Duration Planned

S.no Work discreption


(Days) Start Finish
INTERIOR FIT OUT WORKS FOR DANFOSS 2ND FLOOR 90 3-Apr-23 2-Jul-23
A Pre-Construction 7 27-Mar-23 3-Apr-23
Project pooja 1 27-Mar-23 27-Mar-23
Agreement signoff by Danfoss & KF 7 27-Mar-23 3-Apr-23
Kickoff Meeting with KF sub-vendors 1 3-Apr-23 3-Apr-23
B Design Sign Off Schedule 12 27-Mar-23 8-Apr-23
Prepare Basic drawing of Interior and MEP 7 27-Mar-23 3-Apr-23
Approval on Sample board 2 3-Apr-23 5-Apr-23
Approval of Interior and MEP layouts 2 5-Apr-23 7-Apr-23
Preparation of GFC Drawings and TDS 1 7-Apr-23 8-Apr-23
C Construction 90 3-Apr-23 2-Jul-23
1.00 Long Lead Items Procurement
Light fixtures & designer lights 35 8-Apr-23 13-May-23
Carpet 42 8-Apr-23 20-May-23
Modular furnitutes and Cabin, meeting room tables 42 8-Apr-23 20-May-23
Chair 49 8-Apr-23 27-May-23
Loose furnitures 49 8-Apr-23 27-May-23
AHU 49 8-Apr-23 27-May-23
INTERIOR FLOOR EXECUTION
Floor Marking for the partition and Block works 3 3-Apr-23 6-Apr-23
Modular furnitutes marking completion 2 6-Apr-23 8-Apr-23
Floor raceway marking & Cutting 5 8-Apr-23 13-Apr-23
Floor Raceways fixing 5 13-Apr-23 18-Apr-23
Fixing of floor junction boxes 2 16-Apr-23 18-Apr-23
Finishing of screed concrete for raceway areas 6 16-Apr-23 22-Apr-23
Sprinklers works
Sprinkler pipeline - Marking & support fixing 3 8-Apr-23 11-Apr-23
Main header lines erection 7 11-Apr-23 18-Apr-23
branch pipes erection & welding 15 18-Apr-23 3-May-23
Pressure testing of the sprinkler lines 3 3-May-23 6-May-23
Conduiting & cable tray fixing
Conduiting -Lighting, EMERGENCY, RAWPOWER, AV, DATA, WIFI 30 8-Apr-23 8-May-23
Conduiting for Fire,ACCESS System 35 8-Apr-23 13-May-23
Erection of ceiling Raceway - Data 35 8-Apr-23 13-May-23
Erection of ceiling Raceway - Power 35 8-Apr-23 13-May-23
Erection of Cable Trays 35 8-Apr-23 13-May-23
Laying of earth flats 3 13-May-23 16-May-23
HVAC activities
Marking & Support fixing 3 8-Apr-23 11-Apr-23
Erection of main ducts 15 10-Apr-23 25-Apr-23
Erection of branch ducts 15 26-Apr-23 11-May-23
Marking and support fixing for return air ducts in all cabins 4 11-May-23 15-May-23
Installation of VAVs 4 11-May-23 15-May-23
Cutting and Installation of collars 4 11-May-23 15-May-23
Pressure testing of Ducts 4 11-May-23 15-May-23
Preparation of acoustic insulated ducts 5 11-May-23 16-May-23
Erection of Acoustic insulationed ducts 5 11-May-23 16-May-23
Installation of Fire dampers, sound attenuators for supply air ducts 4 16-May-23 20-May-23
Installation of VCD 4 20-May-23 24-May-23
Cabling & wiring works
FA, PA & BMS cabling 25 13-Apr-23 8-May-23
Wiring for lighting system 7 13-May-23 20-May-23
UPS power cabling along with EGA box fixing in floors 5 20-May-23 25-May-23
Raw power cabling 5 25-May-23 30-May-23
Partition works
Fixing of framework for partition 7 10-Apr-23 17-Apr-23
Fixing of one side gypsum 10 17-Apr-23 27-Apr-23
Fixing conduits on partitions 5 27-Apr-23 2-May-23
fixing of back boxes for socket 3 2-May-23 5-May-23
Fixing of rock wool 7 5-May-23 12-May-23
Clearance for closing partition - checking and signoff 2 12-May-23 14-May-23
fixing of second layer of gypsum 7 14-May-23 21-May-23
Putty finish 10 21-May-23 31-May-23
Primer coat for paint finish for gyp partition 7 29-May-23 5-Jun-23
Fixing of Glass partition sections 5 5-Jun-23 10-Jun-23
Fixing of toughened glass 10 14-Jun-23 24-Jun-23
Fixing of writing board , pen tray ,soft board 5 5-Jun-23 10-Jun-23
Fixing of switch and data sockets 5 5-Jun-23 10-Jun-23
Fixing of doors 5 21-Jun-23 21-Jun-23
Fixing of sliding folding partition 49 10-Apr-23 29-May-23
Ceiling works
Preparation of Ceiling 15 3-Apr-23 18-Apr-23
Putty finish for true Ceiling 15 14-Apr-23 29-Apr-23
Primer coat for true ceiling 4 27-Apr-23 1-May-23
Fixing of window pelmet 7 10-Apr-23 17-Apr-23
Framing for Gypsum Ceiling for cabin 5 6-Jun-23 11-Jun-23
Gypsum boarding & finishing for the Ceiling for cabin 7 11-Jun-23 18-Jun-23
wall angles and support for grid ceiling for cabin and meeting rooms 4 18-Jun-23 22-Jun-23
Framing works for Grid ceiling 2 22-Jun-23 24-Jun-23
Fixing of Light fixtures ,cove light 2 24-Jun-23 26-Jun-23
Fixing of round ducts 2 24-Jun-23 26-Jun-23
Fixing of diffuser plenum boxes 2 24-Jun-23 26-Jun-23
Fixing of diffusers / return air grills 2 24-Jun-23 26-Jun-23
Fixing of sprinkler supports 2 24-Jun-23 26-Jun-23
Fixing of sprinkler flexi hose 2 24-Jun-23 26-Jun-23
Fixing of all detectors, RI, thermostat 2 24-Jun-23 26-Jun-23
Fixing of grid tiles 2 26-Jun-23 28-Jun-23
Aligning of grid ceiling 1 29-Jun-23 30-Jun-23
Acoustic baffle ceiling 15 20-May-23 4-Jun-23
Carpeting works
Prepration of the PCC for carpet laying 2 15-Jun-23 17-Jun-23
Work station & cabin area carpet laying 5 17-Jun-23 22-Jun-23
Work station works
Work station framing 3 20-Jun-23 23-Jun-23
Electrical and data cabling 3 22-Jun-23 25-Jun-23
Electrical & Data socket fixing 2 24-Jun-23 26-Jun-23
Table top fixing 3 23-Jun-23 26-Jun-23
Final alignment 1 26-Jun-23 27-Jun-23
Cabin furniture works
cabin furniture placing 2 25-Jun-23 27-Jun-23
Electrical and data cabling 1 26-Jun-23 27-Jun-23
Table top fixing 1 27-Jun-23 28-Jun-23
Electrical and data socket fixing 1 28-Jun-23 29-Jun-23
Remaining installation works
Installation of main door 2 21-Jun-23 23-Jun-23
Access control devices fixing 3 21-Jun-23 24-Jun-23
CCTV installation 2 21-Jun-23 23-Jun-23
Fixing of storages ,repro 7 23-Jun-23 30-Jun-23
Placing of chairs 1 29-Jun-23 30-Jun-23
Graphics & signage's 2 25-Jun-23 27-Jun-23
Fixing of blinds 2 25-Jun-23 27-Jun-23
Installation and Commissioning of access 5 24-Jun-23 29-Jun-23
final coat of painting for ceiling and walls 10 22-Jun-23 2-Jul-23
Electrical DB Works
Installation of DB's 2 30-May-23 1-Jun-23
Termination of DB's 7 1-Jun-23 8-Jun-23
HVAC WORKS IN AHU ROOM
Installation of AHU 10 27-May-23 6-Jun-23
Installation of Plenum 5 6-Jun-23 11-Jun-23
Connecting of main ducts to the Plenum 5 11-Jun-23 16-Jun-23
commissioning of AHU 10 16-Jun-23 26-Jun-23
SYSTEMS COMMISSIONING
Security system commissioning 10 16-Jun-23 26-Jun-23
Fire detection system commissioning 10 16-Jun-23 26-Jun-23
Final testing and commissioning of all system 10 16-Jun-23 26-Jun-23
D Post Construction 31 2-Jul-23 2-Aug-23
Completion of snags 25 2-Jul-23 27-Jul-23
Project Commercial Closure 5 27-Jul-23 1-Aug-23
Documents Handover & Report Submission 1 1-Aug-23 2-Aug-23