You are on page 1of 20

MODERNIZATION OF WORKSHOP

Brief Work Particulars By Cons. Dept.


PB Item No. Plan 552 of 2022-23 & PH-42 On-going  Modification and extension of A & HT shop. TDC: 28.02.23
Head Work  Widening & conversion of traverser Bay-2 from pit type to surface type.
Year of Sanction: 2008-09 TDC: 07.02.2023
Construction of J-Shop Bay-II: LOA issued on 07.11.22. Site handed over on
Last Sanction Cost
(in Cr.) 122.57 19.11.22. work started on 25.11.22. PDC – Not yet received.
M&Ps:
Expenditure till As per IRPSM As data
02 nos 80T Surface traverser will be provided through M&P program 20-21
date (in Cr.) received under PH-41. Procurement is under progress at COFMOW. Tender Case
no.OP-207511, TOD – 31.08.22. Case is under TC.
Installation of Coach Shot Blasting plant completed. Commissioning trial
started on 17.01.2023. Financial liability is pending. Balance 20% payment will
be made within 31st March,2023.
108.15 134.20
02 nos. 25T EOT Cranes - Indent has been placed and forwarded to HQ. on
14.09.22, onward forwarded to COFMOW on 14.10.22.
10 nos. fabricated racks: Material received on 31.08.22. Physical work
completed. Completion of financial liability is under progress.
Work List of completed Work
Financial Progress (%) 88.24 109.48
Completed
Physical Progress 90.00%
Overall TDC 31/03/2023
(Last mile Work)
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS 
Qty. Executed Remarks
Total Scope work Qty. Till date
Column Foundation & 36 Nos 36 nos. Completed on 25.08.21
A shop New erection
shed-I HD Flooring 2640 Sq. M 2640 Sq M Completed on 21.01.22
(Bay 1st & 2nd ) Roof Sheeting Work 3000 Sq.M 3000Sq.M Completed on 09.12.21
(19.5M X 66M Each) Gabeling of A- Shop 04 Nos 04 nos. Completed on 18.12.21
Shed (Front & Back
side)
Side Sheeting Work 66 M 66 M Completed on 09.12.21
(Northern end)
Photographs Crane Girder erection 264M 264 M Completed on 15.10.21
Crane Girder Rail fixing 264 M 264 M Completed on 23.08.22
Electrical Work Lump-Sum Completed Completed on 15.08.22
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS 
A shop New Total Scope work Qty.
Qty. Executed
Till date
Remarks

shed-II Site handover 3rd & 4th Bay- 28.07.21 & 01.10.21 respectively
Column Foundation 24 nos. 24 nos. Completed on 11.02.22
Column erection 24 nos. 24 nos. Completed on 11.05.22
(Bay 3rd & 4th ) PCC flooring 2640 Sq. M 2640 Sq. M Completed on 02.07.22
(19.5M X 66M Each) RCC flooring 2640 Sq. M 2640 Sq. M Competed on 27.09.22
HD Flooring 2640 Sq. M 2640 Sq. M Competed on 28.09.22
Roof Truss Work 24 nos. 24 nos. Completed on 05.08.22
Roof Purlings 408 nos. 408 nos. Completed on 08.08.22
Photographs Roof Sheeting Work 3000 Sq.M 3000 Sq.M Completed on 22.10.22
Gabeling of A- Shop 4 Nos Front Side Gabelling work completed on 17.10.2022
Shed Back Side Gabelling work completed on 15.10.2022
Crane Girder erection 264M 264M Completed on 28.10.22
Crane Girder Rail fixing 264 M 264 M Completed on 02.12.22
Electrification of the Lump-Sum 0 Work started on
shed 03.01.23
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS 
A shop New Total Scope work Qty.
Qty. Executed Remarks
Till date
shed-III Site handover Handed over to Con/HWH on 07.09.2022. Dismantling work started on
12.09.22
Column Foundation 20 nos. 10 Work Started on 22.11.2022
(Bay 5th & 6th) Column erection 20 nos. 0 Yet to be started
(19.5M X 54 M Each)
PCC flooring 2106 Sq. M 173.85 Sq.M Yet to be started
RCC flooring 2106 Sq. M 0 Yet to be started
Civil PDC- 19.02.23
HD Flooring 2106 Sq. M 0 Yet to be started
Roof Truss Work 20 nos. 0 Yet to be started
Roof Purling 374 nos.
Roof Sheeting Work 2500 Sq.M 0 Yet to be started
Photographs Gabeling of A- Shop 4 Nos 0 Yet to be started
Shed
Side Sheeting Work 54 M 0 Yet to be started
Crane Girder erection 216 M 0 Yet to be started
Crane Girder Rail fixing 216 M 0 Yet to be started
Electrification of the Lump-Sum 0 Yet to be started
shed
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS 
Widening & Total Scope work Qty.
Qty. Executed
Till date
Remarks

Conversion Site handover 02.02.2022


of Traverser Work started 11.02.2022
Dismantling/excavation 4263 Sq. M 4163 Sq. M Work under process
Bay-II
of Work site
Sand filling 4263 Sq. M 4163 Sq.M Work under process
PDC- 07.02.2023 PCC 4263 Sq. M 4100 Sq.M Work under process
Raft Casting 4263 Sq. M 3750.5 Sq.M Work under process
Hume Pipe Laying 450 Sq. M 440 M Work under process
Beam for rail Laying 1050 M. 768 M Work under process
Photographs Rail Laying 1050 M 400 M Work started on 25.11.22
HD Flooring 4263 Sq. M 0 Yet to be started
DSL Column
foundation & erection 13 nos. 0 Yet to be started
LILUAH-MODERNIZATION OF WORKSHOP
ON GOING WORKS STATUS 
J-Shop Total Scope work Qty.
Qty. Executed
Till date
Remarks

Bay-II Work started on


Site handed over on 19.11.22.Dismantling work started on
25.11.22/03.01.23
Piling 153 Nos Yet to be started
Civil PDC- Piling Cap 32 Nos Yet to be started
Not yet received Column erection 32 nos. Yet to be started
PCC Flooring 1350 Sq.M Yet to be started
RCC Flooring 1350 Sq.M Yet to be started
HD Flooring of Bay 1350 Sq.M Yet to be started
Roof leg Girder 16 nos. Yet to be started
Photographs Roof truss 75 nos. Yet to be started
Roof parlings work 360 nos. Yet to be started
Roof Sheeting Work 2200 Sq.m Yet to be started
Side Sheeting Work 550 Sq. m Yet to be started
Crane Girder erection 183 M Yet to be started
Crane Girder Rail fixing 183 M Yet to be started
Laying of Track 183 M Yet to be started
Gutter 220 M Yet to be started
Rain Water Pipe 32 Nos. Yet to be started
Construction Side drain 106 M Yet to be started
Linking of yard with this shed. Lum-Sum Yet to be started
Electrical Lum-Sum Yet to be started
Liluah (J-Shop) - AC overhauling facilities
Brief Work Particulars
PB Item No.& Plan 559 of 2022-23 Ongoing Works
Head & PH-42
Year of Sanction 2015-16 Compressor Completed on 20.02.2022.
Room
Last Sanction Cost 11.42 J-shop 1st Bay Civil: Work completed except rail linking to Yard.
(in Cr.) (14.5m X Elect: Electrical work LOA issued on 01.11.2022. Work
91.5m) started on 24.11.22.
Mech: 02 nos. 25T EOT Cranes, sanction under M&P
program 20-21 in PH-41, AT No: OP-207410 dated 22/08/22.
Order placed on M/s Krane MFG. GAD approved on
06/12/2022. PSD- May’23.
Expenditure till As per As data
date (in Cr.) IRPSM received
6.13 6.85
Financial Progress (%) 53.71 52.99
Physical Progress (%) 80
Overall TDC 30.09.23
(As communicated by Con.
Deptt.)
J-SHOP AC OVERHAULING
ON GOING WORKS STATUS 
J-Shop AC Total Scope work Qty.
Qty. Executed
Till date
Remarks

Overhauling Work started on 14.09.2019


Bay-I Piling 153 Nos 153 nos. Work completed on 29.12.2021
Piling Cap 32 Nos 32 nos. Work completed on 25.02.2022
Column erection 32 nos. 32 nos. Work completed on 18.07.2022
Civil PDC- PCC Flooring 1350 Sq.M 1350 Sq.M Work Completed on 10.10.2022
15.12.2022 RCC Flooring 1350 Sq.M 1350 Sq.M Work Completed on 01.11.2022
HD Flooring of Bay 1350 Sq.M 1350 Sq.M Work completed on 01.12.2022
Roof leg Girder 16 nos. 16 nos. Work completed on 08.09.2022
Roof truss 75 nos. 75 nos. Work Completed on 23.09.2022
Roof parlings work 360 nos. 360 nos. Work Completed on 29.09.2022
Photographs Roof Sheeting Work 2200 Sq.m 2200Sq.M Work Completed on 10.11.2022
Side Sheeting Work 550 Sq. m 44 Sq.M Work Started on 12.12.2022
Crane Girder erection 183 M 183 M Work Completed on 08.11.2022
Crane Girder Rail fixing 183 M 183 M Work started on 31.10.2022
Laying of Track 183 M 183 M Work Completed on 25.11.2022
Gutter 220 M 220 M Work Completed on 22.11.2022
Rain Water Pipe 32 Nos. 32 nos. Work completed on 12.12.22
Construction Side drain 106 M 106 M Work Completed on 14.12.2022
Linking of yard with this shed. Lum-Sum 0 Yet to be started
Electrical Lum-Sum Work started on 24.11.22
LLH – UPGRADATION & AUGMENTATION OF INFRASTRUCTURAL
FACILITY FOR OVERHAULING OF RMPU DURING POH OF LHB COACHES
Brief Work Particulars
UWB Item No. 266 of 2022-23
Plan Head & PH-42 Work Status
Year of Sanction: 2018-19  Change of executive agency to CWM/LLH 23.09.2022.
Sanction Cost (Cr.) 3.52
 Detailed estimate prepared based on changed Civil scope of work and
Expenditure till As per As per data sanctioned on 14.11.22.
date IRPSM received
0 0  Location of the work has been changed. It is required to reframe the detailed
Financial Progress 0 0 estimate based on new requirements.
(%)
 One Indent for procurement of 01 no. EOT crane, CAP 3T from mechanical sub-
Physical Progress 0
(%) estimate has already been sent to HQ on 22.11.22 and require to be returned
Overall TDC 31.08.2024 back due to reframing of detail estimate.
(set by HQ)
LLH – IMPROVEMENT IN INFRASTRUCTURE FOR CRITICAL COACH
COMPONENT SHOPS
Brief Work Particulars
UWB Item No. Plan Head 267 of 2022-23 Work Status
& PH-42
Year of Sanction: 2018-19  Change of executive agency to CWM/LLH dated 23.09.2022.
Sanction Cost (Cr.) 3.38
 Detailed estimate prepared and sanctioned on 14.11.22.
Expenditure till date As per As per data
IRPSM received  Tender to be opened on 10.02.2023.
0 0

0 0  Indent for procurement of 03 nos. EOT crane, CAP 5T have been


Financial Progress (%) sent to HQ on 22.11.22 and onward forwarded to COFMOW on
29.12.22.
0
Physical Progress (%)
Overall TDC 31.08.2024
(set by HQ)
LLH - RENOVATION AND MODERNIZATION OF RAILWAY HOSPITAL

Brief Work Particulars


UWB Item No. Plan Head 325 of 2022-23 Work Status
& PH-51
Year of Sanction: 2009-10 · Ground Floor completed on 20.03.2021.
Sanction Cost (Cr.) 2.56 · First floor OPD to be constructed.
· Existing detailed estimate is required to be revised based on actual
Expenditure till date As per As per data requirements and rate reference.
IRPSM received · Electrical Work: LOA issued for Lift to M/S L T Elevator Pvt. Ltd. On
1.16 1.15 16.12.2022. PDC – 16.03.2023.
45.12 44.92
Financial Progress (%)

50
Physical Progress (%)
Overall TDC 31.08.2024
BGB – IMPROVEMENT OF INFRASTRUCTURE FOR CRITICAL WORKS CENTRE CONSTRUCTION
OF WORKSHOP BMF/BGB

Brief Work Particulars


UWB Item No. Plan 277 of 2022-23 Work Status Ongoing Status
Head
Year of Sanction: 2021-22 ❖ LOA has been issued on 18.08.2022 Civil Work- Yet to be
Sanction Cost (Cr.) 21.79 for civil construction work of shed. started
TDC -18.06.2023. Cost: 3.17 Cr.
❖ GAD submitted by the firm on
Expenditure till As per As per data 24.10.2022. Same is yet to be
date IRPSM received approved.
0 0 ❖ Indent for 5 Axis Machine submitted Mechanical Work- Yet
at COFMOW on 10.06.2022. Presently to be finalized.
0 0 at PCME/COFMOW level. Value: 18.41 Cr.
Financial Progress
(%) ❖ Indent for 5/2 ton EOT Crane will be
submitted after GA Drawing of shed -
Physical Progress 0 TDC 30.10.2022.
❖ Tender for Electrical Work will be Electrical: yet to be
(%) Finalized.
floated after construction of shed.
Overall TDC 0 Value: 0.1977 Cr.
CONTINGENCY. ENVIRONMENT & SPORTS FUND STATUS UNDER PH-42
Fig in Rs.
Contingency Environment Sports
PB/LB/UWB
Sl. No. Name of the work Branch Sanc. Cost Fund
item no. Fund available Exp. Balance Fund Fund available Exp. Balance Fund Exp. Balance Fund
available

Civil 671573512.00 6649242.00 6649242.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Electrical 172073002.00 1703693.00 0.00 1703693.00 0.00 0.00 0.00 0.00 0.00 0.00
LLH- Modernization of PB item no. 552
1 Workshop of 22-23
Mechanical 377109513.00 10517388.5 0.00 10517388.45 0.00 0.00 0.00 0.00 0.00 0.00

Total 1220756027.00 18870323.45 6649242.00 12221081.45 0.00 0.00 0.00 0.00 0.00 0.00
 
Civil 89172906.00 874158.00 0.00 874158.00 882900.00 0.00 882900.00 0.00 0.00 0.00
Liluah (J-Shop)-Ac OVH PB item no. 559 Electrical 8221058.00 80591.00 0.00 80591.00 81397.00 81397.00 0.00 0.00 0.00 0.00
2 facilities of 22-23 Mechanical 21817090.00 0.00 0.00 0.00 208575.00 0.00 208575.00 0.00 0.00 0.00
Total 119211054.00 954749.00 0.00 954749.00 1172872.00 81397.00 1091475.00 0.00 0.00 0.00
 
Civil 11642990.06 21110.73 0.00 21110.73 105553.65 0.00 105553.65 52776.83 0.00 52776.83
Electrical 20628856.00 38871.00 0.00 38871.00 194355.00 0.00 194355.00 97178.00 0.00 97178.00
LLH- Upgradation &
Augmentation of UWB item no. Mechanical 2530050.00 0.00 0.00 0.00 25050.00 0.00 25050.00 0.00 0.00 0.00
3 Infrastructural facility for 266of 22-
OVH of RMPU during POH 23
of LHB coaches Total 34801896.06 59981.73 0.00 59981.73 324958.65 0.00 324958.65 149954.83 0.00 149954.83

 
Civil 18965974.93 34388.55 0.00 34388.55 171942.77 0.00 171942.77 85971.00 0.00 85971.00
LLH- improvement in UWB item no. Electrical 14869593.00 38871.00 0.00 38871.00 194355.00 0.00 194355.00 97178.00 0.00 97178.00
4 infrastructure for Critical 267of 22-
Coach Components Shops 23 Total 33835567.93 73259.55 0.00 73259.55 366297.77 0.00 366297.77 183149.00 0.00 183149.00

Total Balance Fund        13309071.73    1782731.42    333103.83


A shop New shed-I(Bay 1st & 2nd )
A shop New shed-II(Bay 3rd & 4th )
A shop New shed-III(Bay 5th & 6th )
Widening & Conversion of Traverser Bay-II
J-Shop AC Overhauling
J-Shop Bay-II
Work Completed under MOD Project
SN Description of Work Status Date of completion
1 Augmentation & renovation of coach feeding line (11J & 5/20MR). Work Completed 31.05.2017
2 Construction of Washing apron on line no. 9J & 10J. Work Completed 30.10.2014
3 Up-gradation of Bogie Overhauling Sheds and Coach Lifting Bays including wheel shop. Work Completed 31.12.2017
4 L-Shop: Heavy Corrosion repairing Shop at Bay-3 & 4 of L-shop. Work Completed 02.05.2013
5 F-Shop: Modification to Coach Furnishing Shop. Work Completed 30.09.2014
6 Remodeling of MR-Bahar line shed. Work Completed 21.01.2019
7 Conversion of BOX Roller Bearing Section to LHB CTRB Section/ K-Shop. Work Completed 31.12.2016
8 Renovation of ICF Roller Bearing Section / K-shop Work Completed 31.12.2017
9 Remodeling of Spring Shop. Work Completed 31.12.2014
10 Extension/renovation of Air Brake repairing Shops. (AIR BK. RPR)/MR. Work Completed 31.07.2019
11 Extension/renovation of AB repairing Shops/L (DV RPR). Work Completed 31.12.2017
12 Renovation of FRP Section. Work Completed 13.04.2011
13 Renovation & construction of Pathways as well as drain. Work Completed Completed with shed construction.
14 Development of Repair Shop, AC Finishing Shop, & Motor Sec. Work Completed 28.09.2011
15 Up-gradation of Drawing Office. Work Completed 23.08.2012
16 Modification & up-gradation of workshop Canteen. Work Completed 30.06.2019
17 Construction of shed for electrical Power car at Bahr Line. Work Completed 15.10.2018
18 Strengthening of WC Bay for Lifting LHB Coaches. Work Completed 02.05.2013
19 Extension of AC-Alternator Section at L-shop site. Work Completed 13.09.2019
20 Widening and extension of Traverser Bay - 3 Work Completed 23.03.2021

21 Construction of New LHB Bogie Bay shed. Work Completed 27.11.2018


22 Construction of New LHB Lifting Bay. Work Completed 21.04.2021
23 Construction of MR shop Service Building Work completed 22.04.2021
24 Construction of E shop Building. Work Completed 21.12.2021

25 Construction of Trimming Shop Godown Work completed 30.04.2022


26 Construction of New Lean-To-Shed Work completed 30.04.2022

27 Construction of New A&HT Shop (1 st & 2nd Bay) Work completed 11.03.2022/10.11.2022