You are on page 1of 8

SHAURYA CEMENT INDUSTRIES PRIVATE LIMITED

DAILY REPORT: 05.01.2021

Man Power Statement


Description 31.12.2020 01.01.2021 02.01.2021 03.01.2021 04.01.2021 05.01.2021
Civil-plant building 260 260 260 260 263
Mechanical 222 Holiday 210 210 210 210
Electrical 42 40 40 40 40
Ayoki staff 23 23 23 23 23
TOTAL 547 547 533 533 533 536
Shree Krishna 355 276 346 346 344 348
Engineering
Rajpooth 80 46 76 76 76 76
Grand total 982 869 955 955 953 960
Refractory Man power : 00
Shree Krishna man power details:
Insulation man power : 28
Mechanical: 200
On 05.01.2021 Refractory Man power Strike Electrical : 70
Civil : 72
Staff : 06

Daily Progress Report as on 05.01.2021 Daily progress report Mechanical :

1. Preheater :- Columns & beam reinforcement Fabrication :


& shuttering in progress and casting in progress at
4 mtr level * Clinker cooler venting lines fabrication under progress
2. TG Building :- DE shuttering work in progress * Raw mill monorail and brackets fabrication under progress
3. CCR Building :- Grade slab exuviation leveling * ESP roof plate items fabrication under progress
and dressing work in progress between clinker * Gratings fabrication under progress
cooler house
4. Additive coal storage: - Backfilling work under Erection :
progress.
5. ADM Plastering work in progress * Raw mill roller hydraulic unit testing at grinding pressure
6. Boundary wall: - Construction in progress. * Raw mill drilling and reaming work for gearbox to bed plate
7. Packing Plant :- Blocks massonery and dowel pin connection under progress
plastering work under progress * Outside building water line work under progress at pump house
8. Water Reservoir Tank: - PCC and RCC work in * Coal mill building punch point finishing job under progress
progress & Reinforcement work in progress. * Coal mill building handrails work under progress
9. Clinker tank. Prestressing and grouting work in * Clinker transport chutes erection under progress
progress. * NDC fan at TT-5 drive alignment under progress
10. MRSS. Precast construction in progress for * TT 2 staircase welding work under progress
cable trench and gate construction in progress * 231.BC 440 Magnetic separator extended chute erection under
11.Cooling tower. Backfilling, Reinforcement and progress
shuttering work in progress * AQC boiler outlet hopper fit up under progress
12. Switch yards. Earth pits construction in * ESP weather enclosure erection under progress
progress & leveling work in progress * Belt conveyor 133.BC 100 maintenance platform erection under
13. NEA. Switch yards. Manual exuviation in progress
progress for earthling flats. * Coal mill hot air duct welding under progress
* Clinker cooler building handrails painting and finishing work
under progress
* Belt conveyor 131.BC 520 and 133.BC 560 walkway handrails
painting under progress
* Raw mill feed building handrails finishing and painting under
progress
* Coal mill building staircase and platforms handrails finishing
and painting under progress
* Cooler duct damper maintenance platform erection under
progress
* AQC boiler Drum supporting structure ground assembly under
progress
* Coal mill hot air duct welding under progress
* Coal mill venting lines erection under progress
* Belt conveyor 231.BC 440 walkway handrails work under
progress
* Outside building airline erection under progress
*Clinker silo chutes liner fixing and erection under progress
*133.BC560 hand rail painting under progress
*Coal/additive intake and crusher punch points works under
progress
*133.BC420 belt conveyor alignment under progress
* 481.BC600 Belt laying & Jointing under progress
*131.BC100 shed sheeting work under progress
Rain status: 0.0mm

SCIPL / Stores Report / 05 Jan'2020

>>>Inward>>>

1. Sagarmattha suppliers
a. Aggregate - Nil.
b. Sand - Nil.
c. Bolder - 01 load.

2. Gravel - 04 loads From Balua gitti washing.

3. OPC cement 2100 Bag From Riddhi Siddhi.

4. Diesel - 1980 Ltr From jay Deepak trade center.

5. Lime stone - 5932.24 Mt / 208 Loads.

a. Dumping yard - 2784.68 Mt / 94 Loads.


b. Scl galter mines - 3147.56 Mt / 114 Loads.

6. Lpg Refill - 03 Nos From Jitu enterprises.

<<Outward <<

1. Limestone - Nil
LIME STONE REPORT
Opening Stock Inward Outward Closing Stock
465850.63 MT 5932.24 MT 0 MT 471782.87 MT
COAL REPORT
Opening Stock Inward Closing Stock
13363.33 MT 0 MT 13363.33 MT
Site photographs:

Coal mill hand railing welding work

Raw mill drilling and reaming for dowel pin fixing between gearbox and bed plate
Raw mill housing painting under progress

TT-4 staircase handrails finishing work under progress


231.BC 400 HGTU staircase erection work under progress

Clinker transport chutes erection under progress


Blending silo bucket elevator structure painting and finishing under progress

Photographs: Site:

Packing plant shuttering work


Raw water tank shuttering work

Concrete work around earth pits at CCR


Silo aeration blowers room shuttering work