You are on page 1of 4

Project: Proposed Three Storey Residence with Basement

Location: Lot 1 Blk18 Mactan St. Ayala Heights Subd., Old Balara, Quezon City
Subcontractor: Ronnie Galapago
Subject : Progress Billing No. 1 (Electrical Works )

Items ELECTRICAL WORKS 1.0000 % 9.0846


1 Conduits and Boxes
1.1 Main Power Service Entrance System
1.1.1 Rigid Steel Conduits 0.014 0.0000
1.1.2 Power Line PVC Conduits 0.072 25 1.8045
1.1.3 PABX / Telecomms PVC Conduits 0.036 5 0.1804
1.1.4 CATV PVC Conduits 0.009 5 0.0462
1.1.5 CCTV PVC Conduits 0.012 5 0.0606
1.1.6 Miscellaneous Conduits 0.016 25 0.4084
1.1.7 Cable Trays and Wireways
1.1.8 Utility Boxes & Pull Boxes 0.043 25 1.0710
1.1.9 Main Grounding System 0.002 0 0.0000
1.1.10 Cistern-to-Distribution Elec System 0.002 5 0.0122
1.20 Emergency Generator Elec System
Sump Pit Electrical System 0.002 0.0000
2.0 Panel Boards and Breakers
Panel Boards 0.188 5 0.9416
3.0 Wires and Cables
3.10 Power & Lighting Wires 0.285 10 2.8520
3.20 LAN Cables 0.010 0.0000
3.30 PABX Wires 0.027 0.0000
CATV Wires 0.036 0.0000
Miscellaneous Wires 0.001 25 0.0335
Wiring Devices
Power Outlets 0.079 10 0.7895
Switches 0.009 10 0.0871
Auxiliary Outlets 0.005 0.0000
Lighting Fixtures
Lighting Fixtures 0.063 0.0000
Site Supervision 0.080 10 0.7975
As Built Plans 0.006 0.0000
Quezon City
November 04, 2021

Project: Proposed Three Storey Residence with Basement


Location: Lot 1 Blk18 Mactan St. Ayala Heights Subd., Old Balara, Quezon City
Subcontractor: Ronnie Galapago
Subject : Progress Billing No. 1 (Electrical Works )

STATEMENT OF ACCOUNTS

CONTRACT AMOUNT 200,000.0


ACTUAL PERCENTAGE COMPLETION 9.08%

PROGRESS AMOUNT 18,169.2

TOTAL PROGRESS AMOUNT TO DATE Php 18,169.22


Less:
Mobilization 1,816.92

10% Retention 1,816.92

TOTAL AMOUNT COLLECTIBLE TO DATE Php 14,535.38