GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Check electrical tools for grounding Continue unloading material

Joint inspection with PT.AR Install rebar pedestal P6 & Grounding on footing

Completion formwork installation GL 15 - 13 Concrete vibrator inspection


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 11th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Install wall rebar GL 10 - 11 Cleaning footing from scrap material

Install rebar GL 7 - 8 axis A Install rebar GL 7 - 8 axis C


Site Establishment

Continue office & workshop roofing Waterline installation

Continue office & workshop roofing Waterline installation