Rebarman 25 22 242
Mason 20 14 154
Carpenter 25 16 176
Fitter 12 5 55
Boilermaker 8 4 44
Pipe Fitter 6 2 22
34
Indirect * 65 49 509
Civil Foreman 2 2 22
Electrician 2 2 22 Compressor 2
Operator Telehandler 1 1 11
Operator Manlift 1
Operator Trailer 1 1 11
PERI UP Supervisor 2 1 8
2. MAJOR HIGHLIGHT
A. Civil A. Civil
Start bottom rebar GL 4,3 & Column P3A Continue start bottom rebar GL 4,3 & Column P3A
B. Structure : B. Structure :
C. Mechanical : C. Mechanical :
D. Piping : D. Piping :
Joint pipe HDPE filtration feed reach 8 joint 8 Continue Joint pipe HDPE filtration feed
E. Logistic : E. Logistic :
Unloading tools & equipment to TMF area Continue Unloading tools & equipment to TMF area
F. Scaffold : F. Scaffold :
Manpower complete 7
G. Others G. Others
Produce office furniture & site facilities Continue produce office furniture & site facilities
Concern :
Concreting water stop material for Filtration building not enough (25 meter more)
DAILY PHOTOGRAPH
PHOTOGRAPH
GENERAL ACTIVITIES
Install bowplank SF-02 Continue install rebar bottom GL 4 & 3 & Column P3A GL9
Install column axis C GL 9 & Chipping joint construction Install scaffolding GL 13-11
TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources
DAILY PHOTOGRAPH
PHOTOGRAPH
Welding joint no.6 HDPE pipe Welding joint no.7 HDPE pipe
Welding joint no.7 HDPE pipe Continue fit up HDPE pipe Filtration Feed
Prepared by : Approved by :
Project Control