SHAURYA CEMENT INDUSTRIES PRIVATE LIMITED

DAILY REPORT: 04.01.2021

Man Power Statement


Description 30.12.2020 31.12.2020 01.01.2021 02.01.2021 03.01.2021 04.01.2021
Civil-plant building 256 260 260 260 260
Mechanical 252 222 Holiday 210 210 210
Electrical 42 42 40 40 40
Ayoki staff 23 23 23 23 23
TOTAL 573 547 547 533 533 533
Shree Krishna 266 355 276 346 346 344
Engineering
Rajpooth 33 80 46 76 76 76
Grand total 872 982 869 955 955 953
Refractory Man power : 34
Shree Krishna man power details:
Insulation man power : 28
Mechanical: 200
On 05.01.2021 Refractory Man power Strike Electrical : 70
Civil : 68
Staff : 06

Daily Progress Report as on 04.01.2021 Daily progress report Mechanical :

1. Preheater :- Columns & beam reinforcement Fabrication :


& shuttering in progress and casting in progress at
4 mtr level * Raw mill monorail and brackets fabrication under progress
2. TG Building :- DE shuttering work in progress * ESP roof plate items fabrication under progress
3. CCR Building :- Grade slab exuviation leveling * Additive/Coal crusher Monorail fabrication under progress
and dressing work in progress between clinker * Gratings fabrication under progress
cooler house
4. Additive coal storage: - Backfilling work under Erection :
progress.
5. ADM Plastering work in progress * TT 2 staircase welding work under progress
6. Boundary wall: - Construction in progress. * 231.BC 440 Magnetic separator extended chute erection under
7. Packing Plant :- Blocks massonery and progress
plastering work under progress * AQC boiler outlet hopper fit up under progress
8. Water Reservoir Tank: - PCC and RCC work in * Raw mill roller lubrication and gearbox lubrication testing under
progress & Reinforcement work in progress. progress
9. Clinker tank. Prestressing and grouting work in * ESP weather enclosure erection under progress
progress. 10. MRSS. * Belt conveyor 133.BC 100 maintenance platform erection under
Precast construction in progress for cable trench progress
and gate construction in progress * Coal mill hot air duct welding under progress
11.Cooling tower. Backfilling, Reinforcement and * Clinker cooler building handrails painting and finishing work
shuttering work in progress under progress
12. Switch yards. Earth pits construction in * Belt conveyor 131.BC 520 and 133.BC 560 walkway handrails
progress & leveling work in progress painting under progress
13. NEA. Switch yards. Manual exuviation in * Raw mill feed building handrails finishing and painting under
progress for earthling flats. progress
* Coal mill building staircase and platforms handrails finishing
and painting under progress
* Raw mill fan area handrails fixing under progress
* Cooler duct damper maintenance platform erection under
progress
* AQC boiler Drum supporting structure ground assembly under
progress
* Coal mill hot air duct erection under progress
* Coal mill venting lines erection under progress
* Belt conveyor 231.BC 440 walkway handrails work under
progress
* Outside building airline erection under progress
*Clinker silo chutes liner fixing and erection under progress
*133.BC560 hand rail painting under progress
*Coal/additive intake and crusher punch points works under
progress
*133.BC420 belt conveyor alignment under progress
* 481.BC600 Belt laying & Jointing under progress
*131.BC100 shed sheeting work under progress
Rain status: 0.0mm

SCIPL / Stores Report / 04 Jan'2020

>>>Inward>>>

1. Sagarmattha suppliers

a. Aggregate - 04 loads.
b. Sand - 61 loads.
C. Bolder - 09 loads.

2. Gravel - 07 loads From Balua gitti washing.

3. OPC cement 2940 Bag From Riddhi Siddhi.

4. Diesel - 2640 Ltr From jay Deepak trade center.

5. Lime stone - 6454.33 Mt / 231 Loads.


a. Dumping yard - 2849.43 Mt / 97 Loads.
b. Scl galter mines - 3604.90 Mt / 134 Loads.

6. Oxygen refill - 10 Nos From Dhalkewar gas.

7. SSR Rectifier block 2 Amp - 04 Nos From shyam electric house.

<<Outward <<

1. Limestone - Nil
LIME STONE REPORT
Opening Stock Inward Outward Closing Stock
459396.3 MT 6454.33 MT 0 MT 465850.63 MT
COAL REPORT
Opening Stock Inward Closing Stock
13363.33 MT 0 MT 13363.33 MT
Site photographs:

Coal duct welding work u/p

231Bc440 magnetic separator extended chute


Motor alignment work
WHRS outlet hopper welding work u/p

Raw mill roller lubrication and gear box lubrication testing


Esp floor handrailing welding work u/p

TT2 staircase welding work u/p


Photographs: Site:

Packing plant shuttering work

Boundary wall shuttering work


Raw water tank RCC work

Switch yard earthling side wall work


Concrete work around earth pits at CCR

Silo aeration blowers room shuttering work


Cooling tower RCC raft work