Professional Documents
Culture Documents
The criteria for the lining to be adopted for inigation projects are issued for adherence in the works to be
executed hereafter.
1.1 Provision of design mix concrete M-10, MSA-20 mm for cast in situ cement concrete lining shall
be Cone for canals discharge up to 0.3 cumecs & less or depth of water up to 0.50 m whichever is
less.
1.2 Provision of design mix concrete M-I5, MSA-20 mm for cast in situ cement concrete lining shall
be done for canals having discharge more than 0.3 cumecs and depth of water more than 0.50 m
whichever is less. For canals having discharge greater than 50 cumecs and where thickness of
lining is 100 mm or more, the maximum size of aggregate shall be about 25%o of thickness of
lining and accordingly suitable mix design and rate analysis shall be done.
1.3 Concreting nearthejunction ofthe side concrete and bed concreting shall be done such that both
shall rest firmly against each other to resist any back-kick from external hydrostatic forces the
sketches below indicate the procedure for formation ofjunction of the sides with bed depending
upon the sequence oflaying concrete i.e. sides first and vice-versa.
1.4 In case the reach is passing through the hard rock, the excavation shall be done to achieve
desired slopes and surfaces. No over excavation shall be payable.
The sub-grade in rock should be excavated to the required cross section. Over excavation
in rock is generally unavoidable and should be minimized by using wedging and barring
methods, for final dressing. Over-excavation in hard strata having side slopes more than 1: i
beyond the profile line may be backfilled with gravel and aggregate, large aggregate forming
the bulk of backfill with smaller aggregate filling the voids and a layer of pea gravel as binding
material. The bed may then be compacted with road rollers and sides with rammers to form a
firm backing for the lining. For over excavation in hard strata having side slope less than l: l,
C:/Bodhi/Canal/ Ravi
beyond the profile, the backfilling may be suitably done with chip masonry or lean concrete.
However, for bed the backfilling may be done with properly compacted murum. Over
excavation up to 5 cm may be backfilled. If over excavation is up to 10 cm lean concrete may
be used. Beyond l0 cm backfilling with chip masonry is preferable. For slip-form paving, over
excavation up to 10 to 15 cm may be required. Such over excavation may be backfilled with
selected material and compacted at optimum moisture. The material selected should be
machine trimmable and be gravel/stone-free earth.
Decision of lining in hard rock reaches shall be taken by the Superintending Engineer in
accordance with the design discharge. The lining shall be placed directly above the corrected
surface with weep holes at appropriate drainage points identified at field.
Note:- If high liquid limit (higher than 55%o) is accompanied with low shrinkage limit (less than
l0%) swelling pressure test shall be conducted irrespective of plastic limit and plasticity
index.
5.2.2 Physicalproperties:-
5.2.2.1 Gradation
(a) Clay (less than2 micron) 15 to 20%o
(b) Silt (0.06-0.002mm) 30 to 40Yo
(c) Sand (2,0-0.06mm) 30 to 40Yo
(d) Gravel (Greater than2mm) - 0 to 10%
C:/Bodhi/Canal/ Ravi
5,2.2.2 Index properties: -
Liquid limit-less than 55Yo but greater than 30oh Plasticity lndex-less than 30o/o but greater than
15%.
*
r., 30
6
z
>. av
{F
in
5ro
s1
4
30 40 50
Lf OUIO r-IM lT wU .l
5.5 Investigation along the canal alignment and assessment of CNS material:
5.5.i Objective:-Geotechnical investigations shall be canied out to-
(a) Delineate strata and prepare soil profile along the canal alignment and obtain details of ground
water table. (GWT)
(b) Delineate the boundaries of expansive and non-expansive type of soils.
(c) lndentify borrows areas for CNS and other materials to be used for canal lining.
(d) Determine engineering characteristic of each strata in foundation and borrow area.
(e) Determine engineering properties of the foundation material at the in-situ-condition and borrow
material at placement condition.
5.5.2 Method of exploration-
Exploration shall be made by test pits and hand auger holes along canal alignment and borrow
areas. However, where the canal is in deep cut, bores may be needed if the depth of cut is beyond
the auger hole range.
remolded at OMC and compacted to optimum proctor density. The swelling pressure test will be
conducted as per the constant volume method described inIS 2720-1977 (Part XLI). Some quick
tests are also available. However, in absence of properly established co-relation, the quick test
may lead to incorrect result. Hence quick tests for determination of swelling pressure are not
recommended.
5.10 Housing :
Excavation below CBL & side slopes shall be provided for housing of lining including CNS
wherever required. Quantity arrived shall be further increased by 10 % for estimation for filling
of the undulations etc before lavins of the canal concrete linine.
7.2 In respect of ridge canals with discharge less than 1 cumec, no drainage arangements need be
provided.
7.3 When provision of drainage behind lining is necessary advantage shall be taken of nearby natural
drainages for leading out the canal drainage water.
7.4 For Drainage behind lining T.C. No. 20 and specification volume-Ill Para no. 25.3 and 25.4 must
be followed.
7.5 In canal sites (slant length) porous blocks shall not be used for drainage as they were not found
effective.
More than 50 cumecs uoto 200 cumecs More than 2.5 m. upto 100
4.5 m.
More than 200 cumecs upto 300 More than 4.5 m. t20
cumecs upto 6.5m.
More than 300 cumecs upto 700 More than 6.5 m. 150
cumecs upto 9.0 m.
9.0 CURING:-
9.1.1 Bed Lining
After final settling time elapses small bunds longitudinal and cross-wise consisting of earth
materials or lean mortar (l: 15) shall be laid
with 8 cm height for curing. Water pondage should
be maintained for 28 days continuously.
.'(
" 4 \_-.--
C:/Bodhi/Canal/ Ravi Page 7 of 1.0
9.1.2 Side Lining -
The panel in which concreting is done, shall be covered with empty cement gunny bags. Water
shall be continuously sprinkled on the gunny bags keeping them wet for 28 days. Sprinkling shall
be done during night time also. The curing of side slopes may be done by constructing masonry
drains with weep holes or perforated pipes on the coping at the top of lining or by sprinklers.
Free board of canal is the vertical distance from top of canal bank (TBL) to the water surface
(FSL) at the design condition. This distance should be sufficient to prevent waves or fluctuations
in water surface from overflowing the sides and subsequently using damagO due to breach of
canal banks.
11.1 Free board in canals will depend upon canal size, its location, velocity and steepness of slopes,
storm water inflow, water table fluctuations, wind action, curvature in alignment, soil
characteristics, percolation gradient, operational conditions for regulating structures; operating
road requirements and availability of excavated materials etc.
ll.2 ln case of lined canals the lining is not done up to the top of canal bank from economic
consideration. However, certain clearance above FSL is provided to prevent frequent saturation
and subsequent damages to the unlined portion of the canal bank. The vertical difference between
the FSL and the top of lining is termed as 'Lining free board'.
11.3 The following free boards for unlined and lined canals shall be provided:-
Steel ladders shall not be provided. Plain cement concrete steps of grade M10 with 20 mm graded
metal of 30 cm Tread & Rise as per canal side slope, having width 2.0 m shall be provided at an
interval of 300 m c/c on either side of canal in staggered manner. Step shall be provided right up to
the service road/service path,
This T.C. supersedes T.C. 17 issued vide no. I05/BODHUR&C|TC\\ l/88 Bhopal Dated 12.12,88,
T.C' l9 issued vide no. ll5/BODHIIP.&C|TC|lll88 Bhopal Dated 16.06.89 and T.C,60 issued
vide no. l035lBvAl298/BoDHyR&c/TC Bhopal, Dated 31.t2.2016 in fuil.
References-
Along with this T.C., the following IS codes, T.Cs. and Technical Specifications may also,be
referred:-
I ' Is code 3873:1994 laying of cement concrete/stone slab lining on canals-code of practice
(Reaffirmed-2004).
2. Is code 94511994 guidelines for lining of canal in expansive soils-code of practice (Reaffirmed-
2004).
3. Is code 10430:2000 criteria for design of lined canals and guidance for selection of type of
lining.(Reaffi rmed-2009)
4. Is code 456:2000 plain and reinforced concrete-code of practice (Reaffirmed-2o16),
s. T.c. No.3 & T.C. NO.20
6. Specification volume no. I & ilI.
e
c^
Endt. No 34e Ev AnsBnoDHYR&c/rc BHoPAL, batgo: 2 s toltzotg
Copy forwarded to:-
For necessary action, The copies of the amendment must be circulated at your level to all freld
:
i,
| ' officers underjurisdiction.
13. Superintending Engineer (Monitoring), O/o Engineer in Chief, M.P. Water Resources
Depaftment, Bhopal.
14. Web Manager, O/o Engineer-in-Chief, Water Resources Department, Bhopal for uploading in
departmental website.
Encl: As above