Professional Documents
Culture Documents
Permanent Works:
1. Roof slab casting planned for Oct 21, 2020 ( Grid 27 -31)
2. Wall shuttering work in progress for 1 st lift (base slab to concourse) grid 18 -20 in u/l side
3. No manpower deployed in ancillary building.
4. No manpower deployed for walls from concourse slab to roof.
5. Work of backfilling in earth mat area to be expedite.
6. Separate manpower required for UPE wall and Platform wall.
7. OTE casting delayed due to delayed due to manpower.
8. No M/s Normet engineer available at site for supervision.
Last week achieved:
1. Permanent works.
Target in Oct-20 Target date Progress as on date Planned for Remarks %
this month achieved
Grid 22-24 U/L 2nd 20/09/2020 (as Completed on 20/10/2020 23 Rm Insufficient 100%
per 3MRP) Manpower and
rectification
Temporary Works: