Professional Documents
Culture Documents
TITTLE:
By:
Supervisor : Mr L. Ndlovhu
Zvishavane
June 2022
1
I. Declaration
The following students declare that this is their own unaided work, that this report has not
been submitted for examination to another department or institution, and that they understand
plagiarism is a punishable offence.
Introduction
This chapter gives an overview of the project. The background of the mine, project
background, problem statement, justification, aim and objectives of carrying out the project
are explained in this chapter.
1.0. Background
Sabi Gold Mine currently uses negative pressure ventilation system where they make use of
an exhaust fan to drive air from the underground environment to the surface. Air is drawn in
through the main shaft (Anglo shaft) and exhausted through the exhaust shaft. The exhaust
fan is placed 12m from the exhaust shaft in the 6-Level. When blasting is carried out,
compressed air is blown at development ends to exhaust blast fumes. The re-entry at Sabi
mine is scheduled to be 4 hours after blasting is carried out.
Sabi Gold Mine is located in the Midlands province of Zimbabwe about 15km South-East of
Zvishavane along the Rutenga-Beitbridge road in the Mberengwa Greenstone Belt. The
Greenstone belt is associated with minerals like gold, asbestos, nickel and copper. The belt
lies along the famous Great Dyke which is well known for hosting various minerals in
Zimbabwe.
(South, 2014)
The scheduled re-entry time of 4 hours is currently not being met as traces of noxious gases
will still be detected in the exhaust shaft even after the specified time. This is mainly as a
result of the less efficient compressed air system being utilized and leakages from open old
stopes, raises and crosscuts in abandoned working areas. This unplanned extension of the re-
entry time is affecting the overall production. The lashing and hoisting shift is failing to meet
production targets due to limited time. Failure to meet the production targets is causing the
mine to incur financial losses.
1.3 Project Justification
An efficient mine ventilation system plays a major role in the provision of fresh air and
removal of contaminants as a result increasing the morale of the working personnel. It also
facilitates in capital and operating costs, yield and safety. The major operations of a mine
include blasting which produces dust, toxic fumes and heat. A properly ventilated mine
speedily dilutes all noxious elements in time for production and safety. At Sabi Gold Mine,
this does not practically occur since the scheduled re-entry time is not met.
Production targets for the year 2022 have not been able to be met. The graph above clearly
shows how Sabi gold mine is failing to meet production targets for the first four months of
2022. This project will optimize the Sabi Mine ventilation system by introducing fans and
curb the air leakages in old stopes to minimize production losses.
Level Velocity(m/s) Area(m2) Q(m3/s)
1 0.378 8 3.025
2 0.356 8 2.845
3 0.332 8 2.655
4 0.331 8 2.650
5 0.329 8 2.635
6 0.318 8 2.540
7 0.266 8 2.130
8 0.264 8 2.115
9 0.263 8 2.100
10 0.261 8 2.090
11 0.258 8 2.065
12 0.258 8 2.060
28.910
Air quantity decrease from 3.025m3/s at level 1 to 2.060m3/s at level 12 and the
velocity also decreases due to air leakages from open old stopes, raises and crosscuts in
abandoned working areas, airway resistance.
Level CO(ppm) NxOy (ppm) O2
1 0 0 20
2 0 0 22
3 0 0 23
4 0 0 20
5 2 4 19
6 8 5 17
7 35 7 15
8 90 6 14
9 128 8 15
10 125 7 13
11 130 8 12
12 135 9 10
Oxides of nitrogen are above the required limit of ≤ 5 ppm of air from 7-level to 12-
level. NO levels increase also as we go down the mine in working areas because air
distribution poor since most fresh air is lost in upper levels due to airflow leakages
resulting in accumulation of NxOy. Moreover, NxOy components are also denser than
air so they amass in the lower levels.
From 6-level to 12-level, oxygen percentage is below 19% which is the minimum
required percentage in the air because compressed air is reaching lower levels in short
supply.
1.4 Aim
To optimize the Sabi mine ventilation system in order to meet the scheduled re-entry time of
4 hours
1.5 Objectives
In light of the aforementioned problem description, the following major goals have been
defined in an effort to address the issue;
3-Dimensional modelling of Sabi gold mine ventilation system.
Contaminant simulation of the ventilation system to figure out how much air is
needed to reduce the overall contaminants load. Specify the kind of ventilation system
that should be utilized for mining deep portions.
To improve the quantity and direction of air in the current working area.
1.6. Limitations
The project should be finalized and submitted by August 2022. To deal with constraint, we
had to pursue the project with much dedication and focus. More-over COVID restrictions
proved to be a hurdle in our pursuit to acquire the relevant data to carry out the project thus
we had to be vaccinated and be tested for the Covid-19 virus 24 hours before our mine visit
in order to be granted entry into the mine. Only the materials provided to us during the
conduction of the project served as the basis for the analysis that was done. Consequently,
there may be some additional information, that is already available that could slightly modify
the final result of the research and, ultimately, change the conclusion.
1.8. Delimitations
The study focuses on mine ventilation issue of contaminate build up in relation to the depth at
which mining operations are occurring. Since all additional difficulties the mine encounters
are deemed outside the purview of the investigation, they have not been included in the
research but have nonetheless been properly acknowledged.
Chapter 2
Literature Review
2.0 Introduction
A safe and affordable ventilation system is an essential component of all underground mines.
The goal of any underground ventilation system is to provide adequate quantity and quality
air to airflows in order to mitigate air contaminants and achieve safe concentrations in
underground workplaces where workforce is required (McPherson, 2009). It is the
responsibility of ventilation engineers to understand mine ventilation practices, escape and
rescue design, and mine ventilation economics (Wallace, 2015). The efficiency of a mine
ventilation system eventually limits mine production.
There is evidence of a trend in metal mines toward larger diesel equipment, increased
production targets, and increased regulations to reduce respirable particulate dust (silica
and/or DPM) (Brake, 2013). As mines get deeper, the need for refrigeration grows (Du
Plessiss, 2014).VOD theory is based on applying airflow only to working areas while
limiting airflow to the remaining areas. The system necessitates variable frequency drive fan
motors, air gas sensors, regulator and fan control systems, and tagging systems. Monitoring
of fan performance and air quality should be required. Explosive gases should be monitored
in closed gobs and entries. Other parameters such as air temperature and humidity should be
monitored at strategic underground locations and via fan systems.
2.1 Negative Pressure Ventilation System
Natural ventilation pressure is the pressure created by opposing air masses of differing
densities in a closed circuit with a height difference. It is known as natural ventilation flow
when it forms. The difference in air density on either side of the loop under the influence of
earth's gravity creates the natural ventilation pressure, which is in accordance with the law of
energy conservation. A unique variation of the natural ventilation pressure is the pressure
during a fire. One aspect of a mine's ventilation power is its natural ventilation pressure,
which is influenced by the weather on the ground as well as the mine's production and design
elements. The instability of subsurface air flow, which could compromise public safety,
could be brought on by a shift in atmospheric pressure (He Z. Y., Ran. S., and Li. Z. S., et al.)
Without ventilation, a mine would be an extremely inhospitable place for both working
people and machines. As a result, mining ventilation is essential to the day-to-day operations
of mining. It has been shown that mine ventilation has played a crucial role in mining
systems since the very beginning (Hartman, H. L., Mutmansky, Ramani, and Wang, 1997).
REFERENCE
Fox projects reports, September, 2014.
Hartman, H. L., Mutmansky, J. M., Ramani, R. V., & J., W. Y. (1997). Mine Ventilationand
Air conditioning Ed 3. Canada: John Wiley & Sons.
Burrows, J., et al., eds., 1982, Environmental Engineering in South African Mines,Mine
Ventilation Society of South Africa, Johannesburg
Hartman, H.L., Introductory Mining Engineering, 1987, Wiley Interscience, New York.
Hartman, H.L., Mutmansky, J.M., and Wang, Y.J., eds., 1982, Mine Ventilation and
AirConditioning, 2nd ed., Wiley Interscience, New York.
A Guide to Mining Regulations,
Chambers of Mines of South Africa, Measurements in Mine Environmental
Control,Johannesburg, 1982.