You are on page 1of 3

Project Title Goa International Airport, Mopa, Goa

Name of the EPC Contractor M/s Megawide Constructions DMCC


Project Start Date 3-Mar-18
Project Finish Date (As per
Contract) 2-Sep-20

DPR Of Earth works for Goa Airport Project

R Balarama reddy (RBR ) Contractors ( From ch 3000 to 3750 )

Total Scope
Sl. No Item Description UoM for the Scope for Scope Achieved for the day
project the available
Contractor before tree Night
as per LOA cutting Day Shift Shift Total

1 C&G -Runway sqm 1,125,000 315,000 175,000 - - -


2 Excavation Cum 12,540,106 2,600,000 570,000 1,904 1,272 3,176

3 Disposal of -
unsuitable soil Cum
4 Filling Cum 7,543,161 2,000,000 568,000 - - -

Manpower status

RBR Pioneer
Sl. No. Manpower
Day Night Day Night
1
Project Manager 1 - 1

2
Engineers 6 - 3
3 Supervisors 4 3 5
4 Foreman 5 2 1
5 Surveyors 2 - 1.00
6
Operators 11 4 23 2
7
Drivers 9 7 15
8
Eletrician - -
9 Mechanic -
10 Welder - -
11 labour 13 6 7
TOTAL 51 22 56 2
rport Project Dt 22.04.18

Pioneer Global Projects Pvt Ltd( From Ch 2000 to 2200 and Ch 2600 to
rom ch 3000 to 3750 )
3000 )
Cumulative
achieved by
Achieved for the day
Cumulative Scope for
Scope both the
Cumulative
the available contractors
Achieved Till Contractor before tree Achieved Till
Date Night Date during the day
as per LOA cutting Day Shift Shift Total

42,750 380,000 - - - - - -
116,304 2,600,000 260,000 1,296 1,296 28,652 4,472.00

87,344 880 880 3,736 880.00

WIP 2,000,000 - - - - - -

Equipment status

RBR Pioneer
Equipment
Sl. No. Day Night Day Night
1 4 2 4
Excavators

2 Dozers with 4 5 2
ripper
3 Dozers 2 2 2
4 Tippers 9 7 13
5 Grader 1 1

6 Vibromax 1 1
Roller
7 Water 6 2
tanker
8 Tower 1 1
lights
Cumulative
achieved by
both the
contractors till
date

42,750
144,956

91,080

WIP

You might also like