Professional Documents
Culture Documents
Day Shift Overtime Night Shift Day Shift Overtime Night Shift Day Shift Overtime Night Shift Start End Total Hours Remarks
Rebarman 25 23 253
Mason 20 18 198
Carpenter 25 23 253
Fitter 12 8 88
Boilermaker 8 4 44
Pipe Fitter 6 2 22
Indirect * 68 55 578
Planner 1 1 11
Surveyor 3 1 11
HR Staff/Administration 2 1 11
HR/Administration 1 1 11
GA & Supporting 1 1 11
Administration 1 1 11
Civil Foreman 2 2 22
Civil QC Engineer 2 1 11
Operator Trailer 1 1 11
PERI UP Supervisor 2
DAILY CUMULATIVE
BALANCE %
ACTIVITY UNIT QTY Variance REMARKS
ACT. COMPLETE
Plan Actual Plan Actual
Construction
Civil Work Percent 100.00% 0.16% 0.02% 25.03% 11.21% 13.82% 88.79% 11.21%
Piping Work Percent 100.00% 0.04% 0.007% 1.45% 0.53% 0.92% 99.47% 0.53%
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Ongoing Swith Room anchor installation Continue Swith Room anchor installation
Ongoing chipping & finishing EMB footing Continue chipping & finishing EMB footing
Dismantle & cutting precasted SF column rebar Continue dismantle & cutting precasted SF column rebar
Precast Fire Water Filtration Water Servie slab rebar Continue Precast Fire Water Filtration Water Servie slab rebar
B. Structure : B. Structure :
Pre-assembly Tailing transfer service & Pipe Rack Continue Pre-assembly Tailing transfer service & Pipe Rack
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE Field Pipeng & Fitting Ø OSU 400 PN10 Joint 79 Continue Joint pipe HDPE Field Pipe & Fitting Ø OSU 400 PN10
Joint pipe HDPE Field Pipeng & Fitting Ø PSL 400 PN25 Joint 42 Continue Joint pipe HDPE Field Pipe & Fitting Ø PSL 400 PN25
Joint pipe HDPE Field Piping Ø WPR 160 PN10 Joint 73 Continue Joint pipe HDPE Field Piping Ø WPR 160 PN10
Joint pipe HDPE Field Piping Ø PSL 160 PN10 Joint 10 Continue Joint pipe HDPE Field Piping Ø PSL 160 PN10
Joint pipe HDPE Field Piping Ø WFR 90 PN10 Joint 75 Continue Joint pipe HDPE Field Piping Ø WFR 90 PN10
Joint pipe HDPE Field Piping Ø WPO 63 PN10 Joint 70 Continue Joint pipe HDPE Field Piping Ø WPO 63 PN10
Joint pipe HDPE Field Piping Ø PSL 355 PN10 Joint 32 Continue Joint pipe HDPE Field Piping Ø PSL 355 PN10
E. Logistic : E. Logistic :
Unloading Rebar, tools & equipment to TMF area Continue Unloading Rebar, tools & equipment to TMF area
F. Scaffold : F. Scaffold :
G. Others G. Others
Concern :
25/07/2023
PHOTOGRAPH
GENERAL ACTIVITIES
25/07/2023
PHOTOGRAPH
Cutting & chipping Transfomer Bay foting Memilah sampah kayu sama bendrat paku
Install TTS Ladder Dispose mud & cleaning on TMF pipe rack footing
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
25/07/2023
PHOTOGRAPH
Dispose mud & cleaning on TMF pipe rack footing Compacting backfilled TMF
Prepare join pipe 355 pn 16 Joint 32 HDPE pipe dia PSL 355
25/07/2023
PHOTOGRAPH
Project Control