Completed
Average Completed Planned Completion Date Completion date
Total Quantity Spot %
No Activity Unit
Quantity (Previous) Productivity
weekly Quantity Finishing (Spot ( Average Status
Complete
Remarks
Productivity (Till Today) Date Productivity) productivity)
1 Excavation m3 4,274,875 3,643,714 6,620 8,932 3,647,334 14-Apr-2024 4-Jul-2024 10-Jun-2024 in progress 85.32%
2 Blasting m3 350,000 261,001 3,000 3,000 264,001 14-Mar-2024 29-Apr-2024 29-Apr-2024 in progress 75.43%
3 Soil improvement m2 148,561 92,413 410 135 92,809 22-Apr-2024 14-Aug-2024 18-May-2025 in progress 62.47%
5 Concrete (RC) m3 1,027,823 145,198 2,427 948 147,625 1-Oct-2025 29-Mar-2025 16-Oct-2026 in progress 14.36%
6 Rebar Ton 181,626 27,779 226 190 28,005 7-Sep-2025 9-Feb-2026 20-Jun-2026 in progress 15.42%
7 Surface Preparation (Walls) Sqm 159,802 608 0 0 608 28-Jul-2025 in progress 0.38% Work Front 1,123 m2
8 Waterproofing (Walls) Sqm 159,802 228 0 0 228 28-Jul-2025 in progress 0.14% Work Front 1,503 m2
10 Crashers m3 1,499,980 409,400 600 900 410,000 23-Jan-2025 22-Mar-2029 26-Jul-2027 in progress 27.33%
11 Disposal Material m3 2,844,269 2,375,830 11,400 14,883 2,387,230 14-Apr-2024 11-May-2024 1-May-2024 in progress 83.93%