Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 23 253
Mason 20 17 187
Carpenter 25 24 264
Fitter 12 8 88
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 53 559
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1 1 11
Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.51% 0.13% 21.97% 9.92% 12.05% 90.08% 9.92%
Piping Work Percent 100.00% 0.17% 0.77% 0.50% 0.27% 99.50% 0.50%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Pouring concrete Switch Room footing m3 37 Complete pouring concrete Switch Room footing m3 37
Install EMB footing rebar & Plan pouring 15 July 2023 m3 172 Continue Install EMB footing rebar & Plan pouring 15 July 2023 m3 172
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 66 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 37 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 160 PN10
Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Pipe & Fitting Ø 90 PN10
Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Pipe & Fitting Ø 63 PN10
Joint pipe HDPE Field Piping Ø 355 PN16 Joint 24 Continue Joint pipe HDPE Field Pipe & Fitting Ø 355 PN16
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
DAILY PHOTOGRAPH
PHOTOGRAPH
Install dan perkuatan sapot formwork footing switchroom pf4 Install Formwork on EMB south side
DAILY PHOTOGRAPH
PHOTOGRAPH
Complete pouring, continue finishing. Switch Room footing Concreting Trench line
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Finishing Switch Room footing surface Covering Swithc Room after concreting
Piping
Fit Up HDPE Pipe at Sky Way Fit Up HDPE Pipe at South Dump
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Fit Up HDPE Pipe at South Dump Joint pipe to stub end 450-1
Join 24 Dia 355 PN16 PE100 Fit Up HDPE Pipe at South Dump
Joint pipe to stub end 450-2 Fit Up HDPE Pipe at South Dump
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Joint stub end to elbow 45 deg Fit Up flange HDPE Pipe at South Dump
Fit Up flange HDPE Pipe at South Dump Fit Up flange HDPE Pipe at South Dump
Prepared by : Approved by :
Project Control