205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Report Contents:
1. HSSE
7. Skyline Report
9. Areas of concern.
11. Photos
12. Attachments
10.1 Skyline
Page 2 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
1. HSSE
Total to
NO Type of Measures Last Week Pervious Notes
Date
Page 3 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Planned Dates
Planned Actual Dev/
Activity R. Wt.
Start Date Finish Date B/L (%) (%) Item
Page 4 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
2.3.4 Construction
Civil Works
Continue cutting works for Sewer & Storm network.
Continue backfilling works for Roads.
Continue Concrete works at OSBL Area.
Continue finishing works.
Continue Interlocks erection (33,200 m2 out of 111,700 m2).
Mechanical Works
Continue Steel Structure erection works (5,325 ton out of 5,510 ton).
Continue cladding works (50,138 m2 out of 60,000 m2).
Continue grating erection (2,017 m2 out of 8,532 m2).
Continue Ducts installation (360 ton out of 451 ton).
Continue Equipment installation works for production line (4,695 ton out 5,470 ton).
Complete Tanks erection works (501 ton) – Fire tank under painting.
Continue Piping fabrication works in Maadia Workshops (25,085 D.I out of 33,279 D.I).
Continue piping erection works (15,370 D.I out of 21,715 D.I).
Continue HDPE piping erection works (31,955 D.I out of 40,000 D.I).
Continue insulation works (852 m2 out of 26,800 m2).
E&I Works
Continue cable trays erection (21,695 M.L out of 26,000 M.L).
Continue power and control cable laying works (308,041 M.L out of 353,500 M.L).
Continue instrument cable laying works (120,779 M.L out of 359,000 M.L).
Continue termination works (6,351 Ea. out of 16,736 Ea.).
Page 5 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Page 6 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Civil Network 9 - 9 - 9 - 9
Cathodic Protection 28 - 28 - 28 - 28
Fire - Fighting 31 - 31 - 31 - 31
HVAC 46 - 46 - 46 - 46
Instrumentation 38
38 - 38 - 38 -
(Control System)
Loss Prevention 59 - 59 - 59 - 59
Mechanical 17 - 17 - 17 - 17
Piping 26 - 26 - 26 - 26
Process 30 - 30 - 30 - 30
Tanks 83 - 83 - 83 - 83
Page 7 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Civil Network 9 - 9 - 9 - 9
Cathodic Protection 28 - 28 - 28 - 28
Fire - Fighting 31 - 31 - 31 - 31
HVAC 46 - 46 - 46 - 46
Instrumentation 38
38 - 38 - 38 -
(Control System)
Loss Prevention 59 - 59 - 59 - 59
Mechanical 17 - 17 - 17 - 17
Piping 26 - 26 - 26 - 26
Process 30 - 30 - 30 - 30
Tanks 83 - 83 - 83 - 83
Page 8 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
MRQ (Actual
Planned This Week Planned Next Week
Done)
Commodities Total
This This Next
To Date To Date To Date
Week Week Week
Piping Bulk 6 - 6 - 6 - 6
Valves 7 - 7 - 7 - 7
Equipment &
8 - 8 - 8 - 8
Packages
Fire - Fighting 8 - 8 - 8 - 8
Instrumentation 6 - 6 - 6 - 6
Electrical 33 - 33 - 33 - 33
Telecommunication 13 - 13 - 13 - 13
Steel Structure 17 - 17 - 17 - 17
HVAC 13 - 13 - 13 - 13
Page 9 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
3.1.3 Logistics: -
None
Page 10 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Page 11 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Electrical
Lighting Poles Ea. 880 880
Switch & Sockets Lot 100% 100%
Lighting Fixtures (Explosion Proof) Lot 100% 75%
Lighting Fixtures Lot 100% 90%
Earthing Cables M.L 15,000 15,000
Lightning Protection System Lot 100% 100%
MV Switchgear Ea. 23 23
LV Switchgear & Bus Duct Ea. 100 100
Transformers Ea. 12 12
AC UPS Ea. 4 2
DC UPS Ea. 4 4
Emergency Generator Ea. 1
Distribution Board Ea. 35 13
Power & Control Cables M.L 353,500 353,500
Cable Trays M.L 26,000 23,000
Explosion proof material Lot 100% 75%
Capacitor Banks Lot 100%
Cable Glands Lot 100% 100%
Reducers Ea. 710
Conduit M.L 7,000 7,000
Instrumentation (Control System)
Instrument Cables M.L 359,000 319,000
DCS Ea. 1
Cable Glands Lot 100% 100%
Instrument Bulk Material (Hook up) Lot 100% 100%
Instrument JB's Ea. 580 558
Analyzers Lot 100% 100%
Mechanical Level Indicators Lot 100% 100%
Field Instrument Ea. 340 335
Control Valves Ea. 47 28
Flow Meters Lot 100% 100%
Telecommunication
IP Telephone Lot 100% 60%
CCTV Lot 100% 20%
Public Address Lot 100%
Data Network Lot 100% 40%
Data Center Lot 100%
HVAC
HVAC Ea. 208 157
Page 12 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Cathodic Protection
Cathodic Protection Lot 100% 100%
Others “Sec.6”
Tank Agitators Lot 100% 100%
SS Explosion Proof Vent Lot 100% 100%
Over Head Crane Ea. 1 1
Straw Bale Grap for O.H.C Lot 100% 100%
Refractory Ton 275 275
Rails Ton 110 65
Mobile Fuel Station Ea. 1
Mirror Station Lot 100%
Sound / Noise Cabient Ea. 19
GRP Tank for Reject Water (150m3) Ea. 1
HDPE Tanks for Potable Water (20m3) Ea. 2 2
Oils Lot 100%
Safety Barriers & Fence M2 3,000
Electrical secured accesses door Ea. 75
Steel Structures, Plates, Supports & Grating
Steel Structure ton 5,510 5,480
Tank Plates ton 501 501
Grating M2 6,135 2,387
Chuqured Plates M2 1,105
Page 13 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Page 14 of 234
STEEL STRUCTURE STATUS FOR MDF PROJECT
As of date: 11‐02‐23
MATERIAL FABRICATION
TOTAL WEIGHT WSD DWG
AREA ARRIVE FOR
(TON) APPROVAL PLAN ACTUAL
FINAL FAB.
QTY QTY
PLOT‐1 1968 1968 1968 1968 1949
PLOT‐2 1240 1240 1240 1240 1208
PLOT‐3 346 346 345 346 343
PLOT‐4 807 807 807 807 805
PLOT‐5 310 310 310 310 310
PLOT‐6 365 365 365 365 365
PLOT‐7 165 165 165 165 163
Sheds 215 207 205 215 204
Filters 18 18 18 18 16.7
Pipe Racks 14 14 14 14 14
Platforms 31 31 29 31 29
Gates 31 31 31 31 31
TOTAL 5510 5502 5497 5510 5438
Page 15 of 234
MDF PROJECT : MEDIUM‐ DENSITY FIBERBOARD
Equipment Fabrication Status
As of Date:‐ 11‐2‐2023
Page 16 of 234
MDF PROJECT : MEDIUM‐ DENSITY FIBERBOARD
FABRICATION
As of Date:‐ 11‐2‐2023
WEIGHT
EQUIPMENT PLOT START FINISH PLAN ACTUAL DISPATCH
(TON)
CYCLONES 194.5
High Efficiency Cyclone ‐ Group 2420 2 21‐08‐22 10‐10‐22 50.2 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2531 2 30‐03‐21 18‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2532 2 30‐03‐21 16‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2533 2 19‐04‐21 22‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2534 2 19‐04‐21 20‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone ‐ Group 2615/2616 1 09‐11‐21 21‐03‐22 36.5 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4910 2 06‐12‐21 06‐04‐22 7.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4920 1 17‐11‐21 15‐03‐22 7.5 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4946 2 06‐12‐21 03‐04‐22 11.8 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R1) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R2) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R3) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L1) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L2) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L3) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
CHAMBERS 77.4
Vertical combustion chamber ‐ Group 2425.016 ‐ EP (CH‐1000) 3 10‐10‐21 05‐01‐22 40.1 100.0% 100.0% 100.0%
Quench chamber ‐ Group 7385.060 ‐ EP (CH‐1010) 3 13‐10‐21 05‐01‐22 8.5 100.0% 100.0% 100.0%
Mixing chamber ‐ Group 2420‐022 ‐ Dryer (CH‐1030) 7 04‐12‐21 28‐02‐22 13.7 100.0% 100.0% 100.0%
Mixing chamber ‐ Group 7385.065 ‐ EP (CH‐1020) 3 11‐11‐21 30‐01‐22 15.1 100.0% 100.0% 100.0%
VESSELS 153.5
Vessel (Drain Box) ‐ Group 2310 / 2332 4 01‐01‐23 04‐02‐23 10.0 100.0% 80.0% 0.0%
Vessel (Vent Container) ‐ Group 7390 3 16‐12‐21 17‐02‐22 1.8 100.0% 100.0% 100.0%
Emulsion Storage Tank (7ea.) ‐ Group 3226 4 05‐07‐21 07‐02‐22 56.0 100.0% 100.0% 100.0%
Expansion Tank ‐ Group 7390 (T‐1040) 3 30‐10‐21 07‐02‐22 3.5 100.0% 100.0% 100.0%
Fill and Drain Tank ‐ Group 7390 (T‐1050) 3 30‐10‐21 07‐02‐22 7.0 100.0% 100.0% 100.0%
Hot Water Tank ‐ Group 4390 3 16‐12‐21 13‐02‐22 10.0 100.0% 100.0% 100.0%
Blow Down Tank ‐ Group 7395 3 23‐11‐21 27‐02‐22 1.1 100.0% 100.0% 100.0%
Feed water Tank with Deaerator ‐ Group 7395 3 27‐12‐21 07‐03‐22 8.1 100.0% 100.0% 100.0%
PMDI Storage Tank (4a.) 4 21‐08‐22 23‐08‐22 56.0 100.0% 100.0% 100.0%
STACKS 55
Emergency Stack ‐ Group 2425.016 (ST‐1000) 3 20‐10‐21 13‐01‐22 10 100.0% 100.0% 100.0%
Start‐up Stack ‐ Group 7385.090 (ST‐1010) 3 13‐11‐21 03‐03‐22 45 100.0% 100.0% 100.0%
THERMAL OIL HEATER 40
Thermal Oil Heater 3 03‐10‐21 24‐01‐22 40 100.0% 100.0% 100.0%
SILOS 250
Sanding dust Silo ‐ Group 7110 3 21‐08‐22 15‐10‐22 70 100.0% 100.0% 100.0%
Reject Fiber Silo ‐ Group 7120 2 21‐08‐22 14‐09‐22 60 100.0% 100.0% 100.0%
Saw Dust Silo ‐ Group 7130 5 09‐09‐21 30‐04‐22 55 100.0% 100.0% 100.0%
Pulverizer Silo ‐ Group 7140 3 09‐10‐21 30‐04‐22 65 100.0% 100.0% 100.0%
OTHERS 6.0
Safety Cooling Tank ‐ Group 7390 3 20‐12‐21 28‐02‐22 4.0 100.0% 100.0% 100.0%
Containers (2ea.) for Sludge and Solids
1 20‐02‐22 21‐04‐22 2.0 100.0% 100.0% 100.0%
(Sedimentation tank) ‐ Group 4550
TOTAL 776.4 100.0% 99.7% 98.7%
Page 17 of 234
Ducts Manufacturing Status
As of Date: 11‐Feb‐2023
Delivery to Site Plan Actual
Activity Weight (Ton) Plan Actual
(Ton) Qty. Qty.
Ducts Work 451.5 439.6 451.5 441.8 100.0% 98.5%
Engineering ‐ ‐ ‐ ‐ 100.0% 100.0%
Material Supply ‐ ‐ ‐ ‐ 100.0% 100.0%
Fabrication 451.5 439.6 100.0% 97.9%
Pneumatic Conveyors 256.8 256.73 256.8 256.8 100.0% 100.0%
Dryer Duct 38.8 38.76 38.8 38.8 100.0% 100.0%
Crude Gas Duct 31.4 31.36 31.4 31.4 100.0% 100.0%
Energy Plant 65.7 65.65 65.7 65.7 100.0% 100.0%
Connecting Chutes & Supports 58.9 47.14 58.9 49.2 100.0% 83.6%
Page 18 of 234
Ducts Manufacturing Status (Detailed)
As of Date: 11‐Feb‐2023
Activity Weight (Ton) R.W Start Date Finish Date Plan Actual
Ducts (Pneumatic, Dryer, Crude Gas, Energy Plant & Chutes) 100.0% 1‐Jul‐2021 15‐Feb‐2022 100.0% 100.0%
Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (1) ‐ Group 1242 &1243 7.4 2.9% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 1321 / 1331 / 1341 8.1 3.1% 29‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 1531 3.8 1.5% 29‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (3) ‐ Group 1282 &1283 7.5 2.9% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 2531 / 2532 / 2533 / 2534 15.8 6.2% 21‐Nov‐2021 31‐Mar‐2022 100.0% 100.0%
Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (2) ‐ Group 1262 &1263 7.6 3.0% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct Works & Pipes with bends and flanges ‐ Group 2615 / 2616 45.1 17.6% 2‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 2770 / 2780 / 2782 / 2785 15.1 5.9% 24‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 3905 8.4 3.3% 6‐Feb‐2022 16‐Mar‐2022 100.0% 100.0%
Fab.‐Duct Work, Pipes & Hoods ‐ Group 4550 20.9 8.1% 12‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐Duct Work & Pipes ‐ Group 4910 / 4920 / 4946 / 4970 / 4975 78.0 30.4% 29‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 5910 / 5917 / 5920 37.5 14.6% 31‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%
Fab.‐ Pipe ducts with bends and flanges ‐ Group 7112 / 7131 1.5 0.6% 2‐Apr‐2022 23‐May‐2022 100.0% 100.0%
Fab.‐ Drier Duct (From Drier to High Effeciency Cyclone) ‐ Group 2420 38.8 100.0% 1‐Jan‐2023 4‐Feb‐2023 100.0% 100.0%
Fab.‐ Crude gas duct ‐ Group 7410 31.4 100.0% 12‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct work from combustion air fan to the burner ‐ Group 7370.061 2.2 3.3% 6‐Dec‐2021 2‐Mar‐2022 100.0% 100.0%
Fab.‐ Duct work from cooling air fan to the burner ‐ Group 7370.062 1.3 1.9% 1‐Dec‐2021 2‐Mar‐2022 100.0% 100.0%
Fab.‐ Air Grader (new scope) 9.9 15.0% 1‐Jan‐2023 4‐Feb‐2023 100.0% 100.0%
Fab.‐ Transport pipes ducts for dust ‐ Group 7370 1.8 2.8% 21‐Aug‐2022 27‐Aug‐2022 100.0% 100.0%
Fab.‐ Duct work from ambient air fan to quench chamber ‐ Group 7385.060 0.3 0.4% 18‐Jan‐2022 2‐Feb‐2022 100.0% 100.0%
Fab.‐ Duct work from ambient air fan to mixing chamber ‐ Group 7385.065 0.8 1.3% 8‐Jan‐2022 13‐Mar‐2022 100.0% 100.0%
Fab.‐ Duct work from mixing chamber to cyclones ‐ Group 7385.065 0.8 1.3% 8‐Jan‐2022 13‐Mar‐2022 100.0% 100.0%
Fab.‐ Duct work from thermal oil heater to mixing chamber ‐ Group 7385.065 0.8 1.3% 25‐Dec‐2021 21‐Feb‐2022 100.0% 100.0%
Fab.‐ Duct work from dust collector (Cyclones) to Ash Crews ‐ Group 7385.080 10.5 15.9% 10‐Feb‐2022 4‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct work from dust collector (Cyclones) to Main ID fan ‐ Group 7385.080 10.5 15.9% 10‐Feb‐2022 4‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct work from the Main ID fan to Dryer Mixing Chamber ‐ Group 7385.090 5.7 8.6% 28‐Feb‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct work from the main id fan to start up stack ‐ Group 7385.090 5.7 8.6% 28‐Feb‐2022 16‐Apr‐2022 100.0% 100.0%
Fab.‐ Duct work from thermal oil heater fan to mixing chamber ‐ Group 7390 7.7 11.8% 22‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%
Fab.‐ Duct work from thermal oil heater to thermal oil heater fan ‐ Group 7390 7.7 11.8% 3‐Feb‐2022 28‐Mar‐2022 100.0% 100.0%
Chutes ‐ Supports ‐ Silencer ‐ Doors & loose items 58.9 13.1% 21‐Aug‐2022 4‐Feb‐2023 100.0% 83.6%
Fab.‐ Chutes, Doors & loose items ‐ Group 2300 36.3 61.6% 1‐Jan‐2023 4‐Feb‐2023 100.0% 89.3%
Fab.‐ Pneumatic Supports ‐ Group 2600 16.9 28.6% 21‐Aug‐2022 31‐Oct‐2022 100.0% 100.0%
Page 19 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
6. Construction
Actual
Total Plan Qty.
Activity Unit Actual Prog.
Qty. B/L
(%)
Civil Works
Cutting Works M3 712,000 712,000 711,070 99.9%
Backfilling Works M3 1,280,390 1,280,316 1,264,405 98.8%
Piles Work EA 4,483 4,483 4,483 100.0%
Pile Head Cracking EA 4,483 4,483 4,477 99.9%
Concrete Works M3 35,410 35,410 34,563 97.6%
Interlock M2 111,700 111,700 33,200 29.7%
Mechanical Works
Steel Structure Erection Ton 5,510 5,510 5,330 96.7%
Duct Erection Ton 452 452 374 82.9%
SK Equipment Installation Ton 5,470 5,470 4,739 86.6%
Piping Fabrication Inch 33,279 33,279 26,111 78.5%
Piping Erection Inch 21,715 21,715 15,781 72.7%
Piping Erection (SK) Inch 4,315 4,315 3,814 88.4%
Piping HDPE Inch 40,000 40,000 32,805 82.0%
Tanks Erection Ton 501 500 501 99.9%
Electrical Works
Cable Trays Installation M.L 26,000 26,000 23,500 90.4%
Cable Laying M.L 712,500 712,500 474,948 66.7%
Termination EA 16,736 16,736 7,132 42.6%
HVAC EA 208 208 101 48.6%
Lighting Fixtures EA 3,065 3,065 1,286 42.0%
Panels EA 486 486 450 92.6%
Transformers EA 12 12 12 100.0%
Page 20 of 234
Concrete Activity
Concrete for production line: Buildings: Others:
Total Total Total
Activity Plan Actual Activity Plan Actual Activity Plan Actual
Qty. Qty. Qty.
Plot‐1 9,301 9,301 9,301 TCF 670 670 670 Guard Towers 116 116 101
Plot‐2 3,294 3,294 3,294 Substation 440 440 440 Tanks (101‐102‐103) 252 252 252
Plot‐3 814.6 815 815 CH Warehouse 105 105 105 P.W Tank 84 84 84
Plot‐4 2441 2,441 2,441 Scale With Room 283 283 283 Fire Water Tank 60 60 60
Plot‐5 1448 1,448 1,448 HSE & Control Room 769.02 769 769 Pits & Sheds 839 839 385
Plot‐6 1993 1,993 1,993 Air Compressor Shed 277 277 277 P.W Network 228.31 228 228
Plot‐7 1163.5 1,164 1,164 Inds. Pump Station 158 158 158 Sewer Network 499 499 499
Control Room 15 15 15 P.W Pump Station 128 128 128 Storm Network 385 385 370
Switch Rooms 689 689 689 Reject Pump Station 83 83 83 Electrical Network 2968 2,968 2,968
Sub‐Total 21,159 21,159 21,159 Inds. Treatment PKG. 712 712 712 E&I Network 101 101 101
Fire Pump Shed 164 164 164 Piping Sleepers 89 89 89
New Switch Room 94 94 94 Fences (External) 2933 2,933 2,933
Main Security 56 56 56 Gates 60 60 60
Catch Basin , Sound
Security Building 56 56 56 Cabient ,Ditch & 612 612 524
Genrator
Mosque 90 90 90 Trenches Cover 940 940 665
Sub‐Total 4,085 4,085 4,085 Sub‐Total 10,166 #### 9,319
Page 21 of 234
STEEL STRUCTURE STATUS FOR MDF PROJECT
As of date: 11‐02‐23
MATERIAL ERECTION
TOTAL WEIGHT WSD DWG
AREA ARRIVE FOR
(TON) APPROVAL PLAN ACTUAL
FINAL FAB.
QTY QTY
PLOT‐1 1968 1968 1968 1968 1945
PLOT‐2 1240 1240 1240 1240 1185
PLOT‐3 346 346 345 346 338
PLOT‐4 807 807 807 807 764
PLOT‐5 310 310 310 310 309
PLOT‐6 365 365 365 365 365
PLOT‐7 165 165 165 165 157
Sheds 215 207 205 215 186
Filters 18 18 18 18 16.0
Pipe Racks 14 14 14 14 14
Platforms 31 31 29 31 20
Gates 31 31 31 31 31
TOTAL 5510 5502 5497 5510 5330
Page 22 of 234
ﺍﻟﻣﺗﺎﺡ ﺍﻟﻣﺗﺑﻘﻰ ﺍﻟﻭﺣﺩﺓ ﺍﻟﻛﻣﻳﺔ ﺍﻻﺟﻣﺎﻟﻲ ﺍﻟﻛﻣﻳﺔ ﺍﻟﻣﻧﻔﺫﺓ ﺍﻟﻧﺷﺎﻁ
40,299 257,552 454,948 712,500 ﻡﻁ ﺍﻋﻣﺎﻝ ﻓﺭﺩ ﺍﻟﻛﺎﺑﻼﺕ
Power & Control Cables for
405 18,484 143,516 162,000 ﻡﻁ
Production Line (ISBL)
Power & Control Cables From Sub-
5,268 87,232 92,500 ﻡﻁ Station to All Buildings, Packages &
Pumps Station
Lighting cables for the Production
2,000 16,417 62,583 79,000 ﻡﻁ
Line (ISBL)
Lighting cables for outdoor streets
100 2,868 17,132 20,000 ﻡﻁ
(OSBL)
Instrument Cables for the Production
37,794 175,240 139,760 315,000 ﻡﻁ
Line (ISBL)
Instrument Cables for Utilities
39,275 4,725 44,000 ﻡﻁ
(OSBL)
Page 23 of 234
Piping Works In-MDF
1. Metalic Material (CS-SS-SD). As of Date: 9-Feb-23
Total % PO Avilable(From Total DI)
Total Total
Material Fabrication Total D.I PO No. Arrived to Type Arrived Fabricated Erecred Notes
Erection D.I Construction Not construction Done
D.I Site
84 100% ﻣﺤﻠﻲ
85 100% ﻣﺤﻠﻲ
Galvanized 440 100% ﻣﺤﻠﻲ
0 7,911 7,911 6,395 0 0 0 7,407 7,407 0
"Threaded" 257 100% ﻣﺤﻠﻲ
527 92% ﻣﺤﻠﻲ
334 100% ﺧﺎﺭﺟﻲ
84 100% ﻣﺤﻠﻲ
3,733 16 85 100% ﻣﺤﻠﻲ 3,713 3,697 36 3,733 16 3,749
Carbon Steel-CS 440 100% ﻣﺤﻠﻲ . ﺍﺳﺒﻮﻟﺔ ﻣﻦ ﺍﻟﻮﺭﺷﺔ ﻟﻠﺠﻠﻔﻨﺔ247 * ﺗﻢ ﻧﻘﻞ
11,985
"Galvanized" 257 95% ﻣﺤﻠﻲ ﺇﺳﺒﻮﻟﺔ ﻣﻦ ﺍﻟﺠﻠﻔﻨﺔ ﺇﻟﻲ ﺍﻟﻤﻮﻗﻊ ﻭﺗﻢ ﺩﻫﺎﻧﻬﻢ234 * ﺗﻢ ﻭﺻﻮﻝ
7,638 599 527 100% ﻣﺤﻠﻲ 4,612 4,000 3,638 4,089 0 4,089
334 100% ﺧﺎﺭﺟﻲ
84 100% ﻣﺤﻠﻲ
85 100% ﻣﺤﻠﻲ
440 100% ﻣﺤﻠﻲ
Carbon Steel-CS
16,447 9,470 25,917 527 92% ﻣﺤﻠﻲ 23,917 15,890 8,027 14,872 7,363 22,235 ﺑﻮﺻﺔ ﻗﻄﺮﻳﺔ927 * ﺗﻢ ﺇﻋﺎﺩﺓ ﻟﺤﺎﻡ ﺑﺈﺟﻤﺎﻟﻲ ﻛﻤﻴﺔ
"Painted" ﺧﺎﺭﺟﻲ
130 100%
"DIN"
ﺧﺎﺭﺟﻲ
478 100%
"DIN"
334 100% ﺧﺎﺭﺟﻲ
205 100% ﻣﺤﻠﻲ
Stainless Steel-SS 4,870 3,107 7,977 527 92% ﻣﺤﻠﻲ 5,977 3,354 4,623 1,968 907 2,875 . ﺑﻮﺻﺔ ﻗﻄﺮﻳﺔ22 * ﺗﻢ ﺇﻋﺎﺩﺓ ﻟﺤﺎﻡ ﻹﺟﻤﺎﻟﻲ ﻛﻤﻴﺔ
334 100% ﺧﺎﺭﺟﻲ
128 100% ﺧﺎﺭﺟﻲ
Supper Duplex-SD 626 613 1,239 883 0 1,239 482 88 570 0
262 100% ﺧﺎﺭﺟﻲ
33,314 21,714 55,028 45,496 26,941 17,562 25,144 15,780 40,923
Page 25 of 234
21-01-23 MDF TANKS
Capacit INNER TOTAL TOTAL PRE-FABRICATION
HEIGH (TON)
TANK NO. y DIA (M
T (M)
WEIGHT BOTTOM SHELL ROOF MISCELLANEOUS
(M3) ) (TON ) PLAN ACTUAL DONE % DONE % DONE % DONE %
Industrial Raw
3,350 23 10.8 166.2 166.19 166.19 42.17 100% 60.27 100% 55.00 100% 8.75 100%
Water Tank - 101A
Process Water Tank -
2,000 18 10.0 108.5 108.47 108.47 27.74 100% 42.49 100% 31.46 100% 6.77 100%
102A
Demi Water Tank -
1,188 16 7.5 76.2 76.20 76.20 22.20 100% 23.58 100% 24.46 100% 5.97 100%
103A
FIRE WATER TK-
3,000 21 10.5 150.3 150.29 150.29 37.29 100% 49.65 100% 49.51 100% 13.84 100%
001
TOTAL ERECTION
Capacit INNER TOTAL
HEIGH (TON) BOTTOM SHELL ROOF MISCELLANEOUS
TANK NO. y DIA (M
T (M)
WEIGHT
(M3) ) (TON ) PLAN ACTUAL Done % Done % Done % Done %
Industrial Raw
3,350 23 10.8 166.2 166.19 166.19 42.17 100% 60.27 100% 55.00 100% 8.75 100%
Water Tank - 101A
Process Water Tank -
2,000 18 10.0 108.5 108.47 108.39 27.74 100% 42.49 100% 31.46 100% 6.69 98.8%
102A
Demi Water Tank -
1,188 16 7.5 76.2 76.20 76.20 22.20 100% 23.58 100% 24.46 100% 5.97 100.0%
103A
FIRE WATER TK-
3,000 21 10.5 150.3 150.29 150.29 37.29 100% 49.65 100% 49.51 100% 13.84 100%
001
Page 26 of 234
Ducts Erection Status
As of Date: 11‐Feb‐2023
Page 27 of 234
Ducts Erection Status (Detailed)
As of Date: 11‐Feb‐2023
Activity Weight (Ton) R.W Start Date Finish Date Plan Actual
Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (1) ‐ Group 1242 &1243 7.4 2.9% 1‐Jan‐2023 5‐Jan‐2023 100.0% 97.0%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 1321 / 1331 / 1341 8.1 3.1% 20‐Aug‐2022 13‐Oct‐2022 100.0% 100.0%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 1531 3.8 1.5% 1‐Jan‐2023 22‐Jan‐2023 100.0% 100.0%
Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (3) ‐ Group 1282 &1283 7.5 2.9% 1‐Jan‐2023 4‐Jan‐2023 100.0% 97.0%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 2531 / 2532 / 2533 / 2534 15.8 6.2% 12‐Sep‐2022 8‐Oct‐2022 100.0% 100.0%
Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (2) ‐ Group 1262 &1263 7.6 3.0% 1‐Jan‐2023 4‐Jan‐2023 100.0% 97.0%
Erection ‐ Duct Works & Pipes with bends and flanges ‐ Group 2615 / 2616 45.1 17.6% 1‐Jan‐2023 5‐Jan‐2023 100.0% 98.5%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 2770 / 2780 / 2782 / 2785 15.1 5.9% 1‐Jan‐2023 30‐Mar‐2023 100.0% 83.7%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 3905 8.4 3.3% 1‐Jan‐2023 19‐Jan‐2023 100.0% 47.6%
Erection ‐ Duct Work, Pipes & Hoods ‐ Group 4550 20.9 8.1% 30‐Mar‐2023 18‐Apr‐2023 100.0% 97.7%
Erection ‐ Duct Work & Pipes ‐ Group 4910 / 4920 / 4946 / 4970 / 4975 78.0 30.4% 1‐Jan‐2023 17‐May‐2023 100.0% 77.9%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 5910 / 5917 / 5920 37.5 14.6% 11‐Jan‐2023 12‐Mar‐2023 100.0% 84.6%
Erection ‐ Pipe ducts with bends and flanges ‐ Group 7112 / 7131 1.5 0.6% 4‐Mar‐2023 9‐Apr‐2023 100.0% 48.0%
Erection ‐ Dryer Duct (From Dryer to High Efficiency Cyclone) ‐ Group 2420 38.8 100.0% 2‐Mar‐2023 12‐Mar‐2023 100.0% 99.9%
Erection ‐ Crude gas duct ‐ Group 7410 31.4 100.0% 10‐Apr‐2023 29‐Apr‐2023 100.0% 79.3%
Erection ‐ Duct work from combustion air fan to the burner ‐ Group 7370.061 2.2 3.3% 28‐Mar‐2023 30‐Mar‐2023 100.0% 81.0%
Erection ‐ Duct work from cooling air fan to the burner ‐ Group 7370.062 1.3 1.9% 11‐Apr‐2023 15‐Apr‐2023 100.0%
Fab.‐ Air Grader (new scope) 9.9 15.0% 15‐Apr‐2023 20‐Apr‐2023 100.0% 65.0%
Erection ‐ Transport pipes ducts for dust ‐ Group 7370 1.8 2.8% 27‐Mar‐2023 30‐Mar‐2023 100.0%
Erection ‐ Duct work from ambient air fan to quench chamber ‐ Group 7385.060 0.3 0.4% 9‐Apr‐2023 10‐Apr‐2023 100.0% 100.0%
Erection ‐ Duct work from ambient air fan to mixing chamber ‐ Group 7385.065 0.8 1.3% 9‐Jan‐2023 9‐Jan‐2023 100.0% 50.0%
Erection ‐ Duct work from mixing chamber to cyclones ‐ Group 7385.065 0.8 1.3% 9‐Jan‐2023 9‐Jan‐2023 100.0% 50.0%
Erection ‐ Duct work from thermal oil heater to mixing chamber ‐ Group 7385.065 0.8 1.3% 11‐Feb‐2023 11‐Feb‐2023 100.0% 50.0%
Erection ‐ Duct work from dust collector (Cyclones) to Ash Crews ‐ Group 7385.080 10.5 15.9% 6‐Apr‐2022 14‐Apr‐2022 100.0% 100.0%
Erection ‐ Duct work from dust collector (Cyclones) to Main ID fan ‐ Group 7385.080 10.5 15.9% 28‐Mar‐2023 4‐Apr‐2023 100.0% 75.0%
Erection ‐ Duct work from the Main ID fan to Dryer Mixing Chamber ‐ Group 7385.090 5.7 8.6% 7‐Jan‐2023 10‐Jan‐2023 100.0% 95.0%
Erection ‐ Duct work from the main id fan to start up stack ‐ Group 7385.090 5.7 8.6% 9‐Jan‐2023 10‐Jan‐2023 100.0% 95.0%
Erection ‐ Duct work from thermal oil heater fan to mixing chamber ‐ Group 7390 7.7 11.8% 1‐Apr‐2023 9‐Apr‐2023 100.0% 60.0%
Erection ‐ Duct work from thermal oil heater to thermal oil heater fan ‐ Group 7390 7.7 11.8% 3‐Apr‐2023 11‐Apr‐2023 100.0% 60.0%
Chutes ‐ Supports ‐ Silencer ‐ Doors & loose items 58.9 13.1% 1‐Jan‐2023 30‐Apr‐2023 100.0% 54.7%
Fab.‐ Chutes, Doors & loose items ‐ Group 2300 36.3 61.6% 1‐Jan‐2023 30‐Apr‐2023 100.0% 42.4%
Fab.‐ Pneumatic Supports ‐ Group 2600 16.9 28.6% 1‐Jan‐2023 30‐Apr‐2023 100.0% 100.0%
Page 28 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Test Package
Approved Sub-
System
P&ID’s Systems
Total Done Remain
Electrical 15 15 108 -
17 83 334 67 277
Process 34
0 of 17 53 N/A
Miscellaneous
(Civil/ Road / 6 6 39 -
Steel
Page 29 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Man-hours
Manpower Av. No.
This WK.
Indirect Manpower:
Project MGR. 1 60
Construction MGR. 4 240
Project Control & planning MGR. 1 60
Maintenance MGR. 1 60
Technical Office Manager 1 60
Civil Technical office Engineer 3 180
Mechanical Technical office Engineer 5 300
E&I Technical office Engineer 3 180
Civil Construction Engineer 5 300
Mechanical Construction Engineer 14 840
E&I Construction Engineer 12 720
HSE Engineer & Specialist 5 300
Planning Engineer 3 180
DCC 2 120
Material Control Engineer 2 120
QC / QA Manager (Civil) 1 60
QC / QA Manager (Mechanical) 1 60
Mechanical QC Engineer 6 360
Civil QC Engineer 4 240
E&I QC Engineer 2 120
Painting Engineer 2 120
Hydrotest Engineer 1 60
Pre-commissioning & Commissioning Engineer 8 480
NDT Technician 10 600
Material Control Technician 3 180
Hydrotest Technician 17 1,020
Civil NDT Technician 4 240
Page 30 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Surveyor 11 660
Nurse 2 120
Administrator 3 180
HR 5 300
Warehouse man 1 60
HSE Officer 26 1,560
Doctor 1 60
Security 24 1,440
Unskilled Labor 70 4,200
Direct Manpower:
Civil Forman 10 600
Fitter Forman 11 660
Welder Forman 2 120
E&I Forman 9 540
Rigger Forman 2 120
Scaffolding Forman 2 120
Carpenter 16 960
Steel Fixer 11 660
Plumber 11 660
Plasterer 7 420
Concrete Shaper 13 780
Steel Fitter 33 1,980
Rotating Equip. Fitter 12 720
Piping Fitter 17 1,020
Steel Welder 26 1,560
Argon Welder 13 780
Grinder 94 5,640
Rigger 135 8,100
Sandblaster & Painter 12 720
Scaffolding Labor 60 3,600
E&I Steel Fitter 11 660
Electrical Technician 34 2,040
Electrician Helper 36 2,160
Maintenance Labors & Drivers 96 5,760
Crane Operator 27 1,620
TCF Crew 10 600
Page 31 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
7.2 Equipment: -
Equipment NO.
Crane 500 ton 1
Crane 100 ton 1
Crane 90 ton 1
Crane 70 ton 3
Crane 50 ton 13
Crane 35 ton 1
Forklift 7
Boom Man lift 22
Excavator 2
Tractor 2
Compactor 2
Grader 1
Loader 4
Dump Truck 5
Bobcat 2
Air Compressor 3
Generator 9
Lighting Unit 12
Welding Machine (Set) 54
Water Mobile Tank 5
Diesel truck 4
Dewatering Pump 14
Trailer 4
Page 32 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
8. Areas of concern
8.1 Shipments of the Production line Equipment have been arrived of (31)
[ Siemmpelkamp Scope of work], remain the spare parts & commissioning
shipments.
8.2 Level-2 & 3 Revised Schedule (Rev.6) has been submitted for WOTECH
approval 11/02/2023.
8.3 The price increasing for the material supply of the suppliers is still under
negotiating with WOTECH.
8.4 The issuing of the letter of credit (LC) has a negative impact on the external
purchasing (imported material) and hence the project schedule such as :
Emergency Diesel Generator (PO # 148), alternative PO for PICO vendor is
under issuing.
Instrument J.B (PO # 45).
Remaining Rails – 45 Ton (PO # 6444).
Portable Monitors (PO # 513).
Page 33 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Page 34 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
10. Photos
Page 35 of 234
Page 36 of 234
MDF Production Line
Page 37 of 234
Mat-former Area
Page 38 of 234 (Plot 1)
Mat-former Bunker (Plot 1)
Page 39 of 234
Pre-Press Area (Plot 1)
Page 40 of 234
Press & Page
ContiRoll
41 of 234 (Plot 1)
Out Feed Drum for Press & Page
Press Fumes Pipes G.4550 (Plot 1)
42 of 234
Cooling Turner Area (Plot 1)
Page 43 of 234
Sanding & Cutting
Page 44 of Lines
234 G.5400 (Plot 1)
Sanding & Cutting Lines G.5400 (Plot 1)
Page 45 of 234
Sanding Machines (Plot 1)
Page 46 of 234
Extraction System forPageSanding
47 of 234 Machines (Plot 1)
Packing Line G.5700 (Plot 1)
Page 48 of 234
Stacking Area & Rails Installation
Page 49 of 234for Carriage System (Plot 1)
Final Separator
Sedimentation Tank
Fume Extraction Fan
Page 63 of 234
Straw De-stringing Page
& Chopping
64 of 234 Lines (Plot 6)
Overhead Crane Installation (Plot 6)
Page 65 of 234
Dryer Fan & Mixing
Page 66 of Chamber
234 (Plot 7)
Thermal Oil System &PageSteam
67 of 234 Generation (Plot 7)
Thermal Oil Pump room (Plot 7)
Page 68 of 234
PMDI Tanks & Warehouse
Page 69 of 234
Str. (Plots 4 & 7 )
Industrial Tanks Area & Pump Shed (OSBL)
Page 70 of 234
Fire Water Page
Tank Area (OSBL)
71 of 234
Cable Trays
Page 72 installation
of 234
Page 73 of 234
Cable Trays installation
Panels & Switch Gears installation
Page 74 of 234
HSE Building & Truck Shed (OSBL)
Page 75 of 234
MDF Main Gate
Page 76 of 234
MDF Mosque Finishing Works
Page 77 of 234
Chemical Pit Concrete
Page 78 of 234 Works (Plot 2)
Car Parking Shed & TCF Building (OSBL)
Page 79 of 234
Water Treatment Shed (OSBL)
Page 80 of 234
Compressors
Page 81 Shed
of 234 (OSBL)
Trench's Covers Installation Page 82 of 234
Interlock Works for Roads
HDPE Piping Installation
Page 83 of 234
HDPE Piping Installation
Page 84 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Attachment #1
Skyline
Page 85 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Pipes, Fitting, Flanges, Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ
10 Gasket, Bolts (HDPE) - Piping 510/NGE/2022 Local PO Plan Stock 26-06-22 397/NGE/2022
ﺍﻟﻤﻮﺍﺳﻴﺮ
Balance
Act 06-06-22 Page 13-06-22
09-06-22 86 of 234 19-06-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
Pipes Fitting Flanges
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Pipes, Fitting, Flanges, Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ
12 Gasket, Bolts (HDPE) - Piping 956/NGE/2022 Local PO Plan (2) month from PO 23-12-22 816/NGE/2022
ﺍﻟﻤﻮﺍﺳﻴﺮ
Balance
Act 02-10-22 09-10-22 16-10-22 23-10-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
*Piping Bulk Material (CS) - ( ﺇﺳﺒﻮﻉ ﻣﻦ ﺇﺻﺪﺍﺭ8 : 4) ﻣﻦ
13 Piping 436/NGE/2022 Local PO Plan 07-07-22 11-09-22 527/NGE/2022 ﻣﻴﺠﺎ ﻟﻠﺘﺠﺎﺭﺓ
Balance ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ
ETA (Expected to arrive) 15-01-23
Act 15-05-22 22-05-22 27-06-22 07-07-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
*Piping Bulk Material (CS) - 441- CHERO PIPING
14 Piping Local PO Plan ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪFOB ( ﺇﺳﺒﻮﻉ6) 07-09-22 334/411-22/AHN/2022
Balance 22/AHN/2022 S.P.A
Act 15-05-22 22-05-22 21-06-22 28-06-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
552- ﻣﻦ ﺃﻣﺮFOB ( ﺇﺳﺒﻮﻉ16) : (7) ﻣﻦ 2022 / 12 / 1 ﻣﻦ CHERO PIPING
15 *Piping Bulk Material Piping External PO Plan 492/552-22/AHN/2022
22/AHN/2022 ( ﺇﺳﺒﻮﻉ ﺃﺟﺎﺯﺓ ﻛﺮﻳﺴﻤﺎﺱ2) + ﺍﻟﺘﻮﺭﻳﺪ 2023 / 2 / 15 ﺇﻟﻰ S.P.A
555-
External PO Plan 21-11-22
( ﺇﺳﺒﻮﻉ ﻣﻦ ﻓﺘﺢ ﺍﻹﻋﺘﻤﺎﺩ ﺍﻟﻤﺴﺘﻨﺪﻯ4)
16 *Piping Bulk Material Piping 493/555-22/AHN/2022 Gates FZE
22/AHN/2022
ETA (Expected to arrive) 07-03-23
Act 15-09-22 17-09-22 19-09-22 21-09-22 Partial Delivery (8%)
80-
External PO Plan 05-04-23
Page 87 of 234 Delivery Along With PO 34
19 *Piping Bulk Material Piping 77/80-23/AHN/2023 Gates FZE
23/AHN/2023
ETA (Expected to arrive) 07-03-22
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Page 89 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Page 91 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Page 92 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Page 95 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
607/153-
Potable water pump (4ea.) Flowserve
103 Pumps (25 ea.) Package 153/OMG/2021 External PO Plan (19 Wk) FOB from P.O&DWG.
01-06-22 21/OMG/2021
Page 98 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Page 99 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23
Completed 1629/2021
21 TK Mech 13394/2021 Act Completed 17-11-21 30-11-21 02-12-21 1630/2021
1631/2021
Plan 28-09-21 22-11-21 28-11-21 02-12-21 (3) Months 01-03-22
Container for Sludge and Solids - Group 4572 Forecast (1) Week 25-10-21
22 Mech 12953
(IBC -1000 lt)
Others Act 05-07-21 18-09-21 31-10-21 18-10-21 Completed 10452/2021
Electrical secured accesses door and flaps - Plan 20-02-22 20-03-22 27-03-22 03-04-22 (2) Months 01-06-22 rem.
32 Civil
GR-4599 Others Act Completed Completed Completed 23-01-23
Plan 10-10-21 24-11-21 02-12-21 12-12-21 (1.5) Month 27-01-22
33 Rails Mech 14704
Others Act 10-10-21 02-12-21 Completed Completed Partially 6444/22
Plan 09-12-21 30-12-21 09-01-22 16-01-22 (1) Month 15-02-22
34 Grating Mech 1562/22
ST Act 18-11-21 18-11-21 Completed Completed Partially 1561/22
Final MDF WH, Matforming, (Plot -1) Substation Building Roads / Paving
Cooling & Stacking
Press & Contiroll@ Sump Scale With Room Potable Water Network
Dryer & Sifting (Plot-2) HSE Building Fire Fighting Network (HDBE)
Refining Area (Plot-4) Main Security Building U/G Works - OSBL Storm Network
Straw Cleanning Area (Plot-5) Security Building Electrical Network (Concrete Trench)
Not Started
Catch Basin & Trench Covers
In Progress
Page 104 of 234 Completed
SKYLINE (ELECTRICAL WORKS)
Lighting
Cable Trays Pulling Power Pulling Lighting
Cable Trays Panels Erection Termination Poles / Fixtures Earthing F&G HVAC
Supports Cable Cable
Erection
HSE-Control
Plot-1 ISBL ISBL DC UPS ISBL-Equipment ISBL ISBL ISBL
Building
Substation
Plot-6 OSBL OSBL AC UPS OSBL-Equipment OSBL OSBL OSBL
Building
Emergency
Local Pannels Scale Room
Generator
Main Security
DCS
Room
Production
Building
Switch Room
SR01B
Switch Room
SR02B
Switch Room
SR02C
Switch Room
SR022
Refining SR02A
Straw Building
SR01A
Not Started
In Progress Glue Storage Tank
Completed Building
Page 105 of 234
SKYLINE (INSTRUMENTATION WORKS)
Not Started
In Progress
Completed
ISBL OSBL
IP-Telephone IP-Telephone
Not Started
In Progress
Completed
Production Line (Plot-1) Production Line (Plot-1) ISBL-(Plot-1) Champers Industrial Raw Water Tank (101) Industrial Raw Water Tank (101)
Production Line (Plot-2) Production Line (Plot-2) ISBL-(Plot-2) Cyclones DEMI Water Tank (103) DEMI Water Tank (103)
Production Line (Plot-3) Production Line (Plot-3) ISBL-(Plot-3) Silos Process Water Tank (102) Process Water Tank (102)
Production Line (Plot-4) Production Line (Plot-4) ISBL-(Plot-4) Stacks Potable Water Tank
Filters GENERATOR SHED Filters Loading Arm for PMDI OSBL Air Compressor
DN CS-ISBL DN CS-ISBL
SK-PKG's
Second Reheating
WESP
Not Started
In Progress
Completed Page 109 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023
Attachment #1
Detailed Progress
A7750 PR P&ID's - Potable Water System MDF-PTJ-PR-PID-0008 Potable Water System PID 152 20% 31-Jan-21 17-Mar-21 27-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A84500 PR Sewage Treatment Package Process Datasheet MDF-PTJ-PR-DAT-0008 Sewage Treatment Package Process Datasheet 102 13% 01-Apr-21 11-Apr-21 21-Apr-21 28-Apr-21 05-May-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PI PW GENERAL ARRANGEMENT MDF-PTJ-PI-LAY-0004 PW GENERAL ARRANGEMENT 160 21% 13-Nov-21 20-Nov-21 28-Nov-21 05-Dec-21 13-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI POTABLE WATER SYSTEM ISOMETRIC DRAWING MDF-PTJ-PI-ISO-0002 POTABLE WATER SYSTEM ISOMETRIC DRAWING 180 24% 20-Oct-21 27-Oct-21 04-Nov-21 11-Nov-21 19-Nov-21 26-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
Compressed Air System 984 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8210 PR PFD - Compressed Air System MDF-PTJ-PR-PFD-0004 Compressed Air System PFD 228 23% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A8220 PR P&ID's - Compressed Air System MDF-PTJ-PR-PID-0004 Compressed Air System PID 190 19% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8222 PI Piping G.A - Compressed Air System MDF-PTJ-PI-LAY-0005 Compressed Air GENERAL ARRANGEMENT 188 19% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0002 AIR COMPRESSOR Package SPECIFICATION 144 60% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Boiling & Fresh Water System 801 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8150 PR PFD - Boiling & Fresh Water System MDF-PTJ-PR-PFD-0003 Boiling & Fresh Water System PFD 285 36% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A8160 PR P&ID's - Boiling & Fresh Water System MDF-PTJ-PR-PID-0003 Boiling & Fresh Water System PID 190 24% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8162 PI Piping G.A - Boiling & Fresh Water System MDF-PTJ-PI-LAY-0006 Boiling & Fresh Water GENERAL ARRANGEMENT 188 23% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8163 PI Isometric Drawings - Boiling & Fresh Water System MDF-PTJ-PI-ISO-0003 Boiling and Fresh Water System Isometric Drawing 138 17% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Fuel Gas System 801 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8270 PR PFD - Fuel Gas System MDF-PTJ-PR-PFD-0005 Fuel Gas System PFD 285 36% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A8280 PR P&ID's - Fuel Gas System MDF-PTJ-PR-PID-0005 Fuel Gas System PID 190 24% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8282 PI Piping G.A - Fuel Gas System MDF-PTJ-PI-LAY-0007 Fuel GaS GENERAL ARRANGEMENT 188 23% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8283 PI Isometric Drawings - Fuel Gas System MDF-PTJ-PI-ISO-0005 Fuel Gas System ISOMETRIC DRAWING 138 17% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Industrial Water System 1,183 1% 100% 100% 100% 100% 100% 100% 100% 100%
A8090 PR PFD - Industrial Water System MDF-PTJ-PR-PFD-0002 Industrial Water System PFD 285 24% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A8100 PR P&ID's - Industrial Water System MDF-PTJ-PR-PID-0002 Industrial Water System PID 380 32% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8101 PI Piping G.A - Industrial Water System MDF-PTJ-PI-LAY-0008 Industrial Water GENERAL ARRANGEMENT 188 16% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8102 PI Isometric Drawings - Industrial Water System MDF-PTJ-PI-ISO-0001 Industrial Feed Water System Isometric Drawing 138 12% 23-Feb-21 16-May-21 26-May-21 02-Jun-21 09-Jun-21 14-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A8105 PR Data Sheets for Industrial Water package MDF-PTJ-PR-DAT-0005 Data Sheets for Industrial Water package 192 16% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Waste Water & Chemical System 2,069 1% 100% 100% 100% 100% 100% 100% 100% 100%
A8330 PR PFD - Waste Water & Chemical System MDF-PTJ-PR-PFD-0006 Waste Water and chemical System PFD 285 14% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A8340 PR P&ID's - Waste Water & Chemical System MDF-PTJ-PR-PID-0006 Waste Water System PID 228 11% 14-Oct-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8342 PI Piping G.A - Waste Water & Chemical System MDF-PTJ-PI-LAY-0009 Waste Water and chemical GENERAL ARRANGEMENT 752 36% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8343 PI Isometric Drawings - Waste Water & Chemical System MDF-PTJ-PI-ISO-0006 Waste Water and chemical System Isometric Drawing 276 13% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8345 PR Data Sheets for Waste Water and chemical System MDF-PTJ-PR-DAT-0006 Data Sheets for Waste Water and chemical System 288 14% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
PR Chemical Injection Package Process Datasheet MDF-PTJ-PR-DAT-0002 Chemical Injection Package Process Datasheet 240 12% 11-Dec-21 21-Dec-21 31-Dec-21 07-Jan-22 14-Jan-22 24-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
Chemical System 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
A8390 PFD - Chemical System Bulk Chemicals Storage & Handling PFD 0 100% 100% 100% 100% 100% 100% 100% 100%
A8400 P&ID's - Chemical System Chemical System PID 0 100% 100% 100% 100% 100% 100% 100% 100%
A8402 Piping G.A - Chemical System Chemical GENERAL ARRANGEMENT 0 100% 100% 100% 100% 100% 100% 100% 100%
A8403 Isometric Drawings - Chemical System Chemical System ISOMETRIC DRAWING 0 100% 100% 100% 100% 100% 100% 100% 100%
A8405 Data Sheets for Chemical System 0
Spark System 252 0% 100% 100% 100% 100% 100% 100% 100% 100%
PI SPARK SYSTEM-PIPING GENERAL ARRANGEMENT MDF-PTJ-PI-DWG-0001 SPARK SYSTEM-PIPING GENERAL ARRANGEMENT 252 100% 16-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 111 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Process 3,407 1% 100% 100% 100% 100% 100% 100% 100% 100%
A16010 Process -BFD for entire Plant 293 9% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-DIA-0001 Block Flow Diagram for entire Plant 293 100% 03-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Process -Philosophy (Effluent and Drianage - Isolation - line
A16020 1,152 34% 100% 100% 100% 100% 100% 100% 100% 100%
sizing - Design Temp)
PR MDF-PTJ-PR-RPT-0003 Effluent and Drianage PHILOSOPHY 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0004 Isolation Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0005 Line Sizing Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0006 Design Temprature and Pressure Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-MSR-0001 MATERIALS SELECTION PHILOSOPHY REPORT 42 4% 24-Mar-21 31-Mar-21 30-Apr-21 05-May-21 07-May-21 12-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A16030 Process -Basis of Design 225 7% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0001 Process Basis Of Design 225 100% 09-Dec-20 08-Nov-21 08-Dec-21 13-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A16050 Equipment List 333 10% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-LST-0001 Equipment list 333 100% 22-Nov-20 27-Nov-21 07-Dec-21 14-Dec-21 21-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0007 Utilities Description 222 27% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-PRO-0001 Operating Procedures for offsite utilities 293 36% 10-Jan-22 14-Feb-22 24-Feb-22 03-Mar-22 10-Mar-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
A55931 General (Fluid List, Legand, symbols,..) 365 11% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-LST-0003 FLUID LIST 278 76% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-PID-0001 Legend and Symbols 88 24% 22-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A84290 MSG - Material Selection Guide 225 7% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-MSG-0001 MSG-Material Selection Guide 225 100% 09-Dec-20 11-Mar-21 10-Apr-21 15-Apr-21 17-Apr-21 22-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Fire & Gas 3,130 1% 100% 100% 100% 100% 100% 100% 100% 100%
FG.000 F&G & Fiber Optic Cable Specifications 3,130 100% 100% 100% 100% 100% 100% 100% 100% 100%
Gas Suppression system Calculation Report For Refining
FF MDF-PTJ-LP-RPT-0022 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building - SWITCH ROOM -SR02A
Gas Suppression system Calculation Report (SR-02B
FF MDF-PTJ-LP-RPT-0023 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building)
Gas Suppression system Calculation Report For Straw
FF MDF-PTJ-LP-RPT-0024 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Preparation Building
Gas Suppression system Calculation Report For Substation
FF MDF-PTJ-LP-RPT-0025 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building
Gas Suppression system Calculation Report For Production
FF MDF-PTJ-LP-RPT-0026 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
building
FF MDF-PTJ-LP-RPT-0027 Fire Fighting Protection Layout For Switch Room - SR01B 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-RPT-0028 Fire Fighting Protection Layout For Switch Room - SR-02C 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-RPT-0029 Fire Fighting Protection Layout For Switch Room - SR-022 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-SPC-0004 Total Flooding FM200 Gas Suppression system Spec 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-SPC-0005 Total Flooding CO2 Gas Suppression system Spec 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0030 MDF UTILITIES HAZOP REPORT 210 7% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LAY-0002 Equipment layout Drawings 435 40% 07-Dec-20 14-Dec-20 24-Dec-20 31-Dec-20 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A16080 General Arrangement 835 20% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LAY-0003 GENERAL PLOT PLAN ARRANGEMENT 435 52% 03-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LAY-0011 Chemical System Piping GA 400 48% 06-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A19380 Tie - In Schedule 204 5% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-SCH-0001 Tie-In Schedule 204 100% 07-Dec-20 14-Dec-20 24-Dec-20 31-Dec-20 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A19385 PI Line Designation Tables (LDT) MDF-PTJ-PR-LST-0002 LINE DESIGNATION TABLES (LDT) 275 7% 03-Jan-21 01-Dec-21 11-Dec-21 18-Dec-21 25-Dec-21 30-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A19390 Piping Bulk & Valves MTO (Balance) 122 3% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-MTO-0001 Piping Bulk and valves balance MTO 122 100% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Electrical 6,538 3% 100% 100% 100% 100% 100% 100% 100% 100%
A56041 Lightning protection Lay Out 93 1% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0022 Lightning Protection Layout 93 100% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0002 0.4 Low Voltage Switchgear Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0003 distribution board Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0004 AC Uninterruptable Power Supply System Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0005 DC Uninterruptable Power Supply System Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0006 Transformers Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0007 Emergency Diesel Generator Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0008 Electrical Bulk materials Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0010 22 KV Switchgear Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0011 0.4kV System-Soft Starters and VFDs_Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0012 Reactive Power Compensation-Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SPC-0013 Electric motors- specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0002 0.4 Low Voltage Switchgear Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0003 distribution board Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0004 AC Uninterruptable Power Supply System Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0005 DC Uninterruptable Power Supply System Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0006 Transformer Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DAT-0007 Diesel emergency generator Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
Page 113 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-DAT-0008 Reactive Power Compensation - Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0002 Main Low voltage Swichgear SLD. 480 48% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0003 Main lighing Distribution Board SLD 225 23% 19-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A7060 Lists, Calculations & Construction DWG's 2,975 46% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0001 Outdoor lighing & Power Layout 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0002 Earthing Layout 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0003 Cable Routing Layout. 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0022 Lightning protection Layout 140 5% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LST-0001 Load List 310 10% 15-Nov-21 15-Dec-21 22-Dec-21 29-Dec-21 05-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SCH-0001 Cable Schedule 260 9% 28-Nov-20 03-Dec-20 28-Dec-20 02-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SCH-0002 Cable Schedule 240 8% 19-Jan-21 24-Jan-21 18-Feb-21 23-Feb-21 20-Mar-21 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-CAL-0001 lighting Calculations 325 11% 26-Oct-20 31-Oct-20 25-Nov-20 30-Nov-20 25-Dec-20 30-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-CAL-0002 Electrical Power System Study 325 11% 01-Oct-20 06-Oct-20 20-Oct-20 25-Oct-20 01-Nov-20 06-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-CAL-0003 DC BATTERY CHARGER SIZING 325 11% 01-Oct-20 06-Oct-20 20-Oct-20 25-Oct-20 01-Nov-20 06-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0004 EARTHING SYSTEM GENERAL LAYOUT 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0027 INSTALLATION DETAILS OF FLOOD LIGHT Layout 210 7% 30-Sep-21 11-Oct-21 16-Oct-21 21-Oct-21 26-Oct-21 27-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Instrumentation (Control System) 8,288 4% 100% 100% 100% 100% 100% 100% 100% 100%
IN.000 Specifications & Data Sheets 3,850 46% 100% 100% 100% 100% 100% 100% 100% 100%
INSTRUMENTATION AND CONTROL BASIS OF
IN MDF-PTJ-IN-RPT-0001 175 5% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
DESIGN
ISBL AND OSBL AUTOMATION AND CONTROL
IN MDF-PTJ-IN-RPT-0002 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
INTERCONNECTION PHILOSOPHY
IN MDF-PTJ-IN-SPC-0007 INSTRUMENT INSTALLATION specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0008 DCS specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0009 Instruments Specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0010 Control Valve specs 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0011 Analyzer (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0012 Instrument with equipment package 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SPC-0014 Instrument cable and Cable Glandes specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0001 Instruments (Different Type) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0002 Remotely operated Valves (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0003 Analyzer (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0004 DATA SHEET FOR Mechanical level indicator 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0005 DATA SHEET FOR Flow meter 245 6% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0006 DATA SHEET FOR Control Valves "YIC-5150" 245 6% 04-Sep-21 09-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DAT-0007 PH analyzer data sheet 245 6% 05-Oct-21 09-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.010 I/O List & Index 525 6% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LST-0001 INSTRUMENT INDEX List 175 33% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 114 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
IN MDF-PTJ-IN-LST-0002 I/O LIST 175 33% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LST-0003 ALARM LIST 175 33% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.020 Loop DWG's, Cable Routing & Inst. Layout. 2,219 27% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DIA-0006 PLANT AUTOMATION SYSTEM BLOCK DIAGRAM 175 8% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DIA-0007 ICSS Functional, Loop Wiring diagram 175 8% 31-Oct-21 05-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0073 CABLE TERMINATION JUNCTION BOX 175 8% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0076 Instrument electrical hookup drawing 154 7% 16-Mar-21 21-Mar-21 15-Apr-21 20-Apr-21 15-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0077 Instrument mechanical hookup drawing 158 7% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0078 Instrument pneumatic drawing 158 7% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0079 Control room cable trays 245 11% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DWG-0080 Instrument junction Box support 154 7% 16-Mar-21 21-Mar-21 15-Apr-21 20-Apr-21 15-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LAY-0023 INSTRUMENTATION / JB LAYOUT DRAWING 217 10% 01-Nov-21 26-Nov-21 01-Dec-21 11-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LAY-0024 Instrument cable routing layout 217 10% 01-Nov-21 26-Nov-21 01-Dec-21 11-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LAY-0026 Control Rack Room Layout 217 10% 10-Apr-21 05-May-21 10-May-21 20-May-21 27-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DIA-0009 Schematic diagram for signals of motor 175 8% 13-Apr-21 18-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.040 MTO - Control Sys. (Cable Trays, cable and cable glands) 763 9% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-MTO-0006 Instruments Tube and tube fittings 294 39% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-MTO-0007 Instruments Stands 294 39% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-MTO-0009 Instrument cable trays 175 23% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-PR-SCH-0003 Cause and Effect 231 57% 27-Mar-21 01-May-21 04-May-21 09-May-21 14-May-21 19-May-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.250 MTO - Control Sys. (JB's and bulk material) 294 4% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-MTO-0008 Field Junction boxes 294 100% 22-Feb-21 08-Apr-21 15-Apr-21 20-Apr-21 27-Apr-21 02-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Telecommunications 4,368 2% 100% 100% 100% 100% 100% 100% 100% 100%
A8650 Fire Detection and Alarm System Cable Schedule & Plot Plan 320 7% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-SPC-0001 FIRE ALARM SYSTEM SPECIFICATION 220 56% 13-Nov-20 18-Nov-20 13-Dec-20 18-Dec-20 12-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8660 CCTV - Plot Plan 170 4% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0008 CCTV SYSTEM OUTDOOR PLOT PLAN 170 100% 07-Mar-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8662 CCTV Specs & Block Diagram 395 9% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-SPC-0002 CCTV SYSTEM - SPECS 220 56% 13-Nov-20 18-Nov-20 13-Dec-20 18-Dec-20 12-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0002 CCTV SYSTEM - BLOCK DIAGRAM 175 44% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A8672 Data Network Specs & Block Diagram 1,498 34% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0004 DATA NETWORK SYSTEM BLOCK DIAGRAM 175 12% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-SPC-0005 IP telephone Specs 280 19% 02-Oct-20 07-Oct-20 01-Nov-20 06-Nov-20 01-Dec-20 26-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0005 IP Telephone block Diagram 175 12% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0007 IP Telephone block Diagram 180 12% 27-Nov-21 04-Dec-21 11-Dec-21 16-Dec-21 21-Dec-21 28-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8680 Public Address - Plot Plan 170 4% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0012 PUBLIC ADDRESS SYSTEM OUTDOOR PLOT PLAN 170 100% 07-Mar-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8682 Public Address Specs & Block Diagram 395 9% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0003 PUBLIC ADDRESS SYSTEM BLOCK DIAGRAM 175 44% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-SPC-0003 PUBLIC ADDRESS SYSTEM SPECS 220 56% 21-Nov-20 26-Nov-20 21-Dec-20 26-Dec-20 20-Jan-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A8683 Telecomm. - B.O.Q & MTO 1,025 23% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0001 FIRE ALARM SYSTEM B.O.Q 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0002 CCTV SYSTEM - BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0003 PUBLIC ADDRESS SYSTEM BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0004 DATA NETWORK SYSTEM BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0005 IP Telephone MTO 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0006 CCTV SYSTEM - MTO 175 17% 26-May-21 30-Jun-21 05-Jul-21 10-Jul-21 15-Jul-21 20-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC System 570 0% 100% 100% 100% 100% 100% 100% 100% 100%
HVAC System Philosophy, Design Specifications & general
A16640 570 100% 100% 100% 100% 100% 100% 100% 100% 100%
Details
HV MDF-PTJ-HV-RPT-0001 HVAC System Philosophy 200 35% 16-Nov-20 21-Nov-20 16-Dec-20 21-Dec-20 15-Jan-21 30-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-SPC-0001 HVAC Design specifications 200 35% 16-Nov-20 21-Nov-20 16-Dec-20 21-Dec-20 15-Jan-21 30-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-SPC-0002 Fans spec's and data sheet 170 30% 26-Nov-21 31-Dec-21 05-Jan-22 10-Jan-22 15-Jan-22 20-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
Mechanical 1,705 1% 100% 100% 100% 100% 100% 100% 100% 100%
Mechanical - Data Sheets & Specifications (Valves, Pumps,
A16650 1,705 100% 100% 100% 100% 100% 100% 100% 100% 100%
...)
ME MDF-PTJ-ME-DAT-0002 Manual valves Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-DAT-0005 Strainers Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-DAT-0007 Pumps Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-DAT-0008 Safety , relief valves and rupture disk data sheet. 170 10% 26-Oct-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0006 Strainer Specification 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0008 PUMPS SPECIFICATION 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0009 Tank Roof Seal and Drain Technical Specification 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0010 Storm Water & Sewege Submersible Pump Stations 175 10% 26-Oct-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Production Line Structure (incl. MDF Storage & Lab) 81,325 34% 100% 100% 100% 100% 100% 100% 100% 100%
Architectural 7,088 9% 100% 100% 100% 100% 100% 100% 100% 100%
Arch. DWGs for Production line - Warehouse for final
ST.000 3,098 44% 100% 100% 100% 100% 100% 100% 100% 100%
Product
MDF-PTJ-AR-DWG-
AR Production Line Building- Ground floor at level 1.5m 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0108
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- First Floor Level 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0109
Page 116 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-Roof Plan 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0110
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 1 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0111
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 2 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0112
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 3 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0113
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 4 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0114
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- Section A-A 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0115
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- Section B-B 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0116
MDF-PTJ-AR-DWG-
AR Production Line Building- finish schedule 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0117
MDF-PTJ-AR-DWG-
AR Production Line Building- Doors & Windows Schedule 218 7% 27-Sep-21 11-Nov-21 26-Nov-21 11-Dec-21 16-Dec-21 31-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0118
MDF-PTJ-AR-DWG- Production Line Building- Plumbing Works-water drainage
AR 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0119 system
MDF-PTJ-AR-DWG- Production Line Building-Plumbing Works-water supply
AR 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0120 system
Complete architect plans for the building (As per Attach. 2.-
ST.001 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Pos 4)
ST.006 Arch. DWGs for Straw Prep. Building 1,890 27% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- Ground floor 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0180
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- WINDOW PLAN LEVEL 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0181
MDF-PTJ-AR-DWG-
AR Strew Preperation Building-Roof Plan 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0182
MDF-PTJ-AR-DWG-
AR Strew Preperation Building-North Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0183
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- East Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0184
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- West Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0185
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- South Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0186
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- Section A-A 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0187
MDF-PTJ-AR-DWG-
AR Strew Preperation Building finish schedule 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0189
ST.007 Arch. DWGs for Refiner Building 2,100 30% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Refining Building- Ground floor at level 1.5m 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0193
MDF-PTJ-AR-DWG-
AR Refining Building-Roof Plan 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0195
MDF-PTJ-AR-DWG-
AR Refining Building-North Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0196
MDF-PTJ-AR-DWG-
AR Refining Building- East Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0197
MDF-PTJ-AR-DWG-
AR Refining Building- West Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0198
MDF-PTJ-AR-DWG-
AR Refining Building- South Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0199
MDF-PTJ-AR-DWG-
AR Refining Building- Section A-A 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0200
MDF-PTJ-AR-DWG-
AR Refining Building- Doors & Windows and finish schedule 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0202
Steel Structure 46,747 57% 100% 100% 100% 100% 100% 100% 100% 100%
ST.005 Steel Structure - Warehouse for Final Product (Plot-1) 2,103 4% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-SPC-0001 Structural design criteria 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0300 General notes 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0301 General details 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0003 WAREHOUSE FOR FINAL PRODUCT- Calculation Note 480 23% 24-Aug-20 04-Sep-20 09-Sep-20 14-Sep-20 16-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0202 PIPE BRIDGE STEEL STRUCTURE - Isometric View 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0224 Gripper Carriage Steel Frame - Layout Plan 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0225 Gripper Carriage Steel Frame - Connection Details 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0081 Platform 5 inside Production Warehouse - Calculation 480 3% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0076 Steel Structure - HIT BUMPERS - Calculation 380 2% 23-May-21 02-Jul-21 09-Jul-21 14-Jul-21 16-Jul-21 21-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.015 Steel Structure - Straw Preparation (Plot-6) 1,638 4% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0009 STRAW PREPARATION - Calculation Note 390 24% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0051 STRAW PREPARATION - Base Plate (PLAN/SECTIONS) 195 12% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0096 Saw Dust Silo 7130 Steel Platform 1 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0097 Saw Dust Silo 7130 Steel Platform 2 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0098 Saw Dust Silo 7130 Steel Platform 3 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0020 Service Platform fot TKF 1398 Cal 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0100 Service Platform fot TKF 1398 -1 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0117 Steel Structure for Conveyor 1557 - Layout For Base Plate 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0118 Steel Structure for Conveyor 1557 - Layout 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0119 Steel Structure for Conveyor 1557 - Details 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0024 Steel Structures for Refinary Conveyor 1394 Calculations 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0121 Steel Structures for Refinary Conveyor 1394 Base Plate Plan 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0122 Steel Structures for Refinary Conveyor 1394 3D View 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0135 Steel Structure for Refinary Conveyor -1 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0136 Steel Structure for Refinary Conveyor -2 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0137 Steel Structure for Refinary Conveyor -3 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0030 Pipe Rack For Refinary Piping Towards Start up Cyclones Cal 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0148 Pipe Rack For Refinary Piping Towards Start up Cyclones-1 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0149 Pipe Rack For Refinary Piping Towards Start up Cyclones-2 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0150 Pipe Rack For Refinary Piping Towards Start up Cyclones-3 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0304 PIPE RACK FROM PLOT 4 TO PLOT 5 - Base Plate Plan 80 2% 17-Apr-21 22-Apr-21 17-Apr-21 22-Apr-21 24-Apr-21 29-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0074 Dryer Mixing Champer - Base Plate Plan 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0075 Dryer Mixing Champer - Isometric View 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0076 Dryer Mixing Champer - Detail 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0016 GLUE STORAGE SHED - Calculations 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0080 GLUE STORAGE SHED - Base Plate Plan 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0081 GLUE STORAGE SHED - Plans & Elevations 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0082 GLUE STORAGE SHED - Details 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0026 Steel Structure for PUMP ROOM WAREHOUSE Calculation 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Pipe Rack For Fuel GAS (2.20*28.0*8.0) Base Plate Plan &
ST MDF-PTJ-ST-DWG-0315 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Steel Plans Layout
Pipe Rack For Fuel GAS (2.20*28.0*8.0) Elevation, Side
ST MDF-PTJ-ST-DWG-0316 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
View & Connection Details
Pipe Rack For Compressed Air (2.20*20.0*8.0) Base Plate
ST MDF-PTJ-ST-DWG-0317 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan & Steel Plans Layout
Pipe Rack For Compressed Air (2.20*20.0*8.0) Connection
ST MDF-PTJ-ST-DWG-0318 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
Pipe Rack For Fuel GAS,FF,Compressed Air & Firefighting
ST MDF-PTJ-ST-DWG-0319 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate Plan & Steel Plans Layout
Page 122 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Pipe Rack For Fuel GAS,FF,Compressed Air & Firefighting
ST MDF-PTJ-ST-DWG-0320 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Connection Details
STEEL SUPPORTS FOR HEATING PUMP ROOM - Base
ST MDF-PTJ-ST-DWG-0313 130 5% 08-Jul-21 13-Jul-21 18-Jul-21 23-Jul-21 28-Jul-21 02-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Layout
STEEL SUPPORTS FOR HEATING PUMP ROOM - Steel
ST MDF-PTJ-ST-DWG-0314 130 5% 08-Jul-21 13-Jul-21 18-Jul-21 23-Jul-21 28-Jul-21 02-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans & Elevations
ST.370 Steel Structure - Dryer & Sifting Process (Plot-2) 9,600 21% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0033 PLATFORM FOR CYCLONE 4910 Calculations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0256 PLATFORM FOR CYCLONE 4910 Base Plate Plan 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0257 PLATFORM FOR CYCLONE 4910 Elevation for Align . F 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0258 PLATFORM FOR CYCLONE 4910 Connection and Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0034 SUPPROTING BELT 2592 G.2052 Calculations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0170 SUPPROTING BELT 2592 G.2052 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0171 SUPPROTING BELT 2592 G.2052 Plans & Elevations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0172 SUPPROTING BELT 2592 G.2052 Connection Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0049 Platform for Penumatic 4976 Cal 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0250 Platform for Penumatic 4976 - Plan At Elev 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0251 Platform for Penumatic 4976 - Plans & Elevations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0252 Platform for Penumatic 4976 - Connection Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0037 Steel Platform Above fans Sifter - G.2061 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0190 Bridge 1 to Penumatic 2615 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0191 Bridge 1 to Penumatic 2615 - Layout Plans& Elevations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0192 Bridge 1 to Penumatic 2615 - Details Of Connections 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0035 Service Platform 2591 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0174 Service Platform 2591 - ISOMETRIC VIEW 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0175 Service Platform 2591 - Plans& Elevations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0176 Service Platform 2591 - Connection Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0050 Dryer & Sifting Tower 2051 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0164 Dryer & Sifting Tower 2051 - Base Plate Plan 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0165 Dryer & Sifting Tower 2051 - 3D Model 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 123 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0166 Dryer & Sifting Tower 2051 - Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0032 Dryer Tower 64m Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0158 Dryer Tower 64m - Base Plate Plan 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0159 Dryer Tower 64m - 3D Model 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0160 Dryer Tower 64m - Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0056 Service Platform for Conveyor 2781 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0057 Steel Pipe Rack to Dryer Mixing Champer Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0167 Steel Pipe Rack to Dryer Mixing Champer - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0168 Steel Pipe Rack to Dryer Mixing Champer - Plan & Elevation 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0244 Steel Silo 7120 Steel Platform - GENERAL LAYOUT 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0059 Steel Pipe Rack For Penumatic 4946 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0265 Steel Pipe Rack For Penumatic 4946 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0266 Steel Pipe Rack For Penumatic 4946 - Plan at Elev 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0267 Steel Pipe Rack For Penumatic 4946 - Connection Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0060 STEEL STR FOR FILTER 4911 AND 4947 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
STEEL STR FOR FILTER 4911 AND 4947 BASE PLATE
ST MDF-PTJ-ST-DWG-0271 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN & DETAILS
STEEL STR FOR FILTER 4911 AND 4947 Plans &
ST MDF-PTJ-ST-DWG-0272 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevation
STEEL STR FOR FILTER 4911 AND 4947 - Connection
ST MDF-PTJ-ST-DWG-0273 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0061 Pipe Rack For Crude Gas Duct SENA11 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0283 Pipe Rack For Crude Gas Duct SENA11 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0240 SILO-7110 GENERAL LAYOUT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0241 SILO-7110 ANNULAR PLATE ARRANGEMENT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0242 SILO-7110 HANDRAIL DETAILS 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0048 SILO-7140 - Calculation Note 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0245 SILO-7140 - GENERAL LAYOUT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
SILO-7140 - Annular Plate, Bottom Arrangement, Shell
ST MDF-PTJ-ST-DWG-0246 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Arrangement, Roof Arrangement
Page 124 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0247 SILO-7140 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0051 Steel Drawing Filter SFDT 05/12 - D-01 Calculation 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0262 Steel Drawing Filter SFDT 05/12 - D-01 base Plate Plan 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0263 Steel Drawing Filter SFDT 05/12 - D-01 Plans& Elevation 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0264 Steel Drawing Filter SFDT 05/12 - D-01 Details 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0053 PIPE BRIDGE STEEL STRUCTURE 2782 Calculations 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0277 Steel Platform For Penumatic 2785 - Base Plate Plan 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0278 Steel Platform For Penumatic 2785 - Plans& Elevations 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0279 Steel Platform For Penumatic 2785 - Details Of Connections 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0054 WAREHOUSE PAVING PLAN AND DETAILS 520 5% 12-Feb-21 15-Feb-21 20-Feb-21 23-Feb-21 28-Feb-21 05-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0037 PRODUCTION Line Piles layout 750 8% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0038 PILE LAYOUT DRWAING FOR GROUP 4021 390 4% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0039 FOUNDATION PLAN FORMWORK FOR GROUP 4021 260 3% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0006 Straw preparation Platform 1 Piles layout (IF NEEDED) 520 23% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0069 Straw preparation Platform 1 Foundation Plan & Details 520 23% 25-Feb-21 08-Mar-21 09-Mar-21 12-Mar-21 14-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0007 Straw preparation Platform 2 Piles layout (IF NEEDED) 260 12% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0070 Straw preparation Platform 2 Foundation Plan & Details 260 12% 25-Feb-21 08-Mar-21 09-Mar-21 12-Mar-21 14-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0044 Piles layout (IF NEEDED) 520 22% 31-Jan-21 11-Feb-21 12-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0107 Foundation Plan & Details 520 22% 14-Feb-21 25-Feb-21 26-Feb-21 01-Mar-21 03-Mar-21 04-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0121 Piles & Foundation - Foundation Reinforcement 540 22% 29-Nov-21 02-Dec-21 07-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.300 Civil (Piles & FND's ) - Storage Bin (Plot-4) 1,281 6% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0033 Plot 4 - Group- 1051 - 1052 - 2031 - 3031 calculation sheet 78 6% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0016 Plot 4 - Group- 1051 - 1052 - 2031 - 3031 layout 520 41% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Plot 4 - Group- 1051 - 1052 - 2031 - 3031 Foundation Form
CI MDF-PTJ-CI-DWG-0079 520 41% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Work
Structural Works for Storage Bin Platfrom 1Foundation
CI MDF-PTJ-CI-DWG-0080 163 13% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
REINFORCEMENTPlan & Details
ST.310 Civil (Piles & FND's ) - Dryer & Blending (Plot-7) 1,638 8% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0042 Foundation calculation sheet 78 5% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0025 PLOT 7 - Piles layout and Coordinates 520 32% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0088 PLOT 7 - GROUP 3031 Foundation Form Work 520 32% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0043 Foundation calculation sheet 78 5% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0026 Piles layout (IF NEEDED) 520 32% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0089 Foundation Plan & Details 520 32% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAY-0038 Piles layout (IF NEEDED) 520 41% 17-Jan-21 28-Jan-21 29-Jan-21 01-Feb-21 03-Feb-21 04-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0101 Foundation Plan & Details 520 41% 31-Jan-21 11-Feb-21 12-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0102 Foundation REINFORCEMENT PLAN AND DETAILS 163 13% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Electrical 4,730 6% 100% 100% 100% 100% 100% 100% 100% 100%
ST.120 Electrical - Prod. Line 4,730 100% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0023 Lighting and Power Layout Plan PL Building 160 3% 05-Dec-21 14-Jan-22 15-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0023 Earthing Layout PL 160 3% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0036 Electerical Distrebution Diagram PL 160 3% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0037 Emergency Distribution board SLD PL Building 160 3% 05-Dec-21 14-Jan-22 15-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR03)
EL MDF-PTJ-EL-DWG-0047 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LIGHTING LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR03)
EL MDF-PTJ-EL-DWG-0048 160 3% 26-Jul-21 09-Aug-21 20-Aug-21 03-Sep-21 15-Sep-21 28-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
SMALL POWER LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - GROUND FLOOR
EL MDF-PTJ-EL-DWG-0051 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(SR04) LIGHTING LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR04)
EL MDF-PTJ-EL-DWG-0052 160 3% 26-Jul-21 09-Aug-21 20-Aug-21 03-Sep-21 15-Sep-21 28-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
SMALL POWER LAYOUT PLAN
FINAL PRODUCT WAREHOUSE(SR03) S.L.D
EL MDF-PTJ-EL-SLD-0045 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(9998MC07)
FINAL PRODUCT WAREHOUSE(SR04) S.L.D
EL MDF-PTJ-EL-SLD-0046 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(9998MC08)
EL MDF-PTJ-EL-DWG-0049 Production Line Outdoor Lighting Layout - PLOT 2 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
NORMAL OUTDOOR LIGHTING DB - SINGLE LINE
EL MDF-PTJ-EL-SLD-0020 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM - P2-LDB
EL MDF-PTJ-EL-DWG-0053 Production Line Outdoor Lighting Layout - PLOT 3 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0054 Production Line Outdoor Lighting Layout - PLOT 4 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 127 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0022 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM PLOT 4
EL MDF-PTJ-EL-DWG-0055 Production Line Outdoor Lighting Layout - PLOT 5 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0023 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM PLOT 5
PRODUCTION LINE OUTDOOR LAYOUT PLOT-2 -
EL MDF-PTJ-EL-DWG-0056 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP-2061
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0057 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-3
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0021 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM P3-LDB
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0058 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-04
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0059 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-05
EL MDF-PTJ-EL-DWG-0060 PRODUCTION LINE OUTDOOR -LAYOUT PLOT 7 210 4% 23-Sep-21 04-Oct-21 09-Oct-21 14-Oct-21 19-Oct-21 20-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Telecommunication 1,650 2% 100% 100% 100% 100% 100% 100% 100% 100%
ST.130 Telecomm. - Prod. Line 1,650 100% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0078 Production Building & storage Fire alarm plan 165 10% 05-Nov-21 15-Dec-21 16-Dec-21 17-Dec-21 19-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0079 Production Building & storage Fire alarm cabling 165 10% 05-Nov-21 15-Dec-21 16-Dec-21 17-Dec-21 19-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0023 Production Building & storage Public adress system layout 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0066 Production Building & storage Public adress system cabling 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A8551 AR Production Area Layout MDF-PTJ-AR-LAY-0002 Production Area Layout 240 25% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 01-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
A8552 AR General Specification for Buildings MDF-PTJ-AR-SPC-0001 General Specification for Buildings 165 17% 18-Oct-21 01-Nov-21 15-Nov-21 29-Nov-21 13-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
AR Interlock Layout MDF-PTJ-AR-LAY-0003 Interlock Layout 255 27% 15-Sep-21 29-Sep-21 13-Oct-21 27-Oct-21 10-Nov-21 25-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
Civil 730 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8560 CI Soil Investigation Report MDF-PTJ-CI-RPT-0001 Soil Investigation Report 240 33% 08-Aug-20 26-Aug-20 31-Aug-20 05-Sep-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-LAD-0001 PORE HOLE LOCATION PLAN 250 51% 21-Jun-20 05-Jul-20 19-Jul-20 02-Aug-20 16-Aug-20 21-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
Buildings / Warehouses/ Sheds 72,828 31% 100% 100% 100% 100% 100% 100% 100% 100%
Page 128 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Buildings Specification 1,238 2% 100% 100% 100% 100% 100% 100% 100% 100%
Substation Building + (SR022-SR02C-SR02B-SR01B- Substation Building + (SR022-SR02C-SR02B-SR01B-
AR MDF-PTJ-AR-SPC-0002 180 15% 22-Oct-21 05-Nov-21 19-Nov-21 03-Dec-21 17-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
SR01A -SR02A-NEW SR) Spec SR01A -SR02A-NEW SR) Spec
AR Admin Building Spec MDF-PTJ-AR-SPC-0003 Admin Building Spec 195 16% 27-Dec-21 10-Jan-22 24-Jan-22 07-Feb-22 21-Feb-22 24-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
AR HSE Building Spec MDF-PTJ-AR-SPC-0004 HSE Building Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
(PRODUCTION BUILDING -REFINING BUILDING - (PRODUCTION BUILDING -REFINING BUILDING -
AR MDF-PTJ-AR-SPC-0005 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
GLUE STORAGE-PUMP SHED) Spec GLUE STORAGE-PUMP SHED) Spec
(SCALE CONTROL ROOM -SECURITY ROOM - (SCALE CONTROL ROOM -SECURITY ROOM -
AR MDF-PTJ-AR-SPC-0006 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
MOSQUE-GUARD TOWER) Spec MOSQUE-GUARD TOWER) Spec
AR Fence & General Layout Spec MDF-PTJ-AR-SPC-0008 Fence & General Layout Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
AR High security fence Spec MDF-PTJ-AR-SPC-0009 High security fence Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
Administration Building 8,191 11% 100% 100% 100% 100% 100% 100% 100% 100%
A8450 Architecture 3,218 39% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Administration Building-Ground floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
MDF-PTJ-AR-DWG-
AR Administration Building-First Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-AR-DWG-
AR Administration Building-Second Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
MDF-PTJ-AR-DWG-
AR Administration Building-Roof Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
MDF-PTJ-AR-DWG-
AR Administration Building- Elevations 1-2 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0005
MDF-PTJ-AR-DWG-
AR Administration Building- Elevation 3-4 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-AR-DWG-
AR Administration Building- Sections A-A & Scheduals 202 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0007
MDF-PTJ-AR-DWG-
AR Administration Building- Doors & Windows Schedule 202 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0008
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Ground floor Plan
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0009 -water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Ground floor Plan
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0010 water supply system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-first floor Plan -
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0011 water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-first floor Plan -
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0012 water supply system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Second Floor Plan-
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0013 water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Second Floor Plan-
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0014 water supply system
MDF-PTJ-AR-DWG-
AR CAR PARKING SHED - ROOF PLAN 198 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0129
MDF-PTJ-AR-DWG- CAR PARKING SHED - ELEVATION 1 & 2 & SECTION
AR 198 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0130 (A-A)
A8460 Civil & Steel Str. (for Car Shed) 2,708 33% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0001 Calculation sheet For Admin Building 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0003 Administration building - Basis of Structural Design 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0001 Administration building - Foundation Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0002 Administration building - Column and Axes Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0003 Administration building - Slab of Ground Floor 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0004 Administration building - Typical Slab Floor Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0020 CAR PARKING SHEDS Foundation calculation sheet 285 11% 20-Dec-21 03-Feb-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0111 CAR PARKING SHEDS Foundation Plan & Details 285 11% 20-Dec-21 03-Feb-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0021 CAR PARKING SHEDS- Calculation Note 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0022 CAR PARKING SHEDS- Layout For Base Plate 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0023 CAR PARKING SHEDS- Layout Plans& Elevations 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A8465 Electrical 855 10% 100% 100% 100% 100% 100% 100% 100% 100%
Page 129 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-SLD-0005 Main Admin DB SLD 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0006 SUB Normal DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0007 SUB Emergency DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0008 UPS DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0001 Lighting Layout Plan Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0002 Small Power Layout Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8480 Telecomm. 855 10% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0001 ADMINISTRATION BUILDING FIRE ALARM SYSTEM 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
ADMINISTRATION BUILDING FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0002 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0019 ADMINISTRATION BUILDING CCTV 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0006 Scale room - BASIS OF STRUCTURAL DESIGN 98 33% 08-Nov-20 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 10-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0006 Small Power Layout Plan SCL 85 33% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0011 Normal DB SLD Scale Control Room 85 33% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A10310 Telecomm. 510 35% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0056 SCALE ROOM FIRE ALARM SYSTEM LAYOUT 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0059 SCALE ROOM PUBLIC ADDRESS SYSTEM 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0060 SCALE ROOM PUBLIC ADDRESS SYSTEM CABLING 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0061 SCALE ROOM NETWORK SYSTEM 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A10330 HVAC 205 14% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0008 SCALE ROOM HVAC CALCULATIONS 120 59% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-Scale room GROUND plan Scale Room 85 41% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0015
HSE Building 4,662 6% 100% 100% 100% 100% 100% 100% 100% 100%
Page 130 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A10610 Architecture 1,544 33% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR HSE Bilding-Ground floor Level 140 9% 05-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0024
MDF-PTJ-AR-DWG-
AR HSE Bilding-Roof Plan Level 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0025
MDF-PTJ-AR-DWG-
AR HSE Bilding- Elevation 1- 2 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0026
MDF-PTJ-AR-DWG-
AR HSE Bilding- Elevation 3 - 4 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0027
MDF-PTJ-AR-DWG-
AR HSE Bilding- Section A-A & B-B 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0028
MDF-PTJ-AR-DWG-
AR HSE Building-Doors & Windows finish schedule 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0029
MDF-PTJ-AR-DWG-
AR HSE Bilding- FIRST FLOOR PLAN 405 26% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0030
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-Ground floor Plan --water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0031 drainage system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-Ground floor Plan -water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0032 supply system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-First floor Plan --water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0035 drainage system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-First floor Plan -water supply
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0039 system
A10620 Civil & Steel Str. (Car Shed) 1,050 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0002 HSE BUILDING - Calculation sheet 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0004 HSE BUILDING - Basis of Structural Design 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0006 HSE BUILDING - Foundation Plan & Details 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0007 HSE BUILDING - Column and Axes 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0008 HSE BUILDING - Slab at Level 4050 & 4500 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0008 HSE Building Car Shed - Calculation Note 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0047 HSE Building Car Shed - Layout For Base Plate 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0048 HSE Building Car Shed General Arrangement for Roof Plan 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0049 HSE Building Car Shed General Arrangement for Elevations 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0050 HSE Building Car Shed Details of Connection 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A10630. Electrical 810 17% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0003 Lighting Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0004 Small Power Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0012 FIRST FLOOR Lighting Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0013 FIRST FLOOR Small Power Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0009 MAIN DP SLD (HSE-MDP ) 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0010 FIRST FLOOR DP SLD (HSE-1ST.DP ) 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A10640 Telecomm. 810 17% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0017 HSE BUILDING FIRE ALARM SYSTEM 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0018 HSE BUILDING FIRE ALARM SYSTEM CABLING 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0027 MAIN FIRE STATION AND HSE BUILDING CCTV 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MAIN FIRE STATION AND HSE BUILDING PUBLIC
TL MDF-PTJ-TL-DWG-0044 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ADDRESS SYSTEM
MAIN FIRE STATION AND HSE BUILDING PUBLIC
TL MDF-PTJ-TL-DWG-0045 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ADDRESS SYSTEM CABLING
MAIN FIRE STATION AND HSE BUILDING NETWORK
TL MDF-PTJ-TL-DWG-0055 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
A10660 HVAC 448 10% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0002 HSE Build HVAC CALCULATION 112 25% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 131 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-HV-DWG-
HV HVAC-HSE Building-Ground floor plan 168 38% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-HV-DWG-
HV HVAC-HSE Building-First floor plan 168 38% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0007
Switch Rooms 8,691 12% 100% 100% 100% 100% 100% 100% 100% 100%
A84510 Architecture 1,080 12% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-elevations-Scheduales SR01B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0121
MDF-PTJ-AR-DWG-
AR Switch Room-GROUND - FIRST FLOOR PLAN SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0122
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS 1-2 SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0123
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS 3-4 SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0124
MDF-PTJ-AR-DWG-
AR Switch Room-SECTION A-A & SCHEDULES SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0125
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-elevations-Scheduales SR02C 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0126
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-Scheduales SR022 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0127
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS SR022 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0128
Civil 1,650 19% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0072 Switch room - SR01A - Columns and Axis Roof Slab 275 17% 08-Jun-21 23-Jul-21 07-Aug-21 22-Aug-21 27-Aug-21 11-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0114 Switch room SR02C - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0115 Switch room SR022 - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0116 Switch room SR02B - Plans & Details 275 17% 08-Jul-21 22-Aug-21 06-Sep-21 21-Sep-21 26-Sep-21 11-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0117 Switch room SR02A - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0118 Switch room SR01B- Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
TELECOME 90 1% 100% 100% 100% 100% 100% 100% 100% 100%
Switch Room SR02B Data Network & IP Telephone system
TL MDF-PTJ-TL-DWG-0071 90 100% 22-Apr-21 29-Apr-21 06-May-21 13-May-21 20-May-21 27-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
HVAC 1,400 16% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0013 SR01B - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0014 SR02B - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0015 SR02C - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0016 SR022 - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0150 GENERATOR SHED SR02C 147 33% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0151 GENERATOR SHED SR022 147 33% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Electerical 4,030 46% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0028 SWITCH ROOM (SR01A) - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0029 Strew Preparation Building(SR01A) - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0030 SR01A - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 132 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-SLD-0039 SR01A - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0031 SR01B - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0032 SR01B - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0033 SR01B - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0040 SR01B - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0034 SR02A - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0035 SR02A - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0036 SR02A - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0047 SR02A - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0037 SR02B - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0038 SR02B - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0039 SR02B - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0042 SR02B - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0040 SR02C - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0041 SR02C - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0042 SR02C - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0043 SR02C - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0043 SR022 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0044 SR022 - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0045 SR022 - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0044 SR022 - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0046 SR03 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0050 SR04 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
NEW SWITCH ROOM 1,808 2% 100% 100% 100% 100% 100% 100% 100% 100%
A84510 Architecture 270 15% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR New Switch Room Plan-section-Scheduales 135 50% 31-Mar-21 14-Apr-21 28-Apr-21 12-May-21 26-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0049
MDF-PTJ-AR-DWG-
AR New Switch Room ELEVATIONS 135 50% 31-Mar-21 14-Apr-21 28-Apr-21 12-May-21 26-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0060
STEEL Structure 610 34% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0070 NEW SWITCH ROOM - Steel Structure Calculation 210 34% 16-Nov-21 26-Nov-21 03-Dec-21 13-Dec-21 20-Dec-21 25-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0025 New Switch Room - Small Power Layout Plan 155 33% 20-Apr-21 04-May-21 15-May-21 29-May-21 10-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0038 New Switch Room - SLD 155 33% 20-Apr-21 04-May-21 15-May-21 29-May-21 10-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC 308 17% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0019 NEW SWITCHROOM -HVAC SYSTEM CALCULATIONS 140 45% 25-May-21 08-Jun-21 20-Jun-21 04-Jul-21 14-Jul-21 22-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0005 MAIN SECURITY ROOM Basis of Structural Design 60 33% 25-Nov-20 09-Dec-20 21-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0041 Lighting DP SLD MAIN SEC ROOM 140 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A10530 Telecomm. 890 41% 100% 100% 100% 100% 100% 100% 100% 100%
MAIN SECURITY ROOM FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0015 190 21% 01-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
LAYOUT
MAIN SECURITY ROOM FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0016 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING LAYOUT
TL MDF-PTJ-TL-DWG-0026 MAIN SECURITY ROOM CCTV LAYOUT 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0007 Security BUILDING Basis of Structural Design 75 33% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 134 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Security BUILDING Roof slab at Level (3450) Columns &
CI MDF-PTJ-CI-DWG-0012 75 33% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Axis - Foundation Plan & Details
A9750 Electrical 310 12% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0007 Lighting and mall power Layout Plan SEC Building 155 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0013 Lighting DP SLD SEC Building 155 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A9760 Telecomm. 930 36% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0002 Security Room Fire Alarm system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0003 Security Room Fire Alarm system Cabling Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0009 Security Room CCTV system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0014 Security Room Public Address system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0015 Security Room Public Address system Cabling Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0020 Security Room Data Network & IP Telephone system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A9780 HVAC 620 24% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV Security Room - Ground Floor Plan-Layout 155 25% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0011
HV MDF-PTJ-HV-CAL-0005 Security Room - HVAC SYSTEM CALCULATIONS 465 75% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Mosque 2,840 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9840 Architecture 1,020 36% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR MOSQUE - Ground floor Level 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0073
MDF-PTJ-AR-DWG-
AR MOSQUE - Roof Plan Level 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0074
MDF-PTJ-AR-DWG-
AR MOSQUE - Elevations 1&3 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0075
MDF-PTJ-AR-DWG-
AR MOSQUE - Elevations 2&4 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0076
MDF-PTJ-AR-DWG-
AR MOSQUE - Sections & schedule 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0077
MDF-PTJ-AR-DWG- MOSQUE - Plumbing Works-Ground floor Plan --water
AR 85 8% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0079 drainage system
MDF-PTJ-AR-DWG- MOSQUE - Plumbing Works-Ground floor Plan -water
AR 85 8% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0080 supply system
A9850 Civil 700 25% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0011 MOSQUE building (MOSQUE) calculation sheet 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0018 Small Power Layout Plan MOS 160 33% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0028 Normal DB SLD MOS 160 33% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A9870 Telecomm. (Public Address) 320 11% 100% 100% 100% 100% 100% 100% 100% 100%
MOSQUE BUILDING PUBLIC ADDRESS SYSTEM
TL MDF-PTJ-TL-LAY-0013 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN
MOSQUE BUILDING PUBLIC ADDRESS SYSTEM
TL MDF-PTJ-TL-DWG-0046 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
A9890 HVAC 320 11% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0011 MOSQUE HVAC SYSTEM CALCULATIONS 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-MOSQUE-Ground floor plan 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0019
Permanent TCF 3,108 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9950 Architecture 882 28% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Ground plans 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0065
Page 135 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Roof plans 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0066
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Elevations 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0067
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Sections A-A 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0068
MDF-PTJ-AR-DWG- Permanent TCF BUILDING -Doors & Windows finish
AR 84 10% 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 12-Dec-20 15-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0069 schedule
MDF-PTJ-AR-DWG- Permanent TCF BUILDING - Plumbing Works--water
AR 105 12% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0071 drainage system
MDF-PTJ-AR-DWG- Permanent TCF BUILDING - Plumbing Works-water supply
AR 105 12% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0072 system
A9952 CI Civil MDF-PTJ-CI-DWG-0009 Permanent TCF BUILDING Paving Details 120 4% 23-Sep-20 28-Sep-20 03-Oct-20 08-Oct-20 13-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9955 Electrical 870 28% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0015 LIGHTING Layout Plan TCF 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0016 SMALL POWER Layout Plan TCF 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0024 MDP SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0025 PDP SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0026 air condition DP (ACDP) SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0027 lighting DP (LDP) SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9960 Telecomm. 900 29% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0006 TCF office Fire Alarm system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0007 TCF office Fire Alarm system Cabling Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0011 TCF office CCTV system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0018 TCF office Public Address system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0019 TCF office Public Address system Cabling Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0022 TCF office Data Network & IP Telephone system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9970 HVAC 336 11% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0010 HVAC SYSTEM CALCULATIONS - TCF 168 50% 20-Sep-20 25-Sep-20 30-Sep-20 05-Oct-20 10-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-TCF Building-Ground floor plan 168 50% 20-Sep-20 25-Sep-20 30-Sep-20 05-Oct-20 10-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0018
Fence , Guard towers & Gates 2,033 3% 100% 100% 100% 100% 100% 100% 100% 100%
A10060 Architecture 1,285 63% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR FENCE -Plans &Section A-A 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0042
MDF-PTJ-AR-DWG-
AR FENCE - Elevations 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0043
MDF-PTJ-AR-DWG-
AR Guard Towers-Plans 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0045
MDF-PTJ-AR-DWG-
AR Guard Towers - Elevations - Sections 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0046
MDF-PTJ-AR-DWG-
AR Guard Towers - Elevations 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0047
MDF-PTJ-AR-DWG-
AR Guard Towers - Roof Plan & Schedules 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0048
MDF-PTJ-AR-DWG-
AR TYPICAL Gate -Plan - Elevation - Section 325 25% 19-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0152
A10070 Civil 618 30% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0006 RC FENCE calculation sheet 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0013 FENCE FOUNDATION PLAN AND DETAILS 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0008 GUARD TOWER calculation sheet 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0015 GUARD TOWER - Foundation Plan and Details 163 26% 19-Jan-21 06-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 04-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0030 GATES - Foundation Plan & Details 65 11% 19-Jan-21 06-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 04-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
A10075 Electrical 130 6% 100% 100% 100% 100% 100% 100% 100% 100%
Page 136 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-DWG-0008 Lighting and Small power Layout Plan Guard Tower 65 50% 19-Jan-21 02-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0014 Normal DB SLD Guard Tower 65 50% 19-Jan-21 02-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Substation Building 6,985 10% 100% 100% 100% 100% 100% 100% 100% 100%
A10170 Architecture 1,575 23% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Ground floor Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0050
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-First floor Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0051
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING- Roof Plan Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0052
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Elevations 1 & 2 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0053
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Elevations 3 & 4 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0054
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Section A-A 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0055
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Doors & Windows Schedule 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0057
A10180 Civil 1,350 19% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0009 SUBSTATION BUILDING calculation sheet 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-RPT-0009 SUBSTATION BUILDING - Basis of Structural Design 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0016 SUBSTATION BUILDING - Foundation Plan & Details 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0017 SUBSTATION BUILDING - Column and Axes 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0018 SUBSTATION BUILDING - Slab at Level 2250 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0019 SUBSTATION BUILDING - Slab at Level 8250 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A10190 Electrical 1,450 21% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0009 Electrical Equipment layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0010 Lighting Layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0011 Small Power Layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0016 Main Normal DB SLD SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0018 Main Emergency DB SLD SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A10200 Telecomm. 1,740 25% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0005 SUBSTATION BUILDING FIRE ALARM SYSTEM 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0032 SUBSTATION BUILDING PUBLIC ADDRESS SYSTEM 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0001 Liquid Chemical Shed - Steel Base Plate Plan 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0030 LIQUID CHEMICAL SHED SLD 116 50% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A10420 Telecomm. 716 29% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0072 Liquid Chemical Storage FIRE ALARM SYSTEM 200 28% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0075 Liquid Chemical Storage PUBLIC ADDRESS SYSTEM 116 16% 21-May-21 25-Jun-21 30-Jun-21 05-Jul-21 10-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0077 Workshop & Lockers - Calculation 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0310 Workshop & Lockers - Base Plate (Plan/Sections) 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0311 Workshop & Lockers - GA For Roof Plan 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0312 Workshop & Lockers - Details of Connection 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9640 Electrical 945 13% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0020 Lighting Layout Plan WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0021 Small Power Layout Plan WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0031 Main Normal DB SLD WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0032 Sub-Normal DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0033 Main Emergency DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0034 SUB Emergency DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0014 Lightning Protection System WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
A9650 Telecomm. 1,610 22% 100% 100% 100% 100% 100% 100% 100% 100%
Workshop & Spare parts Warehouse Fire Alarm system
TL MDF-PTJ-TL-LAY-0004 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
Workshop & Spare parts Warehouse Fire Alarm system
TL MDF-PTJ-TL-LAY-0005 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Cabling Layout
TL MDF-PTJ-TL-LAY-0010 Workshop & Spare parts Warehouse CCTV system Layout 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0031 Spare parts warehouse Fire alarm cabling 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0034 Spare parts warehouse Public address system layout 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0035 Spare parts warehouse Public address system cabling 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0036 Spare parts warehouse CCTV SYSTEM LAYOUT 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC 580 8% 100% 100% 100% 100% 100% 100% 100% 100%
WORKSHOP & LOCKERS BUILDING HVAC SYSTEM
HV MDF-PTJ-HV-CAL-0020 290 50% 04-Aug-21 11-Aug-21 18-Aug-21 25-Aug-21 01-Sep-21 08-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
CALCULATIONS
MDF-PTJ-HV-DWG- WORKSHOP & LOCKERS BUILDING- HVAC GROUND
HV 290 50% 04-Aug-21 11-Aug-21 18-Aug-21 25-Aug-21 01-Sep-21 08-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
0030 FLOOR PLAN
Page 139 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A9660 Fire Fighting Firefighting system Layout - workshop / warehouse building 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Fire Pump Shed 2,925 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9510 Architecture 1,575 54% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Ground floor Level 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0099
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Roof Level 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0100
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Elevation 1 - 2 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0101
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Elevation 3 - 4 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0102
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Section A-A 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0103
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-finish schedule 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0104
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Doors & Windows Schedule 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0105
MDF-PTJ-AR-DWG- Fire Water Pump Shed-Plumbing Works-water drainage
AR 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0106 system
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Plumbing Works-water supply system 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0107
A9520 Civil & St. Str. 1,080 37% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0014 FIRE PUMP Shed calculation sheet 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0029 FIRE PUMP Shed - Foundation Plan & Details 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0002 FIRE PUMP shed - Structural steel calculations report 135 13% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0010 FIRE PUMP shed - Steel Base Plate Plan 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DTL-0009 FIRE PUMP shed - Steel Elevations & Details 1 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DTL-0010 FIRE PUMP shed - Steel Elevations & Details 2 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
A9530 Electrical 270 9% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0022 Lighting and socket Plan FPS 135 50% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0035 Distribution board SLD FPS 135 50% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
CAR PARK Shed 527 1% 100% 100% 100% 100% 100% 100% 100% 100%
St. Str. 527 100% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0093 CAR PARKING SHED Base Plate Plan & Section 176 33% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0094 CAR PARKING SHED Roof Plan and Elevations 176 33% 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0095 CAR PARKING SHED Connection Details 176 33% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
Air Compressor Shed 2,894 4% 100% 100% 100% 100% 100% 100% 100% 100%
A82350 Steel Str 576 20% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0026 AIR COMPRESSOR SHED - Calculation Note 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0027 AIR COMPRESSOR SHED - Layout For Base Plate 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0028 AIR COMPRESSOR SHED - Layout Plans& Elevations 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0029 AIR COMPRESSOR SHED- Details Of Connections 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9400 Architecture 1,035 36% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Air Compressor Shed -Ground&Roof plans 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0141
MDF-PTJ-AR-DWG-
AR Air Compressor Shed -North&East Elevations 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0142
MDF-PTJ-AR-DWG-
AR Air Compressor Shed - South&West Elevations 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0143
MDF-PTJ-AR-DWG-
AR Air Compressor Shed- Section A-A & Section B-B 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0144
MDF-PTJ-AR-DWG- Air Compressor Shed- finish schedule - Doors & Windows
AR 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0145 Schedule
Page 140 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG- Air Compressor Shed - Plumbing Works--water drainage
AR 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0146 system & -water supply system
A9410 Civil 275 10% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0021 AIR COMPRESSOR Shed Foundation calculation sheet 138 50% 07-Feb-22 15-Feb-22 18-Feb-22 21-Feb-22 24-Feb-22 27-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0112 AIR COMPRESSOR Shed Foundation Plan & Details 138 50% 07-Feb-22 15-Feb-22 18-Feb-22 21-Feb-22 24-Feb-22 27-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A9415 EL Electrical MDF-PTJ-EL-LAY-0010 AIR COMPRESSOR Shed Lighting and socket Layout 144 5% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A9430 Telecomm. 864 30% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0011 AIR COMPRESSOR Shed FIRE ALARM SYSTEM 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
AIR COMPRESSOR Shed FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0012 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0024 AIR COMPRESSOR Shed CCTV 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0038 AIR COMPRESSOR Shed PUBLIC ADDRESS SYSTEM 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0035 Industrial Water Pump Station - Layout For Base Plate 158 17% 21-Jun-21 31-Jul-21 07-Aug-21 12-Aug-21 14-Aug-21 19-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0036 Industrial Water Pump Station - Layout Plans& Elevations 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0037 Industrial Water Pump Station - Details Of Connections 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0082 Industrial Water Pump Station - Calculation Note 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0038 Industrial Water Pump House Shed - Connection & Details 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9290 Architecture 845 38% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Ground floor Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0206
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Roof Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0207
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Elevation 1 - 2 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0208
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Elevation 3 - 4 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0209
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Section A-A 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0210
A9300 Civil 298 13% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0016 Industrial Water Pump Station Foundation calculation sheet 140 47% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0033 Industrial Water Pump Station- Foundation Plan & Details 158 53% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0031 WASTE PUMPS STATION - Layout For Base Plate 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0032 WASTE PUMPS STATION - Layout Plans& Elevations 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0123 Reject Water Pump Shed- Foundation Plan & Details 135 18% 05-Feb-22 07-Feb-22 09-Feb-22 11-Feb-22 13-Feb-22 15-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A9070 Architecture 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
A9080 Civil 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
A9090 Electrical WASTE PUMPS STATION Shed Lighting and socket Layout 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Potable water pump station 2,490 3% 100% 100% 100% 100% 100% 100% 100% 100%
A82360 Steel Str. 1,190 48% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0006 POTABLE Water PUMP Station - Calculation Note 158 13% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0039 POTABLE Water PUMP Station - Layout For Base Plate 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0040 POTABLE Water PUMP Station - Layout Plans& Elevations 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0041 POTABLE Water PUMP Station - Details Of Connections 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0085 POTABLE WATER PUMP HOUSE Connections &Details 140 12% 19-Sep-21 29-Sep-21 06-Oct-21 16-Oct-21 23-Oct-21 28-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
A8960 Architecture 845 34% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Ground floor Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0221
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Roof Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0222
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Elevation 1 - 2 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0223
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Elevation 3 - 4 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0224
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Section A-A 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0225
A8970 Civil 298 12% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0017 POTABLE Water PUMP Station Foundation calculation sheet 140 47% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0034 POTABLE Water PUMP Station- Foundation Plan & Details 158 53% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0113 WATER TREATMENT Foundation Plan & Details 188 50% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A16110 Telecomm. 1,125 38% 100% 100% 100% 100% 100% 100% 100% 100%
WATER TREATMENT BUILDING FIRE ALARM
TL MDF-PTJ-TL-DWG-0013 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
WATER TREATMENT BUILDING FIRE ALARM
TL MDF-PTJ-TL-DWG-0014 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM CABLING
Page 142 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
TL MDF-PTJ-TL-DWG-0025 WATER TREATMENT BUILDING CCTV 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
Loss Prevention 13,544 6% 100% 100% 100% 100% 100% 100% 100% 100%
HAZID & Layout Review 1,260 9% 100% 100% 100% 100% 100% 100% 100% 100%
A6850 HAZID & Layout Review 1,260 100% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0001 HAZID & Layout Review Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0002 HAZID & Layout Review Close Out Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0003 Weather Condition Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
On-Spec. - Project Management 200 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP009 Engineering Documents Register (EDR) 100 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0001 Fire & Gas Mapping assumptions register 100 100% 06-Feb-21 17-Feb-21 22-Feb-21 27-Feb-21 04-Mar-21 14-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP010 Project Schedule 100 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0020 Utilities Layout Review Study 100 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
Onspec. - Loss Prevention 11,274 83% 100% 100% 100% 100% 100% 100% 100% 100%
LP012 Fire Protection Design Philosophy 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0009 Fire Protection Design Philosophy 105 100% 13-Feb-21 24-Feb-21 01-Mar-21 06-Mar-21 11-Mar-21 12-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP013 QRA/FERA and Mapping Assumption Register 205 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0004 Assumption Register for QRA-FERA 105 51% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0006 Quantitative risk assessment (QRA) assumptions register 100 49% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP015 Stage 1-Fire and Explosion Analysis Report (FERA) 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0005 Fire and Explosion Analysis Report (FERA) Report 105 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP016 Quantitative risk assessment (QRA) Report 100 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0007 Quantitative risk assessment (QRA) report 100 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP017 Stage 2-Fire and Explosion Analysis Report (FERA) Report 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0018 Gas Suppression system Calculation Report (HSE Building) 210 100% 28-May-21 08-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 03-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP018 Fire & Gas Mapping Study Report 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0008 Fire & Gas Mapping Study Report 105 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP019 Fire Water and Fire Foam Demand Calculation 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0010 Fire Water and Fire Foam Demand Calculation Report 140 100% 01-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 07-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP020 Preliminary Firefighting Equipment Data Sheet 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP021 Fire Water Network Layout 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0002 Fire Water Network Layout 147 100% 01-Apr-21 12-Apr-21 17-Apr-21 22-Apr-21 27-Apr-21 07-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP022 Hydraulic Calculation Report 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0011 Hydraulic Calculation Report 140 100% 01-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 07-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP023 Fire Water Spray and Foam System Layout (If Required) 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP024 Fire Extinguishers and Safety Equipment Layouts 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP025 Fire Water System P&IDs 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0001 Fire Water System P&IDs 147 100% 14-May-21 25-May-21 30-May-21 04-Jun-21 09-Jun-21 19-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP026 Foam system P&IDs (If Required) 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP028 Fire Equipment Specification 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0003 Fire Equipment Specification 140 100% 14-Feb-21 25-Feb-21 02-Mar-21 07-Mar-21 12-Mar-21 22-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP029 Water Foam Vehicle Specification (If Required) 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0001 Water Foam Vehicle Specification (If Required) 147 100% 14-May-21 25-May-21 30-May-21 04-Jun-21 09-Jun-21 19-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP030 Firefighting water Pump Datasheet 3,732 33% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0002 Firefighting water Pump Datasheet 147 4% 19-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 14-Apr-21 24-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-DAT-0011 MOBILE FOAM UNIT DATASHEET 147 4% 22-Jun-21 03-Jul-21 08-Jul-21 13-Jul-21 18-Jul-21 28-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-DAT-0013 Portable CO2 Fire Extinguishers Datasheet 147 4% 11-Aug-21 22-Aug-21 27-Aug-21 01-Sep-21 06-Sep-21 16-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-MTO-0003 Production Line Fire Extinguishing Nozzles MTO 147 4% 17-Jun-21 28-Jun-21 03-Jul-21 08-Jul-21 13-Jul-21 23-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-MTO-0004 U/G PIPING MTO 147 4% 17-Sep-21 28-Sep-21 03-Oct-21 08-Oct-21 13-Oct-21 23-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Refining Building - GROUND FLOOR PLAN - Switch Room
FF MDF-PTJ-LP-LAY-0015 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
-SR02A Fire Fighting Protection Layout
SR-02B BUILDING - GROUND FLOOR AND CELLER
FF MDF-PTJ-LP-LAY-0016 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FLOORPlans
STRAW PREPARATION BUILDING - GROUND FLOOR
FF MDF-PTJ-LP-LAY-0017 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
AND RAISED FLOOR Plans
SUBSTATION BUILDING - GROUND FLOOR AND
FF MDF-PTJ-LP-LAY-0018 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CELLER FLOOR Plans
PRODUCTION BUILDING - GROUND FLOOR -
FF MDF-PTJ-LP-LAY-0019 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
OVERALL PLAN
FF MDF-PTJ-LP-LAY-0025 Fire Fighting Protection Layout For NEW Switch Room 210 6% 07-Jun-21 18-Jun-21 23-Jun-21 28-Jun-21 03-Jul-21 13-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-LAY-0026 Protection Layout for Production Building - Sprinkler System 200 5% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
FF MDF-PTJ-LP-LAY-0027 FF Protection Layout for Production Building - FHC system 200 5% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0005 F&G Cable Schedule and Spec. 210 52% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP045 F&G Loop Diagram 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0005 F&G Loop Diagram 210 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP046 F&G Cable Routing Layout 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0011 F&G Cable Routing Layout 200 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP047 F&G Hook up Drawings 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0006 F&G Hook up Drawings 200 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP048 F&G Bulk Material MTO 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-MTO-0001 F & G Material MTO 210 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP050 Fire and Gas Cause and Effect 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0012 Fire and Gas Cause and Effect 200 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP051 Firefighting protection Layout for HSE building 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0006 Firefighting protection Layout for HSE building. 147 100% 11-Feb-21 22-Feb-21 27-Feb-21 04-Mar-21 09-Mar-21 19-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP052 Firefighting protection Layout for Masjed building 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0007 Firefighting protection Layout for Masjed building. 147 100% 12-Feb-21 23-Feb-21 28-Feb-21 05-Mar-21 10-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP053 Firefighting protection Layout for Scale Control Room 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0008 Firefighting protection Layout for Scale Control Room. 140 100% 14-Feb-21 25-Feb-21 02-Mar-21 07-Mar-21 12-Mar-21 22-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP054 Firefighting protection Layout for Security Room 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
Firefighting protection Layout for Security Room Ground
LP MDF-PTJ-LP-LAY-0009 147 100% 18-Feb-21 01-Mar-21 06-Mar-21 11-Mar-21 16-Mar-21 26-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Floor Plan
LP055 Firefighting protection Layout for Administration building 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Total Flooding Clean Agent Gaseous Suppression System
LP056 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
Total Flooding Carbon Dioxide Gaseous Suppression System
LP057 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
Total Flooding Carbon Dioxide Gaseous Suppression System
LP MDF-PTJ-LP-DWG-0009 147 100% 05-Mar-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 10-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
LP058 Portable/Mobile Fire Extinguishers Data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0007 Portable/Mobile Fire Extinguishers Data Sheet. 140 100% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP059 Fire Hose and Hose Cabinets data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0008 Fire Hose and Hose Cabinets data Sheet. 140 100% 07-Mar-21 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 12-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
LP062 Escape Route Layout 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0022 Escape Route Layout 200 100% 16-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 21-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP063 Safety Signs Layouts 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0023 Safety Signs Layouts 200 100% 23-May-21 03-Jun-21 08-Jun-21 13-Jun-21 18-Jun-21 28-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP064 HAZOP Study 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0016 HAZOP (Limited to 7-days) 210 100% 26-Feb-21 09-Mar-21 14-Mar-21 19-Mar-21 24-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
LP065 Noise Study Report 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0013 Noise Study Report 210 100% 09-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 05-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP066 Noise Control Design 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0014 Noise Control Design Report 210 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP067 Passive Fire Protection Design Schedule 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-SCH-0001 Passive Fire Protection Design Schedule 210 100% 16-Nov-21 27-Nov-21 02-Dec-21 07-Dec-21 12-Dec-21 22-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP068 Passive Fire Protection Layouts 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0024 Passive Fire Protection Layouts 210 100% 28-May-21 08-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 03-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP069 Waste Management Philosophy and Handling Requirements 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0017 Waste Management Philosophy and Handling Requirements 210 100% 02-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 28-Jun-21 08-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP070 Emissions Control Design 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0015 Emissions Control Design Report 200 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
On-Spec. Piping Engineering Discipline 410 3% 100% 100% 100% 100% 100% 100% 100% 100%
Page 145 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
LP078 Firefighting Network Piping MTO for Storage Area 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
LP079 3D Model 210 51% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0008 3D Model 210 100% 23-Jun-21 04-Jul-21 09-Jul-21 14-Jul-21 19-Jul-21 29-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP080 Firefighting Network Piping MTO 200 49% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-MTO-0002 Piping MTO 200 100% 14-Mar-21 25-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
On-Spec. - Electrical Engineering Discipline 400 3% 100% 100% 100% 100% 100% 100% 100% 100%
LP082 Hazardous Area Classification Schedule 200 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-SCH-0002 Hazardous Area Classification Schedule 200 100% 22-Nov-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 28-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP083 Hazardous Area Classification Drawings 200 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0007 Hazardous Area Classification Drawings 200 100% 29-Dec-21 09-Jan-22 14-Jan-22 19-Jan-22 24-Jan-22 03-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
Storage Tanks 13,780 6% 100% 100% 100% 100% 100% 100% 100% 100%
Civil 1,150 8% 100% 100% 100% 100% 100% 100% 100% 100%
TK.320 Foundations For Industrial Raw Water Tank 340 30% 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION FOR Industrial Raw Water Tanks - TK101-
CI MDF-PTJ-CI-CAL-0100 65 19% 03-Feb-21 11-Feb-21 16-Feb-21 21-Feb-21 25-Feb-21 28-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A - CALCULATION
FOUNDATION DETAILS FOR Industrial Raw Water Tanks
CI MDF-PTJ-CI-DWG-0021 275 81% 04-Feb-21 21-Mar-21 05-Apr-21 20-Apr-21 25-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
- TK101-A
TK.330 Foundations For DEMI Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0053 FOUNDATION DETAILS FOR Demi Water Tank TK-103A 270 100% 20-Jan-21 06-Mar-21 21-Mar-21 05-Apr-21 10-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.340 Foundations For Process Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION DETAILS FOR Process Water Tank TK-
CI MDF-PTJ-CI-DWG-0052 270 100% 20-Jan-21 06-Mar-21 21-Mar-21 05-Apr-21 10-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
102A
TK.430 Foundations For Potable Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0051 FOUNDATION DETAILS FOR Potable Water Tank 270 100% 26-Sep-21 10-Nov-21 25-Nov-21 10-Dec-21 15-Dec-21 30-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.440 Foundations For Emulsion - Chemical Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.450 Foundations For PMDI - Chemical Storage Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.460 Foundations For Fire Water Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
Design Calc. & Data Sheet 2,277 17% 100% 100% 100% 100% 100% 100% 100% 100%
TK.250 Industrial Raw Water Tank 674 30% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-SPC-0001 Gauge Hatch Technical Specification 190 28% 23-Feb-21 09-Apr-21 14-Apr-21 19-Apr-21 24-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-SPC-0002 Agitators Technical Specification 190 28% 14-Sep-21 29-Oct-21 03-Nov-21 08-Nov-21 13-Nov-21 14-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0001 Industrial Raw Water Tanks Design Calculations 138 20% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0001 Industrial Raw Water Tanks Roof Structure Details 117 17% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0002 Industrial Raw Water Tanks Name Plate 39 6% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.260 DEMI Water Tank 294 13% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0003 Demi Water Tanks Design Calculations 138 47% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0003 Demi Water Tanks Roof Structure Details 117 40% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0004 Demi Water Tanks Name Plate 39 13% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.270 Process Water Tank 294 13% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0005 Process Water Tanks Design Calculations 138 47% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0005 Process Water Tanks Roof Structure Details 117 40% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0006 Process Water Tanks Name Plate 39 13% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.280 Potable Water Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.290 Emulsion Chemical Tank 589 26% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0013 Chemical Tank Design Calculations 117 20% 13-Mar-21 16-Mar-21 21-Mar-21 24-Mar-21 27-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0014 Chemical Tank Roof Structure Calculations 120 20% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0013 Chemical Tank Roof Structure Details 176 30% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0014 Chemical Tank Name Plate 176 30% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.300 Fire Water Tank 426 19% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0011 Fire Water Tanks Design Calculations 130 31% 12-Apr-21 15-Apr-21 20-Apr-21 23-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0011 Fire Water Tanks Roof Structure Details 108 25% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-DTL-0012 Fire Water Tanks Name Plate 108 25% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
TK.310 PMDI - Chemical Storage Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Drawings 10,353 75% 100% 100% 100% 100% 100% 100% 100% 100%
TK.000 Industrial Raw Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0005
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0007
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0008
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0010
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0012
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0013
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0014
TK.010 DEMI Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Demi Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0015
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0016
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0017
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0018
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0019
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0020
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0021
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0022
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0024
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0026
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0027
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0028
TK.020 Process Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Process Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0029
MDF-PTJ-TK-DWG-
TK Process Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0030
MDF-PTJ-TK-DWG-
TK Process Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0031
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0032
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0033
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0034
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0035
Page 147 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0036
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0038
MDF-PTJ-TK-DWG-
TK Process Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0040
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0041
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0042
TK.040 Fire Water Tank 1,512 15% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Fire Water Tanks General Arrangement 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0071
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Orientation 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0072
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Bottom Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0073
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0074
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0075
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Manhole 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0076
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Manhole 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0077
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Nozzles 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0078
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Draw-off Sump 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0079
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Nozzles 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0080
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Mechanical Level Indicator 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0081
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Spiral Stairway 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0082
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Handrail 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0083
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Structure Assembly 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0084
TK.240 PMDI - Chemical Storage Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
TK.470 Emulsion Chemical Tank 2,464 24% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Chemical Tank General Arrangement 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0085
MDF-PTJ-TK-DWG-
TK Chemical Tank Orientation 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0086
MDF-PTJ-TK-DWG-
TK Chemical Tank Bottom Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0087
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0088
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0089
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Manhole 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0090
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Manhole 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0091
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Nozzles 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0092
MDF-PTJ-TK-DWG-
TK Chemical Tank Draw-off Sump 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0093
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Nozzles 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0094
MDF-PTJ-TK-DWG-
TK Chemical Tank Mechanical Level Indicator 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0095
MDF-PTJ-TK-DWG-
TK Chemical Tank Spiral Stairway 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0096
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Handrail 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0097
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Structure Assembly 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0098
Cathodic Protection 4,050 2% 100% 100% 100% 100% 100% 100% 100% 100%
CP.000 Industrial Water Tank 1,040 26% 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0001 Internal CP design report for Industrial Raw Water Tanks 140 13% 03-Mar-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 148 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
CP MDF-PTJ-CP-RPT-0008 External CP design report for Industrial Raw Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0001 Anodes distribution drawing for Industrial Raw Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DTL-0001 anodes installation details for Industrial Raw Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0008 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0010 External CP design report for Demi Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0002 anodes distribution drawing for Boiler Feed Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DTL-0002 anodes installation Details for Boiler Feed Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0014 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0009 External CP design report for Process Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0005 anodes distribution drawing for Process Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DTL-0005 anodes installation Details for Process Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0011 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0003 anodes distribution drawing for Fire Water Tanks 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DTL-0003 anodes installation Details for Fire Water Tanks 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0011 External CP design report for Demi Water Tank 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-DWG-0017 EXTERNAL ANODES DISTRIBUTION 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-ME-MTO-
ME painting MTO 175 56% 09-Feb-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 05-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
A10780 Insulation Specifications & MTO 433 58% 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0014 Thermal Insulation specification 88 20% 09-Feb-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 05-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-ME-MTO-
ME Thermal Insulation MTO 170 39% 11-Mar-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 05-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-ME-MTO-
ME MTO for Refractory Material 175 40% 31-Mar-21 05-May-21 10-May-21 15-May-21 20-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
Civil Network 1,761 1% 100% 100% 100% 100% 100% 100% 100% 100%
Page 149 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A16660 Potable water network 636 36% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-LAY-0001 POTABLE WATER NETWORK LAYOUT 318 50% 11-Oct-20 31-Oct-20 20-Nov-20 20-Dec-20 20-Dec-20 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-CAL-0001 CALCULATIONS FOR NETWORKS 318 50% 21-Oct-20 10-Nov-20 20-Nov-20 20-Dec-20 20-Dec-20 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A16670 Sewer & Storm Water network 820 47% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-LAY-0002 SEWER AND STORM WATER NETWORK LAYOUT 210 26% 10-Mar-21 14-Apr-21 19-Apr-21 24-Apr-21 29-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-LAY-0003 STORM WATER LAYOUT 155 19% 02-Apr-21 07-Apr-21 02-May-21 07-May-21 01-Jun-21 30-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A16690 Irrigation network 305 17% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-DTL-0003 Pump Station-2 Details 155 51% 02-Apr-21 07-Apr-21 02-May-21 07-May-21 01-Jun-21 30-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-MTO-0001 INFRASTRUCTUR - MTO 150 49% 26-Sep-21 03-Oct-21 10-Oct-21 17-Oct-21 24-Oct-21 31-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
As Built 7,075 3.0% 100% 100% 100% 100% 100% 100% 100% 20%
A19360 As Built 7,075 100% 07-Jun-22 07-Nov-22 07-Nov-22 16-Jun-23 07-Jun-22 07-Nov-22 100% 100% 100% 100% 100% 100% 100% 20%
A14290 Vendor Print Preview-Air Compressor - Compressed Air Sys. 76 09-Nov-21 24-Feb-22 40% 100% 40% 100% 40%
Boiling & Fresh Water System 314 31-Dec-20 05-Apr-22 1% 100% 1% 100% 1%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 31% 100% 31% 100% 31%
MRQ-Piping, Fitting, Flanges - Boiler Feed Water & Fresh
A8170 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
Water Sys.
TBE - Piping, Fitting, Flanges - Boiler Feed Water & Fresh
A14330 145 11-Apr-21 14-Nov-21 30% 100% 30% 100% 30%
Water Sys.
Vendor Print Preview -Piping, Fitting, Flanges - Boiler Feed
A14360 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Water & Fresh Water Sys.
Piping Valves 286 19-Jan-21 14-Mar-22 31% 100% 31% 100% 31%
A8180 MRQ-Valves - Boiler Feed Water& Fresh Water Sys. 61 19-Jan-21 14-Apr-21 30% 100% 30% 100% 30%
A14340 TBE - Valves - Boiler Feed Water & Fresh Water Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview-Valves - Boiler Feed Water & Fresh
A14370 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Water Sys
Pumps - Thermal Oil 280 21-Feb-21 05-Apr-22 39% 100% 39% 100% 39%
A8190 MRQ-Pumps -Thermal Oil 41 21-Feb-21 18-Apr-21 30% 100% 30% 100% 30%
A14350 TBE - Pumps - Thermal Oil 17 15-Sep-21 10-Oct-21 30% 100% 30% 100% 30%
A14380 Vendor Print Preview-Pumps - Thermal Oil 90 29-Nov-21 05-Apr-22 40% 100% 40% 100% 40%
Fuel Gas System 298 31-Dec-20 14-Mar-22 0.3% 100% 0% 100% 0%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 44% 100% 44% 100% 44%
A8290 MRQ-Piping, Fitting, Flanges - Fuel Gas Sys. 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
A14420 TBE - Piping, Fitting, Flanges - Fuel Gas Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
A14450 Vendor Print Preview -Piping, Fitting, Flanges - Fuel Gas Sys. 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Piping Valves 286 19-Jan-21 14-Mar-22 56% 100% 56% 100% 56%
A8300 MRQ-Valves - Fuel Gas Sys. 61 19-Jan-21 14-Apr-21 30% 100% 30% 100% 30%
A14430 TBE - Valves - Fuel Gas Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
A14460 Vendor Print Preview-Valves - Fuel Gas Sys. 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Industrial Water System 314 31-Dec-20 05-Apr-22 2% 100% 2% 100% 2%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 10% 100% 10% 100% 10%
A8110 MRQ - Piping, Fitting, Flanges-Industrial Water Sys. 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
A14750 TBE - Piping, Fitting, Flanges-Industrial Water Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges-Industrial Water
A14800 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Sys
Piping Valves 287 18-Jan-21 14-Mar-22 13% 100% 13% 100% 13%
A8120 MRQ - Valves- -Industrial Water Sys. 61 18-Jan-21 13-Apr-21 30% 100% 30% 100% 30%
A14760 TBE - Valves- -Industrial Water Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
A90540 MRQ - Piping, Fitting, Flanges - Waste Water & Chemical Sys. 5 30-Nov-21 06-Dec-21 30% 100% 30% 100% 30%
A90570 TBE - Piping, Fitting, Flanges- Waste Water & Chemical Sys. 4 07-Dec-21 12-Dec-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges- Waste Water &
A90610 5 13-Dec-21 19-Dec-21 40% 100% 40% 100% 40%
Chemical Sys.
Piping Valves 106 13-Oct-21 14-Mar-22 0% 100% 0% 100% 0%
A90550 MRQ - Valves - Waste Water & Chemical Sys. 5 13-Oct-21 20-Oct-21 0% 100% 0% 100% 0%
A90580 TBE - Valves - Waste Water & Chemical Sys. 24 17-Oct-21 18-Nov-21 0% 100% 0% 100% 0%
A90620 Vendor Print Preview -Valves - Waste Water & Chemical Sys. 70 05-Dec-21 14-Mar-22 100% 100% 100% 100% 100%
A90530 MRQ - Industrial Water PKG.- Waste Water & Chemical Sys. 29 16-Nov-21 26-Dec-21 100% 100% 100% 100% 100%
Fire Water Pumps 416 15-Mar-21 01-Nov-22 15.2% 100% 15% 100% 15%
Water Spray System & FF Manual Nozzeles 122 01-Dec-21 16-Oct-22 0.9% 100% 1% 100% 1%
FF Equip. (Fire Hydrants, Monitors & Sprinklers) 217 03-Oct-21 15-Mar-23 68.7% 100% 69% 85% 58%
A17200 FF Equipment - RFQ / Bidding 22 03-Oct-21 03-Nov-21 6.0% 100% 6% 100% 6%
A17210 FF Equipment - Technical Evaluation Approval 18 08-Dec-21 07-Feb-22 16.0% 100% 16% 100% 16%
A17220 FF Equipment - Financial Evaluation Approval 4 08-Feb-22 09-Mar-22 6.0% 100% 6% 100% 6%
A17230 FF Equipment - PO 5 10-Mar-22 16-Mar-22 12.0% 100% 12% 100% 12%
A17240 FF Equipment - Manufacturing 79 20-Aug-22 22-Feb-23 15.0% 100% 15% 75% 11%
A17250 FF Equipment - Inspection 1 04-Sep-22 01-Mar-23 6.0% 100% 6% 75% 5%
A17260 FF Equipment - RFS 1 11-Sep-22 08-Mar-23 18.0% 100% 18% 75% 14%
A17270 FF Equipment - Delivery @ Site 30 18-Sep-22 15-Mar-23 21.0% 100% 21% 75% 16%
Fire Fighting Valves 130 13-Dec-21 01-Feb-23 10.7% 100% 11% 95% 10%
A92340 FF Valves - RFQ / Bidding 20 13-Dec-21 10-Jan-22 6.0% 100% 6% 100% 6%
A92350 FF Valves - Technical Evaluation Approval 42 11-Jan-22 10-Mar-22 16.0% 100% 16% 100% 16%
A92360 FF Valves - Commercial Evaluation Approval 5 13-Mar-22 17-Mar-22 6.0% 100% 6% 100% 6%
A92370 FF Valves - PO 5 20-Mar-22 24-Mar-22 12.0% 100% 12% 100% 12%
A92380 FF Valves - Manufacturing 5 20-Aug-22 25-Oct-22 15.0% 100% 15% 100% 15%
A92390 FF Valves - Inspection 0 05-Sep-22 01-Nov-22 6.0% 100% 6% 100% 6%
A92400 FF Valves - RFS 0 12-Sep-22 08-Nov-22 18.0% 100% 18% 100% 18%
A92410 FF Valves - Delivery @ Site 7 15-Sep-22 01-Feb-23 21.0% 100% 21% 75% 16%
Portable Monitors 217 03-Oct-21 01-Jul-23 4.5% 100% 5% 60% 3%
Portable Monitors - RFQ / Bidding 22 03-Oct-21 03-Nov-21 6.0% 100% 6% 100% 6%
Portable Monitors - Technical Evaluation Approval 18 08-Dec-21 07-Feb-22 16.0% 100% 16% 100% 16%
Portable Monitors - Financial Evaluation Approval 4 08-Feb-22 09-Mar-22 6.0% 100% 6% 100% 6%
Portable Monitors - PO 5 10-Mar-22 16-Mar-22 12.0% 100% 12% 100% 12%
Portable Monitors - Manufacturing 79 20-Aug-22 27-May-23 15.0% 100% 15% 33% 5%
Portable Monitors - Inspection 1 22-Dec-22 03-Jun-23 6.0% 100% 6% 33% 2%
Portable Monitors - RFS 1 23-Dec-22 10-Jun-23 18.0% 100% 18% 33% 6%
Portable Monitors - Delivery @ Site 30 01-Dec-22 01-Jul-23 21.0% 100% 21% 33% 7%
Steel Structure 567 01-Sep-20 30-Apr-22 13.8% 100% 14% 100% 14%
Steel Structure for MDF Warehouse (Plot-1) 75 01-Sep-20 14-Nov-20 30.0% 100% 30% 100% 30%
Steel Structure for Matformer, Platforms & Supports (Plot-1) 81 31-Aug-21 19-Nov-21 4.0% 100% 4% 100% 4%
Steel Structure for Spare Parts WH. (Plot-1) 77 19-Jan-22 02-Apr-22 0.1% 100% 0% 100% 0%
Steel Structure for Plot-2 108 13-Jun-21 28-Sep-21 23.0% 100% 23% 100% 23%
Steel Structure for Plot (3, 4, 5 & 7) 99 01-Jul-21 07-Oct-21 30.0% 100% 30% 100% 30%
Steel Structure for Plot-6 156 18-Mar-21 20-Aug-21 6.7% 100% 7% 100% 7%
Steel Structure for Chemical Warehouse 67 11-Nov-21 17-Jan-22 1.1% 100% 1% 100% 1%
Small Power (Switches and Sockets) 172 17-Aug-21 01-Apr-22 0.2% 100% 0% 100% 0%
A17380 Capacitor Banks - RFQ / Bidding 14 19-Aug-21 07-Sep-21 6.0% 100% 6% 100% 6%
A17390 Capacitor Banks - Technical Evaluation Approval 1 24-Oct-21 24-Oct-21 16.0% 100% 16% 100% 16%
A17400 Capacitor Banks - Financial Evaluation Approval 5 25-Oct-21 31-Oct-21 6.0% 100% 6% 100% 6%
A17410 Capacitor Banks - PO 5 01-Nov-21 07-Nov-21 12.0% 100% 12% 100% 12%
A17420 Capacitor Banks - Manufacturing 69 20-Aug-22 02-May-23 15.0% 100% 15% 90% 14%
A17430 Capacitor Banks - Inspection 1 03-May-23 09-May-23 6.0% 100% 6% 0%
A17440 Capacitor Banks - RFS 1 16-May-23 16-May-23 18.0% 100% 18% 0%
A17450 Capacitor Banks - Delivery @ Site 15 17-May-23 15-Jun-23 21.0% 100% 21% 0%
Transformers 384 08-Dec-20 15-Jan-23 3.6% 100% 4% 100% 4%
AC UPS 415 08-Dec-20 15-Feb-23 2.5% 100% 3% 90% 2%
A74380 AC UPS - RFQ / Bidding 18 08-Dec-20 31-Dec-20 6.0% 100% 6% 100% 6%
A74390 AC UPS - Technical Evaluation Approval 1 16-Feb-21 16-Feb-21 16.0% 100% 16% 100% 16%
A74400 AC UPS - Financial Evaluation Approval 37 17-Feb-21 08-Apr-21 6.0% 100% 6% 100% 6%
A74360 AC UPS - PO 69 11-Apr-21 26-Jul-21 12.0% 100% 12% 100% 12%
A74410 AC UPS - Manufacturing 167 27-Jul-21 27-Apr-22 15.0% 100% 15% 100% 15%
A74420 AC UPS - Inspection 1 28-Apr-22 28-Apr-22 6.0% 100% 6% 100% 6%
A74430 AC UPS - RFS 1 29-Apr-22 29-Apr-22 18.0% 100% 18% 100% 18%
A74370 AC UPS - Delivery @ Site 15 24-Sep-22 15-Feb-23 21.0% 100% 21% 50% 11%
DC UPS 322 23-Feb-21 15-Apr-22 0.4% 100% 0% 100% 0%
Emergency Diesel Generator 384 08-Dec-20 01-Jun-23 1.5% 100% 2% 79% 1%
A17620 Generator - RFQ / Bidding 20 08-Dec-20 04-Jan-21 6.0% 100% 6% 100% 6%
A17630 Generator - Technical Evaluation Approval 1 08-Mar-21 08-Mar-21 16.0% 100% 16% 100% 16%
A17640 Generator - Financial Evaluation Approval 47 09-Mar-21 17-May-21 6.0% 100% 6% 100% 6%
A17650 Generator - PO 45 18-May-21 26-Jul-21 12.0% 100% 12% 100% 12%
A17660 Generator - Manufacturing 136 27-Jul-21 28-Apr-22 15.0% 100% 15% 100% 15%
A17670 Generator - Inspection 1 29-Apr-22 29-Apr-22 6.0% 100% 6% 100% 6%
A17680 Generator - RFS 1 30-Apr-22 30-Apr-22 18.0% 100% 18% 100% 18%
A17690 Generator - Delivery @ Site 15 03-May-23 01-Jun-23 21.0% 100% 21% 0%
Distribution Boards 270 31-May-21 01-Feb-23 1.6% 100% 1.6% 79% 1%
A17700 Distribution Boards - RFQ / Bidding 15 31-May-21 20-Jun-21 6.0% 100% 6% 100% 6%
A17710 Distribution Boards - Technical Evaluation Approval 1 20-Oct-21 20-Oct-21 16.0% 100% 16% 100% 16%
A17720 Distribution Boards - Financial Evaluation Approval 26 21-Oct-21 16-Dec-21 6.0% 100% 6% 100% 6%
A17730 Distribution Boards - PO 5 19-Dec-21 02-Feb-22 12.0% 100% 12% 100% 12%
A17740 Distribution Boards - Manufacturing 67 20-Aug-22 11-Jan-23 15.0% 100% 15% 90% 14%
A17750 Distribution Boards - Inspection 1 14-Sep-22 18-Jan-23 6.0% 100% 6% 75% 5%
A17760 Distribution Boards - RFS 1 15-Sep-22 25-Jan-23 18.0% 100% 18% 75% 14%
A17770 Distribution Boards - Delivery @ Site 15 16-Sep-22 01-Feb-23 21.0% 100% 21% 35% 7%
Lighting Poles 145 20-Sep-21 30-Sep-22 1.5% 100% 2% 100% 2%
Electrical MV, Power and Control Cables (OSBL) 150 19-Sep-21 15-Oct-22 30.1% 100% 30% 100% 30%
Cable Trays 200 15-Aug-21 15-Feb-23 7.5% 100% 8% 98% 7%
A11960 Cable Trays - RFQ / Bidding 10 15-Aug-21 26-Aug-21 6.0% 100% 6% 100% 6%
A88790 Sound Cabint & Noise Protection System - Technical Evaluation Approval 15 02-Feb-23 27-Feb-23 16.0% 100% 16% 0%
Sound Cabint & Noise Protection System - Commercial Evaluation
A88800 5 28-Feb-23 07-Mar-23 6.0% 100% 6% 0%
Approval
A88760 Sound Cabint & Noise Protection System - PO 5 08-Mar-23 15-Mar-23 12.0% 100% 12% 0%
A88810 Sound Cabint & Noise Protection System - Manufacturing 42 16-Mar-23 15-May-23 15.0% 100% 15% 0%
A88820 Sound Cabint & Noise Protection System - Inspection 1 16-May-23 16-May-23 6.0% 100% 6% 0%
Engineering (Cutting Sheets, ...) 01-Jun-21 31-Oct-21 10% 100.0% 10% 100.0% 10%
Energy Plant Ducts 01-Dec-21 16-Mar-22 15% 100.0% 15% 100.0% 15%
A75670 Fab.- Duct work from ambient air fan to mixing chamber - Group 7385.065 08-Jan-22 14-Feb-22 1.3% 100% 1% 100% 1%
A79030 Fab.- Duct work from ambient air fan to quench chamber - Group 7385.060 22-Dec-21 05-Jan-22 0.4% 100% 0% 100% 0%
A79040 Fab.- Duct work from cooling air fan to the burner - Group 7370.062 01-Dec-21 15-Feb-22 1.9% 100% 2% 100% 2%
A79050 Fab.- Duct work from mixing chamber to cyclones - Group 7385.065 08-Jan-22 14-Feb-22 1.3% 100% 1% 100% 1%
A79080 Fab.- Duct work from thermal oil heater to mixing chamber - Group 7385.065 25-Dec-21 31-Jan-22 1.3% 100% 1% 100% 1%
A79160 Fab.- Air Girder (new scope) 06-Dec-21 14-Feb-22 15.0% 100% 15% 100% 15%
A75640 Fab.- Duct work from combustion air fan to the burner - Group 7370.061 29-Jan-22 28-Feb-22 3.3% 100% 3% 100% 3%
Fab.- Duct work from the Main ID fan to Dryer Mixing Chamber - Group
A75650 29-Jan-22 28-Feb-22 8.6% 100% 9% 100% 9%
7385.090
A79060 Fab.- Duct work from the Main ID fan to Start up Stack - Group 7385.090 22-Jan-22 28-Feb-22 8.6% 100% 9% 100% 9%
A79070 Fab.- Duct work from thermal oil heater fan to mixing chamber - Group 7390 22-Jan-22 28-Feb-22 11.8% 100% 12% 100% 12%
Fab.- Duct work from thermal oil heater to thermal oil heater fan - Group
A79090 22-Jan-22 28-Feb-22 11.8% 100% 12% 100% 12%
7390
Fab.- Duct work from dust collector (Cyclones) to Ash Crews - Group
A79110 22-Jan-22 28-Feb-22 15.9% 100% 16% 100% 16%
7385.080
Fab.- Duct work from dust collector (Cyclones) to Main ID fan - Group
A79120 30-Dec-21 06-Feb-22 15.9% 100% 16% 100% 16%
7385.080
A79100 Fab.- Transport pipes ducts for dust - Group 7370 26-Jan-22 14-Feb-22 2.8% 100% 3% 100% 3%
A75390 Fab.- Pneumatic Supports - Group 2600 15-Feb-22 16-Mar-22 28.6% 100% 29% 100% 29%
A75490 Fab.- Silencer - Group 4200 30-Dec-21 30-Jan-22 9.8% 100% 10%
OSBL - Tanks 31-Aug-21 27-Mar-22 3% 100% 3% 100% 3%
A76020 Pre-Fabrication Industrial Raw Water Tanks (101) 31-Aug-21 28-Feb-22 33.2% 100% 33% 100% 33%
A76030 Pre-Fabrication Demi Water Tanks (103) 31-Aug-21 28-Feb-22 15.2% 100% 15% 100% 15%
A76040 Pre-Fabrication Process Water Tanks (102) 31-Aug-21 28-Feb-22 21.7% 100% 22% 100% 22%
A76070 Pre-Fabrication Fire Water Tanks 23-Jan-22 27-Mar-22 29.9% 100% 30% 100% 30%
A82890 SR01A - Civil - Raised Floor 12 20-Apr-22 30-May-22 11% 100% 11%
A80840 SR01A - Civil - Doors Fab. & Erection 6 31-May-22 13-Jun-22 7% 100% 7% 80% 5%
SR01B ( Plot-5) 121 04-Oct-21 13-Jun-22 12% 100.0% 11.8% 84.7% 10%
A80850 SR01B - Civil - Concrete Works 24 04-Oct-21 02-Nov-21 28% 100% 28% 100.0% 28%
A80860 SR01B - Civil - Finishing Works 45 08-Feb-22 30-Apr-22 50% 100% 50% 100% 50%
A83690 SR01B - Civil - Raised Floor 12 20-Apr-22 30-May-22 14% 100% 14%
A80870 SR01B - Civil - Doors Fab. & Erection 6 31-May-22 13-Jun-22 8% 100% 8% 80% 7%
SR03 ( LV32 - TR32) 121 21-Dec-21 13-Jun-22 9% 100.0% 9.1% 80.0% 7%
A80880 SR03 - Civil - Concrete Works 24 21-Dec-21 17-Jan-22 6% 100% 6% 100.0% 6%
A80890 SR03 - Civil - Finishing Works 45 08-Feb-22 31-Mar-22 65% 100% 65% 100% 65%
A83710 SR03 - Civil - Raised Floor 12 10-May-22 06-Jun-22 18% 100% 18%
A80900 SR03 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 11% 100% 11% 80% 9%
SR04 ( LV42 - TR42) & ( LV43 - TR43) 121 02-Oct-21 13-Jun-22 9% 100.0% 9.1% 80.0% 7%
A80910 SR04 - Civil - Concrete Works 24 21-Dec-21 17-Jan-22 6% 100% 6% 100.0% 6%
A80920 SR04 - Civil - Finishing Works 45 08-Feb-22 31-Mar-22 65% 100% 65% 100% 65%
A83730 SR04 - Civil - Raised Floor 12 17-May-22 06-Jun-22 18% 100% 18%
A80930 SR04 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 11% 100% 11% 80% 9%
SR02A ( LV22 - TR22) 121 04-Oct-21 13-Jun-22 18% 100.0% 18.5% 90.2% 17%
A80940 SR02A - Civil - Concrete Works 24 04-Oct-21 02-Nov-21 54% 100% 54% 100.0% 54%
Page 178 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A80950 SR02A - Civil - Finishing Works 45 13-Feb-22 05-Apr-22 32% 100% 32% 100% 32%
A83750 SR02A - Civil - Raised Floor 12 24-May-22 06-Jun-22 9% 100% 9%
A80960 SR02A - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 5% 100% 5% 80% 4%
SR02B ( LV21 - TR21) & ( LV23 - TR23) 140 06-Sep-21 13-Jun-22 14% 100.0% 13.7% 86.8% 12%
A80970 SR02B - Civil - Concrete Works 24 06-Sep-21 03-Oct-21 38% 100% 38% 100.0% 38%
A80980 SR02B - Civil - Finishing Works 45 20-Feb-22 12-Apr-22 43% 100% 43% 100% 43%
A83770 SR02A - Civil - Raised Floor 12 31-May-22 13-Jun-22 12% 100% 12%
A80990 SR02B - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 7% 100% 7% 80% 6%
SR02C ( Plot-2) 121 23-Sep-21 13-Jun-22 12% 100.0% 11.7% 84.5% 10%
A81000 SR02C - Civil - Concrete Works 24 23-Sep-21 23-Oct-21 27% 100% 27% 100.0% 27%
A81010 SR02C - Civil - Finishing Works 45 19-Feb-22 19-Apr-22 51% 100% 51% 100% 51%
A83790 SR02C - Civil - Raised Floor 12 31-May-22 13-Jun-22 14% 100% 14%
A81020 SR02C - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 8% 100% 8% 80% 7%
SR22 (plot-2) 121 23-Sep-21 13-Jan-22 12% 100.0% 11.7% 84.5% 10%
A81030 SR22 - Civil - Concrete Works 24 23-Sep-21 23-Oct-21 27% 100% 27% 100.0% 27%
A81040 SR22 - Civil - Finishing Works 45 19-Feb-22 27-Apr-22 51% 100% 51% 100% 51%
A83810 SR22 - Civil - Raised Floor 12 31-May-22 13-Jun-22 14% 100% 14%
A81050 SR22 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 8% 100% 8% 80% 7%
Glue Storage Shed (Plot-7) 36 29-Aug-21 10-Oct-21 0% 100% 0% 100% 0%
A84520 Glue Storage Shed - Civil - Concrete Works 36 29-Aug-21 10-Oct-21 100% 100% 100% 100.0% 100%
Steel Structure Erection Works 312 23-Feb-21 17-Jul-22 12.0% 100.0% 12.0% 85.9% 10%
ISBL - Production Line 57 23-Feb-21 17-Jul-22 71% 100% 71% 97% 69%
Plot-1 391 23-02-21 14-06-22 35.6% 100.00% 35.64% 99.07% 35.31%
A7570 primary Warehouse For Final Product 23-Feb-21 18-Apr-21 85% 100% 85% 100.0% 85%
Page 179 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A7580 Warehouse For Final Product (remaining) 26-May-21 21-Oct-21 1% 100% 1% 100.0% 1%
SPARE PARTS FOR FINAL PRODUCTION
A86690 20-Dec-21 05-Jan-22 3% 100% 3% 95.9% 2%
WAREHOUSE
A85930 Supporting Outlet Tube Above Fan 5910 19-Mar-22 19-May-22 1% 100% 1% 90.0% 0%
A85950 Service Collector Pneumatic 5910 02-Mar-22 13-Mar-22 0% 100% 0% 100.0% 0%
A85960 Platform of Gripper Carriage 12-Mar-22 24-Mar-22 0% 100% 0% 87.5% 0%
A85970 Platform 1 Inside Production Warehouse 07-Apr-22 07-Jun-22 0% 100% 0% 87.5% 0%
A85980 Platform 2 Inside Production Warehouse 19-Apr-22 29-May-22 0% 100% 0% 80.0% 0%
A85990 Platform 3 Inside Production Warehouse 07-May-22 19-May-22 0% 100% 0% 87.5% 0%
A86000 Platform 4 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0% 80.0% 0%
A86010 Platform 5 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0% 66.7% 0%
A86000 Platform 6 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0%
A86010 Platform 7 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0%
A86020 Press Steel Support 16-May-22 29-May-22 0% 100% 0%
A86030 Hit Bumpers 17-Mar-22 30-Mar-22 0% 100% 0% 100.0% 0%
A86040 Pump Room Steel Supports 18-May-22 14-Jun-22 1% 100% 1% 100.0% 1%
A86720 Steel Stair for Mat Reject Tunnel 18-May-22 14-Jun-22 0% 100% 0% 50.0% 0%
A86050 Matformer (01st. Part) 18-May-22 14-Jun-22 2% 100% 2% 100.0% 2%
A86051 Matformer (02nd. Part) 18-May-22 14-Jun-22 6% 100% 6% 97.6% 6%
Plot-2 204 14-12-21 14-07-22 22.5% 100.00% 22.55% 95.56% 21.55%
A86110 Sifting Tower 2051 (01st. Part) 14-Nov-21 24-Mar-22 20% 100% 20% 100.0% 20.2%
A86111 Sifting Tower 2051 (02nd. Part) 15-Feb-22 09-Mar-22 28% 100% 28% 91.7% 26%
STEEL HOUSING FOR SUPPROTING BELT
A86070 08-Mar-22 23-Mar-22 7% 100% 7% 100.0% 7%
(SIFTER AREA)
A86080 PLATFORMS ABOVE FANS (SIFTER AREA) 12-Feb-22 17-Feb-22 3% 100% 3% 95.1% 3%
Page 180 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A86090 SERVICE PLATFORM 2591 (SIFTER AREA) 12-Feb-22 17-Feb-22 0% 100% 0% 100.0% 0%
A86100 Dryer 64m (01st Part) 02-Mar-22 27-Apr-22 5% 100% 5% 100.0% 5%
A89760 Dryer 64m (02nd. Part) 04-Apr-22 07-May-22 6% 100% 6% 94.9% 6%
A86120 PIPE BRIDGE STEAM‐PIPE ITEM 7021. 22-Mar-22 07-Apr-22 5% 100% 5% 100.0% 5%
A86130 PIPE BRIDGE STEEL STRUCTURE 04-Apr-22 07-May-22 3% 100% 3% 86.8% 3%
A86140 SERVICE PLATFORM FOR CONVEYOR 2781. 04-Apr-22 09-May-22 0% 100% 0% 100.0% 0%
A86150 STEEL PIPE RACK FOR PNEUMATIC 4946. 04-Apr-22 07-May-22 1% 100% 1% 100.0% 1%
A86160 STEEL STR FOR FILTER 4911 AND 4947. 06-Apr-22 02-Jun-22 1% 100% 1% 84.6% 1%
A86170 FILTER SFDT 0512‐D‐01.. 02-May-22 08-Jun-22 0% 100% 0% 50.0% 0%
A86180 Bridge 1 to Pneumatic 2615 22-May-22 07-Jun-22 1% 100% 1% 100.0% 1%
A86190 Pipe Rack For Crude Gas Duct SENA11 25-May-22 11-Jun-22 2% 100% 2% 90.0% 1%
A86200 Platform for cyclone 4910 30-May-22 15-Jun-22 7% 100% 7% 98.8% 7%
A86210 Platform for Pneumatic 4976 02-Jun-22 19-Jun-22 0% 100% 0% 66.7% 0%
A86060 St. Str. for Sifter (01st. Part - Main Str.) 23-Jun-22 11-Jul-22 2% 100% 2% 100.0% 2%
A86061 St. Str. for Sifter (02nd. part - Other Str.) 09-Jul-22 14-Jul-22 8% 100% 8% 92.7% 7%
Plot-3 184 30-10-21 04-06-22 6.3% 100.0% 6.29% 97.7% 6.15%
A86220 Fuel Gas Cleaning (01st Part) 31-Oct-21 02-Jan-22 26% 100% 26% 100.0% 26%
A86221 Fuel Gas Cleaning (02nd. Part) 25-Dec-21 29-Jan-22 7% 100% 7% 95.8% 7%
A86230 Fuel Gas Cleaning St-Supports 30-Oct-21 02-Jan-22 1% 100% 1% 100.0% 1%
A86240 Thermal Oil Heating (1st.part) 03-Jan-22 16-Jan-22 14% 100% 14% 100.0% 14%
A86241 Thermal Oil Heating (2nd.part) 02-Jan-22 08-Jan-22 20% 100% 20% 97.1% 19%
A86250 Pipe Bridge Steel Structure 2782 17-Feb-22 21-Mar-22 11% 100% 11% 97.4% 11%
A86260 Steel Structure for Pneumatic 2785 26-Apr-22 04-Jun-22 8% 100% 8% 92.6% 7%
A89820 Platforms & Walkways 28-Mar-22 13-Apr-22 7% 100% 7% 95.7% 6%
Page 181 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A89840 Burner Housing 02-Jun-22 08-Jun-22 7% 100% 7% 95.7% 6%
Plot-4 162 12-02-22 13-06-22 14.6% 100.00% 14.60% 96.15% 14.04%
A86330 Warehouse For Refinery Building (1st. Part) 12-Feb-22 26-Mar-22 19% 100% 19% 100.0% 19%
A86331 Warehouse For Refinery Building (2nd. Part) 06-Apr-22 11-May-22 11% 100% 11% 84.5% 9%
A86340 Pipe Rack For Refiner 06-Apr-22 30-Apr-22 1% 100% 1% 100.0% 1%
A86350 Refinery Structure 06-Apr-22 23-May-22 38% 100% 38% 99.0% 37%
A86270 PIPE RACK FOR PENUMATIC 4970 & 5920 16-Feb-22 14-May-22 3% 100% 3% 68.2% 2%
A86280 CONVEYOR 1557 END SUPPORT STRUCTURE 27-Mar-22 14-May-22 2% 100% 2% 90.0% 2%
A86290 STEEL PLATFORMS FOR FILTER AREA 5091 27-Mar-22 14-May-22 4% 100% 4% 96.7% 4%
A86300 STEEL STRUCTURE FOR CONVEYOR 1557 27-Mar-22 14-May-22 4% 100% 4% 93.9% 4%
A86310 STEEL STRUCTURE FOR CONVEYOR 1555 10-Apr-22 15-May-22 4% 100% 4% 97.1% 4%
A86320 STORAGE BIN 20-Apr-22 09-May-22 11% 100% 11% 100.0% 11%
A86360 STEEL STRUCTURE FOR CONVEYOR 1394 08-May-22 06-Jun-22 2% 100% 2% 94.7% 2%
Plot-5 162 15-01-22 23-06-22 5.6% 100.00% 5.64% 99.68% 5.62%
SIFTING & PLATFORMS G.1031-STRAW MILLING
A86380 G1021 15-Jan-22 12-Feb-22 25.8% 100% 26% 100.0% 26%
(1st part)
SIFTING & PLATFORMS G.1031-STRAW MILLING
A86370 09-Feb-22 03-Mar-22 61.3% 100% 61% 100.0% 61%
G1021
A86390 Service Platform For TKF1398 15-Feb-22 09-Mar-22 0.6% 100% 1% 50.0% 0%
A86400 PIPE RACK FROM PLOT4 TO PLOT5 15-Jan-22 12-Feb-22 3.5% 100% 4% 100.0% 4%
A86410 G.1031 Steel Supports Through Scraper Conveyor 1392 13-Feb-22 09-Apr-22 0.6% 100% 1% 100.0% 1%
A86420 G.1031 & G.1021 STEEL SUPPORTS 13-Feb-22 09-Apr-22 8.1% 100% 8% 100.0% 8%
Plot-6 127 02-10-21 03-03-22 6.6% 100.00% 6.64% 100.00% 6.64%
A86430 St. Str. Erec. - Straw Preparation Building 41 02-Oct-21 21-Nov-21 97.8% 100% 98% 100.0% 98%
Page 182 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A86450 St. Str. Erec. - Straw Pneumatics Drawings 41 03-Oct-21 21-Nov-21 2.2% 100% 2% 100.0% 2%
A86470 Dryer Mixing Chamber (1st. Part) 19-Mar-22 07-Apr-22 7.3% 100% 7% 100.0% 7%
A86471 Dryer Mixing Chamber (2nd. Part) 19-Mar-22 31-Mar-22 6.7% 100% 7% 81.8% 5%
A86500 Steel Structure for Pump Room 19-Mar-22 31-Mar-22 15.8% 100% 16% 92.3% 15%
A86560 5911‐FILTER SFDW 05&12‐D‐07 17-May-22 29-May-22 10% 100% 10% 75.0% 8%
A91800 PLATFORMS FOR SILOS 17-May-22 29-May-22 54% 100% 54% 95.2% 51%
Other 26-04-22 14-07-22 4.9% 100.00% 4.95% 83.90% 4.15%
A7586 MDF‐LIQUID CHEMICAL SHED 26-Apr-22 28-May-22 18% 100% 18% 100.0% 18%
A91730 GENERATOR SHED 04-Jul-22 14-Jul-22 3% 100% 3%
A72970 Car Parking Shed 04-Jul-22 14-Jul-22 7% 100% 7% 100.0% 7%
A72790 Industrial Pump Shed 26-Apr-22 28-May-22 6% 100% 6% 100.0% 6%
Page 183 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A72930 POTABLE WATER PUMP HOUSE 04-Jul-22 14-Jul-22 3% 100% 3% 100.0% 3%
A91780 3 NEW PIPE RACKS 04-Jul-22 14-Jul-22 5% 100% 5% 100.0% 5%
New Fire Truck HSE Shed 26-Apr-22 28-May-22 3% 100% 3% 100.0% 3%
A7585 Fire Pump Shed 04-Jul-22 14-Jul-22 4% 100% 4% 100.0% 4%
A72820 Reject Water Shed 04-Jul-22 14-Jul-22 3% 100% 3% 100.0% 3%
New Water Treatment Shed 26-Apr-22 28-May-22 14% 100% 14% 100.0% 14%
A72900 Compressor Shed 04-Jul-22 14-Jul-22 8% 100% 8% 100.0% 8%
A91760 Transformer Sheds 04-Jul-22 14-Jul-22 4% 100% 4% 60.0% 3%
New MDF Main Gate 04-Jul-22 14-Jul-22 11% 100% 11% 100.0% 11%
New RC Building Platform & Ladder 04-Jul-22 14-Jul-22 1% 100% 1%
New Pits Covers (Chemical & Reject) 04-Jul-22 14-Jul-22 3% 100% 3% 12.5% 0%
New Sound Cabinet for G.4550 04-Jul-22 14-Jul-22 3% 100% 3%
New Loading Arm for PMDI 04-Jul-22 14-Jul-22 5% 100% 5%
Cladding Works 371 19-Apr-21 17-Jul-22 16% 100% 16% 82% 13%
A72990 Cladding Works - Primary MDF Warehouse (Plot-1) 79 19-Apr-21 31-Jul-21 25% 100% 25% 100.0% 25%
A73000 Cladding Works - Final MDF Warehouse (Plot-1) 66 23-Oct-21 07-Jan-22 34% 100% 34% 98.7% 33%
A86600 Cladding Works - (Plot-6) 40 22-Nov-21 07-Jan-22 13% 100% 13% 100.0% 13%
A89670 Cladding Works - (Plot-3) 20 06-Apr-22 30-Apr-22 0% 100% 0%
A86630 Cladding Works - Glue Storage Shed (Plot-7) 20 18-Apr-22 16-May-22 0% 100% 0%
A86620 Cladding Works - Pump Room Warehouse (Plot-7) 32 10-May-22 15-Jun-22 1% 100% 1%
A86590 Cladding Works - (Plot-4) 32 15-May-22 20-Jun-22 11% 100% 11% 28.1% 3%
A86700 Cladding Works - Warehouse For Spare Parts (Plot-1) 32 11-Jun-22 18-Jul-22 2% 100% 2%
A89880 Re-Instatement & Touch Up - ISBL 31 12-Jun-22 06-Aug-22 50% 100% 50%
Page 186 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Electrical Works 220 09-Oct-21 06-Aug-22 9% 100.0% 9.0% 78.4% 7%
Electrical Works - ISBL 172 24-Jan-22 04-Aug-22 32% 100% 32% 86% 27%
A83660 Cable Trays Supports Fab. & Erection 64 24-Jan-22 02-Mar-22 5% 100% 5% 100.0% 5%
A16480 Cable Trays Installation (ISBL) 84 03-Mar-22 21-Jul-22 22% 100% 22% 89.4% 20%
A16490 Cable Pulling (ISBL) 84 10-Mar-22 28-Jul-22 58% 100% 58% 88.6% 52%
A16510 Termination (ISBL) 84 17-Mar-22 04-Aug-22 15% 100% 15% 67% 10%
Lighting & Small Power System 179 05-Feb-22 06-Aug-22 46% 100% 46% 64% 29%
A83670 Cable Trays Supports Fab. & Erection 64 05-Feb-22 05-Apr-22 1% 100% 1% 100% 1%
A16500 Cable Trays Installation (Lighting - ISBL) 72 16-Feb-22 09-Jun-22 10% 100% 10% 98% 9%
A80770 Lighting Fixtures Erection (ISBL) 72 27-Mar-22 19-Jul-22 12% 100% 12% 39% 5%
A80770 JB-Lighting (ISBL) 72 27-Mar-22 19-Jul-22 8% 100% 8% 27% 2%
A80780 Wire Pulling (outdoor - ISBL) 72 06-Mar-22 27-Jun-22 20% 100% 20% 79% 16%
A80790 SW & Sockets 72 23-Mar-22 16-Jul-22 4% 100% 4% 45% 2%
A80790 Galvanized Conduit 72 23-Mar-22 16-Jul-22 17% 100% 17% 86% 15%
A80800 Termination (Iighting-ISBL) 72 13-Apr-22 06-Aug-22 29% 100% 29% 51% 15%
Earthing Works 121 09-Oct-21 24-Jul-22 5% 100% 0.1 93% 5%
A16470 Earthing - Rods Installation 30 09-Oct-21 18-Dec-21 7% 100% 7% 54% 3%
A79410 Earthing - Cable Laying 85 09-Oct-21 03-Apr-22 64% 100% 64% 95% 61%
A79430 Earthing - Bars & Welding Point Installation 85 19-Dec-21 18-Jun-22 17% 100% 17% 97% 17%
A79420 Earthing - Termination 85 23-Jan-22 24-Jul-22 12% 100% 12% 93% 11%
Emergency Power Generator 77 02-Mar-22 23-May-22 0% 100% 0%
A79500 Emergency Diesel Generator Installation 6 16-Mar-22 29-Mar-22 100% 100% 100%
A80060 Cable Pulling (EMG42 & LV42/ SR04) 12 02-Mar-22 29-Mar-22 100%
A80070 Termination (EMG42 & LV42/ SR04) 12 20-Apr-22 23-May-22 100%
Page 187 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Switch Rooms & Local Pannels 100 15-Feb-22 13-Jun-22 17% 100% 17% 99% 17%
SR01A ( LV12 - TR12) 58 26-Feb-22 19-Apr-22 12% 100.0% 12.4% 100.0% 12%
A91810 SR01A - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 84% 100% 84% 100% 84%
A82880 SR01A - Cable Trays 12 02-Mar-22 15-Mar-22 100%
A79820 SR01A - LV12 & Bus Duct Installation 18 14-Mar-22 27-Mar-22 14% 100% 14% 100% 14%
A79820 SR01A - TR12 18 14-Mar-22 27-Mar-22 2% 100% 2% 100% 2%
A79830 SR01A - Cable Pulling 12
A79840 SR01A - Termination 18
SR01B ( LV13 - TR13) 58 26-Feb-22 27-Apr-22 12% 100.0% 11.5% 100.0% 12%
A91820 SR01B - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 90% 100% 90% 100% 90%
A83680 SR01B - Cable Trays 12 02-Mar-22 13-Mar-22 100%
A80000 SR01B - LV13 & Bus Duct Installation 18 16-Mar-22 29-Mar-22 8% 100% 8% 100% 8%
A80000 SR01B - TR13 18 16-Mar-22 29-Mar-22 2% 100% 2% 100% 2%
A80010 SR01B - Cable Pulling 12 14-Mar-22 29-Mar-22 100% 15%
A80020 SR01B - Termination 18 30-Mar-22 27-Apr-22 100%
SR03 ( LV32 - TR32) 58 09-Mar-22 09-May-22 12% 100.0% 11.7% 100.0% 12%
A91830 SR03 - Steel Frames Fab. & Erection 12 09-Mar-22 17-Mar-22 89% 100% 89% 100% 89%
A83700 SR03 - Cable Trays 12 10-Mar-22 20-Mar-22 100%
A79850 SR03 - LV32 & Bus Duct Installation 18 19-Mar-22 31-Mar-22 9% 100% 9% 100% 9%
A79850 SR03 - TR32 18 19-Mar-22 31-Mar-22 2% 100% 2% 100% 2%
A79860 SR03 - Cable Pulling 12 21-Mar-22 05-Apr-22 100%
A79870 SR03 - Termination 18 06-Apr-22 09-May-22 100%
SR04 ( LV42 - TR42) & ( LV43 - TR43) 58 13-Mar-22 16-May-22 14% 100.0% 14.1% 100.0% 14%
A91840 SR04 - Steel Frames Fab. & Erection 12 13-Mar-22 26-Mar-22 74% 100% 74% 100% 74%
Page 188 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83720 SR04 - Cable Trays 12 14-Mar-22 24-Mar-22 100%
SR04 - LV42 / LV43 & UPS42 / UPS 43 & Bus Duct
A79880 18 30-Mar-22 12-Apr-22 23% 100% 23% 100% 23%
Installation
A79880 SR04 - TR42 / TR43 18 30-Mar-22 12-Apr-22 3% 100% 3% 100% 3%
A79890 SR04 Cable Pulling 12 26-Mar-22 12-Apr-22 100%
A79900 SR04 - Termination 18 13-Apr-22 16-May-22 100%
SR02A ( LV22 - TR22) 58 26-Feb-22 23-May-22 12% 100.0% 12.0% 98.9% 12%
A91850 SR02A - Steel Frames Fab. & Erection 12 26-Feb-22 24-Mar-22 87% 100% 87% 100% 87%
A83740 SR02A - Cable Trays 12 21-Mar-22 31-Mar-22 100%
A79910 SR02A - MV20 / LV22 & Bus Duct Installation 18 06-Apr-22 19-Apr-22 11% 100% 11% 90% 10%
A79940 SR02B - LV21 / LV23 & Bus Duct Installation 18 06-Apr-22 19-Apr-22 9% 100% 9% 100% 9%
A83400 ISBL - Fire Alarm - Cable Trays Supports Fab. & Erection 42 23-Jan-22 27-Feb-22 4% 100% 4% 100% 4%
A83410 ISBL - Fire Alarm - Cable Trays Installation 42 28-Feb-22 14-Apr-22 6% 100% 6% 100% 6%
A83420 ISBL - Fire Alarm - JB's Installation 42 28-Feb-22 14-Apr-22 3% 100% 3%
A83430 ISBL - Fire Detectors Installation 42 28-Feb-22 14-Apr-22 20% 100% 20% 22% 4%
A83440 ISBL - Fire Alarm - Cable Pulling 42 14-Mar-22 22-May-22 29% 100% 29% 55% 16%
A83450 ISBL - Fire Alarm - Termination 37 23-May-22 26-Jul-22 38% 100% 38%
Public Address System 104 16-Jan-22 28-Jul-22
ISBL - Public Adress - Cable Trays Supports Fab. &
A83460 40 16-Jan-22 03-Mar-22 100%
Erection
A83470 ISBL - Public Adress - Cable Trays Installation 40 05-Mar-22 19-Apr-22 100%
A83480 ISBL - Public Adress - JB's Installation 40 05-Mar-22 18-May-22 100%
A83490 ISBL - Public Adress - Speakers & Flashers Installation 40 05-Mar-22 18-May-22 100%
A83500 ISBL - Public Adress - Cable Pulling 40 16-Apr-22 29-Jun-22 100%
A83510 ISBL - Public Adress - Termination 40 19-May-22 28-Jul-22 100%
CCTV System 104 24-Mar-22 21-Jul-22 4% 100% 4% 50% 2%
A83520 ISBL - CCTV - Cable Trays Supports Fab. & Erection 40 24-Mar-22 15-May-22 19% 100% 19% 100% 19%
Page 191 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83540 ISBL - CCTV - JB's Installation 40 24-Mar-22 15-May-22 5% 100% 5%
A83530 ISBL - CCTV - Cable Trays Installation 40 07-Apr-22 29-May-22 29% 100% 29% 100% 29%
A83560 ISBL - CCTV - Cable Pulling 40 30-Apr-22 19-Jun-22 33% 100% 33% 5% 2%
A83550 ISBL - CCTV - Camera Installation 40 15-May-22 29-Jun-22 3% 100% 3%
A83570 ISBL - CCTV - Termination 40 05-Jun-22 21-Jul-22 11% 100% 11%
Data Network & IP Telephone-1 104 02-Apr-22 05-Jul-22
ISBL - Data Network & IP Telephone - Cable Trays
A83580 40 02-Apr-22 30-Apr-22 100%
Supports Fab. & Erection
ISBL - Data Network & IP Telephone - Cable Trays
A83590 40 16-Apr-22 06-Jun-22 100%
Installation
A83600 ISBL - Data Network & IP Telephone - JB's Installation 40 30-Apr-22 19-Jun-22 100%
ISBL - Data Network & IP Telephone - IP Telephone
A83610 40 30-Apr-22 19-Jun-22 100%
Installation
A83620 ISBL - Data Network & IP Telephone - Cable Pulling 40 02-May-22 20-Jun-22 100%
A83630 ISBL - Data Network & IP Telephone - Termination 40 19-May-22 05-Jul-22 100%
ISBL - F&G 139 16-Apr-22 04-Aug-22 0% 100.0% 0.5% 64.6% 0%
A83640 ISBL - F&G - Cable Trays Supports Fab. & Erection 46 16-Apr-22 01-Jun-22 26% 100% 26% 100% 26%
A79720 ISBL - F&G - Cable Trays 60 02-Jun-22 14-Jul-22 39% 100% 39% 100% 39%
A79730 ISBL - F&G - J.B's & Local Pannels 60 02-Jun-22 14-Jul-22 3% 100% 3%
A83650 ISBL - F&G - Detectors 60 02-Jun-22 14-Jul-22 2% 100% 2%
A79740 ISBL - F&G - Cable Pulling 60 16-Jun-22 28-Jul-22 21% 100% 21%
A79750 ISBL - F&G - Terminations 60 23-Jun-22 04-Aug-22 10% 100% 10%
HVAC 64 02-Feb-22 02-Aug-22 0% 100.0% 0.4% 49.0% 0%
A7550 HVAC - Prod. Line 64 02-Feb-22 02-Aug-22 100% 100% 100% 49% 49%
Fire- Fighing 108 02-Apr-22 06-Aug-22 0% 100.0% 0.3% 35.0% 0%
A78070 Fire Fighting Erection - Production Line 108 02-Apr-22 06-Aug-22 100% 100% 100% 35% 35%
Page 192 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Insulation 62 19-Mar-22 30-May-22 1.1% 100.0% 1.1% 42.4% 0%
A12860 Insulation PO & Delivery @ Site 30 30-Dec-21 23-Mar-22 40% 100% 40% 100% 40%
A80590 Thermal Insulation application 30 21-May-22 02-Jun-22 60% 100% 60% 4% 2%
A80640 Thermal Insulation application 30 03-Jul-22 07-Aug-22 100%
A80650 Thermal Insulation application 30 03-Jul-22 07-Aug-22 100%
Prod. Line Installation 140 17-Jan-22 06-Sep-22 27% 100.0% 26.8% 84.3% 23%
Prod. Line Installation (EP-Contractor Scope of Delivery) 179 17-Jan-22 06-Sep-22 84.3% 100.0% 84% 86.6% 73%
Overhead Crane 26 14-Mar-22 12-Apr-22 0.4% 100.0% 0% 100% 0%
A73130 Erection- Overhead Cranes 26 14-Mar-22 12-Apr-22 100% 100% 100% 100% 100%
Duct Work & Inspection Door 191 01-Feb-22 15-Aug-22 13.0% 100.0% 13% 83% 11%
Erection - Duct Works & exhaust Pipes - Chipper Line (1) -
n 36 26-Mar-22 17-Apr-22 2% 100% 2% 97% 2%
Group 1242 &1243
Erection - Pipe ducts with bends and flanges - Group 1321 /
40 05-Apr-22 28-Apr-22 2% 100% 2% 100% 2%
n 1331 / 1341
Erection - Pipe ducts with bends and flanges - Group 1531 40 06-Apr-22 30-Apr-22 1% 100% 1% 100% 1%
n
Fab.- Chutes, Doors & loose items - Group 2300 40 10-Apr-22 08-May-22 8% 100% 8% 59% 5%
n
Erection - Dryer Duct (From Dryer to High Efficiency
40 11-Apr-22 09-May-22 9% 100% 9% 100% 9%
n Cyclone) - Group 2420
Erection - Pipe ducts with bends and flanges - Group 2531 /
52 26-Apr-22 28-Jun-22 4% 100% 4% 100% 4%
n 2532 / 2533 / 2534
Fab.- Pneumatic Supports - Group 2600 52 07-May-22 05-Jul-22 4% 100% 4% 100% 4%
n
Erection - Duct Works & Pipes with bends and flanges -
52 02-May-22 04-Jul-22 10% 100% 10% 99% 10%
n Group 2615 / 2616
Erection - Pipe ducts with bends and flanges - Group 2770 /
48 02-May-22 27-Jun-22 3% 100% 3% 84% 3%
n 2780 / 2782 / 2785
Erection - Pipe ducts with bends and flanges - Group 3905 30 25-May-22 09-Jul-22 2% 100% 2% 48% 1%
n
Page 193 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Fab.- Silencer - Group 4200 24 06-Jun-22 23-Jul-22 1% 100% 1%
n
Erection - Duct Work, Pipes & Hoods - Group 4550 30 19-Jun-22 04-Aug-22 5% 100% 5% 98% 5%
n
Erection - Duct Work & Pipes - Group 4910 / 4920 / 4946 /
48 20-Jun-22 01-Aug-22 17% 100% 17% 78% 13%
n 4970 / 4975
Erection - Pipe ducts with bends and flanges - Group 5910 /
48 20-Jun-22 01-Aug-22 8% 100% 8% 85% 7%
n 5917 / 5920
Erection - Pipe ducts with bends and flanges - Group 7112 /
48 20-Jun-22 01-Aug-22 0% 100% 0% 48% 0%
n 7131
Erection - Duct work from combustion air fan to the burner -
48 20-Jun-22 31-Jul-22 0% 100% 0% 81% 0%
n Group 7370.061
Erection - Duct work from the Main ID fan to Dryer Mixing
24 21-Jun-22 01-Aug-22 1% 100% 1% 95% 1%
n Chamber - Group 7385.090
Erection - Crude gas duct - Group 7410 24 23-Jun-22 06-Aug-22 7% 100% 7% 79% 6%
n
Erection - Duct work from ambient air fan to mixing
24 02-Jul-22 13-Aug-22 0% 100% 0% 50% 0%
n chamber - Group 7385.065
Erection - Duct work from ambient air fan to quench
24 02-Jul-22 24-Jul-22 0% 100% 0% 100% 0%
n chamber - Group 7385.060
Erection - Duct work from cooling air fan to the burner -
40 06-Jul-22 19-Jul-22 0% 100% 0%
n Group 7370.062
Erection - Duct work from mixing chamber to cyclones -
40 10-Jul-22 23-Jul-22 0% 100% 0% 50% 0%
n Group 7385.065
Erection - Duct work from the main id fan to start up stack -
40 11-Jul-22 10-Aug-22 1% 100% 1% 95% 1%
n Group 7385.090
Erection - Duct work from thermal oil heater fan to mixing
40 11-Jul-22 15-Aug-22 2% 100% 2% 60% 1%
n chamber - Group 7390
Erection - Duct work from thermal oil heater to mixing
n 29 13-Jul-22 04-Aug-22 0% 100% 0% 50% 0%
chamber - Group 7385.065
Erection - Duct work from thermal oil heater to thermal oil
40 19-Jul-22 01-Aug-22 2% 100% 2% 60% 1%
n heater fan - Group 7390
Erection - Transport pipes ducts for dust - Group 7370 40 19-Jul-22 01-Aug-22 0% 100% 0%
n
Page 194 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Erection - Duct work from dust collector (Cyclones) to Ash
2 13-Mar-22 21-May-22 2% 100% 2% 100% 2%
n Crews - Group 7385.080
Erection - Duct work from dust collector (Cyclones) to Main
2 13-Mar-22 21-May-22 2% 100% 2% 75% 2%
n ID fan - Group 7385.080
Erection - Duct work from mixing chamber to the dust
1 01-Feb-22 03-Feb-22 100%
n collector - Group 7385.060
Erection - Duct Works & exhaust Pipes - Chipper Line (3) -
1 05-Feb-22 05-Feb-22 2% 100% 2% 97% 2%
n Group 1282 &1283
Erection - Duct Work & Pipes - Group 4998 / 4999 3 23-Feb-22 26-Feb-22 100%
n
Fab.- Air Girder (new scope) 6 23-Feb-22 26-Feb-22 2% 100% 2% 65% 1%
n
Erection - Duct Works & exhaust Pipes - Chipper Line (2) -
3 05-Mar-22 07-Mar-22 2% 100% 2% 97% 2%
n Group 1262 &1263
Erection - Duct work - lower section with transition duct -
3 05-Mar-22 07-Mar-22 100%
n Group 7390
Erection - Duct work - outlet duct with vertical flanges to
3 05-Mar-22 07-Mar-22 100% 100%
n dust collector - Group 7390
Safety Barriers & Fence 129 16-Apr-22 04-Jul-22 1.1% 100.0% 1%
A76810 Erection - Fences for drive station 65 16-Apr-22 11-Jun-22 20% 100% 20%
A76820 Erection - Fences for the Forming line 78 16-Apr-22 03-Jul-22 28% 100% 28%
A76840 Erection - Fences for Trimming Saw 40 16-Apr-22 10-May-22 8% 100% 8%
A80450 Erection - Fence for prepress 32 16-Apr-22 02-May-22 6% 100% 6%
A80460 Erection - Fence for intermediate belt station 75 16-Apr-22 21-Jun-22 24% 100% 24%
Erection- Electrical secured accesses door and flaps - GR-
A80620 22 30-May-22 04-Jul-22 14% 100% 14%
4599
Sound Cabient & Noise Protection Erection 129 01-Apr-22 13-Jul-22 1.2% 100.0% 1%
000443 Noise protected cabin for radial fan EQ No. 4540 & 4550 65 01-Apr-22 10-Apr-22 36% 100% 36%
000500 Noise protected cabinet EQ No. 5212 & 5214 78 09-May-22 21-May-22 36% 100% 36%
000558 Noise protected cabin sanding machine EQ No. 5442 40 15-May-22 22-May-22 6% 100% 6%
Page 195 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Noise protected cabin Longitudinal saw EQ No. 5452 & Dur B/L B/L
000559 32 23-May-22 26-May-22 13% 100% 13%
5462
000597 75 11-Jun-22 14-Jun-22 3% 100% 3%
Utilities & Buildings 537 07-Jul-20 07-Dec-22 36% 100% 36% 87% 32%
Site Preparations & Earth Work 492 07-Jul-20 31-Jul-22 1% 100.0% 1.3% 100.0% 1%
A81060 Site Preperation - OSBL 492 07-Jul-20 31-Jul-22 100% 100% 100% 100.0% 100%
Buildings / Warehouses 531 14-Jul-20 01-Dec-22 34% 100.0% 33.7% 95.2% 32%
Permanent TCF Building 171 14-Sep-20 01-Jan-22 10% 100% 10% 100% 10%
TCF - Construction 171 21-Oct-20 31-Aug-21 100% 100.0% 100.0% 100.0% 100%
A5590 Cut Works - TCF 15 21-Oct-20 08-Nov-20 3% 100% 3% 100.0% 3%
A5591 Backfilling with Crashed Stone - TCF 12 09-Nov-20 22-Nov-20 6% 100% 6% 100.0% 6%
A55911 Backfilling with Sand - TCF 22 23-Nov-20 17-Dec-20 1% 100% 1% 100.0% 1%
A5592 Concrete Works 25 19-Dec-20 17-Jan-21 40% 100% 40% 100.0% 40%
A5593 Steel Str, Sandwitch Panels & Finishing Works 62 01-Mar-21 30-Dec-21 50% 100% 50% 100% 50%
Substation Building 241 26-May-21 14-May-22 7% 100% 7% 97% 7%
Earth Work 61 26-May-21 11-Aug-21 16% 100.0% 16.0% 100.0% 16%
A77150 Cut Works - Substation Bldg. 7 26-May-21 02-Jun-21 53% 100% 53% 100.0% 53%
A77380 Backfilling (Replacement) - Substation Bldg. 7 03-Jun-21 10-Jun-21 47% 100% 47% 100.0% 47%
A77710 Backfilling - Substation Bldg. 7 03-Aug-21 11-Aug-21 0% 100% 0% 100.0% 0%
Concrete Works ( Cellar Floor) 66 12-Jun-21 18-Sep-21 27% 100.0% 26.8% 100.0% 27%
A5120 Plain Concrete 4 12-Jun-21 15-Jun-21 6% 100% 6% 100.0% 6%
A57321 RC Foundations 12 16-Jun-21 29-Jun-21 48% 100% 48% 100.0% 48%
Page 196 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57331 RC Columns & Walls 24 01-Jul-21 02-Aug-21 13% 100% 13% 100.0% 13%
A57341 RC Beams & Slabs 12 21-Aug-21 18-Sep-21 20% 100% 20% 100.0% 20%
A57351 Insulation 4 29-Jul-21 02-Aug-21 0% 100% 0% 100.0% 0%
A57361 RC Flooring 7 12-Aug-21 19-Aug-21 12% 100% 12% 100.0% 12%
Concrete Works ( 01st Floor) 36 05-Sep-21 17-Oct-21 7% 100.0% 7.3% 100.0% 7%
A78750 RC Columns & Walls 24 19-Sep-21 17-Oct-21 17% 100% 17% 100.0% 17%
A78760 RC Beams & Slabs 12 19-Oct-21 01-Nov-21 83% 100% 83% 100.0% 83%
Internal Finishing Works (Civil ) 42 02-Nov-21 20-Jan-22 16% 100.0% 16.3% 99.3% 16%
A57071 Masonary Works 6 02-Nov-21 22-Nov-21 21% 100% 21% 100% 21%
A78780 Plumbing Works 10 23-Nov-21 06-Dec-21 3% 100% 3% 100% 3%
A78790 Internal Plastering 12 23-Nov-21 13-Dec-21 42% 100% 42% 100% 42%
A78800 Doors & Windows 12 14-Dec-21 03-Jan-22 3% 100% 3% 80% 3%
A78810 Painting 24 15-Dec-21 20-Jan-22 21% 100% 21% 100% 21%
A78880 Ceramics / Tiles 12 14-Dec-21 03-Jan-22 10% 100% 10% 100% 10%
External Finishing Works (Civil ) 84 09-Dec-21 30-Apr-22 11% 100.0% 10.7% 100.0% 11%
A78030 External Plumbing Works (Sewage) 12 23-Feb-22 22-Mar-22 5% 100% 5% 100% 5%
A78820 External Plastering 24 16-Jan-22 22-Feb-22 53% 100% 53% 100% 53%
A78830 External Coat 24 23-Mar-22 30-Apr-22 21% 100% 21% 100% 21%
A78890 Roof Finish 24 09-Dec-21 15-Jan-22 21% 100% 21% 100% 21%
Lighting & Small Power 60 09-Nov-21 17-Mar-22 13% 100.0% 12.7% 94.7% 12%
A7395 PVC Conduit Installation 12 09-Nov-21 22-Nov-21 60% 100% 60% 100% 60%
A78660 Wire Pulling 12 05-Feb-22 17-Feb-22 100%
A78670 Pannels Erection 6 19-Feb-22 03-Mar-22 2% 100% 2% 100% 2%
A78680 Lighting Fixtures Erection (Substation) 6 19-Feb-22 03-Mar-22 5% 100% 5% 100% 5%
Page 197 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A78690 SW & Sockets 6 19-Feb-22 03-Mar-22 4% 100% 4% 100% 4%
A78700 Termination (Lighting-Substion) 12 05-Mar-22 17-Mar-22 11% 100% 11% 50% 5%
A78710 PVC Connection Boxes 9 23-Nov-21 02-Dec-21 18% 100% 18% 100% 18%
Fire-Fighting 12 24-Mar-22 14-May-22 2% 100.0% 2.3% 50.0% 1%
A78080 Fire Fighting Erection - Substation 12 24-Mar-22 14-May-22 100% 100% 100% 50% 50%
HVAC 38 03-Jan-22 14-Mar-22 4% 100.0% 3.8% 65.0% 2%
A75040 HVAC - Substation 26 08-Feb-22 14-Mar-22 100% 100% 100% 65% 65%
A78900 HVAC - Duct Works 12 03-Jan-22 07-Feb-22 100%
Telecomm. 22 28-Feb-22 14-May-22
A74850 CCTV - Substation Bldg. 22 24-Mar-22 20-Apr-22 100%
A74860 Public Adress - Substation Bldg. 22 05-Mar-22 31-Mar-22 100%
A74870 Data Network & IP Telephone - Substation Bldg. 22 30-Apr-22 14-May-22 100%
A74880 Fire Alarm - Substation Bldg. 22 28-Feb-22 27-Mar-22 100%
Electrical Works 119 01-Jan-22 07-May-22 4% 100.0% 4.2% 94.6% 4%
A82930 Cable Trays Supports Fab. & Erection 18 01-Jan-22 20-Jan-22 0% 100% 0%
A7320 Transformers Installation (Subsation) 12 08-Feb-22 21-Feb-22 5% 100% 5% 100% 5%
A7380 Cable Trays Works (Substaion) 52 15-Jan-22 14-Mar-22 28% 100% 28% 100% 28%
A7390 Cable Pulling 52 16-Feb-22 21-Mar-22 100%
A7400 Termination 41 22-Mar-22 07-May-22 100%
A78840 MV Switch Gear Installation 12 12-Feb-22 24-Feb-22 21% 100% 21% 100% 21%
A78850 LV Switch Gear Installation 12 15-Feb-22 28-Feb-22 4% 100% 4% 100% 4%
A78860 Bus Duct Installation 12 01-Mar-22 14-Mar-22 27% 100% 27% 100% 27%
A78870 UPS & Batteries Installation 6 01-Mar-22 07-Mar-22 7% 100% 7% 100% 7%
A82940 Distribution Pannels Installation 12 08-Mar-22 21-Mar-22 5% 100% 5% 33% 2%
Page 198 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A82950 Capacitor Banks Installation 6 15-Mar-22 21-Mar-22 2% 100% 2%
Warehouse For Chemical and Additive 169 30-Dec-21 14-Jun-22 1% 100% 1% 93% 1%
Earth Work 36 30-Dec-21 08-Feb-22 20% 100.0% 20.1% 100.0% 20%
A92580 Piles Works - Liquid Chemical Warehouse 4 30-Dec-21 01-Jan-22 75% 100% 75% 100.0% 75%
A77160 Cut Works - Liquid Chemical Warehouse 4 30-Dec-21 01-Jan-22 2% 100% 2% 100.0% 2%
A77390 Backfilling (Replacement) - Liquid Chemical Warehouse 4 02-Jan-22 05-Jan-22 18% 100% 18% 100.0% 18%
A77680 Backfilling - Liquid Chemical Warehouse 4 05-Feb-22 08-Feb-22 4% 100% 4% 100.0% 4%
Concrete Works 40 07-Jan-22 22-Feb-22 41% 100.0% 40.7% 100.0% 41%
A5150 Plain Concrete 4 07-Jan-22 10-Jan-22 7% 100% 7% 100.0% 7%
A57611 RC Foundations 8 11-Jan-22 19-Jan-22 84% 100% 84% 100.0% 84%
A57621 RC Columns 8 20-Jan-22 30-Jan-22 5% 100% 5% 100.0% 5%
A57631 Insulation 4 31-Jan-22 03-Feb-22 4% 100% 4% 100% 4%
A57641 RC Flooring 12 09-Feb-22 22-Feb-22 100% 100.0%
Steel Structure 52 23-Feb-22 13-Apr-22 1% 100.0% 1.1% 100.0% 1%
A73020 Cladding Works - Chemical and Additive Warehouse 26 24-Mar-22 13-Apr-22 100% 100% 100% 100.0% 100%
Finishing Works (Civil) 109 14-Apr-22 08-Jun-22 21% 100.0% 21.1% 100.0% 21%
A57651 Plumbing Works 26 14-Apr-22 19-May-22 14% 100% 14% 100% 14%
A78910 Ceramics / Tiles 26 27-Apr-22 31-May-22 57% 100% 57% 100% 57%
A78920 Doors & Windows 26 25-May-22 08-Jun-22 29% 100% 29% 100% 29%
Lighting & Small Power 53 14-Apr-22 28-May-22 11% 100.0% 10.9% 62.6% 7%
A82960 Cable Trays Supports Fab. & Erection 6 04-Apr-22 20-Apr-22 28% 100% 28% 100% 28%
A74610 Cable Trays Installation 6 21-Apr-22 28-Apr-22 32% 100% 32% 100% 32%
A78930 Wire Pulling 6 30-Apr-22 10-May-22 100%
A78940 Pannels Erection 3 11-May-22 14-May-22 7% 100% 7%
Page 199 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A78950 SW & Sockets 3 11-May-22 14-May-22 1% 100% 1% 100% 1%
A78960 Lighting Fixtures Erection (Chemical W.H) 6 11-May-22 17-May-22 11% 100% 11% 6% 1%
A78970 Termination (Lighting - Chemical W.H) 9 18-May-22 28-May-22 22% 100% 22% 6% 1%
Fire-Fighting 26 08-May-22 11-Jun-22 6% 100.0% 6.0% 50.0% 3%
A78090 Fire Fighting Erection - Liquid Chemeical Warehouse 26 08-May-22 11-Jun-22 100% 100% 100% 50% 50%
Telecomm. 22 01-Jun-22 14-Jun-22
A74890 CCTV - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A7490 Fire Alarm - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A74900 Public Adress - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A74910 Data Network & IP Telephone - Chemical WH 22 01-Jun-22 14-Jun-22 100%
Scale With Room 190 06-Dec-21 07-Jun-22 3% 100% 3% 86% 3%
Earth Work 42 06-Dec-21 30-Jan-22 5% 100.0% 5.1% 100.0% 5%
A77100 Piles Work - Scale Room 1 06-Dec-21 14-Dec-21 89% 100% 89% 100.0% 89%
A92610 Cut Works - Air Compressor Shed 6 29-Jan-22 06-Feb-22 3% 100% 3% 100.0% 3%
A77430 Backfilling (Replacement) - Air Compressor Shed 6 07-Feb-22 10-Feb-22 19% 100% 19% 100.0% 19%
A77730 Backfilling - Air Compressor Shed 3 22-Feb-22 26-Feb-22 5% 100% 5% 100.0% 5%
Concrete Works 27 12-Feb-22 07-Mar-22 65% 100.0% 65.2% 100.0% 65%
A5253 Plain Concrete 4 12-Feb-22 13-Feb-22 5% 100% 5% 100.0% 5%
A72750 RC Foundation 8 14-Feb-22 19-Feb-22 94% 100% 94% 100.0% 94%
A72760 Insulation 4 20-Feb-22 21-Feb-22 1% 100% 1% 100% 1%
A72770 RC Flooring 8 27-Feb-22 07-Mar-22 100% 100.0%
Equipment Installation 12 29-Mar-22 11-Apr-22 21% 100.0% 20.6% 100.0% 21%
A72730 Erection- Air Compressor PKG 12 29-Mar-22 11-Apr-22 100% 100% 100% 100% 100%
Steel Structure 18 12-Apr-22 21-Apr-22 0% 100.0% 0.2% 100.0% 0%
A73070 Cladding Works - Air Comp. Shed 6 19-Apr-22 21-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 18 23-Apr-22 30-Apr-22 4% 100.0% 4.3%
Page 204 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A74660 Elect - Air Compressor Shed 18 23-Apr-22 30-Apr-22 100% 100% 100%
Telecomm. 12 23-Apr-22 09-May-22
A74960 Fire Alarm - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74970 CCTV - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74980 Public Adress - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74990 Data Network & IP Telephone - Air Compressor Shed 12 30-Apr-22 09-May-22 100%
Industrial Pump Station 109 18-Jan-22 20-May-22 1% 100% 1% 92% 1%
Earth Work 32 18-Jan-22 17-Feb-22 10% 100.0% 10.3% 100.0% 10%
A77200 Piles Works - Industrial Water Pump Station 6 18-Jan-22 27-Jan-22 71% 100% 71% 100.0% 71%
A92620 Cut Works - Industrial Water Pump Station 6 18-Jan-22 27-Jan-22 5% 100% 5% 100.0% 5%
A77440 Backfilling (Replacement) - Industrial Water Pump Station 6 29-Jan-22 01-Feb-22 19% 100% 19% 100.0% 19%
A77740 Backfilling - Industrial Water Pump Station 4 14-Feb-22 17-Feb-22 5% 100% 5% 100.0% 5%
Concrete Works 28 02-Feb-22 27-Feb-22 68% 100.0% 68.5% 100.0% 68%
A5254 Plain Concrete 4 02-Feb-22 03-Feb-22 8% 100% 8% 100.0% 8%
A57081 RC Foundation 8 05-Feb-22 10-Feb-22 91% 100% 91% 100.0% 91%
A57091 RC Flooring 8 19-Feb-22 27-Feb-22 100% 100.0%
A57101 Insulation 4 12-Feb-22 13-Feb-22 1% 100% 1% 100% 1%
Equipment Installation 12 09-May-22 20-May-22 13% 100.0% 12.9% 100.0% 13%
A72800 Erection- Industrial Water Pumps 12 09-May-22 20-May-22 100% 100% 100% 100% 100%
Steel Structure 18 11-Apr-22 20-Apr-22 0% 100.0% 0.3% 100.0% 0%
A73030 Cladding Works - Industrial Water Pump Station 6 18-Apr-22 20-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 18 21-Apr-22 28-Apr-22 8% 100.0% 8.0%
A74670 Elect - Industrial Water Pump Station 18 21-Apr-22 28-Apr-22 100% 100% 100%
Potable Water Pump Station 110 16-Feb-22 20-May-22 1% 100% 1% 91% 1%
Page 205 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Earth Work 32 16-Feb-22 17-Mar-22 14% 100.0% 13.9% 100.0% 14%
A77230 Piles Works - Potable Pump Station 6 16-Feb-22 24-Feb-22 60% 100% 60% 100.0% 60%
A92630 Cut Works - Potable Pump Station 6 16-Feb-22 24-Feb-22 4% 100% 4% 100.0% 4%
A77470 Backfilling (Replacement) - Potable Pump Station 6 26-Feb-22 01-Mar-22 29% 100% 29% 100.0% 29%
A77770 Backfilling - Potable Pump Station 4 14-Mar-22 17-Mar-22 7% 100% 7% 100.0% 7%
Concrete Works 28 02-Mar-22 27-Mar-22 62% 100.0% 62.1% 100.0% 62%
A5257 Plain Concrete 4 02-Mar-22 03-Mar-22 10% 100% 10% 100.0% 10%
A57171 RC Foundation 8 05-Mar-22 10-Mar-22 89% 100% 89% 100.0% 89%
A57181 Insulation 4 12-Mar-22 13-Mar-22 1% 100% 1% 100% 1%
A57191 RC Flooring 8 19-Mar-22 27-Mar-22 100% 100.0%
Equipment Installation 12 09-May-22 20-May-22 15% 100.0% 14.6% 100.0% 15%
A72860 Erection- Potable Water Pumps 12 09-May-22 20-May-22 100% 100% 100% 100% 100%
Steel Structure 18 11-Apr-22 20-Apr-22 0% 100.0% 0.4% 100.0% 0%
A73060 Cladding Works - Potable Water Pump Station 6 18-Apr-22 20-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 12 21-Apr-22 28-Apr-22 9% 100.0% 9.1%
A74700 Elect - Potable Water Pump Station 12 21-Apr-22 28-Apr-22 100% 100% 100%
Reject Water Pump Station 109 16-Feb-22 20-May-22 1% 100% 1% 87% 1%
Earth Work 32 16-Feb-22 17-Mar-22 19% 100.0% 19.4% 100.0% 19%
A77210 Piles Works - Reject Water Pump Station 6 16-Feb-22 24-Feb-22 42% 100% 42% 100.0% 42%
A92640 Cut Works - Reject Water Pump Station 6 16-Feb-22 24-Feb-22 7% 100% 7% 100.0% 7%
A77450 Backfilling (Replacement) - Reject Water Pump Station 6 26-Feb-22 01-Mar-22 40% 100% 40% 100.0% 40%
A77750 Backfilling - Reject Water Pump Station 4 14-Mar-22 17-Mar-22 10% 100% 10% 100.0% 10%
Concrete Works 28 02-Mar-27 27-Mar-22 51% 100.0% 50.7% 100.0% 51%
A5255 Plain Concrete 4 02-Mar-22 03-Mar-22 9% 100% 9% 100.0% 9%
Page 206 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57111 RC Foundation 8 05-Mar-22 10-Mar-22 89% 100% 89% 100.0% 89%
A57121 Insulation 4 12-Mar-22 13-Mar-22 2% 100% 2% 100% 2%
A57131 RC Flooring 8 19-Mar-22 27-Mar-22 100% 100.0%
Equipment Installation 12 09-May-22 20-May-22 18% 100.0% 18.1% 90.0% 16%
A72830 Erection- Reject Water Pump Station 12 09-May-22 20-May-22 100% 100% 100% 90% 90%
Steel Structure 18 29-Mar-22 07-Apr-22 0% 100.0% 0.5% 100.0% 0%
A73040 Cladding Works - Reject Water Pump Station 6 05-Apr-22 07-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 12 09-Apr-22 14-Apr-22 11% 100.0% 11.3%
A74680 Elect - Reject Water Pump Station 12 09-Apr-22 14-Apr-22 100% 100% 100%
Industrial Water Treatment PKG. 143 14-Feb-22 09-May-22 5% 100% 5% 96% 5%
Earth Work 35 14-Feb-22 15-Mar-22 8% 100.0% 7.7% 100.0% 8%
A77240 Piles Works - Industrial Water Treatment PKG. 4 14-Feb-22 20-Feb-22 84% 100% 84% 100.0% 84%
A92650 Cut Works - Industrial Water Treatment PKG. 4 14-Feb-22 20-Feb-22 2% 100% 2% 100.0% 2%
Backfilling (Replacement) - Industrial Water Treatment
A77490 10 21-Feb-22 24-Feb-22 11% 100% 11% 100.0% 11%
PKG.
A77790 Backfilling - Industrial Water Treatment PKG. 2 12-Mar-22 15-Mar-22 3% 100% 3% 100.0% 3%
Concrete Works 27 26-Feb-22 22-Mar-22 74% 100.0% 74.5% 100.0% 74%
A5259 Plain Concrete 3 26-Feb-22 27-Feb-22 9% 100% 9% 100.0% 9%
A77880 RC Foundation 12 28-Feb-22 08-Mar-22 89% 100% 89% 100.0% 89%
A77890 Insulation 4 09-Mar-22 10-Mar-22 0% 100% 0% 100% 0%
A77900 RC Columns 6 16-Mar-22 22-Mar-22 2% 100% 2% 100.0% 2%
Package Installation 68 23-Mar-22 02-May-22 18% 100.0% 17.8% 75.0% 13%
A72880 Erection- Industrial Water Treatment PKG. 68 23-Mar-22 02-May-22 100% 100% 100% 75% 75%
Telecomm. 22 05-Apr-22 09-May-22
A75000 Fire Alarm - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
Page 207 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A75010 CCTV - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
A75020 Public Adress - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
Data Network & IP Telephone - Industrial Water Treatment
A75030 22 30-Apr-22 09-May-22 100%
PKG.
Fire Pump Shed 137 02-Mar-22 30-May-22 1% 100% 1% 90% 1%
Earth Work 44 02-Nov-21 22-Dec-21 10% 100.0% 10.1% 100.0% 10%
A77180 Piles Works - Fire Pump Shed 12 02-Mar-22 15-Mar-22 74% 100% 74% 100.0% 74%
A77180 Cut Works - Fire Pump Shed 12 02-Mar-22 15-Mar-22 5% 100% 5% 100.0% 5%
A77480 Backfilling (Replacement) - Fire Pump Shed 12 16-Mar-22 22-Mar-22 17% 100% 17% 100.0% 17%
A77780 Backfilling - Fire Pump Shed 6 13-Apr-22 17-Apr-22 4% 100% 4% 100.0% 4%
Concrete Works 28 23-Mar-22 27-Apr-22 61% 100.0% 60.7% 100.0% 61%
A5252 Plain Concrete 3 23-Mar-22 26-Mar-22 8% 100% 8% 100.0% 8%
A57201 RC Foundation 8 27-Mar-22 09-Apr-22 91% 100% 91% 100.0% 91%
A57211 Insulation 3 10-Apr-22 12-Apr-22 1% 100% 1% 100% 1%
A57221 RC Flooring 8 18-Apr-22 27-Apr-22 100% 100.0%
Equipment Installation 12 07-May-22 20-May-22 22% 100.0% 22.0% 85.0% 19%
A72940 Erection- Fire Pumps 12 07-May-22 20-May-22 100% 100% 100% 85% 85%
Steel Structure 18 21-May-22 30-May-22 0% 100.0% 0.3%
A73080 Cladding Works - Fire Pump Shed 6 28-May-22 30-May-22 100% 100% 100%
Lighting & Small Power 12 28-May-22 30-May-22 7% 100.0% 6.9%
A74650 Elect - Fire Pump Shed 12 28-May-22 30-May-22 100% 100% 100%
New Switch Room 143 21-Feb-22 20-Jun-22 1% 100% 1% 82% 1%
Civil Work 35 21-Feb-22 13-Jun-22 87% 100.0% 86.8% 80.9% 70%
A92660 New Switch Room - Civil - Pile Works 4 21-Feb-22 25-Feb-22 9% 100% 9% 100.0% 9%
A92670 New Switch Room - Cut Works 12 02-Mar-22 15-Mar-22 1% 100% 1% 100.0% 1%
Page 208 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A92680 New Switch Room - Backfilling (Replacement) 12 16-Mar-22 22-Mar-22 100% 100.0%
A87160 New Switch Room - Civil - Concrete Works 4 21-Feb-22 13-Mar-22 46% 100% 46% 100.0% 46%
A87170 New Switch Room - Civil - Finishing Works 10 14-Mar-22 03-Apr-22 17% 100% 17% 100.0% 17%
A87190 New Switch Room - Civil - Raised Floor 12 05-Jun-22 13-Jun-22 17% 100% 17%
A87180 New Switch Room - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 10% 100% 10% 80% 8%
Electrical Work 27 26-Feb-22 20-Jun-22 13% 100.0% 13.2% 90.1% 12%
A91810 New Switch Room - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 61% 100% 61% 100% 61%
A82880 New Switch Room - Cable Trays 12 11-Apr-22 21-Apr-22 100%
A79820 New Switch Room - LV12 & Bus Duct Installation 18 18-Apr-22 07-May-22 6% 100% 6% 100% 6%
A79820 New Switch Room - TR12 18 18-Apr-22 07-May-22 9% 100% 9% 100% 9%
A79830 New Switch Room - Cable Pulling 12 23-Apr-22 16-May-22 100%
A79840 New Switch Room - Lighting Fixtures 18 17-May-22 20-Jun-22 12% 100% 12% 58% 7%
A79840 New Switch Room - Termination (Lighting ) 18 17-May-22 20-Jun-22 11% 100% 11% 58% 7%
Main Security Building 187 12-Mar-22 01-Nov-22 2% 100% 2% 88% 2%
Earth Work 70 12-Mar-22 23-May-22 2% 87.6% 1.8% 100.0% 2%
A77120 Cut Works - Main Security Room 4 12-Mar-22 17-Mar-22 38% 100% 38% 100.0% 38%
A77510 Backfilling (Replacement) - Main Security Room 12 19-Mar-22 24-May-22 50% 100% 50% 100.0% 50%
A77810 Backfilling - Main Security Room 2 17-May-23 23-May-23 12% 100.0% 12%
Concrete Works 69 26-Mar-22 09-Jun-22 16% 100.0% 15.8% 100.0% 16%
A5250 Plain Concrete 3 26-Mar-22 28-Mar-22 6% 100% 6% 100.0% 6%
A57511 RC Foundations 15 29-Mar-22 11-Apr-22 28% 100% 28% 100.0% 28%
A57521 RC Columns 15 12-Apr-22 18-Apr-22 7% 100% 7% 100.0% 7%
A57531 RC Beams & Slabs 15 19-Apr-22 11-May-22 30% 100% 30% 100.0% 30%
A57541 Insulation 4 12-May-22 16-May-22 2% 100% 2% 100% 2%
Page 209 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57551 RC Flooring 15 24-May-22 09-Jun-22 28% 100% 28% 100.0% 28%
Internal Finishing Works (Civil) 84 11-Jun-22 15-Oct-22 43% 100.0% 43.5% 82.8% 36%
A81720 Masonary Works - Main Security Room 12 11-Jun-22 09-Jul-22 13% 100% 13% 100% 13%
A81730 Plumbing Works - Main Security Room 12 10-Jul-22 06-Aug-22 5% 100% 5% 100% 5%
A81740 Internal Plastering - Main Security Room 18 07-Aug-22 27-Aug-22 13% 100% 13% 100% 13%
A81750 Ceramics / Tiles - Main Security Room 18 28-Aug-22 17-Sep-22 6% 100% 6%
A81760 Doors & Windows - Main Security Room 12 18-Sep-22 01-Oct-22 56% 100% 56% 80% 45%
A81770 Internal Painting - Main Security Room 24 18-Sep-22 15-Oct-22 7% 100% 7% 100% 7%
External Finishing Works (Civil) 123 03-Aug-22 26-Oct-22 18% 100.0% 17.7% 100.0% 18%
A81780 Roof Finish - Main Security Room 24 03-Aug-22 25-Aug-22 20% 100% 20% 100% 20%
A81790 External Plastering - Main Security Room 24 28-Aug-22 19-Sep-22 52% 100% 52% 100% 52%
A81800 External Plumbing Works (Sewage) - Main Security Room 12 20-Sep-22 03-Oct-22 12% 100% 12% 100% 12%
A81810 External Painting - Main Security Room 24 04-Oct-22 26-Oct-22 16% 100% 16% 100% 16%
Lighting & Small Power 81 10-Jul-22 25-Oct-22 18% 100.0% 17.6% 83.6% 15%
A81640 PVC Conduit Installation 6 10-Jul-22 16-Jul-22 24% 100% 24% 100% 24%
A81650 PVC Connection Boxes 6 17-Jul-22 23-Jul-22 50% 100% 50% 100% 50%
A81660 Wire Pulling 6 28-Aug-22 03-Sep-22 100%
A81670 Pannels Erection 1 07-Sep-22 07-Sep-22 6% 100% 6%
A81680 SW & Sockets 3 04-Sep-22 06-Sep-22 10% 100% 10% 100% 10%
A81690 Lighting Fixtures Erection (Main Security) 3 16-Oct-22 18-Oct-22 3% 100% 3%
A81700 Termination (Lighting-Main Securtiy) 6 19-Oct-22 25-Oct-22 7% 100% 7%
HVAC 45 16-Oct-22 01-Nov-22 3% 100.0% 3.4% 40.0% 1%
A75050 HVAC - Main Secuirty Bldg. 45 16-Oct-22 01-Nov-22 100% 100% 100% 40% 40%
Telecomm. 15 16-Oct-22 01-Nov-22
Page 210 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A74710 Fire Alarm - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74720 CCTV - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74730 Public Adress - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74740 Data Network & IP Telephone - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
Security Building 199 12-Mar-22 01-Nov-22 2% 100% 2% 89% 2%
Earth Work 70 12-Mar-22 23-May-22 2% 100.0% 2.1% 100.0% 2%
A77130 Cut Works - Security Building 4 12-Mar-22 17-Mar-22 38% 100% 38% 100.0% 38%
A77520 Backfilling (Replacement) - Security Building 12 19-Mar-22 24-Mar-22 50% 100% 50% 100.0% 50%
A77820 Backfilling - Security Building 2 17-May-22 23-May-22 12% 100% 12% 100.0% 12%
Concrete Works 69 26-Mar-22 09-Jun-22 16% 100.0% 16.1% 100.0% 16%
A5251 Plain Concrete 3 26-Mar-22 28-Mar-22 6% 100% 6% 100.0% 6%
A57561 RC Foundations 15 29-Mar-22 11-Apr-22 28% 100% 28% 100.0% 28%
A57571 RC Columns 15 12-Apr-22 18-Apr-22 7% 100% 7% 100.0% 7%
A57581 RC Beams & Slabs 15 19-Apr-22 11-May-22 30% 100% 30% 100.0% 30%
A57591 Insulation 4 12-May-22 16-May-22 2% 100% 2% 100% 2%
A57601 RC Flooring 15 24-May-22 09-Jun-22 28% 100% 28% 100.0% 28%
Internal Finishing Works (Civil) 84 11-Jun-22 15-Oct-22 44% 100.0% 44.2% 82.8% 37%
A81820 Masonary Works - Security Room 12 11-Jun-22 09-Jul-22 13% 100% 13% 100% 13%
A81830 Plumbing Works - Security Room 12 10-Jul-22 06-Aug-22 5% 100% 5% 100% 5%
A81840 Internal Plastering - Security Room 18 07-Aug-22 27-Aug-22 13% 100% 13% 100% 13%
A81850 Ceramics / Tiles - Security Room 18 28-Aug-22 17-Sep-22 6% 100% 6%
A81860 Doors & Windows - Security Room 12 18-Sep-22 01-Oct-22 56% 100% 56% 80% 45%
A81870 Internal Painting - Security Room 24 18-Sep-22 15-Oct-22 7% 100% 7% 100% 7%
External Finishing Works (Civil) 123 12-May-22 26-Oct-22 18% 100.0% 18.0% 100.0% 18%
Page 211 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A81880 Roof Finish - Security Room 24 12-May-22 04-Jun-22 20% 100% 20% 100% 20%
A81890 External Plastering - Security Room 24 28-Aug-22 19-Sep-22 52% 100% 52% 100% 52%
A81900 External Plumbing Works (Sewage) - Security Room 12 20-Sep-22 03-Oct-22 12% 100% 12% 100% 12%
A81910 External Painting - Security Room 24 04-Oct-22 26-Oct-22 16% 100% 16% 100% 16%
Lighting & Small Power 81 10-Jul-22 25-Oct-22 18% 100.0% 17.6% 87.0% 15%
A81920 PVC Conduit Installation 6 10-Jul-22 16-Jul-22 25% 100% 25% 100% 25%
A81930 PVC Connection Boxes 6 17-Jul-22 23-Jul-22 50% 100% 50% 100% 50%
A81940 Wire Pulling 6 28-Aug-22 03-Sep-22 100%
A81950 SW & Sockets 3 04-Sep-22 06-Sep-22 6% 100% 6% 100% 6%
A81960 Pannels Erection 1 07-Sep-22 07-Sep-22 10% 100% 10%
A81970 Lighting Fixtures Erection ( Security) 3 16-Oct-22 18-Oct-22 3% 100% 3% 100% 3%
A81980 Termination (Lighting- Securtiy) 6 19-Oct-22 25-Oct-22 6% 100% 6% 50% 3%
HVAC 45 16-Oct-22 01-Nov-22 2% 100.0% 2.1% 66.7% 1%
A75060 HVAC - Secuirty Bldg. 45 16-Oct-22 01-Nov-22 100% 100% 100% 67% 67%
Telecomm. 30 16-Oct-22 01-Nov-22
A74750 Fire Alarm - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74800 CCTV - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74810 Public Adress - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74820 Data Network & IP Telephone - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
Masjid Building [Mosque] 222 31-Mar-22 01-Nov-22 2% 100% 2% 90% 2%
Earth Work 75 31-Mar-22 03-Jul-22 3% 100.0% 3.3% 100.0% 3%
A77140 Cut Works - Masjid 2 31-Mar-22 02-Apr-22 37% 100% 37% 100.0% 37%
A77530 Backfilling (Replacement) - Masjid 2 03-Apr-22 04-Apr-22 51% 100% 51% 100.0% 51%
A77830 Backfilling - Masjid 2 02-Jul-22 03-Jul-22 13% 100% 13% 100.0% 13%
Page 212 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Concrete Works 86 05-Apr-22 20-Jul-22 24% 100.0% 23.6% 100.0% 24%
A5240 Plain Concrete 12 05-Apr-22 18-Apr-22 9% 100% 9% 100.0% 9%
A57381 RC Foundations 15 19-Apr-22 11-May-22 25% 100% 25% 100.0% 25%
A57391 RC Columns 15 12-May-22 29-May-22 14% 100% 14% 100.0% 14%
A57401 RC Beams & Slabs 15 30-May-22 15-Jun-22 26% 100% 26% 100.0% 26%
A57411 Insulation 12 16-Jun-22 29-Jun-22 1% 100% 1% 100.0% 1%
A57421 RC Flooring 15 04-Jul-22 20-Jul-22 25% 100% 25% 100.0% 25%
Internal Finishing Works (Civil) 84 07-Jul-22 12-Oct-22 34% 100.0% 33.9% 81.9% 28%
A82100 Masonary Works - Masjid 12 07-Jul-22 20-Jul-22 25% 100% 25% 100% 25%
A82110 Plumbing Works - Masjid 12 21-Jul-22 03-Aug-22 12% 100% 12% 100% 12%
A82120 Internal Plastering - Masjid 18 04-Aug-22 24-Aug-22 24% 100% 24% 100% 24%
A82130 Ceramics / Tiles - Masjid 18 25-Aug-22 14-Sep-22 16% 100% 16%
A82140 Doors & Windows - Masjid 12 15-Sep-22 28-Sep-22 12% 100% 12% 80% 9%
A82150 Internal Painting - Masjid 24 15-Sep-22 10-Dec-22 13% 100% 13% 100% 13%
External Finishing Works (Civil) 60 25-Aug-22 19-Oct-22 22% 100.0% 22.1% 100.0% 22%
A82170 External Plastering - Masjid 24 25-Aug-22 14-Sep-22 75% 100% 75% 100% 75%
A82180 External Plumbing Works (Sewage) - Masjid 12 15-Sep-22 28-Sep-22 0% 100% 0% 100% 0%
A82190 External Painting - Masjid 24 29-Sep-22 19-Oct-22 25% 100% 25% 100% 25%
Lighting & Small Power 87 21-Jul-22 30-Oct-22 12% 100.0% 11.9% 88.6% 11%
A82200 PVC Conduit Installation 6 21-Jul-22 27-Jul-22 45% 100% 45% 100% 45%
A82210 PVC Connection Boxes 6 28-Jul-22 03-Aug-22 23% 100% 23% 100% 23%
A82220 Wire Pulling 6 25-Aug-22 31-Aug-22 100%
A82230 SW & Sockets 3 01-Sep-22 04-Sep-22 7% 100% 7% 100% 7%
A82240 Pannels Erection 1 05-Sep-22 05-Sep-22 4% 100% 4%
Page 213 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A82250 Lighting Fixtures Erection (Mosque) 3 13-Oct-22 16-Oct-22 7% 100% 7% 100% 7%
A82260 Termination (Lighting- Mosque) 12 17-Oct-22 30-Oct-22 14% 100% 14% 50% 7%
HVAC 28 13-Oct-22 30-Oct-22 5% 100.0% 5.2% 50.0% 3%
A75070 HVAC - Mosque 28 13-Oct-22 30-Oct-22 100% 100% 100% 50% 50%
Telecomm. 10 13-Oct-22 01-Nov-22
A74830 Public Adress - Mosque 10 13-Oct-22 01-Nov-22 100%
Guard Towers 186 23-Apr-22 01-Nov-22 1% 100% 1% 52% 1%
Earth Work 126 23-Apr-22 18-Aug-22 12% 100.0% 11.9% 82.9% 10%
A77940 Piles Works - Guard Towers 120 01-Apr-22 31-Jul-22 72% 100% 72% 100.0% 72%
A92730 Cut Works - Guard Towers 120 23-Apr-22 11-Aug-22 4% 100% 4% 49.3% 2%
A77960 Backfilling - Guard Towers 120 02-May-22 18-Aug-22 24% 100% 24% 36.0% 9%
Concrete Works 156 12-May-22 04-Sep-22 49% 100.0% 49.2% 86.3% 43%
A56991 Plain Concrete 120 12-May-22 24-Jul-22 4% 100% 4% 88.9% 4%
A57001 RC Foundations 120 02-Jun-22 14-Aug-22 59% 100% 59% 83.6% 49%
A57011 RC Coulmns & Beams 120 23-Jun-22 04-Sep-22 35% 100% 35% 92.5% 33%
A57021 Insulation 120 23-Jun-22 04-Sep-22 1% 100% 1% 40% 1%
Finishing Works (Civil) 120 25-Jul-22 01-Nov-22 23% 100.0% 22.8%
A57031 Finishing .Works 120 25-Jul-22 01-Nov-22 100% 100% 100%
Lighting & Small Power 90 25-Jul-22 01-Nov-22 16% 100.4% 16.2%
A74560 Elect - Guard Towers 90 25-Jul-22 01-Nov-22 94% 100% 94%
A74560 Lighting Fixture - Guard Towers 90 25-Jul-22 01-Nov-22 6% 100% 6%
Rice Straw Warehouse 437 14-Jul-20 27-Jan-22 45% 100% 45% 100% 45%
A5610 Backfilling With Cut Material 44 14-Jul-20 08-Sep-20 11% 100% 11% 100.0% 11%
A5620 Backfilling With Supplied Material (Rice Straw Warehouse) 311 19-Jul-20 07-Jul-22 89% 100% 89% 100.0% 89%
Page 214 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Civil Works 311 10-May-21 07-Dec-22 39% 100.0% 39.3% 85.5% 34%
Tanks Civil Works 239 10-May-21 05-Jul-22 8% 100% 8% 82% 6%
Piles Works For Tanks 42 10-May-21 08-Jan-22 39% 100.0% 39.2% 100.0% 39%
A55961 Piles Works - Tanks (01st Batch) 42 10-May-21 10-Jun-21 73% 100% 73% 100.0% 73%
A86660 Piles Works - Fire Water Tank (02nd Batch) 42 16-Jan-21 08-Jan-22 27% 100% 27% 100.0% 27%
A91900 Piles Works - Potable Water Tank (02nd Batch) 42 16-Dec-21 29-Dec-21 100% 100.0%
Industrial Raw Water Tank Foundation 31 27-Jun-21 21-Sep-21 7% 100.0% 7.3% 100.0% 7%
A76970 Cut Works - Industrial Raw Water Tank (101A) 4 27-Jun-21 11-Jul-21 8% 100% 8% 100.0% 8%
A77310 Backfilling (Replacement) - Industrial Raw Water Tank 4 11-Jul-21 29-Jul-21 6% 100% 6% 100.0% 6%
A5670 Plain Concrete 4 31-Jul-21 03-Aug-21 14% 100% 14% 100.0% 14%
A56661 RC Foundations 10 04-Aug-21 06-Sep-21 64% 100% 64% 100.0% 64%
A56691 Insulation 3 07-Sep-21 11-Sep-21 8% 100% 8% 100% 8%
A77610 Backfilling - Industrial Raw Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Demi Water Tank Foundation 31 27-Jun-21 21-Sep-21 5% 100.0% 5.1% 100.0% 5%
A77040 Cut Works - DEMI Water Tank (103A) 4 27-Jun-21 11-Jul-21 9% 100% 9% 100.0% 9%
A77320 Backfilling (Replacement) - DEMI Water Tank 4 12-Jul-21 29-Jul-21 7% 100% 7% 100.0% 7%
A56761 Plain Concrete 4 31-Jul-21 03-Aug-21 12% 100% 12% 100.0% 12%
A56771 RC Foundations 10 04-Aug-21 06-Sep-21 61% 100% 61% 100.0% 61%
A56781 Insulation 3 07-Sep-21 11-Sep-21 11% 100% 11% 100% 11%
A77620 Backfilling - DEMI Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Process Water Tank Foundation 31 27-Jun-21 21-Sep-21 6% 100.0% 5.8% 100.0% 6%
A77050 Cut Works - Process Water Tank (102A) 4 27-Jun-21 11-Jul-21 9% 100% 9% 100.0% 9%
A77330 Backfilling (Replacement) - Process Water Tank 4 12-Jul-21 29-Jul-21 7% 100% 7% 100.0% 7%
A56791 Plain Concrete 4 31-Jul-21 03-Aug-21 13% 100% 13% 100.0% 13%
Page 215 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A56801 RC Foundations 10 04-Aug-21 06-Sep-21 61% 100% 61% 100.0% 61%
A56811 Insulation 3 07-Sep-21 11-Sep-21 10% 100% 10% 100% 10%
A77630 Backfilling - Process Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Potable Water Tank Foundation 60 01-Jan-22 06-Mar-22 5% 100.0% 5.5% 100.0% 5%
A77060 Cut Works - Potable Water Tank 13 01-Jan-22 13-Jan-22 100%
A77340 Backfilling (Replacement) - Potable Water Tank 13 15-Jan-22 29-Jan-22 6% 100% 6% 100.0% 6%
A56821 Plain Concrete 6 30-Jan-22 05-Feb-22 14% 100% 14% 100.0% 14%
A56831 RC Foundations 15 06-Feb-22 22-Feb-22 68% 100% 68% 100.0% 68%
A56841 Insulation 4 23-Feb-22 27-Feb-22 10% 100% 10% 100% 10%
A77640 Backfilling - Potable Water Tank 9 28-Feb-22 06-Mar-22 1% 100% 1% 100.0% 1%
Fire Water Tank Foundation 60 09-Jan-22 31-Jan-22 5% 100.0% 4.5% 100.0% 5%
A77080 Cut Works - Fire Water Tank 13 09-Jan-22 10-Jan-22 12% 100% 12% 100.0% 12%
A77360 Backfilling (Replacement) - Fire Water Tank 13 11-Jan-22 15-Jan-22 5% 100% 5% 100.0% 5%
A56881 Plain Concrete 6 16-Jan-22 17-Jan-22 15% 100% 15% 100.0% 15%
A56891 RC Foundations 15 18-Jan-22 24-Jan-22 55% 100% 55% 100.0% 55%
A56901 Insulation 4 26-Jan-22 27-Jan-22 12% 100% 12% 100% 12%
A77660 Backfilling - Fire Water Tank 9 29-Jan-22 31-Jan-22 1% 100% 1% 100.0% 1%
Paving (Interlock) For Tanks 84 20-Apr-22 05-Jul-22 33% 100.0% 32.5% 45.0% 15%
A82280 Paving for OSBL - Tanks (Interlock) 24 20-Apr-22 05-Jul-22 100% 100% 100% 45.0% 45%
Roads / Paving 240 01-Dec-21 07-Dec-22 38% 100% 38% 68% 26%
A77990 Cut Works - Roads 228 01-Dec-21 14-Sep-22 17% 100% 17% 99.9% 17%
A78020 Backfilling - Roads 228 15-Dec-21 28-Sep-22 23% 100% 23% 98.5% 23%
A5710 Roads Activities - Paving 200 18-May-22 07-Dec-22 33% 100% 33% 14% 4%
A78480 Pits & Sheds 100 18-May-22 07-Dec-22 4% 100% 4% 45.9% 2%
Page 216 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91920 Pile Heads Demolishing (For thr Reamining) 60 21-Dec-21 14-Feb-22 11% 100% 11% 99.6% 11%
A78490 Roads Activities - Gravel Finish 100 18-May-22 07-Dec-22 11% 100% 11% 92.1% 10%
U/G Works - OSBL 64 26% 100% 26% 98% 25%
Potable Water Network 42 3% 100.0% 2.9% 99.9% 3%
A90970 Cut Works - Potable Water Network 52 20% 100% 20% 99.6% 20%
A90980 Bedding Layer - Potable Water Network 52 80% 100% 80% 100.0% 80%
A91000 Valve Bit - Potable Water Network 52 100%
A91010 Pressure Test - Potable Water Network 52 100%
A91020 Backfilling - Potable Water Network 52 100% 100.0%
Fire Fighting Network (HDBE) 42 2% 100.0% 2.2% 99.7% 2%
A91030 Cut Works - Fire Fighting Network 52 100% 100% 100% 99.7% 100%
A91040 Bedding Layer - Fire Fighting Network 52 100% 100.0%
Sewer Network 42 11% 100.0% 10.5% 95.7% 10%
A77980 Cut Works - Sewer Network 52 4% 100% 4% 100.0% 4%
A91070 Shoring & Dewatering - Sewer Network 52 100% 100.0%
A91080 Bedding Layer - Sewer Network 52 4% 100% 4% 100.0% 4%
A91090 Manholes (Concrete) - Sewer Network 52 82% 100% 82% 100.0% 82%
A91100 Piping Laying 52 3% 100% 3% 77.5% 3%
A91110 Grout Box - Sewer Network 52 100% 60.0%
A91120 Testing - Sewer Network 52 100% 60.0%
A78010 Backfilling & Insulation - Sewer Network 52 7% 100% 7% 45.9% 3%
A5680 Covering & Accessories - Sewer Network 52 100%
Storm Network 42 11% 100.0% 11.4% 94.5% 11%
A91150 Cut Works - Storm Network 52 11% 100% 11% 96.3% 11%
A91160 Shoring & Dewatering - Storm Network 52
Page 217 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91170 Bedding Layer - Storm Network 52 6% 100% 6% 95.2% 5%
A91180 Manholes (Concrete) - Storm Network 52 53% 100% 53% 96.3% 51%
A91190 Piping Laying 52 10% 100% 10% 79.2% 8%
A91200 Grout Box - Storm Network 52 100%
A91210 Testing - Storm Network 52 100%
A91220 Backfilling & Insulation - Storm Network 52 20% 100% 20% 96.1% 19%
A91230 Covering & Accessories - Storm Network 52 100%
Electrical Network (Concrete Trench) 42 66% 100.0% 66.4% 98.7% 66%
A77970 Cut Works - Electrical Network 52 1% 100% 1% 99.5% 1%
A91250 PC Concrete - Electrical Network 52 11% 100% 11% 100.0% 11%
A5685 RC Concrete - Electrical Network 52 64% 100% 64% 100.0% 64%
A78000 Insulation & Backfilling - Electrical Network 52 20% 100% 20% 95.7% 19%
A78000 Piping Laying 52 5% 100% 5% 92.2% 5%
Instrumentation Network 42 7% 100.0% 6.6% 95.6% 6%
A91280 Cut Works - E&I Network 52 4% 100% 4% 100.0% 4%
A91290 PC Concrete - E&I Network 52 29% 100% 29% 100.0% 29%
A78000 Insulation & Backfilling - E&I Network 52 3% 100% 3%
A78000 Piping Laying 52 64% 100% 64% 98.3% 63%
Remaining U/G Piping Network (Chemical Waste if Any) 42
A91620 U/G Piping Network (PVC) 52 100%
Piping Sleepers 60 02-Jan-22 12-Apr-22 1% 100% 1% 100% 1%
A78500 Piping Sleepers - Piles Works 150 15-Dec-21 21-Mar-22 31% 100% 31% 100.0% 31%
A78500 Piping Sleepers - Concrete Works 60 02-Jan-22 12-Apr-22 69% 100% 69% 100.0% 69%
Fences (External) 246 11-Oct-21 01-Dec-22 23% 100% 23% 100% 23%
Earth Work 156 11-Oct-21 04-Jun-22 20% 100.0% 20.2% 100.0% 20%
Page 218 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91910 Piles Works - Fences 150 14-Mar-22 28-May-22 17% 100% 17% 100.0% 17%
A77930 Cut Works - Fences 150 11-Oct-21 30-Apr-22 23% 100% 23% 100.0% 23%
A77950 Backfilling - Fences 150 11-Nov-21 04-Jun-22 60% 100% 60% 100.0% 60%
Concrete Works 222 11-Jan-22 29-Nov-22 76% 100.0% 76.2% 99.6% 76%
A5700 Plain Concrete 150 11-Jan-22 04-Aug-22 12% 100% 12% 100.0% 12%
A56941 RC Foundations 150 12-Feb-22 04-Sep-22 53% 100% 53% 100.0% 53%
A56951 RC Coulmns & Beams 150 14-Mar-22 04-Oct-22 19% 100% 19% 100.0% 19%
A56961 Insulation 150 14-Mar-22 04-Oct-22 3% 100% 3% 100% 3%
A56971 Brick Works 150 15-May-22 29-Nov-22 14% 100% 14% 97% 13%
Wiremech 150 10-Jul-22 01-Dec-22 4% 100.0% 3.6% 98.0% 4%
A56981 Wiremech 150 10-Jul-22 01-Dec-22 100% 100% 100% 98% 98%
Gates 180 12-Jun-22 01-Dec-22 3% 100% 3% 95% 3%
A57041 Civil Works 60 12-Jun-22 21-Aug-22 9% 100% 9% 100.0% 9%
A57051 Gates Steel Delivery 90 12-Jun-22 21-Aug-22 45% 100% 45% 100% 45%
A57061 Gates Fabrication & Installation 90 22-Aug-22 01-Dec-22 45% 100% 45% 90% 41%
New Pipe Racks 180 12-Jun-22 01-Dec-22 0% 100% 0% 100% 0%
A91785 New Pipe Racks - Piles Works 60 12-Jun-22 21-Aug-22 41% 100% 41% 100.0% 41%
A92700 New Pipe Racks - Cut Works 90 12-Jun-22 21-Aug-22 4% 100% 4% 100.0% 4%
A92710 New Pipe Racks - Backfilling Works 90 12-Jun-22 21-Aug-22 22% 100% 22% 100.0% 22%
A92690 New Pipe Racks - Concrete Works 90 12-Jun-22 21-Aug-22 34% 100% 34% 100.0% 34%
Lighting Poles - Civil 180 21-Dec-21 28-Feb-22 1% 100% 1% 95% 1%
A91920 Lighting Poles - Piles 60 21-Dec-21 14-Feb-22 47% 100% 47% 100.0% 47%
A57051 Lighting Poles - Foundations 90 04-Jan-22 28-Feb-22 53% 100% 53% 91% 48%
Piping Works 217 13-Jan-22 27-Jun-22 9% 100.0% 8.9% 69.1% 6%
Page 219 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Industrial (Indust.-Raw-Reject-Process-Demi) 115 01-Jan-22 31-May-22 4% 100% 3.9% 29% 1%
A58221 Piping & Piping Supports Fab. (SS) 43 01-Jan-22 20-Apr-22 64% 100% 64% 25% 16%
A58101 Piping & Piping Supports Erection (SS) 23 10-Feb-22 31-May-22 36% 100% 36% 35% 13%
HDPE & PP 115 #REF! 31-May-22 79% 100% 79.4% 82% 65%
A58101 Piping & Piping Supports Erection 23 10-Feb-22 31-May-22 100% 100% 100% 82% 82%
Piping Hydrotest & Re-Instatment 14 25-Apr-22 22-Jun-22 16% 100% 16% 18% 3%
A2010 Piping Hydrotest 14 25-Apr-22 15-Jun-22 50% 100% 50% 35% 18%
A79390 Re-Instatement & Touch Up 14 02-May-22 22-Jun-22 50% 100% 50%
Control & Safety Valves Erection 14 16-Jun-22 27-Jun-22 1% 100% 1%
A79380 Control & Safety Valves Erection 14 16-Jun-22 27-Jun-22 100% 100% 100%
Tanks Erection 205 01-Nov-21 06-Jun-22 9% 100.0% 9.3% 100.0% 9%
Industrial Raw Water Tank (101) 108 01-Nov-21 23-May-22 32% 100% 32% 100% 32%
A7300 Bottom, Shell & Top 78 01-Nov-21 12-Apr-22 78% 100% 78% 100% 78%
A79170 Hydrotest 6 13-Apr-22 19-Apr-22 2% 100% 2% 100% 2%
A79180 Sandblasting & Painting 12 20-Apr-22 09-May-22 15% 100% 15% 100% 15%
A79190 Accessories Erection 12 10-May-22 23-May-22 4% 100% 4% 100% 4%
DEMI Water Tank (103) 114 24-Nov-21 30-May-22 15% 100% 15% 100% 15%
A76110 Bottom, Shell & Top 84 24-Nov-21 19-Apr-22 74% 100% 74% 100% 74%
A79200 Hydrotest 6 20-Apr-22 27-Apr-22 4% 100% 4% 100% 4%
A79210 Sandblasting & Painting 12 28-Apr-22 16-May-22 16% 100% 16% 100% 16%
A79220 Accessories Erection 12 17-May-22 30-May-22 6% 100% 6% 100% 6%
Process Water Tank (102) 120 14-Nov-21 06-Jun-22 21% 100% 21% 100% 21%
A76120 Bottom, Shell & Top 87 14-Nov-21 26-Apr-22 78% 100% 78% 100% 78%
A79230 Hydrotest 6 28-Apr-22 09-May-22 3% 100% 3% 100% 3%
Page 220 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A79240 Sandblasting & Painting 12 10-May-22 23-May-22 15% 100% 15% 100% 15%
A79250 Accessories Erection 12 24-May-22 06-Jun-22 5% 100% 5% 100% 5%
Potable / Reject Water Tanks 36 07-Mar-22 17-Apr-22 2% 100% 2% 100% 2%
A76130 Potable Water Tank Erection 24 07-Mar-22 03-Apr-22 80% 100% 80% 100% 80%
A79280 Accessories Erection 12 04-Apr-22 17-Apr-22 20% 100% 20% 100% 20%
Fire Water Tanks 102 01-Mar-22 29-May-22 29% 100% 29% 100% 29%
A76150 Bottom, Shell & Top 72 01-Mar-22 02-May-22 75% 100% 75% 100% 75%
A79320 Hydrotest 6 07-May-22 12-May-22 2% 100% 2% 100% 2%
A79330 Sandblasting & Painting 12 14-May-22 26-May-22 15% 100% 15% 100% 15%
A79340 Accessories Erection 12 28-May-22 06-Jun-22 8% 100% 8% 100% 8%
OSBL- Electrical Works 201 08-Dec-21 30-Aug-22 4% 100.0% 3.6% 76.1% 3%
Earthing & Lightning Protection 101 08-Dec-21 14-Jun-22 9% 100% 9% 91% 8%
A7360 Earthing - Rods Installation 30 08-Dec-21 30-Jan-22 12% 100% 12% 47% 6%
A79450 Earthing - Cable Laying 60 31-Jan-22 23-Apr-22 100% 50%
A79460 Earthing - Termination 65 07-Feb-22 02-May-22 17% 100% 17% 92% 16%
A79470 Earthing - Bars & C-Clamps Installation 60 31-Jan-22 23-Apr-22 35% 100% 35% 97% 34%
A80740 Lightning Protection Works 45 24-Feb-22 14-Jun-22 36% 100% 36% 100% 36%
Electrical Connections 139 19-Feb-22 07-May-22 52% 100% 52% 91% 48%
OSBL - Cables Laying From Sub-Station to All Buildings,
A79480 90 19-Feb-22 17-Apr-22 86% 100% 86% 94.30% 81%
Packages & Pumps Station
A79490 OSBL - Cables Terminations 47 05-Mar-22 07-May-22 14% 100% 14% 73% 10%
Outdoor Lighting 176 01-Mar-22 30-Aug-22 39% 100% 39% 53% 20%
A7345 Lighting Poles Installation (street Lighting) 122 01-Mar-22 19-Jul-22 20% 100% 20% 70% 14%
A78990 Cable Laying (outdoor - OSBL) 122 13-Mar-22 31-Jul-22 25% 100% 25% 86% 21%
A79000 Lighting Fixtures (Outdoor) 122 27-Mar-22 14-Aug-22 10% 100% 10% 57% 5%
Page 221 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A79000 JB's Installation (Outdoor) 122 27-Mar-22 14-Aug-22 10% 100% 10% 31% 3%
A79010 Termination (Lighting - OSBL) 122 12-Apr-22 30-Aug-22 36% 100% 36% 25% 9%
OSBL - Instrumentation Works 122 01-Mar-22 04-Jun-22 1% 100.0% 1.3% 43.1% 1%
A7485 OSBL- Inst. - Cable Trays Installation 52 22-Mar-22 12-May-22 100%
A79510 OSBL - Inst. - Cable Pulling 52 30-Mar-22 21-May-22 62% 100% 62% 56% 35%
A79520 OSBL - Inst. - J.B's & Local Pannels 52 05-Mar-22 07-Apr-22 16% 100% 16%
A79530 OSBL - Inst. - Field Instrument Calibrations 18 01-Mar-22 04-Apr-22 3% 100% 3%
A79540 OSBL - Field Instrument Installation 34 01-Mar-22 04-Apr-22 6% 100% 6%
A79550 OSBL- Inst. - Terminations 52 13-Apr-22 04-Jun-22 3% 100% 3%
A83120 OSBL- Inst. - Cable Trays Supports Fab. & Erection 36 01-Mar-22 18-Mar-22 3% 100% 3% 100% 3%
A83130 OSBL- Inst. - Tubing Installation 52 05-Mar-22 07-Apr-22 7% 100% 7% 80% 6%
OSBL - F&G 85 19-Mar-22 01-Jun-22 1% 100.0% 0.8% 66.0% 1%
A79560 OSBL - F&G - Cable Trays Installation 20 16-Apr-22 18-May-22 40% 100% 40% 100% 40%
A79570 OSBL - F&G - J.B's & Local Pannels 20 16-Apr-22 18-May-22 1% 100% 1%
A79580 OSBL - F&G - Cable Pulling 20 23-Apr-22 25-May-22 27% 100% 27%
A79590 OSBL - F&G - Terminations 20 02-May-22 01-Jun-22 4% 100% 4%
A83100 OSBL - F&G - Cable Trays Supports Fab. & Erection 20 19-Mar-22 16-Apr-22 26% 100% 26% 100% 26%
A83110 OSBL - F&G - Detectors 20 16-Apr-22 18-May-22 3% 100% 3%
Outdoor - Telecommunication 45 20-Jan-22 07-Jun-22 2% 100.0% 1.8% 36.5% 1%
Outdoor - Fire Alarm 36 20-Jan-22 07-May-22 14% 100% 14% 21% 3%
A83140 OSBL - Fire Alarm - Cable Trays Supports Fab. & Erection 12 20-Jan-22 27-Feb-22 6% 100% 6% 100% 6%
A83150 OSBL - Fire Alarm - Cable Trays Installation 6 05-Feb-22 05-Apr-22 9% 100% 9% 100% 9%
A83160 OSBL - Fire Alarm - JB's Installation 6 28-Feb-22 05-Apr-22 2% 100% 2%
Page 222 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83170 OSBL - Fire Detectors Installation 6 28-Feb-22 05-Apr-22 12% 100% 12%
A83180 OSBL - Fire Alarm - Cable Pulling 12 14-Mar-22 19-Apr-22 43% 100% 43% 15% 6%
A83190 OSBL - Fire Alarm - Termination 6 26-Mar-22 07-May-22 29% 100% 29%
Outdoor - Public Adress 34 29-Jan-22 27-Apr-22 17% 100% 17% 3% 1%
OSBL - Public Adress - Cable Trays Supports Fab. &
A83200 12 29-Jan-22 03-Mar-22 1% 100% 1% 100% 1%
Erection
A83210 OSBL - Public Adress - Cable Trays Installation 6 05-Mar-22 07-Apr-22 2% 100% 2% 100% 2%
A83220 OSBL - Public Adress - JB's Installation 6 05-Mar-22 07-Apr-22 3% 100% 3%
A83230 OSBL - Public Adress - Speakers & Flashers Installation 6 05-Mar-22 07-Apr-22 19% 100% 19%
A83240 OSBL - Public Adress - Cable Pulling 10 16-Mar-22 19-Apr-22 29% 100% 29%
A83250 OSBL - Public Adress - Termination 6 23-Mar-22 27-Apr-22 45% 100% 45%
Outdoor - CCTV 34 08-Mar-22 23-Apr-22 42% 100% 42% 57% 24%
A83260 OSBL - CCTV - Cable Trays Supports Fab. & Erection 12 08-Mar-22 23-Mar-22 1% 100% 1% 70% 1%
A83270 OSBL - CCTV - Cable Trays Installation 6 24-Mar-22 09-Apr-22 66% 100% 66% 84% 56%
A83280 OSBL - CCTV - JB's Installation 6 24-Mar-22 09-Apr-22 1% 100% 1%
A83290 OSBL - CCTV - Camera Installation 6 24-Mar-22 09-Apr-22 5% 100% 5%
A83300 OSBL - CCTV - Cable Pulling 10 31-Mar-22 16-Apr-22 15% 100% 15%
A83310 OSBL - CCTV - Termination 6 07-Apr-22 23-Apr-22 11% 100% 11%
Outdoor - Data Network / IP telephone (Incl. Fiber Optical Cables) 34 20-Mar-22 28-Apr-22 27% 100% 27% 33% 9%
OSBL - Data Network & IP Telephone - Cable Trays
A83320 12 24-Mar-22 28-Apr-22 13% 100% 13% 100% 13%
Supports Fab. & Erection
OSBL - Data Network & IP Telephone - Cable Trays
A83330 6 31-Mar-22 10-May-22 19% 100% 19% 100% 19%
Installation
A83340 OSBL - Data Network & IP Telephone - JB's Installation 6 30-Apr-22 07-Jun-22 1% 100% 1%
R0069 CUSTOMER installation of rails for digester 4 4.5 4.50 100% 0.08%
000107 2310 refiner system 1 4 165.1 156.85 95.0% 2.87%
000108 2332 refiner system 2 4 160.4 152.38 95.0% 2.79%
‐ ‐ main refiner unit (main & start motors) 4 76 ton done
‐ ‐ emergency lubrication refiner 4 ‐
‐ ‐ feed screw 4 ‐ done
‐ ‐ discharge screw 4 ‐ done
‐ ‐ digester 1st level 4 ‐ done
‐ ‐ plug screw 4 ‐ done
‐ ‐ blow back valve 4 ‐
‐ ‐ chip chute plug screw 4 ‐ done
‐ ‐ pre heating screw 4 ‐ done
‐ ‐ pin drum feeder 4 ‐ done
‐ ‐ main machinery complete 4 ‐ done
‐ CUSTOMER chip chute pin drum feeder 4 ‐
‐ ‐ central lubrication 4 ‐
‐ ‐ hydraulic unit 4 ‐
‐ ‐ sealing water feed screw 4 ‐
‐ ‐ sealing water unit mechanical seal 4 ‐
‐ ‐ hot water injection grinding room 4 ‐
‐ ‐ hot water injection pre heating screw 4 ‐
‐ ‐ Start cyclone 4 ‐ done
‐ ‐ piping & sealing 4 ‐
‐ CUSTOMER Vessel (Drain Box) ‐ Group 2310 / 2332 4 10.0
Dryer G.2400 (BÜTTNER) 6%
TR0032/33 CUSTOMER High Efficiency Cyclone ‐ Group 2420 2 50.2 50.20 100.0% 0.92%
TR0009 CUSTOMER Mixing chamber ‐ Group 2420‐022 ‐ Dryer (CH‐1030) 7 13.7 13.70 100% 0.25%
000159 2594 diverter flap on top sifter 2 1.3 1.30 100% 0.02%
000158 2595 distribution flap for sep. to sifter 2 0.9 0.90 100% 0.02%
000157 2596 twin screw conveyor 2 9.6 9.60 100% 0.18%
000155 2597 rotary airlock 2 1.2 1.20 100% 0.02%
000156 2598 rotary airlock 2 1.2 1.20 100% 0.02%
Straw Fibre Sifter System G.2600 6%
000173 2770 radial fan (pneumatic transport) 2 0.7 0.70 100% 0.01%
000172 2771 filter unit 2 5.6 2.80 50% 0.05%
000174 2780 heat exchanger 2 1.2 1.20 100% 0.02%
000176 2781 trough chain conveyor 2 5.7 5.70 100% 0.10%
000175
2782/2783 HP rotary airlock with drive 5&3 1.2 1.20 100% 0.02%
'000603
000177 2784 pulverizer 3 4.9 2.62 54% 0.05%
000178 2785 radial fan (pneumatic transport) 3 6.5 6.50 100% 0.12%
000179 2786 round filter 3 4.5 4.37 97% 0.08%
000180 2787/2788 diverter flap on top silo 7140 3 0.7 0.70 100% 0.01%
Glue Preparation System G.3200 6%
000184
3211 PMDI storage & equipment 7 46.0 46.00 100% 0.84%
'000185
000183 CUSTOMER PMDI Storage Tank (4a.) 4 56.0 56.00 100% 1.02%
000190 3215.201 water transfer sys. (filter 1) 4 1.5 0.45 30% 0.01%
000191 3215.205 water transfer sys. (filter 2) 4 1.5 0.45 30% 0.01%
000194 3226.101 truck discharging station 4 2.0 2.00 100% 0.04%
000193 CUSTOMER Emulsion Storage Tank (7ea.) ‐ Group 3226 4 56.0 56.00 100% 1.02%
Page 227 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000195
3226.103 emulsion tanks/bins accessories 4 2.0 0.70 35% 0.01%
'000196
000197 3226.2 emulsion transfer system 4 0.6 0.60 100% 0.01%
Glue Dosing System G.3300 (Dosing ‐ Cleaning & Protection Agents ‐ 6%
000244
3905 extraction system (fan) 2 2.4 2.40 100% 0.04%
'000245
Stations under Matformer G.4300 (Forming Line) 6%
000253 4399.1 foundation plates of forming line 1 0.9 0.90 100% 0.02%
000254 4310.111 tensioning station 1 3.3 3.30 100% 0.06%
000255 4310.211 Table for bottom spraying divice 1 1.0 1.00 100% 0.02%
000256 4310.311 Intermediate stations under the mat former 1 5.3 5.30 100% 0.10%
000257 4320 belt scale 1 0.8 0.80 100% 0.01%
Matformer G.4200 (Forming Line) 6%
000460 4910 Positioning radials fan for Forming line 2 3.6 3.60 100% 0.07%
000461 4911 Positioning and assembly from filter unit 2 12.6 12.60 100% 0.23%
000462 4920 Positioning radials fan for trimming and cross‐cut 2 4.9 4.90 100% 0.09%
000463 4946 Positioning radials fan for rejected material 2 4.3 4.30 100% 0.08%
000464 4947 Positioning and assembly from filter unit 2 13.0 13.00 100% 0.24%
000465 4949 Rotary Valve & Diverter flap on top of the Silo (7120) 2 6.6 6.60 100% 0.12%
000466 4970 Positioning radials fan for diagonal saw 4 3.0 3.00 100% 0.05%
000467 4971 round filter (DD‐ and trimming saw) 4 12.3 11.81 96% 0.22%
000468 4975 Positioning radial fan 2 1.5 1.50 100% 0.03%
000469
4976 Positioning and assembly from round filter 5 7.5 7.13 95% 0.13%
'000599
A76490 CUSTOMER Cyclone Seperator ‐ Group 4910 2 7.3 7.30 100% 0.13%
A76500 CUSTOMER Cyclone Seperator ‐ Group 4920 1 7.5 7.50 100% 0.14%
A76510 CUSTOMER Cyclone Seperator ‐ Group 4946 2 11.8 11.80 100% 0.22%
Cooling & Stacking Line G.5200 6%
000477
'000479
5253 cooling turner 1 1 10.5 10.50 100% 0.19%
'000481
'000484
000478
'000480
5256/5259 cooling turner 2 1 21.0 21.00 100% 0.38%
'000482
'000487
000483 5252/5254 roller conveyor 1 1 4.5 4.50 100% 0.08%
000484 5255/5257 belt conveyor for cooling turner 1 6.2 6.16 100% 0.11%
000485 5258/5260 roller conveyor 2 1 7.7 7.70 100% 0.14%
000488 5250 Board pusher for cooling‐turner 1 0.8 0.80 100% 0.01%
000489
5269 Roller conveyor between cooling‐turner & stacking table 1 2.4 2.40 100% 0.04%
'000490
000491 5270 Stacking table 1 5.3 5.30 100% 0.10%
CUSTOMER installation of rails for gripper carraige 1 4.1 4.10 100% 0.07%
000492
5271.1 Gripper carriage 1 7.4 7.40 100% 0.14%
000493 5271.2 Runway for gripper carriage 1 21.2 21.15 100% 0.39%
000496 5211 Roller conveyor after ContiRoll‐press outfeed 1 2.4
000497 5212 Longitudinal trimming saw 1 3.7
Page 231 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000498 5216 Saw table for Multi‐diagonal saw 1 4.5
000499 5214 Multiple‐diagonal saw 1 8.8
000500 5218 Noise protected cabinet 1 0.8
000501 5217 Accel. roller conveyor after Multi‐diagonal saw 1 2.8
000502 5221 Belt conveyor on raw board scale 1 1.8
000503 5222 Raw board scale 1 0.3
000504 5226 Stacking roller conveyor under reject board station 1 4.7 4.70 100% 0.09%
000505 5225 Reject board station 1 11.1 11.10 100% 0.20%
000506 5227 Roller conveyor for recject board station 1 2.2
000507 5200.04 Limit switches equipment 1 1.2
000510 sub 5211 Safety fences for cool‐ and stacking line 1 0.3
000511 5200.043/5000 Safety equipment 1 0.6
Storage System G.5300 6%
000514 CUSTOMER installation of rails for storage system 1 89.5 44.75 50% 0.82%
000515 5311 Base vehicle 1 12.7 12.70 100% 0.23%
000516 5312 Basic carriage SFG 1 1 3.4
000517 5313 Basic carriage SFG 2 1 3.4
000518 5390 Limit switches equipment 1 0.8
000520
5300 safety fences & sensors for storage 1 0.5
'000521
Sanding Line G.5400 6%
000551 5478/5479 intermediate roller conveyor/stach conveyor & station 1 3.2 3.20 100% 0.06%
000552 5483/5484 intermediate roller conveyor/stach conveyor & station 1 3.2 3.20 100% 0.06%
000553 5491 Transfer carriage‐ stack 1 2.0 2.00 100% 0.04%
000554 5492 Transfer carriage‐ stack 1 4.2 4.20 100% 0.08%
000555 5490 Protection board feeder 1 6.8 6.80 100% 0.12%
000556 5493 Stack chain conveyor 1 3.5 3.50 100% 0.06%
000557 5494 Stack roller conveyor 1 2.8 2.80 100% 0.05%
000560
'000563 5400 safety fences, sensors & limit switches 1 2.4 1.56 65% 0.03%
'000564
Packing Line G.5700 6%
000588 7110 discharge device & comp. for sanding silo 3 7.7 6.81 89% 0.12%
'000589 CUSTOMER Sanding dust Silo ‐ Group 7110 3 60.0 60.00 100% 1.10%
000590 7112 HP rotary airlock with drive 3 0.8 0.40 50% 0.01%
000592 7120 discharge device & comp. for reject fiber silo 2 14.0 12.46 89% 0.23%
'000593 CUSTOMER Reject Fiber Silo ‐ Group 7120 2 60.0 60.00 100% 1.10%
000595 7130 discharge device & comp. for saw dust silo 5 9.1 8.10 89% 0.15%
'000596 CUSTOMER Saw Dust Silo ‐ Group 7130 5 55.0 55.00 100% 1.01%
000597 7131 Screw conveyor straw fibre 4 1.5 1.50 100% 0.03%
000598 7132 HP rotary airlock with drive 4 1.4 1.40 100% 0.03%
000601 7140 discharge device & comp. for pulverizer silo 3 11.5 10.47 91% 0.19%
'000602 CUSTOMER Pulverizer Silo ‐ Group 7140 3 65.0 65.00 100% 1.19%
Energy Plant G.7300 (BÜTTNER) 6%