Soft Soil Treatment Report by CDM
07/05/21 5
Soft Soil Treatment Report by CDM
METHOD OF CONSTRUCTION
The guideline construction method is as follows:
- The preparation shall be done before construction of
embankment: Clearing, grubbing, digging organic,
dredging mud, excavating the unsuitable soil, using the
excavated soil to embank the water-preventing fence at
both sides and pumping water if needed.
Install geotextile fabric to separate between sand layer
and soft soil layer.
Install monitoring equipment.
Backfill by fine sand (K=0,90) to bottom elevation of sand
cushion.
Fill the medium sand cushion 1,0m thick (K=0,90).
07/05/21 6
Soft Soil Treatment Report by CDM
METHOD OF CONSTRUCTION
Construct the wick drain, note that the the wick drain should be cut
20cm higher than top of sand cushion.
Install the reinforced geotextile fabric according to horizontal
direction, folding 2,0m for each side.
Fill the first layer of embankment with 30cm deep, place the
remaining reinforced geotextile fabric.
Fill the embankment (K=0,95) and soil fill for settlement
compensation on period (phase by phase).
Fill of pavement structure
Observe, if reaching settlement as designed and embankment is
stable or instructed by Supervision Engineer, carries out the next
steps.
Take down (remove) the filled parts for preload and for pavement
structure, fill the surrounding area of drainage gate (outlet).
Plant the grass by placed block of grass on talus suface.
07/05/21 7
Soft Soil Treatment Report by CDM
METHOD OF CONSTRUCTION
Plant the grass by placed block of grass on talus suface.
Construct the structure layers of pavement.
Install the wick drain:
Construction machine: prepare the equipment for placing wick drain which
has proper capacity to carry out up to the depth as required in Design
Document.
The machine must be included the devices of measuring the compressive
depth, inclination.
Construction of the cushion layer and embankment:
After finishing the installation of wick drain, Contractor can construct the
sand cushion and fill the embankment. Process of embankment fill in the
chainages of soft soil treatment must strictly comply with regulations on
filled process specified in soft soil treatment document.
When construct embankment in chainages of soft soil treatment by wick
drain, not permit for using the vibrating roller.
07/05/21 8
Soft Soil Treatment Report by CDM
RECOMMENDATION AND CONCLUSION
1. The route passes through areas of soft soil distribution - the
layers number 1 and 5. The soft soil layers are largely thick
and located on the surface or the underlied layer number 2
(sand). These soil layers number 1 & 5 has a large settlement
compression, a little shear resistance, a small consolidation
coefficient and commonly the disadvantage construction
geotechnical phenomena arisen when building road such as
sliding and settlement of embankment. Therefore it is
necessary to apply geotechnical treatment solutions when
building the road.
07/05/21 9
Soft Soil Treatment Report by CDM
RECOMMENDATION AND CONCLUSION
2. Based on the construction conditions, geotechnical conditions and
treatment solutions applied in the area, recommend to use combination
of wick drain and the period filling (fill implemented phase by phase), the
geotextile fabric and counterweight berm for geotechnical embankment
treatment. Specifically in the length, spacing of wick drain; height of
embankment and settlement time during each period are summarized in
the treatment result summary table.
• Embankment filling rate: 10 cm/day.
• Spacing of wick drains: 1.30 m, triangle lattice (diamond).
• Length of wick drain: From 13.5 to 22.0m
• Thickness of sand bedding layer: 1m – for the entire project.
• Separated Geotextile Fabric Type 25 KN/m : 1 layer installed above
surface after excavating the surface organic soil.
• Consolidation time: 270 - 330 ngày.
•07/05/21
The total time of embankment construction: 360 days. 10
Soft Soil Treatment Report by CDM
RECOMMENDATION AND CONCLUSION
3. Thus, time for construction and embankment treatment is 360
days, the remaining duration of the project is 370 days,
enough time to complete construction of superstructure works
and culverts along the route. To avoid the uneven settlement
between the culvert portion and embankment, recommend
that the construction of culverts will be only implemented after
completing embankment treatment. Therefore the
construction of the chainages which have culvert is first
priority.
07/05/21 11
Soft Soil Treatment Report by CDM
RECOMMENDATION AND CONCLUSION
4. During the construction, the drainage works must be well done
from the embankment to outside, the material shall not be
stored on the embankment with height > designed elevation
(for each phase) . The settlement need to be observed
regularly (once a day observed during construction and after a
week of construction, then gradually reduced to once in 2-7
days). However, the greater observation density is, the
reliability of data is higher and more facilitate for evaluating
the embankment consolidation and estimating the remaining
residual settlement.
07/05/21 12
Soft soil treatment Report by CDM
RECOMMENDATION AND CONCLUSION
45 The design document is based on geological survey data.
During the construction process, need to consider the actual
conditions to adjust the design in accordance with reality.
Additionally, it needs to install monitoring equipment to assess
the efficiency of the geotechnical treatment, the embankment
consolidation analysis, detection and solve timely of incidents
occurring in the embankment construction. At the same time,
basing on monitoring data to adjust the construction schedule.
07/05/21 13
Profile for Soft Soil Treatment
07/05/21 14
Profile for Soft Soil Treatment
07/05/21 15
9th Feb, 2012 Meting at Site office
07/05/21 16
Comments on Results of Soft Soil Treatment Trial Section
Site meeting was held on 9th Feb 2012 at Contract C13a work site
and chaired by Mr Dung Chief Project Director , Department of
Transport, Da Nang. Mr Vy Project Director PMU and Mr T K Zan
RE Supervision Consultant LBG and Contractor PVC 1 jv CRD
representative Mr Dang General Director , Mr Hung CEO and Mr
Bang CRD Director were attended the meeting. The recorded
meeting notes is attached.
In the meeting one of the agenda was discussed by Mr Dung DOT
to construct the trial surcharge section where the wick drain
installation was completed. He requested to make a reading at the
200 m trial surcharge section from the beginning to the end of the
filling surcharge to find out the rate of the settlement and the
settlement status compare with the CDM design settlement
concepts.
07/05/21 17
Comments on Results of Soft Soil Treatment Trial Section
07/05/21 18
Comments on results of Soft Soil Treatment Trial Section
07/05/21 19
Comments on results of Soft Soil Treatment Trial Section
07/05/21 21
Comments on results of Soft Soil Treatment Trial Section
07/05/21 22
Comments on results of Soft Soil Treatment Trial Section
07/05/21 23
Comments on results of Soft Soil Treatment Trial Section
07/05/21 24
Comments on results of Soft Soil Treatment Trial Section
07/05/21 25
Comments on results of Soft Soil Treatment Trial Section
07/05/21 26
Comments on results of Soft Soil Treatment Trial Section
07/05/21 27
Comments on results of Soft Soil Treatment Trial Section
07/05/21 28
Comments on results of Soft Soil Treatment Trial Section
07/05/21 32
Photo Settelment instrument
07/05/21 33
Photo Wick Drain installation
07/05/21 34
Photo Wick Drain installation
07/05/21 35