TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources
Rev. 0
Monday, 26 June 2023

DAILY PROGRESS REPORT

0. DAILY PROGRESS & MANPOWER Construction Phase

MANPOWER WORK HOURS RAINFALL RECORD

PLAN ACTUAL ACTUAL ACTUAL


DISCIPLINE/ACTIVITY

Night
Day Shift Overtime Night Shift Day Shift Overtime Day Shift Overtime Night Shift Start End Total Hours Remarks
Shift

Direct Labor * 144 82 902

Skilled Worker (Source : Jakarta) 110 82 902

Rebarman 25 23 253

Mason 20 18 198

Carpenter 25 24 264

Fitter 12 5 55

Boilermaker 8 4 44

Pipe Fitter 6 2 22

HDPE Piping 4 4 44 OTHER CONDITION

Welder Steel (SMAW+GTAW) 8 2 22


Total
Start End Remarks
Hours
Painter 2

Unskilled Worker (Source : Local) 34

34

Indirect * 66 53 568

Construction Manager 1 1 11 Total Hours :

Site Manager 1 1 15 Note :

Planner 1 1 11 Manhour use for Recyn Project :

Surveyor 3 2 22 From 8th May to 25th June : 8580 hr

Field Engineer/Project Engineer 1 1 11 (Indirect & direct)

HR Staff/Administration 2 1 11

HR/Administration 1 1 11

Civil Foreman 2 2 22

Civil Supervisor 1 1 11 EQUIPMENT ON SITE QTY

Civil QC Engineer 2 1 11

Civil Superintendent 1 1 11 Roughter Crane 50 Ton 1

QC Staff 2 2 22 Roughter Crane 90 Ton 1

Mechanical 6 1 8 Boomtruck 15 Ton 1

SMP Foreman 2 2 22 Concrete Pump 1

SMP Supervisor 1 1 11 Mixer Truck 01 1

SMP QC Engineer (WI qualification) 2 1 11 Mixer Truck 02 1

Scaffolding Inspector 1 1 11 Mixer Truck 03 1

Scaffolder 7 7 77 Mixer Truck 04 1

HSE Supervisor 1 Telehandler 1

Safety Officer 3 3 33 Tractor Head 6X6 1

Logistic and Warehouse 2 2 26 LV 01 (Pajero) 1

Rigger 3 3 33 LV 02 Double Cabin 1

Assisstant Deputy Construction Manager 2 1 11 LV 03 Double Cabin 1

Assistant CM 1 1 15 Generator 45 kVA 4

Electrician 2 2 22 Generator 165 kVA 1

Operator Crane 50T 1 1 11 Compressor 2

Operator Crane 90T 1 1 11 Stamper 4

Operator Telehandler 1 1 11 Light Tower 2

Operator Manlift 1 Total Equipment 26

Operator Boom Truck 1 1 11

Operator Trailer 1 1 11

Operator Concrete Pump 1 1 8

Driver Concrete Pump 1 1 8


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
Rev. 0
Monday, 26 June 2023

DAILY PROGRESS REPORT

Assistant Ops Concrete Pump 1 1 8

Operator Mixer Truck 4 4 32

PERI UP Supervisor 2 1 8

TOTAL 210 135 1470

1. CONSTRUCTION KEY QUANTITIES (*Plan Based on Work Completion Schedule - WCS)

DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual

Overhead (Indirects)* Percent 100% Monthly Update

On Site Management and Control* Percent 100% Monthly Update

Construction

Civil Work Percent 100% 0.54% 0.03% 15.4% 9.1% 6.4% 91% 9.08%

Mechanical Work Percent 100% 100%

Piping Work Percent 100% 0.02% 0.01% 0.41% 0.31% 0.10% 99.69% 0.31%

Structural Steel Percent 100% - 100%

2. MAJOR HIGHLIGHT

Monday, 26 June 2023 Tuesday, 27 June 2023

ACTIVITY UNIT QTY ACTIVITY UNIT QTY

A. Civil A. Civil

Continue PERI UP to complete 60 unit GL 15-11 unit 60 Complete PERI UP to complete 60 unit GL 15-11

Finishing EMB Shear Key formwork Complete Finishing EMB Shear Key formwork

Install LC formwork conduit pipe line 3rd layer LC conduit pipe line 3rd layer

Install stirr up on starter bar column Continue Install stirr up on starter bar column

Install wall horizontal bar Continue Install wall horizontal bar

Start marking Switch Room Continue marking Switch Room

Backfill SF-01 Continue Backfill SF-01

B. Structure : B. Structure :

C. Mechanical : C. Mechanical :

D. Piping : D. Piping :

Mobilize HDPE piping material Continue Mobilize HDPE piping material

Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 30 Continue Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10

Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 23 Continue Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25

Joint pipe HDPE Field Piping Ø 160 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 160 PN10

Joint pipe HDPE Field Piping Ø 90 PN10 Joint 68 Continue Joint pipe HDPE Field Piping Ø 90 PN10

Joint pipe HDPE Field Piping Ø 63 PN10 Joint 62 Continue Joint pipe HDPE Field Piping Ø 63 PN10

Joint pipe HDPE Field Piping Ø 355 PN16 Joint 9 Continue Joint pipe HDPE Field Piping Ø 355 PN16

E. Logistic : E. Logistic :

Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area

F. Scaffold : F. Scaffold :

PERI UP installation GL 15-11 Continue PERI UP installation GL 15-11

Rearrange PERI UP wall 2 & 7 with only 2 lift Rearrange PERI UP wall 2 & 7 with only 2 lift

G. Others G. Others

Online & offline Training Online & offline Training

Concern :

Overall progress minus -9.14%

Base on updated Schedule R

Prepared by : Checked By : Acknowledged By :

Project Control Site Manager


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Thursday, 22 June 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Install LC formwork GL 1-2-3-4-5-6-7 Axis A Install LC formwork conduit switchroom

Continue PERI wall panel assembly Install horizontal wall rebar Axis A, GL 8-12

Install horizontal wall rebar Wall 1, Axis A LC conduit


Piping
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Thursday, 22 June 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint no 68 HDPE pipe dia 90 PN10 Joint no 66 HDPE pipe dia 160 PN10

Joint no 67 HDPE pipe dia 160 PN10 Continue mobilize pipe spool HDPE

Joint no 68 HDPE pipe dia 160 PN10 Joint no 28 HDPE pipe dia 400 PN10

Continue fit up & mobilize HDPE pipe Joint no 29 HDPE pipe dia 400 PN10
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Thursday, 22 June 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Joint no 30 HDPE pipe dia 400 PN10 Assembly HDPE pipe


Prepared by : Approved by :

Project Control