2 Proposal :-
It is proposed to upgrade the existing road by way of P/L of 100mm
thick wet mix,50mm thick bituminous macadam,25 mm thick semi-
dense with 6mm thick seal coat.
All standard norms as prescribed by PWD/IRC shall be followed during
execution of the road as it shall prove to be the main connecting link of
area. All measures shall be taken to make the road eco-friendly.
3 ROAD GEOMETRICS
Route Selection: - The roads are already constructed and pass through
agricultural/horticultural area and do not pass through any forest
sanctuary or cultural heritage area.
C) Pavement:
Pavement will be strengthened as per CBR test. As per this the
additional thickness shall be achieved by providing one coat of WBM-
II ,WBM-III for the entire length and finally 100mm thick wet
mix,50mm macadam and 25mm thick semi-dense. with 6mm thick seal
coat
Other features: Side drain (pacca) shall be constructed in M-10 cement
concrete in built up areas .In non-built up areas earthen drains shall be
provided keeping in view the angle of response of soil ,pipes of
D suitable diameter will be laid at places of necessity ,R-Wall/B-walls
shall be constructed in cement concrete at places of most necessity.
6 Material specification:-
i Enhanced production.
ii Reduction in wastage of marketable surplus.
iii Savings in vehicle operating cost.
iv Savings due to reduction in travel time.
Further the improved connectivity will enhance the proper flow of
technology services especially that of health services and availability of
agricultural inputs.
8 COST ESTIMATES:
The cost estimates as per enclosed annexure include all the works
needed for the execution of strengthening/Upgradation of the road to
proper specifications. The estimates have been framed on PWD
sanctioned schedule of rates in vogue which is based on IRC/MOST
specifications.
TIME OF COMPLETION: -
The project will be completed in one working
Season.
Abstract of Cost For
Construction of Road from Main Road Sedow to Pati -TuliHallan,Mandath to Forest Hut Via Ganie
Mohalla with Interior Links Sedow Incl.Chotipora Nardpora,Gazi Shah and Nazir Chowdary link
Road
Amount
S. No. Item of work Unit Qty. Rate (in
lacs)
1 Earth work
i Earth work cutting Cum 6720 170 11.42
ii Earth work in filling Cum 4567 200 9.13
2 Pavement
i Granular Sub Base Course Cum 2625 700 18.38
ii Providing and laying of WBM Grade-II Cum 1631 2000 32.62
iii Providing and laying of WBM Grade-III Cum 2475 2300 56.93
iv Providing / Laying of 50mm thick
Cum 1650 7500 123.75
bituminous macadam.
v Providing/ Laying of 25 mm thick
Sqm 33000 350 115.50
semidense
3 X-Dranage
i 8m Span RCC Culverts No. 1 9.70 9.70
ii 6m Span RCC Culverts No. 1 33.97 33.97
iii 4M Span RCC Culvert for No. 1 9.70 9.70
iv 3M Span RCC Culvert for No. 1 9.70 9.70
v Construction of 2M Span RCC Culvert No. 2 9.70 19.40
vi Pipe Laying
vii a) 36" dia Rm 70 7000 4.90
viii b) 18" dia Rm 60 4500 2.70
ix c) 10" dia M.S. Pipe Rm 20 13000 2.60
4 Construction of Cement concrete Drain with
Rm 250 3016 7.54
partly Covered
5 Proctutaion Works
Construction of R-Wall in RRM Rm 100 28302 28.30
RCC R. Wall 3m Hight Rm 50 0.46 23.00
RR Stone Masonry Brest Wall Rm 200 13059 26.12
13 Road Sinages :Providing and fixing of road
sinages including all sign boards , painting of L.S 11.50
bitumen surface and Km Stones.
Total = 528.57
Add 4.5% for Work Charge contingencies = 23.79
Add 1.0% for testing & quality control = 5.29
Grand Total = 557.64
(Er.Hakim Imtiyaz)
Say 5.58 Crore
Junior Engineer
PW(R&B Sub- (Er.Khursheed Ah. Pandth)
Division Assistant Executive Engineer
Shopian PW(R&B Sub-Division
Shopian
Amount
S. No. (Er.Hakim Imtiyaz) Item of work Unit Qty. Rate (in
Junior Engineer lacs)
PW(R&B Sub- (Er.Khursheed Ah. Pandth)
Division Assistant Executive Engineer
Shopian PW(R&B Sub-Division
Shopian
S. Amount
Item of work Unit Qty. Rate
No.
1 Earthwork for cutting with mechanical
means
Cum 6720 312 20.97
1x 2.00 x 1000x 1.60 x2.10=
Total = 20.97
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing and laying granular sub-base
material having P.I not more than 6, incl.
spreading in layers not exceeding 150mm
compacted thickness and consolidation by
8-10 Ton power road roller at OMC to
achieve at least 98% of max dry density as
per IS..2720 to the required camber and
grade. Grading-I as per specifications with Cum 2625.00 700 18.38
CBR value not less than 15.incl all leads
lifts, carriage, taxes Ocotori etc.
Total = 18.38
S. Amount
Item of work Unit Qty. Rate
No.
1 Supply and stacking /laying WBM G-II
(63-45mm) size including cost and
carriage of materials upto site of work
including screening of (13.20mm) size
including dusting (Binding material
including consolidation with PRR of 8-
10 Ton capacity complete.
S. Amount
Item of work Unit Qty. Rate
No.
Providing / laying spreading and
compacting stone aggregates of specific
sizes (53-22.5mm) to water bound
macadam specifications including spreading
in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10
tonnes in stages to proper grade and camber,
1 applying and brooming requisite type of
screenign / binding materials to fill up the
interstices of coarse aggregate, watering and
compacting to the required density.
for
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing & laying of 25mm thick semidense
Bituminous concrete with bitumen of 60/70 grade
@5% by weight of total mix. on prepared surface
with specified graded stone aggregate, hot mixing
of bitumen with filler and stone agg. In hot mix
plant , transporting the mixed material by tippers to
paver and laying the mixed material with Sensor
paver finisher fitted with electronic sensing device
to the required level and grade and rolling with
road rollers as per MORTH specifications to
achieve the desired density and compaction but
excl. the cost of primer/ tack coat inculding (6mm
thick seal coatseal coat sealing the voids in a
bituminous surface laid to the specified levels,
grade and cross fall using Type A and B seal coats)
No L B H/D Qty
1.00 10.00 1.80 0.60 10.80 Cum 10.80 252.0 2722
2 Providing and laying of River Bed Material
compacting, dressing and watering and carriage up
to site complete.
NO L B H/D Qty
1.0 10.0 1.80 0.15 2.7 Cum 2.70 850.0 2295
3 Plain cement concrete 1:4:8 nominal mix in
foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days.
NO L B H/D Qty
1.00 10.00 1.80 0.10 1.80 Cum 1.80 4874.00 8773
4 Stone Masonry Work in Cement Mortar 1:4 in
Foundation and walls complete as per Drawing and
Technical Specifications.
NO L B H/D Qty
1.00 10.00 0.60 - 6.00
1.00 10.00 0.30 - 3.00
9.00 Sqm 9.00 270.80 2437
8 Providing and laying of boulders of nominal size
150mm 300mm behind wall (Hand Packed)
including carriage up to site.
NO L B H/D Qty
2.00 8.50 4.50 1.20 91.80 Cum 91.80 252.1 23138.19
2 Providing and laying of River Bed Material
compacting, dressing and watering and carriage up
to site complete. As directed by the engineer in
charge.
NO L B H/D Qty
2.00 7.50 3.50 0.10 5.25 Cum 5.25 850.0 4462.5
3 Providing and laying in position cement concrete of
specified grade including the cost of centring and
shuttering. All work up to plinth level. 1:4:8 (1
cement: 4 coarse sand: 8 graded stone aggregate
40mm nominal) crushed.
NO L B H/D Qty
2.00 7.50 3.0 0.10 4.50 Cum 4.50 4874.0 21933
4 Providing and Laying of Reinforced Cement
Concrete of grade designated M-15 mix in (1:2:4)
Open Foundation complete
(Raft). NO L B H/D Qty
RAFT 2.00 7.50 3.00 0.50 22.50
(Abutment).
2.00 7.50 2.60 1.00 39.00
2.00 7.50 2.20 1.00 33.00
2.00 7.50 1.40 2.00 42.00
136.50 Cum 136.50 4872.0 665028
6 Providing and Laying of Reinforced Cement
Concrete of grade M20 mix (1:1.5:3) in Open
Foundation complete as per Drawing
(Cap & Dirt Wall).
NO L B H/D Qty
Cap 2.00 7.50 0.75 0.45 5.06
Dirt Wall 2.00 7.50 0.35 1.00 5.25
Wheel G 4.00 7.00 0.30 3.00 25.20
Slab 1.000 7.800 7.200 0.500 28.080
63.593 Cum 63.59 7155.5 455033.59
8 Supplying, fitting and placing HYSD bar
reinforcement in sub-structure complete as per
drawing and technical specifications, Quantity @
100Kgs per cum.
NO L B MeanH/D Qty
2.000 7.500 3.500 2.800 147 Cum 147.00 8500.0 1249500
Total 3,397,330
Say Rs 33.97
NO L B H/D Qty
2.00 7.50 4.50 1.20 81.00 Cum 81.00 252.0 20412
2 Providing and laying of River Bed Material
compacting, dressing and watering and carriage up
to site complete. As directed by the engineer in
charge.
NO L B H/D Qty
2.00 7.50 3.50 0.10 5.25 Cum 5.25 850.0 4462.5
3 Providing and laying in position cement concrete of
specified grade including the cost of centring and
shuttering. All work up to plinth level. 1:4:8 (1
cement: 4 coarse sand: 8 graded stone aggregate
40mm nominal) crushed.
NO L B H/D Qty
2.00 7.50 3.0 0.10 4.50 Cum 4.50 4874.0 21933
4 Providing and Laying of Reinforced Cement
Concrete of grade designated M-15 mix in (1:2:4)
Open Foundation complete
(Raft). NO L B H/D Qty
RAFT 2.00 7.50 3.00 0.50 22.50
(Abutment).
2.00 7.50 2.60 1.00 39.00
2.00 7.50 2.20 1.00 33.00
2.00 7.50 1.40 0.45 9.45
103.95 Cum 103.95 4872.0 506444.4
6 Providing and Laying of Reinforced Cement
Concrete of grade M20 mix (1:1.5:3) in Open
Foundation complete as per Drawing
(Cap & Dirt Wall).
NO L B H/D Qty
Cap 2.00 7.50 0.75 0.45 5.06
Dirt Wall 2.00 7.50 0.35 1.00 5.25
Wheel G 4.00 7.00 0.30 3.00 25.20
Slab 1.000 7.800 8.820 0.500 34.398
69.911 Cum 69.91 7155.5 500241.79
8 Supplying, fitting and placing HYSD bar
reinforcement in sub-structure complete as per
drawing and technical specifications, Quantity @
100Kgs per cum.
Total 2,213,266
Say Rs 22.13
Amount
in lacs.
0.18
0.15
0.58
1.53
0.10
0.18
0.02
0.08
0.19
3.02
3016