PROGRESS ON KALADAN MULTI

MODAL TRANSIT TRANSPORT PROJECT

Prepared By
Government of Mizoram
Public Works Department
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

CLASSIFICATION OF PACKAGES
 The whole Kaladan Project is divided into three packages as
follows:

SL.NO PACKAGE NAME NAME OF CONTARCTOR


FOR PACKAGE
1. Package-I RDS Projects Pvt. Ltd
2. Package-II Atlanta ARSS (J.V.)
3. Package-III RDS Projects Pvt. Ltd
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

OVERVIEW OF PACKAGE -I
 One of the major work in this package is the construction
of Bridge at CH.31+700 over River Ruankhum span of
which is fixed at 20.8m.
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

RUANKHUM ABUTMENT A1&A2

Layout given by consultant . Awaiting start of excavation works by the


contractor .
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

OVERVIEW OF PACKAGE -II

 The other major work in Package –II is construction of


Bridge at CH.47+294 ( I-Girder) over River Ngenpui of
span 85.9m
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
PROGRESS ON CONSTRUCTION OF
BRIDGES UNDER PACKAGE –II
1. Construction of Bridge over River Ngenpui

1. Abutment A1- Raft reinf work completed


2. Abutment A2- Concrete casting casted upto bottom of
abutment cap..
3. Pier P1 - Earthwork excavation yet to be started
4. Pier P2 - 10th lift casted

Deadline of completion committed by contractor ( substructure )


MAY 2019
Deadline of completion committed by contractor ( total works )
OCT 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI ABUTMENT A1
Bar chart :

6
Total
5
Completed
4
Balance
3

0
Fdn. works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI ABUTMENT A1
Abutment A1- earthwork excavation is completed

Balance casting to be conducted upto height :11.210 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI ABUTMENT A2
Bar chart :

5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance

1.5
1
0.5
0
Fdn. Works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI ABUTMENT A2
Abutment A2- Concrete casting casted upto bottom of
abutment cap.

Balance casting to be conducted upto height :3.795 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI PIER P1
Bar chart :

25

20

15 Total
Completed
10 Balance

0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI PIER P1
Pier P1 - Earthwork excavation yet to be started

Balance casting to be conducted upto height :28.00 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI PIER P2

Bar chart :

25

20

15 Total
Completed
10 Balance

0
Fdn. Works Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

NGENPUI PIER P2
Pier P2 - Casting completed upto 10th lift pier coloumn

Balance casting to be conducted upto height :16.00 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

OVERVIEW OF PACKAGE -III


 A Total 6 nos of Major and minor Bridges are to be
constructed under this Package which are namely:

Sl. Bridge Name of Bridge CHAINANGE Span


No No.
1. Br-12 Bauklawk CH.(67+923) 20.00 m (approx)
2. Br-13 Lunghauka CH.(69+950) 38.00 m (approx)
3. Br-14 Khwaraup CH.(77+750) 74.00m (approx)
4. Br-15 Hmwangbu CH.(82+65) 85.90m (approx)
5. Br-16 Zochate CH.(84+600) 30.00m (approx)
6. Br-17 Zocha CH.(87+18) 58.90m (approx)
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF BRIDGES


UNDER PACKAGE –III
1. Bridge over River Bawklak

1. Abutment A1- Earthwork excavation yet to be started


2. Abutment A2- Earthwork excavation yet to be started
Deadline of completion committed by contractor ( substructure )
APRIL 2019
Deadline of completion committed by contractor ( total works )
JUNE 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT
PROGRESS ON CONSTRUCTION OF BRIDGES
UNDER PACKAGE -III
2. Bridge over River Lunghauka

1. Abutment A1- Casting completed upto 3rd lift


2. Abutment A2- Casting completed upto 6th lift

Deadline of completion committed by contractor ( substructure )


FEB 2019
Deadline of completion committed by contractor ( total works )
APRIL 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

LUNGHAUKA ABUTMENT A1
Bar chart :

12

10

8
Total

6 Completed
Balance
4

0
Fdn Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

LUNGHAUKA ABUTMENT A1
Abutment A1- Casting completed upto 2nd lift of abutment column

Balance casting to be conducted upto height :11.906m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

LUNGHAUKA ABUTMENT A2
Bar chart :

12

10

8
Total

6 Completed
Balance
4

0
Fdn Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

LUNGHAUKA ABUTMENT A2
Abutment A2- Casting completed upto 6th lift

Balance casting to be conducted upto height :7.106m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF
BRIDGES UNDER PACKAGE -III
3. Bridge over River Khwaraup

1. Abutment A1- Casting completed upto bottom of Abutment cap


2. Abutment A2- Casting completed upto bottom of Abutment cap
3. Pier P1 - Casting completed upto 10th lift pier coloumn
4. Pier P2 - Casting completed upto 12th lift pier coloumn

Deadline of completion committed by contractor ( substructure )


FEB 2019
Deadline of completion committed by contractor ( total works )
MAY 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP ABUTMENT A1
Bar chart :

5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance

1.5
1
0.5
0
Fdn works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP ABUTMENT A1
Abutment A2- Casting completed upto bottom of abutment cap

Balance casting to be conducted upto height :2.495m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP ABUTMENT A2
Bar chart :

5
4.5
4
3.5
Total
3
Completed
2.5
2 Balance

1.5
1
0.5
0
Fdn works Base slab Rtn/Wall Abutment cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP ABUTMENT A2
Abutment A2- Casting completed upto bottom of abutment cap

Balance casting to be conducted upto height :2.495m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP PIER P1
Bar chart :

20
18
16
14
12 Total
10
Completed
8
Balance
6
4
2
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP PIER P1
Pier P1 - Casting completed upto 10th lift pier coloumn

Balance casting to be conducted upto height :8.171m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP PIER P2
Bar chart :

20
18
16
14
12 Total

10 Completed

8 Balance
6
4
2
0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

KHWARAUP PIER P2
Pier P2 - Casting completed upto 12th lift pier coloumn

Balance casting to be conducted upto height :6.171m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF
BRIDGES UNDER PACKAGE -III
4. Bridge over River Hmwangbu
1. Abutment A1- Casting yet to be started.
2. Abutment A2- Raft Fdn casting completed
3. Pier P1 - Raft Fdn reinf. Work in progress
4. Pier P2 - Casting completed upto 8th lift pier coloumn

Deadline of completion committed by contractor ( substructure )


FEB 2019
Deadline of completion committed by contractor ( total works )
NOV 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU ABUTMENT A1
Bar chart :

4
Total

3 Completed
Balance
2

0
Fdn Base slab Rtn/Wall Abutment cap-to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU ABUTMENT A1
Abutment A1- earthwork excavation is completed

Balance casting to be conducted upto height :10.701m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU ABUTMENT A2
Bar chart :

4
Total

3 Completed
Balance
2

0
Fdn Base slab Rtn/Wall Abutment cap-to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU ABUTMENT A2
Abutment A2- Raft Fdn casting completed

Balance casting to be conducted upto height :10.701m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU PIER P1
Bar chart :

16

14

12

10 Total

8 Completed
Balance
6

0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU PIER P1
Pier P1 - Raft Fdn reinf. Work in progress

Balance casting to be conducted upto height :18.577 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU PIER P2

Bar chart :

16

14

12

10 Total

8 Completed
Balance
6

0
Fdn Base slab Rtn/Wall Pier Cap to FRL
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

HMWANGBU PIER P2
Pier P2 - Casting completed upto 8th lift pier coloumn

Balance casting to be conducted upto height :8.97 m


PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF BRIDGES


UNDER PACKAGE -III
5. Bridge over River Zochate
1. Abutment A1- Work yet to be started
2. Abutment A2- Work yet to be started

Deadline of completion committed by contractor ( substructure )


JUNE 2019
Deadline of completion committed by contractor ( total works )
DEC 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF BRIDGES


UNDER PACKAGE -III
6. Bridge over River Zocha
1. Abutment A1- Work yet to be started
2. Abutment A2- Work yet to be started
3. Pier P1 - Work yet to be started

Deadline of completion committed by contractor ( substructure )


JUNE 2019
Deadline of completion committed by contractor ( total works )
DEC 2019
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

PROGRESS ON CONSTRUCTION OF BRIDGES


UNDER PACKAGE -III
6. Bridge over River Zocha
PROGRESS ON KALADAN MULTI MODAL TRANSIT TRANSPORT
PROJECT

THANK YOU