Professional Documents
Culture Documents
Villaverde, Allan A.
DAILY PROGRESS REPORT
Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently the activity “Tile Work and Exterior Skim Coat Application (2nd Layer)”
has been completed.
Manpower Report: Block 04, Lot no. 29-30 Date: September 7, 2022
Current Activities Manpower % Completion
1 Exterior Roof Ceiling Board Installation 2 25%
2 Tile Work 2 100%
3 Exterior Skim Coat Application (2nd Layer) 2 100%
4 Panel Board Relocation 1 50%
TABLE 1.1
Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently the activity “Electrical Wiring” is ongoing with a progress of 30% until
completion.
Manpower Report: Block 06, Lot no. 35-36 Date: September 7, 2022
Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activity “Panel Board Relocation” has been completed.
Manpower Report: Block 06, Lot no. 29-30 Date: September 7, 2022