Laboratory Room Remaining Works

24-Apr'19
Sunday/Holiday 4/22/2019

10-May-19

11-May-19

12-May-19

13-May-19

14-May-19

15-May-19

16-May-19

17-May-19

18-May-19

19-May-19
Revised Revised

22-Apr-19

23-Apr-19

24-Apr-19

25-Apr-19

26-Apr-19

27-Apr-19

28-Apr-19

29-Apr-19

30-Apr-19

1-May-19

2-May-19

3-May-19

4-May-19

5-May-19

6-May-19

7-May-19

8-May-19

9-May-19
Description Action by REMARKS
Schedule Schedule
1 UPS / Electrical room
1.1 Touch-up paint of internal walls and door (Including cable ducts) Jphil 4/23/2019 4/24/2019
1.2 Cleaning of floor Jphil 4/25/2019 4/25/2019
1.3 Installation of UPS Equipment PICMW 4/29/2019 4/30/2019
1.4 Installation of Battery cabinet PICMW 4/30/2019 5/2/2019
1.5 Cabling and cable termination PICMW 5/3/2019 5/6/2019
1.6 Installation of battery switch panel PICMW 5/3/2019 5/4/2019
Jphil to request vendor to come early for
1.7 Testing of UPS System by Vendor Specialist UPS Vendor 5/22/2019 5/25/2019
testing (Tentatively 14-May)
1.8 Pressure test of refrigerant pipe PICMW 4/26/2019 4/27/2019

2 Gas Cylinder room


2.1 Touch-up paint of external walls PICMW 4/24/2019 4/25/2019
2.2 Connection of cables and pipes to cylinder Jphil (Fire-pro) TBA Gas cylinder is still in Custom for release
2.2 Installation of FM-200 cylinder Jphil (Fire-pro) TBA Gas cylinder is still in Custom for release

3 2nd Floor Hallway


3.1 External ducts and supports installation (Supply and exhaust) Crystal Jade 4/25/2019 4/27/2019
3.2 Scaffolding works PICMW 4/24/2019 4/27/2019

4 Toilet Area Corridor


4.1 Installation of exhaust duct along toilet corridor PICMW 4/25/2019 4/28/2019

5 Fabrication of GI ducts Jphil 4/25/2019 4/28/2019


6 Fabrication of SS duct fittings PICMW 4/25/2019 4/29/2019
7 Flexible duct connector fabrication Jphil 4/26/2019 4/27/2019
8 Supply of canvass cloth for duct connector PICMW 4/23/2019 4/24/2019
9 Delivery of fabricated aluminum framing for chemical filter PICMW 4/23/2019 4/24/2019
10 Installation of Fabricated aluminum framing Jphil 4/25/2019 4/26/2019

11 Laboratory Room
11.1 Aluminum door installation PICMW 4/24/2019 4/25/2019
11.2 Installation of tempered glass wall including pass-thru window PICMW 4/24/2019 4/25/2019
11.3 Installation of gypsum board (Fire pro to be left open) PICMW 4/24/2019 4/27/2019
11.4 Painting of ceiling PICMW 4/25/2019 4/28/2019
11.5 Installation of lighting fixtures, FA devices, speaker PICMW 4/28/2019 4/29/2019
11.6 Pressure test of Compressed air pipe PICMW 4/26/2019 4/27/2019
11.7 Drop pipe (1/2") installation Crystal Jade 4/26/2019 4/27/2019
11.8 Flushing test of FM-200 piping Jphil (Fire-pro) 4/25/2019 4/25/2019
Gas cylinder & nozzles are still in Custom
11.9 Installation of discharge nozzles Jphil (Fire-pro) TBA
for release
11.10 Installation of refrigerant pipes (Including Insulation) PICMW 4/26/2019 4/29/2019
11.11 Pressure test of refrigerant pipe PICMW 4/29/2019 4/30/2019
11.12 Control cable installation from indoor to outdoor PICMW 4/26/2019 4/30/2019
11.13 Supply of SS tubing for compressed air Jphil 4/25/2019 4/25/2019
11.14 Installation of exhaust and supply grilles PICMW 4/25/2019 4/26/2019
11.15 Installation of potable water pipe PICMW 4/24/2019 4/25/2019
11.16 Pressure test of potable water piping PICMW 4/26/2019 4/26/2019
11.17 Installation of condensate drain PICMW 4/24/2019 4/25/2019
11.18 Installation of chemical storage pit piping Jphil 4/25/2019 4/26/2019
11.19 Installation of portable FE (7 nos) PICMW TBA FE are still in Custom for release
11.20 Electrical/Functional test of lighting and socket outets PICMW 5/3/2019 5/3/2019
11.21 Illumination test PICMW 5/7/2019 5/7/2019
11.22 Telecom System test PICMW 5/8/2019 5/9/2019
11.23 Installation of temporary cable to UPSMDP panel PICMW 4/30/2019 4/30/2019
11.24 Testing of Socket outlets on Counters PICMW 5/7/2019 5/7/2019

12 Interstitial Room
12.1 Megger test for Panelboards and cables PICMW 4/30/2019 4/30/2019
12.2 Transformer test PICMW 4/30/2019 4/30/2019
12.3 Exhaust/Supply fan test PICMW 5/7/2019 5/9/2019
12.4 Motorized damper control panel test & damper functional test PICMW 5/10/2019 5/10/2019
12.5 Duct leak test PICMW 4/30/2019 4/30/2019
12.6 Energization of Panelboards PICMW 5/3/2019 5/3/2019
12.7 Installation of Exhaust/Supply ducts PICMW 4/26/2019 4/30/2019

13 Missing materials:
13.1 Chemical filter PICMW 5/2/2019 5/2/2019
13.2 Installation of chemical filter framing PICMW 4/25/2019 4/26/2019
Sourcing for available supplier locally.
Temporary spool to be installed in
13.3 Supply of Attenuator Jphil TBA
replacement for attenuator while waiting
for delivery of permanent
13.4 Transistion duct of chemical filter Jphil 4/25/2019 4/26/2019
13.5 Temporary spool in replacement for attenuator (mock-up sample) Jphil 4/25/2019 4/26/2019
13.6 Installation of baffles (egg tray) in attenuator temporary spool PICMW 4/26/2019 4/27/2019

14 Walkdown Schedule
Joint walkdown with Jphil, Archen and
14.1 1st Pre-walkdown for Auxiliary and Laboratory 5/2/2019
Petron Lab
Joint walkdown with Jphil, Archen and
14.2 2nd re-walkdown for Auxiliary, Laboratory and Interstitial 5/7/2019
Petron Lab