Professional Documents
Culture Documents
Amount
S. No. Item of work Unit Qty. Rate
(in lacs)
1 Earth work cutting Cum 6720.00 312 20.97
2 Earth work in filling Cum #REF! #REF! #REF!
3 Granular Sub Base Course Cum 4125.00 1000 41.25
4 Providing and laying of WBM Grade-II Cum 970.60 2500 24.27
Providing and laying of WBM Grade-III Cum 970.60 2500 24.27
5 Providing / Laying of Wet Mix Cum 1940.63 2500 48.52
6 Providing / Laying of 50mm thick bituminous Cum 646.88 11000 71.16
macadam.
7 Providing/ Laying of 25 mm thick semidense Sqm 12937.50 148 19.09
8 Construction of 2M Span RCC Culvert No. 1 913642 9.14
9 Pipe Laying
10 a) 36" dia Rm 70 7000 4.90
b) 18" dia Rm 60 4500 2.70
c) 10" dia M.S. Pipe Rm 20 13000 2.60
11 Construction of Cement concrete Drain with
partly Covered Rm 1000 4038 40.38
Total = #REF!
Add 4.5% for Work Charge contingencies = #REF!
Add 1.0% for testing & quality control = #REF!
S. Amount
Item of work Unit Qty. Rate
No.
1 Earthwork for cutting with mechanical
means
Cum 6720 312 20.97
1x 2.00 x 1000x 1.60 x2.10=
Total = 20.97
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing and laying granular sub-base material
having P.I not more than 6, incl. spreading in layers
not exceeding 150mm compacted thickness and
consolidation by 8-10 Ton power road roller at
OMC to achieve at least 98% of max dry density as
per IS..2720 to the required camber and grade.
Grading-I as per specifications with CBR value not Cum 4125.00 1000 41.25
less than 15.incl all leads lifts, carriage, taxes
Ocotori etc.
Total = 41.25
S. Amount
Item of work Unit Qty. Rate
No.
1 Supply and stacking /laying WBM G-II (63-
45mm) size including cost and carriage of
materials upto site of work including
screening of (13.20mm) size including
dusting (Binding material including
consolidation with PRR of 8-10 Ton capacity
complete.
S. Amount
Item of work Unit Qty. Rate
No.
Providing / laying spreading and
compacting stone aggregates of specific
sizes (53-22.5mm) to water bound
macadam specifications including spreading
in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10
tonnes in stages to proper grade and camber,
1 applying and brooming requisite type of
screenign / binding materials to fill up the
interstices of coarse aggregate, watering and
compacting to the required density.
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing, laying, spreading and compacting
graded stone aggregate to wet-mix macadam
specifications incl pre-mixing the material with
water at OMC in mechanical mix plant carriage of
mixed material by tipper to site, laying in uniform
with paver in base course on well prepared surface
& compacting with vibratory roller to achieve the
desired density specifications thickness 150 mm
compacted thickness (MORT & H specifications.
clause 406..incl all leads lifts, carriage, taxes
Ocotori etc.
Total = 48.52
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing & laying of 50 mm thick compacted
Bituminous Macadam in accordance with IRC/
CPWD/ MOST specification adopting
aggregate adopting agg. Grading-1st with
binder content not less than 3% (60 Kgs/ Cum)
by weight of total mix incl mixing of agg. with
bitumen and laying with Paver finished to the
required level, grade & rolling with 8-10 ton
capacity road roller to achieve the required
compaction & density incl. all costs , carriages
of materials involver, tools, plant , equipment
& all allied machinery, labour, taxes/ octroi,
fees, testing charges for maintaining quality
control.
for
S. Amount
Item of work Unit Qty. Rate
No.
1 Providing & laying of 25mm thick semidense
Bituminous concrete with bitumen of 60/70 grade
@5% by weight of total mix. on prepared surface
with specified graded stone aggregate, hot mixing
of bitumen with filler and stone agg. In hot mix
plant , transporting the mixed material by tippers to
paver and laying the mixed material with Sensor
paver finisher fitted with electronic sensing device
to the required level and grade and rolling with
road rollers as per MORTH specifications to
achieve the desired density and compaction but
excl. the cost of primer/ tack coat inculding (6mm
thick seal coatseal coat sealing the voids in a
bituminous surface laid to the specified levels,
grade and cross fall using Type A and B seal coats)
NO L B H/D
1.00 1.00 3.50 0.15 Cum 0.53 755 396
3 Providing and laying in position cement
concrete of specified grade excluding the
cost of centring and shuttering. All work
up to plinth level. 1:2:4 (1 cement: 2
coarse sand: 4 graded stone aggregate
40mm nominal) crushed.
NO L B H/D
1.00 1.00 3.10 0.10 Cum 0.31 5129 1590
4 Providing and laying in position cement
concrete of specified grade including the
cost of centring and shuttering of design
Mix M-20
NO L B H/D Qty
Key 1.00 1.00 3.10 0.45 1.40
Wall 1.00 1.00 0.50 3.00 1.50
top 1.00 1.00 0.30 0.30 0.09
2.99 Cum 2.99 5383 16068
5 Reinforcement of R.C.C work including
straightening, cutting, bending, placing
in position and binding all complete with
HYSD High Yield Strength Deformed
Bars. Quantity @ 100Kgs per cum.
NO L B H/D
1.00 1.00 3.00 0.80 Cum 2.40 500 1200
7 Providing and laying of PVC pipe of
100mm diameter inclusive of all charges
complete job (for weep holes)
NO L B H/D
2.00 0.50 - - RM 1.00 135 135
TOTAL 40,342
Say = Rs 0.40
No L B H/D Qty
1.000 10.000 1.800 0.600 10.800 Cum 10.800 60.00
Providing and laying of River Bed Material
compacting, dressing and watering and carriage up to
2 site complete.
NO L B H/D Qty
1.00 10.00 1.80 0.15 2.7 Cum 2.70 755.00
Plain cement concrete 1:2:4 nominal mix in
foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in
3 foundation and compacted by vibration including
curing for 14 days.
NO L B H/D Qty
1.00 10.00 1.80 0.10 1.80 Cum 1.80 5129.00
Stone Masonry Work in Cement Mortar 1:3 in
Foundation and walls complete as per Drawing and
4 Technical Specifications.
Amount
648
2039
9232
28823
27524
2286
414
3000
73966
7397
cutive Engineer
W (R&B) Division Shopian
Detailed Estimate for 6m Span RCC Culverts
NO L B H/D Qty
2.00 8.50 4.50 1.20 91.80 Cum 91.80 127.0
2 Providing and laying of River Bed Material
compacting, dressing and watering and carriage up to
site complete. As directed by the engineer in charge.
NO L B H/D Qty
2.00 7.50 3.50 0.100 5.25 Cum 5.25 755.0
3 Providing and laying in position cement concrete of
specified grade including the cost of centring and
shuttering. All work up to plinth level. 1:2:4 (1 cement:
2 coarse sand: 4 graded stone aggregate 40mm
nominal) crushed.
NO L B H/D Qty
2.00 7.50 3.00 0.100 4.50 Cum 4.50 5129.0
4 Providing and Laying of Reinforced Cement Concrete
of grade designated M30 desing mix in Open
Foundation complete as per Drawing and Technical
Specifications (Raft).
NO L B H/D Qty
RAFT 2.00 7.50 3.00 0.50 22.50 Cum 22.50 5706.0
5 Providing and Laying of Reinforced Cement Concrete
of grade designated M30 desing mix in Open
Foundation complete as per Drawing and Technical
Specifications (Abutment).
NO L B H/D Qty
2.00 7.50 2.60 1.00 39.00
2.00 7.50 2.20 1.00 33.00
2.00 7.50 1.40 2.00 42.00
114.00 Cum 114.00 5966.0
6 Providing and Laying of Reinforced Cement Concrete
of grade designated M35 desing mix in Open
Foundation complete as per Drawing and Technical
Specifications (Cap & Dirt Wall).
NO L B H/D Qty
Cap 2.00 7.50 0.75 0.45 5.06
Dirt Wall 2.00 7.50 0.35 1.00 5.25
Wheel G 4.00 7.00 0.30 3.00 25.20
35.51 Cum 35.51 5966.0
7 Providing and Laying of Reinforced cement concrete in
super-structure as per drawing and Technical
Specification including the cost of form work and
shuttering of grade M30 design mix in super structure.
RCC Slab)
NO L B MeanH/D Qty
D.S. 1.000 7.800 7.200 0.500 28.080
28.080 Cum 28.08 6744.0
8 Supplying, fitting and placing HYSD bar reinforcement
in sub-structure complete as per drawing and technical
specifications, Quantity @ 100Kgs per cum.
L/S
50000
11 Back filling behind abutments and where ever required
by boulder of maximum 150mm including hand
packing ramming all complete.
NO L B MeanH/D Qty
2.000 7.500 3.500 2.800 147 Cum 147.00 645.0
12 Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.
NO L B H/D Qty
2.00 7.40 7.00 - 103.60
103.60 Sqm 103.60 266.0
13 Construction of precast RCC railing of M30 Grade,
aggregate size not exceeding 12 mm, true to line and
grade, tolerance of vertical RCC post not to exceed 1
in 500, centre to centre spacing between vertical post
not to exceed 2000 mm, leaving adequate space
between vertical post for expansion, complete as per
approved drawings and technical specifications.
NO L B MeanH/D Qty
2.000 7.400 - - 14.800 Rm 14.80 1853.0
Total
Say Rs
11658.6
3963.75
23080.5
128385
680124
211867.575
189371.52
810229.5
50000
94815
27557.6
27424.4
2,258,477
22.58
tive Engineer
PW (R&B) Division
hopian
Detailed Estimate of 2x3M Span RCC Culvert for
Construcation Upgradation of Road from Gatipora to Sanimarg Via
Zeerbathu Incl.2X 30 Mtr,1X15 Mtr span Steel Gidder Bridge
Amount
S. No. Item of work Unit Qty. Rate
a
4% of
Foundation 4 100 0.45 180.00 Sqm 0.12
concrete
G.Total 4.04
Rate per meter 4038
Pointing with cement mortar (1:3 ) on stone masonry work in walls as per
Technical Specifications
Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item cum 0.03 4245.00 127.35
12.6 )
b) Labour
Mate day 0.04 180.00 7.20
Mason day 0.50 325.00 162.50
Mazdoor day 0.50 150.00 75.00
c) Overhead charges @12% 44.65
input on (a+b)
d) Contractor's profit @10% 41.67
input on (a+b+c)
Rate per 10 sqm (a+b+c+d) 458.37
Rate per sqm 45.84
say 46.00
Rate Analysis for RCC Grade M30 (for Pile Works only)
Pile diameter-750 mm
Bored cast-in-situ M30 grade R.C.C. Pile excluding Reinforcement complete as
per Drawing and Technical Specifications and removal of excavated earth with
all lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M30 cum 6.62 5381.57 35626.01
Rate for concrete may be adopted
same as for bottom plug vide item
no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )
Hire and running charges of hour 6.00 5287.00 31722.00
hydraulic piling rig with power unit
and complete accessories including
shifting from one bore location to
another.
Hire and running charges of light hour 0.50 345.00 172.50
crane for lowering reinforcement
cage
Hire and running charges of hour 6.00 Rate included in piling rig
Bentonite pump
Loader I cum bucket capacity. hour 0.30 780.00 234.00
Tipper 5.5 cum capacity for disposal hour 0.30 400.00 120.00
of muck from pile bore hole
Rate Analysis for RCC Grade M30 (for Pile Works only)
Bored cast-in-situ M30 grade R.C.C. Pile excluding Reinforcement complete as
per Drawing and Technical Specifications and removal of excavated earth with
all lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M30 cum 6.62 4590.00 30385.80
Rate for concrete may be adopted same as for bottom plug vide item no. 12.11( C ) (IV)
say 5382.00
say 6225.00
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer cum 1.00 5382.00 5382.00
relevant item of concrete in item
12.8(G)by using batching plant,
excluding formwork i.e. per cum
basic cost (a+b+c) (Excluding OH &
CP)
( Refer relevant item of concrete in item No. 13.8 (G) except that form 107.64
work may be added at the rate of 2 per cent of cost against 3.5 per
cent provided in the foundation concrete.
HYSD bar reinforcement Rate as per tonne 0.05 67.03 3.35
item No 14.2(Excluding OH & CP)
b) Overhead charges @ input 0.00
on (a)
c) Contractor's profit @ input 0.00
on(a+b)
Rate per cum (a+b+c) 5492.99
say 5493.00
Rate Analysis for RCC Grade M30 (Verttical posts i.e Colums,railing Etc)
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm,
true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer cum 4.09 6225.05 25472.90
relevant item of concrete in Item
14.1(C) by using batching plant,
excluding formwork i.e. per cum basic
cost (a+b+c)
say 141.00
Bituminous Macadam
Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of
75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder,
transported to site, laid over a previously prepared surface with paver finisher to the required grade, level
and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour
Mate day 0.840 180.00
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 150.00
asphalt cutter and assistance for setting out lines, levels and layout
of construction
Skilled mazdoor for checking line & levels day 5.000 300.00
b) Machinery
Hot mix HMP 60-90 TPH @ 75 tonne per hour actual output hour 6.000 13395.00
Mechanical broom hydraulic @ 1250 sqm per hour hour 2.200 345.00
Air compressor 250 cfm hour 2.200 309.00
Paver finisher hydrostatic with sensor control @ 75 cum per hour hour 6.000 2587.00
Smooth wheeled roller 8-10 tonnes for initial break down rolling. hour 6.00x0.65* 4455.00
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.64 180.00
Mason day 1.00 325.00
Mazdoor day 15.00 150.00
b) Material
20 mm Aggregate cum 13.50 1000.00
coarse Sand cum 6.75 750.00
cement tonne 5.25 6500.00
Cost of water KL 18.00 30.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 225.00
Generator 33 KVA hour 6.00 360.00
Water tanker 6 KL capacity hour 2.00 22.40
d) Add 4% of (a+b+c) for form work
e) Overhead charges @12%on (a+b+c+d)
f) Contractor's profit @10% on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e+f)/15
say
Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing course on top of deck slab
excluding prime coat with paving grade bitumen meeting the requirements given in table
500-29, prepared by using mastic cooker and laid to required level and slope after cleaning
the surface, including providing antiskid surface with bitumen precoated fine grained hard
stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both directions, pressed into surface when
the temperature of surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming a density of
2.3 tonnes/cum.
a) Labour
Mate day 0.49 180.00
Mazdoor day 11.00 150.00
Mazdoor (Skilled) day 1.25 300.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 345.00
Air compressor 250 cfm hour 0.06 309.00
Mastic cooker 1 tonne capacity hour 6.00 60.00
Bitumen boiler 1500 litres capacity hour 6.00 256.00
Tractor for towing and positioning of mastic cooker and bitumen hour 1.00 400.00
boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse aggregates
(based on mix design done by CRRI for a specific case)
i) Bitumen VG10@ 10.2 per cent by weight of mix. 2 x 10.2/100 = tonne 0.204 45000.00
0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix = 2 x cum 0.39 800.00
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not less tonne 0.36 3250.00
than 80 per cent by weight @ 17.92 per cent by weight of mix = 2 x
17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per cent by cum 0.55 800.00
weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid resistance cum 0.036 900.00
= 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight = 0.036 x kg 1.05 45.00
1.456 x 2/100 = 0.001048MT = 1.05kg
d) Overhead charges @12%on (a+b+c)
e) Contractor's profit @10%on (a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/72.46
say
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of concrete in item cum 1.00 5706.00
12.8(G)by using batching plant, excluding formwork i.e. per cum
basic cost (a+b+c) (Excluding OH & CP)
HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & tonne 0.05 67028.00
CP)
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 180.00
Mazdoor day 8.00 150.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 10.00 2000.00
c) Overhead charges @12%on (a+b)
d) Contractor's profit @10%on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
say
Cost of dewatering upto 5 per cent of (a+b) may be added, where
required. Assessment for dewatering shall be made as per site conditions..
Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 180.00
Mazdoor day 8.00 150.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 10.00 2000.00
c) Overhead charges @12%on (a+b)
d) Contractor's profit @10%on (a+b+c)
Cost for 210 cum = a+b+c+d
Rate per cum = (a+b+c+d)/210
say
Cost of dewatering upto 7.5 per cent of (a+b) may be added, where
required. Assessment for dewatering shall be made as per site conditions..
Depth above 6m
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 180.00
Mazdoor day 10.00 150.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 10.00 2000.00
c) Overhead charges @12%on (a+b)
d) Contractor's profit @10%on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
say
Rate is Mean of Three
Supplying, fitting and fixing in position true to line and level sliding plate
bearing with PTFE surface sliding on stainless steel complete including all
accessories as per drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.
Providing and laying Filter material underneath pitching in slopes complete as per drawing and Technical specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size of nallah aggregates cum 1.20 400.00
b) Labour
Mate day 0.05 180.00
Mazdoor (Skilled) day 0.25 180.00
Mazdoor * day 1.00 150.00
c) Overhead charges @12%on (a+b)
d) Contractor's profit @10%on (a+b+c)
Rate per cum = (a+b+c+d)
say
Providing and laying Pitching on slopes laid over prepared filter media including boulder
apron laid dry in front of toe of embankment complete as per drawing and Technical
specifications
Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 1000.00
Stone spalls of minimum 25 mm size cum 0.20 850.00
b) Labour
Mate day 0.04 180.00
Mason day 0.35 325.00
Mazdoor day 0.75 150.00
c) Overhead charges @12%on (a+b)
d) Contractor's profit @10%on (a+b+c)
Rate per cum = (a+b+c+d)
say
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent wastage Kg 4.00 70.00
151.20
2400.00
1500.00
80370.00
759.00
679.80
15522.00
4050.00
4680.00
41107.50
4110.75
17374.50
5814.90
4317.30
668250.00
34808.00
130550.00
72530.00
21319.90
133235.38
124353.02
1367883.26
6672.60
6673.00
20 mm nominal size
uring for 14 days.
115.20
325.00
2250.00
13500.00
5062.50
34125.00
540.00
1350.00
2160.00
44.80
2378.90
7422.17
6927.36
76200.92
5080.06
5080.00
254
500
135
op of deck slab
ents given in table
lope after cleaning
d fine grained hard
sqm and at an
d into surface when
4 mm over mastic
88.20
1650.00
375.00
20.70
18.54
360.00
1536.00
400.00
9180.00
312.00
1170.00
440.00
32.40
47.25
1875.61
1750.57
19256.27
265.75
266.00
and formwork
5706.00
3351.40
9057.40
9057.00
57.60
1200.00
20000.00
2550.91
2380.85
26189.36
109.12
109.00
57.60
1200.00
20000.00
2550.91
2380.85
26189.36
124.71
125.00
72.00
1500.00
20000.00
2588.64
2416.06
26576.70
147.65
148.00
127.333333
127
39650.00
4725.00
6885.00
4590.00
162.00
487.50
3150.00
1350.00
2160.00
6316.00
69476.00
8337.12
7781.31
85594.43
5706.30
5706.00
39650.00
4725.00
6885.00
4590.00
162.00
487.50
3150.00
1350.00
2160.00
9474.00
72634.00
8716.08
8135.01
89485.09
5965.67
5966.00
39650.00
4725.00
6885.00
4590.00
162.00
487.50
3150.00
1350.00
2160.00
18948.00
82108.00
9852.96
9196.10
101157.06
6743.80
6744.00
10.80
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
ed concrete surface
lying paint @ of 1
1.80
81.25
45.00
1000.00
135.37
126.34
1389.76
138.98
139.00
echnical specification
480.00
9.00
45.00
150.00
82.08
76.61
842.69
843.00
including boulder
g and Technical
1000.00
170.00
7.20
113.75
112.50
168.41
157.19
1729.05
1729.00
280.00
800.00
75.00
40.00
3.60
6.50
3.00
1.80
3.25
30.00
62.16
156.64
146.19
1608.14
1608.00