You are on page 1of 5

THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64

WEEKLY PROGRESS REPORT


NUWAKOT-64
PROJECT TITLE: THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL

CONTRACT NO: KOICA-NEPAL-2017-01

CONTRACTOR: NEPAL ADARSHA NIRMAN COMPANY PVT. LTD.

1. Weekly Progress Report Number: NUWAKOT - 64

2. Reporting Period: 12.May.2019 ~ 18.May .2019

3. Progress: Plan % / Actual %

4. Manpower
TOTAL TOTAL
STAFF DAILY LABOR MANPOWER DAILY
UP TO DATE UP TO DATE
Project Manager 0 136 Mason 11 4997
QC 7 376 Unskilled Labor 19 7352
Civil Engineer 7 400 Rebar worker 5 4221
Safety Engineer 7 400 Formwork 3 3087
Procurement & Account 7 330 Scaffolding worker 3 731
Site Supervisors 7 390 Masonry Worker 8 3753
Operator 0 255 Electrical worker 1.143 287
Site In Charge 7 381 Plasterer 7 1403
Store Keeper 7 395 Metal worker 8 408
Guard (Night) 7 352 Tile worker
Guard (Day) 7 171 Waterproof worker
Electrician 2 36 Painter 4.286 164
Mech. Engineer Roofing Worker
Fire Fighting Workers 0 30
Sanitary worker 3 473

5. Equipment
OPERATION OPERATION
EQUIPMENT NOS/SET EQUIPMENT NOS/SET
HOURS HOURS
Backhoe Loader Drilling Machine 1 28
Excavator Welding Machine 1 42
Dump Truck Saw Machine 2 22
Compactor Roller Shearing Machine 1 22
Concrete Mixer 1 7 Bar Cutter 1 0
Concrete Vibrator 1 2 Concrete Breaker 1 6
Generator 1 15 Total Station
Concrete Pump Auto Level 1 30
Rebar Cutter Monkey Jumper 1 2
Compression Test Machine Bar Bending Machine 1
Crain Roller
Mortar Mixer Water Pump 2 35
THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64

6. Construction Materials on Site

QTY OF TOTAL QTY


ITEM DATE UNIT CONSUMED STOCK
ON SITE UP TO DATE
Cement Bag 420 13772 124 327
Rebar (size Various) Kg 0 253785 40 45
Fine Aggregate (Sand) m3 0 1228.99 18.85 47.466
Coarse Aggregate (Gravel) m3 0 852.43 3.408 1.371
Brick Nos. 10500 532500 10550 7500
Soil Backfilling m3 - -
Wood Cft. -
Stone -
Plywood Sheet -
Chips m3 - 24.034 0 24.034

7. Work Performed during this Week

1. Laying electrical cables at ground floor of Block A and installing fan hooks on ceiling.
2. Plaster work on Block C second floor.
3. Plastering at staircase side wall.
4. Brickwork at Ground floor of Block B male female toilet.
5. Water supply pipe fitting and insulation work and its testing on building.
6. Laying waste water pipes at Second floor of Block B.
7. Making and laying cable tray for ground floor.
8. Metal staircase work at north face of the building started.
9. Continuing variation works at building as per the revised drawings.
10. Brickwork at duct walls continued.
11. Wall putty work at building.
12. Coating of primer on Block A East and North face.
13. Line, level and grip installed on wall for false ceiling on Block B second floor.
14. Aluminium doors and windows frame made for Block B second floor.

8. Plan for Next Week

1. Laying electric conduits for AC units and continue of laying electric cables on conduits in building.
2. Aluminium works for frame and shutter of doors and windows in block A.
3. Continue sanitary work at building.
4. Conduct external butta plaster at building.
5. Continue plastering at Block C.
6. Continue metal work at emergency staircase.
7. Continue brickwork at Ducts.
8. Continue false ceiling work.
9. Continue screeding at second floor of Block.
10. Start of tile works on Block B second floor.
11. Continue variation works at building as per the revised drawings.

9. Verbal Instructions Received and Deficiencies Corrected

10. Safety [Incident and Hazards


THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64

11. Transmittal Status

No Transmittal No Submit Date Description


1 057 2019/05/13 Intercom cable

12. Others

13. Progress Photos

West view of building External plastering at second floor of Block C

Primer coat at east elevation Laying sanitary waste pipes for first floor
THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64

South-east view of building Conducting PCC work at ground floor

Site Cleaning Brickwork at duct wall

North-east view of building Testing water supply pipes for leakage


THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64

Variation work at X-ray room South-west elevation of Building

Submitted by:
Krishna Govinda Khayamali
Project Manager

You might also like