TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Date : May 22th, 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night Day Overtim Night Overtim Night


Day Shift Overtime Day Shift Start End Total Hours Remarks
Shift Shift e Shift e Shift

Direct Labor * 144 69 759

Skilled Worker (Source : Jakarta) 110 69 759

Rebarman 25 22 242

Mason 20 14 154

Carpenter 25 16 176

Fitter 12 5 55

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) 34

34

Indirect * 65 49 509

Construction Manager 1 1 11 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11 Blasting at purnama Pit, all worker evacuate from

Surveyor 2 2 22 TMF area

Field Engineer/Project Engineer 1 1 11

HR Staff 3 2 22 EQUIPMENT ON SITE QTY

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 Roughter Crane 50 Ton 1

Civil QC Engineer 2 1 11 Roughter Crane 90 Ton 1

Civil Superintendent 1 1 11 Boomtruck 15 Ton 1

QC Staff 2 1 11 Concrete Pump 1

Mechanical 6 1 8 Mixer Truck 01 1

SMP Foreman 2 2 22 Mixer Truck 02 1

SMP Supervisor 1 1 11 Mixer Truck 03 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 04 1

Scaffolding Inspector 1 Telehandler 1

Scaffolder 7 7 77 Tractor Head 6X6 1

HSE Supervisor 1 1 11 LV 01 (Pajero) 1

Safety Officer 3 2 22 LV 02 Double Cabin 1

Logistic and Warehouse 2 1 11 LV 03 Double Cabin 1

Rigger 3 2 22 Generator 45 kVA 4

Driver 3 2 19 Generator 165 kVA 1

Electrician 2 2 22 Compressor 2

Operator Crane 2 2 22 Total Equipment 20

Operator Telehandler 1 1 11

Operator Manlift 1

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 3 3 24

Operator Mixer Truck 4 4 32


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Date : May 22th, 2023

DAILY PROGRESS REPORT

PERI UP Supervisor 2 1 8

TOTAL 209 118 1268

2. MAJOR HIGHLIGHT

Monday, 22 May 2023 Tuesday, 23 May 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Assembly foundation rebar GL -06-05-04 Continue Assembly foundation rebar GL -06-05-04

Start Install formwork GL 13-11 Continue joint survey GL 1,2,3,4,5

Repair formwork for nect pouring Repair formwork for nect pouring

Instal bottom rebar GL 4-3-2 Continue start bottom rebar GL 4-3-2

Assembly PERI UP panel Continue assembly PERI UP panel

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE filtration feed Ø 400 reach 12 joint 12 Continue 'Joint pipe HDPE filtration feed Ø 400

Joint pipe HDPE filtration feed Ø 160 reach 15 joint 15 Continue 'Joint pipe HDPE filtration feed Ø 160

E. Logistic : E. Logistic :

Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Manpower complete 7

G. Others G. Others

Online & offline Training Online & offline Training

Produce office furniture & site facilities Continue produce office furniture & site facilities

Concern :

Cast In plate, Embeded plate, anchor for pedestal not yet arrive at TMF

PERI UP material not yet complete

Concreting water stop material for Filtration building not enough (25 meter more)

Local hire need to joint

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 22th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Coating formwork before install Install formwork GL 11-10-9 Axis A

Install formwork GL 11 Axis B Chiping pedestal P6

Install stopper GL 8 Axis C & Grouting GL 14 Axis B Install formwork GL 11-10-9-8 Axis C
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 22th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Install bowplank GL 7 Cleaning rebar from scrap

Install rebar wall GL 7 & rebar bottom GL 2-3 GL 13-11 ready for concreting
Piping

Joint HDPE pipe diameter 63 Joint HDPE pipe diameter 63

Laydown pipe through sewer Joint HDPE pipe diameter 63


Prepared by : Approved by :

Project Control