Civil Department

Daily Report
Date : 22-November-2020

Site Inspector : Engr. Alvin Badecao


A: Inspected Activities on site:
Description Location Status Remarks
Civil.:
1. Rebar & Formworks for Neck Column Zone-9 Completed 1. Provide vertical &
@Drivers Bldg. Horizontal alignment for
checking.
2. Reflect changes of Fnd/Col.
In the Shop Drawing.
2. Survey checking for Blinding @ Steel Zone-9 Completed Marking/staking shall be
shade area marked actual on the
ground.
3. Rebar’s for Pipe Concrete surround Addt’l Completed Extend pipe & steel until
@ Control room the green areas
4. Replacement of existing GI Roofing Zone-3 Ongoing Submit Inspection Request
@ Mechanical workshop for proper coordination
5. Compaction & installation of Interlock Zone-6 Ongoing 1. Compaction complies as per
tiles @ Old HQ QCS
2. Submit Inspection Request
for proper coordination

B. Transmittals:
Description Action By Status Remarks

1. N/A
i)

C. Concrete Pouring Schedule


Estimated Time of
Structure Element/Location Remarks
Qtty(m³) Casting
1. Blinding @ Steel Shade area-Zone 9 37 7:00 PM 53m³-Completed
2. Neck Column @ Drivers &Helpers 3.6 5:00 PM 5m³-Completed
Bldg.-Zone 9

D. Problems On Site
Action to be
Description Status Corrective action
taken By
1. Approval for submittal of Design EGEC-Civil Pending
drawing for Steel shade bldg.-Zone 09
2. No QA/QC from AMCT was AMCT PM Pending
designated on this project for proper
coordination

Process Signature : Conformed By:


Engr. Alvin Badecao- QA/QC Civil inspector Engr. Amr Eltony- Projects Manager