PROJECT NAME : 21DP0063 CONSTRUCTION OF FLOOD CONTROL WALLS
ALONG ABANDERO RIVER BAR CHART & S-CURVE
STATION LIMITS :
LOCATION : BRGY. SAN JOSE SAN PABLO LAGUNA SCHEDULE
DURATION :
2022
AMOUNT AMOUNT % WT.
ITEM NO DESCRIPTION % WT. SEPT OCT NOV DEC
(Php) contract (Php) balance balance
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16
A General Requirements
A1.4(1) Provision of Progress Photographs 17,010.00 8,505.00 0.06% 0.03%
0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
B.5 Project Billboard/signboard 21,238.40 - 0.07% 0.00%
B.7(1) Occupational Safety & Health Program 842,637.00 421,318.50 2.87% 1.43%
0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
B.9 Mobilization & Demobilization 250,000.89 125,000.45 0.85% 0.43%
0.43%
B Earthworks
100(3)a2 Individual removal of tree 300-500mm. dia). 10,896.41 - 0.04% 0.00%
100(1) Removal of structure and obstruction 200,707.98 - 0.68% 0.00%
102(2) Surplus common excavation 1,533,334.09 230,000.11 5.22% 0.78%
0.26% 0.26% 0.26%
103(3) Foundation fill 225,754.90 112,877.45 0.77% 0.38%
0.19% 0.19%
104(2)a Embankment from borrow (Common soil) 987,323.05 987,323.05 3.36% 3.36%
1.12% 1.12% 1.12%
C Drainage & Slope protection structure 50cu.m 100cu.m 300cu.m 200cu.m 200cu.m 100cu.m
510(2) Concrete slope protection 25,311,097.28 15,072,758.43 86.09% 51.27% 56cu.m
2.00% 1.33% 4.66% 1.33% 1.33% 13.98% 1.33% 9.32% 1.33% 9.32% 5.33%
TOTAL AMOUNT ₱ 29,400,000.00 ₱ 16,957,782.99 100% 58%
% WT. % WT. 42.32% 2.11% 1.44% 5.03% 1.70% 1.70% 14.09% 1.64% 9.63% 1.44% 10.55% 6.56% 1.23% 0.54% 0.00% 0.00%
WEEKLY WEEKLY
Php (M) Php (M) 12.44m 0.62m 0.42m 1.48m 0.5m 0.5m 4.14m 0.48m 2.83m 0.42m 3.1m 1.93m 0.36m 0.16m 0m 0m
PROJECTED ACCOMPLISHEMENT SCHEDULE
% WT. % WT. 42.32% 44.43% 45.87% 50.91% 52.61% 54.32% 68.41% 70.05% 79.67% 81.12% 91.67% 98.23% 99.46% 100.00% 100.00% 100.00%
CUMULATIVE CUMULATIVE
Php (M) Php (M) 12.44m 13.06m 13.48m 14.97m 15.47m 15.97m 20.11m 20.59m 23.42m 23.84m 26.95m 28.88m 29.24m 29.4m 29.4m 29.4m
% WT. % WT. 42.32% 1.05% 1.10% 0.11% 0.05% 0.11% 0.11%
WEEKLY WEEKLY
Php (M) Php (M) 12.44m 0.31m 0.32m 0.03m 0.01m 0.03m 0.03m 0m 0m 0m 0m 0m 0m 0m 0m 0m
ACTUAL ACCOMPLISHEMENT SCHEDULE % WT. % WT. 42.32% 43.37% 44.47% 44.58% 44.63% 44.74% 44.86% 44.86% 44.86% 44.86% 44.86% 44.86% 44.86% 44.86% 44.86% 44.86%
CUMULATIVE CUMULATIVE Var Var 42.32% 43.37% 44.47% 44.58% 44.63% 44.74% 44.86%
Php (M) Php (M) 12.44m 12.75m 13.07m 13.1m 13.12m 13.15m 13.19m 13.19m 13.19m 13.19m 13.19m 13.19m 13.19m 13.19m 13.19m 13.19m
Variance 0.00% -1.06% -1.40% -6.33% -7.98% -9.57% -23.55%
LEGEND : PLANNED ACTIVITY ACTUAL ACTIVITY
PLANNED S-CURVE ACTUAL S-CURVE
CASH FLOW