PROJECT NO.

W912ER21F0131  
SUPER HORNET F-18 (CLIN 3 - GENERAL PURPOSE WAREHOUSE - FACILITY K), AL JABER BASE, KUWAIT
ONGOING - COMPLETED ACTIVITIES
22-Sep-22
 
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Super Hornet Training Facility & Warehouse Design, AJAB, Kuwait - 22 September 2022 426d 0% 22-Sep-21 A 03-Nov-22 79d
CLIN 3 - General Purpose Warehouse - Facility G 426d 0% 22-Sep-21 A 03-Nov-22 79d
Project Milestones 74d 0% 22-Sep-21 A 25-Nov-21 A
PM1000 NTP / Project Start 0d 100% 22-Sep-21 A
PM1020 Start of Construction 0d 100% 25-Nov-21 A
General Requirements 365d 0% 25-Sep-21 A 24-Oct-22 64d
GEN1000 Preconstruction Meeting 1d 100% 30-Sep-21 A 30-Sep-21 A
Preconstruction Submittals 58d 0% 25-Sep-21 A 10-Nov-21 A
GEN1030 Submittal & Approval of CQC Plan 30d 100% 25-Sep-21 A 01-Nov-21 A
GEN1020 Submittal & Approval of Submittal Register 30d 100% 27-Sep-21 A 25-Oct-21 A
GEN1040 Submittal & Approval of Site Safety & Health Plan 30d 100% 04-Oct-21 A 25-Oct-21 A
GEN1010 Submittal & Approval of Baseline Schedule 30d 100% 23-Oct-21 A 10-Nov-21 A
Submittals & Approvals 338d 0% 28-Sep-21 A 24-Oct-22 64d
Submittals 249d 0% 28-Sep-21 A 24-Oct-22 64d
SUB1170 Submittals for doors & windows 30d 100% 28-Sep-21 A 28-Sep-21 A
SUB1020 Submittals for plumbing works 30d 100% 03-Oct-21 A 25-Jun-22 A
SUB1360 Submittals for concrete works 30d 100% 20-Oct-21 A 26-Jan-22 A
SUB1370 Submittal for conrete quality plan for exterior pavement 15d 90% 20-Oct-21 A 24-Oct-22 32d
SUB1040 Submittals for electrical works 30d 100% 01-Nov-21 A 31-Aug-22 A
SUB1210 Re-submittal of demolition plan by AICI 1d 100% 08-Nov-21 A 08-Nov-21 A
SUB1000 Submittals for PEB 30d 100% 10-Nov-21 A 10-Nov-21 A
SUB1080 Submittals for compressed air system 30d 100% 22-Nov-21 A 30-Nov-21 A
SUB1190 Submittals for CMU works 15d 100% 22-Nov-21 A 28-Jul-22 A
SUB1030 Submittals for HVAC works 30d 100% 01-Dec-21 A 18-Aug-22 A
SUB1070 Submittals for communication works 30d 90% 01-Dec-21 A 29-Sep-22 36d
SUB1180 Submittals for door hardware 30d 100% 01-Dec-21 A 09-Dec-21 A
SUB1350 Submittal for access control, intrusion detection system 30d 90% 01-Dec-21 A 11-Oct-22 66d
SUB1060 Submittals for fire alarm works 30d 100% 20-Dec-21 A 25-Aug-22 A
SUB1200 Submittals for furniture 30d 100% 22-Dec-21 A 15-Apr-22 A
SUB1410 Submittal for foundation drawings 30d 100% 28-Dec-21 A 03-Jan-22 A
SUB1050 Submittals for fire suppression works 30d 90% 04-Jan-22 A 28-Sep-22 42d
SUB1270 Submittal for exterior fence 30d 100% 10-Jan-22 A 28-Feb-22 A
SUB1330 Submittal for loading dock levelers 30d 100% 10-May-22 A 23-Jun-22 A
Approvals 327d 0% 28-Sep-21 A 05-Oct-22 75d
APP1170 Approvals for doors & windows 30d 100% 28-Sep-21 A 22-Nov-21 A
APP1020 Approvals for plumbing works 30d 95% 03-Oct-21 A 28-Sep-22 19d
APP1040 Approvals for electrical works 30d 100% 02-Nov-21 A 31-Aug-22 A
APP1360 Approvals for concrete works 30d 100% 02-Nov-21 A 26-Jan-22 A
APP1210 Approval of dimolition plan 4d 100% 09-Nov-21 A 14-Nov-21 A
APP1000 Approvals for PEB 30d 100% 11-Nov-21 A 02-Dec-21 A

Page 1 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
APP1190 Approvals for CMU works 30d 100% 22-Nov-21 A 14-Apr-22 A
APP1080 Approvals for equipments for compressed air system 30d 100% 23-Nov-21 A 24-Nov-21 A
APP1180 Approvals for door hardware 30d 100% 09-Dec-21 A 09-Dec-21 A
APP1370 Approvals for conrete quality plan for exterior pavement 30d 90% 09-Dec-21 A 29-Sep-22 32d
APP1070 Approvals for communication works 30d 80% 28-Dec-21 A 03-Oct-22 27d
APP1010 Approval of foundation drawings 25d 100% 03-Jan-22 A 31-Jan-22 A
APP1350 Approvals for access control, intrusion detection system 30d 90% 10-Jan-22 A 02-Oct-22 66d
APP1250 Approval of exterior fence 30d 100% 10-Jan-22 A 15-Mar-22 A
APP1030 Approvals for HVAC works 30d 100% 09-Feb-22 A 24-Aug-22 A
APP1050 Approvals for fire suppression works 30d 80% 16-Feb-22 A 05-Oct-22 42d
APP1060 Approvals for fire alarm works 30d 100% 15-Mar-22 A 31-Aug-22 A
APP1200 Approvals for furniture 30d 100% 15-Apr-22 A 19-May-22 A
APP1330 Approval for loading dock leveler 30d 100% 19-May-22 A 14-Jul-22 A
Procurement of Long Lead Items 279d 0% 30-Nov-21 A 03-Nov-22 60d
Procurement 279d 0% 30-Nov-21 A 03-Nov-22 60d
MAT1010 Procurement of Equipments for Compressed Air System 150d 100% 30-Nov-21 A 16-Jul-22 A
MAT1030 Procurement of PEB 120d 100% 30-Dec-21 A 09-Mar-22 A
MAT1760 Procurement of Fire Hose Reels with Cabinet 100d 60% 24-Feb-22 A 03-Nov-22 51d
MAT1110 Procurement of Doors 110d 100% 02-Mar-22 A 30-Aug-22 A
MAT1070 Procurement of Fire Alarm Components & Accessories 100d 100% 09-Mar-22 A 21-Jun-22 A
MAT1120 Procurement of HVAC Units 120d 100% 09-Mar-22 A 23-Jun-22 A
MAT1170 Procurement of Fiber Optic Cable 100d 100% 10-Mar-22 A 21-Jul-22 A
MAT1130 Procurement of Access Control, Intrusion Detection Components & Accessories
100d 100% 12-Mar-22 A 19-Jul-22 A
MAT1210 Procurement of Electrical Panel Boards 90d 95% 05-Apr-22 A 20-Oct-22 62d
MAT1080 Procurement of CCTV Components & Accessories 100d 100% 14-Apr-22 A 21-Jun-22 A
MAT1300 Procurement of LED lights 100d 20% 20-Apr-22 A 28-Oct-22 49d
MAT1230 Procurement of Light Poles 100d 100% 21-Apr-22 A 15-Jun-22 A
MAT1090 Procurement of Comm. Racks 100d 95% 28-Apr-22 A 09-Oct-22 64d
Delivery 195d 0% 10-Mar-22 A 21-Oct-22 74d
MAT1035 Delivery of PEB 1d 100% 10-Mar-22 A 10-Mar-22 A
MAT1085 Delivery of CCTV Components & Accessories 1d 100% 29-May-22 A 13-Jun-22 A
MAT1105 Delivery of Access Control, Intrusion Detection Components & Accessories 1d 100% 29-May-22 A 20-Jul-22 A
MAT1115 Delivery of Light Poles 1d 100% 05-Jun-22 A 09-Jun-22 A
MAT1215 Delivery of Electrical Panel Boards 1d 95% 21-Jun-22 A 21-Oct-22 62d
MAT1125 Delivery of HVAC Units 1d 100% 03-Jul-22 A 31-Aug-22 A
MAT1165 Delivery of Doors 1d 100% 13-Jul-22 A 18-Aug-22 A
MAT1095 Delivery of Comm. Racks 1d 95% 13-Jul-22 A 10-Oct-22 64d
MAT1400 Delivery of Equipments for Compressed Air System 1d 100% 28-Jul-22 A 28-Jul-22 A
MAT1145 Delivery of Fiber Optic Cables 1d 100% 28-Jul-22 A 28-Jul-22 A
MAT1075 Delivery of Fire Alarm Components 1d 95% 30-Aug-22 A 29-Sep-22 25d
Construction Works 395d 0% 18-Oct-21 A 02-Nov-22 80d
Mobilization 20d 0% 18-Oct-21 A 13-Nov-21 A
GPW.SITE1000 Site Mobilization Works 20d 100% 18-Oct-21 A 13-Nov-21 A
Demolition Works 240d 0% 25-Nov-21 A 02-Oct-22 81d
GPW.SITE1070 Remove existing light pole & related accessories 6d 100% 25-Nov-21 A 27-Nov-21 A

Page 2 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
GPW.SITE1030 Demolish existing office trailer 10d 100% 07-Dec-21 A 07-Dec-21 A
GPW.SITE1010 Remove existing vegetation 4d 100% 11-Jan-22 A 12-Jan-22 A
GPW.SITE1020 Remove existing barbed wire fence & gates 30d 80% 11-Jan-22 A 02-Oct-22 89d
GPW.SITE1050 Remove existing bollard around fire hydrant 1d 100% 11-Jan-22 A 11-Jan-22 A
GPW.SITE1060 Demolish existing asphalt pavement 5d 100% 11-Jan-22 A 12-Jan-22 A
Site Grading Works 19d 0% 04-Dec-21 A 23-Dec-21 A
GPW.SITE1080 Remove loose soils 6d 100% 04-Dec-21 A 08-Dec-21 A
GPW.SITE1090 Site grading & levelling works 10d 100% 13-Dec-21 A 23-Dec-21 A
Substructures 140d 0% 05-Jan-22 A 06-Oct-22 24d
Warehouse 136d 0% 05-Jan-22 A 06-Oct-22 24d
Footings 66d 0% 05-Jan-22 A 22-Mar-22 A
GPW.SUB1000 Excavation for warehouse foundation 10d 100% 05-Jan-22 A 13-Jan-22 A
GPW.SUB1010 Formworks & steel reinforcements - wall footings 15d 100% 15-Jan-22 A 23-Feb-22 A
GPW.SUB1030 Curing of concrete - wall footings 7d 100% 24-Feb-22 A 03-Mar-22 A
GPW.SUB1020 Casting of concrete - wall footings 1d 100% 24-Feb-22 A 24-Feb-22 A
GPW.SUB1040 Formworks & steel reinforcements - stem walls, pedestals 8d 100% 28-Feb-22 A 09-Mar-22 A
GPW.SUB1050 Casting of concrete - stem walls, pedestals 1d 100% 14-Mar-22 A 14-Mar-22 A
GPW.SUB1060 Curing of concrete - stem walls, pedestals 7d 100% 14-Mar-22 A 21-Mar-22 A
GPW.SUB1080 Backfilling with compaction - stem walls, pedestals 6d 100% 15-Mar-22 A 22-Mar-22 A
GPW.SUB1070 Bitumen paint - stem walls, pedestals 5d 100% 15-Mar-22 A 21-Mar-22 A
Tie Beams 47d 0% 28-Feb-22 A 22-Mar-22 A
GPW.SUB1090 Formworks & steel reinforcements - tie beams 8d 100% 28-Feb-22 A 13-Mar-22 A
GPW.SUB1420 Supply & install steel plates & anchor for steel structure 4d 100% 05-Mar-22 A 09-Mar-22 A
GPW.SUB1100 Casting of concrete - tie beams 1d 100% 14-Mar-22 A 14-Mar-22 A
GPW.SUB1110 Curing of concrete - tie beams 21d 100% 14-Mar-22 A 21-Mar-22 A
GPW.SUB1430 Backfilling with compaction - tie beams 5d 100% 15-Mar-22 A 22-Mar-22 A
GPW.SUB1120 Bitumen paint - tie beams 5d 100% 15-Mar-22 A 21-Mar-22 A
SOG 80d 0% 05-Mar-22 A 06-Oct-22 24d
GPW.SUB1150 Laying of underground MEP utilities 15d 100% 05-Mar-22 A 19-Mar-22 A
GPW.SUB1440 Formworks & steel reinforcements - SOG (part 2) 15d 100% 14-Mar-22 A 24-Mar-22 A
GPW.SUB1130 Grading & compaction of aggregate base course under SOG 10d 100% 16-Mar-22 A 20-Mar-22 A
GPW.SUB1140 Formworks & steel reinforcements - SOG (part 1) 15d 100% 16-Mar-22 A 21-Mar-22 A
GPW.SUB1160 Casting concrete - SOG 4d 100% 21-Mar-22 A 31-Mar-22 A
GPW.SUB1180 Expansion joints, construction joints, isolation joints 5d 60% 30-Mar-22 A 06-Oct-22 19d
GPW.SUB1170 Curing of concrete - SOG 7d 100% 31-Mar-22 A 07-Apr-22 A
Concrete Ramp & Loading Dock 113d 0% 11-Jan-22 A 07-Apr-22 A
GPW.SUB1200 Excavation for ramp & loading dock foundations 7d 100% 11-Jan-22 A 16-Jan-22 A
GPW.SUB1210 Formworks & steel reinforcements - footings 14d 100% 19-Feb-22 A 23-Feb-22 A
GPW.SUB1230 Curing of concrete - footings 7d 100% 24-Feb-22 A 03-Mar-22 A
GPW.SUB1220 Casting of concrete - footings 1d 100% 24-Feb-22 A 24-Feb-22 A
GPW.SUB1240 Formworks & steel reinforcements - pedestals 8d 100% 28-Feb-22 A 13-Mar-22 A
GPW.SUB1300 Formworks & steel reinforcements - SOG 15d 100% 13-Mar-22 A 26-Mar-22 A
GPW.SUB1250 Casting of concrete - pedestals 1d 100% 14-Mar-22 A 14-Mar-22 A
GPW.SUB1260 Curing of concrete - pedestals 7d 100% 14-Mar-22 A 21-Mar-22 A
GPW.SUB1270 Bitumen paint - pedestals 5d 100% 15-Mar-22 A 21-Mar-22 A
GPW.SUB1280 Backfilling with compaction - pedestals 7d 100% 15-Mar-22 A 22-Mar-22 A

Page 3 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
GPW.SUB1290 Grading & compaction of aggregate base course under SOG 6d 100% 17-Mar-22 A 28-Mar-22 A
GPW.SUB1310 Casting concrete - SOG 2d 100% 29-Mar-22 A 31-Mar-22 A
GPW.SUB1320 Curing of concrete - SOG 7d 100% 31-Mar-22 A 07-Apr-22 A
Mechanical Yard 70d 0% 08-Jan-22 A 22-Mar-22 A
GPW.SUB1330 Excavation for mech. yard foundation 4d 100% 08-Jan-22 A 10-Jan-22 A
GPW.SUB1340 Formworks & steel reinforcements - footings 7d 100% 17-Feb-22 A 23-Feb-22 A
GPW.SUB1360 Curing of concrete - footings 7d 100% 24-Feb-22 A 03-Mar-22 A
GPW.SUB1350 Casting of concrete - footings 1d 100% 24-Feb-22 A 24-Feb-22 A
GPW.SUB1370 Formworks & steel reinforcements - stem walls 5d 100% 28-Feb-22 A 13-Mar-22 A
GPW.SUB1380 Casting of concrete - stem walls 1d 100% 14-Mar-22 A 15-Mar-22 A
GPW.SUB1390 Curing of concrete - stem walls 7d 100% 14-Mar-22 A 21-Mar-22 A
GPW.SUB1410 Backfilling with compaction - stem walls 5d 100% 15-Mar-22 A 22-Mar-22 A
GPW.SUB1400 Bitumen paint - stem walls 2d 100% 15-Mar-22 A 21-Mar-22 A
Vehicle Parking Shelter 49d 0% 12-Jan-22 A 30-Mar-22 A
GPW.SITE1560 Excavation for vehicle parking shelter foundation 5d 100% 12-Jan-22 A 12-Mar-22 A
GPW.SITE1570 Formworks & steel reinforcements - footings 12d 100% 12-Mar-22 A 13-Mar-22 A
GPW.SITE1580 Casting of concrete - footings 1d 100% 14-Mar-22 A 14-Mar-22 A
GPW.SITE1590 Curing of concrete - footings 7d 100% 14-Mar-22 A 21-Mar-22 A
GPW.SITE1600 Formworks & steel reinforcements - pedestals 7d 100% 15-Mar-22 A 19-Mar-22 A
GPW.SITE1610 Casting of concrete - pedestals 1d 100% 19-Mar-22 A 19-Mar-22 A
GPW.SITE1620 Curing of concrete - pedestals 7d 100% 19-Mar-22 A 26-Mar-22 A
GPW.SITE1630 Bitumen paint - pedestals 3d 100% 26-Mar-22 A 28-Mar-22 A
GPW.SITE1640 Backfilling with compaction - pedestals 5d 100% 28-Mar-22 A 30-Mar-22 A
General Purpose Warehouse & Loading Dock - Structural Works 180d 0% 27-Mar-22 A 03-Oct-22 96d
GPW.ST1000 Warehouse & Loading Dock - Assembly & erection of steel structure (part 1)20d 100% 27-Mar-22 A 07-Apr-22 A
GPW.ST1070 Warehouse & Loading Dock - Assembly & erection of steel structure (part 2)15d 100% 27-Mar-22 A 05-Apr-22 A
GPW.ST1010 Warehouse & Loading Dock - Construct interior side perimeter CMU walls 25d 100% 08-Apr-22 A 25-May-22 A
GPW.ST1050 Ramp & Loading Dock - Install steel guardrails 4d 100% 20-Jun-22 A 04-Jul-22 A
GPW.AR1000 Supply & install insulated metal wall panels 6d 100% 14-Jul-22 A 04-Aug-22 A
GPW.ST1020 Warehouse & Loading Dock - Assembly & erection of roofing system 15d 100% 20-Jul-22 A 03-Aug-22 A
GPW.ST1040 Supply & install door canopies & window sunshades 10d 70% 30-Aug-22 A 03-Oct-22 61d
General Purpose Warehouse - Interior Construction 156d 0% 05-Apr-22 A 02-Nov-22 67d
Architectural Works 156d 0% 05-Apr-22 A 18-Oct-22 68d
Perimeter Walls 79d 0% 05-Apr-22 A 21-Aug-22 A
GPW.AR1030 Construct exterior side perimeter CMU walls 25d 100% 05-Apr-22 A 26-May-22 A
GPW.AR1020 Supply & install rigid wall insulation 20d 100% 04-Aug-22 A 21-Aug-22 A
GPW.AR1010 Stucco finish for exterior surface 20d 100% 07-Aug-22 A 21-Aug-22 A
Dry Areas 150d 0% 07-Apr-22 A 18-Oct-22 68d
GPW.AR1050 Construct CMU walls for interior partitions 21d 100% 07-Apr-22 A 25-May-22 A
GPW.AR1060 Plastering works for interior CMU Walls 14d 100% 02-Jul-22 A 09-Aug-22 A
GPW.AR1090 Painting works 14d 75% 09-Aug-22 A 13-Oct-22 44d
GPW.AR1070 Install exterior doors 4d 100% 10-Aug-22 A 03-Sep-22 A
GPW.AR1160 Install interior doors 6d 100% 10-Aug-22 A 08-Sep-22 A
GPW.AR1100 Supply & install ceiling grid 7d 35% 21-Aug-22 A 18-Oct-22 37d
GPW.AR1080 Install windows 4d 100% 25-Aug-22 A 31-Aug-22 A
WetAreas 30d 0% 16-Aug-22 A 02-Oct-22 65d

Page 4 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
GPW.AR1220 Supply & install wall tiles 15d 100% 16-Aug-22 A 03-Sep-22 A
GPW.AR1230 Supply & install floor tiles 6d 50% 13-Sep-22 A 02-Oct-22 65d
Mechanical Works 113d 0% 22-May-22 A 22-Oct-22 65d
Drainage System 10d 0% 22-May-22 A 28-Jul-22 A
GPW.MEC1000 Supply & install wall pipes for vent system 5d 100% 22-May-22 A 07-Jun-22 A
GPW.MEC1010 Supply & install overhead pipes for vent system 5d 100% 24-May-22 A 28-Jul-22 A
Water Supply System 98d 0% 02-Jun-22 A 20-Sep-22 A
GPW.MEC1040 Supply & install wall pipes for water supply 10d 100% 02-Jun-22 A 03-Aug-22 A
GPW.MEC1050 Supply & install overhead pipes for water supply 5d 100% 14-Jun-22 A 08-Sep-22 A
GPW.MEC1070 Supply & install water heaters 4d 100% 18-Sep-22 A 20-Sep-22 A
Compressed Air System 32d 0% 02-Aug-22 A 04-Oct-22 71d
GPW.MEC1090 Construct concrete pads for equipment 12d 100% 02-Aug-22 A 14-Aug-22 A
GPW.MEC1080 Supply & install compressed air pipe system 25d 100% 15-Aug-22 A 29-Sep-22 A
GPW.MEC1100 Install air compressor 8d 90% 29-Aug-22 A 04-Oct-22 71d
GPW.MEC1110 Install refrigerated air dryer 8d 100% 10-Sep-22 A 13-Sep-22 A
Interior HVAC Works 80d 0% 16-Jun-22 A 22-Oct-22 61d
GPW.MEC1140 Supply & install duct supports & hangers 15d 100% 16-Jun-22 A 15-Oct-22 A
GPW.MEC1150 Ductworks 20d 95% 24-Jul-22 A 09-Oct-22 43d
GPW.MEC1190 Duct insulation works 15d 95% 24-Jul-22 A 13-Oct-22 64d
GPW.MEC1170 Supply & install condensate pipes 10d 90% 03-Aug-22 A 22-Oct-22 56d
GPW.MEC1180 Suppl & install refrigerant pipes 10d 90% 04-Aug-22 A 22-Oct-22 56d
GPW.MEC1210 Duct air leakage test 4d 10% 20-Sep-22 A 18-Oct-22 64d
Electrical Works 128d 0% 19-May-22 A 02-Nov-22 67d
GPW.ELEC1040 Supply & install light switches, power sockets 12d 90% 19-May-22 A 17-Oct-22 65d
GPW.ELEC1000 Supply & install wall conduits 25d 100% 29-May-22 A 31-Aug-22 A
GPW.ELEC1080 Install electrical panel boards 12d 80% 23-Jul-22 A 25-Sep-22 76d
GPW.ELEC1070 Supply & install ground rod 10d 90% 23-Jul-22 A 03-Oct-22 76d
GPW.ELEC1010 Supply & install overhead conduits & cable trays 14d 80% 02-Aug-22 A 16-Oct-22 37d
GPW.ELEC1020 Supply & install wires for lighting & power circuits, central battery system 12d 70% 03-Sep-22 A 30-Oct-22 40d
GPW.ELEC1030 Supply & install cables for electrical panel boards 15d 40% 12-Sep-22 A 02-Nov-22 67d
GPW.ELEC1060 Supply & install disconnect switches for equipment's 10d 20% 18-Sep-22 A 01-Nov-22 53d
Telecommunication System Works 133d 0% 22-May-22 A 02-Nov-22 36d
Voice & Data System 133d 0% 22-May-22 A 25-Oct-22 43d
GPW.COM1010 Install raceways (conduits, cable trays) 20d 90% 22-May-22 A 19-Oct-22 43d
GPW.COM1020 Install comm. cables 12d 90% 30-Aug-22 A 25-Oct-22 43d
Comm 7. Room 11d 0% 22-Aug-22 A 29-Sep-22 53d
GPW.COM1040 Install fire rated wall plywood 3d 100% 22-Aug-22 A 08-Sep-22 A
GPW.COM1050 Painting of walls 4d 20% 21-Sep-22 A 29-Sep-22 53d
Electronic Security System (ESS) 70d 0% 18-Jul-22 A 02-Nov-22 21d
GPW.COM1100 Install raceways (conduits, cable trays) 20d 90% 18-Jul-22 A 19-Oct-22 21d
GPW.COM1110 Supply & install cables 12d 50% 31-Aug-22 A 02-Nov-22 21d
Fire Alarm & Fire Protection Works 55d 0% 18-Jul-22 A 16-Oct-22 56d
Fire Alarm System 55d 0% 18-Jul-22 A 16-Oct-22 46d
GPW.FA1010 Supply & install raceways 20d 90% 18-Jul-22 A 27-Sep-22 46d
GPW.FA1020 Supply & install cables & wires 15d 60% 28-Aug-22 A 16-Oct-22 46d
Fire Suppression System 19d 0% 27-Jul-22 A 10-Oct-22 61d

Page 5 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
GPW.FA1050 Supply & install overhead fire protection pipes & fire hose pipes 12d 90% 27-Jul-22 A 10-Oct-22 42d
GPW.FA1060 Supply & install vertical fire protection pipes & valves 6d 90% 21-Aug-22 A 02-Oct-22 67d
Site Utilities 186d 0% 27-Jan-22 A 28-Sep-22 68d
Sanitary Sewer System 186d 0% 30-Jan-22 A 12-May-22 A
GPW.SITE1100 Excavation works 10d 100% 30-Jan-22 A 19-Feb-22 A
GPW.SITE1110 Supply & install sanitary sewer piping system 12d 100% 06-Feb-22 A 21-Feb-22 A
GPW.SITE1130 Connection to existing sewer manhole 4d 100% 06-Feb-22 A 10-May-22 A
GPW.SITE1140 Backfilling with compaction 8d 100% 07-Feb-22 A 12-May-22 A
GPW.SITE1120 Supply & install manholes with cover 10d 100% 22-Feb-22 A 12-May-22 A
Storm Water Drainage 15d 0% 27-Jan-22 A 21-Jul-22 A
GPW.SITE1150 Excavation for storm drainage utilities 10d 100% 27-Jan-22 A 02-Feb-22 A
GPW.SITE1160 Supply & install concrete pipes 15d 100% 06-Feb-22 A 14-Jul-22 A
GPW.SITE1170 Supply & install catch basins 15d 100% 06-Feb-22 A 21-Jul-22 A
GPW.SITE1180 Backfilling with compaction 6d 100% 07-Feb-22 A 21-Jul-22 A
Water Distribution System 85d 0% 12-Feb-22 A 30-Jun-22 A
GPW.SITE1190 Excavation works 8d 100% 12-Feb-22 A 23-Mar-22 A
GPW.SITE1200 Supply & install domestic water supply lines & valves 15d 100% 20-Feb-22 A 30-Jun-22 A
GPW.SITE1240 Backfilling with compaction 6d 100% 20-Feb-22 A 30-Jun-22 A
GPW.SITE1210 Construct concrete encasement 10d 100% 13-Apr-22 A 30-Jun-22 A
Fire Protection Water Line 21d 0% 18-Apr-22 A 26-May-22 A
GPW.SITE1250 Excavation for fire protection water line 8d 100% 18-Apr-22 A 24-Apr-22 A
GPW.SITE1260 Supply & install fire protection water piping system 20d 100% 24-Apr-22 A 12-May-22 A
GPW.SITE1270 Backfilling with compaction 10d 100% 16-May-22 A 24-May-22 A
GPW.SITE1280 Supply & install fire hydrants 8d 100% 23-May-22 A 26-May-22 A
Electrical Utilities 22d 0% 14-May-22 A 28-Sep-22 79d
GPW.SITE1300 Excavation for electrical trench 8d 100% 14-May-22 A 21-May-22 A
GPW.SITE1320 Laying of underground cables 8d 100% 18-May-22 A 18-Jul-22 A
GPW.SITE1330 Backfilling with compaction 8d 100% 19-May-22 A 20-Jul-22 A
GPW.SITE1340 Supply & install lightning protection system 6d 80% 22-May-22 A 28-Sep-22 79d
GPW.SITE1350 Supply & install grounding system 6d 85% 26-May-22 A 28-Sep-22 79d
Light Poles 58d 0% 14-May-22 A 21-Jun-22 A
Civil Works for Light Poles 53d 0% 14-May-22 A 21-Jun-22 A
GPW.SITE1360 Excavation for light poles foundation 5d 100% 14-May-22 A 16-May-22 A
GPW.SITE1370 Construct concrete light poles foundation 20d 100% 16-May-22 A 22-May-22 A
GPW.SITE1380 Backfilling with compaction 4d 100% 28-May-22 A 30-May-22 A
GPW.SITE1390 Install light poles 10d 100% 02-Jun-22 A 21-Jun-22 A
Electrical Connections for Light Poles 58d 0% 16-May-22 A 26-May-22 A
GPW.SITE1400 Excavation for cable trench 8d 100% 16-May-22 A 18-May-22 A
GPW.SITE1410 Laying of underground cables 4d 100% 19-May-22 A 22-May-22 A
GPW.SITE1420 Backfilling with compaction 4d 100% 22-May-22 A 24-May-22 A
GPW.SITE1430 Supply & install earthing system for light poles 5d 100% 23-May-22 A 26-May-22 A
Mechanical Yard 164d 0% 15-Mar-22 A 06-Oct-22 93d
GPW.SITE1490 Formworks & steel reinforcements - top beams 10d 100% 15-Mar-22 A 23-Mar-22 A
GPW.SITE1450 Formworks & steel reinforcements - columns 10d 100% 17-Mar-22 A 22-Mar-22 A
GPW.SITE1460 Concrete casting - columns 1d 100% 23-Mar-22 A 23-Mar-22 A
GPW.SITE1510 Construct concrete equipment pads 10d 100% 23-Mar-22 A 27-Mar-22 A

Page 6 of 7    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
GPW.SITE1470 Curing of concrete - columns 7d 100% 24-Mar-22 A 29-Mar-22 A
GPW.SITE1500 Concrete casting - top beams 1d 100% 24-Mar-22 A 24-Mar-22 A
GPW.SITE1520 Curing of concrete - top beams 7d 100% 24-Mar-22 A 29-Mar-22 A
GPW.SITE1530 Laying of gravel 4d 100% 29-Mar-22 A 29-Mar-22 A
GPW.SITE1550 Install outdoor HVAC units 10d 95% 14-Jul-22 A 06-Oct-22 73d
GPW.SITE1480 Supply & install decorative blocks 15d 100% 08-Aug-22 A 08-Sep-22 A
GPW.SITE1540 Supply & install gate 5d 100% 03-Sep-22 A 18-Sep-22 A
Vehicle Parking Shelter 25d 0% 10-Aug-22 A 15-Aug-22 A
Superstructure 25d 0% 10-Aug-22 A 15-Aug-22 A
GPW.SITE1660 Assembly & erection of steel structure for parking shelter 15d 100% 10-Aug-22 A 15-Aug-22 A
GPW.SITE1670 Construct roofing system 10d 100% 10-Aug-22 A 15-Aug-22 A
Site Improvements 147d 0% 18-Apr-22 A 30-Oct-22 62d
Concrete Pavement Test Section 80d 0% 20-Apr-22 A 26-Sep-22 40d
GPW.SI1329 Start of Test Section 0d 100% 20-Apr-22 A
GPW.SI1330 Leveling & compaction of subgrade 2d 100% 21-Apr-22 A 24-Apr-22 A
GPW..SI1020 Grading & compaction of aggregate base course 4d 100% 25-Apr-22 A 14-Jul-22 A
GPW.SI1340 Formworks & dowels 6d 100% 10-Aug-22 A 13-Aug-22 A
GPW.SI1350 Casting concrete pavement 3d 100% 14-Aug-22 A 15-Aug-22 A
GPW.SI1360 Curing of concrete pavement 7d 100% 15-Aug-22 A 22-Aug-22 A
GPW.SI1370 Contraction & construction joints 4d 45% 21-Aug-22 A 26-Sep-22 33d
Heavy Duty Concrete Pavement 16d 0% 11-Jul-22 A 30-Oct-22 32d
GPW.SI1000 Leveling & compaction of subgrade 4d 100% 11-Jul-22 A 15-Aug-22 A
GPW..SI1010 Grading & compaction of aggregate base course 12d 100% 17-Jul-22 A 02-Oct-22 A
GPW.SI1020 Formworks & dowels 15d 50% 10-Aug-22 A 30-Oct-22 32d
Concrete Sidewalk 23d 0% 26-Jun-22 A 13-Sep-22 A
GPW.SI1060 Leveling & compaction of subgrade 2d 100% 26-Jun-22 A 28-Jul-22 A
GPW.SI1080 Formworks & wire fabric 7d 100% 02-Jul-22 A 03-Sep-22 A
GPW.SI1090 Casting concrete sidewalk 1d 100% 27-Aug-22 A 05-Sep-22 A
GPW.SI1100 Curing of concrete sidewalk 7d 100% 06-Sep-22 A 13-Sep-22 A
Asphalt Pavement 10d 0% 01-Sep-22 A 10-Oct-22 32d
GPW.SI1190 Leveling & compaction of subgrade 3d 100% 01-Sep-22 A 04-Sep-22 A
GPW.SI1200 Construct concrete curb 10d 100% 03-Sep-22 A 13-Sep-22 A
GPW.SI1210 Grading & compaction of aggregate base course 4d 60% 12-Sep-22 A 10-Oct-22 32d
Security Fence 65d 0% 18-Apr-22 A 31-Jul-22 A
GPW.SI1270 Excavation for pole footings 10d 100% 18-Apr-22 A 16-May-22 A
GPW.SI1280 Construct concrete footings 14d 100% 21-Apr-22 A 27-May-22 A
GPW.SI1290 Supply & install fence posts 8d 100% 24-Apr-22 A 31-Jul-22 A

Page 7 of 7    
PROJECT NO. W912ER21F0131  
SUPER HORNET F-18 (CLIN 6 - FUNCTIONAL AIRCREW TRAINING CENTER - FACILITY K), AL JABER BASE, KUWAIT
ONGOING - COMPLETED ACTIVITIES
22-Sep-22

Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Super Hornet Training Facility & Warehouse Design, AJAB, Kuwait - 22 September 2022 395d 0% 22-Sep-21 A 04-Dec-22 48d
CLIN 6 - Functional Aircrew Training Center - Facility K 395d 0% 22-Sep-21 A 04-Dec-22 48d
Project Milestones 91d 0% 22-Sep-21 A 24-Oct-21 A
PM1070 NTP / Project Start 0d 100% 22-Sep-21 A
PM1060 Start of Construction 0d 100% 24-Oct-21 A
Project Duration 385d 0% 22-Sep-21 A 04-Dec-22 0d
SP40 Functional Aircrew Training Center - Total Project Duration 380d 2% 22-Sep-21 A 04-Dec-22 0d
SP50 Rooms 168 & 167 - Project Duration 201d 2% 22-Sep-21 A 27-Oct-22 25d
General Requirements 380d 0% 22-Sep-21 A 04-Dec-22 48d
GEN1110 Access Passes 365d 2% 22-Sep-21 A 04-Dec-22 0d
GEN1080 Preconstruction Meeting 1d 100% 30-Sep-21 A 30-Sep-21 A
Preconstruction Submittals 52d 0% 26-Sep-21 A 10-Nov-21 A
GEN1070 Submittal & Approval of CQC Plan 30d 100% 26-Sep-21 A 01-Nov-21 A
GEN1060 Submittal & Approval of Submittal Register 24d 100% 27-Sep-21 A 25-Oct-21 A
GEN1090 Submittal & Approval of Site Safety & Health Plan 30d 100% 04-Oct-21 A 25-Oct-21 A
GEN1050 Submittal & Approval of Baseline Schedule 30d 100% 23-Oct-21 A 10-Nov-21 A
Submittals & Approvals 226d 0% 28-Sep-21 A 02-Oct-22 45d
Submittals 147d 0% 28-Sep-21 A 25-Sep-22 52d
SUB1290 Submittals for doors & windows 15d 100% 28-Sep-21 A 28-Sep-21 A
SUB1220 Submittals for plumbing works 30d 100% 03-Oct-21 A 07-Jun-22 A
SUB1300 Submittals for CMU works 30d 100% 05-Oct-21 A 26-Jan-22 A
SUB1240 Submittals for electrical works 30d 100% 10-Oct-21 A 02-Jun-22 A
SUB1380 Submittal for concrete plan 7d 100% 20-Oct-21 A 15-Nov-21 A
SUB1390 Submittal for concrete mix 7d 100% 20-Oct-21 A 14-Nov-21 A
SUB1400 Re-submittal of demolition plan by AICI 1d 100% 08-Nov-21 A 08-Nov-21 A
SUB1230 Submittals for HVAC works 30d 100% 01-Dec-21 A 31-May-22 A
SUB1280 Submittals for communication works 30d 100% 01-Dec-21 A 16-Jun-22 A
SUB1320 Submittals for access control, intrusion detection system 30d 100% 01-Dec-21 A 05-May-22 A
SUB1310 Submittals for door hardware 30d 100% 09-Dec-21 A 18-Aug-22 A
SUB1420 Submittal of foundation drawings 30d 100% 11-Dec-21 A 15-Dec-21 A
SUB1250 Submittal of furniture 30d 100% 22-Dec-21 A 15-Apr-22 A
SUB1260 Submittals for fire protection works 30d 100% 09-Jan-22 A 17-Aug-22 A
SUB1340 Submittals for fire alarm works 30d 90% 09-Jan-22 A 25-Sep-22 25d
Approvals 196d 0% 28-Sep-21 A 02-Oct-22 45d
APP1290 Approvals for doors & windows 46d 100% 28-Sep-21 A 22-Nov-21 A
APP1220 Approvals for plumbing works 30d 100% 03-Oct-21 A 24-Sep-22 30d
APP1240 Approvals for electrical works 30d 100% 01-Nov-21 A 02-Jun-22 A
APP1300 Approvals for CMU works 30d 100% 01-Nov-21 A 20-Feb-22 A
APP1280 Approval of demolition plan 4d 100% 09-Nov-21 A 14-Nov-21 A
APP1380 Approval for concrete plan 30d 100% 15-Nov-21 A 30-Dec-21 A

Page 1 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
APP1390 Approval for concrete mix 30d 100% 22-Nov-21 A 15-Dec-21 A
APP1310 Approvals for door hardware 30d 100% 09-Dec-21 A 23-Aug-22 A
APP1230 Approvals for HVAC works 30d 100% 13-Dec-21 A 23-Jun-22 A
APP1410 Approval of foundation drawings 30d 100% 15-Dec-21 A 13-Apr-22 A
APP1320 Approvals for access control, intrusion detection system 30d 100% 23-Dec-21 A 02-Jun-22 A
APP1260 Approvals for fire protection works 30d 100% 09-Jan-22 A 31-Aug-22 A
APP1340 Approvals for fire alarm works 30d 80% 09-Jan-22 A 02-Oct-22 25d
APP1270 Approvals for communication works 30d 90% 19-Jan-22 A 28-Sep-22 23d
APP1400 Approval of furniture 30d 100% 15-Apr-22 A 19-May-22 A
Procurement of Long Lead Items 241d 0% 29-Nov-21 A 15-Oct-22 33d
Procurement 222d 0% 29-Nov-21 A 14-Oct-22 33d
MAT1650 Procurement of Frequency Converters 100d 100% 29-Nov-21 A 23-Jun-22 A
MAT1550 Procurement of Doors 100d 100% 16-Dec-21 A 20-Jun-22 A
MAT1520 Procurement of roll up door 120d 100% 30-Dec-21 A 02-Jun-22 A
MAT1750 Procurement of Fire Alarm Components & Accessories 80d 90% 05-Jan-22 A 05-Oct-22 30d
MAT1670 Procurement of Comm. Cables 100d 100% 01-Mar-22 A 05-May-22 A
MAT1610 Procurement of Comm. Equipment Cabinets 100d 100% 03-Mar-22 A 02-Aug-22 A
MAT1460 Procurement of Comm. Raceways 80d 100% 03-Mar-22 A 19-May-22 A
MAT1430 Procurement of Split HVAC Units 120d 100% 05-Mar-22 A 23-Mar-22 A
MAT1710 Procurement of Comm. Components & Accessories 80d 100% 05-Mar-22 A 02-Aug-22 A
MAT1590 Procurement of CCTV Components & Accessories 100d 100% 09-Mar-22 A 05-Jun-22 A
MAT1490 Procurement of LED lights 100d 95% 10-Mar-22 A 29-Sep-22 40d
MAT1450 Procurement of DOAS 120d 100% 10-Mar-22 A 24-Aug-22 A
MAT1570 Procurement of Fire Hose Reels with Cabinet 100d 100% 13-Mar-22 A 11-May-22 A
MAT1690 Procurement of Door Hardwares 100d 60% 15-Mar-22 A 14-Oct-22 33d
MAT1440 Procurement of Electrical Panel Boards 60d 100% 24-Mar-22 A 28-Apr-22 A
MAT1730 Procurement of Access Control, Intrusion Detection Components & Accessories
80d 100% 24-Mar-22 A 28-Jul-22 A
Delivery 148d 0% 03-Feb-22 A 15-Oct-22 33d
MAT1580 Delivery of Fire Hose Reels with Cabinet 1d 100% 03-Feb-22 A 11-May-22 A
MAT1480 Delivey of Electrical Panel Boards 1d 100% 28-Feb-22 A 28-Apr-22 A
MAT1680 Delivery of Comm. Cables 1d 100% 03-Mar-22 A 11-May-22 A
MAT1700 Delivery of Door Hardwares 1d 70% 03-Mar-22 A 15-Oct-22 33d
MAT1780 Delivery of Fire Alarm Components & Accessories 1d 95% 03-Mar-22 A 06-Oct-22 30d
MAT1740 Delivery of Comm. Raceways 1d 100% 10-Mar-22 A 23-Jun-22 A
MAT1470 Delivery of Split HVAC Units 1d 100% 23-Mar-22 A 23-Mar-22 A
MAT1560 Delivery of Doors 1d 100% 30-Mar-22 A 02-Jun-22 A
MAT1500 Delivery of LED lights 1d 95% 25-Apr-22 A 30-Sep-22 40d
MAT1600 Delivery of CCTV Components & Accessories 1d 100% 02-Jun-22 A 02-Jun-22 A
MAT1800 Delivery of Roll up door 1d 80% 02-Jun-22 A 23-Sep-22 36d
MAT1660 Delivery of Frequency Converters 1d 100% 22-Jun-22 A 22-Jun-22 A
MAT1620 Delivery of Comm. Equipment Cabinets 1d 100% 02-Jul-22 A 02-Aug-22 A
MAT1510 Delivery of Access Control, Intrusion Detection Components & Accessories 1d 100% 02-Jul-22 A 30-Jul-22 A
MAT1720 Delivery of Comm. Components & Accessories 1d 100% 02-Jul-22 A 23-Aug-22 A
MAT1630 Delivery of DOAS 1d 100% 24-Aug-22 A 25-Aug-22 A
Construction works 352d 0% 18-Oct-21 A 24-Oct-22 89d

Page 2 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Mobilization 20d 0% 18-Oct-21 A 29-Nov-21 A
ATC.SITE1000 Site Mobilization Works 20d 100% 18-Oct-21 A 29-Nov-21 A
Renovation of Rooms 168 (TOFT 1), 167 (BDS/MOC #1), 268A, 268B 320d 0% 24-Oct-21 A 04-Oct-22 48d
Rooms 168, 167, 268A, 268B - Demolition Works 114d 0% 24-Oct-21 A 23-Dec-21 A
ATC.DEMO1310 Remove existing raised floor system at Room 167 6d 100% 24-Oct-21 A 28-Oct-21 A
ATC.DEMO1070 Demolish existing slabs and underground sanitary pipes 7d 100% 16-Nov-21 A 11-Dec-21 A
ATC.DEMO1040 Remove existing lights 3d 100% 07-Dec-21 A 13-Dec-21 A
ATC.DEMO1000 Demolish existing doors, windows & framing 7d 100% 08-Dec-21 A 13-Dec-21 A
ATC.DEMO1030 Remove existing fire alarm detectors 4d 100% 11-Dec-21 A 14-Dec-21 A
ATC.DEMO1080 Demolish portion of existing wall to create new door opening 6d 100% 12-Dec-21 A 14-Dec-21 A
ATC.DEMO1060 Remove existing CRAC unit & associated piping systems 6d 100% 14-Dec-21 A 20-Dec-21 A
ATC.DEMO1090 Remove existing sanitary vent pipes and cold water pipes 4d 100% 19-Dec-21 A 23-Dec-21 A
Room 168 - Civil Works 46d 0% 23-Dec-21 A 28-Feb-22 A
Room 168 - Footings 39d 0% 23-Dec-21 A 17-Feb-22 A
ATC.CVL0010 Excavation for warehouse foundation 4d 100% 23-Dec-21 A 28-Dec-21 A
ATC.CVL0060 Laying of underground sanitary pipes 5d 100% 29-Dec-21 A 30-Dec-21 A
ATC.CVL0020 Formworks & steel reinforcements - wall footings 7d 100% 26-Jan-22 A 06-Feb-22 A
ATC.CVL0050 Formworks & steel reinforcements - stem walls 6d 100% 26-Jan-22 A 06-Feb-22 A
ATC.CVL0030 Casting of concrete - wall footings 1d 100% 09-Feb-22 A 10-Feb-22 A
ATC.CVL0070 Casting of concrete - stem walls 1d 100% 09-Feb-22 A 09-Feb-22 A
ATC.CVL0040 Curing of concrete - wall footings 7d 100% 10-Feb-22 A 17-Feb-22 A
ATC.CVL0080 Curing of concrete - stem walls 7d 100% 10-Feb-22 A 17-Feb-22 A
ATC.CVL0090 Bitumen paint - stem walls 2d 100% 14-Feb-22 A 15-Feb-22 A
ATC.CVL0100 Backfilling with compaction - stem walls 4d 100% 17-Feb-22 A 17-Feb-22 A
Room 168 - SOG 14d 0% 15-Feb-22 A 28-Feb-22 A
ATC.CVL0110 Grading & compaction of aggregate base course under SOG 5d 100% 15-Feb-22 A 19-Feb-22 A
ATC.CVL0120 Formworks & steel reinforcements - SOG 7d 100% 15-Feb-22 A 19-Feb-22 A
ATC.CVL0130 Supply & install underground MEP utilities 5d 100% 15-Feb-22 A 20-Feb-22 A
ATC.CVL0140 Casting concrete - SOG 1d 100% 20-Feb-22 A 20-Feb-22 A
ATC.CVL0150 Curing of concrete - SOG 7d 100% 21-Feb-22 A 28-Feb-22 A
Rooms 168, 167, 268A, 268B - Architectural Works 96d 0% 02-Jan-22 A 14-Sep-22 A
ATC.AR1010 Room 168 - Construct CMU walls 10d 100% 02-Jan-22 A 28-Feb-22 A
ATC.AR1000 Room 168 - Supply & install wall steel frame 7d 100% 23-Jan-22 A 24-Jan-22 A
ATC.AR1020 Room 168 - Plastering of CMU walls 8d 100% 12-Feb-22 A 07-Mar-22 A
ATC.AR1030 Painting of walls 5d 100% 09-Mar-22 A 14-Sep-22 A
ATC.AR1060 Room 168 - Sealing of concrete floor 6d 100% 19-Mar-22 A 13-Sep-22 A
ATC.AR1080 Room 268B - Install vinyl floor tiles 5d 100% 19-Mar-22 A 23-Mar-22 A
ATC.AR1050 Rooms 168, 167, 268B - Ceiling works 6d 100% 22-Mar-22 A 02-Jul-22 A
ATC.AR1070 Room 168 - Install overhead roll-up door 8d 100% 24-May-22 A 11-Sep-22 A
Rooms 168, 167, 268A, 268B - Plumbing Works 18d 0% 28-Dec-21 A 31-Mar-22 A
ATC.MEC0010 Supply & install vent pipes 4d 100% 28-Dec-21 A 31-Mar-22 A
ATC.MEC0020 Supply & install water supply pipes 6d 100% 29-Mar-22 A 31-Mar-22 A
Rooms 168, 167, 268A, 268B - HVAC Works 157d 0% 13-Feb-22 A 19-Sep-22 A
ATC.MEC0040 Supply & install metal stand for DOAS 8d 100% 13-Feb-22 A 07-Mar-22 A
ATC.MEC0100 Electrical works for HVAC system 8d 100% 08-Mar-22 A 31-Mar-22 A
ATC.MEC0030 Ductworks 12d 100% 09-Mar-22 A 31-Mar-22 A

Page 3 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.MEC0070 Install indoor AC units at Rooms 167 & 268B 8d 100% 26-Mar-22 A 28-Mar-22 A
ATC.MEC0080 Supply & install condensate drain pipes 8d 100% 29-Mar-22 A 02-Apr-22 A
ATC.MEC0090 Supply & install refrigerant & liquid lines 8d 100% 29-Mar-22 A 02-Apr-22 A
ATC.MEC0050 Duct insulation works 12d 100% 29-Mar-22 A 17-Apr-22 A
ATC.MEC0060 Supply & install grilles & diffusers 6d 100% 31-Mar-22 A 06-Jun-22 A
ATC.MEC0110 Install DOAS at Room 268A 15d 100% 23-Aug-22 A 19-Sep-22 A
Rooms 168, 167, 268A, 268B - Electrical Works 81d 0% 05-Feb-22 A 23-Jul-22 A
ATC.ELEC0030 Install LED lights 10d 100% 05-Feb-22 A 02-Jun-22 A
ATC.ELEC0040 Supply & install surface raceways 8d 100% 14-Feb-22 A 31-Mar-22 A
ATC.ELEC1190 Supply & install wires for lights & power 10d 100% 20-Feb-22 A 31-Mar-22 A
ATC.ELEC0010 Supply & install cable trays 8d 100% 21-Feb-22 A 30-Jun-22 A
ATC.ELEC0020 Supply & install main cables 8d 100% 02-Apr-22 A 30-Jun-22 A
ATC.ELEC0080 Supply & install earthing system 5d 100% 04-Apr-22 A 04-Jun-22 A
ATC.ELEC0050 Supply & install light switches & power outlets 5d 100% 07-Apr-22 A 04-Jul-22 A
ATC.ELEC0060 Install SMDB & surge protection device 8d 100% 12-Apr-22 A 05-Jul-22 A
ATC.ELEC0100 Supply & install disconnect switches 6d 100% 25-Apr-22 A 07-Jul-22 A
ATC.ELEC0070 Install frequency converter 5d 100% 06-Jun-22 A 23-Jul-22 A
Rooms 168, 167, 268A, 268B - Communication Works 66d 0% 17-Mar-22 A 03-Oct-22 29d
ATC.COM0010 Install raceways & accessories 6d 100% 17-Mar-22 A 31-Mar-22 A
ATC.COM0020 Install comm. cables 5d 100% 14-Apr-22 A 23-Jul-22 A
ATC.COM0030 Install comm. components & accessories 5d 90% 27-Jul-22 A 03-Oct-22 29d
Rooms 168, 167, 268A, 268B - Electronic Security System 103d 0% 17-Mar-22 A 04-Oct-22 33d
ATC.COM0040 Install raceways & accessories 8d 100% 17-Mar-22 A 31-Mar-22 A
ATC.COM0050 Laying of cables 8d 100% 07-May-22 A 23-Jul-22 A
ATC.COM0080 Install CCTV components & accessories 7d 100% 23-Jul-22 A 29-Aug-22 A
ATC.COM0070 Install ESS components & accessories 11d 90% 03-Sep-22 A 04-Oct-22 33d
Rooms 168, 167, 268A, 268B - Modify Existing Fire Alarm Loop 21d 0% 09-Feb-22 A 13-Apr-22 A
ATC.FA0010 Supply & install raceways 8d 100% 09-Feb-22 A 27-Mar-22 A
ATC.FA0030 Install fire alarm components & accessories 10d 100% 28-Mar-22 A 13-Apr-22 A
ATC.FA0020 Supply & install fire extinguishers 4d 100% 31-Mar-22 A 13-Apr-22 A
Rooms 168, 167, 268A, 268B - Exterior Works - Mechanical Yard 194d 0% 27-Dec-21 A 06-Jul-22 A
ATC.DEMO1300 Demolish existing slab for mechanical screen wall foundation 8d 100% 27-Dec-21 A 28-Dec-21 A
ATC.CVL1780 Excavation for mech. yard foundation 3d 100% 29-Dec-21 A 03-Jan-22 A
ATC.CVL1790 Formworks & steel reinforcements - footings 5d 100% 09-Jan-22 A 29-Jan-22 A
ATC.CVL1800 Casting of concrete - footings 1d 100% 01-Feb-22 A 01-Feb-22 A
ATC.CVL1680 Formworks & steel reinforcements - columns 5d 100% 02-Feb-22 A 05-Feb-22 A
ATC.CVL1720 Formworks & steel reinforcements - top beams 5d 100% 02-Feb-22 A 05-Feb-22 A
ATC.CVL1810 Curing of concrete - footings 7d 100% 02-Feb-22 A 08-Feb-22 A
ATC.CVL1820 Formworks & steel reinforcements - stem walls 4d 100% 02-Feb-22 A 05-Feb-22 A
ATC.CVL1690 Concrete casting - columns 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1730 Concrete casting - top beams 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1750 Construct concrete equipment pads 12d 100% 07-Feb-22 A 14-Feb-22 A
ATC.CVL1830 Casting of concrete - stem walls 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1700 Curing of concrete - columns 7d 100% 08-Feb-22 A 17-Feb-22 A
ATC.CVL1740 Curing of concrete - top beams 7d 100% 08-Feb-22 A 17-Feb-22 A
ATC.CVL1840 Curing of concrete - stem walls 7d 100% 08-Feb-22 A 15-Feb-22 A

Page 4 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.CVL1850 Backfilling with compaction - stem walls 4d 100% 09-Feb-22 A 17-Feb-22 A
ATC.CVL1860 Bitumen paint - stem walls 2d 100% 14-Feb-22 A 16-Feb-22 A
ATC.CVL1770 Supply & install gate 4d 100% 14-Mar-22 A 16-Mar-22 A
ATC.CVL1760 Laying of gravel 3d 100% 27-Mar-22 A 30-Mar-22 A
ATC.MEC1190 Install outdoor AC units 5d 100% 07-Apr-22 A 21-Apr-22 A
ATC.CVL1710 Supply & install decorative blocks 10d 100% 02-Jul-22 A 06-Jul-22 A
Renovation of Other Areas 307d 0% 24-Oct-21 A 24-Oct-22 89d
Rooms 162 (TOFT 2), 161 (BDS/MOC #2), 262A, 262B 292d 0% 24-Oct-21 A 24-Oct-22 90d
Rooms 162, 161, 262A, 262B - Demolition Works 90d 0% 24-Oct-21 A 24-Jan-22 A
ATC.DEMO1250 Remove existing raised floor system at Room 161 6d 100% 24-Oct-21 A 27-Oct-21 A
ATC.DEMO1240 Demolish existing slabs and underground sanitary pipes 15d 100% 29-Nov-21 A 24-Jan-22 A
ATC.DEMO1220 Demolish existing doors, windows & framing 7d 100% 08-Dec-21 A 12-Dec-21 A
ATC.DEMO1280 Remove existing lights 4d 100% 08-Dec-21 A 14-Dec-21 A
ATC.DEMO1290 Remove existing fire alarm detectors 4d 100% 12-Dec-21 A 15-Dec-21 A
ATC.DEMO1230 Demolish portion of existing wall to create new door opening 10d 100% 13-Dec-21 A 15-Dec-21 A
ATC.DEMO1270 Remove existing CRAC unit & associated piping systems 8d 100% 15-Dec-21 A 20-Dec-21 A
ATC.DEMO1260 Remove existing sanitary vent pipes and cold water pipes 5d 100% 20-Dec-21 A 24-Jan-22 A
Room 162 - Civil Works 63d 0% 28-Feb-22 A 03-May-22 A
Room 162 - Footings 55d 0% 28-Feb-22 A 20-Apr-22 A
ATC.CVL1530 Excavation for warehouse foundation 5d 100% 28-Feb-22 A 14-Mar-22 A
ATC.CVL1870 Removal of old slab in room 162 20d 100% 28-Feb-22 A 14-Mar-22 A
ATC.CVL1540 Formworks & steel reinforcements - wall footings 8d 100% 24-Mar-22 A 04-Apr-22 A
ATC.CVL1550 Casting of concrete - wall footings 1d 100% 05-Apr-22 A 05-Apr-22 A
ATC.CVL1560 Curing of concrete - wall footings 7d 100% 05-Apr-22 A 12-Apr-22 A
ATC.CVL1570 Formworks & steel reinforcements - stem walls 6d 100% 05-Apr-22 A 06-Apr-22 A
ATC.CVL1670 Laying of underground sanitary pipes 5d 100% 10-Apr-22 A 13-Apr-22 A
ATC.CVL1580 Casting of concrete - stem walls 1d 100% 12-Apr-22 A 12-Apr-22 A
ATC.CVL1590 Curing of concrete - stem walls 7d 100% 12-Apr-22 A 18-Apr-22 A
ATC.CVL1610 Bitumen paint - stem walls 2d 100% 14-Apr-22 A 17-Apr-22 A
ATC.CVL1600 Backfilling with compaction - stem walls 4d 100% 17-Apr-22 A 20-Apr-22 A
Room 162 - SOG 14d 0% 11-Apr-22 A 03-May-22 A
ATC.CVL1660 Supply & install underground MEP utilities 5d 100% 11-Apr-22 A 24-Apr-22 A
ATC.CVL1630 Formworks & steel reinforcements - SOG 7d 100% 17-Apr-22 A 26-Apr-22 A
ATC.CVL1620 Grading & compaction of aggregate base course under SOG 5d 100% 18-Apr-22 A 20-Apr-22 A
ATC.CVL1640 Casting concrete - SOG 1d 100% 27-Apr-22 A 27-Apr-22 A
ATC.CVL1650 Curing of concrete - SOG 7d 100% 27-Apr-22 A 03-May-22 A
Rooms 162, 161, 262A, 262B - Architectural Works 115d 0% 02-Jan-22 A 24-Oct-22 24d
ATC.AR1220 Room 162 - Construct CMU walls 15d 100% 02-Jan-22 A 08-Feb-22 A
ATC.AR1230 Room 162 - Plastering of CMU walls 10d 100% 12-Feb-22 A 04-May-22 A
ATC.AR1210 Room 162 - Supply & install wall steel frame 7d 100% 28-Mar-22 A 29-May-22 A
ATC.AR1240 Painting of walls 6d 100% 18-May-22 A 08-Jun-22 A
ATC.AR1280 Rooms 161, 162, 262A, 262B - Ceiling works 7d 95% 18-May-22 A 13-Oct-22 24d
ATC.AR1290 Room 162 - Install overhead roll-up doors 12d 50% 29-May-22 A 05-Oct-22 24d
ATC.AR1250 Rooms 162 - Sealing of concrete floor 9d 30% 05-Jul-22 A 24-Oct-22 24d
Rooms 162, 161, 262A, 262B - Plumbing Works 34d 0% 15-Jan-22 A 29-Mar-22 A
ATC.MEC1090 Supply & install vent pipes 4d 100% 15-Jan-22 A 29-Mar-22 A

Page 5 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.MEC1100 Supply & install water supply pipes 7d 100% 22-Mar-22 A 29-Mar-22 A
Rooms 162, 161, 262A, 262B - HVAC Works 72d 0% 09-Mar-22 A 30-Jul-22 A
ATC.MEC1140 Ductworks 12d 100% 09-Mar-22 A 19-May-22 A
ATC.MEC1110 Install indoor AC units 8d 100% 05-Apr-22 A 21-Apr-22 A
ATC.MEC1120 Supply & install condensate drain pipes 10d 100% 10-Apr-22 A 12-Apr-22 A
ATC.MEC1130 Supply & install refrigerant & liquid lines 10d 100% 10-Apr-22 A 13-Apr-22 A
ATC.MEC1150 Duct insulation works 12d 100% 10-Apr-22 A 04-Jun-22 A
ATC.MEC1170 Electrical works for HVAC system 10d 100% 17-Apr-22 A 02-Jul-22 A
ATC.MEC1160 Supply & install grilles & diffusers 8d 100% 24-May-22 A 30-Jul-22 A
Rooms 162, 161, 262A, 262B - Electrical Works 79d 0% 05-Feb-22 A 18-Oct-22 25d
ATC.ELEC1110 Install LED lights 10d 90% 05-Feb-22 A 18-Oct-22 25d
ATC.ELEC1160 Supply & install surface raceways 8d 100% 19-Feb-22 A 07-Jul-22 A
ATC.ELEC1140 Supply & install cable trays 8d 100% 22-Mar-22 A 07-Jul-22 A
ATC.ELEC1200 Supply & install wires for lights & power 10d 100% 26-Mar-22 A 09-Jun-22 A
ATC.ELEC1120 Install SMDB & surge protection device 12d 100% 16-May-22 A 21-May-22 A
ATC.ELEC1170 Supply & install earthing system 8d 100% 19-May-22 A 14-Jul-22 A
ATC.ELEC1100 Supply & install light switches & power outlets 6d 100% 21-May-22 A 14-Jul-22 A
ATC.ELEC1150 Supply & install main cables 8d 100% 21-May-22 A 06-Jul-22 A
ATC.ELEC1130 Install frequency converter 6d 100% 08-Jun-22 A 23-Jul-22 A
Rooms 162, 161, 262A, 262B - Communication Works 103d 0% 29-Mar-22 A 04-Aug-22 A
ATC.COM1070 Install raceways & accessories 8d 100% 29-Mar-22 A 08-Jun-22 A
ATC.COM1080 Install comm. cables 5d 100% 18-May-22 A 23-Jul-22 A
ATC.COM1090 Install comm. components & accessories 8d 100% 28-Jul-22 A 04-Aug-22 A
Rooms 162, 161, 262A, 262B - Electronic Security System 93d 0% 05-Mar-22 A 11-Oct-22 86d
ATC.COM1100 Install raceways & accessories 8d 100% 05-Mar-22 A 14-Jul-22 A
ATC.COM1110 Laying of cables 8d 100% 28-May-22 A 16-Jul-22 A
ATC.COM1130 Install ESS components & accessories 10d 75% 18-Aug-22 A 11-Oct-22 31d
Rooms 162, 161, 262A, 262B - Modify Existing Fire Alarm Loop 67d 0% 12-Feb-22 A 16-Oct-22 27d
ATC.FA1150 Install cables 8d 100% 12-Feb-22 A 08-Jun-22 A
ATC.FA1090 Supply & install raceways 8d 100% 20-Feb-22 A 02-Jun-22 A
ATC.FA1100 Install fire alarm components & accessories 10d 90% 23-Feb-22 A 10-Oct-22 33d
ATC.FA1080 Supply & install fire extinguishers 4d 40% 20-Apr-22 A 16-Oct-22 27d
Rooms 162, 161, 262A, 262B - Exterior Works - Mechanical Yard 194d 0% 27-Dec-21 A 13-Jul-22 A
ATC.DEMO1210 Demolish existing slab for mechanical screen wall foundation 10d 100% 27-Dec-21 A 29-Dec-21 A
ATC.CVL1440 Excavation for mech. yard foundation 4d 100% 29-Dec-21 A 04-Jan-22 A
ATC.CVL1450 Formworks & steel reinforcements - footings 7d 100% 09-Jan-22 A 29-Jan-22 A
ATC.CVL1460 Casting of concrete - footings 1d 100% 01-Feb-22 A 01-Feb-22 A
ATC.CVL1190 Formworks & steel reinforcements - top beams 6d 100% 02-Feb-22 A 05-Feb-22 A
ATC.CVL1470 Curing of concrete - footings 7d 100% 02-Feb-22 A 08-Feb-22 A
ATC.CVL1480 Formworks & steel reinforcements - stem walls 5d 100% 02-Feb-22 A 05-Feb-22 A
ATC.CVL1150 Formworks & steel reinforcements - columns 6d 100% 05-Feb-22 A 05-Feb-22 A
ATC.CVL1160 Concrete casting - columns 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1200 Concrete casting - top beams 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1490 Casting of concrete - stem walls 1d 100% 07-Feb-22 A 07-Feb-22 A
ATC.CVL1170 Curing of concrete - columns 7d 100% 08-Feb-22 A 15-Feb-22 A
ATC.CVL1220 Curing of concrete - top beams 7d 100% 08-Feb-22 A 15-Feb-22 A

Page 6 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.CVL1210 Construct concrete equipment pad 12d 100% 08-Feb-22 A 14-Feb-22 A
ATC.CVL1500 Curing of concrete - stem walls 7d 100% 08-Feb-22 A 15-Feb-22 A
ATC.CVL1520 Backfilling with compaction - stem walls 4d 100% 09-Feb-22 A 19-Feb-22 A
ATC.CVL1510 Bitumen paint - stem walls 2d 100% 14-Feb-22 A 15-Feb-22 A
ATC.CVL1240 Supply & install gate 4d 100% 14-Mar-22 A 16-Mar-22 A
ATC.CVL1230 Laying of gravel 4d 100% 17-Mar-22 A 20-Mar-22 A
ATC.MEC1080 Install outdoor AC units 4d 100% 07-Apr-22 A 27-Apr-22 A
ATC.CVL1180 Supply & install decorative blocks 10d 100% 11-Jul-22 A 13-Jul-22 A
Secure Storage - Rooms 173, 173A, 271, 272 239d 0% 23-Nov-21 A 19-Oct-22 34d
Room 173 - Demolition Works 10d 0% 23-Nov-21 A 04-Dec-21 A
ATC.DEMO1100 Demolish existing slab and trenches 10d 100% 23-Nov-21 A 04-Dec-21 A
Room 173 - Civil Works 84d 0% 04-Dec-21 A 03-Feb-22 A
Room 173 - SOG 84d 0% 04-Dec-21 A 03-Feb-22 A
ATC.CVL1090 Grading & compaction of aggregate base course under SOG 6d 100% 04-Dec-21 A 16-Jan-22 A
ATC.CVL1120 Supply & install underground MEP utilities 8d 100% 06-Jan-22 A 12-Jan-22 A
ATC.CVL1100 Formworks & steel reinforcements - SOG 10d 100% 16-Jan-22 A 25-Jan-22 A
ATC.CVL1130 Casting concrete - SOG 1d 100% 26-Jan-22 A 26-Jan-22 A
ATC.CVL1140 Curing of concrete - SOG 7d 100% 27-Jan-22 A 03-Feb-22 A
Room 173, 173A, 271, 272 - Architectural Works 43d 0% 20-Feb-22 A 19-Oct-22 29d
ATC.AR1100 Room 173 - Install overhead door 4d 50% 20-Feb-22 A 26-Sep-22 43d
ATC.AR1090 Room 173A - CMU wall for fire hose reel cabinet 5d 100% 23-Mar-22 A 30-Mar-22 A
ATC.AR1110 Room 173 - Install doors with door hardware 6d 95% 12-Apr-22 A 15-Oct-22 29d
ATC.AR1120 Room 173 - Painting of walls 6d 100% 12-May-22 A 08-Jun-22 A
ATC.AR1130 Room 173A - Reinstall the existing ceiling tiles 4d 100% 09-Jun-22 A 13-Jun-22 A
ATC.AR1140 Room 190 - Supply & install fire extinguishers 4d 50% 09-Jun-22 A 19-Oct-22 29d
Room 173, 173A, 271, 272 - Electrical Works 59d 0% 22-Mar-22 A 09-Oct-22 37d
ATC.ELEC1300 Supply & install conduits for cable tray 10d 100% 22-Mar-22 A 10-Apr-22 A
ATC.ELEC1250 Supply & install conduits for cable trunkey 12d 100% 09-Apr-22 A 11-Apr-22 A
ATC.ELEC1210 Supply & install light switches & power outlets 8d 100% 12-Apr-22 A 22-Sep-22 51d
ATC.ELEC1290 Supply & install wires for lights & power 10d 100% 11-May-22 A 06-Jul-22 A
ATC.ELEC1220 Install LED lights 10d 60% 07-Jun-22 A 09-Oct-22 36d
Room 173, 173A, 271, 272 - Electronic Security System 127d 0% 03-Apr-22 A 10-Oct-22 32d
ATC.COM1140 Install raceways & accessories 12d 100% 03-Apr-22 A 13-Apr-22 A
ATC.COM1150 Laying of cables 10d 100% 10-May-22 A 23-Jul-22 A
ATC.COM1160 Install ESS components & accessories 15d 95% 11-Aug-22 A 10-Oct-22 32d
Room 118 - LCT 1,Room117 - LCT 2, Room 108 - F-18 COMM, Room 170 - Elec. Room 181d 0% 09-Dec-21 A 24-Oct-22 24d
Room 118,117, 108 - Demolition Works 12d 0% 09-Dec-21 A 25-Dec-21 A
ATC.DEMO1110 Remove existing doors & door frames 4d 100% 09-Dec-21 A 12-Dec-21 A
ATC.DEMO1120 Remove existing ceiling tiles 10d 100% 09-Dec-21 A 15-Dec-21 A
ATC.DEMO1130 Remove existing lights 12d 100% 09-Dec-21 A 15-Dec-21 A
ATC.DEMO1140 Remove existing grilles & diffusers 5d 100% 13-Dec-21 A 15-Dec-21 A
ATC.DEMO1150 Remove existing CRAC unit & associated piping systems 8d 100% 20-Dec-21 A 25-Dec-21 A
Room 118,117, 108 - ArchitecturalWorks 51d 0% 13-Apr-22 A 08-Jun-22 A
ATC.AR1180 Supply & install ceiling tiles 14d 100% 13-Apr-22 A 07-Jun-22 A
ATC.AR1170 Room 108 - Painting of walls 10d 100% 14-Apr-22 A 06-Jun-22 A
ATC.AR1300 Install doors & door hardware 8d 100% 03-May-22 A 08-Jun-22 A

Page 7 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
Room 118,117, 108 - HVAC Works 36d 0% 30-Mar-22 A 26-May-22 A
ATC.MEC1000 Ductwork 21d 100% 30-Mar-22 A 09-Apr-22 A
ATC.MEC1050 Duct insulation works 15d 100% 02-Apr-22 A 12-Apr-22 A
ATC.MEC1010 Install indoor AC units 10d 100% 05-Apr-22 A 09-Apr-22 A
ATC.MEC1020 Supply & install condensate drain pipes 15d 100% 05-Apr-22 A 09-Apr-22 A
ATC.MEC1030 Supply & install refrigerant & liquid lines 15d 100% 05-Apr-22 A 10-Apr-22 A
ATC.MEC1040 Electrical works for HVAC system 12d 100% 11-Apr-22 A 14-Apr-22 A
ATC.MEC1060 Supply & install grilles & diffusers 8d 100% 23-May-22 A 26-May-22 A
Room 118,117, 108, 170 - Electrical Works 107d 0% 20-Jan-22 A 09-Oct-22 34d
ATC.ELEC1000 Supply & install cable trays 21d 100% 20-Jan-22 A 06-Jul-22 A
ATC.ELEC1060 Supply & install power outlets 5d 100% 30-Jan-22 A 22-Jun-22 A
ATC.ELEC1030 Install LED lights 10d 90% 05-Feb-22 A 09-Oct-22 34d
ATC.ELEC1010 Laying of main cables 10d 100% 07-Feb-22 A 16-Jul-22 A
ATC.ELEC1020 Supply & install surface raceways 15d 100% 08-Feb-22 A 17-Jul-22 A
ATC.ELEC1040 Install DBs 6d 100% 07-May-22 A 16-Jul-22 A
ATC.ELEC1070 Supply & install earthing system 8d 100% 07-May-22 A 19-May-22 A
ATC.ELEC1080 Supply & install surge protection devices 6d 100% 25-May-22 A 18-Aug-22 A
ATC.ELEC1050 Install frequency converters at Room 117, 118 6d 100% 08-Jun-22 A 24-Jul-22 A
Room 108 - Communication Works 31d 0% 28-Apr-22 A 17-Oct-22 26d
ATC.COM1000 Room 108 - Install comm. equipment cabinet 10d 90% 28-Apr-22 A 06-Oct-22 26d
ATC.COM1010 Room 108 - Laying of fiber obtic cable 8d 90% 22-Aug-22 A 17-Oct-22 26d
ATC.COM1030 Room 108 - Install & install ladder rack 8d 90% 03-Sep-22 A 17-Oct-22 26d
Room 118,117, 108 - Electronic Security System 135d 0% 23-Mar-22 A 03-Oct-22 37d
ATC.COM1230 Install raceways & accessories 21d 100% 23-Mar-22 A 20-Apr-22 A
ATC.COM1240 Laying of cables 10d 100% 22-May-22 A 23-Jul-22 A
ATC.COM1250 Install ESS components & accessories 10d 90% 01-Sep-22 A 03-Oct-22 37d
Room 118,117, 108 - Modify Existing Fire Alarm Loop 83d 0% 13-Feb-22 A 24-Oct-22 24d
ATC.FA1160 Supply & install raceways 8d 100% 13-Feb-22 A 14-Apr-22 A
ATC.FA1020 Supply & install fire extinguishers 5d 80% 19-Apr-22 A 24-Oct-22 24d
ATC.FA1180 Install fire alarm components & accessories 10d 90% 10-May-22 A 17-Oct-22 26d
ATC.FA1010 Install new fire hose reel with cabinet 5d 100% 11-May-22 A 18-May-22 A
ATC.FA1170 Install cables 8d 100% 18-May-22 A 21-May-22 A
Corridors 168d 0% 23-Jan-22 A 20-Oct-22 23d
Corridors - Architectural Works 125d 0% 23-Jan-22 A 20-Oct-22 23d
ATC.DEMO1160 Remove existing ceiling tiles 10d 100% 23-Jan-22 A 03-Feb-22 A
ATC.AR1190 Re-install existing ceiling tiles 8d 80% 26-May-22 A 20-Oct-22 23d
Corridors - Electrical Works 43d 0% 23-Jan-22 A 12-Apr-22 A
ATC.DEMO1320 Remove existing lights 10d 100% 23-Jan-22 A 03-Feb-22 A
ATC.DEMO1330 Install wires for lights 10d 100% 15-Feb-22 A 12-Apr-22 A
Corridors - Electronic Security System 89d 0% 22-Mar-22 A 29-Sep-22 23d
ATC.COM1200 Install raceways & accessories 20d 100% 22-Mar-22 A 30-Jun-22 A
ATC.COM1210 Laying of cables 15d 100% 18-May-22 A 23-Jul-22 A
ATC.COM1220 Install ESS components & accessories 10d 70% 07-Aug-22 A 29-Sep-22 23d
Corridors - Mechanical Works 8d 0% 03-Feb-22 A 16-Feb-22 A
ATC.DEMO1170 Remove existing mechanical equipment devices 8d 100% 03-Feb-22 A 16-Feb-22 A
Corridors - Fire Protection Works 61d 0% 14-Mar-22 A 31-Mar-22 A

Page 8 of 9    
Activity ID Activity Name Original Performance % Start Finish Total Qtr 4, 2022 Qtr 1, 2023
Duration Complete Float Jan
Oct Nov Dec
ATC.FA1030 Install fire protection pipes 15d 100% 14-Mar-22 A 19-Mar-22 A
ATC.FA1040 Connect new fire protection pipes to existing fire hose pipes 6d 100% 15-Mar-22 A 27-Mar-22 A
ATC.FA1060 Install fire hose reel with cabinet 6d 100% 28-Mar-22 A 31-Mar-22 A
Room 101 - Classroom 49d 0% 17-Aug-22 A 11-Oct-22 47d
Room 101 - Architectural Works 42d 0% 17-Aug-22 A 28-Sep-22 53d
ATC.DEMO1350 Start of classroom 101 0d 100% 17-Aug-22 A
ATC.DEMO1180 Remove existing doors & door frames 2d 100% 17-Aug-22 A 17-Aug-22 A
ATC.DEMO1190 Remove existing ceiling tiles 4d 100% 17-Aug-22 A 17-Aug-22 A
ATC.AR1310 Install doors & door hardware 6d 90% 25-Aug-22 A 28-Sep-22 45d
ATC.AR1330 Paint works 1d 100% 06-Sep-22 A 14-Sep-22 A
ATC.AR1200 Supply & install ceiling tiles 5d 100% 12-Sep-22 A 14-Sep-22 A
Room 101 - HVAC Works 36d 0% 21-Aug-22 A 10-Sep-22 A
ATC.ME1310 Supply & install of CCU Unit Support. 3d 100% 21-Aug-22 A 03-Sep-22 A
ATC.ME1340 Supply & install of CCU Unit Condensate Drain. 3d 100% 25-Aug-22 A 04-Sep-22 A
ATC.ME1320 Supply & install of CCU Unit Condensate Drain Support. 3d 100% 28-Aug-22 A 05-Sep-22 A
ATC.ME1360 Supply & install of HVAC Duct and Damper. 3d 100% 03-Sep-22 A 06-Sep-22 A
ATC.ME1350 Supply & install of HVAC Duct and Damper Support Installation Work. 3d 100% 03-Sep-22 A 06-Sep-22 A
ATC.ME1370 Supply & install of HVAC Duct Insulation Work. 3d 100% 04-Sep-22 A 07-Sep-22 A
ATC.ME1330 Supply & install of CCU Unit. 3d 100% 07-Sep-22 A 08-Sep-22 A
ATC.ME1380 Supply & install of HVAC Diffuser & Flexible duct. 3d 100% 08-Sep-22 A 10-Sep-22 A
Room 101 - Electrical Works 33d 0% 18-Aug-22 A 14-Sep-22 A
ATC.DEMO1200 Remove existing lights 3d 100% 18-Aug-22 A 18-Aug-22 A
ATC.ELEC1090 Supply & install of light conduit and its accessories. 7d 100% 20-Aug-22 A 24-Aug-22 A
ATC.ELEC1310 Supply & install of exit light conduit and its accessories. 8d 100% 20-Aug-22 A 03-Sep-22 A
ATC.ELEC1320 Supply & install of power socket conduit and its accessories(240V 50HZ) 3d 100% 25-Aug-22 A 04-Sep-22 A
ATC.ELEC1330 Supply & install of light power cable. 3d 100% 03-Sep-22 A 11-Sep-22 A
ATC.ELEC1350 Supply & install of Installation of power socket cable. 3d 100% 04-Sep-22 A 11-Sep-22 A
ATC.ELEC1340 Supply & install of exit light power cable. 3d 100% 11-Sep-22 A 12-Sep-22 A
ATC.ELEC1370 Supply & install of Exit Light. 3d 100% 11-Sep-22 A 12-Sep-22 A
ATC.ELEC1380 Supply & install of Light 3d 100% 11-Sep-22 A 14-Sep-22 A
Room 101 - Electronic Security System 17d 0% 21-Aug-22 A 13-Sep-22 A
ATC.COM1170 Install raceways & accessories 5d 100% 21-Aug-22 A 06-Sep-22 A
ATC.COM1180 Laying of cables 5d 100% 27-Aug-22 A 10-Sep-22 A
ATC.COM1190 Install ESS components & accessories 5d 100% 08-Sep-22 A 13-Sep-22 A
Room 101 - Modify Existing Fire Alarm Loop 36d 0% 20-Aug-22 A 11-Oct-22 A
ATC.FA1120 Supply & install raceways 8d 100% 20-Aug-22 A 30-Aug-22 A
ATC.FA1140 Install cables 3d 100% 25-Aug-22 A 01-Sep-22 A
ATC.FA1130 Install fire alarm components & accessories 5d 100% 03-Sep-22 A 06-Sep-22 A
ATC.FA1110 Supply & install fire extinguishers 3d 100% 06-Sep-22 A 11-Oct-22 A