NO Area Activities performed today

1.Intake punp house excavation


1 Intake water pump house
2.Intake dewatering pump installation

1.Workshop building pour concrete for pedestal--completed


2 Workshop 2.Workshop bolt final check--completed
3.Column base waterproofing work

3 Electric building Electric building excavation

1.Marine excavation
2.Marine site leveling for Pond discharge line
4 Marine works 3.The GRP pipeline from Settlement pond to marine
4.GRP pipe butt entanglement
3.Marine cause way backfilling started

1.IWP Water tank area excavation


5 IWP Water tank area 2.2#tank formwork ongoing
3.2#Tank rebar work ongoing

1.WTTCO Water tank area excavation


6 WTTCO Water tank area
2.8# water tank Bedding pouring completed 50%

7 PV PV area leveling work ongoing

Camp and office Temporary facilities work, HSE team


8 Others
inspection,Security,watchmen, Site housekeeping etc