Proposal ID :24549

Initiated On :18-Mar-2024
13:11:04

e Proposal
---------------

Proposal in Circulation

Committee MCC-P&P
SBU/Department Engineering & Projects / Engg.&Proj.-Vashi Terminal
Subject Group Extension of Completion Delivery Date(CDD)
Subject Proposal for Extension of CDD against PO No. 22000353-OQ-10120 (SAP PO No:
5200013593) dated 03.01.2023 placed on M/s Hariom Builders for Structural Shed Works
at Vashi Terminal

Details :

Subject: This proposal is originated to seek approval of MCC-P&P for extension of completion period for PO
No. 22000353-OQ-10120 (SAP PO No: 5200013593) dated 03.01.2023, placed to carry out Structural Shed
Works at Vashi Terminal on M/s Hariom Builders.

Background:

Details of PO No. 22000353-OQ-10120 (SAP PO No: 5200013593) dated 03.01.2023, placed towards
Structural Shed Works at Vashi Terminal are as below:

JOB DESCRIPTION Structural Shed Works at Vashi Terminal

CONTRACTOR M/s. Hariom Builders

PURCHASE ORDER 22000353-OQ-10120 (SAP PO No: 5200013593)

• 7 Months for Phase-I completion


• 17 Months for Phase -II completion (Which includes 3
DELIVERY PERIOD months of stabilisation period of Phase-I facilities)

PO VALUE 1784.44 Lakhs


SCHEDULED DATE OF COMPLETION
02-08-2023
OF PHASE-I WORKS

SCHEDULED DATE OF COMPLETION


02-06-2024
OF PHASE-II WORKS

For extension of completion period,


EXTENSION SOUGHT • Up to 30-04-2024 for Phase-I Completion
• Up to 07.01.2025 for Phase-II Completion

PO No. 22000353-OQ-10120 (SAP PO No: 5200013593) dated 03/01/2023 was placed on M/s. Hariom
Builders towards Structural Shed Works at Vashi terminal with phase wise completion schedule as detailed
above. This PO was approved by MCC-P&P vide meeting No. MCC-P&P/21/2022-23 (e-Proposal ID:89498),
Meeting date:05.12.2022 (Annexure-I).

Scope of job includes,

Phase-I:

• Design, Approval, fabrication and erection of Tank truck gantry- I & II, Pump House – I & II, Gate
Complex, Trestle bridge for Electrical and automation cables, Pipe trestle, TT Checking Platform,
shifting of calibration shed and DU Shed with 7 months completion period

Phase -II:

• Completion of Tank Truck Gantry -III and associated Pipes and cable trestles, Dismantling of balance
existing TT Gantry with 17 months overall completion period

Current Status of Work:


Sr. No. Structural Facility Present Status of Work

1. Erection of gantry structure is completed.


1 Tank Truck Gantry -I 2. Rubble soling, PCC and RCC for driveway completed.
3. Roof sheeting work is under progress.

1. Erection of gantry structure is completed.


2 Tank Truck Gantry - II 2. Rubble soling, PCC and RCC for driveway completed.
3. Roof sheeting work is under progress.

1. All Column foundation works are completed.


2. All Structural Material received at site. Bridge: Part-
3 Admin to TTG Opposite Trestle
I,II,IV,V and VI’s erection completed and assembly of
the bridge: Part-III is under progress.

4.1 Pump House-I 1. Hard rock breaking/ excavation is under progress.

1. Hard rock excavation/ breaking is completed till


structural footing and pump foundation bottom.
2. Structural Column PCC and RCC completed for all 18
4.2 Pump House-II No. of footings and 6 No. of Pump foundation PCC
completed, RCC works are under progress.

1. Structural Column foundation works completed for 6


No. of columns and Excavation works are under progress
for remaining 4 No. of column footings.
5 Pipe Trestle (PH to TTG I) 2. All structural material received at site. Assembly of
structure is under progress.

1. Design of structure completed.


2. Fabrication of structure is under progress.
5 TT Out Gate Checking Platform

1. All Column foundation works are completed.


2. Structural material received at site. Assembly of
structure is under progress.
6 TT in Gate Checking Platform 3. Structural Column footing Work: Excavation is under
progress.
7 Main Gate Complex 1. Design of structure is in progress.

1. Design of structure is completed and fabrication is under


progress.
2. Structural column footing Work: Excavation and PCC
8 Design of Calibration Shed
completed. RCC Work is under progress.

1. All Column foundation works are completed.


2. Structural Material received at site.
9 MCC to QC Lab Trestle
3. Erection of bridge-I, III, IV & VI are completed and
Bridge-II &V assembly is under progress.

1. Admin Area, DU Shed Area and Planning Building


Area: Column foundation works completed. Brick work
10 Grill Fencing
is under progress.
2. Fencing material received at site.

Details of Proposal:

PO was issued on 03/01/2023 and vendor attended Kick-off meeting on 09/01/2023. Vendor has commenced
the design of various structures and supplied the Tank Truck Gantry structures and Pump House Structures by
March,2023, however, could not complete the Phase-I work as per PO scope before CDD due to following
reasons:

1. Vashi Terminal Revamping project includes construction of new facilities in the existing D-99 plot and
in the newly leased TT01 plot. In TT01 plot, there were approx. 501 tress which needs to be cut/
transplanted before commencement of the construction activities.
2. Tree felling permission for TT01 plot was received vide “Permission for felling and transplantation of
trees on plot no.TT01 (ref: No/MIDC/EE&SPA/Dn.II/FMS/I/13130/2023)” dated 14.08.2023 (
Annexure-II) with cooling period of 15 days.
3. Subsequently, after the cooling period, trees were cleared/ transplanted and Workfront for construction
of facilities was handed over to M/s Hariom Builders on 04.09.2024. Hence, effectively, vendor could
commence the construction works from 04.09.23.
4. The following are the facilities, which has to be completed in Phase-I and are located in the TT01 plot
area,
1. 8 Bay Tank Truck Filling Gantry -I
2. Pump House- I & II
3. Calibration Shed
4. Pipe Trestle between Tank truck filling Gantry-I and Pump House-I
5. Connecting trestle between Tank Truck filling Gantry -I & II
6. Trestle bridge from administrative building to Tank Truck Filling Gantry Area
7. Grill Fencing around Tank truck filling gantry

Though M/s Hariom builders has completed design, fabrication and supply of structures of TT Gantry-I & II,
Pump House-I &II by March-2023, could not complete the civil foundation, structural erection and associated
works due to the reasons mentioned above. Hence, extension of CDD is requested basis the following,

1. Work front was handed over to M/s Hariom Builders in the TT01 plot on 04.09.2023 after tree cutting
and transplantation. Hence, as per PO’s Phase-I completion schedule, 7 months required to complete the
facilities of Phase-I from the date of hand over, i.e., till 03.04.2024.
2. However, hard rock strata were encountered in both Pump Houses- I & II, which is delaying the
excavation for structural footing, Pump foundation, Cable trench and associated civil works. Presently,
hard rock breaking, PCC and RCC for Pump House-II structural footing is completed. RCC works of
pump foundation is under progress.
3. Hard rock breaking of Pump House-I is in progress and it is estimated to get completed by 31.03.24.
Subsequently, it is estimated that 1 month is required to complete the structural civil foundation, pump
foundation and structural erection works, i.e., up to 30.04.2024.
4. Tentatively commissioning of Phase-I facilities are planned in the month of July’2024. Subsequently,
considering stabilization period of 2 months, it is estimated to hand over Phase-II front to vendor in the
1st week of September’2024. Subsequently, it is estimated that 4 months is required to complete the
facilities of Phase-II, i.e., up to 07.01.2025.

View above, this e-proposal is initiated for approval of extension of CDD as given below,

1. Schedule for completion of Phase-I facilities – Till 30.04.2024


2. Schedule for completion of Phase-II facilities including 2 months of stabilization period for Phase-I
facilities as per PO - Till 07.01.2025

Vendor has submitted request letter ‘TE/H/IND/HOBMH0018/23-24/0001’ dated 16/03/2024 (Annexure III)
for extension of completion period of Phase-I facilities till 30.04.24 and overall completion period till
07.01.2025.

Vendor has also agreed to execute the job in same rates, terms and conditions of the Purchase Order.

Approving Authority:

As per Clause 11.1.a. of Chapter VI of EAM, Authority of approval of extension of contract /PO beyond
delivery date, for reasons not attributable to contactor with withdrawal/ waiver of LD, after expiry date (of
deliver/ completion period), for the contacts/ POs approved by contracts committee and above lies with
Original Approving Authority (Max. EC) with financial Concurrence.

Approval Sought For :

As per Clause 11.1.a. of Chapter VI of EAM, Authority of approval of extension of contract /PO beyond
delivery date, for reasons not attributable to contactor with withdrawal/ waiver of LD, after expiry date (of
deliver/ completion period), for the contacts/ POs approved by contracts committee and above lies with
Original Approving Authority (Max. EC) with financial Concurrence.

Hence, approval of MCC-P&P is sought for extension of CDD of PO No. 22000353-OQ-10120 (SAP PO No:
5200013593) dated 03/01/2023 placed on M/s Hariom Builders for Structural sheds works at Vashi Terminal,
till 30.04.2024 for Phase-I facilities and till 07.01.2025 for Phase-II facilities, as the delay is not attributable to
the party. Kindly approve.

Initiation - N VINOTHKUMAR - 31961940 on 18-Mar-2024 15:14:56

Approval of MCC-P&P is sought for extension of CDD (extension of contract /PO beyond delivery date) of PO No. 22000353-OQ-
10120 (SAP PO No: 5200013593) dated 03/01/2023 placed on M/s Hariom Builders for Structural sheds works at Vashi Terminal,
till 30.04.2024 for Phase-I facilities and till 07.01.2025 for Phase-II facilities for reasons are not attributed to contractor.
Review - KHOMANE NILESH RAMDAS - 31949100 on 18-Mar-2024 15:14:56

Attachments :

N VINOTHKUMAR(31961940) on 2024-03-18 13:07:29.0

Annexure 1
2024.03.18.13.07.28.969_Annexure I_MCC approval note
for negotiation and order placement-with annexures.pdf

Annexure 2
2024.03.18.13.07.29.031_Annexure II_MIDC Tree Felling-
Transplantation Permission for TT-1_14082023.pdf

Annexure 3
2024.03.18.13.07.29.120_Annexure III_HOB RQ LETTER
CDD EXTEN.pdf