You are on page 1of 234

205,000 M3/Y

MEDIUM- DENSITY FIBERBOARD


MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

WEEKLY PROGRESS REPORT

Page 1 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Report Contents:
1. HSSE

2. Planning and Progress

3. Activities Performed This Week & Planned for Next Week

4. Received Bulk materials & Equipment

5. Manufacturing (Workshop Activities)

6. Construction (Planned and Actual quantities)

7. Skyline Report

8. Weekly Manpower, Man-hours & Equipment

9. Areas of concern.

10. List of correspondence requiring response

11. Photos

12. Attachments

10.1 Skyline

10.2 Progress Summary

Page 2 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

1. HSSE
Total to
NO Type of Measures Last Week Pervious Notes
Date

1 Total Man hours 58,440 4,271,545 4,329,985


2 TOTAL. Safe Man hours 58,440 2,613,255 2,671,695
3 Near Miss Report 0 56 56
4 Hazard Observation / Stop Card 234 10,033 10,267
5 Medical Treatment Cases 0 3 3
6 First aid injury reports 0 4 4
7 Lost time injury reports (LTI) 0 3 3
8 Days Away from Work (DAFWC) 0 241 241
9 Restricted Work Case (RWC) 0 0 0
10 Vehicle accidents 0 1 1
11 Safe kilometers traveled (Km) 12,212 910,377 922,589
12 Emergency exercises/drills 0 2 2
13 Training Hours 8 4,233 4,241
14 Tool Box Talk No. 985 41,465 42,450
15 Work Permit No. 182 9,665 9,847
16 HSE Site inspection / Audits 4 416 420
17 Vehicle’s inspection 11 781 792
18 HSE Meeting 0 15 15
19 Management walks through inspection 0 121 121
20 Monthly management HSE meetings 0 26 26
21 HSE campaigns Work Authorization 15
22 Environmental occurrences 0 0 0

Page 3 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

2. Planning and Progress


2.1 Project Summary

Planned Dates
Planned Actual Dev/
Activity R. Wt.
Start Date Finish Date B/L (%) (%) Item

MDF PROJECT 7-Jul-20 07-Feb-23 100% 100.0% 86.9% -13.1%


Professional Services 7-Jul-20 07-Nov-22 10% 100.0% 98.8% -1.2%
Engineering 7-Jul-20 07-Nov-22 50% 100% 97.6%
Procurement Services 11-Aug-20 29-May-22 40% 100% 100%
Logistics 7-Mar-21 10-Nov-21 10% 100% 100%
Material Supply 01-Sep-20 01-Jul-22 32% 100.0% 93.2% -6.8%
Manufacturing 16-Dec-20 07-Aug-22 10% 100.0% 98.2% -1.8%
Construction & Pre-
7-Jul-20 07-Dec-22 45% 100.0% 83.1% -16.9%
Commissioning
Commissioning & Start Up 07-Jun-22 07-Feb-23 3% 100.0% -100.0%

2.2 Detailed Progress & S-Curves


 Level-2 & 3 Revised Schedule (Rev.2) [B/L] has been Approved on 14/12/2021.
 Level-2 & 3 Revised Schedule (Rev.6) has been submitted for WOTECH Approval on
11/01/2023.

2.3 In Progress Activities


2.3.1 Engineering Works
 Total issue for Review = 1,253 is out of 1,253
 Total issue for Approve = 1,253 is out of 1,253
 Total issue for Construction = 1,253 is out of 1,253
 Total issue for As Built = 397 is out of 1,667 (requisitions are included)
2.3.2 Procurement Services
 Complete issuing PO =140 is out of 141 (excluding st. str., equipment, ducts and others).
 Complete arrived at site PO = 100 out of 141 (excluding st. str., equipment, ducts and others).
 Complete partial arrived at site = 23 out of 140 (excluding st. str., equipment, ducts and others).
2.3.3 Manufacturing
 Continue fabrication of the st. st. in IDKU & ABIS workshops (5,438 ton out of 5,510 ton).
 Continue fabrication of the ISBL-equipment in IDKU workshop (774 ton out of 776 ton).

Page 4 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

 Continue fabrication of the ducts by SHOTMED workshop under supervision of Qattamiya


workshop (442 ton out of 451 ton).
 Complete fabrication of the OSBL-tanks in IDKU workshop (501 ton).
 Complete cable trays supports fabrication in IDKU workshop (20.2 ton).
 Continue piping supports fabrication in IDKU workshop (103 ton out of 139 ton).

2.3.4 Construction
 Civil Works
 Continue cutting works for Sewer & Storm network.
 Continue backfilling works for Roads.
 Continue Concrete works at OSBL Area.
 Continue finishing works.
 Continue Interlocks erection (33,200 m2 out of 111,700 m2).
 Mechanical Works
 Continue Steel Structure erection works (5,325 ton out of 5,510 ton).
 Continue cladding works (50,138 m2 out of 60,000 m2).
 Continue grating erection (2,017 m2 out of 8,532 m2).
 Continue Ducts installation (360 ton out of 451 ton).
 Continue Equipment installation works for production line (4,695 ton out 5,470 ton).
 Complete Tanks erection works (501 ton) – Fire tank under painting.
 Continue Piping fabrication works in Maadia Workshops (25,085 D.I out of 33,279 D.I).
 Continue piping erection works (15,370 D.I out of 21,715 D.I).
 Continue HDPE piping erection works (31,955 D.I out of 40,000 D.I).
 Continue insulation works (852 m2 out of 26,800 m2).
 E&I Works
 Continue cable trays erection (21,695 M.L out of 26,000 M.L).
 Continue power and control cable laying works (308,041 M.L out of 353,500 M.L).
 Continue instrument cable laying works (120,779 M.L out of 359,000 M.L).
 Continue termination works (6,351 Ea. out of 16,736 Ea.).

Page 5 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

3. Activity performed This Week and Planned for Next Week


3.1 Professional Service: -
3.1.1 Engineering: -

3.1.1.1 IFR Status: -

Planned This Planned till


IFR (Actual Done)
Week Next Week
Discipline Total
This This To Next To
To Date
Week Week Date Week Date

Architecture 177 - 177 - 177 - 177


Civil 127 - 127 - 127 - 127
Civil Network 9 - 9 - 9 - 9
Cathodic Protection 28 - 28 - 28 - 28
Electrical 139 - 139 - 139 - 139
Fire - Fighting 31 - 31 - 31 - 31
HVAC 46 - 46 - 46 - 46
Instrumentation
38 - 38 - 38 - 38
(Control System)
Loss Prevention 59 - 59 - 59 - 59
Mechanical 17 - 17 - 17 - 17
Piping 26 - 26 - 26 - 26
Process 30 - 30 - 30 - 30
Steel Structure 340 - 340 - 340 - 340
Tanks 83 - 83 - 83 - 83
Fire & Gas 2 - 2 - 2 - 2
Telecommunication 101 - 101 - 101 - 101
Total 1,253 - 1,253 - 1,253 - 1,253

Page 6 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

3.1.1.2 IFA Status: -

Planned This Planned till


IFA (Actual Done)
Week Next Week
Discipline Total
This This To Next To
To Date
Week Week Date Week Date

Architecture 177 - 177 - 177 - 177

Civil 127 - 127 - 127 - 127

Civil Network 9 - 9 - 9 - 9

Cathodic Protection 28 - 28 - 28 - 28

Electrical 139 - 139 - 139 - 139

Fire - Fighting 31 - 31 - 31 - 31

HVAC 46 - 46 - 46 - 46
Instrumentation 38
38 - 38 - 38 -
(Control System)
Loss Prevention 59 - 59 - 59 - 59

Mechanical 17 - 17 - 17 - 17

Piping 26 - 26 - 26 - 26

Process 30 - 30 - 30 - 30

Steel Structure 340 - 340 - 340 - 340

Tanks 83 - 83 - 83 - 83

Fire & Gas 2 - 2 - 2 - 2

Telecommunication 101 - 101 - 101 - 101

Total 1,253 - 1,253 - 1,253 - 1,253

Page 7 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

3.1.1.3 IFC Status: -

Planned This Planned till Next


IFC (Actual Done)
Week Week
Discipline Total
This This Next
To Date To Date To Date
Week Week Week

Architecture 177 - 177 - 177 - 177

Civil 127 - 127 - 127 - 127

Civil Network 9 - 9 - 9 - 9

Cathodic Protection 28 - 28 - 28 - 28

Electrical 139 - 139 - 139 - 139

Fire - Fighting 31 - 31 - 31 - 31

HVAC 46 - 46 - 46 - 46
Instrumentation 38
38 - 38 - 38 -
(Control System)
Loss Prevention 59 - 59 - 59 - 59

Mechanical 17 - 17 - 17 - 17

Piping 26 - 26 - 26 - 26

Process 30 - 30 - 30 - 30

Steel Structure 340 - 340 - 340 - 340

Tanks 83 - 83 - 83 - 83

Fire & Gas 2 - 2 - 2 - 2

Telecommunication 101 - 101 - 101 - 101

Total 1,253 - 1,253 - 1,253 - 1,253

Page 8 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

3.1.1.4 As Built Status: -

Planned This Planned till Next


As Built (Actual Done)
Week Week
Discipline Total
This This Next
To Date To Date To Date
Week Week Week
As Built 1,667 - 397 - - - -

3.1.2 Procurement Service: -

MRQ (Actual
Planned This Week Planned Next Week
Done)
Commodities Total
This This Next
To Date To Date To Date
Week Week Week

Piping Bulk 6 - 6 - 6 - 6

Valves 7 - 7 - 7 - 7

Equipment &
8 - 8 - 8 - 8
Packages

Fire - Fighting 8 - 8 - 8 - 8

Fire & Gas 1 - 1 - 1 - 1

Instrumentation 6 - 6 - 6 - 6

Electrical 33 - 33 - 33 - 33

Telecommunication 13 - 13 - 13 - 13

Steel Structure 17 - 17 - 17 - 17

HVAC 13 - 13 - 13 - 13

Total 112 - 112 - 112 - 112

Page 9 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

3.1.3 Logistics: -
 None

3.2 Material Supply: -


3.2.1 Purchase Order Status (PO): -

Total PO (Actual Done)


Commodities Responsibility Qty
PO This week To Date
Piping Bulk 22 - 22
Valves 13 - 13
Equipment / Packages & Skids 6 - 6
Pumps 6 - 6
Fire & Gas 2 - 2
Fire- Fighting 7 - 7
Fire Alarm Engineering 1 1
Dept.
Electrical 47 - 47
Instrumentation (Control System) 24 - 24
Telecommunication 5 - 5
HVAC 1 - 1
Cathodic Protection 3 - 3
Others “Sec.6” 4 - 4
Sub-Total “Engineering Dept.” 141 - 141
Tanks 6 - 6
Steel Structure 23 - 23
Project (Site)
Bolts & Nuts 4 - 4
Others 16 - 16
Sub-Total “Project” 49 - 49
Total 190 - 190

Page 10 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

4. Received Bulk materials & Equipment


Commodities Unit Total Qty. Arrived at site
Piping
Piping (HDPE) Inch 40,000 40,000
Piping (CS& GALV) Inch 10,309 10,309
Piping (CS) Inch 26,713 15,890
Piping (SS) Inch 6,488 4,488
Piping (S.D) Inch 833 833
Valves
Valves Lot 100% 95%
Equipment / Packages & Skids
Air Compressors Ea. 7 7
Industrial water treatment PKG. PKG. 100% 70%
Truck Scale PKG. 100% 40%
Steam Traps Ea. 48 48
Pressure Reduction Skid (PRS) Ea. 1 1
Chemical Injection Skids PKG. 3 3
Pumps
Fire Water Pumps Ea. 6 6
Raw Water Pumps Ea. 5 5
Process Water Pumps Ea. 4 4
DEMI Water Pumps Ea. 2 2
Reject Pumps Ea. 5 5
Potable Water Pumps Ea. 2 2
Sewage Pumps Ea. 6 6
Sludge Pumps Ea. 2 2
Hot Water Pumps (Plot-4) Ea. 2 2
Fire & Gas
F&G Lot 100%
Fire- Fighting
Fire Fighting Equipment (PO 1043) Lot 100% 90%
Fire Fighting Equipment (PO 1043) Lot 100% 20%
Steel Bars For FF Network Ea. 1615 115
Portable Monitors Ea. 12 4
Flexible Hoses Ea. 705
Fire Fighting Nozzles Ea. 278 278
Fire Alarm
Fire Alarm Lot 100%

Page 11 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Electrical
Lighting Poles Ea. 880 880
Switch & Sockets Lot 100% 100%
Lighting Fixtures (Explosion Proof) Lot 100% 75%
Lighting Fixtures Lot 100% 90%
Earthing Cables M.L 15,000 15,000
Lightning Protection System Lot 100% 100%
MV Switchgear Ea. 23 23
LV Switchgear & Bus Duct Ea. 100 100
Transformers Ea. 12 12
AC UPS Ea. 4 2
DC UPS Ea. 4 4
Emergency Generator Ea. 1
Distribution Board Ea. 35 13
Power & Control Cables M.L 353,500 353,500
Cable Trays M.L 26,000 23,000
Explosion proof material Lot 100% 75%
Capacitor Banks Lot 100%
Cable Glands Lot 100% 100%
Reducers Ea. 710
Conduit M.L 7,000 7,000
Instrumentation (Control System)
Instrument Cables M.L 359,000 319,000
DCS Ea. 1
Cable Glands Lot 100% 100%
Instrument Bulk Material (Hook up) Lot 100% 100%
Instrument JB's Ea. 580 558
Analyzers Lot 100% 100%
Mechanical Level Indicators Lot 100% 100%
Field Instrument Ea. 340 335
Control Valves Ea. 47 28
Flow Meters Lot 100% 100%
Telecommunication
IP Telephone Lot 100% 60%
CCTV Lot 100% 20%
Public Address Lot 100%
Data Network Lot 100% 40%
Data Center Lot 100%
HVAC
HVAC Ea. 208 157

Page 12 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Cathodic Protection
Cathodic Protection Lot 100% 100%
Others “Sec.6”
Tank Agitators Lot 100% 100%
SS Explosion Proof Vent Lot 100% 100%
Over Head Crane Ea. 1 1
Straw Bale Grap for O.H.C Lot 100% 100%
Refractory Ton 275 275
Rails Ton 110 65
Mobile Fuel Station Ea. 1
Mirror Station Lot 100%
Sound / Noise Cabient Ea. 19
GRP Tank for Reject Water (150m3) Ea. 1
HDPE Tanks for Potable Water (20m3) Ea. 2 2
Oils Lot 100%
Safety Barriers & Fence M2 3,000
Electrical secured accesses door Ea. 75
Steel Structures, Plates, Supports & Grating
Steel Structure ton 5,510 5,480
Tank Plates ton 501 501
Grating M2 6,135 2,387
Chuqured Plates M2 1,105

Page 13 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

5. Manufacturing (Workshop Activities)

Act. Unit Total Qty. Plan Actual


Steel Structure ton 5,510 5,510 5,438
Equipment ton 776 776 774
Ducts ton 451 451 442
Tanks ton 501 501 501
Cable Tray Supports ton 20.2 20.2 20.2

Piping Supports ton 139 139 103


Total 7,397 7,397 7,278

Page 14 of 234
STEEL STRUCTURE STATUS FOR MDF PROJECT
As of date: 11‐02‐23

MATERIAL FABRICATION
TOTAL WEIGHT WSD DWG
AREA ARRIVE FOR
(TON) APPROVAL PLAN ACTUAL
FINAL FAB.
QTY QTY
PLOT‐1 1968 1968 1968 1968 1949
PLOT‐2 1240 1240 1240 1240 1208
PLOT‐3 346 346 345 346 343
PLOT‐4 807 807 807 807 805
PLOT‐5 310 310 310 310 310
PLOT‐6 365 365 365 365 365
PLOT‐7 165 165 165 165 163
Sheds 215 207 205 215 204
Filters 18 18 18 18 16.7
Pipe Racks 14 14 14 14 14
Platforms 31 31 29 31 29
Gates 31 31 31 31 31
TOTAL 5510 5502 5497 5510 5438

Page 15 of 234
MDF PROJECT : MEDIUM‐ DENSITY FIBERBOARD
Equipment Fabrication Status
As of Date:‐ 11‐2‐2023

ACTIVITY R.Wt. PLAN ACTUAL


ENGINEERING 10% 100% 100.0%
MATERIAL SUPPLY 20% 100.0% 100.0%
FABRICATION 70% 100.0% 99.7%
TOTAL 100% 100.0% 99.8%

Page 16 of 234
MDF PROJECT : MEDIUM‐ DENSITY FIBERBOARD
FABRICATION
As of Date:‐ 11‐2‐2023

WEIGHT
EQUIPMENT PLOT START FINISH PLAN ACTUAL DISPATCH
(TON)
CYCLONES 194.5
High Efficiency Cyclone ‐ Group 2420 2 21‐08‐22 10‐10‐22 50.2 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2531 2 30‐03‐21 18‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2532 2 30‐03‐21 16‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2533 2 19‐04‐21 22‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 2534 2 19‐04‐21 20‐01‐22 8.3 100.0% 100.0% 100.0%
Cyclone ‐ Group 2615/2616 1 09‐11‐21 21‐03‐22 36.5 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4910 2 06‐12‐21 06‐04‐22 7.3 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4920 1 17‐11‐21 15‐03‐22 7.5 100.0% 100.0% 100.0%
Cyclone Seperator ‐ Group 4946 2 06‐12‐21 03‐04‐22 11.8 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R1) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R2) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (R3) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L1) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L2) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
Cyclone Flue Gas ‐ Group 7385 (L3) 3 19‐04‐21 05‐01‐22 8.0 100.0% 100.0% 100.0%
CHAMBERS 77.4
Vertical combustion chamber ‐ Group 2425.016 ‐ EP (CH‐1000) 3 10‐10‐21 05‐01‐22 40.1 100.0% 100.0% 100.0%
Quench chamber ‐ Group 7385.060 ‐ EP (CH‐1010) 3 13‐10‐21 05‐01‐22 8.5 100.0% 100.0% 100.0%
Mixing chamber ‐ Group 2420‐022 ‐ Dryer (CH‐1030) 7 04‐12‐21 28‐02‐22 13.7 100.0% 100.0% 100.0%
Mixing chamber ‐ Group 7385.065 ‐ EP (CH‐1020) 3 11‐11‐21 30‐01‐22 15.1 100.0% 100.0% 100.0%
VESSELS 153.5
Vessel (Drain Box) ‐ Group 2310 / 2332 4 01‐01‐23 04‐02‐23 10.0 100.0% 80.0% 0.0%
Vessel (Vent Container) ‐ Group 7390 3 16‐12‐21 17‐02‐22 1.8 100.0% 100.0% 100.0%
Emulsion Storage Tank (7ea.) ‐ Group 3226 4 05‐07‐21 07‐02‐22 56.0 100.0% 100.0% 100.0%
Expansion Tank ‐ Group 7390 (T‐1040) 3 30‐10‐21 07‐02‐22 3.5 100.0% 100.0% 100.0%
Fill and Drain Tank ‐ Group 7390 (T‐1050) 3 30‐10‐21 07‐02‐22 7.0 100.0% 100.0% 100.0%
Hot Water Tank ‐ Group 4390 3 16‐12‐21 13‐02‐22 10.0 100.0% 100.0% 100.0%
Blow Down Tank ‐ Group 7395 3 23‐11‐21 27‐02‐22 1.1 100.0% 100.0% 100.0%
Feed water Tank with Deaerator ‐ Group 7395 3 27‐12‐21 07‐03‐22 8.1 100.0% 100.0% 100.0%
PMDI Storage Tank (4a.) 4 21‐08‐22 23‐08‐22 56.0 100.0% 100.0% 100.0%
STACKS 55
Emergency Stack ‐ Group 2425.016 (ST‐1000) 3 20‐10‐21 13‐01‐22 10 100.0% 100.0% 100.0%
Start‐up Stack ‐ Group 7385.090 (ST‐1010) 3 13‐11‐21 03‐03‐22 45 100.0% 100.0% 100.0%
THERMAL OIL HEATER 40
Thermal Oil Heater 3 03‐10‐21 24‐01‐22 40 100.0% 100.0% 100.0%
SILOS 250
Sanding dust Silo ‐ Group 7110 3 21‐08‐22 15‐10‐22 70 100.0% 100.0% 100.0%
Reject Fiber Silo ‐ Group 7120 2 21‐08‐22 14‐09‐22 60 100.0% 100.0% 100.0%
Saw Dust Silo ‐ Group 7130 5 09‐09‐21 30‐04‐22 55 100.0% 100.0% 100.0%
Pulverizer Silo ‐ Group 7140 3 09‐10‐21 30‐04‐22 65 100.0% 100.0% 100.0%
OTHERS 6.0
Safety Cooling Tank ‐ Group 7390 3 20‐12‐21 28‐02‐22 4.0 100.0% 100.0% 100.0%
Containers (2ea.) for Sludge and Solids
1 20‐02‐22 21‐04‐22 2.0 100.0% 100.0% 100.0%
(Sedimentation tank) ‐ Group 4550
TOTAL 776.4 100.0% 99.7% 98.7%

Page 17 of 234
Ducts Manufacturing Status
As of Date: 11‐Feb‐2023
Delivery to Site Plan Actual
Activity Weight (Ton) Plan Actual
(Ton) Qty. Qty.
Ducts Work 451.5 439.6 451.5 441.8 100.0% 98.5%
Engineering ‐ ‐ ‐ ‐ 100.0% 100.0%
Material Supply ‐ ‐ ‐ ‐ 100.0% 100.0%
Fabrication 451.5 439.6 100.0% 97.9%
Pneumatic Conveyors 256.8 256.73 256.8 256.8 100.0% 100.0%
Dryer Duct 38.8 38.76 38.8 38.8 100.0% 100.0%
Crude Gas Duct 31.4 31.36 31.4 31.4 100.0% 100.0%
Energy Plant 65.7 65.65 65.7 65.7 100.0% 100.0%
Connecting Chutes & Supports 58.9 47.14 58.9 49.2 100.0% 83.6%

Page 18 of 234
Ducts Manufacturing Status (Detailed)
As of Date: 11‐Feb‐2023

Activity Weight (Ton) R.W Start Date Finish Date Plan Actual

Ducts Work 451.5 100% 1‐Jun‐2021 4‐Feb‐2023 100.0% 98.5%


Engineering ‐ 10.0% 1‐Jun‐2021 28‐Dec‐2021 100.0% 100.0%

Pneumatic Conveyors ‐ 56.9% 1‐Jun‐2021 31‐Oct‐2021 100.0% 100.0%

Dryer Duct ‐ 8.6% 1‐Jun‐2021 29‐Sep‐2021 100.0% 100.0%

Crude Gas Duct ‐ 6.9% 1‐Jun‐2021 29‐Sep‐2021 100.0% 100.0%

Energy Plant ‐ 14.5% 1‐Jul‐2021 28‐Dec‐2021 100.0% 100.0%

Connecting Chutes ‐ 13.1% 1‐Jul‐2021 28‐Dec‐2021 100.0% 100.0%

Material Supply ‐ 20.0% 1‐Jul‐2021 15‐Feb‐2022 100.0% 100.0%

Ducts (Pneumatic, Dryer, Crude Gas, Energy Plant & Chutes) 100.0% 1‐Jul‐2021 15‐Feb‐2022 100.0% 100.0%

Material Requisition ‐ 10.0% 1‐Jul‐2021 6‐Jul‐2021 100.0% 100.0%

PO. ‐ 30.0% 7‐Jul‐2021 30‐Sep‐2021 100.0% 100.0%

Material Shipping & Arrival to WS ‐ 60.0% 1‐Sep‐2021 15‐Feb‐2022 100.0% 100.0%

Fabrication 451.5 70.0% 29‐Sep‐2021 4‐Feb‐2023 100.0% 97.9%

Pneumatic Conveyors 256.8 56.9% 29‐Sep‐2021 23‐May‐2022 100.0% 100.0%

Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (1) ‐ Group 1242 &1243 7.4 2.9% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 1321 / 1331 / 1341 8.1 3.1% 29‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 1531 3.8 1.5% 29‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (3) ‐ Group 1282 &1283 7.5 2.9% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 2531 / 2532 / 2533 / 2534 15.8 6.2% 21‐Nov‐2021 31‐Mar‐2022 100.0% 100.0%

Fab.‐ Duct Works & exhaust Pipes ‐ Chipper Line (2) ‐ Group 1262 &1263 7.6 3.0% 29‐Sep‐2021 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct Works & Pipes with bends and flanges ‐ Group 2615 / 2616 45.1 17.6% 2‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 2770 / 2780 / 2782 / 2785 15.1 5.9% 24‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 3905 8.4 3.3% 6‐Feb‐2022 16‐Mar‐2022 100.0% 100.0%

Fab.‐Duct Work, Pipes & Hoods ‐ Group 4550 20.9 8.1% 12‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐Duct Work & Pipes ‐ Group 4910 / 4920 / 4946 / 4970 / 4975 78.0 30.4% 29‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 5910 / 5917 / 5920 37.5 14.6% 31‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%

Fab.‐ Pipe ducts with bends and flanges ‐ Group 7112 / 7131 1.5 0.6% 2‐Apr‐2022 23‐May‐2022 100.0% 100.0%

Dryer Duct 38.8 8.6% 1‐Jan‐2023 4‐Feb‐2023 100.0% 100.0%

Fab.‐ Drier Duct (From Drier to High Effeciency Cyclone) ‐ Group 2420 38.8 100.0% 1‐Jan‐2023 4‐Feb‐2023 100.0% 100.0%

Crude Gas Duct 31.4 6.9% 12‐Jan‐2022 16‐Apr‐2022 100.0% 100.00%

Fab.‐ Crude gas duct ‐ Group 7410 31.4 100.0% 12‐Jan‐2022 16‐Apr‐2022 100.0% 100.0%

Energy Plant 65.7 14.5% 1‐Dec‐2021 4‐Feb‐2023 100.0% 100.0%

Fab.‐ Duct work from combustion air fan to the burner ‐ Group 7370.061 2.2 3.3% 6‐Dec‐2021 2‐Mar‐2022 100.0% 100.0%

Fab.‐ Duct work from cooling air fan to the burner ‐ Group 7370.062 1.3 1.9% 1‐Dec‐2021 2‐Mar‐2022 100.0% 100.0%

Fab.‐ Air Grader (new scope) 9.9 15.0% 1‐Jan‐2023 4‐Feb‐2023 100.0% 100.0%

Fab.‐ Transport pipes ducts for dust ‐ Group 7370 1.8 2.8% 21‐Aug‐2022 27‐Aug‐2022 100.0% 100.0%

Fab.‐ Duct work from ambient air fan to quench chamber ‐ Group 7385.060 0.3 0.4% 18‐Jan‐2022 2‐Feb‐2022 100.0% 100.0%

Fab.‐ Duct work from ambient air fan to mixing chamber ‐ Group 7385.065 0.8 1.3% 8‐Jan‐2022 13‐Mar‐2022 100.0% 100.0%

Fab.‐ Duct work from mixing chamber to cyclones ‐ Group 7385.065 0.8 1.3% 8‐Jan‐2022 13‐Mar‐2022 100.0% 100.0%

Fab.‐ Duct work from thermal oil heater to mixing chamber ‐ Group 7385.065 0.8 1.3% 25‐Dec‐2021 21‐Feb‐2022 100.0% 100.0%

Fab.‐ Duct work from dust collector (Cyclones) to Ash Crews ‐ Group 7385.080 10.5 15.9% 10‐Feb‐2022 4‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct work from dust collector (Cyclones) to Main ID fan ‐ Group 7385.080 10.5 15.9% 10‐Feb‐2022 4‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct work from the Main ID fan to Dryer Mixing Chamber ‐ Group 7385.090 5.7 8.6% 28‐Feb‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct work from the main id fan to start up stack ‐ Group 7385.090 5.7 8.6% 28‐Feb‐2022 16‐Apr‐2022 100.0% 100.0%

Fab.‐ Duct work from thermal oil heater fan to mixing chamber ‐ Group 7390 7.7 11.8% 22‐Jan‐2022 16‐Mar‐2022 100.0% 100.0%

Fab.‐ Duct work from thermal oil heater to thermal oil heater fan ‐ Group 7390 7.7 11.8% 3‐Feb‐2022 28‐Mar‐2022 100.0% 100.0%

Chutes ‐ Supports ‐ Silencer ‐ Doors & loose items 58.9 13.1% 21‐Aug‐2022 4‐Feb‐2023 100.0% 83.6%

Fab.‐ Chutes, Doors & loose items ‐ Group 2300 36.3 61.6% 1‐Jan‐2023 4‐Feb‐2023 100.0% 89.3%

Fab.‐ Pneumatic Supports ‐ Group 2600 16.9 28.6% 21‐Aug‐2022 31‐Oct‐2022 100.0% 100.0%

Fab.‐ Silencer ‐ Group 4200 5.8 9.8% 1‐Jan‐2023 4‐Feb‐2023 100.0%

Page 19 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

6. Construction

Actual
Total Plan Qty.
Activity Unit Actual Prog.
Qty. B/L
(%)

Civil Works
Cutting Works M3 712,000 712,000 711,070 99.9%
Backfilling Works M3 1,280,390 1,280,316 1,264,405 98.8%
Piles Work EA 4,483 4,483 4,483 100.0%
Pile Head Cracking EA 4,483 4,483 4,477 99.9%
Concrete Works M3 35,410 35,410 34,563 97.6%
Interlock M2 111,700 111,700 33,200 29.7%
Mechanical Works
Steel Structure Erection Ton 5,510 5,510 5,330 96.7%
Duct Erection Ton 452 452 374 82.9%
SK Equipment Installation Ton 5,470 5,470 4,739 86.6%
Piping Fabrication Inch 33,279 33,279 26,111 78.5%
Piping Erection Inch 21,715 21,715 15,781 72.7%
Piping Erection (SK) Inch 4,315 4,315 3,814 88.4%
Piping HDPE Inch 40,000 40,000 32,805 82.0%
Tanks Erection Ton 501 500 501 99.9%
Electrical Works
Cable Trays Installation M.L 26,000 26,000 23,500 90.4%
Cable Laying M.L 712,500 712,500 474,948 66.7%
Termination EA 16,736 16,736 7,132 42.6%
HVAC EA 208 208 101 48.6%
Lighting Fixtures EA 3,065 3,065 1,286 42.0%
Panels EA 486 486 450 92.6%
Transformers EA 12 12 12 100.0%

Page 20 of 234
Concrete Activity
Concrete for production line: Buildings: Others:
Total Total Total
Activity Plan Actual Activity Plan Actual Activity Plan Actual
Qty. Qty. Qty.
Plot‐1 9,301 9,301 9,301 TCF 670 670 670 Guard Towers 116 116 101
Plot‐2 3,294 3,294 3,294 Substation 440 440 440 Tanks (101‐102‐103) 252 252 252
Plot‐3 814.6 815 815 CH Warehouse 105 105 105 P.W Tank 84 84 84
Plot‐4 2441 2,441 2,441 Scale With Room 283 283 283 Fire Water Tank 60 60 60
Plot‐5 1448 1,448 1,448 HSE & Control Room 769.02 769 769 Pits & Sheds 839 839 385
Plot‐6 1993 1,993 1,993 Air Compressor Shed 277 277 277 P.W Network 228.31 228 228
Plot‐7 1163.5 1,164 1,164 Inds. Pump Station 158 158 158 Sewer Network 499 499 499
Control Room 15 15 15 P.W Pump Station 128 128 128 Storm Network 385 385 370
Switch Rooms 689 689 689 Reject Pump Station 83 83 83 Electrical Network 2968 2,968 2,968
Sub‐Total 21,159 21,159 21,159 Inds. Treatment PKG. 712 712 712 E&I Network 101 101 101
Fire Pump Shed 164 164 164 Piping Sleepers 89 89 89
New Switch Room 94 94 94 Fences (External) 2933 2,933 2,933
Main Security 56 56 56 Gates 60 60 60
Catch Basin , Sound
Security Building 56 56 56 Cabient ,Ditch & 612 612 524
Genrator
Mosque 90 90 90 Trenches Cover 940 940 665
Sub‐Total 4,085 4,085 4,085 Sub‐Total 10,166 #### 9,319

Total Qty. Plan Actual Deviation


Concrete Works
35,410 35,410 34,563 ‐847

Page 21 of 234
STEEL STRUCTURE STATUS FOR MDF PROJECT
As of date: 11‐02‐23

MATERIAL ERECTION
TOTAL WEIGHT WSD DWG
AREA ARRIVE FOR
(TON) APPROVAL PLAN ACTUAL
FINAL FAB.
QTY QTY
PLOT‐1 1968 1968 1968 1968 1945
PLOT‐2 1240 1240 1240 1240 1185
PLOT‐3 346 346 345 346 338
PLOT‐4 807 807 807 807 764
PLOT‐5 310 310 310 310 309
PLOT‐6 365 365 365 365 365
PLOT‐7 165 165 165 165 157
Sheds 215 207 205 215 186
Filters 18 18 18 18 16.0
Pipe Racks 14 14 14 14 14
Platforms 31 31 29 31 20
Gates 31 31 31 31 31
TOTAL 5510 5502 5497 5510 5330

Page 22 of 234
‫ﺍﻟﻣﺗﺎﺡ‬ ‫ﺍﻟﻣﺗﺑﻘﻰ‬ ‫ﺍﻟﻭﺣﺩﺓ ﺍﻟﻛﻣﻳﺔ ﺍﻻﺟﻣﺎﻟﻲ ﺍﻟﻛﻣﻳﺔ ﺍﻟﻣﻧﻔﺫﺓ‬ ‫ﺍﻟﻧﺷﺎﻁ‬
40,299 257,552 454,948 712,500 ‫ﻡﻁ‬ ‫ﺍﻋﻣﺎﻝ ﻓﺭﺩ ﺍﻟﻛﺎﺑﻼﺕ‬
Power & Control Cables for
405 18,484 143,516 162,000 ‫ﻡﻁ‬
Production Line (ISBL)
Power & Control Cables From Sub-
5,268 87,232 92,500 ‫ﻡﻁ‬ Station to All Buildings, Packages &
Pumps Station
Lighting cables for the Production
2,000 16,417 62,583 79,000 ‫ﻡﻁ‬
Line (ISBL)
Lighting cables for outdoor streets
100 2,868 17,132 20,000 ‫ﻡﻁ‬
(OSBL)
Instrument Cables for the Production
37,794 175,240 139,760 315,000 ‫ﻡﻁ‬
Line (ISBL)
Instrument Cables for Utilities
39,275 4,725 44,000 ‫ﻡﻁ‬
(OSBL)

Page 23 of 234
Piping Works In-MDF
1. Metalic Material (CS-SS-SD). As of Date: 9-Feb-23
Total % PO Avilable(From Total DI)
Total Total
Material Fabrication Total D.I PO No. Arrived to Type Arrived Fabricated Erecred Notes
Erection D.I Construction Not construction Done
D.I Site
84 100% ‫ﻣﺤﻠﻲ‬
85 100% ‫ﻣﺤﻠﻲ‬
Galvanized 440 100% ‫ﻣﺤﻠﻲ‬
0 7,911 7,911 6,395 0 0 0 7,407 7,407 0
"Threaded" 257 100% ‫ﻣﺤﻠﻲ‬
527 92% ‫ﻣﺤﻠﻲ‬
334 100% ‫ﺧﺎﺭﺟﻲ‬
84 100% ‫ﻣﺤﻠﻲ‬
3,733 16 85 100% ‫ﻣﺤﻠﻲ‬ 3,713 3,697 36 3,733 16 3,749
Carbon Steel-CS 440 100% ‫ﻣﺤﻠﻲ‬ .‫ ﺍﺳﺒﻮﻟﺔ ﻣﻦ ﺍﻟﻮﺭﺷﺔ ﻟﻠﺠﻠﻔﻨﺔ‬247 ‫* ﺗﻢ ﻧﻘﻞ‬
11,985
"Galvanized" 257 95% ‫ﻣﺤﻠﻲ‬ ‫ ﺇﺳﺒﻮﻟﺔ ﻣﻦ ﺍﻟﺠﻠﻔﻨﺔ ﺇﻟﻲ ﺍﻟﻤﻮﻗﻊ ﻭﺗﻢ ﺩﻫﺎﻧﻬﻢ‬234 ‫* ﺗﻢ ﻭﺻﻮﻝ‬
7,638 599 527 100% ‫ﻣﺤﻠﻲ‬ 4,612 4,000 3,638 4,089 0 4,089
334 100% ‫ﺧﺎﺭﺟﻲ‬
84 100% ‫ﻣﺤﻠﻲ‬
85 100% ‫ﻣﺤﻠﻲ‬
440 100% ‫ﻣﺤﻠﻲ‬
Carbon Steel-CS
16,447 9,470 25,917 527 92% ‫ﻣﺤﻠﻲ‬ 23,917 15,890 8,027 14,872 7,363 22,235 ‫ ﺑﻮﺻﺔ ﻗﻄﺮﻳﺔ‬927 ‫* ﺗﻢ ﺇﻋﺎﺩﺓ ﻟﺤﺎﻡ ﺑﺈﺟﻤﺎﻟﻲ ﻛﻤﻴﺔ‬
"Painted" ‫ﺧﺎﺭﺟﻲ‬
130 100%
"DIN"
‫ﺧﺎﺭﺟﻲ‬
478 100%
"DIN"
334 100% ‫ﺧﺎﺭﺟﻲ‬
205 100% ‫ﻣﺤﻠﻲ‬
Stainless Steel-SS 4,870 3,107 7,977 527 92% ‫ﻣﺤﻠﻲ‬ 5,977 3,354 4,623 1,968 907 2,875 .‫ ﺑﻮﺻﺔ ﻗﻄﺮﻳﺔ‬22 ‫* ﺗﻢ ﺇﻋﺎﺩﺓ ﻟﺤﺎﻡ ﻹﺟﻤﺎﻟﻲ ﻛﻤﻴﺔ‬
334 100% ‫ﺧﺎﺭﺟﻲ‬
128 100% ‫ﺧﺎﺭﺟﻲ‬
Supper Duplex-SD 626 613 1,239 883 0 1,239 482 88 570 0
262 100% ‫ﺧﺎﺭﺟﻲ‬
33,314 21,714 55,028 45,496 26,941 17,562 25,144 15,780 40,923

2. Non-Metalic Material (HDPE-PP)


Total % PO Avilable
Total Total
Material Fabrication Total D.I PO No. Arrived to Type Arrived Fabricated Erecred Notes
Erection D.I Construction Not construction Done
D.I Site
397 1 ‫ﻣﺤﻠﻲ‬ WP ‫ ﻣﺘﺮ ﻓﻲ ﻧﻈﺎﻡ‬760 ‫ ﻭ‬WF ‫ ﻣﺘﺮ ﻓﻲ ﻧﻈﺎﻡ ﺍﻟﺤﺮﻳﻖ‬6900 ‫*ﺗﻢ ﺇﻧﺰﺍﻝ‬
HDPE 0 39,037 39,037 34,992 34,992 4,045 0 31,955 31,955 ‫ ﺩﺍﺋﺮﺓ ﻟﻨﻈﺎﻡ ﺍﻟﺤﺮﻳﻖ‬32 ‫* ﺗﻢ ﻋﻤﻞ ﺍﺧﺘﺒﺎﺭ ﻟﻌﺪﺩ‬
106 1 ‫ﻣﺤﻠﻲ‬ Industrial Water ‫ ﺩﺍﺋﺮﺓ ﻟﻨﻈﺎﻡ ﺍﻟـ‬25 ‫* ﺗﻢ ﻋﻤﻞ ﺍﺧﺘﺒﺎﺭ ﻟﻌﺪﺩ‬
"‫ ﺍﻟﻤﻮﺭﺩ ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ )ﻓﻴﺘﻨﺞ( "ﺗﻢ ﻭﺻﻮﻟﻪ ﻟﻠﻤﻮﻗﻊ‬10393 ‫* ﺃﻣﺮ ﺗﻮﺭﻳﺪ‬
(‫ )ﻓﻴﺘﻨﺞ‬.‫ ﺍﻟﻤﻮﺭﺩ ﻭﻭﺗﺮ ﺗﻜﻨﻮﻟﻮﺟﻲ ﺑﺎﻳﺐ‬10394 ‫ﺃﻣﺮ ﺗﻮﺭﻳﺪ‬
10393 0% ‫ﻣﺤﻠﻲ‬
PP 0 963 963 0 0 963 0 0 0 (‫ )ﻣﻮﺍﺳﻴﺮ‬09/10/2022 ‫ ﻓﻲ ﺍﻟﺪﺭﺍﺳﺔ ﺍﻟﻔﻨﻴﺔ ﻣﻦ ﺗﺎﺭﻳﺦ‬229902 *
10394 0% ‫ﻣﺤﻠﻲ‬
(‫ )ﻣﺴﺎﻣﻴﺮ‬03/10/2022 ‫ ﻓﻲ ﺍﻟﺪﺭﺍﺳﺔ ﺍﻟﻔﻨﻴﺔ ﻣﻦ ﺗﺎﺭﻳﺦ‬23094
.‫ﻭﺑﺎﻗﻲ ﺍﻟﻔﻴﺘﻨﺞ ﺗﺤﺖ ﺍﻟﻄﺮﺡ‬

0 40,000 40,000 34,992 34,992 5,008 0 31,955 31,955


Page 24 of 234
MDF EQUIPMENT INSTALLATION STATUS
AS OF DATE: 11‐Feb‐23
Estimated Planned Qty Actual Qty
Group Plan Actual
Weight (ton) (ton) (ton)
MDF EQUIPMENT INSTALLATION 5470 5470 4739 100.0% 86.6%
Plot 1 (Production Line) 2342.5 2342 1918 100.0% 81.9%
Plot 2 (Drying & Sifting) 838.5 839 797 100.0% 95.0%
Plot 3 (Energy Plant) 801.1 801 610 100.0% 76.1%
Plot 4 (Refiner & Glue Preparation) 693.7 694 643 100.0% 92.7%
Plot 5 (Straw Milling & Screening) 342.5 342 341 100.0% 99.5%
Plot 6 (Straw Preparation) 318.5 318 318 100.0% 100.0%
Plot 7 (Dryer & Glue Dosing) 122.0 122 112 100.0% 91.5%
Other (G. 7500/7600/7700/8110) 11.3 11 0.4 100.0% 3.7%

Page 25 of 234
21-01-23 MDF TANKS
Capacit INNER TOTAL TOTAL PRE-FABRICATION
HEIGH (TON)
TANK NO. y DIA (M
T (M)
WEIGHT BOTTOM SHELL ROOF MISCELLANEOUS
(M3) ) (TON ) PLAN ACTUAL DONE % DONE % DONE % DONE %
Industrial Raw
3,350 23 10.8 166.2 166.19 166.19 42.17 100% 60.27 100% 55.00 100% 8.75 100%
Water Tank - 101A
Process Water Tank -
2,000 18 10.0 108.5 108.47 108.47 27.74 100% 42.49 100% 31.46 100% 6.77 100%
102A
Demi Water Tank -
1,188 16 7.5 76.2 76.20 76.20 22.20 100% 23.58 100% 24.46 100% 5.97 100%
103A
FIRE WATER TK-
3,000 21 10.5 150.3 150.29 150.29 37.29 100% 49.65 100% 49.51 100% 13.84 100%
001

TOTAL 501.14 501.14 501.14 129.40 175.99 160.42 35.33

TOTAL ERECTION
Capacit INNER TOTAL
HEIGH (TON) BOTTOM SHELL ROOF MISCELLANEOUS
TANK NO. y DIA (M
T (M)
WEIGHT
(M3) ) (TON ) PLAN ACTUAL Done % Done % Done % Done %
Industrial Raw
3,350 23 10.8 166.2 166.19 166.19 42.17 100% 60.27 100% 55.00 100% 8.75 100%
Water Tank - 101A
Process Water Tank -
2,000 18 10.0 108.5 108.47 108.39 27.74 100% 42.49 100% 31.46 100% 6.69 98.8%
102A
Demi Water Tank -
1,188 16 7.5 76.2 76.20 76.20 22.20 100% 23.58 100% 24.46 100% 5.97 100.0%
103A
FIRE WATER TK-
3,000 21 10.5 150.3 150.29 150.29 37.29 100% 49.65 100% 49.51 100% 13.84 100%
001

TOTAL 501.14 501.14 501.06 129.40 175.99 160.42 35.25

Page 26 of 234
Ducts Erection Status
As of Date: 11‐Feb‐2023

Activity Weight (Ton) Plan Qty. Actual Qty. Plan Actual

Erection 451.5 451.5 368.2 100.0% 81.5%


Pneumatic Conveyors 256.8 256.8 224.3 100.0% 87.3%
Dryer Duct 38.8 38.8 38.7 100.0% 99.9%
Crude Gas Duct 31.4 31.4 24.9 100.0% 79.35%
Energy Plant 65.7 65.7 48.1 100.0% 73.2%
Connecting Chutes 58.9 58.9 32.2 100.0% 54.7%

Page 27 of 234
Ducts Erection Status (Detailed)
As of Date: 11‐Feb‐2023

Activity Weight (Ton) R.W Start Date Finish Date Plan Actual

Erection Works 451.5 100% 6‐Apr‐2022 17‐May‐2023 100.0% 81.5%

Pneumatic Conveyors 256.8 56.9% 20‐Aug‐2022 17‐May‐2023 100.0% 87.3%

Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (1) ‐ Group 1242 &1243 7.4 2.9% 1‐Jan‐2023 5‐Jan‐2023 100.0% 97.0%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 1321 / 1331 / 1341 8.1 3.1% 20‐Aug‐2022 13‐Oct‐2022 100.0% 100.0%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 1531 3.8 1.5% 1‐Jan‐2023 22‐Jan‐2023 100.0% 100.0%

Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (3) ‐ Group 1282 &1283 7.5 2.9% 1‐Jan‐2023 4‐Jan‐2023 100.0% 97.0%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 2531 / 2532 / 2533 / 2534 15.8 6.2% 12‐Sep‐2022 8‐Oct‐2022 100.0% 100.0%

Erection ‐ Duct Works & exhaust Pipes ‐ Chipper Line (2) ‐ Group 1262 &1263 7.6 3.0% 1‐Jan‐2023 4‐Jan‐2023 100.0% 97.0%

Erection ‐ Duct Works & Pipes with bends and flanges ‐ Group 2615 / 2616 45.1 17.6% 1‐Jan‐2023 5‐Jan‐2023 100.0% 98.5%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 2770 / 2780 / 2782 / 2785 15.1 5.9% 1‐Jan‐2023 30‐Mar‐2023 100.0% 83.7%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 3905 8.4 3.3% 1‐Jan‐2023 19‐Jan‐2023 100.0% 47.6%

Erection ‐ Duct Work, Pipes & Hoods ‐ Group 4550 20.9 8.1% 30‐Mar‐2023 18‐Apr‐2023 100.0% 97.7%

Erection ‐ Duct Work & Pipes ‐ Group 4910 / 4920 / 4946 / 4970 / 4975 78.0 30.4% 1‐Jan‐2023 17‐May‐2023 100.0% 77.9%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 5910 / 5917 / 5920 37.5 14.6% 11‐Jan‐2023 12‐Mar‐2023 100.0% 84.6%

Erection ‐ Pipe ducts with bends and flanges ‐ Group 7112 / 7131 1.5 0.6% 4‐Mar‐2023 9‐Apr‐2023 100.0% 48.0%

Dryer Duct 38.8 8.6% 2‐Mar‐2023 12‐Mar‐2023 100.0% 99.9%

Erection ‐ Dryer Duct (From Dryer to High Efficiency Cyclone) ‐ Group 2420 38.8 100.0% 2‐Mar‐2023 12‐Mar‐2023 100.0% 99.9%

Crude Gas Duct 31.4 6.9% 10‐Apr‐2023 29‐Apr‐2023 100.0% 79.35%

Erection ‐ Crude gas duct ‐ Group 7410 31.4 100.0% 10‐Apr‐2023 29‐Apr‐2023 100.0% 79.3%

Energy Plant 65.7 14.5% 6‐Apr‐2022 20‐Apr‐2023 100.0% 73.2%

Erection ‐ Duct work from combustion air fan to the burner ‐ Group 7370.061 2.2 3.3% 28‐Mar‐2023 30‐Mar‐2023 100.0% 81.0%

Erection ‐ Duct work from cooling air fan to the burner ‐ Group 7370.062 1.3 1.9% 11‐Apr‐2023 15‐Apr‐2023 100.0%

Fab.‐ Air Grader (new scope) 9.9 15.0% 15‐Apr‐2023 20‐Apr‐2023 100.0% 65.0%

Erection ‐ Transport pipes ducts for dust ‐ Group 7370 1.8 2.8% 27‐Mar‐2023 30‐Mar‐2023 100.0%

Erection ‐ Duct work from ambient air fan to quench chamber ‐ Group 7385.060 0.3 0.4% 9‐Apr‐2023 10‐Apr‐2023 100.0% 100.0%

Erection ‐ Duct work from ambient air fan to mixing chamber ‐ Group 7385.065 0.8 1.3% 9‐Jan‐2023 9‐Jan‐2023 100.0% 50.0%

Erection ‐ Duct work from mixing chamber to cyclones ‐ Group 7385.065 0.8 1.3% 9‐Jan‐2023 9‐Jan‐2023 100.0% 50.0%

Erection ‐ Duct work from thermal oil heater to mixing chamber ‐ Group 7385.065 0.8 1.3% 11‐Feb‐2023 11‐Feb‐2023 100.0% 50.0%

Erection ‐ Duct work from dust collector (Cyclones) to Ash Crews ‐ Group 7385.080 10.5 15.9% 6‐Apr‐2022 14‐Apr‐2022 100.0% 100.0%

Erection ‐ Duct work from dust collector (Cyclones) to Main ID fan ‐ Group 7385.080 10.5 15.9% 28‐Mar‐2023 4‐Apr‐2023 100.0% 75.0%

Erection ‐ Duct work from the Main ID fan to Dryer Mixing Chamber ‐ Group 7385.090 5.7 8.6% 7‐Jan‐2023 10‐Jan‐2023 100.0% 95.0%

Erection ‐ Duct work from the main id fan to start up stack ‐ Group 7385.090 5.7 8.6% 9‐Jan‐2023 10‐Jan‐2023 100.0% 95.0%

Erection ‐ Duct work from thermal oil heater fan to mixing chamber ‐ Group 7390 7.7 11.8% 1‐Apr‐2023 9‐Apr‐2023 100.0% 60.0%

Erection ‐ Duct work from thermal oil heater to thermal oil heater fan ‐ Group 7390 7.7 11.8% 3‐Apr‐2023 11‐Apr‐2023 100.0% 60.0%

Chutes ‐ Supports ‐ Silencer ‐ Doors & loose items 58.9 13.1% 1‐Jan‐2023 30‐Apr‐2023 100.0% 54.7%

Fab.‐ Chutes, Doors & loose items ‐ Group 2300 36.3 61.6% 1‐Jan‐2023 30‐Apr‐2023 100.0% 42.4%

Fab.‐ Pneumatic Supports ‐ Group 2600 16.9 28.6% 1‐Jan‐2023 30‐Apr‐2023 100.0% 100.0%

Fab.‐ Silencer ‐ Group 4200 5.8 9.8% 15‐Apr‐2023 20‐Apr‐2023 100.0%

Page 28 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

 Pre-Commissioning & Commissioning Status

Test Package
Approved Sub-
System
P&ID’s Systems
Total Done Remain

Electrical 15 15 108 -

17 83 334 67 277
Process 34
0 of 17 53 N/A

Miscellaneous
(Civil/ Road / 6 6 39 -
Steel

Total 55 38 283 334 67 277


(20%)

Page 29 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

7. Weekly man-hours summary

Pervious This Week Total


Man-hours
4,271,545 58,440 4,329,985

7.1 Detailed Manpower & Man-hours for This Week: -

Man-hours
Manpower Av. No.
This WK.
Indirect Manpower:
Project MGR. 1 60
Construction MGR. 4 240
Project Control & planning MGR. 1 60
Maintenance MGR. 1 60
Technical Office Manager 1 60
Civil Technical office Engineer 3 180
Mechanical Technical office Engineer 5 300
E&I Technical office Engineer 3 180
Civil Construction Engineer 5 300
Mechanical Construction Engineer 14 840
E&I Construction Engineer 12 720
HSE Engineer & Specialist 5 300
Planning Engineer 3 180
DCC 2 120
Material Control Engineer 2 120
QC / QA Manager (Civil) 1 60
QC / QA Manager (Mechanical) 1 60
Mechanical QC Engineer 6 360
Civil QC Engineer 4 240
E&I QC Engineer 2 120
Painting Engineer 2 120
Hydrotest Engineer 1 60
Pre-commissioning & Commissioning Engineer 8 480
NDT Technician 10 600
Material Control Technician 3 180
Hydrotest Technician 17 1,020
Civil NDT Technician 4 240

Page 30 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Surveyor 11 660
Nurse 2 120
Administrator 3 180
HR 5 300
Warehouse man 1 60
HSE Officer 26 1,560
Doctor 1 60
Security 24 1,440
Unskilled Labor 70 4,200
Direct Manpower:
Civil Forman 10 600
Fitter Forman 11 660
Welder Forman 2 120
E&I Forman 9 540
Rigger Forman 2 120
Scaffolding Forman 2 120
Carpenter 16 960
Steel Fixer 11 660
Plumber 11 660
Plasterer 7 420
Concrete Shaper 13 780
Steel Fitter 33 1,980
Rotating Equip. Fitter 12 720
Piping Fitter 17 1,020
Steel Welder 26 1,560
Argon Welder 13 780
Grinder 94 5,640
Rigger 135 8,100
Sandblaster & Painter 12 720
Scaffolding Labor 60 3,600
E&I Steel Fitter 11 660
Electrical Technician 34 2,040
Electrician Helper 36 2,160
Maintenance Labors & Drivers 96 5,760
Crane Operator 27 1,620
TCF Crew 10 600

Total 974 58,440

Page 31 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

7.2 Equipment: -
Equipment NO.
Crane 500 ton 1
Crane 100 ton 1
Crane 90 ton 1
Crane 70 ton 3
Crane 50 ton 13
Crane 35 ton 1
Forklift 7
Boom Man lift 22
Excavator 2
Tractor 2
Compactor 2
Grader 1
Loader 4
Dump Truck 5
Bobcat 2
Air Compressor 3
Generator 9
Lighting Unit 12
Welding Machine (Set) 54
Water Mobile Tank 5
Diesel truck 4
Dewatering Pump 14
Trailer 4

Page 32 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

8. Areas of concern
8.1 Shipments of the Production line Equipment have been arrived of (31)
[ Siemmpelkamp Scope of work], remain the spare parts & commissioning
shipments.
8.2 Level-2 & 3 Revised Schedule (Rev.6) has been submitted for WOTECH
approval 11/02/2023.
8.3 The price increasing for the material supply of the suppliers is still under
negotiating with WOTECH.
8.4 The issuing of the letter of credit (LC) has a negative impact on the external
purchasing (imported material) and hence the project schedule such as :
 Emergency Diesel Generator (PO # 148), alternative PO for PICO vendor is
under issuing.
 Instrument J.B (PO # 45).
 Remaining Rails – 45 Ton (PO # 6444).
 Portable Monitors (PO # 513).

Page 33 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

9. List of correspondence requiring response


9.1 By Petrojet
 None
9.2 By WOTECH
 None

Page 34 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

10. Photos

Page 35 of 234
Page 36 of 234
MDF Production Line

Page 37 of 234
Mat-former Area
Page 38 of 234 (Plot 1)
Mat-former Bunker (Plot 1)
Page 39 of 234
Pre-Press Area (Plot 1)
Page 40 of 234
Press & Page
ContiRoll
41 of 234 (Plot 1)
Out Feed Drum for Press & Page
Press Fumes Pipes G.4550 (Plot 1)
42 of 234
Cooling Turner Area (Plot 1)
Page 43 of 234
Sanding & Cutting
Page 44 of Lines
234 G.5400 (Plot 1)
Sanding & Cutting Lines G.5400 (Plot 1)
Page 45 of 234
Sanding Machines (Plot 1)
Page 46 of 234
Extraction System forPageSanding
47 of 234 Machines (Plot 1)
Packing Line G.5700 (Plot 1)

Page 48 of 234
Stacking Area & Rails Installation
Page 49 of 234for Carriage System (Plot 1)
Final Separator

Sedimentation Tank
Fume Extraction Fan

Press Fume Extraction System G.4550 (Plot 1)


Page 50 of 234
Extraction Systems & Filters (Plot 2)
Page 51 of 234
Sifting & Dryer
Page 52Towers
of 234 (Plot 2)
Sifting & Dryer Area (Plot 2)
Page 53 of 234
WESP & Sifter Page
Area G.2061 (Plot 2)
54 of 234
Energy
PagePlant
55 of 234 (Plot 3)
Thermal Fluid System Dust Dosing (Plot 3)
Page 56 of 234
Combustion ChamberPage&57 Pulverizer
of 234
Area (Plot 3)
Refiner & Storage Bin Area (Plot 4)
Page 58 of 234
Refiner Installation
Page 59 of 234 (Plot 4)
Page 60 of 234

Round Filters for Extraction Systems (Plot 4)


Straw Milling
Page& Screening
61 of 234 (Plot 5)
Straw Milling
Page& Screening
62 of 234 (Plot 5)
Straw Preparation (Plot 6)

Page 63 of 234
Straw De-stringing Page
& Chopping
64 of 234 Lines (Plot 6)
Overhead Crane Installation (Plot 6)
Page 65 of 234
Dryer Fan & Mixing
Page 66 of Chamber
234 (Plot 7)
Thermal Oil System &PageSteam
67 of 234 Generation (Plot 7)
Thermal Oil Pump room (Plot 7)
Page 68 of 234
PMDI Tanks & Warehouse
Page 69 of 234
Str. (Plots 4 & 7 )
Industrial Tanks Area & Pump Shed (OSBL)
Page 70 of 234
Fire Water Page
Tank Area (OSBL)
71 of 234
Cable Trays
Page 72 installation
of 234
Page 73 of 234
Cable Trays installation
Panels & Switch Gears installation
Page 74 of 234
HSE Building & Truck Shed (OSBL)
Page 75 of 234
MDF Main Gate
Page 76 of 234
MDF Mosque Finishing Works
Page 77 of 234
Chemical Pit Concrete
Page 78 of 234 Works (Plot 2)
Car Parking Shed & TCF Building (OSBL)
Page 79 of 234
Water Treatment Shed (OSBL)
Page 80 of 234
Compressors
Page 81 Shed
of 234 (OSBL)
Trench's Covers Installation Page 82 of 234
Interlock Works for Roads
HDPE Piping Installation
Page 83 of 234
HDPE Piping Installation
Page 84 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Attachment #1
Skyline

Page 85 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 08-04-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21
: ‫ﺍﻟﻜﺮﺑﻮﻥ ﺇﺳﺘﻴﻞ‬
‫ ﺇﺳﺒﻮﻉ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬6
29-03-22 : ‫ﺍﻟﺠﻠﻔﺎﻧﻴﺰ‬
28-06-22 84/YAK/2022 ‫ﺑﺪﺭ ﻟﻠﺨﺪﻣﺎﺕ ﺍﻟﺼﻨﺎﻋﻴﺔ‬
Pipes, Fitting, Flanges, ‫ ﺷﻬﺮ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬3 : 2 ‫ﻣﻦ‬
1 Piping 145/YAK/2021 Local PO Plan
Gasket, Bolts (CS )
13-02-22 (CS): (4 : 6) Wk. from PO (CS) From 13/3 to 27/3 85/YAK/2022 ‫ﺗﻜﻨﻮﺟﺮﻭﺏ‬

20-06-22 (2 : 4) Wk. from PO 13-03-22 440/YAK/2022 ‫ﻣﻴﺠﺎ ﻟﻠﺘﺠﺎﺭﺓ‬

Act 28-04-21 21-11-21 13-01-22 13-02-22 Arrived @ Site


Plan 09-11-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21
* Pipingٍ Balance ‫ﺍﻟﻮﻁﻨﻴﺔ ﻟﻠﺨﺪﻣﺎﺕ‬
2 Piping 279/NGE-2022 Local PO Plan (2 : 4) Wks from PO 19-05-22 257/NGE/2022
(CS ) ‫ﺍﻟﺼﻨﺎﻋﻴﺔ‬
Act 31-03-22 11-04-22 18-04-22 19-04-22 Arrived @ Site
Plan 09-11-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21 Gerab National
* Piping Super Duplex
3 Piping 173/MST/2022 External PO Plan (6 : 8) Wks FOB from 16/3/22 25-05-22 128/173-22/MST/2022 Interprises
(bulk materials )
Act 02-02-22 13-03-22 15-03-22 16-03-22 Arrived @ Site L.L.C
Plan 09-11-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21 Gerab National
* Piping Super Duplex
4 Piping 333/MST/2022 External PO Plan (10 : 12) Wks FOB from PO 07-09-22 262/333-22/MST/2022 Interprises
(Balance )
Act 10-05-22 17-05-22 24-05-22 30-05-22 Arrived @ Site L.L.C
Plan 09-11-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21
* Pipingٍ Stainless Steel
5 Piping 175/NGE/2022 Local PO Plan 27-03-22 (2 : 4) Wks from PO 24-04-22 205/NGE/2022 ‫ﻣﻴﺠﺎ ﻟﻠﺘﺠﺎﺭﺓ‬
(bulk materials )
Act 21-02-22 16-03-22 23-03-22 27-03-22 Arrived @ Site
Pipes, Fitting, Flanges, Plan 22-03-21 22-09-21 06-10-21 01-11-21 (12) Weeks FOB 14 07-02-22
6 Gasket, Bolts (DIN Piping 395/AHN/2021 External PO Plan (12) Weeks FOB 14-02-22 478/AHN/2021 MSA
Standard) Act 22-03-21 22-09-21 06-10-21 01-11-21 Arrived @ Site
Plan 09-11-21 16-11-21 23-11-21 30-11-21 (4) Weeks 4 28-12-21
STEEL
7 * Piping Bulk (DIN Balance) Piping 65/AHN/2022 External PO Plan (6) Wks FOB from PO 08-05-22 130/65-22/AHN/2022
TRADE SRL
Act 02-02-22 09-03-22 13-03-22 21-03-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
‫ ﻣﻦ‬FOB ‫( ﺃﺳﺒﻮﻉ‬9) : ‫ﺍﻟﺸﺤﻨﺔ ﺍﻷﻭﻟﻰ‬
*Special Connections / ‫ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬
8 Piping 248/MOA/2022 External PO Plan 22-09-22 279/248-22/MOA/2022 LISEGA SA
Supports ‫ ﻣﻦ‬FOB ‫( ﺇﺳﺒﻮﻉ‬13) : ‫ﺍﻟﺸﺤﻨﺔ ﺍﻟﺜﺎﻧﻴﺔ‬
‫ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬

Act 17-04-21 19-04-21 25-05-22 01-06-22 Arrived @ Site


Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
Pipes, Fitting, Flanges, ‫ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ‬
9 Piping 158/YAK/2021 Local PO Plan (1.5) month from PO 20-06-22 106/YAK/2022
Gasket, Bolts (HDPE) ‫ﺍﻟﻤﻮﺍﺳﻴﺮ‬
Act 28-04-21 01-02-22 13-02-22 22-02-22 Arrived @ Site

Pipes, Fitting, Flanges, Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
‫ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ‬
10 Gasket, Bolts (HDPE) - Piping 510/NGE/2022 Local PO Plan Stock 26-06-22 397/NGE/2022
‫ﺍﻟﻤﻮﺍﺳﻴﺮ‬
Balance
Act 06-06-22 Page 13-06-22
09-06-22 86 of 234 19-06-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
Pipes Fitting Flanges
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Pipes, Fitting, Flanges,
PO Plan (2) month from PO 23-12-22 397/NGE/2022 ‫ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ‬
11 Gasket, Bolts (HDPE) - Piping 510/NGE/2022 Local
‫ﺗﻌﻠﻴﺔ‬ ‫ﺍﻟﻤﻮﺍﺳﻴﺮ‬
Balance ETA (Expected to arrive) 01-02-23
Act 02-10-22 09-10-22 16-10-22 23-10-22 Partial Delivery (97%)

Pipes, Fitting, Flanges, Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
‫ﺍﻟﺒﺤﺮ ﺍﻷﺣﻤﺮ ﻟﺼﻨﺎﻋﺔ‬
12 Gasket, Bolts (HDPE) - Piping 956/NGE/2022 Local PO Plan (2) month from PO 23-12-22 816/NGE/2022
‫ﺍﻟﻤﻮﺍﺳﻴﺮ‬
Balance
Act 02-10-22 09-10-22 16-10-22 23-10-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
*Piping Bulk Material (CS) - ‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺇﺻﺪﺍﺭ‬8 : 4) ‫ﻣﻦ‬
13 Piping 436/NGE/2022 Local PO Plan 07-07-22 11-09-22 527/NGE/2022 ‫ﻣﻴﺠﺎ ﻟﻠﺘﺠﺎﺭﺓ‬
Balance ‫ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬
ETA (Expected to arrive) 15-01-23
Act 15-05-22 22-05-22 27-06-22 07-07-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
*Piping Bulk Material (CS) - 441- CHERO PIPING
14 Piping Local PO Plan ‫ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬FOB ‫ ( ﺇﺳﺒﻮﻉ‬6) 07-09-22 334/411-22/AHN/2022
Balance 22/AHN/2022 S.P.A
Act 15-05-22 22-05-22 21-06-22 28-06-22 Arrived @ Site
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
552- ‫ ﻣﻦ ﺃﻣﺮ‬FOB ‫( ﺇﺳﺒﻮﻉ‬16) : (7) ‫ﻣﻦ‬ 2022 / 12 / 1 ‫ﻣﻦ‬ CHERO PIPING
15 *Piping Bulk Material Piping External PO Plan 492/552-22/AHN/2022
22/AHN/2022 ‫( ﺇﺳﺒﻮﻉ ﺃﺟﺎﺯﺓ ﻛﺮﻳﺴﻤﺎﺱ‬2) + ‫ﺍﻟﺘﻮﺭﻳﺪ‬ 2023 / 2 / 15 ‫ﺇﻟﻰ‬ S.P.A

Act 15-09-22 17-09-22 19-09-22 21-09-22 Arrived @ Site


Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22

555-
External PO Plan 21-11-22
‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﻓﺘﺢ ﺍﻹﻋﺘﻤﺎﺩ ﺍﻟﻤﺴﺘﻨﺪﻯ‬4)
16 *Piping Bulk Material Piping 493/555-22/AHN/2022 Gates FZE
22/AHN/2022
ETA (Expected to arrive) 07-03-23
Act 15-09-22 17-09-22 19-09-22 21-09-22 Partial Delivery (8%)

Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22


/ ‫ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻡ ﺍﻟﺘﻮﺭﻳﺪ‬FOB ‫( ﺇﺳﺒﻮﻉ‬3)
687-
17 *Piping Bulk Material Piping External PO Plan LC ‫ ﻓﺘﺢ‬/ ‫ﺇﻋﺘﻤﺎﺩ ﺍﻟﻠﻮﺣﺎﺕ‬
18-01-23 582-687-22/AHN/2022 Gates FZE
22/AHN/2022
ETA (Expected to arrive) 07-03-22
Act 13-11-22 20-11-22 22-11-22 24-11-22
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22
‫ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻡ‬FOB ‫( ﺇﺳﺒﻮﻉ‬4 : 2)
44-
18 *Piping Bulk Material Piping External PO Plan LC ‫ ﻓﺘﺢ‬/ ‫ ﺇﻋﺘﻤﺎﺩ ﺍﻟﻠﻮﺣﺎﺕ‬/ ‫ﺍﻟﺘﻮﺭﻳﺪ‬
05-04-23 34/44-22/AHN/2023 Gates FZE
22/AHN/2023
ETA (Expected to arrive) 07-03-22
Act 08-01-23 15-01-23 17-01-23 19-01-23
Plan 08-04-21 02-12-21 09-12-21 16-12-21 (4) Weeks 4 13-01-22

80-
External PO Plan 05-04-23
Page 87 of 234 Delivery Along With PO 34
19 *Piping Bulk Material Piping 77/80-23/AHN/2023 Gates FZE
23/AHN/2023
ETA (Expected to arrive) 07-03-22
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Act 01-02-23 08-02-23 10-02-23 12-02-23
Plan 22-03-21 17-10-21 24-11-21 08-12-21 (17) Weeks FOB 19 20-04-22
(14 ) Wks FOB from PO &
DWG. App.
19-05-22 556/152-21/ABH/2021 FABRICAZIONE
(17 ) Wks FOB from DWG. VECTOR &
Approval
05-07-22 557/152-21/ABH/2021
WELLHEADS
20 Manual Valves Piping 152/ِABO/2021 External PO Plan (16 ) Wks FOB from PO &
DWG. App. (PO issued 7/2/22)
20-06-22 35/152-21/ABH/2021 MSA, A.S
(16 ) Wks FOB from PO, DWG.
App.
21-04-22 559/152-21/ABH/2021 MSA, A.S
Act 22-03-21 17-10-21 24-11-21 09-12-21 Arrived @ Site
Plan 10-10-21 17-10-21 24-11-21 08-12-21 (17) Weeks FOB 19 20-04-22
(9) Wks FOB from DWG.
* Manual Valves (Gate, Approval
12 08-06-22 118/83-22/ABH/2022 ITALBEST
21 Piping 83/ABO/2022 External PO Plan
Check & Globe) (16) Wks FOB from PO 19 27-07-22 119/83-22/ABH/2022 VECTOR
Act 06-02-22 01-03-22 14-03-22 16-03-22 Arrived @ Site
Plan 25-11-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
442- ‫ ﻣﻦ ﻓﺘﺢ ﺍﻹﻋﺘﻤﺎﺩ‬FOB ‫( ﺍﺳﺒﻮﻉ‬2)
22 * Manual Valves Piping External PO Plan 26-10-22 428/442-22/HND/2022 Gates FZE
22/HND/2022 ‫ﺍﻟﻤﺴﺘﻨﺪﻯ‬
Act 24-07-22 31-07-22 07-08-22 14-08-22 Arrived @ Site
Plan 25-11-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
* Manual Valves (Gate & 444-
23 Piping External PO Plan ‫ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬FOB ‫( ﺍﺳﺒﻮﻉ‬14) 07-12-22 394/444-22/ABH/2022 VECTOR
Check) 22/ABH/2022
Act 04-07-22 11-07-22 18-07-22 25-07-22 Arrived @ Site
Plan 25-11-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
443- ‫ ﻣﻦ ﻓﺘﺢ ﺍﻹﻋﺘﻤﺎﺩ‬FOB ‫( ﺍﺳﺎﺑﻴﻊ‬6 : 5) ‫ﻣﻦ‬
24 * Manual Valves (Ball) Piping External PO Plan 10-11-22 389/443-22/AHN/2022 ITALBEST
22/AHN/2022 ‫ﺍﻟﻤﺴﺘﻨﺪﻯ‬
Act 04-07-22 11-07-22 18-07-22 25-07-22 Arrived @ Site
Plan 25-11-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
SAMSON
25 * On / Off Valve Piping 217-22/PET/2022 External PO Plan (16 ) Wks FOB from PO 15-07-22 179/217-22/PET/2022
Controls FZE
Act 03-02-22 09-03-22 14-03-22 09-04-22 Arrived @ Site
Plan 25-11-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
‫ﺍﻻﻧﺪﻟﺲ ﻟﻠﺘﺠﺎﺭﺓ‬
26 * Potable Water Valves Piping 441/NGE/2022 Local PO Plan 23-05-22 (2 ) Wks from PO 2 06-06-22 323/NGE/2022
‫ﻭﺍﻟﻤﻘﺎﻭﻻﺕ‬
Act 02-05-22 09-05-22 16-05-22 23-05-22 Arrived @ Site
Plan 31-03-21 07-07-21 27-07-21 22-09-21 (1) Month 22-10-21
(22:24) Weeks FOB from PO & SICOM ITALIA
27 Strainer Piping 169/ABH/2021 External PO Plan 13-04-22 353 /169-21/ABH/2021
DWG. App. S.R.L
Act 31-03-21 07-07-21 27-07-21 22-09-21 Arrived @ Site
Plan 30-09-21 11-11-21 18-11-21 25-11-21 (7) Weeks FOB 9 27-01-22
(7) Weeks FOB from DWG. ARI - Armaturen
28 Steam Traps Piping 562/NAA/2021 External PO Plan 12 12-04-22 23/562-21/NAA/2022
App. Middle East FZE
Act 30-09-21 11-11-21 10-01-22 18-01-22 Arrived @ Site
Plan 07-12-21 07-01-22 14-01-22 21-01-22 (4) Weeks 4 18-02-22
Page 88 of 234
29 Bolts Piping 936/ALY/2022 Local PO Plan (1 : 2) Weeks from PO 09-11-22 867/ALY/2022 ‫ﺍﻟﻤﺼﺮﻳﺔ ﺍﻷﻭﺭﺑﻴﺔ‬
Act 05-10-22 12-10-22 19-10-22 26-10-22 Arrived @ Site
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 07-12-21 07-01-22 14-01-22 21-01-22 (4) Weeks 4 18-02-22
30 Unions Piping 868/ALY/2022 Local PO Plan (4) Days from PO 30-10-22 940/ALY/2022 ‫ﺍﻟﻤﺼﺮﻳﺔ ﺍﻷﻭﺭﺑﻴﺔ‬
Act 05-10-22 12-10-22 19-10-22 26-10-22 Arrived @ Site
Plan 07-12-21 07-01-22 14-01-22 21-01-22 (10) Weeks FOB 12 15-04-22
PO Plan (8 : 18) Weeks from PO 15-11-22
31 F&G Bulk materials FG 266/NGE/2022 Local 1088/NGE/2022 ‫ﺗﺮﺍﻳﻜﻮﻡ ﻻﻧﻈﻤﺔ ﺍﻟﺘﺤﻜﻢ‬
ETA (Expected to arrive) 14-02-23
Act 29-03-22 11-04-22 20-04-22 28-04-22 RFS
Plan 07-12-21 07-01-22 14-01-22 21-01-22 (10) Weeks FOB 12 15-04-22
PO Plan (8 : 18) Weeks from PO 15-11-22
32 F&G (Balance) FG 1108/ALY/2022 Local 2038/ALY/2022 ‫ﺗﺮﺍﻳﻜﻮﻡ ﻻﻧﻈﻤﺔ ﺍﻟﺘﺤﻜﻢ‬
ETA (Expected to arrive) 14-02-23
Act 21-11-22 28-11-22 05-12-22 12-12-22 RFS
Plan 05-04-21 01-12-21 08-12-21 15-12-21 (20) Weeks 20 04-05-22 ‫ﺍﻟﻤﺼﺮﻳﺔ ﺍﻷﻟﻤﺎﻧﻴﺔ‬
33 Fire Pumps Fire-Fighting 142/YAK/2021 Local PO Plan 20-03-22 (17:18) Wks. from Adv. Pay. 25-07-22 151/YAK/2022 ‫ﻟﻠﻤﻀﺨﺎﺕ )ﺭﻭﻫﺮ‬
Act 21-04-21 08-02-22 10-03-22 20-03-22 Arrived @ Site (‫ﺑﺎﻣﺐ‬

Plan 28-07-21 24-12-21 31-12-21 07-01-22 (10) Weeks FOB 12 01-04-22


Water Spray System (Fire 465/BRK/2021 LECHLER
34 Fire-Fighting External PO Plan EX-Stock - (1) Wk. FOB from
20-04-22
42/465-21/BRK/2022
Fighting Nozzles) PO GMBH
Act 28-07-21 01-12-21 20-12-21 23-03-22 Arrived @ Site
Plan 28-07-21 24-12-21 31-12-21 07-01-22 (10) Weeks FOB 12 01-04-22
Water Spray System (Fire FAGUS -
35 Fire-Fighting 466/BRK/2021 External PO Plan (12) Weeks FOB From PO 25-05-22 43/466-21/BRK/2022
Fighting Nozzles) GRECON
Act 28-07-21 01-12-21 20-12-21 09-02-22 Arrived @ Site
Plan 01-04-21 01-01-22 08-01-22 15-01-22 (16) Weeks 16 07-05-22
(4) months from Adv. Pay. &
22-03-22 Site Clear
19-08-22 1044/YAK/2022 ‫ﺩﻭﺝ ﻻﻧﺪ ﺗﻜﻨﻮﻟﻮﺟﻰ‬
PO Plan
(1:4) months from Adv. Pay. &
36 Fire Fighting Equipment Fire-Fighting 147/YAK/2021 Local 22-03-22 Site Clear & DWG. App.
From 4/5/22 to 2/8/22 1043/YAK/2022 ‫ﺍﻟﻌﺎﻟﻤﻴﺔ ﻟﻸﻧﻈﻤﺔ ﺍﻟﻤﺘﻜﺎﻣﻠﺔ‬

ETA (Expected to arrive) 15-03-23


Act 21-04-21 08-02-22 10-03-22 22-03-22 Partial Delivery (60%)
Plan 01-04-21 01-01-22 08-01-22 15-01-22 (16) Weeks 16 07-05-22
37 Steel Str for Sprinklers Fire-Fighting 61/ALY/2023 Local (2) Months From PO & Adv. ‫ﺩﻭﺝ ﻻﻧﺪ ﺗﻜﻨﻮﻟﻮﺟﻰ‬
PO Plan Pay.
23-03-23
Act 01-01-23 08-01-23 15-01-23 22-01-23 Partial Delivery (8%)

Page 89 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 01-12-21 01-01-22 08-01-22 15-01-22 (16) Weeks 16 07-05-22
(10 WKs from PO) For items 3,
‫ﻧﻮﻓﻴﻚ ﻟﻠﻬﻨﺪﺳﺔ‬
07-07-22 4 , 12, 24, 25 & 26 15-09-22 522/NGE/2022
PO Plan (EX-Stock for other items) ‫ﻭﺍﻟﻤﻘﺎﻭﻻﺕ‬
38 * Firefighting Manual Valves Fire-Fighting 587/NGE/2022 Local
07-07-22 EX-Stock 20-07-22 523/NGE/2022 ‫ﻣﻴﻨﺘﺎ‬
ETA (Expected to arrive) 01-02-23
Act 03-07-22 05-07-22 06-07-22 07-07-22 Partial Delivery (80%)
Plan 01-12-21 01-01-22 08-01-22 15-01-22 (16) Weeks 16 07-05-22
‫ ﺃﺷﻬﺮ ﻣﻦ ﺃﻣﺮ‬6 ‫( ﻣﺪﺓ‬8) ‫ ﻋﺪﺩ‬: (1) ‫ﺍﻟﺒﻨﺪ‬
PO Plan 04-07-22 ‫ﺍﻟﺘﻮﺭﻳﺪ‬ 01-01-23
39 * Portable monitors (12 ea.) Fire-Fighting 589/NGE/2022 Local ‫( ﺑﻀﺎﻋﺔ ﺣﺎﺿﺮﺓ‬4) ‫ﻋﺪﺩ‬: (2) ‫ﺍﻟﺒﻨﺪ‬ 513/NGE/2022 ‫ﺳﻴﻔﺘﻰ ﻣﺼﺮ ﻟﻠﺘﺠﺎﺭﺓ‬
ETA (Expected to arrive) 01-07-23
Act 03-07-22 04-07-22 04-07-22 04-07-22 Partial Delivery (35%)
Plan 10-06-21 25-10-21 10-12-21 17-12-21 (8) Weeks 8 11-02-22
‫ﺍﻟﻜﺘﺮﻭﺑﺎﻟﻚ ﻟﻠﻬﻨﺪﺳﺔ‬
21-03-22 (12) Wk. from PO & DWG. App. 14-06-22 470/YAK/2021 ‫ﻭﺍﻟﺘﻮﺭﻳﺪﺍﺕ ﺍﺑﻴﺴﻜﻮ‬
40 Lighting Poles Electric 298/YAK/2021 Local PO Plan
‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ ﻟﻠﺘﻮﺭﻳﺪﺍﺕ‬
08-12-21 (11) Wk. from DWG. App. 09-03-22 471/YAK/2021 ‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 17-06-21 25-10-21 07-12-21 08-12-21 Arrived @ Site
Plan 10-06-21 31-08-21 15-11-21 10-12-21 (8) Weeks 8 04-02-22
‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ‬
41 Switches and Sockets Electric 309/YAK/2021 Local PO Plan (2 : 3 ) Wks. From PO 23-02-22 51/YAK/2022
‫ﻟﻠﺘﻮﺭﻳﺪﺍﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 10-06-21 31-08-21 15-11-21 03-02-22 Arrived @ Site
Plan 10-06-21 31-08-21 15-11-21 10-12-21 (8) Weeks 8 04-02-22
(‫ﺟﻤﻴﻊ ﺍﻟﺒﻨﻮﺩ )ﻣﺎﻋﺪﺍ ﺍﻟﻠﻮﺣﺎﺕ‬
‫( ﺷﻬﺮ ﻣﻦ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬2) : (1) ‫ﻣﻦ‬
*Switches and Sockets - ‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ‬
42 Electric 653/NGE/2022 Local PO Plan :‫ﺍﻟﻠﻮﺣﺎﺕ‬ 15-10-22 607/NGE/2022
Balance ‫( ﺷﻬﺮ ﻣﻦ ﺇﻋﺘﻤﺎﺩ ﺍﻟﺮﺳﻮﻣﺎﺕ‬2):(1) ‫ﻣﻦ‬ ‫ﻟﻠﺘﻮﺭﻳﺪﺍﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
(PO ‫ ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻟـ‬2 ) ‫ﺍﻟﺘﻰ ﺗﺤﺘﺎﺝ‬

Act 31-07-22 31-07-22 31-07-22 01-08-22 Arrived @ Site


Plan 29-06-21 28-10-21 26-12-21 02-01-22 (8) Weeks 8 27-02-22
‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﻺﺿﺎءﺓ‬
02-02-22 (2) Wks. from PO 16-02-22 507/AHH/2021
‫ﻭﺍﻟﻜﺎﺑﻼﺕ‬
‫ﻣﺎﺗﺮﻳﻜﺲ ﻟﻠﻬﻨﺪﺳﺔ‬
21-02-22 (12 : 16) Wks from Adv. Pay. 14-06-22 508/AHH/2021
Lighting Fixtures (Explosion PO Plan ‫ﻭﺍﻟﺘﺠﺎﺭﺓ‬
43 Electric 349/AHH/2021 Local (3:4) Months from PO & Adv. ‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﻼﺩﻭﺍﺕ‬
Proof) 21-02-22 Pay.
15-06-22 509/AHH/2021 ‫ﻭﺍﻟﻜﺎﺑﻼﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
21-02-22 (14 : 16) Wks from PO 25-05-22 510/AHH/2021 ‫ﺍﻹﻧﺎﺭﺓ ﺍﻟﻌﺎﻣﺔ‬
ETA (Expected to arrive) 01-03-23
Act 29-06-21 28-10-21 26-12-21 02-02-22 Partial Delivery (75%)
Plan 28-01-21 04-03-21 11-03-21 16-03-21 (1) Month 15-04-21 ‫ﺍﻟﻤﺼﺮﻳﺔ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
Earthing Batch-1 Production
44 Electric 306/YAK/2020 Local 03-06-21 (2) Months Arrived @ Site 61/MTF/2021 -‫ﺍﻟﻤﺘﻄﻮﺭﺓ )ﺍﻟﺴﻮﻳﺪﻯ‬
Line & Area Act 12-11-20 26-01-21 13-04-21 (‫ﺳﻴﺪﻛﻮ‬
07-07-21 (3) Months Arrived @ Site 165/YAK/2021
Page 90 of 234
Plan 31-03-21 05-05-21 12-05-21 26-07-21 (3) Months 26-10-21 ‫ﺍﻟﻤﺼﺮﻳﺔ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
Earthing Batch-2 Rest Of
45 Electric 285/YAK/2021 Local PO Plan 26-07-22 174/YAK/2021 -‫ﺍﻟﻤﺘﻄﻮﺭﺓ )ﺍﻟﺴﻮﻳﺪﻯ‬
Plant ( ‫ﻛ‬
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plant (‫ﺳﻴﺪﻛﻮ‬
Act 06-06-21 16-06-21 26-06-21 26-07-21 Arrived @ Site

Page 91 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 31-03-21 05-05-21 12-05-21 26-07-21 (10:12) Weeks 12 18-10-21
‫ﺍﻭﺗﺎﻙ ﻟﻠﺘﺠﺎﺭﺓ ﻭ‬
46 Lightning protection system Electric 12/YAK/2021 Local PO Plan 26-07-22 151/YAK/2021
‫ﺍﻟﻤﻘﺎﻭﻻﺕ‬
Act 06-01-21 28-03-21 05-05-21 26-07-21 Arrived @ Site
Plan 08-12-20 09-05-21 27-06-21 11-11-21 (3) Months 13 08-02-22 ‫ﺍﻟﺸﺮﻛﺔ ﺍﻟﻤﺼﺮﻳﺔ‬
(3) Months from Adv. Pay. & ‫ﻟﻠﺼﻨﺎﻋﺔ ﻭ ﺍﻟﻨﻈﻢ‬
47 MV Switchgear Electric 347/HHA/2020 Local PO Plan 13-02-22 304/HHA/2021
DWG's App. ‫ﺍﻟﻤﺘﻘﺪﻣﺔ‬
Act 27-12-20 10-05-21 03-10-21 11-11-21 Arrived @ Site ‫ﺍﻟﺴﻮﻳﺪﻯ‬-(‫)ﺍﻳﻤﺎﺱ‬
Plan 08-12-20 09-05-21 27-06-21 11-11-21 (3) Months 13 08-02-22
(3) Months from Adv. Pay. & ‫ﺍﻟﺸﺮﻛﺔ ﺍﻟﻤﺼﺮﻳﺔ‬
*MV Switchgear (Software PO Plan DWG's App.
13-11-22 ‫ﻟﻠﺼﻨﺎﻋﺔ ﻭ ﺍﻟﻨﻈﻢ‬
48 Electric 528/NGE/2022 Local 399/NGE/2022
Licenses) ‫ﺍﻟﻤﺘﻘﺪﻣﺔ‬
ETA (Expected to arrive) 01-03-23 ‫ﺍﻟﺴﻮﻳﺪﻯ‬-(‫)ﺍﻳﻤﺎﺱ‬
Act 12-06-22 19-06-22 26-06-22 27-07-22
Plan 31-12-20 10-06-21 20-09-21 01-11-21 (3) Months 13 01-02-22
‫ﺍﻳﻪ ﺑﻰ ﺑﻰ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
49 LV Switchgear Bus Duct Electric 10/YAK/2021 Local PO Plan ‫( ﺃﺷﻬﺮ ﻣﻦ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬5) : (4) ‫ﻣﻦ‬ 06-02-22 407/YAK/2021
‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 14-01-21 10-06-21 17-10-21 07-11-21 Arrived @ Site
Plan 31-12-20 10-06-21 20-09-21 01-11-21 (3) Months 13 01-02-22
*LV Switchgear Bus Duct (2:4) Months from Adv. Pay. & ‫ﺍﻳﻪ ﺑﻰ ﺑﻰ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
50 Electric 209/NGE/2022 Local PO Plan 17 19-08-22 271/NGE/2022
(Utility) DWG's App. (3 days from PO) ‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬

Act 10-03-22 10-04-22 17-04-22 20-04-22 Arrived @ Site


Plan 13-02-21 20-03-21 27-03-21 26-07-21 (3) Months 26-10-21
‫ﺍﻟﻨﺼﺮ ﻟﺼﻨﺎﻋﺔ‬
PO Plan (3) Months from P.O & Adv. Pay 25-10-22
51 Transformers Electric 308/YAK/2020 Local 175/YAK/2021 ‫ﺍﻟﻤﺤﻮﻻﺕ ﻭﺍﻟﻤﻨﺘﺠﺎﺕ‬
ETA (Expected to arrive) 15-01-23 (‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ )ﺍﻟﻤﺎﻛﻮ‬
Act 02-12-20 10-03-21 08-06-22 26-07-21 Arrived @ Site
Plan 15-04-21 20-05-21 27-05-21 26-07-21 (5:6) Months 26-01-22
(5:6) Months from DWG's
PO Plan approval + (4) WKs. Vacations
23-01-22 ‫ﺯﻳﺮﻭ ﻭﺍﻥ‬
52 AC UPS Electric 307/YAK/2021 Local 117/YAK2021
‫ﺍﻟﻴﻜﺘﺮﻭﻧﻜﺲ‬
ETA (Expected to arrive) 15-02-23
Act 01-12-20 18-02-21 18-04-21 26-07-21 Partial Delivery (50%)
Plan 15-04-21 20-05-21 27-05-21 26-07-21 (3.5) Months 10-11-21
‫ﺳﻴﻨﺎ ﻟﻠﻤﺸﺮﻭﻋﺎﺕ‬
53 DC UPS Electric 11/YAK/2021 Local PO Plan (12:14) Wks From PO 23-01-22 145/YAK/021
‫ﺍﻟﻬﻨﺪﺳﻴﺔ‬
Act 31-12-20 06-04-21 10-05-21 26-07-21 Arrived @ Site
Plan 15-03-21 19-04-21 26-04-21 26-07-21 (3) Months 26-10-21
PO Plan (3) Months from P.O & Adv. Pay 25-10-21 ‫ﺗﺮﺍﻳﻨﺠﻞ ﻟﻠﻤﻌﺪﺍﺕ‬
54 Generator Electric 305/YAK/2020 Local 148/YAK/2021
ETA (Expected to arrive) 01-06-23 ‫ﺍﻟﺜﻘﻴﻠﺔ‬
Act 02-12-20 14-03-21 19-05-21 26-07-21 RFS

Page 92 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 15-06-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22 ‫ﺍﻟﺸﺮﻛﺔ ﺍﻟﻤﺼﺮﻳﺔ‬
(3:4 Month From Adv. Pay. & ‫ﻟﻠﺼﻨﺎﻋﺔ ﻭ ﺍﻟﻨﻈﻢ‬
55 Distribution Boards Electric 303/YAK/2021 Local PO Plan 22-06-22 513/YAK/2021
DWG. App.) ‫ﺍﻟﻤﺘﻘﺪﻣﺔ‬
Act 24-06-21 18-11-21 29-12-21 21-02-22 Arrived @ Site ‫ﺍﻟﺴﻮﻳﺪﻯ‬-(‫)ﺍﻳﻤﺎﺱ‬
Plan 15-06-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22
‫ﺍﻟﺸﺮﻛﺔ ﺍﻟﻤﺼﺮﻳﺔ‬
(2:3 Month From Adv. Pay. &
*Distribution Boards PO Plan DWG. App.)
27-06-22 ‫ﻟﻠﺼﻨﺎﻋﺔ ﻭ ﺍﻟﻨﻈﻢ‬
56 Electric 219/NGE/2022 Local 211/NGE/2022
(Utilities) ‫ﺍﻟﻤﺘﻘﺪﻣﺔ‬
ETA (Expected to arrive) 29-03-23
‫ﺍﻟﺴﻮﻳﺪﻯ‬-(‫)ﺍﻳﻤﺎﺱ‬
Act 13-03-22 20-03-22 25-03-22 28-03-22
Plan 15-06-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22
*Distribution Boards ‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺇﻋﺘﻤﺎﺩ‬3) : (1) ‫ﻣﻦ‬ ‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ‬
57 Electric 782/NGE/2022 Local PO Plan 15-10-22 744/NGE/2022
(Utilities) (‫ ﻳﻮﻡ ﻣﻦ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬10) ‫ﺍﻟﺮﺳﻮﻣﺎﺕ‬ ‫ﻟﻠﺘﻮﺭﻳﺪﺍﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 13-03-22 20-03-22 25-03-22 28-03-22 Arrived @ Site
Plan 15-06-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22
‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺇﻋﺘﻤﺎﺩ‬4) : (2) ‫ﻣﻦ‬
* Water treatment electrical PO Plan ‫ﺍﻟﺮﺳﻮﻣﺎﺕ )ﺇﺳﺒﻮﻋﻴﻦ ﻣﻦ ﺇﺳﺘﻼﻡ ﺃﻣﺮ‬ 6 20-12-22 ‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ‬
58 Electric 996/ALY/2022 Local (‫ﺍﻟﺘﻮﺭﻳﺪ‬ 902/ALY/2022
features ‫ﻟﻠﺘﻮﺭﻳﺪﺍﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
ETA (Expected to arrive) 15-02-23
Act 18-10-22 25-10-22 01-11-22 08-11-22 RFS
Plan 14-02-21 20-05-21 09-06-21 21-11-21 (8) Weeks 8 16-01-22
‫ﻣﺎﺗﺮﻳﻜﺲ ﻟﻠﻬﻨﺪﺳﺔ‬
‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻟﺪﻓﻌﺔ ﺍﻟﻤﻘﺪﻣﺔ‬12) : (4) ‫ﻣﻦ‬ 04-05-22 208/YAK/2021
59 Lighting Fixtures Electric 65/YAK/2021 Local PO Plan ‫ﻭﺍﻟﺘﺠﺎﺭﺓ‬
‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬16) : (4) ‫ﻣﻦ‬ 01-06-22 209/YAK/2021 ‫ﺍﻹﻧﺎﺭﺓ ﺍﻟﻌﺎﻣﺔ‬
Act 25-02-21 23-05-21 13-07-21 09-02-22 Arrived @ Site
Plan 14-02-21 20-05-21 09-06-21 21-11-21 (8) Weeks 8 16-01-22
60 *Lighting Fixtures - Balance Electric 523/NGE/2022 Local PO Plan ‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬12) : (10) ‫ﻣﻦ‬ 12-09-22 407/NGE/2022 ‫ﺍﻹﻧﺎﺭﺓ ﺍﻟﻌﺎﻣﺔ‬
Act 12-06-22 16-06-22 18-06-22 19-06-22 Arrived @ Site
Plan 14-02-21 20-05-21 09-06-21 21-11-21 (8) Weeks 8 16-01-22
61 *Lighting Fixtures - Balance Electric 524/NGE/2022 Local PO Plan ‫( ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬12) : (6) ‫ﻣﻦ‬ 12-09-22 408/NGE/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 12-06-22 16-06-22 18-06-22 19-06-22 Arrived @ Site
Plan 14-02-21 20-05-21 09-06-21 21-11-21 (8) Weeks 8 16-01-22
62 *Lighting Fixtures - Balance Electric 522/NGE/2022 Local PO Plan (2) ‫ﺇﺳﺒﻮﻉ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬ 01-07-22 409/NGE/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 12-06-22 14-06-22 15-06-22 16-06-22 Arrived @ Site
Plan 20-06-21 07-12-21 14-12-21 21-12-21 (8) Weeks 8 15-02-22
15-03-22 (8 : 12) Wks from PO 08-06-22 136/YAK/2022 ‫ﺑﻰ ﺍﻯ ﺳﻰ ﺳﻰ‬
Electrical MV, Power and
63 control cables Electric 344/YAK/2021 Local PO Plan 15-03-22 (2 : 10) Wks from PO (4/4/22) 25-05-22 233/YAK/2022 ‫ﺑﻰ ﺍﻯ ﺳﻰ ﺳﻰ‬
OSBL
15-03-22 (2 : 5) Months from PO 13-08-22 138/YAK/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 04-07-21 31-01-22 28-02-22 15-03-22 Arrived @ Site
Page 93 of 234
Plan 29-06-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
64 OSBL-Cable - Balance Electric 573/NGE/2022 Local PO Plan (1:3) months from PO 28-09-22 484/NGE/2022 ‫ﺑﻰ ﺍﻯ ﺳﻰ ﺳﻰ‬
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Act 26-06-22 27-06-22 28-06-22 29-06-22 Arrived @ Site
Plan 29-06-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22 ‫ﺍﻟﻬﻨﺪﺳﻴﺔ ﻟﻸﻋﻤﺎﻝ‬
65 Cable Trays Electric 356/AHH/2021 Local PO Plan (1:3) months from PO 12-06-22 76/AHH/2022 ‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 26-07-21 21-12-21 26-01-22 13-03-22 Arrived @ Site (‫ﻭﺍﻟﻤﻴﻜﺎﻧﻴﻜﻴﺔ )ﺍﻣﻜﻮ‬
Plan 29-06-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22 ‫ﺍﻟﻬﻨﺪﺳﻴﺔ ﻟﻸﻋﻤﺎﻝ‬
66 *Cable Trays Electric 390/YAK/2022 Local PO Plan ‫( ﺷﻬﺮ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬3) ‫ﺧﻼﻝ‬ 27-08-22 342/YAK/2022 ‫ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 12-05-22 19-05-22 26-05-22 28-05-22 Arrived @ Site (‫ﻭﺍﻟﻤﻴﻜﺎﻧﻴﻜﻴﺔ )ﺍﻣﻜﻮ‬
Plan 29-06-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
PO Plan ‫( ﺷﻬﺮ ﻣﻦ ﺇﺳﺘﻼﻡ ﺍﻟﺪﻓﻌﺔ ﺍﻟﻤﻘﺪﻣﺔ‬2) ‫ﺧﻼﻝ‬ 22-12-22 ‫ﺍﻟﺴﻮﻳﺪﻯ )ﺇﻳﺠﻰ‬
67 *Cable Trays Electric 917/ALY/2022 Local 854/ALY/2022
(‫ﺗﺮﺍﻯ‬
ETA (Expected to arrive) 15-02-23
Act 02-10-22 09-10-22 16-10-22 23-10-22 Partial Delivery (60%)
Plan 16-05-21 20-06-21 27-07-21 07-10-21 (3) Months 07-01-22
(2M) for Power
05-02-22 312/YAK/2021 ‫ﺑﻰ ﺍﻯ ﺳﻰ ﺳﻰ ﻟﻠﻜﺎﺑﻼﺕ‬
Electrical Power and Control (4M) for Control
68 Cables Electric 170/YAK/2021 Local PO Plan ‫ﺍﻟﻤﺼﺮﻳﺔ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
ISBL (2 : 4 ) Months 05-02-22 313/YAK/2021(Control) -‫ﺍﻟﻤﺘﻄﻮﺭﺓ )ﺍﻟﺴﻮﻳﺪﻯ‬
(‫ﺳﻴﺪﻛﻮ‬
Act 21-04-21 25-07-21 19-09-21 05-10-22 Arrived @ Site
Plan 07-12-21 17-01-22 24-01-22 01-02-22 (3.5) Month 15 17-05-22
(6:10) Wk. from DWG. App. 31-05-22 199/ABD/2022 ‫ﺍﻟﻜﺘﺮﻭﺑﺎﻟﻚ‬
(3:4) Months from PO & DWG.
App.
20-07-22 200/ABD/2022 ‫ﻓﺎﻟﻜﻮﻥ ﻷﻧﻈﻤﺔ ﺍﻟﻄﺎﻗﺔ‬
PO Plan
69 Explosion proof material Electric 779/ABD/2021 Local
(14:16) Wk. from DWG. App. 12-07-22 201/ABD/2022 ‫ﺍﻟﻤﺸﻜﺎﺓ‬
‫( ﺷﻬﺮ ﻣﻦ ﺍﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬5) : (3) ‫ﻣﻦ‬ 19-08-22 202/ABD/2022 ‫ﺳﻴﺪﻛﻮ‬-‫ﺍﻟﺴﻮﻳﺪﻯ‬
ETA (Expected to arrive) 01-03-23
Act 18-01-22 09-03-22 21-03-22 21-03-22 Partial Delivery (75%)
Plan 31-12-20 10-06-21 20-09-21 01-11-21 (3) Months 13 01-02-22
(7:8) Months from Clear Tech.
PO Plan Approval date
16-11-22 ‫ﻫﻴﺘﺎﺷﻰ ﺇﻧﺮﺟﻰ‬
70 *Capacitor Banks Electric 614/HHA/2021 Local 167/HHA/2022
‫ﺗﻜﻨﻮﻟﻮﺟﻰ‬
ETA (Expected to arrive) 15-05-23
Act 26-10-21 16-01-22 06-03-22 20-03-22
Plan 20-06-21 07-12-21 14-12-21 21-12-21 (10) Weeks FOB 12 15-03-22
(1 : 4) Months from PO &
71 Cable Glands Electric 253/AHH/2022 Local PO Plan DWG's app.
29-07-22 191/AHH/2022 ‫ﺳﻴﺪﻛﻮ‬-‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 24-03-22 24-03-22 28-03-22 30-03-22 Arrived @ Site
Plan 20-06-21 09-12-21 16-12-21 26-12-21 (16) Weeks 16 17-04-22
PO Plan (2:6) Wks from PO. 21-03-23 ‫ﻧﻴﻮ ﻫﺎﻯ ﺑﺎﻭﺭ‬
72 Reducers Electric 90/ALY/2023 Local 58/ALY/2023
ETA (Expected to arrive) 21-03-23 ‫ﻟﻠﺘﻮﺭﻳﺪﺍﺕ ﺍﻟﻜﻬﺮﺑﺎﺋﻴﺔ‬
Act 17-01-23 Page 31-01-23
24-01-23 94 of 234 07-02-23
Plan 20-06-21 09-12-21 16-12-21 26-12-21 (16) Weeks 16 17-04-22
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
PO Plan (2:4) Wks from PO. 01-03-23 ‫ﺍﻟﻤﺼﺮﻳﺔ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
73 MV Termination End Reducer Electric 89/ALY/2023 Local
ETA (Expected to arrive) 01-03-23 ‫ﺍﻟﻤﺘﻄﻮﺭﺓ‬
Act 09-01-23 16-01-23 23-01-23 30-01-23
Plan 20-06-21 09-12-21 16-12-21 26-12-21 (16) Weeks 16 17-04-22
Control System PO Plan (4) Months from PO. 16-07-22 ‫ﺗﺮﺍﻳﻜﻢ ﻻﻧﻈﻤﺔ ﺍﻟﺘﺤﻜﻢ‬
74 INST 357/AHH/2021 Local 160/AHH/2021
DCS ETA (Expected to arrive) 15-02-23 ‫ﻭﺍﻟﺨﺪﻣﺎﺕ‬
Act 13-07-21 06-02-22 07-03-22 17-03-22 RFS
Plan 09-03-21 15-06-21 27-06-21 19-10-21 (8) Weeks FOB 10 03-01-22
75 Mechanical Level Indicator INST 132/OMG/2021 External PO Plan (8) Wks FOB From PO 21-05-22 354/132-21OMG/2021 VAREC INC
Act 09-03-21 15-06-21 27-06-21 19-10-21 Arrived @ Site
Plan 09-03-21 15-06-21 27-06-21 19-10-21 (8) Weeks FOB 10 03-01-22 254/290-22/ADL/2022
*Mechanical Level Indicator 290-
76 INST External PO Plan (6:8) Wks FOB From PO 09-08-22 354/290-22/ADL/2022 VAREC INC
(Balance) 22/ADL/2022
Act 01-05-22 03-05-22 10-05-22 17-05-22 Arrived @ Site

Page 95 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 01-04-21 25-11-21 02-12-21 09-12-21 (10) Weeks FOB 12 03-03-22
MWT
(12) Wks FOB from LOI 126/178-
77 Field Instrument INST 178/OMG/2021 External PO Plan 27-06-22 Mechanical
(14/3/22) 2021/OMG/2022
Works & Tanks
Act 01-04-21 22-02-22 09-03-22 14-03-22 Arrived @ Site
Plan 10-03-21 02-12-21 09-12-21 16-12-21 (14) Weeks FOB 16 07-04-22
(14 : 16) Wks FOB from DWG's
PO Plan app.
21-08-22 SAMSON
78 Control Valves INST 133/PET/2021 External 113/133-21/PET/2022
ETA (Expected to arrive) 07-02-23 Controls FZE
Act 10-03-21 22-02-22 08-03-22 10-04-22 Partial Delivery (60%)
Plan 22-03-21 17-10-21 02-12-21 09-12-21 (10) Weeks FOB 12 03-03-22
549/198-
79 Flow Meters INST 198/SHA/2021 External PO Plan (23) Wks FOB from DWG. App. 27-06-22 Emerson
2021/SHA/2021
Act 22-03-21 17-10-21 05-11-21 28-02-22 Arrived @ Site
Plan 24-05-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
(3 : 5 ) Month from PO 27-08-22 140/HOS/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
PO Plan
80 Instrument Cables INST 229/HOS/2021 Local (20 : 25) Wks from Adv. Pay. 21-09-22 141/HOS/2022 ‫ﺳﻴﻤﻨﺰ‬
ETA (Expected to arrive) 07-03-23
Act 07-06-21 16-01-22 23-02-22 29-03-22 Partial Delivery (90%)
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
81 *Instrument Cables (Balance) INST 992/ALY/2022 Local PO Plan (3:4 Month From PO) 07-03-23 898/ALY/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 23-10-22 30-10-22 06-11-22 07-11-22
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
82 *Instrument Cables (Balance) INST 378/HOS/2021 Local PO Plan (3:5 Month From PO) 28-10-22 236/HOS/2022 ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Act 10-05-22 14-05-22 16-05-22 18-05-22 Arrived @ Site
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
‫ﺍﻟﻜﺘﺮﻭﺑﺎﻟﻚ ﻟﻠﻬﻨﺪﺳﺔ‬
83 *INS. Cables Glandes ISBL INST 268/AHH/2022 Local PO Plan ‫( ﺍﺳﺎﺑﻴﻊ ﻣﻦ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬5) : (4) ‫ﺧﻼﻝ ﻣﻦ‬ 22-08-22 482/AHH/2022
‫ﻭﺍﻟﺘﻮﺭﻳﺪﺍﺕ‬
Act 27-06-22 27-06-22 11-07-22 18-07-22 Arrived @ Site
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
(10) ‫ ﻣﻦ‬+ ‫ﺑﻀﺎﻋﺔ ﺣﺎﺿﺮﺓ ﻟﺒﻌﺾ ﺍﻟﺒﻨﻮﺩ‬
*Instrument Bulk Material ‫( ﺍﺳﺒﻮﻉ ﻣﻦ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ )ﻟﻠﺒﻨﻮﺩ‬12) :
21-09-22 467/NGE/2022 ‫ﺍﻻﻧﺪﻟﺲ ﻟﻠﺘﺠﺎﺭﺓ‬
84 INST 341/NGE/2022 Local PO Plan
(Hook up) ‫ﺑﻀﺎﻋﺔ ﺣﺎﺿﺮﺓ‬ 06-07-22 468/NGE/2022 ‫ﺍﺭﺑﻮﺭ‬
Act 11-05-22 06-06-22 21-06-22 26-06-22 Arrived @ Site
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
*Instrument Bulk Material
85 INST 870/ALY/2022 Local PO Plan ‫ﺇﺳﺒﻮﻋﺎﻥ ﻋﻤﻞ ﻣﻦ ﺇﺻﺪﺍﺭ ﺃﻣﺮ ﺍﻟﺘﻮﺭﻳﺪ‬ 05-12-22 953/ALY/2022 ‫ﺇﺳﺘﻴﻞ ﺳﻴﺘﻰ‬
(Hook up)
Act 06-11-22 13-11-22 20-11-22 21-11-22 Arrived @ Site
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
Instrument JB's and Bulk PO Plan (3:4 Month From DWG. App.) 06-06-22 ‫ﻧﺪﻛﻮ ﺍﻟﻬﻨﺪﺳﻴﺔ‬
86 INST 355/AHH/2021 Local 45/AHH/2022
Materials ETA (Expected to arrive) 15-02-23 ‫ﻟﻠﻤﻘﺎﻭﻻﺕ ﻭﺍﻟﺘﻮﺭﻳﺪﺍﺕ‬
Act 07-06-21 26-10-21 05-01-22 03-02-22 RFS
Page 96 of 234
Plan 10-10-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
* Instrument JB's and Bulk (2:4 Month) From PO & Tech.
87 INST 39/SHY/2022 Local PO Plan 28-07-22 185/SHY/2022 ‫ ﺳﻴﺪﻛﻮ‬- ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Materials App.
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Act 23-01-22 21-02-22 17-03-22 29-03-22 Arrived @ Site
Plan 20-06-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22
‫ﺗﺮﺍﻳﻜﻮﻡ ﻻﻧﻈﻤﺔ‬
88 Analyzer INST 734/YAK/2021 Local PO Plan (4 : 5) Months from Adv. Pay 18-08-22 156/YAK/2022
‫ﺍﻟﺘﺤﻜﻢ‬
Act 23-12-21 01-02-22 07-03-22 20-03-22 Arrived @ Site
Plan 13-10-21 20-10-21 25-11-21 02-12-21 (12) Weeks 12 24-02-22
‫ﺗﺮﺍﻳﻜﻮﻡ ﻻﻧﻈﻤﺔ‬
89 * Analyzer INST 56/YAK/2022 Local PO Plan (4 : 5) Months 16-09-22 192/YAK/2022
‫ﺍﻟﺘﺤﻜﻢ‬
Act 30-01-22 14-03-22 18-04-22 18-04-22 Arrived @ Site
Plan 20-06-21 17-10-21 02-12-21 09-12-21 (12) Weeks 12 24-02-22
22 / 8 / 26 ‫ﻣﻦ‬
90 * Conduit INST 365/NGE/2022 Local PO Plan (3:4) Months from PO 343/NGE/2022 ‫ﺍﻟﻤﺸﻜﺎﺓ‬
22 / 9 / 26 ‫ﺇﻟﻰ‬
Act 28-04-22 28-04-22 28-04-22 28-05-22 Arrived @ Site
Plan 24-05-21 25-11-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
*Utility Instrument cables & (3:5) Months from PO &
91 INST 736/AHH/2021 Local PO Plan 22-10-22 206/AHH/2021 ‫ ﺳﻴﺪﻛﻮ‬- ‫ﺍﻟﺴﻮﻳﺪﻯ‬
Glandes DWG. App.
Act 23-12-21 14-03-22 23-03-22 24-05-22 Arrived @ Site
Plan 11-03-21 12-07-21 29-09-21 05-12-21 (14:16) Weeks 15 20-03-22
PO Plan (14:16) WK. from Adv. Pay 17-08-22 ‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﺘﻘﻨﻴﺔ‬
92 Fire Alarm Telecom 92/YAK/2021 Local 365/YAK/2021
‫ﺍﻟﻤﻌﻠﻮﻣﺎﺕ‬
ETA (Expected to arrive) 01-03-23
Act 07-04-21 12-07-21 20-10-21 29-03-22 Partial Delivery (70%)
Plan 06-06-21 14-10-21 02-12-21 09-12-21 (20) Weeks 20 28-04-22
PO Plan (14:16) WK. from Adv. Pay 20-07-22 ‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﺘﻘﻨﻴﺔ‬
93 IP Telephone Telecom 278/YAK/2021 Local 479/YAK/2021
‫ﺍﻟﻤﻌﻠﻮﻣﺎﺕ‬
ETA (Expected to arrive) 20-06-23
Act 16-06-21 18-10-21 02-12-21 29-03-22 Partial Delivery (60%)
Plan 16-09-21 21-10-21 28-10-21 01-12-21 (14:16) Weeks 16 23-03-22
‫ﺍﻻﻧﻈﻤﺔ ﺍﻟﺘﻜﻨﻮﻟﻮﺟﻴﺔ‬
PO Plan (14:16) WK. from Adv. Pay 14-06-22
94 CCTV Telecom 93/YAK/2021 Local 374/YAK/2021 ‫ﺍﻟﻤﺘﺨﺼﺼﺔ‬
ETA (Expected to arrive) 01-03-23 (‫)ﻫﺎﻳﺘﻜﻨﻮﻓﻞ‬
Act 07-04-21 27-06-21 26-07-21 21-02-22 Partial Delivery (50%)
Plan 03-06-21 06-10-21 02-12-21 09-12-21 (12) Weeks 12 03-03-22
(14:16) WK. from PO, DWG's
PO Plan App. & Adv. Pay
23-05-22 ‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﺘﻘﻨﻴﺔ‬
95 Public Address Telecom 265/YAK/2021 Local 15/YAK/2022
‫ﺍﻟﻤﻌﻠﻮﻣﺎﺕ‬
ETA (Expected to arrive) 15-03-23
Act 03-06-21 06-10-21 03-01-22 30-01-22
Plan 09-06-21 25-11-21 02-12-21 09-12-21 (16) Weeks 16 31-03-22
PO Plan (25 : 26) Wks from Adv. Pay 19-09-22 ‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﺘﻘﻨﻴﺔ‬
96 Data Network Telecom 291/YAK/2021 Local 125/YAK/2022
‫ﺍﻟﻤﻌﻠﻮﻣﺎﺕ‬
ETA (Expected to arrive) 30-04-23
Act 15-06-21 03-01-22 22-02-22 20-03-22 Partial Delivery (40%)
Page 97 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 18-11-21 25-11-21 02-12-21 09-12-21 (16) Weeks 16 31-03-22
PO Plan (8) Months from PO 14-01-23
97 * Data Center Telecom 151/NGE/2022 Local 1047/NGE/2022 MST
ETA (Expected to arrive) 01-03-23
Act 27-02-22 13-03-22 15-03-22 18-05-22
Plan 18-11-21 25-11-21 02-12-21 09-12-21 (16) Weeks 16 31-03-22
‫ﺍﻟﺴﻮﻳﺪﻯ ﻟﻠﺼﻨﺎﻋﺎﺕ‬
98 * Fiber Optical Cables Telecom 295/AHH/2022 Local PO Plan (2 : 4) Months from TBE 29-09-22 337/AHH/2022
‫ﺍﻟﻤﺘﻄﻮﺭﺓ‬
Act 18-05-22 19-05-22 23-05-22 31-05-22 Arrived @ Site
Plan 06-06-21 20-10-21 30-11-21 07-12-21 (8) Weeks 8 01-02-22
PO Plan (3) Months from PO & Adv. Pay. 12-06-22 ‫ﻧﻮﻓﻴﻚ ﻟﻠﻬﻨﺪﺳﺔ‬
99 HVAC HV 273/YAK/2021 Local 1027/YAK/2022
ETA (Expected to arrive) 01-03-23 ‫ﻭﺍﻟﻤﻘﺎﻭﻻﺕ‬
Act 16-06-21 23-10-21 24-02-22 13-03-22 Partial Delivery (75%)
Plan 22-03-21 04-05-21 08-06-21 25-07-21 (2) Months 25-09-21
Cathodic Protection Bulk
100 CP 123/ALD/2021 Local PO Plan 168/ALD/2021
Materials
Act 22-03-21 04-05-21 08-06-21 25-07-21 Arrived @ Site
Plan 15-10-21 19-11-21 26-11-21 22-11-21 (18:22) Weeks 22 25-04-22
(18:22) WK. from PO & DWG. ‫ﺍﻭﺗﺎﻙ ﻟﻠﺘﺠﺎﺭﺓ‬
101 Cathodic Protection Internal CP 236/YAK/2021 Local PO Plan 27-03-22 345/YAK/2021
App ‫ﻭﺍﻟﻤﻘﺎﻭﻻﺕ‬
Act 03-06-21 22-08-21 20-10-21 24-10-21 Arrived @ Site
Plan 15-10-21 19-11-21 26-11-21 22-11-21 (18:22) Weeks 22 25-04-22
*Cathodic Protection (MG (18:22) WK. from PO & DWG. ‫ﺍﻭﺗﺎﻙ ﻟﻠﺘﺠﺎﺭﺓ‬
102 CP 89/NGE/2021 Local PO Plan 01-08-22 80/NGE/2021
Anodes for tanks) App. ‫ﻭﺍﻟﻤﻘﺎﻭﻻﺕ‬
Act 06-02-22 10-02-22 17-02-22 27-02-22 Arrived @ Site
Plan 22-03-21 11-10-21 21-11-21 30-11-21 (21) Weeks FOB 23 10-05-22
Bioler water pump (2ea.)
(22 WK) FOB from P.O&DWG.
01-06-22

Hot water pump (2ea.)


(22 WK) FOB from P.O&DWG.
01-06-22

607/153-
Potable water pump (4ea.) Flowserve
103 Pumps (25 ea.) Package 153/OMG/2021 External PO Plan (19 Wk) FOB from P.O&DWG.
01-06-22 21/OMG/2021

Process water pump (4ea.)


(22 WK) FOB from P.O&DWG.
01-06-22
Rejection water pump (3ea.)
(27 WK) FOB from P.O&DWG.
01-06-22
002-P-100 A/B/C/D/E (5EA.) PUMP WORKS
(16 Wk.) FOB from PO
06-05-22 608/153-21/OMG/2021
610, LLC
Act 22-03-21 11-10-21 23-11-21 28-12-21 Arrived @ Site

Page 98 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 22-12-20 19-08-21 23-09-21 08-11-21 (20) Weeks 20 28-03-22
‫ﻛﻮﻣﺖ ﻟﻠﺘﺠﺎﺭﺓ‬
104 *Sewage Pumps (6ea.) Package 376/HOS/2022 Local PO Plan (20:22) Wks from Adv. Pay. 21-10-22 331/HOS/2022
‫ﻭﺍﻻﻋﻤﺎﻝ ﺍﻟﻬﻨﺪﺳﻴﺔ‬
Act 09-05-22 19-05-22 19-05-22 19-05-22 Arrived @ Site
Plan 22-12-20 19-08-21 23-09-21 08-11-21 (20) Weeks 20 28-03-22
‫ﺷﻮﻧﻚ ﻟﻸﻋﻤﺎﻝ‬
105 *Reject Pumps (2ea.) Package 343/NGE/2022 Local PO Plan (2) Weeks from Adv. Pay. 15-06-22 322/NGE/2022
‫ﺍﻟﻬﻨﺪﺳﻴﺔ‬
Act 23-04-22 17-05-22 24-05-22 31-05-22 Arrived @ Site
Plan 22-12-20 19-08-21 23-09-21 08-11-21 (20) Weeks 20 28-03-22
106 *Sludge Pump Package 509/NGE/2022 Local PO Plan ‫ﺑﻀﺎﻋﺔ ﺣﺎﺿﺮﺓ‬ 27-07-22 390/NGE/2022 ‫ﻫﺎﻳﺪﺭﻭﺗﻚ‬
Act 06-06-22 05-07-22 12-07-22 19-07-22 Arrived @ Site
Plan 22-12-20 19-08-21 23-09-21 08-11-21 (20) Weeks 20 28-03-22
‫ﺑﻴﻜﻮ ﻟﻠﺨﺪﻣﺎﺕ‬
107 Air Compressors Package 274/HOS/2021 Local PO Plan 2021 / 10 / 20 ‫( ﺍﺳﺒﻮﻉ ﻣﻦ‬20) 09-03-21 333/HOS/2021
‫ﺍﻟﺼﻨﺎﻋﻴﺔ‬
Act 27-06-21 18-08-21 20-10-21 23-11-21 Arrived @ Site
Plan 08-12-20 17-03-21 18-04-21 22-11-21 (5.5) Months 24 06-05-22
‫( ﺷﻬﺮ‬5) : (4) ‫ ﻣﻦ‬: ‫ﻣﺪﺓ ﺍﻟﺘﻮﺭﻳﺪ‬
Industrial water treatment PO Plan ‫( ﺷﻬﺮ‬5.5) : (5) ‫ ﻣﻦ‬: ‫ﻣﺪﺓ ﺍﻟﺘﺮﻛﻴﺐ‬
24-06-22
108 Package 346/YAK/2020 Local 1162/YAK/2021 IETOS
PKG. ETA (Expected to arrive) 01-02-23
Act 17-12-20 06-04-21 12-09-21 25-12-21 Partial Delivery (70%)
Plan 10-10-21 17-10-21 24-11-21 08-12-21 (17) Weeks FOB 17 04-05-22
* Chemical Injection Skids PO Plan (10) Wks FOB from PO 30-06-22 PERTOSTAR
109 Package 757/MOA/2021 External 142/757-21/MOA/2022
(3ea.) S.R.L.
Act 28-12-21 15-03-22 18-03-22 24-03-22 Arrived @ Site
Plan 10-10-21 17-10-21 24-11-21 08-12-21 (17) Weeks FOB 04-05-22
* Pressure Reduction Skid PERTOSTAR
110 Package 79/MOA/2022 External PO Plan (10) Wks FOB from PO 22-06-22 127/79-22/MOA/2022
(PRS) S.R.L
Act 03-02-22 09-03-22 12-03-22 16-03-22 Arrived @ Site
Plan 26-05-21 30-06-21 07-07-21 09-07-21 (37) Week 16-03-22 SIEMPELKAMP
111 Over Head Crane Package 250/MOA/2021 External PO Plan (37) Week 16-03-22 250-21/MOA/2021 KRANTECHNIK
GMBH
Act 13-01-21 13-01-21 13-01-21 30-06-21 Arrived @ Site
Plan 26-05-21 30-06-21 07-07-21 09-07-21 (37) Week 16-03-22 SIEMPELKAMP
112 *Straw Bale Grap for O.H.C Package 199/MOA/2022 External PO Plan (30) Week FOB 27-11-22 294/199-22/MOA/2022 KRANTECHNIK
GMBH
Act 27-02-22 13-03-22 27-03-22 10-04-22 Arrived @ Site
Plan 29-09-21 03-11-21 10-11-21 15-11-21 (4) Months 15-03-22
(1) Months from Finishing Civil
PO Plan Works
04-12-21 ‫ﺍﻟﺪﻟﺘﺎ ﻟﻺﺳﺘﺸﺎﺭﺍﺕ‬
113 Truck Scale Package 146/YAK/2021 Local 1152/YAK/2021
‫ﺍﻟﻬﻨﺪﺳﻴﺔ‬
ETA (Expected to arrive) 01-03-23
Act 05-05-21 11-07-21 06-10-21 03-11-21 Partial Delivery (40%)

Page 99 of 234
MDF Procurement Plan (Engineering Dept.)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Bid # Market Prog. Supplier
Technical Commercial
RFQ PO Delivery Time Delivery @ Site PO NO.
Study Evaluation
Plan 17-06-21 14-11-21 05-12-21 12-12-21 (20) Weeks 20 01-05-22
(12) Wk. (FOB) from DWG. PRO.DO.MIX
114 Tank Acc (Agitators) Other 352/SHA/2021 External PO Plan 23-05-22 550/352-2021/SHA/2021
App. S.R.L
Act 17-06-21 14-11-21 01-12-21 27-12-21 Arrived @ Site
Plan 07-12-21 17-01-22 24-01-22 01-02-22 (3.5) Month 15 17-05-22
‫ ﻣﻦ ﺗﺎﺭﻳﺦ ﺃﻣﺮ‬FCA ‫( ﺍﺳﺎﺑﻴﻊ ﻋﻤﻞ‬8)
115 *SS Explosion Proof Vent Electric 150-22/BRK/2022 External PO Plan ‫ﺍﻟﺘﻮﺭﻳﺪ ﻋﻠﻰ ﺍﻥ ﻳﻜﻮﻥ ﺍﻟﺸﺤﻦ ﺑﻤﻌﺮﻓﺔ ﻭﻋﻠﻰ‬ 01-08-22 135/150-22-BRK/2022 REMBE
‫ﺣﺴﺎﺏ ﺑﺘﺮﻭﺟﺖ‬
Act 10-03-22 22-03-22 22-03-22 24-03-22 Arrived @ Site
Plan 07-12-21 17-01-22 24-01-22 01-02-22 (3.5) Month 15 17-05-22
(2) : (3) Wks. From PO &
PO Plan 15-11-22 ‫ﺍﻟﻌﺎﻟﻤﻴﺔ ﻟﻸﻧﻈﻤﺔ‬
116 * Flexible Hoses FF 783/YAK/2022 Local Down Pay. 1161/NGE/2022
ETA (Expected to arrive) 01-04-23 ‫ﺍﻟﻤﺘﻜﺎﻣﻠﺔ‬

Act 20-05-22 21-08-22 02-09-22 14-09-22

Page 100 of 234


MDF Procurement Plan (ٍSite)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Res. Bid # Prog. Technical Commercial Delivery Delivery
RFQ PO PO NO.
Study Evaluation Time @ Site
Plan 10-09-20 07-10-20 13-10-20 15-10-20 (1) Month 17-11-20
1 Mech 202776
ST Act 18-11-20 Completed Completed 20-12-20 Completed 2533/2020
2 ST Mech 21826 Act 20-12-20 Completed Completed 20-01-21 Completed 88/2021
3 Steel Beams (Final Product WH) ST Mech 19923 Act 20-12-20 Completed Completed 20-01-21 Completed 89/2021
4 ST Mech 21719 Act 20-12-20 Completed Completed 20-01-21 Completed 90/2021
5 ST Mech 22318 Act 06-09-20 Completed Completed 10-12-20 Completed 2464/2020
6 ST Mech 12647 Act 22-04-21 Completed Completed 26-06-21 Completed 10301/2021
Plan 28-03-21 12-04-21 19-04-21 22-04-21 (4) Months 21-08-21
7 ST Mech Completed Completed 01-04-21 502/2021
12318 Act 06-02-21 Completed
ST 01-04-21 503/2021
Steel Beams Plot-6 (STREW BUILDING) ST Completed Completed 14-04-21 570/2021
8 ST Mech 12317 Act 06-02-21 14-04-21 Completed 571/2021
ST 14-04-21 572/2021
9 ST Mech 12625/2021 Act 09-05-21 Completed Completed 10-06-21 Completed 803/2021
Plan 25-08-21 09-09-21 16-09-21 21-09-21 (1) Month 21-10-21
10 ST Mech 12316/2021 Act 22-02-21 Completed Completed 21-03-21 Completed 673/2021
ST Completed Completed 23-06-21 895/2021
11 ST Mech 12682/2021 Act 23-05-21 23-06-21 Completed 896/2021
ST 23-06-21 894/2021
ST 1534/2021
12 Steel Beams ( Plot-2 - matformer) Mech 13286 Act 22-09-21 25-10-21 11-11-21 11-11-21 Completed
ST 1535/2021
ST 04-11-21 348/2021
ST 04-11-21 397/2021
13 ST Mech 535/2021 Act 04-06-21 Completed Completed 04-11-21 Completed 394/2021
ST 04-11-21 503/2021
ST 04-11-21 336/2021

Page 101 of 234


MDF Procurement Plan (ٍSite)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Res. Bid # Prog. Technical Commercial Delivery Delivery
RFQ PO PO NO.
Study Evaluation Time @ Site
Plan 02-06-21 10-07-21 25-07-21 10-08-21 10-09-21
14 Bolts Mech 12522 Act 17-03-21 Completed Completed 14-06-21 Completed 5100091269
15 Bolts & Nuts Bolts Mech 12754 Act 02-06-21 Completed Completed 10-08-21 Completed 5100094228
16 Bolts Mech 12297 Act 22-02-21 Completed Completed 20-06-21 Completed 5100091603
17 Bolts Mech 12420 Act 03-01-21 Completed Completed 17-04-21 Completed 5100088328
Plan 17-01-21 07-02-21 14-02-21 18-02-21 (2) Months 19-04-21
18 Mech 12017
TK Act 13-12-20 Completed Completed 07-02-21 Completed 173/2021
19 Tank Plates Batch-1( Industrial, Demi , TK Mech 12271 Act 08-02-21 Completed Completed 27-03-21 Completed 452/2021
20 Process ) TK Mech 12682/2021 Act 24-05-21 Completed Completed 23-06-21 894/2021

Completed 1629/2021
21 TK Mech 13394/2021 Act Completed 17-11-21 30-11-21 02-12-21 1630/2021
1631/2021
Plan 28-09-21 22-11-21 28-11-21 02-12-21 (3) Months 01-03-22
Container for Sludge and Solids - Group 4572 Forecast (1) Week 25-10-21
22 Mech 12953
(IBC -1000 lt)
Others Act 05-07-21 18-09-21 31-10-21 18-10-21 Completed 10452/2021

Plan 28-09-21 24-11-21 01-12-21 08-12-21 (1) Month 07-01-22


23 Assembly Req. & Star Cooler Arm (Wood) Mech
Others Act 29-08-21 29-11-21 Completed Completed Completed 6732/2021
Plan 28-09-21 24-11-21 01-12-21 08-12-21 (1) Month 07-01-22
24 Assembly Req. & Star Cooler Arm (Steel) Mech
Others Act 29-08-21 29-11-21 Completed Completed Completed comp.
Plan 29-08-21 19-09-21 23-09-21 17-10-21 (2) Months 17-12-21
25 Metal Deck Mech 14509
ST Act 10-07-21 12-09-21 03-10-21 11-10-21 Completed 6125/KEA/21

Plan 20-10-21 01-12-21 08-12-21 15-12-21 (2) Months 15-02-22


26 Potable Water Tank (GRP) Mech
TK Act 05-10-21 13-12-21 Completed Completed Completed 6040/KEA/22
Plan 17-01-22 15-02-22 22-02-22 01-03-22 (1) Month 01-04-22
27 Mirrors Station with gear motor - Group 5445 Mech
Others Act Completed Completed Completed Completed RFS 8613/2022
Plan 02-01-22 01-02-22 08-02-22 15-02-22 (2) Months 15-04-22
28 High Pressure Generator Electrical
Others Act Completed Completed Completed Completed Completed

Plan 02-01-22 24-01-22 01-02-22 08-02-22 (2) Months 08-04-22 rem.


29 Noise Protection system Mech
Others Act Completed
Plan 07-11-21 08-12-21 15-12-21 22-12-21 (1) Month 20-01-22
30 Refractory Mech Page 102 of 234
MDF Procurement Plan (ٍSite)
As of Date 11‐02‐23

Current Status Plan


Sr. Material List Discipline Res. Bid # Prog. Technical Commercial Delivery Delivery
RFQ PO PO NO.
Study Evaluation Time @ Site
30 Refractory Mech
Others Act 06-11-21 Completed Completed Completed Completed 6669/22
Plan 02-01-22 01-02-22 08-02-22 15-02-22 (2) Months 15-04-22
31 Safety Barriers & Fence Civil
Others Act Completed Completed Completed 23-01-23

Electrical secured accesses door and flaps - Plan 20-02-22 20-03-22 27-03-22 03-04-22 (2) Months 01-06-22 rem.
32 Civil
GR-4599 Others Act Completed Completed Completed 23-01-23
Plan 10-10-21 24-11-21 02-12-21 12-12-21 (1.5) Month 27-01-22
33 Rails Mech 14704
Others Act 10-10-21 02-12-21 Completed Completed Partially 6444/22
Plan 09-12-21 30-12-21 09-01-22 16-01-22 (1) Month 15-02-22
34 Grating Mech 1562/22
ST Act 18-11-21 18-11-21 Completed Completed Partially 1561/22

Plan 07-10-21 31-10-21 07-11-21 30-11-21 (1) Month 30-12-21 1808/22


35 Piping Support Mech
ST Act 01-05-22 01-05-22 01-05-22 01-05-22 Partially comp.

Plan 22-11-21 13-12-21 20-12-21 27-12-21 (1) Month 25-01-22


36 Handrails Mech
ST Act 01-12-21 Completed Completed Completed Partially comp.

Plan 28-12-21 01-02-22 11-02-22 01-03-22 (4) Month 01-07-22


37 Fuel Station Mech
Others Act 01-12-21 Completed Completed Completed RFS 1655/22

Page 103 of 234


Construction Skyline (Civil Works)

Production Line Buildings / Warehouses / Sheds Civil Works

Permanent TCF Building Tanks Civil Works


Primary MDF Warehouse

Final MDF WH, Matforming, (Plot -1) Substation Building Roads / Paving
Cooling & Stacking

Press & Contiroll@ Sump Scale With Room Potable Water Network

Dryer & Sifting (Plot-2) HSE Building Fire Fighting Network (HDBE)

Silo Area (Plot-3) New Switch Room Sewer Network

Refining Area (Plot-4) Main Security Building U/G Works - OSBL Storm Network

Straw Cleanning Area (Plot-5) Security Building Electrical Network (Concrete Trench)

Straw Preparation (Plot-6) Masjid Building [Mosque] Instrumentation Network

Remaining U/G Piping Network


Dryer & Blending (Plot-7) Guard Towers
(Chemical Waste if Any)

Control Room Warehouse For Chemical and Additive Piping Sleepers

Switch Rooms Rice Straw Warehouse Fences (External)

Glue Storage Shed (Plot-7) Air Compressor Shed Gates

Industrial Pump Station New Pipe Racks

Potable Water Pump Station Lighting Poles - Civil

Reject Water Pump Station

Industrial Water Treatment PKG.

Fire Pump Shed

Not Started
Catch Basin & Trench Covers
In Progress
Page 104 of 234 Completed
SKYLINE (ELECTRICAL WORKS)
Lighting
Cable Trays Pulling Power Pulling Lighting
Cable Trays Panels Erection Termination Poles / Fixtures Earthing F&G HVAC
Supports Cable Cable
Erection

HSE-Control
Plot-1 ISBL ISBL DC UPS ISBL-Equipment ISBL ISBL ISBL
Building

Substation
Plot-6 OSBL OSBL AC UPS OSBL-Equipment OSBL OSBL OSBL
Building

Emergency
Local Pannels Scale Room
Generator

Transformars Lighting Fixtures Security Room

New Switch Room


MVSG
Building

LVSG Mosque Building

Main Security
DCS
Room

Production
Building

Switch Room
SR01B

Switch Room
SR02B

Switch Room
SR02C

Switch Room
SR022

Refining SR02A

Straw Building
SR01A
Not Started
In Progress Glue Storage Tank
Completed Building
Page 105 of 234
SKYLINE (INSTRUMENTATION WORKS)

Pulling Pulling Fiber Optical Field Instrumentation Field Instrumentation


Junction Box Erection Termination
Instrumentation Cables Cables-F.O.C Calibration Installation

ISBL ISBL ISBL ISBL ISBL ISBL

OSBL OSBL OSBL OSBL OSBL OSBL

Not Started
In Progress
Completed

Page 106 of 234


SKYLINE (TELECOMMUNICATION WORKS)

ISBL OSBL

Fire Alarm System Fire Alarm System

Public Address System Public Address System

CCTV System CCTV System

Data Network Data Network

Data Center Data Center

IP-Telephone IP-Telephone

Not Started
In Progress
Completed

Page 107 of 234


Construction Skyline (Mechanical Works)
Structural Steel
Steel Structure Erection Equipment Equipment
Fabrication & Painting Tanks Fabrication Tanks Erection
Works Instalation Fabrication
Works

Production Line (Plot-1) Production Line (Plot-1) ISBL-(Plot-1) Champers Industrial Raw Water Tank (101) Industrial Raw Water Tank (101)

Production Line (Plot-2) Production Line (Plot-2) ISBL-(Plot-2) Cyclones DEMI Water Tank (103) DEMI Water Tank (103)

Production Line (Plot-3) Production Line (Plot-3) ISBL-(Plot-3) Silos Process Water Tank (102) Process Water Tank (102)

Production Line (Plot-4) Production Line (Plot-4) ISBL-(Plot-4) Stacks Potable Water Tank

RC Building Platform &


Production Line (Plot-5) Production Line (Plot-5) ISBL-(Plot-5) Vessels Fire Water Tanks Fire Water Tanks
Ladder
Pits Covers (Chemical &
Production Line (Plot-6) Production Line (Plot-6) ISBL-(Plot-5) Containers
Reject)
MDF‐LIQUID Sound Cabinet for
Production Line (Plot-7) Production Line (Plot-7) ISBL-(Plot-7) Thermal Oil Heater
CHEMICAL SHED G.4550

Filters GENERATOR SHED Filters Loading Arm for PMDI OSBL Air Compressor

ISBL / OSBL - Warehouses & ISBL / OSBL - Warehouses & MDF‐LIQUID


Car Parking Shed Scale With Room
Sheds Sheds CHEMICAL SHED
Industrial Pump
Industrial Pump Shed GENERATOR SHED
Station
POTABLE WATER Potable Water Pump
Car Parking Shed
PUMP HOUSE Station
Reject Water Pump
3 NEW PIPE RACKS Industrial Pump Shed
Station
POTABLE WATER
Fire Truck HSE Shed Fire Pump
PUMP HOUSE

Fire Pump Shed 3 NEW PIPE RACKS

Reject Water Shed Fire Truck HSE Shed

Water Treatment Shed Fire Pump Shed

Compressor Shed Reject Water Shed

Transformer Sheds Water Treatment Shed

MDF Main Gate Compressor Shed

Pits Covers (Chemical &


Transformer Sheds
Reject)
RC Building Platform & Not Started
MDF Main Gate
Ladder In Progress
Completed

Page 108 of 234


Construction Skyline (Piping)

Piping Fabrication Piping Erection

Fuel Gas system FG Fuel Gas system FG

Spark System SE Spark System SE

Compressed Air system AI Compressed Air system AI

Boiling and fresh water Boiling and fresh water


system WH system WH

Chemical System Chemical System

Steam system ST Steam system ST

Demi Water (WD) system Demi Water (WD) system

Process Water (WP) system Process Water (WP) system

Raw Water (WR) system

Rejected Water (WJ) system

Open Drain (DO)

Potable Water (WT) system

Fire Water (WF) system


Under Ground

ONSPEC-Fire Water ONSPEC-Fire Water


above ground above ground

DN CS-ISBL DN CS-ISBL

SK-PKG's

Second Reheating

WESP

Press Fume Extraction

Not Started
In Progress
Completed Page 109 of 234
205,000 M3/Y
MEDIUM- DENSITY FIBERBOARD
MDF PLANT
Date: 15-02-2023 Weekly Report No. 120 Up To: 11-02-2023

Attachment #1
Detailed Progress

Page 110 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Engineering 235,861 100.0% 100% 100% 100% 100% 100% 100% 100% 98%
Potable Water System 765 0% 100% 100% 100% 100% 100% 100% 100% 100%
A7740 PR PFD - Potable Water System MDF-PTJ-PR-PFD-0001 Potable Water System PFD 171 22% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A7750 PR P&ID's - Potable Water System MDF-PTJ-PR-PID-0008 Potable Water System PID 152 20% 31-Jan-21 17-Mar-21 27-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

A84500 PR Sewage Treatment Package Process Datasheet MDF-PTJ-PR-DAT-0008 Sewage Treatment Package Process Datasheet 102 13% 01-Apr-21 11-Apr-21 21-Apr-21 28-Apr-21 05-May-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PI PW GENERAL ARRANGEMENT MDF-PTJ-PI-LAY-0004 PW GENERAL ARRANGEMENT 160 21% 13-Nov-21 20-Nov-21 28-Nov-21 05-Dec-21 13-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

PI POTABLE WATER SYSTEM ISOMETRIC DRAWING MDF-PTJ-PI-ISO-0002 POTABLE WATER SYSTEM ISOMETRIC DRAWING 180 24% 20-Oct-21 27-Oct-21 04-Nov-21 11-Nov-21 19-Nov-21 26-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

Compressed Air System 984 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8210 PR PFD - Compressed Air System MDF-PTJ-PR-PFD-0004 Compressed Air System PFD 228 23% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A8220 PR P&ID's - Compressed Air System MDF-PTJ-PR-PID-0004 Compressed Air System PID 190 19% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

A8222 PI Piping G.A - Compressed Air System MDF-PTJ-PI-LAY-0005 Compressed Air GENERAL ARRANGEMENT 188 19% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

PI COMPRESSED AIR SYSTEM ISOMETRIC


A8223 PI Isometric Drawings - Compressed Air System MDF-PTJ-PI-ISO-0004 138 14% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
DRAWING
A8225 Air Comp -Data Sheet & Specification 240 24% 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-DAT-0001 Air Compressor System data sheet 96 40% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-SPC-0002 AIR COMPRESSOR Package SPECIFICATION 144 60% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

Boiling & Fresh Water System 801 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8150 PR PFD - Boiling & Fresh Water System MDF-PTJ-PR-PFD-0003 Boiling & Fresh Water System PFD 285 36% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A8160 PR P&ID's - Boiling & Fresh Water System MDF-PTJ-PR-PID-0003 Boiling & Fresh Water System PID 190 24% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

A8162 PI Piping G.A - Boiling & Fresh Water System MDF-PTJ-PI-LAY-0006 Boiling & Fresh Water GENERAL ARRANGEMENT 188 23% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8163 PI Isometric Drawings - Boiling & Fresh Water System MDF-PTJ-PI-ISO-0003 Boiling and Fresh Water System Isometric Drawing 138 17% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Fuel Gas System 801 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8270 PR PFD - Fuel Gas System MDF-PTJ-PR-PFD-0005 Fuel Gas System PFD 285 36% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A8280 PR P&ID's - Fuel Gas System MDF-PTJ-PR-PID-0005 Fuel Gas System PID 190 24% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

A8282 PI Piping G.A - Fuel Gas System MDF-PTJ-PI-LAY-0007 Fuel GaS GENERAL ARRANGEMENT 188 23% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8283 PI Isometric Drawings - Fuel Gas System MDF-PTJ-PI-ISO-0005 Fuel Gas System ISOMETRIC DRAWING 138 17% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Industrial Water System 1,183 1% 100% 100% 100% 100% 100% 100% 100% 100%
A8090 PR PFD - Industrial Water System MDF-PTJ-PR-PFD-0002 Industrial Water System PFD 285 24% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A8100 PR P&ID's - Industrial Water System MDF-PTJ-PR-PID-0002 Industrial Water System PID 380 32% 18-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

A8101 PI Piping G.A - Industrial Water System MDF-PTJ-PI-LAY-0008 Industrial Water GENERAL ARRANGEMENT 188 16% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8102 PI Isometric Drawings - Industrial Water System MDF-PTJ-PI-ISO-0001 Industrial Feed Water System Isometric Drawing 138 12% 23-Feb-21 16-May-21 26-May-21 02-Jun-21 09-Jun-21 14-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A8105 PR Data Sheets for Industrial Water package MDF-PTJ-PR-DAT-0005 Data Sheets for Industrial Water package 192 16% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

Waste Water & Chemical System 2,069 1% 100% 100% 100% 100% 100% 100% 100% 100%
A8330 PR PFD - Waste Water & Chemical System MDF-PTJ-PR-PFD-0006 Waste Water and chemical System PFD 285 14% 27-Sep-20 17-Oct-20 27-Oct-20 26-Nov-20 06-Dec-20 31-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

A8340 PR P&ID's - Waste Water & Chemical System MDF-PTJ-PR-PID-0006 Waste Water System PID 228 11% 14-Oct-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

A8342 PI Piping G.A - Waste Water & Chemical System MDF-PTJ-PI-LAY-0009 Waste Water and chemical GENERAL ARRANGEMENT 752 36% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8343 PI Isometric Drawings - Waste Water & Chemical System MDF-PTJ-PI-ISO-0006 Waste Water and chemical System Isometric Drawing 276 13% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8345 PR Data Sheets for Waste Water and chemical System MDF-PTJ-PR-DAT-0006 Data Sheets for Waste Water and chemical System 288 14% 21-Oct-20 12-Dec-20 22-Dec-20 29-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

PR Chemical Injection Package Process Datasheet MDF-PTJ-PR-DAT-0002 Chemical Injection Package Process Datasheet 240 12% 11-Dec-21 21-Dec-21 31-Dec-21 07-Jan-22 14-Jan-22 24-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

Chemical System 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
A8390 PFD - Chemical System Bulk Chemicals Storage & Handling PFD 0 100% 100% 100% 100% 100% 100% 100% 100%
A8400 P&ID's - Chemical System Chemical System PID 0 100% 100% 100% 100% 100% 100% 100% 100%
A8402 Piping G.A - Chemical System Chemical GENERAL ARRANGEMENT 0 100% 100% 100% 100% 100% 100% 100% 100%
A8403 Isometric Drawings - Chemical System Chemical System ISOMETRIC DRAWING 0 100% 100% 100% 100% 100% 100% 100% 100%
A8405 Data Sheets for Chemical System 0
Spark System 252 0% 100% 100% 100% 100% 100% 100% 100% 100%
PI SPARK SYSTEM-PIPING GENERAL ARRANGEMENT MDF-PTJ-PI-DWG-0001 SPARK SYSTEM-PIPING GENERAL ARRANGEMENT 252 100% 16-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 111 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Process 3,407 1% 100% 100% 100% 100% 100% 100% 100% 100%
A16010 Process -BFD for entire Plant 293 9% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-DIA-0001 Block Flow Diagram for entire Plant 293 100% 03-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Process -Philosophy (Effluent and Drianage - Isolation - line
A16020 1,152 34% 100% 100% 100% 100% 100% 100% 100% 100%
sizing - Design Temp)
PR MDF-PTJ-PR-RPT-0003 Effluent and Drianage PHILOSOPHY 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-RPT-0004 Isolation Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-RPT-0005 Line Sizing Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-RPT-0006 Design Temprature and Pressure Philosophy 278 24% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-MSR-0001 MATERIALS SELECTION PHILOSOPHY REPORT 42 4% 24-Mar-21 31-Mar-21 30-Apr-21 05-May-21 07-May-21 12-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A16030 Process -Basis of Design 225 7% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-RPT-0001 Process Basis Of Design 225 100% 09-Dec-20 08-Nov-21 08-Dec-21 13-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A16050 Equipment List 333 10% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-LST-0001 Equipment list 333 100% 22-Nov-20 27-Nov-21 07-Dec-21 14-Dec-21 21-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

Operating, Control and Safeguarding Philosophy, Procedure


A55921 815 24% 100% 100% 100% 100% 100% 100% 100% 100%
& Utility Descrip.
PR MDF-PTJ-PR-RPT-0002 Operating, Control and Safeguarding Philosophy 300 37% 03-Jan-21 06-Jun-21 16-Jun-21 23-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-RPT-0007 Utilities Description 222 27% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-PRO-0001 Operating Procedures for offsite utilities 293 36% 10-Jan-22 14-Feb-22 24-Feb-22 03-Mar-22 10-Mar-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
A55931 General (Fluid List, Legand, symbols,..) 365 11% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-LST-0003 FLUID LIST 278 76% 22-Nov-20 12-Apr-21 22-Apr-21 29-Apr-21 06-May-21 11-May-21 100% 100% 100% 100% 100% 100% 100% 100%

PR MDF-PTJ-PR-PID-0001 Legend and Symbols 88 24% 22-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A84290 MSG - Material Selection Guide 225 7% 100% 100% 100% 100% 100% 100% 100% 100%
PR MDF-PTJ-PR-MSG-0001 MSG-Material Selection Guide 225 100% 09-Dec-20 11-Mar-21 10-Apr-21 15-Apr-21 17-Apr-21 22-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Fire & Gas 3,130 1% 100% 100% 100% 100% 100% 100% 100% 100%
FG.000 F&G & Fiber Optic Cable Specifications 3,130 100% 100% 100% 100% 100% 100% 100% 100% 100%
Gas Suppression system Calculation Report For Refining
FF MDF-PTJ-LP-RPT-0022 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building - SWITCH ROOM -SR02A
Gas Suppression system Calculation Report (SR-02B
FF MDF-PTJ-LP-RPT-0023 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building)
Gas Suppression system Calculation Report For Straw
FF MDF-PTJ-LP-RPT-0024 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Preparation Building
Gas Suppression system Calculation Report For Substation
FF MDF-PTJ-LP-RPT-0025 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Building
Gas Suppression system Calculation Report For Production
FF MDF-PTJ-LP-RPT-0026 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
building
FF MDF-PTJ-LP-RPT-0027 Fire Fighting Protection Layout For Switch Room - SR01B 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-RPT-0028 Fire Fighting Protection Layout For Switch Room - SR-02C 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-RPT-0029 Fire Fighting Protection Layout For Switch Room - SR-022 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-SPC-0004 Total Flooding FM200 Gas Suppression system Spec 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-SPC-0005 Total Flooding CO2 Gas Suppression system Spec 210 7% 19-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0030 MDF UTILITIES HAZOP REPORT 210 7% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

Fire Water Network Hydraulic Calculation Report For


LP MDF-PTJ-LP-RPT-0032 200 6% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
production building
Fire Water Network Hydraulic Calculation Report For Spare
LP MDF-PTJ-LP-RPT-0033 200 6% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
Parts Store
Fire Water Network Hydraulic Calculation Report For Straw
LP MDF-PTJ-LP-RPT-0034 210 7% 01-Sep-21 12-Sep-21 17-Sep-21 22-Sep-21 27-Sep-21 07-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Preparation Building
LP MDF-PTJ-LP-RPT-0035 Dust Explosion Confinement Assessment Support Note 210 7% 01-Sep-21 12-Sep-21 17-Sep-21 22-Sep-21 27-Sep-21 07-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Piping 4,216 2% 100% 100% 100% 100% 100% 100% 100% 100%
A16040 Specifications 928 22% 100% 100% 100% 100% 100% 100% 100% 100%
Page 112 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
PI MDF-PTJ-PI-CAL-0001 Pipe Wall Thickness calculation 193 21% 03-Jan-21 06-Dec-21 07-Dec-21 14-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-SPC-0001 Piping Material Specification (PMS) 385 42% 03-Jan-21 06-Dec-21 07-Dec-21 14-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-SPC-0002 Piping Material Classes 350 38% 22-Nov-20 26-Dec-20 05-Jan-21 12-Jan-21 19-Jan-21 24-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A16060 Stress Analysis 765 18% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-SPC-0003 Stress Analysis Specifications 255 33% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LST-0001 Stress Critical Line List 255 33% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-RPT-0004 Stress Analysis Report 255 33% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A16070 Equipment Layout & Plot Plan 1,088 26% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LAY-0001 UTILITY AREA - Plot Plan 653 60% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

PI MDF-PTJ-PI-LAY-0002 Equipment layout Drawings 435 40% 07-Dec-20 14-Dec-20 24-Dec-20 31-Dec-20 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A16080 General Arrangement 835 20% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-LAY-0003 GENERAL PLOT PLAN ARRANGEMENT 435 52% 03-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

PI MDF-PTJ-PI-LAY-0011 Chemical System Piping GA 400 48% 06-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A19380 Tie - In Schedule 204 5% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-SCH-0001 Tie-In Schedule 204 100% 07-Dec-20 14-Dec-20 24-Dec-20 31-Dec-20 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

A19385 PI Line Designation Tables (LDT) MDF-PTJ-PR-LST-0002 LINE DESIGNATION TABLES (LDT) 275 7% 03-Jan-21 01-Dec-21 11-Dec-21 18-Dec-21 25-Dec-21 30-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A19390 Piping Bulk & Valves MTO (Balance) 122 3% 100% 100% 100% 100% 100% 100% 100% 100%
PI MDF-PTJ-PI-MTO-0001 Piping Bulk and valves balance MTO 122 100% 14-Nov-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

Electrical 6,538 3% 100% 100% 100% 100% 100% 100% 100% 100%
A56041 Lightning protection Lay Out 93 1% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0022 Lightning Protection Layout 93 100% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Electrical Specification (Switchgear,AC/DC UPS,


A5730 1,440 22% 100% 100% 100% 100% 100% 100% 100% 100%
Transformers / Diesel Generator)
EL MDF-PTJ-EL-SPC-0001 Medium Voltage Switchgear Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0002 0.4 Low Voltage Switchgear Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0003 distribution board Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0004 AC Uninterruptable Power Supply System Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0005 DC Uninterruptable Power Supply System Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0006 Transformers Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0007 Emergency Diesel Generator Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0008 Electrical Bulk materials Specefication 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0010 22 KV Switchgear Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0011 0.4kV System-Soft Starters and VFDs_Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0012 Reactive Power Compensation-Specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SPC-0013 Electric motors- specification 120 8% 26-Jul-20 31-Jul-20 05-Aug-20 10-Aug-20 15-Aug-20 19-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%

Electrical Datasheet for Switchgear,AC/DC UPS,


A5740 1,040 16% 100% 100% 100% 100% 100% 100% 100% 100%
Transformers / Diesel Generator
EL MDF-PTJ-EL-DAT-0001 Medium Voltage Switchgear Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0002 0.4 Low Voltage Switchgear Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0003 distribution board Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0004 AC Uninterruptable Power Supply System Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0005 DC Uninterruptable Power Supply System Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0006 Transformer Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DAT-0007 Diesel emergency generator Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
Page 113 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-DAT-0008 Reactive Power Compensation - Data Sheet 130 13% 12-Aug-20 17-Aug-20 22-Aug-20 27-Aug-20 01-Sep-20 07-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

Electrical Datasheet For machines in Owner's scope of supply


A5745 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
(As per SK Attachment 2 Pos 5)
A5750 Single Line Diagram 990 15% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-SLD-0001 Medium voltage Swichgear SLD. 285 29% 27-Jul-20 01-Aug-20 02-Dec-20 07-Dec-20 01-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0002 Main Low voltage Swichgear SLD. 480 48% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0003 Main lighing Distribution Board SLD 225 23% 19-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A7060 Lists, Calculations & Construction DWG's 2,975 46% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-LAY-0001 Outdoor lighing & Power Layout 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0002 Earthing Layout 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0003 Cable Routing Layout. 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0022 Lightning protection Layout 140 5% 05-Feb-21 19-Feb-21 05-Mar-21 19-Mar-21 02-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LST-0001 Load List 310 10% 15-Nov-21 15-Dec-21 22-Dec-21 29-Dec-21 05-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SCH-0001 Cable Schedule 260 9% 28-Nov-20 03-Dec-20 28-Dec-20 02-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SCH-0002 Cable Schedule 240 8% 19-Jan-21 24-Jan-21 18-Feb-21 23-Feb-21 20-Mar-21 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-CAL-0001 lighting Calculations 325 11% 26-Oct-20 31-Oct-20 25-Nov-20 30-Nov-20 25-Dec-20 30-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-CAL-0002 Electrical Power System Study 325 11% 01-Oct-20 06-Oct-20 20-Oct-20 25-Oct-20 01-Nov-20 06-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-CAL-0003 DC BATTERY CHARGER SIZING 325 11% 01-Oct-20 06-Oct-20 20-Oct-20 25-Oct-20 01-Nov-20 06-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0004 EARTHING SYSTEM GENERAL LAYOUT 210 7% 31-May-21 11-Jun-21 16-Jun-21 21-Jun-21 26-Jun-21 27-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0027 INSTALLATION DETAILS OF FLOOD LIGHT Layout 210 7% 30-Sep-21 11-Oct-21 16-Oct-21 21-Oct-21 26-Oct-21 27-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

Instrumentation (Control System) 8,288 4% 100% 100% 100% 100% 100% 100% 100% 100%
IN.000 Specifications & Data Sheets 3,850 46% 100% 100% 100% 100% 100% 100% 100% 100%
INSTRUMENTATION AND CONTROL BASIS OF
IN MDF-PTJ-IN-RPT-0001 175 5% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
DESIGN
ISBL AND OSBL AUTOMATION AND CONTROL
IN MDF-PTJ-IN-RPT-0002 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
INTERCONNECTION PHILOSOPHY
IN MDF-PTJ-IN-SPC-0007 INSTRUMENT INSTALLATION specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0008 DCS specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0009 Instruments Specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0010 Control Valve specs 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0011 Analyzer (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0012 Instrument with equipment package 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-SPC-0014 Instrument cable and Cable Glandes specification 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0001 Instruments (Different Type) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0002 Remotely operated Valves (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0003 Analyzer (Different types) 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0004 DATA SHEET FOR Mechanical level indicator 245 6% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0005 DATA SHEET FOR Flow meter 245 6% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0006 DATA SHEET FOR Control Valves "YIC-5150" 245 6% 04-Sep-21 09-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DAT-0007 PH analyzer data sheet 245 6% 05-Oct-21 09-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.010 I/O List & Index 525 6% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-LST-0001 INSTRUMENT INDEX List 175 33% 28-Oct-21 02-Dec-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 114 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
IN MDF-PTJ-IN-LST-0002 I/O LIST 175 33% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-LST-0003 ALARM LIST 175 33% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.020 Loop DWG's, Cable Routing & Inst. Layout. 2,219 27% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-DIA-0006 PLANT AUTOMATION SYSTEM BLOCK DIAGRAM 175 8% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DIA-0007 ICSS Functional, Loop Wiring diagram 175 8% 31-Oct-21 05-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0073 CABLE TERMINATION JUNCTION BOX 175 8% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0076 Instrument electrical hookup drawing 154 7% 16-Mar-21 21-Mar-21 15-Apr-21 20-Apr-21 15-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0077 Instrument mechanical hookup drawing 158 7% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0078 Instrument pneumatic drawing 158 7% 29-Oct-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0079 Control room cable trays 245 11% 25-Feb-21 01-Apr-21 04-Apr-21 09-Apr-21 14-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DWG-0080 Instrument junction Box support 154 7% 16-Mar-21 21-Mar-21 15-Apr-21 20-Apr-21 15-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-LAY-0023 INSTRUMENTATION / JB LAYOUT DRAWING 217 10% 01-Nov-21 26-Nov-21 01-Dec-21 11-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-LAY-0024 Instrument cable routing layout 217 10% 01-Nov-21 26-Nov-21 01-Dec-21 11-Dec-21 18-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-LAY-0026 Control Rack Room Layout 217 10% 10-Apr-21 05-May-21 10-May-21 20-May-21 27-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-DIA-0009 Schematic diagram for signals of motor 175 8% 13-Apr-21 18-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

IN.040 MTO - Control Sys. (Cable Trays, cable and cable glands) 763 9% 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-MTO-0006 Instruments Tube and tube fittings 294 39% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-MTO-0007 Instruments Stands 294 39% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-IN-MTO-0009 Instrument cable trays 175 23% 12-Oct-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

Hook Up and Procedures Activities (Precomm. , Comm. and


IN.060 231 3% 100% 100% 100% 100% 100% 100% 100% 100%
Start Up)
IN MDF-PTJ-IN-PRO-0001 Procedure for pre-commissioning /commissioning and start -up 231 100% 25-Dec-21 29-Jan-22 01-Feb-22 06-Feb-22 11-Feb-22 16-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
IN.065 Instrument Cable Schedule 406 5% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-SCH-0002 Cable Schedule 175 43% 18-Jan-21 02-Feb-21 03-Apr-21 10-Apr-21 25-Apr-21 05-May-21 100% 100% 100% 100% 100% 100% 100% 100%

IN MDF-PTJ-PR-SCH-0003 Cause and Effect 231 57% 27-Mar-21 01-May-21 04-May-21 09-May-21 14-May-21 19-May-21 100% 100% 100% 100% 100% 100% 100% 100%
IN.250 MTO - Control Sys. (JB's and bulk material) 294 4% 100% 100% 100% 100% 100% 100% 100% 100%
IN MDF-PTJ-IN-MTO-0008 Field Junction boxes 294 100% 22-Feb-21 08-Apr-21 15-Apr-21 20-Apr-21 27-Apr-21 02-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Telecommunications 4,368 2% 100% 100% 100% 100% 100% 100% 100% 100%
A8650 Fire Detection and Alarm System Cable Schedule & Plot Plan 320 7% 100% 100% 100% 100% 100% 100% 100% 100%

FIRE DETECTION AND ALARM SYSTEM FOR THE


TL MDF-PTJ-TL-LAY-0001 170 53% 07-Mar-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT PLAN
TL MDF-PTJ-TL-SCH-0001 FIRE ALARM SYSTEM CABLE SCHEDULE 150 47% 05-Nov-20 10-Nov-20 05-Dec-20 10-Dec-20 04-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8652 Fire Alarm System Specs & Block Diagram 395 9% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0001 FIRE ALARM SYSTEM RISER DIAGRAM 175 44% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-SPC-0001 FIRE ALARM SYSTEM SPECIFICATION 220 56% 13-Nov-20 18-Nov-20 13-Dec-20 18-Dec-20 12-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A8660 CCTV - Plot Plan 170 4% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0008 CCTV SYSTEM OUTDOOR PLOT PLAN 170 100% 07-Mar-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8662 CCTV Specs & Block Diagram 395 9% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-SPC-0002 CCTV SYSTEM - SPECS 220 56% 13-Nov-20 18-Nov-20 13-Dec-20 18-Dec-20 12-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DIA-0002 CCTV SYSTEM - BLOCK DIAGRAM 175 44% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A8672 Data Network Specs & Block Diagram 1,498 34% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0004 DATA NETWORK SYSTEM BLOCK DIAGRAM 175 12% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 115 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
TL MDF-PTJ-TL-SPC-0004 DATA NETWORK SYSTEM SPECS 220 15% 21-Nov-20 26-Nov-20 21-Dec-20 26-Dec-20 20-Jan-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-SPC-0005 IP telephone Specs 280 19% 02-Oct-20 07-Oct-20 01-Nov-20 06-Nov-20 01-Dec-20 26-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DIA-0005 IP Telephone block Diagram 175 12% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

Starw Preparation Building (Control Room)


TL MDF-PTJ-TL-DWG-0070 180 12% 22-Apr-21 29-Apr-21 06-May-21 13-May-21 20-May-21 27-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Data Network&IP Telephone SYSTEM Layout
TL MDF-PTJ-TL-SPC-0006 IP telephone Specs 288 19% 27-Nov-21 02-Dec-21 09-Dec-21 14-Dec-21 21-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0007 IP Telephone block Diagram 180 12% 27-Nov-21 04-Dec-21 11-Dec-21 16-Dec-21 21-Dec-21 28-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
A8680 Public Address - Plot Plan 170 4% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0012 PUBLIC ADDRESS SYSTEM OUTDOOR PLOT PLAN 170 100% 07-Mar-21 11-Apr-21 16-Apr-21 21-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8682 Public Address Specs & Block Diagram 395 9% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DIA-0003 PUBLIC ADDRESS SYSTEM BLOCK DIAGRAM 175 44% 13-Apr-21 18-May-21 23-May-21 28-May-21 02-Jun-21 07-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-SPC-0003 PUBLIC ADDRESS SYSTEM SPECS 220 56% 21-Nov-20 26-Nov-20 21-Dec-20 26-Dec-20 20-Jan-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A8683 Telecomm. - B.O.Q & MTO 1,025 23% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-MTO-0001 FIRE ALARM SYSTEM B.O.Q 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0002 CCTV SYSTEM - BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0003 PUBLIC ADDRESS SYSTEM BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0004 DATA NETWORK SYSTEM BOQ 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0005 IP Telephone MTO 170 17% 21-Mar-21 25-Apr-21 30-Apr-21 05-May-21 10-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-MTO-0006 CCTV SYSTEM - MTO 175 17% 26-May-21 30-Jun-21 05-Jul-21 10-Jul-21 15-Jul-21 20-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC System 570 0% 100% 100% 100% 100% 100% 100% 100% 100%
HVAC System Philosophy, Design Specifications & general
A16640 570 100% 100% 100% 100% 100% 100% 100% 100% 100%
Details
HV MDF-PTJ-HV-RPT-0001 HVAC System Philosophy 200 35% 16-Nov-20 21-Nov-20 16-Dec-20 21-Dec-20 15-Jan-21 30-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

HV MDF-PTJ-HV-SPC-0001 HVAC Design specifications 200 35% 16-Nov-20 21-Nov-20 16-Dec-20 21-Dec-20 15-Jan-21 30-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

HV MDF-PTJ-HV-SPC-0002 Fans spec's and data sheet 170 30% 26-Nov-21 31-Dec-21 05-Jan-22 10-Jan-22 15-Jan-22 20-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

Mechanical 1,705 1% 100% 100% 100% 100% 100% 100% 100% 100%
Mechanical - Data Sheets & Specifications (Valves, Pumps,
A16650 1,705 100% 100% 100% 100% 100% 100% 100% 100% 100%
...)
ME MDF-PTJ-ME-DAT-0002 Manual valves Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-DAT-0005 Strainers Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-DAT-0007 Pumps Data sheets 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-DAT-0008 Safety , relief valves and rupture disk data sheet. 170 10% 26-Oct-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

General Specification for Bulk Material PIPES, FITTINGS,


ME MDF-PTJ-ME-SPC-0003 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
FLANGES, BOLTS & GASKETS)
ME MDF-PTJ-ME-SPC-0004 Manual VALVES Specification 170 10% 26-Oct-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-SPC-0006 Strainer Specification 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-SPC-0008 PUMPS SPECIFICATION 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-SPC-0009 Tank Roof Seal and Drain Technical Specification 170 10% 19-Feb-21 26-Mar-21 31-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ME MDF-PTJ-ME-SPC-0010 Storm Water & Sewege Submersible Pump Stations 175 10% 26-Oct-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

Production Line Structure (incl. MDF Storage & Lab) 81,325 34% 100% 100% 100% 100% 100% 100% 100% 100%
Architectural 7,088 9% 100% 100% 100% 100% 100% 100% 100% 100%
Arch. DWGs for Production line - Warehouse for final
ST.000 3,098 44% 100% 100% 100% 100% 100% 100% 100% 100%
Product
MDF-PTJ-AR-DWG-
AR Production Line Building- Ground floor at level 1.5m 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0108
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- First Floor Level 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0109
Page 116 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-Roof Plan 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0110
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 1 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0111
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 2 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0112
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 3 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0113
MDF-PTJ-AR-DWG-
AR Buildings of Production Line-ELEVATIONS 4 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0114
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- Section A-A 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0115
MDF-PTJ-AR-DWG-
AR Buildings of Production Line- Section B-B 248 8% 16-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0116
MDF-PTJ-AR-DWG-
AR Production Line Building- finish schedule 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0117
MDF-PTJ-AR-DWG-
AR Production Line Building- Doors & Windows Schedule 218 7% 27-Sep-21 11-Nov-21 26-Nov-21 11-Dec-21 16-Dec-21 31-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0118
MDF-PTJ-AR-DWG- Production Line Building- Plumbing Works-water drainage
AR 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0119 system
MDF-PTJ-AR-DWG- Production Line Building-Plumbing Works-water supply
AR 218 7% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 27-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
0120 system
Complete architect plans for the building (As per Attach. 2.-
ST.001 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Pos 4)
ST.006 Arch. DWGs for Straw Prep. Building 1,890 27% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- Ground floor 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0180
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- WINDOW PLAN LEVEL 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0181
MDF-PTJ-AR-DWG-
AR Strew Preperation Building-Roof Plan 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0182
MDF-PTJ-AR-DWG-
AR Strew Preperation Building-North Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0183
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- East Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0184
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- West Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0185
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- South Elevation 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0186
MDF-PTJ-AR-DWG-
AR Strew Preperation Building- Section A-A 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0187
MDF-PTJ-AR-DWG-
AR Strew Preperation Building finish schedule 210 11% 16-Jul-20 30-Jul-20 13-Aug-20 27-Aug-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0189
ST.007 Arch. DWGs for Refiner Building 2,100 30% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Refining Building- Ground floor at level 1.5m 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0193
MDF-PTJ-AR-DWG-
AR Refining Building-Roof Plan 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0195
MDF-PTJ-AR-DWG-
AR Refining Building-North Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0196
MDF-PTJ-AR-DWG-
AR Refining Building- East Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0197
MDF-PTJ-AR-DWG-
AR Refining Building- West Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0198
MDF-PTJ-AR-DWG-
AR Refining Building- South Elevation 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0199
MDF-PTJ-AR-DWG-
AR Refining Building- Section A-A 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0200
MDF-PTJ-AR-DWG-
AR Refining Building- Doors & Windows and finish schedule 263 13% 06-Aug-20 20-Aug-20 03-Sep-20 17-Sep-20 01-Oct-20 19-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0202
Steel Structure 46,747 57% 100% 100% 100% 100% 100% 100% 100% 100%
ST.005 Steel Structure - Warehouse for Final Product (Plot-1) 2,103 4% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-SPC-0001 Structural design criteria 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0300 General notes 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0301 General details 111 5% 15-Jan-21 24-Feb-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0003 WAREHOUSE FOR FINAL PRODUCT- Calculation Note 480 23% 24-Aug-20 04-Sep-20 09-Sep-20 14-Sep-20 16-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

WAREHOUSE FOR FINAL PRODUCT- Layout For Base


ST MDF-PTJ-ST-DWG-0014 480 23% 24-Aug-20 04-Sep-20 09-Sep-20 14-Sep-20 16-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
Plate
Page 117 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
WAREHOUSE FOR FINAL PRODUCT- Layout Plans&
ST MDF-PTJ-ST-DWG-0015 480 23% 24-Aug-20 04-Sep-20 09-Sep-20 14-Sep-20 16-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
WAREHOUSE FOR FINAL PRODUCT- Details Of
ST MDF-PTJ-ST-DWG-0016 330 16% 09-Sep-20 14-Sep-20 20-Sep-20 25-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST.014 Steel Structure - Prod. Line Bldg. (Plot-1) 15,362 33% 100% 100% 100% 100% 100% 100% 100% 100%
Structural Steel Works for Matforming Process Structure -
ST MDF-PTJ-ST-CAL-0039 185 1% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation Note
Structural Steel Works for Matforming Process Structure -
ST MDF-PTJ-ST-DWG-0196 185 1% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout For Base Plate
Structural Steel Works for Matforming Process Structure -
ST MDF-PTJ-ST-DWG-0197 185 1% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout Plans& Elevations
Structural Steel Works for Matforming Process Structure -
ST MDF-PTJ-ST-DWG-0198 185 1% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Details Of Connections
ST MDF-PTJ-ST-CAL-0040 PIPE BRIDGE STEEL STRUCTURE - Calculation 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0202 PIPE BRIDGE STEEL STRUCTURE - Isometric View 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

PIPE BRIDGE STEEL STRUCTURE - Layout Plans&


ST MDF-PTJ-ST-DWG-0203 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
PIPE BRIDGE STEEL STRUCTURE - Details Of
ST MDF-PTJ-ST-DWG-0204 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-CAL-0041 Platform 2 Inside production Warehouse Calculations 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Platform 2 Inside production Warehouse


ST MDF-PTJ-ST-DWG-0208 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate ( Plan / Sections)
Platform 2 Inside production Warehouse
ST MDF-PTJ-ST-DWG-0209 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout for Elevations & Sections
Platform 2 Inside production Warehouse
ST MDF-PTJ-ST-DWG-0210 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Connection Details
INTERNAL PIPE SUPPORTS OF WAREHOUSE FOR
ST MDF-PTJ-ST-CAL-0042 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
FINAL PRODUCTION
Warehouse for Final Product (Internal Pipe Supports)(Plan /
ST MDF-PTJ-ST-DWG-0214 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Sections)
Warehouse for Final Product (Internal Pipe
ST MDF-PTJ-ST-DWG-0215 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Supports)(Elevations / Sections)
Structural Steel supports for Chipper 1960 - Details Of
ST MDF-PTJ-ST-DWG-0216 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-CAL-0043 St. Str. Service collector Pneumatic 5910 - Calculation Note 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
St. Str. Service collector Pneumatic 5910 - Layout For Base
ST MDF-PTJ-ST-DWG-0219 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate
St. Str. Service collector Pneumatic 5910 - Layout Plans&
ST MDF-PTJ-ST-DWG-0220 370 2% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
St. Str. Service collector Pneumatic 5910 - Details Of
ST MDF-PTJ-ST-DWG-0221 111 1% 04-Dec-20 13-Jan-21 20-Jan-21 25-Jan-21 27-Jan-21 01-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-CAL-0044 Gripper Carriage Steel Frame - Calculation Note 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0224 Gripper Carriage Steel Frame - Layout Plan 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0225 Gripper Carriage Steel Frame - Connection Details 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Structural Steel supports for Filter cyclones 5921 - Details Of


ST MDF-PTJ-ST-DWG-0226 111 1% 23-May-21 02-Jul-21 09-Jul-21 14-Jul-21 16-Jul-21 21-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-CAL-0045 Platform 1 inside Production Warehouse - Calculation Note 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Platform 1 inside Production Warehouse - Base Plate


ST MDF-PTJ-ST-DWG-0229 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Section)
Platform 1 inside Production Warehouse - Layout
ST MDF-PTJ-ST-DWG-0230 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations&Sections
Platform 1 inside Production Warehouse - Details Of
ST MDF-PTJ-ST-DWG-0231 111 1% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-CAL-0046 StStr Supporting Outlet Tube Above Fan 5910 Calculation 370 2% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST.STR SUPPORTING OUTLET TUBE FAN 5910 -


ST MDF-PTJ-ST-DWG-0234 370 2% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout For Base Plate
ST.STR SUPPORTING OUTLET TUBE FAN 5910 -
ST MDF-PTJ-ST-DWG-0235 370 2% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout For PLANS&ELEVATIONS
ST.STR SUPPORTING OUTLET TUBE FAN 5910 -
ST MDF-PTJ-ST-DWG-0236 370 2% 18-Dec-20 27-Jan-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
DETAILS OF CONNECTIONS
ST MDF-PTJ-ST-CAL-0067 Platform 3 Inside Production Warehouse Calculation Note 480 3% 25-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Platform 3 Inside Production Warehouse Base Plate
ST MDF-PTJ-ST-DWG-0298 480 3% 25-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Sections)
Page 118 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Platform 3 Inside Production Warehouse Layout for
ST MDF-PTJ-ST-DWG-0299 480 3% 25-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations & Sections
ST MDF-PTJ-ST-DWG-0302 Platform 3 Inside Production Warehouse Connection Details 480 3% 25-Mar-21 05-Apr-21 10-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0081 Platform 5 inside Production Warehouse - Calculation 480 3% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Platform 5 inside Production Warehouse Base Plate


ST MDF-PTJ-ST-DWG-0405 480 3% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Sections)
Platform 5 inside Production Warehouse Layout for
ST MDF-PTJ-ST-DWG-0406 480 3% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans,Elevations&Sections
ST MDF-PTJ-ST-DWG-0407 Platform 5 inside Production Warehouse Connection Detail 480 3% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
STEEL SUPPORT FOR ROLLER CONVEYOR BEHIND
ST MDF-PTJ-ST-CAL-0075 481 3% 05-May-21 16-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
PRESS - Calculation
STEEL STRUCTURE FOR 8' PRESS ENTRY BELT -
ST MDF-PTJ-ST-CAL-0074 481 3% 05-May-21 16-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
STEEL STRUCTURE FOR 8' PRESS ENTRY BELT - Plan,
ST MDF-PTJ-ST-DWG-0303 481 3% 05-May-21 16-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
Sections & Details
ST MDF-PTJ-ST-CAL-0071 Platform 4 inside Production Warehouse - Calculation 185 1% 17-Apr-21 27-May-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

Platform 4 inside Production Warehouse - Base Plate & Plan


ST MDF-PTJ-ST-DWG-0307 185 1% 17-Apr-21 27-May-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Section)
Platform 4 inside Production Warehouse - Layout For Plans &
ST MDF-PTJ-ST-DWG-0308 185 1% 17-Apr-21 27-May-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
Platform 4 inside Production Warehouse - Details of
ST MDF-PTJ-ST-DWG-0309 185 1% 17-Apr-21 27-May-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-DWG-0034 BURNER HOUSING STRUCTURE - Plans 190 1% 21-Jun-21 31-Jul-21 07-Aug-21 12-Aug-21 14-Aug-21 19-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0076 Steel Structure - HIT BUMPERS - Calculation 380 2% 23-May-21 02-Jul-21 09-Jul-21 14-Jul-21 16-Jul-21 21-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.015 Steel Structure - Straw Preparation (Plot-6) 1,638 4% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0009 STRAW PREPARATION - Calculation Note 390 24% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0051 STRAW PREPARATION - Base Plate (PLAN/SECTIONS) 195 12% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

STRAW PREPARATION - GA FOR ROOF PLAN


ST MDF-PTJ-ST-DWG-0052 195 12% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
(showing horizontal bracing members)
ST MDF-PTJ-ST-DWG-0058 STRAW PREPARATION - Details Of Connections 195 12% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

Straw preparation Conveyor supporting structure - Calculation


ST MDF-PTJ-ST-CAL-0012 117 7% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Note
Straw preparation Conveyor supporting structure - Layout For
ST MDF-PTJ-ST-DWG-0066 117 7% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate
Straw preparation Conveyor supporting structure - Layout
ST MDF-PTJ-ST-DTL-0054 117 7% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans& Elevations
Straw preparation Conveyor supporting structure - Details Of
ST MDF-PTJ-ST-DTL-0055 117 7% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-MTO-0001 STRAW WAREHOUSE (MTO) (Plot 6) 195 12% 17-Nov-20 27-Dec-20 03-Jan-21 08-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.340 Steel Structure - Screening area (Plot-5) 6,580 14% 100% 100% 100% 100% 100% 100% 100% 100%
STEEL STRUCTURE SCREEN AREA G.1031
ST MDF-PTJ-ST-CAL-0013 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
SIFTING + FILTER PLATFORM - Calculation Note
SIFTING & FILTER PLATFORM AND STRAW MILLING
ST MDF-PTJ-ST-DWG-0068 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
G.1031 & G.1021 - Base Plate Plan
SIFTING & FILTER PLATFORM GROUP 1031 -
ST MDF-PTJ-ST-DWG-0069 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ISOMETRIC VIEW
SIFTING & FILTER PLATFORM G.1031Details Of
ST MDF-PTJ-ST-DWG-0070 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
Steel Structure -1322 _ FILTER SFDW 05&09-D-03
ST MDF-PTJ-ST-CAL-0018 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 1322 _ Filter SFDW 05&09-D-03 Base Plate
ST MDF-PTJ-ST-DWG-0090 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan
Steel Structure - 1322 _ Filter SFDW 05&09-D-03 Plans &
ST MDF-PTJ-ST-DWG-0091 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
ST MDF-PTJ-ST-DWG-0092 Steel Structure - 1322 _ Filter SFDW 05&09-D-03 - Details 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structure - 1332 _ FILTER SFDW 05&09-D-03


ST MDF-PTJ-ST-CAL-0020 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 1332 _ FILTER SFDW 05&09-D-03 Base
ST MDF-PTJ-ST-DWG-0237 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Steel Structure - 1332 _ FILTER SFDW 05&09-D-03 Plans
ST MDF-PTJ-ST-DWG-0238 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
& Elevations
Page 119 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Steel Structure - 1332 _ FILTER SFDW 05&09-D-03 -
ST MDF-PTJ-ST-DWG-0239 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
Steel Structure - 1342 _ FILTER SFDW 05&09-D-03
ST MDF-PTJ-ST-CAL-0063 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 1342 _ FILTER SFDW 05&09-D-03 Base
ST MDF-PTJ-ST-DWG-0286 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Steel Structure - 1342 _ FILTER SFDW 05&09-D-03 Plans
ST MDF-PTJ-ST-DWG-0287 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
& Elevations
Steel Structure - 1342 _ FILTER SFDW 05&09-D-03 -
ST MDF-PTJ-ST-DWG-0288 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
Steel Structure - 1532 _ FILTER SFDW 05&09-C-01
ST MDF-PTJ-ST-CAL-0064 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 1532 _ FILTER SFDW 05&09-C-01 Base
ST MDF-PTJ-ST-DWG-0289 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Steel Structure - 1532 _ FILTER SFDW 05&09-C-01 Plans
ST MDF-PTJ-ST-DWG-0290 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
& Elevations
Steel Structure - 1532 _ FILTER SFDW 05&09-C-01 -
ST MDF-PTJ-ST-DWG-0291 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Details

STEEL STRUCTURE STRAW MILLING PIPE RACK


ST MDF-PTJ-ST-CAL-0015 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 1021 - Calculations Note

STRAW MILLING PIPE RACKS GROUP 1021


ST MDF-PTJ-ST-DWG-0062 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ISOMETRIC VIEW
STRAW MILLING PIPE RACKS GROUP 1021
ST MDF-PTJ-ST-DWG-0063 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
BASE PLAN @ EL+50 BOB
STRAW MILLING PIPE RACK G.1021
ST MDF-PTJ-ST-DWG-0064 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CONNECTION DETAILS
ST MDF-PTJ-ST-CAL-0019 Saw Dust Silo 7130 Steel Platform Cal 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0096 Saw Dust Silo 7130 Steel Platform 1 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0097 Saw Dust Silo 7130 Steel Platform 2 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0098 Saw Dust Silo 7130 Steel Platform 3 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

STEEL STRUCTURE PLATFORM TKF 1398 -Calculation


ST MDF-PTJ-ST-CAL-0017 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Note
STEEL STRUCTURE PLATFORM TKF 1398 - Plans&
ST MDF-PTJ-ST-DWG-0087 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
STEEL STRUCTURE PLATFORM TKF 1398 - Details Of
ST MDF-PTJ-ST-DWG-0088 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST MDF-PTJ-ST-DWG-0089 STEEL STRUCTURE PLATFORM TKF 1398 130 2% 05-May-21 16-May-21 21-May-21 26-May-21 31-May-21 05-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0020 Service Platform fot TKF 1398 Cal 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0100 Service Platform fot TKF 1398 -1 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Straw Preparation PNUMATIC Supports


ST MDF-PTJ-ST-DWG-0101 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout Plan
Straw Preparation PNUMATIC Supports Section Elevations
ST MDF-PTJ-ST-DWG-0102 130 2% 08-Mar-21 13-Mar-21 08-Mar-21 13-Mar-21 15-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
and Details of Connection
ST MDF-PTJ-ST-CAL-0079 Steel Structure - FILTER PLATFORMS – TYP. DESIGN 132 2% 29-May-21 03-Jun-21 29-May-21 03-Jun-21 08-Jun-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structure - 4911 FILTER SFDW 05&12-D-05


ST MDF-PTJ-ST-CAL-0065 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 4911 FILTER SFDW 05&12-D-05 Base
ST MDF-PTJ-ST-DWG-0292 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Steel Structure - 4911 FILTER SFDW 05&12-D-05 Plans &
ST MDF-PTJ-ST-DWG-0293 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
ST MDF-PTJ-ST-DWG-0294 Steel Structure - 4911 FILTER SFDW 05&12-D-05 - Details 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structure - 5911 _ FILTER SFDW 05&12-D-07


ST MDF-PTJ-ST-CAL-0066 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
Steel Structure - 5911 _ FILTER SFDW 05&12-D-07 Base
ST MDF-PTJ-ST-DWG-0295 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Steel Structure - 5911 _ FILTER SFDW 05&12-D-07
ST MDF-PTJ-ST-DWG-0296 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Isometric View & Plan
Steel Structure - 5911 _ FILTER SFDW 05&12-D-07
ST MDF-PTJ-ST-DWG-0297 130 2% 22-Mar-21 27-Mar-21 22-Mar-21 27-Mar-21 29-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Connection Details
G.1031 & G.1021 STEEL SUPPORTS - PLOT
ST MDF-PTJ-ST-CAL-0068 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
05Calculations
G.1031 & G.1021 STEEL SUPPORTS - CONNECTION
ST MDF-PTJ-ST-DWG-0400 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
DETAILS - PLOT 05
Page 120 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
G.1031 & G.1021 STEEL SUPPORT FOR FILTERS 1311
ST MDF-PTJ-ST-DWG-0401 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
&1321 - BASE PLAN AND DETAILS - PLOT 05

G.1031 & G.1021 STEEL SUPPORT FOR FILTERS 1311


ST MDF-PTJ-ST-DWG-0402 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
&1321 - PLANS AND ELEVATIONS - PLOT 05

G.1031 & G.1021 STEEL SUPPORT FOR FILTERS 1331


ST MDF-PTJ-ST-DWG-0403 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
&1341 - PLANS AND ELEVATIONS - PLOT 05

G.1031 & G.1021 STEEL SUPPORT FOR STRAW


ST MDF-PTJ-ST-DWG-0404 104 2% 08-Apr-21 13-Apr-21 08-Apr-21 13-Apr-21 15-Apr-21 20-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
PREPRATION - PLANS AND ELEVATIONS - PLOT 05

G.1031 STEEL SUPPORTS Through Scraper Conveyor 1392


ST MDF-PTJ-ST-DWG-0415 104 2% 08-May-21 13-May-21 08-May-21 13-May-21 15-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans & Elevations
ST.350 Steel Structure - Storage Bin (Plot-4) 3,520 8% 100% 100% 100% 100% 100% 100% 100% 100%
Structural Steel Works for Storage Bin
ST MDF-PTJ-ST-CAL-0021 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation Note
Structural Steel Works for Storage Bin
ST MDF-PTJ-ST-DWG-0105 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate Plan
Structural Steel Works for Storage Bin
ST MDF-PTJ-ST-DWG-0106 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans& Elevations
Structural Steel Works for Storage Bin
ST MDF-PTJ-ST-DWG-0107 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Details Of Connections
STEEL PLATFORMS FOR FILTER AREA 5091 -
ST MDF-PTJ-ST-CAL-0022 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation Note
STEEL PLATFORMS FOR FILTER AREA 5091 - Base
ST MDF-PTJ-ST-DWG-0111 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate
STEEL PLATFORMS FOR FILTER AREA 5091 - Plans&
ST MDF-PTJ-ST-DWG-0112 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
STEEL PLATFORMS FOR FILTER AREA 5091 - Details
ST MDF-PTJ-ST-DWG-0113 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Of Connections
ST MDF-PTJ-ST-CAL-0023 Steel Structure for Conveyor 1557 - Calculation Note 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0117 Steel Structure for Conveyor 1557 - Layout For Base Plate 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0118 Steel Structure for Conveyor 1557 - Layout 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0119 Steel Structure for Conveyor 1557 - Details 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0024 Steel Structures for Refinary Conveyor 1394 Calculations 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0121 Steel Structures for Refinary Conveyor 1394 Base Plate Plan 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0122 Steel Structures for Refinary Conveyor 1394 3D View 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structures for Refinary Conveyor 1394 Connection


ST MDF-PTJ-ST-DWG-0123 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
CONVEYOR 1557 END SUPPORT STRUCTURE -
ST MDF-PTJ-ST-CAL-0025 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation Note
CONVEYOR 1557 END SUPPORT STRUCTURE -
ST MDF-PTJ-ST-DWG-0125 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate Plan
CONVEYOR 1557 END SUPPORT STRUCTURE -
ST MDF-PTJ-ST-DWG-0126 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
3D View
CONVEYOR 1557 END SUPPORT STRUCTURE -
ST MDF-PTJ-ST-DWG-0127 80 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0027 Steel Structure for Refinary Conveyor Cal 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0135 Steel Structure for Refinary Conveyor -1 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0136 Steel Structure for Refinary Conveyor -2 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0137 Steel Structure for Refinary Conveyor -3 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Structural Steel Works PIPE RACK FOR PNUMATIC 4970


ST MDF-PTJ-ST-CAL-0028 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
& 5920 - Calculation Note
Structural Steel Works PIPE RACK FOR PNUMATIC 4970
ST MDF-PTJ-ST-DWG-0139 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
& 5920 - Isometric View
Structural Steel Works PIPE RACK FOR PNUMATIC 4970
ST MDF-PTJ-ST-DWG-0140 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
& 5920 - Base plate & Plan Layout
Structural Steel Works PIPE RACK FOR PNUMATIC 4970
ST MDF-PTJ-ST-DWG-0141 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
& 5920 - Connection & Details
ST MDF-PTJ-ST-CAL-0029 Ware house for Refinery Building - Calculation Note 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 121 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0143 Ware house for Refinery Building - Layout For Base Plate 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Ware house for Refinery Building - Layout Plans&


ST MDF-PTJ-ST-DWG-0144 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
ST MDF-PTJ-ST-DWG-0145 Ware house for Refinery Building - Details Of Connections 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0030 Pipe Rack For Refinary Piping Towards Start up Cyclones Cal 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0148 Pipe Rack For Refinary Piping Towards Start up Cyclones-1 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0149 Pipe Rack For Refinary Piping Towards Start up Cyclones-2 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0150 Pipe Rack For Refinary Piping Towards Start up Cyclones-3 80 2% 17-Feb-21 22-Feb-21 17-Feb-21 22-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

STEEL STRUCTURE FOR REFINARY BUILDING -


ST MDF-PTJ-ST-CAL-0078 80 2% 03-Jun-21 08-Jun-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
STEEL STRUCTURE FOR REFINARY BUILDING -
ST MDF-PTJ-ST-DWG-0020 80 2% 03-Jun-21 08-Jun-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
BASE PLATE PLAN
STEEL STRUCTURE FOR REFINARY BUILDING -
ST MDF-PTJ-ST-DWG-0025 80 2% 03-Jun-21 08-Jun-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
PLANS & ELEVATIONS
STEEL STRUCTURE FOR REFINARY BUILDING -
ST MDF-PTJ-ST-DWG-0030 80 2% 03-Jun-21 08-Jun-21 03-Jun-21 08-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
DETAILS
ST MDF-PTJ-ST-CAL-0080 PIPE RACK FROM PLOT 4 TO PLOT 5 - Calculation 80 2% 17-Apr-21 22-Apr-21 17-Apr-21 22-Apr-21 24-Apr-21 29-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0304 PIPE RACK FROM PLOT 4 TO PLOT 5 - Base Plate Plan 80 2% 17-Apr-21 22-Apr-21 17-Apr-21 22-Apr-21 24-Apr-21 29-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

PIPE RACK FROM PLOT 4 TO PLOT 5 - Elevations &


ST MDF-PTJ-ST-DWG-0305 80 2% 17-Apr-21 22-Apr-21 17-Apr-21 22-Apr-21 24-Apr-21 29-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans
ST MDF-PTJ-ST-DWG-0306 PIPE RACK FROM PLOT 4 TO PLOT 5 - Details 80 2% 17-Apr-21 22-Apr-21 17-Apr-21 22-Apr-21 24-Apr-21 29-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.360 Steel Structure - Dryer & Blending (Plot-7) 2,884 6% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0014 DRYER MIXING CHAMPER Calculations 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0074 Dryer Mixing Champer - Base Plate Plan 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0075 Dryer Mixing Champer - Isometric View 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0076 Dryer Mixing Champer - Detail 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0016 GLUE STORAGE SHED - Calculations 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0080 GLUE STORAGE SHED - Base Plate Plan 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0081 GLUE STORAGE SHED - Plans & Elevations 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0082 GLUE STORAGE SHED - Details 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0026 Steel Structure for PUMP ROOM WAREHOUSE Calculation 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structure for PUMP ROOM WAREHOUSE isometric


ST MDF-PTJ-ST-DWG-0129 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
View
Steel Structure for PUMP ROOM WAREHOUSE Plan at
ST MDF-PTJ-ST-DWG-0130 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elev & Roof Plan
Steel Structure for PUMP ROOM WAREHOUSE Connection
ST MDF-PTJ-ST-DWG-0131 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
& Details
ST MDF-PTJ-ST-CAL-0031 STEEL STRUCTURE FOR PUMP ROOM Calculation 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Service Platform Inside Pump Room Isometric View & Base


ST MDF-PTJ-ST-DWG-0153 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Plan
Service Platform Inside Pump Room BASE PLATE PLAN
ST MDF-PTJ-ST-DWG-0154 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
AT ELEV. 3770 & 6240 & 9090 T
ST MDF-PTJ-ST-DWG-0155 Service Platform Inside Pump Room Connection & Details 104 4% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Pipe Rack For Fuel GAS (2.20*28.0*8.0) Base Plate Plan &
ST MDF-PTJ-ST-DWG-0315 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Steel Plans Layout
Pipe Rack For Fuel GAS (2.20*28.0*8.0) Elevation, Side
ST MDF-PTJ-ST-DWG-0316 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
View & Connection Details
Pipe Rack For Compressed Air (2.20*20.0*8.0) Base Plate
ST MDF-PTJ-ST-DWG-0317 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan & Steel Plans Layout
Pipe Rack For Compressed Air (2.20*20.0*8.0) Connection
ST MDF-PTJ-ST-DWG-0318 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
Pipe Rack For Fuel GAS,FF,Compressed Air & Firefighting
ST MDF-PTJ-ST-DWG-0319 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Base Plate Plan & Steel Plans Layout
Page 122 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Pipe Rack For Fuel GAS,FF,Compressed Air & Firefighting
ST MDF-PTJ-ST-DWG-0320 160 6% 23-Nov-21 28-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Connection Details
STEEL SUPPORTS FOR HEATING PUMP ROOM - Base
ST MDF-PTJ-ST-DWG-0313 130 5% 08-Jul-21 13-Jul-21 18-Jul-21 23-Jul-21 28-Jul-21 02-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Plate Layout
STEEL SUPPORTS FOR HEATING PUMP ROOM - Steel
ST MDF-PTJ-ST-DWG-0314 130 5% 08-Jul-21 13-Jul-21 18-Jul-21 23-Jul-21 28-Jul-21 02-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans & Elevations
ST.370 Steel Structure - Dryer & Sifting Process (Plot-2) 9,600 21% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0033 PLATFORM FOR CYCLONE 4910 Calculations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0256 PLATFORM FOR CYCLONE 4910 Base Plate Plan 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0257 PLATFORM FOR CYCLONE 4910 Elevation for Align . F 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0258 PLATFORM FOR CYCLONE 4910 Connection and Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0034 SUPPROTING BELT 2592 G.2052 Calculations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0170 SUPPROTING BELT 2592 G.2052 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0171 SUPPROTING BELT 2592 G.2052 Plans & Elevations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0172 SUPPROTING BELT 2592 G.2052 Connection Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0049 Platform for Penumatic 4976 Cal 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0250 Platform for Penumatic 4976 - Plan At Elev 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0251 Platform for Penumatic 4976 - Plans & Elevations 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0252 Platform for Penumatic 4976 - Connection Details 160 2% 03-Feb-21 08-Feb-21 03-Feb-21 08-Feb-21 10-Feb-21 15-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Structure For Sifter & platforms above fans &


ST MDF-PTJ-ST-CAL-0036 supporting Belt 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculations
Steel Structure For Sifter & platforms above fans &
ST MDF-PTJ-ST-DWG-0179 supporting Belt 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Base plate plan
Steel Structure For Sifter & platforms above fans &
ST MDF-PTJ-ST-DWG-0180 supporting Belt 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans& Elevations
Steel Structure For Sifter & platforms above fans &
ST MDF-PTJ-ST-DWG-0181 supporting Belt 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Connection Details

ST MDF-PTJ-ST-CAL-0037 Steel Platform Above fans Sifter - G.2061 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Platform Above fans Sifter - G.2061 - ISOMETRIC


ST MDF-PTJ-ST-DWG-0185 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
VIEW
Steel Platform Above fans Sifter - G.2061 - Plans&
ST MDF-PTJ-ST-DWG-0186 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
Steel Platform Above fans Sifter - G.2061 - Connection
ST MDF-PTJ-ST-DWG-0187 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0038 Bridge 1 to Penumatic 2615 - Calculation 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0190 Bridge 1 to Penumatic 2615 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0191 Bridge 1 to Penumatic 2615 - Layout Plans& Elevations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0192 Bridge 1 to Penumatic 2615 - Details Of Connections 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0035 Service Platform 2591 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0174 Service Platform 2591 - ISOMETRIC VIEW 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0175 Service Platform 2591 - Plans& Elevations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0176 Service Platform 2591 - Connection Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0050 Dryer & Sifting Tower 2051 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0164 Dryer & Sifting Tower 2051 - Base Plate Plan 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0165 Dryer & Sifting Tower 2051 - 3D Model 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 123 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0166 Dryer & Sifting Tower 2051 - Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0032 Dryer Tower 64m Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0158 Dryer Tower 64m - Base Plate Plan 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0159 Dryer Tower 64m - 3D Model 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0160 Dryer Tower 64m - Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0056 Service Platform for Conveyor 2781 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Service Platform for Conveyor 2781 - 3D-View & Base Plate


ST MDF-PTJ-ST-DWG-0161 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Lay Out
Service Platform for Conveyor 2781 - Plan & Elevation
ST MDF-PTJ-ST-DWG-0162 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
ST MDF-PTJ-ST-DWG-0163 Service Platform for Conveyor 2781 - Connection Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0057 Steel Pipe Rack to Dryer Mixing Champer Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0167 Steel Pipe Rack to Dryer Mixing Champer - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0168 Steel Pipe Rack to Dryer Mixing Champer - Plan & Elevation 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Pipe Rack to Dryer Mixing Champer - Connection


ST MDF-PTJ-ST-DWG-0169 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0058 Steel Silo 7120 Steel Platform Calculation 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0244 Steel Silo 7120 Steel Platform - GENERAL LAYOUT 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Steel Silo 7120 Steel Platform - ANNULAR PLATE


ST MDF-PTJ-ST-DWG-0248 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ARRANGEMENT
ST MDF-PTJ-ST-DWG-0249 Steel Silo 7120 Steel Platform - HANDRAIL DETAILS 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0059 Steel Pipe Rack For Penumatic 4946 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0265 Steel Pipe Rack For Penumatic 4946 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0266 Steel Pipe Rack For Penumatic 4946 - Plan at Elev 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0267 Steel Pipe Rack For Penumatic 4946 - Connection Details 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0060 STEEL STR FOR FILTER 4911 AND 4947 Calculations 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
STEEL STR FOR FILTER 4911 AND 4947 BASE PLATE
ST MDF-PTJ-ST-DWG-0271 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN & DETAILS
STEEL STR FOR FILTER 4911 AND 4947 Plans &
ST MDF-PTJ-ST-DWG-0272 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevation
STEEL STR FOR FILTER 4911 AND 4947 - Connection
ST MDF-PTJ-ST-DWG-0273 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0061 Pipe Rack For Crude Gas Duct SENA11 Cal 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0283 Pipe Rack For Crude Gas Duct SENA11 - Isometric View 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Pipe Rack For Crude Gas Duct SENA11 - Layout Plans&


ST MDF-PTJ-ST-DWG-0284 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Elevations
Pipe Rack For Crude Gas Duct SENA11 - Details Of
ST MDF-PTJ-ST-DWG-0285 160 2% 12-Feb-21 17-Feb-21 12-Feb-21 17-Feb-21 24-Feb-21 01-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Connections
ST.380 Steel Structure - Silo area (Plot-3) 5,060 11% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0047 SILO-7110 Calculation Note 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0240 SILO-7110 GENERAL LAYOUT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0241 SILO-7110 ANNULAR PLATE ARRANGEMENT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0242 SILO-7110 HANDRAIL DETAILS 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0048 SILO-7140 - Calculation Note 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0245 SILO-7140 - GENERAL LAYOUT 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
SILO-7140 - Annular Plate, Bottom Arrangement, Shell
ST MDF-PTJ-ST-DWG-0246 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Arrangement, Roof Arrangement
Page 124 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0247 SILO-7140 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0051 Steel Drawing Filter SFDT 05/12 - D-01 Calculation 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0262 Steel Drawing Filter SFDT 05/12 - D-01 base Plate Plan 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0263 Steel Drawing Filter SFDT 05/12 - D-01 Plans& Elevation 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0264 Steel Drawing Filter SFDT 05/12 - D-01 Details 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

STEEL STRUCTURE ENERGY PLANT COMBUSTION


ST MDF-PTJ-ST-CAL-0052 AREA 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
THERMAL OIL HEATING Calculation
STEEL STRUCTURE ENERGY PLANT COMBUSTION
ST MDF-PTJ-ST-DWG-0268 AREA 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
THERMAL OIL HEATING BASE PLATE PLAN
STEEL STRUCTURE ENERGY PLANT COMBUSTION
ST MDF-PTJ-ST-DWG-0269 AREA 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
THERMAL OIL HEATING 3D-VIEW

STEEL STRUCTURE ENERGY PLANT COMBUSTION


ST MDF-PTJ-ST-DWG-0270 AREA 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
THERMAL OIL HEATING CONNECTION DETAILS

ST MDF-PTJ-ST-CAL-0053 PIPE BRIDGE STEEL STRUCTURE 2782 Calculations 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

PIPE BRIDGE STEEL STRUCTURE 2782 ISOMETRIC


ST MDF-PTJ-ST-DWG-0274 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
VIEW
PIPE BRIDGE STEEL STRUCTURE 2782 ELEVATION
ST MDF-PTJ-ST-DWG-0275 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
FOR ALIGN . B &C & D &G
PIPE BRIDGE STEEL STRUCTURE 2782 Connection &
ST MDF-PTJ-ST-DWG-0276 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
details
ST MDF-PTJ-ST-CAL-0054 Steel Platform For Penumatic 2785- Calculation Note 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0277 Steel Platform For Penumatic 2785 - Base Plate Plan 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0278 Steel Platform For Penumatic 2785 - Plans& Elevations 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0279 Steel Platform For Penumatic 2785 - Details Of Connections 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

ST ST ENERGY PLANT COMBUSTION AREA FUEL


ST MDF-PTJ-ST-CAL-0055 GAS CLEANING 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculations
ST ST ENERGY PLANT COMBUSTION AREA FUEL
ST MDF-PTJ-ST-DWG-0280 GAS CLEANING 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
BASE PLATE PLAN & DETAILS
ST ST ENERGY PLANT COMBUSTION AREA FUEL
ST MDF-PTJ-ST-DWG-0281 GAS CLEANING 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
ELEVATION FOR ALIGN. 15 , J & Q
ST ST ENERGY PLANT COMBUSTION AREA FUEL
ST MDF-PTJ-ST-DWG-0282 GAS CLEANING 160 3% 03-Mar-21 08-Mar-21 03-Mar-21 08-Mar-21 10-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
CONNECTION DETAILS

Steel Platform & Ladder for RC Structure at Energy Plan


ST MDF-PTJ-ST-DWG-0042 130 3% 21-Nov-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(typical for Two Locations) - Plan, Section & Details

Steel Handrail & Ladder for RC Structure at Dryer Mixing


ST MDF-PTJ-ST-DWG-0046 130 3% 21-Nov-21 26-Nov-21 03-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Chamber - Plan, Section & Details
Steel Structure ENERGY PLANT FUEL GAS CLEANING
ST MDF-PTJ-ST-CAL-0072 160 3% 23-Apr-21 28-Apr-21 23-Apr-21 28-Apr-21 05-May-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
SUPPORT - Calculation

ENERGY PLANT FUEL GAS CLEANING SUPPORT


ST MDF-PTJ-ST-DWG-0410 160 3% 23-Apr-21 28-Apr-21 23-Apr-21 28-Apr-21 05-May-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PLANS AND ELEVATIONS AND DETAILS
Civil 19,965 25% 100% 100% 100% 100% 100% 100% 100% 100%
Civil (Piles & FND's ) - Warehouse for Final Product &
ST.018 9,473 47% 100% 100% 100% 100% 100% 100% 100% 100%
Prod. Line Bldg. (Plot-1)
WAREHOUSE FOR FINAL PRODUCT Foundation
CI MDF-PTJ-CI-CAL-0018 260 3% 20-Dec-20 31-Dec-20 01-Jan-21 04-Jan-21 06-Jan-21 07-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
calculation sheet
WAREHOUSE FOR FINAL PRODUCT Foundation Plan &
CI MDF-PTJ-CI-DWG-0035 500 5% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
Details
CI MDF-PTJ-CI-RPT-0012 WAREHOUSE Basis Of Design 520 5% 20-Dec-20 31-Dec-20 01-Jan-21 04-Jan-21 06-Jan-21 07-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0054 WAREHOUSE PAVING PLAN AND DETAILS 520 5% 12-Feb-21 15-Feb-21 20-Feb-21 23-Feb-21 28-Feb-21 05-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 125 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
CI MDF-PTJ-CI-CAL-0019 PRODUCTION Line Foundation calculation sheet 130 1% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0037 PRODUCTION Line Piles layout 750 8% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0038 PILE LAYOUT DRWAING FOR GROUP 4021 390 4% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0039 FOUNDATION PLAN FORMWORK FOR GROUP 4021 260 3% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

FOUNDATION PLAN REINFORCEMENT FOR GROUP


CI MDF-PTJ-CI-DWG-0041 390 4% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
4021
FOUNDATION PLAN FORMWORK PART1 FOR
CI MDF-PTJ-CI-DWG-0044 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 4051
FOUNDATION PLAN FORMWORK PART2 FOR
CI MDF-PTJ-CI-DWG-0045 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 4051
FOUNDATION PLAN FORMWORK PART3 FOR
CI MDF-PTJ-CI-DWG-0046 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 4051
FOUNDATION PLAN FORMWORK PART4 FOR
CI MDF-PTJ-CI-DWG-0047 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 4051
FOUNDATION DETAILS FORMWORK PART1 FOR
CI MDF-PTJ-CI-DWG-0048 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 4051
FOUNDATION PLAN REINFORCEMENT FOR GROUP
CI MDF-PTJ-CI-DWG-0050 248 3% 07-Oct-21 06-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
4051
CI MDF-PTJ-CI-DWG-0055 FOUNDATION PLAN FORMWORK FOR GROUP 5021 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

FOUNDATION DETAILS FORMWORK FOR GROUP


CI MDF-PTJ-CI-DWG-0056 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
5021
FOUNDATION PLAN REINFORCEMENT FOR GROUP
CI MDF-PTJ-CI-DWG-0057 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
5021
FOUNDATION DETAILS REINFORCEMENT FOR
CI MDF-PTJ-CI-DWG-0058 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 5021
CI MDF-PTJ-CI-DWG-0060 FOUNDATION PLAN FORMWORK FOR GROUP 5031 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

FOUNDATION DETAILS FORMWORK FOR GROUP


CI MDF-PTJ-CI-DWG-0061 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
5031 SEC A-A
FOUNDATION DETAILS FORMWORK FOR GROUP
CI MDF-PTJ-CI-DWG-0062 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
5031 SEC B-B
CI MDF-PTJ-CI-DWG-0063 FOUNDATION PLAN Formwork FOR GROUP 5031 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

FOUNDATION DETAILS REINFORCEMENT FOR


CI MDF-PTJ-CI-DWG-0064 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 5032
CI MDF-PTJ-CI-DWG-0065 FOUNDATION PLAN FORMWORK FOR GROUP 5041 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

FOUNDATION DETAILS FORMWORK FOR GROUP


CI MDF-PTJ-CI-DWG-0066 250 3% 19-Aug-20 15-Sep-20 22-Sep-20 24-Sep-20 30-Sep-20 01-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
5041
FOUNDATION PLAN REINFORCEMENT FOR GROUP
CI MDF-PTJ-CI-DWG-0067 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
5041
FOUNDATION DETAILS REINFORCEMENT FOR
CI MDF-PTJ-CI-DWG-0068 248 3% 02-Nov-20 02-Dec-20 27-Dec-20 03-Jan-21 10-Jan-21 15-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP 5041
WAREHOUSE FOR FINAL PRODUCT FOUNDATION
CI MDF-PTJ-CI-DWG-0036 360 4% 20-Apr-21 30-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN AND DETAILS
CI MDF-PTJ-CI-DWG-0119 Foundation Above +0.00 Level - Refining Building 660 7% 29-Nov-21 02-Dec-21 07-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.020 Civil (Piles & FND's ) - Straw Preparation (Plot-6) 2,243 11% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0023 Straw preparation Platform 1 Foundation calculation sheet 163 7% 25-Feb-21 08-Mar-21 09-Mar-21 12-Mar-21 14-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0006 Straw preparation Platform 1 Piles layout (IF NEEDED) 520 23% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0069 Straw preparation Platform 1 Foundation Plan & Details 520 23% 25-Feb-21 08-Mar-21 09-Mar-21 12-Mar-21 14-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0007 Straw preparation Platform 2 Piles layout (IF NEEDED) 260 12% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0070 Straw preparation Platform 2 Foundation Plan & Details 260 12% 25-Feb-21 08-Mar-21 09-Mar-21 12-Mar-21 14-Mar-21 15-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

STRAW PREPARATION PLATFORM


CI MDF-PTJ-CI-DWG-0071 520 23% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION RFT PLAN AND DETAILS PART 1
ST.290 Civil (Piles & FND's ) - Screening area (Plot-5) 2,413 12% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0061 Foundation calculation sheet 130 5% 14-Feb-21 25-Feb-21 26-Feb-21 01-Mar-21 03-Mar-21 04-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0044 Piles layout (IF NEEDED) 520 22% 31-Jan-21 11-Feb-21 12-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0107 Foundation Plan & Details 520 22% 14-Feb-21 25-Feb-21 26-Feb-21 01-Mar-21 03-Mar-21 04-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 126 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Screening area Process Foundation REINFORCEMENTPlan
CI MDF-PTJ-CI-DWG-0073 163 7% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
& Details
CI MDF-PTJ-CI-DWG-0120 Typical Details Drawing 540 22% 29-Nov-21 02-Dec-21 07-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0121 Piles & Foundation - Foundation Reinforcement 540 22% 29-Nov-21 02-Dec-21 07-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
ST.300 Civil (Piles & FND's ) - Storage Bin (Plot-4) 1,281 6% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0033 Plot 4 - Group- 1051 - 1052 - 2031 - 3031 calculation sheet 78 6% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0016 Plot 4 - Group- 1051 - 1052 - 2031 - 3031 layout 520 41% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Plot 4 - Group- 1051 - 1052 - 2031 - 3031 Foundation Form
CI MDF-PTJ-CI-DWG-0079 520 41% 07-Feb-21 18-Feb-21 19-Feb-21 22-Feb-21 24-Feb-21 25-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Work
Structural Works for Storage Bin Platfrom 1Foundation
CI MDF-PTJ-CI-DWG-0080 163 13% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
REINFORCEMENTPlan & Details
ST.310 Civil (Piles & FND's ) - Dryer & Blending (Plot-7) 1,638 8% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0042 Foundation calculation sheet 78 5% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0025 PLOT 7 - Piles layout and Coordinates 520 32% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0088 PLOT 7 - GROUP 3031 Foundation Form Work 520 32% 24-Jan-21 04-Feb-21 05-Feb-21 08-Feb-21 10-Feb-21 11-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

PLOT 7 - GROUP 3031 FOUNDATION


CI MDF-PTJ-CI-DWG-0087 520 32% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
REINFORCEMENT Plan & Details
ST.320 Civil (Piles & FND's ) - Dryer & Sifting Process (Plot-2) 1,638 8% 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-CAL-0043 Foundation calculation sheet 78 5% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0026 Piles layout (IF NEEDED) 520 32% 03-Jan-21 14-Jan-21 15-Jan-21 18-Jan-21 20-Jan-21 21-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0089 Foundation Plan & Details 520 32% 10-Jan-21 21-Jan-21 22-Jan-21 25-Jan-21 27-Jan-21 28-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

GROUP 2150 & 2160 & 4091 AND 7140


CI MDF-PTJ-CI-DWG-0090 520 32% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION REINFORCEMENT - Plan & Details
ST.330 Civil (Piles & FND's ) - Silo area (Plot-3) 1,281 6% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0055 Foundation calculation sheet 78 6% 31-Jan-21 11-Feb-21 12-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAY-0038 Piles layout (IF NEEDED) 520 41% 17-Jan-21 28-Jan-21 29-Jan-21 01-Feb-21 03-Feb-21 04-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0101 Foundation Plan & Details 520 41% 31-Jan-21 11-Feb-21 12-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0102 Foundation REINFORCEMENT PLAN AND DETAILS 163 13% 14-Mar-21 25-Mar-21 26-Mar-21 29-Mar-21 31-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Electrical 4,730 6% 100% 100% 100% 100% 100% 100% 100% 100%
ST.120 Electrical - Prod. Line 4,730 100% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0023 Lighting and Power Layout Plan PL Building 160 3% 05-Dec-21 14-Jan-22 15-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0023 Earthing Layout PL 160 3% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0036 Electerical Distrebution Diagram PL 160 3% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0037 Emergency Distribution board SLD PL Building 160 3% 05-Dec-21 14-Jan-22 15-Jan-22 16-Jan-22 18-Jan-22 19-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR03)
EL MDF-PTJ-EL-DWG-0047 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LIGHTING LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR03)
EL MDF-PTJ-EL-DWG-0048 160 3% 26-Jul-21 09-Aug-21 20-Aug-21 03-Sep-21 15-Sep-21 28-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
SMALL POWER LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - GROUND FLOOR
EL MDF-PTJ-EL-DWG-0051 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(SR04) LIGHTING LAYOUT PLAN
FINAL PRODUCT WAREHOUSE - FIRST FLOOR (SR04)
EL MDF-PTJ-EL-DWG-0052 160 3% 26-Jul-21 09-Aug-21 20-Aug-21 03-Sep-21 15-Sep-21 28-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
SMALL POWER LAYOUT PLAN
FINAL PRODUCT WAREHOUSE(SR03) S.L.D
EL MDF-PTJ-EL-SLD-0045 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(9998MC07)
FINAL PRODUCT WAREHOUSE(SR04) S.L.D
EL MDF-PTJ-EL-SLD-0046 155 3% 23-Oct-21 06-Nov-21 17-Nov-21 01-Dec-21 13-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(9998MC08)
EL MDF-PTJ-EL-DWG-0049 Production Line Outdoor Lighting Layout - PLOT 2 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
NORMAL OUTDOOR LIGHTING DB - SINGLE LINE
EL MDF-PTJ-EL-SLD-0020 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM - P2-LDB
EL MDF-PTJ-EL-DWG-0053 Production Line Outdoor Lighting Layout - PLOT 3 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0054 Production Line Outdoor Lighting Layout - PLOT 4 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 127 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0022 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM PLOT 4
EL MDF-PTJ-EL-DWG-0055 Production Line Outdoor Lighting Layout - PLOT 5 210 4% 20-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 17-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0023 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM PLOT 5
PRODUCTION LINE OUTDOOR LAYOUT PLOT-2 -
EL MDF-PTJ-EL-DWG-0056 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
GROUP-2061
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0057 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-3
NORMAL OUTDOOR LIGHTING DB SINGLE LINE
EL MDF-PTJ-EL-SLD-0021 210 4% 31-Aug-21 11-Sep-21 16-Sep-21 21-Sep-21 26-Sep-21 27-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
DIAGRAM P3-LDB
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0058 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-04
PRODUCTION LINE OUTDOOR SOCKET LAYOUT -
EL MDF-PTJ-EL-DWG-0059 210 4% 05-Aug-21 16-Aug-21 21-Aug-21 26-Aug-21 31-Aug-21 01-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT-05
EL MDF-PTJ-EL-DWG-0060 PRODUCTION LINE OUTDOOR -LAYOUT PLOT 7 210 4% 23-Sep-21 04-Oct-21 09-Oct-21 14-Oct-21 19-Oct-21 20-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

PRODUCTION LINE OUTDOOR SOCKET LAYOUT


EL MDF-PTJ-EL-DWG-0061 210 4% 23-Sep-21 04-Oct-21 09-Oct-21 14-Oct-21 19-Oct-21 20-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
PLOT 7
EL MDF-PTJ-EL-LAY-0005 Cable Routing For Plots 210 4% 24-Oct-21 04-Nov-21 09-Nov-21 14-Nov-21 19-Nov-21 20-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

Telecommunication 1,650 2% 100% 100% 100% 100% 100% 100% 100% 100%
ST.130 Telecomm. - Prod. Line 1,650 100% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0078 Production Building & storage Fire alarm plan 165 10% 05-Nov-21 15-Dec-21 16-Dec-21 17-Dec-21 19-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0079 Production Building & storage Fire alarm cabling 165 10% 05-Nov-21 15-Dec-21 16-Dec-21 17-Dec-21 19-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0023 Production Building & storage Public adress system layout 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0066 Production Building & storage Public adress system cabling 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Production Building & storage network & IP telephone


TL MDF-PTJ-TL-LAY-0024 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
system layout
Production Building and Product Warehouse- CCTV
TL MDF-PTJ-TL-DWG-0069 330 20% 01-Mar-21 10-Apr-21 11-Apr-21 12-Apr-21 14-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM LAYOUT
HVAC 1,146 1% 100% 100% 100% 100% 100% 100% 100% 100%
ST.150 HVAC - Prod. Line 1,146 100% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG- production building - HVAC WORKS FOR Ground Floor
HV 80 7% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0013 Level
MDF-PTJ-HV-DWG- HVAC-Warehous for final proudct - Ground floor plan
HV 80 7% 05-Nov-21 15-Dec-21 16-Dec-21 17-Dec-21 19-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0014 Warehouse 1
MDF-PTJ-HV-DWG-
HV production building - HVAC WORKS FOR First Floor Level 80 7% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0016
MDF-PTJ-HV-DWG-
HV production building - HVAC WORKS FOR Roof Level 80 7% 21-Feb-21 02-Apr-21 03-Apr-21 04-Apr-21 06-Apr-21 07-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0017
MDF-PTJ-HV-DWG-
HV STRAW Building - HVAC works for Ground Floor 290 25% 19-May-21 26-May-21 02-Jun-21 09-Jun-21 16-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0027
MDF-PTJ-HV-DWG-
HV Refining - HVAC works for Ground Floor-Layout 290 25% 19-May-21 26-May-21 02-Jun-21 09-Jun-21 16-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0026
PRODUCTION BUILDING HVAC SYSTEM
HV MDF-PTJ-HV-CAL-0012 116 10% 08-Mar-21 22-Mar-21 05-Apr-21 19-Apr-21 14-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CALCULATIONS
MDF-PTJ-HV-DWG- HVAC WORKS FOR ContiRoll PRESS HALL- production
HV 130 11% 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0031 building
Architectural 945 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8550 AR Architecture General Layout MDF-PTJ-AR-LAY-0001 General Layout 285 30% 26-Oct-21 09-Nov-21 19-Nov-21 03-Dec-21 13-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

A8551 AR Production Area Layout MDF-PTJ-AR-LAY-0002 Production Area Layout 240 25% 20-Jun-20 04-Jul-20 18-Jul-20 01-Aug-20 15-Aug-20 01-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

A8552 AR General Specification for Buildings MDF-PTJ-AR-SPC-0001 General Specification for Buildings 165 17% 18-Oct-21 01-Nov-21 15-Nov-21 29-Nov-21 13-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

AR Interlock Layout MDF-PTJ-AR-LAY-0003 Interlock Layout 255 27% 15-Sep-21 29-Sep-21 13-Oct-21 27-Oct-21 10-Nov-21 25-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
Civil 730 0% 100% 100% 100% 100% 100% 100% 100% 100%
A8560 CI Soil Investigation Report MDF-PTJ-CI-RPT-0001 Soil Investigation Report 240 33% 08-Aug-20 26-Aug-20 31-Aug-20 05-Sep-20 10-Sep-20 17-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%

Civil General Details (Misc. FND. / Supports for lighting


A8561 490 67% 100% 100% 100% 100% 100% 100% 100% 100%
poles and pipe support)
CI MDF-PTJ-CI-RPT-0002 Topographical Survey Report 240 49% 17-Dec-20 27-Dec-20 06-Jan-21 16-Jan-21 26-Jan-21 05-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-LAD-0001 PORE HOLE LOCATION PLAN 250 51% 21-Jun-20 05-Jul-20 19-Jul-20 02-Aug-20 16-Aug-20 21-Aug-20 100% 100% 100% 100% 100% 100% 100% 100%
Buildings / Warehouses/ Sheds 72,828 31% 100% 100% 100% 100% 100% 100% 100% 100%
Page 128 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Buildings Specification 1,238 2% 100% 100% 100% 100% 100% 100% 100% 100%
Substation Building + (SR022-SR02C-SR02B-SR01B- Substation Building + (SR022-SR02C-SR02B-SR01B-
AR MDF-PTJ-AR-SPC-0002 180 15% 22-Oct-21 05-Nov-21 19-Nov-21 03-Dec-21 17-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
SR01A -SR02A-NEW SR) Spec SR01A -SR02A-NEW SR) Spec
AR Admin Building Spec MDF-PTJ-AR-SPC-0003 Admin Building Spec 195 16% 27-Dec-21 10-Jan-22 24-Jan-22 07-Feb-22 21-Feb-22 24-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

AR HSE Building Spec MDF-PTJ-AR-SPC-0004 HSE Building Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
(PRODUCTION BUILDING -REFINING BUILDING - (PRODUCTION BUILDING -REFINING BUILDING -
AR MDF-PTJ-AR-SPC-0005 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
GLUE STORAGE-PUMP SHED) Spec GLUE STORAGE-PUMP SHED) Spec
(SCALE CONTROL ROOM -SECURITY ROOM - (SCALE CONTROL ROOM -SECURITY ROOM -
AR MDF-PTJ-AR-SPC-0006 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
MOSQUE-GUARD TOWER) Spec MOSQUE-GUARD TOWER) Spec
AR Fence & General Layout Spec MDF-PTJ-AR-SPC-0008 Fence & General Layout Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

AR High security fence Spec MDF-PTJ-AR-SPC-0009 High security fence Spec 173 14% 14-Nov-21 28-Nov-21 12-Dec-21 26-Dec-21 09-Jan-22 12-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

Administration Building 8,191 11% 100% 100% 100% 100% 100% 100% 100% 100%
A8450 Architecture 3,218 39% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Administration Building-Ground floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
MDF-PTJ-AR-DWG-
AR Administration Building-First Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-AR-DWG-
AR Administration Building-Second Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
MDF-PTJ-AR-DWG-
AR Administration Building-Roof Floor Level 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
MDF-PTJ-AR-DWG-
AR Administration Building- Elevations 1-2 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0005
MDF-PTJ-AR-DWG-
AR Administration Building- Elevation 3-4 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-AR-DWG-
AR Administration Building- Sections A-A & Scheduals 202 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0007
MDF-PTJ-AR-DWG-
AR Administration Building- Doors & Windows Schedule 202 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0008
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Ground floor Plan
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0009 -water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Ground floor Plan
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0010 water supply system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-first floor Plan -
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0011 water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-first floor Plan -
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0012 water supply system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Second Floor Plan-
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0013 water drainage system
MDF-PTJ-AR-DWG- Administration Building- Plumbing Works-Second Floor Plan-
AR 202 6% 29-Jan-21 15-Mar-21 30-Mar-21 14-Apr-21 19-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0014 water supply system
MDF-PTJ-AR-DWG-
AR CAR PARKING SHED - ROOF PLAN 198 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0129
MDF-PTJ-AR-DWG- CAR PARKING SHED - ELEVATION 1 & 2 & SECTION
AR 198 6% 25-Nov-21 09-Jan-22 24-Jan-22 08-Feb-22 13-Feb-22 28-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0130 (A-A)
A8460 Civil & Steel Str. (for Car Shed) 2,708 33% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0001 Calculation sheet For Admin Building 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0003 Administration building - Basis of Structural Design 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0001 Administration building - Foundation Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0002 Administration building - Column and Axes Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0003 Administration building - Slab of Ground Floor 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0004 Administration building - Typical Slab Floor Plan 285 11% 10-Dec-21 24-Jan-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-CAL-0020 CAR PARKING SHEDS Foundation calculation sheet 285 11% 20-Dec-21 03-Feb-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0111 CAR PARKING SHEDS Foundation Plan & Details 285 11% 20-Dec-21 03-Feb-22 08-Feb-22 23-Feb-22 28-Feb-22 15-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0021 CAR PARKING SHEDS- Calculation Note 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0022 CAR PARKING SHEDS- Layout For Base Plate 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0023 CAR PARKING SHEDS- Layout Plans& Elevations 143 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A8465 Electrical 855 10% 100% 100% 100% 100% 100% 100% 100% 100%
Page 129 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-SLD-0005 Main Admin DB SLD 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0006 SUB Normal DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0007 SUB Emergency DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0008 UPS DB SLD Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0001 Lighting Layout Plan Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0002 Small Power Layout Admin Building 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8480 Telecomm. 855 10% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0001 ADMINISTRATION BUILDING FIRE ALARM SYSTEM 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
ADMINISTRATION BUILDING FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0002 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0019 ADMINISTRATION BUILDING CCTV 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%

ADMINISTRATION BUILDING PUBLIC ADDRESS


TL MDF-PTJ-TL-DWG-0028 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
ADMINISTRATION BUILDING PUBLIC ADDRESS
TL MDF-PTJ-TL-DWG-0029 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM CABLING
TL MDF-PTJ-TL-DWG-0047 ADMINISTRATION BUILDING NETWORK SYSTEM 143 17% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A8500 HVAC 556 7% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-ADMIN -Ground floor plan 143 26% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
MDF-PTJ-HV-DWG-
HV HVAC-ADMIN -First floor plan 143 26% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-HV-DWG-
HV HVAC-ADMIN -second floor plan 143 26% 24-Feb-21 10-Apr-21 15-Apr-21 30-Apr-21 05-May-21 20-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
ADMINISTRATION BUILDING HVAC SYSTEM
HV MDF-PTJ-HV-CAL-0001 128 23% 20-Sep-21 30-Sep-21 05-Oct-21 10-Oct-21 15-Oct-21 20-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
CALCULATIONS
Scale Room 1,468 2% 100% 100% 100% 100% 100% 100% 100% 100%
A10280 Architecture 204 14% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Scale room-Ground Level & Elevations 108 53% 01-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 01-Nov-20 09-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0033
MDF-PTJ-AR-DWG-
AR Scale room-Roof plans Level - Section - Schedule 96 47% 04-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 01-Nov-20 09-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0034
A10290 Civil 294 20% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0004 Scale room concrete calculation sheet 98 33% 08-Nov-20 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 10-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0006 Scale room - BASIS OF STRUCTURAL DESIGN 98 33% 08-Nov-20 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 10-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

Scale room ROOF SLAB AT LEVEL COLUMNS &AXIS-


CI MDF-PTJ-CI-DWG-0011 98 33% 08-Nov-20 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 10-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION PLAN & DETAILS
A10300 Electrical 255 17% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0005 Lighting Layout Plan SCL 85 33% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0006 Small Power Layout Plan SCL 85 33% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0011 Normal DB SLD Scale Control Room 85 33% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A10310 Telecomm. 510 35% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0056 SCALE ROOM FIRE ALARM SYSTEM LAYOUT 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

SCALE ROOM FIRE ALARM SYSTEM CABLING


TL MDF-PTJ-TL-DWG-0057 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
LAYOUT
TL MDF-PTJ-TL-DWG-0058 SCALE ROOM CCTV 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0059 SCALE ROOM PUBLIC ADDRESS SYSTEM 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0060 SCALE ROOM PUBLIC ADDRESS SYSTEM CABLING 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0061 SCALE ROOM NETWORK SYSTEM 85 17% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
A10330 HVAC 205 14% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0008 SCALE ROOM HVAC CALCULATIONS 120 59% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-Scale room GROUND plan Scale Room 85 41% 10-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 07-Dec-20 14-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0015
HSE Building 4,662 6% 100% 100% 100% 100% 100% 100% 100% 100%
Page 130 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A10610 Architecture 1,544 33% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR HSE Bilding-Ground floor Level 140 9% 05-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0024
MDF-PTJ-AR-DWG-
AR HSE Bilding-Roof Plan Level 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0025
MDF-PTJ-AR-DWG-
AR HSE Bilding- Elevation 1- 2 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0026
MDF-PTJ-AR-DWG-
AR HSE Bilding- Elevation 3 - 4 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0027
MDF-PTJ-AR-DWG-
AR HSE Bilding- Section A-A & B-B 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0028
MDF-PTJ-AR-DWG-
AR HSE Building-Doors & Windows finish schedule 135 9% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0029
MDF-PTJ-AR-DWG-
AR HSE Bilding- FIRST FLOOR PLAN 405 26% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0030
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-Ground floor Plan --water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0031 drainage system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-Ground floor Plan -water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0032 supply system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-First floor Plan --water
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0035 drainage system
MDF-PTJ-AR-DWG- HSE Building- Plumbing Works-First floor Plan -water supply
AR 81 5% 06-Oct-20 20-Oct-20 03-Nov-20 17-Nov-20 01-Dec-20 07-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0039 system
A10620 Civil & Steel Str. (Car Shed) 1,050 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0002 HSE BUILDING - Calculation sheet 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0004 HSE BUILDING - Basis of Structural Design 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0006 HSE BUILDING - Foundation Plan & Details 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0007 HSE BUILDING - Column and Axes 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0008 HSE BUILDING - Slab at Level 4050 & 4500 120 11% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0008 HSE Building Car Shed - Calculation Note 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0047 HSE Building Car Shed - Layout For Base Plate 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0048 HSE Building Car Shed General Arrangement for Roof Plan 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0049 HSE Building Car Shed General Arrangement for Elevations 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0050 HSE Building Car Shed Details of Connection 90 9% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 14-Feb-21 24-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A10630. Electrical 810 17% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0003 Lighting Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0004 Small Power Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0012 FIRST FLOOR Lighting Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0013 FIRST FLOOR Small Power Layout Plan HSE 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0009 MAIN DP SLD (HSE-MDP ) 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0010 FIRST FLOOR DP SLD (HSE-1ST.DP ) 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A10640 Telecomm. 810 17% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0017 HSE BUILDING FIRE ALARM SYSTEM 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0018 HSE BUILDING FIRE ALARM SYSTEM CABLING 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0027 MAIN FIRE STATION AND HSE BUILDING CCTV 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MAIN FIRE STATION AND HSE BUILDING PUBLIC
TL MDF-PTJ-TL-DWG-0044 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ADDRESS SYSTEM
MAIN FIRE STATION AND HSE BUILDING PUBLIC
TL MDF-PTJ-TL-DWG-0045 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
ADDRESS SYSTEM CABLING
MAIN FIRE STATION AND HSE BUILDING NETWORK
TL MDF-PTJ-TL-DWG-0055 135 17% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 01-Feb-21 07-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
A10660 HVAC 448 10% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0002 HSE Build HVAC CALCULATION 112 25% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 131 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-HV-DWG-
HV HVAC-HSE Building-Ground floor plan 168 38% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-HV-DWG-
HV HVAC-HSE Building-First floor plan 168 38% 09-Dec-20 23-Dec-20 06-Jan-21 20-Jan-21 03-Feb-21 10-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0007
Switch Rooms 8,691 12% 100% 100% 100% 100% 100% 100% 100% 100%
A84510 Architecture 1,080 12% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-elevations-Scheduales SR01B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0121
MDF-PTJ-AR-DWG-
AR Switch Room-GROUND - FIRST FLOOR PLAN SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0122
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS 1-2 SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0123
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS 3-4 SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0124
MDF-PTJ-AR-DWG-
AR Switch Room-SECTION A-A & SCHEDULES SR02B 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0125
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-elevations-Scheduales SR02C 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0126
MDF-PTJ-AR-DWG-
AR Switch Room-Plan-section-Scheduales SR022 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0127
MDF-PTJ-AR-DWG-
AR Switch Room-ELEVATIONS SR022 135 13% 18-Feb-21 04-Mar-21 18-Mar-21 01-Apr-21 15-Apr-21 21-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0128
Civil 1,650 19% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0072 Switch room - SR01A - Columns and Axis Roof Slab 275 17% 08-Jun-21 23-Jul-21 07-Aug-21 22-Aug-21 27-Aug-21 11-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0114 Switch room SR02C - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0115 Switch room SR022 - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0116 Switch room SR02B - Plans & Details 275 17% 08-Jul-21 22-Aug-21 06-Sep-21 21-Sep-21 26-Sep-21 11-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0117 Switch room SR02A - Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0118 Switch room SR01B- Plans & Details 275 17% 03-Aug-21 17-Sep-21 02-Oct-21 17-Oct-21 22-Oct-21 06-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
TELECOME 90 1% 100% 100% 100% 100% 100% 100% 100% 100%
Switch Room SR02B Data Network & IP Telephone system
TL MDF-PTJ-TL-DWG-0071 90 100% 22-Apr-21 29-Apr-21 06-May-21 13-May-21 20-May-21 27-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
HVAC 1,400 16% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0013 SR01B - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

HV MDF-PTJ-HV-CAL-0014 SR02B - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

HV MDF-PTJ-HV-CAL-0015 SR02C - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

HV MDF-PTJ-HV-CAL-0016 SR022 - HVAC SYSTEM CALCULATIONS 140 10% 25-Apr-21 09-May-21 21-May-21 04-Jun-21 14-Jun-21 22-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

SR02A - HVAC SYSTEM CALCULATION - Refining


HV MDF-PTJ-HV-CAL-0017 140 10% 11-May-21 25-May-21 06-Jun-21 20-Jun-21 30-Jun-21 08-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Switch Room
SR01A - HVAC SYSTEM CALCULATION - STRAW
HV MDF-PTJ-HV-CAL-0018 140 10% 11-May-21 25-May-21 06-Jun-21 20-Jun-21 30-Jun-21 08-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Switch room
MDF-PTJ-HV-DWG-
HV SWITCHROOM SR01B - Ground Floor Plan 140 10% 04-May-21 18-May-21 30-May-21 13-Jun-21 23-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
0022
MDF-PTJ-HV-DWG-
HV SWITCHROOM SR02B - Ground and 1st Floor Plan 140 10% 04-May-21 18-May-21 30-May-21 13-Jun-21 23-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
0023
MDF-PTJ-HV-DWG-
HV SWITCHROOM SR02C - Ground Floor Plan 140 10% 04-May-21 18-May-21 30-May-21 13-Jun-21 23-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
0024
MDF-PTJ-HV-DWG-
HV SWITCHROOM SR022 - Ground Floor Plan 140 10% 04-May-21 18-May-21 30-May-21 13-Jun-21 23-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
0025
STEEL Structure 441 5% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0073 GENERATOR SHED SR02B 147 33% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0150 GENERATOR SHED SR02C 147 33% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0151 GENERATOR SHED SR022 147 33% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Electerical 4,030 46% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0028 SWITCH ROOM (SR01A) - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0029 Strew Preparation Building(SR01A) - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0030 SR01A - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 132 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-SLD-0039 SR01A - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0031 SR01B - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0032 SR01B - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0033 SR01B - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0040 SR01B - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0034 SR02A - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0035 SR02A - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0036 SR02A - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0047 SR02A - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0037 SR02B - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0038 SR02B - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0039 SR02B - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0042 SR02B - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0040 SR02C - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0041 SR02C - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0042 SR02C - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0043 SR02C - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0043 SR022 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0044 SR022 - Lighting layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0045 SR022 - Small power layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0044 SR022 - Switch room S.L.D 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0046 SR03 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0050 SR04 - Electrical equipment layout 155 4% 01-Jun-21 15-Jun-21 26-Jun-21 10-Jul-21 22-Jul-21 04-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

NEW SWITCH ROOM 1,808 2% 100% 100% 100% 100% 100% 100% 100% 100%
A84510 Architecture 270 15% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR New Switch Room Plan-section-Scheduales 135 50% 31-Mar-21 14-Apr-21 28-Apr-21 12-May-21 26-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0049
MDF-PTJ-AR-DWG-
AR New Switch Room ELEVATIONS 135 50% 31-Mar-21 14-Apr-21 28-Apr-21 12-May-21 26-May-21 01-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0060
STEEL Structure 610 34% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0070 NEW SWITCH ROOM - Steel Structure Calculation 210 34% 16-Nov-21 26-Nov-21 03-Dec-21 13-Dec-21 20-Dec-21 25-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

NEW SWITCH ROOM - Generator Shed Room


ST MDF-PTJ-ST-DWG-0321 190 31% 17-Nov-21 27-Nov-21 04-Dec-21 14-Dec-21 21-Dec-21 26-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Sections)
NEW SWITCH ROOM - Sectional Side View & Connection
ST MDF-PTJ-ST-DWG-0322 210 34% 16-Nov-21 26-Nov-21 03-Dec-21 13-Dec-21 20-Dec-21 25-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
CIVIL 155 9% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0122 NEW SWITCH ROOM - PLANS AND DETAILS 155 100% 20-Oct-21 03-Nov-21 14-Nov-21 28-Nov-21 10-Dec-21 23-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Electerical 465 26% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0024 New Switch Room - Lighting Layout 155 33% 20-Apr-21 04-May-21 15-May-21 29-May-21 10-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0025 New Switch Room - Small Power Layout Plan 155 33% 20-Apr-21 04-May-21 15-May-21 29-May-21 10-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0038 New Switch Room - SLD 155 33% 20-Apr-21 04-May-21 15-May-21 29-May-21 10-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC 308 17% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0019 NEW SWITCHROOM -HVAC SYSTEM CALCULATIONS 140 45% 25-May-21 08-Jun-21 20-Jun-21 04-Jul-21 14-Jul-21 22-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 133 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-HV-DWG- NEW SWITCH ROOM - HVAC works -Ground Floor-
HV 168 55% 25-May-21 08-Jun-21 20-Jun-21 04-Jul-21 14-Jul-21 22-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
0029 Layout
PUMP ROOM WAREHOUSE 675 1% 100% 100% 100% 100% 100% 100% 100% 100%
A84510 Architecture 675 100% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR PUMP ROOM WAREHOUSE - Ground Floor- Roof Floor 135 20% 23-Mar-21 06-Apr-21 20-Apr-21 04-May-21 18-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0020
MDF-PTJ-AR-DWG-
AR PUMP ROOM WAREHOUSE - ELEVATION 1 135 20% 23-Mar-21 06-Apr-21 20-Apr-21 04-May-21 18-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0021
MDF-PTJ-AR-DWG-
AR PUMP ROOM WAREHOUSE - ELEVATION 2-4 135 20% 23-Mar-21 06-Apr-21 20-Apr-21 04-May-21 18-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0022
MDF-PTJ-AR-DWG-
AR PUMP ROOM WAREHOUSE - ELEVATION 3 135 20% 23-Mar-21 06-Apr-21 20-Apr-21 04-May-21 18-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0023
MDF-PTJ-AR-DWG- PUMP ROOM WAREHOUSE - SECTION A-A &
AR 135 20% 23-Mar-21 06-Apr-21 20-Apr-21 04-May-21 18-May-21 24-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0044 SCHEDULES
Main Security Room 2,172 3% 100% 100% 100% 100% 100% 100% 100% 100%
A10500 Architecture 542 25% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR MAIN SECURITY ROOM-Ground plan 126 23% 05-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0147
MDF-PTJ-AR-DWG-
AR MAIN SECURITY ROOM- Elevations 114 21% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0149
MDF-PTJ-AR-DWG- MAIN SECURITY ROOM- Roof plan Level -Sections-
AR 114 21% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0151 Schdules
MDF-PTJ-AR-DWG-
AR MAIN SECURITY ROOM- Ground Floor Drainage 92 17% 01-Nov-20 11-Nov-20 18-Nov-20 28-Nov-20 05-Dec-20 15-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0178
MDF-PTJ-AR-DWG-
AR MAIN SECURITY ROOM - Ground Floor Water Supply 96 18% 02-Nov-20 12-Nov-20 19-Nov-20 29-Nov-20 06-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0179
A10510 Civil 180 8% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0003 MAIN SECURITY ROOM calculation sheet 60 33% 25-Nov-20 09-Dec-20 21-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0005 MAIN SECURITY ROOM Basis of Structural Design 60 33% 25-Nov-20 09-Dec-20 21-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

MAIN SECURITY ROOM Roof slab at Level Columns &


CI MDF-PTJ-CI-DWG-0110 60 33% 25-Nov-20 09-Dec-20 21-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Axis - Foundation Plan & Details
A10520 Electrical 280 13% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0026 Lighting and mall power Layout Plan MAIN SEC ROOM 140 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0041 Lighting DP SLD MAIN SEC ROOM 140 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A10530 Telecomm. 890 41% 100% 100% 100% 100% 100% 100% 100% 100%
MAIN SECURITY ROOM FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0015 190 21% 01-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
LAYOUT
MAIN SECURITY ROOM FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0016 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING LAYOUT
TL MDF-PTJ-TL-DWG-0026 MAIN SECURITY ROOM CCTV LAYOUT 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

MAIN SECURITY ROOM PUBLIC ADDRESS SYSTEM


TL MDF-PTJ-TL-DWG-0042 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
LAYOUT
MAIN SECURITY ROOM PUBLIC ADDRESS SYSTEM
TL MDF-PTJ-TL-DWG-0043 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING LAYOUT
MAIN SECURITY ROOM DATA & IP TELEPHONE
TL MDF-PTJ-TL-DWG-0054 140 16% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
LAYOUT
A10550 HVAC 280 13% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC- Security Office- plan - MAIN SECURITY ROOM 140 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0012
HVAC SYSTEM CALCULATIONS MAIN SECURITY
HV MDF-PTJ-HV-CAL-0006 140 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 13-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
ROOM
Security Room 2,591 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9730 Architecture 506 20% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Security Room-Ground Level 126 25% 05-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0036
MDF-PTJ-AR-DWG-
AR Security Room-Roof plan Level - Sections - Schedules 114 23% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0037
MDF-PTJ-AR-DWG-
AR Security Room-Elevations 114 23% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0038
MDF-PTJ-AR-DWG-
AR Security Room- Plumbing Works-water drainage system 76 15% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0040
MDF-PTJ-AR-DWG-
AR Security Room- Plumbing Works-water supply system 76 15% 07-Oct-20 17-Oct-20 24-Oct-20 03-Nov-20 10-Nov-20 15-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%
0041
A9740 Civil 225 9% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0005 Security BUILDING calculation sheet 75 33% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0007 Security BUILDING Basis of Structural Design 75 33% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 134 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
Security BUILDING Roof slab at Level (3450) Columns &
CI MDF-PTJ-CI-DWG-0012 75 33% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 10-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
Axis - Foundation Plan & Details
A9750 Electrical 310 12% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0007 Lighting and mall power Layout Plan SEC Building 155 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0013 Lighting DP SLD SEC Building 155 50% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A9760 Telecomm. 930 36% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0002 Security Room Fire Alarm system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0003 Security Room Fire Alarm system Cabling Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0009 Security Room CCTV system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0014 Security Room Public Address system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0015 Security Room Public Address system Cabling Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0020 Security Room Data Network & IP Telephone system Layout 155 17% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A9780 HVAC 620 24% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV Security Room - Ground Floor Plan-Layout 155 25% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0011
HV MDF-PTJ-HV-CAL-0005 Security Room - HVAC SYSTEM CALCULATIONS 465 75% 16-Nov-20 30-Nov-20 12-Dec-20 26-Dec-20 05-Jan-21 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

Mosque 2,840 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9840 Architecture 1,020 36% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR MOSQUE - Ground floor Level 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0073
MDF-PTJ-AR-DWG-
AR MOSQUE - Roof Plan Level 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0074
MDF-PTJ-AR-DWG-
AR MOSQUE - Elevations 1&3 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0075
MDF-PTJ-AR-DWG-
AR MOSQUE - Elevations 2&4 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0076
MDF-PTJ-AR-DWG-
AR MOSQUE - Sections & schedule 170 17% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0077
MDF-PTJ-AR-DWG- MOSQUE - Plumbing Works-Ground floor Plan --water
AR 85 8% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0079 drainage system
MDF-PTJ-AR-DWG- MOSQUE - Plumbing Works-Ground floor Plan -water
AR 85 8% 04-Nov-20 11-Nov-20 19-Nov-20 26-Nov-20 05-Dec-20 13-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0080 supply system
A9850 Civil 700 25% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0011 MOSQUE building (MOSQUE) calculation sheet 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

MOSQUE building (MOSQUE) BASIS OF STRUCTURAL


CI MDF-PTJ-CI-RPT-0011 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
DESIGN
MOSQUE building (MOSQUE) FOUNDATION PLAN
CI MDF-PTJ-CI-DWG-0024 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
AND DETAILS
CI MDF-PTJ-CI-DWG-0025 MOSQUE building (MOSQUE) COLUMNS AND AXIS 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

MOSQUE building (MOSQUE) ROOF SLAB DETAILS AT


CI MDF-PTJ-CI-DWG-0026 140 20% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 01-Feb-21 08-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
LEVEL (+3600 & +4300)
A9860 Electrical 480 17% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0017 Lighting Layout Plan MOS 160 33% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0018 Small Power Layout Plan MOS 160 33% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0028 Normal DB SLD MOS 160 33% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A9870 Telecomm. (Public Address) 320 11% 100% 100% 100% 100% 100% 100% 100% 100%
MOSQUE BUILDING PUBLIC ADDRESS SYSTEM
TL MDF-PTJ-TL-LAY-0013 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN
MOSQUE BUILDING PUBLIC ADDRESS SYSTEM
TL MDF-PTJ-TL-DWG-0046 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
A9890 HVAC 320 11% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0011 MOSQUE HVAC SYSTEM CALCULATIONS 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-MOSQUE-Ground floor plan 160 50% 14-Dec-20 28-Dec-20 08-Jan-21 22-Jan-21 03-Feb-21 16-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
0019
Permanent TCF 3,108 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9950 Architecture 882 28% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Ground plans 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0065
Page 135 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Roof plans 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0066
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Elevations 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0067
MDF-PTJ-AR-DWG-
AR Permanent TCF BUILDING - Sections A-A 147 17% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0068
MDF-PTJ-AR-DWG- Permanent TCF BUILDING -Doors & Windows finish
AR 84 10% 14-Nov-20 21-Nov-20 28-Nov-20 05-Dec-20 12-Dec-20 15-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0069 schedule
MDF-PTJ-AR-DWG- Permanent TCF BUILDING - Plumbing Works--water
AR 105 12% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0071 drainage system
MDF-PTJ-AR-DWG- Permanent TCF BUILDING - Plumbing Works-water supply
AR 105 12% 04-Aug-20 11-Aug-20 18-Aug-20 25-Aug-20 01-Sep-20 13-Sep-20 100% 100% 100% 100% 100% 100% 100% 100%
0072 system
A9952 CI Civil MDF-PTJ-CI-DWG-0009 Permanent TCF BUILDING Paving Details 120 4% 23-Sep-20 28-Sep-20 03-Oct-20 08-Oct-20 13-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9955 Electrical 870 28% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0015 LIGHTING Layout Plan TCF 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0016 SMALL POWER Layout Plan TCF 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0024 MDP SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0025 PDP SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0026 air condition DP (ACDP) SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0027 lighting DP (LDP) SINGLE LINE DIAGRAM 145 17% 31-Jul-20 14-Aug-20 28-Aug-20 11-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9960 Telecomm. 900 29% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-LAY-0006 TCF office Fire Alarm system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0007 TCF office Fire Alarm system Cabling Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0011 TCF office CCTV system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0018 TCF office Public Address system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0019 TCF office Public Address system Cabling Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-LAY-0022 TCF office Data Network & IP Telephone system Layout 150 17% 05-Sep-20 10-Sep-20 15-Sep-20 20-Sep-20 25-Sep-20 05-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
A9970 HVAC 336 11% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0010 HVAC SYSTEM CALCULATIONS - TCF 168 50% 20-Sep-20 25-Sep-20 30-Sep-20 05-Oct-20 10-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%

MDF-PTJ-HV-DWG-
HV HVAC-TCF Building-Ground floor plan 168 50% 20-Sep-20 25-Sep-20 30-Sep-20 05-Oct-20 10-Oct-20 18-Oct-20 100% 100% 100% 100% 100% 100% 100% 100%
0018
Fence , Guard towers & Gates 2,033 3% 100% 100% 100% 100% 100% 100% 100% 100%
A10060 Architecture 1,285 63% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR FENCE -Plans &Section A-A 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0042
MDF-PTJ-AR-DWG-
AR FENCE - Elevations 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0043
MDF-PTJ-AR-DWG-
AR Guard Towers-Plans 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0045
MDF-PTJ-AR-DWG-
AR Guard Towers - Elevations - Sections 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0046
MDF-PTJ-AR-DWG-
AR Guard Towers - Elevations 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0047
MDF-PTJ-AR-DWG-
AR Guard Towers - Roof Plan & Schedules 160 12% 04-Nov-20 11-Nov-20 22-Nov-20 29-Nov-20 10-Dec-20 16-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%
0048
MDF-PTJ-AR-DWG-
AR TYPICAL Gate -Plan - Elevation - Section 325 25% 19-Jan-21 21-Nov-21 01-Dec-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
0152
A10070 Civil 618 30% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0006 RC FENCE calculation sheet 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0013 FENCE FOUNDATION PLAN AND DETAILS 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-CAL-0008 GUARD TOWER calculation sheet 130 21% 17-Dec-20 22-Dec-20 27-Dec-20 01-Jan-21 07-Jan-21 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0015 GUARD TOWER - Foundation Plan and Details 163 26% 19-Jan-21 06-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 04-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0030 GATES - Foundation Plan & Details 65 11% 19-Jan-21 06-Dec-21 16-Dec-21 23-Dec-21 30-Dec-21 04-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
A10075 Electrical 130 6% 100% 100% 100% 100% 100% 100% 100% 100%
Page 136 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
EL MDF-PTJ-EL-DWG-0008 Lighting and Small power Layout Plan Guard Tower 65 50% 19-Jan-21 02-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0014 Normal DB SLD Guard Tower 65 50% 19-Jan-21 02-Apr-21 12-Apr-21 19-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%
Substation Building 6,985 10% 100% 100% 100% 100% 100% 100% 100% 100%
A10170 Architecture 1,575 23% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Ground floor Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0050
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-First floor Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0051
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING- Roof Plan Level 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0052
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Elevations 1 & 2 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0053
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Elevations 3 & 4 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0054
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Section A-A 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0055
MDF-PTJ-AR-DWG-
AR SUBSTATION BUILDING-Doors & Windows Schedule 225 14% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
0057
A10180 Civil 1,350 19% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0009 SUBSTATION BUILDING calculation sheet 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-RPT-0009 SUBSTATION BUILDING - Basis of Structural Design 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0016 SUBSTATION BUILDING - Foundation Plan & Details 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0017 SUBSTATION BUILDING - Column and Axes 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0018 SUBSTATION BUILDING - Slab at Level 2250 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0019 SUBSTATION BUILDING - Slab at Level 8250 225 17% 18-Dec-20 23-Dec-20 28-Dec-20 02-Jan-21 07-Jan-21 14-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A10190 Electrical 1,450 21% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0009 Electrical Equipment layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0010 Lighting Layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0011 Small Power Layout Plan SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0016 Main Normal DB SLD SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0018 Main Emergency DB SLD SS1 290 20% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
A10200 Telecomm. 1,740 25% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0005 SUBSTATION BUILDING FIRE ALARM SYSTEM 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

SUBSTATION BUILDING FIRE ALARM SYSTEM


TL MDF-PTJ-TL-DWG-0006 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0021 SUBSTATION BUILDING CCTV 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0032 SUBSTATION BUILDING PUBLIC ADDRESS SYSTEM 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

SUBSTATION BUILDING PUBLIC ADDRESS SYSTEM


TL MDF-PTJ-TL-DWG-0033 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
SUBSTATION BUILDING NETWORK & IP telephone
TL MDF-PTJ-TL-DWG-0049 290 17% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
system layout
A10220 HVAC 870 12% 100% 100% 100% 100% 100% 100% 100% 100%
HV MDF-PTJ-HV-CAL-0004 HVAC SYSTEM CALCULATIONS SS1 290 33% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG-
HV HVAC-Gis Substation-Ground floor plan SS1 290 33% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0008
MDF-PTJ-HV-DWG-
HV HVAC-Gis Substation- Roof Plan 290 33% 19-Jan-21 25-Mar-21 26-Mar-21 02-Apr-21 03-Apr-21 08-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0010
Glue Storage Shed 1,415 2% 100% 100% 100% 100% 100% 100% 100% 100%
A84560 Architecture 1,125 80% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Glue Storage - Ground Floor- Roof Floor 225 20% 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 07-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0015
MDF-PTJ-AR-DWG-
AR Glue Storage - ELEVATION 1 225 20% 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 07-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0016
MDF-PTJ-AR-DWG-
AR Glue Storage - ELEVATION 2-4 225 20% 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 07-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0017
Page 137 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG-
AR Glue Storage - ELEVATION 3 225 20% 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 07-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0018
MDF-PTJ-AR-DWG-
AR Glue Storage - SECTION A-A & SCHEDULES 225 20% 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 07-Apr-21 14-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0019
HVAC 290 20% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-HV-DWG- GLUE STORAGE SHED - HVAC works for Ground Floor-
HV 290 100% 19-May-21 26-May-21 02-Jun-21 09-Jun-21 16-Jun-21 23-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0028 Layout
Liquid Chemical Warehouse 2,466 3% 100% 100% 100% 100% 100% 100% 100% 100%
A10390 Architecture 590 24% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Liquid Chemical Warehouse - Ground Floor Level 118 20% 11-Jan-21 15-Mar-21 22-Mar-21 01-Apr-21 08-Apr-21 13-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0081
MDF-PTJ-AR-DWG-
AR Liquid Chemical Warehouse - Roof Plan Level 118 20% 11-Jan-21 15-Mar-21 22-Mar-21 01-Apr-21 08-Apr-21 13-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0083
MDF-PTJ-AR-DWG-
AR Liquid Chemical Warehouse - Elevations 2 & 3 118 20% 11-Jan-21 15-Mar-21 22-Mar-21 01-Apr-21 08-Apr-21 13-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0084
MDF-PTJ-AR-DWG-
AR Liquid Chemical Warehouse - Elevations 1 & 4 118 20% 11-Jan-21 15-Mar-21 22-Mar-21 01-Apr-21 08-Apr-21 13-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0085
MDF-PTJ-AR-DWG-
AR Liquid Chemical Warehouse - Section A-A 118 20% 11-Jan-21 15-Mar-21 22-Mar-21 01-Apr-21 08-Apr-21 13-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0086
A10400 Civil & Steel Str 928 38% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0012 LIQUID CHEMICAL WAREHOUSE calculation sheet 116 13% 19-Sep-21 21-Nov-21 28-Nov-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

LIQUID CHEMICAL WAREHOUSE - Foundation Plan &


CI MDF-PTJ-CI-DWG-0027 116 13% 19-Sep-21 21-Nov-21 28-Nov-21 08-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
Details
ST MDF-PTJ-ST-CAL-0062 Liquid Chemical Shed - Steel Calculations 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0001 Liquid Chemical Shed - Steel Base Plate Plan 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Liquid Chemical Shed - Steel Arrangement of Roof Struts &


ST MDF-PTJ-ST-DWG-0002 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
HZ Bracing
ST MDF-PTJ-ST-DWG-0003 Liquid Chemical Shed - Steel Roof Purlins 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Liquid Chemical Shed - Steel Arrangement Elevations & Side


ST MDF-PTJ-ST-DTL-0001 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
View
ST MDF-PTJ-ST-DTL-0002 Liquid Chemical Shed - Details & Connections 116 13% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A10410 Electrical 232 9% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0019 LIQUID CHEMICAL SHED LIGHTING LAYOUT 116 50% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0030 LIQUID CHEMICAL SHED SLD 116 50% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
A10420 Telecomm. 716 29% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0072 Liquid Chemical Storage FIRE ALARM SYSTEM 200 28% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Liquid Chemical Storage FIRE ALARM SYSTEM


TL MDF-PTJ-TL-DWG-0073 200 28% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0074 Liquid Chemical Storage CCTV 200 28% 11-Feb-21 15-Apr-21 22-Apr-21 02-May-21 09-May-21 14-May-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0075 Liquid Chemical Storage PUBLIC ADDRESS SYSTEM 116 16% 21-May-21 25-Jun-21 30-Jun-21 05-Jul-21 10-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

Fire Foam/Water spray System Layout - Liquid chemical


A10430 Fire Fighting 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
warehouse
A10440 HVAC 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
Workshop & Spare parts Warehouse 7,325 10% 100% 100% 100% 100% 100% 100% 100% 100%
A9620 Architecture 1,710 23% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG- Workshop & Spare PartsWarehouse Building - Ground floor
AR 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0089 at level
MDF-PTJ-AR-DWG-
AR Workshop & Spare PartsWarehouse Building - Window level 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0090
MDF-PTJ-AR-DWG- Workshop & Spare PartsWarehouse Building - Roof plan
AR 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0091 level
MDF-PTJ-AR-DWG-
AR Workshop & Spare PartsWarehouse Building - Elevation 1 - 2 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0092
MDF-PTJ-AR-DWG-
AR Workshop & Spare PartsWarehouse Building - Elevation 3 - 4 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0093
MDF-PTJ-AR-DWG-
AR Workshop & Spare PartsWarehouse Building - Section A-A 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0094
MDF-PTJ-AR-DWG- Workshop & Spare PartsWarehouse Building - Doors &
AR 180 11% 14-Mar-21 28-Mar-21 11-Apr-21 25-Apr-21 09-May-21 13-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0096 Windows Schedule
MDF-PTJ-AR-DWG- Workshop & Spare PartsWarehouse Building - Plumbing
AR 90 5% 27-Oct-21 10-Nov-21 24-Nov-21 08-Dec-21 22-Dec-21 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0097 Works-Ground floor Plan -water drainage system
MDF-PTJ-AR-DWG- Workshop & Spare PartsWarehouse Building - Plumbing
AR 90 5% 27-Oct-21 10-Nov-21 24-Nov-21 08-Dec-21 22-Dec-21 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0098 Works-Ground floor Plan -water supply system
Page 138 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG- SPARE PARTS WAREHOUSE Ground Floor Level &
AR 135 8% 22-Mar-21 05-Apr-21 19-Apr-21 03-May-21 17-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0058 SCHEDULES
MDF-PTJ-AR-DWG-
AR SPARE PARTS WAREHOUSEELEVATIONS &SECTION 135 8% 22-Mar-21 05-Apr-21 19-Apr-21 03-May-21 17-May-21 23-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0059
A9630 Civil & Steel Str. 2,480 34% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0013 Workshop. & Spare Parts Warehouse calculation sheet 125 5% 08-Dec-21 22-Dec-21 05-Jan-22 19-Jan-22 02-Feb-22 10-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

Workshop. & Spare Parts Warehouse - Foundation Plan &


CI MDF-PTJ-CI-DWG-0028 125 5% 08-Dec-21 22-Dec-21 05-Jan-22 19-Jan-22 02-Feb-22 10-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
Details
Workshop & Spare Parts Warehouse Structural steel
ST MDF-PTJ-ST-CAL-0001 125 5% 23-Jun-21 28-Jun-21 23-Jun-21 28-Jun-21 30-Jun-21 05-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
calculations report
Workshop & Spare Parts Warehouse Steel BASE PLATE
ST MDF-PTJ-ST-DWG-0005 125 5% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN
Workshop & Spare Parts Warehousel Steel ROOF
ST MDF-PTJ-ST-DWG-0006 125 5% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
FRAMING PLAN

Workshop & Spare Parts Warehouse Steel ROOF FRAMING


ST MDF-PTJ-ST-DWG-0007 125 5% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
PLAN ARRANGMENT OF HZ BRACING

Workshop & Spare Parts Warehouse Steel PLAN FOR


ST MDF-PTJ-ST-DWG-0008 125 5% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
CRANE TRACK GIRDER @ E23.750+
ST MDF-PTJ-ST-DTL-0004 Workshop & Spare Parts Warehouse Steel Elevation 1 125 5% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0077 Workshop & Lockers - Calculation 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0310 Workshop & Lockers - Base Plate (Plan/Sections) 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0311 Workshop & Lockers - GA For Roof Plan 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0312 Workshop & Lockers - Details of Connection 370 15% 20-May-21 29-Jun-21 06-Jul-21 11-Jul-21 13-Jul-21 18-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9640 Electrical 945 13% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0020 Lighting Layout Plan WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-DWG-0021 Small Power Layout Plan WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0031 Main Normal DB SLD WSW 135 14% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0032 Sub-Normal DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0033 Main Emergency DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0034 SUB Emergency DB SLD WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-LAY-0014 Lightning Protection System WSW 135 14% 25-Nov-21 09-Dec-21 23-Dec-21 06-Jan-22 20-Jan-22 26-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
A9650 Telecomm. 1,610 22% 100% 100% 100% 100% 100% 100% 100% 100%
Workshop & Spare parts Warehouse Fire Alarm system
TL MDF-PTJ-TL-LAY-0004 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
Workshop & Spare parts Warehouse Fire Alarm system
TL MDF-PTJ-TL-LAY-0005 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Cabling Layout
TL MDF-PTJ-TL-LAY-0010 Workshop & Spare parts Warehouse CCTV system Layout 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

Workshop & Spare parts Warehouse Public Address system


TL MDF-PTJ-TL-LAY-0016 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
Workshop & Spare parts Warehouse Public Address system
TL MDF-PTJ-TL-LAY-0017 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Cabling Layout
Workshop & Spare parts Warehouse Data Network & IP
TL MDF-PTJ-TL-LAY-0021 135 8% 06-May-21 20-May-21 03-Jun-21 17-Jun-21 01-Jul-21 07-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Telephone system Layout
TL MDF-PTJ-TL-DWG-0030 Spare parts warehouse Fire alarm plan 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0031 Spare parts warehouse Fire alarm cabling 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0034 Spare parts warehouse Public address system layout 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0035 Spare parts warehouse Public address system cabling 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0036 Spare parts warehouse CCTV SYSTEM LAYOUT 160 10% 24-May-21 07-Jun-21 18-Jun-21 02-Jul-21 14-Jul-21 27-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
HVAC 580 8% 100% 100% 100% 100% 100% 100% 100% 100%
WORKSHOP & LOCKERS BUILDING HVAC SYSTEM
HV MDF-PTJ-HV-CAL-0020 290 50% 04-Aug-21 11-Aug-21 18-Aug-21 25-Aug-21 01-Sep-21 08-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
CALCULATIONS
MDF-PTJ-HV-DWG- WORKSHOP & LOCKERS BUILDING- HVAC GROUND
HV 290 50% 04-Aug-21 11-Aug-21 18-Aug-21 25-Aug-21 01-Sep-21 08-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
0030 FLOOR PLAN
Page 139 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A9660 Fire Fighting Firefighting system Layout - workshop / warehouse building 0 0% 100% 100% 100% 100% 100% 100% 100% 100%

Fire Pump Shed 2,925 4% 100% 100% 100% 100% 100% 100% 100% 100%
A9510 Architecture 1,575 54% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Ground floor Level 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0099
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Roof Level 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0100
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Elevation 1 - 2 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0101
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Elevation 3 - 4 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0102
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Section A-A 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0103
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-finish schedule 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0104
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Doors & Windows Schedule 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0105
MDF-PTJ-AR-DWG- Fire Water Pump Shed-Plumbing Works-water drainage
AR 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0106 system
MDF-PTJ-AR-DWG-
AR Fire Water Pump Shed-Plumbing Works-water supply system 175 11% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
0107
A9520 Civil & St. Str. 1,080 37% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0014 FIRE PUMP Shed calculation sheet 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0029 FIRE PUMP Shed - Foundation Plan & Details 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0002 FIRE PUMP shed - Structural steel calculations report 135 13% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0010 FIRE PUMP shed - Steel Base Plate Plan 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

FIRE PUMP shed - Steel Arrangement of Roof Struts & HZ


ST MDF-PTJ-ST-DWG-0011 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
Bracing
ST MDF-PTJ-ST-DWG-0012 FIRE PUMP shed - Steel Roof Purlins 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DTL-0009 FIRE PUMP shed - Steel Elevations & Details 1 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DTL-0010 FIRE PUMP shed - Steel Elevations & Details 2 135 13% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%
A9530 Electrical 270 9% 100% 100% 100% 100% 100% 100% 100% 100%
EL MDF-PTJ-EL-DWG-0022 Lighting and socket Plan FPS 135 50% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

EL MDF-PTJ-EL-SLD-0035 Distribution board SLD FPS 135 50% 12-Feb-22 17-Feb-22 22-Feb-22 24-Feb-22 27-Feb-22 01-Mar-22 100% 100% 100% 100% 100% 100% 100% 100%

CAR PARK Shed 527 1% 100% 100% 100% 100% 100% 100% 100% 100%
St. Str. 527 100% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0093 CAR PARKING SHED Base Plate Plan & Section 176 33% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0094 CAR PARKING SHED Roof Plan and Elevations 176 33% 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 15-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0095 CAR PARKING SHED Connection Details 176 33% 07-Oct-21 12-Oct-21 17-Oct-21 22-Oct-21 27-Oct-21 01-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

Air Compressor Shed 2,894 4% 100% 100% 100% 100% 100% 100% 100% 100%
A82350 Steel Str 576 20% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-DWG-0026 AIR COMPRESSOR SHED - Calculation Note 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0027 AIR COMPRESSOR SHED - Layout For Base Plate 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0028 AIR COMPRESSOR SHED - Layout Plans& Elevations 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0029 AIR COMPRESSOR SHED- Details Of Connections 144 25% 24-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9400 Architecture 1,035 36% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Air Compressor Shed -Ground&Roof plans 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0141
MDF-PTJ-AR-DWG-
AR Air Compressor Shed -North&East Elevations 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0142
MDF-PTJ-AR-DWG-
AR Air Compressor Shed - South&West Elevations 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0143
MDF-PTJ-AR-DWG-
AR Air Compressor Shed- Section A-A & Section B-B 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0144
MDF-PTJ-AR-DWG- Air Compressor Shed- finish schedule - Doors & Windows
AR 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0145 Schedule
Page 140 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-AR-DWG- Air Compressor Shed - Plumbing Works--water drainage
AR 173 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0146 system & -water supply system
A9410 Civil 275 10% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0021 AIR COMPRESSOR Shed Foundation calculation sheet 138 50% 07-Feb-22 15-Feb-22 18-Feb-22 21-Feb-22 24-Feb-22 27-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0112 AIR COMPRESSOR Shed Foundation Plan & Details 138 50% 07-Feb-22 15-Feb-22 18-Feb-22 21-Feb-22 24-Feb-22 27-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

A9415 EL Electrical MDF-PTJ-EL-LAY-0010 AIR COMPRESSOR Shed Lighting and socket Layout 144 5% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A9430 Telecomm. 864 30% 100% 100% 100% 100% 100% 100% 100% 100%
TL MDF-PTJ-TL-DWG-0011 AIR COMPRESSOR Shed FIRE ALARM SYSTEM 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
AIR COMPRESSOR Shed FIRE ALARM SYSTEM
TL MDF-PTJ-TL-DWG-0012 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
TL MDF-PTJ-TL-DWG-0024 AIR COMPRESSOR Shed CCTV 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

TL MDF-PTJ-TL-DWG-0038 AIR COMPRESSOR Shed PUBLIC ADDRESS SYSTEM 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

AIR COMPRESSOR Shed PUBLIC ADDRESS SYSTEM


TL MDF-PTJ-TL-DWG-0039 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
CABLING
AIR COMPRESSOR Shed NETWORK & IP telephone
TL MDF-PTJ-TL-DWG-0052 144 17% 20-Jan-22 28-Jan-22 02-Feb-22 07-Feb-22 12-Feb-22 17-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
system layout
Industrial Pump Station 2,245 3% 100% 100% 100% 100% 100% 100% 100% 100%
A82390 Steel Str 945 42% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0005 Industrial Water Pump Station - Calculation Note 158 17% 21-Jun-21 31-Jul-21 07-Aug-21 12-Aug-21 14-Aug-21 19-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0035 Industrial Water Pump Station - Layout For Base Plate 158 17% 21-Jun-21 31-Jul-21 07-Aug-21 12-Aug-21 14-Aug-21 19-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0036 Industrial Water Pump Station - Layout Plans& Elevations 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0037 Industrial Water Pump Station - Details Of Connections 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-CAL-0082 Industrial Water Pump Station - Calculation Note 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0038 Industrial Water Pump House Shed - Connection & Details 158 17% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
A9290 Architecture 845 38% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Ground floor Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0206
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Roof Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0207
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Elevation 1 - 2 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0208
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Elevation 3 - 4 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0209
MDF-PTJ-AR-DWG-
AR Industrial Water Pump Station-Section A-A 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0210
A9300 Civil 298 13% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0016 Industrial Water Pump Station Foundation calculation sheet 140 47% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0033 Industrial Water Pump Station- Foundation Plan & Details 158 53% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

Industrial Water Pump Station Shed Lighting and socket


A9320 EL Electrical MDF-PTJ-EL-LAY-0017 158 7% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
Boiling & Fresh Water Pump Station 315 0% 100% 100% 100% 100% 100% 100% 100% 100%
A82380 Steel Str 315 100% 100% 100% 100% 100% 100% 100% 100% 100%
BOILING & FRESH WATER PUMPS STATION - Layout
ST MDF-PTJ-ST-DWG-0044 158 50% 15-Jun-21 26-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Plans& Elevations
BOILING & FRESH WATER PUMPS STATION - Details
ST MDF-PTJ-ST-DWG-0045 158 50% 15-Jun-21 26-Jun-21 01-Jul-21 06-Jul-21 11-Jul-21 16-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Of Connections
A9180 Architecture 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
A9190 Civil 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
BOILING & FRESH WATER PUMPS STATION Shed
A9200 Electrical 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Lighting and socket Layout
Waste Pump Station 765 1% 100% 100% 100% 100% 100% 100% 100% 100%
A82370 Steel Str. 765 100% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0004 WASTE PUMPS STATION - Calculation Note 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0031 WASTE PUMPS STATION - Layout For Base Plate 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0032 WASTE PUMPS STATION - Layout Plans& Elevations 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 141 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
ST MDF-PTJ-ST-DWG-0033 WASTE PUMPS STATION - Details Of Connections 158 21% 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 26-Jun-21 01-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0123 Reject Water Pump Shed- Foundation Plan & Details 135 18% 05-Feb-22 07-Feb-22 09-Feb-22 11-Feb-22 13-Feb-22 15-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A9070 Architecture 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
A9080 Civil 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
A9090 Electrical WASTE PUMPS STATION Shed Lighting and socket Layout 0 0% 100% 100% 100% 100% 100% 100% 100% 100%

Potable water pump station 2,490 3% 100% 100% 100% 100% 100% 100% 100% 100%
A82360 Steel Str. 1,190 48% 100% 100% 100% 100% 100% 100% 100% 100%
ST MDF-PTJ-ST-CAL-0006 POTABLE Water PUMP Station - Calculation Note 158 13% 06-Jul-21 16-Jul-21 23-Jul-21 02-Aug-21 09-Aug-21 14-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0039 POTABLE Water PUMP Station - Layout For Base Plate 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0040 POTABLE Water PUMP Station - Layout Plans& Elevations 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0041 POTABLE Water PUMP Station - Details Of Connections 158 13% 11-May-21 22-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

POTABLE WATER PUMP HOUSE Steel Structure


ST MDF-PTJ-ST-CAL-0069 140 12% 19-Sep-21 29-Sep-21 06-Oct-21 16-Oct-21 23-Oct-21 28-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Calculation
POTABLE WATER PUMP HOUSE Base Plate
ST MDF-PTJ-ST-DWG-0083 140 12% 19-Sep-21 29-Sep-21 06-Oct-21 16-Oct-21 23-Oct-21 28-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
(Plan/Section)
ST MDF-PTJ-ST-DWG-0084 POTABLE WATER PUMP HOUSE Roof Layout Plan 140 12% 19-Sep-21 29-Sep-21 06-Oct-21 16-Oct-21 23-Oct-21 28-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

ST MDF-PTJ-ST-DWG-0085 POTABLE WATER PUMP HOUSE Connections &Details 140 12% 19-Sep-21 29-Sep-21 06-Oct-21 16-Oct-21 23-Oct-21 28-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
A8960 Architecture 845 34% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Ground floor Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0221
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Roof Level 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0222
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Elevation 1 - 2 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0223
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Elevation 3 - 4 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0224
MDF-PTJ-AR-DWG-
AR POTABLE Water PUMP Station-Section A-A 169 20% 01-Jun-21 06-Jun-21 11-Jun-21 16-Jun-21 20-Jun-21 25-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0225
A8970 Civil 298 12% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0017 POTABLE Water PUMP Station Foundation calculation sheet 140 47% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0034 POTABLE Water PUMP Station- Foundation Plan & Details 158 53% 05-Jul-21 07-Jul-21 09-Jul-21 11-Jul-21 13-Jul-21 15-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

POTABLE Water PUMP Station Shed Lighting and socket


A8980 EL Electrical MDF-PTJ-EL-LAY-0021 158 6% 30-Jun-21 02-Jul-21 04-Jul-21 06-Jul-21 08-Jul-21 10-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
Layout
Water Treatment Package 3,000 4% 100% 100% 100% 100% 100% 100% 100% 100%
A16090 Architecture 1,500 50% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-AR-DWG-
AR water traetmeant building -Ground&Roof plans 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0170
MDF-PTJ-AR-DWG-
AR water traetmeant building-North&East Elevations 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0171
MDF-PTJ-AR-DWG-
AR water traetmeant building- South&West Elevations 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0172
MDF-PTJ-AR-DWG-
AR water traetmeant building- Section A-A & Section B-B 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0173
MDF-PTJ-AR-DWG-
AR water traetmeant building- finish schedule 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0174
MDF-PTJ-AR-DWG-
AR water traetmeant building- Doors & Windows Schedule 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0175
MDF-PTJ-AR-DWG- water traetmeant building- Plumbing Works--water drainage
AR 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0176 system
MDF-PTJ-AR-DWG- water traetmeant building- Plumbing Works-water supply
AR 188 13% 29-Nov-21 26-Dec-21 09-Jan-22 19-Jan-22 02-Feb-22 07-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
0177 system
A16100 Civil 375 13% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-CAL-0022 WATER TREATMENT Foundation calculation sheet 188 50% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

CI MDF-PTJ-CI-DWG-0113 WATER TREATMENT Foundation Plan & Details 188 50% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
A16110 Telecomm. 1,125 38% 100% 100% 100% 100% 100% 100% 100% 100%
WATER TREATMENT BUILDING FIRE ALARM
TL MDF-PTJ-TL-DWG-0013 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
WATER TREATMENT BUILDING FIRE ALARM
TL MDF-PTJ-TL-DWG-0014 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM CABLING
Page 142 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
TL MDF-PTJ-TL-DWG-0025 WATER TREATMENT BUILDING CCTV 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

WATER TREATMENT BUILDING PUBLIC ADDRESS


TL MDF-PTJ-TL-DWG-0040 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM
WATER TREATMENT BUILDING PUBLIC ADDRESS
TL MDF-PTJ-TL-DWG-0041 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%
SYSTEM CABLING
TL MDF-PTJ-TL-DWG-0053 WATER TREATMENT BUILDING NETWORK SYSTEM 188 17% 06-Dec-21 02-Jan-22 16-Jan-22 26-Jan-22 09-Feb-22 14-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

Loss Prevention 13,544 6% 100% 100% 100% 100% 100% 100% 100% 100%
HAZID & Layout Review 1,260 9% 100% 100% 100% 100% 100% 100% 100% 100%
A6850 HAZID & Layout Review 1,260 100% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0001 HAZID & Layout Review Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0002 HAZID & Layout Review Close Out Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0003 Weather Condition Report 420 33% 29-Sep-20 10-Oct-20 15-Oct-20 20-Oct-20 25-Oct-20 04-Nov-20 100% 100% 100% 100% 100% 100% 100% 100%

On-Spec. - Project Management 200 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP009 Engineering Documents Register (EDR) 100 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0001 Fire & Gas Mapping assumptions register 100 100% 06-Feb-21 17-Feb-21 22-Feb-21 27-Feb-21 04-Mar-21 14-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP010 Project Schedule 100 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0020 Utilities Layout Review Study 100 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

Onspec. - Loss Prevention 11,274 83% 100% 100% 100% 100% 100% 100% 100% 100%
LP012 Fire Protection Design Philosophy 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0009 Fire Protection Design Philosophy 105 100% 13-Feb-21 24-Feb-21 01-Mar-21 06-Mar-21 11-Mar-21 12-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP013 QRA/FERA and Mapping Assumption Register 205 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0004 Assumption Register for QRA-FERA 105 51% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0006 Quantitative risk assessment (QRA) assumptions register 100 49% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP015 Stage 1-Fire and Explosion Analysis Report (FERA) 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0005 Fire and Explosion Analysis Report (FERA) Report 105 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP016 Quantitative risk assessment (QRA) Report 100 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0007 Quantitative risk assessment (QRA) report 100 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

LP017 Stage 2-Fire and Explosion Analysis Report (FERA) Report 210 2% 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0018 Gas Suppression system Calculation Report (HSE Building) 210 100% 28-May-21 08-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 03-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP018 Fire & Gas Mapping Study Report 105 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0008 Fire & Gas Mapping Study Report 105 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP019 Fire Water and Fire Foam Demand Calculation 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0010 Fire Water and Fire Foam Demand Calculation Report 140 100% 01-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 07-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP020 Preliminary Firefighting Equipment Data Sheet 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP021 Fire Water Network Layout 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0002 Fire Water Network Layout 147 100% 01-Apr-21 12-Apr-21 17-Apr-21 22-Apr-21 27-Apr-21 07-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP022 Hydraulic Calculation Report 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0011 Hydraulic Calculation Report 140 100% 01-Nov-21 12-Nov-21 17-Nov-21 22-Nov-21 27-Nov-21 07-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%

LP023 Fire Water Spray and Foam System Layout (If Required) 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP024 Fire Extinguishers and Safety Equipment Layouts 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP025 Fire Water System P&IDs 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0001 Fire Water System P&IDs 147 100% 14-May-21 25-May-21 30-May-21 04-Jun-21 09-Jun-21 19-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP026 Foam system P&IDs (If Required) 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
LP028 Fire Equipment Specification 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0003 Fire Equipment Specification 140 100% 14-Feb-21 25-Feb-21 02-Mar-21 07-Mar-21 12-Mar-21 22-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP029 Water Foam Vehicle Specification (If Required) 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0001 Water Foam Vehicle Specification (If Required) 147 100% 14-May-21 25-May-21 30-May-21 04-Jun-21 09-Jun-21 19-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP030 Firefighting water Pump Datasheet 3,732 33% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0002 Firefighting water Pump Datasheet 147 4% 19-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 14-Apr-21 24-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 143 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
FF MDF-PTJ-LP-DAT-0010 Fire Water Jockey Pump Datasheet 147 4% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-DAT-0011 MOBILE FOAM UNIT DATASHEET 147 4% 22-Jun-21 03-Jul-21 08-Jul-21 13-Jul-21 18-Jul-21 28-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-DAT-0013 Portable CO2 Fire Extinguishers Datasheet 147 4% 11-Aug-21 22-Aug-21 27-Aug-21 01-Sep-21 06-Sep-21 16-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-MTO-0003 Production Line Fire Extinguishing Nozzles MTO 147 4% 17-Jun-21 28-Jun-21 03-Jul-21 08-Jul-21 13-Jul-21 23-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-MTO-0004 U/G PIPING MTO 147 4% 17-Sep-21 28-Sep-21 03-Oct-21 08-Oct-21 13-Oct-21 23-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
Refining Building - GROUND FLOOR PLAN - Switch Room
FF MDF-PTJ-LP-LAY-0015 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
-SR02A Fire Fighting Protection Layout
SR-02B BUILDING - GROUND FLOOR AND CELLER
FF MDF-PTJ-LP-LAY-0016 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
FLOORPlans
STRAW PREPARATION BUILDING - GROUND FLOOR
FF MDF-PTJ-LP-LAY-0017 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
AND RAISED FLOOR Plans
SUBSTATION BUILDING - GROUND FLOOR AND
FF MDF-PTJ-LP-LAY-0018 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
CELLER FLOOR Plans
PRODUCTION BUILDING - GROUND FLOOR -
FF MDF-PTJ-LP-LAY-0019 140 4% 04-Apr-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
OVERALL PLAN
FF MDF-PTJ-LP-LAY-0025 Fire Fighting Protection Layout For NEW Switch Room 210 6% 07-Jun-21 18-Jun-21 23-Jun-21 28-Jun-21 03-Jul-21 13-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-LAY-0026 Protection Layout for Production Building - Sprinkler System 200 5% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%

FF MDF-PTJ-LP-LAY-0027 FF Protection Layout for Production Building - FHC system 200 5% 08-Aug-21 19-Aug-21 24-Aug-21 29-Aug-21 03-Sep-21 13-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%

Fire Fighting Protection Layout for Workshop & Lockers


FF MDF-PTJ-LP-LAY-0029 140 4% 17-Jul-21 28-Jul-21 02-Aug-21 07-Aug-21 12-Aug-21 22-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
Building
CHEMICAL WAREHOUSE BUILDING GROUND
FF MDF-PTJ-LP-LAY-0030 140 4% 17-Jul-21 28-Jul-21 02-Aug-21 07-Aug-21 12-Aug-21 22-Aug-21 100% 100% 100% 100% 100% 100% 100% 100%
FLOOR PLAN
Fire Fighting Layout For Administration Building - GR Floor
FF MDF-PTJ-LP-LAY-0031 210 6% 25-Aug-21 05-Sep-21 10-Sep-21 15-Sep-21 20-Sep-21 30-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan
Fire Fighting Layout For Administration Building - First Floor
FF MDF-PTJ-LP-LAY-0032 210 6% 25-Aug-21 05-Sep-21 10-Sep-21 15-Sep-21 20-Sep-21 30-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan
Fire Fighting Layout For Administration Building - Second
FF MDF-PTJ-LP-LAY-0033 210 6% 25-Aug-21 05-Sep-21 10-Sep-21 15-Sep-21 20-Sep-21 30-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
Floor Plan
Fire Fighting Layout For Administration Building - Roof Floo
FF MDF-PTJ-LP-LAY-0034 210 6% 25-Aug-21 05-Sep-21 10-Sep-21 15-Sep-21 20-Sep-21 30-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%
Plan
FF MDF-PTJ-LP-SPC-0001 FIRE TRUCK SPECIFICATION 210 6% 25-Aug-21 05-Sep-21 10-Sep-21 15-Sep-21 20-Sep-21 30-Sep-21 100% 100% 100% 100% 100% 100% 100% 100%

PIPING MATERIAL SPECEIFCATION FOR


FF MDF-PTJ-LP-SPC-0002 210 6% 24-Sep-21 05-Oct-21 10-Oct-21 15-Oct-21 20-Oct-21 30-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%
FIREFIGHTING
LP031 Firewater Hydrant & Hydrant Cabinet Data Sheet 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0003 Firewater Hydrant & Hydrant Cabinet Data Sheet 147 100% 22-Apr-21 03-May-21 08-May-21 13-May-21 18-May-21 28-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP032 Firewater Monitors Data Sheet 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0004 Firewater Monitors Data Sheet 147 100% 23-Apr-21 04-May-21 09-May-21 14-May-21 19-May-21 29-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP033 Spray Nozzles Data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0005 Spray Nozzles Data Sheet (If Required) 140 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP034 Portable/Mobile Fire Extinguishers Data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0006 Portable/Mobile Fire Extinguishers Data Sheet 140 100% 25-Apr-21 06-May-21 11-May-21 16-May-21 21-May-21 31-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP035 Fire Hose and Hose Cabinets Data Sheet 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0007 Fire Hose and Hose Cabinets Data Sheet 147 100% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP040 Fire & Gas Equipement Specification 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0004 F&G Equipment Specification 210 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP041 Fire and Gas Detection system Layouts 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0010 Fire and Gas Detection system Layouts 210 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP042 F&G Equipment Datasheet 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0007 F&G Equipment Datasheet 210 100% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP043 F&G Junction Boxes Wiring Diagram 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0004 F&G Junction Boxes Wiring Diagram 210 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP044 F&G Cable Schedule and Spec. 402 4% 100% 100% 100% 100% 100% 100% 100% 100%
FG MDF-PTJ-FG-SPC-0002 Fire and Gas cable specification 93 23% 01-Jan-21 31-Jan-21 07-Feb-21 14-Feb-21 21-Feb-21 28-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 144 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
FG MDF-PTJ-FG-SPC-0003 Fiber Optic cable specification 99 25% 26-Dec-20 25-Jan-21 01-Feb-21 08-Feb-21 15-Feb-21 22-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-DWG-0005 F&G Cable Schedule and Spec. 210 52% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP045 F&G Loop Diagram 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0005 F&G Loop Diagram 210 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP046 F&G Cable Routing Layout 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0011 F&G Cable Routing Layout 200 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP047 F&G Hook up Drawings 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0006 F&G Hook up Drawings 200 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP048 F&G Bulk Material MTO 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-MTO-0001 F & G Material MTO 210 100% 25-Oct-21 05-Nov-21 10-Nov-21 15-Nov-21 20-Nov-21 30-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%
LP050 Fire and Gas Cause and Effect 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0012 Fire and Gas Cause and Effect 200 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP051 Firefighting protection Layout for HSE building 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0006 Firefighting protection Layout for HSE building. 147 100% 11-Feb-21 22-Feb-21 27-Feb-21 04-Mar-21 09-Mar-21 19-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP052 Firefighting protection Layout for Masjed building 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0007 Firefighting protection Layout for Masjed building. 147 100% 12-Feb-21 23-Feb-21 28-Feb-21 05-Mar-21 10-Mar-21 20-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP053 Firefighting protection Layout for Scale Control Room 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0008 Firefighting protection Layout for Scale Control Room. 140 100% 14-Feb-21 25-Feb-21 02-Mar-21 07-Mar-21 12-Mar-21 22-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
LP054 Firefighting protection Layout for Security Room 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
Firefighting protection Layout for Security Room Ground
LP MDF-PTJ-LP-LAY-0009 147 100% 18-Feb-21 01-Mar-21 06-Mar-21 11-Mar-21 16-Mar-21 26-Mar-21 100% 100% 100% 100% 100% 100% 100% 100%
Floor Plan
LP055 Firefighting protection Layout for Administration building 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Total Flooding Clean Agent Gaseous Suppression System
LP056 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
Total Flooding Carbon Dioxide Gaseous Suppression System
LP057 147 1% 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
Total Flooding Carbon Dioxide Gaseous Suppression System
LP MDF-PTJ-LP-DWG-0009 147 100% 05-Mar-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 10-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Spec.
LP058 Portable/Mobile Fire Extinguishers Data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0007 Portable/Mobile Fire Extinguishers Data Sheet. 140 100% 28-Apr-21 09-May-21 14-May-21 19-May-21 24-May-21 03-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP059 Fire Hose and Hose Cabinets data Sheet 140 1% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DAT-0008 Fire Hose and Hose Cabinets data Sheet. 140 100% 07-Mar-21 18-Mar-21 23-Mar-21 28-Mar-21 02-Apr-21 12-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
LP062 Escape Route Layout 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0022 Escape Route Layout 200 100% 16-May-21 27-May-21 01-Jun-21 06-Jun-21 11-Jun-21 21-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP063 Safety Signs Layouts 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0023 Safety Signs Layouts 200 100% 23-May-21 03-Jun-21 08-Jun-21 13-Jun-21 18-Jun-21 28-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
LP064 HAZOP Study 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0016 HAZOP (Limited to 7-days) 210 100% 26-Feb-21 09-Mar-21 14-Mar-21 19-Mar-21 24-Mar-21 03-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
LP065 Noise Study Report 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0013 Noise Study Report 210 100% 09-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 05-May-21 15-May-21 100% 100% 100% 100% 100% 100% 100% 100%
LP066 Noise Control Design 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0014 Noise Control Design Report 210 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP067 Passive Fire Protection Design Schedule 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-SCH-0001 Passive Fire Protection Design Schedule 210 100% 16-Nov-21 27-Nov-21 02-Dec-21 07-Dec-21 12-Dec-21 22-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP068 Passive Fire Protection Layouts 210 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-LAY-0024 Passive Fire Protection Layouts 210 100% 28-May-21 08-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 03-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%

LP069 Waste Management Philosophy and Handling Requirements 210 2% 100% 100% 100% 100% 100% 100% 100% 100%

LP MDF-PTJ-LP-RPT-0017 Waste Management Philosophy and Handling Requirements 210 100% 02-Jun-21 13-Jun-21 18-Jun-21 23-Jun-21 28-Jun-21 08-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP070 Emissions Control Design 200 2% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-RPT-0015 Emissions Control Design Report 200 100% 14-Nov-21 25-Nov-21 30-Nov-21 05-Dec-21 10-Dec-21 20-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
On-Spec. Piping Engineering Discipline 410 3% 100% 100% 100% 100% 100% 100% 100% 100%
Page 145 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
LP078 Firefighting Network Piping MTO for Storage Area 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
LP079 3D Model 210 51% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0008 3D Model 210 100% 23-Jun-21 04-Jul-21 09-Jul-21 14-Jul-21 19-Jul-21 29-Jul-21 100% 100% 100% 100% 100% 100% 100% 100%
LP080 Firefighting Network Piping MTO 200 49% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-MTO-0002 Piping MTO 200 100% 14-Mar-21 25-Mar-21 30-Mar-21 04-Apr-21 09-Apr-21 19-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

On-Spec. - Electrical Engineering Discipline 400 3% 100% 100% 100% 100% 100% 100% 100% 100%
LP082 Hazardous Area Classification Schedule 200 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-SCH-0002 Hazardous Area Classification Schedule 200 100% 22-Nov-21 03-Dec-21 08-Dec-21 13-Dec-21 18-Dec-21 28-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
LP083 Hazardous Area Classification Drawings 200 50% 100% 100% 100% 100% 100% 100% 100% 100%
LP MDF-PTJ-LP-DWG-0007 Hazardous Area Classification Drawings 200 100% 29-Dec-21 09-Jan-22 14-Jan-22 19-Jan-22 24-Jan-22 03-Feb-22 100% 100% 100% 100% 100% 100% 100% 100%

Storage Tanks 13,780 6% 100% 100% 100% 100% 100% 100% 100% 100%
Civil 1,150 8% 100% 100% 100% 100% 100% 100% 100% 100%
TK.320 Foundations For Industrial Raw Water Tank 340 30% 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION FOR Industrial Raw Water Tanks - TK101-
CI MDF-PTJ-CI-CAL-0100 65 19% 03-Feb-21 11-Feb-21 16-Feb-21 21-Feb-21 25-Feb-21 28-Feb-21 100% 100% 100% 100% 100% 100% 100% 100%
A - CALCULATION
FOUNDATION DETAILS FOR Industrial Raw Water Tanks
CI MDF-PTJ-CI-DWG-0021 275 81% 04-Feb-21 21-Mar-21 05-Apr-21 20-Apr-21 25-Apr-21 10-May-21 100% 100% 100% 100% 100% 100% 100% 100%
- TK101-A
TK.330 Foundations For DEMI Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0053 FOUNDATION DETAILS FOR Demi Water Tank TK-103A 270 100% 20-Jan-21 06-Mar-21 21-Mar-21 05-Apr-21 10-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.340 Foundations For Process Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
FOUNDATION DETAILS FOR Process Water Tank TK-
CI MDF-PTJ-CI-DWG-0052 270 100% 20-Jan-21 06-Mar-21 21-Mar-21 05-Apr-21 10-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
102A
TK.430 Foundations For Potable Water Tank 270 23% 100% 100% 100% 100% 100% 100% 100% 100%
CI MDF-PTJ-CI-DWG-0051 FOUNDATION DETAILS FOR Potable Water Tank 270 100% 26-Sep-21 10-Nov-21 25-Nov-21 10-Dec-21 15-Dec-21 30-Dec-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.440 Foundations For Emulsion - Chemical Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.450 Foundations For PMDI - Chemical Storage Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.460 Foundations For Fire Water Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
Design Calc. & Data Sheet 2,277 17% 100% 100% 100% 100% 100% 100% 100% 100%
TK.250 Industrial Raw Water Tank 674 30% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-SPC-0001 Gauge Hatch Technical Specification 190 28% 23-Feb-21 09-Apr-21 14-Apr-21 19-Apr-21 24-Apr-21 25-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-SPC-0002 Agitators Technical Specification 190 28% 14-Sep-21 29-Oct-21 03-Nov-21 08-Nov-21 13-Nov-21 14-Nov-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-CAL-0001 Industrial Raw Water Tanks Design Calculations 138 20% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0001 Industrial Raw Water Tanks Roof Structure Details 117 17% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0002 Industrial Raw Water Tanks Name Plate 39 6% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.260 DEMI Water Tank 294 13% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0003 Demi Water Tanks Design Calculations 138 47% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0003 Demi Water Tanks Roof Structure Details 117 40% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0004 Demi Water Tanks Name Plate 39 13% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.270 Process Water Tank 294 13% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0005 Process Water Tanks Design Calculations 138 47% 01-Nov-20 24-Nov-20 26-Nov-20 29-Nov-20 04-Dec-20 09-Dec-20 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0005 Process Water Tanks Roof Structure Details 117 40% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0006 Process Water Tanks Name Plate 39 13% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.280 Potable Water Tank 0 0% 0% 0% 0% 0% 0% 0% 0% 0%
TK.290 Emulsion Chemical Tank 589 26% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0013 Chemical Tank Design Calculations 117 20% 13-Mar-21 16-Mar-21 21-Mar-21 24-Mar-21 27-Mar-21 01-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-CAL-0014 Chemical Tank Roof Structure Calculations 120 20% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0013 Chemical Tank Roof Structure Details 176 30% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0014 Chemical Tank Name Plate 176 30% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
TK.300 Fire Water Tank 426 19% 100% 100% 100% 100% 100% 100% 100% 100%
TK MDF-PTJ-TK-CAL-0011 Fire Water Tanks Design Calculations 130 31% 12-Apr-21 15-Apr-21 20-Apr-21 23-Apr-21 26-Apr-21 01-May-21 100% 100% 100% 100% 100% 100% 100% 100%

Page 146 of 234


11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
TK MDF-PTJ-TK-CAL-0012 Fire Water Tanks Roof Structure Calculations 80 19% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0011 Fire Water Tanks Roof Structure Details 108 25% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%

TK MDF-PTJ-TK-DTL-0012 Fire Water Tanks Name Plate 108 25% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
TK.310 PMDI - Chemical Storage Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Drawings 10,353 75% 100% 100% 100% 100% 100% 100% 100% 100%
TK.000 Industrial Raw Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0005
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0006
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0007
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0008
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0010
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0012
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0013
MDF-PTJ-TK-DWG-
TK Industrial Raw Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0014
TK.010 DEMI Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Demi Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0015
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0016
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0017
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0018
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0019
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0020
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0021
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0022
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0024
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0026
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0027
MDF-PTJ-TK-DWG-
TK Demi Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0028
TK.020 Process Water Tank 2,126 21% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Process Water Tanks General Arrangement 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0029
MDF-PTJ-TK-DWG-
TK Process Water Tanks Orientation 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0030
MDF-PTJ-TK-DWG-
TK Process Water Tanks Bottom Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0031
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Plates 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0032
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Plates 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0033
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0034
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Manhole 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0035
Page 147 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
MDF-PTJ-TK-DWG-
TK Process Water Tanks Shell Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0036
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Nozzles 98 5% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0038
MDF-PTJ-TK-DWG-
TK Process Water Tanks Spiral Stairway 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0040
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Handrail 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0041
MDF-PTJ-TK-DWG-
TK Process Water Tanks Roof Structure Assembly 234 11% 07-Feb-21 19-Mar-21 29-Mar-21 03-Apr-21 10-Apr-21 15-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0042
TK.040 Fire Water Tank 1,512 15% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Fire Water Tanks General Arrangement 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0071
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Orientation 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0072
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Bottom Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0073
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0074
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Plates 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0075
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Manhole 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0076
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Manhole 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0077
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Shell Nozzles 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0078
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Draw-off Sump 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0079
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Nozzles 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0080
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Mechanical Level Indicator 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0081
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Spiral Stairway 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0082
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Handrail 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0083
MDF-PTJ-TK-DWG-
TK Fire Water Tanks Roof Structure Assembly 108 7% 14-Dec-21 17-Dec-21 22-Dec-21 25-Dec-21 28-Dec-21 02-Jan-22 100% 100% 100% 100% 100% 100% 100% 100%
0084
TK.240 PMDI - Chemical Storage Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
TK.470 Emulsion Chemical Tank 2,464 24% 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-TK-DWG-
TK Chemical Tank General Arrangement 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0085
MDF-PTJ-TK-DWG-
TK Chemical Tank Orientation 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0086
MDF-PTJ-TK-DWG-
TK Chemical Tank Bottom Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0087
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0088
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Plates 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0089
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Manhole 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0090
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Manhole 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0091
MDF-PTJ-TK-DWG-
TK Chemical Tank Shell Nozzles 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0092
MDF-PTJ-TK-DWG-
TK Chemical Tank Draw-off Sump 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0093
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Nozzles 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0094
MDF-PTJ-TK-DWG-
TK Chemical Tank Mechanical Level Indicator 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0095
MDF-PTJ-TK-DWG-
TK Chemical Tank Spiral Stairway 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0096
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Handrail 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0097
MDF-PTJ-TK-DWG-
TK Chemical Tank Roof Structure Assembly 176 7% 27-May-21 30-May-21 04-Jun-21 07-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
0098
Cathodic Protection 4,050 2% 100% 100% 100% 100% 100% 100% 100% 100%
CP.000 Industrial Water Tank 1,040 26% 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0001 Internal CP design report for Industrial Raw Water Tanks 140 13% 03-Mar-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
Page 148 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
CP MDF-PTJ-CP-RPT-0008 External CP design report for Industrial Raw Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0001 Anodes distribution drawing for Industrial Raw Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DTL-0001 anodes installation details for Industrial Raw Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0008 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

PERMANENT REFERENCE ELECTRODE


CP MDF-PTJ-CP-DWG-0009 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
INSTALLATION
CP MDF-PTJ-CP-DWG-0010 SCHEMATIC CP LAYOUT 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP.010 DEMI Water Tank 1,050 26% 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0002 Internal CP design report for Boiler Feed Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-RPT-0010 External CP design report for Demi Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0002 anodes distribution drawing for Boiler Feed Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DTL-0002 anodes installation Details for Boiler Feed Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0014 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

PERMANENT REFERENCE ELECTRODE


CP MDF-PTJ-CP-DWG-0015 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
INSTALLATION
CP MDF-PTJ-CP-DWG-0016 SCHEMATIC CP LAYOUT 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP.020 Process Water Tank 1,050 26% 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0005 Internal CP design report for Process Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-RPT-0009 External CP design report for Process Water Tank 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0005 anodes distribution drawing for Process Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DTL-0005 anodes installation Details for Process Water Tanks 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0011 EXTERNAL ANODES DISTRIBUTION 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%

PERMANENT REFERENCE ELECTRODE


CP MDF-PTJ-CP-DWG-0012 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
INSTALLATION
CP MDF-PTJ-CP-DWG-0013 SCHEMATIC CP LAYOUT 150 14% 28-Feb-21 30-Mar-21 09-Apr-21 14-Apr-21 21-Apr-21 26-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
CP.050 Fire Water Tank 910 22% 100% 100% 100% 100% 100% 100% 100% 100%
CP MDF-PTJ-CP-RPT-0003 Internal CP design report for Fire Water Tanks 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0003 anodes distribution drawing for Fire Water Tanks 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DTL-0003 anodes installation Details for Fire Water Tanks 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-RPT-0011 External CP design report for Demi Water Tank 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

CP MDF-PTJ-CP-DWG-0017 EXTERNAL ANODES DISTRIBUTION 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

PERMANENT REFERENCE ELECTRODE


CP MDF-PTJ-CP-DWG-0018 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
INSTALLATION
CP MDF-PTJ-CP-DWG-0019 SCHEMATIC CP LAYOUT 130 14% 21-May-21 26-May-21 31-May-21 05-Jun-21 10-Jun-21 15-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
CP.200 PMDI - Chemical Storage Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
CP.240 Emulsion Chemical Tank 0 0% 100% 100% 100% 100% 100% 100% 100% 100%
Painting & Insulation 748 0% 100% 100% 100% 100% 100% 100% 100% 100%
A10760 Painting Specifications & MTO 315 42% 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0013 surface preparation and painting specification 140 44% 24-Oct-20 29-Oct-20 23-Nov-20 28-Nov-20 23-Dec-20 18-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

MDF-PTJ-ME-MTO-
ME painting MTO 175 56% 09-Feb-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 05-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
0001
A10780 Insulation Specifications & MTO 433 58% 100% 100% 100% 100% 100% 100% 100% 100%
ME MDF-PTJ-ME-SPC-0014 Thermal Insulation specification 88 20% 09-Feb-21 16-Mar-21 21-Mar-21 26-Mar-21 31-Mar-21 05-Apr-21 100% 100% 100% 100% 100% 100% 100% 100%
MDF-PTJ-ME-MTO-
ME Thermal Insulation MTO 170 39% 11-Mar-21 15-Apr-21 20-Apr-21 25-Apr-21 30-Apr-21 05-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0002
MDF-PTJ-ME-MTO-
ME MTO for Refractory Material 175 40% 31-Mar-21 05-May-21 10-May-21 15-May-21 20-May-21 25-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0004
Civil Network 1,761 1% 100% 100% 100% 100% 100% 100% 100% 100%
Page 149 of 234
11-02-23
TotalMan- IFR IFA IFC IFR IFA IFC Overall IFR IFA IFC Overall
Activity ID Dis Activity Name DOCUMENT NO. DESCRIPTION R.Wt.
hours Plan Act.
Start Finish Start Finish Start Finish 50% 20% 30% 50% 20% 30%
A16660 Potable water network 636 36% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-LAY-0001 POTABLE WATER NETWORK LAYOUT 318 50% 11-Oct-20 31-Oct-20 20-Nov-20 20-Dec-20 20-Dec-20 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%

CN MDF-PTJ-CN-CAL-0001 CALCULATIONS FOR NETWORKS 318 50% 21-Oct-20 10-Nov-20 20-Nov-20 20-Dec-20 20-Dec-20 12-Jan-21 100% 100% 100% 100% 100% 100% 100% 100%
A16670 Sewer & Storm Water network 820 47% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-LAY-0002 SEWER AND STORM WATER NETWORK LAYOUT 210 26% 10-Mar-21 14-Apr-21 19-Apr-21 24-Apr-21 29-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%

SEWER AND STORM WATER NETWORK MANHOLES


CN MDF-PTJ-CN-DTL-0001 210 26% 10-Mar-21 14-Apr-21 19-Apr-21 24-Apr-21 29-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
DETAILS
MDF-PTJ-CN-DWG-
CN x SEPTIC TANK 70 9% 10-Mar-21 14-Apr-21 19-Apr-21 24-Apr-21 29-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%
0003
CN MDF-PTJ-CN-DTL-0002 Pump Station-1 Details 175 21% 10-Mar-21 14-Apr-21 19-Apr-21 24-Apr-21 29-Apr-21 04-May-21 100% 100% 100% 100% 100% 100% 100% 100%

CN MDF-PTJ-CN-LAY-0003 STORM WATER LAYOUT 155 19% 02-Apr-21 07-Apr-21 02-May-21 07-May-21 01-Jun-21 30-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%
A16690 Irrigation network 305 17% 100% 100% 100% 100% 100% 100% 100% 100%
CN MDF-PTJ-CN-DTL-0003 Pump Station-2 Details 155 51% 02-Apr-21 07-Apr-21 02-May-21 07-May-21 01-Jun-21 30-Jun-21 100% 100% 100% 100% 100% 100% 100% 100%

CN MDF-PTJ-CN-MTO-0001 INFRASTRUCTUR - MTO 150 49% 26-Sep-21 03-Oct-21 10-Oct-21 17-Oct-21 24-Oct-21 31-Oct-21 100% 100% 100% 100% 100% 100% 100% 100%

As Built 7,075 3.0% 100% 100% 100% 100% 100% 100% 100% 20%
A19360 As Built 7,075 100% 07-Jun-22 07-Nov-22 07-Nov-22 16-Jun-23 07-Jun-22 07-Nov-22 100% 100% 100% 100% 100% 100% 100% 20%

Page 150 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
Procurement Services (MRQ, TBE, Vendor Print) 447 27-Aug-20 14-Jun-22 100% 100.0% 100.0% 100.0% 100.0%
Potable Water System 313 03-Jan-21 05-Apr-22 2% 100% 2% 100% 2%
Piping Fitting & Bulk Material 233 03-Jan-21 12-Dec-21 11% 100% 11% 100% 11%
A7760 MRQ-Piping, Fitting, Flanges- Potable Water Sys. 17 03-Jan-21 27-Jan-21 30% 100% 30% 100% 30%
A14150 TBE - Piping, Fitting, Flanges- Potable Water Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges- Potable Water
A14180 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Sys.
Sewage treatment packages MRQ 29 19-Sep-21 31-Oct-21 4% 100% 4% 100% 4%
A90250 MRQ-Valves - Industrial Water 29 19-Sep-21 31-Oct-21 100% 100% 100% 100% 100%
Piping Valves - Potable Water 281 27-Jan-21 14-Mar-22 14% 100% 14% 100% 14%
A84820 MRQ-Valves - Potable Water Sys. 57 27-Jan-21 15-Apr-21 30% 100% 30% 100% 30%
A84830 TBE- Valves - Potable Water Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
A84840 Vendor Print Preview-Valves - Potable Water Sys. 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Pumps 190 01-Jul-21 05-Apr-22 71% 100% 71% 100% 71%
A7780 MRQ-Pumps - Potable Water Sys. 41 01-Jul-21 02-Sep-21 30% 100% 30% 100% 30%
A14170 TBE- Pumps - Potable Water Sys. 17 15-Sep-21 10-Oct-21 30% 100% 30% 100% 30%
A14200 Vendor Print Preview-Pumps - Potable Water Sys. 90 29-Nov-21 05-Apr-22 40% 100% 40% 100% 40%
Compressed Air System 329 18-Nov-20 14-Mar-22 2% 100% 2% 100% 2%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 12% 100% 12% 100% 12%
A8230 MRQ-Piping, Fitting, - Compressed Air Sys. 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
A14240 TBE -Piping, Fitting, Flanges- Compressed Air Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges- Compressed
A14270 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Air Sys
Piping Valves 286 19-Jan-21 14-Mar-22 15% 100% 15% 100% 15%
A8240 MRQ-Valves - Compressed Air Sys. 61 19-Jan-21 14-Apr-21 30% 100% 30% 100% 30%
A14250 TBE - Valves - Compressed Air Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
A14280 Vendor Print Preview-Valves - Compressed Air Sys. 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Air Compressor Package 317 18-Nov-20 24-Feb-22 74% 100% 74% 100% 74%
A8250 MRQ - Air Compressor - Compressed Air Sys. 47 18-Nov-20 24-Jan-21 30% 100% 30% 100% 30%
A14260 TBE - Air Compressor - Compressed Air Sys. 128 09-Feb-21 18-Aug-21 30% 100% 30% 100% 30%

A14290 Vendor Print Preview-Air Compressor - Compressed Air Sys. 76 09-Nov-21 24-Feb-22 40% 100% 40% 100% 40%

Boiling & Fresh Water System 314 31-Dec-20 05-Apr-22 1% 100% 1% 100% 1%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 31% 100% 31% 100% 31%
MRQ-Piping, Fitting, Flanges - Boiler Feed Water & Fresh
A8170 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
Water Sys.
TBE - Piping, Fitting, Flanges - Boiler Feed Water & Fresh
A14330 145 11-Apr-21 14-Nov-21 30% 100% 30% 100% 30%
Water Sys.
Vendor Print Preview -Piping, Fitting, Flanges - Boiler Feed
A14360 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Water & Fresh Water Sys.
Piping Valves 286 19-Jan-21 14-Mar-22 31% 100% 31% 100% 31%
A8180 MRQ-Valves - Boiler Feed Water& Fresh Water Sys. 61 19-Jan-21 14-Apr-21 30% 100% 30% 100% 30%
A14340 TBE - Valves - Boiler Feed Water & Fresh Water Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview-Valves - Boiler Feed Water & Fresh
A14370 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Water Sys
Pumps - Thermal Oil 280 21-Feb-21 05-Apr-22 39% 100% 39% 100% 39%
A8190 MRQ-Pumps -Thermal Oil 41 21-Feb-21 18-Apr-21 30% 100% 30% 100% 30%
A14350 TBE - Pumps - Thermal Oil 17 15-Sep-21 10-Oct-21 30% 100% 30% 100% 30%
A14380 Vendor Print Preview-Pumps - Thermal Oil 90 29-Nov-21 05-Apr-22 40% 100% 40% 100% 40%
Fuel Gas System 298 31-Dec-20 14-Mar-22 0.3% 100% 0% 100% 0%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 44% 100% 44% 100% 44%
A8290 MRQ-Piping, Fitting, Flanges - Fuel Gas Sys. 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
A14420 TBE - Piping, Fitting, Flanges - Fuel Gas Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
A14450 Vendor Print Preview -Piping, Fitting, Flanges - Fuel Gas Sys. 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Piping Valves 286 19-Jan-21 14-Mar-22 56% 100% 56% 100% 56%
A8300 MRQ-Valves - Fuel Gas Sys. 61 19-Jan-21 14-Apr-21 30% 100% 30% 100% 30%
A14430 TBE - Valves - Fuel Gas Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%
A14460 Vendor Print Preview-Valves - Fuel Gas Sys. 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Industrial Water System 314 31-Dec-20 05-Apr-22 2% 100% 2% 100% 2%
Piping Fitting & Bulk Material 234 31-Dec-20 12-Dec-21 10% 100% 10% 100% 10%
A8110 MRQ - Piping, Fitting, Flanges-Industrial Water Sys. 17 31-Dec-20 26-Jan-21 30% 100% 30% 100% 30%
A14750 TBE - Piping, Fitting, Flanges-Industrial Water Sys. 146 11-Apr-21 15-Nov-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges-Industrial Water
A14800 8 01-Dec-21 12-Dec-21 40% 100% 40% 100% 40%
Sys
Piping Valves 287 18-Jan-21 14-Mar-22 13% 100% 13% 100% 13%
A8120 MRQ - Valves- -Industrial Water Sys. 61 18-Jan-21 13-Apr-21 30% 100% 30% 100% 30%
A14760 TBE - Valves- -Industrial Water Sys. 24 17-Oct-21 18-Nov-21 30% 100% 30% 100% 30%

Page 151 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
A14810 Vendor Print Preview -Valves- -Industrial Water Sys. 70 05-Dec-21 14-Mar-22 40% 100% 40% 100% 40%
Pumps 280 21-Feb-21 05-Apr-22 13% 100% 13% 100% 13%
A8130 MRQ - Pumps --Industrial Water Sys. 41 21-Feb-21 18-Apr-21 30% 100% 30% 100% 30%
A14770 TBE - Pumps --Industrial Water Sys. 17 15-Sep-21 10-Oct-21 30% 100% 30% 100% 30%
A14820 Vendor Print Preview -Pumps --Industrial Water Sys. 90 29-Nov-21 05-Apr-22 40% 100% 40% 100% 40%
Industrial Water PKG 265 18-Jan-21 10-Feb-22 64% 100% 64% 100% 64%
A8440 MRQ - Industrial Water PKG.- -Industrial Water Sys. 29 18-Jan-21 28-Feb-21 30% 100% 30% 100% 30%
A14780 TBE - Industrial Water PKG.- -Industrial Water Sys. 15 15-Mar-21 04-Apr-21 30% 100% 30% 100% 30%
Vendor Print Preview -Industrial Water PKG.- -Industrial
A14830 58 21-Nov-21 10-Feb-22 40% 100% 40% 100% 40%
Water Sys.
Waste Water and chemical System 106 13-Oct-21 14-Mar-22 0% 100% 0% 100% 0%
Piping Fitting & Bulk Material 14 30-Nov-21 19-Dec-21 100% 100% 100% 100% 100%

A90540 MRQ - Piping, Fitting, Flanges - Waste Water & Chemical Sys. 5 30-Nov-21 06-Dec-21 30% 100% 30% 100% 30%

A90570 TBE - Piping, Fitting, Flanges- Waste Water & Chemical Sys. 4 07-Dec-21 12-Dec-21 30% 100% 30% 100% 30%
Vendor Print Preview -Piping, Fitting, Flanges- Waste Water &
A90610 5 13-Dec-21 19-Dec-21 40% 100% 40% 100% 40%
Chemical Sys.
Piping Valves 106 13-Oct-21 14-Mar-22 0% 100% 0% 100% 0%
A90550 MRQ - Valves - Waste Water & Chemical Sys. 5 13-Oct-21 20-Oct-21 0% 100% 0% 100% 0%
A90580 TBE - Valves - Waste Water & Chemical Sys. 24 17-Oct-21 18-Nov-21 0% 100% 0% 100% 0%

A90620 Vendor Print Preview -Valves - Waste Water & Chemical Sys. 70 05-Dec-21 14-Mar-22 100% 100% 100% 100% 100%

Waste Water & Chemical PKG 29 16-Nov-21 26-Dec-21 0% 100% 0% 100% 0%

A90530 MRQ - Industrial Water PKG.- Waste Water & Chemical Sys. 29 16-Nov-21 26-Dec-21 100% 100% 100% 100% 100%

Fire & Gas System 77 24-Nov-21 14-Mar-22 1% 100% 1% 100% 1%


F&G Equipment 77 24-Nov-21 14-Mar-22 100% 100% 100% 100% 100%
LP049 MRQ - F&G - Equipment 3 24-Nov-21 28-Nov-21 30% 100% 30% 100% 30%
FG.40 TBE - F&G - System 20 08-Dec-21 04-Jan-22 30% 100% 30% 100% 30%
FG.50 Vendor Print Preview - F&G - System 36 23-Jan-22 14-Mar-22 40% 100% 40% 100% 40%
Fire - Fighting 132 28-Sep-21 05-Apr-22 2% 100% 2% 100% 2%
Water Foam Vehicle 33 28-Dec-21 14-Feb-22 0% 0% 0%
LP038 Water Foam Vehicle MRQ (If Required) 33 28-Dec-21 14-Feb-22 100% 0% 100% 0%
LP073 Water Foam Vehicle TBER (If Required) 2 13-Feb-22 14-Feb-22 100% 0% 100% 0%
Fire Equipment 90 29-Nov-21 05-Apr-22 25% 100% 25% 100% 25%
LP036 MRQ - FF - Fire Equipment (On-Spec.) 2 23-Dec-21 26-Dec-21 30% 100% 30% 100% 30%
LP071 TBE- FF - Fire Equipment 1 29-Nov-21 29-Nov-21 30% 100% 30% 100% 30%
FF.70 Vendor Print Preview- FF - Fire Equipment 56 17-Jan-22 05-Apr-22 40% 100% 40% 100% 40%
Fire Water Pump 86 30-Nov-21 31-Mar-22 25% 100% 25% 100% 25%
LP037 MRQ - FF - Fire Water Pump (On-Spec.) 1 27-Dec-21 27-Dec-21 30% 100% 30% 100% 30%
LP072 TBE- FF - Fire Water Pump 1 30-Nov-21 30-Nov-21 30% 100% 30% 100% 30%
FF.71 Vendor Print Preview- FF - Fire Water Pump 75 15-Dec-21 31-Mar-22 40% 100% 40% 100% 40%
Fire Truck 5 15-Feb-22 21-Feb-22 0% 100% 0% 100% 0%
LP039 Fire Truck MRQ 3 15-Feb-22 17-Feb-22 0% 100% 0% 100% 0%
LP074 Fire truck TBER 2 20-Feb-22 21-Feb-22 100% 100% 100% 100% 100%
Total Flooding Clean Agent Gaseous Suppression System 132 28-Sep-21 05-Apr-22 25% 100% 25% 100% 25%
MRQ - FF - Total Flooding Clean Agent Gaseous Suppression
LP060 3 28-Sep-21 30-Sep-21 30% 100% 30% 100% 30%
system
TBE- FF - Total Flooding Clean Agent Gaseous Suppression
LP075 2 06-Dec-21 07-Dec-21 30% 100% 30% 100% 30%
system
FF.74 Vendor Print Preview - FF - Clean Agent (Inert Gas) 56 17-Jan-22 05-Apr-22 40% 100% 40% 100% 40%
Total Flooding Carbon Dioxide Gaseous Suppression System 132 28-Sep-21 05-Apr-22 25% 100% 25% 100% 25%
MRQ - FF - Total Flooding Carbon Dioxide Gaseous
LP061 3 28-Sep-21 30-Sep-21 30% 100% 30% 100% 30%
Suppression system
TBE- FF - Total Flooding Carbon Dioxide Gaseous
LP076 2 08-Dec-21 09-Dec-21 30% 100% 30% 100% 30%
Suppression system
FF.120 Vendor Print Preview - FF - Carbon Dioxide 56 17-Jan-22 05-Apr-22 40% 100% 40% 100% 40%
Instrumentation (Control System) 289 31-Jan-21 28-Mar-22 19% 100% 19% 100% 19%
Control System (DCS) 125 29-Sep-21 28-Mar-22 11% 100% 11% 100% 11%
IN.130 MRQ - Control System (DCS) 20 29-Sep-21 28-Oct-21 30% 100% 30% 100% 30%
IN.140 TBE - Control System (DCS) 20 11-Nov-21 08-Dec-21 30% 100% 30% 100% 30%
IN.150 Vendor Print Preview - Control System (DCS) 65 26-Dec-21 28-Mar-22 40% 100% 40% 100% 40%
Field Instrument 248 31-Jan-21 30-Jan-22 11% 100% 11% 100% 11%
IN.050 MRQ - Field Instrument 46 31-Jan-21 04-Apr-21 30% 100% 30% 100% 30%
IN.110 TBE- Field Instrument 25 21-Oct-21 24-Nov-21 30% 100% 30% 100% 30%
IN.120 Vendor Print Preview- Field Instrument 34 12-Dec-21 30-Jan-22 40% 100% 40% 100% 40%
Control Valves 273 31-Jan-21 06-Mar-22 11% 100% 11% 100% 11%

Page 152 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
IN.160 MRQ - Control Valves 67 31-Jan-21 05-May-21 30% 100% 30% 100% 30%
IN.170 TBE - Control Valves 30 21-Oct-21 01-Dec-21 30% 100% 30% 100% 30%
IN.180 Vendor Print Preview - Control Valves 54 19-Dec-21 06-Mar-22 40% 100% 40% 100% 40%
Mechanical level indicator 219 31-Jan-21 16-Dec-21 11% 100% 11% 100% 11%
IN.290 MRQ - Mechanical Level Indicator 46 31-Jan-21 04-Apr-21 31% 100% 31% 100% 31%
IN.300 TBE- Mechanical Level Indicator 39 18-Apr-21 14-Jun-21 31% 100% 31% 100% 31%
IN.310 Vendor Print Preview- Mechanical Level Indicator 42 20-Oct-21 16-Dec-21 39% 100% 39% 100% 39%
Flow meter 248 31-Jan-21 30-Jan-22 11% 100% 11% 100% 11%
IN.320 MRQ - Flow Meter 46 31-Jan-21 04-Apr-21 31% 100% 31% 100% 31%
IN.330 TBE- Flow Meter 30 02-Sep-21 14-Oct-21 31% 100% 31% 100% 31%
IN.340 Vendor Print Preview- Flow Meter 34 12-Dec-21 30-Jan-22 39% 100% 39% 100% 39%
Analyzers 76 05-Oct-21 23-Jan-22 11% 100% 11% 100% 11%
IN.350 MRQ - Analyzers 35 05-Oct-21 24-Nov-21 31% 100% 31% 100% 31%
IN.360 TBE- Analyzers 15 28-Oct-21 17-Nov-21 31% 100% 31% 100% 31%
IN.370 Vendor Print Preview- Analyzers 30 12-Dec-21 23-Jan-22 39% 100% 39% 100% 39%
ISBL - Instrument Cables 195 28-Apr-21 10-Feb-22 11% 100% 11% 100% 11%
IN.620 MRQ - ISBL Instrument Cables 36 28-Apr-21 20-Jun-21 31% 100% 31% 100% 31%
IN.630 TBE- ISBL Instrument Cables 23 25-Jul-21 25-Aug-21 31% 100% 31% 100% 31%
IN.640 Vendor Print Preview - ISBL Instrument Cables 71 02-Nov-21 10-Feb-22 39% 100% 39% 100% 39%
Instrument - JB 240 25-Feb-21 14-Feb-22 11% 100% 11% 100% 11%
IN.650 MRQ - Instrument JB 27 25-Feb-21 04-Apr-21 31% 100% 31% 100% 31%
IN.660 TBE - Instrument JB 30 02-Sep-21 14-Oct-21 31% 100% 31% 100% 31%
IN.670 Vendor Print Preview - Instrument JB 45 12-Dec-21 14-Feb-22 39% 100% 39% 100% 39%
OSBL- Instrument Cables 87 12-Oct-21 14-Feb-22 11% 100% 11% 100% 11%
IN.680 MRQ - OSBL Instrument Cables 8 12-Oct-21 24-Oct-21 31% 100% 31% 100% 31%
IN.690 TBE- OSBL Instrument Cables 23 25-Oct-21 24-Nov-21 31% 100% 31% 100% 31%
IN.700 Vendor Print Preview - OSBL Instrument Cables 45 12-Dec-21 14-Feb-22 39% 100% 39% 100% 39%
Electrical 331 15-Oct-20 13-Feb-22 16% 100% 16% 100% 16%
Earthing Material 205 23-Nov-20 20-Sep-21 7% 100% 7% 100% 7%
A74330 MRQ- Earthing - Batch-1 46 23-Nov-20 27-Jan-21 30% 100% 30% 100% 30%
A74340 TBE - Earthing - Batch-1 30 23-Feb-21 05-Apr-21 30% 100% 30% 100% 30%
A74350 Vendor Print Preview - Earthing - Batch-1 71 06-Jun-21 20-Sep-21 40% 100% 40% 100% 40%
Earthing Material (Building) 143 24-Feb-21 23-Sep-21 7% 100% 7% 100% 7%
A8635 MRQ- Earthing - Batch-2 47 24-Feb-21 02-May-21 30% 100% 30% 100% 30%
A14880 TBE - Earthing - Batch-2 30 19-May-21 29-Jun-21 30% 100% 30% 100% 30%
A14920 Vendor Print Preview - Earthing - Batch-2 42 27-Jul-21 23-Sep-21 40% 100% 40% 100% 40%
Outdoor lighting 93 13-Sep-21 24-Jan-22 7% 100% 7% 100% 7%
A8620 MRQ-Outdoor Lighting 47 13-Sep-21 18-Nov-21 30% 100% 30% 100% 30%
A14860 TBE - Outdoor Lighting 10 05-Dec-21 16-Dec-21 30% 100% 30% 100% 30%
A14900 Vendor Print Preview - Outdoor Lighting 26 19-Dec-21 24-Jan-22 40% 100% 40% 100% 40%
Lightning Protection 261 22-Nov-20 08-Dec-21 6% 100% 6% 100% 6%
A19270 MRQ - Lightning Protection 46 22-Nov-20 26-Jan-21 30% 100% 30% 100% 30%
A19280 TBE - Lightning Protection 31 10-Feb-21 24-Mar-21 30% 100% 30% 100% 30%
A19290 Vendor Print Preview - Lightning Protection 95 26-Jul-21 08-Dec-21 40% 100% 40% 100% 40%
Cable Trays 201 20-Apr-21 13-Feb-22 6% 100% 6% 100% 6%
A19300 MRQ - Cable Trays 45 20-Apr-21 24-Jun-21 30% 100% 30% 100% 30%
A19310 TBE - Cable Trays 61 29-Aug-21 23-Nov-21 30% 100% 30% 100% 30%
A19320 Vendor Print Preview - Cable Trays 45 09-Dec-21 13-Feb-22 40% 100% 40% 100% 40%
Cables (OSBL) 101 05-Sep-21 27-Jan-22 6% 100% 6% 100% 6%
A8630 MRQ- Cables (OSBL) 10 05-Sep-21 16-Sep-21 40% 100% 40% 100% 40%
A14870 TBE - Cables (OSBL) 45 03-Oct-21 06-Dec-21 30% 100% 30% 100% 30%
A14910 Vendor Print Preview- Cables (OSBL) 25 22-Dec-21 27-Jan-22 30% 100% 30% 100% 30%
Cables (ISBL) 200 20-Apr-21 10-Feb-22 6% 100% 6% 100% 6%
A8632 MRQ- Cables (ISBL) 45 20-Apr-21 24-Jun-21 40% 100% 40% 100% 40%
A14875 TBE - Cables (ISBL) 30 25-Jul-21 05-Sep-21 30% 100% 30% 100% 30%
A14915 Vendor Print Preview - Cables (ISBL) 71 02-Nov-21 10-Feb-22 30% 100% 30% 100% 30%
MV Switchgear 316 15-Oct-20 20-Jan-22 7% 100% 7% 100% 7%
A7090 MRQ - MV Switchgear 37 15-Oct-20 07-Dec-20 30% 100% 30% 100% 30%
A14850 TBE - MV Switchgear 94 22-Dec-20 06-May-21 30% 100% 30% 100% 30%
A14890 Vendor Print Preview - MV Switchgear 49 14-Nov-21 20-Jan-22 40% 100% 40% 100% 40%
LV Switchgear and Capacitor Banks 140 21-Jun-21 13-Jan-22 7% 100% 7% 100% 7%
A7091 MRQ - LV Switchgear and capacitor banks 37 21-Jun-21 18-Aug-21 30% 100% 30% 100% 30%

Page 153 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
A14851 TBE - LV Switchgear and capacitor banks 30 08-Sep-21 21-Oct-21 30% 100% 30% 100% 30%
A14891 Vendor Print Preview - LV Switchgear and capacitor banks 48 08-Nov-21 13-Jan-22 40% 100% 40% 100% 40%
Transformer 287 15-Oct-20 09-Dec-21 7% 100% 7% 100% 7%
A7092 MRQ - Transformers 37 15-Oct-20 07-Dec-20 30% 100% 30% 100% 30%
A14852 TBE - Transformers 50 22-Dec-20 03-Mar-21 30% 100% 30% 100% 30%
A14892 Vendor Print Preview - Transformers 95 27-Jul-21 09-Dec-21 40% 100% 40% 100% 40%
AC UPS 307 15-Oct-20 09-Jan-22 6% 100% 6% 100% 6%
A7093 MRQ - AC UPS 37 15-Oct-20 07-Dec-20 31% 100% 31% 100% 31%
A14853 TBE - AC UPS 30 03-Jan-21 15-Feb-21 31% 100% 31% 100% 31%
A14893 Vendor Print Preview - AC UPS 115 27-Jul-21 09-Jan-22 38% 100% 38% 100% 38%
Diesel Emergency Generator 287 15-Oct-20 09-Dec-21 6% 100% 6% 100% 6%
A7094 MRQ - Diesel Emergency Generator 37 15-Oct-20 07-Dec-20 31% 100% 31% 100% 31%
A14854 TBE - Diesel Emergency Generator 42 05-Jan-21 07-Mar-21 31% 100% 31% 100% 31%
A14894 Vendor Print Preview- Diesel Emergency Generator 95 27-Jul-21 09-Dec-21 38% 100% 38% 100% 38%
Distribution Board 220 18-Mar-21 07-Feb-22 7% 100% 7% 100% 7%
A7095 MRQ - Distribution Boards 21 18-Mar-21 15-Apr-21 30% 100% 30% 100% 30%
A14855 TBE - Distribution Boards 79 21-Jun-21 19-Oct-21 30% 100% 30% 100% 30%
A14895 Vendor Print Preview- Distribution Boards 45 05-Dec-21 07-Feb-22 40% 100% 40% 100% 40%
DC UPS 253 17-Dec-20 23-Dec-21 7% 100% 7% 100% 7%
A74520 MRQ - DC UPS 46 17-Dec-20 22-Feb-21 30% 100% 30% 100% 30%
A74530 TBE - DC UPS 21 08-Mar-21 05-Apr-21 30% 100% 30% 100% 30%
A74540 Vendor Print Preview - DC UPS 105 27-Jul-21 23-Dec-21 40% 100% 40% 100% 40%
Lighting Poles 128 25-Jul-21 24-Jan-22 7% 100% 7% 100% 7%
A90760 MRQ - Lighting Poles 40 25-Jul-21 19-Sep-21 30% 100% 30% 100% 30%
A90770 TBE - Lighting Poles 13 04-Oct-21 24-Oct-21 30% 100% 30% 100% 30%
A90780 Vendor Print Preview - Lighting Poles 26 19-Dec-21 24-Jan-22 40% 100% 40% 100% 40%
Production Line Structure (incl. MDF Storage & Lab) 366 27-Aug-20 14-Feb-22 27% 100% 27% 100% 27%
Steel Structure 319 27-Aug-20 07-Dec-21 60% 100% 60% 100% 60%
Plot (1) - MDF Warehouse 44 27-Aug-20 28-Oct-20 11% 100% 11% 100% 11%
ST.050 MRQ - St. Str. for MDF Warehouse (Plot 1) 26 27-Aug-20 01-Oct-20 38% 100% 38% 100% 38%
ST.090 TBE - St. Str. for MDF Warehouse (Plot 1) 17 13-Sep-20 05-Oct-20 24% 100% 24% 100% 24%
ST.100 Vendor Print Preview - St. Str. for MDF Warehouse (Plot 1) 9 18-Oct-20 28-Oct-20 38% 100% 38% 100% 38%
Plot (1) - Matformer 149 24-Mar-21 02-Nov-21 11% 100% 11% 100% 11%
ST.570 MRQ - St. Str. for Matformer (Plot 1) 26 24-Mar-21 29-Apr-21 38% 100% 38% 100% 38%
ST.580 TBE - St. Str. for Matformer (Plot 1) 18 12-Sep-21 05-Oct-21 24% 100% 24% 100% 24%
ST.590 Vendor Print Preview - St. Str. for Matformer (Plot 1) 9 21-Oct-21 02-Nov-21 38% 100% 38% 100% 38%
Plot (2) 93 12-Apr-21 31-Aug-21 11% 100% 11% 100% 11%
ST.390 MRQ - St. Str. for Dryer & Sifting Process (Plot 2) 5 12-Apr-21 18-Apr-21 38% 100% 38% 100% 38%
ST.400 TBE - St. Str. for Dryer & Sifting Process (Plot 2) 26 23-Jun-21 04-Aug-21 24% 100% 24% 100% 24%
Vendor Print Preview - St. Str. for Dryer & Sifting Process (Plot
ST.410 9 19-Aug-21 31-Aug-21 38% 100% 38% 100% 38%
2)
Plot (3) 25 01-Jul-21 11-Aug-21 11% 100% 11% 100% 11%
ST.450 MRQ - St. Str. for Silo area (Plot 3) 14 01-Jul-21 26-Jul-21 38% 100% 38% 100% 38%
ST.460 TBE - St. Str. for Silo area (Plot 3) 7 07-Jul-21 15-Jul-21 24% 100% 24% 100% 24%
ST.470 Vendor Print Preview - St. Str. for Silo area (Plot 3) 8 01-Aug-21 11-Aug-21 38% 100% 38% 100% 38%
Plot (4) 27 01-Jul-21 15-Aug-21 11% 100% 11% 100% 11%
ST.480 MRQ - St. Str. for Storage Bin (Plot 4) 14 01-Jul-21 26-Jul-21 38% 100% 38% 100% 38%
ST.490 TBE - St. Str. for Storage Bin (Plot 4) 7 07-Jul-21 15-Jul-21 24% 100% 24% 100% 24%
ST.500 Vendor Print Preview - St. Str. for Storage Bin (Plot 4) 10 01-Aug-21 15-Aug-21 38% 100% 38% 100% 38%
Plot (5) 25 01-Jul-21 11-Aug-21 11% 100% 11% 100% 11%
ST.510 MRQ - St. Str. for Screening Area (Plot 5) 14 01-Jul-21 26-Jul-21 38% 100% 38% 100% 38%
ST.520 TBE - St. Str. for Screening Area (Plot 5) 7 07-Jul-21 15-Jul-21 24% 100% 24% 100% 24%
ST.530 Vendor Print Preview - St. Str. for Screening Area (Plot 5) 8 01-Aug-21 11-Aug-21 38% 100% 38% 100% 38%
Plot (6) 121 16-Nov-20 09-May-21 11% 100% 11% 100% 11%
ST.560 MRQ - St. Str. for Straw Preparation (Plot 6) 42 16-Nov-20 13-Jan-21 38% 100% 38% 100% 38%
ST.540 TBE - St. Str. for Straw Preparation (Plot 6) 10 28-Mar-21 08-Apr-21 38% 100% 38% 100% 38%
ST.550 Vendor Print Preview - St. Str. for Straw Preparation (Plot 6) 10 22-Apr-21 09-May-21 24% 100% 24% 100% 24%
Plot (7) 27 01-Jul-21 15-Aug-21 11% 100% 11% 100% 11%
ST.420 MRQ - St. Str. for Dryer & Blending (Plot 7) 14 01-Jul-21 26-Jul-21 38% 100% 38% 100% 38%
ST.430 TBE - St. Str. for for Dryer & Blending (Plot 7) 7 07-Jul-21 15-Jul-21 24% 100% 24% 100% 24%
ST.440 Vendor Print Preview - St. Str. for Dryer & Blending (Plot 7) 10 01-Aug-21 15-Aug-21 38% 100% 38% 100% 38%
Remaining Prod. Line 82 12-Aug-21 07-Dec-21 11% 100% 11% 100% 11%
ST.080 MRQ - St. Str. - Remaining Production Line 35 12-Aug-21 29-Sep-21 38% 100% 38% 100% 38%

Page 154 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
ST.095 TBE - St. Str. - Remaining Production Line 26 28-Oct-21 02-Dec-21 24% 100% 24% 100% 24%
ST.110 Vendor Print Preview - St. Str. - Remaining Production Line 3 05-Dec-21 07-Dec-21 38% 100% 38% 100% 38%
Electrical 226 21-Feb-21 18-Jan-22 13% 100% 13% 100% 13%
MRQ-008 125 18-Jul-21 18-Jan-22 50% 100% 50% 100% 50%
ST.640 MRQ - Electrical - Prod. Line 17 18-Jul-21 16-Aug-21 30% 100% 30% 100% 30%
ST.650 TBE - Electrical - Prod. Line 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
ST.660 Vendor Print Preview - Electrical - Prod. Line 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
MRQ-018 226 21-Feb-21 18-Jan-22 50% 100% 50% 100% 50%
ST.160 MRQ - Electrical - Prod. Line 17 21-Feb-21 15-Mar-21 30% 100% 30% 100% 30%
ST.200 TBE - Electrical - Prod. Line 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
ST.240 Vendor Print Preview - Electrical - Prod. Line 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 223 22-Mar-21 14-Feb-22 3% 100% 3% 100% 3%
ST.170 MRQ - Telecomm. - Prod. Line 32 22-Mar-21 06-May-21 30% 100% 30% 100% 30%
ST.210 TBE - Telecomm. - Prod. Line 73 12-Aug-21 24-Nov-21 30% 100% 30% 100% 30%
ST.250 Vendor Print Preview - Telecomm. - Prod. Line 45 12-Dec-21 14-Feb-22 40% 100% 40% 100% 40%
HVAC 192 05-Apr-21 13-Jan-22 24% 100% 24% 100% 24%
Production Line 192 05-Apr-21 13-Jan-22 29% 100% 29% 100% 29%
ST.190 MRQ - HVAC - Prod. Line 31 05-Apr-21 20-May-21 30% 100% 30% 100% 30%
ST.230 TBE - HVAC - Prod. Line 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
ST.270 Vendor Print Preview - HVAC - Prod. Line 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Straw Building 163 19-May-21 13-Jan-22 29% 100% 29% 100% 29%
ST.670 MRQ - HVAC - Straw Building 23 19-May-21 20-Jun-21 30% 100% 30% 100% 30%
ST.680 TBE - HVAC - Straw Building 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
ST.690 Vendor Print Preview - HVAC - Straw Building 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Refining Building 163 19-May-21 13-Jan-22 29% 100% 29% 100% 29%
ST.720 MRQ - HVAC - Refining Building 23 19-May-21 20-Jun-21 30% 100% 30% 100% 30%
ST.700 TBE - HVAC - Refining Building 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
ST.710 Vendor Print Preview - HVAC - Refining Building 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Contiroll Press 110 10-Aug-21 13-Jan-22 14% 100% 14% 100% 14%
ST.730 TBE - HVAC - Contiroll Press 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
ST.750 MRQ - HVAC - Contiroll Press 93 10-Aug-21 20-Dec-21 30% 100% 30% 100% 30%
ST.740 Vendor Print Preview - HVAC - Contiroll Press 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Buildings / Warehouses/ Sheds 431 20-Sep-20 14-Jun-22 25% 100% 25% 100% 25%
Administration Building 245 24-Feb-21 20-Feb-22 17% 100% 17% 100% 17%
Electrical 59 24-Feb-21 20-May-21 25% 100% 25% 100% 25%
A8510 MRQ - Electrical - Admin Bldg. 59 24-Feb-21 20-May-21 100% 100% 100% 100% 100%
Telecomm. 59 24-Feb-21 20-May-21 25% 100% 25% 100% 25%
A8520 MRQ - Telecomm.- Admin. Bldg. 59 24-Feb-21 20-May-21 100% 100% 100% 100% 100%
HVAC 59 24-Feb-21 20-May-21 25% 100% 25% 100% 25%
A8540 MRQ - HVAC - Admin Bldg. 59 24-Feb-21 20-May-21 100% 100% 100% 100% 100%
Fire - Fighting 26 13-Jan-22 20-Feb-22 25% 100% 25% 100% 25%
A8530 MRQ - Fire Fighting - Admin. Bldg. 26 13-Jan-22 20-Feb-22 100% 100% 100% 100% 100%
Scale Room 313 10-Nov-20 10-Feb-22 4% 100% 4% 100% 4%
Electrical 297 10-Nov-20 18-Jan-22 33% 100% 33% 100% 33%
A10340 MRQ - Electrical -Scale Room 25 10-Nov-20 14-Dec-20 30% 100% 30% 100% 30%
A15090 TBE - Electrical -Scale Room 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15120 Vendor Print Preview -Electrical-Scale Room 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 313 10-Nov-20 10-Feb-22 33% 100% 33% 100% 33%
A10350 MRQ - Telecomm. - Scale Room 25 10-Nov-20 14-Dec-20 30% 100% 30% 100% 30%
A15100 TBE - Telecomm. - Scale Room 45 11-Aug-21 13-Oct-21 30% 100% 30% 100% 30%
A15130 Vendor Print PreviewTelecomm. - Scale Room 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 294 10-Nov-20 13-Jan-22 33% 100% 33% 100% 33%
A10370 MRQ - HVAC- Scale Room 25 10-Nov-20 14-Dec-20 30% 100% 30% 100% 30%
A15110 TBE - HVAC - Scale Room 39 24-Aug-21 19-Oct-21 30% 100% 30% 100% 30%
A15140 Vendor Print Preview -HVAC- Scale Room 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
HSE Building 357 07-Oct-20 13-Mar-22 7% 100% 7% 100% 7%
Steel Structure 313 09-Dec-20 13-Mar-22 36% 100% 36% 100% 36%
A19240 MRQ - Steel Str. - HSE Bldg. (Car Parking Shed) 54 09-Dec-20 24-Feb-21 30% 100% 30% 100% 30%
A19250 TBE - Steel Str. - HSE Bldg. (Car Parking Shed) 9 20-Feb-22 02-Mar-22 30% 100% 30% 100% 30%
Vendor Print Preview - Steel Str. - HSE Bldg. (Car Parking
A19260 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%
Shed)
Electrical 320 07-Oct-20 18-Jan-22 26% 100% 26% 100% 26%
A10670 MRQ - Electrical - HSE Bldg. 22 07-Oct-20 08-Nov-20 30% 100% 30% 100% 30%

Page 155 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
A15150 TBE - Electrical - HSE Bldg. 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15180 Vendor Print Preview - Electrical- HSE Bldg. 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 336 07-Oct-20 10-Feb-22 26% 100% 26% 100% 26%
A10680 MRQ - Telecomm.- HSE Bldg. 22 07-Oct-20 08-Nov-20 30% 100% 30% 100% 30%
A15160 TBE - Telecomm.- HSE Bldg. 45 11-Aug-21 13-Oct-21 30% 100% 30% 100% 30%
A15190 Vendor Print Preview - Telecomm.- HSE Bldg. 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 311 15-Oct-20 13-Jan-22 12% 100% 12% 100% 12%
A10700 MRQ - HVAC - HSE Bldg. 23 15-Oct-20 17-Nov-20 30% 100% 30% 100% 30%
A15170 TBE - HVAC- HSE Bldg. 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A15200 Vendor Print Preview - HVAC- HSE Bldg. 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
New Switch Room 159 25-May-21 13-Jan-22 2% 100% 2% 100% 2%
HVAC 159 25-May-21 13-Jan-22 100% 100% 100% 100% 100%
A90630 MRQ - HVAC - New Switch Room 21 25-May-21 22-Jun-21 30% 100% 30% 100% 30%
A90640 TBE - HVAC- New Switch Room 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A90650 Vendor Print Preview - HVAC- New Switch Room 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Spare Part Warehouse 179 24-May-21 10-Feb-22 2% 100% 2% 100% 2%
Telecom. 179 24-May-21 10-Feb-22 100% 100% 100% 100% 100%
A90660 MRQ - Telecom.- Spare Part Warehouse 42 24-May-21 27-Jul-21 30% 100% 30% 100% 30%
A90670 TBE - Telecom.- Spare Part Warehouse 11 12-Aug-21 26-Aug-21 30% 100% 30% 100% 30%
A90680 Vendor Print Preview - Telecom.- Spare Part Warehouse 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
Main Security Room 319 02-Nov-20 10-Feb-22 4% 100% 4% 100% 4%
Electrical 303 02-Nov-20 18-Jan-22 31% 100% 31% 100% 31%
A10560 MRQ - Electrical - Main Security Room 5 02-Nov-20 08-Nov-20 30% 100% 30% 100% 30%
A15210 TBE - Electrical - Main Security Room 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15240 Vendor Print Preview - Electrical- Main Security Room 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 319 02-Nov-20 10-Feb-22 31% 100% 31% 100% 31%
A10570 MRQ - Telecomm.- Main Security Room 5 02-Nov-20 08-Nov-20 30% 100% 30% 100% 30%
A15220 TBE - Telecomm.- Main Security Room 11 11-Aug-21 25-Aug-21 30% 100% 30% 100% 30%
A15250 Vendor Print Preview - Telecomm.- Main Security Room 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 282 26-Nov-20 13-Jan-22 38% 100% 38% 100% 38%
A10590 MRQ - HVAC - Main Security Room 37 26-Nov-20 18-Jan-21 30% 100% 30% 100% 30%
A15230 TBE - HVAC - Main Security Room 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A15260 Vendor Print Preview - HVAC - Main Security Room 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Security Room 330 15-Oct-20 10-Feb-22 4% 100% 4% 100% 4%
Electrical 314 15-Oct-20 18-Jan-22 31% 100% 31% 100% 31%
A9790 MRQ - Electrical - Security Room 16 15-Oct-20 08-Nov-20 30% 100% 30% 100% 30%
A15270 TBE - Electrical - Security Room 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15300 Vendor Print Preview - Electrical - Security Room 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 330 15-Oct-20 10-Feb-22 31% 100% 31% 100% 31%
A9800 MRQ - Telecomm. - Security Room 16 15-Oct-20 08-Nov-20 30% 100% 30% 100% 30%
A15280 TBE - Telecomm. - Security Room 11 11-Aug-21 25-Aug-21 30% 100% 30% 100% 30%
A15310 Vendor Print Preview - Telecomm. - Security Room 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 290 16-Nov-20 13-Jan-22 38% 100% 38% 100% 38%
A9820 MRQ - HVAC - Security Room 2 16-Nov-20 17-Nov-20 30% 100% 30% 100% 30%
A15290 TBE - HVAC - Security Room 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A15320 Vendor Print Preview - HVAC - Security Room 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Mosque 289 14-Dec-20 10-Feb-22 14% 100% 14% 100% 14%
Electrical 273 14-Dec-20 18-Jan-22 33% 100% 33% 100% 33%
A9900 MRQ - Electrical - Mosque 45 14-Dec-20 16-Feb-21 30% 100% 30% 100% 30%
A15330 TBE - Electrical - Mosque 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15360 Vendor Print Preview - Electrical - Mosque 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 289 14-Dec-20 10-Feb-22 33% 100% 33% 100% 33%
A9910 MRQ - Telecomm. - Mosque 45 14-Dec-20 16-Feb-21 30% 100% 30% 100% 30%
A15340 TBE - Telecomm. - Mosque 15 12-Aug-21 01-Sep-21 30% 100% 30% 100% 30%
A15370 Vendor Print Preview - Telecomm. - Mosque 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 270 14-Dec-20 13-Jan-22 33% 100% 33% 100% 33%
A9930 MRQ - HVAC - Mosque 45 14-Dec-20 16-Feb-21 30% 100% 30% 100% 30%
A15350 TBE - HVAC - Mosque 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A15380 Vendor Print Preview - HVAC - Mosque 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Permanent TCF 348 20-Sep-20 10-Feb-22 9% 100% 9% 100% 9%
Electrical 328 24-Sep-20 18-Jan-22 25% 100% 25% 100% 25%
A9975 MRQ - Electrical - Permanent TCF 20 24-Sep-20 22-Oct-20 30% 100% 30% 100% 30%

Page 156 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
A15390 TBE - Electrical - Permanent TCF 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15420 Vendor Print Preview - Electrical - Permanent TCF 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 344 24-Sep-20 10-Feb-22 51% 100% 51% 100% 51%
A9980 MRQ - Telecomm. - Permanent TCF 20 24-Sep-20 22-Oct-20 30% 100% 30% 100% 30%
A15400 TBE - Telecomm. - Permanent TCF 11 11-Aug-21 25-Aug-21 30% 100% 30% 100% 30%
A15430 Vendor Print Preview -Telecomm. - Permanent TCF 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 329 20-Sep-20 13-Jan-22 24% 100% 24% 100% 24%
A9990 MRQ - HVAC - Permanent TCF 20 20-Sep-20 18-Oct-20 30% 100% 30% 100% 30%
A15410 TBE - HVAC - Permanent TCF 15 24-Aug-21 13-Sep-21 30% 100% 30% 100% 30%
A15440 Vendor Print Preview -HVAC - Permanent TCF 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Substation Building 265 18-Jan-21 10-Feb-22 7% 100% 7% 100% 7%
Electrical 249 18-Jan-21 18-Jan-22 51% 100% 51% 100% 51%
A10230 MRQ - Electrical - Substation Bldg. 57 18-Jan-21 07-Apr-21 30% 100% 30% 100% 30%
A15490 TBE - Electrical - Substation Bldg. 24 31-Aug-21 03-Oct-21 30% 100% 30% 100% 30%
A15530 Vendor Print Preview - Electrical - Substation Bldg. 27 12-Dec-21 18-Jan-22 40% 100% 40% 100% 40%
Telecomm. 265 18-Jan-21 10-Feb-22 26% 100% 26% 100% 26%
A10240 MRQ - Telecomm. - Substation Bldg. 57 18-Jan-21 07-Apr-21 30% 100% 30% 100% 30%
A15500 TBE - Telecomm. - Substation Bldg. 11 11-Aug-21 25-Aug-21 30% 100% 30% 100% 30%
A15540 Vendor Print Preview - Telecomm. - Substation Bldg. 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
HVAC 246 18-Jan-21 13-Jan-22 23% 100% 23% 100% 23%
A10260 MRQ - HVAC - Substation Bldg. 57 18-Jan-21 07-Apr-21 30% 100% 30% 100% 30%
A15520 TBE - HVAC - Substation Bldg. 19 24-Aug-21 19-Sep-21 30% 100% 30% 100% 30%
A15560 Vendor Print Preview - HVAC - Substation Bldg. 26 08-Dec-21 13-Jan-22 40% 100% 40% 100% 40%
Liquid Chemical Warehouse 249 10-Feb-21 10-Feb-22 5% 100% 5% 100% 5%
Steel Structure 198 14-Feb-21 01-Dec-21 33% 100% 33% 100% 33%
A10730 MRQ - Steel Str. - Liquid Chemical Wh 62 14-Feb-21 12-May-21 30% 100% 30% 100% 30%
A15610 TBE - Steel Str. - Liquid Chemical Wh 10 25-Oct-21 07-Nov-21 30% 100% 30% 100% 30%
A15660 Vendor Print Preview -Steel Str. - Liquid Chemical Wh 9 21-Nov-21 01-Dec-21 40% 100% 40% 100% 40%
Electrical 221 10-Feb-21 30-Dec-21 33% 100% 33% 100% 33%
A10450 MRQ - Electrical - Liquid Chemical Wh 64 10-Feb-21 12-May-21 30% 100% 30% 100% 30%
A15570 TBE - Electrical - Liquid Chemical Wh 15 14-Oct-21 04-Nov-21 30% 100% 30% 100% 30%
A15620 Vendor Print Preview - Electrical - Liquid Chemical Wh 29 22-Nov-21 30-Dec-21 40% 100% 40% 100% 40%
Telecomm. 249 10-Feb-21 10-Feb-22 33% 100% 33% 100% 33%
A10460 MRQ - Telecomm. - Liquid Chemical Wh 64 10-Feb-21 12-May-21 30% 100% 30% 100% 30%
A15580 TBE - Telecomm. - Liquid Chemical Wh 11 11-Aug-21 25-Aug-21 30% 100% 30% 100% 30%
A15630 Vendor Print Preview -Telecomm. - Liquid Chemical Wh 43 12-Dec-21 10-Feb-22 40% 100% 40% 100% 40%
Workshop & Lockers 44 04-Jul-21 08-Sep-21 5% 100% 5% 100% 5%
Building 14 04-Jul-21 27-Jul-21 33% 100% 33% 100% 33%
A9710 MRQ - Building. - Workshop & Lockers 14 04-Jul-21 27-Jul-21 100% 100% 100% 100% 100%
Telecom. 14 04-Jul-21 27-Jul-21 33% 100% 33% 100% 33%
A9690 MRQ - Telecom. - Workshop & Lockers 14 04-Jul-21 27-Jul-21 100% 100% 100% 100% 100%
HVAC 25 04-Aug-21 08-Sep-21 33% 100% 33% 100% 33%
A9700 MRQ - Fire Fighting- Workshop & Spare Parts Wh 25 04-Aug-21 08-Sep-21 100% 100% 100% 100% 100%
Fire Pump Shed 69 13-Feb-22 25-May-22 3% 100% 3% 100% 3%
Steel Structure 21 13-Feb-22 13-Mar-22 50% 100% 50% 100% 50%
A9580 MRQ - Steel Str. - Fire Pump Shed 5 13-Feb-22 17-Feb-22 30% 100% 30% 100% 30%
A15760 TBE - Steel Str. - Fire Pump Shed 5 20-Feb-22 24-Feb-22 30% 100% 30% 100% 30%
A15780 Vendor Print Preview -Steel Str. - Fire Pump Shed 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%
Electrical 69 13-Feb-22 25-May-22 50% 100% 50% 100% 50%
A9570 MRQ - Electrical - Fire Pump Shed 9 13-Feb-22 23-Feb-22 30% 100% 30% 100% 30%
A15750 TBE - Electrical - Fire Pump Shed 5 24-Feb-22 02-Mar-22 30% 100% 30% 100% 30%
A15770 Vendor Print Preview - Electrical - Fire Pump Shed 55 03-Mar-22 25-May-22 40% 100% 40% 100% 40%
Car Parking Shed 109 07-Oct-21 13-Mar-22 2% 100% 2% 100% 2%
Steel Structure 109 07-Oct-21 13-Mar-22 100% 100% 100% 100% 100%
A90710 MRQ - Steel Str. - Car Parking Shed 17 07-Oct-21 01-Nov-21 30% 100% 30% 100% 30%
A90720 TBE - Steel Str. - Car Parking Shed 5 20-Feb-22 24-Feb-22 30% 100% 30% 100% 30%
A90730 Vendor Print Preview -Steel Str. - Car Parking Shed 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%
Air Compressor Shed 85 21-Dec-21 20-Apr-22 6% 100% 6% 100% 6%
Steel Structure 37 19-Jan-22 13-Mar-22 35% 100% 35% 100% 35%
A9480 MRQ - Steel Str.- Air Comp. Bldg. 14 19-Jan-22 08-Feb-22 30% 100% 30% 100% 30%
A15810 TBE - Steel Str.- Air Comp. Bldg. 9 20-Feb-22 02-Mar-22 30% 100% 30% 100% 30%
A15840 Vendor Print Preview -Steel Str.- Air Comp. Bldg. 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%

Page 157 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
Electrical 85 21-Dec-21 20-Apr-22 33% 100% 33% 100% 33%
A9460 MRQ - Electrical - Air Comp. Bldg. 5 21-Dec-21 27-Dec-21 30% 100% 30% 100% 30%
A15790 TBE - Electrical - Air Comp. Bldg. 5 28-Dec-21 03-Jan-22 30% 100% 30% 100% 30%
A15820 Vendor Print Preview - Electrical - Air Comp. Bldg. 75 04-Jan-22 20-Apr-22 40% 100% 40% 100% 40%
Telecomm. 65 19-Jan-22 20-Apr-22 33% 100% 33% 100% 33%
A9470 MRQ - Telecomm.- Air Comp. Bldg. 21 19-Jan-22 17-Feb-22 30% 100% 30% 100% 30%
A15800 TBE - Telecomm.- Air Comp. Bldg. 16 20-Feb-22 13-Mar-22 30% 100% 30% 100% 30%
A15830 Vendor Print Preview -Telecomm.- Air Comp. Bldg. 28 14-Mar-22 20-Apr-22 40% 100% 40% 100% 40%
Industrial Pump Station 57 18-Jan-22 07-Apr-22 4% 100% 4% 100% 4%
Steel Structure 38 18-Jan-22 13-Mar-22 50% 100% 50% 100% 50%
A9420 MRQ - Steel Str. - Industrial Pump Station 5 18-Jan-22 24-Jan-22 30% 100% 30% 100% 30%
A15860 TBE - Steel Str. - Industrial Pump Station 5 20-Feb-22 24-Feb-22 30% 100% 30% 100% 30%
A15880 Vendor Print Preview - Steel Str. - Industrial Pump Station 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%
Electrical 53 24-Jan-22 07-Apr-22 50% 100% 50% 100% 50%
A9350 MRQ - Electrical - Industrial Pump Station 5 24-Jan-22 31-Jan-22 30% 100% 30% 100% 30%
A15850 TBE - Electrical - Industrial Pump Station 5 01-Feb-22 07-Feb-22 30% 100% 30% 100% 30%
A15870 Vendor Print Preview -Electrical - Industrial Pump Station 43 08-Feb-22 07-Apr-22 40% 100% 40% 100% 40%
Potable water pump station 45 03-Feb-22 06-Apr-22 5% 100% 5% 100% 5%
Steel Structure 27 03-Feb-22 13-Mar-22 50% 100% 50% 100% 50%
A9050 MRQ - Steel Str. - Potable Water Pump Station 5 03-Feb-22 09-Feb-22 30% 100% 30% 100% 30%
A15980 TBE - Steel Str. - Potable Water Pump Station 5 20-Feb-22 24-Feb-22 30% 100% 30% 100% 30%
A16000 Vendor Print Preview -Steel Str. - Potable Water Pump Station 1 13-Mar-22 13-Mar-22 40% 100% 40% 100% 40%
Electrical 33 21-Feb-22 06-Apr-22 50% 100% 50% 100% 50%
A9020 MRQ - Electrical - Potable Water Pump Station 5 21-Feb-22 27-Feb-22 30% 100% 30% 100% 30%
A15970 TBE - Electrical - Potable Water Pump Station 5 01-Mar-22 07-Mar-22 30% 100% 30% 100% 30%
A15990 Vendor Print Preview -Electrical - Potable Water Pump Station 22 08-Mar-22 06-Apr-22 40% 100% 40% 100% 40%
Fuel Station 173 04-Oct-21 14-Jun-22 3% 100% 3% 100% 3%
A82410 MRQ - Fuel Station 50 04-Oct-21 14-Dec-21 30% 100% 30% 100% 30%
A89400 TBE - Fuel Station 22 29-Dec-21 31-Jan-22 30% 100% 30% 100% 30%
A89410 Vendor Print Preview - Fuel Station 70 02-Mar-22 14-Jun-22 40% 100% 40% 100% 40%
Overhead Cranes 296 02-Dec-20 09-Feb-22 2% 100% 2% 100% 2%
CP.210 MRQ - Overhead Cranes 54 02-Dec-20 17-Feb-21 31% 100% 31% 100% 31%
CP.220 TBE - Overhead Cranes 14 07-Mar-21 24-Mar-21 15% 100% 15% 100% 15%
CP.230 Vendor Print Preview - Overhead Cranes 151 01-Jul-21 09-Feb-22 54% 100% 54% 100% 54%
Logistics ( For ISBL - EP CONTRACTOR SOW Delivery ) 206 06-Mar-21 27-Sep-21 100% 100% 100% 100% 100%
Custom Clerance 205 06-Mar-21 26-Sep-21 50% 100% 50% 100% 50%
A16720 Shipment (01) 7 06-Mar-21 12-Mar-21 3% 100% 3% 100% 3%
A78130 Shipment (02) 7 13-Mar-21 19-Mar-21 3% 100% 3% 100% 3%
A78140 Shipment (03) 7 20-Mar-21 26-Mar-21 3% 100% 3% 100% 3%
A78150 Shipment (04) 7 27-Mar-21 02-Apr-21 3% 100% 3% 100% 3%
A78160 Shipment (05) 7 03-Apr-21 09-Apr-21 3% 100% 3% 100% 3%
A78170 Shipment (06) 7 10-Apr-21 16-Apr-21 3% 100% 3% 100% 3%
A78180 Shipment (07) 7 17-Apr-21 23-Apr-21 3% 100% 3% 100% 3%
A78190 Shipment (08) 7 24-Apr-21 30-Apr-21 3% 100% 3% 100% 3%
A78200 Shipment (09) 7 01-May-21 07-May-21 3% 100% 3% 100% 3%
A78210 Shipment (10) 7 08-May-21 14-May-21 3% 100% 3% 100% 3%
A78220 Shipment (11) 7 15-May-21 21-May-21 3% 100% 3% 100% 3%
A78230 Shipment (12) 7 22-May-21 28-May-21 3% 100% 3% 100% 3%
A78240 Shipment (13) 7 29-May-21 04-Jun-21 3% 100% 3% 100% 3%
A78250 Shipment (14) 7 05-Jun-21 11-Jun-21 3% 100% 3% 100% 3%
A78260 Shipment (15) 7 12-Jun-21 18-Jun-21 3% 100% 3% 100% 3%
A78270 Shipment (16) 7 19-Jun-21 25-Jun-21 3% 100% 3% 100% 3%
A78280 Shipment (17) 7 26-Jun-21 02-Jul-21 3% 100% 3% 100% 3%
A78290 Shipment (18) 7 03-Jul-21 09-Jul-21 3% 100% 3% 100% 3%
A86940 Shipment (19) 7 10-Jul-21 16-Jul-21 3% 100% 3% 100% 3%
A86950 Shipment (20) 7 17-Jul-21 23-Jul-21 3% 100% 3% 100% 3%
A86960 Shipment (21) 7 24-Jul-21 30-Jul-21 3% 100% 3% 100% 3%
A86970 Shipment (22) 7 31-Jul-21 06-Aug-21 3% 100% 3% 100% 3%
A86980 Shipment (23) 7 07-Aug-21 13-Aug-21 3% 100% 3% 100% 3%
A86990 Shipment (24) 7 14-Aug-21 20-Aug-21 3% 100% 3% 100% 3%
A87000 Shipment (25) 7 21-Aug-21 27-Aug-21 3% 100% 3% 100% 3%
A87010 Shipment (26) 7 28-Aug-21 03-Sep-21 3% 100% 3% 100% 3%

Page 158 of 234


As of 11‐02‐23

Plan Plan Actual


Activity ID Activity Name Dur. R.Wt.
Start Finish Item O.A Item O.A
A87020 Shipment (27) 7 04-Sep-21 10-Sep-21 3% 100% 3% 100% 3%
A87030 Shipment (28) 8 11-Sep-21 18-Sep-21 3% 100% 3% 100% 3%
A90210 Shipment (29) 8 19-Sep-21 26-Sep-21 3% 100% 3% 100% 3%
Transportation 199 13-Mar-21 27-Sep-21 50% 100% 50% 100% 50%
A78300 Shipment (01) 1 13-Mar-21 13-Mar-21 3% 100% 3% 100% 3%
A78310 Shipment (02) 1 20-Mar-21 20-Mar-21 3% 100% 3% 100% 3%
A78320 Shipment (03) 1 27-Mar-21 27-Mar-21 3% 100% 3% 100% 3%
A78330 Shipment (04) 1 03-Apr-21 03-Apr-21 3% 100% 3% 100% 3%
A78340 Shipment (05) 1 10-Apr-21 10-Apr-21 3% 100% 3% 100% 3%
A78350 Shipment (06) 1 17-Apr-21 17-Apr-21 3% 100% 3% 100% 3%
A78360 Shipment (07) 1 24-Apr-21 24-Apr-21 3% 100% 3% 100% 3%
A78370 Shipment (08) 1 01-May-21 01-May-21 3% 100% 3% 100% 3%
A78380 Shipment (09) 1 08-May-21 08-May-21 3% 100% 3% 100% 3%
A78390 Shipment (10) 1 15-May-21 15-May-21 3% 100% 3% 100% 3%
A78400 Shipment (11) 1 22-May-21 22-May-21 3% 100% 3% 100% 3%
A78410 Shipment (12) 1 29-May-21 29-May-21 3% 100% 3% 100% 3%
A78420 Shipment (13) 1 05-Jun-21 05-Jun-21 3% 100% 3% 100% 3%
A78430 Shipment (14) 1 12-Jun-21 12-Jun-21 3% 100% 3% 100% 3%
A78440 Shipment (15) 1 19-Jun-21 19-Jun-21 3% 100% 3% 100% 3%
A78450 Shipment (16) 1 26-Jun-21 26-Jun-21 3% 100% 3% 100% 3%
A78460 Shipment (17) 1 03-Jul-21 03-Jul-21 3% 100% 3% 100% 3%
A78470 Shipment (18) 1 10-Jul-21 10-Jul-21 3% 100% 3% 100% 3%
A87040 Shipment (19) 1 17-Jul-21 17-Jul-21 3% 100% 3% 100% 3%
A87050 Shipment (20) 1 24-Jul-21 24-Jul-21 3% 100% 3% 100% 3%
A87060 Shipment (21) 1 31-Jul-21 31-Jul-21 3% 100% 3% 100% 3%
A87070 Shipment (22) 1 07-Aug-21 07-Aug-21 3% 100% 3% 100% 3%
A87080 Shipment (23) 1 14-Aug-21 14-Aug-21 3% 100% 3% 100% 3%
A87090 Shipment (24) 1 21-Aug-21 21-Aug-21 3% 100% 3% 100% 3%
A87100 Shipment (25) 1 28-Aug-21 28-Aug-21 3% 100% 3% 100% 3%
A87110 Shipment (26) 1 04-Sep-21 04-Sep-21 3% 100% 3% 100% 3%
A87120 Shipment (27) 1 11-Sep-21 11-Sep-21 3% 100% 3% 100% 3%
A87130 Shipment (28) 1 19-Sep-21 19-Sep-21 3% 100% 3% 100% 3%
A90220 Shipment (29) 1 27-Sep-21 27-Sep-21 3% 100% 3% 100% 3%

Page 159 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
MATERIAL SUPPLY 669 01-Sep-20 02-Aug-22 100.0% 100.0% 100.0% 93.2% 93.2%
Piping (Incl. Thermal Oil) 442 28-Jan-21 08-Dec-22 16.3% 100% 16% 96% 16%
Piping Bulk (CS & GALV) 334 28-Jan-21 15-Jan-23 5.7% 100% 6% 99% 6%
A10910 Piping Bulk ( CS & GALV) - RFQ / Bidding 51 28-Jan-21 08-Apr-21 6.0% 100% 6% 100% 6%
A10911 Piping Bulk ( CS & GALV) - Technical Evaluation Approval 1 16-Nov-21 16-Nov-21 16.0% 100% 16% 100% 16%
A10912 Piping Bulk ( CS & GALV) - Commercial Evaluation Approval 5 17-Nov-21 13-Jan-22 6.0% 100% 6% 100% 6%
A10920 Piping Bulk ( CS & GALV) - PO 5 16-Jan-22 13-Feb-22 12.0% 100% 12% 100% 12%
A10921 Piping Bulk ( CS & GALV) - Manufacturing 11 14-Feb-22 30-Apr-22 15.0% 100% 15% 100% 15%
A10922 Piping Bulk ( CS & GALV) - Inspection 1 28-Feb-22 01-May-22 6.0% 100% 6% 100% 6%
A10923 Piping Bulk ( CS & GALV) - RFS 1 11-Mar-22 12-May-22 18.0% 100% 18% 100% 18%
A13900 Piping Bulk Delivery ( CS & GALV) @ Site 14 15-May-22 15-Jan-23 21.0% 100% 21% 95% 20%
Supper Duplex Piping 334 26-Sep-21 26-Sep-22 1.9% 100% 2% 100% 2%
Stainless Steel Piping 334 26-Sep-21 15-Jan-23 2.9% 100% 3% 98% 3%
A10910 Piping Bulk ( SS) - RFQ / Bidding 51 26-Sep-21 07-Dec-21 6.0% 100% 6% 100% 6%
A10911 Piping Bulk ( SS ) - Technical Evaluation Approval 1 08-Dec-21 09-Feb-22 16.0% 100% 16% 100% 16%
A10912 Piping Bulk ( SS ) - Commercial Evaluation Approval 5 10-Feb-22 16-Feb-22 6.0% 100% 6% 100% 6%
A10920 Piping Bulk ( SS ) - PO 5 17-Feb-22 02-Mar-22 12.0% 100% 12% 100% 12%
A10921 Piping Bulk ( SS ) - Manufacturing 11 03-Mar-22 17-May-22 15.0% 100% 15% 100% 15%
A10922 Piping Bulk ( SS ) - Inspection 1 30-Apr-22 30-May-22 6.0% 100% 6% 100% 6%
A10923 Piping Bulk ( SS ) - RFS 1 01-May-22 31-May-22 18.0% 100% 18% 100% 18%
A13900 Piping Bulk Delivery ( SS ) @ Site 14 20-Aug-22 15-Jan-23 21.0% 100% 21% 90% 19%
Piping Bulk (HDPE) 303 17-Mar-21 01-Sep-22 25.2% 100% 25% 100% 25%
Piping Bulk (DIN) 378 28-Jan-21 15-Sep-22 2.9% 100% 3% 100% 3%
Poly Propylene Pipes 378 28-Jan-21 01-Feb-23 0.4% 100% 0% 70% 0%
Poly Propylene Pipes - RFQ / Bidding 38 28-Jan-21 22-Mar-21 6.0% 100% 6% 100% 6%
Poly Propylene Pipes - Technical Evaluation Approval 1 22-Sep-21 22-Sep-21 16.0% 100% 16% 100% 16%
Poly Propylene Pipes - Financial Evaluation Approval 9 23-Sep-21 05-Oct-21 6.0% 100% 6% 100% 6%
Poly Propylene Pipes - PO 17 07-Oct-21 01-Nov-21 12.0% 100% 12% 100% 12%
Poly Propylene Pipes - Manufacturing 83 20-Aug-22 26-Jan-23 15.0% 100% 15% 50% 8%
Poly Propylene Pipes - Inspection 1 27-Jan-23 28-Jan-23 6.0% 100% 6% 50% 3%
Poly Propylene Pipes - RFS 1 29-Jan-23 30-Jan-23 18.0% 100% 18% 50% 9%
Poly Propylene Pipes @ Site 15 31-Jan-23 01-Feb-23 21.0% 100% 21% 50% 11%
Piping Bulk Material Balance (1) - PO 527 378 28-Jan-21 15-Jan-23 20.0% 100% 20% 100% 20%
Piping Bulk Material Balance (2) PO 334 378 28-Jan-21 15-Sep-22 7.9% 100% 8% 100% 8%
Piping Bulk - Other Systems- PO 492 & 493 157 21-Aug-22 07-Mar-23 10.6% 100% 11% 71% 8%
Piping Bulk - Other Systems - RFQ / Bidding 10 21-Aug-22 01-Sep-22 6.0% 100% 6% 100% 6%
Piping Bulk - Other Systems - Technical Evaluation Approval 10 04-Sep-22 15-Sep-22 16.0% 100% 16% 100% 16%
Piping Bulk - Other Systems - Financial Evaluation Approval 3 18-Sep-22 20-Sep-22 6.0% 100% 6% 100% 6%
Piping Bulk - Other Systems - PO 2 21-Sep-22 22-Sep-22 12.0% 100% 12% 100% 12%
Piping Bulk - Other Systems - Manufacturing 94 23-Sep-22 31-Jan-23 15.0% 100% 15% 80% 12%
Piping Bulk - Other Systems - Inspection 63 02-Nov-22 07-Feb-23 6.0% 100% 6% 80% 5%
Piping Bulk - Other Systems - RFS 63 09-Nov-22 14-Feb-23 18.0% 100% 18% 80% 14%
Piping Bulk - Other Systems - @ Site 63 23-Nov-22 07-Mar-23 21.0% 100% 21% 0%
Piping Bulk - HDPE - Filling Line 73 21-Aug-22 01-Feb-23 7.6% 100% 8% 99% 8%
Piping Bulk - HDPE - Feed Line - RFQ / Bidding 12 21-Aug-22 05-Sep-22 6.0% 100% 6% 100% 6%
Piping Bulk - HDPE - Feed Line - Technical Evaluation Approval 12 06-Sep-22 25-Sep-22 16.0% 100% 16% 100% 16%
Piping Bulk - HDPE - Feed Line - Financial Evaluation Approval 3 22-Sep-22 26-Sep-22 6.0% 100% 6% 100% 6%
Piping Bulk - HDPE - Feed Line - PO 3 27-Sep-22 29-Sep-22 12.0% 100% 12% 100% 12%
Piping Bulk - HDPE - Feed Line - Manufacturing 25 30-Sep-22 24-Oct-22 15.0% 100% 15% 100% 15%
Piping Bulk - HDPE - Feed Line - Inspection 1 25-Oct-22 25-Oct-22 6.0% 100% 6% 100% 6%
Piping Bulk - HDPE - Feed Line - RFS 1 26-Oct-22 26-Oct-22 18.0% 100% 18% 100% 18%
Piping Bulk - HDPE - Feed Line - @ Site 6 27-Oct-22 01-Feb-23 21.0% 100% 21% 97% 20%
Connections / Supports 378 28-Jan-21 01-Nov-22 1.1% 100% 1% 100% 1%
Piping Valves (Manual - Ball) 184 13-Oct-21 01-Nov-22 6.9% 100% 7% 100% 7%
Piping Valves (Manual - Gate, Check & Globe) 184 13-Oct-21 03-Feb-23 5.0% 100% 5% 95% 5%
A12870 Piping Valves (Gate, Check & Globe) - RFQ / Bidding 2 13-Oct-21 09-Nov-21 6.0% 100% 6% 100% 6%
A12871 Piping Valves (Gate, Check & Globe) - Technical Evaluation Approval 1 14-Dec-21 28-Feb-22 16.0% 100% 16% 100% 16%
A12872 Piping Valves (Gate, Check & Globe) - Commercial Evaluation Approval 5 01-Mar-22 07-Mar-22 6.0% 100% 6% 100% 6%
A12880 Piping Valves (Gate, Check & Globe) - PO 4 08-Mar-22 14-Mar-22 12.0% 100% 12% 100% 12%
A12881 Piping Valves - (Gate, Check & Globe) - Manufacturing 101 31-Mar-22 15-May-22 15.0% 100% 15% 100% 15%
A12882 Piping Valves - (Gate, Check & Globe) - Inspection 1 03-Sep-22 31-Oct-22 6.0% 100% 6% 100% 6%
A12883 Piping Valves - (Gate, Check & Globe) - RFS 1 29-Aug-22 13-Jan-23 18.0% 100% 18% 100% 18%
A13910 Piping Valves (Gate, Check & Globe) - Delivery @ Site 30 26-Sep-22 03-Feb-23 21.0% 100% 21% 75% 16%
Potable Water Valves 184 13-Oct-21 01-Sep-22 0.1% 100% 0% 100% 0%
Piping Strainer 315 18-Mar-21 13-Apr-22 1.5% 100% 2% 100% 2%
Steam Traps, Valves & Strainers 133 16-Sep-21 12-Apr-22 0.3% 100% 0% 100% 0%

Page 160 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
Mechanical 468 26-Jan-21 15-Nov-22 8.0% 100% 8% 99% 8%
Pumps 246 05-Sep-21 01-Oct-22 6.7% 100% 7% 100% 7%
Air Compressor 427 26-Jan-21 10-Oct-22 24.3% 100% 24% 100% 24%
Industrial Water Treatment PKG. 383 01-Mar-21 01-Feb-23 57.0% 100% 57% 98% 56%
A13240 Industrial Water Treatment PKG - RFQ / Bidding 10 01-Mar-21 14-Mar-21 6.0% 100% 6% 100% 6%
A13241 Industrial Water Treatment PKG - Technical Evaluation Approval 1 05-Apr-21 05-Apr-21 16.0% 100% 16% 100% 16%
A13242 Industrial Water Treatment PKG - Financial Evaluation Approval 8 06-Apr-21 15-Apr-21 6.0% 100% 6% 100% 6%
A13250 Industrial Water Treatment PKG.- PO 144 18-Apr-21 18-Nov-21 12.0% 100% 12% 100% 12%
A13251 Industrial Water Treatment PKG - Manufacturing 88 20-Aug-22 01-Oct-22 15.0% 100% 15% 100% 15%
A13252 Industrial Water Treatment PKG - Inspection 1 19-Sep-22 08-Oct-22 6.0% 100% 6% 100% 6%
A13253 Industrial Water Treatment PKG - RFS 1 26-Sep-22 15-Oct-22 18.0% 100% 18% 100% 18%
A16800 Industrial Water Treatment PKG- Delivery @ Site 30 27-Oct-22 01-Feb-23 21.0% 100% 21% 90% 19%
Chemical Injection Skid 229 28-Nov-21 01-Oct-22 8.6% 100% 9% 100% 9%
Pressure Reduction Skid (PRS) 198 29-Dec-21 15-Jul-22 1.3% 100% 1% 100% 1%
Reject Pump 198 29-Dec-21 15-Jul-22 0.5% 100% 1% 100% 1%
Sewage Pump 198 29-Dec-21 15-Nov-22 1.5% 100% 2% 100% 2%
Sludge Pump 198 29-Dec-21 20-Sep-22 0.1% 100% 0% 100% 0%
Fire & Gas 143 11-Jan-22 14-Feb-23 5.6% 100% 6% 79% 4%
F&G System 143 11-Jan-22 14-Feb-23 100.0% 100% 100% 79% 79%
A16850 F&G System - RFQ / Bidding 10 11-Jan-22 24-Jan-22 6.0% 100% 6% 100% 6%
A16860 F&G System - Technical Evaluation Approval 1 17-Mar-22 17-Mar-22 16.0% 100% 16% 100% 16%
A16870 F&G System - Financial Evaluation Approval 5 20-Mar-22 24-Mar-22 6.0% 100% 6% 100% 6%
FG.20 F&G System - PO 5 27-Mar-22 31-Mar-22 12.0% 100% 12% 100% 12%
FG.21 F&G System - Manufacturing 53 20-Aug-22 05-Feb-23 15.0% 100% 15% 100% 15%
FG.23 F&G System - Inspection 1 20-Aug-22 06-Feb-23 6.0% 100% 6% 100% 6%
FG.25 F&G System - RFS 1 27-Aug-22 07-Feb-23 18.0% 100% 18% 100% 18%
FG.30 F&G System - Delivery @ Site 30 03-Sep-22 14-Feb-23 21.0% 100% 21% 0%

Fire - Fighting 419 15-Mar-21 01-Jan-23 9.3% 100% 9% 87% 8%

Fire Water Pumps 416 15-Mar-21 01-Nov-22 15.2% 100% 15% 100% 15%
Water Spray System & FF Manual Nozzeles 122 01-Dec-21 16-Oct-22 0.9% 100% 1% 100% 1%
FF Equip. (Fire Hydrants, Monitors & Sprinklers) 217 03-Oct-21 15-Mar-23 68.7% 100% 69% 85% 58%
A17200 FF Equipment - RFQ / Bidding 22 03-Oct-21 03-Nov-21 6.0% 100% 6% 100% 6%
A17210 FF Equipment - Technical Evaluation Approval 18 08-Dec-21 07-Feb-22 16.0% 100% 16% 100% 16%
A17220 FF Equipment - Financial Evaluation Approval 4 08-Feb-22 09-Mar-22 6.0% 100% 6% 100% 6%
A17230 FF Equipment - PO 5 10-Mar-22 16-Mar-22 12.0% 100% 12% 100% 12%
A17240 FF Equipment - Manufacturing 79 20-Aug-22 22-Feb-23 15.0% 100% 15% 75% 11%
A17250 FF Equipment - Inspection 1 04-Sep-22 01-Mar-23 6.0% 100% 6% 75% 5%
A17260 FF Equipment - RFS 1 11-Sep-22 08-Mar-23 18.0% 100% 18% 75% 14%
A17270 FF Equipment - Delivery @ Site 30 18-Sep-22 15-Mar-23 21.0% 100% 21% 75% 16%
Fire Fighting Valves 130 13-Dec-21 01-Feb-23 10.7% 100% 11% 95% 10%
A92340 FF Valves - RFQ / Bidding 20 13-Dec-21 10-Jan-22 6.0% 100% 6% 100% 6%
A92350 FF Valves - Technical Evaluation Approval 42 11-Jan-22 10-Mar-22 16.0% 100% 16% 100% 16%
A92360 FF Valves - Commercial Evaluation Approval 5 13-Mar-22 17-Mar-22 6.0% 100% 6% 100% 6%
A92370 FF Valves - PO 5 20-Mar-22 24-Mar-22 12.0% 100% 12% 100% 12%
A92380 FF Valves - Manufacturing 5 20-Aug-22 25-Oct-22 15.0% 100% 15% 100% 15%
A92390 FF Valves - Inspection 0 05-Sep-22 01-Nov-22 6.0% 100% 6% 100% 6%
A92400 FF Valves - RFS 0 12-Sep-22 08-Nov-22 18.0% 100% 18% 100% 18%
A92410 FF Valves - Delivery @ Site 7 15-Sep-22 01-Feb-23 21.0% 100% 21% 75% 16%
Portable Monitors 217 03-Oct-21 01-Jul-23 4.5% 100% 5% 60% 3%
Portable Monitors - RFQ / Bidding 22 03-Oct-21 03-Nov-21 6.0% 100% 6% 100% 6%
Portable Monitors - Technical Evaluation Approval 18 08-Dec-21 07-Feb-22 16.0% 100% 16% 100% 16%
Portable Monitors - Financial Evaluation Approval 4 08-Feb-22 09-Mar-22 6.0% 100% 6% 100% 6%
Portable Monitors - PO 5 10-Mar-22 16-Mar-22 12.0% 100% 12% 100% 12%
Portable Monitors - Manufacturing 79 20-Aug-22 27-May-23 15.0% 100% 15% 33% 5%
Portable Monitors - Inspection 1 22-Dec-22 03-Jun-23 6.0% 100% 6% 33% 2%
Portable Monitors - RFS 1 23-Dec-22 10-Jun-23 18.0% 100% 18% 33% 6%
Portable Monitors - Delivery @ Site 30 01-Dec-22 01-Jul-23 21.0% 100% 21% 33% 7%
Steel Structure 567 01-Sep-20 30-Apr-22 13.8% 100% 14% 100% 14%
Steel Structure for MDF Warehouse (Plot-1) 75 01-Sep-20 14-Nov-20 30.0% 100% 30% 100% 30%
Steel Structure for Matformer, Platforms & Supports (Plot-1) 81 31-Aug-21 19-Nov-21 4.0% 100% 4% 100% 4%
Steel Structure for Spare Parts WH. (Plot-1) 77 19-Jan-22 02-Apr-22 0.1% 100% 0% 100% 0%
Steel Structure for Plot-2 108 13-Jun-21 28-Sep-21 23.0% 100% 23% 100% 23%
Steel Structure for Plot (3, 4, 5 & 7) 99 01-Jul-21 07-Oct-21 30.0% 100% 30% 100% 30%
Steel Structure for Plot-6 156 18-Mar-21 20-Aug-21 6.7% 100% 7% 100% 7%
Steel Structure for Chemical Warehouse 67 11-Nov-21 17-Jan-22 1.1% 100% 1% 100% 1%

Page 161 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
Steel Structure for Air Comp. & Pumps Sheds 37 24-Feb-22 30-Apr-22 0.7% 100% 1% 100% 1%
Other ST. STR. (Handrails) 75 17-Oct-21 30-Dec-21 1.4% 100% 1% 100% 1%
Metal Deck (Plates) 122 15-Aug-21 14-Dec-21 1.0% 100% 1% 100% 1%
Grating & Chq. Plates 77 14-Nov-21 01-Mar-23 1.0% 100% 1% 66% 1%
A89260 Grating & Chq. Plates - RFQ / Bidding 10 14-Nov-21 25-Nov-21 6.0% 100% 6% 100% 6%
A89270 Grating & Chq. Plates - Technical Evaluation Approval 15 28-Nov-21 16-Dec-21 16.0% 100% 16% 100% 16%
A89280 Grating & Chq. Plates - Financial Evaluation Approval 5 19-Dec-21 23-Dec-21 6.0% 100% 6% 100% 6%
A89240 Grating & Chq. Plates - PO 5 26-Dec-21 30-Dec-21 12.0% 100% 12% 100% 12%
A89290 Grating & Chq. Plates - Manufacturing 13 01-Dec-22 26-Feb-23 15.0% 100% 15% 50% 8%
A89300 Grating & Chq. Plates - Inspection 1 10-Dec-22 27-Feb-23 6.0% 100% 6% 40% 2%
A89310 Grating & Chq. Plates - RFS 1 11-Dec-22 28-Feb-23 18.0% 100% 18% 40% 7%
A89250 Grating & Chq. Plates - Delivery @ Site 15 12-Dec-22 01-Mar-23 21.0% 100% 21% 40% 8%
Piping Supports 92 30-Sep-21 30-Dec-21 1.0% 100% 1% 100% 1%

Electrical 450 08-Dec-20 17-Nov-22 28.5% 100% 29% 98% 28%

Small Power (Switches and Sockets) 172 17-Aug-21 01-Apr-22 0.2% 100% 0% 100% 0%

Lighting Fixtures 110 29-Sep-21 15-Oct-22 1.6% 100% 2% 100% 2%


Lighting Fixtures (Explosion Proof) 99 21-Nov-21 15-Sep-22 1.1% 100% 1% 100% 1%
Earthing Material - (Batch-1) - For Prod. Line 253 28-Jan-21 07-Oct-21 1.4% 100% 1% 100% 1%
Earthing Material - For Buildings 176 04-May-21 26-Oct-21 0.6% 100% 1% 100% 1%
Lightning Protection Material 333 27-Jan-21 25-Dec-21 0.5% 100% 1% 100% 1%
MV Switchgear 428 08-Dec-20 15-Oct-22 2.4% 100% 2% 100% 2%
LV Switchgear, Bus Duct 167 19-Aug-21 01-Oct-22 15.5% 100% 16% 100% 16%
Capacitor Banks 167 19-Aug-21 15-Jun-23 2.0% 100% 2% 54% 1%

A17380 Capacitor Banks - RFQ / Bidding 14 19-Aug-21 07-Sep-21 6.0% 100% 6% 100% 6%

A17390 Capacitor Banks - Technical Evaluation Approval 1 24-Oct-21 24-Oct-21 16.0% 100% 16% 100% 16%
A17400 Capacitor Banks - Financial Evaluation Approval 5 25-Oct-21 31-Oct-21 6.0% 100% 6% 100% 6%
A17410 Capacitor Banks - PO 5 01-Nov-21 07-Nov-21 12.0% 100% 12% 100% 12%
A17420 Capacitor Banks - Manufacturing 69 20-Aug-22 02-May-23 15.0% 100% 15% 90% 14%
A17430 Capacitor Banks - Inspection 1 03-May-23 09-May-23 6.0% 100% 6% 0%
A17440 Capacitor Banks - RFS 1 16-May-23 16-May-23 18.0% 100% 18% 0%
A17450 Capacitor Banks - Delivery @ Site 15 17-May-23 15-Jun-23 21.0% 100% 21% 0%
Transformers 384 08-Dec-20 15-Jan-23 3.6% 100% 4% 100% 4%
AC UPS 415 08-Dec-20 15-Feb-23 2.5% 100% 3% 90% 2%
A74380 AC UPS - RFQ / Bidding 18 08-Dec-20 31-Dec-20 6.0% 100% 6% 100% 6%
A74390 AC UPS - Technical Evaluation Approval 1 16-Feb-21 16-Feb-21 16.0% 100% 16% 100% 16%
A74400 AC UPS - Financial Evaluation Approval 37 17-Feb-21 08-Apr-21 6.0% 100% 6% 100% 6%
A74360 AC UPS - PO 69 11-Apr-21 26-Jul-21 12.0% 100% 12% 100% 12%
A74410 AC UPS - Manufacturing 167 27-Jul-21 27-Apr-22 15.0% 100% 15% 100% 15%
A74420 AC UPS - Inspection 1 28-Apr-22 28-Apr-22 6.0% 100% 6% 100% 6%
A74430 AC UPS - RFS 1 29-Apr-22 29-Apr-22 18.0% 100% 18% 100% 18%
A74370 AC UPS - Delivery @ Site 15 24-Sep-22 15-Feb-23 21.0% 100% 21% 50% 11%
DC UPS 322 23-Feb-21 15-Apr-22 0.4% 100% 0% 100% 0%
Emergency Diesel Generator 384 08-Dec-20 01-Jun-23 1.5% 100% 2% 79% 1%
A17620 Generator - RFQ / Bidding 20 08-Dec-20 04-Jan-21 6.0% 100% 6% 100% 6%
A17630 Generator - Technical Evaluation Approval 1 08-Mar-21 08-Mar-21 16.0% 100% 16% 100% 16%
A17640 Generator - Financial Evaluation Approval 47 09-Mar-21 17-May-21 6.0% 100% 6% 100% 6%
A17650 Generator - PO 45 18-May-21 26-Jul-21 12.0% 100% 12% 100% 12%
A17660 Generator - Manufacturing 136 27-Jul-21 28-Apr-22 15.0% 100% 15% 100% 15%
A17670 Generator - Inspection 1 29-Apr-22 29-Apr-22 6.0% 100% 6% 100% 6%
A17680 Generator - RFS 1 30-Apr-22 30-Apr-22 18.0% 100% 18% 100% 18%
A17690 Generator - Delivery @ Site 15 03-May-23 01-Jun-23 21.0% 100% 21% 0%
Distribution Boards 270 31-May-21 01-Feb-23 1.6% 100% 1.6% 79% 1%
A17700 Distribution Boards - RFQ / Bidding 15 31-May-21 20-Jun-21 6.0% 100% 6% 100% 6%
A17710 Distribution Boards - Technical Evaluation Approval 1 20-Oct-21 20-Oct-21 16.0% 100% 16% 100% 16%
A17720 Distribution Boards - Financial Evaluation Approval 26 21-Oct-21 16-Dec-21 6.0% 100% 6% 100% 6%
A17730 Distribution Boards - PO 5 19-Dec-21 02-Feb-22 12.0% 100% 12% 100% 12%
A17740 Distribution Boards - Manufacturing 67 20-Aug-22 11-Jan-23 15.0% 100% 15% 90% 14%
A17750 Distribution Boards - Inspection 1 14-Sep-22 18-Jan-23 6.0% 100% 6% 75% 5%
A17760 Distribution Boards - RFS 1 15-Sep-22 25-Jan-23 18.0% 100% 18% 75% 14%
A17770 Distribution Boards - Delivery @ Site 15 16-Sep-22 01-Feb-23 21.0% 100% 21% 35% 7%
Lighting Poles 145 20-Sep-21 30-Sep-22 1.5% 100% 2% 100% 2%
Electrical MV, Power and Control Cables (OSBL) 150 19-Sep-21 15-Oct-22 30.1% 100% 30% 100% 30%
Cable Trays 200 15-Aug-21 15-Feb-23 7.5% 100% 8% 98% 7%
A11960 Cable Trays - RFQ / Bidding 10 15-Aug-21 26-Aug-21 6.0% 100% 6% 100% 6%

Page 162 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
A11961 Cable Trays - Technical Evaluation Approval 1 02-Dec-21 02-Dec-21 16.0% 100% 16% 100% 16%
A11962 Cable Trays - Financial Evaluation Approval 5 05-Dec-21 12-Jan-22 6.0% 100% 6% 100% 6%
A11965 Cable Trays - PO 5 13-Jan-22 03-Feb-22 12.0% 100% 12% 100% 12%
A14010 Cable Trays - Manufacturing 67 04-Feb-22 06-Apr-22 15.0% 100% 15% 100% 15%
A14011 Cable Trays - Inspection 1 25-Aug-22 11-Oct-22 6.0% 100% 6% 100% 6%
A14012 Cable Trays - RFS 1 28-Aug-22 13-Oct-22 18.0% 100% 18% 100% 18%
A14020 Cable Trays - Delivery @ Site 15 01-Aug-22 15-Feb-23 21.0% 100% 21% 90% 19%
Electrical Power and Control Cables (ISBL) 248 27-Jun-21 16-Mar-22 21.8% 100% 22% 100% 22%
Explosion proof material 201 21-Nov-21 01-Mar-23 2.9% 100% 3% 95% 3%
A92420 Explosion proof material - RFQ / Bidding 15 21-Nov-21 09-Dec-21 6.0% 100% 6% 100% 6%
A92430 Explosion proof material - Technical Evaluation Approval 59 12-Dec-21 06-Mar-22 16.0% 100% 16% 100% 16%
A92440 Explosion proof material - Financial Evaluation Approval 5 07-Mar-22 13-Mar-22 6.0% 100% 6% 100% 6%
A92450 Explosion proof material - PO 5 14-Mar-22 20-Mar-22 12.0% 100% 12% 100% 12%
A92460 Explosion proof material - Manufacturing 33 20-Aug-22 05-Oct-22 15.0% 100% 15% 100% 15%
A92470 Explosion proof material - Inspection 0 05-Sep-22 06-Oct-22 6.0% 100% 6% 100% 6%
A92480 Explosion proof material - RFS 0 06-Sep-22 07-Oct-22 18.0% 100% 18% 100% 18%
A92490 Explosion proof material - Delivery @ Site 3 08-Sep-22 01-Mar-23 21.0% 100% 21% 75% 16%
Cable Glands 248 27-Jun-21 16-Mar-22 1.1% 100% 1% 100% 1%
Electrical Conduits 248 27-Jun-21 16-Mar-22 0.2% 100% 0% 100% 0%
Instrumentation (Control System) 375 05-Apr-21 02-Nov-22 4.8% 100% 4.8% 98% 5%
Control system (DCS) 166 31-Oct-21 15-Feb-23 4.0% 100% 4.0% 79% 3%
A18280 Control System (DCS) - RFQ / Bidding 9 31-Oct-21 10-Nov-21 6.0% 100% 6% 100% 6%
A18290 Control System (DCS) - Technical Evaluation Approval 1 03-Feb-22 03-Feb-22 16.0% 100% 16% 100% 16%
A18300 Control System (DCS) - Financial Evaluation Approval 5 06-Feb-22 01-Mar-22 6.0% 100% 6% 100% 6%
A18310 Control System (DCS) - PO 5 02-Mar-22 08-Mar-22 12.0% 100% 12% 100% 12%
A18320 Control System (DCS) - Manufacturing 95 20-Aug-22 09-Oct-22 15.0% 100% 15% 100% 15%
A18330 Control System (DCS) - Inspection 1 07-Feb-23 07-Feb-23 6.0% 100% 6% 100% 6%
A18340 Control System (DCS) - RFS 1 08-Feb-23 08-Feb-23 18.0% 100% 18% 100% 18%
A18350 Control System (DCS) - Delivery @ Site 15 09-Feb-23 15-Feb-23 21.0% 100% 21% 0%
Mechanical Level Indicator 274 05-Apr-21 01-Nov-22 1.4% 100% 1.4% 100% 1%
Field instrument 152 03-Oct-21 15-Oct-22 13.7% 100% 13.7% 100% 14%
Control valve 192 28-Sep-21 07-Feb-23 4.7% 100% 4.7% 95% 4%
A18360 Control Valves - RFQ / Bidding 15 28-Sep-21 20-Oct-21 6.0% 100% 6% 100% 6%
A18370 Control Valves - Technical Evaluation Approval 1 28-Feb-22 28-Feb-22 16.0% 100% 16% 100% 16%
A18380 Control Valves - Financial Evaluation Approval 5 01-Mar-22 09-Mar-22 6.0% 100% 6% 100% 6%
A18390 Control Valves - PO 4 13-Mar-22 21-Mar-22 12.0% 100% 12% 100% 12%
A18400 Control Valves - Manufacturing 80 20-Aug-22 30-Oct-22 15.0% 100% 15% 100% 15%
A18410 Control Valves - Inspection 1 30-Sep-22 31-Oct-22 6.0% 100% 6% 100% 6%
A18420 Control Valves - RFS 1 01-Oct-22 01-Nov-22 18.0% 100% 18% 100% 18%
A18430 Control Valves - Delivery @ Site 30 02-Oct-22 07-Feb-23 21.0% 100% 21% 75% 16%
On / Off valve 192 28-Sep-21 01-Dec-22 0.3% 100% 0.3% 100% 0%
Flow Meters 199 17-Aug-21 01-Jan-23 2.6% 100% 2.6% 100% 3%
Instrument Cable 143 12-Oct-21 07-Mar-23 38.5% 100% 39% 99% 38%
A18440 Instrument Cables & Glands - RFQ / Bidding 8 12-Oct-21 24-Oct-21 6.0% 100% 6% 100% 6%
A18450 Instrument Cables & Glands - Technical Evaluation Approval 1 13-Jan-22 13-Jan-22 12.0% 100% 12% 100% 12%
A18460 Instrument Cables & Glands - Financial Evaluation Approval 5 16-Jan-22 20-Feb-22 15.0% 100% 15% 100% 15%
A18470 Instrument Cables & Glands - PO 5 21-Feb-22 06-Mar-22 6.0% 100% 6% 100% 6%
A18480 Instrument Cables & Glands - Manufacturing 67 20-Aug-22 07-Oct-22 6.0% 100% 6% 100% 6%
A18490 Instrument Cables & Glands - Inspection 1 20-Aug-22 13-Oct-22 18.0% 100% 18% 100% 18%
A18500 Instrument Cables & Glands - RFS 1 21-Aug-22 14-Oct-22 21.0% 100% 21% 100% 21%
A18510 Instrument Cables & Glands - Delivery @ Site 15 22-Aug-22 07-Mar-23 16.0% 100% 16% 92% 15%
Instrument JB's and Bulk Material 204 12-Aug-21 20-Feb-23 1.7% 100% 1.7% 98% 2%
A74460 Instrument JB's & Bulk Material - RFQ / Bidding 15 12-Aug-21 01-Sep-21 6.0% 100% 6% 100% 6%
A74470 Instrument JB's & Bulk Material - Technical Evaluation Approval 1 17-Oct-21 17-Oct-21 12.0% 100% 12% 100% 12%
A74480 Instrument JB's & Bulk Material - Financial Evaluation Approval 33 19-Oct-21 16-Jan-22 15.0% 100% 15% 100% 15%
A74440 Instrument JB's & Bulk Material - PO 5 17-Jan-22 02-Feb-22 6.0% 100% 6% 100% 6%
A74490 Instrument JB's & Bulk Material - Manufacturing 67 20-Aug-22 15-Oct-22 6.0% 100% 6% 100% 6%
A74500 Instrument JB's & Bulk Material - Inspection 1 14-Sep-22 16-Oct-22 18.0% 100% 18% 100% 18%
A74510 Instrument JB's & Bulk Material - RFS 1 15-Sep-22 17-Oct-22 21.0% 100% 21% 100% 21%
A74450 Instrument JB's & Bulk Material - Delivery @ Site 15 16-Sep-22 20-Feb-23 16.0% 100% 16% 85% 14%
Analyzer 135 13-Oct-21 15-Oct-22 1.7% 100% 1.7% 100% 2%
Utility Instrument cables & Glandes 235 25-Oct-21 22-Oct-22 10.4% 100% 10.4% 100% 10%
Galvanized Conduits 235 25-Oct-21 26-Sep-22 18.7% 100% 18.7% 100% 19%
Instrument bulk material (hook up) 235 25-Oct-21 01-Feb-23 0.6% 100% 0.6% 100% 1%
Fiber Optical Cables (FOC) 235 25-Oct-21 07-Mar-23 1.7% 100% 1.7% 100% 2%
Fiber Optical Cables (FOC) - RFQ / Bidding 28 25-Oct-21 01-Dec-21 6.0% 100% 6% 100% 6%

Page 163 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
Fiber Optical Cables (FOC) - Technical Evaluation Approval 65 02-Dec-21 06-Mar-22 12.0% 100% 12% 100% 12%
Fiber Optical Cables (FOC) - Commercial Evaluation Approval 5 07-Mar-22 13-Mar-22 15.0% 100% 15% 100% 15%
Fiber Optical Cables (FOC) - PO 5 14-Mar-22 20-Mar-22 6.0% 100% 6% 100% 6%
Fiber Optical Cables (FOC) - Manufacturing 33 20-Aug-22 15-Oct-22 6.0% 100% 6% 100% 6%
Fiber Optical Cables (FOC) - Inspection 0 15-Oct-22 15-Oct-22 18.0% 100% 18% 100% 18%
Fiber Optical Cables (FOC) - RFS 0 16-Oct-22 16-Oct-22 21.0% 100% 21% 100% 21%
Fiber Optical Cables (FOC) - Delivery @ Site 7 17-Oct-22 07-Mar-23 16.0% 100% 16% 100% 16%
Telecommunication 346 18-May-21 14-Jan-23 2.7% 100% 2.7% 63% 2%
Fire Alarm & Detection 215 28-Jul-21 01-Mar-23 6.4% 100% 6% 84% 5%
A11550 Fire Alarm & Detection - RFQ / Bidding 9 28-Jul-21 10-Aug-21 6.0% 100% 6% 100% 6%
A11551 Fire Alarm & Detection - Technical Evaluation Approval 1 14-Oct-21 14-Oct-21 16.0% 100% 16% 100% 16%
A11552 Fire Alarm & Detection - Financial Evaluation Approval 5 17-Oct-21 24-Oct-21 6.0% 100% 6% 100% 6%
A11560 Fire Alarm & Detection - PO 30 25-Oct-21 27-Dec-21 12.0% 100% 12% 100% 12%
A18640 Fire Alarm & Detection - Manufacturing 67 20-Aug-22 26-Feb-23 15.0% 100% 15% 80% 12%
A18650 Fire Alarm & Detection - Inspection 1 28-Sep-22 27-Feb-23 6.0% 100% 6% 70% 4%
A18660 Fire Alarm & Detection - RFS 1 29-Sep-22 28-Feb-23 18.0% 100% 18% 70% 13%
A18670 Fire Alarm & Detection - Delivery @ Site 15 30-Sep-22 01-Mar-23 21.0% 100% 21% 70% 15%
IP Telephone 275 28-Jul-21 20-Jun-23 4.2% 100% 4% 78% 3%
A11575 IP Telephone - RFQ / Bidding 9 28-Jul-21 10-Aug-21 6.0% 100% 6% 100% 6%
A11576 IP Telephone - Technical Evaluation Approval 1 14-Oct-21 14-Oct-21 16.0% 100% 16% 100% 16%
A11577 IP Telephone - Financial Evaluation Approval 34 17-Oct-21 02-Dec-21 6.0% 100% 6% 100% 6%
A11580 IP Telephone - PO 5 05-Dec-21 02-Feb-22 12.0% 100% 12% 100% 12%
A18960 IP Telephone - Manufacturing 123 20-Aug-22 17-Jun-23 15.0% 100% 15% 75% 11%
A18970 IP Telephone - Inspection 1 13-Oct-22 18-Jun-23 6.0% 100% 6% 60% 4%
A18980 IP Telephone - RFS 1 14-Oct-22 19-Jun-23 18.0% 100% 18% 60% 11%
A18990 IP Telephone - Delivery @ Site 15 15-Oct-22 20-Jun-23 21.0% 100% 21% 60% 13%
CCTV 304 24-May-21 01-Mar-23 19.2% 100% 19% 74% 14%
A11565 CCTV - RFQ / Bidding 10 24-May-21 06-Jun-21 6.0% 100% 6% 100% 6%
A11567 CCTV - Technical Evaluation Approval 1 14-Oct-21 14-Oct-21 16.0% 100% 16% 100% 16%
A11568 CCTV - Financial Evaluation Approval 5 17-Oct-21 24-Oct-21 6.0% 100% 6% 100% 6%
A11570 CCTV - PO 28 25-Oct-21 27-Dec-21 12.0% 100% 12% 100% 12%
A18800 CCTV - Manufacturing 95 20-Aug-22 25-Feb-23 15.0% 100% 15% 75% 11%
A18810 CCTV - Inspection 1 14-Nov-22 27-Feb-23 6.0% 100% 6% 50% 3%
A18820 CCTV - RFS 1 15-Nov-22 28-Feb-23 18.0% 100% 18% 50% 9%
A18830 CCTV - Delivery @ Site 15 16-Nov-22 01-Mar-23 21.0% 100% 21% 50% 11%
Public Address 219 28-Jul-21 15-Mar-23 10.9% 100% 11% 51% 6%
A11585 Public Address - RFQ / Bidding 10 28-Jul-21 11-Aug-21 6.0% 100% 6% 100% 6%
A11586 Public Address - Technical Evaluation Approval 1 14-Oct-21 14-Oct-21 16.0% 100% 16% 100% 16%
A11587 Public Address - Financial Evaluation Approval 34 17-Oct-21 02-Dec-21 6.0% 100% 6% 100% 6%
A11590 Public Address - PO 5 05-Dec-21 02-Feb-22 12.0% 100% 12% 100% 12%
A18880 Public Address - Manufacturing 67 20-Aug-22 29-Jan-23 15.0% 100% 15% 75% 11%
A18890 Public Address - Inspection 1 30-Jan-23 30-Jan-23 6.0% 100% 6% 0%
A18900 Public Address - RFS 1 15-Feb-23 15-Feb-23 18.0% 100% 18% 0%
A18910 Public Address - Delivery @ Site 15 14-Feb-23 15-Mar-23 21.0% 100% 21% 0%
Data Network 318 18-May-21 01-May-23 22.4% 100% 22% 69% 16%
A87580 Data Network - RFQ / Bidding 9 18-May-21 30-May-21 6.0% 100% 6% 100% 6%
A87590 Data Network - Technical Evaluation Approval 1 25-Nov-21 30-Dec-21 16.0% 100% 16% 100% 16%
A87600 Data Network - Financial Evaluation Approval 5 02-Jan-22 24-Feb-22 6.0% 100% 6% 100% 6%
A87560 Data Network - PO 5 27-Feb-22 09-Mar-22 12.0% 100% 12% 100% 12%
A87610 Data Network - Manufacturing 95 20-Aug-22 14-Apr-23 15.0% 100% 15% 75% 11%
A87620 Data Network - Inspection 1 15-Apr-23 15-Apr-23 6.0% 100% 6% 40% 2%
A87630 Data Network - RFS 1 16-Apr-23 16-Apr-23 18.0% 100% 18% 40% 7%
A87570 Data Network - Delivery @ Site 15 17-Apr-23 01-May-23 21.0% 100% 21% 40% 8%
Data Center 318 18-May-21 01-Mar-23 36.9% 100% 37% 51% 19%
Data Center - RFQ / Bidding 9 18-May-21 30-May-21 6.0% 100% 6% 100% 6%
Data Center - Technical Evaluation Approval 1 25-Nov-21 30-Dec-21 16.0% 100% 16% 100% 16%
Data Center - Financial Evaluation Approval 5 02-Jan-22 24-Feb-22 6.0% 100% 6% 100% 6%
Data Center - PO 5 27-Feb-22 09-Mar-22 12.0% 100% 12% 100% 12%
Data Center - Manufacturing 95 20-Aug-22 28-Jan-23 15.0% 100% 15% 75% 11%
Data Center - Inspection 1 29-Jan-23 29-Jan-23 6.0% 100% 6% 0%
Data Center - RFS 1 30-Jan-23 30-Jan-23 18.0% 100% 18% 0%
Data Center - Delivery @ Site 15 31-Jan-23 01-Mar-23 21.0% 100% 21% 0%
Tanks (OSBL) 389 30-Dec-20 01-Oct-22 1.9% 100% 2% 98% 2%
Tank Plates (Batch-1)- Industrial / Process / DEMI Tanks 109 30-Dec-20 17-Apr-21 66.0% 100% 66% 100% 66%
Tank Plates (Batch-2) - Fire Tanks 62 22-Nov-21 19-Mar-22 28.0% 100% 28% 100% 28%
Potable Water Tank (HDPE) 134 01-Aug-21 01-Mar-23 6.0% 100% 6% 74% 4%

Page 164 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
TK.350 Potable Water Tank (HDPE) - RFQ / Bidding 10 01-Aug-21 15-Aug-21 6.0% 100% 6% 100% 6%
TK.360 Potable Water Tank (HDPE) - Technical Evaluation Approval 30 16-Aug-21 20-Oct-21 16.0% 100% 16% 100% 16%
TK.370 Potable Water Tank (HDPE) - Financial Evaluation Approval 5 21-Oct-21 23-Dec-21 6.0% 100% 6% 100% 6%
TK.380 Potable Water Tank (HDPE) - PO 5 26-Dec-21 01-Mar-22 12.0% 100% 12% 100% 12%
TK.390 Potable Water Tank (HDPE) - Manufacturing 45 29-Aug-22 16-Feb-23 15.0% 100% 15% 75% 11%
TK.400 Potable Water Tank (HDPE) - Inspection 1 14-Sep-22 19-Feb-23 6.0% 100% 6% 50% 3%
TK.410 Potable Water Tank (HDPE) - RFS 1 15-Sep-22 20-Feb-23 18.0% 100% 18% 50% 9%
TK.420 Potable Water Tank (HDPE) - Delivery @ Site 15 16-Sep-22 01-Mar-23 21.0% 100% 21% 50% 11%
Cathodic Protection 326 31-May-21 15-Jun-22 0.2% 100% 0.2% 100% 0%
Cathodic Protection Bulk Materials 108 31-May-21 15-Sep-21 77.0% 100% 77% 100% 77%
Cathodic Protection Internals 205 29-Sep-21 01-Nov-22 23.0% 100% 23% 100% 23%
SUPPLIES & SERVICES AS PER (ATT.2 SEC-6) 499 18-Feb-21 25-Jan-23 8.9% 100% 8.9% 78% 7%
Tanks Accessories (Agitators) 224 21-Sep-21 23-May-22 3.9% 100% 4% 100% 4%
Overhead Cranes 389 18-Feb-21 16-Mar-22 15.0% 100% 15% 100% 15%
Straw Bale Grab 389 18-Feb-21 27-Nov-22 5.6% 100% 6% 100% 6%
Truck Scale 181 16-Sep-21 01-Mar-23 1.7% 100% 2% 90% 2%
A16109 Truck Scale - RFQ / Bidding 10 16-Sep-21 29-Sep-21 6.0% 100% 6% 100% 6%
A16111 Truck Scale - Technical Evaluation & Approval 23 30-Sep-21 03-Nov-21 16.0% 100% 16% 100% 16%
A16112 Truck Scale - Financial Evaluation Approval 5 04-Nov-21 10-Nov-21 6.0% 100% 6% 100% 6%
A16114 Truck Scale - PO 3 11-Nov-21 15-Nov-21 12.0% 100% 12% 100% 12%
A16181 Truck Scale - Manufacturing 88 16-Nov-21 13-Apr-22 15.0% 100% 15% 100% 15%
A16182 Truck Scale - Inspection 1 14-Apr-22 14-Apr-22 6.0% 100% 6% 100% 6%
A16183 Truck Scale - RFS 1 15-Apr-22 15-Apr-22 18.0% 100% 18% 100% 18%
A16198 Truck Scale - Delivery @ Site 30 31-Jan-23 01-Mar-23 21.0% 100% 21% 50% 11%
Mobile Fuel Station 199 13-Jan-22 01-Feb-23 9.1% 100% 9% 79% 7%
A87660 Fuel Station - RFQ / Bidding 10 13-Jan-22 27-Jan-22 6.0% 100% 6% 100% 6%
A87670 Fuel Station - Technical Evaluation Approval 1 02-Mar-22 02-Mar-22 16.0% 100% 16% 100% 16%
A87680 Fuel Station - Financial Evaluation Approval 7 04-Sep-22 12-Sep-22 6.0% 100% 6% 100% 6%
A87640 Fuel Station - PO 13 13-Sep-22 02-Oct-22 12.0% 100% 12% 100% 12%
A87690 Fuel Station - Manufacturing 105 03-Oct-22 29-Dec-22 15.0% 100% 15% 100% 15%
A87700 Fuel Station - Inspection 1 30-Dec-22 30-Dec-22 6.0% 100% 6% 100% 6%
A87710 Fuel Station - RFS 1 31-Dec-22 31-Dec-22 18.0% 100% 18% 100% 18%
A87650 Fuel Station - Delivery @ Site then construction and commissioning 15 01-Jan-23 01-Feb-23 21.0% 100% 21% 0%
Rails (Gr- 1150, 1151, 2310, 2332, 5390, 5419, 5492) 124 13-Dec-21 01-Mar-23 8.4% 100% 8% 92% 8%
A89100 Rails - RFQ / Bidding 10 13-Dec-21 26-Dec-21 6.0% 100% 6% 100% 6%
A89110 Rails - Technical Evaluation Approval 32 27-Dec-21 10-Feb-22 16.0% 100% 16% 100% 16%
A89120 Rails - Financial Evaluation Approval 6 13-Feb-22 20-Feb-22 6.0% 100% 6% 100% 6%
A89080 Rails - PO 6 21-Feb-22 28-Feb-22 12.0% 100% 12% 100% 12%
A89130 Rails - Manufacturing 30 01-Mar-22 11-May-22 15.0% 100% 15% 100% 15%
A89140 Rails - Inspection 1 12-May-22 12-May-22 6.0% 100% 6% 100% 6%
A89150 Rails - RFS 1 13-May-22 13-May-22 18.0% 100% 18% 100% 18%
A89090 Rails - Delivery @ Site 14 08-Sep-22 01-Mar-23 21.0% 100% 21% 60% 13%
Rails For Overhead Crane 210 13-Oct-21 01-Oct-22 0.8% 100% 1% 100% 1%
SS Explosion Proof Vent 161 23-Jan-22 15-Oct-22 0.6% 100% 0.6% 100% 0.6%
Assembly Requirements & Star Cooler Arm 5253 / 56 / 59 (Plot-1) - Group 5200 115 27-Sep-21 13-Jan-22 2.8% 100% 3% 100% 3%
GRP / IBC Tanks - Group 4572 (IBC -1000 lt) 168 14-Sep-21 28-Feb-22 1.6% 100% 2% 100% 2%
Mirrors Station with Gear Motor - Group 5445 89 31-Mar-22 01-Feb-23 0.3% 100% 0% 79% 0%
A88620 Mirrors Station with gear motor - Group 5445 - RFQ / Bidding 10 21-Aug-22 29-Sep-22 6.0% 100% 6% 100% 6%
Mirrors Station with gear motor - Group 5445 - Technical Evaluation
A88630 20 02-Oct-22 10-Nov-22 16.0% 100% 16% 100% 16%
Approval
Mirrors Station with gear motor - Group 5445 - Commercial Evaluation
A88640 5 13-Nov-22 01-Dec-22 6.0% 100% 6% 100% 6%
Approval
A88600 Mirrors Station with gear motor - Group 5445 - PO 5 04-Dec-22 08-Dec-22 12.0% 100% 12% 100% 12%
A88650 Mirrors Station with gear motor - Group 5445 - Manufacturing 14 09-Dec-22 24-Dec-22 15.0% 100% 15% 100% 15%
A88660 Mirrors Station with gear motor - Group 5445 - Inspection 1 25-Dec-22 25-Dec-22 6.0% 100% 6% 100% 6%
A88670 Mirrors Station with gear motor - Group 5445 - RFS 1 26-Dec-22 26-Dec-22 18.0% 100% 18% 100% 18%
A88610 Mirrors Station with gear motor - Group 5445 - Delivery @ Site 15 31-Dec-22 01-Feb-23 21.0% 100% 21% 0%
High Pressure Generator with hot water for mobile use - Group 7410 117 06-Mar-22 16-Nov-22 0.3% 100% 0% 100% 0%
Sound Cabint & Noise Protection System 110 10-Mar-22 01-Jun-23 6.0% 100% 6% 6% 0%
A88780 Sound Cabint & Noise Protection System - RFQ / Bidding 10 01-Jan-23 01-Feb-23 6.0% 100% 6% 100% 6%

A88790 Sound Cabint & Noise Protection System - Technical Evaluation Approval 15 02-Feb-23 27-Feb-23 16.0% 100% 16% 0%
Sound Cabint & Noise Protection System - Commercial Evaluation
A88800 5 28-Feb-23 07-Mar-23 6.0% 100% 6% 0%
Approval
A88760 Sound Cabint & Noise Protection System - PO 5 08-Mar-23 15-Mar-23 12.0% 100% 12% 0%
A88810 Sound Cabint & Noise Protection System - Manufacturing 42 16-Mar-23 15-May-23 15.0% 100% 15% 0%
A88820 Sound Cabint & Noise Protection System - Inspection 1 16-May-23 16-May-23 6.0% 100% 6% 0%

Page 165 of 234


As of 11‐02‐23

Revised Plan Plan Actual


Activity ID Activity Name Duration R.Wt.
Start Finish Item O.A Item O.A
A88830 Sound Cabint & Noise Protection System - RFS 1 17-May-23 17-May-23 18.0% 100% 18% 0%
A88770 Sound Cabint & Noise Protection System - Delivery @ Site 15 18-May-23 01-Jun-23 21.0% 100% 21% 0%
Safety Barriers & Fences 117 03-Apr-22 15-May-23 12.1% 100% 12% 40% 5%
A88940 Safety Barriers & Fences - RFQ / Bidding 10 01-Jan-23 24-Jan-23 6.0% 100% 6% 100% 6%
A88950 Safety Barriers & Fences - Technical Evaluation Approval 20 25-Jan-23 09-Feb-23 16.0% 100% 16% 100% 16%
A88960 Safety Barriers & Fences - Commercial Evaluation Approval 5 12-Feb-23 19-Feb-23 6.0% 100% 6% 100% 6%
A88920 Safety Barriers & Fences - PO 5 20-Feb-23 27-Feb-23 12.0% 100% 12% 100% 12%
A88970 Safety Barriers & Fences - Manufacturing 42 28-Feb-23 28-Apr-23 15.0% 100% 15% 0%
A88980 Safety Barriers & Fences - Inspection 1 29-Apr-23 29-Apr-23 6.0% 100% 6% 0%
A88990 Safety Barriers & Fences - RFS 1 30-Apr-23 30-Apr-23 18.0% 100% 18% 0%
A88930 Safety Barriers & Fences - Delivery @ Site 15 01-May-23 15-May-23 21.0% 100% 21% 0%
Electrical Secured Accesses Door and Flaps - GR-4599 113 22-Mar-22 15-May-23 10.5% 100% 11% 40% 4%
A89020 Electrical Secured Accesses Door and Flaps - GR-4599 - RFQ / Bidding 10 01-Jan-23 24-Jan-23 6.0% 100% 6% 100% 6%
Electrical Secured Accesses Door and Flaps - GR-4599 - Technical
A89030 20 25-Jan-23 09-Feb-23 16.0% 100% 16% 100% 16%
Evaluation Approval
Electrical Secured Accesses Door and Flaps - GR-4599 - Financial
A89040 5 12-Feb-23 19-Feb-23 6.0% 100% 6% 100% 6%
Evaluation Approval
A89000 Electrical Secured Accesses Door and Flaps - GR-4599 - PO 5 20-Feb-23 27-Feb-23 12.0% 100% 12% 100% 12%
A89050 Electrical Secured Accesses Door and Flaps - GR-4599 - Manufacturing 42 28-Feb-23 28-Apr-23 15.0% 100% 15% 0%
A89060 Electrical Secured Accesses Door and Flaps - GR-4599 - Inspection 1 29-Apr-23 29-Apr-23 6.0% 100% 6% 0%
A89070 Electrical Secured Accesses Door and Flaps - GR-4599 - RFS 1 30-Apr-23 30-Apr-23 18.0% 100% 18% 0%
A89010 Electrical Secured Accesses Door and Flaps - GR-4599 - Delivery @ Site 15 01-May-23 15-May-23 21.0% 100% 21% 0%
Refractory 88 24-Oct-21 01-Feb-23 21.3% 100% 21% 100% 21%

Page 166 of 234


As of Date 11‐02‐23

Start Finish Plan (Baseline) Actual


Activity ID Activity Name R.Wt.
(Baseline) (Baseline)
Item O.A Item O.A
MANUFACTURING (Workshop Activities) 02-Jan-21 24-Apr-22 100% 100.0% 100.0% 98.2% 98.2%
Structural Steel Fabrication & Painting 02-Jan-21 24-Apr-22 59% 98.2% 58% 97.3% 58%
WSD Approval 02-Jan-21 29-Jan-22 10% 100.0% 10.0% 99.9% 10%
ISBL / OSBL - Warehouses & Sheds 18-Dec-21 24-Apr-22 2% 100.0% 2% 96.1% 2%
A58381 MDF‐LIQUID CHEMICAL SHED 18-Dec-21 12-Feb-22 18.8% 100% 19% 100% 19%
A91720 GENERATOR SHED 22-Mar-22 09-Apr-22 3.1% 100% 3%
A72960 Car Parking Shed 22-Mar-22 28-Mar-22 7.0% 100% 7% 100% 7%
A72780 Industrial Pump Shed 22-Mar-22 28-Mar-22 5.9% 100% 6% 100% 6%
A72920 POTABLE WATER PUMP HOUSE 22-Mar-22 18-Apr-22 3.5% 100% 4% 100% 4%
A91770 3 NEW PIPE RACKS 22-Mar-22 28-Mar-22 5.5% 100% 5% 100% 5%
New Fire Truck HSE Shed 26-Mar-22 24-Apr-22 3.1% 100% 3% 100% 3%
A72910 Fire Pump Shed 22-Mar-22 24-Apr-22 3.5% 100% 4% 100% 4%
A72810 Reject Water Shed 28-Mar-22 24-Apr-22 2.3% 100% 2% 100% 2%
New Water Treatment Shed 11-Apr-22 24-Apr-22 15.2% 100% 15% 100% 15%
A72720 Compressor Shed 26-Mar-22 24-Apr-22 8.2% 100% 8% 100% 8%
A91750 Transformer Sheds 22-Mar-22 24-Apr-22 7.8% 100% 8% 90% 7%
New MDF Main Gate 28-Mar-22 24-Apr-22 12.1% 100% 12% 100% 12%
New RC Building Platform & Ladder 11-Apr-22 24-Apr-22 0.8% 100% 1% 100% 1%
New Pits Covers (Chemical & Reject) 22-Mar-22 24-Apr-22 3.1% 100% 3% 100% 3%
ISBL- Production Line 02-Jan-21 06-Apr-22 88% 98.0% 86% 97.0% 85%
Plot-1 02-Jan-21 06-Apr-22 34.7% 100% 35% 99.0% 34%
A7565 primary Warehouse For Final Product 02-Jan-21 31-Mar-21 84.9% 100% 85% 100% 85%
A58371 Warehouse For Final Product (remaining) 22-Feb-21 30-Sep-21 0.7% 100% 1% 100% 1%
A72980 SPARE PARTS FOR FINAL PRODUCTION WAREHOUSE 20-Nov-21 19-Dec-21 2.5% 100% 2% 96% 2%
A80520 Supporting Outlet Tube Above Fan 5910 08-Mar-22 06-Apr-22 0.5% 100% 1% 100% 1%
A85030 Service Collector Pneumatic 5910 01-Jan-22 06-Feb-22 0.1% 100% 0% 100% 0%
A85040 Platform of Gripper Carriage 01-Jan-22 24-Jan-22 0.4% 100% 0% 88% 0%
A85050 Platform 1 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.4% 100% 0% 88% 0%
A85060 Platform 2 Inside Production Warehouse 01-Jan-22 20-Jan-22 0.3% 100% 0% 80% 0%
A85070 Platform 3 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.4% 100% 0% 88% 0%
A85080 Platform 4 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.5% 100% 1% 80% 0%
A85090 Platform 5 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.2% 100% 0% 67% 0%
A85080 Platform 6 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.2% 100% 0%
A85090 Platform 7 Inside Production Warehouse 01-Jan-22 23-Jan-22 0.2% 100% 0%
A85100 Press Steel Support 01-Jan-22 23-Jan-22 0.1% 100% 0% 100% 0%
A85110 Hit Bumpers 01-Jan-22 23-Jan-22 0.3% 100% 0% 100% 0%
A85120 Pump Room Steel Supports 01-Jan-22 19-Jan-22 0.6% 100% 1% 100% 1%
A86710 Steel Stair for Mat Reject Tunnel 01-Jan-22 16-Jan-22 0.1% 100% 0% 100% 0%
A85130 Matformer (01st. Part) 01-Jan-22 15-Jan-22 1.5% 100% 2% 100% 2%
A91650 Matformer (02nd. Part) 17-Mar-22 06-Apr-22 6.3% 100% 6% 98% 6%
Plot-2 29-Sep-21 03-Apr-22 21.9% 100% 22% 97.4% 21%
A85430 Sifting Tower 2051 (01st. Part) 29-Sep-21 31-Jan-22 20.2% 100% 20% 100% 20%
A91660 Sifting Tower 2051 (02nd. Part) 30-Nov-21 03-Apr-22 28.2% 100% 28% 96% 27%
STEEL HOUSING FOR SUPPROTING BELT
A85390 19-Dec-21 19-Jan-22 6.6% 100% 7% 100% 7%
(SIFTER AREA)
A85400 PLATFORMS ABOVE FANS (SIFTER AREA) 19-Dec-21 19-Jan-22 3.3% 100% 3% 95% 3%
A85410 SERVICE PLATFORM 2591 (SIFTER AREA) 15-Jan-22 07-Feb-22 0.2% 100% 0% 100% 0%
A85420 Dryer 64m (01st Part) 07-Dec-21 28-Feb-22 4.8% 100% 5% 100% 5%
A91670 Dryer 64m (02nd. Part) 01-Feb-22 03-Apr-22 6.4% 100% 6% 97% 6%
A85440 PIPE BRIDGE STEAM‐PIPE ITEM 7021. 22-Dec-21 14-Mar-22 4.6% 100% 5% 100% 5%
A85450 PIPE BRIDGE STEEL STRUCTURE 16-Jan-22 28-Mar-22 3.1% 100% 3% 100% 3%
A85460 SERVICE PLATFORM FOR CONVEYOR 2781. 14-Mar-22 03-Apr-22 0.2% 100% 0% 100% 0%
A85470 STEEL PIPE RACK FOR PNEUMATIC 4946. 30-Dec-21 02-Mar-22 0.9% 100% 1% 100% 1%
A85480 STEEL STR FOR FILTER 4911 AND 4947. 01-Dec-21 23-Feb-22 1.0% 100% 1% 85% 1%
A85490 FILTER SFDT 0512‐D‐01.. 09-Jan-22 03-Apr-22 0.2% 100% 0% 50% 0%
A85500 Bridge 1 to Pneumatic 2615 31-Jan-22 26-Mar-22 1.1% 100% 1% 100% 1%
A85510 Pipe Rack For Crude Gas Duct SENA11 31-Jan-22 10-Mar-22 1.6% 100% 2% 90% 1%
A85520 Platform for cyclone 4910 31-Jan-22 03-Mar-22 6.9% 100% 7% 99% 7%
A85530 Platform for Pneumatic 4976 31-Jan-22 28-Feb-22 0.5% 100% 0% 83% 0%
A85380 St. Str. for Sifter (01st. Part - Main Str.) 31-Jan-22 27-Feb-22 2.4% 100% 2% 100% 2%
A91680 St. Str. for Sifter (02nd. part - Other Str.) 31-Jan-22 20-Feb-22 7.7% 100% 8% 93% 7%
Plot-3 01-Aug-21 07-Mar-22 6.1% 100% 6% 99% 6%
A85540 Fuel Gas Cleaning (01st Part) 01-Aug-21 30-Oct-21 26.0% 100% 26% 100% 26%
A85540 Fuel Gas Cleaning (02nd. Part) 30-Aug-21 01-Jan-22 6.9% 100% 7% 100% 7%
A85550 Fuel Gas Cleaning St-Supports 10-Nov-21 23-Dec-21 0.6% 100% 1% 100% 1%
A85560 Thermal Oil Heating (1st.part) 20-Nov-21 27-Dec-21 14.5% 100% 14% 100% 14%
A85560 Thermal Oil Heating (2nd.part) 30-Nov-21 26-Dec-21 19.7% 100% 20% 100% 20%
Page 167 of 234
As of Date 11‐02‐23

Start Finish Plan (Baseline) Actual


Activity ID Activity Name R.Wt.
(Baseline) (Baseline)
Item O.A Item O.A
A85570 Pipe Bridge Steel Structure 2782 01-Aug-21 05-Sep-21 11.3% 100% 11% 100% 11%
A85580 Steel Structure for Pneumatic 2785 01-Aug-21 05-Sep-21 7.8% 100% 8% 93% 7%
A89830 Platforms & Walkways 01-Aug-21 05-Sep-21 6.6% 100% 7% 100% 7%
A89850 Burner Housing 01-Aug-21 05-Sep-21 6.6% 100% 7% 100% 7%
Plot-4 01-Jan-22 05-Apr-22 14.2% 100% 14% 100% 14%
A85650 Warehouse For Refinery Building (1st. Part) 08-Dec-21 14-Feb-22 9.3% 100% 9% 100% 9%
A91690 Warehouse For Refinery Building (2nd. Part) 05-Oct-21 14-Feb-22 20.8% 100% 21% 100% 21%
A85660 Pipe Rack For Refiner 01-Feb-22 05-Apr-22 1.5% 100% 1% 100% 1%
A85670 Refinery Structure 13-Jan-22 08-Mar-22 37.7% 100% 38% 100% 38%
A85590 PIPE RACK FOR PENUMATIC 4970 & 5920 15-Jan-22 14-Mar-22 2.7% 100% 3% 100% 3%
A85600 CONVEYOR 1557 END SUPPORT STRUCTURE 15-Jan-22 05-Apr-22 2.5% 100% 2% 95% 2%
A85610 STEEL PLATFORMS FOR FILTER AREA 5091 13-Jan-22 26-Mar-22 3.7% 100% 4% 100% 4%
A85620 STEEL STRUCTURE FOR CONVEYOR 1557 30-Dec-21 07-Mar-22 4.1% 100% 4% 100% 4%
A85630 STEEL STRUCTURE FOR CONVEYOR 1555 13-Jan-22 09-Mar-22 4.3% 100% 4% 97% 4%
A85640 STORAGE BIN 13-Jan-22 09-Mar-22 11.0% 100% 11% 100% 11%
A85680 STEEL STRUCTURE FOR CONVEYOR 1394 15-Jan-22 07-Mar-22 2.4% 100% 2% 100% 2%
Plot-5 31-Oct-21 14-Feb-22 5.5% 100% 5% 100% 5%
Plot-6 12-Jun-21 17-Oct-21 6.4% 100% 6% 100% 6%

Plot-7 23-Dec-21 17-Mar-22 2.9% 100% 3% 99% 3%


A85800 Pump Room Warehouse 23-Dec-21 15-Feb-22 17.0% 100% 17% 96% 16%
A85810 Steel Supports for Pump Room pipes 15-Jan-22 12-Feb-22 27.9% 100% 28% 100% 28%
A85780 GLUE STORAGE SHED 30-Dec-21 24-Feb-22 25.5% 100% 25% 98% 25%
A85790 Dryer Mixing Chamber (1st. Part) 09-Jan-22 07-Mar-22 7.3% 100% 7% 100% 7%
A85790 Dryer Mixing Chamber (2nd. Part) 15-Jan-22 17-Mar-22 6.7% 100% 7% 100% 7%
A85820 Steel Structure for Pump Room 20-Jan-22 17-Mar-22 15.8% 100% 16% 100% 16%
Filters 30-Dec-21 03-Feb-22 0.9% 100% 0.9% 92% 1%
A85830 1322‐FILTER SFDW 05&09‐D‐03 30-Dec-21 03-Feb-22 5.7% 100% 6% 100% 6%
A85840 1332‐FILTER SFDW 05&09‐D‐03 30-Dec-21 03-Feb-22 5.7% 100% 6% 100% 6%
A85850 1342‐FILTER SFDW 05&09‐D‐03 30-Dec-21 03-Feb-22 5.7% 100% 6% 100% 6%
A85860 1532‐FILTER SFDW 05&09‐C‐01 30-Dec-21 03-Feb-22 3.8% 100% 4% 100% 4%
A85870 4911‐FILTER SFDW 05&12‐D‐05 30-Dec-21 03-Feb-22 5.7% 100% 6% 90% 5%
A85880 5911‐FILTER SFDW 05&12‐D‐07 30-Dec-21 03-Feb-22 7.5% 100% 8% 75% 6%
A91790 St. Str. Fab. - Platforms for Silos 02-Apr-22 24-Apr-22 39.6% 100% 40% 95% 38%
A93510 St. Str. Fab. - Sound Cabient for 4550 02-Apr-22 24-Apr-22 11.3% 100% 11% 83% 9%
A93530 St. Str. Fab. - Loading Arm for PMDI Tanks 02-Apr-22 24-Apr-22 15.1% 100% 15% 88% 13%
Supports 30-Dec-21 03-Feb-22 7.3% 73% 5.3% 74% 5%
A93470 Piping Supports 30-Dec-21 03-Feb-22 87.9% 69% 61% 70% 62%
A93480 Cable Trays Supports 30-Dec-21 03-Feb-22 12.1% 100% 12% 100% 12%
Equipment Fabrication 16-Feb-21 16-Apr-22 27% 100.0% 27% 99.9% 27%
Champers 16-Jun-21 28-Feb-22 9% 100% 9.2% 100% 9%
Cyclones 16-Feb-21 06-Apr-22 31% 100% 31% 100% 31%
Silos 29-Mar-21 14-Mar-22 30% 100% 30% 100% 30%
Stacks 22-Feb-21 03-Mar-22 7% 100% 7% 100% 7%
Vessels 27-Feb-21 16-Apr-22 18% 100% 18% 99% 18%
Engineering 04-Jun-21 04-Aug-21 10% 100.0% 10% 100.0% 10%
Material Supply 27-Feb-21 15-Dec-21 30% 100.0% 30% 100.0% 30%
Fabrication 05-Jul-21 16-Apr-22 60% 100.0% 60% 98.7% 59%
A75910 Fabrication - Emulsion Storage Tank (7ea.) - Group 3226 05-Jul-21 07-Feb-22 36.5% 100% 36% 100% 36%
A75950 Fabrication - Expansion Tank - Group 7390 (T-1040) 30-Oct-21 07-Feb-22 2.3% 100% 2% 100% 2%
A75960 Fabrication - Fill and Drain Tank - Group 7390 (T-1050) 30-Oct-21 07-Feb-22 4.6% 100% 5% 100% 5%
A76000 Fabrication - Feed water Tank with Deaerator- Group 7395 16-Dec-21 24-Feb-22 5.3% 100% 5% 100% 5%
A75980 Fabrication - Blow Down Tank - Group 7395 03-Nov-21 07-Feb-22 0.7% 100% 1% 100% 1%
A75720 Fabrication - Vent Container - Group 7390 16-Dec-21 17-Feb-22 1.2% 100% 1% 100% 1%
A75970 Fabrication - Hot Water Tank - Group 4390 16-Dec-21 13-Feb-22 6.5% 100% 7% 100% 7%
A75710 Fabrication - Vessel (Drain Box) - Group 2310 / 2332 01-Jan-22 12-Mar-22 6.5% 100% 7% 80% 5%
A86670 Fabrication - PMDI Storage Tank (4a.) 01-Jan-22 16-Apr-22 36.5% 100% 36% 100% 36%
Containers 29-Mar-21 28-Feb-22 1% 100% 1% 100% 1%
Thermal Oil Heater 20-Feb-21 24-Jan-22 5% 100% 5% 100% 5%
Duct Work & Inspection Door (Incl. Chutes, Flanges, Hoods, Air Control Flap) 01-Jun-21 16-Mar-22 11.2% 100.0% 11% 98.5% 11%

Engineering (Cutting Sheets, ...) 01-Jun-21 31-Oct-21 10% 100.0% 10% 100.0% 10%

Material Supply 01-Jul-21 30-Nov-21 20% 100% 20% 100% 20%

Ducts Fabrication 01-Sep-21 16-Mar-22 70% 100.0% 70% 97.9% 68%


Penumatic Conveyor Ducts 29-Sep-21 16-Mar-22 57% 100.0% 57% 100.0% 57%
Page 168 of 234
As of Date 11‐02‐23

Start Finish Plan (Baseline) Actual


Activity ID Activity Name R.Wt.
(Baseline) (Baseline)
Item O.A Item O.A
Dryer Ducts 01-Sep-21 27-Feb-22 9% 100.0% 9% 100.0% 9%
A75340 Fab.- Drier Duct (From Drier to High Effeciency Cyclone) - Group 2420 01-Sep-21 27-Feb-22 100.0% 100% 100% 100.0% 100%

Crude Gas Ducts 01-Dec-21 30-Jan-22 7% 100.0% 7% 100.0% 7%

Energy Plant Ducts 01-Dec-21 16-Mar-22 15% 100.0% 15% 100.0% 15%

A75670 Fab.- Duct work from ambient air fan to mixing chamber - Group 7385.065 08-Jan-22 14-Feb-22 1.3% 100% 1% 100% 1%

A79030 Fab.- Duct work from ambient air fan to quench chamber - Group 7385.060 22-Dec-21 05-Jan-22 0.4% 100% 0% 100% 0%

A79040 Fab.- Duct work from cooling air fan to the burner - Group 7370.062 01-Dec-21 15-Feb-22 1.9% 100% 2% 100% 2%
A79050 Fab.- Duct work from mixing chamber to cyclones - Group 7385.065 08-Jan-22 14-Feb-22 1.3% 100% 1% 100% 1%

A79080 Fab.- Duct work from thermal oil heater to mixing chamber - Group 7385.065 25-Dec-21 31-Jan-22 1.3% 100% 1% 100% 1%
A79160 Fab.- Air Girder (new scope) 06-Dec-21 14-Feb-22 15.0% 100% 15% 100% 15%
A75640 Fab.- Duct work from combustion air fan to the burner - Group 7370.061 29-Jan-22 28-Feb-22 3.3% 100% 3% 100% 3%
Fab.- Duct work from the Main ID fan to Dryer Mixing Chamber - Group
A75650 29-Jan-22 28-Feb-22 8.6% 100% 9% 100% 9%
7385.090
A79060 Fab.- Duct work from the Main ID fan to Start up Stack - Group 7385.090 22-Jan-22 28-Feb-22 8.6% 100% 9% 100% 9%

A79070 Fab.- Duct work from thermal oil heater fan to mixing chamber - Group 7390 22-Jan-22 28-Feb-22 11.8% 100% 12% 100% 12%
Fab.- Duct work from thermal oil heater to thermal oil heater fan - Group
A79090 22-Jan-22 28-Feb-22 11.8% 100% 12% 100% 12%
7390
Fab.- Duct work from dust collector (Cyclones) to Ash Crews - Group
A79110 22-Jan-22 28-Feb-22 15.9% 100% 16% 100% 16%
7385.080
Fab.- Duct work from dust collector (Cyclones) to Main ID fan - Group
A79120 30-Dec-21 06-Feb-22 15.9% 100% 16% 100% 16%
7385.080
A79100 Fab.- Transport pipes ducts for dust - Group 7370 26-Jan-22 14-Feb-22 2.8% 100% 3% 100% 3%

Chutes 30-Dec-21 16-Mar-22 13% 100.0% 13% 83.6% 11%


A75320 Fab.- Chutes, Doors & loose items - Group 2300 30-Dec-21 30-Jan-22 61.6% 100% 62% 89% 55%

A75390 Fab.- Pneumatic Supports - Group 2600 15-Feb-22 16-Mar-22 28.6% 100% 29% 100% 29%

A75490 Fab.- Silencer - Group 4200 30-Dec-21 30-Jan-22 9.8% 100% 10%
OSBL - Tanks 31-Aug-21 27-Mar-22 3% 100% 3% 100% 3%
A76020 Pre-Fabrication Industrial Raw Water Tanks (101) 31-Aug-21 28-Feb-22 33.2% 100% 33% 100% 33%
A76030 Pre-Fabrication Demi Water Tanks (103) 31-Aug-21 28-Feb-22 15.2% 100% 15% 100% 15%
A76040 Pre-Fabrication Process Water Tanks (102) 31-Aug-21 28-Feb-22 21.7% 100% 22% 100% 22%
A76070 Pre-Fabrication Fire Water Tanks 23-Jan-22 27-Mar-22 29.9% 100% 30% 100% 30%

Page 169 of 234


Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur. B/L B/L
Item O.A Item O.A
CONSTRUCTION & PRE-COMMISSIONING 537 07-Jul-20 07-Dec-22 100% 100.0% 100.0% 83.1% 83.1%
Production Line 511 07-Jul-20 31-May-22 62% 100% 62% 83% 52%
Site Preparations & Earth Work 93 07-Jul-20 31-Oct-20 1% 100.0% 0.5% 100.0% 1%
A5600 Cut Works Till Lv. (+16.20) 93 07-Jul-20 31-Oct-20 100% 100% 100% 100.0% 100%
Civil Works 420 21-Oct-20 30-Apr-22 36% 100.0% 36.4% 96.3% 35%
Primary MDF Warehouse (Plot -1) 160 22-Oct-20 31-Jul-21 15% 100% 15% 100% 15%
Piles & Earth Work 103 21-Oct-20 21-Feb-21 37% 100.0% 37.4% 99.8% 37%
A5625 Cut Works - Primary MDF Warehouse (Plot-1) 8 14-Dec-20 22-Dec-20 12% 100% 12.4% 100.0% 12%
Backfilling (Replacement) - Primary MDF Warehouse (Plot-
A5630 8 23-Dec-20 31-Dec-20 21% 100% 20.9% 100.0% 21%
1)
A5642 Piles Works for MDF Warehouse (Plot-1)- Batch-1 45 21-Oct-20 13-Dec-20 30% 100% 29.7% 100.0% 30%
A77540 Backfilling - Primary MDF Warehouse (Plot-1) 8 13-Feb-21 21-Feb-21 5% 100% 5.2% 100.0% 5%
Backfilling (Replacement) - Workshop & Spare Parts
A77540 8 13-Feb-21 21-Feb-21 25% 100% 25.4% 100.0% 25%
Warehouse
A77540 Backfilling - Workshop & Spare Parts Warehouse 8 13-Feb-21 21-Feb-21 6% 100% 6.4% 96.9% 6%
Str. St. Foundations 34 02-Jan-21 11-Feb-21 24% 100.0% 23.8% 100.0% 24%
A5101 Plain Concrete 4 02-Jan-21 05-Jan-21 6% 100% 5.6% 100.0% 6%
A56001 RC Foundations 12 14-Jan-21 28-Jan-21 71% 100% 70.6% 100.0% 71%
A56011 RC Coulmns Head 8 30-Jan-21 07-Feb-21 5% 100% 5.1% 100.0% 5%
A56031 Insulation 4 08-Feb-21 11-Feb-21 2% 100% 2.2% 100.0% 2%
A82580 Pile Head Demolishing 6 06-Jan-21 13-Jan-21 16% 100% 16.4% 100.0% 16%
Paving 43 24-Aug-21 13-Jan-22 39% 100.0% 38.7% 100.0% 39%
A5100 Paving (concrete) 43 24-Aug-21 20-Sep-21 85% 100% 85.2% 100.0% 85%
Paving (Interlock) 43 02-Nov-21 13-Jan-22 15% 100% 14.8% 100.0% 15%
Page 170 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Final MDF WH, Matforming, Cooling & Stacking (Plot-1) 336 15-Dec-20 13-Jan-22 18% 100% 18% 96% 17%
Piles & Earth Work 159 15-Dec-20 26-Jul-21 23% 100.0% 22.7% 100.0% 23%
Piles Works for Final MDF Wh., Matforming, Cooling &
A74550 77 14-Dec-20 15-Mar-21 59% 100% 58.5% 100.0% 59%
Stacking (Plot-1)
Backfilling (Replacement) - Final MDF Wh., Matforming,
A77840 12 04-Apr-21 17-Apr-21 23% 100% 22.8% 100.0% 23%
Cooling & Stacking (Plot-1)
Cut Works - Final MDF Wh., Matforming, Cooling &
A77850 16 16-Mar-21 03-Apr-21 13% 100% 13.0% 100.0% 13%
Stacking (Plot-1)
Backfilling - Final MDF Wh., Matforming, Cooling &
A77860 8 12-Jul-21 25-Jul-21 6% 100% 5.7% 100.0% 6%
Stacking (Plot-1)
Str. St. Foundations 46 19-Apr-21 12-Jul-21 13% 100.0% 13.1% 100.0% 13%
A56051 RC Foundations 18 10-May-21 17-Jun-21 58% 100% 57.7% 100.0% 58%
A56061 RC Coulmns Head 8 19-Jun-21 06-Jul-21 6% 100% 6.4% 100.0% 6%
A56081 Insulation 4 07-Jul-21 11-Jul-21 0% 100% 0.4% 100.0% 0%
A5655 Plain Concrete 4 18-Apr-21 21-Apr-21 10% 100% 10.3% 100.0% 10%
A82720 Pile Head Demolishing 12 22-Apr-21 09-May-21 25% 100% 25.1% 100.0% 25%
Equipment Foundations 46 19-Apr-21 12-Jul-21 54% 100.0% 54.4% 100.0% 54%
A56091 RC Foundations 18 10-May-21 16-Jun-21 80% 100% 80.3% 100.0% 80%
A56101 Insulation 4 07-Jul-21 11-Jul-21 0% 100% 0.1% 100.0% 0%
A5662 Plain Concrete 4 18-Apr-21 21-Apr-21 2% 100% 1.6% 100.0% 2%
A82730 Pile Head Demolishing 12 22-Apr-21 09-May-21 3% 100% 2.5% 100.0% 3%
A82750 RC Wall 8 17-Jun-21 06-Jul-21 15% 100% 15.4% 100.0% 15%
Paving 12 02-Nov-21 13-Jan-22 10% 100.0% 9.8% 55.3% 5%
Paving -Matforming / Cooling & Stacking (Plot-1) 12 02-Nov-21 13-Jan-22 100% 100% 100.0% 55.3% 55%
Press & Contiroll@ Sump(Plot-1) 108 16-Feb-21 26-Jul-21 11% 100% 11% 100% 11%
Piles & Earth Work 108 15-Feb-21 25-Jul-21 27% 100.0% 27.4% 100.0% 27%
Page 171 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A82680 Piles Works for Press / Contiroll@ Pit (Plot-1) 25 15-Feb-21 15-Mar-21 62% 100% 61.9% 100.0% 62%
A82690 Backfilling - Press / Contiroll@ Pit (Plot-1) 7 27-May-21 03-Jun-21 21% 100% 20.6% 100.0% 21%
A82700 Cut Works - Press / Contiroll@ Pit (Plot-1) 8 16-Mar-21 24-Mar-21 12% 100% 12.4% 100.0% 12%
A83020 Backfilling (Final) - Press / Contiroll@ Pit (Plot-1) 5 13-Jul-21 25-Jul-21 5% 100% 5.1% 100.0% 5%
Sump Foundation & Wall 70 25-Mar-21 12-Jul-21 73% 100.0% 72.6% 100.0% 73%
A82600 Plain Concrete - Sump 2 25-Mar-21 27-Mar-21 5% 100% 4.9% 100.0% 5%
A82620 RC Foundations - Sump 12 05-Apr-21 22-Apr-21 26% 100% 25.6% 100.0% 26%
A82630 RC Wall - Sump 19 24-Apr-21 26-May-21 11% 100% 11.0% 100.0% 11%
A82740 Pile Head Demolishing - Sump 7 28-Mar-21 04-Apr-21 4% 100% 4.5% 100.0% 4%
A82970 Plain Concrete - Other FND. 2 05-Jun-21 06-Jun-21 6% 100% 6.2% 100.0% 6%
A82980 Pile Head Demolishing - Other FND. 4 07-Jun-21 13-Jun-21 4% 100% 3.8% 100.0% 4%
A82990 RC Foundations - Other FND 6 14-Jun-21 22-Jun-21 40% 100% 40.2% 100.0% 40%
A83000 RC Wall- Others 8 23-Jun-21 07-Jul-21 4% 100% 3.7% 100.0% 4%
A83010 Insulation 3 08-Jul-21 12-Jul-21 0% 100% 0.3% 100.0% 0%
Dryer & Sifting (Plot-2) 311 10-Feb-21 26-Apr-22 14% 100% 14% 95% 13%
Piles & Earth Work 96 10-Feb-21 05-Aug-21 18% 100.0% 18.3% 100.0% 18%
A5645 Piles Works for Dryer & Sifting (Plot-2) 25 10-Feb-21 10-Mar-21 69% 100% 68.7% 100.0% 69%
A76980 Cut Works - Dryer & Sifting (Plot-2) 14 11-Mar-21 27-Mar-21 10% 100% 10.4% 100.0% 10%
A77250 Backfilling (Replacement) - Dryer & Sifting (Plot-2) 8 18-Mar-21 27-Mar-21 17% 100% 16.7% 100.0% 17%
A77560 Backfilling - Dryer & Sifting (Plot-2) 8 28-Jul-21 05-Aug-21 4% 100% 4.2% 100.0% 4%
Str. St. Foundations 49 01-Apr-21 13-Jul-21 54% 100.0% 54.3% 100.0% 54%
A5660 Plain Concrete 6 01-Apr-21 07-Apr-21 4% 100% 3.7% 100.0% 4%
A82860 Pile Heads Demolishing 10 08-Apr-21 19-Apr-21 6% 100% 5.6% 100.0% 6%
A56181 RC Foundations 18 20-Apr-21 07-Jul-21 85% 100% 84.6% 100.0% 85%
Page 172 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A56191 RC Coulmns Head 10 29-Jun-21 13-Jul-21 6% 100% 5.6% 100.0% 6%
A56211 Insulation 5 08-Jul-21 13-Jul-21 1% 100% 0.5% 100.0% 1%
Equipment Foundations & Sumps 49 01-Apr-21 13-Jul-21 12% 100.0% 12.4% 100.0% 12%
A5665 Plain Concrete 6 01-Apr-21 07-Apr-21 21% 100% 20.7% 100.0% 21%
A82870 Pile Heads Demolishing 10 08-Apr-21 19-Apr-21 6% 100% 5.5% 100.0% 6%
A56221 RC Foundations 18 20-Apr-21 07-Jul-21 70% 100% 70.5% 100.0% 70%
A56231 Insulation 5 08-Jul-21 13-Jul-21 0% 100% 0.3% 100.0% 0%
A83030 RC Coulmns Head 10 29-Jun-21 13-Jul-21 3% 100% 3.0% 100.0% 3%
Sump Foundation & Wall 48 28-Mar-21 27-Jul-21 6% 100.0% 5.8% 100.0% 6%
A83040 Plain Concrete 4 15-Apr-21 19-Apr-21 7% 100% 7.0% 100.0% 7%
A83050 Pile Heads Demolishing 10 20-Apr-21 04-May-21 12% 100% 11.8% 100.0% 12%
A83060 RC Foundations 10 05-May-21 03-Jun-21 65% 100% 64.6% 100.0% 65%
A83070 RC Wall - Sump 20 05-Jun-21 10-Aug-21 16% 100% 16.1% 100.0% 16%
A83080 Insulation 4 11-Aug-21 16-Aug-21 1% 100% 0.5% 100.0% 1%
Additional Piles & Concrete Works 52 02-Jan-22 17-Feb-22 4% 100.0% 4.4% 100.0% 4%
A91590 Additional Piles Works 52 02-Jan-22 17-Feb-22 87% 100% 87.0% 100.0% 87%
A91590 Additional Pile Heads Demolishing 10 02-Jan-22 17-Feb-22 13% 100% 13.0% 100.0% 13%
Paving 52 05-Feb-22 26-Apr-22 5% 100.0% 4.8%
A84280
Paving (Interlock) 52 05-Feb-22 26-Apr-22 100% 100% 100.0%
A91400
Silo Area (Plot-3) 286 13-Mar-21 29-Mar-22 4% 100% 4% 95% 3%
Piles & Earth Work 71 13-Mar-21 28-Aug-21 23% 100.0% 23.4% 100.0% 23%
A56121 Piles Works for Silo Area (Plot-3) 12 30-Mar-21 12-Apr-21 77% 100% 76.9% 100.0% 77%
A77000 Cut Works - Silo Area (Plot-3) 7 13-Apr-21 20-Apr-21 8% 100% 7.7% 100.0% 8%
A77270 Backfilling (Replacement) - Silo Area (Plot-3) 7 13-Apr-21 20-Apr-21 12% 100% 12.3% 100.0% 12%
Page 173 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A77570 Backfilling - Silo Area (Plot-3) 8 17-Aug-21 25-Aug-21 3% 100% 3.1% 100.0% 3%
Str. St. Foundations 44 04-Apr-21 18-Aug-21 59% 100.0% 59.3% 100.0% 59%
A56241 Plain Concrete 6 21-Apr-21 28-Apr-21 7% 100% 7.0% 100.0% 7%
A56261 RC Foundations 18 09-May-21 29-Jul-21 84% 100% 83.9% 100.0% 84%
A56271 RC Coulmns Head 10 31-Jul-21 11-Aug-21 1% 100% 0.7% 100.0% 1%
A56291 Insulation 4 12-Aug-21 16-Aug-21 0% 100% 0.1% 100.0% 0%
A82840 Pile Heads Demolishing 6 29-Apr-21 08-May-21 8% 100% 8.3% 100.0% 8%
Equipment Foundations 44 04-Apr-21 18-Aug-21 13% 100.0% 12.7% 100.0% 13%
A56251 Plain Concrete 6 21-Apr-21 28-Apr-21 7% 100% 7.2% 100.0% 7%
A56301 RC Foundations 28 09-May-21 11-Aug-21 81% 100% 81.1% 100.0% 81%
A56311 Insulation 4 12-Aug-21 16-Aug-21 0% 100% 0.4% 100.0% 0%
A82850 Pile Heads Demolishing 6 29-Apr-21 08-May-21 11% 100% 11.3% 100.0% 11%
Paving 52 08-Jan-22 29-Mar-22 5% 100.0% 4.5%
A84270
Paving (Interlock) 52 08-Jan-22 29-Mar-22 100% 100% 100.0%
A91470
Refining Area (Plot-4) 298 11-Feb-21 15-Mar-22 10% 100% 10% 97% 9%
Piles & Earth Work 83 11-Feb-21 29-Sep-21 17% 100.0% 16.9% 100.0% 17%
A56131 Piles Works for Refining Area (Plot-4) 15 11-Feb-21 28-Feb-21 79% 100% 78.7% 100.0% 79%
A77010 Cut Works - Refining Area (Plot-4) 7 01-Mar-21 08-Mar-21 7% 100% 7.1% 100.0% 7%
A77280 Backfilling (Replacement) - Refining Area (Plot-4) 8 09-Mar-21 17-Mar-21 11% 100% 11.4% 100.0% 11%
A77580 Backfilling - Refining Area (Plot-4) 8 21-Sep-21 29-Sep-21 3% 100% 2.8% 100.0% 3%
Str. St. Foundations 45 01-Apr-21 20-Sep-21 68% 100.0% 67.9% 100.0% 68%
A56321 Plain Concrete 6 20-Apr-21 27-Apr-21 3% 100% 2.7% 100.0% 3%
A56341 RC Foundations 18 10-May-21 31-Jul-21 89% 100% 88.8% 100.0% 89%
Page 174 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A56351 RC Coulmns Head 10 01-Aug-21 12-Aug-21 4% 100% 3.6% 100.0% 4%
A56371 Insulation 3 14-Aug-21 16-Aug-21 0% 100% 0.1% 100.0% 0%
A82820 Pile Heads Demolishing 8 28-Apr-21 09-May-21 5% 100% 4.8% 100.0% 5%
Equipment Foundations 46 01-Apr-21 20-Sep-21 12% 100.0% 12.2% 100.0% 12%
A56331 Plain Concrete 6 20-Apr-21 27-Apr-21 5% 100% 4.9% 100.0% 5%
A56381 RC Foundations 28 10-May-21 12-Aug-21 83% 100% 83.2% 100.0% 83%
A56391 Insulation 3 14-Aug-21 16-Aug-21 0% 100% 0.3% 100.0% 0%
A82830 Pile Heads Demolishing 8 28-Apr-21 09-May-21 12% 100% 11.6% 100.0% 12%
Paving 52 15-Jan-22 15-Mar-22 3% 100.0% 3.0%
A84260
Paving (Interlock) 52 15-Jan-22 15-Mar-22 100% 100% 100.0%
A91500
Straw Cleanning Area (Plot-5) 286 11-Mar-21 23-Mar-22 6% 100% 6% 97% 6%
Piles & Earth Work 71 11-Mar-21 21-Aug-21 20% 100.0% 20.4% 100.0% 20%
A56141 Piles Works for Straw Cleanning Area (Plot-5) 15 30-Mar-21 15-Apr-21 73% 100% 72.5% 100.0% 73%
A77020 Cut Works - Straw Cleanning Area (Plot-5) 5 17-Apr-21 21-Apr-21 9% 100% 9.2% 100.0% 9%
A77290 Backfilling (Replacement) - Straw Cleanning Area (Plot-5) 6 22-Apr-21 29-Apr-21 15% 100% 14.7% 100.0% 15%
A77590 Backfilling - Straw Cleanning Area (Plot-5) 7 18-Aug-21 25-Aug-21 4% 100% 3.7% 100.0% 4%
Str. St. Foundations 38 11-Apr-21 12-Aug-21 3% 100.0% 3.4% 100.0% 3%
A56401 Plain Concrete 6 02-May-21 09-May-21 12% 100% 12.2% 100.0% 12%
A56421 RC Foundations 12 23-May-21 03-Aug-21 53% 100% 53.2% 100.0% 53%
A56431 RC Coulmns Head 8 04-Aug-21 14-Aug-21 8% 100% 7.6% 100.0% 8%
A56451 Insulation 3 15-Aug-21 17-Aug-21 2% 100% 1.6% 100.0% 2%
A82800 Pile Heads Demolishing 9 10-May-21 22-May-21 25% 100% 25.5% 100.0% 25%
Equipment Foundations 38 11-Apr-21 12-Aug-21 74% 100.0% 73.5% 100.0% 74%
Page 175 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A56411 Plain Concrete 6 02-May-21 09-May-21 4% 100% 4.4% 100.0% 4%
A56461 RC Foundations 20 23-May-21 14-Aug-21 90% 100% 89.6% 100.0% 90%
A56471 Insulation 3 15-Aug-21 17-Aug-21 0% 100% 0.2% 100.0% 0%
A82810 Pile Heads Demolishing 9 10-May-21 22-May-21 6% 100% 5.7% 100.0% 6%
Paving 52 01-Mar-22 23-Mar-22 3% 100.0% 2.7%
A84250 Paving (Interlock) 52 01-Mar-22 23-Mar-22 100% 100% 100.0%
Straw Preparation (Plot-6) 330 04-Feb-21 23-Mar-22 10% 100% 10% 98% 10%
Piles & Earth Work 78 04-Feb-21 08-Jul-21 30% 100.0% 30.1% 100.0% 30%
A56151 Piles Works for Straw Preparation (Plot-6) 32 07-Feb-21 15-Mar-21 74% 100% 74.2% 100.0% 74%
A77030 Cut Works - Straw Preparation (Plot-6) 7 16-Mar-21 23-Mar-21 9% 100% 8.6% 100.0% 9%
A77300 Backfilling (Replacement) - Straw Preparation (Plot-6) 8 24-Mar-21 01-Apr-21 14% 100% 13.8% 100.0% 14%
A77600 Backfilling - Straw Preparation (Plot-6) 3 01-Jul-21 10-Jul-21 3% 100% 3.4% 100.0% 3%
Str. St. Foundations 28 01-Apr-21 28-Jun-21 10% 100.0% 9.7% 100.0% 10%
A56481 Plain Concrete 2 03-Apr-21 04-Apr-21 27% 100% 27.3% 100.0% 27%
A56501 RC Foundations 7 17-Apr-21 19-Jun-21 51% 100% 51.2% 100.0% 51%
A56511 RC Coulmns Head 6 20-Jun-21 26-Jun-21 5% 100% 4.7% 100.0% 5%
A56531 Insulation 3 27-Jun-21 29-Jun-21 2% 100% 2.5% 100.0% 2%
A82760 Pile Heads Demolishing 10 05-Apr-21 15-Apr-21 14% 100% 14.4% 100.0% 14%
Equipment Foundations 28 01-Apr-21 28-Jun-21 54% 100.0% 54.4% 100.0% 54%
A56491 Plain Concrete 2 03-Apr-21 04-Apr-21 4% 100% 3.9% 100.0% 4%
A56541 RC Foundations 13 17-Apr-21 26-Jun-21 84% 100% 83.8% 100.0% 84%
A56551 Insulation 3 27-Jun-21 29-Jun-21 1% 100% 0.5% 100.0% 1%
A82770 Pile Heads Demolishing 10 05-Apr-21 15-Apr-21 12% 100% 11.8% 100.0% 12%
Paving 52 01-Mar-22 23-Mar-22 6% 100.0% 5.8% 60.0% 3%
Page 176 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A84240 Paving (Plot-6) - Interlock 52 01-Mar-22 23-Mar-22 100% 100% 100.0% 60.0% 60%
Dryer & Blending (Plot-7) 298 17-Mar-21 21-Apr-22 5% 100% 5% 93% 5%
Piles & Earth Work 82 17-Mar-21 09-Sep-21 23% 100.0% 23.1% 100.0% 23%
A56111 Piles Works for Dryer & Blending (Plot-7) 18 16-Mar-21 05-Apr-21 64% 100% 64.1% 100.0% 64%
A76990 Cut Works - Dryer & Blending (Plot-7) 7 06-Apr-21 13-Apr-21 12% 100% 11.6% 100.0% 12%
A77260 Backfilling (Replacement) - Dryer & Blending (Plot-7) 7 06-Apr-21 13-Apr-21 19% 100% 19.4% 100.0% 19%
A77550 Backfilling - Dryer & Blending (Plot-7) 7 18-Aug-21 25-Aug-21 5% 100% 4.8% 100.0% 5%
Str. St. Foundations 50 15-Apr-21 01-Sep-21 54% 100.0% 54.2% 100.0% 54%
A56561 Plain Concrete 6 14-Apr-21 20-Apr-21 5% 100% 4.7% 100.0% 5%
A56581 RC Foundations 21 05-May-21 31-Jul-21 81% 100% 81.3% 100.00% 81%
A56591 RC Coulmns Head 10 01-Aug-21 12-Aug-21 7% 100% 7.1% 100.0% 7%
A56611 Insulation 4 14-Aug-21 17-Aug-21 1% 100% 0.6% 100.0% 1%
A82780 Pile Heads Demolishing 9 21-Apr-21 04-May-21 6% 100% 6.2% 100.0% 6%
Equipment Foundations 50 15-Apr-21 01-Sep-21 16% 100.0% 16.0% 100.0% 16%
A56571 Plain Concrete 6 14-Apr-21 20-Apr-21 6% 100% 6.4% 100.0% 6%
A56621 RC Foundations 31 05-May-21 12-Aug-21 82% 100% 82.1% 100.0% 82%
A56631 Insulation 4 14-Aug-21 17-Aug-21 1% 100% 1.3% 100.0% 1%
A82790 Pile Heads Demolishing 9 21-Apr-21 04-May-21 10% 100% 10.2% 100.0% 10%
Paving 52 19-Feb-22 21-Apr-22 7% 100.0% 6.7%
A84230
Paving (Plot-7) - Interlock 52 19-Feb-22 21-Apr-22 100% 100% 100.0%
A91520
Control Room 110 14-Jun-21 31-Jul-22 1% 100% 0.6% 82% 0.5%
A83820 Control Room - Civil - Concrete Works 24 14-Jun-21 31-Jul-21 8% 100% 8% 100.0% 8%
A83830 Control Room - Civil - Finishing Works 44 01-Aug-21 25-Aug-21 64% 100% 64% 100% 64%
A83840 Control Room - Civil - Doors Fab. & Erection 6 02-Jul-22 07-Jul-22 11% 100% 11% 100% 11%
Page 177 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83850 Control Room - Civil - Raised Floor 12 25-Jul-22 31-Jul-22 18% 100% 18%
Switch Rooms 140 06-Sep-21 13-Jun-22 7% 100% 7% 86% 6%
SR01A ( Plot-6) 121 25-Oct-21 13-Jun-22 15% 100.0% 14.5% 87.5% 13%
A80820 SR01A - Civil - Concrete Works 24 25-Oct-21 21-Nov-21 41% 100% 41% 100.0% 41%
A80830 SR01A - Civil - Finishing Works 45 08-Feb-22 30-Apr-22 41% 100% 41% 100% 41%

A82890 SR01A - Civil - Raised Floor 12 20-Apr-22 30-May-22 11% 100% 11%

A80840 SR01A - Civil - Doors Fab. & Erection 6 31-May-22 13-Jun-22 7% 100% 7% 80% 5%
SR01B ( Plot-5) 121 04-Oct-21 13-Jun-22 12% 100.0% 11.8% 84.7% 10%
A80850 SR01B - Civil - Concrete Works 24 04-Oct-21 02-Nov-21 28% 100% 28% 100.0% 28%
A80860 SR01B - Civil - Finishing Works 45 08-Feb-22 30-Apr-22 50% 100% 50% 100% 50%
A83690 SR01B - Civil - Raised Floor 12 20-Apr-22 30-May-22 14% 100% 14%
A80870 SR01B - Civil - Doors Fab. & Erection 6 31-May-22 13-Jun-22 8% 100% 8% 80% 7%
SR03 ( LV32 - TR32) 121 21-Dec-21 13-Jun-22 9% 100.0% 9.1% 80.0% 7%
A80880 SR03 - Civil - Concrete Works 24 21-Dec-21 17-Jan-22 6% 100% 6% 100.0% 6%
A80890 SR03 - Civil - Finishing Works 45 08-Feb-22 31-Mar-22 65% 100% 65% 100% 65%
A83710 SR03 - Civil - Raised Floor 12 10-May-22 06-Jun-22 18% 100% 18%
A80900 SR03 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 11% 100% 11% 80% 9%
SR04 ( LV42 - TR42) & ( LV43 - TR43) 121 02-Oct-21 13-Jun-22 9% 100.0% 9.1% 80.0% 7%
A80910 SR04 - Civil - Concrete Works 24 21-Dec-21 17-Jan-22 6% 100% 6% 100.0% 6%
A80920 SR04 - Civil - Finishing Works 45 08-Feb-22 31-Mar-22 65% 100% 65% 100% 65%
A83730 SR04 - Civil - Raised Floor 12 17-May-22 06-Jun-22 18% 100% 18%
A80930 SR04 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 11% 100% 11% 80% 9%
SR02A ( LV22 - TR22) 121 04-Oct-21 13-Jun-22 18% 100.0% 18.5% 90.2% 17%
A80940 SR02A - Civil - Concrete Works 24 04-Oct-21 02-Nov-21 54% 100% 54% 100.0% 54%
Page 178 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A80950 SR02A - Civil - Finishing Works 45 13-Feb-22 05-Apr-22 32% 100% 32% 100% 32%
A83750 SR02A - Civil - Raised Floor 12 24-May-22 06-Jun-22 9% 100% 9%
A80960 SR02A - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 5% 100% 5% 80% 4%
SR02B ( LV21 - TR21) & ( LV23 - TR23) 140 06-Sep-21 13-Jun-22 14% 100.0% 13.7% 86.8% 12%
A80970 SR02B - Civil - Concrete Works 24 06-Sep-21 03-Oct-21 38% 100% 38% 100.0% 38%
A80980 SR02B - Civil - Finishing Works 45 20-Feb-22 12-Apr-22 43% 100% 43% 100% 43%
A83770 SR02A - Civil - Raised Floor 12 31-May-22 13-Jun-22 12% 100% 12%
A80990 SR02B - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 7% 100% 7% 80% 6%
SR02C ( Plot-2) 121 23-Sep-21 13-Jun-22 12% 100.0% 11.7% 84.5% 10%
A81000 SR02C - Civil - Concrete Works 24 23-Sep-21 23-Oct-21 27% 100% 27% 100.0% 27%
A81010 SR02C - Civil - Finishing Works 45 19-Feb-22 19-Apr-22 51% 100% 51% 100% 51%
A83790 SR02C - Civil - Raised Floor 12 31-May-22 13-Jun-22 14% 100% 14%
A81020 SR02C - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 8% 100% 8% 80% 7%
SR22 (plot-2) 121 23-Sep-21 13-Jan-22 12% 100.0% 11.7% 84.5% 10%
A81030 SR22 - Civil - Concrete Works 24 23-Sep-21 23-Oct-21 27% 100% 27% 100.0% 27%
A81040 SR22 - Civil - Finishing Works 45 19-Feb-22 27-Apr-22 51% 100% 51% 100% 51%
A83810 SR22 - Civil - Raised Floor 12 31-May-22 13-Jun-22 14% 100% 14%
A81050 SR22 - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 8% 100% 8% 80% 7%
Glue Storage Shed (Plot-7) 36 29-Aug-21 10-Oct-21 0% 100% 0% 100% 0%
A84520 Glue Storage Shed - Civil - Concrete Works 36 29-Aug-21 10-Oct-21 100% 100% 100% 100.0% 100%
Steel Structure Erection Works 312 23-Feb-21 17-Jul-22 12.0% 100.0% 12.0% 85.9% 10%
ISBL - Production Line 57 23-Feb-21 17-Jul-22 71% 100% 71% 97% 69%
Plot-1 391 23-02-21 14-06-22 35.6% 100.00% 35.64% 99.07% 35.31%
A7570 primary Warehouse For Final Product 23-Feb-21 18-Apr-21 85% 100% 85% 100.0% 85%
Page 179 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A7580 Warehouse For Final Product (remaining) 26-May-21 21-Oct-21 1% 100% 1% 100.0% 1%
SPARE PARTS FOR FINAL PRODUCTION
A86690 20-Dec-21 05-Jan-22 3% 100% 3% 95.9% 2%
WAREHOUSE
A85930 Supporting Outlet Tube Above Fan 5910 19-Mar-22 19-May-22 1% 100% 1% 90.0% 0%
A85950 Service Collector Pneumatic 5910 02-Mar-22 13-Mar-22 0% 100% 0% 100.0% 0%
A85960 Platform of Gripper Carriage 12-Mar-22 24-Mar-22 0% 100% 0% 87.5% 0%
A85970 Platform 1 Inside Production Warehouse 07-Apr-22 07-Jun-22 0% 100% 0% 87.5% 0%
A85980 Platform 2 Inside Production Warehouse 19-Apr-22 29-May-22 0% 100% 0% 80.0% 0%
A85990 Platform 3 Inside Production Warehouse 07-May-22 19-May-22 0% 100% 0% 87.5% 0%
A86000 Platform 4 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0% 80.0% 0%
A86010 Platform 5 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0% 66.7% 0%
A86000 Platform 6 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0%
A86010 Platform 7 Inside Production Warehouse 02-May-22 08-Jun-22 0% 100% 0%
A86020 Press Steel Support 16-May-22 29-May-22 0% 100% 0%
A86030 Hit Bumpers 17-Mar-22 30-Mar-22 0% 100% 0% 100.0% 0%
A86040 Pump Room Steel Supports 18-May-22 14-Jun-22 1% 100% 1% 100.0% 1%
A86720 Steel Stair for Mat Reject Tunnel 18-May-22 14-Jun-22 0% 100% 0% 50.0% 0%
A86050 Matformer (01st. Part) 18-May-22 14-Jun-22 2% 100% 2% 100.0% 2%
A86051 Matformer (02nd. Part) 18-May-22 14-Jun-22 6% 100% 6% 97.6% 6%
Plot-2 204 14-12-21 14-07-22 22.5% 100.00% 22.55% 95.56% 21.55%
A86110 Sifting Tower 2051 (01st. Part) 14-Nov-21 24-Mar-22 20% 100% 20% 100.0% 20.2%
A86111 Sifting Tower 2051 (02nd. Part) 15-Feb-22 09-Mar-22 28% 100% 28% 91.7% 26%
STEEL HOUSING FOR SUPPROTING BELT
A86070 08-Mar-22 23-Mar-22 7% 100% 7% 100.0% 7%
(SIFTER AREA)
A86080 PLATFORMS ABOVE FANS (SIFTER AREA) 12-Feb-22 17-Feb-22 3% 100% 3% 95.1% 3%
Page 180 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A86090 SERVICE PLATFORM 2591 (SIFTER AREA) 12-Feb-22 17-Feb-22 0% 100% 0% 100.0% 0%
A86100 Dryer 64m (01st Part) 02-Mar-22 27-Apr-22 5% 100% 5% 100.0% 5%
A89760 Dryer 64m (02nd. Part) 04-Apr-22 07-May-22 6% 100% 6% 94.9% 6%
A86120 PIPE BRIDGE STEAM‐PIPE ITEM 7021. 22-Mar-22 07-Apr-22 5% 100% 5% 100.0% 5%
A86130 PIPE BRIDGE STEEL STRUCTURE 04-Apr-22 07-May-22 3% 100% 3% 86.8% 3%
A86140 SERVICE PLATFORM FOR CONVEYOR 2781. 04-Apr-22 09-May-22 0% 100% 0% 100.0% 0%
A86150 STEEL PIPE RACK FOR PNEUMATIC 4946. 04-Apr-22 07-May-22 1% 100% 1% 100.0% 1%
A86160 STEEL STR FOR FILTER 4911 AND 4947. 06-Apr-22 02-Jun-22 1% 100% 1% 84.6% 1%
A86170 FILTER SFDT 0512‐D‐01.. 02-May-22 08-Jun-22 0% 100% 0% 50.0% 0%
A86180 Bridge 1 to Pneumatic 2615 22-May-22 07-Jun-22 1% 100% 1% 100.0% 1%
A86190 Pipe Rack For Crude Gas Duct SENA11 25-May-22 11-Jun-22 2% 100% 2% 90.0% 1%
A86200 Platform for cyclone 4910 30-May-22 15-Jun-22 7% 100% 7% 98.8% 7%
A86210 Platform for Pneumatic 4976 02-Jun-22 19-Jun-22 0% 100% 0% 66.7% 0%
A86060 St. Str. for Sifter (01st. Part - Main Str.) 23-Jun-22 11-Jul-22 2% 100% 2% 100.0% 2%
A86061 St. Str. for Sifter (02nd. part - Other Str.) 09-Jul-22 14-Jul-22 8% 100% 8% 92.7% 7%
Plot-3 184 30-10-21 04-06-22 6.3% 100.0% 6.29% 97.7% 6.15%
A86220 Fuel Gas Cleaning (01st Part) 31-Oct-21 02-Jan-22 26% 100% 26% 100.0% 26%
A86221 Fuel Gas Cleaning (02nd. Part) 25-Dec-21 29-Jan-22 7% 100% 7% 95.8% 7%
A86230 Fuel Gas Cleaning St-Supports 30-Oct-21 02-Jan-22 1% 100% 1% 100.0% 1%
A86240 Thermal Oil Heating (1st.part) 03-Jan-22 16-Jan-22 14% 100% 14% 100.0% 14%
A86241 Thermal Oil Heating (2nd.part) 02-Jan-22 08-Jan-22 20% 100% 20% 97.1% 19%
A86250 Pipe Bridge Steel Structure 2782 17-Feb-22 21-Mar-22 11% 100% 11% 97.4% 11%
A86260 Steel Structure for Pneumatic 2785 26-Apr-22 04-Jun-22 8% 100% 8% 92.6% 7%
A89820 Platforms & Walkways 28-Mar-22 13-Apr-22 7% 100% 7% 95.7% 6%
Page 181 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A89840 Burner Housing 02-Jun-22 08-Jun-22 7% 100% 7% 95.7% 6%
Plot-4 162 12-02-22 13-06-22 14.6% 100.00% 14.60% 96.15% 14.04%
A86330 Warehouse For Refinery Building (1st. Part) 12-Feb-22 26-Mar-22 19% 100% 19% 100.0% 19%
A86331 Warehouse For Refinery Building (2nd. Part) 06-Apr-22 11-May-22 11% 100% 11% 84.5% 9%
A86340 Pipe Rack For Refiner 06-Apr-22 30-Apr-22 1% 100% 1% 100.0% 1%
A86350 Refinery Structure 06-Apr-22 23-May-22 38% 100% 38% 99.0% 37%
A86270 PIPE RACK FOR PENUMATIC 4970 & 5920 16-Feb-22 14-May-22 3% 100% 3% 68.2% 2%
A86280 CONVEYOR 1557 END SUPPORT STRUCTURE 27-Mar-22 14-May-22 2% 100% 2% 90.0% 2%
A86290 STEEL PLATFORMS FOR FILTER AREA 5091 27-Mar-22 14-May-22 4% 100% 4% 96.7% 4%
A86300 STEEL STRUCTURE FOR CONVEYOR 1557 27-Mar-22 14-May-22 4% 100% 4% 93.9% 4%
A86310 STEEL STRUCTURE FOR CONVEYOR 1555 10-Apr-22 15-May-22 4% 100% 4% 97.1% 4%

A86320 STORAGE BIN 20-Apr-22 09-May-22 11% 100% 11% 100.0% 11%

A86360 STEEL STRUCTURE FOR CONVEYOR 1394 08-May-22 06-Jun-22 2% 100% 2% 94.7% 2%
Plot-5 162 15-01-22 23-06-22 5.6% 100.00% 5.64% 99.68% 5.62%
SIFTING & PLATFORMS G.1031-STRAW MILLING
A86380 G1021 15-Jan-22 12-Feb-22 25.8% 100% 26% 100.0% 26%
(1st part)
SIFTING & PLATFORMS G.1031-STRAW MILLING
A86370 09-Feb-22 03-Mar-22 61.3% 100% 61% 100.0% 61%
G1021
A86390 Service Platform For TKF1398 15-Feb-22 09-Mar-22 0.6% 100% 1% 50.0% 0%
A86400 PIPE RACK FROM PLOT4 TO PLOT5 15-Jan-22 12-Feb-22 3.5% 100% 4% 100.0% 4%
A86410 G.1031 Steel Supports Through Scraper Conveyor 1392 13-Feb-22 09-Apr-22 0.6% 100% 1% 100.0% 1%
A86420 G.1031 & G.1021 STEEL SUPPORTS 13-Feb-22 09-Apr-22 8.1% 100% 8% 100.0% 8%
Plot-6 127 02-10-21 03-03-22 6.6% 100.00% 6.64% 100.00% 6.64%
A86430 St. Str. Erec. - Straw Preparation Building 41 02-Oct-21 21-Nov-21 97.8% 100% 98% 100.0% 98%
Page 182 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A86450 St. Str. Erec. - Straw Pneumatics Drawings 41 03-Oct-21 21-Nov-21 2.2% 100% 2% 100.0% 2%

Plot-7 124 23-02-22 07-04-22 3.0% 100.00% 3.00% 95.15% 2.85%


A86480 Pump Room Warehouse 12-Mar-22 20-Mar-22 17.0% 100% 17% 96.4% 16%
A86490 Steel Supports for Pump Room pipes 23-Feb-22 22-Mar-22 27.9% 100% 28% 95.7% 27%
A86460 GLUE STORAGE SHED 21-Mar-22 30-Mar-22 25.5% 100% 25% 97.6% 25%

A86470 Dryer Mixing Chamber (1st. Part) 19-Mar-22 07-Apr-22 7.3% 100% 7% 100.0% 7%

A86471 Dryer Mixing Chamber (2nd. Part) 19-Mar-22 31-Mar-22 6.7% 100% 7% 81.8% 5%

A86500 Steel Structure for Pump Room 19-Mar-22 31-Mar-22 15.8% 100% 16% 92.3% 15%

Filters 32 17-04-22 29-05-22 0.7% 100.00% 0.71% 92.31% 0.65%

A86510 1322‐FILTER SFDW 05&09‐D‐03 17-Apr-22 02-May-22 8% 100% 8% 100.0% 8%

A86520 1332‐FILTER SFDW 05&09‐D‐03 17-Apr-22 02-May-22 8% 100% 8% 86.7% 7%

A86530 1342‐FILTER SFDW 05&09‐D‐03 17-Apr-22 02-May-22 8% 100% 8% 100.0% 8%

A86540 1532‐FILTER SFDW 05&09‐C‐01 26-Apr-22 14-May-22 5% 100% 5% 100.0% 5%

A86550 4911‐FILTER SFDW 05&12‐D‐05 07-May-22 19-May-22 8% 100% 8% 80.0% 6%

A86560 5911‐FILTER SFDW 05&12‐D‐07 17-May-22 29-May-22 10% 100% 10% 75.0% 8%
A91800 PLATFORMS FOR SILOS 17-May-22 29-May-22 54% 100% 54% 95.2% 51%
Other 26-04-22 14-07-22 4.9% 100.00% 4.95% 83.90% 4.15%
A7586 MDF‐LIQUID CHEMICAL SHED 26-Apr-22 28-May-22 18% 100% 18% 100.0% 18%
A91730 GENERATOR SHED 04-Jul-22 14-Jul-22 3% 100% 3%
A72970 Car Parking Shed 04-Jul-22 14-Jul-22 7% 100% 7% 100.0% 7%
A72790 Industrial Pump Shed 26-Apr-22 28-May-22 6% 100% 6% 100.0% 6%
Page 183 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A72930 POTABLE WATER PUMP HOUSE 04-Jul-22 14-Jul-22 3% 100% 3% 100.0% 3%
A91780 3 NEW PIPE RACKS 04-Jul-22 14-Jul-22 5% 100% 5% 100.0% 5%
New Fire Truck HSE Shed 26-Apr-22 28-May-22 3% 100% 3% 100.0% 3%
A7585 Fire Pump Shed 04-Jul-22 14-Jul-22 4% 100% 4% 100.0% 4%
A72820 Reject Water Shed 04-Jul-22 14-Jul-22 3% 100% 3% 100.0% 3%
New Water Treatment Shed 26-Apr-22 28-May-22 14% 100% 14% 100.0% 14%
A72900 Compressor Shed 04-Jul-22 14-Jul-22 8% 100% 8% 100.0% 8%
A91760 Transformer Sheds 04-Jul-22 14-Jul-22 4% 100% 4% 60.0% 3%
New MDF Main Gate 04-Jul-22 14-Jul-22 11% 100% 11% 100.0% 11%
New RC Building Platform & Ladder 04-Jul-22 14-Jul-22 1% 100% 1%
New Pits Covers (Chemical & Reject) 04-Jul-22 14-Jul-22 3% 100% 3% 12.5% 0%
New Sound Cabinet for G.4550 04-Jul-22 14-Jul-22 3% 100% 3%
New Loading Arm for PMDI 04-Jul-22 14-Jul-22 5% 100% 5%
Cladding Works 371 19-Apr-21 17-Jul-22 16% 100% 16% 82% 13%
A72990 Cladding Works - Primary MDF Warehouse (Plot-1) 79 19-Apr-21 31-Jul-21 25% 100% 25% 100.0% 25%

A73000 Cladding Works - Final MDF Warehouse (Plot-1) 66 23-Oct-21 07-Jan-22 34% 100% 34% 98.7% 33%

A86600 Cladding Works - (Plot-6) 40 22-Nov-21 07-Jan-22 13% 100% 13% 100.0% 13%
A89670 Cladding Works - (Plot-3) 20 06-Apr-22 30-Apr-22 0% 100% 0%

A86630 Cladding Works - Glue Storage Shed (Plot-7) 20 18-Apr-22 16-May-22 0% 100% 0%

A86620 Cladding Works - Pump Room Warehouse (Plot-7) 32 10-May-22 15-Jun-22 1% 100% 1%

A86590 Cladding Works - (Plot-4) 32 15-May-22 20-Jun-22 11% 100% 11% 28.1% 3%

A73010 Cladding Works - Matformer (Plot-1) 16 21-May-22 07-Jun-22 7% 100% 7% 74.5% 5%


Page 184 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A86580 Cladding Works - (Plot-2) 32 09-Jun-22 17-Jul-22 7% 100% 7% 42.4% 3%

A86700 Cladding Works - Warehouse For Spare Parts (Plot-1) 32 11-Jun-22 18-Jul-22 2% 100% 2%

A91740 Cladding Works - Generator Shed 32 07-Jul-22 20-Jul-22 1% 100% 1%

Grating Works 371 19-Apr-21 17-Jul-22 13% 100% 13% 31% 4%


A72990 Grating Works 43 01-Jan-22 20-Apr-22 47% 100% 47% 65.9% 31%
A72990 Grating Works 23 10-Feb-22 31-May-22 53% 100% 53%
Piping Works 115 01-Jan-22 06-Aug-22 8% 100.0% 8.3% 62.0% 5%
Fuel Gas (FG) 115 01-Jan-22 31-May-22 1% 100% 0.7% 72% 1%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 41% 100% 41% 100% 41%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 59% 100% 59% 52% 30%
Spark (SE) 115 01-Jan-22 31-May-22 3% 100% 3.2% 95% 3%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 55% 100% 55% 100% 55%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 45% 100% 45% 89% 40%
Compressed Air (AI) 115 01-Jan-22 31-May-22 14% 100% 13.9% 95% 13%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 25% 100% 25% 100% 25%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 0% 100% 0% 97% 0%
A58101 Piping & Piping Supports Erection (Glav.) 23 10-Feb-22 31-May-22 75% 100% 75% 94% 70%
Boiling and Fresh Water (WH) 115 01-Jan-22 31-May-22 2% 100% 1.6% 52% 1%
A58221 Piping & Piping Supports Fab. (S.D) 43 01-Jan-22 20-Apr-22 60% 100% 60% 78% 47%
A58101 Piping & Piping Supports Erection (S.D) 23 10-Feb-22 31-May-22 40% 100% 40% 14% 6%
Chemical (CL) 115 01-Jan-22 31-May-22 8% 100% 7.9% 51% 4%
A58221 Piping & Piping Supports Fab. (SS) 43 01-Jan-22 20-Apr-22 64% 100% 64% 62% 40%
A58101 Piping & Piping Supports Erection (SS) 23 10-Feb-22 31-May-22 36% 100% 36% 32% 11%
Page 185 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Steam (ST) 115 01-Jan-22 31-May-22 3% 100% 2.6% 59% 2%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 55% 100% 55% 82% 45%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 45% 100% 45% 31% 14%
ONSPEC-Fire Water Above Ground 115 01-Jan-22 31-May-22 17% 100% 17.1% 76% 13%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 71% 100% 71% 68% 48%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 29% 100% 29% 95% 28%
DN CS-ISBL 115 01-Jan-22 31-May-22 12% 100% 12.3% 92% 11%
A58221 Piping & Piping Supports Fab. (CS) 43 01-Jan-22 20-Apr-22 68% 100% 68% 97% 65%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 32% 100% 32% 82% 27%
WESP 115 #REF! 31-May-22 2% 100% 2.3% 100% 2%
A58101 Piping & Piping Supports Erection (SS) 23 10-Feb-22 31-May-22 100% 100% 100% 100% 100%
Second Reheating Pump 115 #REF! 31-May-22 1% 100% 0.9% 83% 1%
A58101 Piping & Piping Supports Erection (CS) 23 10-Feb-22 31-May-22 100% 100% 100% 83% 83%
Press Fume Extraction-(SS) 115 #REF! 31-May-22 2% 100% 2.1% 83% 2%
A58101 Piping & Piping Supports Erection (SS) 23 10-Feb-22 31-May-22 100% 100% 100% 83% 83%
New System [WESP Quench, Chemical Dosing, Steam Condensate, E 115 01-Jan-22 31-May-22 17% 100% 16.5% 28% 5%
A58221 Piping & Piping Supports Fab. 43 01-Jan-22 20-Apr-22 47% 100% 47% 13% 6%
A58101 Piping & Piping Supports Erection 23 10-Feb-22 31-May-22 53% 100% 53% 42% 22%
Piping Supports 115 #REF! 31-May-22 13% 100% 12.7% 40% 5%
A58101 Piping Supports Erection 23 10-Feb-22 31-May-22 100% 100% 100% 40% 40%
Piping Hydrotest & Re-Instatment 161 05-Jun-22 06-Aug-22 6% 100% 6%
A89870 Hydrotest - ISBL 40 05-Jun-22 30-Jul-22 50% 100% 50%

A89880 Re-Instatement & Touch Up - ISBL 31 12-Jun-22 06-Aug-22 50% 100% 50%
Page 186 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Electrical Works 220 09-Oct-21 06-Aug-22 9% 100.0% 9.0% 78.4% 7%
Electrical Works - ISBL 172 24-Jan-22 04-Aug-22 32% 100% 32% 86% 27%
A83660 Cable Trays Supports Fab. & Erection 64 24-Jan-22 02-Mar-22 5% 100% 5% 100.0% 5%
A16480 Cable Trays Installation (ISBL) 84 03-Mar-22 21-Jul-22 22% 100% 22% 89.4% 20%
A16490 Cable Pulling (ISBL) 84 10-Mar-22 28-Jul-22 58% 100% 58% 88.6% 52%
A16510 Termination (ISBL) 84 17-Mar-22 04-Aug-22 15% 100% 15% 67% 10%
Lighting & Small Power System 179 05-Feb-22 06-Aug-22 46% 100% 46% 64% 29%
A83670 Cable Trays Supports Fab. & Erection 64 05-Feb-22 05-Apr-22 1% 100% 1% 100% 1%
A16500 Cable Trays Installation (Lighting - ISBL) 72 16-Feb-22 09-Jun-22 10% 100% 10% 98% 9%
A80770 Lighting Fixtures Erection (ISBL) 72 27-Mar-22 19-Jul-22 12% 100% 12% 39% 5%
A80770 JB-Lighting (ISBL) 72 27-Mar-22 19-Jul-22 8% 100% 8% 27% 2%
A80780 Wire Pulling (outdoor - ISBL) 72 06-Mar-22 27-Jun-22 20% 100% 20% 79% 16%
A80790 SW & Sockets 72 23-Mar-22 16-Jul-22 4% 100% 4% 45% 2%
A80790 Galvanized Conduit 72 23-Mar-22 16-Jul-22 17% 100% 17% 86% 15%
A80800 Termination (Iighting-ISBL) 72 13-Apr-22 06-Aug-22 29% 100% 29% 51% 15%
Earthing Works 121 09-Oct-21 24-Jul-22 5% 100% 0.1 93% 5%
A16470 Earthing - Rods Installation 30 09-Oct-21 18-Dec-21 7% 100% 7% 54% 3%
A79410 Earthing - Cable Laying 85 09-Oct-21 03-Apr-22 64% 100% 64% 95% 61%
A79430 Earthing - Bars & Welding Point Installation 85 19-Dec-21 18-Jun-22 17% 100% 17% 97% 17%
A79420 Earthing - Termination 85 23-Jan-22 24-Jul-22 12% 100% 12% 93% 11%
Emergency Power Generator 77 02-Mar-22 23-May-22 0% 100% 0%
A79500 Emergency Diesel Generator Installation 6 16-Mar-22 29-Mar-22 100% 100% 100%
A80060 Cable Pulling (EMG42 & LV42/ SR04) 12 02-Mar-22 29-Mar-22 100%
A80070 Termination (EMG42 & LV42/ SR04) 12 20-Apr-22 23-May-22 100%
Page 187 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Switch Rooms & Local Pannels 100 15-Feb-22 13-Jun-22 17% 100% 17% 99% 17%
SR01A ( LV12 - TR12) 58 26-Feb-22 19-Apr-22 12% 100.0% 12.4% 100.0% 12%
A91810 SR01A - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 84% 100% 84% 100% 84%
A82880 SR01A - Cable Trays 12 02-Mar-22 15-Mar-22 100%
A79820 SR01A - LV12 & Bus Duct Installation 18 14-Mar-22 27-Mar-22 14% 100% 14% 100% 14%
A79820 SR01A - TR12 18 14-Mar-22 27-Mar-22 2% 100% 2% 100% 2%
A79830 SR01A - Cable Pulling 12
A79840 SR01A - Termination 18
SR01B ( LV13 - TR13) 58 26-Feb-22 27-Apr-22 12% 100.0% 11.5% 100.0% 12%
A91820 SR01B - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 90% 100% 90% 100% 90%
A83680 SR01B - Cable Trays 12 02-Mar-22 13-Mar-22 100%
A80000 SR01B - LV13 & Bus Duct Installation 18 16-Mar-22 29-Mar-22 8% 100% 8% 100% 8%
A80000 SR01B - TR13 18 16-Mar-22 29-Mar-22 2% 100% 2% 100% 2%
A80010 SR01B - Cable Pulling 12 14-Mar-22 29-Mar-22 100% 15%
A80020 SR01B - Termination 18 30-Mar-22 27-Apr-22 100%
SR03 ( LV32 - TR32) 58 09-Mar-22 09-May-22 12% 100.0% 11.7% 100.0% 12%
A91830 SR03 - Steel Frames Fab. & Erection 12 09-Mar-22 17-Mar-22 89% 100% 89% 100% 89%
A83700 SR03 - Cable Trays 12 10-Mar-22 20-Mar-22 100%
A79850 SR03 - LV32 & Bus Duct Installation 18 19-Mar-22 31-Mar-22 9% 100% 9% 100% 9%
A79850 SR03 - TR32 18 19-Mar-22 31-Mar-22 2% 100% 2% 100% 2%
A79860 SR03 - Cable Pulling 12 21-Mar-22 05-Apr-22 100%
A79870 SR03 - Termination 18 06-Apr-22 09-May-22 100%
SR04 ( LV42 - TR42) & ( LV43 - TR43) 58 13-Mar-22 16-May-22 14% 100.0% 14.1% 100.0% 14%
A91840 SR04 - Steel Frames Fab. & Erection 12 13-Mar-22 26-Mar-22 74% 100% 74% 100% 74%
Page 188 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83720 SR04 - Cable Trays 12 14-Mar-22 24-Mar-22 100%
SR04 - LV42 / LV43 & UPS42 / UPS 43 & Bus Duct
A79880 18 30-Mar-22 12-Apr-22 23% 100% 23% 100% 23%
Installation
A79880 SR04 - TR42 / TR43 18 30-Mar-22 12-Apr-22 3% 100% 3% 100% 3%
A79890 SR04 Cable Pulling 12 26-Mar-22 12-Apr-22 100%
A79900 SR04 - Termination 18 13-Apr-22 16-May-22 100%
SR02A ( LV22 - TR22) 58 26-Feb-22 23-May-22 12% 100.0% 12.0% 98.9% 12%
A91850 SR02A - Steel Frames Fab. & Erection 12 26-Feb-22 24-Mar-22 87% 100% 87% 100% 87%
A83740 SR02A - Cable Trays 12 21-Mar-22 31-Mar-22 100%

A79910 SR02A - MV20 / LV22 & Bus Duct Installation 18 06-Apr-22 19-Apr-22 11% 100% 11% 90% 10%

A79910 SR02A - TR20 / TR22 18 06-Apr-22 19-Apr-22 2% 100% 2% 100% 2%

A79920 SR02A - Cable Pulling 12 02-Apr-22 19-Apr-22 100% 15%


A79930 SR02A - Termination 18 20-Apr-22 23-May-22 100%
SR02B ( LV21 - TR21) & ( LV23 - TR23) 69 26-Feb-22 30-May-22 12% 100.0% 11.9% 100.0% 12%
A91860 SR02B - Steel Frames Fab. & Erection 12 26-Feb-22 24-Mar-22 87% 100% 87% 100% 87%
A83760 SR02B - Cable Trays 12 21-Mar-22 31-Mar-22 100%

A79940 SR02B - LV21 / LV23 & Bus Duct Installation 18 06-Apr-22 19-Apr-22 9% 100% 9% 100% 9%

A79940 SR02B - TR21 / TR23 18 06-Apr-22 19-Apr-22 3% 100% 3% 100% 3%

A79950 SR02B - Cable Pulling 12 02-Apr-22 19-Apr-22 100%


A79960 SR02B - Termination 18 20-Apr-22 30-May-22 100%
SR02C ( LV24 - TR24) 58 26-Feb-22 06-Jun-22 12% 100.0% 11.6% 100.0% 12%
A91870 SR02C - Steel Frames Fab. & Erection 12 26-Feb-22 24-Mar-22 90% 100% 90% 100% 90%
Page 189 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83780 SR02C - Cable Trays 12 28-Mar-22 07-Apr-22 100%
A79970 SR02C - LV24 & Bus Duct Installation 18 13-Apr-22 27-Apr-22 9% 100% 9% 100% 9%
A79970 SR02C - TR24 18 13-Apr-22 27-Apr-22 2% 100% 2% 100% 2%
A79980 SR02C - Cable Pulling 12 09-Apr-22 27-Apr-22 100%
A79990 SR02C - Termination 18 28-Apr-22 06-Jun-22 100%
SR22 ( LV25 - TR25) 58 26-Feb-22 13-Jun-22 12% 100.0% 11.5% 100.0% 12%
A91880 SR22 - Steel Frames Fab. & Erection 12 26-Feb-22 24-Mar-22 90% 100% 90% 100% 90%
A83800 SR22 - Cable Trays 12 28-Mar-22 07-Apr-22 100%
A80030 SR22 - LV25 & Bus Duct Installation 18 13-Apr-22 27-Apr-22 8% 100% 8% 100% 8%
A80030 SR22 - TR25 18 13-Apr-22 27-Apr-22 2% 100% 2% 100% 2%
A80040 SR22 - Cable Pulling 12 09-Apr-22 27-Apr-22 100%
A80050 SR22 - Termination 18 28-Apr-22 13-Jun-22 100%
Local Pannels & JB's Installation 100 15-Feb-22 12-Jun-22 3% 100.0% 3.3% 69.2% 2%
A82920 Local Panels & JB's Supports Fab, & erection 42 16-Feb-22 05-Apr-22 15% 100% 15% 68% 10%
A80090 Local Panels & JB's - Cable Pulling 42 02-Mar-22 19-Apr-22 100%
A80080 Local Panels & JB's Installation 42 05-Apr-22 29-May-22 85% 100% 85% 69% 59%
A80100 Local Panels & JB's - Termination 42 19-Apr-22 12-Jun-22 100%
Instrumentation Works (ISBL) 200 03-Mar-22 04-Aug-22 4% 100.0% 4.0% 40.9% 2%
A79670 ISBL - Inst. - Cable Trays Supports Fab. & Installation 63 01-Jan-22 20-Jan-22 100%
A82900 ISBL - Field Instrument Calibration 21 06-Feb-22 19-Mar-22 0% 100% 0%
A7486 ISBL - Inst. - Cable Trays 84 03-Mar-22 21-Jun-22 100%
A79630 ISBL - Inst. - J.B's & Local Pannels 78 05-Mar-22 22-Jun-22 0% 100% 0% 40% 0%
A79640 ISBL - Inst. - Cable Pulling 84 10-Mar-22 28-Jun-22 81% 100% 81% 44% 36%
A79660 ISBL- Inst. - Terminations 84 17-Mar-22 04-Aug-22 17% 100% 17% 29% 5%
Page 190 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A79650 ISBL - Field Instrument Installation 38 18-May-22 28-Jun-22 1% 100% 1%
A82910 ISBL - Field Instrument Tubing Installation 12 29-Jun-22 03-Aug-22 1% 100% 1%
Telecommunication Works 127 16-Jan-22 28-Jul-22 1% 100.0% 0.7% 11.5% 0%
Control Room (DCS) 30 15-May-22 24-Jul-22 65% 100% 65%
A5190 Control Room - DCS Pannels Installation (Machling) 18 15-May-22 29-Jun-22 30% 100% 30%
A83860 Control Room - Desk Top Installation 6 16-Jun-22 29-Jun-22 5% 100% 5%
A83870 Control Room - Cable laying & Termination 12 02-Jul-22 24-Jul-22 65% 100% 65%
Fire Alarm System 127 23-Jan-22 26-Jul-22 31% 100% 31% 30% 9%

A83400 ISBL - Fire Alarm - Cable Trays Supports Fab. & Erection 42 23-Jan-22 27-Feb-22 4% 100% 4% 100% 4%

A83410 ISBL - Fire Alarm - Cable Trays Installation 42 28-Feb-22 14-Apr-22 6% 100% 6% 100% 6%
A83420 ISBL - Fire Alarm - JB's Installation 42 28-Feb-22 14-Apr-22 3% 100% 3%
A83430 ISBL - Fire Detectors Installation 42 28-Feb-22 14-Apr-22 20% 100% 20% 22% 4%
A83440 ISBL - Fire Alarm - Cable Pulling 42 14-Mar-22 22-May-22 29% 100% 29% 55% 16%
A83450 ISBL - Fire Alarm - Termination 37 23-May-22 26-Jul-22 38% 100% 38%
Public Address System 104 16-Jan-22 28-Jul-22
ISBL - Public Adress - Cable Trays Supports Fab. &
A83460 40 16-Jan-22 03-Mar-22 100%
Erection
A83470 ISBL - Public Adress - Cable Trays Installation 40 05-Mar-22 19-Apr-22 100%
A83480 ISBL - Public Adress - JB's Installation 40 05-Mar-22 18-May-22 100%
A83490 ISBL - Public Adress - Speakers & Flashers Installation 40 05-Mar-22 18-May-22 100%
A83500 ISBL - Public Adress - Cable Pulling 40 16-Apr-22 29-Jun-22 100%
A83510 ISBL - Public Adress - Termination 40 19-May-22 28-Jul-22 100%
CCTV System 104 24-Mar-22 21-Jul-22 4% 100% 4% 50% 2%
A83520 ISBL - CCTV - Cable Trays Supports Fab. & Erection 40 24-Mar-22 15-May-22 19% 100% 19% 100% 19%
Page 191 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83540 ISBL - CCTV - JB's Installation 40 24-Mar-22 15-May-22 5% 100% 5%
A83530 ISBL - CCTV - Cable Trays Installation 40 07-Apr-22 29-May-22 29% 100% 29% 100% 29%
A83560 ISBL - CCTV - Cable Pulling 40 30-Apr-22 19-Jun-22 33% 100% 33% 5% 2%
A83550 ISBL - CCTV - Camera Installation 40 15-May-22 29-Jun-22 3% 100% 3%
A83570 ISBL - CCTV - Termination 40 05-Jun-22 21-Jul-22 11% 100% 11%
Data Network & IP Telephone-1 104 02-Apr-22 05-Jul-22
ISBL - Data Network & IP Telephone - Cable Trays
A83580 40 02-Apr-22 30-Apr-22 100%
Supports Fab. & Erection
ISBL - Data Network & IP Telephone - Cable Trays
A83590 40 16-Apr-22 06-Jun-22 100%
Installation
A83600 ISBL - Data Network & IP Telephone - JB's Installation 40 30-Apr-22 19-Jun-22 100%
ISBL - Data Network & IP Telephone - IP Telephone
A83610 40 30-Apr-22 19-Jun-22 100%
Installation
A83620 ISBL - Data Network & IP Telephone - Cable Pulling 40 02-May-22 20-Jun-22 100%
A83630 ISBL - Data Network & IP Telephone - Termination 40 19-May-22 05-Jul-22 100%
ISBL - F&G 139 16-Apr-22 04-Aug-22 0% 100.0% 0.5% 64.6% 0%
A83640 ISBL - F&G - Cable Trays Supports Fab. & Erection 46 16-Apr-22 01-Jun-22 26% 100% 26% 100% 26%
A79720 ISBL - F&G - Cable Trays 60 02-Jun-22 14-Jul-22 39% 100% 39% 100% 39%
A79730 ISBL - F&G - J.B's & Local Pannels 60 02-Jun-22 14-Jul-22 3% 100% 3%
A83650 ISBL - F&G - Detectors 60 02-Jun-22 14-Jul-22 2% 100% 2%
A79740 ISBL - F&G - Cable Pulling 60 16-Jun-22 28-Jul-22 21% 100% 21%
A79750 ISBL - F&G - Terminations 60 23-Jun-22 04-Aug-22 10% 100% 10%
HVAC 64 02-Feb-22 02-Aug-22 0% 100.0% 0.4% 49.0% 0%
A7550 HVAC - Prod. Line 64 02-Feb-22 02-Aug-22 100% 100% 100% 49% 49%
Fire- Fighing 108 02-Apr-22 06-Aug-22 0% 100.0% 0.3% 35.0% 0%
A78070 Fire Fighting Erection - Production Line 108 02-Apr-22 06-Aug-22 100% 100% 100% 35% 35%
Page 192 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Insulation 62 19-Mar-22 30-May-22 1.1% 100.0% 1.1% 42.4% 0%
A12860 Insulation PO & Delivery @ Site 30 30-Dec-21 23-Mar-22 40% 100% 40% 100% 40%
A80590 Thermal Insulation application 30 21-May-22 02-Jun-22 60% 100% 60% 4% 2%
A80640 Thermal Insulation application 30 03-Jul-22 07-Aug-22 100%
A80650 Thermal Insulation application 30 03-Jul-22 07-Aug-22 100%
Prod. Line Installation 140 17-Jan-22 06-Sep-22 27% 100.0% 26.8% 84.3% 23%
Prod. Line Installation (EP-Contractor Scope of Delivery) 179 17-Jan-22 06-Sep-22 84.3% 100.0% 84% 86.6% 73%
Overhead Crane 26 14-Mar-22 12-Apr-22 0.4% 100.0% 0% 100% 0%
A73130 Erection- Overhead Cranes 26 14-Mar-22 12-Apr-22 100% 100% 100% 100% 100%
Duct Work & Inspection Door 191 01-Feb-22 15-Aug-22 13.0% 100.0% 13% 83% 11%
Erection - Duct Works & exhaust Pipes - Chipper Line (1) -
n 36 26-Mar-22 17-Apr-22 2% 100% 2% 97% 2%
Group 1242 &1243
Erection - Pipe ducts with bends and flanges - Group 1321 /
40 05-Apr-22 28-Apr-22 2% 100% 2% 100% 2%
n 1331 / 1341
Erection - Pipe ducts with bends and flanges - Group 1531 40 06-Apr-22 30-Apr-22 1% 100% 1% 100% 1%
n
Fab.- Chutes, Doors & loose items - Group 2300 40 10-Apr-22 08-May-22 8% 100% 8% 59% 5%
n
Erection - Dryer Duct (From Dryer to High Efficiency
40 11-Apr-22 09-May-22 9% 100% 9% 100% 9%
n Cyclone) - Group 2420
Erection - Pipe ducts with bends and flanges - Group 2531 /
52 26-Apr-22 28-Jun-22 4% 100% 4% 100% 4%
n 2532 / 2533 / 2534
Fab.- Pneumatic Supports - Group 2600 52 07-May-22 05-Jul-22 4% 100% 4% 100% 4%
n
Erection - Duct Works & Pipes with bends and flanges -
52 02-May-22 04-Jul-22 10% 100% 10% 99% 10%
n Group 2615 / 2616
Erection - Pipe ducts with bends and flanges - Group 2770 /
48 02-May-22 27-Jun-22 3% 100% 3% 84% 3%
n 2780 / 2782 / 2785
Erection - Pipe ducts with bends and flanges - Group 3905 30 25-May-22 09-Jul-22 2% 100% 2% 48% 1%
n
Page 193 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Fab.- Silencer - Group 4200 24 06-Jun-22 23-Jul-22 1% 100% 1%
n
Erection - Duct Work, Pipes & Hoods - Group 4550 30 19-Jun-22 04-Aug-22 5% 100% 5% 98% 5%
n
Erection - Duct Work & Pipes - Group 4910 / 4920 / 4946 /
48 20-Jun-22 01-Aug-22 17% 100% 17% 78% 13%
n 4970 / 4975
Erection - Pipe ducts with bends and flanges - Group 5910 /
48 20-Jun-22 01-Aug-22 8% 100% 8% 85% 7%
n 5917 / 5920
Erection - Pipe ducts with bends and flanges - Group 7112 /
48 20-Jun-22 01-Aug-22 0% 100% 0% 48% 0%
n 7131
Erection - Duct work from combustion air fan to the burner -
48 20-Jun-22 31-Jul-22 0% 100% 0% 81% 0%
n Group 7370.061
Erection - Duct work from the Main ID fan to Dryer Mixing
24 21-Jun-22 01-Aug-22 1% 100% 1% 95% 1%
n Chamber - Group 7385.090
Erection - Crude gas duct - Group 7410 24 23-Jun-22 06-Aug-22 7% 100% 7% 79% 6%
n
Erection - Duct work from ambient air fan to mixing
24 02-Jul-22 13-Aug-22 0% 100% 0% 50% 0%
n chamber - Group 7385.065
Erection - Duct work from ambient air fan to quench
24 02-Jul-22 24-Jul-22 0% 100% 0% 100% 0%
n chamber - Group 7385.060
Erection - Duct work from cooling air fan to the burner -
40 06-Jul-22 19-Jul-22 0% 100% 0%
n Group 7370.062
Erection - Duct work from mixing chamber to cyclones -
40 10-Jul-22 23-Jul-22 0% 100% 0% 50% 0%
n Group 7385.065
Erection - Duct work from the main id fan to start up stack -
40 11-Jul-22 10-Aug-22 1% 100% 1% 95% 1%
n Group 7385.090
Erection - Duct work from thermal oil heater fan to mixing
40 11-Jul-22 15-Aug-22 2% 100% 2% 60% 1%
n chamber - Group 7390
Erection - Duct work from thermal oil heater to mixing
n 29 13-Jul-22 04-Aug-22 0% 100% 0% 50% 0%
chamber - Group 7385.065
Erection - Duct work from thermal oil heater to thermal oil
40 19-Jul-22 01-Aug-22 2% 100% 2% 60% 1%
n heater fan - Group 7390
Erection - Transport pipes ducts for dust - Group 7370 40 19-Jul-22 01-Aug-22 0% 100% 0%
n
Page 194 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Erection - Duct work from dust collector (Cyclones) to Ash
2 13-Mar-22 21-May-22 2% 100% 2% 100% 2%
n Crews - Group 7385.080
Erection - Duct work from dust collector (Cyclones) to Main
2 13-Mar-22 21-May-22 2% 100% 2% 75% 2%
n ID fan - Group 7385.080
Erection - Duct work from mixing chamber to the dust
1 01-Feb-22 03-Feb-22 100%
n collector - Group 7385.060
Erection - Duct Works & exhaust Pipes - Chipper Line (3) -
1 05-Feb-22 05-Feb-22 2% 100% 2% 97% 2%
n Group 1282 &1283
Erection - Duct Work & Pipes - Group 4998 / 4999 3 23-Feb-22 26-Feb-22 100%
n
Fab.- Air Girder (new scope) 6 23-Feb-22 26-Feb-22 2% 100% 2% 65% 1%
n
Erection - Duct Works & exhaust Pipes - Chipper Line (2) -
3 05-Mar-22 07-Mar-22 2% 100% 2% 97% 2%
n Group 1262 &1263
Erection - Duct work - lower section with transition duct -
3 05-Mar-22 07-Mar-22 100%
n Group 7390
Erection - Duct work - outlet duct with vertical flanges to
3 05-Mar-22 07-Mar-22 100% 100%
n dust collector - Group 7390
Safety Barriers & Fence 129 16-Apr-22 04-Jul-22 1.1% 100.0% 1%
A76810 Erection - Fences for drive station 65 16-Apr-22 11-Jun-22 20% 100% 20%
A76820 Erection - Fences for the Forming line 78 16-Apr-22 03-Jul-22 28% 100% 28%
A76840 Erection - Fences for Trimming Saw 40 16-Apr-22 10-May-22 8% 100% 8%
A80450 Erection - Fence for prepress 32 16-Apr-22 02-May-22 6% 100% 6%
A80460 Erection - Fence for intermediate belt station 75 16-Apr-22 21-Jun-22 24% 100% 24%
Erection- Electrical secured accesses door and flaps - GR-
A80620 22 30-May-22 04-Jul-22 14% 100% 14%
4599
Sound Cabient & Noise Protection Erection 129 01-Apr-22 13-Jul-22 1.2% 100.0% 1%
000443 Noise protected cabin for radial fan EQ No. 4540 & 4550 65 01-Apr-22 10-Apr-22 36% 100% 36%
000500 Noise protected cabinet EQ No. 5212 & 5214 78 09-May-22 21-May-22 36% 100% 36%
000558 Noise protected cabin sanding machine EQ No. 5442 40 15-May-22 22-May-22 6% 100% 6%
Page 195 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Noise protected cabin Longitudinal saw EQ No. 5452 & Dur B/L B/L
000559 32 23-May-22 26-May-22 13% 100% 13%
5462
000597 75 11-Jun-22 14-Jun-22 3% 100% 3%

000111 Sound Potection Equipment - Group 2420 22 28-May-22 02-Jun-22 3% 100% 3%

000175 Noise Reduction Cabinet - Group 2782 22 10-Jul-22 13-Jul-22 3% 100% 3%

Utilities & Buildings 537 07-Jul-20 07-Dec-22 36% 100% 36% 87% 32%
Site Preparations & Earth Work 492 07-Jul-20 31-Jul-22 1% 100.0% 1.3% 100.0% 1%
A81060 Site Preperation - OSBL 492 07-Jul-20 31-Jul-22 100% 100% 100% 100.0% 100%
Buildings / Warehouses 531 14-Jul-20 01-Dec-22 34% 100.0% 33.7% 95.2% 32%
Permanent TCF Building 171 14-Sep-20 01-Jan-22 10% 100% 10% 100% 10%
TCF - Construction 171 21-Oct-20 31-Aug-21 100% 100.0% 100.0% 100.0% 100%
A5590 Cut Works - TCF 15 21-Oct-20 08-Nov-20 3% 100% 3% 100.0% 3%
A5591 Backfilling with Crashed Stone - TCF 12 09-Nov-20 22-Nov-20 6% 100% 6% 100.0% 6%
A55911 Backfilling with Sand - TCF 22 23-Nov-20 17-Dec-20 1% 100% 1% 100.0% 1%
A5592 Concrete Works 25 19-Dec-20 17-Jan-21 40% 100% 40% 100.0% 40%
A5593 Steel Str, Sandwitch Panels & Finishing Works 62 01-Mar-21 30-Dec-21 50% 100% 50% 100% 50%
Substation Building 241 26-May-21 14-May-22 7% 100% 7% 97% 7%
Earth Work 61 26-May-21 11-Aug-21 16% 100.0% 16.0% 100.0% 16%
A77150 Cut Works - Substation Bldg. 7 26-May-21 02-Jun-21 53% 100% 53% 100.0% 53%
A77380 Backfilling (Replacement) - Substation Bldg. 7 03-Jun-21 10-Jun-21 47% 100% 47% 100.0% 47%
A77710 Backfilling - Substation Bldg. 7 03-Aug-21 11-Aug-21 0% 100% 0% 100.0% 0%
Concrete Works ( Cellar Floor) 66 12-Jun-21 18-Sep-21 27% 100.0% 26.8% 100.0% 27%
A5120 Plain Concrete 4 12-Jun-21 15-Jun-21 6% 100% 6% 100.0% 6%
A57321 RC Foundations 12 16-Jun-21 29-Jun-21 48% 100% 48% 100.0% 48%
Page 196 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57331 RC Columns & Walls 24 01-Jul-21 02-Aug-21 13% 100% 13% 100.0% 13%
A57341 RC Beams & Slabs 12 21-Aug-21 18-Sep-21 20% 100% 20% 100.0% 20%
A57351 Insulation 4 29-Jul-21 02-Aug-21 0% 100% 0% 100.0% 0%
A57361 RC Flooring 7 12-Aug-21 19-Aug-21 12% 100% 12% 100.0% 12%
Concrete Works ( 01st Floor) 36 05-Sep-21 17-Oct-21 7% 100.0% 7.3% 100.0% 7%
A78750 RC Columns & Walls 24 19-Sep-21 17-Oct-21 17% 100% 17% 100.0% 17%
A78760 RC Beams & Slabs 12 19-Oct-21 01-Nov-21 83% 100% 83% 100.0% 83%
Internal Finishing Works (Civil ) 42 02-Nov-21 20-Jan-22 16% 100.0% 16.3% 99.3% 16%
A57071 Masonary Works 6 02-Nov-21 22-Nov-21 21% 100% 21% 100% 21%
A78780 Plumbing Works 10 23-Nov-21 06-Dec-21 3% 100% 3% 100% 3%
A78790 Internal Plastering 12 23-Nov-21 13-Dec-21 42% 100% 42% 100% 42%
A78800 Doors & Windows 12 14-Dec-21 03-Jan-22 3% 100% 3% 80% 3%
A78810 Painting 24 15-Dec-21 20-Jan-22 21% 100% 21% 100% 21%
A78880 Ceramics / Tiles 12 14-Dec-21 03-Jan-22 10% 100% 10% 100% 10%
External Finishing Works (Civil ) 84 09-Dec-21 30-Apr-22 11% 100.0% 10.7% 100.0% 11%
A78030 External Plumbing Works (Sewage) 12 23-Feb-22 22-Mar-22 5% 100% 5% 100% 5%
A78820 External Plastering 24 16-Jan-22 22-Feb-22 53% 100% 53% 100% 53%
A78830 External Coat 24 23-Mar-22 30-Apr-22 21% 100% 21% 100% 21%
A78890 Roof Finish 24 09-Dec-21 15-Jan-22 21% 100% 21% 100% 21%
Lighting & Small Power 60 09-Nov-21 17-Mar-22 13% 100.0% 12.7% 94.7% 12%
A7395 PVC Conduit Installation 12 09-Nov-21 22-Nov-21 60% 100% 60% 100% 60%
A78660 Wire Pulling 12 05-Feb-22 17-Feb-22 100%
A78670 Pannels Erection 6 19-Feb-22 03-Mar-22 2% 100% 2% 100% 2%
A78680 Lighting Fixtures Erection (Substation) 6 19-Feb-22 03-Mar-22 5% 100% 5% 100% 5%
Page 197 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A78690 SW & Sockets 6 19-Feb-22 03-Mar-22 4% 100% 4% 100% 4%
A78700 Termination (Lighting-Substion) 12 05-Mar-22 17-Mar-22 11% 100% 11% 50% 5%
A78710 PVC Connection Boxes 9 23-Nov-21 02-Dec-21 18% 100% 18% 100% 18%
Fire-Fighting 12 24-Mar-22 14-May-22 2% 100.0% 2.3% 50.0% 1%
A78080 Fire Fighting Erection - Substation 12 24-Mar-22 14-May-22 100% 100% 100% 50% 50%
HVAC 38 03-Jan-22 14-Mar-22 4% 100.0% 3.8% 65.0% 2%
A75040 HVAC - Substation 26 08-Feb-22 14-Mar-22 100% 100% 100% 65% 65%
A78900 HVAC - Duct Works 12 03-Jan-22 07-Feb-22 100%
Telecomm. 22 28-Feb-22 14-May-22
A74850 CCTV - Substation Bldg. 22 24-Mar-22 20-Apr-22 100%
A74860 Public Adress - Substation Bldg. 22 05-Mar-22 31-Mar-22 100%
A74870 Data Network & IP Telephone - Substation Bldg. 22 30-Apr-22 14-May-22 100%
A74880 Fire Alarm - Substation Bldg. 22 28-Feb-22 27-Mar-22 100%
Electrical Works 119 01-Jan-22 07-May-22 4% 100.0% 4.2% 94.6% 4%
A82930 Cable Trays Supports Fab. & Erection 18 01-Jan-22 20-Jan-22 0% 100% 0%
A7320 Transformers Installation (Subsation) 12 08-Feb-22 21-Feb-22 5% 100% 5% 100% 5%
A7380 Cable Trays Works (Substaion) 52 15-Jan-22 14-Mar-22 28% 100% 28% 100% 28%
A7390 Cable Pulling 52 16-Feb-22 21-Mar-22 100%
A7400 Termination 41 22-Mar-22 07-May-22 100%
A78840 MV Switch Gear Installation 12 12-Feb-22 24-Feb-22 21% 100% 21% 100% 21%
A78850 LV Switch Gear Installation 12 15-Feb-22 28-Feb-22 4% 100% 4% 100% 4%
A78860 Bus Duct Installation 12 01-Mar-22 14-Mar-22 27% 100% 27% 100% 27%
A78870 UPS & Batteries Installation 6 01-Mar-22 07-Mar-22 7% 100% 7% 100% 7%
A82940 Distribution Pannels Installation 12 08-Mar-22 21-Mar-22 5% 100% 5% 33% 2%
Page 198 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A82950 Capacitor Banks Installation 6 15-Mar-22 21-Mar-22 2% 100% 2%
Warehouse For Chemical and Additive 169 30-Dec-21 14-Jun-22 1% 100% 1% 93% 1%
Earth Work 36 30-Dec-21 08-Feb-22 20% 100.0% 20.1% 100.0% 20%
A92580 Piles Works - Liquid Chemical Warehouse 4 30-Dec-21 01-Jan-22 75% 100% 75% 100.0% 75%
A77160 Cut Works - Liquid Chemical Warehouse 4 30-Dec-21 01-Jan-22 2% 100% 2% 100.0% 2%
A77390 Backfilling (Replacement) - Liquid Chemical Warehouse 4 02-Jan-22 05-Jan-22 18% 100% 18% 100.0% 18%
A77680 Backfilling - Liquid Chemical Warehouse 4 05-Feb-22 08-Feb-22 4% 100% 4% 100.0% 4%
Concrete Works 40 07-Jan-22 22-Feb-22 41% 100.0% 40.7% 100.0% 41%
A5150 Plain Concrete 4 07-Jan-22 10-Jan-22 7% 100% 7% 100.0% 7%
A57611 RC Foundations 8 11-Jan-22 19-Jan-22 84% 100% 84% 100.0% 84%
A57621 RC Columns 8 20-Jan-22 30-Jan-22 5% 100% 5% 100.0% 5%
A57631 Insulation 4 31-Jan-22 03-Feb-22 4% 100% 4% 100% 4%
A57641 RC Flooring 12 09-Feb-22 22-Feb-22 100% 100.0%
Steel Structure 52 23-Feb-22 13-Apr-22 1% 100.0% 1.1% 100.0% 1%
A73020 Cladding Works - Chemical and Additive Warehouse 26 24-Mar-22 13-Apr-22 100% 100% 100% 100.0% 100%
Finishing Works (Civil) 109 14-Apr-22 08-Jun-22 21% 100.0% 21.1% 100.0% 21%
A57651 Plumbing Works 26 14-Apr-22 19-May-22 14% 100% 14% 100% 14%
A78910 Ceramics / Tiles 26 27-Apr-22 31-May-22 57% 100% 57% 100% 57%
A78920 Doors & Windows 26 25-May-22 08-Jun-22 29% 100% 29% 100% 29%
Lighting & Small Power 53 14-Apr-22 28-May-22 11% 100.0% 10.9% 62.6% 7%
A82960 Cable Trays Supports Fab. & Erection 6 04-Apr-22 20-Apr-22 28% 100% 28% 100% 28%
A74610 Cable Trays Installation 6 21-Apr-22 28-Apr-22 32% 100% 32% 100% 32%
A78930 Wire Pulling 6 30-Apr-22 10-May-22 100%
A78940 Pannels Erection 3 11-May-22 14-May-22 7% 100% 7%
Page 199 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A78950 SW & Sockets 3 11-May-22 14-May-22 1% 100% 1% 100% 1%
A78960 Lighting Fixtures Erection (Chemical W.H) 6 11-May-22 17-May-22 11% 100% 11% 6% 1%
A78970 Termination (Lighting - Chemical W.H) 9 18-May-22 28-May-22 22% 100% 22% 6% 1%
Fire-Fighting 26 08-May-22 11-Jun-22 6% 100.0% 6.0% 50.0% 3%
A78090 Fire Fighting Erection - Liquid Chemeical Warehouse 26 08-May-22 11-Jun-22 100% 100% 100% 50% 50%
Telecomm. 22 01-Jun-22 14-Jun-22
A74890 CCTV - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A7490 Fire Alarm - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A74900 Public Adress - Chemical WH 22 01-Jun-22 14-Jun-22 100%
A74910 Data Network & IP Telephone - Chemical WH 22 01-Jun-22 14-Jun-22 100%
Scale With Room 190 06-Dec-21 07-Jun-22 3% 100% 3% 86% 3%
Earth Work 42 06-Dec-21 30-Jan-22 5% 100.0% 5.1% 100.0% 5%
A77100 Piles Work - Scale Room 1 06-Dec-21 14-Dec-21 89% 100% 89% 100.0% 89%

A92590 Cut Works - Scale Room 1 06-Dec-21 14-Dec-21 4% 100% 4% 100.0% 4%


A77400 Backfilling (Replacement) - Scale Room 1 15-Dec-21 19-Dec-21 6% 100% 6% 100.0% 6%
A77690 Backfilling - Scale Room 1 26-Jan-22 30-Jan-22 2% 100% 2% 100.0% 2%
Concrete Works 46 20-Dec-21 09-Feb-22 48% 100.0% 47.8% 100.0% 48%
A5170 Plain Concrete - Scale Room 6 20-Dec-21 22-Dec-21 7% 100% 7% 100.0% 7%
A57441 RC Foundations - Scale Room 9 23-Dec-21 02-Jan-22 88% 100% 88% 100.0% 88%
A57451 RC Columns - Scale Room 9 03-Jan-22 09-Jan-22 1% 100% 1% 100.0% 1%
A57461 RC Beams & Slabs - Scale Room 9 10-Jan-22 20-Jan-22 5% 100% 5% 100.0% 5%
A57471 Insulation - Scale Room 6 22-Jan-22 24-Jan-22 0% 100% 0% 100% 0%
A57481 RC Flooring - Scale Room 6 31-Jan-22 09-Feb-22 100% 100.0%
Internal Finishing Works (Civil) 48 10-Feb-22 10-Apr-22 20% 100.0% 19.9% 80.6% 16%
Page 200 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A81080 Masonary Works - Scale Room 6 10-Feb-22 20-Feb-22 19% 100% 19% 100% 19%
A81090 Plumbing Works - Scale Room 6 21-Feb-22 27-Feb-22 3% 100% 3% 100% 3%
A81100 Internal Plastering - Scale Room 12 28-Feb-22 09-Mar-22 38% 100% 38% 100% 38%
A81110 Ceramics / Tiles - Scale Room 12 10-Mar-22 20-Mar-22 19% 100% 19%
A81120 Doors & Windows - Scale Room 12 21-Mar-22 27-Mar-22 3% 100% 3% 80% 3%
A81130 Painting - Scale Room 12 21-Mar-22 10-Apr-22 19% 100% 19% 100% 19%
External Finishing Works (Civil) 84 01-Feb-22 26-Apr-22 13% 100.0% 13.1% 100.0% 13%
A81140 Roof Finish - Scale Room 24 01-Feb-22 28-Feb-22 19% 100% 19% 100% 19%
A81150 External Plastering - Scale Room 24 01-Mar-22 14-Mar-22 57% 100% 57% 100% 57%
A81160 External Plumbing Works (Sewage) - Scale Room 12 15-Mar-22 28-Mar-22 5% 100% 5% 100% 5%
A81170 External Paint - Scale Room - 24 29-Mar-22 26-Apr-22 19% 100% 19% 100% 19%
Equipment Installation 18 11-Apr-22 07-May-22 9% 100.0% 8.9%
A78040 Scale Room - Truck Scale Erection 18 11-Apr-22 07-May-22 100% 100% 100%
Lighting & Small Power 69 21-Feb-22 16-Apr-22 4% 100.0% 4.0% 78.2% 3%
A81180 PVC Conduit Installation 6 21-Feb-22 27-Feb-22 28% 100% 28% 100% 28%
A81190 PVC Connection Boxes 6 21-Feb-22 27-Feb-22 45% 100% 45% 100% 45%
A81200 Wire Pulling 6 28-Feb-22 06-Mar-22 100%
A81210 Pannels Erection 1 07-Mar-22 07-Mar-22 8% 100% 8%
A81220 SW & Sockets 2 07-Mar-22 08-Mar-22 5% 100% 5% 100% 5%
A81230 Lighting Fixtures Erection (Scale Room) 2 11-Apr-22 12-Apr-22 5% 100% 5%
A81240 Termination (Lighting-Scale Room) 3 13-Apr-22 16-Apr-22 9% 100% 9%
HVAC 38 11-Apr-22 20-Apr-22 1% 100.0% 1.2% 66.7% 1%
A75080 HVAC - Scale Room 38 11-Apr-22 20-Apr-22 100% 100% 100% 67% 67%
Telecomm. 14 11-Apr-22 07-Jun-22
Page 201 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A74840 Fire Alarm - Scale Room 14 11-Apr-22 07-May-22 100%
A7510 CCTV - Scale room 14 11-Apr-22 07-May-22 100%
A7520 Public Address - Scale Room 14 11-Apr-22 07-May-22 100%
A7530 Data Network & IP Telephone - Scale Room 14 30-Apr-22 07-Jun-22 100%
Catch Basin & Trench Covers 64 31-May-22 07-Jul-22 2% 100% 2% 75% 2%
A5258 Catch Basin , Sound Cabient ,Ditch & Genrator 64 31-May-22 07-Jul-22 33% 100% 33% 84% 28%
A5258 Trenches Cover 64 31-May-22 07-Jul-22 67% 100% 67% 71% 47%
HSE Building 254 15-Sep-21 29-Jun-22 11% 100% 11% 89% 10%
Earth Work 86 15-Sep-21 02-Nov-21 3% 100.0% 2.6% 100.0% 3%
A92600 Piles Works - HSE Building 2 15-Sep-21 16-Sep-21 25% 100% 25% 100.0% 25%
A77110 Cut Works - HSE Building 2 15-Sep-21 16-Sep-21 29% 100% 29% 100.0% 29%
A77410 Backfilling (Replacement) - HSE Building 2 18-Sep-21 19-Sep-21 37% 100% 37% 100.0% 37%
A77700 Backfilling - HSE Building 2 25-Oct-21 02-Nov-21 9% 100% 9% 100.0% 9%
Concrete Works (01st Floor) 56 20-Sep-21 25-Nov-21 26% 100.0% 26.0% 100.0% 26%
A5210 Plain Concrete - HSE Building 12 20-Sep-21 03-Oct-21 5% 100% 5% 100.0% 5%
Concrete Works for Control Room 20-Sep-21 03-Oct-21 12% 100% 12% 100.0% 12%
A57261 RC Foundations - HSE Building 12 04-Oct-21 19-Oct-21 50% 100% 50% 100.0% 50%
A57271 RC Columns - HSE Building 12 20-Oct-21 02-Nov-21 4% 100% 4% 100.0% 4%
A57281 RC Beams & Slabs - HSE Building 20 03-Nov-21 25-Nov-21 17% 100% 17% 100.0% 17%
A57291 Insulation - HSE Building 4 20-Oct-21 24-Oct-21 0% 100% 0% 100.0% 0%
A57301 RC Flooring - HSE Building 12 03-Nov-21 16-Nov-21 11% 100% 11% 100.0% 11%
Concrete Works (02 nd Floor) 30 27-Nov-21 30-Dec-21 0% 100.0% 0.0% 100.0% 0%
A81260 RC Columns - HSE Building 12 27-Nov-21 09-Dec-21 50% 100% 50% 100.0% 50%
A81270 RC Beams & Slabs - HSE Building 18 11-Dec-21 30-Dec-21 50% 100% 50% 100.0% 50%
Page 202 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Internal Finishing Works (Civil) 96 12-Dec-21 03-Apr-22 30% 100.0% 30.4% 88.7% 27%
A81280 Masonary Works - HSE Building 24 12-Dec-21 08-Jan-22 20% 100% 20% 100% 20%
A81290 Plumbing Works - HSE Building 12 09-Jan-22 22-Jan-22 2% 100% 2% 100% 2%
A81300 Internal Plastering - HSE Building 18 23-Jan-22 13-Feb-22 42% 100% 42% 100% 42%
A81310 Ceramics / Tiles - HSE Building 18 14-Feb-22 06-Mar-22 11% 100% 11%
A81320 Doors & Windows - HSE Building 12 07-Mar-22 20-Mar-22 2% 100% 2% 80% 2%
A81330 Internal Painting - HSE Building 24 07-Mar-22 03-Apr-22 23% 100% 23% 100% 23%
External Finishing Works (Civil) 103 06-Feb-22 07-May-22 13% 100.0% 13.3% 100.0% 13%
A81340 Roof Finish - HSE Building 24 06-Feb-22 05-Mar-22 26% 100% 26% 100% 26%
A81350 External Plastering - HSE Building 24 07-Mar-22 03-Apr-22 52% 100% 52% 100% 52%
A81360 External Plumbing Works (Sewage) - HSE Building 12 21-Mar-22 03-Apr-22 5% 100% 5% 100% 5%
A81370 External Painting - HSE Building 24 04-Apr-22 07-May-22 16% 100% 16% 100% 16%
Lighting & Small Power 114 19-Dec-21 07-May-22 14% 100.0% 13.7% 85.2% 12%
A81380 PVC Conduit Installation 18 19-Dec-21 08-Jan-22 22% 100% 22% 100% 22%
A81390 PVC Connection Boxes 12 09-Jan-22 22-Jan-22 57% 100% 57% 100% 57%
A81400 Wire Pulling 18 05-Feb-22 24-Feb-22 100%
A81410 Pannels Erection 2 26-Feb-22 27-Feb-22 1% 100% 1%
A81420 SW & Sockets 6 26-Feb-22 03-Mar-22 5% 100% 5% 100% 5%
A81430 Lighting Fixtures Erection (HSE) 12 04-Apr-22 17-Apr-22 4% 100% 4%
A81440 Termination (Lighting-HSE) 12 18-Apr-22 07-May-22 9% 100% 9%
HVAC 38 04-Apr-22 07-May-22 2% 100.0% 2.3%
A75100 HVAC - HSE Bldg. 38 04-Apr-22 07-May-22 100% 100% 100%
DCS Installation 38 16-Apr-22 18-May-22 3% 100.0% 2.8%
A91600 DCS Installation - HSE Bldg. 38 16-Apr-22 18-May-22 100% 100% 100%
Page 203 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Telecomm. 30 04-Apr-22 07-Jun-22
A74760 CCTV - HSE Bldg. 22 04-Apr-22 07-May-22 100%
A74770 Public Adress - HSE Bldg. 22 04-Apr-22 07-May-22 100%
A74780 Data Network & IP Telephone - HSE Bldg. 22 30-Apr-22 07-Jun-22 100%
A74790 Fire Alarm - HSE Bldg. 30 04-Apr-22 07-May-22 100%
Car Shed 112 15-Mar-22 29-Jun-22 9% 100.0% 8.8% 100.0% 9%
A57311 Civil Works - Car Shed 26 15-Mar-22 13-Apr-22 100% 100% 100% 100.0% 100%
A73110 Cladding Works - HSE Car Parking Shed 12 31-May-22 29-Jun-22 0% 100% 0% 100.0% 0%
Air Compressor Shed 129 29-Jan-22 09-May-22 2% 100% 2% 96% 2%
Earth Work 31 29-Jan-22 09-May-22 10% 100.0% 9.8% 100.0% 10%
A77190 Piles Works - Air Compressor Shed 6 29-Jan-22 06-Feb-22 73% 100% 73% 100.0% 73%

A92610 Cut Works - Air Compressor Shed 6 29-Jan-22 06-Feb-22 3% 100% 3% 100.0% 3%
A77430 Backfilling (Replacement) - Air Compressor Shed 6 07-Feb-22 10-Feb-22 19% 100% 19% 100.0% 19%
A77730 Backfilling - Air Compressor Shed 3 22-Feb-22 26-Feb-22 5% 100% 5% 100.0% 5%
Concrete Works 27 12-Feb-22 07-Mar-22 65% 100.0% 65.2% 100.0% 65%
A5253 Plain Concrete 4 12-Feb-22 13-Feb-22 5% 100% 5% 100.0% 5%
A72750 RC Foundation 8 14-Feb-22 19-Feb-22 94% 100% 94% 100.0% 94%
A72760 Insulation 4 20-Feb-22 21-Feb-22 1% 100% 1% 100% 1%
A72770 RC Flooring 8 27-Feb-22 07-Mar-22 100% 100.0%
Equipment Installation 12 29-Mar-22 11-Apr-22 21% 100.0% 20.6% 100.0% 21%
A72730 Erection- Air Compressor PKG 12 29-Mar-22 11-Apr-22 100% 100% 100% 100% 100%
Steel Structure 18 12-Apr-22 21-Apr-22 0% 100.0% 0.2% 100.0% 0%
A73070 Cladding Works - Air Comp. Shed 6 19-Apr-22 21-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 18 23-Apr-22 30-Apr-22 4% 100.0% 4.3%
Page 204 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A74660 Elect - Air Compressor Shed 18 23-Apr-22 30-Apr-22 100% 100% 100%
Telecomm. 12 23-Apr-22 09-May-22
A74960 Fire Alarm - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74970 CCTV - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74980 Public Adress - Air Compressor Shed 12 23-Apr-22 30-Apr-22 100%
A74990 Data Network & IP Telephone - Air Compressor Shed 12 30-Apr-22 09-May-22 100%
Industrial Pump Station 109 18-Jan-22 20-May-22 1% 100% 1% 92% 1%
Earth Work 32 18-Jan-22 17-Feb-22 10% 100.0% 10.3% 100.0% 10%
A77200 Piles Works - Industrial Water Pump Station 6 18-Jan-22 27-Jan-22 71% 100% 71% 100.0% 71%

A92620 Cut Works - Industrial Water Pump Station 6 18-Jan-22 27-Jan-22 5% 100% 5% 100.0% 5%
A77440 Backfilling (Replacement) - Industrial Water Pump Station 6 29-Jan-22 01-Feb-22 19% 100% 19% 100.0% 19%
A77740 Backfilling - Industrial Water Pump Station 4 14-Feb-22 17-Feb-22 5% 100% 5% 100.0% 5%
Concrete Works 28 02-Feb-22 27-Feb-22 68% 100.0% 68.5% 100.0% 68%
A5254 Plain Concrete 4 02-Feb-22 03-Feb-22 8% 100% 8% 100.0% 8%
A57081 RC Foundation 8 05-Feb-22 10-Feb-22 91% 100% 91% 100.0% 91%
A57091 RC Flooring 8 19-Feb-22 27-Feb-22 100% 100.0%
A57101 Insulation 4 12-Feb-22 13-Feb-22 1% 100% 1% 100% 1%
Equipment Installation 12 09-May-22 20-May-22 13% 100.0% 12.9% 100.0% 13%
A72800 Erection- Industrial Water Pumps 12 09-May-22 20-May-22 100% 100% 100% 100% 100%
Steel Structure 18 11-Apr-22 20-Apr-22 0% 100.0% 0.3% 100.0% 0%
A73030 Cladding Works - Industrial Water Pump Station 6 18-Apr-22 20-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 18 21-Apr-22 28-Apr-22 8% 100.0% 8.0%
A74670 Elect - Industrial Water Pump Station 18 21-Apr-22 28-Apr-22 100% 100% 100%
Potable Water Pump Station 110 16-Feb-22 20-May-22 1% 100% 1% 91% 1%
Page 205 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Earth Work 32 16-Feb-22 17-Mar-22 14% 100.0% 13.9% 100.0% 14%
A77230 Piles Works - Potable Pump Station 6 16-Feb-22 24-Feb-22 60% 100% 60% 100.0% 60%
A92630 Cut Works - Potable Pump Station 6 16-Feb-22 24-Feb-22 4% 100% 4% 100.0% 4%
A77470 Backfilling (Replacement) - Potable Pump Station 6 26-Feb-22 01-Mar-22 29% 100% 29% 100.0% 29%
A77770 Backfilling - Potable Pump Station 4 14-Mar-22 17-Mar-22 7% 100% 7% 100.0% 7%
Concrete Works 28 02-Mar-22 27-Mar-22 62% 100.0% 62.1% 100.0% 62%
A5257 Plain Concrete 4 02-Mar-22 03-Mar-22 10% 100% 10% 100.0% 10%
A57171 RC Foundation 8 05-Mar-22 10-Mar-22 89% 100% 89% 100.0% 89%
A57181 Insulation 4 12-Mar-22 13-Mar-22 1% 100% 1% 100% 1%
A57191 RC Flooring 8 19-Mar-22 27-Mar-22 100% 100.0%
Equipment Installation 12 09-May-22 20-May-22 15% 100.0% 14.6% 100.0% 15%
A72860 Erection- Potable Water Pumps 12 09-May-22 20-May-22 100% 100% 100% 100% 100%
Steel Structure 18 11-Apr-22 20-Apr-22 0% 100.0% 0.4% 100.0% 0%
A73060 Cladding Works - Potable Water Pump Station 6 18-Apr-22 20-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 12 21-Apr-22 28-Apr-22 9% 100.0% 9.1%
A74700 Elect - Potable Water Pump Station 12 21-Apr-22 28-Apr-22 100% 100% 100%
Reject Water Pump Station 109 16-Feb-22 20-May-22 1% 100% 1% 87% 1%
Earth Work 32 16-Feb-22 17-Mar-22 19% 100.0% 19.4% 100.0% 19%
A77210 Piles Works - Reject Water Pump Station 6 16-Feb-22 24-Feb-22 42% 100% 42% 100.0% 42%
A92640 Cut Works - Reject Water Pump Station 6 16-Feb-22 24-Feb-22 7% 100% 7% 100.0% 7%
A77450 Backfilling (Replacement) - Reject Water Pump Station 6 26-Feb-22 01-Mar-22 40% 100% 40% 100.0% 40%
A77750 Backfilling - Reject Water Pump Station 4 14-Mar-22 17-Mar-22 10% 100% 10% 100.0% 10%
Concrete Works 28 02-Mar-27 27-Mar-22 51% 100.0% 50.7% 100.0% 51%
A5255 Plain Concrete 4 02-Mar-22 03-Mar-22 9% 100% 9% 100.0% 9%
Page 206 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57111 RC Foundation 8 05-Mar-22 10-Mar-22 89% 100% 89% 100.0% 89%
A57121 Insulation 4 12-Mar-22 13-Mar-22 2% 100% 2% 100% 2%
A57131 RC Flooring 8 19-Mar-22 27-Mar-22 100% 100.0%
Equipment Installation 12 09-May-22 20-May-22 18% 100.0% 18.1% 90.0% 16%
A72830 Erection- Reject Water Pump Station 12 09-May-22 20-May-22 100% 100% 100% 90% 90%
Steel Structure 18 29-Mar-22 07-Apr-22 0% 100.0% 0.5% 100.0% 0%
A73040 Cladding Works - Reject Water Pump Station 6 05-Apr-22 07-Apr-22 100% 100% 100% 100.0% 100%
Lighting & Small Power 12 09-Apr-22 14-Apr-22 11% 100.0% 11.3%
A74680 Elect - Reject Water Pump Station 12 09-Apr-22 14-Apr-22 100% 100% 100%
Industrial Water Treatment PKG. 143 14-Feb-22 09-May-22 5% 100% 5% 96% 5%
Earth Work 35 14-Feb-22 15-Mar-22 8% 100.0% 7.7% 100.0% 8%
A77240 Piles Works - Industrial Water Treatment PKG. 4 14-Feb-22 20-Feb-22 84% 100% 84% 100.0% 84%
A92650 Cut Works - Industrial Water Treatment PKG. 4 14-Feb-22 20-Feb-22 2% 100% 2% 100.0% 2%
Backfilling (Replacement) - Industrial Water Treatment
A77490 10 21-Feb-22 24-Feb-22 11% 100% 11% 100.0% 11%
PKG.
A77790 Backfilling - Industrial Water Treatment PKG. 2 12-Mar-22 15-Mar-22 3% 100% 3% 100.0% 3%
Concrete Works 27 26-Feb-22 22-Mar-22 74% 100.0% 74.5% 100.0% 74%
A5259 Plain Concrete 3 26-Feb-22 27-Feb-22 9% 100% 9% 100.0% 9%
A77880 RC Foundation 12 28-Feb-22 08-Mar-22 89% 100% 89% 100.0% 89%
A77890 Insulation 4 09-Mar-22 10-Mar-22 0% 100% 0% 100% 0%
A77900 RC Columns 6 16-Mar-22 22-Mar-22 2% 100% 2% 100.0% 2%
Package Installation 68 23-Mar-22 02-May-22 18% 100.0% 17.8% 75.0% 13%
A72880 Erection- Industrial Water Treatment PKG. 68 23-Mar-22 02-May-22 100% 100% 100% 75% 75%
Telecomm. 22 05-Apr-22 09-May-22
A75000 Fire Alarm - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
Page 207 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A75010 CCTV - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
A75020 Public Adress - Industrial Water Treatment PKG. 22 05-Apr-22 02-May-22 100%
Data Network & IP Telephone - Industrial Water Treatment
A75030 22 30-Apr-22 09-May-22 100%
PKG.
Fire Pump Shed 137 02-Mar-22 30-May-22 1% 100% 1% 90% 1%
Earth Work 44 02-Nov-21 22-Dec-21 10% 100.0% 10.1% 100.0% 10%
A77180 Piles Works - Fire Pump Shed 12 02-Mar-22 15-Mar-22 74% 100% 74% 100.0% 74%
A77180 Cut Works - Fire Pump Shed 12 02-Mar-22 15-Mar-22 5% 100% 5% 100.0% 5%
A77480 Backfilling (Replacement) - Fire Pump Shed 12 16-Mar-22 22-Mar-22 17% 100% 17% 100.0% 17%
A77780 Backfilling - Fire Pump Shed 6 13-Apr-22 17-Apr-22 4% 100% 4% 100.0% 4%
Concrete Works 28 23-Mar-22 27-Apr-22 61% 100.0% 60.7% 100.0% 61%
A5252 Plain Concrete 3 23-Mar-22 26-Mar-22 8% 100% 8% 100.0% 8%
A57201 RC Foundation 8 27-Mar-22 09-Apr-22 91% 100% 91% 100.0% 91%
A57211 Insulation 3 10-Apr-22 12-Apr-22 1% 100% 1% 100% 1%
A57221 RC Flooring 8 18-Apr-22 27-Apr-22 100% 100.0%
Equipment Installation 12 07-May-22 20-May-22 22% 100.0% 22.0% 85.0% 19%
A72940 Erection- Fire Pumps 12 07-May-22 20-May-22 100% 100% 100% 85% 85%
Steel Structure 18 21-May-22 30-May-22 0% 100.0% 0.3%
A73080 Cladding Works - Fire Pump Shed 6 28-May-22 30-May-22 100% 100% 100%
Lighting & Small Power 12 28-May-22 30-May-22 7% 100.0% 6.9%
A74650 Elect - Fire Pump Shed 12 28-May-22 30-May-22 100% 100% 100%
New Switch Room 143 21-Feb-22 20-Jun-22 1% 100% 1% 82% 1%
Civil Work 35 21-Feb-22 13-Jun-22 87% 100.0% 86.8% 80.9% 70%
A92660 New Switch Room - Civil - Pile Works 4 21-Feb-22 25-Feb-22 9% 100% 9% 100.0% 9%
A92670 New Switch Room - Cut Works 12 02-Mar-22 15-Mar-22 1% 100% 1% 100.0% 1%
Page 208 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A92680 New Switch Room - Backfilling (Replacement) 12 16-Mar-22 22-Mar-22 100% 100.0%
A87160 New Switch Room - Civil - Concrete Works 4 21-Feb-22 13-Mar-22 46% 100% 46% 100.0% 46%
A87170 New Switch Room - Civil - Finishing Works 10 14-Mar-22 03-Apr-22 17% 100% 17% 100.0% 17%

A87190 New Switch Room - Civil - Raised Floor 12 05-Jun-22 13-Jun-22 17% 100% 17%

A87180 New Switch Room - Civil - Doors Fab. & Erection 6 07-Jun-22 13-Jun-22 10% 100% 10% 80% 8%
Electrical Work 27 26-Feb-22 20-Jun-22 13% 100.0% 13.2% 90.1% 12%
A91810 New Switch Room - Steel Frames Fab. & Erection 12 26-Feb-22 10-Mar-22 61% 100% 61% 100% 61%
A82880 New Switch Room - Cable Trays 12 11-Apr-22 21-Apr-22 100%
A79820 New Switch Room - LV12 & Bus Duct Installation 18 18-Apr-22 07-May-22 6% 100% 6% 100% 6%
A79820 New Switch Room - TR12 18 18-Apr-22 07-May-22 9% 100% 9% 100% 9%
A79830 New Switch Room - Cable Pulling 12 23-Apr-22 16-May-22 100%
A79840 New Switch Room - Lighting Fixtures 18 17-May-22 20-Jun-22 12% 100% 12% 58% 7%
A79840 New Switch Room - Termination (Lighting ) 18 17-May-22 20-Jun-22 11% 100% 11% 58% 7%
Main Security Building 187 12-Mar-22 01-Nov-22 2% 100% 2% 88% 2%
Earth Work 70 12-Mar-22 23-May-22 2% 87.6% 1.8% 100.0% 2%
A77120 Cut Works - Main Security Room 4 12-Mar-22 17-Mar-22 38% 100% 38% 100.0% 38%
A77510 Backfilling (Replacement) - Main Security Room 12 19-Mar-22 24-May-22 50% 100% 50% 100.0% 50%
A77810 Backfilling - Main Security Room 2 17-May-23 23-May-23 12% 100.0% 12%
Concrete Works 69 26-Mar-22 09-Jun-22 16% 100.0% 15.8% 100.0% 16%
A5250 Plain Concrete 3 26-Mar-22 28-Mar-22 6% 100% 6% 100.0% 6%
A57511 RC Foundations 15 29-Mar-22 11-Apr-22 28% 100% 28% 100.0% 28%
A57521 RC Columns 15 12-Apr-22 18-Apr-22 7% 100% 7% 100.0% 7%
A57531 RC Beams & Slabs 15 19-Apr-22 11-May-22 30% 100% 30% 100.0% 30%
A57541 Insulation 4 12-May-22 16-May-22 2% 100% 2% 100% 2%
Page 209 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A57551 RC Flooring 15 24-May-22 09-Jun-22 28% 100% 28% 100.0% 28%
Internal Finishing Works (Civil) 84 11-Jun-22 15-Oct-22 43% 100.0% 43.5% 82.8% 36%
A81720 Masonary Works - Main Security Room 12 11-Jun-22 09-Jul-22 13% 100% 13% 100% 13%
A81730 Plumbing Works - Main Security Room 12 10-Jul-22 06-Aug-22 5% 100% 5% 100% 5%
A81740 Internal Plastering - Main Security Room 18 07-Aug-22 27-Aug-22 13% 100% 13% 100% 13%
A81750 Ceramics / Tiles - Main Security Room 18 28-Aug-22 17-Sep-22 6% 100% 6%
A81760 Doors & Windows - Main Security Room 12 18-Sep-22 01-Oct-22 56% 100% 56% 80% 45%
A81770 Internal Painting - Main Security Room 24 18-Sep-22 15-Oct-22 7% 100% 7% 100% 7%
External Finishing Works (Civil) 123 03-Aug-22 26-Oct-22 18% 100.0% 17.7% 100.0% 18%
A81780 Roof Finish - Main Security Room 24 03-Aug-22 25-Aug-22 20% 100% 20% 100% 20%
A81790 External Plastering - Main Security Room 24 28-Aug-22 19-Sep-22 52% 100% 52% 100% 52%
A81800 External Plumbing Works (Sewage) - Main Security Room 12 20-Sep-22 03-Oct-22 12% 100% 12% 100% 12%
A81810 External Painting - Main Security Room 24 04-Oct-22 26-Oct-22 16% 100% 16% 100% 16%
Lighting & Small Power 81 10-Jul-22 25-Oct-22 18% 100.0% 17.6% 83.6% 15%
A81640 PVC Conduit Installation 6 10-Jul-22 16-Jul-22 24% 100% 24% 100% 24%
A81650 PVC Connection Boxes 6 17-Jul-22 23-Jul-22 50% 100% 50% 100% 50%
A81660 Wire Pulling 6 28-Aug-22 03-Sep-22 100%
A81670 Pannels Erection 1 07-Sep-22 07-Sep-22 6% 100% 6%
A81680 SW & Sockets 3 04-Sep-22 06-Sep-22 10% 100% 10% 100% 10%
A81690 Lighting Fixtures Erection (Main Security) 3 16-Oct-22 18-Oct-22 3% 100% 3%
A81700 Termination (Lighting-Main Securtiy) 6 19-Oct-22 25-Oct-22 7% 100% 7%
HVAC 45 16-Oct-22 01-Nov-22 3% 100.0% 3.4% 40.0% 1%
A75050 HVAC - Main Secuirty Bldg. 45 16-Oct-22 01-Nov-22 100% 100% 100% 40% 40%
Telecomm. 15 16-Oct-22 01-Nov-22
Page 210 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A74710 Fire Alarm - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74720 CCTV - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74730 Public Adress - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
A74740 Data Network & IP Telephone - Main Secuirty Bldg. 15 16-Oct-22 01-Nov-22 100%
Security Building 199 12-Mar-22 01-Nov-22 2% 100% 2% 89% 2%
Earth Work 70 12-Mar-22 23-May-22 2% 100.0% 2.1% 100.0% 2%
A77130 Cut Works - Security Building 4 12-Mar-22 17-Mar-22 38% 100% 38% 100.0% 38%
A77520 Backfilling (Replacement) - Security Building 12 19-Mar-22 24-Mar-22 50% 100% 50% 100.0% 50%
A77820 Backfilling - Security Building 2 17-May-22 23-May-22 12% 100% 12% 100.0% 12%
Concrete Works 69 26-Mar-22 09-Jun-22 16% 100.0% 16.1% 100.0% 16%
A5251 Plain Concrete 3 26-Mar-22 28-Mar-22 6% 100% 6% 100.0% 6%
A57561 RC Foundations 15 29-Mar-22 11-Apr-22 28% 100% 28% 100.0% 28%
A57571 RC Columns 15 12-Apr-22 18-Apr-22 7% 100% 7% 100.0% 7%
A57581 RC Beams & Slabs 15 19-Apr-22 11-May-22 30% 100% 30% 100.0% 30%
A57591 Insulation 4 12-May-22 16-May-22 2% 100% 2% 100% 2%
A57601 RC Flooring 15 24-May-22 09-Jun-22 28% 100% 28% 100.0% 28%
Internal Finishing Works (Civil) 84 11-Jun-22 15-Oct-22 44% 100.0% 44.2% 82.8% 37%
A81820 Masonary Works - Security Room 12 11-Jun-22 09-Jul-22 13% 100% 13% 100% 13%
A81830 Plumbing Works - Security Room 12 10-Jul-22 06-Aug-22 5% 100% 5% 100% 5%
A81840 Internal Plastering - Security Room 18 07-Aug-22 27-Aug-22 13% 100% 13% 100% 13%
A81850 Ceramics / Tiles - Security Room 18 28-Aug-22 17-Sep-22 6% 100% 6%
A81860 Doors & Windows - Security Room 12 18-Sep-22 01-Oct-22 56% 100% 56% 80% 45%
A81870 Internal Painting - Security Room 24 18-Sep-22 15-Oct-22 7% 100% 7% 100% 7%
External Finishing Works (Civil) 123 12-May-22 26-Oct-22 18% 100.0% 18.0% 100.0% 18%
Page 211 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A81880 Roof Finish - Security Room 24 12-May-22 04-Jun-22 20% 100% 20% 100% 20%
A81890 External Plastering - Security Room 24 28-Aug-22 19-Sep-22 52% 100% 52% 100% 52%
A81900 External Plumbing Works (Sewage) - Security Room 12 20-Sep-22 03-Oct-22 12% 100% 12% 100% 12%
A81910 External Painting - Security Room 24 04-Oct-22 26-Oct-22 16% 100% 16% 100% 16%
Lighting & Small Power 81 10-Jul-22 25-Oct-22 18% 100.0% 17.6% 87.0% 15%
A81920 PVC Conduit Installation 6 10-Jul-22 16-Jul-22 25% 100% 25% 100% 25%
A81930 PVC Connection Boxes 6 17-Jul-22 23-Jul-22 50% 100% 50% 100% 50%
A81940 Wire Pulling 6 28-Aug-22 03-Sep-22 100%
A81950 SW & Sockets 3 04-Sep-22 06-Sep-22 6% 100% 6% 100% 6%
A81960 Pannels Erection 1 07-Sep-22 07-Sep-22 10% 100% 10%
A81970 Lighting Fixtures Erection ( Security) 3 16-Oct-22 18-Oct-22 3% 100% 3% 100% 3%
A81980 Termination (Lighting- Securtiy) 6 19-Oct-22 25-Oct-22 6% 100% 6% 50% 3%
HVAC 45 16-Oct-22 01-Nov-22 2% 100.0% 2.1% 66.7% 1%
A75060 HVAC - Secuirty Bldg. 45 16-Oct-22 01-Nov-22 100% 100% 100% 67% 67%
Telecomm. 30 16-Oct-22 01-Nov-22
A74750 Fire Alarm - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74800 CCTV - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74810 Public Adress - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
A74820 Data Network & IP Telephone - Secuirty Bldg. 30 16-Oct-22 01-Nov-22 100%
Masjid Building [Mosque] 222 31-Mar-22 01-Nov-22 2% 100% 2% 90% 2%
Earth Work 75 31-Mar-22 03-Jul-22 3% 100.0% 3.3% 100.0% 3%
A77140 Cut Works - Masjid 2 31-Mar-22 02-Apr-22 37% 100% 37% 100.0% 37%
A77530 Backfilling (Replacement) - Masjid 2 03-Apr-22 04-Apr-22 51% 100% 51% 100.0% 51%
A77830 Backfilling - Masjid 2 02-Jul-22 03-Jul-22 13% 100% 13% 100.0% 13%
Page 212 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Concrete Works 86 05-Apr-22 20-Jul-22 24% 100.0% 23.6% 100.0% 24%
A5240 Plain Concrete 12 05-Apr-22 18-Apr-22 9% 100% 9% 100.0% 9%
A57381 RC Foundations 15 19-Apr-22 11-May-22 25% 100% 25% 100.0% 25%
A57391 RC Columns 15 12-May-22 29-May-22 14% 100% 14% 100.0% 14%
A57401 RC Beams & Slabs 15 30-May-22 15-Jun-22 26% 100% 26% 100.0% 26%
A57411 Insulation 12 16-Jun-22 29-Jun-22 1% 100% 1% 100.0% 1%
A57421 RC Flooring 15 04-Jul-22 20-Jul-22 25% 100% 25% 100.0% 25%
Internal Finishing Works (Civil) 84 07-Jul-22 12-Oct-22 34% 100.0% 33.9% 81.9% 28%
A82100 Masonary Works - Masjid 12 07-Jul-22 20-Jul-22 25% 100% 25% 100% 25%
A82110 Plumbing Works - Masjid 12 21-Jul-22 03-Aug-22 12% 100% 12% 100% 12%
A82120 Internal Plastering - Masjid 18 04-Aug-22 24-Aug-22 24% 100% 24% 100% 24%
A82130 Ceramics / Tiles - Masjid 18 25-Aug-22 14-Sep-22 16% 100% 16%
A82140 Doors & Windows - Masjid 12 15-Sep-22 28-Sep-22 12% 100% 12% 80% 9%
A82150 Internal Painting - Masjid 24 15-Sep-22 10-Dec-22 13% 100% 13% 100% 13%
External Finishing Works (Civil) 60 25-Aug-22 19-Oct-22 22% 100.0% 22.1% 100.0% 22%
A82170 External Plastering - Masjid 24 25-Aug-22 14-Sep-22 75% 100% 75% 100% 75%
A82180 External Plumbing Works (Sewage) - Masjid 12 15-Sep-22 28-Sep-22 0% 100% 0% 100% 0%
A82190 External Painting - Masjid 24 29-Sep-22 19-Oct-22 25% 100% 25% 100% 25%
Lighting & Small Power 87 21-Jul-22 30-Oct-22 12% 100.0% 11.9% 88.6% 11%
A82200 PVC Conduit Installation 6 21-Jul-22 27-Jul-22 45% 100% 45% 100% 45%
A82210 PVC Connection Boxes 6 28-Jul-22 03-Aug-22 23% 100% 23% 100% 23%
A82220 Wire Pulling 6 25-Aug-22 31-Aug-22 100%
A82230 SW & Sockets 3 01-Sep-22 04-Sep-22 7% 100% 7% 100% 7%
A82240 Pannels Erection 1 05-Sep-22 05-Sep-22 4% 100% 4%
Page 213 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A82250 Lighting Fixtures Erection (Mosque) 3 13-Oct-22 16-Oct-22 7% 100% 7% 100% 7%
A82260 Termination (Lighting- Mosque) 12 17-Oct-22 30-Oct-22 14% 100% 14% 50% 7%
HVAC 28 13-Oct-22 30-Oct-22 5% 100.0% 5.2% 50.0% 3%
A75070 HVAC - Mosque 28 13-Oct-22 30-Oct-22 100% 100% 100% 50% 50%
Telecomm. 10 13-Oct-22 01-Nov-22
A74830 Public Adress - Mosque 10 13-Oct-22 01-Nov-22 100%
Guard Towers 186 23-Apr-22 01-Nov-22 1% 100% 1% 52% 1%
Earth Work 126 23-Apr-22 18-Aug-22 12% 100.0% 11.9% 82.9% 10%
A77940 Piles Works - Guard Towers 120 01-Apr-22 31-Jul-22 72% 100% 72% 100.0% 72%
A92730 Cut Works - Guard Towers 120 23-Apr-22 11-Aug-22 4% 100% 4% 49.3% 2%
A77960 Backfilling - Guard Towers 120 02-May-22 18-Aug-22 24% 100% 24% 36.0% 9%
Concrete Works 156 12-May-22 04-Sep-22 49% 100.0% 49.2% 86.3% 43%
A56991 Plain Concrete 120 12-May-22 24-Jul-22 4% 100% 4% 88.9% 4%
A57001 RC Foundations 120 02-Jun-22 14-Aug-22 59% 100% 59% 83.6% 49%
A57011 RC Coulmns & Beams 120 23-Jun-22 04-Sep-22 35% 100% 35% 92.5% 33%
A57021 Insulation 120 23-Jun-22 04-Sep-22 1% 100% 1% 40% 1%
Finishing Works (Civil) 120 25-Jul-22 01-Nov-22 23% 100.0% 22.8%
A57031 Finishing .Works 120 25-Jul-22 01-Nov-22 100% 100% 100%
Lighting & Small Power 90 25-Jul-22 01-Nov-22 16% 100.4% 16.2%
A74560 Elect - Guard Towers 90 25-Jul-22 01-Nov-22 94% 100% 94%
A74560 Lighting Fixture - Guard Towers 90 25-Jul-22 01-Nov-22 6% 100% 6%
Rice Straw Warehouse 437 14-Jul-20 27-Jan-22 45% 100% 45% 100% 45%
A5610 Backfilling With Cut Material 44 14-Jul-20 08-Sep-20 11% 100% 11% 100.0% 11%

A5620 Backfilling With Supplied Material (Rice Straw Warehouse) 311 19-Jul-20 07-Jul-22 89% 100% 89% 100.0% 89%
Page 214 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Civil Works 311 10-May-21 07-Dec-22 39% 100.0% 39.3% 85.5% 34%
Tanks Civil Works 239 10-May-21 05-Jul-22 8% 100% 8% 82% 6%
Piles Works For Tanks 42 10-May-21 08-Jan-22 39% 100.0% 39.2% 100.0% 39%
A55961 Piles Works - Tanks (01st Batch) 42 10-May-21 10-Jun-21 73% 100% 73% 100.0% 73%
A86660 Piles Works - Fire Water Tank (02nd Batch) 42 16-Jan-21 08-Jan-22 27% 100% 27% 100.0% 27%
A91900 Piles Works - Potable Water Tank (02nd Batch) 42 16-Dec-21 29-Dec-21 100% 100.0%
Industrial Raw Water Tank Foundation 31 27-Jun-21 21-Sep-21 7% 100.0% 7.3% 100.0% 7%
A76970 Cut Works - Industrial Raw Water Tank (101A) 4 27-Jun-21 11-Jul-21 8% 100% 8% 100.0% 8%
A77310 Backfilling (Replacement) - Industrial Raw Water Tank 4 11-Jul-21 29-Jul-21 6% 100% 6% 100.0% 6%
A5670 Plain Concrete 4 31-Jul-21 03-Aug-21 14% 100% 14% 100.0% 14%
A56661 RC Foundations 10 04-Aug-21 06-Sep-21 64% 100% 64% 100.0% 64%
A56691 Insulation 3 07-Sep-21 11-Sep-21 8% 100% 8% 100% 8%
A77610 Backfilling - Industrial Raw Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Demi Water Tank Foundation 31 27-Jun-21 21-Sep-21 5% 100.0% 5.1% 100.0% 5%
A77040 Cut Works - DEMI Water Tank (103A) 4 27-Jun-21 11-Jul-21 9% 100% 9% 100.0% 9%
A77320 Backfilling (Replacement) - DEMI Water Tank 4 12-Jul-21 29-Jul-21 7% 100% 7% 100.0% 7%
A56761 Plain Concrete 4 31-Jul-21 03-Aug-21 12% 100% 12% 100.0% 12%
A56771 RC Foundations 10 04-Aug-21 06-Sep-21 61% 100% 61% 100.0% 61%
A56781 Insulation 3 07-Sep-21 11-Sep-21 11% 100% 11% 100% 11%
A77620 Backfilling - DEMI Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Process Water Tank Foundation 31 27-Jun-21 21-Sep-21 6% 100.0% 5.8% 100.0% 6%
A77050 Cut Works - Process Water Tank (102A) 4 27-Jun-21 11-Jul-21 9% 100% 9% 100.0% 9%
A77330 Backfilling (Replacement) - Process Water Tank 4 12-Jul-21 29-Jul-21 7% 100% 7% 100.0% 7%
A56791 Plain Concrete 4 31-Jul-21 03-Aug-21 13% 100% 13% 100.0% 13%
Page 215 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A56801 RC Foundations 10 04-Aug-21 06-Sep-21 61% 100% 61% 100.0% 61%
A56811 Insulation 3 07-Sep-21 11-Sep-21 10% 100% 10% 100% 10%
A77630 Backfilling - Process Water Tank 6 12-Sep-21 21-Sep-21 1% 100% 1% 100.0% 1%
Potable Water Tank Foundation 60 01-Jan-22 06-Mar-22 5% 100.0% 5.5% 100.0% 5%
A77060 Cut Works - Potable Water Tank 13 01-Jan-22 13-Jan-22 100%
A77340 Backfilling (Replacement) - Potable Water Tank 13 15-Jan-22 29-Jan-22 6% 100% 6% 100.0% 6%
A56821 Plain Concrete 6 30-Jan-22 05-Feb-22 14% 100% 14% 100.0% 14%
A56831 RC Foundations 15 06-Feb-22 22-Feb-22 68% 100% 68% 100.0% 68%
A56841 Insulation 4 23-Feb-22 27-Feb-22 10% 100% 10% 100% 10%
A77640 Backfilling - Potable Water Tank 9 28-Feb-22 06-Mar-22 1% 100% 1% 100.0% 1%
Fire Water Tank Foundation 60 09-Jan-22 31-Jan-22 5% 100.0% 4.5% 100.0% 5%
A77080 Cut Works - Fire Water Tank 13 09-Jan-22 10-Jan-22 12% 100% 12% 100.0% 12%
A77360 Backfilling (Replacement) - Fire Water Tank 13 11-Jan-22 15-Jan-22 5% 100% 5% 100.0% 5%
A56881 Plain Concrete 6 16-Jan-22 17-Jan-22 15% 100% 15% 100.0% 15%
A56891 RC Foundations 15 18-Jan-22 24-Jan-22 55% 100% 55% 100.0% 55%
A56901 Insulation 4 26-Jan-22 27-Jan-22 12% 100% 12% 100% 12%
A77660 Backfilling - Fire Water Tank 9 29-Jan-22 31-Jan-22 1% 100% 1% 100.0% 1%
Paving (Interlock) For Tanks 84 20-Apr-22 05-Jul-22 33% 100.0% 32.5% 45.0% 15%
A82280 Paving for OSBL - Tanks (Interlock) 24 20-Apr-22 05-Jul-22 100% 100% 100% 45.0% 45%
Roads / Paving 240 01-Dec-21 07-Dec-22 38% 100% 38% 68% 26%
A77990 Cut Works - Roads 228 01-Dec-21 14-Sep-22 17% 100% 17% 99.9% 17%
A78020 Backfilling - Roads 228 15-Dec-21 28-Sep-22 23% 100% 23% 98.5% 23%
A5710 Roads Activities - Paving 200 18-May-22 07-Dec-22 33% 100% 33% 14% 4%
A78480 Pits & Sheds 100 18-May-22 07-Dec-22 4% 100% 4% 45.9% 2%
Page 216 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91920 Pile Heads Demolishing (For thr Reamining) 60 21-Dec-21 14-Feb-22 11% 100% 11% 99.6% 11%
A78490 Roads Activities - Gravel Finish 100 18-May-22 07-Dec-22 11% 100% 11% 92.1% 10%
U/G Works - OSBL 64 26% 100% 26% 98% 25%
Potable Water Network 42 3% 100.0% 2.9% 99.9% 3%
A90970 Cut Works - Potable Water Network 52 20% 100% 20% 99.6% 20%
A90980 Bedding Layer - Potable Water Network 52 80% 100% 80% 100.0% 80%
A91000 Valve Bit - Potable Water Network 52 100%
A91010 Pressure Test - Potable Water Network 52 100%
A91020 Backfilling - Potable Water Network 52 100% 100.0%
Fire Fighting Network (HDBE) 42 2% 100.0% 2.2% 99.7% 2%
A91030 Cut Works - Fire Fighting Network 52 100% 100% 100% 99.7% 100%
A91040 Bedding Layer - Fire Fighting Network 52 100% 100.0%
Sewer Network 42 11% 100.0% 10.5% 95.7% 10%
A77980 Cut Works - Sewer Network 52 4% 100% 4% 100.0% 4%
A91070 Shoring & Dewatering - Sewer Network 52 100% 100.0%
A91080 Bedding Layer - Sewer Network 52 4% 100% 4% 100.0% 4%
A91090 Manholes (Concrete) - Sewer Network 52 82% 100% 82% 100.0% 82%
A91100 Piping Laying 52 3% 100% 3% 77.5% 3%
A91110 Grout Box - Sewer Network 52 100% 60.0%
A91120 Testing - Sewer Network 52 100% 60.0%
A78010 Backfilling & Insulation - Sewer Network 52 7% 100% 7% 45.9% 3%
A5680 Covering & Accessories - Sewer Network 52 100%
Storm Network 42 11% 100.0% 11.4% 94.5% 11%
A91150 Cut Works - Storm Network 52 11% 100% 11% 96.3% 11%
A91160 Shoring & Dewatering - Storm Network 52
Page 217 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91170 Bedding Layer - Storm Network 52 6% 100% 6% 95.2% 5%
A91180 Manholes (Concrete) - Storm Network 52 53% 100% 53% 96.3% 51%
A91190 Piping Laying 52 10% 100% 10% 79.2% 8%
A91200 Grout Box - Storm Network 52 100%
A91210 Testing - Storm Network 52 100%
A91220 Backfilling & Insulation - Storm Network 52 20% 100% 20% 96.1% 19%
A91230 Covering & Accessories - Storm Network 52 100%
Electrical Network (Concrete Trench) 42 66% 100.0% 66.4% 98.7% 66%
A77970 Cut Works - Electrical Network 52 1% 100% 1% 99.5% 1%
A91250 PC Concrete - Electrical Network 52 11% 100% 11% 100.0% 11%
A5685 RC Concrete - Electrical Network 52 64% 100% 64% 100.0% 64%
A78000 Insulation & Backfilling - Electrical Network 52 20% 100% 20% 95.7% 19%
A78000 Piping Laying 52 5% 100% 5% 92.2% 5%
Instrumentation Network 42 7% 100.0% 6.6% 95.6% 6%
A91280 Cut Works - E&I Network 52 4% 100% 4% 100.0% 4%
A91290 PC Concrete - E&I Network 52 29% 100% 29% 100.0% 29%
A78000 Insulation & Backfilling - E&I Network 52 3% 100% 3%
A78000 Piping Laying 52 64% 100% 64% 98.3% 63%
Remaining U/G Piping Network (Chemical Waste if Any) 42
A91620 U/G Piping Network (PVC) 52 100%
Piping Sleepers 60 02-Jan-22 12-Apr-22 1% 100% 1% 100% 1%
A78500 Piping Sleepers - Piles Works 150 15-Dec-21 21-Mar-22 31% 100% 31% 100.0% 31%
A78500 Piping Sleepers - Concrete Works 60 02-Jan-22 12-Apr-22 69% 100% 69% 100.0% 69%
Fences (External) 246 11-Oct-21 01-Dec-22 23% 100% 23% 100% 23%
Earth Work 156 11-Oct-21 04-Jun-22 20% 100.0% 20.2% 100.0% 20%
Page 218 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A91910 Piles Works - Fences 150 14-Mar-22 28-May-22 17% 100% 17% 100.0% 17%
A77930 Cut Works - Fences 150 11-Oct-21 30-Apr-22 23% 100% 23% 100.0% 23%
A77950 Backfilling - Fences 150 11-Nov-21 04-Jun-22 60% 100% 60% 100.0% 60%
Concrete Works 222 11-Jan-22 29-Nov-22 76% 100.0% 76.2% 99.6% 76%
A5700 Plain Concrete 150 11-Jan-22 04-Aug-22 12% 100% 12% 100.0% 12%
A56941 RC Foundations 150 12-Feb-22 04-Sep-22 53% 100% 53% 100.0% 53%
A56951 RC Coulmns & Beams 150 14-Mar-22 04-Oct-22 19% 100% 19% 100.0% 19%
A56961 Insulation 150 14-Mar-22 04-Oct-22 3% 100% 3% 100% 3%
A56971 Brick Works 150 15-May-22 29-Nov-22 14% 100% 14% 97% 13%
Wiremech 150 10-Jul-22 01-Dec-22 4% 100.0% 3.6% 98.0% 4%
A56981 Wiremech 150 10-Jul-22 01-Dec-22 100% 100% 100% 98% 98%
Gates 180 12-Jun-22 01-Dec-22 3% 100% 3% 95% 3%
A57041 Civil Works 60 12-Jun-22 21-Aug-22 9% 100% 9% 100.0% 9%
A57051 Gates Steel Delivery 90 12-Jun-22 21-Aug-22 45% 100% 45% 100% 45%
A57061 Gates Fabrication & Installation 90 22-Aug-22 01-Dec-22 45% 100% 45% 90% 41%
New Pipe Racks 180 12-Jun-22 01-Dec-22 0% 100% 0% 100% 0%
A91785 New Pipe Racks - Piles Works 60 12-Jun-22 21-Aug-22 41% 100% 41% 100.0% 41%
A92700 New Pipe Racks - Cut Works 90 12-Jun-22 21-Aug-22 4% 100% 4% 100.0% 4%
A92710 New Pipe Racks - Backfilling Works 90 12-Jun-22 21-Aug-22 22% 100% 22% 100.0% 22%
A92690 New Pipe Racks - Concrete Works 90 12-Jun-22 21-Aug-22 34% 100% 34% 100.0% 34%
Lighting Poles - Civil 180 21-Dec-21 28-Feb-22 1% 100% 1% 95% 1%
A91920 Lighting Poles - Piles 60 21-Dec-21 14-Feb-22 47% 100% 47% 100.0% 47%
A57051 Lighting Poles - Foundations 90 04-Jan-22 28-Feb-22 53% 100% 53% 91% 48%
Piping Works 217 13-Jan-22 27-Jun-22 9% 100.0% 8.9% 69.1% 6%
Page 219 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
Industrial (Indust.-Raw-Reject-Process-Demi) 115 01-Jan-22 31-May-22 4% 100% 3.9% 29% 1%
A58221 Piping & Piping Supports Fab. (SS) 43 01-Jan-22 20-Apr-22 64% 100% 64% 25% 16%
A58101 Piping & Piping Supports Erection (SS) 23 10-Feb-22 31-May-22 36% 100% 36% 35% 13%
HDPE & PP 115 #REF! 31-May-22 79% 100% 79.4% 82% 65%
A58101 Piping & Piping Supports Erection 23 10-Feb-22 31-May-22 100% 100% 100% 82% 82%
Piping Hydrotest & Re-Instatment 14 25-Apr-22 22-Jun-22 16% 100% 16% 18% 3%
A2010 Piping Hydrotest 14 25-Apr-22 15-Jun-22 50% 100% 50% 35% 18%
A79390 Re-Instatement & Touch Up 14 02-May-22 22-Jun-22 50% 100% 50%
Control & Safety Valves Erection 14 16-Jun-22 27-Jun-22 1% 100% 1%
A79380 Control & Safety Valves Erection 14 16-Jun-22 27-Jun-22 100% 100% 100%
Tanks Erection 205 01-Nov-21 06-Jun-22 9% 100.0% 9.3% 100.0% 9%
Industrial Raw Water Tank (101) 108 01-Nov-21 23-May-22 32% 100% 32% 100% 32%
A7300 Bottom, Shell & Top 78 01-Nov-21 12-Apr-22 78% 100% 78% 100% 78%
A79170 Hydrotest 6 13-Apr-22 19-Apr-22 2% 100% 2% 100% 2%
A79180 Sandblasting & Painting 12 20-Apr-22 09-May-22 15% 100% 15% 100% 15%
A79190 Accessories Erection 12 10-May-22 23-May-22 4% 100% 4% 100% 4%
DEMI Water Tank (103) 114 24-Nov-21 30-May-22 15% 100% 15% 100% 15%
A76110 Bottom, Shell & Top 84 24-Nov-21 19-Apr-22 74% 100% 74% 100% 74%
A79200 Hydrotest 6 20-Apr-22 27-Apr-22 4% 100% 4% 100% 4%
A79210 Sandblasting & Painting 12 28-Apr-22 16-May-22 16% 100% 16% 100% 16%
A79220 Accessories Erection 12 17-May-22 30-May-22 6% 100% 6% 100% 6%
Process Water Tank (102) 120 14-Nov-21 06-Jun-22 21% 100% 21% 100% 21%
A76120 Bottom, Shell & Top 87 14-Nov-21 26-Apr-22 78% 100% 78% 100% 78%
A79230 Hydrotest 6 28-Apr-22 09-May-22 3% 100% 3% 100% 3%
Page 220 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A79240 Sandblasting & Painting 12 10-May-22 23-May-22 15% 100% 15% 100% 15%
A79250 Accessories Erection 12 24-May-22 06-Jun-22 5% 100% 5% 100% 5%
Potable / Reject Water Tanks 36 07-Mar-22 17-Apr-22 2% 100% 2% 100% 2%
A76130 Potable Water Tank Erection 24 07-Mar-22 03-Apr-22 80% 100% 80% 100% 80%
A79280 Accessories Erection 12 04-Apr-22 17-Apr-22 20% 100% 20% 100% 20%
Fire Water Tanks 102 01-Mar-22 29-May-22 29% 100% 29% 100% 29%
A76150 Bottom, Shell & Top 72 01-Mar-22 02-May-22 75% 100% 75% 100% 75%
A79320 Hydrotest 6 07-May-22 12-May-22 2% 100% 2% 100% 2%
A79330 Sandblasting & Painting 12 14-May-22 26-May-22 15% 100% 15% 100% 15%
A79340 Accessories Erection 12 28-May-22 06-Jun-22 8% 100% 8% 100% 8%
OSBL- Electrical Works 201 08-Dec-21 30-Aug-22 4% 100.0% 3.6% 76.1% 3%
Earthing & Lightning Protection 101 08-Dec-21 14-Jun-22 9% 100% 9% 91% 8%
A7360 Earthing - Rods Installation 30 08-Dec-21 30-Jan-22 12% 100% 12% 47% 6%
A79450 Earthing - Cable Laying 60 31-Jan-22 23-Apr-22 100% 50%
A79460 Earthing - Termination 65 07-Feb-22 02-May-22 17% 100% 17% 92% 16%
A79470 Earthing - Bars & C-Clamps Installation 60 31-Jan-22 23-Apr-22 35% 100% 35% 97% 34%
A80740 Lightning Protection Works 45 24-Feb-22 14-Jun-22 36% 100% 36% 100% 36%
Electrical Connections 139 19-Feb-22 07-May-22 52% 100% 52% 91% 48%
OSBL - Cables Laying From Sub-Station to All Buildings,
A79480 90 19-Feb-22 17-Apr-22 86% 100% 86% 94.30% 81%
Packages & Pumps Station
A79490 OSBL - Cables Terminations 47 05-Mar-22 07-May-22 14% 100% 14% 73% 10%
Outdoor Lighting 176 01-Mar-22 30-Aug-22 39% 100% 39% 53% 20%
A7345 Lighting Poles Installation (street Lighting) 122 01-Mar-22 19-Jul-22 20% 100% 20% 70% 14%
A78990 Cable Laying (outdoor - OSBL) 122 13-Mar-22 31-Jul-22 25% 100% 25% 86% 21%
A79000 Lighting Fixtures (Outdoor) 122 27-Mar-22 14-Aug-22 10% 100% 10% 57% 5%
Page 221 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A79000 JB's Installation (Outdoor) 122 27-Mar-22 14-Aug-22 10% 100% 10% 31% 3%
A79010 Termination (Lighting - OSBL) 122 12-Apr-22 30-Aug-22 36% 100% 36% 25% 9%
OSBL - Instrumentation Works 122 01-Mar-22 04-Jun-22 1% 100.0% 1.3% 43.1% 1%
A7485 OSBL- Inst. - Cable Trays Installation 52 22-Mar-22 12-May-22 100%
A79510 OSBL - Inst. - Cable Pulling 52 30-Mar-22 21-May-22 62% 100% 62% 56% 35%
A79520 OSBL - Inst. - J.B's & Local Pannels 52 05-Mar-22 07-Apr-22 16% 100% 16%
A79530 OSBL - Inst. - Field Instrument Calibrations 18 01-Mar-22 04-Apr-22 3% 100% 3%
A79540 OSBL - Field Instrument Installation 34 01-Mar-22 04-Apr-22 6% 100% 6%
A79550 OSBL- Inst. - Terminations 52 13-Apr-22 04-Jun-22 3% 100% 3%
A83120 OSBL- Inst. - Cable Trays Supports Fab. & Erection 36 01-Mar-22 18-Mar-22 3% 100% 3% 100% 3%
A83130 OSBL- Inst. - Tubing Installation 52 05-Mar-22 07-Apr-22 7% 100% 7% 80% 6%
OSBL - F&G 85 19-Mar-22 01-Jun-22 1% 100.0% 0.8% 66.0% 1%
A79560 OSBL - F&G - Cable Trays Installation 20 16-Apr-22 18-May-22 40% 100% 40% 100% 40%
A79570 OSBL - F&G - J.B's & Local Pannels 20 16-Apr-22 18-May-22 1% 100% 1%
A79580 OSBL - F&G - Cable Pulling 20 23-Apr-22 25-May-22 27% 100% 27%
A79590 OSBL - F&G - Terminations 20 02-May-22 01-Jun-22 4% 100% 4%
A83100 OSBL - F&G - Cable Trays Supports Fab. & Erection 20 19-Mar-22 16-Apr-22 26% 100% 26% 100% 26%
A83110 OSBL - F&G - Detectors 20 16-Apr-22 18-May-22 3% 100% 3%
Outdoor - Telecommunication 45 20-Jan-22 07-Jun-22 2% 100.0% 1.8% 36.5% 1%
Outdoor - Fire Alarm 36 20-Jan-22 07-May-22 14% 100% 14% 21% 3%

A83140 OSBL - Fire Alarm - Cable Trays Supports Fab. & Erection 12 20-Jan-22 27-Feb-22 6% 100% 6% 100% 6%

A83150 OSBL - Fire Alarm - Cable Trays Installation 6 05-Feb-22 05-Apr-22 9% 100% 9% 100% 9%
A83160 OSBL - Fire Alarm - JB's Installation 6 28-Feb-22 05-Apr-22 2% 100% 2%
Page 222 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83170 OSBL - Fire Detectors Installation 6 28-Feb-22 05-Apr-22 12% 100% 12%
A83180 OSBL - Fire Alarm - Cable Pulling 12 14-Mar-22 19-Apr-22 43% 100% 43% 15% 6%
A83190 OSBL - Fire Alarm - Termination 6 26-Mar-22 07-May-22 29% 100% 29%
Outdoor - Public Adress 34 29-Jan-22 27-Apr-22 17% 100% 17% 3% 1%
OSBL - Public Adress - Cable Trays Supports Fab. &
A83200 12 29-Jan-22 03-Mar-22 1% 100% 1% 100% 1%
Erection
A83210 OSBL - Public Adress - Cable Trays Installation 6 05-Mar-22 07-Apr-22 2% 100% 2% 100% 2%
A83220 OSBL - Public Adress - JB's Installation 6 05-Mar-22 07-Apr-22 3% 100% 3%
A83230 OSBL - Public Adress - Speakers & Flashers Installation 6 05-Mar-22 07-Apr-22 19% 100% 19%
A83240 OSBL - Public Adress - Cable Pulling 10 16-Mar-22 19-Apr-22 29% 100% 29%
A83250 OSBL - Public Adress - Termination 6 23-Mar-22 27-Apr-22 45% 100% 45%
Outdoor - CCTV 34 08-Mar-22 23-Apr-22 42% 100% 42% 57% 24%
A83260 OSBL - CCTV - Cable Trays Supports Fab. & Erection 12 08-Mar-22 23-Mar-22 1% 100% 1% 70% 1%
A83270 OSBL - CCTV - Cable Trays Installation 6 24-Mar-22 09-Apr-22 66% 100% 66% 84% 56%
A83280 OSBL - CCTV - JB's Installation 6 24-Mar-22 09-Apr-22 1% 100% 1%
A83290 OSBL - CCTV - Camera Installation 6 24-Mar-22 09-Apr-22 5% 100% 5%
A83300 OSBL - CCTV - Cable Pulling 10 31-Mar-22 16-Apr-22 15% 100% 15%
A83310 OSBL - CCTV - Termination 6 07-Apr-22 23-Apr-22 11% 100% 11%
Outdoor - Data Network / IP telephone (Incl. Fiber Optical Cables) 34 20-Mar-22 28-Apr-22 27% 100% 27% 33% 9%
OSBL - Data Network & IP Telephone - Cable Trays
A83320 12 24-Mar-22 28-Apr-22 13% 100% 13% 100% 13%
Supports Fab. & Erection
OSBL - Data Network & IP Telephone - Cable Trays
A83330 6 31-Mar-22 10-May-22 19% 100% 19% 100% 19%
Installation
A83340 OSBL - Data Network & IP Telephone - JB's Installation 6 30-Apr-22 07-Jun-22 1% 100% 1%

OSBL - Data Network & IP Telephone - IP Telephone


A83350 6 30-Apr-22 07-Jun-22 13% 100% 13%
Installation Page 223 of 234
Original Start Finish Plan (Baseline) Actual
Activity ID Activity Name R.Wt.
Dur B/L B/L
A83360 OSBL - Data Network & IP Telephone - Cable Pulling 10 07-Apr-22 17-May-22 37% 100% 37% 3% 1%
A83370 OSBL - Data Network & IP Telephone - Termination 6 30-Apr-22 07-Jun-22 18% 100% 18%
Pre-commissioning 80 08-May-22 06-Dec-22 2.0% 100% 2%
OSBL- Pre-commissioning Related to EP CONTRACTOR
A89700 33 08-May-22 07-Jul-22 33% 100% 33%
(Petrojet SOW)
A86640 ISBL - Pre-commissioning Activities 33 07-Aug-22 06-Oct-22 33% 100% 33%

Page 224 of 234


MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
Rice Straw Preparation G.1000 6.00%

000017 1120 receiving conveyor 6 10.5 10.50 100% 0.19%


000018 1130 receiving conveyor 6 10.5 10.50 100% 0.19%
000019 1140 receiving conveyor 6 10.5 10.50 100% 0.19%
000022 1150.0 shuttle carraige 6 4.7 4.70 100% 0.09%
000021 1150.1 receiving conveyor 6 7.2 7.20 100% 0.13%
000020 CUSTOMER installation of rails for shuttle carraige 6 4.0 4.00 100% 0.07%
000024 1151.0 shuttle carraige 6 4.0 4.00 100% 0.07%
000023 1151.1 receiving conveyor 6 7.2 7.20 100% 0.13%
Straw Bale Destringing and Chopping Units G.1200 (Chipper lines ‐ 6%

Drum choppers ‐ Hammer mills)


000032 1231 feeding conveyor 1 6 3.5 3.50 100% 0.06%
000033 1232/1233 destringer unit 1 6 17.2 17.20 100% 0.31%
sub 1234 destringer unit round bales 1 6 10.1 10.10 100% 0.18%
000031
1234 transfer chain conveyor 1 6 9.2 9.20 100% 0.17%
000029 1291 scraper conveyor 6 22.7 22.70 100% 0.41%
000034
1240 drum chopper 1 6 22.6 22.59 100% 0.41%
'000035
000037 1242 hammer mill 1 6 12.1 12.09 100% 0.22%
000038 sub 1242 radial fan 1 5 3.0 3.03 100% 0.06%
000040 1258 shut‐off flap 1 5 2.0 2.00 100% 0.04%
000041 1243 round filter 1 5 12.7 12.70 100% 0.23%
000039 1248 fire protection screw conveyor 1 5 3.3 3.30 100% 0.06%
000045 sub (1260/1280) feeding conveyor 2 6 3.5 3.50 100% 0.06%
000046 1253 destringer unit 2 6 18.9 18.90 100% 0.35%
sub 1254 destringer unit round bales 2 6 10.6 10.60 100% 0.19%
00044
1254 transfer chain conveyor 2 6 10.5 10.50 100% 0.19%
000047
1260 drum chopper 2 6 23.3 23.30 100% 0.43%
'000048
000050 1262 hammer mill 2 6 11.4 11.44 100% 0.21%
000051 sub 1262 radial fan 2 5 3.1 3.10 100% 0.06%
000053 1278 shut‐off flap 2 5 2.0 2.00 100% 0.04%
000054 1263 round filter 2 5 13.1 13.10 100% 0.24%
000052 1268 fire protection screw conveyor 2 5 3.3 3.30 100% 0.06%
000058 1271 feeding conveyor 3 6 3.5 3.50 100% 0.06%
000059 1273 destringer unit 3 6 23.4 23.40 100% 0.43%
sub 1274 destringer unit round bales 3 6 10.5 10.50 100% 0.19%
000057
1274 transfer chain conveyor 3 6 9.5 9.50 100% 0.17%
000060
1280 drum chopper 3 6 25.6 25.60 100% 0.47%
'000061
000063 1282 hammer mill 3 6 11.8 11.76 100% 0.21%
000064 sub 1282 radial fan 3 5 3.1 3.10 100% 0.06%
000066 1298 shut‐off flap 3 5 2.0 2.00 100% 0.04%
000067 1283 round filter 3 5 12.5 12.50 100% 0.23%
000065 1288 fire protection screw conveyor 3 5 3.3 3.30 100% 0.06%
Straw Cleaning Area G.1300 (Silicat Separation Units) 6%

000071 1392 scraper conveyor 5 17.1 17.05 100% 0.31%


000072 1394 scraper conveyor 5 43.2 43.20 100% 0.79%
000073 1318 silicat separation unit 1 5 35.6 35.60 100% 0.65%
000074 1321 radial fan (pneumatic transport) 1 5 2.1 2.10 100% 0.04%
000075 1322 filter unit 1 5 7.5 7.43 99% 0.14%
000076 1338 silicat separation unit 2 5 35.6 35.60 100% 0.65%
000077 1331 radial fan (pneumatic transport) 2 5 2.1 2.10 100% 0.04%
000078 1332 filter unit 2 5 8.4 8.32 99% 0.15%
000079 1358 silicat separation unit 3 5 35.6 35.60 100% 0.65%
000080 1341 radial fan (pneumatic transport) 3 5 2.1 2.10 100% 0.04%
000081 1342 filter unit 3 5 7.8 7.72 99% 0.14%
000082 1398 trough chain conveyor 5 7.1 7.10 100% 0.13%
000083 1395 moisture analyser 5 0.1
Straw Bunker Area G.1500 6%

000086 1556 scraper conveyor 4 23.9 23.90 100% 0.44%


000087 1555 scraper conveyor 4 28.7 28.67 100% 0.52%
000088 1551 screw conveyor 4 2.6 2.60 100% 0.05%
000089 1552 belt conveyor 4 10.1 9.68 96% 0.18%
000090 1554 diverter flap Page 225 of 234 4 1.1 1.10 100% 0.02%
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000091 sub 4342 metal detector 4 0.5 0.50 100% 0.01%
000094 1530.310 straw bunker 4 18.3 18.30 100% 0.33%
000095 1530.320 rake conveyor 4 29.1 29.10 100% 0.53%
000096 1530.340 discharge rollers 4 9.5 9.50 100% 0.17%
000097 1530.330 bottom belt 4 42.8 42.80 100% 0.78%
000098 1530.350 bunker level indicators 4 2.2 2.20 100% 0.04%
000099 1557 belt conveyor 4 5.5 5.50 100% 0.10%
000100 sub 1557 trough chain conveyor 4 5.5 5.50 100% 0.10%
000101 1531 radial fan (pneumatic transport) 4 1.0 1.00 100% 0.02%
000102 1532 filter unit 5 2.6 2.60 100% 0.05%
000103 1530.300 Conditioning and dilution water system 4
Refiner G.2300 (PALLMANN) 6%

R0069 CUSTOMER installation of rails for digester 4 4.5 4.50 100% 0.08%
000107 2310 refiner system 1 4 165.1 156.85 95.0% 2.87%
000108 2332 refiner system 2 4 160.4 152.38 95.0% 2.79%
‐ ‐ main refiner unit (main & start motors) 4 76 ton done
‐ ‐ emergency lubrication refiner 4 ‐
‐ ‐ feed screw 4 ‐ done
‐ ‐ discharge screw 4 ‐ done
‐ ‐ digester 1st level 4 ‐ done
‐ ‐ plug screw 4 ‐ done
‐ ‐ blow back valve 4 ‐
‐ ‐ chip chute plug screw 4 ‐ done
‐ ‐ pre heating screw 4 ‐ done
‐ ‐ pin drum feeder 4 ‐ done
‐ ‐ main machinery complete 4 ‐ done
‐ CUSTOMER chip chute pin drum feeder 4 ‐
‐ ‐ central lubrication 4 ‐
‐ ‐ hydraulic unit 4 ‐
‐ ‐ sealing water feed screw 4 ‐
‐ ‐ sealing water unit mechanical seal 4 ‐
‐ ‐ hot water injection grinding room 4 ‐
‐ ‐ hot water injection pre heating screw 4 ‐
‐ ‐ Start cyclone 4 ‐ done
‐ ‐ piping & sealing 4 ‐
‐ CUSTOMER Vessel (Drain Box) ‐ Group 2310 / 2332 4 10.0
Dryer G.2400 (BÜTTNER) 6%

TR0032/33 CUSTOMER High Efficiency Cyclone ‐ Group 2420 2 50.2 50.20 100.0% 0.92%

TR0009 CUSTOMER Mixing chamber ‐ Group 2420‐022 ‐ Dryer (CH‐1030) 7 13.7 13.70 100% 0.25%

000111 2420/2422 Dryer area 7 30.1 27.39 91% 0.50%


‐ ‐ control and isolation damper 7 ‐ done
‐ ‐ Radial fan 7 12.6 ton done
‐ ‐ Safety water system 7 ‐
‐ ‐ Cyclone extinguishing systems 7 ‐
‐ ‐ Discharge rotary airlock 7 ‐ done
‐ ‐ Diverter flap 2‐way 7 ‐ done
‐ ‐ common equipment 7 ‐ ‐
On Top of Silicat Separation Units G.2500 6%

000153 2501 twin screw conveyor 2 9.0 9.00 100% 0.16%


000151 2502 twin screw conveyor 2 7.7 7.70 100% 0.14%
000152 2503 twin screw conveyor 2 7.7 7.70 100% 0.14%
000148 2505 distribution flap on silicat separation 2 0.6 0.60 100% 0.01%
000150 2506 distribution flap on silicat separation 2 0.6 0.60 100% 0.01%
000147 2511 twin screw conveyor (distribution type) 2 6.6 6.60 100% 0.12%
000149 2512 twin screw conveyor (distribution type) 2 6.6 6.60 100% 0.12%
Straw Fibre Preparation G. 2550 (Blender lines ‐ Fibre Belt Scale 6%

Bunker ‐ Silicat Separation Units)


000117
2551 blender line 1 with drive 2 20.2 11.49 57% 0.21%
'000118
Page 226 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000125
2552 blender line 2 with drive 2 20.2 11.49 57% 0.21%
'000126
000132
2553 blender line 3 with drive 2 20.2 11.49 57% 0.21%
'000133
000140
2554 blender line 4 with drive 2 20.2 11.49 57% 0.21%
'000141
000122 2520 silicat separation unit 1 2 33.6 33.58 100% 0.61%
000129 2522 silicat separation unit 2 2 33.6 33.58 100% 0.61%
000137 2525 silicat separation unit 3 2 33.7 33.67 100% 0.62%
000144 2528 silicat separation unit 4 2 33.7 33.67 100% 0.62%
000119
2541 belt scale bunker 1 2 11.2 11.20 100% 0.20%
'000120
000127
2542 belt scale bunker 2 2 11.0 11.02 100% 0.20%
'000128
000134
2543 belt scale bunker 3 2 10.7 10.74 100% 0.20%
'000135
000142
2544 belt scale bunker 4 2 10.7 10.74 100% 0.20%
'000143
000121 2548 moisture analyser 2 0.1
000136 2549 moisture analyser 2 0.1
A76440 CUSTOMER Cyclone Seperator ‐ Group 2531 2 8.3 8.30 100% 0.15%
A76430 CUSTOMER Cyclone Seperator ‐ Group 2532 2 8.3 8.30 100% 0.15%
A76460 CUSTOMER Cyclone Seperator ‐ Group 2533 2 8.3 8.30 100% 0.15%
A76450 CUSTOMER Cyclone Seperator ‐ Group 2534 2 8.3 8.30 100% 0.15%
000123 2531 radial fan (pneumatic transport) 1 2 2.2 2.20 100% 0.04%
000130 2532 radial fan (pneumatic transport) 2 2 2.0 2.00 100% 0.04%
000138 2533 radial fan (pneumatic transport) 3 2 1.9 1.90 100% 0.03%
000145 2534 radial fan (pneumatic transport) 4 2 1.7 1.70 100% 0.03%
000113 2592/2550/2555 troughed belt conveyor 2 37.3 35.81 96.0% 0.65%
000114 sub 4342 metal detector 2 0.5 0.50 100% 0.01%
000115 2591 flat belt conveyor 2 13.8 13.78 100.0% 0.25%
NEW CUSTOMER installation of rails of blender line 2 1.9 1.90 100% 0.03%
On Top of Straw Fibre Sifter System G.2590 6%

000159 2594 diverter flap on top sifter 2 1.3 1.30 100% 0.02%
000158 2595 distribution flap for sep. to sifter 2 0.9 0.90 100% 0.02%
000157 2596 twin screw conveyor 2 9.6 9.60 100% 0.18%
000155 2597 rotary airlock 2 1.2 1.20 100% 0.02%
000156 2598 rotary airlock 2 1.2 1.20 100% 0.02%
Straw Fibre Sifter System G.2600 6%

000163 2615 sifter unit 1 2 35.8 35.77 100% 0.65%

000168 2616 sifter unit 2 2 35.8 35.77 100% 0.65%

A76470 CUSTOMER Cyclone ‐ Group 2615/2616 1 36.5 36.50 100% 0.67%

HP Blower Unit with Filter G.2700 6%

000173 2770 radial fan (pneumatic transport) 2 0.7 0.70 100% 0.01%
000172 2771 filter unit 2 5.6 2.80 50% 0.05%
000174 2780 heat exchanger 2 1.2 1.20 100% 0.02%
000176 2781 trough chain conveyor 2 5.7 5.70 100% 0.10%
000175
2782/2783 HP rotary airlock with drive 5&3 1.2 1.20 100% 0.02%
'000603
000177 2784 pulverizer 3 4.9 2.62 54% 0.05%
000178 2785 radial fan (pneumatic transport) 3 6.5 6.50 100% 0.12%
000179 2786 round filter 3 4.5 4.37 97% 0.08%
000180 2787/2788 diverter flap on top silo 7140 3 0.7 0.70 100% 0.01%
Glue Preparation System G.3200 6%

000184
3211 PMDI storage & equipment 7 46.0 46.00 100% 0.84%
'000185
000183 CUSTOMER PMDI Storage Tank (4a.) 4 56.0 56.00 100% 1.02%
000190 3215.201 water transfer sys. (filter 1) 4 1.5 0.45 30% 0.01%
000191 3215.205 water transfer sys. (filter 2) 4 1.5 0.45 30% 0.01%
000194 3226.101 truck discharging station 4 2.0 2.00 100% 0.04%
000193 CUSTOMER Emulsion Storage Tank (7ea.) ‐ Group 3226 4 56.0 56.00 100% 1.02%
Page 227 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000195
3226.103 emulsion tanks/bins accessories 4 2.0 0.70 35% 0.01%
'000196
000197 3226.2 emulsion transfer system 4 0.6 0.60 100% 0.01%
Glue Dosing System G.3300 (Dosing ‐ Cleaning & Protection Agents ‐ 6%

Glue Mixing & Injection)


000201
'000202
'000203
'000204 3311 dosing PMDI system 7 2.0 1.50 75% 0.03%
'000205
'000206
'000207
000208
'000209
'000210 3312 dosing Polyol system 7 2.9 1.45 50% 0.03%
'000211
'000212
000215 3315.101 water transfer sys. (tank 1) 7 0.6 0.60 100% 0.01%
000216 3315.105 water transfer sys. (tank 2) 7 0.2 0.20 100% 0.00%
000217
'000218
'000219
3315.2 dosing water system 7 2.3 0.46 20% 0.01%
'000220
'000221
'000222
000226 3326.1 emulsion tank/reservoir 7 0.2 0.20 100% 0.00%
000227
3326.2 emulsion dosing system 7 0.3 0.30 100% 0.01%
'000228
000229
'000230
3330 cleaning & protection agents system 7 0.8
'000231
'000232
000233
'000234
'000235
3380.2 4 dynamic mixers (PMDI & Polyol) 7 1.2
'000236
'000237
'000232
000239
'000240 3390.2 Glue injection pipes 7 0.5
'000241
000242 3390.54 PMDI injection pipes 7 0.7
000243 3390.55 Blowline 7 0.3
Extraction System G.3905 6%

000244
3905 extraction system (fan) 2 2.4 2.40 100% 0.04%
'000245
Stations under Matformer G.4300 (Forming Line) 6%

000253 4399.1 foundation plates of forming line 1 0.9 0.90 100% 0.02%
000254 4310.111 tensioning station 1 3.3 3.30 100% 0.06%
000255 4310.211 Table for bottom spraying divice 1 1.0 1.00 100% 0.02%
000256 4310.311 Intermediate stations under the mat former 1 5.3 5.30 100% 0.10%
000257 4320 belt scale 1 0.8 0.80 100% 0.01%
Matformer G.4200 (Forming Line) 6%

000261 4220.856 General assembly aids 1 6.8 6.75 100% 0.12%


000263
4220.321 Chute under matformer 1 2.7 2.70 100% 0.05%
'000267
000262
4220.424 Forming head (starformer) 1 20.8 20.80 100% 0.38%
'000265
000266 4220.826 Discharge screw 1 1.6 1.60 100% 0.03%
000264
4220.528 Mat equalising unit level and align 1 10.4 10.40 100% 0.19%
'000268
000269 4310.412 Side walls for mat forming upstream of prepress 1 1.4 1.40 100% 0.03%

Page 228 of 234


MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000270
'000272 4220.212/250 Preassembling of bunker parts 1 31.0 31.00 100% 0.57%
'000273
000271 4220.211 limit switches (level monitoring) 1 0.5 0.50 100% 0.01%
000274 4220.213 Bunker leveling system 1 1.0 1.00 100% 0.02%
000275 4220.261 Drive for bunker belt 1 0.3 0.30 100% 0.01%
000276 4220.116 Fibre retarder on top of matformer 1 5.8 5.80 100% 0.11%
000277 4220.115 Distributor chute with drive 1 7.7 7.70 100% 0.14%
000278 4210.03 Douple screw placing on steel structure 1 10.0 10.00 100% 0.18%
000280 4210.781 Explosion vents isolation sys. 1 0.3
000279
4220.781 Explosion protection system 1 1.1 0.55 50% 0.01%
'000281
000282 4220.73 Customer supply explosion protection 1 0.3
000283 4220.21 Bunker belt 1 0.5 0.50 100% 0.01%
Forming Line after Matformer G.4300 (Pre‐press ‐ Edge Trimming 6%

Saw ‐ ancillary Eq. Table ‐ Reject Mat Hopper ‐ Drive Station ‐


Transfer Tray ‐ Forming Line Accessories) 6%

000286 4330.11 foundation plates of pre‐press 1 2.3 2.26 100% 0.04%


000288 4330.856/58 General assembly aids 1 2.4 2.40 100% 0.04%
000289 4330.120/130/150 bottom part of pre‐press 1 46.8 46.80 100.0% 0.86%
000290 4330.14 guide of pre‐press 1 0.3 0.26 85% 0.00%
000291 4330.3 upper part of pre‐press 1 42.2 42.19 100.0% 0.77%
000292 4330.2 main hydraulic cylinder 1 3.2 1.60 50% 0.03%
000293 4330.53/54 gear boxes for pre‐press 1 5.5 4.40 80% 0.08%
000294 4330.52 main drives pre‐press 1 1.6 1.60 100% 0.03%
000295 4330.42/43/44 air evacuation area 1 18.3 15.92 87% 0.29%
000296 4330.45 Side walls evacuation area 1 11.6 9.28 80% 0.17%
000297 4330.16 Side walls of pre‐ press 1 3.9 2.93 75% 0.05%
000298 4330.853/25 Limit switches, sensors 1 3.5 1.75 50% 0.03%
000300 4332.1 Hydraulic aggregat 1 1.0
000301 4332.7 Hydraulic connecting pipes 1 1.3
000303 4336.1 saw unit (gantry ‐ 2 carriage ‐ 2 trimming) 1 5.0
000304
4336.2 collecting hogger and limit switches 1 2.6
'000305
000308 4310.411 Tables for ancillary equipment 1 3.2 2.18 68% 0.04%
000309 sub 4342 metal detector 1 0.5
000310 4341 density mat scanner 1 0.2
000312 4350.014 disintegrating rollers with drives 1 2.4
000313 4350.01 reject mat hopper 1 1.8
000315 4310.556 transport aids (drive station) 1 0.8
000316
4310.511 drive station (frame, drive and gearbox) 1 10.5
'000317
000320 4380.11 Intermediate belt station 1 3.5
000321
4380.111/115 drive parts & gearbox 1 4.4
'000322
000323 4330.75 Servo motor 1 3.8 2.06 55% 0.04%
000324 4380.853 limit switches (transfer tray) 1 0.03
000325 4330.610/630 belt for intermediate station 1 7.4
000330 4328.01 peak detector upstream metal detector 1 0.5
000331 4382.01 Peak detector on intermediate belt 1 0.6
000332 4322.1 Infrared moisture analyser 1 0.4
000333 4327.2 Belt spraying device 1 0.9
000334 4344.2 Mat spraying device 1 1.5
000338 4310.6 Lay on and vulcanize forming line belt 1 1.0
000340 4220.852/853 Technical safety requirements for mat former 1 0.01
000342 4399.353 safety equip./sensors/fences for forming line 1 0.01
000343 4336.852 Safety equp. / fences for trimming saw 1 2.1
000344 4330.852 Safety equip. / fences for prepress 1 1.0 0.50 50% 0.01%
000345 4310.852 Safety equip. / fences for drive station 1 1.4
000346 4380.852/830 Safety equip. / fences for intermediate belt station 1 4.0
ContiRoll G.4520 6%

000349 4520.63 General assembly aids 1 1.0 1.00 100% 0.02%


000350 4520.111 foundation beams 1 97.1 97.07 100% 1.77%
000351 4520.327 Cleaning brush in outfeed area 1 1.1 1.10 100% 0.02%
000352 4520.324 Bottom belt support rolls 1 8.4 8.40 100% 0.15%
Page 229 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000353 4520.334 Insolations tunnel bottom 1 7.8 7.28 93% 0.13%
000354 4520.326 Bottom belt tracking unit 1 13.4 13.44 100% 0.25%
000355 4520.313 Drive shaft for bottom chain return system 1 4.5 4.50 100% 0.08%
000356 4520.31 Chain return guide bottom 1 7.8 7.83 100% 0.14%
000357 sub 4520.111 Press frames (59 Pieces) 1 358.8 358.80 100% 6.56%
000358 4520.112 Pressure distribution plates 1 123.0 123.00 100% 2.25%
000359 4520.314 Chain spanner on the last press frame 1 4.0 4.00 100% 0.07%
000363 4520.119 Collectors for secondary heating 1 2.3 2.30 100% 0.04%
000364 4520.315 Oil tray for chain guide 1 3.8 3.80 100% 0.07%
000365 4520.123 Center guide on the pressure distribution plates 1 2.3 2.30 100% 0.04%
000362
4520.117 Pulling of hot plates (Sandwich) with press cylinders 1 176.0 176.00 100% 3.22%
'000366
000367 4520.113 Press cylinder 1 85.0 85.00 100% 1.55%
000368 4520.114 Press cylinder mounting parts 1 8.5 6.11 72% 0.11%
000369 4520.137 Installation of isolation for hot plates 1 1.6
000370 4520.315 Installation of chain guide 1 3.8 3.80 100% 0.07%
000371 4520.21 Infeed head 1 29.1
000372 4520.313 Drive shaft for upper chain return system 1 3.9 3.90 100% 0.07%
000373 4520.319 Installtion of Infeed frame left and right 1 13.0
000374 4520.326 Upper belt tracking unit 1 13.4
000375 4520.321 Infeed drum 1 21.5
000376 4520.325 Installation of walk ways and handrails 1 73.0 58.40 80% 1.07%
000377 4520.316 Chain return guide upper 1 5.2 5.22 100% 0.10%
000378 4520.333 Isolation tunnel on the top of the Press 1 9.4 9.40 100% 0.17%
000379 4520.318 Cleaning brush in Infeed area 1 2.9 2.90 100% 0.05%
000380 4520.118 Hydraulic pipes 1 5.1
000381 4520.32 Pre‐assembling of outfeed frame 1 28.5 28.46 100% 0.52%
000382 4520.322 Outfeed drum 1 39.1 39.14 100% 0.72%
000383 4520.335 Gearbox mounting parts for main & chain drives 1 3.2 3.20 100% 0.06%
000384 4520.36 Mounting gearboxes with torque support 1 6.6 5.58 85% 0.10%
000385 4520.312 Mounting gearboxes for chain drives 1 9.8
000386 4520.361 Mounting main drives and chain drives 1 8.4 1.26 15% 0.02%
000387 4520.216 Infeed adjusting system 1 2.1
000388 4520.221 Roller‐rod‐guide 1 6.0
000389 4520.212 Infeed steel sheet covering 1 6.1
000390
'000391
'000392 4520.314 pneumatic and lubrication piping 1 11.5
'000393
'000394
000395
4520.328 oil aggregate and piping for lubrication 1 15.6
'000396
000397 4520.323 Suction and covering at outfeed area 1 8.4 8.40 100% 0.15%
000398 4520.331 Transfer roller conveyor 1 1.9
000399 4520.125 Remaining parts (Signboard) 1 0.2
000401 4520.253 Roller‐rod control (Sensors for infeed and oufeed) 1 0.2
000402 4520.41 Limit switches and position encoder 1 0.7
000403 4520.415 Temperature sensor (PT100) 1 0.7
000404 4520.417 Mounting parts position encoder (infeed drum) 1 0.7
000405 mounting parts position encoder (press distance) & measuring
4520.424/430 1 0.7
'000406 frame for control system
000407 4520.33 Steelbelt surface control system 1 0.1
000408
4520.317 roller rod & chain install (10,350 pieces) 1 35.4
'000409
000411 4520.363 Steel belt pulling 1 12.6
000413 4579 steel belt welding apparatus 1 0.1
000414 sub 4520.333/334 Isolation tunnel complement after Steel belt welding 1 9.4
000418 4540.01 Positioning of the hydraulic unit 1 10.0
000419 4540.014 Hydraulic beams on the stairway along the press 1 8.8 8.75 100% 0.16%
Connection hydraulic pipes between hydraulic unit & ContiRoll‐
000420 4540.013 1 12.1 11.57 96% 0.21%
press
000422 4571 steel belt cleaning device 1 3.6
000423 4572 release agent application device 1 9.6

Page 230 of 234


MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000425
'000426
'000427 4592 fire extinguishing system 1 9.8
'000428
'000429
000431 pump station and heating pipes between collectors and hot
4720.12 1 16.8 16.83 100% 0.31%
'000433 plates
000434 4720.13 Connecting heating pipes (Secondary site) 1 13.5 11.09 82% 0.20%
000435 heating pipes (Primary site)/purging & pneumatic pipes for
4720.11 1 15.6 12.78 82% 0.23%
'000436 rapid acting valve
Press Fume Extraction System for ContiRoll G.4550 6%

000441 4550.001 Positioning of sludge tanks 1 0.9 0.86 100% 0.02%


Containers (2ea.) for Sludge (Sedimentation tank) ‐ Group
000446 CUSTOMER 1 2.0
4550
000442 4550.012 Positioning of the radial fan 1 8.0 8.00 100% 0.15%
000444 4550.002 Positioning and installation of sedimentation tank 1 2.5 2.50 100% 0.05%
000445 4550.004 Installation platform on sedimentation tank 1 5.7 5.70 100% 0.10%
000447 4550.003 Positioning and installation of final separator 1 3.5 3.50 100% 0.06%
000448 4550.005 Positioning and installation of preseparator 1 1.5 1.50 100% 0.03%
000449 4550.017 Positioning and installation of pumps 1 1.4 1.40 100% 0.03%
000450 4550.016 Installation of modular component accessories 1 2.5 1.08 44% 0.02%
000451 4550.013 Installation screens 1 1.7 1.19 70% 0.02%
000452 4550.009 Installation of chutes for screens 1 0.9 0.45 50% 0.01%
000453 4550.006 Connecting of air pipes 1 18.8 15.45 82.0% 0.28%
000454 4550.007 Connecting of water pipes 1 6.0 5.34 89% 0.10%
000455 4550.903 Installation support structure for catwalk 1 1.4 1.40 100% 0.03%
000456 4550.008 water injection system (nozzle lances) 1 0.9
000457 4550.014 Installation of sensors 1 1.4
000458 sub 4550.903 Connecting pipes to WESP 2 2.0 1.00 50% 0.02%
Extraction System for Forming Line, Trimming & DD Saw G.4900 6%

000460 4910 Positioning radials fan for Forming line 2 3.6 3.60 100% 0.07%
000461 4911 Positioning and assembly from filter unit 2 12.6 12.60 100% 0.23%
000462 4920 Positioning radials fan for trimming and cross‐cut 2 4.9 4.90 100% 0.09%
000463 4946 Positioning radials fan for rejected material 2 4.3 4.30 100% 0.08%
000464 4947 Positioning and assembly from filter unit 2 13.0 13.00 100% 0.24%
000465 4949 Rotary Valve & Diverter flap on top of the Silo (7120) 2 6.6 6.60 100% 0.12%
000466 4970 Positioning radials fan for diagonal saw 4 3.0 3.00 100% 0.05%
000467 4971 round filter (DD‐ and trimming saw) 4 12.3 11.81 96% 0.22%
000468 4975 Positioning radial fan 2 1.5 1.50 100% 0.03%
000469
4976 Positioning and assembly from round filter 5 7.5 7.13 95% 0.13%
'000599
A76490 CUSTOMER Cyclone Seperator ‐ Group 4910 2 7.3 7.30 100% 0.13%
A76500 CUSTOMER Cyclone Seperator ‐ Group 4920 1 7.5 7.50 100% 0.14%
A76510 CUSTOMER Cyclone Seperator ‐ Group 4946 2 11.8 11.80 100% 0.22%
Cooling & Stacking Line G.5200 6%

000477
'000479
5253 cooling turner 1 1 10.5 10.50 100% 0.19%
'000481
'000484
000478
'000480
5256/5259 cooling turner 2 1 21.0 21.00 100% 0.38%
'000482
'000487
000483 5252/5254 roller conveyor 1 1 4.5 4.50 100% 0.08%
000484 5255/5257 belt conveyor for cooling turner 1 6.2 6.16 100% 0.11%
000485 5258/5260 roller conveyor 2 1 7.7 7.70 100% 0.14%
000488 5250 Board pusher for cooling‐turner 1 0.8 0.80 100% 0.01%
000489
5269 Roller conveyor between cooling‐turner & stacking table 1 2.4 2.40 100% 0.04%
'000490
000491 5270 Stacking table 1 5.3 5.30 100% 0.10%
CUSTOMER installation of rails for gripper carraige 1 4.1 4.10 100% 0.07%
000492
5271.1 Gripper carriage 1 7.4 7.40 100% 0.14%
000493 5271.2 Runway for gripper carriage 1 21.2 21.15 100% 0.39%
000496 5211 Roller conveyor after ContiRoll‐press outfeed 1 2.4
000497 5212 Longitudinal trimming saw 1 3.7
Page 231 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000498 5216 Saw table for Multi‐diagonal saw 1 4.5
000499 5214 Multiple‐diagonal saw 1 8.8
000500 5218 Noise protected cabinet 1 0.8
000501 5217 Accel. roller conveyor after Multi‐diagonal saw 1 2.8
000502 5221 Belt conveyor on raw board scale 1 1.8
000503 5222 Raw board scale 1 0.3
000504 5226 Stacking roller conveyor under reject board station 1 4.7 4.70 100% 0.09%
000505 5225 Reject board station 1 11.1 11.10 100% 0.20%
000506 5227 Roller conveyor for recject board station 1 2.2
000507 5200.04 Limit switches equipment 1 1.2
000510 sub 5211 Safety fences for cool‐ and stacking line 1 0.3
000511 5200.043/5000 Safety equipment 1 0.6
Storage System G.5300 6%

000514 CUSTOMER installation of rails for storage system 1 89.5 44.75 50% 0.82%
000515 5311 Base vehicle 1 12.7 12.70 100% 0.23%
000516 5312 Basic carriage SFG 1 1 3.4
000517 5313 Basic carriage SFG 2 1 3.4
000518 5390 Limit switches equipment 1 0.8
000520
5300 safety fences & sensors for storage 1 0.5
'000521
Sanding Line G.5400 6%

000526 5442 Sanding machine system 1 62.8 62.77 100% 1.15%


000524
CUSTOMER installation of rails for conveyor with fixing material 1 6.0 6.00 100% 0.11%
'000525
000527 5443 Roller conveyor 1 2.9 2.90 100% 0.05%
000528 5439 Roller conveyor 1 2.1 2.05 100% 0.04%
000529 5447 Roller conveyor 1 2.9 2.90 100% 0.05%
000530 5448 Roller conveyor 1 4.1 4.10 100% 0.07%
000531 5445 Inspection station 1 1.6 1.55 100% 0.03%
000532 5467 Board cleaning unit 1 3.8 3.77 100% 0.07%
000533 5452 Longitudinal saw 1 5.1 5.10 100% 0.09%
000534 5459 Roller conveyor 1 2.1 2.06 100% 0.04%
000535 5461 Feeding table 1 8.0 8.00 100% 0.15%
000536 5462 Cross‐cut saw 1 8.5 8.50 100% 0.16%
000537 5465 Roller conveyor before angular station 1 3.7 3.70 100% 0.07%
000538 5466 Angular station 1 6.0 6.00 100% 0.11%
000539 5467 Roller conveyor 1 5.5 5.47 100% 0.10%
000540 5468 Board cleaning unit 1 0.9 0.85 100% 0.02%
000541 5469 Roller conveyor 1 3.8 3.80 100% 0.07%
000542 5441 Roller conveyor 1 4.1 4.10 100% 0.07%
000543 5416 Stack roller conveyor with lifting plat. and hydraulic 1 21.9 21.87 100% 0.40%
000544 5417 Roller conveyor 1 2.6 2.55 100% 0.05%
000545 5419 Feeding station 1 4.7 4.70 100% 0.09%
000546 5412 Chain conveyor 1 6.3 6.30 100% 0.12%
000547 5425.1 Suction carriage 1 2.3 2.30 100% 0.04%
000548 5425.2 Suction carriage track 1 6.9 6.90 100% 0.13%
000549 5470 Stack station under roller conveyor (3 pieces) 1 31.7 31.72 100% 0.58%
000550 5473/5474 intermediate roller conveyor/stach conveyor & station 1 3.2 3.20 100% 0.06%

000551 5478/5479 intermediate roller conveyor/stach conveyor & station 1 3.2 3.20 100% 0.06%

000552 5483/5484 intermediate roller conveyor/stach conveyor & station 1 3.2 3.20 100% 0.06%
000553 5491 Transfer carriage‐ stack 1 2.0 2.00 100% 0.04%
000554 5492 Transfer carriage‐ stack 1 4.2 4.20 100% 0.08%
000555 5490 Protection board feeder 1 6.8 6.80 100% 0.12%
000556 5493 Stack chain conveyor 1 3.5 3.50 100% 0.06%
000557 5494 Stack roller conveyor 1 2.8 2.80 100% 0.05%
000560
'000563 5400 safety fences, sensors & limit switches 1 2.4 1.56 65% 0.03%
'000564
Packing Line G.5700 6%

000567 5711 Stack roller conveyor 1 3.0 3.00 100% 0.05%


Page 232 of 234
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
000568 5725 Longitudinal strapping system 1 0.2 0.20 100% 0.00%
000569 5724 Stack chain conveyor 1 2.2 2.24 100% 0.04%
000570 5729 Stack chain conveyor 1 2.3 2.30 100% 0.04%
000571 5730 Cross strapping system 1 1.5 1.50 100% 0.03%
000572 5731 Stack chain conveyor 1 2.8 2.76 100% 0.05%
000573 5732 Stack chain conveyor 1 3.1 3.13 100% 0.06%
000574
'000576 5700 safety fences, sensors & limit switches 1 1.8 1.17 65% 0.02%
'000577
Extraction System for Finishing Line, Sanding Machine, Trimming Saw 6%

at Sanding Line G.5900


000579 5910 radials fan with drive for sanding machine 1 6.2 6.08 98% 0.11%
000580 5911 lifting platform (filter unit) 1 17.0 16.85 99% 0.31%
000581 5917 HP‐rotary airlock with drive for Silo (7110) 1 0.7 0.70 100% 0.01%
000582 5918 longitudinal feed for round filter (sanding dust) 3 2.8 2.74 98% 0.05%
000583 5920 Positioning radials fan with drive for cut‐to‐size 4 3.3 3.25 100% 0.06%
000584 5921 round filter 4 11.9 11.66 98% 0.21%
Silo Extraction System G.7100 6%

000588 7110 discharge device & comp. for sanding silo 3 7.7 6.81 89% 0.12%
'000589 CUSTOMER Sanding dust Silo ‐ Group 7110 3 60.0 60.00 100% 1.10%
000590 7112 HP rotary airlock with drive 3 0.8 0.40 50% 0.01%
000592 7120 discharge device & comp. for reject fiber silo 2 14.0 12.46 89% 0.23%
'000593 CUSTOMER Reject Fiber Silo ‐ Group 7120 2 60.0 60.00 100% 1.10%

000595 7130 discharge device & comp. for saw dust silo 5 9.1 8.10 89% 0.15%
'000596 CUSTOMER Saw Dust Silo ‐ Group 7130 5 55.0 55.00 100% 1.01%
000597 7131 Screw conveyor straw fibre 4 1.5 1.50 100% 0.03%
000598 7132 HP rotary airlock with drive 4 1.4 1.40 100% 0.03%
000601 7140 discharge device & comp. for pulverizer silo 3 11.5 10.47 91% 0.19%
'000602 CUSTOMER Pulverizer Silo ‐ Group 7140 3 65.0 65.00 100% 1.19%
Energy Plant G.7300 (BÜTTNER) 6%

000606 7385/7370 combustion system 3 40.3 35.67 88.5% 0.65%


‐ ‐ Sander Dust Metering Bin 1 & 2 3 ‐ in progress
‐ ‐ Gas Burner 3 ‐ ‐
‐ ‐ Flue Gas Cleaning System 3 ‐ ‐
‐ ‐ Main ID Fan & Ambient air fans 3 ‐ done
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (R1) 3 8.0 8.00 100% 0.15%
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (R2) 3 8.0 8.00 100% 0.15%
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (R3) 3 8.0 8.00 100% 0.15%
EA0058
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (L1) 3 8.0 8.00 100% 0.15%
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (L2) 3 8.0 8.00 100% 0.15%
CUSTOMER Cyclone Flue Gas ‐ Group 7385 (L3) 3 8.0 8.00 100% 0.15%
EA0035/36 CUSTOMER Vertical combustion ch. ‐ Group 2425.016 ‐ EP (CH‐1000) 3 40.1 40.10 100.0% 0.73%
EA0042 CUSTOMER refractory for vertical combustion ch. 3 159.3 95.58 60.0% 1.75%
EA0046 CUSTOMER Quench chamber ‐ Group 7385.060 ‐ EP (CH‐1010) 3 8.5 8.50 100% 0.16%
EA0047 CUSTOMER refractory for Quench chamber 3 28.5 17.10 60.0% 0.31%
EA0055 CUSTOMER Mixing chamber ‐ Group 7385.065 ‐ EP (CH‐1020) 3 15.1 15.10 100% 0.28%
EA0143 CUSTOMER refractory for Mixing chamber 3 14.5 4.35 30% 0.08%
EA0037 CUSTOMER Emergency Stack ‐ Group 2425.016 (ST‐1000) 3 10.0 10.00 100% 0.18%
EA0076 CUSTOMER Start‐up Stack ‐ Group 7385.090 (ST‐1010) 3 45.0 45.00 100% 0.82%
000607
7390/7395/7397 thermal fluid & steam systems 3 98.9 63.26 64.0% 1.16%
'000608
‐ ‐ thermal oil heater ID fan 3 ‐ done
‐ ‐ Primary Circulation (pumps / motors / fittings) 3 ‐ in progress
‐ ‐ fill and dain pumps (2 ea.) 3 ‐ done
‐ ‐ Hot Water Heat Exchanger 3 ‐ ‐
‐ ‐ Steam Generator Page 233 of 234
3 ‐ done
MDF EQUIPMENT INSTALLATION CONTROL SHEET
As of date: 11‐Feb‐23
Estimated Actual
Activity Actual
Group Description Plot Weight
ID Qty (ton) Item OA
(ton)
EQUIPMENT INSTALLATION (SK SCOPE) ‐ 5470 4738.7 86.6% 86.6%
‐ ‐ feed water & deaerator 3 ‐ ‐
‐ ‐ common equipment 3 ‐
EA0110 CUSTOMER Vessel (Vent Container) ‐ Group 7390 3 1.8 1.80 100% 0.03%
EA0111 CUSTOMER Expansion Tank ‐ Group 7390 (T‐1040) 3 3.5 3.50 100% 0.06%
EA0112 CUSTOMER Fill and Drain Tank ‐ Group 7390 (T‐1050) 7 7.0 7.00 100% 0.13%
EA0116 CUSTOMER Hot Water Tank ‐ Group 4390 3 10.0 10.00 100% 0.18%
EA0127 CUSTOMER Blow Down Tank ‐ Group 7395 7 1.1 1.10 100% 0.02%
EA0133 CUSTOMER Feed water Tank with Deaerator ‐ Group 7395 7 8.1 7.70 95% 0.14%
EA0080/81 CUSTOMER Thermal Oil Heater 3 40.0 24.80 62% 0.45%
EA0119 CUSTOMER refractory for thermal oil heater 3 72.7 26.90 37.0% 0.49%
EA0106 CUSTOMER Safety Cooling Tank ‐ Group 7390 7 4.0 4.00 100% 0.07%
WESP G.7400 6%

000610 7410 WESP installation 2 153.0 153.00 100.0% 2.80%

Cooling Water Unit G.7500 6%

000612 7580 cooling water unit 4 20.0

Explosion Protection System & Spark Detection G.7600/7700 6%

000615 7601 explosion protection system ‐ 3.5 0.42 12% 0.01%

000616 7730 spark detection & extinguishing system ‐ 1.8

000617 7750 anti‐clogging device for cyclone ‐ 1.4

Additional Equipment (optional) G.8110 6%

000619 8110/8130/830x standard lab equipment ‐ 4.6

Page 234 of 234

You might also like