Professional Documents
Culture Documents
DETAILED ESTIMATES
A. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (cu.m/manday)
Total
24,000.00
B. Equipment Cost
Equipment Requirement Output per
Activity Rate per day
Day Total
Particular Equpt. Rqd. Duration (840/hr @ 6hrs)
(cu.m./day)
Mini Dump Truck 2 5.0 2,200.00
22,000.00
Jack Hammer with Compressor 1 7.0 4,100.00
28,700.00
Total
50,700.00
A. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (cu.m/manday)
Laborer 5 1 5.0 300.00
7,500.00
Total
7,500.00
B. Equipment Cost
Equipment Requirement Output per
Activity Rate per day
Day Total
Particular Equpt. Rqd. Duration (840/hr @ 6hrs)
(cu.m./day)
Backhoe, PC 60 1 2 8,800.00
17,600.00
Mini Dump Truck 1 1 2,200.00
2,200.00
Chainsaw 1 2 1,000.00
2,000.00
Total
21,800.00
Total
46,224.00
Direct Cost 46,224.00
Profit 3,651.70
O.C.M. 4,160.16
V.A.T. 2,701.79
Total Indirect
10,513.65
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenters 8 #DIV/0! 350.00 #DIV/0!
Laborers 8 #DIV/0! 0.00 #DIV/0!
Total #DIV/0!
V.A.T.
#DIV/0!
Total Indirect #DIV/0!
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenters 8 1.0 350.00
2,800.00
Laborers 8 1.0 300.00 2400.00
Total
5,200.00
A. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (cu.m/manday)
Laborer 6 8.0 300.00
14,400.00
Total
14,400.00
B. Equipment Cost
Equipment Requirement Output per
Activity Rate per day
Day Total
Particular Equpt. Rqd. Duration (840/hr @ 6hrs)
(cu.m./day)
Backhoe, Wheel Type PC30 1 8.0 6,300.00
50,400.00
Mini Dump Truck 2 8.0 2,200.00
35,200.00
Total
85,600.00
Total
80,520.00
B. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (cu.m/manday)
Laborer 6 10 300.00
18,000.00
Total
18,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Plate Compactor 1 7.0 650.00
4,550.00
Total
4,550.00
2.03 Embankment
B. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (cu.m/manday)
Laborer 10 13.0 300.00
39,000.00
Total
39,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Plate Compactor 2 7.0 500.00
7,000.00
Total
7,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Pump Crete 1 22.0 8,850.00
194,700.00
Concrete Vibrator 2 22.0 1,050.00
46,200.00
Total
240,900.00
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Mason 2 50.0 350.00
35,000.00
Laborer 8 50.0 300.00
120,000.00
Total
155,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
One-Bagger Concrete Mixer 1 50.0 1,250.00
62,500.00
Total
62,500.00
Total
4,605,708.67
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Steelman 10 48.0 350.00
168,000.00
Laborer 10 48.0 300.00
144,000.00
Total
312,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Mobile Crawler Crane 1 48.0 7,000.00
336,000.00
Welding Machine 10 48.0 450.00
216,000.00
H-Frame w/ Cross Bracing
40 48.0 49.00
and Joint Pin 94,080.00
One-Tank Oxygen/ 2-Tank Acetylene 10 set 4,350.00
43,500.00
Electric Grinder 8 48.0 145.00
55,680.00
Provision for Electricity
113,931.29
Total
859,191.29
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Steelman 10 117.0 350.00
409,500.00
Laborer 10 117.0 300.00
351,000.00
Total
760,500.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Bar/Shear Cutter 4 117.0 250.00
117,000.00
Total
117,000.00
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Welder 10 8.0 350.00
28,000.00
Helper 10 8.0 300.00
24,000.00
Total
52,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equipt. Rqd. Day Duration
Welding Machine 10 8.0 450.00
36,000.00
Boom w/ Chainblock 2 8.0 2,500.00
40,000.00
Mobile Crawler Crane 1 8.0 7,000.00
56,000.00
H-Frame Scaffoldings 40 8.0 150.00
48,000.00
One-Tank Oxygen/ 2-Tank Acetylene 4 set 4,350.00
17,400.00
Electric Grinder 6 8.0 145.00
6,960.00
Provision for Electricity
17,188.25
Total
221,548.25
A. Material Cost
Materials
Description of Materials Unit Unit Price Total Cost
Quantity
50mmØ G.I. Pipe Sched. 40 248 le. 1,759.50 436,356.00
19mm Square Bar 302 le. 676.25 204,227.50
Red Oxide Paint 26 gal. 460.00 11,960.00
Paint Thinner 24 gal. 302.00 7,248.00
Welding Rod 266.5 kg. 135.00 35,977.50
Total Material Cost
695,769.00
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total Cost
Designation Day Duration
Rqd.
Welder 2 64.0 350.00
44,800.00
Laborer 2 64.0 300.00
38,400.00
Total Labor Cost
83,200.00
C. Equipment Cost
Equipment Requirement
Output per Activity
Equipment Rate per day Total Cost
Designation Day Duration
Rqd.
Welding Machine 2 64.0 450.00
57,600.00
Electric Grinder 1 64.0 4,350.00
278,400.00
Provision for Power Consumption
15,961.90
Total Equipment Cost
351,961.90
C. Equipment Cost
Equipment Requirement
Output per Activity
Equipment Rate per day Total Cost
Designation Day Duration
Rqd.
Welding Machine 2 29.5 450.00
26,550.00
Provision for Power Consumption
3,000.00
Total Equipment Cost
29,550.00
Total Cost of
1,559,801.06
Item
Unit Cost 2,755.64
Adjusted Cost 1,559,803.79
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Mason 10 21.0 350.00
73,500.00
Laborer 10 21.0 300.00
63,000.00
Total
136,500.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Total Cost of
1,413,748.68
Item
Unit Cost 846.13
Adjusted Cost 1,413,756.31
7.02 Plastering/Finishing
Qty. = 3,709.78 sq.m.
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Mason 10 38.0 350.00
133,000.00
Laborer 10 38.0 300.00
114,000.00
Total
247,000.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Concrete Mixer 3 38.0 1,250.00
142,500.00
Total
142,500.00
Total Cost of
874,698.06
Item
Unit Cost 235.78
Adjusted Cost 874,691.93
8.00 ROOFING & TINSMITHRY WORKS
B. Labor Cost
Manpower Requirement
Activity
Manpower Rate per day Total
Designation Duration
Rqd.
Tinsmith 4 14.0 350.00
19,600.00
Helper/Laborer 4 14.0 300.00
16,800.00
Total
36,400.00
C. Equipment Cost
Equipment Requirement Activity
Rate per day Total
Particular Equpt. Rqd. Duration
Electric Handrill 4 14.0 150.00
8,400.00
Total
8,400.00
B. Labor Cost
Manpower Requirement Output per
Activity
Manpower Day Rate per day Total
Designation Duration
Rqd. (ln.m/manday)
Tinsmith 2 12.0 350.00
8,400.00
Helper/Laborer 2 12.0 300.00
7,200.00
Total
15,600.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equpt. Rqd. Day Duration
Electric Handrill 2 12.0 150.00
3,600.00
Total
3,600.00
Total Cost of
148,841.82
Item
Unit Cost 809.45
Adjusted Cost 148,841.67
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 2 1 29.0 350.00
20,300.00
Helper 2 1 29.0 300.00
17,400.00
Total
37,700.00
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 1 1 5.0 350.00
1,750.00
Helper 1 1 5.0 300.00
1,500.00
Total
3,250.00
Total Cost of
34,865.11
Item
Unit Cost 6,973.02
Adjusted Cost 34,865.10
9.01.3 Hollow Core Flush Door, D3 - 0.70m x 2.10m
Qty. = 10.00 unit
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 2 1 5.0 350.00
3,500.00
Helper 2 1 5.0 300.00
3,000.00
Total
6,500.00
Total Cost of
69,459.86
Item
Unit Cost 6,945.99
Adjusted Cost 69,459.90
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 2 1 13.0 350.00
9,100.00
Helper 2 1 13.0 300.00
7,800.00
Total
16,900.00
Total Cost of
120,558.24
Item
Unit Cost 4,822.33
Adjusted Cost 120,558.25
9.01.5 Hollow Core Flush PWD Door with Louver, D4 - 1.00m x 2.10m
Qty. = 1.00 unit
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 1 1 1.0 350.00
350.00
Helper 1 1 1.0 300.00
300.00
Total
650.00
Total Cost of
8,190.78
Item
Unit Cost 8,190.78
Adjusted Cost 8,190.78
9.02 Window
9.02.1 Jalougrill Window, W1 - 3.550m x 1.50m
Qty. = 29.00 unit
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Installer/ Welder 4 1 8.0 350.00
11,200.00
Helper 4 1 5.0 300.00
6,000.00
Total
17,200.00
Total Cost of
289,081.44
Item
Unit Cost 9,968.33
Adjusted Cost 289,081.57
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Installer/ Welder 2 1 18.0 350.00
12,600.00
Helper 2 1 18.0 300.00
10,800.00
Total
23,400.00
Total Cost of
390,162.18
Item
Unit Cost 11,147.49
Adjusted Cost 390,162.15
Total Cost of
20,626.81
Item
Unit Cost 5,156.70
Adjusted Cost 20,626.80
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Installer/ Welder 2 1 8.0 350.00
5,600.00
Helper 2 1 8.0 300.00
4,800.00
Total
10,400.00
Total Cost of
72,366.58
Item
Unit Cost 4,522.91
Adjusted Cost 72,366.56
Total Cost of
3,016.93
Item
Unit Cost 3,016.93
Adjusted Cost 3,016.93
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 3 - 15.0 350.00
15,750.00
Helper/Laborer 3 - 15.0 300.00
13,500.00
Total
29,250.00
Total Cost of
100,384.85
Item
Unit Cost 700.03
Adjusted Cost 100,384.30
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 3 - 20 350.00
21,000.00
Helper/Laborer 3 - 20 300.00
18,000.00
Total
39,000.00
Total Cost of
155,881.24
Item
Unit Cost 999.24
Adjusted Cost 155,881.44
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 3 - 15.0 350.00
15,750.00
Helper/Laborer 3 - 15.0 300.00
13,500.00
Total
29,250.00
Total Cost of
158,448.76
Item
Unit Cost 3,574.03
Adjusted Cost 158,448.66
Materials
Description of Materials Unit Unit Price Total Cost
Quantity
6" Thk. CHB 314 pc. 15.50 4,867.00
10mmØ x 6.00 def. bars 43 lght. 170.00 7,310.00
Portland Cement 37 bag 266.00 9,842.00
Washed Sand 2.5 cu.m. 646.00 1,615.00
Gravel Class "A" 1.0 cu.m. 610.00 610.00
Gravel YY 3.0 cu.m. 780.00 2,340.00
Ga # 16 Tie Wire 4 kg. 79.00 316.00
Total Material Cost
26,900.00
B. Labor Cost (Including Excavation Works)
Manpower Requirement
Activity
Manpower Output per day Rate per day Total
Designation Duration
Rqd.
Plumber/Mason 2 - 8.0 350.00
5,600.00
Helper/Laborer 4 - 8.0 300.00
9,600.00
Total Labor Cost
15,200.00
Total Cost of
51,675.65
Item
Unit Cost 3,229.73
Adjusted Cost 51,675.68
Total Cost of
26,836.97
Item
Unit Cost 8,945.66
Adjusted Cost 26,836.98
Total Cost of
117,277.47
Item
Unit Cost 117,277.47
Adjusted Cost 117,277.47
10.07 Fixtures
B. Labor Cost
Manpower Requirement Activity
Output Rate per day Total
Designation Requirement Duration
Total Cost of
177,121.04
Item
Unit Cost 7,084.84
Adjusted Cost 177,121.00
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 2 - 10.0 350.00
7,000.00
Helper/Laborer 2 - 10.0 300.00
6,000.00
Total
13,000.00
Total Cost of
70,455.63
Item
Unit Cost 3,522.78
Adjusted Cost 70,455.60
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 2 - 15.0 350.00
10,500.00
Helper/Laborer 2 - 15.0 300.00
9,000.00
Total
19,500.00
Total Cost of
191,675.53
Item
Unit Cost 6,389.18
Adjusted Cost 191,675.40
B. Labor Cost
Manpower Requirement
Activity
Manpower Output Rate per day Total
Designation Duration
Rqd.
Plumber 2 - 2.0 350.00
1,400.00
Helper/Laborer 2 - 2.0 300.00
1,200.00
Total
2,600.00
Total Cost of
13,526.50
Item
Unit Cost 3,381.63
Adjusted Cost 13,526.52
B. Labor Cost
Manpower Requirement Output Activity Rate per day Total
Manpower Duration
Designation
Rqd.
Plumber 2 - 3.5 350.00
2,450.00
Helper/Laborer 2 - 3.5 300.00
2,100.00
Total
4,550.00
Total Cost of
38,284.17
Item
Unit Cost 3,190.35
Adjusted Cost 38,284.20
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Electrician 2 75
350.00 52,500.00
C. Equipment Cost
Equipment Requirement
Output per Activity
Equipment Rate per day Total
Designation Day Duration
Rqd.
Electric Edger 2 75 500.00
75,000.00
Total
75,000.00
Total Cost of
1,625,696.89
Item
Unit Cost 4,553.77
Adjusted Cost 1,625,695.89
B. Installation of Transformer
Qty = 1.00 lot
Total Cost of
55,235.25
Item
Unit Cost 55,235.25
Adjusted Cost 55,235.25
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Mason 8 14.0 350.00
39,200.00
Laborer 8 14.0 300.00
33,600.00
Total
72,800.00
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equipt. Rqd. Day Duration
Tile Cutter 8 14.0 200.00
22,400.00
Total
22,400.00
Total Cost of
504,083.14
Item
Unit Cost 1,204.96
Adjusted Cost 504,082.60
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
Carpenter 8 8.0 350.00
22,400.00
Laborer 8 8.0 300.00
19,200.00
Total
41,600.00
C. Equipment Cost
Output per Activity
Equipment Requirement Rate per day
Day Duration Total
Particular Equipt. Rqd.
Electric Drill 8 8.0 150.00
9,600.00
Total
9,600.00
Direct Cost 231,444.04
Profit 18,284.08
O.C.M. 20,829.96
V.A.T.
13,527.90
Total Indirect
52,641.94
Total Cost of
284,085.98
Item
Unit Cost 516.75
Adjusted Cost 284,083.31
Designation Length (m) Width (m) Height (m) No. of Face Area (sq.m.)
Eaves A = 313.5 sqm. 1 313.52
Total Area
313.52
C. Equipment Cost
Output per Activity
Equipment Requirement Rate per day
Day Duration Total
Particular Equipt. Rqd.
Electric Drill 8 5.0 200.00
8,000.00
Total
8,000.00
Total Cost of
338,873.79
Item
Unit Cost 1,080.87
Adjusted Cost 338,874.36
C. Equipment Cost
Equipment Requirement Output per Activity
Rate per day Total
Particular Equipt. Rqd. Day Duration
Electric Drill 2 9.0 200.00
3,600.00
Total
3,600.00
Total Cost of
66,242.04
Item
Unit Cost 397.13
Adjusted Cost 66,241.28
Total
320,973.15
Total Cost of
393,978.49
Item
Unit Cost 9,267.25
Adjusted Cost 393,978.60
B. Labor Cost
Manpower Requirement
Output (sq.m Activity
Manpower Rate per day Total
Designation per manday) Duration
Rqd.
Painter 10 28.5 350.00
99,878.69
Helper 10 28.5 300.00
85,610.31
Total
185,489.00
Direct Cost 604,415.00
Profit 47,748.79
O.C.M. 54,397.35
V.A.T.
35,328.06
Total Indirect
137,474.20
Total Cost of
741,889.20
Item
Unit Cost 199.98
Adjusted Cost 741,881.80
B. Labor Cost
Manpower Requirement
Output (sq.m Activity
Rate per day Total
Manpower per manday) Duration
Designation
Rqd.
Painter 8 11.0 350.00
30,800.00
Helper 8 11.0 300.00
26,400.00
Total
57,200.00
Total Cost of
318,031.99
Item
Unit Cost 443.84
Adjusted Cost 318,033.55
Materials
Description of Materials Unit Unit Price Total Cost
Quantity
Total
20,048.00
Total Cost of
24,607.92
Item
Unit Cost 6,151.98
Adjusted Cost 24,607.92
Total Cost of
12,338.33
Item
Unit Cost 12,338.33
Adjusted Cost 12,338.33
Total
303,370.00
B. Labor Cost
Manpower Requirement
Output (sq.m Activity
Manpower Rate per day Total
Designation per manday) Duration
Rqd.
Mason 2 6.5 350.00
4,550.00
Laborer 8 17.0 300.00
40,800.00
Steelman 8 3.0 350.00
8,400.00
Painter 2 1.5 350.00
1,050.00
Total
54,800.00
C. Equipment Cost
Output per Activity
Equipment Requirement Rate per day
Day Duration Total
Particular Equipt. Rqd.
Plate Compactor 2 1.5 500.00
1,500.00
One-Bagger Concrete Mixer 1 6.5 1,250.00
8,125.00
Bar/Shear Cutter 4 3.0 250.00
3,000.00
Total
12,625.00
B. Labor Cost
Manpower Requirement
Output per Activity
Manpower Rate per day Total
Designation Day Duration
Rqd.
First Aider/Part Time Practitioner 354 54,600.00 54,600.00
Total
54,600.00
Total Cost of
77,263.04
Item
Unit Cost 77,263.04
Adjusted Cost 77,263.04
SPL-III BILLBOARD
Qty. = 1.00 unit
1 DAY
A. Quantity Take-Off and Costing
Materials
Description of Materials Unit Unit Price Total Cost
Quantity
8' x 8' Tarpaulin on 5mm Thk Marine Plywood with Helevitica Font
(70 dpi) 3" Text Main Information on 2"x2" Lauan Lumber Wooden 1.00 unit 4,070.00
Frame with Stand 4,070.00
Total
4,070.00
Total Cost of
5,000.00
Item
Unit Cost 5,000.00
Adjusted Cost 5,000.00