1. EAST STREET (GL T-S/12), Leakage observed coming from gasket between glass and
aluminum at Level 25 Panel 82 of BPO Tower 2.
2. EAST STREET (GL R-O/12), Leakage observed coming from miter at Level 26 Panel 90, 92,
and 100 of BPO Tower 2.
3. EAST STREET (GL T-S/12), Leakage observed coming from miter at Level 27 Panel 78 of
BPO Tower 2.
Based on the inspection conducted the source of leakages was due to poor workmanship. The leak’s
rectification was completed today. Please see attached plans and photos for your reference.
Thank you.
Yours truly,
ALUACE CORPORATION
Michelle Marcelo
Project-in-Charge
Cc:
Project File
Jenny Rubio
LEAK OBSERVED
LEAK OBSERVED
LEAK OBSERVED
LEAK OBSERVED
LEAK OBSERVED
ACTUAL PHOTOS
Figure 1. Level 25 Panel 82 Leak points rectification Figure 2. Level 25 Panel 82 Leak points rectification
Figure 3. Level 25 Panel 82 Leak points rectification Figure 4. Level 25 Panel 82 Done rectification
Figure 5. Level 25 Panel 82 Done rectification Figure 6. Level 25 Panel 82 Done rectification
ACTUAL PHOTOS
Figure 7. Level 26 Panel 90 Leak occurred in the miter Figure 8. Level 26 Panel 90 Leak done rectification
Figure 9. Level 26 Panel 92 Leak done rectification Figure 10. Level 26 Panel 100 Leak done rectification
Figure 11. Level 27 Panel 78 Leak occurred in the miter Figure 12. Level 27 Panel 78 Leak done rectification