DETAILED ESTIMATES
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Marine Plywood 4.00 pcs 800.00 3,200.00
Coco lumber 75.00 bd.ft. 50.00 3,750.00
Tarpaulin 64.00 sq.ft. 35.00 2,240.00
Common Wire Nails 5.00 kgs 100.00 500.00
Sub - Total 9,690.00
b. Labor
Description Qty No. of Day Rate/Day Total
Mason/Carpentry 1.0 1.0 600.00 600.00
Laborer/Helper 1.0 1.0 500.00 500.00
Sub - Total 1,100.00
a. Materials
Description QTY. UNIT UNIT COST AMOUNT
Safety Shoes(Different Sizes) 15.00 pairs 600.00 9,000.00
Safety Helmet (free size) 15.00 pcs. 600.00 9,000.00
Safety Gloves (free size) 16.00 pairs 600.00 9,600.00
Temporary Bollards 32.00 pcs. 200.00 6,400.00
Caution Tape 2.00 rolls 1,880.00 3,760.00
Sub - Total 37,760.00
b. Labor
Description Qty No. of Day Rate/Day Total
Safety Officer 1.0 30.0 600.00 18,000.00
Sub - Total 18,000.00
Direct Cost 55,760.00
Indirect Cost
OCM
Profit 5,576.00
Tax 7,360.32
Direct + Indirect Cost 68,696.32
Unit Price 24,534.40 mo.
Total for Item B.7(1) 68,696.32
Surplus Common
102(2) Qty.= 188.67 cu.m.
Excavation
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Sub - Total -
b. Labor
Project Engineer 1.00 2.00 800.00 1,600.00
Foreman 1.00 2.00 700.00 1,400.00
Mason/Carpentry 1.00 2.00 600.00 1,200.00
Helper 5.00 2.00 450.00 4,500.00
Sub - Total 8,700.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Backhoe 1.00 1.00 15,500.00 15,500.00
Dump truck 2.00 1.00 10,500.00 21,000.00
Sub - Total 36,500.00
Structure Excavation
103(1)a Qty.= 280.24 cu.m.
(Common Soil)
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Sub - Total -
b. Labor
Project Engineer 1.00 3.00 800.00 2,400.00
Foreman 1.00 3.00 700.00 2,100.00
Mason/Carpentry 1.00 3.00 600.00 1,800.00
Helper 3.00 3.00 450.00 4,050.00
Sub - Total 10,350.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Backhoe 1.00 3.00 15,500.00 46,500.00
Dump truck 1.00 3.00 10,500.00 31,500.00
Sub - Total 78,000.00
Embankment from
104(1)a Roadway Excavation Qty.= 388.02 cu.m.
(Common Soil)
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Sub - Total -
b. Labor
Project Engineer 1.00 3.00 800.00 2,400.00
Foreman 1.00 3.00 700.00 2,100.00
Mason/Carpentry 1.00 3.00 600.00 1,800.00
Helper 3.00 3.00 450.00 4,050.00
Sub - Total 10,350.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Backhoe 1.00 3.00 15,500.00 46,500.00
Dump truck 1.00 3.00 10,500.00 31,500.00
Sub - Total 78,000.00
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Sub - Total -
b. Labor
Project Engineer 1.00 4.00 800.00 3,200.00
Foreman 1.00 4.00 700.00 2,800.00
Mason/Carpentry 1.00 4.00 600.00 2,400.00
Helper 2.00 4.00 450.00 3,600.00
Sub - Total 12,000.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Road Grader 1.00 4.00 14,800.00 59,200.00
Road Roller 1.00 4.00 11,800.00 47,200.00
Sub - Total 106,400.00
Aggregates Subbase
200(1) Qty.= 1,403.12 cu.m.
Course
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Item 200 1,403.12 cu.m. 850.00 1,192,652.00
Sub - Total 1,192,652.00
b. Labor
Project Engineer 1.00 4.00 800.00 3,200.00
Foreman 1.00 4.00 700.00 2,800.00
Mason/Carpentry 1.00 4.00 600.00 2,400.00
Helper 3.00 4.00 450.00 5,400.00
Sub - Total 13,800.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Road Grader 1.00 4.00 14,800.00 59,200.00
Ware Truck 1.00 4.00 9,500.00 38,000.00
Road Roller 1.00 4.00 11,800.00 47,200.00
Sub - Total 144,400.00
a. Materials
Description QTY, UNIT UNIT COST AMOUNT
Pre-mix with additives 931.50 cu.m. 8,200.00 7,638,300.00
Curing Compound 4.00 drum 16,000.00 64,000.00
Asphalt 7.00 bag 4,000.00 28,000.00
Sub - Total 7,730,300.00
b. Labor
Project Engineer 1.00 28.00 800.00 22,400.00
Foreman 1.00 28.00 700.00 19,600.00
Mason/Carpentry 5.00 28.00 600.00 84,000.00
Helper 18.00 28.00 450.00 226,800.00
Sub - Total 352,800.00
c. Equipment
Description QTY, UNIT UNIT COST AMOUNT
Concrete Cutter 1.00 25.00 1,500.00 37,500.00
Sub - Total 37,500.00
Prepared By:
CONTRACT I.D. NO. : 24GK0065
CONTRACT NAME: Construction of Road, Barangay Damgo, Municipality of EB
Magalona, Negros Occidental
LOCATION: EB Magalona, Negros Occidental
84 Days Duration
Description 1st 2nd 3rd 4th
QUARTERLY % ACCOMPLISHMENT 25.00 25.00 25.00 25.00
PHYSICAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE % 50.00
ACCOMPLISHMENT 25.00 75.00 100.00
QUARTERLY CASHFLOW 3,638,272.58 3,638,272.58 3,638,272.58 3,638,272.58
FINANCIAL
ACCOMPLISHMENT QUARTERLY CUMULATIVE CASH
FLOW 3,638,272.58 7,276,545.16 10,914,817.74 14,553,090.32
Total 14,553,090.32
Prepared By:
CONTRACT I.D. NO. : 24GK0065
CONTRACT NAME: Construction of Road, Barangay Damgo, Municipality of EB
Magalona, Negros Occidental
LOCATION: EB Magalona, Negros Occidental
BILL OF QUANTITIES
Pay
Amount
Item Description Unit Quantity Unit Price (Pesos)
(Pesos)
No.
Part B OTHER GENERAL REQUIREMENTS
6,646.64 13,293.28
24,534.40 68,696.32
16,100.00 45,080.00
216,944.00 216,944.00
#NAME?
Total of Part B
344,013.60
Part C EARTHWORKS
308.57 58,217.90
406.06 113,794.25
293.27 113,794.63
One Hundred Fifty Two
Sub Grade Preparation Thirty & 36/100 Pesos Only Thousand Five Hundred Eighteen
105(1)a sq.m. 5,022.00 & 14/100 Pesos Only
(Common Material)
30.37 152,518.14
#NAME?
Total of Part C
438,324.92
Part D SUBBASE AND BASE COURSE
1,240.02 1,739,896.86
#NAME?
Total of Part D
1,739,896.86
Part E SURFACE COURSES
2,582.55 10,459,327.50
#NAME?
Total of Part E
10,459,327.50
3,864.00 1,571,527.44
#NAME?
Total of Part G
1,571,527.44
14,553,090.32
Prepared By:
Department of Public Works and Highways
CONTRACT I.D. NO. : 24GK0065
CONTRACT NAME: Construction of Road, Barangay Damgo, Municipality of EB
Magalona, Negros Occidental
LOCATION: EB Magalona, Negros Occidental
Total
Part No. Part Description
Amount
Part B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/ Signboard 13,293.28
B.7(1) Occupational Safety and Health Program 68,696.32
B.8(1) Traffic Management 45,080.00
B.9 Mobilization/Demobilization 216,944.00
Total of Part B 344,013.60
Part C EARTHWORKS
Surplus Common
102(2) Excavation
Structure Excavation 58,217.90
103(1)a (Common Excavation
Roadway Soil) 113,794.25
104(1)a (Common
Sub GradeSoil)
Preparation 113,794.63
105(1)a (Common Material) 152,518.14
Total of Part C 438,324.92
Part D SUBBASE
Aggregates AND BASE COURSE
Subbase
200(1) Course 1,739,896.86
Total of Part D 1,739,896.86
Part E SURFACE COURSES
(Unreinforced) 0.230m
311(1)c1 thk(14 days) 10,459,327.50
Total of Part E 10,459,327.50
Part G DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap - Class A 1,571,527.44
Total of Part G 1,571,527.44