POWER PLANT AND

OPCC TRANSMISSION PROJECT

Progress : September 2012


Power Plant Executive
Summary
Item Bobot Progres

 Offshore
a.Engineering 7.30% 7.05%
b.Procurement 65.7% 62.49%

 Onshore
a.Construction 27% 23.81%

Overall 100% 93.35%


Highlight of Activities
A. Commissioning of unit #1 equipments such as :
1. Boiler
2. ESP
3. MCC
4. Transformer

B. Commissioning of BOP such as CW System, Demine Plant,


LDO Pump, DG Black start

C. Commissioning of DCS

D.Construction work in Boiler #2, ESP #2, CHP, AHP, Fire


Fighting System, CEMS, Fencing was on progress

3
Milestones
No. Event Target Date

1 Boiler 1 First Firing Dec 2012


2 Boiler 2 First Firing April 2013
3 Main Transformer Energize Dec 2012
4 1st Synchro Unit #1 Jan 2013
5 1st Synchro Unit #2 May 2013
6 Unit #1 Provisional Feb 2013
Acceptance
7 Unit #2 Provisional May 2013
Acceptance / Project
Completion
4
Executive Summary of Supporting Facilities

Facilities Status

a. Water Treatment Plant (WTP) Completed


b. Water Pipe Line Completed
c. Switchyard Completed
d. Remote Substation (RSS) for Interfacing with Completed
GI Tanjung
e. 70kV Transmission Line up to RSS (Common Completed
Corridor)
f. 70kV Transmission Line up to OPCC On going
g. Coal Road in Power Plant and Ash Dyke Completed
h. Additional Bay for OPCC in Switchyard On going
i. Additional Bay for 20kV Transformer in On going
Remote Substation
j. 20kV Distribution Line for WTP On going
OPCC 66kV T/L Executive Summary for
September 2012
Description Progress Schedule Remarks
Overall Progress 86.7 %
- Engineering 100 %
- Procurement 94 %
- Construction 77 %
- Commissioning 0%

Completion Target End of November 2012


Project Status
Item Description Status Remarks
1 Engineering Almost complete
2 Procurement
- Lattice Tower Material 16 on site complete on
site
- Pole Tower Material 23 on site complete on
site
- Insulator On shipment ETA first week
of Nov 2012
- Conductor, OPGW, GSW On site Complete
- Foundation Material On site Complete
Project Status
Item Description Status
3 Construction
- Survey and soil test Complete
- Foundation work -Lattice and Pole : Complete
- Tower Erection - Lattice : 16 tower erected
- Pole : 7 pole erected, delay due
to crane unavailability
- Conductor stringing - on going progress from Lattice #1
until #14
- Run of Wire Land - completed
Clearing

4 Commissioning Tentative on November 12


Project Activities in Pictures

Boiler unit 1 and 2 Chimney, ESP, Boiler

Steam Turbine Generator Electrostatic Precipitator (ESP)


Water Pond Raw Water Reservoir

Coal Handling Plant (CHP) Demine Water Tank


Coal Road Ash Dyke

Switchyard Transmisi 70kV


Water Pipe Line Remote Substation

Clarifier Tank WTP Water Intake


END