shed-II Site handover 3rd & 4th Bay- 28.07.21 & 01.10.21 respectively
Column Foundation 24 nos. 24 nos. Completed on 11.02.22
Column erection 24 nos. 24 nos. Completed on 11.05.22
(Bay 3rd & 4th ) PCC flooring 2640 Sq. M 2640 Sq. M Completed on 02.07.22
(19.5M X 66M Each) RCC flooring 2640 Sq. M 2640 Sq. M Competed on 27.09.22
HD Flooring 2640 Sq. M 2640 Sq. M Competed on 28.09.22
Roof Truss Work 24 nos. 24 nos. Completed on 05.08.22
Roof Purlings 408 nos. 408 nos. Completed on 08.08.22
Photographs Roof Sheeting Work 3000 Sq.M 3000 Sq.M Completed on 22.10.22
Gabeling of A- Shop 4 Nos Front Side Gabelling work completed on 17.10.2022
Shed Back Side Gabelling work completed on 15.10.2022
Crane Girder erection 264M 264M Completed on 28.10.22
Crane Girder Rail fixing 264 M 264 M Completed on 02.12.22
Electrification of the Lump-Sum 0 Work started on
shed 03.01.23
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS
A shop New Total Scope work Qty.
Qty. Executed Remarks
Till date
shed-III Site handover Handed over to Con/HWH on 07.09.2022. Dismantling work started on
12.09.22
Column Foundation 20 nos. 10 Work Started on 22.11.2022
(Bay 5th & 6th) Column erection 20 nos. 0 Yet to be started
(19.5M X 54 M Each)
PCC flooring 2106 Sq. M 173.85 Sq.M Yet to be started
RCC flooring 2106 Sq. M 0 Yet to be started
Civil PDC- 19.02.23
HD Flooring 2106 Sq. M 0 Yet to be started
Roof Truss Work 20 nos. 0 Yet to be started
Roof Purling 374 nos.
Roof Sheeting Work 2500 Sq.M 0 Yet to be started
Photographs Gabeling of A- Shop 4 Nos 0 Yet to be started
Shed
Side Sheeting Work 54 M 0 Yet to be started
Crane Girder erection 216 M 0 Yet to be started
Crane Girder Rail fixing 216 M 0 Yet to be started
Electrification of the Lump-Sum 0 Yet to be started
shed
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS
Widening & Total Scope work Qty.
Qty. Executed
Till date
Remarks
50
Physical Progress (%)
Overall TDC 31.08.2024
BGB – IMPROVEMENT OF INFRASTRUCTURE FOR CRITICAL WORKS CENTRE CONSTRUCTION
OF WORKSHOP BMF/BGB
Civil 671573512.00 6649242.00 6649242.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Electrical 172073002.00 1703693.00 0.00 1703693.00 0.00 0.00 0.00 0.00 0.00 0.00
LLH- Modernization of PB item no. 552
1 Workshop of 22-23
Mechanical 377109513.00 10517388.5 0.00 10517388.45 0.00 0.00 0.00 0.00 0.00 0.00
Total 1220756027.00 18870323.45 6649242.00 12221081.45 0.00 0.00 0.00 0.00 0.00 0.00
Civil 89172906.00 874158.00 0.00 874158.00 882900.00 0.00 882900.00 0.00 0.00 0.00
Liluah (J-Shop)-Ac OVH PB item no. 559 Electrical 8221058.00 80591.00 0.00 80591.00 81397.00 81397.00 0.00 0.00 0.00 0.00
2 facilities of 22-23 Mechanical 21817090.00 0.00 0.00 0.00 208575.00 0.00 208575.00 0.00 0.00 0.00
Total 119211054.00 954749.00 0.00 954749.00 1172872.00 81397.00 1091475.00 0.00 0.00 0.00
Civil 11642990.06 21110.73 0.00 21110.73 105553.65 0.00 105553.65 52776.83 0.00 52776.83
Electrical 20628856.00 38871.00 0.00 38871.00 194355.00 0.00 194355.00 97178.00 0.00 97178.00
LLH- Upgradation &
Augmentation of UWB item no. Mechanical 2530050.00 0.00 0.00 0.00 25050.00 0.00 25050.00 0.00 0.00 0.00
3 Infrastructural facility for 266of 22-
OVH of RMPU during POH 23
of LHB coaches Total 34801896.06 59981.73 0.00 59981.73 324958.65 0.00 324958.65 149954.83 0.00 149954.83
Civil 18965974.93 34388.55 0.00 34388.55 171942.77 0.00 171942.77 85971.00 0.00 85971.00
LLH- improvement in UWB item no. Electrical 14869593.00 38871.00 0.00 38871.00 194355.00 0.00 194355.00 97178.00 0.00 97178.00
4 infrastructure for Critical 267of 22-
Coach Components Shops 23 Total 33835567.93 73259.55 0.00 73259.55 366297.77 0.00 366297.77 183149.00 0.00 183149.00
27 Construction of New A&HT Shop (1 st & 2nd Bay) Work completed 11.03.2022/10.11.2022