On 04-Feb-08 a contract signed between Siemens and Wood beaker (as sub-contractor to provide &
install Joinery works for integrated Kitchen) shows that supply & installation 48 integrated kitchen
units will be within a period by 28-feb-08 & the remaining quantities (140 units) by 15-apr-08.
On 12-Feb-08 Siemens issued a Purchase Order for integrated Kitchen equipment mentioned that
some equipments required by 13-Mar-08
Page 20 of 48
Determination for the Claim of Extension of Time
The contractor submitted a list of evidence for Ground Floor modification, showing the event
effective date was 12 February 08 (without any mentioned reference or reason).
The Contractor used partial as-built schedule updated [01 December 2007] as base to calculate the
delay which originally projected a completion date of 09 July 2008.
Adding new activity for Approval new Arch. Interior design Ground floor with ID (GGNG201)
which started on 12th Feb. 2008 related to successor Activities (CGRKC002 & CGRMC002 &
CGRTC002) (Brick Works Installation) with relation FS and lag = 0. Lead the project to finish on
18th of Aug. 2008
On 10-Dec-07 PMO confirmed the official comments carried out by SBS for ICH site visit in 7 & 8
Nov. 07 for Ground Floor (Conceptual Design Change)
As there is no updated programme submitted by the contractor during this period, the contractor
generated a partial as-built schedule up to 1st Dec. 07 built on the last revised schedule submitted by
the contractor as revised project schedule according to MOU with data date 23rd Aug. 07, which
projected finish date as of 31st Mar. 08
The contractor submitted partial as-built schedule (ASUP) up to date 01st Dec. 07 which projected
finish date as of 09th Jul. 08.
PMO initiated an analysis to establish the effect of ground floor (conceptual design change) to the
progress of works. This is achieved through adding new activities regarding new ground floor
Works in the partial as-built schedule up to 01 December 2007. These activities were prepared by
PMO with the required durations and relationships (extracted from the contractor’s base line
schedule programme (1209)
The new activities added regarding revised ground floor are inserted into the partial as-built
schedule ASUP update of 01 December 2007.
The following Table 2.02.2(A) identifies the new activities with durations.
Page 21 of 48
Determination for the Claim of Extension of Time
Table 2.02.2(A) List of New Activities Added regarding revised Ground Floor drawings
Three activities were added to the program regarding revised ground floor drawings. Table
2.02.2(B) shows the existing activities that were affected by the revised foundations drawings to the
works.
Table 2.02.2(B) List of Existing Activities Affected by revised ground floor drawings
The new activities added regarding Ground Floor (Conceptual Design Change) were inserted in
programme (CLA2) update as of 01 December 2007 and related to existing activities as follows in
Table 2.02.2(C). These relationships were obtained from Contractor’s (MOU) Base Line Schedule
programme (1209)
Table 2.02.2(C) List of New Activities Added Regarding ground floor modification and their
Relationships
ORIG
ACTIVITY DESCRIPTION
ACTIVITY ID DUR
GGNG201 0 Approval new Arch. interior design Ground floor
..ESSGF43A * 0 SU FS 22 Masonry work shop dwgs (Floor Ground) Modification
Page 22 of 48
Determination for the Claim of Extension of Time
The following Table 2.02.2(D) indicates the status of the activities regarding ground floor
modification and those affected by it as of program CAL2 impacted (as built schedule) of 01
December 2007.
Table 2.02.2(D) List for Status of New Activities Added regarding revised ground floor and
Related Existing Activities
According to program ASUP, the original project completion date was 09 July 2008. The effect of
the primavera simulation analysis projected a new project completion date i.e. 22 July 2008.
Therefore, the analysis shows effect on the project completion date. The ground floor modifications
introduced by the Client had 13 Calendar days delay effect on the activities related to it.
2.03 Conclusion
As such, the contractor can be entitled to 13 Calendar days extension of time on account of
conceptual design change of ground floor
Page 23 of 48
Determination for the Claim of Extension of Time
2.04 References
Page 24 of 48
Determination for the Claim of Extension of Time
On 17-Sep-2007 GPP submitted the required concept design for the ground and basement floors as
agreed during the progress meeting # 26, advising the contractor to issue the relevant shop drawings
for approvals.
On 19-Sep-07 Siemens required some clarification regarding ground floor & basement concept
design.
On 22-Sep-07 Siemens required additional information regarding ground floor & basement concept
design.
On 26-Sep-07 reply all contractor requirements regarding his previous two letters.
On 10-Dec-2007 PMO advised the contractors regarding ICH site visit agenda that will include
review and approve the space plan for the lobby/ground floor.
On 01-Jan-08 GPP instructed Siemens to hire qualified Interior Designer to complete the ID design
of the ground floor.
On 30-Jan-08 Siemens submitted architectural shop drawing schedule had shown a proposed date
for submitting ground floor details.
On 11-Mar-08 PMO sent a letter concerning the contractor’s shop drawing status and concerning
that affect the proposed completion date for the ground floor works.
Page 25 of 48