You are on page 1of 8

TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Wednesday, 12 July 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks

Direct Labor * 141 99 1221

Skilled Worker (Source : Jakarta) 110 84 1089

Rebarman 25 23 253

Mason 20 17 187

Carpenter 25 24 264

Fitter 12 8 88

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) : Helper 31 12 132

Unskilled Worker (Source : Local) : Watchmen 3 3 33

Indirect * 68 53 559

Construction Manager 1 Total Hours :

Site Manager 1 1 11 Note :

Planner 1 1 11 Manhour use for Recyn Project :

Surveyor 3 2 22 From 8th May to 12th July :

Field Engineer/Project Engineer 1 1 11 10989 Hr (Indirect & direct)

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

GA & Supporting 1 1 11

Administration 1 1 11

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 1 11 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 1 11 Mixer Truck 03 1

Scaffolder 7 7 77 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 3 33 Tractor Head 6X6 1

Logistic and Warehouse 2 2 22 LV 01 (Pajero) 1

Rigger 3 3 33 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 11 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Wednesday, 12 July 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2

TOTAL 206 152 1648

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirect)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100.00% 0.51% 0.13% 21.97% 9.92% 12.05% 90.08% 9.92%

Mechanical Work Percent 100.00% 0.07% 1.31% 1.31% 100.00%

Piping Work Percent 100.00% 0.17% 0.77% 0.50% 0.27% 99.50% 0.50%

Structural Percent 100.00% 0.02% 1.89% 0.14% 1.75% 99.86% 0.14%

Plate Works Percent 100.00% 0.31% 0.31% 100.00%

Erected Tanks Percent 100.00% 100.00%

Electrical Percent 100.00% 0.02% 0.20% 0.20% 100.00%

Testing and Punch list Percent 100.00% 100.00%

Pre-commisioning Percent 100.00% 100.00%

Total Percent 0.79% 0.13% 26.46% 10.56% 15.90% 10.56%

2. MAJOR HIGHLIGHT

Wednesday, 12 July 2023 Thursday, 13 July 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Pouring concrete Switch Room footing m3 37 Complete pouring concrete Switch Room footing m3 37

Install EMB footing rebar & Plan pouring 15 July 2023 m3 172 Continue Install EMB footing rebar & Plan pouring 15 July 2023 m3 172

Install PERI UP 4m footing GL 1-5 Continue install PERI UP 4m footing GL 1-5

Install rebar Transformer Bay Continue install rebar Transformer Bay

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 66 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 37 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10

Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10

Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10

Joint pipe HDPE Field Piping Ø 355 PN16 Joint 24 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

Hold PERI UP installation GL 15-11 Hold PERI UP installation GL 15-11

Install PERI UP footing GL 1-5 Continue install PERI UP footing GL 1-5

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -15.24%

Base on updated Schedule R

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting TBM at recyn


CIVIL

Switch Room concreting preparation Cleaning footing switchroom

Continue install rebar top EMB Install stopper PF4 Switchroom

Covering Switchroom Pedestal Install concrete stopper on EMB


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Cleaning Switchroom Cleaning EMB

Cleaning EMB North Side Install bowplank EMB

Install dan perkuatan sapot formwork footing switchroom pf4 Install Formwork on EMB south side

Pengerjaan Civil TM pertama


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Slump 16 Concreting switch room footing

Concreting switch room footing Concrit footing switchroom

Continue pouring Switch Room footing Pengerjaan Civil

Complete pouring, continue finishing. Switch Room footing Concreting Trench line
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Arranging Tarpaulin Finishing Switch Room footing surface

Finishing Switch Room footing surface Covering Swithc Room after concreting
Piping

Mobilize Elbow 45° Briefing South Dump

Fit Up HDPE Pipe at Sky Way Fit Up HDPE Pipe at South Dump
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Prepare joint dn 400 Fit Up HDPE Pipe at South Dump

Fit Up HDPE Pipe at South Dump Joint pipe to stub end 450-1

Join 24 Dia 355 PN16 PE100 Fit Up HDPE Pipe at South Dump

Joint pipe to stub end 450-2 Fit Up HDPE Pipe at South Dump
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Wednesday, 12 July 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Fit Up HDPE Pipe at South Dump Install y piece

Joint stub end to elbow 45 deg Fit Up flange HDPE Pipe at South Dump

Fit Up flange HDPE Pipe at South Dump Fit Up flange HDPE Pipe at South Dump
Prepared by : Approved by :

Project Control

You might also like