You are on page 1of 7

Discipline Document Number

BP BERAU LTD.
Civil Engineering
076-WPK-CV-5002

Project/MoC No.
Author’s Org.
Engineering Next Revision Date
N/A

BOG CLIFF PROTECTION

ISSUE TECHNICAL APPROVAL


REV DATE BY
DESCRIPTION APPROVAL AUTHORITY
Iwan WIsnu Refrizal
0 13-8-2011 Juliano/Zulkifli For Approval Mustapha/Partha Boestaman/John
Siregar Wijaya Wallace
Re-route Effluent Water from Desalination Package from Open Ditch to -13 M LAT Common Outfall

1. Description of Change

Section
Description of Change Rev.
Affected

Page 2 of 6
BOG CLIFF PROCTECTION

TABLE OF CONTENT

Page

1. GENERAL…..………………………………………………………………… 4
2. REFERENCE …………… …………………………………………………… 4
3. LAYOUT ……………………………………………………………………… 5
4. SCOPE OF WORK………………………………………………………….. 6
5. MATERIAL TAKE OFF……………………………………………………….. 7
 DRAWING

Page 3 of 6
BOG CLIFF PROCTECTION

1. GENERAL
BOG compressor is located on cliff beside LNG jetty abutment; the distance of outer
perimeter fence to edge of cliff is approximately 9.2 m. From soil boring test, the toe of cliff
is classified as hard soil with N SPT > 30. However, the soil is not strong enough to protect
toe from erosion and sea abrasion. This condition become critical since equipments are
standing on cliff and protection of cliff is must for long-term use.

2. OBJECTIVE
This work package will give information of scope of work that shall be completed to protect
BOG cliff from sea abrasion.

3. LAY OUT

Aerial picture on July 2009

4. REFERENCE
(1) Project Specifications

900-SPE-CV0-1001 Detail Engineering Design Data For Civil & Structure


900-SPE-CV0-1002 Detail Engineering Design Data For Marine Facilities

Page 4 of 6
BOG CLIFF PROCTECTION

900-SPE-RC0-1001 Construction Specification for Concrete Work


900-SPE-CV2-1001 Construction Specification for Earth Work
071-RPT-CV-5001 Bog Cliff Visual Inspection Report
900-VDR-POC-C3100 Design Calc. For Shore Protection-Marine Facilities Works

5. SCOPE OF WORK
Scope of work covered in this package is as follows:
1. Supply and off load rock materials from the Barge at Construction Jetty. Ensure that
the Barge with its full draft can approach to the shore line close to Construction Jetty
during high tide with assistance of shallow draft Tug boats.
2. Off load the rocks from the barge onto the shore using excavators.
3. Conveying the rocks to the designated stock area by provide access road from
construction jetty to BOG cliff
4. Surveying, by a competent surveyor to layout, setting and install the batter board as
a guide for horizontal and vertical control during the course of work
5. Preparing shore line surface (cleaning, grading) using excavator. Particular care must
be taken to avoid any damage to the existing cliff face, as this could increase the risk
of failure of the cliff material. The cliff face should be inspected daily during the
construction operations for signs of any cracking that could lead to falling material,
which would need to be stabilized.
6. Installing the geofabric (double layer) along the shore line
7. Construct amour rock under layer to the design specifications
8. Survey to check the under layer amour rock
9. Construct top layer amour rock
10. Survey to check the top layer amour rock
11. Finishing work

All work shall comply with specification and fulfill Guidance of Certification (GOC)
requirement

Page 5 of 6
BOG CLIFF PROCTECTION

6. MATERIAL TAKE OFF

Remarks
No Description Specification Qty Unit

I Preparation
Site Preparation (include mob-
- demob, demarcation, surveying, ls
1.00 -
setting & measuring)
- Excavation m3
759.55 -

Woven
II Geofabric Single Layer 250 gr/m2, tensile m2
2,257.75 -
2330N/5cm

Woven
III Geofabric Double layer 250 gr/m2, tensile m2
2,255.00 -
2330N/5cm

ASTM C88, ASTM C


Min density
IV Core Aggregate 5-20mm 535, ASTM C 131 m3
1,198.15 2550 kg/m3
ASTM C 127

ASTM C88, ASTM C


V Under Layer Rock 70-90kg 535, ASTM C 131 m3 Min density
1,514.70
ASTM C 127 2550 kg/m3

ASTM C88, ASTM C


Min density
VI Armor Rock 700-900kg 535, ASTM C 131 m3
2,838.00 2550 kg/m3
ASTM C 127

ATTACHMENT
 DRAWING

Page 6 of 6

You might also like