Monthly MIS report
11thJanuary 2022
1.0 INTRODUCTION
Salient information related to the development
• UPVC Door & Windows: M/s. Sohom Fenster ( Tower A ) • Shaft ACP Trap Doors : M/s. Prisicca and Gabriella
• UPVC Door & Windows: M/s. Eco Care Prime (Tower A & C)
• Wooden Floor – M/s. Galaxy Designs
• Door Hardware's : M/s. Spray Systems
• STP : M/s. Crystal Drops
• Fire & Non Fire Doors : M/s. Crystal Engineering
• BESCOM & CEIG : M/s. Tesla Electric & Engineering
Incor Carmel Heights Tower A Finishes
Cumulative
Achieved Planned
Achieved Achieved
Sl. Start Date Completion up to for
Activity Contractor up to as on date Remarks
No R0 Date R2 December January
November 11-01-2023
2022 2023
2022
Bore packing,
waterproofing & 17 floors waterproofing completed.
1 screed
JMC 20-07-2022 30-01-2023 16 1 1 0 18th floor works is on hold due to interior
designs
(1st to 18th floor)
Plumbing 1st Fix Prem Upto 17th floor completed. 18th floor works are
2 (1st floor to 18th floor) Plumbing
17-06-2022 04-02-2023 16 1 1 0
on hold due to interior designs
12 Primer coat JMC 09-11-2022 05-03-2023 0 0 8 0 3 units completed. Further works in progress
( 1st to 18th floor ) Due to 18th floor works date is going upto March 2023.
13 Electrical Wiring SB 09-11-2022 03-03-2023 0 10 8 5 15 floors completed. 16th floor works in progress.
( 1st to 18th Floor ) Electrotech Due to 18th floor works date is going upto March 2023.
Only one unit completed. A 203.
Internal Painting 1st
14 JMC 12-11-2022 07-03-2023 0 0 9 0 Due to 18th floor works date is going upto March 2023.
coat ( 1st to 18th floor )
Incor Carmel Heights Tower A Finishes
Cumulative
Achieved Planned Achieved
Achieved
Start Date Completion up to for as on date
Sl. No Activity Contractor up to Remarks
R1 Date R2 December January 11-01-
November
2022 2023 2023
2022
Works are delaying due to painting work front
Electrical Switch &
constrain.
15 plate fixing(1st to 18th SB Electric 4-11-2022 07-03-2023 - 2 9 0
Floor) Due to 18th floor works date is going upto
March 2023.
Toilet False Ceiling
16 Board fix (1st to 18th JMC 17-11-2022 11-03-2023 - 0 8 0 Due to 18th floor works date is going upto
floor) March 2023.
Acid wash & grout (1st Due to 18th floor works date is going upto
17 JMC 18-11-2022 13-03-2023 - 0 8 0
floor to 18th floor) March 2023.
CP & Sanitary Fix (1st Prem Due to 18th floor works date is going upto
18 20-11-2022 15-03-2023 - 0 8 0
to 18th floor) Plumbing March 2023.
De snags( 1st to 18th Due to 18th floor works date is going upto
19 All 20-11-2022 16-03-2023 - 0 9 0
floor ) March 2023.
Internal paint Final Due to 18th floor works date is going upto
20 23-11-2022 18-03-2023 - 0 9 0
Coat( 1st to 18th floor ) JMC March 2023.
Wooden Flooring ( 1st Galaxy Due to 18th floor works date is going upto
21 26-11-2022 20-03-2023 - 0 9 0
to 18th Floor ) Designs March 2023.
Hand Over( 1st to 18th Due to 18th floor works date is going upto
22 floor ) All 27-11-2022 23-03-2023 - 0 9 0 March 2023.
Incor Carmel Heights Tower C Finishes
Cumulative Achieved Achieved
Planned for
Start Date Completion Achieved up to as on date
Sl. No Activity Contractor January Remarks
R0 Date R2 up to December 11-01-
2023
November 2022 2023
2022
Bore packing,
waterproofing & 14 floors completed. 1st & 16th above floor
1 screed JMC 04-07-2022 21-01-2023 11 3 4 0 works in progress.
(1st to 18th floor)
Plumbing 1st Fix Prem 01-08-2022 29-01-2023 13 floors completed. 14th & above floor works
2 (1st floor to 18th floor) Plumbing
10 2 6 1
in progress.
Internal Main Flooring 10 floors completed. 11th & 12th floor works in
5 & Skirting 1st to 18th JMC 05-08-2022 19-02-2023 6 2 5 2 progress
floor
MS Hand Railing 14 floors completed. North & West elevation
6 Balcony JMC 31-10-2022 25-01-2023 5 7 6 1 completed. East & south side works are in
(1st to 18th Floor) progress.
Incor Carmel Heights Tower C Finishes
Cumulative
Achieved Planned
Achieved Achieved
Start Date Completion up to for
Sl. No Activity Contractor up to as on date Remarks
R1 Date R2 December January
November 11-01-2023
2022 2023
2022
IPS Flooring 14 floors completed. 15th floor works in
7
(1st to 18th Floor)
JMC 16-08-2022 25-01-2023 11 2 5 1 progress.
Boxing & False Ceiling
14 floors completed. 15th and above floor
8 Channel fix JMC 15-11-2022 30-01-2023 3 8 7 3 works are in progress.
(1st to 18th floor)
Electrical Wiring SB
13 ( 1st to 18th Floor ) Electrotech 24-11-2022 15-03-2023 0 0 6 0 807 & 1607 completed.
De snags
19 All 15-12-2022 29-03-2023 - - 5 0
( 1st to 18th floor )
Revised GFC’s are required to commence further. Still, Basement slab works are completed with
1 Tower 2
Manohar consultant details.
2 Clubhouse Revised GFC’s are required to commence further.
3 Tower 1 18th Floor Details
Painting works
Tower A – West Elevation Tower A - Lift Works Tower C – West Elevation
Tower 2 – Basement 1 floor column works completed & Awaiting for the GFC drawings