ADM-21-0598-B
Name of Project: Construction of One(1) Classroom School Building at Barasalon Elementary School. Brgy. Barasalon, Janiuay, Iloilo
Location: Janiuay , Iloilo 52,382.89
ABC: 1,350,000.00 1,297,617.11
Other General Requirements
Item A. Permits and Clearances
Qty: 1.00 lot
A. Materials:
1.00 lot Permits and Clearances @ Php 5,000.00 /lot Php 5,000.00
5,000.00
B. Labor:
1.00 liason Officer @ Php 550.00 / Day for 7 Days Php 3,850.00
3,850.00
Profit 8% 708.00
OCM 8% 708.00
Tax 7% 619.50
A. Materials:
50.00 sq.ft Tarpulin @ Php 85.00 /sq.ft Php 4,250.00
40.00 bd.ft Brace (Good Lumber) @ Php 45.00 /bd.ft Php 1,800.00
3.00 kgs Common Nails Asstd. @ Php 80.00 /kgs Php 240.00
3.00 pcs Marine Plywood 1/4x4x8 @ Php 550.00 /pcs Php 1,650.00
7,940.00
B. Labor:
1.00 Carpenter @ Php 600.00 / Day for 1 Days Php 600.00
1.00 labor @ Php 450.00 / Day for 1 Days Php 450.00
600.00
Profit 8% 683.20
OCM 8% 683.20
Tax 7% 597.80
A. Materials:
1.00 roll Nylon String @ Php 150.00 /roll Php 150.00
15.00 pcs 2x2x12/12 coco lumber @ Php 180.00 /pcs Php 2,700.00
2.00 kls CWN (Asstd) @ Php 80.00 /kls Php 160.00
1.00 l.s Miscellaneous @ Php 1,000.00 /l.s Php 1,000.00
4,010.00
B. Labor:
1.00 Construction Foreman @ Php 650.00 / day for 1.00 days Php 650.00
1.00 Carpenter @ Php 600.00 / day for 1.00 days Php 600.00
3.00 Laborers @ Php 450.00 / day for 1.00 days Php 1,350.00
2,600.00
B. Labor:
1.00 Construction Foreman @ Php 650.00 / Day for 2 Days Php 1,300.00
4.00 Laborers @ Php 450.00 / Day for 2 Days Php 3,600.00
4,900.00
C. Equipment:
Php -
-
Profit 8% 392.00
OCM 7% 343.14
Tax 7% 343.00
B. Labor:
1.00 Construction Foreman @ Php 650.00 / Day for 3 Days Php 1,950.00
4.00 Laborers @ Php 450.00 / Day for 3 Days Php 5,400.00
7,350.00
C. Equipment:
1.00 Plate Compactor @ Php 1,500.00 / day for 1.00 day Php 1,500.00
1,500.00
Profit 8% 2,018.76
OCM 7% 1,767.16
Tax 7% 1,766.42
B. Labor:
1.00 Construction Foreman @ Php 650.00 / Day for 3 Days Php 1,950.00
5.00 Laborers @ Php 450.00 / Day for 3 Days Php 6,750.00
8,700.00
C. Hauling Cost
306.00 2.00 Haulers/Manual @ Php 1,500.00 / day for 3.00 day Php 4,500.00
4,500.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 8 Days Php 4,800.00
5.00 Laborers @ Php 450.00 / Day for 8 Days Php 18,000.00
22,800.00
C. Hauling Cost
913.24 2.00 Haulers/Manual @ Php 1,826.48 / day for 5.00 day Php 9,132.40
9,132.40
1 6"x8"x16" CHB
Qty: 101.13 Sq.m
0.34 hrs
A. Materials: hrs
1,265.00 pcs 6"x8"x16" CHB @ Php 19.00 /pcs Php 24,035.00
21.00 pcs Gravel @ Php 1,350.00 /pcs Php 28,350.00
11.00 pcs Wash Sand @ Php 1,300.00 /pcs Php 14,300.00
54.00 bags Portland Cement @ Php 210.00 /bags Php 11,340.00
78,025.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 10 Days Php 6,000.00
3.00 Masons @ Php 550.00 / Day for 10 Days Php 16,500.00
5.00 Laborers @ Php 450.00 / Day for 10 Days Php 22,500.00
45,000.00
C. Hauling Cost
3,438.42 4.00 Haulers/Manual @ Php 3,570.00 / day for 4.00 day Php 14,280.00
14,280.00
Profit 8% 10,984.40
OCM 7% 9,615.40
Tax 7% 9,611.35
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 2 Days Php 1,200.00
1.00 Masons @ Php 550.00 / Day for 2 Days Php 1,100.00
1.00 Laborers @ Php 450.00 / Day for 2 Days Php 900.00
3,200.00
C. Hauling Cost
342.72 2.00 Haulers/Manual @ Php 1,800.00 / day for 2.00 day Php 3,600.00
3,600.00
Profit 8% 1,015.20
OCM 7% 888.67
Tax 7% 888.30
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 5 Days Php 3,000.00
4.00 Masons @ Php 550.00 / Day for 5 Days Php 11,000.00
4.00 Laborers @ Php 450.00 / Day for 5 Days Php 9,000.00
23,000.00
C. Hauling Cost
7,404.52 4.00 Haulers/Manual @ Php 1,500.00 / day for 3.00 day Php 18,000.00
18,000.00
Profit 8% 5,113.60
OCM 7% 4,476.29
Tax 7% 4,474.40
A. Roof Framing
Qty: 109.00 Sq.m
0.36 hrs
A. Materials: hrs
109.00 sq.m Structural Steel Truss (Angle Bar, C-purlins , Sag Rod, Cross @ Php 680.00 /sq.m Php 74,120.00
Bracing & Steel Plate & Consumables)
74,120.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 6 Days Php 3,600.00
2.00 Welder @ Php 550.00 / Day for 6 Days Php 6,600.00
5.00 Laborers @ Php 450.00 / Day for 6 Days Php 13,500.00
23,700.00
C. Hauling Cost
3,706.00 1.00 lot @ Php 5,000.00 / Day for 2 Days Php 10,000.00
10,000.00
Profit 8% 8,625.60
OCM 7% 7,550.58
Tax 7% 7,547.40
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 4 Days Php 2,400.00
2.00 Skilled/Tin Smith @ Php 550.00 / Day for 4 Days Php 4,400.00
4.00 Laborers @ Php 450.00 / Day for 4 Days Php 7,200.00
14,000.00
C. Hauling Cost
3,706.00 1.00 lot @ Php 10,000.00 / Day for 1 Days Php 10,000.00
10,000.00
Profit 8% 6,149.20
OCM 7% 5,382.82
Tax 7% 5,380.55
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 4 Days Php 2,400.00
2.00 Carpenters/Steelman @ Php 550.00 / Day for 4 Days Php 4,400.00
4.00 Laborers @ Php 450.00 / Day for 4 Days Php 7,200.00
14,000.00
C. Hauling Cost
3,264.00 1.00 lot @ Php 3,000.00 / Day for 2 Days Php 6,000.00
6,000.00
Mterials, Labor & Equip Cost: 47,230.00
Profit 8% 3,778.40
OCM 7% 3,307.49
Tax 7% 3,306.10
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 4 Days Php 2,400.00
2.00 Painter @ Php 550.00 / Day for 4 Days Php 4,400.00
2.00 Laborers @ Php 450.00 / Day for 4 Days Php 3,600.00
10,400.00
C. Hauling Cost
7,404.52 1.00 lot @ Php 1,500.00 / Day for 2 Days Php 3,000.00
3,000.00
Profit 8% 3,503.60
OCM 7% 3,066.94
Tax 7% 3,065.65
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 4 Days Php 2,400.00
2.00 Painter @ Php 550.00 / Day for 4 Days Php 4,400.00
2.00 Laborers @ Php 450.00 / Day for 4 Days Php 3,600.00
10,400.00
C. Hauling Cost
3,264.00 1.00 lot @ Php 1,500.00 / Day for 2 Days Php 3,000.00
3,000.00
Profit 8% 3,082.00
OCM 7% 2,697.89
Tax 7% 2,696.75
B. Labor:
1.00 Construction Foreman @ Php 700.00 / Day for 3 Days Php 2,100.00
1.00 Door Installer @ Php 600.00 / Day for 3 Days Php 1,800.00
2.00 Laborers @ Php 500.00 / Day for 3 Days Php 3,000.00
6,900.00
C. Hauling Cost
68.00 1.00 lot @ Php 1,500.00 / Day for 1 Days Php 1,500.00
1,500.00
Profit 8% 2,936.00
OCM 7% 1,835.00
Tax 7% 2,569.00
B. Labor:
1.00 Construction Foreman @ Php 700.00 / Day for 1 Days Php 700.00
1.00 Door Installer @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Laborers @ Php 500.00 / Day for 1 Days Php 500.00
1,800.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 440.00
OCM 7% 275.00
Tax 7% 385.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Window Installer @ Php 550.00 / Day for 1 Days Php 550.00
2.00 Laborers @ Php 450.00 / Day for 1 Days Php 900.00
2,050.00
C. Hauling Cost
34.00 1.00 lot @ Php 250.00 / Day for 1 Days Php 250.00
250.00
Profit 8% 316.00
OCM 7% 197.50
Tax 7% 276.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 2 Days Php 1,200.00
1.00 Window Installer @ Php 550.00 / Day for 2 Days Php 1,100.00
2.00 Laborers @ Php 450.00 / Day for 2 Days Php 1,800.00
4,100.00
C. Hauling Cost
102.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 616.00
OCM 7% 385.00
Tax 7% 539.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Window Installer @ Php 550.00 / Day for 0.5 Days Php 275.00
2.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 450.00
1,025.00
C. Hauling Cost
34.00 1.00 lot @ Php 250.00 / Day for 1 Days Php 250.00
250.00
Profit 8% 159.60
OCM 7% 99.75
Tax 7% 139.65
Profit 8% 1,710.80
OCM 7% 1,069.25
Tax 7% 1,496.95
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 2 Days Php 1,200.00
1.00 Tile Setters @ Php 550.00 / Day for 2 Days Php 1,100.00
1.00 Laborers @ Php 450.00 / Day for 2 Days Php 900.00
3,200.00
C. Hauling Cost
89.76 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 952.80
OCM 7% 595.50
Tax 7% 833.70
Total Cost Php 14,292.00
2.00 Php 5,413.64
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 2 Days Php 1,200.00
1.00 Plumber @ Php 550.00 / Day for 2 Days Php 1,100.00
1.00 Laborers @ Php 450.00 / Day for 2 Days Php 900.00
3,200.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 696.00
OCM 7% 435.00
Tax 7% 609.00
20mmƟ x PVC Pipe Blue Pipes, 12mmƟ PVC Blue Pipes, PVC
1.00 Elbow, PVC Tee, PVC coupling, PVC Reducer etc.
Profit 8% 616.00
OCM 7% 385.00
Tax 7% 539.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 plumber @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 248.00
OCM 7% 155.00
Tax 7% 217.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 plumber @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 728.00
OCM 7% 455.00
Tax 7% 637.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 plumber @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 488.00
OCM 7% 305.00
Tax 7% 427.00
Qty: 1.00 pc
0.00 hrs
A. Materials: hrs
1.00 pc 20mmƟ Gate Valve Php 1,050.00 /pc Php 1,050.00
1,050.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Plumber @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 148.00
OCM 7% 92.50
Tax 7% 129.50
Profit 8% 248.00
OCM 7% 155.00
Tax 7% 217.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Plumbers @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 156.00
OCM 7% 97.50
Tax 7% 136.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 3 Days Php 1,800.00
1.00 Mason @ Php 600.00 / Day for 3 Days Php 1,800.00
1.00 Plumbers @ Php 550.00 / Day for 3 Days Php 1,650.00
1.00 Laborers @ Php 450.00 / Day for 3 Days Php 1,350.00
6,600.00
C. Hauling Cost
170.00 1.00 lot @ Php 2,500.00 / Day for 1 Days Php 2,500.00
2,500.00
Profit 8% 1,208.00
OCM 7% 755.00
Tax 7% 1,057.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Plumbers @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 328.00
OCM 7% 205.00
Tax 7% 287.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 5 Days Php 3,000.00
1.00 Mason @ Php 549.00 / Day for 5 Days Php 2,745.00
1.00 Plumbers @ Php 550.00 / Day for 2 Days Php 1,100.00
2.00 Laborers @ Php 450.00 / Day for 5 Days Php 4,500.00
11,345.00
C. Hauling Cost
34.00 1.00 lot @ Php 5,000.00 / Day for 1 Days Php 5,000.00
5,000.00
Profit 8% 3,307.60
OCM 7% 2,067.25
Tax 7% 2,894.15
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 5 Days Php 3,000.00
1.00 Plumbers @ Php 550.00 / Day for 5 Days Php 2,750.00
1.00 Laborers @ Php 450.00 / Day for 5 Days Php 2,250.00
8,000.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 840.00
OCM 7% 525.00
Tax 7% 735.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
Profit 8% 340.00
OCM 7% 212.50
Tax 7% 297.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
136.00 Php -
-
Profit 8% 336.00
OCM 7% 210.00
Tax 7% 294.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 1,448.00
OCM 7% 905.00
Tax 7% 1,267.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
204.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 904.00
OCM 7% 565.00
Tax 7% 791.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
136.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 832.00
OCM 7% 520.00
Tax 7% 728.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
102.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Mterials, Labor & Equip Cost: 4,250.00
Profit 8% 340.00
OCM 7% 212.50
Tax 7% 297.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 1.00 lot @ Php 250.00 / Day for 1 Days Php 250.00
250.00
Profit 8% 324.00
OCM 7% 202.50
Tax 7% 283.50
Profit 8% 120.00
OCM 7% 75.00
Tax 7% 105.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 100.00
OCM 7% 62.50
Tax 7% 87.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 91.60
OCM 7% 57.25
Tax 7% 80.15
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
136.00 Php -
-
Mterials, Labor & Equip Cost: 2,400.00
Profit 8% 192.00
OCM 7% 120.00
Tax 7% 168.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 424.00
OCM 7% 265.00
Tax 7% 371.00
Profit 8% 1,188.00
OCM 7% 742.50
Tax 7% 1,039.50
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
3,400.00 1.00 lot @ Php 500.00 / Day for 1 Days Php 500.00
500.00
Profit 8% 688.00
OCM 7% 430.00
Tax 7% 602.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
238.00 1.00 lot @ Php 500.00 / Day for 1 Days Php 500.00
500.00
Profit 8% 118.00
OCM 7% 73.75
Tax 7% 103.25
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
272.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 304.00
OCM 7% 190.00
Tax 7% 266.00
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
68.00 1.00 lot @ Php 1,000.00 / Day for 1 Days Php 1,000.00
1,000.00
Profit 8% 179.20
OCM 7% 112.00
Tax 7% 156.80
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
272.00 Php -
-
Profit 8% 89.60
OCM 7% 56.00
Tax 7% 78.40
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
714.00 Php -
-
Profit 8% 156.40
OCM 7% 97.75
Tax 7% 136.85
Total Cost Php 2,346.00
- Php 111.71
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 0.5 Days Php 300.00
1.00 Electrician @ Php 550.00 / Day for 0.5 Days Php 275.00
1.00 Laborers @ Php 450.00 / Day for 0.5 Days Php 225.00
800.00
C. Hauling Cost
170.00 Php -
-
Profit 8% 114.00
OCM 7% 71.25
Tax 7% 99.75
B. Labor:
1.00 Construction Foreman @ Php 600.00 / Day for 1 Days Php 600.00
1.00 Electrician @ Php 550.00 / Day for 1 Days Php 550.00
1.00 Laborers @ Php 450.00 / Day for 1 Days Php 450.00
1,600.00
C. Hauling Cost
34.00 Php -
-
Profit 8% 248.00
OCM 7% 155.00
Tax 7% 217.00
4,783,566.72
Prepared by : 3,485,949.61
#REF!
ANACLETO A. MAQUILING
Owner
A. MAQUILING CONSTRUCTION AND SUPPLY
September 8, 2021
Bid no. ADM-21-0598-B
Name of Project: Construction of One(1) Classroom School Building at Barasalon Elementary School. Brgy. Barasalon, Janiuay, Iloilo
Location: Janiuay , Iloilo
₱ 10,885.50
₱ 10,504.20
Total for Item I 21,389.70
II Site Works
₱ 8,262.50
Total A 8,262.50
B. Earthworks
₱ 663.95
₱ 663.50
₱ 845.56
₱ 3,577.17
Total B 78,719.48
Total for Item II 86,981.98
₱ 6,503.83
Total for Item III 174,692.85
IV. Masonry Works
A. Masonry Wall
One Thousand Six Hundred
1 6"x8"x16" CHB 101.13 Sq.m Fifty Six Pesos & Forty Four 167,516.15
Cents
₱ 1,656.44
₱ 1,535.93
Total A 182,998.32
₱ 358.09
Total B 77,984.29
Total for Item IV 260,982.61
V. Roof and Roof Framing
₱ 1,206.82
₱ 860.34
Total for Item V 225,321.15
VI. ARCHITECTURAL WORKS
₱ 600.23
Total A 57,621.99
B. Painting Works
₱ 245.34
₱ 489.60
Total B 100,432.83
C. Door and Windowa
1 Doors
₱ 22,020.00
₱ 6,600.00
2 WINDOWS
W1-(1.20M X 2.40M) 13-
BLADER ALUMINUM
JALOUSIE FRAME W/ 22" Four Thousand Seven Hundred
a. 1.00 set 4,740.00
CLEAR GLASS JALOUSIE Forty Pesos
BLADES W/ GRILLES W/
COMPLETE ACCESSORIES
₱ 4,740.00
₱ 3,080.00
W3-(0.60M X 0.60M) 6-
BLADER ALUMINUM
JALOUSIE FRAME W/ 22" Two Thousand Three Hundred
c. 1.00 set 2,394.00
SMOKE GLASS JALOUSIE Ninety Four Pesos
BLADES W/ GRILLES W/
COMPLETE ACCESSORIES
₱ 2,394.00
Total C 67,014.00
D. TILE WORKS
₱ 2,715.56
₱ 5,413.64
Total D 39,954.00
Total for Item VI 265,022.82
VII. PLUMBING WORKS
A. SOIL & DRAINAGE PIPES LINES & FITTINGS
₱ 9,240.00
₱ 3,720.00
Total B 12,960.00
C. Fixtures & Accessories
₱ 10,920.00
Ceramic Lavatory w/ Pedestal Seven Thousand Three
2 1.00 set 7,320.00
( Including Fittings & Accessories) Hundred Pesos
₱ 7,320.00
₱ 2,220.00
₱ 1,860.00
₱ 2,340.00
Total C 26,520.00
Total for Item VII 49,920.00
VIII. Catch Basin
₱ 3,624.00
Piping System 4" PVC Pipes & Four Thousand Nine Hundred
b.) 1.00 lot 4,920.00
Fittings Twenty Pesos
₱ 4,920.00
Total for Item VIII 23,040.00
IX. Septic Tank
₱ 49,614.00
Piping System 4" PVC Pipes & Twelve Thousand Six Hundred
b.) 1.00 lot 12,600.00
Fittings Pesos
₱ 12,600.00
Total for Item IX 62,214.00
X. Electrical Works
A. Panel Board
₱ 5,100.00
Branches
20AT/50AF, 3P, 250VAC, 3ᴓ
One Thousand Two Hundred
2 Circuit Braker,(10KAIC), Bolt-on 4.00 pcs 5,040.00
Sixty Pesos
Type
₱ 1,260.00
5-Holes, 1-main, 4- Branches,
Panel Board 1ᴓ NEMA 1
Twenty One Thousand Seven
3 Enclosure Wall Surface Mounted, 1.00 unit 21,720.00
Hundred Twenty Pesos
20KA bus bracing w/ grounding
terminal
₱ 21,720.00
Total A 31,860.00
B. Lightning Fixtures
₱ 2,260.00
₱ 3,120.00
₱ 1,700.00
₱ 4,860.00
Total B 36,000.00
C. Wiring Devices
1 One Gang Switch Wide Series 2.00 sets Nine Hundred Pesos 1,800.00
₱ 900.00
₱ 1,500.00
Total C 3,300.00
D. Power Devices
₱ 1,374.00
₱ 720.00
Total D 4,254.00
E. Wires & Cables
₱ 6,360.00
3.5 Sq.mm THHN/THWN Copper Eigth Thousand Nine Hundred
2 2.00 Rolls 17,820.00
Wire Ten Pesos
₱ 8,910.00
₱ 103.20
Total E 34,500.00
F. Conduits and Fittings
₱ 252.86
2 20mmƟ Electrical PVC Pipe 8.00 lengths Five Hundred Seventy Pesos 4,560.00
₱ 570.00
₱ 1,344.00
Total F 9,018.00
G. Boxes and Full Boxes w/ Cover
1 PVC Utility Box ( 2" x 4") 8.00 pcs One Hundred Sixty Eight Pesos 1,344.00
₱ 168.00
₱ 111.71
₱ 342.00
Total G 5,400.00
H. Miscellaneous Items
₱ 3,720.00
Total for Item X 128,052.00
ONE MILLION TWO HUNDRED NINETY SEVEN THOUSAND SIX HUNDRED SEVENTEEN PESOS &
ELEVEN CENTS
-
Submitted by: -
ANACLETO A. MAQUILING
Owner
21,389.70
86,981.98
174,692.85
260,982.61
225,321.15
265,022.82
49,920.00
23,040.00
62,214.00
128,052.00
1,297,617.11
-
ITEM NO. QTY. UNIT ARTICLES/SERVICES DESCRIPTION UNIT COST TOTAL ABC/ITEM BID PRICE/ITEM TOTAL BID PRICE
PART B Other General Requirements
B.4(9) #NAME? #NAME? #NAME? 1,344.44 53,777.54 #NAME? #NAME?
Other General Requirements1.00 lot - 8905.08 Php 17,810.15 10,885.50 10,885.50
A. 1 lot Lay-out and Staking 34,430.90 160,792.31 8,262.50 8,262.50
Php 1,297,617.11
Submitted by:
ANACLETO A. MAQUILING
Owner
A. MAQUILING CONSTRUCTION AND SUPPLY
September 8, 2021
Contract ID. ADM-21-0598-B
Project Name: Construction of One(1) Classroom School Building at
Barasalon Elementary School. Brgy. Barasalon, Janiuay,
Contract Location: Janiuay , Iloilo
Iloilo
Position: Owner