FA = 64.00sqm, CIP Wall System,4BR, 2TB, LA=80sqm


Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NO OF UNIT: 2 NO OF UNIT: 4
Date: : November 28, 2020
NTP NO: 09

1.0 2.0 3.0 4.0 5.0 6.0 AT 100% AT 100%


ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1203 B1204 B1213 B1214 B1215 B1216
NO. DUPLEX UNIT QUAD UNIT
DUPLEX UNIT DUPLEX UNIT QUAD UNIT QUAD UNIT QUAD UNIT QUAD UNIT
Module I SUB - STRUCTURE 3.29% 3.29% 0.56% 0.56% 0.56% 0.56% 9.18% 8.79%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.56% 0.56% 0.56% 0.56% 0.62% 0.56%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.68% 2.45%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.76%
1.04 2500psi RC Zucallo Wall 2.43% 2.23%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.79%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.26% 9.34%
2.01 Wires & Conduits 0.68% 0.72%
2.02 PVC Pipes & Fittings 0.54% 0.57%
2.03 GF Wall Concreting 9.04% 8.05%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.25% 7.69%
3.01 2F Slab Concreting 7.25% 7.69%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.49% 10.21%
4.01 Wires & Conduits 0.87% 0.92%
4.02 2F Wall Concreting 10.62% 9.29%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.77% 4.00%
5.01 Roof Framing 3.77% 4.00%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.15% 4.49%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.40% 2.55%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.48% 12.73%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.14% 5.45%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13.39% 14.20%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.89% 9.95%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.59% 10.61%
TOTAL 3.29% 3.29% 0.56% 0.56% 0.56% 0.56% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 3.29% 3.29% 0.56% 0.56% 0.56% 0.56%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3.00 % Weight BILLABLE THIS PERIOD 3.29% 3.29% 0.56% 0.56% 0.56% 0.56%
4.00 % Weight BALANCE AFTER THIS PERIOD 96.71% 96.71% 99.44% 99.44% 99.44% 99.44%
Target date of Completion 5-Apr-21 5-Feb-22 5-Feb-22 5-Jan-22 5-Sep-21 5-Apr-21
No of days remaining/ delays 128.00 434.00 434.00 403.00 281.00 128.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President
Subject : VERDANT HOUSE MODEL CONSTRUCTION MONITORING
FA = 64.00sqm, CIP Wall System,4BR, 2TB, LA=80sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NO OF UNIT: 2 NO OF UNIT: 4
Date: : December 5, 2020
NTP NO: 09

1.0 2.0 3.0 4.0 5.0 6.0 AT 100% AT 100%


ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1203 B1204 B1213 B1214 B1215 B1216
NO. DUPLEX UNIT QUAD UNIT
DUPLEX UNIT DUPLEX UNIT QUAD UNIT QUAD UNIT QUAD UNIT QUAD UNIT
Module I SUB - STRUCTURE 9.18% 9.18% 0.56% 0.56% 0.56% 0.56% 9.18% 8.79%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.56% 0.56% 0.56% 0.56% 0.62% 0.56%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.68% 2.45%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.83% 0.83% 0.76%
1.04 2500psi RC Zucallo Wall 2.43% 2.43% 2.43% 2.23%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.63% 2.63% 2.79%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.26% 9.34%
2.01 Wires & Conduits 0.68% 0.72%
2.02 PVC Pipes & Fittings 0.54% 0.57%
2.03 GF Wall Concreting 9.04% 8.05%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.25% 7.69%
3.01 2F Slab Concreting 7.25% 7.69%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.49% 10.21%
4.01 Wires & Conduits 0.87% 0.92%
4.02 2F Wall Concreting 10.62% 9.29%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.77% 4.00%
5.01 Roof Framing 3.77% 4.00%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.15% 4.49%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.40% 2.55%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.48% 12.73%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.14% 5.45%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13.39% 14.20%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.89% 9.95%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.59% 10.61%
TOTAL 9.18% 9.18% 0.56% 0.56% 0.56% 0.56% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 9.18% 9.18% 0.56% 0.56% 0.56% 0.56%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 3.29% 3.29% 0.56% 0.56% 0.56% 0.56%
3.00 % Weight BILLABLE THIS PERIOD 5.89% 5.89% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 90.82% 90.82% 99.44% 99.44% 99.44% 99.44%
Target date of Completion 5-Apr-21 5-Feb-22 5-Feb-22 5-Jan-22 5-Sep-21 5-Apr-21
No of days remaining/ delays 121.00 427.00 427.00 396.00 274.00 121.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President
Subject : VERDANT HOUSE MODEL CONSTRUCTION MONITORING
FA = 64.00sqm, CIP Wall System,4BR, 2TB, LA=80sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NO OF UNIT: 2 NO OF UNIT: 4
Date: : December 14, 2020
NTP NO: 09

1.0 2.0 3.0 4.0 5.0 6.0 AT 100% AT 100%


ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1203 B1204 B1213 B1214 B1215 B1216
NO. DUPLEX UNIT QUAD UNIT
DUPLEX UNIT DUPLEX UNIT QUAD UNIT QUAD UNIT QUAD UNIT QUAD UNIT
Module I SUB - STRUCTURE 9.18% 9.18% 3.01% 3.01% 3.01% 3.01% 9.18% 8.79%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.56% 0.56% 0.56% 0.56% 0.62% 0.56%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.45% 2.45% 2.45% 2.45% 2.68% 2.45%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.83% 0.83% 0.76%
1.04 2500psi RC Zucallo Wall 2.43% 2.43% 2.43% 2.23%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.63% 2.63% 2.79%
Module II GROUND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.26% 9.34%
2.01 Wires & Conduits 0.68% 0.72%
2.02 PVC Pipes & Fittings 0.54% 0.57%
2.03 GF Wall Concreting 9.04% 8.05%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.25% 7.69%
3.01 2F Slab Concreting 7.25% 7.69%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.49% 10.21%
4.01 Wires & Conduits 0.87% 0.92%
4.02 2F Wall Concreting 10.62% 9.29%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.77% 4.00%
5.01 Roof Framing 3.77% 4.00%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.15% 4.49%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.40% 2.55%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.48% 12.73%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.14% 5.45%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13.39% 14.20%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.89% 9.95%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.59% 10.61%
TOTAL 9.18% 9.18% 3.01% 3.01% 3.01% 3.01% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 9.18% 9.18% 3.01% 3.01% 3.01% 3.01%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 9.18% 9.18% 0.56% 0.56% 0.56% 0.56%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 0.00% 2.45% 2.45% 2.45% 2.45%
4.00 % Weight BALANCE AFTER THIS PERIOD 90.82% 90.82% 96.99% 96.99% 96.99% 96.99%
Target date of Completion 5-Apr-21 5-Feb-22 5-Feb-22 5-Jan-22 5-Sep-21 5-Apr-21
No of days remaining/ delays 112.00 418.00 418.00 387.00 265.00 112.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President
Subject : VERDANT HOUSE MODEL CONSTRUCTION MONITORING
FA = 64.00sqm, CIP Wall System,4BR, 2TB, LA=80sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NO OF UNIT: 2 NO OF UNIT: 4
Date: : January 9, 2021
NTP NO: 09

1.0 2.0 3.0 4.0 5.0 6.0 AT 100% AT 100%


ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1203 B1204 B1213 B1214 B1215 B1216
NO. DUPLEX UNIT QUAD UNIT
DUPLEX UNIT DUPLEX UNIT QUAD UNIT QUAD UNIT QUAD UNIT QUAD UNIT
Module I SUB - STRUCTURE 9.18% 9.18% 3.01% 3.01% 3.01% 3.01% 9.18% 8.79%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.56% 0.56% 0.56% 0.56% 0.62% 0.56%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.45% 2.45% 2.45% 2.45% 2.68% 2.45%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.83% 0.83% 0.76%
1.04 2500psi RC Zucallo Wall 2.43% 2.43% 2.43% 2.23%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.63% 2.63% 2.79%
Module II GROUND FLOOR RC WALL 10.26% 0.00% 0.00% 0.00% 0.00% 0.00% 10.26% 9.34%
2.01 Wires & Conduits 0.68% 0.68% 0.72%
2.02 PVC Pipes & Fittings 0.54% 0.54% 0.57%
2.03 GF Wall Concreting 9.04% 9.04% 8.05%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.25% 7.69%
3.01 2F Slab Concreting 7.25% 7.69%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.49% 10.21%
4.01 Wires & Conduits 0.87% 0.92%
4.02 2F Wall Concreting 10.62% 9.29%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.77% 4.00%
5.01 Roof Framing 3.77% 4.00%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.15% 4.49%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.40% 2.55%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.48% 12.73%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.14% 5.45%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13.39% 14.20%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.89% 9.95%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.59% 10.61%
TOTAL 19.43% 9.18% 3.01% 3.01% 3.01% 3.01% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 19.43% 9.18% 3.01% 3.01% 3.01% 3.01%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 9.18% 9.18% 3.01% 3.01% 3.01% 3.01%
3.00 % Weight BILLABLE THIS PERIOD 10.26% 0.00% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 80.57% 90.82% 96.99% 96.99% 96.99% 96.99%
Target date of Completion 5-Apr-21 5-Feb-22 5-Feb-22 5-Jan-22 5-Sep-21 5-Apr-21
No of days remaining/ delays 86.00 392.00 392.00 361.00 239.00 86.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President
Subject : VERDANT HOUSE MODEL CONSTRUCTION MONITORING
FA = 64.00sqm, CIP Wall System,4BR, 2TB, LA=80sqm
Location : Orchard Place Residences, Brgy. Pinagbarilan, Baliwag Bulacan MODULAR ACCOMPLISHMENT BASED ON NTP
Owner : Prominence Properties Inc.
Contractor: : ADD BUILDERS & ENGINEERING SERVICES NO OF UNIT: 2 NO OF UNIT: 4
Date: : January 9, 2021
NTP NO: 09

1.0 2.0 3.0 4.0 5.0 6.0 AT 100% AT 100%


ACCOMPLISHMENT ACCOMPLISHMENT
MODULE
PAY ITEMS B1203 B1204 B1213 B1214 B1215 B1216
NO. DUPLEX UNIT QUAD UNIT
DUPLEX UNIT DUPLEX UNIT QUAD UNIT QUAD UNIT QUAD UNIT QUAD UNIT
Module I SUB - STRUCTURE 9.18% 9.18% 3.01% 3.01% 3.01% 3.01% 9.18% 8.79%
1.01 Layout, Batterboards & Excavation 0.62% 0.62% 0.56% 0.56% 0.56% 0.56% 0.62% 0.56%
1.02 2500psi RC Wall Footing 2.68% 2.68% 2.45% 2.45% 2.45% 2.45% 2.68% 2.45%
1.03 Wooden Zucallo Forms,600x2400mm 0.83% 0.83% 0.83% 0.76%
1.04 2500psi RC Zucallo Wall 2.43% 2.43% 2.43% 2.23%
1.05 Septic Vault,1200x2800x1600mm 2.63% 2.63% 2.63% 2.79%
Module II GROUND FLOOR RC WALL 10.26% 10.26% 0.00% 0.00% 0.00% 0.00% 10.26% 9.34%
2.01 Wires & Conduits 0.68% 0.68% 0.68% 0.72%
2.02 PVC Pipes & Fittings 0.54% 0.54% 0.54% 0.57%
2.03 GF Wall Concreting 9.04% 9.04% 9.04% 8.05%
Module III SECOND FLOOR SUSPENDED SLAB 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.25% 7.69%
3.01 2F Slab Concreting 7.25% 7.69%
Module IV SECOND FLOOR RC WALL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11.49% 10.21%
4.01 Wires & Conduits 0.87% 0.92%
4.02 2F Wall Concreting 10.62% 9.29%
Module VA STEEL FRAMING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.77% 4.00%
5.01 Roof Framing 3.77% 4.00%
Module VB ROOFING & ACCESSORIES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4.15% 4.49%
Module VC MISCELLANEOUS CONCRETE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2.40% 2.55%
Module VD MASONRY FINISHES 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.48% 12.73%
Module VI SLAB-ON-FILL 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.14% 5.45%
Module VII CARPENTRY 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 13.39% 14.20%
Module VIIIA FINISHING WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9.89% 9.95%
Module VIIIB MOVE-IN-WORKS 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 10.59% 10.61%
TOTAL 19.43% 19.43% 3.01% 3.01% 3.01% 3.01% 100.00% 100.00%

1.00 % Weight TOTAL ACCOMPLISHMENT 19.43% 19.43% 3.01% 3.01% 3.01% 3.01%
2.00 % Weight PREVIOUS ACCOMPLISHMENT 19.43% 9.18% 3.01% 3.01% 3.01% 3.01%
3.00 % Weight BILLABLE THIS PERIOD 0.00% 10.26% 0.00% 0.00% 0.00% 0.00%
4.00 % Weight BALANCE AFTER THIS PERIOD 80.57% 80.57% 96.99% 96.99% 96.99% 96.99%
Target date of Completion 5-Apr-21 5-Feb-22 5-Feb-22 5-Jan-22 5-Sep-21 5-Apr-21
No of days remaining/ delays 86.00 392.00 392.00 361.00 239.00 86.00

Prepared by: Verified by: Checked by: Noted by:

__________________ ___________________ _____________________ ________________


ROBERTO NOLLORA JR. JOHN RICKY CALARA AR JASON HERNANDEZ JOHN PAUL T. DY
OPR-SE A&E - Engineer A&E -Architect President

You might also like