Dadar Station

Report Card-September month Date-21.10.2020


S. Activities Committed Achieved Achieved Overall (%)
No (in numbers) (in numbers) (%) Current month
progress
1 Base slab Grid 03-05 428 sqm 428 sqm 100%
2 Base slab Grid 17-19 373 sqm 373 sqm 100%
3 Main wall Grid 22-24 2nd lift u/l 64.8 sqm 00 On going
4 Main wall Grid 22-24 2nd lift d/l 64.8 sqm 00 On going
5 Main wall Grid 17-191st lift u/l and 129 sqm 00 On going

6 OTE slab Grid 22 -24 U/l and d/l 22.8 rm 00 On going


7 Main wall Grid 27 -31( concourse 146 sqm 146 100%
slab to roof slab

Report Card-planned for October month


S. No Activities Committed Achieved Achieved Overall (%) Current
(in numbers) (in numbers) (%) month progress

1 Base slab Grid 15-17 363 sqm On going


2 Main wall Grid 22-24 2nd 72 sqm 72 sqm 100% 100%
lift u/l
3 Main wall Grid 22-24 1st lift 82.5 82.5 sqm 100% 100%
d/l
4 Main wall Grid 25-27 1st lift 62.5 sqm 0 On going 0%
(concourse slab to roof)
5 Roof slab Grid 27-31 1301 sqm 0 On going
6 OTE slab Grid 22 -24 U/l 22.8 rm 0 On going
and d/l

Permanent Works:

1. Roof slab casting planned for Oct 21, 2020 ( Grid 27 -31)
2. Wall shuttering work in progress for 1 st lift (base slab to concourse) grid 18 -20 in u/l side
3. No manpower deployed in ancillary building.
4. No manpower deployed for walls from concourse slab to roof.
5. Work of backfilling in earth mat area to be expedite.
6. Separate manpower required for UPE wall and Platform wall.
7. OTE casting delayed due to delayed due to manpower.
8. No M/s Normet engineer available at site for supervision.
Last week achieved:

1. Permanent works.
Target in Oct-20 Target date Progress as on date Planned for Remarks %
this month achieved
Grid 22-24 U/L 2nd 20/09/2020 (as Completed on 20/10/2020 23 Rm Insufficient 100%
per 3MRP) Manpower and
rectification
Temporary Works:

1. Delay in PCC works grid 6 -8.