RUALMADINA - Main Package (Infrastructure Work)

Daily Site Tracking Report


October 31, 2023
ON SITE PLANT TOTAL MANPOWER & EQUIPMENT
DAY SHIFT NIGHT SHIFT DAY SHIFT NIGHT SHIFT Moderate
JVC - Satff JVC - Labor WEATHER: Sunny Cloudy Rainy Windy Dusty QTY
Rain
IN DI IN DI IN DI IN DI No. CATEGORY DAY NIGHT
TOTAL
Project Director 1 Civil Team Temp: 40°C X WORK IDLE WORK IDLE
Deputy Project Director 1 Concrete Supervisor PROJECT MILESTONES 1 Excavator 98 79 19
Project Manager 1 Carpenter 171 19 PROJECT START DATE 30-May-22 2 Grader 1 1
Construction Manager 2 Electrician 10 5 PROJECT FINISH DATE 26-Nov-25 3 Loader 37 10 27
QA/QC Manager 1 Rigger PROJECT TOTAL DURATION 1277 days 4 Dozer 3 3
Senoir Qa/Qc Engineer 1 Mason 43 68 TOTAL ACTUAL DURATION DAY 520 5 Dump Truck 497 97 400
Project Control Manager 1 Pipe Fitter REMAINING DAYS 757 6 Low Bed / Truck
Safety Manager 1 Scaffolder 61 4 7 Welding Machine
SUBCONTRACTORS DAILY PROGRESS STATUS
Logistic Manager 1 Steel Fixer 300 95 8 Crane 19 17 2
Coordinator Manager 1 Steel-Fabricator MANPOWER EQUIPMENT 9 Compactor 6 6
Cost Control Manager 1 Plumber 25 COMPANY NAME Indirect Direct Sub-Total 10 Water tanker 4 2 2
Total Day Night
Estimate MEP Manager 1 Store Day Night Day Night Day Night 11 Concrete Transit Mixer
Contract Manager 1 Labour 102 11 12 Concrete Boom Pump
MENARD 10 13 23 23 15
Commercial Manager 1 Surveyor helper 7 13 Telehander 2 2
Interface Manager 1 Helper 14 Forklift 1 1
JEDDAH FOUNDATION 9 2 22 16 31 18 49 27 26
HR Manager 1 Timekeeper Team 15 Truck 7 5 2
Technical Manager 2 Driver 83 410 16 Manlift 3 3
AMMICO 31 2 63 94 2 96 41
Cost Control Engineer 1 Safety Helper 17 Oil Tanker 1 1
Lead Technical Engineer 1 Skilled Workers 3 18 JCB 2 2
RGF 1 4 5 5 2
Site Manager 1 Welder 9 3 19 Light Tower 27 13 14
Senior Planning Engineer 2 Tireman 20 Diesel Tanker 2 2
GEC 7 24 2 31 2 33 13 2
Planning Engineer 1 Operators 127 52 21 Shanur 1 1
Mechanical Engineer 4 Bricklayer 22 Bobcat/Boom Truck 5 5
UEG 4 4 4 4 8 38 38
Architect/QS Engineer 1 Scada Technician 23 Generator 27 20 7
Material Engineer 1 Painter 136 66 24 Air Compressor 8 5 3
Total 62 8 126 18 188 26 214
Structural Engineer 2 202 25 Cable Drum Trailer
Logistic Engineer 1 26 Cable Pulling Winch
Procurement Manager 1 Total 751 273 478
Safety Engineer 1
Safety Supervisor 1
Procurement Engineer 2
Mechanical Engineer 1
Admin 21
Critical Issue Remarks
Civil Engineer 8 Baseline Diff Planned Actual
Technical Engineer 5 1 Stockpile 1 Excavator 56 42 98
QC Engineer (Civil) 4 2 IFC 2 Grader 1 1
Electrical Engineer 3 3 Loader 33 4 37
Geo Tech Engineer 1 4 Dozer -15 18 3
QA/QC Status (WIR & MIR)
Project Engineer 1 5 Dump Truck 484 13 497
Coordination Engineer 1 Under 6 Low Bed / Truck -1 1
No. Type Rejected
Contract Engineer 2 Review 7 Welding Machine
Quantity Surveyor 7 1 WIR (Work Inspection Request) 47 135 8 Crane -23 42 19
Site Engineer 6 2 MIR (Material Inspection Request) 5 10 9 Compactor -125 131 6
Draftsman 12 10 Water Tanker -51 55 4
Chief Surveyor 1 11 Concrete Transit Mixer -63 63
QA/QC Status (SOR)
Lead Surveyor 1 12 Concrete Boom Pump -42 42
Surveyor 7 SOR 13 Auger/Telehander 2 2
Document Control Manager 1 14 Forklift 1 1
No. Trade Issued Pending Closed
Document Controller 2 15 Truck 7 7
Accountant 1 1 QA/QC 40 8 32 16 Manlift 3 3
Store Keeper 4 2 SAFETY 133 45 88 17 Oil Tanker 1 1
Camp Boss 1 Total 173 53 120 18 JCB 2 2
Safety Officer 12 19 Light Tower 27 27
Foreman 65 20 Diesel Tanker 2 2
NCR (Non Conformity Report)
Security 16 21 Shanur 1 1
Office boy 3 NCR 22 Bobcat/Boom Truck 5 5
Translator 1 23 Generator 27 27
No. Trade Issued Pending Closed
Procurement Officer 4 24 Air Compressor 8 8
Sr. Mechanical Engineer 1 QA/QC (TSC) 100 31 69 25 Cable Drum Trailer -1 1
1
Database Supervisor 2 QA/QC (JVC) 41 19 22 26 Cable Pulling Winch -1 1
Data Entry 2 2 SAFETY 53 17 36 Total 338 413 751
Electrical Technician 2 Total 194 67 127
Government Relation Assistant 4 Grand Total Of Equipment:
HR & Relation Manager Assistant 1
SI (Site Instruction)
Total
Plan Of Plan Equipment = 413
HR & Public Relation Manager 1 Total
Actual Of Actual Equipment = 953
IT Technician & Logistic Officer 2
No. Trade Issued Open Closed
Safety Assistant 4
Safety Helper 7 1 QA/QC 1 1
Labor Camp Officer 1 Total 1 1 Trade Open Responded by JVC
Law Specialist 1 No Material delivered Qty Unit
Logistic Officer 1
ISOR (Quality)
Mechanical Technician 2
Network Technician & Logistic Officer 1
No. Trade Issued Pending Closed
Public Relation Officer 1
Quality Technician 1 1 QA/QC 1 1
Secretary 1 Total 1 1
Security Officer 1
Foreman Crusher 12
TOTAL 278 941 667

SHIFT TOTAL DAY SHIFT = 1407 NIGHT SHIFT = 693

DIRECT TOTAL 1,752

INDIRECT TOTAL 348

Grand JVC Total 2,100

1 of 4
DAILY PROGRESS HIGHLIGHTS
HIGHLIGHTED WORKS FOR TODAY MANPOWER / EQUIPMENT AREA OF CONCERN

No. Zone TRADE LOCATION Today Quantity Unit Yesterday Com Today Com Manpower Equipment

A. EXCAVATION:
Zone 01 Excavation Sta. 0+400 Sta. 0+500 2,330 m3 175,472.35 177,802.35 13 13
Zone 02 Excavation Sta. 0+500 Sta. 0+900 m3 392,068.36 392,068.36
Zone 03 Excavation Sta. 0+970 Sta. 1+280 300 m3 358,041.92 358,341.92 6 6
Zone 04 Excavation Sta. 1+280 Sta. 1+700 1,350 m3 441,745.11 443,095.11 17 17
Zone 05 Excavation Sta. 1+700 Sta. 2+200 1,450 m3 271,944.38 273,394.38 22 22
Zone 06 Excavation Sta. 2+200 Sta. 2+450 1,760 m3 573,866.46 575,626.46 22 22
Zone 07 Excavation Sta. 0+340 Sta. 0+320 m3 9,578.23 9,578.23
Zone 08 Excavation Sta. 0+050 Sta. 0+460 3,670 m3 204,844.31 208,514.31 41 41
Zone 09 Excavation Sta. 0+020 Sta. 0+180 3,250 m3 374,038.07 377,288.07 39 39
Zone 10 Excavation Sta. 0+000 Sta. 0+376 m3 142,348.24 142,348.24
Zone 11 Excavation Sta. 0+320 Sta. 0+400 m3 105,655.98 105,655.98
D9-1 Excavation Sta. 0+100 Sta. 0+180 m3 30,076.15 30,076.15
D9-2 Excavation Sta. 0+000 Sta. 0+000 m3 19,184.00 19,184.00
TOTAL 14,110 m3 3,098,863.56 3,112,973.56

B. SOIL IMPROVEMENT:
a). CMC
Zone 1 Soil Improvement (total = 1558), Remaining = 529 pts 1,029 1,029
Zone 2 Soil Improvement (total = 5141), Remaining = 2640 32 pts 2,469 2,501
Zone 3 Soil Improvement (total = 2283), Remaining = 656 pts 1,627 1,627
Zone 4 Soil Improvement (total = 3736), Remaining = -283 pts 4,019 4,019
Zone 10 Soil Improvement (total = 2309), Remaining = 73 pts 2,236 2,236
Zone 11 Soil Improvement (total = 2570), Remaining = 325 pts 2245 2,245
Zone 6A Soil Improvement (total = 1524), Remaining = 863 pts 661 661
Zone 6B Soil Improvement (total = 1237), Remaining = 480 pts 757 757
TOTAL 32 15,043 15,075

b). STRUCTURAL BACKFILL


Zone 2 Backfilling (rock material). m3 720 720
Zone 3 Backfilling of granular material (1+093 to 1+153). m3 1,000 1,000
Zone 4 Backfilling of granular material (1+650 to 1+750). m3 4,575 4,575
Zone 8 Backfilling layer around lift station (3000mm dia.) m3 160 160
Zone 11 Backfilling (sta. 0+115-0+140) m3 450 450
Backfilling of granular material (0+240-0+330). m3 1,800 1,800
Backfilling (0+154-0+240). m3 3,310 3,310
Backfilling (0+074-0+090, 0+320-0+400). m3 9,500 9,500
Zone 6B Backfilling. m3 190 190
TOTAL - 21,705 21,705

c). ZLT
Zone 1 ZLT no 5 5
Zone 2 ZLT no 9 9
Zone 3 ZLT no 8 8
Zone 4 ZLT no 24 24
Zone 9 ZLT no 1 1
Zone 10 ZLT no 1 1
Zone 11 ZLT no 3 3
TOTAL 46 46

C. CONCRETE:
Zone 01 Concrete Sta. 0+000 Sta. 0+500 - m3
Zone 02 Concrete Sta. 0+500 Sta. 0+994 1,280 m3 5,965.00 7,245.00
Zone 03 Concrete Sta. 0+994 Sta. 1+268 264 m3 15,104.00 15,368.00
Zone 04 Concrete Sta. 1+268 Sta. 1+753 - m3 16,318.00 16,318.00
Zone 05 Concrete Sta. 1+753 Sta. 2+157 - m3
Zone 06 Concrete Sta. 2+157 Sta. 2+826.33 - m3 4,218.00 4,218.00
Zone 07 Concrete Sta. 0+040 Sta. 0+389.63 - m3
Zone 08 Concrete Sta. 0+015.13 Sta. 0+553 - m3
Zone 09 Concrete Sta. 0+000 Sta. 0+461-1 - m3
Zone 10 Concrete Sta. 0+000 Sta. 0+432 - m3 9,578.00 9,578.00
Zone 11 Concrete Sta. 0+020 Sta. 0+434.07 - m3 10,558.00 10,558.00
D9-1 Concrete Sta. Sta. - m3
D9-2 Concrete Sta. Sta. - m3
TOTAL 1,544 61,741.00 63,285.00

D. REBARS:
Zone 01 Concrete Sta. 0+000 Sta. 0+500 - ton
Zone 02 Concrete Sta. 0+500 Sta. 0+994 256 ton 1,168.00 1,424.00
Zone 03 Concrete Sta. 0+994 Sta. 1+268 53 ton 3,217.00 3,270.00
Zone 04 Concrete Sta. 1+268 Sta. 1+753 - ton 3,388.00 3,388.00
Zone 05 Concrete Sta. 1+753 Sta. 2+157 - ton - -
Zone 06 Concrete Sta. 2+157 Sta. 2+826.33 26 ton 864.00 890.00
Zone 07 Concrete Sta. 0+040 Sta. 0+389.63 - ton
Zone 08 Concrete Sta. 0+015.13 Sta. 0+553 - ton
Zone 09 Concrete Sta. 0+000 Sta. 0+461-1 - ton
Zone 10 Concrete Sta. 0+000 Sta. 0+432 - ton 2,091.00 2,091.00
Zone 11 Concrete Sta. 0+020 Sta. 0+434.07 - ton 2,098.00 2,098.00
D9-1 Concrete Sta. Sta. - ton
D9-2 Concrete Sta. Sta. - ton
TOTAL 335 12,826.00 13,161.00

E. SHORING PILES:
a). Shoring
Zone 2 Shoring (total = 194), Remaining = 12 nos 182 182
Zone 6B Shoring (total = 452), Remaining = 91 nos 361 361
Zone 10 Shoring (total = 124), Remaining = 14 nos 110 110

Zone 8 Drilling, shoring & concreting of Piles (total = 166), Remaining =


3 nos 169 172
KAAR (Shoring) -6
TOTAL 3 822 825

2 of 4
HIGHLIGHTED WORKS FOR TODAY MANPOWER / EQUIPMENT AREA OF CONCERN

No. Zone TRADE LOCATION Today Quantity Unit Yesterday Com Today Com Manpower Equipment

b). Anchor For Shoring


Zone 2 Anchor (total = 320), Remaining = 51 13 nos 256 269
Zone 6B Anchor (total = 149), Remaining = 89 nos 60 60

c). Waller Beam (LM):


Zone 2 Waller Beam (total = 264), Remaining = 0 m 264 264
Zone 6B Waller Beam (total = 450), Remaining = 400 m 50 50

d). Capping Beam (LM):


Zone 6B Capping Beam (total = 387), Remaining = 159 m 228 228
Zone 10 Capping Beam (total = 106), Remaining = 13 m 93 93

F. DISPOSAL:
Zone 2 Disposal of excavated material. m3 77,780 77,780
Zone 6 A Disposal of excavated material. m3 268,584 268,584
Zone 6 B Disposal of excavated material. m3 151,920 151,920
Zone 11 Disposal of excavated material. m3 7,040 7,040
S4 Disposal of excavated material. m3 111,180 111,180
D9 Disposal of excavated material. 6,360 m3 869,660 876,020
S2 Disposal of excavated material. 12,040 m3 1,176,360 1,188,400
S3 Disposal of excavated material. 10,760 m3 245,280 256,040
29,160 2,907,804 2,936,964

G. DEWATERING:
Zone 1 ongoing
Zone 2 ongoing
Zone 3 ongoing
Zone 4 ongoing
Zone 5 ongoing
Zone 6 ongoing
Zone 10 ongoing
Zone 11 ongoing

H. RELOCATION:
WET WORKS:
Zone 6B Excavation for storm line, 1500mm dia. m 830 830
Excavation of existing sewer line, 300mm dia. m3 100 100

Zone 10 Excavation for sewer line, 1400mm dia. m3 38,330 38,330


Installation of sewer line, 1400mm dia. m 204 204

D9 Excavation for sewer line, 200mm dia. m3 320 320

Al-Sohman District Excavation for sewer line (800mm dia.), by linear meter. m 888 888
Excavation for sewer line (800mm dia.), by volume m3 30,600 30,600
Backfilling for sewer line, 800mm dia. m3 18,000 18,000
Installation of GRP pipes, 800mm dia. m 822 822
Installation of storm line, 1100mm dia. m 111 111

Abo Zar Sewer line (800mm dia.) lm 28 28


Storm line (800mm dia.) lm 84 84
Excavation for storm line, 1200mm dia. m3 518 518
Installation of storm line, 1200mm dia. lm 220 220
Installation of storm line, 1100mm dia. lm 300 300
Excavation for storm line, 1500mm dia. m3 270 270

Niaba Gen.
Excavation for sewer line, 800mm dia. m3 750 750
(zone 7 south)

Ali Bin Abi Talb HDPE pipes 500mm dia. m 4,200 4,200

S8 & D9 Potable water line 900mm dia. m 1,906 1,906

I. CRUSHER WORKS:
Zone 2 Crasher m3 12,417 12,417
Zone 5 Crasher 900 m3 115,500 116,400
Zone 6 Crasher m3 27,103 27,103
Zone 8 Crasher 300 m3 103,473 103,773
Zone 9 Crasher m3 200 200
Zone 11 Crasher 300 m3 17,765 18,065
S2 Crasher 300 m3 5,700 6,000
S4 Crasher 300 m3 3,000 3,300
2,100 285,158 287,258

J. BLASTING WORKS:
Zone 4 Blasting m3 3,200 3,200
Zone 5 Blasting m3 35,600 35,600
Zone 6 Blasting m3 1,300 1,300
Zone 8 Blasting m3 14,800 14,800
- 54,900 54,900

TOTAL

3 of 4
HIGHLIGHTED WORKS FOR TODAY MANPOWER / EQUIPMENT AREA OF CONCERN

No. Zone TRADE LOCATION Today Quantity Unit Yesterday Com Today Com Manpower Equipment

PLANNED WORKS FOR FOLLOWING DAY


No. Zone TRADE LOCATION Quantity Unit Yesterday Com Today Com

A. EXCAVATION:
1 Zone 01 excavation sta. 0+00 sta 0+500 m3 189,718.86 189,718.86
2 Zone 02 excavation sta. 0+500 sta 0+994 m3 612,051.12 612,051.12
3 Zone 03 excavation sta. 1+000 sta 1+060 m3 340,798.06 340,798.06
4 Zone 04 excavation sta. 1+320 sta 1+410 m3 456,376.55 456,376.55
5 Zone 05 excavation sta. 1+753 sta 2+157 m3 762,587.66 762,587.66
6 Zone 06 excavation sta. 2+157 sta 1+850 m3 302,773.22 302,773.22
7 Zone 07 excavation sta. 0+040 sta 0+389 m3 94,922.69 94,922.69
8 Zone 08 excavation sta. 0+015.13 sta 0+533 m3 641,739.08 641,739.08
9 Zone 09 excavation sta. 0+000 sta 0+461-1 m3 659,674.42 659,674.42
10 Zone 10 excavation sta. 0+000 sta 0+300 m3 175,743.29 175,743.29
11 Zone 11 excavation sta. 0+014 sta 0+434 m3 112,485.12 112,485.12
- 4,348,870.05 4,348,870.05
B. DEWATERING:
Zone 02 ongoing
Zone 03 ongoing
Zone 06 ongoing
Zone 08 ongoing
Zone 09 ongoing
Zone 10 ongoing

PROGRESS PHOTOS

31-Oct-23 31-Oct-23 31-Oct-23 31-Oct-23


31-Oct-23 31-Oct-23 31-Oct-23 31-Oct-23
Zone 3 - Removal Of Formworks Al Sohman - Installation Of Storm Zone 10 - Binding Of Roof Zone 2 - Binding Of Wall
Zone 6A - Excavation Zone 8 - Excavation Zone 1 - CMC Zone 6B - Cleaning
(153-173) Line, 1100mm dia. Reinforcement (142-122) Reinforcement (530-550)
WSP - TSC Comments

Prepared By : Eminor B. Roman/Planning Engineer - JVC


Reviewed By : Name/Position - WSP
Issued By : Name/Position - Parsons

4 of 4
SUBCONTRACTORS MANPOWER & EQUIPMENT
Date: 31-Oct-2023
DAY SHIFT NIGHT SHIFT Total DAY SHIFT NIGHT SHIFT Total
MANPOWER EQUIPMENT
IN DI IN DI WORK IDLE IN DI IN DI WORK IDLE
MENARD: MENARD:
Project Manager 1 1 CMC Rig 1 1
QA/QC Engr. 1 1 CPT Rig 0 0
Site Engr. 0 0 Wheel Loader 2 2
Site Manager 1 1 Manlift 2 2
Surveyor 2 2 Landini Pump 2 2
Foreman 2 2 Water Tank 2 2
Safety Officer 2 2 Tower Light 2 2
Wheel Loader operator 2 2 ZLT Equipment 0 0
CMC Rig operator 2 2 Mobile Crane 0 0
Man Lift Operator 1 1 Welding Machine 1 1
Concrete Boom Pump Optr. 0 0 SPT Rig 0 0
Welder 1 1 GPS Survey Eqpt 2 2
Helper 4 4 Generator 1 1
Mechanic 1 1 Transit Mixer 0
Technician 1 1 Concrete Boom Pump 0
Rigger 1 1 Sub-Total 0 15 0 0 15 0
Logistic 1 1
Sub-Total 10 13 0 0 23 0 JEDDAH FOUNDATION:
Piles Drilling Machine 0
JEDDAH FOUNDATION: Crawler Crane 50T 0
Project Manager 1 1 Small Rig Machine 0
Technical Engineer 1 1 Wheel Loader 0
QC Engineer 0 Boom Trucks 0
Procurement Officer 0 Welding Machine 1 1
Mechanical Engineer 0 Generator 6 6 12
Surveyor 1 1 Forklift 0
Safety Officer 1 1 Diesel Pumps 7 7 14
Store Keeper 1 1 2 Mobile Crane 0
Accountant 1 1 Submersable Pump 12 12 24
General Foreman 3 1 4 Excavator 0
Site Engineer 0 Bus 1 1 2
Mechanic 1 1 Sub-Total 0 27 0 26 53 0
Driver 1 1 2
Technician 6 5 11 AMMICO:
Rigger 0 Piling Rig BG-28, C600 3 3
Rig Operator 0 Piling Rig BG-36, HR-35 & SR-250 0 0
Crane Operator 0 Piling Rig HR-35 & Sany 2 2
Loader Operator 1 1 Crawler Crane (50t, 80t) 2 2
Welder 1 1 Mobile Crane 1 1
Boom Truck Driver 0 Klemn Machine 2 2
Labor / Helper 10 9 19 Excavator 3 3
Electrician 2 1 3 Welding Machine 4 4
Anchor Machine Operator 0 Generator 4 4
Forklift Operator 0 CPT Machine 1 1
Sub-Total 9 22 2 16 49 0 Bus & Service Truck 2 2
Flatbed Trailer 1 1
AMMICO: Tower Light 14 14
Business Development Manager 1 1 Transit Mixer
Project Manager 1 1 Concrete Boom Pump
QC Manager 1 1 Air Compressor 1 1
QA/QC Engr. 3 3 Steel Bending & Cutting Machine 1 1
Const Manager 2 2 Sub-Total 0 41 0 0 41 0
Site Engr. 1 1
HSE Manager 0 0 GEC:
HSE Supervisor 1 1 Drilling Rig 1 2 3
HSE Officer 2 1 3 Crawler Crane 2 2
Mech. Engr. 0 Welding Plant 1 1
Site Supervisor 7 1 8 Electrical Generator 2 2
Surveyor 3 3 Dewatering Pump 2 2
CPT Tech 1 1 Water Storage Tank 1 1
Admin 1 1 Tower Light 3 3
Fabricator Supervisor 1 1 Excavator 1 1
Foreman 1 1 Sub-Total 0 13 0 2 15 0
Chargehand 5 3 8
Rig operator 9 9 RGF:
Crane Operator 4 4 Drilling Machine 1 1
Concrete Boom Pump Optr. 0 0 Water Tank 1 1
Mechanic 5 5 Sub-Total 0 2 0 0 2 0
Electrician 2 2
Welder 4 4 UEG:
Rigger 2 2 Generator 6 6 12
Gen Labor 26 26 Diesel Tank 3 3 6
Light Driver 2 2 Sedimentation Tank 4 4 8
Heavy Driver 1 1 Submersible Pump 25 25 50
Store Keeper 1 1 Sub-Total 0 38 0 38 76 0
Store Helper/Cleaner 1 1 Total 0 136 0 66 202 0
Klem Operator 3 3
Sub-Total 31 63 2 0 96 0 Manpower Equipment
SUMMARY- Direct
Day Night Total Day Night Total
GEC: MENARD 13 0 13 15 0 15
Project Manager 1 1 JEDDAH FOUNDATION 22 16 38 27 26 53
Site Manager 1 1 AMMICO 63 0 63 41 0 41
Site Engineer 0 RGF 4 0 4 2 0 2
Site Supervisor 2 2 GEC 24 2 26 13 2 15
QA/QC 1 1 UEG 0 0 0 38 38 76
Safety Officer 1 1 Total 126 18 144 136 66 202
Leadman 2 2
Mechanic 2 2
Electrician 1 1
Rig Operator 2 2 4
Crane Operator 2 2
Rigger 2 2
Surveyor 1 1
Welder 2 2
Excavator Operator 1 1
Helper 10 10
Sub-Total 7 24 0 2 33 0

RGF:
Crew 4 4
Geologist 1 1
Sub-Total 1 4 0 0 5 0

UEG:
Project Engineer 1 1 2
Technician 3 3 6
Sub-Total 4 0 4 0 8 0
Total 62 126 8 18 214 0