Apr-24 Surface preparation work

PMP.3-WP-WL-S2.120Applying of waterproofing material &Membrane Protection work 2 25-Apr-24 28-Apr-24 Applying of waterproofing material &Membrane Protection work

PMP.3-WP-WL-S2.125L.S Back Filling 4 28-Apr-24 02-May-24 L.S Back Filling

WALL WATER PROOFING STAGE-3 7 02-May-24 11-May-24 11-May-24, WALL WATER PROOFING STAGE-3
PMP.3-WP-WL-S3.115Surface preparation work 2 02-May-24 05-May-24 Surface preparation work

PMP.3-WP-WL-S3.120Applying of waterproofing material &Membrane Protection work 2 05-May-24 07-May-24 Applying of waterproofing material &Membrane Protection work

PMP.3-WP-WL-S3.125L.S Back Filling 3 07-May-24 11-May-24 L.S Back Filling

WALL WATER PROOFING STAGE-4 7 11-May-24 19-May-24 19-May-24, WALL WATER PROOFING STAGE-4
PMP.3-WP-WL-S4.115Surface preparation work 2 11-May-24 13-May-24 Surface preparation work

PMP.3-WP-WL-S4.120Applying of waterproofing material &Membrane Protection work 2 13-May-24 15-May-24 Applying of waterproofing material &Membrane Protection work

PMP.3-WP-WL-S4.125L.S Back Filling 3 15-May-24 19-May-24 L.S Back Filling

TOP SLAB WATER PROOFING 5 19-May-24 25-May-24 25-May-24, TOP SLAB WATER PROOFING
PMP.3-WP-SLB-S1.115
Surface preparation work 2 19-May-24 21-May-24 Surface preparation work

PMP.3-WP-SLB-S1.120
Applying of waterproofing material &Membrane Protection work 2 21-May-24 23-May-24 Applying of waterproofing material &Membrane Protection work

PMP.3-WP-SLB-S1.125
Leak Test 1 23-May-24 25-May-24 Leak Test

PLAIN CONCRETE ABOVE SLAB 9 25-May-24 04-Jun-24 04-Jun-24, PLAIN CONCRETE ABOVE SLAB
Part-1 9 25-May-24 04-Jun-24 04-Jun-24, Part-1
PMP.3-PC-P1.120 Plain Concrete Above Top Slab Formwork Installation 6 25-May-24 01-Jun-24 Plain Concrete Above Top Slab Formwork Installation

PMP.3-PC-P1.125 Plain Concrete Casting 1 01-Jun-24 02-Jun-24 Plain Concrete Casting

PMP.3-PC-P1.130 Plain Concrete curing work 1 02-Jun-24 03-Jun-24 Plain Concrete curing work

PMP.3-PC-P1.135 Plain Concrete Formwork removal 1 03-Jun-24 04-Jun-24 Plain Concrete Formwork removal

MECHANICAL ROOM MEP (UCR) 79 01-Jun-24 05-Sep-24 05-Sep-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK 79 01-Jun-24 05-Sep-24 05-Sep-24, ELECTRICAL WORK
POWER SYSTEM 51 01-Jun-24 04-Aug-24 04-Aug-24, POWER SYSTEM
LIGHTING SYSTEM 37 01-Jun-24 17-Jul-24 17-Jul-24, LIGHTING SYSTEM
LS-3-ELI.105 Lighting system Conduit and boxes Installation 8 01-Jun-24 10-Jun-24 Lighting system Conduit and boxes Installation

LS-3-ELI.115 Lighting system Cable Pulling 8 10-Jun-24 24-Jun-24 Lighting system Cable Pulling

LS-3-ELI.125 Lighting system Installations 8 24-Jun-24 03-Jul-24 Lighting system Installations

LS-3-ELI.135 Lighting system Termination 8 03-Jul-24 13-Jul-24 Lighting system Termination

LS-3-ELI.145 Lighting system Initial Testing 5 13-Jul-24 17-Jul-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 01-Jun-24 30-Jul-24 30-Jul-24, CABLE TRAY /CABLE ROUTING SYSTEM
LS-3-ECT.105 Cable Tray Installation 10 01-Jun-24 12-Jun-24 Cable Tray Installation

LS-3-ECT.115 Cable Tray Inspection 10 12-Jun-24 29-Jun-24 Cable Tray Inspection

LS-3-ECT.125 LV Cable pulling 10 29-Jun-24 10-Jul-24 LV Cable pulling

LS-3-ECT.135 LV Cable Termination 10 10-Jul-24 22-Jul-24 LV Cable Termination

LS-3-ECT.145 LV Cable Initial Testing 8 22-Jul-24 30-Jul-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 01-Jun-24 20-Jul-24 20-Jul-24, SMALL POWER SYSTEM


LS-3-ESP.105 Small Power Conduit and boxes Installation 12 01-Jun-24 19-Jun-24 Small Power Conduit and boxes Installation

LS-3-ESP.115 Small Power Cable Pulling 10 19-Jun-24 01-Jul-24 Small Power Cable Pulling

LS-3-ESP.125 Small Power Installations 6 01-Jul-24 08-Jul-24 Small Power Installations

LS-3-ESP.135 Small Power Termination 6 08-Jul-24 15-Jul-24 Small Power Termination

LS-3-ESP.145 Small Power Initial Testing 5 15-Jul-24 20-Jul-24 Small Power Initial Testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
189 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER DISTRIBUTION 39 19-Jun-24 04-Aug-24 04-Aug-24, POWER DISTRIBUTION
GENERATOR 39 19-Jun-24 04-Aug-24 04-Aug-24, GENERATOR
LS-3-EPD.105 Generator Cable Tray Installation 7 19-Jun-24 27-Jun-24 Generator Cable Tray Installation

LS-3-EPD.115 Generator Cable Pulling 7 27-Jun-24 06-Jul-24 Generator Cable Pulling

LS-3-EPD.125 Generator Cell Pannel Installation 7 06-Jul-24 14-Jul-24 Generator Cell Pannel Installation

LS-3-EPD.135 Generator Installation 7 14-Jul-24 21-Jul-24 Generator Installation

LS-3-EPD.145 Generator Pannel / Cable Termination 7 22-Jul-24 29-Jul-24 Generator Pannel / Cable Termination

LS-3-EPD.155 Generator Pannel / Cable initial Testing 5 29-Jul-24 04-Aug-24 Generator Pannel / Cable initial Testing

UPS 28 19-Jun-24 22-Jul-24 22-Jul-24, UPS


LS-3-EPD.165 UPS Cable Tray Installation 5 19-Jun-24 25-Jun-24 UPS Cable Tray Installation

LS-3-EPD.175 UPS Cable Pulling 5 25-Jun-24 01-Jul-24 UPS Cable Pulling

LS-3-EPD.185 UPS Pannel Installation 5 01-Jul-24 07-Jul-24 UPS Pannel Installation

LS-3-EPD.195 UPS Installation 5 07-Jul-24 11-Jul-24 UPS Installation

LS-3-EPD.205 UPS Pannel / Cable Termination 5 13-Jul-24 17-Jul-24 UPS Pannel / Cable Termination

LS-3-EPD.215 UPS Pannel / Cable initial Testing 4 17-Jul-24 22-Jul-24 UPS Pannel / Cable initial Testing

MDB 33 19-Jun-24 27-Jul-24 27-Jul-24, MDB


LS-3-EPD.225 MDB Cable Tray Installation 7 19-Jun-24 27-Jun-24 MDB Cable Tray Installation

LS-3-EPD.235 MDB Cable Pulling 7 27-Jun-24 06-Jul-24 MDB Cable Pulling

LS-3-EPD.245 MDB Pannel Installation 7 06-Jul-24 14-Jul-24 MDB Pannel Installation

LS-3-EPD.255 MDB Pannel / Cable Termination 7 14-Jul-24 21-Jul-24 MDB Pannel / Cable Termination

LS-3-EPD.265 MDB Pannel / Cable initial Testing 5 22-Jul-24 27-Jul-24 MDB Pannel / Cable initial Testing

MCC 33 27-Jun-24 04-Aug-24 04-Aug-24, MCC


LS-3-EPD.325 MCC Cable Tray Installation 7 27-Jun-24 06-Jul-24 MCC Cable Tray Installation

LS-3-EPD.335 MCC Cable Pulling 7 06-Jul-24 14-Jul-24 MCC Cable Pulling

LS-3-EPD.345 MCC Pannel Installation 7 14-Jul-24 21-Jul-24 MCC Pannel Installation

LS-3-EPD.355 MCC Pannel / Cable Termination 7 22-Jul-24 29-Jul-24 MCC Pannel / Cable Termination

LS-3-EPD.365 MCC Pannel / Cable initial Testing 5 29-Jul-24 04-Aug-24 MCC Pannel / Cable initial Testing

SMSB 24 27-Jun-24 24-Jul-24 24-Jul-24, SMSB


LS-3-EPD.275 SMSB Cable Tray Installation 5 27-Jun-24 03-Jul-24 SMSB Cable Tray Installation

LS-3-EPD.285 SMSB Cable Pulling 5 03-Jul-24 09-Jul-24 SMSB Cable Pulling

LS-3-EPD.295 SMSB Pannel Installation 5 09-Jul-24 14-Jul-24 SMSB Pannel Installation

LS-3-EPD.305 SMSB Pannel / Cable Termination 5 15-Jul-24 20-Jul-24 SMSB Pannel / Cable Termination

LS-3-EPD.315 SMSB Pannel / Cable initial Testing 4 20-Jul-24 24-Jul-24 SMSB Pannel / Cable initial Testing

DB 24 03-Jul-24 30-Jul-24 30-Jul-24, DB


LS-3-EPD.375 DB Cable Tray Installation 5 03-Jul-24 09-Jul-24 DB Cable Tray Installation

LS-3-EPD.385 DB Cable Pulling 5 09-Jul-24 14-Jul-24 DB Cable Pulling

LS-3-EPD.395 DB Pannel Installation 5 15-Jul-24 20-Jul-24 DB Pannel Installation

LS-3-EPD.405 DB Pannel / Cable Termination 5 20-Jul-24 25-Jul-24 DB Pannel / Cable Termination

LS-3-EPD.415 DB Pannel / Cable initial Testing 4 25-Jul-24 30-Jul-24 DB Pannel / Cable initial Testing

ISOLATOR 24 03-Jul-24 30-Jul-24 30-Jul-24, ISOLATOR


LS-3-EPD.425 Isolators Cable Tray Installation 5 03-Jul-24 09-Jul-24 Isolators Cable Tray Installation

LS-3-EPD.435 Isolators Cable Pulling 5 09-Jul-24 14-Jul-24 Isolators Cable Pulling

LS-3-EPD.445 Isolators Pannel Installation 5 15-Jul-24 20-Jul-24 Isolators Pannel Installation

LS-3-EPD.455 Isolators Pannel / Cable Termination 5 20-Jul-24 25-Jul-24 Isolators Pannel / Cable Termination

LS-3-EPD.465 Isolators Pannel / Cable initial Testing 4 25-Jul-24 30-Jul-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 03-Jul-24 30-Jul-24 30-Jul-24, LCP/ ELCP

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
190 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-3-EPD.475 LCP/ELCP Cable Tray Installation 5 03-Jul-24 09-Jul-24 LCP/ELCP Cable Tray Installation

LS-3-EPD.485 LCP/ELCP Cable Pulling 5 09-Jul-24 14-Jul-24 LCP/ELCP Cable Pulling

LS-3-EPD.495 LCP/ELCP Pannel Installation 5 15-Jul-24 20-Jul-24 LCP/ELCP Pannel Installation

LS-3-EPD.505 LCP/ELCP Pannel / Cable Termination 5 20-Jul-24 25-Jul-24 LCP/ELCP Pannel / Cable Termination

LS-3-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 25-Jul-24 30-Jul-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 09-Jul-24 05-Sep-24 05-Sep-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 09-Jul-24 26-Aug-24 26-Aug-24, FIRE ALARM SYSTEM
LS-3-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 09-Jul-24 18-Jul-24 Fire Alarm Conduit /Cable Tray Installation

LS-3-ELFA.115 Fire Alarm Cable Pulling 9 20-Jul-24 29-Jul-24 Fire Alarm Cable Pulling

LS-3-ELFA.125 Fire Alarm Devices Installation 9 29-Jul-24 08-Aug-24 Fire Alarm Devices Installation

LS-3-ELFA.135 Fire Alarm Devices and Cable Termination 9 08-Aug-24 19-Aug-24 Fire Alarm Devices and Cable Termination

LS-3-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 19-Aug-24 26-Aug-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 09-Jul-24 26-Aug-24 26-Aug-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
LS-3-ELVS.105 ICT System Conduit /Cable Tray Installation 9 09-Jul-24 18-Jul-24 ICT System Conduit /Cable Tray Installation

LS-3-ELVS.115 ICT System Cable Pulling 9 20-Jul-24 29-Jul-24 ICT System Cable Pulling

LS-3-ELVS.125 ICT System Devices Installation 9 29-Jul-24 08-Aug-24 ICT System Devices Installation

LS-3-ELVS.135 ICT System Devices and Cable Termination 9 08-Aug-24 19-Aug-24 ICT System Devices and Cable Termination

LS-3-ELVS.145 ICT System Devices and Cable initial Testing 6 19-Aug-24 26-Aug-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 09-Jul-24 26-Aug-24 26-Aug-24, ACCESS CONTROL SYSTEM


LS-3-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 09-Jul-24 18-Jul-24 Access Control System Conduit /Cable Tray Installation

LS-3-ELAC.115 Access Control System Cable Pulling 9 20-Jul-24 29-Jul-24 Access Control System Cable Pulling

LS-3-ELAC.125 Access Control System Devices Installation 9 29-Jul-24 08-Aug-24 Access Control System Devices Installation

LS-3-ELAC.135 Access Control System Devices and Cable Termination 9 08-Aug-24 19-Aug-24 Access Control System Devices and Cable Termination

LS-3-ELAC.145 Access Control System Devices and Cable initial Testing 6 19-Aug-24 26-Aug-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 20-Jul-24 05-Sep-24 05-Sep-24, PUBLIC ADDRESS SYSTEM


LS-3-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 20-Jul-24 29-Jul-24 Public Address System Conduit /Cable Tray Installation

LS-3-ELPA.115 Public Address System Cable Pulling 9 29-Jul-24 08-Aug-24 Public Address System Cable Pulling

LS-3-ELPA.125 Public Address System Devices Installation 9 08-Aug-24 19-Aug-24 Public Address System Devices Installation

LS-3-ELPA.135 Public Address System Devices and Cable Termination 9 19-Aug-24 29-Aug-24 Public Address System Devices and Cable Termination

LS-3-ELPA.145 Public Address System Devices and Cable initial Testing 6 29-Aug-24 05-Sep-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 20-Jul-24 05-Sep-24 05-Sep-24, SCADA SYSTEM


LS-3-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 20-Jul-24 29-Jul-24 SCADA System Conduit /Cable Tray Installation

LS-3-ELSC.115 SCADA System Cable Pulling 9 29-Jul-24 08-Aug-24 SCADA System Cable Pulling

LS-3-ELSC.125 SCADA System Devices Installation 9 08-Aug-24 19-Aug-24 SCADA System Devices Installation

LS-3-ELSC.135 SCADA System Devices and Cable Termination 9 19-Aug-24 29-Aug-24 SCADA System Devices and Cable Termination

LS-3-ELSC.145 SCADA System Devices and Cable initial Testing 6 29-Aug-24 05-Sep-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 20-Jul-24 05-Sep-24 05-Sep-24, RADIO RE- BROADCOASTING/ TETRA
LS-3-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 20-Jul-24 29-Jul-24 Radio/TETRA System Conduit /Cable Tray Installation

LS-3-ELRD.115 Radio/TETRA System Cable Pulling 9 29-Jul-24 08-Aug-24 Radio/TETRA System Cable Pulling

LS-3-ELRD.125 Radio/TETRA System Devices Installation 9 08-Aug-24 19-Aug-24 Radio/TETRA System Devices Installation

LS-3-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 19-Aug-24 29-Aug-24 Radio/TETRA System Devices and Cable Termination

LS-3-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 29-Aug-24 05-Sep-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK 15 29-Jul-24 15-Aug-24 15-Aug-24, MECHANICAL WORK


FIRE FIGHTING 13 29-Jul-24 13-Aug-24 13-Aug-24, FIRE FIGHTING
LS-3-MFF.105 Fire Fighting system Pipe and accessories installation 11 29-Jul-24 11-Aug-24 Fire Fighting system Pipe and accessories installation

LS-3-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 07-Aug-24 11-Aug-24 Fire Fighting system fire hose cabinet/extingusher installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
191 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-3-MFF.135 Fire Fighting system initial testing 2 11-Aug-24 13-Aug-24 Fire Fighting system initial testing

HVAC 15 29-Jul-24 15-Aug-24 15-Aug-24, HVAC


LS-3-MHV.105 Duct and accessories installation 12 29-Jul-24 12-Aug-24 Duct and accessories installation

LS-3-MHV.115 Fan installation 4 07-Aug-24 12-Aug-24 Fan installation

LS-3-MHV.135 HVAC inital testing 3 12-Aug-24 15-Aug-24 HVAC inital testing

PLUMBING 4 29-Jul-24 03-Aug-24 03-Aug-24, PLUMBING


LS-3-MPL.105 Plumbing drainage system installation 3 29-Jul-24 01-Aug-24 Plumbing drainage system installation

LS-3-MPL.115 Plumbing drainage system initial testing 1 01-Aug-24 03-Aug-24 Plumbing drainage system initial testing

lIFTING STATION 01 (IN ZONE 03) 409 24-May-23 26-Sep-24 26-Sep-24, lIFTING STATION 01 (IN ZONE 03)
ENGINEERING 109 24-May-23 03-Oct-23 03-Oct-23, ENGINEERING
SHOP DRAWING SUBMITTAL ANDAPPROVAL 109 24-May-23 03-Oct-23 03-Oct-23, SHOP DRAWING SUBMITTAL AND APPROVAL
EARTH WORKS 42 14-Aug-23 03-Oct-23 03-Oct-23, EARTH WORKS
JAH-ENG-SH-LS06.985
Shoring Design Preparation & Submission 14 14-Aug-23 30-Aug-23 Shoring Design Preparation & Submission

JAH-ENG-SH-LS06.990
Shoring Design Review & Approval 14 30-Aug-23 16-Sep-23 Shoring Design Review & Approval

JAH-ENG-SI-LS06.1000
Soil Improvement Design Review & Approval 14 16-Sep-23 03-Oct-23 Soil Improvement Design Review & Approval

JAH-ENG-SI-LS06.995Soil Improvement Design Preparation & Submission 14 30-Aug-23 16-Sep-23 Soil Improvement Design Preparation & Submission

STRUCTURE 56 24-May-23 31-Jul-23 31-Jul-23, STRUCTURE


PMP.4-ENG-CV-ST.130Foundation Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Foundation Shop Drawings Preparation & Submission

PMP.4-ENG-CV-ST.140Foundation Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Foundation Shop Drawings Review & Approval

PMP.4-ENG-CV-ST.150Walls Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Walls Shop Drawings Preparation & Submission

PMP.4-ENG-CV-ST.160Walls Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 Walls Shop Drawings Review & Approval

PMP.4-ENG-CV-ST.170Slab Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Slab Shop Drawings Preparation & Submission

PMP.4-ENG-CV-ST.180Slab Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Slab Shop Drawings Review & Approval

MECHANICAL 56 24-May-23 31-Jul-23 31-Jul-23, MECHANICAL


FIRE FIGHTING SYSTEM 28 24-May-23 25-Jun-23 25-Jun-23, FIRE FIGHTING SYSTEM
PMP.4-ENG-MC-ST.110
Fire Fighting Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Fighting Shop Drawings Preparation & Submission

PMP.4-ENG-MC-ST.120
Fire Fighting Shop Drawings Review & Approval 14 08-Jun-23 25-Jun-23 Fire Fighting Shop Drawings Review & Approval

VENTILATION SYSTEM/AIR CONDITIONING WORKS 28 08-Jun-23 15-Jul-23 15-Jul-23, VENTILATION SYSTEM/AIR CONDITIONING WORKS
PMP.4-ENG-MC-HC.110
HVAC Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 HVAC Shop Drawings Preparation & Submission

PMP.4-ENG-MC-HC.120
HVAC Shop Drawings Review & Approval 14 25-Jun-23 15-Jul-23 HVAC Shop Drawings Review & Approval

PLUMBING SYSTEM 28 25-Jun-23 31-Jul-23 31-Jul-23, PLUMBING SYSTEM


PMP.4-ENG-MC-PI.110
Plumbing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Plumbing System Shop Drawings Preparation & Submission

PMP.4-ENG-MC-PI.120
Plumbing System Shop Drawings Review & Approval 14 15-Jul-23 31-Jul-23 Plumbing System Shop Drawings Review & Approval

ELECTRICAL 95 24-May-23 16-Sep-23 16-Sep-23, ELECTRICAL


CABLE TRAYS 26 24-May-23 22-Jun-23 22-Jun-23, CABLE TRAYS
PMP.4-ENG-EL-CT.110
Cable Tray Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Cable Tray Shop Drawings Preparation & Submission

PMP.4-ENG-EL-CT.120
Cable Tray Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Cable Tray Shop Drawings Review & Approval

POWER CABLES 26 08-Jun-23 12-Jul-23 12-Jul-23, POWER CABLES


PMP.4-ENG-EL-PC.110
Power Cables Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Power Cables Shop Drawings Preparation & Submission

PMP.4-ENG-EL-PC.120
Power Cables Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Power Cables Shop Drawings Review & Approval

LIGHTING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, LIGHTING SYSTEM


PMP.4-ENG-EL-LS.110
Lighting System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Lighting System Shop Drawings Preparation & Submission

PMP.4-ENG-EL-LS.120
Lighting System Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Lighting System Shop Drawings Review & Approval

ELECTRICAL INSTALLATIONS 26 15-Jul-23 14-Aug-23 14-Aug-23, ELECTRICAL INSTALLATIONS


PMP.4-ENG-EL-EI.110Electrical Installations Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Electrical Installations Shop Drawings Preparation & Submission

PMP.4-ENG-EL-EI.120Electrical Installations Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Electrical Installations Shop Drawings Review & Approval

LIGHTNING PROTECTION SYSTEM 26 08-Jun-23 12-Jul-23 12-Jul-23, LIGHTNING PROTECTION SYSTEM


PMP.4-ENG-EL-LP.110Lightning Protection Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Lightning Protection Drawings Preparation & Submission

PMP.4-ENG-EL-LP.120Lightning Protection Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Lightning Protection Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
192 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
EARTHING SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, EARTHING SYSTEM
PMP.4-ENG-EL-ES.110
Earthing System Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Earthing System Shop Drawings Preparation & Submission

PMP.4-ENG-EL-ES.120
Earthing System Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Earthing System Drawings Review & Approval

LOW CURRENT 95 24-May-23 16-Sep-23 16-Sep-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 26 24-May-23 22-Jun-23 22-Jun-23, FIRE DETECTION AND ALARM SYSTEM
PMP.4-ENG-ELL-FA.20
Fire Alarm Shop Drawings Preparation & Submission 14 24-May-23 08-Jun-23 Fire Alarm Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-FA.30
Fire Alarm Shop Drawings Review & Approval 12 08-Jun-23 22-Jun-23 Fire Alarm Shop Drawings Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 26 08-Jun-23 12-Jul-23 12-Jul-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
PMP.4-ENG-ELL-PH.20
Telephone Shop Drawings Preparation & Submission 14 08-Jun-23 25-Jun-23 Telephone Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-PH.30
Telephone Shop Drawings Review & Approval 12 25-Jun-23 12-Jul-23 Telephone Shop Drawings Review & Approval

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 26 25-Jun-23 29-Jul-23 29-Jul-23, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
PMP.4-ENG-ELL-PA.20
Public Address system Shop Drawings Preparation & Submission 14 25-Jun-23 15-Jul-23 Public Address system Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-PA.30
Public Address system Shop Drawings Review & Approval 12 15-Jul-23 29-Jul-23 Public Address system Shop Drawings Review & Approval

VIDEO SURVEILLANCE 26 15-Jul-23 14-Aug-23 14-Aug-23, VIDEO SURVEILLANCE


PMP.4-ENG-ELL-VS.20
Video Surveillance system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 Video Surveillance system Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-VS.30
Video Surveillance system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 Video Surveillance system Shop Drawings Review & Approval

ACCESS CONTROL SYSTEM 26 31-Jul-23 30-Aug-23 30-Aug-23, ACCESS CONTROL SYSTEM


PMP.4-ENG-ELL-AC.20
Access Control system Shop Drawings Preparation & Submission 14 31-Jul-23 16-Aug-23 Access Control system Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-AC.30
Access Control system Shop Drawings Review & Approval 12 16-Aug-23 30-Aug-23 Access Control system Shop Drawings Review & Approval

RADIO RE-BROADCASTING SYSTEM 26 16-Aug-23 16-Sep-23 16-Sep-23, RADIO RE-BROADCASTING SYSTEM


PMP.4-ENG-ELL-RB.20
Radio Re Broadcasting system Shop Drawings Preparation & Submission 14 16-Aug-23 02-Sep-23 Radio Re Broadcasting system Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-RB.30
Radio Re Broadcasting system Shop Drawings Review & Approval 12 02-Sep-23 16-Sep-23 Radio Re Broadcasting system Shop Drawings Review & Approval

SCADA SYSTEM 26 15-Jul-23 14-Aug-23 14-Aug-23, SCADA SYSTEM


PMP.4-ENG-ELL-SD.20
SCADA system Shop Drawings Preparation & Submission 14 15-Jul-23 31-Jul-23 SCADA system Shop Drawings Preparation & Submission

PMP.4-ENG-ELL-SD.30
SCADA system Shop Drawings Review & Approval 12 31-Jul-23 14-Aug-23 SCADA system Shop Drawings Review & Approval

PROCUREMENT 221 15-Nov-23 07-Aug-24 07-Aug-24, PROCUREMENT


CIVIL/STRUCTURAL 16 15-Nov-23 04-Dec-23 04-Dec-23, CIVIL/STRUCTURAL
PMP.4RO-CVL.110 Issue Purchase Order 6 15-Nov-23 22-Nov-23 Issue Purchase Order

PMP.4RO-CVL.120 Material Delivery 10 22-Nov-23 04-Dec-23 Material Delivery

MECHANICAL 105 30-Mar-24 07-Aug-24 07-Aug-24, MECHANICAL


FIRE FIGHTING SYSTEM 105 30-Mar-24 07-Aug-24 07-Aug-24, FIRE FIGHTING SYSTEM
PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS 105 30-Mar-24 07-Aug-24 07-Aug-24, PIPES,FITTINGS,VALVES,FIRE HOSE CABINET,SPRINKLERS
PMP.4RO-MC-FT.110 Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

PMP.4RO-MC-FT.120 Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

VENTILATION SYSTEM 105 30-Mar-24 07-Aug-24 07-Aug-24, VENTILATION SYSTEM


DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS 105 30-Mar-24 07-Aug-24 07-Aug-24, DUCTS,FITTINGS,GRILLS,DIFUSERS,DAMPERS,FANS
PMP.4RO-MC-DCT.110
Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

PMP.4RO-MC-DCT.120
Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

AIR CONDITIONING WORKS 105 30-Mar-24 07-Aug-24 07-Aug-24, AIR CONDITIONING WORKS
SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS 105 30-Mar-24 07-Aug-24 07-Aug-24, SPLIT UNITS,COPPER AC PIPE,UPVC PIPE & FITTINGS
PMP.4RO-MC-SPU.110
Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

PMP.4RO-MC-SPU.120
Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

PLUMBING SYSTEM 105 30-Mar-24 07-Aug-24 07-Aug-24, PLUMBING SYSTEM


PUMPS,PIPES,FITTINGS,VALVES 105 30-Mar-24 07-Aug-24 07-Aug-24, PUMPS,PIPES,FITTINGS,VALVES
PMP.4RO-MC-PMI.110
Issue Purchase Order 15 30-Mar-24 20-Apr-24 Issue Purchase Order

PMP.4RO-MC-PMI.120
Material Delivery 90 20-Apr-24 07-Aug-24 Material Delivery

ELECTRICAL 143 05-Feb-24 28-Jul-24 28-Jul-24, ELECTRICAL


CABLE TRAY 105 05-Feb-24 10-Jun-24 10-Jun-24, CABLE TRAY
CABLE TRAY AND ACCESSORIES,PVC DUCT 105 05-Feb-24 10-Jun-24 10-Jun-24, CABLE TRAY AND ACCESSORIES,PVC DUCT
PMP.4RO-EL-CTRY.130
Issue Purchase Order 15 05-Feb-24 22-Feb-24 Issue Purchase Order

PMP.4RO-EL-CTRY.140
Material Delivery 90 22-Feb-24 10-Jun-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
193 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER CABLES 105 28-Feb-24 08-Jul-24 08-Jul-24, POWER CABLES
HIGH VOLTAGE,LOW VOLTAGE POWER CABLES 105 28-Feb-24 08-Jul-24 08-Jul-24, HIGH VOLTAGE,LOW VOLTAGE POWER CABLES
PMP.4RO-EL-PWCL.140
Issue Purchase Order 15 28-Feb-24 17-Mar-24 Issue Purchase Order

PMP.4RO-EL-PWCL.150
Material Delivery 90 17-Mar-24 08-Jul-24 Material Delivery

LIGHTING SYSTEM 105 14-Feb-24 24-Jun-24 24-Jun-24, LIGHTING SYSTEM


CONDUIT,LIGHT 105 14-Feb-24 24-Jun-24 24-Jun-24, CONDUIT,LIGHT
PMP.4RO-EL-LTS.110Issue Purchase Order 15 14-Feb-24 03-Mar-24 Issue Purchase Order

PMP.4RO-EL-LTS.120Material Delivery 90 03-Mar-24 24-Jun-24 Material Delivery

ELECTRICAL INSTALLATIONS 105 24-Feb-24 03-Jul-24 03-Jul-24, ELECTRICAL INSTALLATIONS


M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS 105 24-Feb-24 03-Jul-24 03-Jul-24, M V SWITCH GEAR,RMUS,SMDB,MDB,MCC,ISOLATERS ,TRANFORMERS
PMP.4RO-EL-INSL.190
Issue Purchase Order 15 24-Feb-24 12-Mar-24 Issue Purchase Order

PMP.4RO-EL-INSL.200
Material Delivery 90 12-Mar-24 03-Jul-24 Material Delivery

LIGHTNING PROTECTION SYSTEM 105 05-Feb-24 10-Jun-24 10-Jun-24, LIGHTNING PROTECTION SYSTEM
LIGHTNING PROTECTION SYSTEM 105 05-Feb-24 10-Jun-24 10-Jun-24, LIGHTNING PROTECTION SYSTEM
PMP.4RO-EL-LPS.110Issue Purchase Order 15 05-Feb-24 22-Feb-24 Issue Purchase Order

PMP.4RO-EL-LPS.120Material Delivery 90 22-Feb-24 10-Jun-24 Material Delivery

ACCESSORIES 0
EARTHING SYSTEM 105 24-Feb-24 03-Jul-24 03-Jul-24, EARTHING SYSTEM
EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES 105 24-Feb-24 03-Jul-24 03-Jul-24, EARTHING RODS,COPPER CONDUCTOR,ACCESSORIES
PMP.4RO-EL-ERS.120Issue Purchase Order 15 24-Feb-24 12-Mar-24 Issue Purchase Order

PMP.4RO-EL-ERS.130Material Delivery 90 12-Mar-24 03-Jul-24 Material Delivery

LOW CURRENT 114 10-Mar-24 28-Jul-24 28-Jul-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 105 10-Mar-24 17-Jul-24 17-Jul-24, FIRE DETECTION AND ALARM SYSTEM
FIRE ALARM CABLE,CONTROLMODULE,SPEAKER, DETECTOR,C PANEL 105 10-Mar-24 17-Jul-24 17-Jul-24, FIRE ALARM CABLE,CONTROL MODULE,SPEAKER, DETECTOR,C PANEL
PMP.4R-ELL-FA130 Issue Purchase Order 15 10-Mar-24 26-Mar-24 Issue Purchase Order

PMP.4R-ELL-FA140 Material Delivery 90 27-Mar-24 17-Jul-24 Material Delivery

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 105 10-Mar-24 17-Jul-24 17-Jul-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIE S 105 10-Mar-24 17-Jul-24 17-Jul-24, UTP CABLE,CONTROL MODULE,TELEPHONES,WIFI,ACCESSORIES
PMP.4R-ELL-PH.130Issue Purchase Order 15 10-Mar-24 26-Mar-24 Issue Purchase Order

PMP.4R-ELL-PH.140Material Delivery 90 27-Mar-24 17-Jul-24 Material Delivery

VOICE EVACAUTION AND PUBLICADDRESS SYSTEM 105 19-Mar-24 28-Jul-24 28-Jul-24, VOICE EVACAUTION AND PUBLIC ADDRESS SYSTEM
CABLE,CIB RACKS,APMLIFIER,ACCESSORIES 105 19-Mar-24 28-Jul-24 28-Jul-24, CABLE,CIB RACKS,APMLIFIER,ACCESSORIES
PMP.4R-ELL-PA.120Issue Purchase Order 15 19-Mar-24 06-Apr-24 Issue Purchase Order

PMP.4R-ELL-PA.130Material Delivery 90 06-Apr-24 28-Jul-24 Material Delivery

VIDEO SURVEILLANCE 105 10-Mar-24 17-Jul-24 17-Jul-24, VIDEO SURVEILLANCE


FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES 105 10-Mar-24 17-Jul-24 17-Jul-24, FIBRE OPTICAL CABLES,CAMERAS,RTU PANELS,ACCESSORIES
PMP.4R-ELL-VS.120Issue Purchase Order 15 10-Mar-24 26-Mar-24 Issue Purchase Order

PMP.4R-ELL-VS.130Material Delivery 90 27-Mar-24 17-Jul-24 Material Delivery

ACCESS CONTROL SYSTEM 105 10-Mar-24 17-Jul-24 17-Jul-24, ACCESS CONTROL SYSTEM
CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER,ACCESSORIES 105 10-Mar-24 17-Jul-24 17-Jul-24, CABLE,DOOR CONTACT,CONTROL PANEL,CARD READER, ACCESSORIES
PMP.4R-ELL-AC.130Issue Purchase Order 15 10-Mar-24 26-Mar-24 Issue Purchase Order

PMP.4R-ELL-AC.140Material Delivery 90 27-Mar-24 17-Jul-24 Material Delivery

RADIO RE-BROADCASTING SYSTEM 105 19-Mar-24 28-Jul-24 28-Jul-24, RADIO RE-BROADCASTING SYSTEM
CABLE,BASE STATION,DAS ANTENA,ACCESSORIES 105 19-Mar-24 28-Jul-24 28-Jul-24, CABLE,BASE STATION,DAS ANTENA,ACCESSORIES
PMP.4R-ELL-RB.120Issue Purchase Order 15 19-Mar-24 06-Apr-24 Issue Purchase Order

PMP.4R-ELL-RB.130Material Delivery 90 06-Apr-24 28-Jul-24 Material Delivery

SCADA SYSTEM 105 19-Mar-24 28-Jul-24 28-Jul-24, SCADA SYSTEM


CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES 105 19-Mar-24 28-Jul-24 28-Jul-24, CABLE,SERVERS,RIO PANELS,CONTROL UPS,ACCESSORIES
PMP.4R-ELL-SDA.130
Issue Purchase Order 15 19-Mar-24 06-Apr-24 Issue Purchase Order

PMP.4R-ELL-SDA.140
Material Delivery 90 06-Apr-24 28-Jul-24 Material Delivery

CONSTRUCTION 314 16-Sep-23 26-Sep-24 26-Sep-24, CONSTRUCTION


EXCAVATION WORKS 47 16-Sep-23 11-Nov-23 11-Nov-23, EXCAVATION WORKS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
194 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
T3-CON-Z11-EX-LS.160Excavation 47 16-Sep-23 11-Nov-23 Excavation

SOIL IMPROVEMENT WORKS 20 11-Nov-23 04-Dec-23 04-Dec-23, SOIL IMPROVEMENT WORKS


T3-CON-Z11-SI-LS.210Soil Improvement 20 11-Nov-23 04-Dec-23 Soil Improvement

SHORING WORKS 0 16-Sep-23 16-Sep-23 16-Sep-23, SHORING WORKS


T3-CON-Z11-SH-LS.245Piles 0 16-Sep-23 16-Sep-23 Piles

T3-CON-Z11-SH-LS.250Capping Beam 0 16-Sep-23 16-Sep-23 Capping Beam

T3-CON-Z11-SH-LS.255Anchore 0 16-Sep-23 16-Sep-23 Anchore

STRUCTURAL WORKS 247 04-Dec-23 26-Sep-24 26-Sep-24, STRUCTURAL WORKS


FOUNDATION 21 04-Dec-23 28-Dec-23 28-Dec-23, FOUNDATION
Part-1 21 04-Dec-23 28-Dec-23 28-Dec-23, Part-1
PMP.4-FDN-P1.150 Foundation Blinding concrete casting 1 04-Dec-23 05-Dec-23 Foundation Blinding concrete casting

PMP.4-FDN-P1.160 Foundation water proofing on blinding concrete 2 05-Dec-23 07-Dec-23 Foundation water proofing on blinding concrete

PMP.4-FDN-P1.170 Foundation Protection screed on water poofing 1 07-Dec-23 09-Dec-23 Foundation Protection screed on water poofing

PMP.4-FDN-P1.180 Foundation Curing for screed 1 09-Dec-23 10-Dec-23 Foundation Curing for screed

PMP.4-FDN-P1.190 Foundation Rebar installation 5 10-Dec-23 16-Dec-23 Foundation Rebar installation

PMP.4-FDN-P1.200 Foundation Formwork installation 4 16-Dec-23 20-Dec-23 Foundation Formwork installation

PMP.4-FDN-P1.220 Foundation concrete casting 1 20-Dec-23 21-Dec-23 Foundation concrete casting

PMP.4-FDN-P1.230 Foundation concrete curing 1 21-Dec-23 23-Dec-23 Foundation concrete curing

PMP.4-FDN-P1.240 Foundation Formwork Removal 1 23-Dec-23 24-Dec-23 Foundation Formwork Removal

Part-1 17 09-Dec-23 28-Dec-23 28-Dec-23, Part-1


PMP.5-FDN-P1.150 Foundation Blinding concrete casting 1 09-Dec-23 10-Dec-23 Foundation Blinding concrete casting

PMP.5-FDN-P1.160 Foundation water proofing on blinding concrete 2 10-Dec-23 12-Dec-23 Foundation water proofing on blinding concrete

PMP.5-FDN-P1.170 Foundation Protection screed on water poofing 1 12-Dec-23 13-Dec-23 Foundation Protection screed on water poofing

PMP.5-FDN-P1.180 Foundation Curing for screed 1 13-Dec-23 14-Dec-23 Foundation Curing for screed

PMP.5-FDN-P1.190 Foundation Rebar installation 5 14-Dec-23 20-Dec-23 Foundation Rebar installation

PMP.5-FDN-P1.200 Foundation Formwork installation 4 20-Dec-23 25-Dec-23 Foundation Formwork installation

PMP.5-FDN-P1.220 Foundation concrete casting 1 25-Dec-23 26-Dec-23 Foundation concrete casting

PMP.5-FDN-P1.230 Foundation concrete curing 1 26-Dec-23 27-Dec-23 Foundation concrete curing

PMP.5-FDN-P1.240 Foundation Formwork Removal 1 27-Dec-23 28-Dec-23 Foundation Formwork Removal

WALLS UP TO SLAB LEVEL 21 21-Dec-23 15-Jan-24 15-Jan-24, WALLS UP TO SLAB LEVEL


WALL CONCRETE CASTING STAGE-1 21 21-Dec-23 15-Jan-24 15-Jan-24, WALL CONCRETE CASTING STAGE-1
Part-1 21 21-Dec-23 15-Jan-24 15-Jan-24, Part-1
PMP.4-WL-SG-1-P1.135
Room Walls Rebar Installation 6 25-Dec-23 01-Jan-24 Room Walls Rebar Installation

PMP.4-WL-SG-1-P1.145
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 01-Jan-24 02-Jan-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-1-P1.155
Room Walls Formwork Installation 7 02-Jan-24 10-Jan-24 Room Walls Formwork Installation

PMP.4-WL-SG-1-P1.165
Room Walls Concrete Casting 1 10-Jan-24 11-Jan-24 Room Walls Concrete Casting

PMP.4-WL-SG-1-P1.175
Room Walls Curing work 1 11-Jan-24 13-Jan-24 Room Walls Curing work

PMP.4-WL-SG-1-P1.185
Room Walls Formwork Removel 2 13-Jan-24 15-Jan-24 Room Walls Formwork Removel

PMP.4-WL-SG-1-P1.195
Room Walls Scafolding for rebar 3 21-Dec-23 25-Dec-23 Room Walls Scafolding for rebar

MIDDLE SLAB 37 15-Jan-24 27-Feb-24 27-Feb-24, MIDDLE SLAB


Part-1 37 15-Jan-24 27-Feb-24 27-Feb-24, Part-1
PMP.4-MS-P1.125 Room Top Slab Formwork Installation 12 15-Jan-24 29-Jan-24 Room Top Slab Formwork Installation

PMP.4-MS-P1.135 Room Top Slab Rebar Installation 8 29-Jan-24 07-Feb-24 Room Top Slab Rebar Installation

PMP.4-MS-P1.145 Room Top Slab Concrete Casting 1 07-Feb-24 08-Feb-24 Room Top Slab Concrete Casting

PMP.4-MS-P1.155 Room Top slab Curing work 12 08-Feb-24 22-Feb-24 Room Top slab Curing work

PMP.4-MS-P1.165 Room Top Slab Formwork Removel 4 22-Feb-24 27-Feb-24 Room Top Slab Formwork Removel

WALL CONCRETE CASTING STAGE-2 20 27-Feb-24 21-Mar-24 21-Mar-24, WALL CONCRETE CASTING STAGE-2

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
195 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Part-1 20 27-Feb-24 21-Mar-24 21-Mar-24, Part-1
PMP.4-WL-SG-2-P1.135
Room Walls Rebar Installation 5 02-Mar-24 07-Mar-24 Room Walls Rebar Installation

PMP.4-WL-SG-2-P1.145
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 07-Mar-24 09-Mar-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-2-P1.155
Room Walls Formwork Installation 7 09-Mar-24 17-Mar-24 Room Walls Formwork Installation

PMP.4-WL-SG-2-P1.165
Room Walls Concrete Casting 1 17-Mar-24 18-Mar-24 Room Walls Concrete Casting

PMP.4-WL-SG-2-P1.175
Room Walls Curing work 1 18-Mar-24 19-Mar-24 Room Walls Curing work

PMP.4-WL-SG-2-P1.185
Room Walls Formwork Removel 2 19-Mar-24 21-Mar-24 Room Walls Formwork Removel

PMP.4-WL-SG-2-P1.195
Room Walls Scafolding for rebar 3 27-Feb-24 02-Mar-24 Room Walls Scafolding for rebar

TOP SLAB BELOW GROUND LEVEL 37 21-Mar-24 07-May-24 07-May-24, TOP SLAB BELOW GROUND LEVEL
Part-1 37 21-Mar-24 07-May-24 07-May-24, Part-1
PMP.4-TS-P1.125 Room Top Slab Formwork Installation 12 21-Mar-24 04-Apr-24 Room Top Slab Formwork Installation

PMP.4-TS-P1.135 Room Top Slab Rebar Installation 8 04-Apr-24 17-Apr-24 Room Top Slab Rebar Installation

PMP.4-TS-P1.145 Room Top Slab Concrete Casting 1 17-Apr-24 18-Apr-24 Room Top Slab Concrete Casting

PMP.4-TS-P1.155 Room Top slab Curing work 12 18-Apr-24 02-May-24 Room Top slab Curing work

PMP.4-TS-P1.165 Room Top Slab Formwork Removel 4 02-May-24 07-May-24 Room Top Slab Formwork Removel

WALLS ABOVE SLAB LEVEL 17 02-May-24 22-May-24 22-May-24, WALLS ABOVE SLAB LEVEL
WALL CONCRETE CASTING STAGE-3 17 02-May-24 22-May-24 22-May-24, WALL CONCRETE CASTING STAGE-3
Part-1 17 02-May-24 22-May-24 22-May-24, Part-1
PMP.4-WL-SG-3-P1.135
Room Walls Rebar Installation 4 06-May-24 11-May-24 Room Walls Rebar Installation

PMP.4-WL-SG-3-P1.145
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 11-May-24 12-May-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-3-P1.155
Room Walls Formwork Installation 5 12-May-24 18-May-24 Room Walls Formwork Installation

PMP.4-WL-SG-3-P1.165
Room Walls Concrete Casting 1 18-May-24 19-May-24 Room Walls Concrete Casting

PMP.4-WL-SG-3-P1.175
Room Walls Curing work 1 19-May-24 20-May-24 Room Walls Curing work

PMP.4-WL-SG-3-P1.185
Room Walls Formwork Removel 2 20-May-24 22-May-24 Room Walls Formwork Removel

PMP.4-WL-SG-3-P1.195
Room Walls Scafolding for rebar 3 02-May-24 06-May-24 Room Walls Scafolding for rebar

WALL CONCRETE CASTING STAGE-4 17 22-May-24 11-Jun-24 11-Jun-24, WALL CONCRETE CASTING STAGE-4
Part-1 17 22-May-24 11-Jun-24 11-Jun-24, Part-1
PMP.4-WL-SG-4-P1.135
Room Walls Rebar Installation 4 26-May-24 30-May-24 Room Walls Rebar Installation

PMP.4-WL-SG-4-P1.145
Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation 1 30-May-24 01-Jun-24 Room Walls PVC Conduit Pipes/Utility Ducts/Sleeves Installation

PMP.4-WL-SG-4-P1.155
Room Walls Formwork Installation 5 01-Jun-24 06-Jun-24 Room Walls Formwork Installation

PMP.4-WL-SG-4-P1.165
Room Walls Concrete Casting 1 06-Jun-24 08-Jun-24 Room Walls Concrete Casting

PMP.4-WL-SG-4-P1.175
Room Walls Curing work 1 08-Jun-24 09-Jun-24 Room Walls Curing work

PMP.4-WL-SG-4-P1.185
Room Walls Formwork Removel 2 09-Jun-24 11-Jun-24 Room Walls Formwork Removel

PMP.4-WL-SG-4-P1.195
Room Walls Scafolding for rebar 3 22-May-24 26-May-24 Room Walls Scafolding for rebar

SLAB ABOVE GROUND LEVEL 33 11-Jun-24 24-Jul-24 24-Jul-24, SLAB ABOVE GROUND LEVEL
Part-1 33 11-Jun-24 24-Jul-24 24-Jul-24, Part-1
PMP.4-SLB-AG-P1.125
Room Top Slab Formwork Installation 8 11-Jun-24 25-Jun-24 Room Top Slab Formwork Installation

PMP.4-SLB-AG-P1.135
Room Top Slab Rebar Installation 8 25-Jun-24 04-Jul-24 Room Top Slab Rebar Installation

PMP.4-SLB-AG-P1.145
Room Top Slab Concrete Casting 1 04-Jul-24 06-Jul-24 Room Top Slab Concrete Casting

PMP.4-SLB-AG-P1.155
Room Top slab Curing work 12 06-Jul-24 20-Jul-24 Room Top slab Curing work

PMP.4-SLB-AG-P1.165
Room Top Slab Formwork Removel 4 20-Jul-24 24-Jul-24 Room Top Slab Formwork Removel

WATER PROOFING 45 24-Jul-24 15-Sep-24 15-Sep-24, WATER PROOFING


WALL WATER PROOFING STAGE-1 10 24-Jul-24 05-Aug-24 05-Aug-24, WALL WATER PROOFING STAGE-1
PMP.4-WP-WL-S1.115Surface preparation work 2 24-Jul-24 27-Jul-24 Surface preparation work

PMP.4-WP-WL-S1.125Applying of waterproofing material &Membrane Protection work 2 27-Jul-24 29-Jul-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S1.135L.S Back Filling 6 29-Jul-24 05-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-2 10 05-Aug-24 17-Aug-24 17-Aug-24, WALL WATER PROOFING STAGE-2

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
196 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
PMP.4-WP-WL-S2.115Surface preparation work 2 05-Aug-24 07-Aug-24 Surface preparation work

PMP.4-WP-WL-S2.125Applying of waterproofing material &Membrane Protection work 2 07-Aug-24 10-Aug-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S2.135L.S Back Filling 6 10-Aug-24 17-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-3 10 17-Aug-24 28-Aug-24 28-Aug-24, WALL WATER PROOFING STAGE-3
PMP.4-WP-WL-S3.115Surface preparation work 2 17-Aug-24 19-Aug-24 Surface preparation work

PMP.4-WP-WL-S3.125Applying of waterproofing material &Membrane Protection work 2 19-Aug-24 21-Aug-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S3.135L.S Back Filling 6 21-Aug-24 28-Aug-24 L.S Back Filling

WALL WATER PROOFING STAGE-4 10 28-Aug-24 09-Sep-24 09-Sep-24, WALL WATER PROOFING STAGE-4
PMP.4-WP-WL-S4.115Surface preparation work 2 28-Aug-24 31-Aug-24 Surface preparation work

PMP.4-WP-WL-S4.125Applying of waterproofing material &Membrane Protection work 2 31-Aug-24 02-Sep-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-WL-S4.135L.S Back Filling 6 02-Sep-24 09-Sep-24 L.S Back Filling

TOP SLAB WATER PROOFING 5 09-Sep-24 15-Sep-24 15-Sep-24, TOP SLAB WATER PROOFING
PMP.4-WP-SLB-S1.115
Surface preparation work 2 09-Sep-24 11-Sep-24 Surface preparation work

PMP.4-WP-SLB-S1.125
Applying of waterproofing material &Membrane Protection work 2 11-Sep-24 14-Sep-24 Applying of waterproofing material &Membrane Protection work

PMP.4-WP-SLB-S1.135
Leak Test 1 14-Sep-24 15-Sep-24 Leak Test

PLAIN CONCRETE ABOVE SLAB 9 15-Sep-24 26-Sep-24 26-Sep-24, PLAIN CONCRETE ABOVE SLAB
Part-1 9 15-Sep-24 26-Sep-24 26-Sep-24, Part-1
PMP.4-PC-P1.120 Plain Concrete Above Top Slab Formwork Installation 6 15-Sep-24 22-Sep-24 Plain Concrete Above Top Slab Formwork Installation

PMP.4-PC-P1.130 Plain Concrete Casting 1 22-Sep-24 24-Sep-24 Plain Concrete Casting

PMP.4-PC-P1.140 Plain Concrete curing work 1 24-Sep-24 25-Sep-24 Plain Concrete curing work

PMP.4-PC-P1.150 Plain Concrete Formwork removal 1 25-Sep-24 26-Sep-24 Plain Concrete Formwork removal

MECHANICAL ROOM MEP (UCR) 79 10-Jun-24 15-Sep-24 15-Sep-24, MECHANICAL ROOM MEP (UCR)
ELECTRICAL WORK 79 10-Jun-24 15-Sep-24 15-Sep-24, ELECTRICAL WORK
POWER SYSTEM 51 10-Jun-24 13-Aug-24 13-Aug-24, POWER SYSTEM
LIGHTING SYSTEM 37 10-Jun-24 27-Jul-24 27-Jul-24, LIGHTING SYSTEM
LS-4-ELI.105 Lighting system Conduit and boxes Installation 8 10-Jun-24 24-Jun-24 Lighting system Conduit and boxes Installation

LS-4-ELI.115 Lighting system Cable Pulling 8 24-Jun-24 03-Jul-24 Lighting system Cable Pulling

LS-4-ELI.125 Lighting system Installations 8 03-Jul-24 13-Jul-24 Lighting system Installations

LS-4-ELI.135 Lighting system Termination 8 13-Jul-24 21-Jul-24 Lighting system Termination

LS-4-ELI.145 Lighting system Initial Testing 5 22-Jul-24 27-Jul-24 Lighting system Initial Testing

CABLE TRAY /CABLE ROUTING SYSTEM 48 10-Jun-24 08-Aug-24 08-Aug-24, CABLE TRAY /CABLE ROUTING SYSTEM
LS-4-ECT.105 Cable Tray Installation 10 10-Jun-24 26-Jun-24 Cable Tray Installation

LS-4-ECT.115 Cable Tray Inspection 10 26-Jun-24 08-Jul-24 Cable Tray Inspection

LS-4-ECT.125 LV Cable pulling 10 08-Jul-24 20-Jul-24 LV Cable pulling

LS-4-ECT.135 LV Cable Termination 10 20-Jul-24 30-Jul-24 LV Cable Termination

LS-4-ECT.145 LV Cable Initial Testing 8 31-Jul-24 08-Aug-24 LV Cable Initial Testing

SMALL POWER SYSTEM 39 10-Jun-24 29-Jul-24 29-Jul-24, SMALL POWER SYSTEM


LS-4-ESP.105 Small Power Conduit and boxes Installation 12 10-Jun-24 29-Jun-24 Small Power Conduit and boxes Installation

LS-4-ESP.115 Small Power Cable Pulling 10 29-Jun-24 10-Jul-24 Small Power Cable Pulling

LS-4-ESP.125 Small Power Installations 6 10-Jul-24 17-Jul-24 Small Power Installations

LS-4-ESP.135 Small Power Termination 6 17-Jul-24 23-Jul-24 Small Power Termination

LS-4-ESP.145 Small Power Initial Testing 5 24-Jul-24 29-Jul-24 Small Power Initial Testing

POWER DISTRIBUTION 39 29-Jun-24 13-Aug-24 13-Aug-24, POWER DISTRIBUTION


GENERATOR 39 29-Jun-24 13-Aug-24 13-Aug-24, GENERATOR
LS-4-EPD.105 Generator Cable Tray Installation 7 29-Jun-24 07-Jul-24 Generator Cable Tray Installation

LS-4-EPD.115 Generator Cable Pulling 7 07-Jul-24 15-Jul-24 Generator Cable Pulling

LS-4-EPD.125 Generator Cell Pannel Installation 7 15-Jul-24 22-Jul-24 Generator Cell Pannel Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
197 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-4-EPD.135 Generator Installation 7 23-Jul-24 30-Jul-24 Generator Installation

LS-4-EPD.145 Generator Pannel / Cable Termination 7 30-Jul-24 07-Aug-24 Generator Pannel / Cable Termination

LS-4-EPD.155 Generator Pannel / Cable initial Testing 5 07-Aug-24 13-Aug-24 Generator Pannel / Cable initial Testing

UPS 28 29-Jun-24 31-Jul-24 31-Jul-24, UPS


LS-4-EPD.165 UPS Cable Tray Installation 5 29-Jun-24 04-Jul-24 UPS Cable Tray Installation

LS-4-EPD.175 UPS Cable Pulling 5 04-Jul-24 10-Jul-24 UPS Cable Pulling

LS-4-EPD.185 UPS Pannel Installation 5 10-Jul-24 15-Jul-24 UPS Pannel Installation

LS-4-EPD.195 UPS Installation 5 16-Jul-24 21-Jul-24 UPS Installation

LS-4-EPD.205 UPS Pannel / Cable Termination 5 21-Jul-24 27-Jul-24 UPS Pannel / Cable Termination

LS-4-EPD.215 UPS Pannel / Cable initial Testing 4 27-Jul-24 31-Jul-24 UPS Pannel / Cable initial Testing

MDB 33 29-Jun-24 05-Aug-24 05-Aug-24, MDB


LS-4-EPD.225 MDB Cable Tray Installation 7 29-Jun-24 07-Jul-24 MDB Cable Tray Installation

LS-4-EPD.235 MDB Cable Pulling 7 07-Jul-24 15-Jul-24 MDB Cable Pulling

LS-4-EPD.245 MDB Pannel Installation 7 15-Jul-24 22-Jul-24 MDB Pannel Installation

LS-4-EPD.255 MDB Pannel / Cable Termination 7 23-Jul-24 30-Jul-24 MDB Pannel / Cable Termination

LS-4-EPD.265 MDB Pannel / Cable initial Testing 5 30-Jul-24 05-Aug-24 MDB Pannel / Cable initial Testing

MCC 33 07-Jul-24 13-Aug-24 13-Aug-24, MCC


LS-4-EPD.325 MCC Cable Tray Installation 7 07-Jul-24 15-Jul-24 MCC Cable Tray Installation

LS-4-EPD.335 MCC Cable Pulling 7 15-Jul-24 22-Jul-24 MCC Cable Pulling

LS-4-EPD.345 MCC Pannel Installation 7 23-Jul-24 30-Jul-24 MCC Pannel Installation

LS-4-EPD.355 MCC Pannel / Cable Termination 7 30-Jul-24 07-Aug-24 MCC Pannel / Cable Termination

LS-4-EPD.365 MCC Pannel / Cable initial Testing 5 07-Aug-24 13-Aug-24 MCC Pannel / Cable initial Testing

SMSB 24 07-Jul-24 03-Aug-24 03-Aug-24, SMSB


LS-4-EPD.275 SMSB Cable Tray Installation 5 07-Jul-24 13-Jul-24 SMSB Cable Tray Installation

LS-4-EPD.285 SMSB Cable Pulling 5 13-Jul-24 17-Jul-24 SMSB Cable Pulling

LS-4-EPD.295 SMSB Pannel Installation 5 18-Jul-24 23-Jul-24 SMSB Pannel Installation

LS-4-EPD.305 SMSB Pannel / Cable Termination 5 23-Jul-24 29-Jul-24 SMSB Pannel / Cable Termination

LS-4-EPD.315 SMSB Pannel / Cable initial Testing 4 29-Jul-24 03-Aug-24 SMSB Pannel / Cable initial Testing

DB 24 07-Jul-24 03-Aug-24 03-Aug-24, DB


LS-4-EPD.375 DB Cable Tray Installation 5 07-Jul-24 13-Jul-24 DB Cable Tray Installation

LS-4-EPD.385 DB Cable Pulling 5 13-Jul-24 17-Jul-24 DB Cable Pulling

LS-4-EPD.395 DB Pannel Installation 5 18-Jul-24 23-Jul-24 DB Pannel Installation

LS-4-EPD.405 DB Pannel / Cable Termination 5 23-Jul-24 29-Jul-24 DB Pannel / Cable Termination

LS-4-EPD.415 DB Pannel / Cable initial Testing 4 29-Jul-24 03-Aug-24 DB Pannel / Cable initial Testing

ISOLATOR 24 13-Jul-24 08-Aug-24 08-Aug-24, ISOLATOR


LS-4-EPD.425 Isolators Cable Tray Installation 5 13-Jul-24 17-Jul-24 Isolators Cable Tray Installation

LS-4-EPD.435 Isolators Cable Pulling 5 18-Jul-24 23-Jul-24 Isolators Cable Pulling

LS-4-EPD.445 Isolators Pannel Installation 5 23-Jul-24 29-Jul-24 Isolators Pannel Installation

LS-4-EPD.455 Isolators Pannel / Cable Termination 5 29-Jul-24 04-Aug-24 Isolators Pannel / Cable Termination

LS-4-EPD.465 Isolators Pannel / Cable initial Testing 4 04-Aug-24 08-Aug-24 Isolators Pannel / Cable initial Testing

LCP/ ELCP 24 13-Jul-24 08-Aug-24 08-Aug-24, LCP/ ELCP


LS-4-EPD.475 LCP/ELCP Cable Tray Installation 5 13-Jul-24 17-Jul-24 LCP/ELCP Cable Tray Installation

LS-4-EPD.485 LCP/ELCP Cable Pulling 5 18-Jul-24 23-Jul-24 LCP/ELCP Cable Pulling

LS-4-EPD.495 LCP/ELCP Pannel Installation 5 23-Jul-24 29-Jul-24 LCP/ELCP Pannel Installation

LS-4-EPD.505 LCP/ELCP Pannel / Cable Termination 5 29-Jul-24 04-Aug-24 LCP/ELCP Pannel / Cable Termination

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
198 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-4-EPD.515 LCP/ELCP Pannel / Cable initial Testing 4 04-Aug-24 08-Aug-24 LCP/ELCP Pannel / Cable initial Testing

LOW CURRENT SYSTEM 50 18-Jul-24 15-Sep-24 15-Sep-24, LOW CURRENT SYSTEM


FIRE ALARM SYSTEM 42 18-Jul-24 04-Sep-24 04-Sep-24, FIRE ALARM SYSTEM
LS-4-ELFA.105 Fire Alarm Conduit /Cable Tray Installation 9 18-Jul-24 28-Jul-24 Fire Alarm Conduit /Cable Tray Installation

LS-4-ELFA.115 Fire Alarm Cable Pulling 9 28-Jul-24 07-Aug-24 Fire Alarm Cable Pulling

LS-4-ELFA.125 Fire Alarm Devices Installation 9 07-Aug-24 18-Aug-24 Fire Alarm Devices Installation

LS-4-ELFA.135 Fire Alarm Devices and Cable Termination 9 18-Aug-24 28-Aug-24 Fire Alarm Devices and Cable Termination

LS-4-ELFA.145 Fire Alarm Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 Fire Alarm Devices and Cable initial Testing

ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA) 42 18-Jul-24 04-Sep-24 04-Sep-24, ICT SYSTEM (VIDEO SURVILLEIENCE, IP TELEPHONE, IP DATA)
LS-4-ELVS.105 ICT System Conduit /Cable Tray Installation 9 18-Jul-24 28-Jul-24 ICT System Conduit /Cable Tray Installation

LS-4-ELVS.115 ICT System Cable Pulling 9 28-Jul-24 07-Aug-24 ICT System Cable Pulling

LS-4-ELVS.125 ICT System Devices Installation 9 07-Aug-24 18-Aug-24 ICT System Devices Installation

LS-4-ELVS.135 ICT System Devices and Cable Termination 9 18-Aug-24 28-Aug-24 ICT System Devices and Cable Termination

LS-4-ELVS.145 ICT System Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 ICT System Devices and Cable initial Testing

ACCESS CONTROL SYSTEM 42 18-Jul-24 04-Sep-24 04-Sep-24, ACCESS CONTROL SYSTEM


LS-4-ELAC.105 Access Control System Conduit /Cable Tray Installation 9 18-Jul-24 28-Jul-24 Access Control System Conduit /Cable Tray Installation

LS-4-ELAC.115 Access Control System Cable Pulling 9 28-Jul-24 07-Aug-24 Access Control System Cable Pulling

LS-4-ELAC.125 Access Control System Devices Installation 9 07-Aug-24 18-Aug-24 Access Control System Devices Installation

LS-4-ELAC.135 Access Control System Devices and Cable Termination 9 18-Aug-24 28-Aug-24 Access Control System Devices and Cable Termination

LS-4-ELAC.145 Access Control System Devices and Cable initial Testing 6 28-Aug-24 04-Sep-24 Access Control System Devices and Cable initial Testing

PUBLIC ADDRESS SYSTEM 42 28-Jul-24 15-Sep-24 15-Sep-24, PUBLIC ADDRESS SYSTEM


LS-4-ELPA.105 Public Address System Conduit /Cable Tray Installation 9 28-Jul-24 07-Aug-24 Public Address System Conduit /Cable Tray Installation

LS-4-ELPA.115 Public Address System Cable Pulling 9 07-Aug-24 18-Aug-24 Public Address System Cable Pulling

LS-4-ELPA.125 Public Address System Devices Installation 9 18-Aug-24 28-Aug-24 Public Address System Devices Installation

LS-4-ELPA.135 Public Address System Devices and Cable Termination 9 28-Aug-24 08-Sep-24 Public Address System Devices and Cable Termination

LS-4-ELPA.145 Public Address System Devices and Cable initial Testing 6 08-Sep-24 15-Sep-24 Public Address System Devices and Cable initial Testing

SCADA SYSTEM 42 28-Jul-24 15-Sep-24 15-Sep-24, SCADA SYSTEM


LS-4-ELSC.105 SCADA System Conduit /Cable Tray Installation 9 28-Jul-24 07-Aug-24 SCADA System Conduit /Cable Tray Installation

LS-4-ELSC.115 SCADA System Cable Pulling 9 07-Aug-24 18-Aug-24 SCADA System Cable Pulling

LS-4-ELSC.125 SCADA System Devices Installation 9 18-Aug-24 28-Aug-24 SCADA System Devices Installation

LS-4-ELSC.135 SCADA System Devices and Cable Termination 9 28-Aug-24 08-Sep-24 SCADA System Devices and Cable Termination

LS-4-ELSC.145 SCADA System Devices and Cable initial Testing 6 08-Sep-24 15-Sep-24 SCADA System Devices and Cable initial Testing

RADIO RE- BROADCOASTING/ TETRA 42 28-Jul-24 15-Sep-24 15-Sep-24, RADIO RE- BROADCOASTING/ TETRA
LS-4-ELRD.105 Radio/TETRA System Conduit /Cable Tray Installation 9 28-Jul-24 07-Aug-24 Radio/TETRA System Conduit /Cable Tray Installation

LS-4-ELRD.115 Radio/TETRA System Cable Pulling 9 07-Aug-24 18-Aug-24 Radio/TETRA System Cable Pulling

LS-4-ELRD.125 Radio/TETRA System Devices Installation 9 18-Aug-24 28-Aug-24 Radio/TETRA System Devices Installation

LS-4-ELRD.135 Radio/TETRA System Devices and Cable Termination 9 28-Aug-24 08-Sep-24 Radio/TETRA System Devices and Cable Termination

LS-4-ELRD.145 Radio/TETRA System Devices and Cable initial Testing 6 08-Sep-24 15-Sep-24 Radio/TETRA System Devices and Cable initial Testing

MECHANICAL WORK 15 07-Aug-24 25-Aug-24 25-Aug-24, MECHANICAL WORK


FIRE FIGHTING 13 07-Aug-24 22-Aug-24 22-Aug-24, FIRE FIGHTING
LS-4-MFF.105 Fire Fighting system Pipe and accessories installation 11 07-Aug-24 20-Aug-24 Fire Fighting system Pipe and accessories installation

LS-4-MFF.125 Fire Fighting system fire hose cabinet/extingusher installation 3 17-Aug-24 20-Aug-24 Fire Fighting system fire hose cabinet/extingusher installation

LS-4-MFF.135 Fire Fighting system initial testing 2 20-Aug-24 22-Aug-24 Fire Fighting system initial testing

HVAC 15 07-Aug-24 25-Aug-24 25-Aug-24, HVAC


LS-4-MHV.105 Duct and accessories installation 12 07-Aug-24 21-Aug-24 Duct and accessories installation

LS-4-MHV.115 Fan installation 4 17-Aug-24 21-Aug-24 Fan installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
199 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
LS-4-MHV.135 HVAC inital testing 3 21-Aug-24 25-Aug-24 HVAC inital testing

PLUMBING 4 07-Aug-24 12-Aug-24 12-Aug-24, PLUMBING


LS-4-MPL.105 Plumbing drainage system installation 3 07-Aug-24 11-Aug-24 Plumbing drainage system installation

LS-4-MPL.115 Plumbing drainage system initial testing 1 11-Aug-24 12-Aug-24 Plumbing drainage system initial testing

DELAY EVENT-7 278 31-May-22 A 26-Apr-23 26-Apr-23, DELAY EVENT-7


RAM1025 Engineer Instruction No 2,3 179 31-May-22 A 28-Dec-22 A Engineer Instruction No 2,3

ZONE 1 90 29-Oct-22 09-Feb-23 09-Feb-23, ZONE 1


RAM1045 Excess Excavation @Sta. 0+120 ~ 0+200 4 29-Oct-22 01-Nov-22 Excess Excavation @Sta. 0+120 ~ 0+200

RAM1050 Excess Excavation @Sta. 0+200 ~ 0+300 82 29-Oct-22 31-Jan-23 Excess Excavation @Sta. 0+200 ~ 0+300

RAM1090 Excess Excavation @Sta. 0+300 ~ 0+400 90 29-Oct-22 09-Feb-23 Excess Excavation @Sta. 0+300 ~ 0+400

RAM1105 Excess Excavation @Sta. 0+400 ~ 0+500 39 29-Oct-22 12-Dec-22 Excess Excavation @Sta. 0+400 ~ 0+500

ZONE 2 122 29-Oct-22 19-Mar-23 19-Mar-23, ZONE 2


RAM1030 Backfilling work 14 29-Oct-22 13-Nov-22 Backfilling work

RAM1035 Shoring for Cemetery 108 14-Nov-22 19-Mar-23 Shoring for Cemetery

RAM1345 Excess Excavation @Sta. 0+500 ~ 0+600 24 29-Oct-22 24-Nov-22 Excess Excavation @Sta. 0+500 ~ 0+600

RAM1450 Excess Excavation @Sta. 0+600 ~ 0+700 22 29-Oct-22 22-Nov-22 Excess Excavation @Sta. 0+600 ~ 0+700

RAM1455 Excess Excavation @Sta. 0+700 ~ 0+800 56 14-Jan-23 19-Mar-23 Excess Excavation @Sta. 0+700 ~ 0+800

RAM1460 Excess Excavation @Sta. 0+800 ~ 0+900 103 20-Nov-22 19-Mar-23 Excess Excavation @Sta. 0+800 ~ 0+900

RAM1465 Excess Excavation @Sta. 0+900 ~ 0+990 55 29-Oct-22 31-Dec-22 Excess Excavation @Sta. 0+900 ~ 0+990

ZONE 3 86 29-Oct-22 05-Feb-23 05-Feb-23, ZONE 3


RAM1470 Excess Excavation @Sta. 0+994 ~ 1+094 29 29-Oct-22 30-Nov-22 Excess Excavation @Sta. 0+994 ~ 1+094

RAM1475 Excess Excavation @Sta. 1+094 ~ 1+194 86 29-Oct-22 05-Feb-23 Excess Excavation @Sta. 1+094 ~ 1+194

RAM1480 Excess Excavation @Sta. 1+194 ~ 1+268 45 29-Oct-22 19-Dec-22 Excess Excavation @Sta. 1+194 ~ 1+268

ZONE 4 138 29-Oct-22 06-Apr-23 06-Apr-23, ZONE 4


RAM1485 Excess Excavation @Sta. 1+268 ~ 1+368 78 29-Oct-22 26-Jan-23 Excess Excavation @Sta. 1+268 ~ 1+368

RAM1490 Excess Excavation @Sta. 1+368 ~ 1+468 56 28-Jan-23 02-Apr-23 Excess Excavation @Sta. 1+368 ~ 1+468

RAM1495 Excess Excavation @Sta. 1+468 ~ 1+568 73 29-Oct-22 21-Jan-23 Excess Excavation @Sta. 1+468 ~ 1+568

RAM1500 Excess Excavation @Sta. 1+568 ~ 1+668 65 22-Jan-23 06-Apr-23 Excess Excavation @Sta. 1+568 ~ 1+668

RAM1505 Excess Excavation @Sta. 1+668 ~ 1+768 87 29-Oct-22 06-Feb-23 Excess Excavation @Sta. 1+668 ~ 1+768

ZONE 5 45 29-Oct-22 19-Dec-22 19-Dec-22, ZONE 5


RAM1510 Excess Excavation @Sta. 1+768 ~ 1+775 45 29-Oct-22 19-Dec-22 Excess Excavation @Sta. 1+768 ~ 1+775

ZONE10 127 29-Oct-22 25-Mar-23 25-Mar-23, ZONE10


RAM1065 Prepare & Submit Traffic Study 21 29-Oct-22 21-Nov-22 Prepare & Submit Traffic Study

RAM1070 Review & Approval Traffic Study 14 22-Nov-22 07-Dec-22 Review & Approval Traffic Study

RAM1075 Detour Closure 7 08-Dec-22 15-Dec-22 Detour Closure

RAM1080 NOCs form Authories ( SEC, NWC,etc.) 14 02-Nov-22 17-Nov-22 NOCs form Authories ( SEC, NWC,etc.)

RAM1085 Utilites Relocation 30 17-Dec-22 19-Jan-23 Utilites Relocation

RAM1091 Excess Excavation @Sta. 0+100 ~ 0+200 47 29-Oct-22 21-Dec-22 Excess Excavation @Sta. 0+100 ~ 0+200

RAM1092 Excess Excavation @Sta. 0+200 ~ 0+300 53 29-Oct-22 28-Dec-22 Excess Excavation @Sta. 0+200 ~ 0+300

RAM1093 Excess Excavation @Sta. 0+300 ~ 0+400 55 21-Jan-23 25-Mar-23 Excess Excavation @Sta. 0+300 ~ 0+400

RAM1095 Prepare and Submit Proposals for Utilites Relocation 4 29-Oct-22 01-Nov-22 Prepare and Submit Proposals for Utilites Relocation

RAM1096 Excess Excavation @Sta. 0+020 ~ 0+100 1 29-Oct-22 29-Oct-22 Excess Excavation @Sta. 0+020 ~ 0+100

ZONE11 152 29-Oct-22 26-Apr-23 26-Apr-23, ZONE11


RAM1100 Prepare & Submit Traffic Study 21 29-Oct-22 21-Nov-22 Prepare & Submit Traffic Study

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
200 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM1106 Excess Excavation @Sta. 0+020 ~ 0+100 5 29-Oct-22 02-Nov-22 Excess Excavation @Sta. 0+020 ~ 0+100

RAM1107 Excess Excavation @Sta. 0+100 ~ 0+200 74 29-Oct-22 22-Jan-23 Excess Excavation @Sta. 0+100 ~ 0+200

RAM1108 Excess Excavation @Sta. 0+200 ~ 0+300 73 29-Oct-22 21-Jan-23 Excess Excavation @Sta. 0+200 ~ 0+300

RAM1109 Excess Excavation @Sta. 0+300 ~ 0+430 80 21-Jan-23 26-Apr-23 Excess Excavation @Sta. 0+300 ~ 0+430

RAM1110 Prepare and Submit Proposals for Utilites Relocation 4 29-Oct-22 01-Nov-22 Prepare and Submit Proposals for Utilites Relocation

RAM1115 NOCs form Authories ( SEC, NWC,etc.) 14 02-Nov-22 17-Nov-22 NOCs form Authories ( SEC, NWC,etc.)

RAM1120 Review & Approval Traffic Study 14 22-Nov-22 07-Dec-22 Review & Approval Traffic Study

RAM1125 Detour Closure 7 08-Dec-22 15-Dec-22 Detour Closure

RAM1130 Utilites Relocation 30 17-Dec-22 19-Jan-23 Utilites Relocation

DELAY EVENT-8 371 31-May-22 A 01-Jun-23 01-Jun-23, DELAY EVENT-8


RAM1185 Delay due to clash between AIP 2400 Dia sewer line and MIP tunnel at zone 1 371 31-May-22 A 16-May-23 Delay due to clash between AIP 2400 Dia sewer line and MIP tunnel at zone 1

RAM1305 Demolish of AIP 2400 Dia sewer line 14 17-May-23 01-Jun-23 Demolish of AIP 2400 Dia sewer line

MOBILIZATION & GENERAL ARRANGEMENT 1138 21-May-22 A 16-Feb-26 16-Feb-26, MOBILIZATION & GENERAL ARRANGEMENT
SITE OFFICES FOR CLIENT/CONSULTANT/CONTRACTOR 1039 07-Jun-22 A 25-Oct-25 25-Oct-25, SITE OFFICES FOR CLIENT/CONSULTANT/CONTRACTOR
SITE FACILITIES & OFFICES 139 07-Jun-22 A 13-Nov-22 13-Nov-22, SITE FACILITIES & OFFICES
RAM-MB-SFO.100 Placement of Portacabins and some Facilities till the site offices Readiness 30 07-Jun-22 A 04-Jul-22 A Placement of Portacabins and some Facilities till the site offices Readiness

RAM-MB-SFO.107 Site Offices Layout Plan Preparation,Submission & Approval 7 05-Jul-22 A 16-Jul-22 A Site Offices Layout Plan Preparation,Submission & Approval

RAM-MB-SFO.108 Site Offices Fabrication Shop Drawings Preparation, Submission & Approval 7 17-Jul-22 A 07-Aug-22 A Site Offices Fabrication Shop Drawings Preparation, Submission & Approval

RAM-MB-SFO.109 Site Offices External Works, MEP & Foundation Submission & Approval 8 16-Jul-22 A 08-Aug-22 A Site Offices External Works, MEP & Foundation Submission & Approval

RAM-MB-SFO.110 Site Office Manufacture & Fabrication 40 07-Aug-22 A 20-Oct-22 A Site Office Manufacture & Fabrication

RAM-MB-SFO.111 Site Clearance, Filling & Compaction Works 30 15-Aug-22 A 18-Oct-22 A Site Clearance, Filling & Compaction Works

RAM-MB-SFO.112 Foundation Work 8 29-Aug-22 A 22-Oct-22 A Foundation Work

RAM-MB-SFO.115 Site Offices Construction 8 06-Oct-22 A 30-Oct-22 Site Offices Construction

RAM-MB-SFO.122 Finishing Work for Site Offices 8 11-Oct-22 A 10-Nov-22 Finishing Work for Site Offices

RAM-MB-SFO.135 MEP Work for Site Offices 7 09-Oct-22 A 05-Nov-22 MEP Work for Site Offices

RAM-MB-SFO.155 Installation Ac/s and Furniture and Electronic Appliances 6 12-Oct-22 A 12-Nov-22 Installation Ac/s and Furniture and Electronic Appliances

RAM-MB-SFO.175 External Works Installation 2 10-Nov-22 13-Nov-22 External Works Installation

RAM-MB-SFO.180 Site Offices Hand over 0 13-Nov-22 Site Offices Hand over

SITE OFFICE MAINTENANCE 900 13-Nov-22 25-Oct-25 25-Oct-25, SITE OFFICE MAINTENANCE
RAM-MB-SFOM.160 Maintenance of Client/Consultant/Contractor Offices 900 13-Nov-22 25-Oct-25 Maintenance of Client/Consultant/Contractor Offices

SITE OFFICE OPERATION 900 13-Nov-22 25-Oct-25 25-Oct-25, SITE OFFICE OPERATION
RAM-MB-SFOO.180 Client/Consultant/Contractor Offices Operation Cost 900 13-Nov-22 25-Oct-25 Client/Consultant/Contractor Offices Operation Cost

CLIENT/CONSULTANT VEHICLES 700 31-May-22 A 01-Nov-22 01-Nov-22, CLIENT/CONSULTANT VEHICLES


RAM-STF-VEH.100 Vehicles for Client/PMC/TSC Staff 700 31-May-22 A 01-Nov-22 Vehicles for Client/PMC/TSC Staff

JV ACCOMMODATION & BUILDING 700 01-Aug-22 A 24-Jul-25 24-Jul-25, JV ACCOMMODATION & BUILDING
JV-STF-ACC.100 Accommodation & Buildings for Contractor Staff 700 01-Aug-22 A 24-Jul-25 Accommodation & Buildings for Contractor Staff

OTHER GENERAL ITEMS 1012 01-Aug-22 A 16-Feb-26 16-Feb-26, OTHER GENERAL ITEMS
Material Testing at Site and/ or Manufacturer 600 13-Feb-23 29-Jan-25 29-Jan-25, Material Testing at Site and/ or Manufacturer
RAM-MB-MT&M.115 Material Testing at Manfacturer 300 13-Feb-23 05-Feb-24 Material Testing at Manfacturer

RAM-MB-MT&M.120 Material Testing at Site 130 25-May-24 28-Oct-24 Material Testing at Site

RAM-MB-MT&M.125 Testing for works 150 07-Aug-24 29-Jan-25 Testing for works

PLANTS 940 13-Nov-22 10-Dec-25 10-Dec-25, PLANTS


RAM-MB-SWLB.110 Plants 940 13-Nov-22 10-Dec-25 Plants

TEMPORARY WORKS METHOD RELATED CHARGES 610 22-Jan-23 20-Jan-25 20-Jan-25, TEMPORARY WORKS METHOD RELATED CHARGES
RAM-MB-TW.100 Temporary Works Method Related Charges Part #01 100 22-Jan-23 22-May-23 Temporary Works Method Related Charges Part #01

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
201 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM-MB-TW.105 Temporary Works Method Related Charges Part #02 200 22-May-23 15-Jan-24 Temporary Works Method Related Charges Part #02

RAM-MB-TW.110 Temporary Works Method Related Charges #03 250 25-Mar-24 20-Jan-25 Temporary Works Method Related Charges #03

PROVISIONAL SUM 400 28-Oct-24 16-Feb-26 16-Feb-26, PROVISIONAL SUM


RAM-MB-PS.120 Provisional Sum Part #01 180 02-Feb-25 08-Sep-25 Provisional Sum Part #01

RAM-MB-PS.125 Provisional Sum Part #02 310 28-Oct-24 03-Nov-25 Provisional Sum Part #02

RAM-MB-PS.130 Provisional Sum Part #03 90 03-Nov-25 16-Feb-26 Provisional Sum Part #03

Specified Temporary Works 827 01-Aug-22 A 07-Aug-25 07-Aug-25, Specified Temporary Works
RAM-MB-STW.115 Specified Temporary Works Part #01 (site securty, cleaning baricated and safe) 30 01-Aug-22 A 01-Dec-22 Specified Temporary Works Part #01 (site securty, cleaning baricated and safe)

RAM-MB-STW.120 Specified Temporary Works Part #02 (site securty, cleaning baricated and safe) 30 02-Mar-23 05-Apr-23 Specified Temporary Works Part #02 (site securty, cleaning baricated and safe)

RAM-MB-STW.125 Specified Temporary Works Part #03 (site securty, cleaning baricated and safe) 30 05-Jul-25 07-Aug-25 Specified Temporary Works Part #03 (site securty, cleaning baricated and safe)

KEEPING THE EXISTING UTILITY SERVICE ARE OPERTIONAL 722 29-Oct-22 05-Mar-25 05-Mar-25, KEEPING THE EXISTING UTILITY SERVICE ARE OPERTIONAL
RAM-MB-KEU.115 Keeping the Existing Utility Services are Operational Part #01 400 29-Oct-22 14-Feb-24 Keeping the Existing Utility Services are Operational Part #01

RAM-MB-KEU.120 Keeping the Existing Utility Services are Operational Part #02 30 30-Jan-25 05-Mar-25 Keeping the Existing Utility Services are Operational Part #02

CONTRACTOR'S DELIVERABLES 111 21-May-22 A 02-Nov-22 02-Nov-22, CONTRACTOR'S DELIVERABLES


RAM-CONT-DEL.100 Bank Account Assessment 20 21-Jun-22 A 21-Jun-22 A Bank Account Assessment

RAM-CONT-DEL.105 Project Insurance 28 21-May-22 A 21-Jun-22 A Project Insurance

RAM-CONT-DEL.110 Performance Bond 28 31-May-22 A 21-Jun-22 A Performance Bond

RAM-CONT-DEL.115 Organization Chart & Key Personnel CV's Submission 15 01-Jun-22 A 04-Sep-22 A Organization Chart & Key Personnel CV's Submission

RAM-CONT-DEL.125 Site Layout Plan 21 12-Jul-22 A 17-Aug-22 A Site Layout Plan

RAM-CONT-DEL.130 Logistics & Interface Plan 21 06-Aug-22 A 11-Aug-22 A Logistics & Interface Plan

RAM-CONT-DEL.135 Health, Safety and Environmental Plan 21 05-Jul-22 A 18-Aug-22 A Health, Safety and Environmental Plan

RAM-CONT-DEL.140 Quality Management Plan 26 20-Jun-22 A 15-Oct-22 A Quality Management Plan

RAM-CONT-DEL.160 Project Baseline Schedule 26 27-Jun-22 A 12-Sep-22 A Project Baseline Schedule

RAM-CONT-DEL.165 Project Execution Plan 26 25-Jun-22 A 29-Aug-22 A Project Execution Plan

RAM-CONT-DEL.170 Project Signboard Drawing Submission & Approval 7 23-Jun-22 A 26-Jun-22 A Project Signboard Drawing Submission & Approval

RAM-CONT-DEL.175 Project Signboard, Manufacture & Installation 35 26-Jun-22 A 02-Nov-22 Project Signboard, Manufacture & Installation

TRAFFIC MANAGMENT 940 13-Nov-22 10-Dec-25 10-Dec-25, TRAFFIC MANAGMENT


RAM-MB-TM.115 Traffic Management 940 13-Nov-22 10-Dec-25 Traffic Management

TRAFFIC DIVERSION PLAN 164 03-Dec-22 14-Jun-23 14-Jun-23, TRAFFIC DIVERSION PLAN
KEY DATES 0 21-Feb-23 21-Feb-23 21-Feb-23, KEY DATES
TMP-KD100 Al Amida Road Completion by Other Contractor 0 21-Feb-23* Al Amida Road Completion by Other Contractor

KAAR TRAFFIC DIVERSION -1 FOR ZONE 8 & 9 35 03-Dec-22 11-Jan-23 11-Jan-23, KAAR TRAFFIC DIVERSION -1 FOR ZONE 8 & 9
TMP-KTD-Z8&9.100 Diversion Plan Preparation & Submission to Client/PMC/TSC 8 03-Dec-22 11-Dec-22 Diversion Plan Preparation & Submission to Client/PMC/TSC

TMP-KTD-Z8&9.105 Diversion Plan Review & Approval From Client/PMC/TSC 7 12-Dec-22 19-Dec-22 Diversion Plan Review & Approval From Client/PMC/TSC

TMP-KTD-Z8&9.110 Client Approved Diversion Plan Submission to Traffic Police Department 1 20-Dec-22 20-Dec-22 Client Approved Diversion Plan Submission to Traffic Police Department

TMP-KTD-Z8&9.115 Traffic Police Department Review & Approval 7 21-Dec-22 28-Dec-22 Traffic Police Department Review & Approval

TMP-KTD-Z8&9.120 Issuance for Permits from Madinah Municipality/Civil Defence 7 29-Dec-22 05-Jan-23 Issuance for Permits from Madinah Municipality/Civil Defence

TMP-KTD-Z8&9.125 Placement of New Jersey Barriers 5 07-Jan-23 11-Jan-23 Placement of New Jersey Barriers

TMP-KTD-Z8&9.130 Installation of Lights & Signage 5 07-Jan-23 11-Jan-23 Installation of Lights & Signage

AIRPORT ROAD TUNNEL DIVERSION - 2 FOR ZONE 6 & 7 37 12-Jan-23 23-Feb-23 23-Feb-23, AIRPORT ROAD TUNNEL DIVERSION - 2 FOR ZONE 6 & 7
TMP-ARTD-Z6&7.100 Diversion Plan Preparation & Submission to Client/PMC/TSC 8 12-Jan-23 21-Jan-23 Diversion Plan Preparation & Submission to Client/PMC/TSC

TMP-ARTD-Z6&7.105 Diversion Plan Review & Approval From Client/PMC/TSC 7 22-Jan-23 29-Jan-23 Diversion Plan Review & Approval From Client/PMC/TSC

TMP-ARTD-Z6&7.110 Client Approved Diversion Plan Submission to Traffic Police Department 1 30-Jan-23 30-Jan-23 Client Approved Diversion Plan Submission to Traffic Police Department

TMP-ARTD-Z6&7.115 Traffic Police Department Review & Approval 7 31-Jan-23 07-Feb-23 Traffic Police Department Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
202 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TMP-ARTD-Z6&7.120 Issuance for Permits from Madinah Municipality/Civil Defence 7 08-Feb-23 15-Feb-23 Issuance for Permits from Madinah Municipality/Civil Defence

TMP-ARTD-Z6&7.125 Placement of New Jersey Barriers 5 16-Feb-23 21-Feb-23 Placement of New Jersey Barriers

TMP-ARTD-Z6&7.130 Installation of Lights & Signage 7 16-Feb-23 23-Feb-23 Installation of Lights & Signage

ABU THAR ROAD DIVERSION - 03 - FOR ZONE 6 37 25-Feb-23 08-Apr-23 08-Apr-23, ABU THAR ROAD DIVERSION - 03 - FOR ZONE 6
TMP-ATRD-Z6.100 Diversion Plan Preparation & Submission to Client/PMC/TSC 8 25-Feb-23 05-Mar-23 Diversion Plan Preparation & Submission to Client/PMC/TSC

TMP-ATRD-Z6.105 Diversion Plan Review & Approval From Client/PMC/TSC 7 06-Mar-23 13-Mar-23 Diversion Plan Review & Approval From Client/PMC/TSC

TMP-ATRD-Z6.110 Client Approved Diversion Plan Submission to Traffic Police Department 1 14-Mar-23 14-Mar-23 Client Approved Diversion Plan Submission to Traffic Police Department

TMP-ATRD-Z6.115 Traffic Police Department Review & Approval 7 15-Mar-23 22-Mar-23 Traffic Police Department Review & Approval

TMP-ATRD-Z6.120 Issuance for Permits from Madinah Municipality/Civil Defence 7 23-Mar-23 30-Mar-23 Issuance for Permits from Madinah Municipality/Civil Defence

TMP-ATRD-Z6.125 Placement of New Jersey Barriers 5 01-Apr-23 05-Apr-23 Placement of New Jersey Barriers

TMP-ATRD-Z6.130 Installation of Lights & Signage 7 01-Apr-23 08-Apr-23 Installation of Lights & Signage

AL AMIDA ROAD DETOUR - 1 FOR ZONE 8 & 9 55 09-Apr-23 14-Jun-23 14-Jun-23, AL AMIDA ROAD DETOUR - 1 FOR ZONE 8 & 9
TMP-AARD-Z8&9.100 Diversion Plan Preparation & Submission to Client/PMC/TSC 15 09-Apr-23 29-Apr-23 Diversion Plan Preparation & Submission to Client/PMC/TSC

TMP-AARD-Z8&9.105 Diversion Plan Review & Approval From Client/PMC/TSC 10 30-Apr-23 10-May-23 Diversion Plan Review & Approval From Client/PMC/TSC

TMP-AARD-Z8&9.110 Client Approved Diversion Plan Submission to Traffic Police Department 1 11-May-23 11-May-23 Client Approved Diversion Plan Submission to Traffic Police Department

TMP-AARD-Z8&9.115 Traffic Police Department Review & Approval 14 13-May-23 28-May-23 Traffic Police Department Review & Approval

TMP-AARD-Z8&9.120 Issuance for Permits from Madinah Municipality/Civil Defence 12 29-May-23 11-Jun-23 Issuance for Permits from Madinah Municipality/Civil Defence

TMP-AARD-Z8&9.125 Placement of New Jersey Barriers 3 12-Jun-23 14-Jun-23 Placement of New Jersey Barriers

TMP-AARD-Z8&9.130 Installation of Lights & Signage 3 12-Jun-23 14-Jun-23 Installation of Lights & Signage

PERMITS & APPROVALS 85 06-Oct-22 A 23-Jan-23 23-Jan-23, PERMITS & APPROVALS


RAM-PRA.100 Traffic Police Department Permits & Approvals 45 06-Oct-22 A 23-Jan-23 A Traffic Police Department Permits & Approvals

RAM-PRA.105 Madinah Munawarah Municipalilty Permits & Approvals 45 29-Oct-22 19-Dec-22 Madinah Munawarah Municipalilty Permits & Approvals

RAM-PRA.110 Saudi Electricity Company (SCECO) Permits & Approvals 45 06-Nov-22 27-Dec-22 Saudi Electricity Company (SCECO) Permits & Approvals

RAM-PRA.115 National Water Company (NWC) Permits & Approvals 45 14-Nov-22 04-Jan-23 National Water Company (NWC) Permits & Approvals

RAM-PRA.120 Ministry of Transport (MOT) Permits & Approvals 45 22-Nov-22 12-Jan-23 Ministry of Transport (MOT) Permits & Approvals

RAM-PRA.125 Obtaining NOC's for Test Pits from Concerned Authorities 45 22-Nov-22 12-Jan-23 Obtaining NOC's for Test Pits from Concerned Authorities

GENERAL ENGINEERING 492 01-Jun-22 A 07-Jan-24 07-Jan-24, GENERAL ENGINEERING


PROCUREMENT OF SUBCONTRACTORS/VENDERS 190 01-Jun-22 A 11-Jan-23 11-Jan-23, PROCUREMENT OF SUBCONTRACTORS/VENDERS
CIVIL 142 01-Jun-22 A 16-Nov-22 16-Nov-22, CIVIL
RAM-PRO-C-S&V.100 Prequalification of Geo-Technical Subcontractor 14 01-Jun-22 A 22-Jun-22 A Prequalification of Geo-Technical Subcontractor

RAM-PRO-C-S&V.105 Prequalification of Blasting Subcontractor 20 22-Jun-22 A 02-Nov-22 Prequalification of Blasting Subcontractor

RAM-PRO-C-S&V.110 Prequalification of Shoring Subcontractor 20 19-Jun-22 A 19-Jun-22 A Prequalification of Shoring Subcontractor

RAM-PRO-C-S&V.115 Prequalification of Dewatering Subcontractor 15 01-Jun-22 A 29-Jun-22 A Prequalification of Dewatering Subcontractor

RAM-PRO-C-S&V.120 Prequalification of Soil Improvement Subcontractor 15 01-Jun-22 A 19-Jun-22 A Prequalification of Soil Improvement Subcontractor

RAM-PRO-C-S&V.125 Prequalification of Site Batching Plants Vender 20 01-Jun-22 A 27-Jun-22 A Prequalification of Site Batching Plants Vender

RAM-PRO-C-S&V.130 Approval of Geo-Technical Subcontractor 12 22-Jun-22 A 27-Jun-22 A Approval of Geo-Technical Subcontractor

RAM-PRO-C-S&V.135 Approval of Blasting Subcontractor 12 03-Nov-22 16-Nov-22 Approval of Blasting Subcontractor

RAM-PRO-C-S&V.140 Approval of Shoring Subcontractor 12 19-Jun-22 A 22-Jun-22 A Approval of Shoring Subcontractor

RAM-PRO-C-S&V.145 Approval of Dewatering Subcontractor 12 29-Jun-22 A 30-Jun-22 A Approval of Dewatering Subcontractor

RAM-PRO-C-S&V.150 Approval of Soil Improvement Subcontractor 12 19-Jul-22 A 22-Jul-22 A Approval of Soil Improvement Subcontractor

RAM-PRO-C-S&V.155 Approval of Site Batching Plant's Vender Approval 12 27-Jun-22 A 03-Jul-22 A Approval of Site Batching Plant's Vender Approval

MECHANICAL 123 12-Jul-22 A 01-Dec-22 01-Dec-22, MECHANICAL


RAM-PRO-M-S&V.100 Prequalification of DI/GRP/MS/HDPE/UPVC Pipes Supplier 30 12-Jul-22 A 02-Oct-22 A Prequalification of DI/GRP/MS/HDPE/UPVC Pipes Supplier

RAM-PRO-M-S&V.105 Prequalification of AV/GV/BV/WO Valves Supplier 30 24-Jul-22 A 26-Sep-22 A Prequalification of AV/GV/BV/WO Valves Supplier

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
203 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM-PRO-M-S&V.110 Prequalification of All Types of Pumps Supplier 30 29-Oct-22 01-Dec-22 Prequalification of All Types of Pumps Supplier

RAM-PRO-M-S&V.115 Prequalification of Firefighting Pipes & Hydrants Supplier 30 04-Aug-22 A 26-Sep-22 A Prequalification of Firefighting Pipes & Hydrants Supplier

ELECTRICAL 128 29-Aug-22 A 11-Jan-23 11-Jan-23, ELECTRICAL


RAM-PRO-E-S&V.120 Prequalification of Cables/Cable Trays/Wires/Conduit Pipes Supplier 30 29-Aug-22 A 11-Sep-22 A Prequalification of Cables/Cable Trays/Wires/Conduit Pipes Supplier

RAM-PRO-E-S&V.125 Prequalification of LV/MV Switchgear/Transformer/UPS Supplier 30 25-Sep-22 A 01-Dec-22 Prequalification of LV/MV Switchgear/Transformer/UPS Supplier

RAM-PRO-E-S&V.130 Prequalification Traffic Signal System Supplier 30 29-Oct-22 01-Dec-22 Prequalification Traffic Signal System Supplier

RAM-PRO-E-S&V.135 Prequalification of Distribution Boards Supplier 30 03-Nov-22 07-Dec-22 Prequalification of Distribution Boards Supplier

RAM-PRO-E-S&V.140 Prequalification of Elevator Supplier 30 08-Dec-22 11-Jan-23 Prequalification of Elevator Supplier

MATERIAL SUBMITTAL 359 09-Oct-22 A 07-Jan-24 07-Jan-24, MATERIAL SUBMITTAL


RAM110 Completion of Material Submittal 0 07-Jan-24* Completion of Material Submittal

DUCTILE IRON PIPES 20 05-Jan-23 28-Jan-23 28-Jan-23, DUCTILE IRON PIPES


RAM-MS-DIP.100 Material Submission 8 05-Jan-23 14-Jan-23 Material Submission

RAM-MS-DIP.105 Review & Approval 12 15-Jan-23 28-Jan-23 Review & Approval

MILD STEEL PIPES 20 15-Jan-23 06-Feb-23 06-Feb-23, MILD STEEL PIPES


RAM-MS-MSP.100 Material Submission 8 15-Jan-23 23-Jan-23 Material Submission

RAM-MS-MSP.105 Review & Approval 12 24-Jan-23 06-Feb-23 Review & Approval

GRP PIPES 20 07-Feb-23 01-Mar-23 01-Mar-23, GRP PIPES


RAM-MS-GRP.100 Material Submission 8 07-Feb-23 15-Feb-23 Material Submission

RAM-MS-GRP.105 Review & Approval 12 16-Feb-23 01-Mar-23 Review & Approval

WATER METER 22 02-Mar-23 27-Mar-23 27-Mar-23, WATER METER


RAM-MS-DIP.190 Material Submission 10 02-Mar-23 13-Mar-23 Material Submission

RAM-MS-DIP.195 Review & Approval 12 14-Mar-23 27-Mar-23 Review & Approval

RC PIPES 20 28-Mar-23 19-Apr-23 19-Apr-23, RC PIPES


RAM-MS-UPVP.110 Material Submission 8 28-Mar-23 05-Apr-23 Material Submission

RAM-MS-UPVP.115 Review & Approval 12 06-Apr-23 19-Apr-23 Review & Approval

DI & GRP PIPES FITTINGS 22 02-Mar-23 27-Mar-23 27-Mar-23, DI & GRP PIPES FITTINGS
RAM-MS-DIF.180 Material Submission 10 02-Mar-23 13-Mar-23 Material Submission

RAM-MS-DIF.185 Review & Approval 12 14-Mar-23 27-Mar-23 Review & Approval

HDPE PIPES 20 02-Mar-23 25-Mar-23 25-Mar-23, HDPE PIPES


RAM-MS-HDP.100 Material Submission 8 02-Mar-23 11-Mar-23 Material Submission

RAM-MS-HDP.105 Review & Approval 12 12-Mar-23 25-Mar-23 Review & Approval

UPVC PIPES 20 26-Mar-23 17-Apr-23 17-Apr-23, UPVC PIPES


RAM-MS-UPVP.100 Material Submission 8 26-Mar-23 03-Apr-23 Material Submission

RAM-MS-UPVP.105 Review & Approval 12 04-Apr-23 17-Apr-23 Review & Approval

VALVES & FITTINGS (GV, BV, AV, WO) 22 18-Apr-23 16-May-23 16-May-23, VALVES & FITTINGS (GV, BV, AV, WO)
RAM-MS-VLV.100 Material Submission 10 18-Apr-23 02-May-23 Material Submission

RAM-MS-VLV.105 Review & Approval 12 03-May-23 16-May-23 Review & Approval

PRECAST RC MANHOLES 22 17-May-23 11-Jun-23 11-Jun-23, PRECAST RC MANHOLES


RAM-MS-RCM.100 Material Submission 10 17-May-23 28-May-23 Material Submission

RAM-MS-RCM.105 Review & Approval 12 29-May-23 11-Jun-23 Review & Approval

FIRE HYDRANTS 22 12-Jun-23 10-Jul-23 10-Jul-23, FIRE HYDRANTS


RAM-MS-FHD.100 Material Submission 10 12-Jun-23 22-Jun-23 Material Submission

RAM-MS-FHD.105 Review & Approval 12 24-Jun-23 10-Jul-23 Review & Approval

SUBMERSIBALE PUMPS 22 11-Jul-23 05-Aug-23 05-Aug-23, SUBMERSIBALE PUMPS


RAM-MS-SMP.100 Material Submission 10 11-Jul-23 22-Jul-23 Material Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
204 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM-MS-SMP.105 Review & Approval 12 23-Jul-23 05-Aug-23 Review & Approval

IMPOUNDING SUMP PUMP 22 06-Aug-23 30-Aug-23 30-Aug-23, IMPOUNDING SUMP PUMP


RAM-MS-ISP.100 Material Submission 10 06-Aug-23 16-Aug-23 Material Submission

RAM-MS-ISP.105 Review & Approval 12 17-Aug-23 30-Aug-23 Review & Approval

AUTOMATIC SCREEN FILTERS 22 31-Aug-23 26-Sep-23 26-Sep-23, AUTOMATIC SCREEN FILTERS


RAM-MS-ACF.100 Material Submission 10 31-Aug-23 11-Sep-23 Material Submission

RAM-MS-ACF.105 Review & Approval 12 12-Sep-23 26-Sep-23 Review & Approval

VERTICAL MULTISTAGE CLOSE COUPLED PUMPS 22 27-Sep-23 22-Oct-23 22-Oct-23, VERTICAL MULTISTAGE CLOSE COUPLED PUMPS
RAM-MS-VMP.100 Material Submission 10 27-Sep-23 08-Oct-23 Material Submission

RAM-MS-VMP.105 Review & Approval 12 09-Oct-23 22-Oct-23 Review & Approval

BEARINGS, EXPANSION JOINTS 22 23-Oct-23 16-Nov-23 16-Nov-23, BEARINGS, EXPANSION JOINTS


RAM-MS-BEJ.110 Material Submission 10 23-Oct-23 02-Nov-23 Material Submission

RAM-MS-BEJ.115 Review & Approval 12 04-Nov-23 16-Nov-23 Review & Approval

GRC PANELS 22 18-Nov-23 12-Dec-23 12-Dec-23, GRC PANELS


RAM-MS-GRCP.120 Material Submission 10 18-Nov-23 28-Nov-23 Material Submission

RAM-MS-GRCP.125 Review & Approval 12 29-Nov-23 12-Dec-23 Review & Approval

EXTRACT FANS 22 13-Dec-23 07-Jan-24 07-Jan-24, EXTRACT FANS


RAM-MS-EF.140 Material Submission 10 13-Dec-23 24-Dec-23 Material Submission

RAM-MS-EF.145 Review & Approval 12 25-Dec-23 07-Jan-24 Review & Approval

FIRE PROTECTION BOARD 22 18-Apr-23 16-May-23 16-May-23, FIRE PROTECTION BOARD


RAM-MS-FPB.130 Material Submission 10 18-Apr-23 02-May-23 Material Submission

RAM-MS-FPB.135 Review & Approval 12 03-May-23 16-May-23 Review & Approval

110 KV HIGH VOLTAGE CABLES 22 02-Mar-23 27-Mar-23 27-Mar-23, 110 KV HIGH VOLTAGE CABLES
RAM-MS-HVC.200 Material Submission 10 02-Mar-23 13-Mar-23 Material Submission

RAM-MS-HVC.205 Review & Approval 12 14-Mar-23 27-Mar-23 Review & Approval

MEDIUM VOLTAGE CABLES 22 15-Oct-22 A 27-Oct-22 A 27-Oct-22 A, MEDIUM VOLTAGE CABLES


RAM-MS-MVC.210 Material Submission 10 15-Oct-22 A 17-Oct-22 A Material Submission

RAM-MS-MVC.215 Review & Approval 12 17-Oct-22 A 27-Oct-22 A Review & Approval

LOW VOLTAGE CABLES 22 09-Oct-22 A 27-Oct-22 A 27-Oct-22 A, LOW VOLTAGE CABLES


RAM-MS-LVC.220 Material Submission 10 09-Oct-22 A 10-Oct-22 A Material Submission

RAM-MS-LVC.225 Review & Approval 12 10-Oct-22 A 27-Oct-22 A Review & Approval

LIGHTING POLES 22 20-Oct-22 A 27-Oct-22 A 27-Oct-22 A, LIGHTING POLES


RAM-MS-LP.230 Material Submission 10 20-Oct-22 A 23-Oct-22 A Material Submission

RAM-MS-LP.235 Review & Approval 12 23-Oct-22 A 27-Oct-22 A Review & Approval

TELECOM CABLES 22 28-Mar-23 25-Apr-23 25-Apr-23, TELECOM CABLES


RAM-MS-TC.240 Material Submission 10 28-Mar-23 08-Apr-23 Material Submission

RAM-MS-TC.245 Review & Approval 12 09-Apr-23 25-Apr-23 Review & Approval

POWER DISTRIBUTION BOARDS 22 12-Jun-23 10-Jul-23 10-Jul-23, POWER DISTRIBUTION BOARDS


RAM-MS-PDB.160 Material Submission 10 12-Jun-23 22-Jun-23 Material Submission

RAM-MS-PDB.165 Review & Approval 12 24-Jun-23 10-Jul-23 Review & Approval

SCADA SYSTEM 22 17-May-23 11-Jun-23 11-Jun-23, SCADA SYSTEM


RAM-MS-SS.150 Material Submission 10 17-May-23 28-May-23 Material Submission

RAM-MS-SS.155 Review & Approval 12 29-May-23 11-Jun-23 Review & Approval

DIESEL GENERATOR 22 12-Jun-23 10-Jul-23 10-Jul-23, DIESEL GENERATOR


RAM-MS-DG.170 Material Submission 10 12-Jun-23 22-Jun-23 Material Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
205 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RAM-MS-DG.175 Review & Approval 12 24-Jun-23 10-Jul-23 Review & Approval

QUALITY ENGINEERING 418 12-Jul-22 A 29-Oct-23 29-Oct-23, QUALITY ENGINEERING


METHOD STATEMENT 152 13-Sep-22 A 29-Oct-23 29-Oct-23, METHOD STATEMENT
JAH-QENG-MOS.100 Excavation & Dewatering Method Statement Preparation & Submission 20 13-Sep-22 A 01-Oct-22 A Excavation & Dewatering Method Statement Preparation & Submission

JAH-QENG-MOS.105 Excavation & Dewatering Method Statement Review & Approval 12 01-Oct-22 A 11-Oct-22 A Excavation & Dewatering Method Statement Review & Approval

JAH-QENG-MOS.110 Tunnel Structural Works Method Statement Preparation & Submission 23 19-Oct-22 A 17-May-23 Tunnel Structural Works Method Statement Preparation & Submission

JAH-QENG-MOS.115 Tunnel Structural Works Method Statement Review & Approval 12 20-Oct-22 A 21-May-23 Tunnel Structural Works Method Statement Review & Approval

JAH-QENG-MOS.120 Concrete Work Method Statement Preparation & Submission 23 22-May-23 17-Jun-23 Concrete Work Method Statement Preparation & Submission

JAH-QENG-MOS.125 Concrete Work Method Statement Review & Approval 12 18-Jun-23 04-Jul-23 Concrete Work Method Statement Review & Approval

JAH-QENG-MOS.130 MEP Works Method Statement Preparation & Submission 20 05-Jul-23 27-Jul-23 MEP Works Method Statement Preparation & Submission

JAH-QENG-MOS.135 MEP Works Method Statement Preparation & Submission 12 29-Jul-23 10-Aug-23 MEP Works Method Statement Preparation & Submission

JAH-QENG-MOS.140 Architectural Decorative Works Method Statement Preparation & Submission 20 19-Sep-23 12-Oct-23 Architectural Decorative Works Method Statement Preparation & Submission

JAH-QENG-MOS.145 Architectural Decorative Works Method Statement Preparation & Submission 14 14-Oct-23 29-Oct-23 Architectural Decorative Works Method Statement Preparation & Submission

CONCRETE MIX DESIGN 148 12-Jul-22 A 31-Dec-22 31-Dec-22, CONCRETE MIX DESIGN
CLASS 20/20 50 12-Jul-22 A 04-Oct-22 A 04-Oct-22 A, CLASS 20/20
CMD-20/20-CL.100 Concrete Mix Design Preparation & Submission 5 12-Jul-22 A 11-Sep-22 A Concrete Mix Design Preparation & Submission

CMD-20/20-CL.105 Concrete Mix Design Review & Approval 12 18-Jul-22 A 15-Sep-22 A Concrete Mix Design Review & Approval

CMD-20/20-CL.110 Sample Preparation, Curing and Submission 21 01-Aug-22 A 26-Sep-22 A Sample Preparation, Curing and Submission

CMD-20/20-CL.115 Sample Strength Testing & Approval 12 25-Aug-22 A 04-Oct-22 A Sample Strength Testing & Approval

CLASS 25/20 116 18-Jul-22 A 29-Nov-22 29-Nov-22, CLASS 25/20


CMD-25/20-CL.100 Concrete Mix Design Preparation & Submission 5 18-Jul-22 A 13-Oct-22 A Concrete Mix Design Preparation & Submission

CMD-25/20-CL.105 Concrete Mix Design Review & Approval 12 24-Jul-22 A 18-Oct-22 A Concrete Mix Design Review & Approval

CMD-25/20-CL.110 Sample Preparation, Curing and Submission 21 29-Oct-22 21-Nov-22 Sample Preparation, Curing and Submission

CMD-25/20-CL.115 Sample Strength Testing & Approval 7 22-Nov-22 29-Nov-22 Sample Strength Testing & Approval

CLASS 50/20 55 29-Oct-22 31-Dec-22 31-Dec-22, CLASS 50/20


CMD-50/20-CL.100 Concrete Mix Design Preparation & Submission 10 29-Oct-22 08-Nov-22 Concrete Mix Design Preparation & Submission

CMD-50/20-CL.105 Concrete Mix Design Review & Approval 12 09-Nov-22 22-Nov-22 Concrete Mix Design Review & Approval

CMD-50/20-CL.110 Sample Preparation, Curing and Submission 21 23-Nov-22 17-Dec-22 Sample Preparation, Curing and Submission

CMD-50/20-CL.115 Sample Strength Testing & Approval 12 18-Dec-22 31-Dec-22 Sample Strength Testing & Approval

CLASS 40/20 104 18-Aug-22 A 17-Dec-22 17-Dec-22, CLASS 40/20


CMD-40/20-CL.100 Concrete Mix Design Preparation & Submission 10 18-Aug-22 A 13-Oct-22 A Concrete Mix Design Preparation & Submission

CMD-40/20-CL.105 Concrete Mix Design Review & Approval 12 30-Aug-22 A 18-Oct-22 A Concrete Mix Design Review & Approval

CMD-40/20-CL.110 Sample Preparation, Curing and Submission 21 09-Nov-22 03-Dec-22 Sample Preparation, Curing and Submission

CMD-40/20-CL.115 Sample Strength Testing & Approval 12 04-Dec-22 17-Dec-22 Sample Strength Testing & Approval

TUNNEL CONSTRUCTION 1238 07-Jun-22 A 18-Jul-26 18-Jul-26, TUNNEL CONSTRUCTION


JADAT AL HARAM TUNNEL 1121 07-Jun-22 A 23-Feb-26 23-Feb-26, JADAT AL HARAM TUNNEL
ZONE 1 - FROM STA. 0+000 ~ 0+500 809 07-Jun-22 A 06-Jan-26 06-Jan-26, ZONE 1 - FROM STA. 0+000 ~ 0+500
ENGINEERING 416 07-Jun-22 A 24-Sep-24 24-Sep-24, ENGINEERING
RAM100 Completion Engineering Work for Zone 1 0 24-Sep-24* Completion Engineering Work for Zone 1

SITE SURVEY 15 07-Jun-22 A 16-Jun-22 A 16-Jun-22 A, SITE SURVEY


JAH-Z1-EN-SS.100 Site Survey/Settingout Control Points 3 07-Jun-22 A 11-Jun-22 A Site Survey/Settingout Control Points

JAH-Z1-EN-SS.105 Review and Approval of Site Survey & Control Points 12 12-Jun-22 A 16-Jun-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 106 15-May-23 18-Sep-23 18-Sep-23, SHOP DRAWINGS


CIVIL/STRUCTURAL 0+133 ~0+233 60 15-May-23 26-Jul-23 26-Jul-23, CIVIL/STRUCTURAL 0+133 ~0+233
JAH-Z1-ENG-CS.100 Plan and Profile Shop Drawings Preparation & Submission 6 15-May-23 21-May-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.105 Plan and Profile Shop Drawings Review & Approval 12 22-May-23 04-Jun-23 Plan and Profile Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
206 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ENG-CS.110 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 05-Jun-23 11-Jun-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.115 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 12-Jun-23 25-Jun-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z1-ENG-CS.120 Tunnel Structural Shop Drawings Submission 6 12-Jun-23 18-Jun-23 Tunnel Structural Shop Drawings Submission

JAH-Z1-ENG-CS.125 Tunnel Structural Shop Drawings Review & Approval 12 19-Jun-23 05-Jul-23 Tunnel Structural Shop Drawings Review & Approval

JAH-Z1-ENG-CS.130 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 19-Jun-23 25-Jun-23 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.135 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 26-Jun-23 12-Jul-23 Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z1-ENG-CS.140 Embedded Items Shop Drawings Preparation & Submission 6 26-Jun-23 05-Jul-23 Embedded Items Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.145 Embedded Items Shop Drawings Review & Approval 12 13-Jul-23 26-Jul-23 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+233 ~0+333 54 05-Jun-23 09-Aug-23 09-Aug-23, CIVIL/STRUCTURAL 0+233 ~0+333


JAH-Z1-ENG-CS.150 Plan and Profile Shop Drawings Preparation & Submission 6 05-Jun-23 11-Jun-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.155 Plan and Profile Shop Drawings Review & Approval 12 12-Jun-23 25-Jun-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z1-ENG-CS.160 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 26-Jun-23 05-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.165 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 06-Jul-23 19-Jul-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z1-ENG-CS.170 Tunnel Structural Shop Drawings Submission 6 06-Jul-23 12-Jul-23 Tunnel Structural Shop Drawings Submission

JAH-Z1-ENG-CS.175 Tunnel Structural Shop Drawings Review & Approval 12 13-Jul-23 26-Jul-23 Tunnel Structural Shop Drawings Review & Approval

JAH-Z1-ENG-CS.180 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 13-Jul-23 19-Jul-23 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.185 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 20-Jul-23 02-Aug-23 Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z1-ENG-CS.190 Embedded Items Shop Drawings Preparation & Submission 6 20-Jul-23 26-Jul-23 Embedded Items Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.195 Embedded Items Shop Drawings Review & Approval 12 27-Jul-23 09-Aug-23 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+333 ~0+433 54 26-Jun-23 30-Aug-23 30-Aug-23, CIVIL/STRUCTURAL 0+333 ~0+433


JAH-Z1-ENG-CS.200 Plan and Profile Shop Drawings Preparation & Submission 6 26-Jun-23 05-Jul-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.205 Plan and Profile Shop Drawings Review & Approval 12 06-Jul-23 19-Jul-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z1-ENG-CS.210 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 20-Jul-23 26-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.215 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 27-Jul-23 09-Aug-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z1-ENG-CS.220 Tunnel Structural Shop Drawings Submission 6 27-Jul-23 02-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z1-ENG-CS.225 Tunnel Structural Shop Drawings Review & Approval 12 03-Aug-23 16-Aug-23 Tunnel Structural Shop Drawings Review & Approval

JAH-Z1-ENG-CS.230 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 03-Aug-23 09-Aug-23 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.235 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 10-Aug-23 23-Aug-23 Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z1-ENG-CS.240 Embedded Items Shop Drawings Preparation & Submission 6 10-Aug-23 16-Aug-23 Embedded Items Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.245 Embedded Items Shop Drawings Review & Approval 12 17-Aug-23 30-Aug-23 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+433 ~0+500 48 20-Jul-23 13-Sep-23 13-Sep-23, CIVIL/STRUCTURAL 0+433 ~0+500


JAH-Z1-ENG-CS.250 Plan and Profile Shop Drawings Preparation & Submission 6 20-Jul-23 26-Jul-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.255 Plan and Profile Shop Drawings Review & Approval 12 27-Jul-23 09-Aug-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z1-ENG-CS.260 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 10-Aug-23 16-Aug-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.265 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 17-Aug-23 30-Aug-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z1-ENG-CS.270 Tunnel Structural Shop Drawings Submission 6 17-Aug-23 23-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z1-ENG-CS.275 Tunnel Structural Shop Drawings Review & Approval 12 24-Aug-23 06-Sep-23 Tunnel Structural Shop Drawings Review & Approval

JAH-Z1-ENG-CS.280 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 24-Aug-23 30-Aug-23 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z1-ENG-CS.285 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 31-Aug-23 13-Sep-23 Dry & Wet Utility Culvert Shop Drawings Review & Approval

ARCHITECTURAL 22 24-Aug-23 18-Sep-23 18-Sep-23, ARCHITECTURAL


JAH-Z1-ENG-AR.100 Tunnel Architectural Shop Drawings Preparation & Submission 10 24-Aug-23 04-Sep-23 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z1-ENG-AR.105 Tunnel Architectural Shop Drawings Review & Approval 12 05-Sep-23 18-Sep-23 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 362 20-Jul-23 24-Sep-24 24-Sep-24, UTILITIES


WET UTILITIES 160 20-Jul-23 23-Jan-24 23-Jan-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 32 20-Jul-23 26-Aug-23 26-Aug-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
207 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-WU-EN-PW.110Shop Drawings Preparation & Submission 20 20-Jul-23 12-Aug-23 Shop Drawings Preparation & Submission

JAH-Z1-WU-EN-PW.115Shop Drawings Review & Approval 12 13-Aug-23 26-Aug-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 32 27-Aug-23 03-Oct-23 03-Oct-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z1-WU-EN-GWD.110
Shop Drawings Preparation & Submission 20 27-Aug-23 18-Sep-23 Shop Drawings Preparation & Submission

JAH-Z1-WU-EN-GWD.115
Shop Drawings Review & Approval 12 19-Sep-23 03-Oct-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 32 04-Oct-23 09-Nov-23 09-Nov-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z1-WU-EN-IRR.110
Shop Drawings Preparation & Submission 20 04-Oct-23 26-Oct-23 Shop Drawings Preparation & Submission

JAH-Z1-WU-EN-IRR.115
Shop Drawings Review & Approval 12 28-Oct-23 09-Nov-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 32 11-Nov-23 17-Dec-23 17-Dec-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z1-WU-EN-CWS.110
Shop Drawings Preparation & Submission 20 11-Nov-23 03-Dec-23 Shop Drawings Preparation & Submission

JAH-Z1-WU-EN-CWS.115
Shop Drawings Review & Approval 12 04-Dec-23 17-Dec-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 32 18-Dec-23 23-Jan-24 23-Jan-24, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z1-WU-EN-AUW.120
Shop Drawings Preparation & Submission 20 18-Dec-23 09-Jan-24 Shop Drawings Preparation & Submission

JAH-Z1-WU-EN-AUW.125
Shop Drawings Review & Approval 12 10-Jan-24 23-Jan-24 Shop Drawings Review & Approval

DRY UTILITIES 202 24-Jan-24 24-Sep-24 24-Sep-24, DRY UTILITIES


POWER 170 24-Jan-24 17-Aug-24 17-Aug-24, POWER
HIGH VOLTAGE 110 KV NETWORK 32 24-Jan-24 29-Feb-24 29-Feb-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z1-DU-EN-PWR.140
Shop Drawings Preparation & Submission 20 24-Jan-24 15-Feb-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-PWR.145
Shop Drawings Review & Approval 12 17-Feb-24 29-Feb-24 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 32 13-Mar-24 22-Apr-24 22-Apr-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z1-DU-EN-PWR.150
Shop Drawings Preparation & Submission 20 13-Mar-24 04-Apr-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-PWR.155
Shop Drawings Review & Approval 12 06-Apr-24 22-Apr-24 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 32 23-Apr-24 29-May-24 29-May-24, LOW VOLTAGE NETWORK


JAH-Z1-DU-EN-PWR.160
Shop Drawings Preparation & Submission 20 23-Apr-24 15-May-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-PWR.165
Shop Drawings Review & Approval 12 16-May-24 29-May-24 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 32 30-May-24 10-Jul-24 10-Jul-24, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z1-DU-EN-PWR.170
Shop Drawings Preparation & Submission 20 30-May-24 26-Jun-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-PWR.175
Shop Drawings Review & Approval 12 27-Jun-24 10-Jul-24 Shop Drawings Review & Approval

LIGHTING SYSTEM 32 11-Jul-24 17-Aug-24 17-Aug-24, LIGHTING SYSTEM


JAH-Z1-DU-EN-PWR.180
Shop Drawings Preparation & Submission 20 11-Jul-24 03-Aug-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-PWR.185
Shop Drawings Review & Approval 12 04-Aug-24 17-Aug-24 Shop Drawings Review & Approval

LOW CURRENT 32 18-Aug-24 24-Sep-24 24-Sep-24, LOW CURRENT


TELECOM SERVICES 32 18-Aug-24 24-Sep-24 24-Sep-24, TELECOM SERVICES
JAH-Z1-DU-EN-LC.130Shop Drawings Preparation & Submission 20 18-Aug-24 09-Sep-24 Shop Drawings Preparation & Submission

JAH-Z1-DU-EN-LC.135Shop Drawings Review & Approval 12 10-Sep-24 24-Sep-24 Shop Drawings Review & Approval

MEP 152 03-Aug-23 28-Jan-24 28-Jan-24, MEP


TUNNEL MECHANICAL WORKS 98 03-Aug-23 26-Nov-23 26-Nov-23, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 03-Aug-23 14-Nov-23 14-Nov-23, FIRE FIGHTING SYSTEM
JAH-Z1-ENG-FF.100 Fire Fighting Pipe Layout Plan Preparation & Submission 10 03-Aug-23 14-Aug-23 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z1-ENG-FF.105 Fire Fighting Pipe Layout Plan Review & Approval 12 15-Aug-23 28-Aug-23 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z1-ENG-FF.110 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 29-Aug-23 09-Sep-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z1-ENG-FF.115 Fire Fighting Sprinkler Layout Plan Review & Approval 12 10-Sep-23 24-Sep-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z1-ENG-FF.120 Foam Tank Installation Layout Preparation & Submission 10 25-Sep-23 05-Oct-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z1-ENG-FF.125 Foam Tank Installation Layout Review & Approval 12 07-Oct-23 19-Oct-23 Foam Tank Installation Layout Review & Approval

JAH-Z1-ENG-FF.130 Fire Extinguishers Layout Plan Preparation & Submission 10 21-Oct-23 31-Oct-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z1-ENG-FF.135 Fire Extinguishers Layout Plan Review & Approval 12 01-Nov-23 14-Nov-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 29-Aug-23 19-Oct-23 19-Oct-23, VENTILATION SYSTEM


JAH-Z1-ENG-VS.100 Fan Layout Preparation & Submission 10 29-Aug-23 09-Sep-23 Fan Layout Preparation & Submission

JAH-Z1-ENG-VS.105 Fan Layout Review & Approval 12 10-Sep-23 24-Sep-23 Fan Layout Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
208 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ENG-VS.110 Cable Route Shop Drawing Preparation & Submission 10 25-Sep-23 05-Oct-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z1-ENG-VS.115 Cable Route Shop Drawing Review & Approval 12 07-Oct-23 19-Oct-23 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 21-Oct-23 14-Nov-23 14-Nov-23, PUMPS INSTALLATION


JAH-Z1-ENG-PI.100 Sump Pump Diagram Preparation & Submission 10 21-Oct-23 31-Oct-23 Sump Pump Diagram Preparation & Submission

JAH-Z1-ENG-PI.105 Sump Pump Diagram Review & Approval 12 01-Nov-23 14-Nov-23 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 15-Aug-23 26-Nov-23 26-Nov-23, DUCTING SYSTEM


JAH-Z1-ENG-DCS.100 Duct Layout Drawing Preparation & Submission 10 15-Aug-23 26-Aug-23 Duct Layout Drawing Preparation & Submission

JAH-Z1-ENG-DCS.105 Duct Layout Drawing Review & Approval 12 27-Aug-23 09-Sep-23 Duct Layout Drawing Review & Approval

JAH-Z1-ENG-DCS.110 Diffuser Details Drawing Preparation & Submission 10 10-Sep-23 20-Sep-23 Diffuser Details Drawing Preparation & Submission

JAH-Z1-ENG-DCS.115 Diffuser Details Review & Approval 12 21-Sep-23 05-Oct-23 Diffuser Details Review & Approval

JAH-Z1-ENG-DCS.120 Dampers Details Preparation & Submission 10 07-Oct-23 17-Oct-23 Dampers Details Preparation & Submission

JAH-Z1-ENG-DCS.125 Dampers Details Review & Approval 12 18-Oct-23 31-Oct-23 Dampers Details Review & Approval

JAH-Z1-ENG-DCS.130 Sand Trap Louvre Layout Drawing Preparation & Submission 10 01-Nov-23 12-Nov-23 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z1-ENG-DCS.135 Sand Trap Louvre Layout Drawing Review & Approval 12 13-Nov-23 26-Nov-23 Sand Trap Louvre Layout Drawing Review & Approval

TUNNEL ELECTRICAL WORKS 142 15-Aug-23 28-Jan-24 28-Jan-24, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 27-Aug-23 02-Jan-24 02-Jan-24, CABLE TRAYS
JAH-Z1-ENG-CTR.100 Cable Tray Layout Drawing Preparation & Submission 10 27-Aug-23 06-Sep-23 Cable Tray Layout Drawing Preparation & Submission

JAH-Z1-ENG-CTR.105 Cable Tray Layout Drawing Review & Approval 12 07-Sep-23 20-Sep-23 Cable Tray Layout Drawing Review & Approval

JAH-Z1-ENG-CTR.110 Cable Tray Diversion Details Preparation & Submission 10 21-Sep-23 03-Oct-23 Cable Tray Diversion Details Preparation & Submission

JAH-Z1-ENG-CTR.115 Cable Tray Diversion Details Review & Approval 12 04-Oct-23 17-Oct-23 Cable Tray Diversion Details Review & Approval

JAH-Z1-ENG-CTR.120 Cable Tray Fixing Details Preparation & Submission 10 18-Oct-23 29-Oct-23 Cable Tray Fixing Details Preparation & Submission

JAH-Z1-ENG-CTR.125 Cable Tray Fixing Details Review & Submission 12 30-Oct-23 12-Nov-23 Cable Tray Fixing Details Review & Submission

JAH-Z1-ENG-CTR.130 Cable Tray Sections Preparation & Submission 10 13-Nov-23 23-Nov-23 Cable Tray Sections Preparation & Submission

JAH-Z1-ENG-CTR.135 Cable Tray Sections Review & Approval 12 25-Nov-23 07-Dec-23 Cable Tray Sections Review & Approval

JAH-Z1-ENG-CTR.140 PVC DuctsSections Preparation & Submission 10 09-Dec-23 19-Dec-23 PVC DuctsSections Preparation & Submission

JAH-Z1-ENG-CTR.145 PVC Sections Review & Approval 12 20-Dec-23 02-Jan-24 PVC Sections Review & Approval

POWER CABLES 44 07-Sep-23 29-Oct-23 29-Oct-23, POWER CABLES


JAH-Z1-ENG-PC.100 Cable Route Shop Drawing Preparation & Submission 10 07-Sep-23 18-Sep-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z1-ENG-PC.105 Cable Route Shop Drawing Review & Approval 12 19-Sep-23 03-Oct-23 Cable Route Shop Drawing Review & Approval

JAH-Z1-ENG-PC.110 Junction Box Layout Plan Preparation & Submission 10 04-Oct-23 15-Oct-23 Junction Box Layout Plan Preparation & Submission

JAH-Z1-ENG-PC.115 Junction Box Layout Plan Review & Approval 12 16-Oct-23 29-Oct-23 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 15-Aug-23 21-Dec-23 21-Dec-23, ELECTRICAL INSTALLATIONS


JAH-Z1-ENG-ELI.100 Wiring Accessories Diagram Preparation & Submission 10 15-Aug-23 26-Aug-23 Wiring Accessories Diagram Preparation & Submission

JAH-Z1-ENG-ELI.105 Wiring Accessories Diagram Review & Approval 12 27-Aug-23 09-Sep-23 Wiring Accessories Diagram Review & Approval

JAH-Z1-ENG-ELI.110 Lighting Layout Drawing Preparation & Submission 10 10-Sep-23 20-Sep-23 Lighting Layout Drawing Preparation & Submission

JAH-Z1-ENG-ELI.115 Lighting Layout Drawing Review & Approval 12 21-Sep-23 05-Oct-23 Lighting Layout Drawing Review & Approval

JAH-Z1-ENG-ELI.120 Circuit Wiring Diagram Preparation & Submission 10 07-Oct-23 17-Oct-23 Circuit Wiring Diagram Preparation & Submission

JAH-Z1-ENG-ELI.125 Circuit Wiring Diagram Review & Approval 12 18-Oct-23 31-Oct-23 Circuit Wiring Diagram Review & Approval

JAH-Z1-ENG-ELI.130 SMDB Line Diagram Preparation & Submission 10 01-Nov-23 12-Nov-23 SMDB Line Diagram Preparation & Submission

JAH-Z1-ENG-ELI.135 SMDB Line Diagram Review & Approval 12 13-Nov-23 26-Nov-23 SMDB Line Diagram Review & Approval

JAH-Z1-ENG-ELI.140 Distribution Board Line Diagram Preparation & Submission 10 27-Nov-23 07-Dec-23 Distribution Board Line Diagram Preparation & Submission

JAH-Z1-ENG-ELI.145 Distribution Board Line Diagram Review & Approval 12 09-Dec-23 21-Dec-23 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 27-Aug-23 28-Jan-24 28-Jan-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 27-Aug-23 28-Jan-24 28-Jan-24, FIRE DETECTION AND ALARM SYSTEM
JAH-Z1-ENG-FD.100 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 27-Aug-23 06-Sep-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
209 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ENG-FD.105 Fire Alarm Control Panel Layout Drawing Review & Approval 12 07-Sep-23 20-Sep-23 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z1-ENG-FD.110 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 21-Sep-23 03-Oct-23 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z1-ENG-FD.115 Fire Alarm Speaker Layout Drawing Review & Approval 12 04-Oct-23 17-Oct-23 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z1-ENG-FD.120 Fire Alarm sounder Layout Drawing Preparation & Submission 10 18-Oct-23 29-Oct-23 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z1-ENG-FD.125 Fire Alarm sounder Layout Drawing Review & Approval 12 30-Oct-23 12-Nov-23 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z1-ENG-FD.130 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 13-Nov-23 23-Nov-23 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z1-ENG-FD.135 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 25-Nov-23 07-Dec-23 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z1-ENG-FD.140 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 09-Dec-23 19-Dec-23 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-FD.145 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 20-Dec-23 02-Jan-24 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z1-ENG-FD.150 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 03-Jan-24 14-Jan-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z1-ENG-FD.155 Double Action Manual Call Point Layout Drawing Preparation & Submission 12 15-Jan-24 28-Jan-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 07-Sep-23 14-Jan-24 14-Jan-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z1-ENG-TPH.1008 core UTP Cable Laying 10 07-Sep-23 18-Sep-23 8 core UTP Cable Laying

JAH-Z1-ENG-TPH.105Junction box Installation 12 19-Sep-23 03-Oct-23 Junction box Installation

JAH-Z1-ENG-TPH.110Emergency Telephone Installation 14 04-Oct-23 19-Oct-23 Emergency Telephone Installation

JAH-Z1-ENG-TPH.115Connection and Testing 8 21-Oct-23 29-Oct-23 Connection and Testing

JAH-Z1-ENG-TPH.1208 Core UTP Cable Layout Drawing Preparation & Submission 10 30-Oct-23 09-Nov-23 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-TPH.1258 Core UTP Cable Layout Drawing Review & Approval 12 11-Nov-23 23-Nov-23 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z1-ENG-TPH.130Junction box Layout Drawing Preparation & Submission 10 25-Nov-23 05-Dec-23 Junction box Layout Drawing Preparation & Submission

JAH-Z1-ENG-TPH.135Junction box Layout Drawing Review & Approval 12 06-Dec-23 19-Dec-23 Junction box Layout Drawing Review & Approval

JAH-Z1-ENG-TPH.140Telephone Location Layout Preparation & Submission 10 20-Dec-23 31-Dec-23 Telephone Location Layout Preparation & Submission

JAH-Z1-ENG-TPH.145Telephone Location Layout Review & Approval 12 01-Jan-24 14-Jan-24 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 19-Sep-23 05-Dec-23 05-Dec-23, PUBLIC ADDRESS


JAH-Z1-ENG-PUBA.100
Cable Layout Drawing Preparation & Submission 10 19-Sep-23 01-Oct-23 Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-PUBA.105
Cable Layout Drawing Review & Approval 12 02-Oct-23 15-Oct-23 Cable Layout Drawing Review & Approval

JAH-Z1-ENG-PUBA.110
Voice alarm control panel Drawing Preparation & Submission 10 16-Oct-23 26-Oct-23 Voice alarm control panel Drawing Preparation & Submission

JAH-Z1-ENG-PUBA.115
Voice alarm control panel Drawing Review & Approval 12 28-Oct-23 09-Nov-23 Voice alarm control panel Drawing Review & Approval

JAH-Z1-ENG-PUBA.120
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 11-Nov-23 21-Nov-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z1-ENG-PUBA.125
Voice Evacuation Horn Speaker Drawing Review & Approval 12 22-Nov-23 05-Dec-23 Voice Evacuation Horn Speaker Drawing Review & Approval

VIDEO SURVEILLANCE 44 02-Oct-23 21-Nov-23 21-Nov-23, VIDEO SURVEILLANCE


JAH-Z1-ENG-VID.100Cable Layout Drawing Preparation & Submission 10 02-Oct-23 12-Oct-23 Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-VID.105Cable Layout Drawing Review & Approval 12 14-Oct-23 26-Oct-23 Cable Layout Drawing Review & Approval

JAH-Z1-ENG-VID.110Camera Layout Drawing Preparation & Submission 10 28-Oct-23 07-Nov-23 Camera Layout Drawing Preparation & Submission

JAH-Z1-ENG-VID.115Camera Layout Drawing Review & Approval 12 08-Nov-23 21-Nov-23 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 14-Oct-23 03-Dec-23 03-Dec-23, SACADA SYSTEM


JAH-Z1-ENG-SCA.100Cable Layout Drawing Preparation & Submission 10 14-Oct-23 24-Oct-23 Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-SCA.105Cable Layout Drawing Review & Approval 12 25-Oct-23 07-Nov-23 Cable Layout Drawing Review & Approval

JAH-Z1-ENG-SCA.110Installation Layout Drawing Preparation & Submission 10 08-Nov-23 19-Nov-23 Installation Layout Drawing Preparation & Submission

JAH-Z1-ENG-SCA.115Installation Layout Drawing Review & Approval 12 20-Nov-23 03-Dec-23 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 25-Oct-23 14-Dec-23 14-Dec-23, RADIO RE-BROADCASTING SYSTEM


JAH-Z1-ENG-RDO.100Cable Layout Drawing Preparation & Submission 10 25-Oct-23 05-Nov-23 Cable Layout Drawing Preparation & Submission

JAH-Z1-ENG-RDO.105Cable Layout Drawing Review & Approval 12 06-Nov-23 19-Nov-23 Cable Layout Drawing Review & Approval

JAH-Z1-ENG-RDO.110Installation Layout Drawing Preparation & Submission 10 20-Nov-23 30-Nov-23 Installation Layout Drawing Preparation & Submission

JAH-Z1-ENG-RDO.115Installation Layout Drawing Review & Approval 12 02-Dec-23 14-Dec-23 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 16-Dec-23 08-Jan-24 08-Jan-24, TUNNEL PLUMBING WORKS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
210 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ENG-PLM.100 Plumbing Services Shop Drawings Preparation & Submission 9 16-Dec-23 25-Dec-23 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z1-ENG-PLM.105 Plumbing Shop Drawings Review & Approval 12 26-Dec-23 08-Jan-24 Plumbing Shop Drawings Review & Approval

PROCUREMENT 519 06-Jul-23 12-Mar-25 12-Mar-25, PROCUREMENT


RAM105 Completion Procurment Work for Zone 1 0 12-Mar-25* Completion Procurment Work for Zone 1

CIVIL/STRUCTURAL 145 06-Jul-23 23-Dec-23 23-Dec-23, CIVIL/STRUCTURAL


JAH-Z1-PRO-CSM.100 Request for Quotation 10 06-Jul-23 17-Jul-23 Request for Quotation

JAH-Z1-PRO-CSM.105 Issue Purchase Order 15 18-Jul-23 03-Aug-23 Issue Purchase Order

JAH-Z1-PRO-CSM.110 Staging Time 30 05-Aug-23 07-Sep-23 Staging Time

JAH-Z1-PRO-CSM.115 Material Delivery 90 09-Sep-23 23-Dec-23 Material Delivery

UTILITIES 475 27-Aug-23 12-Mar-25 12-Mar-25, UTILITIES


WET UTILITIES 273 27-Aug-23 18-Jul-24 18-Jul-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 145 27-Aug-23 12-Feb-24 12-Feb-24, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 27-Aug-23 12-Feb-24 12-Feb-24, DI PIPES
JAH-Z1-WU-PR-PW.220
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.225
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.230
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.235
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

HDPE PIPES 145 27-Aug-23 12-Feb-24 12-Feb-24, HDPE PIPES


JAH-Z1-WU-PR-PW.240
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.245
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.250
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.255
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

GRP PIPES 145 27-Aug-23 12-Feb-24 12-Feb-24, GRP PIPES


JAH-Z1-WU-PR-PW.260
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.265
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.270
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.275
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

DI & GRP FITTING 145 27-Aug-23 12-Feb-24 12-Feb-24, DI & GRP FITTING
JAH-Z1-WU-PR-PW.100
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.105
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.110
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.115
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

GATE VALVE 145 27-Aug-23 12-Feb-24 12-Feb-24, GATE VALVE


JAH-Z1-WU-PR-PW.120
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.125
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.130
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.135
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

BUTTERFLAY VALVE 145 27-Aug-23 12-Feb-24 12-Feb-24, BUTTERFLAY VALVE


JAH-Z1-WU-PR-PW.140
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.145
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.150
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.155
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

WATER METER 145 27-Aug-23 12-Feb-24 12-Feb-24, WATER METER


JAH-Z1-WU-PR-PW.160
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.165
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.170
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.175
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
211 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AIR RELASE VALVE 145 27-Aug-23 12-Feb-24 12-Feb-24, AIR RELASE VALVE
JAH-Z1-WU-PR-PW.180
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.185
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.190
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.195
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

WASHOUT VALVE 145 27-Aug-23 12-Feb-24 12-Feb-24, WASHOUT VALVE


JAH-Z1-WU-PR-PW.200
Request for Quotation 10 27-Aug-23 06-Sep-23 Request for Quotation

JAH-Z1-WU-PR-PW.205
Issue Purchase Order 15 07-Sep-23 25-Sep-23 Issue Purchase Order

JAH-Z1-WU-PR-PW.210
Staging time 30 26-Sep-23 30-Oct-23 Staging time

JAH-Z1-WU-PR-PW.215
Material Delivery 90 31-Oct-23 12-Feb-24 Material Delivery

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 145 04-Oct-23 20-Mar-24 20-Mar-24, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 04-Oct-23 20-Mar-24 20-Mar-24, DI PIPES
JAH-Z1-WU-PR-GWD.098
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.100
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.105
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.110
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

HDPE PIPES 145 04-Oct-23 20-Mar-24 20-Mar-24, HDPE PIPES


JAH-Z1-WU-PR-GWD.113
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.115
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.120
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.125
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

GRP PIPES 145 04-Oct-23 20-Mar-24 20-Mar-24, GRP PIPES


JAH-Z1-WU-PR-GWD.127
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.130
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.135
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.140
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

DI & GRP FITTING 145 04-Oct-23 20-Mar-24 20-Mar-24, DI & GRP FITTING
JAH-Z1-WU-PR-GWD.143
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.145
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.150
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.155
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

GATE VALVE 145 04-Oct-23 20-Mar-24 20-Mar-24, GATE VALVE


JAH-Z1-WU-PR-GWD.158
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.160
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.165
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.170
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

BUTTERFLAY VALVE 145 04-Oct-23 20-Mar-24 20-Mar-24, BUTTERFLAY VALVE


JAH-Z1-WU-PR-GWD.172
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.175
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.180
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.185
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

AIR RELASE VALVE 145 04-Oct-23 20-Mar-24 20-Mar-24, AIR RELASE VALVE
JAH-Z1-WU-PR-GWD.187
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.190
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.195
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.200
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
212 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WASEHOUT VALVE 145 04-Oct-23 20-Mar-24 20-Mar-24, WASEHOUT VALVE
JAH-Z1-WU-PR-GWD.203
Request for Quotation 10 04-Oct-23 15-Oct-23 Request for Quotation

JAH-Z1-WU-PR-GWD.205
Issue Purchase Order 15 16-Oct-23 01-Nov-23 Issue Purchase Order

JAH-Z1-WU-PR-GWD.210
Staging time 30 02-Nov-23 06-Dec-23 Staging time

JAH-Z1-WU-PR-GWD.215
Material Delivery 90 07-Dec-23 20-Mar-24 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 145 11-Nov-23 30-Apr-24 30-Apr-24, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 11-Nov-23 30-Apr-24 30-Apr-24, HDPE PIPES
JAH-Z1-WU-PR-IRR.098
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.100
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.105
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.110
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

GATE VALVE 145 11-Nov-23 30-Apr-24 30-Apr-24, GATE VALVE


JAH-Z1-WU-PR-IRR.113
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.115
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.120
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.125
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

BUTTERFLAY VALVE 145 11-Nov-23 30-Apr-24 30-Apr-24, BUTTERFLAY VALVE


JAH-Z1-WU-PR-IRR.127
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.130
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.135
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.140
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

AIR RELASE VALVE 145 11-Nov-23 30-Apr-24 30-Apr-24, AIR RELASE VALVE
JAH-Z1-WU-PR-IRR.143
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.145
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.150
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.155
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

WASEHOUT VALVE 145 11-Nov-23 30-Apr-24 30-Apr-24, WASEHOUT VALVE


JAH-Z1-WU-PR-IRR.158
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.160
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.165
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.170
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

FIRE HYDRANT 145 11-Nov-23 30-Apr-24 30-Apr-24, FIRE HYDRANT


JAH-Z1-WU-PR-IRR.173
Request for Quotation 10 11-Nov-23 21-Nov-23 Request for Quotation

JAH-Z1-WU-PR-IRR.175
Issue Purchase Order 15 22-Nov-23 09-Dec-23 Issue Purchase Order

JAH-Z1-WU-PR-IRR.180
Staging time 30 10-Dec-23 13-Jan-24 Staging time

JAH-Z1-WU-PR-IRR.185
Material Delivery 90 14-Jan-24 30-Apr-24 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 145 18-Dec-23 06-Jun-24 06-Jun-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 18-Dec-23 06-Jun-24 06-Jun-24, MILD STEEL PIPE
JAH-Z1-WU-PR-CWS.098
Request for Quotation 10 18-Dec-23 28-Dec-23 Request for Quotation

JAH-Z1-WU-PR-CWS.100
Issue Purchase Order 15 30-Dec-23 15-Jan-24 Issue Purchase Order

JAH-Z1-WU-PR-CWS.105
Staging time 30 16-Jan-24 19-Feb-24 Staging time

JAH-Z1-WU-PR-CWS.110
Material Delivery 90 20-Feb-24 06-Jun-24 Material Delivery

MILD STEEL FITTING 145 18-Dec-23 06-Jun-24 06-Jun-24, MILD STEEL FITTING
JAH-Z1-WU-PR-CWS.113
Request for Quotation 10 18-Dec-23 28-Dec-23 Request for Quotation

JAH-Z1-WU-PR-CWS.115
Issue Purchase Order 15 30-Dec-23 15-Jan-24 Issue Purchase Order

JAH-Z1-WU-PR-CWS.120
Staging time 30 16-Jan-24 19-Feb-24 Staging time

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
213 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-WU-PR-CWS.125
Material Delivery 90 20-Feb-24 06-Jun-24 Material Delivery

GATE VALVE 145 18-Dec-23 06-Jun-24 06-Jun-24, GATE VALVE


JAH-Z1-WU-PR-CWS.128
Request for Quotation 10 18-Dec-23 28-Dec-23 Request for Quotation

JAH-Z1-WU-PR-CWS.130
Issue Purchase Order 15 30-Dec-23 15-Jan-24 Issue Purchase Order

JAH-Z1-WU-PR-CWS.135
Staging time 30 16-Jan-24 19-Feb-24 Staging time

JAH-Z1-WU-PR-CWS.140
Material Delivery 90 20-Feb-24 06-Jun-24 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 24-Jan-24 18-Jul-24 18-Jul-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 24-Jan-24 18-Jul-24 18-Jul-24, AUTOMATIC WASTE
EU-Z1-WU-PR-CWS.218
Request for Quotation 10 24-Jan-24 04-Feb-24 Request for Quotation

EU-Z1-WU-PR-CWS.220
Issue Purchase Order 15 05-Feb-24 21-Feb-24 Issue Purchase Order

EU-Z1-WU-PR-CWS.225
Staging time 30 22-Feb-24 27-Mar-24 Staging time

EU-Z1-WU-PR-CWS.230
Material Delivery 90 28-Mar-24 18-Jul-24 Material Delivery

DRY UTILITIES 315 02-Mar-24 12-Mar-25 12-Mar-25, DRY UTILITIES


POWER 283 02-Mar-24 03-Feb-25 03-Feb-25, POWER
HIGH VOLTAGE 110 KV NETWORK 145 02-Mar-24 25-Aug-24 25-Aug-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z1-DU-PR-PWR.160
Request for Quotation 10 02-Mar-24 12-Mar-24 Request for Quotation

JAH-Z1-DU-PR-PWR.165
Issue Purchase Order 15 13-Mar-24 30-Mar-24 Issue Purchase Order

JAH-Z1-DU-PR-PWR.168
Staging time 30 31-Mar-24 07-May-24 Staging time

JAH-Z1-DU-PR-PWR.170
Material Delivery 90 08-May-24 25-Aug-24 Material Delivery

MEDIUM VOLTAGE 13.8 KV NETWORK 145 23-Apr-24 14-Oct-24 14-Oct-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z1-DU-PR-PWR.200
Request for Quotation 10 23-Apr-24 04-May-24 Request for Quotation

JAH-Z1-DU-PR-PWR.205
Issue Purchase Order 15 05-May-24 21-May-24 Issue Purchase Order

JAH-Z1-DU-PR-PWR.210
Staging time 30 22-May-24 30-Jun-24 Staging time

JAH-Z1-DU-PR-PWR.218
Material Delivery 90 01-Jul-24 14-Oct-24 Material Delivery

LOW VOLTAGE NETWORK 145 30-May-24 20-Nov-24 20-Nov-24, LOW VOLTAGE NETWORK
JAH-Z1-DU-PR-PWR.220
Request for Quotation 10 30-May-24 10-Jun-24 Request for Quotation

JAH-Z1-DU-PR-PWR.225
Issue Purchase Order 15 11-Jun-24 02-Jul-24 Issue Purchase Order

JAH-Z1-DU-PR-PWR.230
Material Delivery 90 07-Aug-24 20-Nov-24 Material Delivery

JAH-Z1-DU-PR-PWR.235
Staging time 30 03-Jul-24 06-Aug-24 Staging time

ELECTRICAL DISTRIBUTION SYSTEM 145 11-Jul-24 28-Dec-24 28-Dec-24, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z1-DU-PR-PWR.175
Request for Quotation 10 11-Jul-24 22-Jul-24 Request for Quotation

JAH-Z1-DU-PR-PWR.180
Issue Purchase Order 15 23-Jul-24 08-Aug-24 Issue Purchase Order

JAH-Z1-DU-PR-PWR.190
Staging time 30 10-Aug-24 12-Sep-24 Staging time

JAH-Z1-DU-PR-PWR.195
Material Delivery 90 14-Sep-24 28-Dec-24 Material Delivery

LIGHTING SYSTEM 145 18-Aug-24 03-Feb-25 03-Feb-25, LIGHTING SYSTEM


JAH-Z1-DU-PR-PWR.240
Request for Quotation 10 18-Aug-24 28-Aug-24 Request for Quotation

JAH-Z1-DU-PR-PWR.245
Issue Purchase Order 15 29-Aug-24 15-Sep-24 Issue Purchase Order

JAH-Z1-DU-PR-PWR.255
Staging time 30 16-Sep-24 21-Oct-24 Staging time

JAH-Z1-DU-PR-PWR.260
Material Delivery 90 22-Oct-24 03-Feb-25 Material Delivery

LOW CURRENT 145 25-Sep-24 12-Mar-25 12-Mar-25, LOW CURRENT


TELECOM SERVICES 145 25-Sep-24 12-Mar-25 12-Mar-25, TELECOM SERVICES
JAH-Z1-DU-PR-LC.145Request for Quotation 10 25-Sep-24 06-Oct-24 Request for Quotation

JAH-Z1-DU-PR-LC.150Issue Purchase Order 15 07-Oct-24 23-Oct-24 Issue Purchase Order

JAH-Z1-DU-PR-LC.155Staging time 30 24-Oct-24 27-Nov-24 Staging time

JAH-Z1-DU-PR-LC.160Material Delivery 90 28-Nov-24 12-Mar-25 Material Delivery

MEP 235 08-Jan-24 16-Oct-24 16-Oct-24, MEP


JAH-Z1-PRO-MEP.100 Request for Quotation 10 08-Jan-24 18-Jan-24 Request for Quotation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
214 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-PRO-MEP.105 Issue Purchase Order 15 20-Jan-24 05-Feb-24 Issue Purchase Order

JAH-Z1-PRO-MEP.110 Staging Time 30 06-Feb-24 11-Mar-24 Staging Time

JAH-Z1-PRO-MEP.115 Material Delivery 180 12-Mar-24 16-Oct-24 Material Delivery

ARCHITECTURAL 115 13-Dec-23 28-Apr-24 28-Apr-24, ARCHITECTURAL


JAH-Z1-PRO-ARC.100 Request for Quotation for GRC Panels 10 13-Dec-23 24-Dec-23 Request for Quotation for GRC Panels

JAH-Z1-PRO-ARC.105 Issue Purchase Order 15 25-Dec-23 10-Jan-24 Issue Purchase Order

JAH-Z1-PRO-ARC.110 Staging Time 30 11-Jan-24 14-Feb-24 Staging Time

JAH-Z1-PRO-ARC.115 Material Delivery 60 15-Feb-24 28-Apr-24 Material Delivery

CONSTRUCTION 809 14-Aug-22 A 06-Jan-26 06-Jan-26, CONSTRUCTION


GENERAL SITE ARRANGEMENT 170 04-Sep-22 A 12-Jun-23 12-Jun-23, GENERAL SITE ARRANGEMENT
SITE PREPARATION 170 04-Sep-22 A 12-Jun-23 12-Jun-23, SITE PREPARATION
JAH-CON-Z1-GA-SP.100Site Clearing & Grubbing / Demolition of Obstacles 15 04-Sep-22 A 10-Sep-22 A Site Clearing & Grubbing / Demolition of Obstacles

JAH-CON-Z1-GA-SP.105Disposal /Removal of Unnecessary Objects from Site 8 11-Sep-22 A 12-Sep-22 A Disposal /Removal of Unnecessary Objects from Site

JAH-CON-Z1-GA-SP.110Relocation of Exisiting Utilities 25 15-May-23 12-Jun-23 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 56 14-Aug-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION


JAH-CON-Z1-GTI.100 Borehole Layout Preparation & Submission 15 14-Aug-22 A 20-Aug-22 A Borehole Layout Preparation & Submission

JAH-CON-Z1-GTI.105 Borehole Layout Review & Approval 7 21-Aug-22 A 22-Aug-22 A Borehole Layout Review & Approval

JAH-CON-Z1-GTI.110 Drilling Boreholes 20 24-Aug-22 A 27-Aug-22 A Drilling Boreholes

JAH-CON-Z1-GTI.115 Issuance of Geo-Technical Investigation Report 14 07-Sep-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 620 13-Sep-22 A 26-Nov-24 26-Nov-24, EXCAVATION & DEWATERING
JAH-CON-Z1-DE.102 Dewatering @Sta. 0+133 ~ 0+200 181 26-Jun-23 27-Jan-24 Dewatering @Sta. 0+133 ~ 0+200

JAH-CON-Z1-DE.107 Dewatering @Sta. 0+200 ~ 0+300 251 23-Jul-23 14-May-24 Dewatering @Sta. 0+200 ~ 0+300

JAH-CON-Z1-DE.112 Dewatering @Sta. 0+300 ~ 0+400 301 07-Oct-23 30-Sep-24 Dewatering @Sta. 0+300 ~ 0+400

JAH-CON-Z1-DE.120 Dewatering @Sta. 0+400 ~ 0+500 345 08-Oct-22 A 26-Nov-24 Dewatering @Sta. 0+400 ~ 0+500

JAH-CON-Z1-EX.100 Excavation @Sta. 0+133 ~ 0+200 20 26-Jun-23 22-Jul-23 Excavation @Sta. 0+133 ~ 0+200

JAH-CON-Z1-EX.105 Excavation @Sta 0+200 ~ 0+300 20 23-Jul-23 14-Aug-23 Excavation @Sta 0+200 ~ 0+300

JAH-CON-Z1-EX.110 Excavation @Sta. 0+300 ~ 0+400 20 07-Oct-23 29-Oct-23 Excavation @Sta. 0+300 ~ 0+400

JAH-CON-Z1-EX.115 Excavation @Sta. 0+400 ~ 0+500 25 13-Sep-22 A 02-Nov-23 Excavation @Sta. 0+400 ~ 0+500

SOIL IMPROVEMENT 98 23-Jul-23 14-Nov-23 14-Nov-23, SOIL IMPROVEMENT


JAH-CON-Z1-SIMP.101 Soil Improvement @Sta. 0+000 ~ 0+100 10 23-Jul-23 02-Aug-23 Soil Improvement @Sta. 0+000 ~ 0+100

JAH-CON-Z1-SIMP.106 Soil Improvement @Sta 0+100 ~ 0+200 10 15-Aug-23 26-Aug-23 Soil Improvement @Sta 0+100 ~ 0+200

JAH-CON-Z1-SIMP.111 Soil Improvement @Sta. 0+200 ~ 0+300 10 30-Oct-23 09-Nov-23 Soil Improvement @Sta. 0+200 ~ 0+300

JAH-CON-Z1-SIMP.116 Soil Improvement @Sta. 0+400 ~ 0+500 10 04-Nov-23 14-Nov-23 Soil Improvement @Sta. 0+400 ~ 0+500

STRUCTURAL WORKS 491 31-Aug-23 09-Apr-25 09-Apr-25, STRUCTURAL WORKS


STA. 0+133 ~ 0+153 102 31-Aug-23 28-Dec-23 28-Dec-23, STA. 0+133 ~ 0+153
BASE SLAB 28 31-Aug-23 03-Oct-23 03-Oct-23, BASE SLAB
JAH-Z1-ST-S1-BS.100 Lean Concrete for Base Slab 1 31-Aug-23 31-Aug-23 Lean Concrete for Base Slab

JAH-Z1-ST-S1-BS.105 Waterproofing for Lean Concrete 2 02-Sep-23 03-Sep-23 Waterproofing for Lean Concrete

JAH-Z1-ST-S1-BS.110 Base Slab Rebar Installation 8 04-Sep-23 12-Sep-23 Base Slab Rebar Installation

JAH-Z1-ST-S1-BS.115 Base Slab Formwork Installation 7 13-Sep-23 20-Sep-23 Base Slab Formwork Installation

JAH-Z1-ST-S1-BS.120 Base Slab Concrete Casting 1 21-Sep-23 21-Sep-23 Base Slab Concrete Casting

JAH-Z1-ST-S1-BS.122 Curing work 7 24-Sep-23 01-Oct-23 Curing work

JAH-Z1-ST-S1-BS.125 Base Slab Formwork Removel 2 02-Oct-23 03-Oct-23 Base Slab Formwork Removel

TUNNEL WALLS 37 04-Oct-23 15-Nov-23 15-Nov-23, TUNNEL WALLS


JAH-Z1-ST-S1-TW.100 Tunnel Walls Rebar Installation 8 04-Oct-23 12-Oct-23 Tunnel Walls Rebar Installation

JAH-Z1-ST-S1-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 04-Oct-23 12-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
215 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S1-TW.110 Tunnel Formwork Installation 7 14-Oct-23 21-Oct-23 Tunnel Formwork Installation

JAH-Z1-ST-S1-TW.115 Tunnel Walls Concrete Casting 1 22-Oct-23 22-Oct-23 Tunnel Walls Concrete Casting

JAH-Z1-ST-S1-TW.117 Curing work 7 23-Oct-23 30-Oct-23 Curing work

JAH-Z1-ST-S1-TW.120 Tunnel Walls Formwork Removel 2 31-Oct-23 01-Nov-23 Tunnel Walls Formwork Removel

JAH-Z1-ST-S1-TW.125 Tunnel Wall Waterproofing 12 02-Nov-23 15-Nov-23 Tunnel Wall Waterproofing

BARRIER 33 02-Nov-23 10-Dec-23 10-Dec-23, BARRIER


JAH-Z1-ST-S1-BR.100 Barrier wall Rebar Installation 4 02-Nov-23 06-Nov-23 Barrier wall Rebar Installation

JAH-Z1-ST-S1-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 07-Nov-23 08-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S1-BR.110 Barrier Formwork Installation 4 09-Nov-23 13-Nov-23 Barrier Formwork Installation

JAH-Z1-ST-S1-BR.115 Barrier Concrete Casting 2 14-Nov-23 15-Nov-23 Barrier Concrete Casting

JAH-Z1-ST-S1-BR.117 Curing work 7 16-Nov-23 23-Nov-23 Curing work

JAH-Z1-ST-S1-BR.120 Barrier Formwork Removel 3 25-Nov-23 27-Nov-23 Barrier Formwork Removel

JAH-Z1-ST-S1-BR.125 Barrier Protective coating 4 06-Dec-23 10-Dec-23 Barrier Protective coating

PLAIN CONCRETE FILL 16 11-Dec-23 28-Dec-23 28-Dec-23, PLAIN CONCRETE FILL


JAH-Z1-ST-S1-CF.100 Plain Concrete casting 1 11-Dec-23 11-Dec-23 Plain Concrete casting

JAH-Z1-ST-S1-CF.105 Curing work 7 12-Dec-23 19-Dec-23 Curing work

JAH-Z1-ST-S1-CF.110 Concrete Protective coating 8 20-Dec-23 28-Dec-23 Concrete Protective coating

STA. 0+153 ~ 0+173 204 13-Sep-23 12-May-24 12-May-24, STA. 0+153 ~ 0+173
BASE SLAB 111 13-Sep-23 21-Jan-24 21-Jan-24, BASE SLAB
JAH-Z1-ST-S2-BS.100 Lean Concrete for Base Slab 1 13-Sep-23 13-Sep-23 Lean Concrete for Base Slab

JAH-Z1-ST-S2-BS.105 Waterproofing for Lean Concrete 1 14-Sep-23 14-Sep-23 Waterproofing for Lean Concrete

JAH-Z1-ST-S2-BS.110 Base Slab Rebar Installation 8 24-Dec-23 01-Jan-24 Base Slab Rebar Installation

JAH-Z1-ST-S2-BS.115 Base Slab Formwork Installation 7 02-Jan-24 09-Jan-24 Base Slab Formwork Installation

JAH-Z1-ST-S2-BS.120 Base Slab Concrete Casting 1 10-Jan-24 10-Jan-24 Base Slab Concrete Casting

JAH-Z1-ST-S2-BS.122 Curing work 7 11-Jan-24 18-Jan-24 Curing work

JAH-Z1-ST-S2-BS.125 Base Slab Formwork Removel 2 20-Jan-24 21-Jan-24 Base Slab Formwork Removel

TUNNEL WALLS 37 22-Jan-24 04-Mar-24 04-Mar-24, TUNNEL WALLS


JAH-Z1-ST-S2-TW.100 Tunnel Walls Rebar Installation 8 22-Jan-24 30-Jan-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S2-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-Jan-24 30-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S2-TW.110 Tunnel Formwork Installation 7 31-Jan-24 07-Feb-24 Tunnel Formwork Installation

JAH-Z1-ST-S2-TW.115 Tunnel Walls Concrete Casting 1 08-Feb-24 08-Feb-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S2-TW.117 Curing work 7 10-Feb-24 17-Feb-24 Curing work

JAH-Z1-ST-S2-TW.120 Tunnel Walls Formwork Removel 2 18-Feb-24 19-Feb-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S2-TW.125 Tunnel Wall Waterproofing 12 20-Feb-24 04-Mar-24 Tunnel Wall Waterproofing

BARRIER 33 05-Mar-24 15-Apr-24 15-Apr-24, BARRIER


JAH-Z1-ST-S2-BR.100 Barrier wall Rebar Installation 4 05-Mar-24 09-Mar-24 Barrier wall Rebar Installation

JAH-Z1-ST-S2-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 10-Mar-24 11-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S2-BR.110 Barrier Formwork Installation 4 12-Mar-24 16-Mar-24 Barrier Formwork Installation

JAH-Z1-ST-S2-BR.115 Barrier Concrete Casting 2 17-Mar-24 18-Mar-24 Barrier Concrete Casting

JAH-Z1-ST-S2-BR.117 Curing work 7 19-Mar-24 26-Mar-24 Curing work

JAH-Z1-ST-S2-BR.120 Barrier Formwork Removel 3 27-Mar-24 30-Mar-24 Barrier Formwork Removel

JAH-Z1-ST-S2-BR.125 Barrier Protective coating 4 08-Apr-24 15-Apr-24 Barrier Protective coating

PLAIN CONCRETE FILL 23 16-Apr-24 12-May-24 12-May-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S2-CF.100 Plain Concrete Casting 1 16-Apr-24 16-Apr-24 Plain Concrete Casting

JAH-Z1-ST-S2-CF.105 Curing work 7 17-Apr-24 24-Apr-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
216 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S2-CF.110 Concrete Protective coating 8 04-May-24 12-May-24 Concrete Protective coating

STA. 0+173 ~ 0+193 120 02-Jan-24 23-May-24 23-May-24, STA. 0+173 ~ 0+193
BASE SLAB 27 02-Jan-24 01-Feb-24 01-Feb-24, BASE SLAB
JAH-Z1-ST-S3-BS.100 Lean Concrete for Base Slab 1 02-Jan-24 02-Jan-24 Lean Concrete for Base Slab

JAH-Z1-ST-S3-BS.105 Waterproofing for Lean Concrete 1 03-Jan-24 03-Jan-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S3-BS.110 Base Slab Rebar Installation 8 04-Jan-24 13-Jan-24 Base Slab Rebar Installation

JAH-Z1-ST-S3-BS.115 Base Slab Formwork Installation 7 14-Jan-24 21-Jan-24 Base Slab Formwork Installation

JAH-Z1-ST-S3-BS.120 Base Slab Concrete Casting 1 22-Jan-24 22-Jan-24 Base Slab Concrete Casting

JAH-Z1-ST-S3-BS.122 Curing work 7 23-Jan-24 30-Jan-24 Curing work

JAH-Z1-ST-S3-BS.125 Base Slab Formwork Removel 2 31-Jan-24 01-Feb-24 Base Slab Formwork Removel

TUNNEL WALLS 37 03-Feb-24 16-Mar-24 16-Mar-24, TUNNEL WALLS


JAH-Z1-ST-S3-TW.100 Tunnel Walls Rebar Installation 8 03-Feb-24 11-Feb-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S3-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 03-Feb-24 11-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S3-TW.110 Tunnel Formwork Installation 7 12-Feb-24 19-Feb-24 Tunnel Formwork Installation

JAH-Z1-ST-S3-TW.115 Tunnel Walls Concrete Casting 1 20-Feb-24 20-Feb-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S3-TW.117 Curing work 7 21-Feb-24 28-Feb-24 Curing work

JAH-Z1-ST-S3-TW.120 Tunnel Walls Formwork Removel 2 29-Feb-24 02-Mar-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S3-TW.125 Tunnel Wall Waterproofing 12 03-Mar-24 16-Mar-24 Tunnel Wall Waterproofing

BARRIER 33 17-Mar-24 27-Apr-24 27-Apr-24, BARRIER


JAH-Z1-ST-S3-BR.100 Barrier wall Rebar Installation 4 17-Mar-24 20-Mar-24 Barrier wall Rebar Installation

JAH-Z1-ST-S3-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 21-Mar-24 23-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S3-BR.110 Barrier Formwork Installation 4 24-Mar-24 27-Mar-24 Barrier Formwork Installation

JAH-Z1-ST-S3-BR.115 Barrier Concrete Casting 2 28-Mar-24 30-Mar-24 Barrier Concrete Casting

JAH-Z1-ST-S3-BR.117 Curing work 7 31-Mar-24 07-Apr-24 Curing work

JAH-Z1-ST-S3-BR.120 Barrier Formwork Removel 3 08-Apr-24 14-Apr-24 Barrier Formwork Removel

JAH-Z1-ST-S3-BR.125 Barrier Protective coating 4 23-Apr-24 27-Apr-24 Barrier Protective coating

PLAIN CONCRETE FILL 23 28-Apr-24 23-May-24 23-May-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S3-CF.100 Plain Concrete casting 1 28-Apr-24 28-Apr-24 Plain Concrete casting

JAH-Z1-ST-S3-CF.105 Curing work 7 29-Apr-24 06-May-24 Curing work

JAH-Z1-ST-S3-CF.110 Concrete Protective coating 8 15-May-24 23-May-24 Concrete Protective coating

STA. 0+193 ~ 0+213 115 22-Jan-24 06-Jun-24 06-Jun-24, STA. 0+193 ~ 0+213
BASE SLAB 27 22-Jan-24 21-Feb-24 21-Feb-24, BASE SLAB
JAH-Z1-ST-S4-BS.100 Lean Concrete for Base Slab 1 22-Jan-24 22-Jan-24 Lean Concrete for Base Slab

JAH-Z1-ST-S4-BS.105 Waterproofing for Lean Concrete 1 23-Jan-24 23-Jan-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S4-BS.110 Base Slab Rebar Installation 8 24-Jan-24 01-Feb-24 Base Slab Rebar Installation

JAH-Z1-ST-S4-BS.115 Base Slab Formwork Installation 7 03-Feb-24 10-Feb-24 Base Slab Formwork Installation

JAH-Z1-ST-S4-BS.120 Base Slab Concrete Casting 1 11-Feb-24 11-Feb-24 Base Slab Concrete Casting

JAH-Z1-ST-S4-BS.122 Curing work 7 12-Feb-24 19-Feb-24 Curing work

JAH-Z1-ST-S4-BS.125 Base Slab Formwork Removel 2 20-Feb-24 21-Feb-24 Base Slab Formwork Removel

TUNNEL WALLS 37 22-Feb-24 04-Apr-24 04-Apr-24, TUNNEL WALLS


JAH-Z1-ST-S4-TW.100 Tunnel Walls Rebar Installation 8 22-Feb-24 02-Mar-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S4-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-Feb-24 02-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S4-TW.110 Tunnel Formwork Installation 7 03-Mar-24 10-Mar-24 Tunnel Formwork Installation

JAH-Z1-ST-S4-TW.115 Tunnel Walls Concrete Casting 1 11-Mar-24 11-Mar-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S4-TW.117 Curing work 7 12-Mar-24 19-Mar-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
217 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S4-TW.120 Tunnel Walls Formwork Removel 2 20-Mar-24 21-Mar-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S4-TW.125 Tunnel Wall Waterproofing 12 23-Mar-24 04-Apr-24 Tunnel Wall Waterproofing

BARRIER 33 06-Apr-24 16-May-24 16-May-24, BARRIER


JAH-Z1-ST-S4-BR.100 Barrier wall Rebar Installation 4 06-Apr-24 13-Apr-24 Barrier wall Rebar Installation

JAH-Z1-ST-S4-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 14-Apr-24 15-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S4-BR.110 Barrier Formwork Installation 4 16-Apr-24 20-Apr-24 Barrier Formwork Installation

JAH-Z1-ST-S4-BR.115 Barrier Concrete Casting 2 21-Apr-24 22-Apr-24 Barrier Concrete Casting

JAH-Z1-ST-S4-BR.117 Curing work 7 23-Apr-24 30-Apr-24 Curing work

JAH-Z1-ST-S4-BR.120 Barrier Formwork Removel 3 01-May-24 04-May-24 Barrier Formwork Removel

JAH-Z1-ST-S4-BR.125 Barrier Protective coating 4 13-May-24 16-May-24 Barrier Protective coating

PLAIN CONCRETE FILL 18 18-May-24 06-Jun-24 06-Jun-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S4-CF.100 Plain Concrete casting 1 18-May-24 18-May-24 Plain Concrete casting

JAH-Z1-ST-S4-CF.105 Curing work 2 19-May-24 20-May-24 Curing work

JAH-Z1-ST-S4-CF.110 Concrete Protective coating 8 29-May-24 06-Jun-24 Concrete Protective coating

STA. 0+213 ~ 0+233 115 11-Feb-24 01-Jul-24 01-Jul-24, STA. 0+213 ~ 0+233
BASE SLAB 27 11-Feb-24 12-Mar-24 12-Mar-24, BASE SLAB
JAH-Z1-ST-S5-BS.100 Lean Concrete for Base Slab 1 11-Feb-24 11-Feb-24 Lean Concrete for Base Slab

JAH-Z1-ST-S5-BS.105 Waterproofing for Lean Concrete 1 12-Feb-24 12-Feb-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S5-BS.110 Base Slab Rebar Installation 8 13-Feb-24 21-Feb-24 Base Slab Rebar Installation

JAH-Z1-ST-S5-BS.115 Base Slab Formwork Installation 7 22-Feb-24 29-Feb-24 Base Slab Formwork Installation

JAH-Z1-ST-S5-BS.120 Base Slab Concrete Casting 1 02-Mar-24 02-Mar-24 Base Slab Concrete Casting

JAH-Z1-ST-S5-BS.122 Curing work 7 03-Mar-24 10-Mar-24 Curing work

JAH-Z1-ST-S5-BS.125 Base Slab Formwork Removel 2 11-Mar-24 12-Mar-24 Base Slab Formwork Removel

TUNNEL WALLS 37 13-Mar-24 28-Apr-24 28-Apr-24, TUNNEL WALLS


JAH-Z1-ST-S5-TW.100 Tunnel Walls Rebar Installation 8 13-Mar-24 21-Mar-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S5-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 13-Mar-24 21-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S5-TW.110 Tunnel Formwork Installation 7 23-Mar-24 30-Mar-24 Tunnel Formwork Installation

JAH-Z1-ST-S5-TW.115 Tunnel Walls Concrete Casting 1 31-Mar-24 31-Mar-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S5-TW.117 Curing work 7 01-Apr-24 08-Apr-24 Curing work

JAH-Z1-ST-S5-TW.120 Tunnel Walls Formwork Removel 2 13-Apr-24 14-Apr-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S5-TW.125 Tunnel Wall Waterproofing 12 15-Apr-24 28-Apr-24 Tunnel Wall Waterproofing

BARRIER 33 29-Apr-24 05-Jun-24 05-Jun-24, BARRIER


JAH-Z1-ST-S5-BR.100 Barrier wall Rebar Installation 4 29-Apr-24 02-May-24 Barrier wall Rebar Installation

JAH-Z1-ST-S5-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 04-May-24 05-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S5-BR.110 Barrier Formwork Installation 4 06-May-24 09-May-24 Barrier Formwork Installation

JAH-Z1-ST-S5-BR.115 Barrier Concrete Casting 2 11-May-24 12-May-24 Barrier Concrete Casting

JAH-Z1-ST-S5-BR.117 Curing work 7 13-May-24 20-May-24 Curing work

JAH-Z1-ST-S5-BR.120 Barrier Formwork Removel 3 21-May-24 23-May-24 Barrier Formwork Removel

JAH-Z1-ST-S5-BR.125 Barrier Protective coating 4 02-Jun-24 05-Jun-24 Barrier Protective coating

PLAIN CONCRETE FILL 18 06-Jun-24 01-Jul-24 01-Jul-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S4-CF.115 Plain Concrete casting 1 06-Jun-24 06-Jun-24 Plain Concrete casting

JAH-Z1-ST-S4-CF.120 Curing work 2 08-Jun-24 09-Jun-24 Curing work

JAH-Z1-ST-S4-CF.125 Concrete Protective coating 8 23-Jun-24 01-Jul-24 Concrete Protective coating

STA. 0+233 ~ 0+253 120 02-Mar-24 27-Jul-24 27-Jul-24, STA. 0+233 ~ 0+253
BASE SLAB 27 02-Mar-24 01-Apr-24 01-Apr-24, BASE SLAB
JAH-Z1-ST-S6-BS.100 Lean Concrete for Base Slab 1 02-Mar-24 02-Mar-24 Lean Concrete for Base Slab

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
218 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S6-BS.105 Waterproofing for Lean Concrete 1 03-Mar-24 03-Mar-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S6-BS.110 Base Slab Rebar Installation 8 04-Mar-24 12-Mar-24 Base Slab Rebar Installation

JAH-Z1-ST-S6-BS.115 Base Slab Formwork Installation 7 13-Mar-24 20-Mar-24 Base Slab Formwork Installation

JAH-Z1-ST-S6-BS.120 Base Slab Concrete Casting 1 21-Mar-24 21-Mar-24 Base Slab Concrete Casting

JAH-Z1-ST-S6-BS.122 Curing work 7 23-Mar-24 30-Mar-24 Curing work

JAH-Z1-ST-S6-BS.125 Base Slab Formwork Removel 2 31-Mar-24 01-Apr-24 Base Slab Formwork Removel

TUNNEL WALLS 37 02-Apr-24 18-May-24 18-May-24, TUNNEL WALLS


JAH-Z1-ST-S6-TW.100 Tunnel Walls Rebar Installation 8 02-Apr-24 14-Apr-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S6-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 02-Apr-24 14-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S6-TW.110 Tunnel Formwork Installation 7 15-Apr-24 22-Apr-24 Tunnel Formwork Installation

JAH-Z1-ST-S6-TW.115 Tunnel Walls Concrete Casting 1 23-Apr-24 23-Apr-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S6-TW.117 Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z1-ST-S6-TW.120 Tunnel Walls Formwork Removel 2 02-May-24 04-May-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S6-TW.125 Tunnel Wall Waterproofing 12 05-May-24 18-May-24 Tunnel Wall Waterproofing

BARRIER 33 19-May-24 30-Jun-24 30-Jun-24, BARRIER


JAH-Z1-ST-S6-BR.100 Barrier wall Rebar Installation 4 19-May-24 22-May-24 Barrier wall Rebar Installation

JAH-Z1-ST-S6-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 23-May-24 25-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S6-BR.110 Barrier Formwork Installation 4 26-May-24 29-May-24 Barrier Formwork Installation

JAH-Z1-ST-S6-BR.115 Barrier Concrete Casting 2 30-May-24 01-Jun-24 Barrier Concrete Casting

JAH-Z1-ST-S6-BR.117 Curing work 7 02-Jun-24 09-Jun-24 Curing work

JAH-Z1-ST-S6-BR.120 Barrier Formwork Removel 3 10-Jun-24 12-Jun-24 Barrier Formwork Removel

JAH-Z1-ST-S6-BR.125 Barrier Protective coating 4 26-Jun-24 30-Jun-24 Barrier Protective coating

PLAIN CONCRETE FILL 23 01-Jul-24 27-Jul-24 27-Jul-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S5-CF.100 Plain Concrete casting 1 01-Jul-24 01-Jul-24 Plain Concrete casting

JAH-Z1-ST-S5-CF.105 Curing work 7 02-Jul-24 09-Jul-24 Curing work

JAH-Z1-ST-S5-CF.110 Concrete Protective coating 8 18-Jul-24 27-Jul-24 Concrete Protective coating

STA.0+253 ~ 0+273 120 21-Mar-24 15-Aug-24 15-Aug-24, STA.0+253 ~ 0+273


BASE SLAB 27 21-Mar-24 24-Apr-24 24-Apr-24, BASE SLAB
JAH-Z1-ST-S7-BS.100 Lean Concrete for Base Slab 1 21-Mar-24 21-Mar-24 Lean Concrete for Base Slab

JAH-Z1-ST-S7-BS.105 Waterproofing for Lean Concrete 1 23-Mar-24 23-Mar-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S7-BS.110 Base Slab Rebar Installation 8 24-Mar-24 01-Apr-24 Base Slab Rebar Installation

JAH-Z1-ST-S7-BS.115 Base Slab Formwork Installation 7 02-Apr-24 13-Apr-24 Base Slab Formwork Installation

JAH-Z1-ST-S7-BS.120 Base Slab Concrete Casting 1 14-Apr-24 14-Apr-24 Base Slab Concrete Casting

JAH-Z1-ST-S7-BS.122 Curing work 7 15-Apr-24 22-Apr-24 Curing work

JAH-Z1-ST-S7-BS.125 Base Slab Formwork Removel 2 23-Apr-24 24-Apr-24 Base Slab Formwork Removel

TUNNEL WALLS 37 25-Apr-24 06-Jun-24 06-Jun-24, TUNNEL WALLS


JAH-Z1-ST-S7-TW.100 Tunnel Walls Rebar Installation 8 25-Apr-24 04-May-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S7-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 25-Apr-24 04-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S7-TW.110 Tunnel Formwork Installation 7 05-May-24 12-May-24 Tunnel Formwork Installation

JAH-Z1-ST-S7-TW.115 Tunnel Walls Concrete Casting 1 13-May-24 13-May-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S7-TW.117 Curing work 7 14-May-24 21-May-24 Curing work

JAH-Z1-ST-S7-TW.120 Tunnel Walls Formwork Removel 2 22-May-24 23-May-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S7-TW.125 Tunnel Wall Waterproofing 12 25-May-24 06-Jun-24 Tunnel Wall Waterproofing

BARRIER 33 08-Jun-24 20-Jul-24 20-Jul-24, BARRIER


JAH-Z1-ST-S7-BR.100 Barrier wall Rebar Installation 4 08-Jun-24 11-Jun-24 Barrier wall Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
219 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S7-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 12-Jun-24 13-Jun-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S7-BR.110 Barrier Formwork Installation 4 19-Jun-24 23-Jun-24 Barrier Formwork Installation

JAH-Z1-ST-S7-BR.115 Barrier Concrete Casting 2 24-Jun-24 25-Jun-24 Barrier Concrete Casting

JAH-Z1-ST-S7-BR.117 Curing work 7 26-Jun-24 03-Jul-24 Curing work

JAH-Z1-ST-S7-BR.120 Barrier Formwork Removel 3 04-Jul-24 07-Jul-24 Barrier Formwork Removel

JAH-Z1-ST-S7-BR.125 Barrier Protective coating 4 16-Jul-24 20-Jul-24 Barrier Protective coating

PLAIN CONCRETE FILL 23 21-Jul-24 15-Aug-24 15-Aug-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S7-CF.100 Plain Concrete casting 1 21-Jul-24 21-Jul-24 Plain Concrete casting

JAH-Z1-ST-S7-CF.105 Curing work 7 22-Jul-24 29-Jul-24 Curing work

JAH-Z1-ST-S7-CF.110 Concrete Protective coating 8 07-Aug-24 15-Aug-24 Concrete Protective coating

STA. 0+273 ~ 0+293 121 14-Apr-24 05-Sep-24 05-Sep-24, STA. 0+273 ~ 0+293
BASE SLAB 28 14-Apr-24 15-May-24 15-May-24, BASE SLAB
JAH-Z1-ST-S8-BS.100 Lean Concrete for Base Slab 1 14-Apr-24 14-Apr-24 Lean Concrete for Base Slab

JAH-Z1-ST-S8-BS.105 Waterproofing for Lean Concrete 1 15-Apr-24 15-Apr-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S8-BS.110 Base Slab Rebar Installation 8 16-Apr-24 24-Apr-24 Base Slab Rebar Installation

JAH-Z1-ST-S8-BS.115 Base Slab Formwork Installation 7 27-Apr-24 04-May-24 Base Slab Formwork Installation

JAH-Z1-ST-S8-BS.120 Base Slab Concrete Casting 1 05-May-24 05-May-24 Base Slab Concrete Casting

JAH-Z1-ST-S8-BS.122 Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z1-ST-S8-BS.125 Base Slab Formwork Removel 2 14-May-24 15-May-24 Base Slab Formwork Removel

TUNNEL WALLS 37 16-May-24 02-Jul-24 02-Jul-24, TUNNEL WALLS


JAH-Z1-ST-S8-TW.100 Tunnel Walls Rebar Installation 8 16-May-24 25-May-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S8-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 16-May-24 25-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S8-TW.110 Tunnel Formwork Installation 7 26-May-24 02-Jun-24 Tunnel Formwork Installation

JAH-Z1-ST-S8-TW.115 Tunnel Walls Concrete Casting 1 03-Jun-24 03-Jun-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S8-TW.117 Curing work 7 04-Jun-24 11-Jun-24 Curing work

JAH-Z1-ST-S8-TW.120 Tunnel Walls Formwork Removel 2 12-Jun-24 13-Jun-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S8-TW.125 Tunnel Wall Waterproofing 12 19-Jun-24 02-Jul-24 Tunnel Wall Waterproofing

BARRIER 33 03-Jul-24 10-Aug-24 10-Aug-24, BARRIER


JAH-Z1-ST-S8-BR.100 Barrier wall Rebar Installation 4 03-Jul-24 07-Jul-24 Barrier wall Rebar Installation

JAH-Z1-ST-S8-BR.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 2 08-Jul-24 09-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S8-BR.110 Barrier Formwork Installation 4 10-Jul-24 14-Jul-24 Barrier Formwork Installation

JAH-Z1-ST-S8-BR.115 Barrier Concrete Casting 2 15-Jul-24 16-Jul-24 Barrier Concrete Casting

JAH-Z1-ST-S8-BR.117 Curing work 7 17-Jul-24 24-Jul-24 Curing work

JAH-Z1-ST-S8-BR.120 Barrier Formwork Removel 3 25-Jul-24 28-Jul-24 Barrier Formwork Removel

JAH-Z1-ST-S8-BR.125 Barrier Protective coating 4 06-Aug-24 10-Aug-24 Barrier Protective coating

PLAIN CONCRETE FILL 23 11-Aug-24 05-Sep-24 05-Sep-24, PLAIN CONCRETE FILL


JAH-Z1-ST-S8-CF.100 Plain Concrete casting 1 11-Aug-24 11-Aug-24 Plain Concrete casting

JAH-Z1-ST-S8-CF.105 Curing work 7 12-Aug-24 19-Aug-24 Curing work

JAH-Z1-ST-S8-CF.110 Concrete Protective coating 8 28-Aug-24 05-Sep-24 Concrete Protective coating

STA. 0+293 ~ 0+313 123 25-Apr-24 19-Sep-24 19-Sep-24, STA. 0+293 ~ 0+313
BASE SLAB 27 25-Apr-24 26-May-24 26-May-24, BASE SLAB
JAH-Z1-ST-S9-BS.100 Lean Concrete for Base Slab 1 25-Apr-24 25-Apr-24 Lean Concrete for Base Slab

JAH-Z1-ST-S9-BS.105 Waterproofing for Lean Concrete 1 27-Apr-24 27-Apr-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S9-BS.110 Base Slab Rebar Installation 8 28-Apr-24 06-May-24 Base Slab Rebar Installation

JAH-Z1-ST-S9-BS.115 Base Slab Formwork Installation 7 07-May-24 14-May-24 Base Slab Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
220 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S9-BS.120 Base Slab Concrete Casting 1 15-May-24 15-May-24 Base Slab Concrete Casting

JAH-Z1-ST-S9-BS.122 Curing work 7 16-May-24 23-May-24 Curing work

JAH-Z1-ST-S9-BS.125 Base Slab Formwork Removel 2 25-May-24 26-May-24 Base Slab Formwork Removel

COLUMN 23 27-May-24 26-Jun-24 26-Jun-24, COLUMN


JAH-Z1-ST-S9-CL.100 Column Rebar Installation 8 27-May-24 04-Jun-24 Column Rebar Installation

JAH-Z1-ST-S9-CL.105 Column Formwork Installation 7 05-Jun-24 12-Jun-24 Column Formwork Installation

JAH-Z1-ST-S9-CL.110 Column Concrete Casting 1 13-Jun-24 13-Jun-24 Column Concrete Casting

JAH-Z1-ST-S9-CL.115 Form Work Removal and Curing 7 19-Jun-24 26-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 27-May-24 13-Jul-24 13-Jul-24, TUNNEL WALLS


JAH-Z1-ST-S9-TW.100 Tunnel Walls Rebar Installation 8 27-May-24 04-Jun-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S9-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 27-May-24 04-Jun-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S9-TW.110 Tunnel Formwork Installation 7 05-Jun-24 12-Jun-24 Tunnel Formwork Installation

JAH-Z1-ST-S9-TW.115 Tunnel Walls Concrete Casting 1 13-Jun-24 13-Jun-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S9-TW.117 Curing work 7 19-Jun-24 26-Jun-24 Curing work

JAH-Z1-ST-S9-TW.120 Tunnel Walls Formwork Removel 2 27-Jun-24 29-Jun-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S9-TW.125 Tunnel Wall Waterproofing 12 30-Jun-24 13-Jul-24 Tunnel Wall Waterproofing

TOP SLAB 47 30-Jun-24 22-Aug-24 22-Aug-24, TOP SLAB


JAH-Z1-ST-S9-TS.100 Top Slab Formwork Installation 10 30-Jun-24 10-Jul-24 Top Slab Formwork Installation

JAH-Z1-ST-S9-TS.105 Top Slab Rebar Installation 8 11-Jul-24 20-Jul-24 Top Slab Rebar Installation

JAH-Z1-ST-S9-TS.110 Top Slab Concrete Casting 1 21-Jul-24 21-Jul-24 Top Slab Concrete Casting

JAH-Z1-ST-S9-TS.112 Curing work 7 22-Jul-24 29-Jul-24 Curing work

JAH-Z1-ST-S9-TS.115 Top Slab Formwork Removel 2 30-Jul-24 31-Jul-24 Top Slab Formwork Removel

JAH-Z1-ST-S9-TS.120 Waterproofing for Top Slab 12 10-Aug-24 22-Aug-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 24-Aug-24 19-Sep-24 19-Sep-24, MASS CONCRETE WORK


JAH-Z1-ST-S9-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 24-Aug-24 31-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S9-MC.105 Plain Concrete Casting 1 01-Sep-24 01-Sep-24 Plain Concrete Casting

JAH-Z1-ST-S9-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 02-Sep-24 02-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S9-MC.112 Curing work 7 03-Sep-24 10-Sep-24 Curing work

JAH-Z1-ST-S9-MC.115 Concrete Protective coating 8 11-Sep-24 19-Sep-24 Concrete Protective coating

STA. 0+313 ~ 0+333 123 15-May-24 10-Oct-24 10-Oct-24, STA. 0+313 ~ 0+333
BASE SLAB 27 15-May-24 19-Jun-24 19-Jun-24, BASE SLAB
JAH-Z1-ST-S10-BS.100Lean Concrete for Base Slab 1 15-May-24 15-May-24 Lean Concrete for Base Slab

JAH-Z1-ST-S10-BS.105Waterproofing for Lean Concrete 1 16-May-24 16-May-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S10-BS.110 Base Slab Rebar Installation 8 18-May-24 26-May-24 Base Slab Rebar Installation

JAH-Z1-ST-S10-BS.115 Base Slab Formwork Installation 7 27-May-24 03-Jun-24 Base Slab Formwork Installation

JAH-Z1-ST-S10-BS.120Base Slab Concrete Casting 1 04-Jun-24 04-Jun-24 Base Slab Concrete Casting

JAH-Z1-ST-S10-BS.122Curing work 7 05-Jun-24 12-Jun-24 Curing work

JAH-Z1-ST-S10-BS.125Base Slab Formwork Removel 2 13-Jun-24 19-Jun-24 Base Slab Formwork Removel

COLUMN 23 20-Jun-24 16-Jul-24 16-Jul-24, COLUMN


JAH-Z1-ST-S10-CL.100Column Rebar Installation 8 20-Jun-24 29-Jun-24 Column Rebar Installation

JAH-Z1-ST-S10-CL.105Column Formwork Installation 7 30-Jun-24 07-Jul-24 Column Formwork Installation

JAH-Z1-ST-S10-CL.110 Column Concrete Casting 1 08-Jul-24 08-Jul-24 Column Concrete Casting

JAH-Z1-ST-S10-CL.115 Form Work Removal and Curing 7 09-Jul-24 16-Jul-24 Form Work Removal and Curing

TUNNEL WALLS 37 20-Jun-24 01-Aug-24 01-Aug-24, TUNNEL WALLS


JAH-Z1-ST-S10-TW.100Tunnel Walls Rebar Installation 8 20-Jun-24 29-Jun-24 Tunnel Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
221 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S10-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 20-Jun-24 29-Jun-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S10-TW.110Tunnel Formwork Installation 7 30-Jun-24 07-Jul-24 Tunnel Formwork Installation

JAH-Z1-ST-S10-TW.115Tunnel Walls Concrete Casting 1 08-Jul-24 08-Jul-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S10-TW.117Curing work 7 09-Jul-24 16-Jul-24 Curing work

JAH-Z1-ST-S10-TW.120Tunnel Walls Formwork Removel 2 17-Jul-24 18-Jul-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S10-TW.125Tunnel Wall Waterproofing 12 20-Jul-24 01-Aug-24 Tunnel Wall Waterproofing

TOP SLAB 47 20-Jul-24 11-Sep-24 11-Sep-24, TOP SLAB


JAH-Z1-ST-S10-TS.100 Top Slab Formwork Installation 10 20-Jul-24 30-Jul-24 Top Slab Formwork Installation

JAH-Z1-ST-S10-TS.105 Top Slab Rebar Installation 8 31-Jul-24 08-Aug-24 Top Slab Rebar Installation

JAH-Z1-ST-S10-TS.110 Top Slab Concrete Casting 1 10-Aug-24 10-Aug-24 Top Slab Concrete Casting

JAH-Z1-ST-S10-TS.112 Curing work 7 11-Aug-24 18-Aug-24 Curing work

JAH-Z1-ST-S10-TS.115 Top Slab Formwork Removel 2 19-Aug-24 20-Aug-24 Top Slab Formwork Removel

JAH-Z1-ST-S10-TS.120 Waterproofing for Top Slab 12 29-Aug-24 11-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 12-Sep-24 10-Oct-24 10-Oct-24, MASS CONCRETE WORK


JAH-Z1-ST-S10-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 12-Sep-24 19-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S10-MC.105Plain Concrete Casting 1 21-Sep-24 21-Sep-24 Plain Concrete Casting

JAH-Z1-ST-S10-MC.110Mass Concrete Casting for Base Slab Top Layer 1 22-Sep-24 22-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S10-MC.112Curing work 7 24-Sep-24 01-Oct-24 Curing work

JAH-Z1-ST-S10-MC.115Concrete Protective coating 8 02-Oct-24 10-Oct-24 Concrete Protective coating

STA. 0+333 ~ 0+353 123 04-Jun-24 30-Oct-24 30-Oct-24, STA. 0+333 ~ 0+353
BASE SLAB 27 04-Jun-24 09-Jul-24 09-Jul-24, BASE SLAB
JAH-Z1-ST-S11-BS.100 Lean Concrete for Base Slab 1 04-Jun-24 04-Jun-24 Lean Concrete for Base Slab

JAH-Z1-ST-S11-BS.105 Waterproofing for Lean Concrete 1 05-Jun-24 05-Jun-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S11-BS.110 Base Slab Rebar Installation 8 06-Jun-24 19-Jun-24 Base Slab Rebar Installation

JAH-Z1-ST-S11-BS.115 Base Slab Formwork Installation 7 20-Jun-24 27-Jun-24 Base Slab Formwork Installation

JAH-Z1-ST-S11-BS.120 Base Slab Concrete Casting 1 29-Jun-24 29-Jun-24 Base Slab Concrete Casting

JAH-Z1-ST-S11-BS.122 Curing work 7 30-Jun-24 07-Jul-24 Curing work

JAH-Z1-ST-S11-BS.125 Base Slab Formwork Removel 2 08-Jul-24 09-Jul-24 Base Slab Formwork Removel

COLUMN 23 10-Jul-24 05-Aug-24 05-Aug-24, COLUMN


JAH-Z1-ST-S11-CL.100 Column Rebar Installation 8 10-Jul-24 18-Jul-24 Column Rebar Installation

JAH-Z1-ST-S11-CL.105 Column Formwork Installation 7 20-Jul-24 27-Jul-24 Column Formwork Installation

JAH-Z1-ST-S11-CL.110 Column Concrete Casting 1 28-Jul-24 28-Jul-24 Column Concrete Casting

JAH-Z1-ST-S11-CL.115 Form Work Removal and Curing 7 29-Jul-24 05-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 10-Jul-24 21-Aug-24 21-Aug-24, TUNNEL WALLS


JAH-Z1-ST-S11-TW.100Tunnel Walls Rebar Installation 8 10-Jul-24 18-Jul-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S11-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 10-Jul-24 18-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S11-TW.110Tunnel Formwork Installation 7 20-Jul-24 27-Jul-24 Tunnel Formwork Installation

JAH-Z1-ST-S11-TW.115Tunnel Walls Concrete Casting 1 28-Jul-24 28-Jul-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S11-TW.117Curing work 7 29-Jul-24 05-Aug-24 Curing work

JAH-Z1-ST-S11-TW.120Tunnel Walls Formwork Removel 2 06-Aug-24 07-Aug-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S11-TW.130Tunnel Wall Waterproofing 12 08-Aug-24 21-Aug-24 Tunnel Wall Waterproofing

TOP SLAB 47 08-Aug-24 02-Oct-24 02-Oct-24, TOP SLAB


JAH-Z1-ST-S11-TS.100 Top Slab Formwork Installation 10 08-Aug-24 19-Aug-24 Top Slab Formwork Installation

JAH-Z1-ST-S11-TS.105 Top Slab Rebar Installation 8 20-Aug-24 28-Aug-24 Top Slab Rebar Installation

JAH-Z1-ST-S11-TS.110 Top Slab Concrete Casting 1 29-Aug-24 29-Aug-24 Top Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
222 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S11-TS.112 Curing work 7 31-Aug-24 07-Sep-24 Curing work

JAH-Z1-ST-S11-TS.115 Top Slab Formwork Removel 2 08-Sep-24 09-Sep-24 Top Slab Formwork Removel

JAH-Z1-ST-S11-TS.120 Waterproofing for Top Slab 12 18-Sep-24 02-Oct-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 03-Oct-24 30-Oct-24 30-Oct-24, MASS CONCRETE WORK


JAH-Z1-ST-S11-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 03-Oct-24 10-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S11-MC.105Plain Concrete Casting 1 12-Oct-24 12-Oct-24 Plain Concrete Casting

JAH-Z1-ST-S11-MC.110Mass Concrete Casting for Base Slab Top Layer 1 13-Oct-24 13-Oct-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S11-MC.112Curing work 7 14-Oct-24 21-Oct-24 Curing work

JAH-Z1-ST-S11-MC.115Concrete Protective coating 8 22-Oct-24 30-Oct-24 Concrete Protective coating

STA. 0+353 ~ 0+373 123 29-Jun-24 19-Nov-24 19-Nov-24, STA. 0+353 ~ 0+373
BASE SLAB 27 29-Jun-24 29-Jul-24 29-Jul-24, BASE SLAB
JAH-Z1-ST-S12-BS.100Lean Concrete for Base Slab 1 29-Jun-24 29-Jun-24 Lean Concrete for Base Slab

JAH-Z1-ST-S12-BS.105Waterproofing for Lean Concrete 1 30-Jun-24 30-Jun-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S12-BS.110 Base Slab Rebar Installation 8 01-Jul-24 09-Jul-24 Base Slab Rebar Installation

JAH-Z1-ST-S12-BS.115 Base Slab Formwork Installation 7 10-Jul-24 17-Jul-24 Base Slab Formwork Installation

JAH-Z1-ST-S12-BS.120Base Slab Concrete Casting 1 18-Jul-24 18-Jul-24 Base Slab Concrete Casting

JAH-Z1-ST-S12-BS.122Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z1-ST-S12-BS.125Base Slab Formwork Removel 2 28-Jul-24 29-Jul-24 Base Slab Formwork Removel

COLUMN 23 30-Jul-24 25-Aug-24 25-Aug-24, COLUMN


JAH-Z1-ST-S12-CL.100Column Rebar Installation 8 30-Jul-24 07-Aug-24 Column Rebar Installation

JAH-Z1-ST-S12-CL.105Column Formwork Installation 7 08-Aug-24 15-Aug-24 Column Formwork Installation

JAH-Z1-ST-S12-CL.110 Column Concrete Casting 1 17-Aug-24 17-Aug-24 Column Concrete Casting

JAH-Z1-ST-S12-CL.115 Form Work Removal and Curing 7 18-Aug-24 25-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 30-Jul-24 10-Sep-24 10-Sep-24, TUNNEL WALLS


JAH-Z1-ST-S12-TW.100Tunnel Walls Rebar Installation 8 30-Jul-24 07-Aug-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S12-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 30-Jul-24 07-Aug-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S12-TW.110Tunnel Formwork Installation 7 08-Aug-24 15-Aug-24 Tunnel Formwork Installation

JAH-Z1-ST-S12-TW.115Tunnel Walls Concrete Casting 1 17-Aug-24 17-Aug-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S12-TW.117Curing work 7 18-Aug-24 25-Aug-24 Curing work

JAH-Z1-ST-S12-TW.120Tunnel Walls Formwork Removel 2 26-Aug-24 27-Aug-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S12-TW.125Tunnel Wall Waterproofing 12 28-Aug-24 10-Sep-24 Tunnel Wall Waterproofing

TOP SLAB 47 28-Aug-24 22-Oct-24 22-Oct-24, TOP SLAB


JAH-Z1-ST-S12-TS.100 Top Slab Formwork Installation 10 28-Aug-24 08-Sep-24 Top Slab Formwork Installation

JAH-Z1-ST-S12-TS.105 Top Slab Rebar Installation 8 09-Sep-24 17-Sep-24 Top Slab Rebar Installation

JAH-Z1-ST-S12-TS.110 Top Slab Concrete Casting 1 18-Sep-24 18-Sep-24 Top Slab Concrete Casting

JAH-Z1-ST-S12-TS.112 Curing work 7 19-Sep-24 28-Sep-24 Curing work

JAH-Z1-ST-S12-TS.115 Top Slab Formwork Removel 2 29-Sep-24 30-Sep-24 Top Slab Formwork Removel

JAH-Z1-ST-S12-TS.120 Waterproofing for Top Slab 12 09-Oct-24 22-Oct-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 23-Oct-24 19-Nov-24 19-Nov-24, MASS CONCRETE WORK


JAH-Z1-ST-S12-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 23-Oct-24 30-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S12-MC.105Plain Concrete Casting 1 31-Oct-24 31-Oct-24 Plain Concrete Casting

JAH-Z1-ST-S12-MC.110Mass Concrete Casting for Base Slab Top Layer 1 02-Nov-24 02-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S12-MC.112Curing work 7 03-Nov-24 10-Nov-24 Curing work

JAH-Z1-ST-S12-MC.115Concrete Protective coating 8 11-Nov-24 19-Nov-24 Concrete Protective coating

STA. 0+373 ~ 0+393 123 10-Jul-24 01-Dec-24 01-Dec-24, STA. 0+373 ~ 0+393
BASE SLAB 27 10-Jul-24 10-Aug-24 10-Aug-24, BASE SLAB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
223 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S13-BS.100Lean Concrete for Base Slab 1 10-Jul-24 10-Jul-24 Lean Concrete for Base Slab

JAH-Z1-ST-S13-BS.105Waterproofing for Lean Concrete 1 11-Jul-24 11-Jul-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S13-BS.110 Base Slab Rebar Installation 8 13-Jul-24 21-Jul-24 Base Slab Rebar Installation

JAH-Z1-ST-S13-BS.115 Base Slab Formwork Installation 7 22-Jul-24 29-Jul-24 Base Slab Formwork Installation

JAH-Z1-ST-S13-BS.120Base Slab Concrete Casting 1 30-Jul-24 30-Jul-24 Base Slab Concrete Casting

JAH-Z1-ST-S13-BS.122Curing work 7 31-Jul-24 07-Aug-24 Curing work

JAH-Z1-ST-S13-BS.125Base Slab Formwork Removel 2 08-Aug-24 10-Aug-24 Base Slab Formwork Removel

COLUMN 23 11-Aug-24 05-Sep-24 05-Sep-24, COLUMN


JAH-Z1-ST-S13-CL.100Column Rebar Installation 8 11-Aug-24 19-Aug-24 Column Rebar Installation

JAH-Z1-ST-S13-CL.105Column Formwork Installation 7 20-Aug-24 27-Aug-24 Column Formwork Installation

JAH-Z1-ST-S13-CL.110 Column Concrete Casting 1 28-Aug-24 28-Aug-24 Column Concrete Casting

JAH-Z1-ST-S13-CL.115 Form Work Removal and Curing 7 29-Aug-24 05-Sep-24 Form Work Removal and Curing

TUNNEL WALLS 37 11-Aug-24 22-Sep-24 22-Sep-24, TUNNEL WALLS


JAH-Z1-ST-S13-TW.100Tunnel Walls Rebar Installation 8 11-Aug-24 19-Aug-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S13-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-Aug-24 19-Aug-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S13-TW.110Tunnel Formwork Installation 7 20-Aug-24 27-Aug-24 Tunnel Formwork Installation

JAH-Z1-ST-S13-TW.115Tunnel Walls Concrete Casting 1 28-Aug-24 28-Aug-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S13-TW.117Curing work 7 29-Aug-24 05-Sep-24 Curing work

JAH-Z1-ST-S13-TW.120Tunnel Walls Formwork Removel 2 07-Sep-24 08-Sep-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S13-TW.125Tunnel Wall Waterproofing 12 09-Sep-24 22-Sep-24 Tunnel Wall Waterproofing

TOP SLAB 47 09-Sep-24 03-Nov-24 03-Nov-24, TOP SLAB


JAH-Z1-ST-S13-TS.100 Top Slab Formwork Installation 10 09-Sep-24 19-Sep-24 Top Slab Formwork Installation

JAH-Z1-ST-S13-TS.105 Top Slab Rebar Installation 8 21-Sep-24 30-Sep-24 Top Slab Rebar Installation

JAH-Z1-ST-S13-TS.110 Top Slab Concrete Casting 1 01-Oct-24 01-Oct-24 Top Slab Concrete Casting

JAH-Z1-ST-S13-TS.112 Curing work 7 02-Oct-24 09-Oct-24 Curing work

JAH-Z1-ST-S13-TS.115 Top Slab Formwork Removel 2 10-Oct-24 12-Oct-24 Top Slab Formwork Removel

JAH-Z1-ST-S13-TS.120 Waterproofing for Top Slab 12 21-Oct-24 03-Nov-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 04-Nov-24 01-Dec-24 01-Dec-24, MASS CONCRETE WORK


JAH-Z1-ST-S13-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 04-Nov-24 11-Nov-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S13-MC.105Plain Concrete Casting 1 12-Nov-24 12-Nov-24 Plain Concrete Casting

JAH-Z1-ST-S13-MC.110Mass Concrete Casting for Base Slab Top Layer 1 13-Nov-24 13-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S13-MC.112Curing work 7 14-Nov-24 21-Nov-24 Curing work

JAH-Z1-ST-S13-MC.115Concrete Protective coating 8 23-Nov-24 01-Dec-24 Concrete Protective coating

STA. 0+393 ~ 0+413 123 30-Jul-24 21-Dec-24 21-Dec-24, STA. 0+393 ~ 0+413
BASE SLAB 27 30-Jul-24 29-Aug-24 29-Aug-24, BASE SLAB
JAH-Z1-ST-S14-BS.100Lean Concrete for Base Slab 1 30-Jul-24 30-Jul-24 Lean Concrete for Base Slab

JAH-Z1-ST-S14-BS.105Waterproofing for Lean Concrete 1 31-Jul-24 31-Jul-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S14-BS.110 Base Slab Rebar Installation 8 01-Aug-24 10-Aug-24 Base Slab Rebar Installation

JAH-Z1-ST-S14-BS.115 Base Slab Formwork Installation 7 11-Aug-24 18-Aug-24 Base Slab Formwork Installation

JAH-Z1-ST-S14-BS.120Base Slab Concrete Casting 1 19-Aug-24 19-Aug-24 Base Slab Concrete Casting

JAH-Z1-ST-S14-BS.122Curing work 7 20-Aug-24 27-Aug-24 Curing work

JAH-Z1-ST-S14-BS.125Base Slab Formwork Removel 2 28-Aug-24 29-Aug-24 Base Slab Formwork Removel

COLUMN 23 31-Aug-24 26-Sep-24 26-Sep-24, COLUMN


JAH-Z1-ST-S14-CL.100Column Rebar Installation 8 31-Aug-24 08-Sep-24 Column Rebar Installation

JAH-Z1-ST-S14-CL.105Column Formwork Installation 7 09-Sep-24 16-Sep-24 Column Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
224 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S14-CL.110 Column Concrete Casting 1 17-Sep-24 17-Sep-24 Column Concrete Casting

JAH-Z1-ST-S14-CL.115 Form Work Removal and Curing 7 18-Sep-24 26-Sep-24 Form Work Removal and Curing

TUNNEL WALLS 37 31-Aug-24 13-Oct-24 13-Oct-24, TUNNEL WALLS


JAH-Z1-ST-S14-TW.100Tunnel Walls Rebar Installation 8 31-Aug-24 08-Sep-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S14-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 31-Aug-24 08-Sep-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S14-TW.110Tunnel Formwork Installation 7 09-Sep-24 16-Sep-24 Tunnel Formwork Installation

JAH-Z1-ST-S14-TW.115Tunnel Walls Concrete Casting 1 17-Sep-24 17-Sep-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S14-TW.117Curing work 7 18-Sep-24 26-Sep-24 Curing work

JAH-Z1-ST-S14-TW.120Tunnel Walls Formwork Removel 2 28-Sep-24 29-Sep-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S14-TW.125Tunnel Wall Waterproofing 12 30-Sep-24 13-Oct-24 Tunnel Wall Waterproofing

TOP SLAB 47 30-Sep-24 23-Nov-24 23-Nov-24, TOP SLAB


JAH-Z1-ST-S14-TS.100 Top Slab Formwork Installation 10 30-Sep-24 10-Oct-24 Top Slab Formwork Installation

JAH-Z1-ST-S14-TS.105 Top Slab Rebar Installation 8 12-Oct-24 20-Oct-24 Top Slab Rebar Installation

JAH-Z1-ST-S14-TS.110 Top Slab Concrete Casting 1 21-Oct-24 21-Oct-24 Top Slab Concrete Casting

JAH-Z1-ST-S14-TS.112 Curing work 7 22-Oct-24 29-Oct-24 Curing work

JAH-Z1-ST-S14-TS.115 Top Slab Formwork Removel 2 30-Oct-24 31-Oct-24 Top Slab Formwork Removel

JAH-Z1-ST-S14-TS.120 Waterproofing for Top Slab 12 10-Nov-24 23-Nov-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 24-Nov-24 21-Dec-24 21-Dec-24, MASS CONCRETE WORK


JAH-Z1-ST-S14-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 24-Nov-24 01-Dec-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S14-MC.105Plain Concrete Casting 1 02-Dec-24 02-Dec-24 Plain Concrete Casting

JAH-Z1-ST-S14-MC.110Mass Concrete Casting for Base Slab Top Layer 1 03-Dec-24 03-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S14-MC.112Curing work 7 04-Dec-24 11-Dec-24 Curing work

JAH-Z1-ST-S14-MC.115Concrete Protective coating 8 12-Dec-24 21-Dec-24 Concrete Protective coating

STA. 0+413 ~ 0+433 123 11-Aug-24 01-Jan-25 01-Jan-25, STA. 0+413 ~ 0+433
BASE SLAB 27 11-Aug-24 10-Sep-24 10-Sep-24, BASE SLAB
JAH-Z1-ST-S15-BS.100Lean Concrete for Base Slab 1 11-Aug-24 11-Aug-24 Lean Concrete for Base Slab

JAH-Z1-ST-S15-BS.105Waterproofing for Lean Concrete 1 12-Aug-24 12-Aug-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S15-BS.110 Base Slab Rebar Installation 8 13-Aug-24 21-Aug-24 Base Slab Rebar Installation

JAH-Z1-ST-S15-BS.115 Base Slab Formwork Installation 7 22-Aug-24 29-Aug-24 Base Slab Formwork Installation

JAH-Z1-ST-S15-BS.120Base Slab Concrete Casting 1 31-Aug-24 31-Aug-24 Base Slab Concrete Casting

JAH-Z1-ST-S15-BS.122Curing work 7 01-Sep-24 08-Sep-24 Curing work

JAH-Z1-ST-S15-BS.125Base Slab Formwork Removel 2 09-Sep-24 10-Sep-24 Base Slab Formwork Removel

COLUMN 23 11-Sep-24 08-Oct-24 08-Oct-24, COLUMN


JAH-Z1-ST-S15-CL.100Column Rebar Installation 8 11-Sep-24 19-Sep-24 Column Rebar Installation

JAH-Z1-ST-S15-CL.105Column Formwork Installation 7 21-Sep-24 29-Sep-24 Column Formwork Installation

JAH-Z1-ST-S15-CL.110 Column Concrete Casting 1 30-Sep-24 30-Sep-24 Column Concrete Casting

JAH-Z1-ST-S15-CL.115 Form Work Removal and Curing 7 01-Oct-24 08-Oct-24 Form Work Removal and Curing

TUNNEL WALLS 37 11-Sep-24 24-Oct-24 24-Oct-24, TUNNEL WALLS


JAH-Z1-ST-S15-TW.100Tunnel Walls Rebar Installation 8 11-Sep-24 19-Sep-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S15-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-Sep-24 19-Sep-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S15-TW.110Tunnel Formwork Installation 7 21-Sep-24 29-Sep-24 Tunnel Formwork Installation

JAH-Z1-ST-S15-TW.115Tunnel Walls Concrete Casting 1 30-Sep-24 30-Sep-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S15-TW.117Curing work 7 01-Oct-24 08-Oct-24 Curing work

JAH-Z1-ST-S15-TW.120Tunnel Walls Formwork Removel 2 09-Oct-24 10-Oct-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S15-TW.125Tunnel Wall Waterproofing 12 12-Oct-24 24-Oct-24 Tunnel Wall Waterproofing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
225 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 47 12-Oct-24 04-Dec-24 04-Dec-24, TOP SLAB
JAH-Z1-ST-S15-TS.100 Top Slab Formwork Installation 10 12-Oct-24 22-Oct-24 Top Slab Formwork Installation

JAH-Z1-ST-S15-TS.105 Top Slab Rebar Installation 8 23-Oct-24 31-Oct-24 Top Slab Rebar Installation

JAH-Z1-ST-S15-TS.110 Top Slab Concrete Casting 1 02-Nov-24 02-Nov-24 Top Slab Concrete Casting

JAH-Z1-ST-S15-TS.112 Curing work 7 03-Nov-24 10-Nov-24 Curing work

JAH-Z1-ST-S15-TS.115 Top Slab Formwork Removel 2 11-Nov-24 12-Nov-24 Top Slab Formwork Removel

JAH-Z1-ST-S15-TS.120 Waterproofing for Top Slab 12 21-Nov-24 04-Dec-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 05-Dec-24 01-Jan-25 01-Jan-25, MASS CONCRETE WORK


JAH-Z1-ST-S15-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 05-Dec-24 12-Dec-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S15-MC.105Plain Concrete Casting 1 14-Dec-24 14-Dec-24 Plain Concrete Casting

JAH-Z1-ST-S15-MC.110Mass Concrete Casting for Base Slab Top Layer 1 15-Dec-24 15-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S15-MC.112Curing work 7 16-Dec-24 23-Dec-24 Curing work

JAH-Z1-ST-S15-MC.115Concrete Protective coating 8 24-Dec-24 01-Jan-25 Concrete Protective coating

STA. 0+433 ~ 0+453 123 22-Aug-24 13-Jan-25 13-Jan-25, STA. 0+433 ~ 0+453
BASE SLAB 27 22-Aug-24 22-Sep-24 22-Sep-24, BASE SLAB
JAH-Z1-ST-S16-BS.100Lean Concrete for Base Slab 1 22-Aug-24 22-Aug-24 Lean Concrete for Base Slab

JAH-Z1-ST-S16-BS.105Waterproofing for Lean Concrete 1 24-Aug-24 24-Aug-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S16-BS.110 Base Slab Rebar Installation 8 25-Aug-24 02-Sep-24 Base Slab Rebar Installation

JAH-Z1-ST-S16-BS.115 Base Slab Formwork Installation 7 03-Sep-24 10-Sep-24 Base Slab Formwork Installation

JAH-Z1-ST-S16-BS.120Base Slab Concrete Casting 1 11-Sep-24 11-Sep-24 Base Slab Concrete Casting

JAH-Z1-ST-S16-BS.122Curing work 7 12-Sep-24 19-Sep-24 Curing work

JAH-Z1-ST-S16-BS.125Base Slab Formwork Removel 2 21-Sep-24 22-Sep-24 Base Slab Formwork Removel

COLUMN 23 24-Sep-24 20-Oct-24 20-Oct-24, COLUMN


JAH-Z1-ST-S16-CL.100Column Rebar Installation 8 24-Sep-24 02-Oct-24 Column Rebar Installation

JAH-Z1-ST-S16-CL.105Column Formwork Installation 7 03-Oct-24 10-Oct-24 Column Formwork Installation

JAH-Z1-ST-S16-CL.110 Column Concrete Casting 1 12-Oct-24 12-Oct-24 Column Concrete Casting

JAH-Z1-ST-S16-CL.115 Form Work Removal and Curing 7 13-Oct-24 20-Oct-24 Form Work Removal and Curing

TUNNEL WALLS 37 24-Sep-24 05-Nov-24 05-Nov-24, TUNNEL WALLS


JAH-Z1-ST-S16-TW.100Tunnel Walls Rebar Installation 8 24-Sep-24 02-Oct-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S16-TW.105PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 24-Sep-24 02-Oct-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S16-TW.110Tunnel Formwork Installation 7 03-Oct-24 10-Oct-24 Tunnel Formwork Installation

JAH-Z1-ST-S16-TW.115Tunnel Walls Concrete Casting 1 12-Oct-24 12-Oct-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S16-TW.117Curing work 7 13-Oct-24 20-Oct-24 Curing work

JAH-Z1-ST-S16-TW.120Tunnel Walls Formwork Removel 2 21-Oct-24 22-Oct-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S16-TW.125Tunnel Wall Waterproofing 12 23-Oct-24 05-Nov-24 Tunnel Wall Waterproofing

TOP SLAB 47 23-Oct-24 16-Dec-24 16-Dec-24, TOP SLAB


JAH-Z1-ST-S16-TS.100 Top Slab Formwork Installation 10 23-Oct-24 03-Nov-24 Top Slab Formwork Installation

JAH-Z1-ST-S16-TS.105 Top Slab Rebar Installation 8 04-Nov-24 12-Nov-24 Top Slab Rebar Installation

JAH-Z1-ST-S16-TS.110 Top Slab Concrete Casting 1 13-Nov-24 13-Nov-24 Top Slab Concrete Casting

JAH-Z1-ST-S16-TS.112 Curing work 7 14-Nov-24 21-Nov-24 Curing work

JAH-Z1-ST-S16-TS.115 Top Slab Formwork Removel 2 23-Nov-24 24-Nov-24 Top Slab Formwork Removel

JAH-Z1-ST-S16-TS.120 Waterproofing for Top Slab 12 03-Dec-24 16-Dec-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 17-Dec-24 13-Jan-25 13-Jan-25, MASS CONCRETE WORK


JAH-Z1-ST-S16-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 17-Dec-24 24-Dec-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S16-MC.105Plain Concrete Casting 1 25-Dec-24 25-Dec-24 Plain Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
226 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S16-MC.110Mass Concrete Casting for Base Slab Top Layer 1 26-Dec-24 26-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S16-MC.112Curing work 7 28-Dec-24 04-Jan-25 Curing work

JAH-Z1-ST-S16-MC.115Concrete Protective coating 8 05-Jan-25 13-Jan-25 Concrete Protective coating

STA. 0+453 ~ 0+473 176 03-Sep-24 27-Mar-25 27-Mar-25, STA. 0+453 ~ 0+473
BASE SLAB 27 03-Sep-24 05-Oct-24 05-Oct-24, BASE SLAB
JAH-Z1-ST-S17-BS.100Lean Concrete for Base Slab 1 03-Sep-24 03-Sep-24 Lean Concrete for Base Slab

JAH-Z1-ST-S17-BS.105Waterproofing for Lean Concrete 1 04-Sep-24 04-Sep-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S17-BS.110 Base Slab Rebar Installation 8 05-Sep-24 14-Sep-24 Base Slab Rebar Installation

JAH-Z1-ST-S17-BS.115 Base Slab Formwork Installation 7 15-Sep-24 22-Sep-24 Base Slab Formwork Installation

JAH-Z1-ST-S17-BS.120Base Slab Concrete Casting 1 24-Sep-24 24-Sep-24 Base Slab Concrete Casting

JAH-Z1-ST-S17-BS.122Curing work 7 25-Sep-24 02-Oct-24 Curing work

JAH-Z1-ST-S17-BS.125Base Slab Formwork Removel 2 03-Oct-24 05-Oct-24 Base Slab Formwork Removel

COLUMN 23 06-Oct-24 31-Oct-24 31-Oct-24, COLUMN


JAH-Z1-ST-S17-CL.100Column Rebar Installation 8 06-Oct-24 14-Oct-24 Column Rebar Installation

JAH-Z1-ST-S17-CL.105Column Formwork Installation 7 15-Oct-24 22-Oct-24 Column Formwork Installation

JAH-Z1-ST-S17-CL.110 Column Concrete Casting 1 23-Oct-24 23-Oct-24 Column Concrete Casting

JAH-Z1-ST-S17-CL.115 Form Work Removal and Curing 7 24-Oct-24 31-Oct-24 Form Work Removal and Curing

TUNNEL WALLS 45 06-Oct-24 26-Nov-24 26-Nov-24, TUNNEL WALLS


JAH-Z1-ST-S17-TW.100Tunnel Walls Rebar Installation 8 06-Oct-24 14-Oct-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S17-TW.104PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 15-Oct-24 23-Oct-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S17-TW.105Tunnel Formwork Installation 7 24-Oct-24 31-Oct-24 Tunnel Formwork Installation

JAH-Z1-ST-S17-TW.110Tunnel Walls Concrete Casting 1 02-Nov-24 02-Nov-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S17-TW.112Curing work 7 03-Nov-24 10-Nov-24 Curing work

JAH-Z1-ST-S17-TW.120Tunnel Walls Formwork Removel 2 11-Nov-24 12-Nov-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S17-TW.125Tunnel Wall Waterproofing 12 13-Nov-24 26-Nov-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 13-Nov-24 17-Dec-24 17-Dec-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z1-ST-S17-MS.090Middle Slab Scaffold and Formwork Installation 5 13-Nov-24 18-Nov-24 Middle Slab Scaffold and Formwork Installation

JAH-Z1-ST-S17-MS.100Middle Slab Rebar Installation 8 19-Nov-24 27-Nov-24 Middle Slab Rebar Installation

JAH-Z1-ST-S17-MS.105Middle Slab Vertical Formwork Installation 7 28-Nov-24 05-Dec-24 Middle Slab Vertical Formwork Installation

JAH-Z1-ST-S17-MS.110Middle Slab Concrete Casting 1 07-Dec-24 07-Dec-24 Middle Slab Concrete Casting

JAH-Z1-ST-S17-MS.115Curing work 7 08-Dec-24 15-Dec-24 Curing work

JAH-Z1-ST-S17-MS.120Middle Slab Formwork Removel 2 16-Dec-24 17-Dec-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 18-Dec-24 15-Jan-25 15-Jan-25, UTILITY CULVERT WALLS


JAH-Z1-ST-S17-CW.100Utility Culvert Walls Rebar Installation 8 18-Dec-24 26-Dec-24 Utility Culvert Walls Rebar Installation

JAH-Z1-ST-S17-CW.105Utility Culvert Walls Formwork Installation 7 28-Dec-24 04-Jan-25 Utility Culvert Walls Formwork Installation

JAH-Z1-ST-S17-CW.110Utility Culvert Walls Concrete Casting 1 05-Jan-25 05-Jan-25 Utility Culvert Walls Concrete Casting

JAH-Z1-ST-S17-CW.112Curing work 7 06-Jan-25 13-Jan-25 Curing work

JAH-Z1-ST-S17-CW.115Utility Culvert Walls Walls Formwork Removel 2 14-Jan-25 15-Jan-25 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 16-Jan-25 27-Feb-25 27-Feb-25, TOP SLAB


JAH-Z1-ST-S17-TS.100 Top Slab Rebar Installation 8 16-Jan-25 25-Jan-25 Top Slab Rebar Installation

JAH-Z1-ST-S17-TS.105 Top Slab Formwork Installation 7 26-Jan-25 02-Feb-25 Top Slab Formwork Installation

JAH-Z1-ST-S17-TS.110 Top Slab Concrete Casting 1 03-Feb-25 03-Feb-25 Top Slab Concrete Casting

JAH-Z1-ST-S17-TS.112 Curing work 7 04-Feb-25 11-Feb-25 Curing work

JAH-Z1-ST-S17-TS.115 Top Slab Formwork Removel 2 12-Feb-25 13-Feb-25 Top Slab Formwork Removel

JAH-Z1-ST-S17-TS.120 Waterproofing for Top Slab 12 15-Feb-25 27-Feb-25 Waterproofing for Top Slab

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
227 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
MASS CONCRETE WORK 24 01-Mar-25 27-Mar-25 27-Mar-25, MASS CONCRETE WORK
JAH-Z1-ST-S17-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 01-Mar-25 08-Mar-25 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S17-MC.105Plain Concrete Casting 1 09-Mar-25 09-Mar-25 Plain Concrete Casting

JAH-Z1-ST-S17-MC.110Mass Concrete Casting for Base Slab Top Layer 1 10-Mar-25 10-Mar-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S17-MC.112Curing work 7 11-Mar-25 18-Mar-25 Curing work

JAH-Z1-ST-S17-MC.115Concrete Protective coating 8 19-Mar-25 27-Mar-25 Concrete Protective coating

STA. 0+473 ~ 0+500 166 24-Sep-24 09-Apr-25 09-Apr-25, STA. 0+473 ~ 0+500
BASE SLAB 27 24-Sep-24 24-Oct-24 24-Oct-24, BASE SLAB
JAH-Z1-ST-S18-BS.100Lean Concrete for Base Slab 1 24-Sep-24 24-Sep-24 Lean Concrete for Base Slab

JAH-Z1-ST-S18-BS.105Waterproofing for Lean Concrete 1 25-Sep-24 25-Sep-24 Waterproofing for Lean Concrete

JAH-Z1-ST-S18-BS.110 Base Slab Rebar Installation 8 26-Sep-24 05-Oct-24 Base Slab Rebar Installation

JAH-Z1-ST-S18-BS.115 Base Slab Formwork Installation 7 06-Oct-24 13-Oct-24 Base Slab Formwork Installation

JAH-Z1-ST-S18-BS.120Base Slab Concrete Casting 1 14-Oct-24 14-Oct-24 Base Slab Concrete Casting

JAH-Z1-ST-S18-BS.122Curing work 7 15-Oct-24 22-Oct-24 Curing work

JAH-Z1-ST-S18-BS.125Base Slab Formwork Removel 2 23-Oct-24 24-Oct-24 Base Slab Formwork Removel

COLUMN 23 26-Oct-24 20-Nov-24 20-Nov-24, COLUMN


JAH-Z1-ST-S18-CL.100Column Rebar Installation 8 26-Oct-24 03-Nov-24 Column Rebar Installation

JAH-Z1-ST-S18-CL.105Column Formwork Installation 7 04-Nov-24 11-Nov-24 Column Formwork Installation

JAH-Z1-ST-S18-CL.110 Column Concrete Casting 1 12-Nov-24 12-Nov-24 Column Concrete Casting

JAH-Z1-ST-S18-CL.115 Form Work Removal and Curing 7 13-Nov-24 20-Nov-24 Form Work Removal and Curing

TUNNEL WALLS 37 26-Oct-24 07-Dec-24 07-Dec-24, TUNNEL WALLS


JAH-Z1-ST-S18-TW.100Tunnel Walls Rebar Installation 8 26-Oct-24 03-Nov-24 Tunnel Walls Rebar Installation

JAH-Z1-ST-S18-TW.104PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 26-Oct-24 03-Nov-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z1-ST-S18-TW.105Tunnel Formwork Installation 7 04-Nov-24 11-Nov-24 Tunnel Formwork Installation

JAH-Z1-ST-S18-TW.110Tunnel Walls Concrete Casting 1 12-Nov-24 12-Nov-24 Tunnel Walls Concrete Casting

JAH-Z1-ST-S18-TW.112Curing work 7 13-Nov-24 20-Nov-24 Curing work

JAH-Z1-ST-S18-TW.120Tunnel Walls Formwork Removel 2 21-Nov-24 23-Nov-24 Tunnel Walls Formwork Removel

JAH-Z1-ST-S18-TW.125Tunnel Wall Waterproofing 12 24-Nov-24 07-Dec-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 31 24-Nov-24 29-Dec-24 29-Dec-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z1-ST-S18-MS.090Middle Slab Scaffold and Formwork Installation 5 24-Nov-24 28-Nov-24 Middle Slab Scaffold and Formwork Installation

JAH-Z1-ST-S18-MS.100Middle Slab Rebar Installation 8 30-Nov-24 08-Dec-24 Middle Slab Rebar Installation

JAH-Z1-ST-S18-MS.105Middle Slab Vertical Formwork Installation 7 09-Dec-24 16-Dec-24 Middle Slab Vertical Formwork Installation

JAH-Z1-ST-S18-MS.110Middle Slab Concrete Casting 1 17-Dec-24 17-Dec-24 Middle Slab Concrete Casting

JAH-Z1-ST-S18-MS.115Curing work 7 18-Dec-24 25-Dec-24 Curing work

JAH-Z1-ST-S18-MS.120Middle Slab Formwork Removel 3 26-Dec-24 29-Dec-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 26-Dec-24 23-Jan-25 23-Jan-25, UTILITY CULVERT WALLS


JAH-Z1-ST-S18-CW.100Utility Culvert Walls Rebar Installation 8 26-Dec-24 04-Jan-25 Utility Culvert Walls Rebar Installation

JAH-Z1-ST-S18-CW.105Utility Culvert Walls Formwork Installation 7 05-Jan-25 12-Jan-25 Utility Culvert Walls Formwork Installation

JAH-Z1-ST-S18-CW.110Utility Culvert Walls Concrete Casting 1 13-Jan-25 13-Jan-25 Utility Culvert Walls Concrete Casting

JAH-Z1-ST-S18-CW.112Curing work 7 14-Jan-25 21-Jan-25 Curing work

JAH-Z1-ST-S18-CW.115Utility Culvert Walls Walls Formwork Removel 2 22-Jan-25 23-Jan-25 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 25-Jan-25 08-Mar-25 08-Mar-25, TOP SLAB


JAH-Z1-ST-S18-TS.100 Top Slab Rebar Installation 8 25-Jan-25 02-Feb-25 Top Slab Rebar Installation

JAH-Z1-ST-S18-TS.105 Top Slab Formwork Installation 7 03-Feb-25 10-Feb-25 Top Slab Formwork Installation

JAH-Z1-ST-S18-TS.110 Top Slab Concrete Casting 1 11-Feb-25 11-Feb-25 Top Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
228 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-ST-S18-TS.112 Curing work 7 12-Feb-25 19-Feb-25 Curing work

JAH-Z1-ST-S18-TS.115 Top Slab Formwork Removel 2 20-Feb-25 22-Feb-25 Top Slab Formwork Removel

JAH-Z1-ST-S18-TS.120 Waterproofing for Top Slab 12 23-Feb-25 08-Mar-25 Waterproofing for Top Slab

MASS CONCRETE WORK 24 09-Mar-25 09-Apr-25 09-Apr-25, MASS CONCRETE WORK


JAH-Z1-ST-S18-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 09-Mar-25 16-Mar-25 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z1-ST-S18-MC.105Plain Concrete Casting 1 17-Mar-25 17-Mar-25 Plain Concrete Casting

JAH-Z1-ST-S18-MC.110Mass Concrete Casting for Base Slab Top Layer 1 18-Mar-25 18-Mar-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z1-ST-S18-MC.112Curing work 7 19-Mar-25 26-Mar-25 Curing work

JAH-Z1-ST-S18-MC.115Concrete Protective coating 8 27-Mar-25 09-Apr-25 Concrete Protective coating

WET CULVERT 262 12-Feb-24 22-Dec-24 22-Dec-24, WET CULVERT


Sta 0+000-0+369.618 - @ZONE 1 262 12-Feb-24 22-Dec-24 22-Dec-24, Sta 0+000-0+369.618 - @ZONE 1
1st Sta 0+000-0+200 161 12-Feb-24 25-Aug-24 25-Aug-24, 1st Sta 0+000-0+200
BASE SLAB 95 12-Feb-24 04-Jun-24 04-Jun-24, BASE SLAB
CUL-WT-Z1-ST1-BS.100
Lean concrete for Base slab 10 12-Feb-24 22-Feb-24 Lean concrete for Base slab

CUL-WT-Z1-ST1-BS.105
Waterproofing for Lean concrete 15 24-Feb-24 11-Mar-24 Waterproofing for Lean concrete

CUL-WT-Z1-ST1-BS.110
Base slab Rebar installation 35 12-Mar-24 24-Apr-24 Base slab Rebar installation

CUL-WT-Z1-ST1-BS.115
Base slab formwork Installation 21 25-Apr-24 19-May-24 Base slab formwork Installation

CUL-WT-Z1-ST1-BS.120
Base slab concrete casting 7 20-May-24 27-May-24 Base slab concrete casting

CUL-WT-Z1-ST1-BS.125
Base Slab Formwork Removel, Curing & Strength Gaining 7 28-May-24 04-Jun-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 63 25-Apr-24 11-Jul-24 11-Jul-24, CULVERT WALL


CUL-WT-Z1-ST1-CW.100
Culvert Wall Rebar installation 25 25-Apr-24 23-May-24 Culvert Wall Rebar installation

CUL-WT-Z1-ST1-CW.105
Culvert Wall Formwork Installation 14 25-May-24 09-Jun-24 Culvert Wall Formwork Installation

CUL-WT-Z1-ST1-CW.110
Culvert Wall concrete casting 7 10-Jun-24 22-Jun-24 Culvert Wall concrete casting

CUL-WT-Z1-ST1-CW.115
Culvert Walls Formwork Removel and Curing 7 23-Jun-24 30-Jun-24 Culvert Walls Formwork Removel and Curing

CUL-WT-Z1-ST1-CW.120
Waterproofing for Culvert wall 10 01-Jul-24 11-Jul-24 Waterproofing for Culvert wall

TOP SLAB 62 10-Jun-24 25-Aug-24 25-Aug-24, TOP SLAB


CUL-WT-Z1-ST1-TS.100
Top Slab Scaffold and Bottom Formwork installation 21 10-Jun-24 08-Jul-24 Top Slab Scaffold and Bottom Formwork installation

CUL-WT-Z1-ST1-TS.105
Top slab Rebar installation 12 09-Jul-24 22-Jul-24 Top slab Rebar installation

CUL-WT-Z1-ST1-TS.110
Top slab Vertical formwork installation 7 23-Jul-24 30-Jul-24 Top slab Vertical formwork installation

CUL-WT-Z1-ST1-TS.115
Top slab concrete casting 7 31-Jul-24 07-Aug-24 Top slab concrete casting

CUL-WT-Z1-ST1-TS.120
Top Slab Formwork Removel and Curing 5 08-Aug-24 13-Aug-24 Top Slab Formwork Removel and Curing

CUL-WT-Z1-ST1-TS.125
Waterproofing of Top slab 10 14-Aug-24 25-Aug-24 Waterproofing of Top slab

PLAIN CONCRETE 9 31-Jul-24 10-Aug-24 10-Aug-24, PLAIN CONCRETE


CUL-WT-Z1-ST1-PC.100
Plain concrete formwork installation 5 31-Jul-24 05-Aug-24 Plain concrete formwork installation

CUL-WT-Z1-ST1-PC.105
Plain concrete 4 06-Aug-24 10-Aug-24 Plain concrete

FINISHING 10 11-Aug-24 21-Aug-24 21-Aug-24, FINISHING


CUL-WT-Z1-ST1-FN.100
Concrete Protective coating 10 11-Aug-24 21-Aug-24 Concrete Protective coating

2nd Sta 0+200-0+369.618 156 23-Jun-24 22-Dec-24 22-Dec-24, 2nd Sta 0+200-0+369.618
BASE SLAB 90 23-Jun-24 06-Oct-24 06-Oct-24, BASE SLAB
CUL-WT-Z1-ST2-BS.100
Lean concrete for Base slab 9 23-Jun-24 02-Jul-24 Lean concrete for Base slab

CUL-WT-Z1-ST2-BS.105
Waterproofing for Lean concrete 14 03-Jul-24 18-Jul-24 Waterproofing for Lean concrete

CUL-WT-Z1-ST2-BS.110
Base slab Rebar installation 33 20-Jul-24 26-Aug-24 Base slab Rebar installation

CUL-WT-Z1-ST2-BS.115
Base slab formwork Installation 20 27-Aug-24 18-Sep-24 Base slab formwork Installation

CUL-WT-Z1-ST2-BS.120
Base slab concrete casting 7 19-Sep-24 28-Sep-24 Base slab concrete casting

CUL-WT-Z1-ST2-BS.125
Base Slab Formwork Removel, Curing & Strength Gaining 7 29-Sep-24 06-Oct-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 62 27-Aug-24 07-Nov-24 07-Nov-24, CULVERT WALL


CUL-WT-Z1-ST2-CW.100
Culvert Wall Rebar installation 24 27-Aug-24 24-Sep-24 Culvert Wall Rebar installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
229 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CUL-WT-Z1-ST2-CW.105
Culvert Wall Formwork Installation 14 25-Sep-24 10-Oct-24 Culvert Wall Formwork Installation

CUL-WT-Z1-ST2-CW.110
Culvert Wall concrete casting 7 12-Oct-24 19-Oct-24 Culvert Wall concrete casting

CUL-WT-Z1-ST2-CW.115
Culvert Walls Formwork Removel and Curing 7 20-Oct-24 27-Oct-24 Culvert Walls Formwork Removel and Curing

CUL-WT-Z1-ST2-CW.120
Waterproofing for Culvert wall 10 28-Oct-24 07-Nov-24 Waterproofing for Culvert wall

TOP SLAB 62 12-Oct-24 22-Dec-24 22-Dec-24, TOP SLAB


CUL-WT-Z1-ST2-TS.100
Top Slab Scaffold and Bottom Formwork installation 21 12-Oct-24 04-Nov-24 Top Slab Scaffold and Bottom Formwork installation

CUL-WT-Z1-ST2-TS.105
Top slab Rebar installation 12 05-Nov-24 18-Nov-24 Top slab Rebar installation

CUL-WT-Z1-ST2-TS.110
Top slab Vertical formwork installation 7 19-Nov-24 26-Nov-24 Top slab Vertical formwork installation

CUL-WT-Z1-ST2-TS.115
Top slab concrete casting 7 27-Nov-24 04-Dec-24 Top slab concrete casting

CUL-WT-Z1-ST2-TS.120
Top Slab Formwork Removel and Curing 5 05-Dec-24 10-Dec-24 Top Slab Formwork Removel and Curing

CUL-WT-Z1-ST2-TS.125
Waterproofing of Top slab 10 11-Dec-24 22-Dec-24 Waterproofing of Top slab

PLAIN CONCRETE 9 27-Nov-24 07-Dec-24 07-Dec-24, PLAIN CONCRETE


CUL-WT-Z1-ST2-PC.100
Plain concrete formwork installation 5 27-Nov-24 02-Dec-24 Plain concrete formwork installation

CUL-WT-Z1-ST2-PC.105
Plain concrete 4 03-Dec-24 07-Dec-24 Plain concrete

FINISHING 10 08-Dec-24 18-Dec-24 18-Dec-24, FINISHING


CUL-WT-Z1-ST2-FN.100
Concrete Protective coating 10 08-Dec-24 18-Dec-24 Concrete Protective coating

DRY CULVERT ZONE 1 268 20-May-24 07-Apr-25 07-Apr-25, DRY CULVERT ZONE 1
DRY CULVERT D91 - @ZONE 1 215 20-May-24 30-Jan-25 30-Jan-25, DRY CULVERT D91 - @ZONE 1
BASE SLAB 91 20-May-24 07-Sep-24 07-Sep-24, BASE SLAB
CUL-DR-Z1-D91-BS.100Lean concrete for Base slab 9 20-May-24 29-May-24 Lean concrete for Base slab

CUL-DR-Z1-D91-BS.105Waterproofing for Lean concrete 14 30-May-24 19-Jun-24 Waterproofing for Lean concrete

CUL-DR-Z1-D91-BS.110Base slab Rebar installation 39 20-Jun-24 04-Aug-24 Base slab Rebar installation

CUL-DR-Z1-D91-BS.115Base slab formwork Installation 16 05-Aug-24 22-Aug-24 Base slab formwork Installation

CUL-DR-Z1-D91-BS.120Base slab concrete casting 7 24-Aug-24 31-Aug-24 Base slab concrete casting

CUL-DR-Z1-D91-BS.125Base Slab Formwork Removel, Curing & Strength Gaining 6 01-Sep-24 07-Sep-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 76 24-Aug-24 20-Nov-24 20-Nov-24, CULVERT WALL


CUL-DR-Z1-D91-CW.100
Culvert Wall Rebar installation 29 24-Aug-24 26-Sep-24 Culvert Wall Rebar installation

CUL-DR-Z1-D91-CW.105
Culvert Wall Formwork Installation 18 28-Sep-24 17-Oct-24 Culvert Wall Formwork Installation

CUL-DR-Z1-D91-CW.110
Culvert Wall concrete casting 10 19-Oct-24 29-Oct-24 Culvert Wall concrete casting

CUL-DR-Z1-D91-CW.115
Culvert Walls Formwork Removel and Curing 7 30-Oct-24 06-Nov-24 Culvert Walls Formwork Removel and Curing

CUL-DR-Z1-D91-CW.120
Waterproofing for Culvert wall 12 07-Nov-24 20-Nov-24 Waterproofing for Culvert wall

TOP SLAB 61 30-Oct-24 08-Jan-25 08-Jan-25, TOP SLAB


CUL-DR-Z1-D91-TS.100Top Slab Scaffold and Bottom Formwork installation 19 30-Oct-24 20-Nov-24 Top Slab Scaffold and Bottom Formwork installation

CUL-DR-Z1-D91-TS.105Top slab Rebar installation 14 21-Nov-24 07-Dec-24 Top slab Rebar installation

CUL-DR-Z1-D91-TS.110Top slab Vertical formwork installation 6 08-Dec-24 14-Dec-24 Top slab Vertical formwork installation

CUL-DR-Z1-D91-TS.115Top slab concrete casting 7 15-Dec-24 22-Dec-24 Top slab concrete casting

CUL-DR-Z1-D91-TS.120Top Slab Formwork Removel and Curing 5 23-Dec-24 28-Dec-24 Top Slab Formwork Removel and Curing

CUL-DR-Z1-D91-TS.125Waterproofing of Top slab 10 29-Dec-24 08-Jan-25 Waterproofing of Top slab

PLAIN CONCRETE 9 09-Jan-25 19-Jan-25 19-Jan-25, PLAIN CONCRETE


CUL-DR-Z1-D91-PC.100Plain concrete formwork installation 6 09-Jan-25 15-Jan-25 Plain concrete formwork installation

CUL-DR-Z1-D91-PC.105Plain concrete 3 16-Jan-25 19-Jan-25 Plain concrete

FINISHING 10 20-Jan-25 30-Jan-25 30-Jan-25, FINISHING


CUL-DR-Z1-D91-FN.100Concrete Protective coating 10 20-Jan-25 30-Jan-25 Concrete Protective coating

Sta0+000-Sta0+149.628 - @ZONE 1 190 24-Aug-24 07-Apr-25 07-Apr-25, Sta0+000-Sta0+149.628 - @ZONE 1


BASE SLAB 101 24-Aug-24 19-Dec-24 19-Dec-24, BASE SLAB
CULV-WT-ST1-BS.280 Lean concrete for Base slab 11 24-Aug-24 04-Sep-24 Lean concrete for Base slab

CULV-WT-ST1-BS.285 Waterproofing for Lean concrete 16 05-Sep-24 24-Sep-24 Waterproofing for Lean concrete

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
230 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-WT-ST1-BS.290 Base slab Rebar installation 37 25-Sep-24 06-Nov-24 Base slab Rebar installation

CULV-WT-ST1-BS.295 Base slab formwork Installation 23 07-Nov-24 03-Dec-24 Base slab formwork Installation

CULV-WT-ST1-BS.300 Base slab concrete casting 7 04-Dec-24 11-Dec-24 Base slab concrete casting

CULV-WT-ST1-BS.305 Base Slab Formwork Removel, Curing & Strength Gaining 7 12-Dec-24 19-Dec-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 68 07-Nov-24 25-Jan-25 25-Jan-25, CULVERT WALL


CULV-WT-ST1-CW.250 Culvert Wall Rebar installation 27 07-Nov-24 08-Dec-24 Culvert Wall Rebar installation

CULV-WT-ST1-CW.255 Culvert Wall Formwork Installation 17 09-Dec-24 28-Dec-24 Culvert Wall Formwork Installation

CULV-WT-ST1-CW.260 Culvert Wall concrete casting 7 29-Dec-24 05-Jan-25 Culvert Wall concrete casting

CULV-WT-ST1-CW.265 Culvert Walls Formwork Removel and Curing 7 06-Jan-25 13-Jan-25 Culvert Walls Formwork Removel and Curing

CULV-WT-ST1-CW.270 Waterproofing for Culvert wall 10 14-Jan-25 25-Jan-25 Waterproofing for Culvert wall

TOP SLAB 61 29-Dec-24 09-Mar-25 09-Mar-25, TOP SLAB


CULV-WT-ST1-TS.280 Top Slab Scaffold and Bottom Formwork installation 19 29-Dec-24 19-Jan-25 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST1-TS.285 Top slab Rebar installation 12 20-Jan-25 02-Feb-25 Top slab Rebar installation

CULV-WT-ST1-TS.290 Top slab Vertical formwork installation 7 03-Feb-25 10-Feb-25 Top slab Vertical formwork installation

CULV-WT-ST1-TS.295 Top slab concrete casting 7 11-Feb-25 18-Feb-25 Top slab concrete casting

CULV-WT-ST1-TS.300 Top Slab Formwork Removel and Curing 6 19-Feb-25 25-Feb-25 Top Slab Formwork Removel and Curing

CULV-WT-ST1-TS.305 Waterproofing of Top slab 10 26-Feb-25 09-Mar-25 Waterproofing of Top slab

PLAIN CONCRETE 7 10-Mar-25 17-Mar-25 17-Mar-25, PLAIN CONCRETE


CULV-WT-ST1-PC.160 Plain concrete formwork installation 5 10-Mar-25 15-Mar-25 Plain concrete formwork installation

CULV-WT-ST1-PC.165 Plain concrete 2 16-Mar-25 17-Mar-25 Plain concrete

FINISHING 14 18-Mar-25 07-Apr-25 07-Apr-25, FINISHING


CULV-WT-ST1-FN.130 Concrete Protective coating 14 18-Mar-25 07-Apr-25 Concrete Protective coating

DRY CULVERT D92 - @ZONE 1 151 24-Aug-24 16-Feb-25 16-Feb-25, DRY CULVERT D92 - @ZONE 1
BASE SLAB 73 24-Aug-24 17-Nov-24 17-Nov-24, BASE SLAB
CUL-DR-Z1-D92-BS.100Lean concrete for Base slab 7 24-Aug-24 31-Aug-24 Lean concrete for Base slab

CUL-DR-Z1-D92-BS.105Waterproofing for Lean concrete 11 01-Sep-24 12-Sep-24 Waterproofing for Lean concrete

CUL-DR-Z1-D92-BS.110Base slab Rebar installation 29 14-Sep-24 17-Oct-24 Base slab Rebar installation

CUL-DR-Z1-D92-BS.115Base slab formwork Installation 16 19-Oct-24 05-Nov-24 Base slab formwork Installation

CUL-DR-Z1-D92-BS.120Base slab concrete casting 4 06-Nov-24 10-Nov-24 Base slab concrete casting

CUL-DR-Z1-D92-BS.125Base Slab Formwork Removel, Curing & Strength Gaining 6 11-Nov-24 17-Nov-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 72 19-Oct-24 09-Jan-25 09-Jan-25, CULVERT WALL


CUL-DR-Z1-D92-CW.100
Culvert Wall Rebar installation 29 19-Oct-24 20-Nov-24 Culvert Wall Rebar installation

CUL-DR-Z1-D92-CW.105
Culvert Wall Formwork Installation 16 21-Nov-24 09-Dec-24 Culvert Wall Formwork Installation

CUL-DR-Z1-D92-CW.110
Culvert Wall concrete casting 8 10-Dec-24 18-Dec-24 Culvert Wall concrete casting

CUL-DR-Z1-D92-CW.115
Culvert Walls Formwork Removel and Curing 8 19-Dec-24 28-Dec-24 Culvert Walls Formwork Removel and Curing

CUL-DR-Z1-D92-CW.120
Waterproofing for Culvert wall 11 29-Dec-24 09-Jan-25 Waterproofing for Culvert wall

TOP SLAB 47 10-Dec-24 02-Feb-25 02-Feb-25, TOP SLAB


CUL-DR-Z1-D92-TS.100Top Slab Scaffold and Bottom Formwork installation 17 10-Dec-24 29-Dec-24 Top Slab Scaffold and Bottom Formwork installation

CUL-DR-Z1-D92-TS.105Top slab Rebar installation 11 30-Dec-24 11-Jan-25 Top slab Rebar installation

CUL-DR-Z1-D92-TS.110Top slab Vertical formwork installation 6 12-Jan-25 18-Jan-25 Top slab Vertical formwork installation

CUL-DR-Z1-D92-TS.115Top slab concrete casting 3 19-Jan-25 21-Jan-25 Top slab concrete casting

CUL-DR-Z1-D92-TS.120Top Slab Formwork Removel and Curing 4 22-Jan-25 26-Jan-25 Top Slab Formwork Removel and Curing

CUL-DR-Z1-D92-TS.125Waterproofing of Top slab 6 27-Jan-25 02-Feb-25 Waterproofing of Top slab

PLAIN CONCRETE 7 27-Jan-25 03-Feb-25 03-Feb-25, PLAIN CONCRETE


CUL-DR-Z1-D92-PC.100Plain concrete formwork installation 5 27-Jan-25 01-Feb-25 Plain concrete formwork installation

CUL-DR-Z1-D92-PC.105Plain concrete 2 02-Feb-25 03-Feb-25 Plain concrete

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
231 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
FINISHING 11 04-Feb-25 16-Feb-25 16-Feb-25, FINISHING
CUL-DR-Z1-D92-FN.100Concrete Protective coating 11 04-Feb-25 16-Feb-25 Concrete Protective coating

BACKFILLING UPTO TUNNELWALL 239 18-Mar-24 30-Dec-24 30-Dec-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z1-CON-BF.125 Backfilling & Compaction @ 0+133 ~ 0+200 15 18-Mar-24 03-Apr-24 Backfilling & Compaction @ 0+133 ~ 0+200

JAH-Z1-CON-BF.130 Backfilling & Compaction @ 0+200 ~ 0+300 20 03-Jul-24 25-Jul-24 Backfilling & Compaction @ 0+200 ~ 0+300

JAH-Z1-CON-BF.135 Backfilling & Compaction @ 0+300 ~ 0+400 20 24-Sep-24 16-Oct-24 Backfilling & Compaction @ 0+300 ~ 0+400

JAH-Z1-CON-BF.140 Backfilling & Compaction @ 0+400 ~ 0+500 20 08-Dec-24 30-Dec-24 Backfilling & Compaction @ 0+400 ~ 0+500

STRUCTURAL FILL 465 02-Jul-24 06-Jan-26 06-Jan-26, STRUCTURAL FILL


JAH-Z1-SF-IL.100 Backfilling & Compaction at Invert Level @ 0+133 ~ 0+200 20 02-Jul-24 24-Jul-24 Backfilling & Compaction at Invert Level @ 0+133 ~ 0+200

JAH-Z1-SF-IL.105 Backfilling & Compaction at Invert Level @ 0+200 ~ 0+300 20 12-Oct-24 03-Nov-24 Backfilling & Compaction at Invert Level @ 0+200 ~ 0+300

JAH-Z1-SF-IL.110 Backfilling & Compaction at Invert Level @ 0+300 ~ 0+400 20 02-Jan-25 25-Jan-25 Backfilling & Compaction at Invert Level @ 0+300 ~ 0+400

JAH-Z1-SF-IL.115 Backfilling & Compaction at Invert Level @ 0+400 ~ 0+500 20 14-Dec-25 06-Jan-26 Backfilling & Compaction at Invert Level @ 0+400 ~ 0+500

WET & DRY UTILITIES 133 10-Apr-25 15-Sep-25 15-Sep-25, WET & DRY UTILITIES
INSIDE WET CULVERT 133 10-Apr-25 15-Sep-25 15-Sep-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 59 10-Apr-25 21-Jun-25 21-Jun-25, POTABLE WATER NETWORK
JAH-Z1-IWU-PWN.100Pipe Supports Installation 25 10-Apr-25 08-May-25 Pipe Supports Installation

JAH-Z1-IWU-PWN.105Pipe Installation alongwith Valves, Fittings & Accessories 30 10-May-25 16-Jun-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-PWN.110Testing 4 17-Jun-25 21-Jun-25 Testing

GREY WATER DISTRIBUTION SYSTEM 49 10-May-25 08-Jul-25 08-Jul-25, GREY WATER DISTRIBUTION SYSTEM
JAH-Z1-IWU-GWD.210Pipe Supports Installation 20 10-May-25 01-Jun-25 Pipe Supports Installation

JAH-Z1-IWU-GWD.215Pipe Installation alongwith Valves, Fittings & Accessories 25 02-Jun-25 03-Jul-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-GWD.220Testing 4 05-Jul-25 08-Jul-25 Testing

IRRIGATION NETWORK 78 10-Apr-25 13-Jul-25 13-Jul-25, IRRIGATION NETWORK


JAH-Z1-IWU-IN.540 Pipe Supports Installation 20 10-Apr-25 03-May-25 Pipe Supports Installation

JAH-Z1-IWU-IN.545 Pipe Installation alongwith Valves, Fittings & Accessories 25 04-May-25 01-Jun-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-IN.570 Testing 4 09-Jul-25 13-Jul-25 Testing

CHILLED WATER SUPPLY NETWORK 59 02-Jun-25 12-Aug-25 12-Aug-25, CHILLED WATER SUPPLY NETWORK
JAH-Z1-IWU-CWS.100 Pipe Supports Installation 25 02-Jun-25 03-Jul-25 Pipe Supports Installation

JAH-Z1-IWU-CWS.105 Pipe Installation alongwith Valves, Fittings & Accessories 30 05-Jul-25 07-Aug-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-CWS.110 Testing 4 09-Aug-25 12-Aug-25 Testing

CHILLED WATER RETURN NETWORK 59 05-Jul-25 10-Sep-25 10-Sep-25, CHILLED WATER RETURN NETWORK
JAH-Z1-IWU-CWR.100Pipe Supports Installation 25 05-Jul-25 02-Aug-25 Pipe Supports Installation

JAH-Z1-IWU-CWR.105Pipe Installation alongwith Valves, Fittings & Accessories 30 03-Aug-25 06-Sep-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-CWR.110Testing 4 07-Sep-25 10-Sep-25 Testing

AUTOMATIC WASTE COLLECTION NETWORK 108 10-May-25 15-Sep-25 15-Sep-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z1-IWU-AWC.100Pipe Supports Installation 25 10-May-25 10-Jun-25 Pipe Supports Installation

JAH-Z1-IWU-AWC.105Pipe Installation alongwith Valves, Fittings & Accessories 30 11-Jun-25 15-Jul-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z1-IWU-AWC.110 Testing 4 11-Sep-25 15-Sep-25 Testing

INSIDE DRY CULVERT 114 10-Apr-25 24-Aug-25 24-Aug-25, INSIDE DRY CULVERT
POWER 100 10-Apr-25 07-Aug-25 07-Aug-25, POWER
HIGH VOLTAGE 110 KV NETWORK 30 10-Apr-25 14-May-25 14-May-25, HIGH VOLTAGE 110 KV NETWORK
JAH-Z1-IDU-HV.100 HV Cable Supports Installation 12 10-Apr-25 23-Apr-25 HV Cable Supports Installation

JAH-Z1-IDU-HV.105 Cable Installation with Fittings & Accessories 18 24-Apr-25 14-May-25 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 32 15-May-25 24-Jun-25 24-Jun-25, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z1-IDU-MV.100 MV Cable Supports Installation 12 15-May-25 28-May-25 MV Cable Supports Installation

JAH-Z1-IDU-MV.105 Cables Installation with Fittings & Accessories 20 29-May-25 24-Jun-25 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 32 25-Jun-25 31-Jul-25 31-Jul-25, LOW VOLTAGE NETWORK


JAH-Z1-IDU-LV.100 LV Cable Supports Installation 12 25-Jun-25 08-Jul-25 LV Cable Supports Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
232 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-IDU-LV.105 Cable Laying with Fittings & Accessories 20 09-Jul-25 31-Jul-25 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 70 15-May-25 07-Aug-25 07-Aug-25, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z1-IDU-DS.100 Cable Tray Installation 10 15-May-25 26-May-25 Cable Tray Installation

JAH-Z1-IDU-DS.105 PVC Ducts Installation 5 27-May-25 01-Jun-25 PVC Ducts Installation

JAH-Z1-IDU-DS.110 Cable Installation 10 02-Jun-25 16-Jun-25 Cable Installation

JAH-Z1-IDU-DS.115 Isolators Installation 5 17-Jun-25 22-Jun-25 Isolators Installation

JAH-Z1-IDU-DS.120 Sub Main Distribution Boards Installation 10 23-Jun-25 03-Jul-25 Sub Main Distribution Boards Installation

JAH-Z1-IDU-DS.125 Motor Control Centres Installation 10 05-Jul-25 15-Jul-25 Motor Control Centres Installation

JAH-Z1-IDU-DS.130 Distribution Boards Installation 10 16-Jul-25 27-Jul-25 Distribution Boards Installation

JAH-Z1-IDU-DS.135 Wiring Accessories Installation 10 28-Jul-25 07-Aug-25 Wiring Accessories Installation

LIGHTING SYSTEM 35 27-May-25 09-Jul-25 09-Jul-25, LIGHTING SYSTEM


JAH-Z1-IDU-LS.263 Cables Installation 10 27-May-25 10-Jun-25 Cables Installation

JAH-Z1-IDU-LS.264 Light Point Installation 15 11-Jun-25 28-Jun-25 Light Point Installation

JAH-Z1-IDU-LS.265 Luminaires Installation 10 29-Jun-25 09-Jul-25 Luminaires Installation

TELECOM SERVICES 20 02-Aug-25 24-Aug-25 24-Aug-25, TELECOM SERVICES


JAH-Z1-IDU-TES.100 Mobily Lines 10 02-Aug-25 12-Aug-25 Mobily Lines

JAH-Z1-IDU-TES.105 MOI Line 10 13-Aug-25 24-Aug-25 MOI Line

JAH-Z1-IDU-TES.110 STC Line 10 13-Aug-25 24-Aug-25 STC Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 231 31-Dec-24 05-Oct-25 05-Oct-25, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 160 31-Dec-24 13-Jul-25 13-Jul-25, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 56 31-Dec-24 05-Mar-25 05-Mar-25, FIRE FIGHTING SYSTEM
JAH-Z1-MECH-FF100 Pipe Installation work 20 31-Dec-24 22-Jan-25 Pipe Installation work

JAH-Z1-MECH-FF105 Valves and Accessories Installation 8 23-Jan-25 01-Feb-25 Valves and Accessories Installation

JAH-Z1-MECH-FF110 Sprinklers Installation 5 02-Feb-25 06-Feb-25 Sprinklers Installation

JAH-Z1-MECH-FF115 Fire Extinguishers Installation 8 08-Feb-25 16-Feb-25 Fire Extinguishers Installation

JAH-Z1-MECH-FF120 Foam Tank Installation 6 17-Feb-25 23-Feb-25 Foam Tank Installation

JAH-Z1-MECH-FF125 Pipe Painting work 6 24-Feb-25 02-Mar-25 Pipe Painting work

JAH-Z1-MECH-FF130 Testing work 3 03-Mar-25 05-Mar-25 Testing work

VENTILATION SYSTEM 23 06-Mar-25 06-Apr-25 06-Apr-25, VENTILATION SYSTEM


JAH-Z1-MECH-VS100 Staircase Pressurisation Fan Installation 5 06-Mar-25 11-Mar-25 Staircase Pressurisation Fan Installation

JAH-Z1-MECH-VS105 Extract fan installation 5 12-Mar-25 17-Mar-25 Extract fan installation

JAH-Z1-MECH-VS110 Unidirectional Jet fan 5 18-Mar-25 23-Mar-25 Unidirectional Jet fan

JAH-Z1-MECH-VS115 Reverse Jet fan 5 24-Mar-25 29-Mar-25 Reverse Jet fan

JAH-Z1-MECH-VS120 Testing work 3 03-Apr-25 06-Apr-25 Testing work

PUMPS INSTALLATION 15 07-Apr-25 23-Apr-25 23-Apr-25, PUMPS INSTALLATION


JAH-Z1-MECH-PI100 Sump Pump Installation 7 07-Apr-25 14-Apr-25 Sump Pump Installation

JAH-Z1-MECH-PI105 Pipe Connection work 6 15-Apr-25 21-Apr-25 Pipe Connection work

JAH-Z1-MECH-PI110 Testing work 2 22-Apr-25 23-Apr-25 Testing work

DUCTING SYSTEM 66 24-Apr-25 13-Jul-25 13-Jul-25, DUCTING SYSTEM


JAH-Z1-MECH-DS100 Duct Installation work 28 24-Apr-25 26-May-25 Duct Installation work

JAH-Z1-MECH-DS105 Grills Installation work 7 27-May-25 03-Jun-25 Grills Installation work

JAH-Z1-MECH-DS110 Diffusers Installation work 7 04-Jun-25 15-Jun-25 Diffusers Installation work

JAH-Z1-MECH-DS115 Non Returns Dampers 7 16-Jun-25 23-Jun-25 Non Returns Dampers

JAH-Z1-MECH-DS120 Fire and Smoke Damper 7 24-Jun-25 01-Jul-25 Fire and Smoke Damper

JAH-Z1-MECH-DS125 Sand Trap Louvre 5 02-Jul-25 07-Jul-25 Sand Trap Louvre

JAH-Z1-MECH-DS130 Testing work 5 08-Jul-25 13-Jul-25 Testing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
233 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TUNNEL ELECTRICAL WORKS 178 23-Jan-25 26-Aug-25 26-Aug-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 101 23-Jan-25 25-May-25 25-May-25, CABLE TRAYS
JAH-Z1-ELE-CT100 600mm Cable Tray 21 23-Jan-25 16-Feb-25 600mm Cable Tray

JAH-Z1-ELE-CT105 400mm Cable Tray 14 17-Feb-25 04-Mar-25 400mm Cable Tray

JAH-Z1-ELE-CT110 300mm Cable Tray 10 05-Mar-25 16-Mar-25 300mm Cable Tray

JAH-Z1-ELE-CT115 200mm Cable Tray 8 17-Mar-25 25-Mar-25 200mm Cable Tray

JAH-Z1-ELE-CT120 150mm Cable Tray 8 26-Mar-25 08-Apr-25 150mm Cable Tray

JAH-Z1-ELE-CT125 100mm Cable Tray 6 09-Apr-25 15-Apr-25 100mm Cable Tray

JAH-Z1-ELE-CT130 75mm Cable Tray 5 16-Apr-25 21-Apr-25 75mm Cable Tray

JAH-Z1-ELE-CT135 150mm x 100mm Trunking 7 22-Apr-25 29-Apr-25 150mm x 100mm Trunking

JAH-Z1-ELE-CT140 100mm x 100mm Trunking 6 30-Apr-25 06-May-25 100mm x 100mm Trunking

JAH-Z1-ELE-CT145 100mm x 75mm Trunking 7 07-May-25 14-May-25 100mm x 75mm Trunking

JAH-Z1-ELE-CT150 PVC Ducts150mm dia 5 15-May-25 20-May-25 PVC Ducts150mm dia

JAH-Z1-ELE-CT155 PVC Ducts100mm dia 4 21-May-25 25-May-25 PVC Ducts100mm dia

POWER CABLES 138 17-Feb-25 04-Aug-25 04-Aug-25, POWER CABLES


JAH-Z1-ELE-PC.100 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 17-Feb-25 02-Mar-25 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z1-ELE-PC.105 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 17-Feb-25 13-Mar-25 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z1-ELE-PC.110 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 19-Feb-25 13-Mar-25 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z1-ELE-PC.115 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 28 15-Mar-25 20-Apr-25 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z1-ELE-PC.120 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 06-Apr-25 28-Apr-25 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z1-ELE-PC.125 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 10-Apr-25 28-Apr-25 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z1-ELE-PC.130 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 10-Apr-25 28-Apr-25 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z1-ELE-PC.135 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 05-Apr-25 20-Apr-25 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z1-ELE-PC.140 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 06-Apr-25 20-Apr-25 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z1-ELE-PC.145 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 29-Apr-25 11-May-25 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z1-ELE-PC.150 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 30-Apr-25 11-May-25 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z1-ELE-PC.155 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 12-May-25 19-May-25 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z1-ELE-PC.160 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 28 20-May-25 24-Jun-25 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z1-ELE-PC.165 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 20-May-25 23-Jun-25 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z1-ELE-PC.170 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 40 11-Jun-25 27-Jul-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

JAH-Z1-ELE-PC.175 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 11-Jun-25 10-Jul-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z1-ELE-PC.180 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 25-Jun-25 02-Jul-25 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z1-ELE-PC.185 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 03-Jul-25 10-Jul-25 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

JAH-Z1-ELE-PC.190 Testing work 7 28-Jul-25 04-Aug-25 Testing work

ELECTRICAL INSTALLATIONS 133 03-Mar-25 12-Aug-25 12-Aug-25, ELECTRICAL INSTALLATIONS


JAH-Z1-ELE-INS.100 Circuit Wiring Installation 22 03-Mar-25 27-Mar-25 Circuit Wiring Installation

JAH-Z1-ELE-INS.105 Wiring Accessories 15 29-Mar-25 19-Apr-25 Wiring Accessories

JAH-Z1-ELE-INS.110 Lighting Installation 14 20-Apr-25 05-May-25 Lighting Installation

JAH-Z1-ELE-INS.115 Isolators Installation 12 06-May-25 19-May-25 Isolators Installation

JAH-Z1-ELE-INS.120 SMDB Installation 5 20-May-25 25-May-25 SMDB Installation

JAH-Z1-ELE-INS.125 Motor Control Centres Installation 5 26-May-25 31-May-25 Motor Control Centres Installation

JAH-Z1-ELE-INS.130 Distribution Boards 6 01-Jun-25 10-Jun-25 Distribution Boards

JAH-Z1-ELE-INS.135 Testing work 7 05-Aug-25 12-Aug-25 Testing work

LOW CURRENT 178 23-Jan-25 26-Aug-25 26-Aug-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 82 23-Jan-25 03-May-25 03-May-25, FIRE DETECTION AND ALARM SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
234 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-LOW-FDT.100Fibre-optic Sensing Cable Laying 12 23-Jan-25 05-Feb-25 Fibre-optic Sensing Cable Laying

JAH-Z1-LOW-FDT.105Fire Alarm Control Panel Installation 6 06-Feb-25 12-Feb-25 Fire Alarm Control Panel Installation

JAH-Z1-LOW-FDT.110Tamper switch Installation 5 13-Feb-25 18-Feb-25 Tamper switch Installation

JAH-Z1-LOW-FDT.115Zone Input units Installation 5 19-Feb-25 24-Feb-25 Zone Input units Installation

JAH-Z1-LOW-FDT.120Fire Alarm sounder Installation 4 25-Feb-25 01-Mar-25 Fire Alarm sounder Installation

JAH-Z1-LOW-FDT.125Fire Alarm Speaker Installation 8 02-Mar-25 10-Mar-25 Fire Alarm Speaker Installation

JAH-Z1-LOW-FDT.130Smoke Detector Installation 8 11-Mar-25 19-Mar-25 Smoke Detector Installation

JAH-Z1-LOW-FDT.135Heat Detector Installation 8 20-Mar-25 29-Mar-25 Heat Detector Installation

JAH-Z1-LOW-FDT.140Interface Module Installation 8 03-Apr-25 12-Apr-25 Interface Module Installation

JAH-Z1-LOW-FDT.145Double Action Manual Call Point Installation 7 13-Apr-25 20-Apr-25 Double Action Manual Call Point Installation

JAH-Z1-LOW-FDT.150Flashing Beacon Installation 6 21-Apr-25 27-Apr-25 Flashing Beacon Installation

JAH-Z1-LOW-FDT.155Testing work 5 28-Apr-25 03-May-25 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 73 06-Feb-25 06-May-25 06-May-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z1-LOW-PH.100 8 core UTP Cable Laying 7 06-Feb-25 13-Feb-25 8 core UTP Cable Laying

JAH-Z1-LOW-PH.105 Junction box Installation 4 15-Feb-25 18-Feb-25 Junction box Installation

JAH-Z1-LOW-PH.110 Emergency Telephone Installation 5 19-Feb-25 24-Feb-25 Emergency Telephone Installation

JAH-Z1-LOW-PH.115 Connection and Testing 3 04-May-25 06-May-25 Connection and Testing

PUBLIC ADDRESS SYSTEM 22 07-May-25 01-Jun-25 01-Jun-25, PUBLIC ADDRESS SYSTEM


JAH-Z1-LOW-PA.100 Cables laying public address system 8 07-May-25 15-May-25 Cables laying public address system

JAH-Z1-LOW-PA.105 Wall-mounted Voice Evacuation Horn Speaker Installation 7 17-May-25 24-May-25 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z1-LOW-PA.110 Voice alarm control panel Installation 5 25-May-25 29-May-25 Voice alarm control panel Installation

JAH-Z1-LOW-PA.115 Connection and Testing 2 31-May-25 01-Jun-25 Connection and Testing

VIDEO SURVEILLANCE &ACCESS CONTROL SYSTEM 25 02-Jun-25 03-Jul-25 03-Jul-25, VIDEO SURVEILLANCE & ACCESS CONTROL SYSTEM
JAH-Z1-LOW-VDS.100Single Core Fibre Optical Cable Laying 7 02-Jun-25 12-Jun-25 Single Core Fibre Optical Cable Laying

JAH-Z1-LOW-VDS.105RTU Panel Installation 5 14-Jun-25 18-Jun-25 RTU Panel Installation

JAH-Z1-LOW-VDS.110Overhead Vehicle Detector Installation 4 19-Jun-25 23-Jun-25 Overhead Vehicle Detector Installation

JAH-Z1-LOW-VDS.115Door Contact Installation 2 24-Jun-25 25-Jun-25 Door Contact Installation

JAH-Z1-LOW-VDS.120PTZ Camera mounted on Pole Installation 2 26-Jun-25 28-Jun-25 PTZ Camera mounted on Pole Installation

JAH-Z1-LOW-VDS.125Fixed (AID) Camera Installation 3 29-Jun-25 01-Jul-25 Fixed (AID) Camera Installation

JAH-Z1-LOW-VDS.130Testing work 2 02-Jul-25 03-Jul-25 Testing work

RADIO RE-BROADCASTING SYSTEM 20 14-Jun-25 06-Jul-25 06-Jul-25, RADIO RE-BROADCASTING SYSTEM


JAH-Z1-LOW-RDO.100Leaky Feeder Cable Laying 5 14-Jun-25 18-Jun-25 Leaky Feeder Cable Laying

JAH-Z1-LOW-RDO.105Inline Bidirectional Signal Amplifier Installation 3 19-Jun-25 22-Jun-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z1-LOW-RDO.110End of Line Terminator 4 23-Jun-25 26-Jun-25 End of Line Terminator

JAH-Z1-LOW-RDO.115Connection and Testing 2 05-Jul-25 06-Jul-25 Connection and Testing

TRAFFIC MANAGEMENT SYSTEM 59 19-Jun-25 26-Aug-25 26-Aug-25, TRAFFIC MANAGEMENT SYSTEM


JAH-Z1-LOW-TMS.100Traffic Control Panel Installation 3 19-Jun-25 22-Jun-25 Traffic Control Panel Installation

JAH-Z1-LOW-TMS.105Power Control Cable Installation 7 23-Jun-25 30-Jun-25 Power Control Cable Installation

JAH-Z1-LOW-TMS.110Multicore Cable Installation 7 01-Jul-25 08-Jul-25 Multicore Cable Installation

JAH-Z1-LOW-TMS.115Traffic Message System 6 09-Jul-25 15-Jul-25 Traffic Message System

JAH-Z1-LOW-TMS.120Magnetic Loop 10 16-Jul-25 27-Jul-25 Magnetic Loop

JAH-Z1-LOW-TMS.125Traffic Signal Red & Green 15 28-Jul-25 13-Aug-25 Traffic Signal Red & Green

JAH-Z1-LOW-TMS.130Traffic Control Console at Control Room 7 14-Aug-25 21-Aug-25 Traffic Control Console at Control Room

JAH-Z1-LOW-TMS.135230V/13A UPS Power at Control Room 2 23-Aug-25 24-Aug-25 230V/13A UPS Power at Control Room

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
235 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z1-LOW-TMS.14025A UPS Power 2 25-Aug-25 26-Aug-25 25A UPS Power

SCADA SYSTEM 18 23-Jun-25 13-Jul-25 13-Jul-25, SCADA SYSTEM


JAH-Z1-LOW-SCA.100Cabling Laying 7 23-Jun-25 30-Jun-25 Cabling Laying

JAH-Z1-LOW-SCA.105Remote Terminal Unit Installation 4 01-Jul-25 05-Jul-25 Remote Terminal Unit Installation

JAH-Z1-LOW-SCA.110Programmable Logic Control Unit Installation 3 06-Jul-25 08-Jul-25 Programmable Logic Control Unit Installation

JAH-Z1-LOW-SCA.115SCADA/ PC/ Software/ Printers Installation 2 09-Jul-25 10-Jul-25 SCADA/ PC/ Software/ Printers Installation

JAH-Z1-LOW-SCA.120Testing work 2 12-Jul-25 13-Jul-25 Testing work

TUNNEL PLUMBING WORKS 35 25-Aug-25 05-Oct-25 05-Oct-25, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 25-Aug-25 05-Oct-25 05-Oct-25, DRAINAGE SYSTEM
JAH-Z1-PLU-DS.100 Drainage Pipes Installation Incl. Fittings & Accessories 15 25-Aug-25 10-Sep-25 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z1-PLU-DS105 Collection Chambers 20 11-Sep-25 05-Oct-25 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 06-Oct-25 23-Nov-25 23-Nov-25, TUNNEL INTERNAL ROAD WORK
JAH-Z1-TIRW.107 Kerbs, Channels & Edging 7 06-Oct-25 13-Oct-25 Kerbs, Channels & Edging

JAH-Z1-TIRW.108 Tack Coat Application (MC-1) 10 14-Oct-25 25-Oct-25 Tack Coat Application (MC-1)

JAH-Z1-TIRW.111 Bituminious Base Course Layer 10 14-Oct-25 25-Oct-25 Bituminious Base Course Layer

JAH-Z1-TIRW.112 Tack Coat Application (RC-2) 12 26-Oct-25 08-Nov-25 Tack Coat Application (RC-2)

JAH-Z1-TIRW.114 Asphalt Wearing Course Layer 12 26-Oct-25 08-Nov-25 Asphalt Wearing Course Layer

JAH-Z1-TIRW.135 Pavement Line Marking 5 09-Nov-25 13-Nov-25 Pavement Line Marking

JAH-Z1-TIRW.140 Traffic Signboards Installation 8 15-Nov-25 23-Nov-25 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 40 09-Nov-25 24-Dec-25 24-Dec-25, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z1-TDW.100 Fire Protection Board Installation 10 09-Nov-25 19-Nov-25 Fire Protection Board Installation

JAH-Z1-TDW.105 GRC Panel Board Installation 30 20-Nov-25 24-Dec-25 GRC Panel Board Installation

ZONE 2 - FROM STA. 0+500 ~ 0+994 726 13-Jul-22 A 17-Jun-25 17-Jun-25, ZONE 2 - FROM STA. 0+500 ~ 0+994
ENGINEERING 410 13-Jul-22 A 14-Jul-24 14-Jul-24, ENGINEERING
RAM145 Completion Engineering Work For Zone2 0 14-Jul-24* Completion Engineering Work For Zone2

SITE SURVEY 14 13-Jul-22 A 25-Aug-22 A 25-Aug-22 A, SITE SURVEY


JAH-Z2-EN-SS.110 Site Survey/Settingout Control Points 2 13-Jul-22 A 18-Aug-22 A Site Survey/Settingout Control Points

JAH-Z2-EN-SS.115 Review and Approval of Site Survey & Control Points 12 19-Aug-22 A 25-Aug-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 208 08-Mar-23 13-Nov-23 13-Nov-23, SHOP DRAWINGS


CIVIL/STRUCTURAL 0+510 ~0+610 42 08-Mar-23 29-Apr-23 29-Apr-23, CIVIL/STRUCTURAL 0+510 ~0+610
JAH-Z2-ENG-CS-.300 Plan and Profile Shop Drawings Preparation & Submission 6 08-Mar-23 14-Mar-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.305 Plan and Profile Shop Drawings Review & Approval 12 15-Mar-23 28-Mar-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z2-ENG-CS.310 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 29-Mar-23 04-Apr-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.315 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 05-Apr-23 18-Apr-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z2-ENG-CS.320 Tunnel Structural Shop Drawings Submission 6 05-Apr-23 11-Apr-23 Tunnel Structural Shop Drawings Submission

JAH-Z2-ENG-CS.325 Tunnel Structural Shop Drawings Review & Approval 12 12-Apr-23 29-Apr-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+610 ~0+710 42 19-Apr-23 10-Jun-23 10-Jun-23, CIVIL/STRUCTURAL 0+610 ~0+710


JAH-Z2-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 19-Apr-23 29-Apr-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 30-Apr-23 13-May-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z2-ENG-CS.360 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 14-May-23 20-May-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.365 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 21-May-23 03-Jun-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z2-ENG-CS.370 Tunnel Structural Shop Drawings Submission 6 21-May-23 27-May-23 Tunnel Structural Shop Drawings Submission

JAH-Z2-ENG-CS.375 Tunnel Structural Shop Drawings Review & Approval 12 28-May-23 10-Jun-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+710 ~0+810 42 04-Jun-23 25-Jul-23 25-Jul-23, CIVIL/STRUCTURAL 0+710 ~0+810


JAH-Z2-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 04-Jun-23 10-Jun-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 11-Jun-23 24-Jun-23 Plan and Profile Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
236 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ENG-CS.410 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 25-Jun-23 04-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.415 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 05-Jul-23 18-Jul-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z2-ENG-CS.420 Tunnel Structural Shop Drawings Submission 6 05-Jul-23 11-Jul-23 Tunnel Structural Shop Drawings Submission

JAH-Z2-ENG-CS.425 Tunnel Structural Shop Drawings Review & Approval 12 12-Jul-23 25-Jul-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+810 ~0+910 42 19-Jul-23 05-Sep-23 05-Sep-23, CIVIL/STRUCTURAL 0+810 ~0+910


JAH-Z2-ENG-CS.450 Plan and Profile Shop Drawings Preparation & Submission 6 19-Jul-23 25-Jul-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.455 Plan and Profile Shop Drawings Review & Approval 12 26-Jul-23 08-Aug-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z2-ENG-CS.460 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 09-Aug-23 15-Aug-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.465 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 16-Aug-23 29-Aug-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z2-ENG-CS.470 Tunnel Structural Shop Drawings Submission 6 16-Aug-23 22-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z2-ENG-CS.475 Tunnel Structural Shop Drawings Review & Approval 12 23-Aug-23 05-Sep-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+910 ~0+994 42 30-Aug-23 18-Oct-23 18-Oct-23, CIVIL/STRUCTURAL 0+910 ~0+994


JAH-Z2-ENG-CS.500 Plan and Profile Shop Drawings Preparation & Submission 6 30-Aug-23 05-Sep-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.505 Plan and Profile Shop Drawings Review & Approval 12 06-Sep-23 19-Sep-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z2-ENG-CS.510 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 20-Sep-23 27-Sep-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z2-ENG-CS.515 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 28-Sep-23 11-Oct-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z2-ENG-CS.520 Tunnel Structural Shop Drawings Submission 6 28-Sep-23 04-Oct-23 Tunnel Structural Shop Drawings Submission

JAH-Z2-ENG-CS.525 Tunnel Structural Shop Drawings Review & Approval 12 05-Oct-23 18-Oct-23 Tunnel Structural Shop Drawings Review & Approval

ARCHITECTURAL 22 19-Oct-23 13-Nov-23 13-Nov-23, ARCHITECTURAL


JAH-Z2-ENG-AR.110 Tunnel Architectural Shop Drawings Preparation & Submission 10 19-Oct-23 30-Oct-23 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z2-ENG-AR.115 Tunnel Architectural Shop Drawings Review & Approval 12 31-Oct-23 13-Nov-23 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 160 19-Oct-23 25-Apr-24 25-Apr-24, UTILITIES


WET UTILITIES 136 19-Oct-23 25-Mar-24 25-Mar-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 32 19-Oct-23 25-Nov-23 25-Nov-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
JAH-Z2-WU-EN-PW.120Shop Drawings Preparation & Submission 20 19-Oct-23 11-Nov-23 Shop Drawings Preparation & Submission

JAH-Z2-WU-EN-PW.125Shop Drawings Review & Approval 12 12-Nov-23 25-Nov-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 32 12-Nov-23 18-Dec-23 18-Dec-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z2-WU-EN-GWD.120
Shop Drawings Preparation & Submission 20 12-Nov-23 04-Dec-23 Shop Drawings Preparation & Submission

JAH-Z2-WU-EN-GWD.125
Shop Drawings Review & Approval 12 05-Dec-23 18-Dec-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 32 05-Dec-23 10-Jan-24 10-Jan-24, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z2-WU-EN-IRR.120
Shop Drawings Preparation & Submission 20 05-Dec-23 27-Dec-23 Shop Drawings Preparation & Submission

JAH-Z2-WU-EN-IRR.125
Shop Drawings Review & Approval 12 28-Dec-23 10-Jan-24 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 32 11-Jan-24 17-Feb-24 17-Feb-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z2-WU-EN-CWS.120
Shop Drawings Preparation & Submission 20 11-Jan-24 03-Feb-24 Shop Drawings Preparation & Submission

JAH-Z2-WU-EN-CWS.125
Shop Drawings Review & Approval 12 04-Feb-24 17-Feb-24 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 32 18-Feb-24 25-Mar-24 25-Mar-24, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z2-WU-EN-AUW.130
Shop Drawings Preparation & Submission 20 18-Feb-24 11-Mar-24 Shop Drawings Preparation & Submission

JAH-Z2-WU-EN-AUW.135
Shop Drawings Review & Approval 12 12-Mar-24 25-Mar-24 Shop Drawings Review & Approval

DRY UTILITIES 128 26-Nov-23 25-Apr-24 25-Apr-24, DRY UTILITIES


POWER 96 26-Nov-23 16-Mar-24 16-Mar-24, POWER
HIGH VOLTAGE 110 KV NETWORK 32 26-Nov-23 01-Jan-24 01-Jan-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z2-DU-EN-PWR.190
Shop Drawings Preparation & Submission 20 26-Nov-23 18-Dec-23 Shop Drawings Preparation & Submission

JAH-Z2-DU-EN-PWR.195
Shop Drawings Review & Approval 12 19-Dec-23 01-Jan-24 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 32 26-Nov-23 01-Jan-24 01-Jan-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z2-DU-EN-PWR.200
Shop Drawings Preparation & Submission 20 26-Nov-23 18-Dec-23 Shop Drawings Preparation & Submission

JAH-Z2-DU-EN-PWR.205
Shop Drawings Review & Approval 12 19-Dec-23 01-Jan-24 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 32 26-Nov-23 01-Jan-24 01-Jan-24, LOW VOLTAGE NETWORK


JAH-Z2-DU-EN-PWR.210
Shop Drawings Preparation & Submission 20 26-Nov-23 18-Dec-23 Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
237 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-DU-EN-PWR.215
Shop Drawings Review & Approval 12 19-Dec-23 01-Jan-24 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 32 02-Jan-24 07-Feb-24 07-Feb-24, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z2-DU-EN-PWR.220
Shop Drawings Preparation & Submission 20 02-Jan-24 24-Jan-24 Shop Drawings Preparation & Submission

JAH-Z2-DU-EN-PWR.225
Shop Drawings Review & Approval 12 25-Jan-24 07-Feb-24 Shop Drawings Review & Approval

LIGHTING SYSTEM 32 08-Feb-24 16-Mar-24 16-Mar-24, LIGHTING SYSTEM


JAH-Z2-DU-EN-PWR.230
Shop Drawings Preparation & Submission 20 08-Feb-24 02-Mar-24 Shop Drawings Preparation & Submission

JAH-Z2-DU-EN-PWR.235
Shop Drawings Review & Approval 12 03-Mar-24 16-Mar-24 Shop Drawings Review & Approval

LOW CURRENT 32 17-Mar-24 25-Apr-24 25-Apr-24, LOW CURRENT


TELECOM SERVICES 32 17-Mar-24 25-Apr-24 25-Apr-24, TELECOM SERVICES
JAH-Z2-DU-EN-LC.140Shop Drawings Preparation & Submission 20 17-Mar-24 08-Apr-24 Shop Drawings Preparation & Submission

JAH-Z2-DU-EN-LC.145Shop Drawings Review & Approval 12 13-Apr-24 25-Apr-24 Shop Drawings Review & Approval

MEP 272 23-Aug-23 14-Jul-24 14-Jul-24, MEP


TUNNEL MECHANICAL WORKS 176 23-Aug-23 16-Mar-24 16-Mar-24, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 23-Aug-23 04-Dec-23 04-Dec-23, FIRE FIGHTING SYSTEM
JAH-Z2-ENG-FF.140 Fire Fighting Pipe Layout Plan Preparation & Submission 10 23-Aug-23 03-Sep-23 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z2-ENG-FF.145 Fire Fighting Pipe Layout Plan Review & Approval 12 04-Sep-23 17-Sep-23 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z2-ENG-FF.150 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 18-Sep-23 30-Sep-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z2-ENG-FF.155 Fire Fighting Sprinkler Layout Plan Review & Approval 12 01-Oct-23 14-Oct-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z2-ENG-FF.160 Foam Tank Installation Layout Preparation & Submission 10 15-Oct-23 25-Oct-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z2-ENG-FF.165 Foam Tank Installation Layout Review & Approval 12 26-Oct-23 08-Nov-23 Foam Tank Installation Layout Review & Approval

JAH-Z2-ENG-FF.170 Fire Extinguishers Layout Plan Preparation & Submission 10 09-Nov-23 20-Nov-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z2-ENG-FF.175 Fire Extinguishers Layout Plan Review & Approval 12 21-Nov-23 04-Dec-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 21-Nov-23 10-Jan-24 10-Jan-24, VENTILATION SYSTEM


JAH-Z2-ENG-VS.120 Fan Layout Preparation & Submission 10 21-Nov-23 02-Dec-23 Fan Layout Preparation & Submission

JAH-Z2-ENG-VS.125 Fan Layout Review & Approval 12 03-Dec-23 16-Dec-23 Fan Layout Review & Approval

JAH-Z2-ENG-VS.130 Cable Route Shop Drawing Preparation & Submission 10 17-Dec-23 27-Dec-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z2-ENG-VS.135 Cable Route Shop Drawing Review & Approval 12 28-Dec-23 10-Jan-24 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 11-Jan-24 05-Feb-24 05-Feb-24, PUMPS INSTALLATION


JAH-Z2-ENG-PI.110 Sump Pump Diagram Preparation & Submission 10 11-Jan-24 22-Jan-24 Sump Pump Diagram Preparation & Submission

JAH-Z2-ENG-PI.115 Sump Pump Diagram Review & Approval 12 23-Jan-24 05-Feb-24 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 05-Dec-23 16-Mar-24 16-Mar-24, DUCTING SYSTEM


JAH-Z2-ENG-DS.140 Duct Layout Drawing Preparation & Submission 10 05-Dec-23 16-Dec-23 Duct Layout Drawing Preparation & Submission

JAH-Z2-ENG-DS.145 Duct Layout Drawing Review & Approval 12 17-Dec-23 30-Dec-23 Duct Layout Drawing Review & Approval

JAH-Z2-ENG-DS.146 Diffuser Details Drawing Preparation & Submission 10 31-Dec-23 10-Jan-24 Diffuser Details Drawing Preparation & Submission

JAH-Z2-ENG-DS.150 Diffuser Details Review & Approval 12 11-Jan-24 24-Jan-24 Diffuser Details Review & Approval

JAH-Z2-ENG-DS.155 Dampers Details Preparation & Submission 10 25-Jan-24 05-Feb-24 Dampers Details Preparation & Submission

JAH-Z2-ENG-DS.160 Dampers Details Review & Approval 12 06-Feb-24 19-Feb-24 Dampers Details Review & Approval

JAH-Z2-ENG-DS.165 Sand Trap Louvre Layout Drawing Preparation & Submission 10 20-Feb-24 02-Mar-24 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z2-ENG-DS.170 Sand Trap Louvre Layout Drawing Review & Approval 12 03-Mar-24 16-Mar-24 Sand Trap Louvre Layout Drawing Review & Approval

TUNNEL ELECTRICAL WORKS 184 05-Dec-23 14-Jul-24 14-Jul-24, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 17-Dec-23 25-Apr-24 25-Apr-24, CABLE TRAYS
JAH-Z2-ENG-CTR.150 Cable Tray Layout Drawing Preparation & Submission 10 17-Dec-23 27-Dec-23 Cable Tray Layout Drawing Preparation & Submission

JAH-Z2-ENG-CTR.155 Cable Tray Layout Drawing Review & Approval 12 28-Dec-23 10-Jan-24 Cable Tray Layout Drawing Review & Approval

JAH-Z2-ENG-CTR.160 Cable Tray Diversion Details Preparation & Submission 10 11-Jan-24 22-Jan-24 Cable Tray Diversion Details Preparation & Submission

JAH-Z2-ENG-CTR.165 Cable Tray Diversion Details Review & Approval 12 23-Jan-24 05-Feb-24 Cable Tray Diversion Details Review & Approval

JAH-Z2-ENG-CTR.170 Cable Tray Fixing Details Preparation & Submission 10 06-Feb-24 17-Feb-24 Cable Tray Fixing Details Preparation & Submission

JAH-Z2-ENG-CTR.175 Cable Tray Fixing Details Review & Submission 12 18-Feb-24 02-Mar-24 Cable Tray Fixing Details Review & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
238 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ENG-CTR.180 Cable Tray Sections Preparation & Submission 10 03-Mar-24 13-Mar-24 Cable Tray Sections Preparation & Submission

JAH-Z2-ENG-CTR.185 Cable Tray Sections Review & Approval 12 14-Mar-24 27-Mar-24 Cable Tray Sections Review & Approval

JAH-Z2-ENG-CTR.190 PVC DuctsSections Preparation & Submission 10 28-Mar-24 08-Apr-24 PVC DuctsSections Preparation & Submission

JAH-Z2-ENG-CTR.195 PVC Sections Review & Approval 12 13-Apr-24 25-Apr-24 PVC Sections Review & Approval

POWER CABLES 44 18-Feb-24 08-Apr-24 08-Apr-24, POWER CABLES


JAH-Z2-ENG-PC.120 Cable Route Shop Drawing Preparation & Submission 10 18-Feb-24 28-Feb-24 Cable Route Shop Drawing Preparation & Submission

JAH-Z2-ENG-PC.125 Cable Route Shop Drawing Review & Approval 12 29-Feb-24 13-Mar-24 Cable Route Shop Drawing Review & Approval

JAH-Z2-ENG-PC.130 Junction Box Layout Plan Preparation & Submission 10 14-Mar-24 25-Mar-24 Junction Box Layout Plan Preparation & Submission

JAH-Z2-ENG-PC.135 Junction Box Layout Plan Review & Approval 12 26-Mar-24 08-Apr-24 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 29-Feb-24 14-Jul-24 14-Jul-24, ELECTRICAL INSTALLATIONS


JAH-Z2-ENG-ELI.150 Wiring Accessories Diagram Preparation & Submission 10 29-Feb-24 11-Mar-24 Wiring Accessories Diagram Preparation & Submission

JAH-Z2-ENG-ELI.155 Lighting Layout Drawing Preparation & Submission 10 26-Mar-24 06-Apr-24 Lighting Layout Drawing Preparation & Submission

JAH-Z2-ENG-ELI.160 Circuit Wiring Diagram Preparation & Submission 10 24-Apr-24 05-May-24 Circuit Wiring Diagram Preparation & Submission

JAH-Z2-ENG-ELI.165 Circuit Wiring Diagram Review & Approval 12 06-May-24 19-May-24 Circuit Wiring Diagram Review & Approval

JAH-Z2-ENG-ELI.170 SMDB Line Diagram Preparation & Submission 10 20-May-24 30-May-24 SMDB Line Diagram Preparation & Submission

JAH-Z2-ENG-ELI.175 SMDB Line Diagram Review & Approval 12 01-Jun-24 13-Jun-24 SMDB Line Diagram Review & Approval

JAH-Z2-ENG-ELI.180 Distribution Board Line Diagram Preparation & Submission 10 19-Jun-24 30-Jun-24 Distribution Board Line Diagram Preparation & Submission

JAH-Z2-ENG-ELI.185 Lighting Layout Drawing Review & Approval 12 07-Apr-24 23-Apr-24 Lighting Layout Drawing Review & Approval

JAH-Z2-ENG-ELI.190 Wiring Accessories Diagram Review & Approval 12 12-Mar-24 25-Mar-24 Wiring Accessories Diagram Review & Approval

JAH-Z2-ENG-ELI.195 Distribution Board Line Diagram Review & Approval 12 01-Jul-24 14-Jul-24 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 05-Dec-23 09-May-24 09-May-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 05-Dec-23 09-May-24 09-May-24, FIRE DETECTION AND ALARM SYSTEM
JAH-Z2-ENG-FD.160 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 05-Dec-23 16-Dec-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.165 Fire Alarm Control Panel Layout Drawing Review & Approval 12 17-Dec-23 30-Dec-23 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z2-ENG-FD.170 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 31-Dec-23 10-Jan-24 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.175 Fire Alarm Speaker Layout Drawing Review & Approval 12 11-Jan-24 24-Jan-24 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z2-ENG-FD.180 Fire Alarm sounder Layout Drawing Preparation & Submission 10 25-Jan-24 05-Feb-24 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.185 Fire Alarm sounder Layout Drawing Review & Approval 12 06-Feb-24 19-Feb-24 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z2-ENG-FD.190 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 20-Feb-24 02-Mar-24 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.195 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 03-Mar-24 16-Mar-24 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z2-ENG-FD.200 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 17-Mar-24 27-Mar-24 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.205 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 28-Mar-24 14-Apr-24 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z2-ENG-FD.210 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 15-Apr-24 25-Apr-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z2-ENG-FD.215 Double Action Manual Call Point Layout Drawing Preparation & Submission 12 27-Apr-24 09-May-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 17-Dec-23 25-Apr-24 25-Apr-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z2-ENG-TPH.1508 core UTP Cable Laying 14 17-Dec-23 01-Jan-24 8 core UTP Cable Laying

JAH-Z2-ENG-TPH.155Junction box Installation 8 02-Jan-24 10-Jan-24 Junction box Installation

JAH-Z2-ENG-TPH.160Emergency Telephone Installation 14 11-Jan-24 27-Jan-24 Emergency Telephone Installation

JAH-Z2-ENG-TPH.165Connection and Testing 8 28-Jan-24 05-Feb-24 Connection and Testing

JAH-Z2-ENG-TPH.1708 Core UTP Cable Layout Drawing Preparation & Submission 10 06-Feb-24 17-Feb-24 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-TPH.1758 Core UTP Cable Layout Drawing Review & Approval 12 18-Feb-24 02-Mar-24 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z2-ENG-TPH.180Junction box Layout Drawing Preparation & Submission 10 03-Mar-24 13-Mar-24 Junction box Layout Drawing Preparation & Submission

JAH-Z2-ENG-TPH.185Junction box Layout Drawing Review & Approval 12 14-Mar-24 27-Mar-24 Junction box Layout Drawing Review & Approval

JAH-Z2-ENG-TPH.190Telephone Location Layout Preparation & Submission 10 28-Mar-24 08-Apr-24 Telephone Location Layout Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
239 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ENG-TPH.195Telephone Location Layout Review & Approval 12 13-Apr-24 25-Apr-24 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 02-Jan-24 18-Mar-24 18-Mar-24, PUBLIC ADDRESS


JAH-Z2-ENG-PUBA.130
Cable Layout Drawing Preparation & Submission 10 02-Jan-24 13-Jan-24 Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-PUBA.135
Cable Layout Drawing Review & Approval 12 14-Jan-24 27-Jan-24 Cable Layout Drawing Review & Approval

JAH-Z2-ENG-PUBA.140
Voice alarm control panel Drawing Preparation & Submission 10 28-Jan-24 07-Feb-24 Voice alarm control panel Drawing Preparation & Submission

JAH-Z2-ENG-PUBA.145
Voice alarm control panel Drawing Review & Approval 12 08-Feb-24 21-Feb-24 Voice alarm control panel Drawing Review & Approval

JAH-Z2-ENG-PUBA.150
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 22-Feb-24 04-Mar-24 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z2-ENG-PUBA.155
Voice Evacuation Horn Speaker Drawing Review & Approval 12 05-Mar-24 18-Mar-24 Voice Evacuation Horn Speaker Drawing Review & Approval

VIDEO SURVEILLANCE 44 14-Jan-24 04-Mar-24 04-Mar-24, VIDEO SURVEILLANCE


JAH-Z2-ENG-VID.120Cable Layout Drawing Preparation & Submission 10 14-Jan-24 24-Jan-24 Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-VID.125Cable Layout Drawing Review & Approval 12 25-Jan-24 07-Feb-24 Cable Layout Drawing Review & Approval

JAH-Z2-ENG-VID.130Camera Layout Drawing Preparation & Submission 10 08-Feb-24 19-Feb-24 Camera Layout Drawing Preparation & Submission

JAH-Z2-ENG-VID.135Camera Layout Drawing Review & Approval 12 20-Feb-24 04-Mar-24 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 25-Jan-24 16-Mar-24 16-Mar-24, SACADA SYSTEM


JAH-Z2-ENG-SCA.120Cable Layout Drawing Preparation & Submission 10 25-Jan-24 05-Feb-24 Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-SCA.125Cable Layout Drawing Review & Approval 12 06-Feb-24 19-Feb-24 Cable Layout Drawing Review & Approval

JAH-Z2-ENG-SCA.130Installation Layout Drawing Preparation & Submission 10 20-Feb-24 02-Mar-24 Installation Layout Drawing Preparation & Submission

JAH-Z2-ENG-SCA.135Installation Layout Drawing Review & Approval 12 03-Mar-24 16-Mar-24 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 06-Feb-24 27-Mar-24 27-Mar-24, RADIO RE-BROADCASTING SYSTEM


JAH-Z2-ENG-RDO.120Cable Layout Drawing Preparation & Submission 10 06-Feb-24 17-Feb-24 Cable Layout Drawing Preparation & Submission

JAH-Z2-ENG-RDO.125Cable Layout Drawing Review & Approval 12 18-Feb-24 02-Mar-24 Cable Layout Drawing Review & Approval

JAH-Z2-ENG-RDO.130Installation Layout Drawing Preparation & Submission 10 03-Mar-24 13-Mar-24 Installation Layout Drawing Preparation & Submission

JAH-Z2-ENG-RDO.135Installation Layout Drawing Review & Approval 12 14-Mar-24 27-Mar-24 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 18-Feb-24 12-Mar-24 12-Mar-24, TUNNEL PLUMBING WORKS


JAH-Z2-ENG-PLM.110 Plumbing Services Shop Drawings Preparation & Submission 9 18-Feb-24 27-Feb-24 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z2-ENG-PLM.115 Plumbing Shop Drawings Review & Approval 12 28-Feb-24 12-Mar-24 Plumbing Shop Drawings Review & Approval

PROCUREMENT 473 29-Mar-23 17-Oct-24 17-Oct-24, PROCUREMENT


RAM290 Completion Procurment for Zone 2 0 17-Oct-24* Completion Procurment for Zone 2

CIVIL/STRUCTURAL 63 29-Mar-23 13-Jun-23 13-Jun-23, CIVIL/STRUCTURAL


JAH-Z2-PRO-CS.120 Request for Quotation 10 29-Mar-23 09-Apr-23 Request for Quotation

JAH-Z2-PRO-CS.125 Issue Purchase Order 8 10-Apr-23 18-Apr-23 Issue Purchase Order

JAH-Z2-PRO-CS.128 Staging Time 15 19-Apr-23 09-May-23 Staging Time

JAH-Z2-PRO-CS.130 Material Delivery 45 19-Apr-23 13-Jun-23 Material Delivery

UTILITIES 273 26-Nov-23 17-Oct-24 17-Oct-24, UTILITIES


WET UTILITIES 249 26-Nov-23 18-Sep-24 18-Sep-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 145 26-Nov-23 15-May-24 15-May-24, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 26-Nov-23 15-May-24 15-May-24, DI PIPES
JAH-Z2-WU-PR-PW.278
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.280
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.285
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.290
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

HDPE PIPES 145 26-Nov-23 15-May-24 15-May-24, HDPE PIPES


JAH-Z2-WU-PR-PW.293
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.295
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.300
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.305
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

GRP PIPES 145 26-Nov-23 15-May-24 15-May-24, GRP PIPES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
240 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-WU-PR-PW.308
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.310
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.315
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.320
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

DI & GRP FITTING 145 26-Nov-23 15-May-24 15-May-24, DI & GRP FITTING
JAH-Z2-WU-PR-PW.322
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.325
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.330
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.335
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

GATE VALVE 145 26-Nov-23 15-May-24 15-May-24, GATE VALVE


JAH-Z2-WU-PR-PW.338
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.340
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.345
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.350
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

BUTTERFLAY VALVE 145 26-Nov-23 15-May-24 15-May-24, BUTTERFLAY VALVE


JAH-Z2-WU-PR-PW.352
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.355
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.360
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.365
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

WATER METER 145 26-Nov-23 15-May-24 15-May-24, WATER METER


JAH-Z2-WU-PR-PW.368
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.370
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.375
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.380
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

AIR RELASE VALVE 145 26-Nov-23 15-May-24 15-May-24, AIR RELASE VALVE
JAH-Z2-WU-PR-PW.382
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.385
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.390
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.395
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

WASHOUT VALVE 145 26-Nov-23 15-May-24 15-May-24, WASHOUT VALVE


JAH-Z2-WU-PR-PW.398
Request for Quotation 10 26-Nov-23 06-Dec-23 Request for Quotation

JAH-Z2-WU-PR-PW.400
Issue Purchase Order 15 07-Dec-23 24-Dec-23 Issue Purchase Order

JAH-Z2-WU-PR-PW.405
Staging time 30 25-Dec-23 28-Jan-24 Staging time

JAH-Z2-WU-PR-PW.410
Material Delivery 90 29-Jan-24 15-May-24 Material Delivery

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 145 19-Dec-23 08-Jun-24 08-Jun-24, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 19-Dec-23 08-Jun-24 08-Jun-24, DI PIPES
JAH-Z2-WU-PR-GWD.218
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.220
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.225
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.230
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

HDPE PIPES 145 19-Dec-23 08-Jun-24 08-Jun-24, HDPE PIPES


JAH-Z2-WU-PR-GWD.232
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.235
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.240
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.245
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

GRP PIPES 145 19-Dec-23 08-Jun-24 08-Jun-24, GRP PIPES

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
241 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-WU-PR-GWD.248
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.250
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.255
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.260
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

DI & GRP FITTING 145 19-Dec-23 08-Jun-24 08-Jun-24, DI & GRP FITTING
JAH-Z2-WU-PR-GWD.262
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.265
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.270
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.275
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

GATE VALVE 145 19-Dec-23 08-Jun-24 08-Jun-24, GATE VALVE


JAH-Z2-WU-PR-GWD.277
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.280
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.285
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.290
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

BUTTERFLAY VALVE 145 19-Dec-23 08-Jun-24 08-Jun-24, BUTTERFLAY VALVE


JAH-Z2-WU-PR-GWD.293
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.295
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.300
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.305
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

AIR RELASE VALVE 145 19-Dec-23 08-Jun-24 08-Jun-24, AIR RELASE VALVE
JAH-Z2-WU-PR-GWD.308
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.310
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.315
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.320
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

WASEHOUT VALVE 145 19-Dec-23 08-Jun-24 08-Jun-24, WASEHOUT VALVE


JAH-Z2-WU-PR-GWD.322
Request for Quotation 10 19-Dec-23 30-Dec-23 Request for Quotation

JAH-Z2-WU-PR-GWD.325
Issue Purchase Order 15 31-Dec-23 16-Jan-24 Issue Purchase Order

JAH-Z2-WU-PR-GWD.330
Staging time 30 17-Jan-24 20-Feb-24 Staging time

JAH-Z2-WU-PR-GWD.335
Material Delivery 90 21-Feb-24 08-Jun-24 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 145 11-Jan-24 06-Jul-24 06-Jul-24, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 11-Jan-24 06-Jul-24 06-Jul-24, HDPE PIPES
JAH-Z2-WU-PR-IRR.188
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.190
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.195
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.200
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

GATE VALVE 145 11-Jan-24 06-Jul-24 06-Jul-24, GATE VALVE


JAH-Z2-WU-PR-IRR.203
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.205
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.210
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.215
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

BUTTERFLAY VALVE 145 11-Jan-24 06-Jul-24 06-Jul-24, BUTTERFLAY VALVE


JAH-Z2-WU-PR-IRR.218
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.220
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.225
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.230
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

AIR RELASE VALVE 145 11-Jan-24 06-Jul-24 06-Jul-24, AIR RELASE VALVE

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
242 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-WU-PR-IRR.232
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.235
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.240
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.245
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

WASEHOUT VALVE 145 11-Jan-24 06-Jul-24 06-Jul-24, WASEHOUT VALVE


JAH-Z2-WU-PR-IRR.248
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.250
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.255
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.260
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

FIRE HYDRANT 145 11-Jan-24 06-Jul-24 06-Jul-24, FIRE HYDRANT


JAH-Z2-WU-PR-IRR.262
Request for Quotation 10 11-Jan-24 22-Jan-24 Request for Quotation

JAH-Z2-WU-PR-IRR.265
Issue Purchase Order 15 23-Jan-24 08-Feb-24 Issue Purchase Order

JAH-Z2-WU-PR-IRR.270
Staging time 30 10-Feb-24 14-Mar-24 Staging time

JAH-Z2-WU-PR-IRR.275
Material Delivery 90 16-Mar-24 06-Jul-24 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 145 18-Feb-24 12-Aug-24 12-Aug-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 18-Feb-24 12-Aug-24 12-Aug-24, MILD STEEL PIPE
JAH-Z2-WU-PR-CWS.143
Request for Quotation 10 18-Feb-24 28-Feb-24 Request for Quotation

JAH-Z2-WU-PR-CWS.145
Issue Purchase Order 15 29-Feb-24 17-Mar-24 Issue Purchase Order

JAH-Z2-WU-PR-CWS.150
Staging time 30 18-Mar-24 24-Apr-24 Staging time

JAH-Z2-WU-PR-CWS.155
Material Delivery 90 25-Apr-24 12-Aug-24 Material Delivery

MILD STEEL FITTING 145 18-Feb-24 12-Aug-24 12-Aug-24, MILD STEEL FITTING
JAH-Z2-WU-PR-CWS.158
Request for Quotation 10 18-Feb-24 28-Feb-24 Request for Quotation

JAH-Z2-WU-PR-CWS.160
Issue Purchase Order 15 29-Feb-24 17-Mar-24 Issue Purchase Order

JAH-Z2-WU-PR-CWS.165
Staging time 30 18-Mar-24 24-Apr-24 Staging time

JAH-Z2-WU-PR-CWS.170
Material Delivery 90 25-Apr-24 12-Aug-24 Material Delivery

GATE VALVE 145 18-Feb-24 12-Aug-24 12-Aug-24, GATE VALVE


JAH-Z2-WU-PR-CWS.172
Request for Quotation 10 18-Feb-24 28-Feb-24 Request for Quotation

JAH-Z2-WU-PR-CWS.175
Issue Purchase Order 15 29-Feb-24 17-Mar-24 Issue Purchase Order

JAH-Z2-WU-PR-CWS.180
Staging time 30 18-Mar-24 24-Apr-24 Staging time

JAH-Z2-WU-PR-CWS.185
Material Delivery 90 25-Apr-24 12-Aug-24 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 26-Mar-24 18-Sep-24 18-Sep-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 26-Mar-24 18-Sep-24 18-Sep-24, AUTOMATIC WASTE
JAH-Z2-WU-PR-AWC.100
Request for Quotation 10 26-Mar-24 06-Apr-24 Request for Quotation

JAH-Z2-WU-PR-AWC.105
Issue Purchase Order 15 07-Apr-24 27-Apr-24 Issue Purchase Order

JAH-Z2-WU-PR-AWC.110
Staging time 30 28-Apr-24 01-Jun-24 Staging time

JAH-Z2-WU-PR-AWC.115
Material Delivery 90 02-Jun-24 18-Sep-24 Material Delivery

DRY UTILITIES 241 02-Jan-24 17-Oct-24 17-Oct-24, DRY UTILITIES


POWER 209 02-Jan-24 09-Sep-24 09-Sep-24, POWER
HIGH VOLTAGE 110 KV NETWORK 145 02-Jan-24 26-Jun-24 26-Jun-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z2-DU-PR-PWR.265
Request for Quotation 10 02-Jan-24 13-Jan-24 Request for Quotation

JAH-Z2-DU-PR-PWR.270
Issue Purchase Order 15 14-Jan-24 30-Jan-24 Issue Purchase Order

JAH-Z2-DU-PR-PWR.275
Material Delivery 90 06-Mar-24 26-Jun-24 Material Delivery

JAH-Z2-DU-PR-PWR.295
Staging time 30 31-Jan-24 05-Mar-24 Staging time

MEDIUM VOLTAGE 13.8 KV NETWORK 145 02-Jan-24 26-Jun-24 26-Jun-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z2-DU-PR-PWR.305
Request for Quotation 10 02-Jan-24 13-Jan-24 Request for Quotation

JAH-Z2-DU-PR-PWR.310
Issue Purchase Order 15 14-Jan-24 30-Jan-24 Issue Purchase Order

JAH-Z2-DU-PR-PWR.315
Material Delivery 90 06-Mar-24 26-Jun-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
243 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-DU-PR-PWR.320
Staging time 30 31-Jan-24 05-Mar-24 Staging time

LOW VOLTAGE NETWORK 145 02-Jan-24 26-Jun-24 26-Jun-24, LOW VOLTAGE NETWORK
JAH-Z2-DU-PR-PWR.325
Request for Quotation 10 02-Jan-24 13-Jan-24 Request for Quotation

JAH-Z2-DU-PR-PWR.330
Issue Purchase Order 15 14-Jan-24 30-Jan-24 Issue Purchase Order

JAH-Z2-DU-PR-PWR.335
Material Delivery 90 06-Mar-24 26-Jun-24 Material Delivery

JAH-Z2-DU-PR-PWR.340
Staging time 30 31-Jan-24 05-Mar-24 Staging time

ELECTRICAL DISTRIBUTION SYSTEM 145 08-Feb-24 03-Aug-24 03-Aug-24, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z2-DU-PR-PWR.280
Request for Quotation 10 08-Feb-24 19-Feb-24 Request for Quotation

JAH-Z2-DU-PR-PWR.285
Issue Purchase Order 15 20-Feb-24 07-Mar-24 Issue Purchase Order

JAH-Z2-DU-PR-PWR.290
Material Delivery 90 16-Apr-24 03-Aug-24 Material Delivery

JAH-Z2-DU-PR-PWR.300
Staging time 30 09-Mar-24 15-Apr-24 Staging time

LIGHTING SYSTEM 145 17-Mar-24 09-Sep-24 09-Sep-24, LIGHTING SYSTEM


JAH-Z2-DU-PR-PWR.345
Request for Quotation 10 17-Mar-24 27-Mar-24 Request for Quotation

JAH-Z2-DU-PR-PWR.350
Issue Purchase Order 15 28-Mar-24 17-Apr-24 Issue Purchase Order

JAH-Z2-DU-PR-PWR.355
Material Delivery 90 23-May-24 09-Sep-24 Material Delivery

JAH-Z2-DU-PR-PWR.360
Staging time 30 18-Apr-24 22-May-24 Staging time

LOW CURRENT 145 27-Apr-24 17-Oct-24 17-Oct-24, LOW CURRENT


TELECOM SERVICES 145 27-Apr-24 17-Oct-24 17-Oct-24, TELECOM SERVICES
JAH-Z2-DU-PR-LC.165Request for Quotation 10 27-Apr-24 07-May-24 Request for Quotation

JAH-Z2-DU-PR-LC.170Issue Purchase Order 15 08-May-24 25-May-24 Issue Purchase Order

JAH-Z2-DU-PR-LC.175Material Delivery 90 04-Jul-24 17-Oct-24 Material Delivery

JAH-Z2-DU-PR-LC.180Staging time 30 26-May-24 03-Jul-24 Staging time

MEP 235 19-Apr-23 25-Jan-24 25-Jan-24, MEP


JAH-Z2-PRO-MEP.120 Request for Quotation 10 19-Apr-23 03-May-23 Request for Quotation

JAH-Z2-PRO-MEP.125 Issue Purchase Order 15 04-May-23 21-May-23 Issue Purchase Order

JAH-Z2-PRO-MEP.128 Staging Time 30 22-May-23 25-Jun-23 Staging Time

JAH-Z2-PRO-MEP.130 Material Delivery 180 26-Jun-23 25-Jan-24 Material Delivery

ARCHITECTURAL 115 14-Nov-23 26-Mar-24 26-Mar-24, ARCHITECTURAL


JAH-Z2-PRO-ARC.120 Request for Quotation 10 14-Nov-23 25-Nov-23 Request for Quotation

JAH-Z2-PRO-ARC.125 Issue Purchase Order 15 26-Nov-23 12-Dec-23 Issue Purchase Order

JAH-Z2-PRO-ARC.128 Staging Time 30 13-Dec-23 16-Jan-24 Staging Time

JAH-Z2-PRO-ARC.130 Material Delivery 60 17-Jan-24 26-Mar-24 Material Delivery

CONSTRUCTION 726 17-Aug-22 A 17-Jun-25 17-Jun-25, CONSTRUCTION


GENERAL SITE ARRANGEMENT 238 14-Sep-22 A 26-Aug-23 26-Aug-23, GENERAL SITE ARRANGEMENT
SITE PREPARATION 238 14-Sep-22 A 26-Aug-23 26-Aug-23, SITE PREPARATION
JAH-Z2-CON-GA-SP.115Site Clearing & Grubbing / Demolition of Obstacles 15 14-Sep-22 A 23-Jul-23 Site Clearing & Grubbing / Demolition of Obstacles

JAH-Z2-CON-GA-SP.120Disposal /Removal of Unnecessary Objects from Site 8 25-Sep-22 A 23-Jul-23 Disposal /Removal of Unnecessary Objects from Site

JAH-Z2-CON-GA-SP.125Relocation of Exisiting Utilities 30 23-Jul-23 26-Aug-23 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 72 17-Aug-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION


JAH-Z2-CON-GTI.100 Borehole Layout Preparation & Submission 15 17-Aug-22 A 19-Aug-22 A Borehole Layout Preparation & Submission

JAH-Z2-CON-GTI.105 Borehole Layout Review & Approval 7 20-Aug-22 A 21-Aug-22 A Borehole Layout Review & Approval

JAH-Z2-CON-GTI.110 Drilling Boreholes 30 21-Aug-22 A 22-Aug-22 A Drilling Boreholes

JAH-Z2-CON-GTI.115 Issuance of Geo-Technical Investigation Report 20 23-Aug-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 385 04-Oct-22 A 07-Sep-24 07-Sep-24, EXCAVATION & DEWATERING
JAH-Z2-CON-DE.102 Dewatering @Sta. 0+500 ~ 0+600 256 09-Oct-22 A 30-Oct-23 Dewatering @Sta. 0+500 ~ 0+600

JAH-Z2-CON-DE.107 Dewatering @Sta. 0+600 ~ 0+700 267 17-Oct-22 A 24-Dec-23 Dewatering @Sta. 0+600 ~ 0+700

JAH-Z2-CON-DE.112 Dewatering @Sta. 0+700 ~ 0+800 283 19-Jul-23 22-Jun-24 Dewatering @Sta. 0+700 ~ 0+800

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
244 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-CON-DE.117 Dewatering @Sta. 0+800 ~ 0+900 298 30-Aug-23 20-Aug-24 Dewatering @Sta. 0+800 ~ 0+900

JAH-Z2-CON-DE.125 Dewatering @Sta. 0+900 ~ 0+994 277 12-Oct-23 07-Sep-24 Dewatering @Sta. 0+900 ~ 0+994

JAH-Z2-CON-EX.100 Excavation & Shoring System @Sta. 0+500 ~ 0+600 30 04-Oct-22 A 27-Apr-23 Excavation & Shoring System @Sta. 0+500 ~ 0+600

JAH-Z2-CON-EX.105 Excavation & Shoring System @Sta. 0+600 ~ 0+700 30 04-Jun-23 11-Jul-23 Excavation & Shoring System @Sta. 0+600 ~ 0+700

JAH-Z2-CON-EX.110 Excavation & Shoring System @Sta. 0+700 ~ 0+800 30 15-Oct-22 A 22-Aug-23 Excavation & Shoring System @Sta. 0+700 ~ 0+800

JAH-Z2-CON-EX.115 Excavation & Shoring System @Sta. 0+800 ~ 0+900 30 30-Aug-23 04-Oct-23 Excavation & Shoring System @Sta. 0+800 ~ 0+900

JAH-Z2-CON-EX.120 Excavation & Shoring System @Sta. 0+900 ~ 0+994 30 12-Oct-23 15-Nov-23 Excavation & Shoring System @Sta. 0+900 ~ 0+994

SOIL IMPROVEMENT 179 29-Apr-23 27-Nov-23 27-Nov-23, SOIL IMPROVEMENT


JAH-Z2-CON-SIMP.101 Soil Improvement @Sta. 0+500 ~ 0+600 10 29-Apr-23 09-May-23 Soil Improvement @Sta. 0+500 ~ 0+600

JAH-Z2-CON-SIMP.106 Soil Improvement @Sta. 0+600 ~ 0+700 10 12-Jul-23 23-Jul-23 Soil Improvement @Sta. 0+600 ~ 0+700

JAH-Z2-CON-SIMP.111 Soil Improvement @Sta. 0+700 ~ 0+800 10 23-Aug-23 03-Sep-23 Soil Improvement @Sta. 0+700 ~ 0+800

JAH-Z2-CON-SIMP.116 Soil Improvement @Sta. 0+800 ~ 0+900 10 05-Oct-23 16-Oct-23 Soil Improvement @Sta. 0+800 ~ 0+900

JAH-Z2-CON-SIMP.121 Soil Improvement @Sta. 0+900 ~ 0+994 10 16-Nov-23 27-Nov-23 Soil Improvement @Sta. 0+900 ~ 0+994

STRUCTURAL WORKS 368 27-Aug-23 07-Nov-24 07-Nov-24, STRUCTURAL WORKS


STA. 0+510.033 ~ 0+530.033 168 27-Aug-23 10-Mar-24 10-Mar-24, STA. 0+510.033 ~ 0+530.033
BASE SLAB 27 27-Aug-23 27-Sep-23 27-Sep-23, BASE SLAB
JAH-Z2-ST-S1-BS.100 Lean Concrete for Base Slab 1 27-Aug-23 27-Aug-23 Lean Concrete for Base Slab

JAH-Z2-ST-S1-BS.105 Waterproofing for Lean Concrete 1 28-Aug-23 28-Aug-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S1-BS.110 Base Slab Rebar Installation 8 29-Aug-23 06-Sep-23 Base Slab Rebar Installation

JAH-Z2-ST-S1-BS.115 Base Slab Formwork Installation 7 07-Sep-23 14-Sep-23 Base Slab Formwork Installation

JAH-Z2-ST-S1-BS.120 Base Slab Concrete Casting 1 16-Sep-23 16-Sep-23 Base Slab Concrete Casting

JAH-Z2-ST-S1-BS.122 Curing work 7 17-Sep-23 25-Sep-23 Curing work

JAH-Z2-ST-S1-BS.125 Base Slab Formwork Removel 2 26-Sep-23 27-Sep-23 Base Slab Formwork Removel

COLUMN 23 28-Sep-23 24-Oct-23 24-Oct-23, COLUMN


JAH-Z2-ST-S1-CL.100 Column Rebar Installation 8 28-Sep-23 07-Oct-23 Column Rebar Installation

JAH-Z2-ST-S1-CL.105 Column Formwork Installation 7 08-Oct-23 15-Oct-23 Column Formwork Installation

JAH-Z2-ST-S1-CL.110 Column Concrete Casting 1 16-Oct-23 16-Oct-23 Column Concrete Casting

JAH-Z2-ST-S1-CL.115 Form Work Removal and Curing 7 17-Oct-23 24-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 28-Sep-23 09-Nov-23 09-Nov-23, TUNNEL WALLS


JAH-Z2-ST-S1-TW.100 Tunnel Walls Rebar Installation 8 28-Sep-23 07-Oct-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S1-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Sep-23 07-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S1-TW.105 Tunnel Formwork Installation 7 08-Oct-23 15-Oct-23 Tunnel Formwork Installation

JAH-Z2-ST-S1-TW.110 Tunnel Walls Concrete Casting 1 16-Oct-23 16-Oct-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S1-TW.115 Curing work 7 17-Oct-23 24-Oct-23 Curing work

JAH-Z2-ST-S1-TW.120 Tunnel Walls Formwork Removel 2 25-Oct-23 26-Oct-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S1-TW.125 Tunnel Wall Waterproofing 12 28-Oct-23 09-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-Oct-23 30-Nov-23 30-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S1-MS.090 Middle Slab Scaffold and Formwork Installation 5 28-Oct-23 01-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S1-MS.100 Middle Slab Rebar Installation 8 02-Nov-23 11-Nov-23 Middle Slab Rebar Installation

JAH-Z2-ST-S1-MS.105 Middle Slab Vertical Formwork Installation 7 12-Nov-23 19-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S1-MS.110 Middle Slab Concrete Casting 1 20-Nov-23 20-Nov-23 Middle Slab Concrete Casting

JAH-Z2-ST-S1-MS.115 Curing work 7 21-Nov-23 28-Nov-23 Curing work

JAH-Z2-ST-S1-MS.120 Middle Slab Formwork Removel 2 29-Nov-23 30-Nov-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 02-Dec-23 30-Dec-23 30-Dec-23, UTILITY CULVERT WALLS


JAH-Z2-ST-S1-UCW.100Utility Culvert Walls Rebar Installation 8 02-Dec-23 10-Dec-23 Utility Culvert Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
245 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S1-UCW.105Utility Culvert Walls Formwork Installation 7 11-Dec-23 18-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S1-UCW.110Utility Culvert Walls Concrete Casting 1 19-Dec-23 19-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S1-UCW.112Curing work 7 20-Dec-23 27-Dec-23 Curing work

JAH-Z2-ST-S1-UCW.115Utility Culvert Walls Walls Formwork Removel 2 28-Dec-23 30-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 31-Dec-23 11-Feb-24 11-Feb-24, TOP SLAB


JAH-Z2-ST-S1-TS.090 Top Slab Formwork Installation 7 31-Dec-23 07-Jan-24 Top Slab Formwork Installation

JAH-Z2-ST-S1-TS.100 Top Slab Rebar Installation 8 08-Jan-24 16-Jan-24 Top Slab Rebar Installation

JAH-Z2-ST-S1-TS.110 Top Slab Concrete Casting 1 17-Jan-24 17-Jan-24 Top Slab Concrete Casting

JAH-Z2-ST-S1-TS.112 Curing work 7 18-Jan-24 25-Jan-24 Curing work

JAH-Z2-ST-S1-TS.115 Top Slab Formwork Removel 2 27-Jan-24 28-Jan-24 Top Slab Formwork Removel

JAH-Z2-ST-S1-TS.120 Waterproofing for Top Slab 12 29-Jan-24 11-Feb-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 12-Feb-24 10-Mar-24 10-Mar-24, MASS CONCRETE WORK


JAH-Z2-ST-S1-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 12-Feb-24 19-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S1-MC.105 Plain Concrete Casting 1 20-Feb-24 20-Feb-24 Plain Concrete Casting

JAH-Z2-ST-S1-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 21-Feb-24 21-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S1-MC.112 Curing work 7 22-Feb-24 29-Feb-24 Curing work

JAH-Z2-ST-S1-MC.115 Concrete Protective coating 8 02-Mar-24 10-Mar-24 Concrete Protective coating

STA.0+530.033 ~ 0+550.033 168 07-Sep-23 21-Mar-24 21-Mar-24, STA.0+530.033 ~ 0+550.033


BASE SLAB 27 07-Sep-23 09-Oct-23 09-Oct-23, BASE SLAB
JAH-Z2-ST-S2-BS.100 Lean Concrete for Base Slab 1 07-Sep-23 07-Sep-23 Lean Concrete for Base Slab

JAH-Z2-ST-S2-BS.105 Waterproofing for Lean Concrete 1 09-Sep-23 09-Sep-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S2-BS.110 Base Slab Rebar Installation 8 10-Sep-23 18-Sep-23 Base Slab Rebar Installation

JAH-Z2-ST-S2-BS.115 Base Slab Formwork Installation 7 19-Sep-23 27-Sep-23 Base Slab Formwork Installation

JAH-Z2-ST-S2-BS.120 Base Slab Concrete Casting 1 28-Sep-23 28-Sep-23 Base Slab Concrete Casting

JAH-Z2-ST-S2-BS.122 Curing work 7 30-Sep-23 07-Oct-23 Curing work

JAH-Z2-ST-S2-BS.125 Base Slab Formwork Removel 2 08-Oct-23 09-Oct-23 Base Slab Formwork Removel

COLUMN 23 10-Oct-23 05-Nov-23 05-Nov-23, COLUMN


JAH-Z2-ST-S2-CL.100 Column Rebar Installation 8 10-Oct-23 18-Oct-23 Column Rebar Installation

JAH-Z2-ST-S2-CL.105 Column Formwork Installation 7 19-Oct-23 26-Oct-23 Column Formwork Installation

JAH-Z2-ST-S2-CL.110 Column Concrete Casting 1 28-Oct-23 28-Oct-23 Column Concrete Casting

JAH-Z2-ST-S2-CL.115 Form Work Removal and Curing 7 29-Oct-23 05-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 10-Oct-23 21-Nov-23 21-Nov-23, TUNNEL WALLS


JAH-Z2-ST-S2-TW.100 Tunnel Walls Rebar Installation 8 10-Oct-23 18-Oct-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S2-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 10-Oct-23 18-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S2-TW.105 Tunnel Formwork Installation 7 19-Oct-23 26-Oct-23 Tunnel Formwork Installation

JAH-Z2-ST-S2-TW.110 Tunnel Walls Concrete Casting 1 28-Oct-23 28-Oct-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S2-TW.112 Curing work 7 29-Oct-23 05-Nov-23 Curing work

JAH-Z2-ST-S2-TW.120 Tunnel Walls Formwork Removel 2 06-Nov-23 07-Nov-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S2-TW.125 Tunnel Wall Waterproofing 12 08-Nov-23 21-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 08-Nov-23 12-Dec-23 12-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S2-MS.090 Middle Slab Scaffold and Formwork Installation 5 08-Nov-23 13-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S2-MS.100 Middle Slab Rebar Installation 8 14-Nov-23 22-Nov-23 Middle Slab Rebar Installation

JAH-Z2-ST-S2-MS.105 Middle Slab Vertical Formwork Installation 7 23-Nov-23 30-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S2-MS.110 Middle Slab Concrete Casting 1 02-Dec-23 02-Dec-23 Middle Slab Concrete Casting

JAH-Z2-ST-S2-MS.115 Curing work 7 03-Dec-23 10-Dec-23 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
246 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S2-MS.120 Middle Slab Formwork Removel 2 11-Dec-23 12-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 13-Dec-23 10-Jan-24 10-Jan-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S2-UCW.100Utility Culvert Walls Rebar Installation 8 13-Dec-23 21-Dec-23 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S2-UCW.105Utility Culvert Walls Formwork Installation 7 23-Dec-23 30-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S2-UCW.110Utility Culvert Walls Concrete Casting 1 31-Dec-23 31-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S2-UCW.112Curing work 7 01-Jan-24 08-Jan-24 Curing work

JAH-Z2-ST-S2-UCW.115Utility Culvert Walls Walls Formwork Removel 2 09-Jan-24 10-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 11-Jan-24 22-Feb-24 22-Feb-24, TOP SLAB


JAH-Z2-ST-S2-TS.090 Top Slab Formwork Installation 7 11-Jan-24 18-Jan-24 Top Slab Formwork Installation

JAH-Z2-ST-S2-TS.100 Top Slab Rebar Installation 8 20-Jan-24 28-Jan-24 Top Slab Rebar Installation

JAH-Z2-ST-S2-TS.110 Top Slab Concrete Casting 1 29-Jan-24 29-Jan-24 Top Slab Concrete Casting

JAH-Z2-ST-S2-TS.112 Curing work 7 30-Jan-24 06-Feb-24 Curing work

JAH-Z2-ST-S2-TS.115 Top Slab Formwork Removel 2 07-Feb-24 08-Feb-24 Top Slab Formwork Removel

JAH-Z2-ST-S2-TS.120 Waterproofing for Top Slab 12 10-Feb-24 22-Feb-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 24-Feb-24 21-Mar-24 21-Mar-24, MASS CONCRETE WORK


JAH-Z2-ST-S2-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 24-Feb-24 02-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S2-MC.105 Plain Concrete Casting 1 03-Mar-24 03-Mar-24 Plain Concrete Casting

JAH-Z2-ST-S2-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 04-Mar-24 04-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S2-MC.112 Curing work 7 05-Mar-24 12-Mar-24 Curing work

JAH-Z2-ST-S2-MC.115 Concrete Protective coating 8 13-Mar-24 21-Mar-24 Concrete Protective coating

STA. 0+550.033 ~ 0+570.033 168 19-Sep-23 02-Apr-24 02-Apr-24, STA. 0+550.033 ~ 0+570.033
BASE SLAB 27 19-Sep-23 21-Oct-23 21-Oct-23, BASE SLAB
JAH-Z2-ST-S3-BS.100 Lean Concrete for Base Slab 1 19-Sep-23 19-Sep-23 Lean Concrete for Base Slab

JAH-Z2-ST-S3-BS.105 Waterproofing for Lean Concrete 1 20-Sep-23 20-Sep-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S3-BS.110 Base Slab Rebar Installation 8 21-Sep-23 01-Oct-23 Base Slab Rebar Installation

JAH-Z2-ST-S3-BS.115 Base Slab Formwork Installation 7 02-Oct-23 09-Oct-23 Base Slab Formwork Installation

JAH-Z2-ST-S3-BS.120 Base Slab Concrete Casting 1 10-Oct-23 10-Oct-23 Base Slab Concrete Casting

JAH-Z2-ST-S3-BS.122 Curing work 7 11-Oct-23 18-Oct-23 Curing work

JAH-Z2-ST-S3-BS.125 Base Slab Formwork Removel 2 19-Oct-23 21-Oct-23 Base Slab Formwork Removel

COLUMN 23 22-Oct-23 16-Nov-23 16-Nov-23, COLUMN


JAH-Z2-ST-S3-CL.100 Column Rebar Installation 8 22-Oct-23 30-Oct-23 Column Rebar Installation

JAH-Z2-ST-S3-CL.105 Column Formwork Installation 7 31-Oct-23 07-Nov-23 Column Formwork Installation

JAH-Z2-ST-S3-CL.110 Column Concrete Casting 1 08-Nov-23 08-Nov-23 Column Concrete Casting

JAH-Z2-ST-S3-CL.115 Form Work Removal and Curing 7 09-Nov-23 16-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 22-Oct-23 03-Dec-23 03-Dec-23, TUNNEL WALLS


JAH-Z2-ST-S3-TW.100 Tunnel Walls Rebar Installation 8 22-Oct-23 30-Oct-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S3-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-Oct-23 30-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S3-TW.105 Tunnel Formwork Installation 7 31-Oct-23 07-Nov-23 Tunnel Formwork Installation

JAH-Z2-ST-S3-TW.110 Tunnel Walls Concrete Casting 1 08-Nov-23 08-Nov-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S3-TW.112 Curing work 7 09-Nov-23 16-Nov-23 Curing work

JAH-Z2-ST-S3-TW.120 Tunnel Walls Formwork Removel 2 18-Nov-23 19-Nov-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S3-TW.125 Tunnel Wall Waterproofing 12 20-Nov-23 03-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 20-Nov-23 24-Dec-23 24-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S3-MS.090 Middle Slab Scaffold and Formwork Installation 5 20-Nov-23 25-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S3-MS.100 Middle Slab Rebar Installation 8 26-Nov-23 04-Dec-23 Middle Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
247 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S3-MS.105 Middle Slab Vertical Formwork Installation 7 05-Dec-23 12-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S3-MS.110 Middle Slab Concrete Casting 1 13-Dec-23 13-Dec-23 Middle Slab Concrete Casting

JAH-Z2-ST-S3-MS.115 Curing work 7 14-Dec-23 21-Dec-23 Curing work

JAH-Z2-ST-S3-MS.120 Middle Slab Formwork Removel 2 23-Dec-23 24-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 25-Dec-23 22-Jan-24 22-Jan-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S3-UCW.100Utility Culvert Walls Rebar Installation 8 25-Dec-23 02-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S3-UCW.105Utility Culvert Walls Formwork Installation 7 03-Jan-24 10-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S3-UCW.110Utility Culvert Walls Concrete Casting 1 11-Jan-24 11-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S3-UCW.112Curing work 7 13-Jan-24 20-Jan-24 Curing work

JAH-Z2-ST-S3-UCW.115Utility Culvert Walls Walls Formwork Removel 2 21-Jan-24 22-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 23-Jan-24 05-Mar-24 05-Mar-24, TOP SLAB


JAH-Z2-ST-S3-TS.090 Top Slab Formwork Installation 7 23-Jan-24 30-Jan-24 Top Slab Formwork Installation

JAH-Z2-ST-S3-TS.100 Top Slab Rebar Installation 8 31-Jan-24 08-Feb-24 Top Slab Rebar Installation

JAH-Z2-ST-S3-TS.110 Top Slab Concrete Casting 1 10-Feb-24 10-Feb-24 Top Slab Concrete Casting

JAH-Z2-ST-S3-TS.112 Curing work 7 11-Feb-24 18-Feb-24 Curing work

JAH-Z2-ST-S3-TS.115 Top Slab Formwork Removel 2 19-Feb-24 20-Feb-24 Top Slab Formwork Removel

JAH-Z2-ST-S3-TS.120 Waterproofing for Top Slab 12 21-Feb-24 05-Mar-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 06-Mar-24 02-Apr-24 02-Apr-24, MASS CONCRETE WORK


JAH-Z2-ST-S3-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 06-Mar-24 13-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S3-MC.105 Plain Concrete Casting 1 14-Mar-24 14-Mar-24 Plain Concrete Casting

JAH-Z2-ST-S3-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 16-Mar-24 16-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S3-MC.112 Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z2-ST-S3-MC.115 Concrete Protective coating 8 25-Mar-24 02-Apr-24 Concrete Protective coating

STA. 0+570.033~ 0+590.033 161 02-Oct-23 06-Apr-24 06-Apr-24, STA. 0+570.033~ 0+590.033
BASE SLAB 20 02-Oct-23 24-Oct-23 24-Oct-23, BASE SLAB
JAH-Z2-ST-S4-BS.100 Lean Concrete for Base Slab 1 02-Oct-23 02-Oct-23 Lean Concrete for Base Slab

JAH-Z2-ST-S4-BS.105 Waterproofing for Lean Concrete 1 03-Oct-23 03-Oct-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S4-BS.110 Base Slab Rebar Installation 8 04-Oct-23 12-Oct-23 Base Slab Rebar Installation

JAH-Z2-ST-S4-BS.115 Base Slab Formwork Installation 7 14-Oct-23 21-Oct-23 Base Slab Formwork Installation

JAH-Z2-ST-S4-BS.120 Base Slab Concrete Casting 1 22-Oct-23 22-Oct-23 Base Slab Concrete Casting

JAH-Z2-ST-S4-BS.125 Base Slab Formwork Removel 2 23-Oct-23 24-Oct-23 Base Slab Formwork Removel

COLUMN 20 25-Oct-23 16-Nov-23 16-Nov-23, COLUMN


JAH-Z2-ST-S4-CL.100 Column Rebar Installation 8 25-Oct-23 02-Nov-23 Column Rebar Installation

JAH-Z2-ST-S4-CL.105 Column Formwork Installation 7 04-Nov-23 11-Nov-23 Column Formwork Installation

JAH-Z2-ST-S4-CL.110 Column Concrete Casting 1 12-Nov-23 12-Nov-23 Column Concrete Casting

JAH-Z2-ST-S4-CL.115 Form Work Removal and Curing 4 13-Nov-23 16-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 25-Oct-23 06-Dec-23 06-Dec-23, TUNNEL WALLS


JAH-Z2-ST-S4-TW.100 Tunnel Walls Rebar Installation 8 25-Oct-23 02-Nov-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S4-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 25-Oct-23 02-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S4-TW.105 Tunnel Formwork Installation 7 04-Nov-23 11-Nov-23 Tunnel Formwork Installation

JAH-Z2-ST-S4-TW.110 Tunnel Walls Concrete Casting 1 12-Nov-23 12-Nov-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S4-TW.112 Curing work 7 13-Nov-23 20-Nov-23 Curing work

JAH-Z2-ST-S4-TW.120 Tunnel Walls Formwork Removel 2 21-Nov-23 22-Nov-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S4-TW.125 Tunnel Wall Waterproofing 12 23-Nov-23 06-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 23-Nov-23 27-Dec-23 27-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
248 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S4-MS.090 Middle Slab Scaffold and Formwork Installation 5 23-Nov-23 28-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S4-MS.100 Middle Slab Rebar Installation 8 29-Nov-23 07-Dec-23 Middle Slab Rebar Installation

JAH-Z2-ST-S4-MS.105 Middle Slab Vertical Formwork Installation 7 09-Dec-23 16-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S4-MS.110 Middle Slab Concrete Casting 1 17-Dec-23 17-Dec-23 Middle Slab Concrete Casting

JAH-Z2-ST-S4-MS.115 Curing work 7 18-Dec-23 25-Dec-23 Curing work

JAH-Z2-ST-S4-MS.120 Middle Slab Formwork Removel 2 26-Dec-23 27-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 28-Dec-23 25-Jan-24 25-Jan-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S4-UCW.100Utility Culvert Walls Rebar Installation 8 28-Dec-23 06-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S4-UCW.105Utility Culvert Walls Formwork Installation 7 07-Jan-24 14-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S4-UCW.110Utility Culvert Walls Concrete Casting 1 15-Jan-24 15-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S4-UCW.112Curing work 7 16-Jan-24 23-Jan-24 Curing work

JAH-Z2-ST-S4-UCW.115Utility Culvert Walls Walls Formwork Removel 2 24-Jan-24 25-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 27-Jan-24 09-Mar-24 09-Mar-24, TOP SLAB


JAH-Z2-ST-S4-TS.090 Top Slab Formwork Installation 7 27-Jan-24 03-Feb-24 Top Slab Formwork Installation

JAH-Z2-ST-S4-TS.100 Top Slab Rebar Installation 8 04-Feb-24 12-Feb-24 Top Slab Rebar Installation

JAH-Z2-ST-S4-TS.110 Top Slab Concrete Casting 1 13-Feb-24 13-Feb-24 Top Slab Concrete Casting

JAH-Z2-ST-S4-TS.112 Curing work 7 14-Feb-24 21-Feb-24 Curing work

JAH-Z2-ST-S4-TS.115 Top Slab Formwork Removel 2 22-Feb-24 24-Feb-24 Top Slab Formwork Removel

JAH-Z2-ST-S4-TS.120 Waterproofing for Top Slab 12 25-Feb-24 09-Mar-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 10-Mar-24 06-Apr-24 06-Apr-24, MASS CONCRETE WORK


JAH-Z2-ST-S4-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 10-Mar-24 17-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S4-MC.105 Plain Concrete Casting 1 18-Mar-24 18-Mar-24 Plain Concrete Casting

JAH-Z2-ST-S4-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 19-Mar-24 19-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S4-MC.112 Curing work 7 20-Mar-24 27-Mar-24 Curing work

JAH-Z2-ST-S4-MC.115 Concrete Protective coating 8 28-Mar-24 06-Apr-24 Concrete Protective coating

STA. 0+590.033 ~ 0+610.033 168 14-Oct-23 29-Apr-24 29-Apr-24, STA. 0+590.033 ~ 0+610.033
BASE SLAB 27 14-Oct-23 13-Nov-23 13-Nov-23, BASE SLAB
JAH-Z2-ST-S5-BS.100 Lean Concrete for Base Slab 1 14-Oct-23 14-Oct-23 Lean Concrete for Base Slab

JAH-Z2-ST-S5-BS.105 Waterproofing for Lean Concrete 1 15-Oct-23 15-Oct-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S5-BS.110 Base Slab Rebar Installation 8 16-Oct-23 24-Oct-23 Base Slab Rebar Installation

JAH-Z2-ST-S5-BS.115 Base Slab Formwork Installation 7 25-Oct-23 01-Nov-23 Base Slab Formwork Installation

JAH-Z2-ST-S5-BS.120 Base Slab Concrete Casting 1 02-Nov-23 02-Nov-23 Base Slab Concrete Casting

JAH-Z2-ST-S5-BS.122 Curing work 7 04-Nov-23 11-Nov-23 Curing work

JAH-Z2-ST-S5-BS.125 Base Slab Formwork Removel 2 12-Nov-23 13-Nov-23 Base Slab Formwork Removel

COLUMN 23 14-Nov-23 10-Dec-23 10-Dec-23, COLUMN


JAH-Z2-ST-S5-CL.100 Column Rebar Installation 8 14-Nov-23 22-Nov-23 Column Rebar Installation

JAH-Z2-ST-S5-CL.105 Column Formwork Installation 7 23-Nov-23 30-Nov-23 Column Formwork Installation

JAH-Z2-ST-S5-CL.110 Column Concrete Casting 1 02-Dec-23 02-Dec-23 Column Concrete Casting

JAH-Z2-ST-S5-CL.115 Form Work Removal and Curing 7 03-Dec-23 10-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 14-Nov-23 26-Dec-23 26-Dec-23, TUNNEL WALLS


JAH-Z2-ST-S5-TW.100 Tunnel Walls Rebar Installation 8 14-Nov-23 22-Nov-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S5-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 14-Nov-23 22-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S5-TW.105 Tunnel Formwork Installation 7 23-Nov-23 30-Nov-23 Tunnel Formwork Installation

JAH-Z2-ST-S5-TW.110 Tunnel Walls Concrete Casting 1 02-Dec-23 02-Dec-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S5-TW.112 Curing work 7 03-Dec-23 10-Dec-23 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
249 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S5-TW.120 Tunnel Walls Formwork Removel 2 11-Dec-23 12-Dec-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S5-TW.125 Tunnel Wall Waterproofing 12 13-Dec-23 26-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 13-Dec-23 16-Jan-24 16-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S5-MS.090 Middle Slab Scaffold and Formwork Installation 5 13-Dec-23 18-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S5-MS.100 Middle Slab Rebar Installation 8 19-Dec-23 27-Dec-23 Middle Slab Rebar Installation

JAH-Z2-ST-S5-MS.105 Middle Slab Vertical Formwork Installation 7 28-Dec-23 04-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S5-MS.110 Middle Slab Concrete Casting 1 06-Jan-24 06-Jan-24 Middle Slab Concrete Casting

JAH-Z2-ST-S5-MS.115 Curing work 7 07-Jan-24 14-Jan-24 Curing work

JAH-Z2-ST-S5-MS.120 Middle Slab Formwork Removel 2 15-Jan-24 16-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 17-Jan-24 14-Feb-24 14-Feb-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S5-UCW.100Utility Culvert Walls Rebar Installation 8 17-Jan-24 25-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S5-UCW.105Utility Culvert Walls Formwork Installation 7 27-Jan-24 03-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S5-UCW.110Utility Culvert Walls Concrete Casting 1 04-Feb-24 04-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S5-UCW.112Curing work 7 05-Feb-24 12-Feb-24 Curing work

JAH-Z2-ST-S5-UCW.115Utility Culvert Walls Walls Formwork Removel 2 13-Feb-24 14-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 15-Feb-24 28-Mar-24 28-Mar-24, TOP SLAB


JAH-Z2-ST-S5-TS.090 Top Slab Formwork Installation 7 15-Feb-24 22-Feb-24 Top Slab Formwork Installation

JAH-Z2-ST-S5-TS.100 Top Slab Rebar Installation 8 24-Feb-24 03-Mar-24 Top Slab Rebar Installation

JAH-Z2-ST-S5-TS.110 Top Slab Concrete Casting 1 04-Mar-24 04-Mar-24 Top Slab Concrete Casting

JAH-Z2-ST-S5-TS.112 Curing work 7 05-Mar-24 12-Mar-24 Curing work

JAH-Z2-ST-S5-TS.115 Top Slab Formwork Removel 2 13-Mar-24 14-Mar-24 Top Slab Formwork Removel

JAH-Z2-ST-S5-TS.120 Waterproofing for Top Slab 12 16-Mar-24 28-Mar-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 30-Mar-24 29-Apr-24 29-Apr-24, MASS CONCRETE WORK


JAH-Z2-ST-S5-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 30-Mar-24 06-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S5-MC.105 Plain Concrete Casting 1 07-Apr-24 07-Apr-24 Plain Concrete Casting

JAH-Z2-ST-S5-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 08-Apr-24 08-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S5-MC.112 Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z2-ST-S5-MC.115 Concrete Protective coating 8 21-Apr-24 29-Apr-24 Concrete Protective coating

STA. 0+610.033 ~ 0+630.033 165 25-Oct-23 07-May-24 07-May-24, STA. 0+610.033 ~ 0+630.033
BASE SLAB 27 25-Oct-23 25-Nov-23 25-Nov-23, BASE SLAB
JAH-Z2-ST-S6-BS.100 Lean Concrete for Base Slab 1 25-Oct-23 25-Oct-23 Lean Concrete for Base Slab

JAH-Z2-ST-S6-BS.105 Waterproofing for Lean Concrete 1 26-Oct-23 26-Oct-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S6-BS.110 Base Slab Rebar Installation 8 28-Oct-23 05-Nov-23 Base Slab Rebar Installation

JAH-Z2-ST-S6-BS.115 Base Slab Formwork Installation 7 06-Nov-23 13-Nov-23 Base Slab Formwork Installation

JAH-Z2-ST-S6-BS.120 Base Slab Concrete Casting 1 14-Nov-23 14-Nov-23 Base Slab Concrete Casting

JAH-Z2-ST-S6-BS.122 Curing work 7 15-Nov-23 22-Nov-23 Curing work

JAH-Z2-ST-S6-BS.125 Base Slab Formwork Removel 2 23-Nov-23 25-Nov-23 Base Slab Formwork Removel

COLUMN 23 26-Nov-23 21-Dec-23 21-Dec-23, COLUMN


JAH-Z2-ST-S6-CL.100 Column Rebar Installation 8 26-Nov-23 04-Dec-23 Column Rebar Installation

JAH-Z2-ST-S6-CL.105 Column Formwork Installation 7 05-Dec-23 12-Dec-23 Column Formwork Installation

JAH-Z2-ST-S6-CL.110 Column Concrete Casting 1 13-Dec-23 13-Dec-23 Column Concrete Casting

JAH-Z2-ST-S6-CL.115 Form Work Removal and Curing 7 14-Dec-23 21-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 26-Nov-23 07-Jan-24 07-Jan-24, TUNNEL WALLS


JAH-Z2-ST-S6-TW.100 Tunnel Walls Rebar Installation 8 26-Nov-23 04-Dec-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S6-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 26-Nov-23 04-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
250 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S6-TW.105 Tunnel Formwork Installation 7 05-Dec-23 12-Dec-23 Tunnel Formwork Installation

JAH-Z2-ST-S6-TW.110 Tunnel Walls Concrete Casting 1 13-Dec-23 13-Dec-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S6-TW.112 Curing work 7 14-Dec-23 21-Dec-23 Curing work

JAH-Z2-ST-S6-TW.120 Tunnel Walls Formwork Removel 2 23-Dec-23 24-Dec-23 Tunnel Walls Formwork Removel

JAH-Z2-ST-S6-TW.125 Tunnel Wall Waterproofing 12 25-Dec-23 07-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 25-Dec-23 28-Jan-24 28-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S6-MS.090 Middle Slab Scaffold and Formwork Installation 5 25-Dec-23 30-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S6-MS.100 Middle Slab Rebar Installation 8 31-Dec-23 08-Jan-24 Middle Slab Rebar Installation

JAH-Z2-ST-S6-MS.105 Middle Slab Vertical Formwork Installation 7 09-Jan-24 16-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S6-MS.110 Middle Slab Concrete Casting 1 17-Jan-24 17-Jan-24 Middle Slab Concrete Casting

JAH-Z2-ST-S6-MS.115 Curing work 7 18-Jan-24 25-Jan-24 Curing work

JAH-Z2-ST-S6-MS.120 Middle Slab Formwork Removel 2 27-Jan-24 28-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 29-Jan-24 26-Feb-24 26-Feb-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S6-UCW.100Utility Culvert Walls Rebar Installation 8 29-Jan-24 06-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S6-UCW.105Utility Culvert Walls Formwork Installation 7 07-Feb-24 14-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S6-UCW.110Utility Culvert Walls Concrete Casting 1 15-Feb-24 15-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S6-UCW.112Curing work 7 17-Feb-24 24-Feb-24 Curing work

JAH-Z2-ST-S6-UCW.115Utility Culvert Walls Walls Formwork Removel 2 25-Feb-24 26-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 34 27-Feb-24 06-Apr-24 06-Apr-24, TOP SLAB


JAH-Z2-ST-S6-TS.090 Top Slab Formwork Installation 7 27-Feb-24 05-Mar-24 Top Slab Formwork Installation

JAH-Z2-ST-S6-TS.100 Top Slab Rebar Installation 8 06-Mar-24 14-Mar-24 Top Slab Rebar Installation

JAH-Z2-ST-S6-TS.110 Top Slab Concrete Casting 1 16-Mar-24 16-Mar-24 Top Slab Concrete Casting

JAH-Z2-ST-S6-TS.112 Curing work 4 17-Mar-24 20-Mar-24 Curing work

JAH-Z2-ST-S6-TS.115 Top Slab Formwork Removel 2 21-Mar-24 23-Mar-24 Top Slab Formwork Removel

JAH-Z2-ST-S6-TS.120 Waterproofing for Top Slab 12 24-Mar-24 06-Apr-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 07-Apr-24 07-May-24 07-May-24, MASS CONCRETE WORK


JAH-Z2-ST-S6-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 07-Apr-24 17-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S6-MC.105 Plain Concrete Casting 1 18-Apr-24 18-Apr-24 Plain Concrete Casting

JAH-Z2-ST-S6-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 20-Apr-24 20-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S6-MC.112 Curing work 7 21-Apr-24 28-Apr-24 Curing work

JAH-Z2-ST-S6-MC.115 Concrete Protective coating 8 29-Apr-24 07-May-24 Concrete Protective coating

STA.0+630.033 ~ 0+650.033 168 06-Nov-23 22-May-24 22-May-24, STA.0+630.033 ~ 0+650.033


BASE SLAB 27 06-Nov-23 06-Dec-23 06-Dec-23, BASE SLAB
JAH-Z2-ST-S7-BS.100 Lean Concrete for Base Slab 1 06-Nov-23 06-Nov-23 Lean Concrete for Base Slab

JAH-Z2-ST-S7-BS.105 Waterproofing for Lean Concrete 1 07-Nov-23 07-Nov-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S7-BS.110 Base Slab Rebar Installation 8 08-Nov-23 16-Nov-23 Base Slab Rebar Installation

JAH-Z2-ST-S7-BS.115 Base Slab Formwork Installation 7 18-Nov-23 25-Nov-23 Base Slab Formwork Installation

JAH-Z2-ST-S7-BS.120 Base Slab Concrete Casting 1 26-Nov-23 26-Nov-23 Base Slab Concrete Casting

JAH-Z2-ST-S7-BS.122 Curing work 7 27-Nov-23 04-Dec-23 Curing work

JAH-Z2-ST-S7-BS.125 Base Slab Formwork Removel 2 05-Dec-23 06-Dec-23 Base Slab Formwork Removel

COLUMN 23 07-Dec-23 02-Jan-24 02-Jan-24, COLUMN


JAH-Z2-ST-S7-CL.100 Column Rebar Installation 8 07-Dec-23 16-Dec-23 Column Rebar Installation

JAH-Z2-ST-S7-CL.105 Column Formwork Installation 7 17-Dec-23 24-Dec-23 Column Formwork Installation

JAH-Z2-ST-S7-CL.110 Column Concrete Casting 1 25-Dec-23 25-Dec-23 Column Concrete Casting

JAH-Z2-ST-S7-CL.115 Form Work Removal and Curing 7 26-Dec-23 02-Jan-24 Form Work Removal and Curing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
251 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TUNNEL WALLS 37 07-Dec-23 18-Jan-24 18-Jan-24, TUNNEL WALLS
JAH-Z2-ST-S7-TW.100 Tunnel Walls Rebar Installation 8 07-Dec-23 16-Dec-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S7-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 07-Dec-23 16-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S7-TW.105 Tunnel Formwork Installation 7 17-Dec-23 24-Dec-23 Tunnel Formwork Installation

JAH-Z2-ST-S7-TW.110 Tunnel Walls Concrete Casting 1 25-Dec-23 25-Dec-23 Tunnel Walls Concrete Casting

JAH-Z2-ST-S7-TW.112 Curing work 7 26-Dec-23 02-Jan-24 Curing work

JAH-Z2-ST-S7-TW.120 Tunnel Walls Formwork Removel 2 03-Jan-24 04-Jan-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S7-TW.125 Tunnel Wall Waterproofing 12 06-Jan-24 18-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 06-Jan-24 08-Feb-24 08-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S7-MS.090 Middle Slab Scaffold and Formwork Installation 5 06-Jan-24 10-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S7-MS.100 Middle Slab Rebar Installation 8 11-Jan-24 20-Jan-24 Middle Slab Rebar Installation

JAH-Z2-ST-S7-MS.105 Middle Slab Vertical Formwork Installation 7 21-Jan-24 28-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S7-MS.110 Middle Slab Concrete Casting 1 29-Jan-24 29-Jan-24 Middle Slab Concrete Casting

JAH-Z2-ST-S7-MS.115 Curing work 7 30-Jan-24 06-Feb-24 Curing work

JAH-Z2-ST-S7-MS.120 Middle Slab Formwork Removel 2 07-Feb-24 08-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 10-Feb-24 09-Mar-24 09-Mar-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S7-UCW.100Utility Culvert Walls Rebar Installation 8 10-Feb-24 18-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S7-UCW.105Utility Culvert Walls Formwork Installation 7 19-Feb-24 26-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S7-UCW.110Utility Culvert Walls Concrete Casting 1 27-Feb-24 27-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S7-UCW.112Curing work 7 28-Feb-24 06-Mar-24 Curing work

JAH-Z2-ST-S7-UCW.115Utility Culvert Walls Walls Formwork Removel 2 07-Mar-24 09-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 10-Mar-24 24-Apr-24 24-Apr-24, TOP SLAB


JAH-Z2-ST-S7-TS.090 Top Slab Formwork Installation 7 10-Mar-24 17-Mar-24 Top Slab Formwork Installation

JAH-Z2-ST-S7-TS.100 Top Slab Rebar Installation 8 18-Mar-24 26-Mar-24 Top Slab Rebar Installation

JAH-Z2-ST-S7-TS.110 Top Slab Concrete Casting 1 27-Mar-24 27-Mar-24 Top Slab Concrete Casting

JAH-Z2-ST-S7-TS.112 Curing work 7 28-Mar-24 04-Apr-24 Curing work

JAH-Z2-ST-S7-TS.115 Top Slab Formwork Removel 2 06-Apr-24 07-Apr-24 Top Slab Formwork Removel

JAH-Z2-ST-S7-TS.120 Waterproofing for Top Slab 12 08-Apr-24 24-Apr-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 25-Apr-24 22-May-24 22-May-24, MASS CONCRETE WORK


JAH-Z2-ST-S7-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 25-Apr-24 02-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S7-MC.105 Plain Concrete Casting 1 04-May-24 04-May-24 Plain Concrete Casting

JAH-Z2-ST-S7-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 05-May-24 05-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S7-MC.112 Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z2-ST-S7-MC.115 Concrete Protective coating 8 14-May-24 22-May-24 Concrete Protective coating

STA. 0+650.033 ~ 0+670.033 168 18-Nov-23 03-Jun-24 03-Jun-24, STA. 0+650.033 ~ 0+670.033
BASE SLAB 27 18-Nov-23 18-Dec-23 18-Dec-23, BASE SLAB
JAH-Z2-ST-S8-BS.100 Lean Concrete for Base Slab 1 18-Nov-23 18-Nov-23 Lean Concrete for Base Slab

JAH-Z2-ST-S8-BS.105 Waterproofing for Lean Concrete 1 19-Nov-23 19-Nov-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S8-BS.110 Base Slab Rebar Installation 8 20-Nov-23 28-Nov-23 Base Slab Rebar Installation

JAH-Z2-ST-S8-BS.115 Base Slab Formwork Installation 7 29-Nov-23 06-Dec-23 Base Slab Formwork Installation

JAH-Z2-ST-S8-BS.120 Base Slab Concrete Casting 1 07-Dec-23 07-Dec-23 Base Slab Concrete Casting

JAH-Z2-ST-S8-BS.122 Curing work 7 09-Dec-23 16-Dec-23 Curing work

JAH-Z2-ST-S8-BS.125 Base Slab Formwork Removel 2 17-Dec-23 18-Dec-23 Base Slab Formwork Removel

COLUMN 23 19-Dec-23 14-Jan-24 14-Jan-24, COLUMN


JAH-Z2-ST-S8-CL.100 Column Rebar Installation 8 19-Dec-23 27-Dec-23 Column Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
252 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S8-CL.105 Column Formwork Installation 7 28-Dec-23 04-Jan-24 Column Formwork Installation

JAH-Z2-ST-S8-CL.110 Column Concrete Casting 1 06-Jan-24 06-Jan-24 Column Concrete Casting

JAH-Z2-ST-S8-CL.115 Form Work Removal and Curing 7 07-Jan-24 14-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 19-Dec-23 30-Jan-24 30-Jan-24, TUNNEL WALLS


JAH-Z2-ST-S8-TW.100 Tunnel Walls Rebar Installation 8 19-Dec-23 27-Dec-23 Tunnel Walls Rebar Installation

JAH-Z2-ST-S8-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 19-Dec-23 27-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S8-TW.105 Tunnel Formwork Installation 7 28-Dec-23 04-Jan-24 Tunnel Formwork Installation

JAH-Z2-ST-S8-TW.110 Tunnel Walls Concrete Casting 1 06-Jan-24 06-Jan-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S8-TW.112 Curing work 7 07-Jan-24 14-Jan-24 Curing work

JAH-Z2-ST-S8-TW.120 Tunnel Walls Formwork Removel 2 15-Jan-24 16-Jan-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S8-TW.125 Tunnel Wall Waterproofing 12 17-Jan-24 30-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 17-Jan-24 20-Feb-24 20-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S8-MS.090 Middle Slab Scaffold and Formwork Installation 5 17-Jan-24 22-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S8-MS.100 Middle Slab Rebar Installation 8 23-Jan-24 31-Jan-24 Middle Slab Rebar Installation

JAH-Z2-ST-S8-MS.105 Middle Slab Vertical Formwork Installation 7 01-Feb-24 08-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S8-MS.110 Middle Slab Concrete Casting 1 10-Feb-24 10-Feb-24 Middle Slab Concrete Casting

JAH-Z2-ST-S8-MS.115 Curing work 7 11-Feb-24 18-Feb-24 Curing work

JAH-Z2-ST-S8-MS.120 Middle Slab Formwork Removel 2 19-Feb-24 20-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 21-Feb-24 20-Mar-24 20-Mar-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S8-UCW.100Utility Culvert Walls Rebar Installation 8 21-Feb-24 29-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S8-UCW.105Utility Culvert Walls Formwork Installation 7 02-Mar-24 09-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S8-UCW.110Utility Culvert Walls Concrete Casting 1 10-Mar-24 10-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S8-UCW.112Curing work 7 11-Mar-24 18-Mar-24 Curing work

JAH-Z2-ST-S8-UCW.115Utility Culvert Walls Walls Formwork Removel 2 19-Mar-24 20-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 21-Mar-24 06-May-24 06-May-24, TOP SLAB


JAH-Z2-ST-S8-TS.090 Top Slab Formwork Installation 7 21-Mar-24 28-Mar-24 Top Slab Formwork Installation

JAH-Z2-ST-S8-TS.100 Top Slab Rebar Installation 8 30-Mar-24 07-Apr-24 Top Slab Rebar Installation

JAH-Z2-ST-S8-TS.110 Top Slab Concrete Casting 1 08-Apr-24 08-Apr-24 Top Slab Concrete Casting

JAH-Z2-ST-S8-TS.112 Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z2-ST-S8-TS.115 Top Slab Formwork Removel 2 21-Apr-24 22-Apr-24 Top Slab Formwork Removel

JAH-Z2-ST-S8-TS.120 Waterproofing for Top Slab 12 23-Apr-24 06-May-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 07-May-24 03-Jun-24 03-Jun-24, MASS CONCRETE WORK


JAH-Z2-ST-S8-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 07-May-24 14-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S8-MC.105 Plain Concrete Casting 1 15-May-24 15-May-24 Plain Concrete Casting

JAH-Z2-ST-S8-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 16-May-24 16-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S8-MC.112 Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z2-ST-S8-MC.115 Concrete Protective coating 8 26-May-24 03-Jun-24 Concrete Protective coating

STA. 0+670.033~ 0+690.033 168 29-Nov-23 19-Jun-24 19-Jun-24, STA. 0+670.033~ 0+690.033
BASE SLAB 27 29-Nov-23 30-Dec-23 30-Dec-23, BASE SLAB
JAH-Z2-ST-S9-BS.100 Lean Concrete for Base Slab 1 29-Nov-23 29-Nov-23 Lean Concrete for Base Slab

JAH-Z2-ST-S9-BS.105 Waterproofing for Lean Concrete 1 30-Nov-23 30-Nov-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S9-BS.110 Base Slab Rebar Installation 8 02-Dec-23 10-Dec-23 Base Slab Rebar Installation

JAH-Z2-ST-S9-BS.115 Base Slab Formwork Installation 7 11-Dec-23 18-Dec-23 Base Slab Formwork Installation

JAH-Z2-ST-S9-BS.120 Base Slab Concrete Casting 1 19-Dec-23 19-Dec-23 Base Slab Concrete Casting

JAH-Z2-ST-S9-BS.122 Curing work 7 20-Dec-23 27-Dec-23 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
253 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S9-BS.125 Base Slab Formwork Removel 2 28-Dec-23 30-Dec-23 Base Slab Formwork Removel

COLUMN 23 31-Dec-23 25-Jan-24 25-Jan-24, COLUMN


JAH-Z2-ST-S9-CL.100 Column Rebar Installation 8 31-Dec-23 08-Jan-24 Column Rebar Installation

JAH-Z2-ST-S9-CL.105 Column Formwork Installation 7 09-Jan-24 16-Jan-24 Column Formwork Installation

JAH-Z2-ST-S9-CL.110 Column Concrete Casting 1 17-Jan-24 17-Jan-24 Column Concrete Casting

JAH-Z2-ST-S9-CL.115 Form Work Removal and Curing 7 18-Jan-24 25-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 31-Dec-23 11-Feb-24 11-Feb-24, TUNNEL WALLS


JAH-Z2-ST-S9-TW.100 Tunnel Walls Rebar Installation 8 31-Dec-23 08-Jan-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S9-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 31-Dec-23 08-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S9-TW.105 Tunnel Formwork Installation 7 09-Jan-24 16-Jan-24 Tunnel Formwork Installation

JAH-Z2-ST-S9-TW.110 Tunnel Walls Concrete Casting 1 17-Jan-24 17-Jan-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S9-TW.115 Curing work 7 18-Jan-24 25-Jan-24 Curing work

JAH-Z2-ST-S9-TW.120 Tunnel Walls Formwork Removel 2 27-Jan-24 28-Jan-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S9-TW.125 Tunnel Wall Waterproofing 12 29-Jan-24 11-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 29-Jan-24 03-Mar-24 03-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S9-MS.090 Middle Slab Scaffold and Formwork Installation 5 29-Jan-24 03-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S9-MS.100 Middle Slab Rebar Installation 8 04-Feb-24 12-Feb-24 Middle Slab Rebar Installation

JAH-Z2-ST-S9-MS.105 Middle Slab Vertical Formwork Installation 7 13-Feb-24 20-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S9-MS.110 Middle Slab Concrete Casting 1 21-Feb-24 21-Feb-24 Middle Slab Concrete Casting

JAH-Z2-ST-S9-MS.115 Curing work 7 22-Feb-24 29-Feb-24 Curing work

JAH-Z2-ST-S9-MS.120 Middle Slab Formwork Removel 2 02-Mar-24 03-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 04-Mar-24 01-Apr-24 01-Apr-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S9-UCW.100Utility Culvert Walls Rebar Installation 8 04-Mar-24 12-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S9-UCW.105Utility Culvert Walls Formwork Installation 7 13-Mar-24 20-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S9-UCW.110Utility Culvert Walls Concrete Casting 1 21-Mar-24 21-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S9-UCW.112Curing work 7 23-Mar-24 30-Mar-24 Curing work

JAH-Z2-ST-S9-UCW.115Utility Culvert Walls Walls Formwork Removel 2 31-Mar-24 01-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 02-Apr-24 18-May-24 18-May-24, TOP SLAB


JAH-Z2-ST-S9-TS.090 Top Slab Formwork Installation 7 02-Apr-24 13-Apr-24 Top Slab Formwork Installation

JAH-Z2-ST-S9-TS.100 Top Slab Rebar Installation 8 14-Apr-24 22-Apr-24 Top Slab Rebar Installation

JAH-Z2-ST-S9-TS.110 Top Slab Concrete Casting 1 23-Apr-24 23-Apr-24 Top Slab Concrete Casting

JAH-Z2-ST-S9-TS.112 Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z2-ST-S9-TS.115 Top Slab Formwork Removel 2 02-May-24 04-May-24 Top Slab Formwork Removel

JAH-Z2-ST-S9-TS.120 Waterproofing for Top Slab 12 05-May-24 18-May-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 19-May-24 19-Jun-24 19-Jun-24, MASS CONCRETE WORK


JAH-Z2-ST-S9-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 19-May-24 26-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S9-MC.105 Plain Concrete Casting 1 27-May-24 27-May-24 Plain Concrete Casting

JAH-Z2-ST-S9-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 28-May-24 28-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S9-MC.112 Curing work 7 29-May-24 05-Jun-24 Curing work

JAH-Z2-ST-S9-MC.115 Concrete Protective coating 8 06-Jun-24 19-Jun-24 Concrete Protective coating

STA. 0+690.033~ 0+710.033 166 11-Dec-23 29-Jun-24 29-Jun-24, STA. 0+690.033~ 0+710.033
BASE SLAB 27 11-Dec-23 10-Jan-24 10-Jan-24, BASE SLAB
JAH-Z2-ST-S10-BS.100Lean Concrete for Base Slab 1 11-Dec-23 11-Dec-23 Lean Concrete for Base Slab

JAH-Z2-ST-S10-BS.105Waterproofing for Lean Concrete 1 12-Dec-23 12-Dec-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S10-BS.110 Base Slab Rebar Installation 8 13-Dec-23 21-Dec-23 Base Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
254 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S10-BS.115 Base Slab Formwork Installation 7 23-Dec-23 30-Dec-23 Base Slab Formwork Installation

JAH-Z2-ST-S10-BS.120Base Slab Concrete Casting 1 31-Dec-23 31-Dec-23 Base Slab Concrete Casting

JAH-Z2-ST-S10-BS.122Curing work 7 01-Jan-24 08-Jan-24 Curing work

JAH-Z2-ST-S10-BS.125Base Slab Formwork Removel 2 09-Jan-24 10-Jan-24 Base Slab Formwork Removel

COLUMN 23 11-Jan-24 06-Feb-24 06-Feb-24, COLUMN


JAH-Z2-ST-S10-CL.100Column Rebar Installation 8 11-Jan-24 20-Jan-24 Column Rebar Installation

JAH-Z2-ST-S10-CL.105Column Formwork Installation 7 21-Jan-24 28-Jan-24 Column Formwork Installation

JAH-Z2-ST-S10-CL.110 Column Concrete Casting 1 29-Jan-24 29-Jan-24 Column Concrete Casting

JAH-Z2-ST-S10-CL.115 Form Work Removal and Curing 7 30-Jan-24 06-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 34 11-Jan-24 19-Feb-24 19-Feb-24, TUNNEL WALLS


JAH-Z2-ST-S10-TW.100Tunnel Walls Rebar Installation 8 11-Jan-24 20-Jan-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S10-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-Jan-24 20-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S10-TW.105Tunnel Formwork Installation 7 21-Jan-24 28-Jan-24 Tunnel Formwork Installation

JAH-Z2-ST-S10-TW.110Tunnel Walls Concrete Casting 1 29-Jan-24 29-Jan-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S10-TW.112Curing work 4 30-Jan-24 03-Feb-24 Curing work

JAH-Z2-ST-S10-TW.120Tunnel Walls Formwork Removel 2 04-Feb-24 05-Feb-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S10-TW.125Tunnel Wall Waterproofing 12 06-Feb-24 19-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 07-Feb-24 12-Mar-24 12-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S10-MS.090Middle Slab Scaffold and Formwork Installation 5 07-Feb-24 12-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S10-MS.100Middle Slab Rebar Installation 8 13-Feb-24 21-Feb-24 Middle Slab Rebar Installation

JAH-Z2-ST-S10-MS.105Middle Slab Vertical Formwork Installation 7 22-Feb-24 29-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S10-MS.110Middle Slab Concrete Casting 1 02-Mar-24 02-Mar-24 Middle Slab Concrete Casting

JAH-Z2-ST-S10-MS.115Curing work 7 03-Mar-24 10-Mar-24 Curing work

JAH-Z2-ST-S10-MS.120Middle Slab Formwork Removel 2 11-Mar-24 12-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 13-Mar-24 14-Apr-24 14-Apr-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S10-UC.100Utility Culvert Walls Rebar Installation 8 13-Mar-24 21-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S10-UC.105Utility Culvert Walls Formwork Installation 7 23-Mar-24 30-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S10-UC.110Utility Culvert Walls Concrete Casting 1 31-Mar-24 31-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S10-UC.112Curing work 7 01-Apr-24 08-Apr-24 Curing work

JAH-Z2-ST-S10-UC.115Utility Culvert Walls Walls Formwork Removel 2 13-Apr-24 14-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 15-Apr-24 27-May-24 27-May-24, TOP SLAB


JAH-Z2-ST-S10-TS.090 Top Slab Formwork Installation 7 15-Apr-24 22-Apr-24 Top Slab Formwork Installation

JAH-Z2-ST-S10-TS.100 Top Slab Rebar Installation 8 23-Apr-24 01-May-24 Top Slab Rebar Installation

JAH-Z2-ST-S10-TS.110 Top Slab Concrete Casting 1 02-May-24 02-May-24 Top Slab Concrete Casting

JAH-Z2-ST-S10-TS.112 Curing work 7 04-May-24 11-May-24 Curing work

JAH-Z2-ST-S10-TS.115 Top Slab Formwork Removel 2 12-May-24 13-May-24 Top Slab Formwork Removel

JAH-Z2-ST-S10-TS.120 Waterproofing for Top Slab 12 14-May-24 27-May-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 28-May-24 29-Jun-24 29-Jun-24, MASS CONCRETE WORK


JAH-Z2-ST-S10-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 28-May-24 04-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S10-MC.105Plain Concrete Casting 1 05-Jun-24 05-Jun-24 Plain Concrete Casting

JAH-Z2-ST-S10-MC.110Mass Concrete Casting for Base Slab Top Layer 1 06-Jun-24 06-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S10-MC.115Concrete Protective coating 8 08-Jun-24 20-Jun-24 Concrete Protective coating

JAH-Z2-ST-S10-MC.120Curing work 7 22-Jun-24 29-Jun-24 Curing work

STA. 0+710.033~ 0+730.033 168 23-Dec-23 13-Jul-24 13-Jul-24, STA. 0+710.033~ 0+730.033
BASE SLAB 27 23-Dec-23 22-Jan-24 22-Jan-24, BASE SLAB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
255 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S11-BS.100 Lean Concrete for Base Slab 1 23-Dec-23 23-Dec-23 Lean Concrete for Base Slab

JAH-Z2-ST-S11-BS.105 Waterproofing for Lean Concrete 1 24-Dec-23 24-Dec-23 Waterproofing for Lean Concrete

JAH-Z2-ST-S11-BS.110 Base Slab Rebar Installation 8 25-Dec-23 02-Jan-24 Base Slab Rebar Installation

JAH-Z2-ST-S11-BS.115 Base Slab Formwork Installation 7 03-Jan-24 10-Jan-24 Base Slab Formwork Installation

JAH-Z2-ST-S11-BS.120 Base Slab Concrete Casting 1 11-Jan-24 11-Jan-24 Base Slab Concrete Casting

JAH-Z2-ST-S11-BS.122 Curing work 7 13-Jan-24 20-Jan-24 Curing work

JAH-Z2-ST-S11-BS.125 Base Slab Formwork Removel 2 21-Jan-24 22-Jan-24 Base Slab Formwork Removel

COLUMN 23 23-Jan-24 18-Feb-24 18-Feb-24, COLUMN


JAH-Z2-ST-S11-CL.100 Column Rebar Installation 8 23-Jan-24 31-Jan-24 Column Rebar Installation

JAH-Z2-ST-S11-CL.105 Column Formwork Installation 7 01-Feb-24 08-Feb-24 Column Formwork Installation

JAH-Z2-ST-S11-CL.110 Column Concrete Casting 1 10-Feb-24 10-Feb-24 Column Concrete Casting

JAH-Z2-ST-S11-CL.115 Form Work Removal and Curing 7 11-Feb-24 18-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 23-Jan-24 05-Mar-24 05-Mar-24, TUNNEL WALLS


JAH-Z2-ST-S11-TW.100Tunnel Walls Rebar Installation 8 23-Jan-24 31-Jan-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S11-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 23-Jan-24 31-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S11-TW.105Tunnel Formwork Installation 7 01-Feb-24 08-Feb-24 Tunnel Formwork Installation

JAH-Z2-ST-S11-TW.110Tunnel Walls Concrete Casting 1 10-Feb-24 10-Feb-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S11-TW.115Curing work 7 11-Feb-24 18-Feb-24 Curing work

JAH-Z2-ST-S11-TW.120Tunnel Walls Formwork Removel 2 19-Feb-24 20-Feb-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S11-TW.125Tunnel Wall Waterproofing 12 21-Feb-24 05-Mar-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 21-Feb-24 26-Mar-24 26-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S11-MS.090Middle Slab Scaffold and Formwork Installation 5 21-Feb-24 26-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S11-MS.100Middle Slab Rebar Installation 8 27-Feb-24 06-Mar-24 Middle Slab Rebar Installation

JAH-Z2-ST-S11-MS.105Middle Slab Vertical Formwork Installation 7 07-Mar-24 14-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S11-MS.110Middle Slab Concrete Casting 1 16-Mar-24 16-Mar-24 Middle Slab Concrete Casting

JAH-Z2-ST-S11-MS.115Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z2-ST-S11-MS.120Middle Slab Formwork Removel 2 25-Mar-24 26-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 27-Mar-24 28-Apr-24 28-Apr-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S11-UC.100Utility Culvert Walls Rebar Installation 8 27-Mar-24 04-Apr-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S11-UC.105Utility Culvert Walls Formwork Installation 7 06-Apr-24 16-Apr-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S11-UC.110Utility Culvert Walls Concrete Casting 1 17-Apr-24 17-Apr-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S11-UC.112Curing work 7 18-Apr-24 25-Apr-24 Curing work

JAH-Z2-ST-S11-UC.115Utility Culvert Walls Walls Formwork Removel 2 27-Apr-24 28-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 29-Apr-24 10-Jun-24 10-Jun-24, TOP SLAB


JAH-Z2-ST-S11-TS.090 Top Slab Formwork Installation 7 29-Apr-24 06-May-24 Top Slab Formwork Installation

JAH-Z2-ST-S11-TS.100 Top Slab Rebar Installation 8 07-May-24 15-May-24 Top Slab Rebar Installation

JAH-Z2-ST-S11-TS.110 Top Slab Concrete Casting 1 16-May-24 16-May-24 Top Slab Concrete Casting

JAH-Z2-ST-S11-TS.112 Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z2-ST-S11-TS.115 Top Slab Formwork Removel 2 26-May-24 27-May-24 Top Slab Formwork Removel

JAH-Z2-ST-S11-TS.120 Waterproofing for Top Slab 12 28-May-24 10-Jun-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 11-Jun-24 13-Jul-24 13-Jul-24, MASS CONCRETE WORK


JAH-Z2-ST-S11-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 11-Jun-24 23-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S11-MC.105Plain Concrete Casting 1 24-Jun-24 24-Jun-24 Plain Concrete Casting

JAH-Z2-ST-S11-MC.110Mass Concrete Casting for Base Slab Top Layer 1 25-Jun-24 25-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S11-MC.112Curing work 7 26-Jun-24 03-Jul-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
256 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S11-MC.115Concrete Protective coating 8 04-Jul-24 13-Jul-24 Concrete Protective coating

STA. 0+730.033 ~ 0+750.033 168 03-Jan-24 24-Jul-24 24-Jul-24, STA. 0+730.033 ~ 0+750.033
BASE SLAB 27 03-Jan-24 03-Feb-24 03-Feb-24, BASE SLAB
JAH-Z2-ST-S12-BS.100Lean Concrete for Base Slab 1 03-Jan-24 03-Jan-24 Lean Concrete for Base Slab

JAH-Z2-ST-S12-BS.105Waterproofing for Lean Concrete 1 04-Jan-24 04-Jan-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S12-BS.110 Base Slab Rebar Installation 8 06-Jan-24 14-Jan-24 Base Slab Rebar Installation

JAH-Z2-ST-S12-BS.115 Base Slab Formwork Installation 7 15-Jan-24 22-Jan-24 Base Slab Formwork Installation

JAH-Z2-ST-S12-BS.120Base Slab Concrete Casting 1 23-Jan-24 23-Jan-24 Base Slab Concrete Casting

JAH-Z2-ST-S12-BS.122Curing work 7 24-Jan-24 31-Jan-24 Curing work

JAH-Z2-ST-S12-BS.125Base Slab Formwork Removel 2 01-Feb-24 03-Feb-24 Base Slab Formwork Removel

COLUMN 23 04-Feb-24 29-Feb-24 29-Feb-24, COLUMN


JAH-Z2-ST-S12-CL.100Column Rebar Installation 8 04-Feb-24 12-Feb-24 Column Rebar Installation

JAH-Z2-ST-S12-CL.105Column Formwork Installation 7 13-Feb-24 20-Feb-24 Column Formwork Installation

JAH-Z2-ST-S12-CL.110 Column Concrete Casting 1 21-Feb-24 21-Feb-24 Column Concrete Casting

JAH-Z2-ST-S12-CL.115 Form Work Removal and Curing 7 22-Feb-24 29-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 04-Feb-24 17-Mar-24 17-Mar-24, TUNNEL WALLS


JAH-Z2-ST-S12-TW.100Tunnel Walls Rebar Installation 8 04-Feb-24 12-Feb-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S12-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 04-Feb-24 12-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S12-TW.105Tunnel Formwork Installation 7 13-Feb-24 20-Feb-24 Tunnel Formwork Installation

JAH-Z2-ST-S12-TW.110Tunnel Walls Concrete Casting 1 21-Feb-24 21-Feb-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S12-TW.115Curing work 7 22-Feb-24 29-Feb-24 Curing work

JAH-Z2-ST-S12-TW.120Tunnel Walls Formwork Removel 2 02-Mar-24 03-Mar-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S12-TW.125Tunnel Wall Waterproofing 12 04-Mar-24 17-Mar-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 04-Mar-24 07-Apr-24 07-Apr-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S12-MS.090Middle Slab Scaffold and Formwork Installation 5 04-Mar-24 09-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S12-MS.100Middle Slab Rebar Installation 8 10-Mar-24 18-Mar-24 Middle Slab Rebar Installation

JAH-Z2-ST-S12-MS.105Middle Slab Vertical Formwork Installation 7 19-Mar-24 26-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S12-MS.110Middle Slab Concrete Casting 1 27-Mar-24 27-Mar-24 Middle Slab Concrete Casting

JAH-Z2-ST-S12-MS.115Curing work 7 28-Mar-24 04-Apr-24 Curing work

JAH-Z2-ST-S12-MS.120Middle Slab Formwork Removel 2 06-Apr-24 07-Apr-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 08-Apr-24 09-May-24 09-May-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S12-UC.100Utility Culvert Walls Rebar Installation 8 08-Apr-24 20-Apr-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S12-UC.105Utility Culvert Walls Formwork Installation 7 21-Apr-24 28-Apr-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S12-UC.110Utility Culvert Walls Concrete Casting 1 29-Apr-24 29-Apr-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S12-UC.112Curing work 7 30-Apr-24 07-May-24 Curing work

JAH-Z2-ST-S12-UC.115Utility Culvert Walls Walls Formwork Removel 2 08-May-24 09-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 11-May-24 26-Jun-24 26-Jun-24, TOP SLAB


JAH-Z2-ST-S12-TS.090 Top Slab Formwork Installation 7 11-May-24 18-May-24 Top Slab Formwork Installation

JAH-Z2-ST-S12-TS.100 Top Slab Rebar Installation 8 19-May-24 27-May-24 Top Slab Rebar Installation

JAH-Z2-ST-S12-TS.110 Top Slab Concrete Casting 1 28-May-24 28-May-24 Top Slab Concrete Casting

JAH-Z2-ST-S12-TS.112 Curing work 7 29-May-24 05-Jun-24 Curing work

JAH-Z2-ST-S12-TS.115 Top Slab Formwork Removel 2 06-Jun-24 08-Jun-24 Top Slab Formwork Removel

JAH-Z2-ST-S12-TS.120 Waterproofing for Top Slab 12 09-Jun-24 26-Jun-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 27-Jun-24 24-Jul-24 24-Jul-24, MASS CONCRETE WORK


JAH-Z2-ST-S12-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 27-Jun-24 04-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
257 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S12-MC.105Plain Concrete Casting 1 06-Jul-24 06-Jul-24 Plain Concrete Casting

JAH-Z2-ST-S12-MC.110Mass Concrete Casting for Base Slab Top Layer 1 07-Jul-24 07-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S12-MC.112Curing work 7 08-Jul-24 15-Jul-24 Curing work

JAH-Z2-ST-S12-MC.115Concrete Protective coating 8 16-Jul-24 24-Jul-24 Concrete Protective coating

STA. 0+750.033 ~ 0+770.033 168 15-Jan-24 05-Aug-24 05-Aug-24, STA. 0+750.033 ~ 0+770.033
BASE SLAB 27 15-Jan-24 14-Feb-24 14-Feb-24, BASE SLAB
JAH-Z2-ST-S13-BS.100Lean Concrete for Base Slab 1 15-Jan-24 15-Jan-24 Lean Concrete for Base Slab

JAH-Z2-ST-S13-BS.105Waterproofing for Lean Concrete 1 16-Jan-24 16-Jan-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S13-BS.110 Base Slab Rebar Installation 8 17-Jan-24 25-Jan-24 Base Slab Rebar Installation

JAH-Z2-ST-S13-BS.115 Base Slab Formwork Installation 7 27-Jan-24 03-Feb-24 Base Slab Formwork Installation

JAH-Z2-ST-S13-BS.120Base Slab Concrete Casting 1 04-Feb-24 04-Feb-24 Base Slab Concrete Casting

JAH-Z2-ST-S13-BS.122Curing work 7 05-Feb-24 12-Feb-24 Curing work

JAH-Z2-ST-S13-BS.125Base Slab Formwork Removel 2 13-Feb-24 14-Feb-24 Base Slab Formwork Removel

COLUMN 23 15-Feb-24 12-Mar-24 12-Mar-24, COLUMN


JAH-Z2-ST-S13-CL.100Column Rebar Installation 8 15-Feb-24 24-Feb-24 Column Rebar Installation

JAH-Z2-ST-S13-CL.105Column Formwork Installation 7 25-Feb-24 03-Mar-24 Column Formwork Installation

JAH-Z2-ST-S13-CL.110 Column Concrete Casting 1 04-Mar-24 04-Mar-24 Column Concrete Casting

JAH-Z2-ST-S13-CL.115 Form Work Removal and Curing 7 05-Mar-24 12-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 15-Feb-24 28-Mar-24 28-Mar-24, TUNNEL WALLS


JAH-Z2-ST-S13-TW.100Tunnel Walls Rebar Installation 8 15-Feb-24 24-Feb-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S13-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 15-Feb-24 24-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S13-TW.105Tunnel Formwork Installation 7 25-Feb-24 03-Mar-24 Tunnel Formwork Installation

JAH-Z2-ST-S13-TW.110Tunnel Walls Concrete Casting 1 04-Mar-24 04-Mar-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S13-TW.112Curing work 7 05-Mar-24 12-Mar-24 Curing work

JAH-Z2-ST-S13-TW.120Tunnel Walls Formwork Removel 2 13-Mar-24 14-Mar-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S13-TW.125Tunnel Wall Waterproofing 12 16-Mar-24 28-Mar-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 16-Mar-24 22-Apr-24 22-Apr-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S13-MS.090Middle Slab Scaffold and Formwork Installation 5 16-Mar-24 20-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S13-MS.100Middle Slab Rebar Installation 8 21-Mar-24 30-Mar-24 Middle Slab Rebar Installation

JAH-Z2-ST-S13-MS.105Middle Slab Vertical Formwork Installation 7 31-Mar-24 07-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S13-MS.110Middle Slab Concrete Casting 1 08-Apr-24 08-Apr-24 Middle Slab Concrete Casting

JAH-Z2-ST-S13-MS.115Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z2-ST-S13-MS.120Middle Slab Formwork Removel 2 21-Apr-24 22-Apr-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 23-Apr-24 21-May-24 21-May-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S13-UC.100Utility Culvert Walls Rebar Installation 8 23-Apr-24 01-May-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S13-UC.105Utility Culvert Walls Formwork Installation 7 02-May-24 09-May-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S13-UC.110Utility Culvert Walls Concrete Casting 1 11-May-24 11-May-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S13-UC.115Utility Culvert Walls Walls Formwork Removel 2 12-May-24 13-May-24 Utility Culvert Walls Walls Formwork Removel

JAH-Z2-ST-S13-UC.120Curing work 7 14-May-24 21-May-24 Curing work

TOP SLAB 37 22-May-24 08-Jul-24 08-Jul-24, TOP SLAB


JAH-Z2-ST-S13-TS.090 Top Slab Formwork Installation 7 22-May-24 29-May-24 Top Slab Formwork Installation

JAH-Z2-ST-S13-TS.100 Top Slab Rebar Installation 8 30-May-24 08-Jun-24 Top Slab Rebar Installation

JAH-Z2-ST-S13-TS.110 Top Slab Concrete Casting 1 09-Jun-24 09-Jun-24 Top Slab Concrete Casting

JAH-Z2-ST-S13-TS.112 Curing work 7 10-Jun-24 22-Jun-24 Curing work

JAH-Z2-ST-S13-TS.115 Top Slab Formwork Removel 2 23-Jun-24 24-Jun-24 Top Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
258 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S13-TS.120 Waterproofing for Top Slab 12 25-Jun-24 08-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 09-Jul-24 05-Aug-24 05-Aug-24, MASS CONCRETE WORK


JAH-Z2-ST-S13-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 09-Jul-24 16-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S13-MC.105Plain Concrete Casting 1 17-Jul-24 17-Jul-24 Plain Concrete Casting

JAH-Z2-ST-S13-MC.110Mass Concrete Casting for Base Slab Top Layer 1 18-Jul-24 18-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S13-MC.112Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z2-ST-S13-MC.115Concrete Protective coating 8 28-Jul-24 05-Aug-24 Concrete Protective coating

STA. 0+770.033 ~ 0+790.033 168 27-Jan-24 17-Aug-24 17-Aug-24, STA. 0+770.033 ~ 0+790.033
BASE SLAB 27 27-Jan-24 26-Feb-24 26-Feb-24, BASE SLAB
JAH-Z2-ST-S14-BS.100Lean Concrete for Base Slab 1 27-Jan-24 27-Jan-24 Lean Concrete for Base Slab

JAH-Z2-ST-S14-BS.105Waterproofing for Lean Concrete 1 28-Jan-24 28-Jan-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S14-BS.110 Base Slab Rebar Installation 8 29-Jan-24 06-Feb-24 Base Slab Rebar Installation

JAH-Z2-ST-S14-BS.115 Base Slab Formwork Installation 7 07-Feb-24 14-Feb-24 Base Slab Formwork Installation

JAH-Z2-ST-S14-BS.120Base Slab Concrete Casting 1 15-Feb-24 15-Feb-24 Base Slab Concrete Casting

JAH-Z2-ST-S14-BS.122Curing work 7 17-Feb-24 24-Feb-24 Curing work

JAH-Z2-ST-S14-BS.125Base Slab Formwork Removel 2 25-Feb-24 26-Feb-24 Base Slab Formwork Removel

COLUMN 23 27-Feb-24 24-Mar-24 24-Mar-24, COLUMN


JAH-Z2-ST-S14-CL.100Column Rebar Installation 8 27-Feb-24 06-Mar-24 Column Rebar Installation

JAH-Z2-ST-S14-CL.105Column Formwork Installation 7 07-Mar-24 14-Mar-24 Column Formwork Installation

JAH-Z2-ST-S14-CL.110 Column Concrete Casting 1 16-Mar-24 16-Mar-24 Column Concrete Casting

JAH-Z2-ST-S14-CL.115 Form Work Removal and Curing 7 17-Mar-24 24-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 27-Feb-24 13-Apr-24 13-Apr-24, TUNNEL WALLS


JAH-Z2-ST-S14-TW.100Tunnel Walls Rebar Installation 8 27-Feb-24 06-Mar-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S14-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 27-Feb-24 06-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S14-TW.105Tunnel Formwork Installation 7 07-Mar-24 14-Mar-24 Tunnel Formwork Installation

JAH-Z2-ST-S14-TW.110Tunnel Walls Concrete Casting 1 16-Mar-24 16-Mar-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S14-TW.112Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z2-ST-S14-TW.120Tunnel Walls Formwork Removel 2 25-Mar-24 26-Mar-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S14-TW.125Tunnel Wall Waterproofing 12 27-Mar-24 13-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 27-Mar-24 04-May-24 04-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S14-MS.090Middle Slab Scaffold and Formwork Installation 5 27-Mar-24 01-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S14-MS.100Middle Slab Rebar Installation 8 02-Apr-24 14-Apr-24 Middle Slab Rebar Installation

JAH-Z2-ST-S14-MS.105Middle Slab Vertical Formwork Installation 7 15-Apr-24 22-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S14-MS.110Middle Slab Concrete Casting 1 23-Apr-24 23-Apr-24 Middle Slab Concrete Casting

JAH-Z2-ST-S14-MS.115Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z2-ST-S14-MS.120Middle Slab Formwork Removel 2 02-May-24 04-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 05-May-24 02-Jun-24 02-Jun-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S14-UC.100Utility Culvert Walls Rebar Installation 8 05-May-24 13-May-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S14-UC.105Utility Culvert Walls Formwork Installation 7 14-May-24 21-May-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S14-UC.110Utility Culvert Walls Concrete Casting 1 22-May-24 22-May-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S14-UC.115Utility Culvert Walls Walls Formwork Removel 2 23-May-24 25-May-24 Utility Culvert Walls Walls Formwork Removel

JAH-Z2-ST-S14-UC.120Curing work 7 26-May-24 02-Jun-24 Curing work

TOP SLAB 37 03-Jun-24 20-Jul-24 20-Jul-24, TOP SLAB


JAH-Z2-ST-S14-TS.090 Top Slab Formwork Installation 7 03-Jun-24 10-Jun-24 Top Slab Formwork Installation

JAH-Z2-ST-S14-TS.100 Top Slab Rebar Installation 8 11-Jun-24 24-Jun-24 Top Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
259 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S14-TS.110 Top Slab Concrete Casting 1 25-Jun-24 25-Jun-24 Top Slab Concrete Casting

JAH-Z2-ST-S14-TS.112 Curing work 7 26-Jun-24 03-Jul-24 Curing work

JAH-Z2-ST-S14-TS.115 Top Slab Formwork Removel 2 04-Jul-24 06-Jul-24 Top Slab Formwork Removel

JAH-Z2-ST-S14-TS.120 Waterproofing for Top Slab 12 07-Jul-24 20-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 21-Jul-24 17-Aug-24 17-Aug-24, MASS CONCRETE WORK


JAH-Z2-ST-S14-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 21-Jul-24 28-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S14-MC.105Plain Concrete Casting 1 29-Jul-24 29-Jul-24 Plain Concrete Casting

JAH-Z2-ST-S14-MC.110Mass Concrete Casting for Base Slab Top Layer 1 30-Jul-24 30-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S14-MC.115Concrete Protective coating 8 08-Aug-24 17-Aug-24 Concrete Protective coating

JAH-Z2-ST-S14-MC.120Curing work 7 31-Jul-24 07-Aug-24 Curing work

STA. 0+790.033~ 0+810.033 168 07-Feb-24 28-Aug-24 28-Aug-24, STA. 0+790.033~ 0+810.033
BASE SLAB 27 07-Feb-24 09-Mar-24 09-Mar-24, BASE SLAB
JAH-Z2-ST-S15-BS.100Lean Concrete for Base Slab 1 07-Feb-24 07-Feb-24 Lean Concrete for Base Slab

JAH-Z2-ST-S15-BS.105Waterproofing for Lean Concrete 1 08-Feb-24 08-Feb-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S15-BS.110 Base Slab Rebar Installation 8 10-Feb-24 18-Feb-24 Base Slab Rebar Installation

JAH-Z2-ST-S15-BS.115 Base Slab Formwork Installation 7 19-Feb-24 26-Feb-24 Base Slab Formwork Installation

JAH-Z2-ST-S15-BS.120Base Slab Concrete Casting 1 27-Feb-24 27-Feb-24 Base Slab Concrete Casting

JAH-Z2-ST-S15-BS.122Curing work 7 28-Feb-24 06-Mar-24 Curing work

JAH-Z2-ST-S15-BS.125Base Slab Formwork Removel 2 07-Mar-24 09-Mar-24 Base Slab Formwork Removel

COLUMN 23 10-Mar-24 04-Apr-24 04-Apr-24, COLUMN


JAH-Z2-ST-S15-CL.100Column Rebar Installation 8 10-Mar-24 18-Mar-24 Column Rebar Installation

JAH-Z2-ST-S15-CL.105Column Formwork Installation 7 19-Mar-24 26-Mar-24 Column Formwork Installation

JAH-Z2-ST-S15-CL.110 Column Concrete Casting 1 27-Mar-24 27-Mar-24 Column Concrete Casting

JAH-Z2-ST-S15-CL.115 Form Work Removal and Curing 7 28-Mar-24 04-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 37 10-Mar-24 24-Apr-24 24-Apr-24, TUNNEL WALLS


JAH-Z2-ST-S15-TW.100Tunnel Walls Rebar Installation 8 10-Mar-24 18-Mar-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S15-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 10-Mar-24 18-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S15-TW.105Tunnel Formwork Installation 7 19-Mar-24 26-Mar-24 Tunnel Formwork Installation

JAH-Z2-ST-S15-TW.107Curing work 7 27-Mar-24 03-Apr-24 Curing work

JAH-Z2-ST-S15-TW.110Tunnel Walls Concrete Casting 1 04-Apr-24 04-Apr-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S15-TW.120Tunnel Walls Formwork Removel 2 06-Apr-24 07-Apr-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S15-TW.125Tunnel Wall Waterproofing 12 08-Apr-24 24-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 08-Apr-24 15-May-24 15-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S15-MS.090Middle Slab Scaffold and Formwork Installation 5 08-Apr-24 16-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S15-MS.100Middle Slab Rebar Installation 8 17-Apr-24 25-Apr-24 Middle Slab Rebar Installation

JAH-Z2-ST-S15-MS.105Middle Slab Vertical Formwork Installation 7 27-Apr-24 04-May-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S15-MS.110Middle Slab Concrete Casting 1 05-May-24 05-May-24 Middle Slab Concrete Casting

JAH-Z2-ST-S15-MS.115Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z2-ST-S15-MS.120Middle Slab Formwork Removel 2 14-May-24 15-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 16-May-24 13-Jun-24 13-Jun-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S15-UC.100Utility Culvert Walls Rebar Installation 8 16-May-24 25-May-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S15-UC.105Utility Culvert Walls Formwork Installation 7 26-May-24 02-Jun-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S15-UC.110Utility Culvert Walls Concrete Casting 1 03-Jun-24 03-Jun-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S15-UC.112Curing work 7 04-Jun-24 11-Jun-24 Curing work

JAH-Z2-ST-S15-UC.115Utility Culvert Walls Walls Formwork Removel 2 12-Jun-24 13-Jun-24 Utility Culvert Walls Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
260 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 37 19-Jun-24 31-Jul-24 31-Jul-24, TOP SLAB
JAH-Z2-ST-S15-TS.090 Top Slab Formwork Installation 7 19-Jun-24 26-Jun-24 Top Slab Formwork Installation

JAH-Z2-ST-S15-TS.100 Top Slab Rebar Installation 8 27-Jun-24 06-Jul-24 Top Slab Rebar Installation

JAH-Z2-ST-S15-TS.110 Top Slab Concrete Casting 1 07-Jul-24 07-Jul-24 Top Slab Concrete Casting

JAH-Z2-ST-S15-TS.112 Curing work 7 08-Jul-24 15-Jul-24 Curing work

JAH-Z2-ST-S15-TS.115 Top Slab Formwork Removel 2 16-Jul-24 17-Jul-24 Top Slab Formwork Removel

JAH-Z2-ST-S15-TS.120 Waterproofing for Top Slab 12 18-Jul-24 31-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 01-Aug-24 28-Aug-24 28-Aug-24, MASS CONCRETE WORK


JAH-Z2-ST-S15-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 01-Aug-24 08-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S15-MC.105Plain Concrete Casting 1 10-Aug-24 10-Aug-24 Plain Concrete Casting

JAH-Z2-ST-S15-MC.110Mass Concrete Casting for Base Slab Top Layer 1 11-Aug-24 11-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S15-MC.112Curing work 7 12-Aug-24 19-Aug-24 Curing work

JAH-Z2-ST-S15-MC.115Concrete Protective coating 8 20-Aug-24 28-Aug-24 Concrete Protective coating

STA. 0+810.033 ~ 0+830.033-1 168 19-Feb-24 09-Sep-24 09-Sep-24, STA. 0+810.033 ~ 0+830.033-1
BASE SLAB 27 19-Feb-24 20-Mar-24 20-Mar-24, BASE SLAB
JAH-Z2-ST-S16-BS.100Lean Concrete for Base Slab 1 19-Feb-24 19-Feb-24 Lean Concrete for Base Slab

JAH-Z2-ST-S16-BS.105Waterproofing for Lean Concrete 1 20-Feb-24 20-Feb-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S16-BS.110 Base Slab Rebar Installation 8 21-Feb-24 29-Feb-24 Base Slab Rebar Installation

JAH-Z2-ST-S16-BS.115 Base Slab Formwork Installation 7 02-Mar-24 09-Mar-24 Base Slab Formwork Installation

JAH-Z2-ST-S16-BS.120Base Slab Concrete Casting 1 10-Mar-24 10-Mar-24 Base Slab Concrete Casting

JAH-Z2-ST-S16-BS.122Curing work 7 11-Mar-24 18-Mar-24 Curing work

JAH-Z2-ST-S16-BS.125Base Slab Formwork Removel 2 19-Mar-24 20-Mar-24 Base Slab Formwork Removel

COLUMN 23 21-Mar-24 20-Apr-24 20-Apr-24, COLUMN


JAH-Z2-ST-S16-CL.100Column Rebar Installation 8 21-Mar-24 30-Mar-24 Column Rebar Installation

JAH-Z2-ST-S16-CL.105Column Formwork Installation 7 31-Mar-24 07-Apr-24 Column Formwork Installation

JAH-Z2-ST-S16-CL.110 Column Concrete Casting 1 08-Apr-24 08-Apr-24 Column Concrete Casting

JAH-Z2-ST-S16-CL.115 Form Work Removal and Curing 7 13-Apr-24 20-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 37 21-Mar-24 06-May-24 06-May-24, TUNNEL WALLS


JAH-Z2-ST-S16-TW.100Tunnel Walls Rebar Installation 8 21-Mar-24 30-Mar-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S16-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 21-Mar-24 30-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S16-TW.105Tunnel Formwork Installation 7 31-Mar-24 07-Apr-24 Tunnel Formwork Installation

JAH-Z2-ST-S16-TW.110Tunnel Walls Concrete Casting 1 08-Apr-24 08-Apr-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S16-TW.112Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z2-ST-S16-TW.120Tunnel Walls Formwork Removel 2 21-Apr-24 22-Apr-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S16-TW.125Tunnel Wall Waterproofing 12 23-Apr-24 06-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 23-Apr-24 27-May-24 27-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S16-MS.090Middle Slab Scaffold and Formwork Installation 5 23-Apr-24 28-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S16-MS.100Middle Slab Rebar Installation 8 29-Apr-24 07-May-24 Middle Slab Rebar Installation

JAH-Z2-ST-S16-MS.105Middle Slab Vertical Formwork Installation 7 08-May-24 15-May-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S16-MS.110Middle Slab Concrete Casting 1 16-May-24 16-May-24 Middle Slab Concrete Casting

JAH-Z2-ST-S16-MS.115Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z2-ST-S16-MS.120Middle Slab Formwork Removel 2 26-May-24 27-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 28-May-24 30-Jun-24 30-Jun-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S16-UC.100Utility Culvert Walls Rebar Installation 8 28-May-24 05-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S16-UC.105Utility Culvert Walls Formwork Installation 7 06-Jun-24 13-Jun-24 Utility Culvert Walls Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
261 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S16-UC.110Utility Culvert Walls Concrete Casting 1 19-Jun-24 19-Jun-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S16-UC.112Curing work 7 20-Jun-24 27-Jun-24 Curing work

JAH-Z2-ST-S16-UC.115Utility Culvert Walls Walls Formwork Removel 2 29-Jun-24 30-Jun-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 01-Jul-24 12-Aug-24 12-Aug-24, TOP SLAB


JAH-Z2-ST-S16-TS.090 Top Slab Formwork Installation 7 01-Jul-24 08-Jul-24 Top Slab Formwork Installation

JAH-Z2-ST-S16-TS.100 Top Slab Rebar Installation 8 09-Jul-24 17-Jul-24 Top Slab Rebar Installation

JAH-Z2-ST-S16-TS.110 Top Slab Concrete Casting 1 18-Jul-24 18-Jul-24 Top Slab Concrete Casting

JAH-Z2-ST-S16-TS.112 Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z2-ST-S16-TS.115 Top Slab Formwork Removel 2 28-Jul-24 29-Jul-24 Top Slab Formwork Removel

JAH-Z2-ST-S16-TS.120 Waterproofing for Top Slab 12 30-Jul-24 12-Aug-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 13-Aug-24 09-Sep-24 09-Sep-24, MASS CONCRETE WORK


JAH-Z2-ST-S16-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 13-Aug-24 20-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S16-MC.105Plain Concrete Casting 1 21-Aug-24 21-Aug-24 Plain Concrete Casting

JAH-Z2-ST-S16-MC.110Mass Concrete Casting for Base Slab Top Layer 1 22-Aug-24 22-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S16-MC.112Curing work 7 24-Aug-24 31-Aug-24 Curing work

JAH-Z2-ST-S16-MC.115Concrete Protective coating 8 01-Sep-24 09-Sep-24 Concrete Protective coating

STA. 0+830.033 ~ 0+850.033 168 02-Mar-24 21-Sep-24 21-Sep-24, STA. 0+830.033 ~ 0+850.033
BASE SLAB 27 02-Mar-24 01-Apr-24 01-Apr-24, BASE SLAB
JAH-Z2-ST-S17-BS.100Lean Concrete for Base Slab 1 02-Mar-24 02-Mar-24 Lean Concrete for Base Slab

JAH-Z2-ST-S17-BS.105Waterproofing for Lean Concrete 1 03-Mar-24 03-Mar-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S17-BS.110 Base Slab Rebar Installation 8 04-Mar-24 12-Mar-24 Base Slab Rebar Installation

JAH-Z2-ST-S17-BS.115 Base Slab Formwork Installation 7 13-Mar-24 20-Mar-24 Base Slab Formwork Installation

JAH-Z2-ST-S17-BS.120Base Slab Concrete Casting 1 21-Mar-24 21-Mar-24 Base Slab Concrete Casting

JAH-Z2-ST-S17-BS.122Curing work 7 23-Mar-24 30-Mar-24 Curing work

JAH-Z2-ST-S17-BS.125Base Slab Formwork Removel 2 31-Mar-24 01-Apr-24 Base Slab Formwork Removel

COLUMN 23 02-Apr-24 01-May-24 01-May-24, COLUMN


JAH-Z2-ST-S17-CL.100Column Rebar Installation 8 02-Apr-24 14-Apr-24 Column Rebar Installation

JAH-Z2-ST-S17-CL.105Column Formwork Installation 7 15-Apr-24 22-Apr-24 Column Formwork Installation

JAH-Z2-ST-S17-CL.110 Column Concrete Casting 1 23-Apr-24 23-Apr-24 Column Concrete Casting

JAH-Z2-ST-S17-CL.115 Form Work Removal and Curing 7 24-Apr-24 01-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 02-Apr-24 18-May-24 18-May-24, TUNNEL WALLS


JAH-Z2-ST-S17-TW.100Tunnel Walls Rebar Installation 8 02-Apr-24 14-Apr-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S17-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 02-Apr-24 14-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S17-TW.105Tunnel Formwork Installation 7 15-Apr-24 22-Apr-24 Tunnel Formwork Installation

JAH-Z2-ST-S17-TW.110Tunnel Walls Concrete Casting 1 23-Apr-24 23-Apr-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S17-TW.112Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z2-ST-S17-TW.120Tunnel Walls Formwork Removel 2 02-May-24 04-May-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S17-TW.125Tunnel Wall Waterproofing 12 05-May-24 18-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 05-May-24 08-Jun-24 08-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S17-MS.090Middle Slab Scaffold and Formwork Installation 5 05-May-24 09-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S17-MS.100Middle Slab Rebar Installation 8 11-May-24 19-May-24 Middle Slab Rebar Installation

JAH-Z2-ST-S17-MS.105Middle Slab Vertical Formwork Installation 7 20-May-24 27-May-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S17-MS.110Middle Slab Concrete Casting 1 28-May-24 28-May-24 Middle Slab Concrete Casting

JAH-Z2-ST-S17-MS.115Curing work 7 29-May-24 05-Jun-24 Curing work

JAH-Z2-ST-S17-MS.120Middle Slab Formwork Removel 2 06-Jun-24 08-Jun-24 Middle Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
262 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UTILITY CULVERT WALLS 25 09-Jun-24 11-Jul-24 11-Jul-24, UTILITY CULVERT WALLS
JAH-Z2-ST-S17-UC.100Utility Culvert Walls Rebar Installation 8 09-Jun-24 22-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S17-UC.105Utility Culvert Walls Formwork Installation 7 23-Jun-24 30-Jun-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S17-UC.110Utility Culvert Walls Concrete Casting 1 01-Jul-24 01-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S17-UC.112Curing work 7 02-Jul-24 09-Jul-24 Curing work

JAH-Z2-ST-S17-UC.115Utility Culvert Walls Walls Formwork Removel 2 10-Jul-24 11-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 13-Jul-24 24-Aug-24 24-Aug-24, TOP SLAB


JAH-Z2-ST-S17-TS.090 Top Slab Formwork Installation 7 13-Jul-24 20-Jul-24 Top Slab Formwork Installation

JAH-Z2-ST-S17-TS.100 Top Slab Rebar Installation 8 21-Jul-24 29-Jul-24 Top Slab Rebar Installation

JAH-Z2-ST-S17-TS.110 Top Slab Concrete Casting 1 30-Jul-24 30-Jul-24 Top Slab Concrete Casting

JAH-Z2-ST-S17-TS.112 Curing work 7 31-Jul-24 07-Aug-24 Curing work

JAH-Z2-ST-S17-TS.115 Top Slab Formwork Removel 2 08-Aug-24 10-Aug-24 Top Slab Formwork Removel

JAH-Z2-ST-S17-TS.120 Waterproofing for Top Slab 12 11-Aug-24 24-Aug-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 25-Aug-24 21-Sep-24 21-Sep-24, MASS CONCRETE WORK


JAH-Z2-ST-S17-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 25-Aug-24 01-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S17-MC.105Plain Concrete Casting 1 02-Sep-24 02-Sep-24 Plain Concrete Casting

JAH-Z2-ST-S17-MC.110Mass Concrete Casting for Base Slab Top Layer 1 03-Sep-24 03-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S17-MC.112Curing work 7 04-Sep-24 11-Sep-24 Curing work

JAH-Z2-ST-S17-MC.115Concrete Protective coating 8 12-Sep-24 21-Sep-24 Concrete Protective coating

STA. 0+850.033 ~ 0+870.033 168 13-Mar-24 03-Oct-24 03-Oct-24, STA. 0+850.033 ~ 0+870.033
BASE SLAB 27 13-Mar-24 16-Apr-24 16-Apr-24, BASE SLAB
JAH-Z2-ST-S18-BS.100Lean Concrete for Base Slab 1 13-Mar-24 13-Mar-24 Lean Concrete for Base Slab

JAH-Z2-ST-S18-BS.105Waterproofing for Lean Concrete 1 14-Mar-24 14-Mar-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S18-BS.110 Base Slab Rebar Installation 8 16-Mar-24 24-Mar-24 Base Slab Rebar Installation

JAH-Z2-ST-S18-BS.115 Base Slab Formwork Installation 7 25-Mar-24 01-Apr-24 Base Slab Formwork Installation

JAH-Z2-ST-S18-BS.120Base Slab Concrete Casting 1 02-Apr-24 02-Apr-24 Base Slab Concrete Casting

JAH-Z2-ST-S18-BS.122Curing work 7 03-Apr-24 14-Apr-24 Curing work

JAH-Z2-ST-S18-BS.125Base Slab Formwork Removel 2 15-Apr-24 16-Apr-24 Base Slab Formwork Removel

COLUMN 23 17-Apr-24 13-May-24 13-May-24, COLUMN


JAH-Z2-ST-S18-CL.100Column Rebar Installation 8 17-Apr-24 25-Apr-24 Column Rebar Installation

JAH-Z2-ST-S18-CL.105Column Formwork Installation 7 27-Apr-24 04-May-24 Column Formwork Installation

JAH-Z2-ST-S18-CL.110 Column Concrete Casting 1 05-May-24 05-May-24 Column Concrete Casting

JAH-Z2-ST-S18-CL.115 Form Work Removal and Curing 7 06-May-24 13-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 17-Apr-24 29-May-24 29-May-24, TUNNEL WALLS


JAH-Z2-ST-S18-TW.100Tunnel Walls Rebar Installation 8 17-Apr-24 25-Apr-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S18-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 17-Apr-24 25-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S18-TW.105Tunnel Formwork Installation 7 27-Apr-24 04-May-24 Tunnel Formwork Installation

JAH-Z2-ST-S18-TW.110Tunnel Walls Concrete Casting 1 05-May-24 05-May-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S18-TW.115Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z2-ST-S18-TW.120Tunnel Walls Formwork Removel 2 14-May-24 15-May-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S18-TW.125Tunnel Wall Waterproofing 12 16-May-24 29-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 16-May-24 24-Jun-24 24-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S18-MS.090Middle Slab Scaffold and Formwork Installation 5 16-May-24 21-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S18-MS.100Middle Slab Rebar Installation 8 22-May-24 30-May-24 Middle Slab Rebar Installation

JAH-Z2-ST-S18-MS.105Middle Slab Vertical Formwork Installation 7 01-Jun-24 08-Jun-24 Middle Slab Vertical Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
263 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S18-MS.110Middle Slab Concrete Casting 1 09-Jun-24 09-Jun-24 Middle Slab Concrete Casting

JAH-Z2-ST-S18-MS.115Curing work 7 10-Jun-24 22-Jun-24 Curing work

JAH-Z2-ST-S18-MS.120Middle Slab Formwork Removel 2 23-Jun-24 24-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 25-Jun-24 23-Jul-24 23-Jul-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S18-UC.100Utility Culvert Walls Rebar Installation 8 25-Jun-24 03-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S18-UC.105Utility Culvert Walls Formwork Installation 7 04-Jul-24 11-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S18-UC.110Utility Culvert Walls Concrete Casting 1 13-Jul-24 13-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S18-UC.112Curing work 7 14-Jul-24 21-Jul-24 Curing work

JAH-Z2-ST-S18-UC.115Utility Culvert Walls Walls Formwork Removel 2 22-Jul-24 23-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 24-Jul-24 04-Sep-24 04-Sep-24, TOP SLAB


JAH-Z2-ST-S18-TS.090 Top Slab Formwork Installation 7 24-Jul-24 31-Jul-24 Top Slab Formwork Installation

JAH-Z2-ST-S18-TS.100 Top Slab Rebar Installation 8 01-Aug-24 10-Aug-24 Top Slab Rebar Installation

JAH-Z2-ST-S18-TS.110 Top Slab Concrete Casting 1 11-Aug-24 11-Aug-24 Top Slab Concrete Casting

JAH-Z2-ST-S18-TS.112 Curing work 7 12-Aug-24 19-Aug-24 Curing work

JAH-Z2-ST-S18-TS.115 Top Slab Formwork Removel 2 20-Aug-24 21-Aug-24 Top Slab Formwork Removel

JAH-Z2-ST-S18-TS.120 Waterproofing for Top Slab 12 22-Aug-24 04-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 05-Sep-24 03-Oct-24 03-Oct-24, MASS CONCRETE WORK


JAH-Z2-ST-S18-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 05-Sep-24 12-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S18-MC.105Plain Concrete Casting 1 14-Sep-24 14-Sep-24 Plain Concrete Casting

JAH-Z2-ST-S18-MC.110Mass Concrete Casting for Base Slab Top Layer 1 15-Sep-24 15-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S18-MC.112Curing work 7 16-Sep-24 24-Sep-24 Curing work

JAH-Z2-ST-S18-MC.115Concrete Protective coating 8 25-Sep-24 03-Oct-24 Concrete Protective coating

STA. 0+870.033 ~ 0+890.033 168 25-Mar-24 15-Oct-24 15-Oct-24, STA. 0+870.033 ~ 0+890.033
BASE SLAB 27 25-Mar-24 28-Apr-24 28-Apr-24, BASE SLAB
JAH-Z2-ST-S19-BS.100Lean Concrete for Base Slab 1 25-Mar-24 25-Mar-24 Lean Concrete for Base Slab

JAH-Z2-ST-S19-BS.105Waterproofing for Lean Concrete 1 26-Mar-24 26-Mar-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S19-BS.110 Base Slab Rebar Installation 8 27-Mar-24 04-Apr-24 Base Slab Rebar Installation

JAH-Z2-ST-S19-BS.115 Base Slab Formwork Installation 7 06-Apr-24 16-Apr-24 Base Slab Formwork Installation

JAH-Z2-ST-S19-BS.120Base Slab Concrete Casting 1 17-Apr-24 17-Apr-24 Base Slab Concrete Casting

JAH-Z2-ST-S19-BS.122Curing work 7 18-Apr-24 25-Apr-24 Curing work

JAH-Z2-ST-S19-BS.125Base Slab Formwork Removel 2 27-Apr-24 28-Apr-24 Base Slab Formwork Removel

COLUMN 23 29-Apr-24 25-May-24 25-May-24, COLUMN


JAH-Z2-ST-S19-CL.100Column Rebar Installation 8 29-Apr-24 07-May-24 Column Rebar Installation

JAH-Z2-ST-S19-CL.105Column Formwork Installation 7 08-May-24 15-May-24 Column Formwork Installation

JAH-Z2-ST-S19-CL.110 Column Concrete Casting 1 16-May-24 16-May-24 Column Concrete Casting

JAH-Z2-ST-S19-CL.115 Form Work Removal and Curing 7 18-May-24 25-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 29-Apr-24 10-Jun-24 10-Jun-24, TUNNEL WALLS


JAH-Z2-ST-S19-TW.100Tunnel Walls Rebar Installation 8 29-Apr-24 07-May-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S19-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 29-Apr-24 07-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S19-TW.105Tunnel Formwork Installation 7 08-May-24 15-May-24 Tunnel Formwork Installation

JAH-Z2-ST-S19-TW.110Tunnel Walls Concrete Casting 1 16-May-24 16-May-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S19-TW.115Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z2-ST-S19-TW.120Tunnel Walls Formwork Removel 2 26-May-24 27-May-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S19-TW.125Tunnel Wall Waterproofing 12 28-May-24 10-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-May-24 06-Jul-24 06-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
264 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S19-MS.090Middle Slab Scaffold and Formwork Installation 5 28-May-24 02-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S19-MS.100Middle Slab Rebar Installation 8 03-Jun-24 11-Jun-24 Middle Slab Rebar Installation

JAH-Z2-ST-S19-MS.105Middle Slab Vertical Formwork Installation 7 12-Jun-24 24-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S19-MS.110Middle Slab Concrete Casting 1 25-Jun-24 25-Jun-24 Middle Slab Concrete Casting

JAH-Z2-ST-S19-MS.115Curing work 7 26-Jun-24 03-Jul-24 Curing work

JAH-Z2-ST-S19-MS.120Middle Slab Formwork Removel 2 04-Jul-24 06-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 07-Jul-24 04-Aug-24 04-Aug-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S19-UC.100Utility Culvert Walls Rebar Installation 8 07-Jul-24 15-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S19-UC.105Utility Culvert Walls Formwork Installation 7 16-Jul-24 23-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S19-UC.110Utility Culvert Walls Concrete Casting 1 24-Jul-24 24-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S19-UC.112Curing work 7 25-Jul-24 01-Aug-24 Curing work

JAH-Z2-ST-S19-UC.115Utility Culvert Walls Walls Formwork Removel 2 03-Aug-24 04-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 05-Aug-24 16-Sep-24 16-Sep-24, TOP SLAB


JAH-Z2-ST-S19-TS.090 Top Slab Formwork Installation 7 05-Aug-24 12-Aug-24 Top Slab Formwork Installation

JAH-Z2-ST-S19-TS.100 Top Slab Rebar Installation 8 13-Aug-24 21-Aug-24 Top Slab Rebar Installation

JAH-Z2-ST-S19-TS.110 Top Slab Concrete Casting 1 22-Aug-24 22-Aug-24 Top Slab Concrete Casting

JAH-Z2-ST-S19-TS.112 Curing work 7 24-Aug-24 31-Aug-24 Curing work

JAH-Z2-ST-S19-TS.115 Top Slab Formwork Removel 2 01-Sep-24 02-Sep-24 Top Slab Formwork Removel

JAH-Z2-ST-S19-TS.120 Waterproofing for Top Slab 12 03-Sep-24 16-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 17-Sep-24 15-Oct-24 15-Oct-24, MASS CONCRETE WORK


JAH-Z2-ST-S19-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 17-Sep-24 25-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S19-MC.105Plain Concrete Casting 1 26-Sep-24 26-Sep-24 Plain Concrete Casting

JAH-Z2-ST-S19-MC.110Mass Concrete Casting for Base Slab Top Layer 1 28-Sep-24 28-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S19-MC.112Curing work 7 29-Sep-24 06-Oct-24 Curing work

JAH-Z2-ST-S19-MC.115Concrete Protective coating 8 07-Oct-24 15-Oct-24 Concrete Protective coating

STA. 0+890.033 ~ 0+910.033 168 06-Apr-24 27-Oct-24 27-Oct-24, STA. 0+890.033 ~ 0+910.033
BASE SLAB 27 06-Apr-24 09-May-24 09-May-24, BASE SLAB
JAH-Z2-ST-S20-BS.100Lean Concrete for Base Slab 1 06-Apr-24 06-Apr-24 Lean Concrete for Base Slab

JAH-Z2-ST-S20-BS.105Waterproofing for Lean Concrete 1 07-Apr-24 07-Apr-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S20-BS.110 Base Slab Rebar Installation 8 08-Apr-24 20-Apr-24 Base Slab Rebar Installation

JAH-Z2-ST-S20-BS.115 Base Slab Formwork Installation 7 21-Apr-24 28-Apr-24 Base Slab Formwork Installation

JAH-Z2-ST-S20-BS.120Base Slab Concrete Casting 1 29-Apr-24 29-Apr-24 Base Slab Concrete Casting

JAH-Z2-ST-S20-BS.122Curing work 7 30-Apr-24 07-May-24 Curing work

JAH-Z2-ST-S20-BS.125Base Slab Formwork Removel 2 08-May-24 09-May-24 Base Slab Formwork Removel

COLUMN 23 11-May-24 05-Jun-24 05-Jun-24, COLUMN


JAH-Z2-ST-S20-CL.100Column Rebar Installation 8 11-May-24 19-May-24 Column Rebar Installation

JAH-Z2-ST-S20-CL.105Column Formwork Installation 7 20-May-24 27-May-24 Column Formwork Installation

JAH-Z2-ST-S20-CL.110 Column Concrete Casting 1 28-May-24 28-May-24 Column Concrete Casting

JAH-Z2-ST-S20-CL.115 Form Work Removal and Curing 7 29-May-24 05-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 11-May-24 26-Jun-24 26-Jun-24, TUNNEL WALLS


JAH-Z2-ST-S20-TW.100Tunnel Walls Rebar Installation 8 11-May-24 19-May-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S20-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-May-24 19-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z2-ST-S20-TW.105Tunnel Formwork Installation 7 20-May-24 27-May-24 Tunnel Formwork Installation

JAH-Z2-ST-S20-TW.110Tunnel Walls Concrete Casting 1 28-May-24 28-May-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S20-TW.115Curing work 7 29-May-24 05-Jun-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
265 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S20-TW.120Tunnel Walls Formwork Removel 2 06-Jun-24 08-Jun-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S20-TW.125Tunnel Wall Waterproofing 12 09-Jun-24 26-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 09-Jun-24 17-Jul-24 17-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S20-MS.090Middle Slab Scaffold and Formwork Installation 5 09-Jun-24 13-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S20-MS.100Middle Slab Rebar Installation 8 19-Jun-24 27-Jun-24 Middle Slab Rebar Installation

JAH-Z2-ST-S20-MS.105Middle Slab Vertical Formwork Installation 7 29-Jun-24 06-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S20-MS.110Middle Slab Concrete Casting 1 07-Jul-24 07-Jul-24 Middle Slab Concrete Casting

JAH-Z2-ST-S20-MS.115Curing work 7 08-Jul-24 15-Jul-24 Curing work

JAH-Z2-ST-S20-MS.120Middle Slab Formwork Removel 2 16-Jul-24 17-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 18-Jul-24 15-Aug-24 15-Aug-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S20-UC.100Utility Culvert Walls Rebar Installation 8 18-Jul-24 27-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S20-UC.105Utility Culvert Walls Formwork Installation 7 28-Jul-24 04-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S20-UC.110Utility Culvert Walls Concrete Casting 1 05-Aug-24 05-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S20-UC.112Curing work 7 06-Aug-24 13-Aug-24 Curing work

JAH-Z2-ST-S20-UC.115Utility Culvert Walls Walls Formwork Removel 2 14-Aug-24 15-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 17-Aug-24 29-Sep-24 29-Sep-24, TOP SLAB


JAH-Z2-ST-S20-TS.090 Top Slab Formwork Installation 7 17-Aug-24 24-Aug-24 Top Slab Formwork Installation

JAH-Z2-ST-S20-TS.100 Top Slab Rebar Installation 8 25-Aug-24 02-Sep-24 Top Slab Rebar Installation

JAH-Z2-ST-S20-TS.110 Top Slab Concrete Casting 1 03-Sep-24 03-Sep-24 Top Slab Concrete Casting

JAH-Z2-ST-S20-TS.112 Curing work 7 04-Sep-24 11-Sep-24 Curing work

JAH-Z2-ST-S20-TS.115 Top Slab Formwork Removel 2 12-Sep-24 14-Sep-24 Top Slab Formwork Removel

JAH-Z2-ST-S20-TS.120 Waterproofing for Top Slab 12 15-Sep-24 29-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 30-Sep-24 27-Oct-24 27-Oct-24, MASS CONCRETE WORK


JAH-Z2-ST-S20-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 30-Sep-24 07-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S20-MC.105Plain Concrete Casting 1 08-Oct-24 08-Oct-24 Plain Concrete Casting

JAH-Z2-ST-S20-MC.110Mass Concrete Casting for Base Slab Top Layer 1 09-Oct-24 09-Oct-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S20-MC.112Curing work 7 10-Oct-24 17-Oct-24 Curing work

JAH-Z2-ST-S20-MC.115Concrete Protective Coating 8 19-Oct-24 27-Oct-24 Concrete Protective Coating

STA. 0+910.033 ~ 0+993.979 168 21-Apr-24 07-Nov-24 07-Nov-24, STA. 0+910.033 ~ 0+993.979
BASE SLAB 27 21-Apr-24 21-May-24 21-May-24, BASE SLAB
JAH-Z2-ST-S21-BS.100Lean Concrete for Base Slab 1 21-Apr-24 21-Apr-24 Lean Concrete for Base Slab

JAH-Z2-ST-S21-BS.105Waterproofing for Lean Concrete 1 22-Apr-24 22-Apr-24 Waterproofing for Lean Concrete

JAH-Z2-ST-S21-BS.110 Base Slab Rebar Installation 8 23-Apr-24 01-May-24 Base Slab Rebar Installation

JAH-Z2-ST-S21-BS.115 Base Slab Formwork Installation 7 02-May-24 09-May-24 Base Slab Formwork Installation

JAH-Z2-ST-S21-BS.120Base Slab Concrete Casting 1 11-May-24 11-May-24 Base Slab Concrete Casting

JAH-Z2-ST-S21-BS.122Curing work 7 12-May-24 19-May-24 Curing work

JAH-Z2-ST-S21-BS.125Base Slab Formwork Removel 2 20-May-24 21-May-24 Base Slab Formwork Removel

COLUMN 23 22-May-24 22-Jun-24 22-Jun-24, COLUMN


JAH-Z2-ST-S21-CL.100Column Rebar Installation 8 22-May-24 30-May-24 Column Rebar Installation

JAH-Z2-ST-S21-CL.105Column Formwork Installation 7 01-Jun-24 08-Jun-24 Column Formwork Installation

JAH-Z2-ST-S21-CL.110 Column Concrete Casting 1 09-Jun-24 09-Jun-24 Column Concrete Casting

JAH-Z2-ST-S21-CL.115 Form Work Removal and Curing 7 10-Jun-24 22-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 22-May-24 08-Jul-24 08-Jul-24, TUNNEL WALLS


JAH-Z2-ST-S21-TW.100Tunnel Walls Rebar Installation 8 22-May-24 30-May-24 Tunnel Walls Rebar Installation

JAH-Z2-ST-S21-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-May-24 30-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
266 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ST-S21-TW.105Tunnel Formwork Installation 7 01-Jun-24 08-Jun-24 Tunnel Formwork Installation

JAH-Z2-ST-S21-TW.110Tunnel Walls Concrete Casting 1 09-Jun-24 09-Jun-24 Tunnel Walls Concrete Casting

JAH-Z2-ST-S21-TW.115Curing work 7 10-Jun-24 22-Jun-24 Curing work

JAH-Z2-ST-S21-TW.120Tunnel Walls Formwork Removel 2 23-Jun-24 24-Jun-24 Tunnel Walls Formwork Removel

JAH-Z2-ST-S21-TW.125Tunnel Wall Waterproofing 12 25-Jun-24 08-Jul-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 25-Jun-24 29-Jul-24 29-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z2-ST-S21-MS.090Middle Slab Scaffold and Formwork Installation 5 25-Jun-24 30-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z2-ST-S21-MS.100Middle Slab Rebar Installation 8 01-Jul-24 09-Jul-24 Middle Slab Rebar Installation

JAH-Z2-ST-S21-MS.105Middle Slab Vertical Formwork Installation 7 10-Jul-24 17-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z2-ST-S21-MS.110Middle Slab Concrete Casting 1 18-Jul-24 18-Jul-24 Middle Slab Concrete Casting

JAH-Z2-ST-S21-MS.115Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z2-ST-S21-MS.120Middle Slab Formwork Removel 2 28-Jul-24 29-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 30-Jul-24 27-Aug-24 27-Aug-24, UTILITY CULVERT WALLS


JAH-Z2-ST-S21-UC.100Utility Culvert Walls Rebar Installation 8 30-Jul-24 07-Aug-24 Utility Culvert Walls Rebar Installation

JAH-Z2-ST-S21-UC.105Utility Culvert Walls Formwork Installation 7 08-Aug-24 15-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z2-ST-S21-UC.110Utility Culvert Walls Concrete Casting 1 17-Aug-24 17-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z2-ST-S21-UC.112Curing work 7 18-Aug-24 25-Aug-24 Curing work

JAH-Z2-ST-S21-UC.115Utility Culvert Walls Walls Formwork Removel 2 26-Aug-24 27-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 28-Aug-24 10-Oct-24 10-Oct-24, TOP SLAB


JAH-Z2-ST-S21-TS.090 Top Slab Formwork Installation 7 28-Aug-24 04-Sep-24 Top Slab Formwork Installation

JAH-Z2-ST-S21-TS.100 Top Slab Rebar Installation 8 05-Sep-24 14-Sep-24 Top Slab Rebar Installation

JAH-Z2-ST-S21-TS.110 Top Slab Concrete Casting 1 15-Sep-24 15-Sep-24 Top Slab Concrete Casting

JAH-Z2-ST-S21-TS.112 Curing work 7 16-Sep-24 24-Sep-24 Curing work

JAH-Z2-ST-S21-TS.115 Top Slab Formwork Removel 2 25-Sep-24 26-Sep-24 Top Slab Formwork Removel

JAH-Z2-ST-S21-TS.120 Waterproofing for Top Slab 12 28-Sep-24 10-Oct-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 12-Oct-24 07-Nov-24 07-Nov-24, MASS CONCRETE WORK


JAH-Z2-ST-S21-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 12-Oct-24 19-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z2-ST-S21-MC.105Plain Concrete Casting 1 20-Oct-24 20-Oct-24 Plain Concrete Casting

JAH-Z2-ST-S21-MC.110Mass Concrete Casting for Base Slab Top Layer 1 21-Oct-24 21-Oct-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z2-ST-S21-MC.112Curing work 7 22-Oct-24 29-Oct-24 Curing work

JAH-Z2-ST-S21-MC.115Concrete Protective Coating 8 30-Oct-24 07-Nov-24 Concrete Protective Coating

EGRESS STAIR-1 (ZONE-2) 236 12-Dec-23 19-Sep-24 19-Sep-24, EGRESS STAIR-1 (ZONE-2)
WALL AND 1ST FLIGHT 31 12-Dec-23 16-Jan-24 16-Jan-24, WALL AND 1ST FLIGHT
ENGR-STAIR-1-100 Excavation for Foundation 6 12-Dec-23 18-Dec-23 Excavation for Foundation

ENGR-STAIR-1-105 Foundation Blinding Concrete casting 1 19-Dec-23 19-Dec-23 Foundation Blinding Concrete casting

ENGR-STAIR-1-110 Foundation Rebar Installation 3 20-Dec-23 23-Dec-23 Foundation Rebar Installation

ENGR-STAIR-1-115 Foundation Formwork installation 3 24-Dec-23 26-Dec-23 Foundation Formwork installation

ENGR-STAIR-1-120 Foundation Concrete casting 1 27-Dec-23 27-Dec-23 Foundation Concrete casting

ENGR-STAIR-1-125 Wall and Stair Rebar Installation 4 28-Dec-23 01-Jan-24 Wall and Stair Rebar Installation

ENGR-STAIR-1-130 Wall and Stair Form work Installation 6 02-Jan-24 08-Jan-24 Wall and Stair Form work Installation

ENGR-STAIR-1-135 Form Removal and Curing 7 09-Jan-24 16-Jan-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 17-Jan-24 05-Feb-24 05-Feb-24, WALL AND 2ND FLIGHT
ENGR-STAIR-1-140 Stair Form work Installation 3 17-Jan-24 20-Jan-24 Stair Form work Installation

ENGR-STAIR-1-145 Wall Rebar Installation 3 21-Jan-24 23-Jan-24 Wall Rebar Installation

ENGR-STAIR-1-150 Wall Form work Installation 3 24-Jan-24 27-Jan-24 Wall Form work Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
267 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-1-155 Wall and Stair Concrete casting 1 28-Jan-24 28-Jan-24 Wall and Stair Concrete casting

ENGR-STAIR-1-375 Form Removal and Curing 7 29-Jan-24 05-Feb-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 06-Feb-24 25-Feb-24 25-Feb-24, WALL AND 3RD FLIGHT
ENGR-STAIR-1-180 Stair Form work Installation 3 06-Feb-24 08-Feb-24 Stair Form work Installation

ENGR-STAIR-1-185 Wall Rebar Installation 3 10-Feb-24 12-Feb-24 Wall Rebar Installation

ENGR-STAIR-1-190 Wall Form work Installation 3 13-Feb-24 15-Feb-24 Wall Form work Installation

ENGR-STAIR-1-195 Wall and Stair Concrete casting 1 17-Feb-24 17-Feb-24 Wall and Stair Concrete casting

ENGR-STAIR-1-370 Form Removal and Curing 7 18-Feb-24 25-Feb-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 26-Feb-24 16-Mar-24 16-Mar-24, WALL AND 4TH FLIGHT
ENGR-STAIR-1-160 Stair Form work Installation 3 26-Feb-24 28-Feb-24 Stair Form work Installation

ENGR-STAIR-1-165 Wall Rebar Installation 3 29-Feb-24 03-Mar-24 Wall Rebar Installation

ENGR-STAIR-1-170 Wall Form work Installation 3 04-Mar-24 06-Mar-24 Wall Form work Installation

ENGR-STAIR-1-175 Wall and Stair Concrete casting 1 07-Mar-24 07-Mar-24 Wall and Stair Concrete casting

ENGR-STAIR-1-365 Form Removal and Curing 7 09-Mar-24 16-Mar-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 17-Mar-24 04-Apr-24 04-Apr-24, WALL AND 5TH FLIGHT
ENGR-STAIR-1-240 Stair Form work Installation 3 17-Mar-24 19-Mar-24 Stair Form work Installation

ENGR-STAIR-1-245 Wall Rebar Installation 3 20-Mar-24 23-Mar-24 Wall Rebar Installation

ENGR-STAIR-1-250 Wall Form work Installation 3 24-Mar-24 26-Mar-24 Wall Form work Installation

ENGR-STAIR-1-255 Wall and Stair Concrete casting 1 27-Mar-24 27-Mar-24 Wall and Stair Concrete casting

ENGR-STAIR-1-360 Form Removal and Curing 7 28-Mar-24 04-Apr-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 06-Apr-24 28-Apr-24 28-Apr-24, WALL AND 6TH FLIGHT
ENGR-STAIR-1-260 Stair Form work Installation 3 06-Apr-24 08-Apr-24 Stair Form work Installation

ENGR-STAIR-1-265 Wall Rebar Installation 3 13-Apr-24 15-Apr-24 Wall Rebar Installation

ENGR-STAIR-1-270 Wall Form work Installation 3 16-Apr-24 18-Apr-24 Wall Form work Installation

ENGR-STAIR-1-275 Wall and Stair Concrete casting 1 20-Apr-24 20-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-1-355 Form Removal and Curing 7 21-Apr-24 28-Apr-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 29-Apr-24 18-May-24 18-May-24, WALL AND 7TH FLIGHT
ENGR-STAIR-1-220 Stair Form work Installation 3 29-Apr-24 01-May-24 Stair Form work Installation

ENGR-STAIR-1-225 Wall Rebar Installation 3 02-May-24 05-May-24 Wall Rebar Installation

ENGR-STAIR-1-230 Wall Form work Installation 3 06-May-24 08-May-24 Wall Form work Installation

ENGR-STAIR-1-235 Wall and Stair Concrete casting 1 09-May-24 09-May-24 Wall and Stair Concrete casting

ENGR-STAIR-1-380 Form Removal and Curing 7 11-May-24 18-May-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 19-May-24 06-Jun-24 06-Jun-24, WALL AND 8TH FLIGHT
ENGR-STAIR-1-200 Stair Form work Installation 3 19-May-24 21-May-24 Stair Form work Installation

ENGR-STAIR-1-205 Wall Rebar Installation 3 22-May-24 25-May-24 Wall Rebar Installation

ENGR-STAIR-1-210 Wall Form work Installation 3 26-May-24 28-May-24 Wall Form work Installation

ENGR-STAIR-1-215 Wall and Stair Concrete casting 1 29-May-24 29-May-24 Wall and Stair Concrete casting

ENGR-STAIR-1-385 Form Removal and Curing 7 30-May-24 06-Jun-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 08-Jun-24 01-Jul-24 01-Jul-24, WALL AND 9TH FLIGHT
ENGR-STAIR-1-315 Stair Form work Installation 3 08-Jun-24 10-Jun-24 Stair Form work Installation

ENGR-STAIR-1-320 Wall Rebar Installation 3 11-Jun-24 13-Jun-24 Wall Rebar Installation

ENGR-STAIR-1-325 Wall Form work Installation 3 19-Jun-24 22-Jun-24 Wall Form work Installation

ENGR-STAIR-1-330 Wall and Stair Concrete casting 1 23-Jun-24 23-Jun-24 Wall and Stair Concrete casting

ENGR-STAIR-1-390 Form Removal and Curing 7 24-Jun-24 01-Jul-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 02-Jul-24 21-Jul-24 21-Jul-24, WALL AND 10TH FLIGHT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
268 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-1-335 Stair Form work Installation 3 02-Jul-24 04-Jul-24 Stair Form work Installation

ENGR-STAIR-1-340 Wall Rebar Installation 3 06-Jul-24 08-Jul-24 Wall Rebar Installation

ENGR-STAIR-1-345 Wall Form work Installation 3 09-Jul-24 11-Jul-24 Wall Form work Installation

ENGR-STAIR-1-350 Wall and Stair Concrete casting 1 13-Jul-24 13-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-1-395 Form Removal and Curing 7 14-Jul-24 21-Jul-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 22-Jul-24 10-Aug-24 10-Aug-24, WALL AND 11TH FLIGHT
ENGR-STAIR-1-295 Stair Form work Installation 3 22-Jul-24 24-Jul-24 Stair Form work Installation

ENGR-STAIR-1-300 Wall Rebar Installation 3 25-Jul-24 28-Jul-24 Wall Rebar Installation

ENGR-STAIR-1-305 Wall Form work Installation 3 29-Jul-24 31-Jul-24 Wall Form work Installation

ENGR-STAIR-1-310 Wall and Stair Concrete casting 1 01-Aug-24 01-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-1-400 Form Removal and Curing 7 03-Aug-24 10-Aug-24 Form Removal and Curing

TOP SLAB 35 11-Aug-24 19-Sep-24 19-Sep-24, TOP SLAB


ENGR-STAIR-1-280 Slab Form work Installation 3 11-Aug-24 13-Aug-24 Slab Form work Installation

ENGR-STAIR-1-285 Slab Rebar Installation 3 14-Aug-24 17-Aug-24 Slab Rebar Installation

ENGR-STAIR-1-290 Wall and Stair Concrete casting 3 18-Aug-24 20-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-1-405 Form Removal and Curing 7 21-Aug-24 28-Aug-24 Form Removal and Curing

ENGR-STAIR-1-410 Waterproofing and Coating 19 29-Aug-24 19-Sep-24 Waterproofing and Coating

ENGR-STAIR-1-4195 Railing work 7 11-Sep-24 19-Sep-24 Railing work

EGRESS STAIR-2 (ZONE-2) 236 09-Jan-24 19-Oct-24 19-Oct-24, EGRESS STAIR-2 (ZONE-2)
WALL AND 1ST FLIGHT 31 09-Jan-24 13-Feb-24 13-Feb-24, WALL AND 1ST FLIGHT
ENGR-STAIR-2-100 Excavation for Foundation 6 09-Jan-24 15-Jan-24 Excavation for Foundation

ENGR-STAIR-2-105 Foundation Blinding Concrete casting 1 16-Jan-24 16-Jan-24 Foundation Blinding Concrete casting

ENGR-STAIR-2-110 Foundation Rebar Installation 3 17-Jan-24 20-Jan-24 Foundation Rebar Installation

ENGR-STAIR-2-115 Foundation Formwork installation 3 21-Jan-24 23-Jan-24 Foundation Formwork installation

ENGR-STAIR-2-120 Foundation Concrete casting 1 24-Jan-24 24-Jan-24 Foundation Concrete casting

ENGR-STAIR-2-125 Wall and Stair Rebar Installation 4 25-Jan-24 29-Jan-24 Wall and Stair Rebar Installation

ENGR-STAIR-2-130 Wall and Stair Form work Installation 6 30-Jan-24 05-Feb-24 Wall and Stair Form work Installation

ENGR-STAIR-2-135 Form Removal and Curing 7 06-Feb-24 13-Feb-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 14-Feb-24 04-Mar-24 04-Mar-24, WALL AND 2ND FLIGHT
ENGR-STAIR-2-140 Wall Rebar Installation 3 18-Feb-24 20-Feb-24 Wall Rebar Installation

ENGR-STAIR-2-145 Wall Form work Installation 3 21-Feb-24 24-Feb-24 Wall Form work Installation

ENGR-STAIR-2-150 Wall and Stair Concrete casting 1 25-Feb-24 25-Feb-24 Wall and Stair Concrete casting

ENGR-STAIR-2-300 Stair Form work Installation 3 14-Feb-24 17-Feb-24 Stair Form work Installation

ENGR-STAIR-2-375 Form Removal and Curing 7 26-Feb-24 04-Mar-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 05-Mar-24 24-Mar-24 24-Mar-24, WALL AND 3RD FLIGHT
ENGR-STAIR-2-170 Wall Rebar Installation 3 09-Mar-24 11-Mar-24 Wall Rebar Installation

ENGR-STAIR-2-175 Wall Form work Installation 3 12-Mar-24 14-Mar-24 Wall Form work Installation

ENGR-STAIR-2-180 Wall and Stair Concrete casting 1 16-Mar-24 16-Mar-24 Wall and Stair Concrete casting

ENGR-STAIR-2-305 Stair Form work Installation 3 05-Mar-24 07-Mar-24 Stair Form work Installation

ENGR-STAIR-2-370 Form Removal and Curing 7 17-Mar-24 24-Mar-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 25-Mar-24 16-Apr-24 16-Apr-24, WALL AND 4TH FLIGHT
ENGR-STAIR-2-155 Wall Rebar Installation 3 28-Mar-24 31-Mar-24 Wall Rebar Installation

ENGR-STAIR-2-160 Wall Form work Installation 3 01-Apr-24 03-Apr-24 Wall Form work Installation

ENGR-STAIR-2-165 Wall and Stair Concrete casting 1 04-Apr-24 04-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-2-310 Stair Form work Installation 3 25-Mar-24 27-Mar-24 Stair Form work Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
269 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-2-365 Form Removal and Curing 7 06-Apr-24 16-Apr-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 17-Apr-24 06-May-24 06-May-24, WALL AND 5TH FLIGHT
ENGR-STAIR-2-215 Wall Rebar Installation 3 21-Apr-24 23-Apr-24 Wall Rebar Installation

ENGR-STAIR-2-220 Wall Form work Installation 3 24-Apr-24 27-Apr-24 Wall Form work Installation

ENGR-STAIR-2-225 Wall and Stair Concrete casting 1 28-Apr-24 28-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-2-315 Stair Form work Installation 3 17-Apr-24 20-Apr-24 Stair Form work Installation

ENGR-STAIR-2-360 Form Removal and Curing 7 29-Apr-24 06-May-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 07-May-24 26-May-24 26-May-24, WALL AND 6TH FLIGHT
ENGR-STAIR-2-230 Wall Rebar Installation 3 11-May-24 13-May-24 Wall Rebar Installation

ENGR-STAIR-2-235 Wall Form work Installation 3 14-May-24 16-May-24 Wall Form work Installation

ENGR-STAIR-2-240 Wall and Stair Concrete casting 1 18-May-24 18-May-24 Wall and Stair Concrete casting

ENGR-STAIR-2-320 Stair Form work Installation 3 07-May-24 09-May-24 Stair Form work Installation

ENGR-STAIR-2-355 Form Removal and Curing 7 19-May-24 26-May-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 27-May-24 19-Jun-24 19-Jun-24, WALL AND 7TH FLIGHT
ENGR-STAIR-2-200 Wall Rebar Installation 3 30-May-24 02-Jun-24 Wall Rebar Installation

ENGR-STAIR-2-205 Wall Form work Installation 3 03-Jun-24 05-Jun-24 Wall Form work Installation

ENGR-STAIR-2-210 Wall and Stair Concrete casting 1 06-Jun-24 06-Jun-24 Wall and Stair Concrete casting

ENGR-STAIR-2-325 Stair Form work Installation 3 27-May-24 29-May-24 Stair Form work Installation

ENGR-STAIR-2-380 Form Removal and Curing 7 08-Jun-24 19-Jun-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 20-Jun-24 09-Jul-24 09-Jul-24, WALL AND 8TH FLIGHT
ENGR-STAIR-2-185 Wall Rebar Installation 3 24-Jun-24 26-Jun-24 Wall Rebar Installation

ENGR-STAIR-2-190 Wall Form work Installation 3 27-Jun-24 30-Jun-24 Wall Form work Installation

ENGR-STAIR-2-195 Wall and Stair Concrete casting 1 01-Jul-24 01-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-2-330 Stair Form work Installation 3 20-Jun-24 23-Jun-24 Stair Form work Installation

ENGR-STAIR-2-385 Form Removal and Curing 7 02-Jul-24 09-Jul-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 10-Jul-24 29-Jul-24 29-Jul-24, WALL AND 9TH FLIGHT
ENGR-STAIR-2-270 Wall Rebar Installation 3 14-Jul-24 16-Jul-24 Wall Rebar Installation

ENGR-STAIR-2-275 Wall Form work Installation 3 17-Jul-24 20-Jul-24 Wall Form work Installation

ENGR-STAIR-2-280 Wall and Stair Concrete casting 1 21-Jul-24 21-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-2-335 Stair Form work Installation 3 10-Jul-24 13-Jul-24 Stair Form work Installation

ENGR-STAIR-2-390 Form Removal and Curing 7 22-Jul-24 29-Jul-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 30-Jul-24 18-Aug-24 18-Aug-24, WALL AND 10TH FLIGHT
ENGR-STAIR-2-285 Wall Rebar Installation 3 03-Aug-24 05-Aug-24 Wall Rebar Installation

ENGR-STAIR-2-290 Wall Form work Installation 3 06-Aug-24 08-Aug-24 Wall Form work Installation

ENGR-STAIR-2-295 Wall and Stair Concrete casting 1 10-Aug-24 10-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-2-340 Stair Form work Installation 3 30-Jul-24 01-Aug-24 Stair Form work Installation

ENGR-STAIR-2-395 Form Removal and Curing 7 11-Aug-24 18-Aug-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 19-Aug-24 07-Sep-24 07-Sep-24, WALL AND 11TH FLIGHT
ENGR-STAIR-2-255 Wall Rebar Installation 3 22-Aug-24 25-Aug-24 Wall Rebar Installation

ENGR-STAIR-2-260 Wall Form work Installation 3 26-Aug-24 28-Aug-24 Wall Form work Installation

ENGR-STAIR-2-265 Wall and Stair Concrete casting 1 29-Aug-24 29-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-2-345 Stair Form work Installation 3 19-Aug-24 21-Aug-24 Stair Form work Installation

ENGR-STAIR-2-400 Form Removal and Curing 7 31-Aug-24 07-Sep-24 Form Removal and Curing

TOP SLAB 35 08-Sep-24 19-Oct-24 19-Oct-24, TOP SLAB


ENGR-STAIR-2-245 Slab Rebar Installation 3 11-Sep-24 14-Sep-24 Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
270 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-2-250 Wall and Stair Concrete casting 3 15-Sep-24 17-Sep-24 Wall and Stair Concrete casting

ENGR-STAIR-2-350 Slab Form work Installation 3 08-Sep-24 10-Sep-24 Slab Form work Installation

ENGR-STAIR-2-405 Form Removal and Curing 7 18-Sep-24 26-Sep-24 Form Removal and Curing

ENGR-STAIR-2-410 Waterproofing and Coating 19 28-Sep-24 19-Oct-24 Waterproofing and Coating

ENGR-STAIR-2-415 Railing work 7 10-Oct-24 19-Oct-24 Railing work

BACKFILLING UPTO TUNNELWALL 217 21-Dec-23 07-Sep-24 07-Sep-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z2-CON-BF.125 Backfilling & Compaction @ 0+500 ~ 0+600 20 21-Dec-23 13-Jan-24 Backfilling & Compaction @ 0+500 ~ 0+600

JAH-Z2-CON-BF.130 Backfilling & Compaction @ 0+600 ~ 0+700 20 14-Feb-24 07-Mar-24 Backfilling & Compaction @ 0+600 ~ 0+700

JAH-Z2-CON-BF.135 Backfilling & Compaction @ 0+700 ~ 0+800 20 26-May-24 22-Jun-24 Backfilling & Compaction @ 0+700 ~ 0+800

JAH-Z2-CON-BF.140 Backfilling & Compaction @ 0+800 ~ 0+900 20 29-Jul-24 20-Aug-24 Backfilling & Compaction @ 0+800 ~ 0+900

JAH-Z2-CON-BF.145 Backfilling & Compaction @ 0+900 ~ 0+994 20 15-Aug-24 07-Sep-24 Backfilling & Compaction @ 0+900 ~ 0+994

STRUCTURAL FILL 210 30-Apr-24 05-Jan-25 05-Jan-25, STRUCTURAL FILL


JAH-Z2-SF-IL.100 Backfilling & Compaction at Invert Level @ 0+500 ~ 0+600 20 30-Apr-24 22-May-24 Backfilling & Compaction at Invert Level @ 0+500 ~ 0+600

JAH-Z2-SF-IL.105 Backfilling & Compaction at Invert Level @ 0+600 ~ 0+700 20 03-Oct-24 27-Oct-24 Backfilling & Compaction at Invert Level @ 0+600 ~ 0+700

JAH-Z2-SF-IL.110 Backfilling & Compaction at Invert Level @ 0+700 ~ 0+800 20 27-Oct-24 19-Nov-24 Backfilling & Compaction at Invert Level @ 0+700 ~ 0+800

JAH-Z2-SF-IL.115 Backfilling & Compaction at Invert Level @ 0+800 ~ 0+900 20 19-Nov-24 12-Dec-24 Backfilling & Compaction at Invert Level @ 0+800 ~ 0+900

JAH-Z2-SF-IL.120 Backfilling & Compaction at Invert Level @ 0+900 ~ 0+994 20 12-Dec-24 05-Jan-25 Backfilling & Compaction at Invert Level @ 0+900 ~ 0+994

WET & DRY UTILITIES 371 02-Jan-24 18-Mar-25 18-Mar-25, WET & DRY UTILITIES
INSIDE WET CULVERT 122 28-Oct-24 18-Mar-25 18-Mar-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 59 09-Nov-24 15-Jan-25 15-Jan-25, POTABLE WATER NETWORK
JAH-Z2-IWU-PWN.100Pipe Supports Installation 25 09-Nov-24 07-Dec-24 Pipe Supports Installation

JAH-Z2-IWU-PWN.105Pipe Installation alongwith Valves, Fittings & Accessories 30 08-Dec-24 11-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-PWN.110Testing 4 12-Jan-25 15-Jan-25 Testing

GREY WATER DISTRIBUTION SYSTEM 49 08-Dec-24 02-Feb-25 02-Feb-25, GREY WATER DISTRIBUTION SYSTEM
JAH-Z2-IWU-GWD.240Pipe Supports Installation 20 08-Dec-24 30-Dec-24 Pipe Supports Installation

JAH-Z2-IWU-GWD.245Pipe Installation alongwith Valves, Fittings & Accessories 25 31-Dec-24 28-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-GWD.250Testing 4 29-Jan-25 02-Feb-25 Testing

IRRIGATION NETWORK 88 28-Oct-24 06-Feb-25 06-Feb-25, IRRIGATION NETWORK


JAH-Z2-IWU-IS.590 Pipe Supports Installation 20 28-Oct-24 19-Nov-24 Pipe Supports Installation

JAH-Z2-IWU-IS.595 Pipe Installation alongwith Valves, Fittings & Accessories 25 20-Nov-24 18-Dec-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-IS.600 Testing 4 03-Feb-25 06-Feb-25 Testing

CHILLED WATER SUPPLY NETWORK 59 31-Dec-24 09-Mar-25 09-Mar-25, CHILLED WATER SUPPLY NETWORK
JAH-Z2-IWU-CWS.130 Pipe Supports Installation 25 31-Dec-24 28-Jan-25 Pipe Supports Installation

JAH-Z2-IWU-CWS.135 Pipe Installation alongwith Valves, Fittings & Accessories 30 29-Jan-25 04-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-CWS.140 Testing 4 05-Mar-25 09-Mar-25 Testing

CHILLED WATER RETURN NETWORK 63 31-Dec-24 13-Mar-25 13-Mar-25, CHILLED WATER RETURN NETWORK
JAH-Z2-IWU-CWR.130Pipe Supports Installation 25 31-Dec-24 28-Jan-25 Pipe Supports Installation

JAH-Z2-IWU-CWR.135Pipe Installation alongwith Valves, Fittings & Accessories 30 29-Jan-25 04-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-CWR.140Testing 4 10-Mar-25 13-Mar-25 Testing

AUTOMATIC WASTE COLLECTION NETWORK 87 08-Dec-24 18-Mar-25 18-Mar-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z2-IWU-AWC.130Pipe Supports Installation 25 08-Dec-24 05-Jan-25 Pipe Supports Installation

JAH-Z2-IWU-AWC.135Pipe Installation alongwith Valves, Fittings & Accessories 30 06-Jan-25 09-Feb-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z2-IWU-AWC.140Testing 4 15-Mar-25 18-Mar-25 Testing

INSIDE DRY CULVERT 271 02-Jan-24 21-Nov-24 21-Nov-24, INSIDE DRY CULVERT
POWER 261 02-Jan-24 10-Nov-24 10-Nov-24, POWER
HIGH VOLTAGE 110 KV NETWORK 163 02-Jan-24 17-Jul-24 17-Jul-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z2-IDU-HV.120 HV Cable Supports Installation 12 02-Jan-24 15-Jan-24 HV Cable Supports Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
271 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-IDU-HV.125 Cable Installation with Fittings & Accessories 18 27-Jun-24 17-Jul-24 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 32 18-Jul-24 24-Aug-24 24-Aug-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z2-IDU-MV.120 MV Cable Supports Installation 12 18-Jul-24 31-Jul-24 MV Cable Supports Installation

JAH-Z2-IDU-MV.125 Cables Installation with Fittings & Accessories 20 01-Aug-24 24-Aug-24 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 32 25-Aug-24 01-Oct-24 01-Oct-24, LOW VOLTAGE NETWORK


JAH-Z2-IDU-LV.120 LV Cable Supports Installation 12 25-Aug-24 07-Sep-24 LV Cable Supports Installation

JAH-Z2-IDU-LV.125 Cable Laying with Fittings & Accessories 20 08-Sep-24 01-Oct-24 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 66 25-Aug-24 10-Nov-24 10-Nov-24, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z2-IDU-DS.180 Cable Tray Installation 10 25-Aug-24 04-Sep-24 Cable Tray Installation

JAH-Z2-IDU-DS.185 PVC Ducts Installation 5 05-Sep-24 10-Sep-24 PVC Ducts Installation

JAH-Z2-IDU-DS.190 Cable Installation 10 11-Sep-24 22-Sep-24 Cable Installation

JAH-Z2-IDU-DS.195 Isolators Installation 5 24-Sep-24 29-Sep-24 Isolators Installation

JAH-Z2-IDU-DS.200 Sub Main Distribution Boards Installation 8 30-Sep-24 08-Oct-24 Sub Main Distribution Boards Installation

JAH-Z2-IDU-DS.205 Motor Control Centres Installation 8 09-Oct-24 17-Oct-24 Motor Control Centres Installation

JAH-Z2-IDU-DS.210 Distribution Boards Installation 10 19-Oct-24 29-Oct-24 Distribution Boards Installation

JAH-Z2-IDU-DS.215 Wiring Accessories Installation 10 30-Oct-24 10-Nov-24 Wiring Accessories Installation

LIGHTING SYSTEM 35 05-Sep-24 16-Oct-24 16-Oct-24, LIGHTING SYSTEM


JAH-Z2--IDU-LS.280 Luminaires Installation 10 06-Oct-24 16-Oct-24 Luminaires Installation

JAH-Z2--IDU-LS.285 Cables Installation 10 05-Sep-24 16-Sep-24 Cables Installation

JAH-Z2-IDU-LS.270 Light Point Installation 15 17-Sep-24 05-Oct-24 Light Point Installation

TELECOM SERVICES 30 19-Oct-24 21-Nov-24 21-Nov-24, TELECOM SERVICES


JAH-Z2-IDU-TES.130 Mobily Lines 10 19-Oct-24 29-Oct-24 Mobily Lines

JAH-Z2-IDU-TES.135 STC Line 10 11-Nov-24 21-Nov-24 STC Line

JAH-Z2-IDU-TES.140 MOI Line 10 30-Oct-24 10-Nov-24 MOI Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 160 26-Oct-24 04-May-25 04-May-25, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 158 28-Oct-24 04-May-25 04-May-25, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 56 28-Oct-24 31-Dec-24 31-Dec-24, FIRE FIGHTING SYSTEM
JAH-Z2-MECH-FF.100 Pipe Installation work 20 28-Oct-24 19-Nov-24 Pipe Installation work

JAH-Z2-MECH-FF.105 Valves and Accessories Installation 8 20-Nov-24 28-Nov-24 Valves and Accessories Installation

JAH-Z2-MECH-FF.110 Sprinklers Installation 5 30-Nov-24 04-Dec-24 Sprinklers Installation

JAH-Z2-MECH-FF.115 Fire Extinguishers Installation 8 05-Dec-24 14-Dec-24 Fire Extinguishers Installation

JAH-Z2-MECH-FF.120 Foam Tank Installation 6 15-Dec-24 21-Dec-24 Foam Tank Installation

JAH-Z2-MECH-FF.125 Pipe Painting work 6 22-Dec-24 28-Dec-24 Pipe Painting work

JAH-Z2-MECH-FF.130 Testing work 3 29-Dec-24 31-Dec-24 Testing work

VENTILATION SYSTEM 23 01-Jan-25 27-Jan-25 27-Jan-25, VENTILATION SYSTEM


JAH-Z2-MECH-VS.100Staircase Pressurisation Fan Installation 5 01-Jan-25 06-Jan-25 Staircase Pressurisation Fan Installation

JAH-Z2-MECH-VS.105Extract fan installation 5 07-Jan-25 12-Jan-25 Extract fan installation

JAH-Z2-MECH-VS.110Unidirectional Jet fan 5 13-Jan-25 18-Jan-25 Unidirectional Jet fan

JAH-Z2-MECH-VS.115Reverse Jet fan 5 19-Jan-25 23-Jan-25 Reverse Jet fan

JAH-Z2-MECH-VS.120Testing work 3 25-Jan-25 27-Jan-25 Testing work

PUMPS INSTALLATION 15 28-Jan-25 13-Feb-25 13-Feb-25, PUMPS INSTALLATION


JAH-Z2-MECH-PI.115 Sump Pump Installation 7 28-Jan-25 04-Feb-25 Sump Pump Installation

JAH-Z2-MECH-PI.120 Pipe Connection work 6 05-Feb-25 11-Feb-25 Pipe Connection work

JAH-Z2-MECH-PI.125 Testing work 2 12-Feb-25 13-Feb-25 Testing work

DUCTING SYSTEM 66 12-Feb-25 04-May-25 04-May-25, DUCTING SYSTEM


JAH-Z2-MECH-DS.135Duct Installation work 28 12-Feb-25 16-Mar-25 Duct Installation work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
272 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-MECH-DS.140Grills Installation work 7 17-Mar-25 24-Mar-25 Grills Installation work

JAH-Z2-MECH-DS.145Diffusers Installation work 7 25-Mar-25 06-Apr-25 Diffusers Installation work

JAH-Z2-MECH-DS.150Non Returns Dampers 7 07-Apr-25 14-Apr-25 Non Returns Dampers

JAH-Z2-MECH-DS.155Fire and Smoke Damper 7 15-Apr-25 22-Apr-25 Fire and Smoke Damper

JAH-Z2-MECH-DS.160Sand Trap Louvre 5 23-Apr-25 28-Apr-25 Sand Trap Louvre

JAH-Z2-MECH-DS.165Testing work 5 29-Apr-25 04-May-25 Testing work

TUNNEL ELECTRICAL WORKS 159 26-Oct-24 03-May-25 03-May-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 101 30-Oct-24 24-Feb-25 24-Feb-25, CABLE TRAYS
JAH-Z2-ELC-CT160 600mm Cable Tray 21 30-Oct-24 23-Nov-24 600mm Cable Tray

JAH-Z2-ELC-CT165 400mm Cable Tray 14 24-Nov-24 09-Dec-24 400mm Cable Tray

JAH-Z2-ELC-CT170 300mm Cable Tray 10 10-Dec-24 21-Dec-24 300mm Cable Tray

JAH-Z2-ELC-CT175 200mm Cable Tray 8 22-Dec-24 30-Dec-24 200mm Cable Tray

JAH-Z2-ELC-CT180 150mm Cable Tray 8 31-Dec-24 08-Jan-25 150mm Cable Tray

JAH-Z2-ELC-CT185 100mm Cable Tray 6 09-Jan-25 15-Jan-25 100mm Cable Tray

JAH-Z2-ELC-CT190 75mm Cable Tray 5 16-Jan-25 21-Jan-25 75mm Cable Tray

JAH-Z2-ELC-CT195 150mm x 100mm Trunking 7 22-Jan-25 29-Jan-25 150mm x 100mm Trunking

JAH-Z2-ELC-CT200 100mm x 100mm Trunking 6 30-Jan-25 05-Feb-25 100mm x 100mm Trunking

JAH-Z2-ELC-CT205 100mm x 75mm Trunking 7 06-Feb-25 13-Feb-25 100mm x 75mm Trunking

JAH-Z2-ELC-CT210 PVC Ducts150mm dia 5 15-Feb-25 19-Feb-25 PVC Ducts150mm dia

JAH-Z2-ELC-CT215 PVC Ducts100mm dia 4 20-Feb-25 24-Feb-25 PVC Ducts100mm dia

POWER CABLES 148 30-Oct-24 24-Apr-25 24-Apr-25, POWER CABLES


JAH-Z2-ELC-PC.100 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 30-Oct-24 12-Nov-24 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z2-ELC-PC.105 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 30-Oct-24 24-Nov-24 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z2-ELC-PC.110 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 02-Nov-24 24-Nov-24 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z2-ELC-PC.115 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 28 25-Nov-24 26-Dec-24 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z2-ELC-PC.120 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 12-Dec-24 04-Jan-25 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z2-ELC-PC.125 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 17-Dec-24 04-Jan-25 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z2-ELC-PC.130 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 17-Dec-24 04-Jan-25 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z2-ELC-PC.135 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 11-Dec-24 26-Dec-24 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z2-ELC-PC.140 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 12-Dec-24 26-Dec-24 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z2-ELC-PC.145 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 05-Jan-25 16-Jan-25 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z2-ELC-PC.150 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 06-Jan-25 16-Jan-25 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z2-ELC-PC.155 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 18-Jan-25 25-Jan-25 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z2-ELC-PC.160 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 28 26-Jan-25 26-Feb-25 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z2-ELC-PC.165 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 26-Jan-25 25-Feb-25 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z2-ELC-PC.170 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 40 25-Feb-25 16-Apr-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

JAH-Z2-ELC-PC.175 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 25-Feb-25 26-Mar-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z2-ELC-PC.180 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 27-Feb-25 06-Mar-25 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z2-ELC-PC.185 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 08-Mar-25 15-Mar-25 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

JAH-Z2-ELC-PC.190 Testing work 7 17-Apr-25 24-Apr-25 Testing work

ELECTRICAL INSTALLATIONS 97 06-Jan-25 03-May-25 03-May-25, ELECTRICAL INSTALLATIONS


JAH-Z2-ELC-INS.100 Circuit Wiring Installation 15 06-Jan-25 22-Jan-25 Circuit Wiring Installation

JAH-Z2-ELC-INS.105 Wiring Accessories 15 23-Jan-25 09-Feb-25 Wiring Accessories

JAH-Z2-ELC-INS.110 Lighting Installation 14 10-Feb-25 25-Feb-25 Lighting Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
273 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-ELC-INS.115 Isolators Installation 12 26-Feb-25 11-Mar-25 Isolators Installation

JAH-Z2-ELC-INS.120 SMDB Installation 5 12-Mar-25 17-Mar-25 SMDB Installation

JAH-Z2-ELC-INS.125 Motor Control Centres Installation 5 18-Mar-25 23-Mar-25 Motor Control Centres Installation

JAH-Z2-ELC-INS.130 Distribution Boards 6 24-Mar-25 03-Apr-25 Distribution Boards

JAH-Z2-ELC-INS.135 Testing work 7 26-Apr-25 03-May-25 Testing work

LOW CURRENT 159 26-Oct-24 03-May-25 03-May-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 159 26-Oct-24 03-May-25 03-May-25, FIRE DETECTION AND ALARM SYSTEM
JAH-Z2-LOW-FDT.100Fibre-optic Sensing Cable Laying 12 26-Oct-24 07-Nov-24 Fibre-optic Sensing Cable Laying

JAH-Z2-LOW-FDT.105Fire Alarm Control Panel Installation 6 09-Nov-24 14-Nov-24 Fire Alarm Control Panel Installation

JAH-Z2-LOW-FDT.110Tamper switch Installation 4 16-Nov-24 19-Nov-24 Tamper switch Installation

JAH-Z2-LOW-FDT.115Zone Input units Installation 5 20-Nov-24 25-Nov-24 Zone Input units Installation

JAH-Z2-LOW-FDT.120Fire Alarm sounder Installation 4 26-Nov-24 30-Nov-24 Fire Alarm sounder Installation

JAH-Z2-LOW-FDT.125Fire Alarm Speaker Installation 6 01-Dec-24 07-Dec-24 Fire Alarm Speaker Installation

JAH-Z2-LOW-FDT.130Smoke Detector Installation 8 08-Dec-24 16-Dec-24 Smoke Detector Installation

JAH-Z2-LOW-FDT.135Heat Detector Installation 7 17-Dec-24 24-Dec-24 Heat Detector Installation

JAH-Z2-LOW-FDT.140Interface Module Installation 8 25-Dec-24 02-Jan-25 Interface Module Installation

JAH-Z2-LOW-FDT.145Double Action Manual Call Point Installation 7 04-Jan-25 11-Jan-25 Double Action Manual Call Point Installation

JAH-Z2-LOW-FDT.150Flashing Beacon Installation 5 12-Jan-25 16-Jan-25 Flashing Beacon Installation

JAH-Z2-LOW-FDT.155Testing work 5 28-Apr-25 03-May-25 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 28 09-Nov-24 10-Dec-24 10-Dec-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z2-LOW-PH.120 8 core UTP Cable Laying 7 09-Nov-24 16-Nov-24 8 core UTP Cable Laying

JAH-Z2-LOW-PH.125 Junction box Installation 7 17-Nov-24 24-Nov-24 Junction box Installation

JAH-Z2-LOW-PH.130 Emergency Telephone Installation 7 25-Nov-24 02-Dec-24 Emergency Telephone Installation

JAH-Z2-LOW-PH.135 Connection and Testing 7 03-Dec-24 10-Dec-24 Connection and Testing

PUBLIC ADDRESS 28 09-Nov-24 10-Dec-24 10-Dec-24, PUBLIC ADDRESS


JAH-Z2-LOW-PA.118 Cables laying public address system 7 09-Nov-24 16-Nov-24 Cables laying public address system

JAH-Z2-LOW-PA.120 Wall-mounted Voice Evacuation Horn Speaker Installation 7 17-Nov-24 24-Nov-24 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z2-LOW-PA.125 Voice alarm control panel Installation 7 25-Nov-24 02-Dec-24 Voice alarm control panel Installation

JAH-Z2-LOW-PA.135 Connection and Testing 7 03-Dec-24 10-Dec-24 Connection and Testing

VIDEO SURVEILLANCE 49 17-Nov-24 12-Jan-25 12-Jan-25, VIDEO SURVEILLANCE


JAH-Z2-LOW-VDS.135Single Core Fibre Optical Cable Laying 7 17-Nov-24 24-Nov-24 Single Core Fibre Optical Cable Laying

JAH-Z2-LOW-VDS.140RTU Panel Installation 7 25-Nov-24 02-Dec-24 RTU Panel Installation

JAH-Z2-LOW-VDS.145Overhead Vehicle Detector Installation 7 03-Dec-24 10-Dec-24 Overhead Vehicle Detector Installation

JAH-Z2-LOW-VDS.150Door Contact Installation 7 11-Dec-24 18-Dec-24 Door Contact Installation

JAH-Z2-LOW-VDS.155PTZ Camera mounted on Pole Installation 7 19-Dec-24 26-Dec-24 PTZ Camera mounted on Pole Installation

JAH-Z2-LOW-VDS.160Fixed (AID) Camera Installation 7 28-Dec-24 04-Jan-25 Fixed (AID) Camera Installation

JAH-Z2-LOW-VDS.165Testing work 7 05-Jan-25 12-Jan-25 Testing work

SACADA SYSTEM 35 13-Jan-25 22-Feb-25 22-Feb-25, SACADA SYSTEM


JAH-Z2-LOW-SCA.125Cabling Laying 7 13-Jan-25 20-Jan-25 Cabling Laying

JAH-Z2-LOW-SCA.130Remote Terminal Unit Installation 7 21-Jan-25 28-Jan-25 Remote Terminal Unit Installation

JAH-Z2-LOW-SCA.135Programmable Logic Control Unit Installation 7 29-Jan-25 05-Feb-25 Programmable Logic Control Unit Installation

JAH-Z2-LOW-SCA.140SCADA/ PC/ Soft ware/ Printers Installation 7 06-Feb-25 13-Feb-25 SCADA/ PC/ Soft ware/ Printers Installation

JAH-Z2-LOW-SCA.145Testing work 7 15-Feb-25 22-Feb-25 Testing work

RADIO RE-BROADCASTING SYSTEM 28 23-Feb-25 26-Mar-25 26-Mar-25, RADIO RE-BROADCASTING SYSTEM


JAH-Z2-LOW-RDO.120Leaky Feeder Cable Laying 7 23-Feb-25 02-Mar-25 Leaky Feeder Cable Laying

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
274 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z2-LOW-RDO.125Inline Bidirectional Signal Amplifier Installation 7 03-Mar-25 10-Mar-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z2-LOW-RDO.130End of Line Terminator 7 11-Mar-25 18-Mar-25 End of Line Terminator

JAH-Z2-LOW-RDO.135Connection and Testing 7 19-Mar-25 26-Mar-25 Connection and Testing

TUNNEL PLUMBING WORKS 35 20-Nov-24 30-Dec-24 30-Dec-24, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 20-Nov-24 30-Dec-24 30-Dec-24, DRAINAGE SYSTEM
JAH-Z2-PLB-DS.110 Drainage Pipes Installation Incl. Fittings & Accessories 15 20-Nov-24 07-Dec-24 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z2-PLB-DS.115 Collection Chambers 20 08-Dec-24 30-Dec-24 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 27-Mar-25 19-May-25 19-May-25, TUNNEL INTERNAL ROAD WORK
JAH-Z2-TIRW.370 Kerbs, Channels & Edging 7 27-Mar-25 08-Apr-25 Kerbs, Channels & Edging

JAH-Z2-TIRW.375 Tack Coat Application (MC-1) 10 09-Apr-25 20-Apr-25 Tack Coat Application (MC-1)

JAH-Z2-TIRW.380 Bituminious Base Course Layer 10 09-Apr-25 20-Apr-25 Bituminious Base Course Layer

JAH-Z2-TIRW.385 Tack Coat Application (RC-2) 12 21-Apr-25 04-May-25 Tack Coat Application (RC-2)

JAH-Z2-TIRW.390 Asphalt Wearing Course Layer 12 21-Apr-25 04-May-25 Asphalt Wearing Course Layer

JAH-Z2-TIRW.395 Pavement Line Marking 5 05-May-25 10-May-25 Pavement Line Marking

JAH-Z2-TIRW.400 Traffic Signboards Installation 8 11-May-25 19-May-25 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 35 05-May-25 17-Jun-25 17-Jun-25, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z2-TDW.100 Fire Protection Board Installation 10 05-May-25 15-May-25 Fire Protection Board Installation

JAH-Z2-TDW.105 GRC Panel Board Installation 25 17-May-25 17-Jun-25 GRC Panel Board Installation

ZONE 3 - FROM STA. 0+994 ~ 1+268 1121 27-Jun-22 A 23-Feb-26 23-Feb-26, ZONE 3 - FROM STA. 0+994 ~ 1+268
ENGINEERING 403 27-Jun-22 A 21-Oct-23 21-Oct-23, ENGINEERING
RAM150 Completion Engineering Work For Zone3 0 21-Oct-23* Completion Engineering Work For Zone3

SITE SURVEY 119 27-Jun-22 A 22-Aug-22 A 22-Aug-22 A, SITE SURVEY


JAH-Z3-ENG-SS.100 Site Survey/Settingout Control Points 2 27-Jun-22 A 14-Aug-22 A Site Survey/Settingout Control Points

JAH-Z3-ENG-SS.105 Review and Approval of Site Survey & Control Points 12 29-Jun-22 A 22-Aug-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 168 28-Aug-22 A 14-Feb-23 14-Feb-23, SHOP DRAWINGS


CIVIL/STRUCTURAL 0+994 ~1+094 50 29-Oct-22 25-Dec-22 25-Dec-22, CIVIL/STRUCTURAL 0+994 ~1+094
JAH-Z3-ENG-CS.300 Plan and Profile Shop Drawings Preparation & Submission 6 29-Oct-22 03-Nov-22 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.305 Plan and Profile Shop Drawings Review & Approval 12 05-Nov-22 17-Nov-22 Plan and Profile Shop Drawings Review & Approval

JAH-Z3-ENG-CS.310 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 19-Nov-22 24-Nov-22 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.315 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 26-Nov-22 08-Dec-22 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z3-ENG-CS.320 Tunnel Structural Shop Drawings Submission 6 26-Nov-22 01-Dec-22 Tunnel Structural Shop Drawings Submission

JAH-Z3-ENG-CS.325 Tunnel Structural Shop Drawings Review & Approval 12 12-Dec-22 25-Dec-22 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL1+094 ~1+194 102 28-Aug-22 A 05-Jan-23 05-Jan-23, CIVIL/STRUCTURAL1+094 ~1+194


JAH-Z3-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 10-Dec-22 15-Dec-22 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 17-Dec-22 29-Dec-22 Plan and Profile Shop Drawings Review & Approval

JAH-Z3-ENG-CS.360 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 28-Aug-22 A 01-Jan-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.365 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 07-Sep-22 A 03-Jan-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z3-ENG-CS.370 Tunnel Structural Shop Drawings Submission 6 05-Sep-22 A 03-Jan-23 Tunnel Structural Shop Drawings Submission

JAH-Z3-ENG-CS.375 Tunnel Structural Shop Drawings Review & Approval 12 14-Sep-22 A 05-Jan-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+194 ~1+268 110 01-Sep-22 A 14-Feb-23 14-Feb-23, CIVIL/STRUCTURAL 1+194 ~1+268
JAH-Z3-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 04-Jan-23 10-Jan-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 11-Jan-23 24-Jan-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z3-ENG-CS.410 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 01-Sep-22 A 08-Sep-22 A Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z3-ENG-CS.415 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 08-Sep-22 A 21-Sep-22 A Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z3-ENG-CS.420 Tunnel Structural Shop Drawings Submission 6 25-Jan-23 31-Jan-23 Tunnel Structural Shop Drawings Submission

JAH-Z3-ENG-CS.425 Tunnel Structural Shop Drawings Review & Approval 12 01-Feb-23 14-Feb-23 Tunnel Structural Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
275 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ARCHITECTURAL 22 19-Nov-22 13-Dec-22 13-Dec-22, ARCHITECTURAL
JAH-Z3-ENG-AR.100 Tunnel Architectural Shop Drawings Preparation & Submission 10 19-Nov-22 29-Nov-22 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z3-ENG-AR.105 Tunnel Architectural Shop Drawings Review & Approval 12 30-Nov-22 13-Dec-22 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 117 30-Nov-22 15-Apr-23 15-Apr-23, UTILITIES


WET UTILITIES 117 30-Nov-22 15-Apr-23 15-Apr-23, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 22 30-Nov-22 25-Dec-22 25-Dec-22, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
JAH-Z3-EN-WU-PW.100Shop Drawings Preparation & Submission 10 30-Nov-22 11-Dec-22 Shop Drawings Preparation & Submission

JAH-Z3-EN-WU-PW.105Shop Drawings Review & Approval 12 12-Dec-22 25-Dec-22 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 25 26-Dec-22 23-Jan-23 23-Jan-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z3-EN-WU-GW.100
Shop Drawings Preparation & Submission 13 26-Dec-22 09-Jan-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-WU-GW.105
Shop Drawings Review & Approval 12 10-Jan-23 23-Jan-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 22 24-Jan-23 18-Feb-23 18-Feb-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z3-EN-WU-IRR.100
Shop Drawings Preparation & Submission 10 24-Jan-23 04-Feb-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-WU-IRR.105
Shop Drawings Review & Approval 12 05-Feb-23 18-Feb-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 21 19-Feb-23 14-Mar-23 14-Mar-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z3-EN-WU-CWS.100
Shop Drawings Preparation & Submission 9 19-Feb-23 28-Feb-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-WU-CWS.105
Shop Drawings Review & Approval 12 01-Mar-23 14-Mar-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 27 15-Mar-23 15-Apr-23 15-Apr-23, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z3-EN-WU-AUW.140
Shop Drawings Preparation & Submission 15 15-Mar-23 01-Apr-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-WU-AUW.145
Shop Drawings Review & Approval 12 02-Apr-23 15-Apr-23 Shop Drawings Review & Approval

DRY UTILITIES 95 26-Dec-22 15-Apr-23 15-Apr-23, DRY UTILITIES


POWER 73 26-Dec-22 20-Mar-23 20-Mar-23, POWER
HIGH VOLTAGE 110 KV NETWORK 22 24-Jan-23 18-Feb-23 18-Feb-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z3-EN-DU-PWR.240
Shop Drawings Preparation & Submission 10 24-Jan-23 04-Feb-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-PWR.245
Shop Drawings Review & Approval 12 05-Feb-23 18-Feb-23 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 22 19-Feb-23 15-Mar-23 15-Mar-23, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z3-EN-DU-PWR.250
Shop Drawings Preparation & Submission 10 19-Feb-23 01-Mar-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-PWR.255
Shop Drawings Review & Approval 12 02-Mar-23 15-Mar-23 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 25 26-Dec-22 23-Jan-23 23-Jan-23, LOW VOLTAGE NETWORK


JAH-Z3-EN-DU-PWR.260
Shop Drawings Preparation & Submission 13 26-Dec-22 09-Jan-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-PWR.265
Shop Drawings Review & Approval 12 10-Jan-23 23-Jan-23 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 21 24-Jan-23 16-Feb-23 16-Feb-23, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z3-EN-DU-PWR.270
Shop Drawings Preparation & Submission 9 24-Jan-23 02-Feb-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-PWR.275
Shop Drawings Review & Approval 12 04-Feb-23 16-Feb-23 Shop Drawings Review & Approval

LIGHTING SYSTEM 27 18-Feb-23 20-Mar-23 20-Mar-23, LIGHTING SYSTEM


JAH-Z3-EN-DU-PWR.280
Shop Drawings Preparation & Submission 15 18-Feb-23 06-Mar-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-PWR.285
Shop Drawings Review & Approval 12 07-Mar-23 20-Mar-23 Shop Drawings Review & Approval

LOW CURRENT 22 21-Mar-23 15-Apr-23 15-Apr-23, LOW CURRENT


TELECOM SERVICES 22 21-Mar-23 15-Apr-23 15-Apr-23, TELECOM SERVICES
JAH-Z3-EN-DU-LC.150Shop Drawings Preparation & Submission 10 21-Mar-23 01-Apr-23 Shop Drawings Preparation & Submission

JAH-Z3-EN-DU-LC.155Shop Drawings Review & Approval 12 02-Apr-23 15-Apr-23 Shop Drawings Review & Approval

MEP 272 30-Nov-22 21-Oct-23 21-Oct-23, MEP


TUNNEL MECHANICAL WORKS 176 30-Nov-22 26-Jun-23 26-Jun-23, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 30-Nov-22 12-Mar-23 12-Mar-23, FIRE FIGHTING SYSTEM
JAH-Z3-ENG-FF.180 Fire Fighting Pipe Layout Plan Preparation & Submission 10 30-Nov-22 11-Dec-22 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z3-ENG-FF.185 Fire Fighting Pipe Layout Plan Review & Approval 12 12-Dec-22 25-Dec-22 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z3-ENG-FF.190 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 26-Dec-22 05-Jan-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z3-ENG-FF.195 Fire Fighting Sprinkler Layout Plan Review & Approval 12 07-Jan-23 19-Jan-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z3-ENG-FF.200 Foam Tank Installation Layout Preparation & Submission 10 21-Jan-23 31-Jan-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z3-ENG-FF.205 Foam Tank Installation Layout Review & Approval 12 01-Feb-23 14-Feb-23 Foam Tank Installation Layout Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
276 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ENG-FF.210 Fire Extinguishers Layout Plan Preparation & Submission 10 15-Feb-23 26-Feb-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z3-ENG-FF.215 Fire Extinguishers Layout Plan Review & Approval 12 27-Feb-23 12-Mar-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 27-Feb-23 18-Apr-23 18-Apr-23, VENTILATION SYSTEM


JAH-Z3-ENG-VS.140 Fan Layout Preparation & Submission 10 27-Feb-23 09-Mar-23 Fan Layout Preparation & Submission

JAH-Z3-ENG-VS.145 Fan Layout Review & Approval 12 11-Mar-23 23-Mar-23 Fan Layout Review & Approval

JAH-Z3-ENG-VS.150 Cable Route Shop Drawing Preparation & Submission 10 25-Mar-23 04-Apr-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z3-ENG-VS.155 Cable Route Shop Drawing Review & Approval 12 05-Apr-23 18-Apr-23 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 19-Apr-23 17-May-23 17-May-23, PUMPS INSTALLATION


JAH-Z3-ENG-PI.120 Sump Pump Diagram Preparation & Submission 10 19-Apr-23 03-May-23 Sump Pump Diagram Preparation & Submission

JAH-Z3-ENG-PI.125 Sump Pump Diagram Review & Approval 12 04-May-23 17-May-23 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 13-Mar-23 26-Jun-23 26-Jun-23, DUCTING SYSTEM


JAH-Z3-ENG-DCS.180 Duct Layout Drawing Preparation & Submission 10 13-Mar-23 23-Mar-23 Duct Layout Drawing Preparation & Submission

JAH-Z3-ENG-DCS.185 Duct Layout Drawing Review & Approval 12 25-Mar-23 06-Apr-23 Duct Layout Drawing Review & Approval

JAH-Z3-ENG-DCS.190 Diffuser Details Review & Approval 12 19-Apr-23 06-May-23 Diffuser Details Review & Approval

JAH-Z3-ENG-DCS.195 Dampers Details Preparation & Submission 10 07-May-23 17-May-23 Dampers Details Preparation & Submission

JAH-Z3-ENG-DCS.200 Dampers Details Review & Approval 12 18-May-23 31-May-23 Dampers Details Review & Approval

JAH-Z3-ENG-DCS.205 Sand Trap Louvre Layout Drawing Preparation & Submission 10 01-Jun-23 12-Jun-23 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z3-ENG-DCS.210 Sand Trap Louvre Layout Drawing Review & Approval 12 13-Jun-23 26-Jun-23 Sand Trap Louvre Layout Drawing Review & Approval

JAH-Z3-ENG-DCS.215 Diffuser Details Drawing Preparation & Submission 10 08-Apr-23 18-Apr-23 Diffuser Details Drawing Preparation & Submission

TUNNEL ELECTRICAL WORKS 184 13-Mar-23 21-Oct-23 21-Oct-23, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 25-Mar-23 06-Aug-23 06-Aug-23, CABLE TRAYS
JAH-Z3-ENG-CTR.200 Cable Tray Layout Drawing Preparation & Submission 10 25-Mar-23 04-Apr-23 Cable Tray Layout Drawing Preparation & Submission

JAH-Z3-ENG-CTR.205 Cable Tray Layout Drawing Review & Approval 12 05-Apr-23 18-Apr-23 Cable Tray Layout Drawing Review & Approval

JAH-Z3-ENG-CTR.210 Cable Tray Diversion Details Preparation & Submission 10 19-Apr-23 03-May-23 Cable Tray Diversion Details Preparation & Submission

JAH-Z3-ENG-CTR.215 Cable Tray Diversion Details Review & Approval 12 04-May-23 17-May-23 Cable Tray Diversion Details Review & Approval

JAH-Z3-ENG-CTR.220 Cable Tray Fixing Details Preparation & Submission 10 18-May-23 29-May-23 Cable Tray Fixing Details Preparation & Submission

JAH-Z3-ENG-CTR.225 Cable Tray Fixing Details Review & Submission 12 30-May-23 12-Jun-23 Cable Tray Fixing Details Review & Submission

JAH-Z3-ENG-CTR.230 Cable Tray Sections Preparation & Submission 10 13-Jun-23 24-Jun-23 Cable Tray Sections Preparation & Submission

JAH-Z3-ENG-CTR.235 Cable Tray Sections Review & Approval 12 25-Jun-23 11-Jul-23 Cable Tray Sections Review & Approval

JAH-Z3-ENG-CTR.240 PVC DuctsSections Preparation & Submission 10 12-Jul-23 23-Jul-23 PVC DuctsSections Preparation & Submission

JAH-Z3-ENG-CTR.245 PVC Sections Review & Approval 12 24-Jul-23 06-Aug-23 PVC Sections Review & Approval

POWER CABLES 44 30-May-23 23-Jul-23 23-Jul-23, POWER CABLES


JAH-Z3-ENG-PC.140 Cable Route Shop Drawing Preparation & Submission 10 30-May-23 10-Jun-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z3-ENG-PC.145 Cable Route Shop Drawing Review & Approval 12 11-Jun-23 24-Jun-23 Cable Route Shop Drawing Review & Approval

JAH-Z3-ENG-PC.150 Junction Box Layout Plan Preparation & Submission 10 25-Jun-23 09-Jul-23 Junction Box Layout Plan Preparation & Submission

JAH-Z3-ENG-PC.155 Junction Box Layout Plan Review & Approval 12 10-Jul-23 23-Jul-23 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 11-Jun-23 21-Oct-23 21-Oct-23, ELECTRICAL INSTALLATIONS


JAH-Z3-ENG-ELI.200 Wiring Accessories Diagram Preparation & Submission 10 11-Jun-23 21-Jun-23 Wiring Accessories Diagram Preparation & Submission

JAH-Z3-ENG-ELI.205 Lighting Layout Drawing Preparation & Submission 10 10-Jul-23 20-Jul-23 Lighting Layout Drawing Preparation & Submission

JAH-Z3-ENG-ELI.210 Circuit Wiring Diagram Preparation & Submission 10 05-Aug-23 15-Aug-23 Circuit Wiring Diagram Preparation & Submission

JAH-Z3-ENG-ELI.215 Circuit Wiring Diagram Review & Approval 12 16-Aug-23 29-Aug-23 Circuit Wiring Diagram Review & Approval

JAH-Z3-ENG-ELI.220 SMDB Line Diagram Preparation & Submission 10 30-Aug-23 10-Sep-23 SMDB Line Diagram Preparation & Submission

JAH-Z3-ENG-ELI.225 SMDB Line Diagram Review & Approval 12 11-Sep-23 25-Sep-23 SMDB Line Diagram Review & Approval

JAH-Z3-ENG-ELI.230 Distribution Board Line Diagram Preparation & Submission 10 26-Sep-23 07-Oct-23 Distribution Board Line Diagram Preparation & Submission

JAH-Z3-ENG-ELI.235 Lighting Layout Drawing Review & Approval 12 22-Jul-23 03-Aug-23 Lighting Layout Drawing Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
277 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ENG-ELI.240 Wiring Accessories Diagram Review & Approval 12 22-Jun-23 09-Jul-23 Wiring Accessories Diagram Review & Approval

JAH-Z3-ENG-ELI.245 Distribution Board Line Diagram Review & Approval 12 08-Oct-23 21-Oct-23 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 13-Mar-23 20-Aug-23 20-Aug-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 13-Mar-23 20-Aug-23 20-Aug-23, FIRE DETECTION AND ALARM SYSTEM
JAH-Z3-ENG-FD.220 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 13-Mar-23 23-Mar-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.225 Fire Alarm Control Panel Layout Drawing Review & Approval 12 25-Mar-23 06-Apr-23 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z3-ENG-FD.230 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 08-Apr-23 18-Apr-23 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.235 Fire Alarm Speaker Layout Drawing Review & Approval 12 19-Apr-23 06-May-23 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z3-ENG-FD.240 Fire Alarm sounder Layout Drawing Preparation & Submission 10 07-May-23 17-May-23 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.245 Fire Alarm sounder Layout Drawing Review & Approval 12 18-May-23 31-May-23 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z3-ENG-FD.250 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 01-Jun-23 12-Jun-23 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.255 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 13-Jun-23 26-Jun-23 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z3-ENG-FD.260 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 01-Jul-23 11-Jul-23 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.265 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 12-Jul-23 25-Jul-23 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z3-ENG-FD.270 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 26-Jul-23 06-Aug-23 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z3-ENG-FD.275 Double Action Manual Call Point Layout Drawing Review & Approval 12 07-Aug-23 20-Aug-23 Double Action Manual Call Point Layout Drawing Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 25-Mar-23 06-Aug-23 06-Aug-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z3-ENG-TPH.2008 core UTP Cable Laying 14 25-Mar-23 09-Apr-23 8 core UTP Cable Laying

JAH-Z3-ENG-TPH.205Junction box Installation 8 10-Apr-23 18-Apr-23 Junction box Installation

JAH-Z3-ENG-TPH.210Emergency Telephone Installation 14 19-Apr-23 08-May-23 Emergency Telephone Installation

JAH-Z3-ENG-TPH.215Connection and Testing 8 09-May-23 17-May-23 Connection and Testing

JAH-Z3-ENG-TPH.2208 Core UTP Cable Layout Drawing Preparation & Submission 10 18-May-23 29-May-23 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-TPH.2258 Core UTP Cable Layout Drawing Review & Approval 12 30-May-23 12-Jun-23 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z3-ENG-TPH.230Junction box Layout Drawing Preparation & Submission 10 13-Jun-23 24-Jun-23 Junction box Layout Drawing Preparation & Submission

JAH-Z3-ENG-TPH.235Junction box Layout Drawing Review & Approval 12 25-Jun-23 11-Jul-23 Junction box Layout Drawing Review & Approval

JAH-Z3-ENG-TPH.240Telephone Location Layout Preparation & Submission 10 12-Jul-23 23-Jul-23 Telephone Location Layout Preparation & Submission

JAH-Z3-ENG-TPH.245Telephone Location Layout Review & Approval 12 24-Jul-23 06-Aug-23 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 10-Apr-23 02-Jul-23 02-Jul-23, PUBLIC ADDRESS


JAH-Z3-ENG-PUBA.160
Cable Layout Drawing Preparation & Submission 10 10-Apr-23 20-Apr-23 Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-PUBA.165
Cable Layout Drawing Review & Approval 12 25-Apr-23 08-May-23 Cable Layout Drawing Review & Approval

JAH-Z3-ENG-PUBA.170
Voice alarm control panel Drawing Preparation & Submission 10 09-May-23 20-May-23 Voice alarm control panel Drawing Preparation & Submission

JAH-Z3-ENG-PUBA.175
Voice alarm control panel Drawing Review & Approval 12 21-May-23 03-Jun-23 Voice alarm control panel Drawing Review & Approval

JAH-Z3-ENG-PUBA.180
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 04-Jun-23 14-Jun-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z3-ENG-PUBA.185
Voice Evacuation Horn Speaker Drawing Review & Approval 12 15-Jun-23 02-Jul-23 Voice Evacuation Horn Speaker Drawing Review & Approval

VIDEO SURVEILLANCE 44 25-Apr-23 14-Jun-23 14-Jun-23, VIDEO SURVEILLANCE


JAH-Z3-ENG-VID.140Cable Layout Drawing Preparation & Submission 10 25-Apr-23 06-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-VID.145Cable Layout Drawing Review & Approval 12 07-May-23 20-May-23 Cable Layout Drawing Review & Approval

JAH-Z3-ENG-VID.150Camera Layout Drawing Preparation & Submission 10 21-May-23 31-May-23 Camera Layout Drawing Preparation & Submission

JAH-Z3-ENG-VID.155Camera Layout Drawing Review & Approval 12 01-Jun-23 14-Jun-23 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 07-May-23 26-Jun-23 26-Jun-23, SACADA SYSTEM


JAH-Z3-ENG-SCA.140Cable Layout Drawing Preparation & Submission 10 07-May-23 17-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-SCA.145Cable Layout Drawing Review & Approval 12 18-May-23 31-May-23 Cable Layout Drawing Review & Approval

JAH-Z3-ENG-SCA.150Installation Layout Drawing Preparation & Submission 10 01-Jun-23 12-Jun-23 Installation Layout Drawing Preparation & Submission

JAH-Z3-ENG-SCA.155Installation Layout Drawing Review & Approval 12 13-Jun-23 26-Jun-23 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 18-May-23 11-Jul-23 11-Jul-23, RADIO RE-BROADCASTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
278 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ENG-RDO.140Cable Layout Drawing Preparation & Submission 10 18-May-23 29-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z3-ENG-RDO.145Cable Layout Drawing Review & Approval 12 30-May-23 12-Jun-23 Cable Layout Drawing Review & Approval

JAH-Z3-ENG-RDO.150Installation Layout Drawing Preparation & Submission 10 13-Jun-23 24-Jun-23 Installation Layout Drawing Preparation & Submission

JAH-Z3-ENG-RDO.155Installation Layout Drawing Review & Approval 12 25-Jun-23 11-Jul-23 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 30-May-23 22-Jun-23 22-Jun-23, TUNNEL PLUMBING WORKS


JAH-Z3-ENG-PLM.120 Plumbing Services Shop Drawings Preparation & Submission 9 30-May-23 08-Jun-23 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z3-ENG-PLM.125 Plumbing Shop Drawings Review & Approval 12 10-Jun-23 22-Jun-23 Plumbing Shop Drawings Review & Approval

PROCUREMENT 418 05-Nov-22 13-Mar-24 13-Mar-24, PROCUREMENT


RAM285 Completion Procurment for Zone 3 0 13-Mar-24* Completion Procurment for Zone 3

CIVIL/STRUCTURAL 78 05-Nov-22 02-Feb-23 02-Feb-23, CIVIL/STRUCTURAL


JAH-Z3-PRO-CSM.140 Request for Quotation 10 05-Nov-22 15-Nov-22 Request for Quotation

JAH-Z3-PRO-CSM.145 Issue Purchase Order 8 16-Nov-22 24-Nov-22 Issue Purchase Order

JAH-Z3-PRO-CSM.147 Staging Time 15 26-Nov-22 12-Dec-22 Staging Time

JAH-Z3-PRO-CSM.150 Material Delivery 45 13-Dec-22 02-Feb-23 Material Delivery

UTILITIES 345 29-Jan-23 13-Mar-24 13-Mar-24, UTILITIES


WET UTILITIES 345 29-Jan-23 13-Mar-24 13-Mar-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 235 29-Jan-23 06-Nov-23 06-Nov-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 29-Jan-23 23-Jul-23 23-Jul-23, DI PIPES
JAH-Z3-PR-WU--PW.415
Issue Purchase Order 15 09-Feb-23 26-Feb-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.420
Staging time 30 27-Feb-23 02-Apr-23 Staging time

JAH-Z3-PR-WU--PW.425
Material Delivery 90 03-Apr-23 23-Jul-23 Material Delivery

JAH-Z3-PR-WU--PW.590
Request for Quotation 10 29-Jan-23 08-Feb-23 Request for Quotation

HDPE PIPES 145 26-Mar-23 17-Sep-23 17-Sep-23, HDPE PIPES


JAH-Z3-PR-WU--PW.430
Issue Purchase Order 15 06-Apr-23 26-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.435
Staging time 30 27-Apr-23 31-May-23 Staging time

JAH-Z3-PR-WU--PW.440
Material Delivery 90 01-Jun-23 17-Sep-23 Material Delivery

JAH-Z3-PR-WU--PW.585
Request for Quotation 10 26-Mar-23 05-Apr-23 Request for Quotation

GRP PIPES 145 02-Mar-23 24-Aug-23 24-Aug-23, GRP PIPES


JAH-Z3-PR-WU--PW.445
Issue Purchase Order 15 14-Mar-23 30-Mar-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.450
Staging time 30 01-Apr-23 08-May-23 Staging time

JAH-Z3-PR-WU--PW.455
Material Delivery 90 09-May-23 24-Aug-23 Material Delivery

JAH-Z3-PR-WU--PW.580
Request for Quotation 10 02-Mar-23 13-Mar-23 Request for Quotation

DI & GRP FITTING 145 28-Mar-23 19-Sep-23 19-Sep-23, DI & GRP FITTING
JAH-Z3-PR-WU--PW.460
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.465
Staging time 30 30-Apr-23 03-Jun-23 Staging time

JAH-Z3-PR-WU--PW.470
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-WU--PW.575
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

GATE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, GATE VALVE


JAH-Z3-PR-WU--PW.475
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.480
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU--PW.485
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

JAH-Z3-PR-WU--PW.570
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

BUTTERFLAY VALVE 145 17-May-23 06-Nov-23 06-Nov-23, BUTTERFLAY VALVE


JAH-Z3-PR-WU--PW.490
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.495
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU--PW.500
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

JAH-Z3-PR-WU--PW.565
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
279 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WATER METER 145 28-Mar-23 19-Sep-23 19-Sep-23, WATER METER
JAH-Z3-PR-WU--PW.505
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.510
Staging time 30 30-Apr-23 03-Jun-23 Staging time

JAH-Z3-PR-WU--PW.515
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-WU--PW.560
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

AIR RELASE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, AIR RELASE VALVE
JAH-Z3-PR-WU--PW.520
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.525
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU--PW.530
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

JAH-Z3-PR-WU--PW.555
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

WASHOUT VALVE 145 17-May-23 06-Nov-23 06-Nov-23, WASHOUT VALVE


JAH-Z3-PR-WU--PW.535
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU--PW.540
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU--PW.545
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

JAH-Z3-PR-WU--PW.550
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 235 29-Jan-23 06-Nov-23 06-Nov-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 29-Jan-23 23-Jul-23 23-Jul-23, DI PIPES
JAH-Z3-PR-WU-GW.100
Request for Quotation 10 29-Jan-23 08-Feb-23 Request for Quotation

JAH-Z3-PR-WU-GW.105
Issue Purchase Order 15 09-Feb-23 26-Feb-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.110
Staging time 30 27-Feb-23 02-Apr-23 Staging time

JAH-Z3-PR-WU-GW.135
Material Delivery 90 03-Apr-23 23-Jul-23 Material Delivery

HDPE PIPES 145 26-Mar-23 17-Sep-23 17-Sep-23, HDPE PIPES


JAH-Z3-PR-WU-GW.125
Request for Quotation 10 26-Mar-23 05-Apr-23 Request for Quotation

JAH-Z3-PR-WU-GW.140
Issue Purchase Order 15 06-Apr-23 26-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.155
Staging time 30 27-Apr-23 31-May-23 Staging time

JAH-Z3-PR-WU-GW.210
Material Delivery 90 01-Jun-23 17-Sep-23 Material Delivery

GRP PIPES 145 02-Mar-23 24-Aug-23 24-Aug-23, GRP PIPES


JAH-Z3-PR-WU-GW.115
Request for Quotation 10 02-Mar-23 13-Mar-23 Request for Quotation

JAH-Z3-PR-WU-GW.120
Issue Purchase Order 15 14-Mar-23 30-Mar-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.145
Staging time 30 01-Apr-23 08-May-23 Staging time

JAH-Z3-PR-WU-GW.185
Material Delivery 90 09-May-23 24-Aug-23 Material Delivery

DI & GRP FITTING 145 28-Mar-23 19-Sep-23 19-Sep-23, DI & GRP FITTING
JAH-Z3-PR-WU-GW.130
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z3-PR-WU-GW.150
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.160
Staging time 30 30-Apr-23 03-Jun-23 Staging time

JAH-Z3-PR-WU-GW.215
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

GATE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, GATE VALVE


JAH-Z3-PR-WU-GW.180
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-GW.190
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.220
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-GW.240
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

BUTTERFLAY VALVE 145 17-May-23 06-Nov-23 06-Nov-23, BUTTERFLAY VALVE


JAH-Z3-PR-WU-GW.175
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-GW.195
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.225
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-GW.245
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
280 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AIR RELASE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, AIR RELASE VALVE
JAH-Z3-PR-WU-GW.170
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-GW.200
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.230
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-GW.250
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

WASEHOUT VALVE 145 17-May-23 06-Nov-23 06-Nov-23, WASEHOUT VALVE


JAH-Z3-PR-WU-GW.165
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-GW.205
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-GW.235
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-GW.255
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 231 26-Mar-23 27-Dec-23 27-Dec-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 26-Mar-23 17-Sep-23 17-Sep-23, HDPE PIPES
JAH-Z3-PR-WU-IR.100Request for Quotation 10 26-Mar-23 05-Apr-23 Request for Quotation

JAH-Z3-PR-WU-IR.105Issue Purchase Order 15 06-Apr-23 26-Apr-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.110Staging time 30 27-Apr-23 31-May-23 Staging time

JAH-Z3-PR-WU-IR.155Material Delivery 90 01-Jun-23 17-Sep-23 Material Delivery

GATE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, GATE VALVE


JAH-Z3-PR-WU-IR.130Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-IR.135Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.160Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-IR.190Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

BUTTERFLAY VALVE 145 17-May-23 06-Nov-23 06-Nov-23, BUTTERFLAY VALVE


JAH-Z3-PR-WU-IR.125Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-IR.140Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.165Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-IR.195Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

AIR RELASE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, AIR RELASE VALVE
JAH-Z3-PR-WU-IR.120Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-IR.145Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.170Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-IR.200Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

WASEHOUT VALVE 145 17-May-23 06-Nov-23 06-Nov-23, WASEHOUT VALVE


JAH-Z3-PR-WU-IR.115Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-IR.150Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.175Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-IR.205Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

FIRE HYDRANT 145 11-Jul-23 27-Dec-23 27-Dec-23, FIRE HYDRANT


JAH-Z3-PR-WU-IR.180Request for Quotation 10 11-Jul-23 22-Jul-23 Request for Quotation

JAH-Z3-PR-WU-IR.185Issue Purchase Order 15 23-Jul-23 08-Aug-23 Issue Purchase Order

JAH-Z3-PR-WU-IR.210Staging time 30 09-Aug-23 12-Sep-23 Staging time

JAH-Z3-PR-WU-IR.215Material Delivery 90 13-Sep-23 27-Dec-23 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 227 07-Feb-23 06-Nov-23 06-Nov-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 07-Feb-23 01-Aug-23 01-Aug-23, MILD STEEL PIPE
JAH-Z3-PR-WU-CW.105
Request for Quotation 10 07-Feb-23 18-Feb-23 Request for Quotation

JAH-Z3-PR-WU-CW.110
Issue Purchase Order 15 19-Feb-23 07-Mar-23 Issue Purchase Order

JAH-Z3-PR-WU-CW.120
Staging time 30 08-Mar-23 11-Apr-23 Staging time

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
281 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-PR-WU-CW.130
Material Delivery 90 12-Apr-23 01-Aug-23 Material Delivery

MILD STEEL FITTING 145 07-Feb-23 01-Aug-23 01-Aug-23, MILD STEEL FITTING
JAH-Z3-PR-WU-CW.100
Request for Quotation 10 07-Feb-23 18-Feb-23 Request for Quotation

JAH-Z3-PR-WU-CW.115
Issue Purchase Order 15 19-Feb-23 07-Mar-23 Issue Purchase Order

JAH-Z3-PR-WU-CW.125
Staging time 30 08-Mar-23 11-Apr-23 Staging time

JAH-Z3-PR-WU-CW.135
Material Delivery 90 12-Apr-23 01-Aug-23 Material Delivery

GATE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, GATE VALVE


JAH-Z3-PR-WU-CW.140
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z3-PR-WU-CW.145
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z3-PR-WU-CW.150
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z3-PR-WU-CW.155
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE
JAH-Z3-PR-WU-AWC.120
Issue Purchase Order 15 09-Oct-23 25-Oct-23 Issue Purchase Order

JAH-Z3-PR-WU-AWC.125
Staging time 30 26-Oct-23 29-Nov-23 Staging time

JAH-Z3-PR-WU-AWC.130
Material Delivery 90 30-Nov-23 13-Mar-24 Material Delivery

JAH-Z3-PR-WU-AWC.135
Request for Quotation 10 27-Sep-23 08-Oct-23 Request for Quotation

DRY UTILITIES 229 28-Mar-23 27-Dec-23 27-Dec-23, DRY UTILITIES


POWER 229 28-Mar-23 27-Dec-23 27-Dec-23, POWER
HIGH VOLTAGE 110 KV NETWORK 145 28-Mar-23 19-Sep-23 19-Sep-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z3-PR-DU-PWR.365
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z3-PR-DU-PWR.370
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-DU-PWR.375
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-DU-PWR.395
Staging time 30 30-Apr-23 03-Jun-23 Staging time

MEDIUM VOLTAGE 13.8 KV NETWORK 145 28-Mar-23 19-Sep-23 19-Sep-23, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z3-PR-DU-PWR.405
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z3-PR-DU-PWR.410
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-DU-PWR.415
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-DU-PWR.420
Staging time 30 30-Apr-23 03-Jun-23 Staging time

LOW VOLTAGE NETWORK 145 28-Mar-23 19-Sep-23 19-Sep-23, LOW VOLTAGE NETWORK
JAH-Z3-PR-DU-PWR.425
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z3-PR-DU-PWR.430
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-DU-PWR.435
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-DU-PWR.440
Staging time 30 30-Apr-23 03-Jun-23 Staging time

ELECTRICAL DISTRIBUTION SYSTEM 145 11-Jul-23 27-Dec-23 27-Dec-23, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z3-PR-DU-PWR.380
Request for Quotation 10 11-Jul-23 22-Jul-23 Request for Quotation

JAH-Z3-PR-DU-PWR.385
Issue Purchase Order 15 23-Jul-23 08-Aug-23 Issue Purchase Order

JAH-Z3-PR-DU-PWR.390
Material Delivery 90 13-Sep-23 27-Dec-23 Material Delivery

JAH-Z3-PR-DU-PWR.400
Staging time 30 09-Aug-23 12-Sep-23 Staging time

LIGHTING SYSTEM 145 28-Mar-23 19-Sep-23 19-Sep-23, LIGHTING SYSTEM


JAH-Z3-PR-DU-PWR.445
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z3-PR-DU-PWR.450
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z3-PR-DU-PWR.455
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

JAH-Z3-PR-DU-PWR.460
Staging time 30 30-Apr-23 03-Jun-23 Staging time

LOW CURRENT 145 26-Apr-23 16-Oct-23 16-Oct-23, LOW CURRENT


TELECOM SERVICES 145 26-Apr-23 16-Oct-23 16-Oct-23, TELECOM SERVICES
JAH-Z3-PR-DU-LC.185Request for Quotation 10 26-Apr-23 07-May-23 Request for Quotation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
282 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-PR-DU-LC.190Issue Purchase Order 15 08-May-23 24-May-23 Issue Purchase Order

JAH-Z3-PR-DU-LC.195Material Delivery 90 03-Jul-23 16-Oct-23 Material Delivery

JAH-Z3-PR-DU-LC.200Staging time 30 25-May-23 02-Jul-23 Staging time

MEP 235 16-Nov-22 23-Aug-23 23-Aug-23, MEP


JAH-Z3-PRO-MEP.140 Request for Quotation 10 16-Nov-22 27-Nov-22 Request for Quotation

JAH-Z3-PRO-MEP.145 Issue Purchase Order 15 28-Nov-22 14-Dec-22 Issue Purchase Order

JAH-Z3-PRO-MEP.147 Staging Time 30 15-Dec-22 18-Jan-23 Staging Time

JAH-Z3-PRO-MEP.150 Material Delivery 180 19-Jan-23 23-Aug-23 Material Delivery

ARCHITECTURAL 115 14-Dec-22 30-Apr-23 30-Apr-23, ARCHITECTURAL


JAH-Z3-PRO-ARC.140 Request for Quotation 10 14-Dec-22 25-Dec-22 Request for Quotation

JAH-Z3-PRO-ARC.145 Issue Purchase Order 15 26-Dec-22 11-Jan-23 Issue Purchase Order

JAH-Z3-PRO-ARC.150 Material Delivery 60 16-Feb-23 30-Apr-23 Material Delivery

JAH-Z3-PRO-ARC.155 Staging Time 30 12-Jan-23 15-Feb-23 Staging Time

CONSTRUCTION 1117 02-Jul-22 A 23-Feb-26 23-Feb-26, CONSTRUCTION


GENERAL SITE ARRANGEMENT 30 17-Jul-22 A 01-Dec-22 01-Dec-22, GENERAL SITE ARRANGEMENT
SITE PREPARATION 30 17-Jul-22 A 01-Dec-22 01-Dec-22, SITE PREPARATION
JAH-Z3-CON-GA-SP.130Site Clearing & Grubbing / Demolition of Obstacles 5 17-Jul-22 A 25-Aug-22 A Site Clearing & Grubbing / Demolition of Obstacles

JAH-Z3-CON-GA-SP.135Disposal /Removal of Unnecessary Objects from Site 7 23-Jul-22 A 30-Aug-22 A Disposal /Removal of Unnecessary Objects from Site

JAH-Z3-CON-GA-SP.140Relocation of Exisiting Utilities 30 29-Oct-22 01-Dec-22 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 177 02-Jul-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION


JAH-Z3-CON-GTI.100 Borehole Layout Preparation & Submission 8 02-Jul-22 A 18-Aug-22 A Borehole Layout Preparation & Submission

JAH-Z3-CON-GTI.105 Borehole Layout Review & Approval 7 14-Jul-22 A 21-Aug-22 A Borehole Layout Review & Approval

JAH-Z3-CON-GTI.110 Drilling Boreholes 10 22-Aug-22 A 23-Aug-22 A Drilling Boreholes

JAH-Z3-CON-GTI.115 Issuance of Geo-Technical Investigation Report 10 23-Aug-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 172 04-Sep-22 A 02-Aug-23 02-Aug-23, EXCAVATION & DEWATERING
JAH-Z3-CON-DE.107 Dewatering @Sta. 0+994 ~ 1+094 142 06-Oct-22 A 01-May-23 Dewatering @Sta. 0+994 ~ 1+094

JAH-Z3-CON-DE.112 Dewatering @Sta. 1+094 ~ 1+194 152 14-Jan-23 16-Jul-23 Dewatering @Sta. 1+094 ~ 1+194

JAH-Z3-CON-DE.120 Dewatering @Sta. 1+194 ~ 1+268 147 06-Feb-23 02-Aug-23 Dewatering @Sta. 1+194 ~ 1+268

JAH-Z3-CON-EX.106 Excavation & Shoring System @Sta. 0+994 ~ 1+094 17 04-Sep-22 A 14-Dec-22 Excavation & Shoring System @Sta. 0+994 ~ 1+094

JAH-Z3-CON-EX.110 Excavation & Shoring System @Sta. 1+094 ~ 1+194 20 14-Jan-23 05-Feb-23 Excavation & Shoring System @Sta. 1+094 ~ 1+194

JAH-Z3-CON-EX.115 Excavation & Shoring System @Sta. 1+194 ~ 1+268 20 06-Feb-23 28-Feb-23 Excavation & Shoring System @Sta. 1+194 ~ 1+268

SOIL IMPROVEMENT 75 15-Dec-22 12-Mar-23 12-Mar-23, SOIL IMPROVEMENT


JAH-Z3-CON-SIMP.101 Soil Improvement @Sta. 0+994 ~ 1+094 10 15-Dec-22 26-Dec-22 Soil Improvement @Sta. 0+994 ~ 1+094

JAH-Z3-CON-SIMP.106 Soil Improvement @Sta. 1+094 ~ 1+194 10 06-Feb-23 16-Feb-23 Soil Improvement @Sta. 1+094 ~ 1+194

JAH-Z3-CON-SIMP.111 Soil Improvement @Sta. 1+194 ~ 1+214 10 01-Mar-23 12-Mar-23 Soil Improvement @Sta. 1+194 ~ 1+214

STRUCTURAL WORKS 257 22-Aug-23 25-Jun-24 25-Jun-24, STRUCTURAL WORKS


STA. 0+994 ~ 1+014 163 22-Aug-23 28-Feb-24 28-Feb-24, STA. 0+994 ~ 1+014
BASE SLAB 24 22-Aug-23 18-Sep-23 18-Sep-23, BASE SLAB
JAH-Z3-ST-S1-BS.100 Lean Concrete for Base Slab 1 22-Aug-23 22-Aug-23 Lean Concrete for Base Slab

JAH-Z3-ST-S1-BS.105 Waterproofing for Lean Concrete 1 23-Aug-23 23-Aug-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S1-BS.110 Base Slab Rebar Installation 7 24-Aug-23 31-Aug-23 Base Slab Rebar Installation

JAH-Z3-ST-S1-BS.115 Base Slab Formwork Installation 5 02-Sep-23 06-Sep-23 Base Slab Formwork Installation

JAH-Z3-ST-S1-BS.120 Base Slab Concrete Casting 1 07-Sep-23 07-Sep-23 Base Slab Concrete Casting

JAH-Z3-ST-S1-BS.122 Curing work 7 09-Sep-23 16-Sep-23 Curing work

JAH-Z3-ST-S1-BS.125 Base Slab Formwork Removel 2 17-Sep-23 18-Sep-23 Base Slab Formwork Removel

COLUMNS 23 17-Sep-23 14-Oct-23 14-Oct-23, COLUMNS


JAH-Z3-ST-S1-CL.100 Column Rebar Installation 8 17-Sep-23 26-Sep-23 Column Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
283 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S1-CL.105 Column Formwork Installation 7 27-Sep-23 04-Oct-23 Column Formwork Installation

JAH-Z3-ST-S1-CL.110 Column Concrete Casting 1 05-Oct-23 05-Oct-23 Column Concrete Casting

JAH-Z3-ST-S1-CL.115 Form Work Removal and Curing 7 07-Oct-23 14-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 17-Sep-23 30-Oct-23 30-Oct-23, TUNNEL WALLS


JAH-Z3-ST-S1-TW.100 Tunnel Wallss Rebar Installation 8 17-Sep-23 26-Sep-23 Tunnel Wallss Rebar Installation

JAH-Z3-ST-S1-TW.105 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 17-Sep-23 26-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S1-TW.110 Tunnel Formwork Installation 7 27-Sep-23 04-Oct-23 Tunnel Formwork Installation

JAH-Z3-ST-S1-TW.115 Tunnel Walls Concrete Casting 1 05-Oct-23 05-Oct-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S1-TW.117 Curing work 7 07-Oct-23 14-Oct-23 Curing work

JAH-Z3-ST-S1-TW.120 Tunnel Walls Formwork Removel 2 15-Oct-23 16-Oct-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S1-TW.125 Tunnel Wall Waterproofing 12 17-Oct-23 30-Oct-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 17-Oct-23 20-Nov-23 20-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S1-MS.100 Middle Slab Scaffold and Formwork Installation 5 17-Oct-23 22-Oct-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S1-MS.105 Middle Slab Rebar Installation 8 23-Oct-23 31-Oct-23 Middle Slab Rebar Installation

JAH-Z3-ST-S1-MS.110 Middle Slab Vertical Formwork Installation 7 01-Nov-23 08-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S1-MS.115 Middle Slab Concrete Casting 1 09-Nov-23 09-Nov-23 Middle Slab Concrete Casting

JAH-Z3-ST-S1-MS.117 Curing work 7 11-Nov-23 18-Nov-23 Curing work

JAH-Z3-ST-S1-MS.120 Middle Slab Formwork Removel 2 19-Nov-23 20-Nov-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 21-Nov-23 19-Dec-23 19-Dec-23, UTILITY CULVERT WALLS


JAH-Z3-ST-S1-UCW.100Utility Culvert Walls Rebar Installation 8 21-Nov-23 29-Nov-23 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S1-UCW.105Utility Culvert Walls Formwork Installation 7 30-Nov-23 07-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S1-UCW.110Utility Culvert Walls Concrete Casting 1 09-Dec-23 09-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S1-UCW.112Curing work 7 10-Dec-23 17-Dec-23 Curing work

JAH-Z3-ST-S1-UCW.115Utility Culvert Walls Walls Formwork Removel 2 18-Dec-23 19-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 20-Dec-23 31-Jan-24 31-Jan-24, TOP SLAB


JAH-Z3-ST-S1-TS.090 Top Slab Formwork Installation 7 20-Dec-23 27-Dec-23 Top Slab Formwork Installation

JAH-Z3-ST-S1-TS.100 Top Slab Rebar Installation 8 28-Dec-23 06-Jan-24 Top Slab Rebar Installation

JAH-Z3-ST-S1-TS.110 Top Slab Concrete Casting 1 07-Jan-24 07-Jan-24 Top Slab Concrete Casting

JAH-Z3-ST-S1-TS.112 Curing work 7 08-Jan-24 15-Jan-24 Curing work

JAH-Z3-ST-S1-TS.115 Top Slab Formwork Removel 2 16-Jan-24 17-Jan-24 Top Slab Formwork Removel

JAH-Z3-ST-S1-TS.120 Waterproofing for Top Slab 12 18-Jan-24 31-Jan-24 Waterproofing for Top Slab

FINISHING WORK 24 01-Feb-24 28-Feb-24 28-Feb-24, FINISHING WORK


JAH-Z3-ST-S1-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 01-Feb-24 08-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S1-FW.105 Plain Concrete Casting Inc. Curing Time 1 10-Feb-24 10-Feb-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S1-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 11-Feb-24 11-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S1-FW.112 Curing work 7 12-Feb-24 19-Feb-24 Curing work

JAH-Z3-ST-S1-FW.115 Concrete Protective coating 8 20-Feb-24 28-Feb-24 Concrete Protective coating

STA. 1+014 ~ 1+034 169 02-Sep-23 17-Mar-24 17-Mar-24, STA. 1+014 ~ 1+034
BASE SLAB 24 02-Sep-23 30-Sep-23 30-Sep-23, BASE SLAB
JAH-Z3-ST-S2-BS.100 Lean Concrete for Base Slab 1 02-Sep-23 02-Sep-23 Lean Concrete for Base Slab

JAH-Z3-ST-S2-BS.105 Waterproofing for Lean Concrete 1 03-Sep-23 03-Sep-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S2-BS.110 Base Slab Rebar Installation 7 04-Sep-23 11-Sep-23 Base Slab Rebar Installation

JAH-Z3-ST-S2-BS.115 Base Slab Formwork Installation 5 12-Sep-23 17-Sep-23 Base Slab Formwork Installation

JAH-Z3-ST-S2-BS.120 Base Slab Concrete Casting 1 18-Sep-23 18-Sep-23 Base Slab Concrete Casting

JAH-Z3-ST-S2-BS.122 Curing work 7 19-Sep-23 27-Sep-23 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
284 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S2-BS.125 Base Slab Formwork Removel 2 28-Sep-23 30-Sep-23 Base Slab Formwork Removel

COLUMNS 23 28-Sep-23 24-Oct-23 24-Oct-23, COLUMNS


JAH-Z3-ST-S2-CL.100 Column Rebar Installation 8 28-Sep-23 07-Oct-23 Column Rebar Installation

JAH-Z3-ST-S2-CL.105 Column Formwork Installation 7 08-Oct-23 15-Oct-23 Column Formwork Installation

JAH-Z3-ST-S2-CL.110 Column Concrete Casting 1 16-Oct-23 16-Oct-23 Column Concrete Casting

JAH-Z3-ST-S2-CL.115 Form Work Removal and Curing 7 17-Oct-23 24-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 28-Sep-23 09-Nov-23 09-Nov-23, TUNNEL WALLS


JAH-Z3-ST-S2-TW.100 Tunnel Walls Rebar Installation 8 28-Sep-23 07-Oct-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S2-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Sep-23 07-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S2-TW.105 Tunnel Formwork Installation 7 08-Oct-23 15-Oct-23 Tunnel Formwork Installation

JAH-Z3-ST-S2-TW.110 Tunnel Walls Concrete Casting 1 16-Oct-23 16-Oct-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S2-TW.115 Curing work 7 17-Oct-23 24-Oct-23 Curing work

JAH-Z3-ST-S2-TW.120 Tunnel Walls Formwork Removel 2 25-Oct-23 26-Oct-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S2-TW.125 Tunnel Wall Waterproofing 12 28-Oct-23 09-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-Oct-23 30-Nov-23 30-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S2-MS.090 Middle Slab Scaffold and Formwork Installation 5 28-Oct-23 01-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S2-MS.100 Middle Slab Rebar Installation 8 02-Nov-23 11-Nov-23 Middle Slab Rebar Installation

JAH-Z3-ST-S2-MS.105 Middle Slab Vertical Formwork Installation 7 12-Nov-23 19-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S2-MS.110 Middle Slab Concrete Casting 1 20-Nov-23 20-Nov-23 Middle Slab Concrete Casting

JAH-Z3-ST-S2-MS.115 Curing work 7 21-Nov-23 28-Nov-23 Curing work

JAH-Z3-ST-S2-MS.120 Middle Slab Formwork Removel 2 29-Nov-23 30-Nov-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 02-Dec-23 30-Dec-23 30-Dec-23, UTILITY CULVERT WALLS


JAH-Z3-ST-S2-UCW.100Utility Culvert Walls Rebar Installation 8 02-Dec-23 10-Dec-23 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S2-UCW.105Utility Culvert Walls Formwork Installation 7 11-Dec-23 18-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S2-UCW.110Utility Culvert Walls Concrete Casting 1 19-Dec-23 19-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S2-UCW.112Curing work 7 20-Dec-23 27-Dec-23 Curing work

JAH-Z3-ST-S2-UCW.115Utility Culvert Walls Walls Formwork Removel 2 28-Dec-23 30-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 31-Dec-23 11-Feb-24 11-Feb-24, TOP SLAB


JAH-Z3-ST-S2-TS.090 Top Slab Formwork Installation 7 31-Dec-23 07-Jan-24 Top Slab Formwork Installation

JAH-Z3-ST-S2-TS.100 Top Slab Rebar Installation 8 08-Jan-24 16-Jan-24 Top Slab Rebar Installation

JAH-Z3-ST-S2-TS.110 Top Slab Concrete Casting 1 17-Jan-24 17-Jan-24 Top Slab Concrete Casting

JAH-Z3-ST-S2-TS.112 Curing work 7 18-Jan-24 25-Jan-24 Curing work

JAH-Z3-ST-S2-TS.115 Top Slab Formwork Removel 2 27-Jan-24 28-Jan-24 Top Slab Formwork Removel

JAH-Z3-ST-S2-TS.120 Waterproofing for Top Slab 12 29-Jan-24 11-Feb-24 Waterproofing for Top Slab

FINISHING WORK 30 12-Feb-24 17-Mar-24 17-Mar-24, FINISHING WORK


JAH-Z3-ST-S2-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 12-Feb-24 19-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S2-FW.105 Plain Concrete Casting Inc. Curing Time 7 20-Feb-24 27-Feb-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S2-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 28-Feb-24 28-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S2-FW.112 Curing work 7 29-Feb-24 07-Mar-24 Curing work

JAH-Z3-ST-S2-FW.115 Concrete Protective coating 8 09-Mar-24 17-Mar-24 Concrete Protective coating

STA. 1+034 ~ 1+054 175 04-Sep-23 26-Mar-24 26-Mar-24, STA. 1+034 ~ 1+054
BASE SLAB 24 04-Sep-23 02-Oct-23 02-Oct-23, BASE SLAB
JAH-Z3-ST-S3-BS.100 Lean Concrete for Base Slab 1 04-Sep-23 04-Sep-23 Lean Concrete for Base Slab

JAH-Z3-ST-S3-BS.105 Waterproofing for Lean Concrete 1 05-Sep-23 05-Sep-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S3-BS.110 Base Slab Rebar Installation 7 06-Sep-23 13-Sep-23 Base Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
285 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S3-BS.115 Base Slab Formwork Installation 5 14-Sep-23 19-Sep-23 Base Slab Formwork Installation

JAH-Z3-ST-S3-BS.120 Base Slab Concrete Casting 1 20-Sep-23 20-Sep-23 Base Slab Concrete Casting

JAH-Z3-ST-S3-BS.122 Curing work 7 21-Sep-23 30-Sep-23 Curing work

JAH-Z3-ST-S3-BS.125 Base Slab Formwork Removel 2 01-Oct-23 02-Oct-23 Base Slab Formwork Removel

COLUMNS 23 03-Oct-23 29-Oct-23 29-Oct-23, COLUMNS


JAH-Z3-ST-S3-CL.100 Column Rebar Installation 8 03-Oct-23 11-Oct-23 Column Rebar Installation

JAH-Z3-ST-S3-CL.105 Column Formwork Installation 7 12-Oct-23 19-Oct-23 Column Formwork Installation

JAH-Z3-ST-S3-CL.110 Column Concrete Casting 1 21-Oct-23 21-Oct-23 Column Concrete Casting

JAH-Z3-ST-S3-CL.115 Form Work Removal and Curing 7 22-Oct-23 29-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 03-Oct-23 14-Nov-23 14-Nov-23, TUNNEL WALLS


JAH-Z3-ST-S3-TW.100 Tunnel Walls Rebar Installation 8 03-Oct-23 11-Oct-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S3-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 03-Oct-23 11-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S3-TW.105 Tunnel Formwork Installation 7 12-Oct-23 19-Oct-23 Tunnel Formwork Installation

JAH-Z3-ST-S3-TW.110 Tunnel Walls Concrete Casting 1 21-Oct-23 21-Oct-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S3-TW.112 Curing work 7 22-Oct-23 29-Oct-23 Curing work

JAH-Z3-ST-S3-TW.120 Tunnel Walls Formwork Removel 2 30-Oct-23 31-Oct-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S3-TW.125 Tunnel Wall Waterproofing 12 01-Nov-23 14-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 01-Nov-23 05-Dec-23 05-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S3-MS.090 Middle Slab Scaffold and Formwork Installation 5 01-Nov-23 06-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S3-MS.100 Middle Slab Rebar Installation 8 07-Nov-23 15-Nov-23 Middle Slab Rebar Installation

JAH-Z3-ST-S3-MS.105 Middle Slab Vertical Formwork Installation 7 16-Nov-23 23-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S3-MS.110 Middle Slab Concrete Casting 1 25-Nov-23 25-Nov-23 Middle Slab Concrete Casting

JAH-Z3-ST-S3-MS.115 Curing work 7 26-Nov-23 03-Dec-23 Curing work

JAH-Z3-ST-S3-MS.120 Middle Slab Formwork Removel 2 04-Dec-23 05-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 06-Dec-23 03-Jan-24 03-Jan-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S3-UCW.100Utility Culvert Walls Rebar Installation 8 06-Dec-23 14-Dec-23 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S3-UCW.105Utility Culvert Walls Formwork Installation 7 16-Dec-23 23-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S3-UCW.110Utility Culvert Walls Concrete Casting 1 24-Dec-23 24-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S3-UCW.112Curing work 7 25-Dec-23 01-Jan-24 Curing work

JAH-Z3-ST-S3-UCW.115Utility Culvert Walls Walls Formwork Removel 2 02-Jan-24 03-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 04-Jan-24 15-Feb-24 15-Feb-24, TOP SLAB


JAH-Z3-ST-S3-TS.090 Top Slab Formwork Installation 7 04-Jan-24 11-Jan-24 Top Slab Formwork Installation

JAH-Z3-ST-S3-TS.100 Top Slab Rebar Installation 8 13-Jan-24 21-Jan-24 Top Slab Rebar Installation

JAH-Z3-ST-S3-TS.110 Top Slab Concrete Casting 1 22-Jan-24 22-Jan-24 Top Slab Concrete Casting

JAH-Z3-ST-S3-TS.112 Curing work 7 23-Jan-24 30-Jan-24 Curing work

JAH-Z3-ST-S3-TS.115 Top Slab Formwork Removel 2 31-Jan-24 01-Feb-24 Top Slab Formwork Removel

JAH-Z3-ST-S3-TS.120 Waterproofing for Top Slab 12 03-Feb-24 15-Feb-24 Waterproofing for Top Slab

FINISHING WORK 34 17-Feb-24 26-Mar-24 26-Mar-24, FINISHING WORK


JAH-Z3-ST-S3-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 17-Feb-24 24-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S3-FW.105 Plain Concrete Casting Inc. Curing Time 7 25-Feb-24 03-Mar-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S3-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 04-Mar-24 04-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S3-FW.112 Curing work 7 05-Mar-24 12-Mar-24 Curing work

JAH-Z3-ST-S3-FW.115 Concrete Protective coating 8 18-Mar-24 26-Mar-24 Concrete Protective coating

STA. 1+054 ~ 1+074 170 20-Sep-23 06-Apr-24 06-Apr-24, STA. 1+054 ~ 1+074
BASE SLAB 23 20-Sep-23 17-Oct-23 17-Oct-23, BASE SLAB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
286 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S4-BS.100 Lean Concrete for Base Slab 1 20-Sep-23 20-Sep-23 Lean Concrete for Base Slab

JAH-Z3-ST-S4-BS.105 Waterproofing for Lean Concrete 1 21-Sep-23 21-Sep-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S4-BS.110 Base Slab Rebar Installation 6 24-Sep-23 30-Sep-23 Base Slab Rebar Installation

JAH-Z3-ST-S4-BS.115 Base Slab Formwork Installation 5 01-Oct-23 05-Oct-23 Base Slab Formwork Installation

JAH-Z3-ST-S4-BS.120 Base Slab Concrete Casting 1 07-Oct-23 07-Oct-23 Base Slab Concrete Casting

JAH-Z3-ST-S4-BS.122 Curing work 7 08-Oct-23 15-Oct-23 Curing work

JAH-Z3-ST-S4-BS.125 Base Slab Formwork Removel 2 16-Oct-23 17-Oct-23 Base Slab Formwork Removel

COLUMNS 21 18-Oct-23 11-Nov-23 11-Nov-23, COLUMNS


JAH-Z3-ST-S4-CL.100 Column Rebar Installation 6 18-Oct-23 24-Oct-23 Column Rebar Installation

JAH-Z3-ST-S4-CL.105 Column Formwork Installation 7 25-Oct-23 01-Nov-23 Column Formwork Installation

JAH-Z3-ST-S4-CL.110 Column Concrete Casting 1 02-Nov-23 02-Nov-23 Column Concrete Casting

JAH-Z3-ST-S4-CL.115 Form Work Removal and Curing 7 04-Nov-23 11-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 18-Oct-23 29-Nov-23 29-Nov-23, TUNNEL WALLS


JAH-Z3-ST-S4-TW.100 Tunnel Walls Rebar Installation 6 18-Oct-23 24-Oct-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S4-TW.104 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 18-Oct-23 26-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S4-TW.105 Tunnel Formwork Installation 7 28-Oct-23 04-Nov-23 Tunnel Formwork Installation

JAH-Z3-ST-S4-TW.110 Tunnel Walls Concrete Casting 1 05-Nov-23 05-Nov-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S4-TW.112 Curing work 7 06-Nov-23 13-Nov-23 Curing work

JAH-Z3-ST-S4-TW.120 Tunnel Walls Formwork Removel 2 14-Nov-23 15-Nov-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S4-TW.125 Tunnel Wall Waterproofing 12 16-Nov-23 29-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 16-Nov-23 20-Dec-23 20-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S4-MS.090 Middle Slab Scaffold and Formwork Installation 5 16-Nov-23 21-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S4-MS.100 Middle Slab Rebar Installation 8 22-Nov-23 30-Nov-23 Middle Slab Rebar Installation

JAH-Z3-ST-S4-MS.105 Middle Slab Vertical Formwork Installation 7 02-Dec-23 09-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S4-MS.110 Middle Slab Concrete Casting 1 10-Dec-23 10-Dec-23 Middle Slab Concrete Casting

JAH-Z3-ST-S4-MS.115 Curing work 7 11-Dec-23 18-Dec-23 Curing work

JAH-Z3-ST-S4-MS.120 Middle Slab Formwork Removel 2 19-Dec-23 20-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 21-Dec-23 18-Jan-24 18-Jan-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S4-UCW.100Utility Culvert Walls Rebar Installation 8 21-Dec-23 30-Dec-23 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S4-UCW.105Utility Culvert Walls Formwork Installation 7 31-Dec-23 07-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S4-UCW.110Utility Culvert Walls Concrete Casting 1 08-Jan-24 08-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S4-UCW.112Curing work 7 09-Jan-24 16-Jan-24 Curing work

JAH-Z3-ST-S4-UCW.115Utility Culvert Walls Walls Formwork Removel 2 17-Jan-24 18-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 20-Jan-24 02-Mar-24 02-Mar-24, TOP SLAB


JAH-Z3-ST-S4-TS.090 Top Slab Formwork Installation 7 20-Jan-24 27-Jan-24 Top Slab Formwork Installation

JAH-Z3-ST-S4-TS.100 Top Slab Rebar Installation 8 28-Jan-24 05-Feb-24 Top Slab Rebar Installation

JAH-Z3-ST-S4-TS.110 Top Slab Concrete Casting 1 06-Feb-24 06-Feb-24 Top Slab Concrete Casting

JAH-Z3-ST-S4-TS.112 Curing work 7 07-Feb-24 14-Feb-24 Curing work

JAH-Z3-ST-S4-TS.115 Top Slab Formwork Removel 2 15-Feb-24 17-Feb-24 Top Slab Formwork Removel

JAH-Z3-ST-S4-TS.120 Waterproofing for Top Slab 12 18-Feb-24 02-Mar-24 Waterproofing for Top Slab

FINISHING WORK 30 03-Mar-24 06-Apr-24 06-Apr-24, FINISHING WORK


JAH-Z3-ST-S4-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 03-Mar-24 10-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S4-FW.105 Plain Concrete Casting Inc. Curing Time 7 11-Mar-24 18-Mar-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S4-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 19-Mar-24 19-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S4-FW.112 Curing work 7 20-Mar-24 27-Mar-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
287 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S4-FW.115 Concrete Protective coating 8 28-Mar-24 06-Apr-24 Concrete Protective coating

STA. 1+074 ~ 1+094 171 07-Oct-23 25-Apr-24 25-Apr-24, STA. 1+074 ~ 1+094
BASE SLAB 24 07-Oct-23 02-Nov-23 02-Nov-23, BASE SLAB
JAH-Z3-ST-S5-BS.100 Lean Concrete for Base Slab 1 07-Oct-23 07-Oct-23 Lean Concrete for Base Slab

JAH-Z3-ST-S5-BS.105 Waterproofing for Lean Concrete 1 08-Oct-23 08-Oct-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S5-BS.110 Base Slab Rebar Installation 7 09-Oct-23 16-Oct-23 Base Slab Rebar Installation

JAH-Z3-ST-S5-BS.115 Base Slab Formwork Installation 5 17-Oct-23 22-Oct-23 Base Slab Formwork Installation

JAH-Z3-ST-S5-BS.120 Base Slab Concrete Casting 1 23-Oct-23 23-Oct-23 Base Slab Concrete Casting

JAH-Z3-ST-S5-BS.122 Curing work 7 24-Oct-23 31-Oct-23 Curing work

JAH-Z3-ST-S5-BS.125 Base Slab Formwork Removel 2 01-Nov-23 02-Nov-23 Base Slab Formwork Removel

COLUMNS 23 04-Nov-23 29-Nov-23 29-Nov-23, COLUMNS


JAH-Z3-ST-S5-CL.100 Column Rebar Installation 8 04-Nov-23 12-Nov-23 Column Rebar Installation

JAH-Z3-ST-S5-CL.105 Column Formwork Installation 7 13-Nov-23 20-Nov-23 Column Formwork Installation

JAH-Z3-ST-S5-CL.110 Column Concrete Casting 1 21-Nov-23 21-Nov-23 Column Concrete Casting

JAH-Z3-ST-S5-CL.115 Form Work Removal and Curing 7 22-Nov-23 29-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 04-Nov-23 16-Dec-23 16-Dec-23, TUNNEL WALLS


JAH-Z3-ST-S5-TW.100 Tunnel Walls Rebar Installation 8 04-Nov-23 12-Nov-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S5-TW.104 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 04-Nov-23 12-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S5-TW.105 Tunnel Formwork Installation 7 13-Nov-23 20-Nov-23 Tunnel Formwork Installation

JAH-Z3-ST-S5-TW.110 Tunnel Walls Concrete Casting 1 21-Nov-23 21-Nov-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S5-TW.112 Curing work 7 22-Nov-23 29-Nov-23 Curing work

JAH-Z3-ST-S5-TW.120 Tunnel Walls Formwork Removel 2 30-Nov-23 02-Dec-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S5-TW.125 Tunnel Wall Waterproofing 12 03-Dec-23 16-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 03-Dec-23 06-Jan-24 06-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S5-MS.190 Middle Slab Scaffold and Formwork Installation 5 03-Dec-23 07-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S5-MS.200 Middle Slab Rebar Installation 8 09-Dec-23 17-Dec-23 Middle Slab Rebar Installation

JAH-Z3-ST-S5-MS.205 Middle Slab Vertical Formwork Installation 7 18-Dec-23 25-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S5-MS.210 Middle Slab Concrete Casting 1 26-Dec-23 26-Dec-23 Middle Slab Concrete Casting

JAH-Z3-ST-S5-MS.215 Curing work 7 27-Dec-23 03-Jan-24 Curing work

JAH-Z3-ST-S5-MS.220 Middle Slab Formwork Removel 2 04-Jan-24 06-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 07-Jan-24 04-Feb-24 04-Feb-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S5-UCW.180Utility Culvert Walls Rebar Installation 8 07-Jan-24 15-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S5-UCW.185Utility Culvert Walls Formwork Installation 7 16-Jan-24 23-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S5-UCW.190Utility Culvert Walls Concrete Casting 1 24-Jan-24 24-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S5-UCW.192Curing work 7 25-Jan-24 01-Feb-24 Curing work

JAH-Z3-ST-S5-UCW.195Utility Culvert Walls Walls Formwork Removel 2 03-Feb-24 04-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 05-Feb-24 18-Mar-24 18-Mar-24, TOP SLAB


JAH-Z3-ST-S5-TS.184 Top Slab Formwork Installation 7 05-Feb-24 12-Feb-24 Top Slab Formwork Installation

JAH-Z3-ST-S5-TS.285 Top Slab Rebar Installation 8 13-Feb-24 21-Feb-24 Top Slab Rebar Installation

JAH-Z3-ST-S5-TS.295 Top Slab Concrete Casting 1 22-Feb-24 22-Feb-24 Top Slab Concrete Casting

JAH-Z3-ST-S5-TS.297 Curing work 7 24-Feb-24 02-Mar-24 Curing work

JAH-Z3-ST-S5-TS.300 Top Slab Formwork Removel 2 03-Mar-24 04-Mar-24 Top Slab Formwork Removel

JAH-Z3-ST-S5-TS.305 Waterproofing for Top Slab 12 05-Mar-24 18-Mar-24 Waterproofing for Top Slab

FINISHING WORK 30 19-Mar-24 25-Apr-24 25-Apr-24, FINISHING WORK


JAH-Z3-ST-S5-FW.310 Above Top Slab Formwork Installation for Plain Concrete 7 19-Mar-24 26-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
288 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S5-FW.315 Plain Concrete Casting Inc. Curing Time 7 27-Mar-24 03-Apr-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S5-FW.320 Mass Concrete Casting for Base Slab Top Layer 1 04-Apr-24 04-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S5-FW.322 Curing work 7 06-Apr-24 16-Apr-24 Curing work

JAH-Z3-ST-S5-FW.325 Concrete Protective coating 8 17-Apr-24 25-Apr-24 Concrete Protective coating

STA. 1+094 ~ 1+114 171 23-Oct-23 12-May-24 12-May-24, STA. 1+094 ~ 1+114
BASE SLAB 24 23-Oct-23 19-Nov-23 19-Nov-23, BASE SLAB
JAH-Z3-ST-S6-BS.100 Lean Concrete for Base Slab 1 23-Oct-23 23-Oct-23 Lean Concrete for Base Slab

JAH-Z3-ST-S6-BS.105 Waterproofing for Lean Concrete 1 24-Oct-23 24-Oct-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S6-BS.110 Base Slab Rebar Installation 7 25-Oct-23 01-Nov-23 Base Slab Rebar Installation

JAH-Z3-ST-S6-BS.115 Base Slab Formwork Installation 5 02-Nov-23 07-Nov-23 Base Slab Formwork Installation

JAH-Z3-ST-S6-BS.120 Base Slab Concrete Casting 1 08-Nov-23 08-Nov-23 Base Slab Concrete Casting

JAH-Z3-ST-S6-BS.122 Curing work 7 09-Nov-23 16-Nov-23 Curing work

JAH-Z3-ST-S6-BS.125 Base Slab Formwork Removel 2 18-Nov-23 19-Nov-23 Base Slab Formwork Removel

COLUMNS 23 20-Nov-23 16-Dec-23 16-Dec-23, COLUMNS


JAH-Z3-ST-S6-CL.100 Column Rebar Installation 8 20-Nov-23 28-Nov-23 Column Rebar Installation

JAH-Z3-ST-S6-CL.105 Column Formwork Installation 7 29-Nov-23 06-Dec-23 Column Formwork Installation

JAH-Z3-ST-S6-CL.110 Column Concrete Casting 1 07-Dec-23 07-Dec-23 Column Concrete Casting

JAH-Z3-ST-S6-CL.115 Form Work Removal and Curing 7 09-Dec-23 16-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 20-Nov-23 01-Jan-24 01-Jan-24, TUNNEL WALLS


JAH-Z3-ST-S6-TW.100 Tunnel Walls Rebar Installation 8 20-Nov-23 28-Nov-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S6-TW.104 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 20-Nov-23 28-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S6-TW.105 Tunnel Formwork Installation 7 29-Nov-23 06-Dec-23 Tunnel Formwork Installation

JAH-Z3-ST-S6-TW.110 Tunnel Walls Concrete Casting 1 07-Dec-23 07-Dec-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S6-TW.112 Curing work 7 09-Dec-23 16-Dec-23 Curing work

JAH-Z3-ST-S6-TW.120 Tunnel Walls Formwork Removel 2 17-Dec-23 18-Dec-23 Tunnel Walls Formwork Removel

JAH-Z3-ST-S6-TW.125 Tunnel Wall Waterproofing 12 19-Dec-23 01-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 19-Dec-23 22-Jan-24 22-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S6-MS.224 Middle Slab Scaffold and Formwork Installation 5 19-Dec-23 24-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S6-MS.225 Middle Slab Rebar Installation 8 25-Dec-23 02-Jan-24 Middle Slab Rebar Installation

JAH-Z3-ST-S6-MS.230 Middle Slab Vertical Formwork Installation 7 03-Jan-24 10-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S6-MS.235 Middle Slab Concrete Casting 1 11-Jan-24 11-Jan-24 Middle Slab Concrete Casting

JAH-Z3-ST-S6-MS.240 Curing work 7 13-Jan-24 20-Jan-24 Curing work

JAH-Z3-ST-S6-MS.245 Middle Slab Formwork Removel 2 21-Jan-24 22-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 23-Jan-24 20-Feb-24 20-Feb-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S6-UCW.200Utility Culvert Walls Rebar Installation 8 23-Jan-24 31-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S6-UCW.205Utility Culvert Walls Formwork Installation 7 01-Feb-24 08-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S6-UCW.210Utility Culvert Walls Concrete Casting 1 10-Feb-24 10-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S6-UCW.212Curing work 7 11-Feb-24 18-Feb-24 Curing work

JAH-Z3-ST-S6-UCW.215Utility Culvert Walls Walls Formwork Removel 2 19-Feb-24 20-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 21-Feb-24 03-Apr-24 03-Apr-24, TOP SLAB


JAH-Z3-ST-S6-TS.329 Top Slab Formwork Installation 7 21-Feb-24 28-Feb-24 Top Slab Formwork Installation

JAH-Z3-ST-S6-TS.330 Top Slab Rebar Installation 8 29-Feb-24 09-Mar-24 Top Slab Rebar Installation

JAH-Z3-ST-S6-TS.340 Top Slab Concrete Casting 1 10-Mar-24 10-Mar-24 Top Slab Concrete Casting

JAH-Z3-ST-S6-TS.342 Curing work 7 11-Mar-24 18-Mar-24 Curing work

JAH-Z3-ST-S6-TS.345 Top Slab Formwork Removel 2 19-Mar-24 20-Mar-24 Top Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
289 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S6-TS.350 Waterproofing for Top Slab 12 21-Mar-24 03-Apr-24 Waterproofing for Top Slab

FINISHING WORK 30 04-Apr-24 12-May-24 12-May-24, FINISHING WORK


JAH-Z3-ST-S6-FW.355 Above Top Slab Formwork Installation for Plain Concrete 7 04-Apr-24 15-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S6-FW.360 Plain Concrete Casting Inc. Curing Time 7 16-Apr-24 23-Apr-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S6-FW.365 Mass Concrete Casting for Base Slab Top Layer 1 24-Apr-24 24-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S6-FW.367 Curing work 7 25-Apr-24 02-May-24 Curing work

JAH-Z3-ST-S6-FW.370 Concrete Protective coating 8 04-May-24 12-May-24 Concrete Protective coating

STA. 1+114 ~ 1+134 171 08-Nov-23 28-May-24 28-May-24, STA. 1+114 ~ 1+134
BASE SLAB 24 08-Nov-23 05-Dec-23 05-Dec-23, BASE SLAB
JAH-Z3-ST-S7-BS.100 Lean Concrete for Base Slab 1 08-Nov-23 08-Nov-23 Lean Concrete for Base Slab

JAH-Z3-ST-S7-BS.105 Waterproofing for Lean Concrete 1 09-Nov-23 09-Nov-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S7-BS.110 Base Slab Rebar Installation 7 11-Nov-23 18-Nov-23 Base Slab Rebar Installation

JAH-Z3-ST-S7-BS.115 Base Slab Formwork Installation 5 19-Nov-23 23-Nov-23 Base Slab Formwork Installation

JAH-Z3-ST-S7-BS.120 Base Slab Concrete Casting 1 25-Nov-23 25-Nov-23 Base Slab Concrete Casting

JAH-Z3-ST-S7-BS.122 Curing work 7 26-Nov-23 03-Dec-23 Curing work

JAH-Z3-ST-S7-BS.125 Base Slab Formwork Removel 2 04-Dec-23 05-Dec-23 Base Slab Formwork Removel

COLUMNS 23 06-Dec-23 01-Jan-24 01-Jan-24, COLUMNS


JAH-Z3-ST-S7-CL.100 Column Rebar Installation 8 06-Dec-23 14-Dec-23 Column Rebar Installation

JAH-Z3-ST-S7-CL.105 Column Formwork Installation 7 16-Dec-23 23-Dec-23 Column Formwork Installation

JAH-Z3-ST-S7-CL.110 Column Concrete Casting 1 24-Dec-23 24-Dec-23 Column Concrete Casting

JAH-Z3-ST-S7-CL.115 Form Work Removal and Curing 7 25-Dec-23 01-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 06-Dec-23 17-Jan-24 17-Jan-24, TUNNEL WALLS


JAH-Z3-ST-S7-TW.100 Tunnel Walls Rebar Installation 8 06-Dec-23 14-Dec-23 Tunnel Walls Rebar Installation

JAH-Z3-ST-S7-TW.104 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 06-Dec-23 14-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S7-TW.105 Tunnel Formwork Installation 7 16-Dec-23 23-Dec-23 Tunnel Formwork Installation

JAH-Z3-ST-S7-TW.110 Tunnel Walls Concrete Casting 1 24-Dec-23 24-Dec-23 Tunnel Walls Concrete Casting

JAH-Z3-ST-S7-TW.112 Curing work 7 25-Dec-23 01-Jan-24 Curing work

JAH-Z3-ST-S7-TW.120 Tunnel Walls Formwork Removel 2 02-Jan-24 03-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S7-TW.125 Tunnel Wall Waterproofing 12 04-Jan-24 17-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 04-Jan-24 07-Feb-24 07-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S7-MS.249 Middle Slab Scaffold and Formwork Installation 5 04-Jan-24 09-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S7-MS.250 Middle Slab Rebar Installation 8 10-Jan-24 18-Jan-24 Middle Slab Rebar Installation

JAH-Z3-ST-S7-MS.255 Middle Slab Vertical Formwork Installation 7 20-Jan-24 27-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S7-MS.260 Middle Slab Concrete Casting 1 28-Jan-24 28-Jan-24 Middle Slab Concrete Casting

JAH-Z3-ST-S7-MS.262 Curing work 7 29-Jan-24 05-Feb-24 Curing work

JAH-Z3-ST-S7-MS.270 Middle Slab Formwork Removel 2 06-Feb-24 07-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 08-Feb-24 07-Mar-24 07-Mar-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S7-UCW.220Utility Culvert Walls Rebar Installation 8 08-Feb-24 17-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S7-UCW.225Utility Culvert Walls Formwork Installation 7 18-Feb-24 25-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S7-UCW.230Utility Culvert Walls Concrete Casting 1 26-Feb-24 26-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S7-UCW.232Curing work 7 27-Feb-24 05-Mar-24 Curing work

JAH-Z3-ST-S7-UCW.235Utility Culvert Walls Walls Formwork Removel 2 06-Mar-24 07-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 09-Mar-24 23-Apr-24 23-Apr-24, TOP SLAB


JAH-Z3-ST-S7-TS.374 Top Slab Formwork Installation 7 09-Mar-24 16-Mar-24 Top Slab Formwork Installation

JAH-Z3-ST-S7-TS.375 Top Slab Rebar Installation 8 17-Mar-24 25-Mar-24 Top Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
290 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S7-TS.385 Top Slab Concrete Casting 1 26-Mar-24 26-Mar-24 Top Slab Concrete Casting

JAH-Z3-ST-S7-TS.387 Curing work 7 27-Mar-24 03-Apr-24 Curing work

JAH-Z3-ST-S7-TS.390 Top Slab Formwork Removel 2 04-Apr-24 06-Apr-24 Top Slab Formwork Removel

JAH-Z3-ST-S7-TS.395 Waterproofing for Top Slab 12 07-Apr-24 23-Apr-24 Waterproofing for Top Slab

FINISHING WORK 30 24-Apr-24 28-May-24 28-May-24, FINISHING WORK


JAH-Z3-ST-S7-FW.400 Above Top Slab Formwork Installation for Plain Concrete 7 24-Apr-24 01-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S7-FW.405 Plain Concrete Casting Inc. Curing Time 7 02-May-24 09-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S7-FW.410 Mass Concrete Casting for Base Slab Top Layer 1 11-May-24 11-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S7-FW.412 Curing work 7 12-May-24 19-May-24 Curing work

JAH-Z3-ST-S7-FW.415 Concrete Protective coating 8 20-May-24 28-May-24 Concrete Protective coating

STA. 1+134 ~ 1+154 169 26-Nov-23 12-Jun-24 12-Jun-24, STA. 1+134 ~ 1+154
BASE SLAB 25 26-Nov-23 24-Dec-23 24-Dec-23, BASE SLAB
JAH-Z3-ST-S8-BS.100 Lean Concrete for Base Slab 1 26-Nov-23 26-Nov-23 Lean Concrete for Base Slab

JAH-Z3-ST-S8-BS.105 Waterproofing for Lean Concrete 1 27-Nov-23 27-Nov-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S8-BS.110 Base Slab Rebar Installation 8 28-Nov-23 06-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S8-BS.115 Base Slab Formwork Installation 5 07-Dec-23 12-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S8-BS.120 Base Slab Concrete Casting 1 13-Dec-23 13-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S8-BS.122 Curing work 7 14-Dec-23 21-Dec-23 Curing work

JAH-Z3-ST-S8-BS.125 Base Slab Formwork Removel 2 23-Dec-23 24-Dec-23 Base Slab Formwork Removel

COLUMNS 23 25-Dec-23 20-Jan-24 20-Jan-24, COLUMNS


JAH-Z3-ST-S8-CL.100 Column Rebar Installation 8 25-Dec-23 02-Jan-24 Column Rebar Installation

JAH-Z3-ST-S8-CL.105 Column Formwork Installation 7 03-Jan-24 10-Jan-24 Column Formwork Installation

JAH-Z3-ST-S8-CL.110 Column Concrete Casting 1 11-Jan-24 11-Jan-24 Column Concrete Casting

JAH-Z3-ST-S8-CL.115 Form Work Removal and Curing 7 13-Jan-24 20-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 25-Dec-23 05-Feb-24 05-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S8-TW.100 Tunnel Walls Rebar Installation 8 25-Dec-23 02-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S8-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 25-Dec-23 02-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S8-TW.105 Tunnel Formwork Installation 7 03-Jan-24 10-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S8-TW.110 Tunnel Walls Concrete Casting 1 11-Jan-24 11-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S8-TW.112 Curing work 7 13-Jan-24 20-Jan-24 Curing work

JAH-Z3-ST-S8-TW.120 Tunnel Walls Formwork Removel 2 21-Jan-24 22-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S8-TW.125 Tunnel Wall Waterproofing 12 23-Jan-24 05-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 23-Jan-24 26-Feb-24 26-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S8-MS.274 Middle Slab Scaffold and Formwork Installation 5 23-Jan-24 28-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S8-MS.275 Middle Slab Rebar Installation 8 29-Jan-24 06-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S8-MS.280 Middle Slab Vertical Formwork Installation 7 07-Feb-24 14-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S8-MS.285 Middle Slab Concrete Casting 1 15-Feb-24 15-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S8-MS.290 Curing work 7 17-Feb-24 24-Feb-24 Curing work

JAH-Z3-ST-S8-MS.295 Middle Slab Formwork Removel 2 25-Feb-24 26-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 27-Feb-24 26-Mar-24 26-Mar-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S8-UCW.240Utility Culvert Walls Rebar Installation 8 27-Feb-24 06-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S8-UCW.245Utility Culvert Walls Formwork Installation 7 07-Mar-24 14-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S8-UCW.250Utility Culvert Walls Concrete Casting 1 16-Mar-24 16-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S8-UCW.252Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z3-ST-S8-UCW.255Utility Culvert Walls Walls Formwork Removel 2 25-Mar-24 26-Mar-24 Utility Culvert Walls Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
291 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 37 27-Mar-24 12-May-24 12-May-24, TOP SLAB
JAH-Z3-ST-S8-TS.419 Top Slab Formwork Installation 7 27-Mar-24 03-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S8-TS.420 Top Slab Rebar Installation 8 04-Apr-24 16-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S8-TS.430 Top Slab Concrete Casting 1 17-Apr-24 17-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S8-TS.432 Curing work 7 18-Apr-24 25-Apr-24 Curing work

JAH-Z3-ST-S8-TS.435 Top Slab Formwork Removel 2 27-Apr-24 28-Apr-24 Top Slab Formwork Removel

JAH-Z3-ST-S8-TS.440 Waterproofing for Top Slab 12 29-Apr-24 12-May-24 Waterproofing for Top Slab

FINISHING WORK 27 13-May-24 12-Jun-24 12-Jun-24, FINISHING WORK


JAH-Z3-ST-S8-FW.445 Above Top Slab Formwork Installation for Plain Concrete 7 13-May-24 20-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S8-FW.450 Plain Concrete Casting Inc. Curing Time 7 21-May-24 28-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S8-FW.455 Mass Concrete Casting for Base Slab Top Layer 1 29-May-24 29-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S8-FW.457 Curing work 7 30-May-24 06-Jun-24 Curing work

JAH-Z3-ST-S8-FW.460 Concrete Protective coating 5 08-Jun-24 12-Jun-24 Concrete Protective coating

STA. 1+154 ~ 1+174 166 28-Nov-23 11-Jun-24 11-Jun-24, STA. 1+154 ~ 1+174
BASE SLAB 25 28-Nov-23 26-Dec-23 26-Dec-23, BASE SLAB
JAH-Z3-ST-S9-BS.100 Lean Concrete for Base Slab 1 28-Nov-23 28-Nov-23 Lean Concrete for Base Slab

JAH-Z3-ST-S9-BS.105 Waterproofing for Lean Concrete 1 29-Nov-23 29-Nov-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S9-BS.110 Base Slab Rebar Installation 8 30-Nov-23 09-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S9-BS.115 Base Slab Formwork Installation 5 10-Dec-23 14-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S9-BS.120 Base Slab Concrete Casting 1 16-Dec-23 16-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S9-BS.122 Curing work 7 17-Dec-23 24-Dec-23 Curing work

JAH-Z3-ST-S9-BS.125 Base Slab Formwork Removel 2 25-Dec-23 26-Dec-23 Base Slab Formwork Removel

COLUMNS 22 27-Dec-23 21-Jan-24 21-Jan-24, COLUMNS


JAH-Z3-ST-S9-CL.100 Column Rebar Installation 7 27-Dec-23 03-Jan-24 Column Rebar Installation

JAH-Z3-ST-S9-CL.105 Column Formwork Installation 7 04-Jan-24 11-Jan-24 Column Formwork Installation

JAH-Z3-ST-S9-CL.110 Column Concrete Casting 1 13-Jan-24 13-Jan-24 Column Concrete Casting

JAH-Z3-ST-S9-CL.115 Form Work Removal and Curing 7 14-Jan-24 21-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 27-Dec-23 07-Feb-24 07-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S9-TW.100 Tunnel Walls Rebar Installation 8 27-Dec-23 04-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S9-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 27-Dec-23 04-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S9-TW.105 Tunnel Formwork Installation 7 06-Jan-24 13-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S9-TW.110 Tunnel Walls Concrete Casting 1 14-Jan-24 14-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S9-TW.112 Curing work 7 15-Jan-24 22-Jan-24 Curing work

JAH-Z3-ST-S9-TW.120 Tunnel Walls Formwork Removel 2 23-Jan-24 24-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S9-TW.125 Tunnel Wall Waterproofing 12 25-Jan-24 07-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 29 25-Jan-24 27-Feb-24 27-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S9-MS.299 Middle Slab Scaffold and Formwork Installation 5 25-Jan-24 30-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S9-MS.300 Middle Slab Rebar Installation 7 31-Jan-24 07-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S9-MS.305 Middle Slab Vertical Formwork Installation 7 08-Feb-24 15-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S9-MS.310 Middle Slab Concrete Casting 1 17-Feb-24 17-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S9-MS.315 Curing work 7 18-Feb-24 25-Feb-24 Curing work

JAH-Z3-ST-S9-MS.320 Middle Slab Formwork Removel 2 26-Feb-24 27-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 24 28-Feb-24 26-Mar-24 26-Mar-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S9-UCW.260Utility Culvert Walls Rebar Installation 7 28-Feb-24 06-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S9-UCW.265Utility Culvert Walls Formwork Installation 7 07-Mar-24 14-Mar-24 Utility Culvert Walls Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
292 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S9-UCW.270Utility Culvert Walls Concrete Casting 1 16-Mar-24 16-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S9-UCW.272Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z3-ST-S9-UCW.275Utility Culvert Walls Walls Formwork Removel 2 25-Mar-24 26-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 33 27-Mar-24 07-May-24 07-May-24, TOP SLAB


JAH-Z3-ST-S9-TS.464 Top Slab Formwork Installation 7 27-Mar-24 03-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S9-TS.465 Top Slab Rebar Installation 6 04-Apr-24 14-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S9-TS.475 Top Slab Concrete Casting 1 15-Apr-24 15-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S9-TS.477 Curing work 7 16-Apr-24 23-Apr-24 Curing work

JAH-Z3-ST-S9-TS.480 Top Slab Formwork Removel 2 24-Apr-24 25-Apr-24 Top Slab Formwork Removel

JAH-Z3-ST-S9-TS.485 Waterproofing for Top Slab 10 27-Apr-24 07-May-24 Waterproofing for Top Slab

FINISHING WORK 30 08-May-24 11-Jun-24 11-Jun-24, FINISHING WORK


JAH-Z3-ST-S9-FW.490 Above Top Slab Formwork Installation for Plain Concrete 7 08-May-24 15-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S9-FW.495 Plain Concrete Casting Inc. Curing Time 7 16-May-24 23-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S9-FW.500 Mass Concrete Casting for Base Slab Top Layer 1 25-May-24 25-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S9-FW.502 Curing Time 7 26-May-24 02-Jun-24 Curing Time

JAH-Z3-ST-S9-FW.505 Concrete Protective coating 8 03-Jun-24 11-Jun-24 Concrete Protective coating

STA. 1+174 ~ 1+194 166 28-Nov-23 11-Jun-24 11-Jun-24, STA. 1+174 ~ 1+194
BASE SLAB 25 28-Nov-23 26-Dec-23 26-Dec-23, BASE SLAB
JAH-Z3-ST-S10-BS.100Lean Concrete for Base Slab 1 28-Nov-23 28-Nov-23 Lean Concrete for Base Slab

JAH-Z3-ST-S10-BS.105Waterproofing for Lean Concrete 1 29-Nov-23 29-Nov-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S10-BS.110 Base Slab Rebar Installation 8 30-Nov-23 09-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S10-BS.115 Base Slab Formwork Installation 5 10-Dec-23 14-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S10-BS.120Base Slab Concrete Casting 1 16-Dec-23 16-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S10-BS.122Curing work 7 17-Dec-23 24-Dec-23 Curing work

JAH-Z3-ST-S10-BS.125Base Slab Formwork Removel 2 25-Dec-23 26-Dec-23 Base Slab Formwork Removel

COLUMNS 23 27-Dec-23 22-Jan-24 22-Jan-24, COLUMNS


JAH-Z3-ST-S10-CL.100Column Rebar Installation 8 27-Dec-23 04-Jan-24 Column Rebar Installation

JAH-Z3-ST-S10-CL.105Column Formwork Installation 7 06-Jan-24 13-Jan-24 Column Formwork Installation

JAH-Z3-ST-S10-CL.110 Column Concrete Casting 1 14-Jan-24 14-Jan-24 Column Concrete Casting

JAH-Z3-ST-S10-CL.115 Form Work Removal and Curing 7 15-Jan-24 22-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 27-Dec-23 07-Feb-24 07-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S10-TW.100Tunnel Walls Rebar Installation 8 27-Dec-23 04-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S10-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 27-Dec-23 04-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S10-TW.105Tunnel Formwork Installation 7 06-Jan-24 13-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S10-TW.110Tunnel Walls Concrete Casting 1 14-Jan-24 14-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S10-TW.112Curing work 7 15-Jan-24 22-Jan-24 Curing work

JAH-Z3-ST-S10-TW.120Tunnel Walls Formwork Removel 2 23-Jan-24 24-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S10-TW.125Tunnel Wall Waterproofing 12 25-Jan-24 07-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 25-Jan-24 28-Feb-24 28-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S10-MS.324Middle Slab Scaffold and Formwork Installation 5 25-Jan-24 30-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S10-MS.325Middle Slab Rebar Installation 8 31-Jan-24 08-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S10-MS.330Middle Slab Vertical Formwork Installation 7 10-Feb-24 17-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S10-MS.335Middle Slab Concrete Casting 1 18-Feb-24 18-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S10-MS.340Curing work 7 19-Feb-24 26-Feb-24 Curing work

JAH-Z3-ST-S10-MS.345Middle Slab Formwork Removel 2 27-Feb-24 28-Feb-24 Middle Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
293 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UTILITY CULVERT WALLS 25 29-Feb-24 28-Mar-24 28-Mar-24, UTILITY CULVERT WALLS
JAH-Z3-ST-S10-CW.280Utility Culvert Walls Rebar Installation 8 29-Feb-24 09-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S10-CW.285Utility Culvert Walls Formwork Installation 7 10-Mar-24 17-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S10-CW.290Utility Culvert Walls Concrete Casting 1 18-Mar-24 18-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S10-CW.292Curing work 7 19-Mar-24 26-Mar-24 Curing work

JAH-Z3-ST-S10-CW.295Utility Culvert Walls Walls Formwork Removel 2 27-Mar-24 28-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 30-Mar-24 14-May-24 14-May-24, TOP SLAB


JAH-Z3-ST-S10-TS.509 Top Slab Formwork Installation 7 30-Mar-24 06-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S10-TS.510 Top Slab Rebar Installation 8 07-Apr-24 18-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S10-TS.520 Top Slab Concrete Casting 1 20-Apr-24 20-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S10-TS.522 Curing work 7 21-Apr-24 28-Apr-24 Curing work

JAH-Z3-ST-S10-TS.525 Top Slab Formwork Removel 2 29-Apr-24 30-Apr-24 Top Slab Formwork Removel

JAH-Z3-ST-S10-TS.530 Waterproofing for Top Slab 12 01-May-24 14-May-24 Waterproofing for Top Slab

FINISHING WORK 24 15-May-24 11-Jun-24 11-Jun-24, FINISHING WORK


JAH-Z3-ST-S10-TS.535 Above Top Slab Formwork Installation for Plain Concrete 7 15-May-24 22-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S10-TS.540 Plain Concrete Casting 1 23-May-24 23-May-24 Plain Concrete Casting

JAH-Z3-ST-S10-TS.545 Mass Concrete Casting for Base Slab Top Layer 1 25-May-24 25-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S10-TS.547 Curing work 7 26-May-24 02-Jun-24 Curing work

JAH-Z3-ST-S10-TS.550 Concrete Protective coating 8 03-Jun-24 11-Jun-24 Concrete Protective coating

STA. 1+194 ~ 1+214 166 30-Nov-23 13-Jun-24 13-Jun-24, STA. 1+194 ~ 1+214
BASE SLAB 25 30-Nov-23 28-Dec-23 28-Dec-23, BASE SLAB
JAH-Z3-ST-S11-BS.100 Lean Concrete for Base Slab 1 30-Nov-23 30-Nov-23 Lean Concrete for Base Slab

JAH-Z3-ST-S11-BS.105 Waterproofing for Lean Concrete 1 02-Dec-23 02-Dec-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S11-BS.110 Base Slab Rebar Installation 8 03-Dec-23 11-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S11-BS.115 Base Slab Formwork Installation 5 12-Dec-23 17-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S11-BS.120 Base Slab Concrete Casting 1 18-Dec-23 18-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S11-BS.122 Curing work 7 19-Dec-23 26-Dec-23 Curing work

JAH-Z3-ST-S11-BS.125 Base Slab Formwork Removel 2 27-Dec-23 28-Dec-23 Base Slab Formwork Removel

COLUMNS 23 30-Dec-23 24-Jan-24 24-Jan-24, COLUMNS


JAH-Z3-ST-S11-CL.100 Column Rebar Installation 8 30-Dec-23 07-Jan-24 Column Rebar Installation

JAH-Z3-ST-S11-CL.105 Column Formwork Installation 7 08-Jan-24 15-Jan-24 Column Formwork Installation

JAH-Z3-ST-S11-CL.110 Column Concrete Casting 1 16-Jan-24 16-Jan-24 Column Concrete Casting

JAH-Z3-ST-S11-CL.115 Form Work Removal and Curing 7 17-Jan-24 24-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 30-Dec-23 10-Feb-24 10-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S11-TW.100Tunnel Walls Rebar Installation 8 30-Dec-23 07-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S11-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 30-Dec-23 07-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S11-TW.105Tunnel Formwork Installation 7 08-Jan-24 15-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S11-TW.110Tunnel Walls Concrete Casting 1 16-Jan-24 16-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S11-TW.112Curing work 7 17-Jan-24 24-Jan-24 Curing work

JAH-Z3-ST-S11-TW.120Tunnel Walls Formwork Removel 2 25-Jan-24 27-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S11-TW.125Tunnel Wall Waterproofing 12 28-Jan-24 10-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-Jan-24 02-Mar-24 02-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S11-MS.349Middle Slab Scaffold and Formwork Installation 5 28-Jan-24 01-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S11-MS.350Middle Slab Rebar Installation 8 03-Feb-24 11-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S11-MS.355Middle Slab Vertical Formwork Installation 7 12-Feb-24 19-Feb-24 Middle Slab Vertical Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
294 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S11-MS.360Middle Slab Concrete Casting 1 20-Feb-24 20-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S11-MS.365Curing work 7 21-Feb-24 28-Feb-24 Curing work

JAH-Z3-ST-S11-MS.370Middle Slab Formwork Removel 2 29-Feb-24 02-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 03-Mar-24 31-Mar-24 31-Mar-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S11-CW.300Utility Culvert Walls Rebar Installation 8 03-Mar-24 11-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S11-CW.305Utility Culvert Walls Formwork Installation 7 12-Mar-24 19-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S11-CW.310Utility Culvert Walls Concrete Casting 1 20-Mar-24 20-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S11-CW.312Curing work 7 21-Mar-24 28-Mar-24 Curing work

JAH-Z3-ST-S11-CW.315Utility Culvert Walls Walls Formwork Removel 2 30-Mar-24 31-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 35 01-Apr-24 14-May-24 14-May-24, TOP SLAB


JAH-Z3-ST-S11-TS.554 Top Slab Formwork Installation 7 01-Apr-24 08-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S11-TS.555 Top Slab Rebar Installation 8 13-Apr-24 21-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S11-TS.565 Top Slab Concrete Casting 1 22-Apr-24 22-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S11-TS.567 Curing work 7 23-Apr-24 30-Apr-24 Curing work

JAH-Z3-ST-S11-TS.570 Top Slab Formwork Removel 2 01-May-24 02-May-24 Top Slab Formwork Removel

JAH-Z3-ST-S11-TS.575 Waterproofing for Top Slab 10 04-May-24 14-May-24 Waterproofing for Top Slab

FINISHING WORK 26 15-May-24 13-Jun-24 13-Jun-24, FINISHING WORK


JAH-Z3-ST-S11-FW.580Above Top Slab Formwork Installation for Plain Concrete 5 15-May-24 20-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S11-FW.585Plain Concrete Casting Inc. Curing Time 5 21-May-24 26-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S11-FW.590Mass Concrete Casting for Base Slab Top Layer 1 27-May-24 27-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S11-FW.592Curing work 7 28-May-24 04-Jun-24 Curing work

JAH-Z3-ST-S11-FW.595Concrete Protective coating 8 05-Jun-24 13-Jun-24 Concrete Protective coating

STA. 1+214 ~ 1+239 165 03-Dec-23 19-Jun-24 19-Jun-24, STA. 1+214 ~ 1+239
BASE SLAB 25 03-Dec-23 31-Dec-23 31-Dec-23, BASE SLAB
JAH-Z3-ST-S12-BS.100Lean Concrete for Base Slab 1 03-Dec-23 03-Dec-23 Lean Concrete for Base Slab

JAH-Z3-ST-S12-BS.105Waterproofing for Lean Concrete 1 04-Dec-23 04-Dec-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S12-BS.110 Base Slab Rebar Installation 8 05-Dec-23 13-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S12-BS.115 Base Slab Formwork Installation 5 14-Dec-23 19-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S12-BS.120Base Slab Concrete Casting 1 20-Dec-23 20-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S12-BS.122Curing work 7 21-Dec-23 28-Dec-23 Curing work

JAH-Z3-ST-S12-BS.125Base Slab Formwork Removel 2 30-Dec-23 31-Dec-23 Base Slab Formwork Removel

COLUMNS 23 01-Jan-24 27-Jan-24 27-Jan-24, COLUMNS


JAH-Z3-ST-S12-CL.100Column Rebar Installation 8 01-Jan-24 09-Jan-24 Column Rebar Installation

JAH-Z3-ST-S12-CL.105Column Formwork Installation 7 10-Jan-24 17-Jan-24 Column Formwork Installation

JAH-Z3-ST-S12-CL.110 Column Concrete Casting 1 18-Jan-24 18-Jan-24 Column Concrete Casting

JAH-Z3-ST-S12-CL.115 Form Work Removal and Curing 7 20-Jan-24 27-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 01-Jan-24 12-Feb-24 12-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S12-TW.100Tunnel Walls Rebar Installation 8 01-Jan-24 09-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S12-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 01-Jan-24 09-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S12-TW.105Tunnel Formwork Installation 7 10-Jan-24 17-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S12-TW.110Tunnel Walls Concrete Casting 1 18-Jan-24 18-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S12-TW.112Curing work 7 20-Jan-24 27-Jan-24 Curing work

JAH-Z3-ST-S12-TW.120Tunnel Walls Formwork Removel 2 28-Jan-24 29-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S12-TW.125Tunnel Wall Waterproofing 12 30-Jan-24 12-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 30-Jan-24 04-Mar-24 04-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
295 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S12-MS.374Middle Slab Scaffold and Formwork Installation 5 30-Jan-24 04-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S12-MS.375Middle Slab Rebar Installation 8 05-Feb-24 13-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S12-MS.380Middle Slab Vertical Formwork Installation 7 14-Feb-24 21-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S12-MS.385Middle Slab Concrete Casting 1 22-Feb-24 22-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S12-MS.390Curing work 7 24-Feb-24 02-Mar-24 Curing work

JAH-Z3-ST-S12-MS.395Middle Slab Formwork Removel 2 03-Mar-24 04-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 05-Mar-24 02-Apr-24 02-Apr-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S12-CW.320Utility Culvert Walls Rebar Installation 8 05-Mar-24 13-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S12-CW.325Utility Culvert Walls Formwork Installation 7 14-Mar-24 21-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S12-CW.330Utility Culvert Walls Concrete Casting 1 23-Mar-24 23-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S12-CW.332Curing work 7 24-Mar-24 31-Mar-24 Curing work

JAH-Z3-ST-S12-CW.335Utility Culvert Walls Walls Formwork Removel 2 01-Apr-24 02-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 33 03-Apr-24 14-May-24 14-May-24, TOP SLAB


JAH-Z3-ST-S12-TS.599 Top Slab Formwork Installation 7 03-Apr-24 14-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S12-TS.600 Top Slab Rebar Installation 8 15-Apr-24 23-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S12-TS.610 Top Slab Concrete Casting 1 24-Apr-24 24-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S12-TS.612 Curing work 7 25-Apr-24 02-May-24 Curing work

JAH-Z3-ST-S12-TS.615 Top Slab Formwork Removel 2 04-May-24 05-May-24 Top Slab Formwork Removel

JAH-Z3-ST-S12-TS.620 Waterproofing for Top Slab 8 06-May-24 14-May-24 Waterproofing for Top Slab

FINISHING WORK 27 15-May-24 19-Jun-24 19-Jun-24, FINISHING WORK


JAH-Z3-ST-S12-FW.625Above Top Slab Formwork Installation for Plain Concrete 7 15-May-24 22-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S12-FW.630Plain Concrete Casting Inc. Curing Time 7 23-May-24 30-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S12-FW.635Mass Concrete Casting for Base Slab Top Layer 1 01-Jun-24 01-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S12-FW.637Curing work 7 02-Jun-24 09-Jun-24 Curing work

JAH-Z3-ST-S12-FW.640Concrete Protective coating 5 10-Jun-24 19-Jun-24 Concrete Protective coating

STA. 1+239 ~ 1+268 169 04-Dec-23 25-Jun-24 25-Jun-24, STA. 1+239 ~ 1+268
BASE SLAB 25 04-Dec-23 01-Jan-24 01-Jan-24, BASE SLAB
JAH-Z3-ST-S13-BS.100Lean Concrete for Base Slab 1 04-Dec-23 04-Dec-23 Lean Concrete for Base Slab

JAH-Z3-ST-S13-BS.105Waterproofing for Lean Concrete 1 05-Dec-23 05-Dec-23 Waterproofing for Lean Concrete

JAH-Z3-ST-S13-BS.110 Base Slab Rebar Installation 8 06-Dec-23 14-Dec-23 Base Slab Rebar Installation

JAH-Z3-ST-S13-BS.115 Base Slab Formwork Installation 5 16-Dec-23 20-Dec-23 Base Slab Formwork Installation

JAH-Z3-ST-S13-BS.120Base Slab Concrete Casting 1 21-Dec-23 21-Dec-23 Base Slab Concrete Casting

JAH-Z3-ST-S13-BS.122Curing work 7 23-Dec-23 30-Dec-23 Curing work

JAH-Z3-ST-S13-BS.125Base Slab Formwork Removel 2 31-Dec-23 01-Jan-24 Base Slab Formwork Removel

COLUMNS 23 02-Jan-24 28-Jan-24 28-Jan-24, COLUMNS


JAH-Z3-ST-S13-CL.100Column Rebar Installation 8 02-Jan-24 10-Jan-24 Column Rebar Installation

JAH-Z3-ST-S13-CL.105Column Formwork Installation 7 11-Jan-24 18-Jan-24 Column Formwork Installation

JAH-Z3-ST-S13-CL.110 Column Concrete Casting 1 20-Jan-24 20-Jan-24 Column Concrete Casting

JAH-Z3-ST-S13-CL.115 Form Work Removal and Curing 7 21-Jan-24 28-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 02-Jan-24 13-Feb-24 13-Feb-24, TUNNEL WALLS


JAH-Z3-ST-S13-TW.100Tunnel Walls Rebar Installation 8 02-Jan-24 10-Jan-24 Tunnel Walls Rebar Installation

JAH-Z3-ST-S13-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 02-Jan-24 10-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z3-ST-S13-TW.105Tunnel Formwork Installation 7 11-Jan-24 18-Jan-24 Tunnel Formwork Installation

JAH-Z3-ST-S13-TW.110Tunnel Walls Concrete Casting 1 20-Jan-24 20-Jan-24 Tunnel Walls Concrete Casting

JAH-Z3-ST-S13-TW.112Curing work 7 21-Jan-24 28-Jan-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
296 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ST-S13-TW.120Tunnel Walls Formwork Removel 2 29-Jan-24 30-Jan-24 Tunnel Walls Formwork Removel

JAH-Z3-ST-S13-TW.125Tunnel Wall Waterproofing 12 31-Jan-24 13-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 31-Jan-24 05-Mar-24 05-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z3-ST-S13-MS.399Middle Slab Scaffold and Formwork Installation 5 31-Jan-24 05-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z3-ST-S13-MS.400Middle Slab Rebar Installation 8 06-Feb-24 14-Feb-24 Middle Slab Rebar Installation

JAH-Z3-ST-S13-MS.405Middle Slab Vertical Formwork Installation 7 15-Feb-24 22-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z3-ST-S13-MS.410Middle Slab Concrete Casting 1 24-Feb-24 24-Feb-24 Middle Slab Concrete Casting

JAH-Z3-ST-S13-MS.415Curing work 7 25-Feb-24 03-Mar-24 Curing work

JAH-Z3-ST-S13-MS.420Middle Slab Formwork Removel 2 04-Mar-24 05-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 06-Mar-24 03-Apr-24 03-Apr-24, UTILITY CULVERT WALLS


JAH-Z3-ST-S13-CW.340Utility Culvert Walls Rebar Installation 8 06-Mar-24 14-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z3-ST-S13-CW.345Utility Culvert Walls Formwork Installation 7 16-Mar-24 23-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z3-ST-S13-CW.350Utility Culvert Walls Concrete Casting 1 24-Mar-24 24-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z3-ST-S13-CW.352Curing work 7 25-Mar-24 01-Apr-24 Curing work

JAH-Z3-ST-S13-CW.355Utility Culvert Walls Walls Formwork Removel 2 02-Apr-24 03-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 31 04-Apr-24 13-May-24 13-May-24, TOP SLAB


JAH-Z3-ST-S13-TS.644 Top Slab Formwork Installation 7 04-Apr-24 15-Apr-24 Top Slab Formwork Installation

JAH-Z3-ST-S13-TS.645 Top Slab Rebar Installation 8 16-Apr-24 24-Apr-24 Top Slab Rebar Installation

JAH-Z3-ST-S13-TS.655 Top Slab Concrete Casting 1 25-Apr-24 25-Apr-24 Top Slab Concrete Casting

JAH-Z3-ST-S13-TS.657 Curing work 7 27-Apr-24 04-May-24 Curing work

JAH-Z3-ST-S13-TS.660 Top Slab Formwork Removel 3 05-May-24 07-May-24 Top Slab Formwork Removel

JAH-Z3-ST-S13-TS.665 Waterproofing for Top Slab 5 08-May-24 13-May-24 Waterproofing for Top Slab

FINISHING WORK 33 14-May-24 25-Jun-24 25-Jun-24, FINISHING WORK


JAH-Z3-ST-S13-TS.670 Above Top Slab Formwork Installation for Plain Concrete 8 14-May-24 22-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z3-ST-S13-TS.675 Plain Concrete Casting Inc. Curing Time 7 23-May-24 30-May-24 Plain Concrete Casting Inc. Curing Time

JAH-Z3-ST-S13-TS.680 Mass Concrete Casting for Base Slab Top Layer 1 01-Jun-24 01-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z3-ST-S13-TS.682 Curing work 7 02-Jun-24 09-Jun-24 Curing work

JAH-Z3-ST-S13-TS.685 Concrete Protective Coating 5 20-Jun-24 25-Jun-24 Concrete Protective Coating

EGRESS STAIR-5 (ZONE-03) 236 21-Sep-23 01-Jul-24 01-Jul-24, EGRESS STAIR-5 (ZONE-03)
WALL AND 1ST FLIGHT 31 21-Sep-23 28-Oct-23 28-Oct-23, WALL AND 1ST FLIGHT
Z3-EGR-STAIR #5.100 Excavation for Foundation 6 21-Sep-23 28-Sep-23 Excavation for Foundation

Z3-EGR-STAIR #5.105 Foundation Blinding Concrete casting 1 30-Sep-23 30-Sep-23 Foundation Blinding Concrete casting

Z3-EGR-STAIR #5.110 Foundation Rebar Installation 3 01-Oct-23 03-Oct-23 Foundation Rebar Installation

Z3-EGR-STAIR #5.115 Foundation Formwork installation 3 04-Oct-23 07-Oct-23 Foundation Formwork installation

Z3-EGR-STAIR #5.120 Foundation Concrete casting 1 08-Oct-23 08-Oct-23 Foundation Concrete casting

Z3-EGR-STAIR #5.125 Wall and Stair Rebar Installation 4 09-Oct-23 12-Oct-23 Wall and Stair Rebar Installation

Z3-EGR-STAIR #5.130 Wall and Stair Form work Installation 6 14-Oct-23 19-Oct-23 Wall and Stair Form work Installation

Z3-EGR-STAIR #5.135 Form Removal and Curing 7 21-Oct-23 28-Oct-23 Form Removal and Curing

WALL AND 2ND FLIGHT 17 29-Oct-23 16-Nov-23 16-Nov-23, WALL AND 2ND FLIGHT
Z3-EGR-STAIR #5.140 Stair Form work Installation 3 29-Oct-23 31-Oct-23 Stair Form work Installation

Z3-EGR-STAIR #5.145 Wall Rebar Installation 3 01-Nov-23 04-Nov-23 Wall Rebar Installation

Z3-EGR-STAIR #5.150 Wall Form work Installation 3 05-Nov-23 07-Nov-23 Wall Form work Installation

Z3-EGR-STAIR #5.155 Wall and Stair Concrete casting 1 08-Nov-23 08-Nov-23 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.160 Form Removal and Curing 7 09-Nov-23 16-Nov-23 Form Removal and Curing

WALL AND 3RD FLIGHT 17 18-Nov-23 06-Dec-23 06-Dec-23, WALL AND 3RD FLIGHT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
297 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z3-EGR-STAIR #5.165 Stair Form work Installation 3 18-Nov-23 20-Nov-23 Stair Form work Installation

Z3-EGR-STAIR #5.170 Wall Rebar Installation 3 21-Nov-23 23-Nov-23 Wall Rebar Installation

Z3-EGR-STAIR #5.175 Wall Form work Installation 3 25-Nov-23 27-Nov-23 Wall Form work Installation

Z3-EGR-STAIR #5.180 Wall and Stair Concrete casting 1 28-Nov-23 28-Nov-23 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.185 Form Removal and Curing 7 29-Nov-23 06-Dec-23 Form Removal and Curing

WALL AND 4TH FLIGHT 17 07-Dec-23 26-Dec-23 26-Dec-23, WALL AND 4TH FLIGHT
Z3-EGR-STAIR #5.190 Stair Form work Installation 3 07-Dec-23 10-Dec-23 Stair Form work Installation

Z3-EGR-STAIR #5.195 Wall Rebar Installation 3 11-Dec-23 13-Dec-23 Wall Rebar Installation

Z3-EGR-STAIR #5.200 Wall Form work Installation 3 14-Dec-23 17-Dec-23 Wall Form work Installation

Z3-EGR-STAIR #5.205 Wall and Stair Concrete casting 1 18-Dec-23 18-Dec-23 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.210 Form Removal and Curing 7 19-Dec-23 26-Dec-23 Form Removal and Curing

WALL AND 5TH FLIGHT 17 27-Dec-23 15-Jan-24 15-Jan-24, WALL AND 5TH FLIGHT
Z3-EGR-STAIR #5.215 Stair Form work Installation 3 27-Dec-23 30-Dec-23 Stair Form work Installation

Z3-EGR-STAIR #5.220 Wall Rebar Installation 3 31-Dec-23 02-Jan-24 Wall Rebar Installation

Z3-EGR-STAIR #5.225 Wall Form work Installation 3 03-Jan-24 06-Jan-24 Wall Form work Installation

Z3-EGR-STAIR #5.230 Wall and Stair Concrete casting 1 07-Jan-24 07-Jan-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.235 Form Removal and Curing 7 08-Jan-24 15-Jan-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 16-Jan-24 04-Feb-24 04-Feb-24, WALL AND 6TH FLIGHT
Z3-EGR-STAIR #5.240 Stair Form work Installation 3 16-Jan-24 18-Jan-24 Stair Form work Installation

Z3-EGR-STAIR #5.245 Wall Rebar Installation 3 20-Jan-24 22-Jan-24 Wall Rebar Installation

Z3-EGR-STAIR #5.250 Wall Form work Installation 3 23-Jan-24 25-Jan-24 Wall Form work Installation

Z3-EGR-STAIR #5.255 Wall and Stair Concrete casting 1 27-Jan-24 27-Jan-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.260 Form Removal and Curing 7 28-Jan-24 04-Feb-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 05-Feb-24 24-Feb-24 24-Feb-24, WALL AND 7TH FLIGHT
Z3-EGR-STAIR #5.265 Stair Form work Installation 3 05-Feb-24 07-Feb-24 Stair Form work Installation

Z3-EGR-STAIR #5.270 Wall Rebar Installation 3 08-Feb-24 11-Feb-24 Wall Rebar Installation

Z3-EGR-STAIR #5.275 Wall Form work Installation 3 12-Feb-24 14-Feb-24 Wall Form work Installation

Z3-EGR-STAIR #5.280 Wall and Stair Concrete casting 1 15-Feb-24 15-Feb-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.285 Form Removal and Curing 7 17-Feb-24 24-Feb-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 25-Feb-24 14-Mar-24 14-Mar-24, WALL AND 8TH FLIGHT
Z3-EGR-STAIR #5.290 Stair Form work Installation 3 25-Feb-24 27-Feb-24 Stair Form work Installation

Z3-EGR-STAIR #5.295 Wall Rebar Installation 3 28-Feb-24 02-Mar-24 Wall Rebar Installation

Z3-EGR-STAIR #5.300 Wall Form work Installation 3 03-Mar-24 05-Mar-24 Wall Form work Installation

Z3-EGR-STAIR #5.305 Wall and Stair Concrete casting 1 06-Mar-24 06-Mar-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.310 Form Removal and Curing 7 07-Mar-24 14-Mar-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 16-Mar-24 03-Apr-24 03-Apr-24, WALL AND 9TH FLIGHT
Z3-EGR-STAIR #5.315 Stair Form work Installation 3 16-Mar-24 18-Mar-24 Stair Form work Installation

Z3-EGR-STAIR #5.320 Wall Rebar Installation 3 19-Mar-24 21-Mar-24 Wall Rebar Installation

Z3-EGR-STAIR #5.325 Wall Form work Installation 3 23-Mar-24 25-Mar-24 Wall Form work Installation

Z3-EGR-STAIR #5.330 Wall and Stair Concrete casting 1 26-Mar-24 26-Mar-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.335 Form Removal and Curing 7 27-Mar-24 03-Apr-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 04-Apr-24 27-Apr-24 27-Apr-24, WALL AND 10TH FLIGHT
Z3-EGR-STAIR #5.340 Stair Form work Installation 3 04-Apr-24 07-Apr-24 Stair Form work Installation

Z3-EGR-STAIR #5.345 Wall Rebar Installation 3 08-Apr-24 14-Apr-24 Wall Rebar Installation

Z3-EGR-STAIR #5.350 Wall Form work Installation 3 15-Apr-24 17-Apr-24 Wall Form work Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
298 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z3-EGR-STAIR #5.355 Wall and Stair Concrete casting 1 18-Apr-24 18-Apr-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.360 Form Removal and Curing 7 20-Apr-24 27-Apr-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 28-Apr-24 16-May-24 16-May-24, WALL AND 11TH FLIGHT
Z3-EGR-STAIR #5.365 Stair Form work Installation 3 28-Apr-24 30-Apr-24 Stair Form work Installation

Z3-EGR-STAIR #5.370 Wall Rebar Installation 3 01-May-24 04-May-24 Wall Rebar Installation

Z3-EGR-STAIR #5.375 Wall Form work Installation 3 05-May-24 07-May-24 Wall Form work Installation

Z3-EGR-STAIR #5.380 Wall and Stair Concrete casting 1 08-May-24 08-May-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.385 Form Removal and Curing 7 09-May-24 16-May-24 Form Removal and Curing

TOP SLAB 35 18-May-24 01-Jul-24 01-Jul-24, TOP SLAB


Z3-EGR-STAIR #5.390 Slab Form work Installation 3 18-May-24 20-May-24 Slab Form work Installation

Z3-EGR-STAIR #5.395 Slab Rebar Installation 3 21-May-24 23-May-24 Slab Rebar Installation

Z3-EGR-STAIR #5.400 Wall and Stair Concrete casting 3 25-May-24 27-May-24 Wall and Stair Concrete casting

Z3-EGR-STAIR #5.405 Form Removal and Curing 7 28-May-24 04-Jun-24 Form Removal and Curing

Z3-EGR-STAIR #5.410 Waterproofing and Coating 19 05-Jun-24 01-Jul-24 Waterproofing and Coating

Z3-EGR-STAIR #5.415 Railing work 7 23-Jun-24 01-Jul-24 Railing work

BACKFILLING UPTO TUNNELWALL 93 17-Dec-23 02-Apr-24 02-Apr-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z3-CON-BF.115 Backfilling & Compaction @ 0+994 ~ 1+094 16 17-Dec-23 03-Jan-24 Backfilling & Compaction @ 0+994 ~ 1+094

JAH-Z3-CON-BF.120 Backfilling & Compaction @ 1+094 ~ 1+194 16 08-Feb-24 26-Feb-24 Backfilling & Compaction @ 1+094 ~ 1+194

JAH-Z3-CON-BF.125 Backfilling & Compaction @ 1+194 ~ 1+268 27 03-Mar-24 02-Apr-24 Backfilling & Compaction @ 1+194 ~ 1+268

STRUCTURAL FILL 64 09-Sep-24 24-Nov-24 24-Nov-24, STRUCTURAL FILL


JAH-Z3-SF-IL.100 Backfilling & Compaction at Invert Level @ 0+994 ~ 1+094 16 09-Sep-24 29-Sep-24 Backfilling & Compaction at Invert Level @ 0+994 ~ 1+094

JAH-Z3-SF-IL.105 Backfilling & Compaction at Invert Level @ 1+094 ~ 1+194 16 29-Sep-24 17-Oct-24 Backfilling & Compaction at Invert Level @ 1+094 ~ 1+194

JAH-Z3-SF-IL.110 Backfilling & Compaction at Invert Level @ 1+194 ~ 1+268 26 24-Oct-24 24-Nov-24 Backfilling & Compaction at Invert Level @ 1+194 ~ 1+268

WET & DRY UTILITIES 367 26-Jun-24 06-Sep-25 06-Sep-25, WET & DRY UTILITIES
INSIDE WET CULVERT 367 26-Jun-24 06-Sep-25 06-Sep-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 67 26-Jun-24 11-Sep-24 11-Sep-24, POTABLE WATER NETWORK
JAH-Z3-IWU-PWN.100Pipe Supports Installation 30 26-Jun-24 30-Jul-24 Pipe Supports Installation

JAH-Z3-IWU-PWN.105Pipe Installation alongwith Valves, Fittings & Accessories 30 31-Jul-24 03-Sep-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-PWN.110Testing 7 04-Sep-24 11-Sep-24 Testing

GREY WATER DISTRIBUTION SYSTEM 67 04-Sep-24 21-Nov-24 21-Nov-24, GREY WATER DISTRIBUTION SYSTEM
JAH-Z3-IWU-GWD.225Pipe Supports Installation 30 04-Sep-24 09-Oct-24 Pipe Supports Installation

JAH-Z3-IWU-GWD.230Pipe Installation alongwith Valves, Fittings & Accessories 30 10-Oct-24 13-Nov-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-GWD.235Testing 7 14-Nov-24 21-Nov-24 Testing

IRRIGATION NETWORK 67 14-Nov-24 30-Jan-25 30-Jan-25, IRRIGATION NETWORK


JAH-Z3-IWU-IS.575 Pipe Supports Installation 30 14-Nov-24 18-Dec-24 Pipe Supports Installation

JAH-Z3-IWU-IS.580 Pipe Installation alongwith Valves, Fittings & Accessories 30 19-Dec-24 22-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-IS.585 Testing 7 23-Jan-25 30-Jan-25 Testing

CHILLED WATER SUPPLY NETWORK 67 23-Jan-25 15-Apr-25 15-Apr-25, CHILLED WATER SUPPLY NETWORK
JAH-Z3-IWU-CWS.115 Pipe Supports Installation 30 23-Jan-25 26-Feb-25 Pipe Supports Installation

JAH-Z3-IWU-CWS.120 Pipe Installation alongwith Valves, Fittings & Accessories 30 27-Feb-25 07-Apr-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-CWS.125 Testing 7 08-Apr-25 15-Apr-25 Testing

CHILLED WATER RETURN NETWORK 67 08-Apr-25 28-Jun-25 28-Jun-25, CHILLED WATER RETURN NETWORK
JAH-Z3-IWU-CWR.115Pipe Supports Installation 30 08-Apr-25 12-May-25 Pipe Supports Installation

JAH-Z3-IWU-CWR.120Pipe Installation alongwith Valves, Fittings & Accessories 30 13-May-25 19-Jun-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-CWR.125Testing 7 21-Jun-25 28-Jun-25 Testing

AUTOMATIC WASTE COLLECTION NETWORK 67 21-Jun-25 06-Sep-25 06-Sep-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z3-IWU-AWC.115 Pipe Supports Installation 30 21-Jun-25 24-Jul-25 Pipe Supports Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
299 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-IWU-AWC.120Pipe Installation alongwith Valves, Fittings & Accessories 30 26-Jul-25 28-Aug-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z3-IWU-AWC.125Testing 7 30-Aug-25 06-Sep-25 Testing

INSIDE DRY CULVERT 367 26-Jun-24 06-Sep-25 06-Sep-25, INSIDE DRY CULVERT
POWER 315 26-Jun-24 07-Jul-25 07-Jul-25, POWER
HIGH VOLTAGE 110 KV NETWORK 45 26-Jun-24 17-Aug-24 17-Aug-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z3-IDU-HV.110 HV Cable Supports Installation 20 26-Jun-24 18-Jul-24 HV Cable Supports Installation

JAH-Z3-IDU-HV.115 Cable Installation with Fittings & Accessories 25 20-Jul-24 17-Aug-24 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 45 18-Aug-24 09-Oct-24 09-Oct-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z3-IDU-MV.110 HV Cable Supports Installation 20 18-Aug-24 09-Sep-24 HV Cable Supports Installation

JAH-Z3-IDU-MV.115 Cables Installation with Fittings & Accessories 25 10-Sep-24 09-Oct-24 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 45 10-Oct-24 01-Dec-24 01-Dec-24, LOW VOLTAGE NETWORK


JAH-Z3-IDU-LV.110 HV Cable Supports Installation 20 10-Oct-24 02-Nov-24 HV Cable Supports Installation

JAH-Z3-IDU-LV.115 Cable Laying with Fittings & Accessories 25 03-Nov-24 01-Dec-24 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 150 02-Dec-24 29-May-25 29-May-25, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z3-IDU-DS.140 Cable Tray Installation 20 02-Dec-24 24-Dec-24 Cable Tray Installation

JAH-Z3-IDU-DS.145 PVC Ducts Installation 15 25-Dec-24 11-Jan-25 PVC Ducts Installation

JAH-Z3-IDU-DS.150 Cable Installation 25 12-Jan-25 09-Feb-25 Cable Installation

JAH-Z3-IDU-DS.155 Isolators Installation 20 10-Feb-25 04-Mar-25 Isolators Installation

JAH-Z3-IDU-DS.160 Sub Main Distribution Boards Installation 20 05-Mar-25 27-Mar-25 Sub Main Distribution Boards Installation

JAH-Z3-IDU-DS.165 Motor Control Centres Installation 15 29-Mar-25 19-Apr-25 Motor Control Centres Installation

JAH-Z3-IDU-DS.170 Distribution Boards Installation 20 20-Apr-25 12-May-25 Distribution Boards Installation

JAH-Z3-IDU-DS.175 Wiring Accessories Installation 15 13-May-25 29-May-25 Wiring Accessories Installation

LIGHTING SYSTEM 45 13-May-25 07-Jul-25 07-Jul-25, LIGHTING SYSTEM


JAH-Z3--IDU-LS.270 Luminaires Installation 15 21-Jun-25 07-Jul-25 Luminaires Installation

JAH-Z3--IDU-LS.275 Cables Installation 15 13-May-25 29-May-25 Cables Installation

JAH-Z3-IDU-LS.265 Light Point Installation 15 31-May-25 19-Jun-25 Light Point Installation

TELECOM SERVICES 52 08-Jul-25 06-Sep-25 06-Sep-25, TELECOM SERVICES


JAH-Z3-IDU-TES.115 Mobily Lines 18 08-Jul-25 28-Jul-25 Mobily Lines

JAH-Z3-IDU-TES.125 MOI Line 16 29-Jul-25 16-Aug-25 MOI Line

JAH-Z3-IDU-TES.128 STC Line 18 17-Aug-25 06-Sep-25 STC Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 474 26-Jun-24 10-Jan-26 10-Jan-26, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 474 26-Jun-24 10-Jan-26 10-Jan-26, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 370 26-Jun-24 09-Sep-25 09-Sep-25, FIRE FIGHTING SYSTEM
JAH-Z3-MECH-FF100 Pipe Installation work 20 26-Jun-24 18-Jul-24 Pipe Installation work

JAH-Z3-MECH-FF105 Valves and Accessories Installation 8 20-Jul-24 28-Jul-24 Valves and Accessories Installation

JAH-Z3-MECH-FF110 Sprinklers Installation 5 29-Jul-24 03-Aug-24 Sprinklers Installation

JAH-Z3-MECH-FF115 Fire Extinguishers Installation 8 04-Aug-24 12-Aug-24 Fire Extinguishers Installation

JAH-Z3-MECH-FF120 Foam Tank Installation 6 13-Aug-24 19-Aug-24 Foam Tank Installation

JAH-Z3-MECH-FF125 Pipe Painting work 6 20-Aug-24 26-Aug-24 Pipe Painting work

JAH-Z3-MECH-FF130 Testing work 3 07-Sep-25 09-Sep-25 Testing work

VENTILATION SYSTEM 23 10-Sep-25 07-Oct-25 07-Oct-25, VENTILATION SYSTEM


JAH-Z3-MECH-VS100 Staircase Pressurisation Fan Installation 5 10-Sep-25 15-Sep-25 Staircase Pressurisation Fan Installation

JAH-Z3-MECH-VS105 Extract fan installation 5 16-Sep-25 21-Sep-25 Extract fan installation

JAH-Z3-MECH-VS110 Unidirectional Jet fan 5 22-Sep-25 28-Sep-25 Unidirectional Jet fan

JAH-Z3-MECH-VS115 Reverse Jet fan 5 29-Sep-25 04-Oct-25 Reverse Jet fan

JAH-Z3-MECH-VS120 Testing work 3 05-Oct-25 07-Oct-25 Testing work

PUMPS INSTALLATION 15 08-Oct-25 25-Oct-25 25-Oct-25, PUMPS INSTALLATION

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
300 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-MECH-PI.130 Sump Pump Installation 7 08-Oct-25 15-Oct-25 Sump Pump Installation

JAH-Z3-MECH-PI.135 Pipe Connection work 6 16-Oct-25 22-Oct-25 Pipe Connection work

JAH-Z3-MECH-PI.140 Testing work 2 23-Oct-25 25-Oct-25 Testing work

DUCTING SYSTEM 66 26-Oct-25 10-Jan-26 10-Jan-26, DUCTING SYSTEM


JAH-Z3-MECH-DS.170Duct Installation work 28 26-Oct-25 26-Nov-25 Duct Installation work

JAH-Z3-MECH-DS.175Grills Installation work 7 27-Nov-25 04-Dec-25 Grills Installation work

JAH-Z3-MECH-DS.180Diffusers Installation work 7 06-Dec-25 13-Dec-25 Diffusers Installation work

JAH-Z3-MECH-DS.185Non Returns Dampers 7 14-Dec-25 21-Dec-25 Non Returns Dampers

JAH-Z3-MECH-DS.190Fire and Smoke Damper 7 22-Dec-25 29-Dec-25 Fire and Smoke Damper

JAH-Z3-MECH-DS.195Sand Trap Louvre 5 30-Dec-25 04-Jan-26 Sand Trap Louvre

JAH-Z3-MECH-DS.200Testing work 5 05-Jan-26 10-Jan-26 Testing work

TUNNEL ELECTRICAL WORKS 196 26-Jun-24 10-Feb-25 10-Feb-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 129 20-Jul-24 17-Dec-24 17-Dec-24, CABLE TRAYS
JAH-Z3-ELC-CT.220 600mm Cable Tray 21 20-Jul-24 12-Aug-24 600mm Cable Tray

JAH-Z3-ELC-CT.225 400mm Cable Tray 14 13-Aug-24 28-Aug-24 400mm Cable Tray

JAH-Z3-ELC-CT.230 300mm Cable Tray 10 29-Aug-24 09-Sep-24 300mm Cable Tray

JAH-Z3-ELC-CT.235 200mm Cable Tray 10 10-Sep-24 21-Sep-24 200mm Cable Tray

JAH-Z3-ELC-CT.240 150mm Cable Tray 10 22-Sep-24 03-Oct-24 150mm Cable Tray

JAH-Z3-ELC-CT.245 100mm Cable Tray 10 05-Oct-24 15-Oct-24 100mm Cable Tray

JAH-Z3-ELC-CT.250 75mm Cable Tray 10 16-Oct-24 27-Oct-24 75mm Cable Tray

JAH-Z3-ELC-CT.255 150mm x 100mm Trunking 10 28-Oct-24 07-Nov-24 150mm x 100mm Trunking

JAH-Z3-ELC-CT.260 100mm x 100mm Trunking 10 09-Nov-24 19-Nov-24 100mm x 100mm Trunking

JAH-Z3-ELC-CT.265 100mm x 75mm Trunking 10 20-Nov-24 01-Dec-24 100mm x 75mm Trunking

JAH-Z3-ELC-CT.270 PVC Ducts150mm dia 10 02-Dec-24 12-Dec-24 PVC Ducts150mm dia

JAH-Z3-ELC-CT.275 PVC Ducts100mm dia 4 14-Dec-24 17-Dec-24 PVC Ducts100mm dia

POWER CABLES 155 13-Aug-24 10-Feb-25 10-Feb-25, POWER CABLES


JAH-Z3-ELC-PC.290 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 13-Aug-24 26-Aug-24 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z3-ELC-PC.295 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 13-Aug-24 07-Sep-24 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z3-ELC-PC.300 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 15-Aug-24 07-Sep-24 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z3-ELC-PC.305 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 28 08-Sep-24 10-Oct-24 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z3-ELC-PC.310 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 25-Sep-24 10-Oct-24 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z3-ELC-PC.315 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 26-Sep-24 10-Oct-24 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z3-ELC-PC.320 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 26-Sep-24 19-Oct-24 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z3-ELC-PC.325 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 01-Oct-24 19-Oct-24 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z3-ELC-PC.330 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 01-Oct-24 19-Oct-24 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z3-ELC-PC.335 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 20-Oct-24 31-Oct-24 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z3-ELC-PC.340 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 21-Oct-24 31-Oct-24 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z3-ELC-PC.345 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 02-Nov-24 09-Nov-24 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z3-ELC-PC.350 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 10-Nov-24 10-Dec-24 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z3-ELC-PC.355 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 28 10-Nov-24 11-Dec-24 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z3-ELC-PC.360 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 12-Dec-24 19-Dec-24 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z3-ELC-PC.365 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 21-Dec-24 28-Dec-24 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

JAH-Z3-ELC-PC.370 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 18-Dec-24 16-Jan-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z3-ELC-PC.380 Testing work 7 03-Feb-25 10-Feb-25 Testing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
301 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-ELC-PC375 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 40 18-Dec-24 02-Feb-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

ELECTRICAL INSTALLATIONS 86 02-Nov-24 09-Feb-25 09-Feb-25, ELECTRICAL INSTALLATIONS


JAH-Z3-ELC-INS.180 Wiring Accessories 15 27-Nov-24 14-Dec-24 Wiring Accessories

JAH-Z3-ELC-INS.185 Lighting Installation 14 15-Dec-24 30-Dec-24 Lighting Installation

JAH-Z3-ELC-INS.190 Isolators Installation 12 31-Dec-24 13-Jan-25 Isolators Installation

JAH-Z3-ELC-INS.195 Circuit Wiring Installation 22 02-Nov-24 26-Nov-24 Circuit Wiring Installation

JAH-Z3-ELC-INS.200 SMDB Installation 5 14-Jan-25 19-Jan-25 SMDB Installation

JAH-Z3-ELC-INS.205 Motor Control Centres Installation 5 20-Jan-25 25-Jan-25 Motor Control Centres Installation

JAH-Z3-ELC-INS.210 Distribution Boards 6 26-Jan-25 01-Feb-25 Distribution Boards

JAH-Z3-ELC-INS.215 Testing work 7 02-Feb-25 09-Feb-25 Testing work

LOW CURRENT 180 26-Jun-24 22-Jan-25 22-Jan-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 82 26-Jun-24 30-Sep-24 30-Sep-24, FIRE DETECTION AND ALARM SYSTEM
JAH-Z3-LOW-FDT.220Fire Alarm Control Panel Installation 6 10-Jul-24 16-Jul-24 Fire Alarm Control Panel Installation

JAH-Z3-LOW-FDT.225Tamper switch Installation 5 17-Jul-24 22-Jul-24 Tamper switch Installation

JAH-Z3-LOW-FDT.230Zone Input units Installation 5 23-Jul-24 28-Jul-24 Zone Input units Installation

JAH-Z3-LOW-FDT.235Fire Alarm sounder Installation 4 29-Jul-24 01-Aug-24 Fire Alarm sounder Installation

JAH-Z3-LOW-FDT.240Fire Alarm Speaker Installation 8 03-Aug-24 11-Aug-24 Fire Alarm Speaker Installation

JAH-Z3-LOW-FDT.245Smoke Detector Installation 8 12-Aug-24 20-Aug-24 Smoke Detector Installation

JAH-Z3-LOW-FDT.250Heat Detector Installation 8 21-Aug-24 29-Aug-24 Heat Detector Installation

JAH-Z3-LOW-FDT.255Interface Module Installation 8 31-Aug-24 08-Sep-24 Interface Module Installation

JAH-Z3-LOW-FDT.260Fibre-optic Sensing Cable Laying 12 26-Jun-24 09-Jul-24 Fibre-optic Sensing Cable Laying

JAH-Z3-LOW-FDT.265Double Action Manual Call Point Installation 7 09-Sep-24 16-Sep-24 Double Action Manual Call Point Installation

JAH-Z3-LOW-FDT.270Flashing Beacon Installation 6 17-Sep-24 24-Sep-24 Flashing Beacon Installation

JAH-Z3-LOW-FDT.275Testing work 5 25-Sep-24 30-Sep-24 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 28 10-Jul-24 11-Aug-24 11-Aug-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z3-LOW-PH.140 8 core UTP Cable Laying 7 10-Jul-24 17-Jul-24 8 core UTP Cable Laying

JAH-Z3-LOW-PH.145 Junction box Installation 7 18-Jul-24 25-Jul-24 Junction box Installation

JAH-Z3-LOW-PH.150 Emergency Telephone Installation 7 27-Jul-24 03-Aug-24 Emergency Telephone Installation

JAH-Z3-LOW-PH.155 Connection and Testing 7 04-Aug-24 11-Aug-24 Connection and Testing

PUBLIC ADDRESS 28 12-Aug-24 12-Sep-24 12-Sep-24, PUBLIC ADDRESS


JAH-Z3-LOW-PA.140 Wall-mounted Voice Evacuation Horn Speaker Installation 7 20-Aug-24 27-Aug-24 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z3-LOW-PA.145 Voice alarm control panel Installation 7 28-Aug-24 04-Sep-24 Voice alarm control panel Installation

JAH-Z3-LOW-PA.150 Cables laying public address system 7 12-Aug-24 19-Aug-24 Cables laying public address system

JAH-Z3-LOW-PA.155 Connection and Testing 7 05-Sep-24 12-Sep-24 Connection and Testing

VIDEO SURVEILLANCE 49 14-Sep-24 10-Nov-24 10-Nov-24, VIDEO SURVEILLANCE


JAH-Z3-LOW-VDS.170Single Core Fibre Optical Cable Laying 7 14-Sep-24 21-Sep-24 Single Core Fibre Optical Cable Laying

JAH-Z3-LOW-VDS.175RTU Panel Installation 7 22-Sep-24 30-Sep-24 RTU Panel Installation

JAH-Z3-LOW-VDS.180Overhead Vehicle Detector Installation 7 01-Oct-24 08-Oct-24 Overhead Vehicle Detector Installation

JAH-Z3-LOW-VDS.185Door Contact Installation 7 09-Oct-24 16-Oct-24 Door Contact Installation

JAH-Z3-LOW-VDS.190PTZ Camera mounted on Pole Installation 7 17-Oct-24 24-Oct-24 PTZ Camera mounted on Pole Installation

JAH-Z3-LOW-VDS.195Fixed (AID) Camera Installation 7 26-Oct-24 02-Nov-24 Fixed (AID) Camera Installation

JAH-Z3-LOW-VDS.200Testing work 7 03-Nov-24 10-Nov-24 Testing work

SACADA SYSTEM 35 11-Nov-24 21-Dec-24 21-Dec-24, SACADA SYSTEM


JAH-Z3-LOW-SCA.150Cabling Laying 7 11-Nov-24 18-Nov-24 Cabling Laying

JAH-Z3-LOW-SCA.155Remote Terminal Unit Installation 7 19-Nov-24 26-Nov-24 Remote Terminal Unit Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
302 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z3-LOW-SCA.160Programmable Logic Control Unit Installation 7 27-Nov-24 04-Dec-24 Programmable Logic Control Unit Installation

JAH-Z3-LOW-SCA.165SCADA/ PC/ Soft ware/ Printers Installation 7 05-Dec-24 12-Dec-24 SCADA/ PC/ Soft ware/ Printers Installation

JAH-Z3-LOW-SCA.170Testing work 7 14-Dec-24 21-Dec-24 Testing work

RADIO RE-BROADCASTING SYSTEM 28 22-Dec-24 22-Jan-25 22-Jan-25, RADIO RE-BROADCASTING SYSTEM


JAH-Z3-LOW-RDO.140Leaky Feeder Cable Laying 7 22-Dec-24 29-Dec-24 Leaky Feeder Cable Laying

JAH-Z3-LOW-RDO.145Inline Bidirectional Signal Amplifier Installation 7 30-Dec-24 06-Jan-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z3-LOW-RDO.150End of Line Terminator 7 07-Jan-25 14-Jan-25 End of Line Terminator

JAH-Z3-LOW-RDO.155Connection and Testing 7 15-Jan-25 22-Jan-25 Connection and Testing

TUNNEL PLUMBING WORKS 35 26-Oct-25 04-Dec-25 04-Dec-25, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 26-Oct-25 04-Dec-25 04-Dec-25, DRAINAGE SYSTEM
JAH-Z3-PLB-DS.110 Drainage Pipes Installation Incl. Fittings & Accessories 15 26-Oct-25 11-Nov-25 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z3-PLB-DS.115 Collection Chambers 20 12-Nov-25 04-Dec-25 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 06-Dec-25 22-Jan-26 22-Jan-26, TUNNEL INTERNAL ROAD WORK
JAH-Z3-TIRW.405 Kerbs, Channels & Edging 7 06-Dec-25 13-Dec-25 Kerbs, Channels & Edging

JAH-Z3-TIRW.410 Tack Coat Application (MC-1) 10 14-Dec-25 24-Dec-25 Tack Coat Application (MC-1)

JAH-Z3-TIRW.415 Bituminious Base Course Layer 10 14-Dec-25 24-Dec-25 Bituminious Base Course Layer

JAH-Z3-TIRW.420 Tack Coat Application (RC-2) 12 25-Dec-25 07-Jan-26 Tack Coat Application (RC-2)

JAH-Z3-TIRW.425 Asphalt Wearing Course Layer 12 25-Dec-25 07-Jan-26 Asphalt Wearing Course Layer

JAH-Z3-TIRW.430 Pavement Line Marking 5 08-Jan-26 13-Jan-26 Pavement Line Marking

JAH-Z3-TIRW.435 Traffic Signboards Installation 8 14-Jan-26 22-Jan-26 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 40 08-Jan-26 23-Feb-26 23-Feb-26, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z3-CON-DW.210 Fire Protection Board Installation 10 08-Jan-26 19-Jan-26 Fire Protection Board Installation

JAH-Z3-CON-DW.215 GRC Panel Board Installation 30 20-Jan-26 23-Feb-26 GRC Panel Board Installation

ZONE 4 - FROM STA. 1+268 ~ 1+753 726 01-Aug-22 A 06-Jul-25 06-Jul-25, ZONE 4 - FROM STA. 1+268 ~ 1+753
ENGINEERING 450 01-Aug-22 A 08-Aug-24 08-Aug-24, ENGINEERING
RAM155 Completion Engineering Work For Zone4 0 08-Aug-24* Completion Engineering Work For Zone4

SITE SURVEY 14 01-Aug-22 A 04-Oct-22 A 04-Oct-22 A, SITE SURVEY


JAH-Z4-EN-SS.130 Site Survey/Settingout Control Points 2 01-Aug-22 A 27-Sep-22 A Site Survey/Settingout Control Points

JAH-Z4-EN-SS.135 Review and Approval of Site Survey & Control Points 12 08-Aug-22 A 04-Oct-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 174 15-Feb-23 12-Sep-23 12-Sep-23, SHOP DRAWINGS


CIVIL/STRUCTURAL 1+268 ~1+374 42 15-Feb-23 04-Apr-23 04-Apr-23, CIVIL/STRUCTURAL 1+268 ~1+374
JAH-Z4-ENG-CS.300 Plan and Profile Shop Drawings Preparation & Submission 6 15-Feb-23 21-Feb-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.305 Plan and Profile Shop Drawings Review & Approval 12 22-Feb-23 07-Mar-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z4-ENG-CS.310 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 08-Mar-23 14-Mar-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.315 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 15-Mar-23 28-Mar-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z4-ENG-CS.320 Tunnel Structural Shop Drawings Submission 6 15-Mar-23 21-Mar-23 Tunnel Structural Shop Drawings Submission

JAH-Z4-ENG-CS.325 Tunnel Structural Shop Drawings Review & Approval 12 22-Mar-23 04-Apr-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+374 ~1+474 42 29-Mar-23 20-May-23 20-May-23, CIVIL/STRUCTURAL 1+374 ~1+474


JAH-Z4-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 29-Mar-23 04-Apr-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 05-Apr-23 18-Apr-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z4-ENG-CS.360 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 19-Apr-23 29-Apr-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.365 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 30-Apr-23 13-May-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z4-ENG-CS.370 Tunnel Structural Shop Drawings Submission 6 30-Apr-23 06-May-23 Tunnel Structural Shop Drawings Submission

JAH-Z4-ENG-CS.375 Tunnel Structural Shop Drawings Review & Approval 12 07-May-23 20-May-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+474 ~1+574 42 14-May-23 04-Jul-23 04-Jul-23, CIVIL/STRUCTURAL 1+474 ~1+574


JAH-Z4-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 14-May-23 20-May-23 Plan and Profile Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
303 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 21-May-23 03-Jun-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z4-ENG-CS.410 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 04-Jun-23 10-Jun-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.415 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 11-Jun-23 24-Jun-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z4-ENG-CS.420 Tunnel Structural Shop Drawings Submission 6 11-Jun-23 17-Jun-23 Tunnel Structural Shop Drawings Submission

JAH-Z4-ENG-CS.425 Tunnel Structural Shop Drawings Review & Approval 12 18-Jun-23 04-Jul-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+574 ~1+674 42 25-Jun-23 15-Aug-23 15-Aug-23, CIVIL/STRUCTURAL 1+574 ~1+674


JAH-Z4-ENG-CS.450 Plan and Profile Shop Drawings Preparation & Submission 6 25-Jun-23 04-Jul-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.455 Plan and Profile Shop Drawings Review & Approval 12 05-Jul-23 18-Jul-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z4-ENG-CS.460 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 19-Jul-23 25-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.465 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 26-Jul-23 08-Aug-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z4-ENG-CS.470 Tunnel Structural Shop Drawings Submission 6 26-Jul-23 01-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z4-ENG-CS.475 Tunnel Structural Shop Drawings Review & Approval 12 02-Aug-23 15-Aug-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+674 ~1+754 42 26-Jul-23 12-Sep-23 12-Sep-23, CIVIL/STRUCTURAL 1+674 ~1+754


JAH-Z4-ENG-CS.500 Plan and Profile Shop Drawings Preparation & Submission 6 26-Jul-23 01-Aug-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.505 Plan and Profile Shop Drawings Review & Approval 12 02-Aug-23 15-Aug-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z4-ENG-CS.510 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 16-Aug-23 22-Aug-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z4-ENG-CS.515 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 23-Aug-23 05-Sep-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z4-ENG-CS.520 Tunnel Structural Shop Drawings Submission 6 23-Aug-23 29-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z4-ENG-CS.525 Tunnel Structural Shop Drawings Review & Approval 12 30-Aug-23 12-Sep-23 Tunnel Structural Shop Drawings Review & Approval

ARCHITECTURAL 22 26-Jul-23 20-Aug-23 20-Aug-23, ARCHITECTURAL


JAH-Z4-ENG-AR.130 Tunnel Architectural Shop Drawings Preparation & Submission 10 26-Jul-23 06-Aug-23 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z4-ENG-AR.135 Tunnel Architectural Shop Drawings Review & Approval 12 07-Aug-23 20-Aug-23 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 150 23-Aug-23 14-Feb-24 14-Feb-24, UTILITIES


WET UTILITIES 123 23-Aug-23 14-Jan-24 14-Jan-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 22 23-Aug-23 17-Sep-23 17-Sep-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
JAH-Z4-WU-EN-PW.100Shop Drawings Preparation & Submission 10 23-Aug-23 03-Sep-23 Shop Drawings Preparation & Submission

JAH-Z4-WU-EN-PW.105Shop Drawings Review & Approval 12 04-Sep-23 17-Sep-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 25 18-Sep-23 17-Oct-23 17-Oct-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z4-WU-EN-GW.100
Shop Drawings Preparation & Submission 13 18-Sep-23 03-Oct-23 Shop Drawings Preparation & Submission

JAH-Z4-WU-EN-GW.105
Shop Drawings Review & Approval 12 04-Oct-23 17-Oct-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 27 18-Oct-23 18-Nov-23 18-Nov-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z4-WU-EN-IRR.100
Shop Drawings Preparation & Submission 15 18-Oct-23 04-Nov-23 Shop Drawings Preparation & Submission

JAH-Z4-WU-EN-IRR.105
Shop Drawings Review & Approval 12 05-Nov-23 18-Nov-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 22 19-Nov-23 13-Dec-23 13-Dec-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z4-WU-EN-CWS.100
Shop Drawings Preparation & Submission 10 19-Nov-23 29-Nov-23 Shop Drawings Preparation & Submission

JAH-Z4-WU-EN-CWS.105
Shop Drawings Review & Approval 12 30-Nov-23 13-Dec-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 27 14-Dec-23 14-Jan-24 14-Jan-24, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z4-WU-EN-AUW.150
Shop Drawings Preparation & Submission 15 14-Dec-23 31-Dec-23 Shop Drawings Preparation & Submission

JAH-Z4-WU-EN-AUW.155
Shop Drawings Review & Approval 12 01-Jan-24 14-Jan-24 Shop Drawings Review & Approval

DRY UTILITIES 128 18-Sep-23 14-Feb-24 14-Feb-24, DRY UTILITIES


POWER 96 18-Sep-23 08-Jan-24 08-Jan-24, POWER
HIGH VOLTAGE 110 KV NETWORK 32 18-Sep-23 25-Oct-23 25-Oct-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z4-DU-EN-PWR.290
Shop Drawings Preparation & Submission 20 18-Sep-23 11-Oct-23 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-PWR.295
Shop Drawings Review & Approval 12 12-Oct-23 25-Oct-23 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 32 18-Sep-23 25-Oct-23 25-Oct-23, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z4-DU-EN-PWR.300
Shop Drawings Preparation & Submission 20 18-Sep-23 11-Oct-23 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-PWR.305
Shop Drawings Review & Approval 12 12-Oct-23 25-Oct-23 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 32 18-Sep-23 25-Oct-23 25-Oct-23, LOW VOLTAGE NETWORK

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
304 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-DU-EN-PWR.310
Shop Drawings Preparation & Submission 20 18-Sep-23 11-Oct-23 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-PWR.315
Shop Drawings Review & Approval 12 12-Oct-23 25-Oct-23 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 32 26-Oct-23 02-Dec-23 02-Dec-23, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z4-DU-EN-PWR.320
Shop Drawings Preparation & Submission 20 26-Oct-23 18-Nov-23 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-PWR.325
Shop Drawings Review & Approval 12 19-Nov-23 02-Dec-23 Shop Drawings Review & Approval

LIGHTING SYSTEM 32 03-Dec-23 08-Jan-24 08-Jan-24, LIGHTING SYSTEM


JAH-Z4-DU-EN-PWR.330
Shop Drawings Preparation & Submission 20 03-Dec-23 25-Dec-23 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-PWR.335
Shop Drawings Review & Approval 12 26-Dec-23 08-Jan-24 Shop Drawings Review & Approval

LOW CURRENT 32 09-Jan-24 14-Feb-24 14-Feb-24, LOW CURRENT


TELECOM SERVICES 32 09-Jan-24 14-Feb-24 14-Feb-24, TELECOM SERVICES
JAH-Z4-DU-EN-LC.160Shop Drawings Preparation & Submission 20 09-Jan-24 31-Jan-24 Shop Drawings Preparation & Submission

JAH-Z4-DU-EN-LC.165Shop Drawings Review & Approval 12 01-Feb-24 14-Feb-24 Shop Drawings Review & Approval

MEP 272 18-Sep-23 08-Aug-24 08-Aug-24, MEP


TUNNEL MECHANICAL WORKS 176 18-Sep-23 14-Apr-24 14-Apr-24, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 18-Sep-23 30-Dec-23 30-Dec-23, FIRE FIGHTING SYSTEM
JAH-Z4-ENG-FF.220 Fire Fighting Pipe Layout Plan Preparation & Submission 10 18-Sep-23 30-Sep-23 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z4-ENG-FF.225 Fire Fighting Pipe Layout Plan Review & Approval 12 01-Oct-23 14-Oct-23 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z4-ENG-FF.230 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 15-Oct-23 25-Oct-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z4-ENG-FF.235 Fire Fighting Sprinkler Layout Plan Review & Approval 12 26-Oct-23 08-Nov-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z4-ENG-FF.240 Foam Tank Installation Layout Preparation & Submission 10 09-Nov-23 20-Nov-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z4-ENG-FF.245 Foam Tank Installation Layout Review & Approval 12 21-Nov-23 04-Dec-23 Foam Tank Installation Layout Review & Approval

JAH-Z4-ENG-FF.250 Fire Extinguishers Layout Plan Preparation & Submission 10 05-Dec-23 16-Dec-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z4-ENG-FF.255 Fire Extinguishers Layout Plan Review & Approval 12 17-Dec-23 30-Dec-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 17-Dec-23 05-Feb-24 05-Feb-24, VENTILATION SYSTEM


JAH-Z4-ENG-VS.160 Fan Layout Preparation & Submission 10 17-Dec-23 27-Dec-23 Fan Layout Preparation & Submission

JAH-Z4-ENG-VS.165 Fan Layout Review & Approval 12 28-Dec-23 10-Jan-24 Fan Layout Review & Approval

JAH-Z4-ENG-VS.170 Cable Route Shop Drawing Preparation & Submission 10 11-Jan-24 22-Jan-24 Cable Route Shop Drawing Preparation & Submission

JAH-Z4-ENG-VS.175 Cable Route Shop Drawing Review & Approval 12 23-Jan-24 05-Feb-24 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 06-Feb-24 02-Mar-24 02-Mar-24, PUMPS INSTALLATION


JAH-Z4-ENG-PI.130 Sump Pump Diagram Preparation & Submission 10 06-Feb-24 17-Feb-24 Sump Pump Diagram Preparation & Submission

JAH-Z4-ENG-PI.135 Sump Pump Diagram Review & Approval 12 18-Feb-24 02-Mar-24 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 31-Dec-23 14-Apr-24 14-Apr-24, DUCTING SYSTEM


JAH-Z4-ENG-DCS.220 Duct Layout Drawing Preparation & Submission 10 31-Dec-23 10-Jan-24 Duct Layout Drawing Preparation & Submission

JAH-Z4-ENG-DCS.225 Duct Layout Drawing Review & Approval 12 11-Jan-24 24-Jan-24 Duct Layout Drawing Review & Approval

JAH-Z4-ENG-DCS.230 Diffuser Details Review & Approval 12 06-Feb-24 19-Feb-24 Diffuser Details Review & Approval

JAH-Z4-ENG-DCS.235 Dampers Details Preparation & Submission 10 20-Feb-24 02-Mar-24 Dampers Details Preparation & Submission

JAH-Z4-ENG-DCS.240 Dampers Details Review & Approval 12 03-Mar-24 16-Mar-24 Dampers Details Review & Approval

JAH-Z4-ENG-DCS.245 Sand Trap Louvre Layout Drawing Preparation & Submission 10 17-Mar-24 27-Mar-24 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z4-ENG-DCS.250 Sand Trap Louvre Layout Drawing Review & Approval 12 28-Mar-24 14-Apr-24 Sand Trap Louvre Layout Drawing Review & Approval

JAH-Z4-ENG-DCS.255 Diffuser Details Drawing Preparation & Submission 10 25-Jan-24 05-Feb-24 Diffuser Details Drawing Preparation & Submission

TUNNEL ELECTRICAL WORKS 184 31-Dec-23 08-Aug-24 08-Aug-24, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 11-Jan-24 21-May-24 21-May-24, CABLE TRAYS
JAH-Z4-ENG-CTR.250 Cable Tray Layout Drawing Preparation & Submission 10 11-Jan-24 22-Jan-24 Cable Tray Layout Drawing Preparation & Submission

JAH-Z4-ENG-CTR.255 Cable Tray Layout Drawing Review & Approval 12 23-Jan-24 05-Feb-24 Cable Tray Layout Drawing Review & Approval

JAH-Z4-ENG-CTR.260 Cable Tray Diversion Details Preparation & Submission 10 06-Feb-24 17-Feb-24 Cable Tray Diversion Details Preparation & Submission

JAH-Z4-ENG-CTR.265 Cable Tray Diversion Details Review & Approval 12 18-Feb-24 02-Mar-24 Cable Tray Diversion Details Review & Approval

JAH-Z4-ENG-CTR.270 Cable Tray Fixing Details Preparation & Submission 10 03-Mar-24 13-Mar-24 Cable Tray Fixing Details Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
305 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ENG-CTR.275 Cable Tray Fixing Details Review & Submission 12 14-Mar-24 27-Mar-24 Cable Tray Fixing Details Review & Submission

JAH-Z4-ENG-CTR.280 Cable Tray Sections Preparation & Submission 10 28-Mar-24 08-Apr-24 Cable Tray Sections Preparation & Submission

JAH-Z4-ENG-CTR.285 Cable Tray Sections Review & Approval 12 13-Apr-24 25-Apr-24 Cable Tray Sections Review & Approval

JAH-Z4-ENG-CTR.290 PVC DuctsSections Preparation & Submission 10 27-Apr-24 07-May-24 PVC DuctsSections Preparation & Submission

JAH-Z4-ENG-CTR.295 PVC Sections Review & Approval 12 08-May-24 21-May-24 PVC Sections Review & Approval

POWER CABLES 44 14-Mar-24 07-May-24 07-May-24, POWER CABLES


JAH-Z4-ENG-PC.160 Cable Route Shop Drawing Preparation & Submission 10 14-Mar-24 25-Mar-24 Cable Route Shop Drawing Preparation & Submission

JAH-Z4-ENG-PC.165 Cable Route Shop Drawing Review & Approval 12 26-Mar-24 08-Apr-24 Cable Route Shop Drawing Review & Approval

JAH-Z4-ENG-PC.170 Junction Box Layout Plan Preparation & Submission 10 13-Apr-24 23-Apr-24 Junction Box Layout Plan Preparation & Submission

JAH-Z4-ENG-PC.175 Junction Box Layout Plan Review & Approval 12 24-Apr-24 07-May-24 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 26-Mar-24 08-Aug-24 08-Aug-24, ELECTRICAL INSTALLATIONS


JAH-Z4-ENG-ELI.250 Wiring Accessories Diagram Preparation & Submission 10 26-Mar-24 06-Apr-24 Wiring Accessories Diagram Preparation & Submission

JAH-Z4-ENG-ELI.255 Lighting Layout Drawing Preparation & Submission 10 24-Apr-24 05-May-24 Lighting Layout Drawing Preparation & Submission

JAH-Z4-ENG-ELI.260 Circuit Wiring Diagram Preparation & Submission 10 20-May-24 30-May-24 Circuit Wiring Diagram Preparation & Submission

JAH-Z4-ENG-ELI.265 Circuit Wiring Diagram Review & Approval 12 01-Jun-24 13-Jun-24 Circuit Wiring Diagram Review & Approval

JAH-Z4-ENG-ELI.270 SMDB Line Diagram Preparation & Submission 10 19-Jun-24 30-Jun-24 SMDB Line Diagram Preparation & Submission

JAH-Z4-ENG-ELI.275 SMDB Line Diagram Review & Approval 12 01-Jul-24 14-Jul-24 SMDB Line Diagram Review & Approval

JAH-Z4-ENG-ELI.280 Distribution Board Line Diagram Preparation & Submission 10 15-Jul-24 25-Jul-24 Distribution Board Line Diagram Preparation & Submission

JAH-Z4-ENG-ELI.285 Lighting Layout Drawing Review & Approval 12 06-May-24 19-May-24 Lighting Layout Drawing Review & Approval

JAH-Z4-ENG-ELI.290 Wiring Accessories Diagram Review & Approval 12 07-Apr-24 23-Apr-24 Wiring Accessories Diagram Review & Approval

JAH-Z4-ENG-ELI.295 Distribution Board Line Diagram Review & Approval 12 27-Jul-24 08-Aug-24 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 31-Dec-23 04-Jun-24 04-Jun-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 31-Dec-23 04-Jun-24 04-Jun-24, FIRE DETECTION AND ALARM SYSTEM
JAH-Z4-ENG-FD.280 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 31-Dec-23 10-Jan-24 Fire Alarm Control Panel Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.285 Fire Alarm Control Panel Layout Drawing Review & Approval 12 11-Jan-24 24-Jan-24 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z4-ENG-FD.290 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 25-Jan-24 05-Feb-24 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.295 Fire Alarm Speaker Layout Drawing Review & Approval 12 06-Feb-24 19-Feb-24 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z4-ENG-FD.300 Fire Alarm sounder Layout Drawing Preparation & Submission 10 20-Feb-24 02-Mar-24 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.305 Fire Alarm sounder Layout Drawing Review & Approval 12 03-Mar-24 16-Mar-24 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z4-ENG-FD.310 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 17-Mar-24 27-Mar-24 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.315 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 28-Mar-24 14-Apr-24 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z4-ENG-FD.320 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 15-Apr-24 25-Apr-24 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.325 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 27-Apr-24 09-May-24 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z4-ENG-FD.330 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 11-May-24 21-May-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z4-ENG-FD.335 Double Action Manual Call Point Layout Drawing Preparation & Submission 12 22-May-24 04-Jun-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 11-Jan-24 21-May-24 21-May-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z4-ENG-TPH.2508 core UTP Cable Laying 14 11-Jan-24 27-Jan-24 8 core UTP Cable Laying

JAH-Z4-ENG-TPH.255Junction box Installation 8 28-Jan-24 05-Feb-24 Junction box Installation

JAH-Z4-ENG-TPH.260Emergency Telephone Installation 14 06-Feb-24 21-Feb-24 Emergency Telephone Installation

JAH-Z4-ENG-TPH.265Connection and Testing 8 22-Feb-24 02-Mar-24 Connection and Testing

JAH-Z4-ENG-TPH.2708 Core UTP Cable Layout Drawing Preparation & Submission 10 03-Mar-24 13-Mar-24 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-TPH.2758 Core UTP Cable Layout Drawing Review & Approval 12 14-Mar-24 27-Mar-24 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z4-ENG-TPH.280Junction box Layout Drawing Preparation & Submission 10 28-Mar-24 08-Apr-24 Junction box Layout Drawing Preparation & Submission

JAH-Z4-ENG-TPH.285Junction box Layout Drawing Review & Approval 12 13-Apr-24 25-Apr-24 Junction box Layout Drawing Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
306 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ENG-TPH.290Telephone Location Layout Preparation & Submission 10 27-Apr-24 07-May-24 Telephone Location Layout Preparation & Submission

JAH-Z4-ENG-TPH.295Telephone Location Layout Review & Approval 12 08-May-24 21-May-24 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 28-Jan-24 16-Apr-24 16-Apr-24, PUBLIC ADDRESS


JAH-Z4-ENG-PUBA.190
Cable Layout Drawing Preparation & Submission 10 28-Jan-24 07-Feb-24 Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-PUBA.195
Cable Layout Drawing Review & Approval 12 08-Feb-24 21-Feb-24 Cable Layout Drawing Review & Approval

JAH-Z4-ENG-PUBA.200
Voice alarm control panel Drawing Preparation & Submission 10 22-Feb-24 04-Mar-24 Voice alarm control panel Drawing Preparation & Submission

JAH-Z4-ENG-PUBA.205
Voice alarm control panel Drawing Review & Approval 12 05-Mar-24 18-Mar-24 Voice alarm control panel Drawing Review & Approval

JAH-Z4-ENG-PUBA.210
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 19-Mar-24 30-Mar-24 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z4-ENG-PUBA.215
Voice Evacuation Horn Speaker Drawing Review & Approval 12 31-Mar-24 16-Apr-24 Voice Evacuation Horn Speaker Drawing Review & Approval

VIDEO SURVEILLANCE 44 08-Feb-24 30-Mar-24 30-Mar-24, VIDEO SURVEILLANCE


JAH-Z4-ENG-VID.160Cable Layout Drawing Preparation & Submission 10 08-Feb-24 19-Feb-24 Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-VID.165Cable Layout Drawing Review & Approval 12 20-Feb-24 04-Mar-24 Cable Layout Drawing Review & Approval

JAH-Z4-ENG-VID.170Camera Layout Drawing Preparation & Submission 10 05-Mar-24 16-Mar-24 Camera Layout Drawing Preparation & Submission

JAH-Z4-ENG-VID.175Camera Layout Drawing Review & Approval 12 17-Mar-24 30-Mar-24 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 20-Feb-24 14-Apr-24 14-Apr-24, SACADA SYSTEM


JAH-Z4-ENG-SCA.160Cable Layout Drawing Preparation & Submission 10 20-Feb-24 02-Mar-24 Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-SCA.165Cable Layout Drawing Review & Approval 12 03-Mar-24 16-Mar-24 Cable Layout Drawing Review & Approval

JAH-Z4-ENG-SCA.170Installation Layout Drawing Preparation & Submission 10 17-Mar-24 27-Mar-24 Installation Layout Drawing Preparation & Submission

JAH-Z4-ENG-SCA.175Installation Layout Drawing Review & Approval 12 28-Mar-24 14-Apr-24 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 03-Mar-24 25-Apr-24 25-Apr-24, RADIO RE-BROADCASTING SYSTEM


JAH-Z4-ENG-RDO.160Cable Layout Drawing Preparation & Submission 10 03-Mar-24 13-Mar-24 Cable Layout Drawing Preparation & Submission

JAH-Z4-ENG-RDO.165Cable Layout Drawing Review & Approval 12 14-Mar-24 27-Mar-24 Cable Layout Drawing Review & Approval

JAH-Z4-ENG-RDO.170Installation Layout Drawing Preparation & Submission 10 28-Mar-24 08-Apr-24 Installation Layout Drawing Preparation & Submission

JAH-Z4-ENG-RDO.175Installation Layout Drawing Review & Approval 12 13-Apr-24 25-Apr-24 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 14-Mar-24 07-Apr-24 07-Apr-24, TUNNEL PLUMBING WORKS


JAH-Z4-ENG-PLM.130 Plumbing Services Shop Drawings Preparation & Submission 9 14-Mar-24 24-Mar-24 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z4-ENG-PLM.135 Plumbing Shop Drawings Review & Approval 12 25-Mar-24 07-Apr-24 Plumbing Shop Drawings Review & Approval

PROCUREMENT 445 22-Feb-23 10-Aug-24 10-Aug-24, PROCUREMENT


RAM280 Completion Procurment for Zone 4 0 10-Aug-24* Completion Procurment for Zone 4

CIVIL/STRUCTURAL 85 22-Feb-23 04-Jun-23 04-Jun-23, CIVIL/STRUCTURAL


JAH-Z4-PRO-CSM.160 Request for Quotation 10 22-Feb-23 05-Mar-23 Request for Quotation

JAH-Z4-PRO-CSM.165 Issue Purchase Order 15 06-Mar-23 22-Mar-23 Issue Purchase Order

JAH-Z4-PRO-CSM.170 Material Delivery 45 10-Apr-23 04-Jun-23 Material Delivery

JAH-Z4-PRO-CSM.175 Staging Time 15 23-Mar-23 09-Apr-23 Staging Time

UTILITIES 273 18-Sep-23 10-Aug-24 10-Aug-24, UTILITIES


WET UTILITIES 246 18-Sep-23 09-Jul-24 09-Jul-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 145 18-Sep-23 05-Mar-24 05-Mar-24, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 18-Sep-23 05-Mar-24 05-Mar-24, DI PIPES
JAH-Z4-PR-WU-PW.100
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.105
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.110
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.145
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

HDPE PIPES 145 18-Sep-23 05-Mar-24 05-Mar-24, HDPE PIPES


JAH-Z4-PR-WU-PW.135
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.150
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.170
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.230
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
307 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
GRP PIPES 145 18-Sep-23 05-Mar-24 05-Mar-24, GRP PIPES
JAH-Z4-PR-WU-PW.120
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.125
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.155
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.200
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

DI & GRP FITTING 145 18-Sep-23 05-Mar-24 05-Mar-24, DI & GRP FITTING
JAH-Z4-PR-WU-PW.115
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.130
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.160
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.205
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

GATE VALVE 145 18-Sep-23 05-Mar-24 05-Mar-24, GATE VALVE


JAH-Z4-PR-WU-PW.195
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.210
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.235
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.260
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

BUTTERFLAY VALVE 145 18-Sep-23 05-Mar-24 05-Mar-24, BUTTERFLAY VALVE


JAH-Z4-PR-WU-PW.190
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.215
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.240
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.265
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

WATER METER 145 18-Sep-23 05-Mar-24 05-Mar-24, WATER METER


JAH-Z4-PR-WU-PW.140
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.165
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.175
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.245
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

AIR RELASE VALVE 145 18-Sep-23 05-Mar-24 05-Mar-24, AIR RELASE VALVE
JAH-Z4-PR-WU-PW.185
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.220
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.250
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.270
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

WASHOUT VALVE 145 18-Sep-23 05-Mar-24 05-Mar-24, WASHOUT VALVE


JAH-Z4-PR-WU-PW.180
Request for Quotation 10 18-Sep-23 30-Sep-23 Request for Quotation

JAH-Z4-PR-WU-PW.225
Issue Purchase Order 15 01-Oct-23 17-Oct-23 Issue Purchase Order

JAH-Z4-PR-WU-PW.255
Staging time 30 18-Oct-23 21-Nov-23 Staging time

JAH-Z4-PR-WU-PW.275
Material Delivery 90 22-Nov-23 05-Mar-24 Material Delivery

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 145 18-Oct-23 03-Apr-24 03-Apr-24, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 18-Oct-23 03-Apr-24 03-Apr-24, DI PIPES
JAH-Z4-PR-WU-GWD.100
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.105
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.110
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.140
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

HDPE PIPES 145 18-Oct-23 03-Apr-24 03-Apr-24, HDPE PIPES


JAH-Z4-PR-WU-GWD.135
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.145
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.160
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.215
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
308 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
GRP PIPES 145 18-Oct-23 03-Apr-24 03-Apr-24, GRP PIPES
JAH-Z4-PR-WU-GWD.120
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.125
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.150
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.185
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

DI & GRP FITTING 145 18-Oct-23 03-Apr-24 03-Apr-24, DI & GRP FITTING
JAH-Z4-PR-WU-GWD.115
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.130
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.155
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.190
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

GATE VALVE 145 18-Oct-23 03-Apr-24 03-Apr-24, GATE VALVE


JAH-Z4-PR-WU-GWD.180
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.195
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.220
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.240
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

BUTTERFLAY VALVE 145 18-Oct-23 03-Apr-24 03-Apr-24, BUTTERFLAY VALVE


JAH-Z4-PR-WU-GWD.175
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.200
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.225
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.245
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

AIR RELASE VALVE 145 18-Oct-23 03-Apr-24 03-Apr-24, AIR RELASE VALVE
JAH-Z4-PR-WU-GWD.170
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.205
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.230
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.250
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

WASEHOUT VALVE 145 18-Oct-23 03-Apr-24 03-Apr-24, WASEHOUT VALVE


JAH-Z4-PR-WU-GWD.165
Request for Quotation 10 18-Oct-23 29-Oct-23 Request for Quotation

JAH-Z4-PR-WU-GWD.210
Issue Purchase Order 15 30-Oct-23 15-Nov-23 Issue Purchase Order

JAH-Z4-PR-WU-GWD.235
Staging time 30 16-Nov-23 20-Dec-23 Staging time

JAH-Z4-PR-WU-GWD.255
Material Delivery 90 21-Dec-23 03-Apr-24 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 145 19-Nov-23 08-May-24 08-May-24, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 19-Nov-23 08-May-24 08-May-24, HDPE PIPES
JAH-Z4-PR-WU-IRR.100
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.105
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.110
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.155
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

GATE VALVE 145 19-Nov-23 08-May-24 08-May-24, GATE VALVE


JAH-Z4-PR-WU-IRR.130
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.135
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.160
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.190
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

BUTTERFLAY VALVE 145 19-Nov-23 08-May-24 08-May-24, BUTTERFLAY VALVE


JAH-Z4-PR-WU-IRR.125
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.140
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.165
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.195
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
309 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AIR RELASE VALVE 145 19-Nov-23 08-May-24 08-May-24, AIR RELASE VALVE
JAH-Z4-PR-WU-IRR.120
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.145
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.170
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.200
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

WASEHOUT VALVE 145 19-Nov-23 08-May-24 08-May-24, WASEHOUT VALVE


JAH-Z4-PR-WU-IRR.115
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.150
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.175
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.205
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

FIRE HYDRANT 145 19-Nov-23 08-May-24 08-May-24, FIRE HYDRANT


JAH-Z4-PR-WU-IRR.180
Request for Quotation 10 19-Nov-23 29-Nov-23 Request for Quotation

JAH-Z4-PR-WU-IRR.185
Issue Purchase Order 15 30-Nov-23 17-Dec-23 Issue Purchase Order

JAH-Z4-PR-WU-IRR.210
Staging time 30 18-Dec-23 21-Jan-24 Staging time

JAH-Z4-PR-WU-IRR.215
Material Delivery 90 22-Jan-24 08-May-24 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 145 14-Dec-23 03-Jun-24 03-Jun-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 14-Dec-23 03-Jun-24 03-Jun-24, MILD STEEL PIPE
JAH-Z4-PR-WU-CWS.105
Request for Quotation 10 14-Dec-23 25-Dec-23 Request for Quotation

JAH-Z4-PR-WU-CWS.110
Issue Purchase Order 15 26-Dec-23 11-Jan-24 Issue Purchase Order

JAH-Z4-PR-WU-CWS.120
Staging time 30 13-Jan-24 15-Feb-24 Staging time

JAH-Z4-PR-WU-CWS.130
Material Delivery 90 17-Feb-24 03-Jun-24 Material Delivery

MILD STEEL FITTING 145 14-Dec-23 03-Jun-24 03-Jun-24, MILD STEEL FITTING
JAH-Z4-PR-WU-CWS.100
Request for Quotation 10 14-Dec-23 25-Dec-23 Request for Quotation

JAH-Z4-PR-WU-CWS.115
Issue Purchase Order 15 26-Dec-23 11-Jan-24 Issue Purchase Order

JAH-Z4-PR-WU-CWS.125
Staging time 30 13-Jan-24 15-Feb-24 Staging time

JAH-Z4-PR-WU-CWS.135
Material Delivery 90 17-Feb-24 03-Jun-24 Material Delivery

GATE VALVE 145 14-Dec-23 03-Jun-24 03-Jun-24, GATE VALVE


JAH-Z4-PR-WU-CWS.140
Request for Quotation 10 14-Dec-23 25-Dec-23 Request for Quotation

JAH-Z4-PR-WU-CWS.145
Issue Purchase Order 15 26-Dec-23 11-Jan-24 Issue Purchase Order

JAH-Z4-PR-WU-CWS.150
Staging time 30 13-Jan-24 15-Feb-24 Staging time

JAH-Z4-PR-WU-CWS.155
Material Delivery 90 17-Feb-24 03-Jun-24 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 15-Jan-24 09-Jul-24 09-Jul-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 15-Jan-24 09-Jul-24 09-Jul-24, AUTOMATIC WASTE
JAH-Z4-PR-WU-AWC.100
Request for Quotation 10 15-Jan-24 25-Jan-24 Request for Quotation

JAH-Z4-PR-WU-AWC.105
Issue Purchase Order 15 27-Jan-24 12-Feb-24 Issue Purchase Order

JAH-Z4-PR-WU-AWC.110
Staging time 30 13-Feb-24 18-Mar-24 Staging time

JAH-Z4-PR-WU-AWC.115
Material Delivery 90 19-Mar-24 09-Jul-24 Material Delivery

DRY UTILITIES 241 26-Oct-23 10-Aug-24 10-Aug-24, DRY UTILITIES


POWER 209 26-Oct-23 03-Jul-24 03-Jul-24, POWER
HIGH VOLTAGE 110 KV NETWORK 145 26-Oct-23 15-Apr-24 15-Apr-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z4-PR-DU-PWR.100
Request for Quotation 10 26-Oct-23 06-Nov-23 Request for Quotation

JAH-Z4-PR-DU-PWR.105
Issue Purchase Order 15 07-Nov-23 23-Nov-23 Issue Purchase Order

JAH-Z4-PR-DU-PWR.115
Staging time 30 25-Nov-23 28-Dec-23 Staging time

JAH-Z4-PR-DU-PWR.145
Material Delivery 90 30-Dec-23 15-Apr-24 Material Delivery

MEDIUM VOLTAGE 13.8 KV NETWORK 145 26-Oct-23 15-Apr-24 15-Apr-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z4-PR-DU-PWR.110
Request for Quotation 10 26-Oct-23 06-Nov-23 Request for Quotation

JAH-Z4-PR-DU-PWR.120
Issue Purchase Order 15 07-Nov-23 23-Nov-23 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
310 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-PR-DU-PWR.130
Staging time 30 25-Nov-23 28-Dec-23 Staging time

JAH-Z4-PR-DU-PWR.165
Material Delivery 90 30-Dec-23 15-Apr-24 Material Delivery

LOW VOLTAGE NETWORK 145 26-Oct-23 15-Apr-24 15-Apr-24, LOW VOLTAGE NETWORK
JAH-Z4-PR-DU-PWR.125
Request for Quotation 10 26-Oct-23 06-Nov-23 Request for Quotation

JAH-Z4-PR-DU-PWR.135
Issue Purchase Order 15 07-Nov-23 23-Nov-23 Issue Purchase Order

JAH-Z4-PR-DU-PWR.150
Staging time 30 25-Nov-23 28-Dec-23 Staging time

JAH-Z4-PR-DU-PWR.185
Material Delivery 90 30-Dec-23 15-Apr-24 Material Delivery

ELECTRICAL DISTRIBUTION SYSTEM 145 03-Dec-23 22-May-24 22-May-24, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z4-PR-DU-PWR.180
Request for Quotation 10 03-Dec-23 13-Dec-23 Request for Quotation

JAH-Z4-PR-DU-PWR.195
Issue Purchase Order 15 14-Dec-23 31-Dec-23 Issue Purchase Order

JAH-Z4-PR-DU-PWR.205
Staging time 30 01-Jan-24 04-Feb-24 Staging time

JAH-Z4-PR-DU-PWR.215
Material Delivery 90 05-Feb-24 22-May-24 Material Delivery

LIGHTING SYSTEM 145 09-Jan-24 03-Jul-24 03-Jul-24, LIGHTING SYSTEM


JAH-Z4-PR-DU-PWR.140
Request for Quotation 10 09-Jan-24 20-Jan-24 Request for Quotation

JAH-Z4-PR-DU-PWR.155
Issue Purchase Order 15 21-Jan-24 06-Feb-24 Issue Purchase Order

JAH-Z4-PR-DU-PWR.170
Staging time 30 07-Feb-24 12-Mar-24 Staging time

JAH-Z4-PR-DU-PWR.200
Material Delivery 90 13-Mar-24 03-Jul-24 Material Delivery

LOW CURRENT 145 15-Feb-24 10-Aug-24 10-Aug-24, LOW CURRENT


TELECOM SERVICES 145 15-Feb-24 10-Aug-24 10-Aug-24, TELECOM SERVICES
JAH-Z4-PR-DU-PWR.160
Request for Quotation 10 15-Feb-24 26-Feb-24 Request for Quotation

JAH-Z4-PR-DU-PWR.175
Issue Purchase Order 15 27-Feb-24 14-Mar-24 Issue Purchase Order

JAH-Z4-PR-DU-PWR.190
Staging time 30 16-Mar-24 22-Apr-24 Staging time

JAH-Z4-PR-DU-PWR.210
Material Delivery 90 23-Apr-24 10-Aug-24 Material Delivery

MEP 235 23-Mar-23 30-Dec-23 30-Dec-23, MEP


JAH-Z4-PR-MEP.100 Request for Quotation 10 23-Mar-23 03-Apr-23 Request for Quotation

JAH-Z4-PR-MEP.105 Issue Purchase Order 15 04-Apr-23 20-Apr-23 Issue Purchase Order

JAH-Z4-PR-MEP.110 Staging Time 30 25-Apr-23 29-May-23 Staging Time

JAH-Z4-PR-MEP.115 Material Delivery 180 30-May-23 30-Dec-23 Material Delivery

ARCHITECTURAL 115 21-Aug-23 02-Jan-24 02-Jan-24, ARCHITECTURAL


JAH-Z4-PR-ARC.100 Request for Quotation for GRC Panels 10 21-Aug-23 31-Aug-23 Request for Quotation for GRC Panels

JAH-Z4-PR-ARC.105 Issue Purchase Order 15 02-Sep-23 18-Sep-23 Issue Purchase Order

JAH-Z4-PR-ARC.110 Staging Time 30 19-Sep-23 24-Oct-23 Staging Time

JAH-Z4-PR-ARC.115 Material Delivery 60 25-Oct-23 02-Jan-24 Material Delivery

CONSTRUCTION 690 14-Aug-22 A 06-Jul-25 06-Jul-25, CONSTRUCTION


GENERAL SITE ARRANGEMENT 80 03-Oct-22 A 06-May-23 06-May-23, GENERAL SITE ARRANGEMENT
SITE PREPARATION 80 03-Oct-22 A 06-May-23 06-May-23, SITE PREPARATION
JAH-Z4-CON-GA-SP.145Site Clearing & Grubbing / Demolition of Obstacles 7 03-Oct-22 A 22-Mar-23 Site Clearing & Grubbing / Demolition of Obstacles

JAH-Z4-CON-GA-SP.150Disposal /Removal of Unnecessary Objects from Site 5 06-Oct-22 A 28-Mar-23 Disposal /Removal of Unnecessary Objects from Site

JAH-Z4-CON-GA-SP.155Relocation of Exisiting Utilities 30 29-Mar-23 06-May-23 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 50 14-Aug-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION


JAH-Z4-ENG-GTI.485 Borehole Layout Preparation & Submission 7 14-Aug-22 A 17-Aug-22 A Borehole Layout Preparation & Submission

JAH-Z4-ENG-GTI.490 Borehole Layout Review & Approval 5 18-Aug-22 A 21-Aug-22 A Borehole Layout Review & Approval

JAH-Z4-ENG-GTI.495 Drilling Boreholes 10 22-Aug-22 A 23-Aug-22 A Drilling Boreholes

JAH-Z4-ENG-GTI.500 Issuance of Geo-Technical Investigation Report 10 23-Aug-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 302 10-Oct-22 A 23-Jun-24 23-Jun-24, EXCAVATION & DEWATERING
JAH-Z4-CON-DE.102 Dewatering @Sta. 1+268 ~ 1+368 189 11-Oct-22 A 13-Nov-23 Dewatering @Sta. 1+268 ~ 1+368

JAH-Z4-CON-DE.107 Dewatering @Sta. 1+368 ~ 1+468 209 10-Oct-22 A 30-Dec-23 Dewatering @Sta. 1+368 ~ 1+468

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
311 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-CON-DE.112 Dewatering @Sta. 1+468 ~ 1+568 206 25-Jun-23 24-Feb-24 Dewatering @Sta. 1+468 ~ 1+568

JAH-Z4-CON-DE.117 Dewatering @Sta. 1+568 ~ 1+668 221 09-Aug-23 27-Apr-24 Dewatering @Sta. 1+568 ~ 1+668

JAH-Z4-CON-DE.123 Dewatering @Sta. 1+668 ~ 1+753 236 13-Sep-23 23-Jun-24 Dewatering @Sta. 1+668 ~ 1+753

JAH-Z4-CON-EX.100 Excavation & Shoring System @Sta. 1+268 ~ 1+368 30 10-Oct-22 A 29-May-23 Excavation & Shoring System @Sta. 1+268 ~ 1+368

JAH-Z4-CON-EX.105 Excavation & Shoring System @Sta. 1+368 ~ 1+468 30 11-Oct-22 A 21-Jun-23 Excavation & Shoring System @Sta. 1+368 ~ 1+468

JAH-Z4-CON-EX.110 Excavation & Shoring System @Sta. 1+468 ~ 1+568 30 25-Jun-23 01-Aug-23 Excavation & Shoring System @Sta. 1+468 ~ 1+568

JAH-Z4-CON-EX.115 Excavation & Shoring System @Sta. 1+568 ~ 1+668 30 09-Aug-23 12-Sep-23 Excavation & Shoring System @Sta. 1+568 ~ 1+668

JAH-Z4-CON-EX.120 Excavation & Shoring System @Sta. 1+668 ~ 1+753 30 13-Sep-23 18-Oct-23 Excavation & Shoring System @Sta. 1+668 ~ 1+753

SOIL IMPROVEMENT 128 30-May-23 30-Oct-23 30-Oct-23, SOIL IMPROVEMENT


JAH-Z4-CON-SIMP.101 Soil Improvement @Sta. 1+268 ~ 1+368 20 30-May-23 21-Jun-23 Soil Improvement @Sta. 1+268 ~ 1+368

JAH-Z4-CON-SIMP.106 Soil Improvement @Sta. 1+368 ~ 1+468 20 22-Jun-23 18-Jul-23 Soil Improvement @Sta. 1+368 ~ 1+468

JAH-Z4-CON-SIMP.111 Soil Improvement @Sta. 1+468 ~ 1+568 20 02-Aug-23 24-Aug-23 Soil Improvement @Sta. 1+468 ~ 1+568

JAH-Z4-CON-SIMP.116 Soil Improvement @Sta. 1+568 ~ 1+668 20 13-Sep-23 07-Oct-23 Soil Improvement @Sta. 1+568 ~ 1+668

JAH-Z4-CON-SIMP.121 Soil Improvement @Sta. 1+668 ~ 1+753 10 19-Oct-23 30-Oct-23 Soil Improvement @Sta. 1+668 ~ 1+753

STRUCTURAL WORKS 477 06-Aug-23 22-Feb-25 22-Feb-25, STRUCTURAL WORKS


STA. 1+268.979 ~ 1+293.979 168 06-Aug-23 18-Feb-24 18-Feb-24, STA. 1+268.979 ~ 1+293.979
BASE SLAB 29 06-Aug-23 07-Sep-23 07-Sep-23, BASE SLAB
JAH-Z4-ST-S1-BS.100 Lean Concrete for Base Slab 1 06-Aug-23 06-Aug-23 Lean Concrete for Base Slab

JAH-Z4-ST-S1-BS.105 Waterproofing for Lean Concrete 1 07-Aug-23 07-Aug-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S1-BS.110 Base Slab Rebar Installation 8 08-Aug-23 16-Aug-23 Base Slab Rebar Installation

JAH-Z4-ST-S1-BS.115 Base Slab Formwork Installation 7 17-Aug-23 24-Aug-23 Base Slab Formwork Installation

JAH-Z4-ST-S1-BS.120 Base Slab Concrete Casting 1 26-Aug-23 26-Aug-23 Base Slab Concrete Casting

JAH-Z4-ST-S1-BS.122 Curing work 7 27-Aug-23 03-Sep-23 Curing work

JAH-Z4-ST-S1-BS.125 Base Slab Formwork Removel 2 04-Sep-23 05-Sep-23 Base Slab Formwork Removel

JAH-Z4-ST-S1-BS.130 Plain concrete on Base slab 2 06-Sep-23 07-Sep-23 Plain concrete on Base slab

COLUMN 23 09-Sep-23 05-Oct-23 05-Oct-23, COLUMN


JAH-Z4-ST-S1-CL.100 Column Rebar Installation 8 09-Sep-23 17-Sep-23 Column Rebar Installation

JAH-Z4-ST-S1-CL.105 Column Formwork Installation 7 18-Sep-23 26-Sep-23 Column Formwork Installation

JAH-Z4-ST-S1-CL.110 Column Concrete Casting 1 27-Sep-23 27-Sep-23 Column Concrete Casting

JAH-Z4-ST-S1-CL.115 Form Work Removal and Curing 7 28-Sep-23 05-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 06-Sep-23 19-Oct-23 19-Oct-23, TUNNEL WALLS


JAH-Z4-ST-S1-TW..100 Tunnel Walls Rebar Installation 8 06-Sep-23 14-Sep-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S1-TW..102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 06-Sep-23 14-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S1-TW..105 Tunnel Formwork Installation 7 16-Sep-23 24-Sep-23 Tunnel Formwork Installation

JAH-Z4-ST-S1-TW..110 Tunnel Walls Concrete Casting 1 25-Sep-23 25-Sep-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S1-TW..112 Curing work 7 26-Sep-23 03-Oct-23 Curing work

JAH-Z4-ST-S1-TW..120 Tunnel Walls Formwork Removel 2 04-Oct-23 05-Oct-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S1-TW..125 Tunnel Wall Waterproofing 12 07-Oct-23 19-Oct-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 07-Oct-23 09-Nov-23 09-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S1-MS.090 Middle Slab Scaffolding 5 07-Oct-23 11-Oct-23 Middle Slab Scaffolding

JAH-Z4-ST-S1-MS.100 Middle Slab Vertical Formwork Installation 7 12-Oct-23 19-Oct-23 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S1-MS.105 Middle Slab Rebar Installation 8 21-Oct-23 29-Oct-23 Middle Slab Rebar Installation

JAH-Z4-ST-S1-MS.110 Middle Slab Concrete Casting 1 30-Oct-23 30-Oct-23 Middle Slab Concrete Casting

JAH-Z4-ST-S1-MS.115 Curing work 7 31-Oct-23 07-Nov-23 Curing work

JAH-Z4-ST-S1-MS.120 Middle Slab Formwork Removel 2 08-Nov-23 09-Nov-23 Middle Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
312 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UTILITY CULVERT WALLS 25 11-Nov-23 09-Dec-23 09-Dec-23, UTILITY CULVERT WALLS
JAH-Z4-ST-S1-UCW.100Utility Culvert Walls Rebar Installation 8 11-Nov-23 19-Nov-23 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S1-UCW.105Utility Culvert Walls Formwork Installation 7 20-Nov-23 27-Nov-23 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S1-UCW.110Utility Culvert Walls Concrete Casting 1 28-Nov-23 28-Nov-23 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S1-UCW.112Curing work 7 29-Nov-23 06-Dec-23 Curing work

JAH-Z4-ST-S1-UCW.115Utility Culvert Walls Walls Formwork Removel 2 07-Dec-23 09-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 10-Dec-23 21-Jan-24 21-Jan-24, TOP SLAB


JAH-Z4-ST-S1-TS.100 Top Slab Rebar Installation 8 10-Dec-23 18-Dec-23 Top Slab Rebar Installation

JAH-Z4-ST-S1-TS.105 Top Slab Formwork Installation 7 19-Dec-23 26-Dec-23 Top Slab Formwork Installation

JAH-Z4-ST-S1-TS.110 Top Slab Concrete Casting 1 27-Dec-23 27-Dec-23 Top Slab Concrete Casting

JAH-Z4-ST-S1-TS.112 Curing work 7 28-Dec-23 04-Jan-24 Curing work

JAH-Z4-ST-S1-TS.115 Top Slab Formwork Removel 2 06-Jan-24 07-Jan-24 Top Slab Formwork Removel

JAH-Z4-ST-S1-TS.120 Waterproofing for Top Slab 12 08-Jan-24 21-Jan-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 22-Jan-24 18-Feb-24 18-Feb-24, MASS CONCRETE WORK


JAH-Z4-ST-S1-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 22-Jan-24 29-Jan-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S1-MC.105 Plain Concrete Casting 1 30-Jan-24 30-Jan-24 Plain Concrete Casting

JAH-Z4-ST-S1-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 31-Jan-24 31-Jan-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S1-MC.112 Curing work 7 01-Feb-24 08-Feb-24 Curing work

JAH-Z4-ST-S1-MC.115 Concrete Protective coating 8 10-Feb-24 18-Feb-24 Concrete Protective coating

STA.1+293.979 ~ 1+313.979 166 17-Aug-23 27-Feb-24 27-Feb-24, STA.1+293.979 ~ 1+313.979


BASE SLAB 29 17-Aug-23 19-Sep-23 19-Sep-23, BASE SLAB
JAH-Z4-ST-S2-BS.100 Lean Concrete for Base Slab 1 17-Aug-23 17-Aug-23 Lean Concrete for Base Slab

JAH-Z4-ST-S2-BS.105 Waterproofing for Lean Concrete 1 19-Aug-23 19-Aug-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S2-BS.110 Base Slab Rebar Installation 8 20-Aug-23 28-Aug-23 Base Slab Rebar Installation

JAH-Z4-ST-S2-BS.115 Base Slab Formwork Installation 7 29-Aug-23 05-Sep-23 Base Slab Formwork Installation

JAH-Z4-ST-S2-BS.120 Base Slab Concrete Casting 1 06-Sep-23 06-Sep-23 Base Slab Concrete Casting

JAH-Z4-ST-S2-BS.122 Curing work 7 07-Sep-23 14-Sep-23 Curing work

JAH-Z4-ST-S2-BS.125 Base Slab Formwork Removel 2 16-Sep-23 17-Sep-23 Base Slab Formwork Removel

JAH-Z4-ST-S2-BS.130 Plain concrete on Base slab 2 18-Sep-23 19-Sep-23 Plain concrete on Base slab

COLUMN 23 20-Sep-23 17-Oct-23 17-Oct-23, COLUMN


JAH-Z4-ST-S2-CL.100 Column Rebar Installation 8 20-Sep-23 30-Sep-23 Column Rebar Installation

JAH-Z4-ST-S2-CL.105 Column Formwork Installation 7 01-Oct-23 08-Oct-23 Column Formwork Installation

JAH-Z4-ST-S2-CL.110 Column Concrete Casting 1 09-Oct-23 09-Oct-23 Column Concrete Casting

JAH-Z4-ST-S2-CL.115 Form Work Removal and Curing 7 10-Oct-23 17-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 18-Sep-23 31-Oct-23 31-Oct-23, TUNNEL WALLS


JAH-Z4-ST-S2-TW..100 Tunnel Walls Rebar Installation 8 18-Sep-23 27-Sep-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S2-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 18-Sep-23 27-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S2-TW..105 Tunnel Formwork Installation 7 28-Sep-23 05-Oct-23 Tunnel Formwork Installation

JAH-Z4-ST-S2-TW..110 Tunnel Walls Concrete Casting 1 07-Oct-23 07-Oct-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S2-TW..112 Curing work 7 08-Oct-23 15-Oct-23 Curing work

JAH-Z4-ST-S2-TW..120 Tunnel Walls Formwork Removel 2 16-Oct-23 17-Oct-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S2-TW..125 Tunnel Wall Waterproofing 12 18-Oct-23 31-Oct-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 25 18-Oct-23 15-Nov-23 15-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S2-MS.100 Middle Slab Vertical Formwork Installation 7 18-Oct-23 25-Oct-23 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S2-MS.105 Middle Slab Rebar Installation 8 26-Oct-23 04-Nov-23 Middle Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
313 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S2-MS.110 Middle Slab Concrete Casting 1 05-Nov-23 05-Nov-23 Middle Slab Concrete Casting

JAH-Z4-ST-S2-MS.115 Curing work 7 06-Nov-23 13-Nov-23 Curing work

JAH-Z4-ST-S2-MS.120 Middle Slab Formwork Removel 2 14-Nov-23 15-Nov-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 16-Nov-23 14-Dec-23 14-Dec-23, UTILITY CULVERT WALLS


JAH-Z4-ST-S2-UCW.100Utility Culvert Walls Rebar Installation 8 16-Nov-23 25-Nov-23 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S2-UCW.105Utility Culvert Walls Formwork Installation 7 26-Nov-23 03-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S2-UCW.110Utility Culvert Walls Concrete Casting 1 04-Dec-23 04-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S2-UCW.112Curing work 7 05-Dec-23 12-Dec-23 Curing work

JAH-Z4-ST-S2-UCW.115Utility Culvert Walls Walls Formwork Removel 2 13-Dec-23 14-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 16-Dec-23 27-Jan-24 27-Jan-24, TOP SLAB


JAH-Z4-ST-S2-TS.100 Top Slab Rebar Installation 8 16-Dec-23 24-Dec-23 Top Slab Rebar Installation

JAH-Z4-ST-S2-TS.105 Top Slab Formwork Installation 7 25-Dec-23 01-Jan-24 Top Slab Formwork Installation

JAH-Z4-ST-S2-TS.110 Top Slab Concrete Casting 1 02-Jan-24 02-Jan-24 Top Slab Concrete Casting

JAH-Z4-ST-S2-TS.112 Curing work 7 03-Jan-24 10-Jan-24 Curing work

JAH-Z4-ST-S2-TS.115 Top Slab Formwork Removel 2 11-Jan-24 13-Jan-24 Top Slab Formwork Removel

JAH-Z4-ST-S2-TS.120 Waterproofing for Top Slab 12 14-Jan-24 27-Jan-24 Waterproofing for Top Slab

MASS CONCRETE WORK 27 28-Jan-24 27-Feb-24 27-Feb-24, MASS CONCRETE WORK


JAH-Z4-ST-S2-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 28-Jan-24 04-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S2-MC.105 Plain Concrete Casting 1 05-Feb-24 05-Feb-24 Plain Concrete Casting

JAH-Z4-ST-S2-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 06-Feb-24 06-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S2-MC.112 Curing work 7 07-Feb-24 14-Feb-24 Curing work

JAH-Z4-ST-S2-MC.115 Concrete Protective coating 8 19-Feb-24 27-Feb-24 Concrete Protective coating

STA. 1+313.979 ~ 1+333.979 164 29-Aug-23 07-Mar-24 07-Mar-24, STA. 1+313.979 ~ 1+333.979
BASE SLAB 29 29-Aug-23 02-Oct-23 02-Oct-23, BASE SLAB
JAH-Z4-ST-S3-BS.100 Lean Concrete for Base Slab 1 29-Aug-23 29-Aug-23 Lean Concrete for Base Slab

JAH-Z4-ST-S3-BS.105 Waterproofing for Lean Concrete 1 30-Aug-23 30-Aug-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S3-BS.110 Base Slab Rebar Installation 8 31-Aug-23 09-Sep-23 Base Slab Rebar Installation

JAH-Z4-ST-S3-BS.115 Base Slab Formwork Installation 7 10-Sep-23 17-Sep-23 Base Slab Formwork Installation

JAH-Z4-ST-S3-BS.120 Base Slab Concrete Casting 1 18-Sep-23 18-Sep-23 Base Slab Concrete Casting

JAH-Z4-ST-S3-BS.122 Curing work 7 19-Sep-23 27-Sep-23 Curing work

JAH-Z4-ST-S3-BS.125 Base Slab Formwork Removel 2 28-Sep-23 30-Sep-23 Base Slab Formwork Removel

JAH-Z4-ST-S3-BS.130 Plain concrete on Base slab 2 01-Oct-23 02-Oct-23 Plain concrete on Base slab

COLUMN 26 19-Sep-23 19-Oct-23 19-Oct-23, COLUMN


JAH-Z4-ST-S3-CL.100 Column Rebar Installation 8 19-Sep-23 28-Sep-23 Column Rebar Installation

JAH-Z4-ST-S3-CL.105 Column Formwork Installation 7 03-Oct-23 10-Oct-23 Column Formwork Installation

JAH-Z4-ST-S3-CL.110 Column Concrete Casting 1 11-Oct-23 11-Oct-23 Column Concrete Casting

JAH-Z4-ST-S3-CL.115 Form Work Removal and Curing 7 12-Oct-23 19-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 37 19-Sep-23 01-Nov-23 01-Nov-23, TUNNEL WALLS


JAH-Z4-ST-S3-TW..100 Tunnel Walls Rebar Installation 8 19-Sep-23 28-Sep-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S3-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 19-Sep-23 28-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S3-TW..105 Tunnel Formwork Installation 7 30-Sep-23 07-Oct-23 Tunnel Formwork Installation

JAH-Z4-ST-S3-TW..110 Tunnel Walls Concrete Casting 1 08-Oct-23 08-Oct-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S3-TW..112 Curing work 7 09-Oct-23 16-Oct-23 Curing work

JAH-Z4-ST-S3-TW..120 Tunnel Walls Formwork Removel 2 17-Oct-23 18-Oct-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S3-TW..125 Tunnel Wall Waterproofing 12 19-Oct-23 01-Nov-23 Tunnel Wall Waterproofing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
314 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
MIDDLE SLAB FOR UTILITY CULVERT 25 19-Oct-23 16-Nov-23 16-Nov-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S3-MS.100 Middle Slab Rebar Installation 8 19-Oct-23 28-Oct-23 Middle Slab Rebar Installation

JAH-Z4-ST-S3-MS.105 Middle Slab Vertical Formwork Installation 7 29-Oct-23 05-Nov-23 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S3-MS.110 Middle Slab Concrete Casting 1 06-Nov-23 06-Nov-23 Middle Slab Concrete Casting

JAH-Z4-ST-S3-MS.115 Curing work 7 07-Nov-23 14-Nov-23 Curing work

JAH-Z4-ST-S3-MS.120 Middle Slab Formwork Removel 2 15-Nov-23 16-Nov-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 18-Nov-23 16-Dec-23 16-Dec-23, UTILITY CULVERT WALLS


JAH-Z4-ST-S3-UCW.100Utility Culvert Walls Rebar Installation 8 18-Nov-23 26-Nov-23 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S3-UCW.105Utility Culvert Walls Formwork Installation 7 27-Nov-23 04-Dec-23 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S3-UCW.110Utility Culvert Walls Concrete Casting 1 05-Dec-23 05-Dec-23 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S3-UCW.112Curing work 7 06-Dec-23 13-Dec-23 Curing work

JAH-Z4-ST-S3-UCW.115Utility Culvert Walls Walls Formwork Removel 2 14-Dec-23 16-Dec-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 17-Dec-23 28-Jan-24 28-Jan-24, TOP SLAB


JAH-Z4-ST-S3-TS.090 Top Slab Formwork Installation 7 17-Dec-23 24-Dec-23 Top Slab Formwork Installation

JAH-Z4-ST-S3-TS.100 Top Slab Rebar Installation 8 25-Dec-23 02-Jan-24 Top Slab Rebar Installation

JAH-Z4-ST-S3-TS.110 Top Slab Concrete Casting 1 03-Jan-24 03-Jan-24 Top Slab Concrete Casting

JAH-Z4-ST-S3-TS.112 Curing work 7 04-Jan-24 11-Jan-24 Curing work

JAH-Z4-ST-S3-TS.115 Top Slab Formwork Removel 2 13-Jan-24 14-Jan-24 Top Slab Formwork Removel

JAH-Z4-ST-S3-TS.120 Waterproofing for Top Slab 12 15-Jan-24 28-Jan-24 Waterproofing for Top Slab

MASS CONCRETE WORK 34 29-Jan-24 07-Mar-24 07-Mar-24, MASS CONCRETE WORK


JAH-Z4-ST-S3-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 29-Jan-24 05-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S3-MC.105 Plain Concrete Casting 1 06-Feb-24 06-Feb-24 Plain Concrete Casting

JAH-Z4-ST-S3-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 07-Feb-24 07-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S3-MC.112 Curing work 7 08-Feb-24 15-Feb-24 Curing work

JAH-Z4-ST-S3-MC.115 Concrete Protective coating 8 28-Feb-24 07-Mar-24 Concrete Protective coating

STA. 1+333.979~ 1+353.979 178 10-Sep-23 04-Apr-24 04-Apr-24, STA. 1+333.979~ 1+353.979
BASE SLAB 36 10-Sep-23 22-Oct-23 22-Oct-23, BASE SLAB
JAH-Z4-ST-S4-BS.100 Lean Concrete for Base Slab 1 10-Sep-23 10-Sep-23 Lean Concrete for Base Slab

JAH-Z4-ST-S4-BS.105 Waterproofing for Lean Concrete 1 11-Sep-23 11-Sep-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S4-BS.110 Base Slab Rebar Installation 8 12-Sep-23 20-Sep-23 Base Slab Rebar Installation

JAH-Z4-ST-S4-BS.115 Base Slab Formwork Installation 7 21-Sep-23 30-Sep-23 Base Slab Formwork Installation

JAH-Z4-ST-S4-BS.120 Base Slab Concrete Casting 1 01-Oct-23 01-Oct-23 Base Slab Concrete Casting

JAH-Z4-ST-S4-BS.122 Curing work 7 02-Oct-23 09-Oct-23 Curing work

JAH-Z4-ST-S4-BS.125 Base Slab Formwork Removel 2 10-Oct-23 11-Oct-23 Base Slab Formwork Removel

JAH-Z4-ST-S4-BS.130 Plain concrete on Base slab 2 12-Oct-23 14-Oct-23 Plain concrete on Base slab

JAH-Z4-ST-S4-BS.135 Curing work 7 15-Oct-23 22-Oct-23 Curing work

COLUMN 24 12-Oct-23 08-Nov-23 08-Nov-23, COLUMN


JAH-Z4-ST-S4-CL.100 Column Rebar Installation 8 12-Oct-23 21-Oct-23 Column Rebar Installation

JAH-Z4-ST-S4-CL.105 Column Formwork Installation 7 23-Oct-23 30-Oct-23 Column Formwork Installation

JAH-Z4-ST-S4-CL.110 Column Concrete Casting 1 31-Oct-23 31-Oct-23 Column Concrete Casting

JAH-Z4-ST-S4-CL.115 Form Work Removal and Curing 7 01-Nov-23 08-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 37 12-Oct-23 23-Nov-23 23-Nov-23, TUNNEL WALLS


JAH-Z4-ST-S4-TW..100 Tunnel Walls Rebar Installation 8 12-Oct-23 21-Oct-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S4-TW..102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 12-Oct-23 21-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S4-TW..105 Tunnel Formwork Installation 7 22-Oct-23 29-Oct-23 Tunnel Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
315 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S4-TW..110 Tunnel Walls Concrete Casting 1 30-Oct-23 30-Oct-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S4-TW..112 Curing work 7 31-Oct-23 07-Nov-23 Curing work

JAH-Z4-ST-S4-TW..120 Tunnel Walls Formwork Removel 2 08-Nov-23 09-Nov-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S4-TW..125 Tunnel Wall Waterproofing 12 11-Nov-23 23-Nov-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 11-Nov-23 14-Dec-23 14-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S4-MS.090 Middle Slab Scaffold and Formwork Installation 5 11-Nov-23 15-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S4-MS.100 Middle Slab Rebar Installation 8 16-Nov-23 25-Nov-23 Middle Slab Rebar Installation

JAH-Z4-ST-S4-MS.105 Middle Slab Vertical Formwork Installation 7 26-Nov-23 03-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S4-MS.110 Middle Slab Concrete Casting 1 04-Dec-23 04-Dec-23 Middle Slab Concrete Casting

JAH-Z4-ST-S4-MS.115 Curing work 7 05-Dec-23 12-Dec-23 Curing work

JAH-Z4-ST-S4-MS.120 Middle Slab Formwork Removel 2 13-Dec-23 14-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 16-Dec-23 13-Jan-24 13-Jan-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S4-UCW.100Utility Culvert Walls Rebar Installation 8 16-Dec-23 24-Dec-23 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S4-UCW.105Utility Culvert Walls Formwork Installation 7 25-Dec-23 01-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S4-UCW.110Utility Culvert Walls Concrete Casting 1 02-Jan-24 02-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S4-UCW.112Curing work 7 03-Jan-24 10-Jan-24 Curing work

JAH-Z4-ST-S4-UCW.115Utility Culvert Walls Walls Formwork Removel 2 11-Jan-24 13-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 14-Jan-24 25-Feb-24 25-Feb-24, TOP SLAB


JAH-Z4-ST-S4-TS.090 Top Slab Formwork Installation 7 14-Jan-24 21-Jan-24 Top Slab Formwork Installation

JAH-Z4-ST-S4-TS.100 Top Slab Rebar Installation 8 22-Jan-24 30-Jan-24 Top Slab Rebar Installation

JAH-Z4-ST-S4-TS.110 Top Slab Concrete Casting 1 31-Jan-24 31-Jan-24 Top Slab Concrete Casting

JAH-Z4-ST-S4-TS.112 Curing work 7 01-Feb-24 08-Feb-24 Curing work

JAH-Z4-ST-S4-TS.115 Top Slab Formwork Removel 2 10-Feb-24 11-Feb-24 Top Slab Formwork Removel

JAH-Z4-ST-S4-TS.120 Waterproofing for Top Slab 12 12-Feb-24 25-Feb-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 09-Mar-24 04-Apr-24 04-Apr-24, MASS CONCRETE WORK


JAH-Z4-ST-S4-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 09-Mar-24 16-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S4-MC.105 Plain Concrete Casting 1 17-Mar-24 17-Mar-24 Plain Concrete Casting

JAH-Z4-ST-S4-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 18-Mar-24 18-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S4-MC.112 Curing work 7 19-Mar-24 26-Mar-24 Curing work

JAH-Z4-ST-S4-MC.115 Concrete Protective coating 8 27-Mar-24 04-Apr-24 Concrete Protective coating

STA. 1+353.979 ~ 1+373.979 184 21-Sep-23 27-Apr-24 27-Apr-24, STA. 1+353.979 ~ 1+373.979
BASE SLAB 29 21-Sep-23 25-Oct-23 25-Oct-23, BASE SLAB
JAH-Z4-ST-S5-BS.100 Lean Concrete for Base Slab 1 21-Sep-23 21-Sep-23 Lean Concrete for Base Slab

JAH-Z4-ST-S5-BS.105 Waterproofing for Lean Concrete 1 24-Sep-23 24-Sep-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S5-BS.110 Base Slab Rebar Installation 8 25-Sep-23 03-Oct-23 Base Slab Rebar Installation

JAH-Z4-ST-S5-BS.115 Base Slab Formwork Installation 7 04-Oct-23 11-Oct-23 Base Slab Formwork Installation

JAH-Z4-ST-S5-BS.120 Base Slab Concrete Casting 1 12-Oct-23 12-Oct-23 Base Slab Concrete Casting

JAH-Z4-ST-S5-BS.122 Curing work 7 14-Oct-23 21-Oct-23 Curing work

JAH-Z4-ST-S5-BS.125 Base Slab Formwork Removel 2 22-Oct-23 23-Oct-23 Base Slab Formwork Removel

JAH-Z4-ST-S5-BS.130 Plain concrete on Base slab 2 24-Oct-23 25-Oct-23 Plain concrete on Base slab

COLUMN 23 26-Oct-23 21-Nov-23 21-Nov-23, COLUMN


JAH-Z4-ST-S5-CL.100 Column Rebar Installation 8 26-Oct-23 04-Nov-23 Column Rebar Installation

JAH-Z4-ST-S5-CL.105 Column Formwork Installation 7 05-Nov-23 12-Nov-23 Column Formwork Installation

JAH-Z4-ST-S5-CL.110 Column Concrete Casting 1 13-Nov-23 13-Nov-23 Column Concrete Casting

JAH-Z4-ST-S5-CL.115 Form Work Removal and Curing 7 14-Nov-23 21-Nov-23 Form Work Removal and Curing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
316 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TUNNEL WALLS 37 24-Oct-23 05-Dec-23 05-Dec-23, TUNNEL WALLS
JAH-Z4-ST-S5-TW..100 Tunnel Walls Rebar Installation 8 24-Oct-23 01-Nov-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S5-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 24-Oct-23 01-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S5-TW..105 Tunnel Formwork Installation 7 02-Nov-23 09-Nov-23 Tunnel Formwork Installation

JAH-Z4-ST-S5-TW..110 Tunnel Walls Concrete Casting 1 11-Nov-23 11-Nov-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S5-TW..112 Curing work 7 12-Nov-23 19-Nov-23 Curing work

JAH-Z4-ST-S5-TW..120 Tunnel Walls Formwork Removel 2 20-Nov-23 21-Nov-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S5-TW..125 Tunnel Wall Waterproofing 12 22-Nov-23 05-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 22-Nov-23 26-Dec-23 26-Dec-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S5-MS.090 Middle Slab Scaffold and Formwork Installation 5 22-Nov-23 27-Nov-23 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S5-MS.100 Middle Slab Rebar Installation 8 28-Nov-23 06-Dec-23 Middle Slab Rebar Installation

JAH-Z4-ST-S5-MS.105 Middle Slab Vertical Formwork Installation 7 07-Dec-23 14-Dec-23 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S5-MS.110 Middle Slab Concrete Casting 1 16-Dec-23 16-Dec-23 Middle Slab Concrete Casting

JAH-Z4-ST-S5-MS.115 Curing work 7 17-Dec-23 24-Dec-23 Curing work

JAH-Z4-ST-S5-MS.120 Middle Slab Formwork Removel 2 25-Dec-23 26-Dec-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 27-Dec-23 24-Jan-24 24-Jan-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S5-UCW.100Utility Culvert Walls Rebar Installation 8 27-Dec-23 04-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S5-UCW.105Utility Culvert Walls Formwork Installation 7 06-Jan-24 13-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S5-UCW.110Utility Culvert Walls Concrete Casting 1 14-Jan-24 14-Jan-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S5-UCW.112Curing work 7 15-Jan-24 22-Jan-24 Curing work

JAH-Z4-ST-S5-UCW.115Utility Culvert Walls Walls Formwork Removel 2 23-Jan-24 24-Jan-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 25-Jan-24 07-Mar-24 07-Mar-24, TOP SLAB


JAH-Z4-ST-S5-TS.090 Top Slab Formwork Installation 7 25-Jan-24 01-Feb-24 Top Slab Formwork Installation

JAH-Z4-ST-S5-TS.100 Top Slab Rebar Installation 8 03-Feb-24 11-Feb-24 Top Slab Rebar Installation

JAH-Z4-ST-S5-TS.110 Top Slab Concrete Casting 1 12-Feb-24 12-Feb-24 Top Slab Concrete Casting

JAH-Z4-ST-S5-TS.112 Curing work 7 13-Feb-24 20-Feb-24 Curing work

JAH-Z4-ST-S5-TS.115 Top Slab Formwork Removel 2 21-Feb-24 22-Feb-24 Top Slab Formwork Removel

JAH-Z4-ST-S5-TS.120 Waterproofing for Top Slab 12 24-Feb-24 07-Mar-24 Waterproofing for Top Slab

MASS CONCRETE WORK 40 09-Mar-24 27-Apr-24 27-Apr-24, MASS CONCRETE WORK


JAH-Z4-ST-S5-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 09-Mar-24 16-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S5-MC.105 Plain Concrete Casting 1 17-Mar-24 17-Mar-24 Plain Concrete Casting

JAH-Z4-ST-S5-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 06-Apr-24 06-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S5-MC.112 Curing work 7 07-Apr-24 17-Apr-24 Curing work

JAH-Z4-ST-S5-MC.115 Concrete Protective coating 8 18-Apr-24 27-Apr-24 Concrete Protective coating

STA. 1+373.979 ~ 1+393.979 184 11-Oct-23 15-May-24 15-May-24, STA. 1+373.979 ~ 1+393.979
BASE SLAB 29 11-Oct-23 13-Nov-23 13-Nov-23, BASE SLAB
JAH-Z4-ST-S6-BS.100 Lean Concrete for Base Slab 1 11-Oct-23 11-Oct-23 Lean Concrete for Base Slab

JAH-Z4-ST-S6-BS.105 Waterproofing for Lean Concrete 1 12-Oct-23 12-Oct-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S6-BS.110 Base Slab Rebar Installation 8 14-Oct-23 22-Oct-23 Base Slab Rebar Installation

JAH-Z4-ST-S6-BS.115 Base Slab Formwork Installation 7 23-Oct-23 30-Oct-23 Base Slab Formwork Installation

JAH-Z4-ST-S6-BS.120 Base Slab Concrete Casting 1 31-Oct-23 31-Oct-23 Base Slab Concrete Casting

JAH-Z4-ST-S6-BS.122 Curing work 7 01-Nov-23 08-Nov-23 Curing work

JAH-Z4-ST-S6-BS.125 Base Slab Formwork Removel 2 09-Nov-23 11-Nov-23 Base Slab Formwork Removel

JAH-Z4-ST-S6-BS.130 Plain concrete on Base slab 2 12-Nov-23 13-Nov-23 Plain concrete on Base slab

COLUMN 23 14-Nov-23 10-Dec-23 10-Dec-23, COLUMN

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
317 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S6-CL.100 Column Rebar Installation 8 14-Nov-23 22-Nov-23 Column Rebar Installation

JAH-Z4-ST-S6-CL.105 Column Formwork Installation 7 23-Nov-23 30-Nov-23 Column Formwork Installation

JAH-Z4-ST-S6-CL.110 Column Concrete Casting 1 02-Dec-23 02-Dec-23 Column Concrete Casting

JAH-Z4-ST-S6-CL.115 Form Work Removal and Curing 7 03-Dec-23 10-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 12-Nov-23 24-Dec-23 24-Dec-23, TUNNEL WALLS


JAH-Z4-ST-S6-TW..100 Tunnel Walls Rebar Installation 8 12-Nov-23 20-Nov-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S6-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 12-Nov-23 20-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S6-TW..105 Tunnel Formwork Installation 7 21-Nov-23 28-Nov-23 Tunnel Formwork Installation

JAH-Z4-ST-S6-TW..110 Tunnel Walls Concrete Casting 1 29-Nov-23 29-Nov-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S6-TW..112 Curing work 7 30-Nov-23 07-Dec-23 Curing work

JAH-Z4-ST-S6-TW..120 Tunnel Walls Formwork Removel 2 09-Dec-23 10-Dec-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S6-TW..125 Tunnel Wall Waterproofing 12 11-Dec-23 24-Dec-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 11-Dec-23 14-Jan-24 14-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S6-MS.090 Middle Slab Scaffold and Formwork Installation 5 11-Dec-23 16-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S6-MS.100 Middle Slab Rebar Installation 8 17-Dec-23 25-Dec-23 Middle Slab Rebar Installation

JAH-Z4-ST-S6-MS.105 Middle Slab Vertical Formwork Installation 7 26-Dec-23 02-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S6-MS.110 Middle Slab Concrete Casting 1 03-Jan-24 03-Jan-24 Middle Slab Concrete Casting

JAH-Z4-ST-S6-MS.115 Curing work 7 04-Jan-24 11-Jan-24 Curing work

JAH-Z4-ST-S6-MS.120 Middle Slab Formwork Removel 2 13-Jan-24 14-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 15-Jan-24 12-Feb-24 12-Feb-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S6-UCW.100Utility Culvert Walls Rebar Installation 8 15-Jan-24 23-Jan-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S6-UCW.105Utility Culvert Walls Formwork Installation 7 24-Jan-24 31-Jan-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S6-UCW.110Utility Culvert Walls Concrete Casting 1 01-Feb-24 01-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S6-UCW.112Curing work 7 03-Feb-24 10-Feb-24 Curing work

JAH-Z4-ST-S6-UCW.115Utility Culvert Walls Walls Formwork Removel 2 11-Feb-24 12-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 13-Feb-24 26-Mar-24 26-Mar-24, TOP SLAB


JAH-Z4-ST-S6-TS.090 Top Slab Formwork Installation 7 13-Feb-24 20-Feb-24 Top Slab Formwork Installation

JAH-Z4-ST-S6-TS.100 Top Slab Rebar Installation 8 21-Feb-24 29-Feb-24 Top Slab Rebar Installation

JAH-Z4-ST-S6-TS.110 Top Slab Concrete Casting 1 02-Mar-24 02-Mar-24 Top Slab Concrete Casting

JAH-Z4-ST-S6-TS.112 Curing work 7 03-Mar-24 10-Mar-24 Curing work

JAH-Z4-ST-S6-TS.115 Top Slab Formwork Removel 2 11-Mar-24 12-Mar-24 Top Slab Formwork Removel

JAH-Z4-ST-S6-TS.120 Waterproofing for Top Slab 12 13-Mar-24 26-Mar-24 Waterproofing for Top Slab

MASS CONCRETE WORK 40 27-Mar-24 15-May-24 15-May-24, MASS CONCRETE WORK


JAH-Z4-ST-S6-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 27-Mar-24 03-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S6-MC.105 Plain Concrete Casting 1 04-Apr-24 04-Apr-24 Plain Concrete Casting

JAH-Z4-ST-S6-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 28-Apr-24 28-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S6-MC.112 Curing work 7 29-Apr-24 06-May-24 Curing work

JAH-Z4-ST-S6-MC.115 Concrete Protective coating 8 07-May-24 15-May-24 Concrete Protective coating

STA.1+393.979 ~ 1+413.979 190 23-Oct-23 03-Jun-24 03-Jun-24, STA.1+393.979 ~ 1+413.979


BASE SLAB 36 23-Oct-23 03-Dec-23 03-Dec-23, BASE SLAB
JAH-Z4-ST-S7-BS.100 Lean Concrete for Base Slab 1 23-Oct-23 23-Oct-23 Lean Concrete for Base Slab

JAH-Z4-ST-S7-BS.105 Waterproofing for Lean Concrete 1 24-Oct-23 24-Oct-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S7-BS.110 Base Slab Rebar Installation 8 25-Oct-23 02-Nov-23 Base Slab Rebar Installation

JAH-Z4-ST-S7-BS.115 Base Slab Formwork Installation 7 04-Nov-23 11-Nov-23 Base Slab Formwork Installation

JAH-Z4-ST-S7-BS.120 Base Slab Concrete Casting 1 12-Nov-23 12-Nov-23 Base Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
318 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S7-BS.122 Curing work 7 13-Nov-23 20-Nov-23 Curing work

JAH-Z4-ST-S7-BS.125 Base Slab Formwork Removel 2 21-Nov-23 22-Nov-23 Base Slab Formwork Removel

JAH-Z4-ST-S7-BS.130 Plain concrete on Base slab 2 23-Nov-23 25-Nov-23 Plain concrete on Base slab

JAH-Z4-ST-S7-BS.135 Curing work 7 26-Nov-23 03-Dec-23 Curing work

COLUMN 24 23-Nov-23 20-Dec-23 20-Dec-23, COLUMN


JAH-Z4-ST-S7-CL.100 Column Rebar Installation 8 23-Nov-23 02-Dec-23 Column Rebar Installation

JAH-Z4-ST-S7-CL.105 Column Formwork Installation 7 04-Dec-23 11-Dec-23 Column Formwork Installation

JAH-Z4-ST-S7-CL.110 Column Concrete Casting 1 12-Dec-23 12-Dec-23 Column Concrete Casting

JAH-Z4-ST-S7-CL.115 Form Work Removal and Curing 7 13-Dec-23 20-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 23-Nov-23 04-Jan-24 04-Jan-24, TUNNEL WALLS


JAH-Z4-ST-S7-TW..100 Tunnel Walls Rebar Installation 8 23-Nov-23 02-Dec-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S7-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 23-Nov-23 02-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S7-TW..105 Tunnel Formwork Installation 7 03-Dec-23 10-Dec-23 Tunnel Formwork Installation

JAH-Z4-ST-S7-TW..110 Tunnel Walls Concrete Casting 1 11-Dec-23 11-Dec-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S7-TW..112 Curing work 7 12-Dec-23 19-Dec-23 Curing work

JAH-Z4-ST-S7-TW..120 Tunnel Walls Formwork Removel 2 20-Dec-23 21-Dec-23 Tunnel Walls Formwork Removel

JAH-Z4-ST-S7-TW..125 Tunnel Wall Waterproofing 12 23-Dec-23 04-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 23-Dec-23 25-Jan-24 25-Jan-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S7-MS.090 Middle Slab Scaffold and Formwork Installation 5 23-Dec-23 27-Dec-23 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S7-MS.100 Middle Slab Rebar Installation 8 28-Dec-23 06-Jan-24 Middle Slab Rebar Installation

JAH-Z4-ST-S7-MS.105 Middle Slab Vertical Formwork Installation 7 07-Jan-24 14-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S7-MS.110 Middle Slab Concrete Casting 1 15-Jan-24 15-Jan-24 Middle Slab Concrete Casting

JAH-Z4-ST-S7-MS.115 Curing work 7 16-Jan-24 23-Jan-24 Curing work

JAH-Z4-ST-S7-MS.120 Middle Slab Formwork Removel 2 24-Jan-24 25-Jan-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 27-Jan-24 24-Feb-24 24-Feb-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S7-UCW.100Utility Culvert Walls Rebar Installation 8 27-Jan-24 04-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S7-UCW.105Utility Culvert Walls Formwork Installation 7 05-Feb-24 12-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S7-UCW.110Utility Culvert Walls Concrete Casting 1 13-Feb-24 13-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S7-UCW.112Curing work 7 14-Feb-24 21-Feb-24 Curing work

JAH-Z4-ST-S7-UCW.115Utility Culvert Walls Walls Formwork Removel 2 22-Feb-24 24-Feb-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 25-Feb-24 07-Apr-24 07-Apr-24, TOP SLAB


JAH-Z4-ST-S7-TS.090 Top Slab Formwork Installation 7 25-Feb-24 03-Mar-24 Top Slab Formwork Installation

JAH-Z4-ST-S7-TS.100 Top Slab Rebar Installation 8 04-Mar-24 12-Mar-24 Top Slab Rebar Installation

JAH-Z4-ST-S7-TS.110 Top Slab Concrete Casting 1 13-Mar-24 13-Mar-24 Top Slab Concrete Casting

JAH-Z4-ST-S7-TS.112 Curing work 7 14-Mar-24 21-Mar-24 Curing work

JAH-Z4-ST-S7-TS.115 Top Slab Formwork Removel 2 23-Mar-24 24-Mar-24 Top Slab Formwork Removel

JAH-Z4-ST-S7-TS.120 Waterproofing for Top Slab 12 25-Mar-24 07-Apr-24 Waterproofing for Top Slab

MASS CONCRETE WORK 46 08-Apr-24 03-Jun-24 03-Jun-24, MASS CONCRETE WORK


JAH-Z4-ST-S7-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 08-Apr-24 18-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S7-MC.105 Plain Concrete Casting 1 20-Apr-24 20-Apr-24 Plain Concrete Casting

JAH-Z4-ST-S7-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 16-May-24 16-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S7-MC.112 Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z4-ST-S7-MC.115 Concrete Protective coating 8 26-May-24 03-Jun-24 Concrete Protective coating

STA. 1+413.979 ~ 1+433.979 196 04-Nov-23 26-Jun-24 26-Jun-24, STA. 1+413.979 ~ 1+433.979
BASE SLAB 36 04-Nov-23 14-Dec-23 14-Dec-23, BASE SLAB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
319 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S8-BS.100 Lean Concrete for Base Slab 1 04-Nov-23 04-Nov-23 Lean Concrete for Base Slab

JAH-Z4-ST-S8-BS.105 Waterproofing for Lean Concrete 1 05-Nov-23 05-Nov-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S8-BS.110 Base Slab Rebar Installation 8 06-Nov-23 14-Nov-23 Base Slab Rebar Installation

JAH-Z4-ST-S8-BS.115 Base Slab Formwork Installation 7 15-Nov-23 22-Nov-23 Base Slab Formwork Installation

JAH-Z4-ST-S8-BS.120 Base Slab Concrete Casting 1 23-Nov-23 23-Nov-23 Base Slab Concrete Casting

JAH-Z4-ST-S8-BS.122 Curing work 7 25-Nov-23 02-Dec-23 Curing work

JAH-Z4-ST-S8-BS.125 Base Slab Formwork Removel 2 03-Dec-23 04-Dec-23 Base Slab Formwork Removel

JAH-Z4-ST-S8-BS.130 Plain concrete on Base slab 2 05-Dec-23 06-Dec-23 Plain concrete on Base slab

JAH-Z4-ST-S8-BS.140 Curing work 7 07-Dec-23 14-Dec-23 Curing work

COLUMN 24 05-Dec-23 01-Jan-24 01-Jan-24, COLUMN


JAH-Z4-ST-S8-CL.100 Column Rebar Installation 8 05-Dec-23 13-Dec-23 Column Rebar Installation

JAH-Z4-ST-S8-CL.105 Column Formwork Installation 7 16-Dec-23 23-Dec-23 Column Formwork Installation

JAH-Z4-ST-S8-CL.110 Column Concrete Casting 1 24-Dec-23 24-Dec-23 Column Concrete Casting

JAH-Z4-ST-S8-CL.115 Form Work Removal and Curing 7 25-Dec-23 01-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 05-Dec-23 16-Jan-24 16-Jan-24, TUNNEL WALLS


JAH-Z4-ST-S8-TW..100 Tunnel Walls Rebar Installation 8 05-Dec-23 13-Dec-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S8-TW..103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 05-Dec-23 13-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S8-TW..105 Tunnel Formwork Installation 7 14-Dec-23 21-Dec-23 Tunnel Formwork Installation

JAH-Z4-ST-S8-TW..110 Tunnel Walls Concrete Casting 1 23-Dec-23 23-Dec-23 Tunnel Walls Concrete Casting

JAH-Z4-ST-S8-TW..112 Curing work 7 24-Dec-23 31-Dec-23 Curing work

JAH-Z4-ST-S8-TW..120 Tunnel Walls Formwork Removel 2 01-Jan-24 02-Jan-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S8-TW..125 Tunnel Wall Waterproofing 12 03-Jan-24 16-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 03-Jan-24 06-Feb-24 06-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S8-MS.090 Middle Slab Scaffold and Formwork Installation 5 03-Jan-24 08-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S8-MS.100 Middle Slab Rebar Installation 8 09-Jan-24 17-Jan-24 Middle Slab Rebar Installation

JAH-Z4-ST-S8-MS.105 Middle Slab Vertical Formwork Installation 7 18-Jan-24 25-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S8-MS.110 Middle Slab Concrete Casting 1 27-Jan-24 27-Jan-24 Middle Slab Concrete Casting

JAH-Z4-ST-S8-MS.115 Curing work 7 28-Jan-24 04-Feb-24 Curing work

JAH-Z4-ST-S8-MS.120 Middle Slab Formwork Removel 2 05-Feb-24 06-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 07-Feb-24 06-Mar-24 06-Mar-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S8-UCW.100Utility Culvert Walls Rebar Installation 8 07-Feb-24 15-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S8-UCW.105Utility Culvert Walls Formwork Installation 7 17-Feb-24 24-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S8-UCW.110Utility Culvert Walls Concrete Casting 1 25-Feb-24 25-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S8-UCW.112Curing work 7 26-Feb-24 04-Mar-24 Curing work

JAH-Z4-ST-S8-UCW.115Utility Culvert Walls Walls Formwork Removel 2 05-Mar-24 06-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 07-Mar-24 22-Apr-24 22-Apr-24, TOP SLAB


JAH-Z4-ST-S8-TS.090 Top Slab Formwork Installation 7 07-Mar-24 14-Mar-24 Top Slab Formwork Installation

JAH-Z4-ST-S8-TS.100 Top Slab Rebar Installation 8 16-Mar-24 24-Mar-24 Top Slab Rebar Installation

JAH-Z4-ST-S8-TS.110 Top Slab Concrete Casting 1 25-Mar-24 25-Mar-24 Top Slab Concrete Casting

JAH-Z4-ST-S8-TS.112 Curing work 7 26-Mar-24 02-Apr-24 Curing work

JAH-Z4-ST-S8-TS.115 Top Slab Formwork Removel 2 03-Apr-24 04-Apr-24 Top Slab Formwork Removel

JAH-Z4-ST-S8-TS.120 Waterproofing for Top Slab 12 06-Apr-24 22-Apr-24 Waterproofing for Top Slab

MASS CONCRETE WORK 52 23-Apr-24 26-Jun-24 26-Jun-24, MASS CONCRETE WORK


JAH-Z4-ST-S8-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 23-Apr-24 30-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S8-MC.105 Plain Concrete Casting 1 01-May-24 01-May-24 Plain Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
320 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S8-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 04-Jun-24 04-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S8-MC.112 Curing work 7 05-Jun-24 12-Jun-24 Curing work

JAH-Z4-ST-S8-MC.115 Concrete Protective coating 8 13-Jun-24 26-Jun-24 Concrete Protective coating

STA. 1+433.979~ 1+453.979 202 15-Nov-23 15-Jul-24 15-Jul-24, STA. 1+433.979~ 1+453.979
BASE SLAB 36 15-Nov-23 26-Dec-23 26-Dec-23, BASE SLAB
JAH-Z4-ST-S9-BS.100 Lean Concrete for Base Slab 1 15-Nov-23 15-Nov-23 Lean Concrete for Base Slab

JAH-Z4-ST-S9-BS.105 Waterproofing for Lean Concrete 1 16-Nov-23 16-Nov-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S9-BS.110 Base Slab Rebar Installation 8 18-Nov-23 26-Nov-23 Base Slab Rebar Installation

JAH-Z4-ST-S9-BS.115 Base Slab Formwork Installation 7 27-Nov-23 04-Dec-23 Base Slab Formwork Installation

JAH-Z4-ST-S9-BS.120 Base Slab Concrete Casting 1 05-Dec-23 05-Dec-23 Base Slab Concrete Casting

JAH-Z4-ST-S9-BS.122 Curing work 7 06-Dec-23 13-Dec-23 Curing work

JAH-Z4-ST-S9-BS.125 Base Slab Formwork Removel 2 14-Dec-23 16-Dec-23 Base Slab Formwork Removel

JAH-Z4-ST-S9-BS.130 Plain concrete on Base slab 2 17-Dec-23 18-Dec-23 Plain concrete on Base slab

JAH-Z4-ST-S9-BS.135 Curing work 7 19-Dec-23 26-Dec-23 Curing work

COLUMN 24 17-Dec-23 13-Jan-24 13-Jan-24, COLUMN


JAH-Z4-ST-S9-CL.100 Column Rebar Installation 8 17-Dec-23 25-Dec-23 Column Rebar Installation

JAH-Z4-ST-S9-CL.105 Column Formwork Installation 7 27-Dec-23 03-Jan-24 Column Formwork Installation

JAH-Z4-ST-S9-CL.110 Column Concrete Casting 1 04-Jan-24 04-Jan-24 Column Concrete Casting

JAH-Z4-ST-S9-CL.115 Form Work Removal and Curing 7 06-Jan-24 13-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 17-Dec-23 28-Jan-24 28-Jan-24, TUNNEL WALLS


JAH-Z4-ST-S9-TW..100 Tunnel Walls Rebar Installation 8 17-Dec-23 25-Dec-23 Tunnel Walls Rebar Installation

JAH-Z4-ST-S9-TW..102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 17-Dec-23 25-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S9-TW..105 Tunnel Formwork Installation 7 26-Dec-23 02-Jan-24 Tunnel Formwork Installation

JAH-Z4-ST-S9-TW..110 Tunnel Walls Concrete Casting 1 03-Jan-24 03-Jan-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S9-TW..112 Curing work 7 04-Jan-24 11-Jan-24 Curing work

JAH-Z4-ST-S9-TW..120 Tunnel Walls Formwork Removel 2 13-Jan-24 14-Jan-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S9-TW..125 Tunnel Wall Waterproofing 12 15-Jan-24 28-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 15-Jan-24 18-Feb-24 18-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S9-MS.090 Middle Slab Scaffold and Formwork Installation 5 15-Jan-24 20-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S9-MS.100 Middle Slab Rebar Installation 8 21-Jan-24 29-Jan-24 Middle Slab Rebar Installation

JAH-Z4-ST-S9-MS.105 Middle Slab Vertical Formwork Installation 7 30-Jan-24 06-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S9-MS.110 Middle Slab Concrete Casting 1 07-Feb-24 07-Feb-24 Middle Slab Concrete Casting

JAH-Z4-ST-S9-MS.115 Curing work 7 08-Feb-24 15-Feb-24 Curing work

JAH-Z4-ST-S9-MS.120 Middle Slab Formwork Removel 2 17-Feb-24 18-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 19-Feb-24 18-Mar-24 18-Mar-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S9-UCW.100Utility Culvert Walls Rebar Installation 8 19-Feb-24 27-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S9-UCW.105Utility Culvert Walls Formwork Installation 7 28-Feb-24 06-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S9-UCW.110Utility Culvert Walls Concrete Casting 1 07-Mar-24 07-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S9-UCW.112Curing work 7 09-Mar-24 16-Mar-24 Curing work

JAH-Z4-ST-S9-UCW.115Utility Culvert Walls Walls Formwork Removel 2 17-Mar-24 18-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 19-Mar-24 04-May-24 04-May-24, TOP SLAB


JAH-Z4-ST-S9-TS.090 Top Slab Formwork Installation 7 19-Mar-24 26-Mar-24 Top Slab Formwork Installation

JAH-Z4-ST-S9-TS.100 Top Slab Rebar Installation 8 27-Mar-24 04-Apr-24 Top Slab Rebar Installation

JAH-Z4-ST-S9-TS.110 Top Slab Concrete Casting 1 06-Apr-24 06-Apr-24 Top Slab Concrete Casting

JAH-Z4-ST-S9-TS.112 Curing work 7 07-Apr-24 17-Apr-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
321 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S9-TS.115 Top Slab Formwork Removel 2 18-Apr-24 20-Apr-24 Top Slab Formwork Removel

JAH-Z4-ST-S9-TS.120 Waterproofing for Top Slab 12 21-Apr-24 04-May-24 Waterproofing for Top Slab

MASS CONCRETE WORK 58 05-May-24 15-Jul-24 15-Jul-24, MASS CONCRETE WORK


JAH-Z4-ST-S9-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 05-May-24 12-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S9-MC.105 Plain Concrete Casting 1 13-May-24 13-May-24 Plain Concrete Casting

JAH-Z4-ST-S9-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 27-Jun-24 27-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S9-MC.112 Curing work 7 29-Jun-24 06-Jul-24 Curing work

JAH-Z4-ST-S9-MC.115 Concrete Protective coating 8 07-Jul-24 15-Jul-24 Concrete Protective coating

STA. 1+453.979~ 1+473.979 208 27-Nov-23 03-Aug-24 03-Aug-24, STA. 1+453.979~ 1+473.979
BASE SLAB 36 27-Nov-23 07-Jan-24 07-Jan-24, BASE SLAB
JAH-Z4-ST-S10-BS.100Lean Concrete for Base Slab 1 27-Nov-23 27-Nov-23 Lean Concrete for Base Slab

JAH-Z4-ST-S10-BS.105Waterproofing for Lean Concrete 1 28-Nov-23 28-Nov-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S10-BS.110 Base Slab Rebar Installation 8 29-Nov-23 07-Dec-23 Base Slab Rebar Installation

JAH-Z4-ST-S10-BS.115 Base Slab Formwork Installation 7 09-Dec-23 16-Dec-23 Base Slab Formwork Installation

JAH-Z4-ST-S10-BS.120Base Slab Concrete Casting 1 17-Dec-23 17-Dec-23 Base Slab Concrete Casting

JAH-Z4-ST-S10-BS.122Curing work 7 18-Dec-23 25-Dec-23 Curing work

JAH-Z4-ST-S10-BS.125Base Slab Formwork Removel 2 26-Dec-23 27-Dec-23 Base Slab Formwork Removel

JAH-Z4-ST-S10-BS.130Plain concrete on Base slab 2 28-Dec-23 30-Dec-23 Plain concrete on Base slab

JAH-Z4-ST-S10-BS.135Curing work 7 31-Dec-23 07-Jan-24 Curing work

COLUMN 24 28-Dec-23 24-Jan-24 24-Jan-24, COLUMN


JAH-Z4-ST-S10-CL.100Column Rebar Installation 8 28-Dec-23 06-Jan-24 Column Rebar Installation

JAH-Z4-ST-S10-CL.105Column Formwork Installation 7 08-Jan-24 15-Jan-24 Column Formwork Installation

JAH-Z4-ST-S10-CL.110 Column Concrete Casting 1 16-Jan-24 16-Jan-24 Column Concrete Casting

JAH-Z4-ST-S10-CL.115 Form Work Removal and Curing 7 17-Jan-24 24-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 28-Dec-23 08-Feb-24 08-Feb-24, TUNNEL WALLS


JAH-Z4-ST-S10-TW.100Tunnel Walls Rebar Installation 8 28-Dec-23 06-Jan-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S10-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Dec-23 06-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S10-TW.105Tunnel Formwork Installation 7 07-Jan-24 14-Jan-24 Tunnel Formwork Installation

JAH-Z4-ST-S10-TW.110Tunnel Walls Concrete Casting 1 15-Jan-24 15-Jan-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S10-TW.112Curing work 7 16-Jan-24 23-Jan-24 Curing work

JAH-Z4-ST-S10-TW.120Tunnel Walls Formwork Removel 2 24-Jan-24 25-Jan-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S10-TW.125Tunnel Wall Waterproofing 12 27-Jan-24 08-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 27-Jan-24 29-Feb-24 29-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S10-MS.090Middle Slab Scaffold and Formwork Installation 5 27-Jan-24 31-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S10-MS.100Middle Slab Rebar Installation 8 01-Feb-24 10-Feb-24 Middle Slab Rebar Installation

JAH-Z4-ST-S10-MS.105Middle Slab Vertical Formwork Installation 7 11-Feb-24 18-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S10-MS.110Middle Slab Concrete Casting 1 19-Feb-24 19-Feb-24 Middle Slab Concrete Casting

JAH-Z4-ST-S10-MS.115Curing work 7 20-Feb-24 27-Feb-24 Curing work

JAH-Z4-ST-S10-MS.120Middle Slab Formwork Removel 2 28-Feb-24 29-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 02-Mar-24 30-Mar-24 30-Mar-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S10-UCW100
Utility Culvert Walls Rebar Installation 8 02-Mar-24 10-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S10-UCW105
Utility Culvert Walls Formwork Installation 7 11-Mar-24 18-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S10-UCW110
Utility Culvert Walls Concrete Casting 1 19-Mar-24 19-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S10-UCW112
Curing work 7 20-Mar-24 27-Mar-24 Curing work

JAH-Z4-ST-S10-UCW115
Utility Culvert Walls Walls Formwork Removel 2 28-Mar-24 30-Mar-24 Utility Culvert Walls Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
322 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 37 31-Mar-24 15-May-24 15-May-24, TOP SLAB
JAH-Z4-ST-S10-TS.090 Top Slab Formwork Installation 7 31-Mar-24 07-Apr-24 Top Slab Formwork Installation

JAH-Z4-ST-S10-TS.100 Top Slab Rebar Installation 8 08-Apr-24 20-Apr-24 Top Slab Rebar Installation

JAH-Z4-ST-S10-TS.110 Top Slab Concrete Casting 1 21-Apr-24 21-Apr-24 Top Slab Concrete Casting

JAH-Z4-ST-S10-TS.112 Curing work 7 22-Apr-24 29-Apr-24 Curing work

JAH-Z4-ST-S10-TS.115 Top Slab Formwork Removel 2 30-Apr-24 01-May-24 Top Slab Formwork Removel

JAH-Z4-ST-S10-TS.120 Waterproofing for Top Slab 12 02-May-24 15-May-24 Waterproofing for Top Slab

MASS CONCRETE WORK 64 16-May-24 03-Aug-24 03-Aug-24, MASS CONCRETE WORK


JAH-Z4-ST-S10-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 16-May-24 23-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S10-MC.105Plain Concrete Casting 1 25-May-24 25-May-24 Plain Concrete Casting

JAH-Z4-ST-S10-MC.110Mass Concrete Casting for Base Slab Top Layer 1 16-Jul-24 16-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S10-MC.112Curing work 7 17-Jul-24 24-Jul-24 Curing work

JAH-Z4-ST-S10-MC.115Concrete Protective coating 8 25-Jul-24 03-Aug-24 Concrete Protective coating

STA. 1+473.979~ 1+493.979 207 16-Dec-23 20-Aug-24 20-Aug-24, STA. 1+473.979~ 1+493.979
BASE SLAB 36 16-Dec-23 25-Jan-24 25-Jan-24, BASE SLAB
JAH-Z4-ST-S11-BS.100 Lean Concrete for Base Slab 1 16-Dec-23 16-Dec-23 Lean Concrete for Base Slab

JAH-Z4-ST-S11-BS.105 Waterproofing for Lean Concrete 1 17-Dec-23 17-Dec-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S11-BS.110 Base Slab Rebar Installation 8 18-Dec-23 26-Dec-23 Base Slab Rebar Installation

JAH-Z4-ST-S11-BS.115 Base Slab Formwork Installation 7 27-Dec-23 03-Jan-24 Base Slab Formwork Installation

JAH-Z4-ST-S11-BS.120 Base Slab Concrete Casting 1 04-Jan-24 04-Jan-24 Base Slab Concrete Casting

JAH-Z4-ST-S11-BS.122 Curing work 7 06-Jan-24 13-Jan-24 Curing work

JAH-Z4-ST-S11-BS.125 Base Slab Formwork Removel 2 14-Jan-24 15-Jan-24 Base Slab Formwork Removel

JAH-Z4-ST-S11-BS.130 Plain concrete on Base slab 2 16-Jan-24 17-Jan-24 Plain concrete on Base slab

JAH-Z4-ST-S11-BS.135 Curing work 7 18-Jan-24 25-Jan-24 Curing work

COLUMN 24 16-Jan-24 12-Feb-24 12-Feb-24, COLUMN


JAH-Z4-ST-S11-CL.100 Column Rebar Installation 8 16-Jan-24 24-Jan-24 Column Rebar Installation

JAH-Z4-ST-S11-CL.105 Column Formwork Installation 7 27-Jan-24 03-Feb-24 Column Formwork Installation

JAH-Z4-ST-S11-CL.110 Column Concrete Casting 1 04-Feb-24 04-Feb-24 Column Concrete Casting

JAH-Z4-ST-S11-CL.115 Form Work Removal and Curing 7 05-Feb-24 12-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 16-Jan-24 27-Feb-24 27-Feb-24, TUNNEL WALLS


JAH-Z4-ST-S11-TW.100Tunnel Walls Rebar Installation 8 16-Jan-24 24-Jan-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S11-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 16-Jan-24 24-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S11-TW.105Tunnel Formwork Installation 7 25-Jan-24 01-Feb-24 Tunnel Formwork Installation

JAH-Z4-ST-S11-TW.110Tunnel Walls Concrete Casting 1 03-Feb-24 03-Feb-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S11-TW.112Curing work 7 04-Feb-24 11-Feb-24 Curing work

JAH-Z4-ST-S11-TW.120Tunnel Walls Formwork Removel 2 12-Feb-24 13-Feb-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S11-TW.125Tunnel Wall Waterproofing 12 14-Feb-24 27-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 14-Feb-24 19-Mar-24 19-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S11-MS.090Middle Slab Scaffold and Formwork Installation 5 14-Feb-24 19-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S11-MS.100Middle Slab Rebar Installation 8 20-Feb-24 28-Feb-24 Middle Slab Rebar Installation

JAH-Z4-ST-S11-MS.105Middle Slab Vertical Formwork Installation 7 29-Feb-24 07-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S11-MS.110Middle Slab Concrete Casting 1 09-Mar-24 09-Mar-24 Middle Slab Concrete Casting

JAH-Z4-ST-S11-MS.115Curing work 7 10-Mar-24 17-Mar-24 Curing work

JAH-Z4-ST-S11-MS.120Middle Slab Formwork Removel 2 18-Mar-24 19-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 20-Mar-24 21-Apr-24 21-Apr-24, UTILITY CULVERT WALLS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
323 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S11-UCW100
Utility Culvert Walls Rebar Installation 8 20-Mar-24 28-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S11-UCW105
Utility Culvert Walls Formwork Installation 7 30-Mar-24 06-Apr-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S11-UCW110
Utility Culvert Walls Concrete Casting 1 07-Apr-24 07-Apr-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S11-UCW112
Curing work 7 08-Apr-24 18-Apr-24 Curing work

JAH-Z4-ST-S11-UCW115
Utility Culvert Walls Walls Formwork Removel 2 20-Apr-24 21-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 22-Apr-24 03-Jun-24 03-Jun-24, TOP SLAB


JAH-Z4-ST-S11-TS.090 Top Slab Formwork Installation 7 22-Apr-24 29-Apr-24 Top Slab Formwork Installation

JAH-Z4-ST-S11-TS.100 Top Slab Rebar Installation 8 30-Apr-24 08-May-24 Top Slab Rebar Installation

JAH-Z4-ST-S11-TS.110 Top Slab Concrete Casting 1 09-May-24 09-May-24 Top Slab Concrete Casting

JAH-Z4-ST-S11-TS.112 Curing work 7 11-May-24 18-May-24 Curing work

JAH-Z4-ST-S11-TS.115 Top Slab Formwork Removel 2 19-May-24 20-May-24 Top Slab Formwork Removel

JAH-Z4-ST-S11-TS.120 Waterproofing for Top Slab 12 21-May-24 03-Jun-24 Waterproofing for Top Slab

MASS CONCRETE WORK 63 04-Jun-24 20-Aug-24 20-Aug-24, MASS CONCRETE WORK


JAH-Z4-ST-S11-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 04-Jun-24 11-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S11-MC.105Plain Concrete Casting 1 12-Jun-24 12-Jun-24 Plain Concrete Casting

JAH-Z4-ST-S11-MC.110Mass Concrete Casting for Base Slab Top Layer 1 13-Jun-24 13-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S11-MC.112Curing work 7 04-Aug-24 11-Aug-24 Curing work

JAH-Z4-ST-S11-MC.115Concrete Protective coating 8 12-Aug-24 20-Aug-24 Concrete Protective coating

STA. 1+493.979 ~ 1+513.979 213 27-Dec-23 08-Sep-24 08-Sep-24, STA. 1+493.979 ~ 1+513.979
BASE SLAB 36 27-Dec-23 06-Feb-24 06-Feb-24, BASE SLAB
JAH-Z4-ST-S12-BS.100Lean Concrete for Base Slab 1 27-Dec-23 27-Dec-23 Lean Concrete for Base Slab

JAH-Z4-ST-S12-BS.105Waterproofing for Lean Concrete 1 28-Dec-23 28-Dec-23 Waterproofing for Lean Concrete

JAH-Z4-ST-S12-BS.110 Base Slab Rebar Installation 8 30-Dec-23 07-Jan-24 Base Slab Rebar Installation

JAH-Z4-ST-S12-BS.115 Base Slab Formwork Installation 7 08-Jan-24 15-Jan-24 Base Slab Formwork Installation

JAH-Z4-ST-S12-BS.120Base Slab Concrete Casting 1 16-Jan-24 16-Jan-24 Base Slab Concrete Casting

JAH-Z4-ST-S12-BS.122Curing work 7 17-Jan-24 24-Jan-24 Curing work

JAH-Z4-ST-S12-BS.125Base Slab Formwork Removel 2 25-Jan-24 27-Jan-24 Base Slab Formwork Removel

JAH-Z4-ST-S12-BS.130Plain concrete on Base slab 2 28-Jan-24 29-Jan-24 Plain concrete on Base slab

JAH-Z4-ST-S12-BS.135Curing work 7 30-Jan-24 06-Feb-24 Curing work

COLUMN 24 28-Jan-24 24-Feb-24 24-Feb-24, COLUMN


JAH-Z4-ST-S12-CL.100Column Rebar Installation 8 28-Jan-24 05-Feb-24 Column Rebar Installation

JAH-Z4-ST-S12-CL.105Column Formwork Installation 7 07-Feb-24 14-Feb-24 Column Formwork Installation

JAH-Z4-ST-S12-CL.110 Column Concrete Casting 1 15-Feb-24 15-Feb-24 Column Concrete Casting

JAH-Z4-ST-S12-CL.115 Form Work Removal and Curing 7 17-Feb-24 24-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 28-Jan-24 10-Mar-24 10-Mar-24, TUNNEL WALLS


JAH-Z4-ST-S12-TW.100Tunnel Walls Rebar Installation 8 28-Jan-24 05-Feb-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S12-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Jan-24 05-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S12-TW.105Tunnel Formwork Installation 7 06-Feb-24 13-Feb-24 Tunnel Formwork Installation

JAH-Z4-ST-S12-TW.110Tunnel Walls Concrete Casting 1 14-Feb-24 14-Feb-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S12-TW.112Curing work 7 15-Feb-24 22-Feb-24 Curing work

JAH-Z4-ST-S12-TW.120Tunnel Walls Formwork Removel 2 24-Feb-24 25-Feb-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S12-TW.125Tunnel Wall Waterproofing 12 26-Feb-24 10-Mar-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 26-Feb-24 31-Mar-24 31-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S12-MS.090Middle Slab Scaffold and Formwork Installation 5 26-Feb-24 02-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S12-MS.100Middle Slab Rebar Installation 8 03-Mar-24 11-Mar-24 Middle Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
324 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S12-MS.105Middle Slab Vertical Formwork Installation 7 12-Mar-24 19-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S12-MS.110Middle Slab Concrete Casting 1 20-Mar-24 20-Mar-24 Middle Slab Concrete Casting

JAH-Z4-ST-S12-MS.115Curing work 7 21-Mar-24 28-Mar-24 Curing work

JAH-Z4-ST-S12-MS.120Middle Slab Formwork Removel 2 30-Mar-24 31-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 01-Apr-24 02-May-24 02-May-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S12-UCW100
Utility Culvert Walls Rebar Installation 8 01-Apr-24 13-Apr-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S12-UCW105
Utility Culvert Walls Formwork Installation 7 14-Apr-24 21-Apr-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S12-UCW110
Walls Concrete Casting 1 22-Apr-24 22-Apr-24 Walls Concrete Casting

JAH-Z4-ST-S12-UCW112
Curing work 7 23-Apr-24 30-Apr-24 Curing work

JAH-Z4-ST-S12-UCW115
Utility Culvert Walls Walls Formwork Removel 2 01-May-24 02-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 04-May-24 19-Jun-24 19-Jun-24, TOP SLAB


JAH-Z4-ST-S12-TS.090 Top Slab Formwork Installation 7 04-May-24 11-May-24 Top Slab Formwork Installation

JAH-Z4-ST-S12-TS.100 Top Slab Rebar Installation 8 12-May-24 20-May-24 Top Slab Rebar Installation

JAH-Z4-ST-S12-TS.110 Top Slab Concrete Casting 1 21-May-24 21-May-24 Top Slab Concrete Casting

JAH-Z4-ST-S12-TS.112 Curing work 7 22-May-24 29-May-24 Curing work

JAH-Z4-ST-S12-TS.115 Top Slab Formwork Removel 2 30-May-24 01-Jun-24 Top Slab Formwork Removel

JAH-Z4-ST-S12-TS.120 Waterproofing for Top Slab 12 02-Jun-24 19-Jun-24 Waterproofing for Top Slab

MASS CONCRETE WORK 69 20-Jun-24 08-Sep-24 08-Sep-24, MASS CONCRETE WORK


JAH-Z4-ST-S12-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 20-Jun-24 27-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S12-MC.105Plain Concrete Casting 1 29-Jun-24 29-Jun-24 Plain Concrete Casting

JAH-Z4-ST-S12-MC.110Mass Concrete Casting for Base Slab Top Layer 1 21-Aug-24 21-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S12-MC.112Curing work 7 22-Aug-24 29-Aug-24 Curing work

JAH-Z4-ST-S12-MC.115Concrete Protective coating 8 31-Aug-24 08-Sep-24 Concrete Protective coating

STA. 1+513.979 ~ 1+533.979 218 08-Jan-24 26-Sep-24 26-Sep-24, STA. 1+513.979 ~ 1+533.979
BASE SLAB 36 08-Jan-24 18-Feb-24 18-Feb-24, BASE SLAB
JAH-Z4-ST-S13-BS.100Lean Concrete for Base Slab 1 08-Jan-24 08-Jan-24 Lean Concrete for Base Slab

JAH-Z4-ST-S13-BS.105Waterproofing for Lean Concrete 1 09-Jan-24 09-Jan-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S13-BS.110 Base Slab Rebar Installation 8 10-Jan-24 18-Jan-24 Base Slab Rebar Installation

JAH-Z4-ST-S13-BS.115 Base Slab Formwork Installation 7 20-Jan-24 27-Jan-24 Base Slab Formwork Installation

JAH-Z4-ST-S13-BS.120Base Slab Concrete Casting 1 28-Jan-24 28-Jan-24 Base Slab Concrete Casting

JAH-Z4-ST-S13-BS.122Curing work 7 29-Jan-24 05-Feb-24 Curing work

JAH-Z4-ST-S13-BS.125Base Slab Formwork Removel 2 06-Feb-24 07-Feb-24 Base Slab Formwork Removel

JAH-Z4-ST-S13-BS.130Plain concrete on Base slab 2 08-Feb-24 10-Feb-24 Plain concrete on Base slab

JAH-Z4-ST-S13-BS.135Curing work 7 11-Feb-24 18-Feb-24 Curing work

COLUMN 23 19-Feb-24 16-Mar-24 16-Mar-24, COLUMN


JAH-Z4-ST-S13-CL.100Column Rebar Installation 8 19-Feb-24 27-Feb-24 Column Rebar Installation

JAH-Z4-ST-S13-CL.105Column Formwork Installation 7 28-Feb-24 06-Mar-24 Column Formwork Installation

JAH-Z4-ST-S13-CL.110 Column Concrete Casting 1 07-Mar-24 07-Mar-24 Column Concrete Casting

JAH-Z4-ST-S13-CL.115 Form Work Removal and Curing 7 09-Mar-24 16-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 08-Feb-24 21-Mar-24 21-Mar-24, TUNNEL WALLS


JAH-Z4-ST-S13-TW.100Tunnel Walls Rebar Installation 8 08-Feb-24 17-Feb-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S13-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 08-Feb-24 17-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S13-TW.105Tunnel Formwork Installation 7 18-Feb-24 25-Feb-24 Tunnel Formwork Installation

JAH-Z4-ST-S13-TW.110Tunnel Walls Concrete Casting 1 26-Feb-24 26-Feb-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S13-TW.112Curing work 7 27-Feb-24 05-Mar-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
325 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S13-TW.120Tunnel Walls Formwork Removel 2 06-Mar-24 07-Mar-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S13-TW.125Tunnel Wall Waterproofing 12 09-Mar-24 21-Mar-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 09-Mar-24 15-Apr-24 15-Apr-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S13-MS.090Middle Slab Scaffold and Formwork Installation 5 09-Mar-24 13-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S13-MS.100Middle Slab Rebar Installation 8 14-Mar-24 23-Mar-24 Middle Slab Rebar Installation

JAH-Z4-ST-S13-MS.105Middle Slab Vertical Formwork Installation 7 24-Mar-24 31-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S13-MS.110Middle Slab Concrete Casting 1 01-Apr-24 01-Apr-24 Middle Slab Concrete Casting

JAH-Z4-ST-S13-MS.115Curing work 7 02-Apr-24 13-Apr-24 Curing work

JAH-Z4-ST-S13-MS.120Middle Slab Formwork Removel 2 14-Apr-24 15-Apr-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 16-Apr-24 14-May-24 14-May-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S13-UCW100
Utility Culvert Walls Rebar Installation 8 16-Apr-24 24-Apr-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S13-UCW105
Utility Culvert Walls Formwork Installation 7 25-Apr-24 02-May-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S13-UCW110
Utility Culvert Walls Concrete Casting 1 04-May-24 04-May-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S13-UCW112
Curing work 7 05-May-24 12-May-24 Curing work

JAH-Z4-ST-S13-UCW115
Utility Culvert Walls Walls Formwork Removel 2 13-May-24 14-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 15-May-24 01-Jul-24 01-Jul-24, TOP SLAB


JAH-Z4-ST-S13-TS.090 Top Slab Formwork Installation 7 15-May-24 22-May-24 Top Slab Formwork Installation

JAH-Z4-ST-S13-TS.100 Top Slab Rebar Installation 8 23-May-24 01-Jun-24 Top Slab Rebar Installation

JAH-Z4-ST-S13-TS.110 Top Slab Concrete Casting 1 02-Jun-24 02-Jun-24 Top Slab Concrete Casting

JAH-Z4-ST-S13-TS.112 Curing work 7 03-Jun-24 10-Jun-24 Curing work

JAH-Z4-ST-S13-TS.115 Top Slab Formwork Removel 2 11-Jun-24 12-Jun-24 Top Slab Formwork Removel

JAH-Z4-ST-S13-TS.120 Waterproofing for Top Slab 12 13-Jun-24 01-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 74 02-Jul-24 26-Sep-24 26-Sep-24, MASS CONCRETE WORK


JAH-Z4-ST-S13-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 02-Jul-24 09-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S13-MC.105Plain Concrete Casting 1 10-Jul-24 10-Jul-24 Plain Concrete Casting

JAH-Z4-ST-S13-MC.110Mass Concrete Casting for Base Slab Top Layer 1 11-Jul-24 11-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S13-MC.112Curing work 7 09-Sep-24 16-Sep-24 Curing work

JAH-Z4-ST-S13-MC.115Concrete Protective coating 8 17-Sep-24 26-Sep-24 Concrete Protective coating

STA. 1+533.979 ~ 1+553.979 224 20-Jan-24 15-Oct-24 15-Oct-24, STA. 1+533.979 ~ 1+553.979
BASE SLAB 36 20-Jan-24 29-Feb-24 29-Feb-24, BASE SLAB
JAH-Z4-ST-S14-BS.100Lean Concrete for Base Slab 1 20-Jan-24 20-Jan-24 Lean Concrete for Base Slab

JAH-Z4-ST-S14-BS.105Waterproofing for Lean Concrete 1 21-Jan-24 21-Jan-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S14-BS.110 Base Slab Rebar Installation 8 22-Jan-24 30-Jan-24 Base Slab Rebar Installation

JAH-Z4-ST-S14-BS.115 Base Slab Formwork Installation 7 31-Jan-24 07-Feb-24 Base Slab Formwork Installation

JAH-Z4-ST-S14-BS.120Base Slab Concrete Casting 1 08-Feb-24 08-Feb-24 Base Slab Concrete Casting

JAH-Z4-ST-S14-BS.122Curing work 7 10-Feb-24 17-Feb-24 Curing work

JAH-Z4-ST-S14-BS.125Base Slab Formwork Removel 2 18-Feb-24 19-Feb-24 Base Slab Formwork Removel

JAH-Z4-ST-S14-BS.130Plain concrete on Base slab 2 20-Feb-24 21-Feb-24 Plain concrete on Base slab

JAH-Z4-ST-S14-BS.135Curing work 7 22-Feb-24 29-Feb-24 Curing work

COLUMN 23 02-Mar-24 27-Mar-24 27-Mar-24, COLUMN


JAH-Z4-ST-S14-CL.100Column Rebar Installation 8 02-Mar-24 10-Mar-24 Column Rebar Installation

JAH-Z4-ST-S14-CL.105Column Formwork Installation 7 11-Mar-24 18-Mar-24 Column Formwork Installation

JAH-Z4-ST-S14-CL.110 Column Concrete Casting 1 19-Mar-24 19-Mar-24 Column Concrete Casting

JAH-Z4-ST-S14-CL.115 Form Work Removal and Curing 7 20-Mar-24 27-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 20-Feb-24 02-Apr-24 02-Apr-24, TUNNEL WALLS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
326 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S14-TW.100Tunnel Walls Rebar Installation 8 20-Feb-24 28-Feb-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S14-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 20-Feb-24 28-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S14-TW.105Tunnel Formwork Installation 7 29-Feb-24 07-Mar-24 Tunnel Formwork Installation

JAH-Z4-ST-S14-TW.110Tunnel Walls Concrete Casting 1 09-Mar-24 09-Mar-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S14-TW.112Curing work 7 10-Mar-24 17-Mar-24 Curing work

JAH-Z4-ST-S14-TW.120Tunnel Walls Formwork Removel 2 18-Mar-24 19-Mar-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S14-TW.125Tunnel Wall Waterproofing 12 20-Mar-24 02-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-Mar-24 05-May-24 05-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S14-MS.090Middle Slab Scaffold and Formwork Installation 5 28-Mar-24 02-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S14-MS.100Middle Slab Rebar Installation 8 03-Apr-24 15-Apr-24 Middle Slab Rebar Installation

JAH-Z4-ST-S14-MS.105Middle Slab Vertical Formwork Installation 7 16-Apr-24 23-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S14-MS.110Middle Slab Concrete Casting 1 24-Apr-24 24-Apr-24 Middle Slab Concrete Casting

JAH-Z4-ST-S14-MS.115Curing work 7 25-Apr-24 02-May-24 Curing work

JAH-Z4-ST-S14-MS.120Middle Slab Formwork Removel 2 04-May-24 05-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 06-May-24 03-Jun-24 03-Jun-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S14-UCW100
Utility Culvert Walls Rebar Installation 8 06-May-24 14-May-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S14-UCW105
Utility Culvert Walls Formwork Installation 7 15-May-24 22-May-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S14-UCW110
Utility Culvert Walls Concrete Casting 1 23-May-24 23-May-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S14-UCW112
Curing work 7 25-May-24 01-Jun-24 Curing work

JAH-Z4-ST-S14-UCW115
Utility Culvert Walls Walls Formwork Removel 2 02-Jun-24 03-Jun-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 04-Jun-24 21-Jul-24 21-Jul-24, TOP SLAB


JAH-Z4-ST-S14-TS.090 Top Slab Formwork Installation 7 04-Jun-24 11-Jun-24 Top Slab Formwork Installation

JAH-Z4-ST-S14-TS.100 Top Slab Rebar Installation 8 12-Jun-24 25-Jun-24 Top Slab Rebar Installation

JAH-Z4-ST-S14-TS.110 Top Slab Concrete Casting 1 26-Jun-24 26-Jun-24 Top Slab Concrete Casting

JAH-Z4-ST-S14-TS.112 Curing work 7 27-Jun-24 04-Jul-24 Curing work

JAH-Z4-ST-S14-TS.115 Top Slab Formwork Removel 2 06-Jul-24 07-Jul-24 Top Slab Formwork Removel

JAH-Z4-ST-S14-TS.120 Waterproofing for Top Slab 12 08-Jul-24 21-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 73 22-Jul-24 15-Oct-24 15-Oct-24, MASS CONCRETE WORK


JAH-Z4-ST-S14-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 22-Jul-24 29-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S14-MC.105Plain Concrete Casting 1 30-Jul-24 30-Jul-24 Plain Concrete Casting

JAH-Z4-ST-S14-MC.110Mass Concrete Casting for Base Slab Top Layer 1 28-Sep-24 28-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S14-MC.112Curing work 7 29-Sep-24 06-Oct-24 Curing work

JAH-Z4-ST-S14-MC.115Concrete Protective coating 8 07-Oct-24 15-Oct-24 Concrete Protective coating

STA. 1+553.979~ 1+573.979 230 22-Jan-24 24-Oct-24 24-Oct-24, STA. 1+553.979~ 1+573.979
BASE SLAB 36 22-Jan-24 03-Mar-24 03-Mar-24, BASE SLAB
JAH-Z4-ST-S15-BS.100Lean Concrete for Base Slab 1 22-Jan-24 22-Jan-24 Lean Concrete for Base Slab

JAH-Z4-ST-S15-BS.105Waterproofing for Lean Concrete 1 23-Jan-24 23-Jan-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S15-BS.110 Base Slab Rebar Installation 8 24-Jan-24 01-Feb-24 Base Slab Rebar Installation

JAH-Z4-ST-S15-BS.115 Base Slab Formwork Installation 7 03-Feb-24 10-Feb-24 Base Slab Formwork Installation

JAH-Z4-ST-S15-BS.120Base Slab Concrete Casting 1 11-Feb-24 11-Feb-24 Base Slab Concrete Casting

JAH-Z4-ST-S15-BS.122Curing work 7 12-Feb-24 19-Feb-24 Curing work

JAH-Z4-ST-S15-BS.125Base Slab Formwork Removel 2 20-Feb-24 21-Feb-24 Base Slab Formwork Removel

JAH-Z4-ST-S15-BS.130Plain concrete on Base slab 2 22-Feb-24 24-Feb-24 Plain concrete on Base slab

JAH-Z4-ST-S15-BS.135Curing work 7 25-Feb-24 03-Mar-24 Curing work

COLUMN 23 04-Mar-24 30-Mar-24 30-Mar-24, COLUMN

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
327 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S15-CL.100Column Rebar Installation 8 04-Mar-24 12-Mar-24 Column Rebar Installation

JAH-Z4-ST-S15-CL.105Column Formwork Installation 7 13-Mar-24 20-Mar-24 Column Formwork Installation

JAH-Z4-ST-S15-CL.110 Column Concrete Casting 1 21-Mar-24 21-Mar-24 Column Concrete Casting

JAH-Z4-ST-S15-CL.115 Form Work Removal and Curing 7 23-Mar-24 30-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 22-Feb-24 04-Apr-24 04-Apr-24, TUNNEL WALLS


JAH-Z4-ST-S15-TW.100Tunnel Walls Rebar Installation 8 22-Feb-24 02-Mar-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S15-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-Feb-24 02-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S15-TW.105Tunnel Formwork Installation 7 03-Mar-24 10-Mar-24 Tunnel Formwork Installation

JAH-Z4-ST-S15-TW.110Tunnel Walls Concrete Casting 1 11-Mar-24 11-Mar-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S15-TW.112Curing work 7 12-Mar-24 19-Mar-24 Curing work

JAH-Z4-ST-S15-TW.120Tunnel Walls Formwork Removel 2 20-Mar-24 21-Mar-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S15-TW.125Tunnel Wall Waterproofing 12 23-Mar-24 04-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 46 12-Mar-24 07-May-24 07-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S15-MS.090Middle Slab Scaffold and Formwork Installation 5 12-Mar-24 17-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S15-MS.100Middle Slab Rebar Installation 8 06-Apr-24 17-Apr-24 Middle Slab Rebar Installation

JAH-Z4-ST-S15-MS.105Middle Slab Vertical Formwork Installation 7 18-Apr-24 25-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S15-MS.110Middle Slab Concrete Casting 1 27-Apr-24 27-Apr-24 Middle Slab Concrete Casting

JAH-Z4-ST-S15-MS.115Curing work 7 28-Apr-24 05-May-24 Curing work

JAH-Z4-ST-S15-MS.120Middle Slab Formwork Removel 2 06-May-24 07-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 28-Apr-24 26-May-24 26-May-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S15-UCW100
Utility Culvert Walls Rebar Installation 8 28-Apr-24 06-May-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S15-UCW105
Utility Culvert Walls Formwork Installation 7 07-May-24 14-May-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S15-UCW110
Utility Culvert Walls Concrete Casting 1 15-May-24 15-May-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S15-UCW112
Curing work 7 16-May-24 23-May-24 Curing work

JAH-Z4-ST-S15-UCW115
Utility Culvert Walls Walls Formwork Removel 2 25-May-24 26-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 16-May-24 02-Jul-24 02-Jul-24, TOP SLAB


JAH-Z4-ST-S15-TS.090 Top Slab Formwork Installation 7 16-May-24 23-May-24 Top Slab Formwork Installation

JAH-Z4-ST-S15-TS.100 Top Slab Rebar Installation 8 25-May-24 02-Jun-24 Top Slab Rebar Installation

JAH-Z4-ST-S15-TS.110 Top Slab Concrete Casting 1 03-Jun-24 03-Jun-24 Top Slab Concrete Casting

JAH-Z4-ST-S15-TS.112 Curing work 7 04-Jun-24 11-Jun-24 Curing work

JAH-Z4-ST-S15-TS.115 Top Slab Formwork Removel 2 12-Jun-24 13-Jun-24 Top Slab Formwork Removel

JAH-Z4-ST-S15-TS.120 Waterproofing for Top Slab 12 19-Jun-24 02-Jul-24 Waterproofing for Top Slab

MASS CONCRETE WORK 97 03-Jul-24 24-Oct-24 24-Oct-24, MASS CONCRETE WORK


JAH-Z4-ST-S15-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 03-Jul-24 10-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S15-MC.105Plain Concrete Casting 1 11-Jul-24 11-Jul-24 Plain Concrete Casting

JAH-Z4-ST-S15-MC.110Mass Concrete Casting for Base Slab Top Layer 1 13-Jul-24 13-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S15-MC.112Curing work 7 14-Jul-24 21-Jul-24 Curing work

JAH-Z4-ST-S15-MC.115Concrete Protective coating 8 16-Oct-24 24-Oct-24 Concrete Protective coating

STA. 1+573.979-~ 1+593.979 214 19-Feb-24 03-Nov-24 03-Nov-24, STA. 1+573.979-~ 1+593.979
BASE SLAB 36 19-Feb-24 31-Mar-24 31-Mar-24, BASE SLAB
JAH-Z4-ST-S16-BS.100Lean Concrete for Base Slab 1 19-Feb-24 19-Feb-24 Lean Concrete for Base Slab

JAH-Z4-ST-S16-BS.105Waterproofing for Lean Concrete 1 20-Feb-24 20-Feb-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S16-BS.110 Base Slab Rebar Installation 8 21-Feb-24 29-Feb-24 Base Slab Rebar Installation

JAH-Z4-ST-S16-BS.115 Base Slab Formwork Installation 7 02-Mar-24 09-Mar-24 Base Slab Formwork Installation

JAH-Z4-ST-S16-BS.120Base Slab Concrete Casting 1 10-Mar-24 10-Mar-24 Base Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
328 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S16-BS.122Curing work 7 11-Mar-24 18-Mar-24 Curing work

JAH-Z4-ST-S16-BS.125Base Slab Formwork Removel 2 19-Mar-24 20-Mar-24 Base Slab Formwork Removel

JAH-Z4-ST-S16-BS.130Plain concrete on Base slab 2 21-Mar-24 23-Mar-24 Plain concrete on Base slab

JAH-Z4-ST-S16-BS.135Curing work 7 24-Mar-24 31-Mar-24 Curing work

COLUMN 23 01-Apr-24 30-Apr-24 30-Apr-24, COLUMN


JAH-Z4-ST-S16-CL.100Column Rebar Installation 8 01-Apr-24 13-Apr-24 Column Rebar Installation

JAH-Z4-ST-S16-CL.105Column Formwork Installation 7 14-Apr-24 21-Apr-24 Column Formwork Installation

JAH-Z4-ST-S16-CL.110 Column Concrete Casting 1 22-Apr-24 22-Apr-24 Column Concrete Casting

JAH-Z4-ST-S16-CL.115 Form Work Removal and Curing 7 23-Apr-24 30-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 37 21-Mar-24 06-May-24 06-May-24, TUNNEL WALLS


JAH-Z4-ST-S16-TW.100Tunnel Walls Rebar Installation 8 21-Mar-24 30-Mar-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S16-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 21-Mar-24 30-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S16-TW.105Tunnel Formwork Installation 7 31-Mar-24 07-Apr-24 Tunnel Formwork Installation

JAH-Z4-ST-S16-TW.110Tunnel Walls Concrete Casting 1 08-Apr-24 08-Apr-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S16-TW.112Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z4-ST-S16-TW.120Tunnel Walls Formwork Removel 2 21-Apr-24 22-Apr-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S16-TW.125Tunnel Wall Waterproofing 12 23-Apr-24 06-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 01-May-24 04-Jun-24 04-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S16-MS.090Middle Slab Scaffold and Formwork Installation 5 01-May-24 06-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S16-MS.100Middle Slab Rebar Installation 8 07-May-24 15-May-24 Middle Slab Rebar Installation

JAH-Z4-ST-S16-MS.105Middle Slab Vertical Formwork Installation 7 16-May-24 23-May-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S16-MS.110Middle Slab Concrete Casting 1 25-May-24 25-May-24 Middle Slab Concrete Casting

JAH-Z4-ST-S16-MS.115Curing work 7 26-May-24 02-Jun-24 Curing work

JAH-Z4-ST-S16-MS.120Middle Slab Formwork Removel 2 03-Jun-24 04-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 05-Jun-24 08-Jul-24 08-Jul-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S16-UCW100
Utility Culvert Walls Rebar Installation 8 05-Jun-24 13-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S16-UCW105
Utility Culvert Walls Formwork Installation 7 19-Jun-24 26-Jun-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S16-UCW110
Utility Culvert Walls Concrete Casting 1 27-Jun-24 27-Jun-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S16-UCW112
Curing work 7 29-Jun-24 06-Jul-24 Curing work

JAH-Z4-ST-S16-UCW115
Utility Culvert Walls Walls Formwork Removel 2 07-Jul-24 08-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 09-Jul-24 20-Aug-24 20-Aug-24, TOP SLAB


JAH-Z4-ST-S16-TS.090 Top Slab Formwork Installation 7 09-Jul-24 16-Jul-24 Top Slab Formwork Installation

JAH-Z4-ST-S16-TS.100 Top Slab Rebar Installation 8 17-Jul-24 25-Jul-24 Top Slab Rebar Installation

JAH-Z4-ST-S16-TS.110 Top Slab Concrete Casting 1 27-Jul-24 27-Jul-24 Top Slab Concrete Casting

JAH-Z4-ST-S16-TS.112 Curing work 7 28-Jul-24 04-Aug-24 Curing work

JAH-Z4-ST-S16-TS.115 Top Slab Formwork Removel 2 05-Aug-24 06-Aug-24 Top Slab Formwork Removel

JAH-Z4-ST-S16-TS.120 Waterproofing for Top Slab 12 07-Aug-24 20-Aug-24 Waterproofing for Top Slab

MASS CONCRETE WORK 63 21-Aug-24 03-Nov-24 03-Nov-24, MASS CONCRETE WORK


JAH-Z4-ST-S16-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 21-Aug-24 28-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S16-MC.105Plain Concrete Casting 1 29-Aug-24 29-Aug-24 Plain Concrete Casting

JAH-Z4-ST-S16-MC.110Mass Concrete Casting for Base Slab Top Layer 1 31-Aug-24 31-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S16-MC.112Curing work 7 01-Sep-24 08-Sep-24 Curing work

JAH-Z4-ST-S16-MC.115Concrete Protective coating 8 26-Oct-24 03-Nov-24 Concrete Protective coating

STA. 1+593.979 ~ 1+613.979 212 02-Mar-24 12-Nov-24 12-Nov-24, STA. 1+593.979 ~ 1+613.979
BASE SLAB 36 02-Mar-24 15-Apr-24 15-Apr-24, BASE SLAB

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
329 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S17-BS.100Lean Concrete for Base Slab 1 02-Mar-24 02-Mar-24 Lean Concrete for Base Slab

JAH-Z4-ST-S17-BS.105Waterproofing for Lean Concrete 1 03-Mar-24 03-Mar-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S17-BS.110 Base Slab Rebar Installation 8 04-Mar-24 12-Mar-24 Base Slab Rebar Installation

JAH-Z4-ST-S17-BS.115 Base Slab Formwork Installation 7 13-Mar-24 20-Mar-24 Base Slab Formwork Installation

JAH-Z4-ST-S17-BS.120Base Slab Concrete Casting 1 21-Mar-24 21-Mar-24 Base Slab Concrete Casting

JAH-Z4-ST-S17-BS.122Curing work 7 23-Mar-24 30-Mar-24 Curing work

JAH-Z4-ST-S17-BS.125Base Slab Formwork Removel 2 31-Mar-24 01-Apr-24 Base Slab Formwork Removel

JAH-Z4-ST-S17-BS.130Plain concrete on Base slab 2 02-Apr-24 03-Apr-24 Plain concrete on Base slab

JAH-Z4-ST-S17-BS.135Curing work 7 04-Apr-24 15-Apr-24 Curing work

COLUMN 23 16-Apr-24 12-May-24 12-May-24, COLUMN


JAH-Z4-ST-S17-CL.100Column Rebar Installation 8 16-Apr-24 24-Apr-24 Column Rebar Installation

JAH-Z4-ST-S17-CL.105Column Formwork Installation 7 25-Apr-24 02-May-24 Column Formwork Installation

JAH-Z4-ST-S17-CL.110 Column Concrete Casting 1 04-May-24 04-May-24 Column Concrete Casting

JAH-Z4-ST-S17-CL.115 Form Work Removal and Curing 7 05-May-24 12-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 02-Apr-24 18-May-24 18-May-24, TUNNEL WALLS


JAH-Z4-ST-S17-TW.100Tunnel Walls Rebar Installation 8 02-Apr-24 14-Apr-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S17-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 02-Apr-24 14-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S17-TW.105Tunnel Formwork Installation 7 15-Apr-24 22-Apr-24 Tunnel Formwork Installation

JAH-Z4-ST-S17-TW.110Tunnel Walls Concrete Casting 1 23-Apr-24 23-Apr-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S17-TW.112Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z4-ST-S17-TW.120Tunnel Walls Formwork Removel 2 02-May-24 04-May-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S17-TW.125Tunnel Wall Waterproofing 12 05-May-24 18-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 13-May-24 20-Jun-24 20-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S17-MS.090Middle Slab Scaffold and Formwork Installation 5 13-May-24 18-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S17-MS.100Middle Slab Rebar Installation 8 19-May-24 27-May-24 Middle Slab Rebar Installation

JAH-Z4-ST-S17-MS.105Middle Slab Vertical Formwork Installation 7 28-May-24 04-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S17-MS.110Middle Slab Concrete Casting 1 05-Jun-24 05-Jun-24 Middle Slab Concrete Casting

JAH-Z4-ST-S17-MS.115Curing work 7 06-Jun-24 13-Jun-24 Curing work

JAH-Z4-ST-S17-MS.120Middle Slab Formwork Removel 2 19-Jun-24 20-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 22-Jun-24 20-Jul-24 20-Jul-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S17-UCW100
Utility Culvert Walls Rebar Installation 8 22-Jun-24 30-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S17-UCW105
Utility Culvert Walls Formwork Installation 7 01-Jul-24 08-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S17-UCW110
Utility Culvert Walls Concrete Casting 1 09-Jul-24 09-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S17-UCW112
Curing work 7 10-Jul-24 17-Jul-24 Curing work

JAH-Z4-ST-S17-UCW115
Utility Culvert Walls Walls Formwork Removel 2 18-Jul-24 20-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 21-Jul-24 01-Sep-24 01-Sep-24, TOP SLAB


JAH-Z4-ST-S17-TS.090 Top Slab Formwork Installation 7 21-Jul-24 28-Jul-24 Top Slab Formwork Installation

JAH-Z4-ST-S17-TS.100 Top Slab Rebar Installation 8 29-Jul-24 06-Aug-24 Top Slab Rebar Installation

JAH-Z4-ST-S17-TS.110 Top Slab Concrete Casting 1 07-Aug-24 07-Aug-24 Top Slab Concrete Casting

JAH-Z4-ST-S17-TS.112 Curing work 7 08-Aug-24 15-Aug-24 Curing work

JAH-Z4-ST-S17-TS.115 Top Slab Formwork Removel 2 17-Aug-24 18-Aug-24 Top Slab Formwork Removel

JAH-Z4-ST-S17-TS.120 Waterproofing for Top Slab 12 19-Aug-24 01-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 61 02-Sep-24 12-Nov-24 12-Nov-24, MASS CONCRETE WORK


JAH-Z4-ST-S17-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 02-Sep-24 09-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S17-MC.105Plain Concrete Casting 1 10-Sep-24 10-Sep-24 Plain Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
330 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S17-MC.110Mass Concrete Casting for Base Slab Top Layer 1 11-Sep-24 11-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S17-MC.112Curing work 7 12-Sep-24 19-Sep-24 Curing work

JAH-Z4-ST-S17-MC.115Concrete Protective coating 8 04-Nov-24 12-Nov-24 Concrete Protective coating

STA. 1+613.979 ~ 1+633.979 210 13-Mar-24 21-Nov-24 21-Nov-24, STA. 1+613.979 ~ 1+633.979
BASE SLAB 36 13-Mar-24 27-Apr-24 27-Apr-24, BASE SLAB
JAH-Z4-ST-S18-BS.100Lean Concrete for Base Slab 1 13-Mar-24 13-Mar-24 Lean Concrete for Base Slab

JAH-Z4-ST-S18-BS.105Waterproofing for Lean Concrete 1 14-Mar-24 14-Mar-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S18-BS.110 Base Slab Rebar Installation 8 16-Mar-24 24-Mar-24 Base Slab Rebar Installation

JAH-Z4-ST-S18-BS.115 Base Slab Formwork Installation 7 25-Mar-24 01-Apr-24 Base Slab Formwork Installation

JAH-Z4-ST-S18-BS.120Base Slab Concrete Casting 1 02-Apr-24 02-Apr-24 Base Slab Concrete Casting

JAH-Z4-ST-S18-BS.122Curing work 7 03-Apr-24 14-Apr-24 Curing work

JAH-Z4-ST-S18-BS.125Base Slab Formwork Removel 2 15-Apr-24 16-Apr-24 Base Slab Formwork Removel

JAH-Z4-ST-S18-BS.130Plain concrete on Base slab 2 17-Apr-24 18-Apr-24 Plain concrete on Base slab

JAH-Z4-ST-S18-BS.135Curing work 7 20-Apr-24 27-Apr-24 Curing work

COLUMN 23 17-Apr-24 13-May-24 13-May-24, COLUMN


JAH-Z4-ST-S18-CL.100Column Rebar Installation 8 17-Apr-24 25-Apr-24 Column Rebar Installation

JAH-Z4-ST-S18-CL.105Column Formwork Installation 7 27-Apr-24 04-May-24 Column Formwork Installation

JAH-Z4-ST-S18-CL.110 Column Concrete Casting 1 05-May-24 05-May-24 Column Concrete Casting

JAH-Z4-ST-S18-CL.115 Form Work Removal and Curing 7 06-May-24 13-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 17-Apr-24 29-May-24 29-May-24, TUNNEL WALLS


JAH-Z4-ST-S18-TW.100Tunnel Walls Rebar Installation 8 17-Apr-24 25-Apr-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S18-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 17-Apr-24 25-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S18-TW.105Tunnel Formwork Installation 7 27-Apr-24 04-May-24 Tunnel Formwork Installation

JAH-Z4-ST-S18-TW.110Tunnel Walls Concrete Casting 1 05-May-24 05-May-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S18-TW.112Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z4-ST-S18-TW.120Tunnel Walls Formwork Removel 2 14-May-24 15-May-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S18-TW.125Tunnel Wall Waterproofing 12 16-May-24 29-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 16-May-24 24-Jun-24 24-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S18-MS.090Middle Slab Scaffold and Formwork Installation 5 16-May-24 21-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S18-MS.100Middle Slab Rebar Installation 8 22-May-24 30-May-24 Middle Slab Rebar Installation

JAH-Z4-ST-S18-MS.105Middle Slab Vertical Formwork Installation 7 01-Jun-24 08-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S18-MS.110Middle Slab Concrete Casting 1 09-Jun-24 09-Jun-24 Middle Slab Concrete Casting

JAH-Z4-ST-S18-MS.112Curing work 7 10-Jun-24 22-Jun-24 Curing work

JAH-Z4-ST-S18-MS.120Middle Slab Formwork Removel 2 23-Jun-24 24-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 25-Jun-24 23-Jul-24 23-Jul-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S18-UCW100
Utility Culvert Walls Rebar Installation 8 25-Jun-24 03-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S18-UCW105
Utility Culvert Walls Formwork Installation 7 04-Jul-24 11-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S18-UCW110
Utility Culvert Walls Concrete Casting 1 13-Jul-24 13-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S18-UCW112
Curing work 7 14-Jul-24 21-Jul-24 Curing work

JAH-Z4-ST-S18-UCW115
Utility Culvert Walls Walls Formwork Removel 2 22-Jul-24 23-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 24-Jul-24 04-Sep-24 04-Sep-24, TOP SLAB


JAH-Z4-ST-S18-TS.090 Top Slab Formwork Installation 7 24-Jul-24 31-Jul-24 Top Slab Formwork Installation

JAH-Z4-ST-S18-TS.100 Top Slab Rebar Installation 8 01-Aug-24 10-Aug-24 Top Slab Rebar Installation

JAH-Z4-ST-S18-TS.110 Top Slab Concrete Casting 1 11-Aug-24 11-Aug-24 Top Slab Concrete Casting

JAH-Z4-ST-S18-TS.112 Curing work 7 12-Aug-24 19-Aug-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
331 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S18-TS.115 Top Slab Formwork Removel 2 20-Aug-24 21-Aug-24 Top Slab Formwork Removel

JAH-Z4-ST-S18-TS.120 Waterproofing for Top Slab 12 22-Aug-24 04-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 66 05-Sep-24 21-Nov-24 21-Nov-24, MASS CONCRETE WORK


JAH-Z4-ST-S18-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 05-Sep-24 12-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S18-MC.105Plain Concrete Casting 1 14-Sep-24 14-Sep-24 Plain Concrete Casting

JAH-Z4-ST-S18-MC.110Mass Concrete Casting for Base Slab Top Layer 1 15-Sep-24 15-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S18-MC.112Curing work 7 16-Sep-24 24-Sep-24 Curing work

JAH-Z4-ST-S18-MC.115Concrete Protective coating 8 13-Nov-24 21-Nov-24 Concrete Protective coating

STA. 1+633.979 ~ 1+653.979 216 25-Mar-24 10-Dec-24 10-Dec-24, STA. 1+633.979 ~ 1+653.979
BASE SLAB 36 25-Mar-24 08-May-24 08-May-24, BASE SLAB
JAH-Z4-ST-S19-BS.100Lean Concrete for Base Slab 1 25-Mar-24 25-Mar-24 Lean Concrete for Base Slab

JAH-Z4-ST-S19-BS.105Waterproofing for Lean Concrete 1 26-Mar-24 26-Mar-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S19-BS.110 Base Slab Rebar Installation 8 27-Mar-24 04-Apr-24 Base Slab Rebar Installation

JAH-Z4-ST-S19-BS.115 Base Slab Formwork Installation 7 06-Apr-24 16-Apr-24 Base Slab Formwork Installation

JAH-Z4-ST-S19-BS.120Base Slab Concrete Casting 1 17-Apr-24 17-Apr-24 Base Slab Concrete Casting

JAH-Z4-ST-S19-BS.122Curing work 7 18-Apr-24 25-Apr-24 Curing work

JAH-Z4-ST-S19-BS.125Base Slab Formwork Removel 2 27-Apr-24 28-Apr-24 Base Slab Formwork Removel

JAH-Z4-ST-S19-BS.130Plain concrete on Base slab 2 29-Apr-24 30-Apr-24 Plain concrete on Base slab

JAH-Z4-ST-S19-BS.135Curing work 7 01-May-24 08-May-24 Curing work

COLUMN 23 29-Apr-24 25-May-24 25-May-24, COLUMN


JAH-Z4-ST-S19-CL.100Column Rebar Installation 8 29-Apr-24 07-May-24 Column Rebar Installation

JAH-Z4-ST-S19-CL.105Column Formwork Installation 7 08-May-24 15-May-24 Column Formwork Installation

JAH-Z4-ST-S19-CL.110 Column Concrete Casting 1 16-May-24 16-May-24 Column Concrete Casting

JAH-Z4-ST-S19-CL.115 Form Work Removal and Curing 7 18-May-24 25-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 29-Apr-24 10-Jun-24 10-Jun-24, TUNNEL WALLS


JAH-Z4-ST-S19-TW.100Tunnel Walls Rebar Installation 8 29-Apr-24 07-May-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S19-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 29-Apr-24 07-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S19-TW.105Tunnel Formwork Installation 7 08-May-24 15-May-24 Tunnel Formwork Installation

JAH-Z4-ST-S19-TW.110Tunnel Walls Concrete Casting 1 16-May-24 16-May-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S19-TW.112Curing work 7 18-May-24 25-May-24 Curing work

JAH-Z4-ST-S19-TW.120Tunnel Walls Formwork Removel 2 26-May-24 27-May-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S19-TW.125Tunnel Wall Waterproofing 12 28-May-24 10-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 28-May-24 06-Jul-24 06-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S19-MS.090Middle Slab Scaffold and Formwork Installation 5 28-May-24 02-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S19-MS.100Middle Slab Rebar Installation 8 03-Jun-24 11-Jun-24 Middle Slab Rebar Installation

JAH-Z4-ST-S19-MS.105Middle Slab Vertical Formwork Installation 7 12-Jun-24 24-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S19-MS.110Middle Slab Concrete Casting 1 25-Jun-24 25-Jun-24 Middle Slab Concrete Casting

JAH-Z4-ST-S19-MS.115Curing work 7 26-Jun-24 03-Jul-24 Curing work

JAH-Z4-ST-S19-MS.120Middle Slab Formwork Removel 2 04-Jul-24 06-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 07-Jul-24 04-Aug-24 04-Aug-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S19-UCW100
Utility Culvert Walls Rebar Installation 8 07-Jul-24 15-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S19-UCW105
Utility Culvert Walls Formwork Installation 7 16-Jul-24 23-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S19-UCW110
Utility Culvert Walls Concrete Casting 1 24-Jul-24 24-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S19-UCW112
Curing work 7 25-Jul-24 01-Aug-24 Curing work

JAH-Z4-ST-S19-UCW115
Utility Culvert Walls Walls Formwork Removel 2 03-Aug-24 04-Aug-24 Utility Culvert Walls Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
332 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 37 05-Aug-24 16-Sep-24 16-Sep-24, TOP SLAB
JAH-Z4-ST-S19-TS.090 Top Slab Formwork Installation 7 05-Aug-24 12-Aug-24 Top Slab Formwork Installation

JAH-Z4-ST-S19-TS.100 Top Slab Rebar Installation 8 13-Aug-24 21-Aug-24 Top Slab Rebar Installation

JAH-Z4-ST-S19-TS.110 Top Slab Concrete Casting 1 22-Aug-24 22-Aug-24 Top Slab Concrete Casting

JAH-Z4-ST-S19-TS.112 Curing work 7 24-Aug-24 31-Aug-24 Curing work

JAH-Z4-ST-S19-TS.115 Top Slab Formwork Removel 2 01-Sep-24 02-Sep-24 Top Slab Formwork Removel

JAH-Z4-ST-S19-TS.120 Waterproofing for Top Slab 12 03-Sep-24 16-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 72 17-Sep-24 10-Dec-24 10-Dec-24, MASS CONCRETE WORK


JAH-Z4-ST-S19-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 17-Sep-24 25-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S19-MC.105Plain Concrete Casting 1 26-Sep-24 26-Sep-24 Plain Concrete Casting

JAH-Z4-ST-S19-MC.110Mass Concrete Casting for Base Slab Top Layer 1 23-Nov-24 23-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S19-MC.112Curing work 7 24-Nov-24 01-Dec-24 Curing work

JAH-Z4-ST-S19-MC.115Concrete Protective coating 8 02-Dec-24 10-Dec-24 Concrete Protective coating

STA. 1+653.979 ~ 1+673.979 221 06-Apr-24 28-Dec-24 28-Dec-24, STA. 1+653.979 ~ 1+673.979
BASE SLAB 39 06-Apr-24 23-May-24 23-May-24, BASE SLAB
JAH-Z4-ST-S20-BS.100Lean Concrete for Base Slab 1 06-Apr-24 06-Apr-24 Lean Concrete for Base Slab

JAH-Z4-ST-S20-BS.105Waterproofing for Lean Concrete 1 07-Apr-24 07-Apr-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S20-BS.110 Base Slab Rebar Installation 8 08-Apr-24 20-Apr-24 Base Slab Rebar Installation

JAH-Z4-ST-S20-BS.115 Base Slab Formwork Installation 7 21-Apr-24 28-Apr-24 Base Slab Formwork Installation

JAH-Z4-ST-S20-BS.120Base Slab Concrete Casting 1 29-Apr-24 29-Apr-24 Base Slab Concrete Casting

JAH-Z4-ST-S20-BS.122Curing work 7 30-Apr-24 07-May-24 Curing work

JAH-Z4-ST-S20-BS.125Base Slab Formwork Removel 2 08-May-24 09-May-24 Base Slab Formwork Removel

JAH-Z4-ST-S20-BS.130Plain concrete on Base slab 2 14-May-24 15-May-24 Plain concrete on Base slab

JAH-Z4-ST-S20-BS.135Curing work 7 16-May-24 23-May-24 Curing work

COLUMN 23 11-May-24 05-Jun-24 05-Jun-24, COLUMN


JAH-Z4-ST-S20-CL.100Column Rebar Installation 8 11-May-24 19-May-24 Column Rebar Installation

JAH-Z4-ST-S20-CL.105Column Formwork Installation 7 20-May-24 27-May-24 Column Formwork Installation

JAH-Z4-ST-S20-CL.110 Column Concrete Casting 1 28-May-24 28-May-24 Column Concrete Casting

JAH-Z4-ST-S20-CL.115 Form Work Removal and Curing 7 29-May-24 05-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 11-May-24 26-Jun-24 26-Jun-24, TUNNEL WALLS


JAH-Z4-ST-S20-TW.100Tunnel Walls Rebar Installation 8 11-May-24 19-May-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S20-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-May-24 19-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S20-TW.105Tunnel Formwork Installation 7 20-May-24 27-May-24 Tunnel Formwork Installation

JAH-Z4-ST-S20-TW.110Tunnel Walls Concrete Casting 1 28-May-24 28-May-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S20-TW.112Curing work 7 29-May-24 05-Jun-24 Curing work

JAH-Z4-ST-S20-TW.120Tunnel Walls Formwork Removel 2 06-Jun-24 08-Jun-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S20-TW.125Tunnel Wall Waterproofing 12 09-Jun-24 26-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 09-Jun-24 17-Jul-24 17-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S20-MS.090Middle Slab Scaffold and Formwork Installation 5 09-Jun-24 13-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S20-MS.100Middle Slab Rebar Installation 8 19-Jun-24 27-Jun-24 Middle Slab Rebar Installation

JAH-Z4-ST-S20-MS.105Middle Slab Vertical Formwork Installation 7 29-Jun-24 06-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S20-MS.110Middle Slab Concrete Casting 1 07-Jul-24 07-Jul-24 Middle Slab Concrete Casting

JAH-Z4-ST-S20-MS.115Curing work 7 08-Jul-24 15-Jul-24 Curing work

JAH-Z4-ST-S20-MS.120Middle Slab Formwork Removel 2 16-Jul-24 17-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 18-Jul-24 15-Aug-24 15-Aug-24, UTILITY CULVERT WALLS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
333 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S20-UCW100
Utility Culvert Walls Rebar Installation 8 18-Jul-24 27-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S20-UCW105
Utility Culvert Walls Formwork Installation 7 28-Jul-24 04-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S20-UCW110
Utility Culvert Walls Concrete Casting 1 05-Aug-24 05-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S20-UCW112
Curing work 7 06-Aug-24 13-Aug-24 Curing work

JAH-Z4-ST-S20-UCW115
Utility Culvert Walls Walls Formwork Removel 2 14-Aug-24 15-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 17-Aug-24 29-Sep-24 29-Sep-24, TOP SLAB


JAH-Z4-ST-S20-TS.090 Top Slab Formwork Installation 7 17-Aug-24 24-Aug-24 Top Slab Formwork Installation

JAH-Z4-ST-S20-TS.100 Top Slab Rebar Installation 8 25-Aug-24 02-Sep-24 Top Slab Rebar Installation

JAH-Z4-ST-S20-TS.110 Top Slab Concrete Casting 1 03-Sep-24 03-Sep-24 Top Slab Concrete Casting

JAH-Z4-ST-S20-TS.112 Curing work 7 04-Sep-24 11-Sep-24 Curing work

JAH-Z4-ST-S20-TS.115 Top Slab Formwork Removel 2 12-Sep-24 14-Sep-24 Top Slab Formwork Removel

JAH-Z4-ST-S20-TS.120 Waterproofing for Top Slab 12 15-Sep-24 29-Sep-24 Waterproofing for Top Slab

MASS CONCRETE WORK 77 30-Sep-24 28-Dec-24 28-Dec-24, MASS CONCRETE WORK


JAH-Z4-ST-S20-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 30-Sep-24 07-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S20-MC.105Plain Concrete Casting 1 08-Oct-24 08-Oct-24 Plain Concrete Casting

JAH-Z4-ST-S20-MC.110Mass Concrete Casting for Base Slab Top Layer 1 09-Oct-24 09-Oct-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S20-MC.112Curing work 7 11-Dec-24 18-Dec-24 Curing work

JAH-Z4-ST-S20-MC.115Concrete Protective coating 8 19-Dec-24 28-Dec-24 Concrete Protective coating

STA. 1+673.979~ 1+693.979 227 21-Apr-24 15-Jan-25 15-Jan-25, STA. 1+673.979~ 1+693.979
BASE SLAB 36 21-Apr-24 01-Jun-24 01-Jun-24, BASE SLAB
JAH-Z4-ST-S21-BS.100Lean Concrete for Base Slab 1 21-Apr-24 21-Apr-24 Lean Concrete for Base Slab

JAH-Z4-ST-S21-BS.105Waterproofing for Lean Concrete 1 22-Apr-24 22-Apr-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S21-BS.110 Base Slab Rebar Installation 8 23-Apr-24 01-May-24 Base Slab Rebar Installation

JAH-Z4-ST-S21-BS.115 Base Slab Formwork Installation 7 02-May-24 09-May-24 Base Slab Formwork Installation

JAH-Z4-ST-S21-BS.120Base Slab Concrete Casting 1 11-May-24 11-May-24 Base Slab Concrete Casting

JAH-Z4-ST-S21-BS.122Curing work 7 12-May-24 19-May-24 Curing work

JAH-Z4-ST-S21-BS.125Base Slab Formwork Removel 2 20-May-24 21-May-24 Base Slab Formwork Removel

JAH-Z4-ST-S21-BS.130Plain concrete on Base slab 2 22-May-24 23-May-24 Plain concrete on Base slab

JAH-Z4-ST-S21-BS.135Curing work 7 25-May-24 01-Jun-24 Curing work

COLUMN 23 22-May-24 22-Jun-24 22-Jun-24, COLUMN


JAH-Z4-ST-S21-CL.100Column Rebar Installation 8 22-May-24 30-May-24 Column Rebar Installation

JAH-Z4-ST-S21-CL.105Column Formwork Installation 7 01-Jun-24 08-Jun-24 Column Formwork Installation

JAH-Z4-ST-S21-CL.110 Column Concrete Casting 1 09-Jun-24 09-Jun-24 Column Concrete Casting

JAH-Z4-ST-S21-CL.115 Form Work Removal and Curing 7 10-Jun-24 22-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 22-May-24 08-Jul-24 08-Jul-24, TUNNEL WALLS


JAH-Z4-ST-S21-TW.100Tunnel Walls Rebar Installation 8 22-May-24 30-May-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S21-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-May-24 30-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S21-TW.105Tunnel Formwork Installation 7 01-Jun-24 08-Jun-24 Tunnel Formwork Installation

JAH-Z4-ST-S21-TW.110Tunnel Walls Concrete Casting 1 09-Jun-24 09-Jun-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S21-TW.112Curing work 7 10-Jun-24 22-Jun-24 Curing work

JAH-Z4-ST-S21-TW.120Tunnel Walls Formwork Removel 2 23-Jun-24 24-Jun-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S21-TW.125Tunnel Wall Waterproofing 12 25-Jun-24 08-Jul-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 25-Jun-24 29-Jul-24 29-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S21-MS.090Middle Slab Scaffold and Formwork Installation 5 25-Jun-24 30-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S21-MS.100Middle Slab Rebar Installation 8 01-Jul-24 09-Jul-24 Middle Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
334 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S21-MS.105Middle Slab Vertical Formwork Installation 7 10-Jul-24 17-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S21-MS.110Middle Slab Concrete Casting 1 18-Jul-24 18-Jul-24 Middle Slab Concrete Casting

JAH-Z4-ST-S21-MS.115Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z4-ST-S21-MS.120Middle Slab Formwork Removel 2 28-Jul-24 29-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 30-Jul-24 27-Aug-24 27-Aug-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S21-UCW100
Utility Culvert Walls Rebar Installation 8 30-Jul-24 07-Aug-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S21-UCW105
Utility Culvert Walls Formwork Installation 7 08-Aug-24 15-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S21-UCW110
Utility Culvert Walls Concrete Casting 1 17-Aug-24 17-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S21-UCW112
Curing work 7 18-Aug-24 25-Aug-24 Curing work

JAH-Z4-ST-S21-UCW115
Utility Culvert Walls Walls Formwork Removel 2 26-Aug-24 27-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 28-Aug-24 10-Oct-24 10-Oct-24, TOP SLAB


JAH-Z4-ST-S21-TS.090 Top Slab Formwork Installation 7 28-Aug-24 04-Sep-24 Top Slab Formwork Installation

JAH-Z4-ST-S21-TS.100 Top Slab Rebar Installation 8 05-Sep-24 14-Sep-24 Top Slab Rebar Installation

JAH-Z4-ST-S21-TS.110 Top Slab Concrete Casting 1 15-Sep-24 15-Sep-24 Top Slab Concrete Casting

JAH-Z4-ST-S21-TS.112 Curing work 7 16-Sep-24 24-Sep-24 Curing work

JAH-Z4-ST-S21-TS.115 Top Slab Formwork Removel 2 25-Sep-24 26-Sep-24 Top Slab Formwork Removel

JAH-Z4-ST-S21-TS.120 Waterproofing for Top Slab 12 28-Sep-24 10-Oct-24 Waterproofing for Top Slab

MASS CONCRETE WORK 83 12-Oct-24 15-Jan-25 15-Jan-25, MASS CONCRETE WORK


JAH-Z4-ST-S21-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 12-Oct-24 19-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S21-MC.105Plain Concrete Casting 1 20-Oct-24 20-Oct-24 Plain Concrete Casting

JAH-Z4-ST-S21-MC.110Mass Concrete Casting for Base Slab Top Layer 1 29-Dec-24 29-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S21-MC.112Curing work 7 30-Dec-24 06-Jan-25 Curing work

JAH-Z4-ST-S21-MC.115Concrete Protective coating 8 07-Jan-25 15-Jan-25 Concrete Protective coating

STA. 1+693.979 ~ 1+713.979 168 02-May-24 19-Nov-24 19-Nov-24, STA. 1+693.979 ~ 1+713.979
BASE SLAB 36 02-May-24 12-Jun-24 12-Jun-24, BASE SLAB
JAH-Z4-ST-S22-BS.100Lean Concrete for Base Slab 1 02-May-24 02-May-24 Lean Concrete for Base Slab

JAH-Z4-ST-S22-BS.105Waterproofing for Lean Concrete 1 04-May-24 04-May-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S22-BS.110 Base Slab Rebar Installation 8 05-May-24 13-May-24 Base Slab Rebar Installation

JAH-Z4-ST-S22-BS.115 Base Slab Formwork Installation 7 14-May-24 21-May-24 Base Slab Formwork Installation

JAH-Z4-ST-S22-BS.120Base Slab Concrete Casting 1 22-May-24 22-May-24 Base Slab Concrete Casting

JAH-Z4-ST-S22-BS.122Curing work 7 23-May-24 30-May-24 Curing work

JAH-Z4-ST-S22-BS.125Base Slab Formwork Removel 2 01-Jun-24 02-Jun-24 Base Slab Formwork Removel

JAH-Z4-ST-S22-BS.130Plain concrete on Base slab 2 03-Jun-24 04-Jun-24 Plain concrete on Base slab

JAH-Z4-ST-S22-BS.135Curing work 7 05-Jun-24 12-Jun-24 Curing work

COLUMN 23 03-Jun-24 03-Jul-24 03-Jul-24, COLUMN


JAH-Z4-ST-S22-CL.100Column Rebar Installation 8 03-Jun-24 11-Jun-24 Column Rebar Installation

JAH-Z4-ST-S22-CL.105Column Formwork Installation 7 12-Jun-24 24-Jun-24 Column Formwork Installation

JAH-Z4-ST-S22-CL.110 Column Concrete Casting 1 25-Jun-24 25-Jun-24 Column Concrete Casting

JAH-Z4-ST-S22-CL.115 Form Work Removal and Curing 7 26-Jun-24 03-Jul-24 Form Work Removal and Curing

TUNNEL WALLS 37 03-Jun-24 20-Jul-24 20-Jul-24, TUNNEL WALLS


JAH-Z4-ST-S22-TW.100Tunnel Walls Rebar Installation 8 03-Jun-24 11-Jun-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S22-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 03-Jun-24 11-Jun-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S22-TW.105Tunnel Formwork Installation 7 12-Jun-24 24-Jun-24 Tunnel Formwork Installation

JAH-Z4-ST-S22-TW.110Tunnel Walls Concrete Casting 1 25-Jun-24 25-Jun-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S22-TW.112Curing work 7 26-Jun-24 03-Jul-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
335 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S22-TW.120Tunnel Walls Formwork Removel 2 04-Jul-24 06-Jul-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S22-TW.125Tunnel Wall Waterproofing 12 07-Jul-24 20-Jul-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 07-Jul-24 10-Aug-24 10-Aug-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S22-MS.090Middle Slab Scaffold and Formwork Installation 5 07-Jul-24 11-Jul-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S22-MS.100Middle Slab Rebar Installation 8 13-Jul-24 21-Jul-24 Middle Slab Rebar Installation

JAH-Z4-ST-S22-MS.105Middle Slab Vertical Formwork Installation 7 22-Jul-24 29-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S22-MS.110Middle Slab Concrete Casting 1 30-Jul-24 30-Jul-24 Middle Slab Concrete Casting

JAH-Z4-ST-S22-MS.115Curing work 7 31-Jul-24 07-Aug-24 Curing work

JAH-Z4-ST-S22-MS.120Middle Slab Formwork Removel 2 08-Aug-24 10-Aug-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 11-Aug-24 08-Sep-24 08-Sep-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S22-UCW100
Utility Culvert Walls Rebar Installation 8 11-Aug-24 19-Aug-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S22-UCW105
Utility Culvert Walls Formwork Installation 7 20-Aug-24 27-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S22-UCW110
Utility Culvert Walls Concrete Casting 1 28-Aug-24 28-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S22-UCW112
Curing work 7 29-Aug-24 05-Sep-24 Curing work

JAH-Z4-ST-S22-UCW115
Utility Culvert Walls Walls Formwork Removel 2 07-Sep-24 08-Sep-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 09-Sep-24 22-Oct-24 22-Oct-24, TOP SLAB


JAH-Z4-ST-S22-TS.090 Top Slab Formwork Installation 7 09-Sep-24 16-Sep-24 Top Slab Formwork Installation

JAH-Z4-ST-S22-TS.100 Top Slab Rebar Installation 8 17-Sep-24 26-Sep-24 Top Slab Rebar Installation

JAH-Z4-ST-S22-TS.110 Top Slab Concrete Casting 1 28-Sep-24 28-Sep-24 Top Slab Concrete Casting

JAH-Z4-ST-S22-TS.112 Curing work 7 29-Sep-24 06-Oct-24 Curing work

JAH-Z4-ST-S22-TS.115 Top Slab Formwork Removel 2 07-Oct-24 08-Oct-24 Top Slab Formwork Removel

JAH-Z4-ST-S22-TS.120 Waterproofing for Top Slab 12 09-Oct-24 22-Oct-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 23-Oct-24 19-Nov-24 19-Nov-24, MASS CONCRETE WORK


JAH-Z4-ST-S22-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 23-Oct-24 30-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S22-MC.105Plain Concrete Casting 1 31-Oct-24 31-Oct-24 Plain Concrete Casting

JAH-Z4-ST-S22-MC.110Mass Concrete Casting for Base Slab Top Layer 1 02-Nov-24 02-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S22-MC.112Curing work 7 03-Nov-24 10-Nov-24 Curing work

JAH-Z4-ST-S22-MC.115Concrete Protective coating 8 11-Nov-24 19-Nov-24 Concrete Protective coating

STA. 1+713.979 ~1+733.979 231 14-May-24 12-Feb-25 12-Feb-25, STA. 1+713.979 ~1+733.979
BASE SLAB 36 14-May-24 29-Jun-24 29-Jun-24, BASE SLAB
JAH-Z4-ST-S23-BS.100Lean Concrete for Base Slab 1 14-May-24 14-May-24 Lean Concrete for Base Slab

JAH-Z4-ST-S23-BS.105Waterproofing for Lean Concrete 1 15-May-24 15-May-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S23-BS.110 Base Slab Rebar Installation 8 16-May-24 25-May-24 Base Slab Rebar Installation

JAH-Z4-ST-S23-BS.115 Base Slab Formwork Installation 7 26-May-24 02-Jun-24 Base Slab Formwork Installation

JAH-Z4-ST-S23-BS.120Base Slab Concrete Casting 1 03-Jun-24 03-Jun-24 Base Slab Concrete Casting

JAH-Z4-ST-S23-BS.122Curing work 7 04-Jun-24 11-Jun-24 Curing work

JAH-Z4-ST-S23-BS.125Base Slab Formwork Removel 2 12-Jun-24 13-Jun-24 Base Slab Formwork Removel

JAH-Z4-ST-S23-BS.130Plain concrete on Base slab 2 19-Jun-24 20-Jun-24 Plain concrete on Base slab

JAH-Z4-ST-S23-BS.135Curing work 7 22-Jun-24 29-Jun-24 Curing work

COLUMN 23 19-Jun-24 15-Jul-24 15-Jul-24, COLUMN


JAH-Z4-ST-S23-CL.100Column Rebar Installation 8 19-Jun-24 27-Jun-24 Column Rebar Installation

JAH-Z4-ST-S23-CL.105Column Formwork Installation 7 29-Jun-24 06-Jul-24 Column Formwork Installation

JAH-Z4-ST-S23-CL.110 Column Concrete Casting 1 07-Jul-24 07-Jul-24 Column Concrete Casting

JAH-Z4-ST-S23-CL.115 Form Work Removal and Curing 7 08-Jul-24 15-Jul-24 Form Work Removal and Curing

TUNNEL WALLS 37 19-Jun-24 31-Jul-24 31-Jul-24, TUNNEL WALLS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
336 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S23-TW.100Tunnel Walls Rebar Installation 8 19-Jun-24 27-Jun-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S23-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 19-Jun-24 27-Jun-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S23-TW.105Tunnel Formwork Installation 7 29-Jun-24 06-Jul-24 Tunnel Formwork Installation

JAH-Z4-ST-S23-TW.110Tunnel Walls Concrete Casting 1 07-Jul-24 07-Jul-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S23-TW.112Curing work 7 08-Jul-24 15-Jul-24 Curing work

JAH-Z4-ST-S23-TW.120Tunnel Walls Formwork Removel 2 16-Jul-24 17-Jul-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S23-TW.125Tunnel Wall Waterproofing 12 18-Jul-24 31-Jul-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 18-Jul-24 21-Aug-24 21-Aug-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S23-MS.090Middle Slab Scaffold and Formwork Installation 5 18-Jul-24 23-Jul-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S23-MS.100Middle Slab Rebar Installation 8 24-Jul-24 01-Aug-24 Middle Slab Rebar Installation

JAH-Z4-ST-S23-MS.105Middle Slab Vertical Formwork Installation 7 03-Aug-24 10-Aug-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S23-MS.110Middle Slab Concrete Casting 1 11-Aug-24 11-Aug-24 Middle Slab Concrete Casting

JAH-Z4-ST-S23-MS.115Curing work 7 12-Aug-24 19-Aug-24 Curing work

JAH-Z4-ST-S23-MS.120Middle Slab Formwork Removel 2 20-Aug-24 21-Aug-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 22-Aug-24 19-Sep-24 19-Sep-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S23-UCW100
Utility Culvert Walls Rebar Installation 8 22-Aug-24 31-Aug-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S23-UCW105
Utility Culvert Walls Formwork Installation 7 01-Sep-24 08-Sep-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S23-UCW110
Utility Culvert Walls Concrete Casting 1 09-Sep-24 09-Sep-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S23-UCW112
Curing work 7 10-Sep-24 17-Sep-24 Curing work

JAH-Z4-ST-S23-UCW115
Utility Culvert Walls Walls Formwork Removel 2 18-Sep-24 19-Sep-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 21-Sep-24 03-Nov-24 03-Nov-24, TOP SLAB


JAH-Z4-ST-S23-TS.090 Top Slab Formwork Installation 7 21-Sep-24 29-Sep-24 Top Slab Formwork Installation

JAH-Z4-ST-S23-TS.100 Top Slab Rebar Installation 8 30-Sep-24 08-Oct-24 Top Slab Rebar Installation

JAH-Z4-ST-S23-TS.110 Top Slab Concrete Casting 1 09-Oct-24 09-Oct-24 Top Slab Concrete Casting

JAH-Z4-ST-S23-TS.112 Curing work 7 10-Oct-24 17-Oct-24 Curing work

JAH-Z4-ST-S23-TS.115 Top Slab Formwork Removel 2 19-Oct-24 20-Oct-24 Top Slab Formwork Removel

JAH-Z4-ST-S23-TS.120 Waterproofing for Top Slab 12 21-Oct-24 03-Nov-24 Waterproofing for Top Slab

MASS CONCRETE WORK 24 16-Jan-25 12-Feb-25 12-Feb-25, MASS CONCRETE WORK


JAH-Z4-ST-S23-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 16-Jan-25 23-Jan-25 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S23-MC.105Plain Concrete Casting 1 25-Jan-25 25-Jan-25 Plain Concrete Casting

JAH-Z4-ST-S23-MC.110Mass Concrete Casting for Base Slab Top Layer 1 26-Jan-25 26-Jan-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S23-MC.112Curing work 7 27-Jan-25 03-Feb-25 Curing work

JAH-Z4-ST-S23-MC.115Concrete Protective coating 8 04-Feb-25 12-Feb-25 Concrete Protective coating

STA. 1+733.979~ 1+753.979 229 26-May-24 22-Feb-25 22-Feb-25, STA. 1+733.979~ 1+753.979
BASE SLAB 36 26-May-24 10-Jul-24 10-Jul-24, BASE SLAB
JAH-Z4-ST-S24-BS.100Lean Concrete for Base Slab 1 26-May-24 26-May-24 Lean Concrete for Base Slab

JAH-Z4-ST-S24-BS.105Waterproofing for Lean Concrete 1 27-May-24 27-May-24 Waterproofing for Lean Concrete

JAH-Z4-ST-S24-BS.110 Base Slab Rebar Installation 8 28-May-24 05-Jun-24 Base Slab Rebar Installation

JAH-Z4-ST-S24-BS.115 Base Slab Formwork Installation 7 06-Jun-24 13-Jun-24 Base Slab Formwork Installation

JAH-Z4-ST-S24-BS.120Base Slab Concrete Casting 1 19-Jun-24 19-Jun-24 Base Slab Concrete Casting

JAH-Z4-ST-S24-BS.122Curing work 7 20-Jun-24 27-Jun-24 Curing work

JAH-Z4-ST-S24-BS.125Base Slab Formwork Removel 2 29-Jun-24 30-Jun-24 Base Slab Formwork Removel

JAH-Z4-ST-S24-BS.130Plain concrete on Base slab 2 01-Jul-24 02-Jul-24 Plain concrete on Base slab

JAH-Z4-ST-S24-BS.135Curing work 7 03-Jul-24 10-Jul-24 Curing work

COLUMN 24 01-Jul-24 28-Jul-24 28-Jul-24, COLUMN

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
337 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ST-S24-CL.100Column Rebar Installation 8 01-Jul-24 09-Jul-24 Column Rebar Installation

JAH-Z4-ST-S24-CL.105Column Formwork Installation 7 11-Jul-24 18-Jul-24 Column Formwork Installation

JAH-Z4-ST-S24-CL.110 Column Concrete Casting 1 20-Jul-24 20-Jul-24 Column Concrete Casting

JAH-Z4-ST-S24-CL.115 Form Work Removal and Curing 7 21-Jul-24 28-Jul-24 Form Work Removal and Curing

TUNNEL WALLS 37 01-Jul-24 12-Aug-24 12-Aug-24, TUNNEL WALLS


JAH-Z4-ST-S24-TW.100Tunnel Walls Rebar Installation 8 01-Jul-24 09-Jul-24 Tunnel Walls Rebar Installation

JAH-Z4-ST-S24-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 01-Jul-24 09-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z4-ST-S24-TW.105Tunnel Formwork Installation 7 10-Jul-24 17-Jul-24 Tunnel Formwork Installation

JAH-Z4-ST-S24-TW.110Tunnel Walls Concrete Casting 1 18-Jul-24 18-Jul-24 Tunnel Walls Concrete Casting

JAH-Z4-ST-S24-TW.112Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z4-ST-S24-TW.120Tunnel Walls Formwork Removel 2 28-Jul-24 29-Jul-24 Tunnel Walls Formwork Removel

JAH-Z4-ST-S24-TW.125Tunnel Wall Waterproofing 12 30-Jul-24 12-Aug-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 30-Jul-24 02-Sep-24 02-Sep-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z4-ST-S24-MS.090Middle Slab Scaffold and Formwork Installation 5 30-Jul-24 04-Aug-24 Middle Slab Scaffold and Formwork Installation

JAH-Z4-ST-S24-MS.100Middle Slab Rebar Installation 8 05-Aug-24 13-Aug-24 Middle Slab Rebar Installation

JAH-Z4-ST-S24-MS.105Middle Slab Vertical Formwork Installation 7 14-Aug-24 21-Aug-24 Middle Slab Vertical Formwork Installation

JAH-Z4-ST-S24-MS.110Middle Slab Concrete Casting 1 22-Aug-24 22-Aug-24 Middle Slab Concrete Casting

JAH-Z4-ST-S24-MS.115Curing work 7 24-Aug-24 31-Aug-24 Curing work

JAH-Z4-ST-S24-MS.120Middle Slab Formwork Removel 2 01-Sep-24 02-Sep-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 03-Sep-24 02-Oct-24 02-Oct-24, UTILITY CULVERT WALLS


JAH-Z4-ST-S24-UCW100
Utility Culvert Walls Rebar Installation 8 03-Sep-24 11-Sep-24 Utility Culvert Walls Rebar Installation

JAH-Z4-ST-S24-UCW105
Utility Culvert Walls Formwork Installation 7 12-Sep-24 19-Sep-24 Utility Culvert Walls Formwork Installation

JAH-Z4-ST-S24-UCW110
Utility Culvert Walls Concrete Casting 1 21-Sep-24 21-Sep-24 Utility Culvert Walls Concrete Casting

JAH-Z4-ST-S24-UCW112
Curing work 7 22-Sep-24 30-Sep-24 Curing work

JAH-Z4-ST-S24-UCW115
Utility Culvert Walls Walls Formwork Removel 2 01-Oct-24 02-Oct-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 03-Oct-24 14-Nov-24 14-Nov-24, TOP SLAB


JAH-Z4-ST-S24-TS.090 Top Slab Formwork Installation 7 03-Oct-24 10-Oct-24 Top Slab Formwork Installation

JAH-Z4-ST-S24-TS.100 Top Slab Rebar Installation 8 12-Oct-24 20-Oct-24 Top Slab Rebar Installation

JAH-Z4-ST-S24-TS.110 Top Slab Concrete Casting 1 21-Oct-24 21-Oct-24 Top Slab Concrete Casting

JAH-Z4-ST-S24-TS.112 Curing work 7 22-Oct-24 29-Oct-24 Curing work

JAH-Z4-ST-S24-TS.115 Top Slab Formwork Removel 2 30-Oct-24 31-Oct-24 Top Slab Formwork Removel

JAH-Z4-ST-S24-TS.120 Waterproofing for Top Slab 12 02-Nov-24 14-Nov-24 Waterproofing for Top Slab

MASS CONCRETE WORK 85 16-Nov-24 22-Feb-25 22-Feb-25, MASS CONCRETE WORK


JAH-Z4-ST-S24-MC.100Above Top Slab Formwork Installation for Plain Concrete 7 16-Nov-24 23-Nov-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z4-ST-S24-MC.105Plain Concrete Casting 1 24-Nov-24 24-Nov-24 Plain Concrete Casting

JAH-Z4-ST-S24-MC.110Mass Concrete Casting for Base Slab Top Layer 1 25-Nov-24 25-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z4-ST-S24-MC.112Curing work 7 26-Nov-24 03-Dec-24 Curing work

JAH-Z4-ST-S24-MC.115Concrete Protective Coating 8 13-Feb-25 22-Feb-25 Concrete Protective Coating

EGRESS STAIR-6 (ZONE-4) 236 28-Nov-23 05-Sep-24 05-Sep-24, EGRESS STAIR-6 (ZONE-4)
WALL AND 1ST FLIGHT 31 28-Nov-23 02-Jan-24 02-Jan-24, WALL AND 1ST FLIGHT
ENGR-STAIR-6-100 Excavation for Foundation 6 28-Nov-23 04-Dec-23 Excavation for Foundation

ENGR-STAIR-6-105 Foundation Blinding Concrete casting 1 05-Dec-23 05-Dec-23 Foundation Blinding Concrete casting

ENGR-STAIR-6-110 Foundation Rebar Installation 3 06-Dec-23 09-Dec-23 Foundation Rebar Installation

ENGR-STAIR-6-115 Foundation Formwork installation 3 10-Dec-23 12-Dec-23 Foundation Formwork installation

ENGR-STAIR-6-120 Foundation Concrete casting 1 13-Dec-23 13-Dec-23 Foundation Concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
338 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-6-125 Wall and Stair Rebar Installation 4 14-Dec-23 18-Dec-23 Wall and Stair Rebar Installation

ENGR-STAIR-6-130 Wall and Stair Form work Installation 6 19-Dec-23 25-Dec-23 Wall and Stair Form work Installation

ENGR-STAIR-6-135 Form Removal and Curing 7 26-Dec-23 02-Jan-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 03-Jan-24 22-Jan-24 22-Jan-24, WALL AND 2ND FLIGHT
ENGR-STAIR-6-140 Wall Rebar Installation 3 07-Jan-24 09-Jan-24 Wall Rebar Installation

ENGR-STAIR-6-145 Wall Form work Installation 3 10-Jan-24 13-Jan-24 Wall Form work Installation

ENGR-STAIR-6-150 Wall and Stair Concrete casting 1 14-Jan-24 14-Jan-24 Wall and Stair Concrete casting

ENGR-STAIR-6-300 Stair Form work Installation 3 03-Jan-24 06-Jan-24 Stair Form work Installation

ENGR-STAIR-6-375 Form Removal and Curing 7 15-Jan-24 22-Jan-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 23-Jan-24 11-Feb-24 11-Feb-24, WALL AND 3RD FLIGHT
ENGR-STAIR-6-170 Wall Rebar Installation 3 27-Jan-24 29-Jan-24 Wall Rebar Installation

ENGR-STAIR-6-175 Wall Form work Installation 3 30-Jan-24 01-Feb-24 Wall Form work Installation

ENGR-STAIR-6-180 Wall and Stair Concrete casting 1 03-Feb-24 03-Feb-24 Wall and Stair Concrete casting

ENGR-STAIR-6-305 Stair Form work Installation 3 23-Jan-24 25-Jan-24 Stair Form work Installation

ENGR-STAIR-6-370 Form Removal and Curing 7 04-Feb-24 11-Feb-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 12-Feb-24 02-Mar-24 02-Mar-24, WALL AND 4TH FLIGHT
ENGR-STAIR-6-155 Wall Rebar Installation 3 15-Feb-24 18-Feb-24 Wall Rebar Installation

ENGR-STAIR-6-160 Wall Form work Installation 3 19-Feb-24 21-Feb-24 Wall Form work Installation

ENGR-STAIR-6-165 Wall and Stair Concrete casting 1 22-Feb-24 22-Feb-24 Wall and Stair Concrete casting

ENGR-STAIR-6-310 Stair Form work Installation 3 12-Feb-24 14-Feb-24 Stair Form work Installation

ENGR-STAIR-6-365 Form Removal and Curing 7 24-Feb-24 02-Mar-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 03-Mar-24 21-Mar-24 21-Mar-24, WALL AND 5TH FLIGHT
ENGR-STAIR-6-215 Wall Rebar Installation 3 06-Mar-24 09-Mar-24 Wall Rebar Installation

ENGR-STAIR-6-220 Wall Form work Installation 3 10-Mar-24 12-Mar-24 Wall Form work Installation

ENGR-STAIR-6-225 Wall and Stair Concrete casting 1 13-Mar-24 13-Mar-24 Wall and Stair Concrete casting

ENGR-STAIR-6-315 Stair Form work Installation 3 03-Mar-24 05-Mar-24 Stair Form work Installation

ENGR-STAIR-6-360 Form Removal and Curing 7 14-Mar-24 21-Mar-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 23-Mar-24 14-Apr-24 14-Apr-24, WALL AND 6TH FLIGHT
ENGR-STAIR-6-230 Wall Rebar Installation 3 26-Mar-24 28-Mar-24 Wall Rebar Installation

ENGR-STAIR-6-235 Wall Form work Installation 3 30-Mar-24 01-Apr-24 Wall Form work Installation

ENGR-STAIR-6-240 Wall and Stair Concrete casting 1 02-Apr-24 02-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-6-320 Stair Form work Installation 3 23-Mar-24 25-Mar-24 Stair Form work Installation

ENGR-STAIR-6-355 Form Removal and Curing 7 03-Apr-24 14-Apr-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 15-Apr-24 04-May-24 04-May-24, WALL AND 7TH FLIGHT
ENGR-STAIR-6-200 Wall Rebar Installation 3 18-Apr-24 21-Apr-24 Wall Rebar Installation

ENGR-STAIR-6-205 Wall Form work Installation 3 22-Apr-24 24-Apr-24 Wall Form work Installation

ENGR-STAIR-6-210 Wall and Stair Concrete casting 1 25-Apr-24 25-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-6-325 Stair Form work Installation 3 15-Apr-24 17-Apr-24 Stair Form work Installation

ENGR-STAIR-6-380 Form Removal and Curing 7 27-Apr-24 04-May-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 05-May-24 23-May-24 23-May-24, WALL AND 8TH FLIGHT
ENGR-STAIR-6-185 Wall Rebar Installation 3 08-May-24 11-May-24 Wall Rebar Installation

ENGR-STAIR-6-190 Wall Form work Installation 3 12-May-24 14-May-24 Wall Form work Installation

ENGR-STAIR-6-195 Wall and Stair Concrete casting 1 15-May-24 15-May-24 Wall and Stair Concrete casting

ENGR-STAIR-6-330 Stair Form work Installation 3 05-May-24 07-May-24 Stair Form work Installation

ENGR-STAIR-6-385 Form Removal and Curing 7 16-May-24 23-May-24 Form Removal and Curing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
339 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL AND 9TH FLIGHT 17 25-May-24 12-Jun-24 12-Jun-24, WALL AND 9TH FLIGHT
ENGR-STAIR-6-270 Wall Rebar Installation 3 28-May-24 30-May-24 Wall Rebar Installation

ENGR-STAIR-6-275 Wall Form work Installation 3 01-Jun-24 03-Jun-24 Wall Form work Installation

ENGR-STAIR-6-280 Wall and Stair Concrete casting 1 04-Jun-24 04-Jun-24 Wall and Stair Concrete casting

ENGR-STAIR-6-335 Stair Form work Installation 3 25-May-24 27-May-24 Stair Form work Installation

ENGR-STAIR-6-390 Form Removal and Curing 7 05-Jun-24 12-Jun-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 13-Jun-24 07-Jul-24 07-Jul-24, WALL AND 10TH FLIGHT
ENGR-STAIR-6-285 Wall Rebar Installation 3 22-Jun-24 24-Jun-24 Wall Rebar Installation

ENGR-STAIR-6-290 Wall Form work Installation 3 25-Jun-24 27-Jun-24 Wall Form work Installation

ENGR-STAIR-6-295 Wall and Stair Concrete casting 1 29-Jun-24 29-Jun-24 Wall and Stair Concrete casting

ENGR-STAIR-6-340 Stair Form work Installation 3 13-Jun-24 20-Jun-24 Stair Form work Installation

ENGR-STAIR-6-395 Form Removal and Curing 7 30-Jun-24 07-Jul-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 08-Jul-24 27-Jul-24 27-Jul-24, WALL AND 11TH FLIGHT
ENGR-STAIR-6-255 Wall Rebar Installation 3 11-Jul-24 14-Jul-24 Wall Rebar Installation

ENGR-STAIR-6-260 Wall Form work Installation 3 15-Jul-24 17-Jul-24 Wall Form work Installation

ENGR-STAIR-6-265 Wall and Stair Concrete casting 1 18-Jul-24 18-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-6-345 Stair Form work Installation 3 08-Jul-24 10-Jul-24 Stair Form work Installation

ENGR-STAIR-6-400 Form Removal and Curing 7 20-Jul-24 27-Jul-24 Form Removal and Curing

TOP SLAB 35 28-Jul-24 05-Sep-24 05-Sep-24, TOP SLAB


ENGR-STAIR-6-245 Slab Rebar Installation 3 31-Jul-24 03-Aug-24 Slab Rebar Installation

ENGR-STAIR-6-250 Wall and Stair Concrete casting 3 04-Aug-24 06-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-6-350 Slab Form work Installation 3 28-Jul-24 30-Jul-24 Slab Form work Installation

ENGR-STAIR-6-405 Form Removal and Curing 7 07-Aug-24 14-Aug-24 Form Removal and Curing

ENGR-STAIR-6-410 Waterproofing and Coating 19 15-Aug-24 05-Sep-24 Waterproofing and Coating

ENGR-STAIR-6-415 Railing work 7 28-Aug-24 05-Sep-24 Railing work

EGRESS STAIR-7 (ZONE-4) 236 26-Dec-23 05-Oct-24 05-Oct-24, EGRESS STAIR-7 (ZONE-4)
WALL AND 1ST FLIGHT 31 26-Dec-23 30-Jan-24 30-Jan-24, WALL AND 1ST FLIGHT
ENGR-STAIR-7-100 Excavation for Foundation 6 26-Dec-23 01-Jan-24 Excavation for Foundation

ENGR-STAIR-7-105 Foundation Blinding Concrete casting 1 02-Jan-24 02-Jan-24 Foundation Blinding Concrete casting

ENGR-STAIR-7-110 Foundation Rebar Installation 3 03-Jan-24 06-Jan-24 Foundation Rebar Installation

ENGR-STAIR-7-115 Foundation Formwork installation 3 07-Jan-24 09-Jan-24 Foundation Formwork installation

ENGR-STAIR-7-120 Foundation Concrete casting 1 10-Jan-24 10-Jan-24 Foundation Concrete casting

ENGR-STAIR-7-125 Wall and Stair Rebar Installation 4 11-Jan-24 15-Jan-24 Wall and Stair Rebar Installation

ENGR-STAIR-7-130 Wall and Stair Form work Installation 6 16-Jan-24 22-Jan-24 Wall and Stair Form work Installation

ENGR-STAIR-7-135 Form Removal and Curing 7 23-Jan-24 30-Jan-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 31-Jan-24 19-Feb-24 19-Feb-24, WALL AND 2ND FLIGHT
ENGR-STAIR-7-140 Wall Rebar Installation 3 04-Feb-24 06-Feb-24 Wall Rebar Installation

ENGR-STAIR-7-145 Wall Form work Installation 3 07-Feb-24 10-Feb-24 Wall Form work Installation

ENGR-STAIR-7-150 Wall and Stair Concrete casting 1 11-Feb-24 11-Feb-24 Wall and Stair Concrete casting

ENGR-STAIR-7-300 Stair Form work Installation 3 31-Jan-24 03-Feb-24 Stair Form work Installation

ENGR-STAIR-7-375 Form Removal and Curing 7 12-Feb-24 19-Feb-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 20-Feb-24 10-Mar-24 10-Mar-24, WALL AND 3RD FLIGHT
ENGR-STAIR-7-170 Wall Rebar Installation 3 24-Feb-24 26-Feb-24 Wall Rebar Installation

ENGR-STAIR-7-175 Wall Form work Installation 3 27-Feb-24 29-Feb-24 Wall Form work Installation

ENGR-STAIR-7-180 Wall and Stair Concrete casting 1 02-Mar-24 02-Mar-24 Wall and Stair Concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
340 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-7-305 Stair Form work Installation 3 20-Feb-24 22-Feb-24 Stair Form work Installation

ENGR-STAIR-7-370 Form Removal and Curing 7 03-Mar-24 10-Mar-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 11-Mar-24 30-Mar-24 30-Mar-24, WALL AND 4TH FLIGHT
ENGR-STAIR-7-155 Wall Rebar Installation 3 14-Mar-24 17-Mar-24 Wall Rebar Installation

ENGR-STAIR-7-160 Wall Form work Installation 3 18-Mar-24 20-Mar-24 Wall Form work Installation

ENGR-STAIR-7-165 Wall and Stair Concrete casting 1 21-Mar-24 21-Mar-24 Wall and Stair Concrete casting

ENGR-STAIR-7-310 Stair Form work Installation 3 11-Mar-24 13-Mar-24 Stair Form work Installation

ENGR-STAIR-7-365 Form Removal and Curing 7 23-Mar-24 30-Mar-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 31-Mar-24 22-Apr-24 22-Apr-24, WALL AND 5TH FLIGHT
ENGR-STAIR-7-215 Wall Rebar Installation 3 03-Apr-24 06-Apr-24 Wall Rebar Installation

ENGR-STAIR-7-220 Wall Form work Installation 3 07-Apr-24 13-Apr-24 Wall Form work Installation

ENGR-STAIR-7-225 Wall and Stair Concrete casting 1 14-Apr-24 14-Apr-24 Wall and Stair Concrete casting

ENGR-STAIR-7-315 Stair Form work Installation 3 31-Mar-24 02-Apr-24 Stair Form work Installation

ENGR-STAIR-7-360 Form Removal and Curing 7 15-Apr-24 22-Apr-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 23-Apr-24 12-May-24 12-May-24, WALL AND 6TH FLIGHT
ENGR-STAIR-7-230 Wall Rebar Installation 3 27-Apr-24 29-Apr-24 Wall Rebar Installation

ENGR-STAIR-7-235 Wall Form work Installation 3 30-Apr-24 02-May-24 Wall Form work Installation

ENGR-STAIR-7-240 Wall and Stair Concrete casting 1 04-May-24 04-May-24 Wall and Stair Concrete casting

ENGR-STAIR-7-320 Stair Form work Installation 3 23-Apr-24 25-Apr-24 Stair Form work Installation

ENGR-STAIR-7-355 Form Removal and Curing 7 05-May-24 12-May-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 13-May-24 01-Jun-24 01-Jun-24, WALL AND 7TH FLIGHT
ENGR-STAIR-7-200 Wall Rebar Installation 3 16-May-24 19-May-24 Wall Rebar Installation

ENGR-STAIR-7-205 Wall Form work Installation 3 20-May-24 22-May-24 Wall Form work Installation

ENGR-STAIR-7-210 Wall and Stair Concrete casting 1 23-May-24 23-May-24 Wall and Stair Concrete casting

ENGR-STAIR-7-325 Stair Form work Installation 3 13-May-24 15-May-24 Stair Form work Installation

ENGR-STAIR-7-380 Form Removal and Curing 7 25-May-24 01-Jun-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 02-Jun-24 25-Jun-24 25-Jun-24, WALL AND 8TH FLIGHT
ENGR-STAIR-7-185 Wall Rebar Installation 3 05-Jun-24 08-Jun-24 Wall Rebar Installation

ENGR-STAIR-7-190 Wall Form work Installation 3 09-Jun-24 11-Jun-24 Wall Form work Installation

ENGR-STAIR-7-195 Wall and Stair Concrete casting 1 12-Jun-24 12-Jun-24 Wall and Stair Concrete casting

ENGR-STAIR-7-330 Stair Form work Installation 3 02-Jun-24 04-Jun-24 Stair Form work Installation

ENGR-STAIR-7-385 Form Removal and Curing 7 13-Jun-24 25-Jun-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 26-Jun-24 15-Jul-24 15-Jul-24, WALL AND 9TH FLIGHT
ENGR-STAIR-7-270 Wall Rebar Installation 3 30-Jun-24 02-Jul-24 Wall Rebar Installation

ENGR-STAIR-7-275 Wall Form work Installation 3 03-Jul-24 06-Jul-24 Wall Form work Installation

ENGR-STAIR-7-280 Wall and Stair Concrete casting 1 07-Jul-24 07-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-7-335 Stair Form work Installation 3 26-Jun-24 29-Jun-24 Stair Form work Installation

ENGR-STAIR-7-390 Form Removal and Curing 7 08-Jul-24 15-Jul-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 16-Jul-24 04-Aug-24 04-Aug-24, WALL AND 10TH FLIGHT
ENGR-STAIR-7-285 Wall Rebar Installation 3 20-Jul-24 22-Jul-24 Wall Rebar Installation

ENGR-STAIR-7-290 Wall Form work Installation 3 23-Jul-24 25-Jul-24 Wall Form work Installation

ENGR-STAIR-7-295 Wall and Stair Concrete casting 1 27-Jul-24 27-Jul-24 Wall and Stair Concrete casting

ENGR-STAIR-7-340 Stair Form work Installation 3 16-Jul-24 18-Jul-24 Stair Form work Installation

ENGR-STAIR-7-395 Form Removal and Curing 7 28-Jul-24 04-Aug-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 05-Aug-24 24-Aug-24 24-Aug-24, WALL AND 11TH FLIGHT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
341 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
ENGR-STAIR-7-255 Wall Rebar Installation 3 08-Aug-24 11-Aug-24 Wall Rebar Installation

ENGR-STAIR-7-260 Wall Form work Installation 3 12-Aug-24 14-Aug-24 Wall Form work Installation

ENGR-STAIR-7-265 Wall and Stair Concrete casting 1 15-Aug-24 15-Aug-24 Wall and Stair Concrete casting

ENGR-STAIR-7-345 Stair Form work Installation 3 05-Aug-24 07-Aug-24 Stair Form work Installation

ENGR-STAIR-7-400 Form Removal and Curing 7 17-Aug-24 24-Aug-24 Form Removal and Curing

TOP SLAB 35 25-Aug-24 05-Oct-24 05-Oct-24, TOP SLAB


ENGR-STAIR-7-245 Slab Rebar Installation 3 28-Aug-24 31-Aug-24 Slab Rebar Installation

ENGR-STAIR-7-250 Wall and Stair Concrete casting 3 01-Sep-24 03-Sep-24 Wall and Stair Concrete casting

ENGR-STAIR-7-350 Slab Form work Installation 3 25-Aug-24 27-Aug-24 Slab Form work Installation

ENGR-STAIR-7-405 Form Removal and Curing 7 04-Sep-24 11-Sep-24 Form Removal and Curing

ENGR-STAIR-7-410 Waterproofing and Coating 19 12-Sep-24 05-Oct-24 Waterproofing and Coating

ENGR-STAIR-7-415 Railing work 7 26-Sep-24 05-Oct-24 Railing work

BACKFILLING UPTO TUNNELWALL 213 24-Dec-23 04-Sep-24 04-Sep-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z4-CON-BF.190 Backfilling & Compaction @ 1+268 ~ 1+368 20 24-Dec-23 15-Jan-24 Backfilling & Compaction @ 1+268 ~ 1+368

JAH-Z4-CON-BF.195 Backfilling & Compaction @ 1+368 ~ 1+468 20 27-Feb-24 20-Mar-24 Backfilling & Compaction @ 1+368 ~ 1+468

JAH-Z4-CON-BF.200 Backfilling & Compaction @ 1+468 ~ 1+568 20 06-Apr-24 01-May-24 Backfilling & Compaction @ 1+468 ~ 1+568

JAH-Z4-CON-BF.205 Backfilling & Compaction @ 1+568 ~ 1+668 20 22-Jun-24 14-Jul-24 Backfilling & Compaction @ 1+568 ~ 1+668

JAH-Z4-CON-BF.210 Backfilling & Compaction @ 1+668 ~ 1+753 20 13-Aug-24 04-Sep-24 Backfilling & Compaction @ 1+668 ~ 1+753

STRUCTURAL FILL 323 19-May-24 14-Jun-25 14-Jun-25, STRUCTURAL FILL


JAH-Z4-SF-IL.100 Backfilling & Compaction at Invert Level @ 1+268 ~ 1+368 20 19-May-24 11-Jun-24 Backfilling & Compaction at Invert Level @ 1+268 ~ 1+368

JAH-Z4-SF-IL.105 Backfilling & Compaction at Invert Level @ 1+368 ~ 1+468 20 20-Aug-24 12-Sep-24 Backfilling & Compaction at Invert Level @ 1+368 ~ 1+468

JAH-Z4-SF-IL.110 Backfilling & Compaction at Invert Level @ 1+468 ~ 1+568 20 20-Oct-24 12-Nov-24 Backfilling & Compaction at Invert Level @ 1+468 ~ 1+568

JAH-Z4-SF-IL.115 Backfilling & Compaction at Invert Level @ 1+568 ~ 1+668 20 24-Apr-25 18-May-25 Backfilling & Compaction at Invert Level @ 1+568 ~ 1+668

JAH-Z4-SF-IL.120 Backfilling & Compaction at Invert Level @ 1+668 ~ 1+753 20 18-May-25 14-Jun-25 Backfilling & Compaction at Invert Level @ 1+668 ~ 1+753

WET & DRY UTILITIES 189 20-Nov-24 06-Jul-25 06-Jul-25, WET & DRY UTILITIES
INSIDE WET CULVERT 142 20-Nov-24 08-May-25 08-May-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 59 20-Nov-24 27-Jan-25 27-Jan-25, POTABLE WATER NETWORK
JAH-Z4-WU-PWN.100 Pipe Supports Installation 25 20-Nov-24 18-Dec-24 Pipe Supports Installation

JAH-Z4-WU-PWN.105 Pipe Installation alongwith Valves, Fittings & Accessories 30 19-Dec-24 22-Jan-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-PWN.110 Testing 4 23-Jan-25 27-Jan-25 Testing

GREY WATER DISTRIBUTION SYSTEM 49 19-Dec-24 13-Feb-25 13-Feb-25, GREY WATER DISTRIBUTION SYSTEM
JAH-Z4-WU-GWD.255 Pipe Supports Installation 20 19-Dec-24 11-Jan-25 Pipe Supports Installation

JAH-Z4-WU-GWD.260 Pipe Installation alongwith Valves, Fittings & Accessories 25 12-Jan-25 09-Feb-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-GWD.265 Testing 4 10-Feb-25 13-Feb-25 Testing

IRRIGATION NETWORK 49 23-Feb-25 24-Apr-25 24-Apr-25, IRRIGATION NETWORK


JAH-Z4-WU-IN.605 Pipe Supports Installation 20 23-Feb-25 17-Mar-25 Pipe Supports Installation

JAH-Z4-WU-IN.610 Pipe Installation alongwith Valves, Fittings & Accessories 25 18-Mar-25 20-Apr-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-IN.615 Testing 4 21-Apr-25 24-Apr-25 Testing

CHILLED WATER SUPPLY NETWORK 89 12-Jan-25 29-Apr-25 29-Apr-25, CHILLED WATER SUPPLY NETWORK
JAH-Z4-WU-CWS.145 Pipe Supports Installation 25 12-Jan-25 09-Feb-25 Pipe Supports Installation

JAH-Z4-WU-CWS.150 Pipe Installation alongwith Valves, Fittings & Accessories 30 10-Feb-25 16-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-CWS.155 Testing 4 26-Apr-25 29-Apr-25 Testing

CHILLED WATER RETURN NETWORK 93 12-Jan-25 04-May-25 04-May-25, CHILLED WATER RETURN NETWORK
JAH-Z4-WU-CWR.145 Pipe Supports Installation 25 12-Jan-25 09-Feb-25 Pipe Supports Installation

JAH-Z4-WU-CWR.150 Pipe Installation alongwith Valves, Fittings & Accessories 30 10-Feb-25 16-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-CWR.155 Testing 4 30-Apr-25 04-May-25 Testing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
342 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AUTOMATIC WASTE COLLECTION NETWORK 117 19-Dec-24 08-May-25 08-May-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z4-WU-AWC.145 Pipe Supports Installation 25 19-Dec-24 16-Jan-25 Pipe Supports Installation

JAH-Z4-WU-AWC.150 Pipe Installation alongwith Valves, Fittings & Accessories 30 18-Jan-25 20-Feb-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z4-WU-AWC.155 Testing 4 05-May-25 08-May-25 Testing

INSIDE DRY CULVERT 164 19-Dec-24 06-Jul-25 06-Jul-25, INSIDE DRY CULVERT
POWER 164 19-Dec-24 06-Jul-25 06-Jul-25, POWER
HIGH VOLTAGE 110 KV NETWORK 30 19-Dec-24 22-Jan-25 22-Jan-25, HIGH VOLTAGE 110 KV NETWORK
JAH-Z4-IDC-PO-HV.130
HV Cable Supports Installation 12 19-Dec-24 01-Jan-25 HV Cable Supports Installation

JAH-Z4-IDC-PO-HV.135
Cable Installation with Fittings & Accessories 18 02-Jan-25 22-Jan-25 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 32 23-Jan-25 01-Mar-25 01-Mar-25, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z4-IDC-PO-MV.130
HV Cable Supports Installation 12 23-Jan-25 05-Feb-25 HV Cable Supports Installation

JAH-Z4-IDC-PO-MV.135
Cables Installation with Fittings & Accessories 20 06-Feb-25 01-Mar-25 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 32 02-Mar-25 12-Apr-25 12-Apr-25, LOW VOLTAGE NETWORK


JAH-Z4-IDC-PO-LV.130
HV Cable Supports Installation 12 02-Mar-25 15-Mar-25 HV Cable Supports Installation

JAH-Z4-IDC-PO-LV.135
Cable Laying with Fittings & Accessories 20 16-Mar-25 12-Apr-25 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 70 13-Apr-25 06-Jul-25 06-Jul-25, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z4-IDC-PO-DS.220
Cable Tray Installation 10 13-Apr-25 23-Apr-25 Cable Tray Installation

JAH-Z4-IDC-PO-DS.225
PVC Ducts Installation 5 24-Apr-25 29-Apr-25 PVC Ducts Installation

JAH-Z4-IDC-PO-DS.230
Cable Installation 10 30-Apr-25 11-May-25 Cable Installation

JAH-Z4-IDC-PO-DS.235
Isolators Installation 5 12-May-25 17-May-25 Isolators Installation

JAH-Z4-IDC-PO-DS.240
Sub Main Distribution Boards Installation 10 18-May-25 28-May-25 Sub Main Distribution Boards Installation

JAH-Z4-IDC-PO-DS.245
Motor Control Centres Installation 10 29-May-25 12-Jun-25 Motor Control Centres Installation

JAH-Z4-IDC-PO-DS.250
Distribution Boards Installation 10 14-Jun-25 24-Jun-25 Distribution Boards Installation

JAH-Z4-IDC-PO-DS.255
Wiring Accessories Installation 10 25-Jun-25 06-Jul-25 Wiring Accessories Installation

LIGHTING SYSTEM 35 24-Apr-25 03-Jun-25 03-Jun-25, LIGHTING SYSTEM


JAH-Z4--IDC-LS.295 Cables Installation 10 24-Apr-25 05-May-25 Cables Installation

JAH-Z4--IDU-LS.290 Luminaires Installation 10 24-May-25 03-Jun-25 Luminaires Installation

JAH-Z4-IDU-LS.275 Light Point Installation 15 06-May-25 22-May-25 Light Point Installation

TELECOM SERVICES 30 13-Apr-25 17-May-25 17-May-25, TELECOM SERVICES


JAH-Z4-IDU-TES.145 Mobily Lines 10 13-Apr-25 23-Apr-25 Mobily Lines

JAH-Z4-IDU-TES.150 STC Line 10 06-May-25 17-May-25 STC Line

JAH-Z4-IDU-TES.155 MOI Line 10 24-Apr-25 05-May-25 MOI Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 187 20-Nov-24 03-Jul-25 03-Jul-25, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 160 20-Nov-24 29-May-25 29-May-25, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 56 20-Nov-24 23-Jan-25 23-Jan-25, FIRE FIGHTING SYSTEM
JAH-Z4-MECH-FF100 Pipe Installation work 20 20-Nov-24 12-Dec-24 Pipe Installation work

JAH-Z4-MECH-FF105 Valves and Accessories Installation 8 14-Dec-24 22-Dec-24 Valves and Accessories Installation

JAH-Z4-MECH-FF110 Sprinklers Installation 5 23-Dec-24 28-Dec-24 Sprinklers Installation

JAH-Z4-MECH-FF115 Fire Extinguishers Installation 8 29-Dec-24 06-Jan-25 Fire Extinguishers Installation

JAH-Z4-MECH-FF120 Foam Tank Installation 6 07-Jan-25 13-Jan-25 Foam Tank Installation

JAH-Z4-MECH-FF125 Pipe Painting work 6 14-Jan-25 20-Jan-25 Pipe Painting work

JAH-Z4-MECH-FF130 Testing work 3 21-Jan-25 23-Jan-25 Testing work

VENTILATION SYSTEM 23 25-Jan-25 19-Feb-25 19-Feb-25, VENTILATION SYSTEM


JAH-Z4-MECH-VS100 Staircase Pressurisation Fan Installation 5 25-Jan-25 29-Jan-25 Staircase Pressurisation Fan Installation

JAH-Z4-MECH-VS105 Extract fan installation 5 30-Jan-25 04-Feb-25 Extract fan installation

JAH-Z4-MECH-VS110 Unidirectional Jet fan 5 05-Feb-25 10-Feb-25 Unidirectional Jet fan

JAH-Z4-MECH-VS115 Reverse Jet fan 5 11-Feb-25 16-Feb-25 Reverse Jet fan

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
343 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-MECH-VS120 Testing work 3 17-Feb-25 19-Feb-25 Testing work

PUMPS INSTALLATION 15 20-Feb-25 09-Mar-25 09-Mar-25, PUMPS INSTALLATION


JAH-Z4-MECH-PI.145 Sump Pump Installation 7 20-Feb-25 27-Feb-25 Sump Pump Installation

JAH-Z4-MECH-PI.150 Pipe Connection work 6 01-Mar-25 06-Mar-25 Pipe Connection work

JAH-Z4-MECH-PI.155 Testing work 2 08-Mar-25 09-Mar-25 Testing work

DUCTING SYSTEM 66 10-Mar-25 29-May-25 29-May-25, DUCTING SYSTEM


JAH-Z4-MECH-DS.205Duct Installation work 28 10-Mar-25 15-Apr-25 Duct Installation work

JAH-Z4-MECH-DS.210Grills Installation work 7 16-Apr-25 23-Apr-25 Grills Installation work

JAH-Z4-MECH-DS.215Diffusers Installation work 7 24-Apr-25 01-May-25 Diffusers Installation work

JAH-Z4-MECH-DS.220Non Returns Dampers 7 03-May-25 10-May-25 Non Returns Dampers

JAH-Z4-MECH-DS.225Fire and Smoke Damper 7 11-May-25 18-May-25 Fire and Smoke Damper

JAH-Z4-MECH-DS.230Sand Trap Louvre 5 19-May-25 24-May-25 Sand Trap Louvre

JAH-Z4-MECH-DS.235Testing work 5 25-May-25 29-May-25 Testing work

TUNNEL ELECTRICAL WORKS 187 20-Nov-24 03-Jul-25 03-Jul-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 101 20-Nov-24 17-Mar-25 17-Mar-25, CABLE TRAYS
JAH-Z4-ELC-CT280 600mm Cable Tray 21 20-Nov-24 14-Dec-24 600mm Cable Tray

JAH-Z4-ELC-CT285 400mm Cable Tray 14 15-Dec-24 30-Dec-24 400mm Cable Tray

JAH-Z4-ELC-CT290 300mm Cable Tray 10 31-Dec-24 11-Jan-25 300mm Cable Tray

JAH-Z4-ELC-CT295 200mm Cable Tray 8 12-Jan-25 20-Jan-25 200mm Cable Tray

JAH-Z4-ELC-CT300 150mm Cable Tray 8 21-Jan-25 29-Jan-25 150mm Cable Tray

JAH-Z4-ELC-CT305 100mm Cable Tray 6 30-Jan-25 05-Feb-25 100mm Cable Tray

JAH-Z4-ELC-CT310 75mm Cable Tray 5 06-Feb-25 11-Feb-25 75mm Cable Tray

JAH-Z4-ELC-CT315 150mm x 100mm Trunking 7 12-Feb-25 19-Feb-25 150mm x 100mm Trunking

JAH-Z4-ELC-CT320 100mm x 100mm Trunking 6 20-Feb-25 26-Feb-25 100mm x 100mm Trunking

JAH-Z4-ELC-CT325 100mm x 75mm Trunking 7 27-Feb-25 06-Mar-25 100mm x 75mm Trunking

JAH-Z4-ELC-CT330 PVC Ducts150mm dia 5 08-Mar-25 12-Mar-25 PVC Ducts150mm dia

JAH-Z4-ELC-CT335 PVC Ducts100mm dia 4 13-Mar-25 17-Mar-25 PVC Ducts100mm dia

POWER CABLES 166 15-Dec-24 03-Jul-25 03-Jul-25, POWER CABLES


JAH-Z4-ELC-PC.385 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 15-Dec-24 28-Dec-24 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z4-ELC-PC.390 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 15-Dec-24 08-Jan-25 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z4-ELC-PC.395 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 17-Dec-24 08-Jan-25 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z4-ELC-PC.400 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 28 09-Jan-25 10-Feb-25 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z4-ELC-PC.405 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 26-Jan-25 10-Feb-25 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z4-ELC-PC.410 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 27-Jan-25 10-Feb-25 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z4-ELC-PC.415 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 27-Jan-25 18-Feb-25 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z4-ELC-PC.420 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 01-Feb-25 18-Feb-25 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z4-ELC-PC.425 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 01-Feb-25 18-Feb-25 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z4-ELC-PC.430 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 19-Feb-25 03-Mar-25 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z4-ELC-PC.435 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 04-Mar-25 15-Mar-25 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z4-ELC-PC.440 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 16-Mar-25 23-Mar-25 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z4-ELC-PC.445 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 24-Mar-25 28-Apr-25 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z4-ELC-PC.450 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 28 23-Mar-25 28-Apr-25 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z4-ELC-PC.455 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 29-Apr-25 06-May-25 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z4-ELC-PC.460 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 07-May-25 14-May-25 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
344 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-ELC-PC.465 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 07-May-25 09-Jun-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z4-ELC-PC.470 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 40 07-May-25 25-Jun-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

JAH-Z4-ELC-PC.475 Testing work 7 26-Jun-25 03-Jul-25 Testing work

ELECTRICAL INSTALLATIONS 86 16-Mar-25 01-Jul-25 01-Jul-25, ELECTRICAL INSTALLATIONS


JAH-Z4-ELC-INS220 Wiring Accessories 15 15-Apr-25 01-May-25 Wiring Accessories

JAH-Z4-ELC-INS225 Lighting Installation 14 03-May-25 18-May-25 Lighting Installation

JAH-Z4-ELC-INS230 Isolators Installation 12 19-May-25 01-Jun-25 Isolators Installation

JAH-Z4-ELC-INS235 Circuit Wiring Installation 22 16-Mar-25 14-Apr-25 Circuit Wiring Installation

JAH-Z4-ELC-INS240 SMDB Installation 5 02-Jun-25 10-Jun-25 SMDB Installation

JAH-Z4-ELC-INS245 Motor Control Centres Installation 5 11-Jun-25 16-Jun-25 Motor Control Centres Installation

JAH-Z4-ELC-INS250 Distribution Boards 6 17-Jun-25 23-Jun-25 Distribution Boards

JAH-Z4-ELC-INS255 Testing work 7 24-Jun-25 01-Jul-25 Testing work

LOW CURRENT 180 20-Nov-24 25-Jun-25 25-Jun-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 82 20-Nov-24 23-Feb-25 23-Feb-25, FIRE DETECTION AND ALARM SYSTEM
JAH-Z4-LOW-FDT280 Fire Alarm Control Panel Installation 6 04-Dec-24 10-Dec-24 Fire Alarm Control Panel Installation

JAH-Z4-LOW-FDT285 Tamper switch Installation 5 11-Dec-24 16-Dec-24 Tamper switch Installation

JAH-Z4-LOW-FDT290 Zone Input units Installation 5 17-Dec-24 22-Dec-24 Zone Input units Installation

JAH-Z4-LOW-FDT295 Fire Alarm sounder Installation 4 23-Dec-24 26-Dec-24 Fire Alarm sounder Installation

JAH-Z4-LOW-FDT300 Fire Alarm Speaker Installation 8 28-Dec-24 05-Jan-25 Fire Alarm Speaker Installation

JAH-Z4-LOW-FDT305 Smoke Detector Installation 8 06-Jan-25 14-Jan-25 Smoke Detector Installation

JAH-Z4-LOW-FDT310 Heat Detector Installation 8 15-Jan-25 23-Jan-25 Heat Detector Installation

JAH-Z4-LOW-FDT315 Interface Module Installation 8 25-Jan-25 02-Feb-25 Interface Module Installation

JAH-Z4-LOW-FDT320 Fibre-optic Sensing Cable Laying 12 20-Nov-24 03-Dec-24 Fibre-optic Sensing Cable Laying

JAH-Z4-LOW-FDT325 Double Action Manual Call Point Installation 7 03-Feb-25 10-Feb-25 Double Action Manual Call Point Installation

JAH-Z4-LOW-FDT330 Flashing Beacon Installation 6 11-Feb-25 17-Feb-25 Flashing Beacon Installation

JAH-Z4-LOW-FDT335 Testing work 5 18-Feb-25 23-Feb-25 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 28 04-Dec-24 05-Jan-25 05-Jan-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z4-LOW-PH160 8 core UTP Cable Laying 7 04-Dec-24 11-Dec-24 8 core UTP Cable Laying

JAH-Z4-LOW-PH165 Junction box Installation 7 12-Dec-24 19-Dec-24 Junction box Installation

JAH-Z4-LOW-PH170 Emergency Telephone Installation 7 21-Dec-24 28-Dec-24 Emergency Telephone Installation

JAH-Z4-LOW-PH175 Connection and Testing 7 29-Dec-24 05-Jan-25 Connection and Testing

PUBLIC ADDRESS 28 06-Jan-25 06-Feb-25 06-Feb-25, PUBLIC ADDRESS


JAH-Z4-LOW-PA160 Wall-mounted Voice Evacuation Horn Speaker Installation 7 14-Jan-25 21-Jan-25 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z4-LOW-PA165 Voice alarm control panel Installation 7 22-Jan-25 29-Jan-25 Voice alarm control panel Installation

JAH-Z4-LOW-PA170 Cables laying public address system 7 06-Jan-25 13-Jan-25 Cables laying public address system

JAH-Z4-LOW-PA175 Connection and Testing 7 30-Jan-25 06-Feb-25 Connection and Testing

VIDEO SURVEILLANCE 49 08-Feb-25 09-Apr-25 09-Apr-25, VIDEO SURVEILLANCE


JAH-Z4-LOW-VDS205Single Core Fibre Optical Cable Laying 7 08-Feb-25 15-Feb-25 Single Core Fibre Optical Cable Laying

JAH-Z4-LOW-VDS210RTU Panel Installation 7 16-Feb-25 23-Feb-25 RTU Panel Installation

JAH-Z4-LOW-VDS215Overhead Vehicle Detector Installation 7 24-Feb-25 03-Mar-25 Overhead Vehicle Detector Installation

JAH-Z4-LOW-VDS220Door Contact Installation 7 04-Mar-25 11-Mar-25 Door Contact Installation

JAH-Z4-LOW-VDS225PTZ Camera mounted on Pole Installation 7 12-Mar-25 19-Mar-25 PTZ Camera mounted on Pole Installation

JAH-Z4-LOW-VDS230Fixed (AID) Camera Installation 7 20-Mar-25 27-Mar-25 Fixed (AID) Camera Installation

JAH-Z4-LOW-VDS235Testing work 7 29-Mar-25 09-Apr-25 Testing work

SACADA SYSTEM 35 10-Apr-25 20-May-25 20-May-25, SACADA SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
345 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z4-LOW-SCA175Cabling Laying 7 10-Apr-25 17-Apr-25 Cabling Laying

JAH-Z4-LOW-SCA180Remote Terminal Unit Installation 7 19-Apr-25 26-Apr-25 Remote Terminal Unit Installation

JAH-Z4-LOW-SCA185Programmable Logic Control Unit Installation 7 27-Apr-25 04-May-25 Programmable Logic Control Unit Installation

JAH-Z4-LOW-SCA190SCADA/ PC/ Soft ware/ Printers Installation 7 05-May-25 12-May-25 SCADA/ PC/ Soft ware/ Printers Installation

JAH-Z4-LOW-SCA195Testing work 7 13-May-25 20-May-25 Testing work

RADIO RE-BROADCASTING SYSTEM 28 21-May-25 25-Jun-25 25-Jun-25, RADIO RE-BROADCASTING SYSTEM


JAH-Z4-LOW-RDO160Leaky Feeder Cable Laying 7 21-May-25 28-May-25 Leaky Feeder Cable Laying

JAH-Z4-LOW-RDO165Inline Bidirectional Signal Amplifier Installation 7 29-May-25 09-Jun-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z4-LOW-RDO170End of Line Terminator 7 10-Jun-25 17-Jun-25 End of Line Terminator

JAH-Z4-LOW-RDO175Connection and Testing 7 18-Jun-25 25-Jun-25 Connection and Testing

TUNNEL PLUMBING WORKS 35 23-Feb-25 08-Apr-25 08-Apr-25, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 23-Feb-25 08-Apr-25 08-Apr-25, DRAINAGE SYSTEM
JAH-Z4-MECH-PLM120Drainage Pipes Installation Incl. Fittings & Accessories 15 23-Feb-25 11-Mar-25 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z4-MECH-PLM125Collection Chambers 20 12-Mar-25 08-Apr-25 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 09-Apr-25 27-May-25 27-May-25, TUNNEL INTERNAL ROAD WORK
JAH-Z4-TIRW.440 Kerbs, Channels & Edging 7 09-Apr-25 16-Apr-25 Kerbs, Channels & Edging

JAH-Z4-TIRW.445 Tack Coat Application (MC-1) 10 17-Apr-25 28-Apr-25 Tack Coat Application (MC-1)

JAH-Z4-TIRW.450 Bituminious Base Course Layer 10 17-Apr-25 28-Apr-25 Bituminious Base Course Layer

JAH-Z4-TIRW.455 Tack Coat Application (RC-2) 12 29-Apr-25 12-May-25 Tack Coat Application (RC-2)

JAH-Z4-TIRW.460 Asphalt Wearing Course Layer 12 29-Apr-25 12-May-25 Asphalt Wearing Course Layer

JAH-Z4-TIRW.465 Pavement Line Marking 5 13-May-25 18-May-25 Pavement Line Marking

JAH-Z4-TIRW.470 Traffic Signboards Installation 8 19-May-25 27-May-25 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 35 13-May-25 25-Jun-25 25-Jun-25, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z4-DW.220 Fire Protection Board Installation 10 13-May-25 24-May-25 Fire Protection Board Installation

JAH-Z4-DW.225 GRC Panel Board Installation 25 25-May-25 25-Jun-25 GRC Panel Board Installation

ZONE 5 - FROM STA. 1+753 ~ 2+157 927 02-Jul-22 A 27-Dec-25 27-Dec-25, ZONE 5 - FROM STA. 1+753 ~ 2+157
ENGINEERING 244 02-Jul-22 A 18-Dec-23 18-Dec-23, ENGINEERING
RAM160 Completion Engineering Work For Zone5 0 18-Dec-23* Completion Engineering Work For Zone5

SITE SURVEY 14 02-Jul-22 A 04-Oct-22 A 04-Oct-22 A, SITE SURVEY


JAH-Z5-EN-SS.140 Site Survey/Settingout Control Points 2 02-Jul-22 A 27-Sep-22 A Site Survey/Settingout Control Points

JAH-Z5-EN-SS.145 Review and Approval of Site Survey & Control Points 12 01-Aug-22 A 04-Oct-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 170 22-Aug-22 A 07-Jun-23 07-Jun-23, SHOP DRAWINGS


CIVIL/STRUCTURAL 1+754 ~1+854 42 01-Mar-23 18-Apr-23 18-Apr-23, CIVIL/STRUCTURAL 1+754 ~1+854
JAH-Z5-ENG-CS.300 Plan and Profile Shop Drawings Preparation & Submission 6 01-Mar-23 07-Mar-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.305 Plan and Profile Shop Drawings Review & Approval 12 08-Mar-23 21-Mar-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z5-ENG-CS.310 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 22-Mar-23 28-Mar-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.315 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 29-Mar-23 11-Apr-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z5-ENG-CS.320 Tunnel Structural Shop Drawings Submission 6 29-Mar-23 04-Apr-23 Tunnel Structural Shop Drawings Submission

JAH-Z5-ENG-CS.325 Tunnel Structural Shop Drawings Review & Approval 12 05-Apr-23 18-Apr-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 1+854 ~1+954 42 22-Mar-23 13-May-23 13-May-23, CIVIL/STRUCTURAL 1+854 ~1+954


JAH-Z5-ENG-CS.450 Plan and Profile Shop Drawings Preparation & Submission 6 22-Mar-23 28-Mar-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.455 Plan and Profile Shop Drawings Review & Approval 12 29-Mar-23 11-Apr-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z5-ENG-CS.460 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 12-Apr-23 18-Apr-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.465 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 19-Apr-23 06-May-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z5-ENG-CS.470 Tunnel Structural Shop Drawings Submission 6 19-Apr-23 29-Apr-23 Tunnel Structural Shop Drawings Submission

JAH-Z5-ENG-CS.475 Tunnel Structural Shop Drawings Review & Approval 12 30-Apr-23 13-May-23 Tunnel Structural Shop Drawings Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
346 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CIVIL/STRUCTURAL 1+954 ~2+093 116 22-Aug-22 A 13-May-23 13-May-23, CIVIL/STRUCTURAL 1+954 ~2+093
JAH-Z5-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 22-Aug-22 A 08-Sep-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 08-Sep-22 A 19-Sep-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z5-ENG-CS.410 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 12-Apr-23 18-Apr-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.415 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 19-Apr-23 06-May-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z5-ENG-CS.420 Tunnel Structural Shop Drawings Submission 6 19-Apr-23 29-Apr-23 Tunnel Structural Shop Drawings Submission

JAH-Z5-ENG-CS.425 Tunnel Structural Shop Drawings Review & Approval 12 30-Apr-23 13-May-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 2+093 ~2+157 134 22-Aug-22 A 13-May-23 13-May-23, CIVIL/STRUCTURAL 2+093 ~2+157
JAH-Z5-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 22-Aug-22 A 08-Sep-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 08-Sep-22 A 19-Sep-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z5-ENG-CS.360 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 12-Apr-23 18-Apr-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z5-ENG-CS.365 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 19-Apr-23 06-May-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z5-ENG-CS.370 Tunnel Structural Shop Drawings Submission 6 19-Apr-23 29-Apr-23 Tunnel Structural Shop Drawings Submission

JAH-Z5-ENG-CS.375 Tunnel Structural Shop Drawings Review & Approval 12 30-Apr-23 13-May-23 Tunnel Structural Shop Drawings Review & Approval

ARCHITECTURAL 22 14-May-23 07-Jun-23 07-Jun-23, ARCHITECTURAL


JAH-Z5-ENG-AR.140 Tunnel Architectural Shop Drawings Preparation & Submission 10 14-May-23 24-May-23 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z5-ENG-AR.145 Tunnel Architectural Shop Drawings Review & Approval 12 25-May-23 07-Jun-23 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 192 30-Apr-23 13-Dec-23 13-Dec-23, UTILITIES


WET UTILITIES 120 30-Apr-23 19-Sep-23 19-Sep-23, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 32 30-Apr-23 05-Jun-23 05-Jun-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
JAH-Z5-ENG-WU-PW.100
Shop Drawings Preparation & Submission 20 30-Apr-23 22-May-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-WU-PW.105
Shop Drawings Review & Approval 12 23-May-23 05-Jun-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 22 06-Jun-23 04-Jul-23 04-Jul-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z5-ENG-WU-GW.100
Shop Drawings Preparation & Submission 10 06-Jun-23 17-Jun-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-WU-GW.105
Shop Drawings Review & Approval 12 18-Jun-23 04-Jul-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 22 05-Jul-23 30-Jul-23 30-Jul-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z5-EN-WU-IR100 Shop Drawings Preparation & Submission 10 05-Jul-23 16-Jul-23 Shop Drawings Preparation & Submission

JAH-Z5-EN-WU-IR105 Shop Drawings Review & Approval 12 17-Jul-23 30-Jul-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 22 31-Jul-23 24-Aug-23 24-Aug-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z5-EN-WU-CWS100
Shop Drawings Preparation & Submission 10 31-Jul-23 10-Aug-23 Shop Drawings Preparation & Submission

JAH-Z5-EN-WU-CWS105
Shop Drawings Review & Approval 12 12-Aug-23 24-Aug-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 22 26-Aug-23 19-Sep-23 19-Sep-23, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z5-EN-WU-AWC100
Shop Drawings Preparation & Submission 10 26-Aug-23 05-Sep-23 Shop Drawings Preparation & Submission

JAH-Z5-EN-WU-AWC105
Shop Drawings Review & Approval 12 06-Sep-23 19-Sep-23 Shop Drawings Review & Approval

DRY UTILITIES 160 06-Jun-23 13-Dec-23 13-Dec-23, DRY UTILITIES


POWER 128 06-Jun-23 06-Nov-23 06-Nov-23, POWER
HIGH VOLTAGE 110 KV NETWORK 22 06-Jun-23 04-Jul-23 04-Jul-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z5-ENG-DU-PW.340
Shop Drawings Preparation & Submission 10 06-Jun-23 17-Jun-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-PW.345
Shop Drawings Review & Approval 12 18-Jun-23 04-Jul-23 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 25 05-Jul-23 02-Aug-23 02-Aug-23, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z5-ENG-DU-PW.350
Shop Drawings Preparation & Submission 13 05-Jul-23 19-Jul-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-PW.355
Shop Drawings Review & Approval 12 20-Jul-23 02-Aug-23 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 27 03-Aug-23 03-Sep-23 03-Sep-23, LOW VOLTAGE NETWORK


JAH-Z5-ENG-DU-PW.360
Shop Drawings Preparation & Submission 15 03-Aug-23 20-Aug-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-PW.365
Shop Drawings Review & Approval 12 21-Aug-23 03-Sep-23 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 22 04-Sep-23 30-Sep-23 30-Sep-23, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z5-ENG-DU-PW.370
Shop Drawings Preparation & Submission 10 04-Sep-23 14-Sep-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-PW.375
Shop Drawings Review & Approval 12 16-Sep-23 30-Sep-23 Shop Drawings Review & Approval

LIGHTING SYSTEM 32 01-Oct-23 06-Nov-23 06-Nov-23, LIGHTING SYSTEM

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
347 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ENG-DU-PW.380
Shop Drawings Preparation & Submission 20 01-Oct-23 23-Oct-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-PW.385
Shop Drawings Review & Approval 12 24-Oct-23 06-Nov-23 Shop Drawings Review & Approval

LOW CURRENT 32 07-Nov-23 13-Dec-23 13-Dec-23, LOW CURRENT


TELECOM SERVICES 32 07-Nov-23 13-Dec-23 13-Dec-23, TELECOM SERVICES
JAH-Z5-ENG-DU-LC.170
Shop Drawings Preparation & Submission 20 07-Nov-23 29-Nov-23 Shop Drawings Preparation & Submission

JAH-Z5-ENG-DU-LC.175
Shop Drawings Review & Approval 12 30-Nov-23 13-Dec-23 Shop Drawings Review & Approval

MEP 220 29-Mar-23 18-Dec-23 18-Dec-23, MEP


TUNNEL MECHANICAL WORKS 176 29-Mar-23 28-Oct-23 28-Oct-23, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 29-Mar-23 16-Jul-23 16-Jul-23, FIRE FIGHTING SYSTEM
JAH-Z5-ENG-FF.260 Fire Fighting Pipe Layout Plan Preparation & Submission 10 29-Mar-23 09-Apr-23 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z5-ENG-FF.265 Fire Fighting Pipe Layout Plan Review & Approval 12 10-Apr-23 26-Apr-23 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z5-ENG-FF.270 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 27-Apr-23 08-May-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z5-ENG-FF.275 Fire Fighting Sprinkler Layout Plan Review & Approval 12 09-May-23 22-May-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z5-ENG-FF.280 Foam Tank Installation Layout Preparation & Submission 10 23-May-23 03-Jun-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z5-ENG-FF.285 Foam Tank Installation Layout Review & Approval 12 04-Jun-23 17-Jun-23 Foam Tank Installation Layout Review & Approval

JAH-Z5-ENG-FF.290 Fire Extinguishers Layout Plan Preparation & Submission 10 18-Jun-23 02-Jul-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z5-ENG-FF.295 Fire Extinguishers Layout Plan Review & Approval 12 03-Jul-23 16-Jul-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 03-Jul-23 22-Aug-23 22-Aug-23, VENTILATION SYSTEM


JAH-Z5-ENG-VS.180 Fan Layout Preparation & Submission 10 03-Jul-23 13-Jul-23 Fan Layout Preparation & Submission

JAH-Z5-ENG-VS.185 Fan Layout Review & Approval 12 15-Jul-23 27-Jul-23 Fan Layout Review & Approval

JAH-Z5-ENG-VS.190 Cable Route Shop Drawing Preparation & Submission 10 29-Jul-23 08-Aug-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z5-ENG-VS.195 Cable Route Shop Drawing Review & Approval 12 09-Aug-23 22-Aug-23 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 23-Aug-23 17-Sep-23 17-Sep-23, PUMPS INSTALLATION


JAH-Z5-ENG-PI.140 Sump Pump Diagram Preparation & Submission 10 23-Aug-23 03-Sep-23 Sump Pump Diagram Preparation & Submission

JAH-Z5-ENG-PI.145 Sump Pump Diagram Review & Approval 12 04-Sep-23 17-Sep-23 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 17-Jul-23 28-Oct-23 28-Oct-23, DUCTING SYSTEM


JAH-Z5-ENG-DCS.260 Duct Layout Drawing Preparation & Submission 10 17-Jul-23 27-Jul-23 Duct Layout Drawing Preparation & Submission

JAH-Z5-ENG-DCS.265 Duct Layout Drawing Review & Approval 12 29-Jul-23 10-Aug-23 Duct Layout Drawing Review & Approval

JAH-Z5-ENG-DCS.270 Diffuser Details Review & Approval 12 23-Aug-23 05-Sep-23 Diffuser Details Review & Approval

JAH-Z5-ENG-DCS.275 Dampers Details Preparation & Submission 10 06-Sep-23 17-Sep-23 Dampers Details Preparation & Submission

JAH-Z5-ENG-DCS.280 Dampers Details Review & Approval 12 18-Sep-23 02-Oct-23 Dampers Details Review & Approval

JAH-Z5-ENG-DCS.285 Sand Trap Louvre Layout Drawing Preparation & Submission 10 03-Oct-23 14-Oct-23 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z5-ENG-DCS.290 Sand Trap Louvre Layout Drawing Review & Approval 12 15-Oct-23 28-Oct-23 Sand Trap Louvre Layout Drawing Review & Approval

JAH-Z5-ENG-DCS.295 Diffuser Details Drawing Preparation & Submission 10 12-Aug-23 22-Aug-23 Diffuser Details Drawing Preparation & Submission

TUNNEL ELECTRICAL WORKS 210 10-Apr-23 18-Dec-23 18-Dec-23, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 10-Apr-23 22-Aug-23 22-Aug-23, CABLE TRAYS
JAH-Z5-ENG-CTR.300 Cable Tray Layout Drawing Preparation & Submission 10 10-Apr-23 20-Apr-23 Cable Tray Layout Drawing Preparation & Submission

JAH-Z5-ENG-CTR.305 Cable Tray Layout Drawing Review & Approval 12 25-Apr-23 08-May-23 Cable Tray Layout Drawing Review & Approval

JAH-Z5-ENG-CTR.310 Cable Tray Diversion Details Preparation & Submission 10 09-May-23 20-May-23 Cable Tray Diversion Details Preparation & Submission

JAH-Z5-ENG-CTR.315 Cable Tray Diversion Details Review & Approval 12 21-May-23 03-Jun-23 Cable Tray Diversion Details Review & Approval

JAH-Z5-ENG-CTR.320 Cable Tray Fixing Details Preparation & Submission 10 04-Jun-23 14-Jun-23 Cable Tray Fixing Details Preparation & Submission

JAH-Z5-ENG-CTR.325 Cable Tray Fixing Details Review & Submission 12 15-Jun-23 02-Jul-23 Cable Tray Fixing Details Review & Submission

JAH-Z5-ENG-CTR.330 Cable Tray Sections Preparation & Submission 10 03-Jul-23 13-Jul-23 Cable Tray Sections Preparation & Submission

JAH-Z5-ENG-CTR.335 Cable Tray Sections Review & Approval 12 15-Jul-23 27-Jul-23 Cable Tray Sections Review & Approval

JAH-Z5-ENG-CTR.340 PVC DuctsSections Preparation & Submission 10 29-Jul-23 08-Aug-23 PVC DuctsSections Preparation & Submission

JAH-Z5-ENG-CTR.345 PVC Sections Review & Approval 12 09-Aug-23 22-Aug-23 PVC Sections Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
348 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER CABLES 44 15-Jun-23 08-Aug-23 08-Aug-23, POWER CABLES
JAH-Z5-ENG-PC.180 Cable Route Shop Drawing Preparation & Submission 10 15-Jun-23 26-Jun-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z5-ENG-PC.185 Cable Route Shop Drawing Review & Approval 12 01-Jul-23 13-Jul-23 Cable Route Shop Drawing Review & Approval

JAH-Z5-ENG-PC.190 Junction Box Layout Plan Preparation & Submission 10 15-Jul-23 25-Jul-23 Junction Box Layout Plan Preparation & Submission

JAH-Z5-ENG-PC.195 Junction Box Layout Plan Review & Approval 12 26-Jul-23 08-Aug-23 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 124 01-Jul-23 22-Nov-23 22-Nov-23, ELECTRICAL INSTALLATIONS


JAH-Z5-ENG-ELI.300 Wiring Accessories Diagram Preparation & Submission 10 01-Jul-23 11-Jul-23 Wiring Accessories Diagram Preparation & Submission

JAH-Z5-ENG-ELI.305 Lighting Layout Drawing Preparation & Submission 10 26-Jul-23 06-Aug-23 Lighting Layout Drawing Preparation & Submission

JAH-Z5-ENG-ELI.310 Circuit Wiring Diagram Preparation & Submission 10 06-Sep-23 17-Sep-23 Circuit Wiring Diagram Preparation & Submission

JAH-Z5-ENG-ELI.315 Circuit Wiring Diagram Review & Approval 12 18-Sep-23 02-Oct-23 Circuit Wiring Diagram Review & Approval

JAH-Z5-ENG-ELI.320 SMDB Line Diagram Preparation & Submission 10 03-Oct-23 14-Oct-23 SMDB Line Diagram Preparation & Submission

JAH-Z5-ENG-ELI.325 SMDB Line Diagram Review & Approval 12 15-Oct-23 28-Oct-23 SMDB Line Diagram Review & Approval

JAH-Z5-ENG-ELI.330 Distribution Board Line Diagram Preparation & Submission 10 29-Oct-23 08-Nov-23 Distribution Board Line Diagram Preparation & Submission

JAH-Z5-ENG-ELI.335 Lighting Layout Drawing Review & Approval 12 23-Aug-23 05-Sep-23 Lighting Layout Drawing Review & Approval

JAH-Z5-ENG-ELI.340 Wiring Accessories Diagram Review & Approval 12 12-Jul-23 25-Jul-23 Wiring Accessories Diagram Review & Approval

JAH-Z5-ENG-ELI.345 Distribution Board Line Diagram Review & Approval 12 09-Nov-23 22-Nov-23 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 17-Jul-23 18-Dec-23 18-Dec-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 17-Jul-23 18-Dec-23 18-Dec-23, FIRE DETECTION AND ALARM SYSTEM
JAH-Z5-ENG-FD.340 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 17-Jul-23 27-Jul-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.345 Fire Alarm Control Panel Layout Drawing Review & Approval 12 29-Jul-23 10-Aug-23 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z5-ENG-FD.350 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 12-Aug-23 22-Aug-23 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.355 Fire Alarm Speaker Layout Drawing Review & Approval 12 23-Aug-23 05-Sep-23 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z5-ENG-FD.360 Fire Alarm sounder Layout Drawing Preparation & Submission 10 06-Sep-23 17-Sep-23 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.365 Fire Alarm sounder Layout Drawing Review & Approval 12 18-Sep-23 02-Oct-23 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z5-ENG-FD.370 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 03-Oct-23 14-Oct-23 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.375 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 15-Oct-23 28-Oct-23 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z5-ENG-FD.380 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 29-Oct-23 08-Nov-23 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.385 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 09-Nov-23 22-Nov-23 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z5-ENG-FD.390 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 23-Nov-23 04-Dec-23 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z5-ENG-FD.395 Double Action Manual Call Point Layout Drawing Review & Approval 12 05-Dec-23 18-Dec-23 Double Action Manual Call Point Layout Drawing Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 29-Jul-23 04-Dec-23 04-Dec-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z5-ENG-TPH.3008 core UTP Cable Laying 14 29-Jul-23 13-Aug-23 8 core UTP Cable Laying

JAH-Z5-ENG-TPH.305Junction box Installation 8 14-Aug-23 22-Aug-23 Junction box Installation

JAH-Z5-ENG-TPH.310Emergency Telephone Installation 14 23-Aug-23 07-Sep-23 Emergency Telephone Installation

JAH-Z5-ENG-TPH.315Connection and Testing 8 09-Sep-23 17-Sep-23 Connection and Testing

JAH-Z5-ENG-TPH.3208 Core UTP Cable Layout Drawing Preparation & Submission 10 18-Sep-23 30-Sep-23 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-TPH.3258 Core UTP Cable Layout Drawing Review & Approval 12 01-Oct-23 14-Oct-23 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z5-ENG-TPH.330Junction box Layout Drawing Preparation & Submission 10 15-Oct-23 25-Oct-23 Junction box Layout Drawing Preparation & Submission

JAH-Z5-ENG-TPH.335Junction box Layout Drawing Review & Approval 12 26-Oct-23 08-Nov-23 Junction box Layout Drawing Review & Approval

JAH-Z5-ENG-TPH.340Telephone Location Layout Preparation & Submission 10 09-Nov-23 20-Nov-23 Telephone Location Layout Preparation & Submission

JAH-Z5-ENG-TPH.345Telephone Location Layout Review & Approval 12 21-Nov-23 04-Dec-23 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 14-Aug-23 30-Oct-23 30-Oct-23, PUBLIC ADDRESS


JAH-Z5-ENG-PUBA.220
Cable Layout Drawing Preparation & Submission 10 14-Aug-23 24-Aug-23 Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-PUBA.225
Cable Layout Drawing Review & Approval 12 26-Aug-23 07-Sep-23 Cable Layout Drawing Review & Approval

JAH-Z5-ENG-PUBA.230
Voice alarm control panel Drawing Preparation & Submission 10 09-Sep-23 19-Sep-23 Voice alarm control panel Drawing Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
349 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ENG-PUBA.235
Voice alarm control panel Drawing Review & Approval 12 20-Sep-23 04-Oct-23 Voice alarm control panel Drawing Review & Approval

JAH-Z5-ENG-PUBA.240
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 05-Oct-23 16-Oct-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z5-ENG-PUBA.245
Voice Evacuation Horn Speaker Drawing Preparation & Submission 12 17-Oct-23 30-Oct-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

VIDEO SURVEILLANCE 44 26-Aug-23 16-Oct-23 16-Oct-23, VIDEO SURVEILLANCE


JAH-Z5-ENG-VID.180Cable Layout Drawing Preparation & Submission 10 26-Aug-23 05-Sep-23 Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-VID.185Cable Layout Drawing Review & Approval 12 06-Sep-23 19-Sep-23 Cable Layout Drawing Review & Approval

JAH-Z5-ENG-VID.190Camera Layout Drawing Preparation & Submission 10 20-Sep-23 02-Oct-23 Camera Layout Drawing Preparation & Submission

JAH-Z5-ENG-VID.195Camera Layout Drawing Review & Approval 12 03-Oct-23 16-Oct-23 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 06-Sep-23 28-Oct-23 28-Oct-23, SACADA SYSTEM


JAH-Z5-ENG-SCA.180Cable Layout Drawing Preparation & Submission 10 06-Sep-23 17-Sep-23 Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-SCA.185Cable Layout Drawing Review & Approval 12 18-Sep-23 02-Oct-23 Cable Layout Drawing Review & Approval

JAH-Z5-ENG-SCA.190Installation Layout Drawing Preparation & Submission 10 03-Oct-23 14-Oct-23 Installation Layout Drawing Preparation & Submission

JAH-Z5-ENG-SCA.195Installation Layout Drawing Review & Approval 12 15-Oct-23 28-Oct-23 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 18-Sep-23 08-Nov-23 08-Nov-23, RADIO RE-BROADCASTING SYSTEM


JAH-Z5-ENG-RDO.180Cable Layout Drawing Preparation & Submission 10 18-Sep-23 30-Sep-23 Cable Layout Drawing Preparation & Submission

JAH-Z5-ENG-RDO.185Cable Layout Drawing Review & Approval 12 01-Oct-23 14-Oct-23 Cable Layout Drawing Review & Approval

JAH-Z5-ENG-RDO.190Installation Layout Drawing Preparation & Submission 10 15-Oct-23 25-Oct-23 Installation Layout Drawing Preparation & Submission

JAH-Z5-ENG-RDO.195Installation Layout Drawing Review & Approval 12 26-Oct-23 08-Nov-23 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 25-Apr-23 18-May-23 18-May-23, TUNNEL PLUMBING WORKS


JAH-Z5-ENG-PLM.140 Plumbing Services Shop Drawings Preparation & Submission 9 25-Apr-23 04-May-23 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z5-ENG-PLM.145 Plumbing Shop Drawings Review & Approval 12 06-May-23 18-May-23 Plumbing Shop Drawings Review & Approval

PROCUREMENT 339 27-Apr-23 03-Jun-24 03-Jun-24, PROCUREMENT


RAM275 Completion Procurment for Zone 5 0 03-Jun-24* Completion Procurment for Zone 5

CIVIL/STRUCTURAL 145 14-May-23 02-Nov-23 02-Nov-23, CIVIL/STRUCTURAL


JAH-Z5-PRO-CSM.180 Request for Quotation 10 14-May-23 24-May-23 Request for Quotation

JAH-Z5-PRO-CSM.185 Issue Purchase Order 15 25-May-23 11-Jun-23 Issue Purchase Order

JAH-Z5-PRO-CSM.188 Staging Time 30 12-Jun-23 19-Jul-23 Staging Time

JAH-Z5-PRO-CSM.190 Material Delivery 90 20-Jul-23 02-Nov-23 Material Delivery

UTILITIES 305 06-Jun-23 03-Jun-24 03-Jun-24, UTILITIES


WET UTILITIES 238 06-Jun-23 13-Mar-24 13-Mar-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 145 06-Jun-23 26-Nov-23 26-Nov-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 06-Jun-23 26-Nov-23 26-Nov-23, DI PIPES
JAH-Z5-PR-WU-PW.100
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.105
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.110
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.140
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

HDPE PIPES 145 06-Jun-23 26-Nov-23 26-Nov-23, HDPE PIPES


JAH-Z5-PR-WU-PW.125
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.145
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.165
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.225
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

GRP PIPES 145 06-Jun-23 26-Nov-23 26-Nov-23, GRP PIPES


JAH-Z5-PR-WU-PW.115
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.120
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.150
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.200
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

DI & GRP FITTING 145 06-Jun-23 26-Nov-23 26-Nov-23, DI & GRP FITTING

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
350 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-PR-WU-PW.135
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.155
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.170
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.230
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

GATE VALVE 145 06-Jun-23 26-Nov-23 26-Nov-23, GATE VALVE


JAH-Z5-PR-WU-PW.195
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.205
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.235
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.260
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

BUTTERFLAY VALVE 145 06-Jun-23 26-Nov-23 26-Nov-23, BUTTERFLAY VALVE


JAH-Z5-PR-WU-PW.190
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.210
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.240
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.265
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

WATER METER 145 06-Jun-23 26-Nov-23 26-Nov-23, WATER METER


JAH-Z5-PR-WU-PW.130
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.160
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.175
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.245
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

AIR RELASE VALVE 145 06-Jun-23 26-Nov-23 26-Nov-23, AIR RELASE VALVE
JAH-Z5-PR-WU-PW.185
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.215
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.250
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.270
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

WASHOUT VALVE 145 06-Jun-23 26-Nov-23 26-Nov-23, WASHOUT VALVE


JAH-Z5-PR-WU-PW.180
Request for Quotation 10 06-Jun-23 17-Jun-23 Request for Quotation

JAH-Z5-PR-WU-PW.220
Issue Purchase Order 15 18-Jun-23 08-Jul-23 Issue Purchase Order

JAH-Z5-PR-WU-PW.255
Staging time 30 09-Jul-23 12-Aug-23 Staging time

JAH-Z5-PR-WU-PW.275
Material Delivery 90 13-Aug-23 26-Nov-23 Material Delivery

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 145 05-Jul-23 21-Dec-23 21-Dec-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 05-Jul-23 21-Dec-23 21-Dec-23, DI PIPES
JAH-Z5-PR-WU-GWD.100
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.105
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.110
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.135
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

HDPE PIPES 145 05-Jul-23 21-Dec-23 21-Dec-23, HDPE PIPES


JAH-Z5-PR-WU-GWD.125
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.140
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.155
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.210
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

GRP PIPES 145 05-Jul-23 21-Dec-23 21-Dec-23, GRP PIPES


JAH-Z5-PR-WU-GWD.115
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.120
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.145
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.185
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

DI & GRP FITTING 145 05-Jul-23 21-Dec-23 21-Dec-23, DI & GRP FITTING

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
351 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-PR-WU-GWD.130
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.150
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.160
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.215
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

GATE VALVE 145 05-Jul-23 21-Dec-23 21-Dec-23, GATE VALVE


JAH-Z5-PR-WU-GWD.180
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.190
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.220
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.240
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

BUTTERFLAY VALVE 145 05-Jul-23 21-Dec-23 21-Dec-23, BUTTERFLAY VALVE


JAH-Z5-PR-WU-GWD.175
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.195
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.225
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.245
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

AIR RELASE VALVE 145 05-Jul-23 21-Dec-23 21-Dec-23, AIR RELASE VALVE
JAH-Z5-PR-WU-GWD.170
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.200
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.230
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.250
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

WASEHOUT VALVE 145 05-Jul-23 21-Dec-23 21-Dec-23, WASEHOUT VALVE


JAH-Z5-PR-WU-GWD.165
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-WU-GWD.205
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-GWD.235
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-WU-GWD.255
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 145 31-Jul-23 16-Jan-24 16-Jan-24, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 31-Jul-23 16-Jan-24 16-Jan-24, HDPE PIPES
JAH-Z5-PR-WU-IRR.100
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.105
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.110
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.155
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

GATE VALVE 145 31-Jul-23 16-Jan-24 16-Jan-24, GATE VALVE


JAH-Z5-PR-WU-IRR.130
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.135
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.160
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.190
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

BUTTERFLAY VALVE 145 31-Jul-23 16-Jan-24 16-Jan-24, BUTTERFLAY VALVE


JAH-Z5-PR-WU-IRR.125
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.140
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.165
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.195
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

AIR RELASE VALVE 145 31-Jul-23 16-Jan-24 16-Jan-24, AIR RELASE VALVE
JAH-Z5-PR-WU-IRR.120
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.145
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.170
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.200
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

WASEHOUT VALVE 145 31-Jul-23 16-Jan-24 16-Jan-24, WASEHOUT VALVE

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
352 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-PR-WU-IRR.115
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.150
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.175
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.205
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

FIRE HYDRANT 145 31-Jul-23 16-Jan-24 16-Jan-24, FIRE HYDRANT


JAH-Z5-PR-WU-IRR.180
Request for Quotation 10 31-Jul-23 10-Aug-23 Request for Quotation

JAH-Z5-PR-WU-IRR.185
Issue Purchase Order 15 12-Aug-23 28-Aug-23 Issue Purchase Order

JAH-Z5-PR-WU-IRR.210
Staging time 30 29-Aug-23 03-Oct-23 Staging time

JAH-Z5-PR-WU-IRR.215
Material Delivery 90 04-Oct-23 16-Jan-24 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 145 26-Aug-23 11-Feb-24 11-Feb-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 26-Aug-23 11-Feb-24 11-Feb-24, MILD STEEL PIPE
JAH-Z5-PR-WU-CWS.105
Request for Quotation 10 26-Aug-23 05-Sep-23 Request for Quotation

JAH-Z5-PR-WU-CWS.110
Issue Purchase Order 15 06-Sep-23 24-Sep-23 Issue Purchase Order

JAH-Z5-PR-WU-CWS.120
Staging time 30 25-Sep-23 29-Oct-23 Staging time

JAH-Z5-PR-WU-CWS.130
Material Delivery 90 30-Oct-23 11-Feb-24 Material Delivery

MILD STEEL FITTING 145 26-Aug-23 11-Feb-24 11-Feb-24, MILD STEEL FITTING
JAH-Z5-PR-WU-CWS.100
Request for Quotation 10 26-Aug-23 05-Sep-23 Request for Quotation

JAH-Z5-PR-WU-CWS.115
Issue Purchase Order 15 06-Sep-23 24-Sep-23 Issue Purchase Order

JAH-Z5-PR-WU-CWS.125
Staging time 30 25-Sep-23 29-Oct-23 Staging time

JAH-Z5-PR-WU-CWS.135
Material Delivery 90 30-Oct-23 11-Feb-24 Material Delivery

GATE VALVE 145 26-Aug-23 11-Feb-24 11-Feb-24, GATE VALVE


JAH-Z5-PR-WU-CWS.140
Request for Quotation 10 26-Aug-23 05-Sep-23 Request for Quotation

JAH-Z5-PR-WU-CWS.145
Issue Purchase Order 15 06-Sep-23 24-Sep-23 Issue Purchase Order

JAH-Z5-PR-WU-CWS.150
Staging time 30 25-Sep-23 29-Oct-23 Staging time

JAH-Z5-PR-WU-CWS.155
Material Delivery 90 30-Oct-23 11-Feb-24 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE
JAH-Z5-PR-WU-AWC.160
Issue Purchase Order 15 09-Oct-23 25-Oct-23 Issue Purchase Order

JAH-Z5-PR-WU-AWC.165
Staging time 30 26-Oct-23 29-Nov-23 Staging time

JAH-Z5-PR-WU-AWC.170
Material Delivery 90 30-Nov-23 13-Mar-24 Material Delivery

JAH-Z5-PR-WU-AWC.175
Request for Quotation 10 27-Sep-23 08-Oct-23 Request for Quotation

DRY UTILITIES 283 05-Jul-23 03-Jun-24 03-Jun-24, DRY UTILITIES


POWER 251 05-Jul-23 27-Apr-24 27-Apr-24, POWER
HIGH VOLTAGE 110 KV NETWORK 145 05-Jul-23 21-Dec-23 21-Dec-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z5-PR-DU-PWR.100
Request for Quotation 10 05-Jul-23 16-Jul-23 Request for Quotation

JAH-Z5-PR-DU-PWR.105
Issue Purchase Order 15 17-Jul-23 02-Aug-23 Issue Purchase Order

JAH-Z5-PR-DU-PWR.115
Staging time 30 03-Aug-23 06-Sep-23 Staging time

JAH-Z5-PR-DU-PWR.140
Material Delivery 90 07-Sep-23 21-Dec-23 Material Delivery

MEDIUM VOLTAGE 13.8 KV NETWORK 145 03-Aug-23 20-Jan-24 20-Jan-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z5-PR-DU-PWR.110
Request for Quotation 10 03-Aug-23 14-Aug-23 Request for Quotation

JAH-Z5-PR-DU-PWR.120
Issue Purchase Order 15 15-Aug-23 31-Aug-23 Issue Purchase Order

JAH-Z5-PR-DU-PWR.130
Staging time 30 02-Sep-23 07-Oct-23 Staging time

JAH-Z5-PR-DU-PWR.150
Material Delivery 90 08-Oct-23 20-Jan-24 Material Delivery

LOW VOLTAGE NETWORK 145 04-Sep-23 20-Feb-24 20-Feb-24, LOW VOLTAGE NETWORK
JAH-Z5-PR-DU-PWR.125
Request for Quotation 10 04-Sep-23 14-Sep-23 Request for Quotation

JAH-Z5-PR-DU-PWR.135
Issue Purchase Order 15 16-Sep-23 03-Oct-23 Issue Purchase Order

JAH-Z5-PR-DU-PWR.145
Staging time 30 04-Oct-23 07-Nov-23 Staging time

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
353 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-PR-DU-PWR.160
Material Delivery 90 08-Nov-23 20-Feb-24 Material Delivery

ELECTRICAL DISTRIBUTION SYSTEM 145 01-Oct-23 17-Mar-24 17-Mar-24, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z5-PR-DU-PWR.155
Request for Quotation 10 01-Oct-23 11-Oct-23 Request for Quotation

JAH-Z5-PR-DU-PWR.165
Issue Purchase Order 15 12-Oct-23 29-Oct-23 Issue Purchase Order

JAH-Z5-PR-DU-PWR.170
Staging time 30 30-Oct-23 03-Dec-23 Staging time

JAH-Z5-PR-DU-PWR.175
Material Delivery 90 04-Dec-23 17-Mar-24 Material Delivery

LIGHTING SYSTEM 145 07-Nov-23 27-Apr-24 27-Apr-24, LIGHTING SYSTEM


JAH-Z5-PR-DU-PWR.645
Request for Quotation 10 07-Nov-23 18-Nov-23 Request for Quotation

JAH-Z5-PR-DU-PWR.650
Issue Purchase Order 15 19-Nov-23 05-Dec-23 Issue Purchase Order

JAH-Z5-PR-DU-PWR.655
Material Delivery 90 10-Jan-24 27-Apr-24 Material Delivery

JAH-Z5-PR-DU-PWR.660
Staging time 30 06-Dec-23 09-Jan-24 Staging time

LOW CURRENT 145 14-Dec-23 03-Jun-24 03-Jun-24, LOW CURRENT


TELECOM SERVICES 145 14-Dec-23 03-Jun-24 03-Jun-24, TELECOM SERVICES
JAH-Z5-PR-DU-LC.100Request for Quotation 10 14-Dec-23 25-Dec-23 Request for Quotation

JAH-Z5-PR-DU-LC.105Issue Purchase Order 15 26-Dec-23 11-Jan-24 Issue Purchase Order

JAH-Z5-PR-DU-LC.110Staging time 30 13-Jan-24 15-Feb-24 Staging time

JAH-Z5-PR-DU-LC.115Material Delivery 90 17-Feb-24 03-Jun-24 Material Delivery

MEP 147 27-Apr-23 19-Oct-23 19-Oct-23, MEP


JAH-Z5-PR-DU-MEP.100 Request for Quotation 10 27-Apr-23 08-May-23 Request for Quotation

JAH-Z5-PR-DU-MEP.105 Issue Purchase Order 17 09-May-23 28-May-23 Issue Purchase Order

JAH-Z5-PR-DU-MEP.110 Staging Time 30 29-May-23 05-Jul-23 Staging Time

JAH-Z5-PR-DU-MEP.115 Material Delivery 90 06-Jul-23 19-Oct-23 Material Delivery

ARCHITECTURAL 115 08-Jun-23 24-Oct-23 24-Oct-23, ARCHITECTURAL


JAH-Z5-PR-DU-ARC.100Request for Quotation 10 08-Jun-23 19-Jun-23 Request for Quotation

JAH-Z5-PR-DU-ARC.105Issue Purchase Order 15 20-Jun-23 10-Jul-23 Issue Purchase Order

JAH-Z5-PR-DU-ARC.110Staging Time 30 11-Jul-23 14-Aug-23 Staging Time

JAH-Z5-PR-DU-ARC.115Material Delivery 60 15-Aug-23 24-Oct-23 Material Delivery

CONSTRUCTION 927 11-Aug-22 A 27-Dec-25 27-Dec-25, CONSTRUCTION


GENERAL SITE ARRANGEMENT 123 11-Aug-22 A 18-Jan-23 18-Jan-23, GENERAL SITE ARRANGEMENT
SITE PREPARATION 123 11-Aug-22 A 18-Jan-23 18-Jan-23, SITE PREPARATION
JAH-Z5-CON-GA-SP.160Site Clearing & Grubbing / Demolition of Obstacles 15 11-Aug-22 A 15-Dec-22 Site Clearing & Grubbing / Demolition of Obstacles

JAH-Z5-CON-GA-SP.165Disposal /Removal of Unnecessary Objects from Site 8 23-Aug-22 A 15-Dec-22 Disposal /Removal of Unnecessary Objects from Site

JAH-Z5-CON-GA-SP.170Relocation of Exisiting Utilities 30 15-Dec-22 18-Jan-23 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 62 14-Aug-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION


JAH-Z5-CON-GTI.100 Borehole Layout Preparation & Submission 15 14-Aug-22 A 18-Aug-22 A Borehole Layout Preparation & Submission

JAH-Z5-CON-GTI.105 Borehole Layout Review & Approval 7 17-Aug-22 A 21-Aug-22 A Borehole Layout Review & Approval

JAH-Z5-CON-GTI.110 Drilling Boreholes 25 22-Aug-22 A 23-Aug-22 A Drilling Boreholes

JAH-Z5-CON-GTI.115 Issuance of Geo-Technical Investigation Report 15 23-Aug-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 287 04-Sep-22 A 13-Apr-24 13-Apr-24, EXCAVATION & DEWATERING
JAH-Z5-CON-DE.102 Dewatering @Sta. 1+753 ~ 1+853 162 06-Oct-22 A 05-Sep-23 Dewatering @Sta. 1+753 ~ 1+853

JAH-Z5-CON-DE.107 Dewatering @Sta. 1+853 ~ 1+953 225 07-May-23 28-Jan-24 Dewatering @Sta. 1+853 ~ 1+953

JAH-Z5-CON-DE.113 Dewatering @Sta. 1+953 ~ 2+053 235 30-May-23 03-Mar-24 Dewatering @Sta. 1+953 ~ 2+053

JAH-Z5-CON-DE.118 Dewatering @Sta. 2+053 ~ 2+157 249 20-Jun-23 13-Apr-24 Dewatering @Sta. 2+053 ~ 2+157

JAH-Z5-CON-EX.100 Excavation & Shoring System @Sta. 1+753 ~ 1+853 30 04-Sep-22 A 17-Apr-23 Excavation & Shoring System @Sta. 1+753 ~ 1+853

JAH-Z5-CON-EX.105 Excavation & Shoring System @Sta. 1+853 ~ 1+953 20 07-May-23 29-May-23 Excavation & Shoring System @Sta. 1+853 ~ 1+953

JAH-Z5-CON-EX.110 Excavation & Shoring System @Sta. 1+953 ~ 2+053 18 30-May-23 19-Jun-23 Excavation & Shoring System @Sta. 1+953 ~ 2+053

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
354 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-CON-EX.115 Excavation & Shoring System @Sta. 2+053 ~ 2+157 20 20-Jun-23 16-Jul-23 Excavation & Shoring System @Sta. 2+053 ~ 2+157

SOIL IMPROVEMENT 79 18-Apr-23 25-Jul-23 25-Jul-23, SOIL IMPROVEMENT


JAH-CON-Z5-SIMP.101 Soil Improvement @Sta. 1+753 ~ 1+853 8 18-Apr-23 30-Apr-23 Soil Improvement @Sta. 1+753 ~ 1+853

JAH-CON-Z5-SIMP.106 Soil Improvement@Sta. 1+853 ~ 1+953 8 30-May-23 07-Jun-23 Soil Improvement@Sta. 1+853 ~ 1+953

JAH-CON-Z5-SIMP.111 Soil Improvement @Sta. 1+953 ~ 2+053 8 20-Jun-23 02-Jul-23 Soil Improvement @Sta. 1+953 ~ 2+053

JAH-CON-Z5-SIMP.116 Soil Improvement @Sta. 2+053 ~ 2+157 8 17-Jul-23 25-Jul-23 Soil Improvement @Sta. 2+053 ~ 2+157

STRUCTURAL WORKS 428 01-Nov-23 23-Mar-25 23-Mar-25, STRUCTURAL WORKS


STA. 1+753.979~ 1+773.979 168 01-Nov-23 18-May-24 18-May-24, STA. 1+753.979~ 1+773.979
BASE SLAB 34 01-Nov-23 10-Dec-23 10-Dec-23, BASE SLAB
JAH-Z5-ST-S1-BS.100 Lean Concrete for Base Slab 1 01-Nov-23 01-Nov-23 Lean Concrete for Base Slab

JAH-Z5-ST-S1-BS.105 Waterproofing for Lean Concrete 1 02-Nov-23 02-Nov-23 Waterproofing for Lean Concrete

JAH-Z5-ST-S1-BS.110 Base Slab Rebar Installation 8 04-Nov-23 12-Nov-23 Base Slab Rebar Installation

JAH-Z5-ST-S1-BS.115 Base Slab Formwork Installation 7 13-Nov-23 20-Nov-23 Base Slab Formwork Installation

JAH-Z5-ST-S1-BS.120 Base Slab Concrete Casting 1 21-Nov-23 21-Nov-23 Base Slab Concrete Casting

JAH-Z5-ST-S1-BS.122 Curing work 7 22-Nov-23 29-Nov-23 Curing work

JAH-Z5-ST-S1-BS.125 Base Slab Formwork Removel 2 30-Nov-23 02-Dec-23 Base Slab Formwork Removel

JAH-Z5-ST-S1-BS.130 Curing work 7 03-Dec-23 10-Dec-23 Curing work

COLUMNS 23 03-Dec-23 28-Dec-23 28-Dec-23, COLUMNS


JAH-Z5-ST-S1-CL.100 Column Rebar Installation 8 03-Dec-23 11-Dec-23 Column Rebar Installation

JAH-Z5-ST-S1-CL.105 Column Formwork Installation 7 12-Dec-23 19-Dec-23 Column Formwork Installation

JAH-Z5-ST-S1-CL.110 Column Concrete Casting 1 20-Dec-23 20-Dec-23 Column Concrete Casting

JAH-Z5-ST-S1-CL.115 Form Work Removal and Curing 7 21-Dec-23 28-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 37 03-Dec-23 14-Jan-24 14-Jan-24, TUNNEL WALLS


JAH-Z5-ST-S1-TW.100 Tunnel Walls Rebar Installation 8 03-Dec-23 11-Dec-23 Tunnel Walls Rebar Installation

JAH-Z5-ST-S1-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 03-Dec-23 11-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S1-TW.105 Tunnel Formwork Installation 7 12-Dec-23 19-Dec-23 Tunnel Formwork Installation

JAH-Z5-ST-S1-TW.110 Tunnel Walls Concrete Casting 1 20-Dec-23 20-Dec-23 Tunnel Walls Concrete Casting

JAH-Z5-ST-S1-TW.112 Curing work 7 21-Dec-23 28-Dec-23 Curing work

JAH-Z5-ST-S1-TW.120 Tunnel Walls Formwork Removel 2 30-Dec-23 31-Dec-23 Tunnel Walls Formwork Removel

JAH-Z5-ST-S1-TW.125 Tunnel Wall Waterproofing 12 01-Jan-24 14-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 01-Jan-24 04-Feb-24 04-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S1-MS.090 Middle Slab Scaffold and Formwork Installation 5 01-Jan-24 06-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S1-MS.100 Middle Slab Rebar Installation 8 07-Jan-24 15-Jan-24 Middle Slab Rebar Installation

JAH-Z5-ST-S1-MS.105 Middle Slab Vertical Formwork Installation 7 16-Jan-24 23-Jan-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S1-MS.110 Middle Slab Concrete Casting 1 24-Jan-24 24-Jan-24 Middle Slab Concrete Casting

JAH-Z5-ST-S1-MS.115 Curing work 7 25-Jan-24 01-Feb-24 Curing work

JAH-Z5-ST-S1-MS.120 Middle Slab Formwork Removel 2 03-Feb-24 04-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 05-Feb-24 04-Mar-24 04-Mar-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S1-UCW.100Utility Culvert Walls Rebar Installation 8 05-Feb-24 13-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S1-UCW.105Utility Culvert Walls Formwork Installation 7 14-Feb-24 21-Feb-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S1-UCW.110Utility Culvert Walls Concrete Casting 1 22-Feb-24 22-Feb-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S1-UCW.112Curing work 7 24-Feb-24 02-Mar-24 Curing work

JAH-Z5-ST-S1-UCW.115Utility Culvert Walls Walls Formwork Removel 2 03-Mar-24 04-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 05-Mar-24 20-Apr-24 20-Apr-24, TOP SLAB


JAH-Z5-ST-S1-TS.090 Top Slab Formwork Installation 7 05-Mar-24 12-Mar-24 Top Slab Formwork Installation

JAH-Z5-ST-S1-TS.100 Top Slab Rebar Installation 8 13-Mar-24 21-Mar-24 Top Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
355 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S1-TS.110 Top Slab Concrete Casting 1 23-Mar-24 23-Mar-24 Top Slab Concrete Casting

JAH-Z5-ST-S1-TS.112 Curing work 7 24-Mar-24 31-Mar-24 Curing work

JAH-Z5-ST-S1-TS.115 Top Slab Formwork Removel 2 01-Apr-24 02-Apr-24 Top Slab Formwork Removel

JAH-Z5-ST-S1-TS.120 Waterproofing for Top Slab 12 03-Apr-24 20-Apr-24 Waterproofing for Top Slab

FINISHING WORK 24 21-Apr-24 18-May-24 18-May-24, FINISHING WORK


JAH-Z5-ST-S1-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 21-Apr-24 28-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S1-FW.105 Plain Concrete Casting 1 29-Apr-24 29-Apr-24 Plain Concrete Casting

JAH-Z5-ST-S1-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 30-Apr-24 30-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S1-FW.112 Curing work 7 01-May-24 08-May-24 Curing work

JAH-Z5-ST-S1-FW.115 Concrete Protective coating 8 09-May-24 18-May-24 Concrete Protective coating

STA. 1+773.979 ~ 1+793.979 175 13-Nov-23 06-Jun-24 06-Jun-24, STA. 1+773.979 ~ 1+793.979
BASE SLAB 27 13-Nov-23 13-Dec-23 13-Dec-23, BASE SLAB
JAH-Z5-ST-S2-BS.100 Lean Concrete for Base Slab 1 13-Nov-23 13-Nov-23 Lean Concrete for Base Slab

JAH-Z5-ST-S2-BS.105 Waterproofing for Lean Concrete 1 14-Nov-23 14-Nov-23 Waterproofing for Lean Concrete

JAH-Z5-ST-S2-BS.110 Base Slab Rebar Installation 8 15-Nov-23 23-Nov-23 Base Slab Rebar Installation

JAH-Z5-ST-S2-BS.115 Base Slab Formwork Installation 7 25-Nov-23 02-Dec-23 Base Slab Formwork Installation

JAH-Z5-ST-S2-BS.120 Base Slab Concrete Casting 1 03-Dec-23 03-Dec-23 Base Slab Concrete Casting

JAH-Z5-ST-S2-BS.122 Curing work 7 04-Dec-23 11-Dec-23 Curing work

JAH-Z5-ST-S2-BS.125 Base Slab Formwork Removel 2 12-Dec-23 13-Dec-23 Base Slab Formwork Removel

COLUMNS 23 14-Dec-23 09-Jan-24 09-Jan-24, COLUMNS


JAH-Z5-ST-S2-CL.100 Column Rebar Installation 8 14-Dec-23 23-Dec-23 Column Rebar Installation

JAH-Z5-ST-S2-CL.105 Column Formwork Installation 7 24-Dec-23 31-Dec-23 Column Formwork Installation

JAH-Z5-ST-S2-CL.110 Column Concrete Casting 1 01-Jan-24 01-Jan-24 Column Concrete Casting

JAH-Z5-ST-S2-CL.115 Form Work Removal and Curing 7 02-Jan-24 09-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 14-Dec-23 25-Jan-24 25-Jan-24, TUNNEL WALLS


JAH-Z5-ST-S2-TW.100 Tunnel Walls Rebar Installation 8 14-Dec-23 23-Dec-23 Tunnel Walls Rebar Installation

JAH-Z5-ST-S2-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 14-Dec-23 23-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S2-TW.105 Tunnel Formwork Installation 7 24-Dec-23 31-Dec-23 Tunnel Formwork Installation

JAH-Z5-ST-S2-TW.110 Tunnel Walls Concrete Casting 1 01-Jan-24 01-Jan-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S2-TW.112 Curing work 7 02-Jan-24 09-Jan-24 Curing work

JAH-Z5-ST-S2-TW.120 Tunnel Walls Formwork Removel 2 10-Jan-24 11-Jan-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S2-TW.125 Tunnel Wall Waterproofing 12 13-Jan-24 25-Jan-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 13-Jan-24 15-Feb-24 15-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S2-MS.090 Middle Slab Scaffold and Formwork Installation 5 13-Jan-24 17-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S2-MS.100 Middle Slab Rebar Installation 8 18-Jan-24 27-Jan-24 Middle Slab Rebar Installation

JAH-Z5-ST-S2-MS.105 Middle Slab Vertical Formwork Installation 7 28-Jan-24 04-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S2-MS.110 Middle Slab Concrete Casting 1 05-Feb-24 05-Feb-24 Middle Slab Concrete Casting

JAH-Z5-ST-S2-MS.115 Curing work 7 06-Feb-24 13-Feb-24 Curing work

JAH-Z5-ST-S2-MS.120 Middle Slab Formwork Removel 2 14-Feb-24 15-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 17-Feb-24 16-Mar-24 16-Mar-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S2-UCW.100Utility Culvert Walls Rebar Installation 8 17-Feb-24 25-Feb-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S2-UCW.105Utility Culvert Walls Formwork Installation 7 26-Feb-24 04-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S2-UCW.110Utility Culvert Walls Concrete Casting 1 05-Mar-24 05-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S2-UCW.112Curing work 7 06-Mar-24 13-Mar-24 Curing work

JAH-Z5-ST-S2-UCW.115Utility Culvert Walls Walls Formwork Removel 2 14-Mar-24 16-Mar-24 Utility Culvert Walls Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
356 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TOP SLAB 37 17-Mar-24 01-May-24 01-May-24, TOP SLAB
JAH-Z5-ST-S2-TS.100 Top Slab Rebar Installation 8 17-Mar-24 25-Mar-24 Top Slab Rebar Installation

JAH-Z5-ST-S2-TS.105 Top Slab Formwork Installation 7 26-Mar-24 02-Apr-24 Top Slab Formwork Installation

JAH-Z5-ST-S2-TS.110 Top Slab Concrete Casting 1 03-Apr-24 03-Apr-24 Top Slab Concrete Casting

JAH-Z5-ST-S2-TS.112 Curing work 7 04-Apr-24 15-Apr-24 Curing work

JAH-Z5-ST-S2-TS.115 Top Slab Formwork Removel 2 16-Apr-24 17-Apr-24 Top Slab Formwork Removel

JAH-Z5-ST-S2-TS.120 Waterproofing for Top Slab 12 18-Apr-24 01-May-24 Waterproofing for Top Slab

FINISHING WORK 31 02-May-24 06-Jun-24 06-Jun-24, FINISHING WORK


JAH-Z5-ST-S2-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 02-May-24 09-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S2-FW.105 Plain Concrete Casting 1 19-May-24 19-May-24 Plain Concrete Casting

JAH-Z5-ST-S2-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 20-May-24 20-May-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S2-FW.112 Curing work 7 21-May-24 28-May-24 Curing work

JAH-Z5-ST-S2-FW.115 Concrete Protective coating 8 29-May-24 06-Jun-24 Concrete Protective coating

STA. 1+793.979~ 1+813.979 181 25-Nov-23 30-Jun-24 30-Jun-24, STA. 1+793.979~ 1+813.979
BASE SLAB 27 25-Nov-23 25-Dec-23 25-Dec-23, BASE SLAB
JAH-Z5-ST-S3-BS.100 Lean Concrete for Base Slab 1 25-Nov-23 25-Nov-23 Lean Concrete for Base Slab

JAH-Z5-ST-S3-BS.105 Waterproofing for Lean Concrete 1 26-Nov-23 26-Nov-23 Waterproofing for Lean Concrete

JAH-Z5-ST-S3-BS.110 Base Slab Rebar Installation 8 27-Nov-23 05-Dec-23 Base Slab Rebar Installation

JAH-Z5-ST-S3-BS.115 Base Slab Formwork Installation 7 06-Dec-23 13-Dec-23 Base Slab Formwork Installation

JAH-Z5-ST-S3-BS.120 Base Slab Concrete Casting 1 14-Dec-23 14-Dec-23 Base Slab Concrete Casting

JAH-Z5-ST-S3-BS.122 Curing work 7 16-Dec-23 23-Dec-23 Curing work

JAH-Z5-ST-S3-BS.125 Base Slab Formwork Removel 2 24-Dec-23 25-Dec-23 Base Slab Formwork Removel

COLUMNS 23 26-Dec-23 21-Jan-24 21-Jan-24, COLUMNS


JAH-Z5-ST-S3-CL.100 Column Rebar Installation 8 26-Dec-23 03-Jan-24 Column Rebar Installation

JAH-Z5-ST-S3-CL.105 Column Formwork Installation 7 04-Jan-24 11-Jan-24 Column Formwork Installation

JAH-Z5-ST-S3-CL.110 Column Concrete Casting 1 13-Jan-24 13-Jan-24 Column Concrete Casting

JAH-Z5-ST-S3-CL.115 Form Work Removal and Curing 7 14-Jan-24 21-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 37 26-Dec-23 06-Feb-24 06-Feb-24, TUNNEL WALLS


JAH-Z5-ST-S3-TW.100 Tunnel Walls Rebar Installation 8 26-Dec-23 03-Jan-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S3-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 26-Dec-23 03-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S3-TW.105 Tunnel Formwork Installation 7 04-Jan-24 11-Jan-24 Tunnel Formwork Installation

JAH-Z5-ST-S3-TW.110 Tunnel Walls Concrete Casting 1 13-Jan-24 13-Jan-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S3-TW.112 Curing work 7 14-Jan-24 21-Jan-24 Curing work

JAH-Z5-ST-S3-TW.120 Tunnel Walls Formwork Removel 2 22-Jan-24 23-Jan-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S3-TW.125 Tunnel Wall Waterproofing 12 24-Jan-24 06-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 24-Jan-24 27-Feb-24 27-Feb-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S3-MS.090 Middle Slab Scaffold and Formwork Installation 5 24-Jan-24 29-Jan-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S3-MS.100 Middle Slab Rebar Installation 8 30-Jan-24 07-Feb-24 Middle Slab Rebar Installation

JAH-Z5-ST-S3-MS.105 Middle Slab Vertical Formwork Installation 7 08-Feb-24 15-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S3-MS.110 Middle Slab Concrete Casting 1 17-Feb-24 17-Feb-24 Middle Slab Concrete Casting

JAH-Z5-ST-S3-MS.115 Curing work 7 18-Feb-24 25-Feb-24 Curing work

JAH-Z5-ST-S3-MS.120 Middle Slab Formwork Removel 2 26-Feb-24 27-Feb-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 28-Feb-24 27-Mar-24 27-Mar-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S3-UCW.100Utility Culvert Walls Rebar Installation 8 28-Feb-24 07-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S3-UCW.105Utility Culvert Walls Formwork Installation 7 09-Mar-24 16-Mar-24 Utility Culvert Walls Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
357 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S3-UCW.110Utility Culvert Walls Concrete Casting 1 17-Mar-24 17-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S3-UCW.112Curing work 7 18-Mar-24 25-Mar-24 Curing work

JAH-Z5-ST-S3-UCW.115Utility Culvert Walls Walls Formwork Removel 2 26-Mar-24 27-Mar-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 28-Mar-24 13-May-24 13-May-24, TOP SLAB


JAH-Z5-ST-S3-TS.100 Top Slab Rebar Installation 8 28-Mar-24 06-Apr-24 Top Slab Rebar Installation

JAH-Z5-ST-S3-TS.105 Top Slab Formwork Installation 7 07-Apr-24 17-Apr-24 Top Slab Formwork Installation

JAH-Z5-ST-S3-TS.110 Top Slab Concrete Casting 1 18-Apr-24 18-Apr-24 Top Slab Concrete Casting

JAH-Z5-ST-S3-TS.112 Curing work 7 20-Apr-24 27-Apr-24 Curing work

JAH-Z5-ST-S3-TS.115 Top Slab Formwork Removel 2 28-Apr-24 29-Apr-24 Top Slab Formwork Removel

JAH-Z5-ST-S3-TS.120 Waterproofing for Top Slab 12 30-Apr-24 13-May-24 Waterproofing for Top Slab

FINISHING WORK 37 14-May-24 30-Jun-24 30-Jun-24, FINISHING WORK


JAH-Z5-ST-S3-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 14-May-24 21-May-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S3-FW.105 Plain Concrete Casting 1 22-May-24 22-May-24 Plain Concrete Casting

JAH-Z5-ST-S3-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 08-Jun-24 08-Jun-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S3-FW.112 Curing work 7 09-Jun-24 20-Jun-24 Curing work

JAH-Z5-ST-S3-FW.115 Concrete Protective coating 8 22-Jun-24 30-Jun-24 Concrete Protective coating

STA. 1+813.979 ~ 1+833.979 187 06-Dec-23 18-Jul-24 18-Jul-24, STA. 1+813.979 ~ 1+833.979
BASE SLAB 27 06-Dec-23 06-Jan-24 06-Jan-24, BASE SLAB
JAH-Z5-ST-S4-BS.100 Lean Concrete for Base Slab 1 06-Dec-23 06-Dec-23 Lean Concrete for Base Slab

JAH-Z5-ST-S4-BS.105 Waterproofing for Lean Concrete 1 07-Dec-23 07-Dec-23 Waterproofing for Lean Concrete

JAH-Z5-ST-S4-BS.110 Base Slab Rebar Installation 8 09-Dec-23 17-Dec-23 Base Slab Rebar Installation

JAH-Z5-ST-S4-BS.115 Base Slab Formwork Installation 7 18-Dec-23 25-Dec-23 Base Slab Formwork Installation

JAH-Z5-ST-S4-BS.120 Base Slab Concrete Casting 1 26-Dec-23 26-Dec-23 Base Slab Concrete Casting

JAH-Z5-ST-S4-BS.122 Curing work 7 27-Dec-23 03-Jan-24 Curing work

JAH-Z5-ST-S4-BS.125 Base Slab Formwork Removel 2 04-Jan-24 06-Jan-24 Base Slab Formwork Removel

COLUMNS 23 07-Jan-24 01-Feb-24 01-Feb-24, COLUMNS


JAH-Z5-ST-S4-CL.100 Column Rebar Installation 8 07-Jan-24 15-Jan-24 Column Rebar Installation

JAH-Z5-ST-S4-CL.105 Column Formwork Installation 7 16-Jan-24 23-Jan-24 Column Formwork Installation

JAH-Z5-ST-S4-CL.110 Column Concrete Casting 1 24-Jan-24 24-Jan-24 Column Concrete Casting

JAH-Z5-ST-S4-CL.115 Form Work Removal and Curing 7 25-Jan-24 01-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 07-Jan-24 18-Feb-24 18-Feb-24, TUNNEL WALLS


JAH-Z5-ST-S4-TW.100 Tunnel Walls Rebar Installation 8 07-Jan-24 15-Jan-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S4-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 07-Jan-24 15-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S4-TW.105 Tunnel Formwork Installation 7 16-Jan-24 23-Jan-24 Tunnel Formwork Installation

JAH-Z5-ST-S4-TW.110 Tunnel Walls Concrete Casting 1 24-Jan-24 24-Jan-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S4-TW.112 Curing work 7 25-Jan-24 01-Feb-24 Curing work

JAH-Z5-ST-S4-TW.120 Tunnel Walls Formwork Removel 2 03-Feb-24 04-Feb-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S4-TW.125 Tunnel Wall Waterproofing 12 05-Feb-24 18-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 05-Feb-24 10-Mar-24 10-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S4-MS.090 Middle Slab Scaffold and Formwork Installation 5 05-Feb-24 10-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S4-MS.100 Middle Slab Rebar Installation 8 11-Feb-24 19-Feb-24 Middle Slab Rebar Installation

JAH-Z5-ST-S4-MS.105 Middle Slab Vertical Formwork Installation 7 20-Feb-24 27-Feb-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S4-MS.110 Middle Slab Concrete Casting 1 28-Feb-24 28-Feb-24 Middle Slab Concrete Casting

JAH-Z5-ST-S4-MS.115 Curing work 7 29-Feb-24 07-Mar-24 Curing work

JAH-Z5-ST-S4-MS.120 Middle Slab Formwork Removel 2 09-Mar-24 10-Mar-24 Middle Slab Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
358 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
UTILITY CULVERT WALLS 25 11-Mar-24 08-Apr-24 08-Apr-24, UTILITY CULVERT WALLS
JAH-Z5-ST-S4-UCW.100Utility Culvert Walls Rebar Installation 8 11-Mar-24 19-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S4-UCW.105Utility Culvert Walls Formwork Installation 7 20-Mar-24 27-Mar-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S4-UCW.110Utility Culvert Walls Concrete Casting 1 28-Mar-24 28-Mar-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S4-UCW.112Curing work 7 30-Mar-24 06-Apr-24 Curing work

JAH-Z5-ST-S4-UCW.115Utility Culvert Walls Walls Formwork Removel 2 07-Apr-24 08-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 13-Apr-24 25-May-24 25-May-24, TOP SLAB


JAH-Z5-ST-S4-TS.100 Top Slab Rebar Installation 8 13-Apr-24 21-Apr-24 Top Slab Rebar Installation

JAH-Z5-ST-S4-TS.105 Top Slab Formwork Installation 7 22-Apr-24 29-Apr-24 Top Slab Formwork Installation

JAH-Z5-ST-S4-TS.110 Top Slab Concrete Casting 1 30-Apr-24 30-Apr-24 Top Slab Concrete Casting

JAH-Z5-ST-S4-TS.112 Curing work 7 01-May-24 08-May-24 Curing work

JAH-Z5-ST-S4-TS.115 Top Slab Formwork Removel 2 09-May-24 11-May-24 Top Slab Formwork Removel

JAH-Z5-ST-S4-TS.120 Waterproofing for Top Slab 12 12-May-24 25-May-24 Waterproofing for Top Slab

FINISHING WORK 43 26-May-24 18-Jul-24 18-Jul-24, FINISHING WORK


JAH-Z5-ST-S4-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 26-May-24 02-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S4-FW.105 Plain Concrete Casting 1 03-Jun-24 03-Jun-24 Plain Concrete Casting

JAH-Z5-ST-S4-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 01-Jul-24 01-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S4-FW.112 Curing work 7 02-Jul-24 09-Jul-24 Curing work

JAH-Z5-ST-S4-FW.115 Concrete Protective coating 8 10-Jul-24 18-Jul-24 Concrete Protective coating

STA. 1+833.979 ~ 1+853.979 194 18-Dec-23 07-Aug-24 07-Aug-24, STA. 1+833.979 ~ 1+853.979
BASE SLAB 34 18-Dec-23 25-Jan-24 25-Jan-24, BASE SLAB
JAH-Z5-ST-S5-BS.100 Lean Concrete for Base Slab 1 18-Dec-23 18-Dec-23 Lean Concrete for Base Slab

JAH-Z5-ST-S5-BS.105 Waterproofing for Lean Concrete 1 19-Dec-23 19-Dec-23 Waterproofing for Lean Concrete

JAH-Z5-ST-S5-BS.110 Base Slab Rebar Installation 8 20-Dec-23 28-Dec-23 Base Slab Rebar Installation

JAH-Z5-ST-S5-BS.115 Base Slab Formwork Installation 7 30-Dec-23 06-Jan-24 Base Slab Formwork Installation

JAH-Z5-ST-S5-BS.120 Base Slab Concrete Casting 1 07-Jan-24 07-Jan-24 Base Slab Concrete Casting

JAH-Z5-ST-S5-BS.122 Curing work 7 08-Jan-24 15-Jan-24 Curing work

JAH-Z5-ST-S5-BS.125 Base Slab Formwork Removel 2 16-Jan-24 17-Jan-24 Base Slab Formwork Removel

JAH-Z5-ST-S5-BS.130 Curing work 7 18-Jan-24 25-Jan-24 Curing work

COLUMNS 23 18-Jan-24 13-Feb-24 13-Feb-24, COLUMNS


JAH-Z5-ST-S5-CL.100 Column Rebar Installation 8 18-Jan-24 27-Jan-24 Column Rebar Installation

JAH-Z5-ST-S5-CL.105 Column Formwork Installation 7 28-Jan-24 04-Feb-24 Column Formwork Installation

JAH-Z5-ST-S5-CL.110 Column Concrete Casting 1 05-Feb-24 05-Feb-24 Column Concrete Casting

JAH-Z5-ST-S5-CL.115 Form Work Removal and Curing 7 06-Feb-24 13-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 37 18-Jan-24 29-Feb-24 29-Feb-24, TUNNEL WALLS


JAH-Z5-ST-S5-TW.100 Tunnel Walls Rebar Installation 8 18-Jan-24 27-Jan-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S5-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 18-Jan-24 27-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S5-TW.105 Tunnel Formwork Installation 7 28-Jan-24 04-Feb-24 Tunnel Formwork Installation

JAH-Z5-ST-S5-TW.110 Tunnel Walls Concrete Casting 1 05-Feb-24 05-Feb-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S5-TW.115 Curing work 7 06-Feb-24 13-Feb-24 Curing work

JAH-Z5-ST-S5-TW.120 Tunnel Walls Formwork Removel 2 14-Feb-24 15-Feb-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S5-TW.125 Tunnel Wall Waterproofing 12 17-Feb-24 29-Feb-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 17-Feb-24 21-Mar-24 21-Mar-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S5-MS.090 Middle Slab Scaffold and Formwork Installation 5 17-Feb-24 21-Feb-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S5-MS.100 Middle Slab Rebar Installation 8 22-Feb-24 02-Mar-24 Middle Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
359 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S5-MS.105 Middle Slab Vertical Formwork Installation 7 03-Mar-24 10-Mar-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S5-MS.110 Middle Slab Concrete Casting 1 11-Mar-24 11-Mar-24 Middle Slab Concrete Casting

JAH-Z5-ST-S5-MS.115 Curing work 7 12-Mar-24 19-Mar-24 Curing work

JAH-Z5-ST-S5-MS.120 Middle Slab Formwork Removel 2 20-Mar-24 21-Mar-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 23-Mar-24 23-Apr-24 23-Apr-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S5-UCW.100Utility Culvert Walls Rebar Installation 8 23-Mar-24 31-Mar-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S5-UCW.105Utility Culvert Walls Formwork Installation 7 01-Apr-24 08-Apr-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S5-UCW.110Utility Culvert Walls Concrete Casting 1 13-Apr-24 13-Apr-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S5-UCW.112Curing work 7 14-Apr-24 21-Apr-24 Curing work

JAH-Z5-ST-S5-UCW.115Utility Culvert Walls Walls Formwork Removel 2 22-Apr-24 23-Apr-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 24-Apr-24 05-Jun-24 05-Jun-24, TOP SLAB


JAH-Z5-ST-S5-TS.100 Top Slab Rebar Installation 8 24-Apr-24 02-May-24 Top Slab Rebar Installation

JAH-Z5-ST-S5-TS.105 Top Slab Formwork Installation 7 04-May-24 11-May-24 Top Slab Formwork Installation

JAH-Z5-ST-S5-TS.110 Top Slab Concrete Casting 1 12-May-24 12-May-24 Top Slab Concrete Casting

JAH-Z5-ST-S5-TS.112 Curing work 7 13-May-24 20-May-24 Curing work

JAH-Z5-ST-S5-TS.115 Top Slab Formwork Removel 2 21-May-24 22-May-24 Top Slab Formwork Removel

JAH-Z5-ST-S5-TS.120 Waterproofing for Top Slab 12 23-May-24 05-Jun-24 Waterproofing for Top Slab

FINISHING WORK 50 06-Jun-24 07-Aug-24 07-Aug-24, FINISHING WORK


JAH-Z5-ST-S5-MC.100 Above Top Slab Formwork Installation for Plain Concrete 7 06-Jun-24 13-Jun-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S5-MC.105 Plain Concrete Casting 1 20-Jul-24 20-Jul-24 Plain Concrete Casting

JAH-Z5-ST-S5-MC.110 Mass Concrete Casting for Base Slab Top Layer 1 21-Jul-24 21-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S5-MC.112 Curing work 7 22-Jul-24 29-Jul-24 Curing work

JAH-Z5-ST-S5-MC.115 Concrete Protective coating 8 30-Jul-24 07-Aug-24 Concrete Protective coating

STA. 1+853.979 ~ 1+873.979 189 10-Jan-24 25-Aug-24 25-Aug-24, STA. 1+853.979 ~ 1+873.979
BASE SLAB 27 10-Jan-24 10-Feb-24 10-Feb-24, BASE SLAB
JAH-Z5-ST-S6-BS.100 Lean Concrete for Base Slab 1 10-Jan-24 10-Jan-24 Lean Concrete for Base Slab

JAH-Z5-ST-S6-BS.105 Waterproofing for Lean Concrete 1 11-Jan-24 11-Jan-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S6-BS.110 Base Slab Rebar Installation 8 13-Jan-24 21-Jan-24 Base Slab Rebar Installation

JAH-Z5-ST-S6-BS.115 Base Slab Formwork Installation 7 22-Jan-24 29-Jan-24 Base Slab Formwork Installation

JAH-Z5-ST-S6-BS.120 Base Slab Concrete Casting 1 30-Jan-24 30-Jan-24 Base Slab Concrete Casting

JAH-Z5-ST-S6-BS.122 Curing work 7 31-Jan-24 07-Feb-24 Curing work

JAH-Z5-ST-S6-BS.125 Base Slab Formwork Removel 2 08-Feb-24 10-Feb-24 Base Slab Formwork Removel

COLUMNS 23 11-Feb-24 07-Mar-24 07-Mar-24, COLUMNS


JAH-Z5-ST-S6-CL.100 Column Rebar Installation 8 11-Feb-24 19-Feb-24 Column Rebar Installation

JAH-Z5-ST-S6-CL.105 Column Formwork Installation 7 20-Feb-24 27-Feb-24 Column Formwork Installation

JAH-Z5-ST-S6-CL.110 Column Concrete Casting 1 28-Feb-24 28-Feb-24 Column Concrete Casting

JAH-Z5-ST-S6-CL.115 Form Work Removal and Curing 7 29-Feb-24 07-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 11-Feb-24 24-Mar-24 24-Mar-24, TUNNEL WALLS


JAH-Z5-ST-S6-TW.100 Tunnel Walls Rebar Installation 8 11-Feb-24 19-Feb-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S6-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-Feb-24 19-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S6-TW.105 Tunnel Formwork Installation 7 20-Feb-24 27-Feb-24 Tunnel Formwork Installation

JAH-Z5-ST-S6-TW.110 Tunnel Walls Concrete Casting 1 28-Feb-24 28-Feb-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S6-TW.112 Curing work 7 29-Feb-24 07-Mar-24 Curing work

JAH-Z5-ST-S6-TW.120 Tunnel Walls Formwork Removel 2 09-Mar-24 10-Mar-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S6-TW.125 Tunnel Wall Waterproofing 12 11-Mar-24 24-Mar-24 Tunnel Wall Waterproofing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
360 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
MIDDLE SLAB FOR UTILITY CULVERT 30 11-Mar-24 17-Apr-24 17-Apr-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S6-MS.090 Middle Slab Scaffold and Formwork Installation 5 11-Mar-24 16-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S6-MS.100 Middle Slab Rebar Installation 8 17-Mar-24 25-Mar-24 Middle Slab Rebar Installation

JAH-Z5-ST-S6-MS.105 Middle Slab Vertical Formwork Installation 7 26-Mar-24 02-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S6-MS.110 Middle Slab Concrete Casting 1 03-Apr-24 03-Apr-24 Middle Slab Concrete Casting

JAH-Z5-ST-S6-MS.115 Curing work 7 04-Apr-24 15-Apr-24 Curing work

JAH-Z5-ST-S6-MS.120 Middle Slab Formwork Removel 2 16-Apr-24 17-Apr-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 18-Apr-24 16-May-24 16-May-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S6-UCW.100Utility Culvert Walls Rebar Installation 8 18-Apr-24 27-Apr-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S6-UCW.105Utility Culvert Walls Formwork Installation 7 28-Apr-24 05-May-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S6-UCW.110Utility Culvert Walls Concrete Casting 1 06-May-24 06-May-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S6-UCW.112Curing work 7 07-May-24 14-May-24 Curing work

JAH-Z5-ST-S6-UCW.115Utility Culvert Walls Walls Formwork Removel 2 15-May-24 16-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 18-May-24 03-Jul-24 03-Jul-24, TOP SLAB


JAH-Z5-ST-S6-TS.100 Top Slab Rebar Installation 8 18-May-24 26-May-24 Top Slab Rebar Installation

JAH-Z5-ST-S6-TS.105 Top Slab Formwork Installation 7 27-May-24 03-Jun-24 Top Slab Formwork Installation

JAH-Z5-ST-S6-TS.110 Top Slab Concrete Casting 1 04-Jun-24 04-Jun-24 Top Slab Concrete Casting

JAH-Z5-ST-S6-TS.112 Curing work 7 05-Jun-24 12-Jun-24 Curing work

JAH-Z5-ST-S6-TS.115 Top Slab Formwork Removel 2 13-Jun-24 19-Jun-24 Top Slab Formwork Removel

JAH-Z5-ST-S6-TS.120 Waterproofing for Top Slab 12 20-Jun-24 03-Jul-24 Waterproofing for Top Slab

FINISHING WORK 45 04-Jul-24 25-Aug-24 25-Aug-24, FINISHING WORK


JAH-Z5-ST-S6-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 04-Jul-24 11-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S6-FW.105 Plain Concrete Casting 1 13-Jul-24 13-Jul-24 Plain Concrete Casting

JAH-Z5-ST-S6-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 14-Jul-24 14-Jul-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S6-FW.112 Curing work 7 08-Aug-24 15-Aug-24 Curing work

JAH-Z5-ST-S6-FW.115 Concrete Protective coating 8 17-Aug-24 25-Aug-24 Concrete Protective coating

STA. 1+873.979 ~ 1+893.979 195 22-Jan-24 12-Sep-24 12-Sep-24, STA. 1+873.979 ~ 1+893.979
BASE SLAB 27 22-Jan-24 21-Feb-24 21-Feb-24, BASE SLAB
JAH-Z5-ST-S7-BS.100 Lean Concrete for Base Slab 1 22-Jan-24 22-Jan-24 Lean Concrete for Base Slab

JAH-Z5-ST-S7-BS.105 Waterproofing for Lean Concrete 1 23-Jan-24 23-Jan-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S7-BS.110 Base Slab Rebar Installation 8 24-Jan-24 01-Feb-24 Base Slab Rebar Installation

JAH-Z5-ST-S7-BS.115 Base Slab Formwork Installation 7 03-Feb-24 10-Feb-24 Base Slab Formwork Installation

JAH-Z5-ST-S7-BS.120 Base Slab Concrete Casting 1 11-Feb-24 11-Feb-24 Base Slab Concrete Casting

JAH-Z5-ST-S7-BS.122 Curing work 7 12-Feb-24 19-Feb-24 Curing work

JAH-Z5-ST-S7-BS.125 Base Slab Formwork Removel 2 20-Feb-24 21-Feb-24 Base Slab Formwork Removel

COLUMNS 23 22-Feb-24 19-Mar-24 19-Mar-24, COLUMNS


JAH-Z5-ST-S7-CL.100 Column Rebar Installation 8 22-Feb-24 02-Mar-24 Column Rebar Installation

JAH-Z5-ST-S7-CL.105 Column Formwork Installation 7 03-Mar-24 10-Mar-24 Column Formwork Installation

JAH-Z5-ST-S7-CL.110 Column Concrete Casting 1 11-Mar-24 11-Mar-24 Column Concrete Casting

JAH-Z5-ST-S7-CL.115 Form Work Removal and Curing 7 12-Mar-24 19-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 22-Feb-24 04-Apr-24 04-Apr-24, TUNNEL WALLS


JAH-Z5-ST-S7-TW.100 Tunnel Walls Rebar Installation 8 22-Feb-24 02-Mar-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S7-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 22-Feb-24 02-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S7-TW.105 Tunnel Formwork Installation 7 03-Mar-24 10-Mar-24 Tunnel Formwork Installation

JAH-Z5-ST-S7-TW.110 Tunnel Walls Concrete Casting 1 11-Mar-24 11-Mar-24 Tunnel Walls Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
361 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S7-TW.112 Curing work 7 12-Mar-24 19-Mar-24 Curing work

JAH-Z5-ST-S7-TW.120 Tunnel Walls Formwork Removel 2 20-Mar-24 21-Mar-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S7-TW.125 Tunnel Wall Waterproofing 12 23-Mar-24 04-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 23-Mar-24 29-Apr-24 29-Apr-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S7-MS.090 Middle Slab Scaffold and Formwork Installation 5 23-Mar-24 27-Mar-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S7-MS.100 Middle Slab Rebar Installation 8 28-Mar-24 06-Apr-24 Middle Slab Rebar Installation

JAH-Z5-ST-S7-MS.105 Middle Slab Vertical Formwork Installation 7 07-Apr-24 17-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S7-MS.110 Middle Slab Concrete Casting 1 18-Apr-24 18-Apr-24 Middle Slab Concrete Casting

JAH-Z5-ST-S7-MS.115 Curing work 7 20-Apr-24 27-Apr-24 Curing work

JAH-Z5-ST-S7-MS.120 Middle Slab Formwork Removel 2 28-Apr-24 29-Apr-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 30-Apr-24 28-May-24 28-May-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S7-UCW.100Utility Culvert Walls Rebar Installation 8 30-Apr-24 08-May-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S7-UCW.105Utility Culvert Walls Formwork Installation 7 09-May-24 16-May-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S7-UCW.110Utility Culvert Walls Concrete Casting 1 18-May-24 18-May-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S7-UCW.112Curing work 7 19-May-24 26-May-24 Curing work

JAH-Z5-ST-S7-UCW.115Utility Culvert Walls Walls Formwork Removel 2 27-May-24 28-May-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 29-May-24 15-Jul-24 15-Jul-24, TOP SLAB


JAH-Z5-ST-S7-TS.100 Top Slab Rebar Installation 8 29-May-24 06-Jun-24 Top Slab Rebar Installation

JAH-Z5-ST-S7-TS.105 Top Slab Formwork Installation 7 08-Jun-24 19-Jun-24 Top Slab Formwork Installation

JAH-Z5-ST-S7-TS.110 Top Slab Concrete Casting 1 20-Jun-24 20-Jun-24 Top Slab Concrete Casting

JAH-Z5-ST-S7-TS.112 Curing work 7 22-Jun-24 29-Jun-24 Curing work

JAH-Z5-ST-S7-TS.115 Top Slab Formwork Removel 2 30-Jun-24 01-Jul-24 Top Slab Formwork Removel

JAH-Z5-ST-S7-TS.120 Waterproofing for Top Slab 12 02-Jul-24 15-Jul-24 Waterproofing for Top Slab

FINISHING WORK 51 16-Jul-24 12-Sep-24 12-Sep-24, FINISHING WORK


JAH-Z5-ST-S7-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 16-Jul-24 23-Jul-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S7-FW.105 Plain Concrete Casting 1 24-Jul-24 24-Jul-24 Plain Concrete Casting

JAH-Z5-ST-S7-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 26-Aug-24 26-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S7-FW.112 Curing work 7 27-Aug-24 03-Sep-24 Curing work

JAH-Z5-ST-S7-FW.115 Concrete Protective coating 8 04-Sep-24 12-Sep-24 Concrete Protective coating

STA. 1+893.979 ~ 1+913.979 201 03-Feb-24 02-Oct-24 02-Oct-24, STA. 1+893.979 ~ 1+913.979
BASE SLAB 27 03-Feb-24 04-Mar-24 04-Mar-24, BASE SLAB
JAH-Z5-ST-S8-BS.100 Lean Concrete for Base Slab 1 03-Feb-24 03-Feb-24 Lean Concrete for Base Slab

JAH-Z5-ST-S8-BS.105 Waterproofing for Lean Concrete 1 04-Feb-24 04-Feb-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S8-BS.110 Base Slab Rebar Installation 8 05-Feb-24 13-Feb-24 Base Slab Rebar Installation

JAH-Z5-ST-S8-BS.115 Base Slab Formwork Installation 7 14-Feb-24 21-Feb-24 Base Slab Formwork Installation

JAH-Z5-ST-S8-BS.120 Base Slab Concrete Casting 1 22-Feb-24 22-Feb-24 Base Slab Concrete Casting

JAH-Z5-ST-S8-BS.122 Curing work 7 24-Feb-24 02-Mar-24 Curing work

JAH-Z5-ST-S8-BS.125 Base Slab Formwork Removel 2 03-Mar-24 04-Mar-24 Base Slab Formwork Removel

COLUMNS 23 05-Mar-24 31-Mar-24 31-Mar-24, COLUMNS


JAH-Z5-ST-S8-CL.100 Column Rebar Installation 8 05-Mar-24 13-Mar-24 Column Rebar Installation

JAH-Z5-ST-S8-CL.105 Column Formwork Installation 7 14-Mar-24 21-Mar-24 Column Formwork Installation

JAH-Z5-ST-S8-CL.110 Column Concrete Casting 1 23-Mar-24 23-Mar-24 Column Concrete Casting

JAH-Z5-ST-S8-CL.115 Form Work Removal and Curing 7 24-Mar-24 31-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 37 05-Mar-24 20-Apr-24 20-Apr-24, TUNNEL WALLS


JAH-Z5-ST-S8-TW.100 Tunnel Walls Rebar Installation 8 05-Mar-24 13-Mar-24 Tunnel Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
362 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S8-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 05-Mar-24 13-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S8-TW.105 Tunnel Formwork Installation 7 14-Mar-24 21-Mar-24 Tunnel Formwork Installation

JAH-Z5-ST-S8-TW.110 Tunnel Walls Concrete Casting 1 23-Mar-24 23-Mar-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S8-TW.115 Curing work 7 24-Mar-24 31-Mar-24 Curing work

JAH-Z5-ST-S8-TW.120 Tunnel Walls Formwork Removel 2 01-Apr-24 02-Apr-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S8-TW.125 Tunnel Wall Waterproofing 12 03-Apr-24 20-Apr-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 03-Apr-24 11-May-24 11-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S8-MS.090 Middle Slab Scaffold and Formwork Installation 5 03-Apr-24 08-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S8-MS.100 Middle Slab Rebar Installation 8 13-Apr-24 21-Apr-24 Middle Slab Rebar Installation

JAH-Z5-ST-S8-MS.105 Middle Slab Vertical Formwork Installation 7 22-Apr-24 29-Apr-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S8-MS.110 Middle Slab Concrete Casting 1 30-Apr-24 30-Apr-24 Middle Slab Concrete Casting

JAH-Z5-ST-S8-MS.115 Curing work 7 01-May-24 08-May-24 Curing work

JAH-Z5-ST-S8-MS.120 Middle Slab Formwork Removel 2 09-May-24 11-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 12-May-24 09-Jun-24 09-Jun-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S8-UCW.100Utility Culvert Walls Rebar Installation 8 12-May-24 20-May-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S8-UCW.105Utility Culvert Walls Formwork Installation 7 21-May-24 28-May-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S8-UCW.110Utility Culvert Walls Concrete Casting 1 29-May-24 29-May-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S8-UCW.112Curing work 7 30-May-24 06-Jun-24 Curing work

JAH-Z5-ST-S8-UCW.115Utility Culvert Walls Walls Formwork Removel 2 08-Jun-24 09-Jun-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 10-Jun-24 27-Jul-24 27-Jul-24, TOP SLAB


JAH-Z5-ST-S8-TS.100 Top Slab Rebar Installation 8 10-Jun-24 23-Jun-24 Top Slab Rebar Installation

JAH-Z5-ST-S8-TS.105 Top Slab Formwork Installation 7 24-Jun-24 01-Jul-24 Top Slab Formwork Installation

JAH-Z5-ST-S8-TS.110 Top Slab Concrete Casting 1 02-Jul-24 02-Jul-24 Top Slab Concrete Casting

JAH-Z5-ST-S8-TS.112 Curing work 7 03-Jul-24 10-Jul-24 Curing work

JAH-Z5-ST-S8-TS.115 Top Slab Formwork Removel 2 11-Jul-24 13-Jul-24 Top Slab Formwork Removel

JAH-Z5-ST-S8-TS.120 Waterproofing for Top Slab 12 14-Jul-24 27-Jul-24 Waterproofing for Top Slab

FINISHING WORK 57 28-Jul-24 02-Oct-24 02-Oct-24, FINISHING WORK


JAH-Z5-ST-S8-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 28-Jul-24 04-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S8-FW.105 Plain Concrete Casting 1 05-Aug-24 05-Aug-24 Plain Concrete Casting

JAH-Z5-ST-S8-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 14-Sep-24 14-Sep-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S8-FW.112 Curing work 7 15-Sep-24 22-Sep-24 Curing work

JAH-Z5-ST-S8-FW.115 Concrete Protective coating 8 24-Sep-24 02-Oct-24 Concrete Protective coating

STA. 1+913.979~ 1+933.979 199 14-Feb-24 12-Oct-24 12-Oct-24, STA. 1+913.979~ 1+933.979
BASE SLAB 27 14-Feb-24 16-Mar-24 16-Mar-24, BASE SLAB
JAH-Z5-ST-S9-BS.100 Lean Concrete for Base Slab 1 14-Feb-24 14-Feb-24 Lean Concrete for Base Slab

JAH-Z5-ST-S9-BS.105 Waterproofing for Lean Concrete 1 15-Feb-24 15-Feb-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S9-BS.110 Base Slab Rebar Installation 8 17-Feb-24 25-Feb-24 Base Slab Rebar Installation

JAH-Z5-ST-S9-BS.115 Base Slab Formwork Installation 7 26-Feb-24 04-Mar-24 Base Slab Formwork Installation

JAH-Z5-ST-S9-BS.120 Base Slab Concrete Casting 1 05-Mar-24 05-Mar-24 Base Slab Concrete Casting

JAH-Z5-ST-S9-BS.122 Curing work 7 06-Mar-24 13-Mar-24 Curing work

JAH-Z5-ST-S9-BS.125 Base Slab Formwork Removel 2 14-Mar-24 16-Mar-24 Base Slab Formwork Removel

COLUMNS 23 17-Mar-24 15-Apr-24 15-Apr-24, COLUMNS


JAH-Z5-ST-S9-CL.100 Column Rebar Installation 8 17-Mar-24 25-Mar-24 Column Rebar Installation

JAH-Z5-ST-S9-CL.105 Column Formwork Installation 7 26-Mar-24 02-Apr-24 Column Formwork Installation

JAH-Z5-ST-S9-CL.110 Column Concrete Casting 1 03-Apr-24 03-Apr-24 Column Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
363 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S9-CL.115 Form Work Removal and Curing 7 04-Apr-24 15-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 37 17-Mar-24 01-May-24 01-May-24, TUNNEL WALLS


JAH-Z5-ST-S9-TW.100 Tunnel Walls Rebar Installation 8 17-Mar-24 25-Mar-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S9-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 17-Mar-24 25-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S9-TW.105 Tunnel Formwork Installation 7 26-Mar-24 02-Apr-24 Tunnel Formwork Installation

JAH-Z5-ST-S9-TW.110 Tunnel Walls Concrete Casting 1 03-Apr-24 03-Apr-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S9-TW.112 Curing work 7 04-Apr-24 15-Apr-24 Curing work

JAH-Z5-ST-S9-TW.120 Tunnel Walls Formwork Removel 2 16-Apr-24 17-Apr-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S9-TW.125 Tunnel Wall Waterproofing 12 18-Apr-24 01-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 18-Apr-24 22-May-24 22-May-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S9-MS.090 Middle Slab Scaffold and Formwork Installation 5 18-Apr-24 23-Apr-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S9-MS.100 Middle Slab Rebar Installation 8 24-Apr-24 02-May-24 Middle Slab Rebar Installation

JAH-Z5-ST-S9-MS.105 Middle Slab Vertical Formwork Installation 7 04-May-24 11-May-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S9-MS.110 Middle Slab Concrete Casting 1 12-May-24 12-May-24 Middle Slab Concrete Casting

JAH-Z5-ST-S9-MS.115 Curing work 7 13-May-24 20-May-24 Curing work

JAH-Z5-ST-S9-MS.120 Middle Slab Formwork Removel 2 21-May-24 22-May-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 23-May-24 25-Jun-24 25-Jun-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S9-UCW.100Utility Culvert Walls Rebar Installation 8 23-May-24 01-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S9-UCW.105Utility Culvert Walls Formwork Installation 7 02-Jun-24 09-Jun-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S9-UCW.110Utility Culvert Walls Concrete Casting 1 10-Jun-24 10-Jun-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S9-UCW.112Curing work 7 11-Jun-24 23-Jun-24 Curing work

JAH-Z5-ST-S9-UCW.115Utility Culvert Walls Walls Formwork Removel 2 24-Jun-24 25-Jun-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 26-Jun-24 07-Aug-24 07-Aug-24, TOP SLAB


JAH-Z5-ST-S9-TS.100 Top Slab Rebar Installation 8 26-Jun-24 04-Jul-24 Top Slab Rebar Installation

JAH-Z5-ST-S9-TS.105 Top Slab Formwork Installation 7 06-Jul-24 13-Jul-24 Top Slab Formwork Installation

JAH-Z5-ST-S9-TS.110 Top Slab Concrete Casting 1 14-Jul-24 14-Jul-24 Top Slab Concrete Casting

JAH-Z5-ST-S9-TS.112 Curing work 7 15-Jul-24 22-Jul-24 Curing work

JAH-Z5-ST-S9-TS.115 Top Slab Formwork Removel 2 23-Jul-24 24-Jul-24 Top Slab Formwork Removel

JAH-Z5-ST-S9-TS.120 Waterproofing for Top Slab 12 25-Jul-24 07-Aug-24 Waterproofing for Top Slab

FINISHING WORK 55 08-Aug-24 12-Oct-24 12-Oct-24, FINISHING WORK


JAH-Z5-ST-S9-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 08-Aug-24 15-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S9-FW.105 Plain Concrete Casting 1 17-Aug-24 17-Aug-24 Plain Concrete Casting

JAH-Z5-ST-S9-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 18-Aug-24 18-Aug-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S9-FW.112 Curing work 7 19-Aug-24 26-Aug-24 Curing work

JAH-Z5-ST-S9-FW.115 Concrete Protective coating 8 03-Oct-24 12-Oct-24 Concrete Protective coating

STA. 1+933.979 ~ 1+953.979 206 26-Feb-24 31-Oct-24 31-Oct-24, STA. 1+933.979 ~ 1+953.979
BASE SLAB 27 26-Feb-24 27-Mar-24 27-Mar-24, BASE SLAB
JAH-Z5-ST-S10-BS.100Lean Concrete for Base Slab 1 26-Feb-24 26-Feb-24 Lean Concrete for Base Slab

JAH-Z5-ST-S10-BS.105Waterproofing for Lean Concrete 1 27-Feb-24 27-Feb-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S10-BS.110 Base Slab Rebar Installation 8 28-Feb-24 07-Mar-24 Base Slab Rebar Installation

JAH-Z5-ST-S10-BS.115 Base Slab Formwork Installation 7 09-Mar-24 16-Mar-24 Base Slab Formwork Installation

JAH-Z5-ST-S10-BS.120Base Slab Concrete Casting 1 17-Mar-24 17-Mar-24 Base Slab Concrete Casting

JAH-Z5-ST-S10-BS.122Curing work 7 18-Mar-24 25-Mar-24 Curing work

JAH-Z5-ST-S10-BS.125Base Slab Formwork Removel 2 26-Mar-24 27-Mar-24 Base Slab Formwork Removel

COLUMNS 23 28-Mar-24 27-Apr-24 27-Apr-24, COLUMNS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
364 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S10-CL.100Column Rebar Installation 8 28-Mar-24 06-Apr-24 Column Rebar Installation

JAH-Z5-ST-S10-CL.105Column Formwork Installation 7 07-Apr-24 17-Apr-24 Column Formwork Installation

JAH-Z5-ST-S10-CL.110 Column Concrete Casting 1 18-Apr-24 18-Apr-24 Column Concrete Casting

JAH-Z5-ST-S10-CL.115 Form Work Removal and Curing 7 20-Apr-24 27-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 37 28-Mar-24 13-May-24 13-May-24, TUNNEL WALLS


JAH-Z5-ST-S10-TW.100Tunnel Walls Rebar Installation 8 28-Mar-24 06-Apr-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S10-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Mar-24 06-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S10-TW.105Tunnel Formwork Installation 7 07-Apr-24 17-Apr-24 Tunnel Formwork Installation

JAH-Z5-ST-S10-TW.110Tunnel Walls Concrete Casting 1 18-Apr-24 18-Apr-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S10-TW.115Curing work 7 20-Apr-24 27-Apr-24 Curing work

JAH-Z5-ST-S10-TW.120Tunnel Walls Formwork Removel 2 28-Apr-24 29-Apr-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S10-TW.125Tunnel Wall Waterproofing 12 30-Apr-24 13-May-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 30-Apr-24 03-Jun-24 03-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S10-MS.103Middle Slab Scaffold and Formwork Installation 5 30-Apr-24 05-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S10-MS.105Middle Slab Vertical Formwork Installation 7 06-May-24 13-May-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S10-MS.107Middle Slab Rebar Installation 8 14-May-24 22-May-24 Middle Slab Rebar Installation

JAH-Z5-ST-S10-MS.110Middle Slab Concrete Casting 1 23-May-24 23-May-24 Middle Slab Concrete Casting

JAH-Z5-ST-S10-MS.112Curing work 7 25-May-24 01-Jun-24 Curing work

JAH-Z5-ST-S10-MS.120Middle Slab Formwork Removel 2 02-Jun-24 03-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 04-Jun-24 07-Jul-24 07-Jul-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S10-UCW100
Utility Culvert Walls Rebar Installation 8 04-Jun-24 12-Jun-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S10-UCW105
Utility Culvert Walls Formwork Installation 7 13-Jun-24 25-Jun-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S10-UCW110
Utility Culvert Walls Concrete Casting 1 26-Jun-24 26-Jun-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S10-UCW112
Curing work 7 27-Jun-24 04-Jul-24 Curing work

JAH-Z5-ST-S10-UCW115
Utility Culvert Walls Walls Formwork Removel 2 06-Jul-24 07-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 08-Jul-24 19-Aug-24 19-Aug-24, TOP SLAB


JAH-Z5-ST-S10-TS.101 Top Slab Formwork Installation 7 08-Jul-24 15-Jul-24 Top Slab Formwork Installation

JAH-Z5-ST-S10-TS.102 Top Slab Rebar Installation 8 16-Jul-24 24-Jul-24 Top Slab Rebar Installation

JAH-Z5-ST-S10-TS.110 Top Slab Concrete Casting 1 25-Jul-24 25-Jul-24 Top Slab Concrete Casting

JAH-Z5-ST-S10-TS.112 Curing work 7 27-Jul-24 03-Aug-24 Curing work

JAH-Z5-ST-S10-TS.115 Top Slab Formwork Removel 2 04-Aug-24 05-Aug-24 Top Slab Formwork Removel

JAH-Z5-ST-S10-TS.120 Waterproofing for Top Slab 12 06-Aug-24 19-Aug-24 Waterproofing for Top Slab

FINISHING WORK 62 20-Aug-24 31-Oct-24 31-Oct-24, FINISHING WORK


JAH-Z5-ST-S10-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 20-Aug-24 27-Aug-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S10-FW.105Plain Concrete Casting 1 13-Oct-24 13-Oct-24 Plain Concrete Casting

JAH-Z5-ST-S10-FW.110Mass Concrete Casting for Base Slab Top Layer 1 14-Oct-24 14-Oct-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S10-FW.112Curing work 7 15-Oct-24 22-Oct-24 Curing work

JAH-Z5-ST-S10-FW.115Concrete Protective coating 8 23-Oct-24 31-Oct-24 Concrete Protective coating

STA. 1+953.979~ 1+968.979 204 19-Mar-24 20-Nov-24 20-Nov-24, STA. 1+953.979~ 1+968.979
BASE SLAB 27 19-Mar-24 22-Apr-24 22-Apr-24, BASE SLAB
JAH-Z5-ST-S11-BS.100 Lean Concrete for Base Slab 1 19-Mar-24 19-Mar-24 Lean Concrete for Base Slab

JAH-Z5-ST-S11-BS.105 Waterproofing for Lean Concrete 1 20-Mar-24 20-Mar-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S11-BS.110 Base Slab Rebar Installation 8 21-Mar-24 30-Mar-24 Base Slab Rebar Installation

JAH-Z5-ST-S11-BS.115 Base Slab Formwork Installation 7 31-Mar-24 07-Apr-24 Base Slab Formwork Installation

JAH-Z5-ST-S11-BS.120 Base Slab Concrete Casting 1 08-Apr-24 08-Apr-24 Base Slab Concrete Casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
365 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S11-BS.122 Curing work 7 13-Apr-24 20-Apr-24 Curing work

JAH-Z5-ST-S11-BS.125 Base Slab Formwork Removel 2 21-Apr-24 22-Apr-24 Base Slab Formwork Removel

COLUMNS 23 23-Apr-24 19-May-24 19-May-24, COLUMNS


JAH-Z5-ST-S11-CL.100 Column Rebar Installation 8 23-Apr-24 01-May-24 Column Rebar Installation

JAH-Z5-ST-S11-CL.105 Column Formwork Installation 7 02-May-24 09-May-24 Column Formwork Installation

JAH-Z5-ST-S11-CL.110 Column Concrete Casting 1 11-May-24 11-May-24 Column Concrete Casting

JAH-Z5-ST-S11-CL.115 Form Work Removal and Curing 7 12-May-24 19-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 23-Apr-24 04-Jun-24 04-Jun-24, TUNNEL WALLS


JAH-Z5-ST-S11-TW.100Tunnel Walls Rebar Installation 8 23-Apr-24 01-May-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S11-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 23-Apr-24 01-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S11-TW.105Tunnel Formwork Installation 7 02-May-24 09-May-24 Tunnel Formwork Installation

JAH-Z5-ST-S11-TW.110Tunnel Walls Concrete Casting 1 11-May-24 11-May-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S11-TW.115Curing work 7 12-May-24 19-May-24 Curing work

JAH-Z5-ST-S11-TW.120Tunnel Walls Formwork Removel 2 20-May-24 21-May-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S11-TW.125Tunnel Wall Waterproofing 12 22-May-24 04-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 22-May-24 30-Jun-24 30-Jun-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S11-MS.090Middle Slab Scaffold and Formwork Installation 5 22-May-24 27-May-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S11-MS.100Middle Slab Rebar Installation 8 28-May-24 05-Jun-24 Middle Slab Rebar Installation

JAH-Z5-ST-S11-MS.105Middle Slab Vertical Formwork Installation 7 06-Jun-24 13-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S11-MS.110Middle Slab Concrete Casting 1 19-Jun-24 19-Jun-24 Middle Slab Concrete Casting

JAH-Z5-ST-S11-MS.115Curing work 7 20-Jun-24 27-Jun-24 Curing work

JAH-Z5-ST-S11-MS.120Middle Slab Formwork Removel 2 29-Jun-24 30-Jun-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 01-Jul-24 29-Jul-24 29-Jul-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S11-UCW100
Utility Culvert Walls Rebar Installation 8 01-Jul-24 09-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S11-UCW105
Utility Culvert Walls Formwork Installation 7 10-Jul-24 17-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S11-UCW110
Utility Culvert Walls Concrete Casting 1 18-Jul-24 18-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S11-UCW112
Curing work 7 20-Jul-24 27-Jul-24 Curing work

JAH-Z5-ST-S11-UCW115
Utility Culvert Walls Walls Formwork Removel 2 28-Jul-24 29-Jul-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 30-Jul-24 10-Sep-24 10-Sep-24, TOP SLAB


JAH-Z5-ST-S11-TS.100 Top Slab Formwork Installation 7 30-Jul-24 06-Aug-24 Top Slab Formwork Installation

JAH-Z5-ST-S11-TS.102 Top Slab Rebar Installation 8 07-Aug-24 15-Aug-24 Top Slab Rebar Installation

JAH-Z5-ST-S11-TS.110 Top Slab Concrete Casting 1 17-Aug-24 17-Aug-24 Top Slab Concrete Casting

JAH-Z5-ST-S11-TS.112 Curing work 7 18-Aug-24 25-Aug-24 Curing work

JAH-Z5-ST-S11-TS.115 Top Slab Formwork Removel 2 26-Aug-24 27-Aug-24 Top Slab Formwork Removel

JAH-Z5-ST-S11-TS.120 Waterproofing for Top Slab 12 28-Aug-24 10-Sep-24 Waterproofing for Top Slab

FINISHING WORK 60 11-Sep-24 20-Nov-24 20-Nov-24, FINISHING WORK


JAH-Z5-ST-S11-FW.105Above Top Slab Formwork Installation for Plain Concrete 7 11-Sep-24 18-Sep-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S11-FW.110Plain Concrete Casting 1 02-Nov-24 02-Nov-24 Plain Concrete Casting

JAH-Z5-ST-S11-FW.115Mass Concrete Casting for Base Slab Top Layer 1 03-Nov-24 03-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S11-FW.117Curing work 7 04-Nov-24 11-Nov-24 Curing work

JAH-Z5-ST-S11-FW.120Concrete Protective coating 8 12-Nov-24 20-Nov-24 Concrete Protective coating

STA. 1+968.979 ~ 2+032.088 211 31-Mar-24 10-Dec-24 10-Dec-24, STA. 1+968.979 ~ 2+032.088
BASE SLAB 27 31-Mar-24 04-May-24 04-May-24, BASE SLAB
JAH-Z5-ST-S12-BS.100Lean Concrete for Base Slab 1 31-Mar-24 31-Mar-24 Lean Concrete for Base Slab

JAH-Z5-ST-S12-BS.105Waterproofing for Lean Concrete 1 01-Apr-24 01-Apr-24 Waterproofing for Lean Concrete

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
366 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S12-BS.110 Base Slab Rebar Installation 8 02-Apr-24 14-Apr-24 Base Slab Rebar Installation

JAH-Z5-ST-S12-BS.115 Base Slab Formwork Installation 7 15-Apr-24 22-Apr-24 Base Slab Formwork Installation

JAH-Z5-ST-S12-BS.120Base Slab Concrete Casting 1 23-Apr-24 23-Apr-24 Base Slab Concrete Casting

JAH-Z5-ST-S12-BS.122Curing work 7 24-Apr-24 01-May-24 Curing work

JAH-Z5-ST-S12-BS.125Base Slab Formwork Removel 2 02-May-24 04-May-24 Base Slab Formwork Removel

COLUMNS 23 05-May-24 30-May-24 30-May-24, COLUMNS


JAH-Z5-ST-S12-CL.100Column Rebar Installation 8 05-May-24 13-May-24 Column Rebar Installation

JAH-Z5-ST-S12-CL.105Column Formwork Installation 7 14-May-24 21-May-24 Column Formwork Installation

JAH-Z5-ST-S12-CL.110 Column Concrete Casting 1 22-May-24 22-May-24 Column Concrete Casting

JAH-Z5-ST-S12-CL.115 Form Work Removal and Curing 7 23-May-24 30-May-24 Form Work Removal and Curing

TUNNEL WALLS 37 05-May-24 20-Jun-24 20-Jun-24, TUNNEL WALLS


JAH-Z5-ST-S12-TW.100Tunnel Walls Rebar Installation 8 05-May-24 13-May-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S12-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 05-May-24 13-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S12-TW.105Tunnel Formwork Installation 7 14-May-24 21-May-24 Tunnel Formwork Installation

JAH-Z5-ST-S12-TW.110Tunnel Walls Concrete Casting 1 22-May-24 22-May-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S12-TW.115Curing work 7 23-May-24 30-May-24 Curing work

JAH-Z5-ST-S12-TW.120Tunnel Walls Formwork Removel 2 01-Jun-24 02-Jun-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S12-TW.125Tunnel Wall Waterproofing 12 03-Jun-24 20-Jun-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 03-Jun-24 11-Jul-24 11-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S12-MS.090Middle Slab Scaffold and Formwork Installation 5 03-Jun-24 08-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S12-MS.100Middle Slab Rebar Installation 8 09-Jun-24 22-Jun-24 Middle Slab Rebar Installation

JAH-Z5-ST-S12-MS.105Middle Slab Vertical Formwork Installation 7 23-Jun-24 30-Jun-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S12-MS.110Middle Slab Concrete Casting 1 01-Jul-24 01-Jul-24 Middle Slab Concrete Casting

JAH-Z5-ST-S12-MS.115Curing work 7 02-Jul-24 09-Jul-24 Curing work

JAH-Z5-ST-S12-MS.120Middle Slab Formwork Removel 2 10-Jul-24 11-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 13-Jul-24 10-Aug-24 10-Aug-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S12-UCW100
Utility Culvert Walls Rebar Installation 8 13-Jul-24 21-Jul-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S12-UCW105
Utility Culvert Walls Formwork Installation 7 22-Jul-24 29-Jul-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S12-UCW110
Utility Culvert Walls Concrete Casting 1 30-Jul-24 30-Jul-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S12-UCW112
Curing work 7 31-Jul-24 07-Aug-24 Curing work

JAH-Z5-ST-S12-UCW115
Utility Culvert Walls Walls Formwork Removel 2 08-Aug-24 10-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 11-Aug-24 22-Sep-24 22-Sep-24, TOP SLAB


JAH-Z5-ST-S12-TS.100 Top Slab Rebar Installation 8 11-Aug-24 19-Aug-24 Top Slab Rebar Installation

JAH-Z5-ST-S12-TS.105 Top Slab Formwork Installation 7 20-Aug-24 27-Aug-24 Top Slab Formwork Installation

JAH-Z5-ST-S12-TS.110 Top Slab Concrete Casting 1 28-Aug-24 28-Aug-24 Top Slab Concrete Casting

JAH-Z5-ST-S12-TS.112 Curing work 7 29-Aug-24 05-Sep-24 Curing work

JAH-Z5-ST-S12-TS.115 Top Slab Formwork Removel 2 07-Sep-24 08-Sep-24 Top Slab Formwork Removel

JAH-Z5-ST-S12-TS.120 Waterproofing for Top Slab 12 09-Sep-24 22-Sep-24 Waterproofing for Top Slab

FINISHING WORK 67 24-Sep-24 10-Dec-24 10-Dec-24, FINISHING WORK


JAH-Z5-ST-S12-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 24-Sep-24 01-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S12-FW.105Plain Concrete Casting 1 21-Nov-24 21-Nov-24 Plain Concrete Casting

JAH-Z5-ST-S12-FW.110Mass Concrete Casting for Base Slab Top Layer 1 23-Nov-24 23-Nov-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S12-FW.112Curing work 7 24-Nov-24 01-Dec-24 Curing work

JAH-Z5-ST-S12-FW.115Concrete Protective coating 8 02-Dec-24 10-Dec-24 Concrete Protective coating

STA. 2+032.088~ 2+052.088 218 15-Apr-24 30-Dec-24 30-Dec-24, STA. 2+032.088~ 2+052.088

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
367 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
BASE SLAB 27 15-Apr-24 15-May-24 15-May-24, BASE SLAB
JAH-Z5-ST-S13-BS.100Lean Concrete for Base Slab 1 15-Apr-24 15-Apr-24 Lean Concrete for Base Slab

JAH-Z5-ST-S13-BS.105Waterproofing for Lean Concrete 1 16-Apr-24 16-Apr-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S13-BS.110 Base Slab Rebar Installation 8 17-Apr-24 25-Apr-24 Base Slab Rebar Installation

JAH-Z5-ST-S13-BS.115 Base Slab Formwork Installation 7 27-Apr-24 04-May-24 Base Slab Formwork Installation

JAH-Z5-ST-S13-BS.120Base Slab Concrete Casting 1 05-May-24 05-May-24 Base Slab Concrete Casting

JAH-Z5-ST-S13-BS.122Curing work 7 06-May-24 13-May-24 Curing work

JAH-Z5-ST-S13-BS.125Base Slab Formwork Removel 2 14-May-24 15-May-24 Base Slab Formwork Removel

COLUMNS 23 16-May-24 11-Jun-24 11-Jun-24, COLUMNS


JAH-Z5-ST-S13-CL.100Column Rebar Installation 8 16-May-24 25-May-24 Column Rebar Installation

JAH-Z5-ST-S13-CL.105Column Formwork Installation 7 26-May-24 02-Jun-24 Column Formwork Installation

JAH-Z5-ST-S13-CL.110 Column Concrete Casting 1 03-Jun-24 03-Jun-24 Column Concrete Casting

JAH-Z5-ST-S13-CL.115 Form Work Removal and Curing 7 04-Jun-24 11-Jun-24 Form Work Removal and Curing

TUNNEL WALLS 37 16-May-24 02-Jul-24 02-Jul-24, TUNNEL WALLS


JAH-Z5-ST-S13-TW.100Tunnel Walls Rebar Installation 8 16-May-24 25-May-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S13-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 16-May-24 25-May-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S13-TW.105Tunnel Formwork Installation 7 26-May-24 02-Jun-24 Tunnel Formwork Installation

JAH-Z5-ST-S13-TW.110Tunnel Walls Concrete Casting 1 03-Jun-24 03-Jun-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S13-TW.115Curing work 7 04-Jun-24 11-Jun-24 Curing work

JAH-Z5-ST-S13-TW.120Tunnel Walls Formwork Removel 2 12-Jun-24 13-Jun-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S13-TW.125Tunnel Wall Waterproofing 12 19-Jun-24 02-Jul-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 19-Jun-24 23-Jul-24 23-Jul-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S13-MS.090Middle Slab Scaffold and Formwork Installation 5 19-Jun-24 24-Jun-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S13-MS.100Middle Slab Rebar Installation 8 25-Jun-24 03-Jul-24 Middle Slab Rebar Installation

JAH-Z5-ST-S13-MS.105Middle Slab Vertical Formwork Installation 7 04-Jul-24 11-Jul-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S13-MS.110Middle Slab Concrete Casting 1 13-Jul-24 13-Jul-24 Middle Slab Concrete Casting

JAH-Z5-ST-S13-MS.115Curing work 7 14-Jul-24 21-Jul-24 Curing work

JAH-Z5-ST-S13-MS.120Middle Slab Formwork Removel 2 22-Jul-24 23-Jul-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 24-Jul-24 21-Aug-24 21-Aug-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S13-UCW100
Utility Culvert Walls Rebar Installation 8 24-Jul-24 01-Aug-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S13-UCW105
Utility Culvert Walls Formwork Installation 7 03-Aug-24 10-Aug-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S13-UCW110
Utility Culvert Walls Concrete Casting 1 11-Aug-24 11-Aug-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S13-UCW112
Curing work 7 12-Aug-24 19-Aug-24 Curing work

JAH-Z5-ST-S13-UCW115
Utility Culvert Walls Walls Formwork Removel 2 20-Aug-24 21-Aug-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 22-Aug-24 05-Oct-24 05-Oct-24, TOP SLAB


JAH-Z5-ST-S13-TS.100 Top Slab Rebar Installation 8 22-Aug-24 31-Aug-24 Top Slab Rebar Installation

JAH-Z5-ST-S13-TS.105 Top Slab Formwork Installation 7 01-Sep-24 08-Sep-24 Top Slab Formwork Installation

JAH-Z5-ST-S13-TS.110 Top Slab Concrete Casting 1 09-Sep-24 09-Sep-24 Top Slab Concrete Casting

JAH-Z5-ST-S13-TS.112 Curing work 7 10-Sep-24 17-Sep-24 Curing work

JAH-Z5-ST-S13-TS.115 Top Slab Formwork Removel 2 18-Sep-24 19-Sep-24 Top Slab Formwork Removel

JAH-Z5-ST-S13-TS.120 Waterproofing for Top Slab 12 21-Sep-24 05-Oct-24 Waterproofing for Top Slab

FINISHING WORK 74 06-Oct-24 30-Dec-24 30-Dec-24, FINISHING WORK


JAH-Z5-ST-S13-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 06-Oct-24 13-Oct-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S13-FW.105Plain Concrete Casting 1 11-Dec-24 11-Dec-24 Plain Concrete Casting

JAH-Z5-ST-S13-FW.110Mass Concrete Casting for Base Slab Top Layer 1 12-Dec-24 12-Dec-24 Mass Concrete Casting for Base Slab Top Layer

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
368 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S13-FW.112Curing work 7 14-Dec-24 21-Dec-24 Curing work

JAH-Z5-ST-S13-FW.115Concrete Protective coating 8 22-Dec-24 30-Dec-24 Concrete Protective coating

STA. 2+052.088~ 2+072.088 194 02-Jun-24 19-Jan-25 19-Jan-25, STA. 2+052.088~ 2+072.088
BASE SLAB 27 02-Jun-24 07-Jul-24 07-Jul-24, BASE SLAB
JAH-Z5-ST-S14-BS.100Lean Concrete for Base Slab 1 02-Jun-24 02-Jun-24 Lean Concrete for Base Slab

JAH-Z5-ST-S14-BS.105Waterproofing for Lean Concrete 1 03-Jun-24 03-Jun-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S14-BS.110 Base Slab Rebar Installation 8 04-Jun-24 12-Jun-24 Base Slab Rebar Installation

JAH-Z5-ST-S14-BS.115 Base Slab Formwork Installation 7 13-Jun-24 25-Jun-24 Base Slab Formwork Installation

JAH-Z5-ST-S14-BS.120Base Slab Concrete Casting 1 26-Jun-24 26-Jun-24 Base Slab Concrete Casting

JAH-Z5-ST-S14-BS.122Curing work 7 27-Jun-24 04-Jul-24 Curing work

JAH-Z5-ST-S14-BS.125Base Slab Formwork Removel 2 06-Jul-24 07-Jul-24 Base Slab Formwork Removel

COLUMNS 23 08-Jul-24 03-Aug-24 03-Aug-24, COLUMNS


JAH-Z5-ST-S14-CL.100Column Rebar Installation 8 08-Jul-24 16-Jul-24 Column Rebar Installation

JAH-Z5-ST-S14-CL.105Column Formwork Installation 7 17-Jul-24 24-Jul-24 Column Formwork Installation

JAH-Z5-ST-S14-CL.110 Column Concrete Casting 1 25-Jul-24 25-Jul-24 Column Concrete Casting

JAH-Z5-ST-S14-CL.115 Form Work Removal and Curing 7 27-Jul-24 03-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 08-Jul-24 19-Aug-24 19-Aug-24, TUNNEL WALLS


JAH-Z5-ST-S14-TW.100Tunnel Walls Rebar Installation 8 08-Jul-24 16-Jul-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S14-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 08-Jul-24 16-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S14-TW.105Tunnel Formwork Installation 7 17-Jul-24 24-Jul-24 Tunnel Formwork Installation

JAH-Z5-ST-S14-TW.110Tunnel Walls Concrete Casting 1 25-Jul-24 25-Jul-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S14-TW.112Curing work 7 27-Jul-24 03-Aug-24 Curing work

JAH-Z5-ST-S14-TW.120Tunnel Walls Formwork Removel 2 04-Aug-24 05-Aug-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S14-TW.125Tunnel Wall Waterproofing 12 06-Aug-24 19-Aug-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 06-Aug-24 09-Sep-24 09-Sep-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S14-MS.090Middle Slab Scaffold and Formwork Installation 5 06-Aug-24 11-Aug-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S14-MS.100Middle Slab Rebar Installation 8 12-Aug-24 20-Aug-24 Middle Slab Rebar Installation

JAH-Z5-ST-S14-MS.105Middle Slab Vertical Formwork Installation 7 21-Aug-24 28-Aug-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S14-MS.110Middle Slab Concrete Casting 1 29-Aug-24 29-Aug-24 Middle Slab Concrete Casting

JAH-Z5-ST-S14-MS.115Curing work 7 31-Aug-24 07-Sep-24 Curing work

JAH-Z5-ST-S14-MS.120Middle Slab Formwork Removel 2 08-Sep-24 09-Sep-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 10-Sep-24 09-Oct-24 09-Oct-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S14-UCW100
Utility Culvert Walls Rebar Installation 8 10-Sep-24 18-Sep-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S14-UCW105
Utility Culvert Walls Formwork Installation 7 19-Sep-24 28-Sep-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S14-UCW110
Utility Culvert Walls Concrete Casting 1 29-Sep-24 29-Sep-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S14-UCW112
Curing work 7 30-Sep-24 07-Oct-24 Curing work

JAH-Z5-ST-S14-UCW115
Utility Culvert Walls Walls Formwork Removel 2 08-Oct-24 09-Oct-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 10-Oct-24 21-Nov-24 21-Nov-24, TOP SLAB


JAH-Z5-ST-S14-TS.100 Top Slab Rebar Installation 8 10-Oct-24 19-Oct-24 Top Slab Rebar Installation

JAH-Z5-ST-S14-TS.105 Top Slab Formwork Installation 7 20-Oct-24 27-Oct-24 Top Slab Formwork Installation

JAH-Z5-ST-S14-TS.110 Top Slab Concrete Casting 1 28-Oct-24 28-Oct-24 Top Slab Concrete Casting

JAH-Z5-ST-S14-TS.112 Curing work 7 29-Oct-24 05-Nov-24 Curing work

JAH-Z5-ST-S14-TS.115 Top Slab Formwork Removel 2 06-Nov-24 07-Nov-24 Top Slab Formwork Removel

JAH-Z5-ST-S14-TS.120 Waterproofing for Top Slab 12 09-Nov-24 21-Nov-24 Waterproofing for Top Slab

FINISHING WORK 50 23-Nov-24 19-Jan-25 19-Jan-25, FINISHING WORK

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
369 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S14-FW100 Above Top Slab Formwork Installation for Plain Concrete 7 23-Nov-24 30-Nov-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S14-FW105 Plain Concrete Casting 1 31-Dec-24 31-Dec-24 Plain Concrete Casting

JAH-Z5-ST-S14-FW110 Mass Concrete Casting for Base Slab Top Layer 1 01-Jan-25 01-Jan-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S14-FW112 Curing work 7 02-Jan-25 09-Jan-25 Curing work

JAH-Z5-ST-S14-FW115 Concrete Protective coating 8 11-Jan-25 19-Jan-25 Concrete Protective coating

STA. 2+072.088~ 2+092.088 168 03-Jun-24 21-Dec-24 21-Dec-24, STA. 2+072.088~ 2+092.088
BASE SLAB 27 03-Jun-24 08-Jul-24 08-Jul-24, BASE SLAB
JAH-Z5-ST-S15-BS.100Lean Concrete for Base Slab 1 03-Jun-24 03-Jun-24 Lean Concrete for Base Slab

JAH-Z5-ST-S15-BS.105Waterproofing for Lean Concrete 1 04-Jun-24 04-Jun-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S15-BS.110 Base Slab Rebar Installation 8 05-Jun-24 13-Jun-24 Base Slab Rebar Installation

JAH-Z5-ST-S15-BS.115 Base Slab Formwork Installation 7 19-Jun-24 26-Jun-24 Base Slab Formwork Installation

JAH-Z5-ST-S15-BS.120Base Slab Concrete Casting 1 27-Jun-24 27-Jun-24 Base Slab Concrete Casting

JAH-Z5-ST-S15-BS.122Curing work 7 29-Jun-24 06-Jul-24 Curing work

JAH-Z5-ST-S15-BS.125Base Slab Formwork Removel 2 07-Jul-24 08-Jul-24 Base Slab Formwork Removel

COLUMNS 23 09-Jul-24 04-Aug-24 04-Aug-24, COLUMNS


JAH-Z5-ST-S15-CL.100Column Rebar Installation 8 09-Jul-24 17-Jul-24 Column Rebar Installation

JAH-Z5-ST-S15-CL.105Column Formwork Installation 7 18-Jul-24 25-Jul-24 Column Formwork Installation

JAH-Z5-ST-S15-CL.110 Column Concrete Casting 1 27-Jul-24 27-Jul-24 Column Concrete Casting

JAH-Z5-ST-S15-CL.115 Form Work Removal and Curing 7 28-Jul-24 04-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 09-Jul-24 20-Aug-24 20-Aug-24, TUNNEL WALLS


JAH-Z5-ST-S15-TW.100Tunnel Walls Rebar Installation 8 09-Jul-24 17-Jul-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S15-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 09-Jul-24 17-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S15-TW.105Tunnel Formwork Installation 7 18-Jul-24 25-Jul-24 Tunnel Formwork Installation

JAH-Z5-ST-S15-TW.110Tunnel Walls Concrete Casting 1 27-Jul-24 27-Jul-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S15-TW.115Curing work 7 28-Jul-24 04-Aug-24 Curing work

JAH-Z5-ST-S15-TW.120Tunnel Walls Formwork Removel 2 05-Aug-24 06-Aug-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S15-TW.125Tunnel Wall Waterproofing 12 07-Aug-24 20-Aug-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 07-Aug-24 10-Sep-24 10-Sep-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S15-MS.090Middle Slab Scaffold and Formwork Installation 5 07-Aug-24 12-Aug-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S15-MS.100Middle Slab Rebar Installation 8 13-Aug-24 21-Aug-24 Middle Slab Rebar Installation

JAH-Z5-ST-S15-MS.105Middle Slab Vertical Formwork Installation 7 22-Aug-24 29-Aug-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S15-MS.110Middle Slab Concrete Casting 1 31-Aug-24 31-Aug-24 Middle Slab Concrete Casting

JAH-Z5-ST-S15-MS.115Curing work 7 01-Sep-24 08-Sep-24 Curing work

JAH-Z5-ST-S15-MS.120Middle Slab Formwork Removel 2 09-Sep-24 10-Sep-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 11-Sep-24 10-Oct-24 10-Oct-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S15-UCW100
Utility Culvert Walls Rebar Installation 8 11-Sep-24 19-Sep-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S15-UCW105
Utility Culvert Walls Formwork Installation 7 21-Sep-24 29-Sep-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S15-UCW110
Utility Culvert Walls Concrete Casting 1 30-Sep-24 30-Sep-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S15-UCW112
Curing work 7 01-Oct-24 08-Oct-24 Curing work

JAH-Z5-ST-S15-UCW115
Utility Culvert Walls Walls Formwork Removel 2 09-Oct-24 10-Oct-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 12-Oct-24 23-Nov-24 23-Nov-24, TOP SLAB


JAH-Z5-ST-S15-TS.100 Top Slab Rebar Installation 8 12-Oct-24 20-Oct-24 Top Slab Rebar Installation

JAH-Z5-ST-S15-TS.105 Top Slab Formwork Installation 7 21-Oct-24 28-Oct-24 Top Slab Formwork Installation

JAH-Z5-ST-S15-TS.110 Top Slab Concrete Casting 1 29-Oct-24 29-Oct-24 Top Slab Concrete Casting

JAH-Z5-ST-S15-TS.112 Curing work 7 30-Oct-24 06-Nov-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
370 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S15-TS.115 Top Slab Formwork Removel 2 07-Nov-24 09-Nov-24 Top Slab Formwork Removel

JAH-Z5-ST-S15-TS.120 Waterproofing for Top Slab 12 10-Nov-24 23-Nov-24 Waterproofing for Top Slab

FINISHING WORK 24 24-Nov-24 21-Dec-24 21-Dec-24, FINISHING WORK


JAH-Z5-ST-S15-FW100 Above Top Slab Formwork Installation for Plain Concrete 7 24-Nov-24 01-Dec-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S15-FW105 Plain Concrete Casting 1 02-Dec-24 02-Dec-24 Plain Concrete Casting

JAH-Z5-ST-S15-FW110 Mass Concrete Casting for Base Slab Top Layer 1 03-Dec-24 03-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S15-FW112 Curing work 7 04-Dec-24 11-Dec-24 Curing work

JAH-Z5-ST-S15-FW115 Concrete Protective coating 8 12-Dec-24 21-Dec-24 Concrete Protective coating

STA. 2+092.088~ 2+112.088 175 19-Jun-24 09-Jan-25 09-Jan-25, STA. 2+092.088~ 2+112.088
BASE SLAB 27 19-Jun-24 20-Jul-24 20-Jul-24, BASE SLAB
JAH-Z5-ST-S16-BS.100Lean Concrete for Base Slab 1 19-Jun-24 19-Jun-24 Lean Concrete for Base Slab

JAH-Z5-ST-S16-BS.105Waterproofing for Lean Concrete 1 20-Jun-24 20-Jun-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S16-BS.110 Base Slab Rebar Installation 8 22-Jun-24 30-Jun-24 Base Slab Rebar Installation

JAH-Z5-ST-S16-BS.115 Base Slab Formwork Installation 7 01-Jul-24 08-Jul-24 Base Slab Formwork Installation

JAH-Z5-ST-S16-BS.120Base Slab Concrete Casting 1 09-Jul-24 09-Jul-24 Base Slab Concrete Casting

JAH-Z5-ST-S16-BS.122Curing work 7 10-Jul-24 17-Jul-24 Curing work

JAH-Z5-ST-S16-BS.125Base Slab Formwork Removel 2 18-Jul-24 20-Jul-24 Base Slab Formwork Removel

COLUMNS 23 21-Jul-24 15-Aug-24 15-Aug-24, COLUMNS


JAH-Z5-ST-S16-CL.100Column Rebar Installation 8 21-Jul-24 29-Jul-24 Column Rebar Installation

JAH-Z5-ST-S16-CL.105Column Formwork Installation 7 30-Jul-24 06-Aug-24 Column Formwork Installation

JAH-Z5-ST-S16-CL.110 Column Concrete Casting 1 07-Aug-24 07-Aug-24 Column Concrete Casting

JAH-Z5-ST-S16-CL.115 Form Work Removal and Curing 7 08-Aug-24 15-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 21-Jul-24 01-Sep-24 01-Sep-24, TUNNEL WALLS


JAH-Z5-ST-S16-TW.100Tunnel Walls Rebar Installation 8 21-Jul-24 29-Jul-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S16-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 21-Jul-24 29-Jul-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S16-TW.105Tunnel Formwork Installation 7 30-Jul-24 06-Aug-24 Tunnel Formwork Installation

JAH-Z5-ST-S16-TW.110Tunnel Walls Concrete Casting 1 07-Aug-24 07-Aug-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S16-TW.112Curing work 7 08-Aug-24 15-Aug-24 Curing work

JAH-Z5-ST-S16-TW.120Tunnel Walls Formwork Removel 2 17-Aug-24 18-Aug-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S16-TW.125Tunnel Wall Waterproofing 12 19-Aug-24 01-Sep-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 19-Aug-24 22-Sep-24 22-Sep-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S16-MS.090Middle Slab Scaffold and Formwork Installation 5 19-Aug-24 24-Aug-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S16-MS.100Middle Slab Rebar Installation 8 25-Aug-24 02-Sep-24 Middle Slab Rebar Installation

JAH-Z5-ST-S16-MS.105Middle Slab Vertical Formwork Installation 7 03-Sep-24 10-Sep-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S16-MS.110Middle Slab Concrete Casting 1 11-Sep-24 11-Sep-24 Middle Slab Concrete Casting

JAH-Z5-ST-S16-MS.115Curing work 7 12-Sep-24 19-Sep-24 Curing work

JAH-Z5-ST-S16-MS.120Middle Slab Formwork Removel 2 21-Sep-24 22-Sep-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 24-Sep-24 22-Oct-24 22-Oct-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S16-UCW100
Utility Culvert Walls Rebar Installation 8 24-Sep-24 02-Oct-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S16-UCW105
Utility Culvert Walls Formwork Installation 7 03-Oct-24 10-Oct-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S16-UCW110
Utility Culvert Walls Concrete Casting 1 12-Oct-24 12-Oct-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S16-UCW112
Curing work 7 13-Oct-24 20-Oct-24 Curing work

JAH-Z5-ST-S16-UCW115
Utility Culvert Walls Walls Formwork Removel 2 21-Oct-24 22-Oct-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 23-Oct-24 04-Dec-24 04-Dec-24, TOP SLAB


JAH-Z5-ST-S16-TS.100 Top Slab Rebar Installation 8 23-Oct-24 31-Oct-24 Top Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
371 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S16-TS.105 Top Slab Formwork Installation 7 02-Nov-24 09-Nov-24 Top Slab Formwork Installation

JAH-Z5-ST-S16-TS.110 Top Slab Concrete Casting 1 10-Nov-24 10-Nov-24 Top Slab Concrete Casting

JAH-Z5-ST-S16-TS.112 Curing work 7 11-Nov-24 18-Nov-24 Curing work

JAH-Z5-ST-S16-TS.115 Top Slab Formwork Removel 2 19-Nov-24 20-Nov-24 Top Slab Formwork Removel

JAH-Z5-ST-S16-TS.120 Waterproofing for Top Slab 12 21-Nov-24 04-Dec-24 Waterproofing for Top Slab

FINISHING WORK 31 05-Dec-24 09-Jan-25 09-Jan-25, FINISHING WORK


JAH-Z5-ST-S16-FW100 Above Top Slab Formwork Installation for Plain Concrete 7 05-Dec-24 12-Dec-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S16-FW105 Plain Concrete Casting 1 22-Dec-24 22-Dec-24 Plain Concrete Casting

JAH-Z5-ST-S16-FW110 Mass Concrete Casting for Base Slab Top Layer 1 23-Dec-24 23-Dec-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S16-FW112 Curing work 7 24-Dec-24 31-Dec-24 Curing work

JAH-Z5-ST-S16-FW115 Concrete Protective coating 8 01-Jan-25 09-Jan-25 Concrete Protective coating

STA. 2+112.088~ 2+132.088 219 01-Jul-24 13-Mar-25 13-Mar-25, STA. 2+112.088~ 2+132.088
BASE SLAB 27 01-Jul-24 31-Jul-24 31-Jul-24, BASE SLAB
JAH-Z5-ST-S17-BS.100Lean Concrete for Base Slab 1 01-Jul-24 01-Jul-24 Lean Concrete for Base Slab

JAH-Z5-ST-S17-BS.105Waterproofing for Lean Concrete 1 02-Jul-24 02-Jul-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S17-BS.110 Base Slab Rebar Installation 8 03-Jul-24 11-Jul-24 Base Slab Rebar Installation

JAH-Z5-ST-S17-BS.115 Base Slab Formwork Installation 7 13-Jul-24 20-Jul-24 Base Slab Formwork Installation

JAH-Z5-ST-S17-BS.120Base Slab Concrete Casting 1 21-Jul-24 21-Jul-24 Base Slab Concrete Casting

JAH-Z5-ST-S17-BS.122Curing work 7 22-Jul-24 29-Jul-24 Curing work

JAH-Z5-ST-S17-BS.125Base Slab Formwork Removel 2 30-Jul-24 31-Jul-24 Base Slab Formwork Removel

COLUMNS 23 01-Aug-24 27-Aug-24 27-Aug-24, COLUMNS


JAH-Z5-ST-S17-CL.100Column Rebar Installation 8 01-Aug-24 10-Aug-24 Column Rebar Installation

JAH-Z5-ST-S17-CL.105Column Formwork Installation 7 11-Aug-24 18-Aug-24 Column Formwork Installation

JAH-Z5-ST-S17-CL.110 Column Concrete Casting 1 19-Aug-24 19-Aug-24 Column Concrete Casting

JAH-Z5-ST-S17-CL.115 Form Work Removal and Curing 7 20-Aug-24 27-Aug-24 Form Work Removal and Curing

TUNNEL WALLS 37 01-Aug-24 12-Sep-24 12-Sep-24, TUNNEL WALLS


JAH-Z5-ST-S17-TW.100Tunnel Walls Rebar Installation 8 01-Aug-24 10-Aug-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S17-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 01-Aug-24 10-Aug-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S17-TW.105Tunnel Formwork Installation 7 11-Aug-24 18-Aug-24 Tunnel Formwork Installation

JAH-Z5-ST-S17-TW.110Tunnel Walls Concrete Casting 1 19-Aug-24 19-Aug-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S17-TW.112Curing work 7 20-Aug-24 27-Aug-24 Curing work

JAH-Z5-ST-S17-TW.120Tunnel Walls Formwork Removel 2 28-Aug-24 29-Aug-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S17-TW.125Tunnel Wall Waterproofing 12 31-Aug-24 12-Sep-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 31-Aug-24 05-Oct-24 05-Oct-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S17-MS.090Middle Slab Scaffold and Formwork Installation 5 31-Aug-24 04-Sep-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S17-MS.100Middle Slab Rebar Installation 8 05-Sep-24 14-Sep-24 Middle Slab Rebar Installation

JAH-Z5-ST-S17-MS.105Middle Slab Vertical Formwork Installation 7 15-Sep-24 22-Sep-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S17-MS.110Middle Slab Concrete Casting 1 24-Sep-24 24-Sep-24 Middle Slab Concrete Casting

JAH-Z5-ST-S17-MS.115Curing work 7 25-Sep-24 02-Oct-24 Curing work

JAH-Z5-ST-S17-MS.120Middle Slab Formwork Removel 2 03-Oct-24 05-Oct-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 06-Oct-24 03-Nov-24 03-Nov-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S17-UCW100
Utility Culvert Walls Rebar Installation 8 06-Oct-24 14-Oct-24 Utility Culvert Walls Rebar Installation

JAH-Z5-ST-S17-UCW105
Utility Culvert Walls Formwork Installation 7 15-Oct-24 22-Oct-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S17-UCW110
Utility Culvert Walls Concrete Casting 1 23-Oct-24 23-Oct-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S17-UCW112
Curing work 7 24-Oct-24 31-Oct-24 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
372 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S17-UCW115
Utility Culvert Walls Walls Formwork Removel 2 02-Nov-24 03-Nov-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 88 04-Nov-24 13-Feb-25 13-Feb-25, TOP SLAB


JAH-Z5-ST-S17-TS.100 Top Slab Rebar Installation 8 04-Nov-24 12-Nov-24 Top Slab Rebar Installation

JAH-Z5-ST-S17-TS.105 Top Slab Formwork Installation 7 13-Nov-24 20-Nov-24 Top Slab Formwork Installation

JAH-Z5-ST-S17-TS.110 Top Slab Concrete Casting 1 20-Jan-25 20-Jan-25 Top Slab Concrete Casting

JAH-Z5-ST-S17-TS.112 Curing work 7 21-Jan-25 28-Jan-25 Curing work

JAH-Z5-ST-S17-TS.115 Top Slab Formwork Removel 2 29-Jan-25 30-Jan-25 Top Slab Formwork Removel

JAH-Z5-ST-S17-TS.120 Waterproofing for Top Slab 12 01-Feb-25 13-Feb-25 Waterproofing for Top Slab

FINISHING WORK 24 15-Feb-25 13-Mar-25 13-Mar-25, FINISHING WORK


JAH-Z5-ST-S17-FW100 Above Top Slab Formwork Installation for Plain Concrete 7 15-Feb-25 22-Feb-25 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S17-FW105 Plain Concrete Casting 1 23-Feb-25 23-Feb-25 Plain Concrete Casting

JAH-Z5-ST-S17-FW110 Mass Concrete Casting for Base Slab Top Layer 1 24-Feb-25 24-Feb-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S17-FW112 Curing work 7 25-Feb-25 04-Mar-25 Curing work

JAH-Z5-ST-S17-FW115 Concrete Protective coating 8 05-Mar-25 13-Mar-25 Concrete Protective coating

STA. 2+132.088~ 2+157.088 217 13-Jul-24 23-Mar-25 23-Mar-25, STA. 2+132.088~ 2+157.088
BASE SLAB 27 13-Jul-24 12-Aug-24 12-Aug-24, BASE SLAB
JAH-Z5-ST-S18-BS.100Lean Concrete for Base Slab 1 13-Jul-24 13-Jul-24 Lean Concrete for Base Slab

JAH-Z5-ST-S18-BS.105Waterproofing for Lean Concrete 1 14-Jul-24 14-Jul-24 Waterproofing for Lean Concrete

JAH-Z5-ST-S18-BS.110 Base Slab Rebar Installation 8 15-Jul-24 23-Jul-24 Base Slab Rebar Installation

JAH-Z5-ST-S18-BS.115 Base Slab Formwork Installation 7 24-Jul-24 31-Jul-24 Base Slab Formwork Installation

JAH-Z5-ST-S18-BS.120Base Slab Concrete Casting 1 01-Aug-24 01-Aug-24 Base Slab Concrete Casting

JAH-Z5-ST-S18-BS.122Curing work 7 03-Aug-24 10-Aug-24 Curing work

JAH-Z5-ST-S18-BS.125Base Slab Formwork Removel 2 11-Aug-24 12-Aug-24 Base Slab Formwork Removel

COLUMNS 23 13-Aug-24 08-Sep-24 08-Sep-24, COLUMNS


JAH-Z5-ST-S18-CL.100Column Rebar Installation 8 13-Aug-24 21-Aug-24 Column Rebar Installation

JAH-Z5-ST-S18-CL.105Column Formwork Installation 7 22-Aug-24 29-Aug-24 Column Formwork Installation

JAH-Z5-ST-S18-CL.110 Column Concrete Casting 1 31-Aug-24 31-Aug-24 Column Concrete Casting

JAH-Z5-ST-S18-CL.115 Form Work Removal and Curing 7 01-Sep-24 08-Sep-24 Form Work Removal and Curing

TUNNEL WALLS 37 13-Aug-24 25-Sep-24 25-Sep-24, TUNNEL WALLS


JAH-Z5-ST-S18-TW.100Tunnel Walls Rebar Installation 8 13-Aug-24 21-Aug-24 Tunnel Walls Rebar Installation

JAH-Z5-ST-S18-TW.102PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 13-Aug-24 21-Aug-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z5-ST-S18-TW.105Tunnel Formwork Installation 7 22-Aug-24 29-Aug-24 Tunnel Formwork Installation

JAH-Z5-ST-S18-TW.110Tunnel Walls Concrete Casting 1 31-Aug-24 31-Aug-24 Tunnel Walls Concrete Casting

JAH-Z5-ST-S18-TW.115Curing work 7 01-Sep-24 08-Sep-24 Curing work

JAH-Z5-ST-S18-TW.120Tunnel Walls Formwork Removel 2 09-Sep-24 10-Sep-24 Tunnel Walls Formwork Removel

JAH-Z5-ST-S18-TW.125Tunnel Wall Waterproofing 12 11-Sep-24 25-Sep-24 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 30 11-Sep-24 16-Oct-24 16-Oct-24, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z5-ST-S18-MS.090Middle Slab Scaffold and Formwork Installation 5 11-Sep-24 16-Sep-24 Middle Slab Scaffold and Formwork Installation

JAH-Z5-ST-S18-MS.100Middle Slab Rebar Installation 8 17-Sep-24 26-Sep-24 Middle Slab Rebar Installation

JAH-Z5-ST-S18-MS.105Middle Slab Vertical Formwork Installation 7 28-Sep-24 05-Oct-24 Middle Slab Vertical Formwork Installation

JAH-Z5-ST-S18-MS.110Middle Slab Concrete Casting 1 06-Oct-24 06-Oct-24 Middle Slab Concrete Casting

JAH-Z5-ST-S18-MS.115Curing work 7 07-Oct-24 14-Oct-24 Curing work

JAH-Z5-ST-S18-MS.120Middle Slab Formwork Removel 2 15-Oct-24 16-Oct-24 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 17-Oct-24 14-Nov-24 14-Nov-24, UTILITY CULVERT WALLS


JAH-Z5-ST-S18-UCW100
Utility Culvert Walls Rebar Installation 8 17-Oct-24 26-Oct-24 Utility Culvert Walls Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
373 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ST-S18-UCW105
Utility Culvert Walls Formwork Installation 7 27-Oct-24 03-Nov-24 Utility Culvert Walls Formwork Installation

JAH-Z5-ST-S18-UCW110
Utility Culvert Walls Concrete Casting 1 04-Nov-24 04-Nov-24 Utility Culvert Walls Concrete Casting

JAH-Z5-ST-S18-UCW112
Curing work 7 05-Nov-24 12-Nov-24 Curing work

JAH-Z5-ST-S18-UCW115
Utility Culvert Walls Walls Formwork Removel 2 13-Nov-24 14-Nov-24 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 37 16-Nov-24 28-Dec-24 28-Dec-24, TOP SLAB


JAH-Z5-ST-S18-TS.100 Top Slab Rebar Installation 8 16-Nov-24 24-Nov-24 Top Slab Rebar Installation

JAH-Z5-ST-S18-TS.105 Top Slab Formwork Installation 7 25-Nov-24 02-Dec-24 Top Slab Formwork Installation

JAH-Z5-ST-S18-TS.110 Top Slab Concrete Casting 1 03-Dec-24 03-Dec-24 Top Slab Concrete Casting

JAH-Z5-ST-S18-TS.112 Curing work 7 04-Dec-24 11-Dec-24 Curing work

JAH-Z5-ST-S18-TS.115 Top Slab Formwork Removel 2 12-Dec-24 14-Dec-24 Top Slab Formwork Removel

JAH-Z5-ST-S18-TS.120 Waterproofing for Top Slab 12 15-Dec-24 28-Dec-24 Waterproofing for Top Slab

FINISHING WORK 73 29-Dec-24 23-Mar-25 23-Mar-25, FINISHING WORK


JAH-Z5-ST-S18-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 29-Dec-24 05-Jan-25 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z5-ST-S18-FW.105Plain Concrete Casting 1 06-Jan-25 06-Jan-25 Plain Concrete Casting

JAH-Z5-ST-S18-FW.110Mass Concrete Casting for Base Slab Top Layer 1 07-Jan-25 07-Jan-25 Mass Concrete Casting for Base Slab Top Layer

JAH-Z5-ST-S18-FW.112Curing work 7 08-Jan-25 15-Jan-25 Curing work

JAH-Z5-ST-S18-FW.115Concrete Protective coating 8 15-Mar-25 23-Mar-25 Concrete Protective coating

EGRESS STAIR-8 (ZONE-5) 236 26-Nov-23 03-Sep-24 03-Sep-24, EGRESS STAIR-8 (ZONE-5)
WALL AND 1ST FLIGHT 31 26-Nov-23 31-Dec-23 31-Dec-23, WALL AND 1ST FLIGHT
Z5-EGR-STAIR#8.100 Excavation for Foundation 6 26-Nov-23 02-Dec-23 Excavation for Foundation

Z5-EGR-STAIR#8.105 Foundation Blinding Concrete casting 1 03-Dec-23 03-Dec-23 Foundation Blinding Concrete casting

Z5-EGR-STAIR#8.110 Foundation Rebar Installation 3 04-Dec-23 06-Dec-23 Foundation Rebar Installation

Z5-EGR-STAIR#8.115 Foundation Formwork installation 3 07-Dec-23 10-Dec-23 Foundation Formwork installation

Z5-EGR-STAIR#8.120 Foundation Concrete casting 1 11-Dec-23 11-Dec-23 Foundation Concrete casting

Z5-EGR-STAIR#8.125 Wall and Stair Rebar Installation 4 12-Dec-23 16-Dec-23 Wall and Stair Rebar Installation

Z5-EGR-STAIR#8.130 Wall and Stair Form work Installation 6 17-Dec-23 23-Dec-23 Wall and Stair Form work Installation

Z5-EGR-STAIR#8.135 Form Removal and Curing 7 24-Dec-23 31-Dec-23 Form Removal and Curing

WALL AND 2ND FLIGHT 17 01-Jan-24 20-Jan-24 20-Jan-24, WALL AND 2ND FLIGHT
Z5-EGR-STAIR#8.140 Stair Form work Installation 3 01-Jan-24 03-Jan-24 Stair Form work Installation

Z5-EGR-STAIR#8.145 Wall Rebar Installation 3 04-Jan-24 07-Jan-24 Wall Rebar Installation

Z5-EGR-STAIR#8.150 Wall Form work Installation 3 08-Jan-24 10-Jan-24 Wall Form work Installation

Z5-EGR-STAIR#8.155 Wall and Stair Concrete casting 1 11-Jan-24 11-Jan-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.160 Form Removal and Curing 7 13-Jan-24 20-Jan-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 21-Jan-24 08-Feb-24 08-Feb-24, WALL AND 3RD FLIGHT
Z5-EGR-STAIR#8.165 Stair Form work Installation 3 21-Jan-24 23-Jan-24 Stair Form work Installation

Z5-EGR-STAIR#8.170 Wall Rebar Installation 3 24-Jan-24 27-Jan-24 Wall Rebar Installation

Z5-EGR-STAIR#8.175 Wall Form work Installation 3 28-Jan-24 30-Jan-24 Wall Form work Installation

Z5-EGR-STAIR#8.180 Wall and Stair Concrete casting 1 31-Jan-24 31-Jan-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.185 Form Removal and Curing 7 01-Feb-24 08-Feb-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 10-Feb-24 28-Feb-24 28-Feb-24, WALL AND 4TH FLIGHT
Z5-EGR-STAIR#8.190 Stair Form work Installation 3 10-Feb-24 12-Feb-24 Stair Form work Installation

Z5-EGR-STAIR#8.195 Wall Rebar Installation 3 13-Feb-24 15-Feb-24 Wall Rebar Installation

Z5-EGR-STAIR#8.200 Wall Form work Installation 3 17-Feb-24 19-Feb-24 Wall Form work Installation

Z5-EGR-STAIR#8.205 Wall and Stair Concrete casting 1 20-Feb-24 20-Feb-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.210 Form Removal and Curing 7 21-Feb-24 28-Feb-24 Form Removal and Curing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
374 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL AND 5TH FLIGHT 17 29-Feb-24 19-Mar-24 19-Mar-24, WALL AND 5TH FLIGHT
Z5-EGR-STAIR#8.215 Stair Form work Installation 3 29-Feb-24 03-Mar-24 Stair Form work Installation

Z5-EGR-STAIR#8.220 Wall Rebar Installation 3 04-Mar-24 06-Mar-24 Wall Rebar Installation

Z5-EGR-STAIR#8.225 Wall Form work Installation 3 07-Mar-24 10-Mar-24 Wall Form work Installation

Z5-EGR-STAIR#8.230 Wall and Stair Concrete casting 1 11-Mar-24 11-Mar-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.235 Form Removal and Curing 7 12-Mar-24 19-Mar-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 20-Mar-24 08-Apr-24 08-Apr-24, WALL AND 6TH FLIGHT
Z5-EGR-STAIR#8.240 Stair Form work Installation 3 20-Mar-24 23-Mar-24 Stair Form work Installation

Z5-EGR-STAIR#8.245 Wall Rebar Installation 3 24-Mar-24 26-Mar-24 Wall Rebar Installation

Z5-EGR-STAIR#8.250 Wall Form work Installation 3 27-Mar-24 30-Mar-24 Wall Form work Installation

Z5-EGR-STAIR#8.255 Wall and Stair Concrete casting 1 31-Mar-24 31-Mar-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.260 Form Removal and Curing 7 01-Apr-24 08-Apr-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 13-Apr-24 01-May-24 01-May-24, WALL AND 7TH FLIGHT
Z5-EGR-STAIR#8.265 Stair Form work Installation 3 13-Apr-24 15-Apr-24 Stair Form work Installation

Z5-EGR-STAIR#8.270 Wall Rebar Installation 3 16-Apr-24 18-Apr-24 Wall Rebar Installation

Z5-EGR-STAIR#8.275 Wall Form work Installation 3 20-Apr-24 22-Apr-24 Wall Form work Installation

Z5-EGR-STAIR#8.280 Wall and Stair Concrete casting 1 23-Apr-24 23-Apr-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.285 Form Removal and Curing 7 24-Apr-24 01-May-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 02-May-24 21-May-24 21-May-24, WALL AND 8TH FLIGHT
Z5-EGR-STAIR#8.290 Stair Form work Installation 3 02-May-24 05-May-24 Stair Form work Installation

Z5-EGR-STAIR#8.295 Wall Rebar Installation 3 06-May-24 08-May-24 Wall Rebar Installation

Z5-EGR-STAIR#8.300 Wall Form work Installation 3 09-May-24 12-May-24 Wall Form work Installation

Z5-EGR-STAIR#8.305 Wall and Stair Concrete casting 1 13-May-24 13-May-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.310 Form Removal and Curing 7 14-May-24 21-May-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 22-May-24 10-Jun-24 10-Jun-24, WALL AND 9TH FLIGHT
Z5-EGR-STAIR#8.315 Stair Form work Installation 3 22-May-24 25-May-24 Stair Form work Installation

Z5-EGR-STAIR#8.320 Wall Rebar Installation 3 26-May-24 28-May-24 Wall Rebar Installation

Z5-EGR-STAIR#8.325 Wall Form work Installation 3 29-May-24 01-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#8.330 Wall and Stair Concrete casting 1 02-Jun-24 02-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.335 Form Removal and Curing 7 03-Jun-24 10-Jun-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 11-Jun-24 04-Jul-24 04-Jul-24, WALL AND 10TH FLIGHT
Z5-EGR-STAIR#8.340 Stair Form work Installation 3 11-Jun-24 13-Jun-24 Stair Form work Installation

Z5-EGR-STAIR#8.345 Wall Rebar Installation 3 19-Jun-24 22-Jun-24 Wall Rebar Installation

Z5-EGR-STAIR#8.350 Wall Form work Installation 3 23-Jun-24 25-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#8.355 Wall and Stair Concrete casting 1 26-Jun-24 26-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.360 Form Removal and Curing 7 27-Jun-24 04-Jul-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 06-Jul-24 24-Jul-24 24-Jul-24, WALL AND 11TH FLIGHT
Z5-EGR-STAIR#8.365 Stair Form work Installation 3 06-Jul-24 08-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#8.370 Wall Rebar Installation 3 09-Jul-24 11-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#8.375 Wall Form work Installation 3 13-Jul-24 15-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#8.380 Wall and Stair Concrete casting 1 16-Jul-24 16-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.385 Form Removal and Curing 7 17-Jul-24 24-Jul-24 Form Removal and Curing

TOP SLAB 35 25-Jul-24 03-Sep-24 03-Sep-24, TOP SLAB


Z5-EGR-STAIR#8.390 Slab Form work Installation 3 25-Jul-24 28-Jul-24 Slab Form work Installation

Z5-EGR-STAIR#8.395 Slab Rebar Installation 3 29-Jul-24 31-Jul-24 Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
375 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z5-EGR-STAIR#8.400 Wall and Stair Concrete casting 3 01-Aug-24 04-Aug-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#8.405 Form Removal and Curing 7 05-Aug-24 12-Aug-24 Form Removal and Curing

Z5-EGR-STAIR#8.410 Waterproofing and Coating 19 13-Aug-24 03-Sep-24 Waterproofing and Coating

Z5-EGR-STAIR#8.415 Railing work 7 26-Aug-24 03-Sep-24 Railing work

EGRESS STAIR-9 (ZONE-5) 236 07-Dec-23 15-Sep-24 15-Sep-24, EGRESS STAIR-9 (ZONE-5)
WALL AND 1ST FLIGHT 31 07-Dec-23 11-Jan-24 11-Jan-24, WALL AND 1ST FLIGHT
Z5-EGR-STAIR#9.100 Excavation for Foundation 6 07-Dec-23 13-Dec-23 Excavation for Foundation

Z5-EGR-STAIR#9.105 Foundation Blinding Concrete casting 1 14-Dec-23 14-Dec-23 Foundation Blinding Concrete casting

Z5-EGR-STAIR#9.110 Foundation Rebar Installation 3 16-Dec-23 18-Dec-23 Foundation Rebar Installation

Z5-EGR-STAIR#9.115 Foundation Formwork installation 3 19-Dec-23 21-Dec-23 Foundation Formwork installation

Z5-EGR-STAIR#9.120 Foundation Concrete casting 1 23-Dec-23 23-Dec-23 Foundation Concrete casting

Z5-EGR-STAIR#9.125 Wall and Stair Rebar Installation 4 24-Dec-23 27-Dec-23 Wall and Stair Rebar Installation

Z5-EGR-STAIR#9.130 Wall and Stair Form work Installation 6 28-Dec-23 03-Jan-24 Wall and Stair Form work Installation

Z5-EGR-STAIR#9.135 Form Removal and Curing 7 04-Jan-24 11-Jan-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 13-Jan-24 31-Jan-24 31-Jan-24, WALL AND 2ND FLIGHT
Z5-EGR-STAIR#9.140 Stair Form work Installation 3 13-Jan-24 15-Jan-24 Stair Form work Installation

Z5-EGR-STAIR#9.145 Wall Rebar Installation 3 16-Jan-24 18-Jan-24 Wall Rebar Installation

Z5-EGR-STAIR#9.150 Wall Form work Installation 3 20-Jan-24 22-Jan-24 Wall Form work Installation

Z5-EGR-STAIR#9.155 Wall and Stair Concrete casting 1 23-Jan-24 23-Jan-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.160 Form Removal and Curing 7 24-Jan-24 31-Jan-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 01-Feb-24 20-Feb-24 20-Feb-24, WALL AND 3RD FLIGHT
Z5-EGR-STAIR#9.165 Stair Form work Installation 3 01-Feb-24 04-Feb-24 Stair Form work Installation

Z5-EGR-STAIR#9.170 Wall Rebar Installation 3 05-Feb-24 07-Feb-24 Wall Rebar Installation

Z5-EGR-STAIR#9.175 Wall Form work Installation 3 08-Feb-24 11-Feb-24 Wall Form work Installation

Z5-EGR-STAIR#9.180 Wall and Stair Concrete casting 1 12-Feb-24 12-Feb-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.185 Form Removal and Curing 7 13-Feb-24 20-Feb-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 21-Feb-24 11-Mar-24 11-Mar-24, WALL AND 4TH FLIGHT
Z5-EGR-STAIR#9.190 Stair Form work Installation 3 21-Feb-24 24-Feb-24 Stair Form work Installation

Z5-EGR-STAIR#9.195 Wall Rebar Installation 3 25-Feb-24 27-Feb-24 Wall Rebar Installation

Z5-EGR-STAIR#9.200 Wall Form work Installation 3 28-Feb-24 02-Mar-24 Wall Form work Installation

Z5-EGR-STAIR#9.205 Wall and Stair Concrete casting 1 03-Mar-24 03-Mar-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.210 Form Removal and Curing 7 04-Mar-24 11-Mar-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 12-Mar-24 31-Mar-24 31-Mar-24, WALL AND 5TH FLIGHT
Z5-EGR-STAIR#9.215 Stair Form work Installation 3 12-Mar-24 14-Mar-24 Stair Form work Installation

Z5-EGR-STAIR#9.220 Wall Rebar Installation 3 16-Mar-24 18-Mar-24 Wall Rebar Installation

Z5-EGR-STAIR#9.225 Wall Form work Installation 3 19-Mar-24 21-Mar-24 Wall Form work Installation

Z5-EGR-STAIR#9.230 Wall and Stair Concrete casting 1 23-Mar-24 23-Mar-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.235 Form Removal and Curing 7 24-Mar-24 31-Mar-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 01-Apr-24 23-Apr-24 23-Apr-24, WALL AND 6TH FLIGHT
Z5-EGR-STAIR#9.240 Stair Form work Installation 3 01-Apr-24 03-Apr-24 Stair Form work Installation

Z5-EGR-STAIR#9.245 Wall Rebar Installation 3 04-Apr-24 07-Apr-24 Wall Rebar Installation

Z5-EGR-STAIR#9.250 Wall Form work Installation 3 08-Apr-24 14-Apr-24 Wall Form work Installation

Z5-EGR-STAIR#9.255 Wall and Stair Concrete casting 1 15-Apr-24 15-Apr-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.260 Form Removal and Curing 7 16-Apr-24 23-Apr-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 24-Apr-24 13-May-24 13-May-24, WALL AND 7TH FLIGHT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
376 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z5-EGR-STAIR#9.265 Stair Form work Installation 3 24-Apr-24 27-Apr-24 Stair Form work Installation

Z5-EGR-STAIR#9.270 Wall Rebar Installation 3 28-Apr-24 30-Apr-24 Wall Rebar Installation

Z5-EGR-STAIR#9.275 Wall Form work Installation 3 01-May-24 04-May-24 Wall Form work Installation

Z5-EGR-STAIR#9.280 Wall and Stair Concrete casting 1 05-May-24 05-May-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.285 Form Removal and Curing 7 06-May-24 13-May-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 14-May-24 02-Jun-24 02-Jun-24, WALL AND 8TH FLIGHT
Z5-EGR-STAIR#9.290 Stair Form work Installation 3 14-May-24 16-May-24 Stair Form work Installation

Z5-EGR-STAIR#9.295 Wall Rebar Installation 3 18-May-24 20-May-24 Wall Rebar Installation

Z5-EGR-STAIR#9.300 Wall Form work Installation 3 21-May-24 23-May-24 Wall Form work Installation

Z5-EGR-STAIR#9.305 Wall and Stair Concrete casting 1 25-May-24 25-May-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.310 Form Removal and Curing 7 26-May-24 02-Jun-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 03-Jun-24 26-Jun-24 26-Jun-24, WALL AND 9TH FLIGHT
Z5-EGR-STAIR#9.315 Stair Form work Installation 3 03-Jun-24 05-Jun-24 Stair Form work Installation

Z5-EGR-STAIR#9.320 Wall Rebar Installation 3 06-Jun-24 09-Jun-24 Wall Rebar Installation

Z5-EGR-STAIR#9.325 Wall Form work Installation 3 10-Jun-24 12-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#9.330 Wall and Stair Concrete casting 1 13-Jun-24 13-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.335 Form Removal and Curing 7 19-Jun-24 26-Jun-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 27-Jun-24 16-Jul-24 16-Jul-24, WALL AND 10TH FLIGHT
Z5-EGR-STAIR#9.340 Stair Form work Installation 3 27-Jun-24 30-Jun-24 Stair Form work Installation

Z5-EGR-STAIR#9.345 Wall Rebar Installation 3 01-Jul-24 03-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#9.350 Wall Form work Installation 3 04-Jul-24 07-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#9.355 Wall and Stair Concrete casting 1 08-Jul-24 08-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.360 Form Removal and Curing 7 09-Jul-24 16-Jul-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 17-Jul-24 05-Aug-24 05-Aug-24, WALL AND 11TH FLIGHT
Z5-EGR-STAIR#9.365 Stair Form work Installation 3 17-Jul-24 20-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#9.370 Wall Rebar Installation 3 21-Jul-24 23-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#9.375 Wall Form work Installation 3 24-Jul-24 27-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#9.380 Wall and Stair Concrete casting 1 28-Jul-24 28-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.385 Form Removal and Curing 7 29-Jul-24 05-Aug-24 Form Removal and Curing

TOP SLAB 35 06-Aug-24 15-Sep-24 15-Sep-24, TOP SLAB


Z5-EGR-STAIR#9.390 Slab Form work Installation 3 06-Aug-24 08-Aug-24 Slab Form work Installation

Z5-EGR-STAIR#9.395 Slab Rebar Installation 3 10-Aug-24 12-Aug-24 Slab Rebar Installation

Z5-EGR-STAIR#9.400 Wall and Stair Concrete casting 3 13-Aug-24 15-Aug-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#9.405 Form Removal and Curing 7 17-Aug-24 24-Aug-24 Form Removal and Curing

Z5-EGR-STAIR#9.410 Waterproofing and Coating 19 25-Aug-24 15-Sep-24 Waterproofing and Coating

Z5-EGR-STAIR#9.415 Railing work 7 07-Sep-24 15-Sep-24 Railing work

EGRESS STAIR-10 (ZONE-5) 236 27-Feb-24 07-Dec-24 07-Dec-24, EGRESS STAIR-10 (ZONE-5)
WALL AND 1ST FLIGHT 31 27-Feb-24 02-Apr-24 02-Apr-24, WALL AND 1ST FLIGHT
Z5-EGR-STAIR#10.100 Excavation for Foundation 6 27-Feb-24 04-Mar-24 Excavation for Foundation

Z5-EGR-STAIR#10.105 Foundation Blinding Concrete casting 1 05-Mar-24 05-Mar-24 Foundation Blinding Concrete casting

Z5-EGR-STAIR#10.110 Foundation Rebar Installation 3 06-Mar-24 09-Mar-24 Foundation Rebar Installation

Z5-EGR-STAIR#10.115 Foundation Formwork installation 3 10-Mar-24 12-Mar-24 Foundation Formwork installation

Z5-EGR-STAIR#10.120 Foundation Concrete casting 1 13-Mar-24 13-Mar-24 Foundation Concrete casting

Z5-EGR-STAIR#10.125 Wall and Stair Rebar Installation 4 14-Mar-24 18-Mar-24 Wall and Stair Rebar Installation

Z5-EGR-STAIR#10.130 Wall and Stair Form work Installation 6 19-Mar-24 25-Mar-24 Wall and Stair Form work Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
377 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z5-EGR-STAIR#10.135 Form Removal and Curing 7 26-Mar-24 02-Apr-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 03-Apr-24 25-Apr-24 25-Apr-24, WALL AND 2ND FLIGHT
Z5-EGR-STAIR#10.140 Stair Form work Installation 3 03-Apr-24 06-Apr-24 Stair Form work Installation

Z5-EGR-STAIR#10.145 Wall Rebar Installation 3 07-Apr-24 13-Apr-24 Wall Rebar Installation

Z5-EGR-STAIR#10.150 Wall Form work Installation 3 14-Apr-24 16-Apr-24 Wall Form work Installation

Z5-EGR-STAIR#10.155 Wall and Stair Concrete casting 1 17-Apr-24 17-Apr-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.160 Form Removal and Curing 7 18-Apr-24 25-Apr-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 27-Apr-24 15-May-24 15-May-24, WALL AND 3RD FLIGHT
Z5-EGR-STAIR#10.165 Stair Form work Installation 3 27-Apr-24 29-Apr-24 Stair Form work Installation

Z5-EGR-STAIR#10.170 Wall Rebar Installation 3 30-Apr-24 02-May-24 Wall Rebar Installation

Z5-EGR-STAIR#10.175 Wall Form work Installation 3 04-May-24 06-May-24 Wall Form work Installation

Z5-EGR-STAIR#10.180 Wall and Stair Concrete casting 1 07-May-24 07-May-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.185 Form Removal and Curing 7 08-May-24 15-May-24 Form Removal and Curing

WALL AND 4TH FLIGHT 17 16-May-24 04-Jun-24 04-Jun-24, WALL AND 4TH FLIGHT
Z5-EGR-STAIR#10.190 Stair Form work Installation 3 16-May-24 19-May-24 Stair Form work Installation

Z5-EGR-STAIR#10.195 Wall Rebar Installation 3 20-May-24 22-May-24 Wall Rebar Installation

Z5-EGR-STAIR#10.200 Wall Form work Installation 3 23-May-24 26-May-24 Wall Form work Installation

Z5-EGR-STAIR#10.205 Wall and Stair Concrete casting 1 27-May-24 27-May-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.210 Form Removal and Curing 7 28-May-24 04-Jun-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 05-Jun-24 29-Jun-24 29-Jun-24, WALL AND 5TH FLIGHT
Z5-EGR-STAIR#10.215 Stair Form work Installation 3 05-Jun-24 08-Jun-24 Stair Form work Installation

Z5-EGR-STAIR#10.220 Wall Rebar Installation 3 09-Jun-24 11-Jun-24 Wall Rebar Installation

Z5-EGR-STAIR#10.225 Wall Form work Installation 3 12-Jun-24 19-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#10.230 Wall and Stair Concrete casting 1 20-Jun-24 20-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.235 Form Removal and Curing 7 22-Jun-24 29-Jun-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 30-Jun-24 18-Jul-24 18-Jul-24, WALL AND 6TH FLIGHT
Z5-EGR-STAIR#10.240 Stair Form work Installation 3 30-Jun-24 02-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#10.245 Wall Rebar Installation 3 03-Jul-24 06-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#10.250 Wall Form work Installation 3 07-Jul-24 09-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#10.255 Wall and Stair Concrete casting 1 10-Jul-24 10-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.260 Form Removal and Curing 7 11-Jul-24 18-Jul-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 20-Jul-24 07-Aug-24 07-Aug-24, WALL AND 7TH FLIGHT
Z5-EGR-STAIR#10.265 Stair Form work Installation 3 20-Jul-24 22-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#10.270 Wall Rebar Installation 3 23-Jul-24 25-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#10.275 Wall Form work Installation 3 27-Jul-24 29-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#10.280 Wall and Stair Concrete casting 1 30-Jul-24 30-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.285 Form Removal and Curing 7 31-Jul-24 07-Aug-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 08-Aug-24 27-Aug-24 27-Aug-24, WALL AND 8TH FLIGHT
Z5-EGR-STAIR#10.290 Stair Form work Installation 3 08-Aug-24 11-Aug-24 Stair Form work Installation

Z5-EGR-STAIR#10.295 Wall Rebar Installation 3 12-Aug-24 14-Aug-24 Wall Rebar Installation

Z5-EGR-STAIR#10.300 Wall Form work Installation 3 15-Aug-24 18-Aug-24 Wall Form work Installation

Z5-EGR-STAIR#10.305 Wall and Stair Concrete casting 1 19-Aug-24 19-Aug-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.310 Form Removal and Curing 7 20-Aug-24 27-Aug-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 28-Aug-24 16-Sep-24 16-Sep-24, WALL AND 9TH FLIGHT
Z5-EGR-STAIR#10.315 Stair Form work Installation 3 28-Aug-24 31-Aug-24 Stair Form work Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
378 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z5-EGR-STAIR#10.320 Wall Rebar Installation 3 01-Sep-24 03-Sep-24 Wall Rebar Installation

Z5-EGR-STAIR#10.325 Wall Form work Installation 3 04-Sep-24 07-Sep-24 Wall Form work Installation

Z5-EGR-STAIR#10.330 Wall and Stair Concrete casting 1 08-Sep-24 08-Sep-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.335 Form Removal and Curing 7 09-Sep-24 16-Sep-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 17-Sep-24 07-Oct-24 07-Oct-24, WALL AND 10TH FLIGHT
Z5-EGR-STAIR#10.340 Stair Form work Installation 3 17-Sep-24 19-Sep-24 Stair Form work Installation

Z5-EGR-STAIR#10.345 Wall Rebar Installation 3 21-Sep-24 24-Sep-24 Wall Rebar Installation

Z5-EGR-STAIR#10.350 Wall Form work Installation 3 25-Sep-24 28-Sep-24 Wall Form work Installation

Z5-EGR-STAIR#10.355 Wall and Stair Concrete casting 1 29-Sep-24 29-Sep-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.360 Form Removal and Curing 7 30-Sep-24 07-Oct-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 08-Oct-24 27-Oct-24 27-Oct-24, WALL AND 11TH FLIGHT
Z5-EGR-STAIR#10.365 Stair Form work Installation 3 08-Oct-24 10-Oct-24 Stair Form work Installation

Z5-EGR-STAIR#10.370 Wall Rebar Installation 3 12-Oct-24 14-Oct-24 Wall Rebar Installation

Z5-EGR-STAIR#10.375 Wall Form work Installation 3 15-Oct-24 17-Oct-24 Wall Form work Installation

Z5-EGR-STAIR#10.380 Wall and Stair Concrete casting 1 19-Oct-24 19-Oct-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.385 Form Removal and Curing 7 20-Oct-24 27-Oct-24 Form Removal and Curing

TOP SLAB 35 28-Oct-24 07-Dec-24 07-Dec-24, TOP SLAB


Z5-EGR-STAIR#10.390 Slab Form work Installation 3 28-Oct-24 30-Oct-24 Slab Form work Installation

Z5-EGR-STAIR#10.395 Slab Rebar Installation 3 31-Oct-24 03-Nov-24 Slab Rebar Installation

Z5-EGR-STAIR#10.400 Wall and Stair Concrete casting 3 04-Nov-24 06-Nov-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#10.405 Form Removal and Curing 7 07-Nov-24 14-Nov-24 Form Removal and Curing

Z5-EGR-STAIR#10.410 Waterproofing and Coating 19 16-Nov-24 07-Dec-24 Waterproofing and Coating

Z5-EGR-STAIR#10.415 Railing work 7 28-Nov-24 07-Dec-24 Railing work

EGRESS STAIR-11 (ZONE-5) 236 16-Apr-24 21-Jan-25 21-Jan-25, EGRESS STAIR-11 (ZONE-5)
WALL AND 1ST FLIGHT 31 16-Apr-24 21-May-24 21-May-24, WALL AND 1ST FLIGHT
Z5-EGR-STAIR#11.100 Excavation for Foundation 6 16-Apr-24 22-Apr-24 Excavation for Foundation

Z5-EGR-STAIR#11.105 Foundation Blinding Concrete casting 1 23-Apr-24 23-Apr-24 Foundation Blinding Concrete casting

Z5-EGR-STAIR#11.110 Foundation Rebar Installation 3 24-Apr-24 27-Apr-24 Foundation Rebar Installation

Z5-EGR-STAIR#11.115 Foundation Formwork installation 3 28-Apr-24 30-Apr-24 Foundation Formwork installation

Z5-EGR-STAIR#11.120 Foundation Concrete casting 1 01-May-24 01-May-24 Foundation Concrete casting

Z5-EGR-STAIR#11.125 Wall and Stair Rebar Installation 4 02-May-24 06-May-24 Wall and Stair Rebar Installation

Z5-EGR-STAIR#11.130 Wall and Stair Form work Installation 6 07-May-24 13-May-24 Wall and Stair Form work Installation

Z5-EGR-STAIR#11.135 Form Removal and Curing 7 14-May-24 21-May-24 Form Removal and Curing

WALL AND 2ND FLIGHT 17 22-May-24 10-Jun-24 10-Jun-24, WALL AND 2ND FLIGHT
Z5-EGR-STAIR#11.140 Stair Form work Installation 3 22-May-24 25-May-24 Stair Form work Installation

Z5-EGR-STAIR#11.145 Wall Rebar Installation 3 26-May-24 28-May-24 Wall Rebar Installation

Z5-EGR-STAIR#11.150 Wall Form work Installation 3 29-May-24 01-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#11.155 Wall and Stair Concrete casting 1 02-Jun-24 02-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.160 Form Removal and Curing 7 03-Jun-24 10-Jun-24 Form Removal and Curing

WALL AND 3RD FLIGHT 17 11-Jun-24 04-Jul-24 04-Jul-24, WALL AND 3RD FLIGHT
Z5-EGR-STAIR#11.165 Stair Form work Installation 3 11-Jun-24 13-Jun-24 Stair Form work Installation

Z5-EGR-STAIR#11.170 Wall Rebar Installation 3 19-Jun-24 22-Jun-24 Wall Rebar Installation

Z5-EGR-STAIR#11.175 Wall Form work Installation 3 23-Jun-24 25-Jun-24 Wall Form work Installation

Z5-EGR-STAIR#11.180 Wall and Stair Concrete casting 1 26-Jun-24 26-Jun-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.185 Form Removal and Curing 7 27-Jun-24 04-Jul-24 Form Removal and Curing

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
379 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
WALL AND 4TH FLIGHT 17 06-Jul-24 24-Jul-24 24-Jul-24, WALL AND 4TH FLIGHT
Z5-EGR-STAIR#11.190 Stair Form work Installation 3 06-Jul-24 08-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#11.195 Wall Rebar Installation 3 09-Jul-24 11-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#11.200 Wall Form work Installation 3 13-Jul-24 15-Jul-24 Wall Form work Installation

Z5-EGR-STAIR#11.205 Wall and Stair Concrete casting 1 16-Jul-24 16-Jul-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.210 Form Removal and Curing 7 17-Jul-24 24-Jul-24 Form Removal and Curing

WALL AND 5TH FLIGHT 17 25-Jul-24 13-Aug-24 13-Aug-24, WALL AND 5TH FLIGHT
Z5-EGR-STAIR#11.215 Stair Form work Installation 3 25-Jul-24 28-Jul-24 Stair Form work Installation

Z5-EGR-STAIR#11.220 Wall Rebar Installation 3 29-Jul-24 31-Jul-24 Wall Rebar Installation

Z5-EGR-STAIR#11.225 Wall Form work Installation 3 01-Aug-24 04-Aug-24 Wall Form work Installation

Z5-EGR-STAIR#11.230 Wall and Stair Concrete casting 1 05-Aug-24 05-Aug-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.235 Form Removal and Curing 7 06-Aug-24 13-Aug-24 Form Removal and Curing

WALL AND 6TH FLIGHT 17 14-Aug-24 02-Sep-24 02-Sep-24, WALL AND 6TH FLIGHT
Z5-EGR-STAIR#11.240 Stair Form work Installation 3 14-Aug-24 17-Aug-24 Stair Form work Installation

Z5-EGR-STAIR#11.245 Wall Rebar Installation 3 18-Aug-24 20-Aug-24 Wall Rebar Installation

Z5-EGR-STAIR#11.250 Wall Form work Installation 3 21-Aug-24 24-Aug-24 Wall Form work Installation

Z5-EGR-STAIR#11.255 Wall and Stair Concrete casting 1 25-Aug-24 25-Aug-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.260 Form Removal and Curing 7 26-Aug-24 02-Sep-24 Form Removal and Curing

WALL AND 7TH FLIGHT 17 03-Sep-24 22-Sep-24 22-Sep-24, WALL AND 7TH FLIGHT
Z5-EGR-STAIR#11.265 Stair Form work Installation 3 03-Sep-24 05-Sep-24 Stair Form work Installation

Z5-EGR-STAIR#11.270 Wall Rebar Installation 3 07-Sep-24 09-Sep-24 Wall Rebar Installation

Z5-EGR-STAIR#11.275 Wall Form work Installation 3 10-Sep-24 12-Sep-24 Wall Form work Installation

Z5-EGR-STAIR#11.280 Wall and Stair Concrete casting 1 14-Sep-24 14-Sep-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.285 Form Removal and Curing 7 15-Sep-24 22-Sep-24 Form Removal and Curing

WALL AND 8TH FLIGHT 17 24-Sep-24 13-Oct-24 13-Oct-24, WALL AND 8TH FLIGHT
Z5-EGR-STAIR#11.290 Stair Form work Installation 3 24-Sep-24 26-Sep-24 Stair Form work Installation

Z5-EGR-STAIR#11.295 Wall Rebar Installation 3 28-Sep-24 30-Sep-24 Wall Rebar Installation

Z5-EGR-STAIR#11.300 Wall Form work Installation 3 01-Oct-24 03-Oct-24 Wall Form work Installation

Z5-EGR-STAIR#11.305 Wall and Stair Concrete casting 1 05-Oct-24 05-Oct-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.310 Form Removal and Curing 7 06-Oct-24 13-Oct-24 Form Removal and Curing

WALL AND 9TH FLIGHT 17 14-Oct-24 02-Nov-24 02-Nov-24, WALL AND 9TH FLIGHT
Z5-EGR-STAIR#11.315 Stair Form work Installation 3 14-Oct-24 16-Oct-24 Stair Form work Installation

Z5-EGR-STAIR#11.320 Wall Rebar Installation 3 17-Oct-24 20-Oct-24 Wall Rebar Installation

Z5-EGR-STAIR#11.325 Wall Form work Installation 3 21-Oct-24 23-Oct-24 Wall Form work Installation

Z5-EGR-STAIR#11.330 Wall and Stair Concrete casting 1 24-Oct-24 24-Oct-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.335 Form Removal and Curing 7 26-Oct-24 02-Nov-24 Form Removal and Curing

WALL AND 10TH FLIGHT 17 03-Nov-24 21-Nov-24 21-Nov-24, WALL AND 10TH FLIGHT
Z5-EGR-STAIR#11.340 Stair Form work Installation 3 03-Nov-24 05-Nov-24 Stair Form work Installation

Z5-EGR-STAIR#11.345 Wall Rebar Installation 3 06-Nov-24 09-Nov-24 Wall Rebar Installation

Z5-EGR-STAIR#11.350 Wall Form work Installation 3 10-Nov-24 12-Nov-24 Wall Form work Installation

Z5-EGR-STAIR#11.355 Wall and Stair Concrete casting 1 13-Nov-24 13-Nov-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.360 Form Removal and Curing 7 14-Nov-24 21-Nov-24 Form Removal and Curing

WALL AND 11TH FLIGHT 17 23-Nov-24 11-Dec-24 11-Dec-24, WALL AND 11TH FLIGHT
Z5-EGR-STAIR#11.365 Stair Form work Installation 3 23-Nov-24 25-Nov-24 Stair Form work Installation

Z5-EGR-STAIR#11.370 Wall Rebar Installation 3 26-Nov-24 28-Nov-24 Wall Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
380 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Z5-EGR-STAIR#11.375 Wall Form work Installation 3 30-Nov-24 02-Dec-24 Wall Form work Installation

Z5-EGR-STAIR#11.380 Wall and Stair Concrete casting 1 03-Dec-24 03-Dec-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.385 Form Removal and Curing 7 04-Dec-24 11-Dec-24 Form Removal and Curing

TOP SLAB 35 12-Dec-24 21-Jan-25 21-Jan-25, TOP SLAB


Z5-EGR-STAIR#11.390 Slab Form work Installation 3 12-Dec-24 15-Dec-24 Slab Form work Installation

Z5-EGR-STAIR#11.395 Slab Rebar Installation 3 16-Dec-24 18-Dec-24 Slab Rebar Installation

Z5-EGR-STAIR#11.400 Wall and Stair Concrete casting 3 19-Dec-24 22-Dec-24 Wall and Stair Concrete casting

Z5-EGR-STAIR#11.405 Form Removal and Curing 7 23-Dec-24 30-Dec-24 Form Removal and Curing

Z5-EGR-STAIR#11.410 Waterproofing and Coating 19 31-Dec-24 21-Jan-25 Waterproofing and Coating

Z5-EGR-STAIR#11.415 Railing work 7 13-Jan-25 21-Jan-25 Railing work

BACKFILLING UPTO TUNNELWALL 191 02-Mar-24 19-Oct-24 19-Oct-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z5-CON-BF.210 Backfilling & Compaction @ 1+753 ~ 1+853 20 02-Mar-24 24-Mar-24 Backfilling & Compaction @ 1+753 ~ 1+853

JAH-Z5-CON-BF.215 Backfilling & Compaction @ 1+853 ~ 1+953 20 14-May-24 05-Jun-24 Backfilling & Compaction @ 1+853 ~ 1+953

JAH-Z5-CON-BF.220 Backfilling & Compaction @ 1+953 ~ 2+053 20 15-Aug-24 07-Sep-24 Backfilling & Compaction @ 1+953 ~ 2+053

JAH-Z5-CON-BF.225 Backfilling & Compaction @ 2+053 ~ 2+157 20 26-Sep-24 19-Oct-24 Backfilling & Compaction @ 2+053 ~ 2+157

STRUCTURAL FILL 326 08-Aug-24 02-Sep-25 02-Sep-25, STRUCTURAL FILL


JAH-Z5-SF-IL.100 Backfilling & Compaction at Invert Level @ 1+753 ~ 1+853 20 08-Aug-24 31-Aug-24 Backfilling & Compaction at Invert Level @ 1+753 ~ 1+853

JAH-Z5-SF-IL.105 Backfilling & Compaction at Invert Level @ 1+853 ~ 1+953 20 02-Nov-24 24-Nov-24 Backfilling & Compaction at Invert Level @ 1+853 ~ 1+953

JAH-Z5-SF-IL.110 Backfilling & Compaction at Invert Level @ 1+953 ~ 2+053 20 31-Dec-24 22-Jan-25 Backfilling & Compaction at Invert Level @ 1+953 ~ 2+053

JAH-Z5-SF-IL.115 Backfilling & Compaction at Invert Level @ 2+053 ~ 2+157 20 10-Aug-25 02-Sep-25 Backfilling & Compaction at Invert Level @ 2+053 ~ 2+157

WET & DRY UTILITIES 112 24-Mar-25 09-Aug-25 09-Aug-25, WET & DRY UTILITIES
INSIDE WET CULVERT 112 24-Mar-25 09-Aug-25 09-Aug-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 59 24-Mar-25 04-Jun-25 04-Jun-25, POTABLE WATER NETWORK
JAH-Z5-WU-PWN.100 Pipe Supports Installation 25 24-Mar-25 26-Apr-25 Pipe Supports Installation

JAH-Z5-WU-PWN.105 Pipe Installation alongwith Valves, Fittings & Accessories 30 27-Apr-25 31-May-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-PWN.110 Testing 4 01-Jun-25 04-Jun-25 Testing

GREY WATER DISTRIBUTION SYSTEM 49 27-Apr-25 25-Jun-25 25-Jun-25, GREY WATER DISTRIBUTION SYSTEM
JAH-Z5-WU-GWD.270 Pipe Supports Installation 20 27-Apr-25 19-May-25 Pipe Supports Installation

JAH-Z5-WU-GWD.275 Pipe Installation alongwith Valves, Fittings & Accessories 25 20-May-25 21-Jun-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-GWD.280 Testing 4 22-Jun-25 25-Jun-25 Testing

IRRIGATION NETWORK 78 24-Mar-25 30-Jun-25 30-Jun-25, IRRIGATION NETWORK


JAH-Z5-WU-IN.620 Pipe Supports Installation 20 24-Mar-25 20-Apr-25 Pipe Supports Installation

JAH-Z5-WU-IN.625 Pipe Installation alongwith Valves, Fittings & Accessories 25 21-Apr-25 19-May-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-IN.630 Testing 4 26-Jun-25 30-Jun-25 Testing

CHILLED WATER SUPPLY NETWORK 59 20-May-25 30-Jul-25 30-Jul-25, CHILLED WATER SUPPLY NETWORK
JAH-Z5-WU-CWS.160 Pipe Supports Installation 25 20-May-25 21-Jun-25 Pipe Supports Installation

JAH-Z5-WU-CWS.165 Pipe Installation alongwith Valves, Fittings & Accessories 30 22-Jun-25 26-Jul-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-CWS.170 Testing 4 27-Jul-25 30-Jul-25 Testing

CHILLED WATER RETURN NETWORK 63 20-May-25 04-Aug-25 04-Aug-25, CHILLED WATER RETURN NETWORK
JAH-Z5-WU-CWR.160 Pipe Supports Installation 25 20-May-25 21-Jun-25 Pipe Supports Installation

JAH-Z5-WU-CWR.165 Pipe Installation alongwith Valves, Fittings & Accessories 30 22-Jun-25 26-Jul-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-CWR.170 Testing 4 31-Jul-25 04-Aug-25 Testing

AUTOMATIC WASTE COLLECTION NETWORK 87 27-Apr-25 09-Aug-25 09-Aug-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z5-WU-AWC.160 Pipe Supports Installation 25 27-Apr-25 25-May-25 Pipe Supports Installation

JAH-Z5-WU-AWC.165 Pipe Installation alongwith Valves, Fittings & Accessories 30 26-May-25 02-Jul-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z5-WU-AWC.170 Testing 4 05-Aug-25 09-Aug-25 Testing

INSIDE DRY CULVERT 94 24-Mar-25 19-Jul-25 19-Jul-25, INSIDE DRY CULVERT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
381 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
POWER 94 24-Mar-25 19-Jul-25 19-Jul-25, POWER
HIGH VOLTAGE 110 KV NETWORK 30 24-Mar-25 01-May-25 01-May-25, HIGH VOLTAGE 110 KV NETWORK
JAH-Z5-IDC-PO-HV.140
HV Cable Supports Installation 12 24-Mar-25 10-Apr-25 HV Cable Supports Installation

JAH-Z5-IDC-PO-HV.145
Cable Installation with Fittings & Accessories 18 12-Apr-25 01-May-25 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 32 12-Apr-25 18-May-25 18-May-25, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z5-IDC-PO-MV.140
MV Cable Supports Installation 12 12-Apr-25 24-Apr-25 MV Cable Supports Installation

JAH-Z5-IDC-PO-MV.145
Cables Installation with Fittings & Accessories 20 26-Apr-25 18-May-25 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 34 03-May-25 14-Jun-25 14-Jun-25, LOW VOLTAGE NETWORK


JAH-Z5-IDC-PO-LV.140
LV Cable Supports Installation 12 03-May-25 15-May-25 LV Cable Supports Installation

JAH-Z5-IDC-PO-LV.145
Cable Laying with Fittings & Accessories 20 19-May-25 14-Jun-25 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 70 26-Apr-25 19-Jul-25 19-Jul-25, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z5-IDC-PO-DS.260
Cable Tray Installation 10 26-Apr-25 06-May-25 Cable Tray Installation

JAH-Z5-IDC-PO-DS.265
PVC Ducts Installation 5 07-May-25 12-May-25 PVC Ducts Installation

JAH-Z5-IDC-PO-DS.270
Cable Installation 10 13-May-25 24-May-25 Cable Installation

JAH-Z5-IDC-PO-DS.275
Isolators Installation 5 25-May-25 29-May-25 Isolators Installation

JAH-Z5-IDC-PO-DS.280
Sub Main Distribution Boards Installation 10 31-May-25 14-Jun-25 Sub Main Distribution Boards Installation

JAH-Z5-IDC-PO-DS.285
Motor Control Centres Installation 10 15-Jun-25 25-Jun-25 Motor Control Centres Installation

JAH-Z5-IDC-PO-DS.290
Distribution Boards Installation 10 26-Jun-25 07-Jul-25 Distribution Boards Installation

JAH-Z5-IDC-PO-DS.295
Wiring Accessories Installation 10 08-Jul-25 19-Jul-25 Wiring Accessories Installation

LIGHTING SYSTEM 35 07-May-25 19-Jun-25 19-Jun-25, LIGHTING SYSTEM


JAH-Z5-DU-LS.278 Cables Installation 10 07-May-25 18-May-25 Cables Installation

JAH-Z5-DU-LS.280 Light Point Installation 15 19-May-25 04-Jun-25 Light Point Installation

JAH-Z5-DU-LS.300 Luminaires Installation 10 09-Jun-25 19-Jun-25 Luminaires Installation

TELECOM SERVICES 30 15-Jun-25 19-Jul-25 19-Jul-25, TELECOM SERVICES


JAH-Z5-DU-TES.160 Mobily Lines 10 15-Jun-25 25-Jun-25 Mobily Lines

JAH-Z5-DU-TES.165 STC Line 10 26-Jun-25 07-Jul-25 STC Line

JAH-Z5-DU-TES.170 MOI Line 10 08-Jul-25 19-Jul-25 MOI Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 162 24-Mar-25 07-Oct-25 07-Oct-25, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 86 21-Apr-25 02-Aug-25 02-Aug-25, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 56 21-Apr-25 28-Jun-25 28-Jun-25, FIRE FIGHTING SYSTEM
JAH-Z5-MECH-FF100 Pipe Installation work 20 21-Apr-25 13-May-25 Pipe Installation work

JAH-Z5-MECH-FF105 Valves and Accessories Installation 8 14-May-25 22-May-25 Valves and Accessories Installation

JAH-Z5-MECH-FF110 Sprinklers Installation 5 24-May-25 28-May-25 Sprinklers Installation

JAH-Z5-MECH-FF115 Fire Extinguishers Installation 8 29-May-25 10-Jun-25 Fire Extinguishers Installation

JAH-Z5-MECH-FF120 Foam Tank Installation 6 11-Jun-25 17-Jun-25 Foam Tank Installation

JAH-Z5-MECH-FF125 Pipe Painting work 6 18-Jun-25 24-Jun-25 Pipe Painting work

JAH-Z5-MECH-FF130 Testing work 3 25-Jun-25 28-Jun-25 Testing work

VENTILATION SYSTEM 57 14-May-25 22-Jul-25 22-Jul-25, VENTILATION SYSTEM


JAH-Z5-MECH-VS100 Staircase Pressurisation Fan Installation 5 14-May-25 19-May-25 Staircase Pressurisation Fan Installation

JAH-Z5-MECH-VS105 Extract fan installation 5 20-May-25 25-May-25 Extract fan installation

JAH-Z5-MECH-VS110 Unidirectional Jet fan 5 26-May-25 31-May-25 Unidirectional Jet fan

JAH-Z5-MECH-VS115 Reverse Jet fan 5 01-Jun-25 09-Jun-25 Reverse Jet fan

JAH-Z5-MECH-VS120 Testing work 3 20-Jul-25 22-Jul-25 Testing work

PUMPS INSTALLATION 21 26-May-25 22-Jun-25 22-Jun-25, PUMPS INSTALLATION


JAH-Z5-MECH-PI.160 Sump Pump Installation 7 26-May-25 02-Jun-25 Sump Pump Installation

JAH-Z5-MECH-PI.165 Pipe Connection work 6 03-Jun-25 12-Jun-25 Pipe Connection work

JAH-Z5-MECH-PI.170 Testing work 2 21-Jun-25 22-Jun-25 Testing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
382 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DUCTING SYSTEM 66 14-May-25 02-Aug-25 02-Aug-25, DUCTING SYSTEM
JAH-Z5-MECH-DS.240Duct Installation work 28 14-May-25 18-Jun-25 Duct Installation work

JAH-Z5-MECH-DS.245Grills Installation work 7 19-Jun-25 26-Jun-25 Grills Installation work

JAH-Z5-MECH-DS.250Diffusers Installation work 7 28-Jun-25 05-Jul-25 Diffusers Installation work

JAH-Z5-MECH-DS.255Non Returns Dampers 7 06-Jul-25 13-Jul-25 Non Returns Dampers

JAH-Z5-MECH-DS.260Fire and Smoke Damper 7 14-Jul-25 21-Jul-25 Fire and Smoke Damper

JAH-Z5-MECH-DS.265Sand Trap Louvre 5 22-Jul-25 27-Jul-25 Sand Trap Louvre

JAH-Z5-MECH-DS.270Testing work 5 28-Jul-25 02-Aug-25 Testing work

TUNNEL ELECTRICAL WORKS 134 24-Mar-25 03-Sep-25 03-Sep-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 101 24-Mar-25 27-Jul-25 27-Jul-25, CABLE TRAYS
JAH-Z5-ELC-CT340 600mm Cable Tray 21 24-Mar-25 21-Apr-25 600mm Cable Tray

JAH-Z5-ELC-CT345 400mm Cable Tray 14 22-Apr-25 07-May-25 400mm Cable Tray

JAH-Z5-ELC-CT350 300mm Cable Tray 10 08-May-25 19-May-25 300mm Cable Tray

JAH-Z5-ELC-CT355 200mm Cable Tray 8 20-May-25 28-May-25 200mm Cable Tray

JAH-Z5-ELC-CT360 150mm Cable Tray 8 29-May-25 10-Jun-25 150mm Cable Tray

JAH-Z5-ELC-CT365 100mm Cable Tray 6 11-Jun-25 17-Jun-25 100mm Cable Tray

JAH-Z5-ELC-CT370 75mm Cable Tray 5 18-Jun-25 23-Jun-25 75mm Cable Tray

JAH-Z5-ELC-CT375 150mm x 100mm Trunking 7 24-Jun-25 01-Jul-25 150mm x 100mm Trunking

JAH-Z5-ELC-CT380 100mm x 100mm Trunking 6 02-Jul-25 08-Jul-25 100mm x 100mm Trunking

JAH-Z5-ELC-CT385 100mm x 75mm Trunking 7 09-Jul-25 16-Jul-25 100mm x 75mm Trunking

JAH-Z5-ELC-CT390 PVC Ducts150mm dia 5 17-Jul-25 22-Jul-25 PVC Ducts150mm dia

JAH-Z5-ELC-CT395 PVC Ducts100mm dia 4 23-Jul-25 27-Jul-25 PVC Ducts100mm dia

POWER CABLES 113 22-Apr-25 03-Sep-25 03-Sep-25, POWER CABLES


JAH-Z5-ELC-PC480 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 22-Apr-25 05-May-25 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z5-ELC-PC485 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 22-Apr-25 17-May-25 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z5-ELC-PC490 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 22-Apr-25 14-May-25 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z5-ELC-PC495 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 20 15-May-25 10-Jun-25 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z5-ELC-PC500 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 22-May-25 10-Jun-25 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z5-ELC-PC505 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 24-May-25 10-Jun-25 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z5-ELC-PC510 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 15-May-25 10-Jun-25 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z5-ELC-PC515 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 20-May-25 10-Jun-25 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z5-ELC-PC520 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 20-May-25 10-Jun-25 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z5-ELC-PC525 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 11-Jun-25 23-Jun-25 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z5-ELC-PC530 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 12-Jun-25 23-Jun-25 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z5-ELC-PC535 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 24-Jun-25 01-Jul-25 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z5-ELC-PC540 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 02-Jul-25 02-Aug-25 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z5-ELC-PC545 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 20 10-Jul-25 02-Aug-25 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z5-ELC-PC550 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 03-Aug-25 10-Aug-25 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z5-ELC-PC555 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 11-Aug-25 18-Aug-25 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

JAH-Z5-ELC-PC560 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 28-Jul-25 26-Aug-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z5-ELC-PC565 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 30 23-Jul-25 26-Aug-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

JAH-Z5-ELC-PC570 Testing work 7 27-Aug-25 03-Sep-25 Testing work

ELECTRICAL INSTALLATIONS 86 15-May-25 26-Aug-25 26-Aug-25, ELECTRICAL INSTALLATIONS


JAH-Z5-ELC-INS258 Circuit Wiring Installation 22 15-May-25 12-Jun-25 Circuit Wiring Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
383 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z5-ELC-INS260 Wiring Accessories 15 14-Jun-25 30-Jun-25 Wiring Accessories

JAH-Z5-ELC-INS265 Lighting Installation 14 01-Jul-25 16-Jul-25 Lighting Installation

JAH-Z5-ELC-INS270 Isolators Installation 12 17-Jul-25 30-Jul-25 Isolators Installation

JAH-Z5-ELC-INS280 SMDB Installation 5 31-Jul-25 05-Aug-25 SMDB Installation

JAH-Z5-ELC-INS285 Motor Control Centres Installation 5 06-Aug-25 11-Aug-25 Motor Control Centres Installation

JAH-Z5-ELC-INS290 Distribution Boards 6 12-Aug-25 18-Aug-25 Distribution Boards

JAH-Z5-ELC-INS295 Testing work 7 19-Aug-25 26-Aug-25 Testing work

LOW CURRENT 110 24-Mar-25 06-Aug-25 06-Aug-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 82 24-Mar-25 05-Jul-25 05-Jul-25, FIRE DETECTION AND ALARM SYSTEM
JAH-Z5-LOW-FDT338 Fibre-optic Sensing Cable Laying 12 24-Mar-25 10-Apr-25 Fibre-optic Sensing Cable Laying

JAH-Z5-LOW-FDT340 Fire Alarm Control Panel Installation 6 12-Apr-25 17-Apr-25 Fire Alarm Control Panel Installation

JAH-Z5-LOW-FDT345 Tamper switch Installation 5 19-Apr-25 23-Apr-25 Tamper switch Installation

JAH-Z5-LOW-FDT350 Zone Input units Installation 5 24-Apr-25 29-Apr-25 Zone Input units Installation

JAH-Z5-LOW-FDT355 Fire Alarm sounder Installation 4 30-Apr-25 04-May-25 Fire Alarm sounder Installation

JAH-Z5-LOW-FDT360 Fire Alarm Speaker Installation 8 05-May-25 13-May-25 Fire Alarm Speaker Installation

JAH-Z5-LOW-FDT365 Smoke Detector Installation 8 14-May-25 22-May-25 Smoke Detector Installation

JAH-Z5-LOW-FDT370 Heat Detector Installation 8 24-May-25 01-Jun-25 Heat Detector Installation

JAH-Z5-LOW-FDT375 Interface Module Installation 8 02-Jun-25 14-Jun-25 Interface Module Installation

JAH-Z5-LOW-FDT385 Double Action Manual Call Point Installation 7 15-Jun-25 22-Jun-25 Double Action Manual Call Point Installation

JAH-Z5-LOW-FDT390 Flashing Beacon Installation 6 23-Jun-25 29-Jun-25 Flashing Beacon Installation

JAH-Z5-LOW-FDT395 Testing work 5 30-Jun-25 05-Jul-25 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 28 12-Apr-25 13-May-25 13-May-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z5-LOW-PH180 8 core UTP Cable Laying 7 12-Apr-25 19-Apr-25 8 core UTP Cable Laying

JAH-Z5-LOW-PH185 Junction box Installation 7 20-Apr-25 27-Apr-25 Junction box Installation

JAH-Z5-LOW-PH190 Emergency Telephone Installation 7 28-Apr-25 05-May-25 Emergency Telephone Installation

JAH-Z5-LOW-PH195 Connection and Testing 7 06-May-25 13-May-25 Connection and Testing

PUBLIC ADDRESS 28 20-Apr-25 21-May-25 21-May-25, PUBLIC ADDRESS


JAH-Z5-LOW-PA178 Cables laying public address system 7 20-Apr-25 27-Apr-25 Cables laying public address system

JAH-Z5-LOW-PA180 Wall-mounted Voice Evacuation Horn Speaker Installation 7 28-Apr-25 05-May-25 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z5-LOW-PA185 Voice alarm control panel Installation 7 06-May-25 13-May-25 Voice alarm control panel Installation

JAH-Z5-LOW-PA195 Connection and Testing 7 14-May-25 21-May-25 Connection and Testing

VIDEO SURVEILLANCE 49 28-Apr-25 26-Jun-25 26-Jun-25, VIDEO SURVEILLANCE


JAH-Z5-LOW-VDS240Single Core Fibre Optical Cable Laying 7 28-Apr-25 05-May-25 Single Core Fibre Optical Cable Laying

JAH-Z5-LOW-VDS245RTU Panel Installation 7 06-May-25 13-May-25 RTU Panel Installation

JAH-Z5-LOW-VDS250Overhead Vehicle Detector Installation 7 14-May-25 21-May-25 Overhead Vehicle Detector Installation

JAH-Z5-LOW-VDS255Door Contact Installation 7 22-May-25 29-May-25 Door Contact Installation

JAH-Z5-LOW-VDS260PTZ Camera mounted on Pole Installation 7 31-May-25 10-Jun-25 PTZ Camera mounted on Pole Installation

JAH-Z5-LOW-VDS265Fixed (AID) Camera Installation 7 11-Jun-25 18-Jun-25 Fixed (AID) Camera Installation

JAH-Z5-LOW-VDS270Testing work 7 19-Jun-25 26-Jun-25 Testing work

SACADA SYSTEM 35 28-Jun-25 06-Aug-25 06-Aug-25, SACADA SYSTEM


JAH-Z5-LOW-SCA200Cabling Laying 7 28-Jun-25 05-Jul-25 Cabling Laying

JAH-Z5-LOW-SCA205Remote Terminal Unit Installation 7 06-Jul-25 13-Jul-25 Remote Terminal Unit Installation

JAH-Z5-LOW-SCA210Programmable Logic Control Unit Installation 7 14-Jul-25 21-Jul-25 Programmable Logic Control Unit Installation

JAH-Z5-LOW-SCA215SCADA/ PC/ Soft ware/ Printers Installation 7 22-Jul-25 29-Jul-25 SCADA/ PC/ Soft ware/ Printers Installation

JAH-Z5-LOW-SCA220Testing work 7 30-Jul-25 06-Aug-25 Testing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
384 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
RADIO RE-BROADCASTING SYSTEM 28 28-Apr-25 29-May-25 29-May-25, RADIO RE-BROADCASTING SYSTEM
JAH-Z5-LOW-RDO180Leaky Feeder Cable Laying 7 28-Apr-25 05-May-25 Leaky Feeder Cable Laying

JAH-Z5-LOW-RDO185Inline Bidirectional Signal Amplifier Installation 7 06-May-25 13-May-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z5-LOW-RDO190End of Line Terminator 7 14-May-25 21-May-25 End of Line Terminator

JAH-Z5-LOW-RDO195Connection and Testing 7 22-May-25 29-May-25 Connection and Testing

TUNNEL PLUMBING WORKS 35 27-Aug-25 07-Oct-25 07-Oct-25, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 27-Aug-25 07-Oct-25 07-Oct-25, DRAINAGE SYSTEM
JAH-Z5-PLM-DS140 Drainage Pipes Installation Incl. Fittings & Accessories 15 27-Aug-25 13-Sep-25 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z5-PLM-DS145 Collection Chambers 20 14-Sep-25 07-Oct-25 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 08-Oct-25 25-Nov-25 25-Nov-25, TUNNEL INTERNAL ROAD WORK
JAH-Z5-TIRW.475 Kerbs, Channels & Edging 7 08-Oct-25 15-Oct-25 Kerbs, Channels & Edging

JAH-Z5-TIRW.480 Tack Coat Application (MC-1) 10 16-Oct-25 27-Oct-25 Tack Coat Application (MC-1)

JAH-Z5-TIRW.485 Bituminious Base Course Layer 10 16-Oct-25 27-Oct-25 Bituminious Base Course Layer

JAH-Z5-TIRW.490 Tack Coat Application (RC-2) 12 28-Oct-25 10-Nov-25 Tack Coat Application (RC-2)

JAH-Z5-TIRW.495 Asphalt Wearing Course Layer 12 28-Oct-25 10-Nov-25 Asphalt Wearing Course Layer

JAH-Z5-TIRW.500 Pavement Line Marking 5 11-Nov-25 16-Nov-25 Pavement Line Marking

JAH-Z5-TIRW.505 Traffic Signboards Installation 8 17-Nov-25 25-Nov-25 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 40 11-Nov-25 27-Dec-25 27-Dec-25, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z5-DW.230 Fire Protection Board Installation 10 11-Nov-25 22-Nov-25 Fire Protection Board Installation

JAH-Z5-DW.235 GRC Panel Board Installation 30 23-Nov-25 27-Dec-25 GRC Panel Board Installation

ZONE 6 - FROM STA. 2+157 ~ 2+826.33 887 27-Jun-22 A 24-Aug-25 24-Aug-25, ZONE 6 - FROM STA. 2+157 ~ 2+826.33
ENGINEERING 396 27-Jun-22 A 11-Jan-24 11-Jan-24, ENGINEERING
RAM165 Completion Engineering Work For Zone6 0 11-Jan-24* Completion Engineering Work For Zone6

SITE SURVEY 41 27-Jun-22 A 04-Oct-22 A 04-Oct-22 A, SITE SURVEY


JAH-Z6-EN-SS.150 Site Survey/Settingout Control Points 3 27-Jun-22 A 27-Sep-22 A Site Survey/Settingout Control Points

JAH-Z6-EN-SS.155 Review and Approval of Site Survey & Control Points 7 30-Jun-22 A 04-Oct-22 A Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 192 28-Jun-22 A 27-Dec-22 27-Dec-22, SHOP DRAWINGS


CIVIL/STRUCTURAL 2+157 ~2+258 108 28-Jun-22 A 24-Nov-22 24-Nov-22, CIVIL/STRUCTURAL 2+157 ~2+258
JAH-Z6-ENG-CS.500 Plan and Profile Shop Drawings Preparation & Submission 6 28-Jun-22 A 10-Sep-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.505 Plan and Profile Shop Drawings Review & Approval 12 05-Jul-22 A 21-Sep-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z6-ENG-CS.510 Tunnel Structural Shop Drawings Submission 6 18-Sep-22 A 05-Nov-22 Tunnel Structural Shop Drawings Submission

JAH-Z6-ENG-CS.515 Tunnel Structural Shop Drawings Review & Approval 12 05-Nov-22 17-Nov-22 Tunnel Structural Shop Drawings Review & Approval

JAH-Z6-ENG-CS.520 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 06-Aug-22 A 24-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.525 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 13-Aug-22 A 28-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z6-ENG-CS.530 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 29-Oct-22 03-Nov-22 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.535 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 05-Nov-22 17-Nov-22 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z6-ENG-CS.540 Embedded Items Shop Drawings Preparation & Submission 6 05-Nov-22 10-Nov-22 Embedded Items Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.545 Embedded Items Shop Drawings Review & Approval 12 12-Nov-22 24-Nov-22 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 2+258 ~2+358 130 06-Aug-22 A 27-Nov-22 27-Nov-22, CIVIL/STRUCTURAL 2+258 ~2+358
JAH-Z6-ENG-CS.450 Plan and Profile Shop Drawings Preparation & Submission 6 06-Aug-22 A 08-Sep-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.455 Plan and Profile Shop Drawings Review & Approval 12 13-Aug-22 A 01-Oct-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z6-ENG-CS.460 Tunnel Structural Shop Drawings Submission 6 22-Sep-22 A 07-Nov-22 Tunnel Structural Shop Drawings Submission

JAH-Z6-ENG-CS.465 Tunnel Structural Shop Drawings Review & Approval 12 07-Nov-22 20-Nov-22 Tunnel Structural Shop Drawings Review & Approval

JAH-Z6-ENG-CS.470 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 10-Sep-22 A 24-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.475 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 24-Sep-22 A 28-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z6-ENG-CS.480 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 03-Sep-22 A 06-Nov-22 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
385 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ENG-CS.485 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 11-Sep-22 A 08-Nov-22 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z6-ENG-CS.490 Embedded Items Shop Drawings Preparation & Submission 6 07-Nov-22 13-Nov-22 Embedded Items Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.495 Embedded Items Shop Drawings Review & Approval 12 14-Nov-22 27-Nov-22 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 2+358 ~2+469 152 28-Aug-22 A 06-Dec-22 06-Dec-22, CIVIL/STRUCTURAL 2+358 ~2+469
JAH-Z6-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 06-Sep-22 A 10-Sep-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 10-Sep-22 A 21-Sep-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z6-ENG-CS.410 Tunnel Structural Shop Drawings Submission 6 25-Oct-22 A 15-Nov-22 Tunnel Structural Shop Drawings Submission

JAH-Z6-ENG-CS.415 Tunnel Structural Shop Drawings Review & Approval 12 16-Nov-22 29-Nov-22 Tunnel Structural Shop Drawings Review & Approval

JAH-Z6-ENG-CS.420 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 17-Sep-22 A 24-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.425 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 24-Sep-22 A 28-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z6-ENG-CS.430 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 28-Aug-22 A 08-Nov-22 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.435 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 03-Sep-22 A 10-Nov-22 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z6-ENG-CS.440 Embedded Items Shop Drawings Preparation & Submission 6 16-Nov-22 22-Nov-22 Embedded Items Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.445 Embedded Items Shop Drawings Review & Approval 12 23-Nov-22 06-Dec-22 Embedded Items Shop Drawings Review & Approval

CIVIL/STRUCTURAL 2+469 ~2+518 180 09-Aug-22 A 01-Dec-22 01-Dec-22, CIVIL/STRUCTURAL 2+469 ~2+518
JAH-Z6-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 09-Aug-22 A 21-Aug-22 A Plan and Profile Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 21-Aug-22 A 01-Sep-22 A Plan and Profile Shop Drawings Review & Approval

JAH-Z6-ENG-CS.357 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 25-Aug-22 A 28-Aug-22 A Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.358 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 28-Aug-22 A 07-Sep-22 A Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z6-ENG-CS.360 Tunnel Structural Shop Drawings Submission 6 05-Sep-22 A 10-Nov-22 Tunnel Structural Shop Drawings Submission

JAH-Z6-ENG-CS.365 Tunnel Structural Shop Drawings Review & Approval 12 14-Sep-22 A 13-Nov-22 Tunnel Structural Shop Drawings Review & Approval

JAH-Z6-ENG-CS.370 Dry & Wet Utility Culvert Shop Drawings Preparation & Submission 6 17-Sep-22 A 24-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.375 Dry & Wet Utility Culvert Shop Drawings Review & Approval 12 24-Sep-22 A 28-Sep-22 A Dry & Wet Utility Culvert Shop Drawings Review & Approval

JAH-Z6-ENG-CS.390 Embedded Items Shop Drawings Preparation & Submission 6 12-Nov-22 17-Nov-22 Embedded Items Shop Drawings Preparation & Submission

JAH-Z6-ENG-CS.395 Embedded Items Shop Drawings Review & Approval 12 19-Nov-22 01-Dec-22 Embedded Items Shop Drawings Review & Approval

ARCHITECTURAL 22 03-Dec-22 27-Dec-22 27-Dec-22, ARCHITECTURAL


JAH-Z6-ENG-AR.150 Tunnel Architectural Shop Drawings Preparation & Submission 10 03-Dec-22 13-Dec-22 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z6-ENG-AR.155 Tunnel Architectural Shop Drawings Review & Approval 12 14-Dec-22 27-Dec-22 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 341 03-Dec-22 11-Jan-24 11-Jan-24, UTILITIES


WET UTILITIES 214 03-Dec-22 15-Aug-23 15-Aug-23, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 121 03-Dec-22 25-Apr-23 25-Apr-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
JAH-Z6-EN-WU-PW.100Shop Drawings Preparation & Submission 10 03-Dec-22 13-Dec-22 Shop Drawings Preparation & Submission

JAH-Z6-EN-WU-PW.105Shop Drawings Review & Approval 12 09-Apr-23 25-Apr-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 25 26-Apr-23 24-May-23 24-May-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
JAH-Z6-EN-WU-GW.100
Shop Drawings Preparation & Submission 13 26-Apr-23 10-May-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-WU-GW.105
Shop Drawings Review & Approval 12 11-May-23 24-May-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 22 25-May-23 19-Jun-23 19-Jun-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
JAH-Z6-EN-WU-IRR.100
Shop Drawings Preparation & Submission 10 25-May-23 05-Jun-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-WU-IRR.105
Shop Drawings Review & Approval 12 06-Jun-23 19-Jun-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 27 20-Jun-23 24-Jul-23 24-Jul-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
JAH-Z6-EN-WU-CWS.100
Shop Drawings Preparation & Submission 15 20-Jun-23 10-Jul-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-WU-CWS.105
Shop Drawings Review & Approval 12 11-Jul-23 24-Jul-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 19 25-Jul-23 15-Aug-23 15-Aug-23, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z6-EN-WU-AUW.170
Shop Drawings Preparation & Submission 7 25-Jul-23 01-Aug-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-WU-AUW.175
Shop Drawings Review & Approval 12 02-Aug-23 15-Aug-23 Shop Drawings Review & Approval

DRY UTILITIES 127 16-Aug-23 11-Jan-24 11-Jan-24, DRY UTILITIES


POWER 110 16-Aug-23 23-Dec-23 23-Dec-23, POWER

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
386 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
HIGH VOLTAGE 110 KV NETWORK 22 16-Aug-23 10-Sep-23 10-Sep-23, HIGH VOLTAGE 110 KV NETWORK
JAH-Z6-EN-DU-PWR.390
Shop Drawings Preparation & Submission 10 16-Aug-23 27-Aug-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-PWR.395
Shop Drawings Review & Approval 12 28-Aug-23 10-Sep-23 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 25 11-Sep-23 10-Oct-23 10-Oct-23, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z6-EN-DU-PWR.400
Shop Drawings Preparation & Submission 13 11-Sep-23 26-Sep-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-PWR.405
Shop Drawings Review & Approval 12 27-Sep-23 10-Oct-23 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 19 11-Oct-23 01-Nov-23 01-Nov-23, LOW VOLTAGE NETWORK


JAH-Z6-EN-DU-PWR.410
Shop Drawings Preparation & Submission 7 11-Oct-23 18-Oct-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-PWR.415
Shop Drawings Review & Approval 12 19-Oct-23 01-Nov-23 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 22 02-Nov-23 27-Nov-23 27-Nov-23, ELECTRICAL DISTRIBUTION SYSTEM


JAH-Z6-EN-DU-PWR.420
Shop Drawings Preparation & Submission 10 02-Nov-23 13-Nov-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-PWR.425
Shop Drawings Review & Approval 12 14-Nov-23 27-Nov-23 Shop Drawings Review & Approval

LIGHTING SYSTEM 22 28-Nov-23 23-Dec-23 23-Dec-23, LIGHTING SYSTEM


JAH-Z6-EN-DU-PWR.430
Shop Drawings Preparation & Submission 10 28-Nov-23 09-Dec-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-PWR.435
Shop Drawings Review & Approval 12 10-Dec-23 23-Dec-23 Shop Drawings Review & Approval

LOW CURRENT 17 24-Dec-23 11-Jan-24 11-Jan-24, LOW CURRENT


TELECOM SERVICES 17 24-Dec-23 11-Jan-24 11-Jan-24, TELECOM SERVICES
JAH-Z6-EN-DU-LC.180Shop Drawings Preparation & Submission 5 24-Dec-23 28-Dec-23 Shop Drawings Preparation & Submission

JAH-Z6-EN-DU-LC.185Shop Drawings Review & Approval 12 30-Dec-23 11-Jan-24 Shop Drawings Review & Approval

MEP 220 03-Dec-22 22-Aug-23 22-Aug-23, MEP


TUNNEL MECHANICAL WORKS 176 03-Dec-22 02-Jul-23 02-Jul-23, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 03-Dec-22 14-Mar-23 14-Mar-23, FIRE FIGHTING SYSTEM
JAH-Z6-EN-MP-FF.300 Fire Fighting Pipe Layout Plan Preparation & Submission 10 03-Dec-22 13-Dec-22 Fire Fighting Pipe Layout Plan Preparation & Submission

JAH-Z6-EN-MP-FF.305 Fire Fighting Pipe Layout Plan Review & Approval 12 14-Dec-22 27-Dec-22 Fire Fighting Pipe Layout Plan Review & Approval

JAH-Z6-EN-MP-FF.310 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 28-Dec-22 08-Jan-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

JAH-Z6-EN-MP-FF.315 Fire Fighting Sprinkler Layout Plan Review & Approval 12 09-Jan-23 22-Jan-23 Fire Fighting Sprinkler Layout Plan Review & Approval

JAH-Z6-EN-MP-FF.320 Foam Tank Installation Layout Preparation & Submission 10 23-Jan-23 02-Feb-23 Foam Tank Installation Layout Preparation & Submission

JAH-Z6-EN-MP-FF.325 Foam Tank Installation Layout Review & Approval 12 04-Feb-23 16-Feb-23 Foam Tank Installation Layout Review & Approval

JAH-Z6-EN-MP-FF.330 Fire Extinguishers Layout Plan Preparation & Submission 10 18-Feb-23 28-Feb-23 Fire Extinguishers Layout Plan Preparation & Submission

JAH-Z6-EN-MP-FF.335 Fire Extinguishers Layout Plan Review & Approval 12 01-Mar-23 14-Mar-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 01-Mar-23 20-Apr-23 20-Apr-23, VENTILATION SYSTEM


JAH-Z6-EN-MP-VS.200Fan Layout Preparation & Submission 10 01-Mar-23 12-Mar-23 Fan Layout Preparation & Submission

JAH-Z6-EN-MP-VS.205Fan Layout Review & Approval 12 13-Mar-23 26-Mar-23 Fan Layout Review & Approval

JAH-Z6-EN-MP-VS.210Cable Route Shop Drawing Preparation & Submission 10 27-Mar-23 06-Apr-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z6-EN-MP-VS.215Cable Route Shop Drawing Review & Approval 12 08-Apr-23 20-Apr-23 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 25-Apr-23 20-May-23 20-May-23, PUMPS INSTALLATION


JAH-Z6-EN-MP-PI.150 Sump Pump Diagram Preparation & Submission 10 25-Apr-23 06-May-23 Sump Pump Diagram Preparation & Submission

JAH-Z6-EN-MP-PI.155 Sump Pump Diagram Review & Approval 12 07-May-23 20-May-23 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 15-Mar-23 02-Jul-23 02-Jul-23, DUCTING SYSTEM


JAH-Z6-EN-MP-DCS.300
Duct Layout Drawing Preparation & Submission 10 15-Mar-23 26-Mar-23 Duct Layout Drawing Preparation & Submission

JAH-Z6-EN-MP-DCS.305
Duct Layout Drawing Review & Approval 12 27-Mar-23 09-Apr-23 Duct Layout Drawing Review & Approval

JAH-Z6-EN-MP-DCS.310
Diffuser Details Review & Approval 12 25-Apr-23 08-May-23 Diffuser Details Review & Approval

JAH-Z6-EN-MP-DCS.315
Dampers Details Preparation & Submission 10 09-May-23 20-May-23 Dampers Details Preparation & Submission

JAH-Z6-EN-MP-DCS.320
Dampers Details Review & Approval 12 21-May-23 03-Jun-23 Dampers Details Review & Approval

JAH-Z6-EN-MP-DCS.325
Sand Trap Louvre Layout Drawing Preparation & Submission 10 04-Jun-23 14-Jun-23 Sand Trap Louvre Layout Drawing Preparation & Submission

JAH-Z6-EN-MP-DCS.330
Sand Trap Louvre Layout Drawing Review & Approval 12 15-Jun-23 02-Jul-23 Sand Trap Louvre Layout Drawing Review & Approval

JAH-Z6-EN-MP-DCS.335
Diffuser Details Drawing Preparation & Submission 10 10-Apr-23 20-Apr-23 Diffuser Details Drawing Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
387 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
TUNNEL ELECTRICAL WORKS 210 14-Dec-22 22-Aug-23 22-Aug-23, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 14-Dec-22 20-Apr-23 20-Apr-23, CABLE TRAYS
JAH-Z6-EN-EL-CTR.350Cable Tray Layout Drawing Preparation & Submission 10 14-Dec-22 25-Dec-22 Cable Tray Layout Drawing Preparation & Submission

JAH-Z6-EN-EL-CTR.355Cable Tray Layout Drawing Review & Approval 12 26-Dec-22 08-Jan-23 Cable Tray Layout Drawing Review & Approval

JAH-Z6-EN-EL-CTR.360Cable Tray Diversion Details Preparation & Submission 10 09-Jan-23 19-Jan-23 Cable Tray Diversion Details Preparation & Submission

JAH-Z6-EN-EL-CTR.365Cable Tray Diversion Details Review & Approval 12 21-Jan-23 02-Feb-23 Cable Tray Diversion Details Review & Approval

JAH-Z6-EN-EL-CTR.370Cable Tray Fixing Details Preparation & Submission 10 04-Feb-23 14-Feb-23 Cable Tray Fixing Details Preparation & Submission

JAH-Z6-EN-EL-CTR.375Cable Tray Fixing Details Review & Approval 12 15-Feb-23 28-Feb-23 Cable Tray Fixing Details Review & Approval

JAH-Z6-EN-EL-CTR.380Cable Tray Sections Preparation & Submission 10 01-Mar-23 12-Mar-23 Cable Tray Sections Preparation & Submission

JAH-Z6-EN-EL-CTR.385Cable Tray Sections Review & Approval 12 13-Mar-23 26-Mar-23 Cable Tray Sections Review & Approval

JAH-Z6-EN-EL-CTR.390PVC DuctsSections Preparation & Submission 10 27-Mar-23 06-Apr-23 PVC DuctsSections Preparation & Submission

JAH-Z6-EN-EL-CTR.395PVC Sections Review & Approval 12 08-Apr-23 20-Apr-23 PVC Sections Review & Approval

POWER CABLES 44 15-Feb-23 06-Apr-23 06-Apr-23, POWER CABLES


JAH-Z6-EN-EL-PC.200 Cable Route Shop Drawing Preparation & Submission 10 15-Feb-23 26-Feb-23 Cable Route Shop Drawing Preparation & Submission

JAH-Z6-EN-EL-PC.205 Cable Route Shop Drawing Review & Approval 12 27-Feb-23 12-Mar-23 Cable Route Shop Drawing Review & Approval

JAH-Z6-EN-EL-PC.210 Junction Box Layout Plan Preparation & Submission 10 13-Mar-23 23-Mar-23 Junction Box Layout Plan Preparation & Submission

JAH-Z6-EN-EL-PC.215 Junction Box Layout Plan Review & Approval 12 25-Mar-23 06-Apr-23 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 27-Feb-23 11-Jul-23 11-Jul-23, ELECTRICAL INSTALLATIONS


JAH-Z6-EN-EL-ELI.350Wiring Accessories Diagram Preparation & Submission 10 27-Feb-23 09-Mar-23 Wiring Accessories Diagram Preparation & Submission

JAH-Z6-EN-EL-ELI.355Lighting Layout Drawing Preparation & Submission 10 25-Mar-23 04-Apr-23 Lighting Layout Drawing Preparation & Submission

JAH-Z6-EN-EL-ELI.360Circuit Wiring Diagram Preparation & Submission 10 19-Apr-23 03-May-23 Circuit Wiring Diagram Preparation & Submission

JAH-Z6-EN-EL-ELI.365Circuit Wiring Diagram Review & Approval 12 04-May-23 17-May-23 Circuit Wiring Diagram Review & Approval

JAH-Z6-EN-EL-ELI.370SMDB Line Diagram Preparation & Submission 10 18-May-23 29-May-23 SMDB Line Diagram Preparation & Submission

JAH-Z6-EN-EL-ELI.375SMDB Line Diagram Review & Approval 12 30-May-23 12-Jun-23 SMDB Line Diagram Review & Approval

JAH-Z6-EN-EL-ELI.380Distribution Board Line Diagram Preparation & Submission 10 13-Jun-23 24-Jun-23 Distribution Board Line Diagram Preparation & Submission

JAH-Z6-EN-EL-ELI.385Lighting Layout Drawing Review & Approval 12 05-Apr-23 18-Apr-23 Lighting Layout Drawing Review & Approval

JAH-Z6-EN-EL-ELI.390Wiring Accessories Diagram Review & Approval 12 11-Mar-23 23-Mar-23 Wiring Accessories Diagram Review & Approval

JAH-Z6-EN-EL-ELI.395Distribution Board Line Diagram Review & Approval 12 25-Jun-23 11-Jul-23 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 15-Mar-23 22-Aug-23 22-Aug-23, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 15-Mar-23 22-Aug-23 22-Aug-23, FIRE DETECTION AND ALARM SYSTEM
JAH-Z6-EN-LW-FD.400Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 15-Mar-23 26-Mar-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.405Fire Alarm Control Panel Layout Drawing Review & Approval 12 27-Mar-23 09-Apr-23 Fire Alarm Control Panel Layout Drawing Review & Approval

JAH-Z6-EN-LW-FD.410Fire Alarm Speaker Layout Drawing Preparation & Submission 10 10-Apr-23 20-Apr-23 Fire Alarm Speaker Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.415Fire Alarm Speaker Layout Drawing Review & Approval 12 25-Apr-23 08-May-23 Fire Alarm Speaker Layout Drawing Review & Approval

JAH-Z6-EN-LW-FD.420Fire Alarm sounder Layout Drawing Preparation & Submission 10 09-May-23 20-May-23 Fire Alarm sounder Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.425Fire Alarm sounder Layout Drawing Review & Approval 12 21-May-23 03-Jun-23 Fire Alarm sounder Layout Drawing Review & Approval

JAH-Z6-EN-LW-FD.430Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 04-Jun-23 14-Jun-23 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.435Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 15-Jun-23 02-Jul-23 Smoke Detector & Heat Detector Layout Drawing Review & Approval

JAH-Z6-EN-LW-FD.440Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 03-Jul-23 13-Jul-23 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.445Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 15-Jul-23 27-Jul-23 Fibre-optic Sensing Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-FD.450Double Action Manual Call Point Layout Drawing Preparation & Submission 10 29-Jul-23 08-Aug-23 Double Action Manual Call Point Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-FD.455Double Action Manual Call Point Layout Drawing Review & Approval 12 09-Aug-23 22-Aug-23 Double Action Manual Call Point Layout Drawing Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 27-Mar-23 08-Aug-23 08-Aug-23, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z6-EN-LW-TPH.350
8 core UTP Cable Laying 14 27-Mar-23 11-Apr-23 8 core UTP Cable Laying

JAH-Z6-EN-LW-TPH.355
Junction box Installation 8 12-Apr-23 20-Apr-23 Junction box Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
388 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-EN-LW-TPH.360
Emergency Telephone Installation 14 25-Apr-23 10-May-23 Emergency Telephone Installation

JAH-Z6-EN-LW-TPH.365
Connection and Testing 8 11-May-23 20-May-23 Connection and Testing

JAH-Z6-EN-LW-TPH.370
8 Core UTP Cable Layout Drawing Preparation & Submission 10 21-May-23 31-May-23 8 Core UTP Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-TPH.375
8 Core UTP Cable Layout Drawing Review & Approval 12 01-Jun-23 14-Jun-23 8 Core UTP Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-TPH.380
Junction box Layout Drawing Preparation & Submission 10 15-Jun-23 26-Jun-23 Junction box Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-TPH.385
Junction box Layout Drawing Review & Approval 12 01-Jul-23 13-Jul-23 Junction box Layout Drawing Review & Approval

JAH-Z6-EN-LW-TPH.390
Telephone Location Layout Preparation & Submission 10 15-Jul-23 25-Jul-23 Telephone Location Layout Preparation & Submission

JAH-Z6-EN-LW-TPH.395
Telephone Location Layout Review & Approval 12 26-Jul-23 08-Aug-23 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 12-Apr-23 04-Jul-23 04-Jul-23, PUBLIC ADDRESS


JAH-Z6-EN-LW-PA.101Cable Layout Drawing Preparation & Submission 10 12-Apr-23 26-Apr-23 Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-PA.106Cable Layout Drawing Review & Approval 12 27-Apr-23 10-May-23 Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-PA.111Voice alarm control panel Drawing Preparation & Submission 10 11-May-23 22-May-23 Voice alarm control panel Drawing Preparation & Submission

JAH-Z6-EN-LW-PA.116Voice alarm control panel Drawing Review & Approval 12 23-May-23 05-Jun-23 Voice alarm control panel Drawing Review & Approval

JAH-Z6-EN-LW-PA.121Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 06-Jun-23 17-Jun-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

JAH-Z6-EN-LW-PA.126Voice Evacuation Horn Speaker Drawing Preparation & Submission 12 18-Jun-23 04-Jul-23 Voice Evacuation Horn Speaker Drawing Preparation & Submission

VIDEO SURVEILLANCE 44 27-Apr-23 17-Jun-23 17-Jun-23, VIDEO SURVEILLANCE


JAH-Z6-EN-LW-VID.200
Cable Layout Drawing Preparation & Submission 10 27-Apr-23 08-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-VID.205
Cable Layout Drawing Review & Approval 12 09-May-23 22-May-23 Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-VID.210
Camera Layout Drawing Preparation & Submission 10 23-May-23 03-Jun-23 Camera Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-VID.215
Camera Layout Drawing Review & Approval 12 04-Jun-23 17-Jun-23 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 09-May-23 02-Jul-23 02-Jul-23, SACADA SYSTEM


JAH-Z6-EN-LW-SCA.200
Cable Layout Drawing Preparation & Submission 10 09-May-23 20-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-SCA.205
Cable Layout Drawing Review & Approval 12 21-May-23 03-Jun-23 Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-SCA.210
Installation Layout Drawing Preparation & Submission 10 04-Jun-23 14-Jun-23 Installation Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-SCA.215
Installation Layout Drawing Review & Approval 12 15-Jun-23 02-Jul-23 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 21-May-23 13-Jul-23 13-Jul-23, RADIO RE-BROADCASTING SYSTEM


JAH-Z6-EN-LW-RDO.200
Cable Layout Drawing Preparation & Submission 10 21-May-23 31-May-23 Cable Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-RDO.205
Cable Layout Drawing Review & Approval 12 01-Jun-23 14-Jun-23 Cable Layout Drawing Review & Approval

JAH-Z6-EN-LW-RDO.210
Installation Layout Drawing Preparation & Submission 10 15-Jun-23 26-Jun-23 Installation Layout Drawing Preparation & Submission

JAH-Z6-EN-LW-RDO.215
Installation Layout Drawing Review & Approval 12 01-Jul-23 13-Jul-23 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 26-Dec-22 18-Jan-23 18-Jan-23, TUNNEL PLUMBING WORKS


JAH-Z6-ENG-PLM.150 Plumbing Services Shop Drawings Preparation & Submission 9 26-Dec-22 04-Jan-23 Plumbing Services Shop Drawings Preparation & Submission

JAH-Z6-ENG-PLM.155 Plumbing Shop Drawings Review & Approval 12 05-Jan-23 18-Jan-23 Plumbing Shop Drawings Review & Approval

PROCUREMENT 445 19-Jan-23 07-Jul-24 07-Jul-24, PROCUREMENT


RAM270 Completion Procurment for Zone 6 0 07-Jul-24* Completion Procurment for Zone 6

CIVIL/STRUCTURAL 60 19-Jan-23 29-Mar-23 29-Mar-23, CIVIL/STRUCTURAL


JAH-Z6-PRO-CSM.200 Request for Quotation 10 19-Jan-23 30-Jan-23 Request for Quotation

JAH-Z6-PRO-CSM.205 Issue Purchase Order 10 31-Jan-23 11-Feb-23 Issue Purchase Order

JAH-Z6-PRO-CSM.210 Material Delivery 30 23-Feb-23 29-Mar-23 Material Delivery

JAH-Z6-PRO-CSM.215 Staging Time 10 12-Feb-23 22-Feb-23 Staging Time

UTILITIES 387 28-Mar-23 07-Jul-24 07-Jul-24, UTILITIES


WET UTILITIES 295 28-Mar-23 13-Mar-24 13-Mar-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 185 28-Mar-23 06-Nov-23 06-Nov-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 26-Apr-23 16-Oct-23 16-Oct-23, DI PIPES
JAH-Z6-PR-WUR-PW.955
Issue Purchase Order 15 08-May-23 24-May-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.960
Staging time 30 25-May-23 02-Jul-23 Staging time

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
389 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-PR-WUR-PW.965
Material Delivery 90 03-Jul-23 16-Oct-23 Material Delivery

JAH-Z6-PR-WUR-PW1130
Request for Quotation 10 26-Apr-23 07-May-23 Request for Quotation

HDPE PIPES 145 26-Apr-23 16-Oct-23 16-Oct-23, HDPE PIPES


JAH-Z6-PR-WUR-PW.970
Issue Purchase Order 15 08-May-23 24-May-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.975
Staging time 30 25-May-23 02-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.980
Material Delivery 90 03-Jul-23 16-Oct-23 Material Delivery

JAH-Z6-PR-WUR-PW1125
Request for Quotation 10 26-Apr-23 07-May-23 Request for Quotation

GRP PIPES 145 26-Apr-23 16-Oct-23 16-Oct-23, GRP PIPES


JAH-Z6-PR-WUR-PW.985
Issue Purchase Order 15 08-May-23 24-May-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.990
Staging time 30 25-May-23 02-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.995
Material Delivery 90 03-Jul-23 16-Oct-23 Material Delivery

JAH-Z6-PR-WUR-PW1120
Request for Quotation 10 26-Apr-23 07-May-23 Request for Quotation

DI & GRP FITTING 145 26-Apr-23 16-Oct-23 16-Oct-23, DI & GRP FITTING
JAH-Z6-PR-WUR-PW.105
Request for Quotation 10 26-Apr-23 07-May-23 Request for Quotation

JAH-Z6-PR-WUR-PW.110
Issue Purchase Order 15 08-May-23 24-May-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.120
Staging time 30 25-May-23 02-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.170
Material Delivery 90 03-Jul-23 16-Oct-23 Material Delivery

GATE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, GATE VALVE


JAH-Z6-PR-WUR-PW.145
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z6-PR-WUR-PW.150
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.180
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.200
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

BUTTERFLAY VALVE 145 17-May-23 06-Nov-23 06-Nov-23, BUTTERFLAY VALVE


JAH-Z6-PR-WUR-PW.140
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z6-PR-WUR-PW.155
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.185
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.205
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

WATER METER 145 28-Mar-23 19-Sep-23 19-Sep-23, WATER METER


JAH-Z6-PR-WUR-PW.100
Request for Quotation 10 28-Mar-23 08-Apr-23 Request for Quotation

JAH-Z6-PR-WUR-PW.115
Issue Purchase Order 15 09-Apr-23 29-Apr-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.125
Staging time 30 30-Apr-23 03-Jun-23 Staging time

JAH-Z6-PR-WUR-PW.175
Material Delivery 90 04-Jun-23 19-Sep-23 Material Delivery

AIR RELASE VALVE 145 17-May-23 06-Nov-23 06-Nov-23, AIR RELASE VALVE
JAH-Z6-PR-WUR-PW.135
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z6-PR-WUR-PW.160
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.190
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.210
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

WASHOUT VALVE 145 17-May-23 06-Nov-23 06-Nov-23, WASHOUT VALVE


JAH-Z6-PR-WUR-PW.130
Request for Quotation 10 17-May-23 28-May-23 Request for Quotation

JAH-Z6-PR-WUR-PW.165
Issue Purchase Order 15 29-May-23 14-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-PW.195
Staging time 30 15-Jun-23 23-Jul-23 Staging time

JAH-Z6-PR-WUR-PW.215
Material Delivery 90 24-Jul-23 06-Nov-23 Material Delivery

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 145 25-May-23 14-Nov-23 14-Nov-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
DI PIPES 145 25-May-23 14-Nov-23 14-Nov-23, DI PIPES
JAH-Z6-PR-WUR-GW.100
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.105
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
390 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-PR-WUR-GW.110
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.140
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

HDPE PIPES 145 25-May-23 14-Nov-23 14-Nov-23, HDPE PIPES


JAH-Z6-PR-WUR-GW.125
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.145
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.155
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.210
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

GRP PIPES 145 25-May-23 14-Nov-23 14-Nov-23, GRP PIPES


JAH-Z6-PR-WUR-GW.115
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.120
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.135
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.165
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

DI & GRP FITTING 145 25-May-23 14-Nov-23 14-Nov-23, DI & GRP FITTING
JAH-Z6-PR-WUR-GW.130
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.150
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.160
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.215
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

GATE VALVE 145 25-May-23 14-Nov-23 14-Nov-23, GATE VALVE


JAH-Z6-PR-WUR-GW.185
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.190
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.220
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.240
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

BUTTERFLAY VALVE 145 25-May-23 14-Nov-23 14-Nov-23, BUTTERFLAY VALVE


JAH-Z6-PR-WUR-GW.180
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.195
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.225
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.245
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

AIR RELASE VALVE 145 25-May-23 14-Nov-23 14-Nov-23, AIR RELASE VALVE
JAH-Z6-PR-WUR-GW.175
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.200
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.230
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.250
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

WASEHOUT VALVE 145 25-May-23 14-Nov-23 14-Nov-23, WASEHOUT VALVE


JAH-Z6-PR-WUR-GW.170
Request for Quotation 10 25-May-23 05-Jun-23 Request for Quotation

JAH-Z6-PR-WUR-GW.205
Issue Purchase Order 15 06-Jun-23 22-Jun-23 Issue Purchase Order

JAH-Z6-PR-WUR-GW.235
Staging time 30 24-Jun-23 31-Jul-23 Staging time

JAH-Z6-PR-WUR-GW.255
Material Delivery 90 01-Aug-23 14-Nov-23 Material Delivery

IRR & FF NETWORK BRANCHES & TIE IN POINTS 160 20-Jun-23 27-Dec-23 27-Dec-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
HDPE PIPES 145 20-Jun-23 10-Dec-23 10-Dec-23, HDPE PIPES
JAH-Z6-PR-WUR-IR.100
Request for Quotation 10 20-Jun-23 04-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.105
Issue Purchase Order 15 05-Jul-23 22-Jul-23 Issue Purchase Order

JAH-Z6-PR-WUR-IR.110
Staging time 30 23-Jul-23 26-Aug-23 Staging time

JAH-Z6-PR-WUR-IR.155
Material Delivery 90 27-Aug-23 10-Dec-23 Material Delivery

GATE VALVE 145 20-Jun-23 10-Dec-23 10-Dec-23, GATE VALVE


JAH-Z6-PR-WUR-IR.130
Request for Quotation 10 20-Jun-23 04-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.135
Issue Purchase Order 15 05-Jul-23 22-Jul-23 Issue Purchase Order

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
391 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-PR-WUR-IR.160
Staging time 30 23-Jul-23 26-Aug-23 Staging time

JAH-Z6-PR-WUR-IR.190
Material Delivery 90 27-Aug-23 10-Dec-23 Material Delivery

BUTTERFLAY VALVE 145 20-Jun-23 10-Dec-23 10-Dec-23, BUTTERFLAY VALVE


JAH-Z6-PR-WUR-IR.125
Request for Quotation 10 20-Jun-23 04-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.140
Issue Purchase Order 15 05-Jul-23 22-Jul-23 Issue Purchase Order

JAH-Z6-PR-WUR-IR.165
Staging time 30 23-Jul-23 26-Aug-23 Staging time

JAH-Z6-PR-WUR-IR.195
Material Delivery 90 27-Aug-23 10-Dec-23 Material Delivery

AIR RELASE VALVE 145 20-Jun-23 10-Dec-23 10-Dec-23, AIR RELASE VALVE
JAH-Z6-PR-WUR-IR.120
Request for Quotation 10 20-Jun-23 04-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.145
Issue Purchase Order 15 05-Jul-23 22-Jul-23 Issue Purchase Order

JAH-Z6-PR-WUR-IR.170
Staging time 30 23-Jul-23 26-Aug-23 Staging time

JAH-Z6-PR-WUR-IR.200
Material Delivery 90 27-Aug-23 10-Dec-23 Material Delivery

WASEHOUT VALVE 145 20-Jun-23 10-Dec-23 10-Dec-23, WASEHOUT VALVE


JAH-Z6-PR-WUR-IR.115
Request for Quotation 10 20-Jun-23 04-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.150
Issue Purchase Order 15 05-Jul-23 22-Jul-23 Issue Purchase Order

JAH-Z6-PR-WUR-IR.175
Staging time 30 23-Jul-23 26-Aug-23 Staging time

JAH-Z6-PR-WUR-IR.205
Material Delivery 90 27-Aug-23 10-Dec-23 Material Delivery

FIRE HYDRANT 145 11-Jul-23 27-Dec-23 27-Dec-23, FIRE HYDRANT


JAH-Z6-PR-WUR-IR.180
Request for Quotation 10 11-Jul-23 22-Jul-23 Request for Quotation

JAH-Z6-PR-WUR-IR.185
Issue Purchase Order 15 23-Jul-23 08-Aug-23 Issue Purchase Order

JAH-Z6-PR-WUR-IR.210
Staging time 30 09-Aug-23 12-Sep-23 Staging time

JAH-Z6-PR-WUR-IR.215
Material Delivery 90 13-Sep-23 27-Dec-23 Material Delivery

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 145 25-Jul-23 10-Jan-24 10-Jan-24, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
MILD STEEL PIPE 145 25-Jul-23 10-Jan-24 10-Jan-24, MILD STEEL PIPE
JAH-Z6-PR-WUR-CW.105
Request for Quotation 10 25-Jul-23 05-Aug-23 Request for Quotation

JAH-Z6-PR-WUR-CW.110
Issue Purchase Order 15 06-Aug-23 22-Aug-23 Issue Purchase Order

JAH-Z6-PR-WUR-CW.120
Staging time 30 23-Aug-23 27-Sep-23 Staging time

JAH-Z6-PR-WUR-CW.130
Material Delivery 90 28-Sep-23 10-Jan-24 Material Delivery

MILD STEEL FITTING 145 25-Jul-23 10-Jan-24 10-Jan-24, MILD STEEL FITTING
JAH-Z6-PR-WUR-CW.100
Request for Quotation 10 25-Jul-23 05-Aug-23 Request for Quotation

JAH-Z6-PR-WUR-CW.115
Issue Purchase Order 15 06-Aug-23 22-Aug-23 Issue Purchase Order

JAH-Z6-PR-WUR-CW.125
Staging time 30 23-Aug-23 27-Sep-23 Staging time

JAH-Z6-PR-WUR-CW.135
Material Delivery 90 28-Sep-23 10-Jan-24 Material Delivery

GATE VALVE 145 25-Jul-23 10-Jan-24 10-Jan-24, GATE VALVE


JAH-Z6-PR-WUR-CW.140
Request for Quotation 10 25-Jul-23 05-Aug-23 Request for Quotation

JAH-Z6-PR-WUR-CW.145
Issue Purchase Order 15 06-Aug-23 22-Aug-23 Issue Purchase Order

JAH-Z6-PR-WUR-CW.150
Staging time 30 23-Aug-23 27-Sep-23 Staging time

JAH-Z6-PR-WUR-CW.155
Material Delivery 90 28-Sep-23 10-Jan-24 Material Delivery

AUTOMATIC WASTE COLLECTION NETWORK 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE COLLECTION NETWORK
AUTOMATIC WASTE 145 27-Sep-23 13-Mar-24 13-Mar-24, AUTOMATIC WASTE
JAH-Z6-PR-WU-AWC.180
Issue Purchase Order 15 09-Oct-23 25-Oct-23 Issue Purchase Order

JAH-Z6-PR-WU-AWC.185
Staging time 30 26-Oct-23 29-Nov-23 Staging time

JAH-Z6-PR-WU-AWC.190
Material Delivery 90 30-Nov-23 13-Mar-24 Material Delivery

JAH-Z6-PR-WU-AWC.195
Request for Quotation 10 27-Sep-23 08-Oct-23 Request for Quotation

DRY UTILITIES 250 11-Sep-23 07-Jul-24 07-Jul-24, DRY UTILITIES


POWER 233 11-Sep-23 12-Jun-24 12-Jun-24, POWER
HIGH VOLTAGE 110 KV NETWORK 145 11-Sep-23 27-Feb-24 27-Feb-24, HIGH VOLTAGE 110 KV NETWORK

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
392 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-PR-DU-PW.665
Request for Quotation 10 11-Sep-23 21-Sep-23 Request for Quotation

JAH-Z6-PR-DU-PW.670
Issue Purchase Order 15 24-Sep-23 10-Oct-23 Issue Purchase Order

JAH-Z6-PR-DU-PW.675
Material Delivery 90 15-Nov-23 27-Feb-24 Material Delivery

JAH-Z6-PR-DU-PW.695
Staging time 30 11-Oct-23 14-Nov-23 Staging time

MEDIUM VOLTAGE 13.8 KV NETWORK 145 11-Oct-23 27-Mar-24 27-Mar-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z6-PR-DU-PW.705
Request for Quotation 10 11-Oct-23 22-Oct-23 Request for Quotation

JAH-Z6-PR-DU-PW.710
Issue Purchase Order 15 23-Oct-23 08-Nov-23 Issue Purchase Order

JAH-Z6-PR-DU-PW.715
Material Delivery 90 14-Dec-23 27-Mar-24 Material Delivery

JAH-Z6-PR-DU-PW.720
Staging time 30 09-Nov-23 13-Dec-23 Staging time

LOW VOLTAGE NETWORK 145 02-Nov-23 22-Apr-24 22-Apr-24, LOW VOLTAGE NETWORK
JAH-Z6-PR-DU-PW.725
Request for Quotation 10 02-Nov-23 13-Nov-23 Request for Quotation

JAH-Z6-PR-DU-PW.730
Issue Purchase Order 15 14-Nov-23 30-Nov-23 Issue Purchase Order

JAH-Z6-PR-DU-PW.735
Material Delivery 90 06-Jan-24 22-Apr-24 Material Delivery

JAH-Z6-PR-DU-PW.740
Staging time 30 02-Dec-23 04-Jan-24 Staging time

ELECTRICAL DISTRIBUTION SYSTEM 145 28-Nov-23 18-May-24 18-May-24, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z6-PR-DU-PW.680
Request for Quotation 10 28-Nov-23 09-Dec-23 Request for Quotation

JAH-Z6-PR-DU-PW.685
Issue Purchase Order 15 10-Dec-23 26-Dec-23 Issue Purchase Order

JAH-Z6-PR-DU-PW.690
Material Delivery 90 31-Jan-24 18-May-24 Material Delivery

JAH-Z6-PR-DU-PW.700
Staging time 30 27-Dec-23 30-Jan-24 Staging time

LIGHTING SYSTEM 145 24-Dec-23 12-Jun-24 12-Jun-24, LIGHTING SYSTEM


JAH-Z6-PR-DU-PW.745
Request for Quotation 10 24-Dec-23 03-Jan-24 Request for Quotation

JAH-Z6-PR-DU-PW.750
Issue Purchase Order 15 04-Jan-24 21-Jan-24 Issue Purchase Order

JAH-Z6-PR-DU-PW.755
Material Delivery 90 26-Feb-24 12-Jun-24 Material Delivery

JAH-Z6-PR-DU-PW.760
Staging time 30 22-Jan-24 25-Feb-24 Staging time

LOW CURRENT 145 13-Jan-24 07-Jul-24 07-Jul-24, LOW CURRENT


TELECOM SERVICES 145 13-Jan-24 07-Jul-24 07-Jul-24, TELECOM SERVICES
JAH-Z6-PR-DU-LC.245Request for Quotation 10 13-Jan-24 23-Jan-24 Request for Quotation

JAH-Z6-PR-DU-LC.250Issue Purchase Order 15 24-Jan-24 10-Feb-24 Issue Purchase Order

JAH-Z6-PR-DU-LC.255Material Delivery 90 17-Mar-24 07-Jul-24 Material Delivery

JAH-Z6-PR-DU-LC.260Staging time 30 11-Feb-24 16-Mar-24 Staging time

MEP 235 12-Feb-23 20-Nov-23 20-Nov-23, MEP


JAH-Z6-PRO-MEP.200 Request for Quotation 10 12-Feb-23 22-Feb-23 Request for Quotation

JAH-Z6-PRO-MEP.205 Issue Purchase Order 15 23-Feb-23 12-Mar-23 Issue Purchase Order

JAH-Z6-PRO-MEP.210 Material Delivery 180 17-Apr-23 20-Nov-23 Material Delivery

JAH-Z6-PRO-MEP.215 Staging Time 30 13-Mar-23 16-Apr-23 Staging Time

ARCHITECTURAL 115 13-Mar-23 31-Jul-23 31-Jul-23, ARCHITECTURAL


JAH-Z6-PRO-ARC.200 Request for Quotation 10 13-Mar-23 23-Mar-23 Request for Quotation

JAH-Z6-PRO-ARC.205 Issue Purchase Order 15 25-Mar-23 10-Apr-23 Issue Purchase Order

JAH-Z6-PRO-ARC.210 Material Delivery 60 20-May-23 31-Jul-23 Material Delivery

JAH-Z6-PRO-ARC.215 Staging Time 30 11-Apr-23 18-May-23 Staging Time

CONSTRUCTION 856 03-Jul-22 A 24-Aug-25 24-Aug-25, CONSTRUCTION


GENERAL SITE ARRANGEMENT 20 03-Jul-22 A 27-Nov-22 27-Nov-22, GENERAL SITE ARRANGEMENT
SITE PREPARATION 20 03-Jul-22 A 27-Nov-22 27-Nov-22, SITE PREPARATION
JAH-Z6-CON-GA-SP.175Site Clearing & Grubbing / Demolition of Obstacles 5 13-Jul-22 A 31-Oct-22 Site Clearing & Grubbing / Demolition of Obstacles

JAH-Z6-CON-GA-SP.180Disposal /Removal of Unnecessary Objects from Site 5 03-Jul-22 A 03-Nov-22 Disposal /Removal of Unnecessary Objects from Site

JAH-Z6-CON-GA-SP.185Relocation of Exisiting Utilities 20 05-Nov-22 27-Nov-22 Relocation of Exisiting Utilities

GEO-TECHNICAL INVESTIGATION 39 13-Jul-22 A 01-Oct-22 A 01-Oct-22 A, GEO-TECHNICAL INVESTIGATION

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
393 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ENG-GTI.465 Borehole Layout Preparation & Submission 7 13-Jul-22 A 17-Jul-22 A Borehole Layout Preparation & Submission

JAH-Z6-ENG-GTI.470 Borehole Layout Review & Approval 7 19-Jul-22 A 23-Jul-22 A Borehole Layout Review & Approval

JAH-Z6-ENG-GTI.475 Drilling Boreholes 7 24-Jul-22 A 02-Aug-22 A Drilling Boreholes

JAH-Z6-ENG-GTI.480 Issuance of Geo-Technical Investigation Report 7 16-Aug-22 A 01-Oct-22 A Issuance of Geo-Technical Investigation Report

EXCAVATION & DEWATERING 534 02-Aug-22 A 26-Mar-24 26-Mar-24, EXCAVATION & DEWATERING
JAH-Z6-CON-DE.182 Dewatering @Sta. 2+157 ~ 2+257 293 21-Nov-22 05-Nov-23 Dewatering @Sta. 2+157 ~ 2+257

JAH-Z6-CON-DE.187 Dewatering @Sta. 2+257 ~ 2+357 350 05-Oct-22 A 30-Dec-23 Dewatering @Sta. 2+257 ~ 2+357

JAH-Z6-CON-DE.192 Dewatering @Sta. 2+357 ~ 2+457 394 05-Oct-22 A 26-Mar-24 Dewatering @Sta. 2+357 ~ 2+457

JAH-Z6-CON-DE.197 Dewatering @Sta. 2+457 ~ 2+557 373 05-Oct-22 A 07-Mar-24 Dewatering @Sta. 2+457 ~ 2+557

JAH-Z6-CON-EX.180 Excavation @Sta. 2+157 ~ 2+257 30 21-Nov-22 25-Dec-22 Excavation @Sta. 2+157 ~ 2+257

JAH-Z6-CON-EX.185 Excavation @Sta. 2+257 ~ 2+357 30 02-Aug-22 A 31-Dec-22 Excavation @Sta. 2+257 ~ 2+357

JAH-Z6-CON-EX.190 Excavation @Sta. 2+357 ~ 2+457 25 04-Aug-22 A 04-Jan-23 Excavation @Sta. 2+357 ~ 2+457

JAH-Z6-CON-EX.195 Excavation @Sta. 2+457 ~ 2+557 25 22-Sep-22 A 14-Jan-23 Excavation @Sta. 2+457 ~ 2+557

SOIL IMPROVEMENT 32 26-Dec-22 31-Jan-23 31-Jan-23, SOIL IMPROVEMENT


JAH-CON-Z6-SIMP.101 Soil Improvement @Sta. 2+157 ~ 2+257 15 26-Dec-22 11-Jan-23 Soil Improvement @Sta. 2+157 ~ 2+257

JAH-CON-Z6-SIMP.106 Soil Improvement @Sta. 2+257 ~ 2+357 15 01-Jan-23 17-Jan-23 Soil Improvement @Sta. 2+257 ~ 2+357

JAH-CON-Z6-SIMP.111 Soil Improvement @Sta. 2+357 ~ 2+457 15 05-Jan-23 22-Jan-23 Soil Improvement @Sta. 2+357 ~ 2+457

JAH-CON-Z6-SIMP.116 Soil Improvement @Sta. 2+457 ~ 2+557 15 15-Jan-23 31-Jan-23 Soil Improvement @Sta. 2+457 ~ 2+557

STRUCTURAL WORKS 401 04-Feb-23 27-May-24 27-May-24, STRUCTURAL WORKS


STA. 2+157.088~ 2+182.088 188 04-Feb-23 17-Sep-23 17-Sep-23, STA. 2+157.088~ 2+182.088
BASE SLAB 28 04-Feb-23 07-Mar-23 07-Mar-23, BASE SLAB
JAH-Z6-ST-S1-BS.100 Lean Concrete for Base Slab 2 04-Feb-23 05-Feb-23 Lean Concrete for Base Slab

JAH-Z6-ST-S1-BS.105 Waterproofing for Lean Concrete 1 06-Feb-23 06-Feb-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S1-BS.110 Base Slab Rebar Installation 8 07-Feb-23 15-Feb-23 Base Slab Rebar Installation

JAH-Z6-ST-S1-BS.115 Base Slab Formwork Installation 7 16-Feb-23 23-Feb-23 Base Slab Formwork Installation

JAH-Z6-ST-S1-BS.120 Base Slab Concrete Casting 1 25-Feb-23 25-Feb-23 Base Slab Concrete Casting

JAH-Z6-ST-S1-BS.122 Curing work 7 26-Feb-23 05-Mar-23 Curing work

JAH-Z6-ST-S1-BS.125 Base Slab Formwork Removel 2 06-Mar-23 07-Mar-23 Base Slab Formwork Removel

COLUMNS 23 08-Mar-23 03-Apr-23 03-Apr-23, COLUMNS


JAH-Z6-ST-S1-CL.100 Column Rebar Installation 8 08-Mar-23 16-Mar-23 Column Rebar Installation

JAH-Z6-ST-S1-CL.105 Column Formwork Installation 7 18-Mar-23 25-Mar-23 Column Formwork Installation

JAH-Z6-ST-S1-CL.110 Column Concrete Casting 1 26-Mar-23 26-Mar-23 Column Concrete Casting

JAH-Z6-ST-S1-CL.115 Form Work Removal and Curing 7 27-Mar-23 03-Apr-23 Form Work Removal and Curing

TUNNEL WALLS 45 08-Mar-23 02-May-23 02-May-23, TUNNEL WALLS


JAH-Z6-ST-S1-TW.100 Tunnel Walls Rebar Installation 8 08-Mar-23 16-Mar-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S1-TW.102 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 18-Mar-23 26-Mar-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S1-TW.105 Tunnel Formwork Installation 7 27-Mar-23 03-Apr-23 Tunnel Formwork Installation

JAH-Z6-ST-S1-TW.110 Tunnel Walls Concrete Casting 1 04-Apr-23 04-Apr-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S1-TW.112 Curing work 7 05-Apr-23 12-Apr-23 Curing work

JAH-Z6-ST-S1-TW.120 Tunnel Walls Formwork Removel 2 13-Apr-23 15-Apr-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S1-TW.125 Tunnel Wall Waterproofing 12 16-Apr-23 02-May-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 38 16-Apr-23 01-Jun-23 01-Jun-23, MIDDLE SLAB FOR UTILITY CULVERT
JAH-Z6-ST-S1-MS.090 Middle Slab Scaffold and Formwork Installation 12 16-Apr-23 02-May-23 Middle Slab Scaffold and Formwork Installation

JAH-Z6-ST-S1-MS.100 Middle Slab Rebar Installation 9 03-May-23 13-May-23 Middle Slab Rebar Installation

JAH-Z6-ST-S1-MS.105 Middle Slab Vertical Formwork Installation 7 14-May-23 21-May-23 Middle Slab Vertical Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
394 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S1-MS.110 Middle Slab Concrete Casting 1 22-May-23 22-May-23 Middle Slab Concrete Casting

JAH-Z6-ST-S1-MS.115 Curing work 7 23-May-23 30-May-23 Curing work

JAH-Z6-ST-S1-MS.120 Middle Slab Formwork Removel 2 31-May-23 01-Jun-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 03-Jun-23 04-Jul-23 04-Jul-23, UTILITY CULVERT WALLS


JAH-Z6-ST-S1-UCW.100Utility Culvert Walls Rebar Installation 8 03-Jun-23 11-Jun-23 Utility Culvert Walls Rebar Installation

JAH-Z6-ST-S1-UCW.105Utility Culvert Walls Formwork Installation 7 12-Jun-23 19-Jun-23 Utility Culvert Walls Formwork Installation

JAH-Z6-ST-S1-UCW.110Utility Culvert Walls Concrete Casting 1 20-Jun-23 20-Jun-23 Utility Culvert Walls Concrete Casting

JAH-Z6-ST-S1-UCW.112Curing work 7 21-Jun-23 02-Jul-23 Curing work

JAH-Z6-ST-S1-UCW.115Utility Culvert Walls Walls Formwork Removel 2 03-Jul-23 04-Jul-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 40 05-Jul-23 20-Aug-23 20-Aug-23, TOP SLAB


JAH-Z6-ST-S1-TS.100 Top Slab Rebar Installation 8 05-Jul-23 13-Jul-23 Top Slab Rebar Installation

JAH-Z6-ST-S1-TS.105 Top Slab Formwork Installation 10 15-Jul-23 25-Jul-23 Top Slab Formwork Installation

JAH-Z6-ST-S1-TS.110 Top Slab Concrete Casting 1 26-Jul-23 26-Jul-23 Top Slab Concrete Casting

JAH-Z6-ST-S1-TS.112 Curing work 7 27-Jul-23 03-Aug-23 Curing work

JAH-Z6-ST-S1-TS.115 Top Slab Formwork Removel 2 05-Aug-23 06-Aug-23 Top Slab Formwork Removel

JAH-Z6-ST-S1-TS.120 Waterproofing for Top Slab 12 07-Aug-23 20-Aug-23 Waterproofing for Top Slab

FINISHING WORK 24 21-Aug-23 17-Sep-23 17-Sep-23, FINISHING WORK


JAH-Z6-ST-S1-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 21-Aug-23 28-Aug-23 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S1-FW.105 Plain Concrete Casting 1 29-Aug-23 29-Aug-23 Plain Concrete Casting

JAH-Z6-ST-S1-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 30-Aug-23 30-Aug-23 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S1-FW.112 Curing work 7 31-Aug-23 07-Sep-23 Curing work

JAH-Z6-ST-S1-FW.115 Concrete Protective coating 8 09-Sep-23 17-Sep-23 Concrete Protective coating

STA. 2+182.088~ 2+198.227 194 27-Mar-23 15-Nov-23 15-Nov-23, STA. 2+182.088~ 2+198.227
BASE SLAB 27 27-Mar-23 30-Apr-23 30-Apr-23, BASE SLAB
JAH-Z6-ST-S2-BS.100 Lean Concrete for Base Slab 1 27-Mar-23 27-Mar-23 Lean Concrete for Base Slab

JAH-Z6-ST-S2-BS.105 Waterproofing for Lean Concrete 1 28-Mar-23 28-Mar-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S2-BS.110 Base Slab Rebar Installation 8 29-Mar-23 06-Apr-23 Base Slab Rebar Installation

JAH-Z6-ST-S2-BS.115 Base Slab Formwork Installation 7 08-Apr-23 15-Apr-23 Base Slab Formwork Installation

JAH-Z6-ST-S2-BS.120 Base Slab Concrete Casting 1 16-Apr-23 16-Apr-23 Base Slab Concrete Casting

JAH-Z6-ST-S2-BS.122 Curing work 7 17-Apr-23 27-Apr-23 Curing work

JAH-Z6-ST-S2-BS.125 Base Slab Formwork Removel 2 29-Apr-23 30-Apr-23 Base Slab Formwork Removel

COLUMNS 23 01-May-23 27-May-23 27-May-23, COLUMNS


JAH-Z6-ST-S2-CL.100 Column Rebar Installation 8 01-May-23 09-May-23 Column Rebar Installation

JAH-Z6-ST-S2-CL.105 Column Formwork Installation 7 10-May-23 17-May-23 Column Formwork Installation

JAH-Z6-ST-S2-CL.110 Column Concrete Casting 1 18-May-23 18-May-23 Column Concrete Casting

JAH-Z6-ST-S2-CL.115 Form Work Removal and Curing 7 20-May-23 27-May-23 Form Work Removal and Curing

TUNNEL WALLS 45 10-May-23 04-Jul-23 04-Jul-23, TUNNEL WALLS


JAH-Z6-ST-S2-TW.100 Tunnel Walls Rebar Installation 8 10-May-23 18-May-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S2-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 20-May-23 28-May-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S2-TW.105 Tunnel Formwork Installation 7 29-May-23 05-Jun-23 Tunnel Formwork Installation

JAH-Z6-ST-S2-TW.110 Tunnel Walls Concrete Casting 1 06-Jun-23 06-Jun-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S2-TW.112 Curing work 7 07-Jun-23 14-Jun-23 Curing work

JAH-Z6-ST-S2-TW.120 Tunnel Walls Formwork Removel 2 15-Jun-23 17-Jun-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S2-TW.125 Tunnel Wall Waterproofing 12 18-Jun-23 04-Jul-23 Tunnel Wall Waterproofing

MIDDLE SLAB FOR UTILITY CULVERT 37 18-Jun-23 02-Aug-23 02-Aug-23, MIDDLE SLAB FOR UTILITY CULVERT

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
395 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S2-MS100 Middle Slab Scaffold and Formwork Installation 12 18-Jun-23 04-Jul-23 Middle Slab Scaffold and Formwork Installation

JAH-Z6-ST-S2-MS103 Middle Slab Vertical Formwork Installation 7 15-Jul-23 22-Jul-23 Middle Slab Vertical Formwork Installation

JAH-Z6-ST-S2-MS105 Middle Slab Rebar Installation 8 05-Jul-23 13-Jul-23 Middle Slab Rebar Installation

JAH-Z6-ST-S2-MS110 Middle Slab Concrete Casting 1 23-Jul-23 23-Jul-23 Middle Slab Concrete Casting

JAH-Z6-ST-S2-MS112 Curing work 7 24-Jul-23 31-Jul-23 Curing work

JAH-Z6-ST-S2-MS120 Middle Slab Formwork Removel 2 01-Aug-23 02-Aug-23 Middle Slab Formwork Removel

UTILITY CULVERT WALLS 25 03-Aug-23 31-Aug-23 31-Aug-23, UTILITY CULVERT WALLS


JAH-Z6-ST-S2-UCW.100Utility Culvert Walls Rebar Installation 8 03-Aug-23 12-Aug-23 Utility Culvert Walls Rebar Installation

JAH-Z6-ST-S2-UCW.105Utility Culvert Walls Formwork Installation 7 13-Aug-23 20-Aug-23 Utility Culvert Walls Formwork Installation

JAH-Z6-ST-S2-UCW.110Utility Culvert Walls Concrete Casting 1 21-Aug-23 21-Aug-23 Utility Culvert Walls Concrete Casting

JAH-Z6-ST-S2-UCW.112Curing work 7 22-Aug-23 29-Aug-23 Curing work

JAH-Z6-ST-S2-UCW.115Utility Culvert Walls Walls Formwork Removel 2 30-Aug-23 31-Aug-23 Utility Culvert Walls Walls Formwork Removel

TOP SLAB 40 02-Sep-23 18-Oct-23 18-Oct-23, TOP SLAB


JAH-Z6-ST-S2-TS.100 Top Slab Rebar Installation 8 02-Sep-23 10-Sep-23 Top Slab Rebar Installation

JAH-Z6-ST-S2-TS.105 Top Slab Formwork Installation 10 11-Sep-23 21-Sep-23 Top Slab Formwork Installation

JAH-Z6-ST-S2-TS.110 Top Slab Concrete Casting 1 24-Sep-23 24-Sep-23 Top Slab Concrete Casting

JAH-Z6-ST-S2-TS.112 Curing work 7 25-Sep-23 02-Oct-23 Curing work

JAH-Z6-ST-S2-TS.115 Top Slab Formwork Removel 2 03-Oct-23 04-Oct-23 Top Slab Formwork Removel

JAH-Z6-ST-S2-TS.120 Waterproofing for Top Slab 12 05-Oct-23 18-Oct-23 Waterproofing for Top Slab

FINISHING WORK 24 19-Oct-23 15-Nov-23 15-Nov-23, FINISHING WORK


JAH-Z6-ST-S2-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 19-Oct-23 26-Oct-23 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S2-FW.105 Plain Concrete Casting 1 28-Oct-23 28-Oct-23 Plain Concrete Casting

JAH-Z6-ST-S2-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 29-Oct-23 29-Oct-23 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S2-FW.112 Curing work 7 30-Oct-23 06-Nov-23 Curing work

JAH-Z6-ST-S2-FW.115 Concrete Protective coating 8 07-Nov-23 15-Nov-23 Concrete Protective coating

STA. 2+198.227~ 2+218.227 138 18-Jun-23 29-Nov-23 29-Nov-23, STA. 2+198.227~ 2+218.227
BASE SLAB 27 18-Jun-23 22-Jul-23 22-Jul-23, BASE SLAB
JAH-Z6-ST-S3-BS.100 Lean Concrete for Base Slab 1 18-Jun-23 18-Jun-23 Lean Concrete for Base Slab

JAH-Z6-ST-S3-BS.105 Waterproofing for Lean Concrete 1 19-Jun-23 19-Jun-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S3-BS.110 Base Slab Rebar Installation 8 20-Jun-23 02-Jul-23 Base Slab Rebar Installation

JAH-Z6-ST-S3-BS.115 Base Slab Formwork Installation 7 03-Jul-23 10-Jul-23 Base Slab Formwork Installation

JAH-Z6-ST-S3-BS.120 Base Slab Concrete Casting 1 11-Jul-23 11-Jul-23 Base Slab Concrete Casting

JAH-Z6-ST-S3-BS.122 Curing work 7 12-Jul-23 19-Jul-23 Curing work

JAH-Z6-ST-S3-BS.125 Base Slab Formwork Removel 2 20-Jul-23 22-Jul-23 Base Slab Formwork Removel

COLUMNS 23 23-Jul-23 17-Aug-23 17-Aug-23, COLUMNS


JAH-Z6-ST-S-CL.100 Column Rebar Installation 8 23-Jul-23 31-Jul-23 Column Rebar Installation

JAH-Z6-ST-S-CL.105 Column Formwork Installation 7 01-Aug-23 08-Aug-23 Column Formwork Installation

JAH-Z6-ST-S-CL.110 Column Concrete Casting 1 09-Aug-23 09-Aug-23 Column Concrete Casting

JAH-Z6-ST-S-CL.115 Form Work Removal and Curing 7 10-Aug-23 17-Aug-23 Form Work Removal and Curing

TUNNEL WALLS 45 01-Aug-23 21-Sep-23 21-Sep-23, TUNNEL WALLS


JAH-Z6-ST-S3-TW.100 Tunnel Walls Rebar Installation 8 01-Aug-23 09-Aug-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S3-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 10-Aug-23 19-Aug-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S3-TW.105 Tunnel Formwork Installation 7 20-Aug-23 27-Aug-23 Tunnel Formwork Installation

JAH-Z6-ST-S3-TW.110 Tunnel Walls Concrete Casting 1 28-Aug-23 28-Aug-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S3-TW.112 Curing work 7 29-Aug-23 05-Sep-23 Curing work

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
396 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S3-TW.120 Tunnel Walls Formwork Removel 2 06-Sep-23 07-Sep-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S3-TW.125 Tunnel Wall Waterproofing 12 09-Sep-23 21-Sep-23 Tunnel Wall Waterproofing

TOP SLAB 40 09-Sep-23 25-Oct-23 25-Oct-23, TOP SLAB


JAH-Z6-ST-S3-TS.100 Top Slab Rebar Installation 8 09-Sep-23 17-Sep-23 Top Slab Rebar Installation

JAH-Z6-ST-S3-TS.105 Top Slab Formwork Installation 10 18-Sep-23 30-Sep-23 Top Slab Formwork Installation

JAH-Z6-ST-S3-TS.110 Top Slab Concrete Casting 1 01-Oct-23 01-Oct-23 Top Slab Concrete Casting

JAH-Z6-ST-S3-TS.112 Curing work 7 02-Oct-23 09-Oct-23 Curing work

JAH-Z6-ST-S3-TS.115 Top Slab Formwork Removel 2 10-Oct-23 11-Oct-23 Top Slab Formwork Removel

JAH-Z6-ST-S3-TS.120 Waterproofing for Top Slab 12 12-Oct-23 25-Oct-23 Waterproofing for Top Slab

FINISHING WORK 30 26-Oct-23 29-Nov-23 29-Nov-23, FINISHING WORK


JAH-Z6-ST-S3-FW.120 Above Top Slab Formwork Installation for Plain Concrete 7 26-Oct-23 02-Nov-23 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S3-FW.125 Plain Concrete Casting 1 04-Nov-23 04-Nov-23 Plain Concrete Casting

JAH-Z6-ST-S3-FW.130 Mass Concrete Casting for Base Slab Top Layer 1 05-Nov-23 05-Nov-23 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S3-FW.132 Curing work 7 06-Nov-23 13-Nov-23 Curing work

JAH-Z6-ST-S3-FW.135 Concrete Protective coating 12 16-Nov-23 29-Nov-23 Concrete Protective coating

STA.2+218.227 ~ 2+238.227 136 11-Jul-23 17-Dec-23 17-Dec-23, STA.2+218.227 ~ 2+238.227


BASE SLAB 27 11-Jul-23 10-Aug-23 10-Aug-23, BASE SLAB
JAH-Z6-ST-S4-BS.100 Lean Concrete for Base Slab 1 11-Jul-23 11-Jul-23 Lean Concrete for Base Slab

JAH-Z6-ST-S4-BS.105 Waterproofing for Lean Concrete 1 12-Jul-23 12-Jul-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S4-BS.110 Base Slab Rebar Installation 8 13-Jul-23 22-Jul-23 Base Slab Rebar Installation

JAH-Z6-ST-S4-BS.115 Base Slab Formwork Installation 7 23-Jul-23 30-Jul-23 Base Slab Formwork Installation

JAH-Z6-ST-S4-BS.120 Base Slab Concrete Casting 1 31-Jul-23 31-Jul-23 Base Slab Concrete Casting

JAH-Z6-ST-S4-BS.122 Curing work 7 01-Aug-23 08-Aug-23 Curing work

JAH-Z6-ST-S4-BS.125 Base Slab Formwork Removel 2 09-Aug-23 10-Aug-23 Base Slab Formwork Removel

COLUMNS 23 12-Aug-23 06-Sep-23 06-Sep-23, COLUMNS


JAH-Z6-ST-S4-CL.100 Column Rebar Installation 8 12-Aug-23 20-Aug-23 Column Rebar Installation

JAH-Z6-ST-S4-CL.105 Column Formwork Installation 7 21-Aug-23 28-Aug-23 Column Formwork Installation

JAH-Z6-ST-S4-CL.110 Column Concrete Casting 1 29-Aug-23 29-Aug-23 Column Concrete Casting

JAH-Z6-ST-S4-CL.115 Form Work Removal and Curing 7 30-Aug-23 06-Sep-23 Form Work Removal and Curing

TUNNEL WALLS 45 21-Aug-23 12-Oct-23 12-Oct-23, TUNNEL WALLS


JAH-Z6-ST-S4-TW.100 Tunnel Walls Rebar Installation 8 21-Aug-23 29-Aug-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S4-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 30-Aug-23 07-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S4-TW.105 Tunnel Formwork Installation 7 09-Sep-23 16-Sep-23 Tunnel Formwork Installation

JAH-Z6-ST-S4-TW.110 Tunnel Walls Concrete Casting 1 17-Sep-23 17-Sep-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S4-TW.112 Curing work 7 18-Sep-23 26-Sep-23 Curing work

JAH-Z6-ST-S4-TW.120 Tunnel Walls Formwork Removel 2 27-Sep-23 28-Sep-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S4-TW.125 Tunnel Wall Waterproofing 12 30-Sep-23 12-Oct-23 Tunnel Wall Waterproofing

TOP SLAB 40 30-Sep-23 14-Nov-23 14-Nov-23, TOP SLAB


JAH-Z6-ST-S4-TS.100 Top Slab Rebar Installation 8 30-Sep-23 08-Oct-23 Top Slab Rebar Installation

JAH-Z6-ST-S4-TS.105 Top Slab Formwork Installation 10 09-Oct-23 19-Oct-23 Top Slab Formwork Installation

JAH-Z6-ST-S4-TS.110 Top Slab Concrete Casting 1 21-Oct-23 21-Oct-23 Top Slab Concrete Casting

JAH-Z6-ST-S4-TS.112 Curing work 7 22-Oct-23 29-Oct-23 Curing work

JAH-Z6-ST-S4-TS.115 Top Slab Formwork Removel 2 30-Oct-23 31-Oct-23 Top Slab Formwork Removel

JAH-Z6-ST-S4-TS.120 Waterproofing for Top Slab 12 01-Nov-23 14-Nov-23 Waterproofing for Top Slab

FINISHING WORK 28 15-Nov-23 17-Dec-23 17-Dec-23, FINISHING WORK

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
397 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S4-FW.120 Above Top Slab Formwork Installation for Plain Concrete 7 15-Nov-23 22-Nov-23 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S4-FW.125 Plain Concrete Casting 1 23-Nov-23 23-Nov-23 Plain Concrete Casting

JAH-Z6-ST-S4-FW.130 Mass Concrete Casting for Base Slab Top Layer 1 25-Nov-23 25-Nov-23 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S4-FW.132 Curing work 7 26-Nov-23 03-Dec-23 Curing work

JAH-Z6-ST-S4-FW.135 Concrete Protective coating 12 04-Dec-23 17-Dec-23 Concrete Protective coating

STA. 2+238.227~ 2+258.227 136 31-Jul-23 06-Jan-24 06-Jan-24, STA. 2+238.227~ 2+258.227
BASE SLAB 27 31-Jul-23 30-Aug-23 30-Aug-23, BASE SLAB
JAH-Z6-ST-S5-BS.100 Lean Concrete for Base Slab 1 31-Jul-23 31-Jul-23 Lean Concrete for Base Slab

JAH-Z6-ST-S5-BS.105 Waterproofing for Lean Concrete 1 01-Aug-23 01-Aug-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S5-BS.110 Base Slab Rebar Installation 8 02-Aug-23 10-Aug-23 Base Slab Rebar Installation

JAH-Z6-ST-S5-BS.115 Base Slab Formwork Installation 7 12-Aug-23 19-Aug-23 Base Slab Formwork Installation

JAH-Z6-ST-S5-BS.120 Base Slab Concrete Casting 1 20-Aug-23 20-Aug-23 Base Slab Concrete Casting

JAH-Z6-ST-S5-BS.122 Curing work 7 21-Aug-23 28-Aug-23 Curing work

JAH-Z6-ST-S5-BS.125 Base Slab Formwork Removel 2 29-Aug-23 30-Aug-23 Base Slab Formwork Removel

COLUMNS 23 31-Aug-23 27-Sep-23 27-Sep-23, COLUMNS


JAH-Z6-ST-S5-CL.100 Column Rebar Installation 8 31-Aug-23 09-Sep-23 Column Rebar Installation

JAH-Z6-ST-S5-CL.105 Column Formwork Installation 7 10-Sep-23 17-Sep-23 Column Formwork Installation

JAH-Z6-ST-S5-CL.110 Column Concrete Casting 1 18-Sep-23 18-Sep-23 Column Concrete Casting

JAH-Z6-ST-S5-CL.115 Form Work Removal and Curing 7 19-Sep-23 27-Sep-23 Form Work Removal and Curing

TUNNEL WALLS 45 10-Sep-23 01-Nov-23 01-Nov-23, TUNNEL WALLS


JAH-Z6-ST-S5-TW.100 Tunnel Walls Rebar Installation 8 10-Sep-23 18-Sep-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S5-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 19-Sep-23 28-Sep-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S5-TW.105 Tunnel Formwork Installation 7 30-Sep-23 07-Oct-23 Tunnel Formwork Installation

JAH-Z6-ST-S5-TW.110 Tunnel Walls Concrete Casting 1 08-Oct-23 08-Oct-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S5-TW.112 Curing work 7 09-Oct-23 16-Oct-23 Curing work

JAH-Z6-ST-S5-TW.120 Tunnel Walls Formwork Removel 2 17-Oct-23 18-Oct-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S5-TW.125 Tunnel Wall Waterproofing 12 19-Oct-23 01-Nov-23 Tunnel Wall Waterproofing

TOP SLAB 40 19-Oct-23 04-Dec-23 04-Dec-23, TOP SLAB


JAH-Z6-ST-S5-TS.100 Top Slab Rebar Installation 8 19-Oct-23 28-Oct-23 Top Slab Rebar Installation

JAH-Z6-ST-S5-TS.105 Top Slab Formwork Installation 10 29-Oct-23 08-Nov-23 Top Slab Formwork Installation

JAH-Z6-ST-S5-TS.110 Top Slab Concrete Casting 1 09-Nov-23 09-Nov-23 Top Slab Concrete Casting

JAH-Z6-ST-S5-TS.112 Curing work 7 11-Nov-23 18-Nov-23 Curing work

JAH-Z6-ST-S5-TS.115 Top Slab Formwork Removel 2 19-Nov-23 20-Nov-23 Top Slab Formwork Removel

JAH-Z6-ST-S5-TS.120 Waterproofing for Top Slab 12 21-Nov-23 04-Dec-23 Waterproofing for Top Slab

FINISHING WORK 28 05-Dec-23 06-Jan-24 06-Jan-24, FINISHING WORK


JAH-Z6-ST-S5-FW.120 Above Top Slab Formwork Installation for Plain Concrete 7 05-Dec-23 12-Dec-23 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S5-FW.125 Plain Concrete Casting 1 13-Dec-23 13-Dec-23 Plain Concrete Casting

JAH-Z6-ST-S5-FW.130 Mass Concrete Casting for Base Slab Top Layer 1 14-Dec-23 14-Dec-23 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S5-FW.132 Curing work 7 16-Dec-23 23-Dec-23 Curing work

JAH-Z6-ST-S5-FW.135 Concrete Protective coating 12 24-Dec-23 06-Jan-24 Concrete Protective coating

STA. 2+258.227~ 2+278.227 136 29-Aug-23 04-Feb-24 04-Feb-24, STA. 2+258.227~ 2+278.227
BASE SLAB 27 29-Aug-23 30-Sep-23 30-Sep-23, BASE SLAB
JAH-Z6-ST-S6-BS.100 Lean Concrete for Base Slab 1 29-Aug-23 29-Aug-23 Lean Concrete for Base Slab

JAH-Z6-ST-S6-BS.105 Waterproofing for Lean Concrete 1 30-Aug-23 30-Aug-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S6-BS.110 Base Slab Rebar Installation 8 31-Aug-23 09-Sep-23 Base Slab Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
398 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S6-BS.115 Base Slab Formwork Installation 7 10-Sep-23 17-Sep-23 Base Slab Formwork Installation

JAH-Z6-ST-S6-BS.120 Base Slab Concrete Casting 1 18-Sep-23 18-Sep-23 Base Slab Concrete Casting

JAH-Z6-ST-S6-BS.122 Curing work 7 19-Sep-23 27-Sep-23 Curing work

JAH-Z6-ST-S6-BS.125 Base Slab Formwork Removel 2 28-Sep-23 30-Sep-23 Base Slab Formwork Removel

COLUMNS 23 01-Oct-23 26-Oct-23 26-Oct-23, COLUMNS


JAH-Z6-ST-S6-CL.100 Column Rebar Installation 8 01-Oct-23 09-Oct-23 Column Rebar Installation

JAH-Z6-ST-S6-CL.105 Column Formwork Installation 7 10-Oct-23 17-Oct-23 Column Formwork Installation

JAH-Z6-ST-S6-CL.110 Column Concrete Casting 1 18-Oct-23 18-Oct-23 Column Concrete Casting

JAH-Z6-ST-S6-CL.115 Form Work Removal and Curing 7 19-Oct-23 26-Oct-23 Form Work Removal and Curing

TUNNEL WALLS 45 10-Oct-23 30-Nov-23 30-Nov-23, TUNNEL WALLS


JAH-Z6-ST-S6-TW.100 Tunnel Walls Rebar Installation 8 10-Oct-23 18-Oct-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S6-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 19-Oct-23 28-Oct-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S6-TW.105 Tunnel Formwork Installation 7 29-Oct-23 05-Nov-23 Tunnel Formwork Installation

JAH-Z6-ST-S6-TW.110 Tunnel Walls Concrete Casting 1 06-Nov-23 06-Nov-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S6-TW.112 Curing work 7 07-Nov-23 14-Nov-23 Curing work

JAH-Z6-ST-S6-TW.120 Tunnel Walls Formwork Removel 2 15-Nov-23 16-Nov-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S6-TW.125 Tunnel Wall Waterproofing 12 18-Nov-23 30-Nov-23 Tunnel Wall Waterproofing

TOP SLAB 40 18-Nov-23 02-Jan-24 02-Jan-24, TOP SLAB


JAH-Z6-ST-S6-TS.100 Top Slab Rebar Installation 8 18-Nov-23 26-Nov-23 Top Slab Rebar Installation

JAH-Z6-ST-S6-TS.105 Top Slab Formwork Installation 10 27-Nov-23 07-Dec-23 Top Slab Formwork Installation

JAH-Z6-ST-S6-TS.110 Top Slab Concrete Casting 1 09-Dec-23 09-Dec-23 Top Slab Concrete Casting

JAH-Z6-ST-S6-TS.112 Curing work 7 10-Dec-23 17-Dec-23 Curing work

JAH-Z6-ST-S6-TS.115 Top Slab Formwork Removel 2 18-Dec-23 19-Dec-23 Top Slab Formwork Removel

JAH-Z6-ST-S6-TS.120 Waterproofing for Top Slab 12 20-Dec-23 02-Jan-24 Waterproofing for Top Slab

FINISHING WORK 28 03-Jan-24 04-Feb-24 04-Feb-24, FINISHING WORK


JAH-Z6-ST-S6-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 03-Jan-24 10-Jan-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S6-FW.105 Plain Concrete Casting 1 11-Jan-24 11-Jan-24 Plain Concrete Casting

JAH-Z6-ST-S6-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 13-Jan-24 13-Jan-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S6-FW.112 Curing work 7 14-Jan-24 21-Jan-24 Curing work

JAH-Z6-ST-S6-FW.115 Concrete Protective coating 12 22-Jan-24 04-Feb-24 Concrete Protective coating

STA.2+278.227 ~ 2+298.227 138 10-Sep-23 18-Feb-24 18-Feb-24, STA.2+278.227 ~ 2+298.227


BASE SLAB 27 10-Sep-23 11-Oct-23 11-Oct-23, BASE SLAB
JAH-Z6-ST-S7-BS.100 Lean Concrete for Base Slab 1 10-Sep-23 10-Sep-23 Lean Concrete for Base Slab

JAH-Z6-ST-S7-BS.105 Waterproofing for Lean Concrete 1 11-Sep-23 11-Sep-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S7-BS.110 Base Slab Rebar Installation 8 12-Sep-23 20-Sep-23 Base Slab Rebar Installation

JAH-Z6-ST-S7-BS.115 Base Slab Formwork Installation 7 21-Sep-23 30-Sep-23 Base Slab Formwork Installation

JAH-Z6-ST-S7-BS.120 Base Slab Concrete Casting 1 01-Oct-23 01-Oct-23 Base Slab Concrete Casting

JAH-Z6-ST-S7-BS.122 Curing work 7 02-Oct-23 09-Oct-23 Curing work

JAH-Z6-ST-S7-BS.125 Base Slab Formwork Removel 2 10-Oct-23 11-Oct-23 Base Slab Formwork Removel

COLUMNS 23 12-Oct-23 07-Nov-23 07-Nov-23, COLUMNS


JAH-Z6-ST-S7-CL.100 Column Rebar Installation 8 12-Oct-23 21-Oct-23 Column Rebar Installation

JAH-Z6-ST-S7-CL.105 Column Formwork Installation 7 22-Oct-23 29-Oct-23 Column Formwork Installation

JAH-Z6-ST-S7-CL.110 Column Concrete Casting 1 30-Oct-23 30-Oct-23 Column Concrete Casting

JAH-Z6-ST-S7-CL.115 Form Work Removal and Curing 7 31-Oct-23 07-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 45 22-Oct-23 12-Dec-23 12-Dec-23, TUNNEL WALLS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
399 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S7-TW.100 Tunnel Walls Rebar Installation 8 22-Oct-23 30-Oct-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S7-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 31-Oct-23 08-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S7-TW.105 Tunnel Formwork Installation 7 09-Nov-23 16-Nov-23 Tunnel Formwork Installation

JAH-Z6-ST-S7-TW.110 Tunnel Walls Concrete Casting 1 18-Nov-23 18-Nov-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S7-TW.112 Curing work 7 19-Nov-23 26-Nov-23 Curing work

JAH-Z6-ST-S7-TW.120 Tunnel Walls Formwork Removel 2 27-Nov-23 28-Nov-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S7-TW.125 Tunnel Wall Waterproofing 12 29-Nov-23 12-Dec-23 Tunnel Wall Waterproofing

TOP SLAB 40 29-Nov-23 14-Jan-24 14-Jan-24, TOP SLAB


JAH-Z6-ST-S7-TS.100 Top Slab Rebar Installation 8 29-Nov-23 07-Dec-23 Top Slab Rebar Installation

JAH-Z6-ST-S7-TS.105 Top Slab Formwork Installation 10 09-Dec-23 19-Dec-23 Top Slab Formwork Installation

JAH-Z6-ST-S7-TS.110 Top Slab Concrete Casting 1 20-Dec-23 20-Dec-23 Top Slab Concrete Casting

JAH-Z6-ST-S7-TS.112 Curing work 7 21-Dec-23 28-Dec-23 Curing work

JAH-Z6-ST-S7-TS.115 Top Slab Formwork Removel 2 30-Dec-23 31-Dec-23 Top Slab Formwork Removel

JAH-Z6-ST-S7-TS.120 Waterproofing for Top Slab 12 01-Jan-24 14-Jan-24 Waterproofing for Top Slab

FINISHING WORK 30 15-Jan-24 18-Feb-24 18-Feb-24, FINISHING WORK


JAH-Z6-ST-S7-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 15-Jan-24 22-Jan-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S7-FW.105 Plain Concrete Casting 1 23-Jan-24 23-Jan-24 Plain Concrete Casting

JAH-Z6-ST-S7-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 24-Jan-24 24-Jan-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S7-FW.112 Curing work 7 25-Jan-24 01-Feb-24 Curing work

JAH-Z6-ST-S7-FW.115 Concrete Protective coating 12 05-Feb-24 18-Feb-24 Concrete Protective coating

STA. 2+298.227~ 2+318.227 133 01-Oct-23 03-Mar-24 03-Mar-24, STA. 2+298.227~ 2+318.227
BASE SLAB 27 01-Oct-23 31-Oct-23 31-Oct-23, BASE SLAB
JAH-Z6-ST-S8-BS.100 Lean Concrete for Base Slab 1 01-Oct-23 01-Oct-23 Lean Concrete for Base Slab

JAH-Z6-ST-S8-BS.105 Waterproofing for Lean Concrete 1 02-Oct-23 02-Oct-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S8-BS.110 Base Slab Rebar Installation 8 03-Oct-23 11-Oct-23 Base Slab Rebar Installation

JAH-Z6-ST-S8-BS.115 Base Slab Formwork Installation 7 12-Oct-23 19-Oct-23 Base Slab Formwork Installation

JAH-Z6-ST-S8-BS.120 Base Slab Concrete Casting 1 21-Oct-23 21-Oct-23 Base Slab Concrete Casting

JAH-Z6-ST-S8-BS.122 Curing work 7 22-Oct-23 29-Oct-23 Curing work

JAH-Z6-ST-S8-BS.125 Base Slab Formwork Removel 2 30-Oct-23 31-Oct-23 Base Slab Formwork Removel

COLUMNS 23 01-Nov-23 27-Nov-23 27-Nov-23, COLUMNS


JAH-Z6-ST-S8-CL.100 Column Rebar Installation 8 01-Nov-23 09-Nov-23 Column Rebar Installation

JAH-Z6-ST-S8-CL.105 Column Formwork Installation 7 11-Nov-23 18-Nov-23 Column Formwork Installation

JAH-Z6-ST-S8-CL.110 Column Concrete Casting 1 19-Nov-23 19-Nov-23 Column Concrete Casting

JAH-Z6-ST-S8-CL.115 Form Work Removal and Curing 7 20-Nov-23 27-Nov-23 Form Work Removal and Curing

TUNNEL WALLS 45 01-Nov-23 23-Dec-23 23-Dec-23, TUNNEL WALLS


JAH-Z6-ST-S8-TW.100 Tunnel Walls Rebar Installation 8 01-Nov-23 09-Nov-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S8-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 11-Nov-23 19-Nov-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S8-TW.105 Tunnel Formwork Installation 7 20-Nov-23 27-Nov-23 Tunnel Formwork Installation

JAH-Z6-ST-S8-TW.110 Tunnel Walls Concrete Casting 1 28-Nov-23 28-Nov-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S8-TW.112 Curing work 7 29-Nov-23 06-Dec-23 Curing work

JAH-Z6-ST-S8-TW.120 Tunnel Walls Formwork Removel 2 07-Dec-23 09-Dec-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S8-TW.125 Tunnel Wall Waterproofing 12 10-Dec-23 23-Dec-23 Tunnel Wall Waterproofing

TOP SLAB 40 10-Dec-23 24-Jan-24 24-Jan-24, TOP SLAB


JAH-Z6-ST-S8-TS.100 Top Slab Rebar Installation 8 10-Dec-23 18-Dec-23 Top Slab Rebar Installation

JAH-Z6-ST-S8-TS.105 Top Slab Formwork Installation 10 19-Dec-23 30-Dec-23 Top Slab Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
400 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S8-TS.110 Top Slab Concrete Casting 1 31-Dec-23 31-Dec-23 Top Slab Concrete Casting

JAH-Z6-ST-S8-TS.112 Curing work 7 01-Jan-24 08-Jan-24 Curing work

JAH-Z6-ST-S8-TS.115 Top Slab Formwork Removel 2 09-Jan-24 10-Jan-24 Top Slab Formwork Removel

JAH-Z6-ST-S8-TS.120 Waterproofing for Top Slab 12 11-Jan-24 24-Jan-24 Waterproofing for Top Slab

FINISHING WORK 33 25-Jan-24 03-Mar-24 03-Mar-24, FINISHING WORK


JAH-Z6-ST-S8-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 25-Jan-24 01-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S8-FW.105 Plain Concrete Casting 1 03-Feb-24 03-Feb-24 Plain Concrete Casting

JAH-Z6-ST-S8-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 04-Feb-24 04-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S8-FW.112 Curing work 7 05-Feb-24 12-Feb-24 Curing work

JAH-Z6-ST-S8-FW.115 Concrete Protective coating 12 19-Feb-24 03-Mar-24 Concrete Protective coating

STA. 2+318.227~ 2+338.227 128 21-Oct-23 17-Mar-24 17-Mar-24, STA. 2+318.227~ 2+338.227
BASE SLAB 27 21-Oct-23 20-Nov-23 20-Nov-23, BASE SLAB
JAH-Z6-ST-S9-BS.100 Lean Concrete for Base Slab 1 21-Oct-23 21-Oct-23 Lean Concrete for Base Slab

JAH-Z6-ST-S9-BS.105 Waterproofing for Lean Concrete 1 22-Oct-23 22-Oct-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S9-BS.110 Base Slab Rebar Installation 8 23-Oct-23 31-Oct-23 Base Slab Rebar Installation

JAH-Z6-ST-S9-BS.115 Base Slab Formwork Installation 7 01-Nov-23 08-Nov-23 Base Slab Formwork Installation

JAH-Z6-ST-S9-BS.120 Base Slab Concrete Casting 1 09-Nov-23 09-Nov-23 Base Slab Concrete Casting

JAH-Z6-ST-S9-BS.122 Curing work 7 11-Nov-23 18-Nov-23 Curing work

JAH-Z6-ST-S9-BS.125 Base Slab Formwork Removel 2 19-Nov-23 20-Nov-23 Base Slab Formwork Removel

COLUMNS 23 21-Nov-23 17-Dec-23 17-Dec-23, COLUMNS


JAH-Z6-ST-S9-CL.100 Column Rebar Installation 8 21-Nov-23 29-Nov-23 Column Rebar Installation

JAH-Z6-ST-S9-CL.105 Column Formwork Installation 7 30-Nov-23 07-Dec-23 Column Formwork Installation

JAH-Z6-ST-S9-CL.110 Column Concrete Casting 1 09-Dec-23 09-Dec-23 Column Concrete Casting

JAH-Z6-ST-S9-CL.115 Form Work Removal and Curing 7 10-Dec-23 17-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 45 21-Nov-23 11-Jan-24 11-Jan-24, TUNNEL WALLS


JAH-Z6-ST-S9-TW.100 Tunnel Walls Rebar Installation 8 21-Nov-23 29-Nov-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S9-TW.103 PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 30-Nov-23 09-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S9-TW.105 Tunnel Formwork Installation 7 10-Dec-23 17-Dec-23 Tunnel Formwork Installation

JAH-Z6-ST-S9-TW.110 Tunnel Walls Concrete Casting 1 18-Dec-23 18-Dec-23 Tunnel Walls Concrete Casting

JAH-Z6-ST-S9-TW.112 Curing work 7 19-Dec-23 26-Dec-23 Curing work

JAH-Z6-ST-S9-TW.120 Tunnel Walls Formwork Removel 2 27-Dec-23 28-Dec-23 Tunnel Walls Formwork Removel

JAH-Z6-ST-S9-TW.125 Tunnel Wall Waterproofing 12 30-Dec-23 11-Jan-24 Tunnel Wall Waterproofing

TOP SLAB 40 30-Dec-23 13-Feb-24 13-Feb-24, TOP SLAB


JAH-Z6-ST-S9-TS.100 Top Slab Rebar Installation 8 30-Dec-23 07-Jan-24 Top Slab Rebar Installation

JAH-Z6-ST-S9-TS.105 Top Slab Formwork Installation 10 08-Jan-24 18-Jan-24 Top Slab Formwork Installation

JAH-Z6-ST-S9-TS.110 Top Slab Concrete Casting 1 20-Jan-24 20-Jan-24 Top Slab Concrete Casting

JAH-Z6-ST-S9-TS.112 Curing work 7 21-Jan-24 28-Jan-24 Curing work

JAH-Z6-ST-S9-TS.115 Top Slab Formwork Removel 2 29-Jan-24 30-Jan-24 Top Slab Formwork Removel

JAH-Z6-ST-S9-TS.120 Waterproofing for Top Slab 12 31-Jan-24 13-Feb-24 Waterproofing for Top Slab

FINISHING WORK 28 14-Feb-24 17-Mar-24 17-Mar-24, FINISHING WORK


JAH-Z6-ST-S9-FW.100 Above Top Slab Formwork Installation for Plain Concrete 7 14-Feb-24 21-Feb-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S9-FW.105 Plain Concrete Casting 1 22-Feb-24 22-Feb-24 Plain Concrete Casting

JAH-Z6-ST-S9-FW.110 Mass Concrete Casting for Base Slab Top Layer 1 24-Feb-24 24-Feb-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S9-FW.112 Curing work 7 25-Feb-24 03-Mar-24 Curing work

JAH-Z6-ST-S9-FW.115 Concrete Protective coating 12 04-Mar-24 17-Mar-24 Concrete Protective coating

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
401 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
STA. 2+338.227~ 2+358.227 136 01-Nov-23 07-Apr-24 07-Apr-24, STA. 2+338.227~ 2+358.227
BASE SLAB 27 01-Nov-23 02-Dec-23 02-Dec-23, BASE SLAB
JAH-Z6-ST-S10-BS.100Lean Concrete for Base Slab 1 01-Nov-23 01-Nov-23 Lean Concrete for Base Slab

JAH-Z6-ST-S10-BS.105Waterproofing for Lean Concrete 1 02-Nov-23 02-Nov-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S10-BS.110 Base Slab Rebar Installation 8 04-Nov-23 12-Nov-23 Base Slab Rebar Installation

JAH-Z6-ST-S10-BS.115 Base Slab Formwork Installation 7 13-Nov-23 20-Nov-23 Base Slab Formwork Installation

JAH-Z6-ST-S10-BS.120Base Slab Concrete Casting 1 21-Nov-23 21-Nov-23 Base Slab Concrete Casting

JAH-Z6-ST-S10-BS.122Curing work 7 22-Nov-23 29-Nov-23 Curing work

JAH-Z6-ST-S10-BS.125Base Slab Formwork Removel 2 30-Nov-23 02-Dec-23 Base Slab Formwork Removel

COLUMNS 23 03-Dec-23 28-Dec-23 28-Dec-23, COLUMNS


JAH-Z6-ST-S10-CL.100Column Rebar Installation 8 03-Dec-23 11-Dec-23 Column Rebar Installation

JAH-Z6-ST-S10-CL.105Column Formwork Installation 7 12-Dec-23 19-Dec-23 Column Formwork Installation

JAH-Z6-ST-S10-CL.110 Column Concrete Casting 1 20-Dec-23 20-Dec-23 Column Concrete Casting

JAH-Z6-ST-S10-CL.115 Form Work Removal and Curing 7 21-Dec-23 28-Dec-23 Form Work Removal and Curing

TUNNEL WALLS 45 12-Dec-23 01-Feb-24 01-Feb-24, TUNNEL WALLS


JAH-Z6-ST-S10-TW.100Tunnel Walls Rebar Installation 8 12-Dec-23 20-Dec-23 Tunnel Walls Rebar Installation

JAH-Z6-ST-S10-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 21-Dec-23 30-Dec-23 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S10-TW.105Tunnel Formwork Installation 7 31-Dec-23 07-Jan-24 Tunnel Formwork Installation

JAH-Z6-ST-S10-TW.110Tunnel Walls Concrete Casting 1 08-Jan-24 08-Jan-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S10-TW.112Curing work 7 09-Jan-24 16-Jan-24 Curing work

JAH-Z6-ST-S10-TW.120Tunnel Walls Formwork Removel 2 17-Jan-24 18-Jan-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S10-TW.125Tunnel Wall Waterproofing 12 20-Jan-24 01-Feb-24 Tunnel Wall Waterproofing

TOP SLAB 40 20-Jan-24 05-Mar-24 05-Mar-24, TOP SLAB


JAH-Z6-ST-S10-TS.100 Top Slab Rebar Installation 8 20-Jan-24 28-Jan-24 Top Slab Rebar Installation

JAH-Z6-ST-S10-TS.105 Top Slab Formwork Installation 10 29-Jan-24 08-Feb-24 Top Slab Formwork Installation

JAH-Z6-ST-S10-TS.110 Top Slab Concrete Casting 1 10-Feb-24 10-Feb-24 Top Slab Concrete Casting

JAH-Z6-ST-S10-TS.112 Curing work 7 11-Feb-24 18-Feb-24 Curing work

JAH-Z6-ST-S10-TS.115 Top Slab Formwork Removel 2 19-Feb-24 20-Feb-24 Top Slab Formwork Removel

JAH-Z6-ST-S10-TS.120 Waterproofing for Top Slab 12 21-Feb-24 05-Mar-24 Waterproofing for Top Slab

FINISHING WORK 28 06-Mar-24 07-Apr-24 07-Apr-24, FINISHING WORK


JAH-Z6-ST-S10-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 06-Mar-24 13-Mar-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S10-FW.105Plain Concrete Casting 1 14-Mar-24 14-Mar-24 Plain Concrete Casting

JAH-Z6-ST-S10-FW.110Mass Concrete Casting for Base Slab Top Layer 1 16-Mar-24 16-Mar-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S10-FW.112Curing work 7 17-Mar-24 24-Mar-24 Curing work

JAH-Z6-ST-S10-FW.115Concrete Protective coating 12 25-Mar-24 07-Apr-24 Concrete Protective coating

STA. 2+358.227~ 2+378.227 129 30-Nov-23 01-May-24 01-May-24, STA. 2+358.227~ 2+378.227
BASE SLAB 27 30-Nov-23 31-Dec-23 31-Dec-23, BASE SLAB
JAH-Z6-ST-S11-BS.100 Lean Concrete for Base Slab 1 30-Nov-23 30-Nov-23 Lean Concrete for Base Slab

JAH-Z6-ST-S11-BS.105 Waterproofing for Lean Concrete 1 02-Dec-23 02-Dec-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S11-BS.110 Base Slab Rebar Installation 8 03-Dec-23 11-Dec-23 Base Slab Rebar Installation

JAH-Z6-ST-S11-BS.115 Base Slab Formwork Installation 7 12-Dec-23 19-Dec-23 Base Slab Formwork Installation

JAH-Z6-ST-S11-BS.120 Base Slab Concrete Casting 1 20-Dec-23 20-Dec-23 Base Slab Concrete Casting

JAH-Z6-ST-S11-BS.122 Curing work 7 21-Dec-23 28-Dec-23 Curing work

JAH-Z6-ST-S11-BS.125 Base Slab Formwork Removel 2 30-Dec-23 31-Dec-23 Base Slab Formwork Removel

COLUMNS 23 01-Jan-24 27-Jan-24 27-Jan-24, COLUMNS


JAH-Z6-ST-S11-CL.100 Column Rebar Installation 8 01-Jan-24 09-Jan-24 Column Rebar Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
402 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S11-CL.105 Column Formwork Installation 7 10-Jan-24 17-Jan-24 Column Formwork Installation

JAH-Z6-ST-S11-CL.110 Column Concrete Casting 1 18-Jan-24 18-Jan-24 Column Concrete Casting

JAH-Z6-ST-S11-CL.115 Form Work Removal and Curing 7 20-Jan-24 27-Jan-24 Form Work Removal and Curing

TUNNEL WALLS 38 10-Jan-24 22-Feb-24 22-Feb-24, TUNNEL WALLS


JAH-Z6-ST-S11-TW.100Tunnel Walls Rebar Installation 8 10-Jan-24 18-Jan-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S11-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 20-Jan-24 28-Jan-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S11-TW.105Tunnel Formwork Installation 7 29-Jan-24 05-Feb-24 Tunnel Formwork Installation

JAH-Z6-ST-S11-TW.110Tunnel Walls Concrete Casting 1 06-Feb-24 06-Feb-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S11-TW.112Curing work 7 07-Feb-24 14-Feb-24 Curing work

JAH-Z6-ST-S11-TW.120Tunnel Walls Formwork Removel 2 07-Feb-24 08-Feb-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S11-TW.125Tunnel Wall Waterproofing 12 10-Feb-24 22-Feb-24 Tunnel Wall Waterproofing

TOP SLAB 40 10-Feb-24 26-Mar-24 26-Mar-24, TOP SLAB


JAH-Z6-ST-S11-TS.100 Top Slab Rebar Installation 8 10-Feb-24 18-Feb-24 Top Slab Rebar Installation

JAH-Z6-ST-S11-TS.105 Top Slab Formwork Installation 10 19-Feb-24 29-Feb-24 Top Slab Formwork Installation

JAH-Z6-ST-S11-TS.110 Top Slab Concrete Casting 1 02-Mar-24 02-Mar-24 Top Slab Concrete Casting

JAH-Z6-ST-S11-TS.112 Curing work 7 03-Mar-24 10-Mar-24 Curing work

JAH-Z6-ST-S11-TS.115 Top Slab Formwork Removel 2 11-Mar-24 12-Mar-24 Top Slab Formwork Removel

JAH-Z6-ST-S11-TS.120 Waterproofing for Top Slab 12 13-Mar-24 26-Mar-24 Waterproofing for Top Slab

FINISHING WORK 28 27-Mar-24 01-May-24 01-May-24, FINISHING WORK


JAH-Z6-ST-S11-FW.100Above Top Slab Formwork Installation for Plain Concrete 7 27-Mar-24 03-Apr-24 Above Top Slab Formwork Installation for Plain Concrete

JAH-Z6-ST-S11-FW.105Plain Concrete Casting 1 04-Apr-24 04-Apr-24 Plain Concrete Casting

JAH-Z6-ST-S11-FW.107Curing work 7 06-Apr-24 16-Apr-24 Curing work

JAH-Z6-ST-S11-FW.110Mass Concrete Casting for Base Slab Top Layer 1 17-Apr-24 17-Apr-24 Mass Concrete Casting for Base Slab Top Layer

JAH-Z6-ST-S11-FW.115Concrete Protective coating 12 18-Apr-24 01-May-24 Concrete Protective coating

STA. 2+378.227~ 2+398.227 80 30-Dec-23 31-Mar-24 31-Mar-24, STA. 2+378.227~ 2+398.227


BASE SLAB 27 30-Dec-23 29-Jan-24 29-Jan-24, BASE SLAB
JAH-Z6-ST-S12-BS.100Lean Concrete for Base Slab 1 30-Dec-23 30-Dec-23 Lean Concrete for Base Slab

JAH-Z6-ST-S12-BS.105Waterproofing for Lean Concrete 1 31-Dec-23 31-Dec-23 Waterproofing for Lean Concrete

JAH-Z6-ST-S12-BS.110 Base Slab Rebar Installation 8 01-Jan-24 09-Jan-24 Base Slab Rebar Installation

JAH-Z6-ST-S12-BS.115 Base Slab Formwork Installation 7 10-Jan-24 17-Jan-24 Base Slab Formwork Installation

JAH-Z6-ST-S12-BS.120Base Slab Concrete Casting 1 18-Jan-24 18-Jan-24 Base Slab Concrete Casting

JAH-Z6-ST-S12-BS.122Curing work 7 20-Jan-24 27-Jan-24 Curing work

JAH-Z6-ST-S12-BS.125Base Slab Formwork Removel 2 28-Jan-24 29-Jan-24 Base Slab Formwork Removel

COLUMNS 23 30-Jan-24 25-Feb-24 25-Feb-24, COLUMNS


JAH-Z6-ST-S12-CL.100Column Rebar Installation 8 30-Jan-24 07-Feb-24 Column Rebar Installation

JAH-Z6-ST-S12-CL.105Column Formwork Installation 7 08-Feb-24 15-Feb-24 Column Formwork Installation

JAH-Z6-ST-S12-CL.110 Column Concrete Casting 1 17-Feb-24 17-Feb-24 Column Concrete Casting

JAH-Z6-ST-S12-CL.115 Form Work Removal and Curing 7 18-Feb-24 25-Feb-24 Form Work Removal and Curing

TUNNEL WALLS 45 08-Feb-24 31-Mar-24 31-Mar-24, TUNNEL WALLS


JAH-Z6-ST-S12-TW.100Tunnel Walls Rebar Installation 8 08-Feb-24 17-Feb-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S12-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 18-Feb-24 26-Feb-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S12-TW.105Tunnel Formwork Installation 7 27-Feb-24 05-Mar-24 Tunnel Formwork Installation

JAH-Z6-ST-S12-TW.110Tunnel Walls Concrete Casting 1 06-Mar-24 06-Mar-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S12-TW.112Curing work 7 07-Mar-24 14-Mar-24 Curing work

JAH-Z6-ST-S12-TW.120Tunnel Walls Formwork Removel 2 16-Mar-24 17-Mar-24 Tunnel Walls Formwork Removel

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
403 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ST-S12-TW.125Tunnel Wall Waterproofing 12 18-Mar-24 31-Mar-24 Tunnel Wall Waterproofing

STA. 2+398.227~ 2+424.749 79 18-Jan-24 22-Apr-24 22-Apr-24, STA. 2+398.227~ 2+424.749


BASE SLAB 27 18-Jan-24 18-Feb-24 18-Feb-24, BASE SLAB
JAH-Z6-ST-S13-BS.100Lean Concrete for Base Slab 1 18-Jan-24 18-Jan-24 Lean Concrete for Base Slab

JAH-Z6-ST-S13-BS.105Waterproofing for Lean Concrete 1 20-Jan-24 20-Jan-24 Waterproofing for Lean Concrete

JAH-Z6-ST-S13-BS.110 Base Slab Rebar Installation 8 21-Jan-24 29-Jan-24 Base Slab Rebar Installation

JAH-Z6-ST-S13-BS.115 Base Slab Formwork Installation 7 30-Jan-24 06-Feb-24 Base Slab Formwork Installation

JAH-Z6-ST-S13-BS.120Base Slab Concrete Casting 1 07-Feb-24 07-Feb-24 Base Slab Concrete Casting

JAH-Z6-ST-S13-BS.122Curing work 7 08-Feb-24 15-Feb-24 Curing work

JAH-Z6-ST-S13-BS.125Base Slab Formwork Removel 2 17-Feb-24 18-Feb-24 Base Slab Formwork Removel

COLUMNS 23 19-Feb-24 16-Mar-24 16-Mar-24, COLUMNS


JAH-Z6-ST-S13-CL.100Column Rebar Installation 8 19-Feb-24 27-Feb-24 Column Rebar Installation

JAH-Z6-ST-S13-CL.105Column Formwork Installation 7 28-Feb-24 06-Mar-24 Column Formwork Installation

JAH-Z6-ST-S13-CL.110 Column Concrete Casting 1 07-Mar-24 07-Mar-24 Column Concrete Casting

JAH-Z6-ST-S13-CL.115 Form Work Removal and Curing 7 09-Mar-24 16-Mar-24 Form Work Removal and Curing

TUNNEL WALLS 52 19-Feb-24 22-Apr-24 22-Apr-24, TUNNEL WALLS


JAH-Z6-ST-S13-TW.100Tunnel Walls Rebar Installation 8 19-Feb-24 27-Feb-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S13-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 28-Feb-24 07-Mar-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S13-TW.105Tunnel Formwork Installation 7 17-Mar-24 24-Mar-24 Tunnel Formwork Installation

JAH-Z6-ST-S13-TW.110Tunnel Walls Concrete Casting 1 25-Mar-24 25-Mar-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S13-TW.112Curing work 7 26-Mar-24 02-Apr-24 Curing work

JAH-Z6-ST-S13-TW.120Tunnel Walls Formwork Removel 2 03-Apr-24 04-Apr-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S13-TW.125Tunnel Wall Waterproofing 12 06-Apr-24 22-Apr-24 Tunnel Wall Waterproofing

STA. 2+424.749~ 2+469.749 80 17-Feb-24 22-May-24 22-May-24, STA. 2+424.749~ 2+469.749


BASE SLAB 27 17-Feb-24 18-Mar-24 18-Mar-24, BASE SLAB
JAH-Z6-ST-S14-BS.100Lean Concrete for Base Slab 1 17-Feb-24 17-Feb-24 Lean Concrete for Base Slab

JAH-Z6-ST-S14-BS.105Waterproofing for Lean Concrete 1 18-Feb-24 18-Feb-24 Waterproofing for Lean Concrete

JAH-Z6-ST-S14-BS.110 Base Slab Rebar Installation 8 19-Feb-24 27-Feb-24 Base Slab Rebar Installation

JAH-Z6-ST-S14-BS.115 Base Slab Formwork Installation 7 28-Feb-24 06-Mar-24 Base Slab Formwork Installation

JAH-Z6-ST-S14-BS.120Base Slab Concrete Casting 1 07-Mar-24 07-Mar-24 Base Slab Concrete Casting

JAH-Z6-ST-S14-BS.122Curing work 7 09-Mar-24 16-Mar-24 Curing work

JAH-Z6-ST-S14-BS.125Base Slab Formwork Removel 2 17-Mar-24 18-Mar-24 Base Slab Formwork Removel

COLUMNS 23 19-Mar-24 17-Apr-24 17-Apr-24, COLUMNS


JAH-Z6-ST-S14-CL.100Column Rebar Installation 8 19-Mar-24 27-Mar-24 Column Rebar Installation

JAH-Z6-ST-S14-CL.105Column Formwork Installation 7 28-Mar-24 04-Apr-24 Column Formwork Installation

JAH-Z6-ST-S14-CL.107Column Concrete Casting 1 06-Apr-24 06-Apr-24 Column Concrete Casting

JAH-Z6-ST-S14-CL.110 Form Work Removal and Curing 7 07-Apr-24 17-Apr-24 Form Work Removal and Curing

TUNNEL WALLS 45 28-Mar-24 22-May-24 22-May-24, TUNNEL WALLS


JAH-Z6-ST-S14-TW.100Tunnel Walls Rebar Installation 8 28-Mar-24 06-Apr-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S14-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 07-Apr-24 18-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S14-TW.105Tunnel Formwork Installation 7 20-Apr-24 27-Apr-24 Tunnel Formwork Installation

JAH-Z6-ST-S14-TW.110Tunnel Walls Concrete Casting 1 28-Apr-24 28-Apr-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S14-TW.112Curing work 7 29-Apr-24 06-May-24 Curing work

JAH-Z6-ST-S14-TW.120Tunnel Walls Formwork Removel 2 07-May-24 08-May-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S14-TW.125Tunnel Wall Waterproofing 12 09-May-24 22-May-24 Tunnel Wall Waterproofing

STA. 2+469.749~ 2+498.227 67 07-Mar-24 27-May-24 27-May-24, STA. 2+469.749~ 2+498.227

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
404 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
BASE SLAB 27 07-Mar-24 07-Apr-24 07-Apr-24, BASE SLAB
JAH-Z6-ST-S15-BS100 Lean Concrete for Base Slab 1 07-Mar-24 07-Mar-24 Lean Concrete for Base Slab

JAH-Z6-ST-S15-BS105 Waterproofing for Lean Concrete 1 09-Mar-24 09-Mar-24 Waterproofing for Lean Concrete

JAH-Z6-ST-S15-BS110 Base Slab Rebar Installation 8 10-Mar-24 18-Mar-24 Base Slab Rebar Installation

JAH-Z6-ST-S15-BS115 Base Slab Formwork Installation 7 19-Mar-24 26-Mar-24 Base Slab Formwork Installation

JAH-Z6-ST-S15-BS120 Base Slab Concrete Casting 1 27-Mar-24 27-Mar-24 Base Slab Concrete Casting

JAH-Z6-ST-S15-BS125 Curing work 7 28-Mar-24 04-Apr-24 Curing work

JAH-Z6-ST-S15-BS130 Base Slab Formwork Removel 2 06-Apr-24 07-Apr-24 Base Slab Formwork Removel

TUNNEL WALLS 49 28-Mar-24 27-May-24 27-May-24, TUNNEL WALLS


JAH-Z6-ST-S15-TW.100Tunnel Walls Rebar Installation 8 28-Mar-24 06-Apr-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S15-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 07-Apr-24 18-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S15-TW.105Tunnel Formwork Installation 7 20-Apr-24 27-Apr-24 Tunnel Formwork Installation

JAH-Z6-ST-S15-TW.110Tunnel Walls Concrete Casting 1 02-May-24 02-May-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S15-TW.112Curing work 7 04-May-24 11-May-24 Curing work

JAH-Z6-ST-S15-TW.120Tunnel Walls Formwork Removel 2 12-May-24 13-May-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S15-TW.125Tunnel Wall Waterproofing 12 14-May-24 27-May-24 Tunnel Wall Waterproofing

STA. 2+498.227~ 2+518.227 63 09-Mar-24 23-May-24 23-May-24, STA. 2+498.227~ 2+518.227


BASE SLAB 27 09-Mar-24 08-Apr-24 08-Apr-24, BASE SLAB
JAH-Z6-ST-S16-BS100 Lean Concrete for Base Slab 1 09-Mar-24 09-Mar-24 Lean Concrete for Base Slab

JAH-Z6-ST-S16-BS105 Waterproofing for Lean Concrete 1 10-Mar-24 10-Mar-24 Waterproofing for Lean Concrete

JAH-Z6-ST-S16-BS110 Base Slab Rebar Installation 8 11-Mar-24 19-Mar-24 Base Slab Rebar Installation

JAH-Z6-ST-S16-BS115 Base Slab Formwork Installation 7 20-Mar-24 27-Mar-24 Base Slab Formwork Installation

JAH-Z6-ST-S16-BS120 Base Slab Concrete Casting 1 28-Mar-24 28-Mar-24 Base Slab Concrete Casting

JAH-Z6-ST-S16-BS125 Curing work 7 30-Mar-24 06-Apr-24 Curing work

JAH-Z6-ST-S16-BS130 Base Slab Formwork Removel 2 07-Apr-24 08-Apr-24 Base Slab Formwork Removel

TUNNEL WALLS 45 30-Mar-24 23-May-24 23-May-24, TUNNEL WALLS


JAH-Z6-ST-S16-TW.100Tunnel Walls Rebar Installation 8 30-Mar-24 07-Apr-24 Tunnel Walls Rebar Installation

JAH-Z6-ST-S16-TW.103PVC Conduit Pipes/Utility Ducts/Sleeves Installation 8 08-Apr-24 20-Apr-24 PVC Conduit Pipes/Utility Ducts/Sleeves Installation

JAH-Z6-ST-S16-TW.105Tunnel Formwork Installation 7 21-Apr-24 28-Apr-24 Tunnel Formwork Installation

JAH-Z6-ST-S16-TW.110Tunnel Walls Concrete Casting 1 29-Apr-24 29-Apr-24 Tunnel Walls Concrete Casting

JAH-Z6-ST-S16-TW.112Curing work 7 30-Apr-24 07-May-24 Curing work

JAH-Z6-ST-S16-TW.120Tunnel Walls Formwork Removel 2 08-May-24 09-May-24 Tunnel Walls Formwork Removel

JAH-Z6-ST-S16-TW.125Tunnel Wall Waterproofing 12 11-May-24 23-May-24 Tunnel Wall Waterproofing

WET CULVERT ZONE 6 245 09-Aug-23 25-May-24 25-May-24, WET CULVERT ZONE 6
Sta 2+095.286-Sta2+939.115 - @ZONE 6 245 09-Aug-23 25-May-24 25-May-24, Sta 2+095.286-Sta2+939.115 - @ZONE 6
1st 2+095.286-Sta2+299.115 178 09-Aug-23 04-Mar-24 04-Mar-24, 1st 2+095.286-Sta2+299.115
BASE SLAB 99 09-Aug-23 03-Dec-23 03-Dec-23, BASE SLAB
CULV-WT-ST1-BS100 Lean concrete for Base slab 10 09-Aug-23 20-Aug-23 Lean concrete for Base slab

CULV-WT-ST1-BS105 Waterproofing for Lean concrete 15 21-Aug-23 06-Sep-23 Waterproofing for Lean concrete

CULV-WT-ST1-BS110 Base slab Rebar installation 37 07-Sep-23 21-Oct-23 Base slab Rebar installation

CULV-WT-ST1-BS115 Base slab formwork Installation 22 22-Oct-23 15-Nov-23 Base slab formwork Installation

CULV-WT-ST1-BS120 Base slab concrete casting 8 16-Nov-23 25-Nov-23 Base slab concrete casting

CULV-WT-ST1-BS125 Base Slab Formwork Removel, Curing & Strength Gaining 7 26-Nov-23 03-Dec-23 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 65 22-Oct-23 04-Jan-24 04-Jan-24, CULVERT WALL


CULV-WT-ST1-CW.125Culvert Wall Rebar installation 26 22-Oct-23 20-Nov-23 Culvert Wall Rebar installation

CULV-WT-ST1-CW.130Culvert Wall Formwork Installation 15 21-Nov-23 07-Dec-23 Culvert Wall Formwork Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
405 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-WT-ST1-CW.135Culvert Wall concrete casting 7 09-Dec-23 16-Dec-23 Culvert Wall concrete casting

CULV-WT-ST1-CW.140Culvert Walls Formwork Removel and Curing 7 17-Dec-23 24-Dec-23 Culvert Walls Formwork Removel and Curing

CULV-WT-ST1-CW.145Waterproofing for Culvert wall 10 25-Dec-23 04-Jan-24 Waterproofing for Culvert wall

TOP SLAB 65 09-Dec-23 21-Feb-24 21-Feb-24, TOP SLAB


CULV-WT-ST1-TS.130 Top Slab Scaffold and Bottom Formwork installation 22 09-Dec-23 02-Jan-24 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST1-TS.135 Top slab Rebar installation 14 03-Jan-24 18-Jan-24 Top slab Rebar installation

CULV-WT-ST1-TS.140 Top slab Vertical formwork installation 7 20-Jan-24 27-Jan-24 Top slab Vertical formwork installation

CULV-WT-ST1-TS.145 Top slab concrete casting 7 28-Jan-24 04-Feb-24 Top slab concrete casting

CULV-WT-ST1-TS.150 Top Slab Formwork Removel and Curing 5 05-Feb-24 10-Feb-24 Top Slab Formwork Removel and Curing

CULV-WT-ST1-TS.155 Waterproofing of Top slab 10 11-Feb-24 21-Feb-24 Waterproofing of Top slab

PLAIN CONCRETE 10 11-Feb-24 21-Feb-24 21-Feb-24, PLAIN CONCRETE


CULV-WT-ST1-PC.110Plain concrete formwork installation 5 11-Feb-24 15-Feb-24 Plain concrete formwork installation

CULV-WT-ST1-PC.115Plain concrete 5 17-Feb-24 21-Feb-24 Plain concrete

FINISHING 10 22-Feb-24 04-Mar-24 04-Mar-24, FINISHING


CULV-WT-ST1-FN.105Concrete Protective coating 10 22-Feb-24 04-Mar-24 Concrete Protective coating

2nd 2+299.115-Sta2+499.115 170 07-Sep-23 24-Mar-24 24-Mar-24, 2nd 2+299.115-Sta2+499.115


BASE SLAB 95 07-Sep-23 27-Dec-23 27-Dec-23, BASE SLAB
CULV-WT-ST2-BS.160Lean concrete for Base slab 10 07-Sep-23 18-Sep-23 Lean concrete for Base slab

CULV-WT-ST2-BS.165Waterproofing for Lean concrete 15 19-Sep-23 07-Oct-23 Waterproofing for Lean concrete

CULV-WT-ST2-BS.170Base slab Rebar installation 35 08-Oct-23 16-Nov-23 Base slab Rebar installation

CULV-WT-ST2-BS.175Base slab formwork Installation 21 18-Nov-23 11-Dec-23 Base slab formwork Installation

CULV-WT-ST2-BS.180Base slab concrete casting 7 12-Dec-23 19-Dec-23 Base slab concrete casting

CULV-WT-ST2-BS.185Base Slab Formwork Removel, Curing & Strength Gaining 7 20-Dec-23 27-Dec-23 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 63 18-Nov-23 29-Jan-24 29-Jan-24, CULVERT WALL


CULV-WT-ST2-CW.150Culvert Wall Rebar installation 25 18-Nov-23 16-Dec-23 Culvert Wall Rebar installation

CULV-WT-ST2-CW.155Culvert Wall Formwork Installation 14 17-Dec-23 01-Jan-24 Culvert Wall Formwork Installation

CULV-WT-ST2-CW.160Culvert Wall concrete casting 7 02-Jan-24 09-Jan-24 Culvert Wall concrete casting

CULV-WT-ST2-CW.165Culvert Walls Formwork Removel and Curing 7 10-Jan-24 17-Jan-24 Culvert Walls Formwork Removel and Curing

CULV-WT-ST2-CW.170Waterproofing for Culvert wall 10 18-Jan-24 29-Jan-24 Waterproofing for Culvert wall

TOP SLAB 62 02-Jan-24 13-Mar-24 13-Mar-24, TOP SLAB


CULV-WT-ST2-TS.160 Top Slab Scaffold and Bottom Formwork installation 21 02-Jan-24 25-Jan-24 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST2-TS.165 Top slab Rebar installation 12 27-Jan-24 08-Feb-24 Top slab Rebar installation

CULV-WT-ST2-TS.170 Top slab Vertical formwork installation 7 10-Feb-24 17-Feb-24 Top slab Vertical formwork installation

CULV-WT-ST2-TS.175 Top slab concrete casting 7 18-Feb-24 25-Feb-24 Top slab concrete casting

CULV-WT-ST2-TS.180 Top Slab Formwork Removel and Curing 5 26-Feb-24 02-Mar-24 Top Slab Formwork Removel and Curing

CULV-WT-ST2-TS.185 Waterproofing of Top slab 10 03-Mar-24 13-Mar-24 Waterproofing of Top slab

PLAIN CONCRETE 9 03-Mar-24 12-Mar-24 12-Mar-24, PLAIN CONCRETE


CULV-WT-ST2-PC.120Plain concrete formwork installation 5 03-Mar-24 07-Mar-24 Plain concrete formwork installation

CULV-WT-ST2-PC.125Plain concrete 4 09-Mar-24 12-Mar-24 Plain concrete

FINISHING 10 13-Mar-24 24-Mar-24 24-Mar-24, FINISHING


CULV-WT-ST2-FN.110Concrete Protective coating 10 13-Mar-24 24-Mar-24 Concrete Protective coating

3rd 2+499.115-Sta2+699.115 170 08-Oct-23 25-Apr-24 25-Apr-24, 3rd 2+499.115-Sta2+699.115


BASE SLAB 95 08-Oct-23 25-Jan-24 25-Jan-24, BASE SLAB
CULV-WT-ST3-BS.190Lean concrete for Base slab 10 08-Oct-23 18-Oct-23 Lean concrete for Base slab

CULV-WT-ST3-BS.195Waterproofing for Lean concrete 15 19-Oct-23 05-Nov-23 Waterproofing for Lean concrete

CULV-WT-ST3-BS.200Base slab Rebar installation 35 06-Nov-23 16-Dec-23 Base slab Rebar installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
406 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-WT-ST3-BS.205Base slab formwork Installation 21 17-Dec-23 09-Jan-24 Base slab formwork Installation

CULV-WT-ST3-BS.210Base slab concrete casting 7 10-Jan-24 17-Jan-24 Base slab concrete casting

CULV-WT-ST3-BS.215Base Slab Formwork Removel, Curing & Strength Gaining 7 18-Jan-24 25-Jan-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 63 17-Dec-23 27-Feb-24 27-Feb-24, CULVERT WALL


CULV-WT-ST3-CW.175Culvert Wall Rebar installation 25 17-Dec-23 14-Jan-24 Culvert Wall Rebar installation

CULV-WT-ST3-CW.180Culvert Wall Formwork Installation 14 15-Jan-24 30-Jan-24 Culvert Wall Formwork Installation

CULV-WT-ST3-CW.185Culvert Wall concrete casting 7 31-Jan-24 07-Feb-24 Culvert Wall concrete casting

CULV-WT-ST3-CW.190Culvert Walls Formwork Removel and Curing 7 08-Feb-24 15-Feb-24 Culvert Walls Formwork Removel and Curing

CULV-WT-ST3-CW.195Waterproofing for Culvert wall 10 17-Feb-24 27-Feb-24 Waterproofing for Culvert wall

TOP SLAB 62 31-Jan-24 15-Apr-24 15-Apr-24, TOP SLAB


CULV-WT-ST3-TS.190 Top Slab Scaffold and Bottom Formwork installation 21 31-Jan-24 24-Feb-24 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST3-TS.195 Top slab Rebar installation 12 25-Feb-24 09-Mar-24 Top slab Rebar installation

CULV-WT-ST3-TS.200 Top slab Vertical formwork installation 7 10-Mar-24 17-Mar-24 Top slab Vertical formwork installation

CULV-WT-ST3-TS.205 Top slab concrete casting 7 18-Mar-24 25-Mar-24 Top slab concrete casting

CULV-WT-ST3-TS.210 Top Slab Formwork Removel and Curing 5 26-Mar-24 31-Mar-24 Top Slab Formwork Removel and Curing

CULV-WT-ST3-TS.215 Waterproofing of Top slab 10 01-Apr-24 15-Apr-24 Waterproofing of Top slab

PLAIN CONCRETE 9 01-Apr-24 14-Apr-24 14-Apr-24, PLAIN CONCRETE


CULV-WT-ST3-PC.130Plain concrete formwork installation 5 01-Apr-24 06-Apr-24 Plain concrete formwork installation

CULV-WT-ST3-PC.135Plain concrete 4 07-Apr-24 14-Apr-24 Plain concrete

FINISHING 10 15-Apr-24 25-Apr-24 25-Apr-24, FINISHING


CULV-WT-ST3-FN.115Concrete Protective coating 10 15-Apr-24 25-Apr-24 Concrete Protective coating

4th 2+699.115-Sta2+899.115 170 06-Nov-23 25-May-24 25-May-24, 4th 2+699.115-Sta2+899.115


BASE SLAB 95 06-Nov-23 24-Feb-24 24-Feb-24, BASE SLAB
CULV-WT-ST4-BS.220Lean concrete for Base slab 10 06-Nov-23 16-Nov-23 Lean concrete for Base slab

CULV-WT-ST4-BS.225Waterproofing for Lean concrete 15 18-Nov-23 04-Dec-23 Waterproofing for Lean concrete

CULV-WT-ST4-BS.230Base slab Rebar installation 35 05-Dec-23 14-Jan-24 Base slab Rebar installation

CULV-WT-ST4-BS.235Base slab formwork Installation 21 15-Jan-24 07-Feb-24 Base slab formwork Installation

CULV-WT-ST4-BS.240Base slab concrete casting 7 08-Feb-24 15-Feb-24 Base slab concrete casting

CULV-WT-ST4-BS.245Base Slab Formwork Removel, Curing & Strength Gaining 7 17-Feb-24 24-Feb-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 63 15-Jan-24 27-Mar-24 27-Mar-24, CULVERT WALL


CULV-WT-ST4-CW.200Culvert Wall Rebar installation 25 15-Jan-24 12-Feb-24 Culvert Wall Rebar installation

CULV-WT-ST4-CW.205Culvert Wall Formwork Installation 14 13-Feb-24 28-Feb-24 Culvert Wall Formwork Installation

CULV-WT-ST4-CW.210Culvert Wall concrete casting 7 29-Feb-24 07-Mar-24 Culvert Wall concrete casting

CULV-WT-ST4-CW.215Culvert Walls Formwork Removel and Curing 7 09-Mar-24 16-Mar-24 Culvert Walls Formwork Removel and Curing

CULV-WT-ST4-CW.220Waterproofing for Culvert wall 10 17-Mar-24 27-Mar-24 Waterproofing for Culvert wall

TOP SLAB 62 29-Feb-24 14-May-24 14-May-24, TOP SLAB


CULV-WT-ST4-TS.220 Top Slab Scaffold and Bottom Formwork installation 21 29-Feb-24 24-Mar-24 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST4-TS.225 Top slab Rebar installation 12 25-Mar-24 07-Apr-24 Top slab Rebar installation

CULV-WT-ST4-TS.230 Top slab Vertical formwork installation 7 08-Apr-24 18-Apr-24 Top slab Vertical formwork installation

CULV-WT-ST4-TS.235 Top slab concrete casting 7 20-Apr-24 27-Apr-24 Top slab concrete casting

CULV-WT-ST4-TS.240 Top Slab Formwork Removel and Curing 5 28-Apr-24 02-May-24 Top Slab Formwork Removel and Curing

CULV-WT-ST4-TS.245 Waterproofing of Top slab 10 04-May-24 14-May-24 Waterproofing of Top slab

PLAIN CONCRETE 9 04-May-24 13-May-24 13-May-24, PLAIN CONCRETE


CULV-WT-ST4-PC.140Plain concrete formwork installation 5 04-May-24 08-May-24 Plain concrete formwork installation

CULV-WT-ST4-PC.145Plain concrete 4 09-May-24 13-May-24 Plain concrete

FINISHING 10 14-May-24 25-May-24 25-May-24, FINISHING

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
407 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-WT-ST4-FN.120Concrete Protective coating 10 14-May-24 25-May-24 Concrete Protective coating

5th 2+899.115-Sta2+939.115 144 05-Dec-23 23-May-24 23-May-24, 5th 2+899.115-Sta2+939.115


BASE SLAB 57 05-Dec-23 08-Feb-24 08-Feb-24, BASE SLAB
CULV-WT-ST5-BS.250Lean concrete for Base slab 10 05-Dec-23 16-Dec-23 Lean concrete for Base slab

CULV-WT-ST5-BS.255Waterproofing for Lean concrete 8 17-Dec-23 25-Dec-23 Waterproofing for Lean concrete

CULV-WT-ST5-BS.260Base slab Rebar installation 18 26-Dec-23 15-Jan-24 Base slab Rebar installation

CULV-WT-ST5-BS.265Base slab formwork Installation 12 16-Jan-24 29-Jan-24 Base slab formwork Installation

CULV-WT-ST5-BS.270Base slab concrete casting 4 30-Jan-24 03-Feb-24 Base slab concrete casting

CULV-WT-ST5-BS.275Base Slab Formwork Removel, Curing & Strength Gaining 5 04-Feb-24 08-Feb-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 36 16-Jan-24 26-Feb-24 26-Feb-24, CULVERT WALL


CULV-WT-ST5-CW.225Culvert Wall Rebar installation 14 16-Jan-24 31-Jan-24 Culvert Wall Rebar installation

CULV-WT-ST5-CW.230Culvert Wall Formwork Installation 8 01-Feb-24 10-Feb-24 Culvert Wall Formwork Installation

CULV-WT-ST5-CW.235Culvert Wall concrete casting 5 11-Feb-24 15-Feb-24 Culvert Wall concrete casting

CULV-WT-ST5-CW.240Culvert Walls Formwork Removel and Curing 3 17-Feb-24 19-Feb-24 Culvert Walls Formwork Removel and Curing

CULV-WT-ST5-CW.245Waterproofing for Culvert wall 6 20-Feb-24 26-Feb-24 Waterproofing for Culvert wall

TOP SLAB 86 11-Feb-24 23-May-24 23-May-24, TOP SLAB


CULV-WT-ST5-TS.250 Top Slab Scaffold and Bottom Formwork installation 12 11-Feb-24 24-Feb-24 Top Slab Scaffold and Bottom Formwork installation

CULV-WT-ST5-TS.255 Top slab Rebar installation 7 25-Feb-24 03-Mar-24 Top slab Rebar installation

CULV-WT-ST5-TS.260 Top slab Vertical formwork installation 4 04-Mar-24 07-Mar-24 Top slab Vertical formwork installation

CULV-WT-ST5-TS.265 Top slab concrete casting 3 09-Mar-24 11-Mar-24 Top slab concrete casting

CULV-WT-ST5-TS.270 Top Slab Formwork Removel and Curing 4 12-Mar-24 16-Mar-24 Top Slab Formwork Removel and Curing

CULV-WT-ST5-TS.275 Waterproofing of Top slab 8 15-May-24 23-May-24 Waterproofing of Top slab

PLAIN CONCRETE 7 17-Mar-24 24-Mar-24 24-Mar-24, PLAIN CONCRETE


CULV-WT-ST5-PC.150Plain concrete formwork installation 5 17-Mar-24 21-Mar-24 Plain concrete formwork installation

CULV-WT-ST5-PC.155Plain concrete 2 23-Mar-24 24-Mar-24 Plain concrete

FINISHING 10 25-Mar-24 04-Apr-24 04-Apr-24, FINISHING


CULV-WT-ST5-FN.125Concrete Protective coating 10 25-Mar-24 04-Apr-24 Concrete Protective coating

DRY CULVERT ZONE 6 236 09-Aug-23 14-May-24 14-May-24, DRY CULVERT ZONE 6
DRY CULVERT STA. 1+870.827 ~ 2+725.508 - @ZONE 6 236 09-Aug-23 14-May-24 14-May-24, DRY CULVERT STA. 1+870.827 ~ 2+725.508 - @ZONE 6
1ST STA. 1+870.827-Sta2+065.508 180 09-Aug-23 06-Mar-24 06-Mar-24, 1ST STA. 1+870.827-Sta2+065.508
BASE SLAB 99 09-Aug-23 03-Dec-23 03-Dec-23, BASE SLAB
CULV-DR-ST1-BS.520Lean concrete for Base slab 10 09-Aug-23 20-Aug-23 Lean concrete for Base slab

CULV-DR-ST1-BS.525Waterproofing for Lean concrete 15 21-Aug-23 06-Sep-23 Waterproofing for Lean concrete

CULV-DR-ST1-BS.530Base slab Rebar installation 37 07-Sep-23 21-Oct-23 Base slab Rebar installation

CULV-DR-ST1-BS.535Base slab formwork Installation 22 22-Oct-23 15-Nov-23 Base slab formwork Installation

CULV-DR-ST1-BS.540Base slab concrete casting 8 16-Nov-23 25-Nov-23 Base slab concrete casting

CULV-DR-ST1-BS.545Base Slab Formwork Removel, Curing & Strength Gaining 7 26-Nov-23 03-Dec-23 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 65 22-Oct-23 04-Jan-24 04-Jan-24, CULVERT WALL


CULV-DR-ST1-CW.450Culvert Wall Rebar installation 26 22-Oct-23 20-Nov-23 Culvert Wall Rebar installation

CULV-DR-ST1-CW.455Culvert Wall Formwork Installation 15 21-Nov-23 07-Dec-23 Culvert Wall Formwork Installation

CULV-DR-ST1-CW.460Culvert Wall concrete casting 7 09-Dec-23 16-Dec-23 Culvert Wall concrete casting

CULV-DR-ST1-CW.465Culvert Walls Formwork Removel and Curing 7 17-Dec-23 24-Dec-23 Culvert Walls Formwork Removel and Curing

CULV-DR-ST1-CW.470Waterproofing for Culvert wall 10 25-Dec-23 04-Jan-24 Waterproofing for Culvert wall

TOP SLAB 67 09-Dec-23 24-Feb-24 24-Feb-24, TOP SLAB


CULV-DR-ST1-TS.520Top Slab Scaffold and Bottom Formwork installation 22 09-Dec-23 02-Jan-24 Top Slab Scaffold and Bottom Formwork installation

CULV-DR-ST1-TS.525Top slab Rebar installation 14 06-Jan-24 21-Jan-24 Top slab Rebar installation

CULV-DR-ST1-TS.530Top slab Vertical formwork installation 7 22-Jan-24 29-Jan-24 Top slab Vertical formwork installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
408 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-DR-ST1-TS.535Top slab concrete casting 7 30-Jan-24 06-Feb-24 Top slab concrete casting

CULV-DR-ST1-TS.540Top Slab Formwork Removel and Curing 5 07-Feb-24 12-Feb-24 Top Slab Formwork Removel and Curing

CULV-DR-ST1-TS.545Waterproofing of Top slab 10 13-Feb-24 24-Feb-24 Waterproofing of Top slab

PLAIN CONCRETE 10 13-Feb-24 24-Feb-24 24-Feb-24, PLAIN CONCRETE


CULV-DR-ST1-PC.240Plain concrete formwork installation 5 13-Feb-24 18-Feb-24 Plain concrete formwork installation

CULV-DR-ST1-PC.245Plain concrete 5 19-Feb-24 24-Feb-24 Plain concrete

FINISHING 10 25-Feb-24 06-Mar-24 06-Mar-24, FINISHING


CULV-DR-ST1-FN.170Concrete Protective coating 10 25-Feb-24 06-Mar-24 Concrete Protective coating

2ND STA. 2+065.508-Sta2+265.508 187 07-Sep-23 16-Apr-24 16-Apr-24, 2ND STA. 2+065.508-Sta2+265.508
BASE SLAB 99 07-Sep-23 01-Jan-24 01-Jan-24, BASE SLAB
CULV-DR-ST2-BS.550Lean concrete for Base slab 10 07-Sep-23 18-Sep-23 Lean concrete for Base slab

CULV-DR-ST2-BS.555Waterproofing for Lean concrete 15 19-Sep-23 07-Oct-23 Waterproofing for Lean concrete

CULV-DR-ST2-BS.560Base slab Rebar installation 37 08-Oct-23 19-Nov-23 Base slab Rebar installation

CULV-DR-ST2-BS.565Base slab formwork Installation 22 20-Nov-23 14-Dec-23 Base slab formwork Installation

CULV-DR-ST2-BS.570Base slab concrete casting 8 16-Dec-23 24-Dec-23 Base slab concrete casting

CULV-DR-ST2-BS.575Base Slab Formwork Removel, Curing & Strength Gaining 7 25-Dec-23 01-Jan-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 65 20-Nov-23 03-Feb-24 03-Feb-24, CULVERT WALL


CULV-DR-ST2-CW.475Culvert Wall Rebar installation 26 20-Nov-23 19-Dec-23 Culvert Wall Rebar installation

CULV-DR-ST2-CW.480Culvert Wall Formwork Installation 15 20-Dec-23 06-Jan-24 Culvert Wall Formwork Installation

CULV-DR-ST2-CW.485Culvert Wall concrete casting 7 07-Jan-24 14-Jan-24 Culvert Wall concrete casting

CULV-DR-ST2-CW.490Culvert Walls Formwork Removel and Curing 7 15-Jan-24 22-Jan-24 Culvert Walls Formwork Removel and Curing

CULV-DR-ST2-CW.495Waterproofing for Culvert wall 10 23-Jan-24 03-Feb-24 Waterproofing for Culvert wall

TOP SLAB 72 07-Jan-24 30-Mar-24 30-Mar-24, TOP SLAB


CULV-DR-ST2-TS.550Top Slab Scaffold and Bottom Formwork installation 21 07-Jan-24 30-Jan-24 Top Slab Scaffold and Bottom Formwork installation

CULV-DR-ST2-TS.555Top slab Rebar installation 14 04-Feb-24 19-Feb-24 Top slab Rebar installation

CULV-DR-ST2-TS.560Top slab Vertical formwork installation 8 20-Feb-24 28-Feb-24 Top slab Vertical formwork installation

CULV-DR-ST2-TS.565Top slab concrete casting 8 29-Feb-24 09-Mar-24 Top slab concrete casting

CULV-DR-ST2-TS.570Top Slab Formwork Removel and Curing 7 10-Mar-24 17-Mar-24 Top Slab Formwork Removel and Curing

CULV-DR-ST2-TS.575Waterproofing of Top slab 11 18-Mar-24 30-Mar-24 Waterproofing of Top slab

PLAIN CONCRETE 9 18-Mar-24 27-Mar-24 27-Mar-24, PLAIN CONCRETE


CULV-DR-ST2-PC.250Plain concrete formwork installation 5 18-Mar-24 23-Mar-24 Plain concrete formwork installation

CULV-DR-ST2-PC.255Plain concrete 4 24-Mar-24 27-Mar-24 Plain concrete

FINISHING 14 28-Mar-24 16-Apr-24 16-Apr-24, FINISHING


CULV-DR-ST2-FN.175Concrete Protective coating 14 28-Mar-24 16-Apr-24 Concrete Protective coating

3RD STA. 2+265.508-Sta2+465.508 191 19-Sep-23 02-May-24 02-May-24, 3RD STA. 2+265.508-Sta2+465.508
BASE SLAB 99 19-Sep-23 13-Jan-24 13-Jan-24, BASE SLAB
CULV-DR-ST3-BS.580Lean concrete for Base slab 10 19-Sep-23 01-Oct-23 Lean concrete for Base slab

CULV-DR-ST3-BS.585Waterproofing for Lean concrete 15 02-Oct-23 18-Oct-23 Waterproofing for Lean concrete

CULV-DR-ST3-BS.590Base slab Rebar installation 37 19-Oct-23 30-Nov-23 Base slab Rebar installation

CULV-DR-ST3-BS.595Base slab formwork Installation 22 02-Dec-23 26-Dec-23 Base slab formwork Installation

CULV-DR-ST3-BS.600Base slab concrete casting 8 27-Dec-23 04-Jan-24 Base slab concrete casting

CULV-DR-ST3-BS.605Base Slab Formwork Removel, Curing & Strength Gaining 7 06-Jan-24 13-Jan-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 68 02-Dec-23 18-Feb-24 18-Feb-24, CULVERT WALL


CULV-DR-ST3-CW.500Culvert Wall Rebar installation 26 02-Dec-23 31-Dec-23 Culvert Wall Rebar installation

CULV-DR-ST3-CW.505Culvert Wall Formwork Installation 15 01-Jan-24 17-Jan-24 Culvert Wall Formwork Installation

CULV-DR-ST3-CW.510Culvert Wall concrete casting 8 18-Jan-24 27-Jan-24 Culvert Wall concrete casting

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
409 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
CULV-DR-ST3-CW.515Culvert Walls Formwork Removel and Curing 8 28-Jan-24 05-Feb-24 Culvert Walls Formwork Removel and Curing

CULV-DR-ST3-CW.520Waterproofing for Culvert wall 11 06-Feb-24 18-Feb-24 Waterproofing for Culvert wall

TOP SLAB 74 18-Jan-24 16-Apr-24 16-Apr-24, TOP SLAB


CULV-DR-ST3-TS.580Top Slab Scaffold and Bottom Formwork installation 21 18-Jan-24 11-Feb-24 Top Slab Scaffold and Bottom Formwork installation

CULV-DR-ST3-TS.585Top slab Rebar installation 13 19-Feb-24 04-Mar-24 Top slab Rebar installation

CULV-DR-ST3-TS.590Top slab Vertical formwork installation 8 05-Mar-24 13-Mar-24 Top slab Vertical formwork installation

CULV-DR-ST3-TS.595Top slab concrete casting 8 14-Mar-24 23-Mar-24 Top slab concrete casting

CULV-DR-ST3-TS.600Top Slab Formwork Removel and Curing 7 24-Mar-24 31-Mar-24 Top Slab Formwork Removel and Curing

CULV-DR-ST3-TS.605Waterproofing of Top slab 11 01-Apr-24 16-Apr-24 Waterproofing of Top slab

PLAIN CONCRETE 7 01-Apr-24 08-Apr-24 08-Apr-24, PLAIN CONCRETE


CULV-DR-ST3-PC.260Plain concrete formwork installation 5 01-Apr-24 06-Apr-24 Plain concrete formwork installation

CULV-DR-ST3-PC.265Plain concrete 2 07-Apr-24 08-Apr-24 Plain concrete

FINISHING 14 17-Apr-24 02-May-24 02-May-24, FINISHING


CULV-DR-ST3-FN.180Concrete Protective coating 14 17-Apr-24 02-May-24 Concrete Protective coating

4TH STA. 2+465.508-Sta2+725.508 191 02-Oct-23 14-May-24 14-May-24, 4TH STA. 2+465.508-Sta2+725.508
BASE SLAB 109 02-Oct-23 05-Feb-24 05-Feb-24, BASE SLAB
CULV-DR-ST4-BS.610Lean concrete for Base slab 12 02-Oct-23 15-Oct-23 Lean concrete for Base slab

CULV-DR-ST4-BS.615Waterproofing for Lean concrete 17 16-Oct-23 04-Nov-23 Waterproofing for Lean concrete

CULV-DR-ST4-BS.620Base slab Rebar installation 39 05-Nov-23 19-Dec-23 Base slab Rebar installation

CULV-DR-ST4-BS.625Base slab formwork Installation 25 20-Dec-23 17-Jan-24 Base slab formwork Installation

CULV-DR-ST4-BS.630Base slab concrete casting 8 18-Jan-24 27-Jan-24 Base slab concrete casting

CULV-DR-ST4-BS.635Base Slab Formwork Removel, Curing & Strength Gaining 8 28-Jan-24 05-Feb-24 Base Slab Formwork Removel, Curing & Strength Gaining

CULVERT WALL 79 20-Dec-23 20-Mar-24 20-Mar-24, CULVERT WALL


CULV-DR-ST4-CW.525Culvert Wall Rebar installation 33 20-Dec-23 27-Jan-24 Culvert Wall Rebar installation

CULV-DR-ST4-CW.530Culvert Wall Formwork Installation 19 28-Jan-24 18-Feb-24 Culvert Wall Formwork Installation

CULV-DR-ST4-CW.535Culvert Wall concrete casting 8 19-Feb-24 27-Feb-24 Culvert Wall concrete casting

CULV-DR-ST4-CW.540Culvert Walls Formwork Removel and Curing 8 28-Feb-24 07-Mar-24 Culvert Walls Formwork Removel and Curing

CULV-DR-ST4-CW.545Waterproofing for Culvert wall 11 09-Mar-24 20-Mar-24 Waterproofing for Culvert wall

TOP SLAB 68 19-Feb-24 11-May-24 11-May-24, TOP SLAB


CULV-DR-ST4-TS.610Top Slab Scaffold and Bottom Formwork installation 21 19-Feb-24 13-Mar-24 Top Slab Scaffold and Bottom Formwork installation

CULV-DR-ST4-TS.615Top slab Rebar installation 13 14-Mar-24 28-Mar-24 Top slab Rebar installation

CULV-DR-ST4-TS.620Top slab Vertical formwork installation 8 30-Mar-24 07-Apr-24 Top slab Vertical formwork installation

CULV-DR-ST4-TS.625Top slab concrete casting 8 08-Apr-24 20-Apr-24 Top slab concrete casting

CULV-DR-ST4-TS.630Top Slab Formwork Removel and Curing 7 21-Apr-24 28-Apr-24 Top Slab Formwork Removel and Curing

CULV-DR-ST4-TS.635Waterproofing of Top slab 11 29-Apr-24 11-May-24 Waterproofing of Top slab

PLAIN CONCRETE 6 29-Apr-24 05-May-24 05-May-24, PLAIN CONCRETE


CULV-DR-ST4-PC.270Plain concrete formwork installation 4 29-Apr-24 02-May-24 Plain concrete formwork installation

CULV-DR-ST4-PC.275Plain concrete 2 04-May-24 05-May-24 Plain concrete

FINISHING 8 06-May-24 14-May-24 14-May-24, FINISHING


CULV-DR-ST4-FN.185Concrete Protective coating 8 06-May-24 14-May-24 Concrete Protective coating

BACKFILLING UPTO TUNNELWALL 187 02-Nov-23 10-Jun-24 10-Jun-24, BACKFILLING UPTO TUNNEL WALL
JAH-Z6-CON-BF.235 Backfilling & Compaction @ 2+157 ~ 2+257 22 02-Nov-23 27-Nov-23 Backfilling & Compaction @ 2+157 ~ 2+257

JAH-Z6-CON-BF.240 Backfilling & Compaction @2+257 ~ 2+357 30 03-Feb-24 07-Mar-24 Backfilling & Compaction @2+257 ~ 2+357

JAH-Z6-CON-BF.245 Backfilling & Compaction @ 2+357 ~ 2+457 18 16-May-24 05-Jun-24 Backfilling & Compaction @ 2+357 ~ 2+457

JAH-Z6-CON-BF.250 Backfilling & Compaction @ 2+457 ~ 2+518 15 25-May-24 10-Jun-24 Backfilling & Compaction @ 2+457 ~ 2+518

STRUCTURAL FILL 157 23-Apr-24 28-Oct-24 28-Oct-24, STRUCTURAL FILL

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
410 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-SF-IL.100 Backfilling & Compaction at Invert Level @ 2+157 ~ 2+257 22 27-Aug-24 22-Sep-24 Backfilling & Compaction at Invert Level @ 2+157 ~ 2+257

JAH-Z6-SF-IL.105 Backfilling & Compaction at Invert Level @2+257 ~ 2+357 30 22-Sep-24 28-Oct-24 Backfilling & Compaction at Invert Level @2+257 ~ 2+357

JAH-Z6-SF-IL.110 Backfilling & Compaction at Invert Level @ 2+357 ~ 2+457 26 23-Apr-24 22-May-24 Backfilling & Compaction at Invert Level @ 2+357 ~ 2+457

JAH-Z6-SF-IL.115 Backfilling & Compaction at Invert Level @ 2+457 ~ 2+518 23 28-May-24 27-Jun-24 Backfilling & Compaction at Invert Level @ 2+457 ~ 2+518

WET & DRY UTILITIES 336 15-May-24 24-Jun-25 24-Jun-25, WET & DRY UTILITIES
INSIDE WET CULVERT 336 15-May-24 24-Jun-25 24-Jun-25, INSIDE WET CULVERT
POTABLE WATER NETWORK 66 15-May-24 04-Aug-24 04-Aug-24, POTABLE WATER NETWORK
JAH-Z6-WU-PWN.100 Pipe Supports Installation 30 15-May-24 23-Jun-24 Pipe Supports Installation

JAH-Z6-WU-PWN.105 Pipe Installation alongwith Valves, Fittings & Accessories 30 24-Jun-24 28-Jul-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-PWN.110 Testing 6 29-Jul-24 04-Aug-24 Testing

GREY WATER DISTRIBUTION SYSTEM 66 05-Aug-24 21-Oct-24 21-Oct-24, GREY WATER DISTRIBUTION SYSTEM
JAH-Z6-WU-GWD.285 Pipe Supports Installation 30 05-Aug-24 08-Sep-24 Pipe Supports Installation

JAH-Z6-WU-GWD.290 Pipe Installation alongwith Valves, Fittings & Accessories 30 09-Sep-24 14-Oct-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-GWD.295 Testing 6 15-Oct-24 21-Oct-24 Testing

IRRIGATION NETWORK 66 22-Oct-24 06-Jan-25 06-Jan-25, IRRIGATION NETWORK


JAH-Z6-WU-IS.635 Pipe Supports Installation 30 22-Oct-24 25-Nov-24 Pipe Supports Installation

JAH-Z6-WU-IS.640 Pipe Installation alongwith Valves, Fittings & Accessories 30 26-Nov-24 30-Dec-24 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-IS.645 Testing 6 31-Dec-24 06-Jan-25 Testing

CHILLED WATER SUPPLY NETWORK 66 07-Jan-25 24-Mar-25 24-Mar-25, CHILLED WATER SUPPLY NETWORK
JAH-Z6-WU-CWS.175 Pipe Supports Installation 30 07-Jan-25 10-Feb-25 Pipe Supports Installation

JAH-Z6-WU-CWS.180 Pipe Installation alongwith Valves, Fittings & Accessories 30 11-Feb-25 17-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-CWS.185 Testing 6 18-Mar-25 24-Mar-25 Testing

CHILLED WATER RETURN NETWORK 78 31-Dec-24 05-Apr-25 05-Apr-25, CHILLED WATER RETURN NETWORK
JAH-Z6-WU-CWR.175 Pipe Supports Installation 30 31-Dec-24 03-Feb-25 Pipe Supports Installation

JAH-Z6-WU-CWR.180 Pipe Installation alongwith Valves, Fittings & Accessories 30 04-Feb-25 10-Mar-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-CWR.185 Testing 6 25-Mar-25 05-Apr-25 Testing

AUTOMATIC WASTE COLLECTION NETWORK 66 06-Apr-25 24-Jun-25 24-Jun-25, AUTOMATIC WASTE COLLECTION NETWORK
JAH-Z6-WU-AWC.175 Pipe Supports Installation 30 06-Apr-25 10-May-25 Pipe Supports Installation

JAH-Z6-WU-AWC.180 Pipe Installation alongwith Valves, Fittings & Accessories 30 11-May-25 17-Jun-25 Pipe Installation alongwith Valves, Fittings & Accessories

JAH-Z6-WU-AWC.185 Testing 6 18-Jun-25 24-Jun-25 Testing

INSIDE DRY CULVERT 330 15-May-24 17-Jun-25 17-Jun-25, INSIDE DRY CULVERT
POWER 270 15-May-24 05-Apr-25 05-Apr-25, POWER
HIGH VOLTAGE 110 KV NETWORK 40 15-May-24 04-Jul-24 04-Jul-24, HIGH VOLTAGE 110 KV NETWORK
JAH-Z6-IDC-PO-HV.150
HV Cable Supports Installation 15 15-May-24 01-Jun-24 HV Cable Supports Installation

JAH-Z6-IDC-PO-HV.155
Cable Installation with Fittings & Accessories 25 02-Jun-24 04-Jul-24 Cable Installation with Fittings & Accessories

MEDIUM VOLTAGE 13.8 KV NETWORK 40 06-Jul-24 20-Aug-24 20-Aug-24, MEDIUM VOLTAGE 13.8 KV NETWORK
JAH-Z6-IDC-PO-MV.150
HV Cable Supports Installation 15 06-Jul-24 22-Jul-24 HV Cable Supports Installation

JAH-Z6-IDC-PO-MV.155
Cables Installation with Fittings & Accessories 25 23-Jul-24 20-Aug-24 Cables Installation with Fittings & Accessories

LOW VOLTAGE NETWORK 35 21-Aug-24 01-Oct-24 01-Oct-24, LOW VOLTAGE NETWORK


JAH-Z6-IDC-PO-LV.150
HV Cable Supports Installation 15 21-Aug-24 07-Sep-24 HV Cable Supports Installation

JAH-Z6-IDC-PO-LV.155
Cable Laying with Fittings & Accessories 20 08-Sep-24 01-Oct-24 Cable Laying with Fittings & Accessories

ELECTRICAL DISTRIBUTION SYSTEM 120 02-Oct-24 18-Feb-25 18-Feb-25, ELECTRICAL DISTRIBUTION SYSTEM
JAH-Z6-IDC-PO-DS.300
Cable Tray Installation 10 02-Oct-24 13-Oct-24 Cable Tray Installation

JAH-Z6-IDC-PO-DS.305
PVC Ducts Installation 10 14-Oct-24 24-Oct-24 PVC Ducts Installation

JAH-Z6-IDC-PO-DS.310
Cable Installation 25 26-Oct-24 23-Nov-24 Cable Installation

JAH-Z6-IDC-PO-DS.315
Isolators Installation 15 24-Nov-24 10-Dec-24 Isolators Installation

JAH-Z6-IDC-PO-DS.320
Sub Main Distribution Boards Installation 15 11-Dec-24 28-Dec-24 Sub Main Distribution Boards Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
411 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-IDC-PO-DS.325
Motor Control Centres Installation 15 29-Dec-24 14-Jan-25 Motor Control Centres Installation

JAH-Z6-IDC-PO-DS.330
Distribution Boards Installation 15 15-Jan-25 01-Feb-25 Distribution Boards Installation

JAH-Z6-IDC-PO-DS.335
Wiring Accessories Installation 15 02-Feb-25 18-Feb-25 Wiring Accessories Installation

LIGHTING SYSTEM 35 19-Feb-25 05-Apr-25 05-Apr-25, LIGHTING SYSTEM


JAH-Z6--DU-LS.310 Luminaires Installation 10 20-Mar-25 05-Apr-25 Luminaires Installation

JAH-Z6--DU-LS.315 Cables Installation 10 19-Feb-25 02-Mar-25 Cables Installation

JAH-Z6-DU-LS.285 Light Point Installation 15 03-Mar-25 19-Mar-25 Light Point Installation

TELECOM SERVICES 60 06-Apr-25 17-Jun-25 17-Jun-25, TELECOM SERVICES


JAH-Z6-DU-TES.175 Mobily Lines 20 06-Apr-25 28-Apr-25 Mobily Lines

JAH-Z6-DU-TES.180 STC Line 20 22-May-25 17-Jun-25 STC Line

JAH-Z6-DU-TES.185 MOI Line 20 29-Apr-25 21-May-25 MOI Line

MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS 203 26-Nov-24 28-Jul-25 28-Jul-25, MEP VEHICULAR TUNNEL/ DRY & WET CULVERTS
TUNNEL MECHANICAL WORKS 160 26-Nov-24 04-Jun-25 04-Jun-25, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 56 26-Nov-24 29-Jan-25 29-Jan-25, FIRE FIGHTING SYSTEM
JAH-Z6-MECH-FF.100 Pipe Installation work 20 26-Nov-24 18-Dec-24 Pipe Installation work

JAH-Z6-MECH-FF.105 Valves and Accessories Installation 8 19-Dec-24 28-Dec-24 Valves and Accessories Installation

JAH-Z6-MECH-FF.110 Sprinklers Installation 5 29-Dec-24 02-Jan-25 Sprinklers Installation

JAH-Z6-MECH-FF.115 Fire Extinguishers Installation 8 04-Jan-25 12-Jan-25 Fire Extinguishers Installation

JAH-Z6-MECH-FF.120 Foam Tank Installation 6 13-Jan-25 19-Jan-25 Foam Tank Installation

JAH-Z6-MECH-FF.125 Pipe Painting work 6 20-Jan-25 26-Jan-25 Pipe Painting work

JAH-Z6-MECH-FF.130 Testing work 3 27-Jan-25 29-Jan-25 Testing work

VENTILATION SYSTEM 23 30-Jan-25 25-Feb-25 25-Feb-25, VENTILATION SYSTEM


JAH-Z6-MECH-VS100 Staircase Pressurisation Fan Installation 5 30-Jan-25 04-Feb-25 Staircase Pressurisation Fan Installation

JAH-Z6-MECH-VS105 Extract fan installation 5 05-Feb-25 10-Feb-25 Extract fan installation

JAH-Z6-MECH-VS110 Unidirectional Jet fan 5 11-Feb-25 16-Feb-25 Unidirectional Jet fan

JAH-Z6-MECH-VS115 Reverse Jet fan 5 17-Feb-25 22-Feb-25 Reverse Jet fan

JAH-Z6-MECH-VS120 Testing work 3 23-Feb-25 25-Feb-25 Testing work

PUMPS INSTALLATION 15 26-Feb-25 15-Mar-25 15-Mar-25, PUMPS INSTALLATION


JAH-Z6-MECH-PI.325 Sump Pump Installation 7 26-Feb-25 05-Mar-25 Sump Pump Installation

JAH-Z6-MECH-PI.330 Pipe Connection work 6 06-Mar-25 12-Mar-25 Pipe Connection work

JAH-Z6-MECH-PI.335 Testing work 2 13-Mar-25 15-Mar-25 Testing work

DUCTING SYSTEM 66 16-Mar-25 04-Jun-25 04-Jun-25, DUCTING SYSTEM


JAH-Z6-MECH-DS.625Duct Installation work 28 16-Mar-25 21-Apr-25 Duct Installation work

JAH-Z6-MECH-DS.630Grills Installation work 7 22-Apr-25 29-Apr-25 Grills Installation work

JAH-Z6-MECH-DS.635Diffusers Installation work 7 30-Apr-25 07-May-25 Diffusers Installation work

JAH-Z6-MECH-DS.640Non Returns Dampers 7 08-May-25 15-May-25 Non Returns Dampers

JAH-Z6-MECH-DS.645Fire and Smoke Damper 7 17-May-25 24-May-25 Fire and Smoke Damper

JAH-Z6-MECH-DS.650Sand Trap Louvre 5 25-May-25 29-May-25 Sand Trap Louvre

JAH-Z6-MECH-DS.655Testing work 5 31-May-25 04-Jun-25 Testing work

TUNNEL ELECTRICAL WORKS 203 26-Nov-24 28-Jul-25 28-Jul-25, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 101 19-Dec-24 20-Apr-25 20-Apr-25, CABLE TRAYS
JAH-Z6-ELC-CT1000 600mm Cable Tray 21 19-Dec-24 12-Jan-25 600mm Cable Tray

JAH-Z6-ELC-CT1005 400mm Cable Tray 14 13-Jan-25 28-Jan-25 400mm Cable Tray

JAH-Z6-ELC-CT1010 300mm Cable Tray 10 29-Jan-25 09-Feb-25 300mm Cable Tray

JAH-Z6-ELC-CT1015 200mm Cable Tray 8 10-Feb-25 18-Feb-25 200mm Cable Tray

JAH-Z6-ELC-CT1020 150mm Cable Tray 8 19-Feb-25 27-Feb-25 150mm Cable Tray

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
412 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-ELC-CT1025 100mm Cable Tray 6 01-Mar-25 06-Mar-25 100mm Cable Tray

JAH-Z6-ELC-CT1030 75mm Cable Tray 5 08-Mar-25 12-Mar-25 75mm Cable Tray

JAH-Z6-ELC-CT1035 150mm x 100mm Trunking 7 13-Mar-25 20-Mar-25 150mm x 100mm Trunking

JAH-Z6-ELC-CT1040 100mm x 100mm Trunking 6 22-Mar-25 27-Mar-25 100mm x 100mm Trunking

JAH-Z6-ELC-CT1045 100mm x 75mm Trunking 7 29-Mar-25 09-Apr-25 100mm x 75mm Trunking

JAH-Z6-ELC-CT1050 PVC Ducts150mm dia 5 10-Apr-25 15-Apr-25 PVC Ducts150mm dia

JAH-Z6-ELC-CT1055 PVC Ducts100mm dia 4 16-Apr-25 20-Apr-25 PVC Ducts100mm dia

POWER CABLES 162 13-Jan-25 28-Jul-25 28-Jul-25, POWER CABLES


JAH-Z6-ELC-PC1525 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC 12 13-Jan-25 26-Jan-25 Cable Laying 4C x 300mm2 + 2 nos 1C x 150mm2 ECC

JAH-Z6-ELC-PC1530 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC 22 13-Jan-25 06-Feb-25 Cable Laying 4C x 300mm2 + 1C x 150mm2 ECC

JAH-Z6-ELC-PC1535 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC 20 13-Jan-25 04-Feb-25 Cable Laying 4C x 240mm2 + 1C x 120mm2 ECC

JAH-Z6-ELC-PC1540 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC 28 05-Feb-25 09-Mar-25 Cable Laying 4C x 185mm2 + 1C x 95mm2 ECC

JAH-Z6-ELC-PC1545 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC 14 22-Feb-25 09-Mar-25 Cable Laying 4C x 150mm2 + 1C x 70mm2 ECC

JAH-Z6-ELC-PC1550 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC 13 23-Feb-25 09-Mar-25 Cable Laying 4C x 120mm2 + 1C x 70mm2 ECC

JAH-Z6-ELC-PC1555 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC 20 15-Feb-25 09-Mar-25 Cable Laying 4C x 95mm2 + 1C x 50mm2 ECC

JAH-Z6-ELC-PC1560 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC 16 19-Feb-25 09-Mar-25 Cable Laying 4C x 70mm2 + 1C x 35mm2 ECC

JAH-Z6-ELC-PC1565 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC 16 19-Feb-25 09-Mar-25 Cable Laying 4C x 50mm2 + 1C x 25mm2 ECC

JAH-Z6-ELC-PC1570 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC 11 10-Mar-25 22-Mar-25 Cable Laying 4C x 35mm2 + 1C x 16mm2 ECC

JAH-Z6-ELC-PC1575 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC 10 11-Mar-25 22-Mar-25 Cable Laying 4C x 25mm2 + 1C x 16mm2 ECC

JAH-Z6-ELC-PC1580 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC 7 23-Mar-25 03-Apr-25 Cable Laying 4C x 16mm2 + 1C x 16mm2 ECC

JAH-Z6-ELC-PC1585 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC 27 21-Apr-25 21-May-25 Cable Laying 4C x 10mm2 + 1C x 10mm2 ECC

JAH-Z6-ELC-PC1590 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC 28 21-Apr-25 22-May-25 Cable Laying 4C x 6mm2 + 1C x 6mm2 ECC

JAH-Z6-ELC-PC1595 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC 7 24-May-25 31-May-25 Cable Laying 2C x 16mm2 + 1C x 16mm2 ECC

JAH-Z6-ELC-PC1600 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC 7 01-Jun-25 11-Jun-25 Cable Laying 2C x 10mm2 + 1C x 10mm2 ECC

JAH-Z6-ELC-PC1605 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC 26 01-Jun-25 03-Jul-25 Cable Laying 2C x 6mm2 + 1C x 6mm2 ECC

JAH-Z6-ELC-PC1610 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC 40 01-Jun-25 20-Jul-25 Cable Laying 2C x 4mm2 + 1C x 4mm2 ECC

JAH-Z6-ELC-PC1615 Testing work 7 21-Jul-25 28-Jul-25 Testing work

ELECTRICAL INSTALLATIONS 86 23-Mar-25 08-Jul-25 08-Jul-25, ELECTRICAL INSTALLATIONS


JAH-Z6-ELC-INS700 Wiring Accessories 15 22-Apr-25 08-May-25 Wiring Accessories

JAH-Z6-ELC-INS705 Lighting Installation 14 10-May-25 25-May-25 Lighting Installation

JAH-Z6-ELC-INS710 Isolators Installation 12 26-May-25 11-Jun-25 Isolators Installation

JAH-Z6-ELC-INS715 Circuit Wiring Installation 22 23-Mar-25 21-Apr-25 Circuit Wiring Installation

JAH-Z6-ELC-INS720 SMDB Installation 5 12-Jun-25 17-Jun-25 SMDB Installation

JAH-Z6-ELC-INS725 Motor Control Centres Installation 5 18-Jun-25 23-Jun-25 Motor Control Centres Installation

JAH-Z6-ELC-INS730 Distribution Boards 6 24-Jun-25 30-Jun-25 Distribution Boards

JAH-Z6-ELC-INS735 Testing work 7 01-Jul-25 08-Jul-25 Testing work

LOW CURRENT 180 26-Nov-24 01-Jul-25 01-Jul-25, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 82 26-Nov-24 01-Mar-25 01-Mar-25, FIRE DETECTION AND ALARM SYSTEM
JAH-Z6-LOW-FDT1000Fire Alarm Control Panel Installation 6 10-Dec-24 16-Dec-24 Fire Alarm Control Panel Installation

JAH-Z6-LOW-FDT1005Tamper switch Installation 5 17-Dec-24 22-Dec-24 Tamper switch Installation

JAH-Z6-LOW-FDT1010Zone Input units Installation 5 23-Dec-24 28-Dec-24 Zone Input units Installation

JAH-Z6-LOW-FDT1015Fire Alarm sounder Installation 4 29-Dec-24 01-Jan-25 Fire Alarm sounder Installation

JAH-Z6-LOW-FDT1020Fire Alarm Speaker Installation 8 02-Jan-25 11-Jan-25 Fire Alarm Speaker Installation

JAH-Z6-LOW-FDT1025Smoke Detector Installation 8 12-Jan-25 20-Jan-25 Smoke Detector Installation

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
413 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-LOW-FDT1030Heat Detector Installation 8 21-Jan-25 29-Jan-25 Heat Detector Installation

JAH-Z6-LOW-FDT1035Interface Module Installation 8 30-Jan-25 08-Feb-25 Interface Module Installation

JAH-Z6-LOW-FDT1040Fibre-optic Sensing Cable Laying 12 26-Nov-24 09-Dec-24 Fibre-optic Sensing Cable Laying

JAH-Z6-LOW-FDT1045Double Action Manual Call Point Installation 7 09-Feb-25 16-Feb-25 Double Action Manual Call Point Installation

JAH-Z6-LOW-FDT1050Flashing Beacon Installation 6 17-Feb-25 23-Feb-25 Flashing Beacon Installation

JAH-Z6-LOW-FDT1055Testing work 5 24-Feb-25 01-Mar-25 Testing work

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 28 10-Dec-24 11-Jan-25 11-Jan-25, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
JAH-Z6-LOW-PH400 8 core UTP Cable Laying 7 10-Dec-24 17-Dec-24 8 core UTP Cable Laying

JAH-Z6-LOW-PH405 Junction box Installation 7 18-Dec-24 25-Dec-24 Junction box Installation

JAH-Z6-LOW-PH410 Emergency Telephone Installation 7 26-Dec-24 02-Jan-25 Emergency Telephone Installation

JAH-Z6-LOW-PH415 Connection and Testing 7 04-Jan-25 11-Jan-25 Connection and Testing

PUBLIC ADDRESS 28 12-Jan-25 12-Feb-25 12-Feb-25, PUBLIC ADDRESS


JAH-Z6-LOW-PA400 Wall-mounted Voice Evacuation Horn Speaker Installation 7 20-Jan-25 27-Jan-25 Wall-mounted Voice Evacuation Horn Speaker Installation

JAH-Z6-LOW-PA405 Voice alarm control panel Installation 7 28-Jan-25 04-Feb-25 Voice alarm control panel Installation

JAH-Z6-LOW-PA410 Cables laying public address system 7 12-Jan-25 19-Jan-25 Cables laying public address system

JAH-Z6-LOW-PA415 Connection and Testing 7 05-Feb-25 12-Feb-25 Connection and Testing

VIDEO SURVEILLANCE 49 13-Feb-25 15-Apr-25 15-Apr-25, VIDEO SURVEILLANCE


JAH-Z6-LOW-VDS625Single Core Fibre Optical Cable Laying 7 13-Feb-25 20-Feb-25 Single Core Fibre Optical Cable Laying

JAH-Z6-LOW-VDS630RTU Panel Installation 7 22-Feb-25 01-Mar-25 RTU Panel Installation

JAH-Z6-LOW-VDS635Overhead Vehicle Detector Installation 7 02-Mar-25 09-Mar-25 Overhead Vehicle Detector Installation

JAH-Z6-LOW-VDS640Door Contact Installation 7 10-Mar-25 17-Mar-25 Door Contact Installation

JAH-Z6-LOW-VDS645PTZ Camera mounted on Pole Installation 7 18-Mar-25 25-Mar-25 PTZ Camera mounted on Pole Installation

JAH-Z6-LOW-VDS650Fixed (AID) Camera Installation 7 26-Mar-25 07-Apr-25 Fixed (AID) Camera Installation

JAH-Z6-LOW-VDS655Testing work 7 08-Apr-25 15-Apr-25 Testing work

SACADA SYSTEM 35 16-Apr-25 26-May-25 26-May-25, SACADA SYSTEM


JAH-Z6-LOW-SCA475Cabling Laying 7 16-Apr-25 23-Apr-25 Cabling Laying

JAH-Z6-LOW-SCA480Remote Terminal Unit Installation 7 24-Apr-25 01-May-25 Remote Terminal Unit Installation

JAH-Z6-LOW-SCA485Programmable Logic Control Unit Installation 7 03-May-25 10-May-25 Programmable Logic Control Unit Installation

JAH-Z6-LOW-SCA490SCADA/ PC/ Soft ware/ Printers Installation 7 11-May-25 18-May-25 SCADA/ PC/ Soft ware/ Printers Installation

JAH-Z6-LOW-SCA495Testing work 7 19-May-25 26-May-25 Testing work

RADIO RE-BROADCASTING SYSTEM 28 27-May-25 01-Jul-25 01-Jul-25, RADIO RE-BROADCASTING SYSTEM


JAH-Z6-LOW-RDO400Leaky Feeder Cable Laying 7 27-May-25 03-Jun-25 Leaky Feeder Cable Laying

JAH-Z6-LOW-RDO405Inline Bidirectional Signal Amplifier Installation 7 04-Jun-25 15-Jun-25 Inline Bidirectional Signal Amplifier Installation

JAH-Z6-LOW-RDO410End of Line Terminator 7 16-Jun-25 23-Jun-25 End of Line Terminator

JAH-Z6-LOW-RDO415Connection and Testing 7 24-Jun-25 01-Jul-25 Connection and Testing

TUNNEL PLUMBING WORKS 35 22-Apr-25 01-Jun-25 01-Jun-25, TUNNEL PLUMBING WORKS


DRAINAGE SYSTEM 35 22-Apr-25 01-Jun-25 01-Jun-25, DRAINAGE SYSTEM
JAH-Z6-PLB-DS130 Drainage Pipes Installation Incl. Fittings & Accessories 15 22-Apr-25 08-May-25 Drainage Pipes Installation Incl. Fittings & Accessories

JAH-Z6-PLB-DS135 Collection Chambers 20 10-May-25 01-Jun-25 Collection Chambers

TUNNEL INTERNAL ROAD WORK 42 02-Jun-25 23-Jul-25 23-Jul-25, TUNNEL INTERNAL ROAD WORK
JAH-Z6-TIRW.510 Kerbs, Channels & Edging 7 02-Jun-25 12-Jun-25 Kerbs, Channels & Edging

JAH-Z6-TIRW.515 Tack Coat Application (MC-1) 10 14-Jun-25 24-Jun-25 Tack Coat Application (MC-1)

JAH-Z6-TIRW.520 Bituminious Base Course Layer 10 14-Jun-25 24-Jun-25 Bituminious Base Course Layer

JAH-Z6-TIRW.525 Tack Coat Application (RC-2) 12 25-Jun-25 08-Jul-25 Tack Coat Application (RC-2)

JAH-Z6-TIRW.530 Asphalt Wearing Course Layer 12 25-Jun-25 08-Jul-25 Asphalt Wearing Course Layer

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
414 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
JAH-Z6-TIRW.535 Pavement Line Marking 5 09-Jul-25 14-Jul-25 Pavement Line Marking

JAH-Z6-TIRW.540 Traffic Signboards Installation 8 15-Jul-25 23-Jul-25 Traffic Signboards Installation

TUNNEL INTERNAL DECORATIVE WORKS 40 09-Jul-25 24-Aug-25 24-Aug-25, TUNNEL INTERNAL DECORATIVE WORKS
JAH-Z6-DW.150 Fire protection Board Installation 10 09-Jul-25 20-Jul-25 Fire protection Board Installation

JAH-Z6-DW.155 GRC Panel Board Installation 30 21-Jul-25 24-Aug-25 GRC Panel Board Installation

AIRPORT ROAD TUNNEL 970 25-Oct-22 A 15-Feb-26 15-Feb-26, AIRPORT ROAD TUNNEL
ZONE 7 - FROM STA. 0+040 ~ 0+389.63 970 25-Oct-22 A 15-Feb-26 15-Feb-26, ZONE 7 - FROM STA. 0+040 ~ 0+389.63
ENGINEERING 391 25-Oct-22 A 23-Mar-24 23-Mar-24, ENGINEERING
RAM170 Completion Engineering Work For Zone7 0 23-Mar-24* Completion Engineering Work For Zone7

SITE SURVEY 10 15-Dec-22 26-Dec-22 26-Dec-22, SITE SURVEY


JAH-Z7-EN-SS.160 Site Survey/Settingout Control Points 3 15-Dec-22 18-Dec-22 Site Survey/Settingout Control Points

JAH-Z7-EN-SS.165 Review and Approval of Site Survey & Control Points 7 19-Dec-22 26-Dec-22 Review and Approval of Site Survey & Control Points

SHOP DRAWINGS 140 25-Oct-22 A 31-Aug-23 31-Aug-23, SHOP DRAWINGS


CIVIL/STRUCTURAL CROSSING 42 07-May-23 24-Jun-23 24-Jun-23, CIVIL/STRUCTURAL CROSSING
JAH-Z7-ENG-CS.300 Plan and Profile Shop Drawings Preparation & Submission 6 07-May-23 13-May-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.305 Plan and Profile Shop Drawings Review & Approval 12 14-May-23 27-May-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z7-ENG-CS.310 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 28-May-23 03-Jun-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.315 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 04-Jun-23 17-Jun-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z7-ENG-CS.320 Tunnel Structural Shop Drawings Submission 6 04-Jun-23 10-Jun-23 Tunnel Structural Shop Drawings Submission

JAH-Z7-ENG-CS.325 Tunnel Structural Shop Drawings Review & Approval 12 11-Jun-23 24-Jun-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+40 ~0+140 102 26-Oct-22 A 13-Jul-23 13-Jul-23, CIVIL/STRUCTURAL 0+40 ~0+140
JAH-Z7-ENG-CS.350 Plan and Profile Shop Drawings Preparation & Submission 6 26-Oct-22 A 29-May-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.355 Plan and Profile Shop Drawings Review & Approval 12 30-May-23 12-Jun-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z7-ENG-CS.360 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 13-Jun-23 19-Jun-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.365 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 20-Jun-23 06-Jul-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z7-ENG-CS.370 Tunnel Structural Shop Drawings Submission 6 20-Jun-23 26-Jun-23 Tunnel Structural Shop Drawings Submission

JAH-Z7-ENG-CS.375 Tunnel Structural Shop Drawings Review & Approval 12 01-Jul-23 13-Jul-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+140 ~0+240 106 25-Oct-22 A 30-Jul-23 30-Jul-23, CIVIL/STRUCTURAL 0+140 ~0+240
JAH-Z7-ENG-CS.400 Plan and Profile Shop Drawings Preparation & Submission 6 25-Oct-22 A 14-Jun-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.405 Plan and Profile Shop Drawings Review & Approval 12 15-Jun-23 02-Jul-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z7-ENG-CS.410 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 03-Jul-23 09-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.415 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 10-Jul-23 23-Jul-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z7-ENG-CS.420 Tunnel Structural Shop Drawings Submission 6 10-Jul-23 16-Jul-23 Tunnel Structural Shop Drawings Submission

JAH-Z7-ENG-CS.425 Tunnel Structural Shop Drawings Review & Approval 12 17-Jul-23 30-Jul-23 Tunnel Structural Shop Drawings Review & Approval

CIVIL/STRUCTURAL 0+240 ~0+360 42 03-Jul-23 20-Aug-23 20-Aug-23, CIVIL/STRUCTURAL 0+240 ~0+360


JAH-Z7-ENG-CS.450 Plan and Profile Shop Drawings Preparation & Submission 6 03-Jul-23 09-Jul-23 Plan and Profile Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.455 Plan and Profile Shop Drawings Review & Approval 12 10-Jul-23 23-Jul-23 Plan and Profile Shop Drawings Review & Approval

JAH-Z7-ENG-CS.460 Concrete dimension and Cross Section Shop Drawings Preparation & Submission 6 24-Jul-23 30-Jul-23 Concrete dimension and Cross Section Shop Drawings Preparation & Submission

JAH-Z7-ENG-CS.465 Concrete dimension and Cross Section Shop Drawings Review & Approval 12 31-Jul-23 13-Aug-23 Concrete dimension and Cross Section Shop Drawings Review & Approval

JAH-Z7-ENG-CS.470 Tunnel Structural Shop Drawings Submission 6 31-Jul-23 06-Aug-23 Tunnel Structural Shop Drawings Submission

JAH-Z7-ENG-CS.475 Tunnel Structural Shop Drawings Review & Approval 12 07-Aug-23 20-Aug-23 Tunnel Structural Shop Drawings Review & Approval

ARCHITECTURAL 22 07-Aug-23 31-Aug-23 31-Aug-23, ARCHITECTURAL


JAH-Z7-ENG-AR.160 Tunnel Architectural Shop Drawings Preparation & Submission 10 07-Aug-23 17-Aug-23 Tunnel Architectural Shop Drawings Preparation & Submission

JAH-Z7-ENG-AR.165 Tunnel Architectural Shop Drawings Review & Approval 12 19-Aug-23 31-Aug-23 Tunnel Architectural Shop Drawings Review & Approval

UTILITIES 160 10-Jul-23 13-Jan-24 13-Jan-24, UTILITIES


WET UTILITIES 160 10-Jul-23 13-Jan-24 13-Jan-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 32 10-Jul-23 15-Aug-23 15-Aug-23, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
415 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AP-Z7-EN-WU-PWN.100
Shop Drawings Preparation & Submission 20 10-Jul-23 01-Aug-23 Shop Drawings Preparation & Submission

AP-Z7-EN-WU-PWN.105
Shop Drawings Review & Approval 12 02-Aug-23 15-Aug-23 Shop Drawings Review & Approval

GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS 32 16-Aug-23 21-Sep-23 21-Sep-23, GREY WATER DISTRIBUTION NETWORK BRANCH,HOUSE CONNECTION & TIE IN POINTS
AP-Z7-EN-WU-GW.100Shop Drawings Preparation & Submission 20 16-Aug-23 07-Sep-23 Shop Drawings Preparation & Submission

AP-Z7-EN-WU-GW.105Shop Drawings Review & Approval 12 09-Sep-23 21-Sep-23 Shop Drawings Review & Approval

IRR & FF NETWORK BRANCHES & TIE IN POINTS 32 24-Sep-23 30-Oct-23 30-Oct-23, IRR & FF NETWORK BRANCHES & TIE IN POINTS
AP-Z7-EN-WU-IRR.100Shop Drawings Preparation & Submission 20 24-Sep-23 16-Oct-23 Shop Drawings Preparation & Submission

AP-Z7-EN-WU-IRR.105Shop Drawings Review & Approval 12 17-Oct-23 30-Oct-23 Shop Drawings Review & Approval

CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES 32 31-Oct-23 06-Dec-23 06-Dec-23, CHILLED WATER SUPPLY & RETURN NETWORK BRANCHES AND BURIED LIMNES
AP-Z7-EN-WU-CWS.100
Shop Drawings Preparation & Submission 20 31-Oct-23 22-Nov-23 Shop Drawings Preparation & Submission

AP-Z7-EN-WU-CWS.105
Shop Drawings Review & Approval 12 23-Nov-23 06-Dec-23 Shop Drawings Review & Approval

AUTOMATIC WASTE COLLECTION NETWORK 32 07-Dec-23 13-Jan-24 13-Jan-24, AUTOMATIC WASTE COLLECTION NETWORK
AP-Z7-EN-WU-AUW.180
Shop Drawings Preparation & Submission 20 07-Dec-23 30-Dec-23 Shop Drawings Preparation & Submission

AP-Z7-EN-WU-AUW.185
Shop Drawings Review & Approval 12 31-Dec-23 13-Jan-24 Shop Drawings Review & Approval

DRY UTILITIES 128 16-Aug-23 13-Jan-24 13-Jan-24, DRY UTILITIES


POWER 96 16-Aug-23 06-Dec-23 06-Dec-23, POWER
HIGH VOLTAGE 110 KV NETWORK 32 16-Aug-23 21-Sep-23 21-Sep-23, HIGH VOLTAGE 110 KV NETWORK
AP-Z7-EN-DU-PWR.440
Shop Drawings Preparation & Submission 20 16-Aug-23 07-Sep-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-PWR.445
Shop Drawings Review & Approval 12 09-Sep-23 21-Sep-23 Shop Drawings Review & Approval

MEDIUM VOLTAGE 13.8 KV NETWORK 32 16-Aug-23 21-Sep-23 21-Sep-23, MEDIUM VOLTAGE 13.8 KV NETWORK
AP-Z7-EN-DU-PWR.450
Shop Drawings Preparation & Submission 20 16-Aug-23 07-Sep-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-PWR.455
Shop Drawings Review & Approval 12 09-Sep-23 21-Sep-23 Shop Drawings Review & Approval

LOW VOLTAGE NETWORK 32 16-Aug-23 21-Sep-23 21-Sep-23, LOW VOLTAGE NETWORK


AP-Z7-EN-DU-PWR.460
Shop Drawings Preparation & Submission 20 16-Aug-23 07-Sep-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-PWR.465
Shop Drawings Review & Approval 12 09-Sep-23 21-Sep-23 Shop Drawings Review & Approval

ELECTRICAL DISTRIBUTION SYSTEM 32 24-Sep-23 30-Oct-23 30-Oct-23, ELECTRICAL DISTRIBUTION SYSTEM


AP-Z7-EN-DU-PWR.470
Shop Drawings Preparation & Submission 20 24-Sep-23 16-Oct-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-PWR.475
Shop Drawings Review & Approval 12 17-Oct-23 30-Oct-23 Shop Drawings Review & Approval

LIGHTING SYSTEM 32 31-Oct-23 06-Dec-23 06-Dec-23, LIGHTING SYSTEM


AP-Z7-EN-DU-PWR.480
Shop Drawings Preparation & Submission 20 31-Oct-23 22-Nov-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-PWR.485
Shop Drawings Review & Approval 12 23-Nov-23 06-Dec-23 Shop Drawings Review & Approval

LOW CURRENT 32 07-Dec-23 13-Jan-24 13-Jan-24, LOW CURRENT


TELECOM SERVICES 32 07-Dec-23 13-Jan-24 13-Jan-24, TELECOM SERVICES
AP-Z7-EN-DU-LC.190Shop Drawings Preparation & Submission 20 07-Dec-23 30-Dec-23 Shop Drawings Preparation & Submission

AP-Z7-EN-DU-LC.195Shop Drawings Review & Approval 12 31-Dec-23 13-Jan-24 Shop Drawings Review & Approval

MEP 220 10-Jul-23 23-Mar-24 23-Mar-24, MEP


TUNNEL MECHANICAL WORKS 176 10-Jul-23 31-Jan-24 31-Jan-24, TUNNEL MECHANICAL WORKS
FIRE FIGHTING SYSTEM 88 10-Jul-23 21-Oct-23 21-Oct-23, FIRE FIGHTING SYSTEM
AP-Z7-EN-MP-FF.340 Fire Fighting Pipe Layout Plan Preparation & Submission 10 10-Jul-23 20-Jul-23 Fire Fighting Pipe Layout Plan Preparation & Submission

AP-Z7-EN-MP-FF.345 Fire Fighting Pipe Layout Plan Review & Approval 12 22-Jul-23 03-Aug-23 Fire Fighting Pipe Layout Plan Review & Approval

AP-Z7-EN-MP-FF.350 Fire Fighting Sprinkler Layout Plan Preparation & Submission 10 05-Aug-23 15-Aug-23 Fire Fighting Sprinkler Layout Plan Preparation & Submission

AP-Z7-EN-MP-FF.355 Fire Fighting Sprinkler Layout Plan Review & Approval 12 16-Aug-23 29-Aug-23 Fire Fighting Sprinkler Layout Plan Review & Approval

AP-Z7-EN-MP-FF.360 Foam Tank Installation Layout Preparation & Submission 10 30-Aug-23 10-Sep-23 Foam Tank Installation Layout Preparation & Submission

AP-Z7-EN-MP-FF.365 Foam Tank Installation Layout Review & Approval 12 11-Sep-23 25-Sep-23 Foam Tank Installation Layout Review & Approval

AP-Z7-EN-MP-FF.370 Fire Extinguishers Layout Plan Preparation & Submission 10 26-Sep-23 07-Oct-23 Fire Extinguishers Layout Plan Preparation & Submission

AP-Z7-EN-MP-FF.375 Fire Extinguishers Layout Plan Review & Approval 12 08-Oct-23 21-Oct-23 Fire Extinguishers Layout Plan Review & Approval

VENTILATION SYSTEM 44 08-Oct-23 27-Nov-23 27-Nov-23, VENTILATION SYSTEM


AP-Z7-EN-MP-VS.220 Fan Layout Preparation & Submission 10 08-Oct-23 18-Oct-23 Fan Layout Preparation & Submission

AP-Z7-EN-MP-VS.225 Fan Layout Review & Approval 12 19-Oct-23 01-Nov-23 Fan Layout Review & Approval

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
416 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AP-Z7-EN-MP-VS.230 Cable Route Shop Drawing Preparation & Submission 10 02-Nov-23 13-Nov-23 Cable Route Shop Drawing Preparation & Submission

AP-Z7-EN-MP-VS.235 Cable Route Shop Drawing Review & Approval 12 14-Nov-23 27-Nov-23 Cable Route Shop Drawing Review & Approval

PUMPS INSTALLATION 22 28-Nov-23 23-Dec-23 23-Dec-23, PUMPS INSTALLATION


AP-Z7-EN-MP-PI.160 Sump Pump Diagram Preparation & Submission 10 28-Nov-23 09-Dec-23 Sump Pump Diagram Preparation & Submission

AP-Z7-EN-MP-PI.165 Sump Pump Diagram Review & Approval 12 10-Dec-23 23-Dec-23 Sump Pump Diagram Review & Approval

DUCTING SYSTEM 88 22-Oct-23 31-Jan-24 31-Jan-24, DUCTING SYSTEM


AP-Z7-EN-MP-DCS.340Duct Layout Drawing Preparation & Submission 10 22-Oct-23 01-Nov-23 Duct Layout Drawing Preparation & Submission

AP-Z7-EN-MP-DCS.345Duct Layout Drawing Review & Approval 12 02-Nov-23 15-Nov-23 Duct Layout Drawing Review & Approval

AP-Z7-EN-MP-DCS.350Diffuser Details Review & Approval 12 28-Nov-23 11-Dec-23 Diffuser Details Review & Approval

AP-Z7-EN-MP-DCS.355Dampers Details Preparation & Submission 10 12-Dec-23 23-Dec-23 Dampers Details Preparation & Submission

AP-Z7-EN-MP-DCS.360Dampers Details Review & Approval 12 24-Dec-23 06-Jan-24 Dampers Details Review & Approval

AP-Z7-EN-MP-DCS.365Sand Trap Louvre Layout Drawing Preparation & Submission 10 07-Jan-24 17-Jan-24 Sand Trap Louvre Layout Drawing Preparation & Submission

AP-Z7-EN-MP-DCS.370Sand Trap Louvre Layout Drawing Review & Approval 12 18-Jan-24 31-Jan-24 Sand Trap Louvre Layout Drawing Review & Approval

AP-Z7-EN-MP-DCS.375Diffuser Details Drawing Preparation & Submission 10 16-Nov-23 27-Nov-23 Diffuser Details Drawing Preparation & Submission

TUNNEL ELECTRICAL WORKS 210 22-Jul-23 23-Mar-24 23-Mar-24, TUNNEL ELECTRICAL WORKS
CABLE TRAYS 110 22-Jul-23 27-Nov-23 27-Nov-23, CABLE TRAYS
AP-Z7-EN-EL-CTR.400 Cable Tray Layout Drawing Preparation & Submission 10 22-Jul-23 01-Aug-23 Cable Tray Layout Drawing Preparation & Submission

AP-Z7-EN-EL-CTR.405 Cable Tray Layout Drawing Review & Approval 12 02-Aug-23 15-Aug-23 Cable Tray Layout Drawing Review & Approval

AP-Z7-EN-EL-CTR.410 Cable Tray Diversion Details Preparation & Submission 10 16-Aug-23 27-Aug-23 Cable Tray Diversion Details Preparation & Submission

AP-Z7-EN-EL-CTR.415 Cable Tray Diversion Details Review & Approval 12 28-Aug-23 10-Sep-23 Cable Tray Diversion Details Review & Approval

AP-Z7-EN-EL-CTR.420 Cable Tray Fixing Details Preparation & Submission 10 11-Sep-23 21-Sep-23 Cable Tray Fixing Details Preparation & Submission

AP-Z7-EN-EL-CTR.425 Cable Tray Fixing Details Review & Submission 12 24-Sep-23 07-Oct-23 Cable Tray Fixing Details Review & Submission

AP-Z7-EN-EL-CTR.430 Cable Tray Sections Preparation & Submission 10 08-Oct-23 18-Oct-23 Cable Tray Sections Preparation & Submission

AP-Z7-EN-EL-CTR.435 Cable Tray Sections Review & Approval 12 19-Oct-23 01-Nov-23 Cable Tray Sections Review & Approval

AP-Z7-EN-EL-CTR.440 PVC DuctsSections Preparation & Submission 10 02-Nov-23 13-Nov-23 PVC DuctsSections Preparation & Submission

AP-Z7-EN-EL-CTR.445 PVC Sections Review & Approval 12 14-Nov-23 27-Nov-23 PVC Sections Review & Approval

POWER CABLES 44 24-Sep-23 13-Nov-23 13-Nov-23, POWER CABLES


AP-Z7-EN-EL-PC.220 Cable Route Shop Drawing Preparation & Submission 10 24-Sep-23 04-Oct-23 Cable Route Shop Drawing Preparation & Submission

AP-Z7-EN-EL-PC.225 Cable Route Shop Drawing Review & Approval 12 05-Oct-23 18-Oct-23 Cable Route Shop Drawing Review & Approval

AP-Z7-EN-EL-PC.230 Junction Box Layout Plan Preparation & Submission 10 19-Oct-23 30-Oct-23 Junction Box Layout Plan Preparation & Submission

AP-Z7-EN-EL-PC.235 Junction Box Layout Plan Review & Approval 12 31-Oct-23 13-Nov-23 Junction Box Layout Plan Review & Approval

ELECTRICAL INSTALLATIONS 110 05-Oct-23 10-Feb-24 10-Feb-24, ELECTRICAL INSTALLATIONS


AP-Z7-EN-EL-ELI.400 Wiring Accessories Diagram Preparation & Submission 10 05-Oct-23 16-Oct-23 Wiring Accessories Diagram Preparation & Submission

AP-Z7-EN-EL-ELI.405 Lighting Layout Drawing Preparation & Submission 10 31-Oct-23 11-Nov-23 Lighting Layout Drawing Preparation & Submission

AP-Z7-EN-EL-ELI.410 Circuit Wiring Diagram Preparation & Submission 10 26-Nov-23 06-Dec-23 Circuit Wiring Diagram Preparation & Submission

AP-Z7-EN-EL-ELI.415 Circuit Wiring Diagram Review & Approval 12 07-Dec-23 20-Dec-23 Circuit Wiring Diagram Review & Approval

AP-Z7-EN-EL-ELI.420 SMDB Line Diagram Preparation & Submission 10 21-Dec-23 01-Jan-24 SMDB Line Diagram Preparation & Submission

AP-Z7-EN-EL-ELI.425 SMDB Line Diagram Review & Approval 12 02-Jan-24 15-Jan-24 SMDB Line Diagram Review & Approval

AP-Z7-EN-EL-ELI.430 Distribution Board Line Diagram Preparation & Submission 10 16-Jan-24 27-Jan-24 Distribution Board Line Diagram Preparation & Submission

AP-Z7-EN-EL-ELI.435 Lighting Layout Drawing Review & Approval 12 12-Nov-23 25-Nov-23 Lighting Layout Drawing Review & Approval

AP-Z7-EN-EL-ELI.440 Wiring Accessories Diagram Review & Approval 12 17-Oct-23 30-Oct-23 Wiring Accessories Diagram Review & Approval

AP-Z7-EN-EL-ELI.445 Distribution Board Line Diagram Review & Approval 12 28-Jan-24 10-Feb-24 Distribution Board Line Diagram Review & Approval

LOW CURRENT 132 22-Oct-23 23-Mar-24 23-Mar-24, LOW CURRENT


FIRE DETECTION ANDALARM SYSTEM 132 22-Oct-23 23-Mar-24 23-Mar-24, FIRE DETECTION AND ALARM SYSTEM
AP-Z7-EN-LW-FD.460 Fire Alarm Control Panel Layout Drawing Preparation & Submission 10 22-Oct-23 01-Nov-23 Fire Alarm Control Panel Layout Drawing Preparation & Submission

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
417 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AP-Z7-EN-LW-FD.465 Fire Alarm Control Panel Layout Drawing Review & Approval 12 02-Nov-23 15-Nov-23 Fire Alarm Control Panel Layout Drawing Review & Approval

AP-Z7-EN-LW-FD.470 Fire Alarm Speaker Layout Drawing Preparation & Submission 10 16-Nov-23 27-Nov-23 Fire Alarm Speaker Layout Drawing Preparation & Submission

AP-Z7-EN-LW-FD.475 Fire Alarm Speaker Layout Drawing Review & Approval 12 28-Nov-23 11-Dec-23 Fire Alarm Speaker Layout Drawing Review & Approval

AP-Z7-EN-LW-FD.480 Fire Alarm sounder Layout Drawing Preparation & Submission 10 12-Dec-23 23-Dec-23 Fire Alarm sounder Layout Drawing Preparation & Submission

AP-Z7-EN-LW-FD.485 Fire Alarm sounder Layout Drawing Review & Approval 12 24-Dec-23 06-Jan-24 Fire Alarm sounder Layout Drawing Review & Approval

AP-Z7-EN-LW-FD.490 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission 10 07-Jan-24 17-Jan-24 Smoke Detector & Heat Detector Layout Drawing Preparation & Submission

AP-Z7-EN-LW-FD.495 Smoke Detector & Heat Detector Layout Drawing Review & Approval 12 18-Jan-24 31-Jan-24 Smoke Detector & Heat Detector Layout Drawing Review & Approval

AP-Z7-EN-LW-FD.500 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission 10 01-Feb-24 12-Feb-24 Fibre-optic Sensing Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-FD.505 Fibre-optic Sensing Cable Layout Drawing Review & Approval 12 13-Feb-24 26-Feb-24 Fibre-optic Sensing Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-FD.510 Double Action Manual Call Point Layout Drawing Preparation & Submission 10 27-Feb-24 09-Mar-24 Double Action Manual Call Point Layout Drawing Preparation & Submission

AP-Z7-EN-LW-FD.515 Double Action Manual Call Point Layout Drawing Review & Approval 12 10-Mar-24 23-Mar-24 Double Action Manual Call Point Layout Drawing Review & Approval

COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE 110 02-Nov-23 09-Mar-24 09-Mar-24, COMMUNICATION SYSTEM/ EMERGENCY TELEPHONE
AP-Z7-EN-LW-TPH.4008 core UTP Cable Laying 14 02-Nov-23 18-Nov-23 8 core UTP Cable Laying

AP-Z7-EN-LW-TPH.405Junction box Installation 8 19-Nov-23 27-Nov-23 Junction box Installation

AP-Z7-EN-LW-TPH.410Emergency Telephone Installation 14 28-Nov-23 13-Dec-23 Emergency Telephone Installation

AP-Z7-EN-LW-TPH.415Connection and Testing 8 14-Dec-23 23-Dec-23 Connection and Testing

AP-Z7-EN-LW-TPH.4208 Core UTP Cable Layout Drawing Preparation & Submission 10 24-Dec-23 03-Jan-24 8 Core UTP Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-TPH.4258 Core UTP Cable Layout Drawing Review & Approval 12 04-Jan-24 17-Jan-24 8 Core UTP Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-TPH.430Junction box Layout Drawing Preparation & Submission 10 18-Jan-24 29-Jan-24 Junction box Layout Drawing Preparation & Submission

AP-Z7-EN-LW-TPH.435Junction box Layout Drawing Review & Approval 12 30-Jan-24 12-Feb-24 Junction box Layout Drawing Review & Approval

AP-Z7-EN-LW-TPH.440Telephone Location Layout Preparation & Submission 10 13-Feb-24 24-Feb-24 Telephone Location Layout Preparation & Submission

AP-Z7-EN-LW-TPH.445Telephone Location Layout Review & Approval 12 25-Feb-24 09-Mar-24 Telephone Location Layout Review & Approval

PUBLIC ADDRESS 66 19-Nov-23 03-Feb-24 03-Feb-24, PUBLIC ADDRESS


AP-Z7-EN-LW-PUBA.280
Cable Layout Drawing Preparation & Submission 10 19-Nov-23 29-Nov-23 Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-PUBA.285
Cable Layout Drawing Review & Approval 12 30-Nov-23 13-Dec-23 Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-PUBA.290
Voice alarm control panel Drawing Preparation & Submission 10 14-Dec-23 25-Dec-23 Voice alarm control panel Drawing Preparation & Submission

AP-Z7-EN-LW-PUBA.295
Voice alarm control panel Drawing Review & Approval 12 26-Dec-23 08-Jan-24 Voice alarm control panel Drawing Review & Approval

AP-Z7-EN-LW-PUBA.300
Voice Evacuation Horn Speaker Drawing Preparation & Submission 10 09-Jan-24 20-Jan-24 Voice Evacuation Horn Speaker Drawing Preparation & Submission

AP-Z7-EN-LW-PUBA.305
Voice Evacuation Horn Speaker Drawing Preparation & Submission 12 21-Jan-24 03-Feb-24 Voice Evacuation Horn Speaker Drawing Preparation & Submission

VIDEO SURVEILLANCE 44 30-Nov-23 20-Jan-24 20-Jan-24, VIDEO SURVEILLANCE


AP-Z7-EN-LW-VID.220Cable Layout Drawing Preparation & Submission 10 30-Nov-23 11-Dec-23 Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-VID.225Cable Layout Drawing Review & Approval 12 12-Dec-23 25-Dec-23 Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-VID.230Camera Layout Drawing Preparation & Submission 10 26-Dec-23 06-Jan-24 Camera Layout Drawing Preparation & Submission

AP-Z7-EN-LW-VID.235Camera Layout Drawing Review & Approval 12 07-Jan-24 20-Jan-24 Camera Layout Drawing Review & Approval

SACADA SYSTEM 44 12-Dec-23 31-Jan-24 31-Jan-24, SACADA SYSTEM


AP-Z7-EN-LW-SCA.220Cable Layout Drawing Preparation & Submission 10 12-Dec-23 23-Dec-23 Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-SCA.225Cable Layout Drawing Review & Approval 12 24-Dec-23 06-Jan-24 Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-SCA.230Installation Layout Drawing Preparation & Submission 10 07-Jan-24 17-Jan-24 Installation Layout Drawing Preparation & Submission

AP-Z7-EN-LW-SCA.235Installation Layout Drawing Review & Approval 12 18-Jan-24 31-Jan-24 Installation Layout Drawing Review & Approval

RADIO RE-BROADCASTING SYSTEM 44 24-Dec-23 12-Feb-24 12-Feb-24, RADIO RE-BROADCASTING SYSTEM


AP-Z7-EN-LW-RDO.220
Cable Layout Drawing Preparation & Submission 10 24-Dec-23 03-Jan-24 Cable Layout Drawing Preparation & Submission

AP-Z7-EN-LW-RDO.225
Cable Layout Drawing Review & Approval 12 04-Jan-24 17-Jan-24 Cable Layout Drawing Review & Approval

AP-Z7-EN-LW-RDO.230
Installation Layout Drawing Preparation & Submission 10 18-Jan-24 29-Jan-24 Installation Layout Drawing Preparation & Submission

AP-Z7-EN-LW-RDO.235
Installation Layout Drawing Review & Approval 12 30-Jan-24 12-Feb-24 Installation Layout Drawing Review & Approval

TUNNEL PLUMBING WORKS 21 02-Aug-23 26-Aug-23 26-Aug-23, TUNNEL PLUMBING WORKS

WBS Summary Summary Date Revision Checked Approved

Actual Work
Remaining Work
418 of 847
Critical Remaining Work
Milestone
W-02A

Activity ID Activity Name Original Start Finish


Duration 2022 2023 2024 2025 2026 2027
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
AP-Z7-EN-PLB.160 Plumbing Services Shop Drawings Preparation & Submission 9 02-Aug-23 12-Aug-23 Plumbing Services Shop Drawings Preparation & Submission

AP-Z7-EN-PLB.165 Plumbing Shop Drawings Review & Approval 12 13-Aug-23 26-Aug-23 Plumbing Shop Drawings Review & Approval

PROCUREMENT 388 28-Mar-23 08-Jul-24 08-Jul-24, PROCUREMENT


RAM265 Completion Procurment for Zone 7 0 08-Jul-24* Completion Procurment for Zone 7

CIVIL/STRUCTURAL 145 25-Jun-23 14-Dec-23 14-Dec-23, CIVIL/STRUCTURAL


AP-Z7-PRO-CSM.220 Request for Quotation 10 25-Jun-23 09-Jul-23 Request for Quotation

AP-Z7-PRO-CSM.225 Issue Purchase Order 15 10-Jul-23 26-Jul-23 Issue Purchase Order

AP-Z7-PRO-CSM.230 Material Delivery 90 31-Aug-23 14-Dec-23 Material Delivery

AP-Z7-PRO-CSM.235 Staging Time 30 27-Jul-23 30-Aug-23 Staging Time

UTILITIES 388 28-Mar-23 08-Jul-24 08-Jul-24, UTILITIES


WET UTILITIES 376 28-Mar-23 24-Jun-24 24-Jun-24, WET UTILITIES
POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS 260 28-Mar-23 01-Feb-24 01-Feb-24, POTABLE WATER NETWORK BRANCH, HOUSE CONNECTIONS,TIE IN POINTS
DI PIPES 145 16-Aug-23 01-Feb-24 01-Feb-24, DI PIPES
AP-Z7-PR-WU-PW.1135
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1140
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1145
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1310
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

HDPE PIPES 145 16-Aug-23 01-Feb-24 01-Feb-24, HDPE PIPES


AP-Z7-PR-WU-PW.1150
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1155
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1160
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1305
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

GRP PIPES 145 16-Aug-23 01-Feb-24 01-Feb-24, GRP PIPES


AP-Z7-PR-WU-PW.1165
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1170
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1175
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1300
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

DI & GRP FITTING 145 16-Aug-23 01-Feb-24 01-Feb-24, DI & GRP FITTING
AP-Z7-PR-WU-PW.1180
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1185
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1190
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1295
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

GATE VALVE 145 16-Aug-23 01-Feb-24 01-Feb-24, GATE VALVE


AP-Z7-PR-WU-PW.1195
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1200
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1205
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1290
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

BUTTERFLAY VALVE 145 16-Aug-23 01-Feb-24 01-Feb-24, BUTTERFLAY VALVE


AP-Z7-PR-WU-PW.1210
Issue Purchase Order 15 28-Aug-23 13-Sep-23 Issue Purchase Order

AP-Z7-PR-WU-PW.1215
Staging time 30 14-Sep-23 19-Oct-23 Staging time

AP-Z7-PR-WU-PW.1220
Material Delivery 90 21-Oct-23 01-Feb-24 Material Delivery

AP-Z7-PR-WU-PW.1285
Request for Quotation 10 16-Aug-23 27-Aug-23 Request for Quotation

WATER METER 205 28-Mar-23 29-Nov-23 29-Nov-23, WATER METER


AP-Z7-PR-WU-PW.1225
Issue Purchase Order