CERRO VERDE PRODUCTION UNIT


EXPANSION

Coarse Ore Vibrating Screens Lifting pipe Details

Document No. SN-100462-MD21

G:\SALES & SERVICE\CERRO VERDE FASE II\MASTER DOCUMENTS\NATIVE FORMAT DOCUMENTS\SN-100462-MD21 REV 2 - LIFTING PIPE DETAILS.DOCX
DOCUMENT CONTROL PAGE

Document Title: Coarse Ore Vibrating Screens Lifting pipe details


Document Number/(code) SN-100462-MD21/(CALC)
File Location: G:\Sales & Service\Cerro Verde Fase II\Master Documents
Original date of issue: 03/04/2012
Author: Cristobal Brant
Job No: SN-100462
Engineering Track No: 4831

Client: Fluor
Site: Sociedad Minera Cerro Verde
Client Contact: Michael Taylor

REPORT CONTROL
For External Distribution: Limited External Distribution – Only to be distributed by
Ludowici Ltd. This document is not to be passed on to other
parties without written permission from Ludowici Ltd.

REVISION HISTORY
Rev Date Author Checked by Approved For Description (main changes)
Release by

0 03/04/2012 Cristobal Eddie Mckerr Eddie Mckerr Original Release


Brant

1 19/04/2012 Cristobal Sarah Bauer Eddie Mckerr Screens Tag Nos. Revised in
Brant section 1.

2 26/04/2012 Cristobal Sarah Bauer Eddie Mckerr Lifting pipe end view added.
Brant

G:\SALES & SERVICE\CERRO VERDE FASE II\MASTER DOCUMENTS\NATIVE FORMAT DOCUMENTS\SN-100462-MD21 REV 2 - LIFTING PIPE DETAILS.DOCX
i

CONTENTS

1 SUMMARY 1

2 LIFTING PIPE DETAILS 1

G:\SALES & SERVICE\CERRO VERDE FASE II\MASTER DOCUMENTS\NATIVE FORMAT DOCUMENTS\SN-100462-MD21 REV 2 - LIFTING PIPE DETAILS.DOCX
1

1 SUMMARY
This document is to detail the lifting pipes used in the coarse ore vibrating screens Tag No. C2-3340-
SC011 TO 030.

Note that no lifting lugs as such are used in these vibrating screens. Two structural cross pipes are used
for rigging and lifting the machines.

This document is to be used with the Screen Installation Layout SN-100462-D001.

2 LIFTING PIPE DETAILS


The following figures outline the details for the lifting pipes. For lifting pipe location on the screen refer
to SN-100462-D001.

1 Lifting/Spreader Pipe
2 End plate
3 Ring

Figure 1: Lifting pipe 3D view and main parts.

Each lifting pipe is secured to the side plates using eight (8) off C50LRBR32-20 Huck bolts.

Pipe used is 250DN-SCH60.

G:\SALES & SERVICE\CERRO VERDE FASE II\MASTER DOCUMENTS\NATIVE FORMAT DOCUMENTS\SN-100462-MD21 REV 2 - LIFTING PIPE DETAILS.DOCX
2

Figure 2: Lifting pipe end view. Note that ring was hidden for clarity.

Figure 3: Lifting pipe front view.

G:\SALES & SERVICE\CERRO VERDE FASE II\MASTER DOCUMENTS\NATIVE FORMAT DOCUMENTS\SN-100462-MD21 REV 2 - LIFTING PIPE DETAILS.DOCX