Professional Documents
Culture Documents
:PEO-21-1429-B
Name of Project: :Concreting of Road, Brgy. Ayubo, Tubungan, Iloilo
Location: :Tubungan, Iloilo
Starting Date: March 28, 2022
B.4(10), B-9
Contract Duration: 40.00 Calendar Days B.5 101(1) 100(2) 102(2)
1 2 3 4 5
Expiry Date: MAY 06, 2022 1 cd 3 cd 2 cd 2 cd 14 cd
Revised end of Contract May 18, 2022
ORIGINAL VERSION
Date Start March 28,
2022
NO. ITEM/DESCRIPTION QUANTITY UNIT UNIT COST TOTAL COST WT % Mar-22 APRIL 2022
4 CALENDAR DAYS 30 CALENDAR DAYS
2.88%
I. Item B.4 (10) - Miscellaneous Survey and Staking 1.00 l.s ₱ 114,300.00 ₱ 114,300.00 2.88% 1 1
2 cd
1.91%
II. Item B.5 - Project Billboard/Signboard 4.00 each ₱ 18,981.47 ₱ 75,925.88 1.91% 1
1 cd
0.26%
III. Item B.8 - Traffic Management 1.47 mos. ₱ 63,500.00 ₱ 93,345.00 2.35% 1 1 1 1
4 cd
2.63%
IV. Item B.9 - Mobilization/Demobilization 1.00 l.s ₱ 208,916.27 ₱ 208,916.27 5.26% 1
1 cd
5.18%
V. Item 101(1) - Removal of Actual Structures and Obstruction 1.00 l.s ₱ 205,486.00 ₱ 205,486.00 5.18% 1 2
2 cd
3.87%
VI. Item 102(2)- Surplus Common Excavation 610.05 cu.m. ₱ 252.00 ₱ 153,732.60 3.87% 2 2
2 cd
SUSPENDED DUE TO WEATHER
VII. Item 103(1)a - Structure Excavation 784.44 cu.m. ₱ 464.08 ₱ 364,042.92 9.17%
VIII. Item 104(1)a - Embankment from Road Excavation 219.60 cu.m. ₱ 507.48 ₱ 111,442.61 2.81%
IX. Item 104(7) - Embankment from Structure Excavation 368.73 cu.m. ₱ 723.29 ₱ 266,698.72 6.72%
XI. Item 200(1) - Aggregate Sub-Base Course 165.93 cu.m. ₱ 3,522.55 ₱ 584,496.72 14.73%
XIII. Item 500(3)b1 - Lined Canal (Concrete) 144.00 l.m ₱ 1,153.44 ₱ 166,095.36 4.18%
XIV Item 510(2) - Concrete Slope Protection 29.55 cu.m. ₱ 7,504.88 ₱ 221,769.20 5.59%
Mar-22 APRIL
MANPOWER
4 CALENDAR DAYS 30 CALENDA
PROJECT ENGINEER 1 1 1 1 1 1 1 1
FOREMAN 1 1 1 1 1 1 1 1
TRAFFIC MAN 2 2 4 4
SKILLED WORKERS 3 3 3 3
UNSKILLED WORKERS 2 2 2 2 4 8 8 8
TOTAL 4 4 4 4 11 15 17 17
Mar-22 APRIL
DESCRIPTION
4 CALENDAR DAYS 30 CALENDA
BACKHOE 1 1 1 1
ROAD GRADER
VIBRATORY ROLLER
TRANSIT MIXER
DUMPTRUCK 1 1 1 1 1 1
CONCRETE SCHREDDER
CONCRETE VIBRATOR
1-BAGGER MIXER
CONCRETE CUTTER
BAR CUTTER 1 1 1 1
WATER TRUCK
500(3)b 510(2),500(3)
10 11 13
7 cd 5 cd
0.91% 1.18%
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
18 cd
2.63%
1
1 cd
30.30% 62.27%
37.73% 16.858543622688600% 100.00%
Recommending Approval: A P P R O V E D:
LEONARDO G. SUPERIO ISAGANI D. BALDEVIESO ROMEO C. ANDIG
Engineer III Assistant Provincial Engineer Provincial Engineer
MANPOWER UTILIZATION SCHEDULE
Recommending Approval: A P P R O V E D:
LEONARDO G. SUPERIO ISAGANI D. BALDEVIESO ROMEO C. ANDIG
Engineer III Assistant Provincial Engineer Provincial Engineer
PERCENTA NUMBER
GE OF DAYS
Bid No. :PEO-21-1429-B
Name of Project: :Concreting of Road, Brgy. Ayubo, Tubungan, Iloilo
Location: :Tubungan, Iloilo
Starting Date: March 28, 2022
Contract Duration: 40.00 Calendar Days
Expiry Date: MAY 06, 2022
TOTAL AM
Prepared by :
HIROKI CONSTRUCTION
Contractor
alendar Days
ACCOMPLISHMENT
UNIT UNIT COST TOTAL COST WT % LAST
REPORT
(F)
100.00% 2.88%
100.00% 1.91%
80.50% 1.89%
50.00% 2.63%
100.00% 5.18%
100.00% 3.87%
35.00% 3.21%
85.00% 2.39%
38.00% 5.76%
45.00% 6.63%
36.35%
AMOUNT ACCOMPLISHED
PRESENT TO DATE
₱114,300.00
₱75,925.88
₱75,142.73
₱104,458.14
₱205,486.00
₱153,732.60
₱127,415.02
₱94,726.22
₱228,691.53
₱263,023.52
₱1,442,901.63