Professional Documents
Culture Documents
1 INTRODUCTION
DOI: 10.1201/9781003348030-12
90
Figure 1. Location of Al-Salam pump station (google.com/map).
The masterplan included a preliminary design of the pumping station. Following tendering
and award of the contract for construction, an alternative design of the underground struc
tures of the pumping station was proposed by the contractor. The objective of this study is to
present the alternative design, in particular the shaft design, from the conceptual studies, con
struction methodology, numerical modelling and detailed design, until the value engineering.
2 PROJECT DESCRIPTION
91
– Top soil and backfill layer reaching down to the elevation +0.70 m MSL.
– A thin medium dense silty sand layer, around 1.30m thick.
– A substantial layer of loose/very loose clayey silty sands or sandy clays extending down to
the bottom level of the return pool structure, i.e., -7.65 m MSL.
– A thick deep layer of stiff to hard sandy fat/lean clay of a clear cohesive nature whose
bottom elevation reaches -15.63 m MSL.
Based on the in-situ and laboratory examinations, the geotechnical parameters of the soil
layers are reported as listed in Table 1 along with the acronym adopted for each layer.
k: permeability, Cu: undrained shear strength, φf: Friction angle, γd: Dry density, γw: Unit weight, E: Young modulus
92
In the contractor’s alternative design, hydraulic studies were carried out to confirm and opti
mize the layout and the design of the pumping station, the foreseen equipment, and the oper
ation procedures from a hydraulic point of view. The hydraulic conditions, focusing on the
streamlines, velocity vectors, water levels and shear stresses are analyzed by CFD modelling
using the Flow-3D software. CFD models have been largely used to predict the flow patterns
and optimize the hydrodynamic behavior in sumps and forebays of pumping stations. Results
of these studies, presented in Amini et al. 2022, were used to finalize the geometry of the shaft
and the basin and to proceed with the geotechnical and structural design and construction.
1 Surface preparation for jet grouting including superficial filling and/or dewatering as required.
2 Jet grouting around the return pool excavation zone
3 Implementing the shaft slurry walls and the head capping beam
4 Excavation in return pool down to the elevation of the pool bottom slab.
5 Starting deep pumping in the shaft
6 Excavation in the shaft down to the elevation of the pool bottom slab
7 Demolishing the separating slurry walls between pool and the shaft and installing struts
8 Concrete works in the pool (walls and slab)
9 Completing excavation in the shaft to the bottom level of shaft slab.
10 Concreting the shaft bottom slab
11 Excavation of the connection tunnel
12 Concerting the shaft internal liner and pumping stoppage.
13 Concrete work in the basin (walls and slab) – End of the construction
3 CONSTRUCTION METHODOLOGY
93
Figure 3. Bottom slab concreting (left) and the general overview (right). (photo courtesy Abuljadayel
Co. for Cont. & Maint.).
94
The analyses are first carried out with a diaphragm wall depth of 40m, to be adjusted based
on obtained results. The shaft is covered by an internal reinforced concrete liner of 0.50m
nominal thickness with concrete class C30/37.
The connection hydraulic tunnel is of a 3.5m diameter. Its excavation is carried out in one
step in its entire length, and the soil gradual deconfinement due to the front advancement is
simulated indirectly through the confinement-convergence method by admitting a deconfine
ment ratio of 30% prior to the installation of the tunnel support/liner.
The elastic-perfectly plastic Mohr-Coulomb constitutive law is used for ground layers. Con
crete is modelled using a linear elastic law. The Young’s modulus is reduced for slurry walls.
The initial-boundary condition corresponds to a K0 condition with hydrostatic under
ground water pressure calculated for the high tide groundwater elevation (+1.4 m MSL).
A coupled hydro-mechanical is used at each calculation phase, pore pression is first evalu
ated automatically by the software hydraulic module according to the model geometry, soil
permeability, and the pressure boundary condition. The calculated pressure is then used in the
mechanical module to obtain soil effective stress based on the soil parameters.
Soil-structure interaction is handled automatically by the software through simulating nat
ural concrete-soil contact by using zero-thickness interface elements whose friction angle is
taken 2/3 of that of the adjacent soil and whose cohesion is null.
The joint between the panels is also dealt using the zero-thickness cohesionless interface
elements whose friction angle is taken 20°, as suggested by suggestions in ASSHTO 2007.
Figure 6. Hydraulic head as calculated at the end of excavation (left) & Variation of safety factor
against piping with respect to depth of excavation (right).
95
4.2 Model results & design
Numerical results provided information both for the geomechanical behavior of the shaft in
interaction with the surrounding ground, and the structural safety of the shaft components
including the slurry wall and the bottom slab. Figure 5 shows the vertical displacements at the
end of excavation. The obtained displacements are withing the acceptable values with limited
plastic zones around the shaft and close to the surface. The presented modelling and calcula
tions approved the stability and the safety of the proposed shaft structure design. The circular
shape of the shaft allows an optimized design of the diaphragm wall panels. No abnormal
stress concentration is seen in load carry body. Displacements are also limited guarantying the
serviceability of the structure.
Explicit seepage analyses were carried out to assess the safety of excavation and evaluate
the risk of piping. The construction methodology foresees deep drainage holes to keep the
water level inside the shaft always below the excavation level. Accordingly, the hydraulic gra
dient increases with excavation depth, approaching the critical hydraulic gradient and redu
cing the safety factor. Results are presented in Figure 6. These results suggest that the
drawdown can be delayed at least until when the excavation reaches the elevation of -8m
MSL and only for the last 10m the drainage wells are needed.
5 VALUE ENGINNERING
Shaft VE1 - Circular shaft without struts Circular shape for the shaft
Circular shaft and frames instead of rect Construction using Diaphragm walls
angular shaft Reinforced concrete internal lining
Water control using deep drainage holes
Shaft VE1 - Circular shaft without struts and Increased rigidity and stability thanks to the
Circular frames instead of rectangular shaft hoop effect in the circular form without need
shaft for additional stabilizing measures such as
struts and frames.
Larger storage volume
Systematic jet grouting not required for DW
(Continued )
96
Table 4. (Continued )
. VE Concept Description Advantages & Justification
VE2 - Reinforced concrete lining 500 mm Increased durability and structure life
Reinforced thickness instead of shotcreting Decreasing the operation cots due to miti
concrete gated leakage risks
lining
The VECP considers the Revised Design (RD) proposed by the contractor as an alter
native to the rectangular base Tender Design (TD). The VE process seeks to improve
the value of the project by evaluating the functions of various project components and
determining whether alternative design can be used to achieve the same functions at an
overall higher benefit in terms of cost, risk and sustainability. It looks to the project
effectiveness with cost and risk considerations and examines the performance of RD
alternative compared to TD alternative.
5.2 VE concepts
To identify the value engineering concepts, both the construction and operation aspects are
considred. In one hand, saving, safety and optimisation of construction methods and on the
other hand the sustainability and enhanced operation is sought. Table below summarizes the
value engineering concepts applicable to Revised Design.
97
6 CONCLUSIONS
ACKNOWLEDGEMENTS
The authors acknowledge the permission granted by Abuljadayel Co. for Contacting & Main
tenance, in charge of construction, to publish the main results of the present study on Al-
Salam pumping station, and specially thank Engineer Rateb Jawish and Eamonn Leavey for
their special help and support. The authors also acknowledge the contribution of Geotest Ltd
and Stunex Ltd on the early stages of the project.
REFERENCES
AASHTO. LRFD Bridge Design Specifications (SI). Tech. Rep. LFRDSI-4-M, American Association of
State Highway and Transportation Officials, 2007.
Abu Abdullah, M.M., Youssef, A.M., Nashar, F. and Abu Al Fadail E. (2019). Statistical analysis of
rainfall patterns in Jeddah City, KSA: future impacts, Chapter 9 of: Rainfall - Extremes, Distribution
and Properties, Editors: Abbot J., Hammond, A., Publisher: IntechOpen.
Amini A., Wickenhäuser M., Koliji A. (2022), Three-Dimensional Numerical Modelling of Al-Salam
Storm Water Pumping Station in Saudi Arabia, Proceedings of the 39th IAHR World Congress, 19-
24 June 2022 Granada, Spain
Anni, A.H., Cohen, S. and Praskievicz, S (2020). Sensitivity of urban flood simulations to stormwater
infrastructure and soil infiltration. Journal of Hydrology, 588 (9).
Barbosa, A.E., Fernandes, J.N. and David L.M. (2012). Key issues for sustainable urban stormwater
management, Water Research, 46 (20).
Farooq, Q.O. and Alluqmani, A.E. (2021). Application of soil based low impact development system for
Flash Flood management of Jeddah, Saudi Arabia, Journal of King Saud University - Engineering
Sciences, (12).
Fernández, D.S. and Lutz, M.A. (2010). Urban flood hazard zoning in Tucumán Province, Argentina,
using GIS and multicriteria decision analysis, Engineering Geology, 111, 90–98.
Goonetilleke, A., Thomas, E., Ginnc, S, and Gilbert, D (2005). Understanding the role of land use in
urban stormwater quality management, Journal of Environmental Management, 74, 31–42.
Subyani, A.M. and Hajjar A.F. (2016) Rainfall analysis in the contest of climate change for Jeddah area,
Western Saudi Arabia, Arabian Journal of Geosciences, 9 (122).
Weber, A. (2019). What is Urban Flooding? Natural Resources Defense Council (NRDC), https://www.
nrdc.org/experts/anna-weber/what-urban-flooding
98