SUPER HORNET F-18 (CLIN 3 & 6) - AL JABER AIR BASE, KUWAIT
22-Sep-22      
Three weeks lookahead - Ongoing & Completed Activities (Internal Schedule)

Activity Name Original Activity % Start Finish Total


Duration Complete Float

Super Hornet Training Facility & Warehouse Design, AJAB, Kuwait491d


- 22 September22-Sep-21
2022 A 08-Jan-23 13d
CLIN 3 - General Purpose Warehouse - Facility G 491d 22-Sep-21 A 08-Jan-23 13d
Project Duration 486d 22-Sep-21 A 08-Jan-23 13d
General Requirements 491d 22-Sep-21 A 08-Jan-23 13d
Procurement of Long Lead Items 193d 24-Feb-22 A 30-Nov-22 33d
Procurement 193d 24-Feb-22 A 30-Nov-22 33d
Procurement of Fire Hose Reels with Cabinet 100d 60% 24-Feb-22 A 03-Nov-22 51d
Procurement of Electrical Panel Boards 90d 95% 05-Apr-22 A 20-Oct-22 62d
Procurement of LED lights 100d 20% 20-Apr-22 A 28-Oct-22 49d
Procurement of Light Poles 100d 100% 21-Apr-22 A 15-Jun-22 A
Procurement of Comm. Racks 100d 95% 28-Apr-22 A 09-Oct-22 64d
Procurement of Loading Dock Levelers 72d 0% 23-Jul-22 A 27-Oct-22 59d
Procurement of Sliding Steel Doors 55d 0% 15-Aug-22 A 22-Oct-22 63d
Procurement of Furnitures, Steel Shelves, Kitchen Appliances, Cabinets,
70dCountertop
0% 22-Sep-22 30-Nov-22 13d
Procurement of Door Hardwares 20d 0% 12-Oct-22 31-Oct-22 56d
Delivery 99d 29-May-22 21-Oct-22 74d
Construction Works 263d 11-Jan-22 AA 02-Nov-22 80d
Demolition Works 30d 11-Jan-22 A 02-Oct-22 89d
Remove existing barbed wire fence & gates 30d 80% 11-Jan-22 A 02-Oct-22 89d
Substructures 5d 30-Mar-22 A 06-Oct-22 19d
Warehouse 5d 30-Mar-22 A 06-Oct-22 19d
SOG 5d 30-Mar-22 A 06-Oct-22 19d
Expansion joints, construction joints, isolation joints 5d 60% 30-Mar-22 A 06-Oct-22 19d
General Purpose Warehouse & Loading Dock - Structural Works 10d 30-Aug-22 A 03-Oct-22 61d
Supply & install door canopies & window sunshades 10d 70% 30-Aug-22 A 03-Oct-22 61d
General Purpose Warehouse - Interior Construction 135d 19-May-22 02-Nov-22 67d
Architectural Works 35d A
09-Aug-22 A 18-Oct-22 58d
Perimeter Walls 10d 26-Sep-22 06-Oct-22 37d
Construct aerated concrete planks for elec. room ceiling (Fire rated sheet)
10d 0% 26-Sep-22 06-Oct-22 37d
Dry Areas 29d 09-Aug-22 A 18-Oct-22 40d
Painting works 14d 75% 09-Aug-22 A 13-Oct-22 44d
Supply & install ceiling grid 7d 35% 21-Aug-22 A 18-Oct-22 37d
Wet Areas 7d 13-Sep-22 A 10-Oct-22 65d
Supply & install floor tiles 6d 50% 13-Sep-22 A 02-Oct-22 65d
Ceiling works 6d 0% 03-Oct-22 10-Oct-22 65d
Mechanical Works 57d 24-Jul-22 A 22-Oct-22 65d
Drainage System 8d 11-Oct-22 19-Oct-22 67d
Supply & install sanitary fixtures 8d 0% 11-Oct-22 19-Oct-22 67d
Supply & install toilet accessories 6d 0% 11-Oct-22 17-Oct-22 69d
Water Supply System 4d 26-Sep-22 29-Sep-22 19d
Supply & install expansion tank 4d 0% 26-Sep-22 29-Sep-22 19d
Compressed Air System 8d 29-Aug-22 A 04-Oct-22 71d

Page 1 of 4    
Activity Name Original Activity % Start Finish Total
Duration Complete Float

Install air compressor 8d 90% 29-Aug-22 A 04-Oct-22 71d


Interior HVAC Works 56d 24-Jul-22 A 22-Oct-22 61d
Ductworks 20d 95% 24-Jul-22 A 09-Oct-22 43d
Duct insulation works 15d 95% 24-Jul-22 A 13-Oct-22 64d
Supply & install condensate pipes 10d 90% 03-Aug-22 A 22-Oct-22 56d
Suppl & install refrigerant pipes 10d 90% 04-Aug-22 A 22-Oct-22 56d
Duct air leakage test 4d 10% 20-Sep-22 A 18-Oct-22 64d
Install indoor HVAC units 12d 0% 26-Sep-22 10-Oct-22 56d
Electrical Works 76d 19-May-22 02-Nov-22 67d
Supply & install light switches, power sockets 12d 90% 19-May-22 17-Oct-22 65d
Install electrical panel boards 12d 80% 23-Jul-22 A 25-Sep-22 76d
Supply & install ground rod 10d 90% 23-Jul-22 A 03-Oct-22 76d
Supply & install overhead conduits & cable trays 14d 80% 02-Aug-22 A 16-Oct-22 37d
Supply & install wires for lighting & power circuits, central battery system
12d 70% 03-Sep-22 A 30-Oct-22 40d
Supply & install cables for electrical panel boards 15d 40% 12-Sep-22 A 02-Nov-22 67d
Supply & install disconnect switches for equipment's 10d 20% 18-Sep-22 A 01-Nov-22 53d
Telecommunication System Works 133d 22-May-22 02-Nov-22 36d
Voice & Data System 133d 22-May-22 25-Oct-22 43d
Install raceways (conduits, cable trays) 20d 90% 22-May-22 19-Oct-22 43d
Install comm. cables 12d 90% 30-Aug-22 A 25-Oct-22 43d
Comm 7. Room 14d 21-Sep-22 A 12-Oct-22 53d
Painting of walls 4d 20% 21-Sep-22 A 29-Sep-22 53d
Supply & install ladder rack 10d 0% 01-Oct-22 12-Oct-22 53d
Electronic Security System (ESS) 70d 18-Jul-22 A 02-Nov-22 21d
Install raceways (conduits, cable trays) 20d 90% 18-Jul-22 A 19-Oct-22 21d
Supply & install cables 12d 50% 31-Aug-22 A 02-Nov-22 21d
Fire Alarm & Fire Protection Works 55d 18-Jul-22 A 17-Oct-22 61d
Fire Alarm System 55d 18-Jul-22 A 16-Oct-22 46d
Supply & install raceways 20d 90% 18-Jul-22 A 27-Sep-22 46d
Supply & install cables & wires 15d 60% 28-Aug-22 A 16-Oct-22 46d
Fire Suppression System 29d 27-Jul-22 A 17-Oct-22 61d
Supply & install overhead fire protection pipes & fire hose pipes 12d 90% 27-Jul-22 A 10-Oct-22 42d
Supply & install vertical fire protection pipes & valves 6d 90% 21-Aug-22 A 02-Oct-22 67d
Supply & install sprinkler heads 6d 0% 11-Oct-22 17-Oct-22 61d
Site Utilities 100d 22-May-22 12-Oct-22 68d
Water Distribution System 4d 09-Oct-22 A 12-Oct-22 64d
Connection to water mains 4d 0% 09-Oct-22 12-Oct-22 64d
Electrical Utilities 6d 22-May-22 28-Sep-22 79d
Supply & install lightning protection system 6d 80% 22-May-22 28-Sep-22 79d
Supply & install grounding system 6d 85% 26-May-22 28-Sep-22 79d
Mechanical Yard 10d 14-Jul-22 A 06-Oct-22 73d
Install outdoor HVAC units 10d 95% 14-Jul-22 A 06-Oct-22 73d
Vehicle Parking Shelter 21d 25-Sep-22 19-Oct-22 66d
Superstructure 21d 25-Sep-22 19-Oct-22 66d
Asphalt works 6d 0% 25-Sep-22 01-Oct-22 66d
Supply & install wheelstops 4d 0% 02-Oct-22 05-Oct-22 73d
Electrical works 15d 0% 02-Oct-22 19-Oct-22 66d
Laying of gravel 4d 0% 06-Oct-22 11-Oct-22 73d

Page 2 of 4    
Activity Name Original Activity % Start Finish Total
Duration Complete Float
Site Improvements 54d 10-Aug-22 A 30-Oct-22 57d
Concrete Pavement Test Section 54d 21-Aug-22 A 27-Oct-22 33d
Contraction & construction joints 4d 45% 21-Aug-22 A 26-Sep-22 33d
Inspection of Test Section 1d 0% 27-Sep-22 27-Sep-22 33d
Flexural Strength Test for Test Section 1d 0% 28-Sep-22 28-Sep-22 33d
Prepare & submit Test Reports for Test Section 10d 0% 29-Sep-22 11-Oct-22 33d
Approval of Test Section 14d 0% 12-Oct-22 27-Oct-22 33d
Heavy Duty Concrete Pavement 15d 10-Aug-22 A 30-Oct-22 32d
Formworks & dowels 15d 50% 10-Aug-22 A 30-Oct-22 32d
Concrete Sidewalk 5d 12-Oct-22 18-Oct-22 67d
Contraction & expansion joints 5d 0% 12-Oct-22 18-Oct-22 67d
Asphalt Pavement 9d 12-Sep-22 A 12-Oct-22 32d
Grading & compaction of aggregate base course 4d 60% 12-Sep-22 A 10-Oct-22 32d
Prime coat 2d 0% 11-Oct-22 12-Oct-22 32d
Security Fence 10d 09-Oct-22 20-Oct-22 49d
Supply & install chain link fabric 10d 0% 09-Oct-22 20-Oct-22 49d
CLIN 6 - Functional Aircrew Training Center - Facility K 400d 22-Sep-21 A 04-Dec-22 10d
Project Duration 385d 22-Sep-21 A 04-Dec-22 0d
General Requirements 370d 22-Sep-21 A 04-Dec-22 0d
Procurement of Long Lead Items 228d 05-Jan-22 A 30-Nov-22 -14d
Procurement 228d 05-Jan-22 A 30-Nov-22 -15d
Procurement of Fire Alarm Components & Accessories 80d 90% 05-Jan-22 A 05-Oct-22 30d
Procurement of LED lights 100d 95% 10-Mar-22 A 29-Sep-22 40d
Procurement of Door Hardwares 100d 60% 15-Mar-22 A 14-Oct-22 33d
Procurment of furniture 120d 0% 02-Jul-22 A 30-Nov-22 -15d
Delivery 70d 03-Mar-22 A 15-Oct-22 33d
Construction works 206d 05-Feb-22 A 24-Oct-22 51d
Renovation of Rooms 168 (TOFT 1), 167 (BDS/MOC #1), 268A, 268B 43d 27-Jul-22 A 13-Oct-22 29d
Rooms 168, 167, 268A, 268B - Communication Works 5d 27-Jul-22 A 03-Oct-22 29d
Install comm. components & accessories 5d 90% 27-Jul-22 A 03-Oct-22 29d
Rooms 168, 167, 268A, 268B - Electronic Security System 11d 03-Sep-22 A 04-Oct-22 33d
Install ESS components & accessories 11d 90% 03-Sep-22 A 04-Oct-22 33d
Rooms 168, 167, 268A, 268B - Testing & Commissioning 15d 26-Sep-22 13-Oct-22 29d
Testing & Commissioning - electrical system 3d 0% 26-Sep-22 28-Sep-22 41d
Testing, Adjusting, Balancing - HVAC system 3d 0% 01-Oct-22 03-Oct-22 37d
Testing & Commissioning - access control system 3d 0% 05-Oct-22 09-Oct-22 33d
Testing & Commissioning - communication works 3d 0% 11-Oct-22 13-Oct-22 29d
Renovation of Other Areas 206d 05-Feb-22 A 24-Oct-22 51d
Rooms 162 (TOFT 2), 161 (BDS/MOC #2), 262A, 262B 143d 05-Feb-22 A 24-Oct-22 24d
Rooms 162, 161, 262A, 262B - Architectural Works 42d 18-May-22 24-Oct-22 24d
Rooms 161, 162, 262A, 262B - Ceiling works 7d 95% 18-May-22 13-Oct-22 24d
Room 162 - Install overhead roll-up doors 12d 50% 29-May-22 05-Oct-22 24d
Rooms 162 - Sealing of concrete floor 9d 30% 05-Jul-22 A 24-Oct-22 24d
Rooms 162, 161, 262A, 262B - Electrical Works 24d 05-Feb-22 A 18-Oct-22 25d
Install LED lights 10d 90% 05-Feb-22 A 18-Oct-22 25d
Supply & install wires for lights & power 10d 100% 26-Mar-22 A 09-Jun-22 A
Rooms 162, 161, 262A, 262B - Electronic Security System 10d 18-Aug-22 A 11-Oct-22 31d

Page 3 of 4    
Activity Name Original Activity % Start Finish Total
Duration Complete Float

Install ESS components & accessories 10d 75% 18-Aug-22 A 11-Oct-22 31d
Rooms 162, 161, 262A, 262B - Modify Existing Fire Alarm Loop 52d 23-Feb-22 A 16-Oct-22 27d
Install fire alarm components & accessories 10d 90% 23-Feb-22 A 10-Oct-22 33d
Supply & install fire extinguishers 4d 40% 20-Apr-22 A 16-Oct-22 27d
Secure Storage - Rooms 173, 173A, 271, 272 118d 20-Feb-22 A 19-Oct-22 29d
Room 173, 173A, 271, 272 - Architectural Works 40d 20-Feb-22 A 19-Oct-22 29d
Room 173 - Install overhead door 4d 50% 20-Feb-22 A 26-Sep-22 43d
Room 173 - Install doors with door hardware 6d 95% 12-Apr-22 A 15-Oct-22 29d
Room 173A - Reinstall the existing ceiling tiles 4d 100% 09-Jun-22 A 13-Jun-22 A
Room 190 - Supply & install fire extinguishers 4d 50% 09-Jun-22 A 19-Oct-22 29d
Room 173, 173A, 271, 272 - Electrical Works 44d 12-Apr-22 A 09-Oct-22 37d
Supply & install light switches & power outlets 8d 100% 12-Apr-22 A 22-Sep-22 51d
Install LED lights 10d 60% 07-Jun-22 A 09-Oct-22 36d
Room 173, 173A, 271, 272 - Electronic Security System 15d 11-Aug-22 A 10-Oct-22 32d
Install ESS components & accessories 15d 95% 11-Aug-22 A 10-Oct-22 32d
Room 118 - LCT 1, Room 117 - LCT 2, Room 108 - F-18 COMM, Room 170 - Elec. Room
124d 05-Feb-22 A 24-Oct-22 24d
Room 118, 117, 108, 170 - Electrical Works 10d 05-Feb-22 A 09-Oct-22 34d
Install LED lights 10d 90% 05-Feb-22 A 09-Oct-22 34d
Room 108 - Communication Works 37d 28-Apr-22 A 17-Oct-22 26d
Room 108 - Install comm. equipment cabinet 10d 90% 28-Apr-22 A 06-Oct-22 26d
Room 108 - Laying of fiber obtic cable 8d 90% 22-Aug-22 A 17-Oct-22 26d
Room 108 - Install & install ladder rack 8d 90% 03-Sep-22 A 17-Oct-22 26d
Room 108 - Install & terminate patch panels 8d 0% 09-Oct-22 17-Oct-22 26d
Room 118, 117, 108 - Electronic Security System 10d 01-Sep-22 A 03-Oct-22 37d
Install ESS components & accessories 10d 90% 01-Sep-22 A 03-Oct-22 37d
Room 118, 117, 108 - Modify Existing Fire Alarm Loop 23d 19-Apr-22 A 24-Oct-22 24d
Supply & install fire extinguishers 5d 80% 19-Apr-22 A 24-Oct-22 24d
Install fire alarm components & accessories 10d 90% 10-May-22 17-Oct-22 26d
Corridors 91d 26-May-22 20-Oct-22 47d
Corridors - Architectural Works 8d 26-May-22 20-Oct-22 23d
Re-install existing ceiling tiles 8d 80% 26-May-22 20-Oct-22 23d
Corridors - Electrical Works 10d 02-Oct-22 13-Oct-22 23d
Re-install LED lights 10d 0% 02-Oct-22 13-Oct-22 23d
Corridors - Telecommunication Works 20d 22-Sep-22 16-Oct-22 27d
Disconnect & remove existing fiber optic cable 8d 0% 22-Sep-22 01-Oct-22 23d
Supply & install above ceiling cable tray 10d 0% 22-Sep-22 03-Oct-22 27d
Laying of fiber obtic cable 10d 0% 04-Oct-22 16-Oct-22 27d
Corridors - Electronic Security System 10d 07-Aug-22 A 29-Sep-22 23d
Install ESS components & accessories 10d 70% 07-Aug-22 A 29-Sep-22 23d
Corridors - Mechanical Works 10d 03-Oct-22 16-Oct-22 51d
Re-install existing mechanical equipment devices 10d 0% 03-Oct-22 16-Oct-22 51d
Room 101 - Classroom 6d 25-Aug-22 A 28-Sep-22 45d
Room 101 - Architectural Works 6d 25-Aug-22 A 28-Sep-22 45d
Install doors & door hardware 6d 90% 25-Aug-22 A 28-Sep-22 45d
Building Commissioning 20d 22-Sep-22 16-Oct-22 31d
Testing & Commissioning - sanitary sewer system 4d 0% 22-Sep-22 26-Sep-22 47d
Testing, adjusting, balancing - HVAC system 4d 0% 01-Oct-22 04-Oct-22 40d
Testing & Commissioning - electronic security system 4d 0% 11-Oct-22 16-Oct-22 31d