Project: Critical Path for

diversion of Existing Railway


Near Line Hufuf
Activity ID Activity Name Planned Start Finish Planned Total Cost 2022 2023
Duration
Oct Nov Dec Jan Feb
Diversion of existing railway line near Hofuf_11 223 22-Sep-04 23-Jul-12 SAR19,773,737.65

MILESTONES 223 22-Sep-04 23-Jul-12 SAR0.00

M-001 Project Start Date 0 22-Sep-04 SAR0.00


M-225 Project Finished 0 23-Jul-12 SAR0.00
GENERAL ITEMS 201 22-Sep-15 23-Jul-12 SAR1,840,000.00

M-011 Mobilization 15 22-Sep-15 22-Oct-08 SAR240,000.00Mobilization


M-012 Demobilization 15 23-Jun-19 23-Jul-12 SAR1,600,000.00

BRIDGES AND DRAINAGE CULVERTS 144 22-Sep-15 23-Apr-15 SAR14,843,097.65

Bridge No.2 144 22-Sep-15 23-Apr-15 SAR14,843,097.65


Reinforcing steel, Grade 60 132 22-Sep-18 23-Mar-30 SAR4,585,237.58
M-215 Reinforcing Steel Grade 60 - Pier Bored Piling Steel ( L=25m
25 ) 22-Sep-18 22-Oct-25 SAR902,673.40 Reinforcing Steel Grade 60 - Pier Bored Piling Steel ( L=25m )
M-217 Reinforcing Steel Grade 60 - Pier-Footing 3 22-Nov-06 22-Nov-10 SAR472,866.36 Reinforcing Steel Grade 60 - Pier-Footing
M-220 Reinforcing Steel Grade 60 - Pier Plinth 4 22-Nov-21 22-Nov-27 SAR292,887.03 Reinforcing Steel Grade 60 - Pier Plinth
M-218 Reinforcing Steel Grade 60 - Pier Column 3 22-Nov-27 22-Nov-30 SAR774,785.74 Reinforcing Steel Grade 60 - Pier Column
M-219 Reinforcing Steel Grade 60 - Pier Cap Beam 3 22-Dec-19 22-Dec-22 SAR331,674.95 Reinforcing Steel Grade 60 - Pier Cap Beam
M-210 Reinforcing Steel Grade 60 - Abutment 1- Cap Beam 2 22-Dec-27 22-Dec-29 SAR218,764.97 Reinforcing Steel Grade 60 - Abutment 1- Cap Beam
M-209 Reinforcing Steel Grade 60 - Abut1 Bufffer block & Bearing
2 seat23-Jan-05 23-Jan-08 SAR32,588.18 Reinforcing Steel Grade 60 - Abut1 Bufffer block & Bearing s
M-214 Reinforcing Steel Grade 60 - Diaphragm 3 23-Jan-21 23-Jan-25 SAR43,915.07 Reinforcing Steel Grade 60 - Diaphrag
M-213 Reinforcing Steel Grade 60 - Deskslab 4 23-Jan-31 23-Feb-06 SAR501,992.43 Reinforcing Steel Grad
M-212 Reinforcing Steel Grade 60 - Parapet Kerb 3 23-Feb-12 23-Feb-16 SAR146,099.80
M-221 Reinforcing Steel Grade 60 - Section D & E(WW3) 3 23-Feb-25 23-Mar-01 SAR197,133.69
M-211 Reinforcing Steel Grade 60 - Approach slab 2 23-Mar-28 23-Mar-30 SAR669,855.97
1200mm Diameter piles (fc 35Mpa) 26 22-Sep-29 22-Nov-06 SAR2,606,210.27 22-Nov-06, 1200mm Diameter piles (fc 35Mpa)
M-240 1200mm Bored Piling (fc=35 mpa) Pier 1 & 2/ concrete26 22-Sep-29 22-Nov-06 SAR2,606,210.27 1200mm Bored Piling (fc=35 mpa) Pier 1 & 2/ concrete
Lean concrete for Bridge (fc 20Mpa) 130 22-Sep-15 23-Mar-25 SAR70,079.70
M-184 Lean/Screed Concrete ( 20 mpa) Pier 1 & 2 2 22-Sep-15 22-Sep-18
Lean/Screed
SAR38,621.20
Concrete ( 20 mpa) Pier 1 & 2
M-185 Lean/Screed Concrete ( 20 mpa) ABT 2 Wing Wall 3-D1& E 23-Feb-23 23-Feb-25 SAR13,108.64
M-187 Lean/Screed Concrete ( 20 mpa) ABT 2 Apr slab (Left &1 Right) 23-Mar-23 23-Mar-25 SAR18,349.86
Structural concrete for substructure, (fc 35Mpa) 102 22-Nov-10 23-Apr-09 SAR3,940,098.60
M-196 Structural Concrete for Substructure (35 mpa) Piers Ftg.7 22-Nov-10 22-Nov-21 SAR1,928,905.24 Structural Concrete for Substructure (35 mpa) Piers Ftg.
M-197 Structural Concrete for Substructure (35 mpa) Piers Columns
3 22-Dec-01 22-Dec-05 SAR411,818.61 Structural Concrete for Substructure (35 mpa) Piers Columns
M-198 Structural Concrete for Substructure (35 mpa) Piers Cap
3 Beam 22-Dec-22 22-Dec-27 SAR359,563.86 Structural Concrete for Substructure (35 mpa) Piers Cap Beam
M-190 Structural Concrete for Substructure (35 mpa) ABT 1 Cap
2 Beam22-Dec-31
Right 23-Jan-02 SAR133,561.48 Structural Concrete for Substructure (35 mpa) ABT 1 Cap Beam Rig
M-189 Structural Concrete for Substructure (35 mpa) ABT 1 Cap
2 Beam23-Jan-02
Left 23-Jan-04 SAR133,561.48 Structural Concrete for Substructure (35 mpa) ABT 1 Cap Beam L
M-203 Structural Concrete for Substructure (35 mpa) Buffer Block
3 (Piers,
23-Jan-08
Abt 1 & 2) 23-Jan-12 SAR34,606.69 Structural Concrete for Substructure (35 mpa) Buffer Blo
M-202 Structural Concrete for Substructure (35 mpa) Curtain Wall
3 (Piers,
23-Jan-12
Abt 1 & Abt 2 23-Jan-16 SAR26,191.57 Structural Concrete for Substructure (35 mpa) Cur
M-194 Structural Concrete for Substructure (35 mpa) ftg. WW34 (D & E)23-Mar-01 23-Mar-07 SAR324,391.64
M-199 Structural Concrete for Substructure (35 mpa) Apr. Slab3Abt 1 (Left
23-Mar-30
& Right) 23-Apr-04 SAR293,749.01
M-200 Structural Concrete for Substructure (35 mpa) Apr. Slab3Abt 2 (Left
23-Apr-04
& Right) 23-Apr-09 SAR293,749.01
Supply and installation of Waterproofing Membrane 77 22-Dec-05 23-Mar-28 SAR336,737.10
M-234 Supply and Installation of Water Proofing Membrane for
2 Pie r Footi
22-Dec-05
ng 22-Dec-08 SAR59,260.48 Supply and Installation of Water Proofing Membrane for Pier Footing
M-232 Supply and Installation of Water Proofing Membrane for
2 Wingwal
23-Mar-07
l s 1,2,3&4 Top 23-Mar-09
of Footings,Counterports
SAR243,502.38
& Walls (Backface)
M-235 Supply and Installation of Water Proofing Membrane for
2 Approach
23-Mar-25
Slab 23-Mar-28 SAR33,974.24

Remaining Level of Effort Summary Date Revision Checked Approved


Page 1 of 2 PLANNER: ILYAS AHMAD
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Project: Critical Path for
diversion of Existing Railway
Near Line Hufuf
Activity ID Activity Name Planned Start Finish Planned Total Cost 2022 2023
Duration
Oct Nov Dec Jan Feb
Structural backfilling 72 22-Dec-08 23-Mar-23 SAR16,203.44
M-183 Structural Backfilling; Around Piers 7 22-Dec-08 22-Dec-18 SAR1,035.73 Structural Backfilling; Around Piers
M-182 Structural Backfilling; Wing Wall 04 (Abt 2) (@ Back Face)
9 23-Mar-11 23-Mar-23 SAR15,167.72
Reinf. Elastomeric Pad including erection of girders 3 23-Jan-17 23-Jan-21 SAR1,600,000.00 23-Jan-21, Reinf. Elastomeric Pad including
M-238 Reinf. Elastomeric Pad including erection of girders 3 23-Jan-17 23-Jan-21 SAR1,600,000.00 Reinf. Elastomeric Pad including erection of
Structural concrete for superstructure (fc 35Mpa) 12 23-Jan-25 23-Feb-12 SAR1,079,388.40 23-Feb-12, Stru
M-204 Structural Concrete for Superstructure (35 mpa) Diaphram
4 23-Jan-25 23-Jan-31 SAR133,443.16 Structural Concrete for Superst
M-205 Structural Concrete for Superstructure (35 mpa) Deck Slab
4 23-Feb-06 23-Feb-12 SAR945,945.24 Structural Conc
Reinforced concrete Bridge Parapet (fc' 30Mpa) 3 23-Feb-16 23-Feb-20 SAR164,193.17
M-206 Reinforced Concrete for Bridge Parapet (fc=30 mpa) 3 23-Feb-16 23-Feb-20 SAR164,193.17
Structural Excavation 2 23-Feb-21 23-Feb-23 SAR188,715.40
M-176 Abutment 2, Wing Wall 3- E, section D & E 2 23-Feb-21 23-Feb-23 SAR188,715.40
Special expansion joints for bridge deck 4 23-Apr-09 23-Apr-15 SAR256,234.00
M-227 Special Expansion Joints 4 23-Apr-09 23-Apr-15 SAR256,234.00
Rail works 42 23-Apr-15 23-Jun-19 SAR3,090,640.00
M-429 Rail movement joints 12 23-Apr-15 23-May-06 SAR1,260,000.00
M-428 Transit ion Rails 11 23-May-06 23-May-22 SAR119,000.00
M-434 CEN 60 Rail 11 23-May-22 23-Jun-07 SAR758,640.00
M-432 Special Sleepers 4 23-Jun-07 23-Jun-13 SAR872,000.00
M-431 Kilometer posts 4 23-Jun-13 23-Jun-19 SAR81,000.00

Remaining Level of Effort Summary Date Revision Checked Approved


Page 2 of 2 PLANNER: ILYAS AHMAD
Actual Work
Remaining Work
Critical Remaining Work
Milestone