Professional Documents
Culture Documents
Prepared By
Government of Mizoram
Public Works Department
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
CLASSIFICATION OF PACKAGES
The whole Kaladan Project is divided into three packages as
follows:
OVERVIEW OF PACKAGE -I
One of the major work in this package is the construction
of Bridge at CH.31+700 over River Ruankhum span of
which is fixed at 20.8m.
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
NGENPUI ABUTMENT A1
Bar chart :
6
Total
5
Completed
4
Balance
3
0
Fdn. works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
NGENPUI ABUTMENT A1
Abutment A1- earthwork excavation is completed
NGENPUI ABUTMENT A2
Bar chart :
5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance
1.5
1
0.5
0
Fdn. Works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
NGENPUI ABUTMENT A2
Abutment A2- Concrete casting casted upto bottom of
abutment cap.
NGENPUI PIER P1
Bar chart :
25
20
15 Total
Completed
10 Balance
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
NGENPUI PIER P1
Pier P1 - Earthwork excavation yet to be started
NGENPUI PIER P2
Bar chart :
25
20
15 Total
Completed
10 Balance
0
Fdn. Works Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
NGENPUI PIER P2
Pier P2 - Casting completed upto 10th lift pier coloumn
LUNGHAUKA ABUTMENT A1
Bar chart :
12
10
8
Total
6 Completed
Balance
4
0
Fdn Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
LUNGHAUKA ABUTMENT A1
Abutment A1- Casting completed upto 2nd lift of abutment column
LUNGHAUKA ABUTMENT A2
Bar chart :
12
10
8
Total
6 Completed
Balance
4
0
Fdn Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
LUNGHAUKA ABUTMENT A2
Abutment A2- Casting completed upto 6th lift
PROGRESS ON CONSTRUCTION OF
BRIDGES UNDER PACKAGE -III
3. Bridge over River Khwaraup
KHWARAUP ABUTMENT A1
Bar chart :
5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance
1.5
1
0.5
0
Fdn works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
KHWARAUP ABUTMENT A1
Abutment A2- Casting completed upto bottom of abutment cap
KHWARAUP ABUTMENT A2
Bar chart :
5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance
1.5
1
0.5
0
Fdn works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
KHWARAUP ABUTMENT A2
Abutment A2- Casting completed upto bottom of abutment cap
KHWARAUP PIER P1
Bar chart :
20
18
16
14
12 Total
10
Completed
8
Balance
6
4
2
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
KHWARAUP PIER P1
Pier P1 - Casting completed upto 10th lift pier coloumn
KHWARAUP PIER P2
Bar chart :
20
18
16
14
12 Total
10 Completed
8 Balance
6
4
2
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
KHWARAUP PIER P2
Pier P2 - Casting completed upto 12th lift pier coloumn
PROGRESS ON CONSTRUCTION OF
BRIDGES UNDER PACKAGE -III
4. Bridge over River Hmwangbu
1. Abutment A1- Casting yet to be started.
2. Abutment A2- Raft Fdn casting completed
3. Pier P1 - Raft Fdn reinf. Work in progress
4. Pier P2 - Casting completed upto 8th lift pier coloumn
HMWANGBU ABUTMENT A1
Bar chart :
4
Total
3 Completed
Balance
2
0
Fdn Base slab Rtn/Wall Abutment cap-to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
HMWANGBU ABUTMENT A1
Abutment A1- earthwork excavation is completed
HMWANGBU ABUTMENT A2
Bar chart :
4
Total
3 Completed
Balance
2
0
Fdn Base slab Rtn/Wall Abutment cap-to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
HMWANGBU ABUTMENT A2
Abutment A2- Raft Fdn casting completed
HMWANGBU PIER P1
Bar chart :
16
14
12
10 Total
8 Completed
Balance
6
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
HMWANGBU PIER P1
Pier P1 - Raft Fdn reinf. Work in progress
HMWANGBU PIER P2
Bar chart :
16
14
12
10 Total
8 Completed
Balance
6
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
HMWANGBU PIER P2
Pier P2 - Casting completed upto 8th lift pier coloumn
THANK YOU