You are on page 1of 13

DAILY PROGRESS REPORT

Project No : 44AC9100
Report For : July 31, 2022 (Sunday) Client : IOCL Gujarat Refinery
Date of Reporting: August 1, 2022 (Monday) Project Title : AA/BA Acrylics Oxo-Alocohol Project
Location : IOCL-Dumad , Vadodara
Weather : Cloudy
Quantity Yesterday's Plan & Monthly Plan- June'22 Target
actual
Sl No Actvity Description Unit Estimated Remarks
Drawing Cumm. Balance % Completion Plan Actual Plan for Next Plan Actual Completion Date
Scope release Qty Completed day

Fire Water Tanks foundations


1 Civil Works
1.1 Excavation Work cum 396 396 396 0 100% - - completed
1.2 PCC Work cum 8 8 8 0 100% - - completed
1.3 RCC Work cum 249 249 249 0 100% - - completed
1.4 Sand Filling cum 2,742 2,742 2,742 0 100% - - completed
Warehouse
1 Civil Works
1.1 Excavation Work cum 4,892 4,892 4,892 0 100% - - completed

1.2 PCC Work (substructure) cum 55 55 55 0 100% - - completed

1.3 RCC Work Substructure (Footings) cum 430 430 430 0 100% - - completed

1.4 RCC Work structure (columns ) cum 120 120 118 2 99% - 32.50 completed 643.35

1.5 PCC Work (Plinth Beam) cum 7 7 7 0 100% - -

1.6 RCC Work (Plinth Beam) cum 95 95 95.00 0 100% - -

1.7 PCC (Grade slab) cum 89 89 89.00 0 100% - -

1.8 RCC (Grade slab) cum 240 240 0.00 240 0% -

1.9 RCC Slab cum 137 137 0.00 137 0% -

Admin Building
1 Civil Works
1.1 Excavation Work cum 8,425 8,425 7,071 1,354 84% - -

1.2 Plum Concrete Work (1:3:6) cum 1,852 1,852 1,810 42 98% - -

1.3 RCC Work (Raft & Footing) cum 4,400 4,400 4,360 40 99% - - Completed

1.4 RCC Work ( Columns upto102.975 ) cum 121 121 121 0 - 11.50 Completed

1.5 Retaining Wall cum 97 97 97 0 - - 0.50 Completed

1.6 PCC Ramp Retaing Wall cum 39 39 22 18 56% - 1.00 Completed

1.7 RCC (Ground slab) cum 635 635 635 0 100% - 373.00 Completed

1.8 Grade Slab cum 4.5 4.5 0 5 0% - Completed

1.8 RCC (First slab) cum 630 630 0 630 0% - Completed

Page 1 of 13
DAILY PROGRESS REPORT
Project No : 44AC9100
Report For : July 31, 2022 (Sunday) Client : IOCL Gujarat Refinery
Date of Reporting: August 1, 2022 (Monday) Project Title : AA/BA Acrylics Oxo-Alocohol Project
Location : IOCL-Dumad , Vadodara
Weather : Cloudy
Quantity Yesterday's Plan & Monthly Plan- June'22 Target
actual
Sl No Actvity Description Unit Estimated Remarks
Drawing Cumm. Balance % Completion Plan Actual Plan for Next Plan Actual Completion Date
Scope release Qty Completed day

1.9 RCC (Second slab) cum 672 672 0 672 0% - Completed

2.0 RCC (Stair case) cum 67 67 3 64 4% -

2.1 RCC(Lintel Beam) cum 18.4 18.4 0 18 0% -

2.1 RCC(Columns above 102.975) cum 98.0 98.0 65 33 67% -

Workshop
1 Civil Works
1.1 Excavation Work cum 4,856 4,856 4,856 0 100% - - completed

1.2 PCC Work cum 56 56 56 0 100% - - completed

1.3 RCC Work (Footings ) cum 430 430 430 0 100% - - completed

1.4 RCC Work Column cum 250 250 99 151 39% 2.50 17.50 completed

1.5 PCC Below Plinth Beam cum 52.5 52.5 21 32 40% - 3.50

1.6 Brick Work Plinth Beam cum 115 115 115.00 0 100% - - completed

1.8 RCC Plinth Beam cum 92.0 92.0 92 0 100% - 92.00

1.8 PCC Grade Slab 24.0 24.0 14 10 - 14.00

1.9 Grade Slab M 20 cum 170.0 170.0 0 170 0% - -

2.0 RCC Slab cum 158.0 158.0 0 158 0% - -

2.1 Lintel Beam cum 30.0 30.0 0 30 0% - -

Security Office
1 Civil Works
1.1 Excavation Work cum 2,512 2,512 2,512 0 100% - - Completed

1.2 PCC Work cum 65 65 65 0 100% - - Completed

1.3 RCC Work (Footings ) cum 400 400 400 0 100% - - Completed

RCC Work ( Columns upto bottom of


1.4 cum 60 60 58.86 1 98% - 0.50
plinth beam )

1.5 PCC Work(below Plinth Beam) cum 29 29 29 0 100% - - Completed

1.6 Brick Work cum 120 120 120 0 100% - - Completed

1.7 Retaing Wall cum 19.07 19.07 17.5 2 92% - -

1.8 Cable Trench RCC cum 9 9 5.5 4 61% - -

1.9 RCC Plinth Beam cum 94 94 86 8 91% - -

2.0 PCC FOR GRADE SLAB CUM 47 47 40.5 7 86% -

Page 2 of 13
DAILY PROGRESS REPORT
Project No : 44AC9100
Report For : July 31, 2022 (Sunday) Client : IOCL Gujarat Refinery
Date of Reporting: August 1, 2022 (Monday) Project Title : AA/BA Acrylics Oxo-Alocohol Project
Location : IOCL-Dumad , Vadodara
Weather : Cloudy
Quantity Yesterday's Plan & Monthly Plan- June'22 Target
actual
Sl No Actvity Description Unit Estimated Remarks
Drawing Cumm. Balance % Completion Plan Actual Plan for Next Plan Actual Completion Date
Scope release Qty Completed day

2.1 RCC Grdae slab cum 138 138 15.5 123 11% -

2.2 RCC Roof Slab cum 226 226 0 226 0% -

2.3 RCC Stair case cum 13 13 0 13 0% -

2.4 RCC Lintel Beam cum 14.3 14.3 0 14 0% -

2.5 RCC Columns above Plinth Beam cum 49.2 49.2 22.2 27 45% -

Cable Trench (LPG to Boundary wall)


1 Civil Works
1.1 Excavation Work cum 2,647 2,647 2,647 0 100% - - completed

1.2 PCC Work cum 71 71 71 1 99% - 27.50

1.3 RCC Work cum 520 520 520 0 100% 11.50 156.00

1.4 Plaster Sqm 1,082 1,082 1,082 0 100% -

1.5 Precast cover slab(upto 451 m) Nos. 1,200 1,200 1,020 180 85% -

1.6 ERC cum 101 -

Security Office Near Material Gate


1 Civil Works

1.1 Excavation Work cum 346 346 346 0 100% - - Completed

1.2 PCC Work cum 4 4 4 0 100% - - Completed

1.3 RCC Work (Footings) cum 16 16 16 0 100% - - Completed

1.4 RCC Column cum 9 9 3.3 6 37% - 1.50 Completed

1.5 PCC Grade cum 2.2 2.2 2 0% - -

1.6 RCC Grade Slab cum 4.4 4.4 4 0% - -

1.7 Plinth Beam & Slab cum 19.0 19.0 19 0% - -

Security Check Building


1 Civil Works
1.1 Excavation Work cum 157 157 157 0 100% - - Completed

1.2 PCC Work cum 5.0 5.0 5 0 100% - - Completed

1.3 RCC Work (Footings) cum 37 37 35 2 95% - - Completed

1.4 RCC Works Column cum 10 10 5.6 5 54% - 2.00

1.5 PCC (Bottom of Brick work) cum 4 4 4.0 0 100% - - Completed

Page 3 of 13
DAILY PROGRESS REPORT
Project No : 44AC9100
Report For : July 31, 2022 (Sunday) Client : IOCL Gujarat Refinery
Date of Reporting: August 1, 2022 (Monday) Project Title : AA/BA Acrylics Oxo-Alocohol Project
Location : IOCL-Dumad , Vadodara
Weather : Cloudy
Quantity Yesterday's Plan & Monthly Plan- June'22 Target
actual
Sl No Actvity Description Unit Estimated Remarks
Drawing Cumm. Balance % Completion Plan Actual Plan for Next Plan Actual Completion Date
Scope release Qty Completed day

1.6 Plinth Beam cum 6 6 6.0 0 100% - - Completed

1.7 PCC for Grade slab cum 1 1 1.0 0 100% - 1.00

1.8 RCC for Grade Slab cum 3 3 3 0% - -

1.9 RCC Slab cum 15 15 15 0% -

Foam shed
1 Civil Works
1.1 Excavation Work cum 920 920 920 0 100% - 920.00 Completed

1.2 PCC Work cum 15 15 15 0 100% - 14.50 Completed

1.3 RCC Work (Footings) cum 89 89 89 0 100% - 89.00 Completed

Page 4 of 13
Manpower Details
### Report For July 31, 2022 (Sunday)
### Date of Reporting August 1, 2022 (Monday)

Sl No Trade Admin Warehouse Workshop Security Building Security Building Security Check Foam Shed/Fire Cable Trench Inside Cable Storm water Drain Other Total (Nos.)
Near Material Gate Building Station Trench

1 Carpenter 20 6 3 5 3 37
2 Barbender/ Steel Fitter 22 5 2 2 4 35
3 Operators 2 2
4 Welder reinforcement 0 0
5 Welder Structural / Tank 0
6 Welder-Piping / Mech 0
7 Structural/Millwright -Fabricator 0
8 Pipe Fitter 0
9 Pipe Fabricator 0
10 Grinder 0
11 Tack welder 0
12 Electrician 0
13 Masons/ Khalasi 4 5 5 5 4 23
14 Blaster 0
15 Painter 0
16 Riggers 0
17 Security Guard 4 4
18 Drivers 5 5
19 Office boy 1 1
20 Housekeeping (shifts) 3 3
21 Unskilled Labour 8 10 3 3 4 2 30
22 Scaffolder 10 8 4 5 27
23 Insulator / Laminator 0
24 Gas/ Plasma-cutter 0
25 Others 2 2
26 Surveyor /Technician 1 1
27 Prime contractor staff / Engineers 1 1 1 1 1 3 20 28
Total Available at site (Nos.) 67 35 18 21 1 15 0 0 0 3 38 198

Page 5 of 13
Machinery Details

Sl No Description

1 Piling Rigs
2 Batching plant
3 Crane
JCB / Excavator
4
5 Hydra
6 Wheel loader / Tractor trolley
7 Trolley(Hydraulic)
8 DG set
9 BOB Cat / Baby Roller
10 Diesel welding generator
11 10/7 Mixer With Weigh Bacher
12 Dumper
13 Cube testing machine
14 Bar / Plate bending machine
15 Concrete Mixer
16 Portable welding m/c
17 Welding Rectifier m/c
18 Cutting machine / torch
19 Compressor
20 Hopper / concrete funnel
21 Porta Cabin / Container
22 Jack Hammer
23 Level instrument
24 Water tanker

Page 6 of 13
Machinery Details

Sl No Description

25 Thedolite/ Total station


26 Ambulance
27 Car & Jeeps
28 AJAX / Fourey
29 Ply cutting machine
30 Vibrators / needles
31 Mono Pump
32 De-watering pump
33 Chopsaw Machine
34 Auto Level
35 Weight Machine
36 Core Cutting set
37 Winch Machine
38 Truck mounted bore well rig
39 Compactor
40 Back hoe loader
41 Tower crane
42 Drilling Machine
43 Boom Placer
44 Grinding Machine
45 Fpug
46 JLG/ Manlift
47 Paver block machine
48 Blasting machine
49 All cut machine

Page 7 of 13
Machinery Details

Sl No Description

50 Gantry 20 Ton - 20 mtr span


51 Heavy truck
52 Plate rolling machine
53 Pug cutting machine
54 Pipe threading machine
55 Trailer
56 Concrete / vertical pump

Page 8 of 13
Machinery Details

Total (Nos.)

NA
1
NA
3
2
0/1
NA
2
1/0
NA
NA
4
1
1/0
NA
1
1
1/0
1
NA
2
NA
1
1

Page 9 of 13
Machinery Details

Total (Nos.)

1
1
1

1
2
1
NA
NA
1
1
1
NA
NA
1

1
NA
1
1

NA
NA
NA
NA

Page 10 of 13
Machinery Details

Total (Nos.)

NA
NA
NA
NA
1
NA

Page 11 of 13
Materials Details
Received Materials

S.NO Materials/Item Unit Previous Qty Today Received


Received Qty

1 TMT STEEL MT 1321.730 100.340

2 AGGREGATE MT

3 OPC CEMENT MT

4 SAND CUM

5 RCC PIPE RM

6 UPVC PIPE RM

7 SCRAFFOLDING MT
ails

Total Received Qty

1422.1