4. Manpower
TOTAL TOTAL
STAFF DAILY LABOR MANPOWER DAILY
UP TO DATE UP TO DATE
Project Manager 0 136 Mason 11 4997
QC 7 376 Unskilled Labor 19 7352
Civil Engineer 7 400 Rebar worker 5 4221
Safety Engineer 7 400 Formwork 3 3087
Procurement & Account 7 330 Scaffolding worker 3 731
Site Supervisors 7 390 Masonry Worker 8 3753
Operator 0 255 Electrical worker 1.143 287
Site In Charge 7 381 Plasterer 7 1403
Store Keeper 7 395 Metal worker 8 408
Guard (Night) 7 352 Tile worker
Guard (Day) 7 171 Waterproof worker
Electrician 2 36 Painter 4.286 164
Mech. Engineer Roofing Worker
Fire Fighting Workers 0 30
Sanitary worker 3 473
5. Equipment
OPERATION OPERATION
EQUIPMENT NOS/SET EQUIPMENT NOS/SET
HOURS HOURS
Backhoe Loader Drilling Machine 1 28
Excavator Welding Machine 1 42
Dump Truck Saw Machine 2 22
Compactor Roller Shearing Machine 1 22
Concrete Mixer 1 7 Bar Cutter 1 0
Concrete Vibrator 1 2 Concrete Breaker 1 6
Generator 1 15 Total Station
Concrete Pump Auto Level 1 30
Rebar Cutter Monkey Jumper 1 2
Compression Test Machine Bar Bending Machine 1
Crain Roller
Mortar Mixer Water Pump 2 35
THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64
1. Laying electrical cables at ground floor of Block A and installing fan hooks on ceiling.
2. Plaster work on Block C second floor.
3. Plastering at staircase side wall.
4. Brickwork at Ground floor of Block B male female toilet.
5. Water supply pipe fitting and insulation work and its testing on building.
6. Laying waste water pipes at Second floor of Block B.
7. Making and laying cable tray for ground floor.
8. Metal staircase work at north face of the building started.
9. Continuing variation works at building as per the revised drawings.
10. Brickwork at duct walls continued.
11. Wall putty work at building.
12. Coating of primer on Block A East and North face.
13. Line, level and grip installed on wall for false ceiling on Block B second floor.
14. Aluminium doors and windows frame made for Block B second floor.
1. Laying electric conduits for AC units and continue of laying electric cables on conduits in building.
2. Aluminium works for frame and shutter of doors and windows in block A.
3. Continue sanitary work at building.
4. Conduct external butta plaster at building.
5. Continue plastering at Block C.
6. Continue metal work at emergency staircase.
7. Continue brickwork at Ducts.
8. Continue false ceiling work.
9. Continue screeding at second floor of Block.
10. Start of tile works on Block B second floor.
11. Continue variation works at building as per the revised drawings.
12. Others
Primer coat at east elevation Laying sanitary waste pipes for first floor
THE CONSTRUCTION OF NEW NUWAKOT DISTRICT HOSPITAL, NEPAL l Weekly progress report 64
Submitted by:
Krishna Govinda Khayamali
Project Manager