DAILY PROGRESS REPORT
Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently, the activities “Fascia Board Installation, Gutter Installation and Roof
Flashing Installation” has been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: September 1, 2022
  Current Activities Manpower % Completion
1 Fascia Board Installation 2 100%
2 Gutter Installation 2 100%
3 Roof Flashing Installation 2 100%
4 2nd Floor Putty Application 1 50%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, the activity “Ceiling Board Installation” has been completed.

Manpower Report: Block 06, Lot no. 35-36 Date: September 1, 2022

Current Activities Manpower % Completion


1 Interior Skim Coating (2nd layer) 2 95%
2 1st and 2nd Floor Window Finishing 2 50%
3 Ceiling Board Installation 3 100%
4 Clearing 2 50%
TABLE 1.2

Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activities “Clearing, Ceiling Frame Installation and T & B Window
Finishing” have been completed.

Manpower Report: Block 06, Lot no. 29-30 Date: September 1, 2022

Current Activities Manpower % Completion


1 Clearing 2 100%
2 Ceiling Frame Installation 2 100%
3 T & B Window Finishing 1 100%
TABLE 1.3