TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources

Date : May 27th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

Continue install rebar pedestal wall GL 5 Cleaning foundation GL 13 - 08

Joint survey foundation GL 13 - 08 Continue fabricate PERI wall panel

Install pedestal Column P6


Piping
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 27th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Continue transfer HDPE pipe to TMF Continue Fit up HDPE Field Pipe
Prepared by : Approved by :