You are on page 1of 7

SHAURYA CEMENT INDUSTRIES PRIVATE LIMITED

DAILY REPORT: 17.02.2021

Man Power Statement for project


Description 12.02.2021 13.02.2021 14.02.2021 15.02.2021 16.02.2021 17.02.2021
Civil-plant building 244 250 229 250 250 235
Mechanical 240 240 225 225 225 225
Electrical 35 35 35 35 35 20
Ayoki staff 23 23 23 23 23 23
TOTAL 542 548 512 533 533 503
Shree Krishna 341 337 340 338 338 300
Engineering
Rajpooth 90 90 90 90 90 90
Grand total 973 975 942 961 961 893
Refractory Man power : 00
Insulation man power : 28 Shree Krishna man power details:
Mechanical: 193
Electrical : 44
Civil : 57
Staff : 06

Man Power Statement for Pyro Operation


Description 12.02.2021 13.02.2021 14.02.2021 15.02.2021 16.02.2021 17.02.2021
Civil 40
Mechanical 65
Electrical 14
Process & lab 16
TOTAL 136
Daily Progress Report as on 17.02.2021 Daily progress report Mechanical :

1. TT-3 & TT-4 :- Block massonery work under Fabrication


progress
2. Preheater :- Preparation for lift wall in progress * Packing plant venting lines fabrication under progress
3. Drain: - Excavation work under progress. Also * Gratings fabrication under progress
rebar work under progress. * Cement silo feed chutes fabrication under progress
4. Cooler House: - Grade slab work under * Packing plant chutes fabrication under progress
progress.
5. Cooling Tower: - Wall rebar and shuttering Erection :
work under progress.
6. Clinker Silo: - Reject bin foundation work under * Cement silo-2 to packing plant bucket elevator air slides
progress. assembly and erection preparation under progress
7. Cement Mill Feed: Soil filling work under * Packing plant truss sheet work under progress
progress in this area. * Clinker silo penthouse sheet work under progress
8. Canteen Building: - Column rebar and * Cement mill building handrails painting and finishing under
shuttering with RCC work under progress. progress
9. Store and workshop Building: - Excavation and * Packing plant bucket elevator platforms erection under
backfilling work under progress. Also footings and progress
column rebar and shuttering work under * Coal mill structure cladding runner erection under progress
progress. * Raw mill all bolts re-tightening after 12 hours 3rd time
10. Boundary wall work under progress. completed.
11. Plant housekeeping work under progress. Coal Mill 2nd bolt tightening completed.
Exuviation work in progress for weight bridge. * Packing plant venting lines erection under progress
12. ADM Building: - Internal finishing work and * Packing plant compressed air line erection under progress
block massonery work under progress. * Packing plant staircase erection under progress
13. Staff quarter: - Ground floor finishing work * Belt conveyor 531.BC 200 skirt board fixing under progress
under progress in C1, C2. * Cement silo-1 open air slides erection under progress
14. Coal Mill building. Grid slab casting in progress *Packing plant air slides platform erection under progress
*Packing plant truss erection under progress
* Cement silo top air slide support structure erection under
progress
* Cement mill building platform gratings fixing and handrails
fixing under progress
* Limestone crusher building structure erection completed.
* Low alkali silo top bag filter venting lines erection completed.
* Packing plant building staircase handrails erection under
progress
* Cement mill building outside air line water line erection under
progress
*Cement silo-1 top handrails erection under progress
* Cement silo-2 bin extraction system erection under progress
* Cement mill hot air duct pending jobs completion under
progress
* Cement silo - 2 to packing plant air slide structure erection
under progress
* Cement silo feed bucket elevator structure staircase and drive
platform members received under progress
* Cement silo-1 extraction system erection under progress
* Cement mill bag house weather enclosure structure assembly
and preparation for erection
* Outside building airline erection under progress
Rain status: 0.0mm

SCIPL / Stores Report / 17 Feb' 2021

>>>Inward>>>
1. Lime Stone - 4776.51 Mt/ 176 Loads.
a. SCL Dumping yard - 28.58 Mt/ 1 Loads. b. SCP Galtar Mines - 4747.93 Mt/ 175 Loads
2. Oxygen Cylinder Refill 10 nos from Dhalkewar Gas Udyog
3. Diesel 20000 Ltr from Parewashwari Oil
4. Steam Coal - 30.22 MT / 1 Loads from Ripley Overseas
5. Pet Coke - 10.28 MT ( As per lab report ) bill not received
6. LPG Refill 4 nos from Jitu Enterprises
7. Stationery Items from Laxmi Pustak Pasal
8. Plant & Machinery Items 1 trip from FLSmidth
9. Surge Arrestor from Lamco Industries
10. CSK Bolt, Self-Taping Screw from Arya Trading

<<Outward <<
1. Limestone - Nil
LIME STONE REPORT
Opening Stock Inward Outward Closing Stock
726128.35 MT 4776.51 MT 0 MT 730904.86 MT
COAL REPORT
Opening Stock Inward Closing Stock
17318.43 MT 30.22 MT 17348.65 MT
Pet Coke
Opening Stock Inward Closing Stock
1331.16 MT 30.22 MT 1361.38 MT
Site photographs:

Clinker silo penthouse sheet work under progress

Cement mill baghouse insulation work under progress


Packing plant staircase erection under progress

Cement silo top airslide structure assembly under progress


Packing plant truss assembly under progress

Cement mill baghouse weather enclosure structure erection under progress


Photographs: Site:

Cooling tower shuttering work

Canteen RCC raft work


Stores RCC raft work